Agenda Item No.

CITY OF YUCAIPA

AGENDA REPORT
TO: Honorable Mayor and City Council
FROM: Fermin Preciado, Director of Development Services/City Engineer Landon Kern, Assistant City Engineer ale
Crystal Campbell, Associate Engineeropl-&
FOR: City Council Meeting of November 13, 2023
SUBJECT: Reject All Bids — Phase II-B Yucaipa Boulevard ADA Improvements 2nd Street to 5th Street, — Project No. 10959-2
RECOMMENDATION:

That the City Council:
1) Reject all bids for Phase I1-B Yucaipa Boulevard ADA Improvements 2nd Street to 5th Street, — Project No. 10959-2; and
2) Direct Staff to rebid the Project and conduct additional outreach for construction bids.

BACKGROUNDMISCUSSION:

Phase II-B of the Yucaipa Boulevard ADA Improvements 2nd Street to 5th Street Project (Project) consists of constructing curb, gutter, sidewalk, ADA curb ramps, bike lanes, and associated street improvements between 3rd Street and 4th Street.

The construction of Phase I between 4th Street and 5th Street was completed in August of 2016, with the construction of Phase II -A between 2"d Street and Yd Street following in October of 2019. The overall completed project will join with the street improvements completed in 2011 as part of the Uptown Streetscape Project. By completing the Project, the pedestrian and street improvements on Yucaipa Boulevard will be completed from 5th Street, to just west of the Bryant Street intersection, which is in line with the City Council's goal to focus on the completion of current projects and facilities, as well as the goal to enhance pedestrian safety. The Project is consistent with the City's General Plan.

The Project was advertised for construction bids in September of 2023. On October 12, 2023, five (5) sealed bids were received and opened as follows:

Contractor
Bid Amount
Three Peaks Corporation
$1,215,908.50
I.E. General Engineering, Inc.
$1,571,020.00
LCR Earthworks
$1,722,572.25

Onyx Paving Company, Inc. $1,727,000.00
Hardy & Harper $1,930,000.00
Engineer's Estimate $840,000
The amounts of the bids received were significantly higher than the engineer's estimate due to the current high costs of construction associated with labor and material shortages, among other economic factors. Staff believes that re -advertising the Project at a later date, and conducting outreach to potential contractors will allow for more bidders to submit bid proposals, and therefore result in more competitive bids. Consequently, staff is recommending that the City Council reject all bids for the Project.

FISCAL IMPACT:

None
Attachments:

1. Bid Summary
Approved by:�

Attachment 1

Bid Tabulation -Yucaipa Blvd Streetscape
Improvements 2nd to 5th St PhaseII-B 3rd to Oct-23
4th
IE General Engineering
Onyx Paving Company Inc
Three Peaks
LCR Earthworks
Hardy & Harper
Beaumont, CA
Item
Item Description
Qty
Unit
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.
1 Mobilization (Not To Exceed 5% of Base Bid)

1.00 LS
$70,000.00
$70,000.00
$77,000.00
$77,000.00
$40,000.00
$40,000.00
$82,027.25
$82,027.25
$95,000.00
$95,000.00
2 SWPPP Preparation and Implementation

1.00 LS
$8,000.00
$8,000.00
$11,000.00
$11,000.00
$35,000.00
$35,000.00
$15,000.00
$15,000.00
$15,000.00
$15,000.00
3 Traffic Control

1.00 LS
$150,000.00
$150,000.00
$333,000.00
$333,000.00
$40,000.00
$40,000.00
$85,000.00
$85,000.00
$222,060.00
$222,060.00
4 Sawcut & Remove Existing AC Pavement
29,000.00
SF
$4.00
$116,000.00
$2.22
$64,380.00
$3.25
$94,250.00
$2.50
$72,500.00
$2.00
$58,000.00
5 Sawcut & Remove Existing Curb or Curb and Gutter
2,290.00
LF
$12.00
$27,480.00
$22.00
$50,380.00
$15.00
$34,350.00
$12.00
$27,480.00
$25.00
$57,250.00
6 Sawcut &Remove Existing Concrete
15,400.00
SF
$4.00
$61,600.00
$5.55
$85,470.00
$3.25
$50,050.00
$5.50
$84,700.00
$9.00
$138,600.00
7 Remove Portion of Existing Wall in Right of Way

42.00 LF
$180.00
$7,560.00
$222.00
$9,324.00
$100.00
$4,200.00
$85.00
$3,570.00
$265.00
$11,130.00
Relocate Existing Water Meter Per Utility Owner
8 Standards

6.00 EA
$8,000.00
$48,000.00
$6,000.00
$36,000.00
$3,500.00
$21,000.00
$3,500.00
$21,000.00
$12,000.00
$72,000.00
9 Remove, Salvage &Replace Existing Bus Bench/Shelter

2.00 EA
$2,400.00
$4,800.00
$9,000.00
$18,000.00
$6,500.00
$13,000.00
$5,000.00
$10,000.00
$6,000.00
$12,000.00
10 Remove, Salvage & Replace Existing Sign on New Post

12.00 EA
$650.00
$7,800.00
$500.00
$6,000.00
$500.00
$6,000.00
$800.00
$9,600.00
$400.00
$4,800.00
11 Relocate Existing Fence Behind Right of Way

60.00 LF
$95.00
$5,700.00
$222.00
$13,320.00
$48.00
$2,880.00
$550.00
$33,000.00
$275.00
$16,500.00
12 Remove Existing Pilaster

2.00 EA
$550.00
$1,100.00
$2,200.00
$4,400.00
$500.00
$1,000.00
$2,000.00
$4,000.00
$3,500.00
$7,000.00
13 Remove Existing Tree

2.00 EA
$2,500.00
$5,000.00
$5,500.00
$11,000.00
$5,000.00
$10,000.00
$2,500.00
$5,000.00
$5,000.00
$10,000.00
14 Remove existing Bollard

6.00 EA
$500.00
$3,000.00
$1,000.00
$6,000.00
$500.00
$3,000.00
$600.00
$3,600.00
$1,300.00
$7,800.00
15 Relocate Existing Business Sign Behind Right of Way

2.00 EA
$22,000.00
$44,000.00
$13,500.00
$27,000.00
$2,500.00
$5,000.00
$900-001
$1,800.00
$3,500.001
$7,000.00

Bid Tabulation -Yucaipa Blvd Streetscape
Improvements 2nd to 5th St PhaseII-B 3rd to Oct-23
4th
IE General Engineering
Onyx Paving Company Inc
Three Peaks
LCR Earthworks
Hardy & Harper
Beaumont, CA
Item
Item Description
Qty
Unit
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.
16 Remove, Salvage & Replace Existing Newspaper Stand

5.00 EA
$500.00
$2,500.00
$2,200.00
$11,000.00
$500.00
$2,500.00
$400.00
$2,000.00
$2,500.00
$12,500.00
Sawcut & Remove Existing Concrete V-Gutter & Cutoff
17 Wall.

55.00 SF
$20.00
$1,100.00
$55.00
$3,025.00
$50.00
$2,750.00
$15.00
$825.00
$20.00
$1,100.00
Relocate Existing Concrete Sign Base Behind Right Of
18 Way

1.00 EA
$6,000.00
$6,000.00
$6,000.00
$6,000.00
$2,500.00
$2,500.00
$1,300.00
$1,300.00
$1,000.00
$1,000.00
19 Sawcut And Remove Existing AC Berm
100.00
LF
$15.00
$1,500.00
$22.00
$2,200.00
$5.00
$500.00
$10.00
$1,000.00
$20.00
$2,000.00
20 Remove Existing Sign Post

6.00 EA
$200.00
$1,200.00
$200.00
$1,200.00
$50.00
$300.00
$300.00
$1,800.00
$125.00
$750.00
21 Remove, Salvage & Replace Existing Mailbox Bank

1.00 EA
$2,500.00
$2,500.00
$6,000.00
$6,000.00
$500.00
$500.00
$650.00
$650.00
$1,500.00
$1,500.00
22 Remove Existing Utility Pole Anchor

1.00 EA
$3,000.00
$3,000.00
$10,303.50
$10,303.50
$3,000.00
$3,000.00
$2,500.00
$2,500.00
$1,500.00
$1,500.00
Remove and Replace Existing Fire Hydrant at Final
23 Grade

1.00 EA
$8000.00
$8,000.00
$11,000.00
$11,000.00
$15,500.00
$15,500.00
$25,000.00
$25,000.00
$19,000.00
$19,000.00
24 Remove Existing Concrete Curb Stop

5.00 EA
$100.00
$500.00
$200.00
$1,000.00
$150.00
$750.00
$500.00
$2,500.00
$130.00
$650.00
25 Construct 3" AC/4" 2-Sack Slurry
2,400.00
SF
$12.50
$30,000.00
$5.55
$13,320.00
$8.20
$19,680.00
$20.00
$48,000.00
$19.00
$45,600.00
Edge Grind & Construct 2" AC Overlay per City Std.
26 160-0
13,100.00
SF
$4.60
$60,260.00
$3.33
$43,623.00
$5.20
$68,120.00
$2.00
$26,200.00
$4.50
$58,950.00
27 Construct 8" Curb &Gutter Per SBCO Std. 115
1,195.00
LF
$42.00
$50,190.00
$77.00
$92,015.00
$58.00
$69,310.00
$70.00
$83,650.00
$80.00
$95,600.00
28 Construct 6" Curb per APWA Std. 120-3, Type Al-6

60.00 LF
$40.00
$2,400.00
$66.00
$3,960.00
$51.00
$3,060.00
$95.00
$5,700.00
$80.00
$4,800.00
29 Construct 4" PCC Sidewalk per City Std. 115-2
7,630.00
SF
$6.00
$45,780.00
$11.00
$83,930.00
$12.30
$93,849.00
$14.00
$106,820.00
$12.001
$91,560.00
Construct Modified Curb Ramp to Conform to APWA
30 Std. Plan 111-5
500.00
SF
$7.50
$3,750.00
$22.00
$11,000.00
$40.00
$20,000.00
$45.00
$22,500.00
$20.00
$10,000.00

Bid Tabulation -Yucaipa Blvd Streetscape
Improvements 2nd to 5th St PhaseII-B 3rd to Oct-23
4th
IE General Engineering
Onyx Paving Company Inc
Three Peaks
LCR Earthworks
Hardy & Harper
Beaumont, CA
Item
Item Description
Qty
Unit
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.
31 Construct 8" Curb per APWA Std. 120-3, Type Al-8
140.00
LF
$45.00
$6,300.00
$66.00
$9,240.00
$55.00
$7,700.00
$65.00
$9,100.00
$80.00
$11,200.00
Construct Commercial Driveway Approach per City Std.
32 110-1
15,000.00
SF
$12.00
$180,000.00
$17.00
$255,000.00
$13.00
$195,000.00
$30.00
$450,000.00
$23.00
$345,000.00
Extend PVC Curb Drain Through Curb Face Per Mod
33 APWA Std. Plan 150-4

2.00 EA
$1,500.00
$3,000.00
$1,000.00
$2,000.00
$200.00
$400.00
$6,500.00
$13,000.00
$3,200.00
$6,400.00
34 Remove & Replace Existing Pullbox at Final Grade

2.00 EA
$2,000.00
$4,000.00
$2,200.00
$4,400.00
$450.00
$900.00
$5,000.00
$10,000.00
$2,500.00
$5,000.00
35 Adjust Existing Meter or Vault to Grade

7.00 EA
$6,500.00
$45,500.00
$3,300.00
$23,100.00
$500.00
$3,500.00
$500.00
$3,500.00
$2,500.00
$17,500.00
36 Adjust Existing Fire Hydrant to Grade

3.00 EA
$8,500.00
$25,500.00
$3,300.00
$9,900.00
$4,500.00
$13,500.00
$3,500.00
$10,500.00
$2,500.00
$7,500.00
37 Adjust Existing Valve Cover to Grade

2.00 EA
$1,200.00
$2,400.00
$600.00
$1,200.00
$500.00
$1,000.00
$400.00
$800.00
$1,600.00
$3,200.00
38 Adjust Existing Manhole to Grade

12.00 EA
$4,500.00
$54,000.00
$1,000.00
$12,000.00
$2,720.00
$32,640.00
$1,200.00
$14,400.00
$1,600.00
$19,200.00
39 Install 24" and 1-2" Sch. 40 PVC Irrigation Sleeves
950.00
LF
$30.00
$28,500.00
$66.00
$62,700.00
$48.00
$45,600.00
$25.00
$23,750.00
$75.00
$71,250.00
Remove, Repair & Replace Existing Landscape and
40 Irri ation
9,500.00
SF
$15.00
$142,500.00
$5.00
$47,500.00
$1.50
$14,250.00
$7.00
$66,500.00
$4.00
$38,000.00
41 Install 6' Precast Concrete Curb Stop

9.00 EA
$200.00
$1,800.00
$200.00
$1,800.00
$150.00
$1,350.00
$200.00
$1,800.00
$100.00
$900.00
42 Construct 3" AC/3" PMB
10,750.00
SF
$5.00
$53,750.00
$5.55
$59,662.50
$7.10
$76,325.00
$7.50
$80,625.00
$8.50
$91,375.00
Install 2-2" Sch. 80 PVC Conduits For Future Street
43 Lighting
1,310.00
If
$100.00
$131,000.00
$44.00
$57,640.00
$46.00
$60,260.00
$75.00
$98,250.00
$80.00
$104,800.00
44 Install #6 Pullbox Per Caltrans Std. Plan ES-8

9.00 EA
$1,100.00
$9,900.00
$2,200.00
$19,800.00
$1,525.00
$13,725.00
$5,500.00
$49,500.00
$1,000.00
$9,000.00
45 Adjust Existing Electrical Cabinet To Grade

1.00 EA
$6,500.00
$6,500.00
$9,000.0
$$9,000.00
$3,500.00
$3,500.00
$10,500.00
$10,500.00
$5,000.00
$5,000.00

Bid Tabulation -Yucaipa Blvd Streetscape
Improvements 2nd to 5th St PhaseII-B 3rd to Oct-23
4th
IE General Engineering
Onyx Paving Company Inc
Three Peaks
LCR Earthworks
Hardy & Harper
Beaumont, CA
Item
Item Description
Qty
Unit
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
Unit Price
Extension
No.

Construct Concrete Slough Wall Per L.A. County DPW
46 plan 6203-1

30.00 LF
$700.00
$21,000.00
$333.00
$9,990.00
$250.00
$7,500.00
$550.00
$16,500.00
$360.00
$10,800.00
47 Install Truncated Domes Per APWA Std Plan 111-5

5.00 EA
$650.00
$3,250.00
$1,400.00
$7,000.00
$670.00
$3,350.00
$750.00
$3,750.00
$3,000.00
$15,000.00
48 Construct 8" Asphalt Concrete Dike Per SBCO Std 117

40.00 LF
$65.00
$2,600.00
$33.00
$1,320.00
$99.00
$3,960.00
$25.00
$1,000.00
$115.00
$4,600.00
49 Adjust Existing Cleanout To Grade

2.00 EA
$900.00
$1,800.00
$1,000.00
$2,000.00
$250.00
$500.00
$900.00
$1,800.00
$1,600.00
$3,200.00
50 Construct PCC Concrete Swale Per Detail On Sheet 2

65.00 SF
$80.00
$5,200.00
$55.00
$3,575.00
$12.30
$799.50
$55.00
$3,575.00
$25.00
$1,625.00
Construct Parkway Drain Per APWA Std Plan 151-2.
51 T e Per Plan

2.00 EA
$6,500.00
$13,000.00
$13,000.00
$26,000.00
$4,850.00
$9,700.00
$5,500.00
$11,000.00
$14,000.00
$28,000.00
Construct Concrete Block Slough Wall Per APWA Std
52 Plan 622-3

6.00 LF
$800.00
$4,800.00
$1,111.00
$6,666.00
$500.00
$3,000.00
$1,000.00
$6,000.00
$1,200.00
$7,200.00
Remove and Reconstruct Existing Brick Planter To Like
53 or Better Condition

32.00 LF
$500.00
$16,000.00
$333.00
$10,656.00
$200.00
$6,400.00
$500.00
$16,000.00
$425.00
$13,600.00
54 Proposed Striping Per Plan

1.00 LS
$30,000.00
$30,000.00
$33,000.00
$33,000.00
$49,000.00
$49,000.00
$32,000.00
$32,000.00
$30,000.00
$30,000.00
Total
$1,571,020.00
Total
$1,727,000.00
Total
$1,215,908.50
Total
$1,722,572.25
Total
$1,930,000.00