Cities Index.
Item 11 - Change Order No. 1 Pickleball Courts

Yucaipa City Council
October 23, 2023

Document
Item 11 - Change Order No. 1 Pickleball Courts
Meeting
October 23, 2023
Body
Yucaipa City Council
Pages
5
Original file
6 KB
Text extracted from the city's file for reading and search. Open the original on coydocs.yucaipa.gov. That file is the official record.

Agenda Item No.

CITY OF YUCAIPA

AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Services/City Engineery Landon Kern, Assistant City Engine LI!
Todd Gutjahr, Public Works Analys
FOR: City Council Meeting of October 23, 2023
SUBJECT: Change Order No. 1 - 7th Street Pickleball Courts — Concrete Footings and Steel Structure/Cover Installation Project — Project No. 11150-2 RECOMMENDATION:

That the City Council approve and authorize the City Manager to execute Change Order No. 1 to the contract with Three Peaks Corporation in the amount of $21,291.92 for the 7th Street Pickleball Courts — Concrete Footings and Steel Structure/Cover Installation Project — Project No. 11150-2, for a revised contract amount of $177,141.92.

BACKGROUND/DISCUSSION:

On September 12, 2022, the City Council approved the revised Conceptual Pickleball Master Plan for the 7th Street Pickleball facility and approved the development of Phase 1 of the facility which includes the following:

1. Removal of the existing 7th Street Modular Skate Park equipment and construction of four new pickleball exclusive courts.

2. Installation of a steel structure over the four proposed pickleball courts that emulates/expands the existing steel structure cover.

3. Installation of lighting under the new steel structure cover over the four pickleball courts.

4. Demolition of the existing theatre building located east of the existing basketball courts.

On January 23, 2023, the City Council awarded a contract to Western Steel Buildings of Park City, Utah (Western Steel) for the Engineering Design and Fabrication Services Including Delivery for Yucaipa Pickleball Court Cover Project— Project No. 11150 in the amount of $149,702.46 and approved a total project budget of $169,702.46.

On August 28, 2023, the City Council awarded a contract to Three Peaks Corporation of Calimesa, CA (Three Peaks) for the 7th Street Pickleball Courts — Concrete Footings and Steel Structure/Cover Installation — Project No. 11150-2 (Project). The Project consists of installing the

concrete footings for the steel structure cover, leveling the existing concrete surface, and installing the steel structure per the plans and specifications.

During the excavation for the installation of the concrete footings required for the steel structure, unanticipated soil conditions, including rocks/boulders were encountered to be in conflict with the concrete footings. Staff consulted with the City's structural engineer/architect who designed the footings to address the unanticipated soil conditions. Since the rocks and boulders that were encountered limited the excavation for the concrete footings, the most cost-effective solution was determined to be the construction of additional horizontal concrete footings to mitigate the unforeseen conditions. This will result in additional costs for concrete and steel to construct the horizontal concrete footings.

This additional work is required to complete the installation of the steel structure. As a result, staff is recommending that the City Council approve Change Order No. 1 to the contract with Three Peaks in the amount of $21,291.92.

FISCAL IMPACT:

The FY24 Annual Budget includes the cost of the additional $21,291.92.

Attachments:

1. Contract Change Order No. 1 - Three Peaks Corporation Approved by: -'��

Attachment 1

City of
POO*

PUBLIC WORKS DIVISION
Date: 10/23/2023 City Project No
Contract No
Contract Amendment No. 1
Contractor: Three Peaks Corporation
11150-2
20441
Project: 7th Street Pickleball Courts — Concrete Footings and Steel Structure/Cover Installation — Project No. 11150-2 Chance Proposed:

Additive:

1. Construct grade beam between North footing per revised plan by Psomas and extension of roof line to mitigate drip line between new cover and existing cover. $ 21,291.92
Deductive: None
The additive and/or deductive work as stated above is compensable as Changes In Work under the provisions of Section 3 of Standard Specifications for Public Works Construction (Latest Edition).

Deductive Additive
$0.00 $21,291.92
Adjustment of Contract Time of Completion: N/A
Agreed Contract Change Order price:

Contract Amount: $ 155,850.00
Previously Approved Change Order Numbers: $ -
Previously Approved Contract Change Order Amount: $ 155,850.00 New/Revised Total Contract Amount:

Approved by City Engineer:

Approved by City Manager:

Accepted by:

Three Peaks Corporation
$21,291.92
$177,141.92
Date
Date
Date

THREE PEAKS CORP.

CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME: 7th Street Pickball Cover C.O.R. NO.:

PROJECT NO: CRBIFI REF.:

GENERAL CONTRACTOR: Three Peaks Corp. DATE:

DESCRIPTION OF CHANGE: Construct grade beam between North footing per revised plan by Psomas. 1016/2023
Extension of roof line to mitigate drip line between new cover and existing cover. Roof materials provided by Owner.

General Contractor Costs
Additive Costs
Labor
Material 1 $7,563.24
Equipment 5.

Subtotal of Additive Cost 1 $17,690.20
Deductive Costs (use minus sign to denote negative figures) Labor
Material
Equipment
Subtotal of Deductive Cost
Contractor's Total Cost
Contractor's Mark-up
Total Subcontractor Costs
General Contractor's Mark-up on Subcontractor Costs
General Contractor's Bond
General Contracotr's Insurance
$0.00
$208.74
$208.74
Total General Contractor Change Request $21,291.92

← All documents from this meeting