TULARE AVE. STREET
REHABILITATION
MAY 19 TH , 2025 | 7:00PM
INTRODUCTIONS
CITY ENGINEER, CITY OF VISALIA
Chris Crawford
ASSOCIATE ENGINEER, CITY OF VISALIA
Jonathan Frausto
RESIDENT ENGINEER, 4CREEKS
Ian Williams, P.E.
CONSTRUCTION MANAGER, 4CREEKS
Dustin Smith
01 02
03 04
PROJECT APPROVAL
• City Council approved in 2025.
PROJECT FUNDING
• Construction contract: $5,202,396.00
GOAL & COMMUNITY BENEFIT
• The project aims to support the City’s ongoing efforts to rehabilitate streets identified in the pavement
management plan, while also upgrading traffic signals,
ADA ramps, and adding protected bike lanes. The goal is to create safer, more accessible streets for all users.
PROJECT BACKGROUND
PROJECT OVERVIEW
PHASE 1
WHERE: East side of Mooney Blvd. to Watson St.
WHEN: June through August 2025
• Work Hours: Monday–Friday, 7:00AM – 3:30PM
• Complete Road Rehabilitation, ADA Ramp and Traffic Signal Upgrades • Expected side street road closures at Giddings, Sowell, and Watson • Anticipated 2–3-day road closures for northbound and southbound traffic
PROJECT BACKGROUND
CONTINUED
PROJECT OVERVIEW
DISCLAIMER:
Dates shown are approximate
and are subject to change.
TULARE AVE. STREET REHABILITATION
TULARE AVE. WILL HAVE ONE LANE OPEN IN EACH DIRECTION DURING CONSTRUCTION.
PHASE 2
WHERE: Demaree St. to West of Mooney Blvd.
WHEN: September through November 2025
• Work Hours: Monday–Friday, 7:00AM – 3:30 PM
• Complete Road Rehabilitation, ADA Ramp and Traffic Signal Upgrades • Expected side street road closures at Mountain and Woodland • Anticipated 2–3-day road closures for northbound and southbound traffic
PROJECT BACKGROUND
CONTINUED DISCLAIMER:
Dates shown are approximate
and are subject to change.
PROJECT OVERVIEW
TULARE AVE. STREET REHABILITATION
TULARE AVE. WILL HAVE ONE LANE OPEN IN EACH DIRECTION DURING CONSTRUCTION.
PHASE 3
WHERE: East of Watson to Cotta Street
WHEN: December 2025 to January 2026
• Work Hours: Monday–Friday, 7:00 AM – 3:30PM
• Complete Road Rehabilitation, ADA Ramp and Traffic Signal Upgrades • No road closures are expected per contract documents
PROJECT BACKGROUND
CONTINUED DISCLAIMER:
Dates shown are approximate
and are subject to change.
PROJECT OVERVIEW
TULARE AVE. STREET REHABILITATION
TULARE AVE. WILL HAVE ONE LANE OPEN IN EACH DIRECTION DURING CONSTRUCTION.
PROJECT TIMELINE
PROJECT ADVERTISED FOR BID & BID OPENING
• February 27 – April 8, 2025
CONSTRUCTION CONTRACT AWARD
• April 22, 2025
CONSTRUCTION START
• Expected June 2025
CONSTRUCTION COMPLETION
• Anticipated Early 2026
NOTICE OF COMPLETION
• February 2026
01 02
03 04
05 DISCLAIMER:
Dates shown are approximate
and are subject to change.
PARTIAL ROAD
CLOSURE/TRAFFIC DETOUR
PARTIAL ROAD CLOSURE
TRAFFIC DETOUR
PHASE 1:
SOUTH SIDE OF
GIDDINGS & NOBLE –
SOFT CLOSURE
NORTH SIDE OF
TULARE & GIDDINGS
– HARD CLOSURE
Tulare
Noble
Tulare
PARTIAL ROAD
CLOSURE/TRAFFIC DETOUR
PARTIAL ROAD CLOSURE
TRAFFIC DETOUR
PHASE 1:
SOUTH SIDE OF
TULARE & GIDDINGS
– HARD CLOSURE
NORTH SIDE OF
WALNUT AND
GIDDINGS – SOFT
CLOSURE
Tulare
Tulare
Walnut
AREAS OF CONCERN
Traffic Congestion Near Local School Districts
• City staff are committed to maintaining traffic flow
in both eastbound and westbound directions
Partial Road Closures Impacting Traffic
• Partial road closures are expected to last 2–3 days
Areas of Limited Access for Residents
• Soft closures will be implemented to allow local
traffic through
LIMITED ACCESS
OUR COMMITMENTS
TO YOU
Maintain Continuous and Safe Access to Properties
Maintain Safe Pedestrian Routes
Provide Advance Notice and Road Closure Signs
Post, Sign, and Maintain Detour Routes
Be Good Neighbors
Complete the Project Expeditiously
01 02
03 04
05 06
STAY UP
TO DATE
01 TEXT ALERT SIGN-UP
Text TULARE to +1 (520)
506-5092 to receive project
updates
02 PROJECT QUESTIONS
Call Jonathan Frausto
+1 (559) 713-4369
TULARE AVE. STREET REHABILITATION