Attachment 2 - Project List

Yountville City Council
May 5, 2026

Document
Attachment 2 - Project List
Meeting
May 5, 2026
Body
Yountville City Council
Original file
294 KB
Text extracted from the city's file for reading and search. Open the original on townofyountville.primegov.com. That file is the official record.

Project Description Location of each proposed project*
Engineer's
Estimate
Project’s
Estimated
Completion Useful Life
Trail Improvements $5,000 FY26/27 40
Hopper Creek $25,000 FY26/27 40
Yountville Cross Roads $8,500 FY26/27 40
Various locations as needed. $8,500 FY26/27 40
Paving Projects-Engineering and
Construction Various locations as needed to supplement Measure U project list. $55,000 FY26/27 10+ Total $102,000
* All locations are an estimate and have yet to be finalized.

Curb, Gutter,Sidewalk, ADA Path and or
Ramp Replacement
Exhibit A
SB 1 List of Projects FY 26/27
Town of Yountville
FY Proposed Title Description Location Components Est Start Est Completion
Est Useful Life Assembly Senate Est. Cost
26/27
Curb, Gutter,
Sidewalk, ADA Path
and or Ramp
Replacement
This project will include: Sidewalk and/or Crosswalk Installation (New), Cost Estimating, ADA Curb Ramp Rehab/Repair (Existing), Pavement Rehab/Repair (Existing), Sidewalk and/or Crosswalk Rehab/Repair (Existing), Document Preparation, ADA Curb Ramp Installation (New), Repair of pedestrian hazards on pedestrian trail, Preliminary Design Trail Improvements,.Hopper Creek Path,Yountville Cross
Roads, * All locations are an estimate and have yet to be finalized. Pre-Construction
and Construction
7/25/2026
08-2026
11/2026
08/2027 20-40 40 3 $100,000
26/27
Paving ProjectsEngineering and
Construction
This project will include: Environmental Study/Documents, Cost Estimating, Pavement Rehab/Repair (Existing), Document Preparation, Paving and/or Striping Rehab/Repair (Existing Safety)
Various locations as needed to supplement Measure U
project list, Californai Drive, Yountville Cross Road. All locations are an estimate and have yet to be finalized.

Pre-Construction
and Construction
07/2026
12/2026
10/2026
08/2027
5-15 40 3 $60,000
Exhibit A- FY 2026-27 Proposed Project List SB1: The Road Repair Accountability Act