ACTION:
____________________________
Clerk/Secretary
Department: Engineering Item No: C4
Prepared by:

Erin Adams, Administrative Programs Manager
Daniel Carns, Capital Projects Manager Meeting Date: February 24, 2026 Approved by:

Greg Mayer, Department Director
John Conley, City Manager Agenda Location: Consent Calendar SUBJ
ECT: CIP 8902 – CITY-WIDE ELECTRIC VEHICLE CHARGING STATIONS PROJECT – SDG&E

POWER YOUR DRIVE PARTICIPATION AGREEMENTS
RECO
MMENDATION:

1. Adopt City Council Resolution No. 2026- , approving the SDG&E Power Your Drive for Fleets Make - Ready Infrastructure Program Participation Agreements and Addendums.

2. Adopt City Council Resolution No. 2026- , amending the Capital project Budget for Fiscal Years 2024/25 and 2025/26.

CORRE
LATION TO CITY COUNCIL GOALS: Fiscal Responsibility and Climate and Environmental Responsibility
PR
IOR CITY COUNCIL ACTION: O n June 11, 2024, adopted City Council Resolution No. 2024- 86, adopting a Capital Project Budget for Fiscal Years 2024/25 and 2025/26 (Vote: 5-0).

On
December 10th, 2024, adopted City Council Resolution No. 2024196, approving the first amendment to the agreement with PAR Western Line Contractors, LLC for design/build services for the City-Wide Electric Vehicle Charging Stations Project (CIP No. 8902) (Vote: 5-0).

On
February 22, 2025, adopted City Council Resolution No. 2025- 22, approving a contract with Blink Network LLC for electric vehicle equipment for the City-Wide Electric Vehicle Charging Stations Project (CIP No. 8902) (Vote: 5-0)
ST
ATEMENT ON THE SUBJECT: Capital Improvement Program (CIP) Project No. 8902, City-Wide Electric Vehicle Charging Stations Project, will design , upgrade electrical services, construct ADA parking and access improvements, and install electric vehicle (EV) charging stations at 10 City-owned properties. The 10 sites are located at the Civic Center, Public Works, Sports Park, Luz Duran Park, Brengle Terrace Park, Breeze Hill Park, Shadowridge Park, Wave Water Park, Downtown Parking Lot, and Fire Station No. 6. A total of 99 EV charging stalls consisting of Level 2 and Level 3 chargers for fleet and public use are proposed at the sites shown above. The EV charging units are proposed to be supplied to the contractor from the City as owner-supplied equipment.

In D
ecember 2024, the City applied for San Diego Gas and Electric’s rebate program “Power Your Drive for Fleets Make-Ready Infrastructure Program at the Public Works Yard and Civic Center sites. The goal of AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
Approved above recommendation, adopted the following: 1) City Council Resolution No. 2026-27.

Vote: 4-0 (O'Donnell absent); 2) City Council Resolution No. 2026-28. Vote: 4-0 (O'Donnell absent)