Agenda Item No.
CITY OF YUCAIPA
AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Services/City Engineer^? Landon Kern, Assistant City Engineer L K
FOR: City Council Meeting of August 14, 2023
SUBJECT: Acceptance of Contract Work — Adams Street and Avenue B Street Sidewalk Improvements CDBG Project — Project No. 11089
RECOMMENDATION:
That the City Council:
1) Accept the contract and extension work completed by Three Peaks Corp. in the amount of $571,946.74 for the Adams Street and Avenue B Street Sidewalk Improvements CDBG Project — Project No. 11089; and
2) Authorize the recordation of the Notice of Completion for the Project; and 3) Approve the as -built plans and specifications for the Project.
BACKGROUND/DISCUSSION:
The approved FY2022/2023 Capital Improvement Program (CIP) includes multiple projects funded through the Community Development Block Grant (CDBG) Program. The CDBG Grant Program provides funding for pedestrian and transit related improvements such as sidewalk, curb ramps, bus stop improvements and curb/gutter. One of these projects is the Adams Street and Avenue B Street Sidewalk Improvements Project (Project). A total of $570,133 in CDBG funds is available for the Project. In addition to other funding sources, the Project also includes $50,502 in TDA Article 3 Grant Funds specifically identified for bus stop landing and sidewalk improvements along the Omnigo Route 310 bus route.
The Project consists of constructing curb, gutter, sidewalk, bus stop improvements, and concrete drive approaches along the east and west side of Adams Street between Yucaipa Boulevard and Avenue B, and on the north side of Avenue B from Adams Street to 1 st Street.
On October 10, 2022, the City Council awarded a construction contract to Three Peaks Corp. of Calimesa, CA in the amount of $547,635. The City Council also approved the amount of $55,000 for construction contract contingency and $43,000 for construction contract administration staff time, inspection, and testing, for a total construction budget in the amount of $645,635.
Throughout the course of construction, staff approved Change Orders 1 through 4 for a net increase in the amount of $24,312. The change orders included additional items of work such as additional tree removals, concrete driveway removal and replacement, fire hydrant relocation, concrete curb/flatwork and cross gutter required to construct the Project. The total approved change order amount of $24,312 are less than the construction contract contingency amount of $55,000 approved by City Council for this contract.
The construction of the Project has been completed. Field inspections performed by staff during the course of the work and upon completion of the work have assured that the work was completed according to the as -built plans and specifications for the Project. As a result, staff is recommending that the City Council accept the contract work, approve the final payment and direct staff to file the Notice of Completion for the Project.
FISCAL IMPACT:
The table below includes the approved available funding for the Project:
Funding Sources
Amount
Community Development Block Grant (CDBG) Funds
$570,133
Pavement Management Program (PMP) Funds
$95,000
Air Quality Management District AQMD Funds
$25,000
TDA Article 3 Grant Funds
$50,502
Total Available Funding
$740,635
The total budgeted and actual construction costs are shown in the table below:
Budgeted Amount
Actual Costs
Construction Contract
$547,635
$547,635
Construction Contract Contingency
$55,000
$24,312
Construction Contract Admin./
Inspection/Survey/Testing/coordination
$43,000
$43,000
Total Construction Cost
$645,635
$614,947
Balance Remaining
$30,689
The table below includes the total actual costs to date for the Project:
Project Costs
Amount
Non -Construction Engineering/Survey/Utility Coordination/Grant Program Administration
$95,000
Construction Costs (From Table Above)
$614.947
Total Project Costs to Date
$709,947
As shown in the tables above, the actual cost of the construction of the Project in the amount of $614,947 is less than the budget amount approved by the City Council in the amount of $645,635.
No further fiscal impact is being requested.
Attachments:
1. Notice of Completion — Project No. 11089
Approved by: r�
Attachment 1
RECORDING REQUESTED BY
City of Yucaipa
WHEN RECORDED RETURN TO:
City Clerk
City of Yucaipa
34272 Yucaipa Blvd.
Yucaipa, CA 92399
Recording Fee $0 SPACE ABOVE THIS LINE FOR RECORDER'S USE Government Code 6103
NOTICE OF COMPLETION
Pursuant to the provisions of Section 9204 of the Civil Code of the State of California, NOTICE IS HEREBY GIVEN that work on the certain project known as:
PROJECT NO. 11089
ADAMS STREET AND AVENUE B STREET SIDEWALK IMPROVEMENTS
CDBG PROJECT
No APN Number
for the City of Yucaipa was completed and accepted by the City of Yucaipa on the 14th day of August 2023
The said work was performed by Three Peaks Corporation of Calimesa, CA in accordance with the terms of the written agreement dated the 10th day of October 2022.
Dated August 14, 2023
CITY OF YUCAIPA, a Municipal Corporation, Owner
34272 Yucaipa Blvd, Yucaipa, CA 92399
Fermin G. Preciado, Director of Development Services/City Engineer A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or validity of the document.
STATE OF CALIFORNIA
COUNTY OF SAN BERNARDINO
Subscribed and sworn to (or affirmed) before me on this 14th day of August 2023, by Fermin G. Preciado, proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.
Date
Ana V. Sauseda, CMC
Director of General Services/City Clerk