Fire Station 51 Project Update
Engineering & Building Department
Fire Department
August 4, 2025
1 VICINITY MAP
Acequia Avenue
Stevenson Street
Conyer Street
Mineral King Avenue

NEW FIRE STATION 51 LOCATION PLAN

NEW FIRE STATION 51 SITE PLAN
Conyer Street
Mineral King Avenue (south of Mineral King Avenue
Acequia Avenue (north of office building)
Stevenson Street

DRAFT FLOOR PLAN

DRAFT FLOOR PLAN (north side)

DRAFT FLOOR PLAN (central)

DRAFT FLOOR PLAN (south side)

FIRE STATION 51

FIRE STATION 52

FIRE STATION 53

FIRE STATION 54

FIRE STATION 55

FIRE STATION 56

Example fire station images

Example fire station images

EARLY CALIFORNIA

Example fire station images

Budget Summary: CP0415
Project Funding
Available CIP Funding
$4,400,000
Estimated Project Costs:

Estimated Construction Costs
$20,350,000
Architect/Engineer (actual cost)
$794,787
Construction Manager (actual cost)
$889,000
Surveying (1%)
$200,000
City Staff Time (2%)
$400,000
Construction Contingency (10%)
$2,000,000
Inspection/Testing (2%)
$400,000
Permits/Fees (2%)
$400,000
Total Estimated Project Costs
$25,433,787
Total Estimated Deficit
($21,033,787)

PRELIMINARY COST ESTIMATE

Site Plan Review August 2025
Complete PS&E July 2026
Bidding August 2026
Award Contract September 2026
Start Construction October 2026
End Construction September 2028
Move-in October 2028

TENTATIVE PROJECT SCHEDULE