PG&E’s Recent Work to
Serve Yountville
Feb 18, 2025
Internal
PG&E’s Recent work
 PG&E installed a new circuit that feeds a majority
of the Town of Yountville and the Veterans Home
of California
 The new circuit is fed from a new substation
transformer PG&E installed in 2023.
 More direct route to Yountville and Veterans
Home along highway 29 instead of Silverado Trail
 1.5 miles of conductor replaced with new larger
conductor
 1.7 miles of newly installed conductor and poles
 0.4 miles of newly installed underground cable
Internal
Benefits to the Town of Yountville
 Increased capacity for the Town of Yountville
to allow for growth in housing and businesses
 Possible alternate feed to the Town in the
event there is an outage.