RECOMMENDATION
Adopt Resolution Number 26-4407 approving an amendment to the existing Professional Services Agreement (PSA) with Prunuske Chatham, Inc., increasing the agreement's maximum amount from $60,000 to $78,000 and authorizing the Town Manager to execute the amendment and following amendments for this contract up to the budgeted amount.
DISCUSSION/BACKGROUND
On April 13, 2023, the Town entered into a Professional Services Agreement (PSA) with Prunuske Chatham, Inc. for environmental permitting services as part of the Recycled Water Transmission Main Repair. The Town owns and operates a Recycled Water Transmission Main that delivers treated wastewater to the golf course and various vineyard pond customers located on both the east and west sides of the Napa River. This recycled water transmission line runs under the Napa River and during the 2023 storms, a leak was discovered. Due to the location of the leak under the Napa River, any repair or replacement project would require various environmental permits to meet wildlife and water regulatory requirements. The Town hired Prunuske Chatham to assist with these regulatory permits.
The initial contract was approved by the Town Manager for $44,900. As the project design progressed and a final design was chosen, the environmental permit process required additional services to secure the approval of the regulatory agencies such as the Department of Fish and Wildlife and the State Water Resources Control Board.
In addition to the increased cost for services during design, it is also necessary to include additional funds for pre-construction environmental biological survey work. The extent of this survey will not be known until the design is finalized, and the project is entering construction. The regulatory agencies will issue final permits with conditions the Town must follow including details for the pre-construction environmental biological survey work.
Amendment Number 2 was authorized to increase the contract by $15,100 to $60,000 to cover the costs of the extended work to complete the environmental permitting and process and begin the coordination for the biological surveys. Staff is proposing the approval of Amendment Number 3 to cover costs for the preconstruction and construction biological surveys. Amendment Number 3 will raise the contract from $60,000 to $78,000. This work is necessary to meet the requirements of regulatory environmental permits. Due to the location of the construction work in relation to the Napa River and vineyards, staff anticipates additional charges related to the environmental work required to meet the regulatory permits.
Staff recommends that Town Council adopt Resolution Number 26-4407 approving an amendment to Professional Service Agreement Number 2023-802 with Prunuske Chatham, Inc. to provide consulting services beyond the original scope of work and authorize the Town Manager to execute this amendment and following amendments for this contract up to the budgeted amount.
ENVIRONMENTAL REVIEW
Exempt per California Environmental Act (CEQA) Guideline, Section 15061(b)(3).
FISCAL IMPACT
Is there a Fiscal Impact? Yes
Is it Currently Budgeted? Yes
Where is it Budgeted? WW 0042 Recycled Water Transmission Main Repair Is it Mandatory or Discretionary? Discretionary
Is there a Staff Resource Impact? Nominal
ATTACHMENTS
1. Resolution No 26-4407
2. Amended Scope of Work