ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: C12
Prepared by:
Erin Adams, Administrative Programs Manager
Darra Woods, Principal Transportation Mobility
Planner Meeting Date: June 24, 2025
Approved by:
Greg Mayer, City Engineer
John Conely, City Manager Agenda Location: Consent Calendar
SUBJECT: CIP NO. 8294 - TRAFFIC SIGNAL INTERCONNECT EMERALD DRIVE, POINSETTIA AVENUE AND N. MELROSE DRIVE PROJECT– AWARD OF CONTRACT
RECOMMENDATION: Adopt City Council Resolution No. 2025- , awarding a construction contract to Baker Electric & Renewables LLC for the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N.
Melrose Drive Project (CIP No. 8294).
CORRELATION TO CITY COUNCIL GOALS: Traffic: Continue to enhance mobility safety, improve the flow of traffic for all forms of travel, reduce congestion, and improve our roads and sidewalks.
PRIOR ACTION: On June 11, 2024, adopted City Council Resolution No. 2024 -86, adopting a Capital Project Budget for Fiscal Years 2024/25 and 2025/26 (Vote: 5-0).
STATEMENT ON THE SUBJECT: Capital Improvement Project (CIP) No. 8294, the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project, will install segments of new conduit, fiber optic interconnect cable, and traffic signal equipment to more reliably and efficiently connect 8 additional traffic signals to the City’s communication system. These improvements will allow for optimized traffic signal timing and synchronization along these corridors. A Vicinity Map is included as Exhibit 3.
Staff advertised the project for competitive bids on March 13, 2025, on the City’s procurement website and online procurement portal, OpenGov. On April 10, 2025, the following five bids were received:
Bidder’s Name Office Location Total Bid Amount
Baker Electric & Renewables LLC Escondido, CA $ 966,471.56 HHS Construction LLC Ontario, CA $ 971,443.56
DBX, Inc. Temecula, CA $ 1,047,834.00
HMS Construction Inc. Vista, CA $1 ,150,000.00
Select Electric, Inc. Anaheim, CA $1,234,567.89
Staff reviewed the bid of $966,471.56 from Baker Electric & Renewables LLC and determined that they are the lowest responsible bidder who responded to all the requirements of the bid request. Therefore, s taff recommend that the City Council award the contract for the Traffic Signal Interconnect f or Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project (CIP No. 8294) to Baker Electric & Renewables LLC.
AGENDA
REPORT
CITY COUNCIL
COMMUNITY DEVELOPMENT COMMISSION
SUCCESSOR AGENCY
BUENA SANITATION DISTRICT
JOINT POWERS FINANCING AUTHORITY
06/24/2025
C12
1 of 244
MEETING DATE: June 24, 2025 PAGE 2
SUBJECT: CIP NO. 8294 - TRAFFIC SIGNAL INTERCONNECT EMERALD DRIVE, POINSETTIA AVENUE AND N. MELROSE DRIVE PROJECT– AWARD OF CONTRACT
FISCAL IMPACT: The construction contract is $966,471.56, with 1 0% contingency for a total budget of $1,063,118.76. Sufficient funding is budgeted and available in the Fiscal Years 2024/25 and 2025/26 Capital Improvement Budgets in CIP 8294 Traffic Congestion Management Source Appropriation accounts (Nos. 0026555.578999.8294 and 1106595.578999.8294).
EXHIBITS:
1. City Council Resolution 2025- , awarding a construction contract to Baker Electric & Renewables LLC for the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project (CIP No. 8294)
2. Contract with Baker Electric & Renewables LLC
3. Vicinity Map
06/24/2025
C12
2 of 244
00029213 7
RESOLUTION NO. 2025-
A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF
VISTA, CALIFORNIA, AWARDING A CONSTRUCTION CONTRACT TO
BAKER ELECTRIC AND RENEWABLES LLC FOR THE TRAFFIC SIGNAL INTERCONNECT FOR EMERALD DRIVE, POINSETTIA AVENUE AND N.
MELROSE DRIVE PROJECT (CIP NO. 8294)
The City Council of the City of Vista does resolve as follows:
1. Findings. The City Council hereby finds and declares the following:
A. The City solicited bids for construction of the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project and on April 10, 2025 public bids were opened and Baker Electric and Renewables LLC was the lowest bidder.
B. Staff determined that the bid submitted by Baker Electric and Renewables LLC is responsive in all material aspects to the request for bids, and that the bid from Baker Electric and Renewables LLC for the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project has been determined to be the lowest responsive and responsible bid.
2. Action.
A. The contract between the City of Vista, on the one hand, and Baker Electric and Renewables LLC, on the other hand, for the Traffic Signal Interconnect for Emerald Drive, Poinsettia Avenue and N. Melrose Drive Project is approved and the Mayor is authorized to execute the contract.
3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on June 24, 2025, by the following vote:
AYES:
NOES:
ABSTAIN:
APPROVED AS TO FORM:
WALTER CHUNG, CITY ATTORNEY
By:
APPROVED
Walter C. Chung
20250610113934
JOHN B. FRANKLIN, MAYOR
ATTEST:
KATHY VALDEZ, CITY CLERK
By:
06/24/2025
C12
3 of 244
EXHIBIT 1
SUMMARY CONSTRUCTION – COV LOCAL
BAKER ELECTRIC & RENEWABLES LLC
[00064028-1] 00064028 14900-3738-8604, v. 2
CONSTRUCTION CONTRACT
THIS CONTRACT is made and entered into as of _____________________________ (“Contract Date”), by and between the City of Vista, a chartered municipal corporation (“Agency”), and Baker Electric & Renewables LLC, a California limited liability company (“Contractor”). Agency and Contractor are sometimes individually referred to as a “Party” and collectively as “Parties.”
In consideration of the mutual covenants contained herein, Agency and Contractor agree as follows:
SECTION 1
The Contract Documents consisting of the PROJECT SPECIFICATIONS, comprised of the NOTICE INVITING BIDS, the INSTRUCTIONS TO BIDDERS, the accepted BID PROPOSAL; BID SCHEDULE; CONTRACTOR’S LICENSING STATEMENT; PROJECT REFERENCES; CONTRACTOR’S LIST OF SUBCONTRACTORS; PUBLIC CONTRACT CODE STATEMENTS AND QUESTIONNAIRE; NON-COLLUSION AFFIDAVITS; the CONSTRUCTION CONTRACT, CONTRACTOR’S CERTIFICATE, SUPPLEMENTARY GENERAL PROVISIONS, SUPPLEMENTARY TECHNICAL PROVISIONS, Special Provisions, Plans, Standard Plans and Specifications; together with all additions, deletions, modifications, appendices, and all addenda (No. 0), as prepared prior to the date of bid opening setting forth any modifications or interpretations of any said documents, are hereby incorporated in and made a part of this Contract as fully as if set forth herein.
SECTION 2
For and in consideration of the payments and agreements to be made and performed by the Agency as set forth in said Contract Documents, the Contractor agrees with the Agency to construct
TRAFFIC SIGNAL COMMUNICATIONS IMPROVEMENTS
as specifically set forth in documents entitled
TRAFFIC SIGNAL INTERCONNECT FOR EMERALD DRIVE, POINSETTIA AVENUE AND N.
MELROSE DRIVE (CIP NO. 8294)
for which award of the Contract was made, to furnish at his own proper cost and expense all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, and to do everything required therein. In accordance with the provisions of Section 3700 of the Labor Code, the Contractor will be required to secure the payment of Worker’s Compensation Insurance for its employees.
SECTION 3
For furnishing all said services and materials, payment of premiums on insurance policies, obtaining all permits and licenses of a temporary nature, furnishing and removing all plant, temporary work or structures, tools, and equipment, and for doing all the Work contemplated Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
4 of 244
EXHIBIT 2
SUMMARY CONSTRUCTION – COV LOCAL Page 2 of 3 BAKER ELECTRIC & RENEWABLES LLC [00064028-1] 00064028 14900-3738-8604, v. 2
and embraced in this Contract, also for all loss and damage arising out of the nature of the aforesaid work during its progress or prior to acceptance from the action of the elements and from any unforeseen difficulties which may arise or be encountered in the prosecution of the Work, and for all other risks of any description connected with the Work, also for all expenses incurred by or in consequence of the suspension or discontinuance of work, except such as in the said Contract Documents are expressly stipulated to be borne by the Agency, and for well and faithfully completing the Work and the whole thereof within the stipulated time and in the manner shown and described in the said documents, and in accordance with the requirements of the Engineer under them, the Agency will pay, and the Contractor shall receive in full compensation therefore, the prices set forth by him in the accepted bid. The total compensation will be computed on the basis of the units of work actually performed in accordance with the requirements of the Contract Documents and paid for at the stipulated prices named in the BID SCHEDULE for completion of the Work.
SECTION 4
The Agency hereby promises and agrees with the said Contractor to employ, and does hereby employ the said Contractor to provide the materials and to do the Work according to the terms and conditions herein contained and referred to, for the price aforesaid, and hereby contracts to pay the same at the time, in the manner, and upon the conditions set forth in the Contract Documents, and the Parties for themselves, their heirs, executors, administrators, successors and assigns do hereby agree to the full performance of the covenants herein contained.
SECTION 5
Contractor agrees to indemnify, defend, and save harmless, the Agency, its officers, agents, employees and volunteers from and against any and all claims, demands, damages, losses and expenses, defense costs including attorney fees, or liability of any kind or nature which the Agency, its officers, agents and employees may sustain or incur or which may be imposed upon them for injury to or death of persons, or damage to property as a result of, arising out of, or in any manner connected with the Contractor’s performance under the terms of this Contract, caused in whole or in part by any negligent or willful acts or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, except where caused by the active negligence, sole negligence, or willful misconduct of the Agency.
[Continued on page 3.]
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
5 of 244
SUMMARY CONSTRUCTION – COV LOCAL Page 3 of 3 BAKER ELECTRIC & RENEWABLES LLC [00064028-1] 00064028 14900-3738-8604, v. 2
SECTION 6
Contractor agrees that the Payment Bond and Performance Bond attached to/submitted concurrently with this Contract are for reference purposes only, and shall not be considered a part of this Contract. Contractor further agrees that said bonds are separate obligations of the Contractor and its surety, and that any attorneys’ fee provision contained in any payment bond or performance bond shall not apply to this Contract. In the event there is any litigation between the Parties arising from the breach of this Contract, each Party will bear its own attorneys’ fees in the litigation.
IN WITNESS WHEREOF, the Parties have caused this Contract to be executed as of the Contract Date.
CITY OF VISTA, a chartered municipal
corporation
By:
JOHN B. FRANKLIN, MAYOR
ATTEST:
KATHY VALDEZ, CITY CLERK
By:
APPROVED AS TO FORM:
WALTER CHUNG, CITY ATTORNEY
By:
RISK MANAGEMENT REVIEW:
ANALISA HOLBROOK, RISK MANAGER
By:
BAKER ELECTRIC & RENEWABLES
LLC, a California limited liability company
By:
Name/Title
By:
Name/Title
APPROVED
Amanda L. Guy
20250428103111
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 Project ExecutiveJason Rupp
Executive Vice PresidentScott Williams
06/24/2025
C12
6 of 244
CITY OF VISTA ENGINEERING DEPARTMENT
PROJECT SPECIFICATIONS FOR
TRAFFIC SIGNAL INTERCONNECT FOR
EMERALD DRIVE, POINSETTIA AVENUE AND
N. MELROSE DRIVE PROJECT
C.I.P. No. 8294
Dwg. No. 4684
March 2025
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
7 of 244
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
8 of 244
1 PROJECT SPECIFICATIONS FOR
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N.
MELROSE DRIVE (C.I.P. No. 8294)
TABLE OF CONTENTS
BIDDING AND CONTRACTUAL DOCUMENTS PAGE
Notice Inviting Bids ................................................................................................. 3
Instructions to Bidders ........................................................................................... 5
Proposal Forms
Bid Proposal ............................................................................................... 23 Bid Schedule .............................................................................................. 28 Contractor’s Licensing Statement ............................................................ 34 Project References..................................................................................... 35 Contractor’s List of Subcontractors .......................................................... 36 Non-Collusion Declaration ......................................................................... 37 Bid Security Forms ..................................................................................... 38
Agreement and Bonds
Construction Contract ................................................................................ 42 Faithful Performance Bond ....................................................................... 45 Payment Bond ............................................................................................ 48 Contractor's Certificate .............................................................................. 50 Non-Collusion Declaration for Subcontractors ......................................... 51
SPECIAL PROVISIONS
Supplementary General Provisions........................................................................ 52 Supplementary Technical Provisions ..................................................................... 112
APPENDICES
Appendix A: City of Vista Guidelines for the Preparation of Traffic Signal Design Plans
Appendix B: City of Vista Stormwater Management Permit Application Form & Reference Information
Appendix C: City of Vista Standard Drawings
Appendix D: San Diego Regional Standard Drawings
Appendix E: Project Sign Layout Example
Appendix F: City of Visa Encroachment Permit
Appendix G: City of Vista Pedestrian Curb Ramp Checklist
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
9 of 244
2 PLANS
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294) (per separate document) Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
10 of 244
3 PART I
BIDDING AND CONTRACTUAL DOCUMENTS
NOTICE INVITING BIDS
PUBLIC NOTICE IS HEREBY GIVEN that sealed bids will be received by the City Clerk of the chartered City of Vista (“ Agency”) for furnishing all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, for the “TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)” in strict accordance with the Project Specifications and Plans on file in the City of Vista Engineering Department.
1. DATE OF OPENING BIDS
All Bidders are required to submit their bid electronically through the City’s Electronic Bidding System (OpenGov Procurement). Hardcopy bids will not be accepted. Bidders must register by creating a free account with OpenGov Procurement at: https://secure.procurenow.com/signup.
Registered bidders may obtain bid materials and view submission procedures at:
https://secure.procurenow.com/portal/cityofvista. Bidders must also download this bid solicitation to appear on the Bidder’s List as a “Prospective Bidder,” receive addenda, and submit a bid. Bids shall be submitted electronically no later than 4:00 PM on THURSDAY, APRIL 10, 2025.
Immediately after the bid submission deadline, bids will be unsealed and posted at:
https://secure.procurenow.com/portal/cityofvista. OpenGov Procurement will determine the official time for the advertised bid opening and such determination will be final. Bid Tabulation results will be available through OpenGov Procurement
Any bids not received in a timely manner on the Bid Opening Date, as described above, will not be considered.
Note: The City of Vista complies with the Americas with Disabilities Act. If you require reasonable accommodations for the bid opening, please contact the Office of the City Clerk, 760-639-6125, at least forty-eight (48) hours prior to the bid opening.
2. DESCRIPTION OF WORK
The Work generally consists of: mobilization, storm water pollution prevention and erosion control, traffic control, utility potholing, conduit installation, traffic signal fiber optic interconnect cable installation and connection (sp licing), traffic signal / communications equipment installation, radio equipment removal, pull box and fiber optic vault installation, and sidewalk/ concrete repair.
3. LOCATION OF WORK
The Work to be constructed is located on the following corridors in the City of Vista, California:
- Emerald Drive between West Drive and W. Vista Way
- W. Vista Way between Emerald Drive and N. Melrose Drive Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
11 of 244
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
12 of 244
5 INSTRUCTIONS TO BIDDERS
1. SITE REVIEW
Prospective bidders are expected to conduct a site review of the Project prior to submitting a bid.
2. LOCAL CONDITIONS AND BID QUANTITIES
Bidders shall read the Project Specifications and documents , examine the Plans, review available documents, and make their own estimates of the existing facilities and the difficulties that will attend the execution of the Work called for by the proposed Contract including federal, state, and local laws and regulations, local conditions, uncertainty of weather , traffic, soil conditions and all other contingencies.
Since incorporation in 1963 and chartering in 2007, the City of Vista has constructed numerous projects throughout the City. The projects may have led to development of files and records that may materially affect the Contract. All bidders are strongly encouraged to request copies of those records and familiarize themselves with those records.
Bidders shall satisfy themselves by personal examination of the location of the proposed Work, and by such other means as they may choose as to actual conditions and requirements, and as to the accuracy of the quantities stated in the BID SCHEDULE. The submission of a bid shall be conclusive evidence that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality and scope of work to be performed, as to the quantity of materials to be furnished, and as to the requirements of these Contract Documents.
Information derived from the Plans, Project Specifications, profiles or drawings, maps, other reports, or from the Engineer or his assistants, shall not relieve the bidder of this responsibility, and the interpretation of the data disclosed by borings or other preliminary investigations is not warranted or guaranteed, either expressly or implied, by the Agency. The bidder’s failure or omission to receive or examine any part of the Contract Documents or to visit the site and be familiar with the existing conditions, shall in no way relieve the bidder from obligation with respect to this bid or to the performance of the Work under this Contract.
The quantities of work or material stated in the unit price items of the BID S CHEDULE are supplied only to give an indication of the general scope of the Work . The Agency does not expressly or by implication agree that the actual amount of work or material will correspond therewith, but reserves the right to increase or decrease the amount of any unit price item of the Work by an amount up to and including twenty-five percent (25%) of any bid item(s), or to omit portions of such work as may be deemed necessary or expedient by the Engineer without a change in the unit price.
Bidders shall not, at any time after the submission of a bid, make or have any claim for damages or anticipated profits or loss of profit or otherwise because of any difference between the quantities of work actually done and material furnished and those stated in said unit price items of the BID SCHEDULE.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
13 of 244
6 The Bidder understands that the unit prices and total bid amount set forth by the Bidder in the BID SCHEDULE shall include all appurtenant expenses, premiums, taxes, royalties and fees. The Bidder shall make no reference in the BID SCHEDULE to sales tax, use tax, or any other tax. The Bidder shall make no reference in the BID SCHEDULE to any patent fees or royalties on any patented article or process which may be furnished or used or to any premium for insurance or surety bonds in the Bid. All amounts bid shall be deemed and held to include any such taxes, fees, royalties or premiums which may be applicable.
The Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, project, or device which is the subject of patent rights or copyrights held by others.
The Contractor shall pay all sales, consumer, use and other similar taxes for the Work or portions thereof provided by the Contractor which are legally enacted at the time bids are received by the Agency, whether or not yet effective. The total bid amount shall be deemed to include such taxes and the Contractor shall not be entitled to separate compensation for such taxes.
3. DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM
This Project is not a Federally-funded project.
4. INTERPRETATION OF PLANS AND PROJECT SPECIFICATIONS
If any person contemplating the submittal of a bid for the proposed Contract is in doubt as to the meaning of any requirement of the Plans or Project Specifications, or he finds any discrepancies in or omissions from the Plans or Project Specifications, they shall submit a written request for an interpretation or correction thereof via “Q&A” through the City’s Electronic Bidding System, OpenGov Procurement.
The written request must be received by the deadline listed in the City’s Electronic Bidding System, or if no deadline is listed, at least five (5) Working Days prior to the date fixed for opening of bids. The person making the request will be responsible for its prompt delivery.
Interpretations or corrections will be made only by ADDENDA to the Project Specifications or by dated revisions of the drawings . Addenda will be sent to registered bidders that have downloaded this solicitation through the City’s Electronic Bidding System.
All addenda so issued shall become part of the Contract Documents. Acknowledgement of receipt of any and all addenda is required in the BID SCHEDULE. Failure of any bidder to receive any addenda shall not relieve such bidder from any obligations imposed by such addenda. The effect of all addenda to the Contract Documents shall be considered in the bid and said addenda shall be acknowledged on the Bid Proposal. Before submitting a bid, each bidder shall inform himself as to whether or not any addenda have been issued. Failure to determine the existence of any addenda, to obtain and review such addenda, or to include in the bid any obligations imposed by such addenda issued may render the bid irregular and may result in its rejection.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
14 of 244
7 5. BIDDERS INTERESTED IN MORE THAN ONE BID
No person, firm or corporation shall make, file or be interested in more than one (1) bid for the same work unless alternative bids are specifically requested. A person, firm or corporation who has submitted a sub-proposal to a bidder, or who has quoted prices of materials to a bidder, is not disqualified from submitting a sub-proposal or quoting prices to other bidders.
6. FORM OF BID AND SIGNATURE
The bids shall be made on the Bid forms provided through the City’s Electronic Bidding System.
These documents shall constitute the bid. The bid shall be submitted electronically for this solicitation on the City’s OpenGov Procurement portal at:
https://secure.procurenow.com/portal/cityofvista. Bidders must also mail their bid security or original bidder’s bond with a postmarked date no later than the Bid Date as described in Section 11 Bid Security / Return of Bid Securities below.
The Bid for the Work is intended to establish a total cost for the Work in its entirety. The Bidder shall state in the Bid the unit prices or Lump Sums for which he proposes to supply the labor, materials, supplies and equipment necessary to complete the Work required by the Contract Documents. Certain permit requirements, General Provisions, Supplementary General Provisions, and other work required by the Plans and/or the Specifications may not be listed in the Bid Schedule and are, in general, applicable to more than one listed Bid Item. Other required work may not be listed as a separate item in the Bid Schedule, but is necessary to complete the Work described in the Plans and/or the Project Specifications. The Bidder shall include the cost of all work not listed as a separate item in the Bid Schedule in the various related items of work listed in the Bid Schedule, so that the Bid for the Project reflects the total cost for completing the Work in its entirety.
If the proposal is made by an individual, it shall be signed and his full name and address shall be given; if it is made by a firm, it shall be signed with the partnership name by a member of the firm, who shall also sign his own name, and the name and ad dress of each member shall be given; and if it is made by a corporation, the name of the corporation shall be signed by its duly authorized officer or officers attested by the corporate seal, and the names and titles of all officers of the corporation shall be given.
7. PREPARATION OF THE BID / REJECTION OF THE BID
The Bid shall be prepared such that it is complete and responsive to all requirements of the Contract Documents. The completed Bid shall consist of the following forms:
a) Bid Proposal
b) Bid Schedule (to be completed through the City’s Electronic Bidding System, OpenGov Procurement)
c) Description of Base Bid Items (copy, include, and upload with bid package) d) Contractor’s Licensing Statement
e) Project References
f) Contractor’s List of Subcontractors
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
15 of 244
8 g) Non-Collusion Declaration
h) Bid Security Form (with bid bond, cash, certified check or cashier’s check included)
Registered bidders may obtain the Contract Documents through the City’s Electronic Bidding System. If any bid forms are missing from the Contract Documents obtained by the Bidder, directly from OpenGov Procurement or through other means, it shall be the Bi dder's responsibility to contact the Agency and obtain all required Bid Document forms prior to submitting a bid.
Blank spaces in the Bid shall be properly filled in (using figures in the Bid Schedule). The Bid shall contain an acknowledgment of receipt of all addenda.
The phraseology of the Bid must not be changed, and no addition shall be made to the items mentioned therein. Alternative bids shall not be considered unless specifically requested and authorized by the Agency.
The Bid shall be signed in accordance with the “Instructions for Signing Bids, Bonds, and Contracts”, included in the Contract Documents, and as required by the City’s Electronic Bidding System.
.
The bidder shall set forth for each unit basis item of work a unit price and a total for the item, and for each lump sum item a total for the item, all in clearly legible figures in the respective spaces provided for that purpose. In the case of unit basi s items, the amount set forth under the "Item Total" column shall be the product of the unit price bid and the estimated quantity for the item. Unit prices shall not exceed two (2) decimal places.
All extensions of the unit prices bid and sums will be subject to verification by the Agency. If the unit prices entered by the Bidder exceed two (2) decimal places, the Agency will only use the first two (2) digits after the decimal points without rounding up or down.
In case of discrepancy between the unit price and the total set forth for a unit basis item, the unit price shall prevail, except as provided in (a) or (b), as follows:
a) If the amount set forth as a unit price is unreadable or otherwise unclear, or is omitted, or is the same as the amount as the entry in the item total column, then the amount set forth in the item total column for the item shall prevail and shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price;
b) If the product of the entered unit price and the estimated quantity is exactly off by a factor of ten, one hundred, etc., or one -tenth, or one -hundredth, etc. from the entered total, the discrepancy will be resolved by using the entered unit price or item total, whichever most closely approximates percentage -wise the unit price or item total in the Agency's Final Estimate of cost.
Bids on lump sum items shall be item totals only; if any unit price for a lump sum item is included in a bid and it differs from the item total, the item total shall prevail.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
16 of 244
9 If both the unit price and the item total are unreadable or otherwise unclear, or are omitted, the bid may be deemed irregular. Likewise if the item total for a lump sum item is unreadable or otherwise unclear, or is omitted, the bid may be deemed irregul ar unless the project being bid has only a single item and a clear, readable total bid is provided.
A Bid shall be considered irregular if certain situations occur, including, but not limited to, the following:
a) The Bid contains blank spaces that are not properly filled in. b) The Bid contains unauthorized provisions, conditions, limitations, or alternatives. c) The Bid is either not typewritten or not printed in ink. d) The Bid contains interlineations, alterations, erasures, clerical errors or is otherwise illegible or unclear, or not properly initialed.
e) The Bid is not properly signed in accordance with the instructions. f) The Bid contains unit prices and/or item totals that are unreadable or otherwise unclear, or are omitted.
g) The Bid contains a significant “material” difference between the bid total written in figures, the bid total written in words, and/or the sum of the item totals after any math errors are corrected.
Bidder’s failure to submit the Bid on time through the City’s Electronic Bidding System, submit a complete Bid using all of the required Bid forms provided in the Contract documents or addenda, include a price for any Bid item that requires the Bidder to s ubmit a price, acknowledge all addenda, or submit the appropriate Bid Security shall render the Bid non -responsive and shall be cause for its rejection.
In accordance with the provisions of Section 1771.1(b) of the California Labor Code – the Agency will not accept bid or enter into a Contract without proof of the contractor’s current registration with the California Department of Industrial Relations pursuant to Section 1725.5.
The Agency, in its sole discretion, reserves the right to reject any or all bids, and to waive any informalities or minor irregularities in the Bids, unless waiving such irregularity would give a competitive advantage to a Bidder.
8. ALTERNATIVE SCHEDULES
Bidders are directed to review the BID SCHEDULE and the appendices for details regarding the alternate bid items, if included.
The Agency will evaluate the bids based on the total amount of the Base Bid Items, and will not include the Alternate Bid Item(s) in determining the lowest responsible bidder. The Agency reserves the right to award the Contract on the Base Bid Items, and with or without any or all of the Alternate Bid Item(s). The Agency reserves the right to adjust the quantity of the Alternate Bid Item(s) after the award of contract.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
17 of 244
10 9. LIST OF SUBCONTRACTORS FILED WITH BID
In accordance with the provisions of Sections 4100 through 411 3, inclusive, of the Public Contract Code of the State of California (“Subletting and Subcontracting Fair Practices Act”), each bidder shall submit with his bid the name, location of place of business, and Contractor’s License Number of each proposed subcontractor who will perform work or labor or render service to the principal Contractor in an amount in excess of one -half of one percent (0.5%) of the principal Contractor's bid, or in the case of the construction of streets or highways, in exces s of one-half of one percent (0.5%) or ten thousand dollars ($10,000), whichever is greater, and shall state the portion and dollar value of the Work which will be done by each such subcontractor in the List of Subcontractors form. If no subcontractor is listed for a portion of the Work, then the Contractor is required to perform that portion with his own forces.
An inadvertent error in listing the subcontractor’s license number shall not be grounds for filing a bid protest, or grounds for considering the bid nonresponsive, if the corrected contractor’s license number is submitted to the public entity by the prime contractor within 24 hours after the bid opening, provided that the corrected license number corresponds to the submitted name and location of the subcontractor.
Pursuant to Section 1725.5 of the Labor Code of the State of California , no contractor may be awarded a public works contract and no subcontractor of any tier may work on a public works project without proof of registration with the Department of Industrial Relations. To comply with these regulations, each bidder being considered for award of the C ontract shall submit to the Agency the names and PWC Registration Number of each proposed subcontractor of any tier who will perform work or labor or render service to the principal Contractor in any amount within 7 days after the bid opening date. The inadvertent listing on the bid documents of a subcontractor that is not registered with the California Department of Industrial Relations will not necessarily invalidate the bid. An unregistered subcontractor can be replaced with one who is registered.
10. NON-COLLUSION DECLARATIONS
The bidder is required to execute a Non-Collusion Declaration in the form attached hereto, and submit the form with the bid. The Agency reserves the right to require, before awarding the contract, that the principal Contractor secure from each proposed subcontractor a Non-Collusion Declaration in the form also attached hereto, and submit all forms to the Agency.
If at any time it shall be found that the person, firm or corporation to whom the Contract has been awarded has, in presenting any bid or bids, colluded with any other party or parties, then the Contract so awarded shall be null and void, and the Contractor and the Contractor’s sureties shall be liable to the Agency for all loss or damage which the Agency may suffer thereby, and the Agency may advertise anew for bids for such work.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
18 of 244
11 11. BID SECURITY / RETURN OF BID SECURITIES
Each bidder shall submit with his bid an unconditional certified or cashier's check drawn on a solvent state or national bank, or a bidder's bond with a responsible corporate surety, on the form attached hereto, subject to the provisions for “Bonds” herein . Unless otherwise stated in the Contract Documents, said bid security or bidder's bond shall be in a sum at least ten percent (10%) of the total base bid amount, and shall be made payable to the Agency as a guaranty that the bidder will, if an award is made, in accordance with the terms of his bid, promptly execute a Contract in the required form, secure payment of Workmen's Compensation, and furnish satisfactory Performance Bond, Payment Bond, and certificates of insurance, and endorsements within ten (10) Working Days following the posting of the Notice of Intent to Award a contract.
Notice of instructions to Principal and Surety regarding completion of Bidder’s Bond:
1) Principal’s signature with title must be properly notarized (i.e., proprietorship, partnership, corporation, joint venture). If corporation, affix seal; 2) Signature of Attorney-in-Fact for Surety must be properly notarized; 3) Attach certified copy of Power of Attorney for Surety’s Attorney-in-Fact; and 4) If bond is executed in excess of surety company’s treasury limit, evidence of how bond was reinsured must be attached over signature of Attorney-in-Fact.
Bidders must scan and upload a copy of their bid security or bidder’s bond with their electronic bid submittal in OpenGov Procurement.
Bidders must also mail their bid security or original bidder’s bond with a postmarked date no later than the Bid Date, to the following address:
ATTN: Darra Woods, Principal Transportation Mobility Planner City of Vista Engineering Department
200 Civic Center Drive
Vista, CA 92084
If a bidder to whom an award is made fails or refuses to execute the Contract, secure the payment of Worker's Compensation and furnish the required bonds and proof of insurance, all within the time stated in the provisions for “ Execution of Contract / FAILURE TO EXECUTE CONTRACT” herein, the money represented by said check or bidder's bond shall become and remain the property of the Agency, the amount thereof being agreed to by the bidder as liquidated damages due the Agency on account of the delay in the execution of the Performance Bond, Payment Bond, and proof of insurance coverage, and in the performance of work thereunder, resulting from such failure or refusal.
The Agency reserves the right to retain the bid security of the three (3) apparent lowest responsible Bidders until the Contract Documents have been formally executed by the successful Bidder and the A gency, and the successful Bidder has filed with the A gency the Faithful Performance Bond, the Contractor’s Payment Bond , and the insurance policies or certificates required by the Bid Documents, after which such bid securities will be returned to the respective Bidders whose bids they have accompanied.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
19 of 244
12 12. PROJECT REFERENCES
All bidders shall provide evidence satisfactory to the Agency that the bidder has prior experience to properly perform in accordance with the terms of these Plans and Specifications by completing and submitting the PROJECT REFERENCES spreadsheet with his bid. The PROJECT REFERENCES list shall include projects succe ssfully performed by the Bidder of comparable magnitude that he or his associates are personally competent to manage the proposed undertaking, and to carry it forward to a successful conclusion.
13. LICENSE REQUIREMENTS
All prospective contractors submitting a bid shall have the appropriate license as required by these specifications. Failure to possess the specified license at the time of award shall render the bid as non-responsive and shall act as an absolute bar to award the Contract to any bidder not possessing said license at the time of award. Any Contract awarded to a contractor who was not properly licensed at the time of award or at any time during the Contract period shall be void pursuant to Section 7028.15 of the Business and Professions Code. The Agency shall verify that a contractor is properly licensed prior to the award of the Contract as part of determining the lowest responsible and responsive bidder.
14. CONTRACTOR'S REQUIRED SHARE OF CONTRACT WORK
In accordance with Subsection 3-2, SELF-PERFORMACE of the Standard Specifications for Public Works Construction, the Contractor shall perform, with its own personnel from within its organization, Contract work amounting to at least fifty percent (50%) of the Contract Price, except that any designated "Specialty Items" may be performed by subcontract and the amount of any such "Specialty Items" so performed may be deducted from the Contract Price before computing the amount of work required to be perform ed by the Contractor with its own personnel [i.e. the percentage of work which will not be performed by a Bidder’s own forces will be determined by (1) adding the dollar value of all contracts shown on the list of subcontractors (excluding the dollar amoun t of any specialty items), then (2) dividing such total by the Bidder’s Total Bid Amount (excluding the dollar amount of specialty bid items)].
Specialty Items shall be as listed in Subsection 3-2 (“SELF-PERFORMACE.”) of the latest edition of the San Diego Regional Supplement of the Standard Specifications for Public Works Construction (“Greenbook”) and as identified with an “S” in the Bid Item Number column of the BID SCHEDULE.
15. ANNUAL PUBLIC WORKS BIDDER REGISTRATION (SB 854)
In accordance with the provisions of California Senate Bill 854, passed by the California State Senate on June 20, 2014, all contractors and subcontractors bidding and performing work on Public Works Projects must register on an annual basis with the California Department of Industrial Relations (DIR) and furnish electronic payroll records to the Labor Commissioner’s Office.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
20 of 244
13 In accordance with the provisions of Section 1771.1(a) of the California Labor Code, a contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any Contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the Contract is awarded. Prime contractors and their subcontractors must possess and maintain such registration with DIR in order to be awarded contracts and to perform work.
The Agency will verify that the contractors or subcontractors that bid on, or are listed in the bid proposal of, this Contract are currently registered and qualified to perform public work pursuant to Section 1725.5 in the State of California through the following URL website link at:
https://services.dir.ca.gov/gsp?id=dir_contractors&table=x_cdoi2_letf_core_contracto r_lookup
In accordance with the provisions of Section 1771.1(a) of the California Labor Code – the Agency will not accept a bid or enter into a Contract without proof of the contractor’s current registration to perform public works pursuant to Section 1725.5.
In accordance with the provisions of Section 1773.3 of the California Labor Code, the Agency will provide notice to the Department of Industrial Relations of any public works Contract within thirty (30) days of the award, but in no event later than the first day in which a contractor has workers employed upon the public work, using the online PWC-100 “Extract of Public Works Contract Award” form, which can be found at:.
https://www.dir.ca.gov/pwc100ext/LoginPage.aspx
The online PWC-100 form is also transmitted to the Department of Apprenticeship Standards (DAS) to inform them of the award of a contract.
16. MODIFICATION AND WITHDRAWAL OF THE BID
Any Bidder may modify his prior to the scheduled closing time for receipt of bids by submitting an amended bid through the City’s Electronic Bidding System.
A bidder may withdraw his bid before the hour fixed for opening bids, without prejudice to himself, by cancelling their bid submission through the City’s Electronic Bidding System . No proposal may be withdrawn after the hour fixed for opening bids without rendering the accompanying certified or cashier's check or bidder's bond subject to forfeiture as liquidated damages in like manner as in the case of failure to execute the Contr act after award, as hereinafter provided.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
21 of 244
14 After the bids have been publicly opened, they shall not be withdrawn by the Bidders for a period of at least ninety (90) calendar days subject to the execution stated in the paragraph below. The ninety (90) calendar day review period may be extended by t he Agency and written approval by the Bidder.
A Bidder shall be permitted to withdraw a bid after the opening of the bids only if the Bidder established to the satisfaction of the Agency ALL of the following:
a) A clerical error was made by the Bidder in filling out the bid; and the error was not due to:
1) an error in judgment;
2) an error in inspecting the site of the Work, or;
3) an error in reading the Plans and Contract Documents. b) The clerical error made the bid materially different than the Bidder intended the bid to be. c) The Bidder gave the Agency written notice within five (5) Working Days excluding Saturdays, Sundays, and State holidays, after the opening of the bids, in which said notice specifies in detail the nature of the error and how the error was made per Public Contract Code 5103(b).
17. (INTENTIONALLY LEFT BLANK)
18. PUBLIC OPENING OF BIDS
No bid received after the time named or at any place other than the place stated in the Notice Inviting Bids shall be considered. Immediately after the bid submission deadline, bids will be unsealed and posted at: https://secure.procurenow.com/portal/cityofvista. OpenGov Procurement will determine the official time for the advertised bid opening and such determination will be final. Bid Tabulation results will be available through OpenGov Procurement.
After the bids are publicly opened, the Agency shall review all bids for responsiveness, compare the bids to the Engineer’s Opinion of Probable Cost and investigate the responsibility and qualifications of all Bidders to whom the award is contemplated, for a period not to exceed ninety (90) calendar days after the Bids have been opened. Based on the findings from the review of the Bids, the Agency will provide a Notice of Intent to Award a contract to all bidders.
Following the posting of the Notice of Intent to Award a contract, anyone interested in inspecting bid documents in person or receiving electronic copies shall make a request to the City Engineer following the posting of the Notice of Intent to Award a con tract. Bid documents will be sent electronically, and appointments for inspection of the bid documents will be scheduled to occur, within five (5) Working Days after the request is received by the Agency.
19. DISQUALIFICATION OF BIDDERS
Any one or more of the following causes may be considered as sufficient for the disqualification of Bidder and the rejection of the Bidder’s bid or bids:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
22 of 244
15 a) Submittal of more than one (1) bid for the same work from an individual firm, partnership, or corporation under the same or different names.
b) Evidence of collusion among Bidders.
c) Modification of BID SCHEDULE.
d) Submittal of an incomplete or invalid bid, and / or failure to include all required information, which precludes full analysis and review of said Bid and / or which precludes meaningful comparison of the Bid with other bids received by the Agency.
20. BID PROTESTS
Any bidder who submits a valid bid shall have the right to file a bid protest with the Agency before 5:00 p.m. on the fifth Working Day following the posting date of the Notice of Intent to Award a contract. However, bidder shall receive an extension to this deadline if the Agency has not fulfilled bidder’s request for electronic copies of the bid documents or for an opportunity to inspect the bid documents at least two (2) Working Days prior to the deadline. In such cases, bidder may submit a bid protest before 5:00 p.m. on the fifth Working Day following the date on which bidder receives, or is provided an opportunity to inspect, the bid documents. Bid protests must be submitted in writing to the City Engineer of the City of Vista, City of Vista Civic Center, Engineering Department, 200 Civic Center Drive, Vista, California 92084-6275. The time limits and requirements set forth in this section are mandatory, and are the bidder’s sole and exclusive remedy in the event of a bid protest, and failure to comply with these requirements shall constitute a waiver of any right to further pursue the bid protest, including filing a Government Code Claim or legal proceedings. If a protest is received from anyone other than a bidder, or after the specified time period, the protest shall be invalid. The pro test shall conform to the following requirements:
a) The initial protest document shall contain a complete statement of the basis for the protest. b) The protest shall refer to the specific portion, or portions, of the document that form the basis for the protest.
c) The protest shall contain the name, address, and telephone number of the person representing the protesting party.
d) The party filing the protest shall concurrently transmit a copy of the initial protest document, and any attached documentation, to all other parties with a direct financial interest that may be adversely affected by the outcome of the protest. Such p arties shall inc lude all other bidders or proposers who appear to have a reasonable prospect of receiving an award depending upon the outcome of the protest.
e) The Agency shall issue a decision on the protest.
21. AWARD OF CONTRACT
No bidder may withdraw its bid for a period of ninety (90) calendar days.
The Contract shall be awarded within ninety (90) calendar days after the opening of bids, if it is in the interest of the Agency to do so. The Agency reserves the right to waive any informality or minor irregularities in any bid, to reject any or all bids, to reject one part of a bid and accept the Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
23 of 244
16 other, except, to the extent that bids are qualified by specific limitations, to take bids under advisement for a period of ninety (90) calendar days after the date the bids are publicly opened, and to make award to the lowest responsible bidder as the interest of the Agency may require.
All terms and conditions contained in the Contract Documents shall become a part of the contract.
22. LOCAL BUSINESS ENTITY PREFERENCE
A Local Business Entit y, as defined below, may be entitled to a preference as provided for in Section 3.08.040 of the Vista Municipal Code. If the lowest bid is submitted by someone other than a Local Business Entity, the Local Business Entity who submitted the lowest bid that is within five percent (5%) of the lowest bid shall be given the opportunity to become the lowest bidder by reducing its bid to match the bid of the lowest bidder. In order to be deemed the lowest bidder, the Local Business Entity must agree in writing to reduce its bid to match the bid of the lowest bidder within three (3) Working Days of the City’s request to match. Thereafter, the Contract may be awarded to that Local Business Entity if it otherwise qualifies as the Lowest Responsible Bidder.
A “Local Business entity” is:
1) a) A business entity providing services when the entity’s principal place of business is located within the City as identified on a City business license or other official documents; or
b) a vendor making a sale of goods provided that such business or entity possesses a valid and current seller’s permit or equivalent issued by the State Board of Equalization or its successor which identifies the City of Vista as the points of sale for all of its taxable retail sales within the City’s jurisdiction; and
2) Holds a City of Vista business license that has been in effect for at least six (6) months prior to the issuance of a request for bids/proposals for which the company wishes to bid; and
3) Employs at least two (2) full-time, or four (4) part-time employees of the company whose primary residence is located within the City of Vista; or, if the company has no employees, then is at least fifty percent (50%) owned by one or more persons whose primary residences are located within the City of Vista.
23. VETERAN-OWNED BUSINESS ENTITY [(CITY PROJECTS ONLY – DELETE THIS SECTION IF A BSD CONTRACT)]
A Veteran-Owned Business Entity, as defined below, may be entitled to a preference as provided for in section 3.08.020 of the Vista Municipal Code. Should the bidder who submits the lowest bid not be a Veteran-Owned Business Entity, then the lowest bid submitted by a Veteran-Owned Business Entity which is within two percent (2%) of the lowest bid may be deemed the Lowest Monetary Bidder, whether or not that bidder is the second lowest bidder, if the Veteran -Owned Business Entity agrees, in writing, to reduce its bid to match the bid of the lowest bidder within three days of the City’s request to match. Thereafter, the Contract may be awarded to the Veteran-Owned Business Entity if it otherwise qualifies as the Lowest Responsible Bidder.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
24 of 244
17 A “Veteran-Owned Business Entity” is:
1) Is a business entity which at least fifty one percent (51%) owned by one or more veterans; and
2) Holds a business license for at least 6 months prior to the issuance of the request for bids/proposals in
(a) the City of Vista; or
(b) one of the other Innovate 78 Corridor Economic Development Initiative cities of Carlsbad, Escondido, Oceanside, or San Marcos, provided that the city issuing the business license has enacted a substantially similar veterans business preference program as determined by the City Manager; and 3) (a) Is a Service -Disabled Veteran-Owned Small Business (SDVOSB) or Veteran -Owned Small Business (VOSB) registered with the Office of Small & Disadvantaged Business Utilization’s Vets First Verification Program, a division of the U.S. Department of Veteran Affairs, or (b) is a disabled Veteran Business Enterprise (DVBE) certified and registered with the Office of Small Business and DVBE Service, a division of the California Department of General Services.
24. EXECUTION OF CONTRACT / FAILURE TO EXECUTE CONTRACT
A bidder whose proposal is being recommended for acceptance shall execute a written Contract with the Agency, in the form of the CONSTRUCTION CONTRACT attached hereto, prior to contract award and within the time requested by the Agency. Thereafter, a bidder to whom an award is made shall secure the payment of Workmen's Compensation, and furnish good and approved bonds and insurance certificates, all as required in the following paragraph and all in accordance with the provisions hereof, w ithin ten (10) Working Days from the date of the posting of the Notice of Intent to Award a contract, by the Agency to the bidder, according to the address given by him in his proposal.
If a bidder to whom award is made fails or refuses execute the Contract prior to bid award, or to thereafter conform to any of the stipulated requirements in connection therewith, the money represented by his check or bidder's bond shall become the property of the Agency, as provided in the provisions for “Bid Security” herein, any award made will be annulled, and, at the discretion of the Agency, an award may be made to the bidder whose proposal is next most acceptable to the Agency, and such bidder shall fulfill every stipulation embraced herein as if he were the party to whom the first award was made. A corporation whose proposal is being recommended for acceptance may be required, before the Contract is executed, to furnish evidence of its corporate existence, of its right to do business in California, and of the authority of the officer signing the Contract and bonds for the corporation.
25. BONDS
Except as otherwise provided in the Contract Documents, a bidder to whom the Contract is awarded shall, within the time stated in the provisions for “EXECUTION OF CONTRACT / FAILURE TO EXECUTE CONTRACT” herein, furnish a bond with an admitted corporate surety, or corporate Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
25 of 244
18 sureties conditione d upon the faithful performance of the said bidder of all covenants and stipulations in the Contract. Said bond, hereinafter referred to as the Faithful Performance Bond, shall be in the form approved by the Agency and in the penal sum of at least one hundred percent (100%) of the total base bid amount payable under the Contract secured by two (2) or more sufficient sureties or by a surety company.
Within the time mentioned in the preceding paragraph, the bidder to whom the Contract is awarded shall also furnish a Payment Bond, approved by the Agency, in accordance with the provisions of Civil Code Section 3225 -3228, inclusive, and Sections 3247 -3252, inclusive.
Unless otherwise specified in the Contract Documents, said Payment Bond shall be in a sum not less than one hundred percent (100%) of the total amount payable by the terms of this Contract, but not less than the sum prescribed by Section 3248 of the Civil Code, in any case.
Each bond shall incorporate, by reference, the Contract, and be signed by both the Contractor and the Surety.
Sureties must:
1) be listed in the latest version of U.S. Department of Treasury Circular 570 at:
https://www.fiscal.treasury.gov/fsreports/ref/suretyBnd/c570_a-z.htm
2) be authorized to issue bonds in California;
3) have bonding limitation shown in said Circular 570 sufficient to provide bonds in the amount required for the contract.
The Agency will verify that the corporate surety or sureties that furnish bonds for this Contract are admitted sureties authorized to provide such services in the State of California through the following URL website link at:
http://www.insurance.ca.gov
The surety or sureties on all bonds furnished must be satisfactory to the Agency. All insurance or surety companies providing insurance or surety bond(s) under the Contract shall be admitted in the State of California to transact the insurance business in the class of the type provided and shall have a general policy holder's rating of "A" or higher and a Financial Class V ($10,000,000) or better as established in the most current A. M. Best's Key Rating Guide or equivalent or greater rating established by another recognized rating entity such as Moody’s; provided however, that for the workers' compensation and employers' liability insurance business and having a general policy holders' rating of "A" or higher and a Financial Class VI or higher in the most current A.M.
Best's Key Rating Guide. The party required to furnish bonds pursuant to these instructions shall furnish such bonds at his cost and expense. The Agency reserves the right to reject any bond if, in the opinion of the Engineer, the surety's acknowledgment is not in the form included in the Contract Documents or in another form substantially as prescribed by law.
Surety companies and insurance companies shall familiarize themselves with all of the conditions and provisions of the contract, and they waive the right of special notification of any change or modification of the Contract or of decreased or increased work or of the cancellation Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
26 of 244
19 of the contract, or of any other acts by the Agency or its authorized agents, under the terms of the contract. Notwithstanding the provisions of any other contract or agreement, the failure of any surety company or insurance company to receive notification of any of the aforesaid changes shall in no way relieve the surety company or insurance company of its obligations under the contract. Notwithstanding any other provisions of the Contract Documents inconsistent with the provisions of this section, the C ontractor shall not be responsible for the cost of repairing or restoring damage to the Work in excess of five percent (5%) of the Contract price caused by an act or acts of God, as defined in Public Contract Code Section 7105, occurring after the Contract for the Work is entered into.
To be approved, the Payment Bond must be in the form provided in these Project Specifications.
Unless a Contractor’s Payment Bond is filed and approved as herein provided, no claim in favor of the Contractor arising under the Contract shall be audited, allowed or paid by the Agency. Any persons named in Section 3181 of the California Civil Code shall receive payment of their respective claims in the manner provided by Chapter 4, Part 4, Division 3, Title 15 of the California civil Code upon having complied with the conditions of Section 3183 of the California Civil Code.
26. NOTIFICATION OF SURETY COMPANIES
The surety companies and other signers of any of the above mentioned bonds and insurance companies, shall familiarize themselves with all of the conditions and provisions of the contract, and they waive the right of special notification of any change or mo dification of the Contract or of extension of time, or of decreased or increased work, or of the cancellation of the Contract, or of any other act or acts by the A gency or its authorized agents, under the terms of the Contact; and failure to so notify the aforesaid surety companies or insurance companies of changes shall in no way relieve the surety companies of their obligation under the Contract.
27. LIABILITY INSURANCE
Before the Contract is executed on behalf of the Agency, a bidder to whom the Contract has been awarded shall furnish to the Agency a policy or certificate of protective liability insurance in which the Agency shall be named as an additional insured with the bidder. The policy shall insure the Agency, its officers and its employees, the bidder, his employees, and his subcontractors and their employees, and their heirs, agents, and employees, while acting within the scope of their duties, against all claims arising out of or in connection with the Work to be performed, and shall remain in full force and effect until the Work is accepted by the Agency. The policy shall provide for the limits stated with any insurance policy carried by the Agency. The public liability insurance shall be in the amounts set forth in of the Supplementary General Provisions. The insurance company shall meet the financial strength rating requirements set forth in the General Provisions.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
27 of 244
20 28. INSURANCE CODE REQUIREMENTS
Attention is called to the provisions of the Insurance Code of the State of California with reference to the writing of insurance policies and bonds covering risks located in this state, and the premiums and commissions thereon. A bidder to whom the Contract is awarded shall furnish, at the time his bond or bonds are submitted for approval, satisfactory evidence that the requirements of said code have been observed.
29. ASSIGNMENT
In accordance with Section 4552 of the Government Code, the bidder shall conform to the following requirements. In submitting a bid to the Agency, the bidder offers and agrees that if the bid is accepted, it will assign to the Agency all rights, title and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec tion 15) or under the Cartwright Act [Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code], arising from purchases of goods, services or materials by the Bidder for sale to the purchasing body pursuant to the bid. Such assignment shall be made and become effective at the time the purchasing body tenders final payment to the bidder.
30. WAGE RATES
Pursuant to the Vista City Charter and the Vista Municipal Code, payment of prevailing wages and compliance with the California Labor Code Sections 1770 et seq IS required for this Project.
It shall be mandatory upon the Contractor to whom the Contract is awarded, and upon all subcontractors under him, to pay not less than the general prevailing rates of wages to all workers employed in the execution of this Contract in accordance with the provisions of the California Labor Code and general law. Certified payroll on an approved compliance format is required for all work under this Contact and shall be submitted directly to the Labor Commissioner’s Office as required by law.
In accordance with the requirements of Section 1726 of the Labor Code, the Agency will ensure that public works contractors pay prevailing wages and are in compliance with public works laws and will report any suspected violations to the Labor Commissioner:
In accordance with the requirements of Section 1727 (a) of the Labor Code, the Agency will withhold and retain all amounts required to satisfy any Civil Wage and Penalty Assessment.
Information on the current prevailing wages can be obtained by contacting the State of California, Department of Industrial Relations, Division of Labor Statistics and Research, PO Box 420603, San Francisco, California, 94142, (415) 703 -4774 or from the California Department of Industrial Relations’ internet website at http://www.dir.ca.gov.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
28 of 244
21 31. SUBSTITUTION OF SECURITIES IN LIEU OF RETENTION
The Contractor may elect to receive one hundred percent (100%) of payments due under the Contract Documents from time to time, without retention from any portion of the payment by the Agency, if the Contractor deposits securities of equivalent value with the Agency in accordance with the provisions of Section 22300 of the California Public Contract Code. Such securities, if deposited by the Contractor, shall be valued by the Agency, whose decision on valuation of the securities shall be final. Securities eligible for investment under this provision shall be limited to those listed in Section and 16430 of the California Government Code.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
29 of 244
22 INSTRUCTIONS FOR SIGNING BIDS, BONDS AND CONTRACTS
CORPORATIONS
Give name of corporation.
Proof of authorization shall be established (pursuant to Corporation Code Section 313) when the corporate officers listed below both sign the documents:
Signatures: Chairman of Board or President or Vice -President AND Secretary or Assistant Secretary or Chief Financial Officer or Assistant Treasurer.
Affix corporate seal and Notary's acknowledgment.
Others may sign to bind the corporation if the Agency has been furnished a certified copy of a resolution of the corporate board of directors authorizing them to do so.
PARTNERSHIPS
Signatures: All members of partnership. One may sign if the Agency has a copy of authorization [i.e., a Certificate of Partnership (State form LP -1 for Limited Partnerships) or a copy of the partnership agreement is sufficient to establish the authority of a single general partner to bind the partnership].
Affix Notary's acknowledgment.
JOINT VENTURES
Give the names of the joint ventures.
Signatures: All joint ventures. One may sign if the Agency has a copy of authorization.
Affix Notary's acknowledgment.
INDIVIDUALS
Signature: The individual.
Affix Notary's acknowledgment.
FICTITIOUS NAMES
Show fictitious names.
Satisfy all pertinent requirements shown above (note: If the Bidder is a sole proprietorship, either a Fictitious Business Name Statement or a City of Vista business license is sufficient to establish the authority of an individual to bind the sole proprietorship).
BONDS
In addition to all pertinent requirements above, give signature of Attorney -in-Fact and apply surety's seal.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
30 of 244
23 BID PROPOSAL
From: ______________________________________________________________, Bidder,
For: The construction of
TRAFFIC SIGNAL COMMUNICATIONS IMPROVEMENTS
as specifically set forth in documents entitled
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N.
MELROSE DRIVE (C.I.P. No. 8294)
The undersigned hereby proposes and agrees that if his bid as submitted in the attached BID SCHEDULE be accepted, he will contract in the form so approved to perform all work for which a Contract may be awarded him, to furnish any and all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore as provided in the Contract Documents, and to do everything required therein for the proposed Project as specifically set forth in said Contract Documents, together with appurtenances thereto, all as set forth on the Drawings and in the Project Specifications and other Contract Documents; and he further proposes and agrees to complete all the Work called for by the Drawings, Project Specifications, and other Contract Documents in strict conformity therewith within the time limits set forth therein; and that he will accept as full payment therefore the prices set forth in the BID SCHEDULE forming a part hereof.
The undersigned hereby submits either a Bid Bond or Bid Security in the form of Cash, a Cashier’s Check, or a Certified Check, using the forms included in these Bid Documents, properly made payable to CITY OF VISTA, hereinafter designated as the Agency, in an amount that is at least ten percent (10%) of the total base bid amount. The Bid Bond or Bid Security is attached hereto and is given as a guaranty that the undersigned will execute the Contract and furnish the required bonds if awarded the Contract and, in case of failure to do so within the time provided, the proceeds of said bond or bid security shall be forfeited to the Agency. The Surety’s liability to the Agency for forfeiture of the face amount of the bond shall be considered as established.
(Continued on next page)
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
31 of 244
24 It is understood and agreed that:
1. The undersigned has carefully examined all Bid documents and other Documents which will form the Contract, including all addenda as prepared prior to the date of bid opening setting forth any modifications or interpretations of any said documents.
2. The undersigned has, by investigatin g the site of work, by reviewing and analyzing the Plans and Specifications, and by otherwise familiarizing himself with the Project, has satisfied himself as to the nature and location of the Work and has fully informed himself as to all conditions and matters which can in any way affect the Work or the cost thereof.
3. The undersigned fully understands the scope of the Work and has included in the various related items of Work the cost of all work not listed as a separate item so that the Bid for the Project reflects the total cost for completing the Work in its entirety, has checked carefully all words and figures inserted in this Bid, and he further agrees that the Agency shall in no way be responsible for any errors or omissions in the preparation of this proposal.
4. The undersigned will execute the Contract and furnish the required Performance Bond, Payment Bond, and proof of insurance coverage within the stipulated time after the posting of a notice to him of acceptance of his bid by the Agency; and further, that this bid may not be withdrawn for a period of ninety (90) calendar days after the date set for the opening thereof unless otherwise required by law. If any bidder shall withdraw his bid within said period, the bidder shall be liable under the provisions of the Bid Security, or the bidder and his surety shall be liable under the Bid Bond, as the case may be.
5. The surety or sureties and insurance companies named in the space provided have agreed to furnish bonds, insurance, and endorsements in the form and amounts set forth in the Contract Documents in the event the Contract is awarded on the basis of this proposal.
6. The undersigned hereby certifies that this proposal is genuine and not sham or collusive or made in the interest or in behalf of any person not herein named, and the undersigned has not directly or indirectly induced or solicited any other bidder to put in a sham bid, or any other person, firm or corporation to refrain from bidding, and the undersigned has not in any manner sought by collusion to secure for himself an advantage over any other bidder.
7. In conformance with current statutory requirements of Section 1860, et. seq., of the Labor Code of the State of California, the undersigned confirms the following as his certification:
“I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.”
8. Receipt of Addenda No. ___ through ___ is hereby acknowledged. (If none, write “NONE”).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
32 of 244
25 9. In compliance with the Notice Inviting Bids and all the provisions hereinbefore stipulated, the undersigned, with full cognizance thereof, hereby proposes to perform the entire work for the prices set forth in the attached BID SCHEDULE upon which award of the Contract is made.
(Continued on next page)
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
33 of 244
26 DATE: ________________, 20_____ BIDDER’S NAME___________________________
BY______________________________________
Signature
________________________________________
Printed Name
TITLE____________________________________
BY______________________________________
Signature
________________________________________
Printed Name
TITLE____________________________________
(CORPORATE SEAL) BIDDER'S MAILING ADDRESS:
Name and address of all members ________________________________________ of the firm or names of all officers
of the corporation. ________________________________________
CORPORATION ORGANIZED UNDER THE LAWS
_________________________________ OF THE STATE OF
_________________________________ ________________________________________
_________________________________ CONTRACTOR'S LICENSE # _________________
_________________________________ EXPIRATION DATE_________________________
_________________________________ CONTRACTOR'S LICENSE CLASS______________
_________________________________ SURETY OR SURETIES: _____________________
_________________________________ ________________________________________
_________________________________ INSURANCE COMPANY:
_________________________________ ________________________________________
I certify (or declare) under penalty of perjury under the laws of the State of California that the foregoing is true and correct:
______________ _________________________________
Date CONTRACTOR'S SIGNATURE
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
34 of 244
27 BID SCHEDULE
To be completed through the City’s Electronic Bidding System (OpenGov Procurement)
Pursuant to and in compliance with the Notice Inviting Bids and other Contract Documents relating to the proposal for the construction of
TRAFFIC SIGNAL COMMUNICATIONS IMPROVEMENTS
as specifically set forth in documents entitled
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
all in accordance with the Plans and Project Specifications on file at the City of Vista Engineering Department, the undersigned bidder, having familiarized himself with the terms of the Contract, the local conditions affecting the performance of the Contract and the cost of the Work at the place the Work is to be done; and with the Plans, Project Specifications and other Contract Documents, hereby stipulated; the Contractor agrees to complete the Contract, including all of its component parts and everything required to be performed, and to provide and furnish any and all labor, materials, tools, equipment, expendable supplies and all utility and transportation services necessary to perform the Contract, and c omplete in a workmanlike manner all of the Work required in connection with the Contract, all in strict conformance with the Plans and Project Specifications on file at the City of Vista Engineering Department.
All items shall be finished and functional per Plans and the Contract Documents. Items designated with an ‘S’ in the Bid Item column of the Bid Schedule are Specialty Items per Subsection 3-2 (“SELF- PERFORMACE”) of the San Diego Regional Supplement to the Greenbook.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
35 of 244
28 BID SCHEDULE
(Provided for reference only)
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
TO BE COMPLETED THROUGH THE CITY’S ELECTRONIC OPENGOV PROCUREMENT BIDDING SYSTEM
NOTE 1: The Bid Schedule Worksheet is only provided as a reference for preparing the bid. Only the unit prices and totals entered in the OpenGov Procurement bidding system will be considered valid for purposes of the City’s bid evaluation. The low bidder bid schedule from OpenGov Procurement will be printed and inserted into the final contract documents.
Note 2: Unit prices shall prevail over extended total and grand total prices. Late bids will not be accepted.
The following “Description of Base Bid Items” is part of the Bid Schedule and shall be submitted with the bid.
Base Bid Items
Bid
Item Description Of Work Qty. Unit
1 Mobilization & Demobilization
(5% maximum of Total Base Bid) 1 LS
2 Project Information Sign 6 EA
3 Storm Water Pollution Prevention and Erosion
Control 1 LS
4 Traffic Control and Construction Staging 1 LS
5 Utility Potholing 1 LS
6 Record Drawing (“As-Built”) Plans (stipulated
amount) $1,500.00
7 Furnish and Install 12 Strand Single Mode Fiber
Optic Cable (SMFOC) 19,446 LF
8 Furnish and Install 6 Strand Single Mode Fiber
Optic Cable (SMFOC) 208 LF
9 Furnish and Install 24 Strand Single Mode Fiber
Optic Cable (SMFOC) 7,894 LF
10 Furnish and Install 3" HDPE Conduit 6,930 LF
11 Furnish and Install 2" Galvanized Steel Conduit 60 LF 12 Furnish and Install Tracer Wire 6,930 LF
13 Furnish and Install #6 Pull box with Extension 22 EA 14 Furnish and install 45-degree (3") HDPE conduit
bends in existing pull box or vault 3 EA
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
36 of 244
29 Bid
Item Description Of Work Qty. Unit
15 Locate existing city conduit, furnish and install a
#6 Pull box with extension over the conduit, and
including 45-degree bends for fiber optic cable
27 EA
16 Furnish and Install Fiber Optic Communication
Vault 12 EA
17 Furnish and Install Strand Splice Enclosure 11 EA
18 Furnish and Install Fiber Distribution Unit with 1U
Rack Mount Housing with Splice Cassette 10 EA
19 Connect to existing Switch with fiber ports and all
cables/ connectors 10 EA
20 Remove all radio equipment 6 EA
21 Sidewalk/ Concrete Repair 850 SF
22 Fiber Field Splices 1 LS
23 Fiber Testing, Documentation, and System and
Acceptance Testing. 1 LS
BID SCHEDULE WORKSHEET – END
(Provided for reference only)
BID SCHEDULE TO BE COMPLETED THROUGH THE CITY’S ELECTRONIC BIDDING SYSTEM (OPENGOV PROCUREMENT)
NOTE: Determination of the lowest bid shall be based solely on the lowest T OTAL BASE BID FOR IMPROVEMENTS. Unit prices shall prevail over extend ed total and grand total prices . Late bids will not be accepted.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
37 of 244
30 Description of Base Bid Items:
Bid Item 1 - Mobilization, Demobilization, Bonds & Insurance. (5% Maximum of Total Base Bid); Bid item shall include full compensation for all bonds, insurance, sureties, licenses, permits, facilities, labor, equipment and material necessary to complete all work required in advance of construction operations, and upon the initiation of construction operations, to mobilize all required equipment, materials and personnel on-site, and complete all associated and appurtenant work in acco rdance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The Bid Item shall also include all labor, equipment and material required to clean-up and restore the site, demobilize and remove all equipment, materials, and staging, and complete all work required at the end of construction operations in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Payment for this bid item is a lump sum (LS) price which shall not exceed 5% of the total contract price (5% maximum of Total Base Bid).
Bid Item 2 - Project Information Sign: Bid item shall include full compensation for work, labor, materials, and equipment to design, fabricate including anti -graffiti coating , install , move, maintain, and salvage project information signs. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 3 - Storm Water Pollution Prevention and Erosion Control : Bid item shall include full compensation for all labor, materials, and equipment required to complete all work necessary to maintain, repair and replace all temporary construction BMPs and associated work as required to ensure the project’s full compliance with State Water Resources Board’s General Construction Permit (Order No. 2009-0009-DWQ) and Section 3-12.6 of the Supplementary General Provisions. Bid item shall include all necessary labor, materials, and equipment and all other related costs for preparation, installation, adjustments, and removal shall be considered as included in the bid price. Payment for this bid item shall be at the lump sum (LS) price.
Bid Item 4 - Traffic Control and Construction Staging: Bid item shall include full compensation for all labor, materials, and equipment required to complete all work required to develop, submit, and obtain approved Traffic Control Plans with Encroachment Permit from the City of Vista Traffic Engineering Department; handle traffic (including flagging costs and person(s) to safely control pedestrian and vehicular traffic), furnish tools, equipment, and incidentals, and for performing all work involved in staging, constructing, furnishing, placing, removing, storing, maintaining, moving to new locations, replacing and disposing of the components of the traffic control system (including traffic control devices, temporary road resurfacing); installation and removal of all required temporary striping, and signing associated and appurtenant work as specified in the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Payment for this bid item shall be at the lump sum (LS) price.
Bid Item 5 - Utility Potholing: Bid item shall include full compensation for all coordination, labor, equipment and material required to locate, protect and restore all existing utilities and improvements which “may be affected” or “are affected” by the Work in accordance with the Stand ard Specifications, the Supplementary General Provisions of these Specifications, and as directed by the Engineer. The location, protection, and restoration of existing utilities and improvements (including street pavements, sidewalks and landscaping/irrigation), specifically identified for payment under other bid items shall not be included for payment within this bid item. All other location, protection and restoration required to complete the Work shall be incorporated into this bid item. Payment for this bid item shall be at the lump sum (LS) price.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
38 of 244
31 Bid Item 6 - Record Drawing (“As-Built”) Plans. (Stipulated Amount): Bid item shall include full compensation for all labor, materials, and equipment required to provide City with accurate “red line” plans showing the exact location of all improvements, particularly the location and depth of conduit runs and crossings, the locations of pull boxes and vaults , and other substructures , as-built splice/ communication diagrams, and existing utilities that have been modified as part of the Work. Payment for this item shall be included in the stipulated lump sum price listed in the bid schedule for this item of work.
Bid Item 7 - Furnish and Install 12 Strand Single Mode Fiber Optic Cable (SMFOC): Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install a new trunk, all dielectric, fully water-blocked, loose tube, gel -free, 12 Strand SMFOC, Coring 012ZU4 -T4F22D20 or approved equal, including coiling 50 feet of trunk 12-strand SMFOC slack in every pull box or vault which has sufficient space per the project plans and cable manufacturer’s allowable minimum bending radius. Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Bid Item 8 - Furnish and Install 6 Strand Single Mode Fiber Optic Cable (SMFOC ): Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install a new trunk, all dielectric, fully water -blocked, loose tube, gel -free, 6 Strand SMFOC, Coring 012ZU4 -T4F22D20 or approved equal.
Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Bid Item 9 – Furnish and Install 24 Strand Single Mode Fiber Optic Cable (SMFOC): Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install a new trunk, all dielectric, fully water-blocked, loose tube, gel -free, 24 Strand SMFOC, Coring 012ZU4 -T4F22D20 or approved equal, including coiling 50 feet of trunk 24-strand SMFOC slack in every pull box or vault which has sufficient space per the project plans (unless stated otherwise) and cable manufacturer’s allowable minimum bending radius.
Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Bid Item 10 – Furnish and Install 3” HDPE Conduit : Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install 3” HDPE conduit to a depth of 30” using directional boring, unless otherwise specified for trenching, for fiber optic cable per the project plans. This bid item shall include removals of asphalt concrete and subgrade material necessary for conduit installation including bore pits for directional drilling , backfill, compaction, asphalt concrete pavement resurfacing per City standard drawings and requirements, and other incidentals required for the completion of this bid item in its entirety .
Payment for this item shall be based on the actual quantity, Linear Feet (LF). There shall be no further compensation for this item.
Bid Item 11 – Furnish and Install 2” Galvanized Steel Conduit: Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install 2” galvanized steel conduit into existing controller cabinets for fiber optic cable as shown on the project plans. Payment for this bid item shall be based on the actual quantity, Linear Feet (LF). Concrete/ sidewalk repairs associated with this item which include the removal of concrete and subgrade material for this conduit installation, backfill, and compaction per City standard drawings and requirements will be paid from a separate bid item and are not included for payment within this bid item
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
39 of 244
32 Bid Item 12 – Furnish and Install Tracer Wire: Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install THWN coated No. 8 AWG tracer wire inside fiber optic interconnect conduits, including demonstration and documentation of proper tracer wire operation prior to acceptance (Ex. Advantage Digital Cable (ADC) XHHW -2 power cable, green in color ). No tracer wire splices are permitted between pull boxes. Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Bid Item 13 – Furnish and Install #6 Pull box with Extension: Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install No. 6 pull box (with extension) with 45-degree bends for fiber optic cable. No.6 pull boxes with extension shall be spaced no more than 500 feet apart.
Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 14 – Furnish and install 45 -degree (3") HDPE conduit bends in existing pull box or vault : Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install furnish and install 45-degree (3") HDPE conduit bends in existing pull boxes or vault for fiber optic cable. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 15 – Locate existing city conduit, furnish and install a #6 Pull box with extension over the conduit, and including 45 -degree bends for fiber optic cable : Bid item shall include full compensation for all labor, materials, and equipment required to locate existing city conduit, furnish and install a #6 pull box with extension over the existing conduit, furnish and install 45-degree conduit bends for fiber optic cable per the project plans. Per the project plans locations with existing pull boxes will be removed, disposed, and replaced with new #6 pull box with extension. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 16 – Furnish and Install Fiber Optic Communication Vault : Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install fiber optic splice vault for fiber optic cable per the project plans including base layer, grounding rods, lifting rings and bolts, and vault cover with required markings and finishes. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 17 – Furnish and Install Strand Splice Enclosure: Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install Corning splice enclosure, models SCF -4C-18-01 (or City approved equal) per the project plans. It shall have a minimum 48-fiber splice capability; provide cable ports as required; have a moisture -tight sealing arrangement; and have re -entry capability. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 18 –Furnish and Install Fiber Distribution Unit with 1U Rack Mount Housing with Splice Cassette: Bid item shall include full compensation for all labor, materials, and equipment required to furnish and install Corning fiber optic distribution unity with 1U rack mount housing, and splice cassette including all jumpers, CAT 6 ethernet patch cables, data cables, and all appurtenances necessary for communications per the project plans. Payment for this bid item shall be at the contract price per Each (EA).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
40 of 244
33 Bid Item 19 – Connect to existing Switch with fiber ports and all cables/connectors: Bid item shall include full compensation for all labor, materials, and equipment required to connect to existing layer 2 or 3 ethernet switch with 2-dual fiber/ transceiver ports including all cables, connectors, and auxiliary equipment necessary to establish communication to all network capable devices per the project plans. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 20 – Remove all radio equipment: Bid item shall include full compensation for all labor, materials, and equipment required to remove and salvage existing radio equipment including cabling and deliver to the City per the project plans. Payment for this bid item shall be at the contract price per Each (EA).
Bid Item 21 – Sidewalk/ Concrete Repair: Bid item shall include full compensation for all labor, materials, and equipment required to remove, dispose, and replace PCC s idewalk/concrete improvements including associated backfill and compaction required to complete the wor k for pull box, fiber optic vault, and rigid conduit installation per SDRSD G-07, G-09, G-10 and G -11 in accordance with the Standard Specifications, the Supplementary General Provisions, the Supplementary Technical Provisions, and as directed by the Engineer. Concrete sidewalks near controller cabinets that are in conflict with proposed conduit routing and impracticable to bore or tunnel under, unless specified otherwise, shall be removed and replaced between expansion joints (In complete/ whole panels), and no t saw cut through slab. Concrete class shall be 560 -C- 3250. Concrete/ sidewalk replacement associated with utility potholing will be paid under that bid item lump sum price, and shall not be included for payment within this bid item. Payment for this item shall be based on the actual quantity, Square Foot (SF).
Bid Item 2 2 – Field Fiber Splices: Bid item shall include full compensation for all labor, materials, and equipment required to perform necessary splicing of the 12 -strand and/ or 24-strand trunk fiber cable with the 6 -strand fiber cable per the splice details on the p roject plans, not including the cost for the splice enclosures which are a separate bid item. All remaining unused fiber strands in the trunk cable must remain intact and if cut, must be rejoined by splicing. Payment for this bid item shall be at the lump sum (LS) price.
Bid Item 23 – Fiber Testing, Documentation, and System and Acceptance Testing: Bid item shall include full compensation for all labor, materials, and equipment required to test the fiber optic cable installed, spliced, and terminated as part of the project including system acceptance testing. This item includes pre-installation and post installation testing of the cable , conducting acceptance tests and subsequent re -tests, and documentation of the test results which must be provided as a condition of project acceptance. The City shall approve the test results before final acceptance. Payment for this bid item shall be at the lump sum (LS) price.
--END OF BID SCHEDULE--
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
41 of 244
34 CONTRACTOR'S LICENSING STATEMENT
The undersigned is licensed in accordance with the laws of the State of California providing for the registration of Contractors.
Contractor's License Number: _________________________________________________________________
Contractor's License Class: _________________________________________________________________
Expiration Date: _________________________________________________________________
(As described in the INSTRUCTIONS FOR SIGNING BIDS, BONDS AND CONTRACTS, complete and sign the appropriate section for your company)
Name of Individual Contractor (Print or type): ____________________________________________________
Signature of Contractor: _________________________________________________________________
Business Address: _________________________________________________________________
or
Name of Partnership or Joint Venture Firm: ____________________________________________________
Business Address: ________________________________________________________________________
Signature, printed name, title and address of members signing on behalf of the partnership:
Signature: _____________________ Name: ______________________ Title: ______________________
Address: _________________________________________________________________________________
Signature: _____________________ Name: ______________________ Title: ______________________
Address: _________________________________________________________________________________
or
Name of Corporation: ________________________________________________________________________
Business Address: ________________________________________________________________________
Corporation organized under the laws of the State of _____________________________________________
_______________________________________ __________________________________________ Signature of Officer of Corporation Printed Name and Title
_______________________________________ __________________________________________ Signature of Officer of Corporation Printed Name and Title
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
42 of 244
35 PROJECT REFERENCES
The Bidder shall provide evidence that the Bidder has had the prior experience to properly perform in accordance with the terms of these Plans and Project Specifications.
List ALL contracts with public agencies entered within the past five (5) years of the most recent projects for which the Bidder has completed work of similar size and complexity to this project as the General (or Prime) Contractor, and the names and phone numbers of the contracting public agencies. Make copies of this page for listing additional projects.
Project
No. Date Completed Public Agency Name,
Contact Person & Phone
Project Name and Description of
Work Contract Amount
1. 2.
3. 4.
5. 6.
7. Note: Attached pre-printed list to this page to list additional projects.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
43 of 244
36 CONTRACTOR’S LIST OF SUBCONTRACTORS
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
NAME OF BIDDER: ______________________________________________________________________________
In accordance with Division 2, Part 1, Chapter 4 of the Public Contract Code, the prime Contractor shall submit with its Bid a list of subcontractors who will perform work in excess of one -half of one percent (0.5%) of the prime Contractor’s total Bid or $10,000, whichever is greater.
Subcontractors listed must be properly licensed for the type of work they are to perform, and their license numbers must be indicated below. Do not list alternate subcontractors for the same work.
Name under which
Subcontractor is licensed
License No.
and Class
Address of Office,
Mill or Shop
DBE
(Yes/No)
Bid
Item
No(s).
Description of
Subcontractor’s
Portion of Work
Dollar Value
of
Subcontract
(Provide additional copies of this sheet if needed)
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
44 of 244
37 NON-COLLUSION DECLARATION
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
The undersigned declares:
I am the __________________ of _________________________________, the party making the foregoing bid. (Title) (Company Name)
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited a ny other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organi zation, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on
________________________, at ________________________________, ___________________________.” (Date) (City) (State)
________________________________________
Signature
________________________________________
Printed Name
________________________________________
Title
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
45 of 244
38 BID SECURITY FORM
(For Cash or Checks)
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
Note: This form is to be used when the Bidder chooses to submit cash or a check instead of a bid bond as bid security. Cash or a cashier’s or certified check in the amount of not less than ten percent (10%) of the total Base Bid must accompany the bid.
KNOW ALL PERSONS BY THESE PRESENTS that:
WHEREAS the City of Vista (“Agency”) has issued an invitation for bids for the work described as follows:
Work Description.
WHEREAS
(Name, address, and telephone number of Bidder)
the undersigned bidder (“Bidder”), has submitted the accompanying bid to Agency for the work.
WHEREAS, bidders are required under the provisions of the Vista Municipal Code to furnish a form of bidder’s security with their bid.
NOW, THEREFORE, the undersigned Bidder, is held and firmly bound unto Agency in the penal sum not less than ten percent (10%) of the total base bid amount, in lawful money of the United States of America in the form of *Cash, *a Certified Check, *a Cashier’s Check (* Strike out the inapplicable words) for the payment of which sum we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the Bidder shall not withdraw said bid within the period specified in the bidding specification, or, if no period be specified, for ninety (90) calendar days after the bid opening; or if the Bidder does not attempt to withdraw the bid when the requirements of Public Contract Code §5101 et seq. are not met; or if the Bidder is awarded a contract for the work by Agency and, within the time and in the manner required by the bidding specification , or if no peri od be specified, within ten (10) working days after the Contract is awarded, enters into the written form of contract included with bidding specification, furnishes the required bonds, one to guarantee faithful performance and the other to guarantee payment for labor and materials, and furnishes the required insurance coverages, then this obligation shall become null and void and the cash or check shall be returned to Bidder; otherwise, the proceeds of the cash or check shall become the property of the Agency and the Bidder shall have no further interest therein. [Text and signatures continued on page 2.]
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
46 of 244
39 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
In case suit is brought against the Bidder based on this obligation, Bidder further agrees to pay all court costs incurred by Agency in the suit and reasonable attorneys’ fees in an amount fixed by the court.
IN WITNESS WHEREOF, this instrument has been duly executed by Bidder on the date set forth below, the name of each corporate officer being hereto affixed, and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
Bidder
By:
Its
By:
Its
(Seal)
This form must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
47 of 244
40 BID SECURITY FORM
Bond No.:
BID BOND
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
KNOW ALL PERSONS BY THESE PRESENTS that:
The City of Vista (“City”) has issued an invitation for bids for the work described as follows:
Work Description.
(Name, address, and telephone number of Bidder)
the undersigned bidder (“Principal”), has submitted the accompanying bid to City for the work.
Bidders are required under the provisions of the Contract to furnish a form of bidder’s security with their bid.
NOW, THEREFORE, we, the undersigned Principal, and
(Name, address, and telephone number of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto City in the penal sum not less than ten percent (10%) of the total base bid amount, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal shall not withdraw said bid within the period specified in the bidding specification, or, if no period be specified, for ninety (90) calendar days after the bid opening; or if the Principal does not attempt to withdraw the bid when the requirements of Public Contract Code §5101 et seq. are not met; or if the Principal is awarded a contract for the work by City and, within the time and in the manner required by the bidding specification , or if no period be specified, within ten (10) working days after the Contract is awarded, enters into the written form of contract included with bidding specification, furnishes the required bonds, one to guarantee faithful performance and the other to guarantee payment for labor and materials, and furnishes the required insurance coverages, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect.
In case suit is brought upon this bond, Surety further agrees to pay all court costs incurred by City in the suit and reasonable attorneys’ fees in an amount fixed by the court.
Surety, for value received, hereby stipulates and agrees that no change, extension of time for award of a contract after opening of bids, alteration, addition, modification, or supplement to the terms of the bidding documents, the work to be performed thereunder, or the Contract Documents shall in any way affect Surety’s obligations under this Bond, and Surety does hereby waive notice of any such change, extension of time, alteration, addition, modification or supplement to the terms of said Bidding Documen ts, the Work to be performed thereunder, or the Contract Documents. Surety hereby waives the provisions of California Civil Code §§ 2819, 2845, and 2849. City is an intended beneficiary of this bond and has all rights of a party thereto. [Text and signatures continued on page 2.]
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
48 of 244
41 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
IN WITNESS WHEREOF, this instrument has been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed, and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
“Principal”
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
“`Surety”
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
This bond must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
49 of 244
42 CONSTRUCTION CONTRACT
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
THIS CONTRACT is made and entered into as of _____________________________ (“Contract Date”), by and between the City of Vista, a chartered municipal corporation (“Agency”), and Namex, status (“Contractor”). Agency and Contractor are sometimes individually referred to as a “Party” and collectively as “Parties.”
In consideration of the mutual covenants contained herein, Agency and Contractor agree as follows:
SECTION 1
The Contract Documents consisting of the PROJECT SPECIFICATIONS, comprised of the NOTICE INVITING BIDS, the INSTRUCTIONS TO BIDDERS, the accepted BID PROPOSAL; BID SCHEDULE; CONTRACTOR’S LICENSING STATEMENT; PROJECT REFERENCES; CONTRACTOR’S LIST OF SUBCONTRACTORS;; PUBLIC CONTRACT CODE STATEMENTS AND QUESTIONNAIRE; NON- COLLUSION AFFIDAVITS; the CONSTRUCTION CONTRACT, CONTRACTOR’S CERTIFICATE,
SUPPLEMENTARY GENERAL PROVISIONS, SUPPLEMENTARY TECHNICAL PROVISIONS, Special Provisions, Plans, Standard Plans and Specifications; together with all additions, deletions, modifications, appendices, and all addenda (No. ?), as prepared prior to the date of bid opening setting forth any modifications or interpretations of any said documents, are hereby incorporated in and made a part of this Contract as fully as if set forth herein.
SECTION 2
For and in consideration of the payments and agreements to be made and performed by the Agency as set forth in said Contract Documents, the Contractor agrees with the Agency to construct
TRAFFIC SIGNAL COMMUNICATIONS IMPROVEMENTS
as specifically set forth in documents entitled
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
for which award of the Contract was made, to furnish at his own proper cost and expense all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, and to do everything required therein. In accordance with the provisions of Section 3700 of the Labor Code, the Contractor will be required to secure the payment of Worker’s Compensation Insurance for its employees.
SECTION 3
For furnishing all said services and materials, payment of premiums on insurance policies, obtaining all permits and licenses of a temporary nature, furnishing and removing all plant, temporary work or structures, tools, and equipment, and for doing all the Work contemplated and embraced in this Contract, also for all loss and damage arising out of the nature of the aforesaid work during its progress Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
50 of 244
43 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
or prior to acceptance from the action of the elements and from any unforeseen difficulties which may arise or be encountered in the prosecution of the Work, and for all other risks of any description
connected with the Work, also for all expenses incurred by or in consequence of the suspension or discontinuance of work, except such as in the said Contract Documents are expressly stipulated to be borne by the Agency, and for well and faithfully completing the Work and the whole thereof within the stipulated time and in the manner shown and described in the said documents, and in accordance with the requirements of the Engineer under them, the Agency will pay, and the Contractor shall receive in full compensation therefore, the prices set forth by him in the accepted bid. The total compensation will be computed on the basis of the units of work actually performed in accordance with the requirements of the Contract Documents and paid for at the stipulated prices named in the BID SCHEDULE for completion of the Work.
SECTION 4
The Agency hereby promises and agrees with the said Contractor to employ, and does hereby employ the said Contractor to provide the materials and to do the Work according to the terms and conditions herein contained and referred to, for the price aforesaid, and hereby contracts to pay the same at the time, in the manner, and upon the conditions set forth in the Contract Documents, and the Parties for themselves, their heirs, executors, administrators, successors and assigns do hereby agree to the full performance of the covenants herein contained.
SECTION 5
Contractor agrees to indemnify, defend, and save harmless, the Agency, its officers, agents, employees and volunteers from and against any and all claims, demands, damages, losses and expenses, defense costs including attorney fees, or liability of any kind or nature which the Agency, its officers, agents and employees may sustain or incur or which may be imposed upon them for injury to or death of persons, or damage to property as a result of, arising out of, or in any manner connected with the Contractor’s performance under the terms of this Contract, caused in whole or in part by any negligent or willful acts or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, except where caused by the active negligence, sole negligence, or willful misconduct of the Agency.
[Continued on page 3.]
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
51 of 244
44 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
SECTION 6
Contractor agrees that the Payment Bond and Performance Bond attached to/submitted concurrently with this Contract are for reference purposes only, and shall not be considered a part of this Contract.
Contractor further agrees that said bonds are separate obligations of the Contractor and its surety, and that any attorneys’ fee provision contained in any payment bond or performance bond shall not apply to this Contract. In the event there is any litigation between the Parties arising from the breach of this Contract, each Party will bear its own attorneys’ fees in the litigation.
IN WITNESS WHEREOF, the Parties have caused this Contract to be executed as of the Contract Date.
CITY OF VISTA, a chartered municipal
corporation
By:
JOHN B. FRANKLIN, MAYOR
ATTEST:
KATHY VALDEZ, CITY CLERK
By:
APPROVED AS TO FORM:
WALTER CHUNG, CITY ATTORNEY
By:
RISK MANAGEMENT REVIEW:
ANALISA HOLBROOK, RISK MANAGER
By:
NAMEX, status
By:
Name/Title
By:
Name/Title
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
52 of 244
45 Bond No.
Premium: $
Effective Date:
PERFORMANCE BOND
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
KNOW ALL PERSONS BY THESE PRESENTS that:
The City of Vista (“City”) has awarded a contract (the “Contract”) with ThePrincipal (“Principal”) as follows:
Contract Title,
which Contract, and all Contract Documents set forth therein, are incorporated herein and made a part thereof by this reference.
Principal is required under the terms of the Contract to furnish a bond guaranteeing the prompt, full, and faithful performance of the Contract concurrently with delivery of the signed Contract to City.
NOW, THEREFORE, we, the undersigned Principal, and
,
(Name, address, and telephone number of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto City in the penal sum of Amount Dollars ($xxx), this amount being not less than one hundred percent (100%) the total contract price, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, succes sors, and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal, his, her or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform all the undertakings, te rms, covenants, conditions and agreements in the Contract and any alteration thereof made as therein provided, on Principal’s part to be kept and performed, all within the time and in the manner therein specified, and in all respects according to their tru e intent and meaning, and shall indemnify and hold harmless City and its officers, agents, and others as therein provided, from any and all losses, liability and damages, claims, judgments, stop payment notices, costs, and fees of every description, whether imposed by law or equity, which may be incurred by City by reason of the failure or default on the part of Principal in t he performance of any or all of the terms or the obligations of the Contract Documents, as they may be amended and supplemented including, but not limited to, Principal’s liability for City’s damages (including direct and consequential damages incurred by City for: rental expenses; losses of use, income, profit, business, and reputation; increased financing costs; and loss of management or employee productivity or of the services of such persons) caused by Principal’s delays, as well as Principal’s liability for other delay damages or liquidated damages, and any warranties or guarantees required thereunder; then this obligation shall bec ome null and void; otherwise, it shall be and remain in full force and effect.
When City declares that Principal is in default under the Contract, Surety shall promptly, take one of the following actions:
(a) Remedy the default;
(b) Undertake through its agents or independent contractors reasonably acceptable to City, to complete the Project according to the Contract Documents’ terms and conditions then in effect including without limitation, all obligations with respect to warranties, guarantees, and the payment of liquidated damages; or, if required by City; Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
53 of 244
46 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
(c) Obtain a bid or bids for completing the Contract in accordance with its terms and conditions using a procurement methodology approved by City, select a contractor or contractors — acceptable to City — to complete all of the Work, and arrange for a contract between the contractor(s) and City, to be secured with performance and payment bonds executed by an admitted surety insurer equivalent to the bonds issued on the Construction Contract, and Surety shall make available, as the Work progresses, sufficient funds to pay the cost of completion less the balance of the Contract Sum, and to pay and perform all obligations of Principal under the Contract and Contract Documents, including other costs and damages for which Surety is liable under this Bond and all obligations with respect to warranties, guarantees, and the payment of liquidated damages as a result of Contractor’s default; (d) Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
(i) After investigation, determine the amount for which it may be liable to City and, as soon as practicable after the amount is determined, make payment to City; or (ii) Deny liability in whole or in part and notify City, citing the reasons for denial.
If Surety does not proceed as provided above with reasonable promptness, Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from City to Surety demanding that Surety perform its obligations under this Bond, and City shall be entitled to enforce any remedy available to City. If Surety admits liability and tenders payment, and City refuses the payment, or Surety has denied liability, in whole or in part, without further notice City shall be entitled to enforce any remedy available to City.
In case suit is brought upon this bond, Surety further agrees to pay all court costs and reasonable attorneys’ fees in an amount fixed by the court. Principal and Surety agree that this Performance Bond shall not be considered a part of the Contract but r ather is a separate obligation of Principal and its Surety, and that any attorneys’ fee provision contained in this Performance Bond shall not apply to the Contract. In the event there is any litigation between the parties arising from the breach of the Co ntract, each party will bear its own attorneys’ fees in the litigation.
FURTHER, Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, addition or modification to the terms of the Contract, or of the work to be performed thereunder, or the specifications for the same, shall in any way affect its obligations under this bond, and it does hereby waive notice of any such change, extension of time, alteration, addition, or modification to the terms of the Contract or to the work or to the specifications thereunder. Surety hereby waiv es the provisions of California Civil Code §§ 2819, 2845, and 2849.
City is an intended beneficiary of this bond and has all rights of a party thereto. [Text and signatures continued on page 3.]
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
54 of 244
47 PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed an original hereof, have been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being h ereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
“Principal”
THEPRINCIPAL
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
“`Surety”
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
This bond must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
55 of 244
48 Bond No.
Premium: $
Effective Date:
PAYMENT BOND
(LABOR AND MATERIALS)
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
KNOW ALL PERSONS BY THESE PRESENTS that:
The City of Vista (“City”) has awarded a contract (the “Contract”) to ThePrincipal (“Principal”) as follows:
Contract Title,
which Contract, and all Contract Documents set forth therein, are incorporated herein and made a part thereof by this reference.
Principal is required under the terms of the Contract and the California Civil Code to furnish a bond to secure the prompt, full, and faithful payment of any Claimant, as hereinafter defined, for all labor, materials or services used or reasonably required for use in the performance of the work, concurrently with delivery to City of the signed Contract.
NOW, THEREFORE, we, the undersigned Principal, and
,
(Name, address, and telephone number of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto City in the penal sum of Amount Dollars ($xxx), this amount being not less than one hundred percent (100%) of the total contract price, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, suc cessors, and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal, his, her or its heirs, executors, administrators, successors or assigns, or subcontractors shall fail to pay any of the persons named in Division 4, Part 6, Title 3 of the California Civil Code (§ 9000 et seq.), or any amounts due under the Unemployment Insurance Code with respect to work or labor performed under the Contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Depar tment from the wages of employees of Principal and subcontractors pursuant to Section 13020 of the Unemployment Insurance Code, with respect to work or labor performed under the Contract (“Claimants”), Surety will pay for the same in an amount not exceedin g the penal sum specified in this bond; otherwise, this obligation shall become null and void.
This bond shall inure to the benefit of any of the persons named in Division 4, Part 6, Title 3 of the California Civil Code (§ 9000 et seq.), so as to give a right of action to such persons or their assigns in any suit brought upon the bond.
In case suit is brought upon this bond to enforce or interpret this bond’s terms, Surety further agrees to pay all court costs and reasonable attorneys’ fees in an amount fixed by the court. Principal and Surety agree that this Performance Bond shall not be considered a part of the Contract but rather is a separate obligation of Principal and its Surety, and that any attorneys’ fee provision contained in this Performance Bond shall not apply to the Contract.
In the event there is any litigation between the parties arising from the breach of the Contract, each party will bear its own attorneys’ fees in the litigation.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
56 of 244
49 FURTHER, Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, addition or modification to the terms of the Contract, or of the work to be performed thereunder, or the specifications for the same, shall in any way affect its obligations under this bond, and it does hereby waive notice of any such change, extension of time, alteration, addition, or modification to the terms of the Contract or to the work or to the specifications thereunder. Surety hereby waives the provisions of California Civil Code §§ 2819, 2845, and 2849.
City is an intended beneficiary of this bond and has all rights of a party thereto.
IN WITNESS WHEREOF, this instrument has been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
“Principal”
THEPRINCIPAL
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
“`Surety”
By:
Signature
Name and Title
By:
Signature
Name and Title
(Seal)
This bond must be dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
57 of 244
50 CONTRACTOR'S CERTIFICATE
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
CONTRACTOR'S CERTIFICATE PURSUANT TO
SECTION 1861 OF THE LABOR CODE
I am aware of the provisions of Section 3700 of the Labor Code that requires every employer to be insured against liability for Worker's Compensation or to undertake self-insurance in accordance with the provisions of that Code, and I will comply with such provisions before commencing the performance of the Work of this Contract.
___________________________________
Name of Contractor
By: ________________________________
Signature
___________________________________
Printed Name
___________________________________
Title
___________________________________
Date
By: ________________________________
Signature
___________________________________
Printed Name
___________________________________
Title
___________________________________
Date
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
58 of 244
51 NON-COLLUSION DECLARATION FOR SUBCONTRACTORS
TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
TO BE EXECUTED BY EACH AWARDEE OF A SUBCONTRACT
The undersigned declares:
I am the __________________ of _________________________________, the party making the foregoing bid. (Title) (Company Name)
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited a ny other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organi zation, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and do es execute, this declaration on behalf of the bidder. The provisions of this declaration shall not be held as disqualifying a person, firm or corporation who has submitted a sub-proposal to one bidder from submitting separate sub-proposals or quoting prices for materials or work to other bidders.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on
________________________, at ________________________________, ___________________________.” (Date) (City) (State)
________________________________________
Signature
________________________________________
Printed Name
________________________________________
Title
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
59 of 244
52 SUPPLEMENTARY GENERAL PROVISIONS
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
This section makes additions, deletions, or revisions to PART 1 – GENERAL PROVISIONS of the 2024 Standard Specifications for Public Works Construction (“Greenbook”) . All sections and subsections which are not changed remain in full force and effect.
SECTION 1 – GENERAL, TERMS, DEFINITIONS,
ABBREVIATIONS, UNITS OF MEASURE AND SYMBOLS
1-1 GENERAL.
Add the following paragraphs to this subsection:
The terms “as shown,” “as indicated,” or “as specified” are understood to be followed by the phrase “in the Contract Documents.”
Working titles having a masculine gender, such as “workman” and “journeyman” and the pronoun “he,” are used in the Specifications for the sake of brevity, and are intended to refer to persons of either gender.
1-2 TERMS AND DEFINITIONS.
Modify the following terms and definitions to read as follows:
Agency or City or Owner - The legal entity for which the Work is being performed, either the City of Vista, the Vista Community Development Commission, or the Buena Sanitation District.
Board – Where the word Board appears in the Standard Specifications, it shall mean t he officer or body constituting the awarding authority of the Agency, either the City Council of the City of Vista, the Commission of the Vista Community Development Commission, or the Board of the Buena Sanitation District.
Special Provisions - Means the Supplementary General Provisions and Technical Provisions of the Project Specifications.
Standard Plans or Standard Drawings - Means the most recent editions of the Standard Drawings of the City of Vista and the San Diego Regional Standard Drawings (SDRSD), unless otherwise noted.
The City of Vista Standard Drawings takes precedence over the San Diego Regional Standard Drawings.
Specifications or Standard Specifications - The Standard Specifications of the Agency are the latest edition of the Standard Specifications for Public Works Construction (“Greenbook”), as written and Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
60 of 244
53 promulgated by Public Works Standards, Inc., together with the most current Cumulative Supplement adopted by the Greenbook Committee of Public Works Standards, Inc. and along with the latest San Diego Regional Supplement to “Greenbook” as approved and adop ted by the San Diego Regional Standards Committee.
The Standard Specifications set forth above will control the general provisions, construction materials, and construction methods for this contract, except as amended by the Plans , Special Provisions, or other Contract D ocuments. The Special Provisions are supplemental to the provisions of the Standard Specifications, unless otherwise noted. O nly those sections requiring elaborations, amendments specifying options, additions or deletions are called out.
Working Day - Modify c) as follows:
The Agency recognizes ten (10) holidays on which no work is to be scheduled, as follows:
HOLIDAY OBSERVED ON
New Year’s Day January 1
Martin Luther Day, Jr. Day 3rd Monday in January
President’s Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1st Monday in September
Veteran’s Day November 11
Thanksgiving Day 4th Thursday in November
The day after Thanksgiving Friday after 4th Thursday in November Christmas Day December 25
Add the following new terms and definitions to this subsection:
Acceptance – Formal action of the Agency in determining that the Contactor’s Work has been completed in accordance with the Contract, filing a Notice of Completion with the County Recorder, which stipulates that date that the Work was completed, and notifying the Contractor in writing of the acceptability of the Work.
Award of Contract (Award) – Date of – Date on which the Mayor or designee executes the Contract.
ASTM Designations – The latest revised Specifications or tentative Specifications of the American Society for Testing and Materials.
Best Management Practices (BMPs) – (a) A measure implemented to protect water quality and reduce the potential for pollution (associated with storm water runoff); (b) Any program, technology, process, siting criteria, operating method, measure, or device that controls, prevents, removes, or reduce pollution.
CA MUTCD – California Manual on Uniform Traffic Control Devices.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
61 of 244
54 Disadvantaged Business Enterprise (DBE) - A for-profit “small business concern” that is at least fifty- one percent (51%) owned and controlled by one or more socially and economically disadvantaged individuals certified by the California Department of Transportation (Caltrans).
Inspector – The engineering or technical personnel authorized to act as agents for the Engineer in the supervision of work covered by these Specifications, limited to the particular duties entrusted to them.
Main or Trunkline Facility - An Owner owned and maintained principal subsurface conduit that collects sewage or storm drainage, or distributes potable water.
Material and Labor Bond - The Payment Bond as defined in the Civil Code of California relating to Payment Bond for Public Works.
Notice of Completion (NOC) – A document the Agency will file with the County Recorder, if in the Agency’s judgment, the Work has been completed. NOC stipulates the date that the Engineer accepted the Work. See California Civil Code section 3093.
Portable Emissions Unit - Any type of portable equipment which may discharge air contaminants into the atmosphere as stated in the San Diego County Air Pollution Control District Rules and Regulations.
Project - Means the total construction of all improvements located on the Site identified in the plan drawings and contractual documents.
Project Specifications - Comprised of the Notice Inviting Bids, the Instructions to Bidders, the BID documents, the Contract Documents, the Special Provisions, which include the Supplementary General Provisions and the Technical Provisions, permits issued by jurisdictional regulatory agencies, all appendices, the Standard Specifications, and all reference Specifications.
Punchlist – List of incomplete items of Work and of items of Work that are not in conformance with the Contract.
1-3 ABBREVATIONS.
1-3.2 Common Usage.
Add the following abbreviations to this subsection:
AC .................... ............ ............ Asphalt Concrete AT&T ................ ............ ............ Local and long distance telephone company (formerly SBC and Pacific Bell)
CGP ................. ............ ............ Construction General Permit LUP .................. ............ ............ Linear Underground / Overhead Project NCTD ............... ............ ............ North County Transit District OSHA ............... ............ ............ Occupational Safety and Health Administration (Department of Labor) PCR ................. ............ ............ Point of curb return Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
62 of 244
55 SWMP ............. ............ ............ Storm Water Management Plan VID................... ............ ............ Vista Irrigation District WPCP .............. ............ ............ Water Pollution Control Plan WDID ............... ............ ............ Waste Discharge Identification Number
1-3.3 Institutions.
Add the following institutions to this subsection:
APWA ............... ............ ............ American Public Works Association SDRWQCB ....... ............ ............ California Regional Water Quality Control Board, San Diego Region
1-7 AWARD AND EXECUTION OF CONTRACT.
Modify this subsection to read as follows:
1-7 AWARD AND EXECUTION OF CONTRACT. Award and Execution of Contract shall be as provided for in the Project Specifications, Notice Inviting Bids, Instructions to Bidders, or the Specifications.
For proj ects with a value of $ 150,000 and less, the City Manager is authorized to award the Contract and the Agency will send a “Notice of Intent to Award” to the Contractor accepting the Bidder’s proposal. Within ten (10) Working Days of the date of this notification, the Contractor shall submit the completed “Agreement and Bonds” portion of the Contract and the insurance certificates. The City Manager will then execute the Contract for the Agency.
For projects with a value greater than $ 150,000, the City Council will award the Contract. The Agency will send a “Notice of Intent to Award” to the Contractor. Within ten (10) Working Days of the date of this notice, the Contractor shall submit the completed “Agreement and Bonds” portion of the Contract and the insurance certificates. After the City Council approves the Contract, t he Mayor will execute the Contract for the Agency.
1-7.3 Integration.
Add the following new subsection:
1-7.3 Integration. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.
1-7.4 Change in Name and Nature of Contactor’s Legal Entity.
Add the following new subsection:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
63 of 244
56 1-7.4 Change in Name and Nature of Contactor’s Legal Entity. Should a change be contemplated in the name or nature of the Contractor’s legal entity, the Contractor shall first notify the Agency in order that proper steps may be taken to have the change reflected on the Contract.
SECTION 2 – SCOPE OF THE WORK
2-1 WORK TO BE DONE.
Add the following paragraphs to this subsection:
The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention.
The Contractor shall be solely responsible for all construction means, methods, techniques, sequences and procedures relating to the Work, and shall coordinate all portions of the Work under the contract, including the relations of the various trades to the progress of the Work, in accordance with these provisions.
The Contractor shall be responsible to the A gency for the acts and omissions of the Contractor’s employees, subcontractors and their agents and employees, and any other persons performing any of the Work under a Contract with the Contractor.
Any plan or method suggested to the Contractor by the Engineer but not specified or required, if adopted or followed in whole or in part, shall be used at the risk and responsibility of the Contractor; and the City and the Engineer will assume no responsibility therefore.
Nothing in these specifications shall be interpreted to make the Contractor an agent of the Agency.
Unless otherwise provided in these specifications, the Contractor shall provide and pay for furnishing all labor, materials, equipment, tools, implements, construction equipment and machinery, methods or processes, water, heat, utilities, transportation, and other facilities , services and incidentals necessary for the proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. Contractor shall leave the construction site in a neat, clean, and orderly condition upon completion of the Work.
2-2 PERMITS.
Add the following paragraphs to this subsection:
The issuance of a permit based on Plans, specifications, and other data shall not prevent the Agency from ordering correction of errors in said Plans, specifications, or other data, or from preventing construction operations being carried on hereunder when in violation of any law, code or ordinance.
The Contractor shall submit to the Engineer for review and approval a completed City of Vista Storm Water Management Permit application (see Appendices or contact the Agency for forms and instructions). As part of the permit application, the Contractor must submit a Storm Water Pollution Prevention Plan (SWPPP) (if required) to the Engineer for review and acceptance as required by the Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
64 of 244
57 Regional Water Quality Control Board. The Contractor shall comply with all provisions of the permit throughout the course of the Work. The permit must be approved by the Engineer prior to starting work. The Contractor shall include all costs for obtaining and complying with the requirements of the permit in the various items of work, and no additional compensation will be paid.
Compliance with the provisions of this section shall be considered as included in the various Contract items of work to which such regulations are applicable and no additional compensation shall be allowed therefore. Further, the enforcement of any requirements of the permits required during the performance of the Contract work shall not be made the basis for additional compensation.
If the Contractor is required to obtain permit(s) from other agency (agencies) to complete the Work in accordance with the Drawings and Project Specifications, the Agency will compensate the Contractor for the actual cost of the permit fee unless otherwise specified that the Contractor is responsible to pay the fee. The Contractor shall include all other costs associated with obtaining permits in various bid items for which the permit is required, and no additional compensation will be paid.
2-2.1 City of Vista Business License.
Add the following new subsection:
2-2.1 City of Vista Business License. A City of Vista Business License is required of the Contractor and all his/her Subcontractors prior to execution of the Contract . A fee will be charged for any new Business Licenses or renewal of any expired Business Licenses.
2-2.2 City of Vista No-Fee Construction Permit.
Add the following new subsection:
2-2.2 City of Vista No -Fee Construction Permit. After execution of the Contract and prior to beginning work, the Contractor shall apply for and obtain a no-fee Construction Permit from the Agency.
Prior to applying for the permit, the Contractor shall first submit the following documents to the Engineer with proof that the policies / licenses are current:
1] Contractor’s License of appropriate classification.
2] City of Vista Business License [see Subsection 2-2.1 (“City of Vista Business License.”)]
3] General Liability Insurance Certificate. The Certificate shall be issued with the Agency listed as the Certificate Holder. The Agency shall also be listed as an additional insured. See the Supplementary General Provisions for additional Certificate requirements and the amounts and types of li ability coverage. If any Subcontractor does not have the amount of liability insurance required in the Project Specifications, the General Contractor must produce evidence that the Subcontractor's work is covered by the General Contractor's liability insurance policy.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
65 of 244
58 4] Worker's Compensation Insurance Certificate. The Certificate shall be issued with the Agency listed as the Certificate Holder.
5] Waste Management Permit Application. The Contractor shall be required to recycle at least fifty percent (50%) of the generated waste in accordance with Vista Municipal Code Chapter
13.17. A permit will be issued by the Agency to the Contractor covering the Contractor and all Subcontractors.
2-3 RIGHT-OF-WAY.
Add the following paragraphs to this subsection:
The Contractor shall not allow his employees to use private property for any reason or to use water or electricity from such property without written permission from the owner. The C ontractor shall provide evidence of such permission in writing to the Engineer before entering upon such lands. In performing any work or doing any activity on lands outside the public rights-of-way, the Contractor shall comply with all applicable Federal, state and local laws, ordinances, codes and regulations. The Contractor shall indemnify and hold the Agency, its officials, officers, employees, and agents free and harmless from all claims or suits for damages occasioned by such work or activity, whether done according to this subsection and with permission from the owner or in violations of this subsection without permission from the owner.
For all projects t he Contractor shall be fully responsible for locating and obtaining permission to use construction storage area(s) and stockpile site(s) in addition to staging areas provided by the Agency. Where the Contractor may find it advantageous to use private property, it shall arrange for its use. The C ontractor shall assume full responsibility for its rental, preparation, maintenance and cleanup in a manner satisfactory to the Agency and the property owner.
2-4 COOPERATION AND COLLATERAL WORK.
Replace the first paragraph in this subsection with the following:
Nothing contained in these documents shall be interpreted as granting to the Contractor exclusive occupancy of the construction site for the Work. Should construction be under way or subsequently begun by other forces or by other contractors within or adjacent to the limits of the Work, or in the vicinity of the Work to be done under this Contract, the Contractor shall so conduct his operations as to interfere to the least possible extent with the Work of such other forces or contractors. If the performance of this Contract is likely to be interfered with by the simultaneous performance of some other forces or contractors, the Engineer will decide which contractor shall continue or whether the Work can proceed simultaneously.
Any difference or conflicts that may arise between the Contractor and such other forces or contractors because of delays or hindrance to each other, shall be adjusted and determined by the Engineer. If the Work of the Contractor is delayed because of any acts or omissions of any other contractor or force, the Contractor shall on that account have no claim for additional compensation or extra cost against the Agency.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
66 of 244
59 Add the following paragraphs to this subsection:
The Contractor shall perform the Work in such a manner as to maintain in operation all existing utilities and other public services. The Contractor shall allow operations and maintenance crews from any utility or other public service agency to access their facilities at any time. Owners o f the various utilities, and / or facilities at or near the Project site are as follows:
UTILITY OWNER
Gas and Electric Power Transmission and
Distribution Facilities San Diego Gas & Electric Company (SDG&E) Telephone and Communication Facilities AT&T Corporation Cable Television and / or Communication
Facilities
Cox Communications, Inc. , Times Warner
Cable, Crown Castle and/or Coastal
Sewer City of Vista Public Works and Buena
Sanitation District
Traffic Signals, Street Lights, and Fiber Optic
Communication Facilities City of Vista Public Works
Storm Drains City of Vista Public Works
Well Water Distribution or Irrigation City of Vista Public Works Water Vista Irrigation District (VID)
Water and Sewer
(for Emerald Dr., Olive Ave. and S. Melrose Dr.) City of Oceanside Utilities Department Water and Sewer
(for Palomar Airport Rd., Poinsettia Ave. and Linda Vista Dr.) Vallecitos Water District Bus / Railroad North County Transit District (NCTD)
State Highways California Department of Transportation
(Caltrans), District 11
2-5 THE CONTRACTOR’S EQUIPMENT AND FACILITIES.
2-5.1 General.
Replace the second paragraph in this subsection with the following paragraph:
The Contractor shall provide his own sanitary accommodations, including enclosed portable toilets and hand washing stations, for the convenience of the workers on the Project. The accommodations shall be regularly maintained by a company that specializes in providing and maintaining those facilities. The Contractor shall ensure that all workers on the Project, including those of subcontractors, use the Contractor’s accommodations and do not use any public or private facilities while working on the Project.
Add the following paragraphs to this subsection:
The Contractor must furnish adequate equipment to properly perform the Work in a workmanlike manner. Such equipment must be in good state of repair and maintained in such state during the progress of the Work. No worn or obsolete equipment shall be used, and in no case shall the maker’s rating of capacity for any equipment be exceeded. Equipment not suitable to produce the quality or Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
67 of 244
60 work required for this Project will not be permitted to operate. Such equipment and facilities shall meet all requirements of applicable ordinances and laws.
All construction equipment, stationary or mobile , shall be equipped with properly operated and maintained muffler exhaust systems. Stockpiling in vehicle staging area shall be located as far as practical from occupied dwelling units and shall be subject to approval by the Engineer.
Full compensation for conforming to the requirements of this provision shall be considered as included in the Contract price paid for various items of work and no additional compensation will be allowed therefore.
2-5.2 Temporary Utility Services.
Add the following paragraph to this subsection:
The Contractor may contact Vista Irrigation District (VID) to obtain a construction water meter and determine all terms, costs, conditions, and regulations imposed on the Contractor for use thereof.
Contractor will be required to pay for usage of water through construction water meter.
If VID does not have a construction water meter available, the Contractor shall use a water truck or other water storing equipment for use on the project and obtain water from offsite.
2-5.5 Emissions Near K-12 Schools.
Add the following new subsection:
2-5.5 Emissions Near K -12 Schools. The Contractor must notify the Agency twenty -five (25) Working Days in advance of when striping activities or operation of a portable emission unit will occur one thousand feet (1,000’) of any K-12 school (public or private) so that applicable public and student notification can occur. The Contractor shall provide notification to the schools affected.
2-6 CHANGES REQUESTED BY THE CONTRACTOR.
Add the following paragraph to this subsection:
The Contractor shall give written notice of a proposed Change Order required for compliance with the Contract Documents within seven (7) Working Days of discovery of the facts giving rise to the proposed Change Order.
2-6.1 Cost Reduction Proposal.
Add the following new subsection:
2-6.1 Cost Reduction Proposal. The Contractor may submit to the engineer in writing, proposals for modifying the Plans, Specifications, or other requirements of the Contract for the sole purpose of reducing the total cost of construction.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
68 of 244
61 The cost reduction proposal must not impair, in any manner, the essential functions or characteristics of the Project such as service life, economy of operation, ease of maintenance, desired appearance, or design and safety standards.
The Contractor shall include the following information in the cost reduction proposal:
a) A description of both the existing Contract requirements for performing the work and the proposed changes.
b) An itemization of the Contract requirements that must be changed if the proposal is adopted. c) A detailed estimate of the cost of performing the work under the existing Contract and under the proposed change.
d) A statement of the time within which the engineer must make a decision thereon. e) The Contract items of Work affected by the proposed changes, including any quantity variation attributable thereto.
These provisions of this subsection do not require the Engineer to consider any cost reduction proposal which may be submitted hereunder; nor will the Agency be liable to the Contractor for failure to accept or act upon any cost reduction proposal the Cont ractor has submitted pursuant to this subsection, nor for any delays to the Work attributable to any such proposal.
If a cost reduction proposal is similar to the information included in the Contract Documents or adopted by the Agency after the advertisement for the Contract, the Engineer will not accept such proposal and reserves the right to make such changes without compensation to the Contractor under the provisions of this subsection.
The Contractor must continue to perform the Work in accordance with the requirements of the Contract until a Change Order, incorporating the cost reduction proposal has been issued. If a Change Order has not been issued by the date upon which the Contractor’s cost reduction proposal specified that a decision thereon should be made, or such other date as the Contractor may subsequently have specified in writing, such cost reduction proposal must be deemed rejected.
The Engineer is the sole judge of the acceptability of a cost reduction proposal and the estimated net savings. In determining the estimated net savings, the Agency has the right to disregard the Contract Bid prices if, in the judgment of the Engineer, su ch prices do not represent fair measure of the value of the work to be performed or to be deleted.
The Agency reserves the right, where it deems such action appropriate, to require the Contractor to share in the Agency’s costs of investigating the Contractor’s cost reduction proposal as a condition of considering such proposal. Where such a condition i s imposed, the Contractor shall indicate his acceptance in writing allowing the Agency to deduct amounts payable to the Contractor for any monies due or that may become due to the Contractor under the Contract.
If the Engineer accepts your cost reduction proposal in whole or in part, the Engineer will issue a Change Order to incorporate the changes in the Plans and Specifications which are necessary to permit the cost reduction proposal, or such part of it as has been acceptable to be put into effect. If the Engineer’s approval is conditional, the Change Order will include any conditions upon which the Engineer’s approval is based.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
69 of 244
62 The Change Order shall also include the estimated net savings in the cost of performing the Work due to the accepted cost reduction proposal and provides that the Contract cost be adjusted by crediting the Agency with fifty percent (50%) of estimated net savings amount.
The Contract time will not be extended by the acceptance of the cost reduction proposal and performance of the Work unless specified otherwise in the Change Order.
The amount specified as payable to the Contractor in the Change Order is full compensation for the cost reduction proposal and the performance of the Work.
The Agency expressly reserves the right to adopt a cost reduction proposal for general use on contracts administered by the Agency when it determines that said proposal is suitable for application to other contracts. When an accepted cost reduction proposal is adopted for general use, only the Contractor who first submitted such proposal will be eligible fo r compensation subject to this subsection, and in that case, only for contracts awarded prior to submission of the accepted cost reduction proposal.
The cost reduction proposals identical or similar to previously submitted proposals will be eligible for consideration and compensation under the provisions of this subsection, if the identical or similar, previously submitted proposal were not adopted for general application to other contracts administered by the Agency.
Subject to the provisions contained herein, the Agency must have the right to use all or any part of any submitted cost reduction proposal without obligation or compensation of any kind to the Contractor.
The Contractor must bear all costs to revise bonds for the Project to include the cost reduction incentive proposal Work.
2-7 CHANGES INITIATED BY THE AGENCY.
2-7.1 General.
Add the following paragraph to this subsection:
Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any change resulting in a decrease or omission of any item or portion of work to be done. Whenever any change is made as provided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, conditions and provisions of the original Contract.
2-8 EXTRA WORK.
Add the following paragraphs to this subsection:
Any Extra Work performed by the Contactor without an approved Contract Change Order from the engineer shall be at the Contractor’s risk and the Contractor shall not be entitled to payment without Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
70 of 244
63 an approved Change Order. All Extra work shall be adjusted daily upon report sheets furnished by the Contractor, reviewed by the Engineer and signed by both parties. The daily report shall be considered thereafter as the true record of Extra Work done. New and unforeseen work will be classed as Extra Work only when said work is not covered and cannot be paid for under any of the various items or combination of items for which a bid price appears in the Bid Forms.
The Agency reserves the right to direct the Contractor to solicit competitive Bids for Extra work. If required by the Engineer, you must obtain competitive Bids from Subcontractor acceptable to the Contractor and must deliver such Bids to the Engineer who will then determine which Bids will be accepted.
Any request by the Contractor to change the Contract Price to include the price of Extra Work must be by written notice to the Engineer and must include itemized estimates. The Contractor’s itemized estimates must detail all applicable elements of price ( e.g. labor and payroll costs, quantities, crew composition, production rates, material costs, Subcontractor and Supplier costs, equipment costs, and supplemental costs).
If the Contractor’s request to change the Contract Price arises from changes in the Schedule affecting all or part of the Project, or if the Contractor seeks a change in the Contract time, the Contractor’s request must include the analysis require by Subsection 6-1 (“CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK.”).
SECTION 3 – CONTROL OF WORK
3-1 ASSIGNMENT.
Add the following paragraph to this subsection:
In accordance with Section 4551 of the Government Code, the Contractor and subcontractors shall conform to the following requirements. In entering into a public works contract or a subcontract to supply goods, services or materials pursuant to a public works contract, the Contractor or subcontractor offers and agrees to assign to the awarding body all rights, title and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or arising from purchases of goods, services or material s pursuant to the public works C ontract or the subcontract.
This assignment shall be made and become effective at the time the awarding body tenders final payment to the Contractor, without further acknowledgment by the parties.
3-5 INSPECTION.
Delete the second sentence in its entirety. Add the following paragraphs to the end of this subsection:
All work which is defective and has been rejected shall be remedied, or removed and replaced and made good by the Contractor in an acceptable manner . Unsuitable materials may be rejected notwithstanding the fact that such unsuitable materials have been previously overlooked by the engineer and accepted. No additional compensation will be allowed to the Contractor for the removal and replacement of remedial or defective work, or unsuitable materials.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
71 of 244
64 Any work done beyond the lines and grades shown on the Plans or established by the Engineer, or any Extra Work done without written notice by the Engineer, will be considered as unauthorized work and will not be paid for. Upon order of the Engineer unauthorized work shall be remedied, removed or replaced at the Contractor’s expense.
Upon failure of the Contractor to comply promptly with any order of the Engineer made under Subsection 3-5 (“INSPECTION.”), the Agency may cause rejected or unauthorized work to be remedied, removed or replaced, and to deduct the costs from any monies due or to become due to the Contractor.
The Contractor shall notify the Agency at least twenty-four (24) hours in advance of the time required for the inspection of any Work which will be covered or which will require special inspection procedures.
INSPECTION TYPE PHONE NUMBER
City of Vista Building Inspection 760-639-6106
City of Vista Engineering Inspection 760-639-6113
City of Vista Landscape and Irrigation Inspection 760-643-5467
The Agency will pay for costs of inspection and materials testing, sufficient to verify the quality of the Contractor’s work. Any retesting of failing areas, or costs due to the Contractor’s failure to be ready for inspections requested by the Contractor, shall be paid for by the Contractor.
If the Contractor elects to work under this Contract more than eight (8) hours a day or more than forty (40) hours in a week, Saturday, Sunday or Agency holidays, unless otherwise specified, he shall arrange with the Engineer for the required inspection service and pay the Overtime Inspection Fees which will be charged at the following rates:
NUMBER OF OVERTIME HOURS COST
4 hours or less per day $375.00
4 to 8 hours per day $750.00
When Overtime Inspection is required, the Contractor shall notify the Agency and pay inspection fees twenty-four (24) hours in advance. If the Contractor is directed by the Agency to work under this Contract more than eight (8) hours a day or more than forty (40) hours a week, the Special Inspection fee requirements will be waived.
The Contractor shall notify the Engineer of the completion of the Work and the Engineer will make an inspection of the Work. The Engineer will not make the final inspection until the Work provided for and contemplated by the Contractor has been completed and the final clean up performed. The Contractor may be present at the final inspection. The Contractor will be notified in writing of any defects or deficiencies to be remedied. When notified that corrective work is completed, the Engineer will again i nspect the Work and when the Engineer is satisfied that all work has been done in accordance with the Plans and Specifications, the Engineer will recommend that the Work be formally accepted.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
72 of 244
65 3-5.1 Inspection by Other Jurisdictions.
Add the following new subsection:
3-5.1 Inspection by Other Jurisdictions. Whenever any part of the Work to be performed is under the jurisdiction or control of, or is to be paid for, in whole or in part, by another public agency, entity, or jurisdiction, including but not limited to another city, Vista Irrigation District, North County Transit District, the County of San Diego, the State of California, or the United States Government, such Work, in addition to Agency inspection, shall be subject to inspection and approval by the proper officials of such entities or jurisdictions.
3-6 THE CONTRACTOR’S REPRESENTATIVE.
Replace the first two sentences in this subsection with the following:
Before starting the Work, t he Contractor shall provide in writing to the Agency a list of the representatives with local area codes and telephone numbers of at least two (2) persons in charge of or responsible for the Work, who can be reached for emergency work twenty -four (24) hours a day, seven (7) days a week.
Replace the third and fourth sentences in this subsection with the following:
Contractor shall have on the site, at all times, a Superintendent who will be in charge of all aspects of the Contractor’s work. The Superintendent shall be the individual authorized to receive directions from the Engineer of the Project and who will at all times act as the Contractor’s representative. Any order or communication given to the Superintendent shall be deemed delivered to the Contractor.
Contractor shall only replace the Superintendent upon written approval of the Agency. The Agency shall have the right to request that the Contractor appoint a new Superintendent if the Engineer or the Agency determines that such a replacement would be in the best interest of the Project.
Add the following paragraphs to this subsection:
The Contractor shall submit a daily report to the Engineer from the Contractor and all subcontractors, on forms approved by the Engineer. The report shall include a listing of all labor, materials and equipment involved for that working day. Failure to submit the daily report by the close of the next working day shall be just cause for the Agency to dispute progress pay requests. The Contractor shall coordinate daily with the Engineer to reconcile the report, and it shall be signed by both the Engineer and the Contractor. In the event of disagreement, pertinent notes shall be entered by each party to explain points which cannot be resolved immediately. Each party shall retain a signed copy of the report. Reports by subcontractors or others shall be sub mitted through the Contractor.
The report shall:
1] Show names of workers, classifications, and hours worked. 2] Show type of equipment, size, identification number, and hours of operation. 3] Describe the work done that working day, and what work was completed. 4] Describe status of any unresolved issues in such detail as the Agency may require.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
73 of 244
66 3-7 CONTRACT DOCUMENTS.
3-7.1 General.
Add the following to the second paragraph in this subsection:
As shown on the Plans or described in the Specifications, each element of the Work must be furnished complete, finished and functional. Figured dimensions on drawings shall govern, but work not dimensioned shall be as directed. Work not particularly shown or specified shall be the same as similar parts that are shown or specified. Specifications shall govern as to materials, workmanship and installation procedures. The specification calling for the higher material or workmanship shall prevail.
In the event of any doubt or question arising resp ecting the true meaning of the specifications, reference shall be made to the representative of the owner of the facility affected by the work, whose decision shall be final.
Replace the last paragraph in this subsection with the following:
If the Contractor, either commencing work or in the course of the work, finds any discrepancy between the Specifications and the Plans, or between either and the physical conditions at the site of the Work, or finds any error or omission in any of the Plan s, or in any survey, the Contractor shall promptly notify the Engineer in writing of any discrepancy, error, or omission. No work shall be done in any area of such discrepancy until the Engineer has given approval for same in writing. The Contractor shall forward written Requests for Information (RFIs) to the Engineer in all such matters.
Only written authorization from the Agency shall be binding over any deviation or changes in the Plans and Project Specifications. If the Contractor observes that any Plans or Specifications are at variance with any applicable law, ordinance, regulation, order or decree, the Contactor shall promptly notify the Engineer in writing of such conflict.
The Engineer on receipt of any such written notice will promptly investigate the circumstances and give appropriate instruction to the Contractor in writing. Until such instructions are given, any work done by the Contractor, either directly or indirectly , after the Contractor’s discovery of such error, discrepancy or conflict, shall be at the Contractor’s own risk, and the Contractor shall bear all costs arising therefrom.
3-7.2 Precedence of the Contract Documents.
Add the following paragraphs to this subsection:
With reference to the Drawings, the order of precedence, from highest to lowest, shall be as follows:
a) Figures govern over scale dimensions. In the event of any discrepancy between any drawings and the figures thereon, the figures shall be taken as correct. b) Detail drawings govern over general drawings
c) Large scale details shall take precedence over smaller scale drawings as to shape and details of construction.
d) Work not particularly shown or specified shall be the same as similar work that is shown or specified.
e) Addenda or Change Order drawings govern over Contract Drawings Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
74 of 244
67 f) Contract Drawings govern over Standard Drawings
g) Contract Drawings govern over Shop Drawings
The specifications contained in the Agency’s Supplementary Special Provisions (General and Technical) take precedence over the specifications contained in the San Diego Regional Supplement to the Greenbook and the Greenbook. The specifications contained i n the San Diego Regional Supplement to the Greenbook take precedence over the specifications contained in the Greenbook.
Should it appear that the Work to be done, or any of the matters relative thereto, are not sufficiently detailed or explained on the Contract Documents, or in the event of any doubt or question arising respecting the true meaning of the Specifications, the Contractor shall forward written Requests for Information (RFIs) to the Engineer for such further explanation as may be necessary and the Engineer’s decision shall be final and binding.
3-8 SUBMITTALS.
3-8.1 General.
Add the following to the end of the first paragraph in this subsection:
Promptly after the Notice to Proceed has been received by the Contractor, the Contractor shall provide to the Engineer a complete list of names and addresses of all suppliers of materials to be used on the Work.
Modify the second paragraph in this subsection as follows:
The Contractor shall allow a min imum of ten (10) Working Days for review of shop drawings and submittals. Each set of shop drawings or submittals shall be accompanied by a letter of transmittal and the Contractor’s certification (see description of certification below).
Add the following paragraphs to this subsection:
All submittals shall be submitted prior to the start of the Work unless otherwise approved by the Engineer. No work shall begin until the construction schedule has been approved by the Engineer.
The Contractor shall submit for Agency review and approval shop drawings and submittals for all long lead supplies, materials, and equipment within five (5) Working Days after the Notice to Proceed letter has been issued. The Contractor shall furnish the Engineer with a statement from the vendor(s) that the order(s) for said supplies, materials, and equipment has been received and accepted by said vendor(s) within fifteen (15) Working Days of said Notice to Proceed.
No work shall begin on the respective items of work that require a submittal until the submittals for those items of work have been approved in writing by the Engineer. When submitted for the Engineer’s review, shop drawings shall include the Contractor’s certification that the Contractor has reviewed, checked, and approved the shop drawings as conforming to the requirements of the Contract Documents. The following Contractor’s certification shall appear on all submittals:
“It is hereby certified that the (equipment, material) shown and marked in this submittal is that proposed to be incorporated into this Project, is in compliance with Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
75 of 244
68 the Contract Documents, can be installed in the allocated spaces, and is submitted for review.
Certified by: ________________________________________
Printed name: ________________________________________
Title: ________________________________________
Date: ________________________________________
A copy of each shop drawing and each sample as reviewed by the Engineer shall be kept in good order by the Contractor at the site and shall be available to the engineer. A review fee of two hundred dollars ($200.00) will be withheld from the Contractor’s progress payment for every re-submittal after the third time a submittal has been reviewed and rejected.
Submittals shall be mailed, emailed or delivered to the City of Vista Engineering Department listed below. Submittals by facsimile (FAX) are not acceptable.
Attention: Darra Woods, Principal Transportation Mobility Planner City of Vista
Engineering Department
200 Civic Center Drive
Vista, CA 92084-6275
Email: [email protected]
3-8.2 Working Drawings.
Add the following to Table 3-8.2:
TABLE 3-8.2 Note
Item Subsection Number Title Subject
15 306-7 Pipe laying Pipeline shop drawings
16 306-5 Dewatering Dewatering Plan
Notes: 1. The diagrams shall be of a size and scale to show clearly all necessary details. Pipeline layouts, for reference only, may be submitted in tabulated form in increasing order of alignment stationing.
2. Pipeline layout diagrams or schedules required for approval shall be submitted in accordance with 3-8.3. Layout diagrams or schedules are required for pipelines using pipe materials conforming to the indicated subsections.
The diagrams or schedules will be submitted for reference only, but curve layouts are required for approval.
Modify the fourth paragraph in this subsection to read as follows:
Working Drawings listed above as Items 4-7, 9-15 and 16 shall be prepared by a Civil or Structural Engineer registered by the State of California.
3-8.3 Shop Drawings.
Add the following to this subsection:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
76 of 244
69 The following procedures will apply to shop drawing submittals:
a) The Contractor shall submit to the Engineer for review five (5) copies of all shop drawings.
These drawings shall be complete, certified by the Contractor, and shall contain all required information in detail. The Contractor shall make any corrections to shop drawings required by the Engineer.
b) It is considered reasonable that the Contractor shall make a complete and acceptable submittal to the Engineer by the third submission of a submittal item. (1) If a submittal is returned to the Contractor marked “No exceptions taken,” formal revision and resubmission of said submittal will not be required. (2) If a submittal is returned to the Contractor marked “Make corrections noted,” formal revision and resubmission of said submittal will not be required. (3) If a submittal is returned to the Contractor marked “Amend-Resubmit,” the Contractor shall revise said submittal and shall resubmit the required number of copies of the revised submittal to the Engineer.
(4) If a submittal is returned to the Contractor marked “Rejected -Resubmit,” the Contractor shall revise said submittal and shall resubmit the required number of copies of said revised submittal to the Engineer.
c) When reviewed by the Engineer, each copy of the drawings will be stamped and signed by the Engineer.
d) Two sets of said drawings will be returned to the Contractor. e) The review of the drawings shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. The Contractor shall assume all responsibility for accuracy of data, details, and dimensions shown in the submittals. f) The Contractor agrees that if deviations, discrepancies, or conflicts between shop drawing submittals and the Contract Documents in the form of Plans and Specifications, except as particularly noted within the submittal, are discovered either prior to or a fter shop drawings submittals are processed by the Engineer, the Plans and Specifications shall control and shall be followed.
g) Revisions indicated on shop drawings shall be considered as changes necessary to meet the requirements of the Contract Plans and Specifications and shall not be taken as the basis of claims for Extra Work. The Contractor shall have no claims for damages o r extension of time due to any delay resulting from making required revisions to shop drawings. The review of said drawings by the Engineering will apply to general design only and will in no way relieve the Contractor of responsibility for errors or omis sions contained therein nor will such review operate to waive or modify any provisions or requirements contained in these Contract Specifications or on the Contract Drawings.
h) The Contractor shall furnish to the Engineer eight (8) copies of instruction and maintenance manuals and parts lists of all major equipment furnished. Data in these manuals shall cover completely all items as specified and as supplied.
i) Shop fabrication drawings and lay sheets are required for all steel pipelines sixteen inches and greater in diameter (16”+ Ø). The drawings and lay sheets shall fully illustrate horizontal station and vertical elevation of all joints and angle points, true angular deflection at locations of combined vertical and horizontal bends, and horizontal station for pipeline appurtenances.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
77 of 244
70 3-8.4 Supporting Information.
Add the following items to this subsection:
n) City of Vista Stormwater Management Permit and Storm Water Pollution Prevention Plan (SWPPP), if required, per Subsection 2-2 (“PERMITS.”).
o) Waste Management Plan Permit Application per S ubsection 3-12 (“WORK SITE MAINTENANCE.”).
p) Noise Control Notification per Subsection 3-12.3 (“Noise Control.”). q) Traffic Control Plans per Subsection 601-2 (“Traffic Control Plan (TCP).”). r) Night Work Plan per Subsection 5-7.1.3 (“Safety for Night Work.”).
Add the following paragraphs to this subsection:
Compliance certificates and weigh slips shall be provided for all fill material, aggregate base, asphalt concrete, Portland Cement Concrete, reinforcing steel, etc. The Contractor shall submit mix designs for asphalt concrete and Portland Cement Concrete to the Engineer for approval. All asphalt concrete and Portland Cement Concrete weigh slips (delivery tickets) shall include the mix design and number or the actual weights of aggregate, sand, cement and water in each truckload. In addition, the Contractor must schedule a meeting and meet with the Engineer each working day to confirm the quantities of materials shown on the weigh slips. The Engineer shall approve any admixtures prior to use. The Contractor shall submit to the Engineer a certified mill test report for each heat or size of reinforcing steel.
The Contractor shall submit the names and addresses of all suppliers of mineral construction materials, and the mine from which the materials were obtained, along with a copy of the Office of Mine Reclamation AB 3098 List (per California Assembly Bill 3098) showing that the mining operation is listed, prior to delivering any mineral construction materials to the Project site. This documentation regarding the Office of Mine Reclamation AB 3098 List (per California Assembly Bill 3098) shall be made a part of every submittal required on the Project that includes mineral construction materials.
Failure to identify the supplier and the mine may result in rejection of the submittal.
3-8.7 Record Drawings (“As-Builts”).
Add the following new subsection:
3-8.7 Record Drawings (“As-Builts”). It shall be the Contractor's responsibility to keep and maintain, on the job site, a clean, accurate, full-size and legible print set of Project plans that indicate all changes in work, modifications and existing conditions that are different from what is shown on the Plans. The Contractor shall record the location, by stationing to nearest foot, and the depth, by elevation to the nearest tenth of a foot (+/ - 0.1’), of all underground utility facilities, including pipes, valves, plugged tees, capped ends, etc. The Contractor shall record, by dimension and / or scale drawings, all wiring, conduits and pull boxes as actually installed. All information necessary to maintain and / or service any concealed work shall be noted on the record drawings. The locations by station of sewer laterals and water services (both perpendicular and skewed) to their mains must be not ed on the record drawings. Records shall be kept up to date with all entries checked by the Engineer Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
78 of 244
71 before the Work is buried or covered up. The Contractor shall make the Record Drawings available for review by the Engineer at any time.
Upon completion of the Work and prior to final acceptance, the complete set of Plans, marked up to show as -built conditions, shall be delivered to the Engineer for review . Full compensation for preparing, maintaining and providing Record Drawings (“As-Builts”) shall be included in the stipulated lump sum price for this item of work. If no item is shown in the bid, then the Contractor shall include all costs in the various items of work.
3-9 SUBSURFACE DATA.
Add the following paragraph to this subsection:
The Contractor shall investigate the existing geotechnical (soil) conditions prior to submitting a bid, and shall satisfy himself as to the existing geotechnical ( soil) conditions, and include all costs to address those conditions in the bid. Upon removal of the existing surface improvements and excavation to subgrade by the Contractor, the Agency will sample existing soils for analysis of the R - value, moisture content, and compaction. Upon determination of the existing geotechnical ( soil) conditions and a final street structural section, the Agency will advise the Contractor regarding addition of geogrid or adjustments to the thickness of the aggregate base and the asphalt concrete layers.
For the TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294), the excavation, placement, conditioning, and compaction of material shall be in accordance with the Plans, Specifications, the City of Vista Development Code (Chapter 17 Section 17.52 and Section 17.56).
3-10 SURVEYING.
3-10.1 General.
Replace all three paragraphs in this subsection with the following:
3-10.1 General. The Contractor shall notify the Engineer and the Professional Land Surveyor or Registered Civil Engineer authorized to practice land surveying in the State of California (“Surveyor”) performing construction staking at least five (5) Working Days before starting work to allow for the preservation of reference points, survey monuments, lot stakes (tagged), benchmarks and other survey points.
In accordance with the Professional Land Surveyors Act (State of California Business and Professions Code 8771(a), (b) and 8773.2 (as amended by California Senate Bill 1563), the Surveyor performing construction staking for the Project shall file in the Office of the County Surveyor a Corner Record form or Record of Survey prior to the completion of construction for the replacement of survey monuments. The Contractor shall not disturb survey monuments, lot stakes (tagged), or benchmarks without the consent of the Engineer, and in the case of willful or careless destruction, shall be liable for and charged with the cost of their replacement and of any expenses resulting from their unnecessary loss. Replacement shall be done only under the direction of the E ngineer by a Register Land Surveyor or a Register Civil engineer authorized to practice land surveying within the State of California.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
79 of 244
72 Upon submittal of all Corner Record forms or Records of Survey to the San Diego County Surveyor’s office, the Surveyor performing construction staking for the Project shall submit copies of the same records to the Agency. Upon acceptance and approval by the San Diego County Surveyor’s office, the Surveyor shall also submit Corner Record forms or Records of Survey (Mylar) copies of the same records to the Agency prior to completion of the Project.
By contract with the Agency, the Surveyor shall coordinate and be responsible for the accuracy of all surveying performed for the Project. If the Professional Land Surveyor or Registered Civil Engineer (“Surveyor”) performing construction control surveying / staking requires additional information, he shall request it from the Agency. All construction surveying, monument preservation and monument replacement surveying necessary to complete the Work as shown on the Plans and as provided for in the Specifications and other Contract Documents shall be accomplished by or under the direction of a Surveyor. The Agency reserves the right to direct additional construction survey work when the Engineer determines it to be necessary to adequately construct the Work . The Contractor shall preserve construction survey stakes and marks for the duration of their usefulness.
The Contractor shall notify the Engineer and the Surveyor performing construction staking in writing by submitting a completed “ City of Vista Engineering Construction Survey Request Instructions and Form” at least three (3) Working Days before survey services will be required in connection with the laying out of any portion of the Work. The Surveyor performing construction staking for the Project shall set and station stakes for clearing limits, rough grade, sewers, storm drains, water, dry utilities, structures, finish (precise) grade, curbs, headers, base grade, pavement and other improvements. The Surveyor shall submit acceptable preconstruction survey tie notes to the Engineer for approval. A corresponding cut or fill to finish grade (or flowline) will be indicated on the Surveyor’s grade (cut) sheet. The Contractor shall be required to excavate all holes necessary for offset line and grade stakes if in excess of one-half foot (0.5’) deep.
All survey monuments, centerline ties and survey reference points shall be protected in place or reestablished where disturbed, in accordance with Section 8771 of the Professional Land Surveyor’s Act (Business & Professions Code Section 8700 et seq.), prior to Project acceptance.
3-10.2 Line and Grade.
Replace the first and second paragraphs in this subsection with the following:
All work, including finished surfaces, shall during its progress and upon completion conform to the lines, grades, cross-sections, elevations and dimensions shown on the Plans. All distances and measurements are given thereon and will be made in a horizontal plane. Three (3) consecutive points shown on the same rate of slope must be used in common in order to detect any variation from a straight line. In the event any discrepancy exists, it must be reported to the Engineer. Failure to make this report shall make the Contractor responsible for any error in the finished work. Minor deviations from approved Plans, whenever required by the exigencies of construction, shall be determined in all cases by the Engineer and authorized in writing.
Add the following paragraphs and table to this subsection:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
80 of 244
73 The Professional Land Surveyor or Registered Civil Engineer authorized to practice land surveying in the State of California (“Surveyor”) performing construction staking will furnish construction stakes to prosecute the Work as part of the various items of work. Surveying and staking shall be performed using survey equipment and methods appropriate for the Work. For grades equal to or less than one- half percent (0.5%), elevations for staking shall be established by differential leveling. The Surveyor performing construction staking for the Project shall provide the following stakes as needed to complete the Work:
STAKE TYPE STAKE REQUIREMENTS
Clearing and Grubbing Show limits of Work at fifty foot ( 50’) maximum intervals and at angle points
Slope Show rough grading for slopes at fifty foot (50’) maximum intervals as needed for construction
Rough Grade Show rough grading for road subgrade on centerline at fifty foot (50’) maximum intervals and on slopes as needed to achieve cut or fill to finished grade as indicated on a grade sheet Drainage Structure Two (2) front corners with line stakes with ten foot (10’) maximum offset, invert elevations in and out, and information for top of structure elevation
Pipelines (storm drain,
sewer, water, etc.)
At twenty-five foot (25’) maximum intervals for invert elevation or top of pipe; also at change of alignment or grade
Sewer and Storm
Drain Manholes
Centerline, invert elevations in and out, and top of rim Road Base Establish finish base grade at centerline of street and intersections, provide “blue tops” at fifty foot ( 50’) maximum on centerline of street and at ten to fifteen foot (10’ - 15’) grid within intersections
Finish Asphalt Grade At twenty-five foot ( 25’) maximum intervals for irregular asphalt cuts and fills to set leveling surfaces and at ten to fifteen foot (10’ - 15’) grid within intersections with additional stakes for landings at the bottom of curb ramps
Curb and Gutter At twenty -five foot ( 25’) maximum intervals and at the top of driveway entrance wings
Curb Return At each quarter (1/4) delta with a stake at the curb return radius point
Curb Ramp Top and bottom of curb transitions, lip of depressed gutter, finished surface at four (4) corners of top landing, & transitions Driveway Centerline and wings (join lines if matching to existing) Street Light and Traffic
Signal poles
Five to seven foot ( 5’ - 7’) maximum offset showing centerline of poles
The Surveyor performing construction control surveying / staking shall provide one (1) copy of all grade sheets to the Engineer.
The cost to reset construction survey stakes lost or destroyed during construction operations shall be borne by the Contractor.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
81 of 244
74 3-10.3 Payment.
Add the following new subsection:
3-10.3 Payment. The Professional Land Surveyor or Registered Civil Engineer authorized to practice land surveying in the State of California (Land Surveyor) performing construction control surveying / staking will furnish construction stakes to prosecute the Work, and no compensation will be made to the Contractor for delays to the Work caused by the Contractor’s lack of coordination with the Agency to schedule Construction Staking. The cost to reset stakes lost or destroyed during construction operations shall be borne by the Contractor. Payment for providing construction staking on the Project will be made by the Agency directly to the Land Surveyor under contract with the Agency.
3-11 CONTRACT INFORMATION SIGNS.
3-11.1 City of Vista Project Information Signs.
3-11.1 City of Vista Project Information Signs. Before the start of any work, the Contractor shall design, supply, install, and maintain six (6) aluminum 4’ x 4’ signs to inform the public about the Project. The signs shall be designed and made by a professional sign company. Sample artwork for each sign is included in the appendices (see list of Appendices in Table of Contents on Page 2). The Contractor shall submit the sign layout to the Engineer for approval before signs are fabricated.
Project Information shall include:
a) City Name and logo
b) Project Name and CIP number
c) Names of the City Council
d) Construction duration “M/D/Y to M/D/Y
e) “Possible Traffic Impacts or Delays”
f) “For Project Information contact [email protected] or (760) 643-5387. g) Funding source(s)
Project Information Signs shall be posted with 4” x 4” wood posts within the parkway adjacent to the street at a location approved by the Engineer and at least seven feet (7’) above the pedestrian travel way. Signs and sign posts shall be located within the public right-of-way and may not hinder or obstruct driver’s line of sight. The text on the sign shall be large and legible from a distance. All signs provided by the Contractor shall be protected by an anti -graffiti coating similar to 3M/1160.. Signs shall be posted at least three (3) Working Days prior to start of construction and remain posted until the final job walk is completed. The signs shall then be removed and property disposed. Contractor shall be responsible for the maintenance of these signs until removed.
Full compensation for the Project Information Signs, including design, construction, anti -graffiti coating, deployment, maintenance, removal at project completion and furnishing of all necessary labor, equipment, materials, and all other related costs shall be considered as included in the Bid price for “Project Information Sign.” Payment for the Project Information Signs shall be paid under the unit price bid for each sign as shown on the BID SCHEDULE at ninety percent (90%) for the completed installation of the signs, ten percent (10%) for the removal and delivery of the signs upon completion of the Work and no additional compensation shall be allowed therefore.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
82 of 244
75 3-11.2 Public Notification.
Add the following new subsection:
3-11.2 Public Notification. The Contractor shall prepare typewritten Public Notification fliers in English and Spanish. Fliers shall notify residents and businesses of the Work and include information describing the Work, how it may affect them and contact information of Agency and Contractor personnel responsible for the work. The Engineer will provide the contact information for the Agency to be included on the flier at the Pre -Construction Meeting. The Contractor shall submit draft versions of the flier in English and Spanish to the Engineer for review and approval prior to starting the Work. The Contractor shall to provide advance notifications of the Work to residents and businesses adjacent to or affected by the Work by hand delivering “door knob type” fliers distributed at least five (5) Working Days prior to Work.
These notices shall also be distributed at other times during the Work as required to notify affected people in the area of impending work, including, but not limited to, prior to commencing rehabilitation, resurfacing, or reconstruction work on streets that will affect access to traffic or pedestrians.
Based upon the work schedule, the Contractor shall notify residents and businesses of the work and post temporary “No Parking” signs to all residences and businesses located in the work limits and along any detour routes.
The Contractor shall provide additional notification for night work that creates excessive noise, as described in Subsection 3-12.3 (“Noise Control.”) of these Specifications.
Full compensation for conforming to the requirements of this Subsection 3-11.2 shall be considered as included in the various items of work involved and no additional compensation shall be allowed therefor.
3-12 WORK SITE MAINTENANCE.
3-12.1 General.
Replace the second paragraph in this subsection with the following:
The Contractor and all Subcontractors are required to clean up the site on a daily basis. This cleanup shall include, but not be limited to, the Contractor furnish ing and operating a self-loading motorized street sweeper equipped with a functional water spray system or by hand (depending on the size of the daily job/cleanup), removal of all construction material that is no longer needed on the job site, daily removal of all construction rubbish/trash away from the job site , proper storage of all construction equipment including traffic control devices that are not in use. The sweeper shall clean all paved areas within the Work site and all paved routes at least once each working day for the purpose of keeping paved areas acceptably clean whenever construction, including restoration, is incomplete. It shall be the Contractor’s responsibility to keep vehicle and pedestrian travel ways broom clean at all t imes. Failure to comply with these daily cleanup requirements may result in the Agency performing the cleanup work and deducting the cost from the Contractor’s payment(s).
The sweeper shall be certified to conform to the South Coast Air Quality Management District’s (SCAQMD) (California) Rule 1186 requirements, which limit the amount of very fine particles of dust Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
83 of 244
76 that can become airborne during sweeping operations. For additional information regarding SCAQMD’s Rule 1186, go to Internet URL website link at:
http://www.aqmd.gov/home/rules-compliance/rules/fleet-rules/sweepers
Upon completion and before making application for acceptance of the Work, the contractor shall clean the construction site and all ground occupied by him in connection with the Work of all rubbish, excess materials, temporary structures, and equipment. Al l parts of the Work area shall be left in a near and presentable condition.
Care should be taken to prevent spillage on streets over which hauling is done, and any such spillage or debris deposited on streets due to the Contractor's operation shall be immediately cleaned up.
The Contractor shall remove and dispose of all structures, debris, or other obstructions to the construction of the Work as specified. Where such obstructions consist of improvements not required by law to be removed by the owner thereof, all such improve ments shall be removed, maintained, and permanently replaced by the Contractor at his expense as required for performance of the Work.
The Contractor shall furnish all water necessary for compaction, cleaning, flushing, dust control, etc.
No separate payment will be made for any work performed or material used to control dust resulting from the Contractor’s performance of the Work, or by public traffic, either inside or outside the right-of-way.
Full compensation for conforming to the requirements of this Subsection 3-12.1 shall be considered as included in the various items of work involved and no additional compensation shall be allowed therefor.
Add the following paragraphs to this subsection:
EDCO Waste and Recycling Company has an exclusive franchise agreement with the Agency for waste hauling. If the Contractor requires waste disposal service, that service must be provided by EDCO. The Contractor is to make his own arrangements with EDCO an d pay for all waste disposal, which is to be included in his overall Contract bid.
As a result of AB 939, the Agency has established a Construction and Demolition (C&D) Recycling Ordinance (Vista Municipal Code Chapter 13.17) to help divert waste from landfills and to comply with mandates of the California Integrated Waste Management Board ( per City of Vista Ordinance No. 2006-19). Many of the materials generated from construction and demolition projects can be recycled or reused. The Agency requires any contractor that generates debris to use a recycling service (EDCO or other Agency -approved recycling company) and fill out a Was te Management Plan (WMP). The Contractor shall cooperate with the Agency’s Inspector and Agency’s Waste Management Compliance Officer in completing the WMP prior to obtaining the required “No Fee” Construction Permit. If you have any questions about the Agency’s Construction and Demolition Recycling Ordinance or how to get a copy of this form, please contact the City of Vista at (760) 639-6108.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
84 of 244
77 The Contractor shall provide copies of all receipts from EDCO and include all demolition costs in his construction bid.
Full compensation for furnishing all labor, materials, equipment and incidentals for clean -up and dust control as specified, including weekends and other non -working days at the Agency’s request, shall be considered as included in related items of work and no additional compensation will be allowed therefore.
3-12.2 Air Pollution Control.
Add the following paragraph to this subsection:
All cold milling equipment, sandblast pots over one -hundred pounds (100 lbs.), portable engines over fifty horsepower (50 HP), and auxiliary engines on construction equipment which are not used to drive equipment require permits from the San Diego County A ir Pollution Control District (SDAPCD).
The Contractor must obtain and maintain all required permits, and follow all permit requirements.
3-12.3 Noise Control.
Add the following paragraphs to this subsection:
The Contractor shall comply with local ordinances regulating noise level (see Vista Municipal Code Chapter 8.32).
All construction activities (including, but not limited to, the use of tools, machinery or equipment used in connection with construction operations), regardless of hours of operation, shall be kept below an average hourly sound level of seventy-five (75) dBA Leq measured at fifty feet (50’) from the noise source. A noise level limit of ninety-five ( 95) dB at a distance of fifty feet (50 ’) shall apply to all construction equipment on or related to the job whether owned by the Contractor or not. Examples include but are no t limited to: equipment startups, equipment staging in or near the project, truck deliveries to the project, construction traffic loud talking, etc.
This ordinance applies to all grading operations and all public improvement construction on private or public property.
The Contractor shall not perform high -noise producing work (e.g. jack-hammering, saw-cutting, sand blasting, cold milling, compacting, etc.) between the hours of 10:00PM and 7:00AM, unless the Contractor is directed to perform work at night as part of a unique project, to avoid excessive impacts to traffic, businesses, or schools. The Contractor shall provide written notification to all residential properties within five hundred feet (500’) of the work zone at least seventy-two (72) hours in advance of per forming: 1) work during these hours ; 2) high -noise producing during working hours. The proposed notification form and list of properties shall be submitted to the Engineer for approval.
Stationary construction equipment shall be placed such that emitted noises are directed away from sensitive noise receivers such as residential uses. The Contractor shall make every effort to create the greatest distance between noise sources and receptors during construction operations.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
85 of 244
78 The Contractor shall use only such equipment on the Work and in such state or repair, that the emission of sound therefrom is within the noise tolerance level of that equipment, as established by accepted standards of the industry. Should the Agency deter mine that the muffling device on any equipment used on the Work is ineffective or defective so that the noise tolerance of such equipment, as established by accepted standards of the industry, is exceeded, such equipment shall not, after such determination by the Agency, be used on the Work until its muffling device is repaired or replaced so as to bring the noise tolerance level of such equipment within such standards.
3-12.4 Storage of Equipment and Materials.
3-12.4.1 General.
Add the following paragraphs to this subsection:
The Contractor shall obtain and maintain, at his own cost, a construction staging area outside of the right of way or outside the boundaries of the Agency’s property, unless a staging area is specifically shown on the Plans or described in the specificatio ns. Any posted signs for or related to the staging area must be of professional quality and approved by the Engineer prior to placement. The staging area must be established, maintained and removed in a manner acceptable to the Engineer and the owner of the land where the staging area is situated. The Contractor shall be solely responsible for the security and liability of the staging area. The staging area maybe fenced, lighted and locked. Guard dogs are not allowed at the construction staging area. Such staging areas shall meet all requirements of applicable standards, codes, ordinances and laws, and shall be established at least five (5) Working Days prior to commencement of work.
When any product, material or equipment is to be stored outside the highway or street right-of-way or Agency property, the Contractor shall first obtain written permission from the property owner on whose property the storage is to be made. The Contractor shall file with the Engineer an original permission letter, together with a written release from the property owner absolving the Agency or its employees from any and all responsibility in connection with storage of materials, products or equipment on said property.
3-12.4.2 Storage in Public Streets.
Add the following paragraphs to this subsection:
Personal vehicles of the Contractor’s employees shall not be parked on any section closed to the public traffic.
No equipment or materials may be stored o n public street rights-of-way unless pre-approved by the City of Vista Traffic Engineering Division.
3-12.4.3 Storage on Private Property.
Add the following new subsection:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
86 of 244
79 3-12.4.3 Storage on Private Property. The Contractor and all Subcontractors shall minimize the effects of construction operations upon private properties adjacent to the Work.
Prior to storing equipment or material on private property, the Contractor shall provide copies of all letters of permission or written agreements executed by affected property owners for the purpose of granting trespass rights to enter upon, stockpile or store Contractor's supplies and equipment to the Engineer. The Contractor shall, as a penalty to the Agency, forfeit one hundred dollars ($100) per day as a fine for each parcel as determined by the Engineer for failure to provide copies of such documentation to the Engineer prior to storing equipment or material on private property. Said fine or fines will be deducted from the Contractor’s subsequent monthly progress payment. The Contractor is solely responsible to initiate contact and negotiate agreement with property owners if the Contractor should desire to use private property for storage or other purposes.
Materials or equipment placed on private property without owner's consent or in breach of owner/contractor Contract shall constitute ground for immediate issuance of a stop work notice to the Contractor. The Contractor shall then be required to suspend all operations until affected property is cleaned up and restored to original condition. Additional Contract days will not be granted due to stop work action against Contractor.
3-12.6 Water Pollution Control.
3-12.6.1 General.
Add the following to this subsection:
The Contractor shall adhere to, the requirements of the San Diego Regional Water Quality Control Board (RWQCB). All work shall be performed in accordance with ORDER NO. R9 -2013-0001, AS AMENDED BY ORDER NOS. R9-2015-0001 AND R9-2015-0100 NPDES NO. CAS0109266 - NATIONAL
POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) PERMIT AND WASTE DISCHARGE
REQUIREMENTS FOR DISCHARGES FROM THE MUNICIPAL SEPARATE STORM SEWER SYSTEMS (MS4s) DRAINING THE WATERSHEDS WITHIN THE SA N DIEGO REGION, which can be found on the Internet at:
http://www.waterboards.ca.gov/rwqcb9/water_issues/programs/stormwater/index.shtml
The Contractor shall adhere to, and shall perform in accordance with the requirements of Vista Municipal Code Chapter 13.18 – Storm Water Management and Discharge Control Program.
As part of the application for City of Vista Storm Water Management Permit, the Contractor shall submit an erosion control plan showing all pollution prevention, erosion and sediment control, and site management practices, to the City Engineer for review and approval, and shall implement and maintain all ap propriate measures to prevent polluted discharges from entering storm water conveyance facilities (e.g. channels, storm drains, and water bodies). The Storm Water Management Permit application and erosio n control plan must be prepared and submitted by the Contractor and approved by the City Engineer before any land disturbance activities can take place on the construction site.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
87 of 244
80 For projects not subject to the Construction General Permit, before commencement, and until final acceptance of the Work by the City, the Contractor shall provide all measures necessary to avoid erosion and adverse drainage conditions, in conformance with the current Order and the City of Vista Grading Ordinance.
3-12.6.1.1 Compliance.
Add the following new subsection:
3-12.6.1.1 Compliance. The Contractor shall make every effort to comply with the provisions of this subsection. However, should the Contractor violate any of the provisions of this subsection, or if pollution occurs in the work area for any reason, the Contractor shall immediat ely notify the City Engineer. If an unmitigated non -storm water discharge leaves the construction site, the Contractor shall immediately stop all the activity causing the discharge and mitigate the discharge and immediately notify the City Engineer or call the Storm Water Hotline at 760-643-2804. In addition the Contractor shall, with seven (7) calendar days, submit written confirmation to the City Engineer describing the incident and corrective actions taken. If pollution, for whatever reason, is detected by the City Engineer before notification by the Contractor, the required written confirmation shall also include any explanation of why the Contractor had not notified the City Engineer.
As soon as practical, any and all waste material, sediment, debris or other pollution from any discharge shall be removed from the work area and/or the drainage system by the Contractor. Any remedial actions will be the sole responsibility of the Contractor.
The Agency may make any further corrective actions, as deemed necessary, for abatement of water pollution if the Contractor has violated any of the provisions of this subsection. The Contractor shall be responsible for all costs incurred for the corrective actions. Failure to comply with the requirements of this subsection may result in the suspension of Work per Subsections 6-6 and 6-4.3 (“SUSPENSION OF THE WORK.” and “Payment for Delays.”). The City’s Municipal Code (Vista Municipal Code) Section 13.18 allows for administrative, misdemeanor penalties, infractions, and civil actions for non-compliance and enforcement actions that include stop work orders. Failure may also result in significant fines and possible imprisonment. A prosecuting authority may asses s fines of up to $37,500 per calendar day for each violation. The Contractor shall also reimburse the Agency for any fines assessed against and paid by the Agency and that are the result of the Contractor’s failure to comply with these specifications.
Compliance with the requirements of this subsection shall in no way relieve the Contractor from its responsibility to comply with other provisions of the Contract, in particular its responsibility for repair of damage and for preservation of property.
3-12.6.2 Best Management Practices (BMPs).
Add the following to this subsection:
Prior to commencement of any land disturbance activities, the Contractor shall educate all employees, subcontractors, and suppliers about storm water pollution prevention and mitigation Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
88 of 244
81 measures needed during various construction activities to prevent the impacts originating from construction discharges. The Contractor shall ensure that all personnel are periodically trained in storm water and urban runoff management. A list of attendees and copies of the educational materials shall be kept on file at the site and submitted to the City Engineer at the conclusion of each training session, upon request.
The Contractor shall designate a qualified person who is trained and competent in the use of Best Management Practices (BMPs) and who shall be on the site daily to evaluate the conditions of the site with respect to storm water pollution prevention. This person shall ensure the implementation of the conditions of the City of Vista Storm Water Management Permit, erosion control plan, Contract Documents, and other State and local regulations and ordinances with respect to the control of erosion, sediment and other forms of water pollution, as well as other waste management regulations.
The Contractor shall implement pollution control measures and BMPs to prevent the impounding of runoff, nuisance water, sediment movement, and debris movement from the construction site onto adjacent properties or from adjacent properties onto the con struction site. If the City Engineer determines that the Contractor’s measures are not adequate, the Contractor shall provide whatever additional measures are required to gain compliance.
The Contractor shall protect with BMPs, such as gravel bags and filter fabric, all new and existing storm water conveyance system structures and other facilities from sedimentation or other related construction debris and discharges, or by any other equal product that is acceptable to the City Engineer. The Contractor shall schedule and conduct land disturbance operations, such as demolition, clearing, and grading, to minimize or avoid rain fall induced erosion and sediment discharges and prevent tracking at the construction site during ingress and egress. Water pollution control activities shall also consist of implementing good housekeeping BMPs to reduce the discharge of pollutants from construction sites. Such features as drainage gutters, slope protection blankets, and retention basins, if applicable to the site as described in the erosion control plan, shall be constructed prior to start of work. The Contractor shall prevent any discharge of concrete rinse water or other pollutant into a storm water conveyance facility by using physical barriers.
The Contractor shall maximize the preservation of existing native and non -native vegetation and minimize soil disturbance within the limits of Work.
The Contractor shall show on the erosion control plan all water pollution, erosion control, and sediment control BMPs for the Work including the locations for concrete washout, vehicle maintenance, staging, dispensing of fuel, and storage areas. Further, the Contractor shall show all pollutant control measu res or BMPs to be used to confine construction waste in designated areas, including construction entrance stabilization and wheel -wash measures to reduce the tracking or deposition of sediment onto public and private roads.
During the dry season (May 1 through September 30 each year), the Contractor shall inspect at least monthly all pollutant control measures or BMPs installed to mitigate construction activities during the dry season. During the rainy season (October 1 through April 30 each year), the Contractor shall inspect at least weekly all pollutant control measures, inspect before and after every rain event and every twenty-four (24) hours during any prolonged rain event.
The Contractor shall implement the following water pollution control measures:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
89 of 244
82 (a) Minimum Water Quality Protection Requirements:
(1) Eroded sediments and other pollutants must be retained on site and may not be transported from the Work site via sheet flow, swales, area drains, natural drainage, tracking by vehicles or equipment, or wind. Erosion from slopes and channels shall be controlled by implementing an effective combination of BMPs, such as the limiting o f grading scheduled during the rainy season; planting and maintenance of vegetation on slopes; and cover to prevent or minimize erosion of susceptible slopes. (2) Stockpiles of earth and other work -related materials must be protected from being transported from the site by wind or water.
(3) Fuels, oils, solvents, and other toxic and non -toxic substances shall be stored in accordance with the manufacturers’ instructions. All storage containers shall be protected from the weather. Fuels, oils, solvents, and other toxic substances originat ing from the Contractor’s operations shall not be allowed to contaminate the soil, storm water or surface waters or enter the ground water or be placed where they will enter a live stream, channel, drain, or other water conveyance facility.
(4) The Contractor may not wash excess or waste concrete onto the ground or into the public rights of way or any drainage system. Provisions shall be made to retain concrete wastes onsite with containment until it can be appropriately disposed of or recycled. (5) Trash and construction-related solid wastes must be deposited into a covered receptacle to prevent contamination of rainwater and dispersal by wind. (6) Vehicle and equipment traffic shall not track sediments and other materials from the construction site. The Contractor must stabilize the entrance roadways to the construction site to inhibit sediments from being deposited into the public rights of wa ys. Accidental depositions must be swept up immediately and may not be washed down by rain or by any other means. All loose soil and debris shall be removed from street areas upon starting operations and periodically thereafter as directed by the City Engineer. (7) Non-storm water, wash water and runoff from equipment and vehicle washing and any other activity shall be contained at the construction site. (8) The Contractor shall protect all new and existing storm drain system structures from sedimentation, or other construction related debris and discharges with gravel bags and filter fabric or by any other equal product or measure acceptable to the City E ngineer.
Accumulated debris shall be cleaned up and properly disposed of by the Contractor to prevent the materials from entering or being carried into storm water conveyances. (9) When making sawcuts in pavement, use as little water as possible and perform during dry weather. Cover each storm drain inlet completely with filter fabric or plastic during the sawing operation and contain the slurry by placing straw bales, sandbags, or gravel dams around the inlets. After the liquid drains or evaporates, shovel or vacuum the slurry residue from the pavement or gutter and remove from site. Alternatively, a small onsite vacuum may be used to pick up the slurry as this will prohibit s lurry from reaching storm drain inlets.
(10) Pavement marking:
• Schedule pavement marking activities for dry weather. • Develop paint handling procedures for proper use, storage, and disposal of paints. • Transfer and load paint and hot thermoplastic away from storm drain inlets. • Provide drop cloths and drip pans in paint mixing areas. • Properly maintain application equipment.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
90 of 244
83 • Street sweep all grindings. Yellow thermoplastic grindings may require special handling as they may contain lead.
• Paints containing lead or tributyltin are considered a hazardous waste and must be disposed of properly.
• Use water based paints whenever possible. If using water based paints, clean the application equipment in a sink that is connected to the sanitary sewer. • Properly store leftover paints if they are to be kept for the next job, or dispose of properly.
(11) After the completion of the Work, the construction site shall be cleared of trash and debris and restored to a condition equal to or better than that existing before construction by completing all approved landscaping and permanent or post -construction se diment controls.
(b) Erosion Control Plan
Whenever it appears that the construction site will have grading during the rainy season, or as requested by the City Engineer, the Contractor shall be prepared to execute a rain event action plan based on implementation of BMPs as specified in the Project’s Erosion Control Plan.
The Contractor shall mark with a stencil, concrete stamp, or ceramic tile every storm drain inlet within the Project boundaries to indicate that no dumping is allowed in storm drainage facilities that discharge in the ocean. The stencil or tiles are available from the City Engineer, with five (5) Working Days advance notice. On curb inlets, the stencil shall be placed at the curb line on the inlet roof, the stamp should be placed on the inlet roof or in the sidewalk behind the inlet, and the tile shall be affixed to the gutter with pavement-marker adhesive or inset in the concrete in the center of the inlet opening.
On catch basins, the stencil, stamp, and tile shall be placed or imprinted next to the inlet grate. Extra concrete may be required next to the grate to accommodate the stencil, stamp, or tile dimensions.
3-12.6.5 Payment.
Replace the paragraphs in this subsection with the following:
All costs for the work required to comply with the requirements of this subsection shall be included in the bid item for Storm Water Pollution Prevention and Erosion Control as shown on the BID SCHEDULE. If no bid item is provided, the cost of the work required to comply with this subsection shall be considered as included in the prices bid for the various items of work.
3-13 COMPLETION, ACCEPTANCE, AND WARRANTY.
3-13.3 Warranty.
Replace the first paragraph in this subsection with the following:
The Work shall be warranted by the Contractor against defective materials and workmanship for a period of one (1) year, or longer as specified below:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
91 of 244
84 a) The warranty period for installed fiber optic cable shall be two (2) years. b) The warranty period for the Work under Section 500 must be at least three (3) years. c) The warranty period for LED signal modules requires at least three (3) years of manufacturer’s warranty.
d) The warranty period for LED luminaires requires at least ten (10) years of manufacturer’s warranty. Provide documentation verifying that the LED luminaire model(s) being offered for the Project are covered by the ten-year warranty.
The warranty period shall begin when the Work is accepted as complete by the Agency after the Notice of Completion has been recorded at the County Recorder’s Office.
Replace the last paragraph in this subsection with the following:
If at any time during the warranty period, or during the extended warranty period specified, the Engineer finds the Work, or any part of the Work, to be defective or not in conformance with the plans and specifications, whether or not manufactured, fabricated, installed, completed or overlooked and accepted by the Engineer, the Contractor must, in accordance with the Engineer’s written instructions and within the specified time limits, either correct the defective or non-conforming Work, or, if it has been re jected by the Engineer, remove it from the Site and replace it with non -defective and conforming Work.
The Engineer may determine in its sole discretion to accept defective work in lieu of requiring the Contractor to correct or remove and replace the d efective work. However, the Contractor must bear all di rect and indirect costs of the defective w ork, and the diminished value to the Project, as determined by the Engineer. If the Engineer’s acceptance of defective w ork occurs prior to Final Payment, the Engineer will issue a Change Order incorporating the necessary revisions in the Contract Documents with respect to the defective w ork and affording the Agency the appropriate decrease in the Contract Price.
If the Contractor fails to correct, remove, or replace defective work or non-conforming work within five (5) Working Days from the date of written notice from the Engineer, the Engineer may proceed expeditiously with any correction undertaken in accordance with this section. The Agency may remedy after five (5) Working Days from the date of written notice when the Contractor fails to correct the Work in accordance with the Contract Documents, or when he fails to comply with any other provision of the Contract Documents. If, in the opinion of the Agency, the non -conforming work or defective work creates a dangerous condition or requires immediate attention or correction to prevent further loss to the Agency or any other party, or to prevent interruption of operation of an y Agency service or any service of any other party, The Agency will attempt to give notice required by this paragraph. If the contractor cannot be contacted or does not comply with the Agency’s request for correction within a reasonable time determined by the Agency, then the Agency or other party may proceed to provide attention or make required corrections, and the cost of all correction or attention shall be charged to and paid for by the Contractor. The Agency may remedy immediately in the event of an emergency.
When undertaking remedial action under this section, the City may: exclude the Contractor from all or part of the Site; take possession of all or part of the Work, and suspend the Contractor’s Work and or Services; and incorporate into the Project all materials and equipment stored at the Site or for which the City has paid but the Contractor has stored elsewhere.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
92 of 244
85 The City will not allow an extension of the Contract Time or milestones because of any delay in the performance of the Project attributable to the City’s undertaking remedial action to correct Defective Work.
For Building Projects which require a certificate of occupancy, not including sewer and water facilities, if the Contractor fails to correct the defective work listed on the Agency’s “Punchlist” within forty-five (45) Working days after the Contract Time, he must reimburse the Agency for all costs to provide inspection services required to monitor Work beyond the forty-five (45) days. The Agency will bill the Contractor for the additional inspection at the Agency’s established rates.
If the Contractor completes the Project or portions of the Project prior to the Notice of completion (NOC), he must preserve equipment by developing and implementing a preventive maintenance program in compliance with manufacturer's recommendations.
The Contractor must repair or replace the traffic signal and lighting system equipment within seventy-two (72) hours after notification of defects by the Engineer.
The Contractor must pay for any claims, costs, losses, and damages incurred by the Agency in remedying any deficiency (e.g., all costs of repair or replacement of Defective Work and all costs of repair of any other Work on the Project destroyed or damaged by correction, removal, or replacement of your Defective Work).
Add the following paragraphs to this subsection:
Replacement of earthfill or backfill, where it has settled below the required finish surfaces, shall be considered part of repairs of defective work, and any repair of surfacing constructed by the Contractor, which becomes necessary because of settlement or ground movement, shall be likewise considered part of such repair work.
Any existing improvements which are damaged by the Contractor’s operations, or any new work, including concrete, which is cracked, chipped, discolored, improperly finished, heaved, vandalized, or for any other reason does not conform to the specifications, shall be replaced by the Contractor at no additional cost to the Agency.
The parties agree that no certificate given, with the exception of the certificate of final payment, shall be conclusive evidence of the faithful performance of the Contract, either in whole or in part, and that no payment shall be construed to be in acceptance of any defective work or improper materials.
Further, the certificate of final payment shall not terminate the Contractor’s obligations under his warranty herein above. The Contractor agrees that payment of the amount due under the Contract and the adjustments and payments due for any work done in accordance with any alterations of the same, shall release the Agency, the Agency’s Council and its officials, officers and employees from any and all claims or liability on account of work performed under the Contract or any alteration thereof.
No materials, supplies, or equipment for the Work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale contract or other agreement or supplier. The Contractor warrants clear and good title to all materials, supplies, and equipment installed and incorporated in the Work and agrees upon completion of all work to deliver the premises, together with all improvements and appurtenances constructed or placed thereon by the Contractor, and further agrees that neither t he Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
93 of 244
86 Contractor nor any person, firm or corporation furnishing any material or labor for any work covered by the Contract shall have any right to a lien upon the premises or any improvement or appurtenance thereon, provided that this shall not preclude the Contractor from installing metering devices or other equipment of utility companies the title of which is commonly retained by the utility company. Nothing contained in this article, however, shall defeat or impair the right of such persons furnishing materials or labor under any bond given by the Contractor for their protection, or any right under any law permitting such persons to look to funds due the Contractor, which are in the hands of the Agency. The provisions of this article shall be inserted in all subcontracts and material contracts, and notices of its provisions shall be given to all persons furnishing materials for the Work when no formal contract is entered into for such materials.
With respect to all warranties, express or implied, from Subcontractors, manufacturers, or suppliers for Work performed and materials furnished under this Contract, the Contractor shall:
a) Obtain for Agency all warranties that would be given in normal commercial practice; b) Require all warranties to be executed, in writing, for the benefit of the Agency or other parties; and
c) Enforce all warranties for the benefit of the Agency or other parties , unless otherwise authorized in writing by the Agency.
This subsection shall not limit the Agency’s rights under this Contract or with respect to latent defects, gross mistakes, or fraud. The Agency specifically reserves all rights related to defective work, including but not limited to the defect claims pursuant to California Code of Civil Procedure Section 337.15.
3-14 SITE EXAMINATION.
Add the following new subsection:
3-14 SITE EXAMINATION . The Contractor shall have the sole responsibility of satisfying itself concerning the nature and location of the Work, and the general and location conditions, such as, but not limited to, all other matters which could in any way affect the Work or the costs thereof. The failure of the Contractor to acquaint itself with all available information regarding any applicable existing or future conditions shall not relieve it from the responsibility for properly estimating the difficulties, responsibilities, or costs of successfully performing the Work according to the Contract Documents.
3-15 FLOW AND ACCEPTANCE OF WATER.
Add the following new subsection:
3-15 FLOW AND ACCEPTANCE OF WATER . Storm, surface, nuisance, or other waters may be encountered at various times during construction of the Work. Therefore, the Contractor, by submitting a Bid, hereby acknowledges that it has investigated the risk arising from such waters, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising there from.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
94 of 244
87 3-16 NOTICE OF THIRD PARTY CLAIMS.
Add the following new subsection:
3-16 NOTICE OF THIRD PARTY CLAIMS . Pursuant to Public Contract Code Section 9201, the Agency will provide Contractor with timely notification of the receipt of any third-party claim relating to the Contract. Contractor shall attempt to verify and resolve claims promptly.
3-17 SEPARATE CONTRACTS.
Add the following new subsection:
3-17 SEPARATE CONTRACTS. The Agency reserves the right to let other contracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.
To ensure proper execution of its subsequent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the work in place or discrepancies with the Contract Documents.
Contractor shall ascertain to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by the Agency in prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor exclusive occupancy at site of the Project.
Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any Contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer will decide which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so t hat contractors may proceed simultaneously. The Agency shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.
SECTION 4 – CONTROL OF MATERIALS
4-1 GENERAL.
Replace this subsection with the following:
4-1 GENERAL. It is the intent of the Agency in drafting the Contract Documents to accept only first class work, materials, parts, equipment and workmanship. All materials, parts and equipment furnished by Contractor for the Work shall be new, high grade, free from defects, of specified kind and fully equal to samples when such samples are required. Used or secondhand materials, parts and equipment may be used only if permitted by the Specifications. When the quality or kind of material or articles required under the Contract are not particularly specified, the Contractor shall provide those representing the best of their class or kind. Quality of work shall be in strict accordance with generally Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
95 of 244
88 accepted standards. Materials, parts and equipment shall be furnished in such quantities, kinds and at such times as to ensure uninterrupted progress of the Work.
The quality of m aterial, parts, equipment and work shall be subject to approval by the Engineer.
The Engineer shall have access to the Work at all times during construction, and shall be furnished with every reasonable facility for securing full knowledge with regard to the progress, workmanship and character of the materials, parts and equipment use d or employed in the Work. Materials and workmanship of a quality not conforming to the requirements of the Specifications shall be considered defective, and shall be subject to rejection. Defective work or material, whether in place or not, shall be remedied or removed and replaced by the Contractor, at its expense, and defective materials shall be removed from the Work site immediately, at the Contractor’s expense, when so directed by the Engineer.
Any work done beyond the lines shown on the Plans or established by the Engineer, or any Extra Work done without written authority, will be considered unauthorized and will not be paid for by Agency.
Upon Contractor’s failure to comply promptly with any order of the Engineer made under the provisions of this Section, the Engineer shall have authority to cause such defective or unauthorized work to be remedied or removed and replaced, and to deduct the costs thereof from any monies due or to become due the Contractor. If the Work is found to be in compliance with these Specifications, the Engineer will furnish the Contractor with a certificate to that effect.
No rejected materials, the defects of which have been subsequently corrected, shall be used until approval in writing has been given by the Engineer. Upon failure of the Contractor to comply with any order of the Engineer made under the provisions of this subsection, the Engineer shall have the authority to remove and replace defective materials and to deduct the cost of removal and replacement from any monies due or to become due the Contractor.
If, during the prosecution of the work, the Contractor fails to immediately correct the defective or non-conforming work upon notice, or fails to correct the defective or non-conforming work in a manner conforming to the Contract Documents, the Engineer may order the Contractor to stop all or part of the Project. The Agency’s right to stop the Project does not give rise to any duty on the Agency’s part to stop Work for the Contractor’s benefit or the benefit of any other party. The Contractor shall bear all direct and indirect costs and damages that result from the Agency’s stop work notice.
When removing asbestos products, the C ontractor shall comply with the requirements of Title 8, CCR, General Industry Safety Orders and Construction Safety Orders.
4-1.1 Agency-furnished Materials.
Add the following new subsection:
4-1.1 Agency-furnished Materials. The Agency may provide certain items (e.g. traffic signal poles, mast arms, meter pedestals, street lights, etc.) for use by the Contractor for this Project at no cost to the Contractor as described in the Special Provisions. The Contractor shall inspect the materials / equipment prior to submitting a bid and shall satisfy himself of the suitability of the materials / equipment for use on the Project, and include all costs in the bid. The Contractor shall provide all Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
96 of 244
89 hardware and any other materials, equipment and appurtenances necessary to use the Agency - furnished items in the Work.
Upon written request from the Contractor at least twenty-four (24) hours in advance, any materials / equipment furnished by the Agency for the Project shall be available to the Contractor to take delivery of the items during regular Public Works Department Working Hours at the Agency’s Public Works Yard at 1165 E. Taylor Street or the Agency’s Storage Yard at 2430 Lupine Hills Drive as designated by the Agency. The Contractor shall inspect the materials / equipment at time of pick -up and shall satisfy himself of the suitability and quantity of the materials / equipment for use on the Project. The Contractor shall provide loading at the Agency’s designated location, handling, transportation and delivery of the items to the Project site. The cost of handlin g and placing all materials / equipment after they are made available to the Contractor shall be considered as included in the Contract prices for items in connection with which they are used. No markup shall be applied to any material provided by the Agency.
The Contractor shall assume full responsibility for all Agency -furnished materials and/or equipment made available to him as soon as loading commences. Deductions will be made from any monies due to the Contractor to make good any shortages and deficienci es, from any cause whatsoever, which may occur after said materials and/or equipment have been furnished to the Contractor.
4-3 INSPECTION.
4-3.1 General.
Modify the first paragraph to read as follows:
4-3.1 General. Unless otherwise specified in these Specifications, inspection may be required at the source for such typical materials and fabricated items including, but not limited to, bituminous paving mixtures, structural concrete, precast concrete, street lighting poles, metal fabrication, metal casting, welding, concrete pipe manufacture, protective coating application, plastic liner, fiberglass tanks, plastic liner pipe, and similar shop or plant operations.
Modify the third sentence of the second paragraph to read as follows:
Special items of equipment such as designed electrical panel boards, large pumps, sewage plant equipment, etc., are subject to inspection at the source.
4-4 TESTING.
Add the following paragraphs to this subsection:
Geotechnical (soil) testing of fill materials, subgrade, subbase, and base will be conducted by the Agency and the Geotechnical Engineer. Geotechnical (soil) tests may include relative compaction tests, sand equivalents tests, sieve analysis, R-values, etc. The results shall be presented directly by the laboratory to the Engineer. No base, concrete or pavement shall be placed before the subgrade, subbase, base and fill have been compacted, tested and approved. The cost of any initial geotechnical Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
97 of 244
90 (soil) test shall be borne by the Agency. Additional geotechnical (soil) tests necessitated by a failure of one (1) or more of the initial tests shall be made by the laboratory at the expense of the Contractor.
The Contractor shall make allowances in his construction procedure to permit testing of the Work in progress by the Engineer and no additional compensation shall be paid to the Contractor for delays due to testing.
Testing of any cast -in-place structure or concrete surface improvement will be conducted by the Agency. Concrete tests may include slump tests, air content, and compressive strength. Any results shall be presented directly by the laboratory to the Engineer. The cost of any initial concrete test shall be borne by the Agency. Additional concrete tests necessitated by a failure of one (1) or more of the initial tests shall be made by the laboratory at the expense of the Contractor. The Contractor shall make allowances in his construction procedure to permit testing of the Work in progress by the Engineer and no additional compensation shall be paid to the Contractor for delays due to testing.
The Contractor shall maintain and secure all material samples on the Project site, available to the Engineer for inspection and evaluation during normal working hours.
All packaged, manufactured products / materials for use on the Work shall be delivered to the Project site in their original unopened containers, bearing thereon the manufacturer’s name and the brand name of the product.
Wherever any product / material is selected to be used on the Work, all such products or materials shall be of the same brand and manufacturer throughout the Work.
All products / materials shall be stored in such a manner that they will be completely protected from weather damage.
The C ontractor shall pay for all failing tests that the C ontractor or the A gency’s representative request in conformance with the referenced specifications or as enumerated in the supplementary provisions.
4-6 TRADE NAMES:
Add the following paragraphs to this subsection:
In accordance with the provisions of Section 3400 of the California Public Contract Code, the Contractor shall be provided a period of not less than seven (7) Working Days after award of the Contract for submission of data substantiating a request for a substitution of an "equal" item. Data submitted after this time period may be rejected by the Agency.
The Contractor shall substantiate his offer for use of substitute materials, processes, or equipment, which he considers to be equivalent to that indicated, by submitting thr ee (3) copies of a package of description, information, and performance data, showing the equality of the offered item, and such other necessary or related information as may be required by the Engineer (including, but not limited to, complete calculations, technical specifications, samples, or published documents relating to the perfor mance and physical characteristics of the proposed substitute) . The burden of proof as to the comparative quality and suitability of alternative material, process, or equipment shall Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
98 of 244
91 be the Contractor’s responsibility. Independent testing or evaluation at qualified test facilities, including destructive testing, may be required as a condition of acceptance. Life cycle costs of the substitute items must be equivalent to those of the items indicated. The Engineer may require the Contractor to furnish a special performance warranty or other surety with respect to any proposed substitute. The Engineer shall be the sole judge as to the comparative quality and suitability of the substitute items, and the Engineer’s decision shall be final.
The Contractor’s offer of the substitute items shall contain the following statements and/or information that shall be considered by the Engineer in evaluating the proposed substitution:
1. A statement that the evaluation, and acceptance or rejection of the proposed substitute, will not prejudice the Contractor’s completion of the Project in the specified time.
2. A statement as to whether or not acceptance of the proposed substitute will require a change in the Contract Documents.
3. A list identifying all variations of the proposed substitute from that specified.
4. A description of available maintenance, repair, and replacement service.
5. An itemized estimate of all costs or credits that will result directly or indirectly from acceptance of the proposed substitute, including redesign and claims from others.
4-9 REMOVAL OF INTERFERING OBSTRUCTIONS.
Add the following new subsection:
4-9 REMOVAL OF INTERFERING OBSTRUCTIONS. The Contractor shall remove and dispose of all debris, abandoned structures, tree roots and obstructions of any character met during the process of excavation, it being understood that the cost of said removals are made a part of the unit price bid by the Contractor under other various items of work.
4-10 PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY.
Add the following new subsection:
4-10 PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY. Any portions of curb, gutter, sidewalk or any other City improvement not identified for removal but damaged by the Contractor during the course of construction shall be replaced by the Contractor at the Contractor’s own cost, at no additional charge to the Agency. The cost of additional replacement of curb, gutter or sidewalk in excess of the estimated quantities shown in the B ID SCHEDULE and Specifications and found necessary during the process of construction (but not due to damage resulting from careles sness on the part of the Contractor during construction operations), shall be paid to the Contractor at the unit prices submitted in the Bid.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
99 of 244
92 SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES
5-3 LABOR.
5-3.1 General.
Add the following paragraphs to this subsection:
No contractor or subcontractor of any tier may be awarded a Contract for public work on a public works project or work on a public works project without proof of registration with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
Registrations under Section 1725.5 expire annually at the end of June, and Contractor is responsible for verifying the renewal status of each subcontractor, of any tier, working on this Contract, and providing City with an updated list of all subcontractors and their registration status.
Subcontractors who do not timely renew their registration must be removed from the job site until they are registered. The removal of a subcontractor for failure to be registered shall not be cause for any extension of time or additional compensation of any nature under the Contract.
In accordance with the requirements of Section 1771.1(j) of the Labor Code, the Agency will observe and enforce any Stop Order issued by the Labor Commissioner where a contractor or subcontractor engages in the performance of any public work Contract without having been registered in violation of the requirements of Section 1725.5 or this section, and will not allow the unregistered contractor or the unregistered subcontractor to work on any public works until the unregistered contractor or unregistered subcontractor is registered.
In accordance with the provisions of Section 1771.4(a)(1) of the California Labor Code, this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
In accordance with the provisions of Section 1771.4(a)(2) of the California Labor Code, the prime contractor shall post job site notices, as prescribed by regulation.
5-3.2 Prevailing Wages.
Replace this subsection with the following paragraphs:
Pursuant to the Vista City Charter and the Vista Municipal Code, payment of prevailing wages and compliance with the California Labor Code Sections 1770 et seq IS required for this Project.
State prevailing rates of wages and classifications, as applicable to this contract, are ascertained and adopted by the State of California, Director of Industrial Relations (DIR) pursuant to California Labor Code Article 2 of Chapter 1 of Part 7 of Division 2, as amended, which is made a part herein, and the provisions of Section 1777.5 and 1 777.6 of the Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under him. Certified payroll on an approved compliance format is required for all work under this Contract.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
100 of 244
93 Pursuant to Section 1773 of the Labor Code, the general prevailing wage rates in the county, or counties, in which the Work is to be done have been determined by the Director of the California Department of Industrial Relations (DIR). These wages are set forth in the General Prevailing Wage Rates for this Project, available at the California Department of Industrial Relations’ (DIR) Internet URL website link at:
http://www.dir.ca.gov/DLSR/PWD
When the Contractor intends to use a craft or classification not shown in the wage provisions, it will be required to pay the wage rate of that craft or classification most closely related to that craft or classification as shown on the wage provisions. In case of disagreement between the Contractor and the Agency, the Engineer shall decide the prevailing wages for the labor.
The Contractor shall comply with the provisions of California Labor Code Section 1773.8 which requires the payment of travel and subsistence payments to each worker needed to execute the work to the extent required by law.
The Contractor shall, as a penalty to the Agency, forfeit not more than fifty dollars ($50) for each calendar day, or portion thereof, for each worker paid less than the prevailing rates as determined by the Director of Industrial Relations for the work or craft in which the worker is employed for any public work done under the Contract by Contractor or by any subcontractor.
5-3.2.1 Apprentices.
Add the following new subsection:
5-3.2.1 Apprentices. Attention is directed to the provisions of Section 1777.5 and 1777.6 of the labor Code concerning the employment of apprentices by the Contractor or any Subcontractor under him/her. The Contractor and any Subcontractor under him/her shall comply with the requirements of said sections in the employment of apprentices.
The Agency will provide notice to the Department of Industrial Relations of any public works Contract using the online PWC -100 form. The online PWC -100 form is also transmitted to the Department of Apprenticeship Standards (DAS) to inform them of the awar d of a contract. The Contractor and each subcontractor shall also submit a “Public Works Contract Award Information” form (DAS form 140) to inform all applicable apprenticeship committees of the award of a contract.
The Contractor and each subcontractor shall provide written evidence to the Agency that the request for dispatch of apprentices to the training agencies has been completed using the DAS 142 form .
Contributions to a training fund, or the California Apprenticeship Council, for every worker on the job, are required.
The Contractor and all subcontractors shall submit to the Agency copies of the “Public Works Contract Award Information” forms (DAS form 140) and all requests for dispatch of apprentices on the DAS 142 form. These DAS forms are available from the California Department of Industrial Relations’ (DIR) Division of Apprenticeship Standards website link at:
http://www.dir.ca.gov/DAS/das.html
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
101 of 244
94 The Contractor is not required to use apprentices on projects under thirty thousand Dollars ($30,000).
5-3.3 Payroll Records.
Add the following paragraph to this subsection:
In accordance with the requirements of the California Prevailing Wage Laws, Contractor and each Subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time, and overtime hours w orked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the work. The payroll records shall be certified and submitted to the DIR electronically in accordance with the California Prevailing Wage Laws. Contractor shall be subject to, and fully comply with, all California Prevailing Wage Laws, including, but not limited to, those pertaining to the maintenance and inspection of certified payroll rec ords. Copies of the record of wages paid shall be certified by the Contractor and submitted to the DIR with each progress payment request. In the event of noncompliance with the requirements of this section for payroll records, and upon the request of the DIR, contractor penalties shall be withheld from Contract payments.
5-4 INSURANCE.
5-4.1 General.
Delete this subsection in its entirety and replace with the following:
The Contractor shall procure and maintain for the duration of the Contract, and for 1 year thereafter, insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his agents, representatives, employees, or subcontractors.
Without limiting the Contractor's indemnification, it is agreed that the Contractor shall maintain in force at all times the following policy, or policies, of insurance covering its operations:
(a) Commercial General Liability (CGL) -- Insurance Work Office Form CG 00 01 covering CGL on an “occurrence” basis, including products, completed operations, property damage, bodily injury, and personal & advertising injury with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this Project/location or the general aggregate limit shall be twice the required occurrence limit.
(b) Automobile Liability -- Insurance Work Office Form Number CA 0001 covering Code 1 (any auto), with limits no less than $2,000,000 per accident for bodily injury and property damage. Any and all mobile equipment, including cranes, which are not covered under Automobile Liability, shall have said coverage provided for under Comprehensive General Liability policy.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
102 of 244
95 If the contractor maintains higher limits than the minimums shown above, the City requires and shall be entitled to coverage for the higher limits maintained by the contractor. Any available insurance proceeds in excess of the specified minimum limits of i nsurance and coverage shall be available to the City.
Any deductibles or self -insured retentions must be declared to and approved by the City. At the option of the City, either: the contractor shall cause the insurer shall reduce or eliminate such deductibles or self -insured retentions as respects the City, i ts officers, officials, employees, and volunteers; or the Contractor shall provide a financial guarantee satisfactory to the City guaranteeing payment of losses and related investigations, claim administration, and defense expenses.
Certificates of insurance and a complete copy of the insurance policies evidencing the coverages required by the clauses set forth above shall be filed with the Agency prior to the effective date of this Agreement. This is a condition precedent to the for mation of any obligation by the Agency to compensate the Contractor under this Agreement.
The insurance policies are to contain, or be endorsed to contain, the following provisions:
1. The City, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operation s and automobiles owned, leased, hired, or borrowed by or on behalf of the Contractor. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10 and CG 20 37 forms if later revisions used), unless otherwise approved in advance by City.
2. For any claims related to this Project, the Contractor’s insurance coverage shall be primary insurance as respects the City, its officers, officials, employees, and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.
3. Each insurance policy required by this clause shall provide that coverage shall not be canceled, except with notice to the City.
Contractor may submit evidence of Builder’s Risk insurance in the form of Course of Construction coverage. Such coverage shall name the City as a loss payee as their interest may appear. If the Project does not involve new or major reconstruction, at the option of the City, an Installation Floater may be acceptable. For such Projects, a Property Installation Floater shall be obtained that provides for the improvement, remodel, modification, alteration, conversion or adjustment to existing buildings, structures, processes, machinery and equipment. The Property Installation Floater shall provide property damage coverage for any building, structure, machinery or equipment damaged, impaired, broken, or destroyed during the performance of the Work, including du ring transit, installation, and testing at the City’s site.
If any coverage required is written on a claims-made coverage form:
1. The retroactive date must be shown, and this date must be before the execution date of the Contract or the beginning of Contract work.
2. Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of Contract work.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
103 of 244
96 3. If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the Contract effective date, or start of work date, the Contractor must purchase extended reporting period coverage for a minimum of five (5) years after completion of Contract work.
4. A copy of the claims reporting requirements must be submitted to the City for review.
5. If the services involve lead-based paint or asbestos identification/remediation, the Contractors Pollution Liability policy shall not contain lead-based paint or asbestos exclusions. If the services involve mold identification/remediation, the Contractors Pollution Liability policy shall not contain a mold exclusion, and the definition of Pollution shall include microbial matter, including mold.
Insurance is to be placed with insurers with a current A.M. Best rating of no less than A: VII, unless otherwise approved by the City.
Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of the City for all work performed by the Contractor, its employees, agents and subcontractors.
Contractor shall furnish the City with original certificates and amendatory endorsements, or copies of the applicable insurance language, effecting coverage required by this Contract. All certificates and endorsements are to be received and approved by the City before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Contractor’s obligation to provide them. The City reserves the right to require complete, certified copies of all required insurance policies, including endorsements, required by these specifications, at any time.
Contractor shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure that City is an additional insured on insurance required from subcontractors. For CGL coverage, subcontractors shall provide coverage with a format least as broad as CG 20 38 04 13.
Contractor agrees to assist in every manner possible in the reporting and investigation of any accident and, upon request, to cooperate with all interested insurance carriers in the handling of any claim by securing and giving evidence and obtaining the at tendance of witnesses as required for the resolution of any claim or lawsuit.
Nothing contained in these insurance requirements is to be construed as limiting the type, quality or quantity of insurance that the Contractor should maintain, or the extent of the Contractor's responsibility or liability for payment of damages resulting for the Contractor's operations under the contract. The carrying of the insurance specified herein shall not be construed to be a limitation of liability on the part of the Contractor or as a matter of law.
5.4.2 General Liability Insurance
Delete this subsection in its entirety
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
104 of 244
97 5.4.4 Auto Liability Insurance
Delete this subsection in its entirety
5-4.5 Failure to Procure Insurance.
Add the following new subsection:
5-4.5 Failure to Procure Insurance. Contractor’s failure to procure or maintain required insurance program shall constitute a material breach of Contract under which the Agency may immediately terminate the Contract or, at its discretion, procure or renew such insurance to protect the Agency’s interests and pay any and all premiums in connection herewith, and recover all monies so paid from Contractor, or deduct all monies so paid from payments due Contractor.
5-6 PATENT FEES OR ROYALTIES.
Delete the subsection in its entirety and replace with the following:
The Contractor shall absorb in its Bid all costs arising from the use of patented materials, equipment, devices, or processes used in or incorporated in the Work and agrees to indemnify and hold harmless the Agency and its duly authorized representatives, from all suits of law, or actions of every nature for or on account of the use of any patented materials, equipment, devices or processes.
5-7 SAFETY.
5-7.1 Work Site Safety.
5-7.1.3 Safety for Night Work.
Add the following new subsection:
5-7.1.3 Safety for Night Work. The delineation of the Work that will need to be performed at night during certain phases of the Project shall be indicated on the Traffic Control Plans. The Contractor shall conduct all work in a safe manner, but shall provide additional safety measures at night to ensure the safety of the public, the work force, Agency and utility staff, and anyone else who passes through or works in the Project area. All light fixtures shall be mounted and directed in a manner precluding glare to approaching traffic.
The Contractor shall submit a detailed written night work plan, which includes night-related traffic control equipment and materials, site safety rules, and safety training materials.
Payment for performing all work necessary to provide safety measures for night work shall be included in the bid items for which night work is required.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
105 of 244
98 5-7.2 Safety Orders.
5-7.2.1 General.
Add the following paragraphs to this subsection:
In accordance with generally accepted construction practices, the Contractor shall be solely and completely responsible for conditions of the job site, including safety of all persons and property during performance of the Work, and the Contractor shall fully comply with all OSHA, State and Federal laws, rules, regulations and orders relating to safety of the public and workers.
Whenever, in the opinion of the Engineer, an emergency exists against which the Contractor has not taken sufficient precaution for the public safety, protection of utilities and protection of adjacent structures or property which may be damaged by the Contractor’s operations, and when in the opinion of the Engineer, immediate action shall be considered necessary in order to protect the public or property adjacent to the Contractor ’s operations under this contract, the Engineer will order the Contractor to provide a remedy for the unsafe condition. If the Contractor fails to act on the situation, the Engineer may provide suitable protection to said interests by causing such work to be done and material to be furnished as may be necessary.
The cost and expense of said labor and material, together with the cost and expense of such repairs as are deemed necessary, shall be borne by the Contractor. All expenses by the Agency for emergency repairs will be deducted from the progress payments and the final payments due to the Contractor. However, if the Agency does not take such remedial measures, the Contractor is not relieved of the full responsibility for public safety.
The acceptance by the Agency of a copy of the State of California Department of Industrial Relations Division of Occupational Safety & Health (CalOSHA) permit to perform excavation or trench work shall in no way be construed to impose tort liability on the Agency or any of its officers or employees by reason of any damage to person, including death or property damage resulting from or arising out of the use of such plan, and the Contractor shall be fully responsible for any such damage and shall indemnify and hold harmless the Agency, its officers and employees from any loss or liability resulting from the use of such plan.
5-7.8 Steel Plate Covers.
5-7.8.1 General.
Add the following paragraphs to this subsection:
The surface of all structural steel plate covers used by the Contractor to bridge any excavation in the public right-of-way shall have a non-skid coating (“Skid Guard” or equal) with a minimum coefficient of friction = 0.35 per California Test Method 342 for all traffic steel plate covers within the traveled roadway of streets and alleys, and a minimum coefficient of friction of 0.50 per ASTM C 1028 for those steel plate covers in pedestrian crosswalks or accessible areas. The non-skid coating shall be black.
When required by the Engineer, the Contractor shall certify in writing to the Agency that the steel plate covers to be used in the Work meet the required static coefficient of friction. Also, when required by the Engineer, the Contractor shall have the steel plate covers to be used in the Work tested in accordance with the above standards for the verification of the required static coefficient of friction.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
106 of 244
99 Testing shall be done by an independent laboratory approved by the Engineer. The Contractor shall pay for any costs associated with the testing of the steel plate covers.
5-8 RESPONSIBILITY FOR DAMAGE.
Add the following new subsection:
5-8 RESPONSIBILITY FOR DAMAGE. In addition to the provisions of Subsection 5-4 (“INSURANCE of the Standard Specifications as between the Agency and the Contractor, the Contractor shall take and assume all responsibility for the Work as stated herein and/or shown on the Plans.
The Contractor shall bear all losses and damages directly or indirectly resulting to him, to the Agency, the Engineer, their officers, employees, and agents, or to others on account of the performance or character of the work, unforeseen difficulties, accidents or any other causes whatsoever.
The Contractor shall assume the defense of and indemnify and save harmless the Agency, the Engineer, their officers, employees, and agents respectively from all claims, loss, damage, injury and liability of every kind, nature, and description, directly or indirectly arising from the performance of the Contract or work, regardless of responsibility for negligence; and from any and all claims, loss, damage, injury, and liability, howsoever the same may be caused, resulting directly or indirectly from the nature of the work covered by the Contract, regardless of responsibility for negligence.
The Agency does not, and shall not; waive any rights against the Contractor which it may have be reason of the aforesaid hold harmless agreements, because of the acceptance by the Agency or deposit with the Agency by Contractor, of any insurance policies required herein or as described in Subsection 5-4. The aforesaid hold harmless agreement by Contractor shall apply to all damages and claims for damages of every kind suffered, or alleged to have been suffered by reason of any of the aforesaid operations of Contractor, or any Subcontractor, regardless of whether or not such insurance policies are determined to be applicable to any of such damages or claims for damages.
No act by the Agency, Engineer or their representatives in processing or accepting any plans, in releasing any bond, in inspecting or accepting any work, or of any other nature, shall in any respect relieve the Contractor or anyone else, from any legal responsibility, obligat ion or liability he might otherwise have.
5-9 INDEMNIFICATION.
Add the following new subsection:
5-9 INDEMNIFICATION. Contractor shall defend (with counsel of Agency’s choosing), indemnify and hold the Agency, its officials, officers, agents, employees, and representatives free and harmless from any and all claims, demands, causes of action, costs, expenses, liabilities, losses, damages or injuries, in law or equity, regardless of whether the allegations are false, fraudulent, or groundless, to property or persons, including wrongful death, to the extent arising out of or incident to any acts, omissions or willful misconduct of Contractor, its officials, officers, employees, agents, consultants Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
107 of 244
100
and contractors arising out of or in connection with the performance of the Work or this Contract, including claims made by Subcontractors for nonpayment, including without limitation the payment of all consequential damages and other related costs and exp enses. Contractor shall defend, at Contractor’s own cost, expense and risk, with counsel of Agency’s choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or instituted against Agency, its officials, officers, agents, employees and representatives. To the extent of its liability, Contractor shall pay and satisfy any judgment, award or decree that may be rendered against Agency, its officials, officers, employees, agents, employees and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse Agency, its officials, officers, agents, employees and representatives for any and all costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code Section 2782.
5-10 EMERGENCY PHONE NUMBERS.
Add the following new subsection:
5-10 EMERGENCY PHONE NUMBERS. The Contractor shall provide the Engineer an emergency contact name and telephone number prior to the start of the Work that may be used to contact the Contractor in the event of an emergency for the duration of the Contract. Contractor shall also keep a list of emergency telephone numbers on the job site. In the case that more than ten (10) employees are on the job site at any time, said list shall be posted on a bulletin board, to be supplied and installed on the job site by the Contractor in a location visible and accessible to all employees.
The following emergency telephone numbers are listed for the convenience of the Contractor to assist in complying with these requirements:
AGENCY PHONE NUMBER
City of Vista Fire Department (North County Dispatch) 858-756-3006 City of Vista Fire Department (Emergency) 911
San Diego County Sheriff’s Office (Emergency) 911
Tri-City Medical Center, 4002 Vista Way, Oceanside, CA 92056 911 San Diego Gas and Electric (Gas Emergency) 800-611-7343 San Diego Gas and Electric (Electrical Emergency) 800-411-7343
5-11 DOCUMENT RETENTION & EXAMINATION.
Add the following new subsection:
5-11 DOCUMENT RETENTION & EXAMINATION . In accordance with Government Code Section 8546.7, records of both the Agency and the Contractor shall be subject to examination and audit by the State Auditor General for a period of three (3) years after final payment. Contractor shall make available to the Agency any of the Contractor’s other documents related to the Project immediately upon request of the Agency.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
108 of 244
101
In addition to the State Auditor rights above, the Agency shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Contractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to the Agency, for a period of four (4) years after final payment.
5-12 STATE LICENSE BOARD NOTICE.
Add the following new subsection:
5-12 STATE LICENSE BOARD NOTICE. Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of th e date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board , P.O. Box 26000, Sacramento, California 95826.
SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK.
6-1.1 Construction Schedule.
Delete this subsection in its entirety and replace with the following:
6-1.1 Construction Schedule. Within ten (10) Working Days after execution of the Contract or at the Pre-Construction Meeting, and prior to the commencement of work, the Contractor shall submit its proposed construction schedule to the Engineer using a scheduling program (e.g. Microsoft Project, Oracle’s Primavera or other approved equal program capable of producing the required information).
The construction schedule shall be in the form of a tabulation, bar or Gantt chart, or graph satisfactory to the Engineer, and in sufficient detail to show chronological rel ationship of all activities on the Project. Said activities include, but are not limited to, estimated start and finish dates of all tasks that make up each bid item , submittal of shop drawings to the Engineer for approval, procurement of materials, and scheduling of equipment. Along with the construction schedule, the C ontractor shall submit a cash -flow projection showing the anticipated amount of each monthly payment that will become due the Contractor in accordance with the construction schedule.
The Contractor shall schedule and stage the Work on all streets to cause the least possible inconvenience to vehicular traffic (including busses and trash vehicles) , bicyclists, pedestrians, adjacent businesses, local residences and schools.
The Contract time listed in the Specifications is the Agency’s best estimate of how long it will take to complete the Work. The construct ion schedule shall reflect all C ontract requirements, shall recognize the requirements of Subsection 402-5 (“DELAYS DUE TO UTILITY CONFLICTS .”), and shall Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
109 of 244
102
reflect completion of all work under the contract, including Punchlist items, in the specified time and in accordance with the Project Specifications and Plans. No schedule shall call for completion of the Project before or after the Contract completion date. The Project owns the float time and is not for the exclusive benefit of any Party. As such, liability for delay of the project completion date rests with the party actually causing the delay to the project completion date. By way of the Contractor assigning activity durations and proposing the sequence of the work, the Contractor hereby agrees to utilize sufficient and necessary management and other resources to perform the work in accordance with the construction schedule.
A Notice to Proceed shall be issued after the Pre-Construction Meeting, provided the Storm Water Pollution Prevention Plan (SWPPP) and the Construction Staging / Traffic Control Plan have been submitted by the Contractor and accepted by the Engineer, and all other appropriate Contract requirements are fulfilled. The Work shall start within ten (10) Working Days thereafter, and shall be diligently prosecuted to completion within the time provided in the Project Specifications.
For projects of forty-five (45) Working Days or more, the Contractor shall submit to the Engineer an updated construction schedule each month, showing the actual progress of the Work, as part of the Partial Payment request. Monthly progress payments are conditioned upon the Engineer receiving from the Contractor the monthly schedule update. Schedule updates must accurately reflect the “as- built” schedule. All changes to the schedule shall be highlighted or otherwise identified. Approved Change Orders shall also be incorporated in the updated schedule. It is highly recommended that a narrative be included with each update. The narrative should include a description of any logic changes made to the Project, a commentary as to gains and losses to critical and near critical activities, and a quantificati on of the gains and losses to the critical path. Failure to provide an updated construction schedule may result in withholding Contract payments until one is submitted.
If the Contractor desires to make a major change in the method of operations after commencing construction, or if the schedule fails to reflect the actual progress of the Work for any reason, the Contractor shall submit to the Engineer a revised construction schedule in advance of beginning revised operations. In the event that an action either by the Agency or the Contractor results in a delay to the schedule, it is beneficial if the parameters pertaining to that action are recorded as they happen.
6-1.3 Pre-Construction Meeting.
Add the following new subsection:
6-1.3 Pre-Construction Meeting. A Pre-Construction Meeting shall be scheduled after the award and prior to construction. The Contractor (Principal and Project Superintendent) and any subcontractor for five percent (5%) or more of the work shall attend and be prepared to provide or discuss the following information:
a) Construction schedule
b) Subcontractors
c) City of Vista Stormwater Permit and Storm Water Pollution Prevention Plan (SWPPP), if required d) Traffic Control Plans
e) Survey requirements
f) Materials and delivery schedule
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
110 of 244
103
g) Local phone numbers for supervisory personnel
h) List of Emergency phone numbers (see Subsection 7-17 of these Specifications) i) Required permits
j) Coordination with other agencies
The Construction Schedule to be provided shall be as described in Subsection 6-1.1 (“Construction Schedule.”) of these Supplementary General Provisions.
6-3 TIME OF COMPLETION.
6-3.1 General.
Replace this subsection with the following:
6-3.1 General. The Contractor shall complete all portions of the Work , including Punchlist items, in accordance with the terms and conditions of the Contract Documents, within 95 working days from the date of the Notice to Proceed. Construction on the Project shall begin within ten (10) Working Days of the Notice to Proceed and progress in good faith towards completion without unnecessary delay.
The Contractor must work diligently to complete all Punchlist items within twenty (20) Working Days after the Engineer provides the Punchlist.
During the course of construction of the Work, the Agency may require the Contractor to complete portions or phases of the Project, including backfill, compaction, testing, paving and site cleanup, before the Contractor will be allowed to proceed with other portions or phases of the Project. The specific requirements and limits, if necessary for this Contract, are either specified in the Special Provisions, shown on the construction drawings, or shall be determined by the Engineer.
6-3.3 Working Days / Hours.
Add the following new subsection:
6-3.3 Working Days / Hours. Unless otherwise specified, the Contractor’s activities shall be confined to normal working hours between 7:00AM and 5:00PM, Monday through Friday. Lane closures will be confined to the hours between 8:30AM and 3:30PM, Monday through Friday.
No work shall be done on Saturdays, Sundays, or holidays without authorization by the Engineer.
Deviation from these non-Working Days will not be permitted without the prior consent of the Engineer except in emergencies involving immediate hazard to persons or property.
Deviation from these working days and hours will not be permitted without the prior consent of the Engineer except in emergencies involving immediate hazard to persons or property. In the event of either a requested or emergency deviation during non-Working Days / Hours, overtime inspection fees will be charged against the Contractor. The overtime inspection fees will be calculated at overtime rates and will be deducted from any amounts due the Contractor.
Other conditions such as pedestrian access and the presence of schools or other special traffic and pedestrian generating facilities may affect the working hours.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
111 of 244
104
6-4 DELAYS AND EXTENSIONS OF TIME.
6-4.2 Extensions of Time.
Add the following paragraph to this subsection:
Delays to the project caused by labor disputes or strikes involving trades not directly related to the project, or involving trades not affecting the project as a whole shall not warrant an extension of time.
Daily charges for time extensions or delays from other causes shall be limited to negotiated amounts, or if no amounts are agreed upon, shall not exceed those charges documented to Agency’s satisfaction for additional labor and material costs associated with the delay, and an amount not exceeding 10% thereof for overhead and profit.
6-4.4 Written Notice and Report.
Replace the paragraph in this subsection with the following:
6-4.4 Written Notice and Report. If the Contractor desires payment for a delay as specified in Subsection 6-4.3 (“Payment for Delays.”), or an extension of time, it shall file with the Agency a written request and report of cause within ten (10) Working Days after the beginning of the event or occurrence giving rise to the delay. The written notice shall include a statement or estimate of the time extension or compensation being requested, documents supporting the request, including but not limited to eviden ce of all facts supporting the alleged claim and a current schedule showing the impact of the event or occurrence on the critical path. The request for payment or extension must be made at least fifteen (15) Working Days before the specified completion date. Failure by the Contractor to file these items within the times specified will be considered grounds for refusal by the Agency to consider such request.
By submitting a request for compensation or time extension, the Contractor agrees to make all books and records, including original bid estimates, subcontracts, daily reports, and correspondence, available to the Agency for review. The Contractor also agr ees to include this requirement in all subcontracts.
6-6 SUSPENSION OF THE WORK.
6-6.1 General.
Replace this subsection with the following:
6-6.1 General. The Engineer shall have the authority to suspend the Work, wholly or in part, for such period as the Engineer may deem necessary, due to unsuitable weather or to such other conditions (including an act of God or Force Majeure) as are considered unfavorable for the suitable prosecution of the Work, or for such time as the Engineer may deem necessary due to the failure on the part of the Contractor to carry out orders given or to perform any provisions of the Work. The Contractor shall immediately comply with the written order of the Engineer to suspend the Work wholly or in part and shall not resume the Work until ordered to do so in writing by the Engineer. Such suspension shall be without liability to the Contractor on the par t of the City except as otherwise specified in Subsection 6-4.3 (“Payment for Delays.”).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
112 of 244
105
In the event a suspension of work is ordered because of failure on the part of the Contractor to carry out orders given or to perform any provisions of the Work, such suspension of work shall not relieve the Contractor of his responsibility to complete the Work within the time limit set forth herein and shall not be considered cause for extension of the time for completion and, further, such suspension of work shall not entitle the Contractor to any additional compensation.
If the work is suspended or otherwise not continuously prosecuted for any cause whatsoever, within or without the time for completion, the Contractor shall, at his sole cost and expense, remove and replace all or any portion of the work already completed and inspected which Agency, at its sole discretion, could have been damaged during the suspension of work.
6-9 LIQUIDATED DAMAGES.
Replace this subsection with the following:
6-9 LIQUIDATED DAMAGES. Failure of the Contractor to complete the Work within the time allowed will result in damages being sustained by the Agency. For each consecutive working day in excess of the time specified for completion of Work, as adjusted in accordance with Subsection 6-4 (“DELAYS AND EXTENSIONS OF TIME .”), the Contractor shall pay to the Agency, or have withheld from monies due the Contractor, the sum of five hundred dollars ($500.00)
Execution of the Contract shall constitute agreement by the Agency and Contractor that the sum of five hundred dollars ($500.00) per working day is the value of the costs and actual damage caused by the failure of the Contractor to complete the Work within the allotted time. Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due the Contractor if such delay occurs.
SECTION 7 – MEASUREMENT AND PAYMENT
7-3 PAYMENT.
7-3.1 General.
Add the following paragraph to this subsection:
Except as may otherwise be provided in specific instances, nothing in the Contract shall be construed as vesting in the Contractor any property, any material, article or structure existing at the time of the award of Contract within the area in which the Work is to be done or in any material, article or structure subsequently furnished for the Work by the Agency, or in any material, article, structure or Work furnished or performed by the Contractor after having been accounted for on an approved estimate supporting the Contractor's demand for payment as provided in Subsection 7-3 (“Payment.”) of the Greenbook. In the latter event any such material, article, structure or Work shall become the property of the Agency after being so accounted for.
7-3.2 Partial and Final Payment
Replace the fifth paragraph of this subsection with the following:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
113 of 244
106
Pursuant to Section 22300 of the California Public Contract Code, the Contractor may substitute securities for any money held by the Agency to ensure performance of the Contract. At the request and expense of the Contractor, securities equivalent to the amount withheld shall be d eposited with the Agency, or with a state or federally chartered bank as an escrow agent, who shall return such securities to the Contractor upon satisfactory completion of the Contract. Deposit of securities with an escrow agent shall be subject to writt en Contract in accordance with the provisions of Section 22300 of the California Public Contract Code. For purposes of the escrow agreement, the Agency shall not certify that the Contract has been completed until at least forty five (45) calendar days after filing by the Agency of a Notice of Completion. Securities eligible for investment under this Section shall be limited to those listed in Section 16430 of the California Government Code, bank or savings and loan certificates of deposit, interes t bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed upon by the Contractor and the Agency.
Add the following paragraphs to this subsection:
Requests for partial payments shall be submitted in a form satisfactory to the Agency. At a minimum, the form shall include all bid items, itemized breakdowns of lump sum bid items from the schedule of values (provided by Contractor), unit or lump sum prices bid, the quantities of each bid item for the current and past invoices, the dollar amount of each bid item, a total amount, and the name, address and phone number of the Contractor.
The Contractor shall meet with the Engineer to field measure quantities, and if an agreement is NOT reached, the disputed quantities shall be documented at that time. The Contractor shall not include in his invoice any quantities that have not been approv ed by the Engineer. The Engineer will not be required to pay for any disputed quantities of work until an agreement is reached with respect to the actual quantity in place. The Engineer may make payments for disputed quantities of work based on his own estimate, until such time that an agreement is reached.
The Agency will make partial payments in accordance with Section 20104.50 of the Public Contract Code, and these specifications. The Agency will pay progress payments within thirty (30) calendar days of receipt of an undisputed, complete and properly prepared payment request from the Contractor, or pay interest to the Contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Any payment request determined not to be a proper payment request suitable for payment shall be returned to the Contractor as soon as practicable, but not later than seven (7) calendar days, after receipt.
As part of the monthly request for partial payment, the Contractor shall submit:
1] A list of all subcontractors who worked on the project, along with their PWC Registration Number, so the Agency can ensure that all contractors and subcontractors are registered as required by Labor Code Section 1771.1;
2] Conditional and unconditional lien releases for the Contractor and all subcontractors; 3] An updated construction schedule (showing actual progress of the Work); 4] The Record Drawings (updated to indicate all changes made up to the end of the billing period). 5] Certified payroll records to the Labor Commissioner’s Office;
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
114 of 244
107
Monthly progress payments are conditioned upon the Agency having received from the Contractor the monthly schedule update and other specified documents.
Contractor shall provide to City, as a condition precedent to the payment of Contractor’s final retention, a complete list of all subcontractors who have worked on the Project, including their PWC Registration Numbers. This list must be provided at least 30 days prior to the payment of the final retention and shall be submitted under penalty of perjury.
The Agency is required by State Law to withhold final payment to the Contractor until at least 30 days after PWC-100 information has been submitted to the DIR, including the list of subcontractors who worked on the Project.
A prime contractor or subcontractor shall pay any subcontractor not later than ten (10) Working Days of receipt of each progress payment for satisfactory performance in accordance with the provision in Section 7108.5 of the California Business Code concerning prompt payment to subcontractors. The ten (10) Working Days is applicable unless a longer period is agreed to in writing.
Any delay or postponement of payment over thirty (30) calendar days may take place only for good cause and with the Agency’s prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanction, and other remedies of that section.
The Agency will hold retainage from the prime contractor and will make prompt and regular incremental acceptances of portions, as determined by the Agency of the Contract work, and pay retainage to the prime contractor based on these acceptances. The prime contractor, or subcontractor, shall return all monies withheld in retention from a subcontractor within seven (7) calendar days after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the Contract work by the Agency.
7-3.3 Delivered Materials.
Add the following paragraph to this subsection:
Progress payments may include payment for specialty materials that will remain permanent features of the Work, not incorporated in the Work, but delivered and suitably stored at the site or at another location, insured and bonded by the Contractor and agreed to, in writing, by the Engineer.
Payment for stored materials will be based on a cost breakdown, acceptable to the Engineer, indicating the value and installation costs of such materials, provided each individual item has a value of more than five-thousand dollars ($5,000). The Agency will pay a maximum of seventy-five percent (75%) of the value of the material, until such time as the material is permanently installed in the Work. The Contractor shall submit a bill of sale, invoice, or other documentation warranting that the Contractor has received the materials free and clear of liens, charges, security interests, and encumbrances, and evidence that the materials and equipment are covered by appropriate property insurance.
7-3.4 Mobilization.
Delete this subsection in its entirety and replace with the following:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
115 of 244
108
7-3.4 Mobilization and Demobilization. Mobilization and Demobilization shall consist of preparatory work and operations, including, but is not limited to those necessary for the move-on and move-off operations such as:
1] Supplying, maintaining, and finally removing temporary facilities; including portable field office, sanitary facilities, electric power, water, telephone and other utilities, enclosures for storage of construction equipment, products / materials and incidentals;
2] Furnishing all insurance, bonds, licenses, materials, tools, equipment and incidentals involved in mobilization and preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidental to the project; for all other facilities, sureties, work and operations which must be performed or costs incurred prior to beginning work or various contractor items on or off the project site;
3] Making arrangements for construction personnel vehicle parking;
4] Application and acquiring permits from other agencies as required for the Project;
5] For other items not directly related to the bid items.
Payment for Mobilization and Demobilization shall be paid by the lump sum price bid as shown on the BID SCHEDULE. If the Mobilization and Demobilization bid item states a maximum percentage of total base bid on the BID SCHEDULE, the Agency reserves the right to conform the bid item price to the maximum stated percentage. This bid item has a 5% maximum percentage of total base bid per the BID SCHEDULE . When the Agency has to conform the bid item price to the maximum stated percentage, such action does not constitute a reason for the Contractor to withdraw their bid. If no separate item is shown in the bid for mobilization and demobilization, then the Contractor shall include all costs in the various items of work.
Placement of facilities and storage of construction equipment and materials shall be approved in advance by the Engineer. All such facilities and equipment shall remain the property of the Contractor.
The Contractor shall be held responsible for all dama ge caused during mobilization and demobilization. The Contractor shall leave all storage areas in a neat clean condition, satisfactory to the Engineer and in accordance with the provisions of storage permits set by the property owner.
When a separate bid item is included in the BID SCHEDULE, payments for mobilization and demobilization will be made in accordance to the following schedule:
a] When the approved monthly partial payment estimate of the amount earned, not including the amount earned for mobilization and demobilization, is ten percent (10%) or more of the original Contract amount, twenty-five percent (25%) of the Contract item price for mobilization and demobilization will be included in the estimate for payment.
b] When the approved monthly partial payment estimate of the amount earned, not including the amount earned for mobilization and demobilization, is twenty - five percent (25%) or more of the original Contract amount, the total amount earned for mobilization and demobilization shall be fifty percent (50%) of the Contract item price for mobilization and demobilization will be included in the estimate for payment.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
116 of 244
109
c] When the approved monthly partial payment estimate of the amount earned, not including the amount earned for mobilization and demobilization, is fifty percent (50%) or more of the original Contract amount, the total amount earned for mobilization and demobilization shall be seventy-five percent (75%) of the Contract item price for mobilization and demobilization will be included in the estimate for payment.
d] When the approved monthly partial payment estimate of the amount earned, not including the amount earned for mobilization and demobilization, is seventy -five percent (75%) or more of the original Contract amount, the total amount earned for mobilization and demobilization shall be ninety-five percent (95%) of the Contract item price for mobilization and demobilization will be included in the estimate for payment.
e] After final acceptance of the Project, the remaining unpaid amount, of the Contract item price for mobilization will be included for payment in the final progress payment.
7-3.7 Agreed Prices.
Add the following to this subsection:
Agreed prices shall be negotiated before commencement of the Work.
7-4 PAYMENT FOR EXTRA WORK.
7-4.1 General.
Replace the first sentence in this subsection with the following:
When the cost and time for Extra Work cannot be agreed upon prior to the commencement of the Work, the Agency will pay for Extra Work based on the accumulation of costs as provided herein and grant additional time to the Contract duration. Extra Work shall be paid for under a written Change Order, approved by the Agency, in accordance with the terms therein provided. Generally, payment for Extra Work will be made at the unit price or lump sum previously agreed upon between the Contractor and the Agency.
7-4.2.3 Tools and Equipment Rental.
Replace the second paragraph in this subsection with the following:
Regardless of ownership, the rates to be used in determining equipment rental costs shall not exceed most current listed rates found in the Caltrans Labor Surcharge and Equipment Rental Rates, which is available online at:
https://dot.ca.gov/programs/construction/equipment-rental-rates-and-labor-surcharge
Add the following paragraphs to this subsection:
Where the Contractor can substantiate that the rental rates prevailing locally exceed the published rate by more than fifteen percent (15%), the Contractor will be entitled to a rental rate adjustment.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
117 of 244
110
For equipment not listed in said publication, rental rates must not exceed listed rates prevailing locally at equipment rental agencies or distributors, at the time the Work is performed.
Whenever possible, Extra work must be accomplished using equipment available on Site or owned by the Contractor. If a specific piece of equipment must be rented to be used exclusively for the Extra Work, the rental rate will be the invoiced rate.
7-4.3 Markup.
7-4.3.1 Work by Contractor.
Replace the paragraph in this subsection with the following:
7-4.3.1 Work by Contractor: The following allowable overhead and profit percentages shown in Table 7-4.3.1 below shall be added to the Contractor’s costs and shall constitute the markup for all overhead, insurance, and profits on work performed by the Contractor:
Table 7-4.3.1
COMPONENT OVERHEAD PROFIT
Labor 10% 10%
Materials 10% 5%
Equipment Rental 10% 5%
Other Items and Expenditures 10% 5%
Regardless of the number of hierarchical tiers of Subcontractors, the five percent (5%) which is the Contractor’s allowance 3.5% (for overhead) and 1.5% (for profit) may be applied one time only to the performing Subcontractor’s total cost.
One percent (1%) shall be added to the sum of the costs and markups provided for in the subsection as compensation for bonding.
7-4.3.2 Work by Subcontractor.
Replace the paragraph in this subsection with the following:
7-4.3.2 Work by Subcontractor: When all or any part of the Extra Work is performed by a Subcontractor, the markup established in 7-4.3.1 shall be applied to the Subcontractor’s actual cost of such work. A markup of ten percent (10%) on the first Five-Thousand Dollars ($5,000) of the subcontracted portion of the Extra Work and a markup of five percent (5%) on work added in excess of Five-Thousand dollars ($5,000) of the subcontracted portion of the Extra Work may be added by the Contractor.
The markups specified in Subsections 7-4.3.1 (“Work by Contractor. ”) and 7-4.3.2 (“Work by Subcontractor.”) shall be considered as full compensation and include, but not be limited to, the Contractor’s labor costs for personnel not working directly on the Extra Work, including the cost of administration and any tools or equipment that the y may use. Such costs shall not be reported as Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
118 of 244
111
labor or equipment costs elsewhere except when they are actually used in the performance of the Extra Work. Labor costs shall in that case be reported for the labor classification corresponding to the type and nature of Extra Work performed.
7-4.4 Daily Reports.
Add the following as the first sentence in this subsection:
The Contractor shall notify the Engineer at the beginning of each working day when Extra Work is in progress.
7-6 BID ITEMS.
Add the following new subsection:
7-6 BID ITEMS. Payment for the work included in each Bid Item shall be made at the actual quantity constructed, using the units listed in the BID SCHEDULE and the Unit Prices included in the BID. All other work shown or mentioned on the Plans, in the Specifications, o r in any one of the Contract Documents shall be considered as included in the related Bid Items shown in the BID SCHEDULE. The Contractor must complete all work that is shown or described in the Contract Documents, whether or not there is a specific Bid Item for that work, and no additional compensation will be allowed.
SECTION 8 – FACILITIES FOR AGENCY PERSONNEL
Facilities for Agency personnel will not be required.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
119 of 244
112
SUPPLEMENTARY TECHNICAL PROVISIONS
PROJECT NAME: TRAFFIC SIGNAL INTERCONNECT PROJECT FOR EMERALD DRIVE, POINSETTIA AVENUE, AND N. MELROSE DRIVE (C.I.P. No. 8294)
This section makes additions, deletions, or revisions to PART 2 – CONSTRUCTION MATERIALS, PART 3 – CONSTRUCTION METHODS, PART 4 – EXISTING IMPROVEMENTS , PART 5 – PIPELINE SYSTEM REHABILITATION, PART 6 – TEMPORARY TRAFFIC CONTROL, PART 7 – STREET LIGHTING AND TRAFFIC SIGNAL SYSTEMS, AND PART 8 – LANDSCAPING AND IRRIGATION of the 2024 Standard Specifications for Public Works Construction (“Greenbook”). As a convenience, these additions and amendments have been arranged in a format that parallels the Greenbook. All sections and subsections which are not changed remain in full force and effect. Additional Special Provision sections and subsections may be included in these supplements which may be written in a format different from that of the Standard Specifications. These additional Special Provision sections and subsections are intended to complement the Standard Specifications.
PART 2 - CONSTRUCTION MATERIALS
SECTION 200 – ROCK MATERIALS
200-1 ROCK PRODUCTS.
200-1.1 General.
Add the following paragraph to this subsection:
In accordance with the provisions of Section 20676 of the State of California Public Contract Code, it shall be mandatory upon the Contractor to whom the Contract is awarded, and upon all subcontractors and suppliers under him, to obtain all construction aggregate, sand, gravel, crushed stone, road base, fill materials, and any other mineral materials, including those used in other construction materials such as asphalt concrete and Portland Cement concrete, from a supplier that is included on the most current Office of Mine Reclamation AB 3098 List (per California Assembly Bill 3098). Failure to identify the supplier and the mine may result in rejection of the submittal, and any work completed using materials from an unlisted mine will be SUBJECT TO REJECTION.
200-2 UNTREATED BASE MATERIALS.
200-2.1 General.
Add the following paragraph to this subsection:
Aggregate base shall be Class 2 per Subsection 26-1.02B, “Class 2 Aggregate Base ” of the Caltrans Standard Specifications , and associated AGGREGATE GRADING REQUIREMENTS and QUALITY REQUIREMENTS tables or Crushed Aggregate Base per Subsection 200-2.2 (“Crushed Aggregate Base. ”) and as shown in the gradation in TABLE 200 -2.2.2 of Subsection 200-2.2.2 (“Grading.”) of the Greenbook.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
120 of 244
113
Aggregate may include up to one hundred percent (100%) material processed from reclaimed asphalt concrete, Portland Cement concrete , lean concrete base, cement treated base or a combination of any of these materials. It should be noted, this does not change the specification requirements for material or placement quality. It is still the Contractor’s responsibility to verify that any blend of reclaimed paving materials with or without virgin materials shall meet all the specification requirements.
SECTION 201 – CONCRETE, MORTAR, AND RELATED MATERIALS
201-1 PORTLAND CEMENT CONCRETE.
201-1.1 General.
Add the following paragraph to this subsection after the first paragraph:
Contractor shall furnish the Engineer a copy of the mix design to be used and with legible certified weight-master’s certificate for each load of PCC delivered to the Work. Portland Cement concrete delivered to the project site having a water content and/or slump greater than that specified in the mix design shall be rejected and removed from the Work site.
201-1.2.6.3 Accelerating Admixtures
Modify this subsection to read as follows:
Calcium Chloride shall not be used as an admixture. Other accelerating admixtures shall conform to ASTM C 494, accelerating (Type C), or water -reducing and accelerating (Type E) admixtures, shall be approved by the Engineer prior to use.
201-1.3.3 Concrete Specified by Class and Alternate Class.
Modify the third paragraph of the subsection to read as follows:
The concrete class, alternate class, and maximum slump for various types of construction shall be as specified in Table 201 -1.3.3 except for the concrete class specified for Street Surface Improvements. Street Surface Improvements shall have a concrete class of 560-C-3250.
201-1.5.4 Hand Mixing.
Replace the first sentence in this subsection with the following:
Hand mixing concrete shall not be allowed except by prior permission from the Engineer and, if permitted, only when the amount of concrete required is less than one cubic yard (1 yd. 3).
Prepackaged unmixed concrete shall not be allowed except by prior permission from the Engineer.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
121 of 244
114
201-2 REINFORCEMENT FOR CONCRETE.
201-2.2 Steel Reinforcement.
201-2.2.1 Reinforcing Steel.
Replace the first sentence in this subsection with the following:
Unless otherwise specified, reinforcing steel, except longitudinal steel, shall be Grade 60 billet steel conforming to ASTM A615.
201-3 EXPANSION JOINT FILLER AND JOINT SEALANTS.
201-3.1 General.
Replace the second paragraph of this subsection with the following:
All expansion joints shall be formed with joint filler and sealed with Type “A” two-part polyurethane sealant per Subsection 201-3.4 (“Type “A” Sealant (Two-Part Polyurethane Sealant”). The filler shall be placed in the correct position before concrete is placed against it. Holes or joints in the joint filler shall be filled with joint sealant to prevent the passage of mortar or concrete from one side of the joint to the other.
SECTION 203 – BITUMINOUS MATERIALS
203-5 RUBBERIZED EMULSION-AGGREGATE SLURRY (REAS).
203-5.1 General.
Add the following paragraph to this subsection:
Type 1 slurry seal shall be used on residential streets and Type 2 slurry seal shall be used on residential collector streets.
203-6 ASPHALT CONCRETE.
203-6.1 General.
Add the following paragraphs to this subsection:
The grading of the combined aggregates and the percentages of asphalt binder shall be as follows:
Class and Grade
Three-quarter inch (3/4”) Base Course B-PG 64-10 RAP
One-half inch (1/2”) Surface Course C2-PG 64-10 RAP
One-half inch (1/2”) AC Dike D2-AR-8000 RAP
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
122 of 244
115
A minimum of five (5) Working Days prior to the paving operation, the Contractor shall submit to the Engineer the pavement supplier’s certification of gradation and oil content of the asphalt concrete to be used for this Contract.
SECTION 207 – GRAVITY PIPE
209-7 PIPELINE IDENTIFICATION.
209-7.2 Requirements.
Add the following to this subsection:
Detectable Underground Utility Marking Tape shall have a minimum 0.005” overall thickness, with no less than a 35 gauge (AWG) aluminum foil core. The foil must be visible from both sides. The layers shall be laminated together with the extrusion lamination process, not adhesives. No inks or printing shall extend to the edges of the tape. All printing shall be encased to avoid ink rub -off. Detectable Underground Utility Marking Tape shall conform to the properties listed in TABLES 209-7.2 (A) and 209-7.2 (B) below.
TABLE 209-7.2 (A)
DETECTABLE UNDERGROUND UTILITY MARKING TAPE PROPERTIES
PROPERTY METHOD VALUE
Thickness ASTM D2103 0.0056”
Tensile strength ASTM D882 25 lbs/inch (5,500 psi)
Elongation ASTM D882-88 <50% at break
Printability ASTM D2578 >50 dynes/cm2
Flexibility ASTM D671-81 Pliable hand
Inks Manufacturing specifications Heat-set Mylex
Message repeat Manufacturing specifications Every 20”
Foil Manufacturing specifications Dead soft/annealed
Top layer Manufacturing specifications Virgin PET
Bottom layer Manufacturing specifications Virgin LDPE
Adhesives Manufacturing specifications >30%, solid 1.5#/R Bond strength Boiling H2O at 100 degrees Celsius Five (5) hours without peel Colors APWA Code See Table 209-7.2 (B) below
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
123 of 244
116
TABLE 209-7.2 (B)
DETECTABLE UNDERGROUND UTILITY MARKING TAPE COLORS
COLOR UTILITY MARKED
Red Electric power, distribution, transmission, and municipal electric systems.
Yellow Gas and oil distribution and transmission, dangerous materials, product and steam.
Orange Telephone and telegraph systems, police and fire communications, and cable television.
Blue Water systems.
Green Sanitary and storm sewer systems, nonpotable.
209-7.3 Material Approvals.
Add the following new subsection:
209-7.3 Material Approvals. Detectable Underground Utility Marking Tape shall meet the requirements of each of the following agency / association publications:
(1) Department of Transportation, Materials Transportation Bureau, Office of Pipeline Safety.
USAS code for pressure piping B31.8, paragraph 192.321(e).
(2) National Transportation Safety Board, Washington, DC, Special Study Prevention of Damage to Pipelines. Adopted June 7, 1974. Report NTSB-PSS-73-1.
(3) American Petroleum Institute (API). Recommended practice for marking buried liquid petroleum pipelines - APR RP 1109.
(4) General Services Administration, Washington, DC, Public Buildings Service Guide Specification for Mechanical and Electrical Equipment - PBS 4 -1501, Amendment 2, Page 501 -14, Paragraph 18, Subparagraph 18.1, Clause 18.1.1.
(5) Rural Electrification Authority (REA), U.S. Department of Agriculture, Washington, DC, National Electrical Safety Code for Underground Construction for remote and immediate hazards.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
124 of 244
117
PART 3 - CONSTRUCTION METHODS
SECTION 300 – EARTHWORK
300-1 CLEARING AND GRUBBING.
300-1.1 General.
Add the following paragraphs to this subsection:
Clearing and Grubbing shall include the protection of all items to remain, sawcutting, cold milling AC pavement, demolition of existing improvements, salvaging existing materials (topsoil) and improvements as specified or shown on the Plans, removal of deleterious materials, and proper disposal from the Project site of all existing surface and subsurface materials as required to construct the improvement as shown on the Plans and as described in the Specifications. Typical items to be removed include, but are not limited to, trash, fences, posts, poles, gates, street signs, AC dikes, AC paving, striping (by grinding), decorative concrete, concrete driveway entrance, concrete sidewalk, concrete curb and gutter, concrete headwall structures, retaining walls, landscape border logs, decorative walls, concrete pavers, reinforcing steel, rock, boulders and cobbles, trees, stumps and roots, shrubs, other vegetation or organic materials, soil, irrigation systems, spoils, debris, sewer pipe, storm drain pipe, storm drain inlets and grates, electrical conduits and pullboxes, wire, utility cabinets or boxes, drinking fountains, guardrails, delineators, pavement markers, and all other objectionable materials which interfere with the Work whether or not specifically indicated on the Plans or otherwise shown to be protected or relocated . Abandoned utility lines and structures not removed with Engineer’s approval shall be filled with blown sand and conduits plugged. Concrete and bituminous pavement shall be removed to neatly sawed edges. Sawcuts shall be to a minimum depth of three inches (3”).
Clearing and grubbing shall also include the relocation, adjusting or salvaging of all facilities so indicated on the Plans which are not designated as separate bid items or which are not included in other bid items.
If there are decorative items on private lots, including decorative concrete pavers, decorative wall blocks, rocks used for landscape decoration, boulders, and custom signs, and the Contractor would prefer to salvage items for the property owners, the items shall be removed carefully and placed at a location near the disturbed area on the private property, with the property owner’s approval.
The Contractor shall remove existing irrigation systems (including both water supply and water distribution lines, electrical supply, and electrical control elements of the system) that are within the Project limits and place these materials on the property owner’s property. Contractor shall cap ends of cut lines and wires, and mark locations with lath so that property owner can locate them later.
Miscellaneous fencing materials may be encountered during Work. The terminal post of each fence removed shall be reinforced by bracing or other appropriate means to maintain the structural integrity of the portion of fence to remain. Relocation and reconnection of existing fences as shown on the Plans shall include all posts, hardware, and all incidentals necessary to complete the Work.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
125 of 244
118
Terminations for all fire hydrants, WARF type services and associated piping to be removed and salvaged shall be in accordance with the Vista Irrigation District (VID) standards. The minimum requirements shall include removal of piping back to the mainline, closing the valve, and installation of a blind flange and thrust block.
All existing water services shall be relocated or extended to behind curb or behind sidewalk if contiguous to curb. The Contractor shall inspect and verify that the existing service, including the connection at the main, meets current Vista Irrigation District (VID) standards. Where existing services meet VID standards, extension of the service will be allowed at the price bid for water meter relocations.
All existing sewer or water facilities to be abandoned within the proposed Project limits shall be terminated at the mainline in accordance with district requirements. This shall include removal of the sewer and water service back to the main. The sewer lateral shall be capped with a fitting and sealed with concrete at the wye connection. The water service shall be terminated at the corporation stop and the stop closed.
During surface clearing operations, the Contractor shall not cover or bury any plant growth or other objectionable materials on public or private property. If the Contractor cannot successfully separate the plant growth from the surface soil and advertently or inadvertently mixes organic or other objectionable materials with the soil, the soil so contaminated shall be removed from the site by the Contractor. All costs, if any, associated with removing the soil mixed with organic or other objectionable materials and importing soil to replace said contaminated soil shall be borne by the Contractor and no additional payment shall be made to the Contractor.
During grading operations, the Contractor shall provide temporary graded driveways and continuing maintenance thereof to provide safe, smooth, stable and continuous access to all residences and businesses within the Project area. All costs, if any, associated with such grading operations shall be borne by the Contractor and no additional payment shall be made to the Contractor.
Unless otherwise noted on Plans, the Contractor shall protect all existing sewer, water, electric, telephone, communication, television, fire lines, street lights, traffic signal , red light cameras, irrigation, and other utilities, services and systems, whether shown on the Plans or not. The Contractor shall maintain all services in working condition during the course of the Work. The Contractor shall remove all existing abandoned pipelines and conduits of any type or use, and pipelines and conduits of any type or use that are abandoned during the course of the Work and shall replace said pipelines and conduits with properly compacted soils. The Contractor shall immediately restore to full operation any utilities, services or systems that are disturbed during the course of the Work.
300-1.4 Payment.
Modify this subsection to read as follows:
300-1.4 Payment. The BID SCHEDULE DOES NOT include a bid item for Clearing and Grubbing.
Full compensation for any necessary Clearing and Grubbing required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore. Payment for removal Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
126 of 244
119
and disposal of abandoned utilities shall be included in the various items of work and no additional compensation will be allowed therefore.
300-2 UNCLASSIFIED EXCAVATION.
300-2.1 General.
Modify this subsection to read as follows:
300-2.1 General. Unclassified excavation shall consist of all excavation, including roadway excavation, removal and stockpiling of suitable material, mixing and moisture conditioning of dry material, mixing and drying of wet material by various methods , disposal of unsuitable materials (including cobbles, rocks and boulders), salvage and stockpile of existing topsoil for use on the Project, and all other required earthwork operations to bring all areas that are within the grading and excavation limits on both public and private property to the required subgrade elevations and cross sections as shown on the Plans and as required in the Project’s geotechnical investigation. Suitable excavated material may be used onsite to make all fills shown on the Plans. Unclassified excavation shall also include pumping and disposal of storm water and groundwater. Any tree roots or other deleterious material uncovered during excavation shall be completely removed and cut back so that new improvements will not be affected by future root growth.
In the event weather conditions make drying by aeration or other processes impractical as determined by the engineer, he may suspend the Work. However, the Contractor shall continuously provide for traffic and access requirements during the suspension period in conformance with these Technical Provisions. The Work shall be suspended as provided for in Section 6 (“PROSECUTION, PROGRESS, AND ACCEPTANCE OF THE WORK.”) of the Standard Specifications except the suspension shall not be deemed to be suspension by the Agency for its own convenience or benefit.
Stockpiling of material and storage of equipment or supplies associated with excavation and /or soil aeration activities within existing or proposed wetland, willow woodland or riparian areas is strictly prohibited.
The Geotechnical Report is not available for this Project. The excavation, placement, conditioning, and compaction of material shall be in accordance with the Plans, Specifications, and the City of Vista Development Code (Chapter 17 Section 17.52 and Section 17.56).
300-2.2 Unsuitable Material.
300-2.2.1 General.
Modify this subsection to read as follows:
300-2.2.1 General. All excess material generated by the grading operations that is not suitable for backfill shall be excavated and disposed of by the Contractor at a legal disposal site. The Agency makes no claim on the suitability or moisture content of the existing materials. Any suitable local borrow materials at the site that the Contractor wishes to re-use shall be stockpiled by the Contractor.
The location of stockpiles shall be approved by the Engineer prior to placement of materials, and all stockpiles shall be protected by erosion control measures.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
127 of 244
120
All subgrade areas to receive fills or structures shall be inspected by the Geotechnical Engineer.
All alluvial and colluvial soils, loose or poorly compacted soils, or existing dry material must be reworked before the placement of base or concrete can proceed. Areas where soils are loose or poorly compacted shall be reworked by excavating, blending and recompacting the loose soils to the specified compaction. The existing loose soils to be reworked shall be removed by the Contractor until a firm unyielding surface is exposed or to a depth determined by the Engineer. Dry materials shall be scarified and moisture conditioned to achieve the specified compaction. With the approval of the Geotechnical Engineer, the Contractor may choose to stabilize poorly -compacted areas with geogrid at his own expense.
If the Contractor wishes to temporarily stockpile material for disposal at a later date in any area other than the project area or construction staging area, the Contractor shall locate a suitable space which is outside the Public Right -of-Way and suitable to the Agency. The location of stockpiles shall be approved by the Engineer prior to placement of materials, and all stockpiles shall be protected by storm water pollution prevention and erosion control measures. The stockpiles shall be removed regularly from the Project site so as not to interfere with access to the Project.
If the excavated material is unsatisfactory as excavated for other uses in the Project, as determined by the Engineer, the Contractor shall remove and dispose of such excavated material off the site. The Contractor shall be responsible for obtaining a suitable legal disposal site for any unsuitable excavated materials in accordance with the appropriate section in the Standard Specifications.
300-2.2.2 Wet Material.
Modify this subsection to read as follows:
300-2.2.2 Wet Material. If required excavated material is unsatisfactory for the specified use on the Project solely because the material has a moisture content of four percent (4%) or more above the optimum moisture content, the Contractor shall process the material to reduce the moisture content to an optimum condition, or remove the material and replace it with suitable material. The material may be processed by blending the wet soil with soils having a lower moisture content and / or spreading the excavated material in a manner that enables the material to dry to optimum moisture content. With the approval of the Geotechnical Engineer, the Contractor may choose to stabilize unstable subgrade areas with geogrid at his own expense.
300-2.7 Selected Material.
Modify this subsection to read as follows:
300-2.7 Selected Material. Selected material encountered in excavation within the right -of-way shall be used as directed by the Engineer. Topsoil excavated within the limits of the Project may be considered as a selected material only for the purpose of backfilling areas to be planted.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
128 of 244
121
300-2.8 Measurement.
Add the following paragraph to this subsection:
The Plans and the Specifications show work to be done which requires earthwork, both cut and fill, to establish the lines and grades shown on the Plans. The Agency has endeavored to establish reasonable accurate earthwork quantities of the work actually involved and these quantities represent the results of actual survey measurements and data and calculated adjustments for changes proposed on the Plans, h owever, due to the approximate nature of such data and therefore the difficulty of making accur ate measurements of earthwork quantities for this type of project, the estimated quantities for grading will be assumed to be the actual quantity. The Contractor shall review the site and make his own estimate of the Work required to complete the Project. No modifications shall be made to the quantity shown on the Plans and in the Specifications, unless additional quantities of grading are ordered by the Engineer.
300-2.9 Payment.
Modify this subsection to read as follows:
300-2.9 Payment. The BID SCHEDULE for this Project DOES NOT include a bid item for Unclassified Excavation. Full compens ation for all necessary Unclassified Excavation required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore.
The excavation, stockpiling, and placement of topsoil and suitable local borrow material will be included in Unclassified Excavation. Removing such material from the stockpile and placing it in its final position is also included in Unclassified Excavation. The Contractor may stockpile suitable local borrow material or import suitable borrow material; however, no separate payment will be made for excavating material from an optional stockpile or importing suitable borrow material and placing the material in its final position.
The removal and disposal of unsuitable material, and the over -excavating and reworking of material that can be made suitable, including groundwater removal by various drying procedures or other remedial geotechnical ( soil) treatment shall be included in Unclassified Excavation and no additional compensation will be allowed.
The over-excavation and processing or removal and disposal of wet materials shall be included in Unclassified Excavation and no additional compensation will be allowed.
No separate payment will be made for excavating topsoil temporarily stockpiled and placing in its final location on the slope and other areas to be planted for erosion control planting or landscaping, whether or not required by the Contract Documents or by the Engineer.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
129 of 244
122
300-3 STRUCTURE EXCAVATION AND BACKFILL.
300-3.1 General.
Add the following paragraphs to this subsection:
In accordance with the provisions of Section 20676 of the State of California Public Contract Code, it shall be mandatory upon the Contractor to whom the Contract is awarded, and upon all subcontractors and suppliers under him, to obtain all construction aggregate, sand, gravel, crushed stone, road base, fill materials, and any other mineral materials used for Structure Backfill, from a supplier that is included on the most current Office of Mine Reclamation AB 3098 List (per California Assembly Bill 3098) . Failure to identify the supplier and the mine may result in rejection of the submittal, and any work completed using materials from an unli sted mine will be SUBJECT TO REJECTION.
The Geotechnical Report is not available for this Project”. The excavation, placement, conditioning, and compaction of material shall be in accordance with the Plans, Specifications, and the City of Vista Development Code (Chapter 17 Section 17.52 and Section 17.56).
The Contractor shall excavate to the lines and grades required, whether or not specifically shown on the Plans. The Contractor shall provid e and remove all shoring, sheeting, bracing, cribbing, pumping, lagging, piling, tiebacks, soil anchors, shields, temporary retaining structures, planking, or other types of support for the walls of all open excavations required. The Contractor shall excavate and maintain the bottom of all trenches and excavations in a condition that is level, firm, clean and free from all debris or foreign matter. Excavations shall be kept free from water at all times. The Contractor shall remove any unsuitable material encountered below grade as directed by the Engineer.
300-3.7 Payment.
Add the following paragraphs to this subsection:
Full compensation for any necessary work related to Unsuitable Materials required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore.
Full compensation for supporting the excavation for structures shall include furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in providing excavation safety, shoring or sloping of excavations including, but not limited to, design of the shoring system ; obtaining all necessary permits from the Division of Occupational Safety and Health ; constructing shoring; and removal and disposal of the shoring materials; all as shown on the Plans, or as specified in the General Conditions, Standard Specifications, and these Supplementary Special Provisions; shall be considered as included in the related items of work and no additional compensation will be allowed.
No change will be made in the amount to be paid for supporting the excavation for structures as a result of required revisions in the excavation support details due to a type of soil encountered which requires a method of trench support different from that approved.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
130 of 244
123
300-4 UNCLASSIFIED FILL.
300-4.1 General.
Add the following paragraphs to this subsection:
The Geotechnical Report is not available for this Project. The excavation, placement, conditioning, and compaction of material shall be in accordance with the Plans, Specifications, and the City of Vista Development Code (Chapter 17 Section 17.52 and Section 17.56).
Any objectionable material, including organic and inorganic debris, shall be removed, and shall not be placed in the fill.
The Contractor shall establish rough grade of the areas to be planted by placing fill material to a minimum of six inches (6”) below the finished grade shown on the Plans. The Contractor shall then complete the grading work to establish finished grade by placing a minimum of six inches (6”) of topsoil that has been stockpiled from the existing site or imported.
Excess soil remaining from excavations on the Project site may only be used for fill material when rocks, lumps, cobbles, clods, base material, or other solid materials such as broken concrete or asphalt from removal operations are suitable for the particular area to be filled as determined by the Engineer and conform to the requirements of the geotechnical investigation. Broken concrete or asphalt pavement materials shall not be allowed within site grading fill areas or roadway fills less than three feet ( 3’) in height, within three feet (3’) of final grade in any area or within five feet (5’) (vertically) of the existing ground water table. Any concrete or asphalt placement shall be approved by the Geotechnical Engineer.
Concrete or asphalt pieces shall be less than six inches (6”) in maximum dimension and surrounded by soil particles when used as compacted fill. No nesting shall occur. If the Contractor wishes to use any of the excess material remaining from the Project excavations for any purpose, the material must be suitable for use as fill or backfill and meet the requirements of S ubsection 300-4 (“UNCLASSIFIED FILL.”) of the Standard Specifications and the geotechnical investigation for this Project. The Contractor shall first remove all organic material, construction debris, miscellaneous debris, rubbish, and other objectionable materials contained therein, then obtain tests of the material to confirm its suitability.
Geotechnical (soil) testing of all fill materials; subgrade, subbase, and base will be conducted by the Agency and the Geotechnical Engineer. Geotechnical (soil) tests may include relative compaction tests, sand equivalent tests, sieve analysis, R-values, etc. The results shall be presented directly by the laboratory to the Engineer. No base or PCC pavement shall be placed prior to the subgrade or subbase being compacted, tested and approved by the Engineer.
The cost of a ny initial geotechnical ( soil) tests shall be borne by the Agency. Additional geotechnical (soil) tests due to the failure of one (1) or more of the initial tests shall be conducted by the laboratory and any costs borne by the Contractor. The Contractor shall make allowances in his construction procedure to permit testing of the Work in progress by the Engineer, and no additional compensation shall be paid to the Contractor for delays due to testing.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
131 of 244
124
300-4.10 Payment.
Modify this subsection to read as follows:
300-4.10 Payment. The BID SCHEDULE for this Project DOES NOT list a bid item for Unclassified Fill. Full compensati on for any necessary Unclassified Fill required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore.
300-5 BORROW EXCAVATION.
300-5.2 Imported Borrow.
Add the following paragraph to this subsection:
In accordance with the provisions of Section 20676 of the State of California Public Contract Code, it shall be mandatory upon the Contractor to whom the Contract is awarded, and upon all subcontractors and suppliers under him, to obtain all construction aggregate, sand, gravel, crushed stone, road base, fill materials, and any other mineral materials used for Imported Borrow, from a supplier that is included on the most current Office of Mine Reclamation AB 3098 List (as proposed in California Assembly Bill 3098 and now codified in Section 2717.(b) of the State of California Public Resources Code). Failure to identify the supplier and the mine may result in rejection of the submittal, and any work completed using materials from an unlisted mine will be SUBJECT TO REJECTION.
300-5.4 Measurement and Payment.
Modify this subsection to read as follows:
300-5.4 Measurement and Payment. The BID SCHEDULE for this Project DOES NOT list a bid item for borrow excavation. Full compensation for any necessary borrow required to perform the construction operations specified shall be considered as included in the related items of work for which the borrow excavation is required, and no additional compensation will be allowed therefore.
300-12 EROSION CONTROL.
300-12.1 General.
Add the following new subsection:
300-12.1 General. The Contractor shall provide erosion control and water pollution control conforming to the requirements shown on the Plans, as specified herein, and as elsewhere required by the Contract Documents. Erosion control and water pollution control shall include the Work specified herein, and such additional measures, as may be directed by the Engineer, to meet Best Management Practices, as defined herein, and to properly control erosion and storm water damage of the limits of work and construction impacts upon areas receiving drainage flows from within the limits of work.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
132 of 244
125
The work covers the prevention, control and abatement of waterborne silts, sediments, earth materials, inorganics, chemicals, construction materials, trash, and debris in order that pollution of the existing onsite and downstream watercourses is prevented or minimized. The Work includes preventing, controlling or abating water polluting elements or materials which may result both directly and indirectly from within and outside the Project work limits. This includes water flow from, to, or through the site resulting from rainfall runoff, groundwater movement, and stream storm water discharge.
The work includes:
a] the exercise of care and the execution of every reasonable precaution by the Contractor as required by the conditions of the site, weather and construction activities involved;
b] the implementation of construction of various devices, facilities, or features shown on the Plans;
c] the implementation or construction of any devices, facilities, or programs as required conditions of any regulatory agency permits for the Project. The Work therefore includes, but is not limited to, the construction and / or installation of temporary devices such as hay (straw) bales; silt fences; gravel bags; erosion control netting, fabric, blankets, or mats; silt or sediment basins; dikes or berms; swales, linings; ponds; diversion structures, pipes, and related facilities.
d] the cleaning, repairing, silt and sediment removal, maintenance and the removal of devices.
Note: The Contractor’s attention is also directed to the specific requirements contained within the regulatory agency conditional agreements.
Unless other more restrictive requirements are specified elsewhere in the General Conditions or these Special Provisions, or as a requ irement of regulatory or other A gency permits, the following minimum provisions shall be met:
a] Equipment and workers for emergency work shall be made available at all times during the rainy season. All necessary materials shall be stockpiled on site at convenient locations to facilitate rapid construction or deployment of temporary devices when rain is imminent.
b] Devices shown on the Plans shall not be moved or modified without the approval of the Engineer.
c] The Contractor shall restore all erosion control devices to working order to the satisfaction of the Engineer after each runoff-producing rainfall, and every 24 hours during a prolonged storm event, as needed.
d] The Contractor shall install additional erosion control measures as may be required by the Engineer due to uncompleted grading operations or unforeseen circumstances which may arise.
e] The Contractor shall be responsible and shall take necessary precautions to prevent public trespass onto areas when impounded waters create a hazardous condition.
f] During the rainy season and when rainfall is probable, graded areas around the Project perimeter must drain away from the face of slope at the conclusion of each working day.
g] All removable protective devices shown shall be in place at the end of each working day when the five (5) calendar day rain probability forecast exceeds thirty percent (30%).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
133 of 244
126
Compliance with the requirements of this subsection shall in no way relieve the Contractor from his responsibility to comply with the other provisions of the contract, in particular his responsibility for damage and for preservation or property.
Failure to take said measures satisfactory to the Engineer or regulatory agencies will subject Contractor to orders to cease operations. Any losses to Contractor associated therewith shall be at Contractor’s sole expense.
300-12.2 Grading Controls.
Add the following new subsection:
300-12.2 Grading Controls. The Contractor shall protect all areas that have been graded and/or cleared and grubbed as well as areas that have not been graded and/or cleared and grubbed within the limits of work from erosion. The Contractor shall provide temporary earth berm, fiber rolls, gravel bags, silt fences, stabilized construction entrances and similar measures, coordinated with its construction procedures, as necessary and as shown on the Plans to control on site and off site erosion during the construction period. The Contractor shall protect areas which have been cleared and grubbed prior to excavation or embankment operations, and which are subject to runoff during the duration of the contract. The criteria used to determine the appropriate erosion control measures shall be the “Best Management Practices”, hereinafter BMP, d efined and described in the latest edition of the "California Storm Water Best Management – Construction Handbook" as published by the Storm Water Quality Task Force [go to the CASQA on -line bookstore at the following URL to purchase, download or view handbook(s)]:
http://www.cabmphandbooks.com
The Contractor shall maintain a copy of the latest edition of the "California Storm Water Best Management – Construction Handbook" on the Project site and shall conduct its operations in conformity to said Handbook.
Excavation and Embankment areas, while being brought to grade and during periods of completion prior to final surface construction, shall be protected from erosion and the resulting siltation of downstream facilities and adjacent areas, and be graded so as to direct runoff into impoundment areas within the limits of work where such runoff shall have pollutants removed by BMP methods. The Contractor shall provide protection by BMP measures to eliminate erosion and the siltation of downstream facilities and adjacent areas. These measures shall include all means necessary to prevent polluted runoff from leaving the site.
300-12.4 Payment.
Add the following new subsection:
300-12.4 Payment. Payment for all work required to provide Storm Water Pollution Prevention and Erosion Control shall be included in the lump sum price included in the Bid specified as Storm Water Pollution Prevention and Erosion Control . Such price shall include full compensation fo r preparing the Storm Water Management Permit, the Storm Water Pollution Prevention Plan (SWPPP) Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
134 of 244
127
where applicable , performing erosion control and water pollution control, conforming to the operational requirements herein, providing and maintaining all BMPs, removing all construction BMPs, conforming to the requirements of the current State Water Resources Control Board of California Order, and the current City of Vista Grading Ordinance, and no additional compensation will be allowed therefore.
SECTION 301 –SUBGRADE PREPARATION, TREATED MATERIALS,
AND PLACEMENT OF BASE MATERIALS
301-1 SUBGRADE PREPARATION.
301-1.1 General.
Modify this subsection to read as follows:
301-1.1 General. This subgrade preparation specification shall govern the preparation of natural, filled, or excavated material prior to the final placement of subbase or base material, geotextile fabric, drainage facilities, pavement, curbs and gutters, driveways, sidewalks, retaining walls or any concrete facilities or roadway structures. Subgrade preparation shall include, but not be limited to scarification and moisture adjustment and compaction of the top twelve inches ( 12”) of the subgrade in the pavement areas to ninety-five percent ( 95%) relative compaction, and attendant work, export of remaining excess material to a disposal site or spoil area acquired by the Contractor and pumping and disposal of storm and ground water. In areas where existing utilities may interfere with subgrade preparation work in the roadway prism, the Contractor may choose to place geogrid to stabilize the subgrade and reduce the depth of excavation.
Geotechnical (soil) testing of all fill materials; subgrade, subbase, and base will be conducted by the Agency and the Geotechnical Engineer. Geotechnical (soil) tests may include relative compaction tests, sand equivalent tests, sieve analysis, R -values, etc. The results shall be presented directly by the laboratory to the Engineer. No base or PCC pavement shall be placed prior to the subgrade or subbase being compacted, tested and approved by the Engineer.
The cost of any initial geotechnical ( soil) tests shall be borne by the Agency. Additional geotechnical (soil) tests due to the failure of one (1) or more of the initial tests shall be conducted by the laboratory and any expenses borne by the Contractor. The Contractor shall make allowances in his construction procedure to permit testing of the Work in progress by the Engineer, authorized representative or the Inspector, and no additional compensation shall be paid to the Contractor for delays due to testing.
301-1.7 Payment.
Revise this subsection to read as follows:
301-1.7 Payment. The BID SCHEDULE DOES NOT include a bid item for subgrade preparation. Full compensation for Subgrade Preparation required to perform the construction operations specified or Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
135 of 244
128
shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore.
301-2 UNTREATED BASE.
301-2.1 General.
Add the following to this subsection:
Concrete curb, gutter, cross gutter, spandrel, sidewalk, driveway, and flatwork shall be placed on untreated compacted aggregate base, unless the existing material under the areas being repaired is determined to be firm and unyielding by the Engineer. New Asphalt Concrete Pavement shall also be placed on untreated compacted aggregate base. Untreated compacted aggregate base shall have the following thicknesses under respective concrete surface improvement unless shown otherwise on the Plans or specified:
PCC Sidewalk shall be placed on six inches (6”) of untreated compacted aggregate base.
PCC Curb and Gutter shall be placed on six inches (6”) of untreated compacted aggregate base.
PCC Pedestrian Access Ramp shall be placed on six inches (6”) of untreated compacted aggregate base.
PCC Driveway Entrance shall be placed on six inches (6”) of untreated compacted aggregate base.
PCC Cross Gutter and Spandrel shall be placed on twelve inches (12”) of untreated compacted aggregate base.
Asphalt Concrete Pavement shall be placed on untreated compacted aggregate base, using the thicknesses shown on the Plans.
The Contractor will be allowed to reuse any existing base that is removed if the base material is removed without being contaminated by subgrade soils or other deleterious materials. The re -used base material must be moisture conditioned and compacted as specified. The Contractor shall provide water and compact the surface of any base material that will form the foundation for subsequent improvements, to meet the requirements of the Plans and specifications. The Contractor shall remove and replace any existing aggregate base that becomes contaminated.
301-2.3 Compacting.
Add the following as the first paragraph:
301-2.3 Compacting. It shall be the Contractor’s responsibility to provide adequate equipment and methods to accomplish the Work in accordance with these Specifications. The grading shall be done to the elevations provided in the Plans. Any field conditions that prevent the Contractor from matching design elevations shall be immediately notified to the Engineer.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
136 of 244
129
Revise the third paragraph of this subsection to read as follows:
The relative compaction of each layer of compacted base material shall not be less than ninety- five percent (95%) for curbs, driveways and pavement for a minimum depth of one foot (1.0’) below the grading plane . C ompaction under sidewalks and in the excepted areas shall be as specified in Subsection 211-1 (“COMPACTION TESTS .”) with each layer of compacted base material having a minimum compaction of ninety percent (90%).
301-2.4 Measurement and Payment.
Revise this subsection to read as follows:
301-2.4 Measurement and Payment . The BID SCHEDULE DOES NOT include a bid item for untreated base . Full compensation for Untreated Base required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work, and no additional compensation will be allowed therefore.
SECTION 302 – ROADWAY SURFACING
Revise this subsection to read as follows:
302-5 ASPHALT CONCRETE PAVEMENT.
302-5.1 General.
Modify the first paragraph of this subsection to read as follows:
302-5.1 General. Asphalt concrete pavement shall consist of two (2) or more courses of a mixture of paving asphalt and graded aggregate as specified in Subsection 203-6 (“ASPHALT CONCRETE.”), placed on a prepared surface of existing or new untreated base, or over existing paving, as necessary to construct the roadway as shown on the Plans or as required to complete the Work (i.e. where new curb is placed, utility cuts , and manhole reconstruction area) . The courses shall be of the type of mixture specified. The thickness of asphalt concrete pavement for initial patch areas next to gutters, spandrels, and curbs shall be a minimum of six inches (6”), and the thickness in trenches next to curbs and driveways and in trenches shall be one -inch (1”) thicker than the existing pavement. The initial asphalt concrete patch base course for the items of work shown on the Plans shall be placed full depth from the aggregate base to the existing pavement surface as soon as the adjacent improvements are cured sufficiently to allow the paving to proceed. The initial asphalt concrete patch shall be placed in multiple move-ins to accommodate the required traffic control and staging phases, and to ensure that traffic is allowed to use the improvements as quickly as possible. Asphalt concrete in streets and parking lot areas where there is no base shall be placed on a prepared section of subgrade material to the thickness shown on the Plans. The surface course of asphalt concrete shall be a minimum of one and one-half inches (1-1/2”) thick with a one inch (1”) minimum thickness at the overlay key. The surface course shall be placed in the minimum number of move -ins necessary to accommodate the required traffic control and staging phases, but minimize the joints in the new asphalt concrete surface. Before the surface course is placed, the edges of existing pavement shall be cold milled to form an overlay key as shown on the Plans or as specified.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
137 of 244
130
In a parking lot, the entire accessible parking stall and loading area shall not exceed two percent (2.00%) in any direction, NO EXCEPTIONS.
Add the following paragraph to read as follows:
Temporary asphalt concrete pavement and striping may be required to implement the traffic control and construction phasing shown on the Plans or specified. In sidewalk areas temporary AC surfacing shall be at least one inch (1”) thick. In the streets, a greater thickness may be required.
Temporary surfacing and striping shall be placed before the end of the work period so traffic can be restored at the time of day specified, and it shall remain in place or be replaced regularly until the area is ready fo r permanent pavement and striping. Full compensation for all work required to install, maintain, and dispose of temporary asphalt concrete pavement and striping will be considered as included in the price bid for Traffic Control and Construction Phasing and no additional compensation will be allowed therefore.
302-5.2.3 Tack Coat.
Replace the first sentence of the first paragraph in this subsection with the following:
If the asphalt concrete pavement is being constructed directly upon an existing hard -surfaced pavement, a Tack Coat of PG 64-10 paving asphalt shall be uniformly applied at a rate no less than
0.07 gallons per square yard (g/sq. yd.) upon the existing pavement preceding the placement of asphalt concrete. Payment for this item shall be included in the unit price for the related asphalt concrete pavement or overlay and no additional compensation will be allowed.
302-5.9 Placement.
302-5.9.1 General.
Add the following paragraphs to this subsection:
Asphalt paving equipment shall be equipped with automatic screed controls and a sensing device or devices. When placing asphalt concrete, the automatic controls shall control the longitudinal grade and transverse slope of the screed. Grade and slope refer ences shall be furnished, installed, and maintained by the Contractor.
At locations where new asphalt concrete pavement joins an unimproved shoulder, the Contractor shall taper the new asphalt edge by raking out all aggregate three-eighths inch or larger (3/8+”) and feathering the new paving to form a smooth transition to join the unimproved shoulder. The transition shall extend a minimum of eighteen inches (18”) onto the shoulder. Additional tack coat shall be applied to all tapered transitions to prevent raveling of the new pavement. Tapers shall be raked, rolled, and compacted so there is no lip exceeding one-quarter inch (1/4”).
Should the methods and equipment furnished by the Contractor fail to produce a layer of asphalt concrete conforming to the requirements, including straightedge tolerance, of Subsection 302-5.11 Compaction and 302-5.12 Smoothness of the Standard Specifications, the paving operations shall be discontinued and the Contractor shall modify their equipment or furnish substitute equipment.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
138 of 244
131
Careful attention shall be given to maintaining proposed surface drainage conditions during placement of asphalt overlay. Unless otherwise directed by the Engineer, existing drainage patterns shall be maintained.
Should the automatic screed controls fail to operate properly during any work period, the Contractor may use manual control of the spreading equipment for the remainder of the work period; however, the equipment shall be corrected or replaced with alternat ive automatically controlled equipment conforming to the requirements in this Subsection before starting another work period.
Prior to placing asphalt concrete, the Contractor shall provide covers over all existing storm drain grates and inlets to prevent entry of debris.
The streets identified for overlay may have rutting, offset crowns, high spots, or low spots that need to be corrected to re-establish the proper street grade. Cold milling shall be used to remove high spots.
Tack coat and leveling courses of asphalt concrete shall be placed to fill low spots and ruts and to re- establish street grades prior to the placement of asphalt concrete overlay. The Contractor shall use cold milling to remove high spots and to provide joints for AC leveling course, in areas as directed by the Engineer. The Contractor shall place tack coat in the areas delineated by the Engineer, and rake the edges of the variable thickness AC leveling course to create smooth feathering. If a quantity of AC leveling course is included in the Bid Schedule, it is a rough estimate for bidding purposes. If Leveling Course is needed, that work shall be directed by the Engineer in the field. The Contractor shall cooperate with the Engineer in placing the leveling course as required to re-establish street grades, and perform the work as directed by the Engineer.
302-5.9.2 Joints.
Replace the first paragraph in this subsection with the following:
Longitudinal joints between successive runs shall be placed to match striped lane lines. If this placement pattern cannot be met, joints between successive runs shall be in the center of the driving lane.
302-5.12 Smoothness.
Add the following paragraphs to this subsection:
Contractor shall have a ten foot (10’) straightedge onsite at all times during all paving operations for use in checking the smoothness of the surface.
The finished surface of the asphalt concrete pavement shall be placed three-eighths inch (3/8”) above the gutter lip to allow full compaction of the asphalt at the gutter edge and to prevent damage to the gutter lip caused by the roller.
At curb ramps the finished surface of the asphalt concrete pavement shall be placed one -eighth inch (1/8”) above the gutter lip. If the asphalt concrete surface is more than one-quarter inch (1/4”) Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
139 of 244
132
above the lip or if the slope of the asphalt concrete surface at the gutter lip exceeds five percent (5%), the Contractor shall grind the pavement until it is equal to or less than five percent (5%) and flush with the gutter lip.
302-5.14 Payment.
302-5.14.5 Asphalt Concrete
Modify the first paragraph of this subsection to read as follows:
302-5.14.5 Asphalt Concrete. Asphalt concrete pavement will be considered as included in the price bid for related items of work, and no additional compensation will be allowed therefore.
303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLY INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.
303-5.1 Requirements.
303-5.1.1 General.
Modify the second paragraph of this subsection to read as follows:
Unless otherwise prescribed in Subsection 303-5.1.3 (“Driveway Entrances .”), the minimum thickness of walks shall be four inches (4”). The height of curbs a nd the thickness of gutters, cross gutters, alley intersections, curb ramps and driveway aprons shall be as shown on the Plans.
303-5.1.2 Drainage Outlets Through Curb.
Modify the first paragraph of this subsection to read as follows:
Drains shall be constructed beneath the sidewalk as shown in SDRSD No. D-27 (“SIDEWALK UNDERDRAIN PIPE”) to connect existing building drains or yard drains along the line of Work through curb outlet sleeves to the gutter, or to serve low areas on adjacent property where pre-existing drainage conditions have been affected by the Work. Each separate parcel shall be provided with a minimum of two (2) drains, one (1) at the low side o f the parcel and one (1) at the high side of the driveway, or as shown on the Plans. Payment for all work required to install curb sleeves and under-sidewalk drains will be considered as included in the related concrete items, and no additional compensation will be allowed therefore.
303-5.1.3 Driveway Entrances.
Add the following paragraphs to this subsection:
Where walk is constructed adjacent to driveways, both commercial and residential, provisions shall be made for an accessible walkway within the right-of-way at the back of the sloped driveway apron, with a minimum width of forty-eight inches (48”) and a maximum cross slope of two percent (2.00%).
The longitudinal slope of the walk shall match the slope of the street, taken at the gutter lip or gutter flow line.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
140 of 244
133
PCC Driveway Entrances and PCC Driveways shall be in accordance with City of Vista Municipal Code Section 16.57.090, with smooth transitions to join existing improvements, and no grade breaks exceeding fourteen percent (14%) in eleven feet (11’) for a crest, or twenty -three percent (23%) in eleven feet (11’) for a sag.
303-5.1.4 Curb and Gutter.
Add the following new subsection:
303-5.1.4 Curb and Gutter . PCC Curb and Gutter shall be formed along the gutter lip using specified form material. For projects where curb and gutter is being constructed adjacent to existing pavement, a section of pavement twelve inches (12”) wide, measured from the lip of the gutter, shall be removed to allow for the gutter lip to be formed. The twelve inch (12”) slot shall be paved after the curb and gutter is fully cured, to avoid damage from paving operations.
The Contractor shall exercise great care to construct curbs conforming strictly to ADA standards at locations where curb ramps will be constructed. The curb face shall be depressed to a flush surface with no lip at the flowline. The slope of the asphalt leading up to the curb ramp shall not exceed five percent (5.00%) for a distance of four feet (4’) with a maximum two percent (2.00%) cross slope per SDRSD No. G-32A.
The Contractor shall install eight inch (8”) mow curb in accordance with the San Diego Regional Standard Drawing (SDRSD) No. L-3 (“CONCRETE MOWING STRIP”). All mow curb shall be reinforced as shown on the standard drawing. New mow curb shall have weakened plane joints every ten feet (10’), and expansion joints every thirty feet (30’) and where new mow curb joins other improvements.
The Contractor shall identify locations of water and sewer laterals by stamping a “W” for water service and an “S” for sewer laterals in the green concrete curb after finish troweling is complete. The stamps shall be professionally fabricated, with letters three inches (3”) high.
Expansion joints are required only at beginning and ending of curb returns.
303-5.1.5 Walks.
Add the following new subsection:
303-5.1.5 Walks. Sidewalks shall be constructed in strict conformance with ADA standards. The cross slope on sidewalks shall in no case exceed two percent (2.00%). The clear width of sidewalk shall not be less than forty-eight inches (48”), measured from the bac k of cu rb. Construction tolerances shall not be a reason to exceed the minimum or maximum standards of the ADA. The width of the top of the curb cannot be counted as part of the sidewalk clearance.
If a monolithic retaining curb at the back of curb ramp or sidewalk with a maximum height of six inches (6”) is required to minimize erosion or match existing improvements or earth, the Contractor shall construct those retaining curbs at the back of the curb ramp or sidewalk to the limits determined Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
141 of 244
134
by the Engineer. Retaining curbs shall not reduce the sidewalk clear width below the minimum of forty- eight inches (48”).
Where curbs are sleeved to provide connections to the gutter for yard drains, new sidewalk shall be constructed with under -sidewalk drains, i n accordance with Subsection 303-5.1.2 (“Drainage Outlets Through Curb.”) and SDRSD D-27 (“SIDEWALK UNDERDRAIN PIPE”).
Any irrigation facilities removed or adjusted for the construction of the sidewalk or other work shall be replaced, relocated, or re -configured with similar materials, so that the irrigation system is fully functional. Unless there is a bid item for landscaping and irrigation, payment for this work will be considered as included with other items of work.
Any turf, sod or landscaping remove d adjacent to the Work for the construction of the sidewalk shall be replaced with new turf, sod or landscaping of the sa me type from a commercial nursery .
Unless there is a bid item for landscaping and irrigation, payment for this work will be considered as included in the related items of work.
Expansion joints are required only at beginning and ending of curb returns.
303-5.1.6 Curb Ramp.
Add the following new subsection:
303-5.1.6 Curb Ramp. PCC Curb Ramp shall be constructed in strict conformance with ADA standards. The ADA standards are shown in the latest edition of the San Diego Regional Standard Drawings (SDRSD). For the construction of curb ramps, the Contractor shall refer to, and comply with, all of the requirements for curb ramps shown in the most recent version of the SDRSD Nos. G-27 through G-32B (“CURB RAMP ”) (inclusive) . The City of Vista has developed a checklist of ADA standards for curb ramps, to be used by the Contractor and the Engineer in confirming compliance with ADA standards for sidewalks and any type of curb ramps. The checklist is either included in the appendices to these specifications (see list of Appendices in Table of Contents on Page 2) , or is available to the Contractor upon request.
The Contractor shall modify, adjust or relocate any adjacent improvements so the curb ramp can be constructed to ADA Standards. Before the placement of any concrete curb or curb ramp, the Contractor shall notify the Engineer if it appears that the specified maximum slopes will be exceeded due to existing conditions, to allow the Engineer the opp ortunity to provide direction. If the Engineer determines that a TYPE C CURB RAMP (per SDRSD No. G-29) must be constructed instead of a TYPE A or TYPE B CURB RAMP (per SDRSD No. G-27), to fit existing conditions or minimize impacts to private property, the Contractor shall construct the alternate type of ramp. The Engineer shall pay the bid price for the specified ramp if there is no bid price for the alternate ramp.
If a monolithic retaining curb with a maximum height of six inches (6”) is required to minimize erosion or match existing improvements at the back sid e of the curb ramp, the Contractor shall construct those curbs at the back of the sidewalk to the limits determined by the Engineer, otherwise they may be eliminated . Retaining curbs shall not reduce the clear width of the landing below the minimum of forty-eight inches (48”).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
142 of 244
135
The Contractor shall depress the curb to flush (0” curb face) in front of the curb ramp to meet ADA standards. The Contractor shall construct the road paving or remove and replace sufficient asphalt concrete paving and base to provide a four foot (4’) minimum square landing area, measured from the gutter flowline, where the slopes do not exceed five percent (5%) in any direction per California Building Code (CBC) 1127 B.5.3. The surface of the curb ramp and side flares shall be of contrasting finish from that of the adjacent sidewalk per CBC 1127 B.5.5.
If a diagonal curb ramp on a corner is being constructed at a crossing marked on the pavement, the Contractor shall provide twenty-four inch (24”) long segments of straight curb on each side of the curb ramp, per CBC 1127 B.5.9.
The Contractor shall install a detectible warning surface pad on all pedestrian access ramps and curb ramps leading to hazardous area (e.g. vehicular traffic), as shown on the Plans or in the Standard Plans. The detectable warning surface pad shall extend the full width of the ramp forty-eight inches (48”) minimum and shall measure at least thirty-six inches (36”) along the ramp slope. The detectable warning surface pad or tile shall be securely attached to the surface of the concrete using adhesive and anchors as recommended by the manufacturer of the detectible warning surface. The concrete surface shall be recessed if required by the manufacturer of the detectable warning pad, and the Contractor shall follow all other manufacturer installation instructions. The detectable warning surface pad shall be integrally-colored “DARK GRAY” at all pedestrian access ramps (or curb ramps) on street intersections.
The Contractor shall include in the unit price for Curb Ramps all related costs not covered by other bid items.
303-5.2 Forms.
303-5.2.2 Slip-Forms.
Add the following sentence to the end of the first paragraph in this subsection:
Contractor shall give Engineer the opportunity to confirm the slip-form shoe is set at the correct batter for the concrete curb and gutter.
303-5.5 Finishing.
303-5.5.4 Gutter.
Add the following before the first sentence of the first paragraph in this subsection:
303-5.5.4 Gutter. Cross gutters and spandrels shall be constructed in accordance with the Plans.
Prior to acceptance of the valley gutter constructed by the Contractor, a flow test shall be conducted by the Contractor in the presence of the Engineer. Any new work found to be defective shall be repaired or replaced by the Contractor in accordance with Subsection 303-5.7 (“Repairs and Replacements.”).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
143 of 244
136
303-5.7 Repairs and Replacements.
Modify this subsection to read as follows:
303-5.7 Repairs and Replacements. Any new work found to be defective or damaged, cracked, chipped, discolored, improperly finished, heaved, vandalized, or for any other reason does not conform to the specifications, prior to its acceptance, shall be replaced by the Contractor, at the Contractor’s expense, as approved by the Engineer.
The Contractor shall exercise great care in the construction of curb ramps to ensure compliance with the ADA standards. Any curb ramps that do not satisfy the ADA requirements in any aspect, including exceeding the minimum or maximum values by ANY amount, shall be removed and replaced by the Contractor at his expense. Construction tolerances shall not be a reason to exceed the minimum or maximum standards of the ADA.
303-5.9 Measurement and Payment.
Modify this subsection to read as follows:
303-5.9 Measurement and Payment . The BID S CHEDULE lists items that include concrete / sidewalk repair. Items of work shall be measured and paid for as shown in the Bid, per square foot.
PCC Sidewalk shall be measured and paid for by the square foot as stated in the BID SCHEDULE.
Quantities of PCC Sidewalk will be measured from the back of the curb to the back of the walk, and between adjacent concrete improvements covered, if applicable, by separate items in the bid, such as driveway entrances, curb ramps, cross gutters or alley aprons. The top surface of monolithic retaining curb with a maximum height of six inches (6”) will be included in the quantity of sidewalk. Full compensation for any necessary work required to perform the construction operations specified or shown on the Plans, including clearing and grubbing, earthwork, grading adjacent swales for drainage, subgrade preparation, placing reinforcing steel and dowels, installing j oints per SDRSD Nos. G-7 through G-11, installing under-sidewalk drain pipes through curb sleeves to the gutter and providing monolithic retaining curbs or toe curbs as shown on the Plans or where designated by the Engineer, will be considered as included in the square foot price bid and no additional compensation will be allowed therefore.
The location, protection, and restoration of existing utilities and improvements associated with utility potholing (including street pavements, sidewalks and landscaping/irrigation), specifically identified for payment under other bid items shall not be included for payment within this bid item.
For other items of work that include concrete construction for which there is no bid item, the cost of such items shall be included in the related Bid Items . Full compensation for any necessary work required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for the related items of work and no additional compensation will be allowed therefore.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
144 of 244
137
SECTION 306 – OPEN TRENCH CONDUIT CONSTRUCTION
306-1 OPEN TRENCH OPERATIONS.
306-1.1 Trench Excavation.
306-1.1.1 General.
Add the following paragraphs after the third paragraph:
The groundwater removal work shall include furnishing, installing, and operating a dewatering system capable of dewatering any excavation for any work in progress or planned, and subsequent removal of such equipment from the site.
The Contractor shall limit the area to be excavated at any one time to that area which can be properly dewatered by the equipment in use. The equipment in use shall be both capable of removing any water that accumulates in the excavation and maintaining the excavation in a dry condition while construction is in progress. The surface of the ground shall be sloped away from the excavation or temporary dikes or pipe culverts provided to prevent surface water from entering the excavation.
Disposal of the water from the dewatering system shall be in such a way as not to damage or overload the existing drainage facilities in the area. Protect from injury any portion of the Work completed or in progress, surfaces of streets, lawns or private property. No water shall be directed across a public street outside the construction limits.
All water encountered during the excavation shall be disposed of by the Contractor in such a manner as will not damage public or private property or create a nuisance or health menace. The Contractor shall furnish, install, and operate pumps, pipes, appli ances, and equipment of sufficient capacity to keep all excavations free from water until the excavation is backfilled, unless otherwise authorized by the Engineer. The Contractor shall provide all means or facilities necessary to conduct water to the pumps.
Discharge of pumped groundwater shall be in conformance with the requirements of the Regional Water Quality Control Board, the County of San Diego Department of Environmental Health, the City of Vista, and other agencies having jurisdiction. The Contractor shall obtain all required permits before pumped water from naturally occurring groundwater or from rainfall is discharged to any storm drain or sewer. A means shall be provided for desilting the water before discharging it where required by the Engineer or by the terms of the discharge permits.
306-1.1.5 Removal and Replacement of Surface Improvements.
Revise this subsection to read as follows:
306-1.1.5 Removal and Replacement of Surface Improvements. Bituminous pavement, concrete pavement, landscaping, fences, curbs, sidewalks, or driveways removed in connection with construction shall be removed and reconstructed in accordance with these specifications.
306-1.3 Backfill and Densification.
306-1.3.1 General.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
145 of 244
138
Add the following after the third paragraph:
Material obtained from the project excavations may only be used as backfill after it has been determined to be acceptable and approved by the Geotechnical Engineer and the Engineer.
306-1.3.4 Backfilling Narrow Trenches.
Revise the first paragraph of this subsection to read as follows:
306-1.3.4 Backfilling Narrow Trenches. All narrow trenches for electrical and irrigation work shall be backfilled immediately after inspection and approval of the conduit placement by the Agency Inspector to minimize the length of time traffic control is required for the trench work. Narrow trenches are defined as ten inches (10”) or less in width. Backfill for narrow trenches shall be placed as specified in Subsection 306-1.3.1 (“General.”) except as modified herein. Narrow trenches shall be backfilled by use of trench backfill slurry per Subsection 201-1 (“PORTLAND CEMENT CONCRETE.”), unless otherwise approved by the Engineer. A sphalt Concrete resurfacing of the trench per City of Vista Standard Drawings SRF-08A and SRF-08B (“TRENCH PAVING STANDARD”) may commence with other paving operations.
306-1.3.5 Jetted Bedding and Backfill Compaction Requirements.
Replace the first paragraph with the following:
306-1.3.5 Jetted Bedding and Backfill Compaction Requirements. Except as specified otherwise, trench bedding and backfill densified thru jetting shall be densified to a minimum ninety percent (90%) relative compaction.
306-1.5 Trench Resurfacing.
306-1.5.1 Temporary Resurfacing.
Modify the fourth paragraph to read as follows:
Full compensation for the furnishing, placing, maintaining, removing, and disposing of temporary resurfacing materials shall be included in the unit price of the underground conduit.
306-3.2 Removal of Surface Improvements.
Modify this subsection to read as follows:
306-3.2 Removal of Surface Improvements . B ituminous pavement, concrete pavement, landscaping, fences, curbs, sidewalks, or driveways removed in connection with construction shall be removed and reconstructed in accordance with these specifications.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
146 of 244
139
306-5 DEWATERING.
Add the following paragraphs to this subsection:
The groundwater removal work shall include furnishing, installing, and operating a dewatering system capable of dewatering any excavation for any work in progress or planned, and subsequent removal of such equipment from the site.
The Contractor shall limit the area to be excavated at any one time to that area which can be properly dewatered by the equipment in use. The equipment in use shall be both capable of removing any water that accumulates in the excavation and maintaining the excavation in a dry condition while construction is in progress. The surface of the ground shall be sloped away from the excavation or temporary dikes or pipe culverts provided to prevent surface water from entering the excavation.
Disposal of the water from the dewatering system shall be in such a way as not to damage or overload the existing drainage facilities in the area. Protect from injury any portion of the Work completed or in progress, surfaces of streets, lawns or private property. No water shall be directed across a public street outside the construction limits.
All water encountered during the excavation shall be disposed of by the Contractor in such a manner as will not damage public or private property or create a nuisance or health menace. The Contractor shall furnish, install, and operate pumps, pipes, appliances, and equipment o f sufficient capacity to keep all excavations free from water until the excavation is backfilled, unless otherwise authorized by the Engineer. The Contractor shall provide all means or facilities necessary to conduct water to the pumps.
Discharge of pumped groundwater shall be in conformance with the requirements of the Regional Water Quality Control Board, the County of San Diego Department of Environmental Health, the City of Vista, and other agencies having jurisdiction. The Contractor shall obtain all required permits before pumped water from naturally occurring groundwater or from rainfall is discharged to any storm drain or sewer. A means shall be provided for desilting the water before discharging it where required by the Engineer or by the terms of the discharge permits.
306-12 BACKFILL.
306-12.1 General.
Add the following after the second paragraph in this subsection:
Material obtained from the project excavations may only be used as backfill after it has been determined to be acceptable and approved by the Geotechnical Engineer and the Engineer.
306-12.2 Backfill for Narrow Trenches.
Modify the first paragraph of this subsection to read as follows:
306-12.2 Backfill for Narrow Trenches. All narrow trenches for electrical and irrigation work shall be backfilled immediately after inspection and approval of the conduit placement by the Agency Inspector to minimize the length of time traffic control is required for the trench work. Narrow trenches Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
147 of 244
140
are defined as ten inches (10”) or less in width. Backfill for narrow trenches shall be placed as specified in Subsection 306-12.1 (“General.”) except as modified herein. Narrow trenches shall be backfilled by use of trench backfill slurry per Subsection 201-1 (“PORTLAND CEMENT CONCRETE.”), unless otherwise approved by the Engineer. A sphalt Concrete resurfacing of the trench per City of Vista Standard Drawings SRF-08A and SRF-08B (“TRENCH PAVING STANDARD”) may commence with other paving operations.
306-12.4 Jetted Trench Backfill.
306-12.4.2 Compaction Requirements.
Replace the first paragraph in this subsection with the following:
306-12.4.2 Compaction Requirements . Except as specified otherwise, trench bedding and backfill densified thru jetting shall be densified to a minimum ninety percent (90%) relative compaction.
306-14 MEASUREMENT.
306-14.7 Valves, Hydrants, Buried Structures, and Pipeline Appurtenances.
Add the following after the first paragraph in this subsection:
Water valves and fire hydrants shall be installed as shown on the Plans, installed per Vista Irrigation District (VID) standards, and inspected by VID.
Relocate Fire Hydrant shall consist of trenching, removing existing fire hydrant and lateral up to the main line tee, installing a blind flange on the terminated tee, installing new tee on main line, six - inch (6”) PVC lateral, concrete thrust blocking, PVC elbow, PVC extension spool, break off check valve, extension spool, reinstalling existing fire hydrant to the location shown on the Plans, trench restoration, painting fire hydrant, and other Work necessary to provide a fully functional and operational fi re hydrant to VID Standards.
306-14.8 Temporary Resurfacing
Modify this subsection to read as follows:
Unless otherwise specified, temporary resurfacing will not be measured separately for payment.
306-15 PAYMENT.
306-15.9 Temporary Resurfacing.
Modify the first paragraph in this subsection to read as follows:
Full compensation for the furnishing, placing, maintaining, removing, and disposing of temporary resurfacing materials shall be included in the unit price of the underground conduit.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
148 of 244
141
PART 4 – EXISTING IMPROVEMENTS
SECTION 400 – PROTECTION AND RESTORATION
400-1 GENERAL.
Add the following paragraphs:
The Contractor shall exercise due care to avoid injury to existing improvements or facilities, utility facilities, signage, adjacent property, trees, turf, lawn and shrubbery that are to be relocated or not to be removed.
All trees, turf, lawn, and shrubbery that are not to be removed, and pole lines, fences, signs, survey markers and monuments, buildings and structures, conduits, pipelines under or above ground, sewer and waterlines, highway or street signs and facilities, and any other improvements or facilities within or adjacent to the Work shall be protected from damage. The Contractor shall provide and install suitable safeguards to protect such objects from damage. Relocations, repairs, replacements or reestablishments shall be equal to the existing improvements and shall match such improvements in finish and dimensions unless otherwise specified as approved by the Engineer.
In addition to any requirements imposed by law, the Contractor shall shore up, brace, underpin, and protect, as may be necessary, all foundations and other parts of all existing structures, and all portions of other existing facilities including waterlines, storm drains, and sewer lines, adjacent to and adjoining the site of the Work, which are in any wa y affected by the excavations or other operations connected with the performance of the Work.
The Contractor shall maintain all existing roadside mailboxes and official signs other than those called for removal, including but not limited to directional, warning, advisory, regulatory and street markers. The mailboxes and signs shall be maintained in an erect and functional position and condition at all times during the construction period in either temporary or permanent location as designated by the Engineer. Any of these facilities which are damaged or lost shall be replaced by the Contractor at no cost to the Agency.
The Contractor shall maintain in operation all existing traffic signals and street lighting for the benefit of the public during the progress of the Work. Existing electric services, traffic signal equipment, traffic signs, and street lights that are being replaced or relocated shall remain in service until the replacement facilities are installed and operational or useable).
All costs involved in protection and restoration of existing improvements shall be included in related items of work and no additional compensation shall be allowed therefore.
SECTION 401 – REMOVAL
401-2 ASPHALT CONCRETE PAVEMENT.
Delete this subsection in its entirety and replace with the following:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
149 of 244
142
Bituminous pavement shall be removed to clean, straight lines. Sawcutting of edges to be joined is required, unless the entire pavement section is removed by cold milling. Where only the surface of existing bituminous pavement is to be removed, the method of removal shall be cold milling or other method approved by the Engineer, and a minimum laying depth of one and one -half inches (1-1/2”) of new pavement material shall be provided at the edge of new pavement. Where new bituminous pavement adjoins existing pavement, either at a trench or a section where pavement has been removed or is being widened, the edges where new pavement meets existing pavement shall be trimmed to neat straight lines and cold milled a minimum of one and one -half inches (1-1/2”) deep for a minimum of six inches (6”) wide from the edge before paving or resurfacing, to ensure that all surfaces being paved or resurfaced are accessible to the rollers used to compact the subgrade or paving materials, and to provide an overlay key at the join line.
401-3 CONCRETE AND MASONRY IMPROVEMENTS.
401-3.1 Concrete Pavement.
Modify the first two sentences of this subsection to read as follows:
Concrete pavement shall be removed to neatly sawed edges. Sawcuts shall be made to a minimum depth of three inches (3”).
401-3.2 Concrete Curb, Walk, Gutters, Cross Gutters, Curb Ramps, Driveway, and Alley Intersections.
Modify the first sentence of this subsection to read as follows:
Concrete shall be removed to neatly sawed edges with saw cuts made to a minimum depth of three inches (3”).
Modify the last sentence of this subsection to read as follows:
Curb and gutter shall be sawed to a minimum depth of three inches (3”), or otherwise as required to prevent damage to the adjacent concrete to remain, on a neat line at right angles to the curb face.
SECTION 402 – UTILITIES
402-1 LOCATION.
402-1.1 General.
Modify the first sentence of the second paragraph of this subsection to read as follows:
At least two (2) Working Days (48 hours minimum), but not more than fourteen (14) days, prior to any potholing or excavating, the Contractor shall contact Underground Service Alert of Southern California at 811 -422-4133 or 800-422-4133 for a Dig Alert I.D. Number and shall ensure that all existing underground utilities have been marked by their owners prior to any potholing or excavating.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
150 of 244
143
Section 4216 / 4217 of the Government Code requires a Dig Alert I.D. Number to be issued before a “Permit to Excavate” will be valid.
Replace the third, fourth, and fifth paragraph with the following:
Unless specified otherwise as previously potholed, elevations shown on the Plans for existing utilities are based on a search of record information available during the design only and are solely for the Contractor’s convenience. The Agency does not warrant the accuracy of the completeness of the location, elevation or type of existing utilities and substructures shown on the Plans. The Contractor shall pothole (or by other suitable methods) and determine the location and depth of all utilities marked by their owners, and of all service connections and laterals, which may affect or be affected by the Contractor’s operations. The Contractor shall provide all survey necessary to locate the proposed alignment for potholing purposes. Said potholing shall be done ahead of trench excavation and pipe laying such that the information on horizontal location and depth, in the form of a tabulated pothole report with utility type, stations, top of pipe elevation, and clearance from proposed facility profile, shall be given to the Engineer at least fourteen (14) Working Days ahead of trench excavation or other construction but not greater than thirty (30) Working Days ahead of construction in that area.
The Contractor shall pothole all underground utilities which are shown on the Plans, or marked in the field by utility owners, as being within five feet (5’) horizontal distance from the edge of any planned Project sewer main or lateral, water main or service, storm drain, electrical conduit, gas main, telephone and cable TV conduit, fiber optic conduit or irrigation conduit alignment, and which are within the trench excavation section or above the planned Project facility. The potholes shall be at all crossings of each utility and at one hundred foot (100’) intervals along each parallel utility. The Contractor shall refill these potholes immediately after establishing those locations. The refilling shall conform to the relative compaction requirements for trenches. In the event obstructions not shown on the Plans are encountered during the progress of the Work which will require alterations to the Plans, or if potholing indicates utilities are located other than as s hown on the Plans, the Engineer shall change the Plans and order the necessary deviation from the Project planned line and grade. The Contractor shall not make any deviation from the specified line and grade without approval by the Engineer. Should any deviations in the line and grade be permitted by the Engineer at the request of the Contractor, any additional costs for thrust blocks, valves, concrete, or other additional costs shall be borne by the Contractor. Full compensation for such work shall be considered as included in the prices bid for other items of work. No extension of time or additional compensation will be made for delays caused by failure of the Contractor to complete necessary potholing in a timely manner. The Contractor shall bear the cost of repairing or replacing any existing facility damaged by his potholing work, and shall have affected services back in operation within four (4) hours of interruption.
402-1.2 Payment
Replace the subsection with the following:
402-1.2 Payment. The lump sum price for Utility Potholing in the BID SCHEDULE shall include all labor, materials, and equipment necessary to perform the work and document the results, and no additional compensation will be allowed. The location, protection, and restoration of existing utilities and improvements (including street pavements, sidewalks and landscaping/irrigation) associated with conduit, pull box, and vault installation, specifically identified for payment under other bid items shall Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
151 of 244
144
not be included for payment within this bid item. If no bid item is shown in the BID SCHEDULE the payment is considered to be included in the prices bid for various related items of the Work.
402-2 PROTECTION.
Modify the second paragraph to read:
The Contractor shall furnish and place the necessary protection at its expense to ensure support of utilities located as shown on the Plans or in accordance with 402-1. Any damage to a utility shall be repaired by the Contractor to the satisfaction of the organization owning the facility at no additional cost to the Agency. The Agency reserves the right, if so requested by the utility owner, to permit the utility owner to repair such damage, and all expenses of whatever nature arising from such damage shall be borne by the Contractor.
Modify the third paragraph to read:
Upon learning of the existence and location of any underground utility main structures omitted from or shown incorrectly on the Plans, the Contractor shall immediately notify the Engineer and utility owner in writing. When authorized by the Engineer, support or protection of the utility main substructure will be paid for as provided in Subsection 7-3 or 7-4.
Add the following paragraph to this subsection:
During construction of the Work, some of the existing utilities may fall within the prism of trenches.
If the existing utility does fall within the Contractor’s trenches, the utility involved shall be supported properly by the Contractor to the satisfaction of the utility owner. The method of support of the utility, precautions to be taken during trench backfill and compaction, etc., shall be per the utility owner’s requirements. The cost to support and protect existing utilities shall be included in the various bid items and no additional compensation shall be allowed. The Contractor shall contact the utility owner should it anticipate such exposure of any of the existing utilities.
402-4 RELOCATION.
Modify the third paragraph to read:
The Contractor shall alter, relocate, or reconstruct all fire hydrants, traffic signal and street light pullboxes, sewer cleanouts and manholes, storm drain cleanouts and manholes, and other surface and subsurface structures owned by the City of Vista or by the City of Oceanside, or those facilities required in the Plans or Specifications to be altered, relocated, reconstructed, or adjusted to grade.
Payment for this work shall be as shown in the BID SCHEDULE. If no item is included in the Bid for this work, the cost for this work shall be included in the related items of Work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience shall be its responsibility and it shall make all arrangements and bear all costs.
All water valve covers and meter boxes owned by VID; CP Test Station covers; electrical utility vaults and transformers; gas utility valve covers; telecommunication vaults, manholes and risers; and Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
152 of 244
145
other surface and subsurface structures, not owned by the City of Vista, or required in the Plans or Specifications to be relocated or adjusted to grade “By Others”, shall be relocated or adjusted to grade by the owner of the respective utility. The Contractor shall notify each utility owner a minimum of two (2) Working Days before commencing the Work near their facilities.
Modify the fourth paragraph to read:
The utility owner will alter or relocate service connections as necessary within the limits of the Work or within temporary construction or slope easements. For sewer and water services , the Contractor shall arrange for the alteration or relocation of service connections as necessary between the sewer main or the water meter and property line, or between the sewer main or the water meter and the limits of temporary construction or slope easements. In all cases of alteration or relocation of service connections, the Contractor shall notify residences being affected a minimum of four (4) hours prior to said alteration or relocation, and service connections shall be returned to service in no more than four (4) hours. Payment for the alteration or relocation of sewer or water service connections shall be as shown in the Bid Schedule. If no item is included in the Bid for this work, the cost of this relocation shall be included in the Bid for the items of Work necessitating such relocation. Payment for the relocation of other utility service connections, when directed by the Engineer, shall be in accordance with 7-3 or 7-4. Payment will include the restoration of all existing improvements which may be affected thereby. The Contractor may agree with the owner of any utility to disconnect and reconnect interfering service connections. The Agency will not be involved in any such agreement.
402-6 COOPERATION.
Modify the first paragraph to read:
The Contractor shall so conduct its operations as to permit access to the Work site and provide time for utility work to be accomplished during the progress of the Work. The Agency has initiated communication with the appropriate utility companies that provide for the various service connections or utility relocations and adjustments as noted on the Plans. The responsibility for coordination with utility companies will be transferred to the Contractor with the Notice to Proceed and the Contractor shall assume the responsibility for all further coordination with the utility company. The Contractor shall be responsible for maintaining contact with the utility company representatives and providing necessary effort in scheduling utility work so that delays in overall construction schedule are avoided and utility services are in place for connection upon completion of Contract construction.
Add the following paragraphs to this Subsection:
The Contractor shall be responsible for coordinating with utility companies and other public service agencies, as necessary, to assure timely relocation or adjustment of franchise utilities and other facilities within the specified Contract completion time. The Contractor shall schedule his work to accommodate the adjustments, relocations and / or replacements, to avoid interference with the Contractor's work. The Contractor is required to contact the following organizations (as appropriate for the Project) prior to the start of the Work for updates to the status of the utility work, and for details regarding their respective schedules and requirements (i.e. inspections, etc.).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
153 of 244
146
COMPANY UTILITY CONTACT TELEPHONE EMAIL
Vista Sanitation District Sewer Ken Knatz 760-643-5416 [email protected] Buena Sanitation District Sewer Ken Knatz 760-643-5416 [email protected] City of Vista Well Water
City of Vista Storm Drain Chris Arce 760-643-5459 [email protected] City of Vista Traffic Signal Chris Arce 760-643-5459 [email protected] City of Vista Street Lights Chris Arce 760-643-5459 [email protected] City of Vista Fiber Optic Communication Chris Arce 760-643-5459 [email protected] Vista Irrigation District Water Engineering 760-597-3116 [email protected] City of Oceanside Utilities Water and Sewer Cari Dale [email protected] City of Oceanside Utilities Contracts John McKelvey [email protected] Vallecitos Water District Water and Sewer Lee Kirby 760-744-0460 [email protected] SDG&E Electric Keenon Holmes 858-654-8602 [email protected] SDG&E Gas Vincent Vargas 619-214-2961 [email protected]
SDG&E Street Lights Nicole Brodbeck 858-636-6832 [email protected] AT&T Tele Communications Kristy McClaskey 760-489-3115 [email protected] Cox Communications Tele Communications Debra Capter 619-266-5217 [email protected] Charter Communications Tele Communications Michael Estrada 619-341-0516 [email protected] Charter Communications Tele Communications Peter S. Crampton 619-207-7513 [email protected] Crown Castle Tele Communications Andrew Armstrong 760-613-4671 Andrew.armstrong @crowncastle.com NCTD Bus / Railroad Ruth H. Mbah 760-967-2834 [email protected] NCTD Bus / Railroad ALT Dept. Email [email protected]
The Contractor shall contact the organizations at the beginning of the Project, obtain information on their requirements, provide the m a construction schedule that meets their requirements, update the construction schedule on a weekly basis, meet with the co mpany representatives, provide an adequate construction window and a clear area for them to work, document meetings and coordination efforts, provide copies of all correspondence and other documentation to the Agency on a weekly basis, and perform all other necessary coordination work to the satisfa ction of the organizations and the Engineer. Notifications by the Contractor shall be in writing, with proof of receipt.
Copies of each notification and proof of receipt shall be submitted to the Engineer.
SECTION 404 – COLD MILLING
404-1 GENERAL.
Add the following paragraphs to this subsection:
For resurfacing, the existing asphalt concrete pavement shall be cold milled for pavement removal, header cuts and edge cuts, as detailed on the Plans and in the City of Vista Standard Cold Milling Details. The Contractor shall cold mill pavement adjacent to all concrete gutters, median curbs, AC Berms, across intersecting side streets, and at the project limits. The cold milled area for edge cuts and header cuts on low-volume side streets will be at the width shown on the Plans, or a minimum of five feet (5’) wide, and tapered from the one and one-half inches (1-1/2”) minimum depth to a depth of zero inches (0”). Header cuts for high -volume side streets and across the main street will be a minimum of ten feet (10’) wide, tapered from one and one-half inches (1-1/2”) minimum depth to zero inch (0”) depth.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
154 of 244
147
The Contractor shall cold mill around drain grates in the street, to maintain positive drainage toward the drainage structure after new asphalt concrete is placed. Prior to cold milling, the Contractor shall provide covers over all existing storm drain grates and inlets to prevent entry of debris.
The pavement removal thicknesses and resurfacing thicknesses may exceed the thickness of the existing asphalt concrete pavement. The contractor shall remove asphalt concrete, base, subbase, and subgrade materials to the specified depth, using cold milling or other removal methods. The Contractor shall be prepared to perform the required cold milling, removals, subgrade preparation, and compaction work before pavement is replaced, whether the existing asphalt concrete pavement section is thicker or thinner than the specified asphalt concrete pavement section.
Contractor shall furnish one or more cold milling machines operated by experienced workmen.
The surface produced shall have a tolerance so that a ten -foot (10’) straight edge laid laterally will indicate variance of less than three-sixteenth of an inch (3/16”). Removal shall consist of: (1) planning and cutting the pavement to form a keyway header cut; and (2) removing the loosened material.
Loosened material shall be stored on the property of the Contractor and shall be disposed of off -site at the end of each workday.
Directly following the cold milling operation, all asphalt pavement joints within travel lanes that have vertical separation of more than one -half inch (1/2”) shall be ramped with temporary asphalt concrete. Tamps shall be no less than ten feet (10’) in l ength from the joint and shall extend across all travel lanes. Temporary asphalt ramps shall be completely removed and disposed of the job site prior to overlay application.
404-8 DISPOSAL OF MILLINGS.
Add the following paragraph to this subsection:
Prior to acceptance of the work, the Contractor shall sweep and/or remove all loose material created by the work from streets, gutters, curbs, medians, parkways, sidewalks, intersecting streets, adjacent lots, and driveways.
404-9 TRAFFIC SIGNAL LOOP DETECTORS.
Add the following to this subsection:
The Contractor shall notify the Engineer a minimum of three (3) Working Days prior to the start of cold milling asphalt concrete pavement on any street containing traffic signal loop detectors.
404-10 PAVEMENT TRANSITIONS.
Modify this subsection to read as follows:
404-10 PAVEMENT TRANSITIONS. The Contractor shall trim edges with a saw to neat straight lines at all locations where new asphalt concrete paveme nt is joining or overlaying existing asphalt Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
155 of 244
148
pavement. The Contractor shall also cold mill the edge a minimum of one and one-half inches (1 1/2”) deep for a minimum of six inches (6”) wide from the existing edge before paving or resurfacing. These measures are required to ensure that all surfaces b eing paved or resurfaced are accessible to the rollers used to compact the subgrade or paving materials, and to provide an overlay key at the join line. All temporary structures and vertical joints in the cold-milled area which are transverse to through traffic and greater than one inch (1”) in height, shall be ramped with temporary asphalt concrete pavement as specified in Subsection 306-13.1 (“Temporary Resurfacing. ”). Ramps shall be constructed the same day as cold milling and removed the same day as permanent paving is installed.
Ramp dimensions and compaction shall be approved by the Engineer.
404-11 MEASUREMENT.
Modify this subsection to read as follows:
404-11 MEASUREMENT. Quantities of cold milling shall be measured as shown in the Bid Schedule.
404-12 PAYMENT.
Modify this subsection to read as follows:
404-12 PAYMENT. Full compensation for any necessary cold milling and construction, removal and disposal of temporary asphalt concrete ramps required to perform the construction operations specified or shown on the Plans will be considered as included in the price bid for related items of work, and no additional compensation will be allowed therefore.
PART 6 – TEMPORARY TRAFFIC CONTROL
SECTION 600 – ACCESS
600-1 GENERAL.
Add the following paragraphs to this subsection:
The Contractor shall make every effort to keep driveways open during working hours. After hours all driveways shall be accessible with smooth and safe crossings through the construction.
In addition, only one (1) lane of traffic in each direction may be closed at one (1) time and two- directional traffic must be maintained at all times.
Vehicular lane and bicycle lane closures will only be allowed between the hours of 8:30AM and 3:30PM to avoid impacts on commuter traffic and to avoid impacts to the adjacent businesses, local residences and schools.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
156 of 244
149
The Contractor shall provide and maintain variable message boards , for each direction of travel, to warn motorists to expect delays on W. Vista Way and Melrose Drive when work requiring lane closures is occurring along the street. The variable message boards shall be required in addition to arrow boards required for traffic control. The locations and messages of the signs shall be approved by the Engineer.
600-3 PEDESTRIAN ACCESS.
Sidewalks through the work area may be closed temporarily as long as alternate pedestrian access through the adjacent area or on the opposite side of the street is available at ALL times. The work must be phased so that pedestrian access is maintained at ALL times along street segments and through intersections. This includes performing construction activities only one side of a street segment at a time or on one corner of an intersection at a time to ensure that pedestr ian access through the street segment or the intersection is always maintained.
SECTION 601 – TEMPORARY TRAFFIC CONTROL FOR CONSTRUCTION AND MAINTENANCE WORK ZONES
601-1 GENERAL.
Add the following paragraphs to this subsection:
The Contractor shall prepare and submit a traffic control, construction phasing, and detour plan for approval by the Agency, showing how traffic and access will be maintained during the work.
At least two (2) lanes of traffic, one in each direction, must be kept open during construction periods on all streets. The Contractor shall furnish, install and maintain all necessary and appropriate signing and striping for lane closures to accommodate the work zone.
Emergency vehicles shall be permitted to pass through the work area without delay at all times.
Work shall be performed in a portion of the street section while the remainder of the street section is kept open and unobstructed until the newly-constructed improvements are ready for use by traffic.
The Contractor shall phase the removal operations so as to maintain the specified traffic lanes on existing pavement until sufficient new pavement is constructed to accommodate the traffic requirements. A smooth, even surface and a condition satisfactory for traffic shall be maintained on the portion of street where the two-directional traffic is being maintained.
The Contractor shall cooperate with local authorities relative to handling local traffic and providing access to necessary services through the area and shall make his own arrangements relative to keeping the working area clear of parked vehicles.
If temporary ‘No Parking’ zones are part of the approved Traffic Control Plan, the Contractor shall be responsible for furnishing and posting temporary ‘No Parking’ signs a minimum of forty -eight (48) hours in advance of work. Signs shall have the correct legend and any other necessary information Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
157 of 244
150
such as hours of the day; days of the week; dates that the temporary ‘No Parking’ zone applies; and citation of the applicable section of the California Vehicle Code or the Vista Municipal Code. Signs shall be posted at one -hundred foot (100’) maximum int ervals along the approved temporary ‘No Parking’ zone. Signs may be attached to existing sign and street light poles in the public right -of-way as approved in the Traffic Control Plan. When necessary to meet the spacing requirement or to ensure sign visibility, the Contractor shall furnish posts or barricades. The Contractor is responsible for the removal of all temporary “No Parking” signs and fasteners or tape used after the Work is completed on each street or alley.
The Contractor shall be responsible for furnishing and posting temporary ‘No Parking’ signs along all streets approved for closure. In addition to other requirements for temporary “No Parking” signs, “No Parking” signs for temporary road closures shall be posted at one-hundred foot (100’) maximum intervals on each side of the street to be closed, at all intersections, and ends of all cul-de-sac streets.
Implementation of traffic control devices per the approved Traffic Control Plan may not begin each workday before the hours specified on the approved Traffic Control Plan. In addition, construction work must be stopped before the end of the approved work period to allow sufficient time for all traffic control devices to be removed and for other devices and measures to be in place and operational as shown on the approved Traffic Control Plans within the specified time restrictions. The Contractor shall mak e adjustments to the construction staging and provide any required improvements or additional facilities, including temporary trench steel plate covers, temporary asphalt concrete pavement, barricades and delineators, and temporary signing and striping, wh ich are necessary to make the work site functional and safe at all times. Improvements and facilities necessary to make the work site functional and safe shall be submitted to the Agency’s Traffic engineer for approval as part of the Traffic Control Plan.
Adequate drainage facilities shall be provided to maintain the traveled pavement surface in a condition free from ponding or running water. Water shall not be diverted from existing courses or allowed to pond on private property without the explicit permission, in writing, from the property owner.
Trenches in streets open to traffic shall be provided with temporary pavement surfacing, to maintain a smooth paved travel surface, if the street is not to be provided with permanent pavement surfacing within forty-eight (48) hours after pavement removal. Trench steel plate covers shall not be left in place longer than four (4) consecutive Working Days.
601-2 TEMPORARY TRAFFIC CONTROL PLAN (TCP).
601-2.1 General.
Add the following paragraphs to this subsection:
The Contractor shall be prepared to discuss the traffic control plan and issues related to traffic control and access at the Pre-Construction Meeting. The Contractor shall submit traffic control plans for approval per Subsection 3-8.4 (“Supporting Information.”) at least ten (10) Working Days prior to commencement of work. All phases of the traffic control plans shall be prepared by a California licensed Traffic Control Services Consultant (C31 Contractor’s License – Construction Zone traffic Control Contractor) or a California registered Civil or Traffic Engineer and performed in conformance to the requirements of the latest editions of the California Manual on Uniform Traffic Control Devices Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
158 of 244
151
(CA MUTCD) for Streets and Highways, Caltrans Standard Specifications and Standard Plans, the Traffic Control Plans included in the latest edition of the San Diego Regional Standard Drawing s (SDRSD), and the WATCH Manual (Work Area Traffic Control Handbook). No work shall commence until this plan and each construction phase of the Work that significantly affects existing traffic operations has been reviewed and approved by the Engineer.
The Contractor’s Traffic Control Plan shall list the Working Days and Hours scheduled for each street and each phase of the work, as described in these Specifications.
The relocation and / or installation of traffic and / or parking signs and other directional signage, as required on the Plans, shall conform to the City of Vista Standards, the California Manual on Uniform Traffic Control Devices (CA MUTCD), Caltrans Standard Plans and Standard Specifications, San Diego Regional Standard Drawings (SDRSD), and all current ADA regulations All signs, including those to be relocated or replaced, need to have their new locations approved by the Traffic Engineering Division of the Engineering Department before placement. If not otherwise specified, the work re quired for Traffic Striping and Signing shall conform to these specifications and those in Section 314.
All signing, including “DETOUR AHEAD” signs and “OPEN DURING CONSTRUCTION” signs shall be proposed by the traffic control plan. The Engineer may direct alteration of the above sign messages and locations.
All traffic lanes shall have a minimum width of eleven feet (11’) unless otherwise specified. In addition to the lane width specified herein, the Contractor shall maintain a clearance of two feet (2’) feet to curbs, barricades, and other vertical obstructions.
It shall be the Contractor's responsibility to notify the appropriate utility companies listed in these Project Specifications and the other agencies listed below, at least two weeks in advance, when access to the public right-of-way is altered in any way. Notifications by the Contractor shall be in writing, with proof of receipt. Copies of each notification and proof of receipt shall be submitted to the Engineer.
UTILITY COMPANY / AGENCY PHONE NUMBER
City of Vista Fire Department (Business Office) 760-643-2801 San Diego County Sheriff’s Office (Non-emergency) 760-940-4551 EDCO Waste and Recycling Company (Customer Service) 760-727-1600 City of Vista Engineering Inspection (24 hour answering machine)
760-639-6113
City of Vista Building Division 760-639-6105
City of Vista Building Inspection Request Line (24 hour answering machine)
760-639-6106
City of Vista Parks and Community Services 760-639-6151 North County Transit District (Monica Coria) 760-967-2851 Vista “Out and About” transit service 760-639-6161 x 1537 Vista Unified School District (Maintenance, Operations & Grounds)
760-726-2170 x 92702
United States Post Office (Vista, CA branch) 800-275-8777
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
159 of 244
152
601-2.2 Payment.
Add the following paragraph to this subsection:
Full compensation for developing and maintaining (single or multi-phase) approved Traffic Control Plan with Encroachment Permit from the City of Vista Traffic Engineering Department and Construction Staging, and furnishing Project traffic control, including the cost of all barricades, signs, all variable message signs, tools, equipment, incidentals, flagmen, providing notices, asphalt concrete and aggregate base for temporary resurfacing (and its removal), temporary conflicting traffic stripe application and grinded removal, trench steel plate cover installation and removal, and any other safety measures used for the control of traffic, any temporary rerouting of traffic or maintenance of access to properties during the Project construction period shall be paid for by the lump sum price bid as shown on the BID SCHEDULE and no additional compensation will be allowed.
PART 7 – STREET LIGHTING AND TRAFFIC SIGNAL SYSTEMS
SECTION 700 – MATERIALS
700-1 GENERAL.
Add the following paragraph to this subsection:
All electrical components and electrical materials providing and / or using electrical service shall conform to all applicable City of Vista standards / ordinances, SDG&E Standards, Caltrans Standard Specifications, Caltrans Standard Plans, and the City of Vista Guidelines for the Preparation of Traffic Signal Design Plans.
700-3 COMMON COMPONENTS.
700-3.5 Conduit.
Add the following sentence to this subsection:
Conduit shall conform to the provisions in Subsection 86-1.02B, "Conduit and Accessories" of the Caltrans Standard Specifications and these Special Provisions.
700-3.5.2 Rigid Metallic Conduit.
Replace the first sentence in this subsection with the following:
Conduit and conduit fittings shall be Type 1 (Hot-dip galvanized rigid steel) and, unless otherwise stated, a minimum standard two inches (2”) in diameter.
700-3.5.4 Rigid Non-Metallic Conduit
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
160 of 244
153
Add the following to this subsection:
Traffic signal interconnect conduit shall be 3” High Density Polyethylene (HDPE) 9SDR-9 Wall Type unless otherwise shown on plans and shall conform to the UL Standard for Rigid Non -Metallic Conduit, Publication UL 651B.
HDPE conduit shall be orange in color and comply to ASTM F2160 with Type E ultraviolet stabilizer.
700-3.7 Pull Boxes.
Delete this subsection in its entirety and replace with the following:
700-3.7 Pull Boxes. Pull boxes shall conform to the provisions in Subsection 86-1.02C(2), “Nontraffic Pull Boxes ”, Subsection 86-1.02C(3), “ Traffic Pull Boxes ” and Subsection 86-1.02C(4) “Tamper Resistant Pull Box” of the Caltrans Standard Specifications and these special provisions.
Pull boxes and covers shall be precast reinforced concrete except when the box is subjected to vehicular traffic loads. Steel reinforcing shall be as regularly used in the standard products of the respective manufacturer.
Cover marking on all new traffic signal pull boxes shall be “Traffic Signal” for traffic signal systems and “Lighting” for street light systems. The marking text shall be between one to three inches (1”-3”) high. Enclosures, covers, and extensions shall be concrete gray color. All covers shall have two (2)
0.375” brass or stainless steel stud bolts with nuts and washers recessed into the cover for securing the cover to the box. Pull box covers shall not contain hold-down bolts or hold-down bolt holes.
Unless otherwise stated, fiber -optic interconnect pull boxes shall be standard size 6E (with extension). All fiber optic pull box lids shall be concrete, one-piece lids. Fiber optic pull box covers shall be marked with the words “SIGNAL COMMUNICATIONS” or “SIGNAL COMMS”.
Add the following new subsection:
700-3.12 Tracer Wire. All HDPE fiber optic interconnect conduits shall contain a No. 8 AWG green insulated stranded xhhw -2 copper trace wire. The wires shall be carefully placed so as not to be damaged. The tracer wire shall be continuous thru the entire length of each run from pull box to pull box, enclosure, or pole. No tracer wire splices are permitted between pull boxes. The 5 feet of slack shall be extended into each pull box and fiber optic vault from each direction. Proper operation of the tracer wire shall be demonstrated prior to acceptance.
700-3.12.1 Tracer Wire Payment. Payment for Tracer Wire shall include full compensation for all labor, materials, and equipment required to furnish and install tracer wire inside fiber optic interconnect conduits, including demonstration and documentation of proper tracer wire operation prior to acceptance. Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
161 of 244
154
Add the following new subsection:
700-3.13 Fiber Optic Communication (Splice) Vault. Fiber optic communication vault shall exceed the minimum clearances specified in the se Special provisions and shall be fabricated and installed per the details on the project plans.
700-3.13.1 Fiber Optic Communication Vault Payment. Payment for Fiber Optic Communication Vault shall include full compensation for all labor, materials, and equipment required to furnish and install fiber optic splice vault for fiber optic cable per the project plans including base layer, grounding rods, lifting rings and bolts, and vault cover with required markings and finishes. Payment for this bid item shall be at the contract price per Each (EA).
700-5 TRAFFIC SIGNAL MATERIALS.
700-5.3 Conductors and Cable.
700-5.3.4 Fiber Optic Cable (FOC).
700-5.3.4.1 General.
Add the following paragraph to this subsection:
All fiber optic cable on this project shall be from the same manufacturer, who is regularly engaged in the production of this material. The glass used shall be manufactured by Corning or equivalent approved by the Engineer. All fiber optic cable shall be Corning, all-dielectric, fully water-blocked, loose tube, gel-free Single Mode Fiber Optic cable (SMFOC), cable strand count shall be per plan.
The Contractor shall submit to the Engineer for approval a certification that the Manufacturer has been engaged in the production of this material for a minimum of three (3) years.
General Fiber Optic Cable Requirements:
Outdoor, Loose Tube, Fiber -Optic Cable shall be constructed with loose buffer tubes containing fibers in the quantities specified and indicated. All fiber -optic cable shall be from the same manufacturer. Cable shall meet or exceed the following specifications and conform to the latest issue of ICEA S-104-696 Standard for Indoor-Outdoor Optical Fiber Cable.
The loose tube cables shall comply with the optical and mechanical requirements over an operating temperature range of -40°C to +70°C. The cable shall be tested in accordance with EIA - 455-3A (FOTP-3), “Procedure to Measure Temperature Cycling Effects on Optical Fiber, Optical Cable, and Other Passive Fiber Optic Components.” The change in optical attenuation at extreme operational temperature (-40°C to +70°C) for single mode fiber shall not be greater than 0.20 dB/km, with 80 percent of the measured values no greater than 0.15 dB/km. The single mode fiber measurement is made at 1550 nm.
Materials used within a given cable shall be compatible with all other materials used in the same cable when such materials come into contact. All cable components used shall not adversely affect the optical transmission or the mechanical integrity of the fiber placed in the cable. All materials used shall be non -toxic, non-corrosive, and shall present no dermal hazard. Cable shall be manufactured continuous with no factory splices in the fiber.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
162 of 244
155
The fiber optic cable shall not be adversely affected by the following mechanical and environmental conditions.
1. Crush resistance:
The cable shall not be crushed by a 10,000 N/m (6.78 lb./ft.) load.
2. Minimum Bending Radius
The cable shall be designed for a minimum bending radius of:
a. Installation (Loaded): 20 x cable diameter
b. Static (Installed): 10 x cable diameter
3. Temperature:
a. Operational: -40 to +70°C
b. Storage: -40 to +70°C
4. Humidity: 0 to 100%
5. Tensile Strength: The cable shall not be damaged under the following tensile load:
a. Installation: 2,700 N (600 lb.-f)
b. Static: 600 N (135 lb.-f)
Cables shall withstand an installation tensile load of not less than 600 pounds force and not less than 200 pounds force continuous tensile load.
When tested in accordance with FOTP-33, "Fiber-optic cable Tensile Loading and Bending Test," and FOTP-38, “Measurement of Fiber Strain in Cables Under Tensile Load,” a length of cable shall be tested to the rated tensile load. The rated tensile load sha ll be 2670 N (600 lb.-f). While under the rated tensile load, the fiber shall not experience a measured fiber strain greater than 60% of the fiber proof test level. After being held at the residual load (30% of the rated tensile load) the fiber shall not experience a measured fiber strain greater than 20% of the fiber proof test level nor an attenuation change greater than
0.15 dB at 1550 nm (single-mode). After the tensile load is removed, the fibers shall not experience an attenuation change greater than 0.40 dB at 1550 nm (single-mode).
The cables shall withstand an impact of 1.5 lbs. /in. as a minimum, and shall have a crush resistance of 300 pounds per square inch as a minimum. When tested in accordance with FOTP-25, "Repeated Impact Testing of Fiber-optic cables and Cable Assemblies," the cable shall withstand a minimum of 2 impact cycles at 3 locations separated by at least 150 mm. The impact energy shall be 4.4 NM. The fibers shall not experience an attenuation change greater than 0.40 dB at 1550 nm (single-mode) or greater than 0.60 dB at 1300 nm (multimode). The presence of visible cracks, splits, tears, or other openings on the outer surface of the jacket constitute a failure
6. Compressive Load: When tested in accordance with FOTP -41, "Compressive Loading Resistance of Fiber-optic cables," the cable shall withstand a minimum compressive load of 220 N/cm (125 lb.-f/in) applied uniformly over the length of the sample. The 220 N/cm (125 Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
163 of 244
156
lb.-f/in.) load shall be applied at a rate of 2.5 mm (0.1 in) per minute. The load shall be maintained for a period of 1 minute. The load shall then be decreased to 110 N/cm (63 lb. - f/in.). Alternatively, it is acceptable to remove the 220
N/cm (125 lb.-f/in.) load entirely and apply the 110 N/cm (63 lb.-f/in.) load within five minutes at a rate of 2.5 mm (0.1 in) per minute. The 110 N/cm (63 lb.-f/in.) load shall be maintained for a period of 10 minutes. Attenuation measurements shall be p erformed before release of the 110 N/cm (63 lb.-f/in.) load. The change in attenuation shall not exceed 0.15 dB at 1550 nm for single-mode fibers.
7. All fiber optic cables shall be all dielectric.
8. All fiber optic cables shall contain single mode fibers conforming to the requirements specified below.
a. Each optical fiber shall be glass and consist of a doped silica core surrounded by concentric silica cladding. All fibers in the buffer tube shall be usable fibers, and shall be sufficiently free of surface imperfections and inclusions to meet the op tical, mechanical, and environmental requirements of these Special Provisions. The required fiber grade SM shall reflect the maximum individual fiber attenuation, to guarantee the required performance of each and every fiber in the cable.
b. The single mode FOC shall comply with TIA /EIA 492 -CAAB and the following optical specifications including the zero water peak.
c. Operational Wavelengths: 1,310 nm, 1383 nm and 1,550 nm
d. Optical Attenuation: For all fibers the attenuation specification shall be a maximum attenuation for each fiber over the entire operating temperature range of the cable.
(1) @ 1,310 nm, 20 C: less than 0.38 dB/km
(2) @ 1,383 nm, 20 C: less than 0.36 dB/km
(3) @ 1,550 nm, 20 C: less than 0.26 dB/km
e. Optical fibers shall be single -mode (SM) step index optical glass wave -guides with a nominal core diameter of 8 to 9 microns. The fiber shall have a transmission window centered at 1310 nanometer (nm) wavelength and an optical window from 1300 to 1600 nm.
f. Cladding diameter shall be 125 microns plus or minus 3 microns. Core cladding offset shall be less than 1 micron. Minimum tensile strength of the fiber after primary protective coating shall be greater than 100,000 psi. Softening point of the clad material of the optical fiber shall be 1630 degrees C plus or minus 50 degrees.
g. Optical fiber shall be coated with suitable material to preserve the intrinsic high tensile strength of the glass fiber. Outside diameter of the coated optical fiber shall be 250 plus or minus 15 microns. Coating material shall be readily removable, mechanically or chemically, without damaging the optical fibers when the removal is desired. The coating Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
164 of 244
157
of each optical fiber shall be a dual layered, UV cured acrylate. The coating shall be mechanically or chemically strippable without damaging the fiber.
h. Each fiber shall be distinguishable by means of color -coding in accordance with TIA/EIA598-A, “Optical Fiber Cable Color Coding” and shall be targeted in accordance with the Munsell color shades. The color formulation shall be compatible with the fiber coating and the buffer tube filling compound and be heat stable. In buffer tubes containing multiple fibers, the colors shall be stable across the specified storage and operating temperature range and not subject to fading or smearing onto each o ther or into the gel filling material. Colors shall not cause fibers to stick together.
I Optical fibers shall be distinguishable from others in the same buffer tube by means of color coding according to the following:
1. Blue (BL) 7. Red (RD)
2. Orange (OR) 8. Black (BK)
3. Green (GR) 9. Yellow (YL)
4. Brown (BR) 10. Violet (VL)
5. Slate (SL) 11. Rose (RS)
6. White (WT) 12. Aqua (AQ)
9. Single Mode Fiber Optic Cable (FOC): Shall be all dielectric and conform to the following requirements:
a. Buffer tube:
Loose buffer tubes shall provide clearance between the fibers and the inside of the tube to allow for expansion without constraining the fiber. The fibers shall be loose or suspended within the tubes and shall not adhere to the inside of the tube.
The loose buffer tubes shall be extruded from a material having a coefficient of friction sufficiently low to allow free movement of the fibers. The material shall be tough and abrasion resistant to provide mechanical and environmental protection of the fibers, yet designed to permit safe.
b. Dry Core, Water Blocking and Dielectric strength member:
Cable shall have dry core buffer tube with water swellable strength member surrounding the core buffer tube to prevent water migration.
Tensile strength shall be provided by high tensile strength aramid yarns or fiberglass which shall be placed evenly around the cable core buffer tube and shall not adhere to other cable components.
The water blocking tape and strength member may be a single or multiple layer(s).
c. FastAccess Locator Ridge:
The cable shall have a FastAccess Locator Ridge enabling the jacket to be split.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
165 of 244
158
d. Outer jacket:
Cable jacket shall be marked with manufacturer’s name, sequential meter or foot markings, date of manufacture and a telecommunication handset symbol, as required by Section 350G of the National Electrical Safety Code (NESC). The markings shall be in contrasting color to the cable jacket.
Cable jacketing for exterior and aerial installations shall be medium density polyethylene material containing at least 2.6 percent carbon black with only black pigment added for coloring.
Jacketing for interior/exterior rated cable shall be UV -resistant polyvinyl chloride (PVC), which complies with optical fiber nonconductive riser (OFNR) requirements.
e. Maximum Cable Diameter:
The cable diameter shall not exceed 7.7 mm (0.30 inches).
700-5.3.4.1.1 Overview of Fiber Optic Cable Plant.
Add the following new subsection:
700-5.3.4.1.1 Overview of Fiber Optic Cable Plant. This section is intended to provide an overview of the fiber optic cable plant to be installed as part of this project. The plans and all other sections of the specifications shall take precedence over this overview in the event of any conflicts.
This project involves the installation of multi -strand single mode fiber optics cable in new communications conduit. The project plans specify the exact fiber count to be installed in each trunk conduit section.
For the purposes of testing, all fiber strands shall be fusion spliced to factory terminated pigtails within a fully ST populated 48 position FDU located in a McCain Traffic Supply 332 Fiber Optic Data Node. All pigtails shall be factory terminated , shall be s pliced into pigtails terminated with ST connectors. Jumpers as needed to connect the Fiber Optic Cable from the 332 NODE to the Control Center equipment shall be provided. These pigtails shall be a minimum of 20’ in length. The 332 Node shall be ut ilized to test the fiber optic cable plant to be installed as part of this project. In addition, all data transceiver and other fiber optic electronics shall be tested at this point prior to connection to the control center by others.
The following is a glossary of terms, which are subsequently utilized in this specification:
Breakout: A "breakout" cable shall be produced by (1) removing the jacket just beyond the last tie -wrap point, (2) exposing 3’ to 6’ of the cable buffers, aramid strength yarn and central fiberglass strength member, and (3) cutting the aramid yarn, central strength member and the buffer tubes to expose the individual glass fibers for splicing or connection to the appropriate device.
Connector: A mechanical device used to align and join two (2) fibers together to provide a means for attaching to and decoupling from a transmitter, receiver, or another fiber (patch panel).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
166 of 244
159
Connectorized: A term that describes the termination point of a fiber after connectors have been affixed.
Couplers: Couplers are devices which mates two (2) fiber optic connectors to facilitate the transition of optical light signals from one connector into another. Couplers may also be referred to as: adapters, feed -thrus, and barrels. They are normally located withi n FDFs mounted in panels. They may also be used unmounted, to join two (2) simplex fiber runs.
EIA: Stands for Electronic Industries Association.
Fiber Distribution
Unit (FDU): A combination of the Connector Module Housing (CMH) and the Splice Module Housing (SMH) in the same enclosure.
Jumper: A short fiber optic cable that has connectors installed on both ends, and is used for connection within a FDF.
Light Source: A transportable piece of fiber optic test equipment that, when coupled with a power meter, is used to perform end -to-end attenuation testing. This device contains a stabilized light source operating at the designed wavelength of the system under test. It also couples light from the source into the fiber to be received at the far end by the receiver.
Link: A passive section of the system, the ends of which are to be connected to active components. A link may include splices and couplers.
Mechanical Splice: A device that permanently joins fiber ends to identical or similar fibers.
Mechanical splices are not to be permanently utilized on this project.
Optical Time Domain
Reflectometer
(OTDR): A piece of fiber optic test equipment similar in appearance to an oscilloscope that is used to measure the total amount of power loss between two (2) points.
This test instrument provides a visual and printed display of the relative location of system components such as fiber sections, splices and connectors as well as the losses that are attributed to each component.
Patchcord: A short jumper.
Pigtail: Relatively short length of fiber optic cable that is connectorized on only one (1) end.
Power Meter: A transportable piece of fiber optic test equipment that, when coupled with a light source, is used to perform end -to-end attenuation testing. It contains a detector that is sensitive to light at the designed wavelength of the system Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
167 of 244
160
under test. Its display indicates the amount of power injected by the light source that arrives at the receiving end of the link.
Segment: A section of fiber optic cable that is not connected to any active device and may or may not have splices per the design.
Splice Closure: A container used to organize and protect splice trays. The container allows splitting or routing of fiber cables from multiple locations. The container is environmentally sealed to protect the fibers.
Splice Module
Housing (SMH): The SMH stores splice trays as well as pigtails and short cable lengths.
Splice Tray: A container used to organize and protect spliced fibers.
Splice Vault: A box for fiber optic communication with a minimum inside clearance of 32”W x 44”L x 36”D which is used to house splice closures.
700-5.3.4.1.1.1 Single Mode Fiber Optic Outside Plant Cable - General.
Add the following new subsection:
700-5.3.4.1.1.1 Single Mode Fiber Optic Outside Plant Cable - General. Each trunk fiber optic cable for this project shall be waterblocked, loose tube, all-dielectric, gel-free and contain single mode (SM) dual-window (1300 nm and 1550 nm) fibers as shown on the Plans and shall conform to these special provisions.
The cable shall comply with all the requirements of the United States Department of Agriculture Rural Electrification Administration specifications REA-PE-90.
700-5.3.4.1.1.2 Fiber Optic Equipment – Quality Assurance.
Add the following new subsections:
700-5.3.4.1.1.2 Fiber Optic Equipment – Quality Assurance. All work and material described in this section shall meet or exceed the applicable provisions of the following documents:
• CFR 1755.900, RUS Specification for Filled Fiber Optic Cables • ANSI, C8.47-1983, American National Standard for Polyolefin -insulated Thermoplastic Jacketed Communication Cables
• EIA-455-27A, Method of Measuring (Uncoated) Diameter of Optical Waveguide Fibers • EIA-455-28B, Method For Measuring Tensile Failure Point of Optical Waveguide Fibers • EIA/TIA-455-82A, Water Penetration Test
• EIA-455-95, Absolute Optical Power Test for Optical Fibers and Cables • EIA-455-103, Buffered Fiber Bend Test
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
168 of 244
161
• EIA-359-A-1, Special Colors
700-5.3.4.1.1.3 Ethernet Switch
New ethernet switches shall be Dymec KY -3170MX-10 Port Layer 2 managed ethernet switches.
The project shall connect to existing layer 2 and layer 3 switches with 2-dual fiber/transceiver ports, cables, connectors, and dual SFP’s required to achieve intended communications per the plans.
Payment for Connection to Existing Switches shall include full compensation for all labor, materials, and equipment required to connect to existing layer 2 or 3 ethernet switch with 2-dual fiber/ transceiver ports including all cables, connectors, and auxiliary equipment necessary to establish communication to all network capable devices per the locations shown on the project plans. Payment for this bid item shall be at the contract price per Each (EA) location.
700-5.3.4.7 Fiber Optic Node Transceiver.
Add the following new subsection:
700-5.3.4.7 Fiber Optic Node Transceiver. The Fiber Node Optic Transceiver shall be micro - processor based and shall be configurable as a fully redundant, fault tolerant, self -healing ring configuration, that provides for un-interruptible communications between network node transceivers, even if a fiber break occurs between one or more transceivers in the ring.
The Fiber Optic Node Transceiver shall operate with single mode fiber at 1310nm. The optical connector shall be ST type.
The Fiber Optic Transceiver shall have AUTOMATIC GAIN CIRCUITRY (AGC) allowing for back to back dynamic range operation for light budgets of up to 30 dB. NO IN -LINE ATTENUATORS WILL BE ALLOWED.
The Fiber Optic Node Transceiver shall be capable of operating from -29F to 165F.
The Fiber Optic Node Transceiver shall be compatible with the Agency’s local traffic signal control and central traffic system control software. The Fiber Optic Node Transceiver shall have a female DB25 connector and shall be compliant with EIA RS-232D \ EIA RS422. A cable shall be provided with each Fiber Optic Transceiver when connected to a 170 controller C-2 port.
The Fiber Optic Node Transceiver shall have a built in Network Management System. Each Transceiver shall be addressable and shall be capable of monitoring the status of any Transceiver from any Transceiver in the Network through the NMS interface port. The NMS shall monitor the condition of the fiber ring, data transmission and the condition of the NMS. Configuration of all Transceivers in network may be done directly from the MASTER FIBER OPTIC TRANSCEIVER or from a LOCAL FIBER OPTIC TRANSCEIVER. All software required for the Network Management System shall be supplied with the Fiber Optic Node Transceiver. All Fiber Optic Transceiver Network Management System functions shall be transparent to the Agency’s central and local traffic signal software and therefore have no effect on the system while utilizing the NMS functions.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
169 of 244
162
The data transceiver installation shall include all mounting hardware necessary to mount it 72” tall. Nineteen inch (19”) EIA rail Rack Enclosure with removable side panels, solid rear door, smoked plexi-glass front door and rollers. The Transceivers in the Rack Enclosure will be chassis -mounted.
The size and mounting arrangements shall be consistent with the space available. It shall be mounted in a manner that allows easy access to all connections and indicators.
The data transceiver shall operate over a temperature range of -29F to 165F.
Power shall be supplied from an existing 120 VAC 5 percent, power source. The data transceiver shall include a power supply, which may be external to the transceiver. The power supply shall supply all voltages required by the transceiver for operation, and panel indicators visible from the front of the transceiver that show power on and received optical signal present.
The Contractor shall perform pre-installation testing to verify that the transceiver and transceiver are compatible, meet manufacturer’s specifications and the requirements of these specifications.
The Contractor shall furnish and install a power supply, as recommended by the manufacturer, to power to the data transceiver.
700-5.4 Controllers.
700-5.4.4 Components.
700-5.4.4.4 Connectors.
Add the following new paragraphs to this subsection:
The fiber optic connectors shall be the ceramic ferrule ST type for single mode applications.
All fiber optic connectors shall be the 0.1” ST connector ferrule type with Zirconia Ceramic material with a PC (Physical Contact) pre-radiused tip.
The ST connector operating temperature range shall be -40F to +176F. Insertion loss shall not exceed 0.4 dB and the return reflection loss on single mode connectors shall be at least 40 dB.
Connection durability shall be less than a 0.2 dB change per 1000 mating cycles. All terminations shall provide a minimum fifty pound (50 lb.) pull-out strength.
SECTION 701 – CONSTRUCTION
701-4 DAMAGE TO EXISTING SYSTEMS.
Add the following paragraph to this subsection:
No payment shall be made for incidental repairs needed to improve surfaces or landscaping required for the construction and installation of these systems. Costs for any such efforts shall be included in the cost of related items themselves listed within the bid items.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
170 of 244
163
701-11 PULL BOXES.
701-11.1 General.
Replace a) after the third paragraph with the following:
No more than 500 feet apart for traffic signal interconnect pull boxes.
Add the following sentence to b) after the fourth paragraph:
Pull boxes shall not be located in or within one foot (1’) of any part of any curb ramp (sloped portions of the ramp; wings; grooves; or landings).
Replace the seventh paragraph with the following:
The Contractor may, at its own expense and subject to the approval of the Engineer, install additional pullboxes or use a larger standard size than that shown or specified, to facilitate the Work.
Add the following paragraphs after the seventh paragraph:
When pull boxes within the limits of concrete work are being relocated or adjusted to grade, new pull boxes and covers to match the existing pull box shall be furnished and installed by the Contractor.
If a larger pull box is needed to better accommodate the existing wires or conduit, the Contractor shall furnish and install the larger size pull box as directed by the Engineer.
Fiber optic pull boxes that are being adjusted to grade or relocated must be reconstructed like a new pull box.
When a pull box is subjected to vehicular traffic load, the cover shall be steel embossed with a non-skid pattern. Steel covers have a thirty-six inch (36”) minimum length bonding jumper attached to the systems ground. The box shall rest on a cast in place six inches (6”) wide by six inches (6”) deep minimum concrete footing around the full perimeter of the box.
Pull boxes in existing or future sidewalk areas shall be placed at sidewalk elevation. If there is no existing or future sidewalk in the area and an elevation is not shown on plans, pull boxes shall be set at the same elevation as adjacent signal standard base, service cabinet base or signal controller cabinet base. Pull boxes shall be five feet (5’) from base or as shown on the plans. The pull box elevations for pull boxes installed in median areas shall match the slope of the two adjacent curbs.
The pull box elevation for pull boxes installed in planting areas adjacent to sidewalk or sidewalk area shall be at sidewalk grade. Pull box elevation shall be one-tenth of a foot (0.1’) above finished grade for all other areas unless elevation is shown on plans or otherwise directed by the Engineer.
When pull boxes are placed in dirt and planting areas, a concrete collar shall be constructed around the pull box. The top of the pull box shall match slope of the adjacent top of curb. The surface elevation of the collar shall match the surface elevatio n of the pull box and slope away from the pull box at a rate of 1:50 (2% slope). The width of the collar shall be twelve inches (12”) wide and three and one-half inches (3-½”) in depth.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
171 of 244
164
The Contractor shall clean all pull boxes entered for installation of conduit or wire of all dirt and debris. All pull box lids damaged by Contractor operations shall be replaced at his/her expense. The wiring in these pull boxes shall be neatly bundled, recoiled and reinstalled in the box.
Where existing pull boxes are removed and adjusted to grade, or replaced with new larger boxes, the existing conduits within which the conductors or cables are installed shall be cut back to within two and one-half inches (2-½”) of the edge of the new box. When the conduits are cut, the existing cables or conductors must either be removed or well protected. The ends of the cut conduits must have bushings placed on them. The bushings can be threadless. The existing conductors or cables shall be re-routed to fit in the pull box.
Removed pull boxes shall become property of the Contractor and shall be removed from the project. Removed pull boxes within an improved surface such as concrete sidewalks, will replaced with the improved surface in kind, using methods described within these specifications. The repair of concrete improved surfaces associated with pull box installation shall be paid under a separate bid item per the Bid.
701-11.3 Payment.
Replace this subsection with the following:
701-11.3 Payment. Payment for pull boxes shall include full compensation for all labor, materials, and equipment required to furnish and install No. 6 pull box (with extension) with 45-degree bends for fiber optic cable, including work associated with locating existing city conduit and installing pull boxes over existing conduit as noted on the project plans, as included in the Contract Unit Price per Each in the Bid for the work and no additional compensation. Concrete/ sidewalk repairs associated with this item which include the removal of concrete improved surfaces and subgrade material for this conduit installation, backfill, and compaction per City standard drawings and requirements will be paid from a separate bid item and are not included for payment within this bid item.
701-12 CONDUIT.
701-12.1 General.
Add the following paragraphs:
Conduit shall conform to the provisions in Subsection 86-1.02, "MATERIALS", 87-1.03B, “Conduit Installation” of the Caltrans Standard Specifications and these Special Provisions.
All conduit placed under the roadway shall be installed by jacking or drilling / directional boring methods as provided in Subsection 87-1.03B, “ Conduit Installation” of the Caltrans Standard Specifications. The “Trenching in Pavement Method” may be allowed at the discretion of the Project Engineer or Inspector such as in the event of obstructions or utility conflicts and provided that traffic delay will not exceed five (5) minutes. Depth of trenches for conduit installation shall be thirty inches (30”) minimum depth to top of conduit unless otherwise approved by Project Engineer or Inspector.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
172 of 244
165
Conduit shall have a maximum 45-degree sweep. The minimum conduit bend radii shall be twelve (12) times the cable diameter or twelve inches (12”) minimum. At locations where existing conduit is to be used that does not meet these requirements for sweep and bend radii, conduit shall be replaced with new sweeps or bends with minimum radii.
With the exception for bends to and from pull boxes and foundations the conduit shall run straight and true so that cable pulling forces are minimized.
After cables have been installed, the ends of conduits terminating in pull boxes and/or controller cabinets will be sealed with an approved type of sealing compound.
Cement slurry and trench backfill to be placed as described within these specifications.
Existing conduit to be incorporated into a new system shall be cleaned with cylindrical wire brush, the proper size mandrel shall be verified by the Engineer and the conduit shall be blown out with compressed air. Both old and new cables shall be pulled i nto the conduit as a unit or as directed by the Engineer.
If pull boxes for traffic detector loops are relocated or adjusted to grade, new conduits shall be installed under the curb and gutter to provide access to the detector loop wires in the street.
Where conduit is installed in sidewalk and walkway areas the Contractor shall replace the sidewalk or walkway paving at the existing joint lines. The replacement surfacing shall match line, grade and material of the adjacent surfaces. The repair of concrete improved surfaces associated with conduit installation shall be paid under a separate bid item per the Bid. The repair of damaged landscape features and replacement of existing conduit shall be included in the contract unit price for conduit installation.
701-12.4 Rigid Non-Metallic Conduit.
Replace the second sentence with the following:
A separate No. 8 AWG, solid bare ground wire and a pull rope conforming to Subsections 700-3.6 (“Pull Tape or Rope.”) and 700-3.12 (“Tracer Wire”) shall be inside at the time of installation.
701-12.7 Payment.
Replace the first paragraph of this subsection with the following:
Payment for conduit shall be considered as included in the Contract Unit Price in the Bid for the work that required conduit , including pull tape or rope, and no additional compensation shall be allowed.
Payment for 3” HDPE Conduit shall include full compensation for all labor, materials, and equipment required to furnish and install 3” HDPE conduit to a depth of 30” using drilling/ directional boring, unless otherwise specified for trenching, for fiber op tic cable per the project plans. This bid Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
173 of 244
166
item shall include removals of asphalt concrete and subgrade material necessary for conduit installation including bore pits for directional drilling, backfill, compaction, asphalt concrete pavement resurfacing per City standard drawings and requirements, and other incidentals required for the completion of this bid item in its entirety. Payment for this item shall be based on the actual quantity, Linear Feet (LF).
Payment for 2” Galvanized Steel Conduit shall include full compensation for all labor, materials, and equipment required to furnish and install 2” galvanized steel conduit into existing controller cabinets for fiber optic cable as shown on the project plans. Payment for this bid item shall be based on the actual quantity, Linear Feet (LF). Concrete/ sidewalk repairs associated with this item which include the removal of concrete improved surfaces and subgrade material for this conduit installation, backfill, and compaction per City standard drawings and requirements will be paid from a separate bid item and are not included for payment within this bid item.
Payment for furnishing and installing 45 -degree (3") HDPE conduit bends in existing pull box or vault shall include full compensation for all labor, materials, and equipment required to perform this work and shall be at the contract price per Each (EA) per the Bid.
701-17.4.5 Fiber Optic Cable (FOC).
701-17.4.5.1 General.
Add the following paragraphs to this subsection:
Installation procedures shall be in conformance with the procedures specified by the cable manufacturer for the specific cable being installed. The Contractor shall submit the procedures to the engineer in writing a minimum or 30 days prior to the start of cable pulling.
FOC installation personnel shall also be familiar with the methods and procedures of installing fiber optic cables specified in this contract. The Contractor shall strictly adhere to the FOC manufacturer’s qualification of installation personnel and installation procedures.
The Contractor shall trim all existing conduit in existing pull boxes, as needed, to enable the FOC to be installed without exceeding the minimum bending radius of the cable.
Under no circumstances shall fiber-optic cables be bent over a radius less than the manufacturer's minimum bending radius.
The Contractor shall take care in handling the fiber-optic cable and reels. The Contractor shall be held responsible for any and all damage to the fiber-optic cable and/or fiber-optic cable reels. If cable reels are damaged, they shall be repaired or replaced with a new reel of FOC prior to installation. When lifting reels, a spreader bar shall be used to prevent lifting cables from touching the reel flanges. Reels in storage shall be securely blocked up off the ground.
Particular care shall be taken at all times to prevent the fiber -optic cable from being kinked, twisted, abraded or damaged in any manner. If the FOC is damaged in any way, then the Contractor shall notify the Engineer and inform the Engineer of the proposed remedial action plan to address the Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
174 of 244
167
situation. FOC cables shall only be spliced at locations shown on the Plans, unless otherwise approved by the Engineer in writing. If the Contractor requests permission from the Engineer to install additional fusion splices, not shown on the Plans and pe rmission is granted by the Engineer, then the cost for furnishing, installing and testing, the additional fusion splices shall be at the Contractors expense.
At locations where it is not practical to prevent the fiber -optic cable from coming in contact with the ground surface or other obstruction, suitable shielding boards shall be placed under the fiber-optic cable to protect it from damage.
Mechanical aids may be used to install the FOC, provided that a tension measuring device is placed in tension to the end of the cable, and the allowable tension does not exceed the manufacturer’s recommended pulling tension. A calibrated break-away feature shall be employed to work in tandem with the tension measuring device and limit excessive tension by disengaging just before the maximum allowable cable tension is exceeded.
Information submittal on the proposed FOC pulling and stringing methods to be used shall be submitted to the Engineer within 30 days following the Notice to Proceed and a minimum of 30 days prior to the start of cable installation. The submittal shall contain project title and number; identify if it is for aerial or underground cable installation; equipment description and specifications; manufacturer’s test data covering the performance of the equipment and cable stress in a typical installation using cable equivalent to cable to be installed on this project; and user/installer manual for the equipment and installation procedures. Cable pulling shall not begin until all submittal reviews have been completed and all of the Engineers comments have been addressed in writing. The review process of the submittal shall follow the process described in Section 10-1.13, “Submittals,” of these Special Provisions.
Following the completion of all reviews of the submittal and prior to the start of cable pulling, the Contractor shall conduct a training session with his staff and the CITY staff, The Contractor shall notify the Engineer a minimum of 72 hours in advance of such training.
The Contractor shall utilize installation methods that will maintain the minimum loaded bending radius of the cable at all times.
The take-up reel shall be started and the cable pulled at a speed no more than 5 miles per hour.
Once cable movement has started a constant pull speed shall be maintained.
The brake at the payoff reel shall be engaged to maintain adequate back tension and to prevent the cable from running free. Loss of back tension during the pull may result in twisting and possible damage to the cable.
At all times during the pull, the tensional operator shall monitor the tension meter to assure that the maximum pulling tension is not exceeded.
The cable shall be continuously inspected as it leaves the reels. If any damage or deformity is found, stringing shall be stopped, and corrective action shall be taken prior to continuing the pull. The Project Manager shall first approve any corrective action.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
175 of 244
168
Pull the cable to the locations indicated at each terminal facility. Install a storage coil of 50 feet of cable in every run of FOC at underground splice box or pull box shown on the Plans, unless otherwise stated on the plans or directed by the Engineer.
When the pulling grip is removed, cut off a minimum of twenty feet past the end of the grip to assure no stressed cable is used.
Fiber Optic Cables Pulled in Conduits and Raceways
All wiring and cabling shall be installed in conduit, except where overhead, or where cable is run inside the pole.
Raceways shall be thoroughly cleaned prior to installation to verify that no obstructions exist. All conduits shall be mandrelled prior to start of wire pulling to remove all debris and clear obstructions.
No kinks in wire and cable will be permitted and b ends shall be larger in radius than the minimum recommended by the manufacturer and those specified these Special Provisions.
A pulling machine shall be used that will not exceed the tension and bending radius ratings of the cable and will not cause any damage to the cable. All cable pulling equipment shall prevent sudden changes in cable tension and shall maintain minimum bending radius of 20 inches or greater.
Apply an approved cable pulling lubricant to the cable as it is pulled off the payoff reel to minimize friction.
The cable shall not be pulled through more than 180 degrees of total bends in a continuous run.
Where the cable is to be pulled through a raceway containing more than 180 degrees of load change, the cable shall be installed through multiple pulls by setting up pull and payoff points at intermediate vaults, manholes, or pull boxes. If intermediate pulls are not possible, consult with Engineer before proceeding.
Contractor shall be responsible for pumping or removing any dirt, slurry, mud, or water from any vault, pull-box or manhole as required to properly installing the cable.
The Contractor shall take any and all necessary measures to assure that the minimum bend radius of the cable is not violated, and that maximum pulling tensions are not exceeded.
Fusion Splicing
Following execution of contract, additional detail will be provided identifying specific fibers to be spliced together. The contract drawings identify the number of fibers to be spliced and location of splices. All terminations of fiber optic cables to patch panels shall have pigtails that are fusion spliced.
FOC splices shall be fusion type. Every splice shall be tested. The mean splice loss shall be obtained by measuring the loss through the splice in both directions and then averaging the resultant values. The test shall be conducted at 1550 nanometers using an OTDR in conformance with Section 701-18, “Testing,” of these Special Provisions.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
176 of 244
169
At locations where new FOCs are being spliced together, the mean splice loss shall not exceed
0.07 dB per splice. If the mean splice loss exceeds 0.07 dB, then the Contractor shall cut out the splice and re-splice the cable until it passes. All costs asso ciated with re-splicing and retesting shall be included in the price paid for various other items of work and no separate payment will be allowed therefor.
At least 48 hours prior to the start of work at each location containing existing FOC, the Contractor shall notify the Engineer in writing of the schedule of all work activities at each site. The schedule shall include the time and date the Contractor intends to start work at each of the sites. Within 10 minutes after arriving at each existing FOC site for the first time, the Contractor shall take photos of the existing cables and any apparent damage to the existing cables. The Contractor shall submit quality copies of the photos on quality photo paper to the Engineer within 24 hrs. after the photos are taken. It shall be assumed that the existing cables are in pristine condition if the Contractor fails to take and submit the photos within the time frames specified above.
At locations where existing FOC cables are to be spliced, the Contractor shall properly clean, cut, and prepare the cable ends and fiber strands for splicing.
At locations where new FOC is to be spliced onto existing FOC, the mean splice loss shall be lower than 0.1 dB per splice, unless otherwise specified herein. If the mean splice loss is greater than 0.1 dB, then the Contractor shall re-splice and retest. If after the third attempt at obtaining a splice with a mean splice loss less than 0.1dB the splice still does not pass, then the Contractor shall average the results of the three previous tests. If the mean splice loss of the splice is average or less than average and does not exceed 3dB, then the splice is acceptable. If not, then Contractor shall re -splice and retest the loss until the result is average or less than average of all of the previous tests and does not exceed 3dB. If after a total of five attempts the mean splice loss continues to exceed 3 dB, then the Contractor shall contact the Engineer for direction.
The Contractor is not responsible for any preexisting conditions in the existing cable prior to the Contractor arriving at the site, however, the Contractor shall be held responsible for damage to existing cables resulting from the Contractor’s work activi ties or if the Engineer is of the opinion that the Contractor failed to properly perform work involving the existing cables that is covered under this contract ( i.e. take photos of the existing cable and submitting them prior to start of work ). All cost s associated with re- splicing and retesting shall be included in the price paid for various other items of work and no separate payment will be allowed therefor.
The field splices shall connect the fibers of the two FOC lengths together. These splices shall be placed in a splice tray and these splice tray(s) shall then be placed in the splice closure.
Fibers of the same buffer tube, but not being spliced shall be placed in a splice tray alongside spliced fibers. Buffer tubes that do not require enclosed fibers to be spliced shall not be disturbed and placed in the splice closure.
The termination splices shall connect the FOC span ends with pigtails. The termination splices shall be placed in a splice tray and the splice tray(s) shall then be placed in the fiber distribution unit (FDU). The individual fibers shall be looped one full turn within the splice tray to avoid micro bending.
A 50 mm minimum bend radius shall be maintained during installation and after final assembly in the optical fiber splice tray. Each bare fiber shall be individually restrained in a splice tray. The o ptical Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
177 of 244
170
fibers in buffer tubes and the placement of the bare optical fiber in the splice tray shall be such that there is no discernible tensile force on the optical fiber.
All splices shall be protected with a metal reinforced thermal shrink sleeve.
All fiber optic cables shall be labeled in the splice tray. Pigtail ends shall also be labeled to identify the destination of the fiber.
Contractor shall perform fusion splicing in clean environment. Personnel shall be trained, certified and have minimum of three years of experience.
Splices are only allowed where shown on the Plans, unless otherwise approved by the Engineer in writing.
Furnish and install heat-shrink fusion splice sleeves to all splices.
The Contractor is responsible for all testing and documentation required for approval and acceptance of the production, installation and operation of these materials and equipment. All indicators shall be verified to function correctly.
Attention is directed to “System Testing and Documentation,” elsewhere in these special provisions regarding testing the data transceiver/receivers.
701-17.4.5.1.1 Data Transmission Equipment.
Add the following new subsection:
701-17.4.5.1.1 Data Transmission Equipment. The data transmission equipment shall consist of a fiber optic modem, capable of transmitting a receiving data over the single mode fiber optic cable.
For this equipment the Contractor shall install additional 120 volt duplex outlets as required for connection of this equipment to 120 volt power. The connection shall provide isolation and surge protection. If required, additional outlets shall be protected and controlled through the installation of an additional circuit b reaker in the Model 332 Cabinet Power Distribution Assemble. This circuit breaker shall be clearly marked.
In order to ensure compatibility, all new fiber optic modems shall be Vilink Model 230 or an equivalent approved by the City of Vista Engineer. Prior to installation, the operation of all equipment shall be verified using the same type of cable it is to be installed with. The fiber optic path for each data link shall have been tested and verified in accordance with the Contract prior to the data transmitter/receiver installation.
701-17.4.5.1.2 Installation of Data Transmission Equipment in Traffic Signal Cabinet.
Add the following new subsection:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
178 of 244
171
701-17.4.5.1.2 Installation of Data Transmission Equipment in Traffic Signal Cabinet. The data transceiver shall be installed at the cabinet locations shown on the plans. The Contractor shall verify the desired physical space for the data transceiver with the Engineer prior to installation.
The Contractor shall furnish and install single mode fiber optic pig tails to connect the transceiver to the fiber distribution units. The pig tails shall have ST connectors. The Contractor is responsible for ensuring the connectors on the pig tails are fully compatible with those on the fiber distribution unit and the transceiver. The Contractor shall neatly route the pig tail from the transceiver to the distribution unit. No cables shall be installed with a bend radius less than the manufacturer's minimum recommended bending radius.
The data transceiver, also referred to as a fiber optic modem, shall accept data signals and convert them to a signal suitable for launching into one single mode optical fiber. The data transceiver shall fit into a small ruggedized metal package suitable for installation in a traffic signal controller cabinet.
The data transceiver shall have a center wavelength in the range from 80nm to 1310nm with an operating temperature from -29F to 165F.
The Contractor shall furnish and install a 12 volt DC 500mA power supply, as recommended by the manufacturer, to power to the data transceiver.
The Contractor shall input a data test signal into the data transceiver and set the optical power measured at the transceiver end of the fiber to the data transceiver sensitivity level. The optical signal shall then be connected to the data transceiver. The Engineer shall then qualitatively assess the data output. The Signal-to-Noise and signal-to-low frequency noise shall be measured and recorded.
701-17.4.5.1.3 Installation of Data Transmission Equipment in the Control Center.
Add the following new subsection:
701-17.4.5.1.3 Installation of Data Transmission Equipment in the Control Center. The data transceiver shall be installed in a standard nineteen-inch (19”) rack mountable card cage. The data out of the transceiver shall interface with the DB25 and RS232 / 422 port on the backside of the card cage.
The Contractor shall furnish and install single mode fiber optic jumpers to connect the transceiver to the fiber distribution unit. The jumpers shall have factory terminated ST connectors. The Contractor is responsible for ensuring the connectors on the jumpers are fully compatible with those on the fiber distribution unit and the transceiver. The Contractor shall neatly route the jumpers from the transceiver to the distribution unit. No cables shall be installed with a bend radius less than the manufact urer's minimum recommended bending radius.
The data transceiver, also referred to as a fiber modem, shall be connected by optical fiber to form a link having a center wavelength 1310nm. The data link is to provide point-to-point transmission and reception of data from signals using one single mode optical fiber as the transmission medium.
The data transceiver shall receive the optical signal launched into the single mode optical fiber of the corresponding data transceiver. The optical interface to the transceiver shall be an ST -style Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
179 of 244
172
connector. The data transceiver sensitivity shall be defined as the minimum optical power required operating at the minimum data link performance specifications. If the saturation level of the transceiver is not greater than the transceiver launch power level minus one dB, fixed attenuators shall be installed between the fiber and the transceiver to attenuate the received signal level. The data output interface from the data transceiver shall be a nickel-plated, ST connector.
701-17.4.5.1.4 Installation of Fiber Optic Node Transceiver.
Add the following new subsection:
701-17.4.5.1.4 Installation of Fiber Optic Node Transceiver. The Contractor shall perform pre - installation testing to verify that the transceiver and transceiver are compatible, meet manufacturer’s specifications and the requirements of these specifications.
The Contractor shall furnish and install a power supply, as recommended by the manufacturer, to power to the data transceiver.
The Contractor shall perform pre-installation testing to verify that the transmitter and receiver are compatible, meet manufacturer’s specifications and the requirements of these specifications.
The Contractor shall furnish and install fiber jumpers to connect the receiver to the fiber distribution unit. The Contractor shall neatly train all fiber strands together when routing them along the same path and shall neatly train them along the support rails in the equipment racks. No cables shall be installed with a bend radius less than the manufacturer’s minimum recommended bending radius.
The Contractor is responsible for all testing and documentation required for approval and acceptance of the production, installation and operation of these materials and equipment. All indicators shall be verified to function correctly.
Attention is directed to “System Testing and Documentation,” elsewhere in these special provisions regarding testing the data transceiver.
701-17.4.5.1.5 Connectors.
Add the following new subsection:
701-17.4.5.1.5 Connectors. Factory test results shall be documented and submitted to the Engineer prior to installing any of the connectors. Single mode connectors shall have a yellow color on the body and/or boot.
Field termination shall be limited to splicing of adjoining trunk cable ends and pigtail breakouts.
The pigtails shall utilize factory installed ST connectors.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
180 of 244
173
701-17.4.5.1.6 Fiber Distribution Unit in Cabinets.
Add the following new subsection:
701-17.4.5.1.6 Fiber Distribution Unit in Cabinets. The Contractor shall furnish and install a fiber distribution unit in each traffic signal controller cabinet having fiber installed as shown on the plans.
The units shall have provisions for storage of a fiber splice tray capable of housing up to twelve (12) single mode fiber splice tubes.
The fiber distribution unit shall be a rack mount, nineteen inch (19”) size, to be mounted inside the existing Cabinet. Each fiber distribution unit shall be able to hold a minimum of one (1) fiber splice tray. The fiber splice trays shall be metallic and capable of housing twelve (12) single mode fusion splice tubes.
701-17.4.5.1.6 Fiber Distribution Unit Payment. Payment for Fiber Distribution Unit (FDU) shall include full compensation for all labor, materials, and equipment required to furnish and install Corning fiber optic distribution unity with 1U rack mount housing, and splice cassette including all jumpers, CAT 6 ethernet patch cables, data cables, and all appurtenances necessary for communications per the project plans. Payment for this bid item shall be at the contract price per Each (EA).
701-17.4.5.1.7 INTENTIONALLY LEFT BLANK.
701-17.4.5.1.8 Fiber Optic Pig Tail Unit.
Add the following new subsection:
701-17.4.5.1.8 Fiber Optic Pig Tail Unit . The pig tail unit shall be composed of six (6) pre - connectorized fiber optic pig tails. All optical fibers shown on the plans to be connectorized shall be terminated with a ST connector. All cables shall use the same connectors. The connector shall not require a mechanical splice to a factory polished tip. All connectors must be pre -connectorized with pig tails that meet the fiber specifications under “Items 8-13.” The pig tail unit shall be composed of 6-900 micron color coded pig tails. The pig tails shall be two feet (2’) long.
The surface of the fiber end installed in a connector shall be free of scratches, pits and chips at two hundred times ( 200 x) magnification. No index-matching fluids, gels or anti -reflection coatings shall be applied to the end of the fiber.
The connectors shall conform to the following:
• Insertion Loss: 0.25 dB typical, 0.4 dB Maximum.
• Reflectance: Less than -50 dB at 1310 nm measured with a back reflection meter. • Optical Fiber Nominal Outside Diameter: 0.05 inch.
• Tensile Strength: Less than a 0.2 dB change, based upon a 22 lb. load without adhesive. • Temperature Cycling: Less than a 0.2 dB change, based upon -40F to +176F, 100 cycles. • Humidity: Less than 0.2 dB change, 140F at 95% relative humidity for 500 hours. • Durability: Less than 0.2 dB change per 1000 insertions, cleaned every 25th insertion. • Undercut/protrusion ±50 nm.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
181 of 244
174
• Apex offset less than 1.97 inch.
Connectorized fibers shall be clearly labeled using a labeling convention approved by the Engineer.
The Contractor is responsible for ensuring that existing cable and wiring is reconnected exactly as found and is left fully functional after new cables are installed. The Contractor shall conduct tests, in the presence of the Engineer, to record the operational condition of existing wires and cables prior to removal if it is suspected that such wires or cables are not currently fully functional.
701-17.4.5.1.9 Fiber Optic Cable (FOC) Payment.
Add the following new subsection:
Payment for Single Mode Fiber Optic Cable (SMFOC) shall include full compensation for all labor, materials, and equipment required to furnish and install a new trunk, all dielectric, fully water-blocked, loose tube, gel -free, Strand SMFOC, Coring 012ZU4 -T4F22D20 or approved equal, including coiling 50 feet of trunk strand SMFOC slack in every pull box or vault which has sufficient space per the project plans and cable manufacturer’s allowable minimum bending radius. Payment for this item shall be based on the actual quantity, Linear Feet (LF) per the bid items in the bid schedule.
701-17.4.5.2 Splicing.
Add the following paragraphs:
All permanent fiber optic cable splices shall be the fusion type and shall not exceed 0.15 dB loss per splice.
Splices shall be made in pull boxes, splice boxes, or housed in standard cabinets.
Splicing of fiber optic cable shall not be permitted except in emergency conditions.
The field splices shall connect the fibers of two (2) or more fiber optic cable lengths together as indicated on the conductor schedules. These splices shall be placed in a splice tray and these splice tray(s) shall then be placed in the splice enclosure.
The termination splices shall connect the fiber optic cable span ends with pigtails. The termination splices shall be placed in a splice tray. The individual fibers shall be looped one (1) full turn within the splice tray to avoid micro bending. A two -inch (2”) (50.8 mm) minimum bend radius shall be maintained during installation and after final assembly in the optical fiber splice tray. Each bare fiber shall be individually restrained in a splice tray. The optic fibers in buffer tubes and the placement of the bare optical fibers in the splice tray shall be such that there is no discernible tensile force on the optical fiber.
Fiber Field Splice Payment. Payment for fiber field splices shall include full compensation for all labor, materials, and equipment required to perform necessary splicing of the 12 -strand and/ or 24- strand trunk fiber cable with the 6 -strand fiber cable per the splice details on the project plans, not including the cost for the splice enclosures which are a separate bid item. All remaining unused fiber Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
182 of 244
175
strands in the trunk cable must remain intact and if cut, must be rejoined by splicing. Payment for this bid item shall be at the lump sum (LS) price.
701-17.4.5.2.1 Splice Enclosures.
Add the following new subsection:
701-17.4.5.2.1 Splice Enclosures. Fiber optic cable field splices shall be enclosed in splice enclosures which shall be waterproof, rodent proof and re -enterable. The fiber optic splice enclosure shall be suitable for a temperature range of 0°C to 50°C.
The fiber optic splice enclosure shall consist of an outer closure, an inner closure and complete with splice organizer trays, brackets, plugs, clips, cable ties and sealants as needed and shall conform to the following special provisions.
The size of the enclosure shall allow all the fibers of the largest fiber optic trunk cable or buffer tube to be spliced to a second cable or buffer tube of the same size, plus fibers from fiber optic pigtail cable. The enclosure shall be not more than 22 inches in length and not more than 6 inches in diameter.
All materials in the enclosures shall be nonreactive and shall not support galvanic cell action. The outer-closure shall be compatible with the other closure components, the inner closure, splice trays, and cables. The end plate shall consist of two sections and shall have capacity for two fiber optic trunk cables and fiber optic branch cables. The outer -closure shall protect the splices from mechanical damage, shall provide strain relief for the cable, and shall be resistant to salt corrosion. The outer - closure shall be waterproof, re-enterable and shall be sealed with a gasket. The outer-closure shall be flash-tested at 15 psi. The inner -closure shall be of metallic construction. The inner -closure shall be compatible with the outer closure and the splice trays and shall allow access to and removal of individual splice trays. The splice trays shall be compatible with the inner closure and shall be constructed of rigid plastic or metal. Adequate splice trays shall be provided to splice all fibers of the largest communication cable or buffer tube plus FPC in the splice cabinet. Vinyl markers shall be used to identify each spliced fiber in the trays as described under "Fiber Optic Cable Labeling" elsewhere in these special provisions. Each splice shall be individually mounted and mechanically protected in the splice tray.
The Contractor shall install the fiber splice enclosure in the splice vault or cabinet as shown on the plans where splicing is required. The Contractor shall provide all mounting hardware required to securely mount the fiber optic splice enclosures to the splice vault. The fiber splice enclosure shall be mounted as shown on the plans in a manner that allows the cables to enter at the end of the enclosure.
The unprotected fibers exposed for splicing within the enclosure shall be protected from mechanical damage using the fiber support tube or tubes and shall be secured within the fiber splice enclosure.
Upon completion of the splices, the splice trays shall be secured to the inner closure. The enclosure shall be sealed using a procedure recommended by the ma nufacturer that will provide a waterproof environment for the splices. Encapsulant shall be injected between the inner and outer closures. Care shall be taken at the cable entry points to ensure a tight salt resistant and waterproof seal is made which will not leak upon aging. It is not acceptable to have multiple cables enter the fiber splice enclosure through one hole.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
183 of 244
176
A splice enclosure shall be provided at all locations identified on Plans. If the Contractor requires additional splice enclosures to support the pulling plan, these enclosures shall be provided and installed at no additional cost to the City.
701-17.4.5.2.2 Splice Enclosure Payment. Payment for Splice Enclosure shall include full compensation for all labor, materials, and equipment required to furnish and install Corning splice enclosure, models SCF -4C-18-01 (or City approved equal) per the project plans and shall have a minimum 48 -fiber splice capability; provide cable ports as required; have a moisture -tight sealing arrangement; and have re-entry capability. Payment for this bid item shall be at the contract price per Each (EA).
701-17.6 Detectors.
701-17.6.3 Inductive Loop Detectors.
701-17.6.3.1 General.
Add the following paragraphs to this subsection:
The Contractor shall mark out and document all locations of existing loop detectors, advanced loops, and home runs, before they are taken out of service, so that the existing loops can be replaced in-place. The mark -outs and documentation shall be approved by the inspector before work that disturbs the loops begins. The Contractor shall coordinate with the Inspector to confirm that all loops are working prior to being taken out of service.
New loops shall be installed in the new pavement surface course. Bicycle-sensitive detector loops shall be installed where shown on the Plans, or as specified. After the pavement work is completed, the Contractor shall return the detector loops to full operation.
701-17.8 Remove all Radio Equipment
Add the following new subsection:
701-17.8.1 Remove Radio Payment. Payment shall include full compensation for all labor, materials, and equipment required to remove and salvage existing radio equipment including cabling and deliver to the City per the project plans. Payment for this bid item shall be at the contract price per Each (EA).
701-18 TESTING.
701-18.1 General.
701-18.1.1 Fiber Optic Cable Testing – General.
Add the following new subsection:
701-18.1.1 Fiber Optic Cable Testing – General. Testing shall follow Caltrans procedure in fiber optic testing and the Contractor shall provide and complete the “Link Loss Budget Work Sheet.”
Testing shall include the tests on elements of the passive fiber optic components:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
184 of 244
177
(1) at the factory,
(2) after delivery to the project site but prior to installation, (3) after installation but prior to connection to any other portion of the system, and (4) during the final system testing.
The active components shall be tested after installation. The Contractor shall provide all personnel, equipment, instrumentation and materials necessary to perform all testing. The Engineer shall be notified in writing a minimum of two (2) Working Days prior to all field tests. The notification shall include the exact location of the system to be tested.
Documentation of all test results shall be provided to the Engineer for approval within two (2) Working Days after the test involved. The Contractors attention is directed to Record Drawings (“As - Builts”) elsewhere in these special provisions, regarding the requirements for recording test results.
Attenuation tests shall be performed with an OTDR capable of recording and displaying anomalies of point zero two (0.2) dB as a minimum. Single mode fibers (SM) shall be tested at 1310 nm and 1550 nm. The OTDR shall have a printer capable of producing a verifying test trace with fiber identification as shown in the “Link Loss Budget Work Sheet”, numerical loss values, the date and the operator’s name. It shall also have a DOS based three and one -half inch (3 -1/2”) disk recording capability that has assoc iated software to do comparisons and reproductions on eight and one -half inch by eleven inch (8.5” x 11”) paper, via a personal computer.
Prior to arrival of the cable, the Contractor shall provide detailed test procedures for all field testing to the Engineer. The procedures shall include the tests involved and how the tests are to be conducted.
These test plans shall be subject to the approval of the Engineer.
701-18.1.2 Factory Testing.
Add the following new subsection:
701-18.1.2 Factory Testing. Verification of the fiber specifications as listed in the Fiber Characteristics Table shall be supplied by the Manufacturer with the appropriate documentation. After cabling, before shipment but while on the shipping reel, one hundred percent (100%) of all fibers shall be tested for attenuation. Copies of the results shall be (1) maintained on file at the Contractor’s, Manufacturer’s and Owner’s place of business with a file identification number for a minimum of ten (10) years, (2) attached to the cable reel in a waterproof pouch, and (3) submitted to the Contractor and to the Engineer prior to the delivery of the cable to the jobsite.
701-18.1.3 Arrival on Site.
Add the following new subsection:
701-18.1.3 Arrival on Site. The cable and reel shall be physically inspected by the Contractor on delivery and one hundred percent (100%) of the fibers shall be tested with the OTDR for attenuation to confirm that the cable meets requirements. Test results shall be recorded, dated, compared and filed with the copy results shall be recorded, dated, compared and filed with the copy accompanyi ng Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
185 of 244
178
the shipping reel in a weather proof envelope. Attenuation deviations from the shipping records greater than five percent (5%) shall be brought to the attention of the Engineer in writing. The cable shall not be installed until completion of this test sequence and written approval by the Engineer is received. Copies of traces and test results shall be submitted to the Engineer. If the OTDR test results are unsatisfactory, the reel of fiber optic cable shall be considered unacceptable and all records corresponding to that reel of cable shall be marked accordingly. The unsatisfactory reels of cable shall be replaced with new reels of cable at the Contractor’s expense. The new reels of cable shall then be tested to demonstrate acceptability. Copies of the test results shall be submitted to the Engineer for approval.
701-18.1.4 After Cable Installation Testing.
Add the following new subsection:
701-18.1.4 After Cable Installation Testing. After the fiber optic cable has been pulled but before breakout and termination, one hundred (100%) percent of all the fibers shall be tested with the OTDR for attenuation. Test results shall be recorded, dated, compared and filed with the previous copies of these tests. Copies of traces and test results shall be submitted to the Engineer for approval. If the OTDR test results are unsatisfactory, the fiber optic cable segment will be unacceptable. The unsatisfactory segment of cable shall be replaced with a new segment, without additional splices, at the Contractor’s expense. The new segment of cable shall then be tested to demonstrate acceptability.
Copies of the test results shall be submitted to the Engineer for approval.
701-18.1.5 Testing Outdoor Splices.
Add the following new subsection:
701-18.1.5 Testing Outdoor Splices. At the conclusion of all outdoor splices at one (1) location, and before they are enclosed and sealed, all splices shall be tested with the OTDR, in both directions.
Splice segments shall be tested at 1310 nm and at 1550 nm. Individual fusion splice losses shall not exceed 0.2 dB. Measurement results shall be recorded, dated, validated by the OTDR trace printout and filed with the records of the respective cable runs. Copies of traces and test results shall be submitted to the Engineer. If the OTDR test results are unsatisfactory, the splice shall be unacceptable. The unsatisfactory splice shall be replaced at the Contractor’s expense. The new splice shall then be tested to demonstrate acceptability. Copies of the test results shall be submitted to the Engineer for approval.
701-18.1.6 System Verification at Completion – OTDR Testing.
Add the following new subsection:
701-18.1.6 System Verification at Completion – OTDR Testing. Once the passive cabling system has been installed and is ready for activation, one hundred percent (100%) of the fiber links shall be tested with the OTDR for attenuation. Test results shall be recorded, dated, compared and filed with previous copies. Copies of traces and test results shall be submitted to the Engineer for approval. If Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
186 of 244
179
the OTDR test results are unsatisfactory the link shall be replaced at the Contractor's expense. The new link shall then be tested to demonstrate acceptability. Copies of the test results shall be submitted to the Engineer for approval.
701-18.1.7 Installed System Link Loss Budget.
Add the following new subsection:
701-18.1.7 Installed System Link Loss Budget. The Link Loss Budget Worksheet shall be completed for each communication point, as defined in the conductor schedules, using the data gathered throughout the installation process. The completed worksheets shall be included as part of the system documentation and in the Record Drawing (“As -Built”) Plans. Refer to Record Drawings ("As-Built”) Plans in this specification for additional requirements.
The total connector losses shall be calculated by the Contractor by summing the individual attenuation values for each connector pair in the path, excluding the transmitter and receiver connectors.
The total splice losses shall be calculated by the Contractor by summing the individual attenuation values for each splice in the link.
The total of other losses shall be calculated by summing the individual attenuation values for each component in the link not previously addressed. These items may include, but are not limited to, couplers, splitters, routers and switches.
The Total System Loss shall be recorded on the Link Loss Budget Worksheet.
701-18.1.8 Test Failures.
Add the following new subsection:
701-18.1.8 Test Failures. If during any of these system verification tests, the results prove to be unsatisfactory, the fiber optic cable and or defective splice enclosures will not be accepted. The unsatisfactory components shall be replaced at the Contractor's expense. The new segment of cable shall undergo the same testing procedure to determine acceptability. Copies of the test results shall be submitted to the Engineer for approval. The removal and replacement of a segment of cable shall be interpreted as the removal and replacement of a single contiguous length of cable connecting two (2) splices, two (2) connectors, or a splice and a connector. The removal of only the small section containing the failure and therefore introducing new unplanned splices will not be allowed.
The Contractor shall perform fiber continuity and attenuation testing and fiber backscatter measurements at several stages in the system construction.
OTDR (optical time domain reflectometer) testing shall be done at the following points in the system construction:
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
187 of 244
180
• At cable delivery (reel test)
• Following cable installation prior to connectorization, termination or splicing. • End to End following installation of all pigtails, connectors and termination devices
In addition, the final test (pos t-connectorization test) shall be completed with an optical power meter and light source.
All fibers shall be tested end to end. The end to end total attenuation shall not exceed the sum of the maximum allowable attenuation for the component cable segments, splices and typical loss for connectors. Nor shall the attenuation from an individual connector exceed the maximum allowable losses. If the fibers in the cable exceed the allowable loss, the Contractor shall take corrective measures to bring the cable’s total attenuation below the allowable limit, including replacement of the cable at the Contractor’s expense.
The Contractor shall perform all OTDR testing in the presence of the Engineer. The Engineer shall attach their written mark to all test documentation made by the Contractor at the time of the test.
Testing performed by the Contractor and not witnessed by the Engineer shall not be accepted, re - testing will be required.
The Contractor shall verify that the attenuation and optical continuity of each active and spare optical fiber in the cable plant satisfies the specified requirements.
Attenuation and continuity shall be measured at the operational wavelength of the equipment being used on the link. If the operational wavelength is unknown, the attenuation shall be measured at both 1310nm and 1550nm.
Attenuation shall be calculated by the insertion method. Calibration between the light source and the power meter shall be performed at the beginning of each day of testing.
The Contractor shall record the attenuation of each optical link. Optical links shall be identified in the test results by identifying the label identifier on each drop cable and by identifying the field cabinet at which light was launched and at which it was received.
An acceptable OTDR shall be used to measure the backscattered light profile of the designated optical links. The OTDR shall include all necessary hardware to couple it to either a connectorized or non-connectorized fiber. While performing backscatter mea surements, the end of the fiber link that is not connected to the OTDR shall be capped to prevent the ingress of infrared radiation. The OTDR used shall be provided with certification of its most recent calibration and shall not be more than twelve (12) months old.
A three thousand two hundred and eighty foot (3,280’) launch cable shall be inserted between the OTDR and the optical link to overcome the initial “dead zone” on the fiber trace.
The OTDR testing shall be done at a scale of at least one (1) dB per division on the vertical scale.
It shall have a dynamic range of at least thirty ( 30) dB at 1 ,310 nm and distance measurement accuracy of plus or minus one-one hundredths of one percent (± 0.01%).
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
188 of 244
181
The Contractor shall record each optical link measured for attenuation by means of an electronic data file of the OTDR trace. The Contractor shall supply a licensed software package (installed on the Network Management Computer) to read, store, compare, and analyze the electronic data files created by the OTDR instrument. A hard copy printout of each trace shall also be provided, which shall include the measurements listed below. The OTDR traces shall be compared with this software following each testing stage of the installation. Documentation of this comparison shall be provided to the Engineer.
Optical links shall be designated in the test results by indicating the label identifier on each drop cable and by identifying the field cabinet at which light was launched.
The OTDR traces shall be marked noting the physical location of each splice or connector. The notation shall be clear and understandable.
The OTDR shall be of a manufacture recommended by the cable supplier. The OTDR operator shall hold a current operators certificate for the equipment used. This certificate shall represent not less than sixteen ( 16) hours of training from the equipment manufacture. This certificate shall be presented to the Engineer at the start of testing.
The test results shall include the following measurements:
• total measured length of the optical link
• total attenuation of the optical link
• mean attenuation of each splice in the optical link under test • wavelength of the measurement
Attenuation shall be measured in decibels.
The Contractor shall demonstrate that each fiber and splice satisfies the specified requirements.
Add the following new subsection:
701-18.1.9 System Testing and Documentation.
Description: The system testing and documentation shall cover pre -installation testing, subsystem testing, acceptance testing, physical inspection and functional testing. Performance testing, final acceptance and system documentation that is required to validate the operational performance of the system and described elsewhere in these special provisions.
Configuration: The contractor shall provide a technician to test and verify the operation of the Traffic Signal Interconnect System. The contractor shall show that all signals included in the project are properly connected and configured and can communicate with each other and with the existing BI Tran Systems/QuicNet 4 Advanced Traffic Management System installed on the Traffic Server at Vista City Hall at 200 Civic Center Drive. The technician shall ensure that local communication addresses are correctly set at each controller and that all modems are properly configured and transmitting data.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
189 of 244
182
Test Plan: The Contractor shall develop and submit within thirty (30) Working Days to the Engineer an installation and test plan for approval, which details the method of installation and all testing for all material, equipment, and cable and the associated schedule of activities, based on these special provisions, plans, the manufacturer's recommended test procedures, and industry standard practices. Five (5) copies of the test plan shall be submitted to the Engineer for approval. The Engineer will revie w then approve or disapprove the plan within four (4) weeks. If the Engineer rejects the test plan the Contractor shall submit a revised test plan within ten (10) Working Days for review and approval by the Engineer. No testing shall be performed until Contractor's test plan has been approved by the Engineer. The tests shall quantitatively demonstrate that the design and production of material and equipment meet the requirements of these special provisions and plans. All test results, including results of failed test or re -tests, shall be submitted and delivered to the Engineer and a copy placed with the equipment at the site. All test equipment shall be supplied by the Contractor. All testing shall be done in the presence of the project manager and signed off by the project manager.
The Contractor shall notify the Engineer of their intent to proceed with functional and subsystem testing forty-eight ( 48) hours prior to commencement of each test. Full environmental conditions shall be tested as part of the functional tests for field equipment. Subsystem testing and inspections shall include visual inspection for damaged or in correct installation, adjustments and alignment, and measurement of parameters and operating conditions.
Pre-Installation
Testing: Pre-inspection testing shall include testing of all material, equipment and cables in a laboratory environment prior to delivery to the site. Use of laboratory facilities, shall be arranged by the Contractor. The tests shall either be conducted at the eq uipment manufacturer's premises or at a laboratory arranged by the Contractor.
All material, except test equipment and special tools, shall be bench tested in accordance with the following paragraphs, which include those items described elsewhere requiring pre-installation testing for each individual item where applicable.
All active equipment shall be connected to normal operating power, energized and subjected to normal operating conditions for a continuous period of time in the laboratory of not less than forty-eight (48) hours.
Functional testing shall be performed by the manufacturer on all material prior to delivery to the site. The functional tests shall be performed in accordance with an approved test plan. Any material or equipment which fails to meet the requirements of the Contract shall be repaired or replaced and the test shall be repeated until satisfactory. All functional test results, including results of Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
190 of 244
183
failed tests or re-tests, shall be submitted and delivered with all material and equipment delivered to the site.
Full performance tests shall be performed by the manufacturer or by the Contractor on not less than five percent (5%) or at least one unit of material selected at random from the normal production run. The full performance test shall be performed in accordance with a test plan developed by the Contractor and approved by the Engineer.
Subsystem
Testing: Subsystem testing shall encompass the testing of all material, equipment and cable after installation, but prior to acceptance tests. These tests shall be done in accordance with the performance testing called out under each individual item in these special provisions.
Equipment and hardware shall be installed in accordance with the plans and special provisions. All material, equipment and cable shall be tested after installation at the site. Subsystem testing and inspections shall include visual inspection for damaged or incorrect installation, adjustments and alignment, and measurement of parameters and operating conditions. The Contractor shall notify the Engineer of their intent to proceed with subsystem testing forty- eight (48) hours prior to commencement of each test.
Installation documentation and test results shall be provided for all material, equipment and cable prior to commencement of acceptance tests. Installation documentation shall be in accordance with these special provisions and shall include the following as appropriate:
• Model, part number and serial number for all material and equipment. • Test equipment model number, serial number, settings, and date of last calibration. • All strap and switch settings.
• Record of all adjustments and levels.
• Alignment measurements.
• Identification of interconnections.
• All factory, laboratory and site test results.
Acceptance
Testing: The acceptance testing shall be conducted in accordance with the approved test plan. The acceptance testing shall include conducting acceptance tests and subsequent re-tests, and documentation of the test results.
Final acceptance tests shall be conducted after the site and subsystem test results have been reviewed and accepted by the Engineer. These tests include the complete system in normal operations. The test plan shall address the full testing requirements of the specifications. The test plan shall detail all tests to be performed, the test results which are expected and the test schedule.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
191 of 244
184
The acceptance test plan shall include the following major test and acceptance categories:
• Physical inspection
• Functional tests
• Performance tests
The Contractor shall test the communications system according to the approved acceptance test plan and shall provide all test equipment, labor and ancillary items required to perform the testing.
The test equipment shall be certified to be calibrated to the manufacturer's specifications. The model and part numbers and date of last calibration of all test equipment shall be included with the test results.
Acceptance testing shall not commence until all material required by these special provisions and plans are delivered, installed, and aligned and all production test and site test documentation and results have been approved by the Engineer.
All acceptance test results shall be fully documented and such documentation provided as a condition of acceptance.
Physical
Inspection: The Contractor shall provide documentation to prove delivery of all material, equipment, cable and documentation. If any material or documentation is outstanding or have been replaced under pre-acceptance warranty a physical inspection and documentation shall be provided for this material. The physical inspection shall consist of inspecting all instal led material to ensure workmanship satisfies the specified requirements.
Functional Tests: The Contractor shall test all system functions to demonstrate that all data circuits and all equipment satisfy the functional requirements of the specifications.
The connectivity of each data channel shall be demonstrated. The Contractor shall document all functional test results. In the event that any aspect of the functional tests are determined by the Engineer to have failed, the Contractor shall cease all acceptance testing and determine the cause of the failure and make repairs to the satisfaction of the Engineer. Acceptance testing shall, at the discretion of the Engineer, be repeated beginning from the start of functional tests.
Performance
Tests: The Contractor shall conduct operational performance tests on the following:
• Response to alarm inputs
• System diagnostics
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
192 of 244
185
If any circuit or element fails to satisfy the specified performance requirements the Contractor shall determine the cause and correct the failure to the satisfaction of the Engineer. The full performance tests shall be repeated under operating conditions as determined by the Engineer.
System
Documentation: The Contractor shall submit a draft copy of all documentation for review and approval prior to production of documentation. The Engineer will review and approve or reject the draft documentation within four (4) weeks of receipt.
The Contractor shall modify the documentation if required and submit provisional documentation.
The Engineer will approve or reject the provisional documentation within three weeks of receipt. The Contractor shall arrange for re -submission in a timely ma nner to meet the schedule in the case that the documents are rejected.
Draft documentation shall be submitted eight weeks prior to the start of installation. The draft documentation shall show the general approach in preparing the final manuals.
Upon approval of the draft documentation provisional documentation shall be supplied three (3) weeks prior to the start of site testing. The provisional documentation shall be of the same format as the final manuals but with temporary insertion for items which cannot be finalized until the system is completed tested and accepted. Final documentation shall be submitted no later than four (4) weeks after completion of the acceptance tests and shall incorporate all comments made during the approval stages. The Contractor shall be responsible for all delay caused by non -compliance to the specified requirements.
Final documentation shall be approved prior to its production. Ten copies of all final documents shall be delivered. The copies shall be on eight and one-half inch by eleven inch (8.5” x 11”) paper and bound in three -ring hard-covered binders complete with dividers. Also the documentation shall be furnished electronically in “Word” format on three and one -half inch (3 -½”) disks . System documentation shall be arranged in an operation and maintenance (O & M) manual format providing all the information necessary to operate, maintain and repair the equipment and cable to the lowest module or component level. The operation and maintenance manual shall as a minimum consist of the following sub-section as described below:
Master
Items Index: This shall be the first section of the O & M manual. The section shall describe the purpose of each manual and brief description to the directory of the manual. It shall also reference equipment manuals as required for additional and support material.
System
Description and
Technical Data: This section shall contain an overall description of the system and associated equipment and cables with illustrative block diagrams. This section shall identify all equipment and cables in the system stating the exact module and option number that are employed in the system. Technical data specification and settings for every type of equipment or cable shall be provided. Any modification that has been done on the equipment shall be clearly described.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
193 of 244
186
Theory of
Operation: The manual shall contain a functional description of each element of the system, explaining how each function is being achieved separately and how each element works together to form the complete system.
Software
Documentation: Proper documentation for all software shall be provided. The software documentation shall include a clear description of the system's functionalities and specifications. Description of each software module and program shall be provided. The Contractor shall supply related programming and system user manuals, application and utilities software user manual and all associated proprietary software manuals. Software listing of all custom programs shall also be provided, as well as a copy of any software source code.
Operations: The manual shall describe how to operate the system and each particular type of equipment and software. Equipment layout, layout of controls, displays, software operating procedures and all other information required to correctly operate the system and each functional unit shall be provided. Procedures shall also be provided for initial tune -up of the system and adjustment and checkout required to ensure that the system is functioning within the performance requirements. Warning of special procedures shall be given. The functions and setting of all parameters shall be explained.
Corrective
Maintenance: The manual shall include fault diagnostic and repair procedures to permit the location and correction of faults to the level of each replaceable module.
Procedures shall include alignment and testing of the equipment following repair, the test equipment, tools, diagnostic software required and the test set up.
Preventative
Maintenance: The manual shall include procedures for preventative maintenance in order to maintain the performance parameters of the system, equipment and cables within the requirements of the specifications.
Parts List: The manual shall include a list of all replaceable parts with exact parts description and number and a directory of recommended suppliers with correspondence address, telephone and facsimile (FAX) numbers.
Test Results: This section shall include a copy of the results for all he tests that have been conducted for the contract.
System schematic drawings shall be provided to identify the type of equipment at each location and the function of all equipment. The drawings shall also show how the system is interconnected. A comprehensive list of cabling and wiring shall be provided to clearly identify the interconnection and labeling.
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
194 of 244
187
The Contractor shall cooperate and coordinate with Contractors performing related contracts, to the extent feasible, to facilitate overall system testing.
Replace the entire subsection with the following:
701-18.2 Testing Payment. Payment for Fiber Testing, Documentation, and System and Acceptance Testing shall include full compensation for all labor, materials, and equipment required to test the fiber optic cable installed, spliced, and terminated as part of the project including system acceptance testing.
This item includes pre-installation and post installation testing of the cable, conducting acceptance tests and subsequent re-tests, and documentation of the test results which must be provided as a condition of project acceptance. The City shall approve the test results before final acceptance. Payment for this bid item shall be at the lump sum (LS) price.
701-20 SALVAGE.
Replace the entire subsection with the following:
701-20 SALVAGE. The Contractor shall salvage the existing traffic signal equipment including radio equipment, associated cabling, etc. as shown on the Plans or specified by the Engineer to be salvaged.
The Contractor shall deliver any salvaged equipment to the Agency’s storage yard at 2430 Lupine Hills Drive. Any items not specified to be salvaged shall become the property of the C ontractor and shall be removed from the Work site. Any salvage value shall be reflected in the Bid.
Care shall be exercised in removing equipment to be salvaged so that it will remain in the condition existing prior to its removal. To avoid any live wires remaining in service, the entire length of wire extending to traffic signal pole(s) being removed shall be disconnected at the power supply and removed from the site. Complete restoration of affected surface improvements shall be required.
***END OF SECTION***
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
195 of 244
188
INTENTIONALLY LEFT BLANK
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
196 of 244
TRAFFIC SIGNAL INTERCONNECT PLANS FOR
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
TRAFFIC SIGNAL INTERCONNECT NOTES
1. CONDUIT RUNS ARE SHOWN ON THE PLANS IN SCHEMATIC FORM ONLY.
2. CONTRACTOR SHALL VERIFY UNEAR FEET OF CONDUIT AND FIBER OPTIC CABLE BY FIELD INSPECTION.
3. DISTANCES SHOWN ON THE PLANS ARE APPROXIMATE. CONTRACTOR SHALL CAREFULLY
MEASURE ACTUAL DISTANCES AND MAKE ALLOWANCE FOR SLACK BEFORE CUTTING FIBER OPTIC CABLE.
4. ALL TRENCHING FOR CONDUIT INSTALLATION MUST BE ACCOMPLISHED USING UNDERGROUND BORING METHODS UNLESS SPECIFICALLY NOTED ON THE PLANS.
5. CONDUITS MUST BE INSTALLED WITHIN THREE FEET OF THE FACE OF CURB OR, IF NO CURB EXISTS. WITHIN TWO FEET OF THE EDGE OF PAVEMENT, EXCEPT AS NECESSARY TO AVOID CONFLICTS.
6. IF OPEN TRENCHING IS ALLOWED FOR CERTAIN SEGMENTS, THEN TRENCH PAVING MUST
BE PERFORMED IN ACCORDANCE WITH CITY OF VISTA STANDARD DRAWING NUMBER SRF-8A & B. TYPE B. °- 1DPE SPECIE -
7. FIBER OPTIC CABLE SHALL BE INSTALLED IN 2 PVC CIIEvl ,. 80--C;;;`^;;,'1T.
8. ALL CONDUIT BENDS ARE TO BE FACTORY MADE.
9. PULL BOXES SHALL BE NO. 6E UNLESS OTHERWISE NOTED ON THE PLANS, SPACED NO MORE THAN 500' APART AND SHALL NOT BE CLOSER THAN THREE FEET TO DRIVEWAYS.
10. PULL BOX LOCATIONS BETWEEN INTERSECTIONS SHOWN ON THE PLANS ARE
APPROXIMATE AND MAY BE FIELD LOCATED BY THE CONTRACTOR WITH THE APPROVAL OF THE CITY INSPECTOR TO AVOID OBSTRUCTIONS AND FACILITATE CONSTRUCTION.
11. PULL BOXES SHALL NOT BE LOCATED IN OR WITHIN 1' OF ANY PART OF ANY CURB RAMP ( SLOPED PORTIONS OF THE RAMP; WINGS GROOVES; OR LANDINGS).
12. ALL PULL BOX AND VAULT COVERS SHALL BE MARKED WITH THE WORDS SIGNAL COMMUNICATIONS.
13. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO DETERMINE THE EXACT LOCATION OF ALL LOOP DETECTORS PRIOR TO COMMENCING WORK IN THE AREA. THE
CONTRACTOR IS RESPONSIBLE FOR AVOIDING ALL LOOP DETECTORS DURING
CONSTRUCTION AND SHALL NOT CUT OR BREAK ANY LOOPS, ANY DAMAGE TO
EXISTING LOOP DETECTION DURING CONSTRUCTION SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO REPLACE. BORING UNDER LOOP DETECTOR LEAD-IN CABLE IS ALLOWED PROVIDED THAT A MINIMUM 5' DISTANCE BE OBSERVED ON EACH SIDE
OF THE LOOP, AND OPERATIONS DO NOT RESULT IN PAVEMENT SAG OR LOOP DAMAGE,
14. CONTRACTOR SHALL REPLACE, AT CONTRACTOR'S EXPENSE, ANY FIBER OPTIC CABLE IN WHICH THE ATTENUATION OF ANY SINGLE MODE STRAND AT 1310 NM EXCEEDS 0«4DB-[KM, EXCLUDING SINGLE POINT EVENTS AT AUTHORIZED SPLICES AND
CONNECTORS,
15. WHEN THREE OR MORE FIBER OPTIC CABLES ENTER AN ENCLOSURE, EACH FIBER OPTIC
CABLE SHALL BE LABELED INDICATING THE LOCATION OF THE FAR END OF THE FIBER OPTIC CABLE.
16. DEFLECTION UMITS OF ALL SINGLE MODE FIBER OPTIC CABLE SHALL NOT EXCEED 20 TIMES THE OUTSIDE DIAMETER OF THE FIBER OPTIC CABLE BEING INSTALLED.
17. CONCRETE SIDEWALKS NEAR CONTROLLER CABINETS THAT ARE IN CONFLICT WITH
PROPOSED CONDUIT ROUTING AND IMPRACTICABLE TO BORE OR TUNNEL UNDER SHALL
BE REMOVED AND REPLACED BETWEEN EXPANSION JOINTS, AND NOT SAW CUT THROUGH SLAB. REMOVAL AND REPLACEMENT OF CONCRETE SHALL INCLUDE COMPLETE SLABS.
18. A SPANDREL SECTION OF AN EXISTING CROSS GUTTER THAT IS IN CONFUCT WITH
PROPOSED CONDUIT ROUTING AND IMPRACTICABLE TO BORE OR TUNNEL UNDER SHALL
BE REMOVED AND REPLACED BETWEEN EXPANSION JOINTS, AND NOT SAW CUT THROUGH THE SLAB. REMOVAL AND REPLACEMENT OF CONCRETE SHALL INCLUDE COMPLETE SPANDREL SECTIONS FROM JOINT TO JOINT.
19. AN AS - BUILT" DRAWING CLEARLY SHOWING THE ACTUAL LOCATIONS OF ALL SYSTEM /
COMPONENTS AND OTHER IMPROVEMENTS SHALL BE SUBMITTED BY THE
CONTRACTOR AND APPROVED BY THE CITY ENGINEER PRIOR TO THE ACCEPTANCE OF THE IMPROVEMENTS.
20. ALL EQUIPMENT AND PARTS CALLED OUT ON THE PLANS TO BE SALVAGED MUST BE DELIVERED TO THE CITY'S PUBLIC WORKS SATELLITE YARD LOCATED AT 2430 LUPINE HILLS DRIVE. HOWEVER, THE CONTRACTOR MUST FIRST CONTACT ONE OF THE
FOLLOWING PUBLIC WORKS STAFF MEMBERS AT LEAST TWO WORKING DAYS IN ADVANCE TO COORDINATE DELIVERY OF THE SALVAGED EQUIPMENT AND PARTS:
KEITH GARDNER....76O.518.4738
JD RUBIDOUX... 760.644.6797
SPECIAL NOTES
1. THE FOLLOWING NOTES ARE PROVIDED TO GIVE INSTRUCTIONS TO THE CONTRACTOR BY THE ENGINEER OF WORK. THE CITY ENGINEER'S SIGNATURE ON THESE PLANS DOES
NOT CONSTITUTE APPROVAL OF ANY OF THESE NOTES, AND THE CITY WILL NOT BE RESPONSIBLE FOR THEIR ENFORCEMENT.
2. NEITHER THE OWNER NOR THE ENGINEER OF WORK WILL ENFORCE SAFETY MEASURES OR REGULATIONS. THE CONTRACTOR SHALL DESIGN, CONSTRUCT, AND MAINTAIN ALL
SAFETY DEVICES, INCLUDING SHORING, AND SHALL BE SOLELY RESPONSIBLE FOR CONFORMING TO ALL LOCAL, STATE, AND FEDERAL SAFETY AND HEALTH STANDARDS.
LAWS, AND REGULATIONS.
3. CONTRACTOR SHALL MAKE EXPLORATION EXCAVATIONS AND LOCATE EXISTING
UNDERGROUND FACILITIES SUFFICIENTLY AHEAD OF CONSTRUCTION TO PERMIT
REVISIONS TO PLANS IF REVISIONS ARE NECESSARY BECAUSE OF ACTUAL LOCATION OF EXISTING FACILITIES. NOTIFY ENGINEER OF WORK OF ANY DISCREPANCIES BETWEEN THESE PLANS AND ACTUAL FIELD CONDITIONS PRIOR TO STARTING CONSTRUCTION.
4. LOCATION AND ELEVATION OF IMPROVEMENTS TO BE MET BY WORK TO BE DONE
SHALL BE CONFIRMED BY FIELD MEASUREMENTS PRIOR TO CONSTRUCTION OF NEW WORK.
5. BEFORE EXCAVATING FOR THIS CONTRACT, VERIFY LOCATION OF UNDERGROUND UTILITIES. THE EXISTENCE AND LOCATION OF ANY UNDERGROUND UTILITY PIPES OR
STRUCTURE SHOWN ON THESE PLANS HAS BEEN OBTAINED FROM AVAILABLE RECORDS ONLY AND MAY NOT REFLECT ALL EXISTING UTILITIES. LOCATIONS OF ALL EXISTING
UTILITIES SHALL BE CONFIRMED BY FIELD MEASUREMENTS BY CONTRACTOR PRIOR TO CONSTRUCTION OF WORK.
6. CONTRACTOR IS REQUIRED TO TAKE PRECAUTIONARY MEASURES TO PROTECT THE
UTILITY LINES SHOWN HEREON AND ANY OTHER EXISTING LINES NOT OF RECORD OR NOT SHOWN ON THESE PLANS.
7. WHERE TRENCHES ARE ADJACENT TO FUTURE BUILDING SITES, SOILS REPORTS WHICH
CERTIFY THAT TRENCH BACKFILL WAS COMPACTED AS DIRECTED BY THE SOILS
ENGINEER IN ACCORDANCE WITH THE ON - SITE EARTHWORK SPECIFICATIONS SHALL BE SUBMITTED TO THE ENGINEER OF WORK BY A QUALIFIED SOILS ENGINEER.
8. SAFETY FENCES SHALL BE PROVIDED BY THE CONTRACTOR WHERE REQUIRED BY THE CITY ENGINEER.
9. DURING ACTIVE CONSTRUCTION , AREAS SHALL BE WATERED TO REDUCE FUGITIVE DUST.
10. CONTRACTOR SHALL ADJUST ALL PROPOSED AND EXISTING FACILITIES TO GRADE.
11. CONTRACTOR SHALL REMOVE/REPLACE/RELOCATE ALL EXISTING FACILITIES REQUIRED TO INSTALL PROPOSED IMPROVEMENTS.
12. CONTRACTOR SHALL REMOVE/REPLACE/RELOCATE ANY LANDSCAPING/HARDSCAPING
WHICH CONFLICTS IN ANY WAY WITH THE INSTALLATION OR PROPER FUNCTIONING OF THE PROPOSED IMPROVEMENTS.
13. CURB HEIGHT SHALL BE 6" FACE UNLESS OTHERWISE NOTED ON THE PLANS.
CONSTRUCTION NOTES
1. CONNECT TO LAYER 2 SWITCH WITH NEW NETWORK CABLE ONLY IF NOT CONNECTED.
2. IN EXISTING # 6 PULL BOX, INSTALL NEW 45 — DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2, COIL 50' OF FIBER CABLE. NO. 6E PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART.
2o. FURNISH AND INSTALL # 6 PULL BOX, INSTALL. NEW 45 — DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART,
3. 7r.E.`:wx, FURNISH AND INSTALL 2-3" HDPE CONDUIT TO A DEPTH OF 30" USING DIRECTIONAL BORING FOR FIBER OPTIC CABLE. ALL CONDUIT BENDS SHALL BE FACTORY MADE. FURNISH AND INSTALL A NEW NO. 8 TWHN TRACER WIRE AND MULE TAPE,
4. FURNISH AND INSTALL A NEW TRUNK, ALL — DIELECTRIC, FULLY WATER — BLOCKED, LOOSE TUBE, GEL — FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 0122U4—T4F22.D20 OR APPROVED EQUAL CONTRACTOR SHALL COIL TRUNK 12 — STRAND QSMFO CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2. C2)5. FURNISH AND INSTALL A NEW BRANCH, ALL — DIELECTRIC, FULLY WATER — BLOCKED, LOOSE TUBE, GEL — FREE, 6 — STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4—T4F22D20 OR APPROVED EQUAL CONTRACTOR SHALL COIL 6 — STRAND SMFO CABLE
SLACK IN EVERY PULL BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
6. FURNISH AND INSTALL FIBER OPTIC SPLICE VAULT AND A NEW CORNING SCF-4C-18-01 OR // APPROVED EQUAL SPLICE ENCLOSURE PER DETAIL A & D ON SHEET 2 NEXT TO EACH LjCABINET. IT SHALL HAVE A MINIMUM 48 — FIBER SPLICE CAPABILITY. PROVIDE CABLE PORTS AS REQUIRED. HAVE A MOISTURE — TIGHT SEALING ARRANGEMENT AND HAVE RE—ENTRY --- CAPABILITY. TEST AND DOCUMENT CABLE AND ALL SPLICES.
7. PERFORM NECESSARY SPUCING OF THE TRUNK FIBER CABLE WITH THE 6 — STRAND FIBER CABLE PER DETAIL E ON SHEET 2 AND SPLICE DIAGRAMS AT THE FRONT OF THE PLAN SET. ALL REMAINING UNUSED FIBER STRANDS IN THE TRUNK CABLE MUST REMAIN INTACT AND IF CUT, MUST BE REJOINED BY SPLICING.
8. CONNECT TO EXISTING LAYER 3 ETHERNET SWITCH WITH 2 - DUAL FIBER/TRANSCEIVERPORTS IN THE TRAFFIC SIGNAL CONTROLLER CABINET. PROVIDE ALL. CABLES, CONNECTORS
AND AUXILIARY EQUIPMENT NECESSARY TO ESTABLISH COMMUNICATION TO ALL NETWORK CAPABLE DEVICES.
9. FURNISH AND INSTALL CORNING FIBER OPTIC DISTRIBUTION UNIT WITH 1U RACK MOUNT HOUSING, AND SPLICE CASSETTE. PROVIDE ALL JUMPERS, CAT 6 ETHERNET PATCH CABLE,DATA CABLES, AND ALL APPURTENANCES NECESSARY FOR COMMUNICATIONS PER DETAIL F ON SHEET 2 AND SPLICE DIAGRAMS. [ HOUSING - CORNING CCH-01U, PIGTAILED PATCH PANEL - CORNING CCH-CP12-AP-PD3RH, SPLICE TRAY - CORNING M67-048, SFP - DYMEC KY-SGSFP-LX10KMD, FIBER JUMPER - LC - LC PATCH CABLE, ANY BRAND, PREFERABLY 6 FT] , N Ej DEL
10. 2" INTERCONNECT CONDUIT INTO CABINET PER DETAIL " I" ON SHEET 2. PULL F.O. SIGNAL INTERCONNECT INTO CONTROLLER CABINET AND CONNECT AS DIRECTED BY THE ENGINEER.
MODIrir-CONTR011.EVSS`MS AS NeTer' IN .., r AL 4ROVIe'ON5:
11. LOCATE EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH EXTENSION) OVER THE CITY'S 1.25" CONDUIT. INSTALL NEW 45 — DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES SHALL BE SPACED NO MORE e
THAN 500 FEET APART: _ .. ADEN AL C+7T. _' CTIOo. NOTES ON EACH PAGE.
Ts.—FLP3`tii.SiH-rAkirD- i iiklSaTA — A—NEW-MCI-PULL BOX — PER DE.TAL A ON HE
13. REMOVE ALL RADIO EQUIPMENT & CABLING TO CITY YARD.
14. FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE. GEL - FREE, 24 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR APPROVED EQUAL CONTRACTOR SHALL COIL TRUNK 24 - STRAND
SMFO CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS, SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
15. FURNISH AND INSTALL FIBER OPTIC SPLICE VAULT AND A NEW CORNING SCF-4C-18-01 OR APPROVED EQUAL SPLICE ENCLOSURE PER DETAIL A & D ON SHEET 2 NEXT TO EACH CABINET. IT SHALL HAVE A MINIMUM 24 - FIBER SPLICE CAPABILITY'. PROVIDE CABLE PORTS AS REQUIRED. HAVE A MOISTURE - TIGHT SEALING ARRANGEMENT AND HAVE RE-ENTRY
CAPABILITY, TEST AND DOCUMENT CABLE AND ALL SPLICES,
16. FURNISH AND INSTALL CAT6 CABLE.
CB. INSTALL CONDUIT INTO EXISTING PULL BOX.
GENERAL NOTES
1. A CONSTRUCTION PERMIT IS REQUIRED FOR ALL CONTRACTORS PERFORMING ANY OF THE WORK SHOWN ON THIS PLAN. THE PERMIT CAN BE OBTAINED AT THE CITY OF VISTA DEVELOPMENT SERVICES CENTER, 600 EUCALYPTUS AVENUE, VISTA, CA. A PERMIT WILL BE ISSUED ONLY TO THE CONTRACTOR WHO IS TO PERFORM THE WORK. THE PERMITTEE SHALL GIVE NOTICE TO THE CITY
OF VISTA ENGINEERING INSPECTION DEPARTMENT FOR A PRECONSTRUCTION CONFERENCE AT LEAST 48 HOURS PRIOR TO COMMENCING THE WORK. ANY WORK DONE WITHOUT PROPER INSPECTION WILL BE SUBJECT TO REJECTION. PHONE: ( 760)639-6113 FOR INSPECTION.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE LOCATION AND PROTECTION OF ALL UTILITIES.
FOR LOCATION OF UNDERGROUND UTILITIES, OR FOR EMERGENCY ASSISTANCE CALL:
UNDERGROUND SERVICE ALERT
UNDERGROUND SERVICE ALERT
SAN DIEGO GAS & ELECTRIC
PACIFIC BELL TELEHPHONE CO.
VISTA IRRIGATION DISTRICT
COX CABLE
ADELPHIA COMMUNICATIONS
CITY OF VISTA
CITY OF VISTA
CITY OF VISTA AFTER HOURS EMERGENCY DISPATCH
FOR SEWER SPILLS OR STORM DRAIN
CONTAMINATION CALL NORTH COMM DISPATCH
SDG&E)
EMERGENCY)
EMERGENCY)
ENG. DEPT.)
EMERGENCY)
EMERGENCY)
MAIN NUMBER)
ENG. DEPT. DIRECT LINE)
EMERGENCY)
800) 422-4133
800) 227-
2600
800) 411-7343
DIAL) 611
760) 597-3116
760) 599-6063
760) 438-7741
760) 726-1340
760) 639-6111
858) 756-3006
3. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THESE PLANS, THE STANDARD SPECIFICATION FOR PUBLIC WORKS CONSTRUCTION. AND THE SAN DIEGO SPECIAL SUPPLEMENT TO THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION, AS LAST AMENDED.
4. THE STRUCTURAL SECTION OF THE STREETS SHALL BE DESIGNED BASED ON " R" VALUES OF SOILS AND ON A T.I. OF 6. MINIMUM SECTION SHALL BE 4" A.C. ON 8" CLASS 2 BASE. STRUCTURAL SECTIONS DESIGN SHALL BE APPROVED BY THE CITY ENGINEER ( PRIOR TO CONSTRUCTION. ALL DRIVEWAY APRONS, CURB & GUTTER, AND SIDEWALKS WITH AN ' R' VALUE LESS THAN 25 MUST HAVE A MINIMUM OF 6" D.G. OR EQUAL
5. " AS - BUILT" DRAWINGS) SHALL BE SUBMITTED BY THE ENGINEER OF WORK AND APPROVED BY THE CITY ENGINEER PRIOR TO THE ACCEPTANCE OF THE IMPROVEMENTS. SEPARATE " AS - BUILT" DRAWING(S) SHALL BE SUBMITTED FOR THE STREET LIGHTING SYSTEM.
6. STREET TREES IN NEW DEVELOPMENTS ARE TO BE PLANTED AT A MINIMUM OF EVERY FORTY FEET OR ONE ( 1) TREE PER LOT WHICHEVER IS GREATER,
7. PRIOR TO CONSTRUCTION OF STREET UGHTS, A PLAN [ ON 24"x36" SHEET(S)] APPROVED BY SAN
DIEGO GAS & ELECTRIC SHOWING EXACT PLACEMENT OF ALL STREET LIGHTS, PULL BOXES, SIZE
AND LOCATION OF CONDUITS AND SOURCES OF POWER SHALL BE SUBMITTED TO THE CITY
ENGINEER,
CIP NO. 8294
KEY MAP
0 VI
CINITY
NOT TO SCALE
VN s
UNDERGROUND SERVICE ALERT
SECTION 4216 & 4217 OF THE GOVERNMENT CODE
REQUIRES A DIG ALERT IDEN TTFICATTON NUMBER BE
ISSUED BEFORE A " PERMIT TO EXCAVATE" WILL BE
VALID. FOR YOUR DIG ALERT Li. NUMBER CALL
UNDERGROUND SERVICE ALERT AT 811 TWO ( 2)
WORKING DAY BEFORE YOU DIG
WEB ADDRESS: www. digolert. org or www.
coII811.com
CITY OF VISTA FIRE DEPARTMENT
APPROVED
VISTA IRRIGATION DISTRICT
THE APPROVAL GIVEN HERE IS FOR THE GRADING
LAYOUT AND IS bat FOR THE CONSTRUCTION OF
ANY PIJBUC WATER FACILITIES THAT MAY BE SHOWN
HEREON. NOR DOES IT IMPLY THAT WATER SERVICE
WILL BE PROVIDED.
DATE APPROVED
CITY OF VISTA SANITATION DEPARTMENT
BASIN:
RCE DATE APPROVED DATE
Plotted — 12/19/2023 9:15:30 AM :: Saved — 12/19/2023 9:15: 04 AM :: J: \ 2021\JC12039 Vista On — Call Fiber Optic \ Design\_CutSheet\TITLE SHEET.dwg :: aburgos
VICINITYVA'
NOT TO SCALE
KEY MAP
KEY MAP LEGEND
DESCRIPTION SYMBOL
SEET NUMBER
r-
NO. DESCRIPTION CITY DATE MD DATE
APPROVED CHANGES ENGINEER OF WORK
11 KEY MAP LEGEND
DESCRIPTION SYMBOL
SHEET NUMBER
U F
NITY MA
NOT TO SCALE
ENGINEER OF NRK
C52655 12/31 / 2024 12/19/23
LICE EXP.LIC.DATE DATE
I
STANDARDS
TRAFFIC SIGNAL DESIGN AND INSTALLATION IN THE CITY OF
VISTA SHALL CONFORM TO THE FOLLOWING:
1. CITY OF VISTA DEVELOPMENT CODE
2. CITY OF VISTA STANDARD DRAWINGS
3. THE LATEST EDITION OF CALTRANS STANDARD PLANS
4. THE LATEST EDITION OF CALTRANS STANDARD SPECIFICATIONS
5. THE LATEST EDITION OF CALTRANS STANDARD SPECIAL PROVISIONS
6. THE LATEST EDITION OF THE CALIFORNIA MANUAL ON UNIFORM TRAFFIC
CONTROL DEVICES ( CA MUTCD)
7. THE LATEST EDITION OF THE CALTRANS TRAFFIC MANUAL ( ONLY THE PARTS
THAT ARE STILL IN EFFECT)
8. THE LATEST EDITION OF THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION (* GREEN BOOK"), INCLUDING SUPPLEMENTS THERETO
9. THE LATEST EDITION OF THE SAN DIEGO REGIONAL STANDARD DRAWINGS.
10. PROJECT PLANS AND SPECIFICATIONS
THE ENGINEER OF WORK SHALL:
1 « BE A CIVIL ENGINEER ( NOT A TRAFFIC ENGINEER) WITH CURRENT CALIFORNIA
REGISTRATION AND SHALL SIGN AND SEAL THE FINAL PLANS,
2. MEET WITH THE CITY'S PROJECT ENGINEER TO REVIEW DESIGN CONCEPTS AND SHALL PREPARE A " REDLINED" CONCEPT DRAWING FOR DISCUSSION.
3. OBTAIN AN ELECTRICAL SERVICE POINT USING THE APPLICABLE PROCESS FOR THE SERVING UTILITY.
4. PRIOR TO BEGINNING DESIGN, SEND A MAP OF THE AREA WHERE THE
IMPROVEMENTS ARE PROPOSED TO ALL UTILITY COMPANIES ( SAN DIEGO GAS
ELECTRIC, AT&T, COX COMMUNICATIONS, TIME WARNER CABLE, VISTA
IRRIGATION DISTRICT, CITY OF VISTA, CITIES OF SAN MARCOS AND
OCEANSIDE AND THE COUNTY OF SAN DIEGO IF PROJECT IS NEAR THEIR
BOUNDARIES) SO THAT THE UTILITY COMPANIES CAN PROVIDE AS - GUILTS OF THEIR UTILITIES. NEXT, SEND TO THE UTILITY COMPANIES DRAFT DESIGN
PLANS SHOWING THE PROPOSED IMPROVEMENTS ALONG WITH THE UTIUTIES
PLOTTED FROM THE AS-BUILTS SO THAT THE UTILITY COMPANIES CAN
VERIFY THE LOCATION OF THEIR UTILITIES AND CHECK FOR CONFUCTS WITH THE PROPOSED IMPROVEMENTS. IF CONFLICTS ARE FORESEEN, UTILITY
COMPANIES AT THEIR DISCRETION, SHALL POTHOLE LOCATIONS OF POTENTIAL CONFLICTS PRIOR TO COMPLETION OF THE DESIGN PLANS. ANAL APPROVED
DESIGN PLANS MUST ALSO BE SENT TO THE UTILITY COMPANIES FOR FINAL
VERIFICATION OF UTILITY LOCATIONS AND CONFUCT CHECKS AND FOR USE IN UTILITY RELOCATION, IF NEEDED.
5. PERFORM AN AS - BUILT AND RECORD SEARCH TO DEPICT ON THE PLANS
ALL EXISTING UTILITIES ( WATER, SEWER, STORM DRAIN, TRAFFIC SIGNAL FIBER OPTIC. OTHER COMMUNICATIONS INFRASTRUCTURE, ETC.) WITHIN THE ENTIRE FOOTPRINT OF THE WORK AREA.
6. VERIFY THAT ALL EXISTING TRAFFIC SIGNAL EQUIPMENT AND ANY PROPOSED TRAFFIC IMPROVEMENTS CONFORM TO CURRENT STANDARDS. ADDITIONALLY,
THE ENGINEER OF WORK SHALL VERIFY THAT EXISTING EQUIPMENT CAN BE RE - USED, REPLACED, SALVAGED, AND/OR DISPOSED OF.
7. SUBMIT ELECTRONIC CAD AND PDF DRAWINGS REFLECTING AS - BUILT CHANGES AS SUBMITTED BY THE CONTRACTOR USING BUBBLES AND DELTAS.
THE ENGINEERING DEPARTMENT WILL PLOT THE AS - BUILT, OBTAIN SIGNATURES AND FILE THE AS-BUILTS IN THE CITY'S SYSTEM. NOTE THAT
THE ORIGINAL ELECTRONIC CAD FILE MUST BE SAVED SEPARATELY PRIOR TO MAKING ANY AS - BUILT CHANGES.
ENGINEER'S NOTE: THE ENGINEER PREPARING FOR, UNAUTHORIZED CHANGES & USES OF THESE PLANS. ALL CHANGES TO 7HE PLANS MUST BE OM WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
DECL A RA TI ON OF RESPONSIBLE CHARGE
1 HEREBY DECLARE THAT 1 AM THE ENGINEER OF NOR ( FOR THIS PROJECT, THAT I HAW
EXERCISEDRESPONSIBLE CHARGE OVER THE DESIGN OF THE PRO ECT AS DEFINED IN SECTION 5703 OF THE CALIFORNIA BUSINESS AND PROFESSIONS COD& AND THAT THE DEESGNIS
CCWSISTENTWITH CURRENT CITY OF VISTA STANDARDS I AGREE THAT THE WORKPERFORMED
BY ME COMPUES INTH GENERALLY ACCEPTED STANDARDS AND PRACTICES OF MY TRADE OR
PRC ESS L I FURTHER AGREE THAT THE WORK PERFORMED HEREIN IS IN ACCORDANCE INTN
THE RULES AND REG JLA TTCOWSREQUIRED BY THE CITY OF VISTA, I AGREE MAT PLAN CHECK
OR REWEW OF PROECT DRAWINGS AND SPECIFICATIONS BY THE CITY OF VISTA, IN ITS CAPACITYAS A PUBLIC ENTITY FOR THE PLANS PREPARED BY ME; IS CONFINED 70 A REVIEW
ONLY AND IS NOT A DETERMINATION BY THE CITY OF VISTA OF THE TECHNICAL SUFFICIENCY OR ADEQUACY OF THE PLANS OR DESIGN AND THEREFORE DOZESNOT RELIEVE« ME; AS
ENGINEEROF WORK, OF MY RESPONSIBILITIES FOR THE PLANS OR DESIGN OF IMPROVEMENTS BASED I AGREE 70 INDEMNIFY AND HOLD HARMLESS THE CITY OF VISTA, ITS ClFFICERS,, AGENTS; AND EMPLOYEES FROM PROPERTY DAMAGE OR BODILY INJJRY ARISING SOLELY FROM THE NEGLIGENT ACTS; ERRORS, OR OMISSIONS Cr THE ENC4NEEIRITS AGSM , OR ITS EMPLOYEES; ACTING WHIN THE COURSE AND SCOPE OF SUCH AGENCY AND EMPLOYMENT,
AND ARISING OUT OF THE WORK PERFORMED BY ME
ENGINEER OF WORK
offSlk,
WALTER OK!TSU C 52655 EXP DATE 12/31/2024
SHEET INDEX
TITLE SHEET - 1
DETAIL SHEET - 2
NETWORK DIAGRAM - 3-5
PLAN SHEETS - 6-19
RAP SHEETS - 20-21
KOA
PLANNING I ENGINEERING I
CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd. Suite 330
San Diego, California 92123
TeL ( 519) 683.3933 Fax: ( 619) 683-7982
STORM WATER
INSPECTION PRIORITY WDID
AS BUILT"
RCE EXP.
DATE
REVIEWED BY:
INSPECTOR DATE
CITY of VISTA
TRAFFIC SIGNAL PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DR, POINSETTIA AVE AND
N MELROSE DR
TITLE SHEET
APPROVED
CITY ENGINEER
70741 06 / 30 / 25 ,.. 7//0//,-
RCE EXPIRES DATE
BENCHMARK:
SHEET 1 OF 21
DWG - 4684
COMPLETENESS
LL
0 W
LU
LDS. 23-033 CIP NO. 8294
TRAFFIC SIGNAL PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DR, POINSETTIA AVE AND
N MELROSE DR
TITLE SHEET
APPROVED
CITY ENGINEER
70741 06 / 30 / 25 ,.. 7//0//,-
RCE EXPIRES DATE
BENCHMARK:
SHEET1 OF 21
DWG - 4684
COMPLETENESS
LL
0 W
LU
LDS. 23-033 CIP NO. 8294
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
197 of 244
LAST
SAVED
BY:
Optic\Design\_CutSheet\Detail
Sheet
to
On —
Call
PATH:
J: \
202
PLOT
DATE:
44"
3/4" LIFTING HOLES 1' DIA. PICK HOLES L
LLL
LLLLL
L_LLLL LLL
LLLLLLLLLLLLLL
LLLLL LLLLLLL
LL A LLLLL
1 - 1/2"x1 - 1/2"x1/4"
ANGLE ALL AROUND
12" MIN.
6" TOP INCL FRAME HEIGHT
W/RPM COVER 2'-O" X 3'-0"
8"X16"
KNOCKOUTS
2 EA. SIDE
3/4" HARDWARE CLOTH
BY CONTRACTOR
12" OF CLEAN
CRUSHED ROCK SUMP
NOTES:
1. TWO GROUNDING RODS SHALL BE
PROVIDED BY CONTRACTOR.
2. LIFTING RINGS AND BOLTS SHALL BE
PROVIDED.
3. PLATE. 5/16" SAFETY PLATE FOR TRAFFIC COVER.
4. ALL METAL SURFACES FOR SPECIAL FRAME
AND COVER SHALL HAVE A GALVANIZED FINISH.
5. ALL WELDING, MACHINE AND DRIWNG SHALL BE DONE BEFORE GALVANIZING.
6. PLUG THREADS MUST BE GREASED THOROUGHLY PRIOR TO INSTALLATION.
7. WHEN PROPOSED SPUCE/PULL BOX AND CONDUIT ARE WITHIN THE SIDEWALK, REPLACE ENTIRE SIDEWALK PANEL AS NEEDED TO ACCOMMODATE THE WORK. 12" MIN.
3/16" DIAMOND PLATE
PARKWAY COVER
21-0" X 3'-O"STAMP
SIGNAL COMMUNICATIONS'
U - SLOT IN PLATE & ANGLE
FOR BOLT DOWN TO FRAME
4 LIFTING INSERTS
2 EA. SIDE
CABLE BENDING RADIUS NOT TO EXCEED
MANUFACTURERS RECOMMENDATIONS
BUSHING
30` MIN
NEW CONDUIT
BEND
NOT TO SCALE
DETAIL A
12 15
FIBER OPTIC SPLICE BOX VAULT
CONDUIT
PULL BOX COVER
MIN.
CRUSHED ROCK
NOT TO SCALE
DETAIL B
6 PULLBOX WITH EXTENSION
2 11
9 -
NO. 6 PULL BOX WITH EXTENSION INSTALLATION
NOTES:
1. DIMENSIONS VARY ACCORDING TO SIZE OF CONDUIT ETC.,
WITH A MINIMUM BEND RADIUS OF SIX TIMES THE
CONDUIT DIAMETER FOR ALL CONDUITS.
2. ALL BENDS SHALL BE FACTORY BENDS.
3. CONTRACTOR SHALL ADAPT CONDUIT STUB OUTS FOR
SPECIFIC PROJECT REQUIREMENTS.
4. PROVIDE ONE FULL WRAP OF CABLE AT ALL PULL BOXES,
EXCEPT NO, 3 PULL BOXES.
5. WHEN PROPOSED SPUCE/PULL BOX AND CONDUIT ARE WITHIN THE SIDEWALK, REPLACE ENTIRE SIDEWALK PANEL AS NEEDED TO ACCOMMODATE THE WORK.
O O
FIBER PIGTAILS
CONDUIT
CONDUIT
FIBER OPTIC TRUNK CABLE
a
CONDUIT --\\
0 MAINTAIN 12" MIN. RADIUS
FOR FIBER CABLE ( TYP.)
4•,
NOT TO SCALE
COILED FIBBEROPTIC CABLE
CONDUIT
PULL BOX
DETAIL C
4 5
cr-
PULL BOX WITH NO SPUCE
14 BRANCH FIBER OPTIC CABLE
TO TRUNK FIBER
OPTIC CABLE IN " _
SPLICE ENCLOSURE
NOTE:
CONTRACTOR SHALL SPLICE ONLY BLUE OR ORANGE SUBCABLES. REMAINING SUBCABLES SHALL BE RETAINED IN PRISTINE CONDITION.
6 —FIBER, BREAKOUT CABLE
TO CABINET
PULL BOX OR SPLICE VAULT
SPLICE ENCLOSURE
FIBER OPTIC TRUNK CABLE
NOT TO SCALE
DETAIL D
CONDUIT
6 15
PULL BOX OR SPLICE
VAULT WITH SPLICE
ENCLOSURE.
SPLICE ENCLOSURE
EXISTING TRAFFIC SIGNAL
CONTROLLER CABINET
PATCH PANEL
FIBER DISTRIBUTION UNIT
ova
TRUNK CABLE
12 STRAND COUNT
PER PLAN.
A
LAN VIEW
DETAIL
10 BRANCH CABLE IN
CONDUIT, STRAND COUNT
PER PLAN.
1 NOT TO SCALE
DETAIL E
TRUNK CABLE
12 STRAND
or COUNT PER
PLAN.
7 TYPICAL SPUCE BETA EN FIBER
OPTIC TRUNK AND BRANCH
NOTE:
USE CAUTION WHEN DRILLING
TO AVOID COMPONENTS ON
INSIDE WALL OF CABINET
TE CON CT ENTRY TO CABI\ET
ENTER LEFT — REAR QUADRANT
OF CONTROLLER FOUNDATION
WITH INTERCONNECT CONDUIT
AS DIRECTED BY THE ENGINEER
PROPOSED 3" INTERCONNECT
CONDUIT WITH PULL ROPE AS
SPECIFIED ON PLANS. TYPICAL
PROPOSED NO. 6 PULL BOX
OR SPUCE COX-VAULT/N.
TRAFFIC SIGNAL
CONDUIT. TYPICAL
PLAN VIEW
EXISTING TYPE 332 CABINET
OT
DETAIL F
CONDUIT TO
BE ALIGNED
NOTE:
NO LOOPS SHALL BE PLACED
FOR NO. 6 PULL BOX
TYPICAL ETHERNET SWITCH INSTALLATION
COMMUNICATION
PULL BOX
12" RADIUS
MINIMUM)
NOT TO SCALE
DETAIL G
9 CONDUIT TO
BE ALIGNED
OUTLINE OF
CONTROLLER CABINET
PROPOSED NO.6 PULL
BOX OR SPUCE VAULT
CONTROLLER
FOUNDATION
CONTROLLER
PULL BOX
L-uHDPE
DETAIL H
KA
PLANNING I ENGINEERING I
CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California % 123
Tel ( 619) 683-2933 Fax: ( 619) 683-1982
TYPICAL MINIMUM BENDING RADIUS
GROUTUNE
45SWEEP ELL,
TYPICAL
CONTROLLER
1 FOUNDATION
EXISTING -\
SIDEWALK
STEEL
90^SWEEP ELL,
CONTROLLER ONLY
3"RIGID METAL CONDUIT
AND PULL ROPE
SECTION " A - A"
NO. DESCRIPTION
Revision
art
City
DAZE
3/6/25 DESNA
SCAM
DRAM
DAZE: _ 02/11/2021
APPROVED CHANGES
Oa, 044,, 05265512/31/2024 12/19/23
ENGINEER OF WORK RCE EXP.LIC.DATE DATE
CITY of VISTA
IMPROVEMENT PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
ADDRESS:
FOR CITY ENGINEER
BENCH MARK:
70A1,__ 6130/2'5
RCE EXPIRES ' DATE
LOlk23-033
SHEET_..OFFIL
DWG - 4684
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
198 of 244
fn
0 0
LAST
SAVED
BY:
PLOT
DATE:
TO FIRE STATION 1
EX
ETHERN
EMERALD DR & W. VISTA WAY
TRAFFIC SIGNAL CABINET
EXFDU
C
PROPOSED
JUMPERS
X X
PROPOSED 6 SMFOC
EX
ETHERN
1 GRAPEVINE ROAD & W. VISTA WAY
TRAFFIC SIGNAL CABINET
ET
EX FDU
SWITH
PROPOSED
JUMPERS
c1 * uiW
C )--- PROPOSED 6 SMFOC
r-
u
PROPOSED SPLICE BOX W/ SPLICE
ENCLOSUR5
PROPOSED SPUCE BOX W/ SPLICE ENCLOSURE
PROPOSED 12 SMFOC - PROPOSED 12 SMFOC
1 2-
3 4
5 6
7 8
9 10
11-
12 1-14: S. MELROSE DRIVE & W. VISTA WAY
TRAFFIC SIGNAL CABINET
EXISTING PULL BOX W/ SPUCE ENCLOSURE
NORTH WEST CORNER)
EXISTINGJUMPERS'
ctMwInmr W
x
x
EXISTING PULL BOX W/ SPUCE ENCLOSURE
PROPOSED 12 SMFOC
X X X X
G
a
VISTA BREAKOUT TO CABINET
1 9
2 10
3 11
KOA
PLANNING I ENGINEERING I
CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: ( 619} 683-2933 Far ( 8191 683-7982
LEGEND
Q -- EXISTING FIBER SPLICE
PROPOSED FIBER SPLICE
X - CUT END OF FIBER, NO SPLICE
EXISTING SIGNAL CARRYING FIBER
PROPOSED SIGNAL CARRYING FIBER
NO. DESCRIPTION CITY DATE SCALE
IDESKtt
IDRAM
DATE 02/11/2021
APPROVED CHANGES
0,4$„ C5265512/31/2024 12/19/23
ENGINEER OF WORK RCE EXP.LIC.DATE DATE
CITY of VISTA
IMPROVEMENT PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
ADDRESS:
APPROVED
C 70741 6/30/25 , j/./tJ:
FOR CITY ENGINEER RCE EXPIRES DATE
BENCH MARK:
SHEET _ OF..2L
DWG - 4684
D# 23-033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
199 of 244
LAST
SAVED
BY:
aburgos
2039
Vista
On —
Call
Fiber
Optic\Design\_CutShe
PLOT
DATE:
12/19/2023
EXISTING
PULL
BOX
W,/
PROPOSED
SPLICE
VAULT
EXISTING
PULL
BOX
W/
SPLICE
ENCLOSURE
2 C)
Nom , m m. 0:4 O1 CA Pa
LEGEND
Q - EXISTING FIBER SPLICE
PROPOSED FIBER SPLJCE
X — CUT END OF FIBER, NO SPLICE
EXISTING SIGNAL CARRYING FIBER
PROPOSED SIGNAL CARRYING FIBER
f
P1
mm
x
A.
NEW 12 — STRAND SPLICED TO
BREAKOUT CABLE TO BUSINESS
PARK DR & POINSETTIA
X _
N , rr„ p m o Ci tl1 W N j
1 2
3 4 _
m
m rn
MD X
2 3
4 6
7 8;
9 10
11 12
C
CI!
m
C en
rvrriz ri
I I•
13 z
m
EX
ETHERN
POINSETTIA AVE & ACTIVITY DR
TRAFFIC SIGNAL CABINET
SWITCH
WI WI
C _ PROPOSED
JUMPERS
Ex FDu
IM 41
EN OP
m
BLUE BUFFER TUBE
2 a
r
r7
co
rn
iiV
Y4OIVd
d1S
IA
3A
IdO
NelVd
PROPOSED6 SMFOC
EX
ETHERN
POINSETTIA AVE & LA MIRADA DRIVE
TRAFFIC SIGNAL CABINET
ET
EX FDU
SWITCH
PROPOSED
JUMPERS
040
OP OM
cv PE1w ul sa
PROPOSED PULL BOX W/ SPLICE ENCLOSURE
PROPOSED 12 SMFOC
PROPOSED 6 SMFOC
XX
PROPOSED PULL BOX W,% SPLICE ENCLOSURE
PROPOSED 12 SMFOC
KOA
PLANNING I ENGINEERING I
CONSTRUCTION MANAGEMENT
5095 MurphyCanyon Rd, Suite 330
San Diego, California 92123
Tel: ( 613) 683-2933 Fax x679) 683-7982
NO, OPTION DALE SCALE
DESIGN:
DRAM
aft
DAM 02"1 / 2021
APPROVED CHANGES
41,1 C4k, C5265512/31/2024 12/19/23
ENGINEER OF WORK RCE EXP.UC.DATE DATE
CiTY of VISTA
IMPROVEMENT PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
ADDRESS:
f, FOR CITY ENGINEER
70741 6/,30125 3//01
RCE EXPIRES DATE
BENCHMARK:
WO 23-033
SHEET4OF2L
DWG - 4684
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
200 of 244
E
0 L.
Optic\Design\_CutSheet\FO
a)
LL
to
On —
Call
JC12039
Vi
N
C7
N
H-
B_
roa
N
L
N
O CS)
LAST
SAVED
BY:
PLOT
DATE:
EX
ETHERNET
3-27:N. MELROSE DRIVE & COPPER DRIVE
TRAFFIC SIGNAL CABINET
a"
m
X X
1 2
3 4
5 6
7 8
9 10
11 12.
EX
ETHERNET
4-28: N. MELROSE DRIVE & OLIVE AVE TRAFFIC
SIGNAL CABINET
C _
axixi
rrnnp
XI
D
SWITCH
m
OP
LL
I-
v
LL
cc
PROPOSED 6 SMFOC
11 EX
ETHERNET
5-113: N. MELROSE DRIVE & W.LOS ANGELES
DR TRAFFIC SIGNAL CABINET
SWITCH
DEffiElp0
a
C _ POSED 6 SMFOC
mC cc
N
U-
F -
Q
CO
X X
rN
EX
ETHERNET
BLUE BUFFER TUBE
ORANGE BUFFER TUBE
1 2
3 4
5 6
7 8
9 10
11 12
6-64:N. MELROSE DRIVE & NORTH AVE
TRAFFIC SIGNAL CABINET
c-
a xi
rri o
v
SWITCH
MQDpDDD
C _
7C511- ILI-
Qccix 0
ix cr
Q=
cc
C\
411. 0111,
PROPOSED 6 SMFOC
x
EXISTING PULL BOX W/ SPLICE ENCLOSURE
EXISTING 24 SMFOC
LEGEND
Q - EXISTING FIBER SPLICE
PROPOSED FIBER SPLICE
X - CUT END OF FIBER, NO SPLICE
EXISTING SIGNAL CARRYING FIBER
PROPOSED SIGNAL CARRYING FIBER
U
PROPOSED 24 SMFOC
PROPOSED SPLICE BOX W/ SPUCE ENCLOSURE
PROPOSED 24 SMFOC
PROPOSED SPUCE BOX W/ SPLICE ENCLOSURE
PROPOSED 24 SMFOC
PROPOSED SPLICE BOX W/ SPUCE ENCLOSURE
KOA
PLANNING I ENGINEERING I
CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: ( 619) 683-2933 Fat ( 619} 583-7982
NO. DESCRIPTION OTY DATE SCALE
tenet
DRAM
CHECICIDk
DATES 02/111/21
APPROVED CHANGES
G 05265512/31 / 2024 12/19/23
ENGINEER OF WORK RCE EXP.UC.DATE DATE
L CITY of VISTA
IMPROVEMENT PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
ADDRESS:
APPROVED
FOR CITY ENGINEER
70741 6/30/25 . 3/i l
RCE EXPIRES DATE
BENCH MARK:
SHEET. , OF.iL
DWG - 4684
Wit 23-033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
201 of 244
0 0
LAST
SAVED
BY:
C
I*
a)
C>
C
a)
c
0. 0
s_
v
0 C
0 0
0)
0)
0 N
1 N
0 i
F --
PO
N
0 N
N
0 F-
0 J
Ii
Ch
N
co
it<
130 Cif)
it§
I
ri
IN
6 7 101/I\
b
0140
3 4 10 , i\
EMERALD DR
C 3,E
1 8 9 EX. CONTROLLER CABINET
5E TRAFFIC 3 4 r
3 4 1 6
r-- r _- ', y3
3 4 2q a
2-4---s\ S S EXISTING CONDUITz34---I _______.-- - ---------- - it,t 4'r— 1 I
I----
rte
11.__1.tix _TRAFFIC
R/W
z
1,;
8 9 EX. CONTROLLER CABINET
EXISTING CONDUIT EXISTING CONDUIT
Ts led5
3 \-
y 6 A
N—
6 TRAFFIC CB
2 1
1 \ MC1 VAULTI \\1
rig t2 MATCHLINE SEE SHEET 7
g lb
VINI
5 FURNISH AND INSTALL A NEW BRANCH, ALL -- DIELECTRIC, FULLY WATER — BLOCKED, LOOSE TUBE, GEL 6 SINGLE MODE FIBER OPTIC ( SMFO) CABLE, FURNISH AND INSTALL CORNING FIBER OPTIC DISTRIBUTION UNIT WITH 1U CONSTRUCTION NOTES:
FREE, — STRAND
CORNING 012ZU4-T4F22D20 OR APPROVED EQUAL. CONTRACTOR SHALL COIL 6 - STRAND SMFO CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS RACK MOUNT HOUSING, AND SPLICE CASSETTE. PROVIDE ALL JUMPERS, CAT 6
ETHERNET PATCH CABLE, DATA CABLES, AND ALL APPURTENANCES NECESSARY FOR COMMUNICATIONS PER DETAIL F ON SHEET 2 AND SPLICE
SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
DIAGRAMS. [ HOUSING - CORNING CCH-01U, PIGTAILED PATCH PANEL - CORNING CCH-CP12-AP-PD3RH, SPLICE TRAY - CORNING M67-048, SFP - CONNECT TO LAYER 2 SWITCH WITH NEW NETWORK CABLE ONLY IF NOT CONNECTED. DYMEC KY-SGSFP-LX10KMD, FIBER JUMPER - LC - LC PATCH CABLE, ANY 1 6 FURNISH AND INSTALL FIBER OPTIC SPLICE VAULT AND A NEW CORNING BRAND, PREFERABLY 6 FT] " H"SCF-4C-18-01 OR APPROVED EQUAL SPLICE ENCLOSURE PER DETAIL A & D ON AND DETAIL NY
I"SHEET 2 NEXT TO EACH CABINET. IT SHALL HAVE A MINIMUM 48 - FIBER SPLICE
A MOISTURE SEALING
10 2" INTERCONNECT CONDUIT INTO CABINET PER DETAIL ON SHEET 2. PULL 2 IN EXISTING ,{ 6 PULL BOX, INSTALL NEW 45 - DEGREE CONDUIT BENDS FOR FIBER CAPABILITY. PROVIDE CABLE PORTS AS REQUIRED. HAVE - TIGHT
DOCUMENT CABLE AND
F.O. SIGNAL INTERCONNECT INTO CONTROLLER CABINET AND CONNECT AS ARRALL
NGEMENT AND HAVE RE-ENTRY CAPABILITY. TEST AND
DIRREC-SPEMEDBY
ENGINEER. MODIFY CONTROLLER - ssEMBL - S-9 ° OTED : N-
LEGEND-
OPTIC CABLE PER DETAIL B ON SHEET 2, COIL 50' OF FIBER CABLE. NO. 6E PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART. YTHE Z 11 LOCATE EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH EXTENSION) OVER THE CITY'S 1.25" CONDUIT. INSTALL NEW 45 - DEGREE CONDUIT PROPOSED CONDUIT 2 FURNISH AND INSTALL # 6 PULL BOX, INSTALL NEW 45 - DEGREE CONDUIT BENTS FOR 7 PERFORM NECESSARY SPLICING OF THE TRUNK FIBER CABLE WITH THE 6 - STRAND FIBER CABLE PER DETAIL E ON SHEET 2 AND SPLICE DIAGRAMS AT THE FRONT OF BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART. THE PLAN SET. ALL REMAINING UNUSED FIBER STRANDS IN THE TRUNK CABLE MUST SHALL BE SPACED NO MORE THAN 500 FEET APART. 40' 2a' o o° 40' REMAIN INTACT AND IF CUT, MUST BE REJOINED BY SPLICING. 1" 40' GRAPHIC SCALE I=
PROPOSED PULLBOX CB INSTALL CONDUIT INTO EXISTING PULL BOX.
TRENCH; FURNISH AND INSTALL 2-3" HDPE CONDUIT TO A DEPTH OF 30" USING CONNECT TO EXISTING LAYER 3 ETHERNET SWITCH WITH 2 - DUAL FIBER TRANSCEIVER3 BDIRECTIONAL BORING FOR FIBER OPTIC CABLE. ALL CONDUIT BENDS SHALL BE PORTS IN THE TRAFFIC SIGNAL CONTROLLER CABINET. PROVIDE ALL CABLES, a
EXISTING PULLBOX FACTORY MADE. FURNISH AND INSTALL A NEW NO. 8 TWHN TRACER WIRE AND MULE CONNECTORS AND AUXILIARY EQUIPMENT NECESSARY TO ESTABLISH COMMUNICATION TAPE. TO ALL NETWORK CAPABLE DEVICES.
KONA
f f
J f
III JJJ - V 111 IA
PLANNING I ENGINEtRING 1EXISTING CONTROLLER CABINET FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE, CONSTRUCTION MANAGEMENT IMPROVEMENT PLANS FOR:4 GEL - FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR NOT: TO CONTRACTOR: IF # 6 PULL BOX NEXT TO CABINET DOES NOT HAVE ROOM SO95Murphy Canyon Rif, SU,re330 APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 12 - STRAND SMFO CABLE SLACK IN EVERY PULL FOR SWEEP ON THE OUTSIDE OF CABINET, INSTALL NEW # 6 PULL BOX. San( 19)69 - 233 a2123
Tel: ( G59j G$3-2933 Far. ( 6191(M - 79n TRAFFIC SIGNAL INTERCONNECT
EXISTING CONDUIT BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE BENDING RADIUS AND DETAIL C ON SHEET 2. NCI. DESCRIPTION c1TY DATE SCALE:
Revision City 3/6/25 DESIGN:
QRpFESslr,y
C.
J a/t-
C
ADDRESS:
TRAFFIC SIGNAL CONTROLLED DRAWN:
L, Gz
APPRrJ
t
Q
INTERSECTION m
f
L . r t 70741 6'/30/25 . 3 t -
SHEET OF 21CC,HECKE[3: „
FQRLCITY
re
No. 052655 6
ENGINEER RCE EXPIRES DATE
DATE: 02/11/2021
Oa.- BENCH MARK:
O5265512/31/2O24 12/19/23
0->.
c1Vll- ` P
or 4 DWG - 4684
ENGINEER OF WORK RCE EXP.LIC.DATE DATE CA0
APPROVED CHANGES
LD#- 23—033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
202 of 244
cei
0 cn
I-
0)
a)
0 C
as
6 ay
O
CL
0 0
L=
0 0
0 0
N
CTJ
r
i
T
I-
0 O
Is
O
LAST
SAVED
BY:
2" MCI CONDUIT
EX, 1.25" CITY CONDUIT 4
tin
5E TRAFFIC K
y
EX. 1.25" CITY CONDUIT 4
1-
0 I
EX. 1.25" CITY CONDUIT 4
f -
n
LU
I``- -
2" MCI CONDUIT
z
I1I
5E TRAFFIC ' Y VISTA WAY
MCI
C
Tl
P
41 - r
LiJ - 2
K-RAIL ITFI
f
ili
41 III
4 EX. 4" CITY CONDUIT
ZL '.. 7 5 4I'Pf E:
CD 4 EX. 1.25" CITY CONDUIT
2„ MCI CONDUIT 6
1611 6 TRAFFIC EX. 3" CITY CONDUIT 4 2 7 EX. CONTROLLER CABINET1 8 9 13 10 5E TRAFFIC IiV VISTA
11 6 TRAFFIC
1,WAY 11 6 4 EX. 1.25" CITY CONDUIT I
1i 6
Q. - rCB 2" MCI CONDUIT
Z
PI
EX. 3" CITY CONDUIT 4 CB 11 6
PI
m1-u 3 4
TRENCH MCI
0 I)
1 FT1
EOP
CO
PERFORM
FIBER
NECESSARY SPLICING OF THE TRUNK FIBER CABLE WITH THE 6 - STRAND CABLE PER DETAIL E ON SHEET 2 AND SPLICE DIAGRAMS AT THE FRONT OF CONSTRUCTION NOTES:
THE
REMAIN
PLAN SET. ALL REMAINING UNUSED FIBER STRANDS IN THE TRUNK CABLE MUST INTACT AND IF CUT, MUST BE REJOINED BY SPLICING.
1 CONNECT TO LAYER 2 SWITCH WITH NEW NETWORK CABLE ONLY IF NOT CONNECTED. 8 CONNECT PORTS
TO EXISTING LAYER 3 ETHERNET SWITCH WITH 2 - DUAL FIBER/TRANSCEIVER IN THE TRAFFIC ' SIGNAL CONTROLLER CABINET. PROVIDE ALL CABLES,
CONNECTORS
TO
AND AUXILIARY EQUIPMENT NECESSARY TO ESTABLISH COMMUNICATION ALL NETWORK CAPABLE DEVICES.
2 IN EXISTING # 6 FULL BOX, INSTALL NEW 45 - DEGREE CONDUIT BENDS FOR FIBER CABLE PER DETAIL B ON SHEET 2, COIL 50' OF FIBER CABLE. NO. 6E PULL FURNISH AND INSTALL CORNING FIBER OPTIC DISTRIBUTION UNIT WITH 1 U RACKOPTIC 9 MOUNT HOUSING, AND SPLICE CASSETTE. PROVIDE ALL JUMPERS, CAT 6 ETHERNETBOXES SHALL BE SPACED NO MORE THAN 500 FEET APART.
PATCH
COMMUNICATIONS
CABLE, DATA CABLES, AND ALL APPURTENANCES NECESSARY FOR PER DETAIL F ON SHEET 2 AND SPLICE DIAGRAMS. [ HOUSING - 3 TRENCH FURNISH AND INSTALL 2-3" HOPE CONDUIT TO A DEPTH OF 30" USING DIRECTIONAL BORING FOR FIBER OPTIC CABLE. ALL CONDUIT BENDS SHALL BE FACTORY
CORNING
SPLICE
CCH-01 U, PIGTAILED PATCH PANEL - CORNING CCH-CP12-AP-PD3RH, TRAY - CORNING M67-048, SFP - DYMEC KY-SGSFP-LXIOKMD, FIBER MADE. FURNISH AND INSTALL A NEW NO. 8 TWHN TRACER WIRE AND MULE TAPE. JUMPER LC - LC PATCH CABLE, ANY BRAND, PREFERABLY 6 FT] H"
LEGEND:
AND ( DETAIL
I"
13 REMOVE ALL RADIO EQUIPMENT & CABLING TO CITY YARD.
10 2" INTERCONNECT CONDUIT INTO CABINET PER DETAIL ON SHEET 2. PULL F.O.
FURNISH AND INSTALL TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE SIGNAL INTERCONNECT INTO CONTROLLER CABINET AND CONNECT AS DIRECTED BY4 tni -
PROPOSED CONDUIT
NEW
GEL—FREE,TUBE, GEL FREE 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING THE V e._AlllTIfi ,,. e_flA1-C®Ill I C r vvirr vw r r.v „_,,,,` r r%"'r'vfv v.ENGINEER. Ik.IODIr Y C.,,..ROLLER A ED-,,.-S°FC-`1-i°ROVISIONS CB0i2ZU4—T4F22D20 OR APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 12 — STRAND INSTALL CONDUIT INTO EXISTING PULL BOX. 40' ,. 0 2o' , 0' SMFO CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER LOCATE EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2. 11 NEW 45 CONDUIT 1."=40' GRAPHIC sG'uz
o
PROPOSED PULLBOX
CABLE MANUFACTURER'S EXTENSION)
BENDS
OVER THE CITY'S 1.25" CONDUIT, INSTALL - DEGREE
FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES 5 FURNISH AND INSTALL A NEW BRANCH, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE SHALL BE SPACED NO MORE THAN 500 FEET APART. EXIS T 1NG PULL BOXES TUBE, GEL 6 SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNINGFREE, - STRAND PULLBOX Oi2ZU4-T4F22D20 0R APPROVED EQUAL. CONTRACTOR SHALL COIL 6 - STRAND SMFO
CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE vV6LL BE REMOVED, DISPOSED, AND REPLACED WITH A NO.6 PULL BOX WITH EXTENSION PER THIS CONSTRUCTION NOTE.
KomCEXISTING f
MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
EXISTING CONTROLLER CABINET NOTE TO CONTRACTOR: IF # 6 PULL BOX NEXT TO CABINET DOES NOT HAVE ROOM
PLANNING I ENGINEERING
CONSTRUCTLON MANAGEMENT IMPROVEMENT PLANS FOR:
FOR SWEEP ON THE OUTSIDE OF CABINET, INSTALL NEW # 6 PULL BOX. 5095 Murphy Canyon FCd.Suite 330 San(619)63-2933'rFa6
TM ( 619}683-2933 Fa X; ( 619}663-7982
2123
FURNISH AND INSTALL FIBER OPTIC SPLICE VAULT AND A NEW CORNING S:CF-4C-18---O1 aFax TRAFFIC SIGNAL INTERCONNECT EXISTING CONDUIT OR APPROVED EQUAL SPLICE ENCLOSURE PER DETAIL A & D ON SHEET 2 NEXT TO EACH CABINET. IT SHALL HAVE A MINIMUM 48 - FIBER SPLICE CAPABILITY. PROVIDE NO. DESCRIPTION CITY DATE SCALE:
cofESS/C4,4
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
CABLE PORTS AS REQUIRED. HAVE A MOISTURE — TIGHT SEALING ARRANGEMENT AND HAVE RE—ENTRY CAPABILITY. TEST AND DOCUMENT CABLE AND ALL SPLICES, Revision City I3I6125DESIGN: r{`'l tc - 04-f <" ADDRESS:
41)
TRAFFIC SIGNAL CONTROLLED DRAWN: cnGz APPROVED
INTERSECTION
1 r 4 , ae. 70741 6/30/25,3/'./ SHEET 7 OF 21CHECKED: OFDR CITY ENGINEER RCE EXPIRES DATE f
D2/11 / 2021 LDATE: r
Tq
BENCH MARK:
t,L C5265512/31/2024 12/19/23 CIV1L 1-
OF CAL\Fa DWG - 4684
ENGINEER OF WORK RCE EXP.LIC.DATE DATEAPPROVED CHANGES
LD#. 23-033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
203 of 244
LAST
SAVED
BY:
aburgos
O)
Fri
I
cn
H-
0 a)
t
f-
p°3
C
0 a)
0 O
O
O
as
LL
O
1 O
O
cn
0 N
0 N
0 N
H -
N
0 N
03 N
6.3 I-
0 I-
0 J
rl
o
4 EX. 1.25" CITY CONDUIT 11 TRAFFIC
4 EX. 1.25" CITY CONDUIT
6 2" MCI CONDUIT ( ry MCI
Y VISTA WA
MCI CONDUIT
i
1 2»
5E TRAFFIC --
co
I 1
m
f)
m
m
O
m2
m EOP
sse
21 I
sp4EX. 1.25" CITY CONDUIT
11 6 TRAFFIC
K
r W VISTA WA / 4 2" MCI CONDUIT
4 EX. 1.25" CITY CONDUIT
5E TRAFFIC 2
2 MCI CONDUIT -- - - - -- - -m 21
m
MCI --
EOP -- -
I)
m
U7
0 2
LEGEND:
2 ciD
PROPOSED CONDUIT CONSTRUCTION NOTES:
40' 20' 0 20' 40'
1"-4Q' GRAPHIC SCALE
o
PROPOSED PULLBOX
FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE,4 GEL - FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR y/ o 1
EXISTING PULLBOX
APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 12 - STRAND SMFO CABLE SLACK IN EVERY PULL KoA n i if IA
BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM A BENDING RADIUS AND DETAIL C ON SHEET 2. PLANNING I ENGINEERING IEXISTING CONTROLLER CABINET CONSTRUCTION MANAGEMENT IMPROVEMENT PLANS FOR:
11 LOCATE EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH SD95 MurphyCanyon Rd, Suite 33D San Diego, Calrrornia 523
EXTENSION) OVER THE CITY'S 1.25" CONDUIT. INSTALL NEW 45 - DEGREE CONDUIT Tel :( 619)663-2933FaFac(51 ) 6g3-7982 BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES
TRAFFIC SIGNAL INTERCONNECT
EXISTING CONDUIT EMERALD DRIVE, POINSETTIA AVENUE AND N MELR0SE DRIVESHALL BE SPACED NO MORE THAN 500 FEET APART. EXISTING PULL BOXES WILL BE REMOVED, NO. DESCRIPTION CITY DATE SCALE: af'ESSlp ED, AND REPLACED WITH A NO.6 PULL BOX WITH EXTENSION PER THIS CONSTRUCTION NOTE.
Revision City 13/6125 1D€sicrr:
y,
y
ADDRESS:
S TRAFFIC SIGNAL CONTROLLED NOTE TO IF PULL BOX NEXT TO CABINET DOES NOT HAVE ROOM IDRAWN: ei' c
APPROVED
CONTRACTOR: # 6
INTERSECTION FOR SWEEP ON THE OUTSIDE OF CABINET, INSTALL NEW # 6 PULL BOX. 1CHECKED: No. C52655 SHEETITCITY ENGINEER RCE EXPIRES DATEmrFC}R DATE: 42/11/2021
ofAK,
A- BENCH MARK:CidititK• C5265512/31/2024 12/19/23 s,4 CIy11.
OFCA- DWG - 4684
ENGINEER OF WORK RCE EXP.LIC.DATE DATEAPPROVED CHANGES
LD# 23-033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
204 of 244
LAST
SAVED
BY:
Optic\Design\_CutSheet\TS—04.dwg
PLOT
DATE:
12/19/2023
PATH:
J: \
2021 \
JC12039
Vista
On —
Call
Fibe
3>
C7
r -
z
rn
w
1 rn
in
CO
LEGEND:
PROPOSED CONDUIT
PROPOSED PULLBOX
EXISTING PULLBOX
EXISTING CONTROLLER CABINET
EXISTING CONDUIT
TRAFFIC SIGNAL CONTROLLED
INTERSECTION
EX. 1.25" CITY CONDUIT
4 6 I NAFFIC
2" MCI CONDUIT
b'1
ValVSYVS
VINVS
EX. 1.25" CITY CONDUIT
2" MCI CONDUIT
CONSTRUCTION NOTES:
A' 1
W VISTA WAY
WVISTAWAY
5E TRAFFIC
2" MCI CONDUIT
MCI
EOP
FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE, GEL - FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 12 - STRAND SMFO CABLE SLACK IN EVERY PULL
BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
LOCATE EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH EXTENSION) OVER THE CITY'S 1.25" CONDUIT. INSTALL NEW 45 — DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART.
EXISTING PULL BOXES WILL BE REMOVED, DISPOSED, AND REPLACED WITH A NO. 6 PULL BOX WITI-I EXTENSION PER THIS CONSTRUCTION NOTE.
DETAIL A ON SHEET 2:
NOTE TO CONTRACTOR: W # 6 PULL BOX NEXT TO CABINET DOES NOT HAVE ROOM FOR SWEEP ON THE OUTSIDE OF CABINET, INSTALL NEW # 6 PULL BOX, EOP
6 TRAFFICMCI
EX. 1.25" CITY CONDUIT
2" MCI CONDUIT
EX. 1.25" CITY CONDUIT
3NflHOIN
N
3NflHJIVIN
KOA
PLANNING I ENGINEERING]
CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 380
San Diego, California 92123
Tel: ( 619) 683-2933 Fax ( 619) 6$3-7982
40' 20'
1"-40'
o 20' 40'
GRAPHIC SCALE
DESCRIPTION CITY DATE SCALE:
Revision Cites 3/6/25 DESIGN:
DRAWN:
CHECKED:
DATE: 02/11/2021
APPROVED CHANGES
G 05265512/31/2024 12/19/23
ENGINEER OF WORK RCE EXP.LIC.DATE DATE
C//Y of VISTA
IMPROVEMENT PLANS FOR:
TRAFFIC SIGNAL INTERCONNECT
EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE
ADDRESS:
APPROVED
Q /
FOR CITY ENGINEER
BENCH MARK:
s . 70741 6/30/25,31/01Z
RCE EXPIRES DATE
SHEET 9 OF 21
DWG - 4684
LD• 23—033
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
205 of 244
LAST
SAVED
BY:
LU
I --
d
0 I-
0 CI
SI
37 Lrl
4 EX. 1.25" CITY CONDUIT ] 3 K
5- 11 5 TRAFFIC rS4 EX. 1.25" CITY CONDUIT
12" MCI CONDUIT
ill WVISTA WAY. 11 6E TRAFFIC „ r-MCI CONDUIT _
n
2 -_— __ _.----
e -
ill m
i MCI
ill
M
r
EOP
m
7 I—
M
q
4 D
11 6 TRAFFIC 4 EX. 1.25" CITY CONDUIT
Z VISTAA WAY 2" MCI CONDUITYM
I 4 EX. 1.25" CITY CONDUIT y.
5E TRAFFIC
O
a
2" MCI CONDUITM i
C
1 - : --
Z
P1
XI
X
MCI P1
M
m
I
LEGEND:
EOP
nil
1 CONSTRUCTION NOTES:
PROPOSED CONDUIT
40' 20' 0 20' 40'
FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE,4 GEL - FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING O1,2ZU4-T4F22D20 OR i"=40' GRAPHIC scar
o
PROPOSED PULLBOX APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 1.2 - STRAND SMFO CABLE SLACK IN EVERY PULL
BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM
EXISTING PULLBOX A
BENDING RADIUS AND DETAIL C ON SHEET 2.
C/ /EXISTING CONDUIT, FURNISH AND INSTALL A NO. 6 PULL BOX ( WITH EXTENSION) OVER THE KOA
oVISILOCATE
CITY'S 1.25" CONDUIT. INSTALL NEW 45 - DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2. NO. 6 PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART.
PLANNING I ENGINEERING I
EXISTING CONTROLLER CABINET CONSTRUCTION MANAGEMENT IMPROVEMENT PLANS FOR:.
EXISTING PULL BOXES WILL BE REMOVED, DISPOSED, AND REPLACED WITH A NO. 6 PULL BOX WITH 5095 MurphyCanyon Rd, Suite 330 EXTENSION PER THIS CONSTRUCTION NOTE.
San Diego, California
92123Tel:(619) 83-2933 Fax: ( 619)683-7982 TRAFFIC SIGNAL INTERCONNECT EXISTING CONDUIT NOTE TO CONTRACTOR: IF # 6 PULL BOX NEXT TO CABINET DOES NOT HAVE ROOM EMERALD DRIVE, POINSETTIA AVENUE AND N MELROSE DRIVE FOR SWEEP ON THE OUTSIDE OF CABINET, INSTALL NEW # 6 PULL BOX. NO. DESCRIPTION CITY DATE SCALE: pcESS1(}4 4 9`J.
Q Revision 1 City 3/6/25 IDESIGN: dr ` ADDRESS:
el
TRAFFIC SIGNAL CONTROLLED DDRAWN:
44,cy
G S APPROVED
INTERSECTION m srk
P
70741 6J3Li/25c3f o 7. --
CCHECKED: as
No. C5 SHEET 10 OF 2
i FOR CITY ENGINEER RCE EXPIRES DATE
02/11/2021DATE: BENCH MARK:
C5265512/31 / 2024 12/19/23 5
I.
OM
0 arCM. DWG - 4684
ENGINEER OF WORK RCE EXP.L1C.DATE DATEAPPROVED CHANGES
LD#: 23--03.3
Docusign Envelope ID: 435BC255-2852-404A-B659-95B947933360 06/24/2025
C12
206 of 244
0 0
ID
LAST
SAVED
BY:
Optic`+,,Design\_CutSheet\TS—Q6.
dwg
1)
2021\JC12039
Vista
On —
Call
PLOT
DATE:
2" MCI CONDUIT
5E TRAFFIC
LEGEND:
PROPOSED CONDUIT
PROPOSED PULLBOX
EXISTING PULLBOX
EXISTING CONTROLLER CABINET
EXISTING CONDUIT
TRAFFIC SIGNAL CONTROLLED
INTERSECTION
4 EX. 1.25" CITY CONDUIT
4 EX. 1.25" CITY CONDUIT
EX. CONTROLLER CABINET
2" MCI CONDUIT
W VISTA WAY
1 2
2" MCI CONDUIT
EOP
6 9 8 1
CB
10 5
111#6 TRAFFIC
EXISTING CURB
CONSTRUCTION NOTES:
110
35106'73141N
6 TRAFFIC
3 4
2" MCI CONDUIT
f
MCI
CONNECT TO LAYER 2 SWITCH WITH NEW NETWORK CABLE ONLY IF NOT CONNECTED.
IN EXISTING # 6 PULL BOX, INSTALL NEW 45 - DEGREE CONDUIT BENDS FOR FIBER OPTIC CABLE PER DETAIL B ON SHEET 2, COIL 50' OF FIBER CABLE. NO. 6E PULL BOXES SHALL BE SPACED NO MORE THAN 500 FEET APART.
3 ITRENCH,
T
FURNISH AND INSTALL 2-3" HDPE CONDUIT TO A DEPTH OF 30" USING DIRECTIONAL BORING FOR FIBER OPTIC CABLE. ALL CONDUIT BENIDS SHALL BE FACTORY MADE. FURNISH AND INSTALL A NEW NO. 8 TWHN TRACER WIRE AND MULE TAPE.
4 5
L
L_!
MCI
6 TRAFFIC
A /
5E TRAFFIC
W VISTA WAY
FURNISH AND INSTALL A NEW TRUNK, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE, GEL - FREE, 12 STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR APPROVED EQUAL. CONTRACTOR SHALL COIL TRUNK 12 - STRAND SMFO CABLE SLACK IN EVERY PULL
BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
FURNISH AND INSTALL A NEW BRANCH, ALL - DIELECTRIC, FULLY WATER - BLOCKED, LOOSE TUBE, GEL - FREE, 6 - STRAND SINGLE MODE FIBER OPTIC ( SMFO) CABLE, CORNING 012ZU4-T4F22D20 OR APPROVED EQUAL. CONTRACTOR SHALL COIL 6 - STRAND SMFO
CABLE SLACK IN EVERY PULL BOX OR VAULT WHICH HAS SUFFICIENT SPACE PER CABLE MANUFACTURER'S ALLOWABLE MINIMUM BENDING RADIUS AND DETAIL C ON SHEET 2.
FURNISH AND INSTALL FIBER OPTIC SPLICE VAULT AND A NEW CORNING SCF-4C-18-01 OR APPROVED EQUAL SPLICE ENCLOSURE PER DETAIL A at D ON SHEET 2 NEXT TO EACH CABINET. IT SHALL HAVE A MINIMUM 48 — FIBER SPLICE CAPABILITY. PROVIDE CABLE PORTS AS REQUIRED. HAVE A MOISTURE - TIGHT SEALING ARRANGEMENT AND HAVE RE-ENTRY CAPABILITY. TEST AND DOCUMENT CABLE AND ALL SPLICES.
7 8
9 10
2" MCI CONDUIT