2018

INTEGRATED RESOURCE PLAN
Anaheim Public Utilities

2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 1 ends

TABLE  OF CONTENTS

Table of Contents .......................................................................................................................................................... 1 Table of Graphs .............................................................................................................................................................. 4 Table of Tables ............................................................................................................................................................... 7 I. Executive Summary .................................................................................................................................................... 8 II. APU Fact Sheet ........................................................................................................................................................ 21 III. Planning Goals ........................................................................................................................................................ 22 A. Sustainable Resources ......................................................................................................................................... 22 B. High Reliability ..................................................................................................................................................... 23 C. Affordable Rates .................................................................................................................................................. 25 IV. Key Policy Drivers Affecting the Utility ................................................................................................................... 26 A. Reducing Greenhouse Gas (GHG) Emissions ....................................................................................................... 27 B. Increasing Procurement for Renewable Resources ............................................................................................. 28 C. Transformation of the Regional Grid ................................................................................................................... 29 V. Renewable Energy Procurement Plan and Enforcement Program ......................................................................... 30 A. Elements of the RPS Program .............................................................................................................................. 30 B. Planning and Procurement .................................................................................................................................. 32 C. Status of APU’s RPS Portfolio............................................................................................................................... 34 D. Potential Compliance Delays ............................................................................................................................... 35 E. Cost Limitations ................................................................................................................................................... 36 F. Enforcement Program .......................................................................................................................................... 39 VI. Energy Demand and Peak Forecasts ...................................................................................................................... 41 A. Energy Demand Forecast ‐ Methodology & Assumptions ................................................................................... 43 B. Peak Forecast ‐ Methodology & Assumptions ..................................................................................................... 53 VII. Resource Portfolio Evaluation ............................................................................................................................... 60 A. Portfolio Consideration and Performance Measures .......................................................................................... 62 B. Resource Options ................................................................................................................................................ 69 C. Model Analysis – Production Cost Model ............................................................................................................ 75 D. Model Analysis – Input Assumptions .................................................................................................................. 78 E. Model Analysis – Output Evaluation .................................................................................................................... 81 F. Stress Testing ....................................................................................................................................................... 89 G. Optimum Portfolio Recommendation ................................................................................................................. 95 H. Rate Impact ....................................................................................................................................................... 100 2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 2 ends

VIII. Reliability & Electric System Overview ............................................................................................................... 106 A. APU Electric System Overview .......................................................................................................................... 107 B. Generation and Transmission Resources .......................................................................................................... 108 C. CAISO Resource Adequacy Requirements ......................................................................................................... 116 D. Distribution System Overview ........................................................................................................................... 120 IX. Greenhouse Gas Emission Reduction ................................................................................................................... 128 X. Transportation Electrification ................................................................................................................................ 134 A. Quantification,  Characterization,  and Location ............................................................................................ 134 B. Transportation  Electrification  Programs ....................................................................................................... 136 C. Prioritization  and Funding Leverage .............................................................................................................. 141 D. Education and Outreach Plans ....................................................................................................................... 143 E. Alignment with State Policy and Local Needs ............................................................................................... 144 XI. Solar and Other Distributed Generation .............................................................................................................. 149 A. Customer Owned Solar PV .............................................................................................................................. 149 B. Solar for Schools .............................................................................................................................................. 151 C. Solar Power Program ....................................................................................................................................... 152 D. Anaheim Solar Energy Plant at the Convention Center ............................................................................... 152 F. Non‐Solar Distributed  Generation .................................................................................................................. 153 XII. Energy Efficiency and Demand Response Programs ........................................................................................... 155 A. Program History ............................................................................................................................................... 155 B. Target Setting ................................................................................................................................................... 155 C. Program Highlights  .......................................................................................................................................... 156 D. Existing Programs ............................................................................................................................................ 158 E. Challenges and Future Program Development  ............................................................................................. 161 F. Demand Response Programs ............................................................................................................................. 163 XIII. Programs for the Low Income and Disadvantaged Communities ...................................................................... 165 A. Definition of Low Income and Disadvantaged Communities ............................................................................ 165 B. Interdepartmental Strategies ............................................................................................................................ 166 C. APU Strategies ................................................................................................................................................... 169 Appendix A – Renewable Procurement Plan ............................................................................................................. 171 Appendix B – Public Engagement .............................................................................................................................. 172 A. Customer Survey Summary ............................................................................................................................... 172 B. Customer Survey Types ..................................................................................................................................... 172 C. Total Surveys Collected...................................................................................................................................... 173 D. Survey Topics and Summary Results ................................................................................................................. 175 2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 3 ends

E. Residential Analysis by Income Level ................................................................................................................. 184 F. Other Survey Results .......................................................................................................................................... 186 Appendix C – Portfolio Evaluation Details ................................................................................................................. 187 A. RPS and GHG Compliance .................................................................................................................................. 187 B. Regulatory Risk .................................................................................................................................................. 190 C. Resource Adequacy ........................................................................................................................................... 192 D. Portfolio Diversification ..................................................................................................................................... 196 E. Expected Cost .................................................................................................................................................... 197 F. Managed Market Risk ........................................................................................................................................ 198 Appendix D – Acronyms and Definitions ................................................................................................................... 200

2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 4 ends

TABLE  OF GRAPHS

Graph 1: APU GHG Reduction Targets ........................................................................................................ 28 Graph 2: Cumulative Adjustments to Base Load Forecast .......................................................................... 42 Graph 3: Anaheim Actual Energy Demand 2001 ‐ 2016 ............................................................................. 43 Graph 4: Historical and Base Energy Demand Forecast by Month ............................................................. 45 Graph 5: Estimated Electric Vehicle Energy Demand Growth .................................................................... 47 Graph 6: Estimated Behind‐the‐Meter Solar PV Impact to Energy Demand .............................................. 48 Graph 7: Adjusted Base Energy Demand Forecast ..................................................................................... 50 Graph 8: APU vs. IEPR Energy Demand Forecast ........................................................................................ 50 Graph 9: Cal‐Adapt vs APU Maximum Temperature Forecast ................................................................... 51 Graph 10: Forecasted Energy Demand with Extreme Temperatures ......................................................... 52 Graph 11: APU Historical Peak Demand ..................................................................................................... 53 Graph 12: Estimated Distributed (Behind‐the‐Meter) Solar PV Capacity ................................................... 54 Graph 13: Average Hourly Solar Profile by Month: Anaheim Convention Center...................................... 55 Graph 14: Estimated Distributed (Behind‐the‐Meter) Solar PV Impact to Energy Demand ...................... 56 Graph 15: Estimated Average Hourly Shape for Distributed Solar Generation .......................................... 56 Graph 16: Peak Demand Shift ..................................................................................................................... 57 Graph 17: Estimated Annual Peak Demand ................................................................................................ 57 Graph 18: Renewables Serving Peak Demand – Day with High Renewables & Low Energy Demand ....... 58 Graph 19: Renewables Serving Peak Demand – Day with Low Renewables & High Energy Demand ....... 59 Graph 20: Forecasted Peak demand with Extreme Temperatures ............................................................ 59 Graph 21: Selection Process of the Optimum Resource Portfolio .............................................................. 61 Graph 22: APU Resource Stack in 2006 ...................................................................................................... 62 Graph 23: APU Resource Stack in 2016 ...................................................................................................... 63 Graph 24: Historical and Planned Renewable Energy ................................................................................ 64 Graph 25: Planned GHG Reduction ............................................................................................................. 65 Graph 26: Available Resource Adequacy (RA) System Capacity ................................................................. 66 Graph 27: IPP Replacement Options ........................................................................................................... 69 Graph 28: New Power Supply Options – Cost Comparison ........................................................................ 70 Graph 29: Simulated RPS Compliance Requirement .................................................................................. 71 Graph 30: System Diagram ......................................................................................................................... 77 Graph 31: Average Annual SP‐15 Energy Price ........................................................................................... 78 Graph 32: CAISO Interconnection Projects ................................................................................................. 79 Graph 33: Candidate Portfolio Results: RPS Compliance ............................................................................ 81 Graph 34: Candidate Portfolio Results: Forecasted GHG Reduction .......................................................... 82 Graph 35: Candidate Portfolio Results: System Capacity Shortfall ............................................................. 83 Graph 36: Local Capacity Resources and LCR Requirement ....................................................................... 84 Graph 37: CAISO Flexible Capacity Requirement ........................................................................................ 84 Graph 38: Candidate Portfolio Results: Portfolio Diversity in 2030 ........................................................... 85 Graph 39: Candidate Portfolio Results: Net Power Supply Cost ................................................................. 86 2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 5 ends

Graph 40: Candidate Portfolio Results: Wholesale Energy Purchase as a % of Total Energy Portfolio ...... 87 Graph 41: Stressed Gas Prices .................................................................................................................... 89 Graph 42: Stressed Carbon Prices ............................................................................................................... 90 Graph 43: Stressed Utility Scale Solar Capacity Growth ............................................................................. 90 Graph 44: Stressed System Load Growth or Reduction (GWh) .................................................................. 91 Graph 45: Stress Test Results: Extreme High Costs vs. Extreme Low Costs ............................................... 93 Graph 46: Stress Test Results: Extreme High Demand vs. Extreme Low Demand ..................................... 93 Graph 47: Variable Portfolio Meets or Exceeds Compliance Targets ......................................................... 95 Graph 48: Variable Portfolio Forecasted Resource Adequacy .................................................................... 96 Graph 49: Resource Mix for Retail Energy Demand: 2018 vs. 2030 ........................................................... 97 Graph 50: Variable Portfolio Power Supply Cost Structure ........................................................................ 98 Graph 51: Comparison of Monthly Residential Electric Bills .................................................................... 101 Graph 52: Rate Comparison ...................................................................................................................... 104 Graph 53: Total Residential Customer Monthly Bill ................................................................................. 104 Graph 54: Commercial Customer Monthly Bill ......................................................................................... 105 Graph 55: Customer Class Data ................................................................................................................ 107 Graph 56: CAISO “Duck Curve” ‐ Impacts of Variable Energy Resources ................................................. 118 Graph 57: Anaheim’s Reliability Performance in Terms of SAIDI, SAIFI, and CAIDI Since 1990 ............... 124 Graph 58: APU at the Top Quartile of Utilities Nationwide for Reliability ............................................... 125 Graph 59: Basic Characteristics of Smart Grid .......................................................................................... 126 Graph 60: Advanced Metering Infrastructure .......................................................................................... 127 Graph 61: 2015 GHG Emissions by Sector ................................................................................................ 128 Graph 62: GHG Intensity of Electricity12 ................................................................................................... 128 Graph 63: APU GHG Reduction Targets .................................................................................................... 130 Graph 64: Emission Reductions Resulting from Transportation Electrification ....................................... 131 Graph 65: APU GHG Emission for System Energy Demand ...................................................................... 133 Graph 66: EV Charging Stations within APU Service Territory .................................................................. 135 Graph 67: IRP Customer Survey Result: % Renters vs. Home Owners Who Own, Lease or Anticipate Acquiring an EV within the Next Three Years ........................................................................................... 137 Graph 68: Cumulative Solar Capacity Installed ‐ Customer Owned Solar Systems .................................. 150 Graph 69: Map of SB 1 Residential Solar Rebate and Solar for School Sites ............................................ 150 Graph 70: Annual kWh Savings Targets .................................................................................................... 155 Graph 71: Cumulative Energy Efficiency Saving Goals with CEC Adjustments ......................................... 156 Graph 72: FY 16/17 Residential Program Energy Savings ......................................................................... 160 Graph 73: FY 16/17 Commercial Program Energy Savings ....................................................................... 161 Graph 74: Map of APU’s Low Income and Disadvantaged Communities ................................................. 165 Graph 75: Map of Home Utility Checkup by Dollar Spent 2016‐2017 ...................................................... 169 Graph 76: Residential Customer Satisfaction Rating: APU vs. CMUA ....................................................... 175 Graph 77: Business Customer Satisfaction Rating: APU vs. CMUA ........................................................... 176 Graph 78: Customer Survey – Support of Renewable Energy .................................................................. 176 Graph 79: Customer Survey – Support of IRP Approach .......................................................................... 177 Graph 80: Customer Survey – Support of Over 50% RPS with Potential Rate Increase ........................... 178 2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 6 ends

Graph 81: Customer Survey – Residential Controlled Group on Potential Bill Increase Due To Over 50% RPS ............................................................................................................................................................ 178 Graph 82: Customer Survey – Air Quality Ratings .................................................................................... 179 Graph 83: Customer Survey – Solar and Distributed Generation Ownership % ...................................... 180 Graph 84: Customer Survey – Residential and Small‐to‐Medium Businesses Interest in Community Solar .................................................................................................................................................................. 181 Graph 85: Customer Survey – Residential Interest in Community Solar Breakdown ............................... 181 Graph 86: Customer Survey – Current and Planned EV Ownership ......................................................... 182 Graph 87: Customer Survey – Large Business Current and Planned EV Ownership Breakdown ............. 182 Graph 88: Customer Survey – Residential Controlled Group on Impact of Rebate vs. Public Charging Accessibility on EV Ownership .................................................................................................................. 183 Graph 89: Customer Survey – Energy Efficiency Participation and Satisfaction Rating ........................... 183 Graph 90: Customer Survey – Large Business Customers Demand Response Potential .......................... 184

2018 Integrated Resource Plan
Table of Contents

Anaheim Public Utilities

Page 7 ends

TABLE  OF TABLES

Table 1: Temperature Summary ................................................................................................................. 44 Table 2: APU Energy Efficiency Targets including Codes & Standards (Navigant Study) ............................ 48 Table 3: Historical Load Factors (as of December 2017) ............................................................................ 54 Table 4: Renewable Capacity Required to Meet RPS Target ...................................................................... 72 Table 5: New Resource Capacity by Candidate Portfolio ............................................................................ 79 Table 6: System Capacity Purchases Cost ................................................................................................... 83 Table 7: Anaheim EVs and Emission Savings per Vehicle ......................................................................... 131 Table 8: Types of Customer Surveys and Number of Surveys Collected .................................................. 173 Table 9: High School Student Events and Number of Surveys Collected .................................................. 174 Table 10: Customer Survey – Residential and Small‐to‐Med Businesses Open Group on Potential Bill Increase Due To Over 50% RPS ................................................................................................................. 179 Table 11: Customer Survey – Air Quality Rating by Renters vs. Homeowners ......................................... 185 Table 12: Customer Survey – Residential Controlled Group Survey Results by Income Categories ........ 185 2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 8 ends

I. EXECUTIVE  SUMMARY
Introduction
Anaheim  Public  Utilities  (APU)  operates  a
consumer‐owned  vertically  integrated  electric
utility,  which  has  the  privilege  and  obligation  to reliably  serve  electricity  customers  located  within its 50 square mile service territory. As such, APU is
responsible  for  planning  adequate  power
generation  resources  to  reliably  meet  customer
demand  for  electricity  after  making  adjustments
for i) customer energy efficiency savings, ii) added
energy demand from electric vehicles (EV), and iii)
reductions  from  customer‐owned  power
generation  (e.g.  roof‐top  solar),  all  while
considering sustainability policy goals which call for
reductions in greenhouse gas (GHG) emissions. As a
not‐for‐profit utility, APU also considers the impact
of resource additions on customer rates. The following graphic shows how APU balances adjustments to customer energy demand and sustainability goals to develop an integrated resource plan (IRP).

The  IRP  serves  as  a  long‐term  comprehensive  roadmap  to  continue  APU’s  long  standing  focus  on customers  by  balancing  the  demand  and  supply‐side  factors  of  the  electric  utility.  The  IRP  provides  a framework showing how APU will transition away from carbon intensive resources such as coal, to clean renewable  resources  such  as  wind,  geothermal,  biogas,  small  hydro  and  solar.  This  aligns  with  APU’s GHG emission reduction targets and is in accordance with the State’s policy goals required by Senate Bill (SB) 350, including the requirement to establish an IRP by January 1, 2019.

The IRP process commenced in early 2017 with customer outreach efforts, which played an important role in APU’s selection herein of the optimum power generation resource mix to reliably serve customer demand while meeting the goals established in the IRP. Customer feedback indicated broad support for APU is responsible for planning adequate
power generation resources to reliably
meet customer demand for electricity after
making adjustments for i) customer energy
efficiency savings, ii) added energy demand
from electric vehicles (EV), and iii)
reductions from customer‐owned power
generation (e.g. roof‐top solar), all while
considering sustainability policy goals
which call for reductions in greenhouse gas
(GHG) emissions.

APU is responsible for planning adequate
power generation resources to reliably
meet customer demand for electricity after
making adjustments for i) customer energy
efficiency savings, ii) added energy demand
from electric vehicles (EV), and iii)
reductions from customer‐owned power
generation (e.g. roof‐top solar), all while
considering sustainability policy goals
which call for reductions in greenhouse gas
(GHG) emissions.

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 9 ends

APU’s responsible transition away from carbon intensive energy resources to an increased procurement of renewable energy resources supplemented by cleaner burning resources.

Assessment of Customer Energy Demand
APU  uses  a  statistical  model  to  forecast  a  baseline  customer  energy  demand,  which  is  adjusted  up  or down  based  on  i)  planned  customer  additions,  ii)  expected  electric  vehicle  usage,  iii)  estimated customer‐owned  rooftop  solar  installations,  and  iv)  expected  customer  energy  efficiency  reductions.

Based on the results of this modeling, APU expects a cumulative reduction in customer energy demand of 0.86 percent between 2018 and 2030, which is effectively a zero‐growth energy demand forecast. In summary,  this  zero‐growth  forecast  is  primarily  the  result  of  simultaneous,  opposing  dynamics  of  i) expected  system  expansion  and  EV  growth  that  increase  energy  demand  being  offset  by  ii)  customer solar  installation  and  energy  efficiency  reductions  that  reduce  energy  demand.  The  following  graphic shows the various additions and subtractions to the baseline energy demand forecast.

Transition to Clean Energy Resources
In  planning  to  serve  the  customer  energy  demand  forecast  established  above,  APU  must  consider  its existing power generation resource mix and plan the resource changes necessary to meet its reliability and sustainability goals outlined in the IRP. Although APU’s current resource mix is adequate to reliably serve the zero‐growth energy demand forecast, it currently includes a significant amount of coal energy.

APU recognizes the importance of having reliable, sustainable, and cost‐effective electricity supplies to drive the regional economy, support residents, businesses, schools and visitors, as well as protecting the local environment. Carbon dioxide is the primary GHG associated with electricity generation.   APU has been  steadily  transforming  its  electric  power  supply  portfolio  since  2003  through  increased procurement of renewable resources and accelerating the exit of coal ownership agreements and other contractual obligations.

At the end of 2017, APU fully divested of its ownership interest in the San Juan Generating Station (San Juan), a coal‐fired generating plant located in New Mexico. Once APU’s exit of the Intermountain Power Base Energy Demand Forecast
+ Energy Demand Addition
•System Expansion
•EV Penetration
‐ Energy Demand Reduction
•Solar Installation
•Energy Efficiency
= Adjusted Energy Demand
Forecast
(120)
(70)
(20)
30 80GWh
GWh
Cumulative Adjustments to Base Energy
Demand Forecast (2018‐2030)
Energy Efficiency
Solar PV
EV Adoption
Planned Expansion
Cumulative Impact on Energy Demand
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 10 ends

Project (IPP) contract in mid‐2027 is complete, its power supply portfolio will be 100 percent free of coal resources.  Transitioning  away  from  coal  resources  and  replacing  them  with  clean  renewable  energy resources ultimately proved to be the optimum resource portfolio, as further described in Section VII of this IRP.

These  renewable  energy  resource
additions,  along  with  APU’s  support  for
accelerating  transportation  electrification,
will  reduce  APU’s  GHG  emissions  by  more
than  70%  below  1990  emission  levels  by
the  year  2030;  significantly  exceeding  the
State’s  overall  target  of  40%  below  1990
emission levels by 2030.

APU’s Current Power Resource Mix
APU’s current power resource portfolio consists of a diverse mix of generation resources, which provide high reliability, stable prices, and is comprised of roughly 30% renewable energy resources. The diversity also protects APU’s customers from contingencies such as fuel unavailability, fuel price fluctuations and changes in energy policies that can drive up the cost of a particular fuel.

Renewable Energy Resource Procurement Plan
On February 28, 2017, the City Council approved APU’s latest renewable energy resource procurement and  enforcement  plans,  which  expanded  the  procurement  of  renewable  energy  resources  to  serve Anaheim electric customers from 33% to 50% renewable energy by 2030, consistent with the mandates of  SB  350.   SB  350  also  requires  that  utilities  incorporate  current  renewable  energy  resource Renewable
29%
Coal
34%Large Hydro
2%
Natural Gas
28%
Purchases
7%
2018 RESOURCE MIX
Wind
24% Small
Hydro
2%
Solar
<1%Biogas
55%
Geothermal
18%
The divestiture from coal energy, along with the
support for accelerating transportation
electrification, will reduce APU’s GHG emissions by
more than 70% below 1990 emission levels by the
year 2030.

The divestiture from coal energy, along with the
support for accelerating transportation
electrification, will reduce APU’s GHG emissions by
more than 70% below 1990 emission levels by the
year 2030.
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 11 ends

procurement plan into IRPs going forward.  This IRP includes APU’s most recent update to its renewable energy  resource  procurement  plan,  which  is  in  accordance  with  the  50%  renewable  energy  by  2030 target previously approved by City Council. The following graphic shows the optimum renewable energy resource procurement plan that will serve as a target for compliance with the RPS required by State law by 2030.

The  IRP  also  updates  the  cost  limitation  methodology  used  to  prevent  a  disproportionate  impact  on customer  electric  rates  caused  by  a  significant  increase  in  costs  associated  with  the  procurement  of renewable energy resources.

The State’s RPS law permits the local governing board
of each Publicly Owned Utility (POU), such as APU, to
implement  a  cost  limitation  for  its  RPS  activities.  All versions of the RPS Policy previously approved by City
Council  included  a  cost  limitation  provision  for  the protection  of  APU  customers.  This  cost  limitation methodology is now outdated since it was based on a
2010  base  year  and  a  33%  RPS,  which  has  been
mandated by the State to increase to 50% by 2030. As
part of this IRP, APU is highlighting how it will procure new  renewable  energy  resources  in  a  manner  that
does  not  cause  an  increase  in  overall  power  supply costs  greater  than  $0.01  per  kilowatt‐hour  in  any  fiscal  year,  which  represents  a  10%  increase  over current power supply costs or approximately four times the expected rate of general inflation in a single year, and is considered to be an undue burden on customers.

Renewable
50%
Natural Gas
21%
Purchases
27%
Large Hydro
2%
2030 RESOURCE MIX
Wind
17%
Solar
15%
Biogas
52%
Geothermal
16%

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 12 ends

Balancing the Renewables Portfolio
APU’s renewable portion of its overall power resource mix consists mainly of baseload renewables such as  geothermal,  landfill  gas  and  biofuels.  These  baseload  resources  operate  continuously  around‐the‐ clock  and  are  not  dependent  on  favorable  weather  conditions  unlike  intermittent  resources  such  as wind  or  solar  power  generation.  The  consistency  and  reliability  that  comes  with  baseload  renewables has  historically  also  come  with  a  premium  price.  To  maintain  competitive  rates  for  APU  customers, Anaheim explored adding less expensive intermittent resources to balance its renewable portfolio in its plan to transition out of coal and procure from 30% to 50% renewable energy by 2050. The following graphics show the three resource portfolios analyzed prior to selecting the optimum resource portfolio and the overall resource mix planned to be reached by 2030:

A production cost modeling analysis was used to compare the overall power supply cost of APU’s existing resources plus any new resources considered for each portfolio. In addition to the expected  cost  of  each  portfolio  scenario,  the  following  five factors  were  also  considered  in  determining  the  optimum portfolio:  Compliance,  Regulatory  Risk,  Resource  Adequacy, Portfolio Diversification, and Financial  Exposure. The Variable Portfolio  outperformed  the  other  portfolios  under  both expected  conditions  and  stress  tested  conditions,  such  as extreme  heat,  extreme  carbon  pricing,  extreme  fuel  price volatility,  and  extreme  high  or  low  energy  efficiency,  solar penetration and electric vehicle penetration.

Under  the  recommended  Variable  Portfolio,  APU  will  achieve  a  diverse  and  low‐emission  resource portfolio that meets the RPS and GHG reduction goals, achieves resource adequacy and local reliability, and  maintains  affordable  electric  rates.  The  following  graphic  show  that  the  Variable  Portfolio  causes the lowest overall increase in power supply costs.

IPP Coal
Replacement
Variable Portfolio
(Optimum):
68% Baseload
32% Intermittent
Mixed Portfolio:
81% Baseload
19% Intermittent
Baseload Portfolio:
85% Baseload
15% Intermittent
Under the Variable Portfolio,
APU will achieve a diverse and
low‐emission resource portfolio
that meets RPS and GHG
reduction goals, achieves
resource adequacy and local
reliability, and maintains
affordable electric rates.

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 13 ends

*Net power supply costs excludes transmission and wholesale energy revenues APU’s  resource  portfolio  will  be  coal‐free  by  mid‐2027,  and  at  a  minimum,  50%  of  APU’s  electricity deliveries  will  come  from  renewable  energy  resources.  Based  on  current  law  and  draft  regulations, APU’s  optimum  resource  portfolio  under  this  IRP  will  achieve  the  upper  bound  of  the  proposed  GHG reduction target range (77% GHG reduction). However, the GHG reduction target for POUs is currently under  development  by  the  California  Air  Resources  Board  (CARB)  and  may  ultimately  be  77%  to  87% below  1990  levels  by  2030.  If  the  final  regulation  requires  that  APU  achieve  the  lower  bound  of  the target  range  (87%  GHG  reduction),  that  target  level  could  not  be  achieved  without  significant  cost impacts  to  APU  and  its  customers.  If  California  Air  Resources  Board  (CARB)  were  to  indeed  adopt  the more stringent 87% GHG reduction target it would require the shutdown, or “stranding,” of a reliable and  efficient  baseload  natural  gas  resource  Magnolia  Power  Plant,  which  has  20‐years  of  unavoidable debt  service  costs  that  would  still  need  to  be  paid  by  APU  customers  in  addition  to  replacement renewable  resources.  APU  is  closely  following  relevant  regulatory  proceedings  and  will  work  with  the CARB  and  CEC  to  recommend  methodologies  to  further  reduce  APU  carbon  emissions,  such  as accounting for the effect of electric vehicle (EV) penetration on emission reduction.

$245,000
$265,000
$285,000
$305,000
$325,000
$345,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Thousands
New Power Supply Options ‐ Cost Comparison
Variable Portfolio Mixed Portfolio
Baseload Portfolio New Natural Gas Plant
250
350
450
550
650
750
850
950
1,050
1,150
1,250
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MMT of CO2  (Thousands)
APU GHG Emission ‐ System Energy Demand
APU Emission APU Emission + EV Emission Reduction
APU GHG Emission Target Range
304,611 ‐ 538,146 MMT
(77% ‐ 87% lower than 1990 level)
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 14 ends

Projected Effect on Customer Rates
APU strives to find resources that are cost‐effective and minimize rate  impacts  on  customer  utility  bills,  while  still  meeting  its compliance obligations for increased renewables and lower GHG emissions. By responsibly divesting of its coal assets and utilizing its  peaking  resources  to  integrate  more  renewable  purchases, APU  has  been  able  to  maintain  affordable  electric  rates.  The following  graphic  shows  the  expected  net  power  supply  cost forecast  from  2019  through  2030  based  on  the  recommended Variable  Portfolio  and  the  expected  consumption  case.  Such  net power supply costs are expected to increase an average of 1.34% per year from 2019 to 2030, which is less than the expected rate of inflation over the same time period.

Given the large amount of reliable baseload renewable resources in APU’s portfolio, as compared to the small  amount  of  intermittent  solar  and  wind  resources,  the  cost  to  support  and  backup  intermittent renewable  resources  attributed  to  APU  by  the  California  Independent  System  Operator  (CAISO)  has remained relatively low to date. However, to mitigate future renewable integration costs, APU currently has plans to add a 1 MW energy storage pilot project by December 31, 2021 and an additional 10 MW of energy  storage  by  December  31,  2026,  if  the  pilot  project  proves  to  be  cost‐effective.  Energy  storage technologies  include  batteries  and  other  systems  that  are  able  to  store  power  for  later  use  in  a controlled manner.

$253 $291
‐$50
$0
$50
$100
$150
$200
$250
$300
$350Millions
Net Power Supply Cost 2019 ‐ 2030
Total Transmission Cost Scheduling Coordinator Costs Conventional Unit Fixed Costs Unit Variable Cost Unit Fuel Cost Debt Service Cost
Wholesale Purchase Cost Renewable Long Term PPA Cost Renewable Short Term PPA Cost Total Wholesale Revenue Total Transmission Revenue Total Net Cost Renewables & Storage $60M to $76M
Market Purchases $9M to $62M
Average 1.34%
annual increase
By responsibly divesting of its
coal assets and utilizing its
peaking resources to integrate
more renewable purchases,
APU has been able to maintain
affordable and competitive
electric rates.

Thermal $151M to $78M
Transmission and Scheduling
Services $76M to $97M
By responsibly divesting of its
coal assets and utilizing its
peaking resources to integrate
more renewable purchases,
APU has been able to maintain
affordable and competitive
electric rates.
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 15 ends

Local Reliability and Air Quality
Of  APU’s  approximate  700  MWs  of  generation  capacity,  240  MWs  are  located  within  the  City.  The Canyon  and  Kraemer  Power  Plants  provide  flexible  power  generation  capability,  known  as  resource adequacy capacity, near the Anaheim load center, including black‐start capability, which enhances local and  statewide  reliability.  The  power  plants  use  clean‐burning  natural  gas  fuel,  include  air  emission controls  to  further  reduce  air  pollutants  that  cause  smog,  have  much  lower  GHG  emissions  than  coal resources, and operate as flexible peaking units to support the morning and evening ramping needs of the power grid and backup fluctuations in solar output due to weather.

According to a recent APU customer survey, 95% of the respondents indicated that they have acceptable to  excellent  air  quality  near  their  home,  and  89%  of  the  respondents  indicate  the  air  quality  has improved  or  stayed  the  same  over  the  past  few  years.  These  respondents  mainly  attributed  any  air quality  concerns  to  traffic  and  emissions  from  mobile  sources,  and  none  attributed  it  to  APU’s  local power generation.

To  improve  local  air  quality  and  support  sustainability goals,  APU  facilitates  and  promotes  transportation electrification  through  electric  vehicle  time‐of‐use rates,  rebate  incentives  for  public  access  and  private use charging stations, and the electrification of utilities field services vehicles. APU also supports and facilitates the  installation  of  fast‐charging  infrastructure  to  be used  by  visitors  and  residents  without  home  charging facilities,  which  helps  to  remove  fossil  fueled  vehicles from the road and improves local air quality.

In  addition,  APU  supported  customer‐owned  solar
distributed  generation  by  fully  implementing  the
Senate Bill (SB) 1 solar initiative rebates. To date, over 28,000  totaling  26  MW  of  customer‐owned  solar
systems have been installed in Anaheim. APU continues
to  expand  clean  local  distributed  generation  through utility‐owned  solar  projects.  As  an  example,  APU  is installing  and  will  maintain  1.5 MW  solar  carports  and lunch  shelters  at  nine  public  schools  throughout
Anaheim  through  its  Solar  for  Schools  program,  and  is expected  to  continue  adding  solar  school  facilities  in future years.

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 16 ends

Programs for the Low Income and Disadvantaged Communities APU has a tradition of helping low income customers use energy efficiently to reduce their electric bills, and  APU  has  historically  provided  rate  discounts  to  income‐qualified  seniors,  military  veterans  and disabled customers. More recently, APU has implemented programs to address the needs of its income‐ qualified  customers  considering  that  the  2015  U.S.  Census  shows  that  nearly  58%  of  Anaheim households  are  under  the  low  income  designation.  Additionally,  APU  has  incorporated  programs  that assist “disadvantaged communities (DAC),” as defined by Senate Bill 535 (De León) and the most current version of CalEPA’s California Communities Environmental Health Screening Tool (“CalEnviroScreen”).

The CalEnviroScreen considers area pollution exposure levels in addition to income and unemployment levels to determine which areas are disadvantaged. However, APU programs serve expanded DAC areas, which  include  low  income  areas  defined  by  the  Department  of  Housing  and  Urban  Development  as Community  Development  Block  Grant  (CDBG)  areas.  The  following  map  illustrates  this  expanded  DAC area served by APU DAC programs:

To ensure energy efficiency, transportation electrification and renewable energy is accessible to the low income  and  disadvantaged  communities  (LI‐DACs),  APU  offers  program  incentives  and  works  closely with  other  City  departments  including  Planning
and  Building,  Public  Works,  Community  Services
and  Community  and  Economic  Development  to
service LI‐DAC customers. Some examples include:
 Offering  rebates  for  enhanced  energy
efficiency  and  publicly  accessible  EV  charging
stations  located  at  schools  and  Affordable
Housing  Developments.  The  public  access  EV
rebate  program  is  funded  by  proceeds  from  the
California  Low  Carbon  Fuel  Standard  (LCFS)
program.
 Actively  seeking  grant  opportunities  to
support  EV  charging  stations  and  shade  trees  for

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 17 ends

qualifying  commercial,  industrial,  and  residential  projects  and  multi‐family  developments  near freeways and within LI‐DACs.
 Transitioning to LED street lights and partnering with the Southern  California  Gas  Company  to  offer  no‐cost
weatherization services that are frequently located within LI‐DACs.
 Providing EV charging stations at park sites within LI‐DACs through grant funding opportunities.
 Providing  customer  education  and  outreach  on  energy efficiency  and  income‐qualified  programs  at  community meetings.
 Hosting community outreach events within LI‐DAC areas, specifically  promoting  sustainable  resources  and
conservation programs.
 Developing  an  income‐qualified  solar  discount  program that integrates with the Solar for Schools energy production to allow households to receive bill savings, where these customers may otherwise not be able to access solar benefits because they are living in multi‐family dwellings.

APU’s low income energy discount is offered to seniors, military veterans, and disabled customers who meet  specified  income  thresholds.  Low  Income  Home  Energy  Assistance  Program  (LIHEAP)  is  also available for customers needing additional bill assistance.

Data  analytics  is  utilized  to  maximize  LI‐DAC  residents’  participation  in  efficiency  programs.  As  an example, a significant majority of the customers who participate in the Home Utility Checkup Program are within LI‐DACs, as illustrated in the following map below. APU’s weatherization program is therefore enhanced through the Home Utility Checkup Program. Eligible customers applying for the Home Utility Checkup are also pre‐qualified for free weatherization installations.                                                                 x

2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 18 ends

APU’s  data  analytics  show  in  the  map  below  that  residential  solar  rebates  were  evenly  distributed throughout APU, which is partially attributed to the income‐qualified solar incentives offered at a higher rate. In addition, 8 out of the 9 Solar for School sites are located in LI‐DACs.

Customer Support of IRP Approach
The  Variable  Portfolio,  recommended  by  this  IRP  as  the optimum  portfolio,  is  also  closely  aligned  with  the preferences  of  APU  customers,  as  evidenced  by  a
customer survey conducted in late 2017.

As  a  customer‐owned  electric  utility,  APU  actively solicited  input  from  customers  and  received  responses from  approximately  1,200  residents  and  businesses
through  online  surveys,  phone  interviews,  and  outreach events.  Survey  respondents  overwhelmingly  expressed high  satisfaction  with  APU  services.  Customers  indicated that they are likely to contact APU for advice on solar and other distributed generation, and feel that APU will offer fair and balanced advice.

In 2016, California Municipal Utilities Association (CMUA) conducted a statewide customer satisfaction survey  that  reached  nearly  1,400  residential  customers.   In  comparison  to  the  CMUA  municipal customers surveyed, APU customers expressed a significantly higher overall customer satisfaction with APU services.

Customer Survey Quotes
“Good for the environment and our kids’
future!”
“Protect the planet.”
“As a community, we need to reduce
greenhouse gas emissions.”
“Reducing coal usage helps keeping air
pollution low.”
“Renewable energy is the future.”
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 19 ends

Customers  also  expressed  high  support  of  the  IRP  approach  to  eliminate  coal  resources  and  reach  a renewable energy target of 50% by 2030.

In  addition  to  the  customer  survey,  in  March  2018  APU  held  community  events  at  public  locations  in each  of  Anaheim’s  six  council  districts,  at  which  a  summary  of  the  IRP  was  presented,  including greenhouse  gas  reductions,  phasing‐out  of  coal  resources,  50%  renewable  portfolio  standard, transportation electrification, local solar projects, and energy efficiency.

Executive Oversight and Governing Board Approval
Executive Oversight
The IRP development is guided by an Executive Oversight group consisting of the following members:
o General Manager
o Assistant General Manager – Power Supply
o Assistant General Manager – Electric Services
o Assistant General Manager – Finance and Administration o Chief Risk Officer
During IRP development, quarterly meetings were held to discuss APU policy, guiding principles and key components of the IRP. Staff receives direction and support from the Executive Oversight group on all 55%
74%
0% 10% 20% 30% 40% 50% 60% 70% 80%
%
% of Very Satisfied Customers
2017 APU Residential
2016 CMUA Residential
65% 54%
82%

8.1 7.6

8.8 0.0

2.0 4.0

6.0 8.0

10.0 0%
20%
40%
60%
80%
100%
Residential Small ‐to‐Medium Businesses Large  Businesses Support of IRP Approach by Anaheim Customers
% of Very Supportive Customers (Scores 8‐10 in a Scale of 0‐10) Average Customer Score
2018 Integrated Resource Plan
I. Executive Summary

Anaheim Public Utilities

Page 20 ends

aspects of the IRP, particularly the cross‐departmental efforts such as transportation electrification and programs and resources targeted for the low income and disadvantaged communities.

Board and Council Approval
This  IRP  and  future  updates  will  be  presented  to  the  Public  Utilities  Board  for  their  consideration  and recommendation to the Anaheim City Council for approval.

The Public Utilities Board is made up of seven Anaheim residents who are appointed to staggered four‐ year  terms  by  members  of  the  Anaheim  City  Council.  Their  role  is  to  make  recommendations  to  the Anaheim City Council on utility matters, including:
o Annual capital and operating budgets
o Renewable energy resource options
o Sources of water and power supply
o Water and electric rates
o Water and energy conservation and efficiency incentives Following  the  Board's  recommendation  for  approval,  the  IRP  will  be  presented  to  the  Anaheim  City Council for approval and adoption.

2018 Integrated Resource Plan
II. APU Fact Sheet

Anaheim Public Utilities

Page 21 ends

Dukku Lee
Utilities General
Manager
Brian Beelner
Assistant General Manager
Finance & Administration
Janet Lonneker
Assistant General
Manager
Electric Services
Graham Bowen
Assistant General
Manager
Power Supply
Michael Moore
Assistant General
Manager
Water Services
Janis Lehman
Chief Risk Officer
II. APU FACT  SHEET

Local Ownership & Control
Anaheim  Public  Utilities  is  a  city‐owned,  not‐for‐profit  electric  and  water  utility  that  offers  quality  electric  and  water services to residents and businesses in Anaheim at rates among the lowest in California.

Anaheim citizens are more than utilities customers: they are owners of their utilities. They have input to the decision process  both  directly  and  through  an  appointed  citizen  advisory  Public  Utilities  Board.  With  final  authority  vested  in Anaheim's  elected  City  Council,  decisions  are  made  in  the  best  interest  of  our  citizens,  quality  of  life,  and  local economy. As a municipal, not‐for‐profit utilities, our rates are based on our costs of providing water and electricity. 1 Two Plants in Anaheim Service Area
2 One Plant in Anaheim Service Area
Electric Services Facts
Anaheim Public Utilities operates the only
municipal electric utility in Orange County,
delivering more than 3.7 million megawatt‐hours
to Anaheim's 350,000 residents and more than
15,000 businesses, including multi‐million dollar
tourism, sports and manufacturing customers.

Revenues & Expenditures
APU’s total electric utility revenue is more than
$458 million a year, and net investment in utility
plants is $880 million.

Power Use
Residential customers make up 85% of APU’s total
customer meter base; however, nearly 75% of total
load is consumed by commercial and industrial
customers.

Resource Adequacy
APU has over 700 megawatts (MW) of generation
capacity from various types of resources.  The
record peak customer demand of 593 megawatts
was reached on July 14, 2006.

Power Resources
3 natural gas plants (in‐state1)
1 coal plant (out‐of‐state)
1 large hydroelectric plant (out‐of‐state)
4 small hydroelectric plants (in‐state)
2 solar photovoltaic plants (in‐state2)
2 geothermal plants (1 out‐of‐state)
3 wind plants (1 out‐of‐state)
2 landfill gas plants (in‐state)
Distribution Infrastructure
Transmission, 220kV
 1.2 circuit miles
Sub‐Transmission, 69kV
 32.9 circuit miles of overhead
 57.2 circuit miles of underground
Distribution, 12kV and lower, circuit miles
 Overhead – 401 primary, 1,219 secondary
 Underground – 709 primary, 963
secondary
Transformer Capacity, KVA
 220kV to 69kV – 1,808,000
 69kV to 12kV – 1,157,800
 12kV to customer – 1,633,671

13 Substations
19,902 Streetlights
13,022 Distribution Transformers
2018 Integrated Resource Plan
III. Planning Goals

Anaheim Public Utilities

Page 22 ends

50% renewables by 2030
GHG reduction of 40% below
1990 levels by 2030
Cumulative doubling of energy
efficiency savings by 2030
Phase Out of Coal
III.  PLANNING  GOALS
APU’s mission is to be an agile, customer‐focused, water and power utility operating in an ever‐changing world providing reliable, high quality, environmentally sustainable, and competitively priced water and power  and  delivering  the  maximum  value  to  our  customer‐owners  in  order  to  preserve  Anaheim’s health  and  prosperity.  This  IRP  supports  this  mission  by  establishing  resource  planning  goals  of sustainable resources, high reliability, and affordable rates, including the following sub‐goals:

A. SUSTAINABLE  RESOURCES
For  more  than  two  decades  APU  has  been  a  leader  in i) helping its customers use energy wisely and efficiently and ii) transitioning to sustainable power resources such as wind, geothermal, biogas, small hydro, and solar. APU currently  serves  29%  of  its  customer  load  from
renewable  resources  and  in  2017  the  Anaheim  City Council  adopted  a  policy  for  APU  to  achieve  a  50% renewable portfolio standard by 2030, which are both in compliance with California policy goals.

In  2006,  Assembly  Bill  (AB)  32  established  a  statewide GHG  emissions  reduction  target  of  20%  below  1990 levels  by  2020.   This  goal  was  recently  expanded  by  the passage  of  Senate  Bill  (SB)  32,  which  established  a  statewide  GHG  emissions  reduction  target  of  40% below 1990 levels by 2030. To help achieve the State's GHG reduction goals, Governor Brown signed SB 350,  which  established  targets  for  all  California  electric  utilities,  including  APU,  to  increase  the  use  of renewable resources to serve customer load to 50% by 2030. SB 350 also set a goal to double electricity and natural gas energy efficiency savings statewide by 2030.

This  IRP  lays  out  a  plan  for  APU’s  resource  portfolio  to  achieve  Anaheim’s  sustainability  goals  and comply with all of California’s legislative and regulatory requirements, including the following:

Sustainable
Resources
• 50% RPS
• 40% GHG
Reduction
•L o w e s t
Regulatory Risk
High
Reliability
•R e s o u r c e
Adequacy
• Portfolio
Diversification
Affordable
Rates
•L o w e s t Expected
Cost
• Managed
Market Risk
2018 Integrated Resource Plan
III. Planning Goals

Anaheim Public Utilities

Page 23 ends

 Meet or exceed the following Renewables Portfolio
Standard  (RPS)  targets,  as  a  percentage  of  retail load:
 33% by December 31, 2020;
 40% by December 31, 2024;
 45% by December 31, 2027;
 50%  by  December  31,  2030,  and
each year thereafter.

 Meet  or  exceed  the  GHG  emissions  reduction
targets  established  by  the  California  Air  Resources Board (CARB) for electric utilities, which contribute
toward  a  statewide  GHG  emissions  reduction  goal
of 20% below 1990 levels by 2020, and 40% below
1990 levels by 2030. The GHG reduction target for
POUs  which  is  currently  under  development  by
CARB may ultimately be 77% to 87% below 1990 levels by 2030.

 Meet or exceed the energy efficiency targets established by the Anaheim City Council for APU electricity  customers,  which  contribute  toward  a  statewide  cumulative  doubling  of  energy efficiency  savings  in  the  electricity  and  natural  gas  sector  final  end  uses  by  2030.  The  energy efficiency target established for APU by City Council is currently a 1.1% reduction in electricity sales per year.

 Phase‐out of all APU coal resources by 2027.

These  sustainability  goals  and  reasonable  Regulatory  Risk  were  considered  in  the  development  of  the power  supply  scenarios  evaluated  under  this  IRP.  Regulatory  Risk  measures  the  ability  to  remain compliant  with  current  and  anticipated  future  legislative  or  regulatory  changes.  The  recommended optimum portfolio is expected to achieve all of these goals and be resilient to future regulatory risk.

B. HIGH  RELIABILITY
High  overall  electric  service  reliability  is  a  key  APU  goal  considered  in  the  development  of  this  IRP.

Overall  electric  service  reliability  is  comprised  of  i)  high  power  supply  reliability  and  ii)  high  electric distribution system reliability.

High  power  supply  reliability  is  measured  by  two  quantitative  portfolio  performance  measures:

Resource Adequacy and Portfolio Diversification.

1. Resource  Adequacy  is  measured  by  the  ability  to  achieve  an  additional  15%  capacity  over  the forecasted system peak demand, and to meet local and flexible capacity requirements.

Sustainable Resources
50% RPS is measured by percent of
renewable energy delivered to serve retail
load.
40% GHG Reduction is measured by
percent of GHG reduction of the total
generation portfolio.

Regulatory Risk measures the ability to
remain compliant with current and
anticipated future legislative or
regulatory changes.
2018 Integrated Resource Plan
III. Planning Goals

Anaheim Public Utilities

Page 24 ends

2. Portfolio  Diversification  is  measured  by  the  different  types  of  resources,  fuel  and  contract lengths within the portfolio, which increases flexibility, reliability, and operational performance of the overall portfolio.

While  the  power  supply  portfolio  scenarios  evaluated under  this  IRP  primarily  considered  power  supply
reliability  (versus  distribution  system  reliability),  the addition of customer‐owned distributed energy resources (DER),  such  as  rooftop  solar,  fuel  cells,  and  batteries,  the proliferation  of  electric  vehicle  charging  infrastructure, and  increased  energy  efficiency  measures  could  have  an effect  on  electric  distribution  system  reliability;  as  such, they  were  also  considered  and  addressed  under  various sections of this IRP. The recommended portfolio maintains high  power  supply  reliability  through  2030  and  beyond, and  the  expected  effect  of  the  aforementioned  demand‐ side  factors  were  determined  to  have  no  adverse  impact on  APU’s  high  electric  distribution  reliability  going forward.

More specifically regarding power supply reliability, APU operates within the supply/demand balancing area  of  the  California  Independent  System  Operator  (CAISO),  and  the  CAISO  is  within  the  Western Interconnection  of  the  United  States,  known  as  the  electric  “Grid.”  The  electric  Grid  interconnects thousands  of  power  generation  plants  across  the  14 western  states  and  parts  of  Canada  and  Mexico using a high voltage power transmission system, and all of these generators collectively serve customer electric demands. By participating in this interconnected Grid system, APU enjoys extremely high power supply  reliability  because  the  loss  of  any  single  generator  does  not  affect  the  delivery  of  electricity  to APU customers. There has not been a regional blackout affecting APU since August 1996, demonstrating that APU’s interconnection to the Grid serves its customers very well.

To maintain high reliability the CAISO and other Grid operators require load serving entities such as APU to  maintain  adequate  power  generation  capacity  beyond  that  required  to  serve  its  own  customers, which  is  known  as  a  “Resource  Adequacy”  requirement.  CAISO’s  current  Resource  Adequacy requirement  is  15%  of  forecasted  peak  load.  APU  employs  a  diversified  portfolio  of  power  generation resources to comply with its Resource Adequacy obligation, and maintaining a diversified and resilient Resource  Adequacy  portfolio  was  a  factor  in  the  evaluation  of  the  power  supply  scenarios  considered under this IRP.

In addition to maintaining Resource Adequacy to cover any unexpected losses of power generation, the CAISO and the other balancing authorities operating the Grid also adhere to reliability and cyber security standards  established  and  monitored  by  the  North  American  Reliability  Corporation  (NERC)  under  the auspices  of  the  Federal  Energy  Regulatory  Commission  (FERC).  APU  is  in  full  compliance  with  NERC reliability standards, and in 2014 passed an audit of all applicable NERC standards with no violations.

High Reliability
Resource Adequacy is measured by the
ability to achieve 15 percent above
system peak forecast, and to meet
forecasted local and flexible capacity
requirements.

Portfolio Diversification is measured
by the different types and length of
resource investment within the
portfolio.
2018 Integrated Resource Plan
III. Planning Goals

Anaheim Public Utilities

Page 25 ends

APU  adheres  to  the  CAISO  tariffs  and  Business  Process  Manuals  pertaining  to  the  Grid‐level  reliability requirements. The reliability requirements and Resource Adequacy programs provide performance and deliverability  criteria  for  generation  resources  required  for  each  load  serving  entity.  APU’s  resources fully comply with the system‐wide, local, and flexible Resource Adequacy requirements established by the  CAISO,  and  the  recommended  portfolio  is  expected  to  maintain  this  reliability  as  APU  phases  out coal resources and adds renewable resources to achieve a 50% RPS. Also, to improve system resiliency, a diversified  and  flexible  portfolio  is  considered  to  minimize  risks  of  unplanned  facility  outages accompanied with acquisition of resources with complementary generation profiles.

C. AFFORDABLE  RATES
As  a  customer‐owned  utility,  maintaining  affordable  electric  rates  is  a  key  APU  goal  considered  in  the development  of  this  IRP.  APU  has  consistently  maintained  electric  rates  that  are  lower  than  adjacent investor owned utilities, and the recommended portfolio is expected to help maintain affordable rates throughout the planning period.

Sections 205 and Section 206 of the Federal Power Act stipulate that “all rules and regulations affecting or  pertaining  to  such  [public  utility]  rates  or  charges  shall  be  just  and  reasonable.”  State  statute  also requires that the integrated resource plan “enable each electrical corporation to fulfill its obligation to serve its customers at just and reasonable rates.” In addition, Article XIII C of the California Constitution requires that electric rates do not exceed APU's reasonable cost to provide electricity to its customers.

The optimum (recommended) portfolio consists of a balanced mix of renewable resources and ensures high  reliability,  while  at  the  same  time  maintaining  affordable  rates.   APU’s  IRP  process  includes comprehensive production cost modeling to ensure the resource portfolio serving APU's customer load is met at the lowest possible cost.

The  long‐term  resource  planning  process  introduces  many assumptions and each of them may deviate from the original assumptions.  A modeling “stress test” is introduced to ensure the  optimal  portfolio  outperforms  the  alternatives  under  all scenarios.  In  addition,  the  portfolio  financial  exposure  is calculated to evaluate mitigating factors.

Achieving  affordable  rates  is  measured  by  two  quantitative portfolio  performance  measures:  Expected  Cost  and  Market Risk.  Lowest  expected  cost  is  measured  by  the  total  cost  to supply  power,  while  Market  Risk  is  measured  by  percentage of  energy  purchased  from  the  wholesale  market,  and  the portfolio’s  ability  to  withstand  market  price  volatility.

Affordable Rates
Expected Cost is measured by the
total cost to supply power.

Market Risk is measured by the
percentage of energy purchased
from the wholesale market, and the
portfolio’s ability to withstand
market price volatility.
2018 Integrated Resource Plan
IV. Key Policy Drivers Affecting the Utility

Anaheim Public Utilities

Page 26 ends

IV. KEY POLICY  DRIVERS  AFFECTING  THE UTILITY
California  is  considered  a  leader  in  its  many  efforts  to  combat  the  effects  of  climate  change.  The overarching  goal  of  the  State’s  climate  change  strategy  is  to  reduce  statewide  GHG  emissions  to  40% below 1990 levels by 2030.  To reach this goal, the State has put forward several key legislative actions over  the  past  several  years  that  have  a  direct  effect  on  how  APU  plans  for  and  manages  its  resource portfolio now and into the future. APU is committed to reducing GHG emissions by implementing not only  the  letter  of  state  laws  and  regulations,  but  also  their  spirit,  which  supports  Anaheim’s  goal  of  a more sustainable environment for future generations.  In doing so, APU’s long‐term strategies focus on striking a balance amongst numerous legislative and regulatory issues and challenges while maintaining affordable rates and reliable service for its customers.

The following table is a summary of the California laws passed since 2006 requiring electric utilities to reduce  GHG  emissions  and  increase  the  proportion  of  renewable  energy  in  their  power  supply portfolios:

Date Legislation Description
July 26, 2017 Assembly Bill 617 (Christina Garcia, Chapter 136, Statutes of 2017)
Companion to Cap-and-Trade
Establishes a groundbreaking program to measure and reduce air pollution from mobile and stationary sources at the nei ghborhood level in the communities most impacted by air pollutants. Requires the Air Resources Board to work closely with local air districts and communities to establish neighborhood air quality monitoring networks and to develop and implement plans to reduce emissions. The focus on community-based air monitoring and emission reductions will provide a national model for enhanced community protection.

July 25, 2017 Assembly Bill 398 (Eduardo Garcia, Chapter 135, Statutes of 2017)
Cap-and-Trade Extension
Extends and improves the Cap-and-Trade Pr ogram, which will enable the State to meet its 2030 emission reduction goals in the most cost-effective manner.

Furthermore, extending the Cap-and-Trade Program will provide billions of dollars in auction proceeds to invest in communities across California.

September 8, 2016 Assembly Bill 197 (Eduardo Garcia, Chapter 250, Statutes of 2016)
Greenhouse gas regulations
Prioritizes direct emission reductions from large stationary sources and mobile sources.

September 8, 2016 Senate Bill 32 (Pavley, Chapter 249, Statutes of 2016)
Greenhouse Gas emission reduction target for 2030
Establishes a statewide greenhouse gas (GHG ) emission reduction target of 40 percent below 1990 levels by 2030.

October 7, 2015
Senate Bill 350 (De León, Chapter 547,
Statutes of 2015)
Clean Energy and Pollution Reduction Act of 2015
Establishes targets to increase retail sales of renewable electricity to 50 percent by 2030 and double the energy efficiency savings in electricity and natural gas end 2018 Integrated Resource Plan
IV. Key Policy Drivers Affecting the Utility

Anaheim Public Utilities

Page 27 ends

uses by 2030.

April 12, 2011 Senate Bill X1-2 (Simitian, Chapter 1, Statutes of 2011)
Governor Edmund G. Brown, Jr. signed Senate Bill X1-2 into law to codify the ambitious 33 percent by 2020 goal. SBX1-2 directs California Public Utilities Commission's Renewable Energy Resources Program to increase the amount of electricity generated from eligible renewable energy resources per year to an amount that equals at least 20% of the total electricity sold to retail customers in California per year by December 31, 2013, 25% by December 31, 2016 and 33% by December 31, 2020. The new RPS goals applies to all electricity retailers in the state including publicly owned utilities (POUs), inve stor-owned utilities, electricity service providers, and community choice a ggregators. This new RPS preempts the California Air Resources Board’s 33 percent Renewable Electricity Standard.

September 27, 2006 Assembly Bill 32 (Núñez, Chapter 488, Statutes of 2006)
California Global Warming Solutions Act of 2006. This bill requires Air Resources Board (ARB) to adopt a statewide greenhous e gas emissions limit equivalent to the statewide greenhouse gas emissions leve ls in 1990 to be achieved by 2020. ARB shall adopt regulations to require the reporting and verification of statewide greenhouse gas emissions and to monito r and enforce compliance with this program. AB 32 directs Climate Action T eam established by the Governor to coordinate the efforts set forth under Executive Order S-3-05 to continue its role in coordinating overall climate policy.

See more information on AB 32 at ARB.

Source: http://www.climatechange.ca.gov/state/legislation.html

A. REDUCING  GREENHOUSE  GAS (GHG)  EMISSIONS
The passage of AB 32 in 2006 requires a statewide reduction in GHG emissions to 1990 levels by the year 2020; effectively a 30% decline in emissions from current statewide output. In 2016, SB 32 expanded the statewide GHG emissions reduction goal to 40% below 1990 levels by the year 2030.  To meet the AB 32 and SB 32 goals, APU began reducing its reliance on generation resources that produce GHG emissions by transitioning from fossil fuel‐fired generating resources to renewable resources and cleaner natural gas generation technologies.   The most significant contribution that APU can make in reducing GHG is the  reduction  of  energy  resources  that  produce  GHG  emissions  from  its  power  supply.  In  addition  to GHG  emission  reductions  from  APU’s  power  supply,  further  GHG  reductions  will  come  from complementary efforts including increased energy efficiency measures, local solar, energy storage, and transportation electrification.

In July 2015, APU developed its first utility‐specific Greenhouse Gas Reduction Plan with the purpose of developing  a  clear  and  comprehensive  long‐term  strategic  framework  to  reduce  GHG  emissions.   The Plan identifies a goal to reduce GHG emissions by 20% below 1990 levels by 2020, and a minimum of 40% below 1990 levels by 2030.   It is important to note that the 40% reduction below 1990 levels is a statewide  goal;  however,  California  utilities  will  likely  be  called  upon  to  do  more.   The  California  Air Resources  Board,  in  conjunction  with  California  Energy  Commission,  is  in  the  process  of  developing utility‐specific GHG reduction targets for California utilities as prescribed through the passage of SB 350.

The development of utility‐specific GHG reduction targets is not expected to be completed before the adoption of this IRP; however, APU is well positioned to meet GHG reduction targets beyond the current 2018 Integrated Resource Plan
IV. Key Policy Drivers Affecting the Utility

Anaheim Public Utilities

Page 28 ends

40%  mainly  as  a  result  of  increased  renewables  procurement  and  divestiture  plans  underway  for  coal resources under contract.

APU achieved its goal of 20% below 1990 levels through the increased renewable generation from 11% in 2010 to 33% of overall sales in calendar year 2015.  Further GHG emissions reductions are forecasted to  reach  near  the  40%  reduction  target  upon  the  divesture  of  the  San  Juan  Generating  Station  which occurred  at  the  end  of  2017.  As  shown  in  Graph  1,  upon  APU’s  exit  from  the  Intermountain  Power Project  in  2027,  APU’s  overall  GHG  emissions  from  its  power  supply  portfolio  is  expected  to  reach approximately  70%  below  its  1990  emissions  by  2028  based  on  projected  GHG  emissions  from  any  of the portfolio scenarios analyzed and discussed further in Section VII.

Graph 1: APU GHG Reduction Targets

B. INCREASING  PROCUREMENT  FOR RENEWABLE  RESOURCES
APU has steadily been increasing the renewable energy component of its resource portfolio since 2003.

In  response  to  Senate  Bill  1078,  the  Anaheim  City  Council  adopted  a  renewable  portfolio  objective  in July  2003  requiring  APU  to  provide  15%  of  retail  energy  requirements  with  energy  from  renewable resources by  2017.   That  objective was revised  by  Council  Resolution  No. 2006‐187 in August 2006 to achieve  a  target  of  20%  by  2015  as  a  result  of  Assembly  Bill  1362,  which  accelerated  the  statewide target to 20% by 2010. The passage of SB X1‐2 in 2011 increased the State’s renewables target to 33%

2018 Integrated Resource Plan
IV. Key Policy Drivers Affecting the Utility

Anaheim Public Utilities

Page 29 ends

by 2020, and was further expanded in late 2015 through the passage of SB 350 which requires APU to provide 50% of its retail energy sales to customers from renewable energy resources by the year 2030.

The  Renewable  Portfolio  Standard  (RPS)  is  a  key  element  of  the  State’s  strategy  to  reduce  statewide GHG  emissions.   Today,  APU  delivers  nearly  one  third  of  its  retail  electricity  sales  from  renewable resources.  APU  is  a  fully  resourced  utility,  meaning  APU’s  resource  portfolio  has  sufficient  generation capacity  to  serve  customer  energy  demand  and  meet  Resource  Adequacy  requirements.   The  State’s increasing  renewable  energy  procurement  mandates  create  a  challenge  in  balancing  the  costs associated with the current resource portfolio with the added costs of further increasing the renewable energy component of the overall resource mix. Section VII further discusses the effect of an accelerated RPS, along with strategies to minimize costs, risk and maintain affordable rates for the customers.

C. TRANSFORMATION  OF THE REGIONAL  GRID
APU is a market participant within the CAISO, which manages approximately 80 percent of California’s electric  grid  and  operates  a  competitive  wholesale  market.  The  CAISO  is  also  responsible  for  Grid reliability and efficiency. While California’s RPS is one of the more effective ways of lowering emissions of  GHGs,  integrating  a  significant  amount  of  variable  renewable  energy  resources,  such  as  wind  and solar,  into  the  physical  electric  power  grid  presents  various  challenges  for  Grid  reliability  and  the stability of energy markets. As the State’s share of variable renewable energy generation increases, the need for resources to respond to intermittent generation becomes critical for grid operators especially when this is occurring on a minute‐by‐minute basis, with changes in hourly, daily, and seasonal patterns of variable generation.

As  a  consequence  of  the  State’s  RPS,  including  solar  generation  installed  by  residents  and  businesses, the  CAISO  is  dealing  with  an  over‐supply  of  daytime  electricity  produced  by  solar  generation.  When there  is  less  demand  for  electricity  than  there  is  supply,  the  result  is  a  drop  in  wholesale  electricity prices;  which  in  turn  forces  generation  to  shut  down  (or  curtail)  until  the  demand  for  electricity increases  later  in  the  day.  During  times  of  extreme  energy  oversupply,  the  CAISO  may  need  to  send market signals through negative energy pricing, resulting in generators paying other entities to take the energy. This will lead to additional costs if market participants own generation that cannot be ramped down  due  to  technology  constraints  such  as  non‐dispatchable  renewables  or  a  minimum  capacity requirement.
2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 30 ends

V. RENEWABLE  ENERGY  PROCUREMENT  PLAN  AND ENFORCEMENT  PROGRAM A. ELEMENTS  OF THE RPS PROGRAM
A.1. PROCUREMENT  TARGETS
Public  Utilities  Code  Section  399.30(o),  as  amended  by  SB  350  (De  Leon),  directs  the  CEC  to  establish POU  enforcement  rules  and  procedures  for  the  RPS.  Unless  otherwise  provided  herein,  all  section references  will  refer  to  the  California  Code  of  Regulations,  Title  20,  Division  2,  Chapter  13,  Sections 3200‐3208  (Regulation).  Section  3204  of  the  Regulation  requires  APU  to  adopt  and  implement  a Procurement  Plan  to  demonstrate  that  it  procures  a  minimum  quantity  of  electricity  products  from eligible  renewable  energy  resources,  including  Renewable  Energy  Credits  (RECs).  The  CEC,  through  its formal  rulemaking  process,  adopted  multi‐year  Compliance  Periods  and  procurement  targets  for  each calendar  year  (CY)  through  2020.  SB  350  continues  the  same  multi‐year  Compliance  Period  construct and establishes a 50% RPS by 2030.   The CEC is scheduled to adopt the 2021 through 2030 Compliance Period and annual procurement targets in 2018. The current and proposed (*) Compliance Periods and procurement targets are outlined below:

Compliance Period
(CP)
Compliance Period Targets

CP 2
(CY 2014‐CY 2016)
Total renewable procurement for CP 2 must be equal to or greater than the sum of:
[(20% of 2014 retail sales)+(20% of 2015 retail sales)+(25% of 2016 retail sales)] CP 3
(CY 2017‐CY 2020)
Total renewable procurement of CP 3 must be equal to or greater than the sum of:
[(27% of 2017 retail sales)+(29% of 2018 retail sales)+(31% of 2019 retail sales)+(33% of 2020 retail sales)]
*CP 4
(CY 2021‐CY 2024)
Total renewable procurement of CP 4 must be equal to or greater than the sum of:
[(34.8%  of  2021  retail  sales)+(36.5%  of  2022  retail  sales)+(38.3%  of  2023  retail sales)+(40% of 2024 retail sales)]
*CP 5
(CY 2025‐CY 2027)
Total renewable procurement of CP 5 must be equal to or greater than the sum of:
[(41.7% of 2025 retail sales)+(43.3% of 2026 retail sales)+(45% of 2027 retail sales)] *CP 6
(CY 2028‐CY 2030)
Total renewable procurement of CP 6 must be equal to or greater than the sum of:
[(46.7% of 2028 retail sales)+(48.3% of 2029 retail sales)+(50% of 2030 retail sales)] *Post‐2030
Compliance periods beginning on and after January 1, 2031, shall be three (3) years in length.   Total  renewable  procurement  in  each  three  year  compliance  period  must meet an average of 50% over each compliance period.
2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 31 ends

A.2. PORTFOLIO  CONTENT  CATEGORY  REQUIREMENTS
Per Section 3202(a)(2), any renewable contracts executed after June 1, 2010 will be categorized into one of three portfolio content categories (PCCs). The table below describes the types of resources that are subject to the PCC limitations, and the minimums and maximums allowed for each Compliance Period.

Any renewable contracts executed prior to June 1, 2010 are not subject to the following PCC limitations:

Portfolio Content Categories (PCCs)

Percentage Requirements
(Post‐June 1, 2010 Procurement)
PCC 1:

Energy  or  RECs  from  eligible  resources  interconnected  to  a transmission network within the Western Electricity Coordinating Council (WECC) that:

1. Has  its  first  point  of  interconnection  within  the  metered boundaries of a California (CA) balancing authority area; or

2. Has  its  first  point  of  interconnection  to  an  electricity distribution  system  used  to  serve  end  users  within  the metered boundaries of a CA balancing authority area; or

3. Is  scheduled  into  a  CA  balancing  authority  without substituting  electricity  from  another  source.  If  another source  provides  real‐time  ancillary  services  to  maintain  an hourly  import  schedule  into  CA,  only  the  fraction  of  the schedule  actually  generated  by  the  renewable  resource  will count; or

4. Has an agreement to dynamically transfer electricity to a CA balancing authority area.

CP 2: Minimum of 65%

CP  3,  and  thereafter:  Minimum  of
75%
PCC 2:

Energy  or  RECs  from  eligible  resources  interconnected  to  a transmission  network  within  the  WECC  that  must  be  matched with  incremental  energy  that  is  scheduled  into  a  CA  balancing authority area.

CP 2: Maximum of 35%

CP  3,  and  thereafter:  Maximum  of
25%
PCC 3:

Energy  or  RECs  from  eligible  resources  that  do  not  meet  the requirements of PCC 1 or PCC 2, including unbundled RECs.

CP 2: Maximum of 15%

CP  3,  and  thereafter:  Maximum  of
10%

2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 32 ends

B. PLANNING  AND PROCUREMENT
B.1. PLANNING  ACTIVITIES
APU’s  Integrated  Resources  (IR)  division  is  responsible  for  managing  APU’s  energy  resource  portfolio (both conventional and renewable). To effectively manage the overall resource portfolio, IR develops a Power Supply Forecast on an annual basis. When developing this forecast, IR considers several factors including,  but  not  limited  to,  an  assessment  of  the  resource  supply  portfolio  and  a  projection  of customer  energy  and  peak  demand  requirements.  This  annual  review  results  in  a  twenty  (20)  year projection that includes all contracted projects, potential projects, and other viable technologies to fill resource  needs  that  are  required  to  meet  California  Independent  System  Operator  (CAISO)  reliability requirements, as well as legislative mandates. IR determines its expected renewable procurement needs by comparing its forecasted RPS procurement quantity targets to its forecasted energy deliveries from its renewable energy resource portfolio, all of which are key components of the Power Supply Forecast.

IR  takes  the  RPS  program’s  regulatory  framework  into  account  when  planning  for  renewable procurement, and meets to discuss its RPS requirements and progress on a regular basis. This process includes  a  thorough  analysis  of  project  performance,  as  well  as  short‐term  and  long‐term  RPS  needs.

Other  factors  taken  into  consideration  while  conducting  this  analysis  include,  but  are  not  limited  to:
renewable integration costs, the risk of delay or failure associated with renewable resources contracted or  under  consideration,  transmission  availability,  developer  experience,  financial  considerations (including the ability of the developer to secure funding), technology (i.e., new technology versus proven technology), and any other factors that can potentially delay or indefinitely postpone a project.

IR’s  objective  is  to  identify  renewable  projects  that  are  viable  and  cost‐effective,  enhance  APU’s resource portfolio, and optimize each PCC in an effort to minimize overall costs.

State law requires APU to develop this Integrated Resources Plan (IRP) prior to January 31, 2019. This comprehensive plan outlines APU’s activities in order to meet a 50% RPS by 2030 and greenhouse gas (GHG)  emission  reduction  targets.  It  must  also  address  impacts  on  customer  rates,  energy  efficiency, system  reliability  and  the  integration  of  various  distributed  energy  resources  within  the  APU  service area. The IRP describes APU’s strategy for effectively managing its overall energy resource portfolio into the future. Going forward, the two components of the RPS Policy, (i.e., the Renewable Energy Resources Procurement  and  Enforcement  Plans),  will  be  incorporated  into  the  IRP,  which  will  be  presented  for review and recommendation by the Public Utilities Board, considered for approval and adoption by the Anaheim City Council, and updated at least once every five years thereafter.

B.2 PROCUREMENT  (ORIGINATION)
APU  intends  to  demonstrate  its  progress  in  reaching  its  RPS  targets  in  compliance  with  State’s established  RPS  goals;  however,  it  is  important  to  note  that  APU  is  fully  resourced  and additional
resources will exceed the retail sales needs.   Per PUC §399.15(a) “… in order to fulfill unmet long‐term resource  needs,  the  commission  shall  establish  a  renewable  portfolio  standard…”  (emphasis  added). 2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 33 ends

APU has sufficient long‐term resources to meet anticipated needs.   Future resource procurement plans will be based upon load forecasts, any new power supplies required, if any, to cover unmet needs, and divestiture  of  existing  coal  resources.  Additionally,  as  a  member  of  the  CAISO,  APU  is  mandated  to procure resources to meet 115 percent (115%) of its forecasted peak demand for each month to ensure that more than sufficient resources are available to meet customer loads.

To  date  in  the  third  Compliance  Period,  IR  executed  five  (5)  additional  renewable  energy  contracts, which  includes  36  MW  of  solar  energy  sourced  within  California.  APU’s  procurement  strategy incorporates  both  near  and  long‐term  renewable  power  purchase  agreements  to  meet  the  complex requirements of the RPS Regulation.

APU routinely reviews its procurement strategy every month, not only for meeting its RPS goals, but to also  ensure  the  reliability  of  its  distribution  system.  In  addition,  APU  evaluates  the  viability  of  energy storage,  demand  response,  and  distributed  generation  resources  to  maintain  grid  reliability  and  meet the State’s overall energy policy goals.

2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program Anaheim Public Utilities

Page 34 ends

C. STATUS  OF APU’S RPS PORTFOLIO
C.1. PROGRESS TOWARD MEETING TARGETS
APU met the Compliance Period 1 target of an average 20% of its power from renewable resources, and its Compliance 2 target of providing no less than 25% of its power from renewable resources by the end of 2016. APU is on track to meet the RPS target of 33% by 2020. Planning activities undertaken in 2017 while developing  the  IRP  incorporate  a  variety  of  renewable  resources  as  a  way  to  ensure  continued diversification of the portfolio while progressing toward an aggressive goal of 50% renewables by 2030.

C.2.  RENEWABLE  RESOURCE  PROCUREMENT  PLAN
Appendix A – Renewable Procurement Plan provides a detailed summary of APU’s Renewable Resource Energy Procurement Plan. The table includes all grandfathered and contracted resources, as well as any contracts being actively negotiated. This chart also provides expected RPS compliance percentages and expenditures. The data is based on actual data for past years and forecasted data for all future years.

Appendix A may be revised, with the approval of the General Manager, without further approval by the Anaheim City Council to reflect updated Renewable Resource Procurement Plan information or data.

C.3.  BANKING  OF EXCESS  PROCUREMENT
Due to the inconsistent nature of renewables development and energy production, there may be years when  the  APU  exceeds  its  projected  RPS  targets.  In  order  to  preserve  the  investment  our  customers have made, and will continue to make, in the development of these resources, the legislature and State agencies recognized that the ability  to use any excess procurement  for future compliance is essential.

Pursuant  to  Section  3206,  the  City  Council  may  permit  APU  to  accumulate  excess  procurement  of eligible  renewable  resources  in  one  Compliance  Period  to  be  applied  to  any  subsequent  Compliance Period.  APU  intends  to  continue  banking  any  excess  procurement,  as  appropriate,  and  will  use  any surplus to help satisfy its future RPS compliance targets in the most cost‐effective manner.

C.4.  REPORTING  REQUIREMENTS
APU  is  required  to  provide  the  CEC  with  documentation  and  reports,  pursuant  to  Section  3207.

Compliance  reports  are  due  by  July  1  after  every  Compliance  Period;  however,  similar  reports  are required  annually  for  the  CEC  to  track  each  publicly  owned  utility’s  progress  toward  meeting  RPS targets. APU has demonstrated full compliance for the years 2011‐2013 in its July 2014 compliance filing to the CEC. The second Compliance Period filing covering the years 2014‐2016 was filed ahead of the July 1 2017 deadline, and is awaiting verification from the CEC. 2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 35 ends

D. POTENTIAL  COMPLIANCE  DELAYS
D.1 COMPLIANCE  PERIOD  2 EVENTS
As  discussed  in  Section  B.1.  above,  in  planning  its  renewable  procurement  position  and  needs,  APU accounts for potential issues that could delay RPS compliance. Unforeseen circumstances in the future may potentially hinder APU’s ability to comply. Achieving renewable energy goals is dependent on the successful  performance  of  renewable  developers  in  meeting  contractual  obligations,  completing construction  milestones  in  a  timely  fashion,  and  achieving  commercial  operation.  During  Compliance Period  (CP)  2,  APU  experienced  delays  associated  with  two  renewable  resource  contracts;  however, short‐term  renewable  energy  was  purchased  to  maintain  compliance.  The  first  contract  delay  was caused  by  the  developer’s  inability  to  secure  site  and  fuel  agreements  in  a  timely  manner,  and  the second  contract  delay  was  due  to  the  difficulties  the  developer  encountered  with  transmission interconnection  and  permitting.  To  the  extent  delays  and  resource  underperformance  occur,  the amount of delivered energy which APU can rely upon to reach its goals is reduced.

APU’s  forward  procurement  strategy  includes  the  probability  of  circumstances,  such  as  the  ones outlined above, occurring, and as such, APU considers procuring additional eligible renewable resources above  and  beyond  planned  procurement  to  account  for  potential  energy  delivery  shortfalls.   Going forward  into  the  next  Compliance  Periods,  APU  will  continue  to  consider  all  factors  in  the  planning process that may have an effect on its renewables portfolio and delay timely compliance with the RPS.

2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 36 ends

E. COST  LIMITATIONS
E.1. BACKGROUND
The State’s RPS law permits the local governing board of each POU to implement, at its sole discretion, a cost limitation for its RPS activities, consistent with Section 3206(a)(3).  The City Council, in the manner set  forth  in  this  and  previous  versions  of  the  RPS  Policy,  has  implemented  a  cost  limitation  in  its  RPS Policy for the protection of its customers and continues to review its methodology in coordination with updates to the Procurement Plan. Previous versions of the RPS Policy included a cost limitation based on a goal of 33% renewables by 2020.  APU is revising the cost limitation methodology to account for costs related to the increased State goal of a 50% RPS by the year 2030.

Through  the  approval  and  adoption  of  this  IRP,  the  Anaheim  City  Council  is  implementing  a  cost limitation that relies on:
  The most recent Procurement Plan (which is contained herein); and  Procurement  expenditures  that  approximate  the  expected  cost  of  building,  owning  or operating  eligible  renewable  resources,  which  does  not  include  indirect  expenses  as described in Section 3206(a)(3)(B)(3); and
 The potential that some planned resource additions may be delayed or cancelled.

This cost limitation meets all of the requirements of Section 3206(a)(3). The cost limitation value which is contained herein may be updated on a periodic basis.

E.2. SUMMARY  OF COST LIMITATION  ELEMENTS
APU’s cost limitation is intended to reflect current market conditions, address any disproportionate rate impacts to customers, and reflect the added costs of committing public funds to additional projects as some  are  delayed  or  permanently  removed  from  a  construction  queue.  The  analysis  for  the  cost limitation  is  calculated  based  on  the  most  recent  power  supply  forecast.  The  City  Council,  in  ensuring that customers do not face a disproportionate burden, has the authority to implement a cost limitation, which may result in the temporary suspension of RPS compliance activities.

E.3. COST LIMITATION  THRESHOLD
The  City  Council  hereby  approves  and  directs  APU  to  implement  the  following  RPS  cost  limitation threshold  to  prevent  a  disproportionate  customer  rate  impact  associated  with  the  implementation  of State‐mandated RPS procurement targets:

In no event shall the cost of procuring any new renewable energy resources cause an increase in overall power  supply  costs  greater  than  $0.01  per  kilowatt‐hour  in  any  fiscal  year  during  a  20‐year  planning horizon.  A  $0.01  per  kilowatt‐hour  increase  is  considered  to  be  an  undue  burden  on  customers  as  it 2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 37 ends

represents a 10% increase over current power supply costs in a single year, which is approximately four times the expected rate of general inflation.

E.4. PROCESS  FOR IMPLEMENTATION
APU  continuously  monitors  its  expenditure  levels  and  will  advise  the  City  Council  routinely  of  its  RPS expenditures. Below is the process that APU
will follow to advise the City Council when the threshold to implement its cost limitation is met and the direction it will take, as directed by City Council:
1) APU  Staff  will  advise  City  Council,  via  staff  report,  that  the  threshold  for  the  cost limitation  has  been  reached  and  will  recommend  a  course  of  action  for  City  Council consideration.
2) City  Council,  at  its  sole  discretion,  may  choose  to  implement  the  cost  limitation provision and direct APU to cease its activities related to RPS compliance. 3) Through  the  direction  provided  by  City  Council,  APU  will  either  cease  its  activities related to RPS compliance or continue its RPS compliance activities.

E.5. DETAILS  ON COST  LIMITATION  THRESHOLD
This section provides background on APU’s actions, when a cost limitation threshold is reached.

1. Disproportionate Rate Impacts
APU  forecasts  RPS  procurement  costs  when  developing  the  annual  power  supply forecast. The forecast provides a projection of supply and demand, including costs, and provides an estimation of anticipated increases in costs. It is determined that renewable procurement costs that exceed an increase of $0.01/kWh will cause a disproportionate burden on customers.  A $0.01/kWh increase is considered a disproportionate burden as it represents a 10% increase over current power supply costs in a single year, which is approximately four times the expected rate of general inflation. This cost limitation is a proactive  measure  which  aims  to  prevent  undue  economic  consequences  of  the  RPS statute and Regulation on customers.

2. Projects Delayed or Cancelled
Per Section 3206(a)(3)(C) cost limitations can include “the potential that some planned resource additions may be delayed or canceled.”
As  discussed  in  detail  in  the  Procurement  Plan,  APU  staff  contracts  for  the  required amount of RPS resources, to meet compliance obligations. However, issues outside the APU’s  control  (i.e.,  permitting,  financing  of  the  project,  interconnection  issues,  cost 2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 38 ends

projections, etc.) may delay or indefinitely postpone a project.  As a POU, Anaheim must be selective when entering into contracts for renewable procurement as these contracts are associated with financial obligations and tie up public funds. The cost of the delay or indefinite  postponement  of  any  project  should  be  included  when  determining detrimental rate impacts or calculating an increase to power supply costs.

3. Other Circumstances
The  City  Council  may  choose  to  implement  additional  cost  limitations,  consistent  with the Regulation upon the occurrence of, but not limited to, the following examples:
 Changes in the Regulation
In  the  event  that  the  RPS  Regulation  is  modified,  there  is  a  possibility  that contracted resources may not fully count toward APU’s RPS, as anticipated. The cost of replacing the lost renewable energy that was expected to be delivered from these resources must be taken into consideration.
 Force Majeure
The  occurrence  of  a  Force  Majeure  event  which  adversely  impacts  the  delivery  of renewable resources and thereby increases RPS compliance costs. It is expected that such  Force  Majeure  events  will  place  an  undue  economic  burden  on  Anaheim  as well as its customers.

2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 39 ends

F. ENFORCEMENT  PROGRAM
WAIVER  FOR NONCOMPLIANCE
APU monitors its progress in reaching its RPS targets on a monthly basis, as well as through the APU’s annual  budgeting  process,  subject  to  the  approval  of  budgeted  expenditures  by  the  City  Council  as recommended by the Public Utilities Board. The City Council is responsible for enforcing the RPS Policy through the Enforcement Program, and will consider any recommendation by the Public Utilities Board.

Current law authorizes the City Council to waive APU’s compliance requirements, consistent with PUC §399.15(b)(5)  and  Section  3206(a)(2)  of  the  Regulation,  if  APU  can  demonstrate  any  of  the  following conditions are beyond the control of the utility, and will prevent timely compliance.  The conditions for waiver  or  delaying  compliance  include,  but  are  not  limited  to  the  following  (which  may  delay  or indefinitely postpone a project):

1. Inadequate  transmission  capacity:  [Section  3206(a)(2)(A)(1)].  There  is  inadequate  transmission capacity  to  allow  for  sufficient  electricity  to  be  delivered  from  proposed  eligible  renewable energy resource projects using the current operational protocols of the California Independent System  Operator  (CAISO).  City  Council  interprets  this  to  mean  the  inability  to  bring  eligible renewable  resources  into  the  CAISO  due  to  transmission  limitations.  This  includes  instances where  transmission  outages  may  prevent  renewable  energy  from  entering  into  the  CAISO market. This may cause APU to be out of compliance for a Compliance Period. The City Council has the authority to waive APU’s compliance for this instance.

2. Permitting,  interconnection,  or  other  circumstances  that  delay  procured  renewable  energy resource  projects  or  insufficient  supply  of  eligible  renewable  energy  resources:  [Section 3206(a)(2)(A)(2)].   Examples include, but are not limited to, the following:
 Development (i.e., permitting, financing, etc.): City Council interprets this to include a  renewable  resource  developer's  inability  to  obtain  financing,  permits, interconnection, or the rights to build the project. This may cause APU to be short of compliance  for  a  Compliance  Period.  The  City  Council  has  the  authority  to  waive APU’s compliance for this instance.

 Operation (i.e., fires, accidents, outages, etc.): City Council interprets this to include any  unforeseen  circumstances  preventing  the  renewable  resource  from  being developed  or  delaying  its  output.  This  includes  outages  at  the  renewable  energy facility.  For  example,  if  there  is  a  wildfire,  transmission  outage,  or  facility  outage that prevents resources from delivering energy into the CAISO may cause APU to be short of compliance for a Compliance Period. The City Council has the authority to waive APU’s compliance for this instance.

 Regulatory  Delays:  City  Council  interprets  this  to  include  instances  where  State agencies  delay  timely  requests  by  APU  for  registering  renewable  resources, certifying  renewable  resources,  and  accepting  renewable  resources  into  its 2018 Integrated Resource Plan
V. Renewable Energy Procurement Plan and Enforcement Program

Anaheim Public Utilities

Page 40 ends

renewable  portfolio.  In  addition,  these  also  include  changes  to  State  mandates, which  may  lead  to  a  delay  in  compliance.    The  City  Council  has  the  authority  to waive APU’s compliance for this instance.

3. Unanticipated curtailment to address needs of a balancing authority: [Section 3206(a)(2)(A)(3)].

City  Council  interprets  this  section  to  include  the  CAISO  directing  a  renewable  resource  to modify  their  energy  obligations,  due  to  the  needs  of  the  balancing  authority.  This  may  cause APU to be short of compliance for a Compliance Period.   The City Council has the authority to waive APU’s compliance for this instance.

APU  will  monitor  its  progress  in  reaching  its  RPS  targets;  however,  as  listed  above,  there  may  be circumstances that prevent APU from procuring renewable resources to meet its RPS targets.  In such an instance,  APU  will  request  City  Council  authority  to  approve  a  waiver  of  compliance,  consistent  with Section 3206(a)(2).

2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 41 ends

VI. ENERGY  DEMAND  AND PEAK  FORECASTS
Integrated  resource  planning  is  the  process  in  which  APU  evaluates  a  multitude  of  supply‐side  and demand‐side  resources  to  meet  customer  energy  needs  in  an  efficient,  cost  effective,  and  reliable manner.  Traditionally  this  integrated  resource  planning  activity  was  primarily  to  ensure  that  all  cost‐ effective demand side resources were deployed prior to commitment to new supply‐side resources such as  power  plants.  Supply‐side  resources  usually  involved  long  lead  times  to  develop  and  increased  the use  of  fossil  fuel  causing  the  depletion  of  a  limited  resource  and  adverse  effects  on  the  environment.

More  recently,  the  passage  of  SB  350  now  requires  integrated  resource  planning  to  consider  and address the following elements in addition to traditional demand‐side and supply‐side resources:
 Actively  involve  stakeholders.  (APU  proactively  solicited  feedback  from  residents,  small  to medium businesses, large businesses, high school students and the Latino Utilities Coalition.)  Include energy efficiency and demand side management activities.  Incorporate more robust analysis of more aspects of utility activities.  Explicitly  account  for  commodity  price  volatility  and  other  risks  to  quantify  the  risk/reward tradeoff.
 Reflect a set of goals that are broader than just meeting energy demand, such as meeting RPS goals and GHG goals.
 Accommodate  the  load  increases  and  decreases  caused  by  transportation  electrification  and distributed energy resources such as rooftop solar.

The  energy  demand  forecast  and  peak  forecast  are  both  developed  as  a  first  step  to  evaluate  APU’s future  energy  needs.  APU’s  forecasting  methodology  and  different  components  of  the  forecasts  are detailed below.

2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 42 ends

Pursuant  to  this  IRP,  APU  performed  a  long‐term  statistical  forecast  of  its  expected  load  growth  and then  adjusted  this  base  load  forecast  for  the  factors  described  above.  This  adjusted  load  forecast projects  a  total  load  reduction  of  0.86%  between  2018  and  2030,  effectively  a  no  growth  energy demand forecast, which indicates that the expected customer expansion and EV growth is being offset by customer solar installation and energy efficiency reductions.

Graph 2: Cumulative Adjustments to Base Load Forecast

In determining APU’s energy demand forecast, staff considered historical energy demand and customer growth trends as the basis for statistical modeling and econometric forecasting techniques to develop a “base energy demand forecast.” Once developed, the base forecast was further adjusted (referred to as the  adjusted  energy  demand  forecast)  by  planned  system  expansion,  expected  EV  energy  demand, estimated customer‐side solar PV installation, and the effect of demand side management and energy efficiency.  While  system  expansion  and  EV  growth  increase  the  energy  demand,  solar  installation  and energy efficiency programs reduce the energy demand.

The adjusted energy demand forecast was then used as the basis for the development of power supply expansion portfolio scenarios, which were analyzed to determine the recommended supply (resource) portfolio.

Base Energy Demand Forecast
+ Energy Demand Addition
•System Expansion
•EV Penetration
‐ Energy Demand Reduction
•Solar Installation
•Energy Efficiency
= Adjusted Energy Demand
Forecast
(120)
(70)
(20)
30 80GWh
GWh
Cumulative Adjustments to Base Energy
Demand Forecast (2018‐2030)
Energy Efficiency
Solar PV
EV Adoption
Planned Expansion
Cumulative Impact on Energy Demand
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 43 ends

A. ENERGY  DEMAND  FORECAST  ‐  METHODOLOGY  & ASSUMPTIONS The energy demand forecast is determined in two steps:

The  first  step  establishes  the  base  energy  demand  forecast.  It  relies  on  traditional  econometric forecasting  techniques  to  develop  relational  equations  that  reflect  historic  consumption  trends.   The base forecast for energy demand is developed using a 5‐year running average of historical temperature.

The second step adjusts the base energy demand forecast by taking into consideration residential and commercial  projects  within  the  City  of  Anaheim  (City)  that  may  affect  energy  demand.  Information related  to  these  projects  is  collected  through  collaboration  with  the  City’s  Planning  Department,  APU Electric System Planning, and Business & Community Programs. Examples of such projects include City‐ wide  development  and  expansion  plans,  customer‐specific  capacity  additions  and/or  energy  reduction plans,  and  the  installation  of  commercial‐scale  solar  photovoltaic  (PV)  and  other  behind‐the‐meter distributed  generation  resources.  Project  timelines  are  evaluated  and  incorporated  into  adjustments that either increase or decrease the “base” forecast.

A.1. BASE  ENERGY  DEMAND  FORECAST
HISTORICAL  ENERGY  DEMAND
Prior to the economic recession in 2008, APU’s average energy demand was between 2,500 and 2,700 GWh. From 2008 to 2011, a decline in energy demand growth was observed due to economic conditions impacting  demand.  The  economy  began  to  stabilize
in  2011  and  continued  to  improve  through  2016.

However,  the  corresponding  demand  growth  was  offset  by  behind‐the‐meter  distributed  generation, such  as  fuel  cell  and  solar  PV  installation,  as  well  as  by  energy  efficiency  in  both  the  commercial  and residential sectors.

Graph 3: Anaheim Actual Energy Demand 2001 ‐ 2016

2,300
2,350
2,400
2,450
2,500
2,550
2,600
2,650
2,700
2,750
GWh
Base Energy Demand
Forecast

2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 44 ends

ECONOMETRIC  MODELING
Econometric  modeling  is  the  application  of  mathematical  and  statistical  methods  to  forecast  future values  and  understand  the  relationship  between  variables.  APU  develops  its  forecast  of  total  system energy  consumption  using  econometric  modeling.  Hourly  energy  demand  is  estimated  using  least squares estimation and variables for expected temperature, calendar (weekday versus holiday), season and  time  effects  (which  capture  specific  hours  as  well  as  the  cumulative  impact  of  prolonged  heat waves). Five years of historical hourly data are used to estimate the following econometric equation:

Total Energyt = α + 1 Temperaturet + D1 Holidayt + Vt + Mt + εt Where:

Temperaturet = Temperature at hour t
Holidayt = Dummy variable to identify weekend and NERC holidays Vt = Vector of dummy variables for the hours
Mt = Vector of dummy variables for the months
εt = Error term

VARIABLES  INCLUDED:  TEMPERATURE  FORECAST
APU  owns  calibrated  equipment  at  the  Linda‐Vista  Reservoir  that  records  hourly  temperature  in  the Supervisory  Control  and  Data  Acquisition  (SCADA)  system.  The  IRP  energy  demand  forecast  assumes normal  weather  conditions  and  uses  average  hourly  temperatures  from  the  past  five  years  (2011  – 2016). The forecasted monthly temperatures in degrees Fahrenheit are summarized below:

Table 1: Temperature Summary
Month  Average  Minimum  Maximum
January  60  35  89
February  60  32  95
March  62  41  96
April  65  39  96
May  67  49  104
June  70  53  105
July  75  58  103
August  76  59  101
September  76  56  105
October  71  49  105
November  63  43  95
December  57  37  89

2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 45 ends

VARIABLES  EXCLUDED:  ECONOMIC  AND DEMOGRAPHIC  FORECAST Anaheim is a fully developed Orange County city with historically consistent growth and median income level and employment rate. A series of modeling tests determined that the inclusion of economic and demographic  variables  leads  to  increased  variability,  and  results  in  overly  optimistic  demand  growth.

The hourly demand estimation excluding these variables proved to be more accurate.

Although economic and demographic variables are excluded from the base model, planned expansions and  energy  reductions  are  included  as  adjustments  after  the  econometric  regression  modeling  is complete.

MODEL  VALIDATION
The  base  econometric  model  is  validated  by  comparing  modeling  results  to  historical  energy  demand data.  Essentially,  the  model  is  used  to  develop  energy  demand  forecasts  for  historical  years  2013 through  2016.  The  forecast  results  are  compared  to  historical  actual  values  and  analyzed  for reasonableness. The base model was proven to produce efficient estimation results in the range of 0.4% to  2.1%  variance  for  the  testing  period.  Had  the  model  been  proven  inefficient,  alternative  variables would have been introduced and a new model established to go through the validation process again.

FORECAST  RESULTS
After validating the  model, the base forecast for future years is  generated and compared  to historical energy  demand.  As  seen  in  Graph  4,  the  energy  demand  forecast  is  comparable  to  historical  energy demand. Overall, annual energy demand shape remains fairly constant, while peak demand appears to be lower than that of recent years. This is mostly due to the assumption of normal weather conditions rather than the incorporation of heat shocks in the base model.

Graph 4: Historical and Base Energy Demand Forecast by Month

150
170
190
210
230
250
270
290
Jan Feb Mar Apr May June July August Sept Oct Nov Dec
GWh
Historical and Base Energy Demand Forecast by Month
2012 2013 2014 2015 2016 Base Forecast
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 46 ends

A.2. ADJUSTMENTS
Planned  energy  growth  and  reductions  are  included  as  adjustments  to  the  base  economic  model.

Adjustments  include  planned  new  development,  electric  vehicle  growth,  behind‐the‐meter  distributed generation, and energy efficiency targets.

This section focuses on the energy demand impact. The
design,  funding  and  details  of  these  programs  can  be found in the following sections:

X. Transportation Electrification
XI. Solar and Other Distributed Generation
XII. Energy Efficiency and Demand Response Programs
XIII. Programs for the Low Income and Disadvantaged Communities

SYSTEM  EXPANSION
Most of the open land in Anaheim is fully developed. While new building developments may contribute to  energy  demand  increase,  a  corresponding  decrease  also  incurs  from  the  demolition  of  existing buildings  and  infrastructure.  As  such,  it  is  not  appropriate  to  apply  a  growth  rate  based  on  historical trends. Rather, new development data is gathered from City permits and from Electric System Planning, and these net impacts to energy demand are applied to the base model.

Anaheim’s most recent development projects are expected to cumulatively contribute an additional 33 MW  capacity  to  Anaheim’s  distribution  infrastructure  through  2030.  When  estimating  the  impact  to load,  staff  took  into  consideration  both  the  distribution  system  expansion  and  the  varying  levels  of capacity factors for each customer sector.

EV PENETRATION  & TRANSPORTATION  ELECTRIFICATION
Electric vehicle growth is estimated using the CEC “Transportation Electrification Common Assumptions

3.0” workbook published in 20171. Anaheim’s electric vehicle energy demand forecast adopts the CEC growth assumption to meet the Governor’s Order for 1.5 million electric vehicles on the road by 2025, and assumed growth to 2.6 million electric vehicles on the road by 2030.

1 “2016 SB 350 Common Assumption Guidelines for Transportation Electrification Analysis”, Version 3.0, Updated April 6, 2017. This workbook is subsequently replaced by updated versions and no longer available via the CEC website. The most updated version is available for download at http://www.energy.ca.gov/sb350/IRPs/. A comparison of Version 3.0 and the updated version may be found under Section IX. GREENHOUSE GAS EMISSION REDUCTION.
+ Energy Demand Additions
•System Expansion
•EV Penetration
‐ Energy Demand Reductions
•Solar Installation
•Energy Efficiency & Demand Response

2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 47 ends

According  to  the  model  within  the  CEC  workbook,  APU’s  share  of  total  California  registered  electric vehicles is 0.63%, or an estimated 16,280 electric vehicles by 2030.

To estimate energy demand growth, APU adopted the CEC’s assumptions in the workbook in terms of energy  consumption.  According  to  the  workbook,  the  16,280  electric  vehicles  will  contribute  up  to 63,261 MWh in energy demand growth in Anaheim in 2030.

Graph 5: Estimated Electric Vehicle Energy Demand Growth

SOLAR  INSTALLATION  & OTHER  DISTRIBUTED  GENERATION
Historical  behind‐the‐meter  distributed  generation  information  is  obtained  from  SB  1  and  City  permit applications. This includes micro turbine, fuel cell, and photovoltaic (PV) installations.

Short‐term  PV  installation  growth  is  estimated  using  system  size  data  listed  on  the  resident’s  permit application. Long‐term PV installation growth is estimated using a linear trend of historical installation totals. APU estimates to have 33 MW of installed PV capacity by 2019, and 87 MW by 2030. To estimate PV generation, a proxy capacity factor of 18.38% is applied to the PV capacity forecast. Detailed solar PV capacity calculation and peak impact analysis may be found in the “Peak Shift Analysis” section.

In 2019, behind‐the‐meter solar distributed generation is estimated to account for 2.1% of APU’s total energy  demand  and  is  expected  to  grow  by  0.3%  annually  reaching  a  total  of  5.4%  of  total  energy demand by 2030.

Graph 6 shows the estimated annual impact of behind‐the‐meter solar PV installation growth.

0 10,000
20,000
30,000
40,000
50,000
60,000
70,000
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MWh
Estimated Electric Vehicle Energy Demand
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 48 ends

Graph 6: Estimated Behind‐the‐Meter Solar PV Impact to Energy Demand

Planned distributed generation projects other than solar PV are forecasted only in the short term, with system size estimates obtained from Electric System Planning.

ENERGY  EFFICIENCY
In  accordance  with  AB  2021,  APU  is  required  to  establish  specific  annual  energy  saving  goals  as  a percentage  of  total  annual  retail  electric  consumption.  SB  350  also  mandated  that  the  CEC  develop utility‐specific  energy  efficiency  saving  targets  to  help  achieve  doubling  statewide  energy  efficiency savings in electricity and natural gas end uses by 2030.

APU, in conjunction with other members within the California Municipal Utilities Association, contracted with  Navigant  Consulting,  Inc.  (Navigant)  to  identify  all  potentially  achievable  cost‐effective  electricity efficiency  savings  and  establish  annual  targets  for  energy  efficiency  savings  for  2018‐2027.  The  final report “Energy Efficiency in California’s Public Power Sector”2 was published and submitted to the CEC in 2017. Anaheim City Council adopted APU’s ten‐year energy saving goal in March 2017, based on study results from the Navigant report.

APU’s energy saving goal, along with its impact to Energy Demand, are summarized in Table 2.

Table 2: APU Energy Efficiency Targets including Codes & Standards (Navigant Study)

* 2028‐2030 are projections based on 2027 targets. 10‐Yr Average Calculated for 2018‐2027.

APU’s voluntary demand response program is only called upon under extreme conditions, and therefore is not included in the energy demand adjustments under normal weather conditions. In addition, the

2 https://www.anaheim.net/DocumentCenter/View/11240
‐
500
1,000
1,500
2,000
2,500
3,000
GWh
Net Energy Demand Solar PV
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028  * 2029  *2 0 3 0  * Avg. 10 Yr. kWh 1.15% 1.15% 1.09% 1.06% 1.04% 1.00% 0.95% 0.91% 0.86% 0.80% 0.80% 0.80% 0.80% 1.00% kW 1.11% 1.12% 1.13% 1.15% 1.19% 1.14% 1.15% 1.13% 1.09% 1.04% 1.04% 1.04% 1.04% 1.13% Targets w/ C&S
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 49 ends

pilot residential demand response program generated 794 kWh savings in summer 2017. It is considered negligible to APU’s total energy demand at this time. Estimated adjustments for demand response reductions will be calculated when future program expansion demonstrates greater impact to the total energy demand.

A.3. ADJUSTED  BASE  ENERGY  DEMAND  FORECAST
In total, APU expects a 0.86% net energy demand reduction between 2018 and 2030, which is essentially a  no  growth  forecast.  The  net  energy  demand  forecast  is  used  in  Section  VII.  Resource  Portfolio Evaluation to determine the recommended resource portfolio to meet APU’s future energy needs.

Graph  2  displays  the  estimated  cumulative  impacts  to  the  Base  Energy  Demand  Forecast.  The  energy demand additions are estimated to increase by 82 GWh cumulatively due to planned expansion projects and  electric  vehicle  growth.  During  the  same  period,  solar  PV  and  energy  efficiency  are  estimated  to reduce the energy demand by approximately 102 GWh cumulatively. The overall cumulative net energy demand reduction is estimated to be approximately 20 GWh as indicated by the red line on Graph 2.

Graph 7 below depicts the Adjusted Energy Demand Forecast. The sum of all three bars is the anticipated Base Energy Demand Forecast, assuming no growth or reduction. Additions such as planned expansion projects and electric vehicles are displayed by the light green bar. The total Reductions are displayed by both the light green and white bars. The Adjusted Energy Demand is the sum of the dark green and light green bars. The remaining white bar is the estimated net energy demand reduction per year.

Base Energy Demand Forecast
+ Energy Demand Addition
•System Expansion
•EV Penetration
‐ Energy Demand Reduction
•Solar Installation
•Energy Efficiency
= Adjusted Energy Demand
Forecast
(120)
(70)
(20)
30 80GWh
GWh
Cumulative Adjustments to Base Energy
Demand Forecast (2018‐2030)
Energy Efficiency
Solar PV
EV Adoption
Planned Expansion
Cumulative Impact on Energy Demand
Graph 2: Cumulative Adjustments to Base Load Forecast
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 50 ends

Graph 7: Adjusted Base Energy Demand Forecast

APU’s energy demand forecast was completed in 2017. The CEC released its energy demand forecast for the  2018  Integrated  Energy  Policy  Report  (IEPR)  in  February  2018.  Staff  compared  APU’s  adjusted  (or expected) energy demand – excluding EV Impacts – against the IEPR demand forecast: Medium Baseline Demand  with  Medium  Additional  Achievable  Energy  Efficiency  (AAEE)  and  Additional  Achievable Photovoltaic  (AAPV).  APU’s  forecast  is  very  close  to  the  IEPR  forecast  in  the  early  years,  with  a  4% variance observed by 2030. The difference is considered acceptable for planning purposes. In addition, a range  of  high  and  low  energy  demand  will  be  tested  under  Resource  Portfolio  Evaluation  –  Stress Testing.

Graph 8: APU vs. IEPR Energy Demand Forecast

2,000
2,050
2,100
2,150
2,200
2,250
2,300
2,350
2,400
2,450
2,500
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GWh
Adjusted Base Energy Demand Forecast
Net Load Load Growth Load Reduction
Total Load
Growth
‐
500
1,000
1,500
2,000
2,500
3,000
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GWh
APU vs. IEPR Energy Demand Forecast
APU Adjusted (Expected) Energy Demand ‐ Excluding EV Impact CEC Mid Baseline Demand Mid AAEE‐AAPV
Total Load
Reduction
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 51 ends

A.4.  OTHER  CONSIDERATIONS  ‐ EXTREME  WEATHER
It  is  important  to  analyze  the  impact  of  weather  extremes  on  energy  demand  due  to  its  sensitivity related to temperature changes. Extreme temperature forecasts under high and low emission scenarios are  available  through  Cal‐Adapt,  a  climate  change  resource  database  developed  by  the  Geospatial Innovation  Facility  at  the  University  of  California,  Berkeley  with  funding  and  advisory  oversight  by  the California Energy Commission.

The  daily  extreme  temperature  forecast  data  for  the  Anaheim  area  was  obtained  through  Cal‐Adapt3 and  then  compared  to  APU’s  internal  temperature  forecast,  which  was  developed  using  five‐year minimum and maximum temperatures. APU’s forecast consistently produces higher extremes than the Cal‐Adapt forecast. The deviations between the forecasts are shown in Graph 9, which displays the high and low emissions Cal‐Adapt high temperature forecast compared to APU high temperature forecast for the spring and summer of 2023. As the APU forecast produces higher extremes, it was selected to be the preferred temperature forecast to conduct the extreme weather analysis on energy demand.

Graph 9: Cal‐Adapt vs APU Maximum Temperature Forecast

The  econometric  model  described  in  VI.A.1.  estimates  a  coefficient  of  1.16  MWh  for  the  temperature variable. This is interpreted as an increase in energy demand of 1.16 MWh for every degree Fahrenheit increase. For example, an increase in temperature of 20 degrees Fahrenheit results in a corresponding increase  in  demand  for  that  hour  of  23.2  MWh.  Applying  the  extreme  temperature  forecast  to  the economic  model  produces  a  bandwidth  of  expected  energy  demand  under  high  and  low  temperature extremes.

3 http://cal‐adapt.org/
60 65
70 75
80 85
90 95
100
105
110
Date
6‐Apr‐23
12‐Apr‐23
18‐Apr‐23
24‐Apr‐23
30‐Apr‐23
6‐May‐23
12‐May‐23
18‐May‐23
24‐May‐23
30‐May‐23
5‐Jun‐23
11‐Jun‐23
17‐Jun‐23
23‐Jun‐23
29‐Jun‐23
5‐Jul‐23
11‐Jul‐23
17‐Jul‐23
23‐Jul‐23
29‐Jul‐23
4‐Aug‐23
10‐Aug‐23
16‐Aug‐23
22‐Aug‐23
28‐Aug‐23
3‐Sep‐23
9‐Sep‐23
15‐Sep‐23
21‐Sep‐23
27‐Sep‐23
3‐Oct‐23
9‐Oct‐23
15‐Oct‐23
21‐Oct‐23
27‐Oct‐23
Degrees Fahrenheit
Cal‐Adapt High Emission Anaheim Cal‐Adapt Low Emission
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 52 ends

Graph  10  below  displays  the  estimated  deviations  from  expected  energy  demand  due  to  extreme weather impacts. The high weather extreme results in an increase from expected energy demand of 81 GWh annually, with the highest monthly impact in the month of October of 8.2 GWh. The low weather extreme  results  in  a  decrease  from  expected  energy  demand  of  71  GWh  annually,  with  the  largest decrease being in the month of February of 7.5 GWh.

Graph 10: Forecasted Energy Demand with Extreme Temperatures

The energy demand variation due to extreme weather impacts will be used to stress test the resource portfolio in VII. F. Stress Testing.

1,500
1,700
1,900
2,100
2,300
2,500
2,700
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
GWh
Expected Temp High Temp Low Temp
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 53 ends

B. PEAK  FORECAST  ‐  METHODOLOGY  & ASSUMPTIONS
The peak forecast is also developed along with the energy demand forecast for use in consideration of the reliability aspects of power supply Resource Adequacy and electric distribution system planning:
 Peak forecast is used to determine the Resource Adequacy capacity needed to meet reliability requirements.
 Hour‐by‐hour peak and energy profile analysis is used to determine which resource’s generation portfolio  provides  the  best  match.  It  also  assists  APU’s  effort  to  explore  possibilities  in  using clean energy to meet the peak demand.
 Electric System Planning relies on the long‐term peak forecast to plan for necessary distribution system expansion.

B.1. CONSIDERATION  OF THE HISTORICAL  SYSTEM  PEAK
Although APU’s total energy demand declined from 2008 to 2011, the total system peak has fluctuated over  the  past  several  years  between  540  and  580  MWh.  Anaheim’s  annual  system  peak  is  typically observed  in  the  month  of  September,  when  temperatures  average  76  degrees  and  reach  up  to  105 degrees.

Graph 11: APU Historical Peak Demand

B.2. DEVELOPING  THE PEAK FORECAST
When developing the peak demand forecast, APU considers historical load factors.

APU’s load factor is calculated by taking the total energy demand for each month and dividing it by the peak demand for the same month. Historical average load factors are calculated for each month for the 440
460
480
500
520
540
560
580
600
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
MW
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 54 ends

most recent five years. The load factors are applied to the adjusted monthly energy demand forecast to develop the peak demand forecast.

Table 3: Historical Load Factors (as of December 2017)

Month  2013  2014  2015  2016  2017  AVERAGE
July  68%  67%  66%  69%  62%  66%
Aug  68%  60%  65%  65%  63%  64%
Sept  63%  59%  59%  60%  58%  60%
Oct  57%  72%  62%  59%  50%  60%
Nov  67%  70%  66%  79%  62%  69%
Dec  78%  77%  88%  78%  80%
Jan  80%  73%  79%  78%  77%
Feb  80%  77%  72%  69%  74%
Mar  75%  76%  68%  75%  74%
Apr  77%  66%  62%  68%  68%
May  58%  55%  61%  75%  62%
June  64%  74%  66%  54%  64%

The peak demand forecast is validated by comparing the model’s “backcast” output to the previous five year’s actual data. The peak forecast’s accuracy to predict monthly peak is between 0.3% and 3.5%. The annual peak forecast accuracy was in the range of ‐1% to 5% and within the acceptable confidence level.

B.3. OTHER  CONSIDERATIONS
Peak Shift
APU estimates to have 33 MW of installed PV capacity by 2019 and 87 MW by 2030. Graph 12 details the estimated installed PV capacity for APU’s service territory.

Graph 12: Estimated Distributed (Behind‐the‐Meter) Solar PV Capacity

0 10
20 30
40 50
60 70
80 90
100
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 55 ends

To  develop  an  estimation  methodology  for  customer‐owned,  behind‐the‐meter  solar  PV  generation, APU studied the solar generation from the City‐owned Anaheim Convention Center solar PV system. The system generates approximately 3,400 MWh of solar energy per year (as recorded in 2015 and 2016), and has a capacity factor of 18.38%.

On  average,  July  produces  the  highest  generation  per  year,  with  12.5  MWh  per  day.  The  month  of December produces the least amount of generation per year, on average with 4.75 MWh per day. Graph 13  details  each  month’s  average  hourly  solar  profile,  as  derived  from  the  generation  of  the  Anaheim Convention Center solar PV system. Peak solar generation is at noon November through March and at Hour 13 (1 PM) for the remainder of the year.

Graph 13: Average Hourly Solar Profile by Month: Anaheim Convention Center

Although  production  varies  from  system  to  system,  the  calculated  capacity  factor  from  the  Anaheim Convention  Center  serves  as  a  strong  proxy  to  estimate  production  from  installed  private  PV  capacity within the City. This is especially true because the Convention Center is located in the center of Anaheim and is capable of capturing City specific weather effects.

To calculate total distributed solar generation, the 18.38% capacity factor is applied to PV capacity data collected from SB 1 applications and City permits. Graph 14 details the estimated monthly distributed solar  generation  in  2016,  and  its  effect  on  APU  energy  demand.  The  total  estimated  effect  on  energy demand using the proposed methodology for 2016 was 26,235 MWh, or a 1% reduction of Anaheim’s total energy demand.

‐

0.20 0.40

0.60 0.80

1.00 1.20

1.40 1.60

1.80 123456789 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 MWh
Jan Feb Mar Apr May June
July Aug Sept Oct Nov Dec
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 56 ends

Graph 14: Estimated Distributed (Behind‐the‐Meter) Solar PV Impact to Energy Demand

The  profile  for  distributed  solar  generation  can  also  be  estimated  using  the  convention  center  solar shape.  Graph  15  details  the  estimated  average  hourly  shape  for  total  distributed  solar  generation  for 2016, 2019 and 2030.

Graph 15: Estimated Average Hourly Shape for Distributed Solar Generation

The estimated solar shape was applied to the daily energy demand forecast to estimate the future peak shift  for  APU  energy  demand.  Assuming  distributed  solar  grows as  expected;  there  is  a  corresponding peak shift from hour 17 to 19 by 2030 as depicted in Graph 16 below. Peak demand is estimated to shift from hour 17 in 2016 to hour 18 in 2019, and hour 19 by 2030.

‐
50 100
150
200
250
300
GWh
Net Energy Demand PV Energy Demand
‐
10 20
30 40
50 60
1 2 3 4 5 6 7 8 9 1 01 11 21 31 41 51 61 71 81 92 02 12 22 32 4 MWh
2016 2019 2030
2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 57 ends

Graph 16: Peak Demand Shift

In  addition  to  shifting  the  traditional  peak  hour,  the  solar  PV  penetration  will  also  result  in  a  peak reduction  of  approximately  2  MW  every  year  throughout  2030.  Graph  17  details  the  estimated cumulative impact to peak demand due to solar growth.

Graph 17: Estimated Annual Peak Demand

Clean Peak Analysis
Aligning renewable generation with peak demand is a current industry challenge.

In  an  effort  to  meet  peak  demand  with  renewable  or  other  clean  energy  resources,  APU  takes  into consideration its existing renewable generation portfolio, efficiency of Grid operations, energy storage options  and  forecasts,  distributed  energy  resources,  and  energy  reduction  measures  such  as  energy 150
200
250
300
350
400
450
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MWh
Average Load August 2016 2019 2030
500
510
520
530
540
550
560
570
580
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Base Peak Demand Adjusted Peak Demand w/Solar PV Growth 2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 58 ends

efficiency  and  demand  response  programs.  The  comprehensive  consideration  ensures  APU  meets energy  and  reliability  needs  during  its  peak,  while  reducing  the  need  for  new/additional  electric generation, distribution, and transmission resources.

During  certain  times  of  the  year,  system  peak  can  be  served  with  a  higher  percentage  of  renewable energy.  As  an  example  in  April  2017,  the  Intermountain  Power  Plant  (IPP)4 underwent  a  scheduled maintenance outage for most of the month, which caused a significant reduction in generation capacity.

The  energy  need  was  replaced  by  two  firmed  and  shaped  renewable  contracts,  supplemented  with ample wind and hydro energy that was available during the same month. On April 16, 2017, APU’s 246 MW peak was served by 80% or 195 MW of renewables.

Graph 18: Renewables Serving Peak Demand – Day with High Renewables & Low Energy Demand

During  other  times  of  the  year,  serving  the  peak  with  renewable  energy  faces  its  challenges.  This  is generally  due  to  a  higher  peak  demand,  renewable  resource  availability,  and  CAISO  dispatch  signals.

APU  employed  its  voluntary  residential  demand  response  events  in  summer  2017  to  reduce  energy demand; however, additional energy was still needed in the hot and humid summer days.

On September 1, 2017, APU reached a system peak of 562 MW; more than double the system peak in the previous example. During the peak hour, only 11% or 60 MW of renewable energy was available to meet the demand for various reasons, which included:
 De‐rated landfill and geothermal generating units due to extreme heat;  Small hydro producing less than 60% of April energy output; and  Near zero wind output.

Also during the peak day, the CAISO dispatched APU’s fossil fuel units to meet not only the APU peak, but  also  the  system  demand  of  other  California  load  serving  entities.  The  orange  bars  in  Graph  19 indicate the thermal (non‐renewable) energy APU sold into CAISO market, per market dispatch signals.

4 Details of the power plant may be found in Section VIII.B. Generation and Transmission Resources Renewables
195 MW
Peak
246 MW
‐
100
200
300
400
500
600
HE01
HE02
HE03
HE04
HE05
HE06
HE07
HE08
HE09
HE10
HE11
HE12
HE13
HE14
HE15
HE16
HE17
HE18
HE19
HE20
HE21
HE22
HE23
HE24
Megawatt‐hours (MWh)
High Renewables/Low Energy Demand
April 16, 2017
Renewable | Retail Thermal | Retail Thermal | Wholesale Utility Customer Load 2018 Integrated Resource Plan
VI. Energy Demand and Peak Forecasts

Anaheim Public Utilities

Page 59 ends

Graph 19: Renewables Serving Peak Demand – Day with Low Renewables & High Energy Demand

Other  than reducing peak demand  through efficiency  measures  and  demand  response programs, APU takes  into  consideration  how  renewables  or  other  zero  emission  resources  may  provide  more  clean energy  during  the  peak  hour.  Energy  storage  is  periodically  evaluated;  in  addition,  the  location  and generation  profile  of  new  renewable  projects  are  also  considered.  The  goal  is  to  acquire  renewable projects with generation profiles most aligned with APU’s energy demand profile.

Extreme Weather Impacts
Peak  demand  estimates  are  obtained  for  the  extreme  weather  analysis  using  the  load  factor methodology, as described in VI.B.2. DEVELOPING THE PEAK FORECAST. Graph 20 displays the impact of extreme  temperatures  on  peak  demand.  On  average,  peak  demand  is  estimated  to  be  14  MW  higher with  extremely  high  temperatures,  with  the  highest  impact  of  18  MW  in  October.  Similarly,  peak demand is estimated to be 12 MW lower with extremely low temperatures, with the highest impact of 15 MW in October.

Graph 20: Forecasted Peak demand with Extreme Temperatures

Renewables
60 MW
Peak
562 MW
‐
100
200
300
400
500
600
700
800
HE01
HE02
HE03
HE04
HE05
HE06
HE07
HE08
HE09
HE10
HE11
HE12
HE13
HE14
HE15
HE16
HE17
HE18
HE19
HE20
HE21
HE22
HE23
HE24
Megawatt‐hours (MWh)
Low Renewables/High Energy Demand
September 1, 2017
Renewable | Retail Thermal | Retail Purchase | Retail CAISO Market Renewable | Wholesale Thermal | Wholesale Utility Customer Load 250
300
350
400
450
500
550
600
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
MW
High Temp Expected Temp Low Temp
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 60 ends

VII.  RESOURCE  PORTFOLIO  EVALUATION
After  forecasting  the  energy  and  peak  demand,  the  supply  side  analysis  is  detailed  in  this  section  to answer  one  question:  What  is  the  optimal  resource  mix  to  supply  the  forecasted  energy  and  peak demand given APU’s planning goals of sustainable resources, high reliability and affordable rates? This  section  starts  with  basic  considerations,  such  as  how  to  transition  from  fossil  fuels  to  clean renewable energy and determining the performance measures to evaluate available supply‐side options.

Candidate  portfolio  scenarios  were  developed  based  on  current  technology  and  market  intelligence regarding  resource  availability.  These  supply‐side  options  were  then  screened  to  filter  out  the  non‐ viable scenarios given APU’s planning goals, and the remaining scenarios were analyzed using extensive quantitative  production  cost  modeling  analysis.  The  model  outputs  were  scored  and  stress  tests performed before a final portfolio was recommended. Graph 21 below summarize the selection process used to choose the optimum resource additions needed to satisfy customer demand and reliability and sustainability goals:

Coal to Clean Energy Transition

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 61 ends

Graph 21: Selection Process of the Optimum Resource Portfolio

The selection process started with Section A. Portfolio Consideration and Performance Measures followed by Section B, the consideration of Resource Options. Components of the model analysis are outlined in Sections C. Model Analysis – Production Cost Model, D. Model Analysis – Input Assumptions, and E. Model Analysis – Output Evaluation. The resource portfolios under evaluation also went through a series of Stress Testing in Section F, before the optimum portfolio is recommended in Section G.

A. Portfolio
Considerations &
Performance
Measures
•Optimize Existing
Resources
•GHG Reduction;
50% Renewables
•Regulatory
Compliance
•Reliability;
Diversification
•Expected Cost;
Market Risk
B. Resource
Options
•Natural Gas
Resources
•Market Purchases
•Renewable
Resources
•Baseload,
Intermittent or
Balanced
•Energy Storage
C. D. & E. Model
Analysis
•Input
Assumptions
•Resource
Properties,
Market Outlook
•Dispatch Model
Simulation
•Output
Evaluation
•GHG Reduction,
Renewable %,
Reliability,
Production Cost
F. Stress Testing
•Market Volatility
•High/Low Fuel,
Energy, Carbon
Markets
•Customer
Demand Variation
•High/Low
Temperature,
Solar, EV, Energy
Efficiency
G. Optimum
Portfolio
Recommendation

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 62 ends

A. PORTFOLIO  CONSIDERATION  AND PERFORMANCE  MEASURES

A.1.  COAL‐TO‐CLEAN  ENERGY  TRANSITION
Prior to the heightened awareness about carbon intensive fuels on the environment as a result of  GHG emissions, APU was fully resourced to meet local energy demand with long‐term, low‐cost, and base‐loaded coal‐fired power plants. Coal‐fired power plants were historically a preferred resource nationally due to the abundance of coal as  a  fuel,  its  low  cost,  and  the  reliable  coal  generation  technologies  available  to produce  electricity.  Also,  in  the  1980s,  nuclear  energy  was  out  of  favor,  due  to  the waste  issue  and  the  associated  capital  risk,  and  it  was  illegal  to  use  natural  gas  for power  generation  due  to  its  scarcity  and  higher  value  as  a  space  heating  fuel.  For these  reasons,  APU  invested  in  two  coal  facilities  that  served  APU  customers  very well for several decades, and approximately two‐thirds of APU’s energy needs were met by these two coal‐fired power plants.

APU has actively transitioned from the carbon intensive resource mix to clean renewable energy since 2003,  as  it  has  increased  renewable  energy  from  1%  to  29%  while  reducing  coal  power  from  73%  to 32%.  Today,  APU’s  resource  stack  is  very  different  from  the  historical  view,  with  a  much  greater percentage  of  retail  energy  demand  met  by  sustainable  energy.  The  following  graphs  show  change  in APU’s power supply resource stack over the past decade, from 2006 to 2016:

Graph 22: APU Resource Stack in 2006

Note: Generation above the retail energy demand was sold into the CAISO wholesale energy market.

0 500
1,000
1,500
2,000
2,500
3,000
3,500
4,000GWh
Purchases
Coal
Natural Gas
Nuclear
Large Hydro
Renewable
Retail Energy Demand

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 63 ends

Graph 23: APU Resource Stack in 2016

Note: Generation above the retail energy demand represents energy sold into the CAISO wholesale energy market.

Roughly one‐third of APU’s 2017 energy supply still came from two coal plants – San Juan Power Plant and Intermountain Power Project (IPP). APU successfully negotiated the divestiture of the San Juan coal plant at the end of 2017, which was 5 years prior to the original contract termination date. APU has also taken action to allow its IPP coal contract to expire without renewal effective 2027, at which time APU will have divested of all coal resources.

The divested coal resources will need to be replaced prior to 2027 to maintain high reliability, achieve APU’s  sustainability  goals,  comply  with  State  mandates,  and  mitigate  market  price  risk.  To  select  the optimum resource portfolio, which includes the replacement of the divested coal resources, APU used quantitative  performance  measures  and  production  cost  modeling  to  evaluate  the  portfolio  scenarios pursuant to its planning goals, as briefly mentioned in Section III. Planning Goals

B.2. PORTFOLIO  PERFORMANCE  MEASURES
APU’s mission is to be an agile, customer‐focused, water and power utility operating in an ever‐changing world providing reliable, high quality, environmentally sustainable, and competitively priced water and power  and  delivering  the  maximum  value  to  our  customer‐owners  in  order  to  preserve  Anaheim’s health and prosperity.

The  integrated  resource  planning  process  maintains  three  main  planning  goals  to  achieve  the organizational mission: Sustainable Resources, High Reliability, and Affordable Rates. 0 500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500GWh
Purchases
Coal
Natural Gas
Large Hydro
Renewable
Retail Energy Demand
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 64 ends

Achieve at Least a 50% RPS
The RPS is measured by the percentage of renewable energy delivered to serve retail load. Portfolios considered must contain at least 40% eligible renewable energy by 2024, 45% by 2027 and 50% by 2030.

In addition, per the RPS statute, 65% of APU’s RPS obligation in any given year must come from long‐ term contracts (i.e., greater than 10 years in length).

APU has procured a sufficient amount of renewable energy contracts to meet RPS compliance up to year 2025. However, in order to meet renewable compliance obligations post‐2025, APU will need to either extend  the  terms  of  its  current  renewable  contracts,  or  procure  new  contracts.  Graph  24  details  the historical and planned renewable compliance targets.

Graph 24: Historical and Planned Renewable Energy

Sustainable
Resources
• 50% RPS
• 40% GHG
Reduction
•R e g u l a t o r y Risk
High
Reliability
•R e s o u r c e
Adequacy
• Portfolio
Diversification
Affordable
Rates
•E x p e c t e d Cost
•M a r k e t Risk
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 ‐
500
1,000
1,500
2,000
2,500
GWh
Renewable Energy Retail Sales Renewable Target
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 65 ends

Greenhouse Gas Emission Reductions
Greenhouse gas emission reductions are measured by the percent of GHG reduction for the overall resource portfolio. Portfolios considered must meet the GHG emissions reduction targets ultimately established by the California Air Resources Board (CARB) that achieves the economy‐wide greenhouse gas emissions reductions of 20% below 1990 levels by 2020, and 40% below 1990 levels by 2030.

With  the  planned  exit  of  IPP,  APU  is  on  track  to  meet  its  internal  GHG  reduction  planning  goals  of 480,000 MTCO2e by 2020 and 920,000 MTCO2e by 2030, a 20% and 40% reduction, respectively. Graph 25 details the planned GHG reductions with and without the GHG emissions reductions expected from vehicle  electrification.  Due  to  the  divestiture  of  coal  units,  APU  is  on  track  to  meet  internal  GHG reduction planning goals without any changes to its remaining power resouces. Since the replacement energy  is  needed  due  to  APU’s  exit  from  IPP,  it  will  be  replaced  with  non‐emitting  resouces,  the estimated  GHG  reduction  as  displayed  in  Graph  25  will  remain  consistent  for  any  renewable replacement options.

Graph 25: Planned GHG Reduction

Regulatory Risk
Regulatory Risk measures the ability to remain compliant with current and anticipated future legislative or regulatory changes. The State’s RPS targets have steadily increased over the past several years; therefore, this IRP considers the likelihood of higher renewable energy requirements in the future. 600
700
800
900
1,000
1,100
1,200
1,300
1,400
1,500
1,600
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Metric Tons of CO2e (Thousands)
Total Emissions Emissions with EV
IPP Exit
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 66 ends

For example, Senate Bill 100 was introduced in the 2017 legislative session requiring electric utilities to achieve a 60% RPS by 2030. It also contains language seeking to require that eligible renewable energy resources  and  other  zero  GHG‐emitting  resources  supply  100%  of  retail  energy  sales  no  later  than December 31, 2045. As of the writing of this IRP, the bill remains active in the legislature.

The optimum portfolio should have enough flexibility to absorb additional renewable purchases beyond the current 50% RPS requirement. Also, the optimum portfolio should be sufficiently diversified so that APU minimizes technological risk where one technology becomes obsolete or less cost‐effective.

Resource Adequacy (Reliability)
Resource Adequacy is measured by the ability to achieve a 15% reserve margin above the system peak forecast while meeting forecasted local and flexible capacity requirements.

Resource portfolios not achieving this measure are still included for consideration by identifying future capacity  shortages
and  planned  capacity  purchases.  Costs  for  capacity  purchases  are  added  to  the portfolio.

Graph 26: Available Resource Adequacy (RA) System Capacity

Graph 26 illustrates the resources APU may use to meet Resource Adequacy requirements. Although APU exited San Juan in 2017, ample capacity from renewable resources is available to replace the 50 0 100
200
300
400
500
600
700
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Intermountain Units 1 and 2 Magnolia Peak Magnolia Base Canyon Power Plant Anaheim CTG Geothermal Raser Thermo
Ormat Geothermal Bowerman MWD Small Hydro
Brea Power Partners System Capacity Requirement
250 MW Capacity Needs
after IPP Divestiture
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 67 ends

MW previously provided by San Juan. When APU exits IPP in 2027, 250 MW of capacity will need to be procured to ensure resource adequacy and system reliability. The new capacity can be in the form of new energy resources with capacity, capacity‐only purchases, or both.

Canyon Power Plant and the Bowerman and Brea landfill gas‐to‐energy plants are long‐term and reliable resources  located  in  and  near  Anaheim,  and  they  provide  more  than  100%  of  the  local  and  flexible generation capacity required by the CAISO.

The  Resource  Adequacy  generation  capacity  needed  after  2027,  upon  the  expiration  of  the  IPP  coal contract, is system‐wide capacity that may be produced anywhere in the 14 western states as long as it is  deliverable  to  California.  Current  system‐wide  capacity  markets  indicate  that  this  product  is abundantly  available  at  a  much  lower  cost  than  building  new  peaking  power  plants  or  utility  scale energy storage facilities. This is due to the great number of new renewable energy facilities being added system‐wide.

APU plans to procure the requisite Resource Adequacy at least two years prior to the expiration of the IPP  contract  through  competitive  solicitations;  however,  APU  will  continue  to  monitor  the  capacity markets as compared to the cost of constructing new capacity facilities locally. Given the relatively small amount  of  Resource  Adequacy  capacity  needed  by  APU,  the  abundance  of  capacity  available  for purchase, the Regulatory Risk of constructing new natural gas peaking power plants that may become obsolete  if  State  law  requires  100%  emission‐free  resources,  and  the  potential  for  a  technological breakthrough  that  would  significantly  reduce  the  cost  of  energy  storage,  APU  does  not  recommend committing to new Resource Adequacy facilities at this time. Also, should the cost of Resource Adequacy capacity  increase  significantly  prior  to  2027,  APU  has  the  option  of  investing  to  extend  the  life  of  the Kraemer Power Plant or build new generation facilities at the Canyon Power Plant site.

Portfolio Diversification
Portfolio diversification is measured by the different types and length of resource investment within the portfolio. A diversified resource portfolio increases flexibility, reliability, and overall performance.

APU’s  2018  renewable  portfolio  consists  of  15%  intermittent  resources  and  85%  baseload  resources.

The baseload resources are very reliable and do provide local Resource Adequacy capacity, but the cost of these resources is now significantly greater than intermittent resources such as solar and wind and APU’s  local  capacity  requirements  are  satisfied  with  existing  resources.  Due  to  APU’s  substantial investment in baseload renewable resources in the early years of the RPS Program, diversity is now an important consideration in the development of the optimum resource portfolio.

Expected Cost
Expected Cost is measured by the total cost to supply power.  Each resource portfolio is evaluated with a
goal to minimize impacts on customer bills and to serve customers at just and reasonable rates. 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 68 ends

As previously discussed, APU has been and continues to be fully resourced to meet local demand with long‐term baseload power plants. Any costs associated with additional resource procurement necessary to meet environmental goals must be carefully considered and prudently managed. A key consideration in  selecting  the  optimum  resource  portfolio  is  leveraging  existing  resources  and  minimizing  customer impact.

Market Risk
Market Risk is measured by percentage of energy APU must purchase from the wholesale market, and the portfolio’s ability to withstand market price volatility.  The financial exposure of the overall resource portfolio increases when a larger percentage of energy is procured from the wholesale market.

With  236  MW  of  capacity,  IPP  meets  the  largest  portion  of  APU  baseload  energy  needs,  with  the remainder baseload energy demand supplied by the natural gas and renewable generation facilities. The predictable  cost  structure  of  a  baseload  unit  protects  the  resource  portfolio  from  price  swings  in  the wholesale  market.  The  replacement  energy  needs  resulting  from  APU’s  exit  from  IPP  will  come  from renewable energy resources. Because of the intermittent nature of variable renewables (i.e., wind and solar), financial exposure must be evaluated when considering replacement energy from these types of resources.

Intermittent renewable energy resources such as wind and solar have seasonal and hourly generation profiles that are not always aligned with energy demand, and can be unpredictable at times due to changing weather patterns. Due to this variability in production, there are times when generation levels exceed energy demand, resulting in decreases in market prices and revenue from the sales of energy.  Conversely, at times when energy demand exceeds the amount of generation available, market prices and the purchase of energy to meet energy demand will increase.

Modeling  “stress  tests”  are  introduced  in  Section  F.  Stress  Testing  to  ensure  the  optimum  portfolio outperforms the alternatives under all market cost and load growth/reduction scenarios.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 69 ends

B. RESOURCE  OPTIONS
B.1.  IPP REPLACEMENT  OPTIONS
With extensive quantitative analysis, this IRP examines several scenarios for replacing the energy resulting from the exit of coal resources. Replacing the coal power plants with a new natural gas power plant or wholesale market purchases would be carbon heavy and costly.   APU will still have a need to purchase renewable energy to meet the  State’s  environmental  goals;  therefore,  replacing  energy  needs  resulting  from APU’s  exit  from  coal  power  plants  with  renewable  energy  is  the  most  optimal solution.

Graph 27 shows the screening process used to evaluate the options for replacing the IPP coal plant. Replacing IPP with a natural gas power plant (Scenario 1) or wholesale market  purchases  (Scenario  2)  would  still  be  carbon  heavy  as  compared  to renewables and would be costly because APU would still need to purchase renewable energy to meet the State’s 50% mandate, resulting in “over‐procurement.”

Graph 27: IPP Replacement Options

Graph 28  shows  that  a  new  natural  gas  plant  is  not  viable  given  APU’s  sustainability  goals  and  State regulatory requirements. As an example, the Variable Portfolio is one of the renewable portfolios being evaluated  to  replace  IPP.  It  is  more  costly  to  maintain  a  natural  gas  power  plant  while  also  acquiring renewable energy to meet the sustainability goal.

IPP Coal
Replacement
Scenario 3:

Renewables
Lower Costs;
Sustainable
Scenario 2:

Wholesale Market
Purchases
Over‐Procurement
Carbon Heavy
Scenario 1:

Gas Unit
Over‐Procurement
Carbon Heavy

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 70 ends

Graph 28: New Power Supply Options – Cost Comparison

*Net power supply costs excludes transmission and wholesale energy revenues

B.2. RENEWABLE  OPTIONS
Determine Renewable Generation and Capacity Needs
Staff  went  through  the  following  steps  to  determine  the  renewable  generation  and  capacity  needs  to meet RPS targets.

1. Determine Annual RPS Targets
In developing the candidate portfolios, the first step was to calculate the amount of renewable energy needed  to  meet  the  RPS  targets.  RPS  targets  are  statutorily  established  and  in  the  case  of  publicly owned  utilities  like  APU,  are  enforced  by  the  CEC.   These  targets  are  calculated  as  a  percentage  of customer retail energy demand.

Retail Energy Demand Forecast * RPS % = Renewable Energy Required Due to the inconsistent nature of renewables development and energy production, there may be years when APU exceeds its projected RPS targets. To preserve the value of the renewable energy resources, the  Legislature  and  State  agencies  recognize  the  ability  to  use  any  excess  renewable  procurement  for future  compliance  through  the  “banking”  of  excess  renewable  energy  credits  (“REC”)  as  they  are produced. APU has banked RECs produced in excess of RPS compliance requirements to date, intends to continue  banking  surplus  RECs  for  future  use,  and  will  use  such  surplus  to  help  satisfy  its  future  RPS compliance targets in the most cost‐effective manner possible. $245,000
$265,000
$285,000
$305,000
$325,000
$345,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Thousands
New Power Supply Options ‐ Cost Comparison
Variable Portfolio New Natural Gas Plant
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 71 ends

As  detailed  in  the  green  bar  on  Graph  29,  the  renewable  generation  forecast  indicates  that  APU  will have  procured  a  sufficient  amount  of  renewable  energy  to  meet  its  RPS  obligations  through  2026.  In order  to  meet  compliance  obligations  after  2026,  APU  will  need  to  negotiate  extensions  of  existing contracts or procure new renewable resources.

2. Determine Long‐Term Contract Obligation
Pursuant  to  SB  350,  the  RPS  Program  also  requires  that  starting  in  the  year  2021,  65%  of  APU’s  RPS obligations must be met by renewable resources under contract for more than 10 years in length, shown by the blue dotted line on Graph 29. Currently, most of APU’s renewable energy comes from resources under  long‐term  contracts.  However,  post‐2026,  APU  will  need  to  secure  additional  long‐term renewable  contracts  in  combination  with  short‐term  renewable  purchases  in  order  to  meet  this compliance obligation.

Graph 29: Simulated RPS Compliance Requirement

3. Determine New Contract Size and Implementation Dates The next step in the development of candidate portfolios for consideration was to identify a timeline for new contract implementation and capacity purchases to replace the capacity lost with the divestiture of IPP. It is less expensive to purchase capacity than to over‐procure renewable generation. As such, future renewable  contracts  were  incrementally  layered  into  APU’s  portfolio  to  meet  renewable  targets,  and the capacity shortfall is planned to be covered with capacity purchases as discussed under the Resource Adequacy performance measure section.
0 200
400
600
800
1,000
1,200
1,400
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GWh
Forecasted RECs w/Current Contracts RPS Obligation Long Term Contract Obligation 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 72 ends

APU  identified  replacement  energy  from  the  responses  to  the  SCPPA  Request  for  Proposals5 for renewable  generation.  This  list  was  developed  based  on  the  knowledge  of  expected  costs  and availability of a larger list of possible clean power supplies. The likely resources are:
•  Wind (intermittent)
•  Solar (intermittent)
•  Geothermal (baseload)
•  Biomass (baseload)
•  Landfill Gas (baseload)
Capacity  calculations  vary  by  the  operating  characteristics  of  the  renewable  technology.  Baseload renewables have a much higher capacity factor than intermittent resources such as wind and solar (95%, 27%,  and  25%,  respectively).  Table  4  below  is  an  example  of  the  estimated  capacity  required  from  all baseload, solar, or wind  contracts. As  expected,  there is a much  higher amount of  megawatt capacity that must be procured if selecting intermittent resources.   If APU procured only baseload renewables, it would need to procure a 15 MW contract, as opposed to 45 MW of solar or 55 MW of wind to generate the same amount of energy as a 15 MW baseload generation resource. Table 4 summarizes the amount of renewable capacity required for each resource type to meet RPS energy requirements:

Table 4: Renewable Capacity Required to Meet RPS Target Baseload Contracts Only (MW)  2027  2028  2029  2030
Baseload 1  5  5  5  5
Baseload 2     5  5
Baseload 3       5
Total Baseload  5  5  10  15

Solar Contracts Only (MW)  2027  2028  2029  2030
Solar 1  10  10  10  10
Solar 2     25  25
Solar 3       10
Total Solar  10  10  35  45

Wind Contracts Only (MW)  2027  2028  2029  2030
Wind 1  15  15  15  15
Wind 2     25  25
Wind 3       15
Total Wind  15  15  40  55

5 http://www.scppa.org/page/RFP‐Request‐for‐Proposals‐Archives 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 73 ends

Renewable Portfolios Evaluated
 Baseload Portfolio (Baseload Renewables)
The  first  candidate  portfolio  replaces  coal  generation  with  baseload  renewable  resources  such  as geothermal,  biomass  or  biogas.  Baseload  resources  are  reliable  and  stable,  which  translates  to  less capacity  needed  to  generate  the  same  amount  of  energy  as  intermittent  resources.  However,  these resources  are  expensive  compared  to  intermittent  resources  like  wind  or  solar.  APU’s  most  recent biogas resource price is $91/MWh, compared to recent offers of $37/MWh for solar and $45/MWh for wind resources in 2017.
 Mixed Portfolio (50% Intermittent/50% Baseload Renewables) The second candidate portfolio replaces coal generation with 50% intermittent renewable resources and the other 50% with baseload renewable resources. This option provides the benefit of stable generation and lower cost resources.
 Variable Portfolio (100% Intermittent Renewables)
The third candidate portfolio replaces coal generation with fully intermittent renewable resources and provides the advantage of procuring the lowest cost renewable resources currently available. It is called the  “Variable”  Portfolio  due  to  the  fact  that  the  existing  APU  renewable  mix  is  mostly  composed  of baseload  resources.  Adding  more  intermittent  resources  would  inherently  make  the  portfolio  more balanced.

The  candidate  portfolios  described  are  referred  to  from  here  on  forward  as  the  Baseload  Portfolio, Mixed Portfolio and Variable Portfolio, respectfully.

IPP
Replacement
Variable Portfolio:
100% Intermittent
Mixed Portfolio:
25% Wind
25% Solar
50% Geothermal/Biogas
Baseload Portfolio:
100%
Geothermal/Biomass/Biogas
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 74 ends

B.3. ENERGY  STORAGE
Energy storage may be used to facilitate the integration of unpredictable intermittent resources such as wind and solar energy; however, energy storage itself is not a renewable resource. APU is a distribution utility operating under the CAISO supply/demand balancing authority, and, as such, the CAISO requires APU  to  provide  certain  levels  and  types  of  Resource  Adequacy  capacity  given  its  profile  of  resources used  to  serve  APU’s  load.  The  baseload  renewable  resources  procured  by  APU  provide  adequate Resource Adequacy capacity, and energy storage  has not been  required to integrate APU’s renewable resource  portfolio.  Nevertheless,  energy  storage  may  play  a  more  significant  role  in  the  future  should technological breakthroughs make energy storage a viable replacement for the lost Resource Adequacy capacity upon the expiration of the IPP coal contract in 2027.

Pursuant  to  the  requirements  of  Assembly  Bill  2514  (Skinner,  Chapter  469,  Statues  of  2010),  APU submitted  to  the  CEC  on  September  30,  2017  its  latest  re‐evaluation  of  energy  storage  (ES)  system procurement  targets.  Please  see  the  City  of  Anaheim’s  Energy  Storage  Resolution  No.  2017‐142,  Staff Report,  and  Updated  Energy  Storage  System  Plan  for  the  detailed  evaluation  on  the  CEC  website  at AB2514 ‐ Anaheim6 or AB2514 ‐ CEC ‐Energy Storage7.

Currently APU has a procurement target of up to 11 MW of energy storage (ES) by December 31, 2026, subject  to  Anaheim  City  Council  authorization  for  future  capital  expenditures.  The  11  MW  target consists of a 1 MW ES pilot project at Harbor Substation, to be completed by December 31, 2021, and depending on the results of the pilot project and future ES technologies, up to 10 MW of additional ES installation at Canyon Power Plant by December 31, 2026.

Based  on  APU’s  analyses,  ES  currently  has  a  limited  effect  in  its  ability  to  shift  energy  from  one  time period to another in the CAISO wholesale electricity market. However, APU studied the potential for ES to provide ancillary services. The costs of regulation and spinning reserves in the CAISO market for APU have increased significantly from 2014 to 2016. Since ancillary services are much smaller in megawatt volume  compared  to  energy  products,  current  battery  ES  technologies,  particularly  the  Lithium‐Ion technology, may be a potentially viable and cost‐effective means to self‐provide ancillary services. The 1 MW  ES  pilot  project  and  continued  monitoring  of  ancillary  service  costs  will  help  determine  the feasibility  of  these  benefits  for  future  ES  projects,  and  whether  or  not  market  conditions  dictate potential acceleration of upcoming projects.

APU considers taking incremental steps towards integrating ES within its local grid to be prudent as solar and  wind  generation  is  projected  to  increase  over  time  resulting  in  excess  generation  during  certain times of the day. The 1 MW ES pilot project will allow APU to gain first‐hand experience and validate the conceptual  assumptions  for  future  ES  deployments.  With  the  pilot  project  being  completed,  APU expects  to  have  more  data  and  experience  on  how  to  optimize  the  operation  of  ES  and  demonstrate value to APU customers prior to seeking City Council approval on future ES procurement.

6 http://www.energy.ca.gov/assessments/ab2514_reports/City_of_Anaheim/ 7 http://www.energy.ca.gov/assessments/ab2514_energy_storage.html 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 75 ends

C. MODEL  ANALYSIS  – PRODUCTION  COST  MODEL
The Public Utilities Code Section 9621(c)(1) requires the IRP to address procurement for energy efficiency and demand response resources, energy storage, transportation electrification, short‐term and long‐term electricity, electricity‐related, and resource adequacy products.

Energy efficiency, demand response and transportation electrification are considered in the demand forecast and model stress tests.

As previously discussed, APU has established a procurement target of up to 11 MW of energy storage by December 2026, should the 1 MW pilot energy storage project be  deemed  feasible,  suitable  and  cost‐effective.  This  pilot  project  will  be  used  to identify potential uses such as the ability to self‐provide ancillary services. In this IRP, energy storage is incorporated as a component to reduce Ancillary Service charges.

PRODUCTION  COST  MODEL
Considerable  quantitative  analysis  was  performed  to  evaluate  the  candidate  portfolios.  Staff  used  a production cost model to perform hourly chronological unit commitment and evaluated dispatch model runs of how APU would meet its energy demand from the present through 2030. The following graphic shows the elements of the production cost modeling process:

INPUT  ASSUMPTIONS
The  main  input  assumptions  include  energy  demand,  resource  constraints  and  costs,  and  fuel  and carbon prices.

APU’s energy demand was developed under Section VI. Energy Demand and Peak Forecasts. APU has a licensing agreement for a production cost model that contains information of other utility areas’ energy •Energy Demand
•Generation, Transmission
and Other Resources
•Market Conditions (Fuel,
Carbon)
Model Input
Assumptions
•Deterministic Model
Run
•Hourly Dispatch
Model
Simulation
•Resource Dispatch &
Generation
•Wholesale Energy
Prices
•Portfolio Costs
Model Output

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 76 ends

demand  forecast,  and  the  generation,  transmission,  and  other  resources  such  as  energy  storage  and demand response.

The  production  cost  model  has  an  extensive  database  of  the  Western  Interconnect  that  includes extensive grid‐wide data such as hydro conditions, fuel prices, heat rates, maintenance schedules, area demand, emissions, transmission constraints, and variable and fixed unit costs. The model obtains grid‐ wide  data  via  publically  available  sources  from  the  North  American  Electric  Reliability  Corporation (NERC),  the  Energy  Information  Administration  (EIA),  the  Environmental  Protection  Agency  (EPA),  and various balancing authorities. Input assumptions are periodically updated, and the model run results are validated against historical actuals.

These  base  assumptions  can  be  modified  to  allow  utility‐specific  and  detailed  analysis.  APU  updates market  conditions  including  fuel  prices  and  carbon  allowance  costs  to  reflect  the  most  updated information. Key input assumptions are detailed in D. Model Analysis – Input Assumptions.

MODEL  SIMULATION
APU  uses  the  deterministic  model  which  calculates  an  hourly  dispatch  to  simulate  how  the  energy market will dispatch the available resources to meet the region’s estimated energy demand on an hourly basis. A model simulation was performed for each of the candidate portfolios.

Once the input assumptions are incorporated into the database, portfolio simulations or model runs are conducted.  As  an  example,  Graph  30  illustrates  the  system  diagram  for  hour  13  on  January  8,  2017, including  the  energy  flow  from  between  balancing  areas  containing  loads  and  resources.  The  energy demand is displayed within the utility bubble (APU is within the Southern California Edison Company – SCE  –  territory);  the  energy  flows  between  utilities  areas  are  displayed  on  the  arrows  that  depict transmission lines. The colors of the bubbles are indicators of energy prices, with red representing the highest  and  green  the  lowest  energy  prices.  This  process  is  conducted  in  hourly  intervals  for  the  time span specified by the user. The results of the market simulation are retrieved in the output tables of the associated model run.

Deterministic model runs reflect expected or normal conditions for each hour of the year. For example under  deterministic  analysis,  weather,  unit  forced  outages,  gas  prices,  and  intermittent  resource generation are all assumed to be normal on every day of the year. The abnormal or extreme conditions are introduced after the initial model runs, in F. Stress Testing.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 77 ends

Graph 30: System Diagram

MODEL  OUTPUT
With the input assumptions and model simulation, the production cost modeling software will produce the model output including the following:
 Hourly  resource  generation  (MWh):  The  resources  that  are  dispatched  to  meet  the  energy demand during the specific hour and their respective dispatch costs.  Wholesale energy prices: The wholesale energy price for the hour.  Portfolio costs: The fixed, variable, fuel, and carbon costs The  output  for  each  candidate  portfolio  was  evaluated  and  compared  against  each  other  in  E.  Model Analysis – Output Evaluation.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 78 ends

D. MODEL  ANALYSIS  – INPUT  ASSUMPTIONS
Key input assumptions utilized in the production cost model are shown below.

CAISO  UTILITY  SCALE  RENEWABLES
Without a corresponding increase in demand, the surge of utility scale renewables on the  Grid  has  caused  wholesale  energy  prices  to  decline.  Graph  31  illustrates  the average  hourly  energy  price  at  SP‐158 for  2013  through  2017.  Between  2013  and 2017, the average SP‐15 price dropped from $44.9/MWh to $31.5/MWh.

Graph 31: Average Annual SP‐15 Energy Price

While the model has a detailed database of newer renewable resources that are currently in operation, it does not include all planned resources that are expected to come online in the future. By incorporating the planned CAISO interconnection projects for solar capacity and energy storage into the production cost model, the impact of new utility‐scale solar on market prices is captured.

Graph 32 below details the total solar and energy storage capacity that is anticipated to come online for 2017 through 2022. This data was obtained from the CAISO’s published Grid Generation Queue as of June 2017.

8 South of California transmission Path 15, a CAISO pricing zone covering Southern California. $0
$10
$20
$30
$40
$50
$60
$70
HE01
HE02
HE03
HE04
HE05
HE06
HE07
HE08
HE09
HE10
HE11
HE12
HE13
HE14
HE15
HE16
HE17
HE18
HE19
HE20
HE21
HE22
HE23
HE24
Average Annual Energy Price
2013
2014
2015
2016
2017

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 79 ends

Graph 32: CAISO Interconnection Projects

EXISTING  RESOURCES
For each APU resource or contract, staff examined the generic data in the model, and updated model input  where  necessary.  The  information  updated  may  include  heat  rate,  minimum  run  time,  start‐up time,  fuel  type,  variable  costs,  fixed  costs,  emission  factor,  capacity,  capacity  shape,  planned  outages, area, resource beginning and end date, and any other information that impacts the unit dispatch.

NEW RENEWABLE  RESOURCES

1. Renewable Percentage and Contract Terms
Renewable  energy  was  assumed  to  meet  current  regulatory  requirements  of  50%  renewable energy by 2030. Post 2021, 65% of renewable generation was assumed to come from resources with long‐term contracts, defined as 10‐years or longer contract terms.

New  resources  were  layered  into  the  portfolio  over  several  years,  which  strategically  meet  all compliance goals while keeping costs and potential over‐generation minimized.   Table 5 details the  new  resources  layered  into  the  production  cost  model  for  each  scenario.  Contract  terms were assumed to be 20 years.

Table 5: New Resource Capacity by Candidate Portfolio

* Intermittent resources were modeled as wind energy to offset the larger proportion of solar energy in Anaheim’s portfolio post 2027.

1.3 GW

2.2 GW

5.3 GW

8.7 GW

4.7 GW
.4 GW.5 GW

1.5 GW 2.1 GW
.7 GW .4 GW

0.0 2.0

4.0 6.0

8.0 10.0
2017 2018 2019 2020 2021 2022
GW
Planned Solar Capacity
Planned Battery Storage Capacity
Baseload Portfolio  2027  2028  2029  2030
Baseload Contract 1  5  5  5  5
Baseload Contract 2      5  5
Baseload Contract 3        5
Mixed Portfolio  2027  2028  2029  2030
Baseload Contract 1  5  5  5  5
Intermittent Contract 1      10  10
Baseload Contract 2      5  5
Variable Portfolio  2027  2028  2029  2030
Intermittent* Contract 1  15  15  15  15
Intermittent Contract 2     25  25
Intermittent Contract 3       15
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 80 ends

2. Renewable Resource Price
Price  estimates  for  baseload  resources  were  mapped  to  APU’s  most  recent  baseload  resource signed  in  2017.  Price  estimates  for  intermittent  resources  were  mapped  to  the  responses obtained  from  a  2017  Request  for  Proposal  administered  by  Southern  California  Public  Power Authority  (SCPPA).  Resources  assume  a  2%  price  escalation  rate,  following  industry  common practice.

3. Resource Generation Profile
Resource shapes were mapped to existing contracts. Baseload, solar and wind resources were mapped  to  the  most  recent  geothermal,  solar  and  wind  contracts  in  APU’s  portfolio, respectively.

NATURAL  GAS PRICE
Natural gas prices were derived from the Intercontinental Exchange (ICE) Henry Hub gas forward prices and  adjusted  for  basis  differential  between  Henry  Hub  and  the  SoCal  City  Gate.  An  escalation  rate  of

1.65% is applied to develop the expected gas forward curve.

CAP AND TRADE  ALLOWANCE  PRICES
This IRP assumed the continuation of freely allocated carbon allowances for retail sales compliance and APU’s  practice  of  purchasing  carbon  allowances  for  compliance  obligations  associated  with  any wholesale  electricity  purchases  assuming  an  escalation  rate  of  5%  +  the  Bureau  of  Labor  Statistics Consumer Price Index (CPI).
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 81 ends

E. MODEL  ANALYSIS  – OUTPUT  EVALUATION
Market  simulations  were  conducted  for  each  candidate  portfolio.  All  input assumptions  were  consistent,  with  the  exception  of  the  new  renewable  contracts layered  into  each  portfolio.  This  allows  the  most  accurate  comparison  between portfolios.  The  candidate  portfolio’s  model  simulation  results  were  analyzed  and scored based on the six performance measures.

The  analysis  results  are  summarized  in  this  section,  with  supporting  information  in Appendix C – Portfolio Evaluation Details.

50% RPS & 40% GHG REDUCTION
PERFORMANCE MEASURE  VARIABLE  MIXED  BASELOAD
RPS and GHG Compliance  3  1  2
Legend: 3=Best, 2=Middle, 1=Worst
Each portfolio meets RPS  and  GHG  targets, as shown in  Graph  33 and  Graph 34. While  each  portfolio performed equally in meeting renewable portfolio standards, the Baseload Portfolio and Mixed Portfolio produce  slightly  more  GHG  than  the  Variable  Portfolio.  By  2030,  the  Mixed  Portfolio  is  estimated  to produce 10,150 MTco2 more than the Variable Portfolio. The Baseload Portfolio is estimated to produce 2,551 MTco2 more than the Variable Portfolio. Because all three portfolios equally meet RPS compliance targets, they are ranked in order of the best portfolio having the least amount of GHG emissions. Using this raking strategy, the Variable Portfolio performed the best, followed by the Baseload Portfolio and then the Mixed Portfolio
Graph 33: Candidate Portfolio Results: RPS Compliance

0 200
400
600
800
1,000
1,200
1,400
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GWh
RPS Compliance
Variable Portfolio Mixed Portfolio Baseload Portfolio RPS Mandate

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 82 ends

Graph 34: Candidate Portfolio Results: Forecasted GHG Reduction

REGULATORY  RISK
PERFORMANCE MEASURE  VARIABLE  MIXED  BASELOAD
Regulatory Risk  3  2  1
Legend: 3=Best, 2=Middle, 1=Worst
As  discussed  in  Section  A.  Portfolio  Consideration  and  Performance  Measures,  to  achieve  the  least amount  of  Regulatory  Risk,  the  preferred  resource  portfolio  should  have  enough  flexibility  to  absorb additional  renewable  purchases  beyond  the  current  50%  RPS  requirement.  The  preferred  portfolio should also be sufficiently diversified so that APU minimizes the technological risk where one technology becomes obsolete or less cost‐effective.

To address the potential for higher RPS targets, APU recommends the portfolio with the lowest power supply cost and the highest degree of diversification, which is the Variable Portfolio. Please refer to the Expected Cost and Diversification sections below for details.

RESOURCE  ADEQUACY
PERFORMANCE MEASURE  VARIABLE  MIXED  BASELOAD
Resource Adequacy  1  2  3
Legend: 3=Best, 2=Middle, 1=Worst

600
800
1,000
1,200
1,400
1,600
1,800
2,000
2,200
2,400
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Metric Tons of CO2e
(Thousands)
GHG Reduction
Variable Portfolio Mixed Portfolio
Baseload Portfolio GHG Reduction Target
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 83 ends

System Capacity
Although  the  new  resources  in  each  candidate  portfolio  will  contribute  to  system  capacity,  these purchases will not likely be sufficient to meet all resource adequacy requirements. The baseload, solar, and  wind  contracts  are  estimated  to  have  a  capacity  factor  of  95%,  27%,  and  21%,  respectively.  The system  capacity  values  for  each  portfolio  are  summarized  in  Table  5:  New  Resource  Capacity  by Candidate Portfolio.

Graph 35 details the monthly capacity shortfall for each candidate portfolio. In the short run for years 2027‐2030, the capacity shortfall is very similar between all three portfolios. Post 2030, the differences become larger and the Variable Portfolio has the largest shortfall of capacity, followed by the Mixed and Baseload Portfolios, respectively.

Graph 35: Candidate Portfolio Results: System Capacity Shortfall

* Minor differences in capacity shortfall are due to when contracts are layered in.

The  capacity  shortfalls  will  be  supplemented  with  capacity  contract  purchases.  Cost  of  replacement capacity has been estimated at the average 2017 market rate of $2/kW‐month with a 2.5% escalation rate. The Mixed Portfolio is estimated to save $146,730 in capacity purchases through 2030 compared to  the  Variable  Portfolio.  The  Baseload  Portfolio  is  estimated  to  save  $147,133  in  capacity  purchases through 2030 compared to the Variable Portfolio.

Table 6: System Capacity Purchases Cost
CY 2027  CY 2028  CY 2029  CY 2030  Total
Mixed Portfolio ‐ $50,442 ‐ $51,703 ‐ $105,991  $61,406 ‐ $146,730 Baseload Portfolio ‐ $50,442 ‐ $51,703  $4,608 ‐ $49,597 ‐ $147,133 Local Capacity
The  CAISO  local  capacity  requirement  is  determined  by  local  energy  demand  and  transmission availability, and would not vary based on resource portfolio mix. The CAISO local capacity requirement for APU has been below 230 MW in the past few years and remains stable. APU has over 290 MW of natural gas and baseload renewable power plants located within the LA Basin. ‐
100
200
300
400
500
600
700
800
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Variable Portfolio Mixed Portfolio
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 84 ends

During  the  planning  horizon  of  this  IRP,  APU  has  sufficient  local  resources  that  exceed  CAISO’s  local capacity requirements. In the next IRP, APU will consider the local capacity impact of plant retirements and baseload contract expirations.

Graph 36: Local Capacity Resources and LCR Requirement

Flexible Capacity
On average, APU has a monthly flexible capacity requirement of 40 MW, which peaks in December with a capacity requirement of 80 MW. The introduction of additional intermittent resources is estimated to increase the flexible capacity requirements by 3 MW for a 20 MW solar contract and 5 MW for 20 MW wind contract.

As  Canyon  Power  Plant  has  194  MW  of  eligible  flexible  capacity,  APU  has  sufficient  flexible  capacity available  through  Canyon  to  meet  the  additional  requirements  for  flexible  capacity.  The  Baseload Portfolio requires the least amount of flexible capacity, while the Variable Portfolio requires the highest amount. Graph 37 shows that under all scenarios APU has ample Flexible Capacity resources throughout the planning period:

Graph 37: CAISO Flexible Capacity Requirement

0 50
100
150
200
250
300
350
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Local Capacity Resources and LCR Requirement
Brea Power Partners MWD Small Hydro Bowerman
Anaheim CTG Canyon Power Plant LCR Requirement
‐
50 100
150
200
250
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
CAISO Flexible Capacity Requirement
Variable Portfolio Mixed Portfolio Baseload Portfolio Flexi Capacity Available 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 85 ends

The  portfolio  that  requires  the  least  amount  of  capacity  purchases  is  given  the  highest  ranking.  The Baseload  Portfolio  requires  the  least  amount  of  system  capacity  purchases,  followed  by  the  Mixed Portfolio  and  then  Variable  Portfolio.  These  costs  are  included  in  the  net  power  supply  cost  detailed below in the Expected Cost paragraphs.

PORTFOLIO  DIVERSIFICATION
PERFORMANCE MEASURE  VARIABLE  MIXED  BASELOAD
Portfolio Diversification  3  2  1
Legend: 3=Best, 2=Middle, 1=Worst
Graph 38 shows the estimated portfolio diversification for each of the candidate portfolios in 2030. The Variable  Portfolio  offers  the  most  diversification,  with  31%  of  the  renewable  generation  coming  from intermittent resources. This is significantly more diverse than the Mixed and Baseload Portfolios, which only  have  8%  and  1%  intermittent  resources  in  their  portfolios,  respectfully.  As  diversity  increases flexibility,  reliability,  and  performance,  a  higher  grading  is  awarded  for  higher  diversity.  The  highest diversified portfolio is the Variable Portfolio, therefore it is the preferred portfolio under this category.

Graph 38: Candidate Portfolio Results: Portfolio Diversity in 2030

EXPECTED  COST
PERFORMANCE MEASURE  VARIABLE  MIX  BASELOAD
Expected Cost  3  2  1
Legend: 3=Best, 2=Middle, 1=Worst
Intermittent
32%
Baseload
68%
Variable Portfolio
Intermittent
19%
Baseload
81%
Mixed Portfolio
Intermittent
15%
Baseload
85%
Baseload Portfolio
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 86 ends

One  of  APU’s  goals  is  to  minimize  impacts  on  customer  bills  and  to  serve  customers  at  just  and reasonable rates. As such, the total power supply cost for each portfolio is estimated, with lower cost portfolios being awarded a higher rating.

The Variable Portfolio is estimated to be the least cost portfolio, costing $3.2 billion from 2019 through 2030.  The  Mixed  Portfolio  is  estimated  to  cost  an  additional  $15.1  million  compared  to  the  Variable Portfolio,  and  the  Baseload  Portfolio  is  estimated  to  cost  an  additional  $17.4  million  compared  to  the Variable Portfolio.   Grading is awarded in order of the least cost being the best portfolio. The Variable Portfolio scored the highest under this performance measure.

Graph  39  displays  the  total  annual  power  supply  costs  for  each  portfolio.  Each  portfolio  performs similarly in the first several years until 2027, when new contracts come online. In the subsequent years, the cost difference grows exponentially with the Variable Portfolio remaining significantly less expensive than the other two portfolios.

Graph 39: Candidate Portfolio Results: Net Power Supply Cost

*Net Power Supply Cost = Total power supply costs net of transmission revenues and wholesale energy revenues

MARKET  RISK
PERFORMANCE MEASURE  VARIABLE  MIX  BASELOAD
Market Risk  3  1  2
Legend: 3=Best, 2=Middle, 1=Worst
Graph 40 displays the estimated financial exposure from the candidate portfolios. Financial exposure is determined by the percentage of wholesale energy purchases compared to system load as well as the cost impact of wholesale market purchases. The market purchase percentages for the Variable, Mixed, and Baseload Portfolios were very close, averaging 41.21%, 41.20% and 41.27%, respectively, from 2019 $220
$230
$240
$250
$260
$270
$280
$290
$300
$310
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Millions
Net Power Supply Costs
Variable Portfolio Mixed Portfolio Baseload Portfolio
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 87 ends

to 2030; therefore, the portfolios were awarded similar scores for this criteria. However, by 2030, the Baseload  Portfolio  requires  an  additional  $139,000  annually  in  energy  purchases  compared  to  the Variable Portfolio, and the Mixed Portfolio is estimated to require an additional $1.2 million in energy wholesale  energy  purchases.  A  higher  grade  is  awarded  to  the  portfolios  with  the  least  amount  of energy purchases required.

Graph 40: Candidate Portfolio Results: Wholesale Energy Purchase as a % of Total Energy Portfolio

*Slight differences in 2029 and 2030 are due to when contracts are layered in.

It  is  important  to  note  that  market  exposure  is  limited  by  the  generation  capacity  available  from  APU resources.  When  the  wholesale  market  price  rises  above  predetermined  prices,  all  APU  units  will  be dispatched to serve the retail customers. The percentage of market energy purchases will therefore be lower under higher wholesale market price conditions.

SUMMARY
Overall the Variable Portfolio, which replaces lost IPP generation with intermittent renewable resources, performed the best. This portfolio was estimated to have a lower overall power supply cost.  It also has the  least  amount  of  Regulatory  Risk  and  resulted  in  the  most  diverse  portfolio.  Due  to  the unpredictability  of  intermittent  generation,  this  portfolio  posed  the  highest  exposure  to  market  price spikes  and  required  additional  capacity  purchases  to  meet  Resource  Adequacy  capacity  requirements.

However, this market exposure is mitigated by the large amount of existing baseload resources under fixed price contracts. Additionally, an analysis of the system‐wide capacity market indicates that these resources will be readily available at a much lower cost than building new peaking power plants or utility scale energy storage facilities.

The  Mixed  Portfolio,  which  replaces  lost  IPP  generation  with  half  intermittent  and  half  baseload renewable resources, was ranked second best and performed averagely over most of the criteria.

The Baseload Portfolio had the least financial exposure to market dynamics due to the stable nature of baseload  generation.  This  portfolio  was  also  ranked  the  highest  for  Resource  Adequacy  as  baseload 0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Variable Portfolio Mixed Portfolio Baseload Portfolio
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 88 ends

resources have a high capacity value. However, this portfolio was also the most expensive, provided the least amount of portfolio diversification and posed the highest Regulatory Risk.

The following table displays a summary of the performance measure results for each portfolio scenario considered:

PERFORMANCE MEASURE

VARIABLE

MIXED

BASELOAD

Compliance  3  1  2
Regulatory Risk  3  2  1
Resource Adequacy  1  2  3
Portfolio Diversification  3  2  1
Expected Cost  3  2  1
Managed Market Risks  3  1  2
Total  16  10  10
Legend: 3=Best, 2=Middle, 1=Worst

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 89 ends

F. STRESS  TESTING
Additional  analysis  of  the  candidate  portfolios  was  conducted  using  stress  tests  to determine  whether  or  not  the  portfolio  performance  would  change  under  extreme market and load changes. Portfolio simulations were performed for each  candidate portfolio to address the following situations.

G.1.  COMPONENTS  OF THE STRESS  TESTS
TEST 1: EXTREME HIGH COSTS VS. EXTREME LOW COSTS
A market simulation stress test was conducted by simulating portfolio performance under extreme cost situations. Each case uses the extreme high and low estimates of:
resource costs, wholesale energy prices, carbon prices, and utility solar growth into the production cost model.

GAS PRICE
APU owns and contracts power resources that use natural gas as a fuel. In addition, resource dispatch and  market  prices  are  heavily  influenced  by  gas  prices.  Two  standard  deviations  were  added  to  the expected gas price to develop the high gas price scenario. One standard deviation was deducted from the expected gas price to develop the low gas price scenario. Standard deviations were calculated using five‐year historical data of the SoCal Citygate price. Graph 41 shows the gas prices used to stress test the three portfolio scenarios:

Graph 41: Stressed Gas Prices

$0
$1
$2
$3
$4
$5
$6
$7
Jan‐17
Jul‐17
Jan‐18
Jul‐18
Jan‐19
Jul‐19
Jan‐20
Jul‐20
Jan‐21
Jul‐21
Jan‐22
Jul‐22
Jan‐23
Jul‐23
Jan‐24
Jul‐24
Jan‐25
Jul‐25
Jan‐26
Jul‐26
Jan‐27
Jul‐27
Jan‐28
Jul‐28
Jan‐29
Jul‐29
Jan‐30
Jul‐30
$/MMBtu
Low Gas High Gas Expected Gas

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 90 ends

CARBON  PRICE
A high carbon price forecast was developed using a $60 increase from the floor price, as discussed in the rulemaking for Post‐2020 allowance allocation approved by  the  CARB on  July 27, 20179. A  low carbon price scenario was developed using the floor price.

Compared to the Preliminary GHG Price Projections10 used in the 2017 Integrated Energy Policy Report (IEPR)  Demand  Forecast,  APU’s  low  carbon  price  forecast  is  lower  than  the  IEPR’s  low  price  forecast; APU’s  high  price  forecast  is  higher  than  the  IEPR’s  high  price  forecast  with  the  only  exception  in  year 2030. APU chose to use its own extreme carbon price forecast as it stresses the model more. Graph 41 shows the carbon prices used to stress test the three portfolio scenarios:

Graph 42: Stressed Carbon Prices

UTILITY  SCALE  SOLAR  GROWTH
The  high  utility‐scale  solar  growth  scenario  was  developed  assuming  a  25%  increase  of  all  current planned  CAISO  interconnection  projects  and  growth  of  2.5%  annually  post  2022.  The  low  utility  scale solar  growth  assumed  no  future  CAISO  interconnection  projects  would  be  built.  Graph  43  shows  the solar growth rates used to stress test the three portfolio scenarios:

Graph 43: Stressed Utility Scale Solar Capacity Growth

9 See Table 13 Estimated Range of Cap‐and‐Trade Allowance Price 2021–2030 of the CARB California’s 2017 Climate Change Scoping Plan, https://www.arb.ca.gov/cc/scopingplan/scoping_plan_2017.pdf. The Estimated Cap‐and‐Trade Reserve Price was $56.7 above the Floor Price.

For planning purposes, this IRP uses $60 above the floor price for stress testing. 10 TN216271_20170227T161611_Preliminary_GHG_Price_Projections__Energy_Assessment_Division $0
$50
$100
$150
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
$/Mt
High Carbon Low Carbon Expected Carbon
‐
5 10
15 20
25 30
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GW
High Solar Growh Low Solar Growh Expected Solar Growth
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 91 ends

TEST 2: EXTREME HIGH DEMAND VS. EXTREME LOW DEMAND
A high demand scenario was developed by applying extremes to the base demand forecast described in Section V.A. Energy Demand Forecast ‐ Methodology & Assumptions. Energy efficiency and solar growth effects  were  removed  from  the  base  demand  forecast,  and  accelerated  growth  in  transportation electrification was applied. The accelerated EV growth was assumed to be 25% above Governor Brown’s Executive Order B‐16‐12, resulting in 45,000 registered electric vehicles in APU by 2038.

Similarly, a low demand scenario was also developed by applying extremes to the base demand forecast described in Section V.A. Energy Demand Forecast ‐ Methodology & Assumptions. Electric vehicle growth was removed from the base demand forecast, and double energy efficiency goals were applied in addition to accelerated behind‐the‐meter solar capacity installation. The accelerated PV growth was estimated to be 25% above the capacity forecast, and energy efficiency was estimated to be 3% of retail load.

Graph 44 below also displays Policy Initiative Input as a comparison with the demand stress test values.

The  Policy  Initiative  Inputs  incorporates  high  energy  efficiency,  high  consumer  solar  installation,  and high electric transportation growth assumptions to reflect the impact of the State’s policy initiatives on APU load.

Graph 44: Stressed System Load Growth or Reduction (GWh)

G.2.  MODEL  RESULTS  UNDER  STRESS  TESTS
The  following  table  displays  a  summary  of  the  performance  measure  results  after  stress  testing  each portfolio scenario.

2,000
2,100
2,200
2,300
2,400
2,500
2,600
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 High Demand Low Demand Policy Initiative Input Expected Demand 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 92 ends

PERFORMANCE MEASURE

VARIABLE

MIXED

BASELOAD

Compliance  3  1  2
Regulatory Risk  3  2  1
Resource Adequacy  1  2  3
Portfolio Diversification  3  2  1
Expected Cost  3  2  1
Managed Market Risks  3  1  2
Total  16  10  10
Legend: 3=Best, 2=Middle, 1=Worst

The  model  simulation  results  held  constant  for  all  three  portfolios  under  the  stress  tests,  with  the Variable Portfolio performing the best. Below are details of the tests:

Under either stress test of High versus Low Costs or High versus Low Demand, the portfolio scores of the following  performance  measures  stayed  the  same:  Compliance,  Regulatory  Risk,  Resource  Adequacy, Portfolio Diversification, and Financial Exposure. The only components that could change are Expected Cost, or the power supply costs, as detailed below.

Graph  45  displays  the  simulation  results  for  each  candidate  portfolio  under  these  cost  extremes.  The total portfolio cost for each candidate portfolio with high and low cost scenarios are displayed as lines, and total retail revenue is displayed in columns. The Variable Portfolio, shown as the green dotted line, performs the best under both high and low cost market situations. The Baseload Portfolio performs the worst,  with  expenses  being  notably  higher  than  the  Variable  Portfolio,  but  very  close  to  the  Mixed Portfolio  costs.  The  scaling  to  retail  revenue  is  intended  as  a  reference  to  potential  rate  increases needed to supplement the changing portfolio.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 93 ends

Graph 45: Stress Test Results: Extreme High Costs vs. Extreme Low Costs

Similarly,  a  load  simulation  stress  test  was  conducted  by  simulating  portfolio  performance  under extreme load situations. A high load growth extreme incorporates assumptions of high electric vehicle growth,  low  privately  owned  solar  PV,  and  low  energy  efficiency.  A  low  load  growth  extreme incorporates  assumptions  of  low  electric  vehicle  growth,  high  consumer  installed  solar  PV,  and  high energy efficiency. Graph 46 displays the simulation results for each candidate portfolio under these load growth extremes.

Graph 46: Stress Test Results: Extreme High Demand vs. Extreme Low Demand

$240
$260
$280
$300
$320
$340
$360
$380
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Thousands
High Demand Growth vs. Low Demand Growth
LD Retail Revenue HD Retail Revenue Variable Portfolio Mixed Portfolio Baseload Portfolio Variable Portfolio Mixed Portfolio Baseload Portfolio $220
$240
$260
$280
$300
$320
$340
$360
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Thousands
High Market Cost vs Low Market Cost
Retail Revenue Variable Portfolio Mixed Portfolio Baseload Portfolio Variable Portfolio Mixed Portfolio Baseload Portfolio
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 94 ends

The  total  portfolio  cost  for  each  candidate  portfolio  under  high  and  low  load  growth  scenarios  are displayed as lines and total retail revenue is displayed in columns. Estimated retail revenue for the low load growth scenario is displayed as only the dark green column, while estimated retail revenue for the high  load  growth  scenario  is  displayed  as  the  total  of  the  light  green  columns.  The  Variable  Portfolio, shown as the brown dotted line, performs the best under both load situations. The Baseload Portfolio performs  the  worst,  with  expenses  being  notably  higher  than  the  Variable  Portfolio,  but  very  close  to the  Mixed  Portfolio  costs.  The  scaling  to  retail  revenue  is  intended  as  a  reference  to  potential  rate increases needed to supplement the changing load scenarios.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 95 ends

G. OPTIMUM  PORTFOLIO  RECOMMENDATION
The  optimum  portfolio  recommendation  is  the
Variable  Portfolio,  which  would  replace  lost  IPP
generation  with  intermittent  renewable  resources.

The  Variable  Portfolio  performed  the  best  under
normal as well as stress conditions. It is estimated to have  the  least  power  supply  cost,  the  least
Regulatory  Risk,  and  most  diverse  portfolio.  As
intermittent  generation  is  unpredictable,  this
portfolio  may  pose  a  higher  exposure  to  market
price  spikes;  however,  this  risk  is  forecasted  to  be very  small,  as  under  extreme  market  conditions
which  simulated  high  market  prices,  this  portfolio performed the best, including capacity purchases included in the power supply cost.

50% RPS & 40% GHG REDUCTION
As  shown  in  Graph  47,  the  Variable  Portfolio  is  in  compliance  with  current  legislative  and  regulatory requirements, and meets or exceeds renewable and GHG emission reduction targets. It is also provides the most flexibility for adjusting to potential future regulatory or legislative changes, as opposed to the other portfolio options.

Graph 47: Variable Portfolio Meets or Exceeds Compliance Targets

0 200
400
600
800
1,000
1,200
1,400GWh
RPS Compliance
Variable Portfolio RPS Mandate
50%
Renewables
600
800
1,000
1,200
1,400
1,600
1,800
2,000
2,200
2,400
Metric Tons of CO23 (Thousands)
GHG Reduction
Variable Portfolio GHG Reduction Target
40% below 1990 Level
20% below 1990 Level
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 96 ends

RESOURCE ADEQUACY & RELIABILITY
The  Variable  Portfolio  requires  capacity  purchases  to  meet  resource  capacity  requirements.  Graph  48 displays  the  change  in  capacity  from  2019  to  2030.  Capacity  purchases  will  be  acquired  in  2027  to replace  the  system  capacity  lost  with  the  divestiture  of  IPP.  Any  increase  in  flexible  capacity requirements will be met with the Canyon Power Plant.

Graph 48: Variable Portfolio Forecasted Resource Adequacy

DIVERSIFICATION
Graph 49 below displays the changing resource mix under the Variable Portfolio.

0 100
200
300
400
500
600
700
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Capacity Purchases New Intermittent Resources Intermountain Units 1 and 2 Magnolia Peak Magnolia Base Canyon Power Plant
Anaheim CTG Geothermal Raser Thermo Ormat Geothermal
Bowerman MWD Small Hydro Brea Power Partners
System Capacity Requirement
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 97 ends

Graph 49: Resource Mix for Retail Energy Demand: 2018 vs. 2030

The change in resource mix has a corresponding impact on the cost structure in the future years.

Graph 50 displays the power supply cost structure of the portfolio in 2019 and 2030. In total, the net cost to supply power is estimated to be $38 million higher in 2030 compared to 2019, or a 1.34% average annual increase over the next 12 years. The increase is mainly caused by estimated scheduling services fees outside of the power supply.

Scheduling  services  costs  are  expected  to  be  $21  million  higher  in  2030  compared  to  2019.  These charges  consist  of  CAISO  transmission  access  charges,  grid  management  fees,  congestion,  losses, Renewable
29%
Coal
34%Large Hydro
2%
Natural Gas
28%
Purchases
7%
2018 RESOURCE MIX
Wind
24% Small
Hydro
2%
Solar
<1%Biogas
55%
Geothermal
18%
Renewable
50%
Natural Gas
21%
Purchases
27%
Large Hydro
2%
2030 RESOURCE MIX
Wind
17%
Solar
15%
Biogas
52%
Geothermal
16%
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 98 ends

ancillary  services,  and  other  energy  charges,  and  are  expected  to  increase  by  approximately  4% annually. Capacity purchases to meet the resource adequacy requirements are also included here.

The total energy costs will decrease even though each component may move up or down depending on the energy category. The highest increase in cost is wholesale energy purchases to serve load, which are estimated to be $53 million higher in 2030. This increase is due to higher prices and volumes purchased.

The  average  wholesale  market  energy  price  is  forecasted  to  be  $62/MWh  in  2030,  compared  to $36/MWh in 2019. Also, an additional 680 MWh are forecasted to be procured in the wholesale energy in market in 2030, compared to 2019.

As more renewable energy sources are being included into the portfolio, the cost of renewable energy is expected to increase by $16 million. Conversely, the divestiture in fossil fuel resources results in a cost savings totaling $73 million.

Graph 50: Variable Portfolio Power Supply Cost Structure

*Net power supply costs = Total power supply costs net of transmission revenues and wholesale energy revenues

MARKET RISK
While  the  Variable  Portfolio  has  a  higher  market  risk  due  to  exposure  to  market  price  spikes,  it  still performed the best under extreme market conditions.  When energy costs are either extremely high or extremely low, the cost to maintain the Variable Portfolio is consistently the lowest.

1. When the market cost is extremely low, APU purchases the low‐cost energy from the wholesale energy market.
$253 $291
‐$50
$0
$50
$100
$150
$200
$250
$300
$350Millions
Net Power Supply Cost 2019 ‐ 2030
Total Transmission Cost Scheduling Coordinator Costs Conventional Unit Fixed Costs Unit Variable Cost Unit Fuel Cost Debt Service Cost
Wholesale Purchase Cost Renewable Long Term PPA Cost Renewable Short Term PPA Cost Total Wholesale Revenue Total Transmission Revenue Total Net Cost Linear (Total Net Cost)
Renewables and Storage $60M to $76M
Market Purchases $9M to
$62MAverage 1.34%
annual increase
Thermal $151M to $78M
Transmission and Scheduling
Services $76M to $97M
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 99 ends

2. When  the  market  cost  is  extremely  high,  the  APU  resources  are  dispatched  to  meet  retail customer needs, therefore limiting the market risk.

The Variable Portfolio has the best ability to leverage lower market prices, and market risks are capped by the resources available in APU’s portfolio.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 100 ends

H. RATE  IMPACT
ANAHEIM  ELECTRIC  RATES
APU strives to find resources that are cost‐effective and minimize rate impacts on customer utility bills, while  still  meeting  its  compliance  obligations  for  increased  renewables  and  lower  GHG  emissions.  By responsibly divesting of its coal assets and utilizing its peaking resources to integrate more renewable purchases,  APU  has  been  able  to  maintain  affordable  electric  rates.  The  recommended  Variable Portfolio  is  expected  to  help  APU  maintain  affordable  electric  rates  over  the  planning  period  as  net power supply costs are expected to increase by only 1.34% per year, on average, which is less than the expected rate of inflation.

APU strives to provide just and reasonable rates for the service it provides to customers as required by Federal Law and, at the same time in compliance with the California Constitution, the electric rates do not  exceed  APU's  reasonable  cost  to  provide  electric  service  to  its  customers.  Consistent  with  these state  and  federal  mandates,  Section  1221  of  the  Anaheim  City  Charter  requires  that  electric  rates  be based  on  the  cost  of  service  requirements  for  each  customer  class.  The  Anaheim  City  Council  has adopted electric rates in accordance with this requirement and the additional Charter requirements that the electric rates be sufficient to pay for (1) operations and maintenance of the APU's electric system, (2)  the  payment  of  principal  and  interest  on  debt,  (3)  creation  and  maintenance  of  financial  reserves adequate  to  assure  debt  service  on  bonds  outstanding,  (4)  capital  construction  of  new  facilities  and improvements  of  existing  facilities,  or  maintenance  of  a  reserve  fund  for  that  purpose,  and  (5)  other costs.    APU has designed its rate schedules to maintain simplicity and send appropriate pricing signals that encourage prudent consumption of electricity while fully complying with federal, state mandates, and the Charter. To accomplish these objectives, Anaheim offers several base rates as well as optional rates that customers may opt into if they choose.

Base Electric Rates
• Domestic Service (i.e., residential)
• Small Commercial
• Medium Commercial
• Large Commercial
• Industrial
• Agricultural
• Lighting
• Municipal

Optional Rates
• Thermal Energy Storage
• Feed‐In‐Tariff
• Economic Development / Business Retention
• Domestic
Time‐Of‐Use
• Commercial Time‐Of‐Use
• Net Energy Metering
• Domestic Electric Vehicle
2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 101 ends

Generally,  all  costs  of  APU’s  Electric  System,  including  power  supply  costs,  are  recovered  through  the application of these base rates.   Anaheim’s customer rates also include a Rate Stabilization Adjustment (RSA)  which  contains  two  components  (1)  a  Power  Cost  Adjustment  (PCA)  to  recover  fluctuations  in power  supply  costs  and  other  relevant  operational  costs,  and  (2)  an  Environmental  Mitigation Adjustment (EMA) to recover fluctuations in environmental mitigation costs related to the procurement, generation, transmission, or distribution of electricity.   The RSA helps facilitate timely recovery of costs and  thereby  helps  to  maintain  financial  performance  goals  including  debt  service  coverage  ratios  and reserve levels. The  RSA also provides a mechanism  to reduce rates when costs decrease. Additionally, APU  offers  a  low  income  energy  discount  to  seniors,  military  veterans,  and  disabled  customers  who meet specified income thresholds.

APU continuously monitors its rates, rate options, and fees to ensure it provides customers with options that  meet  their  needs  and  that  encourage  adoption  of  environmentally  friendly  technologies.  To  that end,  APU  has  added  a  commercial  electric  vehicle  (EV)  rate  to  encourage  further  adoption  of  electric transit buses, school buses, delivery vehicles, and other fleet vehicles within the City. This effort will also enhance the City’s economic justice efforts by encouraging public transportation agencies to invest in EV fleets that serve a broad array of demographics within the City.

AVERAGE  RESIDENTIAL  RATE COMPARISON
APU’s residential electric rates are competitive with other electric utilities serving Southern California.

APU  residents  benefit  from  electric  bills  that  are  17%  to  35%  lower  than  those  charged  by  Southern California  Edison  and  San  Diego  Gas  &  Electric,  the  only  electric  utilities  that  serve  Orange  County residents, other than Anaheim.

Graph 51: Comparison of Monthly Residential Electric Bills

$‐
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
Anaheim Burbank LADWP Riverside Pasadena SCE Glendale SDG&E Comparison of Monthly Residential Electric Bills
(Based on 500kWh)
Calculated as of July 2017 and includes taxes and surcharges, as applicable. 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 102 ends

APU balances its goal of maintaining low electric rates with the goal of providing reliable electric service to its customers and maintaining the long‐term financial viability of APU. In addition to continuous cost mitigation efforts, this requires periodic rate adjustments to help ensure adequate funding is available for investing in the system and to maintain key financial metrics that support APU’s investment grade credit  rating.  Key  metrics  include  debt  service  coverage  with  a  goal  of  2.0x  coverage  and  sufficient financial reserves with a goal of 90 days operating cash plus $50 million in the rate stabilization account.

The rates APU charges to its customers must be sufficient to recover, among other things, the full cost of providing reliable service and maintaining financial stability.

RATE STRUCTURES
APU’s rate structures include a fixed customer charge, tiered energy rates, the RSA, and an underground surcharge that pays for undergrounding of overhead power lines to improve reliability and beautify the City.  Rates  for  each  customer  classification  employ  these  components  while  medium  and  large commercial  and  industrial  rates  include  a  demand  charge.  Additionally,  time‐of‐use  rates  also  include higher rates  during on‐peak time periods when  the  demand for  energy is high and lower  rates during mid‐peak and off‐peak time periods when the demand for energy is lower.

As  mentioned  earlier,  the  RSA  contains  two  components,  i.e.  the  PCA  and  the  EMA.  The  PCA  is structured  so  that  it  can  increase  up  to  ½¢  per  kWh  in  any  12‐month  period  to  collect  for  changes  in power  production  costs,  purchased  power  costs,  regulatory  compliance  costs,  debt  service,  and  any other costs involved in delivering energy.  The EMA is structured similarly to the PCA in that the annual limit of the increase is ½¢ per kWh in any 12‐month period to collect for environmental mitigation costs such  as  greenhouse  gas  emissions,  purchase  of  emission  credits,  taxes  on  emissions,  and  any  cost differential between renewable power supply and traditional carbon‐based power supply not recovered by the PCA.

With  respect  to  any  RSA  adjustment,  APU  first  considers  costs  of  service  recovery  and  the  impact  on customer bills with a goal of maintaining total electric charges that are competitive with those of other utilities  in  the  region.   Any  change  indicated  by  the  RSA  calculation  is  reviewed  against  other  known long‐term  factors  prior  to  any  automatic  implementation  of  rate  changes.   This  allows  APU  to  blend forecasted increases or decreases in the projected power supply or operational costs to meet financial requirements and mitigate large fluctuations in electrical costs to customers.

RATE IMPACT  UNDER  RECOMMENDED  PORTFOLIO
Using the Variable Portfolio, APU performed rate impact analyses under the high, medium, and low load growth scenarios.

APU  performs  financial  modeling  for  the  purpose  of  monitoring  and  forecasting  the  financial performance of its electric utility and for identifying necessary rate adjustments. This financial model is 2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 103 ends

used  to  help  determine  the  cost  impact  of  various  changes  in  regulatory  requirements,  power  supply scenarios, capital improvements, and debt issuances.

For  purposes  of  the  IRP,  the  different  scenarios  under  evaluation  were  overlaid  onto  the  existing forecasts of capital, O&M, debt service, and other cost of service requirements. In developing the IRP, scenarios were eliminated that would result in large customer impacts. Rate impacts reflected in the IRP are calculated on a system‐wide basis.

APU’s forecasting model, like any other, includes significant assumptions. While the model used for the IRP  analysis  was  based  on  information  available  at  a  single  point  in  time,  it  is  not  uncommon  for assumptions  to  change  over  time  as  new  or  better  information  is  made  available.  An  analysis  was conducted for multiple scenarios and a range of potential rate impacts was developed to illustrate what management believes to be a realistic bandwidth of potential rate impacts over the course of the period analyzed.

The  expected  scenario  assumes  APU  will  meet  the  50%  RPS  requirement,  its  allocated  portion  of  the State goal of 1.5  million electric vehicles (EV) on the road in California, and  meet all energy efficiency (EE)  targets.  It  also  assumes  moderate  local  solar  growth  of  5  MW  per  year.  The  high  energy consumption scenario assumes 50% RPS, high EV growth, low EE growth, and low local solar. The low energy consumption scenario assumes 50% RPS, no EV growth, high EE growth, and high local solar. The overall  upward  trend  in  estimated  rates  for  all  three  scenarios  reflects  a  modest  increase  in  power supply, operating, maintenance, and debt service costs.

The results of the study suggest that the high energy consumption scenario results in lower average rate increases, as compared to the expected and low consumption scenarios. This is primarily the result of fixed  system‐wide  costs  being  recovered  over  a  greater  number  of  billing  units.  The  low  consumption scenario, on the other hand, is expected to result in higher average rate increases due to system‐wide costs being recovered over a smaller number of billing units. As noted, the study is based on forward‐ looking  assumptions  and  is  subject  to  change  due  to  commodity  price  fluctuations,  policy  changes, technological developments, changes in cash requirements, and/or changing customer behavior.

APU  will  continue  to  update  its  long‐term  plan  as  expectations  change  in  order  to  maintain  accurate forecasts. The following chart illustrates the results of the study based on the three scenarios described above.  The  chart  represents  forecasted  average  rates  based  on  system‐wide  averages  and  does  not account for rate structure variations across and within customer classes.

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 104 ends

Graph 52: Rate Comparison

The above graph shows the results of a rate analyses performed pursuant to this IRP, which includes the expected  power  supply  costs  associated  with  the  three  IRP  portfolio  scenarios  as  well  as  non‐power supply  operating  and  maintenance  costs,  debt  service,  and  financial  metric  requirements.  For  the expected  consumption  rate  projection  case  and  the  Variable  Portfolio,  net  power  supply  costs  are expected to increase an average of 1.34% per year from 2019 to 2030, which is less than the expected rate of inflation over the same time period.

Monthly bills for individual customers and customer classes may be more or less than these estimates due  to  the  different  rate  structures  of  the  various  customer  classifications  and  variations  in  individual customer  energy  consumption  profiles.  The  charts  below  reflect  the  estimated  impact  to  monthly customer bills for a typical residential customer and a commercial customer.

Graph 53: Total Residential Customer Monthly Bill

2018 Integrated Resource Plan
VII. Resource Portfolio Evaluation

Anaheim Public Utilities

Page 105 ends

Graph 54: Commercial Customer Monthly Bill

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 106 ends

VIII.  RELIABILITY  & ELECTRIC  SYSTEM  OVERVIEW
This section starts with an introduction to APU’s electric system (A. APU Electric System Overview) and generation and transmission resources (B. Generation and Transmission Resources).

PUC  Section  9621  requires  POUs  to  adopt  an  IRP  to  ensure  that  the  POU  meets  the  goal  of  ensuring system and local reliability. APU’s Balancing Authority is the CAISO, which has reliability and Resource Adequacy  requirements  for  load  serving  entities.  Section  C.  CAISO  Resource  Adequacy  Requirements discusses how APU plans to meet the CAISO system, local and flexible capacity requirements during the IRP’s planning horizon.

PUC Section 9621 also requires POUs to adopt an IRP to ensure POUs achieve the goal of strengthening the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities.

APU  entered  into  several  transmission  contracts  through  Southern  California  Public  Power  Authority (SCPPA)  and  with  the  Los  Angeles  Department  of  Water  and  Power  (LADWP)  in  order  to  ensure  the energy  from  APU’s  owned  or  contracted  resources  is  consistently  delivered  into  the  CAISO  from resources  located  outside  of  the  CAISO  footprint.  On  October  10,  2006,  APU  transferred  operational control  of  all  contracts  for  transmission  resources  to  CAISO.  According  to  the  North  American  Electric Reliability  Corporation  (NERC)  reliability  standards,  APU  is  a  Distribution  Provider  (DP),  and  not  a Transmission Operator (TOP), Transmission Owner (TO), Transmission Planner (TP), Transmission Service Provider (TSP), Generator Owner (GO), or Generator Operator (GOP). As such, the CAISO is responsible for evaluating the regional short‐term and long‐term infrastructure needs during its annual Transmission Planning Process.

APU has a long standing reputation of  providing its  customers with highly reliable electric  distribution services  over  a  robust  and  well‐maintained  electric  distribution  system.  In  2017,  the  American  Public Power  Association  recognized  APU  once  again  as  a  Reliable  Public  Power  Provider  (RP3).  The  RP3 designation  lasts  three  years  and  recognizes  utilities  that  demonstrate  high  proficiency  in  reliability, safety, work  force development, and system improvement.  Of the 2,000 public  power  utilities  nation‐ wide,  only  235  hold  the  RP3  designation.   APU’s  distribution  system  and  reliability  considerations  are described in section D. Distribution System Overview.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 107 ends

A. APU ELECTRIC  SYSTEM  OVERVIEW
The City of Anaheim is the second largest city in Orange County and tenth largest city in California. It is best known as the home to the Disneyland® Resort and the Anaheim Convention Center.

APU  is  a  city‐owned,  not‐for‐profit  electric  and  water  utility  that  offers  quality  electric  and  water services to residents and businesses in Anaheim at rates among the lowest in California. It operates the only municipal electric utility in Orange County. That means that the customers of this community own their utility, and therefore, have a say in decisions concerning its operation.

Anaheim citizens are more than just utilities customers; they are owners of their utility. They have input to  the  decision  process  both  directly  and  through  an  appointed  citizen  advisory  Public  Utilities  Board.

With final authority vested in Anaheim's elected City Council, decisions are made in the best interest of its citizens, quality of life, and local economy. As a municipal, not‐for‐profit utility, APU’s rates are based on the costs of providing water and electricity.

APU’s  system  delivers  electricity  to  Anaheim's  350,000  residents  and  more  than  15,000  businesses, including multi‐million dollar tourism, sports, and manufacturing customers.

Although  residential  customers  make  up  85%  of  APU’s  total  customers,  nearly  75%  of  total  electrical load  is  consumed  by  commercial  and  industrial  customers.  APU  experiences  seasonal  trends  in  which the summer months experience higher loads due to cooling needs, while the rest of the year tends to remain  fairly  stable.  Total  retail  load  is  estimated  as  total  system  load  less  system  losses,  which  have historically been approximately 3.5%.

Graph 55: Customer Class Data

‐
50 100
150
200
250
300
GWh
Monthy Electricity Sales by Customer Class (GWh)

INDUSTRIAL

COMMERCIAL

RESIDENTIAL
OTHER
Residential,

85.5%
Commercial,

14.2%
Industrial,

0.3%
Other, 0.1%
Active Meters by Customer Class
2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 108 ends

B. GENERATION  AND TRANSMISSION  RESOURCES
APU’s  power  supply  comes  from  resources  located  in  Anaheim  and  across  the  western  United  States.

This section introduces APU’s long‐term generation and transmission resources.

GENERATION  RESOURCES
ARP‐LOYALTON  BIOMASS  PROJECT
APU,  along  with  nine  other  California
publicly‐owned  utilities,  has  contracted  with
ARP‐Loyalton Cogen, LLC for the purchase of
renewable  biomass  electricity  from  a
biomass  project  located  in  northern
California.   Transmission  is  provided  by  the
CAISO.  This  contract  provides  Anaheim  with

0.81  MW  of  its  proportionate  share  of
renewable  biomass  energy  as  required
pursuant  to  Senate  Bill  859.   The  5‐year
contract expires on March 31, 2023.

BOWERMAN  POWER  FACILITY
APU  executed  a  Power  Purchase
Agreement  with  Bowerman
Power,  LLC  for  the  purchase  of

19.6  MW  of  renewable  energy
generated  from  landfill  gas  from
the Frank R. Bowerman Landfill in
Irvine, California.

Transmission  is  provided  by  the
CAISO. The 20‐year contract expires on April 30, 2036.

BREA POWER  II
APU  executed  a  Power  Purchase
Agreement with Brea Power Partners, LP
to  deliver  landfill  gas  renewable  energy
to APU to help satisfy demand.

The  original  5  MW  contract  was

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 109 ends

superseded by a second long‐term contract for a total of 27 MW from the new unit at the Olinda Landfill project.  The 33‐year contract expires on October 31, 2045.

DESERT  HARVEST  OR MAVERICK  FACILITY
The Cities of Anaheim, Burbank, and Vernon have contracted with  Desert  Harvest  II,  LLC  through  SCPPA  for  a  share  of intermittent solar energy from one of two solar projects: the Desert Harvest project or the Maverick project. APU’s share is  36  MW.  Transmission  is  provided  by  the  CAISO.  The  25‐ year contract expires on November 30, 2045.

HEBER  SOUTH
The  Cities  of  Anaheim,  Banning,  Glendale,
and  Pasadena  have  contracted  with  Ormat
Technologies,  through  Southern  California
Public  Power  Authority  (SCPPA)  for  a  share
of  a  14  MW  (net)  geothermal  project.  The
renewable  energy  is  delivered  to  the
Imperial  Irrigation  District’s  Mirage
Interconnection and then imported into the
CAISO.

The  contract  includes  mutual  termination  rights  at  years  15  and  20.  The  25‐year  contract  expires  on December 31, 2031.

THERMO  NO. 1
APU  executed  a  Power
Purchase  Agreement  with
this resource for energy from
an  11  MW  geothermal
project.   The  project  is
located  in  central  Utah  and
energy  is  being  delivered
over  the  Northern
Transmission  System  at  the
Mona  interconnection  tie  in
the  Los  Angeles  Department

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 110 ends

of Water and Power (LADWP) control area.  Additional transmission costs are required to get the energy delivered  from  Thermo  No.  1  to  the  Mona  interconnection  point.  This  20‐year  agreement  expires  on September 30, 2033.

HIGH WINDS  ENERGY  CENTER
APU  has  purchased  6  MW  of  intermittent
renewable  wind  energy  from  Avangrid
Renewables, LLC (a subsidiary of Iberdrola USA,
Inc.). Transmission is provided by the CAISO.

The  contract  includes  mutual  termination
rights at year 20 provided notice is given on or
before  December  31,  2022.   The  25‐year
contract expires on December 31, 2028.

PLEASANT  VALLEY  ENERGY  CENTER
APU  has  purchased  30  MW  of  intermittent
renewable  wind  energy  from  Avangrid
Renewables, LLC (a subsidiary of Iberdrola USA,
Inc.).  Energy  from  the  Pleasant  Valley  Wind
Energy  Center  is  delivered  through  the
Northern  Transmission  System  at  the  Mona
interconnection  tie  into  the  LADWP  control
area.

APU receives and pays for energy only when the
units  are  operating.  The  20‐year  contract
expires on June 30, 2025.

SAN GORGONIO  WIND FARM
APU executed a Power Purchase Agreement with
San  Gorgonio  Farms,  Inc.  for  31  MW  of
intermittent  renewable  wind  energy  from  the
existing  San  Gorgonio  Farms  Wind  Farm  located
in  Whitewater,  California  (near  Palm  Springs).

Transmission  is  provided  by  the  CAISO.  This
agreement has an initial term of ten years ending

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 111 ends

December 31, 2023, with an option to extend for two additional 10‐year periods.

WESTSIDE  SOLAR  WSP PV1
APU  executed  a  Power  Purchase
Agreement with Westside Assets, LLC
for  the  purchase  of  2  MW  of
renewable intermittent solar energy.

This  project  is  located  in  Kings
County, California.

Transmission  is  provided  by  the
CAISO.   This 25‐year contract expires
on June 30, 2041.

MWD COYOTE  CREEK,  PERRIS,  RIO HONDO  AND VALLEY  VIEW The  Cities  of  Anaheim,  Azusa,  and
Colton  have  contracted  with  The
Metropolitan  Water  District  (MWD)
of  Southern  California,  through
SCPPA,  for  17.1  MW  of  intermittent
renewable hydro electricity from four
small  hydroelectric  plants  located  in
the Los Angeles Basin.  APU is entitled
to  56.5%  of  the  project’s  output,  or

9.7  MW  from  all  four  plants.

Transmission is provided by the CAISO.  The 15‐year, 2‐month contract expires on December 31, 2023.

HOOVER  DAM
The Boulder Canyon Project (Hoover Dam)
consists  of  17  hydroelectric  generating
units  located  approximately  25  miles  from
Las  Vegas,  Nevada.  Forty‐six  (46)
participants  within  the  states  of  Arizona,
California,  and  Nevada  participate  in  the
Hoover Dam project. SCPPA members have
obtained  entitlements  totaling  665  MW
(32% of the Plant Capacity, of which APU has 1.9477%) through its Power Sales Agreements with SCPPA.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 112 ends

The  new  Electric  Service  Contract  with  Boulder  Canyon  commences  upon  expiration  of  the  existing Agreement on October 31, 2017, and expires on September 30, 2067.

CANYON  POWER  PROJECT
APU entered into a Power Sales
Agreement with SCPPA for all of
the  200  MW  nameplate
capacity  and  energy  from  the
Canyon  Power  Project  (CPP).

The  CPP  is  a  conventional
simple  cycle,  natural  gas‐fired
peaking  facility  comprised  of
four  combustion  turbine
generators  located  in  the
Canyon  industrial  area  of
Anaheim.  CPP  provides  enhanced  local  reliability  and  is  dispatched  when  its  generation  costs  are  less than the cost to serve APU’s load.

KRAEMER  PEAKING  PLANT
APU owns 100% of the Kraemer
Peaking Plant (KPP), also known
as the Anaheim Peaking Plant. It
is  a  48  MW  natural  gas‐fired,
combustion  turbine
conventional electric generating
plant  located  in  the  northeast
part of the City, adjacent to the
City’s  Dowling  Substation.

There  is  also  a  heat  recovery
steam  generator  for  emissions
control and power augmentation.

Since 2000, the operations of the Kraemer Peaking Plant have increased as the California energy market has been redesigned.   KPP is now dispatched when its generation costs are less than the cost to serve APU’s load.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 113 ends

MAGNOLIA  POWER  PROJECT
The  Magnolia  Power  Project  (MPP)
is  a  clean,  natural  gas‐fired,
combined  cycle  conventional
electric  generating  plant  located  in
Burbank, California.   MPP  is owned
by  SCPPA  and  is  operated  by
Burbank Water & Power.

APU  has  a  38%  (92  MW  base
capacity  and  26  MW  of  peaking
capacity) entitlement in the project
through  a  Power  Sales  Agreement
with SCPPA.

INTERMOUNTAIN  POWER  PLANT  (IPP)
APU  executed  a  Power  Sales
Agreement  with  Intermountain
Power Agency (IPP) in the early 1980s
for  13.225%  of  the  energy  output
from  IPP.  Thirty‐six  utilities  serving
California  and  Utah  receive  capacity
and energy from this project.  Energy
is  delivered  to  Anaheim  and  other
California  participants  through  the
Southern  Transmission  System  to  the  Victorville/Lugo  interconnection  with  the  CAISO.  The  40‐year contract expires on June 15, 2027.

TRANSMISSION  RESOURCES
MEAD‐ADELANTO  TRANSMISSION  PROJECT
APU  entered  into  a  transmission  service  contract
with  SCPPA  to  acquire  transmission  capacity  from
the Mead‐Adelanto Transmission Project to bring in
energy from Nevada based projects.

A  202  mile,  500  kV  AC  transmission  line  that  runs from the Marketplace Substation near Boulder City,

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 114 ends

Nevada  to  the  Adelanto  Substation  near  Victorville,  California.  The  transmission  line  has  a  transfer capability of 1,291 MW; APU’s share is 159 MW.

MEAD‐PHOENIX  TRANSMISSION  PROJECT
APU  entered  into  a  transmission  service  contract
with  SCPPA  to  acquire  transmission  transfer
capacity  from  the  Mead‐Phoenix  Transmission
Project.

A 256 mile, 500 kV AC transmission line that extends
from  the  Westwing  Substation  near  Phoenix,  AZ,
connects  with  the  Mead  substation  near  Boulder
City,  NV,  and  terminates  at  the  Marketplace
Substation nearby. The transmission line has a transfer capability of 1,923 MW; APU’s share is 155 MW.

NORTHERN  TRANSMISSION  SYSTEM
APU  entered  into  a  transmission  service  contract  with  LADWP  to  acquire  a  share  of  LADWP’s  transfer capability  of  the  Northern  Transmission  System  to  bring  power  from  the  Intermountain  Power  Plant (IPP) in Utah to the Mona substation in Utah and the Gonder substation in Nevada.

A  490  mile,  500  kV  DC  transmission  line  that  extends  from  IPP  near  Delta,  Utah  to  the  Adelanto Substation in Southern California, with an AC/DC converter station at each end of the transmission line.

The transmission line has a transfer capability of 2,400 MW; APU’s share is 257 MW.

SOUTHERN  TRANSMISSION  SYSTEM
APU  entered  into  a  transmission  service  contract
with  SCPPA  to  acquire  transfer  capability  of  the Southern Transmission System to bring power from
the  Intermountain  Power  Project  (IPP)  near  Delta, Utah  to  the  Adelanto  Substation  in  Southern
California.

A  490  mile,  500  kV  DC  transmission  line  that
extends from IPP near Delta, Utah to the Adelanto
Substation in Southern California, with an AC/DC converter station at each end of the transmission line.

The transmission line has a transfer capability of 2,400 MW; APU’s share is 424 MW.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 115 ends

ADELANTO ‐VICTORVILLE/LUGO  TRANSMISSION  SYSTEM
APU entered into a firm bi‐directional transmission
service  contract  with  LADWP  to  bring  power
between  the  Adelanto  and  Victorville  Substations
and  the  Lugo/Victorville  line  near  Victorville,
California to the City.

The approximately 23 mile, 500 kV AC transmission
line  extends  between  the  Adelanto  and  Victorville Substations  and  the  midpoint  of  the
Lugo/Victorville  500  kV  line.   The  transmission  line has a transfer capacity of 2,400 MW; APU’s share is
110 MW.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 116 ends

C. CAISO  RESOURCE  ADEQUACY  REQUIREMENTS
C.1. SYSTEM  RESOURCE  ADEQUACY
The  consequences  of  the  California  energy  crisis  from  2000  to  2001  highlighted  several  fundamental flaws in California’s existing electricity market design soon after the partial deregulation of the electric market.   Key  issues  were  identified  such  as  the  lack  of  long‐term  contracting  between  the  unbundled generation and distribution sectors, and the over‐reliance on spot market transactions as major causes for the market disruptions impeding system reliability.   Immediately after  the energy  crisis, the CAISO began addressing underlying infrastructure challenges such as transmission and generation deficiencies, and  began  a  comprehensive  market  redesign  and  technology  upgrade  (MRTU)  program  upon  the Federal Energy Regulatory Commission’s (FERC) approval.

State  regulators  implemented  a  Resource  Adequacy  (RA)  obligation  in  2004  requiring  Load  Serving Entities  (LSE),  such  as  APU,  to  procure  capacity  resources  for  100%  of  their  total  forecasted  customer load,  as  well  as  an  additional  15%  Planning  Reserve  Margin  (PRM),  for  a  total  of  115%  to  ensure adequate energy resources are available when needed.   This requirement is known as the “system” RA requirement.

APU  uses  a  mix  of  its  owned  and  contracted  resources  to  meet  the  system  RA  obligations.   These resources include both renewable and conventional generation within the State, and imported into the State from various regions. The optimum portfolio – Variable Portfolio – requires capacity purchases to meet  system  RA  requirements.  Graph  48  displays  the  change  in  capacity  from  2019  to  2030.  Capacity purchases will be acquired after 2027 to replace the system capacity lost with the divestiture of IPP.  The cost of capacity contracts are included in the power supply cost evaluation.

Graph 48: Variable Portfolio Forecasted Resource Adequacy

0 100
200
300
400
500
600
700
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Capacity Purchases New Intermittent Resources Intermountain Units 1 and 2 Magnolia Peak Magnolia Base Canyon Power Plant
Anaheim CTG Geothermal Raser Thermo Ormat Geothermal
Bowerman MWD Small Hydro Brea Power Partners
System Capacity Requirement
2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 117 ends

C.2. LOCAL  RESOURCE  ADEQUACY
In  addition  to  the  overall  system  RA  requirement,  the  CAISO  also  requires  that  a  certain  amount  of  a LSE’s  RA  obligation  must  meet  criteria  known  as  “local”  and  “flexible”  RA  requirements.  The  local  RA requirement  addresses  reliability  concerns  within  transmission‐constrained  areas  where  local generation resources are needed to ensure reliable electric grid operations to serve the area.

Under the CAISO Local Capacity Requirement (LCR) program, CAISO completes an LCR study each year using the most up‐to‐date information available for transmission system configuration, generation tied to the grid, and load forecasts approved by the CEC. The CAISO uses the annual LCR Study results as a basis for establishing each LSEs proportionate share of LCR for RA purposes.

The CAISO identifies 10 transmission‐constrained local pockets.   APU is in the local area defined as the LA Basin Area.   Results from the 2018 Local Capacity Technical Analysis issued by the CAISO on May 1, 2017, assigned a LCR of 225 MW for APU within the LA Basin Area.

The  CAISO  local  capacity  requirement  for  APU  has  been  below  230  MW  in  the  past  few  years  and remained  stable.  APU  has  over  290  MW  of  natural  gas  and  baseload  renewable  power  plants  located within  the  LA  Basin.  During  the  planning  horizon  of  this  IRP,  APU  has  sufficient  local  resources  that exceed CAISO’s local capacity requirements.

Graph 36: Local Capacity Resources and LCR Requirement

C.3. FLEXIBLE  CAPACITY  RESOURCE  ADEQUACY
The last component of RA procurement addresses the need to have generation resources available that can respond quickly to “up” and “down” electrical demand on the Grid. In order to meet energy demand 0 50
100
150
200
250
300
350
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
Local Capacity Resources and LCR Requirement
Brea Power Partners MWD Small Hydro Bowerman
Anaheim CTG Canyon Power Plant LCR Requirement
2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 118 ends

at certain times of the day when the CAISO must respond quickly to variations in load, LSEs are required to procure a certain amount of its RA obligation from resources defined as “flexible” in the CAISO tariff.

Increased  amounts  of  variable  energy  resources  puts  further  stress  on  what  is  known  as  the  “Duck Curve”  or  the  effect  solar  and  wind  generation  resources  have  on  net  demand  (demand  less  variable energy resources). As illustrated in Graph 56 below, in order to manage the effects of variable energy resources, the CAISO must have a resource mix to call upon that can react and adjust quickly to meet net  demand  while  mitigating  the  risk  of  over  generation.   To  do  so,  the  CAISO  must  ramp  generation resources  down  in  the  morning  hours  when  solar  generation  begins  to  produce  and  ramp  resources back up in the evening when solar generation drops off as the sun sets.

Graph 56: CAISO “Duck Curve” ‐ Impacts of Variable Energy Resources

Similar to LCR, the CAISO performs annually a system wide assessment of flexible capacity needs using a Monthly  Maximum  Three‐Hour  Net  Load  Ramp  plus  3.5%  of  expected  peak  load  to  determine  the required procurement target for each LSE.  The net load curves represent the variable demand that the CAISO must meet in real‐time.   In order to maintain reliability, the CAISO must match the demand for electricity  with  the  supply  on  a  second  by  second  basis  using  the  remaining  dispatchable  generation fleet.   To ensure reliability under the changing conditions seen on the Grid, the CAISO requires flexible resources with operational characteristics as follows:
 Ability to sustain upward and downward ramps
 Respond for a defined period of time, change ramping direction quickly  React quickly and meet expected operating levels
 Start with short notice from zero or low electric operating level  Start and stop multiple times per day

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 119 ends

To satisfy the CAISO’s procurement target for flexible capacity, APU typically utilizes the Canyon Power Plant.   This resource is not only local to APU’s load, but has the ability to start at a moment’s notice to ramp up or down as needed throughout the day providing 194 MW of eligible flexible capacity.

On average, APU has a monthly flexible capacity requirement of 40 MW, which peaks in December with a capacity requirement of 80 MW. The introduction of additional intermittent resources is estimated to increase the flexible capacity requirements by 3 MW for a 20 MW solar contract and 5 MW for 20 MW wind contract.

As  Canyon  Power  Plant  has  194  MW  of  eligible  flexible  capacity,  APU  has  sufficient  flexible  capacity available  through  Canyon  to  meet  the  additional  requirements  for  flexible  capacity.  Even  though  the optimum  portfolio  –  Variable  Portfolio  –  requires  the  highest  amount  of  flexible  capacity,  the  Canyon Power Plant provides more than sufficient flexible capacity to accommodate the additional intermittent resources.

Graph 37: CAISO Flexible Capacity Requirement

0 50
100
150
200
250
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MW
CAISO Flexible Capacity Requirement
Variable Mix Baseload Flexi Capacity Available
2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 120 ends

D. DISTRIBUTION  SYSTEM  OVERVIEW
D.1. DISTRIBUTION  SYSTEM
D.1.1. Electric System Overview
APU  delivers  electricity  to  its  approximately  350,000  residents  and  more  than  15,000  businesses, including the Anaheim Resort Area, Platinum Triangle, sports arena, Honda Center, City National Grove of Anaheim, etc.  APU serves about 119,000 electric meters throughout 50 square mile service area.

The APU electric system is a carefully planned and robust system. It consists of a 69 kV radial network serving eleven 69/12 kV distribution substations, where reliable power is transformed and distributed to homes and businesses, with a total  combined historic peak  demand of approximately 600 MW.    APU has  emergency  procedures  and  redundancy  built  into  its  system  to  address  the  unlikely  event  of  a catastrophic failure of a substation.

D.1.2. Distribution System
APU’s  distribution  system  includes  approximately  110  distribution  circuits  fed  by  eleven  distribution substations across 50 square miles. It provides high quality and reliable power service to customers.  The system is evaluated thoroughly on an annual basis to ensure it can meet forecasted peak demand in the five year planning horizon, as well as maintain and improve its reliability performance under normal and emergency  conditions.  To  achieve  these  goals,  APU  has  upgraded  and  reinforced  its  electrical infrastructures with various on‐going programs, and capital projects.

A new Harbor 69/12kV Substation is planned to be constructed and placed in service in the summer of 2019.  It is needed in order to serve new hotels and residential/commercial units under construction and planned future developments in the Platinum Triangle and Anaheim Resort areas.  This project will add needed  transformer  capacity  in  the  fast  growing  area  and  also  provide  loading  relief  to  the  adjacent substations.  It also greatly improves system reliability in the area.

A new 69/12kV transformer is planned to be  constructed and  placed in service in 2019. Similarly, this project is needed to accommodate new industrial and commercial loads in Eastern Anaheim area. It also will provide loading relief to adjacent substations and improves system reliability in the area.

APU  is  currently  upgrading  the  12kV  switchgears  to  higher  ampacity  rating  at  one  of  the  substations located  in  the  east  end  of  the  City.   It  is  expected  to  be  completed  in  2018.  This  project  is  needed  to serve  increased  load  growth  in  the  area.  It  will  also  improve  the  system  reliability  and  provide operational flexibility.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 121 ends

D.1.3. Recent Reliability Projects
In  2008,  APU  upgraded  its  electrical
infrastructure  to  increase  system  reliability  by
constructing the Vermont 220/69 kV Substation
which  is  radially  fed  from  Lewis  Substation,
normally  opened  at  Lewis  terminal.  A  major
69kV  network  in  the  affected  area  was
reconfigured  and  about  4,500  circuit  feet  were
also  undergrounded.  The  new  Vermont
Substation  was  built  to  serve  as  a  back‐up
source for Anaheim load in the event of a total
loss  of  the  Lewis  69  kV  Substation.   Photo  1
shows Vermont 220 kV GIS switchgear.

In 2006, APU accomplished a first‐of‐its‐kind in
the  United  States  when  it  constructed  under  a
park  an  electric  substation  with  gas  insulated
switchgear  (GIS)  and  with  the  capacity  to
provide power to 25,000 residential customers.

This  project  also  improves  system  reliability  in
the  east  of  Anaheim  system.   Photo  2  shows
Park Substation underneath the park.

Photo 2: Park Substation
Photo 1: Vermont 220kV GIS Switchgear
2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 122 ends

In  addition,  Anaheim
operates  two  gas‐fired
generating  plants,
Canyon  Power  Plant  and
Kraemer  within  its
service  territory  with  a
total  combined  capacity
of about 240 MW.  These
generating  resources  are
used  to  offset  power
imported  from  outside
resources  during  peak
load  periods,  and  they
both  have  black  start
capability  to  serve  APU  load  independent  of  the  Grid  in  the  event  of  a  sustained  regional  blackout.

Canyon Power Plant was built in 2011. The facility received silver LEED certification by utilizing systems that  limit  environmental  impacts;  these  systems  are  using  100%  recycled  water  and  powering  the control  room  with  solar  energy.   The  plant  produces  enough  energy  to  power  150,000  residential customers annually.  Photo 3 shows Canyon Power Plant.

D.1.4. Underground Conversion Program
In 1991, Anaheim City Council established the Underground Conversion Program to improve reliability and aesthetics along the City’s major streets by removing overhead power, phone, and cable TV lines.

Anaheim residents and businesses benefit from improved reliability of the electric system.  As of today, APU  has  converted  approximately  128  circuit  miles  or  50%  of  its  existing  overhead  circuits.   Photo  4 shows before and after of one of the underground projects.

Photo 4: Before and After Underground Project

Photo 3: Canyon Power Plant

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 123 ends

D.1.5. Distributed Generation
In  2014  APU  completed,  what  was
at  the  time  of  installation,  the
largest  city‐owned  convention
center  roof‐mounted  system  in
North  America.  This  2.4  MW  solar
plant  can  generate  enough  energy
to  support  approximately  600
homes  a  year.   Photo  5  shows  the

2.4  MW  Anaheim  Solar  Energy
Plant at the Convention Center.

Approximately  25  MW  of  rooftop
solar  generation  is  installed
throughout  the  Anaheim  system.

To  date,  there  are  little  to  no  impacts  to  the  distribution  network  resulting  from  these  installations, which are relatively small in size and not concentrated in one area, but rather scattered throughout the system.

Similarly, APU has not experienced or expects any significant impacts to the distribution network due to plug‐in electric vehicles (PEV) since they are not concentrated in one area or on a specific circuit at this point in time.

APU  continues  to  monitor  potential  impact  from  distributed  generation  and  from  electric  vehicle charging stations and will make necessary infrastructure investments to maintain system reliability and resiliency. As an example, APU evaluates commercial customers’ plans to install charging stations, and will  upgrade  local  transformers  when  multiple  charging  stations  are  planned  to  be  installed  in  a concentrated area.

D.2 SYSTEM  RELIABILITY
APU provides high quality electric service to approximately 119,000  metered  residential  and  business  customers through  a  modern  and  well  maintained  distribution network.

In 2017, the American Public Power Association recognized APU  once  again  as  a  Reliable  Public  Power  Provider  (RP3).

The  RP3  designation  lasts  three  years  and  recognizes utilities  that  demonstrate  high  proficiency  in  reliability, safety, work force development, and system improvement.

Of  the  2,000  public  power  utilities  nation‐wide,  only  235 hold the RP3 designation.

Photo 5: The 2.4 MW Anaheim Solar Energy Plant at Convention Center 2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 124 ends

Performance  metrics  are  regularly  utilized  to  measure  outage  duration,  number  and  type  of  outage events, as well as restoration time.  Electric reliability is measured by recording how many times service is interrupted (System Average Interruption Frequency Index or SAIFI), how long the average customer is interrupted (System Average Duration Index or SAIDI), and how long it takes to restore service once a customer  is  interrupted  (Customer  Average  Interruption  Duration  Index  or  CAIDI).   These  three measures  of  reliability  have  been  standardized  and  are  recognized  by  the  electric  industry  as  best practices  for  comparing  reliability  performance  among  utilities.  Below  is  a  graph  showing  Anaheim’s reliability performance in terms of SAIDI, SAIFI, and CAIDI since 1990.

Graph 57: Anaheim’s Reliability Performance in Terms of SAIDI, SAIFI, and CAIDI Since 1990

Many  factors  that  affect  service  reliability  are  beyond  APU’s  control,  such  as  wind,  vehicles  hitting power poles, earthquakes, etc. However, other factors are controllable, such as maintaining equipment in  good  operating  order  by  continually  monitoring  and  inspecting  the  system,  tightening  connectors, cleaning  dirt  from  insulators,  detecting  and  replacing  damaged  or  aging  components  before  they  fail, and systematically replacing equipment nearing the end of its useful life.

APU is continually working to improve its electric distribution system. For example, APU has installed a significant  number  of  remotely  controlled  field  switching  to  improve  outage  restoration  times,  in conjunction  with  a  program  to  remove  old  direct‐buried  cable  from  the  system  and  replacing  it  with cable encased in conduit. APU is also aggressively converting existing overhead lines along major streets to underground as a way of enhancing reliability and the visual appeal of streetscapes throughout the community.

APU is ranked in the top 25% (quartile) of utilities nationwide when it comes to electric system reliability, which means that APU customers have fewer and shorter power outages than the other 75% of utilities nationwide.

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 125 ends

Graph 58: APU at the Top Quartile of Utilities Nationwide for Reliability

D.3 SYSTEM  RESILIENCY
The City of Anaheim has undertaken a comprehensive planning effort in developing the Hazard Mitigation Plan11 by organizing resources, assessing risks, and developing and implementing a mitigation plan and monitoring process. On May 9, 2017, the Anaheim City Council adopted the Hazard Mitigation Plan, which was developed through City and community collaboration. It evaluates the risk of hazards and demonstrates how Anaheim will lower its risk and exposure to potential disasters, including earthquake, wildfire, and climate change.

Specifically, Section 9 of the Hazard Mitigation Plan details the risk factors of wildfire and preventative measures including fire mitigation education, vegetation management, routine inspections, fire resistant building material, and fire preventive building features. To ensure rapid response and adequate fire protection in times of major fire events, Anaheim also participates in the Standardized Emergency Management System, which enhances multi‐agency coordination for local and regional emergencies.

D.4 SMART  GRID
APU  has  always  strived  to  enhance  its  system  reliability,  improve  efficiency  and  power  quality,  and empower  customers  with  real  time  knowledge  of  energy  demand  through  implementation  of  new commercially  available  and  proven
technologies,  including  but  not  limited  to  distribution  automation, smart grid applications, and advanced metering infrastructure programs.

D.4.1  Distribution Automation
Smart Grid refers to modernization of the electricity delivery system primarily through automation.   It allows  for  a  more  reliable,  secure  electrical  service,  and  is  characterized  by  a  two‐way  flow  of

11 http://local.anaheim.net/docs_agend/questys_pub/13502/13532/13533/13578/13581/2.%20Hazard%20Mitigation%20Plan13581.pdf

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 126 ends

information,  control  systems,  and  computer  processing  to  create  an  automated,  widely  distributed energy  delivery  network.  These  cutting  edge  technologies  include  advanced  sensors  and  relays  that sense and recover from faults in the substation automatically, automated feeder switches that re‐route power to other feeders, automatic re‐closers with smart protective devices that quickly restore power following  momentary  outages,  and  automated  feeder  capacitors  that  switch  on/off  automatically  as needed to maintain fairly constant feeder voltages.

Some major advantages of implementing Smart Grid projects are 1) a self‐healing power system which uses  digital  information  and  automated  control  to  supply  more  reliable  power  with  fewer,  briefer outages,  2)  the  ability  to  immediately  and/or  remotely  validate  and  manage  outages  and  restoration work  which  reduces  the  time  needed  to  restore  service,  3)  a  reduction  in  the  number  of  times employees  are  sent  to  a  particular  address  to  validate  power  supply  to  a  meter,  and  4)  reductions  in total energy use, peak demand, energy loss, as well as potential reduction in end‐user consumption.

APU  performed  a  Smart  Grid  study  to  assess  each  of  the  distribution  circuits  in  the  system  and  to identify  which  overhead  and  underground  switches,  field  capacitor  banks  that  need  to  be  automated, and  where  branch  line  fuses  should  be  installed.   In  addition,  the  study  also  identifies  the  potential locations to install automatic re‐closers (AR).

Anaheim’s  electric  system  has  continually  been  reinforced  and  enhanced  to  meet  increasing  load demand  while  maintaining  system  reliability.  The  use  of  computer  based  remote  control  and communication  equipment  can  help  ensure  that  the  distribution  system  communicates  and  works together  to  deliver  electricity  more  reliably  and  efficiently.  The  automated  infrastructure  modernizes the  grid,  makes  it  more  resilient.  It  further  reduces  the  number  of  customers  affected  during  power outages, the frequency and duration of power outages, and the impacts of naturally occurring events. In addition,  APU  also  benefits  from  a  modernized  grid,  including  improved  security,  reduced  peak  loads, increased integration of renewables, and improved operational efficiency.

Graph 59: Basic Characteristics of Smart Grid

2018 Integrated Resource Plan
VIII. Reliability & Electric System Overview

Anaheim Public Utilities

Page 127 ends

APU has actively promoted, implemented, and expanded Smart Grid projects for its electric system since 2010.   To  date,  APU  has  spent  several  million  dollars  on  Smart  Grid  projects  and  automatic  devices system‐wide  including,  but  not  limited  to,  automated  re‐closers,  automated  switches,  automated capacitor banks, and SCADA linked fault indicators.

Future application of Smart Grid projects will evolve into  more  sophisticated and  complex operations, such  as  predicting  failing  equipment  and  automatically  isolating  faulty  equipment  before  a  failure occurs,  automatically  restoring  customers  immediately  after  outages  (self‐healing),  and  integrating distributed energy resources and demand response programs.

D.4.2  Advanced Metering Infrastructure
As a critical component of the Smart Grid, APU has deployed approximately 9,000 Advanced Metering Infrastructure (AMI) systems within its service territory.

APU used a radio frequency network communication for its electric distribution automation system for almost 20 years. The network consisted of over 400 radios and 130 routers installed throughout the City.

In order to leverage the existing communication network and gain the greatest synergy and lower long‐ term costs, APU plans to deploy compatible smart meters while phasing out dated technology.

Graph 60: Advanced Metering Infrastructure

Currently, APU is looking at improving the deployment process and performing other testing as needed prior to a full scale AMI deployment.  Full deployment of smart electric meters will begin FY 2018/2019, along with smart water meters a year later.  A full deployment of electric and water meters is expected to take approximately 5‐6 years.

2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 128 ends

IX. GREENHOUSE  GAS EMISSION  REDUCTION
STATEWIDE  GHG EMISSION  PROFILE
The passage of AB 32 in 2006 established statewide target to reduce GHG emissions to 1990 levels by the  year  2020;  effectively  a  30%  decline  in  emissions  from  current  statewide  output.   In  2016,  SB  32 expanded the statewide GHG emissions reduction goal to 40% below 1990 levels by the year 2030.

Graph 61: 2015 GHG Emissions by Sector12

According  to  CARB’s  2017  GHG  Emission  Inventory  report,  emissions  from  the  electric  power  sector comprised  19%  of  2015  statewide  GHG  emissions,  and  was  the  third  largest  source  of  GHG  emissions following  the  transportation  (37%)  and  industrial  (21%)  sectors.12 From  2000  to  2015,  the  electricity sector has reduced emissions by 20%, while the transportation and industrial sectors reduced emissions by 6% and 2%, respectively.13  The overall emission decrease in the electricity sector is driven by reduced reliance  on  carbon‐based  fuels,  increased  use  of  renewable  energy,  incrementally  higher  energy efficiency standards, increased deployment of distributed renewable generation, vehicle electrification, and energy storage technologies.

Graph 62: GHG Intensity of Electricity12

12 https://www.arb.ca.gov/cc/inventory/pubs/reports/2000_2015/ghg_inventory_trends_00‐15.pdf 13 2017 Edition California Greenhouse Gas Inventory for 2000‐2015 —  by Sector and Activity; downloaded from:
https://www.arb.ca.gov/app/ghg/2000_2015/ghg_sector.php

2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 129 ends

APU’S EMISSION  REDUCTION  EFFORTS
To meet the AB 32 and SB 32 goals, APU began reducing its reliance  on  generation  resources  that  produce  GHG emissions  by  transitioning  from  fossil  fuel‐fired  generating resources  to  renewable  resources  and  cleaner  natural  gas generation technologies.   The most significant contribution that  APU  can  make  in  reducing  GHG  is  the  reduction  of energy  resources  that  produce  GHG  emissions  from  its power supply. In addition to GHG emission reductions from APU’s  power  supply,  further  GHG  reductions  will  come from  complementary  efforts  including  increased  energy efficiency measures, local solar, energy storage, and electrification of the transportation sector.

2015
GREENHOUSE  GAS REDUCTION  PLAN
In  July  2015,  APU  developed  its  first  utility‐
specific  Greenhouse  Gas  Reduction  Plan14 with
the  purpose  of  developing  a  clear  and
comprehensive long‐term strategic framework to
reduce GHG emissions.  The Plan identifies a goal
to  reduce  GHG  emissions  by  20%  below  1990
levels  by  2020  and  a  minimum  of  40%  below
1990 levels by 2030.   It is important to note that
the  40%  reduction  below  1990  levels  is  a
statewide  goal;  however,  California  utilities  will likely be called upon to do more.

APU  achieved  its  goal  of  20%  below  1990  levels
through  the  increased  renewable  generation
from  11%  in  2010  to  33%  of  overall  sales  in
calendar  year  2015.   Further  GHG  emissions
reductions  are  expected  to  reach  near  the  40%
target  in  2018  due  to  the  divesture  of  the  San Juan Generating Station in 2017. Upon APU’s exit
from  the  Intermountain  Power  Project  in  2027,
APU’s  overall  GHG  emissions  from  its  power

14 http://www.anaheim.net/DocumentCenter/View/7996
Renewable
Energy
Energy
Efficiency
Local Solar Energy Storage
Transportation
Electrification

2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 130 ends

supply  portfolio  is  expected  to  reach  or  exceed  70%  below  its  1990  emissions  by  2028.   Significant emission reductions are observed in each of the  portfolio scenarios analyzed and discussed in Section VII. Resource Portfolio Evaluation.

Graph 63: APU GHG Reduction Targets

EMISSION  REDUCTIONS  ASSOCIATED  WITH TRANSPORTATION  ELECTRIFICATION Electric vehicle growth is estimated using the CEC’s “2016 SB 350 Common Assumption Guidelines for Transportation  Electrification  Analysis  3.0”  workbook  published  in  April  2017.15 According  to  the  CEC workbook, APU’s share of total California registered electric vehicles is 0.63%, or an estimated 16,280 electric vehicles by 2030.

The model also provides estimates of the emissions savings per vehicle. In 2015, the estimated savings in emissions per electric vehicle is 2.31 MTCO2e. As more electric vehicles are deployed, the impact on emissions per EV is expected to decline to 1.761 MTCO2e by 2030.

15 “2016 SB 350 Common Assumption Guidelines for Transportation Electrification Analysis”, Version 3.0, Updated 4/6/2017. This workbook is subsequently replaced by updated versions and no longer available via the CEC website. The most updated version is available for download at http://www.energy.ca.gov/sb350/IRPs/.

2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 131 ends

Table 7: Anaheim EVs and Emission Savings per Vehicle
Year  Estimated Number of Vehicles  Emissions Savings Per Vehicle (MTCO2e) 2018  2,343  2.125
2019  3,045  2.082
2020  3,870  2.044
2021  4,807  2.009
2022  5,844  1.976
2023  6,970  1.945
2024  8,171  1.916
2025  9,434  1.887
2026  10,748  1.860
2027  12,100  1.833
2028  13,478  1.808
2029  14,874  1.784
2030  16,280  1.761

Based on the CEC’s estimates, APU could have a total of 16,280 EVs within the service territory by the year  2030,  resulting  in  a  GHG  emission  reduction  of  approximately  28,675  MTCO2e.  In  APU’s  high extreme  energy  demand  forecast,  the  projected  EV’s  registered  in  Anaheim  are  25%  above  the  1.5M statewide goal, which estimates 20,350 EVs by 2030 and an emissions reduction of 35,844 MTCO2e.

Graph 64: Emission Reductions Resulting from Transportation Electrification

The CEC has since released several updated versions of “2017 SB 350 Common Assumption Guidelines for Transportation Electrification Analysis” in late 2017 through early 2018.16 The most updated analysis

16 The most updated Light‐Duty Plug‐in Electric Vehicle Energy and Emissions Calculator may be found on the CEC’s Integrated Resource Planning webpage: http://www.energy.ca.gov/sb350/IRPs/
(55)
(45)
(35)
(25)
(15)
(5)
5 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Metric Tons of CO23 (Thousands)
Total Emissions Reductions from EV

1.5M by 2025 25% Above 1.5M by 2025
2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 132 ends

(Version 3.5‐2, dated 1/12/18) available as of the writing of this IRP resulted in slightly higher number of EVs  that  were  still  lower  than  the  high  EV  extreme  scenario.  The  updated  analyses  also  resulted  in slightly higher emission savings per vehicle. This IRP presents the original emission savings per vehicle to be  consistent  with  the  rest  of  the  EV  calculations.  It  also  reflects  a  more  conservative  approach  in  EV emission savings calculation.

EMISSION  REDUCTION  TARGET  – SYSTEM  ENERGY  DEMAND
Senate Bill 350, the Clean Energy and Pollution
Reduction Act of 2015 (de León, Chapter 547,
Statutes  of  2015)  (SB  350)  requires  the
California  Public  Utilities  Commission  (CPUC)
and the California Energy Commission (Energy
Commission)  to  establish  IRP  processes  to
ensure  that  load‐serving  entities  (LSEs)  and
qualifying  publicly  owned  utilities  (POUs) 17
meet  the  GHG  emission  reduction  targets
established  by  the  California  Air  Resources
Board (CARB) for the electricity sector and each LSE and POU for the year 2030.

CARB,  in  conjunction  with  CEC,  is  in  the  process  of  developing  utility‐specific  GHG  reduction  planning target  ranges  for  California  POUs  as  mandated  through  the  passage  of  SB  350.   The  development  of utility‐specific GHG reduction target ranges is not expected to be finalized before the adoption of this IRP.

While the CARB is ultimately responsible for setting the GHG reduction target ranges for all utilities, the CEC  released  a  memo  titled  “Proposed  Method  for  Setting  POU‐Specific  GHG  Emission  Reduction Targets  for  Integrated  Resource  Planning”  dated  February  15,  2018.  In  this  memo,  the  CEC  provided their interim guidance and recommended POU GHG reduction planning targets to inform and assist the CARB  with  establishing  the  official  target  planning  ranges.  As  of  the  writing  of  this  IRP,  CARB  has indicated that the GHG reduction targets being established for APU by CARB are intended to be IRP GHG reduction planning targets only.

The  CEC’s  methodology  established  a  proposed  range  of  GHG reduction  targets  for  APU  between  304,009  and  537,957  MTCO2e.

This  proposed  target  range  represents  an  approximate  emission level between 77% ‐  87% below APU’s 1990 emission levels. If this GHG reduction range is ultimately adopted by CARB, then it would be  significantly  greater  than  the  statewide  targeted  reduction  of 40%  below  1990  emission  levels  established  by  SB  32,  and  lower

17 The IRP requirement applies only to POUs with annual demand exceeding 700 GWh.

The CEC’s proposed target
range represents an
approximate emission level
between 77% ‐ 87% below
APU’s 1990 emission levels.

The CEC’s proposed target
range represents an
approximate emission level
between 77% ‐ 87% below
APU’s 1990 emission levels.

2018 Integrated Resource Plan
IX. Greenhouse Gas Emission Reduction

Anaheim Public Utilities

Page 133 ends

bound  of  the  range  would  be  difficult  to  achieve  without  significantly  increasing  APU  power  supply costs.

Graph 65: APU GHG Emission for System Energy Demand

APU’s  resource  portfolio  will  be  coal‐free  by  mid‐2027  and,  at  a  minimum,  50%  of  APU’s  electricity deliveries  will  come  from  renewable  energy  resources.  Based  on  current  law  and  regulations,  APU’s optimum resource portfolio under this IRP will achieve the upper bound of the proposed GHG reduction target  range;  however,  the  lower  bound  of  the  range  (i.e.,  87%  GHG  reduction)  will  not  be  achieved without significant cost impacts. If CARB adopts the more stringent 87% GHG reduction target it would cause a significant rate impact to APU customers as it would require the shutdown, or “stranding,” of a very reliable  and efficient  baseload natural gas resource  Magnolia Power Plant, which  has 20‐years of unavoidable  debt  service  costs  that  would  still  need  to  be  paid  by  APU  customers  in  addition  to replacement  renewable  resources.  APU  is  closely  following  relevant  regulatory  proceedings  and  will work with CARB and CEC to recommend methodologies to further reduce APU carbon emissions, such as accounting for the effect of electric vehicle (EV) penetration on emission reduction.

250
350
450
550
650
750
850
950
1,050
1,150
1,250
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 MMT of CO2  (Thousands)
APU GHG Emission ‐ System Energy Demand
APU Emission APU Emission + EV Emission Reduction
APU GHG Emission Target Range
304,611 ‐ 538,146 MMT
(77% ‐ 87% lower than 1990 level)
2018 Integrated Resource Plan
X. Transportation Electrification

Anaheim Public Utilities

Page 134 ends

X. TRANSPORTATION  ELECTRIFICATION
Transportation Electrification (TE) is the transition from fossil‐fuel powered vehicles to vehicles powered by  clean  and  sustainable  electricity.  This  includes  passenger  and  commercial  automobiles  as  well  as transit buses and medium to heavy‐duty trucks. APU’s holistic efforts related to TE date back to 2012, soon  after  modern  EVs  became  commercially  available.  APU  had  a  vision  to  facilitate  customers’ interests in EVs by addressing EV readiness, charging infrastructure plans, financial tools for customers, ease  of  permitting,  and  enhanced  customer  service.  Since  then,  APU  has  developed  various  programs and  continues  to  support  TE  while  providing  environmentally  sustainable  and  competitively  priced power.

A. Quantification,  Characterization,  and Location
LOAD IMPACT & GHG EMISSION REDUCTIONS
Using the CEC “Transportation Electrification Common Assumptions 3.0” workbook that was distributed to  California  utilities  in  2017,  APU  estimated  the  electricity  consumption  and  net  NOx,  particulate matter,  and  GHG  emissions  reductions  associated  with  Light  Duty  Plug‐In  Electric  Vehicle  (LD  PEV) deployment through 2030.   APU’s demand forecast assumes the CEC growth assumptions to meet the Governor’s  order  of  1.5  million  electric  vehicles  on  the  road  by  2025.  The  CEC  workbook  calculates Anaheim’s share of total California registered electric vehicles to be 0.63%, which equals an estimated total of 16,280 electric vehicles contributing to 63,261 MWh in load growth in Anaheim by 2030.

EV CHARGING STATIONS
As of December 2017, APU has installed a total of
69  charging  stations.  While  some  of  these
charging stations are located within APU and the
City’s facilities, 48 out of 69 (or 70%) are open to
the  public  and  strategically  located
in  key  public
venues or transportation hubs.

The IRP Customer Survey results indicate that the
surveyed  residential  customers  who  anticipate
acquiring  an  EV  within  the  next  three  years
spread evenly throughout APU’s service territory.

Additionally, about half of these customers live in
multi‐family  dwellings,  signifying  the  possible
need  for  public  access  charging  stations.  APU’s
public  charging  stations  will  provide  these  potential  EV  owners  geographical  convenience  for  their fueling options.

Photo 6: Charging Stations at Anaheim Regional Transportation Intermodal Center

2018 Integrated Resource Plan
X. Transportation Electrification

Anaheim Public Utilities

Page 135 ends

According to the Alternative Fuels Data Center18 of the U.S. Department of Energy (DOE), within the City of  Anaheim,  there  are  a  total  of  193  public  access  charging  stations  (3  Level  1  stations,  186  Level  2 stations,  and  4  DC  Fast  Charging  stations)  as  of  December  2017.  These  charging  stations  include  both privately‐owned stations and the above mentioned public access stations under APU control.

Graph 66: EV Charging Stations within APU Service Territory

Utilities Fleet
APU’s earliest effort of fleet electrification focuses on the  light‐duty  field  services  vehicles  since  1)  these vehicles  tend  to  have  frequent  stops  such  as  for meter reading and 2) light‐duty EVs and hybrid plug‐in
EVs  are  more  technologically  mature  and
commercially available. APU has achieved 10% low or
zero  emission  vehicles  in  its  light‐duty  fleet.  In addition,  36%  of  APU’s  light‐duty  fleet  are  low
emission Compressed Natural Gas (CNG) vehicles.

18 U.S. Department of Energy’s Alternative Fuels Data Center, http://www.afdc.energy.gov/data_download, December 20, 2017.

Photo 7: Early Model Electric Toyota RAV‐4 Used by APU for Fleet Testing
2018 Integrated Resource Plan
X. Transportation Electrification

Anaheim Public Utilities

Page 136 ends

APU  will  continue  to  convert  the  older  and  higher‐polluting  vehicles  to  EVs  and  hybrid  EVs  to  meet South  Coast  Air  Quality  Management  District  (SCAQMD)  and  DOE  requirements.  For  example,  APU’s current field services light duty fleet has a total 14 vehicles, of which 6 are already low or zero emission.

APU anticipates transforming its field services fleet into 100% low or zero emission vehicles by acquiring 10 Chevrolet Bolt EVs.

Medium‐duty  and  heavy‐duty  vehicles  provide  essential  services  such  as  emergency  response  and outage restoration during blackouts. APU relies more on traditional or biodiesel fuel to ensure that the services will not be interrupted due to mileage range limitations. As of December 2017, biodiesel (20% blend) powers 5% and 76% of APU’s medium‐duty and heavy‐duty fleet, respectively.

It  is  worth  mentioning  that  APU
owns  a  hybrid  electric  bucket
truck.  APU  acquired  the  truck  to
gain  first‐hand  experience  with
heavy‐duty  low  emission  vehicles
and  is  still  evaluating  the
performance  of  the  hybrid  truck.

APU  will  continue  to  evaluate
technological  readiness  for  the
electrification  or  the  medium  and
heavy‐duty fleet.

B. Transportation  Electrification  Programs
APU’s transportation electrification programs including the following:

B.1. EMPLOYEE WORKPLACE CHARGING PROGRAM
To  the  extent  possible,  APU  offers  its  employees  and  the  City’s  employees  free  charging  at  its  EV charging  stations  located  in  the  employee  and  fleet  parking  facilities.  APU  will  continue  to  encourage and support its employees’ adoption of EVs
whenever feasible.

B.2. EV RATES
APU offers residential customers the option to charge their electric vehicles on a time‐based rate (Developmental Schedule D‐EV of City of Anaheim’s Electric Rates, Rules and Regulations, available online at http://www.anaheim.net/documentcenter/view/1248). The rate currently charges $0.2634 per kWh and $0.1117 per kWh for energy used during on‐peak and off‐peak hours, respectively from June 1 Photo 8: Current Nissan Leaf EV in APU Fleet
2018 Integrated Resource Plan
X. Transportation Electrification

Anaheim Public Utilities

Page 137 ends