Fire Station 51 Project Update
Engineering & Building Department
Fire Department
August 4, 2025
1 VICINITY MAP
Acequia Avenue
Stevenson Street
Conyer Street
Mineral King Avenue
NEW FIRE STATION 51 LOCATION PLAN
NEW FIRE STATION 51 SITE PLAN
Conyer Street
Mineral King Avenue (south of Mineral King Avenue
Acequia Avenue (north of office building)
Stevenson Street
DRAFT FLOOR PLAN
DRAFT FLOOR PLAN (north side)
DRAFT FLOOR PLAN (central)
DRAFT FLOOR PLAN (south side)
FIRE STATION 51
FIRE STATION 52
FIRE STATION 53
FIRE STATION 54
FIRE STATION 55
FIRE STATION 56
Example fire station images
Example fire station images
EARLY CALIFORNIA
Example fire station images
Budget Summary: CP0415
Project Funding
Available CIP Funding
$4,400,000
Estimated Project Costs:
Estimated Construction Costs
$20,350,000
Architect/Engineer (actual cost)
$794,787
Construction Manager (actual cost)
$889,000
Surveying (1%)
$200,000
City Staff Time (2%)
$400,000
Construction Contingency (10%)
$2,000,000
Inspection/Testing (2%)
$400,000
Permits/Fees (2%)
$400,000
Total Estimated Project Costs
$25,433,787
Total Estimated Deficit
($21,033,787)
PRELIMINARY COST ESTIMATE
Site Plan Review August 2025
Complete PS&E July 2026
Bidding August 2026
Award Contract September 2026
Start Construction October 2026
End Construction September 2028
Move-in October 2028
TENTATIVE PROJECT SCHEDULE
QUESTIONS?