Item 06 - Award of Contract for the Pase 2 Construction of the Dunlap Blvd. Bridge Removal and Replacement Project at Wilson Creek Channel Project No. 11098

Yucaipa City Council
April 24, 2023

Document
Item 06 - Award of Contract for the Pase 2 Construction of the Dunlap Blvd. Bridge Removal and Replacement Project at Wilson Creek Channel Project No. 11098
Meeting
April 24, 2023
Body
Yucaipa City Council
Pages
4
Original file
23 KB
Text extracted from the city's file for reading and search. Open the original on coydocs.yucaipa.gov. That file is the official record.

Agenda Item No. 6

CITY OF YUCAIPA

AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Services/City Engineer Landon Kern, Assistant City Engineer
FOR: City Council Meeting of April 24, 2023
SUBJECT: Award of Contract for the Phase 2 Construction of the Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel — Project No. 11098 RECOMMENDATION:

That the City Council:

1. Award and authorize the Mayor to execute a contract, and the City Manager or his designee to administer the terms of the contract to the lowest responsible bidder, IE General Engineering Inc. of Beaumont, CA in the amount of $2,098,054 for the Phase 2 Construction of the Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel — Project No. 11098, and

2. Authorize a construction contract contingency amount of $275,000 for the project, the amount of $175,000 for construction contract administration, inspection, testing, survey and staff time for a total construction contract budget in the amount of $2,548,054; and

3. Approve Amendment No. 5 to the contract with Dudek in the amount of $30,000 for construction engineering and design support services for this project; and

4. Approve the plans and specifications prepared for the project.

BACKGROUND/ DISCUSSION:

The Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel (Project) is an important drainage infrastructure project that will remove a significant number of properties in the City's Dunlap area from the FEMA designated floodplain/floodway and is included in the adopted FY2022/2023 Capital Improvement Program (CIP). The existing Dunlap Boulevard bridge over Wilson Creek is "under sized" and does not provide sufficient capacity for Wilson Creek to convey storm flows under Dunlap Boulevard. As defined in the 2015 Conditional Letter of Map Revision (CLOMR) report for Wilson Creek Channel, several areas within the vicinity of the existing bridge currently remain in the FEMA mapped floodplain/floodway. The Project involves the removal and replacement of the existing Dunlap Boulevard Bridge at Wilson Creek Channel. The replacement bridge is taller and longer to 04/24/2023 City Council Agenda 103

City Council Meeting of April 24, 2023
Award of Contract for Phase 2 Construction of the Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel — Project No. 11098

Page 2 of 4 ends

increase the storm water conveyance capacity of the channel, while maintaining vehicular (one way) and pedestrian access across the channel.

At the March 25, 2019, City Council Meeting, Council awarded a professional services agreement to Dudek for the engineering design of the Project. The design was completed and the construction of the Project was identified at that time to be completed in phases. Phase 1 construction was completed and accepted by City Council at the February 27, 2023 City Council Meeting. The Phase 1 improvements included the construction of the new bridge foundation, structure and utility casings in anticipation of the utility relocations planned with the Phase 2 improvements. The proposed Phase 2 improvements include the transfer of the existing utilities onto the new bridge structure, fabrication and installation of the steel trusses on the new bridge, Dunlap Boulevard intersection and drainage improvements, removal of the existing bridge, and construction of channel improvements under the new bridge.

The Phase 2 Project was publicly advertised for bids on February 27, 2023. On April 6, 2023 four (4) sealed bids were received from contractors as follows; Bidder
Bid Amount
IE General Engineering Inc.
$2,098,054
Beador Construction Company
$2 360,300
KEC Engineering
$2 703,255
Riverside Construction Com2any
$3 504,937
The Engineer's Estimate for Phase 1 of the Project is in the amount of $1,900,000. IE General Engineering Inc. is the apparent responsive low bidder for the Project in the amount of $2,098,054.

Staff has reviewed the bid documents and determined that the documents meet the requirements of the construction contract specifications. IE General Engineering Inc. has completed previous similar work for the City of Yucaipa and other public agencies and their work has been deemed satisfactory. As a result, staff recommends that City Council award the contract to IE General Engineering Inc.in the amount of $2,098,054 for the Project.

Due to the nature of the proposed bridge construction, including the protection of existing bridge and utility infrastructure, staff recommends approval of Amendment No. 5 to the contract with Dudek in the amount of $30,000 for construction engineering and design support services for the construction of the proposed Project. This will allow Dudek to provide engineering design support to the City during construction.

FISCAL IMPACT;
The table below includes available and proposed funding and estimated costs for the Project:

Funding Source
Amount
Proposition I A
$29 000
I Capital Loan to DFF
900,000
04/24/2023 City Council Agenda 104

City Council Meeting of April 24, 2023
Award of Contract for Phase 2 Construction of the Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel Project No. 1 ] 098

Page 3 of 4 ends

DFF
681,000
GF One Time Capital Loan to TFF
135,000
Traffic Safety Fund 16/17 loan
1,037,000
Yucai pa Boulevard 1511 to I-10
1,502 000
PMp Loan to DFF from Yucaipa Blvd, l 5"' to 1-10
660,000
Utility Underground Reimbursement from Yucaipa Boulevard 640,000
Fill Dirt Reimbursement to DFF Wildwood Basin
441,000
Total Available Funding
$6.025,000
Total Available Funding Exclud ng Reimbursement Funding) $4,944,000
Design and Construction Costs
Wilson Creek Channel Project Desi n/CLOMR Costs
Design Contract plan Preparation)
$242,191
Desi n Contract Contingency
24,000
Design Contract Administration/Staff Time/Grant Coordination 30 000
Total Wilson Creels Channel Project Desi n/CLOMR Costs
$296,191
Dunlap Blvd Bridge Removal/Replacement Project Design Costs Design Contract
$218,593
Design Contract Contingency
43,720
Design Contract Administration/Staff Time/Grant Coordination 10,930
Total Design Costs
$273,243
Environmental Review/Permitting Costs
$38,600
Total Design/Environmental Costs to Date
S608,304
Wilson Creek Channel Retaining Wall
Construction Contract
$259,136
Construction Contract Contingency
25,762
Construction Contract Administration
13,000
Total Wilson Creek Channel Retaining Wall Costs
297,898
Dunlap Blvd Bridge Removal/Replacement Phase 1 Construction Construction Contract
$1,112,060
Construction Contract Contingency
22,049
Construction Contract Administration
29,200
Inspection/Material Testing/Survey/Staff Time
134,230
Utility Coordination/Relocations
58,690
Total Phase 1 Construction Budget Cost
$1,356,229
Wilson Creek Channel LOMR Application
Engineering Contract LOMR Application
$51 750
04/24/2023 City Council Agenda 105

City Council Meeting of April 24, 2023
Award of Contract for Phase 2 Construction of the Dunlap Boulevard Bridge Removal and Replacement Project at Wilson Creek Channel -- Project No. 11098

Page 4 of 4 ends

Engineering Contract Contingency
6,000
E4meering Contract Administration/Staff Time
5,000
Total LOMR AplAteation Costs
$62 750
Dunlap Blvd Bride Removal/Re lacement Phase 2 Construction Proposed Construction Contract (1)
$2,098 054
Proposed Construction Contract Contingency
275,000
Proposed Construction Contract Administration
175,000
Proposed Construction Contract Budget
$2,548,054
Proposed Dudek Amendment No. 5 — Construction/Design Support Services
$30,000
Total Estimated Phase 2 Construction Budget
$2 578,054
Total Available Funding, (Excluding Reimbursement Funding) $4,944,000
Total Estimated/Proposed Overall Project Costs to Date (1) $4 902,965
Remaining Balance
$41,035
(1) Part of this Council Action.

With the total available funding included in the table above, there is sufficient funding available to accommodate staff s recommendations.

Attachments: 1. Bid Summary

2. Construction Agreement

3. Dudek Agreement Amendment No. 5
Approved by:
04/24/2023 City Council Agenda 106

Attachment 1
Bid Tabulation -Dunlap Blvd Bridge &
Replacement Project Crossing Wilson Creek April 2023
Channel -phase 2 Project No. 11098
!E General Engineering
BeadorConstruction Company
NEC Engineering
Riverside Construction Company
Beaumont, CA
Costa Mesa, CA
Corona, CA
Riverside, CA
Item
Item Description
Qty
Unit
UnIt Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.
1 Mobilization/Demobilization

1.00 LS
$250,000.00
5250,000.00
$250,000-00
$250,ODD.00
$67,000.00
$67,000.00
$550,000.00
$550,000.00
2 SWPPP and Stormwater Qua IIty Compliance
1,00
LS
$50,000.00
$10,000.00
$30.000.00
$30,ODO.00
$36,000.00
$36,000.00
$75,000.00
$75,000.00
3 Traffic Control
"Oo
LS
$40,000-00
$40,000.00
$224,093-00
$224,093.00
$37,000.00
$37,000-00
$75,000.001
$75,000.00
Construct AC Roadway per plan, profile and modified City of 4 Yucaipa Std Plan 102-1 with 5" AC over 6" CAB; Prepare subgrade 12" below CAB per Geotech Report and compact to 6,734-00
SF
95%relative density per AST D-1557
$8.50
557,239.00
$21,00
$141,414.00
$11.00
$74,074-00
$8.00
$53,872-00
Construct 6" Curb and Gutter per plan, profile, and San 5 Bernardino County Std Plan 116
350.00
LF
$45,00
515,750.Q0
$100.00
$35,000.00
$82,00
$28,700,00
$55.00
$19,250.00
6 Construct Commercial Driveway Approach per plan and San Bernardino County Std Plan 129
4 00
EA
$9,000-00
$36,000.00
$9,100-00
536,400.00
$5,000-00
$20,000.00
$3,500,00
$14,000.00
Construct Curb Return Sid ewa]k Ramp per plan and San
Bernardino County Std Plan 110

2.00 EA
$8,500.00
$17,00D.Q0
$6,000.00
$12,000.00
$8,000,00
$16,000.00
$3,500,00
$7,000.QO
Relocate Fence per plan and San Bernardino County Std Plan 8 300
127.00
LF
$70,00
58,890.00
$48-00
$6,096,00
$120-00
$15,240,00
$45.00
$5,715,00
9 Construct 8 Ft Wide Urban Streets ide MuIt! -Use DG Trail per City of Yucaipa Std Plan 602.1
108.00
SY
$60.00
$6,480.00
$90-00
$9,720,00
$270,00
$29,160.00
$60,00
$6,480.00
Construct 7' Curb Opening Catch Basin per SPPWC Std Plan 10 307-3
1-0D
EA
$18,000.00
$18,000-00
$11,000.00
$11,000-00
$14,000.00
$14,000-00
$16,000.00
$16,000.00
Construct Warped Wingwall Channel Transition per plan and 11 Caltrans Std Plan D86A
4•00
EA
$25,500,001
$102,000.00
$19,250,00
$77,000.00
578,000,00
$312,000A01
5200,000.00
$800,000,00
12 Furnish & Install 18" RCP per plan and profile
141.00
LF
$200.00
$28,200.00
$27S,00f
$38,775.00
$240-00
$33,840.00
$300-09
$42,300.00
13 Furnish & install 24" RCP per plan and profile
197.00
LF
$225.D0
$44,325.00
$260.D0
551,220.D0
$200.00
$39,400.00
5330.00
$65,010.00
Construct 7' Curb Opening Catch Basin per SPPWC Std Plan 14 300-3, 8�

3.00 EA
$26,500.00
$79,500-00
$10,500.00
$31,500-DO
$7,000.00
$21,000.D0
$16,00Q.00
$48,000.00
15 Construct Junction Structure -- Pipe to Trapezoidal Channel

3.00 EA
per Riverside County Flood Std DwgJS 231
$4,200.00
$12,600.00
$4,000.001
$12,000-00
$4,000.00
$12,000.00
$6,000.00
$18,000.00
16 Construct Manhole Pipe -to -Pipe per SPPWC Std Plan 321-2 S.OQ
EA
$7,000.00
$35,000.00
$7,250.00
$36,250.00
$5,000.00
$25,000.00
$15,500.00
577,500.00
04/24/2023 City Council Agenda 107
1 Bid Tabulation -Dunlap Blvd Bridge &
Replacement Project Crossing Wilson Creek April 2023
Channel -Phase 2 Project No. 11098
IE General Engineering
Bea dor Construction Company
KEC Engineering
Riverside Construction Company
Beaumont, CA
Costa Mesa, CA
Corona, CA
Riverside, CA
Item
Item Description
City
Unit
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.
17 Construct Access Road Gate per LACDPW Std Plan 6102-1— 4 00
EA
Mod ifed Picket Railing Double Drive Gate, Location per Plan $7,100.00
$28,400,00
$7,700,00
530,800-00
$15,000.00
$60,000.00
$7,000.00
$28,000-00
18 Construct Access Road Drainage Apron per Plan and Detail on 4,00
EA
Sheet 17
$32,000.001
$128,0D0.00
$16,500.00
$66,000,00
$34,000.00
$136,000.00
$27,500.00
$110,000.00
Construct 6" Thick CAB (per SSPWC Sect 200-2) Access Road 19 per Plan Over Native Soil Compacted to 95% Relative
788,00
SY
Compaction per ASTM 0 155 7
$53,00
$41,764,00
$55.00
$43,340,00
$25,00
$19,700.00
$32,00
$25,216-00
Construct Modified Single Grate Curbside Catch Basin per 20 SSPWC 303.3, Curb Varying from 6" to 1"
1-00
EA
$27 000 00
$27 000 00
$7,250-00
$7,250,00
$12,000.00
$12,000,00
$16,500.00
$16,500.00
21 Raise Existing Sewer to Manhole to Grade

2.00 EA
$3 600-00
$7,200,00
$4,000,00
$8,000,00
$1,700,00
$3,400.00
$1,750-00
$3,500.00
22 Construct Local Depression per Modified San Bernardino 5,00
EA
County Std Plan 203, CF Trans 6" to 8"
$1,400-00
$7,000.00
$4,000.001
$20,000,00
$4,000.00
$20,000.00
$2,500-00
$12,500.00
23 Construct Masonry Wall per SSPWC Std Plan 61.8-3, Type A LOD
LS
515,000.00
$15,000,00
540,000-00
$40,000.00
$20,000.00
$20,000.00
$80,000.00
$80,000,00
24 Construct Rip -Rap Channel per section 3 on Sheet 17 569.00
CY
$50-00
$28,450,00
$170,00
$96,730.00
$715.00
$406,835.00
$450-00
$2.56,050.00
InstalJ Contech's 12-inch Hel-Cor 16-Gage Slotted Drain, or 25 Approved Equal, per Plan & Manufacture's Specifications

21.00 LF
$375,00
$7,875-00
$525-00
$11,025.00
$320.00
$6,720-00
$350.00
$7,350.00
26 furnish & Install 12" CMP per Pian and Profile
32,00
LF
$200.00
$6,40D-00
$350.00
$11,200.00
$250-00
$8,000,00
$230.00
$7,360.00
Construct Residential Driveway per City of Yucaipa Std Plan 27 109-2 and Section A -A, Sheet 8

1.00 EA
$11,550.00
$11,S50.00
$8,500.00
$8,500.00
$12,500-00
$12,500.00
$16,500.0o
$16,500.00
Construct Sidewalk per Modified City of Yucaipa Std Pian 115- 28 2 Type A, Width per Plan
1 248.00
SF
$8-50
510,608.00
$18,00
$22,464.00
$20-00
$24,960.00
$12-001
$14,976.00
Construct AC Roadway per Plan, Profile, and Madified City of Yucaipa Std Plan 102-1 Width Per Plan. Prepare Subgrade 12" 24 Below AB per Geotech Report and Compact to 9 5 % Min 2,637-00
SF
Relative Density per ASTM 0.1557
$25,001
$65,925-00
$10-OD
$26,370,00
$11.00
$29,007,00
$8,00
$21,096.00
30 Construct Thickened Curb and Gutter per Detail 1, Sheet 15 12,00
LF
$45,00
$540-00
$230.00
$2,760.00
$320.00
$3,840-00
$40,00
$480.00
Construct AC Roadway Width Transition, 5" AC Over 6" AB 31 (SPPWC Section 200-1.2), Prepare 5ubgrade 12" 8elow AB per 184 00
SF
Geotech Report and Compact to 95% Relative Density [per ASTM D-1557 , Extents per Plan
$30-00
$5,520-00
$90-00
$16,560,00
$29,00
$5,336.00
$8.00
$1,472,00
04/24/2023 City Council Agenda 108 2

Bid Tabulation -Dunlap Blvd Bridge &
Replacement Project Crossing Wilson Creek April 2023
Channel -Phase 2 Project No. 11098
I General Engineering
Beador Construction Company
KEC Engineering
Riverside Construction Company
Beaumont, CA
Costa Mesa, CA
Corona, CA
Riverside, CA
Item Qty Unit
Description
Unit Price Extension
Unit Price Extension
Unit Price Extension
Unit Price Extension
No,Item
32 Construct AC Dike per San Bernardino County Std Plan 117 111.00
LF
$45.00
$4,995.00
$74.00
58,214.00
$100.00
511,100.00
$30.00
$3,330.00
33 Unidentified Utility Allowance

1.00 AL
$20,000.00
$20,000,00
$20,000,00
$20,000.00
$20,0p0.00
$20,000.00
$20,000,00
$20,000.00
34 Construct Curb Return Sidewalk Ramp per Plan and SPPWC.

Std Plan 111-5, X=10'

1.00 EA
59 500.00
$9,500,001
$6,000.00
$6,000.00
$9,500.D0
$9,500.00
$6,500,00
$6,500.0D
35 Construct Parkway Drain per SPPWC Std Plan 151-2 Inlet Type 2, 5 2
1 00
EA
$7,40D.00
$7,400,00
$4,000.00
$4,000.00
$3,000.00
$3,000,00
54,500.0D
$4,500.00
36 Construct Modified Curb per SPPWC Std Plan 120-2, Type Al 6 (150). Height Varies per Plan
26 00
LF
$35.00
$910,00
$190.00
$4,940.00
$250.D0
$6,500,00
$40.00
$1,040.00
37 Construct Curb Height Transition, Curb Height per Plan

0.20 CY
53,000.00
$600.00
$8,500.D0
$1,700,00
$B4ODD.00
$1,600.00
$5,000.00
51,000.00
38 Demolish Existing Civii Improvements
1,00
LS
$75,000.00
$75,000.00
$55,000,00
$55,000.00
$135,000.00
$135,000,00
$250,000.00
$250,000.00
39 Structure Excavation (Bridge)

44.00 CY
$2,500.00
$110,000.00
$320.00
$14,090.00
$1,500.00
$66,000.00
$100,00
$4,400.00
40 Structural Concrete Bridge

42.00 CY
$3,000,00
$126,000.00
$4,200,00
$176,400.00
$2,350.00
$98,700.00
$2,5D0.00
$105,000.00
41 Drill and Bond Dowel
135.00
LF
$100.00
$13,500,00
$28.00
$3,780.00
$41.00
$5,535,00
$100,DOI
$13,500.00
42 Excavate, Store, Backfili, and Compact as Required
695.00
CY
$75,00
$52,125,00
$240.00
$166,800.00
$60.00
$41,700.00
$140.00
$97,300.00
43 Construct Modified Picket Railing Fence per Plan and LAC FCD 40500
LF,
Std. Plan 6102-1
$320 00
$129,600,00
$203.0D
$82,215,00
$320.00
$129,600,00
$200.00
$81,000.00
44 Construct Sidewalk per Plan and City of Yucaipa Std Plan 115- 2 Type -A
724 OD
SF

59.50 $6,878.00
$21.00
$15,204.00
$17.00
$12,308.00
$10.00
$7,240.00
45 Furnish and Erect Structural Steel

1.00 L5
$374,330.00
$374,330.00
$380,000.00
$380,000.00
$600,000.00
$600,000.00
$420,000.00
$420,000.00
46 Construct Curb Opening Catch Basin with Two Gratings per

1.00 EA
SPPWC 302-3, V=5.2
$15,000.00
$15,000.00
$8,500.00
$8,500.00
$14,000.00
$14,000.00
$16,000.00
$16,000.013
Total
$2,098,054.00
Total
$2,360,300.00
Total
$2,703,255.00
Total
$3,504,937.00
04/24/2023 City Council Agenda 10n
7 3

Attachment 2

AGREEMENT
THIS AGREEMENT is made and entered into this 24th day of April 2023, by and between the City of Yucaipa, a municipal corporation, hereinafter referred to as "City", and I.E. General Engineering, Inc. located at 1440 Ucaurnont Avenue, Ste. A2-130 Contractor/ Company Name Street Address
Beaumont
City
CA 92223 951 616-3311 hereinafter referred to as "Contractor" State Zip Code Phone
PROJECT- Dunlap Slvd Bride c�c Rctslsicenient Project Crossing Wilson Creek Channel Phase 2 Project No.11098 - — — —
WITNESSETH, in this consideration of their covenants, the parties hereto agree as follows:

The contract documents for the Project shall consist of the Notice Inviting Sealed Bids, Instructions to Bidders, Proposal, General Specifications, Standard Specifications, Special Provisions, Plans, and all referenced specifications and appendices; together with this Agreement and all required bonds, insurance certificates, permits, notices, and affidavits; and also including any and all addenda or supplemental agreements clarifying, amending, or extending the work contemplated as may be required to insure its completion in an acceptable manner (collectively, the "Contract Documents"). The Contract Documents are made a part hereof as trough fully set forth herein.

In consideration of such work, City agrees to pay Contractor and Contractor agrees to accept the sum of Two Million _Ninety-Eit;lit Thonssurtl _Fifty -Four Dollars and Zero Cents (S2,099,064,00) in the manner provided in the Contract Documents and subject to adjustment provided therein_
Concurrently with the execution of this Agreement, Contractor shall file with the City the bonds and certificates of insurance specified in the Contract Documents and subject to adjustment provided therein.

This Contract shall not be assigned without the written pennission of the City Council, IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and year first above written.

ATTEST:

Ana Sauseda, City Clerk

FUNDS AVAILABLE/INSURANCE
APPROVED:

Phillip White, Director of Finance
Fermin G. Preciado, Director of
Development Services/City Engineer
APPROVED AS TO FORM:

Steven Graham, City Attorney

CITY OF YUCAIPA
A Municipal Corporation
,Justin Beaver, Mayor
CONTRACTOR:
1 E General Engineering Inc_
Date
Date
04/24/2023 City Council Agenda 110

Attachment 3
AMENDMENT NO, 5

AGREEMENT WITH CITY OF YUCAIPA FOR THE PROFESSIONAL ENGINEERING

DESIGN OF THE DUNLAP BOULEVARD BRIDGE REMOVAL AND REPLACEMENT

PROJECT CROSSING WISLON CREEK CHANNEL
THIS AMENDMENT, made and entered into this 24th day of April, 2023, by and between DUDEK, hereinafter called "CONSULTANT," and City of Yucaipa, a municipal corporation, hereinafter called "CITY,"
NOW, THEREFORE, CONSULTANT and CITY mutually agree as follows:

Subject to the terms and conditions of the original agreement dated March 25th, 2019, between subject CONSULTANT" and CITY, and Amendment No. 1-4 to the original agreement, and Amendment No. 5 to the original agreement dated April 2411, 2023, shall be as follows for the design of the Dunlap Boulevard Bridge Removal and Replacement Project Crossing Wilson Creek Channel.

Original Agreement Amount
$218,593
Amendment No. 1
$18,740
Amendment No. 2
$14,953
Amendment No. 3
$10,027
Amendment No. 4
$20,000
Amendment No. 5
$30 Q00
Revised Agreement Amount
$312,313
CITY Fee and Payment Thereof
The CITY will pay the CONSULTANT for services rendered in the total amount NOT TO EXCEED $30,000 for the additional contract design services to provide construction support services.

IN WITNESS WHEREOF, the parties hereto have executed this agreement on the 24`' day of April, 2023.

Dudek CITY of Yucaipa
Date Authorized Agent for City Date
04/24/2023 City Council Agenda 111