ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: C6
Prepared by:

Erin Adams, Management Analyst
Jason Rivera, Capital Projects Manager Meeting Date: September 12, 2023 Approved by:

Greg Mayer, City Engineer
John Conley, City Manager Agenda Location: Consent Calendar SUBJECT: CIP 8225 and 8313: STREET REHABILITATION PROJECT 2023 – AWARD OF

CONTRACT
RECOMMENDATION:

1. Adopt City Council Resolution No. 2023- , awarding a construction contract to Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors for the Street Rehabilitation Project 2023 (CIP Numbers 8225 and 8313).

2.Adopt City Council Resolution No. 2023- , amending the Capital Project Budget for fiscal Years 2022/23 and 2023/24.

CORRELATION TO CITY COUNCIL GOALS: Fiscal Responsibility, Climate and Environmental Responsibility, and Traffic: Continue to improve the flow of traffic for all forms of travel, reduce congestion, and improve our roads and sidewalks.

PRIOR ACTION: On June 28, 2022, adopted City Council Resolution No. 2022-108, approving a Six-Year Capital Improvement Program and FYs 2022/23 and 2023/24 Capital Project Budget and authorizing appropriations for Fiscal Years 2022/23 and 2023/24 Capital Projects (Vote: 4-0, Ritter absent (Ritter experienced technical difficulties)).

STATEMENT ON THE SUBJECT: Capital Improvement Projects (CIP) Numbers 8225, Street Rehabilitation & Maintenance, and 8313, the Residential Street Rehabilitation projects, are designed to improve the overall condition of City streets. This project will significantly improve the asphalt surface of certain arterial and residential streets. A list of streets is included as Exhibit 5.

Staff advertised the project for competitive bids on July 27, 2023, on the City’s procurement website and online procurement portal, OpenGov. On August 17, 2023, the following four bids were received:

Bidder’s Name Office Location Total Bid Amount
Martin Marietta San Diego Aggregates, LLC San Diego, CA $7,691,608.81 dba ATP General Engineering Contractors
Eagle Paving Company, Inc. Poway, CA $8,231,488.00
Hazard Construction Engineering, LLC Lakeside, CA $8,683,036.10 TC Construction Company, Inc. Santee, CA $8,737,532.33 Engineer’s Estimate: $8,110,000
AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
Approved above recommendation, adopted the following: 1) City Council Resolution No. 2023-160. Vote: 5-0; 2) City Council Resolution No. 2023-161. Vote: 5-0.

MEETING DATE: September 12, 2023 PAGE 2
SUBJECT: CIP 8225 and 8313: STREET REHABILITATION PROJECT 2023 – AWARD OF

CONTRACT
Staff has reviewed the bid of $7,691,608.81 from Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors and has determined that they are the lowest responsible bidder who responded to all the requirements of the bid request. Therefore, staff recommends that the City Council award the contract for the Street Rehabilitation Project 2023 (CIP No. 8225) and the Residential Street Rehabilitation projects (CIP No. 8313) to Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors.

FISCAL IMPACT: The construction contract is $7,691,608.81, with a 10 percent contingency for a total budget of $8,460,769.69. Sufficient funding is budgeted and available in the Fiscal Year 2023/24 Capital Improvement Budgets in CIP Numbers 8225 and 8313, in Source Appropriation Accounts (Nos. 1116101.578999.8225, 0026555.578999.8225, 0026555.578999.8313 and 1296640.578999.8313). In order to use the most restrictive funding first, approval of this staff request will also amend the Capital Project Budget for Fiscal Year 2023/24 by appropriating $1,402,441 in deferred street construction funds to CIP 8225.

EXHIBITS:

1.City Council Resolution 2023- , awarding a construction contract to Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors for the Street Rehabilitation Project 2023 (CIP Numbers 8225 and 8313)

2.City Council Resolution 2023- , amending the Capital Project Budget for Fiscal Years 2022/23 and 2023/24

3.Contract with ATP General Engineering Contractors

4.Bid Documents – On file in the City Clerk’s Office

5.List of Streets
09/12/2023 C6 Page 2 of 57

00029213 7
RESOLUTION NO. 2023-

A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF

VISTA, CALIFORNIA, AWARDING A CONSTSRUCTION CONTRACT TO

MARTIN MARIETTA SAN DIEGO AGGREGATES LLC, DBA ATP GENERAL

ENGINEERING CONTRACTORS FOR THE STREET REHABILITATION
PROJECT 2023 (CIP NUMBERS 8225 AND 8313)
The City Council of the City of Vista does resolve as follows:

1. Findings. The City Council hereby finds and declares the following:

A.The City solicited bids for the Street Rehabilitation Project 2023 (CIP Nos. 8225 and 8313) and on August 17, 2023 public bids for construction were opened and ATP General Engineering contractors was the lowest bidder.

B.Staff determined that the bid submitted by Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors is responsive in all material aspects to the request for bids, and that the bid from ATP General Engineering Contractors for the construction of the Street Rehabilitation Project 2023 has been determined to be the lowest responsive, responsible bid.

2. Action.

A.The contract between the City of Vista and Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors for the Street Rehabilitation Project 2023 is approved, and the Mayor is authorized to execute the contract.

3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on September 12, 2023, by the following vote:

AYES:

NOES:

ABSTAIN:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY
By:

APPROVED
Walter C. Chung
20230825102046
JOHN B. FRANKLIN, MAYOR
ATTEST:

KATHY VALDEZ, CITY CLERK
By:
09/12/2023 C6 Page 3 of 57
EXHIBIT 1

00029213 7
RESOLUTION NO. 2023-

A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF

VISTA, CALIFORNIA, AMENDING THE CAPITAL PROJECT BUDGET FOR FISCAL YEARS 2022/23 AND 2023/24
The City Council of the City of Vista does resolve as follows:

1. Findings. The City Council hereby finds and declares the following:

A. On June 28, 2022, the City Council adopted Resolution 2022-108 approving the Six-Year Capital Improvement Program, the Capital Project Budget for Fiscal Years 2022/23 and 2023/24, and authorizing appropriations for Fiscal Years 2022/23 and 2023/24 capital projects.

B. The City Council desires to amend the Capital Project Budget at this time to reflect changed circumstances.

2. Action.

A. The Capital Project Budget for Fiscal Years 2022/23 and 2023/24 is amended as set forth in Exhibit A.

3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on ________________________, by the following vote:

AYES:

NOES:

ABSTAIN:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY
By:

APPROVED
Walter C. Chung
20230731113809

JOHN FRANKLIN, MAYOR
ATTEST:

KATHY VALDEZ, CITY CLERK
By:
09/12/2023 C6 Page 4 of 57
EXHIBIT 2

RESOLUTION NO. 2023-

CITY COUNCIL FOR THE CHARTERED CITY OF VISTA
PAGE 1 EXHIBIT A

1. Account Number Account Description Increase Decrease 1280000.310410 Deferred Street Construction - Fund Balance 1,402,441$ 1286565.578999.8225 Source Appropriation 1,402,441$
Appropriations are hereby made to fund the Street Rehabilitation Project 2023 (CIP Nos. 8225 and 8313). 09/12/2023 C6 Page 5 of 57

SUMMARY CONSTRUCTION – COV LOCAL Page 1 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba

ATP GENERAL ENGINEERING CONTRACTORS
[00064028-1] {00111737 1}

CONSTRUCTION CONTRACT
THIS CONTRACT is made and entered into as of _____________________________ (“Contract Date”), by and between the City of Vista, a chartered municipal corporation (“Agency”), and Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors, a California limited liability company (“Contractor”). Agency and Contractor are sometimes individually referred to as a “Party” and collectively as “Parties.” In consideration of the mutual covenants contained herein, Agency and Contractor agree as follows:

SECTION 1
The Contract Documents consisting of the PROJECT SPECIFICATIONS, comprised of the NOTICE INVITING BIDS, the INSTRUCTIONS TO BIDDERS, the accepted BID PROPOSAL; BID SCHEDULE; CONTRACTOR’S LICENSING STATEMENT; PROJECT REFERENCES; CONTRACTOR’S LIST OF SUBCONTRACTORS; PUBLIC CONTRACT CODE STATEMENTS AND QUESTIONNAIRE; NON-COLLUSION AFFIDAVITS; the CONSTRUCTION CONTRACT, CONTRACTOR’S CERTIFICATE, SUPPLEMENTARY GENERAL PROVISIONS, SUPPLEMENTARY TECHNICAL PROVISIONS, Special Provisions, Plans, Standard Plans and Specifications; together with all additions, deletions, modifications, appendices, and all addenda (1), as prepared prior to the date of bid opening setting forth any modifications or interpretations of any said documents, are hereby incorporated in and made a part of this Contract as fully as if set forth herein.

SECTION 2
For and in consideration of the payments and agreements to be made and performed by the Agency as set forth in said Contract Documents, the Contractor agrees with the Agency to construct

STREET REHABILITATION
as specifically set forth in documents entitled
STREET REHABILITATION PROJECT 2023
for which award of the Contract was made, to furnish at his own proper cost and expense all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, and to do everything required therein. In accordance with the provisions of Section 3700 of the Labor Code, the Contractor will be required to secure the payment of Worker’s Compensation Insurance for its employees.

SECTION 3
For furnishing all said services and materials, payment of premiums on insurance policies, obtaining all permits and licenses of a temporary nature, furnishing and removing all plant, temporary work or structures, tools, and equipment, and for doing all the Work contemplated and embraced in this Contract, also for all loss and damage arising out of the nature of the 09/12/2023 C6 Page 6 of 57EXHIBIT 3

SUMMARY CONSTRUCTION – COV LOCAL Page 2 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba

ATP GENERAL ENGINEERING CONTRACTORS
[00064028-1] {00111737 1}
aforesaid work during its progress or prior to acceptance from the action of the elements and from any unforeseen difficulties which may arise or be encountered in the prosecution of the Work, and for all other risks of any description connected with the Work, also for all expenses incurred by or in consequence of the suspension or discontinuance of work, except such as in the said Contract Documents are expressly stipulated to be borne by the Agency, and for well and faithfully completing the Work and the whole thereof within the stipulated time and in the manner shown and described in the said documents, and in accordance with the requirements of the Engineer under them, the Agency will pay, and the Contractor shall receive in full compensation therefore, the prices set forth by him in the accepted bid. The total compensation will be computed on the basis of the units of work actually performed in accordance with the requirements of the Contract Documents and paid for at the stipulated prices named in the BID SCHEDULE for completion of the Work.

SECTION 4
The Agency hereby promises and agrees with the said Contractor to employ, and does hereby employ the said Contractor to provide the materials and to do the Work according to the terms and conditions herein contained and referred to, for the price aforesaid, and hereby contracts to pay the same at the time, in the manner, and upon the conditions set forth in the Contract Documents, and the Parties for themselves, their heirs, executors, administrators, successors and assigns do hereby agree to the full performance of the covenants herein contained.

SECTION 5
Contractor agrees to indemnify, defend, and save harmless, the Agency, its officers, agents, employees and volunteers from and against any and all claims, demands, damages, losses and expenses, defense costs including attorney fees, or liability of any kind or nature which the Agency, its officers, agents and employees may sustain or incur or which may be imposed upon them for injury to or death of persons, or damage to property as a result of, arising out of, or in any manner connected with the Contractor’s performance under the terms of this Contract, caused in whole or in part by any negligent or willful acts or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, except where caused by the active negligence, sole negligence, or willful misconduct of the Agency.
[Continued on page 3.]
09/12/2023 C6 Page 7 of 57

SUMMARY CONSTRUCTION – COV LOCAL Page 3 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba

ATP GENERAL ENGINEERING CONTRACTORS
[00064028-1] {00111737 1}
SECTION 6
Contractor agrees that the Payment Bond and Performance Bond attached to/submitted concurrently with this Contract are for reference purposes only, and shall not be considered a part of this Contract. Contractor further agrees that said bonds are separate obligations of the Contractor and its surety, and that any attorneys’ fee provision contained in any payment bond or performance bond shall not apply to this Contract. In the event there is any litigation between the Parties arising from the breach of this Contract, each Party will bear its own attorneys’ fees in the litigation.

IN WITNESS WHEREOF, the Parties have caused this Contract to be executed as of the Contract Date.

CITY OF VISTA, a chartered municipal
corporation
By:

JOHN B. FRANKLIN, MAYOR
ATTEST:

KATHY VALDEZ, CITY CLERK
By:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY
By:

RISK MANAGEMENT REVIEW:

DOLORES GASCON, RISK MANAGER
By:

MARTIN MARIETTA SAN DIEGO
AGGREGATES, LLC dba ATP GENERAL
ENGINEERING CONTRACTORS, a
California limited liability company
By:

Name/Title
By:

Name/Title

APPROVED
Amanda L. Guy
20230825114831
09/12/2023 C6 Page 8 of 57

BID PROPOSAL
From: Martin Marietta San Diego Aggregates LLC dba ATP General Engineering Contractors For: The construction of

STREET IMPROVEMENTS
as specifically set forth in documents entitled
STREET REHABILITATION PROJECT 2023 (CIP No. 8225)
, Bidder,
The undersigned hereby proposes and agrees that if his bid as submitted in the attached BID SCHEDULE be accepted, he will contract in the form so approved to perform all work for which a Contract may be awarded him, to furnish any and all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore as provided in the Contract Documents, and to do everything required therein for the proposed Project as specifically set forth in said Contract Documents, together with appurtenances thereto, all as set forth on the Drawings and in the Project Specifications and other Contract Documents; and he further proposes and agrees to complete all the Work called for by the Drawings, Project Specifications, and other Contract Documents in strict conformity therewith within the time limits set forth therein; and that he will accept as full payment therefore the prices set forth in the BID SCHEDULE forming a part hereof.

The undersigned hereby submits either a Bid Bond or Bid Security in the form of Cash, a Cashier's Check, or a Certified Check, using the forms included in these Bid Documents, properly made payable to CITY OF VISTA, hereinafter designated as the Agency, in an amount that is at least ten percent (10%) of the total base bid amount. The Bid Bond or Bid Security is attached hereto and is given as a guaranty that the undersigned will execute the Contract and furnish the required bonds if awarded the Contract and, in case of failure to do so within the time provided, the proceeds of said bond or bid security shall be forfeited to the Agency. The Surety's liability to the Agency for forfeiture of the face amount of the bond shall be considered as established.

It is understood and agreed that:

1.The undersigned has carefully examined all Bid documents and other Documents which will form the Contract, including all addenda as prepared prior to the date of bid opening setting forth any modifications or interpretations of any said documents.

2.The undersigned has, by investigating the site of work, by reviewing and analyzing the Plans and Specifications, and by otherwise familiarizing himself with the Project, has satisfied himself as to the nature and location of the Work and has fully informed himself as to all conditions and matters which can in any way affect the Work or the cost thereof.

3.The undersigned fully understands the scope of the Work and has included in the various related items of Work the cost of all work not listed as a separate item so that the Bid for the Project reflects the total cost for completing the Work in its entirety, has checked carefully all words and figures inserted in this Bid, and he further agrees that the Agency shall in no way be responsible for any errors or omissions in the preparation of this proposal. 23 09/12/2023 C6 Page 9 of 57

09/12/2023 C6 Page 10 of 57

09/12/2023 C6 Page 11 of 57

09/12/2023 C6 Page 12 of 57

09/12/2023 C6 Page 13 of 57

27 BID SCHEDULE WORKSHEET
(Provided for reference only, see NOTE 1 page 26 above)

STREET REHABILITATION PROJECT 2023 (C.I.P. No. 8225)

BID SCHEDULE TO BE COMPLETED THROUGH THE CITY’S ELECTRONIC BIDDING SYSTEM

PROCURENOW (OPENGOV)

Base Bid Items

Bid
Item Description Of Work Qty. Unit Unit Price Item Total

GENERAL
1 Mobilization & Demobilization
(5% maximum of Total Base Bid) 1 LS
2 Project Information Sign 2 EA
3 Public Notification per Supplementary
General Provisions, Section 7-12.2 1 LS
4 Storm Water Pollution Prevention and
Erosion Control 1 LS
5 Traffic Control and Construction Staging
(Caltrans locations) 1 LS
6 Traffic Control and Construction Staging 1 LS
7 Variable Message Board and arrow board 6 EA

ASPHALT PAVEMENT REHABILITATION
8 4-foot Wide Header Cut (2.0-inch to 0-inch) 123,845 SF 9 15-foot Wide Header Cut at cross gutters 22,806 SF
10 2-inch Deep Cold Mill 1,335,588 SF
11 4-Inch Deep Dig Out 43,124 SF
12 1.5-inch Thick Leveling Course 2,180 TN
13 AC Fabric (Petromat Enviro) Appendix G 55,794 SY
09/12/2023 C6 Page 14 of 57

28 Bid
Item Description Of Work Qty. Unit Unit Price Item Total 14 PMAC Overlay (2-inch Thick) 7,199 TN
15 PMAC Overlay (2-inch Thick) with Pacific
Geosource Forta-Fi Fibers
(Appendix G)
19,121 TN

UTILITY AND MONUMENT COVER ADJUSTMENTS
16 Adjust 24-inch Manhole to Finish Grade 77 EA
17 Adjust 36-inch Manhole to Finish Grade 82 EA
18 Adjust 8” Sewer Clean out to Finish Grade 14 EA
19 Adjust Water Valve Cover to Finish Grade
(stipulated amount) 534 EA $300.00 $160,200.00
20 Adjust Gas Valve Cover to Finish Grade 23 EA
21 Adjust Monument Cover to Finish Grade 47 EA
22 Adjust Caltrans 8” detector Cover to Finish
Grade 7 EA
23 Adjust SDGE Vault to Finish Grade 4 EA

TRAFFIC
24 Replace Existing Traffic Signal Inductive
Loop Detectors 324 EA
25 Replace All Existing Striping (2 coats) 1 LS
26 Replace All Existing Thermoplastic
Crosswalks, Stop Bars, Legends, and
Arrows
1 LS

GENERAL CONCRETE SURFACE IMPROVEMENTS
27 PCC ADA Corner Ramp SDRSD G-27 Type A
with 6” aggregate base 11 EA
28 PCC ADA Corner Ramp SDRSD G-27 Type A
with Spandrel with 6” aggregate base 10 EA
29 PCC ADA Corner Ramp SDRSD G-29 Type C
with 6” aggregate base 6 EA
30 PCC ADA Corner Ramp SDRSD G-29 Type C
with Spandrel with 6” aggregate base 11 EA
31 PCC cross gutter SDRSD G-12 with 6”
aggregate base 2891 SF
09/12/2023 C6 Page 15 of 57

29 Bid
Item Description Of Work Qty. Unit Unit Price Item Total 32 1311 Lagan Ave Remove & Replace PCC
Curb & Gutter SDRSD G-02 with 6”
aggregate base
21 LF
33 1311 Lagan Ave - Remove & Replace PCC
sidewalk SDRSD G-07 with 6” aggregate
base
105 SF
34 Valencia Drive near Tangerine Grove -
Remove & Replace PCC Curb & Gutter
SDRSD G-02 with 6” aggregate base
21 LF
35 Valencia Drive near Tangerine Grove -
Remove & Replace sidewalk SDRSD G-07
with 6” aggregate base
170 SF
36 Valencia Drive at 3rd church dwy - Remove
& Replace PCC Curb & Gutter SDRSD G-02
with 6” aggregate base
66 LF
37 Valencia Drive at 3rd church dwy - Remove
& Replace sidewalk SDRSD G-07 with 6”
aggregate base
75 SF
38 Valencia Drive at 3rd church dwy - Remove
& Replace driveway SDRSD G-14B with 6”
aggregate base
273 SF
39 411 Palmbark St - Remove & Replace PCC
Curb & Gutter SDRSD G-02 with 6”
aggregate base
95 LF
40 411 Palmbark St - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
281 SF
41 411 Palmbark St - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
133 SF
42 423 Palmbark St - Remove & Replace PCC
Curb & Gutter SDRSD G-02 with 6”
aggregate base
40 LF
43 423 Palmbark St - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
262 SF
44 423 Palmbark St - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
210 SF
45 567 to 561 Stewart Dr - Remove &
Replace PCC Curb & Gutter SDRSD G-02
with 6” aggregate base
70 LF
46 567 Stewart Dr - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
136 SF
09/12/2023 C6 Page 16 of 57

30 Bid
Item Description Of Work Qty. Unit Unit Price Item Total 47 567 Stewart Dr - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
160 SF
48 561 to 545 Stewart Dr - Remove &
Replace PCC Curb & Gutter SDRSD G-02
with 6” aggregate base
86 LF
49 553 Stewart Dr - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
196 SF
50 553 Stewart Dr - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
150 SF
51 554 to 546 Stewart Dr - Remove &
Replace PCC Curb & Gutter SDRSD G-02
with 6” aggregate base
71 LF
52 554 Stewart Dr - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
137 SF
53 554 Stewart Dr - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
135 SF
54 633 Ascot Dr - Remove & Replace west
curb and gutter SDRSD G-02 with 6”
aggregate base
34 LF
55 633 Ascot Dr - Remove & Replace west
driveway SDRSD G-14D with 6” aggregate
base
150 SF
56 633 Ascot Dr - Remove & Replace sidewalk
at west driveway SDRSD G-07 with 6”
aggregate base
70 SF
57 Dana Dr & Maryland north corner - Remove
AC dike & replace with PCC G-01 6"Curb
with 6” aggregate base
76 LF
58 1356 Caren Rd - Remove & Replace PCC
Curb & gutter SDRSD G-02 with 6”
aggregate base
50 LF
59 1356 Caren Rd - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
216 SF
60 417 Santa Clara Dr - Remove & Replace
PCC 8" Curb & Gutter SDRSD G-02 with 6”
aggregate base
64 LF
61 417 Santa Clara Dr - Remove & Replace
sidewalk SDRSD G-07 with 6” aggregate
base
200 SF
09/12/2023 C6 Page 17 of 57

31 Bid
Item Description Of Work Qty. Unit Unit Price Item Total 62 417 Santa Clara Dr - Remove & Replace
driveway SDRSD G-14B with 6” aggregate
base
180 SF
63 2180 La Mirada Dr - Remove & Replace
PCC Curb SDRSD G-01 with 6” aggregate
base
17 LF
64 2180 La Mirada Dr - Remove & Replace
driveway (alley apron G-17) with 6”
aggregate base
200 SF
65 1251 Avenida Chelsea-inside curve -
Remove & Replace PCC 8" Curb & Gutter
SDRSD G-02 with 6” aggregate base
27 LF
66 1223 Avenida Chelsea - Remove &
Replace PCC 8" Curb & Gutter SDRSD G-02
with 6” aggregate base
87 LF
67 1230 Avenida Chelsea near east curb
outlet- Remove & Replace PCC 8" Curb &
Gutter SDRSD G-02 with 6” aggregate base
26 LF
68 1230 Avenida Chelsea - Remove &
Replace PCC curb outlet 5' wide D-25A with
6” aggregate base
1 LS
69 1230 Avenida Chelsea mid block- Remove
& Replace PCC Curb & Gutter SDRSD G-02
with 6” aggregate base
15 LF
70 816 Highland Dr – 3” AC ditch in shoulder
with 6” aggregate base 240 SF

NOTE: Determination of the lowest bid shall be based solely on the lowest TOTAL BASE BID FOR IMPROVEMENTS. Unit prices shall prevail over extended total and grand total prices. Late bids will not be accepted.

BID SCHEDULE WORKSHEET – END
(Provided for reference only, see NOTE 1 page 26)

BID SCHEDULE TO BE COMPLETED THROUGH THE CITY’S ELECTRONIC BIDDING SYSTEM

PROCURENOW (OPENGOV)

09/12/2023 C6 Page 18 of 57

32 A. Description of Base Bid Items:

GENERAL

Bid Item 1 - Mobilization & Demobilization (5% maximum of Total Base Bid): Bid item shall include full compensation for all bonds, insurance, sureties, licenses, permits, facilities, labor, equipment and material necessary to complete all work required in advance of construction operations, and upon the initiation of construction operations, to mobilize all required equipment, materials and personnel on-site, and complete all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The Bid Item shall also include all labor, equipment and material required to clean-up and restore the site, demobilize, and remove all equipment, materials, and staging, and complete all work required at the end of construction operations in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The lump sum price for this item shall not exceed 5% of the total contract price (5% maximum of Total Base Bid).

Bid Item 2 - Project Information Sign: Bid item shall include full compensation for labor, materials and equipment to fabricate, install and maintain 4x4 project information signs to be mounted to Variable Message Boards to notify the public and motorists of the project being constructed. An example of a past project information sign can be found in the appendix. A current project information sign will be provided at the Pre- Construction Meeting.

Bid Item 3 - Public Notification per Supplementary General Provisions, Section 7-12.2: Bid Item includes all public notifications in accordance with Section 7-12.2 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 4 - Storm Water Pollution Prevention and Erosion Control: Bid item shall include full compensation for submitting the required storm water permit (located in the appendix) including all labor, equipment and materials required to complete all work necessary to install, maintain, repair and replace all temporary construction BMPs to prevent the discharge of any materials into the storm drain system. No additional compensation will be made.

Bid Item 5 - Traffic Control and Construction Staging (Caltrans locations): Bidders/contractor shall review and understand the Pre-approved Caltrans Encroachment Permits with pre- approved site-specific Traffic control Plans for the SR78 crossings (Appendix K). Bid item shall include full compensation for all labor, equipment and materials required to complete all work required to prepare, coordinate, submit, meet all permit requirements, and obtain final approval of the Caltrans Encroachment permit including but not limited to Contractor Authorization form, Letter of Authorization for contractor, Water Pollution Control Plan/Stormwater pollution prevention plan. The encroachment permit is a no fee however if there is an unexpected fee associated with the Caltrans permit, the successful low bid contractor will be reimbursed the amount by the City of Vista. Bid item shall include full compensation for all labor, equipment and materials required to implement approved Caltrans traffic control plan (including message board, arrow boards, flagging costs and person(s) to safely control pedestrian and vehicular traffic), furnish tools, equipment and incidentals, and for doing all work involved in staging constructing, furnishing, placing, removing, storing, maintaining, moving to new locations, replacing and disposing of the components of the traffic control system (including traffic control devices, temporary steel plate bridging, temporary road resurfacing); installation and removal of all required temporary striping and signing associated and appurtenant work as specified in the Standard Specifications, the Supplementary General Provisions, Caltrans permit and as directed by the Engineer.

Bid Item 6 - Traffic Control and Construction Staging for City of Vista: Bid item shall include full compensation for all labor, equipment and materials required to complete all work required to prepare, submit and obtain approved (site specific) Traffic Control Plans from the City of Vista Traffic Engineering Department; implement 09/12/2023 C6 Page 19 of 57

33 traffic control (including flagging costs and person(s) to safely control pedestrian and vehicular traffic), furnish tools, equipment and incidentals, and for doing all work involved in staging constructing, furnishing, placing, removing, storing, maintaining, moving to new locations, replacing and disposing of the components of the traffic control system (including traffic control devices, temporary steel plate bridging, temporary road resurfacing); installation and removal of all required temporary striping and signing associated and appurtenant work as specified in the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer.

Bid Item 7 - Variable Message Board: Bid item shall include full compensation for labor, materials and equipment to place, install and maintain project changeable message boards and associated cones or other traffic control required to protect signs that will warn and inform motorist, pedestrians and the general public to use alternate routes and other information as directed by the Engineer. Multiple mobilizations and demobilization will be required based on the work being performed on a major street. Variable message boards shall be placed 5 days in advance of construction and through the duration of the street rehabilitation work under this bid item for arterials/collector roads. The message boards will be installed on the collector streets adjacent to the SR78 Caltrans crossings to inform the locationsseparate or in addition to Caltrans permit requirements within City right of way. Project Information Signs shall be mounted to two Variable Message Boards payable under Bid Item No. 2. No additional compensation will be made.

ASPHALT PAVEMENT REHABILITATION

Bid Item 8 - 4-foot Wide Header Cut (2.0-inch to 0-inch): Bid item shall include full compensation for all labor, equipment, material, and mobilization for the milling, removal, and disposal of existing AC pavement adjacent to existing PCC curb and gutter, AC driveways, AC berms, and existing pavement. The cold milling will be from 0-inch to a depth of 2.0-inches to provide a smooth 4’ transition and match the existing improvements bounding the sides of the street. The Work shall include milling, removal, hauling, disposal, and associated work, in accordance with Section 302-1 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 9 - 15-foot Wide Header Cut at crossgutters: Bid item shall include full compensation for all labor, equipment, material, and mobilization for the milling, removal, and disposal of existing AC pavement adjacent to existing PCC cross gutters and existing pavement. Where the street being rehabilitation intersects with another street or continuation of the same street the Header Cut shall taper for 15-feet. The cold milling will be from 0-inch to a depth of 2.0-inches to provide a smooth 15-foot transition. The Work shall include milling, removal, hauling, disposal, and associated work, in accordance with Section 302-1 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 10 – 2-inch-Deep Cold Mill: Bid item shall include full compensation for all labor, equipment, material, and mobilization for the removal of 2-inches of existing AC pavement. The Work shall include milling, removal, hauling, disposal, and associated work, in accordance with Section 302-1 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 11 – 4-inch Deep Dig Out: Bid item shall include full compensation for all labor, equipment, material, and mobilization for removal of 4-inches of existing street section (below the 2-inch-deep cold mill) and installation of asphalt concrete pavement. The Work shall include, but may not necessarily be limited to removal, hauling and disposal of 4-inches of existing street section, and installation of PG64-10 hot mix asphalt concrete pavement including, tack coat, distribution, spreading, rolling, compacting, joining, and 09/12/2023 C6 Page 20 of 57

34 appurtenant work, in accordance with Section 302-5.9 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 12 – 1.5-inch Thick Leveling Course: Bid item shall include full compensation for all labor, equipment, material, and mobilization for the placement of asphalt concrete pavement, Type III-C3-PG64-10, approved (Leveling Course). The Work shall include, but may not necessarily be limited to filling of milled areas, regrading necessary to provide a smooth finish surface providing positive drainage, restore roadway crown, and associated work, in accordance with Section 302-5 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 13 – AC Fabric (Petromat Enviro) Appendix G AC Fabric: Bid item shall include full compensation for all labor, equipment, material, and mobilization for the placement of asphalt concrete paving fabric. Asphalt concrete paving fabric shall be Petromat Enviro, see Appendix G. The Work shall include but may not necessarily be limited to installing hot tack coat, providing and installing pavement fabric with required overlaps. filling of milled areas, regrading necessary to provide a smooth finish surface providing positive drainage, restore roadway crown, and associated work, in accordance with Section 302-7 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 14 – PMAC Overlay (2-inch Thick): Bid item shall include full compensation for all labor, equipment, material, and mobilization for installation of 1.5-inch and 2-inch surface course (as specified per street) of Polymer Modified Asphalt Concrete (PMAC), compacted in place. The final AC surface will be completed at the end of the project to provide a clean, uniform, and finished look throughout the project limits. The Work shall include, but may not necessarily be limited to tack coat or trackless tack coat, distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 302-5.9 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 15 – PMAC Overlay (2-inch Thick) with Pacific Geosource Forta-Fi Fibers (Appendix G): Bid item shall include full compensation for all labor, equipment, material, and mobilization for installation of 1.5-inch and 2-inch surface course (as specified per street) of Polymer Modified Asphalt Concrete (PMAC), compacted in place. Bid item shall include full compensation for all labor, equipment, material, and mobilization for addition of Pacific Geosource Forta-Fi Fibers (Appendix G) to the AC mix at the plant per the manufacturer’s specifications and recommendations. The final AC surface will be completed at the end of the project to provide a clean, uniform, and finished look throughout the project limits. The Work shall include, but may not necessarily be limited to tack coat or trackless tack coat, distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 302-5.9 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

UTILITY AND MONUMENT COVER ADJUSTMENTS

Bid Item 16 - Adjust 24-inch Manhole to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing 24-inch manholes to flush and even with final finish 09/12/2023 C6 Page 21 of 57

35 pavement surfaces, including concrete collar (the collar grade elevation shall be 1.5-inches to 2-inches below the AC overlay), and all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 17 - Adjust 36-inch Manhole to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing 36-inch manholes to flush and even with final finish pavement surfaces, including concrete collar (the collar grade elevation shall be 1.5-inches to 2-inches below the AC overlay), and all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 18 - Adjust 8” Sewer Clean out to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing gas valve cover flush and even with final finish pavement surfaces, including all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 19 - Adjust Water Valve Cover to Finish Grade (stipulated amount): Bid item shall include full compensation for all labor, equipment and material required to adjust existing water valve covers flush and even with final and temporary finish surfaces per VID Specifications and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. If this work is performed by VID forces the Contractor will not be entitled to perform this work. This Bid Item is not subject to Section 3 Changes In Work.

Bid Item 20 - Adjust Gas Valve Cover to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing gas valve cover flush and even with final finish pavement surfaces, including all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 21 - Adjust Monument Cover to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing monument cover flush and even with final finish pavement surfaces, including all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 22 - Adjust Caltrans 8” detector Cover to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing detector cover flush and even with final finish pavement surfaces, including all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

Bid Item 23 - Adjust SDGE Vault to Finish Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing SDGE vault cover flush and even with final finish pavement surfaces, including all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made.

TRAFFIC

Bid Item 24 - Replace Existing Traffic Signal Inductive Loop Detectors: Bid item shall include full compensation for all labor, equipment and material required to document all existing traffic signal inductive loop detectors, 09/12/2023 C6 Page 22 of 57

36 and replace them at the same locations, and any other related work shall be considered as included or included in the costs of other work in accordance with Section 307-17.7.3 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Bid item shall include full compensation for all labor, equipment and material required to replace all traffic signal inductive loop detectors as directed by the Engineer, shown on the plans for City of Vista Standard Drawing TRF-05 Standard Loop Detector Layout and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 25 – Replace All Existing Striping (2 coats): Bid item shall include full compensation for all labor, equipment and material required to document all existing traffic striping, pavement markings, and replace it at the completion of the street rehabilitation with 2 coats of paint, and any other related work shall be considered as included or included in the costs of other work in accordance with Section 314-4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Bid item shall include full compensation for all labor, equipment and material required to provide all traffic striping and markings as directed by the Engineer, and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

Bid Item 26: - Replace All Existing Thermoplastic Crosswalks, Stop Bars, Legends, and Arrows: Bid item shall include full compensation for all labor, equipment and material required to document all existing thermoplastic crosswalks, stop bars, legends and arrows pavement markings prior to cold milling or paving operations, and replace it at the completion of the street rehabilitation, and any other related work shall be considered as included or included in the costs of other work in accordance with Section 314 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Bid item shall include full compensation for all labor, equipment and material required to provide all thermoplastic as directed by the Engineer, and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

GENERAL CONCRETE SURFACE IMPROVEMENTS

Bid Item 27 – PCC ADA Corner Ramp SDRSD G-27 Type A: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of existing concrete or asphalt street corner from ECR to ECR as shown on the exhibit, remove and recompact existing subgrade material, install and compact 6-inches of aggregate base under proposed curb and gutter, sidewalk, and corner ramp, install PCC curb and gutter, PCC sidewalk, and PCC Corner Ramp per SDRSD G-27, Type A with truncated domes (grey color), reinstall signage on new pole (if applicable), full depth AC slot patch and reestablish any cut irrigation lines from the work, as directed by the Engineer, shown on the plans and any other related work shall be considered as included in the per each cost bid as stated in the Bid Schedule and no additional compensation will be made.

Bid Item 28 – PCC ADA Corner Ramp SDRSD G-27 Type A w/ Spandrel: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of existing concrete or asphalt street corner from ECR to ECR and spandrel as shown on the exhibit, remove and recompact existing subgrade material, install and compact 6-inches of aggregate base under proposed spandrel, curb and gutter, sidewalk, and corner ramp, dowel new spandrel into existing cross gutter, install PCC spandrel, PCC curb and gutter, PCC sidewalk, and PCC Corner Ramp per SDRSD G-27, Type A with truncated domes (grey color), reinstall signage on new pole (if applicable), full depth AC slot patch and reestablish any cut irrigation lines from the work, as directed by the Engineer, shown on the plans and any other related work shall be considered as included in the per each cost bid as stated in the Bid Schedule and no additional compensation will be made.

Bid Item 29 – PCC ADA Corner Ramp SDRSD G-29 Type C: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of existing concrete or asphalt street corner from ECR to ECR as shown on the exhibit, remove and recompact existing subgrade material, install and 09/12/2023 C6 Page 23 of 57

37 compact 6-inches of aggregate base under proposed curb and gutter, sidewalk, and corner ramp, install PCC curb and gutter, PCC sidewalk, and PCC Corner Ramp per SDRSD G-27, Type C with truncated domes (grey color), reinstall signage on new pole (if applicable), full depth AC slot patch and reestablish any cut irrigation lines from the work, as directed by the Engineer, shown on the plans and any other related work shall be considered as included in the per each cost bid as stated in the Bid Schedule and no additional compensation will be made.

Bid Item 30 – PCC ADA Corner Ramp SDRSD G-29 Type C w/ Spandrel: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of existing concrete or asphalt street corner from ECR to ECR and spandrel as shown on the exhibit, remove and recompact existing subgrade material, install and compact 6-inches of aggregate base under proposed spandrel, curb and gutter, sidewalk, and corner ramp, dowel new spandrel into existing cross gutter, install PCC spandrel, PCC curb and gutter, PCC sidewalk, and PCC Corner Ramp per SDRSD G-27, Type C with truncated domes (grey color), reinstall signage on new pole (if applicable), full depth AC slot patch and reestablish any cut irrigation lines from the work, as directed by the Engineer, shown on the plans and any other related work shall be considered as included in the per each cost bid as stated in the Bid Schedule and no additional compensation will be made.

Bid Item 31 – Remove and Replace PCC Cross Gutter: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing cross gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the cross gutter, install and compact 6” of aggregate base, dowel both sides of existing cross gutter being tied to, install PCC Cross Gutter per SDRSD G- 12 to the dimensions and slopes of existing cross gutter, full depth AC slot patch as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 32 –1311 Lagan Ave Remove & Replace PCC Curb & Gutter SDRSD G-02 – Remove and Replace PCC Curb and Gutter: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 33 – 1311 Lagan Ave - Remove & Replace PCC sidewalk SDRSD G-07 – Remove and Replace PCC Sidewalk: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-

5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 34 – Valencia Drive near Tangerine Grove - Remove & Replace PCC Curb & Gutter SDRSD G-02– Remove and Replace PCC Curb and Gutter: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 09/12/2023 C6 Page 24 of 57

38 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 35 – Valencia Drive near Tangerine Grove - Remove & Replace sidewalk SDRSD G-07– Remove and Replace PCC Sidewalk: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 36 – Valencia Drive at 3rd church dwy - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of:
existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 37 – Valencia Drive at 3rd church dwy - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 38 – Valencia Drive at 3rd church dwy - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 39 – 411 Palmbark St - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 40 – 411 Palmbark St - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, 09/12/2023 C6 Page 25 of 57

39 remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 41 – 411 Palmbark St - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 42 – 423 Palmbark St - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 43 – 423 Palmbark St - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 44 – 423 Palmbark St - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 45 – 567 to 561 Stewart Dr - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.
09/12/2023 C6 Page 26 of 57

40 Bid Item 46 – 567 Stewart Dr - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 47 – 567 Stewart Dr - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 48 – 561 to 545 Stewart Dr - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 49 – 553 Stewart Dr - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 50 – 553 Stewart Dr - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 51 – 554 to 546 Stewart Dr - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard 09/12/2023 C6 Page 27 of 57

41 Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 52 – 554 Stewart Dr - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 53 – 554 Stewart Dr - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 54 – 633 Ascot Dr - Remove & Replace west curb and gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 55 – 633 Ascot Dr - Remove & Replace west driveway SDRSD G-14D: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 56 –633 Ascot Dr - Remove & Replace sidewalk at west driveway SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 57 - Dana Dr & Maryland north corner - Remove AC dike & Replace with PCC G-01 6" Curb: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of:
existing AC dike, AC pavement, remove and compact existing subgrade material to a maximum of 6” below the 09/12/2023 C6 Page 28 of 57

42 bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, 6” curb per SDRSD G-01, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 58 – 1356 Caren Rd - Remove & Replace PCC Curb & gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 59 – 1356 Caren Rd - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 60 – 417 Santa Clara Dr - Remove & Replace PCC 8" Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 61 –417 Santa Clara Dr - Remove & Replace sidewalk SDRSD G-07: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing sidewalk, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new sidewalk, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Sidewalk, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 62 –417 Santa Clara Dr - Remove & Replace driveway SDRSD G-14B: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway Entrance per SDRSD G-14, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made. 09/12/2023 C6 Page 29 of 57

43 Bid Item 63 – 2180 La Mirada Dr - Remove & Replace Curb SDRSD G-01: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC 6” curb per SDRSD G-1, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 64 –2180 La Mirada Dr - Remove & Replace driveway (alley apron SDRSD G-17): Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing driveway entrance, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new driveway entrance, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Driveway (alley apron) per SDRSD G-17, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 65 – 1251 Avenida Chelsea - inside curve - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of:
existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 66 – 1223 Avenida Chelsea - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 67 – 1230 Avenida Chelsea near east curb outlet - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 68 – 1230 Avenida Chelsea -Remove & Replace PCC Curb Outlet 5’ wide SDRSD D-25A: Bid item shall include full compensation for all labor, equipment and material required to sawcut, remove and dispose 09/12/2023 C6 Page 30 of 57

44 of: sawcut existing curb outlet, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC curb outlet per SDRSD D-25A, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Dowel and epoxy into existing curb outlet. Adjust all existing irrigation. No additional compensation will be made.

Bid Item 69 – 1230 Avenida Chelsea mid-block C&G - Remove & Replace PCC Curb & Gutter SDRSD G-02: Bid item shall include full compensation for all labor, equipment and material required to remove and dispose of: existing curb and gutter, remove and compact existing subgrade material to a maximum of 6” below the bottom of the new curb and gutter, remove tree roots in conflict with the Work, install and compact 6” of aggregate base, install PCC Type G curb and gutter per SDRSD G-2, install full depth AC slot patch, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work in accordance with Section 303-5.1.4 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. No additional compensation will be made.

Bid Item 70– 816 Highland Dr – 3” thick AC ditch in shoulder: Bid item shall include full compensation for all labor, equipment, material, and mobilization for installation of 3” thick asphalt concrete ditch along the shoulder. The Work shall include, but may not necessarily preparatory grading and compaction be limited to tack coat or trackless tack coat, distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 302-5.9 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made.

B. Street Rehabilitation Work Required By Street Segment:

On the Street Rehabilitation Project 2023, the Contractor shall install asphalt concrete by the end of the day in which the street received a 2-inch cold mill. No streets shall be left in a cold milled condition by the end of the workday under the specified working hours for that street. Header cuts are acceptable to be left overnight, in which, temporary AC ramping may be required.

Highland Drive shall be completed first due to City Council priority. Highland Dr (Judilyn to Rose Dr- 2” grind/overlay with fibers), Highland Dr (Rose Dr to Maryland Dr- 2” grind/overlay with fibers), Highland Dr (Judilyn Dr to 150’ north of Olive Ave – leveling coarse and AC fabric) and Highland Dr (150’ north of Olive to to Olive Ave- 2” grind/overlay with fibers)

Leveling coarse and AC fabric
Huff St (Spur), Palm Bark St, Cinchona St, Lagan Avenue, Valencia Dr, Bonita Dr, Palmbark St, Ruby Dr (Spur 550’ S/Olive Ave), Ruby Dr (Spur 270’ S/Olive Ave), Moon Rd , Stewart Dr, Ascot Dr, Judilyn Dr, Cielita Linda Dr , Cocapah St, Dana Dr, Huff St, Caren Rd, Durian Ct, Rose Dr, Santa Clara Dr ,Jonathon St, Highland Dr (Judilyn Dr to 150’ north of Olive Dr): Street is marked showing areas of dig outs. Remove and replace 4- inches of street section as a dig out at marked locations. Streets shall have 4-foot-wide header cut (2” to 0”) required along gutter lip (and/or along street edge or 12-inches from outside edge of white edge line) and 15- feet wide where street joins perpendicular street or at existing cross gutter. Approximately, 1.5-inches of leveling course shall be installed between header cuts to fill cracks, smooth the surface, and to develop crown.

Paving fabric shall be installed over hot tack coat from gutter lip to gutter lip with overlaps. 2.0-inches of PMAC to be overlaid over paving fabric.

09/12/2023 C6 Page 31 of 57

45 2” Grind & Overlay (AC with fibers)
Joshua Way, Commerce Way, La Mirada Dr, Ave Chelsea, Wesley Way, Ash St, Old Foothill Drive, Green Oak Rd, S. Emerald Dr (SR78 to Hacienda Dr), Emerald Dr S (Hacienda Dr to City Limits (Skyhaven Rd), Lupine Hills Dr (Shadowridge Dr (W) toParkview Dr), Lupine Hills Dr (Parkview Dr to Coronado Pl), Lupine Hills Dr (Coronado Pl to Links Way (E)), Lupine Hills Dr (Links Way (E) to Optimist Way), Lupine Hills Dr (Optimist Way to Shadowridge Dr (E)), Sunset Dr (Crestview Rd to Seaview Pl), Sycamore Av NB (SR78 to University Dr), Sycamore Av SB (SR78 to Thibodo Rd), Civic Center Dr SB (Pala Vista Dr to RR Tracks), Civic Center Dr NB (RR Tracks to Pala Vista Dr), Civic Center Drive (Crest View Rd to RR Tracks), Emerald Dr S (SR 78 to W. Vista Way), Melrose Dr S (Hacienda Dr to SR78), Melrose Dr N (SR 78 to W. Vista Way), Vista Village Dr (Hacienda Dr to SR78), Vista Village Dr (SR78 to Lado de Loma), Vista Village Dr (Lado de Loma to W. Vista Way), Mar Vista Dr (SR78 to Stoneridge Terrace), Highland Dr (Maryland Dr to Rose Dr to Judilyn Dr), Highland Dr (150’ north of Olive to Olive Ave) : Street is marked showing areas of dig outs. Remove and replace 4-inches of street section as a dig out at marked locations. Streets shall be cold milled 2-inches from gutter lip to gutter lip, tack coat and shall receive 2-inch PMAC with fibers (Appendix G) overlay.

09/12/2023 C6 Page 32 of 57

Street Rehabilitation Project 2023
Bid Tabulation for ATP General Engineering Contractors
Line
Item Description Quantity
Unit of
Measure Unit Cost Total
1 Mobilization & Demobilization
(5% maximum of Total Base Bid)1 LS $380,000.00 $380,000.00 2 Project Information Sign 2 EA $750.00 $1,500.00
3 Public Notification per Supplementary General Provisions, Section 1 LS $25,000.00 $25,000.00 4 Storm Water Pollution Prevention and Erosion Control 1 LS $1,500.00 $1,500.00 5 Traffic Control and Construction Staging (Caltrans locations)1 LS $203,500.00 $203,500.00 6 Traffic Control and Construction Staging 1 LS $462,000.00 $462,000.00 7 Variable Message Board and arrow board 6 EA $4,000.00 $24,000.00 8 4-foot Wide Header Cut (2.0-inch to 0-inch)107,025 SF $.54 $57,793.50 9 15-foot Wide Header Cut at cross gutters 22,806 SF $.54 $12,315.24 10 2-inch Deep Cold Mill 1,335,588 SF $.54 $721,217.52
11 4-Inch Deep Dig Out 43,124 SF $7.00 $301,868.00
12 1.5-inch Thick Leveling Course 2,180 TN $135.00 $294,300.00 13 AC Fabric (Petromat Enviro) Appendix G 55,794 SY $3.20 $178,540.80 14 PMAC Overlay (2-inch Thick)7,199 TN $128.00 $921,472.00 15 PMAC Overlay (2-inch Thick) with Pacific Geosource Forta-Fi Fibers 19,121 TN $140.00 $2,676,940.00 16 Adjust 24-inch Manhole to Finish Grade 77 EA $875.00 $67,375.00 17 Adjust 36-inch Manhole to Finish Grade 82 EA $950.00 $77,900.00 18 Adjust 8” Sewer Clean out to Finish Grade 14 EA $575.00 $8,050.00 19 Adjust Water Valve Cover to Finish Grade (stipulated amount)534 EA $300.00 $160,200.00 20 Adjust Gas Valve Cover to Finish Grade 23 EA $575.00 $13,225.00 21 Adjust Monument Cover to Finish Grade 47 EA $825.00 $38,775.00 22 Adjust Caltrans 8” detector Cover to Finish Grade 7 EA $750.00 $5,250.00 23 Adjust SDGE Vault to Finish Grade 4 EA $3,575.00 $14,300.00 24 Replace Existing Traffic Signal Inductive Loop Detectors 324 EA $530.00 $171,720.00 25 Replace All Existing Striping (2 coats)1 LS $150,000.00 $150,000.00 26 Replace All Existing Thermoplastic Crosswalks, Stop Bars, Legends, 1 LS $175,000.00 $175,000.00 27 PCC ADA Corner Ramp SDRSD G-27 Type A with 6” aggregate base 11 EA $5,000.00 $55,000.00 28 PCC ADA Corner Ramp SDRSD G-27 Type A with Spandrel with 6” 10 EA $9,500.00 $95,000.00 29 PCC ADA Corner Ramp SDRSD G-29 Type C with 6” aggregate base 6 EA $5,500.00 $33,000.00 30 PCC ADA Corner Ramp SDRSD G-29 Type C with Spandrel with 6” 11 EA $9,850.00 $108,350.00 31 PCC cross gutter SDRSD G-12 with 6” aggregate base 2,891 SF $22.00 $63,602.00 32 1311 Lagan Ave Remove & Replace PCC Curb & Gutter SDRSD G-02 21 LF $115.00 $2,415.00 33 1311 Lagan Ave - Remove & Replace PCC sidewalk SDRSD G-07 105 SF $19.25 $2,021.25 34 Valencia Drive near Tangerine Grove - Remove & Replace PCC Curb & Gutter SDRSD G-02 with 6” aggregate base 21 LF $115.00 $2,415.00 35 Valencia Drive near Tangerine Grove - Remove & Replace sidewalk SDRSD G-07 with 6” aggregate base 170 SF $19.25 $3,272.50 36 Valencia Drive at 3rd church dwy - Remove & Replace PCC Curb & Gutter SDRSD G-02 with 6” aggregate base 66 LF $95.00 $6,270.00 37 Valencia Drive at 3rd church dwy - Remove & Replace sidewalk 75 SF $19.25 $1,443.75 38 Valencia Drive at 3rd church dwy - Remove & Replace driveway 273 SF $19.25 $5,255.25 39 411 Palmbark St - Remove & Replace PCC Curb & Gutter SDRSD G-95 LF $115.00 $10,925.00 40 411 Palmbark St - Remove & Replace sidewalk SDRSD G-07 with 6” 281 SF $19.25 $5,409.25 41 411 Palmbark St - Remove & Replace driveway SDRSD G-14B with 133 SF $27.25 $3,624.25 42 423 Palmbark St - Remove & Replace PCC Curb & Gutter SDRSD G-40 LF $115.00 $4,600.00 43 423 Palmbark St - Remove & Replace sidewalk SDRSD G-07 with 6” 262 SF $19.25 $5,043.50 44 423 Palmbark St - Remove & Replace driveway SDRSD G-14B with 210 SF $27.25 $5,722.50 09/12/2023 C6 Page 33 of 57

Street Rehabilitation Project 2023
Bid Tabulation for ATP General Engineering Contractors
45 567 to 561 Stewart Dr - Remove & Replace PCC Curb & Gutter 70 LF $115.00 $8,050.00 46 567 Stewart Dr - Remove & Replace sidewalk SDRSD G-07 with 6” 136 SF $19.25 $2,618.00 47 567 Stewart Dr - Remove & Replace driveway SDRSD G-14B with 160 SF $27.25 $4,360.00 48 561 to 545 Stewart Dr - Remove & Replace PCC Curb & Gutter 86 LF $115.00 $9,890.00 49 553 Stewart Dr - Remove & Replace sidewalk SDRSD G-07 with 6” 196 SF $19.25 $3,773.00 50 553 Stewart Dr - Remove & Replace driveway SDRSD G-14B with 150 SF $27.25 $4,087.50 51 554 to 546 Stewart Dr - Remove & Replace PCC Curb & Gutter 71 LF $115.00 $8,165.00 52 554 Stewart Dr - Remove & Replace sidewalk SDRSD G-07 with 6” 137 SF $19.25 $2,637.25 53 554 Stewart Dr - Remove & Replace driveway SDRSD G-14B with 135 SF $27.25 $3,678.75 54 633 Ascot Dr - Remove & Replace west curb and gutter SDRSD G-34 LF $115.00 $3,910.00 55 633 Ascot Dr - Remove & Replace west driveway SDRSD G-14D 150 SF $27.25 $4,087.50 56 633 Ascot Dr - Remove & Replace sidewalk at west driveway 70 SF $19.25 $1,347.50 57 Dana Dr & Maryland north corner - Remove AC dike & replace with PCC G-01 6"Curb with 6” aggregate base 76 LF $115.00 $8,740.00 58 1356 Caren Rd - Remove & Replace PCC Curb & gutter SDRSD G-02 50 LF $115.00 $5,750.00 59 1356 Caren Rd - Remove & Replace driveway SDRSD G-14B with 6” 216 SF $19.25 $4,158.00 60 417 Santa Clara Dr - Remove & Replace PCC 8" Curb & Gutter 64 LF $115.00 $7,360.00 61 417 Santa Clara Dr - Remove & Replace sidewalk SDRSD G-07 with 200 SF $19.25 $3,850.00 62 417 Santa Clara Dr - Remove & Replace driveway SDRSD G-14B 180 SF $27.25 $4,905.00 63 2180 La Mirada Dr - Remove & Replace PCC Curb SDRSD G-01 with 17 LF $115.00 $1,955.00 64 2180 La Mirada Dr - Remove & Replace driveway (alley apron G-200 SF $27.25 $5,450.00 65 1251 Avenida Chelsea-inside curve - Remove & Replace PCC 8" Curb & Gutter SDRSD G-02 with 6” aggregate base 27 LF $115.00 $3,105.00 66 1223 Avenida Chelsea - Remove & Replace PCC 8" Curb & Gutter 87 LF $115.00 $10,005.00 67 1230 Avenida Chelsea near east curb outlet- Remove & Replace PCC 8" Curb & Gutter SDRSD G-02 with 6” aggregate base 26 LF $115.00 $2,990.00 68 1230 Avenida Chelsea - Remove & Replace PCC curb outlet 5' wide 1 LS $9,500.00 $9,500.00 69 1230 Avenida Chelsea mid block- Remove & Replace PCC Curb & Gutter SDRSD G-02 with 6” aggregate base 15 LF $115.00 $1,725.00 70 816 Highland Dr – 3” AC ditch in shoulder with 6” aggregate base 240 SF $35.00 $8,400.00 Total $7,691,608.81
09/12/2023 C6 Page 34 of 57

09/12/2023 C6 Page 35 of 57

09/12/2023 C6 Page 36 of 57

09/12/2023 C6 Page 37 of 57

09/12/2023 C6 Page 38 of 57

09/12/2023 C6 Page 39 of 57

09/12/2023 C6 Page 40 of 57

09/12/2023 C6 Page 41 of 57

09/12/2023 C6 Page 42 of 57

09/12/2023 C6 Page 43 of 57

09/12/2023 C6 Page 44 of 57

09/12/2023 C6 Page 45 of 57

09/12/2023 C6 Page 46 of 57

09/12/2023 C6 Page 47 of 57

09/12/2023 C6 Page 48 of 57

09/12/2023 C6 Page 49 of 57

CITY OF VISTA Page 1 of 2 MARTIN MARIETTA SAN DIEGO AGGREATES, LLC dba

ATP GENERAL ENGINEERING CONTRACTS
{00111739 1} [00065304 3] PAYMENT BOND (LABOR & MATERIALS) Bond No.

Premium: $
Effective Date:

PAYMENT BOND
(LABOR AND MATERIALS)

KNOW ALL PERSONS BY THESE PRESENTS that:

The City of Vista (“City”) has awarded a contract (the “Contract”) to Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors (“Principal”) as follows:

Street Rehabilitation Project 2023,
which Contract, and all Contract Documents set forth therein, are incorporated herein and made a part thereof by this reference.

Principal is required under the terms of the Contract and the California Civil Code to furnish a bond to secure the prompt, full, and faithful payment of any Claimant, as hereinafter defined, for all labor, materials or services used or reasonably required for use in the performance of the work, concurrently with delivery to City of the signed Contract.

NOW, THEREFORE, we, the undersigned Principal, and

,
(Name, address, and telephone number of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto City in the penal sum of Seven Million Six Hundred Ninety-One Thousand Six Hundred Eight Dollars and Eighty-One Cents ($7,691,608.81), this amount being not less than one hundred percent (100%) of the total contract price, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal, his, her or its heirs, executors, administrators, successors or assigns, or subcontractors shall fail to pay any of the persons named in Division 4, Part 6, Title 3 of the California Civil Code (§ 9000 et seq.), or any amounts due under the Unemployment Insurance Code with respect to work or labor performed under the Contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of Principal and subcontractors pursuant to Section 13020 of the Unemployment Insurance Code, with respect to work or labor performed under the Contract (“Claimants”), Surety will pay for the same in an amount not exceeding the penal sum specified in this bond; otherwise, this obligation shall become null and void.

This bond shall inure to the benefit of any of the persons named in Division 4, Part 6, Title 3 of the California Civil Code (§ 9000 et seq.), so as to give a right of action to such persons or their assigns in any suit brought upon the bond.

In case suit is brought upon this bond to enforce or interpret this bond’s terms, Surety further agrees to pay all court costs and reasonable attorneys’ fees in an amount fixed by the court. Principal and Surety agree that this Performance Bond shall not be considered a part of the Contract but rather is a separate obligation of Principal and its Surety, and that any attorneys’ fee provision contained in this Performance Bond shall not apply to the Contract.

In the event there is any litigation between the parties arising from the breach of the Contract, each party will bear its own attorneys’ fees in the litigation.

FURTHER, Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, addition or modification to the terms of the Contract, or of the work to be performed thereunder, or the specifications for the same, shall in any way affect its obligations under this bond, and it does hereby waive notice of any such change, extension of time, alteration, addition, or modification to the terms of the Contract or to the work or to the specifications thereunder. Surety hereby waives the provisions of California Civil Code §§ 2819, 2845, and 2849.

City is an intended beneficiary of this bond and has all rights of a party thereto. 09/12/2023 C6 Page 50 of 57

CITY OF VISTA Page 2 of 2 MARTIN MARIETTA SAN DIEGO AGGREATES, LLC dba

ATP GENERAL ENGINEERING CONTRACTS
{00111739 1} [00065304 3] PAYMENT BOND (LABOR & MATERIALS) IN WITNESS WHEREOF, this instrument has been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.

Dated:
“Principal”

MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC
dba ATP GENERAL ENGINEERING CONTRACTORS
By:

Signature
Name and Title
By:

Signature
Name and Title
(Seal)

APPROVED
Amanda L. Guy
20230825120258
“`Surety”
By:

Signature
Name and Title
By:

Signature
Name and Title
(Seal)
This bond must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
09/12/2023 C6 Page 51 of 57

CITY OF VISTA Page 1 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba ATP GENERAL ENGINEERING CONTRACTORS
{00111741 1} [00065305 3] PERFORMANCE BOND (FAITHFUL PERFORMANCE) Bond No.

Premium: $
Effective Date:

PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS that:

The City of Vista (“City”) has awarded a contract (the “Contract”) with Martin Marietta San Diego Aggregates, LLC dba ATP General Engineering Contractors (“Principal”) as follows:

Street Rehabilitation Project 2023,
which Contract, and all Contract Documents set forth therein, are incorporated herein and made a part thereof by this reference.

Principal is required under the terms of the Contract to furnish a bond guaranteeing the prompt, full, and faithful performance of the Contract concurrently with delivery of the signed Contract to City.

NOW, THEREFORE, we, the undersigned Principal, and
,
(Name, address, and telephone number of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto City in the penal sum of Seven Million Six Hundred Ninety-One Thousand Six Hundred Eight Dollars and Eighty-One Cents ($7,691,608.81), this amount being not less than one hundred percent (100%) the total contract price, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal, his, her or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform all the undertakings, terms, covenants, conditions and agreements in the Contract and any alteration thereof made as therein provided, on Principal’s part to be kept and performed, all within the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and hold harmless City and its officers, agents, and others as therein provided, from any and all losses, liability and damages, claims, judgments, stop payment notices, costs, and fees of every description, whether imposed by law or equity, which may be incurred by City by reason of the failure or default on the part of Principal in the performance of any or all of the terms or the obligations of the Contract Documents, as they may be amended and supplemented including, but not limited to, Principal’s liability for City’s damages (including direct and consequential damages incurred by City for: rental expenses; losses of use, income, profit, business, and reputation; increased financing costs; and loss of management or employee productivity or of the services of such persons) caused by Principal’s delays, as well as Principal’s liability for other delay damages or liquidated damages, and any warranties or guarantees required thereunder; then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect.

When City declares that Principal is in default under the Contract, Surety shall promptly, take one of the following actions:
(a)Remedy the default;
(b)Undertake through its agents or independent contractors reasonably acceptable to City, to complete the Project according to the Contract Documents’ terms and conditions then in effect including without limitation, all obligations with respect to warranties, guarantees, and the payment of liquidated damages; or, if required by City; (c)Obtain a bid or bids for completing the Contract in accordance with its terms and conditions using a procurement methodology approved by City, select a contractor or contractors — acceptable to City — to complete all of the Work, and arrange for a contract between the contractor(s) and City, to be secured with performance and payment bonds executed by an admitted surety insurer equivalent to the bonds issued on the Construction Contract, 09/12/2023 C6 Page 52 of 57

CITY OF VISTA Page 2 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba ATP GENERAL ENGINEERING CONTRACTORS
{00111741 1} [00065305 3] PERFORMANCE BOND (FAITHFUL PERFORMANCE) and Surety shall make available, as the Work progresses, sufficient funds to pay the cost of completion less the balance of the Contract Sum, and to pay and perform all obligations of Principal under the Contract and Contract Documents, including other costs and damages for which Surety is liable under this Bond and all obligations with respect to warranties, guarantees, and the payment of liquidated damages as a result of Contractor’s default; (d) Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
(i) After investigation, determine the amount for which it may be liable to City and, as soon as practicable after the amount is determined, make payment to City; or (ii) Deny liability in whole or in part and notify City, citing the reasons for denial.

If Surety does not proceed as provided above with reasonable promptness, Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from City to Surety demanding that Surety perform its obligations under this Bond, and City shall be entitled to enforce any remedy available to City. If Surety admits liability and tenders payment, and City refuses the payment, or Surety has denied liability, in whole or in part, without further notice City shall be entitled to enforce any remedy available to City.

In case suit is brought upon this bond, Surety further agrees to pay all court costs and reasonable attorneys’ fees in an amount fixed by the court. Principal and Surety agree that this Performance Bond shall not be considered a part of the Contract but rather is a separate obligation of Principal and its Surety, and that any attorneys’ fee provision contained in this Performance Bond shall not apply to the Contract. In the event there is any litigation between the parties arising from the breach of the Contract, each party will bear its own attorneys’ fees in the litigation.

FURTHER, Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, addition or modification to the terms of the Contract, or of the work to be performed thereunder, or the specifications for the same, shall in any way affect its obligations under this bond, and it does hereby waive notice of any such change, extension of time, alteration, addition, or modification to the terms of the Contract or to the work or to the specifications thereunder. Surety hereby waives the provisions of California Civil Code §§ 2819, 2845, and 2849.

City is an intended beneficiary of this bond and has all rights of a party thereto. [Text and signatures continued on page 3.]

09/12/2023 C6 Page 53 of 57

CITY OF VISTA Page 3 of 3 MARTIN MARIETTA SAN DIEGO AGGREGATES, LLC dba ATP GENERAL ENGINEERING CONTRACTORS
{00111741 1} [00065305 3] PERFORMANCE BOND (FAITHFUL PERFORMANCE) IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed an original hereof, have been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.

Dated:
“Principal”

MARTIN MAREITTA SAN DIEGO AGGREGATES, LLC
dba ATP GENERAL ENGINEERING CONTRACTORS
By:

Signature
Name and Title
By:

Signature
Name and Title
(Seal)

APPROVED
Amanda L. Guy
20230825120531
“`Surety”
By:

Signature
Name and Title
By:

Signature
Name and Title
(Seal)
This bond must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
09/12/2023 C6 Page 54 of 57

EXHIBIT 4

BID DOCUMENTS
On file in the City Clerk’s Office
09/12/2023 C6 Page 55 of 57
EXHIBIT 4

City of Vista
EXH 5
STREET REHABILITATION PROJECT 2023 (CIP No. 8225)
Highlands Dr -TO BE COMPLETED FIRST
Highland Dr (Judilyn to Rose Dr)
Highland Dr (Rose Dr to Maryland Dr)
Highland Dr (Judilyn Dr to Olive Ave)
Huff St (SPUR) (300' N/Date to End (E))
Palm Bark St (Tylee St to Cinchona St)
Cinchona St (Tylee St to End)
Lagan Ave (Indian Rock Rd W to End)
Valencia Dr (Vista Way W to End)
Bonita Dr (Bluegrass Rd S/S to 145' S/Bluegrass Rd)
Bonita Dr (145' S/Bluegrass Rd to 495' S/Bluegrass Rd
Palm Bark St (Mistletoe St to Tylee St)
Ruby Dr (SPUR) 550' S/Olive Av to End (S Cul-de-sac)
Moon Rd (Grapevine Rd to Galaxy Dr)
Stewart Dr (Collyn St to Jonathon St)
Ruby Dr (SPUR) 270' S/Olive Av to End (N Cul-de-sac)
Ascot Dr (Melrose Dr N to 935' W/Melrose Dr N)
Judilyn Dr (Rose Dr to Cielita Linda Dr (Highland)
Cocapah St (OcoƟllo Dr to Melrose Dr N)
Dana Dr (Maryland Dr to End)
Huff St (Vista Way W to Date St)
Caren Rd (Galaxy Dr to Mistletoe St)
Durian Ct (Durian St to End)
Rose Dr (Maryland Dr to Highland Dr)
Santa Clara Dr (Tylee St to End)
Jonathon St (Grapevine Rd to Collyn St)
Caren Rd (Mistletoe St to End)
Cielita Linda Dr (Judilyn Dr to Highland Dr)
Joshua Way (Business Park Dr to End)
Commerce Way (Progress St to La Mirada Dr)
La Mirada Dr (Engineer St to End)
Ave Chelsea (Park Center Dr to End)
Wesley Way (Buena Vista Dr to End)
Ash St (La Mirada Dr to End)
Old Foothill Drive (240’/S to End)
Green Oak Rd (S Melrose to End)
09/12/2023 C6 Page 56 of 57
EXHIBIT 5

S. Emerald Dr (SR78 Bridge to Hacienda Dr)
Emerald Dr S (Hacienda Dr to City Limits (Skyhaven Rd)
Lupine Hills Dr ( Shadowridge Dr (W) to Parkview Dr)
Lupine Hills Dr (Parkview Dr to Coronado Pl)
Lupine Hills Dr (Coronado Pl to Links Way (E))
Lupine Hills Dr (Links Way (E) to OpƟmist Way)
Lupine Hills Dr (OpƟmist Way to Shadowridge Dr (E))
Sunset Dr (Crestview Rd to Seaview Pl)
Sycamore Av NB (SR78 to University Dr)
Sycamore Av SB (SR78 to Thibodo Rd)
Civic Center Dr SB (Pala Vista Dr to RR Tracks)
Civic Center Dr NB (RR Tracks to Pala Vista Dr)
Civic Center Drive (Crest View Rd to RR Tracks)
Emerald Dr S (SR 78 to W. Vista Way)
Melrose Dr S (Hacienda Dr to SR78)
Melrose Dr N (SR 78 to W. Vista Way)
Vista Village Dr (Hacienda Dr to SR78)
Vista Village Dr (SR78 to Lado de Loma)
Vista Village Dr (Lado de Loma to W. Vista Way)
Mar Vista Dr (SR78 to Stoneridge Terrace)

09/12/2023 C6 Page 57 of 57