V. SCOPE OF WORK/PROJECT SPECIFICATIONS

The successful contractor shall provide all labor, equipment, tools, and materials necessary to install new irrigation, shrubs, trees, and mulch, located at Lisendra Heights Landscape & Lighting District, 5300 Block of West Whitendale Ave, Visalia. The work will consist of:

 Removal of existing shrubs, drip irrigation, and grading of landscape area.  Removal of existing turf within parkway area and grading for installation of new landscape. Delete parkway turf removal and landscaping.  Installation of new irrigation per landscape plan. (see attached landscape plans). Delete parkway irrigation and relandscaping.
 Installation of new groundcover, shrubs, and trees per landscape plan. (see attached landscape plans for size and quantity). Delete parkway irrigation and relandscaping.  Installation of five (5) inches recycled landscape mulch of per landscape plan. ( see attached landscape plans). Delete parkway irrigation and relandscaping.  Installation of new irrigation controller, flow sensor, and master valve per landscape plans. (see attached landscape plans). Delete parkway irrigation and relandscaping.  Existing water service, backflow device, mainline, and electrical service to protected in place and reused.
 Contractor is responsible for having the area marked for utilities (811 Before You Dig) before the project begins.
 Any damage to existing irrigation, concrete sidewalks or block wall shall be repaired at the expense of the contractor.
 Contractor shall be responsible for clean-up and disposal of all waste materials.  Work to be performed for the Lisendra Heights Landscape and Lighting District Landscape Enhancement Project shall be compensated at the contract unit cost and shall include mobilization, and furnishing all labor, materials, tools, equipment and incidentals, and for doing all work of completing the installation of new irrigation components and plant material , in accordance with this bid request and as directed by the City’s Project Manager, and per the City Standard Specifications to provide fully completed improvements. No additional payment will be made therefor.