ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: D3
Prepared by: Husam Hasenin, Principal Engineer Meeting Date: January 24, 2023 Approved by:

Greg Mayer, City Engineer
Amanda Lee, Acting City Manager Agenda Location: Discussion SUBJECT: GREEN BIKE LANES
RECOMMENDATION: Discuss implementation of green bike lanes in the City and provide direction to staff.

CORRELATION TO CITY COUNCIL GOALS: (1) Public Safety and (2) Traffic: Continue to improve flow of traffic for all forms of travel, reduce congestion, and improve our roads and sidewalks.

PRIOR ACTION: On November 15, 2022, adopted City Council Resolution No. 2022-162, awarding a construction contract to Eagle Paving Company, Inc. for the Street Rehabilitation Project 2022 (CIP No. 8225). Directed staff to paint eligible bike lanes in the project green if the cost is less than the ten percent contingency included in the budget or to come back with an estimate if it is higher, as well as to put an item on a future agenda to discuss painting bike lanes green city-wide. (Vote: 3-2, Ritter and Franklin opposed) On June 23, 2020, adopted City Council Resolution No. 2020-107, approving the Six-Year Capital Improvement Program and Fiscal Years 2020/21 and 2021/22 Capital Project Budget and authorizing appropriations for Fiscal Years 2020/21 and 2021/22 Capital Projects (Vote: 5-0).

STATEMENT ON THE SUBJECT: Green painted bike lanes are intended to highlight the presence of the bike lanes and gain motorists’ attention as they drive alongside them or across them. Staff had a cost estimate developed for the implementation of green bike lanes considering two distinct scenarios. The first scenario would implement green bike lanes along the entire length of all bike lanes in the City, including at intersection approaches. Intersection approaches are considered to be conflict areas where potentially large volumes of motor traffic traverse bike lanes and where through bicyclists must weave across right turning motor vehicles. The second scenario considers the installation of green bike lanes only at intersection approaches within conflict areas.

Within each scenario, implementation of green bike lanes was estimated using either green paint or thermoplastic. Green paint is applied in two coats. Thermoplastic is applied by heating plastic polymer material onto the pavement, which solidifies and sticks to the pavement after cooling. Green paint must be replaced more frequently due to fading over time. Thermoplastic is a long-lasting improvement but must be replaced following any street paving or resurfacing. The estimated costs for both scenarios are attached as Exhibits 1 and 2 and are summarized below.

AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
01/24/2023 D3 1 of 4
Discussed implementation of green bike lanes in the City and instructed staff to paint green bike lanes at intersections and revisit Bike Master Plan for protected bike lanes and coordinate with Safe Routes to School plan. Vote: 5-0

MEETING DATE: January 24, 2023 PAGE 2
SUBJECT: GREEN BIKE LANES

GREEN BIKES LANES CITYWIDE
Material Estimated Cost Maintenance Interval
Paint $1,527,750 3 years
Thermoplastic $13,236,300 7 years (following new paving)

GREEN BIKES LANES AT INTERSECTIONS
Material Estimated Cost Maintenance Interval
Paint $211,735 3 years
Thermoplastic $1,438,750 7 years (following new paving) FISCAL IMPACT: The estimated fiscal impacts associated with a green bike lane program are included in the tables above. Defined fiscal impacts would be presented with any contract award to a striping contractor to install green bike lanes following the City Council’s direction.

EXHIBITS:

1.Citywide Cost Estimate

2.Intersection Cost Estimate
01/24/2023 D3 2 of 4

Item No.Description Linear Feet
of Lanes
SF of Green
Paint Unit Price Total
Bike Lane Paint
1 Solid Bike Lane 199,050 803,240 $1.50 $1,204,860 2 Dashed Bike Lane 36,965 64,060 $1.50 $96,090 Item No.Description Unit Price Total
Symbols
3 Bicycle lane symbols $200.00 $226,800
Sub Total $1,527,750
Item No.Description Linear Feet
of Lanes
SF of Green
Paint Unit Price Total
Bike Lane Paint
1 Solid Bike Lane 199,050 803,240 $15.00 $12,048,600 2 Dashed Bike Lane 36,965 64,060 $15.00 $960,900 Item No.Description Unit Price Total
Symbols
3 Bicycle lane symbols $200.00 $226,800
Sub Total $13,236,300
Approximate Quantity
1134
City of Vista Bike Facilities Inventory - Citywide

SUMMARY OF PROBABLE COST - GREEN PAINT
1/2/2023

SUMMARY OF PROBABLE COST - THERMOPLASTIC
Approximate Quantity
(Each)
1134
1/2/2023
01/24/2023 D3 3 of 4
EXHIBIT 1

Item No.Description Linear Feet
of Lanes
SF of Green
Paint Unit Price Total
Bike Lane Paint
1 Solid Bike Lane 18,570 73,755 $1.50 $110,633 2 Dashed Bike Lane 10,340 17,135 $1.50 $25,703 Item No.Description Unit Price Total
Symbols
3 Bicycle lane symbols $200.00 $75,400
Sub Total $211,735
Item No.Description Linear Feet
of Lanes
SF of Green
Paint Unit Price Total
Bike Lane Paint
1 Solid Bike Lane 18,570 73,755 $15.00 $1,106,325 2 Dashed Bike Lane 10,340 17,135 $15.00 $257,025 Item No.Description Unit Price Total
Symbols
3 Bicycle lane symbols $200.00 $75,400
$1,438,750
377
Sub Total
377

SUMMARY OF PROBABLE COST - THERMOPLASTIC
1/2/2023
Approximate Quantity
City of Vista Bike Facilities Inventory - Intersections

SUMMARY OF PROBABLE COST - GREEN PAINT
1/2/2023
Approximate Quantity
(Each)
01/24/2023 D3 4 of 4
EXHIBIT 2

From:Sarah Spinks
To:Public Comments
Subject:C4, D2, D3 & D4, ORAL COMMUNICATIONS
Date:Tuesday, January 24, 2023 8:00:48 AM
Attachments:PXL 20230121 210304675.jpg
PXL 20230121 210234975.jpg
Dear Mayor and Vista City Council,
First, Happy Anniversary to the City of Vista!
C4. Public Lemon Mural Approval - I am excited for this new piece of interactive public art to come to downtown Vista. Thank you to Traci Lawson for bringing this project to this corner of downtown Vista.

D2. Traffic Calming Techniques - I support calming traffic in the City of Vista and prioritizing the safety of people who walk and live in neighborhoods that need some help slowing down these cars. Today, in fact, a car speeding north on North Citrus where I live flipped me off while I was pulling into my driveway. I wish this was a rare occurrence, but it isn't. Cars go absurdly fast down the narrow little street we live on and it is especially concerning because of all the Vista Magnet Middle School students who walk both two and from school. People use the neighborhood as a cut through, which is fine, but so many are not cutting through at a safe speed.

Sometimes I wonder if exploring the idea of making old, narrow streets like N. Citrus into one way directional streets could be a solution, and at the same time increasing parking options for neighbors. I remember attending a meeting when a consultant talked about how street parking actually increases pedestrian safety.

Other ideas for my street would be speed humps or more frequent stop signs - I would suggest placing one at the intersection of Washington and N. Citrus. I also think the crosswalks at intersections where neighborhoods and major arterial roads meet (such as N. Citrus and Vista Village) need something more to protect pedestrians in the crosswalks. I have been nearly run over countless times in the crosswalk I use daily - including a time I was almost run over by a City of Vista vehicle. The crosswalks at Vista Village & Civic Center and North Santa Fe & California Ave need to be repainted, especially because they are so often used by children.

In summary, I support whatever needs to happen to make walking safer and slowing cars down in neighborhoods.

D3. Green Bike Lanes - I support investing in bike infrastructure and think green bike lanes are beautiful. I look forward to Vista moving in this direction and investing in creating a community where more people get out of their cars. (I can't wait for the Rail Trail to finally be completed!)
D4. Proposed Changes to Municipal Code Regarding Appointment of Members of the City Council to the San Diego Association of Governments - I support changing the municipal code to allow city council to appoint a SANDAG representative that is not the Mayor's nomination.

The crucial vote to advance a sustainable and equitable transportation plan for our region is important to me, and I believe a representative decided by council majority best demonstrates our city's commitment to democratic values and principles.

ADD TO PACKET

ORAL COMMUNICATIONS
Please see attached photos of VHB graffiti all over the Creek Walk in Vista Village. I would like to suggest allocating funding in the future to install public art as a solution to prevent future vandalism at this site. A mixture of mosaic and murals would be a nice addition to this area where families and friends meet, people walk pets and children are often having their portraits taken. The area is so beautiful and full of so much potential and it is so sad to see it look this way. Another suggestion would be to program music events (like jazz, singer/songwriter type genre) to help positively activate the space and create a deeper sense of community stewardship.

Thank you for your attention.

Sincerely,
Sarah Spinks
N. Citrus Ave

CITY- OF VISTA .

C P L I F 0 P N f P
City Council
January 24 , 2023

CITY OF VISTA

0*0
Green Bike Lanes

CITY OF VISTA
• The City Council directed staff to place an item on the agenda to discuss
painting bike lanes green citywide
• Green painted bike lanes are intended
to highlight the presence of the bike
lanes

0*0
Green Bike Lanes

CITY OF VISTA
• Staff considered two scenarios and
developed cost estimates:
— Installing green paint along the entire
length of all existing bike lanes
— Installing green paint in existing bike
lanes in conflict areas at intersections

RnXi uF�
+ MUST
00,00

CITY OF VISTA
� illRF RFLX1
. "MIl1 limmi ROE
gr�encolamd
- - � oauement�opt�wwfl
+ IEGM
. TELI�MNES
PA-4 M togrmm WW 9f
fum gfYy fM�!fmf

IV
}":FY OF VISTA
.
+x L I F 0 R N 1 A
L UI
V
im
•r� y k 1
Y
t; R Or
FIt +. F
5 + ~

CITY OF VISTA

•may.: ��,• $ a
GOO le ■■■

WHERE VEHICLE PARKING IS PROHIBITED
Cenhlel:nE w Lana L me 50 ti t4 704 R
S"FlWre3G101?CA,
T CITY .

VISTA
r }
Cwe at EdEdea Plrntrr m 4 R Murmum 14I1(CA)
WNW rkmo,
S fY M,r mu., pmerrem
1hr#►�GMme� �opdo�alJ
oa AkNItING SIN XA)
81KE 111 MICA)
LAM 11ME
Uf►1 �
ErME R11104

WHERE VEHICLE PARKING IS PERMITTED
"A to m R Gemerline or L-am Line
So Fignt-lil
Sir Ma41r L9reM]F
j
Gr4 w Edyr d P rAaWM
d inYlUMf WILWW(opelnnu} J R#11CN k>I1F1 4 In MAID Npldlr4{ WITHOUT MARKED 3r+-+<almd WfTH!NARKED
PARKING STALLS pavemert PARKING STALLS
Nor 70 SCALE

'fir; .-t► Via`* "� ���L� i �

i�4
`JS
" [...-
I Stanton
Innnn Encinitas 0 0 _
i

0*0
Green Bike Lanes

CITY OF VISTA
• Entire length of all bike lanes:
$ 175277750
— Maintenance required every 3 years
— Annual maintenance budget: $ 500K

0*0
Green Bike Lanes

CITY OF VISTA
• Conflict areas only:
— $ 2117735
— Maintenance required every 3 years
— Annual maintenance budget: $ 70K