Text extracted from the city's file for reading and search. Open the original on sandimasca.primegov.com. That file is the official record.

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 19 -
c) No formal cemeteries were found on or near the project site. Most Native American human remains are found in association with prehistoric archaeological sites. Since the region has moderate sensitivity to resources, mitigation measure CUL-1, through and CUL-3 will be incorporated to reduce potential impacts to less than significant.

Mitigation Measures:

CUL-1 – Prior to the commencement of grading or excavation, all workers and supervisors will receive Worker Environmental Awareness Program (WEAP) training from a qualified archaeologist regarding the potential for sensitive archaeological and paleontological resources to be unearthed during grading activities. The training shall educate and direct the workers to report any unusual specimens of bone, stone, ceramics or other archaeological artifacts or features observed during excavation, grading, and/or other construction activities to their foremen and to cease grading activities in the immediate vicinity of the discovery until a qualified archaeologist or Native American cultural monitor is notified of the discovery at the project site and can assess their significance. Upon completion of the WEAP, workers shall sign a form stating that they attended the program, understand all protection measures, and shall abide by all the rules of the WEAP. If new construction personnel are added to the project later, the construction foreman shall ensure that new personnel receive training before they start working. The WEAP shall be implemented throughout the duration of project construction. A record of all trained personnel shall be kept at the project field construction office and shall be made available to any resource agency personnel.

CUL-2 – If previously unidentified cultural resources and/or tribal cultural resources are unearthed during ground activity, all work shall immediately be suspended within 100 feet of the discovery and the City shall be immediately notified. A qualified archaeologist and a Native American monitor shall assess the significance of the find and determine if it is a California Register of Historic Resource (CRHR)-eligible archaeological resource and/or tribal cultural resource. If the qualified archaeologist determines that adverse impacts to tribal cultural resources or significant archaeological resources could occur during the Project, then the resources shall be avoided from direct Project impacts by Project redesign, if feasible.

If the resource cannot be avoided, then an archaeological treatment plan shall be developed and implemented.

CUL-3 – In compliance with Section 5097.98 of the Public Resources Code and Section 7050.5 of the California Health and Safety Code, if human remains are encountered, all ground disturbing activities shall be immediately suspended within 100 feet of the discovery, and the County Coroner should be notified immediately. If the Coroner determines the remains are Native American in origin, they must notify the Native American Heritage Commission within 24 hours of such identification so that the Native American Heritage Commission can contact the Most Likely Descendant (MLD). The MLD shall be provided access to the discovery and will provide recommendations for treatment of the remains within 48 hours of accessing the discovery site. The MLD recommendations may include scientific removal and nondestructive analysis of human remains and items associated with Native American burials, preservation of Native American human remains and associated items in place, relinquishment of Native American human remains and associated items to the descendants for treatment, or any other culturally appropriate treatment. Disposition of human remains and any associated grave goods, if encountered, shall be treated in accordance with procedures and requirements set forth in Sections 5097.94 and 5097.98 of the Public Resources Code; Section 7050.5 of the California Health and Safety Code and CEQA Guidelines Section 15064.5.

Page 422 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 20 -

3.6 Energy
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Result in potentially significant environmental
impact due to wasteful, inefficient, or unnecessary
consumption of energy resources, during project
construction or operation?
X
b) Conflict with or obstruct a state or local plan for
renewable energy or energy efficiency? X
Discussion:
a) The proposed sites do not require or result in potentially significant environmental impacts due to wasteful, inefficient, or unnecessary consumption of energy resources during project construction or operation. Minimal energy will be required during operation of the yard and park for light post facilities to illuminate pedestrian pathways during nighttime. Therefore, there is no anticipated impact.
b) The proposed sites will not obstruct a state or local plan for renewable energy or energy efficiency.

The parking lot will include electric vehicle (EV) charging stations. This is consistent with the state guidelines for reducing the reduction of greenhouse gases and reducing reliance on fossil fuels. The utility system has enough available capacity to provide for the energy use for the EV charging stations. Therefore, there is no anticipated impact.

Page 423 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 21 -

3.7 Geology and Soils
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Directly or indirectly cause potential substantial
adverse effects, including the risk of loss, injury, or death involving:
i) Rupture of a known earthquake fault, as
delineated on the most recent Alquist-Priolo
Earthquake Fault Zoning Map issued by the State
Geologist for the area or based on other substantial
evidence of a known fault? Refer to Division of
Mines and Geology Special Publication 42.

X
ii) Strong seismic ground shaking? X
iii) Seismic-related ground failure, including
liquefaction? X
iv) Landslides? X
b) Result in substantial soil erosion or the loss of
topsoil? X
c) Be located on a geologic unit or soil that is
unstable, or that would become unstable as a result
of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence, liquefaction or collapse?
X
d) Be located on expansive soil, as defined in Table
18-1-B of the Uniform Building Code (1994),
creating substantial direct or indirect risks to life or property?
X
e) Have soils incapable of adequately supporting
the use of septic tanks or alternative waste water
disposal systems where sewers are not available for
the disposal of waste water?
X
f) Directly or indirectly destroy a unique
paleontological resource or site or unique geologic
feature?
X

Page 424 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 22 -
Discussion:
a)
i) The Project site is located in southern California, a seismically active region. Although the Project is not within a known earthquake fault zone as delineated on an Alquist-Priolo Earthquake Fault Zoning Map, the City’s General Plan indicates that the northern portion of the City lies within the “potentially active” Sierra Madre Fault zone. Indian Hill Fault runs east west and just south of Arrow Highway in the area and Walnut Creek Fault runs just south of the Indian Hill Fault. However, the project site is not within this zone.

Therefore, the potential impact from fault rupture is considered less than significant. ii) The Project site is located in southern California, a seismically active area. However, the likelihood of hazards related to strong seismic ground shaking, such as ground surface rupture, is low. The Project will be designed and constructed in compliance with federal, state, and municipal building codes governing seismic safety. Thus, the impact from strong seismic ground shaking is considered less than significant. iii) Liquefaction refers to the loss of soil strength in saturated, coarse-grained soils during seismic activity. Liquefaction susceptibility is influenced by soil properties such as grain size, relative density, fines content, and the presence of clay-size fractions. The California Geological Survey indicates that the Project is located within a liquefaction zone. However, the Project will adhere to the recommendations in the project’s geotechnical report to minimize and mitigate potential adverse effects from seismic activity. Therefore, the impact from liquefaction is considered less than significant. iv) According to the California Geological Survey, the project site is not located in an area identified as a landslide hazard zone. As such, all structures in the project’s design will be protected from landslides and other ground movements. No impact from landslides is anticipated.
b) Construction of the Project will require minimal vegetation removal and involve various earthwork activities, including grading, excavation, and fill, which could result in localized soil erosion. However, standard erosion control measures will be implemented during construction, including revegetation or stabilization of disturbed areas following construction. Therefore, impacts related to erosion are considered less than significant.
c) As noted in Sections 3.7(a) and (b), and according to a geotechnical report prepared by Terracon Consultants, Inc. in September 2024, the Project is not in a fault or landslide zone but is within a liquefaction zone. The Project will follow the requirements outlined in the geotechnical report to minimize and mitigate potential adverse impacts related to soil stability. Therefore, the potential hazards associated with soil stability are considered less than significant. d) Expansive soils, which expand when wet and shrink when dry, can cause structures to move unevenly, leading to cracking. According to the September 2024 geotechnical report by Terracon Consultants, Inc., the project site contains sandy silty clay and poorly graded sand. These soil types are generally not expansive. Although sandy silty clay may contain some clay, its sandy component reduces the potential for expansive behavior. Similarly, poorly graded sand, consisting mostly of sand particles, provides good drainage and exhibits minimal shrink-swell behavior. Measures outlined

Page 425 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 23 -
in the geotechnical report, as well as any future geotechnical studies, will be followed during design and construction. Therefore, no impacts are anticipated. e) The Project will not require the installation of septic tanks or alternative wastewater disposal systems, as it does not involve the construction of habitable structures or restroom facilities. Therefore, no impact is anticipated.
f) The project area contains artificial fill and alluvial flood plain deposits, as part of the Holocene geological epoch, both of which have no paleontological sensitivity. The Project will involve significant ground disturbance, including excavation and grading of subsurface materials. As outlined in the geotechnical report, care will be taken to avoid damage to subgrade soils, and any water accumulation around the excavation areas will be managed to prevent erosion or disturbance of sensitive layers. Based on the soil conditions and not anticipating any potential paleontological resources, mitigation measures CUL-1 will be incorporated to reduced impacts to less than significant.

Page 426 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 24 -

3.8 Greenhouse Gas Emissions
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Generate greenhouse gas emissions, either
directly or indirectly, that may have a significant
impact on the environment?
X
b) Conflict with an applicable plan, policy or
regulation adopted for the purpose of reducing the
emissions of greenhouse gases?
X
Discussion:
a) As discussed in the Air Quality impact analysis, the Greenhouse Gas (GHG) emissions generated by the proposed Project would not exceed the SCAQMD threshold of 3,000 metric tons (MT) CO2 per year. The construction phase’s GHG emissions were calculated using the CalEEMod, Version 2022.1.1.22. Table 3-2 shows the unmitigated, yearly emissions rate in comparison to the Regional Significance Threshold. Because GHG missions will not exceed the threshold, the Project would have a less than significant impact on GHG.

Table 3-2 Greenhouse Gas Emissions for Project
Pollutant CO2
Maximum Construction Emissions rate (MT/year) 170
SCAQMD Threshold (MT/year) 3000
Exceed Threshold? No
b) The Project would not conflict with the State plan and policy AB 32 (California Global Warming Solutions Act of 2006) quantitative goal of AB 32 is to reduce GHG emissions to 1990 levels by 2020.

Because the Project does not conflict with an applicable plan, policy, or regulation adopted for the purpose of reducing the emission of GHG, there would be no anticipated impact.

Page 427 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 25 -

3.9 Hazards and Hazardous Materials
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Create a significant hazard to the public or the
environment through the routine transport, use, or
disposal of hazardous materials?
X
b) Create a significant hazard to the public or the
environment through reasonably foreseeable upset
and accident conditions involving the release of
hazardous materials into the environment?
X
c) Emit hazardous emissions or handle hazardous or
acutely hazardous materials, substances, or waste
within one-quarter mile of an existing or proposed
school?
X
d) Be located on a site which is included on a list of
hazardous materials sites compiled pursuant to
Government Code Section 65962.5 and, as a result,
would it create a significant hazard to the public or
the environment?
X
e) For a project located within an airport land use
plan or, where such a plan has not been adopted,
within two miles of a public airport or public use
airport, would the project result in a safety hazard
or excessive noise for people residing or working in
the project area?
X
f) Impair implementation of or physically interfere
with an adopted emergency response plan or
emergency evacuation plan?
X
g) Expose people or structures, either directly or
indirectly, to a significant risk of loss, injury or
death involving wildland fires?
X
Discussion:
a) Construction activities for this Project may involve excavation, grading, drilling, and other ground-disturbing activities. Anticipated construction activities may require the transport, storage, use, and disposal of small amounts of hazardous materials, including gasoline, diesel, hydraulic fluids, oils and lubricants and other similar substances. Long-term operation of the infiltration system is not

Page 428 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 26 -
anticipated to develop hazardous materials onsite. However, if hazardous materials are generated, they will be transported, used, or disposed of in compliance with applicable regulations. Therefore, impacts are considered to be less than significant.
b) As described above, there is limited potential for hazardous materials to cause a significant hazard through the routine transport, use, or disposal of hazardous materials. However, such materials will be used during construction of the Project. Handling and disposal of materials during construction would be conducted in compliance with existing federal, state, and county regulations, and would not be expected to result in the accidental release of hazardous materials into the environment.

Therefore, impacts would be less than significant.
c) The nearest school, Gladstone Elementary School, is adjacent to the project site. As discussed earlier, handling and disposal of hazardous materials is anticipated to be minimal, and would be conducted in compliance with existing federal, state, and county regulations. GHG emissions and criteria air pollutants will be emitted, but not in a significant amount, as none of the GHG emissions exceed SCAQMD thresholds. Therefore, impacts are anticipated to be less than significant. d) There are no Federal Superfund or other cleanup sites in the vicinity of the proposed Project.

According to the California Department of Toxic Substances Control, the nearest Federal Superfund site is located approximately 7 miles southeast of the project site, near Phillips Ranch at 86 Rio Rancho Rd, Pomona, CA 91766. Therefore, no impacts are anticipated. e) The nearest airport is Brackett Field Airport, located approximately three miles southeast of the project site. Because the airport is not within two miles of the project site, there are no anticipated impacts.
f) The Project will not interfere with any emergency response or evacuation plans, as none of the roads potentially affected by the Project are designated as Disaster Routes by the City of San Dimas.

Additionally, the Project will not increase the population in the area or the demand for emergency access. Therefore, no impacts are anticipated.
g) According to the Cal OES MyHazards Tool, the City of San Dimas is not designated as a Fire Hazard Severity Zone. The city is situated in a highly urbanized area, which reduces the likelihood of exposing people or structures to significant risks from wildland fires. Therefore, no impacts are anticipated.

Page 429 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 27 -

3.10 Hydrology and Water Quality
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Violate any water quality standards or waste
discharge requirements or otherwise substantially
degrade surface or ground water quality?
X
b) Substantially decrease groundwater supplies or
interfere substantially with groundwater recharge
such that the project may impede sustainable
groundwater management of the basin?
X
c) Substantially alter the existing drainage pattern
of the site or area, including through the alteration
of the course of a stream or river or through the
addition of impervious surfaces, in a manner which
would:
i) result in substantial erosion or siltation on- or off-site; X ii) substantially increase the rate or amount of
surface runoff in a manner which would result in
flooding on- or offsite;
X
iii) create or contribute runoff water which would
exceed the capacity of existing or planned
stormwater drainage systems or provide substantial
additional sources of polluted runoff; or
X
iv) impede or redirect flood flows? X
d) In flood hazard, tsunami, or seiche zones, risk
release of pollutants due to project inundation? X
e) Conflict with or obstruct implementation of a
water quality control plan or sustainable
groundwater management plan?
X
Discussion:
a) The proposed Project would not significantly violate water quality standards, waste discharge requirements, or surface or ground water quality because project construction would comply with regulations instated by the Federal Clean Water Act, Los Angeles Regional Water Quality Control Board (LARWQCB), Los Angeles County, City of San Dimas, and other water quality control

Page 430 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 28 -
regulations. BMPs will be implemented with respect to machinery and other contaminants. During construction, silt fencing or other sediment control BMPs will be placed around the perimeter of the construction site to prevent sediment from construction related activities from leaving the Project site. Gravel bags, plastic covers, erosion control blankets, and/or other erosion control BMPs will be implemented to be consistent with the Project’s erosion control plan. In the event of a hazardous materials spill, it will be immediately reported to the appropriate public agencies, including the City, the U.S. Army Corps of Engineers (USACE), LARWQCB, and CDFW. Therefore, impacts are anticipated to be less than significant.
b) Groundwater supplies will not be affected since the project does not include the installation of any groundwater wells. The Project will capture and infiltrate dry- and wet-weather runoff, replenishing groundwater and providing a beneficial impact. Therefore, there are no anticipated impacts. c)
i. The Project will not result in substantial erosion or siltation on- or off-site as it will not alter the existing drainage patterns of the site or alter the flows in San Dimas Wash. As noted in Section 3.10(a), construction BMPs will be implemented to prevent erosion or siltation during construction. Therefore, impacts are anticipated to be less than significant.
ii. The Project will not substantially increase surface runoff or significantly raise the imperviousness of the area, which could lead to flooding on or offsite. The Project will route some of the stormwater from running downstream and provide minor relief to any downstream storm drains that may have smaller capacities. Therefore, impacts are expected to be less than significant.
iii. While the addition of the parking lot will slightly increase impervious surfaces, the minimal increase in imperviousness will not exceed the capacity of the drainage system.

Thus, the impact will be less than significant.
iv. The Project will be constructed outside the San Dimas Wash and is not expected to impede or redirect flood flows. Since no work is being conducted within the channel, there are no anticipated impacts on flood flow patterns. d) The proposed Project is located within both a flood hazard zone and a potential seiche zone.

According to the Federal Emergency Management Agency (FEMA), the project area is situated in Zone X, which represents a 0.2% annual chance flood area. According to the City’s General Plan, seiches, or earthquake-generated waves, pose a potential hazard due to the presence of Puddingstone Reservoir and San Dimas Canyon Reservoir. The proposed Project is approximately 30 miles northeast of the Pacific Ocean and is situated 845 feet above sea level. Therefore, impacts related to flooding and seiches are anticipated to be less than significant. e) The Project will not conflict with the Los Angeles Region Basin Plan for the Coastal Watersheds of Los Angeles and Ventura Counties. All new developments are required to implement site design measures and best management practices to protect water quality and maintain natural drainage systems. Therefore, no impacts to water quality or drainage are anticipated.

Page 431 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 29 -

3.11 Land Use and Planning
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Physically divide an established community? X
b) Cause a significant environmental impact due to
a conflict with any land use plan, policy, or
regulation adopted for the purpose of avoiding or
mitigating an environmental effect?
X
Discussion:
a) The Project is located within the City of San Dimas and must adhere to the City’s adopted plans, policies, and regulations. The Project is designed to enhance community connectivity by incorporating an all-abilities playground, basketball court, parking lot, and demonstration garden.

These facilities are not expected to physically divide or disrupt the surrounding community.

Consequently, no significant impact is anticipated.
b) The project site is currently designated as public open space. Therefore, the implementation of the Project will not result in any alterations to the existing land use zoning or conflict with any applicable land use plans, policies, or regulations intended to prevent or mitigate environmental impacts. As a result, no significant impact is anticipated.

Page 432 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 30 -

3.12 Mineral Resources
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Result in the loss of availability of a known
mineral resource that would be of value to the
region and the residents of the state?
X
b) Result in the loss of availability of a locally-important mineral resource recovery site delineated on a local general plan, specific plan or other land
use plan?
X
Discussion:
a) The Surface Mining and Reclamation Act of 1975 (SMARA) mandates the classification of land into Mineral Resource Zones (MRZs) based on the known or inferred mineral potential of the area. The MRZ categories are as follows:
 MRZ-1: Areas where adequate information indicates that no significant mineral deposits are present or where it is judged that little likelihood exists for their presence.  MRZ-2: Areas where adequate information indicates significant mineral deposits are present, or where it is judged that a high likelihood exists for their presence.  MRZ-3: Areas containing mineral deposits the significance of which cannot be evaluated from available data.
 MRZ-4: Areas where available information is inadequate for assignment to any other MRZ A majority of the City of San Dimas, including the project site, is classified by the California Geological Survey as MRZ-3, indicating an area of uncertain mineral potential. The City’s General Plan identifies an area within San Dimas classified as MRZ-2, which is associated with significant aggregate deposits.

However, most of the land in this area is urbanized, and mining the remaining resources would result in considerable impacts to surrounding neighborhoods. Therefore, as there are no feasible mining opportunities within or adjacent to the proposed project boundaries, no impact is anticipated. b) As noted above, mineral resources within the Project site and the City of San Dimas are limited. No identified mineral resources are present on or near the project site. Consequently, the Project will not result in the loss of significant mineral resource recovery sites, and therefore, no impact is anticipated.

Page 433 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 31 -

3.13 Noise
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Generation of a substantial temporary or
permanent increase in ambient noise levels in the
vicinity of the project in excess of standards
established in the local general plan or noise
ordinance, or applicable standards of other
agencies?
X
b) Generation of excessive groundborne vibration or
groundborne noise levels? X
c) For a project located within the vicinity of a
private airstrip or an airport land use plan or, where
such a plan has not been adopted, within two miles
of a public airport or public use airport, would the
project expose people residing or working in the
project area to excessive noise levels?
X
Discussion:
a) The Project is primarily located within the Residential zoned properties.

Because implementation of the Project may result in the generation of construction noise within the areas surrounding the Project during construction and project operations, a Noise Assessment was performed on November 21, 2024. To identify baseline noise conditions, short-term ambient noise level measurements at the Project and at nearby representative sensitive receptors were recorded utilizing sound level meters, as shown in Figure 3-1. The ambient noise level measurements were taken during day-time hours, or when construction would typically occur. Table 3-3 shows the results of the noise assessment, identifying minimum, average, and maximum A-weighted decibels (dBA) at nearby sensitive, residential, and educational land uses.

Page 434 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 32 -
Table 3-3 Noise Assessment Results
Number Location Description Minimum
(dBA)
Average
(dBA)
Maximum
(dBA)
1 W. Gladstone Avenue and
N. Valley Center Avenue
42 60 80
2 W. Juanita Avenue and
Nugget Court 39 50 80
3 W. Juanita Avenue and
N. Rennell Avenue
33 48 81
4 W. Kirkwall Road and
N. Darwood Avenue
33 44 59
5 Gladstone Elementary School 37 47 72
6 W. Gladstone Avenue and
N. Balton Avenue
43 63 80
7 N. Jansen Avenue and
Kirkwall Road 34 43 70
8 N. Rennell Avenue and
Kirkwall Road 31 40 70
Figure 3-1 Noise Measurement Locations
Construction will take place between the hours of 8:00 AM until 5:00 PM Monday through Friday. The San Dimas Municipal code has exemptions for Noise listed in Chapter 8.36, which includes construction. Construction hours are limited to Monday through Saturday from 7:00 am to 8:00 pm,

Page 435 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 33 -
excluding holidays. The City’s Municipal Code also states that noise levels must meet the criteria based on land use, as depicted in Table 3-4.

Table 3-4 City of San Dimas Land Use Guidelines for Exterior Noise Noise Zone Allowable Noise Level
Residential low and medium density 50 dBA
Residential high density 60 dBA
Commercial 60 dBA
Industrial 70 dBA
As shown in Table 3-5, the Federal Highway Administration (FHWA) identified predicted noise limits at a reference distance of 50 feet. By utilizing these values, noise levels at nearby sensitive receptors can be calculated and predicted.

Table 3-5 Construction Equipment Noise Emission Levels
Equipment Description Lmax Noise Limit at 50 feet., dB
Slow
Is Equipment an Impact
Device?
All other equipment > 5HP 85 No
Backhoe 78 No
Compactor (ground) 83 No
Compressor (air) 78 No
Concrete Mixer Truck 79 No
Concrete Saw 90 No
Crane 81 No
Dozer 82 No
Dump Truck 76 No
Excavator 81 No
Flat Bed truck 74 No
Front End Loader 79 No
Generator 81 No
Impact/Vibratory Pile Driver 101 Yes
Jackhammer 89 Yes
Mounted Impact Hammer 90 Yes
Pavement Scarifier 85 No
Pumps 81 No
Roller 80 No
Sand Blasting (single nozzle) 96 No
Slurry Trenching Machine 80 No
Vacuum Street Sweeper 82 No
Welder / Torch 74 No

Page 436 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 34 -
Construction activities for this Project will comply with the City’s Noise Ordinance and meet all noise level requirements. The nearest sensitive receptors are the residential homes along the Project perimeter. The Project will potentially involve excavation, grading, drilling, trenching, pile driving, and other ground disturbing activities. Noise generated from construction activities would be temporary.

During construction of the Project, the contractor will be required to use construction muffler devices, sound blankets, or other means to reduce noise levels to ambient levels. No long-term noise impacts are anticipated from the Project since there are no components as a part of the project that would produce noise.

Therefore, with incorporation of mitigation measures NOISE-1 through NOISE-3, impacts by noise from construction would be less than significant. Excessive noise levels will no longer occur from the Project once construction is complete.
b) Construction of the Project will generate some groundborne vibrations as part of the construction activities. The Project is expected to utilize equipment that may typically produce higher vibration levels, such as pile drivers and bulldozers. However, with the implementation of mitigation measures NOISE-1 through NOISE-3, the impacts from groundborne vibrations are anticipated to be less than significant. Once construction is completed, all groundborne vibrations will cease. c) The Project is not located within an airport land use designation and is situated more than two miles from Brackett Field Airport. As a result, the Project will not expose people residing or working in the area to excessive noise levels associated with airport operations. The Project site is outside the noise contours associated with the airport. As noted in part a), construction equipment will temporarily elevate ambient noise levels in the area. Due to the proximity of nearby schools and residences, the contractor will be required to monitor noise levels and implement construction mufflers to minimize noise impacts. This elevated noise is limited to the construction phase and will subside upon completion of construction. Therefore, no long-term impacts are anticipated.

Mitigation Measures:

NOISE-1 – The City of San Dimas and their designees shall implement the following measures during construction as needed:
 Include design measures necessary to reduce the construction noise levels where feasible. These measures may include noise barriers, curtains, or shields.  Place noise-generating construction activities (e.g., operation of compressors and generators, cement mixing, general truck idling) as far as possible from the nearest noise-sensitive land uses.  Locate stationary construction noise sources as far from adjacent noise-sensitive receptors as possible.
 Identify a liaison for off-site sensitive receptors, such as residents and property owners, to contact with concerns regarding construction noise and vibration. The liaison’s telephone number(s) shall be prominently displayed at construction locations.  Notify, in writing, all landowners, occupants of properties adjacent to the construction area, and nearby sensitive receptors of the anticipated construction schedule at least 2 weeks prior to groundbreaking.
 Prepare visible signs indicating “Noise Control Zone.”

Page 437 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 35 -
 Use noise-control devices that meet original specifications and performance.  To the extent practical, use electrically-powered equipment.  Implement temporary noise barriers and sound-control curtains where project activity is unavoidably close to noise-sensitive receivers. In particular, noise barriers of 8 feet and 12 feet tall should be established around work sites to remove noise impacts from the different construction operation areas. The construction contractor should regularly evaluate the noise level at nearby sensitive receptors to ensure noise levels are not in exceedance. If so, the following noise barrier measures should also be incorporated:
 Break line of sight from noise source to receiver
 Use a frame to secure an appropriate acoustic blanket or paneling  Use a solid material with a minimum surface density of 3 lb/ft2 or mass-loaded acoustic blankets with at least STC 25
 Overlap or seal any gaps in the barriers
 Designate haul routes to be used based on the least overall noise impact route, with heavily-loaded trucks away from residential streets, if possible. Identify haul routes streets with the fewest noise sensitive receivers if no alternatives are available.  Place earth-moving equipment, fixed noise-generating equipment, stockpiles, staging areas, and other noise-producing operations as far as practicable from noise-sensitive receivers.  Eliminate the use of horns, whistles, alarms, and bells.  Phase demolition, earth moving, and ground impacting operations so they do not occur in the same time period.
 In the case of nighttime construction, the contractor shall comply with the provisions of the nighttime noise variance issued by the City.
 Conduct periodic noise measurements in accordance with an approved noise monitoring plan, specifying monitoring locations, equipment, procedures, and schedule of measurements and reporting methods to be used.

NOISE-2 – All construction activities that employ mechanized stationary equipment that generate noise levels shall comply with the applicable noise standards established by the City of San Dimas. The equipment shall be designed with noise-attenuating features (e.g., enclosures) and/or located at areas (e.g., belowground) where nearby noise-sensitive land uses would not be exposed to a perceptible noise increase in their noise environment.

NOISE-3 – To prevent impacts from vibrations, large vibration producing equipment should be placed as far as is feasible from sensitive receptors. Furthermore, the City of San Dimas and their designees should implement the following measures as needed:
 Pre-construction Survey - A before and after survey should include inspecting building foundations and taking photographs (or installing crack monitors) of pre-existing conditions, cracks, or other flaws. The survey can be limited to buildings closest to the pile driving activities, except for the case of unusually fragile or historic structures that are located within approximately 200 feet of construction.

Page 438 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 36 -
 Sonic Pile Driving - At the upper range reference vibration for the sonic/vibratory pile driver, the risk for damage to nearby buildings begins when the equipment is 32 feet or closer to the structure. The nearest piling is expected to be 20 feet from the closest structure, so vibration limit exceedances would remain with use of a vibratory pile driver.  Drilled Piles - Noise emission levels from bored/drilled pilling methods are approximately 15 dB lower and peak particle velocity (PPV) levels may be more than 15 times lower than those due to traditional impact piling. The use of these methods will eliminate the vibration impacts of all receivers. These methods will also substantially reduce the noise impacts and in most cases they will also be eliminated, with the use of a suitable noise barrier.  Hammer Energy - A recommended way to reduce PPV is to lower the hammer energy since there is a direct relationship between hammer energy and the resultant ground vibration. Ground PPV generally follows a square root relationship with hammer energy (i.e. PPV ~ √Hammer Energy).

The degree of hammer energy reduction must be balanced against the likelihood/severity of expected exceedances, increase in total driving time, and ability to drive to required friction tolerances.
 Vibration Monitoring - It is recommended that vibration monitoring be conducted at any building where equipment is operating closer than the limits noted in Table 3-6.

Table 3-6 Construction Equipment Vibration Reference Levels Equipment Description Minimum Separation Distance
Pile Driver (impact) 52 feet
Pile Driver (Vibratory) 32 feet
Vibratory Roller 14 feet
Compactor (Ground) 13 feet
Large Bulldozer 8 feet

Page 439 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 37 -

3.14 Population and Housing
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Induce substantial unplanned population growth
in an area, either directly (for example, by
proposing new homes and businesses) or indirectly
(for example, through extension of roads or other
infrastructure)?
X
b) Displace substantial numbers of existing people
or housing, necessitating the construction of
replacement housing elsewhere?
X
Discussion:
a) The Project will not induce substantial unplanned population growth, either directly or indirectly. Its primary objective is to provide water quality improvements and enhance open space areas, not to develop new homes, businesses, or infrastructure that would attract population growth. Since the Project does not involve the construction of additional housing or commercial developments, nor does it extend roads or infrastructure in a way that would support such growth, population increase is anticipated, and no related impacts are expected.
b) The Project will not affect any residential areas, housing units, or other buildings, and there are no plans to displace any individuals or families. As such, no displacement of people is anticipated, and the construction of replacement housing elsewhere is not necessary. Therefore, no impacts related to displacement are anticipated.

Page 440 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 38 -

3.15 Public Services
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Result in substantial adverse physical impacts
associated with the provision of new or physically
altered governmental facilities, need for new or
physically altered governmental facilities, the
construction of which could cause significant
environmental impacts, in order to maintain
acceptable service ratios, response times or other
performance objectives for any of the public
services:
i. Fire protection? X
ii. Police protection? X
iii. Schools? X
iv. Parks? X
v. Other public facilities? X
Discussion:
a)
i. The nearest fire stations are Los Angeles County Fire Department Station 85, approximately 1 mile west of the Project at 650 E. Gladstone Street, Glendora, CA 91740, Los Angeles County Fire Department Fire Station 86, approximately 1.4 miles northeast of the Project at 520 Amelia Avenue, Glendora, CA 91741, Los Angeles County Fire Department Station 153, approximately 1.7 miles southwest of the Project at 1577 Cypress Street, Covina, CA 91724, and Los Angeles County Fire Department Station 64, approximately 1.8 miles southeast of the Project at 164 S Walnut Avenue, San Dimas, CA 91773. If at any point during construction it is needed to close lanes or affect the flow of traffic, emergency services will be notified 10 days before construction. Therefore, impacts are expected to be less than significant with mitigation measures incorporated.
ii. The nearest police station is San Dimas Sheriff’s Department, approximately 1.8 miles southeast of the Project at 270 S. Walnut Avenue, San Dimas, CA 91773. If at any point during construction it is needed to close lanes or affect the flow of traffic, emergency services will be notified 10 days before construction. The construction of the Project could attract people for recreational purposes, and therefore, could impact police services in the future. However, impacts are expected to be less than significant with mitigation measures incorporated.

Page 441 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 39 -
iii. The nearest schools are Gladstone Elementary School (directly north of the Project site at 1314 W. Gladstone Street, San Dimas, CA 91771), Willow Elementary School (0.3 miles west at 1427 Willow Avenue, Glendora, CA 91740), Dove Day School (0.6 miles southeast at 908 W. Arrow Highway, San Dimas, CA 91773), Arrow Montessori School of San Dimas (0.6 miles east at 818 W. Gladstone Street, San Dimas, CA 91773), and Arrow High School (0.7 miles west at 1505 S. Sunflower Avenue, Glendora, CA 91740). The Project is not anticipated to impact operations or increase student population. The Project will temporarily impact normal traffic levels during construction; therefore, impacts would be less than significant.
iv. The proposed Project will enhance existing park and open space areas. This will provide a benefit to the community and help reach the goals from the City’s General Plan.

Consequently, other parks’ number of recreational users may fluctuate. Therefore, there is a less than significant impact.
v. Other services, such as City Hall, public libraries, and municipal services, are located outside of the Project’s area. While City staff will be needed to maintain park functions, impacts to service ratios are not expected to be significant. As a result, impacts would be less than significant.

Mitigation Measures:

PS-1 – The City shall provide reasonable advance notification to service providers such as fire, police, and emergency medical services as well as to local businesses, homeowners, and other residents adjacent to and within areas potentially affected by the proposed Project about the nature, extent, and duration of construction activities. Interim updates should be provided to inform the public of the status of the construction activities.

PS-2 – The City shall provide advance notice (at least 10-days prior) to emergency (fire, police, medical) services for any lane or street closures that may impact traffic circulation during construction.

Page 442 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 40 -

3.16 Recreation
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Would the project increase the use of existing
neighborhood and regional parks or other
recreational facilities such that substantial physical
deterioration of the facility would occur or be
accelerated?
X
b) Does the project include recreational facilities or
require the construction or expansion of
recreational facilities which might have an adverse
physical effect on the environment?
X
Discussion:
a) The proposed Project will enhance public park space within an urban environment. While this may result in increased use of existing neighborhood parks, potentially accelerating the physical deterioration of those facilities, no population growth is anticipated. Key BMPs, including the installation of bioswales and/or rain gardens, will be implemented alongside improvements to park facilities and city infrastructure. Therefore, the impacts are expected to be less than significant. b) The proposed Project will improve stormwater treatment for a drainage area covering 335 acres.

Lone Hill Park will feature new recreational amenities such as an all-abilities playground, a demonstration garden with native landscaping, and a redesigned parking lot. The native landscaping in the proposed park is likely to enhance the surrounding environment, thereby increasing and improving the recreational services available to the local community. Consequently, impacts are expected to be less than significant.

Page 443 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 41 -

3.17 Transportation/Traffic
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Conflict with a program plan, ordinance or policy
addressing the circulation system, including transit,
roadway, bicycle and pedestrian facilities?
X
b) Would the project conflict or be inconsistent
with CEQA Guidelines section 15064.3, subdivision
(b)?
X
c) Substantially increase hazards due to a
geometric design feature (e.g., sharp curves or
dangerous intersections) or incompatible uses
(e.g., farm equipment)?
X
d) Result in inadequate emergency access? X
Discussion:
a) The Project will not conflict with any program, plan, ordinance, or policy addressing the circulation system. Roadways will not be modified as part of the Project, and therefore, no impacts are anticipated. Additionally, there are no transit lines along the Project area boundary. Currently, the City does not have any bike lanes or bike routes, so no impacts are anticipated in this regard. While construction activities may temporarily affect pedestrian crosswalks and surrounding roads, these impacts are expected to be less than significant.
b) CEQA Guidelines Section 15064.3(b) provides criteria for evaluating transportation impacts, including those related to land use and transportation projects, qualitative analysis, and methodology.

According to CEQA Guidelines Section 15064.3(b), projects located within one-half mile of an existing transit stop or transit corridor are generally presumed to result in a less-than-significant transportation impact, as such proximity encourages transit use and reduces vehicle miles traveled.

The nearest transit stops are located at Arrow Highway and W. Rennell Avenue, Arrow Highway and W. Valley Center Avenue, and Lone Hill Ave and Las Colinas Way, each approximately 0.25 miles from the project site. This is within 0.5 miles of the project site, and the Project will not interfere with these transit stops or affect transit stops or affect transit routes. Therefore, transportation impacts are anticipated to be less than significant.
c) The Project will not alter any traffic design features and is anticipating no impact. d) None of the bordering roads of the Project area are part of the City’s Disaster Routes. During construction, there may be lane closures. With the mitigation measure TRAF-1 through TRAF-2, the Project will provide emergency access at all times and therefore will not result in inadequate

Page 444 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 42 -
emergency access. Construction related traffic has the potential to affect operations on the State Highway System, however, compliance with applicable standards is expected to maintain public safety and mobility during construction. Therefore, impacts will be less than significant with mitigation measures.

Mitigation Measures:

TRAF-1 – The Contractor will notify the local Police and Fire Departments of its intent to implement lane closures at least ten (10) days before work begins. The Contractor shall cooperate with local authorities in managing traffic through the area.

TRAF-2 – Transportation of heavy construction equipment and/or materials which requires use of oversized-transport vehicles on State highways will need a Caltrans transportation permit. Project specifications will limit construction traffic to off-peak periods to minimize the potential impact on State facilities. If construction traffic is expected to cause delays on any State facilities, a construction traffic control plan detailing these delays shall be submitted for Caltrans’ review.

Page 445 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 43 -

3.18 Tribal Cultural Resources
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Cause a substantial adverse change in the
significance of a tribal cultural resource, defined in
Public Resources Code section 21074 as either a
site, feature, place, cultural landscape that is
geographically defined in terms of the size and
scope of the landscape, sacred place, or object
with cultural value to a California Native American
tribe, and that is:
i) Listed or eligible for listing in the California
Register of Historical Resources, or in a local
register of historical resources as defined in Public
Resources Code section 5020.1(k), or
X
ii) A resource determined by the lead agency, in
its discretion and supported by substantial
evidence, to be significant pursuant to criteria set
forth in subdivision (c) of Public Resources Code
Section 5024.1. In applying the criteria set forth in
subdivision (c) of Public Resource Code Section
5024.1, the lead agency shall consider the
significance of the resource to a California Native
American tribe.

X
Discussion:
a)
i. In a letter dated December 4, 2024, from the Native American Heritage Commission included information on a record search for Sacred Lands Files and reported that the search was positive for sacred lands. Tribes listed in relation to the sacred lands will be contacted for consultation, along with the tribes that affiliated with the project area. Consultation and mitigation measures below would ensure impacts to Sacred Lands or tribal cultural resources would be less than significant with mitigation incorporated.
ii. The California Native American Heritage Commission (NAHC) was consulted about the Project and responded that sacred sites have been identified by the Gabrieleno Band of Mission Indians as within the project region. Therefore, the Project has high sensitivity due to the potential of finding tribal cultural resources, although there are no known tribal cultural resources that have been identified at the Project site to date.

Page 446 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 44 -
The City of San Dimas sent out notification letters on September 4, 2025, to the Cahuilla Band of Indians, Gabrielino Band of Mission Indians – Kizh Nation, Gabrielino/Tongva San Gabriel Band of Mission Indians, Gabrielino Tongva Indians of California Tribal Council, Gabrielino/Tongva Nation, Gabrielino-Tongva Tribe, San Manuel Band of Mission Indians, Santa Rosa Band of Cahuilla Indians, and Soboba Band of Luiseno Indians, pursuant to Assembly Bill 52 and Public Resources Code Section 21080.3.1. The Gabrielino Band of Mission Indians – Kizh Nation, was the only tribe who engaged in tribal consultation process and provided substantial evidence.

Mitigation Measures:

TCR-1 – Retain a Native American Monitor 30 Days Prior to Commencement of Ground-Disturbing Activities.
 The City of San Dimas shall retain a Native American Monitor from the Gabrieleño Band of Mission Indians – Kizh Nation. The monitor shall be retained prior to the commencement of any “ground-disturbing activity” for the subject project at all project locations (i.e., both on-site and any off-site locations that are included in the project description/definition and/or required in connection with the project, such as public improvement work). “Ground-disturbing activity” shall include, but is not limited to, demolition, pavement removal, potholing, auguring, grubbing, tree removal, boring, grading, excavation, drilling, and trenching.  The monitor will complete daily monitoring logs that will provide descriptions of the relevant ground-disturbing activities, the type of construction activities performed, locations of ground-disturbing activities, soil types, cultural-related materials, and any other facts, conditions, materials, or discoveries of significance to the Tribe. Monitor logs will identify and describe any discovered TCRs, including but not limited to, Native American cultural and historical artifacts, remains, places of significance, etc., (collectively, tribal cultural resources, or “TCR”), as well as any discovered Native American (ancestral) human remains or burial goods. Copies of monitoring logs will be provided to the Tribe upon written request to the City of San Dimas.  Upon discovery of any TCRs, all construction activities in the immediate vicinity of the discovery shall cease (i.e., not less than the surrounding 50 feet) and shall not resume until the discovered TCR has been fully assessed by the Native American Monitor or qualified archaeologist. The Native American Monitor or qualified archaeologist will recover and retain all discovered TCRs in the form and/or manner the Tribe deems appropriate, in the Tribe’s sole discretion, and for any purpose the Tribe deems appropriate, including for educational, cultural and/or historic purposes.

TCR-2 – Unanticipated Discovery of Human Remains and Associated Funerary Objects  Native American human remains are defined in PRC 5097.98 (d)(1) as an inhumation or cremation, and in any state of decomposition or skeletal completeness. Funerary objects, called associated grave goods in Public Resources Code Section 5097.98, are also to be treated according to this statute.
 If Native American human remains and/or grave goods discovered or recognized on the project site, then all construction activities shall immediately cease. Health and Safety Code Section 7050.5 dictates that any discoveries of human skeletal material shall be immediately reported to the County Coroner and all ground-disturbing activities shall immediately halt and shall remain

Page 447 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 45 -
halted until the coroner has determined the nature of the remains. If the coroner recognizes the human remains to be those of a Native American or has reason to believe they are Native American, he or she shall contact, by telephone within 24 hours, the Native American Heritage Commission, and Public Resources Code Section 5097.98 shall be followed.  Human remains and grave/burial goods shall be treated alike per California Public Resources Code section 5097.98(d)(1) and (2).
 Construction activities may resume in other parts of the project site at a minimum of 200 feet away from discovered human remains and/or burial goods, if the monitor determines in its sole discretion that resuming construction activities at that distance is acceptable and provides the project manager express consent of that determination (along with any other mitigation measures the Native American monitor and/or archaeologist deems necessary). (CEQA Guidelines Section 15064.5(f).)
 Preservation in place (i.e., avoidance) is the preferred manner of treatment for discovered human remains and/or burial goods. Any historic archaeological material that is not Native American in origin (non-TCR) shall be curated at a public, non-profit institution with a research interest in the materials, if such an institution agrees to accept the material. If no institution accepts the archaeological material, it shall be offered to a local school or historical society in the area for educational purposes.
 Any discovery of human remains/burial goods shall be kept confidential to prevent further disturbance.

TCR-3 – Procedures for Burials and Funerary Remains
 As the MLD, the Koo-nas-gna Burial Policy shall be implemented. To the Tribe, the term “human remains” encompasses more than human bones. In ancient as well as historic times, Tribal Traditions included, but were not limited to, the preparation of the soil for burial, the burial of funerary objects with the deceased, and the ceremonial burning of human remains.  If the discovery of human remains includes four or more burials, the discovery location shall be treated as a cemetery and a separate treatment plan shall be created.  The prepared soil and cremation soils are to be treated in the same manner as bone fragments that remain intact. Associated funerary objects are objects that, as part of the death rite or ceremony of a culture, are reasonably believed to have been placed with individual human remains either at the time of death or later; other items made exclusively for burial purposes or to contain human remains can also be considered as associated funerary objects. Cremations will either be removed in bulk or by means as necessary to ensure complete recovery of all sacred materials.
 In the case where discovered human remains cannot be fully documented and recovered on the same day, the remains will be covered with muslin cloth and a steel plate that can be moved by heavy equipment placed over the excavation opening to protect the remains. If this type of steel plate is not available, a 24-hour guard should be posted outside of working hours. The Tribe will

Page 448 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 46 -
make every effort to recommend diverting the project and keeping the remains in situ and protected. If the project cannot be diverted, it may be determined that burials will be removed.  In the event preservation in place is not possible despite good faith efforts by the project applicant/developer and/or landowner, before ground-disturbing activities may resume on the project site, the landowner shall arrange a designated site location within the footprint of the project for the respectful reburial of the human remains and/or ceremonial objects.  Each occurrence of human remains and associated funerary objects will be stored using opaque cloth bags. All human remains, funerary objects, sacred objects and objects of cultural patrimony will be removed to a secure container on site if possible. These items should be retained and reburied within six months of recovery. The site of reburial/repatriation shall be on the project site but at a location agreed upon between the Tribe and the landowner at a site to be protected in perpetuity. There shall be no publicity regarding any cultural materials recovered.
 The Tribe will work closely with the project’s qualified archaeologist to ensure that the excavation is treated carefully, ethically and respectfully. If data recovery is approved by the Tribe, documentation shall be prepared and shall include (at a minimum) detailed descriptive notes and sketches. All data recovery-related forms of documentation shall be approved in advance by the Tribe. If any data recovery is performed, once complete, a final report shall be submitted to the Tribe and the NAHC. The Tribe does NOT authorize any scientific study or the utilization of any invasive and/or destructive diagnostics on human remains.

Page 449 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 47 -

3.19 Utilities and Service Systems
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Require or result in the relocation or construction
of new or expanded water, wastewater treatment
or storm water drainage, electric power, natural
gas, or telecommunication facilities, the
construction or relocation of which could cause
significant environmental effects?
X
b) Have sufficient water supplies available to serve
the project and reasonably foreseeable future
development during normal, dry, and multiple dry
years?
X
c) Result in a determination by the wastewater
treatment provider which serves or may serve the
project that it has adequate capacity to serve the
project’s projected demand in addition to the
provider’s existing commitments?
X
d) Generate solid waste in excess of State or local
standards, or in excess of the capacity of local
infrastructure, or otherwise impair the attainment of
solid waste reduction goals?
X
e) Comply with federal, state, and local
management and reduction statutes and
regulations related to solid waste?
X
Discussion:
a) The proposed Project includes the construction of an expanded stormwater drainage system designed to capture, treat, and infiltrate stormwater tributary to the Gladstone Street storm drain.

Additionally, the Project will enhance the existing park and garden area. The Project is not expected to significantly increase demand on water, wastewater treatment, stormwater drainage, electric power, natural gas, or telecommunications facilities, nor would it require the construction or relocation of new or expanded utility infrastructure beyond the proposed on-site improvements. The stormwater improvements are intended to improve existing drainage and water quality conditions through nature-based infiltration and treatment features. Therefore, the Project would not result in significant environmental effects associated with utility infrastructure expansion, and impacts would be less than significant.

Page 450 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 48 -
b) The proposed Project will incorporate native, predominantly drought-tolerant landscaping, allowing vegetation to thrive during normal, dry, and multiple dry years while minimizing potable water demand. The design also includes efficient, low-water-use irrigation systems within the demonstration garden area. In addition, the Project’s bioretention basin will capture and infiltrate stormwater runoff, supporting groundwater recharge and reducing reliance on potable water supplies. The Project consists primarily of stormwater and park improvements and would not substantially increase water demand or require new or expanded water supply entitlements.

Therefore, sufficient water supplies would be available to serve the Project during normal, dry, and multiple dry years, and impacts would be less than significant.

The Project does not include facilities or activities that would generate substantial increases in wastewater flows. Therefore, impacts related to wastewater generation would be less than significant.
c) During construction, some debris may be generated, with portions being recycled. However, the amount of waste is expected to be minimal and should not exceed the capacity of local infrastructure or interfere with the achievement of solid waste reduction goals. Therefore, impacts to local infrastructure and solid waste reduction goals are expected to be less than significant. d) Waste disposal BMPs involve strategies to reduce, manage, and properly dispose of waste generated during construction or operation. These practices include waste segregation, recycling, hazardous waste management, and minimizing waste generation, ensuring that materials are disposed of in an environmentally responsible manner while complying with all applicable federal, state, and local regulations. Disposal will adhere to all relevant regulatory requirements. Therefore, no significant impacts are anticipated.

Page 451 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 49 -

3.20 Wildfire
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Substantially impair an adopted emergency
response plan or emergency evacuation plan? X
b) Due to slope, prevailing winds, and other factors,
exacerbate wildfire risks, and thereby expose
project occupants to, pollutant concentrations from
a wildfire or the uncontrolled spread of a wildfire?
X
c) Require the installation or maintenance of
associated infrastructure (such as roads, fuel
breaks, emergency water sources, power lines or
other utilities) that may exacerbate fire risk or that
may result in temporary or ongoing impacts to the
environment?
X
d) Expose people or structures to significant risks,
including downslope or downstream flooding or
landslides, as a result of runoff, post-fire slope
instability, or drainage changes?
X
Discussion:
a) According to the CAL FIRE Fire Hazard Severity Zones Viewer, the Project area is not located within a designated fire hazard severity zone. Although the Project may temporarily impact traffic on the surrounding roads, none of the roads are part of the City’s Disaster routes, and emergency services will be notified 10 days in advance of any road closures. Therefore, there is less than significant impact anticipated.
b) The proposed Project will feature native vegetation, which are all flammable and susceptible to wildfires, but due to the Project’s location in a highly urbanized area, there is no potential for wildfires. Therefore, there would be no anticipated impact. c) The Project will not require the installation or maintenance of infrastructure, such as roads, fuel breaks, emergency water sources, power lines, or other utilities. Therefore, the Project would not exacerbate fire risk, and there would be no impact.
d) The Project is built on a relatively flat and urbanized area. The Project is not anticipated to expose people or structures to significant risks of flooding or landslides. Therefore, there would be no anticipated impact.

Page 452 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 50 -

3.21 Mandatory Findings of Significance
Would the project:

Environmental Issue
Potentially
Significant
Impact
Less Than
Significant
with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Does the project have the potential to
substantially degrade the quality of the
environment, substantially reduce the habitat of a
fish or wildlife species, cause a fish or wildlife
population to drop below self-sustaining levels,
threaten to eliminate a plant or animal community,
substantially reduce the number or restrict the
range of a rare or endangered plant or animal or
eliminate important examples of the major periods
of California history or prehistory?
X
b) Does the project have impacts that are
individually limited, but cumulatively considerable?
("Cumulatively considerable" means that the
incremental effects of a project are considerable
when viewed in connection with the effects of past
projects, the effects of other current projects, and
the effects of probable future projects)?
X
c) Does the project have environmental effects
which will cause substantial adverse effects on
human beings, either directly or indirectly?
X
Discussion:
a) Due to its location in an urbanized environment, the Project is not anticipated to affect the quality of the environment, habitat, fish, wildlife, or plant populations at the Project Site during construction or post-construction. Consequently, the Project will result in a less-than-significant impact, provided that appropriate mitigation measures are implemented. b) The proposed Project could potentially result in significant impacts unless mitigated for the following environmental issues: air quality, biology, cultural, noise, public services, transportation, and tribal cultural resources. Mitigation measures have been identified for each of these environmental areas to reduce impacts to a level that is less than significant. Cumulatively, the proposed Project will not result in any significant impacts that would combine substantially with impacts from other current or foreseeable future developments, assuming all other projects within the city comply with the established regulatory framework.

Page 453 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 51 -
c) The Project may have potential environmental effects on humans, most of which would be related to construction activities. These impacts are primarily associated with noise and air quality. As discussed in Section 3.3 and Section 3.13, these impacts are considered less than significant, or mitigation measures will be implemented to protect nearby sensitive receptors.

The Project will comply with all applicable local, state, and federal regulations. No long-term impacts on human health are anticipated from the operation of the infiltration system, and routine maintenance activities are not expected to result in significant effects on nearby sensitive receptors. Therefore, potential impacts on human health and well-being would be less than significant with the incorporation of mitigation measures.

Page 454 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 52 -

4. References
California Department of Transportation. California Scenic Highway Mapping System. https://caltrans.maps.arcgis.com/apps/webappviewer/index.html?id=465dfd3d807c46cc8e80571 16f1aacaa
California Department of Conservation. California Geologic Survey. Regulatory Maps. http://gmw.conservation.ca.gov/SHP/EZRIM/Maps/EL_MONTE_EZRIM.pdf California Department of Conservation. California Important Farmland Finder. https://maps.conservation.ca.gov/dlrp/ciff/
California Department of Conservation. California Williamson Act Enrollment Finder. https://maps.conservation.ca.gov/dlrp/WilliamsonAct/
California Department of Conservation. Earthquake Fault Zones. https://www.conservation.ca.gov/cgs/documents/publications/special-publications/SP_042- a11y.pdf
California Department of Toxic Substances Control. Envirostor. https://www.envirostor.dtsc.ca.gov/public/map/?global
CalEEMod. California Emissions Estimator Model.

CalEEMod - https://www.caleemod.com/model
CAL FIRE. Fire Hazard Severity Zones in SRA. 2024.
https://osfm.fire.ca.gov/what-we-do/community-wildfire-preparedness-and-mitigation/fire-hazard-severity-zones Cal OES. MyHazards.
https://myhazards.caloes.ca.gov/
FEMA Flood Map Service Center.
https://msc.fema.gov/portal/search?AddressQuery=manhattan%20beach%2C%20ca#searchresu ltsanchor
Los Angeles County. Disaster Routes. September 8, 2008. https://pw.lacounty.gov/dsg/DisasterRoutes/map/San%20Dimas.pdf LSA. Cultural Resources Assessment. January 2025.

National Ambient Air Quality Standards and California Ambient Air Quality Standards Attainment Status for South Coast Air Basin
https://www.aqmd.gov/docs/default-source/clean-air-plans/air-quality-management-plans/naaqs-caaqs-feb2016.pdf?sfvrsn=2 San Dimas, City of. City of San Dimas General Plan.

Page 455 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 53 -
https://sandimasca.gov/departments/community_development/planning_division/general_plan/g eneral_plan_sections.php
San Dimas, City of. Code of Ordinances.
https://ecode360.com/SA5002
South Coast Air Quality Management District
https://www.aqmd.gov/docs/default-source/default-document-library/map-of-jurisdiction.pdf Terracon Consultants, Inc. Geotechnical Engineering Report. Stormwater Capture Feasibility Study.

August 5, 2024.

United States Fish and Wildlife Service. National Wetlands Inventory. Wetlands Mapper. https://www.fws.gov/wetlands/Data/Mapper.html
United States Fish and Wildlife Service. Information for Planning and Consultation. Species Mapper. https://ipac.ecosphere.fws.gov/location/index

Page 456 ends

City of San Dimas California Environmental Quality Act
Initial Study/Mitigated Negative Declaration
- 1 -
Appendix A
Mitigation Monitoring and Reporting Plan

Page 457 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 1 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
AIR-1
Pursuant to Rule 403 of the SCAQMD, the following
dust minimizing measures shall be implemented:
 City of San Dimas and its designees shall
comply with all applicable SCAQMD Rules and
Regulations, including Rule 403 ensuring the
cleanup of construction-related dirt on
approach routes to the site. Rule 403 prohibits
the release of fugitive dust emissions from any
active operation, open storage pile or disturbed
surface area visible beyond the property line of
the emission source.
 City of San Dimas and its designees shall
comply with all SCAQMD established minimum
requirements for construction activities to
reduce fugitive dust and PM10 emissions.
 Adequate water techniques shall be employed
to mitigate the impact of construction-related
dust particulates. Portions of the site that are
undergoing surface earth moving operations
shall be dewatered such that a crust will be
formed on the ground surface, and then
watered again at the end of each day. Site
watering shall be performed as necessary to
mitigate blowing dust.

City of San Dimas Construction City of San
Dimas N/A

Page 458 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 2 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
 Grading operations shall be suspended during
first stage ozone episodes or when winds
exceed 25 mph. A high wind response plan
shall be formulated for enhanced dust control if
winds are forecast to exceed 25 mph in any
upcoming 24-hour period.
 Any construction equipment using direct
internal combustion engines shall use a diesel
fuel with a maximum of 0.05 percent sulfur and
four-degree retard.
 Construction operations affecting roadways
within the project area including detour routes,
shall be scheduled by implementing traffic
hours and shall minimize obstruction of through
traffic lanes.
 The engines of idling trucks or heavy
equipment shall be turned off if the expected
duration of idling exceeds five minutes.
 On-site heavy equipment used during grading
and construction shall be equipped with diesel
particulate filters unless it is demonstrated that
such equipment is not available, or its use is
not cost-competitive.

Page 459 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 3 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
 All haul trucks leaving or entering the site shall
be covered or have at least two feet of
freeboard.
 Any on-site stockpiles of debris, dirt or other
dusty material shall be covered or watered
twice daily.
 Any site access points within 30 minutes of any
visible dirt deposition on any public right-of-way shall be mechanically or manually swept.

BIO-1
Prior to ground-disturbing activities in areas that could support sensitive biological resources, a habitat
assessment shall be conducted by a qualified biologist
to determine the potential for special-status wildlife
species to occur within affected areas, including areas directly or indirectly impacted by construction or
operation of the BMPs. If a special-status wildlife
species is found, pre-construction surveys of proposed
work zones should be conducted 14 days prior to
construction. Areas, including construction areas,
staging areas, and right-of-ways, should be staked,
flagged, fenced, or otherwise clearly delineated to
restrict the limits of construction to the minimum
necessary near areas that may support special-status
wildlife species with special-status wildlife species; if avoidance is not possible, the City of San Dimas should consult with the appropriate regulating agency (United
City of San Dimas Pre-Construction City of San
Dimas
United States
Army Corps of
Engineers
United States
Fish and
Wildlife Service
California
Department of
Fish and
Wildlife

Page 460 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 4 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
States Army Corps of Engineers [USACE]/ United States
Fish and Wildlife Service [USFWS]/ California
Department of Fish and Wildlife [CDFW]) to determine
a strategy for compliance with the Endangered Species
Act, California Fish and Wildlife Code, or other
regulations supporting special-status species. The City of San Dimas will work together with those regulating
agencies to determine appropriate impact minimization
measures and compensation for any permanent
impacts due to the Project. If no breeding and nesting
birds and/or raptors are found, then construction may
proceed as scheduled with no additional monitoring or
measured required.

BIO-2
To protect nesting birds that may occur on site or
adjacent to the Project boundary, no construction shall occur from February 1 through September 15, as early
as January 1 for some raptors, unless a qualified
biologist completes a survey for nesting bird activity
within a 500-foot radius of the construction site. The
nesting bird surveys shall be conducted at appropriate
nesting times and concentrate on potential roosting or
perch sites. The City of San Dimas should require
surveys be conducted by a qualified biologist no more
than 7 days prior to the beginning of any Project-related activity likely to impact raptors and migratory songbirds, for the entire Project site. If Project
activities are delayed or suspended for more than 7
City of San Dimas Pre-Construction City of San
Dimas
California
Department of
Fish and
Wildlife

Page 461 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 5 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
days during the breeding season, the surveys shall be
repeated. If nesting raptors and migratory songbirds
are identified, the following minimum no-disturbance
buffers shall be implemented: 300 feet around active
passerine (perching birds and songbirds) nests, 500
feet around active non-listed raptor nests and 0.5 mile around active listed bird nests. These buffers shall be maintained until the breeding season has ended or until a qualified biologist has determined that the birds have fledged and are no longer reliant upon the nest or
parental care for survival. The qualified biologist may authorize construction activities to proceed during the nesting season, including modified avoidance buffers or work restrictions, if, in their professional judgement, the proposed activities will not result in take, nest
abandonment, or disturbance as defined under the
Migratory Bird Treaty Act. Such determinations shall be based on observed nesting behavior, distance to work
activities, species tolerance, and current site condition.

Any sensitive and special status species data
documented by the Project shall be submitted to the
California Natural Diversity Database with all applicable data fields filled out. The City of San Dimas and/or a
designee will notify the CDFW once submitted.

BIO-3
The Project shall implement BMPs to prevent erosion
and the discharge of sediment and pollutants into
drainages during Project activities. BMPs shall be
City of San Dimas Construction City of San
Dimas N/A

Page 462 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 6 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
monitored and repaired, if necessary, to ensure
maximum erosion, sediment, and pollution control. The
Project proponent shall prohibit the use of erosion
control materials potentially harmful to fish and wildlife species, such as mono-filament netting (erosion control matting) or similar material. All fiber rolls, straw
wattles, and/or hay bales utilized within and adjacent to the Project site shall be free of nonnative plant
materials. Fiber rolls or erosion control mesh shall be made of loose-weave mesh that is not fused at the
intersections of the weave, such as jute, or coconut
(coir) fiber, or other products without welded weaves.

CUL-1
Prior to the commencement of grading or excavation,
all workers and supervisors will receive Worker
Environmental Awareness Program (WEAP) training
from a qualified archaeologist regarding the potential
for sensitive archaeological and paleontological
resources to be unearthed during grading activities.

The training shall educate and direct the workers to
report any unusual specimens of bone, stone, ceramics
or other archaeological artifacts or features observed
during excavation, grading, and/or other construction
activities to their foremen and to cease grading
activities in the immediate vicinity of the discovery until a qualified archaeologist or Native American cultural
monitor is notified of the discovery at the project site and can assess their significance. Upon completion of
City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission

Page 463 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 7 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
the WEAP, workers shall sign a form stating that they
attended the program, understand all protection
measures, and shall abide by all the rules of the WEAP.

If new construction personnel are added to the project
later, the construction foreman shall ensure that new
personnel receive training before they start working.

The WEAP shall be implemented throughout the
duration of project construction. A record of all trained personnel shall be kept at the project field construction office and shall be made available to any resource
agency personnel.

CUL-2
If previously unidentified cultural resources and/or
tribal cultural resources are unearthed during ground
activity, all work shall immediately be suspended within 100 feet of the discovery and the City shall be
immediately notified. A qualified archaeologist and a
Native American monitor shall assess the significance of the find and determine if it is a California Register of Historic Resource (CRHR)-eligible archaeological
resource and/or tribal cultural resource. If the qualified archaeologist determines that adverse impacts to tribal cultural resources or significant archaeological
resources could occur during the Project, then the
resources shall be avoided from direct Project impacts
by Project redesign, if feasible. If the resource cannot be avoided, then an archaeological treatment plan shall be developed and implemented.

City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission

Page 464 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 8 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
CUL-3
In compliance with Section 5097.98 of the Public
Resources Code and Section 7050.5 of the California
Health and Safety Code, if human remains are
encountered, all ground disturbing activities shall be
immediately suspended within 100 feet of the
discovery, and the County Coroner should be notified
immediately. If the Coroner determines the remains
are Native American in origin, they must notify the
Native American Heritage Commission within 24 hours
of such identification so that the Native American
Heritage Commission can contact the Most Likely
Descendant (MLD). The MLD shall be provided access
to the discovery and will provide recommendations for
treatment of the remains within 48 hours of accessing
the discovery site. The MLD recommendations may
include scientific removal and nondestructive analysis of human remains and items associated with Native
American burials, preservation of Native American
human remains and associated items in place,
relinquishment of Native American human remains and
associated items to the descendants for treatment, or
any other culturally appropriate treatment. Disposition of human remains and any associated grave goods, if
encountered, shall be treated in accordance with
procedures and requirements set forth in Sections
5097.94 and 5097.98 of the Public Resources Code;
City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission
County Coroner

Page 465 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 9 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
Section 7050.5 of the California Health and Safety Code and CEQA Guidelines Section 15064.5.

NOISE-1
The City of San Dimas and their designees shall
implement the following measures during construction
as needed:
 Include design measures necessary to reduce
the construction noise levels where feasible.

These measures may include noise barriers,
curtains, or shields.
 Place noise-generating construction activities
(e.g., operation of compressors and generators,
cement mixing, general truck idling) as far as
possible from the nearest noise-sensitive land
uses.
 Locate stationary construction noise sources as
far from adjacent noise-sensitive receptors as
possible.
 Identify a liaison for off-site sensitive receptors,
such as residents and property owners, to
contact with concerns regarding construction
noise and vibration. The liaison’s telephone
number(s) shall be prominently displayed at
construction locations.
 Notify, in writing, all landowners, occupants of
properties adjacent to the construction area,
City of San Dimas Construction City of San
Dimas N/A

Page 466 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 10 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
and nearby sensitive receptors of the
anticipated construction schedule at least 2
weeks prior to groundbreaking.
 Prepare visible signs indicating “Noise Control
Zone.”
 Use noise-control devices that meet original
specifications and performance.
 To the extent practical, use electrically-powered
equipment.
 Implement temporary noise barriers and
sound-control curtains where project activity is
unavoidably close to noise-sensitive receivers.

In particular, noise barriers of 8 feet and 12
feet tall should be established around work
sites to remove noise impacts from the
different construction operation areas. The
construction contractor should regularly
evaluate the noise level at nearby sensitive
receptors to ensure noise levels are not in
exceedance. If so, the following noise barrier
measures should also be incorporated:
 Break line of sight from noise source to
receiver
 Use a frame to secure an appropriate
acoustic blanket or paneling

Page 467 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 11 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
 Use a solid material with a minimum
surface density of 3 lb/ft2 or mass-loaded
acoustic blankets with at least STC 25
 Overlap or seal any gaps in the barriers
 Designate haul routes to be used based on the
least overall noise impact route, with heavily-loaded trucks away from residential streets, if possible. Identify haul routes streets with the
fewest noise sensitive receivers if no
alternatives are available.
 Place earth-moving equipment, fixed noise-generating equipment, stockpiles, staging areas, and other noise-producing operations as
far as practicable from noise-sensitive
receivers.
 Eliminate the use of horns, whistles, alarms,
and bells.
 Phase demolition, earth moving, and ground
impacting operations so they do not occur in
the same time period.
 In the case of nighttime construction, the
contractor shall comply with the provisions of
the nighttime noise variance issued by the City.
 Conduct periodic noise measurements in
accordance with an approved noise monitoring

Page 468 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 12 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
plan, specifying monitoring locations,
equipment, procedures, and schedule of
measurements and reporting methods to be
used.

NOISE-2
All construction activities that employ mechanized
stationary equipment that generate noise levels shall
comply with the applicable noise standards established
by the City of San Dimas. The equipment shall be
designed with noise-attenuating features (e.g.,
enclosures) and/or located at areas (e.g., belowground) where nearby noise-sensitive land uses would not be
exposed to a perceptible noise increase in their noise
environment.

City of San Dimas Construction City of San
Dimas N/A
NOISE-3
To prevent impacts from vibrations, large vibration
producing equipment should be placed as far as is
feasible from sensitive receptors. Furthermore, the City of San Dimas and their designees should implement the
following measures as needed:
 Pre-construction Survey - A before and after
survey should include inspecting building
foundations and taking photographs (or
installing crack monitors) of pre-existing
conditions, cracks, or other flaws. The survey
can be limited to buildings closest to the pile
driving activities, except for the case of
unusually fragile or historic structures that are
City of San Dimas Pre-Construction/
Construction
City of San
Dimas N/A

Page 469 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 13 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
located within approximately 200 feet of
construction.
 Sonic Pile Driving - At the upper range
reference vibration for the sonic/vibratory pile
driver, the risk for damage to nearby buildings
begins when the equipment is 32 feet or closer
to the structure. The nearest piling is expected
to be 20 feet from the closest structure, so
vibration limit exceedances would remain with
use of a vibratory pile driver.
 Drilled Piles - Noise emission levels from
bored/drilled pilling methods are approximately
15 dB lower and peak particle velocity (PPV)
levels may be more than 15 times lower than
those due to traditional impact piling. The use
of these methods will eliminate the vibration
impacts of all receivers. These methods will
also substantially reduce the noise impacts and
in most cases they will also be eliminated, with
the use of a suitable noise barrier.
 Hammer Energy - A recommended way to
reduce PPV is to lower the hammer energy
since there is a direct relationship between
hammer energy and the resultant ground
vibration. Ground PPV generally follows a
square root relationship with hammer energy

Page 470 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 14 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
(i.e. PPV ~ √Hammer Energy). The degree of
hammer energy reduction must be balanced
against the likelihood/severity of expected
exceedances, increase in total driving time, and
ability to drive to required friction tolerances.
 Vibration Monitoring - It is recommended that
vibration monitoring be conducted at any
building where equipment is operating closer
than the limits noted in the table below.

Construction Equipment Vibration Reference
Levels
Equipment Description Minimum Separation
Distance
Pile Driver (impact) 52 feet
Pile Driver (Vibratory) 32 feet
Vibratory Roller 14 feet
Compactor (Ground) 13 feet
Large Bulldozer 8 feet
PS-1
The City shall provide reasonable advance notification
to service providers such as fire, police, and emergency medical services as well as to local businesses,
homeowners, and other residents adjacent to and
within areas potentially affected by the proposed
Project about the nature, extent, and duration of
construction activities. Interim updates should be
City of San Dimas Construction City of San
Dimas
Los Angeles
County Fire
Department

Page 471 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 15 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
provided to inform the public of the status of the
construction activities.

PS-2
The City shall provide advance notice (at least 10-days prior) to emergency (fire, police, medical) services for any lane or street closures that may impact traffic
circulation during construction.

City of San Dimas Construction City of San
Dimas N/A
TRAF-1
The Contractor will notify local Police and Fire
Departments of its intent for a full street closure at
least ten (10) days before closure is to begin. The
Contractor shall cooperate with local authorities relative to handling traffic through the area.

City of San Dimas Construction City of San
Dimas N/A
TRAF-2
Transportation of heavy construction equipment and/or
materials which requires use of oversized-transport
vehicles on State highways will need a Caltrans
transportation permit. Project specifications will limit construction traffic to off-peak periods to minimize the potential impact on State facilities. If construction
traffic is expected to cause delays on any State
facilities, a construction traffic control plan detailing these delays shall be submitted for Caltrans’ review.

City of San Dimas Construction City of San
Dimas
California
Department of
Transportation
TCR-1
Retain a Native American Monitor 30 Days Prior to
Commencement of Ground-Disturbing Activities.
 The City of San Dimas shall retain a Native
American Monitor from the Gabrieleño Band of
Mission Indians – Kizh Nation. The monitor
shall be retained prior to the commencement of
any “ground-disturbing activity” for the subject
City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission

Page 472 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 16 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
project at all project locations (i.e., both on-site
and any off-site locations that are included in
the project description/definition and/or
required in connection with the project, such as
public improvement work). “Ground-disturbing
activity” shall include, but is not limited to,
demolition, pavement removal, potholing,
auguring, grubbing, tree removal, boring,
grading, excavation, drilling, and trenching.
 The monitor will complete daily monitoring logs
that will provide descriptions of the relevant
ground-disturbing activities, the type of
construction activities performed, locations of
ground-disturbing activities, soil types, cultural-related materials, and any other facts, conditions, materials, or discoveries of
significance to the Tribe. Monitor logs will
identify and describe any discovered TCRs,
including but not limited to, Native American
cultural and historical artifacts, remains, places
of significance, etc., (collectively, tribal cultural
resources, or “TCR”), as well as any discovered
Native American (ancestral) human remains or
burial goods. Copies of monitoring logs will be
provided to the Tribe upon written request to
the City of San Dimas.

Page 473 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 17 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
 Upon discovery of any TCRs, all construction
activities in the immediate vicinity of the
discovery shall cease (i.e., not less than the
surrounding 50 feet) and shall not resume until
the discovered TCR has been fully assessed by
the Native American Monitor or qualified
archaeologist. The Native American Monitor or
qualified archaeologist will recover and retain
all discovered TCRs in the form and/or manner
the Tribe deems appropriate, in the Tribe’s sole
discretion, and for any purpose the Tribe
deems appropriate, including for educational,
cultural and/or historic purposes.

TCR-2
Unanticipated Discovery of Human Remains and
Associated Funerary Objects
 Native American human remains are defined in
PRC 5097.98 (d)(1) as an inhumation or
cremation, and in any state of decomposition or
skeletal completeness. Funerary objects, called
associated grave goods in Public Resources
Code Section 5097.98, are also to be treated
according to this statute.
 If Native American human remains and/or
grave goods discovered or recognized on the
City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission

Page 474 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 18 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
Project site, then all construction activities shall
immediately cease. Health and Safety Code
Section 7050.5 dictates that any discoveries of
human skeletal material shall be immediately
reported to the County Coroner and all ground-disturbing activities shall immediately halt and shall remain halted until the coroner has
determined the nature of the remains. If the
coroner recognizes the human remains to be
those of a Native American or has reason to
believe they are Native American, he or she
shall contact, by telephone within 24 hours, the
Native American Heritage Commission, and
Public Resources Code Section 5097.98 shall be
followed.
 Human remains and grave/burial goods shall be
treated alike per California Public Resources
Code section 5097.98(d)(1) and (2).
 Construction activities may resume in other
parts of the Project site at a minimum of 200
feet away from discovered human remains
and/or burial goods, if the monitor determines
in its sole discretion that resuming construction
activities at that distance is acceptable and
provides the Project manager express consent

Page 475 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 19 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
of that determination (along with any other
mitigation measures the Native American
monitor and/or archaeologist deems
necessary). (CEQA Guidelines Section
15064.5(f).)
 Preservation in place (i.e., avoidance) is the
preferred manner of treatment for discovered
human remains and/or burial goods. Any
historic archaeological material that is not
Native American in origin (non-TCR) shall be
curated at a public, non-profit institution with a
research interest in the materials, if such an
institution agrees to accept the material. If no
institution accepts the archaeological material,
it shall be offered to a local school or historical
society in the area for educational purposes.
 Any discovery of human remains/burial goods
shall be kept confidential to prevent further
disturbance.

TCR-3
Procedures for Burials and Funerary Remains
 As the MLD, the Koo-nas-gna Burial Policy shall
be implemented. To the Tribe, the term
“human remains” encompasses more than
human bones. In ancient as well as historic
City of San Dimas Construction City of San
Dimas
Native
American
Heritage
Commission

Page 476 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 20 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
times, Tribal Traditions included, but were not
limited to, the preparation of the soil for burial,
the burial of funerary objects with the
deceased, and the ceremonial burning of
human remains.
 If the discovery of human remains includes four
or more burials, the discovery location shall be
treated as a cemetery and a separate
treatment plan shall be created.
 The prepared soil and cremation soils are to be
treated in the same manner as bone fragments
that remain intact. Associated funerary objects
are objects that, as part of the death rite or
ceremony of a culture, are reasonably believed
to have been placed with individual human
remains either at the time of death or later;
other items made exclusively for burial
purposes or to contain human remains can also
be considered as associated funerary objects.

Cremations will either be removed in bulk or by
means as necessary to ensure complete
recovery of all sacred materials.
 In the case where discovered human remains
cannot be fully documented and recovered on

Page 477 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 21 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
the same day, the remains will be covered with
muslin cloth and a steel plate that can be
moved by heavy equipment placed over the
excavation opening to protect the remains. If
this type of steel plate is not available, a 24-
hour guard should be posted outside of
working hours. The Tribe will make every
effort to recommend diverting the Project and
keeping the remains in situ and protected. If
the Project cannot be diverted, it may be
determined that burials will be removed.
 In the event preservation in place is not
possible despite good faith efforts by the
Project applicant/developer and/or landowner,
before ground-disturbing activities may resume
on the Project site, the landowner shall arrange
a designated site location within the footprint of
the Project for the respectful reburial of the
human remains and/or ceremonial objects.
 Each occurrence of human remains and
associated funerary objects will be stored using
opaque cloth bags. All human remains,
funerary objects, sacred objects and objects of
cultural patrimony will be removed to a secure
container on site if possible. These items

Page 478 ends

City of San Dimas California Environmental Quality Act
Mitigation Monitoring and Reporting Plan
- 22 -
San Dimas Lone Hill Park Regional Watershed Management Program Project MND Mitigation Monitoring and Reporting
Mitigation Measure Implementation
Party
Implementation
Phase
Monitored
By
Outside
Agency
Coordination
should be retained and reburied within six
months of recovery. The site of
reburial/repatriation shall be on the Project site
but at a location agreed upon between the
Tribe and the landowner at a site to be
protected in perpetuity. There shall be no
publicity regarding any cultural materials
recovered.
 The Tribe will work closely with the Project’s
qualified archaeologist to ensure that the
excavation is treated carefully, ethically and
respectfully. If data recovery is approved by
the Tribe, documentation shall be prepared and
shall include (at a minimum) detailed
descriptive notes and sketches. All data
recovery data recovery-related forms of
documentation shall be approved in advance by
the Tribe. If any data recovery is performed,
once complete, a final report shall be submitted
to the Tribe and the National American
Heritage Commission (NAHC). The Tribe does
NOT authorize any scientific study or the
utilization of any invasive and/or destructive
diagnostics on human remains.

Page 479 ends

Infiltration System
Trash Capture
Stormwater Diversion
Infiltration System
Trash Collection
Stormwater Diversion

PUBLIC OUTREACH
ATTACHMENT 3

Page 480 ends

COLOR PALETTE: MANUFACTURERS:

BRITTANY BOURBONNAIS

LONE HILL PARK AGES
JUly 8, 2026 Page 481.9524
earth scape DRAWING# C25019SPR5 26 212

SAN DIMAS, CA
PROJECT: DESIGNED BY:

PROJECT# 25001182
DESIGNED FOR:

COLOR PALETTE: MANUFACTURERS:

WAT
BRITTANY BOURBONNAIS SINCE 19/3

LONE HILL PARK AGES
JUly 8, 2026 Page 482 9 524
earth scape DRAWING# C25019SPR5 26 212

SAN DIMAS, CA
PROJECT: DESIGNED BY:

PROJECT# 25001182
DESIGNED FOR:

October 24, 2026

VIA EMAIL AND PUBLIC HEARING SUBMISSION
To: Honorable Mayor and Members of the San Dimas City Council City of San Dimas
245 East Bonita Avenue
San Dimas, CA 91773
RE: FORMAL WRITTEN OPPOSITION — LONE HILL PARK REGIONAL WATERSHED

MANAGEMENT PROGRAM PROJECT
Public Hearing: November 9, 2026
Project Location: 500 North Shellman Avenue, San Dimas, CA 91773 State Clearinghouse No.: 2026021076
Reference: Initial Study/Mitigated Negative Declaration (February 2026) Dear Mayor and Members of the City Council:

I am submitting this letter to formally express my strong opposition to the Lone Hill Park Regional Watershed Management Program Project as currently proposed, particularly the construction of an additional parking lot, the potential loss of existing green space and mature trees, and the environmental and neighborhood impacts associated with the proposed improvements.

As a lifelong San Dimas resident and frequent visitor to Lone Hill Park, I am familiar with the park's existing conditions, recreational activities, and importance to the surrounding community.

I recognize the importance of responsible stormwater management, groundwater replenishment, and compliance with applicable water-quality requirements. My opposition is not directed toward those objectives. Rather, I question whether certain proposed surface improvements, particularly the additional parking lot, are necessary or appropriate given their potential impact on existing parkland, wildlife habitat, neighborhood conditions, and public resources.

Having reviewed the City's February 2026 Initial Study/Mitigated Negative Declaration (IS/MND), I believe several aspects of the proposed design warrant further examination and explanation before the City Council proceeds with approval.

1. Proposed Additional Parking Lot and Loss of Existing Green Space My primary objection concerns the proposed construction of an additional parking lot along Juanita Avenue.

ATTACHMENT 5

Page 483 ends

Lone Hill Park is an established neighborhood recreational resource whose existing open space, mature landscape, and natural environment should be preserved to the greatest extent feasible.

While the City proposes permeable paving for the additional parking area, converting existing grass or landscaped areas to vehicle parking would nevertheless result in a loss of natural green space and its associated recreational and environmental benefits.

I am particularly concerned that the parking expansion may be intended primarily to accommodate the significant number of participants and spectators attending organized softball activities. These events regularly attract substantial attendance, particularly on weekends during softball season.

If accommodating peak athletic-event parking demand is a primary justification for the expansion, I believe the City should demonstrate why that need warrants the permanent conversion of neighborhood parkland.

I am also concerned about the proximity of Gladstone Elementary School, located directly adjacent to Lone Hill Park. Any proposed increase in parking capacity should be evaluated in relation to school-related traƯic, pedestrian safety, neighborhood circulation, and access along Juanita Avenue, Shellman Avenue, and Gladstone Street.

Section 3.17 of the City's IS/MND concludes that significant transportation impacts are not anticipated. However, the available discussion does not clearly establish the actual parking demand or provide a detailed evaluation of the proposed parking area's operational eƯects near the school.

I respectfully request that the City provide:

1. A detailed, to-scale site plan identifying the exact location, dimensions, and number of proposed additional parking spaces.

2. A comparison showing the square footage of existing grass, landscaping, and open space that would be permanently converted to parking.

3. Any parking-demand or utilization studies supporting the proposed expansion, including demand during ordinary park use, weekend softball activities, and evening practices.

4. A traƯic and pedestrian-safety assessment addressing the surrounding residential streets and Gladstone Elementary School.

Page 484 ends

5. Documentation identifying alternative designs that would eliminate the additional parking lot while preserving the project's necessary stormwater-management functions.

6. The estimated construction and ongoing maintenance costs attributable specifically to the proposed parking expansion.

I strongly request that the City reconsider and eliminate the proposed additional parking lot in favor of preserving the park's existing natural green space.

2. Environmental Review, Wildlife Habitat, and Preservation of Mature Trees I have significant concerns regarding the potential environmental impacts of the project, particularly the disturbance or removal of existing vegetation and wildlife habitat.

Lone Hill Park supports a variety of wildlife, including falcons, wild parakeets, other birds, squirrels, rabbits, and additional species that I regularly observe throughout the park.

The existing trees, grass, and landscaped areas provide important shelter, nesting opportunities, and feeding habitat for these animals.

Section 3.4 of the City's IS/MND evaluates biological resources and relies in part on the park's developed, urban setting when assessing habitat suitability. However, the study also acknowledges that existing trees may provide nesting habitat and that some trees are proposed for removal.

Although Mitigation Measures BIO-1 through BIO-3 establish certain biological assessment and protection requirements, I believe greater clarification is warranted regarding actual site conditions and the implementation of these measures.

I respectfully request:

1. The biological field surveys and supporting documentation used to evaluate wildlife species and nesting habitat at Lone Hill Park.

2. A complete inventory identifying mature trees proposed for removal, trees to be preserved, and the size and species of replacement trees.

3. Specific consideration of existing birds of prey, including falcons, and the potential eƯects of construction on nesting and breeding activity.

4. An explanation of how the required biological mitigation measures will be implemented, monitored, and enforced.

Page 485 ends

5. An assessment of habitat impacts associated with the additional parking lot, new lighting, removal of vegetation, and prolonged construction.

6. Consideration of alternatives that preserve additional existing trees, grassland, and natural habitat.

The replacement of mature trees with new landscaping does not immediately restore the ecological benefits, shade, and wildlife habitat provided by established vegetation.

I therefore request that preservation of existing mature trees and natural areas receive priority in the final project design.

I also request that the City identify the supporting evidence for its conclusions regarding biological resources and determine whether additional site-specific environmental analysis is warranted before adopting the Mitigated Negative Declaration.

3. Project Budget, Financial Accountability, and Evaluation of Alternatives Given the substantial public investment contemplated for this project, I believe the City should provide greater financial transparency regarding the proposed improvements and their long-term costs.

Previously published information has identified an estimated capital cost of approximately $9.9 million, along with earlier design funding of approximately $900,000. I recognize that these figures may not represent the project's current approved budget.

Nevertheless, it is important for residents to understand how these public funds will be allocated and whether the proposed improvements are necessary to accomplish the project's primary stormwater-management objectives.

The City's project description identifies the capture, treatment, and infiltration of stormwater runoƯ from approximately 335 acres as a principal objective.

I respectfully request clarification regarding which components are necessary to achieve these environmental requirements and which represent discretionary recreational or parking improvements.

Specifically, I request:

1. The current total project budget, including amounts already expended, committed, or anticipated.

2. An itemized allocation of costs for the underground stormwater infrastructure, additional parking lot, recreational courts, playground, pathways, landscaping, and other proposed improvements.

Page 486 ends

3. Identification of all project funding sources, including applicable Measure W funding, grants, and City contributions.

4. Clarification of any restrictions on funding that would aƯect the City's ability to modify or eliminate particular improvements.

5. Estimated annual operation, maintenance, inspection, and replacement costs following project completion.

6. A comparative cost and feasibility assessment of alternative designs that would preserve existing parkland and eliminate the additional parking area.

I recognize that the project provides important stormwater-management benefits.

However, the necessity of the underground infrastructure should be evaluated separately from the proposed surface improvements wherever feasible.

Before committing substantial public funds, the City should demonstrate that the proposed design represents an appropriate balance of environmental compliance, financial responsibility, neighborhood recreational needs, and preservation of existing parkland.

4. Existing Park Maintenance and Operational Concerns
Lone Hill Park already experiences substantial recreational activity, particularly during organized softball games, tournaments, and evening practices.

I have personally documented recurring problems involving excessive litter, overflowing trash receptacles, and substantial waste left behind following sporting activities.

I have also discussed these conditions directly with the landscaping personnel responsible for maintaining the park. These employees routinely face the burden of collecting preventable litter associated with organized recreational use.

I have photographs documenting these conditions, which have not previously been submitted to the City and are available for inclusion in the public record.

Additionally, I have observed what appears to be alcohol consumption by participants, spectators, and individuals appearing to serve as coaches during softball games and practices.

I request clarification of the City's applicable park regulations, whether organized sporting groups are subject to specific permit conditions, and how those requirements are enforced.

Page 487 ends

I have also observed recurring overnight vehicle occupancy and individuals sleeping or sheltering in landscaped areas within and around the park. I have contacted the SheriƯ's Department regarding these conditions.

I recognize the importance of treating individuals experiencing homelessness with dignity while also maintaining safe, sanitary, and accessible public facilities.

These issues raise legitimate questions regarding existing maintenance resources, enforcement responsibilities, and the potential operating impacts of additional parking.

Before expanding vehicle capacity or introducing facilities that may increase usage, I request that the City evaluate:

1. Existing trash collection capacity, weekend maintenance schedules, and cleanup responsibilities of organized athletic groups.

2. Whether additional trash receptacles, event cleanup requirements, or enforceable permit conditions are necessary.

3. Applicable alcohol regulations and current enforcement procedures.

4. Existing overnight parking and camping policies, including coordination with appropriate outreach services.

5. Whether the proposed parking expansion could increase maintenance or overnight management challenges.

6. The additional staƯing, maintenance, and enforcement costs associated with the proposed improvements.

These concerns are relevant to the long-term operation and stewardship of Lone Hill Park and should be considered when evaluating the necessity and appropriateness of additional facilities.

5. Community Input and Neighborhood Recreational Priorities When this project was initially introduced, I attended the informational meeting held at Lone Hill Park and provided my contact information, expressing my interest in reviewing future plans and oƯering suggestions.

Although I did not receive subsequent project updates, I recognize that the City has undertaken a formal public review process.

Page 488 ends

Given the scope of the proposed improvements, I respectfully request access to the current detailed engineering and landscape plans and an additional opportunity for interested neighborhood residents to review the design before final approval.

This request is consistent with Section 2 of the City's IS/MND, which identifies incorporating community-based input among the project's objectives.

During the initial meeting, residents also suggested incorporating a modest, designated dog-friendly area within the park.

I would appreciate clarification regarding whether that suggestion was evaluated and whether an appropriately designed dog area could be considered without unnecessarily reducing existing green space or disturbing sensitive wildlife habitat.

More broadly, I request that the City explain how recreational improvements were prioritized, including whether neighborhood needs assessments, resident surveys, or other documented community input informed the current design.

Section 3.16 of the IS/MND concludes that the proposed recreational improvements will benefit the community. I believe that conclusion would be better supported by a transparent explanation of how existing recreational space, proposed amenities, and resident preferences were evaluated.

6. Construction Impacts and Protection of Surrounding Residents The City's published project information has contemplated approximately 16 months of construction, subject to funding and scheduling.

Given the park's proximity to Gladstone Elementary School and surrounding residences, I request that the City provide detailed information regarding construction impacts and the measures intended to protect nearby properties, pedestrians, schoolchildren, park users, and wildlife.

Sections 3.3 and 3.13 of the IS/MND address air quality, noise, and vibration, including mitigation measures intended to reduce construction-related impacts.

I respectfully request:

1. A detailed construction schedule identifying anticipated phases, temporary closures, and the duration of disruptions.

2. Proposed construction vehicle routes, equipment staging locations, and traƯic-control measures.

3. Specific protections for school-related pedestrian and vehicle circulation.

Page 489 ends

4. Procedures for controlling and monitoring construction noise, dust, and vibration.

5. Measures to protect nearby residential properties, existing mature trees, and wildlife habitat.

6. Identification of the responsible City representative for construction-related complaints and mitigation compliance.

Residents should receive advance notice of significant construction activities and have access to a clear process for reporting and resolving concerns throughout the project.

7. Requests Regarding the Initial Study/Mitigated Negative Declaration Based on my review of the February 2026 IS/MND, I respectfully request that the City Council consider the following matters before adopting the environmental document or approving the project.

Biological Resources — Section 3.4: Provide the supporting evidence for the biological conclusions, including applicable field surveys, proposed tree removals, and the implementation and monitoring requirements associated with Mitigation Measures BIO-1 through BIO-3.

Hydrology and Water Quality — Section 3.10: Clarify whether the proposed parking lot is necessary to achieve the stormwater project's regulatory objectives and whether a design preserving existing green space would remain technically feasible.

Recreation — Section 3.16: Explain how the City evaluated the loss or modification of existing recreational open space, the selection of proposed amenities, and alternative designs responsive to neighborhood needs.

Transportation — Section 3.17: Provide supporting documentation addressing parking demand, operational circulation, and pedestrian safety in relation to the adjacent elementary school and surrounding neighborhood.

Construction Noise and Vibration — Section 3.13: Identify how mitigation requirements will be monitored and enforced and how nearby residents and school representatives will be notified of and protected from significant construction activity.

I further request access to the project's current Mitigation Monitoring and Reporting Program, underlying technical studies, and any public or agency comments and responses prepared in connection with the environmental review.

I am not asserting that the City has necessarily violated applicable environmental requirements. Rather, I respectfully request that the Council carefully consider whether the

Page 490 ends

available analysis adequately addresses the site-specific concerns identified in this correspondence and whether additional environmental review or project modifications are warranted.

FORMAL REQUESTS FOR CITY COUNCIL ACTION
For the reasons outlined above, I respectfully request that the City Council:

1. Continue the November 9, 2026 public hearing and defer adoption of the Mitigated Negative Declaration and approval of the project in its currently proposed form until the identified issues have been adequately addressed.

2. Direct staƯ to evaluate eliminating the proposed additional parking lot along Juanita Avenue and preserving the aƯected existing green space.

3. Provide complete current engineering drawings, landscape plans, environmental supporting studies, parking analyses, and detailed project cost information.

4. Evaluate and publicly present feasible alternatives that accomplish the project's required stormwater-management objectives while minimizing impacts on existing parkland and wildlife habitat.

5. Consult with Gladstone Elementary School and the responsible school district regarding traƯic, pedestrian safety, and construction impacts.

6. Evaluate existing park maintenance, sanitation, enforcement, and overnight management concerns in connection with any proposed increase in parking or recreational capacity.

7. Explain how resident suggestions and neighborhood recreational priorities, including the proposed dog area, have been considered.

8. Conduct an additional public meeting and provide a reasonable opportunity for residents to review the current detailed design.

9. Provide written responses to the substantive questions and requests identified in this letter.

10. Include this correspondence and any supplemental photographic evidence in the oƯicial public hearing and administrative record.

Page 491 ends

Conclusion
I support responsible stormwater management and environmental improvements that provide meaningful benefits to San Dimas.

However, those goals should be pursued in a manner that preserves existing neighborhood parkland to the greatest extent feasible, protects mature trees and wildlife habitat, and ensures that proposed improvements are supported by demonstrated need and appropriate financial and environmental analysis.

Lone Hill Park is an established community resource whose natural landscape, open space, recreational functions, and proximity to Gladstone Elementary School deserve careful consideration before permanent changes are approved.

I respectfully urge the City Council to reconsider the proposed parking expansion, evaluate less disruptive alternatives, and provide greater transparency and meaningful public participation before proceeding.

Please distribute this correspondence to all City Council members, include it in the oƯicial hearing and administrative record, and acknowledge receipt in writing.

I also request written responses to the substantive matters raised and inclusion in all future project notices, updates, and public review opportunities.

Thank you for your time and consideration.

Sincerely,
Kourtney Preston
San Dimas Resident
626-475-6767
Supporting Materials: Photographs documenting excessive litter and apparent alcohol consumption associated with organized park activities are included below.

Page 492 ends

Photos from 3/16/26

Page 493 ends

Photos from 2/2/26

Page 494 ends

Photo from 9/8/25

Page 495 ends

Photo from 12/16/24

Page 496 ends

Photo from 9/12/24

Page 497 ends

ATTACHMENT 6
Response to November 9, 2026
Public Notice Comment Letter
This document summarizes responses to the comment letter dated October 24, 2026 in relation to the Lone Hill Park Regional Watershed Management Program Project (Project) in advance of the November 9, 2026 scheduled public hearing. The subsections below follow the format of the comment letter.

1. Proposed Additional Parking Lot and Loss of Existing Green Space
A new parking lot is proposed off Juanita Avenue just east of Shellman Avenue to support softball programming. The parking lot will help reduce street parking demand. The inclusion and details of the parking lot do not significantly impact the findings included in the Mitigated Negative Declaration (MND).

1. The design plans include details on the parking lot layout. This level of detail is not required for the environmental document. The parking lot includes 20 spaces, of which, two (2) support Electric Vehicle (EV) charging and one (1) is Americans with Disabilities Act (ADA) accessible.

2. The parking lot is approximately 9,500 square feet. Existing turf area will be replaced with the parking lot, which includes pervious pavement parking stalls.

3. Specific studies were not required to support the design. During softball programming, cars can be observed parking on the adjacent neighborhood streets.

4. This is not applicable or required to support the inclusion of the parking lot.

5. The parking lot is not related to the stormwater management functions. The stormwater capture features are located on the north side of the park. The parking lot is included to help address other park needs (parking to support programming).

6. Parking lot maintenance is considered minimal. The pervious pavement will be inspected and cleaned annually. City includes municipal parking lots in the bi-weekly street sweeping schedule.

2. Environmental Review, Wildlife Habitat, and Preservation of Mature Trees

1. Field surveys evaluating biological resources and nesting habitats will be performed prior to construction activities. The MND highlights potential findings based on available resources.

Site specific studies will be available prior to construction. It is common for biological resource assessments to be performed prior to construction, such that the most relevant information can be collected prior to disturbance, especially in more developed areas.

2. The design plans include details on tree removal, protection, and new trees. This level of detail is not required for the environmental document.

3. Mitigation Measure BIO-2 identifies requirements for nesting bird surveys, which will be performed prior to construction activities within the nesting bird season. The qualified biologist will make recommendations or define set back requirements if nesting birds are observed.

4. The City is responsible for implementing mitigation measures in accordance with the MND and Mitigated Monitoring and Reporting Program (MMRP).

Page 498 ends

5. In accordance with the biological resource mitigation measures, a habitat assessment will be performed prior to Project construction.

6. The Project footprint covers the area required for the amenities included. Trees were avoided when possible and new trees will be planted as part of the Project. New native/low water use planting is included in the design, which will support native bees, butterflies, and other habitats.

3. Project Budget, Financial Accountability, and Evaluation of Alternatives
Construction funding has not been secured at this point. The City received funding from the Safe, Clean Water Program (SCWP) to support the Project design. That funding program, along with other potential future funding programs, prioritize multi-benefit projects that combine features like stormwater management with other community benefits, such as park enhancements.

1. The estimated construction budget is approximately $15 million, while the actual cost will depend on when construction moves forward, funding availability, and other economic conditions at the time of construction. The City received $900,000 from SCWP to support the design of the Project.

2. An itemized cost opinion will be included as part of the final design package and is not relevant to the environmental document.

3. The City has secured $900,000 for the Project design from the SCWP Regional Infrastructure funding program. Construction funding has not been secured at this time.

4. As noted above, the City has not secured construction funding at this time. Depending on the funds secured, certain improvements may or may not be eliminated. This will depend on the final funding agreements between the City and partnering/funding agencies.

5. Operation, maintenance, inspection, and replacement costs will depend on the final constructed conditions, weather patterns, and other details that are not available at the time of environmental document adoption. Typically, annual operation and maintenance costs for similar projects is around $150,000 per year.

6. As noted above, the parking lot helps meet park programming needs. Alternatives are not being assessed.

4. Existing Park Maintenance and Operational Concerns

1. The City regularly maintains Lone Hill Park, including trash collection and litter removal. Staff will evaluate whether adjustments to maintenance schedules are warranted during periods of increased recreational activity.

2. The City will evaluate the need for additional trash receptacles and cleanup requirements for organized athletic activities to help maintain park cleanliness.

3. Alcohol consumption is subject to applicable City park regulations. Concerns regarding violations may be reported to the Los Angeles County Sheriff's Department for appropriate enforcement

4. Overnight parking and camping are subject to applicable City regulations, with enforcement coordinated through the Sheriff's Department and appropriate outreach services as needed.

The proposed design includes a sidewalk extending around the perimeter of the park that will accommodate Sheriff's deputies driving through the park to conduct patrols and address security concerns.

Page 499 ends

5. As noted above, parking lot maintenance is considered minimal. The pervious pavement will be inspected and cleaned annually. It is not anticipated that the new parking lot will significantly increase maintenance or overnight management challenges.

6. As noted above, additional staffing, maintenance, and enforcement is not anticipated because of the new parking lot. The stormwater management system will require maintenance (additional details above), while it does not directly require additional staffing or enforcement.

5. Community Input and Neighborhood Recreational Priorities The City can provide the latest conceptual design plans for review. The City held three initial public outreach events to gather community feedback on preferred recreational amenities and a theme for the new playground, reaching approximately 400 residents. Pickleball courts and a full-size basketball court were identified as the top priorities and are included in the conceptual design. A dog park ranked third; however, given the park’s existing recreational uses, available space, and proposed improvements, it was determined that a designated dog park would not be appropriate for this location. The proposed amenities were subsequently reviewed by the Parks & Recreation Commission.

The conceptual design is not final, and the specific improvements will depend on the availability and amount of construction funding secured. Should construction funding be obtained, the plans will be refined based on available funding, and the City will conduct an additional public outreach event at Lone Hill Park to provide residents an opportunity to review the updated design and provide feedback. The event will be scheduled during a period of high park usage to maximize participation. Residents surrounding the park will again be notified by mail, and the event will be advertised through the City's social media channels.

Community feedback will be presented to the Parks & Recreation Commission for review and recommendations. The final design, incorporating community input and Commission feedback, will then be presented to the City Council for consideration and final approval.

6. Construction Impacts and Protection of Surrounding Residents

1. A detailed construction schedule will be developed once the City has secured construction funding and a contractor is selected. The timeline and sequencing of the Project will depend on the funding received (elements funded) and construction start date. The Project specifications require work in front of Gladstone Elementary School on Shellman Avenue during the summer months when school is not in session.

2. Proposed construction vehicle routes, equipment staging locations, and traffic control measures will be detailed by the contractor once selected and will be in accordance with local ordinances and Project specifications.

3. Pedestrian and school access must be maintained during construction. Work will be coordinated with the elementary school and school district once funding is secured.

4. The City team will work with the selected contractor to monitor construction noise, dust, and vibration. Specific monitoring requirements will be included in the Project specifications in alignment with the MND and associated mitigation measures. On similar projects, monitoring devices have been installed and monitored by the City team.

5. The MND includes mitigation measures that help reduce impacts on nearby residential properties, trees, and habitat. For some specific examples, refer to Sections 3.3 (Air Quality),

3.4 (Biological Resources), and 3.13 (Noise).

Page 500 ends

6. The City representative for construction-related complaints and mitigation compliance will be determined and shared once the construction phase receives funding and the construction schedule is confirmed.

7. Requests Regarding the Initial Study/Mitigated Negative Declaration
Refer to responses on most of these comments in the sections above. Unfortunately, the public comment period has closed. Most of the comments are related to Project design and do not present evidence of a significant environmental impact that the MND did not address.

Page 501 ends

Agenda Item Staff Report
To: Honorable Mayor and Members of City Council
For the Meeting of November 9, 2026
From: Brad McKinney, City Manager
Prepared by: Joseph Jones, Recreation Manager
Subject: Discuss Future Fourth of July Celebrations and the San Dimas 2026 Event Cost
____________________________________________________________________________

SUMMARY
At the July 28, 2026, City Council Meeting, the City Council asked staff to return with an agenda item to discuss future Fourth of July celebrations, including a report on the cost of the San Dimas 2026 event held on July 3, 2026: Stars, Stripes and Drone Lights. The event cost $108,187.29, which covered City staff, San Dimas Sheriff’s Department staff, live entertainment, street closures, food, supplies and the Drone Show. The 2026 Committee raised $76,400 toward these costs, and the City paid the remaining $31,787.29. Without the Committee’s fundraising, an annual Fourth of July event would require approximately $81,000 - $90,000 in new funding each year, depending on whether it is held on July 3 or July 4.

RECOMMENDATION
Staff recommends that the City Council continue the City Birthday celebration and Music in the Park programming without adding an annual Fourth of July event, due to the event’s financial impact on the City's Special Events budget and the extensive planning and coordination it requires. Returning to the 2024 format, in which the City Birthday celebration and Music in the Park are combined into one celebration during the first week of August, would allow the City to continue offering community events while maximizing the use of available resources and helping manage event-related costs.

This approach would support the City's ongoing commitment to community engagement and quality programming while maintaining greater fiscal responsibility and limiting new demands on the City's budget.

Page 502 ends

Future July 4th/City Birthday Celebrations Page 2
For the Meeting of November 9, 2026
GOVERNMENT CODE §84308 APPLIES:
https://leginfo.legislature.ca.gov
No

FISCAL IMPACT
There would be no additional fiscal impact if the City Council approves the staff recommendation.

If the City Council instead chooses to hold an annual Fourth of July event, the City would need to replace the $76,400 the 2026 Committee raised. Based on staff's estimates for 2027 (Table 1), the City would need to add the following to its annual Special Events budget:
• July 3 event: approximately $81,000 for a total of $112,787.29 • July 4 event: approximately $90,000 for a total budget of $121,812.73, which includes an estimated $9,056 in holiday overtime for City and Sheriff's Department staff The amounts listed above were based on the costs at the time of the event and may increase for 2027. Salary and benefit costs are expected to increase between 1-4% based on the adopted memorandum of understanding. Costs for the drone show and public safety are expected to rise as well; however, those amounts are unknown at this time.

BACKGROUND
On July 22, 2016, Public Law 114-196 was signed into law, which established the United States Semi Quincentennial Commission to plan national celebrations and encourage state and local efforts to coordinate with the national effort to celebrate the 250th Anniversary of the Declaration of Independence.

On April 26, 2022, City Council adopted a resolution officially recognizing the San Dimas Rotary Foundation as the City’s Official Planning Organization for Events Related to the 250th Anniversary of the Declaration of Independence (Resolution 2022-24).

The San Dimas Rotary and Foundation led the effort to establish a local community committee to further coordinate celebrations locally with the national celebrations contemplated under Public Law 114-196. The City participated in this planning effort along with community members from organizations including the Rotary Club of San Dimas, San Dimas Masonic Lodge, San Dimas/ La Verne Woman’ s Club, La Verne/San Dimas Educational Foundation, San Dimas Rotary Foundation, San Dimas Sheriff’ s Boosters, San Dimas Historical Society, Bonita Unified School District, Bonita Unified School District Parent Teacher Association, and the San Dimas Chamber of Commerce.

DISCUSSION/ANALYSIS
Planning and Fundraising
The 2026 San Dimas Committee was tasked with planning the celebration in partnership with the City of San Dimas and raising sufficient funds to ensure the event would not create additional costs for the City's annual Special Events budget.

Page 503 ends

Future July 4th/City Birthday Celebrations Page 3
For the Meeting of November 9, 2026
For the first four years, the committee met monthly to plan and coordinate the celebration. During the final year, meetings increased to a weekly schedule to address the additional planning, coordination, and logistical requirements associated with the event. Through donations, sponsorships, and fundraising efforts, the committee successfully raised $76,400. These funds directly supported several key components of the celebration, including the opening ceremony flyover, the National Marine Corps Band, the Fife and Drum Band, and the first-ever drone show featuring 400 drones.
2026 Event Costs and Projected Future Costs
The 2026 event cost a total of $108,187.29. After applying the Committee's $76,400, the City's net cost was $31,787.29. Table 1 itemizes the 2026 costs and compares them with staff's estimate for a July 4 event in 2027.

Table 1: 2026 Actual Costs and 2027 July 4 Estimate
July 3, 2026 (Actual) July 4, 2027
(Estimate)*
Difference
City Staff $12,116.92 $14,903.58 $2,786.66
Sheriff's Staff $12,539.43 $18,809.15 $6,269.72
Live Entertainment $2,500.00 $2,600.00 $100.00
Street Closures $2,488.80 $3,000.00 $511.20
Food & Supplies $1,976.14 $2,500.00 $523.86
Drone Show $76,566.00 $80,000.00 $3,434.00
Total Cost $108,187.29 $121,812.73 $13,625.44
Less Committee
Fundraising
($76,400.00) $0.00 $76,400.00
Net Cost to City $31,787.29 $121,812.73 $90,025.44

Page 504 ends

Future July 4th/City Birthday Celebrations Page 4
For the Meeting of November 9, 2026
* Staffing: 26 full-time and 23 part-time City staff; 9 deputies and 2 sergeants. 2027 staffing estimates reflect holiday overtime at current pay rates. Estimates do not include future cost-of-living adjustments (COLAs) or Consumer Price Index (CPI) adjustments.

Holding the event on July 4 rather than July 3 would add an estimated $9,056 in holiday overtime: $2,787 for City staff and $6,270 for Sheriff's Department staff. Depending on the size of the event, additional Sheriff's Department resources may also be needed.

Comparison with Other City Events
For comparison, the City Birthday celebration cost $14,078, and a single Music in the Park event (one of ten held each year) cost $4,118. When the two were combined into one event, the total cost was $16,500, about $1,700 less than holding them separately.

These events are valuable to the community, but they are not directly comparable to the Fourth of July celebration. The Fourth of July draws larger crowds and requires more public safety personnel, coordination across multiple City departments, and the closing and reopening of streets for the drone show. These factors account for its substantially higher cost.

The 2026 Committee invested five years of planning, coordination, and fundraising to deliver a major community celebration while working toward the goal of minimizing the financial impact on the City's Special Events budget. The Committee's fundraising efforts helped fund the event's featured attractions, while additional funds supported essential operational expenses.

ALTERNATIVES

1. Approve the staff recommendation and return to the 2024 format, combining the City Birthday celebration and Music in the Park into one celebration during the first week of August.

2. Hold an annual Fourth of July celebration on July 3, in a format similar to 2026, and add approximately $81,000 to the annual Special Events budget.

3. Hold an annual Fourth of July celebration on July 4 and add approximately $90,000 to the annual Special Events budget.

4. Provide other direction to staff.

ENVIRONMENTAL REVIEW
Pursuant to CEQA guidelines Section 15061 (b)(3), CEQA does not apply to this item because there is no potential for causing a significant effect on the environment. Therefore, no additional environmental review is needed at this time.

Respectfully submitted,
Joseph Jones
Recreation Manager

Page 505 ends

Agenda Item Staff Report
To: Honorable Mayor and Members of City Council
For the Meeting of November 9, 2026
From: Brad McKinney, City Manager
Prepared by: Travis Sais, Assistant City Manager
Subject: Provide Direction and Select a Proposed Location for a Proposed Route 66 Centennial Monument Sign Project; Approve Necessary Budget Appropriations ____________________________________________________________________________

SUMMARY
In June 2026, the City Council asked staff to explore installing a Route 66 monument sign on Foothill Boulevard in recognition of the Route 66 Centennial. The sign would be part of a national program led by VOX Industries LLC, which is installing matching, interactive monument signs in cities along Route 66 from Chicago to Santa Monica.

Staff met with Brian Brown of VOX Industries LLC to review the program’s requirements, cost, and siting criteria. VOX Industries LLC has the signs fabricated and installed for a flat fee of $37,500. The City would be responsible for securing and preparing the site and providing power to the sign. Azusa and Claremont have installed signs, Upland has committed to participate, and several other California cities are considering the program.

Staff evaluated five potential sites on Foothill Boulevard, as well as right-of-way constraints and power options, including solar. Staff recommends 333 E. Foothill Boulevard (Canyon Trail Plaza) for its visibility, ample parking, and attractive setting. The property owner has confirmed interest in hosting the sign.

Staff requests that the City Council decide whether to proceed with the project, approve funding, and select a preferred location.

RECOMMENDATION
Staff recommends that the City Council:

1. Discuss and provide direction to staff on the Route 66 Centennial Monument Sign Project and a location for the sign; and

2. Approve a budget appropriation of $37,500 for the sign and $22,500 for electrical service and site preparation work, for a total of $60,000 to account number 070.4314.041.047.

Page 506 ends

Provide direction on a proposed Route 66 Centennial Monument Sign Project Page 2 For the Meeting of November 9, 2026
GOVERNMENT CODE §84308 APPLIES:
https://leginfo.legislature.ca.gov
No

FISCAL IMPACT
VOX Industries charges a flat fee of $37,500 to fabricate and install the sign. The City would also be responsible for the cost of providing power, which depends on the site and the power source selected. A standard electrical connection would likely require trenching, conduit, wiring, and utility connection fees, and the cost increases with the distance from an existing power source. A solar option would need panels large enough to run the sign, which could affect how the sign looks.

Staff is evaluating both options and estimates that either would cost approximately $22,500, which includes site preparation work. Funding for the monument sign would utilize reserves within the new equipment reserve fund 070.

BACKGROUND
Cities and national organizations are preparing for the 100th anniversary of Route 66 on November 11, 2026. VOX Industries LLC is leading a program to install matching monument signs in participating cities from Illinois to California. In California, VOX Industries contracts with California Sign Company, a licensed contractor, to install the signs. Participating cities in the region include:
• Azusa: Sign installed at Foothill Boulevard and Alameda Avenue. • Claremont: Sign installed in the public parkway on the north side of Foothill Boulevard, west of Indian Hill Boulevard, adjacent to the Old School House parking lot. • Upland: The first sign is scheduled for installation in November 2026. According to VOX Industries LLC, the City of Upland has also committed to a second sign.

As of the writing of this report, 37 signs have been dedicated, with others in progress. VOX Industries places orders with its sign manufacturer once five cities have committed. According to VOX Industries, San Dimas would be the third commitment toward the next order.

Within the City, the public right-of-way along Foothill Boulevard typically extends only eight feet from the curb. Some street corners have slightly more space, but not enough to accommodate a permanent sign and a safe area for visitors to stand. As a result, the sign would need to be installed on private property with the owner’s permission.

DISCUSSION/ANALYSIS
Vox Industries LLC has indicated that the sign program guidelines call for signs to be placed where visitors can park, walk up to the sign, and take photos safely without standing in traffic or driveways. For this reason, street medians and the narrow parkway strips along the curb are not suitable.

Staff evaluated five potential sites on Foothill Boulevard based on parking, photo setting and location along the corridor.

Page 507 ends

Provide direction on a proposed Route 66 Centennial Monument Sign Project Page 3 For the Meeting of November 9, 2026

1. 333 E. Foothill Boulevard (Canyon Trail Plaza / Twisted Sage Cafe) — Staff Preferred Location
a. Strengths: Attractive building backdrop, a popular restaurant, ample on-site parking, and a central location that is highly visible from the street. b. Property Owner: The owner, SeaWest Enterprises (Eric Simison), has confirmed interest in hosting the sign on the property.

2. 455 E. Foothill Boulevard (Near Montessori School)
a. Strengths: Attractive backdrop near the center of the City’s segment of Route 66. b. Drawbacks: Heavy pedestrian and vehicle traffic during school drop-off could create crowded and unsafe conditions for visitors stopping to take photos. Public parking is limited.

3. 630 E. Foothill Boulevard (Golden State Water Company) a. Strengths: A long-standing local business with community ties. b. Drawbacks: Lacks the mountain backdrop available at sites farther west.

4. 269 W. Foothill Boulevard (Pinnacle Peak Site)
a. Strengths: Located at the western entry to the City’s segment of Route 66. b. Drawbacks: The site is less attractive than sites to the east.

5. 416 E. Foothill Boulevard (Kosmo Burger)
a. Strengths: Highly visible and located in a busy commercial area. b. Drawbacks: Limited parking and room for group photos.

Staff believes 333 E. Foothill Boulevard offers the best combination of visibility, safety, appearance, and parking. Staff contacted the property owner, who confirmed interest in having the sign installed on the west end of the property, facing Foothill Boulevard (as shown in the PowerPoint Attachment)
Staff is evaluating two ways to power the sign; a standard electrical connection or solar. Of the Route 66 Centennial signs VOX Industries LLC has installed so far, only one is solar-powered. It was installed in Bethany, Oklahoma, in May 2026, and VOX reports that it has performed well.

However, solar panels could affect the sign’s appearance. At 333 E. Foothill Boulevard, staff estimates that bringing power to the sign and completing the necessary site preparation would cost approximately $22,500 under either power option. These improvements include items such as sidewalk or decomposed granite, landscaping, and curb work.

Each sign includes a QR code on its post that directs visitors to a page about the City on the national program’s website. The page serves as a travel guide for domestic and international Route 66 travelers, highlighting local businesses, history, and points of interest. The URL for the project website is https://route66monuments.com/.

The sign could also bring visitors to local businesses. Travelers who stop to photograph it can scan a QR code that lists nearby restaurants, shops, and attractions. San Dimas will also have its own page on the Route 66 Centennial Monument website, which will stay up after the centennial year. Staff can promote the page on the City’s website and social media.

If the City Council approves the Route 66 Centennial Monument Sign Project at 333 E. Foothill Boulevard, staff will seek an easement from the property owner, in a form approved by the City Attorney. If the owner does not grant an easement, staff will return to the City Council to request approval of a license agreement instead.

Page 508 ends

Provide direction on a proposed Route 66 Centennial Monument Sign Project Page 4 For the Meeting of November 9, 2026

ALTERNATIVES

1. Choose a Different Site: The Council may direct staff to pursue one of the other four sites (455 E., 630 E., 269 W., or 416 E. Foothill Boulevard) or to evaluate additional locations.

2. Require a Standard Electrical Connection: The Council may direct staff to pursue a standard electrical connection only and not consider solar.

3. Do Not Participate (Receive and File): The Council may decline to participate in the program at this time and take no further action.

ENVIRONMENTAL REVIEW
Pursuant to CEQA guidelines Section 15061 (b)(3), CEQA does not apply to this item because there is no potential for causing a significant effect on the environment. Therefore, no additional environmental review is needed at this time.

Respectfully submitted,
Travis Sais
Assistant City Manager
Attachments:

1. Proposal from Vox Industries LLC

2. PowerPoint Presentation – Route 66 Centennial Monument Sign Project

Page 509 ends

ATTACHMEN
Introducing
THE ROUTE 66 CENTENNIAL

MONUMENT PROJECT
ROUTE
66 1926-2026

CENTENNIAL

SAN DIMAS

PROPOSAL PREPARED FOR
City of San Dimas
ATTACHMENT 1

Page 510 ends

AN OFFICIALLY RECOMMENDED PROJECT OF THE US ROUTE GEN 54 MIAL COMMISSION

SAN DIMAS

Page 511 ends

MONUMENT TOTAL $37,500.00

MONUMENT LOCATION

MONUMENT

QTY DESCRIPTION PRICE TOTAL
1 $37,500.00 $37,500.00
2026 WARRANTY AND TERMS
Warranty, Network Responsibility, Project Terms & Service Support Warranty (Two-Year Limited Workmanship Warranty)
Vox Audio Visual (“Vox AV”) provides atwo (2) year limited warranty from the date of system commissioning covering workmanship and system integration performed by Vox AV.

Workmanship & Integration Warranty (2 Years)
For a period of two (2) years from system commissioning, Vox AV warrants:

Installation workmanship
System integration and configuration
Termination, labeling, and routing of cabling installed by Vox AV Rack assembly, equipment mounting, and physical system build quality If a covered workmanship issue is identified during this period, Vox AV will repair or correct the issue at no cost to the client.

Equipment & Manufacturer Warranty (Up to Two Years Maximum) All equipment supplied by Vox AV is coveredexclusively by the original manufacturer’s warranty, subject to the manufacturer’s terms and conditions.

Manufacturer warranties are passed through to the client and honored to the extent provided by the manufacturer.

Warranty periods vary by manufacturer and product and typically range fromone (1) year up to two (2) years.

Under no circumstances will Vox AV warrant hardware for more than two (2) years, regardless of any longer manufacturer-stated warranty.

Extended Manufacturer Warranties
In cases where a manufacturer offers a warranty period longer than two (2) years, any coverage beyond the two-year period may be available Placemaking Monument
PREPARED FOR: City of San Dimas
SCOPE:

SOLE SOURCE:

The Route 66 Centennial Monument Project is a unique art project designed to provide a continuous connection between Route 66 communities along the historic corridor from Chicago, Illinois to Santa Monica, California. This artwork was designed by Vox Industries in collaboration with public artist Stan Carroll. Each art piece is custom fabricated by Vox Industries of Oklahoma City. No other artists or fabricators are authorized to produce or attempt to replicate the custom art piece. The art was formally endorsed by the Oklahoma Route 66 Centennial Commission as an official Centennial project on August 13, 2024. Procuring an official Route 66 Centennial Monument is considered a unique and sole-sourced endeavor.

The Route 66 Centennial
Monument Project
DATE:July 7, 2026
QUOTE NUMBER: P-1165
PROJECT NAME: CA-San Dimas-City of San Dimas-Route 66
Centennial Monument

Page 3 of 8 ends
Page 512 ends

directly through the manufacturer. Vox AV does not administer, extend, or provide support for manufacturer warranties beyond two (2) years, and any such coverage is subject to the manufacturer’s terms, processes, and approval.

Important Manufacturer Warranty Timing Notice
Manufacturer warranty periods typically begin at the time of shipment, delivery to the distributor, or receipt by Vox AV —notthe client’s installation or commissioning date. As a result, a portion of the manufacturer warranty period may elapse prior to installation if equipment is staged or stored before deployment.

Vox AV does not reset, extend, or supplement manufacturer warranty timelines.

Warranty Applicability for System Additions, Expansions, or Modifications For projects involving additions, expansions, upgrades, or modifications to an existing system:

This warranty appliesonly to the equipment, cabling, programming, configuration, networking, and workmanshipprovided under the current project scope.

Existing or retained equipment and infrastructure remain subject to theiroriginal warranties and installation terms, if any.

Vox AV does not extend, renew, or reinstate warranties on existing systems unless expressly stated in writing.

Vox AV is not responsible for failures, compatibility issues, or performance limitations arising from pre-existing equipment, infrastructure, or conditions outside the current scope of work. Any service required to diagnose or correct issues related to retained systems is not covered under warranty and will be billed at standard service rates.

Optional Service Agreement Support
Vox AV may offer aseparate Service Agreement providing expanded service response, preventative maintenance, and administrative assistance with manufacturer warranty claims.

Service Agreements are optional and governed by their own written terms.

Such agreements do not extend or increase manufacturer warranty coverage or duration.

Hardware-related support under any Service Agreement shallnot exceed the applicable manufacturer warranty period.

Service Agreements are not included unless expressly stated in writing.

Network Infrastructure & Responsibility
Vox AV may design, install, or configure network infrastructure in support of AV systems.

AV-Dedicated Networks
Networks installed and maintained by Vox AV are intendedsolely for AV system operation, control, monitoring, and communication.

These networks are not general-purpose IT networks, except where required for wireless AV control or communication.

Vox AV does not act as a managed service provider unless expressly stated in writing.

Vox AV warrants AV network configurationonly while Vox AV retains controlof the network equipment and configuration as delivered at commissioning.

Client-Managed, Third-Party, or External Networks
When AV systems rely on
Client-managed networks,
Third-party IT providers,
External systems or services, includinginternet connectivity, Vox AV is not responsible for AV system issues caused by outages, configuration changes, firmware updates, security policies, bandwidth limitations, or third-party services. Such issues are excluded from warranty coverage.

Network Access Requirements
Where required for system configuration, commissioning, monitoring, updates, licensing, or support, theclient is responsible for providing The Route 66 Centennial
Monument Project
DATE:July 7, 2026
QUOTE NUMBER: P-1165
PROJECT NAME: CA-San Dimas-City of San Dimas-Route 66
Centennial Monument

Page 4 of 8 ends
Page 513 ends

Vox AV with timely access to:

Internet connectivity, and/or
The client’s internal network infrastructure
Delays in providing required network or internet access may:

Delay system commissioning or completion
Prevent remote configuration or testing
Result in remobilization, return visits, or additional labor charges Any additional costs resulting from delayed or unavailable network access are not covered under warranty and will be billed at standard service rates.

Network-Related Service & Support
Network-related issues are covered under warranty only when Vox AV supplied, configured, and retains control of the network environment. Issues arising from third-party control, client-managed infrastructure, or external dependencies are billable at standard service rates.

Warranty Exclusions
This warranty does not cover damage or failures resulting from:

Acts of God (fire, flood, lightning, power surges, water intrusion, etc.) Vandalism, theft, or loss of equipment
Improper or unauthorized operation or configuration changes Firmware or software updates for systems not network-connected Modifications or repairs by parties other than Vox AV
Normal wear or cosmetic damage
Project Timeline, Installation Assumptions & Client Responsibilities Project Timeline & Scheduling
Engineering begins upon signed contract.

Procurement and staging begin only aftercleared receipt of payment.

Delays caused by payment issues, site access restrictions, approval delays, construction delays, or scope changes will result in corresponding schedule extensions.

Typical project timelines range from2–8 weeks, depending on scope and equipment availability.

Installation Scheduling Assumptions
Project labor and installation pricing are based on the assumption ofconsecutive installation days, scheduled and directed by Vox AV, to allow for efficient use of labor and resources.

If installation progress is interrupted due to:

Client-imposed scheduling limitations
Construction delays or incomplete site readiness
Restricted access, limited working hours, or stop-start conditions Delays caused by other trades or third parties under client control Vox AV reserves the right to billadditional labor, remobilization, and return-trip costs at standard service rates. Such costs are not covered under warranty.

Client Site Access & Installation Requirements
The client is responsible for providing Vox AV withsafe, timely, and reasonable access to the project site, including:

The Route 66 Centennial
Monument Project
DATE:July 7, 2026
QUOTE NUMBER: P-1165
PROJECT NAME: CA-San Dimas-City of San Dimas-Route 66
Centennial Monument

Page 5 of 8 ends
Page 514 ends

2026 WARRANTY AND TERMS $0.00
SALES TAX $0.00
TOTAL +$0.00
Clear access for Vox AV personnel and fleet vehicles
Designated loading zones, docks, or service entrances where available Access to freight or service elevators as required
Parking and unloading locations within a reasonable distance of building entry points If paid parking is required,parking must be validated or reimbursed. Unvalidated parking will be billed to the client at cost.

The client shall ensure:

Work areas are accessible, safe, and free of obstructions Required building permissions, badges, escorts, or security access are arranged in advance Power, HVAC, lighting, and network services are available and operational when required Delays or inefficiencies caused by inadequate access or site readiness may result in additional charges and schedule extensions.

Supply Chain & Pricing Terms
Proposal pricing is valid through the stated expiration date.

Pricing may be adjusted due to vendor cost changes, tariffs, or global trade conditions.

Vox AV is not responsible for delays caused by supply chain disruptions or governmental actions.

Service & Support
Phone Support
Complimentary during standard business hours (Monday–Friday) After-hours support subject to availability
Onsite Response
Standard response within48 business hours
Same-day response for urgent issues reported before 3:00 PM Central Time, subject to availability Service Rates
The following rates apply to services not covered under warranty or outside an active Service Agreement:

Remote Support:
$150/hour — 1 hour minimum
Onsite Service Calls:
$350/hour — 2 hour minimum
Operational Support & Programming:
$275/hour — 2 hour minimum
Travel time, lift rentals, parking, permits, after-hours work, or extraordinary access requirements may be billed separately unless otherwise stated in writing.

Final Notes
This document represents the standard terms governing Vox Audio Visual projects unless otherwise modified in writing. No implied warranties or obligations exist beyond those expressly stated herein.

The Route 66 Centennial
Monument Project
DATE:July 7, 2026
QUOTE NUMBER: P-1165
PROJECT NAME: CA-San Dimas-City of San Dimas-Route 66
Centennial Monument

Page 6 of 8 ends
Page 515 ends

LONGEVITY ESTIMATES AND WARRANTY
HOW IT’S CONSTRUCTED
The Route 66 Centennial Monument is designed to last decades. Made of routed acrylic, inlaid steel and aluminum, each unit is carefully handcrafted to stand the test of time. Each metal piece is coated with a reflective UV-resistant automotive paint, pinned, riveted, and bolted to mating parts. The aesthetic facia and supporting lighting enclosure is attached to a steel superstructure. The interior is illuminated with long-lasting commercial-grade LED illumination. The monument is set into a concrete pier for support.

The entire monument is designed to withstand the impact of sustained winds up to 120 mph.

PROJECTED WEAR
As with any manmade object that is completely exposed to the outdoor elements, there will be some degradation over time. Paint is estimated to last without the beginning of fade for eight years and LED illumination may require occasional replacement of power supplies depending on the quality of power over time. The entire unit is estimated to last for 30-years before it is recommended to remove the monument for disassembly for shop-level refurbishment. A threaded eyelet connection at the very top of the monument allows the illumination chamber to be easily removed from the supporting mast for quick and easy maintenance or warranty repairs.

The illumination chamber is designed to be easily access the lighting equipment should any onsite lighting maintenance be required.

WARRANTY
The Route 66 Centennial Monument is warrantied for 5-years for any structural or mechanical failures resulting from a failure of workmanship during the fabrication or installation process. We believe this is an adequate period of time in which any substandard issues accidentally occurring can be resolved and meaningfully remedied without escalating the costs for each monument.

The 5-year warranty begins on the date of the completion of erecting the monument. Any issue arising from a product failure should be reported immediately to the Route 66 Centennial Monument Project Office.

EXCLUSIONS
Vox Industries LLC does not cover Route 66 Centennial Monument lighting failure as the result of power surges, dirty power, lightning damage, or other acts beyond the control of Vox Industries LLC. Vandalism, theft, vehicular impact, intentional harm, unintentional physical harm, and other degradation caused to the monument is not covered under warranty. Damaged caused by wind blown debris at any mph is not covered under warranty. Wind damage caused by winds or air turbulence sustained or unsustained above 120mph is not covered under warranty. The Route 66 Centennial Monument is not warrantied for lighting damage caused by direct or indirect contact with lightning. The Route 66 Centennial Monument is not warranted for flood or severe water damage resulting from the immersion of the lighting chamber. The Route 66 Centennial Monument is not warrantied for damage caused by earthquakes and earthen seismic ground shifts including but not limited to such event causing the unit to permanently tilt or collapse. The Route 66 Centennial Monument is not warrantied for damage caused by the improper connection to electricity by others for illumination. Vox Industries LLC does not cover issues related to the installation of the Route 66 Monument if the installation is performed by contractors or others not directly engaged by Vox Industries LLC.

Upon receiving notice of a warranty issue, The Route 66 Centennial Monument Project Office Staff shall vet the severity of the reported issue, determine if it poses a safety issue to the public, make recommendations to the customer, and initiate a warranty solution according to their judgement as to the best resolution.

RECOMMENDATIONS
The Route 66 Centennial Monument Project and Vox Industries LLC recommend that the monument be connected to the electricity by a licensed electrician and that all local, state, and federal rules, mandates, and building codes be followed according to the law.

Electrical connections are recommended to be connected to a GFCI (Ground Fault Circuit Interrupter) to protect against electrical shock in the event of a device or wiring failure.

The Route 66 Centennial
Monument Project
DATE: July 7, 2026
DESCRIPTION: CA-San Dimas-City of San Dimas-Route
66 Centennial Monument
QUOTE NUMBER: P-1165

Page 7 of 8 ends
Page 516 ends

PAYMENT SCHEDULE
50% Equipment Fees Deposit Due upon Signing
Ensures product is ordered to avoid price
changes due to market volatility
Product must arrive in full and be received
before installation will be scheduled
Product will be warehoused and staged until
installation begins
50% Labor Fees Due upon physical installation
completion
Any Change Orders approved after contract signing
will be billed at 100% of all equipment, labor, and
programming upon signing.

EQUIPMENT TOTAL $37,500.00
SHIPPING TOTAL $0.00
ENGINEERING $0.00
INSTALLATION $0.00
MANAGEMENT $0.00
PROGRAMMING $0.00
LABOR TOTAL $0.00
SUBTOTAL $37,500.00
TOTAL SALES TAX $0.00
PROJECT TOTAL $37,500.00

SIGNED DATE

PRINT NAME TITLE

SIGNED DATE

PRINT NAME TITLE

ACCEPTANCE

FINANCIAL
TERMS
I accept this proposal and hereby authorize The Route 66 Centennial Monument Project to proceed with the installation of the included systems at the facilities of City of San Dimas constructing at 245 East Bonita Avenue SAN DIMAS, CA 91773 as described in the totality of this document. I further authorize The Route 66 Centennial Monument Project to be granted the facility access that will be required to complete this project in a workmanlike and timely manner and for payment to be made to The Route 66 Centennial Monument Project. In keeping with the Terms of Payment listed above: It has been made clear to me that there exist no understandings regarding this project with any relevant party unless and until City of San Dimas and The Route 66 Centennial Monument Project agree to such additional or alternate understandings in writing. Project cost and pricing are dependent upon a continual flow of work without interruption or delays imposed by City of San Dimas or their staff, construction, other building trades or any other party, and additional costs may be incurred by City of San Dimas from The Route 66 Centennial Monument Project. If such delays result in additional costs that are not covered by the pricing in this proposal: I agree that any additions to and/or deletions from the materials and labor to be provided by my acceptance of this proposal and any resulting change(s) in cost of this project shall only be by way of written change order(s) and shall be valid only after being signed by City of San Dimas and The Route 66 Centennial Monument Project.

ACCEPTANCE

CITY OF SAN DIMAS
THE ROUTE 66 CENTENNIAL MONUMENT PROJECT
The Route 66 Centennial
Monument Project
DATE: July 7, 2026
DESCRIPTION: CA-San Dimas-City of San Dimas-Route
66 Centennial Monument
QUOTE NUMBER: P-1165

Page 8 of 8 ends
Page 517 ends

CITY OF SAN DIMAS
City Council Special Meeting
November 9, 2026
Route 66 Centennial
Monument Sign Project
ATTACHMENT 2

Page 518 ends

CITY OF SAN DIMAS
Tity of
SAN
DIMAS
Background California
1960
Regional participation
37 Azusa
Installed Foothill Blvd & Alameda Ave
matching signs dedicated along Route
66, Chicago to Santa Monica Claremont Installed Indian Hill Blvd and Foothill Blvd Centennial: November 11, 2026 First sign Nov 2026; committed to Upland Committed
a second sign
National program led by VOX
Industries LLC
• Interactive sign with QR code to a Site constraint: Foothill Blvd right-of-way extends only ~8 ft travel-guide page from the curb, too narrow for a sign plus a safe photo area. The sign would have to be placed on private property with the owner's permission.

Centennial Monument Project Page 519 - 524

CITY OF SAN DIMAS
Location Selection

Page 520 ends

ROUTE
6°6 THE ROUTE 66 CENTENNIAL

MONUMENT PROJECT

SAN DIMAS
route6ómonuments.com
San Dimas, CA

PROPOSED

LOCATION
E Foothill Bivd
N Walnut Ave
STOP
764
E Foothill Bivd E Foothill Bivd
E Foothill Bird
E Foothill Bivd

Page 521 ends

San Dimas, CA

SAN DIMAS
CA

Page 522 ends

CITY OF SAN DIMAS
Project Cost

Page 523 ends

CITY OF SAN DIMAS
Recommendation
•Discuss and provide direction to staff on the Route 66 Centennial Monument Sign Project and a location for
the sign; and
• Approve a budget appropriation of $37,500 for the
sign and $22,500 for electrical service and site
preparation work, for a total of $60,000.

Page 524 ends