Resolution Number 24-4336

A RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF YOUNTVILLE

AUTHORIZING THE FILING OF A NOTICE OF COMPLETION AND ACCEPTING THE WORK FOR THE MT-3025 MEASURE T SOLANO AVENUE REHABILITATION

PROJECT PERFORMED BY ARGONAUT CONSTRUCTORS UNDER THE TOTAL CONTRACT AMOUNT OF $610,409.15.
______________________________________________________________________ Recitals
A. At the September 17, 2024, Town Council meeting, Council awarded the MT–3025 Measure T Rehabilitation on Solano Avenue to Argonaut Constructors at the bid price of $610,409.15.

B. This project consisted of the rehabilitation of Solano Avenue from the southern Town limits to California Drive. The work limits were street surface from the lip of gutter to lip of gutter, with no work on the concrete curbs
C. Construction of the project commenced on October 14, 2024, and is now complete. There was 1 change order for this project. The total project cost is under the budgeted amount of $610,409.15.

D. All the work has been completed to the satisfaction of the Public Works Department. By this Resolution, the Town Council authorizes the Director of Public Works to execute the Notice of Completion and directs the Town Clerk to file said Notice of Completion with the Napa County Clerk Recorder and accepts the work for the MT-3025 Measure T Street Rehabilitation on Solano Avenue.

Now therefore, the Town Council of the Town of Yountville does resolve as follows:

1. The Council hereby accepts the work performed by Argonaut Constructors.

2. The Town Clerk is hereby directed to file a Notice of Completion for said project with the Napa County Clerk Recorder within 10 days and accepts the work for the MT-3025 Measure T Street Rehabilitation on Solano Avenue.

3. The Resolution is hereby adopted and becomes effective and in full force immediately upon adoption.

PASSED AND ADOPTED at a regular meeting of the Town Council of the Town of Yountville, State of California, held on this 7th day of January 2025 by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:
___________________
Margie Mohler, Mayor
ATTEST:
_____________________
Kami Noriega, Acting Town Clerk