Department: Public Works Item No: D1
Prepared by: Chris Arce, Director Meeting Date: April 28, 2026 Approved by:
Imelda Huerta, Assistant City Manager
John Conley, City Manager Agenda Location: Discussion
SUBJECT: CITYWIDE FACILITIES MASTER PROGRAM - UPDATE
RECOMMENDATION: Discuss the status of City facilities and provide direction to staff.
CORRELATION TO CITY COUNCIL GOALS: Routine operational item not directly corresponding to a specific City Council goal.
PRIOR ACTION: On April 22, 2025, a Citywide Facilities Master Program update was provided to City Council. City Council discussed and stated support for the Facilities Master Program list and provided direction for staff. (Vote: No Vote)
On March 12, 2024, the Citywide Facilities Master Program was introduced to City Council. City Council discussed and stated support for the Facilities Master Program list and provided direction for staff. (Vote:
No Vote)
STATEMENT ON THE SUBJECT: In March of 2024, staff presented the Citywide Facilities Master Program to assess the condition of City-owned facilities, identify operational needs and prioritize projects to ensure that City facilities are maintained to an acceptable level of service. Under the program, staff assess facility conditions to identify necessary repairs and upgrades, evaluate current and future needs and develop project cost projections. A comprehensive project list has been established which is regularly reviewed and revised as conditions evolve and needs are identified.
Staff have prepared a project status update for Fiscal Year 2025/26, and a current list of projects recommended for completion in Fiscal Year 2026/27. The total projected cost for proposed repairs and upgrades in Fiscal Year 2026/27 is $3,678,000. A detailed breakdown of projects and associated costs is provided in Exhibit 1.
Staff recommend utilizing Prop L and Redevelopment Fund Reserves to fund the proposed FY 2026/27 projects and will return to City Council to allocate funds in future fiscal periods.
FISCAL IMPACT: There is no direct fiscal impact associated with the staff recommendation. Any fiscal impacts will be evaluated and implemented after receiving direction from the City Council and will be included in the FY2026/27 Operating Budget.
EXHIBITS:
1.Project List Fiscal Year 2026/27
AGENDA
REPORT
CITY COUNCIL
COMMUNITY DEVELOPMENT COMMISSION
SUCCESSOR AGENCY
BUENA SANITATION DISTRICT
JOINT POWERS FINANCING AUTHORITY
Discussed the status of City Facilities and approved the proposed list of projects. Vote: 5-0
Number FY Site Item Description Estimate
1 27 Vista Sports Park, Brengle
Terrace Park, Thibodo Park
LED lights Upgrade lights to LED lights at five sites: Vista Sports Park Ballfields, Brengle Terrace Park and Thibodo Park Tennis Courts, Pickleball Courts, and Basketball Courts.
$700,000
2 27 Thibodo Park, Breeze Hill Park,
Raintree Park, Wildwood Park,
Buena Vista Park and Ballfields
Park signs Upgrade park entrance signs. $45,000
3 27 Adobe Electrical panels Replace exterior electrical panels in trash enclosure. Map circuits in electrical panels and label panels and outlets for all buildings.
$100,000
4 27 Adobe Renovation Exterior upgrades and renovation. $300,000 5 27 AVO Playhouse Fire alarm Replace fire alarm. $125,000 6 27 Brengle Terrace Park Fence Replace fencing around the softball field.$200,000 7 27 Civic Center *Concrete Replace damaged concrete throughout the facility.$80,000 8 27 Citywide Lighting Replace cell tower streetlights with solar.$35,000 9 27 Civic Center *A/C units Replace condenser coils on A/C units 1, 2, and 4.$200,000 10 27 Downtown, Bub Williamson
Park, Pala Vista Park, Skate
Parks 1 and 2
Lighting and electrical timers Replace existing lighting and electrical timers.$30,000 11 27 Fire Station 2 *Termite control Tent building for termite treatment.$8,000 12 27 Fire Stations 1, 5, 6 *Lighting controllers Replace lighting controls. $30,000 13 27 JP Recreation Center Renovation Interior and exterior upgrades and repairs throughout the facility, including flooring, paint and fixtures in identified areas.$500,000 14 27 Moonlight *Chairs Replace old folding chairs. $45,000 15 27 Moonlight *Alarm system Replace fire alarm system in Stagehouse.$45,000 16 27 Moonlight *Turf Replace Amphitheatre seating area turf.$110,000 17 27 Moonlight *Roof Replace all five Stagehouse roofs and office roof.$650,000 18 27 Senior Center Soundproofing Install sound absorbing panels. $130,000 19 27 Sheriff Substation - Moon Road Roof Replace roof.$75,000 20 27 Thibodo Ranch House Renovation Upgrade Ranch House interior. Replace doors and crash bars, replace upper windows, clean and repair interior and exterior fireplaces, repaint interior, install new interior light fixtures and other minor interior upgrades. $250,000
21 27 Wave Waterpark Fire alarm Replace fire alarm panel. $20,000 $3,678,000
*These projects will be funded by Proposition L. Additional projects will be funded by Redevelopment Funds.
FY26/27
Total
04/28/2026 D1 2 of 2