Presentation to the Yountville Town Council on the
LATA Grant Project -
Broadband Engineering Feasibility Study and
Partnership Development Opportunities Report
April 1, 2025
Presented by:

Tom Robinson, President & CEO
Dick Nielsen, Senior Engineer
CBG Communications, Inc.
36 Bryan Avenue
Malvern, PA 19355
P: 445-245-4618
Introductions
CBG Communications Project Team:
 Tom Robinson, President & CEO
 Dick Nielsen, Senior Engineer
 Krystene Rivers, Senior Research
Associate
 Andrew Entrikin, GIS Specialist
2 Two Key Components of the Project
Broadband Engineering Feasibility
Study
Partnership Development Review and
Analysis
3 Broadband Engineering Feasibility
Study
 The Study was designed to ensure that broadband
infrastructure and services were available
throughout the Town, and if not, design
infrastructure to “fill in the gaps”.
 Broadband is defined as 100 megabits per second
(Mbps) download/20 Mbps upload, and the Federal and
State goal is to have it be scalable to symmetrical 100 Mbps download/upload.
4 Broadband Engineering Feasibility
Study
 Broadband system design and service review, review
of the Federal Communications Commission’s
(FCC’s) broadband maps, discussions with
broadband providers and a walkout of the available
broadband infrastructure in the Town showed that
wireline broadband service is available to all
residents and businesses within the Town.
 That wireline service is planned to be increased to above symmetrical 100 Mbps by the end of 2026.
5 Broadband
Engineering
Feasibility
Study
6 Broadband Engineering Feasibility
Study
 The Study then shifted to reviewing where public
access to the Internet should be provided at key
public gathering spots (for both residents and
visitors/tourists) in the Town.
 Areas identified included: the largest, most utilized public parks; public facilities and campuses; and the
Washington Street business corridor.
7 Broadband Engineering Feasibility
Study
 Multiple designs were made, evaluated and reviewed.

The final recommended design is proposed to be built,
based on available funding and contributions by
partners, in three phases.
 It would provide no cost to the public, wireless symmetrical 100 Mbps download/upload in all the proposed locations.  It would include multiple wireless broadband access points (APs), high-capacity wireless backhaul, fiber optic
interconnects, and access to up to a 10 gigabits per second (Gbps), fiber optic-based, Internet access backhaul network. 8 Phase 1
of the
Public Access
Network
9 Phase 2
of the
Public Access
Network
10 Phase 3
of the
Public Access
Network
11 Total Design of
the
Public Access
Network
Project
(all 3 Phases)
12 Potential Cost of the Project
Total Costs, By Phase
Phase 1 Total  $133,075
Phase 2 Total  $222,075
Phase 3 Total  $145,500
Total Cost of the Three Phases $500,650
13 Partnership Development Opportunities
 Multiple potential partnerships were explored to help develop and implement the proposed broadband
network, including with organizations that serve key
populations in the Town (i.e., seniors, veterans, etc.).  Discussions were held with Broadband providers and
system vendors, including Comcast, wireless provider
Valley Internet and others.
 Discussions were held with the Chamber of Commerce,
concerning the positive impact that enhanced
broadband can have on economic and workforce
development.
14 Partnership Development Opportunities
 A Survey was then developed and sent out to
approximately 60 members of the Chamber, with 14
businesses responding (23% response rate). Some key
findings from the Survey included:
 Approximately half of the respondents indicated their broadband service/Internet access did not meet their current needs, indicating that the service was too slow and/or was unreliable.
 Eight of thirteen survey respondents indicated that a highcapacity wireless broadband system in the Washington Street corridor and other business areas established by the Town would be beneficial to them.
15 Partnership Development Opportunities
 Eight of eleven survey respondents indicated that a highcapacity wireless broadband system covering public places would be beneficial to them, their customers and clients.  The majority of the survey respondents indicated that they weren’t sure yet how willing they would be to help financially support initial development and sustainability of such a system until they knew more about what the cost would be and how they would be asked to support it (e.g., sponsorship, advertising placement on splash pages, etc.).
 Overall, business community involvement in development and sustainability of the network will require more detailed discussions.
16 Partnership Development Opportunities
 Discussions were held with potential public partners
including the Napa County Library and the Veterans Home of California - Yountville.
 The Napa County Library presents the best opportunity for partnership, because of a current project underway to expand public Wi-Fi at the Yountville Library, that could be further expanded into the Town Center complex and
would leverage the Library’s high-capacity Internet
backhaul.
 There would need to be a detailed partnership
agreement, in a form such as a Memorandum of
Understanding.
17 Overall Conclusions and Recommendations
 Depending on available funding and contributions by
partners, the Town should:
Develop a Memorandum of Understanding with the Napa
County Library to develop and deploy, at a minimum, the first phase of the public broadband Wi-Fi system.
Work with the Library through the established MOU or a private vendor/provider partner to develop and deploy
the second phase of the system implementation -- public broadband Wi-Fi Internet access in the four designated
parks.
18 Overall Conclusions and Recommendations
Work with the Library or a private vendor/provider
partner in conjunction with the Chamber of Commerce to
develop and deploy the third phase of the public
broadband Wi-Fi Internet access system to the Washington Street and other business corridors.
Leverage the public broadband Wi-Fi Internet access
system for broadband Internet adoption-spurring efforts.  Such efforts should focus on:
 Affordable access to the Internet by the public.
 Enabling the public to gain access to digital skills training while utilizing the system.
19 Q & A
20 Thank you!