Agenda Item No.
CITY OF YUCAIPA
AGBNDA REPORT
FROM:
Honorable Mayor and City Council
Fermin Preciado, Director of Development Services/City Engineer L/( f'D( f - ? Landon Kern, Assistant City Engineer Ll(
Daniel Meisenbach, Construction Engineer D*(
FOR:City Council Meeting of February 12,2024
SUBJECT: Acceptance of Contract Work - Installation of Asphalt Speed Humps on Adams Street Project - Project No. I I199
RECOMMENDATION:
That the City Council
I ) Accept the contract work completed by NPG Corporation of Perris, CA. in the amount of $26,198 forthe Installation of Asphalt Speed Humps on Adams Street Project- Project No. lll99and;
2) Authorize the recordation of the Notice of Completion for the Project.
BACKGROUND/DISCUSSION :
In 2008, the City Council adopted the FY200712008 Neighborhood Traffic Calming Program (Program) for the City of Yucaipa. The intent of the Program is to create an objective and consistent process to address traffic issues on residential streets such as speeding, parking and other safety-related matters.
On September 25, 2023, the implementation of seven (7) mitigation measures were approved by the City Council to address concerns that were determined to be of significance under the Program.
One of the approved measures included the installation of permanent asphalt speed humps on Adams Street between Avenue D and Avenue E. As a result, staff prepared the plans, specifications, and bid documents for the Installation of Asphalt Speed Humps on Adams Street Project, Project No. lll99 (Project). This includes the installation of permanent asphalt speed humps and associated signage and striping.
On November I 3h 2023 , the City Council awarded a contract to NPL Corporation of Perris, CA for the Project in the amount of $26,198. The City Council also approved the amount of $5,000 for contract contingency, for a total construction budget in the amount of $31,198.
Inspections performed by staff during the course of the work and upon completion of the work have ensured that the work was completed in accordance with the contract specifications for the Project.
Staff is recommending acceptance of the contract work for the Project in the amount of $26,198.
FISCAL IMPACT:
There is no additional fiscal impact as a result of the proposed recommendations.
Attachments:
1. Notice of Completion - Project No. 1l199
Approved by -4 ,z-
Attachment I
RECORDING REQUESTED BY
City of Yucaipa
WHEN RECORDED RETURN TO:
City Clerk
City of Yucaipa
34272 Yucaipa Blvd
Yucaipa, CA 92399
Recording Fee $0 SPACE ABOVE THIS LINE FOR RECORDER'S USE Government Code 6103
NOTICE OF COMPLETION
Pursuant to the provisions of Section 9204 of the Civil Code of the State of California, NOTICE lS HEREBY GIVEN that work on the certain project known as:
PROJECT NO. 11199
INSTALLATION OF ASPHALT SPEED HUMPS ON ADAMS STREET
No APN Number
for the City of Yucaipa was completed and accepted by the City of Yucaipa on the 12th day of February 2024.
The said work was performed by NPG Corporation of Perris, CA in accordance with the terms of the written agreement dated the 13th day of November 2023.
Dated February 12,2024
CITY OF YUCAIPA, a Municipal Corporation, Owner
34272 Yucaipa Blvd, Yucaipa, CA 92399
Fermin G. Preciado, Director of Development Services/City Engineer A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or valid of the document.
STATE OF CALIFORNIA
COUNTY OF SAN BERNARDINO
Subscribed and sworn to (or affirmed) before me on this 12th day of February 2024 by Fermin G. Preciado, proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.
Date
)
)
Ana Sauseda, Director of General Services/City Clerk