Cities Index.
Item 03 - Acceptance of Contract work Installation of Playground Equipment for Flag Hill Veterans Memorial Park Project No. 11163

Yucaipa City Council
May 23, 2022

Document
Item 03 - Acceptance of Contract work Installation of Playground Equipment for Flag Hill Veterans Memorial Park Project No. 11163
Meeting
May 23, 2022
Body
Yucaipa City Council
Pages
2
Original file
5 KB
Text extracted from the city's file for reading and search. Open the original on coydocs.yucaipa.gov. That file is the official record.

Agenda Item No. 3

CITY OF YUCAIPA

AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Service/City Engineer VP Scott Washburn, Public Works Manager I& f.. Sw
Todd Gutjahr, Public Works Analyst a
FOR: City Council Meeting of May 23, 2022
SUBJECT: Acceptance of Contract Work - Installation of Playground Equipment for Flag Hill Veterans Memorial Park — Project No. 11163
RECOMMENDATION:

That City Council:

1. Accept the contract work completed by Three Peaks Corporation of Calimesa, California for the Installation of Playground Equipment for Flag Hill Veterans Memorial Park — Project No. 11163 in the amount of $41,520; and

2. Approve the final payment for the Project; and

3. Authorize the recordation of the Notice of Completion BACKGROUND/DISCUSSION:

In early 2021, the playground equipment at Flag Hill Veterans Memorial Park was approximately 20 years old and exceeded its useful life. In March of 2021, portions of the playground equipment were closed for public use due to its deteriorating condition. On April 26, 2021, City Council approved and authorized the City Manager, or his designee, to acquire replacement playground equipment for Flag Hill Veterans Memorial Park from Miracle Recreation Equipment Company for the amount of $43,098.92. The playground equipment consists of a two-story structure, three slides, multiple climbing apparatuses, and a gymnastics outrigger feature. This contract was for the purchase and delivery only and did not include the installation of the playground equipment.

On October 11, 2021, City Council awarded and authorized the Mayor to execute a contract in the amount of $41,520 with Three Peaks Corporation of Calimesa, CA. for the Installation of Playground Equipment for Flag Hill Veterans Memorial Park — Project No. 11163 (Project) and authorized a contract contingency in the amount of $2,075 and the amount of $1,500 for construction contract administration/inspection costs for a total construction/installation budget of $45,095 for the Project.

The Project has been completed. Field inspections performed by staff during the course of the work and upon completion of the work have assured that the work was completed according to the plans and specifications for this Project. As a result, staff recommends that City Council accept the contract work and direct staff to file the Notice of Completion for the Project. -17-

City Council Meeting of May 23, 2022
Acceptance of Contract Work - Installation of Playground Equipment for Flag Hill Veterans Memorial Park - Project No. 11163

Page 2 of 2 ends

FISCAL IMPACT:

The table below includes the available funding identified in the FY2021/2022 Capital Improvement Program (CIP) for the Project:

Funding Source
Amount
Parks Capital Replacement Fund
$15,095
FY2021 /2022 Capital Improvement Program Funds (Playground Maintenance)
30,000
Total Available Funding
$45,095
The total budgeted and actual costs of the Project are included in the table below:

Approved Budget
Actual Costs
Construction Contract
$41,520
$41,520
Construction Contract Contingency
2,075
0 Construction Contract Admin./Inspection/TestingAdmin./Inspection/Testing 1,500
1,500
Total Program Construction Cost
1 $45,095
$43,020
On October 11, 2021, City Council approved a budget in the amount of $45,095 for the Project. The total actual cost of the Project is in the amount of $43,020. As shown in the table above, sufficient funding is available to accommodate staff s recommendations. The balance of the funds remaining will be used for playground maintenance activities as required during the current fiscal year.

Attachments: Notice of Completion
Approved by:

RECORDING REQUESTED BY
City of Yucaipa
WHEN RECORDED RETURN TO:

City Clerk
City of Yucaipa
34272 Yucaipa Blvd.

Yucaipa, CA 92399
Recording Fee $0 SPACE ABOVE THIS LINE FOR RECORDER'S USE Government Code 6103

NOTICE OF COMPLETION
Pursuant to the provisions of Section 9204 of the Civil Code of the State of California, NOTICE IS HEREBY GIVEN that work on the certain project known as:

PROJECT NO. 11163

INSTALLATION OF PLAYGROUND EQUIPMENT FOR FLAG HILL

VETERANS MEMORIAL PARK
No APN Number
for the City of Yucaipa was completed and accepted by the City of Yucaipa on the 23rd day of May, 2022
The said work was performed by Three Peaks Corporation of Calimesa, CA in accordance with the terms of the written agreement dated the 11t" day of October 2021.

Dated May 23, 2022,
CITY OF YUCAIPA, a Municipal Corporation, Owner
34272 Yucaipa Blvd, Yucaipa, CA 92399
Fermin G. Preciado, Director of Development Services/City Engineer A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or validity of the document.

STATE OF CALIFORNIA

COUNTY OF SAN BERNARDINO
Subscribed and sworn to (or affirmed) before me on this 23rd day of May 2022, by Fermin G. Preciado, proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.

Date
Jennifer Crawford, Assistant City Manager
/City Clerk
-19-