City of Visalia
MR Bike Pedestrian Projects
City # Status Fed # Limits Current Allocation CMAQ TE ATP Amt Left for
SupplementalsSupplementals (MR) Remaining Capacity
Proposed
Reallocation
Updated Remaining
Capacity Designate funds to project(s):

Mill Creek Trail 3,700,000 $ 422,000$ - $ 141,000$ 3,137,000$ 2,754,330.08$ 382,670 $ (382,670)$ - $ 9919 Active Lovers Ln to Cain 780,000.00 $
0118 Complete 5044(103) Tipton to Burke 141,000 $ 169,996.93 $ 0121 Complete Burke to Goshen 686,153.63 $
8292 Complete 5044(073) Akers to Marcin 422,000 $ 330,917.80 $ 0187 Complete Mill Creek Bridge East of Shirk 395,000.00 $ 9843 Complete Garden Park to McAuliff 224,852.78 $
8267 Complete Garden Park to McAuliff (Rehab) 71,976.68 $ 9100/8133 Complete Marcin to Tommy 80,421.88 $
8203 Complete Mill Creek Trail 11,000.00 $
8295 Complete Murray to Road 152 4,010.38 $
Santa Fe Trail 7,370,057 $ 560,000$ - $ -$ 6,810,057$ 3,663,220.14$ 3,146,837$ (512,837)$ 2,634,000$ Santa Fe Bike Lanes Project 0480 Active Santa Fe Class IV Bike Lane from Tulare Ave. to Houston Ave. 400,000.00 $ 8118 Complete 5044(090) Houston to Riggin 560,000 $ 544,928.49 $ 8117 Complete Ave 272 to Tulare 2,718,291.65 $
St Johns River Trail 3,000,000 $ 1,181,000$ 245,000$ - $ 1,574,000$ 1,946,985.90$ (372,986)$ 372,986$ - $ 8131 Active 5044(105) Riggin to Dinuba 1,181,000 $ 353,970.00 $ 0119 Complete Riverway Dr 835,000.00 $
9716 Complete McAuliff to Rd 148 153,119.88 $
8261 Complete Riparian W of Dinuba (EEM) 74,937.00 $
8314 Complete Hughes Property Acquisition 42,819.58 $
8041 Complete 5044(061) Rd 148 to Cutler Park 245,000 $ 487,139.44 $ Packwood Creek Trail 5,746,764 $ 1,937,000$ 368,000$ - $ 3,441,764$ 3,438,249.20$ 3,515 $ -$ 3,515$ 0012 Complete 5044(104) Santa Fe to Crumal 1,137,000 $ 745,065.50 $ 9915 Complete 5044(040) Along Cameron Ave 616,917.11 $
9956 Complete 5044(075) Caldwell to Cameron 480,000 $ 725,546.44 $ 8285 Complete 5044(078) Cameron to Visalia Pkwy 118,000 $ 327,272.26 $ 8119 Complete 5044(074) Walnut Ave RR to Cedar 320,000 $ 255,379.30 $ 8120 Complete 5044(077) Crumal to Sue 250,000 $ 768,068.59 $ Modoc Ditch Trail 3,000,000 $ 818,000$ - $ -$ 2,182,000$ 2,052,683.17$ 129,317 $ 170,700$ 300,017$ Modoc Basin Trail (Design) 8228 Complete Gidding to Demaree 730,000 $ 573,548.21 $ 8229 Complete Court to St. Johns River 588,376.17 $
8128 Complete 5044(085) Dinuba to Giddings 88,000 $ 709,692.81 $ 8208 Complete Mooney to Riggin 160,775.58 $
8296 Complete Ferguson & Dinuba (EEM) 20,290.40 $
Goshen Trail 3,000,000 $ - $ -$ -$ 3,000,000$ 1,736,630.00$ 1,263,370$ 1,912,000$ 3,175,370$ Goshen Trail Replacement Project 8130 Active Giddings to Akers 1,736,630.00 $
Cameron Creek path 3,000,000 $ - $ - $ -$ 3,000,000$ - $ 3,000,000$ (3,000,000)$ - $ K Street Bike Path - $ -$ - $ -$ -$ -$ -$ K Road along SJ line 737,179 $ - $ - $ -$ 737,179$ - $ 737,179$ (737,179)$ - $ Visalia Class 1 Trails 836,000 $ 228,000$ - $ 1,000,000$ (392,000)$ 515,514.69$ (907,515)$ 1,677,000$ 769,485$ ESRP Basins - Trails 0189 Active Mill Creek Bridge on Greenway Trail 242,744.69 $ 298 Active Greenway Belt Trail 1,000,000 $ 140,670.00 $ 175 Complete Santa Fe Trail Crossing 228,000 $ 102,100.00 $ 8408 Complete Greenway Trail MasterPlan(St. Johns River) 30,000.00 $ Maintenance & Security 500,000$ 500,000$ New Maintenance Category 30,390,000$ 5,146,000$ 613,000$ 1,141,000$ 23,490,000$ 16,107,613.18$ 7,382,387 $ - $ 7,382,387$ TOTAL