Cities Index.
Project Traffic Impacts and Outreach Presentation

Visalia City Council
May 19, 2025

Document
Project Traffic Impacts and Outreach Presentation
Meeting
May 19, 2025
Body
Visalia City Council
Original file
15.3 MB
Text extracted from the city's file for reading and search. Open the original on visalia.legistar1.com. That file is the official record.

RIGGIN AVENUE

WIDENING &

IMPROVEMENTS
(KELSEY TO SHIRK)
City of Visalia, Engineering & Building Department
May 19, 2025

INTRODUCTIONS
 NV5 Resident Engineer, Kolton Walker, P .E.,
Resident Engineer
 Outreach Specialist, Georgiena Vivian, President,
VRPA Technologies
 City of Visalia Project Manager – Diego Corvera, P .E., Senior Civil Engineer, City of Visalia

PROJECT

BACKGROUND
 Project Approval:
 Construction Award: April 2025
 Project Funding:
 Contract Amount: $8,098,281.00
 Federal, State & Locally Funded
 Project Purpose and Need:
 Provide Increased Traffic Capacity for
Recent & Future Development Along
Riggin Ave.

PROJECT IMPROVEMENTS
 Roadway Widening
 Riggin Avenue to be widened to a 4-lane road from Kelsey Street to Shirk Road
• Including median curb and protected turn lanes
• SCE Pole relocation
• Full Depth Recycling – Cement (FDR-C) method of
roadway construction.
 Class IV Bike Lane
 A Class IV protected bike lane will be constructed running parallel with Riggin Avenue from Kelsey Street to Shirk Road.  Underground Utility Improvements
 Improvements to sanitary sewer, storm drain, and water utilities

PROJECT IMPROVEMENTS
 Electrical Improvements
 Signalization of Riggin Avenue & Shirk Road
 A traffic signal will be constructed at the intersection of Riggin Avenue & Shirk Road.
 Streetlights
 Street lighting improvements along Riggin Avenue
 Concrete Improvements
 Improvements include curb & gutter, curb ramps, and
concrete median curbs with stamped median concrete.
 Landscaping Improvements
 Planting of 40+ trees in the median of Riggin Avenue

PROJECT OVERVIEW
 Tentative Construction Dates – June 2025 through
December 2025
• Roadway Construction: Riggin Ave from Kelsey
St. to Shirk St.
• Work Hours: 7 am – 3:30 pm Monday-Friday
• Riggin Avenue Planned to be open to traffic during
construction.

PROJECT PHASING
• Roadway construction to be completed in three (3) phases:
• Phase 1(Orange): West bound (north of existing Riggin Ave) widening & improvements
• Phase 2 (Blue): East bound (south of existing Riggin Ave) widening & improvements
• Phase 3 (Green): Existing Riggin Avenue roadway reconstruction

CURRENT PROJECT
STATUS
 Project Team Kick-Off Meeting
 Tentative Late May
 Prior and Current Field Activities
 Notice of Award Issued: 04/21/2025
 Notice to Proceed Issued TBD
 Earliest Start Work Date: Early to Mid June
2025
 Contract Reflects 120 Working Days
 Lead Construction Contractor – Agee
Construction

COMMITMENTS TO YOU
 Maintain Continuous & Safe Access to
Properties
 Maintain Safety Through Project Limits
 Communicate Project Updates with
Community
 Be Good Neighbors

CHECKING OUR

PROGRESS/OUTREACH PLAN
 Purpose
 Provide Regular Updates to Give & Receive
Information
 Outreach Strategies
 Text Message Alert Notification System
 Direct Mailing
 Press Releases and Updates
 Social Media

CONTACT US
 Primary - NV5 Resident Engineer, Kolton Walker, P .E.  Phone: (559) 355-9506
 Email: [email protected]
 Outreach Specialist, Georgiena Vivian
 Phone: (559) 259-9257
 Email: [email protected]
 City of Visalia Project Manager – Diego Corvera, P .E.  Phone: (559) 713-4209
 Email: [email protected]

 Text alerts: 1-877-309-3802 text
RIGGIN to receive project updates
 City of Visalia Social Media
Accounts
 Contact Construction Manager:

Kolton Walker: (559) 355-9506

HOW TO STAY UP TO
DATE

← All documents from this meeting