Cities Index.
Item 07 - Acceptance of Contract Work Replacement Installation of Carpet and Flooring at the Senior Center

Yucaipa City Council
February 23, 2026

Document
Item 07 - Acceptance of Contract Work Replacement Installation of Carpet and Flooring at the Senior Center
Meeting
February 23, 2026
Body
Yucaipa City Council
Pages
4
Original file
5 KB
Text extracted from the city's file for reading and search. Open the original on coydocs.yucaipa.gov. That file is the official record.

DATE:

TO:

FROM:

PREPARED BY:

Item No. 7

STAFF REPORT
February 23, 2026
Honorable Mayor and City Council
Dr. Sean M. Moore, City Manager fit,/Fermin Preciado, Director of Development Services/City Engineer Scott Washburn, Deputy Director of Public Works,_��
Todd Gutjahr, Public Works Analyst
SUBJECT: Acceptance of Contract Work — Replacement/Installation of Carpet and Flooring at the Scherer Community Center— Project No. 11228 (CDBG Project No. YUCA-24-1-03A/0286)
RECOMMENDATION:

That the City Council:

Accept the contract work completed by Del Mar Flooring Covering, Inc. in the amount of $68,000 for the Replacement/Installation of Carpet and Flooring at the Scherer Community Center — Project No. 11228 (CDBG Project No. YUCA-24-1-03A/0286); and

2. Authorize the recordation of the Notice of Completion for the Replacement/Installation of Carpet and Flooring at the Scherer Community Center — Project No. 11228 (CDBG Project No. YUCA-24-1-03A/0286); or

3. Provide further direction to staff.

BACKGROUND/DISCUSSION:

The Adopted FY26 Capital Improvement Program (CIP) includes several projects funded by the Community Development Block Grant (CDBG) Program. The CDBG Program provides funding for pedestrian and transit -related improvements, such as sidewalks, ADA curb ramps, and bus stop upgrades. It also funds enhancements to public facilities and buildings. In 2024, staff recommended and Council approved, the submission of an application seeking CDBG Program funding to replace the flooring and carpet at the Scherer Community Center (Center). The Center's flooring was over 20 years old, with significant wear from heavy use, including cracked tiles and torn carpet. The City's request for $80,000 in CDBG Program funding was subsequently approved.

The Replacement and Installation of Carpet and Flooring at the Scherer Community Center - Project No. 11228 (CDBG Project No. YUCA-24-1-03A/0286) (Project) involved removing and replacing 02/23/2026 City Council Agenda

flooring and carpet throughout the Center. The scope of work included, but was not limited to, removing and replacing Luxury Vinyl Tile (LVT) and carpet, cleaning and preparing subfloors, placing new rubber cove base, installing and finishing new LVT and carpet, and disposing of existing flooring materials. The Project also included material testing of the existing flooring prior to the installation of the new flooring to identify the presence of potentially hazardous materials. The test results were provided in an asbestos survey report (Report) to City staff, which identified the presence of asbestos underneath the existing flooring in the tile adhesive. The Report was helpful to identify the manner in which the new flooring installation could be accomplished by not disturbing the existing flooring materials.

After going through the public competitive bid process, on December 8, 2025, the City Council awarded a contract to Del Mar Floor Covering, Inc. in the amount of $55,000 to complete the Project.

The City Council also approved a contract contingency amount of $13,000, for a Project contract total of $68,000. Inspections were performed during the work and upon completion to ensure that the work was completed in accordance with the contract specifications.

The contract work has been completed for a total Project cost of $68,000, which totals the authorized construction contract and contingency amount for the Project. All expenditures are eligible for reimbursement through the CDBG Program.

FISCAL IMPACT:

The recommendations do not result in a fiscal impact.

Attachments:

1. Notice of Completion — Project No. 11228
02/23/2026 City Council Agenda

ATTACHMENT 1
02/23/2026 City Council Agenda

RECORDING REQUESTED BY
City of Yucaipa
WHEN RECORDED RETURN TO:

City Clerk
City of Yucaipa
34272 Yucaipa Blvd.

Yucaipa, CA 92399
Recording Fee $0
Government Code 6103

SPACE ABOVE THIS LINE FOR RECORDER'S USE

NOTICE OF COMPLETION
Pursuant to the provisions of Section 9204 of the Civil Code of the State of California, NOTICE IS HEREBY GIVEN that work on the certain project known as:

REPLACEMENT/INSTALLATION OF CARPET AND FLOORING AT THE
SCHERER COMMUNITY CENTER — PROJECT NO. 11228 (CDBG PROJECT NO. YUCA-24-1-03A/0286)
for the City of Yucaipa was completed and accepted by the City of Yucaipa on the 23rd day of February 2026.

The said work was performed by Del Mar Flooring Covering, Inc. of Ontario, CA in accordance with the terms of the written agreement dated the 8th day of December 2025.

Dated February 23, 2026.

CITY OF YUCAIPA, a Municipal Corporation, Owner
34272 Yucaipa Blvd, Yucaipa, CA 92399
Fermin G. Preciado, Director of Development Services/City Engineer A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or validity of the document.

STATE OF CALIFORNIA

COUNTY OF SAN BERNARDINO
Subscribed and sworn to (or affirmed) before me on this 23rd day of February 2026, by Fermin G. Preciado, proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.

Date
Ana V. Sauseda, MMC
Director of General Services/City Clerk