Visalia Civic Center Phase III Scope of Work & Amenities Engineering and Building

City Hall Phase 3 Amenities
Administration Office Building
Café / Food Service & Patio Space
Employee Health Clinic
Fourth Floor Growth / Lease Space
Training Facility / Practice Range
2 Building and Engineering

3 Construction Cost Estimates
4 Building and Engineering

Overall Project Cost Estimates
5 Building and Engineering

Civic Center Funding
6 Building and Engineering
Assumptions:

Budget Surplus (26/27 & 27/28)
GF Assumptions:

Revenues Conservative
No Additional Capital
No Vacancies

Current General Fund Debt
7 Building and Engineering

Debt Payment Scenarios
8 Building and Engineering
Bonds/COP Interest Rate Factors:

Market Conditions
Inflation Expectations (expected to rise – higher interest rates) Maturity Timeframe (long term bonds – higher interest rate) Supply & Demand
Agency’s Financial Stability (credit risk)
Reserves
Management Policies
Financial Planning
Current Debt

Design Schedule
Execute A/E Agreement July 2026
Space Needs Assessment August 2026
Schematic Design Phase September 2026
Design Development Phase October 2026
Construction Documents Phase October 2027
9 Building and Engineering

Staff Recommendation
10 Building and Engineering
Staff is recommending that Council Approve the following:

Approve Option 1, which includes:

Fourth Floor Addition
PD training facility/range
Café/patio
Health Clinic
Approve sole source contract with Darden Architects for design of phase 3.

Appropriate $5,721,000 from the Civic Center Reserve Fund

Thank you
11