Item 16 - Environmental Review and Right of Way Acquisition County Line Road Mobile Source Air Pollution Reduction Review Committee Grant Funded Project

Yucaipa City Council
August 22, 2022

Document
Item 16 - Environmental Review and Right of Way Acquisition County Line Road Mobile Source Air Pollution Reduction Review Committee Grant Funded Project
Meeting
August 22, 2022
Body
Yucaipa City Council
Pages
4
Original file
9 KB
Text extracted from the city's file for reading and search. Open the original on coydocs.yucaipa.gov. That file is the official record.

Agenda Item No. 16

CITY OF YUCAIPA

AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Services/City Engineer Benjamin Matlock, Planning Manager/City Planner/'f..i'— Katrina Kunkel, Associate Engineer
FOR: City Council Meeting of August 22, 2022
SUBJECT: Environmental Review and Right -of -Way Acquisition — County Line Road Mobile Source Air Pollution Reduction Review Committee (MSRC) Grant Funded Project RECOMMENDATION:

That City Council:
1) Find that the construction of street improvements and acquisition of property required to construct the County Line Road Mobile Source Air Pollution Reduction Review Committee (MSRC) Project along County Line Road between 40, Street and Calimesa Boulevard is Categorically Exempt pursuant to Section 15301(c) of the CEQA guidelines, and direct staff to file a Notice of Exemption; and 2) Authorize staff to proceed with the right-of-way acquisition necessary for the Project; and
3) Authorize the City Manager to execute the necessary documents to complete the right-of-way acquisition process.

BACKGROUND/DISCUSSION:

At the July 8, 2013 meeting, City Council approved the Citywide Miscellaneous Intersection Roundabout Study (Study) prepared by RBF Consulting. The Study identified strategic intersections along arterial streets including Yucaipa Boulevard, Avenue E, and County Line Road, in the City where vehicular traffic circulation would be improved and operate more efficiently in the long term with the construction of roundabouts. The Study also showed that potential single -lane roundabout intersections would improve operation and traffic flow along street segments between intersections along the arterial streets. As a result of the implementation of roundabout intersections into the City's General Plan Transportation Element, certain segments of the City's arterials would not require widening from two (2) lanes to four (4) lanes.

These intersection improvements reduced the need for street widening and significantly reduce the amount of right-of-way (and associated costs) and street improvements required to accommodate future traffic conditions along these corridors. Additionally, roundabout intersections introduce significant intersection safety enhancements for both pedestrians and -302-

City Council Meeting of August 22, 2022
Environmental Review and Right -of -Way Acquisition for County Line Road MSRC Project

Page 2 of 4 ends

vehicles and represents a cost savings to the City when considering the long-term maintenance costs associated with traffic signal equipment and utility costs.

In early 2017, discussions were held with the City of Calimesa regarding joint participation for the improvements on County Line Road in order to improve operation and traffic flow through the intersections and improve safety for pedestrians and bicyclists. Since both cities will mutually benefit from these improvements, an agreement was prepared in order to identify the responsibility and funding commitment of both cities for the various improvements along County Line Road. These improvements along County Line Road between Bryant Street and Calimesa Boulevard make up the County Line Road Transportation Corridor Project (Project).

To fund the Project, the City of Yucaipa and City of Calimesa collaborated on grant funding applications. The Cities successfully acquired grant funding from Caltrans - Active Transportation Program (ATP) in the amount of $512,000 (lead agency - Yucaipa) for street improvements between California Street and 3rd Street; Air Quality Management District - Mobile Source Reduction Committee (MSRC) in the amount of $380,000 (lead agency - Yucaipa) for street improvements between Calimesa Blvd and 4th Street; and California Transportation Commission, Local Partnership Program (LPP) in the amount of $3,747,000 (lead agency - Calimesa) for the remaining segments of the Project. For the City of Yucaipa Development Impact Fee (DIF), Pavement Management program (PMP), SB 1 and Measure I funds are being used as the local match for the grant funding. The ATP funded portion of the Project has been completed, the LPP funded portion is currently under construction and the MSRC portion is planned to be constructed next. At the August 13, 2018 City Council Meeting, Council approved a Professional Services Agreement with LAN Engineering to complete the engineering, design and construction plans for the MSRC portion.

The MSRC grant includes funding for the construction of pedestrian access improvements, including sidewalk and curb ramps, and bicycle lanes on the north and south side of County Line Road, between Calimesa Boulevard and a point just west of 41h Street. This grant funded project does not include the roundabout at County Line Road and 5th Street, which is a component of the LPP funded portion currently under construction.

Prior to approval and construction of the MSRC portion of the Project, the City must complete the California Environmental Quality Act (CEQA) environmental review. This is also required to move forward with the right-of-way acquisitions that will be necessary for the MSRC portion of the Project.

The CEQA analysis prepared by staff concluded that the proposed Project is eligible for a Categorical Exemption pursuant to Section 15301(c) of the CEQA guidelines, as the project involves the minor alteration of existing public streets and public improvements involving negligible expansion of use beyond what is existing. The scope of the project would result in modifications and improvements of County Line Road, but will maintain the vehicle and pedestrian access. Staff recommends that City Council find that the construction of street improvements and acquisition of property related to construction of street improvements along County Line Road between 4th Street and Calimesa Boulevard is Categorically Exempt pursuant to Section 15301(c) of the CEQA guidelines.
-303-

City Council Meeting of August 22, 2022
Environmental Review and Right -of -Way Acquisition for County Line Road MSRC Project

Page 3 of 4 ends

FISCAL IMPACT:

The FY2022/2023 CIP identifies the following funding for the Project:

County Line Road Corridor Pro ect:

Funding Sources
Amount
MSRC Grant
$380,000
Measure I Arterial Funds
2,929,000
Measure I Advanced Expenditure Funds
2,106,000
Pavement Management Program (PMP)
200,000
SB 1
685,000
SB1/LPP Grant
1,986,000
Total Funding Available
$8,286,000
Estimated Costs
Project Design (MSRC & LPP Project)
Design Contract
$663,172
Design Contract Contingency
85,862
Design Contract Administration/Staff Time/Grant Coord./Environ. 301,323
Total Design Costs to Date
$1,050,357
Right -of -Way Acquisition
Right of Way Acquisition
$1,782,559
Right of Way Acquisition Coordination/Staff Time
98,500
Right of Way Legal Fees
101,820
Total Right of Way Costs to Date
$1,982,879
Structure Demolition
Demolition Contract
$37,000
Demolition Contract Contingency
6,000
Demolition Contract Permitting/Inspection
4,500
Phase 1 Assessment/Environmental Review
13,154
Total Estimated Costs to Date
$60,654
Construction
LPP Maximum Fair Share Contribution to City of Calimesa (1) $4,581,463
Total Estimated Costs to Date
$7,675,353
Balance Remaining
$610,647
<<� Fair Share agreement approved by City Council on 3/12/2018. Costs include construction, construction management/inspection, and environmental review.

As listed in the table above, the FY2022/2023 Capital Improvement Program (CIP) includes funding in the amount of $8,286,000 for the Project. If approved, staff will return to Council with a recommendation regarding actual right-of-way acquisition costs at a later date. -304-

City Council Meeting of August 22, 2022
Environmental Review and Right -of -Way Acquisition for County Line Road MSRC Project

Page 4 of 4 ends

Attachment: Right -of -Way Layout Exhibits
Approved by:
_,h 4
-305-

;. u
J
\ \ \ w I EXIST. R/Wun 22
\ (n U I I
n PROP. R/W /
a EXIST. R/W 20
�� -- EXIST. R/W
Q 12 14 1s 11 _�--/ CITY OF YUCAIF 10
EXIST. R/W EXIST. R/W EXIST. R/W - w, CITY OF CALIME;
COUNTY LINE R D EXIST. R/W ____ u-`
\ I EXIST. R/W n
I

RIGHT OF WAY ACQUISITION PROPOSED RIGHT OF WAY

ACQUISITION
�29 FROM STA. 12+97f TO STA. 23+24f

NOT TO SCALE
52 w
H EXIST. IR/W
= T PROP. R/W
I�
I / EXI T. R/W -1
Set
I �
_ - -
CITY OF YUCAIPA ��!ST�R�/W 58
CITY OF CALIMESA XIST. W —
N

RIGHT OF WAY ACQUISITION
FROM STA. 55+60f TO STA. 59+52+

NOT TO SCALE
Li
U
H
O
N
r EXIST. R/W
COUNTY LINE RD u~
60 62
i
u w EXIST. R
J
U U
H F--
O O
N N
-306-

← All documents from this meeting