AMENDMENT No. [ ] TO PROFESSIONAL SERVICES AGREEMENT FOR

CONSULTANT SERVICES
(Town of Yountville and__ _________________)
This Amendment No. (“Amendment”) to Professional Services Agreement for Consultant Services (“Agreement”) is made on this day of _____________at Yountville, California, by and between the Town of Yountville, a municipal corporation, 6550 Yount Street, Yountville, CA 94599 (“Town”) and______________________,_____________________________ ( “Consultant”).

This Amendment modifies the original Agreement between the Town and the Consultant dated _______________in the following fashion:

A. Town and Consultant desire to amend the Agreement by modifying section 3.1 – “Scope of Services” as set forth in Consultant’s ______________proposal to Town attached hereto as Exhibit [A-1] and incorporated herein by this reference.

B. Town and Consultant desire to amend the Agreement by modifying section 3.3 – “Approved Fee Schedule” as set forth in Consultant’s ______________fee schedule to Town attached hereto as Exhibit [B-1] and incorporated herein by this reference.

C. Town and Consultant desire to amend the Agreement by modifying section 3.4 – “Maximum Amount” of the Agreement to read as follows:

3.4 “Maximum Amount”: The highest total compensation and costs payable to Consultant by Town under this Agreement. The Maximum Amount under this Agreement is ___________________________ Dollars
($____________________).

D. Town and Consultant desire to amend the Agreement by modifying section 3.6 – “Termination Date” of the Agreement to read as follows:

3.6 “Termination Date”: __________________________.

E. Integration. This Amendment amends, as set forth herein, the Agreement and except as specifically amended hereby the Agreement shall remain in full force and effect.

To the extent there is any conflict between this Amendment and the Agreement, the terms and provisions of this Amendment shall control. This Amendment and the Agreement, including any exhibits attached to the Agreement and this Amendment, integrate all the terms and conditions of the Parties’ agreement and supersede all negotiations with respect hereto.
3 3
Prunuske Chatham, Inc. Prunuske Chatham, Inc. 24 March, 2026 103 Morris Street, Suite A-5, Sebastopol, CA April 12, 2023 ✔ ✔
Month, Day, Year Month, Day, Year seventy seven thousand six hundred and ninety one 77,691 06/30/2027 Amendment No. [ _ ] to Professional Services Agreement for Consultant Services Town of Yountville / ____________________ Approved for use August 2, 2024 Page 2 of 2
310157.2
TO EFFECTUATE THIS AGREEMENT, the parties have caused their duly authorized representatives to execute this Agreement on the dates set forth below. “Town”
Town of Yountville
By: ______________________________
[Name, Title]
Date: _______________
Attest:

By: ______________________________
Hilary Gaede, Town Clerk
Date: _______________
Approved as to form:

By: ______________________________
John Hope, Town Attorney
“Consultant”
___________________________
By:______________________________
[Name, Title]
Date: __________________
By:______________________________
[Name, Title]
Date: __________________
#townmanagersignature
#townmanagerdate
#consultantsignature #consultanttitle
#consultantdate
#townclerksignature
#townclerkdate
#townattorneysignature
#townmanagertitle
#clerkdate
3 Prunuske Chatham, Inc. Prunuske Chatham, Inc.
103 Morris Street, Suite A-5 Sebastopol, CA 95472 707-824-4600 fax 707-824-6854 March 10, 2026
John Ferons
Public Works Director
Town of Yountville
via email: [email protected]
Subject: Town of Yountville Recycled Water Transmission Main Repair Project Amendment No.3 for Planning and Biological Consulting Services Dear John,
PCI Ecological is pleased to offer planning, and preconstruction and construction biological consulting services to the Town of Yountville associated with the Yountville Recycled Water Transmission Main Repair Project located at the Napa River, southeast of the Town of Yountville, 94599 (Latitude 38.39869, Longitude -122.34348). The project entails the installation of a highdensity polyethylene (HDPE) pipe using horizontal directional drilling (HDD) methods under the Napa River (below grade) in order to restore recycled water conveyance services and replace an existing polyvinyl chloride (PVC) pipe that was rendered unusable following a collapse in February 2023. Following installation of the new HDPE water main, the temporary repair will be decommissioned and removed from the site. Authorization from the San Francisco Bay Regional Water Quality Control Board (RWB) via a Notice of Applicability and the California Department of Fish and Wildlife (CDFW) via a Final Streambed Alteration Agreement (SAA) has been issued to implement the project.

The following are the scope and budget estimate to meet the requirements as noted in the above authorizations from the RWB and CDFW in order to implement the project. This budget estimate includes the existing budget under Phase 330 Pre-Construction Biological Services, approved via the Modification Request (Amendment No. 2) dated July 10, 2025. Work will be conducted under PCI’s current Professional Services Agreement (Amendment No. 3) or a new standalone agreement.

SERVICES TO BE PERFORMED BY PCI ECOLOGICAL
The following tasks outline the scope of work to be completed by PCI.

1. Review contractor-prepared Frac Out Plan and submit to CDFW and RWB prior to construction.

2. Prepare and submit biologist(s) qualifications to CDFW staff for approval.

3. Pre-construction Swainson’s hawk surveys
• Conduct Swainson’s hawk surveys within a 0.5-mile buffer of the project site prior to construction as described in Measure 2.19 of the CDFW SAA and in the Recommended Timing and Methodology for Swainson’s Hawk Nesting Surveys in California’s Central Yountville Recycled Water Transmission Main Repair Project Planning and Biological Consulting Services
March 10, 2026

Page 2 of 5 ends

Valley survey protocol1. This includes conducting surveys within a minimum of two (2) survey periods prior to construction; each period requires 3 surveys for a total of 6 surveys.2
• Prepare and submit survey results to CDFW.

4. Preconstruction special-status species surveys
• Prepare and submit foothill yellow-legged frog (FYLF) survey methodology to CDFW for approval prior to completion of the preconstruction FYLF survey. • Complete one (1) preconstruction biological survey within 48 hours of start of work.

Survey will focus on identifying presence of foothill yellow-legged frog, northwestern pond turtle, American badger occupied habitat, and active native bird nests. Nesting bird surveys are only needed if work occurs within the designated nesting season (February 1 - August 31).
• Prepare and submit preconstruction survey results to CDFW. • Coordinate preconstruction surveys and access with the Town of Yountville and the contractor.

5. Construction monitoring and crew training
• Prepare training materials and present the materials to all construction personnel employed on the project to discuss biological resources issues and protection measures per project permits(one [1] training budgeted). The training will be completed on the first day of construction, and documentation of the training will be prepared and provided to CDFW.
• Complete daily site inspections prior to the start of work each day until CDFW approves transitioning from on-site biological monitoring to an on-call qualified biologist. PCI has budgeted 8 hours for one (1) day of biological monitoring during initial vegetation disturbance and 4 hours for five (5) additional daily site inspections; time includes travel. • Coordinate training and construction monitoring activities with the Town of Yountville and the contractor.
• Prepare and submit contractor training and site inspection documentation to CDFW as needed.

6. Project completion as-built report
• Establish a minimum of six (6) photo-documentation points (three (3) at the entry point and three (3) at the exit point of drilling activities) to be imaged pre- and post-construction within the project area; use to track impacts and overall project success. • Prepare a site map with the photo-documentation points clearly marked. 1 Swainson’s Hawk Technical Advisory Committee. 2000. Recommended Timing and Methodology for Swainson’s Hawk Nesting Surveys in California’s Central Valley. May 31, 2000. Accessed at:
https://nrm.dfg.ca.gov/FileHandler.ashx?DocumentID=83990&inline 2 Survey timing example: If the project starts after June 21 and before the end of Swainson’s Hawk nesting season (August 31), surveys should be conducted in Period III (April 5 to April 20) and Period V (June 10 to July 30). Surveys should never be initiated in period IV (April 21 to June 10) and should not be conducted at all if active nests have not already been identified in previous survey periods. Exact survey timing will be determined based on project start time.

Yountville Recycled Water Transmission Main Repair Project Planning and Biological Consulting Services
March 10, 2026

Page 3 of 5 ends

• Review the contractor-prepared report that describes the collection and containment of bore spoils and drilling fluids, any backfilling of boreholes, and the disposal of bore spoils and drilling fluids.
• Review and submit contractor-prepared as-built report with these post-construction summaries, photographs, and map to CDFW and RWB.

PCI DELIVERABLES
• PCI review comments on the contractor-prepared Frac Out Plan; submit final version to CDFW and RWB prior to the start of construction.
• Biologist(s) qualifications; submitted to CDFW prior to the start of construction. • Swainson’s hawk survey results memo; submitted to CDFW prior to the start of construction.
• Foothill yellow-legged frog survey methodology; submitted to CDFW 30 days prior to the start of construction.
• Preconstruction survey results memo; submit to Town for review and submit the final memo to CDFW prior to the start of construction.
• Documentation of biological training submitted to CDFW. • Email inspection summaries as needed to CDFW.
• Submit as-built report developed by the contractor or the City to CDFW and RWB post construction.

ASSUMPTIONS
Swainson’s Hawk Survey Assumptions:
• Swainson’s hawk nesting survey timing will be based on the start of construction date.

The Town of Yountville will provide this date or a working estimate to PCI by April 5, 2026, which is the latest date Swainson’s hawk surveys can be started and still meet the minimum requirements.
• The Town of Yountville will provide or facilitate survey access to 0.5-miles of land surrounding the project area, to the extent feasible, for nesting surveys. • If access is not available to some of the 0.5-mile area around the project site for nesting surveys and it is reasonable given Swainson hawk natural history and site considerations, PCI will request that CDFW consider the accessible area surveyed sufficient for this project. PCI is not responsible for a positive response from CDFW in this eventuality. • PCI anticipates that CDFW will approve PCI biologists to complete Swainson’s hawk surveys. If CDFW does not grant approval, PCI will assist the Town of Yountville in identifying a CDFW-approved qualified biologist to complete surveys. • This scope and budget do not include monitoring Swainson’s hawk nests if one is identified during the survey. Nest monitoring services will require additional scope and budget; PCI may be able to provide these services if needed.

All Other Preconstruction and Construction-period Biology Task Assumptions:
• PCI will have access to the project site, and surrounding 500-foot area, to conduct preconstruction surveys and construction monitoring tasks. • The cost estimate includes one preconstruction nesting bird survey. If construction pauses for seven (7) or more consecutive days during the nesting season and then Yountville Recycled Water Transmission Main Repair Project Planning and Biological Consulting Services
March 10, 2026

Page 4 of 5 ends

resumes, an additional nesting bird survey will be required. PCI can complete additional surveys as needed, but additional budget may be required. • The cost estimate assumes a Town of Yountville staff member or contractor crew member will be approved by CDFW to carry out the California freshwater shrimp habitat protection silt fence daily inspection described in measure 2.17 of the SAA. • A CDFW-approved PCI Qualified Biologist will conduct the preconstruction surveys and provide the required crew training. Once those tasks are complete, a Qualified Biologist or approved Biological Monitor will conduct the daily site checks during construction, if needed, and within the budgeted amount. If CDFW requires monitoring beyond what is included in the cost estimate, PCI can provide additional monitoring for an additional budget.
• A PCI Qualified Biologist will be on-call when not onsite during construction hours to be available to travel to the site if a special-status species is identified onsite and needs to be relocated and/or documented. Additional budget may be required for on-call Qualified Biologist Services if they are needed; there are no hours allocated for on-call services in the existing budget.
• PCI assumes a CESA Incidental Take Permit (ITP) from CDFW is not required to implement the project. Should CDFW request a CESA ITP, additional budget will be necessary. • The contractor will prepare the Frac-Out Plan, and the report that describes the collection and containment of bore spoils and drilling fluids, any backfilling of boreholes, and the disposal of bore spoils and drilling fluids. This report would be included in the as-build report.

SCHEDULE
PCI will work with the Town of Yountville and the contractor, as needed, to develop a project schedule. PCI will submit biologist resumes to CDFW upon authorization from the Town of Yountville. Swainson’s hawk nesting surveys may begin as soon as March 2026, after CDFW provides notice of approval and a construction start date is determined.

ESTIMATED COST
Our estimated cost to complete the services described above based on stated assumptions is $17,691. A detailed cost estimate is enclosed and includes the existing budget under Phase 330 Pre-Construction Biological Services, in the amount of $9,786. Final cost may vary depending on the actual time and materials required. We will not exceed the total estimate by more than 10% without authorization. PCI’s actual fees will be on a time and materials basis in accordance with the Fee Schedule, enclosed.

PERSONNEL
Samantha Thomas, Senior Environmental Planner, will be PCI’s project manager and primary point of contact for the project. Carrie Lukacic, Principal Environmental Planner, will be the project principal. Celia Chatham, Biologist, will be the lead biologist. Other PCI personnel may assist as needed.

Yountville Recycled Water Transmission Main Repair Project Planning and Biological Consulting Services
March 10, 2026

Page 5 of 5 ends

If you have any questions or concerns, please feel free to contact me at (707) 628-8135 or via email at [email protected]. PCI appreciates this opportunity to offer our services in helping to restore recycled water conveyance services to the Town’s customers.

Sincerely,
Samantha Thomas
Senior Environmental Planner
Enclosures: Cost Estimate
Fee Schedule
Town of Yountville Recycled Water Transmission Main Repair Project Amendment #3
Cost Estimate
March 2026
$17,691 Principal
Ecologist
Principal
Vegetation
Ecologist
Environmental
Planner III Biologist III Biologist II IRS rate GPS Equipment Line Item Subtotal $239 $150 $197 $170 $154 $0.725 $200 Cost
hour hour hour hour hour mile day
Frac Out Plan; review and submit to CDFW and RWB 2 $394 Biologist(s) qualifications; prepare and submit to CDFW 2 $340 Swainson's Hawk Nesting Surveys (includes 6 surveys, survey summary memo and coordination) 1 4 56 480 3 $11,495 Preconstruction Special-status Species Surveys
Prepare and submit FYLF monitoring survey methodology to CDFW for approval 3 $510 Qualified biologist conduct pre-construction nesting bird/turtle/FYLF/badger surveys; identify RPZ; access and coordination 10 80 $1,758
Reporting to CDFW 1 6 $1,259
Construction Monitoring and Crew Training
Prepare and conduct pre-construction crew training 6 80 $1,078 Biologist on-site daily inspection visit (Qualified bio/Bio monitor; assumes one 8-hr day for initial disturbance monitoring; 5 site checks, 4 hours per site visit; includes travel); 28 480 $5,108 Contractor coordination 3 $510
Reporting to CDFW 8 $1,360
As-build Report; review and submit to CDFW and RWB 4 2 $1,128 Project Management; meetings and coordination 2 7 4 $2,537 Existing Budget Available -$9,786.00
Total 4 0 17 128 0 1120 3 $17,691
3/10/2026 1 of 1
2026 Consulting Fee Schedule
Classification Hourly Rate
Overtime Hourly
Rate
Design & Planning Services
Founding Principal $251
Principal Civil Engineer $239
Principal Landscape Architect $239
Principal Geomorphologist $239
Principal Hydrologist $239
Principal Environmental Planner $239
Principal Vegetation Ecologist $239
Registered Civil Engineer V $239
Registered Civil Engineer IV $229
Registered Civil Engineer III $214
Registered Civil Engineer II $197
Registered Civil Engineer I $180
Assistant Engineer III $174 $209
Assistant Engineer II $157 $189
Assistant Engineer I $141 $169
Senior Hydrologist/ Geomorphologist $207
Project Manager/ Physical Scientist II $191
Project Manager/ Physical Scientist I $174
Registered Landscape Architect V $239
Registered Landscape Architect IV $219
Registered Landscape Architect III $202
Registered Landscape Architect II $186
Registered Landscape Architect I $178
Assistant Landscape Architect IV $174 $209
Assistant Landscape Architect III $163 $196
Assistant Landscape Architect II $152 $182
Assistant Landscape Architect I $135 $162
QSD/CPESC/RPF $186
QSP $147
Environmental Planner IV $213
Environmental Planner III $197
Environmental Planner II $169 $202
Environmental Planner I $135 $162
Sr. Wildlife Biologist/Botanist/Vegetation Ecologist IV $191 $229 Wildlife Biologist/Botanist/Vegetation Ecologist III $170 $204 Wildlife Biologist/Botanist/Vegetation Ecologist II $154 $184 Wildlife Biologist/Botanist/Vegetation Ecologist I $136 $163 Technical Assistant $120 $144
Project Administrator $107 $128
Clerical $90 $108
PW Survey Chief of Party $197 $236
PW Survey Instrument Person $169 $203
PW Survey Chain Person/ Rod Person $158 $190
PW Construction Inspector Gr3 (earthwork/ grading) $197 $236 PW Laborer Gr3/ Specialist $115 $138
Project Consumed Materials cost plus 15%
Rented Vehicles and Equipment cost plus 15%
Subconsultants / Subcontractors cost plus 15%
PCI-owned Vehicle IRS rate per mile
Employee-owned Vehicle $75/ day
PCI-owned Survey or GPS Equipment $200 per day
Lodging GSA rate per day
Per Diem GSA rate per day
Pressure Transducer $100 per month
Invoicing occurs monthly for 100% of the work completed during the invoice period unless otherwise arranged. Fees are calculated on a time and materials basis in accord with this fee schedule. Payment is due upon receipt. Fees are subject to change annually.

Prunuske Chatham Inc. (PCI Ecological) 103 Morris Street, Suite A-5 Sebastopol, CA 95472 (707) 824-4600 Contractor Lic.: #590735 (A, C-27)