3. On-site Inspection and testing
Scope/Description Hours Rate Total
Principal Engineer 8 $ 195.00 $ 1,560.00
Principal Surveyor $ 195.00 $ -
Associate Engineer $ 174.00 $ -
Project Manager 3400 $ 153.00 $ 520,200.00
Special Inspector / Materials Technician (Prevailing) 720 $ 173.00 $ 124,560.00 Laboratory Materials Testing 1 $ 25,000.00 $ 25,000.00
Project Coordinator 180 $ 111.00 $ 19,980.00
Administrative Assistant $ 95.00 $ -
Qualified SWPPP Developer (QSD) $ 174.00 $ -
Qualified SWPPP Practitioner (QSP) $ 137.00 $ -
Two-Man Survey Crew $ 450.00 $ -
Vehicle mileage/per diem 28840 $ 0.75 $ 21,630.00
Sub-total $ 712,930.00
4. Redesign Based on Unforeseen Conflicts
Scope/Description Hours Rate Total
Principal Engineer 10 $ 195.00 $ 1,950.00
Principal Surveyor 8 $ 195.00 $ 1,560.00
Associate Engineer $ 174.00 $ -
Project Manager 235 $ 153.00 $ 35,955.00
Senior Designer 80 $ 137.00 $ 10,960.00
Designer $ 111.00 $ -
Project Coordinator 8 $ 111.00 $ 888.00
Administrative Assistant $ 95.00 $ -
Qualified SWPPP Developer (QSD) 8 $ 174.00 $ 1,392.00
Qualified SWPPP Practitioner (QSP) 8 $ 137.00 $ 1,096.00 Two-Man Survey Crew $ 450.00 $ -
Vehicle mileage/per diem $ 0.75 $ -
Sub-total $ 53,801.00
Provide on-site, full-time and periodic inspection and any required testing per construction plans and specifications.
This is an estimate for the scope of work proposed. All work to be done on a time and material basis per Merrell Johnson Companies approved contact rates.
Perform redesign based on unforeseen conflicts due to utilities and other infrastructure entities requiring mitigation.
City requested changes due to geographical adaptations and local specific needs. Neighborhood requests for design modifications on site specific conditions not considered in overall design process to mitigate construction disturbances and adverse activities.
11.e
Packet Pg. 373 Attachment: Task Order (Attachment F) (6272 : Award of Bid for the FY 25-26 Street Rehabilitation Project) Exhibit B FEE PROPOSAL/ESTIMATE
5. Reproduction
Scope/Description Hours Rate Total
Project Manager 6 $ 153.00 $ 918.00
Senior Designer 8 $ 137.00 $ 1,096.00
Designer $ 111.00 $ -
Project Coordinator 8 $ 111.00 $ 888.00
Administrative $ 95.00 $ 760.00
Bond (24 x 36) 208 $ 6.00 $ 1,248.00
Bond (30 x 42) $ 8.00 $ -
Mylar (24 x 36) 104 $ 10.00 $ 1,040.00
Mylar (30 x 42) $ 15.00 $ -
Photographic Paper (24 x 36) $ 30.00 $ -
Photographic Paper (30 x 42) $ 40.00 $ -
Thumb Drive 32 GB Flash Memory 2 $ 16.00 $ 32.00
8 1/2 x 11 $ 0.35 $ -
8 1/2 x 14 $ 0.50 $ -
11 x 17 208 $ 0.75 $ 156.00
Sub-total $ 6,138.00
Total Merrell-Johnson Engineering $ 1,598,920.00
The cost for plotting and running prints is based on the number of prints each agency requires for submittal and the client is requesting. This is invoiced on a time and materials basis. Plotting will also be invoiced on a time and materials basis per our schedule of fees. Time and Fees are estimated based on our understanding of the project scope at the time of this proposal.