Attachment 4 - RPGS Commissioning Schedule & Vendor Contact Package (October 5–23, 2026)

Visalia City Council
July 20, 2026

Document
Attachment 4 - RPGS Commissioning Schedule & Vendor Contact Package (October 5–23, 2026)
Meeting
July 20, 2026
Body
Visalia City Council
Original file
127 KB
Text extracted from the city's file for reading and search. Open the original on visalia.legistar1.com. That file is the official record.

Day Date Activity Purpose Hours Unabated Hours SCR Status 1 Oct 5 Mobilization, kick-off, walkdown Commissioning step to verify system performance and readiness 8 0 SCR Offline 2 Oct 6 Electrical/mechanical verification Commissioning step to verify system performance and readiness 30 0 SCR Offline 3 Oct 7 Controls, I/O, calibration Commissioning step to verify system performance and readiness 30 0 SCR Offline 4 Oct 8 Aux systems + interlocks Commissioning step to verify system performance and readiness 30 0 SCR Offline 5 Oct 9 Switchgear + generator checks Commissioning step to verify system performance and readiness 30 0 SCR Offline 6 Oct 12 First fire + initial run Commissioning step to verify system performance and readiness 12 8 SCR Offline 7 Oct 13 Load ramp + alarms testing Commissioning step to verify system performance and readiness 36 4 SCR Offline 8 Oct 14 Blending tuning + stabilization Commissioning step to verify system performance and readiness 36 4 SCR Offline 9 Oct 15 Catalyst loading + prep Commissioning step to verify system performance and readiness 30 2 SCR Offline 10 Oct 16 SCR activation Commissioning step to verify system performance and readiness 30 0 SCR Online 11 Oct 19 SCR tuning Commissioning step to verify system performance and readiness 30 0 SCR Online 12 Oct 20 Final SCR tuning Commissioning step to verify system performance and readiness 30 0 SCR Online 13 Oct 21 Utility witness testing
requirements, Source test prep Commissioning step to verify system performance and readiness 30 0 SCR Online 14 Oct 22 Utility witness testing
requirements, Source testing Commissioning step to verify system performance and readiness 36 0 SCR Online 15 Oct 23 Final validation + demob Commissioning step to verify system performance and readiness 8 0 SCR Online Notes
Hours include some level of debugging / Trouble shooting Startup notification lead times required by each vendor / Approximately 8 Trades will be overlaying each other, View Vendor Presence Column Need to define the Utility witness testing requirements, including timing assumptions and expected duration Commissioning Contact list. Confirmation of availability and commitment for the full October 5–23 window Cummins Commissioning Team
Brad Warren -Technical Advisor
Integrated Gas and Microgrids
Cummins Sales and Service NA
Mobile 612-505-2576
Home 906-486-9037
Cummins Branch
David Watts
Sr. Service Supervisor
559-274-4405
[email protected]
Cummins Inc.
2755 S. Cherry Avenue
Fresno, California 93706
PEECO
Chris Lynam
Service Manager
Power Systems Specialist
Office: 484-840-0860 Ext. 11/ Fax: 484-840-0863
&
Anthony Laspata
Project Manager
Philadelphia Electrical Equipment Company, Inc.
14 Mount Pleasant Road | Aston, Pennsylvania 19014
Phone: 484-840-0860 ext.18 / Fax: 484-840-0863
peecoenergy.com | Offices: Aston, PA | Panama City, FL
Miratech

GREGORY SAGE
PROJECT MANAGER III | MIRATECHCORP.COM
O: 918 442 2432 | M: 918 861 8067
ACS/Preferred
Jeremy Pulice Engineering Manager
2727 E 21st Street Suite 400 Tulsa OK 74114, Danbury CT 06810 | www.PREFERRED-MFG.com
office: 203.743.6741 x1101 | cell: 918.805.5574
&
Dennis Garcia
31 35 South Street, Danbury CT 06810 | www.PREFERRED-MFG.com office: 203.743.6741 | cell: 4752895466 | [email protected] Cummins, PEECO, Miratech
Please note:

The commissioning schedule reflects a dynamic field execution plan. Activities may overlap, shift within the defined window, or be completed ahead of or behind the nominal daily allocation depending on system readiness, interdependencies, and real-time operational conditions. Vendor presence is defined by phase and may extend across adjacent days to support continuous commissioning activities.”
Cummins, Miratech, ACS/Preferred
Cummins, PEECO, Miratech, ACS/Preferred
Cummins, PEECO, Miratech, ACS/Preferred
Cummins, PEECO, Miratech, ACS/Preferred
Cummins, PEECO, Miratech, ACS/Preferred
Cummins, PEECO, Miratech, ACS/Preferred
Cummins, Miratech, ACS/Preferred
Miratech
Cummins, Miratech, ACS/Preferred
Cummins, Miratech, ACS/Preferred
Cummins, PEECO,
Vendor Presence
Cummins, PEECO, Miratech
Cummins, PEECO, Miratech
Cummins, PEECO, Miratech