CITY OF
City of Weed
WEED
Agenda Item Summary
VIT
Meeting: City Council - 9 July 2026
Department: Chris Davis, Public Works Director
Agenda Item Title: Mill Fire Storm Drainage Infrastructure Replacement Project Staff Recommends: City Council Approve Resolution No. 31-2026 awarding the Mill Fire Storm Drainage Infrastructure Replacement Project to Tullis Inc in the amount of $1,113,269.00 Summary: On June 25, 2026, bids were received up to 2:00 PM. Those bids were as follows:

Buzy Bee Paving Company: $1,045,897.00
Tullis Inc: $1,113,269.00
Shasta Services TBD Timberworks: $1,114,250.00
Mike Peters Inc: $1,254,929.50
Stimple Wiebelhaus: $1,372,997.50
S.T. Rhoades Construction Inc: $1,520,028.00
Fiscal impact:
$548,000 of Mill Fire Fund
Alternative Actions:

1. Approve Resolution Awarding the Contract

2. Deny

3. Other actions at Council's discretion
Environmental Review:

None.

Attachments:

Recommendation of Award Letter
Resolution
Bid Summary
5155 VENTURE PARKWAY
PACE®
REDDING, CA 96002
(530) 244-0202

ENGINEERING

RECOMMENDATION OF AWARD
July 7, 2026
161.110
Chris Davis, Public Works Director
City of Weed
550 Main Street
Weed, CA 96094
[email protected]
Members of the City Council:

Subject: Mill Fire Storm Drainage Infrastructure Replacement Project The bid opening for the subject project was held on June 25, 2026. PACE Engineering, Inc. (PACE) has reviewed the bids received, and enclosed is the Bid Summary.

Mt. Shasta Paving, Inc. dba Buzy Bee Paving Company submitted the apparent low bid of $1,045,897.

PACE identified bid-document and responsiveness issues, including omitted or incomplete required bid documents and a separate proposal adding terms, conditions, disclaimers, and limitations. In accordance with City Attorney guidance, the City has provided Buzy Bee Paving Company written notice of the finding of non-responsiveness. PACE recommends that the City reject Buzy Bee's bid as nonresponsive.

The next lowest bidder is Tullis, Inc., with a total bid amount of $1,113,269. PACE has examined Tullis, Inc.'s bid proposal and finds it complete and acceptable. Subject to City Council rejection of Buzy Bee's bid, PACE recommends that the City award the Contract to Tullis, Inc. in the amount of $1,113,269.

Once PACE is notified that the Contract has been awarded, a Notice of Award will be sent to Tullis, Inc. together with the Agreement and Bond forms. Instructions will be included for the Contractor to sign and complete the necessary documents and return them to PACE for review. PACE will then forward them to the City of Weed for signature, which will constitute execution of the Contract.

Sincerely,
Cuntie Payt
Curtis Paget
Senior Engineer
Enclosure
M: Nobs\0161 City of Weed\0161.110 Mill Fire SD Infrastructure Replacement\15 Bidding-Award\07 Award\Recommendation of Award Letter.docx
RESOLUTION NO. 31-2026

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WEED TO AWARD A

CONTRACT FOR THE MILL FIRE STORM DRAIN INFRASTRUCTURE

REPLACEMENT PROJECT
WHEREAS, the Council authorized the City Engineer to solicit bids for the Mill Fire Storm Drain Infrastructure Replacement Project; and
WHEREAS, the bids were advertised and opened pursuant to California law; and WHEREAS, the City Engineer, after reviewing such bids, has determined that Tullis, Inc nas submitted the most competent bid and, thus recommends that a contract to complete suct project be awarded to Tullis, Inc.; and
WHEREAS, Council finds good cause to accept the recommendation of the City Engineer,
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Weed:

SECTION 1: That Tullis, Inc. is hereby awarded a contract to perform and complete the Mill Fire Storm Drain Infrastructure Replacement Project in the amount of $1,113,269.00.

SECTION 2: A copy of the bid summary is attached hereto and made a part hereof.

SECTION 3: The City Manager or Mayor is hereby authorized to execute a contract with Tullis, Inc., pending legal review, for the project.

I HEREBY CERTIFY the foregoing resolution was introduced and adopted at a regular meeting of the City Council of the City of Weed held the 9h day of July 2026 by the following vote to wit:

AYES: Council Members
NOES:

ABSENT:

Mayor
ATTEST:

City Clerk
Adopted

BID SUMMARY
PACE® PROJECT: MILL FIRE STORM DRAINAGE INFRASTRUCTURE REPLACEMENT PROJECT OWNER: CITY OF WEED
ENGINEERING BID DATE: 6/25/2026
5155 Venture Parkway JOB NO: 161.110
Redding, CA 96002
Ph: 530.244.0202
BID ENGINEER'S Stimple-Wiebelhaus S. T. Rhoades
ITEM DESCRIPTION QTY UNIT Buzy Bee Paving Co. Tullis, Inc Timberworks M. Peters, Inc.

ESTIMATE Associates, Inc. Construction, Inc.

Construction of All Work $1,472,000.00 $1,024,897.001 $1,109,769.00 $1,095,750.00 $1,233,179.50 $1,365,497.50| $1 505.008.00 Sheeting, Shoring, and Bracing $13,000.00 $20,000.00 $2,500.00 $7,500.00 $7,250.00 $5,000.00 $12.520.00 Installation Floater Insurance $15,000.00 $1,000.00 $1,000.00 $11,000.00 $14,500.00 $2,500.00 $2,500.00 TOTAL BASIS OF BID:| $1,500,000.00| $1,045,897.00 $1,113,269.00 $1,114,250.00 $1,254,929.50 $1,372,997,50 $1.520.028.00 M: Jobs\0161 City of Weed 0161.110 Mill Fire SD Infrastructure Replacement\15 Bidding-Award106 Bid Review\Bid Summary.xisx 1 of 1