SHIRK STREET

CAPACITY

ENHANCEMENT

PROJECT
City of Visalia, Engineering & Building Department
March 17, 2025

INTRODUCTIONS
 NV5 Resident Engineer, Kolton Walker, P .E.,
Resident Engineer
 Outreach Specialist, Georgiena Vivian, President,
VRPA Technologies
 City of Visalia Project Manager – Diego Corvera, P .E., Senior Civil Engineer, City of Visalia

PROJECT

BACKGROUND
 Project Approval:
 Council Approved the Project in 2024
 Project Funding:
 Contract Amount: $16,444,225.00
 State & Locally Funded
 Project Purpose and Need:
 To Provide Increased Sanitary Sewer Capacity
for Recent & Future Development Along Shirk
St.
 To add for additional traffic capacity by
widening Shirk St.

PROJECT BACKGROUND
(Continued)
 Project Overview
 Phase 1 – March through May 2025
• Sewer Installation: Doe Ave. to Riggin Ave .
• Work Hours: 7 am – 3:30 pm Monday-Friday
• Complete Sewer Mainline - Sewer Line in Place & Trench Backfilled. Street Widening. Concrete Improvements.

Electrical Improvements.
 Phase 2 – May 2025 through September 2025
• Sewer Installation: School Ave. to south of Goshen Ave. • Work Hours: 7 am – 3:30 pm Monday-Friday
• Complete Sewer Mainline - Sewer Line in Place & Trench Backfilled. Storm Drain Installation. Street Widening.

Concrete Improvements. Electrical Improvements.
 Phase 3 – September 2025 through January 2026
• Sewer Installation: Goshen Ave. to Doe Ave.
• Work Hours: 7 am – 3:30 pm Monday-Friday
• Complete Sewer Mainline - Sewer Line in Place & Trench Backfilled. Street Widening. Concrete Improvements.

Electrical Improvements.

Phase 3
Sewer Installations
Goshen Ave
to Doe Ave

CURRENT PROJECT
STATUS
 Project Team Kick-Off Meeting
 Friday, January 28, 2025
 Prior and Current Field Activities
 Notice of Award Issued: 11/15/2024
 Notice to Proceed Issued 3/3/2025
 Earliest Start Work Date: Early to Mid March 2025
 Contract Reflects 225 Working Days
 Right-of-way Acquisition Process
 Major Right of way Acquisitions have been Completed
 Traffic Control Plan Development
 Access to be Maintained to Businesses & Residences
 Traffic Control & Street Reconstruction Work to be
Accomplished in Three (3) Phases:
 Phase 1: Just South of Doe Ave. to North of Riggin Ave.  Phase 2: Hillsdale Ave. to Just South of Goshen Ave.
 Phase 3: Goshen Ave. to Doe Ave.
 Lead Construction Contractor - Avison

ROAD CLOSURE /

TRAFFIC DETOUR
Riggin Ave @ Shirk St Closed
03/17 through 03/21
Phase 1a: Riggin Ave @ Shirk St

ROAD CLOSURE /

TRAFFIC DETOUR

ROAD CLOSURE /

TRAFFIC DETOUR

ROAD CLOSURE /

TRAFFIC DETOUR
Phase 2a

ROAD CLOSURE /

TRAFFIC DETOUR
Phase 2b

ROAD CLOSURE /

TRAFFIC DETOUR
Phase 2c

ROAD CLOSURE /

TRAFFIC DETOUR
Final portion of Phase 2

ROAD CLOSURE /

TRAFFIC DETOUR

AREAS OF CONCERN
 Limited Access
 Driveways for 527 & 535 Shirk St.
• Only One (1) Entrance/Exit (Driveway)
• Homes will be Directly Affected - Sewer Line on that Side of the Street  Stonegate Estates
• Only One (1) Entrance/Exit (Approach)
• Sewer Line Excavation will be Across the Street Resulting in Limited Access  Shepherds Ranch - South of Pershing Ave.
• Has Another Temporary Driveway Entrance Just to the South • Job Site will be Directly Affected by Sewer Line Excavation on that Side of the Street

AREAS OF CONCERN
 Limited Access (Continued)
 Commercial Property on the West Side of Shirk & Pershing • Road Dead Ends as You Drive West
• Intersection is the Only Way In & Out
• Many Businesses with Access Cutoff for a Day or so During Construction
 Near Pershing looking north to Goshen Ave
• Sewer Line Excavation - West Side of Shirk St.
• Area Where Jack & Bore Steel Casing will Occur
• Businesses & Residence will have Very Limited Access

AREAS OF CONCERN
 Limited Access (Continued)
 Shirk St. looking south towards Goshen Ave.
• Install Two (2) Sewer Lines & a Storm Drain Line
• Intersection will be Closed at Various Stages
 Shirk Entrance to the Tuscany Villas Apartments
• Access will be Provided During Construction
• Apartments have Another Entrance from Doe Ave.
 Activity Centers
 Access will be Maintained to Activity Centers (Churches, Schools, Etc., Including:
• Hurley & Denton Elementary Schools, Ridgeview Middle School, Mid-County Community School, and St. Paul’s Church & School
 Detours - Will be Noticed & Posted in Advance
 Street Closures – Will be Noticed & Posted in Advance

COMMITMENTS TO YOU
 Maintain Continuous & Safe Access to
Properties
 Maintain Safe Pedestrian Routes
 Notice & Sign Road Closures
 Notice, Sign & Maintain Detour Routes
 Be Good Neighbors
 Deliver the Project Expeditiously

CHECKING OUR

PROGRESS/OUTREACH PLAN
 Purpose
 Ensure Meaningful & Sustained Participation by the
Public
 Provide Regular Updates to Give & Receive
Information
 Outreach Strategies
 Public Meetings
 Text Message Alert Notification System
 Direct Mailing
 24-Hour Hotline
 Press Releases and Updates
 Webpage & Social Media Information
 Social Media

 Mailer Notice to be Distributed by March 10, 2025
 Public Meeting to be Held on March 19, 2025, at
Ridgeview Middle School between 5:30 & 6:30 PM
 Phase 1: March 2025 - May 2025
 Traffic Control Setup and Mobilization
 All Potholing is Done at the Beginning of the Project  Sewer System Installation
 Electrical Work
 Roadway Widening & Reconstruction
 Phase 2: May 2025 - September 2025
 Traffic Control Setup and Mobilization
 Utility Relocation
 Sewer System and Storm Drain Installation
 Electrical Work
 Roadway Widening & Reconstruction
 Phase 3 – September 2025 – January 2026
 Traffic Control Setup and Mobilization
 Utility Relocation
 Sewer System Installation
 Electrical Work
 Roadway Widening & Reconstruction

NEXT STEPS

CONTACT US
 Primary - NV5 Resident Engineer, Kolton Walker, P .E.  Phone: (559) 355-9506
 Email: [email protected]
 Outreach Specialist, Georgiena Vivian
 Phone: (559) 259-9257
 Email: [email protected]
 City of Visalia Project Manager – Diego Corvera, P .E.  Phone: (559) 713-4209
 Email: [email protected]

 Text alerts: 888-477-3146 text
“Shirk” to receive project updates
 Visit the City web page at
www.visalia.city/shirk for project
updates
 Contractor 24-hour phone line -
Joseph Kochergen 559-718-1546

HOW TO STAY UP TO
DATE