Qty Unit Price p/ Unit Total
Non-Supplemental Improvements - Transportation
1 Mobilization 1 LS $1,800.00 2,070.00$
2 Rough Grading 41615 SF $1.70 81,357.33$
3 12" AB 41615 SF $1.79 85,664.48$
4 7" AC 41615 SF $2.33 111,507.39$
5 Add 1" AB 41615 SF $0.83 39,721.52$
6 Demo Existing AC 25825 SF $0.48 14,255.40$
7 Demo Existing Curb & Gutter 259 LF $6.66 1,983.68$
8 Demo AC Berm/Dike 846 LF $5.59 5,438.51$
9 Signage & Striping 1 LS $18,024.00 20,727.60$
10 Median Curb 1864 LF $18.24 39,099.26$
11 Median Stamped Concrete 2774 SF $10.09 32,188.11$
12 Median Landscape 1 LS $56,300.00 64,745.00$
13 SWPPP 1 LS $7,407.56 8,518.69$
14 Storm Drain 16 LF $1,194.67 21,981.93$
15 Storm Drain Manhole 1 EA $6,658.11 7,656.83$
16 Traffic Signal Modifcation (Mid-Valley) 1 LS $237,887.00 273,570.05$ Subtotal 810,485.78$
17 Design & Construction Management 12% 97,258.29 $
Total 907,744.07$
18 Right of Way Dedication 1.6 Ac $871,200.00 1,393,920.00$ 2,301,664.07 $
Visalia Oaks Marketplace - Visalia Parkway Reimbursment EXHIBIT 1
*Price per acre reflects Citywide land value appraisal
report at time right of way was dedicated.
*
per TIF program guidelines.
Exhibit 1 - Reimbursement Summary
Visalia City Council
June 16, 2025
- Document
- Exhibit 1 - Reimbursement Summary
- Meeting
- June 16, 2025
- Body
- Visalia City Council
- Original file
- 28 KB
Text extracted from the city's file for reading and search. Open the original on visalia.legistar1.com. That file is the official record.