Agenda Item No. _9—

CITY OF YUCAIPA

AGENDA, REPORT
TO: Honorable Mayor and City Council
FROM. Fermin Preciado, Director of Development Services/City Engineer VP Landon Kern, Assistant City Engineer L[
Katrina Kunkel, Associate Engineer 0'
FOR: City Council Meeting of September 12, 2022
SUBJECT: Acceptance of Contract Work. — 2021/2022 Street Striping Program - Project No. 11157
RECOMMENDATION:

That City Council:
1) Accept the contract work completed by Superior Pavement Markings, Inc. in the amount of $65,261 for the 2021/2022 Street Striping Program- Project No. 11157; and 2) Authorize the recordation of the Notice of Completion for the project.

BACKGROUND/DISCUSSION:

On April 26, 2021 City Council approved the FY2021/2022 Pavement Management Program (PMP). Included as part of the PMP is the 2021/2022 Street Striping Program (Program).

The Program includes installation of new striping and signage, and revitalization of existing pavement striping and markings throughout the City as part of the City's overall Pavement Management Program (PMP). Also included in the Program is the restriping of the "edge line", between the travel lanes and on -street parking areas along Yucaipa Boulevard between Bryant Street and 2nd Street. The edge -line restriping would include red, white, and blue striping.

On April 11, 2022, City Council awarded a contract to Superior Pavement Markings of Cypress, CA in the amount of $61,740 for the Program. At that meeting, City Council consensus was to reduce the limits of the proposed red, white, and blue edge -line striping. The revised limits are Yucaipa Boulevard between Adams Street and 111 Street.
-199-

City Council Meeting of September 12, 2022
Acceptance of Contract Work—2021-2022 Striping Program- Project No, It 157

Page 2 ends

FISCAL IMPACT:

The table below includes the approved budget and actual construction costs for Program:

Approved
Budget
Actual Cost
Construction Contract
$61,740
$61,740
Construction Contract Contingency
6,500
3,521
Construction Contract Administration/Staff Time/Inspection 5,000
4,795
Total Construction Cost
$73,240
$70,056
The Approved FY2021/2022 CIF PMP Budget (including soft costs) is as follows:

Sub -Program
Budget
Expenditures
to Date
Note
2020/2021 & 2021/2022 Street Rehabilitation Program
$3 726 747
$2 760 860
1,2
2020/2021 & 2021/2022 Micro -Surface-
Arterial/Collector/Residential
$309,722
$309,722.10
i'
2021/2022 Concrete Replacement Program
$140,000
$91,701.60

1.2 2021/2022 Street Patching Program
$277,000
$221,643
1,2,3
2021/2022 Crack Scaling Program
$100 000
$100,000
1,2
_
2021/2022 Street Striping Program
$73,240
$70,056
2, 4.5
2021/2022 Survey Monument Preservation
$30,000
$0
1 2021/2022 Traffic Calming
$100 000
$57 000
1,2,3
2021/2022 Alley Improvement Program
$50,000
$50,000
l
2021/2022 Under Street Drain Pipe Repair/Replacement
$30,000
$0
1 New City Yard Project
$240,000
$0
l
Avenue E SRTS - 131' Street to Dunlap Channel
$70,000
$0
1 Live Oak Canyon Road at Wildwood Creek- LWC
$40 000
$0
1 -Retesting of City -Wide Streets
$3,000
$0
Indirect Costs
$ I4,000
$0
Interagency Pavement Agreement
$40,000
$0
Local Match for Grants
$50,000
$0
Totals
$5 253 709
$3,660,983
(1) To be completed under separate contract(s)
(2) Includes carryover funds from previous year(s)
(3) Includes funding from approved FY2022/2023 PMP Budget (4) Part of this council action
(5) Includes the $13,240 in FY2021/2022 Unallocated PMP Any and all cost savings from the proposed programs will be returned to the Unallocated PMP Fund balance
-200-

City Co►rncil Meeting of September 12, 2022
Acceptance of Contract Work—2021-2022 Striping Program- Project No. 11157

Page 3 ends

Attachments: Notice of Completion — Project No. 11152
Approved by:
-201-

RECORDING REQUESTED BY
City of Yucaipa
WHEN RECORDED RETURN TO.

City Clerk
City of Yucaipa
34272 Yucaipa Blvd.

Yucaipa, CA 92399
Recording Fee $0 SPACE ABOVE THIS LINE FOR RECORDER'S USE Government Code 6103

NOTICE OF COMPLETION
Pursuant to the provisions of Section 9204 of the Civil Code of the State of California, NOTICE IS HEREBY GIVEN that work on the certain project known as:

PROJECT NO. 11157
2021/2022 STREET STRIPING PROGRAM — PROJECT NO. 11157
Z57-AW►111110RTi, ;M
for the City of Yucaipa was completed and accepted by the City of Yucaipa on the 121" day of September 2022
The said work was performed by Superior Pavement Markings, Inc. of Cypress, CA in accordance with the terms of the written agreement dated the 111" day of April, 2022.

Dated September 12, 2022,
CITY OF YUCAIPA, a Municipal Corporation, Owner
34272 Yucaipa Blvd, Yucaipa, CA 92399
Fermin G. Preciado, Director of Development Services/City Engineer A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or validity of the document.

STATE OF CALIFORNIA

COUNTY OF SAN BERNARDINO
Subscribed and sworn to (or affirmed) before me on this 12t" day of September 2022, by Fermin G. Preciado, proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.