CONTRACTING REQUIREMENTS
December 2024 00700 - 78 City of Yuba City
General Conditions Municipal Well No. 3

3. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and

4. Other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, wetlands, pavements, roadways, structures, utilities, and underground facilities not designated for removal, relocation, or replacement in the course of construction, even if not shown on the Contract Drawings.

5. The Contractor shall comply with all applicable laws and regulations of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury, or loss and shall erect and maintain all necessary safeguards for such safety and protection. The Contractor shall notify owners of adjacent property and of underground facilities and utility districts when prosecution of the Work may affect them and shall cooperate with them in the protection, removal, relocation, and replacement of their property. All damage, injury or loss to any property caused, directly or indirectly, in whole or in part, by the Contractor, any subcontractor, supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be remedied by the Contractor, and the Contractor shall be responsible for any direct or indirect costs resulting from such damage, injury or loss.

E. Excavation Safety:

1. In accordance with the provisions of §6705 of the California Labor Code, the Contractor shall submit, in advance of excavation of any trench or trenches five (5) feet or more in depth, a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plans vary from the shoring system standards set forth in the Construction Safety Orders of the Division of Industrial Safety in Title 8, Subchapter 4, Article 6, California Code of Regulations, the plans shall be prepared and signed by a registered civil or structural engineer employed by the Contractor, and all costs therefor shall be included in the price named in the Contract for completion of the work as set forth in the Contract Documents. Nothing in this Section shall be deemed to allow the use of a shoring, bracing, sloping, or other protective system less effective than that required by the Construction Safety Orders. Nothing in this Section shall be construed to impose a tort liability on the City, the Design Engineer, the Construction Manager, nor any of their officers, officials, employees, agents, consultants or volunteers. The City's review of the Contractor's excavation plan is only for general conformance to the Construction Safety Orders.

2. Prior to commencing any excavation, the Contractor shall designate in writing to the Construction Manager the "competent person(s)" with the authority and responsibilities designated in the Construction Safety Orders.

F. Safety Emergencies:

1. In emergencies affecting the safety or protection of persons or the Work or property at the Project Site or adjacent thereto, the Contractor, without special instruction or authorization from the Construction Manager, is obligated to act to prevent threatened damage, injury, or loss. The Contractor shall give the Construction Manager prompt written notice if the Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby.

G. Safety Violations:

1. Should the Contractor fail to correct an unsafe condition, the City shall have the right to notify the Contractor through the Construction Manager that an unsafe condition may exist and must be corrected or the work in question can be stopped in accordance with Section 00700-8.09, Suspension of Work, until the condition is corrected to the satisfaction of the City. No extension of time or additional compensation will be granted as a result of any stop order so issued. The notification and suspension of such work or the failure to provide such notification and suspension by the City shall not relieve the Contractor of its sole responsibility and liability for safety and the correction of any unsafe conditions.

2. The City shall have the authority to require the removal from the project of any worker and the foreman and/or superintendent in responsible charge of the work where safety violations occur.

Page 290 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 79 City of Yuba City
General Conditions Municipal Well No. 3
H. Equipment Safety Provisions:

1. The completed Work shall include all necessary permanent safety devices, such as machinery guards and similar safety items, required by the State and Federal (OSHA) industrial authorities and applicable local and national codes. Further, any features of the Work, including City-selected equipment, subject to such safety regulations shall be fabricated, furnished, and installed in compliance with these requirements. All equipment furnished shall be grounded and provided guards and protection as required by safety codes. Where vapor-tight or explosion-proof electrical installation is required by safety codes, this shall be provided. Contractors and manufacturers of equipment shall be held responsible for compliance with the requirements included herein. The Contractor shall notify all equipment suppliers and subcontractors of the provisions of this paragraph.

I. Confined Spaces:

1. The Project requires work in confined spaces and requires compliance with Cal/OSHA and Federal OSHA requirements. Confined spaces for the purposes of this Section shall be as defined by the Division of Industrial Safety. Notwithstanding any classifications relative to the Tunnel Safety Orders, work within confined spaces of this project is subject to the definitions and applicable provisions of Section 1950 et. seq., Title 8, Division 1, Chapter 4, Subchapter 4, Article 37 of California Code of Regulations.

2. Entry into existing “permit” confined spaces as defined by OSHA shall be allowed only in compliance with a confined space entry permit program by the Contractor that meets the requirements of Cal/OSHA Sections 1953-1962. While the City (Host Employer) has identified certain existing facilities as confined spaces, other confined spaces may exist on the Project. It shall be the responsibility of the Contractor (Controlling Contractor) to notify the City of unidentified confined spaces, reference Cal/OSHA Section 1952(h) for permit space entry communication and coordination requirements.

3. Sources of ignition, including smoking, shall be prohibited in any confined space, including open cut trenches of any depth.

4. It is anticipated that the Contractor may encounter hazardous conditions within these confined spaces which include, but are not limited to the following:

Exposure to hydrogen sulfide, methane, carbon dioxide and other gases and vapors commonly found in municipal sewers which could have or has the potential of having Immediate Danger to Life or Health Conditions (IDLH).

Exposure to atmosphere containing insufficient oxygen to support human life.

Exposure to combustible, flammable, and/or explosive atmosphere.

Exposure to sewage which may contain bacteriological, chemical, and other constituents harmful to humans.

Work in conditions where engulfment or entrapment may occur.

Work in environments which may be slippery and/or have uneven work surfaces.

Work in structures which have limited and/or restricted access and egress.

Work in structures where workers may trip, slip, and/or fall several feet.

J. Construction Activity Permits:

1. The Contractor must submit a copy of its respective current DOSH permit before beginning work on any the following construction activities:

2. Construction of trenches or excavations which are five feet or deeper and into which a person is required to descend.

3. Construction of any building, structure, scaffolding or falsework more than three stories high or the equivalent height (36 feet).

4. Demolition of any building or structure, or dismantling of scaffolding or falsework more than three stories high or the equivalent height (36 feet).

Page 291 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 80 City of Yuba City
General Conditions Municipal Well No. 3

5. Erection or dismantling of vertical shoring systems more than three stories high, or the equivalent height (36 feet).

12.02 PUBLIC ACCESS, SAFETY AND CONVENIENCE
A. In accordance with the provisions of §6500 of the Labor Code the Contractor shall conduct its work so as to ensure the least possible obstruction to traffic and inconvenience to the general public and the residents in the vicinity of the Work and to ensure the protection of persons and property. No road or street shall be closed to the public except with the permission of the Construction Manager and the proper governmental authority. Fire hydrants on or adjacent to the Work shall be accessible to firefighting equipment at all times. Temporary provisions shall be made by the Contractor to ensure the use of sidewalks, private and public driveways, and proper functioning of gutters, sewer inlets, drainage ditches and culverts, irrigation ditches and natural water courses. To the maximum extent permitted by law, Contractor shall indemnify, hold harmless and defend City from any and all liability, including attorneys’ fees and costs of litigation, arising from any failure to comply with this Section by Contractor or its privities.

B. The Contractor shall, at all times, provide for "Public Convenience and Safety", as described in the City’s Standard Specifications, OSHA and State of California Safety regulations.

C. The Contractor shall schedule and conduct the work so as to minimize the inconvenience to the public, as well as to City employees at any City facilities and adjoining areas impacted by the work. Any phase of the work which requires disruption of utilities, shall be scheduled three (3) days in advance with the affected parties.

D. The design of the facilities included in this Project has been based on the concept that the structures are not accessible to and usable by the handicapped and the general public. Consequently, stairs, landings, platforms, railings, ladders, exits, and the like, for treatment facilities were designed to conform only to the requirements for industrial use by authorized persons.

E. The Contractor shall have complete responsibility for the work and protection thereof and for preventing injuries to persons and damage to the work, property, and utilities on or about the work until completion and final acceptance thereof. The Contractor shall in no way be relieved of its responsibility by any right of the Engineer to give permission or directions relating to any part of the work, by any such permission or directions given, or by failure of the Engineer to give such permission or directions.

F. The Contractor is prohibited from using a wireless telephone while driving on City business and/or City property unless the vehicle has been equipped with a stationary, hands-free device to enable conversations without the use of one or both of the driver’s hands. When operating any vehicle that requires a Class A or B license or a special use certification, the use of cellular phones, radios, or any other communication device, while on City property, is prohibited.

G. Refer to Division 1- General Requirements, for any further requirements on safety procedures to be followed in and about public roadways.

H. The Contractor shall provide and maintain all necessary safety equipment, such as fences, barriers, signs, lights, walkways, guards, and fire-prevention and fire-fighting equipment, and shall take such other action as is required to fulfill its obligations under this Section.

I. Contractor shall make use of slating and screening in any fencing around the job Site or staging area to keep areas reasonably hidden from view.

J. The Contractor shall so conduct its operations as not to close or obstruct any portion of any railroad, highway, road, or other property until permits therefor have been obtained from the governmental or other authorities having jurisdiction thereof. If any of the above are required to be kept open and are damaged or rendered unsafe by the Contractor's operations, the Contractor shall, at its expense, make such repairs and provide such temporary guards, bridges, lights, and other signals as necessary or required for public safety and as will be acceptable to the governmental or other authorities having jurisdiction thereof. Fences that interfere with any work may, upon prior written approval of the City, be removed by the Contractor but must then be restored to their original condition prior to final acceptance.

Such removing and restoring shall be by and at the expense of the Contractor.

Page 292 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 81 City of Yuba City
General Conditions Municipal Well No. 3
K. Unless otherwise specifically provided in the Contract, the Contractor shall not do any work that would affect any pipeline, telephone, telegraphic, or electric transmission line, irrigation ditch, or other structure, nor enter upon the rights-of-way or lands appurtenant thereto, until notified by the owners that the City has obtained proper authority therefor from the owners thereof.

L. Thereafter and before such work begins, the Contractor shall give said owners convenient access and reasonable cooperation in their removing, shoring, supporting, or otherwise protecting such lines, ditches, and structures, and for replacing same.

M. Care shall be exercised by the Contractor to prevent damage to adjacent walks, streets, culverts, and gutters; where equipment will pass over these obstructions, suitable planking shall be placed.

N. The Contractor shall not be entitled to any extension of time or any extra compensation on account of any postponement, interference, or delay caused by any such line, ditch, or structure being on or adjacent to the Site of work, except as provided in this Section 00700-9.02.G, Differing Site Conditions.

O. The Contractor shall preserve and protect all cultivated and planted areas, and vegetation such as trees, plants, shrubs, and grass on or adjacent to the premises, which, as determined by the Engineer, do not reasonably interfere with the performance of work. The Contractor will be held responsible for damage to any such areas and vegetation and for unauthorized cutting of trees and vegetation, including without limitation, damage arising from the performance of its work through operation of equipment or stockpiling of materials. All costs in connection with any repairs or restoration necessary or required by reason of any such damage or unauthorized cutting shall be borne by the Contractor.

P. Adequate warning and construction signs shall be maintained at the construction Site for the safety of the public. Additional signs for the convenience of the public shall be maintained as directed by the City.

Q. The Contractor shall maintain sufficient safeguards against occurrence of accidents, injuries, or damage to any person or property and shall be responsible for same if such occurs. The Contractor shall also maintain adequate protection of its work and materials from destruction and loss and shall protect the City's property from damage arising in connection with this contract, and shall make good any such damage, destruction or loss.

R. Contractor must pave pedestrian openings through falsework or provide full width continuous wood walks and keep all walkways clear. Contractor must protect pedestrians from falling objects and water runoff. Overhead protection for pedestrians must extend not less than four (4) feet beyond the edge of a structure.

S. Contractor's equipment must enter and leave the Project area via access routes designated or accepted in writing by City, and move in the direction of public traffic at all times. All movements on or across public traveled ways must not endanger public traffic.

T. Contractor must immediately remove any spillage, debris, dirt, or mud resulting from hauling operations along or across any public traveled way.

12.03 PROTECTION AND RESTORATION OF PROPERTY
A. California Civil Code §832 provides requirements relating to notification of adjacent property owners (30 Day notification required) and protection of adjacent property when performing excavation that may adversely impact the lateral and subjacent support to adjoining land or structures. In addition to these requirements and any other requirements imposed by law, Contractor must shore up, brace, underpin, and protect as may be necessary, all foundations and other parts of all existing structures adjacent to and adjoining the Site of the Work which are in any way affected by the excavations or other operations connected with the Work pursuant to this Contract. Whenever any notice is required to be furnished by City or Contractor to any adjoining or adjacent landowner or other party before commencement of any Work pursuant to this Contract, Contractor must provide such notice. Contractor shall indemnify and hold City harmless from any damages for which City may become liable in consequence of such injury or damage to adjoining or adjacent structures and premises.

B. Contractor shall immediately repair, at Contractor’s sole cost and expense, any damage arising from or in consequence of the performance of the Contract, to improvements or property, whether above or

Page 293 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 82 City of Yuba City
General Conditions Municipal Well No. 3
below the ground, private or public, within or adjacent to the Project. If, in City's opinion, City's best interests require such repair to be made before execution of any part of the Work included in this Contract, City will so notify Contractor who will delay or discontinue the performance of that part of the Work until the necessary repair has been made. Such delay shall not be considered unavoidable, and no extension of the Contract Time shall be allowed.

C. When Ordered by City to make any repair, Contractor shall start work thereon within four (4) hours and must prosecute the same with diligence to completion. Upon Contractor's failure to comply with such Order, or upon Contractor's failure to make immediate Emergency repairs which are necessary in the best interests of City or the public, City may cause such repairs to be made and deduct the costs thereof from any money due, or that may become due Contractor.

D. In an Emergency affecting the safety of life or property, including adjoining property, Contractor is authorized to act at its discretion, without special instructions or authorization from City, to prevent such threatened loss or injury, and Contractor must act whether or not instructed by City. Contractor must maintain adequate protection against damage to life and property involved in Project and on property adjacent thereto until Acceptance and must Provide all necessary guards, barricades, night lights, facilities, tools, equipment, materials and other needed or required protective devices.

E. Contractor will until Acceptance maintain adequate protection of all its Work and work performed by others pursuant to the Contract Documents from damage, loss, or defacement. Contractor must repair or replace any such damage and remove any damaged or defaced material or equipment from the premises at no extra cost to City except as may be due directly to errors in the Contract Documents or caused by City.

F. The Contractor must ensure the limits of Work to be free of graffiti or other similar defacements during the entire Contract Time; if such defacement occurs, the Contractor must promptly remove, repair, or correct the affected area(s). The Contractor must protect all exposed finished surfaces within the limits of Work (both temporary and final), with anti-graffiti coatings, and maintain such protection continuously during the entire Contract Time.

12.04 PRESERVATION OF CULTURAL RESOURCES
A. Pursuant to the National Historic Preservation Act of 1966, State laws and County ordinances, the following procedures are implemented to ensure historic preservation and fair compensation to Contractor for construction delays that may occur due to cultural resources discoveries.

B. In the event potentially historical, architectural, archaeological or cultural resources (hereinafter "resources") are discovered during subsurface excavations at the Project Site, the following procedures apply:

C. City will issue a "Cultural Resources – Suspend Work Order" Directing Contractor to temporarily suspend all operations at the location of such potential resources.

D. Such "Cultural Resources – Suspend Work Order" will be effective until such time as a qualified Consultant can assess the value of such resources and make recommendations. Any "Cultural Resources – Suspend Work Order" will contain the following:

1. A description of the potential resource, its location, and the area where Contractor's Work is suspended;

2. A description of what part or all of Contractor's Work is suspended;

3. Instructions regarding suspension of orders by Contractor for materials and services;

4. Guidance regarding action to be taken by Subcontractors;

5. Estimated duration of the temporary suspension.

E. If the Consultant determines that the potential find is indeed a cultural resource, City will, as expeditiously as possible, advise Contractor in writing of the action to be taken regarding the find, and the anticipated time frame and extent of any Work suspension.

F. Adjustment of Contract Time and Contract Sum

Page 294 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 83 City of Yuba City
General Conditions Municipal Well No. 3

1. If, in the Notice Inviting Bids, the Work Site was deemed "Archaeologically Sensitive", then the Contract Time(s) includes five (5) work days of temporary suspension for cultural resources finds and there will be no payment for such suspension or any inefficiencies related thereto, up to a maximum cumulative duration of five (5) work days delay to the Critical Path(s) of the Official Progress Schedule. If such suspension occurs, the first five (5) work days of the Critical Path delay will be treated as an excusable non-compensable delay and the Contract Time will be extended in accordance with Section 00700-8.04, Time Extensions.

2. If a cultural discovery at an Archaeologically Sensitive Site results in a cumulative Critical Path delay that exceeds five (5) work days, then Contractor will be entitled to an adjustment of the Contract for the Critical Path delay in excess of five (5) work days. The Critical Path delay in excess of five (5) work days will be treated as an excusable compensable delay and the Contract Time will be extended in accordance with Section 00700-8.04, Time Extensions.

3. If a cultural resource discovery was unforeseen (i.e. if the Work Site was not deemed "Archaeologically Sensitive" in the Notice Inviting Bids), Contractor may be entitled to an adjustment of the Contract in accordance with Section 00700-8.04, Time Extensions.

4. If, as a result of a temporary suspension, City agrees that Contractor sustains a loss which could not have been avoided by judicious handling of its forces or equipment, or by redirection of forces or equipment to perform other Work on the Contract, Contractor will be paid for idle time of equipment and labor by Force Account as provided in Section 00700-9.02.D, Field Order- Force Account Work.

G. Documentation:

1. Beginning with the first Day of suspension, and for each following Day, Contractor must maintain detailed hourly records of the labor and equipment idled by such suspension, plus substantiation as to why such labor and equipment could not be used on other parts of the Work if such were the case. Such records must be of a form acceptable to City, signed by Contractor, and are subject to verification by City.

2. Failure by Contractor to furnish the aforesaid records constitutes a waiver of Contractor's right to an adjustment in the Contract Sum.
**END ARTICLE 12**

Page 295 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 84 City of Yuba City
General Conditions Municipal Well No. 3
ARTICLE 13 - INSURANCE AND INDEMNIFICATION

13.01 INSURANCE
Contractor shall maintain, at its own expense, all the insurance required by this article and submit coverage verification for approval by the City prior to the City’s execution of the Agreement.

The Agreement will not be executed by the City, and the Contractor shall not commence Work, until such insurance has been approved by the City. Such insurance shall remain in full force and effect at all times during the prosecution of the Work and until the Final Completion thereof. In addition, the commercial general liability insurance shall be maintained for a minimum of three (3) years after Final Completion of the Work. The City’s issuance of the Notice to Proceed does not relieve the Contractor of the duty to obtain such insurance as required herein.

The Contractor shall require and verify that all subcontractors maintain insurance meeting all requirements stated herein, and Contractor shall ensure that the City is an additional insured on insurance required from subcontractors. For CGL coverage, subcontractors shall provide coverage with a form at least as broad as CG 20 38 04 13.

Insurance is to be placed with insurers with a current A.M. Best’s rating of no less than A:VII or equivalent and that are admitted to and authorized to do business and in good standing in California, unless otherwise approved by the City. In the case of workers’ compensation and employer’s liability insurance, coverage provided by the California State Compensation Insurance Fund is acceptable.

Each insurance policy required by the this article shall be endorsed to state that coverage shall not be suspended, voided, canceled by either party, or reduced in coverage or in limits except after thirty (30) days prior written notice has been given to the City by the insurance carrier. Should the insurance carrier refuse to provide this notice, the Contractor shall be obligated to provide to the City thirty (30) days prior written notice of any insurance coverage being suspended, voided, reduced or canceled by either party, or any reduction in coverage or in limits.

The Contractor shall include all costs for insurance in its Total Bid Price.

Nothing contained in these insurance requirements is to be construed as limiting the extent of the Contractor's responsibility for payment of damages resulting from its operations under the Contract Documents. For any claims related to Contractor's Work, as opposed to work City has contracted to parties other than Contractor, the Contractor’s insurance coverage shall be primary insurance as respects the City, Construction Manager, Engineer, Funding Agencies and their directors, officers, elected officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, and volunteers. For any claims related to Contractor's Work, any insurance or self-insurance maintained by the City, Construction Manager, Engineer, Funding Agencies and their directors, elected officials, officers, officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, or volunteers shall be in excess of the Contractor’s insurance and shall not contribute with it.

All insurance coverage maintained or procured pursuant to this Contract shall be endorsed to waive subrogation against the City, Construction Manager, Engineer, Funding Agencies, and their directors, officers, elected officials, employees, agents, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, and volunteers or shall specifically allow Contractor - or others providing insurance evidence in compliance with these specifications - to waive their right of recovery prior to a loss. Contractor hereby waives its own right of recovery against the City, Construction Manager, Engineer, Funding Agencies, and their directors, officers, elected officials, employees, agents, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, and volunteers, and shall require similar written express waivers and insurance clauses from each of its subcontractors. Copies of these waivers shall be submitted to the City prior to commencement of work.

Any failure of the Contractor to comply with reporting or other provisions of the policies including breaches of warranties shall not affect coverage provided to the City, Construction Manager, Engineer, Funding Agencies and their directors, elected officials, officers, officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, or volunteers.

Page 296 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 85 City of Yuba City
General Conditions Municipal Well No. 3
The Contractor shall take out, pay for, and maintain throughout the duration of the Contract and for such additional periods as more specifically required herein the following insurance against claims for injuries to persons or damages to property which may be caused by the performance of the Work hereunder by the Contractor, the Contractor’s agents, representatives, employees or subcontractors, or from operations under the Agreement.

A. Commercial General Liability and Automobile Liability Insurance – This insurance shall protect the Contractor from claims for bodily injury, personal injury and property damage which may be caused by the performance of the Work hereunder by the Contractor, the Contractor’s agents, representatives, employees or subcontractors, or from operations under the Contract Documents. The commercial general liability insurance shall be maintained for three (3) years after Final Completion of the Work and shall provide coverage on an occurrence basis.

1. Additional Insureds – The commercial general liability and automobile policies of insurance shall include as additional insureds or be endorsed to contain the following provisions: the City, Construction Manager, Engineer, Funding Agencies and their directors, elected officials, officers, officials, employees, agents, consultants and volunteers are to be covered as additional insureds as respects: liability arising out of activities performed by or on behalf of the Contractor; products and completed operations of the Contractor; premises owned, occupied or used by the Contractor and or automobiles owned, leased, hired or borrowed by the Contractor. The coverage shall contain no special limitation on the scope of protection afforded to the City, Construction Manager, Engineer, Funding Agency, Design Engineer, and their directors, elected officials, officers, officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, or volunteers and coverage provided to such additional insured. This policy shall provide coverage to each of the said additional insureds with respect to said work. For any claims related to this project, the Contractor’s insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees, and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.

2. Minimum Amount of Coverage (General Contractor) – Commercial General Liability (CGL):

Insurance Services Office (ISO) Form CG 00 01 covering CGL on an “occurrence” basis, including products and completed operations, property damage, bodily injury and personal & advertising injury with limits no less than $5,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location (ISO CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit. Automobile Liability: Insurance Services Office Form CA 0001 covering Code 1 (any auto), with limits no less than $5,000,000 per accident for bodily injury and property damage. Any self-insured retentions must be declared to and approved by the City.

If the contractor maintains broader coverage and/or higher limits than the minimums shown above, the City requires and shall be entitled to the broader coverage and/or the higher limits maintained by the contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City.

3. Minimum Amount of Coverage for all Listed Subcontractors included in Section 00430 - The Contractor shall require and verify that all subcontractors maintain insurance meeting all requirements stated herein: The bodily injury, personal injury and property damage liability of the Commercial General Liability insurance shall provide coverage in the following minimum limits of liability: $2,000,000 on account of any one occurrence for bodily injury and property damage, $4,000,000 personal and advertising injury limit with an annual general aggregate limit of not less than $4,000,000, and $2,000,000 products and completed operations aggregate, combined single limit. The Automobile Liability insurance policy shall provide minimum limits of $1,000,000 per accident as a combined single limit arising out of the ownership, maintenance, or use of any owned or non-owned vehicles. These minimum amounts of insurance coverage do not preclude the Contractor from requiring higher limits or additional insurance coverage as it deems necessary.

4. Minimum Amount of Coverage for Subcontractors NOT included in Section 00430 - The Contractor shall require and verify that all subcontractors maintain insurance meeting all requirements stated

Page 297 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 86 City of Yuba City
General Conditions Municipal Well No. 3
herein. The bodily injury, personal injury and property damage liability of the Commercial General Liability insurance shall provide coverage in the following minimum limits of liability: $2,000,000 on account of any one occurrence for bodily injury and property damage, $1,000,000 personal and advertising injury limit with an annual general aggregate limit of not less than $2,000,000, and $1,000,000 products and completed operations aggregate, combined single limit. The Automobile Liability insurance policy shall provide minimum limits of $1,000,000 per accident as a combined single limit arising out of the ownership, maintenance, or use of any owned or non-owned vehicles.

These minimum amounts of insurance coverage do not preclude the Contractor from requiring higher limits or additional insurance coverage as it deems necessary.

5. Subcontractors – The bodily injury and property damage liability insurance shall not be deemed to require the Contractor to have its subcontractors named as additional insureds in the Contractor’s policy, but the policy shall protect the Contractor from contingent liability which may arise from operations of its subcontractors.

6. Included Coverage – The above commercial general liability insurance shall be at least as broad as the most current ISO CGL Form 00 01 including, but not limited to, also include the following coverages:
• Premises – Operations.
• Independent Contractors.
• Products - Completed Operations.
• Personal Injury - False Arrest, Libel, Wrongful Eviction, etc. • Advertising Injury.
• Broad Form Property Damage - Including, Completed Operations. • Separation of Insureds/Cross-Liability Provision.
• Duty to Defend all Insureds.
• Deletion of any Limitation on Coverage for Bodily Injury or Property Damage Arising out of Subsidence or Soil or Earth Movement.
• Additional Insured Coverage Not Limited to Vicarious Liability – Insurance coverage for additional insureds shall be for all covered acts and occurrences, whether or not they arise out of, or result from, the Contractor’s own acts or omissions in performing the Work. • Separate Aggregate – A provision that the annual general aggregate shall apply separately to each project for which Contractor provides services away from premises owned by or rented to Contractor.
• XCU – Explosion, Collapse, Underground Damage.
• Blanket Contractual Liability – Provisions or endorsements shall state that the insurance, subject to all of its other terms and conditions, applies to the liability assumed by the Contractor under the Agreement, including, without limitation, insurable liabilities set forth in the indemnity articles of the Contract Documents.

7. Umbrella Policy – The Contractor may use an umbrella or excess policy to meet the limits requirement of Article 13.01.A.2, and listed subcontractors may use an umbrella or excess policy to meet the limit of requirements of Article 13.01.A.3. However, any such umbrella/excess policy must be approved by the City and maintain an A.M. Best Rating of no less than A:VII.

B. Workers’ Compensation Insurance – In accordance with the provisions of Article 5, Chapter 1, Part 7, Division 2 (commencing with Section 1860) and Chapter 4, Part 1, Division 4 (commencing with Section 3700) of the Labor Code of the State of California, the Contractor is required to secure the payment of compensation to its employees and for that purpose obtain and keep in effect adequate Workers’ Compensation Insurance. In accordance with California Labor Code Section 1861, the Contractor shall sign and include Section 00560, Workers Compensation Insurance Certificate, with the Contract. If the Contractor, in the sole discretion of the City, satisfies the City of its responsibility and capacity under

Page 298 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 87 City of Yuba City
General Conditions Municipal Well No. 3
the applicable Workers’ Compensation Laws, if any, to act as self-insurer, the Contractor may so act, and in such case, the insurance required by this article need not be provided.

The Contractor is advised of the provisions of Section 3700 of the Labor Code, which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and shall comply with such provisions and have employers’ liability limits of $1,000,000 per accident and per employee, and in the aggregate for injury by disease, before commencing the performance of the Work of this Agreement.

Before the Notice to Proceed with the Work under this Contract is issued, the Contractor shall submit written evidence that the Contractor has obtained for the period of the contract workers’ compensation and employer’s liability insurance as required for all persons whom it employs or may employ in carrying out the Work under this Agreement. Such evidence of coverage shall be accompanied by an endorsement from the insurer agreeing to waive all rights of subrogation against the City, Construction Manager, Engineer, Funding Agencies and their directors, elected officials, officers, officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, and volunteers which might arise by reason of any payment under the policy. This insurance shall be in accordance with the requirements of the most current and applicable State Workers’ Compensation Insurance Laws.

C. Professional Liability Insurance – All submittals required of the Contractor which are to be prepared by a licensed California engineer shall be prepared only by a licensed engineer who is covered by a professional liability insurance policy issued by a California-admitted carrier or a carrier authorized to do business in California with a Best's rating of A:VII or better, with an limit per claim of at least $2,000,000, and a $4,000,000 in the aggregate for errors and omissions. Such insurance shall be maintained in effect by said engineer at all times while performing Work on the Project and for at least three (3) years after Final Completion of the Project. Contractor shall submit an insurance certificate for such engineer prior to beginning Work for approval by the City.

D. Builder's Risk Insurance – Until the completion and final acceptance by City of all the Work under and implied by this Contract, the Work shall be under the Contractor’s responsible care and charge. The Contractor shall rebuild, repair, restore, and make good all injuries, damages, re-erections, and repairs occasioned or rendered necessary by causes of any nature whatsoever. Contractor shall provide "Special Form" Builder's Risk Insurance on the replacement cost basis as listed below:

Amount of Coverage - Equal to the full replacement cost of the Work on a completed value basis, without deduction for depreciation and shall also provide coverage for “soft costs” such as but not limited to design and engineering fees and inspection costs caused by an insured peril, up to a maximum total for all soft costs of $250,000. The builder’s risk insurance may contain sub-limits not less than the following:
• Debris removal - $250,000.
• Pollution Clean-up cost - $25,000.

Additional Insureds/Loss Payees - This insurance shall name the City, Engineer, Construction Manager, the Funding Agencies and Contractor as insureds/loss payees, as their interests may appear. Builder’s risk insurance policies shall contain the following provisions:

1. The City, Engineer, Design Engineer, Construction Manager, Contractor and subcontractors of every tier shall be named as insureds.

2. Each insured shall waive all rights of subrogation against each of the other insureds.

Included Coverage – The above builder’s risk insurance shall include the following coverages:

1. Including, but not by way of limitation, for all damages of loss to the Work and to appurtenances, to materials and equipment to be incorporated into the Project while the same are in transit, stored on or off the Site, to construction plant and temporary structures.

2. Such insurance shall cover, but shall not be limited to, the perils of fire, lightning, windstorm, hail, explosion, riot, riot attending a strike, civil commotion, smoke damage, damage by aircraft or vehicles, vandalism and malicious mischief, theft, collapse, and flood.

3. The policy shall cover the costs of debris removal, including demolition as may be made

Page 299 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 88 City of Yuba City
General Conditions Municipal Well No. 3
reasonably necessary by the application of any law, ordinance, or regulation.

4. Start-up & testing, and machinery breakdown including electrical arching.

5. Consequential losses due to delay in completing the Work. The builder’s risk insurance limit for consequential losses is $1,000,000.

6. The policy shall provide the City the right to occupy the premises without termination of the policy until Final Completion of the Project.

Deductibles - Builder’s risk insurance may have a deductible clause not to exceed the amounts below. Contractor shall be responsible for paying any and all deductible costs.

All Other Perils - $50,000.

Application of Loss Proceeds - In the event of a covered loss, proceeds of builder’s risk insurance shall be applied first to reimburse actual costs of demolition, debris removal, reconstruction, and repair or replacement incurred in the discharge of the Contractor’s obligations of repair or replacement under this Contract. Insurance proceeds shall be deposited in a separate account in a local bank satisfactory to the City and shall be withdrawn only with the City’s written approval to reimburse such actual costs as the builder’s risk carrier has agreed to reimburse. The City shall have no liability for failure of the builder’s risk carrier to pay for any particular cost of repairs. In the event of the termination of the Contractor for default, the Contractor shall forfeit all rights to builder’s risk insurance proceeds and City may expend such proceeds to complete the Project as if they were unpaid contract monies.

E. Contractor’s Pollution Liability Insurance. The Contractor shall obtain Pollution Liability Insurance. This insurance shall cover liability for bodily injury, property damage, and environmental damage resulting from pollution and related cleanup costs incurred, all arising out of any Work to be performed under the Agreement, including liability for and defense of lawsuits and regulatory actions. Coverage shall be provided for both Work performed on Site, as well as during the transport of hazardous materials.

Coverage shall apply to sudden as well as gradual pollution conditions, including without limitation conditions resulting from the escape or release of smoke, vapors, fumes, acids, alkalis, toxic chemicals, liquids, or gases, natural gas, waste materials, or other irritants, contaminants, or pollutants, including asbestos. The liability limits shall be not less than:
• Each occurrence or claim: $2,000,000.
• General Aggregate: $2,000,000.

If the coverage required is written on a claims-made coverage form:
• The retroactive date must be shown, and this date must be before the award date of the Agreement.
• Insurance must be maintained, and evidence of insurance must be provided for at least five (5) years after final payment.
• If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the Agreement award date, the Contractor must purchase extended reporting period coverage for a minimum of five (5) years after Final Payment. • A copy of the claims reporting requirements must be submitted to the City for review.

F. Proof of Coverage – Before execution of the Contract, the Contractor shall furnish the City with certificate(s) evidencing issuance of all insurance mentioned herein, copies of the policy declaration or information page(s) and additional insured endorsements. The certificate(s) and endorsements for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf.

The endorsements are to be on endorsement forms acceptable to the City. The certificate(s), policy declaration or information page(s), and endorsements are to be received and approved by the City before Work commences. Except for the waiver of subrogation rights endorsements, as required herein, no other endorsements are required for workers compensation or excess liability insurance. Such certificates of insurance shall provide that the insurance policy shall be endorsed to state that coverage shall not be suspended, voided, cancelled by either party, reduced in coverage or limits except after thirty (30) days prior written notice has been given to the City. The Contractor shall also provide certificate(s) evidencing renewals of all insurance required herein prior to the expiration date of any such insurance. The City reserves the right to require complete, certified copies of all required insurance policies, at any time.

Page 300 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 89 City of Yuba City
General Conditions Municipal Well No. 3
For all insurance policy renewals during the term of this Contract, Contractor shall send insurance certificates reflecting the policy renewals directly to the City of Yuba City 1201 Civic Center Boulevard, Yuba City, CA, 95993.

Any self-insured retentions must be declared to and approved by the City. At the option of the City, either:
• The insurer shall reduce or eliminate such self-insured retentions as respects the City, Construction Manager, Engineer, Funding Agencies and their directors, elected officials, officers, officials, employees, agents, consultants, attorneys, divisions, related agencies and entities, successors and assigns, contractors and representatives, and volunteers; or • The Contractor shall procure a bond guaranteeing payment of losses and related investigations, claim administration and defense expenses.

In the event of the breach of any provision of this article, or in the event of any notices received which indicates any required insurance coverage will be diminished or canceled, City, at its option, may, notwithstanding any other provisions of this Agreement to the contrary, declare a material breach of this Agreement and suspend all further work pursuant to this Agreement until Contractor has provided evidence that its insurance coverage meets the requirements of the Contract Documents.

G. Third Party Insurance Requirements - The Work, as contemplated by the Contract Documents does specifically require an encroachment permit(s) from other public agencies, railroads, and/or utilities.

Contractor shall ensure that the insurance it obtains in accordance therewith complies with all requirements mandated by each permitting agency from whom permits shall be obtained for the Work and any other third parties from whom third party agreements are necessary to perform the Work (collectively, the "Third Party(ies)"). To the extent there is a conflict between the Third Party(ies)'s Insurance Requirements and those set forth by the City herein, the requirement(s) providing the more protective coverage for both the City and the Third Party(ies) shall control and be purchased and maintained by Contractor.

Contractor shall be responsible to determine what insurance requirements exist as a condition precedent to obtaining permit(s) for the Work, if any. Contractor shall be solely responsible for any delay(s) arising from its failure and/or its subcontractors' failure to timely obtain all required insurance.

All required third party insurance shall be submitted to the City at the same time Contractor submits all other contractually required insurance, which is no later than ten (10) days after Notice of Intent to Award, unless otherwise agreed to in writing by the City prior to this deadline.

H. Insurance During Guarantee Period - For all work the Contractor or its subcontractors perform during the guarantee period, workers compensation and commercial general liability insurance in the amounts and format required herein shall remain in force and be maintained for three (3) years after Final Completion of the Work.

The Contractor shall be responsible for paying any and all deductible costs for claims against its workers compensation and commercial general liability insurance.

13.02 GENERAL INDEMNIFICATION OBLIGATIONS
A. The Contractor shall indemnify, defend with counsel acceptable to City, and hold harmless to the full extent permitted by law, at the Contractor’s expense, the City, and their directors, elected officials, officers, officials, employees, agents, consultants, design engineers, Funding Agencies and each of them (collectively the “Indemnified Parties”), from and against any and all liability, loss, damage, claims, actions, causes of action, expenses and costs (including, without limitation, reasonable City staff attorney fees and outside attorney fees, and costs and fees of litigation) (collectively, “Liability”) of every nature to the extent caused by Contractor’s negligent performance of the Work under this Agreement or its failure to comply with any of its obligations contained in this Agreement, except that such obligation to defend and indemnify does not apply to the extent such Liability was caused by the active negligence, sole negligence or willful misconduct of the Indemnified Parties. Such indemnification by the Contractor shall include, but not be limited to, the following:

1. Liability or claims resulting directly or indirectly from the negligence or carelessness of the Contractor, its subcontractors, employees, or agents in the performance of the Work, or in

Page 301 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 90 City of Yuba City
General Conditions Municipal Well No. 3
guarding or maintaining the same, or from any improper materials, implements, or appliances used in its construction, or by or on account of any act or omission of the Contractor, its employees, or agents;

2. Liability or claims arising directly or indirectly from Contractor’s negligent acts that cause bodily injury, occupational sickness or disease, or death of the Contractor’s, or supplier’s own employees, or agents engaged in the Work resulting in actions brought against the Indemnified Parties;

3. Liability or claims arising directly or indirectly from or based on the violation of any laws or regulations, whether by the Contractor, its subcontractors, employees, or agents;

4. Liability or claims arising directly or indirectly from the negligent or legally unauthorized use or manufacture by the Contractor, its subcontractors, employees, or agents in the performance of this Agreement of any copyrighted or uncopyrighted composition, secret process, patented or unpatented invention, article, or appliance, unless otherwise specified stipulated in this Agreement.

5. Liability or claims arising directly or indirectly from the breach of any warranties, whether express or implied, made to the City or any other parties by the Contractor, its subcontractors, employees, or agents;

6. Liability or claims arising directly or indirectly from the willful misconduct of the Contractor, its subcontractors, employees, or agents;

7. Liability or claims arising directly or indirectly from any breach of the obligations assumed in this Agreement by the Contractor;

8. Liability or claims arising directly or indirectly from, relating to, or resulting from a hazardous condition created by the Contractor, subcontractors, suppliers, or any of their employees or agents due to Contractor’s negligence or breach of any obligation in this Agreement;

9. Liability or claims arising directly, or indirectly, or consequentially out of any action, legal or equitable, brought against the Indemnified Parties, their consultants, subconsultants, and the directors, officers, elected officials, employees, agents and volunteers of each or any of them, to the extent caused by the Contractor’s negligent or improper use of any premises acquired by permits, rights of way, or easements, the Site, or any land or area contiguous hereto or its performance of the Work thereon;

10. Liability arising directly or indirectly from exposure to hazards in violation of the California Labor Code that may be asserted by any person or entity, including, but not limited to, the Contractor, arising out of or in connection with the negligent activities of the Contractor, its agents, employees or privities pursuant to this Agreement, whether or not there is concurrent negligence on the part of the Indemnified Parties;

11. Liability or claims arising out of the Contractor's performance of the Work.

B. The Contractor shall reimburse the Indemnified Parties for all costs and expenses, (including but not limited to reasonable fees and charges of engineers, architects, attorneys, and other consultants and professionals and court costs of appeal) incurred by said Indemnified Parties arising out of or in enforcing the provisions of this article.

C. The indemnification obligation under this Article 13.02 shall not be limited in any way by any limitation on the amount or type of insurance carried by Contractor or by the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor or other person or organization under workers’ compensation acts, disability benefit acts, or other employee benefit acts.

D. Pursuant to California Public Contract Code Section 9201, City shall timely notify Contractor of receipt of any third-party claim relating to this Contract.

E. The Contractor’s obligations pursuant to this provision will survive the expiration or earlier termination of this Agreement.

F. The Contractor hereby agrees at its expense promptly to assume the defense of and to defend, with counsel acceptable to the City, against any indemnified Claim, suit or other proceeding brought thereon, and promptly to pay any and all costs, charges, attorney’s fees, and other expenses and any and all

Page 302 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 91 City of Yuba City
General Conditions Municipal Well No. 3
judgments that may be incurred against the City, and each elected officials, officers, representatives, agents, consultants, design engineers or employees, or any of them to the extent arising from any negligent act, error, or omission, or from any willful misconduct of the Contractor in the performance of the Contractor's obligations under this Agreement.

G. The only limitations on this provision shall be those imposed by Civil Code section 2782.

13.03 HAZARDOUS SUBSTANCE INDEMNIFICATIONS OBLIGATIONS
Neither the Contractor nor its subcontractors or suppliers shall use, generate, manufacture, store or dispose of on, under or about the Site, or transport to, from, along or across the Site, any flammable, explosive radioactive material, toxic substance, hazardous waste, hazardous material, hazardous substance, or the equivalent, as those terms may now or in the future be defined by common practice or by any federal, state or local statute, ordinance or regulation or any governmental body or agency (hereinafter “Hazardous Substance”).

A. Without limiting any remedies the City may have, in the event any disposal, release, discharge or spill of a Hazardous Substance or other contamination occurs within the Site at any time during, or as a result of, the Contractor’s use of the Site, except such spills or contamination to the extent directly caused by the sole negligence or willful misconduct of the City, its contractors, officers, representatives, agents, consultants, design engineers or employees, the Contractor shall immediately notify City and take all action to mitigate the effects of such disposal, release, discharge, spill or contamination. The Contractor shall at the Contractor’s own expense, unless otherwise directed by the City, remediate such disposal, release, discharge of spill or contamination in compliance with all applicable laws, rules and regulations. The City shall have the option to perform the remediation itself or through any contractor if the Contractor fails to do so. The Contractor shall cooperate with the City to complete the remediation and shall reimburse the City for all costs and expenses incurred in connection with the remediation.

B. In the event that the Contractor observes any material that the Contractor believes or has reason to believe may be a Hazardous Substance or encounters any unknown physical condition of any unusual nature within the Site, other than disposals, releases, discharges, spills or contamination covered in paragraph A, above, the Contractor shall, without disturbing the condition, immediately cease all use of the Site and notify the City. The City shall investigate the condition and take any clean-up or other remedial action City deems necessary in its sole discretion.

C. In the event the City or its contractor elects to perform remediation work, the Contractor shall upon notice from the City, cease use of the Site as directed in the notice. The City will notify the Contractor when the condition has been resolved, at which time, but not before, the Contractor may resume its use of the Site.

D. The Contractor agrees to assume liability for and to defend and hold harmless the Indemnified Parties from and against all injuries or death to any person and damage to any property, and all related expense, including without limitation attorneys’ fees, investigators’ fees, administrative charges, litigation expenses and any judgments, fines, penalties or other charges assessed against Indemnified Parties, resulting from the Contractor’s failure to comply with this article and any laws, rules or regulations concerning the subject matter hereof. The provisions of this article shall survive the expiration and termination of this Agreement.

The obligations and liabilities arising under the Article 13.03, HAZARDOUS SUBSTANCE INDEMNIFICATIONS OBLIGATIONS, shall be in addition to and independent of those obligations and/or liabilities arising under the other provisions of this Agreement and shall in no way limit, alter, reduce or eliminate the effect of such other provisions.

E.
**END ARTICLE 13**

Page 303 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 92 City of Yuba City
General Conditions Municipal Well No. 3
ARTICLE 14 - UNCOVERING AND CORRECTION WORK

14.01 GENERAL
A. The Contractor must notify the Construction Manager two (2) days prior to covering any Work.

B. If a portion of the Work is covered prior to Construction Manager’s review, it must, if requested in writing by the Construction Manager, be uncovered for Construction Manager observation and replaced at the Contractor's expense without change in the Contract Time.

14.02 CORRECTION OF WORK AND CORRECTIVE ACTION PLANS
A. The Contractor must promptly correct Work rejected by Construction Manager or Work failing to conform to the requirements of the Contract Documents, whether or not Fabricated, Installed or completed, even if such non-conforming Work was previously inspected or approved by the City or the Construction Manager. The Contractor bears the costs of correcting such rejected Work, including additional testing and inspections required, and compensation for City provided services and expenses made necessary thereby.

B. The Contractor may take one of two actions to remediate Work that does not conform to the Contract Documents:

1. Contractor may, at his own expense, remove defective Work and install Work that complies with the Contract Documents;

2. Contractor may develop and submit to Construction Manager, as a Submittal (not an RFI), a Corrective Action Plan (CAP). The CAP describes possible solution(s) to address the defective Work including “work-arounds” that would leave the defective Work in place. To facilitate the City’s review and possible acceptance of the CAP the Contractor may employ the services of a licensed Engineer or Architect to develop, sign and stamp the CAP for submission to the City.

Alternatively, the Contract may submit a CAP that is more general in description and substance and leave it to the Design Engineer to evaluate and develop a formal solution.

The Contractor shall compensate the Design Engineer for costs incurred via City issuance of a deductive change order to the Contract.

3. In the event the City determines that a practical solution is not available that would enable the defective Work to be left in place, then the Contractor must remove the defective Work and build per the Contract Documents.

C. Notwithstanding Section 00700-14.02.A, in the event of an Emergency constituting an immediate hazard to the health or safety of City’s employees, agents, representatives, property, or licensees, City may undertake, at the Contractor's expense and without prior notice, all work necessary to correct such hazardous condition(s) when it was caused by work of the Contractor not being in accordance with requirements of the Contract Documents.

D. The Contractor must remove from the Project Site portions of the Work that are not in accordance with the requirements of the Contract Documents, and are neither corrected by the Contractor nor accepted by the City.

E. If the Contractor fails to correct nonconforming Work, as per Section 00700-14.02.A, or fails to remove nonconforming work, as per Section 00700-14.02.C, City may correct or remove the nonconforming Work per Section 00700-14.02.E.

F. If the Contractor does not submit a Corrective Action Plan or proceed with correction or removal of nonconforming Work, within such time fixed by the Contract Documents or written notice from Construction Manager, the City may remove and store the salvable materials, articles and/or equipment at the Contractor's expense. If the Contractor does not pay all costs of such removal and storage within fourteen (14) Days after written notice, City may, upon fourteen (14) additional Days written notice, sell such materials articles and/or equipment at an auction or private sale, and shall account for the proceeds thereof, after deducting costs and damages that would have been borne by the Contractor, including compensation for City services and expenses made necessary thereby. If the proceeds of a sale do not cover all costs that the Contractor would have borne, the Contract Sum will be reduced by

Page 304 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 93 City of Yuba City
General Conditions Municipal Well No. 3
the deficiency. If payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor must pay the difference to City.

G. The Contractor bears the cost of correcting destroyed or damaged Work, which is caused by the Contractor’s correction, or removal of Work that is not in accordance with requirements of the Contract Documents, including work performed by City or separate contractors that is damaged or destroyed by the Contractor during the Contract Time or Guarantee period.

H. Nothing contained in this Section 00700-14.02, Correction of the Work and Correction Action Plans, establishes a period of limitation with respect to other obligations that the Contractor might have in the Contract Documents. Establishment of the Warranty/Guarantee period(s), as described in Section 00700-15.12, Warranties & Guarantees, relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with requirements of the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability with respect to the Contractor's obligations other than specifically to correct the Work.

14.03 ACCEPTANCE OF NONCONFORMING WORK
A. If City prefers to accept any or all of the Work that is not in accordance with requirements of the Contract Documents, City may do so instead of requiring its correction and/or removal, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not Final Payment to the Contractor has been made.
**END ARTICLE 14**

Page 305 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 94 City of Yuba City
General Conditions Municipal Well No. 3
ARTICLE 15 - FINAL COMPLETION AND ACCEPTANCE

15.01 USE BEFORE ACCEPTANCE
A. City has the right to utilize or place into service any item of equipment or other usable portion of the Work before Final Acceptance of the entire Project. Whenever City plans to exercise said right, City’s Representative will notify Contractor in writing, identifying the specific portion or portions of the Work to be so utilized or otherwise placed into service, hereinafter referred to as "Use Before Acceptance".

B. Until the City’s Representative issues such written notification, Contractor is responsible for all care and maintenance of all items or portions of the Work.

C. Upon City's issuance of written notice of Use Before Acceptance, City accepts responsibility for the protection and maintenance of all such items or portions of the Work described in the written notice, excepting any injury or damage resulting from Contractor's actions or negligence.

D. If, by reason of City’s Use Before Acceptance, the premium for the Contractor’s bodily injury and property damage insurance is increased, City will reimburse the Contractor for the additional amount necessarily incurred, allocable to the area and the period of City’s occupancy, up to the Date of Acceptance of the Work.

E. City’s Use Before Acceptance does not constitute Acceptance of the Work, or any portion of the Work, by City, nor will it relieve the Contractor of responsibility for correcting defective and/or Deficient Work or materials found at any time before Acceptance of the Work or during the Guarantee period after City’s Acceptance. However, when the Project includes separate buildings, and one or more of the buildings is entirely occupied by City, then upon written request by the Contractor and by written consent from City, the Guarantee period on the building entirely occupied by City will commence to run from the date of City occupancy of such building or buildings.

F. Notwithstanding any Use Before Acceptance, Contractor retains full responsibility for fulfillment of all the requirements of the Contract Documents.

G. Should the City elect to partially occupy or use portions of the Work prior to Acceptance, Contractor must perform final cleaning for those portions of the Work prior to their being so occupied or used.

15.02 CONTRACTOR’S RESPONSIBILITY TO MANAGE INCOMPLETE AND DEFICIENT WORK A. Pursuant to Section 01450, Quality Control and Inspection, the Contractor is responsible for identifying and managing Incomplete and Deficient work. Incomplete and Deficient work includes, but is not limited to: non-compliance items, re-work items, and non-conforming tests, pursuant to Section 01450; deficiencies relating to inspections by the Building Official if applicable to this Contract; and items of work not complete per the Contract Documents.

B. The Preliminary Final Inspection and Final Inspection will not be conducted until:

1. The entire Work of the Milestone/Project is complete;

2. Cleaning and waste management has occurred pursuant to the Contract Documents; and

3. Deficient Work identified in all outstanding non-compliance notices has been corrected.

C. For each completion Milestone, Contractor must include activities for conducting the Preliminary Final Inspection, completion of Punch-list, and Final Inspection, in Contractor’s Progress Schedule.

15.03 COMPLETION OF INTERMEDIATE MILESTONES
A. When the Construction Manager determines that all Work of a Milestone is complete, including cleaning, the Construction Manager must so certify to the City’s Representative and request a Preliminary Final Inspection, pursuant to Section 01450, Quality Control and Inspection.

B. If the Contract Documents include a Milestone for the completion of the entire Work of the Project, three (3) copies of the Milestone Completion certification must be submitted concurrently with the Contractor’s certification that all the Work of the Project is complete as required by Section 00700-

15.03.A.

Page 306 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 95 City of Yuba City
General Conditions Municipal Well No. 3

15.04 PRELIMINARY FINAL INSPECTION FOR INTERMEDIATE MILESTONE(S) A. Within seven (7) Days of receipt of Construction Manager’s certification that all Work of a Milestone is complete, City's Representative, Project Inspector, Architect of Record, and other staff, will conduct a Preliminary Final Inspection with the Construction Manager and the Project Superintendent.

B. If the City's Representative determines that, based on the results of the Preliminary Inspection, the Incomplete/Deficient work identified is greater in substance and/or volume, than can be appropriately declared as Punch-list, then the Work is not complete enough to complete the Preliminary Final Inspection. The Contractor will be so notified in writing. Contractor must complete the Work and reinitiate procedures for another Preliminary Final Inspection. Any costs to City for more than two (2) Preliminary Inspections may be charged to the Contractor.

C. If the results of the Preliminary Final Inspection are satisfactory to the City’s Representative, a Punchlist will be prepared and issued to the Contractor. Pursuant to Section 01450, Quality Control and Inspection, neither the City’s preparation of the Punch List, nor any omission from the Punch-list of items of Incomplete and/or Deficient Work, relieves the Contractor from completing all the Work required by the Contract Documents.

15.05 FINAL INSPECTION FOR INTERMEDIATE MILESTONE(S)
A. When the Punch-list generated from the Preliminary Final Inspection is complete the QC Manager must certify that the entire Work of the Milestone, including Punch-list, is complete. Upon delivery of such certification to the City’s Representative, and if the City’s Representative agrees with the Contractor’s certification, a Final Inspection will occur within ten (10) calendar days of the Contractor’s delivery of certification of final completion
B. If the City’s Representative determines the Work is deficient, Contractor will again be furnished with a Punch-list identifying the observed deficiencies in the Work. After all deficiencies have been corrected, Contractor must initiate procedures for another Final Inspection. If more than two (2) Final Inspections are required any costs to City for additional Final Inspections may be changed to the Contractor.

C. If the results of the Final Inspection are satisfactory, the City’s Representative will issue the Contractor a Milestone Completion letter.

D. Contractor’s Progress Schedule must include activities for Final Inspection of Milestones.

15.06 COMPLETION OF FINAL PROJECT MILESTONE
A. Pursuant to Section 01450, Quality Control and Inspection, the Contractor’s Quality Control Manager must certify that the final Milestone for the Work is complete. Completion of the Work of the Final Milestone includes, but is not limited to, submission to and acceptance by the City of all Milestone completion submittals. Section 01770, Contract Closeout, describes in greater detail the submittal requirements to achieve Milestone Completion. Additionally, all training (except previously-scheduled factory training) must be completed.

B. Conducting the Preliminary Final Inspection, and Final Inspection, of the Work required of the final Project Milestone, follows the requirements of paragraphs 15.04 and 15.05 above.

C. The Contractor’s QC Manager’s certification also includes the completion of all Punch-list work and the correction of all rework.

D. The Contractor must submit all documents required by Section 01770, Contract Closeout.

E. After acceptance of the Contractor’s QC Manager’s final certification, the City’s Representative will issue a Milestone Completion letter to the Contractor. This letter will establish the date of the Final Milestone Completion of the Work of the Project. The assessment of Liquidated Damages, if any, will cease accruing as of the date of Final Milestone Completion.

Page 307 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 96 City of Yuba City
General Conditions Municipal Well No. 3

15.07 RECOMMENDATION FOR ACCEPTANCE BY THE CITY ENGINEER A. After establishing Final Milestone Completion of the Work, the City’s Representative will recommend that the City Engineer formally accept the Work if the Contractor has satisfactorily:

1. Corrected all deficiencies observed during the Final Inspection and no new deficiencies have been observed;

2. Submitted required copies of As-Built Documents;

3. Submitted required Spare Parts;

4. Submitted copies of all documents required by Section 01770, Contract Closeout; and

5. Submitted all other required contract deliverables.

B. The Project Manager must submit the following Project Completion certification prior to City Engineer Acceptance of the Project:
“I certify that, to the best of my knowledge, all Work of the Project is Complete, including the fulfillment of all administrative requirements of the Contract. I request the City accept the Project as complete.”
Project Manager of the Contractor

15.08 ACCEPTANCE OF THE WORK
A. Acceptance of the Work will be made by the City Engineer, only after the City’s Representative has recommended Acceptance.

B. After the formal Acceptance of the Work, the City will record a Notice of Completion.

C. City's Acceptance establishes conformity with the Contract except for delays in completion, latent defects, fraud, or such gross errors as amount to fraud, willful misconduct, or gross negligence, and subject to any Guarantee and Warranty, express or implied.

D. Determinations by City’s Representative that the Work is complete or Acceptance of the Work by the City Engineer, does not bar any action by the City against the Contractor pursuant to Section 00700-

15.12, Warranties & Guarantees.

15.09 FINAL PAYMENT – SEE ARTICLE 10.09- FINAL INSPECTION AND PAYMENT

15.10 CONTRACTOR’S DUTIES AND RESPONSIBILITIES AFTER ACCEPTANCE A. After Acceptance of the Work, Contractor is relieved of the duty of maintaining and protecting the entire Work, and Contractor is not required to perform any further Work thereon, except as otherwise required by law or the Contract Documents.

B. Contractor is relieved of responsibility for injury to persons or property or damage to the Work that occurs after City's Acceptance, provided that such injury/damage is not in any way caused by Contractor.

C. City's Acceptance does not relieve Contractor of responsibility for faulty materials or workmanship or of complying with the requirements of Warranties and Guarantees.

15.11 RETENTION PROCEEDS, WITHHOLDING AND DISBURSEMENT
A. Pursuant to California Public Contract Code §7107, within sixty (60) Days after the date of “completion” of the Work, the retention withheld by City shall be released, subject to all withholds required and authorized by law including Stop Notice claims and Liquidated Damages (pursuant to California Government Code §53069.85). In the event of a Dispute between City and Contractor, City may withhold from the Final Payment an amount not to exceed one hundred fifty percent (150%) of the disputed amount.

Page 308 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 97 City of Yuba City
General Conditions Municipal Well No. 3
B. For purposes of release of retention, "completion" means any of the following:

1. The Acceptance by City of the Work.

2. After the commencement of Work, a cessation of labor on the Work for a continuous period of one-hundred (100) Days or more, due to factors beyond Contractor's control.

3. After the commencement of Work, a cessation of labor on the Work for a continuous period of thirty (30) Days or more, if City records a Notice Of Cessation or a Notice Of Completion with the County Recorder.

C. Subject to Section 00700-15.11.D below, within seven (7) Days from the time that all or any portion of the retention proceeds are received by Contractor, Contractor must pay each of its Subcontractors from whom retention has been withheld, each Subcontractor's share of the retention received. However, if a retention payment received by Contractor is specifically designated for a particular Subcontractor, payment of the retention shall be made to the designated Subcontractor, if the payment is consistent with the terms of the Subcontract. (California Public Contract Code §7107(d)) D. Contractor may withhold from a Subcontractor its portion of the retention proceeds if a bona fide dispute exists between the Subcontractor and Contractor. The amount withheld from the retention payment shall not exceed one hundred fifty percent (150%) of the estimated value of the disputed amount.

E. In the event that retention payments are not made within the time periods required by California Public Contract Code (PCC) §7107, the City or Contractor withholding the unpaid amounts shall be subject to a charge of two percent (2%) percent per month on the improperly withheld amount, in lieu of any interest otherwise due. Additionally, in any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to attorney's fees and costs. (PCC §7107)

15.12 WARRANTY & GUARANTEES
A. Neither the final Acceptance, nor payment, nor any provision in the Contract Documents relieves Contractor of responsibility for faulty materials or workmanship.

B. Contractor must guarantee all workmanship and materials for a period of one year, or as specified in the technical sections of the Contract Documents (specifications), from and after the Date of Acceptance of the Work by the City’s Director of Public Works.

C. Contractor may also be required to furnish a written Guarantee covering all or certain items of Work for longer periods of time from the Date of Acceptance of the Contract. The Work to be Guaranteed, the form, and the time limit of the Guarantee will be specified in the Contract Documents. Said Guarantee must be signed and submitted to City before Acceptance of the Work.

D. The Warranty/Guarantee period begins at the Date of Acceptance of the Work by the City Engineer.

E. In addition to any other warranties in this contract, the Contractor warrants, except as provided in Paragraph J of this clause, that work performed under this Contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

F. This Warranty shall continue for a period of one year from the date of final acceptance of the work by the City Engineer. If, pursuant to Section 00700-15.01 above, City takes possession of any part of the work before final acceptance, this Warranty shall continue for a period of 1 year from the date the City takes possession the specific Work identified pursuant to 15.01.

G. The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to City-owned or controlled real or personal property, when that damage is the result of:

1. The Contractor’s failure to conform to contract requirements; or

2. Any defect of equipment, material, workmanship, or design furnished.

H. The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s Warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

Page 309 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 98 City of Yuba City
General Conditions Municipal Well No. 3
I. With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall—

1. Obtain all warranties that would be given in normal commercial practice;

2. Require all warranties to be executed, in writing, for the benefit of the City, if directed by the City’s Representative; and

3. Enforce all warranties for the benefit of the City, if directed by the City’s Representative.

J. Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the City nor for the repair of any damage that results from any defect in City-furnished material or design.

K. This Warranty shall not limit the City’s rights under the Milestone Completion and City Engineer acceptance paragraphs of this Contract with respect to latent defects, gross mistakes, or fraud.

L. Contractor must repair or replace all defective Work, together with any other Work affected by the repair or replacement during said Guarantee period without expense whatsoever to City.

M. The aforesaid one-year Warranty/Guarantee period does not in any way limit or waive City's rights to legal recourse for latent construction defects, pursuant to California Civil Code of Procedure §337.15 nor for patent construction defects pursuant to §337.1.

N. Approximately fifteen (15) Days before completion of the entire Work of the Project, Contractor must meet with City regarding Warranty/Guarantee requirements. City will establish communication procedures for notifying Contractor of Warranty defects, priorities regarding the type of defect, time required for Contractor response, and other details deemed necessary by City for execution of the Warranty/Guarantee.

O. If the Contractor fails to remedy any failure, defect, or damage, within five (5) calendar days of City’s notice, or commence to remedy and proceed with due diligence when the repair cannot be completed within five (5) days, the City may replace, repair or otherwise remedy the failure, defect or damage at the Contractor’s expense.
**END ARTICLE 15**

Page 310 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 99 City of Yuba City
General Conditions Municipal Well No. 3
ARTICLE 16 - MISCELLANEOUS PROVISIONS

16.01 CONTRACTOR’S USE OF COMPUTER SOFTWARE
A. Contractor certifies that it has appropriate systems and controls in place to ensure that City funds will not be used in the performance of this Contract for the acquisition, operation or maintenance of computer software in violation of copyright laws.

16.02 RIGHTS IN LAND AND IMPROVEMENTS
A. Nothing in the Contract shall be construed as allowing Contractor to make any arrangements with any person to permit occupancy or use of any land, structure, or building within the physical limits of the Project for any purpose whatsoever, either with or without compensation, nor act in conflict with any agreement between City and any owner, former owner, or tenant of such land, structure, or building.

B. Contractor must not occupy City's property outside the Project limits as shown on the Plans or on maps available in City's offices, unless Contractor enters into a written agreement with City. **END ARTICLE 16**
**END OF SECTION 00700**

Page 311 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00700 - 100 City of Yuba City
General Conditions Municipal Well No. 3
(THIS PAGE LEFT BLANK INTENTIONALLY)

Page 312 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00800 - 1 City of Yuba City
Supplementary General Conditions Municipal Well No. 3
SECTION 00800

SUPPLEMENTARY GENERAL CONDITIONS
DELAYS

1.1 Damages for Delays Allowed for Completion
In accordance with the provisions of Section 00700-8.02, Contract Time, the following substantial completion and final completion contract times shall be completed within the number of consecutive calendar days from the date established in the Notice to Proceed for the commencement of Contract Time:

Contractual Completion Event
Completion Time
(# of calendar days from
Notice to Proceed date)
Substantial Completion 120 Days
Final Completion 140 Days

1.2 Damages for Delays
In accordance with the provisions of Section 00700-6.5, Liquidated Damages, for the period of time that any portion of the Work remains unfinished after the time fixed for an interim milestone and/or Substantial Completion in Section 00800-1.1, Time Allowed for Completion, as modified by extensions of time granted by the Owner, it is understood and agreed by the Contractor and the Owner that the Contractor shall pay the Owner the damages listed below.

Contractual Completion Event
Daily
Liquidated Damages
Substantial Completion $750
Final Completion $500
In accordance with the provisions of Section 00700-8.03.C.1.b, Weather Delays, an allowance of three (3) working days of weather caused delay have been included in the time allowed for completion. This allowance represents a reasonable assessment of anticipated lost working days based on historical weather patterns. These weather days shall be included in the Contractor’s schedule as specified in Section 01324-1.09, WEATHER CONDITIONS AND WEATHER DAY ALLOWANCE.

OTHER DAMAGES

2.1 Public Hardship or Negative Impact
A. Work Hours
Maintaining or running equipment outside the permitted hours.

First occurrence Warning
Second occurrence $ 500
Third and subsequent occurrences $1,000
B. Site Cleanliness
Failure to maintain the cleanliness of the construction site.

First Occurrence Warning
Second Occurrence $ 500
Third and subsequent Occurrences $1,000

Page 313 of 519 ends

CONTRACTING REQUIREMENTS
December 2024 00800 - 2 City of Yuba City
Supplementary General Conditions Municipal Well No. 3
C. Maintenance of Temporary Pavement:

Failure to maintain temporary paving as required by the affected pavement owner.

First Occurrence Warning
Second Occurrence $ 500
Third and Subsequent Occurrences $1,000
D. Right-of-Way Restrictions:

Failure to comply with right-of-way restrictions (see Section 01734).

First Occurrence Warning
Second Occurrence $ 500
Third and Subsequent Occurrences $1,000
E. Tree Protection:

Failure to comply with all tree and root protection requirements (see Section 01560-1.19).

First Occurrence Warning
Second Occurrence $ 1,000
Third and Subsequent Occurrences $ 2,000

END OF SECTION

Page 314 of 519 ends

December 2023 01170 - 1 City of Yuba City
Novel Corona Virus (COVID-19) Safety Requirements Municipal Well 3 SECTION 01170
NOVEL CORONA VIRUS (COVID-19) SAFETY REQUIREMENTS

GENERAL

1.01 SECTION INCLUDES
A. COVID-19 safety requirements in response to the need for work on essential construction projects that are permissible under the Sutter County Health Services COVID-19 Safety Orders and applicable State and Federal guidelines/orders, to continue as safely as possible.

B. These COVID-19 safety requirements are not all encompassing and may need to be modified by the Contractor to individual construction tasks and updated as the COVID-19 pandemic evolves.

C. The Contractor and all its sub-tier level subcontractors and suppliers shall account in their Bid and sub-bids for all cost impacts whether affecting labor (including, but not limited to obtaining qualified workers, quantity of workers, as well as their productivity), deliveries, supervision, testing and/or procurement of materials and/or equipment and time caused by COVID-19 safety requirements found in this Section 01170 and also all public health and/or governmental directives in place at the time Bids are received by the City for this Project.

1.02 COVID-19 EXPOSURE PREVENTION, PREPAREDNESS, AND RESPONSE PLAN A. Contractor’s Responsibility:

1. Prepare a COVID-19 Exposure Prevention, Preparedness and Response Plan specific to this Project that describes how to prevent worker exposure to coronavirus, protective measures to be taken on the jobsite, personal protective equipment and work practice controls to be used, cleaning and disinfecting procedures, and what to do if a worker(s) shows symptoms of COVID-19 illness or tests positive for COVID-19. The Contractor should review the latest OSHA COVID-19 Workplace Safety Guidance document (https://www.osha.gov/Publications/OSHA3990.pdf ) as a resource in preparation of their Site Specific Health and Safety Plan. Other reliable and current sources of COVID-19 information can be found at:
a. California Department of Public Health (CDPH, State):
https://www.cdph.ca.gov/Programs/CID/DCDC/Pages/Immunization/nCOV2019.aspx b. Centers for Disease Control and Prevention (CDC, National):
http://www.cdc.gov/coronavirus/novel-coronavirus-2019.html.

2. This plan shall, at a minimum, address the following COVID-19 safety guidelines:
a. COVID-19 Employee and Visitor training and check-list before entering worksite. b. Employee distancing and strategies to maximize distancing when possible. c. Limitations on gathering size.
d. Personal Protective Equipment (PPE) requirements.
e. Identify “choke points” and “high risk areas” such as hallways, hoists and elevators, break areas and vehicles.
f. Stagger trades and modify work schedules to reduce worker density to maximize distancing opportunities.
g. COVID-19 employee good personal hygiene measures.
h. Disinfecting and cleaning requirements.
i. Personal prevention actions requirements for all employees. j. Toolbox and Tailgate COVID-19 employee training.
k. Recognizing COVID-19 Symptoms.

Page 315 of 519 ends

December 2023 01170 - 2 City of Yuba City
Novel Corona Virus (COVID-19) Safety Requirements Municipal Well 3 l. Establish a COVID-19 Exposure Action and Notification Plan. m. Establish daily screening protocols for arriving workers and visitors to ensure potentially infected workers and visitors do not enter the Site. n. Maintain daily attendance log of all workers and visitors who enter the Site.

3. Also, as part of this Plan, the Contractor shall draft and implement a COVID-19 Code of Safe Practices that is posted in areas visible to all employees and visitors.

4. The Contractor shall be prepared at each Progress and Coordination Meeting, if requested by the Construction Manager, to provide information relevant to the application, enforcement and implementation of such COVID-19 Safe Practices.

5. All Contractor managers and supervisors (from forepersons to project managers) must be familiar with this Plan and be ready to answer questions from employees, subcontractors, suppliers and visitors. Managers and supervisors must set a good example by following this Plan at all times. This involves practicing good personal hygiene and jobsite safety practices to prevent the spread of the virus. Managers and supervisors must encourage this same behavior from all employees, subcontractors, suppliers and visitors.

6. The Contractor shall immediately notify the Construction Manager if any person under the Contractor’s control on this Project has tested positive for COVID-19.

1.03 SUBMITTALS
A. The following information shall be provided in accordance with Section 01330, Submittal Procedures, after the Award of Contract and before any work begins at the Site:

1. COVID-19 Exposure Prevention, Preparedness and Response Plan.

2. COVID-19 Code of Safe Practices.

B. To the extent that there are material amendments or modifications made to any of the above plans or practices during the performance of the Work, the Contractor shall provide to the Owner as soon as practicable the amendments and shall post them as part of the notification plan to all employees and visitors who enter the Site.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION

Page 316 of 519 ends

December 2024 01312 - 1 City of Yuba City
Project Meetings Municipal Well 3
SECTION 01312

PROJECT MEETINGS

GENERAL

1.01 SECTION INCLUDES
A. Requirements for calling for and conducting meetings for the Work.

1.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section:

1. Section 01324 – Progress Schedules and Reports.

1.03 GENERAL
A. Project meetings and conferences are an important administration and communication requirement of all project participants. Meetings will be conducted throughout the course of the construction to address issues related to the Work, review and coordinate progress of the Work, and to discuss other matters of common interest to project participants.

B. Meeting and conference locations and qualified participants will be determined by the Construction Manager, Engineer and the Contractor based on the meeting agenda topics.

C. The Construction Manager may change in-person meetings to virtual on-line meetings. The virtual meeting platform used by the Construction Manager will accommodate video, audio and screen sharing by using providers such as MS TEAMS and Zoom. When the Construction Manager hosts such virtual meetings, it is required that all attendees turn on video camera for better interaction among meeting participants.

1.04 PRECONSTRUCTION CONFERENCE
A. Prior to the start of construction, the Construction Manager will schedule a meeting of the Contractor, Engineer, Owner, and their respective representatives. The general purpose of the meeting will be to establish working relationships, begin coordination of construction matters, discuss the Work, and to review the pertinent features of the Contract. The duration of the preconstruction conference will take approximately 4 hours.

B. The agenda for the meeting will cover at least the following items, a more detailed agenda will be distributed at the meeting:

1. Organization of the Contractor's forces and personnel, including subcontractors and materials suppliers.

2. Lines of authority and channels and procedures for communication.

3. Contractor’s construction schedule, including sequence of critical work.

4. Processing of shop drawings and other data that will be submitted to Owner for review.

5. Processing of change order requests and monthly applications for payment.

6. Procedures for quality control, housekeeping and related matters.

C. Contractor should be prepared to discuss the following topics:

1. Preliminary construction schedule and critical path.

2. Schedule of submittals and submittals needing short turn-around times.

3. Schedule of Values for construction payments.

4. Critical work sequencing.

Page 317 of 519 ends

December 2024 01312 - 2 City of Yuba City
Project Meetings Municipal Well 3

5. Plans for mobilization, arrangement and use of staging and storage areas, use of site, location and arrangement of field offices, and site security.

D. Minutes of Meeting:

1. The Construction Manager will compile minutes of the meeting and distribute copies to all participants.

1.05 PROGRESS MEETINGS
A. Unless otherwise arranged, there will be a weekly progress meeting at a time and at an on-site location that is mutually agreed upon between the Contractor, Construction Manager, Engineer, and Owner:

1. Meetings are to enable orderly project review during the progress of work.

2. Construction Manager, Engineer, Owner, Contractor’s Superintendent, representatives of subcontractors, suppliers’ representatives as may be needed, other Contractors working at the site, and other parties shall attend these meetings.

3. Construction Manager will preside over the meeting and will compile and distribute minutes of the meeting.

B. The purpose of the weekly meetings is to coordinate the efforts of all concerned to result in smooth and coordinated progress towards completion of the overall project.

C. Contractor shall bring to each weekly meeting the updated 2-week “look ahead” schedule.

D. The Contractor will be required to address the following items at the weekly meeting:

1. Work completed last week.

2. Work anticipated next week.

3. Log of submittals and Requests for Information.

4. Contract document deficiencies or questions noted during prior week.

5. Schedule status and corrective measures and procedures that are planned to place the project back on schedule, if such action is necessary.

6. Report of any accidents, and any site safety issues that need to be addressed.

E. Other agenda items to be discussed include:

1. Review and revise as necessary and approve minutes of previous meetings.

2. Status of Requests for Information, Change Order Requests, submittals and shop drawings.

3. Identify problems that impede planned progress.

4. Other current business pertaining to the Work.

F. Revision of Minutes:

1. Unless published minutes are challenged in writing prior to the next regularly scheduled progress meeting, they will be accepted as properly stating the activities and decisions of the meeting.

2. Persons challenging published minutes shall reproduce and distribute copies of the challenge to all indicated recipients of the particular set of minutes.

3. Challenge to minutes shall be settled as priority item of "old business" at the next regularly scheduled meeting.

Page 318 of 519 ends

December 2024 01312 - 3 City of Yuba City
Project Meetings Municipal Well 3

1.06 PROGRESS SCHEDULE AND PROGRESS BILLING MEETINGS
A. Once each month, a progress schedule and progress payment meeting will be conducted with the Construction Manager. The purpose of this meeting is to review the Progress Payment Estimate and reach agreement on the extent of the Work completed during the pay period.

B. The meeting date will be scheduled in accordance with the Owner’s deadline for submittal of Progress Pay Estimate.

C. The updated progress schedule will also be reviewed at this meeting as described in Section 01324. Schedule impacts, time extension requests, actual and anticipated schedule activity sequence/duration changes, delays, and other schedule-related topics will be discussed.

D. The Construction Manager may require more frequent progress schedule meetings should there be schedule revisions that necessitate such a meeting.

1.07 SUBMITTAL MEETINGS
A. When required in the individual technical specification, or if requested by the Contractor, Construction Manager, or the Engineer, a meeting regarding a required submittal will be held to facilitate the timeliness of the submittal preparation and review process.

1.08 QUALITY ASSURANCE MEETINGS
A. The Contractor or the Engineer may request a meeting prior to the start of a particular phase of the project to discuss how the Work shall be accomplished in accordance with the quality requirements of the Contract Documents, Codes, permits and industry standards. Quality assurance inspections and tests that are applicable to the Work will be discussed.

1.09 SPECIAL MEETINGS
A. Any time during progress of the Work, the Owner and the Construction Manager shall have the authority to require the Contractor and any subcontractor, suppliers, or service providers to attend job-site conferences on matters which require immediate or special attention. Any notice of such conference shall be duly observed and complied with by the Contractor and subcontractors, suppliers, or service providers without extra cost to Owner.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION

Page 319 of 519 ends

December 2024 01312 - 4 City of Yuba City
Project Meetings Municipal Well 3
(THIS PAGE LEFT BLANK INTENTIONALLY)

Page 320 of 519 ends

December 2024 01324 - 1 City of Yuba City
Progress Schedules and Reports Municipal Well 3
SECTION 01324

PROGRESS SCHEDULES AND REPORTS

GENERAL

1.01 SECTION INCLUDES
A. Progress Scheduling and reporting requirements.

1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section:

1. Section 00510 – Agreement

2. Section 00700 – General Conditions

1.03 SUMMARY
A. The Progress Schedule for this Project will also be referred to as the Critical Path Method (CPM) Schedule. A CPM network schedule is a graphical depiction of the Contractor’s construction plan, showing the sequential activities necessary to complete the Work within the specified contract times and constraints. The CPM network schedule for this project shall depict events and tasks as activities, showing their interrelationships, and shall identify the progress required for each activity before subsequent activities can start. Activities shall be logically presented in a network showing the activities' interrelationships chronologically. Because each activity has an assigned duration, the completed network shall show the critical path of activities that must be completed on time to ensure timely project completion. The earliest and latest start and finish times for each activity shall also be shown. The CPM network shall be comprehensive and shall include all interdependencies and interactions required to perform the Work.

B. The construction schedules and accompanying reports outlined in this section are important to the City as they budget, plan and administer the project. The City, Construction Manager and/or Engineer will regularly analyze the most current progress schedule during construction to monitor progress status of the project relative to contract times. The Schedule Updates and Weekly Schedules will be an agenda item at all project coordination meetings as project participants work together in prioritizing their respective tasks and action items to efficiently perform their duties.

C. The Time Impact Analyses are very important submittals to the Construction Manager and City as they evaluate activity durations and the relationships between activities before deciding on possible changes to the contract time and/or viable options to mitigate time impacts.

D. By submitting a bid for this Project, the Contractor represents to the City that Contractor will have included all costs within its Total Bid Price to fully comply with all scheduling and reporting requirements hereinafter prescribed in this Section.

1.04 RESPONSIBLE SCHEDULING PERSON
A. The Contractor shall designate, in writing within five (5) calendar days after Notice of Award the person responsible for preparation, maintenance, updating and revision of all schedules required in this Section.

B. The qualifications of this Responsible Scheduling Person shall include:

1. Capable of understanding this project scheduling specification and producing a schedule and reports to the standards defined in this specification.

Page 321 of 519 ends

December 2024 01324 - 2 City of Yuba City
Progress Schedules and Reports Municipal Well 3

2. Five (5) years verifiable experience in preparation of construction schedules for projects of similar value, size and complexity.

3. Must be very proficient in the use of CPM scheduling utilizing Oracle Primavera Professional Project Manager (P6) PPM scheduling software or MS Project 2016 or later version.

C. The Contractor shall provide references of three (3) project Owners or Construction Managers who have personal experience with this scheduler on previous projects. References shall include current contact information (telephone and/or email) for Construction Manager to verify the qualifications of the proposed responsible scheduling person.

D. Contractor’s Responsible Scheduling Person shall be available on-site as needed and have authority to act on behalf of the Contractor. All scheduling software and hardware shall be located on-site. Scheduler shall attend project meetings as called for by the Construction Manager for proper explanation of all schedule updates.

E. In the event the Contractor does not have an employee with the required scheduling qualifications, as determined by the Construction Manager, the Contractor will be required to employ a qualified CPM scheduling consultant who regularly performs these services and who in the opinion of the Construction Manager possesses the required scheduling qualifications and availability to perform the CPM scheduling for this Project.

F. Construction Manager reserves the right to remove scheduler from the project if found to be incompetent.

1.05 SCHEDULING FORMAT AND SOFTWARE
A. Schedule Format: Utilize critical path method (CPM) format utilizing Precedence Diagramming Method.

B. Prepare computerized schedules utilizing Oracle Primavera Professional Project Manager (P6) PPM scheduling software compatible with Windows 8 or later version or Microsoft Project Professional 2016 or later version compatible with Windows 8 or later version.

1.06 PRECONSTRUCTION SCHEDULING MEETING AND PREPARATION A. The Construction Manager will conduct a Preconstruction Scheduling Meeting with Contractor’s Project Manager and Responsible Scheduling Person within seven days (7) calendar days after approval of the Contractor’s designated Scheduler. This meeting is separate from the Preconstruction Conference Meeting and is intended to only cover schedule requirements for this project. These requirements would include formatting, color coding, activity detail, coding structure, calendar requirements, reporting requirements, updates, revisions, and schedule delay analysis.

B. Contractor shall present their schedule methodology, planned sequence of operations and proposed activity coding structure.

1. The coding structure shall, at a minimum, include code fields for Project Segment or Phase, Area of Work, Type of Work, Submittal/Procurement/Construction and Responsibilities (this would include all subcontractors).

2. The activity code structure shall be sufficient to allow future sorting and/or grouping by responsibility or subcontractor, area/location, CSI division, milestones and change orders.

This will allow the “rollup” of the activities in the form of a Summary Schedule.

C. During preparation of the Preliminary and Baseline Schedules, the Construction Manager will facilitate Contractor's efforts by being available to answer questions regarding sequencing issues, scheduling constraints, interface points, and dependency relationships.

Page 322 of 519 ends

December 2024 01324 - 3 City of Yuba City
Progress Schedules and Reports Municipal Well 3

1.07 BASELINE SCHEDULE
A. Baseline Schedule Submittal:

1. The Contractor shall submit an acceptable Critical Path Method (CPM) Baseline Schedule to the Construction Manager within thirty-five (35) days after the receipt of the Notice to Proceed for all Work of the Project. Subsequent revisions to Baseline Schedule shall be submitted as set forth hereinafter.

2. The Contractor shall produce and provide four (4) complete set each of time-scaled network logic diagrams and bar charts in color on 11-inch by 17- inch sheets and one electronic copy on a CD with data in native file format. The network logic diagram shall be clear and legible. Critical activities shall be indicated in red color on both schedules.

3. The Contractor shall include with the Baseline Schedule Submittal a signed statement from each Subcontractor listed on the Contractor’s Section 00430, DESIGNATION OF SUBCONTRACTORS, which confirms they have evaluated the Contractor’s Baseline Schedule and agree that the Baseline Schedule accurately depicts the quantity, logic and durations for all activities assigned to their company.

4. The Construction Manager will review the schedule and provide any comments, its favorable review of the schedule, or request a meeting to review the schedule with the Contractor within fifteen (15) days of receipt of the schedule. If requested, the Contractor shall participate in a review and evaluation of the proposed network diagrams and analysis by the Construction Manager. Any revisions necessary as a result of this review shall be resubmitted for review by the Construction Manager within ten (10) days. When completed, the favorably reviewed schedule shall then be the schedule to be used by the Contractor for planning, organizing, and directing the work, and for reporting progress. If the Contractor thereafter desires to make significant changes in its method of operating and scheduling, the Contractor shall notify the Construction Manager in writing stating the reasons for the change.

5. No more than two (2) progress payments will be made prior to submission and acceptance of the CPM Baseline Schedule by the Construction Manager.

6. Failure to include an activity required for execution of the Work does not excuse Contractor from completing the Work and portions thereof within specified contract times and contract price. Failure of Contractor to include required schedule constraints, sequences or milestones in schedule shall not relieve Contractor of obligation to conform to requirements of Contract. Acceptance of schedule shall not waive Contract requirements. In event of conflict between accepted schedule and Contract requirements, terms of Contract shall govern at all times, unless requirements are waived in writing by the City.

7. Contractor shall not unilaterally change the accepted Baseline Schedule without the prior written notification to and acceptance and consent of the Construction Manager, excepting only the reporting of Actual Start, Actual Finish, and Activity Progress. The accepted Baseline Schedule shall be used for comparison with the current updated schedule, and possible revised schedules, during the Contract.

B. Baseline Schedule Requirements:

1. Prepare schedule utilizing Precedence Diagramming Method.

2. The Contractor’s proposed CPM Baseline Schedule and all updates or revisions thereto, shall meet the following requirements:

3. Schedule and Project Completion- The Baseline Schedule and all updates or revisions shall show completion of the project within the required contract times and constraints on the Work. Failure to do so may result in the City terminating for cause under Section 00700, General Conditions 8.10, City’s Right to Terminate Contract.

Page 323 of 519 ends

December 2024 01324 - 4 City of Yuba City
Progress Schedules and Reports Municipal Well 3

4. If the Contractor’s schedule is based on less time than the maximum time allowed for milestone(s) or Contract completion no compensation for extended overhead expenses will be considered until the expiration of the entire time periods provided for in the Contract as adjusted by any time extensions granted other than compensable time extensions.

5. Acceptance of the Contractor’s Base CPM Schedule, monthly updates or revised schedule, when based on less time than the maximum time allowed for milestone(s) or Contract completion does not serve to change any Contract duration, nor serve as a waiver of the Contractor’s nor the City’s right to utilize the full amount of time specified in the Contract, unless so modified in a Contract Change Order.

6. Prepare schedule utilizing activity durations in terms of working days. Do not exceed fifteen (15) working day duration on activities except concrete curing, submittal review, and equipment fabrication and deliveries. Where duration of continuous work exceeds fifteen (15) working days, subdivide activities by location, stationing, or other sub-element of the Work. Coordinate holidays and Furlough calendars to be observed with the City and incorporate them into the schedule as non-working days.

7. Schedule Logic: Schedule shall be assembled to show order in which Contractor proposes to carry out Work, indicate restrictions of access, availability of Work areas, and availability and use of manpower, materials and equipment. The Contractor shall indicate all dependencies and logic between activities so that it may be established what effect the progress of any one activity has on the schedule. The following criteria shall form basis for assembly of schedule logic:
a. Which activities must be completed before subsequent activities can be started? b. Which activities can be performed concurrently?
c. Which activities must be started immediately following completed activities? d. What major facility, equipment or manpower restrictions are required for sequencing these activities?

8. Resource Loading and Leveling: The CPM Schedule shall not incorporate resource loading and leveling. The Contractor shall provide hard coded logic constraints as necessary to incorporate any resource requirements that may be applicable to the Project construction.

The Contractor shall determine and allocate the proper resources to complete the Project by the specified Contract completion date.

9. Network Activities- The selection and number of detailed network activities shall be subject to favorable review by the Construction Manager and shall meet the following requirements:
a. All Work activities should be of sufficient detail to ensure adequate planning and execution of the Work and such that schedules provide an appropriate basis for monitoring and evaluating the progress of the Work. A work activity is defined as a single task that requires time and resources (manpower, equipment and/or material) to complete in a continuous operation, excluding submittal activities, review/acceptance activities, and fabrication/procurement activities. Durations for on-site work activities shall be in working days and shall not exceed ten (10) workdays. Passive on-site activities such as curing and testing periods can be in calendar days if desired by Contractor. All such passive on-site activities shall be included in the Contractor’s schedule and durations should be as specified in the Contract Documents. b. The submittal and approval of samples and equipment, fabrication of special material and equipment and their installation and testing. Should the Contractor expect multiple submittals and deliveries for materials or equipment from the same supplier, the Contractor shall show each planned submittal and delivery and the logic to the respective on-site Work activity(s).
c. The critical path shall be shown on all reports and on the graphic network logic diagram. The activities which constitute the critical path shall be identified.

Page 324 of 519 ends

December 2024 01324 - 5 City of Yuba City
Progress Schedules and Reports Municipal Well 3
d. Progress milestone events or other significant stages of completion, as defined in Section 00510, Agreement, Article 4 – Contract Times. System shutdown and tie-in dates must be identified and included in the schedule.
e. The lead time required for testing, inspection and other procedures required prior to acceptance of the work. All witnessed factory tests shall be shown as individual activities.
f. The activity numbers shall be grouped by responsibility, phases, milestones, work area, trade and subcontractor to provide logical summary activities. g. All activities of the City and the Construction Manager that affect progress along with required contract dates for completion of all parts of the work. h. All activities of utilities, regulatory agencies and permitting agencies. i. All mobilization and demobilization activities, including temporary controls. j. Schedule shall show all hydraulic testing of structures, pipe testing, field testing, training and demonstration periods as required. Field testing and training activities should be broken down to reflect all individual system and equipment components. k. Float shall not be an activity unless approved by the Construction Manager.

10. Network Logic Diagram- The graphic network diagram shall include for each activity, the description, activity number, the estimated duration in workdays, and all activity relationship lines. The network diagram shall be drawn for the early start and early finish of all activities.

The diagrams shall show elements of the project in detail and an entire project summary.

Diagrams shall show the order and interdependence of all activities and sequence in which the work is to be accomplished as planned by the Contractor and its subcontractors. The basic concept of a network analysis diagram shall be followed to show how the start of a given activity is dependent on the completion of preceding activities and its completion restricts the start of following activities. The Primavera layout of the network logic diagrams shall be time-scaled and show the following as a minimum:
a. Activity numbers and description.
b. Activity duration and total float.
c. Critical path, highlighted in red color.
d. Relationships between activities and lag times, if any. e. Start, completion and milestone dates.

11. Float:
a. “Total Float" or “Float” shall be defined as the difference between the early finish and late finish dates for an activity. On the CPM Schedule delineate the specified Contract duration and identify the planned completion of the Work as the final finish milestone.

The time period between these two dates, if any, shall be considered float. Float in any activity, milestone completion date or Contract completion date shall be considered a resource available to both the City and the Contractor. Neither the City nor the Contractor has ownership of the float.
b. The parties agree that float, as properly shown on the baseline schedule and all updates thereto, is not for the exclusive benefit of either party. Consequently, either party may, without liability to the other for actual or liquidated damages for delay, delay a schedule activity provided that such delay shall not cause the float of the affected activity to become negative. If the float of the activity is already negative, as shown on the most recent schedule update, either party may delay such activity, without liability to the other for actual or liquidated damages for delay, provided that such delay shall not cause the negative float of the delayed activity to exceed the negative float of all other schedule activities. If the project has interim milestones with separate liquidated damages, only delays by the City to the Project Critical Path shall potentially entitle the Contractor to extended overhead costs and only subject to the limitations of General Conditions 8.04, Time Extensions.

Page 325 of 519 ends

December 2024 01324 - 6 City of Yuba City
Progress Schedules and Reports Municipal Well 3
c. Pursuant to these float sharing requirements, use of float suppression techniques such as preferential sequencing or logic, special lead or lag logic restraints, extended activity duration’s or imposed dates shall be cause for rejection of any schedule submittal.

12. City-furnished Equipment or Materials (If Applicable):
a. Immediately after Award of Contract, Contractor shall obtain from Construction Manager anticipated delivery dates of City-furnished equipment or materials if they are not already specified in the Contract Documents.
b. These dates shall be shown on Baseline Construction Schedule in same manner indicated by Construction Manager.

1.08 WEATHER CONDITIONS AND WEATHER DAY ALLOWANCE
A. Seasonal weather conditions shall be considered in the planning and scheduling of work activity durations influenced by high or low ambient temperatures or precipitation to ensure the completion of the Work within the Contract Time. No time extensions will be granted for the Contractor's failure to take into account such weather conditions for the location of the Work and for the period of time in which the Work is to be accomplished.

B. The expected loss of working three (3) days shall be included in a separate identifiable critical activity labeled "Weather Days Allowance" to be included as the last critical activity of the project schedule. When weather days are experienced, and are approved as such by the Construction Manager, the Contractor shall either:

1. Increase the duration of the current critical activity(ies) by the number of weather days experienced.

2. Add a critical activity to the schedule to reflect the occurrence of the weather day(s).

C. The duration of the weather day allowance activity shall be reduced as weather days are experienced and included in the schedule. Any remaining weather days in the weather day allowance activity at the completion of the project shall be considered as float and shall not be for the exclusive use or benefit of either the City or Contractor.

1.09 UPDATING THE BASELINE SCHEDULE
A. Contractor shall update the Baseline Schedule on a monthly basis (or at shorter intervals if deemed necessary by Construction Manager to identify corrections necessary, such as work activities ten (10) days or more behind schedule) for the purpose of recording and monitoring the progress of the work. The Updated Baseline Schedule shall incorporate changes mutually agreed upon by Contractor and Construction Manager during preceding periodic reviews and changes resulting from approved Change Orders and Field Orders.

B. The Contractor shall produce and provide four (4) complete sets each of time-scaled network logic diagrams and bar charts in color on 11-inch by 17-inch sheets and one electronic copy on a CD with data in native format. The network logic diagram shall be clear and legible. Critical activities shall be indicated in red color on both schedules.

1. The City will not make monthly progress payments to the Contractor until the Construction Manager has received and accepted all schedule updates and reports as herein specified:
a. The Contractor shall submit schedule updates and reports to Construction Manager at least five (5) days before Contractor’s submission of its request for progress payment for same monthly period.

Page 326 of 519 ends

December 2024 01324 - 7 City of Yuba City
Progress Schedules and Reports Municipal Well 3

1.10 SCHEDULE REVISIONS
A. The conditions under which the Construction Manager may require revisions of the Construction Schedule include the following:

1. When delay in completion of any work item or sequence of work items results in an estimated extension of project completion by either fifteen (15) working days or by five percent (5 percent) of the remaining duration of time to complete the Contract, whichever is less. This slippage duration may be reduced further for any contract time that is a critical fixed completion date which must be met.

2. When delays in submittals or deliveries make re-planning or re-scheduling of the work necessary.

3. When the schedule does not represent actual prosecution and progress of the work.

4. When any change to the sequence of activities, the completion date for major portions of the work, or changes occur which affect the critical path.

5. When Contract modification necessitates schedule revision.

1.11 WEEKLY SCHEDULE
A. Submit to Construction Manager, on the last working day of every week, a progress schedule showing the activities completed during the previous week and the Contractor's schedule of activities for the following three (3) weeks.

B. The Weekly Schedule may be a CPM schedule or a bar chart but shall utilize the logic and conform to the status of the current progress schedule. In the event that the Weekly Schedule no longer conforms to the current schedule Contractor may be required to revise the schedule in accordance with Article, "Revisions to Schedule".

C. The activity designations and activity numbers used in the Weekly Schedule shall be consistent with those used in the Baseline Schedule and the monthly Schedule Updates.

D. The format of the Weekly Schedule shall be as agreed upon between the Contractor and the Construction Manager.

1.12 TIME IMPACT ANALYSIS
A. When change orders are initiated, delays are experienced, or the Contractor desires to revise the schedule logic, the Contractor shall submit to the Construction Manager a written Time Impact Analysis illustrating the influence of each change, delay, or Contractor request on the current contract schedule completion date. Each Time Impact Analysis shall include a fragmentary network analysis demonstrating how the Contractor proposes to incorporate the change order, delay, or Contractor request into the Schedule. The analysis shall demonstrate the time impact based on the date of occurrence of the change, delay or revision; the status of construction at that point in time; and the impact of all affected activities. The event times used in the analysis shall be those included in the latest updated copy of the CPM Schedule or as adjusted by mutual agreement between the Construction Manager and Contractor.

B. Activity time delays will not automatically mean that an extension of Contract Time is warranted or due the Contractor:

1. It is possible that a strike or contract modification will not affect existing critical activities or cause non-critical activities to become critical, i.e., a strike or modification may result in only absorbing a part of the available total float that may exist within an activity chain of the network, thereby not causing any effect on the Contract completion date or time.

2. The Contractor acknowledges and agrees that mitigation for delays due to changes, differing site conditions, suspension of the Work and other causes will require revision of preferential sequences of the Work before proposing an updated schedule which supports

Page 327 of 519 ends

December 2024 01324 - 8 City of Yuba City
Progress Schedules and Reports Municipal Well 3
a delay to the Project as a whole. When a delay to the Project as a whole can be avoided by revising preferential sequencing, and the Contractor chooses not to implement the revisions, the Contractor will be entitled to a time extension but is not entitled to compensation for extended overhead.

3. Float or slack shall not be for the exclusive use or benefit of the City or the Contractor.

Extensions of time for performance will be granted only to the extent that the equitable time adjustments for the activity or activities affected exceeds the total float along the activity chain involved at the time the change was ordered or the delay occurred.

C. Time Impact Submittal and Review:

1. Time Impact Analyses shall be submitted in triplicate and within fifteen (15) days after a delay occurs or with the Contractor's cost proposal in response to a notice of change from the Construction Manager. In cases where the Contractor does not submit a Time Impact Analysis for a specific change order, delay, or Contractor request within the specified period of time, then it is mutually agreed that the particular change order, delay, or Contractor request has no time impact on the Contract completion date and no time extension is required:
a. Approval or rejection of Time Impact Analyses by the Construction Manager and the City will be made within fifteen (15) days after receipt of the Time Impact Analysis unless subsequent meetings and negotiations are necessary. b. Upon approval, a copy of the Time Impact Analysis signed by the Construction Manager and City will be returned to the Contractor.
c. Upon mutual agreement by both parties, schedule revisions illustrating the influence of change orders, delays, and/or Contractor requests will be incorporated into the next schedule update.

1.13 RESPONSIBILITY FOR COMPLETION
A. Contractor agrees that at the sole judgment of Construction Manager, whenever it becomes apparent from the current monthly Updated Contract Baseline Schedule that the contract completion date and/or any milestone dates will not be met, Contractor will take the appropriate following actions, acceptable to Construction Manager, at no additional cost to City:

1. Increase construction labor in such quantities and crafts as will substantially eliminate, in the judgment of Construction Manager, the backlog of work.

2. Increase the number of working hours per shift, shifts per working day, working days per week, or the amount of construction equipment, or any combination of the foregoing, sufficiently to substantially eliminate, in the judgment of Construction Manager, the backlog of work. This paragraph shall not be construed to allow work outside the allowable hours and days specified in the Contract Documents.

3. Reschedule activities to achieve maximum practical concurrence of completion of activities.

1.14 FINAL SCHEDULE SUBMITTAL
A. As a condition precedent to the release of retainage the final Schedule Update shall be identified by the Contractor as the As-Built Schedule.

B. The As-Built Schedule shall reflect the exact manner in which the project was constructed by reflecting actual start and completion dates for all activities accomplished on the project.

C. The As-Built Schedule shall be signed and certified by the Contractor’s Project Manager and Responsible Scheduler as being an accurate record of the way in which the project was actually constructed.

Page 328 of 519 ends

December 2024 01324 - 9 City of Yuba City
Progress Schedules and Reports Municipal Well 3

1.15 CONTRACTOR’S DAILY REPORTS
A. Maintain daily job reports recording all significant activity on the project, including number of workers on site, active construction equipment used, notable deliveries, work activities, delays, interruptions or any problems encountered.

B. Record this information on a Contractor’s Daily Report form. Submit to Construction Manager for approval no later than the following morning for the previous work day.

C. If there is no work performed on any given day, note the reasons for no work and submit a daily report to the Construction
D. Manager on those days also.

E. Failure to stay current with daily reporting will be just cause for the City not processing a progress payment until reports are submitted.

END OF SECTION

Page 329 of 519 ends

December 2024 01324 - 10 City of Yuba City
Progress Schedules and Reports Municipal Well 3
(THIS PAGE LEFT BLANK INTENTIONALLY)

Page 330 of 519 ends

December 2024 01330 - 1 City of Yuba City
Submittal Procedures Municipal Well 3
SECTION 01330

SUBMITTAL PROCEDURES
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes: Requirements and procedures for submitting Shop Drawings, Product Data, Samples, other submittals relating to products, and as specified in individual sections.

B. Submittals shall follow the procedures in this Section regardless of reference to this Section in the individual sections.

C. All submittals shall be transmitted via email to the Construction Manager, William Jow, at [email protected].

D. Approved Equal and Substitutions shall be as defined and managed pursuant to Section 01605.

E. Referenced Sections:

1. Section 01324 – Progress Schedules and Reports

2. Section 01605 – Product Requirements and Substitutions F. Additional Requirements for submittal procedures are described in other Technical Specifications (LSCE Technical Specifications) of these Contract Documents.

1.02 DEFINITIONS
A. Manufacturer’s Instructions: Instructions, stipulations, directions, and recommendations issued in printed form by the manufacturer of a product addressing handling, installation, erection, and application of the product.

B. Shop Drawings: Drawings, diagrams, schedules, and other data specially prepared for the Work to illustrate some portion of the Work.

C. Product Data: Illustrations, standard schedules, performance charts, brochures, diagrams, and other information to illustrate materials or equipment for some portion of the Work. Product Data will also include engineering calculations and related information, where specified.

Product Data will also include engineering calculations and related information, where specified.

D. Samples: Physical examples which illustrate materials, equipment, or workmanship and establish standards by which the Work will be judged.

E. Special Samples: Physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged, and will be incorporated in the Work.

1.03 PROCEDURES
A. Within fifteen (15) calendar days after the Notice To Proceed, the Contractor shall submit a preliminary Schedules of Submittals which shall list each required submittal and the proposed times for submitting, reviewing, and processing each submittal.

B. Contractor shall submit a preliminary Project Schedule for the project as specified in Section 01324.

C. Within thirty (30) calendar days after award of Contract, the Contractor shall submit all submittals required to start the project. The submittals should include but are not limited to the following items:

Page 331 of 519 ends

December 2024 01330 - 2 City of Yuba City
Submittal Procedures Municipal Well 3

1. Project Baseline CPM Schedule, Section 01324.

D. Contractor shall be responsible for furnishing the remaining submittals identified in the Schedule of Submittals in sufficient time for approval action, including resubmittals, without delaying the project.

E. Contractor shall be responsible for coordinating each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

F. No extension of Contract Time will be authorized due to a failure to transmit submittals sufficiently in advance of the Work to permit processing.

G. Submittals shall be provided via email to the Construction Manager, William Jow, at [email protected]. Submittals which cannot be provided electronically, such as samples, shall be delivered to the City's main office or to the Engineering office at the City's treatment plant, unless another mutually agreeable place is designated.

H. Each submittal shall include a Submittal Transmittal Form, with the following additional information, where applicable:

1. Subcontractor and major supplier.

2. Reference submittal to Contract Documents by Drawing or detail.

3. Variations from Contract Documents when variations are included in submittal.

4. When applicable, follow Section 01605, to request for material substitution.

I. Each submittal shall be submitted via email to William Jow, [email protected]. Submit one electronic copy in a searchable Adobe Acrobat pdf format with bookmarks (tabs) for each separate components of the submittal. In addition, one full-size hard copy of any submittals as requested by the Construction Manager.

J. Submittals and subsequent resubmittals shall be in the following format: “XXXXX” denotes the Specification Number, “YY” denotes the sequential number of submittals in that Specification Section, and “ZZ” indicates whether the submittal is an original or a resubmittal.

K. Provide or furnish products and execute the Work in accordance with accepted submittals, unless in conflict with Contract Documents.

L. When minor deviations from Contract Documents are accepted, modify Contract Documents in accordance with the Conditions of the Contract.

M. Contractor to provide one (1) clean and conformed hard copy of each approved submittal to the Construction Manager.

1.04 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
A. Submit Shop Drawings, Product Data, Samples, and other pertinent information in sufficient detail to show compliance with specified requirements.

B. Check, verify, and revise submittals as necessary to bring them into conformance with Contract Documents and actual field conditions:

1. Determine and verify quantities, dimensions, specified design and performance criteria, materials, catalog numbers, and similar data.

2. Coordinate submittal with other submittals and with the requirements of the Contract Documents.

3. Excise or cross out non-applicable information and clearly mark applicable information with citations to, and terminology consistent with Contract Documents. On catalog cuts, clearly mark the items to be used, including proposed options and alternatives.

Page 332 of 519 ends

December 2024 01330 - 3 City of Yuba City
Submittal Procedures Municipal Well 3
C. After completion of checking, verification, and revising; stamp, sign, and date submittals indicating review and approval by the Contractor; and submit to City:

1. Stamp and signature indicates Contractor has satisfied shop drawing review responsibilities and constitutes Contractor’s written approval of shop drawing.

2. Shop drawings without Contractor’s written approval will be returned for resubmission.

D. Submittal Drawings: Submit drawings prepared in AutoCAD, latest version.

E. Product Data and Manufacturer’s Instructions: Submit one electronic copy.

F. Samples: Submit two (2) samples labeled with reference to applicable Specification Section and submittal number. Label will be returned with reviewer’s selection when appropriate, comments, and stamp. Samples will not be returned unless return is requested in writing and additional sample is submitted.

G. Special Samples: Submit one (1) samples labeled with reference to applicable Contract Documents and submittal number. Samples and one (1) label will be returned for installation in the Work.

H. Assume risk of expense and delays when proceeding with work related to required submittals without review and acceptance.

I. Contractor to review all shop drawings submitted by Subcontractors for compliance with Contract Documents.

J. Contractor to distribute additional sets of samples to subcontractors, suppliers, fabricators, installers, etc. as required for the performance of the Work. Must show distribution on transmittal forms.

1.05 PERFORMANCE SPECIFICATIONS AND CONTRACTOR DESIGNED WORK A. Work under this Contract may be specified by a combination of descriptive, performance, reference standard and proprietary specifications. In the event of conflict between any of the various specification methods used to specify a single item the order of precedence shall be the order in which the methods are listed in the preceding sentence. The terms used to describe types of Specifications are taken from the Construction Specification Institute (CSI) Handbook of Practice.

B. Where Specifications are used to define the characteristics of Contractor designed systems, items or components, the Contractor shall be fully responsible to design, engineer, manufacture, and install the systems, items and components to meet the specified functional requirements, performance requirements, quality standards, durability standards and conditions of use as well as all applicable codes, regulations and referenced trade or industry standards. The Contractor shall perform such design by employing engineers licensed in the State in which the Work is being constructed. The Contractor's design submittals shall include calculations and assumptions on which the design is based and shall be stamped and signed by appropriately licensed engineers.

C. Where performance type specifications are used or where pre-engineered or Contractor designed systems, elements, equipment or components are called for, the City, the Design Engineer and the Engineer shall have the right to rely on the Contractor's design. Favorable Review of the Contractor's design submittal shall be limited to acknowledgment that the design was prepared with the intent of meeting the specified performance criteria, but the Engineer's review shall not constitute a review of the design itself, of the designer's calculations, or of the effectiveness of the design in actually satisfying the specified criteria. Favorable review of the Contractor's design submittal shall not relieve the Contractor from full responsibility for the adequacy of the Contractor design.

1.06 ASSET MANAGEMENT DATA (NOT USED)

Page 333 of 519 ends

December 2024 01330 - 4 City of Yuba City
Submittal Procedures Municipal Well 3

1.07 MANUFACTURER’S INSTRUCTIONS
A. Submit manufacturer’s instructions wherever made available by manufacturers and when installation, erection, or application in accordance with manufacturer’s instructions is required by the Specifications.

B. Submit manufacturer’s instructions prior to installation, erection, or application of equipment and other project components. Submit manufacturer’s instructions in accordance with requirements for Product Data.

1.08 CITY’S REVIEW
A. City’s review of submittals shall not release Contractor from Contractor’s responsibility for performance or requirements of Contract Documents. Neither shall City’s review release Contractor from fulfilling purpose of installation nor from Contractor’s liability to replace defective work.

B. Do not consider submittals as Contract Documents. Purpose of submittals is to demonstrate how Contractor intends to conform to the design concepts.

C. City’s review of shop drawings, samples, or test procedures will be only for conformance with design concepts and for compliance with information given in Contract Documents:

1. City’s review does not extend to:
a. Accuracy of dimensions, quantities, or performance of equipment and systems designed by Contractor.
b. Contractor’s means, methods, techniques, sequences, or procedures except when specified, indicated on the Drawings, or required by Contract Documents. c. Safety precautions or programs related to safety which shall remain the sole responsibility of the Contractor.

D. Except as may be provided in subsequent specifications or specified herein, a submittal will be returned within thirty (30) calendar days after receipt:

1. Submittals will be reviewed with appropriate comments as indicated below:
a. If the review indicates that the material, equipment, or work method complies with the project specifications, submittal copies will be marked “NO EXCEPTIONS TAKEN”. In this event, the Contractor may begin to implement the work method or incorporate the material or equipment covered by the submittal.
b. If the review indicates limited corrections are required, copies will be marked “MAKE CORRECTIONS NOTED”. The Contractor may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections. Where submittal information will be incorporated in O&M data, a corrected copy shall be provided.
c. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked “AMEND AND RESUBMIT”. Except at his own risk, the Contractor shall not undertake work covered by this submittal until it has been revised, resubmitted and returned marked wither “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.
d. If the review indicates that the material, equipment, or work method does not comply with the project specifications, copies of the submittal will be marked “REJECTED – SEE REMARKS”. Submittals with deviations which have not been identified clearly may be rejected. Except at his own risk, the Contractor shall not undertake the work covered by such submittals until a new submittal is made and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.

Page 334 of 519 ends

December 2024 01330 - 5 City of Yuba City
Submittal Procedures Municipal Well 3
e. Product Data submittals for information only:
1) Such information is not subject to submittal review procedures and shall be provided as part of the work under this contract and its acceptability determined under normal inspection procedures.
2) Product data review status will be classified similarly to other submittals.

2. When a submittal cannot be returned within that period, City will, within a reasonable time after receipt of the submittal, give notice of the date by which that submittal will be returned.

3. A longer review duration will be required for large and complex submittals, particularly, but not limited to, those that require review by multiple engineering disciplines or where multiple sub-systems are part of a larger complex system. Identifications of submittals that are considered to be large and complex will be made jointly by the City and the Contractor, and shall be identified in the submittal schedule specified in Section 01324.

E. Submittals returned as “REVISE AND RESUBMIT” contain specific attention in writing to revisions other than the corrections called for by the City on previous submittals. Rejected submittals contain remarks relative to further submittal. The resubmittal will be returned within thirty (30) calendar days after receipt.

F. All resubmittals must be complete and not piecemeal. If a resubmittal is required it shall be submitted in its entirety.

G. City will be entitled to rely upon the accuracy or completeness of designs, calculations, or certifications made by licensed professionals accompanying a particular submittal whether or not a stamp or seal is required by Contract Documents or Laws and Regulations.

H. Costs incurred by City as a result of additional reviews of a particular submittal after the second time it has been reviewed shall be borne by Contractor. Reimbursement to City will be made by deducting such costs from Contractor’s subsequent partial payments.

I. Costs incurred by unnecessary submittals, such as submitting on multiple products for the same requirement for the convenience of the Contractor, shall be borne by Contractor.

Reimbursement to City will be made by deducting such costs from Contractor’s subsequent partial payments.

1.09 MINOR OR INCIDENTAL PRODUCTS AND EQUIPMENT SCHEDULES A. Shop Drawings of minor or incidental fabricated products will not be required, unless requested.

B. Submit tabulated lists of minor or incidental products showing the names of the manufacturers and catalog numbers, with Product Data and Samples as required to determine acceptability.

1.10 SUBMITTALS FOR INFORMATION OR RECORD ONLY
A. Submit one electronic copy.

B. Mill Test Reports:

1. Submit one electronic copy of factory and mill test reports for record only.

2. Do not incorporate Products in the Work which have not passed testing and inspection satisfactorily.

3. Contractor shall pay for mill and factory tests.

1.11 PROJECT LIST OF SUBMITTALS
A. The Contractor shall develop a comprehensive Master Submittal List of all specified submittals.

The list shall be serially numbered in accordance with the appropriate specification section.

The list shall be developed and submitted to the Construction Manager for review within fourteen (14) days following the Notice to Proceed. The Construction Manager will conduct a

Page 335 of 519 ends

December 2024 01330 - 6 City of Yuba City
Submittal Procedures Municipal Well 3
meeting to review the Master Submittal List with the Contractor within five (5) working days following receipt of the list.

B. The Contractor shall develop a schedule for the submission and review of all specified submittals for the project. The schedule shall be developed in accordance with the Section 01324. The schedule shall include individual activities for submission and review (and fabrication and delivery for equipment and material) for each submittal. The submittal schedule shall be a separate subnet of the master CPM construction schedule with each submittal activity linked to the appropriate construction activity. Every projected submittal shall be listed and incorporated into the schedule.

C. The Contractor shall meet at least once per month with the Construction Manager to review the status of all submittals. In addition, the Contractor shall develop and transmit monthly, a written list of the submittals which require review within the following ninety (90) days. The list of projected submittals shall include the estimated date of submission for each submittal and a reference Master Submittal List for each item to be included in the submittal.

D. This section shall not supersede or modify any specific requirements for submittals or the submittal process described elsewhere in these specifications, but shall be a supplement to the existing requirements.

END OF SECTION

Page 336 of 519 ends

December 2024 01340 - 1 City of Yuba City
Request for Interpretation Municipal Well 3
SECTION 01340

REQUEST FOR INTERPRETATION

GENERAL

1.01 GENERAL REQUIREMENTS
A. The Contractor shall prepare a Request for Interpretation (RFI) when additional information, clarification or interpretation of the Contract Documents is needed. RFIs may also be used for apparent conflicts, inconsistencies, ambiguities, or omissions. “Request for Interpretation” and “Request for Information” shall have the same meaning.

B. RFIs shall be submitted to the Construction Manager immediately upon discovery, but no less than fifteen (15) days prior to the start date of the activities related to the clarification, based on the latest updated and accepted construction schedule. Any work undertaken prior to receipt of an RFI response shall be at the risk of Contractor.

C. RFIs generated during submittal and shop drawing preparation must be submitted by the Contractor sufficiently in advance to not only allow for investigation and preparation of a response, but also for inclusion of the response into the submittal and shop drawing. Failure by the Contractor to provide sufficient time will not be cause for entitlement to a time extension.

D. The Contractor is responsible for its cost to implement and administer RFIs throughout the Contract duration. Regardless of the number of RFIs submitted, the Contractor will not be entitled to additional compensation.

E. RFIs shall not be used for submittals or for substitute of material, equipment or for waiving of requirements.

1.02 SUBMITTAL
A. Before submitting each RFI, the Contractor shall carefully review the following relevant information:

1. All field measurements, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto.

2. All materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work.

3. All information relative to means, methods, techniques, sequences, and procedures of construction and safety precautions and programs incident thereto.

4. The coordination of each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents.

5. The Contract Documents.

6. The Project correspondence and documentation.

B. RFIs shall be submitted on an RFI Form via the City-furnished, Web Based Construction Document Management system in accordance with Section 01322. Each RFI shall deal with only one topic, item, issue or system.

C. RFIs shall clearly describe the problem and specifically state what is needed. Relevant portions of the Contract Documents shall be cited, marked-up and attached.

D. The Contractor shall review each RFI before submitting and compare it with the Contract Documents to verify that a response is required. RFIs will only be accepted from the Contractor and not from subcontractors or suppliers.

E. A recommendation or proposed solution may be included when appropriate or expedient.

Page 337 of 519 ends

December 2024 01340 - 2 City of Yuba City
Request for Interpretation Municipal Well 3
F. Known schedule or cost impacts shall be noted in the RFI.

1.03 RESPONSES
A. The Construction Manager will respond in writing to an RFI from the Contractor within a reasonable amount of time, but no more than fifteen (15) calendar days following receipt of RFI from the Contractor. The Contractor shall indicate a priority for responses if more than five (5) RFIs are pending at the same time.

B. The Construction Manager and/or Design Engineer’s review of an RFI will be only to provide clarification and interpretation of the Contract Documents.

C. The Contractor shall reply within ten (10) calendar days if there is disagreement concerning the RFI response.

D. Subsequent resubmittals shall be identified with the same RFI number and a consecutive letter designation. Resubmittals shall clearly state the reason for resubmitting.

E. RFIs will not be recognized or accepted, if in the opinion of the Construction Manager, one of the following conditions exists:

1. The Contractor submits an RFI as a submittal.

2. The Contractor submits the RFI under the pretense of a Contract Documents discrepancy or omission without thoroughly reviewing the documents. In this case, the Contractor shall be responsible for both the Construction Manager’s and Design Consultant’s administrative costs to process the RFI. Such costs may be deducted from the Contractor’s progress payments.

3. The Contractor submits the RFI in a manner that suggests that specific portions of the Contract Documents are assumed to be excluded, or be taken as an isolated portion of the Contract Documents in part rather than whole.

4. The Contractor submits an RFI in an untimely manner without proper coordination and scheduling of work or related trades.

F. The Construction Manager and/or Design Engineer’s review shall not relieve the Contractor from the responsibility for a variation from the requirements of the Contract Documents unless the Contractor has in writing called attention to each such variation at the time of each RFI submittal and Construction Manager has given written approval of each such variation by specific written notation thereof incorporated in the RFI review; nor will any review by City relieve Contractor from responsibility for compliance with the requirements for careful review above.

G. The Construction Manager and/or Design Engineer’s review will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto.

H. The Construction Manager may furnish the Contractor additional detailed written instructions to further explain the work, and such instructions shall be a part of the Contract Documents.

Clarifications will be issued using the above RFI system and Field Orders. Should additional detailed instructions in the opinion of the Contractor constitute work in excess of the scope of the Contract, the Contractor shall submit notification immediately and written notification thereof to the Construction Manager no more than seven (7) days following receipt of such instruction, and in any event prior to the commencement of work thereon. If the Construction Manager considers it justified, the instructions of the Engineer will be revised or a proposed change order will be issued for the Owner’s consideration. The Contractor shall have no claim for additional compensation or extension of the schedule because of any such additional instructions unless the Contractor provides the Construction Manager written notice thereof within the time frame specified above. In addition, the Contractor shall within fifteen (15) days

Page 338 of 519 ends

December 2024 01340 - 3 City of Yuba City
Request for Interpretation Municipal Well 3
from the date of notification provide detailed justification and analysis as well as complete pricing and schedule CPM fragmentary network to support any request for time extension.

I. The City’s review shall not relieve the Contractor from the responsibility for a variation from the requirements of the Contract Documents unless the Contractor has in writing called attention to each such variation at the time of each RFI submittal and Construction Manager has given written approval of each such variation by specific written notation thereof incorporated in the RFI review; nor will any review by City relieve Contractor from responsibility for compliance with the requirements for careful review above.

END OF SECTION

Page 339 of 519 ends

December 2024 01340 - 4 City of Yuba City
Request for Interpretation Municipal Well 3
(THIS PAGE LEFT BLANK INTENTIONALLY)

Page 340 of 519 ends

December 2024 01450 - 1 City of Yuba City
Quality Control and Inspection Municipal Well 3
SECTION 01450

QUALITY CONTROL AND INSPECTION
PART 1 - GENERAL

1.01 SECTION INCLUDES
A. Requirements for quality control, inspection and testing of the Work.

1.02 CONTRACTOR’S QUALITY CONTROL
A. General:

1. Ensure that products, services, workmanship and Site conditions comply with the requirements of the Contract Documents by coordinating, supervising, testing and inspecting its Work.

2. Utilize only suitably qualified, skilled and trained personnel experienced in the tasks required to complete the Work in accordance with the quality requirements of the Contract Documents.

3. Should there be no quality basis specifically prescribed for any portion of the Work, the quality and testing procedures shall be in accordance with the best-accepted practices of the construction industry for the locale of the Project, for projects of this type, or standards set by engineering or technical societies (e.g. ASTM or ASHRAE), whichever is more stringent.

B. Quality of Work:

1. Quality of Products: Unless otherwise indicated or specified, all products shall be new, free of defects, and fit for the intended use.

2. Quality of installation: All Work shall be produced plumb, level, square and true, or true to indicated angle, and with proper alignment and relationship between the various elements, as shown on or required by Contract Documents.

3. Protection of Completed Work: Take all measures necessary to preserve completed Work free from damage, deterioration, soiling, and staining, until acceptance by City.

4. Standards and Code Compliance and Manufacturer's Instructions and Recommendations:

Unless more stringent requirements are indicated or specified, comply with manufacturer's instructions and recommendations, reference standards and building code research report requirements in preparing, fabricating, erecting, installing, applying, connecting, and finishing Work.

5. Deviations from Standards and Code Compliance and Manufacturer's instructions and Recommendations: Secure City's advanced written consent. Document and explain all deviations from reference standards and building code research report requirements and manufacturer's product installation instructions and recommendations, including acknowledgement by the manufacturer that such deviations are acceptable and appropriate for the Project.

6. Verification of Quality: Work shall be subject to verification of quality by City in accordance with provisions of the Contract Documents.

C. Defective Work:

1. Defective Work shall be modified, replaced, repaired or redone by the Contractor at no change in Contract Sum or Contract Time.

2. Acceptance of Defective Work, without specific written acknowledgement and approval of City, shall not relieve the Contractor of the obligation to correct such Work.

Page 341 of 519 ends

December 2024 01450 - 2 City of Yuba City
Quality Control and Inspection Municipal Well 3

3. Should City determine that it is not feasible or in City's interest to require Defective Work to be repaired or replaced, an equitable reduction in Contract Sum shall be made by agreement between City and Contractor. If equitable amount cannot be agreed upon, a Construction Change Directive will be issued and the amount in dispute resolved in accordance with the Contract Documents.

4. City and City's consultants disclaim any and all responsibility for Work produced not in conformance with the Drawings and Specifications. Contractor shall have full responsibility for all extra inspection, correction and re-work costs by Contractor and City resulting from Defective Work, as well as all delay damages in accordance with the liquidated damages provisions of the Contract Documents. Contractor waives excuses for defective work relating to City's prior review of Submittals and/or prior failure to notice Defective Work in place on inspection.

1.03 INSPECTION AND TESTING
A. General:

1. Additional Requirements for tests are described in other Technical Specifications (LSCE Technical Specifications) of these Contract Documents.

2. Construction Manager:
a. Where the Contract Documents require work to be field tested or approved, it shall be tested in the presence of the Construction Manager or its authorized representative. b. The Construction Manager shall have the right to witness all on-site tests performed by the Contractor and any shop tests. The results of any tests performed by the Contractor shall be made available for the information of the Construction Manager. c. Inspections, tests or favorable reviews by the Construction Manager or others shall not relieve the Contractor from its obligation to perform the work in accordance with the requirements of the Contract Documents or for its sole responsibility for the quality of workmanship and materials.

3. Testing and Sampling:
a. Except as specifically required under the technical specifications for testing and inspection, all tests for materials furnished by the Contractor will be done in accordance with commonly recognized standards of national organizations. b. Where tests are to be performed by the Construction Manager or by an independent laboratory or agency, the Contractor shall furnish such samples of all materials as required by the Construction Manager without charge.
c. The sample or samples of materials to be tested shall be selected by such laboratory or agency, or the Construction Manager, and not by the Contractor. d. No material for which the Contract Documents require the submittal and approval of tests, certificates of compliance or other documentation shall be incorporated in the Work until such submittal has been made and approved.
e. Provide safe access, including plants where materials or equipment are manufactured or fabricated, for the Construction Manager and inspectors to adequately inspect the quality of work and the conformance with the Contract Documents. f. Furnish the Construction Manager the necessary labor and facilities for such things as excavation in the compacted fill to the depths required to take samples. g. Provide adequate lighting, ventilation, ladders and other protective facilities as may be necessary for the safe performance of inspections.

4. Final Inspection:
a. Upon completion of the Work the Construction Manager will conduct a final inspection as provided for in General Conditions. Records shall be available at all reasonable

Page 342 of 519 ends

December 2024 01450 - 3 City of Yuba City
Quality Control and Inspection Municipal Well 3
hours for inspection by other local or State agencies to ascertain compliance with laws and regulations.

5. Contractor’s Responsibility:
a. Neither the employment of independent testing and inspection agency nor observations or tests by City and City’s consultants shall in any manner relieve the Contractor of obligation to perform Work in full conformance to all requirements of the Contract Documents.
b. The City reserves the right to reject all Work not in conformance to the requirements of the Contract Documents, or otherwise Defective.

B. Notice:

1. Notify the Construction Manager, in writing, at least twenty-four (24) hours before any field testing or special inspections are required to be performed by the Construction Manager or independent laboratory furnished by the City. The Contractor shall notify the Construction Manager at least two hours before any inspection is required to be performed or to witness the Contractor’s on-site field testing.

2. Whenever the Contractor varies the period during which work is carried on each day, the Contractor shall give due notice to the Construction Manager so that proper inspection may be provided. Any work done in the absence of the Construction Manager shall be considered to be rejected. It will be the responsibility of the Contractor to demonstrate to the satisfaction the Construction Manager that the work meets all conditions of the specification and if such conditions are not met to remove the work.

3. Notify the Construction Manager, in writing, at least thirty (30) days prior to the shipment of materials and equipment to be tested and/or inspected at the point of origin. Satisfactory tests and inspections at the point of origin shall not be construed as a final acceptance of the materials and equipment nor shall such tests and inspections preclude retesting or reinspection at the site of the Work.

C. Costs of Testing:

1. The Contractor shall be responsible for, and shall pay for, all quality control and off site tests of materials required including all source and mix design tests for the approval of soil and concrete materials except those tests specifically noted to be performed and paid for by the City.

2. The City or Construction Manager, will perform the soils and concrete confirmation tests detailed in the Technical Specifications during the performance of the Work.

3. All other testing required by the technical specifications shall be the responsibility of the Contractor.

4. Additional Tests and Inspections:
a. The Construction Manager shall have the authority to require additional tests or inspections due to the manner in which the Contractor executes its work. b. Examples of such additional tests and inspections include; tests of materials substituted for previously accepted materials, or substituted for specified materials, or retests made necessary by failure of material to comply with the requirements of the Specifications.
c. Where such tests and inspections are required by Contract to be performed by the City, the City will pay for the additional tests and inspections but will issue a unilateral Change Order to deduct these costs from the Contract price.

D. Work Covered Prior to Inspection and/or Testing:

1. Work requiring inspection and/or testing shall not be concealed or buried prior to the acceptance of such inspection or testing.

Page 343 of 519 ends

December 2024 01450 - 4 City of Yuba City
Quality Control and Inspection Municipal Well 3

2. Work covered without the favorable review or consent of the Construction Manager shall, if required by the Construction Manager, be uncovered for inspection and/or testing at the Contractor's expense.

E. Work Covered With Prior Inspection and/or Testing:

1. If the Construction Manager considers it necessary or advisable that covered work which was favorably inspected and tested be uncovered for re-inspection and/or retesting, the Contractor, at the Construction Manager's request, will uncover, expose or otherwise make available for observation, inspection or testing as the Construction Manager may require, that portion of the work in question, furnishing all necessary labor, materials, tools, and equipment.

2. If it is found that such work is defective, the Contractor will bear all expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction.

3. If, however, such work is not found to be defective the Contractor will be allowed an increase in the Contract price or an extension of the Contract time, or both, directly attributable to such uncovering, exposure, observation, testing and reconstruction, and a Change Order shall be issued for such additional work.

F. Coordination of County, City Building and Other Inspections:

1. The Contractor is completely responsible for scheduling all County, City and any other agency inspections in accordance with the County, City and agency requirements.

2. Notify the Construction Manager of all building and other work component inspection notices and schedules.

3. Failure of the Contractor to properly coordinate and schedule these inspections shall not be cause for time extensions.

G. Special Tests and Inspections:

1. As provided for in the Contract Documents and laws and regulations, specialized tests and inspections shall be performed by special inspectors certified by the International Conference of Building Officials (ICBO).

2. Unless otherwise stated in the Contract Documents, each of these tests will be performed and paid for by the City.

H. Inspections and Tests by Serving Utilities:

1. Unless otherwise indicated in the Contract Documents, the Contractor shall cause, schedule and conduct inspections and tests by serving Utilities required for the Work under this Contract.

I. Inspections and Tests by Serving Manufacturers:

1. Unless otherwise indicated in the Contract Documents, the Contractor shall cause all required tests and inspections to be conducted by materials, equipment or systems manufacturers.

2. Additionally, all tests and inspections required by materials, equipment or systems manufacturers as conditions of warranty or certification of Work shall be made, the cost of which shall be included in the Contractor’s bid.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 344 of 519 ends

December 2024 01605 - 1 City of Yuba City
Product Requirements and Substitutions Municipal Well 3 SECTION 01605

PRODUCT REQUIREMENTS AND SUBSTITUTIONS
PART 1 - GENERAL

1.01 SECTION INCLUDES
A. Product requirements, product selection, products schedule, execution, manufacturer’s instructions, and delivery, handling, and storage.

1.02 REFERENCED SECTIONS:

A. Section 01330 – Submittal Procedures.

1.03 PRODUCT REQUIREMENTS
A. Comply with Specifications and referenced standards as minimum requirements.

B. Provide products by same manufacturer when products are of similar nature, unless otherwise specified.

C. Provide identical products when products are required in quantity.

D. Provide products with interchangeable parts whenever possible.

E. Require each equipment manufacturer to have maintenance facilities meeting the following requirements:

1. Minimum three years operational experience.

2. Location in continental United States.

3. Equipment and tools capable of making repairs.

4. Staff qualified to make repairs.

5. Inventory of maintenance spare parts.

F. Provide evidence of product compliance pursuant to appropriate specification section, this Section, and Section 01330.

1.04 PRODUCT SELECTION
A. When products are specified by standard or specification designations of technical societies, organizations, or associations only, provide products which meet or exceed reference standard and Specifications.

B. When products are specified with names of manufacturers but no model numbers or catalog designations, provide:

1. Products by one of named manufacturers which meets or exceeds Specifications.

2. Accepted or equals.

C. When products are specified with names of manufacturers and model numbers or catalog designations, provide:

1. Products with model numbers or catalog designations by one of named manufacturers.

2. Accepted or equals.

D. When products are specified with names of manufacturers, but with brand or trade names, model numbers, or catalog designations by one manufacturer only, provide:

1. Products specified by brand or trade name, model number, or catalog designation.

Page 345 of 519 ends

December 2024 01605 - 2 City of Yuba City
Product Requirements and Substitutions Municipal Well 3

2. Products by one of named manufacturers proven in accordance with requirements for or equals to meet or exceed quality, appearance and performance of specified brand or trade name, model number, or catalog designation.

3. Accepted or equals.

E. When products are specified with only one manufacturer followed by "or Equal," provide:

1. Products meeting or exceeding Specifications by specified manufacturer.

2. Accepted or equals.

1.05 APPROVED EQUAL AND SUBSTITUTION
A. Specified Item: Material, equipment, product, thing, or service referenced in this Project Plans and Specifications that has been identified by specific brand, manufacturer, model number, catalog number, or trade name.

B. Equal Items: Items, as referenced in this Project Plans and Specifications are those, which, to the City’s knowledge, meet the requirements of the Project Plans and Specifications and are considered equal to the Specified Items.

C. Substitutions: Substitutions are considered changes to the Contract.

D. Submissions for Evaluation:

1. The Contractor shall submit to the City in accordance with Public Contract Code Section 3400, after contract award but no later than thirty (30) days after the date of Notice to Proceed, proposal(s) for acceptance of a proposed Equal Item for a Specified Item or a Substitution. At the sole discretion of the City, City may give written consent to the submission of the proposed Equal Item or Substitution after the expiration of the thirty (30) day time limit.

2. The Contractor shall completely fill out the Material/Product Substitution Request Form (located at the end of this Section) and submit sufficient data, drawings, samples, literature, calculations, and all other information requested by City to demonstrate to the City that the proposed Equal Item or Substitution is a suitable replacement for the Specified Item(s).

3. Failure of the Contractor to submit the proposed Equal Item or Substitution for review in the manner and time described above shall be sufficient cause for rejection by the City of the proposed Equal Item or Substitution.

4. Burden of proof as to the submitted items being equal to the Specified Items, or a suitable Substitution, is the responsibility of the Contractor.

E. Evaluation as Equal:

1. Submission of items which are proposed as equal to the Specified Items will be evaluated in accordance with the following provisions.

2. In addition to the complete Substitution Request Form located at the end of this Section, and information specified above, Contractor shall provide a table showing equivalency between the Specified Item and the proposed equal item.

3. The City’s evaluation of the submitted items proposed as being equal to the Specified Items is based on, but not limited to, the following:
a. Performance.
b. Functionality.
c. Efficiency.
d. Durability.
e. Life cycle costs.
f. Ease and economy of maintenance and operation.

Page 346 of 519 ends

December 2024 01605 - 3 City of Yuba City
Product Requirements and Substitutions Municipal Well 3 g. Construction and physical characteristics as compared to the Specified Items, or as delineated in the Project Plans and Specifications.
h. Dimensional compatibility with the materials it combined to produce a unified design system.
i. Compatibility with products in use.
j. Impact to Project design, construction schedule, or construction sequencing. k. All aspects of finished appearance including form, texture, and color, that may affect other design elements.

4. The City will be the sole judge in this matter. In the event the City rejects the proposal items based on one of the above criteria, the Contractor shall submit the Specified Items.

F. Submission of items which are proposed as substitution of the Specified Items shall be subject to requirements for proposed equal evaluation and the following additional provisions:

1. Substitution(s) of Specified Item(s) proposed by the Contractor may require modifications in the Project design, Project schedule, and/or construction sequencing. The Contractor shall identify all necessary project modification required for the substitution(s). Necessary project modifications may include, but not be limited to, construction cost (credit), electrical, instrumentation, structural, mechanical, architectural, testing, engineering costs, and other related modifications.

2. The Contractor is responsible for all costs associated with the substitutions(s) including submittal reviews and any project redesigns and modifications. Contractor refusal to accept any of these costs shall be just cause for disapproval of the substitution(s).

3. The City will review and respond in writing to the Contractor’s proposed substitution within thirty (30) days after receipt of all information the City requires to make a final determination.

4. If the proposed items are accepted, all cost saving shall be credited to the City.

1.06 QUALITY ASSURANCE
A. Employ entities that meet or exceed specified qualifications, to execute the Work.

B. Inspect conditions before executing subsequent portions of the Work. Accept responsibility for correcting unsatisfactory conditions upon executing subsequent portions of the Work.

C. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, and racking.

1.07 TOOLS AND SPARE PARTS (NOT USED)

1.08 PROTECTION OF EQUIPMENT AFTER INSTALLATION:

A. After installation, all equipment shall be protected from damage from, including but not limited to, dust, abrasive particles, debris and dirt generated by the placement, chipping, sandblasting, cutting, finishing and grinding of new or existing concrete, terrazzo and metal; and from the fumes, particulate matter, and splatter from welding, brazing and painting of new or existing piping and equipment.

B. As a minimum, vacuum cleaning, blowers with filters, protective shieldings, and other dust suppression methods will be required at all times to adequately protect all equipment.

C. During concreting, including finishing, all equipment that may be affected by cement dust must be completely covered.

D. During painting operations, all grease fittings and similar openings shall be covered to prevent the entry of paint.

Page 347 of 519 ends

December 2024 01605 - 4 City of Yuba City
Product Requirements and Substitutions Municipal Well 3 E. Electrical switchgear, unit substation, and motor load centers shall not be installed until after all concrete work and sandblasting in those areas have been completed and accepted and the ventilation systems installed.

1.09 MANUFACTURER'S INSTRUCTIONS
A. Deliver, handle, store, install, erect, or apply products in accordance with manufacturer's instructions, Contract Documents, and industry standards.

B. Periodically inspect to assure products are undamaged and maintained under required conditions.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)

END OF SECTION

Page 348 of 519 ends

December 2024 01605 - 5 City of Yuba City
Product Requirements and Substitutions Municipal Well 3

PRODUCT REQUIREMENTS SUPPLEMENT

MATERIAL / PRODUCT SUBSTITUTION REQUEST FORM
Project Name: Municipal Well No. 3 Date:

A. We hereby submit for your consideration the following product instead of the specified item:

1. Section _____________________________________ Sub-article

2. Specified Item

3. Proposed Substitution (Mfr, Type, Model, etc.)
B. Complete all of the following:

1. Does this substitution offer the City a cost credit (including costs for changes by other trades)? If so, how much?

2. Does this substitution offer earlier delivery or less construction time? How much and why?

3. How does this substitution affect any dimensions, layout, or details of other trades as shown on the Drawings?

4. What are the specific differences between this substitution and the specified item? C. Attach the following items as applicable: Check if applicable

1. Manufacturer’s technical data

2. Laboratory test or performance results

3. Drawings and wiring diagrams of the proposed product

4. Drawings & description of changes required by other trades

5. Samples

6. Manufacturer’s guarantee and maintenance instructions

7. Documentation of code compliance for all specified uses

Page 349 of 519 ends

December 2024 01605 - 6 City of Yuba City
Product Requirements and Substitutions Municipal Well 3 The undersigned agrees to pay for all additional review, design, testing, changes in the Contract Documents and construction as a result of the acceptance of this substitution, at no cost to the City Submitted by (Firm)
Signature Date
Accepted Rejected Revise and Resubmit See attached
By (City / Engineer) Date

Page 350 of 519 ends

December 2024 01770 - 1 City of Yuba City
Contract Closeout Municipal Well 3
SECTION 01770

CONTRACT CLOSEOUT

GENERAL

1.01 SECTION INCLUDES
A. Administrative and procedural requirements for Contract closeout.

1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section:

1. Section 00700 – General Conditions.

1.03 FINAL CLEANING
A. Immediately prior to submittal of a request for inspection for Substantial Completion, clean the project site and make ready for City’s use and occupancy.

B. Employ experienced workers or professional cleaners for final cleaning.

C. Use cleaning materials which are recommended by manufacturers of surfaces to be cleaned.

D. Complete the following cleaning operations:

1. Clean the project site, yard and grounds which were disturbed by construction activities.

Remove rubbish, waste material, litter and other foreign material.

2. Remove all rocks and other non-native materials from agricultural fields used for staging areas and re-grade fields to original or better condition. Employ laser leveling equipment to verify smooth grade free from mounding, depressions, swales or other surface irregularities.

3. Sweep paved areas, remove oil stains, grease, dust and dirt.

4. Remove tools, construction equipment, machinery, storage sheds, temporary fences and surplus material.

5. Broom clean sidewalks.

6. Clean storm drains impacted by construction.

7. Clean and repair landscaped areas impacted by construction.

E. Waste Disposal:

1. Arrange for and dispose of surplus materials, waste products, and debris off-site:
a. Prior to making disposal on private property, obtain written permission from Owner of such property.

2. Do not fill ditches, washes, or drainage ways which may create drainage problems.

3. Do not create unsightly or unsanitary nuisances during disposal operations.

4. Maintain disposal site in safe condition and good appearance.

5. Complete leveling and cleanup prior to final acceptance of the Work

1.04 SUBSTANTIAL COMPLETION
A. General:

1. Comply with procedural requirements for Substantial Completion as specified in Section 00700, General Conditions.

Page 351 of 519 ends

December 2024 01770 - 2 City of Yuba City
Contract Closeout Municipal Well 3
B. Complete final cleaning operations before requesting inspection for Substantial Completion.

C. Prior to requesting inspection for Substantial Completion, complete and submit the following:

1. List of items to be completed or corrected (punch list). Organize list by facility, space, system and piece of equipment.

2. Specific warranties, bonds, maintenance service agreements, final certifications and similar documents.

D. Inspection for Substantial Completion:

1. Engineer, City and Contractor shall jointly walk through and inspect the project site to determine whether the Work is satisfactory and Substantially Complete.

2. The Contractor’s punch list will be reviewed and additional items identified during the inspection requiring corrective actions will be added to the list as determined by the inspection.

1.05 FINAL COMPLETION
A. Final Completion Submittals:

1. At least seven (7) days prior to submitting final Application for Payment, complete and submit the following:

2. Final Project Record Documents.

3. Guaranty, Warranties, and Bonds.

4. Punch List with all corrective actions completed and ready for Final Inspection.

5. Releases from Agreements with property owners or public agencies.

6. Releases or Waivers of Liens, Claims, and Stop Payment Notice as specified in conditions of the Contract.

7. Evidence of final, continuing insurance coverage complying with insurance requirements.

8. Consent of Surety to Final Payment.

B. Final Inspection:

1. Submit written request for final inspection for Project Acceptance.

2. Engineer will either proceed with the inspection or advise Contractor of unfulfilled requirements.

3. Engineer will prepare a final Certificate of Completion after satisfactory inspection of the Work.

1.06 FINAL APPLICATION FOR PAYMENT
A. Following a satisfactory Final Inspection and receipt of a final Certificate of Completion from the Engineer, submit the final Application for Payment in accordance with the procedures and requirements specified in Section 00700, General Conditions.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION

Page 352 of 519 ends

December 2024 01785 - 1 City of Yuba City
Warranties and Bonds Municipal Well 3
SECTION 01785

WARRANTIES AND BONDS

GENERAL

1.01 GUARANTEE OF WORK
A. The Contractor hereby agrees to make, at its own expense, all repairs or replacements necessitated by defects in materials or workmanship, supplied under terms of this Contract, and pay for any damage to other works resulting from such defects, which becomes evident within one (1) year after the date of acceptance of the project or the Substantial Completion date whichever is applicable or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required by the Contract Documents. The Contractor further assumes responsibility for a similar guarantee for all work and materials provided by subcontractors or manufacturers of packaged equipment components. The Contractor also agrees to indemnify, defend, and hold the City harmless from liability of any kind arising from damage due to said defects.

B. The Contractor shall execute and submit a completed Warranty Form provided by the Construction Manager for the Work, and any portion of the Work possessed in accordance with Section 00700-3.04, City’s Right to Use or Occupy. The Warranty Form shall be submitted prior to the Substantial Completion date or the final acceptance of the project or within five (5) days of the occupancy or use of a portion of the Work, whichever is applicable. In addition, the Contractor shall submit the other specified additional warranties, guarantees, and bonds from manufacturers and suppliers.

C. The Contractor shall, upon the receipt of notice in writing from the City, promptly make all repairs arising out of defective materials, workmanship, or equipment. The City is hereby authorized to make such repairs, and the Contractor and its Surety shall be liable for the cost thereof, if ten (10) days after giving of such notice to the Contractor, the Contractor has failed to make or undertake the repairs with due diligence. In case of emergency, where in the opinion of the City delay could cause serious loss or damage, repairs may be made without notice being sent to the Contractor, and the expense in connection therewith shall be charged to the Contractor, and its Surety shall be liable for the cost thereof.

D. Prior to the expiration of the Warranty period, the City reserves the right to hold a meeting and require the attendance of the Contractor. The purpose of the meeting is to review warranties, bonds, and maintenance requirements and determine required repair or replacement of defective items.

E. For the purpose of this paragraph, acceptance of the Work or a portion of the Work by the City, shall not extinguish any covenant or agreement on the part of the Contractor to be performed or fulfilled under this Contract which has not, in fact, been performed or fulfilled at the time of such acceptance. All covenants and agreements shall continue to be binding on the Contractor until they have been fulfilled.

F. The City and the Contractor agree that warranty on the parts of the work possessed and used by the City in accordance with Section 00700-3.04, City’s Right to Use or Occupy, shall commence on the date that the City takes possession of such work and so notifies the Contractor in writing. The City and the Contractor further agree that such possession, and use of the work shall not be deemed as Substantial Completion or acceptance of any other part of the Work.

G. If, after installation, the operation or use of the materials or equipment furnished under this Contract proves to be unsatisfactory to the Construction Manager or City, the City shall have the right to operate and use such materials or equipment until it can, without damage to the City, be taken out of service for correction or replacement. Such period of use of the defective materials or equipment pending correction or replacement shall in no way decrease the

Page 353 of 519 ends

December 2024 01785 - 2 City of Yuba City
Warranties and Bonds Municipal Well 3
guarantee period required for the acceptable corrected or replaced items of materials or equipment.

H. Nothing in this Section shall be construed to limit, relieve or release the Contractor's, subcontractor's and equipment supplier's liability to the City for damages sustained as the result of latent defects in the equipment furnished caused by the negligence of the supplier's agents, employees or subcontractors. Stated in another manner, the warranty contained in this Section shall not amount to nor shall it be deemed to be a waiver by the City of any rights or remedies (or time limits in which to enforce such rights or remedies) it may have against the supplier of the equipment to be furnished under these Specifications for defective workmanship or defective materials under the laws of this State pertaining to acts of negligence.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION

Page 354 of 519 ends

1 Specifications for the City of Yuba
City Well No. 3
Prepared for
By
December 2024

Page 355 of 519 ends

2 SECTION TABLE OF CONTENTS
Contents

1. GENERAL................................................................................................................... 1

1.1. References ................................................................................................................. 1

1.2. General Requirements............................................................................................... 1

1.2.1. Purpose and Scope of Work .................................................................................................1

1.2.2. Design Criteria and Performance Requirements ..................................................................4

1.2.3. Other Data.............................................................................................................................5

1.2.4. Termination and Alternative Well ..........................................................................................5

1.2.5. Contractor's Experience and Equipment...............................................................................5

1.2.6. Drilling Fluids.........................................................................................................................5

1.2.7. Water for Drilling....................................................................................................................6

1.2.8. Nuisance Water and Drill Cuttings ........................................................................................6

1.2.9. Records and Forms...............................................................................................................6

1.2.10. Supervision............................................................................................................................7

1.2.11. Construction Inspection.........................................................................................................7

1.2.12. Notifications and Permits ......................................................................................................8

1.2.13. Project Site and Well Security...............................................................................................8

1.3. Submittals: General................................................................................................... 8

1.3.14. Submittals: Materials.............................................................................................................9

2. WELL CONSTRUCTION MATERIALS ......................................................................10

2.1. Materials ....................................................................................................................10

2.1.1. Conductor Casing................................................................................................................10

2.1.2. Grout ...................................................................................................................................10

2.1.3. Casing Assembly.................................................................................................................11

2.1.4. Gravel Envelope..................................................................................................................12

2.1.5. Disinfection Agent ...............................................................................................................12

3. WELL CONSTRUCTION AND TESTING ...................................................................12

3.1. Mobilization...............................................................................................................12

3.1.1. General................................................................................................................................12

3.1.2. Reverse Rotary Drilling Equipment.....................................................................................13

3.1.3. Noise Mitigation Measures..................................................................................................13

3.2. Conductor Casing Installation .................................................................................13

3.2.1. Scope ..................................................................................................................................13

3.2.2. Construction Methods .........................................................................................................13

3.3. Test Hole Drilling ......................................................................................................14

3.4. Discrete Zone Sampling ...........................................................................................15

3.4.1. Scope ..................................................................................................................................15

3.4.2. Construction Method ...........................................................................................................15

3.5. Borehole Reaming ....................................................................................................17

3.5.1. Scope ..................................................................................................................................17

3.5.2. Construction Method ...........................................................................................................17

3.6. Installation of Well Casing, Screens, Gravel Fill Pipe, and Sounding Pipe ..........20

3.6.1. Scope ..................................................................................................................................20

3.6.2. Construction Method ...........................................................................................................20

3.7. Gravel Envelope and Annular Seal Installation ......................................................22

3.7.1. Scope ..................................................................................................................................22

3.7.2. Gravel Packing Method.......................................................................................................22

Page 356 of 519 ends

3 3.7.3. Annular Sealing Method......................................................................................................23

3.8. Well Development.....................................................................................................23

3.8.1. Scope ..................................................................................................................................23

3.8.2. Discharge of Initial Development Water..............................................................................24

3.8.3. Discharge of Pump Development/Testing Water................................................................24

3.8.4. Equipment ...........................................................................................................................24

3.8.5. Development Methods ........................................................................................................25

3.8.6. Well Performance Requirements ........................................................................................27

3.9. Well and Aquifer Testing..........................................................................................27

3.9.1. Scope ..................................................................................................................................27

3.9.2. Test Pumping Procedures...................................................................................................27

3.9.3. Dynamic Flowmeter (Spinner) Survey ................................................................................28

3.9.4. Water Samples....................................................................................................................29

3.9.5. Records ...............................................................................................................................29

3.10. Plumbness and Alignment Testing..........................................................................29

3.10.1. Scope ..................................................................................................................................29

3.10.2. Methods...............................................................................................................................30

3.11. Video Survey.............................................................................................................30

3.12. Disinfection of Well...................................................................................................30

3.13. Well Head Completion ..............................................................................................31

3.14. Well Performance Requirements .............................................................................31

3.15. Rejected Well ............................................................................................................32

3.15.1. Non-Payment ......................................................................................................................32

3.15.2. Well Sealing ........................................................................................................................32

3.15.3. Construction of Replacement Well......................................................................................32

3.16. Destruction of Well ...................................................................................................32

3.16.1. General................................................................................................................................32

3.16.2. Methods...............................................................................................................................32

3.17. Standby Time ............................................................................................................33

3.18. Site Clean-up and Records ......................................................................................33

3.18.1. Cleanup ...............................................................................................................................33

3.18.2. Records ...............................................................................................................................33

4. Measurement and Payment......................................................................................33

4.1. Measurement and Payment......................................................................................33

4.1.1. Well Site Mobilization (Bid Item 1) ......................................................................................33

4.1.2. Sound Walls (Bid Item 2) ....................................................................................................34

4.1.3. Conductor Casing (Bid Item 3)............................................................................................34

4.1.4. Pilot Borehole Drilling (Bid Item 4) ......................................................................................34

4.1.5. Geophysical Logging (Bid Item 5).......................................................................................34

4.1.6. Zonal Sampling (Bid Item 6)................................................................................................34

4.1.7. Borehole Reaming (Bid Item 7)...........................................................................................35

4.1.8. Blank Well Casing (Bid Items 8)..........................................................................................35

4.1.9. Wire Wrapped Well Screen (Bid Item 9) .............................................................................35

4.1.10. Sounding Pipe (Bid Item 10) ...............................................................................................35

4.1.11. Gravel Fill Pipe (Bid Item 11) ..............................................................................................35

4.1.12. Gravel Envelope (Bid Item 12)............................................................................................36

4.1.13. Annular Seal (Bid Item 13)..................................................................................................36

4.1.14. Well Development (Bid Item 14) .........................................................................................36

4.1.15. Install and Remove Test Pump (Bid Item 15) .....................................................................36

Page 357 of 519 ends

4 4.1.16. Well and Aquifer Testing (Bid Item 16) ...............................................................................36

4.1.17. Plumbness and Alignment Testing and Video Surveys (Bid Item 17) ................................36

4.1.18. Dynamic Flowmeter (Spinner) Testing (Bid Item 18).........................................................37

4.1.19. Disinfection of Well (Bid Item 19)........................................................................................37

4.1.20. Disposal of Drill Cuttings (Bid Item 20) ...............................................................................37

4.1.21. Well Standby Time (Bid Item 21) ........................................................................................37

Page 358 of 519 ends

1 1. GENERAL

1.1. References
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. The most recently published edition of each of the reference standards applies. • AWS - American Welding Society
• ASTM - American Society of Testing and Materials
• NSF/ANSI - Standard 60, Drinking Water Treatment Chemicals • NSF/ANSI 61 - Drinking Water System Components – Health Effects • API - Standard 13-A, Drilling Fluid Materials, American Petroleum Institute • API - Standard 13-B, Recommended Practice Standard Procedure for Field Testing OilBased Drilling Fluids • ANSI/AWWA - A100-20 Water Wells
• Water Well Standards, State of California; Bulletin 74-90 (Supplement to Bulletin 74-81) June 1991 or latest applicable edition/revision.

1.2. General Requirements

1.2.1. Purpose and Scope of Work

1.2.1.1. Purpose
The water supply well to be constructed under this Contract and in accordance with these Technical Provisions is intended for use as both a drinking water supply well and a water injection well (Aquifer Storage and Recovery Well). The well site and well to be constructed are summarized below:

The well site is located at the Yuba City (City) Water Treatment Plant, which is located at 701 Northgate Drive, Yuba City, California, as depicted in the plans. Information from numerous existing wells located at the City Treatment Plant was used for preliminary well design information.

The design capacity of the well is tentatively 2,500 gpm. The well will be constructed of 18-inch diameter stainless-steel casing, and stainless-steel wire wrapped well screen with a slot size of

0.060-inches to a depth of 530 feet. The well assembly will be installed in a 36-inch diameter borehole drilled to a depth of approximately 600 feet.

1.2.1.2. General
A. The work consists of furnishing all required permits, materials, labor, equipment, fuel, tools, transportation, and services for the drilling, construction, development, testing, and completion of a water supply well, all in accordance with these Technical Provisions.

B. Other work by the Contractor shall include keeping records of all construction activities,

Page 359 of 519 ends

2 including time-drilling and work logs; capping of the well casing and cleaning and restoration of the well site upon completion of work; and performing all necessary tasks for the safe and efficient construction and completion of the well specified in these Technical Provisions. The Contractor shall make available to the Engineer all daily drilling and work records, as well as other specific information listed in these specifications, for the construction activities that are a part of this Contract.

C. The Owner is:

City of Yuba City
1201 Civic Center Boulevard
Yuba City, CA 95993
Contact Person: William Jow
Telephone: (530) 822-4638
Email: [email protected]
D. The Engineer is:

Luhdorff and Scalmanini, Consulting Engineers
500 First Street
Woodland, CA 95695
Contact Person: Mr. Eddy Teasdale, P.G., C.HG
Telephone: (530) 661-0109
Cellular Telephone: (530) 419-9484
Email: [email protected]
The Engineer is the Owner's agent with respect to design, project coordination, and inspection.

1.2.1.3. Services Provided the Owner
The owner has obtained the necessary legal right-of-way for the drilling and well construction work.

1.2.1.4. Work Area Restrictions
A. General -- The Contractor shall protect all existing facilities and shall keep the site clear and open at all times.

B. Coordination with Other Activities -- The Contractor is advised that other work may be conducted at the project site. The Contractor shall limit all activities to the designated work areas at the site.

C. Work Hours – 24-hour operations for drilling and construction of the well are allowed.

D. Traffic Control—The Contractor shall exercise caution and provide adequate traffic control when entering or exiting the project site. The Contractor shall provide and arrange all traffic control signage as required by project permits and accepted safety practices.

E. Health and Safety -- Contractor shall provide and adhere to a health and safety plan to address actual or potential hazards associated with the Work. A copy of the Contractor’s health and safety form shall be posted at the job site.

F. Hazardous Materials -- The Contractor shall comply with all government laws, rules, and regulations concerning the use of hazardous materials and the disposal of hazardous

Page 360 of 519 ends

3 wastes at the job site, including but not limited to the following:

1. The Contractor shall not bring hazardous materials onto the job site or deliver hazardous materials without providing the Engineer with Material Safety Data Sheets for each hazardous material in advance.

2. All hazardous materials shall be stored and used safely and according to the manufacturer's recommendations.

3. Any hazardous products, waste, or empty containers used or generated shall be properly and legally disposed of and shall not be poured down any drain or sewer nor disposed of in any trash container or dumpster.

4. The Contractor will be considered the hazardous waste generator and will be responsible for the legal transport and disposal of all hazardous waste. No containers or trash will be left on any job site.

5. Violation of any of the above methods shall be sufficient cause for the Engineer to stop all work. Any expense incurred by the Engineer caused by the work stoppage will be borne by the Contractor. These expenses will include all costs to return the job site and all other areas contaminated by the Contractor to a hazard-free condition.

6. The Contractor will be solely responsible for all the costs, including fines and penalties, the investigation and cleanup of any suspected hazardous materials the Contractor used, left on the job site, or disposed of through a municipal drain or sewer, and any damage to property and/or injury to any person.

1.2.1.5. Water Well Construction and Testing
A. The proposed well site is located in Sutter County in Yuba City, as shown in the Plans.

B. Time is of the essence for this project. The Contractor shall mobilize, construct, and test the well within the timeframe set forth in the Contract Documents. Failure to do so will result in sufficient hardship and possible financial loss to the Owner.

C. Depth to first encountered ground water at the project site is estimated to be approximately 30 feet below ground surface (bgs).

D. The construction of the well structures shall consist of the following steps:

1. Drilling a conductor borehole and grouting in place a steel conductor casing as specified in the Plans.

2. Establishing and maintaining a drilling fluid program to maintain borehole stability, transport cuttings to the surface, and mitigate flowing groundwater conditions.

3. Drilling a minimum 17.5-inch diameter borehole beneath the conductor casing.

4. Performing geophysical, borehole diameter, and gyroscopic surveys in the completed borehole.

5. Perform groundwater zone sampling of no more than three zones.

6. Reaming the borehole to the final specified diameter.

7. Installing a casing assembly consisting of blank well casing and well screen, all as specified in the final well design.

Page 361 of 519 ends

4 8. Equipping the casing with centralizers to ensure that the casing assembly is centered in the borehole.

9. Installing two; 2-inch diameter, Schedule 40 Type 304, stainless steel pipe where it will enter the well casing to serve as a still well for measuring water levels in the well as specified in the Plans.

10. Installing two; 3-inch diameter, Schedule 40 BSP steel pipe to be used as a gravel fill pipe as specified in the Plans.

11. Conditioning of the drilling fluids for casing installation and gravel packing.

12. Installing a graded gravel envelope between the well casing and borehole wall from the bottom of the production borehole to the depth specified in the Plans by the tremie pipe method.

13. Placement of sand/cement annular seal from the top of the gravel envelope to ground surface as specified in the plans by the tremie pipe method.

F. Initial development of the well shall consist of open-ended airlift pumping from the sump and a combination of airlift pumping and swabbing, through the screened intervals. An engine-driven deep well turbine pump shall be temporarily installed for final well development and testing. For bidding purposes, the temporary pump shall be installed to a depth of 250 feet.

The pump and engine shall be capable of pumping 150 percent of the well’s design capacity. The final development methods shall include frequent surging and shall proceed until the well satisfies performance requirements concerning sand content and well efficiency, as specified herein.

G. After final development and when the well meets the specified performance requirements, pumping tests will be performed, including an 12-hour step test with steps at 50, 75, 100, 125, and 150 percent of the final design capacity of the well and an 8-hour constant rate discharge test at the final design capacity. The final design capacity of the well will be determined by the Engineer based on the evaluation of well performance during the step test.

1.2.2. Design Criteria and Performance Requirements
The design of the subject well includes specifications for screen intake locations, slot size and gravel pack gradation for sand control, sealing for sanitary and other water quality concerns, and consideration of other structural requirements. The specified design does not relieve the Contractor of the performance requirements that are a part of these Technical Provisions. Should the Contractor feel that the design furnished by the Owner will affect Contractor’s ability to achieve the performance requirements based upon the Contractor's interpretation of the formation samples obtained during the drilling of the production well, the Contractor shall, within 24 hours following completion of the drilling of the borehole, inform the Owner of Contractor’s concerns and furnish a written report to the Engineer specifying alternate recommendations for completion of the well which would satisfy these Technical Provisions and the performance requirements herein.

The alternate recommendations shall include the Contractor’s estimate of the yield that will be obtained, sieve analyses of the formation samples, the material settings, the size of screen openings, and the type and grading of gravel material to be used for a gravel envelope.

Page 362 of 519 ends

5 1.2.3. Other Data
Information for existing wells in the vicinity of the proposed well has been reviewed to determine their current yield (i.e., pumping capacity), drawdown, and specific capacity. The Contractor may inspect and evaluate all information concerning the existing wells upon written request to the Engineer. This information will be made available solely for the purpose of assisting with the bidding process and is not intended to relieve the Contractor of any responsibility to perform the work under the terms of these Technical Provisions.

1.2.4. Termination and Alternative Well
The Owner reserves the right to terminate the work on the well at any time. In such an event, the Contractor shall be paid for work completed at that time on the basis of the unit bid prices. The Owner reserves the right to select an alternate well site to replace an abandoned well. If the Owner chooses an alternate site, the Contractor shall be paid for the work done on the alternate well on the basis of the unit bid prices.

1.2.5. Contractor's Experience and Equipment

1.2.5.1. Contractor’s Experience
The Contractor must have successfully completed at least five projects of similar size and scope within the past five years, subject to the Owner's evaluation and approval.

1.2.5.2. Contractor’s Equipment
The water supply well to be drilled in accordance with these Technical Provisions shall be drilled by the reverse rotary drilling method, with drilling equipment in good condition and of sufficient capacity to drill the hole required by these Technical Provisions. All drilling equipment, including mast and draw works, air compressors, drilling fluid pumps, drill pipe, etc., must be of requisite size, sufficient capacity, and suitable condition to drill and set casing to the specified depth.

1.2.6. Drilling Fluids

1.2.6.1. Drilling Fluid Control Program
A. A drilling fluid control program shall be submitted and approved by the Engineer prior to the commencement of drilling operations. Selection and use of the drilling fluid materials shall be a part of this Contract. The Contractor shall be responsible for maintaining the quality of the drilling fluid to ensure the protection of water-bearing and potential waterbearing formations exposed in the borehole and the ability to obtain representative samples of the aquifer materials encountered during the drilling process. The Contractor shall use fresh, non-polluted water from the approved source to prepare the drilling fluid.

Any modification of the approved drilling fluid control program shall first be approved by the Engineer.

B. The Contractor shall submit, for approval by the Engineer, a list of all additives that will be employed or are anticipated to be used during the drilling operations prior to the commencement of drilling. Drilling fluid additives shall meet or surpass Standard 13-A, Drilling Fluid Materials, American Petroleum Institute. All drilling fluid additives must comply with recognized industry standards and practices, and they must be applied and used as prescribed by the manufacturer. Toxic or dangerous substances shall not be added to the drilling fluid. The disallowance of any material by the Owner prior to or during

Page 363 of 519 ends

6 construction of the well will not relieve the Contractor of the responsibility to complete the drilling program as defined in these Technical Provisions.

1.2.6.2. Failure to Maintain Proper Control
Proper control of the drilling fluid must be maintained to the satisfaction of the Engineer.

The Contractor will be required, at the Contractor's expense, to retain or employ an experienced, qualified drilling fluid engineer to supervise and maintain the drilling fluid properties if such control cannot be accomplished by the Contractor to the satisfaction of the Engineer.

1.2.6.3. Non-Compliance
If at any time the drilling fluid does not comply with these Technical Provisions or the approved recommendations of a drilling fluid engineer, the drilling fluid shall be reconditioned and tested until the drilling fluid obtains the specified characteristics. If proper drilling fluid properties cannot be maintained, the drilling fluid shall be replaced at the Contractor's expense.

1.2.7. Water for Drilling
The Contractor is responsible for arranging for an approved water source for drilling and well construction. Water for drilling will be available at the project site via an existing hydrant located within 1,300 feet of the proposed well location. The Contractor is responsible for supplying the necessary equipment for delivering the water from the connection point to the drilling location.

The Contractor shall obtain a permit for potable water for drilling and well construction in accordance with Section 6-6.18 of the City of Yuba City Municipal Code. The City’s water meter use application is provided in Attachment C. Water used for well construction and human consumption shall be kept free from contamination and shall conform to the requirements of the federal, state and local authorities for potable water and water well drilling.

1.2.8. Nuisance Water and Drill Cuttings
• Nuisance Water—Nuisance water, such as rainfall or surface runoff, may occur at the well site during the period of construction under this contract. The Contractor shall at all times protect the Work from damage by such waters and shall take all due measures to prevent delays in the progress of the Work caused by such waters. • Drill Cuttings—The Contractor may stockpile drill cuttings at the site as directed by the Engineer before they are spread onsite at a final location determined by the Owner.

1.2.9. Records and Forms
The Contractor shall maintain current records on the site at all times to show:

A. Time, depth, and results of all drilling fluid tests.

B. All materials added to the system, kind, amount, time and depth.

C. Variances or modifications from the agreed-to drilling fluid program; time, depth, reason for variance/modification, and authorization.

Page 364 of 519 ends

7 1.2.10. Supervision
The Contractor shall designate one person who will have full decision-making authority to represent the Contractor on a daily basis at the project site.

1.2.11. Construction Inspection

1.2.11.1. General
The Contractor will be required to contact the Engineer at various stages of construction for the purpose of construction inspection. The Contractor shall perform no work until the Engineer has made such inspections. The Contractor shall notify the Engineer at least 24 hours prior to each of the required inspections to ensure that a representative will be available to conduct the inspection.

1.2.11.2. Inspection Items
The following is a list of required inspection items. Inspection and approval of each item by the Engineer are required before proceeding to a subsequent stage of the project.

Description Item
1) Mobilization Equipment (Drilling Equipment and
Accessories), Site layout, Sound Walls, Storm
Water Prevention Measures, Sanitary Facilities
2) Construction Materials Drilling Fluid Additives
Casing and Screen Sections
Gravel Fill Pipe, Sounding Pipe, and Sounding
Pipe Inlet Structure,
Gravel
3) Drilling
4) Zonal Sampling
Drilling Fluid Properties
Geophysical, Caliper, and Borehole Geometry
Survey
Zone Construction and Development
Groundwater Sampling
5) Construction Conductor Casing Installation
Casing Assembly Installation
Gravel Fill and Sounding Tube Installation
Gravel Envelope Installation
Seal Placement
6) Plumbness and Alignment Equipment
Testing
7) Well Development Swabbing Tool
Pumping Equipment
Discharge Assembly

Page 365 of 519 ends

8 Description Item
8) Well Testing Sand Test
Well and Aquifer Tests
Video Survey
Plumbness and Alignment Testing
9) Disinfection Disinfection Agent
Disinfection
10) Final Casing Stick-up and Security
Site Clean-up

1.2.11.3. Access for Inspection
Contractor shall provide safe access to all areas of the work site and to allow for permit inspection by the Engineer at all times.

1.2.12. Notifications and Permits
It shall be the Contractor’s responsibility to obtain the appropriate well permits and to satisfy all requirements of that permit. The well permitting agency for this project is:

Sutter County – Developmental Services Department
1130 Civic Center Boulevard, Suite A
Yuba City, CA 95993
(530) 822-7400
The Contractor shall provide the Engineer with completed permit applications for review and approval before submission to the permitting agency.

The Contractor shall notify the Engineer and the appropriate regulatory agencies in advance of the start and completion of the well.

1.2.13. Project Site and Well Security
The Contractor shall provide, at all times during well construction, suitable means of protecting the well bore and casing assemblies, when installed, from the entrance of foreign objects and from vandalism.

1.3. Submittals: General
The Contractor shall submit the following general submittals as part of a single package to the Engineer before mobilization to the project site.

A. A description of the drilling equipment including rig manufacturer, model, mast height, capacity, maximum casing length, and drill pipe diameter, length, and connection type.

B. A construction schedule for well construction and testing.

C. A site plan of the drilling location delineating the location and size of the drilling rig and related support equipment, tank locations, access roads, casing and gravel storage, sanitary facilities, drill cuttings stockpile, and site trash storage.

D. A storm water protection program and plan.

Page 366 of 519 ends

9 E. The Contractor's daily report form.

F. A health and safety plan.

G. A list of supervisory personnel who will be responsible for the performance of all work associated with the Contract. The list will include the phone numbers where the personnel may be reached by the Engineer.

H. List of proposed subcontractors.

I. A drawing illustrating the tools, equipment, and discharge piping to be used during the zonal sampling operations.

J. A drawing delineating the size, location, and plumbing arrangement of the equipment to be used during the gravel packing operations.

K. A drawing illustrating the tools, equipment, and discharge piping to be used during the well development operations.

L. The Contractor’s estimates of the volumes of gravel and sealing material required to fill the theoretical annular spaces in the well in accordance with the specified design.

M. A proposed drilling fluid control program.

1.3.14. Submittals: Materials
The Contractor shall submit certificates of compliance for the following materials for approval by the Engineer. No material shall be incorporated into the work until certificates of compliance have been approved in writing by the Engineer.

A. Conductor Casing
B. Sand Cement Grout
C. Blank Production Well Casing
D. Production Well Screen
E. Sounding Pipe
F. Gravel Fill Pipe
G. Gravel Envelope Material
H. Sieve Analysis of the Gravel Pack material.

I. Disinfection Agent

1.3.14.1. Product Submittal Requirements
A. Certificates of compliance from the Contractor, suppliers, and/or manufacturers, shall clearly indicate that the material to be delivered to the job site will meet all requirements of these Technical Provisions. A certificate of compliance shall include, but not be limited to, the project title, delivery location, date (or approximate date) of delivery, name of the material with appropriate classification or model numbers, quantity, name of the manufacturer, statement of compliance with all requirements of the Technical Provisions, and the name, title, and signature of the certifying agent.

B. NSF/ANSI 60/61 certifications shall be submitted for each material used in the drilling of the borehole or construction of the well.

Page 367 of 519 ends

10 C. A factory or mill certification (laboratory test report) shall be submitted with the certificates of compliance for all components of the casing assembly. The factory or mill certification shall not be a substitute for the certificate of compliance unless it contains all information required for a certificate of compliance as described above.

D. Insufficient, incomplete, or unclear certificates will be rejected, and the Contractor shall be responsible for all delays caused by any need for re-submittal. Said delays will not serve as a condition for awarding additional workdays for determining liquidated damages.

2. WELL CONSTRUCTION MATERIALS

2.1. Materials
All materials provided by the Contractor to be incorporated into the work shall be new.

2.1.1. Conductor Casing
A. Conductor Casing and Collars - The conductor casing for the well shall be manufactured of ASTM A-139 Grade B steel. Conductor Casing shall have the following dimensions:
40-inch O.D. x 1/2-inch wall
Collars, if utilized, shall be of the same thickness and have the same physical and chemical properties as the casing, 5 inches minimum in width, shall be rolled to fit the outside diameter, and shall be circumferentially welded to the casing section. The inside edge of the collars shall be ground or sufficiently scarfed to remove sharp edges, burs, and welds. Alignment holes shall be provided in each collar to ensure proper matching of the sections. The male end of the casing section shall be ground to remove the excess welding bead for a distance of 4 inches to permit the casing section to enter the collar during field assembly without binding.

B. Alignment - All casing section ends shall be flat and perpendicular to the axis of the casings. Longitudinal welds shall be ground flush, and the inside of the collar and outside of the casing sections shall be de-burred and fitted prior to assembly. The ends of all sections shall not vary more than 0.010 inches at any point from a true plane perpendicular to the casing.

C. Centralizers - Centralizers shall be manufactured of the same material thickness as the casing. They shall be a minimum of 2 inches in width and 30 inches in length and shall be angled to provide a minimum 2-1/2-inch offset between the casing and borehole wall. Each centralizer strip shall provide at least a 1-foot length of bearing surface at the bore interface. A minimum of 4 centralizers shall be provided at each location for centering the casing. Centralizers shall be placed on the conductors five feet below ground surface and five feet from the bottom of the conductor.

D. Roundness - The casing shall be round such that neither the largest nor smallest outer diameter differs from that specified to the equivalent of less than or equal to one percent ellipticity.

2.1.2. Grout
The grouting material shall consist of a sand-cement mixture as described by California Department of Water Resources Well Standards, Bulletin 74-81/Supplement 74-90. The cement shall be Type I or II as defined by the Standards. The mixture shall conform to State standards

Page 368 of 519 ends

11 and local ordinances (well permitting agency) for sanitary seals.

2.1.3. Casing Assembly
The casing assembly consists of blank well casing, screen intake section, and external sounding and gravel fill pipes. The Contractor shall provide materials and components that are compatible with field assembly.

A. Blank Well Casing

1. The blank well casing shall be as specified below and as shown in the Plans.

2. For field assembly, the ends of casing sections shall be furnished with collars. Collars shall be of the same thickness and have the same physical and chemical properties as the corresponding casing section, shall be 5 inches minimum in width, shall be rolled to fit the outside diameter, and shall be circumferentially welded to the casing section. The inside edge of the collars shall be ground or sufficiently scarfed to remove sharp edges, burs, and welds. Alignment holes shall be provided in each collar to ensure proper matching of the sections. The male end of the casing section shall be ground to remove the excess welding bead for a distance of 4 inches to permit the casing section to enter the collar during field assembly without binding.

B. Wire Wrapped Well Screen

1. Wire wrapped well screen and attached end fittings shall be as specified below and as shown in the Plans and shall be fabricated from ASTM A-778 Type 304 stainless steel.

The well screen shall be manufactured by Roscoe Moss Company, Johnson Screens, or approved equal. The screen sections shall be furnished with collars of the same material as the screen body and with the tolerances specified for blank well casing.

2. The width of the well screen slots shall be 0.060 inches

3. For field assembly, the ends of casing sections shall be furnished with collars. Collars shall be of the same thickness and have the same physical and chemical properties as the corresponding casing section, shall be 5 inches minimum in width, shall be rolled to fit the outside diameter, and shall be circumferentially welded to the casing section. The inside edge of the collars shall be ground or sufficiently scarfed to remove sharp edges, burs, and welds. Alignment holes shall be provided in each collar to ensure proper matching of the sections. The male end of the casing section shall be ground to remove the excess welding bead for a distance of 4 inches to permit the casing section to enter the collar during field assembly without binding.

4. The blank well casing and intake screen shall be manufactured by the same source to ensure compatibility for field assembly.

C. Alignment - All casing section ends shall be machined flat and perpendicular to the axis of the casings. Longitudinal welds shall be ground flush, and the inside of the collar and outside of the casing sections shall be de-burred and fitted prior to assembly. The ends of all sections shall not vary more than 0.010 inches at any point from a true plane perpendicular to the casing.

D. Centralizers - Centralizers shall be manufactured of the same material thickness as the

Page 369 of 519 ends

12 casing. They shall be a minimum of 2 inches in width and 30 inches in length and shall be angled to provide a 5-inch offset between the casing and borehole wall. Each centralizer strip shall provide at least a 1-foot length of bearing surface at the bore interface. A minimum of 4 centralizers shall be provided at each location for centering the casing.

E. Roundness - The casing shall be round such that neither the largest nor smallest outer diameter differs from that specified to the equivalent of less than or equal to one percent ellipticity.

F. Bottom Plate - The bottom end piece of the casing assembly shall be secured by a SEtype head of the same thickness and material as the blank well casing.

G. Sounding Pipe – Two-inch Schedule 40, Stainless Steel pipe, in random lengths, shall be furnished for the installation of the sounding pipe to the specified depths. The sounding pipe shall be furnished with collars for assembly by welding.

H. Gravel Fill Pipe - Three-inch Schedule 40 Stainless Steel pipe, in random lengths, shall be furnished for the installation of the gravel fill pipe to the specified depths. The gravel fill pipe shall be assembled by butt welding.

2.1.4. Gravel Envelope
The gravel envelope for the well shall consist of glass beads manufactured by Johnson Screens, SiLi, or approved equal.

The gradation of the pack material shall conform to that published by the manufacturer and shall consist of washed, rounded silica material. The gravel shall be delivered to the well site and stored in super sacks. Upon delivery to the well site, the Engineer will inspect and verify that the gravel meets the specified type and gradation before it is installed in the well. Failure to meet the specified gradation shall be grounds for rejection of the delivered gravel material. The gravel shall be protected at the job site and kept free of all foreign matter.

2.1.5. Disinfection Agent
Liquid sodium hypochlorite shall be used to disinfect the gravel pack material. The disinfectant shall be delivered to the site in original unopened containers bearing the manufacturer’s label indicating the percentage of available chlorine. Liquid sodium hypochlorite shall not be stored for more than 60 days after the manufactured date prior to use. During secured storage, disinfectants shall not be exposed to the atmosphere or to direct sunlight.

3. WELL CONSTRUCTION AND TESTING

3.1. Mobilization

3.1.1. General
A. Mobilization shall include transportation of personnel, equipment, and operating supplies to and from the site; providing portable sanitary facilities; providing approved fencing or barricades suitable to keep unauthorized personnel away from construction activities around the site; providing site security, providing pumping equipment, discharge lines, and other necessary facilities at the site; and other preparatory work at the site for the

Page 370 of 519 ends

13 Contractor to conduct the specified work.

B. The Contractor shall provide a complete reverse rotary drilling unit; all tools, accessories, power, fuel, materials, supplies, lighting, piping, and other equipment; and experienced personnel necessary to conduct safe and efficient drilling operations. The drilling unit shall be in good condition and of such capacity as to drill the borehole required by these Technical Provisions. All drilling equipment shall be thoroughly steam cleaned prior to performing any work on the project.

3.1.2. Reverse Rotary Drilling Equipment
A. The drilling equipment shall be equipped with a dial reading weight indicator suitable for reading the weight of the drilling string and the casing loads.

B. Tanks shall be used for circulation of drilling fluids during drilling and construction of the well as specified below. The volume of the tanks shall be at least 100% the volume of the borehole.

3.1.3. Noise Mitigation Measures
Temporary sound attenuation (sound walls) is required for this project. For the purposes of bidding, it is assumed that 250 feet of sound walls will be needed on the north side of the drill site.

3.2. Conductor Casing Installation

3.2.1. Scope
This item shall consist of drilling of a borehole, furnishing and installing conductor casing, and grouting it into place for each well.

3.2.2. Construction Methods
The Contractor shall drill a 48-inch diameter borehole to a depth of 50 feet.

The conductor borehole shall be drilled using the bucket auger drilling method.

A. Centralization - Care shall be taken to install the casings plumb. A set of four centralizer strips shall be attached on 90 degrees spacing at each centralizer location. The centralizers shall be attached directly to the casing by welding in order to center and hold the casing in the proper position until grouting is completed. Centralizers shall be installed at 5 feet from the top, at the center of the string, and 5 feet from the bottom.

B. Grouting

1. Grouting operations shall comply with State and local ordinances.

2. Cement grout shall be pumped into the annular spaces by means of a tremie pipe.

The tremie pipe must be set within five (5) feet of the bottom of the borehole at the start of the placement. The tremie pipe may be raised during seal placement to avoid excessive pump pressures on the casing. The end of the tremie pipe must remain submerged in grout, and the tremie pipe shall be kept full of grout at all times during the seal placement. Upon completion of the sealing operation, grout shall be visible above the surface of the ground outside the casing.

Page 371 of 519 ends

14 3. The grout shall be placed in one continuous lift for each casing string. The Contractor shall keep the inside of the casing full of water during the sealing operation.

4. After grouting operations are completed, the well shall be secured and left undisturbed. Work shall not resume until 24 hours have elapsed.

3.3. Test Hole Drilling
Purpose -- The test hole shall serve to evaluate the lithologic character of subsurface formations and aquifers at the candidate well site and to determine characteristics of the aquifer materials through geophysical surveys and measurements.

A. Scope -- The test hole shall be drilled using the direct rotary method. The hole shall be drilled at a minimum diameter of 17.5 inches. The final depth of the test hole will depend on the lithology encountered while drilling and will be determined by the Engineer. It is anticipated that the final test hole depth will be 600 feet bgs.

B. Methods

1. The test hole shall be drilled using the reverse rotary drilling method of construction. The drilling fluid for the reverse rotary drilling operation shall conform to the specifications in Section 3.5.2 Construction Method, D. Drilling Fluid Program.

2. The drilling operations shall be conducted using equipment that is adequate to reach the depth and perform the evaluations specified in the Technical Provisions. If, in the opinion of the Engineer, the Contractor's equipment is not capable of satisfactorily performing the specified work, the Contractor, at his/her own expense, shall substitute equipment that is satisfactory to the Engineer.

3. The Contractor shall take all measures necessary to protect the top portions of the test hole from caving or raveling.

4. The Contractor shall keep records providing the following information:
a) A record of construction activities for each shift.
b) A time drilling log of the test hole recording the time (in minutes) required to drill down each section of the drill pipe.
c) A log of drilling bit types and depths of changes.
d) Record of drilling fluid properties at 4-hour intervals during drilling operations. The record shall show drilling fluid weights, Marsh Funnel viscosity, sand content, drilling fluid losses, and any additives used. e) A drilling log that defines and classifies the type of formations encountered during the drilling. The log will consist of the depth at which each change in formation is encountered, the classification of the material encountered, its color, and particle size. Classification of silt, sand, gravel, cobbles, etc., shall be based

Page 372 of 519 ends

15 on the size of the material encountered in accordance with the established and accepted geologic standard for the classification of these materials. If more than one size of the material is encountered in a formation such as "sand and clay," an estimate of the quantity of each shall be recorded, such as "20% sand, 80% clay". f) All measurements for depth shall be referenced to the existing ground surface at the well site.

5. During the drilling of the test hole, the Contractor shall collect representative samples of the rotary drill cuttings at 10-foot intervals and at formation changes. The Engineer may direct the Contractor to collect samples at more frequent intervals if deemed appropriate.

The samples collected shall not be washed. They shall be carefully drained of excess drilling fluid but in a manner that will preserve the finer particle size of the sample. Each sample taken shall be preserved in quart-size “Zip-Lock” plastic freezer bags and marked as to date, depth, and well number. The samples shall be properly stored by the Contractor in a manner as to prevent breakage or loss until they are accepted by the Engineer.

6. Upon completion of the test hole drilling, a geophysical log shall be conducted according to Section 3.5.2 Construction Method, E. Geophysical Log.

3.4. Discrete Zone Sampling

3.4.1. Scope
Upon drilling to the final depth and completion of geophysical logging, up to three (3) discrete zones will be selected by the Engineer for zone sampling. This section includes the construction of temporary isolated zones for the evaluation of aquifer properties, and air lifting to approximate the yield of the aquifer at each isolated zone.

3.4.2. Construction Method
The contractor shall commence zonal sampling with the deepest zone selected and proceed progressively to shallower zones until all specified zones have been tested. Procedures for zone construction and testing include:
1) Install a slotted sampling tool to a specified depth. 2) Fill the borehole annulus with gravel pack materials (coarse-grained sand or pea gravel, as approved by the Engineer) to a depth of approximately 30 feet below the lowest slot of the sampling tool or as specified by the Engineer.

Gravel pack shall be installed via tremie pipe methods. 3) Install a 10-foot-thick lower bentonite chip seal in the annulus above the gravel pack via tremie pipe.
4) Install gravel pack materials via tremie pipe above the lower bentonite chip seal to a depth of approximately 20 feet above the upper slots of the

Page 373 of 519 ends

16 sampling tool.
5) Install a 5-foot-thick layer of plaster sand via tremie pipe. 6) Install a 10-foot-thick upper bentonite chip seal via tremie pipe above the plaster sand.
7) Install a 20-foot-thick layer of gravel pack material in the annulus above the upper bentonite seal.
8) Upon completion, allow a minimum of 12-hours for bentonite seals to hydrate and set up before beginning airlift development.
9) Install air line inside the sampling tool to a depth of at least 100-feet below static water level in isolated aquifer zone. Adjust the depth of the airline as needed to accommodate conditions encountered.
10) Record static water level in the sampling tool prior to starting airlift operations. 11) Develop the isolated aquifer zone:
a. Use airlifting methods for a minimum of 6 hours, or as directed by the engineer, or until discharge water is free of drilling fluids and fine sediments, and the specific conductance stabilizes to the satisfaction of the Engineer.
b. Collect and preserve water samples at 30-minute intervals during airlifting using containers acceptable to the Engineer. c. Record the final stabilized static water level in the isolated aquifer zone after airlift pumping has been stopped.
12) At the Engineers option, install a submersible pump inside of the sampling tool string to a depth specified by the Engineer, generally on the order of 100- feet below static water level in the zone tested.
a. Record static water level.
b. Commence pumping the isolated aquifer zone for a minimum of 2 hours after discharge water clears and specific conductance, pH, and temperature of discharge water stabilizes to the satisfaction of the Engineer.
c. Measure and record the pumping rate and pumping water level at a frequency based on Section 3.9.2
d. Calculate the specific capacity.
e. Assist the Engineer with sample collection as requested.

Page 374 of 519 ends

17 f. After the final water sample is collected, cease pumping and allow the water level in the isolated zone to stabilize.
g. Measure and record stabilized water level.
h. Remove the sampling pump and repeat the above procedures to construct and test the next isolated aquifer zone.
13) Once all samples have been collected and equipment removed from the pilot borehole, backfill the remaining open borehole with gravel pack material as directed by the Engineer.
14) The Contractor will be responsible for the proper disposal of all fluids generated during discrete zone sampling activities, in accordance with Sections 3.8.2 and 3.8.3.
15) The Engineer will be responsible for the collection, preservation, transport, and analysis of all groundwater samples during isolated aquifer zone testing. 16) After all isolated aquifer zone samples have been collected, an evaluation period will begin:
a. The evaluation period begins following completion of zone testing from all aquifer zones testing.
b. No standby time shall accrue during this period.
c. Assume a 7 to 14 calendar day evaluation period.
d. After evaluating water sample results, the Engineer will provide the Contractor with the final details for the construction of a new well.

3.5. Borehole Reaming

3.5.1. Scope
This item shall consist of reaming the test hole to the proper diameter to achieve the production borehole diameter.

3.5.2. Construction Method
The production borehole shall be constructed using reverse rotary drilling equipment. The borehole shall be drilled at a diameter of 36 inches to a depth of 550 feet.

A. Materials On-Site
All equipment and materials must be on-site before commencing drilling of the production borehole.

B. Establishment of an Acceptable Drilling Fluid System - At the completion of conductor casing installation, the Contractor shall recondition or replace the drilling fluid system to comply with the approved drilling fluid program.

Page 375 of 519 ends

18 C. Drilling Method

1. The borehole may be constructed using multiple passes to achieve the specified borehole diameter. If the borehole is constructed with multiple passes, a pilot bit shall be used for each successive pass.

2. The Contractor shall be responsible for keeping the well bore full at all times in order to maintain the integrity of the borehole. Sufficient piping of adequate diameter to convey water from the approved source to the drilling sump is the responsibility of the Contractor.

3. The Contractor shall employ appropriate drill collars to ensure that the hole remains straight and plumb during drilling operations.

D. Drilling Fluid Program - A drilling fluid program shall be employed by the contractor in accordance with the following general conditions.

1. A drilling fluid control program shall be submitted to the Engineer for approval.

Selection and use of the drilling fluid materials shall be a part of this agreement.

The Contractor shall be responsible for maintaining the quality of the drilling fluid to ensure the protection of water-bearing and potential water-bearing formations exposed in the borehole and the ability to obtain reliable representative samples of the formation materials.

2. Material used by the Contractor to prepare the drilling fluid shall be composed of water from an assigned source and drilling additives processed to meet or surpass the specification in the American Petroleum Institute "Std. 13-A for Drilling Fluid Materials". All drilling fluid additives will comply with recognized industry standards and practices, and they shall be used as prescribed by the manufacturer. Toxic and/or dangerous substances shall not be added to the drilling fluid.

3. The drilling fluid for the reverse rotary construction shall be made up of high-grade bentonite clays or organic polymer additives in common drilling usage in the water well industry and shall possess such characteristics as required to condition the walls of the borehole to prevent caving of formations and excessive loss of circulation, facilitate removal of the cuttings, and produce an easily removed thin filter cake.

4. In accordance with these Technical Provisions, the Contractor shall submit a drilling fluid program for approval prior to construction. The submittal shall include the recommendations for make-up water conditioning, quantities of clay base, and additives required to maintain a drilling fluid having properties within the ranges specified below for drilling operations.

Weight 8.3 to 9.0 lb./gal.

Marsh Funnel Viscosity 28 to 35 sec./qt.

Sand Content (Returns) 0-2% by volume
API Filter Cake <3/32” Thickness

5. The above drilling fluid parameters can be modified to address flowing conditions.

Any proposed modifications to address such conditions shall be prepared by a drilling fluid specialist and submitted to the Engineer for approval before implementation.

Page 376 of 519 ends

19 6. The drilling rig must be equipped with equipment to measure the above drilling fluid properties. The measurements must be made at a minimum of once every 4 hours with the results reported on the daily drilling log.

7. Proper control of the drilling fluid must be maintained to the satisfaction of the Engineer. The Contractor will be required, at the Contractor's expense, to retain or employ an experienced, qualified drilling fluid, or mud engineer acceptable to the Engineer to supervise and maintain drilling fluid characteristics to the satisfaction of the Engineer if such control cannot be accomplished by the Contractor.

8. If at any time the drilling fluid is not in compliance with these Technical Provisions or the recommendations of the drilling fluid engineer, as approved by the Engineer, the properties shall be adjusted, and the tests rerun until the drilling fluid obtains the specified characteristics. If the specified properties cannot be maintained, the drilling fluid shall be replaced at the Contractors expense.

E. Geophysical Log

1. When drilling has reached the prescribed final depth, the Contractor shall conduct a geophysical survey in the borehole. Acceptable service companies include Pacific Surveys, Stewart Well Logging, or equivalent as approved by the Engineer.

The Borehole geophysical survey shall include spontaneous potential (SP), natural gamma, and multiple resistivity logs.

2. The spontaneous potential survey shall be plotted on a scale of one inch equal to plus or minus 20 millivolts. The multiple resistivity survey shall consist of a point resistivity curve and multiple resistivity curves for 16-inch short normal and 64- inch-long normal recordings on a one-inch equal to 20- or 40-ohm scale. All surveys shall be plotted on a depth scale of one inch equal to 20 feet.

3. The Contractor is responsible for the integrity of the borehole to ensure that the geophysical logging is successfully completed. The Contractor shall maintain circulation in the borehole with tools on the bottom of the hole until the logging equipment is on location and prepared to conduct the surveys. The logging service company shall have access to a ditch sample of the circulation fluid for calibration of the logs prior to ceasing circulation. When the logging service company is fully prepared, the Contractor shall pull drilling tools from the well, and the logging services immediately commence. If the logging tools fail to reach the desired depth, the Contractor, at the Contractor’s expense, shall reinstall the drilling tools into the borehole, clean out the borehole to the final drilled depth, and recondition the hole to allow for logging operations.

4. Upon completion of logging, the Contractor will deliver to the Engineer four (4) field prints and a digital file of the geophysical surveys, including the raw data (e.g., .las files). The Engineer shall approve the field copies of the surveys before the Contractor releases the logging service company from the site.

F. Caliper Log

1. When drilling has reached the prescribed final depth, the Contractor shall conduct a caliper survey to confirm the diameter of the borehole. The caliper survey will be used to verify the quantities of gravel that will be required for later installation during

Page 377 of 519 ends

20 the well construction.

2. If at any point within the intake or screened portion of the well, a minimum gravel pack thickness of 5 inches cannot be achieved, the borehole will be considered unacceptable for completion. The Contractor shall then proceed to ream the hole at the Contractor’s own expense. A second caliper log shall be conducted on completion of the reaming, at the expense of the Contractor, to satisfy the requirements of the Contract. If the borehole remains unacceptable and it is determined that the well cannot be reasonably constructed to satisfy these Technical Provisions, the Contractor shall abandon the hole and re-drill the well at a new location on the site, all in accordance with the requirements of Section 3.15 and Section 3.16. All costs for abandonment to meet these requirements shall be borne by the Contractor. Additional workdays may be awarded at the sole discretion of the Engineer.

G. Borehole Geometry Survey
The borehole geometry survey tool shall be incorporated into an X-Y caliper tool and shall measure borehole inclination and direction using an integrated magnetometer and accelerometers. Inclination shall be reported in degrees and direction shall be reported in azimuthal degrees. If the results of the borehole geometry survey indicate that the Contractor will not be in compliance with the well casing plumbness and/or alignment requirements described in Section 3.14, the Contractor is advised to correct the deviation prior to the commencement of well construction. Failure to comply with the plumbness and/or alignment requirements is grounds for rejection of the completed well.

3.6. Installation of Well Casing, Screens, Gravel Fill Pipe, and Sounding Pipe

3.6.1. Scope
This item shall consist of providing and installing casing, screens, tremie pipe, sounding pipe, and gravel fill pipe.

3.6.2. Construction Method
At the completion of the drilling and geophysical operations, the Contractor will prepare the borehole for casing installation. The Contractor shall ensure that all cuttings have been removed from the borehole. During the electric log and caliper survey, the borehole shall be kept full of drilling fluid. The Contractor will not be required to return to the bottom with the drilling tools if the casing installation immediately follows the caliper survey, assuming acceptable results are achieved.

A. Tremie, Accessory Pipes, and Casing Installation

1. A tremie pipe having a minimum inside diameter of 2 inches shall be run into the borehole to the specified casing installation depth. Circulation shall commence 30 minutes prior to casing installation and continue until the start of gravel packing.

Circulation shall commence using drilling fluid from the circulation tanks of the same viscosity as that in the borehole and thinned using clean water containing less than 2 percent solids. With the tremie pipe remaining in the borehole, casing installation shall proceed in accordance with the specified well design.

2. Circulation through the tremie pipe shall continue during the casing and screen

Page 378 of 519 ends

21 installation.

3. Three-inch steel pipe shall be used as a gravel fill pipe. The pipe shall be installed to the depth specified in the Plans. The pipe assembly shall be butt welded together to provide a watertight seal. The gravel fill pipe shall be pulled to the side and welded to the conductor casing at ground level, as shown in the Plans.

Orientation of the 3-inch pipe shall be offset from the future pump discharge side of the well as specified in the Plans.

4. All casing sections must be welded together in the field in a vertical position. Field joints shall be properly lap welded during installation into the borehole with a minimum of two passes per circumference. Welding electrodes used for welding shall be of a grade applicable to the material being welded. All alignment holes shall be filled by welding to prevent the entry of water into the completed well through the holes.

5. Centralizers, 4 per set, placed on 90-degree spacing, shall be attached directly to the casing by welding in order to center and hold the casing in the proper position until the gravel is in place. Centralizers shall be positioned at the sump, above and below each screen section, and every 80 feet of the production casing. The casing shall not be centralized between the ground surface and a depth of 80 feet, however.

6. Two-inch collared stainless steel sounding pipe to be used as a still well shall be connected to the sounding box and held close to the casing with U-shaped straps or rings as shown on the Plans. The pipe shall be run concurrently with the casing and attached to the outside of the production casing as shown in the Plans. The sounding pipe assembly shall be welded together to provide a watertight seal. The sounding pipe shall not be attached to the casing within 50 feet of the ground surface. The sounding pipe shall be pulled to the side and welded to the conductor casing at ground level, as shown in the Plans. Orientation of the 2-inch pipe shall be offset from the future pump discharge side of the well as specified in the Plans.

7. The casing shall be suspended in tension from the surface by means of an appropriate hanger or clamp. The use of float plugs to land and set casing will not be permitted. The bottom of the casing assembly shall be at a sufficient distance above the bottom of the borehole to ensure that none of the casing assembly will be supported from the bottom of the hole. Verification of this requirement will be confirmed by the Engineer by observation of the total weight suspended by the drill rig on the weight indicator.

8. If, for any reason, the casing assembly cannot be landed in the correct position or at a depth acceptable to the Engineer, the Contractor shall remove the casing and screen from the well and ream the borehole. In no event shall the Contractor attempt to drive or "spud" the casing and screen assembly. If problems arise that prevent the Contractor from completing the well, it will be considered rejected, and the provisions of Section 3.15 will apply.

9. The casing shall be centered in the conductor casing. Failure to center the casing in the conductor will be grounds for rejection, and the provisions of Section 3.15 will apply.

B. Casing and Accessory Pipe Stick-up

Page 379 of 519 ends

22 1. The well casing assembly and accessory pipes shall be installed with a minimum of 3 feet of stick-up above the existing ground level.

C. Preliminary Plumbness and Alignment Survey - A preliminary test to examine the plumbness and alignment of the casing may be made by the Contractor after the casing has been installed in the borehole and before gravel packing is commenced. The intent of preliminary testing is to identify any plumbness and alignment problems so that they may be corrected before installation of the gravel envelope. Any determination made by the Contractor concerning the plumbness and alignment of the well at this point in construction shall not relieve the Contractor of the requirements specified in Section 3.14.

Any measures required to correct faulty plumbness and/or alignment shall be at the Contractors own expense.

3.7. Gravel Envelope and Annular Seal Installation

3.7.1. Scope
This item shall consist of providing and installing a graded gravel pack material and sealing material in the annulus between the casing assembly and the borehole.

3.7.2. Gravel Packing Method
Prior to gravel packing, the borehole fluid shall be conditioned as follows:

Weight < or = to 8.9 lb./gal.

Marsh Funnel Viscosity < or = to 30 sec./qt.

If the borehole fluid exceeds this specification, the Contractor shall thin the fluid with the addition of clean water to the drilling fluid tank or sump while circulating the entire system. The Contractor shall avoid directly injecting water into the well before the hole fluid has been properly conditioned and the densities and consistencies are matched.

A. Placement

1. Gravel envelope material shall be gravity-fed through the tremie pipe with conditioned fluid. The feed system shall consist of a hopper that will allow for the measurement of the amount of gravel packing material entering the borehole and a pump capable of displacing the gravel and drilling fluid mixture through the tremie pipe.

2. The tremie pipe shall be removed in approximately 20-foot intervals (one joint) when the gravel in the borehole reaches the tremie pipe. The gravel shall not be permitted to free-fall in the annulus for more than 30 feet.

3. The gravel shall be sterilized by continuously mixing at least one gallon of 5-1/2 percent liquid sodium hypochlorite solution per 100 cubic feet of gravel as it is placed in the well.

4. Gravel packing shall continue uninterrupted until the gravel pack material is installed to the specified depth.

B. Attaining Proper Fill - The quantities of gravel placed in the annulus of the well shall not be less than the computed volume calculated from the caliper log and verified by the Engineer. A quantity less than the computed value may be judged as an indication of voids, and corrective measures may be required of the Contractor. Significant

Page 380 of 519 ends

23 differences between the estimated and total volume of gravel installed in the well may be grounds for the rejection of the well under Section 3.15.

C. Consolidation Using Swab Tool - Immediately following the gravel packing, the gravel pack shall be consolidated to ensure that no voids in the gravel pack exist. This can be accomplished with a swab or bailer lowered in the well and moved up and down for a minimum of one hour. After consolidation, the gravel level shall be measured to determine if consolidation has occurred. If the gravel level has dropped, additional gravel shall be added to bring the gravel level to the specified level and swabbed or bailed again. This process will be repeated until the gravel level is stable at the level specified in the plans. A detailed record shall be kept of the amount of gravel added during placement and consolidation, and the quantity of gravel placed in the annulus shall be at least the calculated volume of the annulus. The contractor shall submit the record indicating the total volume of gravel used and the calculated volume of the annulus to the Engineer. The Contractor shall measure and record the depth to the top of the gravel pack within the gravel fill pipe and ensure that it coincides with the bottom, open end of the gravel fill pipe so that there is no gravel pack within the gravel feed tube.

D. Fine Sand Transition Seal - A five-foot, fine sand transition seal consisting of #30 sand shall be placed on top of the consolidated gravel envelope via the tremie pipe. The transition sand shall be clean and delivered to the project site in pre-packaged 50-pound sacks.

3.7.3. Annular Sealing Method
Installation of the annular seal shall conform to State Water Well Standards and the requirements of the well-permitting agency.

A. The Contractor shall proceed with sealing operations after the Engineer verifies the depth of the top of the gravel and transition sand in the well annulus.

B. The tremie pipe shall be installed no more than 5 feet above the fine sand transition seal before beginning cement grout seal placement. The bottom of the tremie pipe shall remain submerged in the grout sealing material, maintaining a positive displacement throughout the sealing process until the grouting material has reached the ground surface.

C. The Contractor shall take measures to ensure that the weight of the cement column does not collapse the well casing during the sealing operation.

D. The annular seal will be required to be placed in three lifts as specified on the Plans. Each lift shall be allowed to be set for a minimum of two hours before placement of subsequent lifts.

E. Well development shall not commence until a minimum of 24 hours after placement of the seal.

3.8. Well Development

3.8.1. Scope
A. Well development shall consist of initially airlifting drilling fluids from the well through an open-ended pipe; swabbing, airlift pumping, and placement of Aqua Clear PFD, or other approved dispersing agent, in screen intake section; installation of an engine-driven

Page 381 of 519 ends

24 turbine test pump; pumping and surging of the well until the well is fully developed and meets the requirements of minimum sand production, turbidity, and specific capacity; and bailing the well of materials introduced into the casing during development.

B. The gravel fill and sounding pipes shall be cleaned of solids and drilling fluid residues by continually adding clean water to the pipes during development, placement of Aqua Clear PFD, and brushing.

3.8.2. Discharge of Initial Development Water
Drilling fluids and initial development water produced during open-ended airlifting and swabbing shall be discharged to a location onsite designated by the Owner within 300 feet of the well site.

Discharge permit through the Central Valley Region will be completed by the Engineer. Specific discussion regarding discharge will be discussed during the mandatory pre-bid meeting.

3.8.3. Discharge of Pump Development/Testing Water
Fluids produced during pump development and pump testing shall be discharged to a location designated by the Owner within 300 feet of the well site. Discharge permit through the Central Valley Region will be completed by the Engineer. Specific discussion regarding discharge will be discussed during the mandatory pre-bid meeting.

3.8.4. Equipment
A. The Contractor shall provide sufficient drill pipe and a mechanical combination swab/airlifting tool with a double rubber packer assembly designed to be run in the intake sections of the well. The equipment will be assembled in a manner that will allow simultaneous airlift pumping and swabbing to occur. The pumping and swabbing will be done between a double rubber packer assembly with the packers no more than 10 feet apart. The outside diameter of the swabs shall be 0.5 inches smaller than the inside diameter of the well screen. A polypropylene brush with the same diameter as the inside diameter of the well casing shall be attached to the swab tool below the bottom swab. A drawing of an acceptable swab assembly tool is shown on the Plans without the polypropylene brush attached.

B. The eductor pipe on the swab assembly, the air pipe, the air compressor, and all other necessary equipment required to perform airlift operations shall be capable of pumping 500 gpm during development.

C. Upon completion of the swabbing airlift pumping, the Contractor shall furnish and install one engine-driven deep well turbine pump, diesel engine, appropriate drive shaft, and incidental equipment for the safe operation of the pumping equipment. The test pump engine shall have a minimum continuous horsepower rating, which will allow for the continuous pumping of the well at the maximum desired flow rate and pumping level.

D. The Contractor shall furnish and install discharge piping from the well to the designated discharge point as shown on the plans. The discharge area shall be properly contained to receive and control all development water.

E. The Contractor shall furnish the necessary gate valves, calibrated totalizing and instantaneous flow meter, sand testing equipment, and other incidental equipment required to accurately measure the flow rate, water levels, sand production, and time of pumping. The installation of the flow meter shall be as defined by the manufacturer for its

Page 382 of 519 ends

25 distance from any elbows or valves so as to provide reliable test information. An acceptable discharge piping arrangement is shown on the Plans. The Engineer will confirm that the flowmeter is measuring properly. If it is determined that the flow meter is not measuring flow correctly, the Contractor shall replace the meter with a properly measuring meter at their own cost.

F. Water level measurements shall be made with either an electric sounder or with other equipment pre-approved by the Engineer. Water level measurements shall be recorded to the nearest 0.01 foot.

G. The equipment for sand testing shall be the Rossum Centrifugal Sand Sampler as specified in the American Water Works Association Standard for Water Wells, A100-20, Section E.2.4.

3.8.5. Development Methods
The intake screen and gravel envelope shall be cleaned of all fluids, wall cake, and any substances that would impede the flow of water into the well.

A. Swab-Airlift Development

1. Open-ended Development
Initially, and within 24 to 36 hours after completion of the annular sealing operation, the well shall be cleaned of residual drilling fluids by displacing the well through an open-ended drill pipe or tubing set in the well sump. This process shall be conducted for a minimum of 4 hours and until the discharge is clear of residual drilling fluids. After drilling residues have been displaced from the well, the development tool shall be installed in the well.

2. Swabbing/Airlifting
Swabbing and airlifting shall be conducted with the development tool alternately over no more than the length of one joint of drill pipe until that section of the screen is fully developed.

Swabbing and airlift pumping operations will be conducted from the top screen section to the bottom, alternately over no more than the length of one joint of the drill pipe.

Screen sections will be swabbed and pumped for a minimum of 7 minutes per foot of well screen or until cleaned of all drilling fluids. During pumping, the drill pipe shall be continuously moved up and down to achieve a swabbing action and uniform pumping across the screen section.

After the initial swabbing-airlift pass, a solution of potable water and Baroid “Aqua Clear PFD” product, or approved equal, shall be placed in the well. The product shall be mixed at the surface in the manufacturer-recommended proportion and injected evenly across each screened section of the well. The solution shall be displaced by adding a volume of potable water equal to the inside of the drill pipe and swabbed without airlifting. After placement of the solution, the well shall then remain idle for a period of 12 hours. Swabbing and airlift pumping of the well shall then resume from the top screen section to the bottom for a minimum of 5 minutes per foot of well screen.

If there continues to be circulation of sand, silt, mud, or water with a turbidity in excess

Page 383 of 519 ends

26 of 25 Nephelometric Turbidity Units (NTU) to the surface from the section of screen being cleaned, additional swabbing and pumping shall be performed until the section is cleaned of such material. It is anticipated that the mechanical development described above will take on the order of 12 minutes per foot of well screen.

2. The sounding pipe and gravel fill pipe shall be cleaned by circulating water and a solution of potable water and Baroid “Aqua Clear PFD” through the pipes.

3. The level of the gravel in the gravel fill pipe shall be measured periodically during well development operations. Gravel must not be added to the gravel fill pipe without prior authorization of the Engineer.

B. Well Video
After completion of swab/airlift operations, the Contractor shall conduct a video survey of the screen assembly. The survey shall be witnessed by the Engineer. The camera shall be in color and have side-scan capability. The logging speed of the video survey shall not exceed 30 feet per minute. The record of survey shall be recorded in DVD or mp4 format and shall be submitted to the Engineer.

The purpose of the video survey is to visually confirm that all drilling fluids, mud, debris have been removed from the well screens to the satisfaction of the Engineer.

If the Engineer determines that there is blockage of screens with drilling mud or any other material, the Contractor shall, at his own expense, continue swab/airlift operations until such material has been removed. If additional swab/airlift operations are required, a second video, at the Contractors expense, shall be performed.

C. Final Development

1. Upon completion of the swabbing and airlift pumping operations, a turbine pump and piping assembly shall be installed. No foot valve shall be installed on the pump and the gearhead shall not be equipped with a non-reverse ratchet installed.

2. Development pumping shall commence within 10 working days after the completion of Initial Development. Pumping shall be initiated at the lowest pumping (i.e., flow) rate possible with the installed pumping equipment. Throughout development pumping, the well shall be surged frequently to achieve maximum compaction of the gravel pack and to remove residual drilling fluids and wall cake. Surging and pumping will continue until the water produced is clear and sand-free, at which time the pumping rate will be increased in increments of 250 gallons per minute, and the pumping and surging will resume. This process will be repeated until the capacity of the well achieves a minimum of 150 percent of the design capacity of the well unless the Contractor is directed by the Engineer to pump the well at lower capacities.

3. Development records shall be maintained at a frequency of at least every 30 minutes showing pumping rate, static water level, pumping water level, drawdown, sand production, and any other pertinent information concerning well development.

Development pumping shall continue until the following conditions have been met:
a) The specific capacity (gallons per minute per foot of drawdown) no longer increases at the design capacity of the well.
b) The sand content satisfies the requirements of these Technical Provisions

Page 384 of 519 ends

27 as specified in Section 3.8.5.C.5

4. Development pumping shall be conducted for a minimum of 24 hours.

5. Sand Testing
The equipment for sand testing shall be the Rossum Centrifugal Sand Sampler. Sand continent shall be measured over a 30-minute interval after a surge at the target well capacity. The sand content shall be measured and recorded every minute over the 30 minutes of pumping after surging. The average sand content for any 5-minute period shall not exceed 5 parts per million during the 30-minute test. If the average sand content exceeds 5 parts per million for any 5-minute period, the Contractor, at Contractor’s expense, shall do the necessary redevelopment work until the sand content is 5 parts per million or less.

Sand testing shall be witnessed by the Engineer.

3.8.6. Well Performance Requirements
At the conclusion of well development, it is the responsibility of the Contractor to meet the requirements contained in Section 3.14 of these Technical Provisions. If the Contractor fails to meet these requirements after the development pumping operations, development shall continue at the Contractor's expense until the well satisfies the specified performance criteria.

3.9. Well and Aquifer Testing

3.9.1. Scope
After final development and when the well meets the specified performance requirements, tests will be performed, including an 8-hour step pumping test at capacities of 50, 75, 100, 125, and 150 percent of the target design capacity of the well and a 12-hour aquifer test at the final design capacity as determined by the Engineer based upon evaluation of well performance during the step test. The test capacities may be modified by the Engineer before or during the testing based on the results of development and test pumping. Well and aquifer testing shall not exceed 40 hours without written direction from the Engineer/Owner.

3.9.2. Test Pumping Procedures
A. Static Water Level
At the start of each day of pumping, the Contractor shall record the static water level in the well. At all other times, the static water level shall be considered to be attained when three successive water level measurements spaced ten minutes apart show no appreciable change.

B. Flow Metering

1. During each test or step, the discharge of the pump shall be measured with an accurate, calibrated totalizing and instantaneous flow meter, or other type as approved by the Engineer. The pump discharge rate shall be maintained at all times during the test within plus or minus 5 percent of the pump test rate by means of an approved gate valve in concert with engine speed.

2. Throughout the test, the Contractor shall frequently record flow rate and totalizer readings to ensure that the pumping rate remains constant.

Page 385 of 519 ends

28 C. Measurements

1. The Contractor shall measure the depth to water, flow rate, and sand content at the time intervals specified herein to the nearest 0.01 feet.

2. Each pumping test shall be monitored by the Contractor, with data recorded according to the following applicable time schedules:
a) Turn pump on to approved test pumping capacity at time (t) = 0. b) Contractor shall measure and record the depth to water as follows:
- each minute, from t = 1 to t = 10.
- each 2 minutes, from t = 10 to t = 20.
- each 5 minutes from t = 20 to t = 50.
- each 10 minutes from t = 50 to t = 100.
- at t = 120, t = 150, t = 180, t = 240, and t = 300.
- each 100 minutes after t = 300.
c) Each recovery test shall be recorded according to the following applicable schedule:
d) Contractor shall measure the depth to water and record as follows (t' refers to the time since pump shut off):
- each minute, t' = 1 to t' = 10
- each 2 minutes, t' = 10 to t' = 20
- each 5 minutes, t' = 20 to t' = 50
- each 10 minutes, t' = 50 to t' = 100
- at t' = 120, t' = 150, t' = 180, t' = 240, t' = 300
D. Pump Failure
In the case of failure or interruption of the pump operation for a period greater than one (1) percent of the elapsed pumping time from t = 0, the test shall be suspended until the static water level has been attained. Should the test be aborted as a result of a deficiency on the part of the Contractor's equipment or personnel, all time consumed in waiting for complete water level recovery and in resuming the pump test to the point where it was aborted shall be at no cost to the Owner.

E. Completion
After the well testing has been completed, the record of water level measurements shall be delivered to the Engineer on the forms provided as part of these documents. The test pump shall not be removed from the well until the Engineer has evaluated the data and authorized its removal.

3.9.3. Dynamic Flowmeter (Spinner) Survey
A vertical flowmeter (spinner) survey shall be conducted in each well during the 12-hour constant rate test. The type of spinner survey tool used shall be capable of accurately measuring flows from each screened section at the pumping rate during the constant rate test.

Page 386 of 519 ends

29 The survey shall be run after the pumping level has stabilized, which will be determined in the field by the Engineer. A dynamic test and static stop counts shall be made under pumping conditions from above the screen section to below of the screen interval. Three down runs shall be conducted during dynamic testing at rates of 20, 40, and 60 ft per minute. Each static stop count test shall consist of two-minute readings made at 10-foot increments. The record for the test shall indicate either meter speed or percentage of total meter speed with depth.

The meter used for the survey shall be calibrated within the uppermost and lowermost blank sections of the well casing.

The Contractor shall provide five (5) copies of the survey to the Engineer upon completion.

Calculation of flow rates and the percentage of each flow rate, from the screened interval, shall be performed by the logging subcontractor and submitted to the Engineer in tabular format.

The spinner survey measurements shall also be provided electronically to the Engineer in both Adobe PDF and ASCII digital format.

3.9.4. Water Samples
During constant rate testing of the well, the Contractor shall provide access to the well for sample collection by the Engineer.

3.9.5. Records
The Contractor shall keep accurate records of the pumping tests and furnish copies of all records to the Engineer upon completion of the test. The records shall be available to the Engineer for inspection at any time during testing. The records shall also include a description of the point from which depth to water measurements were made and its measured height above land surface.

3.10. Plumbness and Alignment Testing

3.10.1. Scope
This item shall consist of testing to determine the plumbness and alignment of the installed casing in the well. The plumbness and alignment test may be performed at any time following gravelpacking and sealing operations. The completed well shall be constructed round, plumb, and true to line as defined herein.

A. Alignment Equipment - Alignment shall be tested with a section of pipe 40 feet long or a dummy of the same length. The outer diameter of the pipe or dummy shall be not more than 0.5 inches smaller than the inside diameter of that part of the well being tested. The dummy, if used, shall consist of a rigid spindle of at least 6-inch diameter extra heavy pipe with three rings, rigidly fixed to the pipe so that they cannot move longitudinally along the pipe. The rings shall be at least 12 inches in length, truly cylindrical, and shall be placed one at each end of the dummy and with one ring in the center. The rings shall consist of suitable material that will not harm the interior of the casing while being lowered or raised. An example of an approved dummy is shown in the Plans.

B. Plumbness Equipment - The test for plumbness shall be conducted using a digital gyroscopic deviation probe capable of measuring inclination and direction of drift. The output of the survey shall consist of station depth, inclination, azimuth, true vertical depth, departures, and the plane of closure (displacement). Log presentation shall consist of color plots of plan, vertical, and three-dimensional views of the production well casing.

Page 387 of 519 ends

30 Acceptable service companies to perform plumbness testing are listed in Section 3.5.2.E.1 of these Technical Specifications.

3.10.2. Methods
A. Alignment Testing - Alignment shall be tested by lowering into the well to the top of the screened intake portion of the well, a section of pipe 40 feet long or a dummy of the same length.

B. Plumbness Survey - The plumbness of the well shall be determined in 10-foot intervals from the ground surface to the bottom of the well.

3.11. Video Survey

1. After final clean-up of the well and prior to disinfection, and before welding a plate on the top of the casing, the Contractor shall conduct a video survey of the entire casing and screen assembly. The camera shall be in color and have side-scan capability.

The survey shall be witnessed by the Engineer.

If the Engineer determines that any portion of the video survey record is of inadequate quality (e.g., clarity) to allow detailed examination of the inside of the well, the Contractor shall rerun the survey at Contractor’s expense. Clarity should be of sufficient quality to evaluate the integrity of all joints, screen openings, the sounding port, and the entire inside surface of the casing assembly. Logging speed of the video survey shall not exceed 30 feet per minute.

2. The record of the survey shall be recorded and provided to the Engineer in digital form.

3.12. Disinfection of Well
A. Disinfection Preparation - The Contractor shall conduct disinfection after construction of the well and all specified tests and video logging have been completed. The Contractor shall carry out adequate cleaning procedures immediately preceding disinfection where evidence indicates that normal well construction and development work have not adequately cleaned the well. All oil, grease, soil, and other materials that could harbor and protect bacteria from disinfectants shall be removed from the well. Unless prior approval is obtained for employing chemicals or unusual cleaning methods, the cleaning operation is to be carried out by pumping and swabbing only. Where test pumping equipment is to be utilized, such equipment shall be installed prior to or during disinfection and shall be thoroughly hosed, scrubbed or otherwise cleaned of foreign material prior to its installation into the well. The Contractor is responsible for removing or mitigating the effects of all materials introduced into the well during drilling, construction, development, and testing.

B. Interim Disinfection - Should a delay of five days or more be anticipated between the completion of the well and the regularly scheduled well disinfection, an interim disinfection shall be provided by the Contractor. The Contractor shall apply liquid chlorine in an amount equal to 25 percent of the amount required for final disinfection. For this purpose, the disinfection agent shall be furnished or prepared in liquid form and placed in the well through a tremie pipe of sufficient length to extend to the bottom of the well. The disinfection agent shall be applied through the tremie pipe. A volume of water sufficient enough to displace the disinfection agent from the tremie pipe will be added to the tremie pipe. The disinfection agent shall be placed at regular intervals sufficient to achieve a

Page 388 of 519 ends