ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: C3
Prepared by:

Erin Adams, Administrative Programs
Manager Meeting Date: September 24, 2024
Approved by:

Greg Mayer, Director of Engineering
John Conley, City Manager Agenda Location: Consent Calendar SUBJECT: CIP NO. 8334 – CIVIC CENTER SOLAR PROJECT – FIRST AMENDMENT TO THE

AGREEMENT WITH BAKER ELECTRIC & RENEWABLES, LLC
RECOMMENDATION: Adopt City Council Resolution No. 2024- , approving the first amendment to the agreement with Baker Electric & Renewables, LLC for design/build services for the Civic Center Solar Project (CIP No. 8334).

CORRELATION TO CITY COUNCIL GOALS: Climate and Environmental Responsibility PRIOR ACTION: On August 22, 2023, the City Council adopted Resolution No. 2023-154 approving an agreement with Baker Electric & Renewables, LLC for design/build services for the Civic Center Solar Project (CIP No. 8334) (Vote: 5-0).

On June 11, 2024, adopted City Council Resolution No. 2024-86, adopting a Capital Project Budget for Fiscal Years 2024/25 and 2025/26 (Vote: 5-0).

STATEMENT ON THE SUBJECT: Capital Improvement Program (CIP) Project No. 8334, Civic Center Solar Project, will produce 977,601 kilowatt hours of electric power annually, from a grid-tied solar photovoltaic system, with solar panels installed over the Alta Vista Drive parking lot located at 200 Civic Center Drive. The location of the solar canopies is due to the proximity of existing electrical infrastructure, and overall long-term value compared to installing solar panels on the existing building roof. The Civic Center’s electrical utility bill will decrease by almost half, and the project is expected to have a 6.7-year payback period. Additionally, this Project promotes the City’s Climate Action Plan and provides GHG- reducing co-benefits by increasing distributed solar generation.

The installation of solar canopies in the Alta Vista parking lot will result in the removal of 38 trees, which will be replaced on the Civic Center site as part of the project. The location of the solar canopies, and the resulting tree removals, were designed to retain the trees along the Civic Center Drive frontage. These trees were retained to avoid negatively impacting the view of the Civic Center from Civic Center Drive. The trees along the Alta Vista Drive frontage are also being retained but will be trimmed to work with the solar canopy that parallels Alta Vista Drive. The replacement trees include seven oaks and 31 Forest Pansy Eastern Redbud, which will primarily be located behind the Civic Center in the dry creek bed area.

AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
Approved above recommendation, adopted City Council Resolution No. 2024-151. Vote: 5-0.

MEETING DATE: SEPTEMBER 24, 2024 PAGE 2

SUBJECT: CIP NO. 8334 – CIVIC CENTER SOLAR PROJECT – FIRST AMENDMENT TO THE

AGREEMENT WITH BAKER ELECTRIC & RENEWABLES, LLC
First Amendment to the Design-Build Agreement. On August 22, 2023, City Council awarded the Design-Build Team (DBT) of Baker Electric & Renewables, LLC. (Baker Electric) the design portion of the project. The DBT has completed the design, and staff has negotiated a Guaranteed Maximum Price (GMP) with the DBT and recommends approval of the first amendment to establish the GMP of $2,505,353.21. The proposed amendment to the agreement with Baker Electric establishes the GMP and allows the DBT to begin Phase 2 construction services and Phase 3 operation/startup services as specified in Sections 6 and 7 of the original agreement (Exhibit 3).

FISCAL IMPACT: The cost of this amendment is $2,277,035.21 for a new contract ceiling of $2,505,353.21 for Baker Electric to provide design-build services for the Design and Construction of the Civic Center Solar Project Phase 2 and Phase 3. Sufficient funding is budgeted and available in the Fiscal Years 2024/25 and 2025/26 Capital Improvement Budgets in CIP No. 8334, the Civic Center Solar Project Source Appropriation Account (No. 1176208.578999.8334).

EXHIBITS:

1. City Council Resolution No. 2024- , approving the first amendment to the agreement with Baker Electric & Renewables, LLC for design/build services for the Civic Center Solar Project (CIP No. 8334)

2. First Amendment with Baker Electric & Renewables, LLC

3. Original Contract with Baker Electric & Renewables, LLC 09/24/2024 C3 2 of 191

00029213 7
RESOLUTION NO. 2024-

A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF

VISTA, CALIFORNIA, APPROVING THE FIRST AMENDMENT TO THE

AGREEMENT WITH BAKER ELECTRIC & RENEWABLES, LLC FOR

DESIGN/BUILD SERVICES FOR THE CIVIC CENTER SOLAR PROJECT (CIP NO. 8334)
The City Council of the City of Vista does resolve as follows:

1. Findings. The City Council hereby finds and declares the following:

A. On August 22, 2023, the City of Vista entered into an agreement with Baker Electric & Renewables, LLC for design / build services for the Civic Center Solar Project (CIP No. 8334).

B. The City now desires to amend the agreement with Baker Electric & Renewables, LLC to establish the Guaranteed Maximum Price (GMP) of $2,505,353.21.

2. Action.

A. The First Amendment between the City of Vista and Baker Electric & Renewables, LLC for design / build services for the Civic Center Solar Project establishing the Guaranteed Maximum Price (GMP) of $2,505,353.21 is approved, and the Mayor is authorized to execute the amendment.

3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on September 24, 2024, by the following vote:

AYES:

NOES:

ABSTAIN:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY

By:

APPROVED
Walter C. Chung
20240916080137

JOHN B. FRANKLIN, MAYOR

ATTEST:

KATHY VALDEZ, CITY CLERK

By:

09/24/2024 C3 3 of 191

00098064 4

FIRST AMENDMENT TO THE CONTRACT BETWEEN THE CITY OF VISTA

AND BAKER ELECTRIC & RENEWABLES, LLC FOR DESIGN / BUILD SERVICES FOR THE CIVIC CENTER SOLAR PROJECT (CIP NO. 8334) THIS FIRST AMENDMENT (“First Amendment”) to the Contract between the City of Vista and Baker Electric & Renewables, LLC, dated August 22, 2023 (“Contract”), is made and entered into as of _______________________ (“First Amendment Date”), by and between the City of Vista, a chartered municipal corporation (“City”), and Baker Electric & Renewables, LLC, a California Limited Liability Company (“Contractor”).

Recitals: City and Contractor now desire to enter into a First Amendment to the Contract by modifying the terms of the Contract.

NOW, THEREFORE, in consideration of these recitals and the mutual covenants contained herein, City and Contractor agree as follows:

1. The Guaranteed Maximum Price (GMP) for the Civic Center Solar Project is hereby established as $2,505,353.21, which includes $228,318.00 in preconstruction and design services, in accordance with Section 1.3 of the Contract. A breakdown of the GMP is included as Exhibit A.

2. The construction schedule is established as set forth in Exhibit B.

3. The City Engineering is directed to approve the 100% construction documents prior to Written Notice to Proceed with Construction Services pursuant to Vista Municipal Code Section 2.30.020B.

4. All other conditions of the Contract not specifically amended or superseded by the terms herein shall continue in full force and effect.

[Text and signatures on page 2.]

09/24/2024 C3 4 of 191

Contract Amendment

Page 2 ends

00098064 44879-6417-1741, v. 2
IN WITNESS WHEREOF, the parties have executed and entered into this First Amendment as of the First Amendment Date.

CITY OF VISTA, a chartered municipal
corporation

By:

JOHN B. FRANKLIN, MAYOR

ATTEST:

KATHY VALDEZ, CITY CLERK

By:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY

By:

RISK MANAGEMENT REVIEW:

DOLORES GASCON, RISK MANAGER

By:

APPROVED
Amanda L. Guy
20240826152834

BAKER ELECTRIC & RENEWABLES,
LLC, a California Limited Liability Company

By:

NAME/Title

By:

NAME/Title

09/24/2024 C3 5 of 191

Line #Description Amount
1 Special Inspection Services 10,990.00$
2 Demolition - Landscape & Hardscape 68,231.00$
3 Landscaping & irrigation 43,724.00$
4 Asphalt paving & striping 8,000.00$
5 Site concrete 2,500.00$
6 Concrete Foundations & Pads 6,000.00$
7 Steel Canopy Structures 465,153.00$
8 Signage 2,299.22$
9 Equipment rentals 76,206.84$
10 Electrical & Solar Scope 925,375.00$
11 Subtotal hard costs lines 1-10 1,608,479.06$
12 2% contingency 32,169.58$
13 Baker General Conditions 204,921.17$
14 Subtotal with lines 11-13 1,845,569.81$
15 Baker 20% fee on all above 369,113.96$
16 Subtotal with lines 14-15 2,214,683.77$
17 liability insurance % on line 16 22,146.84$
18 COC insurance % on line 16 22,146.84$
19 Subtotal with lines 16-18 2,258,977.45$
20 Contract for Precon 228,318.00$
21 Subtotal with lines 19-20 2,487,295.45$
22 Bond .726% for entire project 18,057.76$
23 Contract Total 2,505,353.21$
GMP BREAKDOWN 8/24/24

EXHIBIT A
CIVIC CENTER SOLAR PROJECT (CIP 8334)
09/24/2024 C3 6 of 191

ID Task Name Duration Start Finish
1 PV Project Schedule 555 days Tue 8/22/23 Thu 10/30/25 2 Pre-Contract 1 day Tue 8/22/23 Tue 8/22/23
3 Executed Contract 1 day Tue 8/22/23 Tue 8/22/23
4 Design/Engineering/Permitting 275 days Wed 8/23/23 Mon 9/30/24 5 Bus Tap Inspection 1 day Sat 1/6/24 Mon 1/8/24
6 Dig Alert 3 days Wed 9/20/23 Fri 9/22/23
7 Underground Locating - GPRS 1 day Mon 9/18/23 Mon 9/18/23 8 Underground Survery - Spiro 1 day Wed 10/11/23 Wed 10/11/23 9 Underground Survey - Geotech 1 day Thu 9/21/23 Thu 9/21/23 10 Electrical/Structural Engineering 144 days Wed 8/23/23 Tue 3/26/24 11 90% Plans Submitted For Review 1 day Wed 2/7/24 Wed 2/7/24 12 Comments Received/Addressing Comments 21 days Mon 2/26/24 Mon 3/25/24 13 90% Plans Re-Submitted For Review 1 day Tue 3/26/24 Tue 3/26/24 14 Comments Received/Addressing Comments 22 days Wed 3/27/24 Thu 4/25/24 15 90% Plans Approved 1 day Fri 4/26/24 Fri 4/26/24
16 Submit for Plan Check 1 day Wed 5/1/24 Wed 5/1/24
17 AHJ Review 12 days Thu 5/2/24 Fri 5/17/24
18 Receive AHJ Comments 41 days Mon 5/20/24 Wed 7/17/24 19 Re-Submit for Plan Check 1 day Thu 7/18/24 Thu 7/18/24 20 AHJ Review 14 days Fri 7/19/24 Wed 8/7/24
21 Landscape Review - Estimated 25 days Fri 7/19/24 Thu 8/22/24 22 Re-Submit for Plan Check - Estimated 1 day Fri 8/30/24 Fri 8/30/24 23 AHJ Review - Estimated 15 days Tue 9/3/24 Mon 9/23/24 24 Permit Approval - Estimated 5 days Tue 9/24/24 Mon 9/30/24 25 City Council Meeting for Approval - Estimated 1 day Tue 9/24/24 Tue 9/24/24 26 Procurement 250 days Wed 9/25/24 Mon 9/15/25
27 Modules 60 days Wed 9/25/24 Thu 12/19/24
28 Inverters 60 days Wed 9/25/24 Thu 12/19/24
29 Switchgear 250 days Wed 9/25/24 Mon 9/15/25
30 Remaining Gear 40 days Wed 9/25/24 Tue 11/19/24
31 Monitoring 20 days Wed 9/25/24 Tue 10/22/24
32 Structural Steel (Carports)40 days Wed 9/25/24 Tue 11/19/24 33 Construction 258 days Mon 9/30/24 Tue 9/30/25
34 Mobilization 4 days Mon 9/30/24 Thu 10/3/24
35 Container Delivery/Site Layout/Safety Setup 2 days Mon 9/30/24 Tue 10/1/24 36 UG Tracing 2 days Wed 10/2/24 Thu 10/3/24
37 Landscaping 10 days Wed 10/2/24 Tue 10/15/24
38 Tree Removal & Trimming 10 days Wed 10/2/24 Tue 10/15/24 39 Civil Scope 36 days Fri 10/4/24 Fri 11/22/24
40 Saw Cut for Trench 10 days Fri 10/4/24 Thu 10/17/24
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Vista Civic Center PV
Project Schedule
Exhibit B

Page 1 ends

Project: Vista Civic CenterPV
Date: Mon 8/26/24
09/24/2024 C3 7 of 191

ID Task Name Duration Start Finish
41 Trenching & Other Excavation 10 days Fri 10/18/24 Thu 10/31/24 42 Install UG Conduit 10 days Fri 11/1/24 Thu 11/14/24
43 Backfill, Patch Back for Trenches, & Remove Spoils 6 days Fri 11/15/24 Fri 11/22/24 44 Carports 89 days Mon 11/25/24 Wed 4/2/25
45 Drill Footings 10 days Mon 11/25/24 Tue 12/10/24
46 Place Rebar Cages 5 days Wed 12/11/24 Tue 12/17/24
47 Set Columns 5 days Wed 12/18/24 Tue 12/24/24
48 Pour Concrete Foundations 5 days Thu 12/26/24 Thu 1/2/25 49 Erect Steel 8 days Fri 1/3/25 Tue 1/14/25
50 Spoils Removal 3 days Wed 1/15/25 Fri 1/17/25
51 Purlin Installation & Welding 8 days Wed 1/15/25 Fri 1/24/25 52 Install AC Gear 10 days Wed 1/15/25 Tue 1/28/25
53 Install Inverters 5 days Wed 1/15/25 Tue 1/21/25
54 Install DC Conduit on Structure 10 days Wed 1/15/25 Tue 1/28/25 55 Install AC Conduit on Structure 10 days Wed 1/15/25 Tue 1/28/25 56 Install Lighting 5 days Wed 1/29/25 Tue 2/4/25
57 Run DC Homeruns 10 days Wed 1/29/25 Tue 2/11/25
58 Module Installation 12 days Wed 2/12/25 Thu 2/27/25
59 Module to Module Wiring 12 days Fri 2/28/25 Mon 3/17/25 60 Pull AC Wire to Lighting, Inverters, DAS, & Gear 12 days Tue 3/18/25 Wed 4/2/25 61 Landscaping 20 days Thu 4/3/25 Wed 4/30/25
62 Irrigation Repairs 10 days Thu 4/3/25 Wed 4/16/25
63 Installation of Trees & Foliage 10 days Thu 4/17/25 Wed 4/30/25 64 System Finalization 2 days Thu 4/3/25 Fri 4/4/25
65 Shutdown for Interconnection to Utility - Tentative 1 day Thu 4/3/25 Thu 4/3/25 66 Installation of Placards/Safety Labels & Demobilzation 1 day Fri 4/4/25 Fri 4/4/25 67 Switchgear Remobilization 11 days Tue 9/16/25 Tue 9/30/25 68 Remobilize to Install Switchgear 1 day Tue 9/16/25 Tue 9/16/25 69 Switchgear Installation Period 10 days Wed 9/17/25 Tue 9/30/25 70 PV Project Closeout 4 days Fri 4/4/25 Wed 4/9/25
71 QC Walk 2 days Fri 4/4/25 Mon 4/7/25
72 Punch List Items 3 days Mon 4/7/25 Wed 4/9/25
73 Remobilization Project Closeout 22 days Wed 10/1/25 Thu 10/30/25 74 Testing & Commissioning 2 days Wed 10/1/25 Thu 10/2/25 75 Final AHJ Inspections (Substantial Completion)1 day Wed 10/1/25 Wed 10/1/25 76 As-Built Drawings 10 days Wed 10/1/25 Tue 10/14/25
77 O&M Manual 10 days Wed 10/1/25 Tue 10/14/25
78 PTO Period 15 days Thu 10/2/25 Wed 10/22/25
79 Energize System & Monitor for One Week 5 days Thu 10/23/25 Wed 10/29/25 80 Owner Training (Final Completion) - Estimated 1 day Thu 10/30/25 Thu 10/30/25 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Vista Civic Center PV
Project Schedule
Exhibit B

Page 2 ends

Project: Vista Civic CenterPV
Date: Mon 8/26/24
09/24/2024 C3 8 of 191

09/24/2024 C3 9 of 191

09/24/2024 C3 10 of 191

09/24/2024 C3 11 of 191

09/24/2024 C3 12 of 191

09/24/2024 C3 13 of 191

09/24/2024 C3 14 of 191

09/24/2024 C3 15 of 191

09/24/2024 C3 16 of 191

09/24/2024 C3 17 of 191

09/24/2024 C3 18 of 191

09/24/2024 C3 19 of 191

09/24/2024 C3 20 of 191

09/24/2024 C3 21 of 191

09/24/2024 C3 22 of 191

09/24/2024 C3 23 of 191

09/24/2024 C3 24 of 191

09/24/2024 C3 25 of 191

09/24/2024 C3 26 of 191

09/24/2024 C3 27 of 191

09/24/2024 C3 28 of 191

09/24/2024 C3 29 of 191

09/24/2024 C3 30 of 191

09/24/2024 C3 31 of 191

09/24/2024 C3 32 of 191

09/24/2024 C3 33 of 191

09/24/2024 C3 34 of 191

09/24/2024 C3 35 of 191

09/24/2024 C3 36 of 191

09/24/2024 C3 37 of 191

09/24/2024 C3 38 of 191

09/24/2024 C3 39 of 191

09/24/2024 C3 40 of 191

09/24/2024 C3 41 of 191

09/24/2024 C3 42 of 191

09/24/2024 C3 43 of 191

09/24/2024 C3 44 of 191

09/24/2024 C3 45 of 191

09/24/2024 C3 46 of 191

09/24/2024 C3 47 of 191

09/24/2024 C3 48 of 191

09/24/2024 C3 49 of 191

09/24/2024 C3 50 of 191

09/24/2024 C3 51 of 191

09/24/2024 C3 52 of 191

09/24/2024 C3 53 of 191

09/24/2024 C3 54 of 191

09/24/2024 C3 55 of 191

09/24/2024 C3 56 of 191

09/24/2024 C3 57 of 191

09/24/2024 C3 58 of 191

09/24/2024 C3 59 of 191

09/24/2024 C3 60 of 191

09/24/2024 C3 61 of 191

09/24/2024 C3 62 of 191

09/24/2024 C3 63 of 191

09/24/2024 C3 64 of 191

09/24/2024 C3 65 of 191

09/24/2024 C3 66 of 191

09/24/2024 C3 67 of 191

09/24/2024 C3 68 of 191

09/24/2024 C3 69 of 191

09/24/2024 C3 70 of 191

09/24/2024 C3 71 of 191

09/24/2024 C3 72 of 191

09/24/2024 C3 73 of 191

09/24/2024 C3 74 of 191

09/24/2024 C3 75 of 191

09/24/2024 C3 76 of 191

09/24/2024 C3 77 of 191

09/24/2024 C3 78 of 191

09/24/2024 C3 79 of 191

09/24/2024 C3 80 of 191

09/24/2024 C3 81 of 191

09/24/2024 C3 82 of 191

09/24/2024 C3 83 of 191

09/24/2024 C3 84 of 191

09/24/2024 C3 85 of 191

09/24/2024 C3 86 of 191

09/24/2024 C3 87 of 191

09/24/2024 C3 88 of 191

09/24/2024 C3 89 of 191

09/24/2024 C3 90 of 191

09/24/2024 C3 91 of 191

09/24/2024 C3 92 of 191

09/24/2024 C3 93 of 191

09/24/2024 C3 94 of 191

09/24/2024 C3 95 of 191

09/24/2024 C3 96 of 191

09/24/2024 C3 97 of 191

09/24/2024 C3 98 of 191

09/24/2024 C3 99 of 191

09/24/2024 C3 100 of 191

09/24/2024 C3 101 of 191

09/24/2024 C3 102 of 191

09/24/2024 C3 103 of 191

09/24/2024 C3 104 of 191

09/24/2024 C3 105 of 191

09/24/2024 C3 106 of 191

09/24/2024 C3 107 of 191

09/24/2024 C3 108 of 191

09/24/2024 C3 109 of 191

09/24/2024 C3 110 of 191

09/24/2024 C3 111 of 191

09/24/2024 C3 112 of 191

09/24/2024 C3 113 of 191

09/24/2024 C3 114 of 191

09/24/2024 C3 115 of 191

09/24/2024 C3 116 of 191

09/24/2024 C3 117 of 191

09/24/2024 C3 118 of 191

09/24/2024 C3 119 of 191

09/24/2024 C3 120 of 191

09/24/2024 C3 121 of 191

09/24/2024 C3 122 of 191

09/24/2024 C3 123 of 191

09/24/2024 C3 124 of 191

09/24/2024 C3 125 of 191

09/24/2024 C3 126 of 191

09/24/2024 C3 127 of 191

09/24/2024 C3 128 of 191

09/24/2024 C3 129 of 191

09/24/2024 C3 130 of 191

09/24/2024 C3 131 of 191

09/24/2024 C3 132 of 191

09/24/2024 C3 133 of 191

09/24/2024 C3 134 of 191

09/24/2024 C3 135 of 191

09/24/2024 C3 136 of 191

09/24/2024 C3 137 of 191

09/24/2024 C3 138 of 191

09/24/2024 C3 139 of 191

09/24/2024 C3 140 of 191

09/24/2024 C3 141 of 191

09/24/2024 C3 142 of 191

09/24/2024 C3 143 of 191

09/24/2024 C3 144 of 191

09/24/2024 C3 145 of 191

09/24/2024 C3 146 of 191

09/24/2024 C3 147 of 191

09/24/2024 C3 148 of 191

09/24/2024 C3 149 of 191

09/24/2024 C3 150 of 191

09/24/2024 C3 151 of 191

09/24/2024 C3 152 of 191

09/24/2024 C3 153 of 191

09/24/2024 C3 154 of 191

09/24/2024 C3 155 of 191

09/24/2024 C3 156 of 191

09/24/2024 C3 157 of 191

09/24/2024 C3 158 of 191

09/24/2024 C3 159 of 191

09/24/2024 C3 160 of 191

09/24/2024 C3 161 of 191

09/24/2024 C3 162 of 191

09/24/2024 C3 163 of 191

09/24/2024 C3 164 of 191

09/24/2024 C3 165 of 191

09/24/2024 C3 166 of 191

09/24/2024 C3 167 of 191

09/24/2024 C3 168 of 191

09/24/2024 C3 169 of 191

09/24/2024 C3 170 of 191

09/24/2024 C3 171 of 191

09/24/2024 C3 172 of 191

09/24/2024 C3 173 of 191

09/24/2024 C3 174 of 191

09/24/2024 C3 175 of 191

09/24/2024 C3 176 of 191

09/24/2024 C3 177 of 191

09/24/2024 C3 178 of 191

09/24/2024 C3 179 of 191

09/24/2024 C3 180 of 191

09/24/2024 C3 181 of 191

09/24/2024 C3 182 of 191

09/24/2024 C3 183 of 191

09/24/2024 C3 184 of 191

09/24/2024 C3 185 of 191

09/24/2024 C3 186 of 191

09/24/2024 C3 187 of 191

09/24/2024 C3 188 of 191

09/24/2024 C3 189 of 191

09/24/2024 C3 190 of 191

09/24/2024 C3 191 of 191

ID Task Name Duration Start Finish
1 PV Project Schedule 495 days Tue 8/22/23 Thu 8/7/25
2 Pre-Contract 1 day Tue 8/22/23 Tue 8/22/23
3 Executed Contract 1 day Tue 8/22/23 Tue 8/22/23
4 Design/Engineering/Permitting 271 days Wed 8/23/23 Tue 9/24/24 5 Bus Tap Inspection 1 day Sat 1/6/24 Mon 1/8/24
6 Dig Alert 3 days Wed 9/20/23 Fri 9/22/23
7 Underground Locating - GPRS 1 day Mon 9/18/23 Mon 9/18/23 8 Underground Survery - Spiro 1 day Wed 10/11/23 Wed 10/11/23 9 Underground Survey - Geotech 1 day Thu 9/21/23 Thu 9/21/23 10 Electrical/Structural Engineering 144 days Wed 8/23/23 Tue 3/26/24 11 90% Plans Submitted For Review 1 day Wed 2/7/24 Wed 2/7/24 12 Comments Received/Addressing Comments 21 days Mon 2/26/24 Mon 3/25/24 13 90% Plans Re-Submitted For Review 1 day Tue 3/26/24 Tue 3/26/24 14 Comments Received/Addressing Comments 22 days Wed 3/27/24 Thu 4/25/24 15 90% Plans Approved 1 day Fri 4/26/24 Fri 4/26/24
16 Submit for Plan Check 1 day Wed 5/1/24 Wed 5/1/24
17 AHJ Review 12 days Thu 5/2/24 Fri 5/17/24
18 Receive AHJ Comments 41 days Mon 5/20/24 Wed 7/17/24 19 Re-Submit for Plan Check 1 day Thu 7/18/24 Thu 7/18/24 20 AHJ Review 14 days Fri 7/19/24 Wed 8/7/24
21 Landscape Review 25 days Fri 7/19/24 Thu 8/22/24
22 Re-Submit for Plan Check 1 day Wed 8/28/24 Wed 8/28/24 23 Re-Submit for Landscape Plan Check 1 day Wed 8/28/24 Wed 8/28/24 24 AHJ Review 5 days Thu 8/29/24 Thu 9/5/24
25 Permit Approval 6 days Fri 9/6/24 Fri 9/13/24
26 Permit Issuance 1 day Mon 9/16/24 Mon 9/16/24
27 City Council Meeting for Approval 1 day Tue 9/24/24 Tue 9/24/24 28 Procurement 190 days Wed 9/25/24 Mon 6/23/25
29 Modules 60 days Wed 9/25/24 Thu 12/19/24
30 Inverters 60 days Wed 9/25/24 Thu 12/19/24
31 Switchgear 190 days Wed 9/25/24 Mon 6/23/25
32 Remaining Gear 40 days Wed 9/25/24 Tue 11/19/24
33 Monitoring 20 days Wed 9/25/24 Tue 10/22/24
34 Structural Steel (Carports)28 days Wed 9/25/24 Fri 11/1/24 35 Construction 194 days Mon 10/7/24 Wed 7/9/25
36 Mobilization 3 days Mon 10/7/24 Wed 10/9/24
37 Container Delivery/Site Layout/Safety Setup 2 days Mon 10/7/24 Tue 10/8/24 38 UG Tracing 1 day Wed 10/9/24 Wed 10/9/24
39 Landscaping 6 days Wed 10/9/24 Wed 10/16/24
40 Tree Removal & Trimming 6 days Wed 10/9/24 Wed 10/16/24 41 Civil Scope 20 days Thu 10/10/24 Wed 11/6/24
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Vista Civic Center PV
Project Schedule
Exhibit B

Page 1 ends

Project: Vista Civic CenterPV
Date: Tue 9/17/24

ADD TO PACKET
C3

ID Task Name Duration Start Finish
42 Saw Cut for Trench 5 days Thu 10/10/24 Wed 10/16/24
43 Trenching & Other Excavation 5 days Thu 10/17/24 Wed 10/23/24 44 Install UG Conduit 5 days Thu 10/24/24 Wed 10/30/24
45 Backfill, Patch Back for Trenches, & Remove Spoils 5 days Thu 10/31/24 Wed 11/6/24 46 Carports 74 days Mon 11/4/24 Wed 2/19/25
47 Drill Footings 5 days Mon 11/4/24 Fri 11/8/24
48 Place Rebar Cages 15 days Mon 11/11/24 Tue 12/3/24
49 Set Columns 15 days Mon 11/11/24 Tue 12/3/24
50 Pour Concrete Foundations 15 days Mon 11/11/24 Tue 12/3/24 51 Erect Steel 10 days Wed 12/4/24 Tue 12/17/24
52 Spoils Removal 2 days Wed 12/18/24 Thu 12/19/24
53 Purlin Installation & Welding 8 days Wed 12/18/24 Mon 12/30/24 54 Install AC Gear 10 days Wed 12/18/24 Thu 1/2/25
55 Install Inverters 4 days Wed 12/18/24 Mon 12/23/24
56 Install DC Conduit on Structure 10 days Wed 12/18/24 Thu 1/2/25 57 Install AC Conduit on Structure 10 days Wed 12/18/24 Thu 1/2/25 58 Install Lighting 5 days Fri 1/3/25 Thu 1/9/25
59 Run DC Homeruns 8 days Fri 1/3/25 Tue 1/14/25
60 Module Installation 8 days Wed 1/15/25 Fri 1/24/25
61 Module to Module Wiring 8 days Mon 1/27/25 Wed 2/5/25 62 Pull AC Wire to Lighting, Inverters, DAS, & Gear 10 days Thu 2/6/25 Wed 2/19/25 63 Landscaping 20 days Mon 1/13/25 Fri 2/7/25
64 Irrigation Repairs 10 days Mon 1/13/25 Fri 1/24/25
65 Installation of Trees & Foliage 10 days Mon 1/27/25 Fri 2/7/25 66 Switchgear Remobilization 12 days Tue 6/24/25 Wed 7/9/25 67 Remobilize to Install Switchgear 1 day Tue 6/24/25 Tue 6/24/25 68 Switchgear Installation Period 10 days Wed 6/25/25 Tue 7/8/25 69 Shutdown for Interconnection to Utility 1 day Wed 7/9/25 Wed 7/9/25 70 PV Project Closeout 5 days Thu 3/20/25 Wed 3/26/25
71 Installation of Placards/Safety Labels 1 day Thu 3/20/25 Thu 3/20/25 72 QC Walk 2 days Thu 3/20/25 Fri 3/21/25
73 Punch List Items & Demobilzation 3 days Mon 3/24/25 Wed 3/26/25 74 Remobilization Project Closeout 22 days Wed 7/9/25 Thu 8/7/25 75 Testing & Commissioning 2 days Wed 7/9/25 Thu 7/10/25 76 Final AHJ Inspections (Substantial Completion)1 day Wed 7/9/25 Wed 7/9/25 77 As-Built Drawings 10 days Wed 7/9/25 Tue 7/22/25
78 O&M Manual 10 days Wed 7/9/25 Tue 7/22/25
79 PTO Period 15 days Thu 7/10/25 Wed 7/30/25
80 Energize System & Monitor for One Week 5 days Thu 7/31/25 Wed 8/6/25 81 Owner Training (Final Completion) - Estimated 1 day Thu 8/7/25 Thu 8/7/25 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Vista Civic Center PV
Project Schedule
Exhibit B

Page 2 ends

Project: Vista Civic CenterPV
Date: Tue 9/17/24