NAPA VALLEY FORWARDOAKVILLE INTERSECTION IMPROVEMENT
The Napa Valley Transportation Authority (NVTA) is working with the Metropolitan Transportation Commission (MTC) to develop multi-modal safety and operational improvements on SR 29 Up Valley in Oakville. The proposed improvement includes adding a compact roundabout at State Route 29 and Oakville Cross Road.

The roundabout will significantly improve safety and reduce congestion for all modes of travel and operations along the busy SR 29 corridor.

SR 29 is the only contiguous north-south route that connects Napa to the adjacent counties of Lake and Solano. It is a critical evacuation route for thousands of people during wildfires and other public safety emergencies.

NVTA will study future improvements at SR 29/Rutherford Road and SR 29/Madison Street in Yountville at a later date.

Equity
This project will
improve travel for
the adjacent Equity
Priority Communities
located in south
St. Helena and the
unincorporated area
near Yountville. These
communities live
below the federal
poverty line; have
significant populations
who are elderly,
disabled, and/or
communities of color;
and have a high
concentration of
non-English speakers.

Jobs and
Economic
Development
The project will
support Napa’s
wine and hospitality
industries as they
continue to recover
from the widespread
impacts of the
COVID-19 pandemic.

The project will
also create direct
and indirect jobs.

The improvements
will connect to the
multipurpose path, the
Napa Valley Vine Trail,
which runs west of SR
29 between St. Helena
and Yountville.
?
Questions?
Email NVTA Deputy
Executive Director
Danielle Schmitz:
[email protected]
Learn more at: nvta.ca.gov/
napa-valley-forward-intersection-improvements

SCHEDULE TIMELINE
(ESTIMATED)
Environmental Fall 2024
Final Design Spring 2025
ROW Clearance Fall 2025
Construction Spring 2026
funding dependent

EXPENDITURE COST
($ x 1,000)
Oakville Roundabout
Final PS&E $1,000
Utility & Misc. $155
ROW Engineering/Support $297
ROW Capital $650
Construction Support $7,793
Total $9,895
FACTS
SR 29 at Oakville Cross Road, Oakville | Napa Valley