cc 2023 AR 05/23 cip 8355 nevada and lemon sidewalks and lighting project - award of design contract

Vista City Council
May 23, 2023

Document
cc 2023 AR 05/23 cip 8355 nevada and lemon sidewalks and lighting project - award of design contract
Meeting
May 23, 2023
Body
Vista City Council
Pages
21
Original file
384 KB
Text extracted from the city's file for reading and search. Open the original on portal.laserfiche.com. That file is the official record.

ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: C7
Prepared by:

Gabe Grewe, Capital Projects Manager
Erin Adams, Management Analyst Meeting Date: May 23, 2023 Approved by:

Greg Mayer, Acting Engineering Director
John Conley, City Manager Agenda Location: Consent Calendar SUBJECT: CIP 8355 NEVADA AND LEMON SIDEWALKS AND LIGHTING PROJECT – AWARD OF

DESIGN CONTRACT
RECOMMENDATION: Adopt City Council Resolution No. 2023- , awarding a contract to Chen Ryan Associates, Inc. for engineering design services for the Nevada Lemon Sidewalks and Lighting Project (CIP No. 8355).

CORRELATION TO CITY COUNCIL GOALS: Traffic: Continue to improve the flow of traffic for all forms of travel, reduce congestion, and improve our roads and sidewalks.

PRIOR ACTION: On June 28, 2022, adopted City Council Resolution No. 2022-108, approving a Six- Year Capital Improvement Program and FYs 2022/23 and 2023/24 Capital Project Budget and authorizing appropriations for Fiscal Years 2022/23 and 2023/24 Capital Projects (Vote: 4-0, Ritter absent (Ritter experienced technical difficulties)).

STATEMENT ON THE SUBJECT: The Nevada and Lemon Sidewalks and Lighting Project (CIP No. 8355) will construct sidewalks along one side of Nevada Avenue and along one side of Lemon Avenue providing a continuous accessible pathway from N. Santa Fe Avenue to Townsite Drive. The project will also include enhanced lighting to fill in areas where there are no streetlights, pedestrian ramps at intersections, and green streets storm water improvements.

On January 18, 2023, staff issued a Request for Proposals (RFP) for professional services for design surveying, geotechnical investigation, engineering design, and construction support for the Nevada and Lemon Pedestrian Mobility Sidewalks project. The RFP was advertised on the City’s website and the City’s procurement portal, OpenGov Procurement, and is included as part of the contract exhibits. The following seven firms responded to the RFP:

Firm Office Location
Chen Ryan Associates, Inc. San Diego, CA
Kimley-Horn San Diego, CA
KOA Corporation Monterey Park, CA
Michael Baker International San Diego, CA
O’Day Consultants, Inc. Carlsbad, CA
Quality Infrastructure Corporation La Mesa, CA
RailPros San Diego, CA
AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
05/23/2023 C7 1 of 201
Approved above recommendation, adopted City Council Resolution No. 2023-78.

Vote: 5-0

MEETING DATE: May 23, 2023 PAGE 2
SUBJECT: CIP 8355 NEVADA AND LEMON SIDEWALKS AND LIGHTING PROJECT – AWARD OF

DESIGN CONTRACT
Staff reviewed the proposals based upon predetermined criteria identified in the RFP, including project understanding, projects of a similar nature, and quality of work. Staff then reviewed the fee proposal from Chen Ryan Associates, Inc. and determined it to be fair and equitable with respect to expertise and geographic region.

Staff recommends awarding the design contract to Chen Ryan Associates, Inc. with a contract ceiling of $322,646.

FISCAL IMPACT: The contract has a ceiling of $322,646 over a three-year term with an option to extend up to an additional two years. Sufficient funding is budgeted and available in the Fiscal Years 2022/23 and 2023/24 Capital Improvement Budgets in CIP No. 8355, Nevada and Lemon Sidewalks and Lighting Project Source Appropriation Accounts (No. 1176209.578999.8355).

EXHIBITS:

1.City Council Resolution No. 2023- , awarding a contract to Chen Ryan Associates, Inc. for engineering design services for the Nevada Lemon Sidewalks and Lighting Project (CIP No. 8355)

2. Contract with Chen Ryan Associates, Inc.
05/23/2023 C7 2 of 201

00029213 7
RESOLUTION NO. 2023-

A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF

VISTA, CALIFORNIA, AWARDING A CONTRACT TO CHEN RYAN
ASSOCIATES, INC. FOR ENGINEERING DESIGN SERVICES FOR THE NEVADA LEMON SIDEWALKS AND LIGHTING PROJECT (CIP NO. 8355) The City Council of the City of Vista does resolve as follows:

1. Findings. The City Council hereby finds and declares the following:

A. Pursuant to section 3.08.040 of the Vista Municipal Code, a request for proposals (RFP) was issued on January 18, 2023.

B. Seven proposals were submitted in response to the RFP and were evaluated based upon the predetermined set of criteria identified in the RFP.

C. Staff recommends the selection of Chen Ryan Associates, Inc. as the consultant to provide engineering design services for the Nevada Lemon Sidewalks and Lighting Project (CIP No. 8355).

2. Action.

A. The contract between the City of Vista and Chen Ryan Associates, Inc. for engineering design services for the Nevada Lemon Sidewalks and Lighting Project (CIP No. 8355) is approved, and the Mayor is authorized to execute the contract.

3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on May 23, 2023, by the following vote:

AYES:

NOES:

ABSTAIN:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY
By:

APPROVED
Walter C. Chung
20230509095633
JOHN B. FRANKLIN, MAYOR
ATTEST:

KATHY VALDEZ, CITY CLERK
By:
05/23/2023 C7 3 of 201
EXHIBIT 1

05/23/2023 C7 4 of 201
EXHIBIT 2

05/23/2023 C7 5 of 201

05/23/2023 C7 6 of 201

05/23/2023 C7 7 of 201

05/23/2023 C7 8 of 201

05/23/2023 C7 9 of 201

05/23/2023 C7 10 of 201

05/23/2023 C7 11 of 201

05/23/2023 C7 12 of 201

{00111183 1} Exhibit A

EXHIBIT A

REQUEST FOR PROPOSALS

05/23/2023 C7 13 of 201

REQUEST FOR PROPOSALS (RFP)

FOR PROFESSIONAL SERVICES

FOR

NEVADA AND LEMON PEDESTRIAN MOBILITY SIDEWALKS
CIP No. 8290

Issue Date: January 18, 2023

Submittal Deadline: 4:00 PM, February 23, 2023

05/23/2023 C7 14 of 201

2 REQUEST FOR PROPOSALS

NEVADA AND LEMON PEDESTRIAN MOBILITY SIDEWALKS
CIP No. 8290

I. INTRODUCTION

The City of Vista is requesting proposals from qualified engineering firms to provide professional services for design surveying, geotechnical investigation, engineering design, and construction support for the Nevada and Lemon Pedestrian Mobility Sidewalks project.

All interested firms must have sufficient, readily available resources in the form of trained personnel, support services, specialized subconsultants, and financial resources to carry out the work without delay or shortcomings.

All Consultants must create an account on the City’s Electronic Bidding System, OpenGov Procurement to submit a proposal. Consultants can register using the ‘Sign Up’ link at the top of the page at:
https://secure.procurenow.com/portal/cityofvista

Once registered, Consultants must download this solicitation in order to appear on the Bidder’s List as a “Prospective Bidder.” Consultants that fail to specifically download this solicitation will not appear on the Bidders’ List and will be unable to participate or be considered for this RFP. See further instructions related to OpenGov Procurement under Section VIII (Proposal), below.

Special Requirements
As required by Article 2 of Chapter l of Part 7 of Division 2 of the California Labor Code, the Consultant and all subconsultants shall pay not less than the prevailing rate of wages to all workmen employed in the execution of this Contract as ascertained and adopted by the State of California, Director of Industrial Relations pursuant to the Labor Code.

The Consultant and all subconsultants shall have a City of Vista Business License prior to award of contract. Business licenses can be obtained at www.vistabl.com . A City of Vista Business License is not required to propose on this request for proposals.

II. BACKGROUND AND PROJECT DESCRIPTION

The City of Vista has identified a priority area where there is high pedestrian traffic or ADA- access issues. Nevada Avenue and Lemon Avenue were identified in this area as existing streets that are missing sections of sidewalk. The City of Vista has identified available 05/23/2023 C7 15 of 201

3 Community Development Block Grant (CDBG) funds for use on eligible portions of this project. The project generally consists of constructing curb, gutter, and sidewalk along Lemon Avenue from Raintree Place to Nevada Avenue on either the West or East side of the street, and Nevada Avenue from North Santa Fe Avenue to Lemon Avenue on either the North or South side of the street. Reconstruction of numerous driveways will be needed to accommodate the proposed improvements.

The following design objectives should be considered during the design development of the project:

1. Ensure ADA accessibility for all improvements,

2. Increase safety and mobility for non-motorized users,

3. Minimize impacts to private property,

4. Maximize the preservation of mature landscaping and healthy tree specimens.

5. Incorporate sustainable design principles and meet or exceed all stormwater regulations and requirements.

6. Minimize construction costs and long-term maintenance costs.

Attachment “A” contains exhibits showing the proposed improvements and the engineer’s budget construction cost estimate. The engineer’s estimate of probable construction cost for this project is $ 1,302,900.

III. PROPOSED SCOPE OF SERVICES

A draft Scope of Work, included as Attachment “B”, details the tasks that the selected consultant will likely be required to perform to complete the project. The proposed scope and fees should be based on the tasks listed in the draft Scope of Work.

IV. CITY RESPONSIBILITIES

The following is a list of the City’s responsibilities during the term of the agreement:

1. Provide all available existing plans, studies, reports, aerial photos, available LIDAR topographic information, and other records.

2. Coordinate access to the site for Consultant review prior to submittal of proposal.

3. Process and respond to requests to the City.

4. Provide contact information for both internal staff and external stakeholders.

5. Coordinate, notice, and schedule all public meetings, and meetings with City’s boards, commissions, and City Council.

6. Prepare all administrative reports to the commissions and City Council.

7. Provide meeting site arrangements for public meetings and workshops.

8. Review submittals from the Consultant in a timely manner.

9. Distribute public information through newsletters, mailings, email blasts, City website, and printed flyers.
05/23/2023 C7 16 of 201

4 10. Submit CEQA Environmental documents to State Clearinghouse,

11. Prepare and execute agreements with other agencies or entities.

12. Obtain and pay for all permits, agreements, and permissions for contract work on property not owned or controlled by the City.

13. Provide templates and examples of WQTR’s, plans, and specifications to Consultant.

14. Provide utility company contact information for use in coordination.

15. Prepare all project specifications.

16. Advertise and award construction contracts.

17. Administer construction contract.

V. COORDINATION

Coordination with the City, other consultants and other involved agencies is required to achieve compatible designs, phasing of construction with existing or designed conditions, and timely delivery of the contract services. Coordination may include, but not be limited to, coordination with Vista Unified School District, Vista Irrigation District, U.S. Army Corps of Engineers, San Diego Regional Water Quality Control Board, California Department of Fish and Wildlife, NCTD and other organizations.

The City will decide the manner in which the coordination of individual matters is undertaken. At the City’s option, coordination efforts may be performed by the Consultant’s direct contact, by the Consultant acting though the City or by the City only. When coordination efforts require agreement, such agreement shall be coordinated through the City.

VI. PROJECT PROGRESS

The Contract shall begin upon approval by the City, and the Consultant shall commence work after notification to proceed by the City. Unless extended by contract amendment, the contract shall terminate upon acceptance by the City of the project as constructed and upon completion by the Consultant and approval of the City of the as-built plans.

The Consultant is advised that any recommendation for contract award is not binding on the City until the Agreement is fully executed and approved by the City.

Progress Review Meetings shall be held at intervals deemed appropriate by the City. At or before each of these meetings, the Consultant shall furnish two (2) copies of all completed or partially completed work products which have been developed or altered since the last Progress Review Meeting.

Progress Reports shall be submitted at monthly intervals, indicating progress achieved during the reporting period in relation to the progress scheduled. The Consultant shall provide the City with the Progress Report at least four (4) working days before the Monthly Progress Meeting.
05/23/2023 C7 17 of 201

5 VII. PROPOSAL

A. Schedule. The City’s schedule for the selection process is as follows:

1. City Releases RFP January 18, 2023

2. Deadline for Questions February 10, 2023 at 4:00 PM

3. Proposals Due February 23, 2023 at 4:00 PM

4. Notice of Consultant Shortlist March 2, 2023

5. Consultant Interview (If Needed) March 9, 2023

6. Notice of Consultant Selection March 14, 2023

7. Complete Negotiation of Agreement March 21, 2023

8. Council Award April 25, 2023

A Notice to Proceed for this project is tentatively scheduled to be issued in May 2023. Upon issuance of Notice to Proceed, the Consultant shall submit a detailed schedule for the project including milestones and progress reports.

All dates are subject to change, and the City reserves the right to extend the date by which proposals are due.

All questions must be submitted via “Q&A” through the City’s Electronic Bidding System, OpenGov Procurement. Phone call questions will not be accepted. Answers to all submitted questions will be provided in an addendum through OpenGov Procurement.

To receive addenda and submit a proposal, Consultants shall register on the City’s Electronic Bidding System at https://secure.procurenow.com/portal/cityofvista . Once registered, Consultants must download the RFP while logged in under their own name and identification number to appear on the Electronic Prospective Bidders List as a “Prospective Bidder.” Consultants that fail to download the RFP will not appear on the Electronic Prospective Bidders List and their proposals will be considered non-responsive. If a Consultant is unable to register or download the RFP from OpenGov Procurement, a Consultant representative may contact OpenGov Procurement to troubleshoot the problem.

All proposal documents and supplementary documents must be uploaded using OpenGov Procurement prior to event date and time as instructed in this solicitation. Once file(s) have been uploaded and the Submission Status shows as “Submitted” the submission is complete. At that point respondents will receive an email confirmation from OpenGov Procurement.

OpenGov Procurement will determine the official time for the advertised proposal due date and such determination will be final. Any proposals not received in a timely manner on the Proposal Due Date, as described above, will not be considered.

05/23/2023 C7 18 of 201

6 Note: The City of Vista complies with the Americans with Disabilities Act. If you require reasonable accommodations, please contact the Office of the City clerk, 760-639-6125, at least forty-eight (48) hours prior to the bid opening.

B. Requirements.

In order to maintain uniformity with all proposals furnished by Consultants, it is hereby requested the proposals be limited to a maximum of ten (10) pages (excluding front and back covers, section dividers, Scope of Work, Fee Proposal, Work Schedule, sample Work Product, and resumes).

The Proposal should typically be formatted to fit on 8-1/2 x 11 pages. Larger pages up to 11x17 can be used for exhibits, such as a schedule, if needed to make the exhibits legible due to a substantial amount of detail. The page count is based on pages of information included in the RFP that indicates the Consultant’s qualifications. Double-sided pages are acceptable, and a page that says “this side intentionally left blank” does not count toward the page limit. Proposals should include, at a minimum, the following elements:

1. COVER LETTER, which includes:
a. The name and address of the firm on formal letterhead, b. The name of the project, and
c. The name, title, and signature of an individual with authority to bind the Consultant.

2. STATEMENT OF QUALIFICATIONS, which includes:
a. A synopsis of the firm’s qualifications,
b. An Organization Chart showing the names and classifications of key personnel, and project team relationships,
c. A staffing plan and descriptions of the qualifications of the Project team members,
d. Resumes of key prime and subconsultant staff members assigned to the project, e. A list of similar contracts completed by the firm or team members within the last five (5) years. Include the project name; project description; location; role and level of involvement of the prime firm as well as any sub-consultants; design and/or construction dates of completion; bid costs vs. final construction costs, and client references with name, phone number and email address, and f. Information related to the financial responsibility of the firm.

3. WORK PLAN which describes:
a. The Consultant’s understanding of the project,
b. The approach and methodology to be used to accomplish the required services, and
05/23/2023 C7 19 of 201

7 c. The Consultant’s proposed Scope of Work. The proposed Scope of Work should be based on the tasks listed in the draft Scope of Work included in this Request for Proposals, with suggested alternatives to the proposed tasks or deliverables that may improve upon achievement of the project objectives. The Consultant should clearly identify any proposed modifications to the tasks listed in the draft Scope of Work.

4. FEE PROPOSAL which includes:
a. A breakdown of costs by task, together with
b. The cost of non-labor and subconsultant services. This information will be used by City staff to evaluate the reasonableness of the fee proposal and will be used in negotiating the final fee amounts for the Professional Services Agreement. The Consultant’s Standard Hourly Billing Rates for all classifications of staff likely to be involved in the project shall be included with the fee proposal along with the mark-up rate for any non-labor expenses and subconsultants.

5. Detailed WORK SCHEDULE, which shows:
a. The time required for each task, and
b. The reasonable amount of time the Consultant will require to perform the required services. The proposed Work Schedule should list the tasks with begin and end dates and should be based on the proposed start date listed in this RFP.

Project milestones such as submittals should be shown, and a reasonable amount of time should be shown for City review of each submittal.

6. Comments on the City of Vista Standard CONSULTANT AGREEMENT. Identify any concerns with the terms and conditions of the City’s Standard Consultant Agreement, including Insurance and Indemnification provisions. If terms are acceptable, provide a statement that the Consultant will sign the City’s Agreement as presented.

7. Copies of SAMPLE WORK PRODUCT from a previous similar project completed by the Consultant. The consultant shall submit examples of reports and bid packages consisting of Plans, Specifications, and Estimates for a project similar to the ones described in this RFP.

VIII. CRITERIA FOR SELECTION

The City's consultant evaluation and selection process is based on Qualifications Based Selection (QBS) for professional services. An evaluation committee appointed by the City Engineer will review the proposals. The criteria and weight for evaluating the proposals submitted will be as follows:

1. Project Understanding: Demonstrated understanding of the project requirements, degree of creativity and innovation demonstrated with respect to the project 05/23/2023 C7 20 of 201

8 approach and scope of work, and reasonableness of the schedule for the work and how the time has been allocated to specific tasks (30 points)

2. Responsiveness to Client’s Needs: Familiarity with City, State, and federal requirements and procedures; and thoroughness and completeness of proposal in response to RFP (20 points)

3. Firm’s Experience with Similar Projects: Technical experience of project team in performing work of a closely related nature, experience working with public agencies, record of completing work on schedule and within budget. (15 points)

4. Staff and Project Experience: Qualifications of project team staff members, key personnel’s level of involvement in performing related work, logic of project organization, and adequacy of labor commitment. (15 points)

5. Resource Allocation and Cost: Financial Responsibility of the firm, reasonableness of the total price for the work and how the costs have been allocated to specific tasks (10 points)

6. Quality of Work Product: Demonstrated technical ability based on relevance and quality of sample work product (10 points)

Fee Schedule (separate electronic file uploaded to OpenGov Procurement). The fee schedule of the top ranked Consultant will be opened at the conclusion of the consultant evaluation and selection process. Fees will not be used to determine the ranking of the consultants. The City will may interview a short list of top ranked qualified consultants or proceed directly to negotiating the final fee schedule with the top ranked consultant. The ultimate consultant selection will be based upon both technical merit and value to the City.

The contract award, if any, will go to the Consultant whose proposal best serves the interests of the City, as it determines in its sole discretion according to the evaluation criteria described above.

The individual or composite ratings and evaluation forms prepared by City’s evaluators will not be revealed.

IX. REQUIREMENTS FOR PROVIDING SERVICES
The selected Consultant shall be expected to comply with all applicable federal, state, and local regulations, and contract provisions. The selected consultant will be expected to perform the work as described in this RFP.

Consultant shall carry out the instructions received from the City and shall cooperate with the City and other involved agencies.

The Consultant will be required to assume responsibility for all services offered in their proposals. The selected consultant will be the sole point of contact with regard to contractual matters, including payment of any and all charges resulting from contracts.

The Consultant shall have a Quality Control and Quality Assurance (QA/QC) plan in effect during 05/23/2023 C7 21 of 201

9 the entire time work is being performed under the Agreement. The QC/QA plan shall establish a process whereby plans and other work products are independently checked, corrected, and back checked, and all job-related correspondence and memoranda are dated and then bound in appropriate job files.

Consultant is responsible for researching available records, determining their usefulness on this project, and paying any charges for copies of records.

All exhibits, studies, reports, plans, specifications, estimates, calculations, and other documents shall be prepared in accordance with the scope of work. City of Vista standards and San Diego Regional Standard Drawings shall be utilized where applicable and may be called out on the plans as a reference. Improvement plans shall adhere to City of Vista Standards and the Standard Specifications for Public Works Construction (GREENBOOK). Plans and exhibits shall be computer drafted in AutoCAD, ArcView or other compatible software and delivered to the City of Vista at project completion on electronic media in a format readable by the City, along with .pdf files for archival purposes.

The exhibits, studies, reports, plans, specifications, estimates, calculations, and other documents furnished under the Agreement shall be of a quality acceptable to the City. All work products shall be of neat appearance, well organized, technically and grammatically correct, internally consistent, thoroughly reviewed and checked, dated, designated with an accurate “percent complete” number, and having the maker and checker identified. The minimum standard of appearance, organization and content of the drawings and other work products shall be that of similar types provided by the Consultant in its Proposal as Sample Work Products and as set forth in related City of Vista standards and guidelines. The Consultant shall modify its work as necessary to meet the level of acceptability defined by the criteria above.

The Consultant has total responsibility for the accuracy and completeness of the studies, reports, exhibits, plans and related designs, specifications and estimates prepared and shall check all such materials accordingly. The reports, plans, and other work products will be reviewed by the City for conformity with the requirements of the Agreement. Reviews by the City do NOT include detailed review or checking of design or the accuracy with which such designs are depicted on the plans. The responsibility for accuracy and completeness of such items remains solely that of Consultant.

Consultant or its subconsultants shall not incorporate in the design any materials or equipment of single or sole source origin without written approval of the City.

All completed work, including surveys, workshop documents, schematic designs, ancillary reports, calculations, correspondence, and all other work product developed as part of this project, whether in written, video, or electronic formats, becomes the property of the City at the end of the project.

05/23/2023 C7 22 of 201

10 X. ESTABLISHMENT OF FEES

The Consultant shall be paid based upon hourly rates and unit costs for services rendered as negotiated. Sub-consultant costs shall be allocated on a per task basis but does not need to be broken out by each staff classifications. The City limits mark up for sub-consultants and direct costs to 5%. This information will be used by City staff to evaluate the reasonableness of the estimated cost of services and will be used in negotiating the final fee amounts for the contract agreement. Hourly rates shall be based on work occurring in 2023. Proposed rates shall clearly correlate with names and classifications of staff likely to be involved with the projects.

The Consultant shall be paid based upon hourly rates for services rendered as negotiated.

There will be no compensation to the Consultant for hours expended due to the Consultant’s errors and omissions. There will be no adjustments including an increase in the hourly rate.

XI. METHOD OF PAYMENT

The Consultant shall submit monthly invoices to the City. Each invoice shall include a detailed breakdown of the services, the tasks, the hours, the personnel, and staff type who worked on the project, and hourly rates. No more than 85 percent of the total payment amount will be made prior to the final completion and approval of all work and delivery of final products.

XII. CONSULTING AGREEMENT

A sample Standard Consulting Agreement is enclosed for review, as Attachment “C”. The RFP and the Consultant’s Proposals will be attached and become part of the Agreement as exhibits.

The signer of the proposal must declare in writing that the only person, persons, company or parties interested in the proposal as principals are named therein; that the proposal is made without collusion with any other person, persons, company, or parties submitting a proposal; that it is in all respects fair and in good faith without collusion or fraud; and, that the signer of the proposal has full authority to bind the principal proposer.

Please refer to the sample agreement for the necessary amounts of general liability, automotive, worker’s compensation and professional liability insurance. The appropriate endorsements are also shown within the sample contract agreement. The insurance certificate shall include the City of Vista, its officers and employees as insured or additional insured.

The contents of the Proposal of the successful Consultant shall become a contractual obligation if a contract ensues. Failure of a Consultant to accept this obligation will result in 05/23/2023 C7 23 of 201

11 the cancellation of any award. Any damage accrued by the City as a result of a failure to contract may be recovered from the Consultant.

XIII. ASSIGNED REPRESENTATIVES

The City will assign a responsible representative to administer the contract, and to assist the Consultant in obtaining information. The Consultant also shall assign a responsible representative (Project Manager), who shall be identified in the proposal. The Consultant’s representative will remain in responsible charge of the Consultant’s duties from the Notice- to-Proceed through project completion. If the Consultant’s Project Manager should be unable to continue with the project, then the Consultant shall notify the City’s representative in writing. The City’s representative shall first approve any substitution of representatives or sub-consultants identified in the proposal in writing. The City reserves the right to review and approve/disapprove all key staff and sub-consultant substitution or removal and may consider such changes not approved to be a breach of contract. This breach of contract will not apply if the Project Manager leaves the Consulting firm.

XIV. RIGHT TO REJECT PROPOSALS

The City reserves the right to delay the project or reject any or all proposals submitted, and no representation is made hereby that any contract will be awarded pursuant to this RFP or otherwise.

The City reserves the right to extend the due date for proposals, accept or reject any or all proposals received as a result of this RFP, negotiate with any qualified consultant or cancel this RFP in part or in its entirety. The City may require the selected Consultant to participate in negotiations and to submit such technical, fee, or other revisions of their proposals as may result from negotiations.

All costs incurred in the preparation of the proposal, the submission of additional information and/or any aspect of a proposal prior to award of a written contract will be borne by the Respondent. The City will provide only the staff assistance and documentation specifically referred to herein and will not be responsible for any other cost or obligation of any kind, which may be incurred by the Respondent. All proposals submitted to the City of Vista become the property of the City.

XV. DISCLOSURE

The City is a public agency subject to the disclosure requirements of the Public Records Act, California Government Code Section 6250 and following. These requirements include an exemption for “trade secrets”. If any proprietary information is contained in or attached to the written proposal, it must be clearly identified in Consultant’s proposal. In order to protect trade secrets from disclosure, pursuant to a Public Records Act request, you must agree in writing to defend and indemnify the City of Vista if litigation results. 05/23/2023 C7 24 of 201

12 XVI. LATE, MODIFIED, OR WITHDRAWN PROPOSAL

Any Proposal received after the exact time specified for submittal will not be considered.

Any modification of a proposal, except a modification resulting from the City's request for "best and final" offer, is subject to the same conditions as the initial submission.

Proposals may be withdrawn by written notice received at any time prior to Notice of Intent to Award. Thereafter, all proposals constitute firm offers, subject to negotiation and execution of definitive documents that will remain open and cannot be revoked, withdrawn, or modified for a period of six (6) months thereafter.

XVII. CONCLUSION

If after reviewing the above requirements, the Consultant is interested in proposing your services to the City of Vista, the Consultant should notify the City of their interest and their intent to submit a proposal. All submittals must be received in the Engineering Department by the date and time listed in this RFP.

The selected consultant will be asked to negotiate a final scope of work, fee, and schedule for the project. Small contracts up to $150,000 may be awarded by the City Manager.

Larger contracts over $150,000 must be approved by the City Council.

If you have any questions, please contact me.

Sincerely,

Gabe Grewe
Capital Projects Manager
760.643-5413
[email protected]

Attachment A: Proposed Improvements and Engineer’s Budget Construction Estimate Attachment B: Draft Scope of Work
Attachment C: City of Vista Standard Consulting Agreement

05/23/2023 C7 25 of 201

13 ATTACHMENT A

Proposed Improvements and Engineer’s Budget Construction Estimate

05/23/2023 C7 26 of 201

NEVADA AND LEMON PEDESTRIAN MOBILITY SIDEWALKS
August 18, 2022
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search,appraisal, survey, or for zoning verification. ±
1 inch = 100 feetPrint Date:0 90 18045
ft
05/23/2023 C7 27 of 201

Project:Nevada and Lemon Pedestrian Mobility Sidewalks. CIP No. 8290 Location:Nevada Avenue and Lemon Avenue
Agency:City of Vista
Prepared By:Gabe Grewe
Date:10/26/2022
Item #Item Description Unit Quantity Unit Cost Amount
1 Mobilization, Demobilization, Bonds & Insurance. (5% Maximum of Total Base Bid)LS 1 $45,000.00 $45,000.00
2 Project Information Sign.EA 2 $1,150.00 $2,300.00
3 Public Notification per Supplementary General Provisions, Section 7-12.2.LS 1 $6,000.00 $6,000.00
4 Storm Water Pollution Prevention, SWPPP, and Erosion Control.LS 1 $48,000.00 $48,000.00 5 Traffic Control and Construction Staging.LS 1 $25,000.00 $25,000.00 6 Utility Potholing and Coordination. LS 1 $8,000.00 $8,000.00 7 Record Drawing (“As-Built”) Plans. (Stipulated Amount)LS 1 $2,000.00 $2,000.00 8 Clearing, Grubbing, Saw cutting, and Removals of Existing Vegetation, Roots, Concrete, Asphalt, and other Existing Improvements Interfering with New Work.LS 1 $60,000.00 $60,000.00 9 Relocate, Reconstruct, or Replace Existing Mailbox and Post per City of Vista Standard Drawing SRF-04 Including Reflective Address Numbers on Front and Side of Mailbox. (2” Minimum)EA 30 $350.00 $10,500.00 10 Replace street signs in new sidewalk EA 7 $300.00 $2,100.00 12 Move Street Light Pole and electrical EA 2 $10,000.00 $20,000.00 13 Reconfigure Existing Private Irrigation Systems and Replace Turf and Groundcover to Match Existing Private Landscaping Disturbed by Construction. Install Sleeves Under Sidewalk.LS 1 $10,000.00 $10,000.00 14 Install Gravity Retaining Wall SF 500 $45.00 $22,500.00 15 Unclassified Excavation and Fill.LS 1 $20,000.00 $20,000.00 16 Install 3” Sidewalk Underdrain per SDRSD D-27.EA 30 $200.00 $6,000.00 17 Stormwater Treatment System (Tree Wells, Iirrigation, Storm Drain, etc.)LS 1 $174,000.00 $174,000.00
18 Install 6” Type ‘G’ Curb and Gutter per SDRSD No. G-02 on 6- inches of Class II Aggregate Base and Pavement Restoration per COV SRF-13.LF 1965 $80.00 $157,200.00
19 Install Type C Curb Ramp per SDRSD No. G-29 on 6" of Class II Aggregate Base EA 6 $5,680.00 $34,080.00
20 4” PCC Sidewalk per SDRSD G-07 and G-09 on 6-inches of Class II Aggregate Base. SF 4000 $13.00 $52,000.00
21 4” PCC sidewalk per SDRSD G-07 and G-09 with Monolithic Retaining Curb on 6-inches of Class II Aggregate Base. Width per SF 4000 $15.00 $60,000.00 22 Remove and Replace 5.5” PCC Residential Driveway Entrance per SDRSD Nos. G-14A, G-14B & G14F on 6-inches of Class II Aggregate Base.SF 5220 $30.00 $156,600.00
23 Remove and Replace 7.5” PCC Commercial Driveway Entrance per SDRSD Nos. G-14A, G-14B & G14F on 6-inches of Class II Aggregate Base.SF 500 $35.00 $17,500.00
24 Header/Edge Cut. (1.5-inch to 0-inch)SF 17864 $.48 $8,574.72 25 2” Leveling Course. (Use 155 lbs/cf for Estimating Quantities)TN 500 $149.00 $74,500.00 26 AC Fabric. (Petromat Enviro) SY 4800 $7.25 $34,800.00 27 1.5” PMAC Overlay. (Use 155 lbs/cf for Estimating Quantities)TN 460 $112.00 $51,520.00 28 Lemon Road Parking Area Widen 6" AC Depth TN 270 $149.00 $40,230.00 29 Remove and Install new 36-inch Manhole Frame and Cover to Finish Grade.EA 6 $3,300.00 $19,800.00
30 Adjust Water Valve Cover to Finish Grade. (Stipulated amount)EA 15 $150.00 $2,250.00 31 Replace All Existing Thermoplastic Crosswalks, STOP, and Stop LS 1 $6,000.00 $6,000.00 32 Replace All Existing Striping. (2 coats)LS 1 $8,000.00 $8,000.00 1,184,454.72$
118,445.47$
1,302,900.19$ Total:

ENGINEER'S COST ESTIMATE
Sub Total:

Construction Contingency (10%):
05/23/2023 C7 28 of 201

14 ATTACHMENT B

Draft Scope of Work

05/23/2023 C7 29 of 201

B-1

NEVADA AND LEMON PEDESTRIAN MOBILITY SIDEWALKS
CIP 8290

DRAFT SCOPE OF WORK

The Scope of Work included in the Proposal should include the following tasks:

Task 1 – Project Initiation, Management and Coordination

A. Schedule and hold an initial meeting with City staff and subconsultants to discuss the approach to the project, scope of work, schedule and address any questions or requests for information from the consultant or subconsultants
B. Coordinate the day-to-day activities on the project and manage all subconsultants and coordinate their activities
C. Hold up to six formal meetings with City staff to develop the design of the project, resolve design issues, discuss staff comments on plans, estimate, and document submittals, discuss progress and address any other issues. It is important that the design of the project is developed in coordination with the City to ensure that the City’s goals and objectives are met.

D. Produce and distribute meeting agendas and minutes.

E. Maintain open and regular communications with City staff and subconsultants.

Deliverables:

Meeting agendas; meeting minutes; progress reports, and project documentation.

Task 2 – Data Collection and Field Review

A. Obtain aerial topographic survey of the project site from the City for use in developing a preliminary layout of the proposed improvements.

B. Collect existing as-built plans for street improvements, sewer, water, and storm drain systems for the project site.

C. Obtain utility maps from utility companies.

D. Conduct a field review to become familiar with the physical layout and features of the project site. Note any features that may need special attention or may present a challenge in the design development or final design of the project.

E. Conduct a study of existing conflicts and determine the best layout for the proposed sidewalks on either the North or South side of Nevada Avenue and the West or East side of Lemon Avenue.

See proposed improvements in Attachment A. The proposed sidewalk location shall be in the best interest of the City to minimize construction costs, long-term maintenance costs, and potential for flooding.

Deliverables:

Documentation of all data collected in the tasks above.

Task 3 –Design Surveying and Base Map Development

A. Obtain and review existing maps, Records of Survey (ROS), Corner Records (CR), etc. for existing right-of-way / property lines, easements, etc.
05/23/2023 C7 30 of 201

B-2
B. Establish vertical and horizontal control for the project based on City of Vista benchmarks and first order control map, ROS 14023.

C. Notify property owners / tenants with “doorknob” hangers at least two working days prior to entering private property if needed. The format of the notification shall be approved by the City’s Project Manager prior to distribution.

D. Establish and set semi-permanent horizontal and vertical control points for use during design and construction.

E. Locate and identify existing boundary and other survey monumentation to establish right-of-way & property line, and to perpetuate monumentation within the limits of work. Show all existing monuments within the project limits on the topographic base map so all monuments can be labeled on the improvements plans to be protected or replaced.

F. Establish the centerline and right-of way for the project streets and depict on the base map. Tie the public right-of-way and topography to NAD ’83 Coordinate system.

G. Prepare topographic base map. Develop topography within the project limits of work and 20 feet beyond the ultimate right-of-way of the project streets unless otherwise specified (i.e. driveways).

H. Locate and identify all visible VID water and franchise utility facilities. Provide top of pad or top of vault elevation and size for all pull-boxes, vaults, and enclosures.

I. Locate and identify all streetlight facilities. Provide finish surface, top of pad, or top of vault elevations and size for all poles, pull-boxes, vaults, and enclosures.

J. Locate and identify all sewer and storm drain facilities. Provide finish surface, top of rim or grate, flowline, and invert elevations and size for all structures, manholes, pipes, cleanouts, and enclosures.

K. Obtain USA mark-out and locate and identify underground utility pipe and conduit locations based on utility mark-outs prior to potholing.

L. Locate and identify other surface features, including:

1. Top of curb including elevation and centerline offset distance with identifier, if applicable (PCR, BC, EC, PCC, etc.)

2. Gutter lip

3. Pedestrian ramps

4. Cross Gutters

5. Structures

6. Trees and large shrubs. Coordinates shall be to the center of the tree or shrub and include tree type and diameter, elevation of tree at trunk base, approximate tree height, surface root and drip line perimeters

7. Driveways and driveway aprons including elevations within a 50-foot area behind the driveway apron, at all construction / expansion joints and where driveways meet concrete slab of garage. Sufficient field data of driveways (to garage doors), located adjacent to proposed curb, gutter, and sidewalk improvements, in order to redesign the driveways and yards

8. Sidewalks including back of sidewalk location and elevation, especially any lifted portions

9. Fences and walls including type and condition

10. Mailboxes including type and condition

11. Steps including type and condition

12. Retaining walls including type (reinforced or unreinforced, footing or no footing) and condition

13. AC paving and dikes

14. Signs

15. Striping and pavement markings

16. Other significant surface features
M. Prepare a digital AutoCAD topographic base map of all the elements and elevations obtained in the topographic survey, at 20 scale with 1-foot contours. 05/23/2023 C7 31 of 201

B-3
N. After the horizontal alignments of the new curbs have been established, profile the existing surface at the street centerline and the proposed curb lines, with elevations measured at maximum 50-foot intervals and at other locations where anomalies exist, to provide accurate finish grade elevations for vertical alignment design.

Deliverables:

A digital AutoCAD base map containing all the elements and elevations obtained in the tasks above, and existing surface profiles at centerline and at proposed curb lines.

Task 4 – Geotechnical Investigation and Report Preparation

A. Conduct geotechnical testing of existing soil along shoulders of Nevada Avenue and Lemon Avenue to determine adequacy for road widening improvements with street structural section recommendation.

B. Conduct geotechnical testing at any locations where a retaining wall is proposed and provide the geotechnical parameters needed to design the retaining wall. At a minimum, provide the saturated unit weight; angle of internal friction; allowable soil bearing value for the retained zone, reinforced zone, and foundation zone; and backfill recommendations C. Prior to any subsurface excavations a no fee right-of-way permit (and possibly an approved traffic control plan) from the City of Vista and a USA mark out would be required D. Prepare a report documenting geotechnical investigation and testing and all findings and recommendations by a Licensed Geotechnical Engineer.

Deliverables:

Geotechnical Investigation Report.

Task 5 – Water Quality Technical Report

A. Prepare a Project Determination Checklist using the template provided by the City. The City of Vista has determined that the Urban Runoff Threat Assessment is “high” for all projects.

B. If the project is determined to be a Standard or Priority Project, prepare a Stormwater Quality Management Plan(SWQMP) using the template provided by the City.

C. Prepare Municipal Stormwater Permit documentation in accordance with San Diego Regional Water Quality Control Board Order No. R9-2013-0001/2015-0001, using the City of Vista BMP Design Manual. Determine applicable design requirements. Evaluate potential for any exemptions related to sidewalk projects. Submit report to the City for review and make changes as requested by the City.

D. Incorporate all required hydro-modification improvements and permanent BMP’s into the project design.

Deliverables:

Project Determination Checklist, SWQMP, Water Quality Technical Report, and Design Exhibits.

Task 6 – Preliminary and Final Design

A. Coordinate with other ongoing and planned projects such to ensure compatibility of the proposed improvements with those other projects.
05/23/2023 C7 32 of 201

B-4
B. Using the AutoCAD topographic base map, develop a preliminary horizontal layout of the improvements and a preliminary striping plan showing lane configuration for review and acceptance by the City. Make adjustments as requested by the City.

C. Identify and label existing features, including survey monuments, utilities, streetlights, and spot elevations.

D. Based on supplemental survey elevations, develop, design and draft the horizontal and vertical geometrics and alignments of the project improvements in plan and profile layouts.

E. Analyze the drainage patterns after the plan and profile layouts are developed to ensure that the streets and private properties will drain properly. Adjust the design to include drainage features or grading work to ensure proper drainage is maintained.

F. Design hydromodification and stormwater treatment improvements based off the recommendations within the Water Quality Technical Report.

G. Call out all the proposed improvements using detailed and distinct construction notes and refer to standard drawings or details shown elsewhere on the plans as appropriate H. Design typical cross sections to reflect the existing conditions and the proposed improvements I. Provide details of improvements such as retaining walls, curb ramps, curb pop-outs, and driveways, to clearly show the required construction, to enable a contractor to construct the improvements with minimal, if any, requests for information and change orders.

J. Draft Title Sheet and detail sheets containing general notes, special notes, special provisions, typical sections, construction details, etc., similar to other City of Vista projects, using City standard templates adjusted for this project.

K. Prepare striping and signing plans.

L. Design a schematic erosion control plan with specific erosion control measures and temporary BMPs called out at specific locations where excavation is proposed, similar to other City of Vista projects, using City standard templates adjusted for this project.

M. Submit the plans to the City for review at 60%, 90% and 100% design levels. Depending on the level of completeness of the submitted plans, allow for a minimum of four iterations of comments by the City and corrections or revisions to the plans.

Deliverables:

Preliminary horizontal layout, design plans of the project improvements at the 60%, 90%, and 100% design levels, and bid-ready construction plans signed and sealed by the Engineer of Work.

Task 7 –Utility Coordination

A. Submit preliminary horizontal layout on topographic base map to utility companies and request confirmation that utility facilities are depicted accurately.

B. Submit the preliminary design plans to all utility companies and request a conflict check.

C. Coordinate with utility companies who have utilities in conflict with the proposed improvements.

Obtain pothole information for utility conflicts and adjust locations of facilities to avoid or minimize conflicts if possible. Request relocation of utility facilities where conflicts cannot be avoided. Obtain schedule of relocation design and construction from utility companies.

D. Submit final construction plans signed by the Engineer of Work and City Engineer and confirm that utility companies are designing their relocations.

E. Ensure that the utility companies who have utilities in conflict with the proposed improvements schedule the construction of the relocation of their utilities through their internal procedures.

F. Obtain signatures from VID on the plans if any water facilities are affected by the proposed improvements.

05/23/2023 C7 33 of 201

B-5
Deliverables:

Copies of correspondence with utility companies and copy of pothole report.

Task 8 –Construction Cost Estimates

A. Using the 60% design plans, develop a preliminary engineer’s estimate of the costs to construct the proposed improvements. The estimate is to include a list of all items of work, including any items not detailed on the 60% plans. Cost information shall include item quantities, unit cost per item and total cost for each item as well as contingencies and total construction cost. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

B. Update the engineer’s estimates at the 90% and 100% design levels to include all items of work and appropriate quantities and contingencies. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

C. Prepare a Final Engineer’s Estimate of Construction Cost, using only the limited number of items of work that will be included in the Bid Schedule and showing no contingencies.

Deliverables:

Detailed Engineer’s construction cost estimates at the 60%, 90%, and 100% design stages, and a Final Engineer’s Estimate of Construction Cost.

Task 9 – Construction Support for Design

A. Provide written and graphical responses to questions from bidders related to the project plans during the construction bid phase.

B. Prepare addenda as required during the construction bid phase.

C. Provide other support during the construction bid phase as needed D. Attend the pre-construction meeting
E. Respond to Requests for Information from the construction contractor during the construction phase.

F. Provide other support during the construction phase

Deliverables:

Written responses to questions from bidders, written addenda, written responses to RFI’s from the Contractor, and other construction support documentation.

Task 10 – As-Built Plans and Project Close-out

A. Upon completion of construction and using Change Orders and red line plans marked by the City inspector and construction contractor, draft as-built plans for the project. Incorporate all changes to the plans electronically with all necessary revision notations B. Submit a plan set signed by the Engineer of Work to the City with an electronic copy of the final as-built drawings, for review and approval by the City inspector and City Engineer.

C. Submit an electronic copy of all the files developed during the project, including research, survey, geotechnical, utility coordination, design, plans, estimates and all other project documentation.

Deliverables:

Final signed as-built plans and electronic copy of the project files. 05/23/2023 C7 34 of 201

B-6
Task 11 – Conduct Quality Control and Quality Assurance

The Consultant shall have a quality control & quality assurance plan in effect during the entire time work is being performed under the Agreement. The Quality control plan shall establish a process whereby plans and other project documents are independently checked, corrected, and back checked prior to submittal to the City. The Consultant is to maintain neat and organized project files.

Deliverables:

Copy of QA/QC Plan to be followed during the project, and quality control and quality assurance evidenced in the quality of all plans and documents submitted to the City. City may request to view internal plan check comments to verify QA/QC.

05/23/2023 C7 35 of 201

15 ATTACHMENT C

City of Vista Standard Consulting Agreement
05/23/2023 C7 36 of 201

Professional Services (Non-Construction) (RFP)(NPW) 1 of 9 NAMEX [51960-2] 00051960 4

CONTRACT FOR PROFESSIONAL SERVICES

TYPE OF SERVICES
THIS “CONTRACT” is entered into by and between the “Parties” as of ___________________ (“Contract Date”).

1.0 THE “PARTIES”
The “City”:

CITY OF VISTA, a chartered municipal
corporation
200 Civic Center Drive
Vista, CA 92084

Working Contact: workingname
Billing Contact: billingname
The “Contractor”

NAMEX, statusx
Address1
Address2

Contact: contactname

2.0 BASIC TERMS

2.1 The “Services” to be performed by Contractor are set forth in the Request for Proposals attached as Exhibit A.

2.2 The “Required License” for the Services is: type.

2.3 Contractor, an entity holding the Required License, desires to enter into this “Contract” with City for the Services.

2.4 The “Project” for which the Services are required is described in Exhibit A.

2.5 Contractor has submitted to City a Proposal to perform the Services dated proposaldate (“Exhibit B”).

2.6 The “Contract Ceiling Price” is: pricex

2.7 Any references in Exhibit A or Exhibit B to “Consultant” shall mean Contractor for the purposes of this Contract.

3.0 CONTRACT TERM

3.1 This Contract shall take effect as of the Contract Date.

3.2 This Contract shall be in effect for xx calendar months (“Term”) from the Contract Date. The Term may be extended at the City’s option for an additional yy months, in increments of City’s choice, for a maximum Term of zz months from the Contract Date.

3.3 City may terminate this Contract upon 30-days’ written notice to Contractor. In such event, or upon request of City, Contractor shall assemble all City documents in the Contractor's possession, put them in order for proper filing and closing, and deliver the documents to City. In the event of termination, Contractor shall be paid for work performed to the termination date. City shall make the final determination as to the portion of tasks completed and the compensation to be paid.
05/23/2023 C7 37 of 201

Professional Services (Non-Construction) (RFP)(NPW) 2 of 9 NAMEX [51960-2] 00051960 4

4.0 SCOPE
Contractor shall perform all Services including, but not limited to, the furnishing of all tools, equipment, materials, software, and supplies, and for furnishing all transportation, services, including fuel, power and water, essential communications, and the performance of all labor, work, or other operations, as may be required from time to time, in accordance with Exhibit A and Exhibit B. In the event of a conflict between the provisions of Exhibit A and Exhibit B, the provisions of Exhibit A shall control.

5.0 COMPENSATION

5.1 City shall pay Contractor for the Services to be performed as set forth in Exhibit B.

5.2 An invoice for payment shall be submitted in a form satisfactory to City. At a minimum, the invoice shall include: the purchase order number, the work order number, a description of the work performed, and a total amount.

5.3 Changes in, additions to, or deductions from the Services, including increases or decreases in any item or portion of the Services, shall be set forth in a written change order executed by City and by the Contractor which shall specify:

5.3.1 The changes, additions, and deductions to be made.

5.3.2 The increase or decrease in compensation due the Contractor, if any.

5.3.3 Adjustment in the time of completion, if any.

5.4 Contract Ceiling Price

5.4.1 In no event shall City be liable for paying more than the Contract Ceiling Price for Contractor's services rendered under this contract.

5.4.2 If it becomes foreseeable that Contractor will need to perform services such that the cumulative total of costs to City will exceed the maximum permitted by this Contract, any such cost overrun will be handled pursuant to the change order procedure in Vista Municipal Code Chapter 3.08. City and Contractor recognize that City lacks authority to exceed the cost ceiling without the express authorization of the City Council. If the maximum cost to City for this Contract is exceeded unexpectedly, payment shall be made as mutually agreeable and disputes shall be handled pursuant to this Contract, but work shall cease as soon as is reasonably feasible once the cost ceiling plus allowable change orders, if any, is exceeded.

5.5 Except as provided in Exhibit B, Contractor shall not be reimbursed for any expenses incurred in rendering services under this Contract. 05/23/2023 C7 38 of 201

Professional Services (Non-Construction) (RFP)(NPW) 3 of 9 NAMEX [51960-2] 00051960 4

6.0 CONTRACT DOCUMENTS
The Contract comprises the following documents including all additions, deletions, modifications, and appendices and all addenda setting forth any modifications or interpretations of any these documents: Documents required under Exhibits A–E.

7.0 TIME FOR COMPLETION AND COMMENCEMENT OF SERVICES
All Services under the Contract must be completed in compliance with the schedule in Exhibit A.

8.0 STANDARD OF PERFORMANCE

8.1 Contractor represents and warrants that it has the training, qualifications, experience, and facilities necessary to properly perform the Services required under this Contract in a thorough, competent, and professional manner. At all times Contractor shall faithfully, competently and to the best of its ability, experience, and talent, perform all services described herein. In meeting its obligations under this Contract, Contractor shall employ, at a minimum, generally accepted standards and practices utilized by persons engaged in providing services similar to those required of Contractor under this Contract.

8.2 Contractor shall keep itself informed of and comply with all applicable federal, state, and local laws, statutes, codes, ordinances, regulations, and rules in effect during the Term of this Contract. Contractor shall obtain any and all licenses, permits and authorizations necessary to perform the services set forth in this Contract, including any business licenses required by City. Neither City, nor any elected or appointed boards, officers, officials, employees, or agents of City, shall be liable, at law or in equity, as a result of any failure of Contractor to comply with this Section.

9.0 CONTRACTOR’S STATUS; CONTRACTOR’S EMPLOYEES

9.1 Contractor shall perform the services provided for herein in Contractor's own way as an independent contractor and in pursuit of Contractor's independent calling. Contractor is not to be considered an employee of City, nor shall any employees of Contractor be considered employees of City, for any purpose. Contractor shall be under the direction and control of City staff only as to the results to be accomplished. This Contract is not intended to create the relationship of partnership, joint venture, or association between City and Contractor.

9.2 Contractor represents and warrants that all professional services required under this Contract shall be provided by a person or persons duly licensed by the State of California to provide those types of services.

9.3 Neither Contractor, nor any of Contractor's officers, employees, or agents, shall obtain any rights to retirement, health care or any other benefits which may otherwise accrue to City’s employees. Contractor expressly waives any claim Contractor may have to any such rights.

9.4 Contractor is aware of the requirements of the Immigration Reform and Control Act of 1986 and shall comply with those requirements, including, but not limited to, verifying the eligibility for employment of all of Contractor’s officers, employees, agents, and subcontractors that are included in this Contract.

05/23/2023 C7 39 of 201

Professional Services (Non-Construction) (RFP)(NPW) 4 of 9 NAMEX [51960-2] 00051960 4

9.5 The payment made to Contractor pursuant to this Contract shall be the full and complete compensation to which Contractor and Contractor’s officers, employees, agents, and subcontractors are entitled for performance of any work under this contract. Neither Contractor nor Contractor’s officers or employees are entitled to any salary or wages, or retirement, health, leave or other fringe benefits applicable to employees of the City. City will not make any federal or state tax withholdings on behalf of Contractor. City shall not be required to pay any workers' compensation insurance on behalf of Contractor.

9.6 Contractor agrees to defend and indemnify City for any obligation, claim, suit, or demand for tax, retirement contribution including any contribution to the Public Employees Retirement System (PERS), social security, salary or wages, overtime payment, or workers' compensation payment which City may be required to make on behalf of Contractor or any employee of Contractor, or any employee of Contractor construed to be an employee of City, for work done under this contract. This is a continuing obligation that survives the termination of this Contract.

10.0 CIVIL RIGHTS

10.1 Contractor agrees to comply with Title VII of the Civil Rights Act of 1964, as amended, the California Fair Employment Practices Act, the Americans with Disabilities Act of 1990, any other applicable federal and state laws and regulations hereinafter enacted.

10.2 Contractor shall not knowingly deny an opportunity or benefit, discriminate against or harass, any employee or applicant for employment on account of the person’s race, color, ethnicity, national origin, ancestry, religion, creed, veteran status, physical disability, mental disability, medical condition, marital status, sex, sexual orientation, age, or other status protected from workplace discrimination by state or federal law.

10.3 Contractor shall not knowingly give preferential treatment to any applicant for employment on the basis of race, color, ethnicity, national origin, ancestry, religion, creed, physical disability, mental disability, medical condition, marital status, sex, or sexual orientation.

10.4 This section shall be interpreted in a manner that is consistent with the California and United States Constitutions and applicable state and federal statutes governing workplace discrimination. The terms used in this section shall have the same meaning as defined in state statutes governing the same subject matter.

10.5 Nothing in this section shall be interpreted as prohibiting bona fide occupational qualifications consistent with applicable state and federal law and reasonably necessary to the normal operation of Contractor. Nothing in this section shall be interpreted as prohibiting regulations and policies to prevent nepotism or conflicts of interest.

10.6 Nothing in this Section shall be interpreted as prohibiting action taken to establish or maintain eligibility for any federal program, where ineligibility would result in a loss of federal funds to City.

10.7 To the fullest extent permitted by law and without limitation by the other provisions of this Contract relating to indemnification and insurance, Contractor shall also indemnify, defend, and hold harmless City, and its directors, officers, employees, and agents from and against all liability (including without limitation all claims, damages, penalties, fines, and judgments, associated investigation and administrative expenses, and defense costs, 05/23/2023 C7 40 of 201

Professional Services (Non-Construction) (RFP)(NPW) 5 of 9 NAMEX [51960-2] 00051960 4
including but not limited to reasonable attorneys' fees, court costs, and costs of alternative dispute resolution) resulting from any claim of discrimination or harassment, including but not limited to sexual harassment, arising from the conduct of the Contractor or any of the Contractor’s officers, employees, agents, licensees, or subcontractors. In the event of a discrimination or harassment complaint against any employee, agent, licensee, or subcontractors of Contractor or its subcontractors, Contractor shall take immediate and appropriate action in response to such complaint, including, but not limited to termination or appropriate discipline of any responsible employee, agent, licensee, or subcontractors. The provisions of this Section survive completion of the services or termination of the Contract.

11.0 CONTROL OF SERVICES
Each Party shall appoint a representative who shall have the authority to represent and act for that Party (“Representative”). Any written or verbal directions or requests of City's Representative delivered to the Contractor’s Representative shall have the same force and effect as if delivered to the Contractor. The Contractor's Representative shall have the authority to sign any change order, coordinate the work of all subcontractors and make other decisions pertaining to the Contract.

12.0 ASSIGNMENT AND SUBCONSULTING

12.1 Neither this Contract nor any interest herein may be transferred, assigned, conveyed, hypothecated, or encumbered voluntarily or by operation of law, whether for the benefit of creditors or otherwise, without the prior written approval of the City. Transfers restricted hereunder shall include the transfer to any person or group of persons acting in concert of more than twenty-five (25%) of the present ownership and/or control of Contractor, taking all transfers into account on a cumulative basis. In the event of any such unapproved transfer, including any bankruptcy proceeding, this Contract shall be void. No approved transfer shall release the Contractor or any surety of Contractor of any liability hereunder without the express consent of City.

12.2 Contractor shall be fully responsible to the City for any acts and omissions of Contractor's subcontractor, including persons either directly or indirectly employed by subcontractor, in the event Contractor subcontracts any of the work to be performed under this contract. Contractor's responsibility under this paragraph shall be identical to Contractor's liability for acts and omissions of Contractor and employees of the Contractor. Nothing contained in this Contract shall create any contractual relationship between City and any subcontractor of Contractor, but Contractor shall bind every subcontractor and every subcontractor of a subcontractor by the terms of this contract applicable to Contractor's work, unless such change, omission, or addition is approved in advance in writing by the City Manager or the City Manager’s designee. All subcontractors are subject to the prior written review and approval of the City Manager or the City Manager’s designee.

13.0 LICENSES
If a license of any kind, which term is intended to include evidence of registration, is required of Contractor, its employees, agents, or subcontractors by federal, state, or local law, Contractor warrants that such license has been obtained, is valid and in good standing, and that any required bond has been posted in accordance with all applicable laws and regulations. 05/23/2023 C7 41 of 201

Professional Services (Non-Construction) (RFP)(NPW) 6 of 9 NAMEX [51960-2] 00051960 4

14.0 FINANCIAL RECORDS

14.1 Contractor shall maintain any and all documents, ledgers, books of account, invoices, vouchers, canceled checks, or records demonstrating or relating to Contractor’s performance of services pursuant to this Contract or evidencing or relating to expenditures and disbursements charged to City pursuant to this Contract. Any and all such documents or records shall be maintained in accordance with generally accepted accounting principles and shall be sufficiently complete and detailed so as to permit an accurate evaluation of the services provided by Contractor pursuant to this Contract. Any and all such documents or records shall be maintained for three years from the date of execution of this Contract and to the extent required by laws relating to audits of public agencies and their expenditures. It is expressly understood and agreed that the provisions of this Section will survive termination of this Contract.

14.2 Any and all records or documents required to be maintained pursuant to this Section shall be made available for inspection, audit and copying, at any time during regular business hours, upon request by City or its designated representative. Copies of such documents or records shall be provided directly to the City for inspection, audit and copying when it is practical to do so; otherwise, unless an alternative is mutually agreed upon, such documents and records shall be made available at Contractor's address indicated for receipt of notices in this Contract or the primary location from which services are rendered, whichever is closer.

15.0 OWNERSHIP OF DOCUMENTS
Upon delivery, the work product, including without limitation, all original reports, writings, recordings, drawings, files, and detailed calculations developed under this contract are the property of City. Contractor agrees that all copyrights which arise from creation of the work pursuant to this contract shall be vested in City and waives and relinquishes all claims to copyright or other intellectual property rights in favor of City. City acknowledges that its use of the work product is limited to the purposes contemplated by the scope of Services and that Contractor makes no representation of the suitability of the work product for use in or application to circumstances not contemplated by the scope of Services.

16.0 CONFIDENTIALITY

16.1 Contractor shall treat all information obtained from City in the performance of this Contract as confidential and proprietary to City. Contractor shall treat all records and work product prepared or maintained by Contractor in the performance of this Contract as confidential.

16.2 Contractor agrees that it will not use any information obtained as a consequence of the performance of work for any purpose other than fulfillment of Contractor’s scope of Services. Contractor will not disclose any information prepared for City, or obtained from City or obtained as a consequence of the performance of work to any person other than City, or its own employees, agents or subcontractors who have a need for the information for the performance of Services under this Contract unless such disclosure is specifically authorized in writing by City.

16.3 Contractor’s obligations under this paragraph shall survive the termination of this Contract.
05/23/2023 C7 42 of 201

Professional Services (Non-Construction) (RFP)(NPW) 7 of 9 NAMEX [51960-2] 00051960 4

17.0 CONFLICT OF INTEREST REQUIREMENT
Contractor agrees that, to the extent applicable, it shall comply with and be bound by all laws and regulations deriving from the relationship of the Contractor to the City, including the Political Reform Act (Government Codes Section 87100 et seq.) Chapters 2.32 or 2.33 of the Vista Municipal Code, the Community Redevelopment Act (Health & Safety Code 33000 et seq.) and all regulations promulgated thereunder (collectively “Conflict Laws”). As a condition precedent to the formation of this Contract, Contractor warrants and covenants that it is adequately informed regarding the obligations and duties imposed by the Conflict Laws and that to the best of Contractor's knowledge and belief, there exists no conflict of interest (under the laws) that would disqualify the Contractor from participation in any decisions arising out of the performance of this Contract. Prior to commencement of any work in the performance of this Contract, Contractor shall comply with any applicable requirements of Chapter 2.32 of the Vista Municipal Code, including any requirement to file a financial disclosure statement with the City Clerk.

Contractor further agrees that no employee, agent or subcontractor for Contractor shall perform any work for the City pursuant to this Contract which will violate the Conflict Laws.

18.0 PROHIBITION OF FINANCIAL INTEREST BY CITY OFFICIAL Contractor warrants and covenants to City that no City Official has or will have any current or future financial interest in this Contract as of the date approved, nor shall Contractor promise, offer, or enter into any written, oral or implied Contract, to provide any financial interest or remuneration of any kind or manner to any City official with respect to this Contract. For purposes of this Section, the term “City Official” shall mean and include any elected or appointed officer of City, any employee of City, or any spouse or financial dependent of a City official or employee. A violation of this provision shall render this Contract null and void and Contractor shall be subject to restitution of all fees or money paid or earned under this Contract.

19.0 DUTY OF INDEMNIFICATION

19.1 To the fullest extent permitted by law, Contractor shall (1) immediately defend and (2) indemnify City, and its directors, officers, and employees from and against all liabilities regardless of nature or type that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor, or its employees, agents, or subcontractors.

Liabilities subject to the duties to defend and indemnify include, without limitation, all claims, losses, damages, penalties, fines, and judgments; associated investigation and administrative expenses; defense costs, including but not limited to reasonable attorneys’ fees; court costs; and costs of alternative dispute resolution (“Duty of Indemnification”). Contractor’s obligations to both defend and indemnify apply unless it is finally adjudicated that the liability or liabilities, in whole or in part, do not arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor or its employees, agents, or subcontractors. Defense counsel shall be approved by City.

19.2 The review, acceptance or approval of Contractor’s work or work product by any indemnified party shall not affect, relieve, or reduce Contractor’s indemnification or defense obligations. This Section survives completion of the services or the termination of this contract.

The provisions of this Section are not limited by and do not affect the provisions of this contract relating to insurance.

19.3 Contractor’s costs of defense shall not exceed Contractor’s proportionate percentage of fault as adjudicated by a court of law, as required by California Civil Code section 2782.8.
05/23/2023 C7 43 of 201

Professional Services (Non-Construction) (RFP)(NPW) 8 of 9 NAMEX [51960-2] 00051960 4

20.0 INSURANCE AND BONDS
Contractor shall comply with the insurance provisions set forth in Exhibit C.

21.0 SERVICE OF NOTICE

21.1 Any notice, which either Party may desire to give to the other Party, must be in writing and may be given by personal delivery to the Party’s Representative or by overnight courier service to the Party’s address set forth in Section 1.0. Notice may also be given by mailing it by registered or certified mail, return receipt requested, to the other Party at the address set forth in Section 1.0. Any notice given by mail will be deemed given 48 hours after such notice is deposited in the United States mail, addressed as provided with postage fully prepaid.

21.2 A Party may change its address by giving notice as provided above, and the changed address shall thereafter be deemed to be the address set forth in Section 1.0.

22.0 SPECIAL PROVISIONS
This Contract is subject to, and Contractor shall comply with, the special provisions referenced in Exhibit E, if any.

23.0 EXHIBITS
All documents referenced as exhibits in this Contract, or referenced in an exhibit to this Contract, are incorporated herein.

24.0 APPLICABLE LAW, VENUE
This Contract shall be construed and enforced under the laws of the State of California. If any action is commenced by any Party to this Contract, such action shall be filed in a court of competent jurisdiction within the County of San Diego, California.

25.0 COUNTERPARTS; ELECTRONIC SIGNATURES; ELECTRONIC DELIVERY This Agreement may be executed in separate counterparts, none of which need contain the signatures of both Parties, and each of which, when so executed, shall be deemed an original and all together shall constitute and be one of the same instrument. The Parties agree that this Agreement, whether executed by electronic signature, digital signature, or constituting a scanned or electronically reproduced copy or image of this Agreement bearing the signatures of the Parties, will be deemed an original and will represent competent evidence of the execution, terms and existence of this Agreement notwithstanding the failure or inability to produce an original executed Agreement or counterpart thereof, and without the requirement that the unavailability of such original executed Agreement or counterpart thereof first be proven.

Further, the exchange of this entire executed Agreement (and/or such exhibit(s) or document(s)) that is in photostatic or portable document format (.pdf) form by electronic mail or by another electronic means shall be considered original(s) and shall constitute effective execution and delivery of the original(s).

26.0 MODIFICATIONS
This Contract contains the entire agreement, between the Parties and supersedes all prior negotiations, discussions, obligations, and rights of the Parties in respect of each other regarding the subject matter of this Contract. There is no other written or oral understanding 05/23/2023 C7 44 of 201

Professional Services (Non-Construction) (RFP)(NPW) 9 of 9 NAMEX [51960-2] 00051960 4
between the Parties. No modification, amendment or alteration of this Contract shall be valid unless it is in writing and signed by all Parties.

[Continued on page 9.]

27.0 EXECUTION
IN WITNESS WHEREOF; the Parties hereto have executed this Contract as of the Contract Date.

“City”

CITY OF VISTA, a chartered municipal
corporation

By:

PATRICK JOHNSON, CITY MANAGER

JUDYRITTER, MAYOR

ATTEST:

KATHY VALDEZ, CITY CLERK

By:

APPROVED AS TO FORM:

WALTER CHUNG, ACTING CITY ATTORNEY

By:

RISK MANAGEMENT REVIEW:

DOLORES GASCON, RISK MANAGER

By:

“Contractor”

NAMEX, statusx

By:

Name/Title

By:

Name/Title

05/23/2023 C7 45 of 201

00051960 4 Exhibit B

EXHIBIT B
CONTRACTOR’S PROPOSAL

05/23/2023 C7 46 of 201

ASSOCIATESASSOCIATESASSOCIATESASSOCIATES

CITY OF VISTA
(CIP NO. 8290)NEVADA AND LEMON

PEDESTRIAN MOBILITY SIDEWALKS
PROPOSAL February 23, 2023 • 4:00 PM
05/23/2023 C7 47 of 201

p / 1CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
CRA P#2023.019
Attention: Gabe Grewe, Capital Projects Manager
City of Vista
200 Civic Center Dr., Vista, CA 92084
February 23, 2023
Dear Mr. Grewe and Members of the Selection Committee:

The Nevada and Lemon Pedestrian Mobility Sidewalk project is a great opportunity for the City of Vista to use CDBG funds to build a stronger and more resilient community by constructing infrastructure that will improve accessibility for non-motorized users. CR Associates (CRA) has years of experience planning and designing projects that include pedestrian, green infrastructure and stormwater quality improvements. We are excited to team with the City to complete these improvements in the City of Vista; working with us will provide the following benefits to the project:

Experience with Similar Accessibility Projects. CRA staff has designed multiple sidewalk improvement projects with similar challenges: limited right-of-way, steep elevations, stormwater management, non-ADA compliant driveways, private encroachments in public right-of-way, and lack of existing infrastructure. Our past experience brings an array of solutions that can be applied to successfully deliver this project.

Team of Experts. We have assembled a dedicated team for this project with a history of delivering for the City and working collaboratively on similar projects. Our proficient in-house design team has successfully provided design services for similar type of projects for many local agencies. We appreciate the opportunity to present our qualifications and look forward to providing our services to the City of Vista.

Experienced and Responsive Project Manager. Mobility projects are my passion. Over the last eight years, I have worked almost exclusively as a project manager providing preliminary design, environmental, final design, and construction period services for green street projects in Southern California. As project manager, I will be your point of contact during the delivery of this project, ensuring the overall quality and timeliness of all project deliverables. I pride myself on my responsiveness to client needs and encourage you to contact our references to learn firsthand about the attention and quality you will receive working with our team.

Thanks for your consideration and we look forward to establishing a fruitful relationship with the City. Matt Capuzzi, the Principal-In-Charge for this team, is the authorized signer for this proposal.

Sincerely,

CR ASSOCIATES

Roberto Ruiz-Salas PE Matt Capuzzi PE
Project Manager Principal-In-Charge
RE: Nevada and Lemon Pedestrian Mobility Sidewalks (CIP No. 8290) 3900 5th Avenue, Suite # 310 • San Diego, CA 92103 • www.cramobility.com

1. Cover Letter
CR Associates has reviewed
the City’s Standard
Agreement and has no
exceptions to the terms
therein.
05/23/2023 C7 48 of 201

Section 2.

Statement of
Qualifications
05/23/2023 C7 49 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
CRA P#2023.019
p / 3
Section 1: Statement of Qualifications

FIRM AND TEAM QUALIFICATIONS
CR Associates (CRA) is recognized as a local industry leader providing transportation engineering design services and transportation planning to a variety of public agencies. We continue to apply our expertise to a wide range of transportation projects throughout the Southern California Region and beyond, including innovative pedestrian and bicycle projects, Complete and Green Streets projects, traffic calming projects, and roadway and intersection design.

CRA was founded in 2011, as a woman-owned business that focuses on delivering high quality transportation projects for local agencies and communities in Southern California. Today, we have two offices in downtown San Diego and Los Angeles with 40+ professionals. To date, our staff has planned and designed 30+ active transportation projects.

CRA staff are inspired to provide clients with innovative, high-quality, and cost-effective services, and are dedicated to keeping projects on schedule and within budget.

For this project, we are teaming with local experts in their respective disciplines: Tory R. Walker Engineering (stormwater design), Gold Coast Surveying, Inc. (GCSI) (surveying), Leighton (Geotech), and Underground Solutions (potholing).

Tory and his team have a long history of working with the City and provide a deep understanding of the City’s stormwater system, regulations, and requirements. GCSI have previously completed an aerial survey of the project area and will perform the field survey that will serve as the base for the design. Leighton and Underground Solutions have been long-time partners with CRA and have worked in this region for many years on similar projects.

YOUR TEAM OF EXPERTS
Our staff has years of experience, not only delivering
roadway and pedestrian design, but also in advancing
projects through preliminary into final design, and then construction. We know full well the relentless attention to detail and deep understanding of the existing conditions that will be needed to make this project a success.

We have put together a local team that has experienced
in delivering projects that include sidewalk design, curb ramps, and stormwater quality design. Our organizational chart (see page 4) identifies the key staff members
needed to complete the scope of work for this project
and defines relationships between the disciplines and task leads. Each staff member was selected based on their
capability to perform the high quality work needed within the project schedule.

We thoroughly understand local laws, ordinances,
regulations, policies, requirements, and permitting
procedures—which means you can rest easy knowing
we don’t cut corners and we get it done right. You
will also see the resumes of our key personnel on the
following pages.

EXPERIENCED PROJECT MANAGER
Roberto Ruiz-Salas, PE, our project manager, brings 14
years designing and managing transportation and public
works projects. He has experience managing multi-
disciplined public works projects from the preliminary
conceptual phase through construction.

He has designed and constructed over 16 miles of
pedestrian and bicycle facilities in the last eight years, including three corridors with similar challenges to those we anticipate along Nevada and Lemon.

Roberto will be your primary point of contact for this
project. He will oversee and be involved in every phase of the project, and will be supported by our in-house staff and subconsultants that are experts in their disciplines and will partner with the City to deliver this project.

We have analyzed our current workload and determined
the proposed staff can be readily available for this project.

Additional staff will be assigned if needed.

WHY CHOOSE THE CRA TEAM?
A team of professionals located entirely within Southern California Engineers and surveyors who have designed over $250M in mobility improvements over the last five years Key staff with significant ADA accessibility planning and design experience; with years of experience delivering projects for multiple public works departments in the region A project manager with a successful track record of completing multi-disciplined pedestrian improvement projects 05/23/2023 C7 50 of 201

p / 4CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
City of Vista

PRINCIPAL-IN-CHARGE
Matt Capuzzi, PE

PROJECT MANAGER
Roberto Ruiz-Salas, PE

QA/QC MANAGER
Ross Duenas, PE
* Tory R. Walker Engineering / Bold = Key Personnel / % = Availability

GEOTECH
Leighton

SURVEYING
Gold Coast Surveying, Inc.

UTILITY POTHOLING
Underground Solutions
Roberto Ruiz-Salas, PE
Blanca Soto, PE
Hailey Tyson, PE

CIVIL ENGINEERING STORMWATER DESIGN
/ WATER QUALITY
Tory R. Walker, PE CFM *
Bryan Hill, PE, QSD *
Scott Cartwright, PE

PAVEMENT ASSESSMENT
Aryo Rad, PE
Tomo Takahashi, PE
Tyler Rausch, EIT

TRAFFIC ENGINEERINGUTILITY COORDINATION
Roberto Ruiz-Salas, PE
Resumes
On the following pages, we showcase our team’s credentials, qualifications, and most relevant experience.

We have assembled a comprehensive team to meet every need of the City.

Organizational Chart

FINANCIAL RESPONSIBILITY
Our internal fiscal responsibility is supported by the
tools that we employ for our accounting and project
management systems. CRA uses the interactive web-
based management system, Ajera, to manage and
track all the financial aspects of the company. Ajera
fully integrates time entry, accounting, and project
management so data flows seamlessly and is updated in
real-time.

Our project managers use Ajera to successfully maintain control of a project budget by providing real-time
status reports on performance, variances, forecasts,
and expenditures for all project tasks. Our Accounting
staff utilize it for accounts payable, accounts receivable, billings and financial statement reporting.

We also feel a sense of external fiscal responsibility
in how we use public funds. We work closely with our
municipal clients to effectively utilize available project budget. Our diverse cross-trained staff ensure that
project tasks are performed by responsible individuals
with the appropriate level of experience. We understand that construction and long-term maintenance costs far
outweigh design costs, and we have a proven history of
creative value engineering solutions that provide cost
savings to the Client.
65%
45%
55%
15%10%
20%
30%
20%
05/23/2023 C7 51 of 201

p / 5CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Roberto is a civil engineer with 14 years of experience providing engineering consulting services to local municipalities to develop their capital improvement projects, including multimodal transportation and public utilities design. Over the last eight years he has been responsible for managing private and public-works projects that include various disciplines and multiple subconsultants. He has been the lead engineer for numerous projects specializing in sidewalks, roadway, municipal parks, water quality, site grading, roundabouts, signing and striping, bicycle facilities, and utility design, as well as surface water hydrology, open channel hydraulics, and hydrologic and hydraulic computer modeling. Roberto has extensive experience working with Southern California agencies and is familiar with local design guidelines.

RELEVANT PROJECT EXPERIENCE
Sidewalk Repair Program, Los Angeles, CA. - Roberto is the lead Senior Engineer for a multi-year citywide program to replace non-ADA compliant sidewalks and curb ramps.

The project requires complex design for the construction of ADA compliant facilities in a built urban environment with minimal impact to site drainage. *El Toyon Las Palmas, City of National City, CA. - Project manager who provided the City of National City grant writing, planning, environmental, stakeholder coordination, and design services to construct a bicycle boulevard that traveled National City north to south parallel to interstate 805. The project included 2,650 linear feet of sidewalk design with multiple residential driveways. The project required a Caltrans encroachment permit at four locations, and the completion of three Design Deviation Forms. *Heffernan sidewalk improvements, Heber, CA. - Roberto was the Project manager and lead design for a project with the Imperial County Public Works to construct 3,400 linear feet of sidewalk in Heber, CA surrounding Heber Elementary. The project included the design of eight residential driveways and designing stormwater conveyance solutions.

Roberto and his team assisted the City in providing an ADA compliant path for students to travel to school in the rural community.
*Market and Euclid Complete Streets, San Diego, CA. - Project manager for the design of a project that constructed over 6,000 linear feet of pedestrian and bicycle facilities for the City of San Diego. The project included sidewalk widening, bulb-outs, retaining wall design, ADA driveway design, traffic signal modifications, stormwater quality BMPs, and water and sewer line replacement. Roberto led coordination with multiple City departments, as well as public outreach, utility coordination, and support during construction.
*Safe Routes to School, City of National City, CA. - Project engineer who provided the City of National City grant writing, planning, environmental and design services for a citywide project that included the reconstruction of over 60 curb ramp and ADA improvements near National City schools, as well as a neighborhood traffic circle and traffic calming improvements adjacent to Las Palmas Park and Las Palmas Elementary School.

EXPERIENCE
14 years

EDUCATION
BS, Civil Engineering,
California Polytechnic State
University, San Luis Obispo

ACCREDITATION
Professional Engineer,
California #81946

AFFILIATIONS
American Public Works
Association (APWA) -
member
American Society of
Civil Engineers (ASCE) -
member
Roberto Ruiz-Salas PE
Project Manager
* Prior to joining CRA.
65%

AVAILABILITY
05/23/2023 C7 52 of 201

p / 6CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Matt Capuzzi’s experience has focused on designing and managing transportation projects for public agencies. He has designed multi-disciplinary projects involving multi-modal Complete Streets and Green Streets, bikeways, traffic calming, and outdoor recreation spaces. Matt’s responsibilities include oversight of grading, improvement, and traffic plan preparation, roadway design, traffic engineering, stormwater analysis and design, wet utility design, and water quality.

RELEVANT PROJECT EXPERIENCE
Village and Barrio Traffic Circles, City of Carlsbad, Carlsbad, CA. - Project manager leading the team for the Carlsbad Village and Barrio Traffic Circles recently completed the preliminary design phase of this project. Matt is now leading the project toward the final construction documents, speci¬fications, and estimates for seven intersections that include five traffic circles and two traffic calming treatments within the Village and Barrio.

The design includes bike network enhancements, street light improvements, landscape and irrigation improvements, and a decorative art display within two of the traffic circles.

Park Boulevard Bikeway – PA/ED and PS&E, SANDAG, San Diego, CA. - Project manager leading a team providing civil and traffic engineering preliminary and final design services that will construct a segment of the regional bike network along Park Boulevard. The addition of this missing segment will complete the Park Boulevard Bikeway that connects to the Eastern Hillcrest Bikeways and North Park – Mid-City Bikeways. One of the key project features is a protected intersection that will allow for safe movement for people riding bikes as they negotiate a busy five-leg intersection.

University Bikeway, SANDAG, San Diego, CA. - Project manager currently leading the PS&E phase of this project. This 2.9-mile urban bikeway runs through the Mid-City and Eastern neighborhoods of San Diego, ultimately connecting to the City of La Mesa at its eastern terminus. Proposed improvements include protected bikeways (Class IV), bus islands to eliminate bus/bike conflicts, a protected intersection, fully protected bike movements at signalized intersections, two-stage left-turn queue boxes, enhanced mid- block pedestrian crossings, the re-purposing of travel lanes, and innovative use of floating islands to slow side street turning movements.

Leucadia Boulevard Roundabout, City of Encinitas, Encinitas, CA. - Principal-in-charge overseeing the design of a modern roundabout along Leucadia Boulevard at Hygeia Avenue. The project includes the construction of LID design features, decorative retaining walls to protect existing utilities and provide screening for the adjacent properties, street lighting, and landscape and irrigation improvements. The design also includes drainage upgrades to resolve existing flood control issues and the introduction of roadside water quality BMPs to improve storm water quality. The precise grading design was particularly challenging due to the steep slopes on two of the four intersection approaches and the shallow depth of various utility lines.

EXPERIENCE
22 years

EDUCATION
BS Civil Engineering,
Villanova University

ACCREDITATION
Professional Engineer,
California #69815

AFFILIATIONS
Women’s Transportation
Seminar (WTS), Member
American Public Works
Association (APWA),
Member
Association of Pedestrian
and Bicycle Professional
(APBP), Member
Matt Capuzzi PE
Principal-In-Charge
05/23/2023 C7 53 of 201

p / 7CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Ross Duenas has 18 years of experience designing and managing transportation and public works projects for public agencies. He has managed multi-disciplinary projects involving multimodal Complete Streets, traffic control, traffic calming, and large outdoor pedestrian spaces. Ross’ responsibilities have included managing traffic-related improvement projects, designing, and preparing traffic control plans, as well as signing and striping plans, roadway design, site design, stormwater analysis and design, wet utility design, and water quality.

RELEVANT PROJECT EXPERIENCE
Leucadia Boulevard Roundabout, City of Encinitas, Encinitas, CA. - Project manager leading the design of a modern roundabout along Leucadia Boulevard at Hygeia Avenue.

The project includes the construction of LID design features, decorative retaining walls to protect existing utilities and provide screening for the adjacent properties, street lighting, and landscape and irrigation improvements. The design also includes drainage upgrades to resolve existing flood control issues and the introduction of roadside water quality BMPs to improve storm water quality. The precise grading design was particularly challenging due to the steep slopes on two of the four intersection approaches and the shallow depth of various utility lines.

El Cajon Boulevard Roundabout/Streetscape, City of El Cajon, El Cajon, CA. - Project manager for the design of an innovative roundabout at the El Cajon Boulevard/Johnson Avenue intersection and a road diet and streets¬cape enhancements along El Cajon Boulevard to foster the revitalization of an urban village along the boulevard. The project will replace the existing five-leg signalized intersection with a modern roundabout, thus increasing safety and traffic calming at the intersection.

Main Street Green Street, City of El Cajon, El Cajon, CA. - QA/QC Manager for the revitalization of the Main Street corridor by implementing enhanced sidewalks, Class IV separated bikeways, LID planters, signage, thematic site furnishings, and lighting. These improvements will effectively extend the El Cajon transit center’s mobility hub and active transportation connections to nearby health care offices, schools, social services, and neighborhoods. The project includes Green Infrastructure BMPs strategically sized and located to minimize impacts to existing utilities while still complying with regional MS4 Permit requirements.

Jamacha Road Safety Improvements, City of El Cajon, El Cajon, CA. - Project manager who partnered with the City of El Cajon to prepare a successful HSIP Cycle 9 application and is currently leading the PS&E effort. The project includes both vehicular and pedestrian safety countermeasures along this primary thoroughfare: pedestrian crossing improvements at signalized intersections, raised medians, and enhanced pedestrian crossings. In addition to the proposed safety improvements the project will also be a “Green Street” by reducing the impervious area within the areas of work to reduce the corridors storm water impacts on the existing drainage infrastructure.

EXPERIENCE
18 years

EDUCATION
BS, Civil Engineering,
Florida State University

ACCREDITATION
Professional Engineer,
California #84324

AFFILIATIONS
American Public Works
Association (APWA),
Member
Ross Duenas PE
QC/QA Manager
05/23/2023 C7 54 of 201

p / 8CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019

EXPERIENCE
25 years

EDUCATION
MS, Civil Engineering,
California State University,
Fullerton
MS, Systems Engineering,
Industrial Management
Institute, Tehran

ACCREDITATION
Professional Engineer,
California #C81231
Qualified SWPPP
Developer/Practitioner,
California #81231

AFFILIATIONS
American Public Works
Association (APWA),
Southern California
Chapter
AWARDS
American Society of Civil
Engineers
American Public Works
Association
American Association
of State Highway and
Transportation Officials
Aryo Rad brings more than two decades of civil engineering experience in the areas of con- structing roadways, streetscapes, pedestrian facilities, storm drains, traffic, bikeways, and transportation projects in Southern California. He has a successful track record of leading complex multidisciplinary transportation and streetscape projects.

He has worked with public works and planning departments for more than 30 regional municipalities, assisting with roadway improvement and pavement rehabilitation projects.

Aryo is familiar with the challenges surrounding mobility and roadway projects through his experience working on identical projects.

RELEVANT PROJECT EXPERIENCE
Main Street Green Street – Phase 1 Improvements, City of El Cajon, El Cajon, CA. - QA/QC manager for the revitalization of the Main Street corridor, which will become an attractive multimodal gateway. CR Associates (CRA) is finalizing the design to implement a road diet and vehicle lane narrowing in order to install enhanced sidewalks and access ramps, Class IV separated bikeways, enhanced pedestrian crossings, LID planters, signage, thematic site furnishings, and safety lighting.

Jamacha Road Improvements (HSIP), City of El Cajon, El Cajon, CA. - Technical advisor for this proposed project, which is part of Caltrans Highway Safety Improvement Program (HSIP) Cycle 9. Proposed improvements include median nose modification, high visibility crosswalks, curb extensions, center raised medians, ADA improvements, traffic signal modifications, RRFB crossings, bulb-outs, and bike lane improvements.

South Main Street Corridor Improvements, City of Santa Ana, Santa Ana, CA.* - Project manager responsible for the development and implementation of a downtown revitalization plan that focuses on improving street beautification, traffic safety, walkability, environmental sustainability, security, and neighborhood amenities. The project involved creating solutions for street beautification, traffic safety, walkability, bike circulation, environmental sustainability, and neighborhood amenities.

Ramona Boulevard Street Resurfacing (STPL), City of El Monte, El Monte, CA.* - Project manager for street improvement project that included a Class III bike route along Ramona Boulevard, from Peck Road to east city limit, for more than 1 mile of arterial corridor. Project elements consisted of pavement evaluation, pavement rehabilitation alternatives, ADA improvements, new median islands, right-of-way acquisition, utility coordination, low impact design, and stakeholder engagement. * Prior to joining CRA.

Aryo Rad PE
Pavement Assessment
15%

AVAILABILITY
05/23/2023 C7 55 of 201

p / 9CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Tory R. Walker has over 36 years’ experience in surface water management, providing services to both public and private entities. He’s conducted thousands of hydrologic studies, including preparation of regional drainage master plans and hydrologic model calibrations and has analyzed and designed numerous hydraulic structures, including stream stabilization structures, embankments, channels, culverts, and detention, retention, and debris basins. Tory has conducted numerous floodplain studies for natural and urban stream systems, which have included sediment transport analysis, bridge scour analysis, floodway encroachment and unsteady flow analysis.

RELEVANT PROJECT EXPERIENCE
SOUTH SANTA FE REDEVELOPMENT DRAINAGE PROJECT - VISTA, CA. - Mr. Walker managed this $800,000 drainage design project for the City of Vista, which incorporates the Buena Vista Creek studies prepared under his supervision. He managed a team of sub-consultants and his own staff on this vital City project. Project elements include final hydrologic studies and hydraulic design of the South Santa Fe Avenue drainage system, utility coordination, geotechnical exploration, environmental permitting and mitigation, regular project team meetings and City meetings, preparation of construction documents, agency coordination and conducting public meetings for a City skate park. Upon completion of construction he oversaw the preparation and processing of a LOMR application that now removes this downtown redevelopment area from the FEMA floodplain.

VISTA PROFESSIONAL DEVELOPMENT REVIEW SERVICES - VISTA, CA. - Mr. Walker is overseeing the professional development review services contract with the City of Vista. These services relate to hydrology and hydraulic studies and water quality technical reports, ensuring conformance between submitted reports and plans as well as conformance to regulatory requirements.

SOUTH SANTA FE STREETSCAPE PROJECT - VISTA, CA. - Mr. Walker managed all aspects of this important revitalization project in the South Santa Fe Corridor of Vista, which was also selected as the APWA 2021 Project of the Year in the Sustainable/Green category. The South Santa Fe Streetscape Project (also known as the Paseo Santa Fe Corridor) is an ongoing redevelopment of the South Santa Fe urban corridor. Extensive streetscape upgrades are underway with enhanced pedestrian-friendly designs, street furniture, trees, traffic calming, and decorative pavers. TRWE provided hydrologic, hydraulic, and stormwater design, and assisted the design team and City staff with water quality designs, reports, and state grant backup. Extensive trunk and lateral storm drain designs, retrofit drainage designs for existing facilities, and stormwater provisions were all provided for the design team and the City. Extensive coordination with other consultants and City staff was required in the effort, due to multiple utility and existing roadway constraints and design issues.

EXPERIENCE
36 years

EDUCATION
B.S. Civil Engineering,
University of California,
Irvine
B.A., Engineering-Physics,
Westmont College,
Santa Barbara, California

ACCREDITATION
Registered Civil Engineer,
California (No. 45005)
Registered Civil,
Environmental Engineer,
Oregon (No. 16313)
Registered Civil Engineer,
Washington (No. 29503)
Certified Floodplain
Manager (No.US-08-03678)
Certified Water Right
Examiner, Oregon (No.
344)
IGP Qualified Industrial
Stormwater Practitioner

AFFILIATIONS
American Society of
Civil Engineers
Floodplain Management
Association
International Erosion
Control
American Public Works
Association
Tory R. Walker PE, CFM, QISP
Sr. Stormwater Quality Manager
10%

AVAILABILITY
05/23/2023 C7 56 of 201

p / 10CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Mr. Hill has nearly 20 years of experience in civil engineering design in Southern Califor- nia,with an emphasis on storm water management and mitigation. He has worked primarily inprivate development, managing storm water analysis and design on dozens of projects, fromconcept to completion. Project analysis typically includes hydrologic and hydraulic study,peak flow detention routing, and continuous simulation hydromodification analysis usingEPA SWMM.

RELEVANT PROJECT EXPERIENCE
CENTRUM RESIDENTIAL APARTMENTS - SAN DIEGO, CA. - Provided project support and design for storm drain and storm water mitigation systems for multiple phases of discretionary and finalengineering process of this high density redevelopment project. Design efforts included regional public storm drain systems,biofiltration planters, underground detention systems, and proprietary biofiltration systems, all in conformance with underlying masterdrainage plan documents. All phases of planning and development included Storm Water Quality Management Plan (SWQMP) andDrainage Study preparation and oversight.

NORTH CITY EAST - SAN MARCOS, CA. - Provided project support, Drainage Study preparation and oversight, and design for storm drain and storm water mitigation systemsfor multiple phases of discretionary and final engineering process of this high density mixed-use project. Initial efforts involved masterplanning drainage analysis of the approximately 150 acre University District Specific Plan area. Design efforts included regional publicstorm drain systems, biofiltration planters, underground detention systems, and proprietary biofiltration systems, all in conformancewith the underlying master planning documents. Particular focus was placed on developing an innovative biofiltration system design,in collaboration with the City of San Marcos, to address water quality, hydromodification, and peak flow mitigation within a limitedfootprint in the public right-of-way. All phases of planning and development included Storm Water Quality Management Plan(SWQMP) and Drainage Study preparation and oversight.

CALIFORNIA STATE UNIVERSITY SAN MARCOS (CSUSM) EXTENDED LEARNING BUILDING - SAN MARCOS, CA. - The CSUSM Extended Learning Building is an off-campus extension of CSUSM, that includes a pedestrian bridge to provide seamlessconnectivity with the main campus. The building is the first academic building in California developed through a public-privatepartnership that required no additional state funds for design and construction. Project efforts included Storm Water QualityManagement Plan (SWQMP) and Drainage Study preparation, and design of biofiltration planters, underground detention systems,and proprietary biofiltration systems.

EXPERIENCE
20 years

EDUCATION
B.S., Mechanical
Engineering, SanDiego
State University, San Diego

ACCREDITATION
Registered Civil Engineer,-
California (No. C69339)

QSD (No. C69339)
Bryan Hill PE, QSD
Stormwater Quality Manager
20%

AVAILABILITY
05/23/2023 C7 57 of 201

p / 11CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Scott Cartwright has served as lead engineer or project manager for a wide variety of public street and infrastructure improvement projects. He specializes in storm water management addressing flood control, water quality, and hydromodification management. Scott’s ability to guide projects from planning to design and through construction brings a critical per- spective for cost effective solutions.

Scott specializes in stormwater management addressing flood control, water quality, and hydromodification management—including for roundabouts. His ability to guide projects from planning to design and through construction brings a critical perspective for cost-ef- fective solutions.

RELEVANT PROJECT EXPERIENCE
Main Street Green Street, City of El Cajon, El Cajon, CA. - Project manager for the revitalization of the Main Street corridor by implementing enhanced sidewalks, Class IV separated bikeways, LID planters, signage, thematic site furnishings, and lighting. These improvements will effectively extend the El Cajon transit center’s mobility hub and active transportation connections to nearby health care offices, schools, social services, and neighborhoods. The project includes Green Infrastructure BMPs strategically sized and located to minimize impacts to existing utilities while still complying with regional MS4 Permit requirements.

Connect Main Street Phases 1-3, City of Lemon Grove, Lemon Grove, CA. - Project manager for Phases I-III of Connect Main Street that provides a continuous ADA accessible trail, at times paralleled by a multi-use path. To accommodate these facilities, a portion of Main Street will be closed (Davidson to Buena Vista) and another converted to one-way (Burnell to San Miguel). Phases I-III also include custom designed gateway structures, interpretive panels, exercise stations, and a community garden, all based on the thematic time periods developed as part of the initial planning efforts. To further enhance the corridor, lighting, drainage, water quality, signing & striping, signal modifications, and parking improvements are also included.

El Cajon Boulevard Streetscape, City of El Cajon, El Cajon, CA. - Deputy project manager and stormwater management lead for the design of an innovative roundabout at the El Cajon Boulevard/ Johnson Avenue intersection and a road diet and streetscape enhancements along El Cajon Boulevard to foster the revitalization of an urban village along the boulevard. The project will replace the existing five-leg signalized intersection with a modern roundabout, thus increasing safety and traffic calming at the intersection.

Village and Barrio Traffic Circles, City of Carlsbad, Carlsbad, CA. - Drainage lead for the design of five traffic circles to provide traffic calming and beautification in the Barrio.

The project includes an initial feasibility analysis as well as final PS&E. Scott developed a hydrology and hydraulics report to support the design and retrofit of a storm drain infrastructure. The project includes green infrastructure BMPs to collect and infiltrate storm water runoff in accordance the local MS4 Permit requirements.

EXPERIENCE
17 years

EDUCATION
BS, Civil Engineering,
Brigham Young University

ACCREDITATION
Professional Engineer,
California #77512

AFFILIATIONS
American Public Works
Association (APWA), Chair
of the Transportation
Committee
Scott Cartwright PE
Stormwater/Water Quality Engineer
30%

AVAILABILITY
05/23/2023 C7 58 of 201

p / 12CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Tomo Takahashi’s technical expertise includes design for traffic signals, lighting, ITS, signing and striping, and temporary traffic control. He has been involved in a variety of traffic design projects, including but not limited to bikeways, roundabouts, traffic circles, ADA upgrades, and signal interconnect systems. Tomo has led the traffic design efforts for projects, throughout Southern California, of all magnitudes, from large freeway design-builds to localized curb ramp improvements. He has facilitated various coordination and technical meetings, working directly with contractors, agencies, and other consultants.

RELEVANT PROJECT EXPERIENCE
Bayshore Bikeway Barrio Logan Segment, SANDAG, San Diego, CA. - Traffic engineering lead for this proposed Class I bikeway along Harbor Drive, including six traffic signal modifications. These improvements will significantly enhance the safety of this multi-use corridor. This project successfully developed and processed a “Request for Experimentation” through the CTCDC and FHWA to test the novel application of flashing indicators to enhance bicyclist safety at signalized intersections.

University Bikeway, SANDAG, San Diego, CA. - Senior traffic engineer providing design oversight for 10 traffic signal modifications, which includes implementing new bicycle signals, bike signal indications, providing protected bicycle movements, and updating signals to meet current ADA standards. Tomo is also providing oversight for the striping design along the entire corridor. The University Avenue Bikeway Project plans to implement Class IV bike lanes and enhanced bus islands along 2.8 miles of University Avenue. The project also includes a new signal to provide connectivity to the City’s bike network and rectangular rapid flashing beacon (RRFB) for a mid-block crossing.

Main Street Green Street, City of El Cajon, El Cajon, CA. - Traffic design lead for the modification of three signals, a new rectangular rapid flashing beacon (RRFB) mid- block crossing, signing and striping, and decorative lighting. Main Street is the primary access from the El Cajon transit center to downtown El Cajon. To revitalize the corridor into an attractive multi-modal gateway, CR Associates is currently leading the design to implement a road diet and vehicle lane narrowing to implement pedestrian and bicycle safety enhancements including widened sidewalks, Class IV separated bikeways, LID planting, striping and signage improvements, thematic site furnishings, and decorative lighting.

Leucadia Blvd Streetscape Ph 2, City of Encinitas, Encinitas, CA. - Senior traffic engineer who is currently leading the traffic engineering and lighting design for this modern roundabout in Encinitas at Hygeia Avenue. The proposed striping was designed to blend with the existing roundabout on each side of Hygeia Avenue to create an integrated corridor along Leucadia Boulevard. Additionally, the striping design will provide an increase of on-street parking and buffered bike lanes along the roadway approaches. The proposed lighting design will incorporate the use of the same lighting standard that has been previously installed along the corridor, and was modeled to balance the neighborhood’s preference for limited street lighting with the safety needs of pedestrians and vehicles at the roundabout.

EXPERIENCE
16 years

EDUCATION
BS, Civil Engineering,
Arizona State

ACCREDITATION
Professional Engineer,
California #81522
Professional Engineer,
Arizona #73374
Tomo Takahashi PE
Sr. Traffic Engineer
20%

AVAILABILITY
05/23/2023 C7 59 of 201

p / 13CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
Blanca Soto assists project managers in the transportation and traffic department. Her ex- perience includes designing and preparing street improvement plans, traffic control plans, signing and striping plans, and traffic signal plans.

Blanca brings nine years of designing and preparing street improvement plans, traffic con- trol plans, signing and striping plans, and traffic signal plans—all in San Diego County. She worked extensively on the Coast Highway roundabouts and sidewalk improvements that are currently in construction in Leucadia.

RELEVANT PROJECT EXPERIENCE
College Boulevard Improvement Project, City of Oceanside, CA. - Project Engineer.

College Boulevard improvements start at the intersection of Waring Road and College Boulevard and end at the intersection Old Grove Road (approximately 2.5 miles).

These improvements will include modification to the roadway medians, curb and gutter, parkways, sidewalks, ADA ramps, storm drain system, street lighting, traffic signal and utilities. The project also proposes to be widened to a 6-lane major arterial from Olive Drive to Old Grove Road. CRA is currently working on the conceptual phase of the project. PS&E will start in the summer of 2023.

El Cajon Boulevard Streetscape, City of El Cajon, El Cajon, CA. - Project engineer for the final design of a modern roundabout at the intersection of El Cajon Boulevard and Johnson Avenue that will serve as a direct connection for the proposed Class I Johnson Avenue Neighborhood Trail. Other design elements include a road diet, widened sidewalks with bulb-outs, a new rectangular rapid flashing beacon (RRFB) mid-block crossing, decorative lighting, fiber optic relocation, placemaking to allow opportunities for businesses and community gathering, and landscaping with trees and LID planters.

This is one of two concurrent adjacent projects, which both will provide much-needed multimodal connections. These projects were developed based on the city’s Transit District Specific Plan (CRA developed the mobility improvement recommendations) and are both funded by the SANDAG SGIP grant program for design and construction (CRA prepared the grant applications).

Jamacha Road Safety Enhancements, City of El Cajon, El Cajon, CA. - Project engineer supporting the PS&E effort. The project includes both vehicular and pedestrian safety countermeasures along this primary thoroughfare: pedestrian crossing improvements at signalized intersections, raised medians, and enhanced pedestrian crossings. In addition to the proposed safety improvements the project will also be a “Green Street” by reducing the impervious area within the areas of work to reduce the corridors storm water impacts on the existing drainage infrastructure.

Imperial Beach Boulevard, Imperial Beach, CA.* - Project Engineer. Created complete, green streets to make more functional connections between residences, schools, transit, tourist attractors, and businesses around the city. Added dedicated bike lanes, landscaped “pop-outs” for aesthetic and water quality benefits, newly enhanced bus stops, and upgraded pedestrian features. The concept applies the complete green street ideology on Imperial Beach Boulevard from Seacoast Drive to Connecticut Street.

Created a road diet to extend the concept from Connecticut Street to the easterly City limits near 15th Street, removing a lane of traffic in each direction to accommodate bike and pedestrian facilities.

EXPERIENCE
9 years

EDUCATION
BS, Civil Engineering,
California State University,
Chico
AA, Architectural Drafting
and Design, Palomar
College

ACCREDITATION
Professional Engineer,
California #86597
Blanca Soto PE
Civil Engineer
45%

AVAILABILITY
* Prior to joining CRA.
05/23/2023 C7 60 of 201

p / 14CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
CR Associates recently completed the preliminary design phase of this project. CR Associates is now leading the PS&E for eight intersections that include five traffic circles and two traffic calming treatments within the Village and Barrio. The design includes bike network enhancements, street light improvements, landscape and irrigation improvements, and a decorative art display within one of the traffic circles.

CR Associates is currently leading the NEPA and PS&E phases of this project. While working for a previous firm, a member of our staff served as the Project Manager for the Preliminary Engineering and CEQA phase of this project. This

2.9-mile urban bikeway runs through the mid-city and eastern neighborhoods of San Diego, ultimately connecting to the City of La Mesa at its eastern terminus. Proposed improvements include protected bikeways (Class IV), bus platforms to eliminate bus/bike conflicts, a protected intersection, fully protected bike movements at signalized intersections; two-stage, left-turn queue boxes; enhanced, mid-block, pedestrian crossings; bike signals, traffic signal modification, traffic calming measures, re-purposing of travel lanes, and innovative use of floating islands to slow side street turning movements. CR Associates is finalizing the PS&E package for this project.

VILLAGE AND BARRIO TRAFFIC CIRCLES
UNIVERSITY BIKEWAY – SANDAG

CITY OF CARLSBAD
Lauren Ferrell, Associate Engineer
[email protected]
442.339.2558
SANDAG
Chris Romano, Associate Active
Transportation Planner
[email protected]
619.699.6980

REFERENCE CONTACT

REFERENCE CONTACT

REFERENCE CONTACT

CRA STAFF ON THIS PROJECT

CRA STAFF ON THIS PROJECT

CRA STAFF ON THIS PROJECT
Matt Capuzzi, PE (Project Manager)
Scott Cartwright, PE / Stormwater/Water
Quality Engineer
Tomo Takahashi, PE / Sr. Traffic Engineer
Hailey Tyson, PE / Asst. Civil Engineer
Matt Capuzzi, PE / Project Manager
Scott Cartwright, PE / Stormwater/Water
Quality Engineer
Tomo Takahashi, PE / Sr. Traffic Engineer
Hailey Tyson, PE / Asst. Civil Engineer

SIMILAR CONTRACTS
LOCATION: CARLSBAD, CALIFORNIA • DURATION: 2019-ONGOING • COST: $475,314 LOCATION: SAN DIEGO, CALIIFORNIA • DURATION: 4/2018-ONGOING • COST: $17M While working for a previous firm, Roberto Ruiz-Salas, served as the Project Manager for the design of a 1.75 mile bicycle boulevard in National City that crosses the City south to north parallel to I-805. The project constructed over 3,000 feet of non-existing sidewalk along a residential street providing an ADA accessible path. Matt Capuzzi and Roberto help the City secure ATP grant funding for this project with grant writing assistance, then advanced the project through construction. Civil Design, environmental permits, stormwater quality compliance, traffic signal engineering, public outreach, utility coordination, and construction support where all services that Roberto provided through project closeout.

EL TOYON LAS PALMAS BICYCLE BOULEVARD

NATIONAL CITY
Roberto Yano, Director of Public Works
[email protected]
619.336.4383
Roberto Ruiz-Salas, PE /
Project Manager
Matt Capuzzi, PE / Grant Writing/
Preliminary Engineering
LOCATION: NATIONAL CITY, CALIIFORNIA • DURATION: 1/2017-2022 • BID COST: $1.5M 05/23/2023 C7 61 of 201

p / 15CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 1: Statement of QualificationsCRA P#2023.019
This important urban bikeway project constructs approximately 1/2 mile of the regional bike network along Park Boulevard. The addition of this missing segment will provide a critical connection between the eastern Hillcrest bikeways and the North Park Mid-City bikeways. To create a safe and comfortable bike facility that encourages more people of all ages and abilities to take up active transportation, the proposed improvements on Park Boulevard (a two-lane collector) include Class II buffered bikeways with double-buffers and a protected intersection at the intersection of Park Boulevard and Robinson Avenue. Best practices in treatments mitigate the conflict between vehicles and bicyclist to ensure that riders are kept visible and safe. CRA was responsible for preparation of construction bid documents consisting of roadway design, bike lanes geometrics, grading, traffic signal modification, and signing and striping.

CR Associates is currently designing a modern roundabout along Leucadia Boulevard at Hygeia Avenue in Encinitas, California. The design elements include construction of LID design features, decorative retaining walls (masonry and concrete materials) to protect existing utilities and provide screening for the adjacent properties, street lighting, and landscape and irrigation improvements. The design also includes drainage upgrades to resolve existing flood control issues and the introduction of roadside water quality BMPs to improve storm water quality. The precise grading design was particularly challenging due to the steep slopes on two of the four intersection approaches and the shallow depth of various utility lines. The project design also includes the relocation of three segments of water mains.

PARK BOULEVARD BIKEWAY - PROTECTED INTERSECTION

LEUCADIA BOULEVARD ROUNDABOUT

CITY OF SANDAG
Chris Kluth
[email protected]
619.699.1952

CITY OF ENCINITAS
Matt Widelski,
Principal Engineer
[email protected]
760.633.2862
Matt Capuzzi, PE / Task Manager
Blanca Soto, PE / Civil Engineer
Tomo Takahashi, PE / Sr. Traffic Engineer
Ross Duenas
Scott Cartwright, PE / Stormwater/Water Quality
Engineer
Tomo Takahashi, PE / Sr. Traffic Engineer
LOCATION: SAN DIEGO, CALIFORNIA • DURATION: 2018-ONGOING • COST: $1.2M LOCATION: ENCINITAS, CALIFORNIA • DURATION: 2018-2021 • COST: $4M

REFERENCE CONTACT

REFERENCE CONTACT

CRA STAFF ON THIS PROJECT

CRA STAFF ON THIS PROJECT

ROBINSON AVENUE
PAR
K

B
O
U
L
E
V
A
R
D
05/23/2023 C7 62 of 201

Section 3.

Work Plan
05/23/2023 C7 63 of 201

p / 17CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
CRA P#2023.019
Section 3. Work Plan
a. PROJECT UNDERSTANDING
The City will use CDBG funds to construct much needed sidewalk and curb ramps along Nevada Avenue from N. Santa Fe Avenue to Lemon Avenue and along Lemon Avenue from Nevada Avenue to Raintree Place. This grant program has the goal of building a stronger and more resilient community, and this project will accomplish that by providing a walkable path for residents of Vista. These corridors have very little existing pedestrian infrastructure, and some of what is out there is not ADA compliant. Adding sidewalk to one side of each street and adding/upgrading curb ramps will provide a great benefit to these residents by allowing safe and comfortable walking paths.

From our experience designing and constructing similar projects, we see the following as key challenges for this project:
ƒStorm water conveyance
ƒLimited right-of-way
ƒPrivate encroachments
ƒStorm water treatment
ƒConforms with existing
conditions
ƒADA retrofit
ƒPavement restoration
Each option on both corridors has different design and constructability challenges that can be overcome using an innovative approach and proven design methods. In general, street parking is valuable in this part of town, and any design consideration shall include street parking as part of the proposed solution. The following are our findings for each segment of the project based on our site visit and limited public input:

Nevada Ave Option 1 (North Side)
ƒ520’ of existing sidewalk
ƒ550’ of existing walking path separated by AC dike
ƒUtilities blocking the accessible path
ƒNon-ADA compliant driveways
ƒProperties are slightly higher than the street
ƒRight-of-way is behind walkable path
ƒStormwater drains east to west along Nevada
Nevada Ave Option 2 (South Side)
ƒLimited existing sidewalk
ƒNo walkable path outside of limited sidewalk
ƒSomewhat steep driveways connect to the road along the accessible path ƒSignificant elevation difference between properties
ƒProperties higher than street
Lemon Ave Option 1 (East Side)
ƒProperties significantly higher than street
ƒSidewalk may cause “bottoming out” of vehicles
ƒSignificant amount of small retaining walls/curbs may be needed to provide sidewalk
ƒSteep driveways connect to the road along the accessible path ƒLemon Avenue has both a high point and a low point between Nevada and Raintree, with existing curb inlets approximately 100’ south of Raintree taking the stormwater from the part of Lemon that drains north, with the remaining water draining south on Lemon or west unto Nevada Lemon Ave Option 2 (West Side)
ƒProperties lower than street – flooding into properties is a concern ƒNo walkable path nor curb
ƒSignificant private encroachment into public right-of-way 05/23/2023 C7 64 of 201

p / 18CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
b. PROJECT APPROACH AND METHODOLOGY
The City of Vista requires a consultant with experience in successfully designing projects that overcome the
challenges discussed in the Project Understanding. Our
team’s approach to pedestrian improvements comes from
years of experience delivering dozens of similar projects.

Our fundamental understanding of the City’s goals,
the local area, and our experience in delivering similar projects have all contributed to our approach to complete this project on-time and on-budget.

PRELIMINARY DESIGN
Preliminary design typically only includes 2D design,
but we consider that for this project a preliminary 3D
design will determine the opportunities, challenges,
and constraints that each corridor option presents. Our surveyor Gold Coast Surveying, Inc (GCSI) completed the aerial topography of this area in 2021, using that data and other information provided by the City, our team will:
ƒEstablish a flowline for each corridor
ƒPrepare sections at three driveways for each corridor:
this will visually present the impact to private property ƒSchematically lay out the impacts to private
encroachments in public right-of-way (we began this
exhibit as shown on exhibit A on page 20)
ƒIdentify drainage impacts for each option
ƒComplete a preliminary constructability review of
each option
Addressing these challenges through preliminary design
is an important part of our approach as it will give the City the information needed to make correct decisions on the improvements that will be constructible under the funded budget.

TOPOGRAPHIC SURVEY
Once an option is selected for each corridor, we will work with GCSI in determining the amount of field topographic survey that will be necessary to supplement the aerial
topography completed in 2021. We invited GCSI to form
our team, because of their knowledge of the city, their reputation for attention to detail, and their commitment to improving the City of Vista. The project will require a detail survey of public right-of-way and private property, as providing an accessible path that connects to private property might require encroaching into the adjacent
land.

DRIVEWAY DESIGN
An important component of this project is to minimize
the impact to adjacent properties. To ensure ADA
accessibility, ADA compliant driveways have to be
built along the selected corridors. Our team has
completed similar right-of-way constrained projects
and have designed different driveways that adapt to
the built environment restrictions. An important aspect of driveway selection is the reduction of impacts to
vehicles entering/leaving and preventing “bottoming
out”. To do so, each driveway has to be designed to be either a Type A or B contiguous driveway per the San
Diego Regional Standards Drawings (SDRSD) G-14A or
G-14F, a depressed driveway similar to SDRSD G-14D,
or if needed replace a driveway with a rolled curb per
City of Vista Standard Drawing SRF-10A. Our team
will determine the correct driveway that will reduce
the impact of “bottoming out” but also of stormwater
impacting private properties, and work directly with City staff in making the adequate selection.

STORMWATER QUALITY DESIGN
Our team includes local stormwater experts Tory R.

Walker Engineering (TRWE), with years of experience
designing storm water treatment and drainage systems.

We anticipate that this project will qualify for a Priority Development Project (PDP) Green Streets exemption, and
that hydromodification mitigation will not be required.

We understand that the City of Vista prefers to construct “traditional” BMPs for water quality treatment, as
described in the BMP Design Manual dated June 2016
and revised on September 2021, but we understand that
the City is open to installing proprietary BMPs, such as a Modular Wetland System, when right-of-way and space
is limited. Our team has done a preliminary analysis of the site and reviewed the as-builts provided by the City through Amendment 02 of this RFP, and have determined
that there is an opportunity to construct water quality BMPs in the public right-of-way on Nevada Avenue
east of the curb inlet located on the south side near the intersection with Santa Fe Avenue, and south of the curb inlet located on Santa Fe Avenue north of the intersection with Nevada Ave.
05/23/2023 C7 65 of 201

p / 19CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019

PAVEMENT IMPACT
Through our field assessment, we observed large areas of alligator cracking on Nevada Avenue. It is our experience that these areas require full depth replacement rather
than simply slurry seal or mill and overlay. CRA staff Aryo Rad has over 25 years of experience in pavement design, and will provide the required guidance to the City for a cost effective approach to these improvements. Leighton Engineering has been the geotechnical engineer of
record for numerous projects in the City of Vista, they understand this area and will support our team with
pavement recommendations.

UTILITY COORDINATION
There are multiple utilities that will require relocation to ensure ADA accessibility through these corridors. Our
staff has led the utility coordination on similar projects, and understand that utility relocation might be a critical path to meet the projects’ schedule. As soon as a notice to proceed is provided, we will request utility maps from the companies in the City including: AT&T, Cox, SDG&E,
Spectrum and the Vista Irrigation District. Using these utility maps along with the As-Builts provided by the
City we will create a utility base map and a utility conflict matrix to track the impacts to existing utilities from our proposed improvements. Beginning coordination with
utility companies in the preliminary design phase and
continuing it throughout the design process will reduce delays.

PROJECT MANAGEMENT APPROACH
Delivering a high-quality design in the requested
timeframe proposed by the City will require close
collaboration between the design team and City staff.

This will be a true working partnership! Proven and
successful communication and project management
protocols are paramount when working on projects
with various moving parts. Having worked on multiple
pedestrian improvement projects in the past, our team is very familiar with completing complex projects with strict deadlines and has developed a number of tried-and-true
strategies. One effective strategy we would propose to
implement is to maintain active communication with City staff through bi-weekly conference calls, and in-person meetings to discuss deliverables at the Preliminary
Design phase, and the multiple submittals of the Final
Engineering phase.. These will greatly aid in formally
keeping the lines of communication open. Another
tactic we’ve employed on past projects is the creation
and maintenance of an action item matrix which is used
to track each item a stakeholder is responsible for. This approach has proven to foster accountability and improve the timeliness of each action’s completion.

As projects evolve, we know that requests can spring up at a moment’s notice. Our team prides itself on our past history of responsiveness to client’s requests as well as our flexibility to seamlessly accommodate project updates.

These characteristics have been woven into the fabric of how we go about our business. We encourage you to
contact our past and current clients to learn more about our passion for responsiveness. Lastly, as laid out above we’ve found that identifying challenges early is key to maintaining the project schedule. The upfront investment in developing driveway sections, private construction in public right-of-way impacts, stormwater conveyance, and utility relocations have time and again proven worth their weight in gold when the PS&E documents are created,
and as the projects are constructed.

QUALITY CONTROL APPROACH
CR Associates is passionate about providing quality
services and products. CRA was founded on a
commitment to fostering a workplace culture dedicated
to delivering products that are accurate, well-written, based on sound reasoning and assumptions, and have
been thoroughly reviewed by the senior staff before
submission. CRA has the policies and procedures in
place to ensure that our team delivers a quality product every time. Our team’s quality control plan will include reviews by the project manager, by an internal 3rd party reviewer who is an expert in the individual discipline, and an interdisciplinary review by the project manager
before submittal. This same approach has been used very successfully by our team on similar sidewalk improvement projects.
05/23/2023 C7 66 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290) p / 20
Section 3. Work PlanCRA P#2023.019
Exhibit A, 1 of 2
N C
I
T
R
U
S

A
V
E
8 '

4. 5
'

NEVADA AVE
59 .
5 '
5 0
.
6 '
60'
8 '
10 '
LE
M
O
N

A
V
E
N
S
A
N
T
A

F
E

A
V
E
NEVADA AVE50
.
1 '
8'
10 '
8'
Nevada and Lemon
Pedestrian Mobility Sidewalks
2/20/2023
Sheet 1 of 2
P:
\
P
r
o
p
o
s
a
l
\
2 0
2 3
\
2 0
2 3
.
0 1
9 _
C
i
t
y

o
f

V
i
s
t
a
_
N
e
v
a
d
a

a
n
d

L
e
m
o
n

P
e
d
e
s
t
r
i
a
n

M
o
b
i
l
i
t
y

S
i
d
e
w
a
l
k
s
\
R
F
P
\
E
x
h
i
b
i
t
\
S
i
d
e
w
a
l
k
s

E
x
h
i
b
i
t
_
4 0

S
c
a
l
e
.
d
wg

P
l
o
t
:

L
a
u
r
e
n

M
c
K
e
l
v
e
y

D
a
t
e
:

2 /
2 0
/
2 0
2 3

8 :
4 6
:
4 1

A
M
N
0'40'80'
N
N
C
I
T
R
U
S

A
V
E
8 '

4. 5
'

NEVADA AVE
59 .
5 '
5 0
.
6 '
60'
8 '
10 '
LE
M
O
N

A
V
E
N
S
A
N
T
A

F
E

A
V
E
NEVADA AVE50
.
1 '
8'
10 '
8'
Nevada and Lemon
Pedestrian Mobility Sidewalks
2/20/2023
Sheet 1 of 2
P:
\
P
r
o
p
o
s
a
l
\
2 0
2 3
\
2 0
2 3
.
0 1
9 _
C
i
t
y

o
f

V
i
s
t
a
_
N
e
v
a
d
a

a
n
d

L
e
m
o
n

P
e
d
e
s
t
r
i
a
n

M
o
b
i
l
i
t
y

S
i
d
e
w
a
l
k
s
\
R
F
P
\
E
x
h
i
b
i
t
\
S
i
d
e
w
a
l
k
s

E
x
h
i
b
i
t
_
4 0

S
c
a
l
e
.
d
wg

P
l
o
t
:

L
a
u
r
e
n

M
c
K
e
l
v
e
y

D
a
t
e
:

2 /
2 0
/
2 0
2 3

8 :
4 6
:
4 1

A
M
N
0'40'80'
N

SD INLET

PAVEMENT REPAIR

ELEVATION DIFFERENCE

POSSIBLE

LOCATION
OF BMP

DRIVEWAY

LOCATION
(TYP)PARCEL LINES

FROM SANGIS
(TYP)

INTERSECTION IMPROVEMENTS

POSSIBLE LOCATION OF BMP

UTILITY RELOCATIONS
05/23/2023 C7 67 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290) p / 21
Section 3. Work PlanCRA P#2023.019
Exhibit A, 2 of 2
RA
I
N
T
R
E
E

P
L
58 '

LEMON AV
E
5 6
.
8 '
5 .
5 '
'0
6 5.
5 '
10'
'0
1 LEMON AVE
Nevada and Lemon
Pedestrian Mobility Sidewalks
2/20/2023
Sheet 2 of 2
P:
\
P
r
o
p
o
s
a
l
\
2 0
2 3
\
2 0
2 3
.
0 1
9 _
C
i
t
y

o
f

V
i
s
t
a
_
N
e
v
a
d
a

a
n
d

L
e
m
o
n

P
e
d
e
s
t
r
i
a
n

M
o
b
i
l
i
t
y

S
i
d
e
w
a
l
k
s
\
R
F
P
\
E
x
h
i
b
i
t
\
S
i
d
e
w
a
l
k
s

E
x
h
i
b
i
t
_
4 0

S
c
a
l
e
.
d
wg

P
l
o
t
:

L
a
u
r
e
n

M
c
K
e
l
v
e
y

D
a
t
e
:

2 /
2 0
/
2 0
2 3

8 :
4 6
:
4 4

A
M
0'40'80'
N
N
RA
I
N
T
R
E
E

P
L
58 '

LEMON AV
E
5 6
.
8 '
5 .
5 '
'0
6 5.
5 '
10'
'0
1 LEMON AVE
Nevada and Lemon
Pedestrian Mobility Sidewalks
2/20/2023
Sheet 2 of 2
P:
\
P
r
o
p
o
s
a
l
\
2 0
2 3
\
2 0
2 3
.
0 1
9 _
C
i
t
y

o
f

V
i
s
t
a
_
N
e
v
a
d
a

a
n
d

L
e
m
o
n

P
e
d
e
s
t
r
i
a
n

M
o
b
i
l
i
t
y

S
i
d
e
w
a
l
k
s
\
R
F
P
\
E
x
h
i
b
i
t
\
S
i
d
e
w
a
l
k
s

E
x
h
i
b
i
t
_
4 0

S
c
a
l
e
.
d
wg

P
l
o
t
:

L
a
u
r
e
n

M
c
K
e
l
v
e
y

D
a
t
e
:

2 /
2 0
/
2 0
2 3

8 :
4 6
:
4 4

A
M
0'40'80'
N
N

PARCEL LINES

FROM SANGIS
(TYP)

POSSIBLE CONSTRUCTION OF CURB RAMP - TBD THROUGH DESIGN

PRIVATE CONSTRUCTION IN PUBLIC RIGHT OF WAY

PRIVATE CONSTRUCTION IN PUBLIC RIGHT OF WAY

STEEP DRIVEWAYS

TWO INLETS ON LEMON AVE
05/23/2023 C7 68 of 201

p / 22CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
c. SCOPE OF WORK
We accept the scope of work as outlined on the RFP but have made minor cost saving modifications as outlined below.

We have copied the RFP’s scope of work below and highlighted the modifications made (added a strike mark on the scope removed and shown in blue the scope language added). ➥Task 1 – Project Initiation, Management, Meetings and Coordination A. Schedule and hold an initial meeting with City staff and subconsultants to discuss the approach to the project, scope of work, schedule and address any questions or requests for information from the consultant or subconsultants
B. Coordinate the day-to-day activities on the project and manage all subconsultants and coordinate their activities
C. Hold up to six formal meetings with City staff to develop the design of the project, resolve design issues, discuss staff comments on plans, estimate, and document submittals, discuss progress and address any other issues. It is important that the design of the project is developed in coordination with the City to ensure that the City’s goals and objectives are met.

C. Maintain open and regular communications with City staff and subconsultants.

D. Meetings:
ƒHold up to six formal 1 hour in-person meetings with City staff at the following stages:
à 1 meeting for Preliminary Design
review
à 1 meeting after the 60% submittal to
discuss City comments.
à 1 meeting to discuss SWQMP and
water quality approach.
à 1 meeting after the 90% submittal to
discuss City comments.
à 1 meeting after the 100% submittal to
discuss City comments.
à 1 meeting prior to project releasing for
bid.
ƒBiweekly virtual 30-minute meetings to discuss project progress and design (up to 12 meetings) ƒProduce and distribute meeting agendas and minutes.
✔Deliverables:

Meeting agendas; meeting minutes; progress reports, and project documentation. ➥Task 2 – Data Collection and Field Review
A. Obtain aerial topographic survey of the project site from the City for use in developing a preliminary layout of the proposed improvements.

B. Collect existing as-built plans for street improvements, sewer, water, and storm drain systems for the project site.

C. Obtain utility maps from utility companies.

D. Conduct a field review to become familiar with the physical layout and features of the project site. Note any features that may need special attention or may present a challenge in the design development final design of the project.

E. Conduct a study of existing conflicts and determine the best layout for the proposed sidewalks on either the North or South side of Nevada Avenue and the West or East side of Lemon Avenue. Study of existing conflicts and layout selection part of Task 6
✔ Deliverables: Documentation of all data collected in the tasks above. 05/23/2023 C7 69 of 201

p / 23CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
➥Task 3 – Design Surveying and Base Map Development
A Obtain and review existing maps, Records of Survey (ROS), Corner Records (CR), etc. for existing right- of-way / property lines, easements, etc.

B. Establish vertical and horizontal control for the project based on City of Vista benchmarks and first order control map, ROS 14023.

C. Notify property owners / tenants with “doorknob” hangers at least two working days prior to entering private property if needed. The format of the notification shall be approved by the City’s Project Manager prior to distribution.

D. Establish and set semi-permanent horizontal and vertical control points for use during design and construction.

E. Locate and identify existing boundary and other survey monumentation to establish right-of-way & property line, and to perpetuate monumentation within the limits of work. Show all existing monuments within the project limits on the topographic base map so all monuments can be labeled on the improvements plans to be protected or replaced.

F. Establish the centerline and right-of way for the project streets and depict on the base map. Tie the public right-of-way and topography to NAD ’83 Coordinate system.

G. Prepare topographic base map. Develop topography within the project limits of work and 20 feet beyond the ultimate right-of-way of the project streets unless otherwise specified (i.e. driveways) (+/- 26 total driveways).

Tasks E through G have already been completed by CRA’s subconsultant Gold Coast Surveying, Inc.

H. Locate and identify all visible VID water and franchise utility facilities. Provide top of pad or top of vault elevation and size for all pull-boxes, vaults, and enclosures.

I. Locate and identify all streetlight facilities. Provide finish surface, top of pad, or top of vault elevations and size for all poles, pull-boxes, vaults, and enclosures.

J. Locate and identify all sewer and storm drain facilities. Provide finish surface, top of rim or grate, flowline, and invert elevations and size for all structures, manholes, pipes, cleanouts, and enclosures.

K. Obtain USA mark-out and locate and identify underground utility pipe and conduit locations based on utility mark-outs prior to potholing. USA mark out included as part of Task 7 – Utility Coordination L. Locate and identify other surface features, including:

1. Top of curb including elevation and centerline offset distance with identifier, if applicable (PCR, BC, EC, PCC, etc.)
2 Gutter lip

3. Pedestrian ramps

4. Cross Gutters

5. Structures

6. Trees and large shrubs. Coordinates shall be to the center of the tree or shrub and include tree type and diameter, elevation of tree at trunk base, approximate tree height, surface root and drip line perimeters

7. Driveways and driveway aprons including elevations within a 50-foot area behind the driveway apron, at all construction / expansion joints and where driveways meet concrete slab of garage.

Sufficient field data of driveways (to garage doors), located adjacent to proposed curb, gutter, and sidewalk improvements, in order to redesign the driveways and yards 05/23/2023 C7 70 of 201

p / 24CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019

8. Sidewalks including back of sidewalk location and elevation, especially any lifted portions

9. Fences and walls including type and condition

10. Mailboxes including type and condition

11. Steps including type and condition

12. Retaining walls including type (reinforced or unreinforced, footing or no footing) and condition

13. AC paving and dikes

14. Signs

15. Striping and pavement markings

16. Other significant surface features
M. Prepare a digital AutoCAD topographic base map of all the elements and elevations obtained in the topographic survey, at 20 scale with 1-foot contours.

N. After the horizontal alignments of the new curbs have been established, profile the existing surface at the street centerline and the proposed curb lines, with elevations measured at maximum 50-foot intervals and at other locations where anomalies exist, to provide accurate finish grade elevations for vertical alignment design. This work is included as part of Task 6
✔Deliverables:

A digital AutoCAD base map containing all the elements and elevations obtained in the tasks above, and existing surface profiles at centerline and at proposed curb lines (upon request). ➥ Task 4 – Geotechnical Investigation and Report Preparation A. Conduct geotechnical testing of existing soil along shoulders of Nevada Avenue and Lemon Avenue to determine adequacy for road widening improvements with street structural section recommendation.

B. Conduct geotechnical testing at any locations where a retaining wall is proposed and provide the geotechnical parameters needed to design the retaining wall. At a minimum, provide the saturated unit weight; angle of internal friction; allowable soil bearing value for the retained zone, reinforced zone, and foundation zone; and backfill recommendations
C. Prior to any subsurface excavations a no fee right-of-way permit (and possibly an approved traffic control plan) from the City of Vista and a USA mark out would be required D. Prepare a report documenting geotechnical investigation and testing and all findings and recommendations by a Licensed Geotechnical Engineer.

A. Complete a review of documents regarding the known geotechnical conditions pertinent to the alignment area.

B. Complete a geotechnical reconnaissance of the site, markout, and coordination with Underground Service Alert.

C. Prepare a Traffic Control Plan and submit to the City of Vista. Obtain necessary City of Vista no-fee right-of-way permits for drilling in public right of way (ROW). Traffic control services will be provided during the field exploration.

D. Perform three (3) geotechnical borings to a maximum depth of 10 feet to evaluate subsurface conditions within the alignment. A geologist or engineer will log the geotechnical borings.

Since the borehole locations are proposed within the shoulder of the street proposed for future improvements, we have assumed that sawcutting and patching with hot mix asphalt will not be required. We propose to patch the boreholes with aquaphalt. If City of Vista requires sawcutting and patching the holes with HMA, we can perform this service for an additional cost of $4,500. 05/23/2023 C7 71 of 201

p / 25CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
E. Obtain representative soils samples during drilling to perform sieve analysis, direct shear, R-Value, and corrosion series laboratory tests.

F. Complete a geotechnical analysis of data obtained.

G. Prepare one geotechnical report for the project presenting our findings and recommendations. ✔Deliverables:

Geotechnical Investigation Report.
➥Task 5 – Water Quality Technical Report
A. Prepare a Project Determination Checklist using the template provided by the City. The City of Vista has determined that the Urban Runoff Threat Assessment is “high” for all projects.

B. If the project is determined to be a Standard or Priority Project, prepare a Stormwater Quality Management Plan(SWQMP) using the template provided by the City.

C. Prepare Municipal Stormwater Permit documentation in accordance with San Diego Regional Water Quality Control Board Order No. R9-2013-0001/2015-0001, using the City of Vista BMP Design Manual.

Determine applicable design requirements. Evaluate potential for any exemptions related to sidewalk projects. Submit report to the City for review and make changes as requested by the City.

D. Incorporate all required hydro-modification improvements and permanent BMP’s into the project design.

B. STORMWATER QUALITY MANAGEMENT PLAN (SWQMP)
The CRA team will prepare a SWQMP using the current City of Vista template and in conformance with the current City of Vista BMP Design Manual, dated June 2016. As a sidewalk project, it is anticipated that the Nevada and Lemon Pedestrian Mobility improvements will qualify for a Priority Development Project (PDP) Green Streets exemption and, as such, hydromodification mitigation will not be required. The report will provide Design Capture Volume (DCV) calculations and operations and maintenance guidance for the proposed storm water pollutant control mitigation systems. The SWQMP will be provided as a deliverable at each of the prescribed submittal intervals of 60%, 90%, and 100% design levels, and will contain a level of detail consistent with the corresponding design plans.
✔Deliverables:

Project Determination Checklist, SWQMP, Water Quality Technical Report, and Design Exhibits. ➥Task 5a – Drainage Study
The CRA team will prepare a final engineering drainage study in accordance with the methodologies set forth in the San Diego County Hydrology Manual (SDCHM) to demonstrate that the proposed project does not significantly alter the existing hydrologic conditions or adversely impact downstream drainage infrastructure during the 100-year storm event. The drainage study will include rational method calculations and, if appropriate, hydraulic calculations for the proposed systems. It is assumed that the proposed project will not significantly increase peak flows and, as such, peak flow detention will not be required. It is also assumed that the public drainage systems downstream of the project area are adequately sized to collect and convey tributary runoff. The project does not propose any extension or expansion of the existing public drainage systems. Project improvements are limited to those required for water quality mitigation requirements. ✔Deliverables:

Drainage Study (60%, 90%, AND 100%)
05/23/2023 C7 72 of 201

p / 26CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
➥Task 6 – Preliminary and Final Design
A. Coordinate with other ongoing and planned projects such to ensure compatibility of the proposed improvements with those other projects.

B. Preliminary Design
Create the following for each corridor option (four total) ƒUsing the AutoCAD topographic base map, and aerial imagery from NearMap, develop a preliminary horizontal layout of the improvements and a preliminary striping plan showing lane configuration of the four options as depicted in Exhibit A. ƒDesign a profile of the flowline along the gutter.
ƒDesign a 3D 5’ sidewalk with a 6” curb and gutter.
ƒCreate up to three sections of different driveways per corridor option (total of up to twelve)

CRA will create preliminary plans using the City’s standard titleblock (Arch D – 24x36), with plan views that can later be used for final design. Preliminary plans will show:
ƒExisting features: survey monuments, utilities, streetlights, spot elevations, and existing landscape.
ƒProposed curb line, back of walk, sidewalk, driveways (SDRSD G-14A, G-14D, or G-14F; depending on right-of-way constraints), and potential stormwater BMP locations. ƒImpacts to private encroachments in public right-of-way Preliminary plans will not include:
ƒDetailed vertical design of flowline, top of curb, and driveways.

As identified in Task 1, an in-person meeting will be held with City staff to discuss the preliminary plans, and select an option for each corridor to move towards final design. It is assumed that horizontal or vertical revisions to the preliminary design will be addressed as part of the 60% plans of final design.

C. Final Design
CRA will prepare 60%, 90%, and 100% construction documents for City review and comment, and a Final set of construction documents for bid after the 100% plan review. The design will be based on the following standards: City of Vista Standard Drawings, San Diego Regional Standard Drawings, Caltrans Highway Design Manual and the California Manual on Uniform Traffic Control Devices (CA-MUTCD).

CRA’s design will consist of the following sheets:

SHEET TITLE SCALE # OF SHEETS
Title Sheet/Vicinity Map 1
General Notes 1
Key Map 1
Construction Details 2
Typical Sections 1
Survey Control Plans 1” = 40’1
Demolition Plans (double stacked plans)1” = 20’2
Improvement Pans (plan and profile)1” = 20’4
Driveway Details*1” = 10’1
Storm Drain and Permanent BMP Details 1” = 20’2
Signing and Striping Plans and Details 1” = 40’2
Lighting and Electrical Plans and Details**1” = 40’2
Temporary Erosion Control Plans 1” = 40’2
Total Sheets 22
05/23/2023 C7 73 of 201

p / 27CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
*The Driveway Detail sheets will include horizontal and vertical control points, impacts to private encroachments in public right-of-way, and project impacts to private property (grading) for four typical driveways.
** Lighting and Electrical Plans will depict features such as light fixture placement, conduit and pull box layout, conductor information, utility service connection point(s), and other relevant information needed to depict the design. A photometrics analysis will be conducted to determine appropriate lighting levels within the project limits. The focus of the analysis will be on the lighting levels for pedestrian walkways within the project limits and the intersection of Nevada Avenue and N. Citrus Avenue. It is assumed that Voltage Drop calculations will not be required, and that existing lighting conductors and circuit boards have capacity for additional proposed lighting.

It is assumed that the City will provide consolidated plan comments after the 60%, 90%, and 100%, and that CRA will meet with City staff through an in-person meeting as identified in Task 1 to discuss the comments.

The CRA team includes Neri Landscape Architecture (Neri LA) on an as-needed basis to provide Landscape Architecture design services if the permanent BMPs require landscaping and irrigation, as well as if connections to private properties impact existing landscaping. Once the scope of Neri LA is determined, the effort and scope will be submitted to the City and will only be completed after written approval by City staff.

B. Using the AutoCAD topographic base map, develop a preliminary horizontal layout of the improvements and a preliminary striping plan showing lane configuration for review and acceptance by the City. Make adjustments as requested by the City.

C. Identify and label existing features, including survey monuments, utilities, streetlights, and spot elevations.

D. Based on supplemental survey elevations, develop, design and draft the horizontal and vertical geometrics and alignments of the project improvements in plan and profile layouts.

E. Analyze the drainage patterns after the plan and profile layouts are developed to ensure that the streets and private properties will drain properly. Adjust the design to include drainage features or grading work to ensure proper drainage is maintained.

F. Design hydromodification and stormwater treatment improvements based off the recommendations within the Water Quality Technical Report.

G. Call out all the proposed improvements using detailed and distinct construction notes and refer to standard drawings or details shown elsewhere on the plans as appropriate H. Design typical cross sections to reflect the existing conditions and the proposed improvements I. Provide details of improvements such as retaining walls, curb ramps, curb pop-outs, and driveways, to clearly show the required construction, to enable a contractor to construct the improvements with minimal, if any, requests for information and change orders.

J. Draft Title Sheet and detail sheets containing general notes, special notes, special provisions, typical sections, construction details, etc., similar to other City of Vista projects, using City standard templates adjusted for this project.

K. Prepare striping and signing plans.
05/23/2023 C7 74 of 201

p / 28CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
L. Design a schematic erosion control plan with specific erosion control measures and temporary BMPs called out at specific locations where excavation is proposed, similar to other City of Vista projects, using City standard templates adjusted for this project.

M. Submit the plans to the City for review at 60%, 90% and 100% design levels. Depending on the level of completeness of the submitted plans, allow for a minimum of four iterations of comments by the City and corrections or revisions to the plans.
✔Deliverables:
• Preliminary design plans (pdf format)
• Construction documents at 60%, 90%, 100% and a Bid-ready set (pdf format) Preliminary horizontal layout design plans, design plans of the project improvements at the 60%, 90%, and 100% design levels, and bid-ready construction plans signed and sealed by the Engineer of Work. ➥Task 7 – Utility Coordination
A. Submit preliminary horizontal layout on topographic base map to utility companies and request confirmation that utility facilities are depicted accurately.

B. Submit the preliminary design plans to all utility companies and request a conflict check.

C. Prepare a Utility Conflict Matrix (xls format)
D. Coordinate with utility companies who have utilities in conflict with the proposed improvements.

Obtain pothole information for utility conflicts and adjust locations of facilities to avoid or minimize conflicts if possible. Request relocation of utility facilities where conflicts cannot be avoided. Obtain schedule of relocation design and construction from utility companies.

E. Submit final construction plans signed by the Engineer of Work and City Engineer and confirm that utility companies are designing their relocations.

F. Ensure that the utility companies who have utilities in conflict with the proposed improvements schedule the construction of the relocation of their utilities through their internal procedures.

G. Obtain signatures from VID on the plans if any water facilities are affected by the proposed improvements.

Assumptions:
• It is assumed that potholing activities will be completed in 1 day • It is assumed that tasks 7.A, 7.B, 7.D*, 7.E, 7.F, and 7.G will be completed by the client. *Obtaining utility pothole information to be completed by CRA team ✔Deliverables:

Copies of correspondence with utility companies and copy of pothole report. 05/23/2023 C7 75 of 201

p / 29CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
➥Task 8 – Construction Cost Estimates
A. Using the 60% design plans, develop a preliminary engineer’s estimate of the costs to construct the proposed improvements. The estimate is to include a list of all items of work, including any items not detailed on the 60% plans. Cost information shall include item quantities, unit cost per item and total cost for each item as well as contingencies and total construction cost. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

B. Update the engineer’s estimates at the 90% and 100% design levels to include all items of work and appropriate quantities and contingencies. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

C. Prepare a Final Engineer’s Estimate of Construction Cost, using only the limited number of items of work that will be included in the Bid Schedule and showing no contingencies. ✔Deliverables:

Detailed Engineer’s construction cost estimates at the 60%, 90%, and 100% design stages, and a Final Engineer’s Estimate of Construction Cost.
➥Task 9 – Construction Support for Design
A. Provide written and graphical responses to questions from bidders related to the project plans during the construction bid phase. Up to 5 responses have been included in this scope.

B. Prepare addenda as required during the construction bid phase. Prepare one conformed construction plan set with revisions made through the bid phase.

C. Provide other support during the construction bid phase as needed. Up to 10 hours of CRA staff time have been included in this scope.

D. Attend the pre-construction meeting
E. Respond to Requests for Information from the construction contractor during the construction phase. Up to 15 RFI responses have been included in this scope.

F. Provide other support during the construction phase. Up to 40 hours have been included in this scope. ✔Deliverables:

Written responses to questions from bidders, written addenda, written responses to RFI’s from the Contractor, and other construction support documentation.
➥Task 10 – As-Built Plans and Project Close-out
A. Upon completion of construction and using Change Orders and red line plans marked by the City inspector and construction contractor, draft as-built plans for the project. Incorporate all changes to the plans electronically with all necessary revision notations B. Submit a plan set signed by the Engineer of Work to the City with an electronic copy of the final as-built drawings, for review and approval by the City inspector and City Engineer.

C. Submit an electronic copy of all the files developed during the project, including research, survey geotechnical, utility coordination, design, plans, estimates and all other project documentation. ✔Deliverables:

Final signed as-built plans and electronic copy of the project files. ➥Task 11 – Conduct Quality Control and Quality Assurance 05/23/2023 C7 76 of 201

p / 30CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
Section 3. Work PlanCRA P#2023.019
CRA will prepare a quality control & quality assurance plan to have in effect during the entire time work is being performed under the Agreement. The Quality control plan shall establish a process whereby plans and other project documents are independently checked, corrected, and back checked prior to submittal to the City. CRA will maintain neat and organized project files.

Copy of QA/QC Plan to be followed during the project, and quality control and quality assurance evidenced in the quality of all plans and documents submitted to the City. City may request to view internal plan check comments to verify QA/QC.
✔Deliverables:
• QA/QC plan (upon request)
• Internal QA/QC for each deliverable upon request (pdf format) 05/23/2023 C7 77 of 201

Section 4.

Fee Proposal
As requested in the RFP, the Fee Proposal
has been uploaded as a seperate file.
05/23/2023 C7 78 of 201

ASSOCIATESASSOCIATESASSOCIATESASSOCIATES

CITY OF VISTA
(CIP NO. 8290)NEVADA AND LEMON

PEDESTRIAN MOBILITY SIDEWALKS
FEE PROPOSAL February 23, 2023 • 4:00 PM
3900 5th Avenue, Suite 310
San Diego, CA 92103
05/23/2023 C7 79 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290) p / 1
CRA P#2023.004CRA P#2023.019
Section 4. Fee Proposal
City of Vista-
Nevada and Lemon Pedestrian Mobility Sidewalks
CIP No. 8290
City of Vista, Professional Services for Nevada and Lemon Pedestrian Mobility Sidewalks (CIP No. 8290) Schedule of Billing Rates
05/23/2023 C7 80 of 201

CRA P#2023.004 Section 4. Fee ProposalCRA P#2023.019

SAN DIEGO
3900 5th Avenue, Suite 310
San Diego, CA 92103

LOS ANGELES
714 W Olympic Blvd, Suite 609
Los Angeles, CA 90015

ASSOCIATESASSOCIATESASSOCIATESASSOCIATES
05/23/2023 C7 81 of 201

Section 5.

Work Schedule
05/23/2023 C7 82 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290) p / 33
CRA P#2023.019
Section 5. Work Schedule
ID Task Name Duration Start
1 NTP 0 days Wed 5/24/23
2 Task 1 - Project Management 264 days Mon 5/1/23
3 Kick Off Meeting 1 day Mon 5/29/23
4 Biweekly Meetings 264 days Mon 5/1/23
5 In-Person Meetings 120 days Thu 8/3/23
6 Preliminary Design 1 day Thu 8/3/23
7 60% Submittal 1 day Tue 10/24/23
8 SWQMP 1 day Thu 9/7/23
9 90% Stage Review 1 day Wed 11/15/23
10 100% Submittal 1 day Fri 12/29/23
11 Prior to Project going to Bid 1 day Wed 1/17/24
12 Task 2 - Data Collection and Field Review 15 days Tue 6/6/23 13 Task 3 - Design Surveying and Base Map
Development
60 days Fri 8/18/23
14 Task 4 - Geotechnical Investigation and Report Prep 60 days Fri 9/15/23 15 Task 5 - Water Quality Technical Report 79 days Thu 8/10/23 16 Task 5a - Drainage Study 79 days Thu 8/10/23
17 Task 6 - Preliminary and Final Design 144 days Tue 6/27/23 18 Preliminary Design 25 days Tue 6/27/23
19 Prelim Design 20 days Tue 6/27/23
20 Prelim Design - City Review 5 days Tue 7/25/23
21 Final Design 116 days Fri 8/4/23
22 60% Plans 45 days Fri 8/4/23
23 60% City Review 10 days Fri 10/6/23
24 100% Plans 35 days Wed 10/25/23
25 100% City Review 10 days Wed 12/13/23
26 Bid Plans 10 days Mon 1/1/24
27 Task 7 - Utility Coordination 197 days Fri 8/11/23
28 Submit preliminary plans 14 days Fri 8/11/23
29 Submit 100% plans 14 days Wed 11/8/23
30 Design relocations as necessary 120 days Tue 11/28/23 31 Task 8 - Construction Cost Estimates 71 days Fri 10/13/23 32 60% OPCC 15 days Fri 10/13/23
33 100% OPCC 10 days Wed 11/15/23
34 Final Construction Cost Estimate 5 days Mon 1/15/24
35 Task 9 - Construction Support for Design 280 days Mon 1/15/24 36 Bid Phase 60 days Mon 1/15/24
37 Conformed Plans for construction 14 days Mon 4/8/24
38 Construction Phase 180 days Mon 6/3/24
39 Task 10 - As-Built Plans and Project Close-Out 63 days Mon 3/10/25 40 As-Built Plans 23 days Mon 3/10/25
41 Project Close-Out 40 days Thu 4/10/25
42 Task 11 - QC&QA 535 days Thu 5/18/23
5/24
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 2023 2024 2025

Page 1 of 1 ends
Page 1 ends

05/23/2023 C7 83 of 201

Section 6.

Consultant Agreement
Section 6. Consultant Agreement
CR Associates has reviewed the City’s Standard
Agreement and has no exceptions to the terms therein.
05/23/2023 C7 84 of 201

CITY OF VISTA - NEVADA AND LEMON PEDESTRIAN
MOBILITY SIDEWALKS (CIP NO. 8290)
CRA P#2023.019
Section 7.

Sample Work Product
05/23/2023 C7 85 of 201

I
-
5 N
.

V
U
L
C
A
N

A
V
E
.
"
P
A
C
I
F
I
C

O
C
E
A
N
"
H
Y
G
E
I
A

A
V
E
H
Y
M
E
T
T
U
S

A
V
E
H
E
R
M
E
S

A
V
E

LEUCADIA

B
L
V
D
F
U
L
V
I
A

S
T

PROJECT
SITE E
O
L
U
S

A
V
E
OR
P
H
E
U
S

A
V
E
N
.

C
O
A
S
T

H
W
Y

1 0
1 TRAIN
TRACKS

2. 3.

4. “”

5. 6.

7. 8.

9. 10.

11. 12.”

13. 14.

15. 16.

17. 18.

19. 20.

20.A.

21. 22.

23. 24.

25. 26.

27. 28.

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
1 LEUCADIA BLVD

ROUNDABOUT
05/23/2023 C7 86 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
2 W
SS
G
T
E
//
®
05/23/2023 C7 87 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS

MOUNTABLE CURBB

ROUNDABOUT CENTER ISLAND TYPICAL SECTIONA

BIKE RAMPE
80MM PAVERC
3 SAWCUT IN AC PAVEMENT D

SAWCUT IN AC PAVEMENT NEAR C&G

ROADWAY SAWCUT DETAIL CONCRETE SIDEWALK WITH MONOLITHIC BACK CURBF

TYPICAL SIDEWALK SECTIONSG

SIDEWALK LOWER THAN TOP OF CURB

BACK OF SIDEWALK EDGE CONDITIONS
05/23/2023 C7 88 of 201

SECTION B-B

SECTION A-A

PLAN VIEW
DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS

BMP CURB INLET AND OUTLETH

CURB & GUTTER TRANSITION I

ROCK SWALEL
BROW DITCH - MODIFIED TYPE A PER SDRSD D-75K

SPLASH PADM
4 IMPERMEABLE LINER CONNECTIONN

CONCRETE RETAINING WALLSJ

TYPE A RETAINING WALL ADJACENT TO SDG&E VAULT

RETAINING WALL ADJACENT TO LANDSCAPE
05/23/2023 C7 89 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS

CHECK DAMP

VEGETATED BASIN, THICKENED CURB AND GUTTER, AND PLANTER WALLO LINER PENETRATIONQ

VEGETATED BASIN IN OPEN AREA

VEGETATED BASIN IN PARKWAY - SOUTHERN SIDE OF LEUCADIA BLVD 5 VEGETATED BASIN IN PARKWAY - NORTHERN SIDE OF LEUCADIA BLVD 05/23/2023 C7 90 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
8 TYPICAL SECTION I-I

TYPICAL SECTION J-J TYPICAL SECTION K-K

TYPICAL SECTION M-MTYPICAL SECTION L-L
05/23/2023 C7 91 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
MA
T
C
H
L
I
N
E

S
T
A
.

1 8
+
1 5
.
0 0
SE
E

S
H
E
E
T

10 9
05/23/2023 C7 92 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
14 05/23/2023 C7 93 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
15 05/23/2023 C7 94 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
MA
T
C
H
L
I
N
E

S
T
A
.

1 8
+
8 0
.
0 0
SE
E

S
H
E
E
T

21 19
05/23/2023 C7 95 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
20 MA
T
C
H
L
I
N
E

S
T
A
.

1 8
+
8 0
.
0 0
SE
E

S
H
E
E
T

2 2

LEUCADIA BLVD
05/23/2023 C7 96 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
26 DRIVEWAY
DETAIL
05/23/2023 C7 97 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
27 DIRECTIONAL ADA CURB RAMP
05/23/2023 C7 98 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
32 18+90 DRIVEWAY17+40 DRIVEWAY
16+86 DRIVEWAY 18+22 DRIVEWAY
17+75 DRIVEWAY 16+40 DRIVEWAY
20+00 DRIVEWAY
05/23/2023 C7 99 of 201

80 85
90 95
100
105
110
115
120
80 85
90 95
100
105
110
115
120
DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
33 RW 1
05/23/2023 C7 100 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
38 ”

BLOW OFF PIPEA
05/23/2023 C7 101 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
41 05/23/2023 C7 102 of 201

90 95
100
105
110
115
90 95
100
105
110
115
80 85
90 95
100
105
110
115
PLAN

SECTION A-A

SECTION B-B
NOTES:

ANCHOR DETAIL
DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
42 STORM DRAINS 1, 3, AND 4 STORM DRAIN 2
80 85
90 95
100
105
110
115

SIDEWALK UNDER DRAINA
05/23/2023 C7 103 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
44 CONSTRUCTION NOTESLEGEND

TYPICAL ROUNDABOUT CROSSWALK DETAIL
05/23/2023 C7 104 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
46 SIGN LEGEND
LIMIT

INTERSECTION EXTENSION GREEN BIKE

LANE CONFLICT MARKING DETAIL

TYPICAL DIAGONAL BUFFER

HATCHING

BIKE LANE WITH ARROW PAVEMENT

MARKING DETAIL
SIGNING AND STRIPING GENERAL NOTES:

LEGEND

WHITE YIELD DETAIL
05/23/2023 C7 105 of 201

M
A
T
C
H
L
I
N
E

S
T
A
.

1 8
+
7 5
S
E
E

S
H
E
E
T

4 7
DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
48 MA
T
C
H
L
I
N
E

S
T
A
.

2 3
+
7 5
SE
E

S
H
E
E
T

49 05/23/2023 C7 106 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
50 05/23/2023 C7 107 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
52 DETAIL A
CONSTRUCTION NOTES:

LEGEND
(SIDE VIEW) POST-MOUNT TRANSFORMER DETAIL
05/23/2023 C7 108 of 201

DRAWING NO.

SHEET OF 74

CITY OF ENCINITAS - DEVELOPMENT SERVICES DEPARTMENTENGINEERING DIVISION APPROVALSBENCHMARK LEUCADIA BLVD @ HYGEIA AVE
CITY OF ENCINITAS SI-126

AS-BUILT APPROVALS
M
A
T
C
H
L
I
N
E

S
T
A
.

1 8
+
7 5

-

S
E
E

S
H
E
E
T

L
2 .
1 SEE SHEET L2.4 FOR PLANT LEGEND

LEUCADIA BLVD
H
Y
G
E
I
A

A
V
E
F
U
L
V
I
A

S
T
L2.2
PLANTING PLAN FOR:
64 MA
T
C
H
L
I
N
E

S
T
A
.

2 3
+
7 5

-

S
E
E

S
H
E
E
T

L
2 .
3 05/23/2023 C7 109 of 201

Item No.Item Unit Approx.

Quantity Unit Price Amount
General
1 Mobilization/Demobilization LS 1 $325,000.00 $325,000.00 2 Progress Schedule LS 1 $27,500.00 $27,500.00
3 Storm Water Pollution Prevention and Erosion Control LS 1 $70,000.00 $70,000.00 4 Traffic Control LS 1 $130,000.00 $130,000.00
5 Clearing and Grubbing LS 1 $358,045.00 $358,045.00
6 Unclassified Excavation CY 1,055 $85.00 $89,675.00
7 Signing and Striping LS 1 $79,015.00 $79,015.00
8 Install Landscape and Irrigation Improvements w/ 90 day Maintenance Period LS 1 $215,000.00 $215,000.00 Sub Total $1,294,235.00
Improvements
9 Construct 6" Concrete Curb and Gutter Type G per SDRSD G-02 LF 1,850 $40.00 $74,000.00 10 Construct Thickened Concrete Curb and Gutter LF 50 $45.00 $2,250.00 11 Construct 6" Median Curb Type B-1 per SDRSD G-06 LF 750 $25.00 $18,750.00 12 Construct BMP Curb Cut Inlet EA 3 $40.00 $120.00
13 Construct BMP Curb Cut Outlet EA 2 $40.00 $80.00
14 Construct Mountable Concrete Curb LF 150 $30.00 $4,500.00 15 Construct Concrete Flush Header Curb LF 220 $25.00 $5,500.00 16 Construct 4" Thick Colored and Stamped Concrete Sidewalk per SDRSD G-07 SF 4,865 $25.00 $121,625.00 17 Construct 4" Thick Colored Concrete Sidewalk per SDRSD G-07 SF 4,630 $20.00 $92,600.00 18 Construct Colored Concrete ADA Curb Ramp (All Types) with Truncated Domes EA 9 $3,750.00 $33,750.00 19 Construct Colored Concrete Type A ADA Passageway per Caltrans Std Plan A88B with Truncated Domes SF 325 $45.00 $14,625.00
20 Construct Colored Concrete Bike Ramp EA 5 $3,000.00 $15,000.00 21 Construct Concrete Residential Driveway per SDRSD G-14C SF 4,710 $20.00 $94,200.00 22 Construct Concrete Cross Gutter per SDRSD G-12 SF 575 $25.00 $14,375.00 23 Construct 80mm Pavers SF 1,875 $45.00 $84,375.00
24 Place Class II Aggregate Base CY 1,365 $85.00 $116,025.00 25 Place HMA Pavement TON 840 $210.00 $176,400.00
26 Place Slurry Seal SY 5,305 $6.00 $31,830.00
27 Place Mirafi RS380i, or Approved Equal, Geosynthetic SY 960 $5.00 $4,800.00 28 Place Mirafi MPM30 (PGM-30), or Approved Equal, Paving Interlayer SY 360 $8.00 $2,880.00 29 Construct Masonry Retaining Wall SF 7,230 $70.00 $506,100.00 30 Construct Masonry Pilaster EA 34 $5,000.00 $170,000.00 31 Construct Cable Railing per Caltrans Std Plan B11-47 with Steel Coating LF 465 $65.00 $30,225.00 32 Furnish and Install Pedestrian Gate EA 1 $4,000.00 $4,000.00 33 Construct Chain Link Fence per SDRSD M-06 LF 120 $55.00 $6,600.00 34 Construct PIP Colored Concrete Wall SF 265 $85.00 $22,525.00 35 Construct Colored Concrete Retaining Wall per SDRSD C-09 (All Types) with Skate Stoppers SF 375 $65.00 $24,375.00
36 Construct Colored Concrete Planter Wall LF 65 $50.00 $3,250.00 Water Improvements
37 Construct 3/4" Type K Copper Water Service per SDWAS Dwg No WS-01 LF 60 $65.00 $3,900.00 38 Construct 6" Fire Hydrant Lateral Connection per SDWAS Dwg No WF-01 EA 1 $8,000.00 $8,000.00 39 Construct 8" C900 PVC Water Main w/ Restrained Joints LF 125 $150.00 $18,750.00 40 Construct 12" C900 PVC Water Main w/ Restrained Joints LF 335 $170.00 $56,950.00 41 Construct 2" Manual Air Valve per SDWAS Dwg No WA-01 EA 3 $4,000.00 $12,000.00 Drainage Improvements
42 Construct Type A Storm Drain Cleanout Per SDRSD D-09 EA 3 $9,500.00 $28,500.00 43 Construct Type B-1 Curb Inlet per SDRSD D-02 EA 2 $24,000.00 $48,000.00 44 Construct Type G-2 Catch Basin per SDRSD D-08 EA 1 $7,500.00 $7,500.00 45 Construct Type F Catch Basin per SDRSD D-07 EA 1 $9,000.00 $9,000.00 46 Construct 18" x 18" Concrete Catch Basin EA 2 $2,000.00 $4,000.00 47 Construct 4" Round Brow Ditch Drain EA 1 $1,000.00 $1,000.00 48 Construct Concrete Brow Ditch (All Types)LF 265 $40.00 $10,600.00 49 Construct Vegetated BMP SF 755 $55.00 $41,525.00
50 Construct 3" PVC Drain Pipe Outlet per SDRSD D-27 LF 65 $60.00 $3,900.00 51 Construct 8" PVC Storm Drain LF 60 $90.00 $5,400.00
52 Construct 12" PVC Storm Drain LF 5 $110.00 $550.00
53 Construct 18" RCP Storm Drain LF 230 $240.00 $55,200.00 54 Construct Pipe Collar per SDRSD D-62 EA 1 $2,800.00 $2,800.00 55 Furnish and Install Kor 'n Tee or Approved Equal EA 6 $1,000.00 $6,000.00 Lighting Improvements
56 Furnish and Install New Light Pole and Fixture EA 13 $7,500.00 $97,500.00 57 Furnish and Install New Low Voltage / Up Light EA 10 $1,000.00 $10,000.00 58 Furnish and Install Service Pedestal EA 1 $10,000.00 $10,000.00 59 Furnish and Install Pedestrian Push Button and Pole EA 8 $2,500.00 $20,000.00 60 Furnish and Install Rectangular Rapid Flashing Beacon System EA 4 $17,500.00 $70,000.00 61 Furnish and Install Pull Boxes, Conduit, Conductors LS 1 $35,000.00 $35,000.00 Subtotal $2,240,835.00
Construction Total $3,535,070.00

12.5% Contingency $441,883.75
Project: TOTAL $3,976,953.75
City of Encinitas
100% SUMMARY OF PROBABLE CONSTRUCTION COST
Date: March 20, 2020
FOR THE CONSTRUCTION OF:

Leucadia Blvd Roundabout Improvements
Leucadia Blvd Roundabout
100% OPCC Page 105/23/2023 C7 110 of 201

Item No.Item Unit Approx.

Quantity Unit Price Amount
General
1 Mobilization/Demobilization LS 1 $50,000.00 $50,000.00 2 Progress Schedule LS 1 $12,500.00 $12,500.00
3 Storm Water Pollution Prevention and Erosion Control LS 1 $20,000.00 $20,000.00 4 Traffic Control LS 1 $20,000.00 $20,000.00
5 Clearing and Grubbing
Full Depth HMA Pavement Section Removal SF 4,115 $3.25 $13,373.75 Remove Concrete Sidewalk SF 115 $3.25 $373.75
Remove Landscape SF 3,545 $3.25 $11,521.25
Remove HMA Dike LF 395 $3.25 $1,283.75
Remove Concrete Curb and Gutter LF 50 $3.25 $162.50
Remove Chain Link Fence and Foundations LF 250 $5.00 $1,250.00 Remove Block Wall LF 7 $5.00 $35.00
Sawcut LF 470 $2.00 $940.00
Adjust Water Valve EA 3 $750.00 $2,250.00
Adjust to Grade At&t Handhole EA 1 $1,000.00 $1,000.00
Relocate Fire Hydrant EA 2 $2,500.00 $5,000.00
6 Unclassified Excavation
Subgrade Preparation SF 4,980 $1.00 $4,980.00
Fine Grading SF 8,525 $0.35 $2,983.75
Unclassified Excavation CY 320 $5.00 $1,600.00
Export CY 60 $65.00 $3,900.00
7 Signing and Striping LS 1 $12,000.00 $12,000.00
8 Install Landscape and Irrigation Improvements w/ 90 day Maintenance Period LS 1 $25,000.00 $25,000.00 Sub Total $190,153.75
Improvements
9 Construct 6" Concrete Curb and Gutter Type G per SDRSD G-02 LF 455 $40.00 $18,200.00 10 Construct 6" Concrete Median Curb per SDRSD G-06 LF 10 $25.00 $250.00 11 Construct 4" Thick Colored Concrete Sidewalk per SDRSD G-07 SF 2,420 $20.00 $48,400.00 12 Construct Colored Concrete ADA Curb Ramp (All Types) with Truncated Domes EA 1 $3,750.00 $3,750.00 13 Construct Colored Concrete Bike Ramp EA 1 $3,000.00 $3,000.00 14 Construct Concrete Cross Gutter per SDRSD G-12 SF 575 $25.00 $14,375.00 15 Place Class II Aggregate Base CY 75 $85.00 $6,375.00 16 Place HMA Pavement TON 50 $210.00 $10,500.00
17 Place Slurry Seal SY 1,685 $6.00 $10,110.00
18 Place Mirafi MPM30 (PGM-30), or Approved Equal, Paving Interlayer SY 160 $8.00 $1,280.00 19 Construct Masonry Retaining Wall SF 1,530 $70.00 $107,100.00 20 Construct Cable Railing per Caltrans Std Plan B11-47 with Steel Coating LF 265 $65.00 $17,225.00 21 Construct Chain Link Fence per SDRSD M-06 LF 120 $55.00 $6,600.00 Drainage Improvements
22 Construct 3" PVC Storm Drain LF 12 $60.00 $720.00
23 Lighting Improvements
Furnish and Install New Light Pole and Fixture EA 2 $7,500.00 $15,000.00 Furnish and Install Pull Box EA 2 $750.00 $1,500.00
Construct Conduit and Conductors LF 250 $20.00 $5,000.00 Subtotal $269,385.00
Construction Total $459,538.75

12.5% Contingency $57,442.34
Project: TOTAL $516,981.09
City of Encinitas
100% SUMMARY OF PROBABLE CONSTRUCTION COST
Date: March 20, 2020
FOR THE CONSTRUCTION OF:

Leucadia Blvd Roundabout Improvements - Fulvia to Hymettus Leucadia Blvd Roundabout
100% OPCC Page 105/23/2023 C7 111 of 201

Prepared for:

City of Encinitas
Prepared by:
3900 Fifth Avenue, Suite 310
San Diego, CA 92103
Leucadia @ Hygeia Roundabout
Green Street Report
May, 2020
05/23/2023 C7 112 of 201

3900 Fifth Avenue, Suite 310
San Diego, CA 92103
619-795-6086

Green Street Report

_________________________________________________
Ross P. Duenas, P.E. RCE 84324 EXP: 09-30-21

3900 Fifth Avenue, Suite 310
San Diego, CA 92103

For
City of Encinitas

05/23/2023 C7 113 of 201

3 3900 Fifth Avenue, Suite 310
San Diego, CA 92103
619-795-6086

Table of Contents

1.0 PROJECT DESCRIPTION ............................................................................................................4

2.0 GREEN STREET APPROACH ......................................................................................................4

3.0 LAND USE SUMMARY ..............................................................................................................4

4.0 GREEN STREET ELEMENTS IMPLEMENTED ................................................................................5

05/23/2023 C7 114 of 201

4 3900 Fifth Avenue, Suite 310
San Diego, CA 92103
619-795-6086

1.0 PROJECT DESCRIPTION
This project area encompasses approximately 1.27 acres of residential land use, landscape and roadway along Leucadia Blvd between Hermes Ave and Fulvia St . The project area also extends approximately 125 feet to the north and 150 feet to the south along Hygeia. The project proposes a roundabout at the intersection of Hygeia Ave and Leucadia Blvd, concrete sidewalks along Leucadia Blvd, drainage and green street facilities, and landscaping

2.0 GREEN STREET APPROACH
Per the City of Encinitas Engineering Design Manual dated February 2016, the project will be PDP exempt by following the USEPA Green Street guidance set forth in the “Managing Wet Weather with Green Infrastructure – Municipal Handbook: Green Streets”. This manual describes various green street design methodologies that can be implemented along streetscape projects. The first design implementation utilized is the layout and location of the pervious areas throughout the corridor. The pervious area layout was designed to minimized impervious area, respect the existing hydrologic functions of the land, while also providing safe routes of travel. The high concentration of proposed pervious planters throughout the corridor will provide source control of storm water and reduce the transport of pollutants to the existing storm drain system. The pervious area layout separates otherwise hydraulically connected impervious areas with planters, such as detached sidewalks, as well as planted street trees. The project will also incorporate two (2) bioretention basins along Leucadia Blvd. These basins will utilize curb cuts for the entrance and exit of storm water runoff. There is also a third proposed basin located behind the curb return at the northwest corner of the Leucadia/Hygeia intersection. This basin has an outflow structure to discharge runoff to the storm drain system. The basins will incorporate native soils, planted vegetation, be irrigated, and lined with impermeable membranes. The infiltration rate for the underlying native soil was tested and determined to be between 0.67 in/hr and 1.94 in/hr.

3.0 LAND USE SUMMARY
Existing land use Proposed land use Difference
Total Project
Area
55,301 SQFT 55,301 SQFT -
Total Pervious
Area
17,889 SQFT 19,640 SQFT +1,751 SQFT
Total Impervious
area
37,412 SQFT 35,661 SQFT -1,751 SQFT

05/23/2023 C7 115 of 201

5 3900 Fifth Avenue, Suite 310
San Diego, CA 92103
619-795-6086

4.0 GREEN STREET ELEMENTS IMPLEMENTED
Below is a list of Green Street Elements Implemented in the proposed design:

1. Minimization of Impervious area (net reduction)

2. Bioretention

3. Street Trees

4. Impervious Area Dispersion (detached sidewalk)

See Appendix A for an exhibit showing BMP locations and for associated fact sheets. Also included in Appendix A are standard BMP sizing calculations for the proposed bioretention areas.

05/23/2023 C7 116 of 201

LEUCADIA AT HYGEIA ROUNDABOUT

EXISTING PERVIOUS AREA EXHIBIT
5/14/2020
Sheet 1 of 105/23/2023 C7 117 of 201

DA 2
92,846 SF
DA 1
4,101 SF
DA 3
96,668 SF

LEUCADIA AT HYGEIA ROUNDABOUT

PROPOSED BMP EXHIBIT
5/29/2020
Sheet 1 of 105/23/2023 C7 118 of 201

Category #Description i ii iii iv v vi vii viii ix x Units 1 Drainage Basin ID or Name 1 2 3 unitless
2 85th Percentile 24-hr Storm Depth 0.60 0.60 0.60 inches 3 Impervious Surfaces Not Directed to Dispersion Area (C=0.90) 1,612 3,330 11,773 sq-ft 4 Semi-Pervious Surfaces Not Serving as Dispersion Area (C=0.30)sq-ft 5 Engineered Pervious Surfaces Not Serving as Dispersion Area (C=0.10)sq-ft 6 Natural Type A Soil Not Serving as Dispersion Area (C=0.10)sq-ft 7 Natural Type B Soil Not Serving as Dispersion Area (C=0.14)sq-ft 8 Natural Type C Soil Not Serving as Dispersion Area (C=0.23)sq-ft 9 Natural Type D Soil Not Serving as Dispersion Area (C=0.30)sq-ft 10 Does Tributary Incorporate Dispersion, Tree Wells, and/or Rain Barrels?No No No No No No No No No No yes/no 11 Impervious Surfaces Directed to Dispersion Area per SD-B (Ci=0.90) sq-ft 12 Semi-Pervious Surfaces Serving as Dispersion Area per SD-B (Ci=0.30)sq-ft 13 Engineered Pervious Surfaces Serving as Dispersion Area per SD-B (Ci=0.10)sq-ft 14 Natural Type A Soil Serving as Dispersion Area per SD-B (Ci=0.10)sq-ft 15 Natural Type B Soil Serving as Dispersion Area per SD-B (Ci=0.14)sq-ft 16 Natural Type C Soil Serving as Dispersion Area per SD-B (Ci=0.23)sq-ft 17 Natural Type D Soil Serving as Dispersion Area per SD-B (Ci=0.30)sq-ft 18 Number of Tree Wells Proposed per SD-A #
19 Average Mature Tree Canopy Diameter ft
20 Number of Rain Barrels Proposed per SD-E #
21 Average Rain Barrel Size gal
22 Total Tributary Area 1,612 3,330 11,773 0 0 0 0 0 0 0 sq-ft 23 Initial Runoff Factor for Standard Drainage Areas 0.90 0.90 0.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 unitless 24 Initial Runoff Factor for Dispersed & Dispersion Areas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 unitless 25 Initial Weighted Runoff Factor 0.90 0.90 0.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 unitless 26 Initial Design Capture Volume 73 150 530 0 0 0 0 0 0 0 cubic-feet 27 Total Impervious Area Dispersed to Pervious Surface 0 0 0 0 0 0 0 0 0 0 sq-ft 28 Total Pervious Dispersion Area 0 0 0 0 0 0 0 0 0 0 sq-ft 29 Ratio of Dispersed Impervious Area to Pervious Dispersion Area n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a ratio 30 Adjustment Factor for Dispersed & Dispersion Areas 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 ratio 31 Runoff Factor After Dispersion Techniques 0.90 0.90 0.90 n/a n/a n/a n/a n/a n/a n/a unitless 32 Design Capture Volume After Dispersion Techniques 73 150 530 0 0 0 0 0 0 0 cubic-feet 33 Total Tree Well Volume Reduction 0 0 0 0 0 0 0 0 0 0 cubic-feet 34 Total Rain Barrel Volume Reduction 0 0 0 0 0 0 0 0 0 0 cubic-feet 35 Final Adjusted Runoff Factor 0.90 0.90 0.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 unitless 36 Final Effective Tributary Area 1,451 2,997 10,596 0 0 0 0 0 0 0 sq-ft 37 Initial Design Capture Volume Retained by Site Design Elements 0 0 0 0 0 0 0 0 0 0 cubic-feet 38 Final Design Capture Volume Tributary to BMP 73 150 530 0 0 0 0 0 0 0 cubic-feet False
False
Automated Worksheet B.1: Calculation of Design Capture Volume (V2.0) Dispersion
Area, Tree Well
& Rain Barrel
Inputs
(Optional)
Standard
Drainage Basin
Inputs
Results
Tree & Barrel
Adjustments
Initial Runoff
Factor
Calculation
Dispersion
Area
Adjustments
No Warning Messages
05/23/2023 C7 119 of 201

Category #Description i ii iii iv v vi vii viii ix x Units 1 Drainage Basin ID or Name 1 2 3 -------unitless
2 85th Percentile Rainfall Depth 0.60 0.60 0.60 -------inches 3 Predominant NRCS Soil Type Within BMP Location D D D unitless 4 Is proposed BMP location Restricted or Unrestricted for Infiltration Activities? Unrestricted Unrestricted Unrestricted unitless 5 Nature of Restriction unitless
6 Do Minimum Retention Requirements Apply to this Project?No No No Yes Yes Yes Yes Yes Yes Yes yes/no 7 Are Habitable Structures Greater than 9 Stories Proposed?yes/no 8 Has Geotechnical Engineer Performed an Infiltration Analysis?Yes Yes Yes yes/no 9 Design Infiltration Rate Recommended by Geotechnical Engineer 0.950 0.500 0.500 in/hr 10 Design Infiltration Rate Used To Determine Retention Requirements 0.950 0.500 0.500 -------in/hr 11 Percent of Average Annual Runoff that Must be Retained within DMA 0.0%0.0%0.0%-------percentage 12 Fraction of DCV Requiring Retention 0.00 0.00 0.00 -------ratio 13 Required Retention Volume 0 0 0 -------cubic-feet
-Retention requirements have been omitted in these calculations. Such an omission is only be acceptable for Green Street projects or projects that submit supplemental calculations demonstrating retention requirements are satisfied at the project-level.

False
Automated Worksheet B.2: Retention Requirements (V2.0)
Advanced
Analysis
Basic Analysis
Result
Attention!
05/23/2023 C7 120 of 201

Category #Description i ii iii iv v vi vii viii ix x Units 1 Drainage Basin ID or Name 1 2 3 -------sq-ft
2 Design Infiltration Rate Recommended 0.950 0.500 0.500 -------in/hr 3 Design Capture Volume Tributary to BMP 73 150 530 -------cubic-feet 4 Is BMP Vegetated or Unvegetated?Vegetated Vegetated Vegetated unitless 5 Is BMP Impermeably Lined or Unlined?Unlined Unlined Unlined unitless 6 Does BMP Have an Underdrain?No Underdrain No Underdrain No Underdrain unitless 7 Does BMP Utilize Standard or Specialized Media?Standard Standard Standard unitless 8 Provided Surface Area 225 90 433 sq-ft
9 Provided Surface Ponding Depth 6 12 12 inches
10 Provided Soil Media Thickness 18 18 18 inches
11 Provided Gravel Thickness (Total Thickness)24 24 24 inches 12 Underdrain Offset inches
13 Diameter of Underdrain or Hydromod Orifice (Select Smallest)inches 14 Specialized Soil Media Filtration Rate in/hr
15 Specialized Soil Media Pore Space for Retention unitless 16 Specialized Soil Media Pore Space for Biofiltration unitless 17 Specialized Gravel Media Pore Space unitless
18 Volume Infiltrated Over 6 Hour Storm 73 23 108 0 0 0 0 0 0 0 cubic-feet 19 Ponding Pore Space Available for Retention 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 unitless 20 Soil Media Pore Space Available for Retention 0.25 0.25 0.25 0.05 0.05 0.05 0.05 0.05 0.05 0.05 unitless 21 Gravel Pore Space Available for Retention (Above Underdrain)0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 unitless 22 Gravel Pore Space Available for Retention (Below Underdrain)0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 unitless 23 Effective Retention Depth 20.10 26.10 26.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 inches 24 Fraction of DCV Retained (Independent of Drawdown Time)6.16 1.46 1.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ratio 25 Calculated Retention Storage Drawdown Time 21 52 52 0 0 0 0 0 0 0 hours 26 Efficacy of Retention Processes #N/A 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ratio 27 Volume Retained by BMP (Considering Drawdown Time)#N/A 150 530 0 0 0 0 0 0 0 cubic-feet 28 Design Capture Volume Remaining for Biofiltration #N/A 0 0 0 0 0 0 0 0 0 cubic-feet 29 Max Hydromod Flow Rate through Underdrain 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 cfs 30 Max Soil Filtration Rate Allowed by Underdrain Orifice 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 in/hr 31 Soil Media Filtration Rate per Specifications 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 in/hr 32 Soil Media Filtration Rate to be used for Sizing 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 in/hr 33 Depth Biofiltered Over 6 Hour Storm 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 inches 34 Ponding Pore Space Available for Biofiltration 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 unitless 35 Soil Media Pore Space Available for Biofiltration 0.00 0.00 0.00 0.20 0.20 0.20 0.20 0.20 0.20 0.20 unitless 36 Gravel Pore Space Available for Biofiltration (Above Underdrain)0.00 0.00 0.00 0.40 0.40 0.40 0.40 0.40 0.40 0.40 unitless 37 Effective Depth of Biofiltration Storage 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 inches 38 Drawdown Time for Surface Ponding 6 24 24 0 0 0 0 0 0 0 hours 39 Drawdown Time for Effective Biofiltration Depth 0 0 0 0 0 0 0 0 0 0 hours 40 Total Depth Biofiltered 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 inches 41 Option 1 - Biofilter 1.50 DCV: Target Volume #N/A 0 0 0 0 0 0 0 0 0 cubic-feet 42 Option 1 - Provided Biofiltration Volume #N/A 0 0 0 0 0 0 0 0 0 cubic-feet 43 Option 2 - Store 0.75 DCV: Target Volume #N/A 0 0 0 0 0 0 0 0 0 cubic-feet 44 Option 2 - Provided Storage Volume #N/A 0 0 0 0 0 0 0 0 0 cubic-feet 45 Portion of Biofiltration Performance Standard Satisfied #N/A 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ratio 46 Do Site Design Elements and BMPs Satisfy Annual Retention Requirements?#N/A Yes Yes -------yes/no 47 Overall Portion of Performance Standard Satisfied (BMP Efficacy Factor)#N/A 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ratio 48 Deficit of Effectively Treated Stormwater #N/A 0 0 n/a n/a n/a n/a n/a n/a n/a cubic-feet Biofiltration
Calculations
False
False
False
False
Result
False
False
No Warning Messages
Retention
Calculations
Automated Worksheet B.3: BMP Performance (V2.0)
False
False
BMP Inputs
05/23/2023 C7 121 of 201

!"#
!"#$%&'()
$"#)'%#*+(!,"#%-%#*$%&'!
!"#$%&'%()*+&(,-#.&%/-#0 1234-+"2".05 6789:;)<
05/23/2023 C7 122 of 201

H-2

PART 2

CONSTRUCTION MATERIALS

SECTION 200 - ROCK MATERIALS

200-1 ROCK PRODUCTS. ADD the following Subsection:

200-1.7 Biofiltration Soil Media
200-1.7.1 General
Bioretention Soil Media (BSM) is intended to filter storm water and support plant growth while minimizing the leaching of potential pollutants. This specification includes requirements that apply to BSM used in stormwater treatment BMPs.

A summary of BSM specification requirements is included in Table 1.

Table 1. BSM Specification Requirement Summary
Component Requirement
BSM Material Composition Sand: 60-80% by volume
Topsoil: 0-20% by volume
Compost: 0-20% by volume
Alternative Blends Acceptable but they must meet performance- based specifications.

Sand Type Washed sand conforming to particle size
distribution
Topsoil Type Sandy loam or loamy sand with clay < 15% and gravel < 25%
Compost Type From a CalRecycle permitted facility. Biosolids derived materials are not acceptable
BSM Permeability 8 to 24-inches/hour for BMPs; testing is required to demonstrate.

Agronomic Suitability
Requirements
Limits for salts and potential toxins. C:N ratio
between 15 and 40.

Water Quality Related Limits Requirements related to specific pollutants when water quality of receiving waters is impaired for
those pollutants.

Blended BSM shall consist of 60% to 80% by volume sand, up to 20% by volume topsoil, and up to 20% by volume compost. Sand, Topsoil, and Compost used in BSM shall conform to requirements listed herein, respectively.
05/23/2023 C7 123 of 201

H-3

Alternative mix components and proportions may be utilized, provided that the whole blended mix conforms to whole BSM criteria. Alternative mix designs may include alternative proportions and/or alternative organic amendments. Alternative mixes are subject to approval by the Engineer. 200-1.7.2 Submittals
At least thirty (30) days prior to ordering materials, the Contractor shall submit the following to the Engineer:
• Source/supplier of BSM
• Location of source/supplier
• A physical sample of the BSM
• BSM test results from a third-party independent laboratory • Test results for individual component materials as required • Description of proposed methods and schedule for mixing, delivery, and placement of BSM.

The test results shall be no older than 120 days and shall accurately represent the materials and feed stocks that are currently available from the supplier. 200-1.7.3 Quality Assurance
Close adherence to the material quality controls herein are necessary in order to support healthy vegetation, minimize pollutant leaching, and assure sufficient permeability to infiltrate/filter runoff during the life of the facility. Amendments may be included to adjust agronomic properties.

Acceptance of the material will be based on test results certified to be representative. Test results shall be conducted no more than 120 days prior to delivery of the blended BSM to the project site.

For projects installing more than 100 cubic yards of BSM, batch-specific tests of the blended mix shall be provided to the Engineer for every 100 cubic yards of BSM along with a site plan showing the placement locations of each BSM batch within the facility.

Test results shall demonstrate conformance to agronomic suitability and hydraulic suitability criteria listed herein. No delivery, placement, or planting of BSM shall begin until test results confirm the suitability of the BSM. The Contractor shall submit a written request for approval which shall be accompanied by written analysis results from a written report of a testing agency. The testing agency must be registered by the State for agronomic soil evaluation laboratory test fees shall be paid for by the Contractor.
200-1.7.4 Agronomic Suitability
The BSM shall conform to the requirements herein to support plant growth. BSM which requires amending to comply with the below specifications shall be uniformly blended and tested in its blended state prior to testing and delivery:
a) pH range shall be between 6.0-8.5.
b) Salinity shall be between 0.5 and 3.0 millimho/cm (as measure by electrical conductivity) c) Sodium absorption ratio (SAR) shall be less than 5.0 d) Chloride shall be less than 800 ppm.
e) Cation exchange capacity shall be greater than 10 meq/100 g. f) Organic matter shall be between 2 and 5%.
g) Carbon:Nitrogen ratio shall be between 15 and 40.

Textural class fraction shall adhere to limits in Table 2, as determined by ASTM Method D422 or an approved alternative method:
05/23/2023 C7 124 of 201

H-4

Table 2. Textural Class Fraction
Textural Class
(ASTM D422) Size Range Mass Fraction
(percent)
Gravel Larger than 2 mm 0 to 25 of total sample
Clay Smaller than 0.005 mm 0 to 5 of non-gravel
fraction
Test results shall show the following information:
a) Date of testing
b) Project name, contractor name, and source of materials and supplier name c) Copies of all testing reports including, at a minimum, analytical results sufficient to confirm compliance with all requirements listed in this section. 200-1.7.5 Hydraulic Suitability
BSM shall have the appropriate hydraulic properties for filtering stormwater. BSM which requires amending, shall be uniformly blended and tested in its blended state prior to testing and delivery. 200-1.7.6 Testing
The saturated hydraulic conductivity of the whole BSM shall be measured according to the method detailed in the measurement of hydraulic conductivity (USDA Handbook 60, method 34b), commonly available as part of standard agronomic soil evaluation, or ASTM D24234 Permeability of Granular Soils (at approximately 85% relative compaction Standard Proctor, ASTM D698).

BSM shall conform to hydraulic criteria associated with the BMP design configuration that best applies to the facility where the BSM will be installed. 200-1.7.7 Systems without Underdrains
The BSM shall have a hydraulic conductivity of at least 5-inches per hour, or at least 2 times higher than the design infiltration rate of the underlying soil, whichever is greater. 200-1.7.8 Compost Testing
Compost shall meet the following requirements as demonstrated through standard agronomic testing methods:
a) Carbon to Nitrogen (C:N) ratio. C:N shall be between 15:1 and 40:1, preferably above 20:1 to reduce the potential for nitrogen leaching/washout. b) pH. pH shall be between 6.0 and 8.5.
c) Soluble Salt Concentration. Soluble Salt Concentration shall be less than 10 dS/m. (Method TMECC 4.10-A, USDA and U.S. Composting Council). d) Stability. Carbon Dioxide evolution rate shall be less than 3.0 mg CO2-C per g compost organic matter (OM) per day or less than 6 mg CO2-C per g compost carbon per day, whichever unit is reported. (Method TMECC 5.08-B, USDA and U.S. Composting Council). Alternatively, a Solvita rating of 5.5 or higher is acceptable.

05/23/2023 C7 125 of 201

H-5

200-1.7.9 Pathogens and Pollutant Limits
Select pathogens shall pass US EPA Class A standard, 40 CFR Section 503.32(a). Trace Metals shall pass US EPA Class A standard, 40 CFR Section 503.13, Table 1 for Ceiling Concentrations. 200-1.7.10 Sand for BSM
Sand used in BSM shall be washed prior to delivery and meet sieve analysis requirements in Table 5.

A sieve analysis shall be performed in accordance with California Test 202, ASTM D 422, or approved equivalent method to demonstrate compliance with the gradation limits shown in Table

5. Fines passing the No. 200 sieve shall be non-plastic.

Table 5. Sand Gradation Limits
Percentage Passing Sieve (by weight)
Sieve Size (ASTM D422) Minimum Maximum
3/8-inch 100 100
#4 90 100
#8 70 100
#16 40 95
#30 15 70
#40 5 55
#100 0 15
#200 0 5
200-1.7.11 Topsoil for BSM
Topsoil shall be free of hazardous materials and shall be consistent with a common definition of topsoil. Decomposed granite and derivatives of decomposed granite are not considered to be topsoil for the purpose of this specification.

Topsoil shall be classified as a sandy loam or a loamy sand according to the US Department of Agriculture soil classification system. In addition, a textural class analysis shall be performed in accordance with ASTM D422, or an approved alternative method to demonstrate compliance with the gradation limits in Table 6.

Table 6. Topsoil Textural Class
Textural Class (ASTM
D422)
Size Range Mass Fraction (percent)
Gravel Larger than 2 mm 0 to 25 of total sample
Clay Smaller than 0.005 mm 0 to 15 of non-gravel
fraction

05/23/2023 C7 126 of 201

H-6

200-1.7.12 Compost for BSM
Compost shall be produced at a facility inspected and regulated by the local enforcement agency for CalRecycle. Compost should also preferably be certified by the U.S. Composting Council’s Seal of Testing Assurance Program (USCC STA) or an approved equivalent program. Compost shall not be produced from biosolids feedstock.

A sieve analysis shall be performed in accordance with ASTM D 422 or approved equivalent method to demonstrate compliance with the gradation limits show in Table 7.

Table 7. Compost Gradation Limits
Sieve Size (ASTM D422) Percent Passing Sieve (by weight) 1/2” 97 to 100
#10 40 to 90

Organic Material Content shall be 35% to 100% by dry weight and moisture shall be 25% to 60% wet weight basis. Physical contaminants (manmade inert materials) shall not exceed 1% by dry weight.

ADD the following Subsection:

200-1.8 Rock and Sand Materials for BMP Drainage Layers 200-1.8.1 General
All sand and stone products used in BMP drainage layers shall be clean and thoroughly washed.

200-1.8.2 Filter Course
Graded aggregate choker material is installed as a filter course to separate the BSM from the drainage rock reservoir layer. The purpose of this layer is to limit migration of sand or other fines from the BSM. The filter course shall consist of two layers of choking material increasing in particle size. The top layer (closest to the BSM) of the filter course shall be constructed of thoroughly washed ASTM C33 Choker Sand as detailed in Table 200-1.5.5 of the Standard Specifications.

The bottom layer of the filter course shall be constructed of thoroughly washed ASTM No. 8 aggregate material.

200-1.8.3 Open-Graded Aggregate Stone
Open-graded aggregate material is installed below the filter course layers to provide additional storm water storage capacity. This layer shall be constructed of thoroughly washed ¾” to 1-1/2” open graded gravel. The ¾” to 1-1/2” open graded clean gravel shall conform to the gradation limits contained in Table 200-1.2.1 for 1” material of the Standard Specifications.

200-2 UNTREATED BASE MATERIALS

200-2.2 Crushed Aggregate
Aggregate base material shall be Crushed Aggregate Base that conforms to Section 200-2.2 of the Standard Specifications or Class II Aggregate Base (not recycled base) per the aggregate gradation requirements and quality requirements as called out in Section 26-1.02A of the Caltrans Standard Specifications (2018 Edition).
05/23/2023 C7 127 of 201

H-7

Recycled base (made of reclaimed asphalt concrete, Portland cement concrete, lean concrete base, cement treated base, etc.) shall not be used anywhere on the project. Furthermore, crushed miscellaneous base as called out in Section 200-2.4 in the Standard Specifications shall not be used anywhere on the project.

SECTION 201 - CONCRETE, MORTAR, AND RELATED MATERIALS

201-1 PORTLAND CEMENT CONCRETE. ADD the following:
201-1.1 Requirements
201-1.1.1 General
Contractor shall submit concrete mix designs at least fifteen (15) working days prior to commencement of Work. The same brand, type, and source of cement and aggregate shall be used for all Portland cement concrete.

Concrete mix designs shall conform to ASTM C 94, except as modified herein.

Concrete shall be specified by class per the Standard Specifications with a 4-inch slump. 201-1.1.2 Concrete Specified by Class and Alternate Class. ADD the following:

All Concrete driveways shall be 560-C-3250.

All Stamped and Colored Concrete Type A ADA Passageways shall be 560-C-3250.

All Concrete Cross Gutters shall be 560-C-3250.
201-1.1.5 Tests for Portland Cement Concrete. ADD the following:

1. Concrete quality testing may be performed on the concrete by the City’s representative as follows:
a. Frequency of Sampling: Cast four (4) concrete test cylinders from each 50 cubic yards, or a fraction thereof, of each class of concrete placed in any one day. Sampling and curing of cylinders shall conform to ASTM C 31.
b. Strength Testing: Test cylinders in accordance with ASTM C 39. Test one (1) cylinder at seven (7) days for information, two (2) cylinders at 28 days for acceptance and hold one (1) cylinder for verification. When samples are taken from same concrete delivery, strength acceptance will be based on the average strengths of the two (2) cylinders for verification.

Strength acceptance will be based on the average of the strengths of the two (2) cylinders tested at 28 days. If one (1) cylinder of 28-day test manifests evidence of improper sampling, molding or testing other than low strength, discard it and use the fourth cylinder for the test result.
c. Determine concrete slump by ASTM C 143 with each strength test sampling and as required to establish consistency.
d. Determine air content of the concrete using ASTM C 231 to verify the percentage of air in the concrete immediately prior to depositing in forms.
05/23/2023 C7 128 of 201

H-8

e. If the 28-day strength tests fail to meet the specified minimum compressive strength, the concrete will be assumed to be defective and one (1) set of three (3) cores from each area may be taken as selected by the City’s representative and in accordance with ASTM C 42.

All tests for compressive strength must pass. The City may require additional coring, nondestructive load testing or repair of defective concrete. Costs of coring, testing of cores, load testing and required repairing pertaining thereto, shall be paid by the Contractor at no extra cost to the City.

2. To facilitate concrete sampling and testing, the Contractor shall:
a. Furnish labor to assist the City’s representative in obtaining and handling samples at the project site.
b. Advise the City’s representative 48 hours in advance of concrete placing operations to allow for scheduling and completion of quality testing.
c. Provide and maintain facilities for safe storage and proper curing of concrete test specimens on the project site, as required by ASTM C 31.
201-1.2 Materials
201-1.2.1 Cement. ADD the following:

Cement shall conform to ASTM C 150, Type II, with maximum tricalcium aluminate not to exceed 8%. The maximum percent alkalis shall not exceed 0.6%. 201-1.2.2 Aggregates. ADD the following:

Aggregates shall comply with ASTM C 33 and shall be free from asbestos and any substances that will react with the cement alkalis.
201-1.2.4 Chemical Admixtures. ADD the following:

Concrete shall contain an air-entraining admixture conforming to ASTM C 260, except it shall be non-toxic after 30 days and shall contain no chlorides. Admixture shall be Master Builders MB-AE 10, Sika AER (Sikamix 104) or approved equivalent.

Concrete shall contain a water-reducing admixture conforming to ASTM C 494, Types A or D, except it shall contain no chlorides, shall be non-toxic after 30 days, and shall be compatible with air- entraining admixtures. The amount of admixture to be added to the concrete shall be in accordance with the manufacturer’s written recommendations. Admixture shall be Master Builders Pozzolith polymer-type normal setting, Plastocrete (Sikamix 160) Normal Set, Sika Corporation, or approved equivalent.

Do not use any admixture that contains chlorides or other corrosive elements in any concrete. “High-Early” concrete mixes may be utilized where approved by the Engineer. Calcium Chloride shall not be used.

05/23/2023 C7 129 of 201

H-9

ADD the following Subsection:
201-1.2.7 Colored Concrete
At least fourteen (14) working days prior to the placement of colored concrete flatwork, walls, and stamped colored concrete, the Contractor shall construct at least two (2) test panels with varying amounts of integral colorant and finishing techniques, for each type of finish specified on the Plans. The test panels shall be constructed, finished, and cured with the same materials, tools, equipment, and methods that will be used in placing the colored concrete. At the completion of the curing period, the test panels shall exhibit a color and finish that closely matches the specified condition.

Seven (7) working days after placement of test panels, the Contractor shall request, in writing, that the Engineer review the panels and select the test panel that best matches the design intent. If none of the panels are considered to represent a reasonable match, as determined at the sole discretion of the Engineer, the Contractor shall prepare additional panels in accordance with the above.

The approved test panels shall be the standard of comparison in determining the acceptability of colored, and colored and stamped concrete. Upon successful completion of all colored and colored, and stamped concrete, the test panels may be incorporated into the final product, if approved by the Engineer.

Surrounding exposed surfaces shall be protected during placement, finishing, and curing operations of colored concrete.

Construction of colored, and colored and stamped, concrete shall incorporate integrally colored admixture as identified in the Plans and shall be the following (or equal, as approved by the Engineer):

Manufacturer: L.M. Schofield Company
Series: Chromix Integral Color Admixture
Color:

Stamp:

Adobe Tan (flatwork) and Sudan Brown (walls)
Charcoal relief by Schofield, Garden Stone pattern by
Bomacron [where shown on the Plans]
Curing: Schofield Lithochrome Colorwax

Integral color shall consist of colored admixtures developed for use in ready mixed concrete.

Integral color pigments shall meet or exceed ASTM-C-979. The dosage shall not exceed 10 percent by weight of cementitious material in the concrete mix design. The coloring method shall be designed for concrete flatwork applications, as well as vertical surfaces, and other types of architectural concrete. Pigment shall be a permanent coloration, uniform throughout the concrete surface and interior, and shall be UV and fade resistant. The appearance of the finished colored surface shall be uniform, consistent and free of color variations.

Colored admixture shall be air-entraining and water-reducing, meeting the requirements of ASTM C494, AASHTO M 194, and CRD C87.

The Contractor shall submit technical data and manufacturer's specifications for colored concrete components and a proposed plan for mixing, delivery, placement, stamp pattern, finishing, and curing of the colored, and colored and stamped concrete. This plan shall be submitted to the Engineer for approval at least twenty (20) days prior to constructing the first test panel. 05/23/2023 C7 130 of 201

H-10

The Contractor shall monitor the water content, weight of cementitious materials, and the size, weight, and color of aggregates to maintain consistency and accuracy of the mixed colored concrete. The Contractor shall schedule delivery of concrete to provide consistent mix times from batching until discharge. No water shall be added after a portion of the batch has been discharged.

If more than one concrete pump is used to place concrete, the Contractor shall designate the pumps to receive colored concrete. The designated pumps shall receive only colored concrete throughout the concrete placement operation.

Consistent finishing practices shall be used to ensure uniformity of texture and color.

201-3 EXPANSION JOINT FILLER AND JOINT SEALANTS
201-3.4 Type “A” Sealant (Two-Part Polyurethane Sealant). ADD the following:

All finished concrete surfaces, unless otherwise noted, shall have a ½” continuous expansion joint at locations indicated on the Plans. Expansion joints shall be located either parallel or perpendicular to the curb line, where applicable.

The Contractor shall provide joint sealants that have been produced and installed to establish and to maintain watertight and airtight continuous seals without causing staining or deterioration of joint substrates.

Contractor shall submit product data from the manufacturer of each joint sealant product required, including instructions for joint preparation and joint sealer application. Contractor shall also submit samples for initial selection purposes in form of manufacturer’s standard bead samples, consisting of strips of actual products showing full range of colors available, for each product exposed to view. Samples shall be submitted to Engineer. Submit complete schedule of type (and location where type is to be used) of each sealant.

Contractor shall engage an experienced installer who has completed joint sealant applications similar in material, design and extent to that indicated on the Plans and within these Special Provisions, that have resulted in construction with a record of successful in-service performance.

Provide joint sealants, joint fillers, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by sealant manufacturer based on testing and field experience.

Provide color selections made by Engineer from manufacturer’s full range of standard colors for products of type indicated.

Joint sealants shall be multi-component polyurethane sealant. Except as otherwise indicated, provide manufacturer’s standard, non-modified, 2-or-more-part, polyurethane-based, elastomeric sealant; complying with either ASTM-C-920-87, Type M, Grade P, Class 25, or FS TT-S 0227E Class A, non-sag, Type II.

Provide sealant backings of material and type that are non-staining; are compatible with joint substrates, sealants, primers and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

05/23/2023 C7 131 of 201

H-11

Plastic foam joint fillers shall be pre-formed, compressible, resilient, non-staining, non-waxing, non- extruding strips of flexible plastic foam either open-cell polyurethane foam or closed-cell polyethylene foam, subject to approval of sealant manufacturer, for cold-applied sealants only.

Polystyrene foam is not acceptable.

201-4 CONCRETE CURING MATERIALS.
201-4.1 Membrane Curing Compounds.
201-4.1.1 General. ADD the following:

Curing compounds shall conform to ASTM C 309, Type 1, Class B.

Curing compounds shall be compatible with required finishes and coatings.

Cost for curing compound shall be included in the appropriate bid items, and no additional compensation will be made therefor.

Integrally colored concrete shall be cured with Schofield Lithochrome Colorwax, or approved equal. Color shall match to the concrete. The Contractor shall provide a sample panel(s) of all colors to be used in the installation on identical surfaces for approval of the Engineer prior to construction. Curing compounds containing calcium chloride shall not be used. The time between completing surface finishing and applying curing compound shall be the same for each colored concrete component.

201-4.2 Sheet Curing Materials
201-4.2.1 General. ADD the following:

Mats, Paper, and Sheeting for Curing

1. Burlap maps small conform to AASHTP specification M182.

2. Sisal – Kraft paper and polyethylene sheets shall conform to ASTM C171.

3. Cost for mats, paper, and sheeting for curing shall be included in the appropriate concrete bid items and no additional compensation will be made therefor.

4. Cost for curing compound shall be included in the appropriate concrete bid items and no additional compensation will be made therefor.

SECTION 202 – MASONRY MATERIALS

202-1 BRICK. ADD the following Subsection:

202-1.5 80mm Pavers
Pavers shall be the size, color, and manufacturer, or approved equivalent, as shown on the Plans.

Pavers shall be of a tumbled texture.

Submit manufacturer’s product data, documentation of installer’s experience, manufacturer’s instructions, and a minimum of four (4) full-size samples of the proposed paver to the Engineer for approval at least twenty (20) days prior to ordering materials.

05/23/2023 C7 132 of 201

H-12

Deliver pavers to the site in such a manner that no damage occurs during shipping, handling, unloading, and storage.

Both the installer and manufacturer shall provide a one (1) year written guarantee of the materials and installation.

All pavers shall be sound and free of defects that would interfere with the proper placing of pavers or impair the strength or permanence of the construction.

SECTION 203 - BITUMINOUS MATERIALS

203-1 PAVING ASHPALT

203-1.1 General. ADD the following:

The asphalt concrete design mix shall be submitted for approval a minimum of two (2) weeks prior to start of Work.

203.1.2 Testing Requirements. ADD the following:

Paving asphalt shall be specified by Performance Grade. Performance Grade shall conform to the requirements in Table 203-1.2(A). As used in Table 203-1.2(A), the term “binder” shall mean paving asphalt.

203-1.3 Test Reports and Certification. ADD the following:

The Contractor shall furnish asphalt in conformance with Caltrans “Certification Program for Suppliers of Asphalt”. Caltrans maintains the program requirement, procedures, and a list of approved suppliers at:

http://www.dot.ca.gov/hq/esc/Translab/fpmcoc.htm

The Contractor shall prevent the formation of carbonized particles caused by overheating Asphalt during manufacturing or construction.

203-1.4 Temperatures. ADD the following:

Asphaltic concrete shall arrive at the job site at a temperature of at least 300 degrees-F.

203-5 SLURRY SEAL

203-5.1 General. REPLACE this Section with the following:

Slurry seal shall be plant mixed emulsion-aggregate slurry (EAS) conforming to Section 203-5.4 of the Standard Specifications.

203-6 ASPHALT CONCRETE

203-6.2 Materials
203-6.2.2 Rock Products for Asphalt Concrete Mixtures. ADD the following:

All coarse aggregates used in the production of Hot Mix Asphalt (HMA), excluding RAP, must be mined only from a hard rock- blasted quarry. All coarse aggregates used in the production of Hot Mix Asphalt shall also have a minimum Durability Index (California Test 229) of 35.

05/23/2023 C7 133 of 201

H-13

When aggregate is found to be subject to stripping via prescribed test procedures, dry hydrated lime conforming to the requirements of ASTM C 207, or Type N Portland Cement conforming to applicable requirements, or other approved anti-strip agents shall be added.

Coarse aggregate is material retained on the No. 4 sieve. Fine aggregate is material passing the No. 4 sieve.

Blending sand shall be clean, hard and sound material, either naturally occurring sand or crushed fines which will readily accept asphalt coating.

203-6.2.4 Mineral Filler. ADD the following:

Mineral filler shall conform to the requirements of the Standard Specifications. Mineral filler shall consist of Portland Cement or mechanically reduced rock. Mechanically reduced rock shall conform to the following grading when tested in accordance with ASTM D422.

Particle Size Percent Passing

Passing No. 200 Sieve 75-100
Finer than 0.05 mm 65-100
Finer than 0.02mm 35-65
Finer than 0.01 26-35
Finer than 0.005 mm 10-22

The amount of mineral filler to be used shall be determined by the Engineer. The method of adding the mineral filler shall be such that the aggregate is uniformly coated and the mineral filler is uniformly distributed without loss or waste within the material prior to adding the asphalt to the mixture.

203-6.3 Job Mix Formula (JMF) and Mix Designs
203-6.3.1 General. ADD the following:

The combined aggregates sampled after all processing, except the adding of asphalt and mineral filler, shall conform to the following requirements:

The ratio of the percentage of aggregate by weight passing the No. 30 sieve to that passing the No. 8 sieve, shall not exceed 65 percent in all dense graded asphalt concrete mixes.

At least 80 percent by weight of the aggregate retained on the No. 8 sieve shall consist of particles which have at least one rough, angular surface produced by crushing.

The Contractor shall furnish the Engineer with a Job Mix Formula (JMF) for the asphalt concrete no later than two (2) weeks prior to the actual placement of the material. The JMF shall indicate the percentage passing each specified sieve size and the percent asphalt to be used for each asphalt concrete mixture to be incorporated in the work. The JMF (gradation) with allowable tolerance for a single test, shall be used for job control. Single test variation tolerance is shown below. In no event shall there be more than 2 percent passing the no. 200 sieve.

05/23/2023 C7 134 of 201

H-14

JOB MIX FORMULA GRADING TOLERANCE
(FOR SINGLE TEST)

Sieve Size Percent

No. 4 or larger +6
No. 30 +5
No. 200 +2
Asphalt, percent by weight of mix +0.3

SAMPLES

The Engineer shall have the right to obtain samples of all such materials to be used in the work and to test such samples for the purpose of determining specification compliance. The Engineer reserves the right to obtain said samples at the point of delivery and/or at the point of manufacture. The Engineer shall also have the right to inspect sources of materials to be used for the work to determine acceptability of procedures used by the materials supplier.

203-6.4 Asphalt Concrete Mixtures
203-6.4.1 Class and Grade. ADD the following:

Asphalt concrete base course shall be class and grade: B-PG 64-10 (B-PG 70-10 is also allowable). Minimum asphalt concrete base course pavement lift thickness shall be 2.5-inches, maximum asphalt concrete base course lift thickness shall be 4.0-inches.

Asphalt concrete surface course and overlay shall be class and grade: C1-PG 70-10 and shall be placed in a single 2.0-inch lift.

CERTIFICATE OF COMPLIANCE

At the pre-construction meeting, the Contractor shall submit Certificate of Compliance for the Asphalt Concrete, Tack Coat, and Class II Aggregate Base.

Prior to the time of delivery of each shipment of any materials to be used in the project, the Contractor shall deliver to the City certified copies of all the test results as required by these specifications for those materials to be used (emulsified asphalt, mineral filler, aggregate, etc.). The test report shall indicate the name of the material supplier, type and grade of materials to be delivered, date and point of delivery, quantity to be delivered, delivery ticket number, purchase order number and the results of the specified tests. The test report shall be signed by an authorized representative of the material testing agency and shall certify that the product delivered conforms to these specifications. In addition, the City of Encinitas will select three samples of the materials shipped for conformance testing. The testing for these additional samples shall be provided by the City at no cost to the Contractor, except if the material samples fail any of the tests. In this case, the Contractor shall bear the cost of the testing of those failed samples. NO material from that shipment shall be utilized or employed in performance of the work UNTIL certified test reports and samples of the material have been furnished to, checked by and approved by the Engineer.

Cost of all testing shall be included in the bid item for Place HMA Pavement and no additional compensation will be made therefor.

05/23/2023 C7 135 of 201

H-15

203-6.5.5 Statistical Testing. ADD the following:

The aggregate and mix to be incorporated into the work must also meet the following requirements:

INDIVIDUAL

Test Test Results

Loss in L.A. Rattler per California Test Method 211 (after 500 revolutions)……45% Max.

Sand Equivalent per California Test Method 217…………………………………50 Min.

Stabilimeter Value per California Test Method 366………………………………35 Min Swell per California Test Method 305……………………………………………...0.030” Max.

Moisture Vapor Susceptibility per California Test Method 307…………………..25 Min.

Air Voids Content (mix), percentage………………………………………………..3 Min/5 Max Index of Ret. Strength per ASTM D1075, percentage…………………………….60 Min

SECTION 206 – MISCELLANEOUS METAL ITEMS

206-4 BRONZE CASTINGS.
206-4.1 General. ADD the following:

Skate stoppers shall be installed on raised concrete retaining walls where adjacent to sidewalks.

Skate stoppers shall be “Starfish (6-piece family)” by Skate Stoppers or approved equal.

Skate stoppers shall be cast silicon bronze with brown patina finish, spaced at 36” on-center, installed per manufacturer’s requirements.

SECTION 209 – PRESSURE PIPE

209-4 PVC PRESSURE PIPE

209-4.1 General. ADD the following:

Public potable water mains, services, and appurtenances shall be constructed in accordance Water Agency Standards (W.A.S.).

SECTION 210 – PAINT AND PROTECTIVE COATINGS

ADD the following Subsection:

210-6 REACTIVE TREATMENT FOR GALVANIZED SURFACES

210-6.1 General
This work consists of applying an environmentally safe galvanized surface finish, specifically formulated for galvanized metal, that will not fade, crack, or peel from sun exposure. Product shall achieve a rustic brown color (mostly dark brown with some lighter brown hues and characteristics that produce an aged/rustic look) and shall be applied to cable railing posts. 05/23/2023 C7 136 of 201

H-16

Reactive treatment shall be manufactured and applied by Natina Steel Solution, or approved equivalent.
210-6.2 Submittals
A. Submit the following items:

1. A copy of the manufacturer's product Safety Data Sheet.

2. Independent lab tests showing that the material is environmentally safe.

3. Bend Test results showing that the galvanized steel, treated by the reactive color treatment, exhibits no lifting or separation from mechanical stress as per ASTM B571.

4. Cross-sectional metallographic examinations, in accordance with ASTM E3, conclude an average conversion depth of 0.18 mil and no decrease in total thickness.

5. Corrosion resistance showing the performance of the galvanized steel, treated with the reactive color treatment, meets or exceeds the corrosion resistance of un-treated galvanized steel after 50 hours of salt spray as per ASTM B117.

6. Reactive color treatment must not include volatile organic compounds (VOC’s) or chromate compounds.

B. Applicator Qualifications

1. Company must have a minimum of five (5) years of application experience.

2. Submit description of (5) previous projects where the application of the colorant was made. Descriptions shall demonstrate substantial conformance to the work being performed and include the following information:
a. Name of project;
b. Location of project;
c. Description of work performed;
d. Photos showing the finish on metal as dark rustic brown. e. Company contact information.

3. Demonstrate professional ability and financial constancy. Submit the following materials:
a. Contractor qualifications;
b. Proof of necessary licensing (for three years minimum); c. Insurance certificates as required.

210-6.3 Quality Control and Assurance
The Contractor shall apply the approved colorant to one (1) galvanized cable rail post for review and approval by the Engineer at least twenty (20) days prior to ordering the treatment of the posts.

The approved sample shall be the standard of comparison in determining acceptability of final color and treatment.
210-6.4 Materials
Galvanized Surface Colorant
The colorant must be a soluble solution (never in powdered form) and must also contain organic acids to etch slightly into galvanized surfaces without harming the protection of the galvanized layer. Organic acids used will have no negative effects on the environment. The product must 05/23/2023 C7 137 of 201

H-17

react with the target surface to produce a rustic brown color. The color produced must be resistant to fading from the sun.

SECTION 212 – WATER AND SEWER SYSTEM VALVES AND APPURTENANCES

212-1 GENERAL

212-1.2 Products Conveying Potable Water. ADD the following:

Public potable water mains, services, and appurtenances shall be constructed in accordance Water Agency Standards (W.A.S.).

SECTION 213 – ENGINEERING GEOSYNTHETICS

213-4 PAVING FABRIC. REPLACE Table 213-4.1 with the following:

Paving interlayer fabric shall be Mirafi MPM30 (PGM-30) or approved equivalent and shall be constructed of high strength glass filaments bonded to a polyester fabric, conforming to the following properties:

Mechanical
Properties
Test Method Unit Minimum Average
Roll Value
Tensile Strength @
0°
ASTM D5035
(2C-E)
lbs 200
Tensile Strength @
90°
200
Tensile Elongation ASTM D5035 % <5
Minimum Test Value
Melting Point ASTM D276 F°
(C°)
450° (232°)
Asphalt Retention ASTM D6140 gal/yd² 0.10
Mass/Unit Area ASTM D5261 oz/yd² 4.0

Physical Properties Unit Roll Characteristics
Roll Dimensions (width x length) ft 10 x 450 12.5 x 360 Roll Area yd² 500 500
Estimated Roll Weight lbs 172 172

213-5 GEOTEXTILES AND GEOGRIDS. ADD the following:

Subgrade stabilization geosynthetic reinforcement shall be Mirafi RS380i or approved equivalent, conforming to the following properties:

05/23/2023 C7 138 of 201

H-18

Roadway Design and
Performance Properties
Guidance
Document/
Test Method
Unit Design/Calibration
Value
Base Course MR Improvement
Factor
AASHTO R50-
09 --- 1.40
Subgrade MR Improvement /
Increase
AASHTO R50-
09 lb/in2
(MPa)
9,000 (62.0)
Cyclic Tensile Modulus: Jcyclic ASTM D7556 kip/ft
(kN/m)
MD CD
60 (876) 160
(2,336)
Resilient Interface Shear
Stiffness: GI
ASTM D7499 kip/in2
(MPa)
329 (2,268)
Traffic Benefit Ratio: TBR AASHTO R50-
09 --- 9.0/ 13.1 / 39.0
Interaction Coefficient: Ci ASTM D6706 --- 0.90
Pore Pressure Dissipation
Ratio
Measured --- 2.0
Typical Dynamic Filtration Pore
Size 095 / 050
ASTM D6767 microns 337 / 192
Maximum Percent Open Area:

MPOA
ASTM D6767 Percent 7.3
Tensile Strength @ 2% Strain
(MARV)
ASTM D4595 lb/ft (kN/m) 480 (7.0) 1,800
(26.3)
Tensile Strength @ 5% Strain
(MARV)
ASTM D4595 lb/ft (kN/m) 1,440
(21.0)
4,380
(63.9)

Index Properties Test Method Unit Roll Value
Apparent Opening Size, AOS
(Maximum Roll Value)
ASTM D4751 U.S Sieve
(mm)
40 (0.425)
Hydraulic Flow Rate (MARV) ASTM D4491 gal/min/ft2
(l/min/m2)
75 (3,056)
Permittivity (MARV) ASTM D4491 sec-1 1.0
UV Resistance
(at 500 hours exposure)
ASTM D4355 % strength
retained
90 ADD the following Subsection:

213-6 IMPERMEABLE LINER
Impermeable liner shall be a 30-mil, single-ply, construction Polyvinyl Chloride (PVC) geomembrane material made with virgin resins and meeting the requirements of ASTM D7176. Attachment hardware shall consist of an aluminum bar with stainless steel anchor bolts and washers per the dimensions shown on the Plans.

05/23/2023 C7 139 of 201

H-19

SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS,

AND PAVEMENT MARKERS

214-4 PAINT FOR STRIPING AND MARKINGS

214-4.1 General. ADD the following:

Traffic line paint shall be rapid dry paint and shall contain reflective material conforming to Sections 84-1 and 84-3 of the Caltrans Standard Specifications, 2018 edition. Paint shall comply with all application of local air pollution control regulations.

All traffic stripes and pavement markings shall be reflectorized. The Contractor shall apply two coats on all traffic striping.

Samples of traffic striping and pavement marking materials shall be submitted to the Engineer at least two weeks prior to application.

214-5 THERMOPLASTIC MATERIAL FOR TRAFFIC STRIPING AND MARKINGS

214-5.1 General. ADD the following:

All crosswalks, legends, markings, arrows and limit lines/stop bars, etc. shall be pre-formed thermoplastic. All thermoplastic legends, markings, arrows, etc. within crosswalks and bike lanes shall provide greater than 60 British Pendulum Number (BPN) slip resistance when tested in accordance with ASTM: E 303, and as described herein.

All details and dimensions for pavement markings shall conform to City approved stencils and the latest edition of the CA-MUTCD.

ADD the following Subsection:

214-5.2 Green Bike Lane Conflict Marking
The material for green bike lane conflict marking shall meet the following specifications:

214-5.2.1 Use
A durable, high skid resistant, retroreflective pavement marking material suitable for use as a bike lane marking.

The material shall be a resilient light green color thermoplastic product, the surface of which must contain glass beads and abrasives in an alternating pattern optimizing both skid resistance and retroreflectivity.

The material shall be resistant to the detrimental effects of motor fuels, lubricants, hydraulic fluids etc.

The material shall be capable of being affixed to bituminous and/or Portland cement concrete pavements by use of the normal heat of a propane torch.

The material shall be capable of conforming to pavement contours, breaks and faults through the action of traffic at normal pavement temperatures. The markings shall have re-sealing characteristics, such that it is capable of fusing with itself and previously applied thermoplastic.

05/23/2023 C7 140 of 201

H-20

The material shall not have minimum ambient and road temperature requirements for normal application, storage, or handling. When manufacturer’s standard application procedures require the use of a 2-component sealer, the material shall be capable of being applied with a compatible 2-component sealer recommended by the manufacturer, at minimum ambient and surface temperatures of 45⁰F without any special storage, preheating or treatment of the material before application.

214-5.2.2 Material
Must be composed of an ester modified rosin resistant to degradation by motor fuels, antifreeze, lubricants, etc. in conjunction with aggregates, pigments, binders, abrasives, and glass beads which have been factory produced as a finished product, and meets the requirements of the current edition of the Manual on Uniform Traffic Control Devices for Streets and Highways, including the April 15, 2011 FHWA “Interim Approval for Optional Use of Green Colored Pavement for Bike Lanes (IA-14).” The thermoplastic material shall conform to AASHTO designation M249- 79 (98), with the exception of the relevant differences due to the material being supplied in a preformed state.

Graded Glass Beads:

The material must contain a minimum of thirty percent (30%) intermixed graded glass beads by weight. The intermixed beads shall be clear and transparent. Not more than twenty percent (20%) consists of irregular fused spheroids, or silica. The index of refraction shall not be less than 1.50.

The material must have factory applied coated surface beads and abrasives in addition to the intermixed beads at a rate of 1/2 lb. (± 20%) per 11 sq. ft. The surface beads and abrasives must be applied in an alternating arrangement across the surface of the material so that the surface is covered in what is best described as a “checkerboard” pattern of glass beads and abrasive materials. The abrasive material must have a minimum hardness of 8 (Mohs scale). These factory-applied coated surface beads shall have the following specifications:

a. Minimum 80% rounds;
b. Minimum refractive index of 1.5;
c. Minimum SiO2 Content of 70%;
d. Maximum iron content of 0.1%;

Pigments: Light Green:

The material shall be manufactured with appropriate pigment to ensure that the resulting colors complies with the Light Green color as specified in the FHWA Memorandum dated April 15th, 2011: Interim Approval for Optional Use of Green Colored Pavement for Bike Lanes (IA-14). 05/23/2023 C7 141 of 201

H-21

Daytime chromaticity coordinates for the color used for green colored pavement shall be as follows:

Nighttime chromaticity coordinates for the color used for green colored pavement shall be as follows:

The pigment system must not contain heavy metals or any carcinogen, as defined in 29 CFR 1910.1200 in amounts exceeding permissible limits as specified in relevant Federal Regulations.

Heating indicators:

The top surface of the material shall have regularly spaced indents. The closing of these indents during application, shall act as a visual cue that the material has reached a molten state allowing for satisfactory adhesion and proper bead embedment, and as a post-application visual cue that the application procedures have been followed.

Skid Resistance:

The surface of the pre-formed retroreflective marking materials, wherein every other shaped portion contains glass beads, or abrasives with a minimum hardness of 7 (Mohs scale), shall provide a minimum skid resistance value of 60 BPN when tested according to ASTM E 303.

Thickness:

The material must be supplied at a minimum thickness of 90 mils (2.29 mm).

Retroreflectivity:

The preformed retroreflective marking materials, upon application, shall exhibit adequate and uniform nighttime retroreflectivity of 50 mcd·m-2·lx-1when measured using a Delta LTL 2000 or LTL-X Retroreflectometer using the ASTM E1710 method. Note: Initial retroreflection and skid resistance are affected by the amount of heat applied during installation. When ambient temperatures are such that greater amounts of heat are required for proper installation, initial retroreflection and skid resistance levels may be affected.

Environmental Resistance:

The material must be resistant to deterioration due to exposure to sunlight, water, salt or adverse weather conditions and impervious to oil and gasoline.

Abrasives:

The abrasives and surface beads must be applied in an alternating arrangement across the surface of the material so that the surface is covered in what is best described as a “checkerboard” pattern of glass beads and abrasive materials. The abrasive material must have a minimum 05/23/2023 C7 142 of 201

H-22

hardness of 7 (Mohs scale).

214-5.2.3 Application
The material shall be capable of being applied using the propane torch method recommended by the manufacturer, without minimum requirements for ambient and road temperatures, and without any preheating of the pavement to a specified temperature. The material shall be capable of being applied without the use of a thermometer. The pavement shall be clean, dry and free of debris.

Supplier must enclose application instructions with each box/package.

214-5.2.4 Packaging
The preformed thermoplastic markings shall be placed in protective plastic film with cardboard stiffeners where necessary to prevent damage in transit. Linear material must be cut to a maximum of 3' long pieces. Legends and symbols must also be supplied in flat pieces. The cartons in which packed shall be non-returnable and shall not exceed 40" in length and 25" in width, and be labeled for ease of identification. The weight of the individual carton must not exceed seventy (70) pounds. A protective film around the box must be applied in order to protect the material from rain or premature aging.

214-5.2.5 Sealer
A two-component sealer must be used for the installation of preformed thermoplastic material per the following specifications:

Use:

A two-component epoxy sealer used to enhance the bond strength between the substrate (asphalt concrete) and preformed thermoplastic materials made from resins and/or polymers, and inorganic fillers.

Properties:

The sealer must be environmentally safe – no VOC solvents. a. The sealer must bond to dry and damp surfaces.

b. The sealer must have a low viscosity that allows it to penetrate into concrete and in particular penetrate through laitance, if present.

c. To allow for the application area to be re-opened to traffic, the sealer must cure rapidly.

During a normal application process the sealer will have cured and bonded to the preformed thermoplastic material in less than 10 minutes.

d. To allow for work time for correct positioning of the preformed thermoplastic material, the sealer must have a gel time of at least 20 minutes at 80ºF.

Application:

The sealer shall be capable of being applied to the substrate either by brush, roller, or sprayer.

It shall be capable of being applied in a thin, even, uniform coat.

Packaging:

Each cartridge must be properly labeled and packed in a heat-sealed polyethylene bag. Three mixing nozzles, 2 cartridge re-closing caps, 2 application rollers, and 3 pairs of latex gloves must be packaged in a separate heat-sealed compartment of the same bag. Detailed Application 05/23/2023 C7 143 of 201

H-23

Instructions and MSDS must be included in each kit, which must consist of two cartridge/accessory bags.

214-6 PAVEMENT MARKERS

214-6.1 Types of Markers. ADD the following:

Pavement markers shall conform to Section 85 of the Caltrans Standard Specifications (2018 edition).

Pavement marker height shall be 0.70 inch minimum. “Low profile” type markers will not be acceptable.

214-7 ADHESIVES FOR PAVEMENT MARKERS

214-7.1 General. ADD the following:

Adhesives for pavement markers shall be either rapid-set epoxy adhesive or hot-melt bituminous adhesive.

SECTION 217 – BEDDING AND BACKFILL MATERIALS

217-1 BEDDING MATERIAL

217-1.1 General. ADD the following:

Public potable water mains, services, and appurtenances shall be constructed in accordance Water Agency Standards (W.A.S.) as modified herein.

IMPORTED GRANULAR MATERIAL – PIPE ZONE
The pipe zone is defined as that area extending from six (6) inches below the bottom of the pipe grade to 12 inches over the crown of the pipe, and the trench width as defined under excavation above. The Imported Granular Material (SAND) shall have a sand equivalent of not less than 30 and shall be free from clay balls. Under no circumstances will decomposed granite or native earth backfill be allowed or used in the pipe base or pipe zone areas. Imported sand shall have the following gradation:

Sieve Size Percent Passing by Weight
½-inch 100
No. 4 75-100
No. 16 35-75
No. 50 10-40
No. 200 0-10
The area shall be carefully compacted to 90 percent of maximum density at optimum moisture content. Compaction shall be obtained by mechanical means or, if approved by the Engineer, by using excess water and passing a vibrator between the pips and side of trench.

05/23/2023 C7 144 of 201

H-24

217-2 TRENCH BACKFILL

217-2.1 General. ADD the following:

Public potable water mains, services, and appurtenances shall be constructed in accordance Water Agency Standards (W.A.S.) as modified herein.

IMPORTED GRANULAR MATERIAL – TRENCH ZONE
Select native material most closely meeting the granular material specifications excavated from the various project locations may be used in lieu of imported granular material in the trench zone.

Contractor will be required to perform a sieve analysis on the select native material at its own expense if requested to be used in exchange of import material.

05/23/2023 C7 145 of 201

H-25

PART 3

CONSTRUCTION METHODS

SECTION 300 – EARTHWORK

300-1 CLEARING AND GRUBBING

300-1.1 General. ADD the following:

Prior to actual performance of the Work, the Contractor shall field review the locations and limits of the Work to be done.

All existing pavement, concrete sidewalk, asphalt sidewalk, driveway, concrete curb and gutter, asphalt dike, base material, and/or native material shall be completely removed within the limits of sawcut and/or grading limits. Sawcut and excavation of said materials shall leave clean, straight edges, and square corners free of loose material, water, or debris.

The Contractor shall prevent sawcut slurry discharges to gutters, storm drains, and watercourses. The Contractor shall shovel, absorb or vacuum the slurry residue from the pavement or gutters and remove from the site at the end of the day or job (whichever is sooner).

Areas of pavement and concrete removal and excavation shall be properly maintained until permanent surfacing is placed.

The Contractor’s attention is directed to the existence of certain underground facilities that may require special precautions to be taken by the Contractor to protect the health, safety, and welfare of workers and of the public. Facilities requiring special precautions include, but are not limited to:
natural gas pipelines, AC water lines, and underground electrical/communication supply lines.

The Contractor shall notify the Engineer, Underground Service Alert, and the utility companies at least (2) Working Days, but not more than fourteen (14) calendar days, prior to performing any excavation or other work close to any underground pipeline, conduit, duct, wire, or other structure.

The Contractor shall locate all existing underground utilities including signal wires, streetlighting wires, irrigation lines, communication lines, and other underground facilities as necessary to complete the improvements without damage to existing facilities. The Contractor shall have said facilities located and marked out by an approved utility locating contractor familiar with utility facilities.

At least two (2) weeks prior to demolition work, the Contractor shall pothole all existing utilities prior to the start of digging adjacent to or above each utility, at such frequency to ensure a thorough understanding of each utility’s location and elevation. Through the potholing efforts, the Contractor shall determine the depth of all pipe and conduit that is encased in concrete and slurry using either destructive or non-destructive testing methods.

Additionally, existing utilities shall be potholed at all crossings of proposed utilities, structures, and foundations, and throughout the project area as necessary to facilitate a thorough understanding of their locations and elevations.

The Contractor shall submit all pothole data, along with a certification of the accuracy of said data, to the Engineer for review and approval a minimum of two (2) weeks prior to the start of any demolition work, and any work to be done requiring potholing.

05/23/2023 C7 146 of 201

H-26

Some utility conduits are encased in Portland cement concrete or a cement-sand slurry backfill and extend vertically into the new asphaltic concrete and pavement structural sections. Where concrete encasement and cement-sand slurry backfill are encountered and extend into the new pavement structural sections, the same shall be lowered in a manner approved by the respective utilities to at least ten (10) inches below finished surface elevation.

CONTRACTOR SHALL BE MADE AWARE THAT SOME UTILITY PROVIDERS MAY CHOOSE TO PERFORM THE WORK DESCRIBED IN THIS PARAGRAPH WITH THEIR OWN FORCES;

IN SUCH CASE, CONTRACTOR IS REQUIRED TO INCORPORATE THE UTILITY PROVIDER’S WORK SCHEDULE INTO THE PROJECT CONSTRUCTION SCHEDULE TO AVOID DELAYS.

Following Notice to Proceed, the Contractor shall coordinate and meet with utility agencies listed on the Plans and incorporate each utility provider’s respective work schedules into the Contractor’s proposed baseline schedule. Contractor shall also include utility provider work schedules in the 3-week look-ahead schedules that shall be submitted to the Engineer and discussed at the weekly meetings. The Contractor shall coordinate with, and invite, the utility provider to the weekly meeting(s) when utility provider’s work will be discussed and is part of the Contractor’s 3-week look-ahead schedule. The Contractor shall coordinate with, and invite, each utility provider to a separate, formal pre-meeting prior to any digging to establish protocol for broken lines.

The Contractor shall coordinate its work with all utility relocations and adjustments (including adjustments to finished grade) required to be performed by others (i.e., utility providers or their contractors) during the course of construction. The Contractor shall include the timing and duration of such work in its Progress Schedule (e.g., “utility windows”). The Contractor must provide utilities with twenty (20) working days written notice that the site has been or will be prepared; including the date preparation has been or will be complete, for all utility relocation and adjustment work to be performed by others. The Contractor shall set-up a pre-construction meeting with the utility provider and the City’s representative(s), for each relocation or adjustment no sooner than ten (10) working days prior to the start of the utility provider’s work.

The Contractor shall notify the Engineer within 24 hours of discovery of any existing utilities found to be in conflict with the proposed improvements that are not otherwise shown on the Plans.

For utilities that the Contractor is responsible for adjusting to finished grade, the Contractor must provide 48 hours advanced notification of the work to be performed and the location to the utility providers.

300-1.3 Removal and Disposal of Materials
300-1.3.2 Requirements

(a) Bituminous pavement. REVISE the second and third sentences to read:

Sawcutting edges to be joined shall be mandatory. Saw cuts shall be to a minimum depth of three (3) inches. Where only the surface of existing bituminous pavement is to be removed, the method of removal shall be approved by the Engineer, and a minimum laying depth of 2.0-inches of new pavement material shall be provided.

05/23/2023 C7 147 of 201

H-27

ADD the following:

(d) Miscellaneous.

The following items of work are included under Clearing and Grubbing unless otherwise covered by a special bid item:

1. Removal of existing asphaltic concrete sections, concrete pavement sections, curb, curb and gutter, sidewalks, and curb ramps; including asphaltic concrete, concrete, and aggregate base materials.

2. Excavation of test pits (potholing) sufficient to determine the exact locations (horizontal and vertical) of all underground utility lines located throughout the work area. This will be the first order of work prior to any construction, and adjustments will not be considered as reason for additional compensation.

3. Temporary support of all sloped and vertical plains of excavation. Shoring where needed shall be placed to protect exiting improvement including adjacent properties. Temporary shoring design is Contractor responsibility and shall be designed by a Registered Engineer.

Contractor shall submit the calculation to the City’s prior commencement of the construction.

4. Maintenance of dust control at all times.

5. Protection of existing and relocated improvements, utilities, private irrigation systems, and utility structures, prior to and during, construction of the proposed improvements.

6. Removing, relocating, adjusting, and salvaging of all facilities as shown on the Plans.

7. Disposal and/or recycling of soil, organic, and other objectionable materials.

8. Removal and disposal of any additional items not specifically mentioned which may be found within the work limits.

9. Removal of underground structures.

10. Clearing for, and providing, temporary graded driveways and continuing maintenance thereof to provide for safe, smooth, stable, and continuous all-weather access to all residences within the work limits and as directed by the Engineer.

11. Milling of asphalt pavement.

12. Termination of street lighting to be removed in accordance with the National Electrical Code. To avoid any live wires remaining in service, the entire length of wire extending to street lights in conflict with the proposed improvements shall be disconnected at the power supply and removed from the site. If the existing connected street light standards are to remain, Contractor shall re-establish the electrical connection from the power supply to the street light.

13. Removal of existing water mains, services, and appurtenances, conducted in accordance with W.A.S. standards.
05/23/2023 C7 148 of 201

H-28

14. Deleterious materials resulting from Clearing and Grubbing operations shall be hauled away and legally disposed of at a site obtained by the Contractor.

15. Maintenance of project appearance.

16. Control of water and dewatering during construction.

17. Clean-up of project area every week and upon completion of work.

18. Other items of work as directed in these Special Provisions.

WORKING WITH AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL Asbestos containing particles are considered a hazardous material. Cutting or other manipulation of asbestos pipe which creates such particles is not allowed. The Contractor is fully responsible for taking the necessary measures and precautions when working with asbestos pipe.

Friable asbestos-containing materials (ACM) are regulated as a hazardous waste and must be transported by a licensed hazardous waste hauler and disposed of in an appropriate landfill. A friable material is defined as material that can be crumbled, pulverized, or reduced to powder in the hand. The Contractor is fully responsible for the transportation and disposal of friable ACM’s.

The Contractor is required to abide by the above requirements and to pay all costs, including lab analysis fees, vehicle dump fees, special handling fees, administrative fees, and any other fees required in the removal and disposal of asbestos materials.

300-2 UNCLASSIFIED EXCAVATION

300-2.2 Unsuitable Material
300-2.2.1 General. ADD the following:

Unclassified excavation shall consist of making all cuts and fills to the lines and grades shown on the Plans, stockpiling of suitable materials, transport of stockpiled material to its ultimate location, removal of unsuitable material, structure excavation and backfill, borrow excavation, transportation, all mixing, moisture conditioning, and compaction, and export of excess material to a legal site.

The onsite soils are generally considered suitable for use as compacted fill provided they are free of organic materials, debris, and rock fragments larger than six (6) inches in maximum dimension. All native fill soils shall be brought to a moisture content of at least three (3) percent above the laboratory optimum and compacted in uniform lifts to at least 90 percent, unless otherwise noted, relative compaction based on laboratory standard ASTM Test Method D1557. Fill shall be placed in lifts not exceeding eight (8) inches in thickness.

All undocumented fill soils within the project limits extending two (2) feet outside of the improvements shall be removed; moisture conditioned, and recompacted to a depth of two and a half feet. All loose surficial fill soils not removed by the planned grading shall be processed, moisture conditioned, and then compacted prior to placing any additional fill.

05/23/2023 C7 149 of 201

H-29

The Contractor is responsible to locate all existing utilities that might be disturbed or damaged from the Contractor’s operation. The cost of this work, including removal and disposal of excess material, is considered included in the various bid items and no additional compensation shall be allowed therefor.

300-2.2.2 Wet Material. ADD the following:

If unsuitable material is encountered, the Engineer may direct its removal, disposal, and replacement with crushed aggregate base, conforming to Section 200-2.2 of the Standard Specifications. For this type of application, the Contractor shall place one layer of subgrade stabilization geosynthetic reinforcement (Mirafi: 600X or FW700, or approved equivalent) at the bottom of the excavation.

300-2.6 Surplus Material. ADD the following:

Excavated material shall be removed at the end of that day's operations. Storage or stockpiling of excavated material within the right-of-way will not be allowed overnight. No temporary storage or stockpiling of any excavated materials will be allowed in any planted or landscaped parkway or within any sidewalk or established walking path, private drive, or access way.

Material obtained from removal and excavation operations shall become the property of the Contractor and shall be disposed of at a legal site.

The Contractor shall be responsible for obtaining a suitable, legal, disposal site for excavated material, and file with the Engineer the written consent of the owner of the property upon which he intends to dispose of such material.

300-3 STRUCTURE EXCAVATION AND BACKFILL

300-3.1 General. ADD the following:

Structure excavation shall include the temporary support of all sloped and vertical plains of excavation. Shoring, where needed, shall be placed to protect exiting improvements including adjacent properties. Temporary shoring design is the Contractor’s responsibility and shall be designed in accordance with State of California Department of Industrial Relations, Division of Occupational Safety and Health requirements, and stamped by a registered engineer in the State of California. The Contractor shall submit the shoring plans and calculations to the Engineer for review and approval prior to the commencement of the construction for which the shoring is required.

Full compensation for furnishing all labor, materials, and equipment necessary to design, permit, and perform the structure excavation shoring and bracing is considered included in the various bid items which require the shoring, and no additional compensation will be allowed therefor.

300-3.5 Structure Backfill
300-3.5.2 Pervious Backfill. REPLACE the first sentence with the following:

Pervious retaining wall backfill shall be composed of ¾” to 1-1/2” open graded clean gravel conforming to the gradation limits contained in Table 200-1.2.1 for 1” material of the Standard Specifications.

300-4 UNCLASSIFIED FILL

300-4.3 Other Fill Materials. REPLACE this Subsection with the following:

Excess soil remaining in the Project Site from excavations other than Unclassified Excavation my only be used for fill material when rocks, lumps, cobbles, clods, or other solid materials such as 05/23/2023 C7 150 of 201

H-30

broken concrete or asphalt from removal operations are suitable for the particular area to be filled, as determined by the Engineer and in conformance with the requirements of the Project Geotechnical Investigation. Broken concrete or asphalt pavement materials shall not be allowed within fill areas or roadway fills less than three (3) feet in height, within three (3) feet of final grade, or within five (5) feet vertically of the existing ground water table.

Concrete and asphalt pieces shall be less than six (6) inches in greatest dimension and shall be surrounded by soil particles when used as compacted fill. No nesting shall occur. 300-4.9 Measurement. REPLACE this Subsection with the following:

No separate measurement will be made for unclassified fill.

300-4.10 Payment. REPLACE this Subsection with the following:

Full compensation for unclassified fill shall be included in the contract unit price paid for Unclassified Excavation and no separate payment shall be made therefor.

300-5 BORROW EXCAVATION

300-5.2 Imported Borrow. Add the following:

Imported borrow shall be clean, well graded soil, consisting of material conforming to all requirements in the Standard Specifications, these Special Provisions, and the following:

Test Test Method Number Requirement
R-Value California 301 40 Minimum
Expansion Index UBC Standard 18-2 30 Maximum
Plasticity Index ASTM D 424 4 Maximum
Sieve Analysis ASTM D 422 15% Maximum Passing No. 200

Imported borrow shall be tested by the Contractor and the results submitted to the Engineer for approval prior to being delivered to the site.

300-6 EARTHWORK FOR DEBRIS DAMS AND BASINS

300-6.1 General. ADD the following:

BSM shall be thoroughly mixed prior to delivery using mechanical mixing methods such as a drum mixer. The Contractor shall protect soils and mixes from absorbing excess water and from erosion at all times.

The Contractor shall not deliver or place soils in wet or muddy conditions.

The Contractor shall not store materials unprotected during large rainfall events (>0.25-inches).

If water is introduced into the material while it is stockpiled, the Contractor shall allow the material to drain to the acceptance of the Engineer before placement.

BSM shall be lightly compacted and placed in loose lifts approximately 12-inches (300 mm) to ensure reasonable settlement without excessive compaction. Compaction within the BSM area should not exceed 75 to 85% standard proctor within the BSM. Machinery shall not be used in the bioretention facility to place the BSM. A conveyor or spray system shall be used for media placement in large facilities. Low ground pressure equipment may be authorized for large facilities at the discretion of the Engineer. Placement methods and BSM quantities shall account for 05/23/2023 C7 151 of 201

H-31

approximately 10% loss of volume due to settling. Planting methods and timing shall account for settling of media without exposing plant root systems.

Aggregate placed within storm water management treatment areas shall be deposited on underlying layers at a uniform quantity per linear foot, which quantity will provide the required compacted thickness within the tolerances specified herein without resorting to spotting, picking up, or otherwise shifting the aggregate material.

Each of the two filter course layers (top layer of ASTM C33 Choker Sand and bottom layer of ASTM No. 8 stone) shall be installed to a thickness of 3 inches (75 mm). Both layers shall be spread in single layers. Marker stakes should be used to ensure uniform lift thickness.

BMP material layers shall be as delivered as uniform mixtures and each layer shall be spread in one operation. Segregation within each aggregate layer shall be avoided and the layers shall be free from pockets of course or fine material.

Filter course material and aggregate storage material shall be lightly compacted to approximately 80% standard proctor without the use of vibratory compaction.

300-6.6 Payment. REPLACE this Subsection with the following:

Full compensation for clearing and grubbing shall be included in the contract lump sum price paid for Clearing and Grubbing and no separate payment shall be made therefor.

Full compensation for earthwork for debris dams and basins shall be included in the contract unit price paid for Unclassified Excavation and no separate payment shall be made therefor.

Full compensation for the installation of storm water management BMP materials shall be included in the contract unit price paid for Construct Vegetated BMP and no separate payment shall be made therefor.

Full compensation for the installation of landscape and irrigation materials within the Vegetated BMPs shall be included in the contract lump sum price paid for Furnish and Install Landscape and Irrigation Improvements and no separate payment shall be made therefor.

300-8 GEOTEXTILES FOR DRAINAGE

ADD the following Subsection:

300-8.2 Impermeable Liners
Impermeable liners shall be stored and installed in accordance with the manufacturer’s requirements and as shown on the Plans. The Contractor shall submit technical data and manufacturer's specifications for the impermeable liners and a proposed plan for delivery, storage, and placement. This plan shall be submitted to the Engineer for approval at least twenty (20) days prior to ordering the material.

300-10 GEOTEXTILES FOR SEPARATION

300-10.1 Subgrade Enhancement
300-10.1.1 Placement. ADD the following Subsection:

Subgrade stabilization geosynthetic reinforcement shall be stored and installed in accordance with the manufacturer’s requirements and as shown on the Plans. The Contractor shall submit technical data and manufacturer's specifications for the geosynthetic reinforcement and a proposed plan 05/23/2023 C7 152 of 201

H-32

for delivery, storage, and placement. This plan shall be submitted to the Engineer for approval at least twenty (20) days prior to ordering the material.

05/23/2023 C7 153 of 201

H-33

SECTION 301 – SUBGRADE PREPARATION

301-1 SUBGRADE PREPARATION

301-1.2 Preparation of Subgrade. ADD the following:

Subgrade shall be scarified, moisture conditioned, and compacted in accordance with Section 301-

1.3 as described below.

301-1.3 Relative Compaction. REPLACE this Subsection with the following:

Prior to placing aggregate base beneath asphalt, concrete, curb, curb and gutter, and paver roadway surfacing, the upper 12-inches of subgrade soils shall be scarified, moisture conditioned to at least optimum moisture content and compacted to a minimum 95 percent relative compaction based on laboratory standard ASTM Test Method D1557.

Prior to placing aggregate base beneath concrete sidewalks, the upper 12-inches of subgrade soils shall be scarified, moisture conditioned to at least three percent above optimum moisture content and compacted to a minimum 90 percent relative compaction based on laboratory standard ASTM Test Method D1557.

All aggregate base shall be compacted to a minimum 95% relative compaction based on laboratory standard ASTM Test Methods D1557.

301-1.6 Adjustment of Manhole Frame and Cover Sets to Grade. ADD the following:

The Contractor shall adjust electrical and communication pull boxes, gas valves, street light pull boxes, water meter boxes, water valves, sanitary sewer cleanouts, and other City owned or maintained facilities and structures to grade as shown on the Plans. The Contractor shall replace existing structures that have been damaged or are otherwise not suitable for re-use in adjusting to grade. The cost for replacing damaged structures called out to be adjusted to grade shall be paid for by the Contractor.

Adjustment of all existing storm drain manhole frame and covers to new grade, as shown on the Plans, shall conform to Section 302-5.8 of the Standard Specifications. Adjustment of sanitary sewer manhole frame and covers to new grade, as shown on the Plans, shall conform with the Leucadia Wastewater District standards. The Portland cement concrete to be used in the manhole adjusting operations shall be 560-C-3250 conforming to Section 201-1 of the Standard Specifications. The Contractor shall remove the asphalt concrete around the manhole lid, install 560-C-3250 concrete in accordance to Section 201-1 of the Standard Specifications up to within 2 ½ inches of the finished surface, and install the final 2 ½ inch lift of asphalt concrete in accordance to Section 302-5.8. The asphalt concrete shall match the mix design of the asphalt concrete surface course on that particular street. During adjusting operations, the contractor shall keep the manholes and the channels at the bottom of the manholes clean at all times. After placement of the concrete, and after it has adequately set, the Contractor shall place the permanent asphalt concrete around the structure.

The Contractor shall not use any adjustable rings (fiberglass, cast iron, etc.) when adjusting manholes.

As shown on the Plans, survey monument frames and covers will be raised at the time of paving by the Contractor and in conformance to Section 15 of the State of California Department of 05/23/2023 C7 154 of 201

H-34

Transportation Standard Specifications (2018 Edition). A commercial cast iron riser ring shall be use.

Lids of survey monuments shall be clean and legible after grade adjustment has been made.

The Contractor shall adjust all San Dieguito Water District (SDWD) water valves, vaults, manual air release valves, and blow off assemblies, as shown on the Plans, to grade in accordance to W.A.S Standards. The Contractor shall supply and install ID locators (similar to the SDG&E ID locators) on all SDWD water valves, manual air release valves, water vaults and blow-off assemblies.

SECTION 302 – ROADWAY SURFACING

302-4 SLURRY SEAL SURFACING

302-4.6.1 General. ADD the following:

For areas to be slurry sealed, all existing thermoplastic legends, stop bars, crosswalks, and striping shall be grounded down, and all pavement markers shall be removed prior to placement of the slurry seal.

The Contractor shall remediate cracks, potholes, and large areas of “alligator cracking” prior to placing the slurry seal. Remediation shall be accomplished by full depth removal of the existing asphalt pavement section, or by crack cleaning and sealing of all cracks, as designated by the Engineer. The Contractor shall fill and seal cracks in accordance with the Caltrans Standard Specifications (2018 Edition) and as described herein.

Prior to applying rubberized crack sealant, the Contractor shall apply an herbicide using Roundup, or approved equal, on all cracks containing vegetation (grass, weeds, etc.). The herbicide shall be placed at least five (5) working days prior to placing the crack seal.

At least five (5) working days after the application of the herbicide, and no more than five (5) working days prior to the placing of the crack seal, the Contractor shall remove all vegetation from the cracks.

Cracks shall be cleaned prior to the crack sealant application to provide an intact bonding surface which is free from all dust, moisture or other contaminants.

Cracks with an average clear opening of 3/8 inches or more shall be sealed with either RS-2 emulsified asphalt or asphalt-rubber crack sealant. Prior to placing of the crack sealant, cracks which are 3/8 inches or wider shall be cleaned to a minimum depth of ¾ inches. Prior to placing the crack sealant, all cracks to be sealed shall be cleaned by blast-cleaning or by hand methods, and then cleaned with high pressure air jets to remove all residue and foreign materials. Exposed surfaces shall be dry when the crack sealant is applied.

Asphalt-rubber crack sealant shall be heated and placed in conformance with the manufacturer’s written instructions. Joint sealant materials shall not be placed when the pavement surface temperature is below 50 ºF.

302-4.6.4 Aggregate Application Rate.
302-4.6.4.1 General. ADD the following:

The application rate for the EAS shall be for Type II EAS as stated in Table 302-4.6.4.1.

05/23/2023 C7 155 of 201

H-35

302-5 ASPHALT CONCRETE PAVEMENT

302-5.1 General. ADD the following:

The final surface course of asphalt concrete shall be installed as a last order of Work after the completion of all surrounding concrete and utility improvements.

302-5.4 Tack Coat. ADD the following:

Tack coat consisting of grade SS-1h emulsified asphalt shall be utilized.

302-7 PAVEMENT FABRIC

302-7.1 General. ADD the following:

Pavement fabric shall be stored and installed in accordance with the manufacturer’s requirements, the Standard Specifications, as specified in these Special Provisions, and as shown on the Plans.

Where a conflict exists between these requirements, the more stringent requirement will apply. The Contractor shall submit technical data and manufacturer's specifications for the impermeable liners and a proposed plan for delivery, storage, and placement. This plan shall be submitted to the Engineer for approval at least twenty (20) days prior to ordering the material.

SECTION 303 - CONCRETE AND MASONRY CONSTRUCTION

303-4 MASONRY CONSTRUCTION

303-4.2 Brick Masonry
303-4.2.2 Bricklaying. ADD the following:

Pavers shall be installed in accordance with the manufacturer’s requirements in a herringbone pattern.

303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY

INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS

303-5.1 Requirements
303-5.1.1 General. MODIFY as follows:

The first sentence of the second paragraph shall read: Unless otherwise shown on the Plans, and except as otherwise specified in these Special Provisions, the minimum thickness of concrete sidewalks shall be four (4) inches.

ADD the following:

All Concrete driveways shall be 560-C-3250, with a minimum thickness of 5.5-inches.

All Colored and Stamped Concrete Type A ADA Passageways shall be 560-C-3250, with a minimum thickness of 6-inches.

All Concrete Cross Gutters shall be 560-C-3250, with a minimum thickness of 7-inches.

All Stamped and Colored Concrete Sidewalk shall have a minimum thickness of 5-inches. 05/23/2023 C7 156 of 201

H-36

All concrete sidewalks, ADA ramps, ADA passageways, bike ramps, cross gutters, and retaining wall foundations, shall have 4 inches, or as shown on the Plans, of Crushed Aggregate Base or Class II Aggregate Base placed under the concrete.

All concrete curbs, curb gutters, and driveways shall have 6 inches, or as shown on the Plans, of Crushed Aggregate Base or Class II Aggregate Base placed under the concrete. 303-5.2 Forms
303.5.2.1 Standard Forms. ADD the following:

Forms shall be designed in accordance with ACE 347.

Forms shall be treated with a release agent that shall effectively prevent absorption of moisture and prevent bonding with the concrete. The release agent shall be non-staining and non-toxic after 30 days.

303-7 COLORED CONCRETE

303-7.2 Method A (Dry Shake). DELETE this Subsection in its entirety. Colored concrete shall be produced by the integral color method.

SECTION 306 – OPEN TRENCH CONDUIT CONSTRUCTION

306-1 GENERAL. ADD the following:

Public potable water mains, services, and appurtenances shall be constructed in accordance Water Agency Standards (W.A.S.), including any advance notifications required prior to shut downs.

The Contractor shall exercise extreme care when completing any work above, adjacent, or impacting existing ACP waterlines. The Contractor shall submit a plan for approval by the Engineer prior to any removals of and digging operations above or adjacent to existing ACP waterlines. The plan shall include identification of shutoff locations and times, planned method for removal, transport, and disposal of ACP, and identification of immediate stand-by services for pipe section replacement.

306-2 DELIVERY, STORAGE, HANDLING, AND PROTECTION OF PIPELINE MATERIALS,

FITTINGS, VALVES, AND APPURTENANCES

306.2.7 Shutdowns of Existing Pipelines
306.2.7.1 General. ADD the following:

POTABLE WATER MAIN ORDER OF WORK
(a) The work shall be carried out at such locations on the project, and in such order or precedence, as may be found necessary by the Engineer in order to expedite the completion of the project and minimize the impact on customers, traffic, and adjacent property owners. (b) Potable water main work shall be sequenced as follows, subject to modification by the Engineer:

1. Install line stop valve on existing 12" ACP water main in Hygeia Avenue, south of Leucadia Boulevard.
05/23/2023 C7 157 of 201

H-37

2. Install 12" x 12" cross with four (4) 12" valves. Connect valves (east and west) to existing 12" ACP water main. Abandon existing fire hydrant lateral by removing existing gate valve and installing blind flange.

3. Install new fire hydrant on Leucadia Boulevard, west of Hygeia Ave.

4. Build 12" PVC water main (north and south) with test plates and temporary end caps.

5. Complete pressure and bacteriological testing of new 12" PVC water main (north and south).

6. Tie in to existing 12" ACP water main (north and south). Remove existing 12" x 12" cross and four (4) existing 12" valves. Connect to existing 12" ACP water main (east and west) with 12" PVC water main.

7. Build 12" PVC water main (east and west), east of Hygeia Avenue with test plates and temporary end caps.

8. Complete pressure and bacteriological testing of new 12" PVC water main (east and west).

9. Tie in to existing 12" PVC/ACP water main (east and west). Replace two (2) fire hydrant lateral valves in Leucadia Boulevard, east of Hygeia Avenue.

10. Build 8" PVC water main (east and west), east of Hygeia Avenue with test plates and temporary end caps.

11. Complete pressure and bacteriological testing of new 8" PVC water main (east and west).

12. Tie in to existing 8" PVC water main (east and west).

13. Relocate water meter(s), fire hydrant(s) and 6" blow off pipe.

POTABLE WATER MAIN UTILITY INTERRUPTIONS AND CONNECTIONS (a) The Contractor shall give at least seven (7) days advance written notice to the San Dieguito Water District of its desire for an existing valve to be operated or an existing facility or pipeline to be shut down. The District will operate the existing valve or shut down the existing facility.

The Contractor will be responsible to provide the work zone and traffic control required for these aspects of the work.
(b) The Contractor shall also give at least seven (7) days advance written notice to the San Dieguito Water District requesting the supervision for the draining of a line, or a connection to an existing line performed by the Contractor.
(c) Shut-down periods for existing facilities shall be kept to a minimum - eight (8) hours maximum unless otherwise approved by the Engineer in writing. The Contractor shall 05/23/2023 C7 158 of 201

H-38

schedule its work accordingly. The shut-down will begin at 8:00 AM and shall not extend past 5:00 PM. The Contractor will be expected to break the pipe connections by 9:00 AM. The Contractor will need to restore the pipe connections and backfill by 4:00 PM. San Dieguito Water District staff will flush the lines and restore service by 5:00 PM.

The Contractor will be responsible to provide the work zone and traffic control required for these aspects of the work.
(d) No additional compensation will be paid for any work necessary to keep the shutdown periods within these requirements, nor for any work resulting from faulty operation or leakage through the existing valves. The Contractor shall provide, at its own expense, all equipment, materials, and labor whenever required by the Engineer to facilitate the drainage of the lines. The Contactor shall ensure no silt or debris are deposited in the gutters or storm drains. The Contactor shall ensure that waters from the leakage through existing valves do not enter into existing open pipes or fill the hole during construction. (e) Connections shall be made in accordance with the Plans, and testing shall be accomplished in accordance with Water Agency Standard Specifications. All ACP to PVC transition couplings indicated on the Plans require a restraint device on the PVC side of the coupling to prevent movement from taking place.
(f) Contractor shall verify the location of all utilities prior to commencing work. Underground Service Alert of Southern California shall be notified two (2) working days before field trenching. (1-800-422-4133)

306-3 TRENCH EXCAVATION

306-3.1 General. ADD the following:

A geotechnical engineering firm or individual licensed in the State of California shall monitor the soil conditions during the trench excavation and backfill operations.

306-6 BEDDING

306-6.5 Placement and Compaction
306-6.5.1 General. MODIFY as follows:

The first sentence of the first paragraph shall read: The material in the bedding zone shall be compacted mechanically.

DELETE the third paragraph in its entirety.

306-12 BACKFILL

306.12.1 General. MODIFY as follows:

Beneath paved surfaces, the upper 6” of trench backfill shall be compacted to 95% relative compaction.

306.12.4 Jetted Trench Backfill. DELETE this Subsection in its entirety.

05/23/2023 C7 159 of 201

H-39

306-14 MEASUREMENT

306-14.6 Temporary Resurfacing. REPLACE this Subsection with the following:

No separate measurement will be made for temporary resurfacing.

306-15 PAYMENT

306-15.1 General. REPLACE item “m” with the following:
m) all other work necessary to install the pipe, conduit, or structures complete in-place;

ADD the following:
n) shoring and bracing;
o) dewatering;
p) connections to existing pipes and structures;
q) fittings;
r) collars;
s) cleaning and removal of sediment and debris from existing drainage structures and pipes to remain;
t) air valves;
u) restrained joints;
v) blow offs;
w) couplings;
x) polymer water boxes;
y) furnishing, placing, maintaining, removing, and disposing of temporary resurfacing; z) drainage of lines, water shut-offs, and notifications.

306-15.2 Shoring and Bracing. REPLACE this Subsection with the following:

Full compensation for furnishing all labor, material, and equipment necessary to design, permit, and perform trench shoring and bracing is considered included in the various bid items that require shoring and bracing, and no additional compensation will be allowed therefor.

306-15.3 Dewatering. REPLACE this Subsection with the following:

Full compensation for furnishing all labor, material, and equipment necessary to perform dewatering is considered included in the various bid items that require dewatering, and no additional compensation will be allowed therefor.

306-15.5 Valves. REPLACE the first sentence of this Subsection with the following:

Payment for valves is considered included in the contract unit prices paid for linear footage of pipe, or fire hydrant lateral which they serve, and no additional compensation will be allowed therefor.

306-15.9 Temporary Resurfacing. DELETE this Subsection in its entirety.

SECTION 310 – PAINTING

310-5 PAINTING VARIOUS SURFACES

310-5.3 Painting Galvanized Surfaces. ADD the following:

Galvanized metal cable railing post coating application:
05/23/2023 C7 160 of 201

H-40

Target surfaces to be treated must be free of excessive oils, dirt, and other contaminants. All surfaces must be dry before application of colorant.

After areas to be treated have been prepared and the sample approved, apply colorant to target galvanized surfaces. Apply product according to the manufacturer′s instructions to achieve a color consistent with the approved sample.

Colorant must be applied uniformly. Irregularities (above and beyond those that the product naturally produces) must be corrected according to the product manufacturer′s recommendations.

Treated surfaces must be kept dry for a period of five (5) days following the application of colorant, or additional coats may be required.

Material should be applied outdoors with daytime temperatures above 60 degrees F and nighttime temperature, preferably, above 45 degrees F.

Treated surfaces must be stored properly at the construction yard after delivery and before, and up to, time of installation.

If components stack (as with guardrail), spacers should be placed between rows to allow for necessary airflow.

Items should be stacked perpendicular to the ground slope to allow for proper drainage.

Items should be elevated so they do not come into direct contact with soil or plant matter.

Any and all other standard storage procedures for galvanized metal should be met.

It is the responsibility of the Contractor to ensure that all components are stored properly on site.

SECTION 314 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS,

AND PAVEMENT MARKERS

314-2 REMOVAL OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS

314-2.2 Measurement. REPLACE this Subsection with the following:

No separate measurement will be made for the removal of traffic striping and curb and pavement markings.

314-2.3 Payment. REPLACE this Subsection with the following:

Full compensation for the removal of traffic striping and curb and pavement markings shall be included in the contract unit price paid for Clearing and Grubbing and no separate payment shall be made therefor.

314-3 REMOVAL OF PAVEMENT MARKERS

314-3.2 Measurement. REPLACE this Subsection with the following:

No separate measurement will be made for the removal of pavement markers.

05/23/2023 C7 161 of 201

H-41

314-3.3 Payment. REPLACE this Subsection with the following:

Full compensation for the removal of pavement markers shall be included in the contract unit price paid for Clearing and Grubbing and no separate payment shall be made therefor.

314-4 APPLICATION OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS

314-4.3 Painted Traffic Striping and Curb and Pavement Markings 314-4.3.5 Application. ADD the following:

The Contractor must obtain approval from the City’s Traffic Engineer on the striping layout prior to applying any permanent striping.

The Contractor shall furnish the necessary control points for all striping markings and shall be responsible for the completeness and accuracy thereof to the satisfaction of the Engineer.

Where applicable, the Contractor shall be responsible to mark and/or document the types and limits of existing striping, pavement markings and pavement markers in a manner adequate to ensure its replacement in original location, alignment, color size, and/or type. Control of alignment and layout shall be the responsibility of the Contractor and subject to approval by the Engineer.

Raised markings for fire hydrants shall be replaced in kind at all locations.

Two coats of striping paint shall be applied for all street striping. The first coat shall be applied a minimum of seven (7) days after the asphalt surface course has been placed. The second coat shall be applied seven (7) days after the first coat is applied. The maximum thickness of the two coats combined shall not be greater than 18 MILS when completely dried.

All newly placed pavement must receive temporary markings (i.e. – temporary tabs, etc.) as directed by the Engineer prior to any portion of the roadway being opened for travel. All temporary striping and/or markings shall be maintained by the Contractor until the permanent striping is complete and accepted by the City.

Contractor shall be responsible for maintaining safe traffic operation through the work area.

314-4.3.7 Payment. ADD the following:

Payment for the installation of traffic striping and curb and pavement markings including all labor, equipment, and materials shall be included in the contract lump sum price paid for Signing and Striping and no separate compensation will be allowed therefor.

Payment for the installation, maintenance, and removal of temporary striping and markings including all labor, equipment, and materials shall be included in the contract lump sum price paid for Traffic Control no separate compensation will be allowed therefor.

314-4.4 Thermoplastic Traffic Striping and Pavement Markings 314-4.4.6 Payment. ADD the following:

Payment for the installation of thermoplastic traffic striping and pavement markings including all labor, equipment, and materials shall be included in the contract lump sum price paid for Signing and Striping and no separate compensation will be allowed therefor.

05/23/2023 C7 162 of 201

H-42

314-5 PAVEMENT MARKERS

314-5.7 Payment. ADD the following:

Payment for the installation of pavement markers including all labor, equipment, and materials shall be included in the contract lump sum price paid for Signing and Striping and no separate compensation will be allowed therefor.

05/23/2023 C7 163 of 201

SAN DIEGO
3900 5th Avenue, Suite 310
San Diego, CA 92103

LOS ANGELES
714 W Olympic Blvd, Suite # 609
Los Angeles, CA 90015

ASSOCIATESASSOCIATESASSOCIATESASSOCIATES
05/23/2023 C7 164 of 201

00051960 4 Exhibit C, Page 1 of 3

EXHIBIT C

INSURANCE REQUIREMENTS
Contractor shall procure and maintain for the duration of the contract, [and for x years thereafter,] insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his agents, representatives, employees, or subcontractors. Nothing in these provisions shall limit Contractor’s Duty of Indemnification.

MINIMUM SCOPE AND LIMIT OF INSURANCE
Coverage shall be at least as broad as:

1. Commercial General Liability (“CGL”): Insurance Services Office Form CG 00 01 covering CGL on an “occurrence” basis, including products, completed operations, property damage, bodily injury, and personal & advertising injury with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this Project/location or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability: Insurance Services Office Form Number CA 0001 covering Code 1 (any auto), with limits no less than $2,000,000 per accident for bodily injury and property damage.

3. Workers’ Compensation insurance as required by the State of California, with Statutory Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per accident for bodily injury or disease.

Contractor shall also provide the additional coverages checked below and at least as broad as:

4. Professional Liability, with limits no less than $1,000,000 per occurrence or claim, and $2,000,000 policy aggregate.

If the Contractor maintains higher limits than the minimums shown above, City requires and shall be entitled to coverage for the higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to City.

Deductibles and Self-Insured Retentions
Any deductibles or self-insured retentions must be declared to and approved by City. At the option of City, either: the Contractor shall cause the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects City, its officers, officials, employees, and volunteers; or the Contractor shall provide a financial guarantee satisfactory to City guaranteeing payment of losses and related investigations, claim administration, and defense expenses.

Other Insurance Provisions
The insurance policies are to contain, or be endorsed to contain, the following provisions:
05/23/2023 C7 165 of 201

00051960 4 Exhibit C, Page 2 of 3

1. The City, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operations and automobiles owned, leased, hired, or borrowed by or on behalf of the Contractor. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10 and CG 20 37 forms if later revisions used), unless otherwise approved in advance by City.

2. For any claims related to this Project, the Contractor’s insurance coverage shall be primary insurance as respects City, its officers, officials, employees, and volunteers.

Any insurance or self-insurance maintained by City, its officers, officials, employees, and volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.

3. Each insurance policy required by this clause shall provide that coverage shall not be canceled, except with notice to City.

Claims Made Policies
If any coverage required is written on a claims-made coverage form:

1. The retroactive date must be shown, and this date must be before the execution date of the contract or the beginning of contract work.

2. Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of contract work.

3. If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the contract effective, or start of work date, the Contractor must purchase extended reporting period coverage for a minimum of five (5) years after completion of contract work.

4. A copy of the claims reporting requirements must be submitted to City for review.

Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best rating of no less than A: VII, unless otherwise acceptable to City.

Waiver of Subrogation
Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of City for all work performed by the Contractor, its employees, agents and subcontractors.

Verification of Coverage
Contractor shall furnish City with original certificates and amendatory endorsements, or copies of the applicable insurance language, effecting coverage required by this contract. All certificates and endorsements are to be received and approved by City before work 05/23/2023 C7 166 of 201

00051960 4 Exhibit C, Page 3 of 3
commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Contractor’s obligation to provide them. City reserves the right to require complete, certified copies of all required insurance policies, including endorsements, required by these specifications, at any time.

Subcontractors
Contractor shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure that City is an additional insured on insurance required from subcontractors. For CGL coverage, subcontractors shall provide coverage with a format least as broad as CG 20 38 04 13.

Special Risks or Circumstances
City reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other circumstances.

05/23/2023 C7 167 of 201

00051960 4 Exhibit D

AGREEMENT TO COMPLY WITH CALIFORNIA LABOR LAW REQUIREMENTS [Labor Code §§ 1720, 1771.1, 1773.8, 1775, 1776, 1777.5, 1813, 1860, 1861, 3700]

NOT APPLICABLE TO THIS CONTRACT

05/23/2023 C7 168 of 201

00051960 4 Exhibit E

EXHIBIT E

SPECIAL PROVISIONS
This Contract is subject to the following provisions, if checked:

1. State of California grant conditions, as attached.

2. Federal grant conditions, as attached.

3. Other conditions, as attached.

05/23/2023 C7 169 of 201

{00111183 1} Exhibit B

EXHIBIT B
CONTRACTOR’S PROPOSAL

05/23/2023 C7 170 of 201

{00111183 1} Exhibit C, Page 1 of 3

EXHIBIT C

INSURANCE REQUIREMENTS
Contractor shall procure and maintain for the duration of the contract, insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his agents, representatives, employees, or subcontractors. Nothing in these provisions shall limit Contractor’s Duty of Indemnification.

MINIMUM SCOPE AND LIMIT OF INSURANCE
Coverage shall be at least as broad as:

1. Commercial General Liability (“CGL”): Insurance Services Office Form CG 00 01 covering CGL on an “occurrence” basis, including products, completed operations, property damage, bodily injury, and personal & advertising injury with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this Project/location or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability: Insurance Services Office Form Number CA 0001 covering Code 1 (any auto), with limits no less than $2,000,000 per accident for bodily injury and property damage.

3. Workers’ Compensation insurance as required by the State of California, with Statutory Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per accident for bodily injury or disease.

Contractor shall also provide the additional coverages checked below and at least as broad as:

4. Professional Liability, with limits no less than $1,000,000 per occurrence or claim, and $2,000,000 policy aggregate.

If the Contractor maintains higher limits than the minimums shown above, City requires and shall be entitled to coverage for the higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to City.

Deductibles and Self-Insured Retentions
Any deductibles or self-insured retentions must be declared to and approved by City. At the option of City, either: the Contractor shall cause the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects City, its officers, officials, employees, and volunteers; or the Contractor shall provide a financial guarantee satisfactory to City guaranteeing payment of losses and related investigations, claim administration, and defense expenses.

Other Insurance Provisions
The insurance policies are to contain, or be endorsed to contain, the following provisions:

1. The City, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of with respect 05/23/2023 C7 171 of 201

{00111183 1} Exhibit C, Page 2 of 3
to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operations and automobiles owned, leased, hired, or borrowed by or on behalf of the Contractor. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10 and CG 20 37 forms if later revisions used), unless otherwise approved in advance by City.

2. For any claims related to this Project, the Contractor’s insurance coverage shall be primary insurance as respects City, its officers, officials, employees, and volunteers.

Any insurance or self-insurance maintained by City, its officers, officials, employees, and volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.

3. Each insurance policy required by this clause shall provide that coverage shall not be canceled, except with notice to City.

Claims Made Policies
If any coverage required is written on a claims-made coverage form:

1. The retroactive date must be shown, and this date must be before the execution date of the contract or the beginning of contract work.

2. Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of contract work.

3. If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the contract effective, or start of work date, the Contractor must purchase extended reporting period coverage for a minimum of five (5) years after completion of contract work.

4. A copy of the claims reporting requirements must be submitted to City for review.

Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best rating of no less than A: VII, unless otherwise acceptable to City.

Waiver of Subrogation
Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of City for all work performed by the Contractor, its employees, agents and subcontractors.

Verification of Coverage
Contractor shall furnish City with original certificates and amendatory endorsements, or copies of the applicable insurance language, effecting coverage required by this contract. All certificates and endorsements are to be received and approved by City before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Contractor’s obligation to provide them. City reserves the right to require 05/23/2023 C7 172 of 201

{00111183 1} Exhibit C, Page 3 of 3
complete, certified copies of all required insurance policies, including endorsements, required by these specifications, at any time.

Subcontractors
Contractor shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure that City is an additional insured on insurance required from subcontractors. For CGL coverage, subcontractors shall provide coverage with a format least as broad as CG 20 38 04 13.

Special Risks or Circumstances
City reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other circumstances.

05/23/2023 C7 173 of 201

{00111183 1} Exhibit D

AGREEMENT TO COMPLY WITH CALIFORNIA LABOR LAW REQUIREMENTS [Labor Code §§ 1720, 1771.1, 1773.8, 1775, 1776, 1777.5, 1813, 1860, 1861, 3700]

NOT APPLICABLE TO THIS CONTRACT

05/23/2023 C7 174 of 201

{00111183 1}Exhibit E

EXHIBIT E

SPECIAL PROVISIONS
This Contract is subject to the following provisions, if checked:

1. 2.

3. State of California grant conditions, as attached.

Federal grant conditions, as attached. Contractor shall comply with all subrecipient obligations.

Other conditions, as attached.
05/23/2023 C7 175 of 201

FY 2023 COMMUNITY PROJECT FUNDING
GRANT AGREEMENT NO. B-23-CP-CA-0157
Grantee Name: City of Vista
Grantee Address: 200 Civic Center Dr. Vista, CA 92084
Grantee's Unique Entity Identifier (UEI):

Grantee's Employer Identification Number (EIN)
Federal Award Identification Number (FAIN) B-23-CP-CA-0157 Assistance Listing Number and Name 14.251 Economic Development Initiative, Community Project Funding, and Miscellaneous Grants
Period of Performance/Budget Period Start Date Date of grant obligation Period of Performance/Budget Period End Date August 31, 2031 This Grant Agreement between the Department of Housing and Urban Development (HUD) and City of Vista (the Grantee) is made pursuant to the authority of the Consolidated Appropriations Act, 2023 (Public Law 117-328) and the Explanatory Statement for Division L of that Act, which was printed in the Senate section of the Congressional Record on December 20, 2022 (Explanatory Statement).

In reliance upon and in consideration of the mutual representations and obligations under this Grant Agreement, HUD and the Grantee agree as follows:

ARTICLE I. Definitions
The definitions at 2 CFR 200.1 apply to this Grant Agreement, except where this Grant Agreement specifically states otherwise.

Budget period is defined in 2 CFR 200.1 and begins and ends on the dates specified above for the Period of Performance/Budget Period Start Date and Period of Performance/Budget Period End Date.

Period of Performance is defined in 2 CFR 200. l and begins and ends on the dates specified above for the Period of Performance/Budget Period Start Date and Period of Performance/Budget Period End Date.

ARTICLE II. Total Grant Amount
Subject to the provisions of the Grant Agreement, HUD will make grant funds in the amount of $2,231,000 available to the Grantee.

ARTICLE III. Award-Specific Requirements
A. Federal Award Description. The Grantee must use the Federal funds provided under this Grant Agreement (Grant Funds) to carry out the Grantee's "Project." Unless changed in accordance with Article III, section C of this Grant Agreement, the Grantee's Project shall be as described in the Project Narrative that is approved by HUD as of the date that HUD signs this Grant Agreement. For reference, HUD will attach this approved Project Narrative as Appendix l to the Grant Agreement on the date that HUD signs this Grant Agreement.
05/23/2023 C7 176 of 201

FY 2023 COMMUNITY PROJECT FUNDING
GRANT AGREEMENT NO. B-23-CP-CA-0157
B. Approved Budget. The Grantee must use the Grant Funds as provided by the Approved Budget. Unless changed in accordance with Article III, section C of this Grant Agreement, the Approved Budget shall be the line-item budget that is approved by HUD as of the date that HUD signs this Grant Agreement. For reference, HUD will attach this approved line-item budget as Appendix 2 to this Grant Agreement on the date that HUD signs this Grant Agreement.

C. Project and Budget Changes. All changes to the Grantee's Project or Approved Budget must be made in accordance with 2 CFR 200.308 and this Grant Agreement. To request HUD's approval for a change in the Project or Approved Budget, the Grantee must submit a formal letter to the Director of HUD's Office of Economic Development -Congressional Grants Division through the assigned Grant Officer. The letter must be submitted by email to the assigned Grant Officer and must provide justification for the change. The email submitting the letter must also include a revised project narrative or revised line-item budget, as applicable, that includes the requested change. The Grantee is prohibited from making project or budget changes that would conflict with the Applicable Appropriations Act Conditions described in Article III, section D of this Grant Agreement. The assigned Grant Officer for this grant is provided in the Award Letter for this grant and found on HUD's website. The HUD Office of Economic Development - Congressional Grants Division will notify the Grantee in writing, by email, whether HUD approves or disapproves the change. Before the Grantee expends Grant Funds in accordance with any change approved by HUD or otherwise allowed by 2 CFR 200.308, the Grantee must update its grant information in Disaster Recovery Grant Reporting (DRGR) to reflect that change.

D. Applicable Appropriations Act Conditions. The conditions that apply to the Grant Funds as provided by the Consolidated Appropriations Act, 2023 and the Explanatory Statement are hereby incorporated and made part of this Grant Agreement. In the event of a conflict between those conditions, the conditions provided by the Act will govern. The Grant Funds are not subject to the Community Development Block Grants regulations at 24 CFR part 570 or Title I of the Housing and Community Development Act of 1974.

E. In accordance with 2 CFR 200.307(b ), costs incidental to the generation of program income may be deducted from gross income to determine program income, provided these costs have not been charged to the grant. As authorized under 2 CFR 200.307(e)(2), program income may be treated as an addition to the Federal award, provided that the Grantee uses that income for allowable costs under this Grant Agreement. In accordance with 2 CFR 200.307(b ), costs incidental to the generation of program income may be deducted from gross income to determine program income, provided these costs have not been charged to the grant. Any program income that cannot be expended on allowable costs under this Grant Agreement must be paid to HUD before closeout of the grant, unless otherwise specified by an applicable Federal statute.

Page 2 ends