CAMARILLO SANITARY DISTRICT
PUBLIC WORKS DEPARTMENT
CAPITAL PROJECTS
NOTICE TO BIDDERS, PROPOSAL, CONTRACT
AND SPECIFICATIONS
FOR THE CONSTRUCTION OF
WASTEWATER SYSTEM GENERATOR REPLACEMENT
AT PS3 & PS5
PROJECT NO. SS-5120-1
BIDS TO BE OPENED ON
September 18, 2025 AT 3:00 P.M.
RYAN LI PPINCOTT
PRINCIPA L CIVIL ENGINEER
JAMES CAMPERO
DISTRICT
ENGINEER
R. C. E. 76459, Exp. 12/31/2026
WASTEWATER SYSTEM GENERATOR
REPLACEMENT AT PS3 & PS5
PROJECT NO. SS-5120-1
PROJECT ADMINISTRATION
All inquiries relative to this project shall be directed to Ryan Lippincott , Principal Civil Engineer of the Camarillo Sanitary District Public Works Department, prior to opening of bids. All questions relating to interpretation of the Contract Documents or products must be submitted via PlanetBids five (5) business days prior to the opening of bids, and responses modifying the contract documents will be in the form of written addenda, if required as further described in the bid documents. Questions submitted after this time period will not be answered.
Ryan Lippincott
Principal Civil Engineer
Public Works Department
601 Carmen Drive
Camarillo, CA 93010
Telephone: (805) 388-5340
Fax: (805) 388-5387
Email: [email protected]
(8-2023)
CAMARILLO SANITARY DISTRICT
1. NOTICE INVITING BIDS
2. INSTRUCTIONS TO BIDDERS
3. BID PROPOSAL
4. PUBLIC WORKS CONTRACT
5. GENERAL CONDITIONS/SPECIFICATIONS
6. SPECIAL PROVISIONS
WASTEWATER SYSTEM GENERATOR REPLACEMENT AT
PS3 & PS5
PROJECT NO. SS-5120-1
Project Number: SS-5120
-1
Date: July 31, 2025
District Engineer
BIDS WILL BE RECEIVED UNTIL
September 18, 2025 AT 3:00 P.M.
Via electronic transmission on the Camarillo Sanitary District PlanetBids portal site
(8-2023)
NOTICE INVITING BIDS
- 1 -
CAMARILLO SANITARY DISTRICT
NOTICE INVITING BIDS
NOTICE IS HEREBY GIVEN that the Camarillo Sanitary District (“DISTRICT”), will receive bids for the below stated Project ONLY via electronic transmission on the DISTRICT’S online PlanetBids portal site until 3:00 p .m., September 18, 2025 , and will be opened and posted online via PlanetBids portal site immediately thereafter.
WASTEWATER SYSTEM GENERATOR REPLACEMENT AT
PS3 & PS5
PROJECT NO. SS-5120-1
The project to be constructed consists of replacing Pump Station 3 (PS3) and Pump Station 5 (PS5) generators at the Water Reclamation Plant (WRP) to provide standby power in case of an emergency or power loss, and related work.
Obtaining Bid Documents: The Bid Documents for this project are on file in the office of the undersigned. In addition prospective bidders may obtain free copies of these documents, including Proposal, Bid forms, Specifications, and Plans by registering online as a prospective bidder on the C amarillo Sanitary District PlanetBids portal site:
https://pbsystem.planetbids.com/portal/56271/portal-home. Hard copies are also available from the Camarillo Sanitary District, at 601 Carmen Drive, Camarillo, California 93010. THERE IS A $70 SERVICE CHARGE (ADD $ 15 POSTAGE IF PLANS ARE TO BE MAILED). These amounts are not refundable. Checks should be made payable to the Camarillo Sanitary District.
Bidders may also obtain Bid Documents from the DISTRICT website at https://www.cityofcamarillo.org/cip with no fee.
Plans, general and special provisions, and proposal forms for the project are also filed with the following: Dodge Data & Analytics, www.construction.com; Ventura County Contractors’ Association, 1830 Lockwood Street, Suite 110, Oxnard, California 93030; BidAmerica, 41085 Elm Street, Murrieta, California 92562 (www.bidamerica.com); Plan Room, Construction Bidboard, Inc., 11622 El Camino Real, 1
st Floor, San Diego, California 92130; Builders
Notebook, 133 E. De La Guerra Street, Suite 62, Santa Barbara, California, 93101; and are by reference made a part of this Notice.
Bidders must be registered on the Camarillo Sanitary District’s PlanetBids portal in order to receive addendum notifications and to submit a bid. Go to PlanetBids for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.
Plans and special provisions are based on the use of the Standard Specifications for Public Works Construction, 2024 edition, written and promulgated by Public Works Standards, Inc. and all supplements thereto.
Bid Bond: The bid must be accompanied with an uploaded scanned copy to PlanetBids of the bid security in the form of a money order, a certified cashier’s check, or bidder’s bond executed by an admitted surety, made payable to DISTRICT. The bid security shall be an amount equal (8-2023)
NOTICE INVITING BIDS
- 2 -
to ten percent (10%) of the total annual bid amount included with their proposals as required by California law.
Note: The original security of the three (3) lowest bidders must be submitted to the Public Works Department at 601 Carmen Drive, Camarillo, California 93010, in a sealed envelope and be received or postmarked within three (3) District business days after the bid due date and time for the bid to be considered. The sealed envelope should list the Bidder’s Name and be plainly marked on the outside: “SEALED BID SECURITY FOR WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5 – PROJECT NO. SS-5120-1.” Pre-Bid Meeting: A non-mandatory pre-bid meeting is scheduled for 10:00 a.m. on August 28, 2025, at the Camarillo Water Reclamation Plant at 150 Howard Road, Camarillo, California 93012.
Required Contractor’s License(s) : Under Business & Professions Code section 7028.15 (e), a bid submitted to the District must be by a licensed contractor in accordance with Division 3, Chapter 9 of the Business & Professions Code unless one of the exceptions in Section 7028.15 applies.
Under Public Contract Code section 3300, the bidder must possess at the time a contract is awarded all classifications of contractor’s licenses required by the District. For this project, the District requires that the bidder possess a valid Class A contractor’s license.
Under Public Contract Code section 20103.5, failure of a bidder to be properly licensed at the time of the award of the contract will constitute a failure to execute the contract and will result in a forfeiture of the security of the bidder.
Required Contractor and Subcontractor DIR Registration: The District will accept bids only from bidders that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code § 7029.1) or if federal funds are involved in the project, then District may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded. Information on registration with the DIR is available at: https://www.dir.ca.gov/Public-Works/Contractor-Registration.html.
This is a separate requirement from the Contractors State License Board licensing requirement.
Substitution of Securities: In accordance with Public Contract Code section 22300, substitution of eligible and equivalent securities for any moneys withheld to ensure performance under the contract for the work to be performed will be permitted at the request and expense of the successful bidder. Such equivalent securities must be deposited with District or with a state or federally chartered bank as the escrow agent who will then pay such moneys to the contractor. Upon satisfactory completion of the contract, the securities will be returned to the contractor. Securities eligible for investment include those listed in Government Code section 16430, bank or savings and loan certificates of deposit, interest bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed to by the contractor and District. The contractor will be the beneficial owner of any securities used to secure its performance. Any escrow agreement will be substantially similar to the form set forth in Public Contract Code section 22300.
Federal Certificate: If this Notice indicates that this project is a federally-funded project and the Bid Proposal is for more than $100,000, the bidder and each of its subcontractors must submit (8-2023)
NOTICE INVITING BIDS
- 3 -
signed copies of the Federal Certificate for Contracts, Grants, Loans and Cooperative Agreements.
Labor Code Compliance: Any contract entered into pursuant to this Notice will incorpor ate the applicable provisions of the California Labor Code.
Prevailing Wage Laws : The successful bidder must comply with all prevailing wage laws applicable to the project, and related requirements contained in the contract documents. Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the contract, as determined by Director of the State of California Department of Industrial Relations, are on file at the City, and may be obtained from the DIR website:
https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm. Upon request, Dist rict will make
available copies to any interested party. Also, the successful bidder must post the applicable prevailing wage rates at the work site.
If federal funds are used to pay f or
the project, contractor and any subcontractor must agree to comply, as applicable, with the labor and reporting requirements of the Davis -Bacon Act (40 USC § 276a-7), the Copeland Act (40 USC § 276c and 18 USC § 874), and the Contract Work Hours and Safety Standards Act (40 USC § 327 and following).
Federal Wage Rates: For projects using federal funds that are subject to the Davis-Bacon Act (40 USC § 276a-7), a copy of the Federal determination of prevailing wages is available on the Internet at https://sam.gov/content/home and t he determinations must be complied with.
Prevailing wage determinations must also be posted at each job site. The successful bidder and any subcontractor must agree to comply, as applicable, with the labor and reporting requirements of the Davis -Bacon Act, the Copeland Act (40 USC § 276c and 18 USC §874), and the Contract Work Hours and Safety Standards Act (40 USC § 327 and following).
Payroll Records and P revailing Wage Monitoring: This project is subject to prevailing wage compliance monitoring and enforcement by the Department of Industrial Relations. (Labor Code § 1771.4.). Each contractor and subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the contractor or subcontractor in connection with the public work. These records must be certified and made available by the contractor as required by Labor Code section 1776. In the case of state -funded public works projects, certified payroll reports must be provided to District on a weekly basis. In the case of federally -funded public works project and in accordance with 29 C. F. R. § 5.5(a)(3), the contractor will be required to submit weekly payroll reports and compliance statements for this project.
Reservation of Rights: The Board of Directors reserves the right to reject any or all bids, waive any irregularities in the bids, and to make an award or any rejection in what it alone considers to be in the best interest of the District.
Dated this 31
st day of July, 2025.
CAMARILLO SANITARY DISTRICT
By:
James Campero
District Engineer
(8-2023)
INSTRUCTIONS TO BIDDERS
- 1 -
CAMARILLO SANITARY DISTRICT
INSTRUCTIONS TO BIDDERS
WORK IDENTIFICATION: WASTEWATER SYSTEM GENERATOR
REPLACEMENT AT PS3 & PS5
PROJECT NO. SS-5120-1
1. Terms Defined
1.1 Terms used in these Instructions to Bidders which are defined in the General Conditions/Specifications have the meaning assigned to them in the General Conditions/Specifications.
1.2 The term “successful bidder” means the lowest, responsible bidder to whom District makes an award of contract on the basis of District’s evaluation as provided in these Instructions.
1.3 The term “Standard Specifications” or “S.S.P.W.C.” means Standard Specifications for Public Works Construction written and promulgated by Public Works Standards, Inc., 2024 edition and all supplements thereto, available from BNi Publications, Inc., 990 Park Center Drive, Suite E Vista, CA 92081.
2. Copies of Contract Documents
2.1 Bidders may obtain complete sets of the Contract Documents from PlanetBids, the Camarillo Sanitary District website, or the District’s Public Works Department for the sum stated in the notice inviting bids.
2.2 Bidders will use a complete set of Contract Documents in preparing bids.
2.3 The District makes copies of the Contract Documents available, on the above terms, for the sole purpose of obtaining bids for the Work and does not confer a license or grant permission for any other use of the Contract Documents.
2.4 Complete sets of Contract Documents must be used in preparing bids. It is the bidder’s obligation to ensure that the bidder has received a complete set of Contract Documents. Neither District nor its agents, officers or employees assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Contract Documents.
The District does not assume any liability or responsibility based on any defective or incomplete copying, excerpting, scanning, faxing, downloading, or printing of the Bidding Documents.
3. Qualifications of Bidder
3.1 The District will accept bids only from bidders that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to (8-2023)
INSTRUCTIONS TO BIDDERS
- 2 -
Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code §7029.1) or if federal funds are involved in the project, then District may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded. This is a separate requirement from the Contractors State License Board licensing requirement below.
3.2 The bidder must be licensed to perform as prime contractor in accordance with the provisions of the Contractor’s State License Law (Bus. & Prof. Code § 7000 and following). Prior to awarding a bid, unless an exemption set forth in Business and Professions Code section 7028.15 applies, District will verify that the bidder was properly licensed when the bid was submitted. If a bidder was not so licensed, the bid will be considered non -responsive and will be rejected by District.
Under Public Contract Code section 3300, the bidder must possess at the time a contract is awarded all classifications of contractor’s licenses required by the District. For this project, the District requires that the bidder possess a valid Class A contractor’s license.
3.3 In addition to a state license, the contractor must also obtain a City of Camarillo business tax certificate before commencing work. The business tax certificate may be secured after the bids are opened, but prior to executing the contract. The business tax certificate must be kept current throughout the project until the recording of the Notice of Completion.
3.4 In order for District to determine the successful bidder, the bidder must be prepared to submit in writing, within five days after being requested to do so by District, such information and data as District may request, including without limitation, financial data, and previous experience. District reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy District that the bidder is the lowest responsible bidder properly qualified to carry out the contract.
3.5 The bidder may be required to establish to the satisfaction of District the reliability and responsibility of the persons or entities proposed to furnish and perform the work described in the Contract Documents.
3.6 Experience: The bidder must have a minimum of 3-years of experience in constructing work similar in character and magnitude to the work included in the bid. The work must be prosecuted with employees meeting the experience requirements along with appropriate apprentices. Employees used for satisfying this experience requirement or alternate staff with equal or better experience must be used continuously for the duration of the project.
Changes in staffing must be submitted for approval by the Engineer.
4. Examination of Contract Documents and Site
4.1 Before submitting a bid, the bidder must: (i) examine the Contract Documents thoroughly, including without limitation the Contract wherein each of the other Contract Documents is identified; (ii) visit the site and the locality where the work is to be performed to become familiar with local conditions that may in any manner affect the cost, progress or performance of the work in strict accordance with the Contract Documents; (iii) become familiar with all federal, state and local laws, ordinances, rules and regulations that may in any manner affect the cost, progress or performance of the work in strict accordance with the (8-2023)
INSTRUCTIONS TO BIDDERS
- 3 -
Contact Documents; and (iv) study and carefully correlate bidder’s observations with the Contract Documents.
4.2 Under Public Contract Code section 3400 and the Contract Documents, all specifications are deemed to include the words “or equal,” provided, however, permissible exceptions may be noted in the General Conditions/Specifications.
4.3 Reports, if any, of investigations and test of subsurface and latent physical conditions at the work site or otherwise affecting cost, progress or performance of the work which have been relied upon by the District Engineer in preparing the drawings and specifications are identified in the Special Provisions. District will make copies of such reports available to any bidder upon request. These reports are not guaranteed as to accuracy or completeness, nor are they part of the Contract Documents. Before submitting the bid, the bidder must, at bidder’s expense, make such additional investigations and tests as the bidder may deem necessary to determine its bid for performance of the work in strict accordance with the Contract Documents.
4.4 Upon request to the office of the District Engineer at 601 Carmen Drive, Camarillo, 805-388-5340, District will provide each bidder reasonable access to the job site to conduct such investigations and tests as the bidder may deem necessary for submission of its bid. Bidders performing investigative testing must obtain permit and restore areas affected by such activities. Investigations and tests that cause unreasonable disruptions may not be permitted.
4.5 The lands upon which the work is to be performed, rights -of-way for access thereto and other lands designated for use by contractor in performing the work are identified in the Drawings and/or Specifications.
4.6 By submitting a bid, the bidder warrants that it has complied with every requirement of this Section 4 and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the work.
5. Interpretation
5.1 In the event of conflict between requirements as shown on the drawings and the specifications, the following order of precedence will govern: permits from other agencies; change orders; supplemental agreements and approved revisions to plans and specifications; Special Provisions ; General Conditions/Specifications; plan details ; Plans; Standard Plans; Standard Specifications; Reference Specifications. In the event of any discrepancy between any drawings and the figures written thereon, the figures will govern.
5.2 All questions about the meaning or intent of the Contract Documents must be submitted to the Engineer in writing not less than five days prior to the date for the opening of bids.
5.3 All interpretations will be issued by written Addenda, which will be on file in the office of the District Engineer at 601 Carmen Drive, Camarillo, and posted to the District’s website, PlanetBids, and distributed to the planrooms listed in the Notice Inviting Bids It is the bidder’s responsibility to determine if any Addenda have been issued. Failure of the bidder to receive any such Addenda will not relieve the bidder from any obligation under its submitted bid. (8-2023)
INSTRUCTIONS TO BIDDERS
- 4 -
5.4 Only interpretations issued by written Addenda will be binding. All such Addenda will become part of the Contract Documents. Interpretations issued orally or by any means other than as specified in this Section 5 will have no legal effect.
6. Bid Proposal
6.1 Bids MUST be submitted on the Camarillo Sanitary District PlanetBids Portal. Hard copy bids submitted or any other method of bid submission to the Camarillo Sanitary District will not be accepted. Each bid must be on a Bid Proposal furnished by District as part of the Contract Documents. Any change in, or addition to, the Bid Proposal or any other modification of the Bid Proposal which is not specifically called for in the Contract Documents or the omission from the Bid Proposal of any information or response which is specifically called for in the Contract Documents may result in District’s rejection of the bid as not being responsive to the Notice Inviting Bids.
6.2 All blanks in the Bid Proposal must be appropriately responded to. If an answer or other response to a blank is not applicable, the bidder should respond with “N.A.”
6.3 Bid on all items listed in the Bid Schedule including all Prices (Unit and Total).
6.4 State in figures the unit prices, lump sum prices and extensions as indicated, which will be the prices for which you propose to supply all services and materials and to perform all work required by the plans and specifications. All items described are to be construed as complete and in place.
6.5 Include in the items for which bids are entered, all work shown on the plans or required by the specifications for which a specific bid item is not provided.
6.6 The Bid Proposal may not contain any erasures, interlineations or other corrections, unless each such correction is suitably authenticated by affixing in the margin immediately opposite the correction the initials of the person(s) signing the bid.
6.7 The Bid Proposal and each Attachment must be executed in the manner required by Section 14 below.
6.8 No person, including without limitation, any individual, partnership or corporation, may make, file or be interested in more than one bid for the work unless alternate bids are specifically called for in the Specifications. A person that has submitted a sub-bid to a bidder or that has quoted prices of materials to a bidder is not disqualified from submitting a sub-bid or quoting prices to other bidders or making a prime bid.
6.9 When the Notice Inviting Bids indicates that this project is a federally-funded project and the Bid Proposal is for more than $100,000, the bidder and each of its subcontractors must submit signed copies of the Federal Certificate for Contracts, Grants, Loans and Cooperative Agreements.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 5 -
7. Submission of Bid
7.1 The bid must be submitted within the time prescribed, at the place and in the manner indicated in the Notice Inviting Bids.
7.2 The bid must be accompanied by bidder’s security in an amount equal to at least ten percent (10%) of the bid amount, which security must be lawful money of the United States of America and in one of the following forms: (i) cash; (ii) cashier’s check made payable to District; (iii) certified check made payable to District; or (iv) bid bond executed by a surety insurer authorized to do business in the State of California and made payable to District. If the security is a bid bond, it must be submitted on the form which is part of the Bid Proposal or on a form substantially similar thereto. (Public Contract Code § 20170.)
7.3 All bids must be accompanied with an uploaded scanned copy of the bid security uploaded to PlanetBids. The original security of the three (3) lowest bidders must be submitted to the Public Works Department at 601 Carmen Drive, Camarillo, California 93010, in a sealed envelope and be received or postmarked within three (3) District business days after the bid due date and time for the bid to be considered. The sealed envelope should list the Bidder’s Name and be plainly marked on the outside: “SEALED BID SECURITY FOR WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5 – PROJECT NO.
SS-5120-1.”
7.4 The bid form, bid security, and all other documents required to be submitted with the bid must be submitted via electronic transmission on the Camarillo Sanitary District PlanetBids portal site as further described in the Notice to Bidders.
7.5 Bidders must be registered on the Camarillo Sanitary District’s PlanetBids portal in order to submit a bid. Go to the PlanetBids portal site for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.
7.6 Submission of a bid on PlanetBids portal shall constitute acknowledgement and acceptance of all terms and conditions set forth herein.
8. Withdrawal or Modification of Bid
The bidder may withdraw or modify its bid in the PlanetBids Portal system at any time prior to the opening of bids.
9. Bids to Remain Open
All bids will remain open for 60 days after the date of the opening of bids. Prior to that date, District may, at its sole discretion, (i) release any bid and return the bidder’s security, or (ii) release all bids and return all bidder’s security, upon the successful bidder’s furnishing of the required bonds and certificate and any other required documents and return to District the required number of executed copies of the Contract.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 6 -
10. Errors In Bid
10.1 If a discrepancy between the unit price and the item total of a bid exists, the unit price will control unless the unit price is illegible, omitted, or the same as the item total, in which case the bid will be deemed nonresponsive. If applicable, the total bid amount will be adjusted according to any revised item totals.
10.2 If a discrepancy between the item totals and the total bid amount exists, the item totals will control unless the total bid is illegible or omitted, in which case the bid will be deemed nonresponsive.
10.3 Except as provided in Sections 10.4 and 10.5 below, bidders will not be released from their bids on account of error.
10.4 Where the prime contractor asserts a claim of inadvertent clerical error in the listing of a subcontractor, District will allow the substitution of the intended subcontractor under the procedures set forth in Public Contract Code section 4107.5.
10.5 Where the bidder gives District notice addressed to the District contact listed in the Project Administration page within five days of the opening of the bid and can establish to the satisfaction of District that a mistake was made which makes the bid materially different than intended, that the mistake was made in filling out the bid and not due to error in judgment or carelessness in inspecting the site or in reading the plans or specifications and specifies how the mistake occurred, District will relieve the bidder without forfeiture of security in accordance with Public Contract Code section 5100 and following.
11. Bid Analysis and Determination of Responsive Bid
11.1 After the bids have been opened and uploaded to PlanetBids , the Bid Schedule will be checked and compared; and after the withdrawal of any bids as provided in Section 8 above; and after errors in bids are adjusted as provided in Section 10 above, the results will be made public.
11.2 F ailure of a bidder to attend a mandatory pre-bid meeting will result in its Bid not being accepted and/or being rejected.
11.3 A b id from any individual, firm, partnership, corporation, or association which prepared, in part or in whole, the Plans, Specifications, or estimates for the Contract will be rejected.
11.4 More than one bid for the same Contract from any individual, firm, partnership, corporation, or association under the same or different names may be rejected.
Reasonable grounds for believing that any bidder has an interest in more than one b id for the Work may be cause for rejecting all bids in which such bidder is interested. However, this requirement does not prevent a bidder who submits a bid from being listed as a subcontractor by another bidder. Apparent collusion among bidders may be sufficient cause for rejecting any or all bids, and the participants in such collusion may be barred from future bidding.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 7 -
11.5 A bid in which a bid item is left totally blank will be considered nonresponsive and will be rejected.
11.6 A bid in which the Contract Unit Prices are unbalanced may be considered nonresponsive and may be rejected.
11.7 A b id in which the signature of the bidder has been omitted may be considered nonresponsive and may be rejected.
11.8 A bid in which each section of the Bid Proposal has not been completely filled out, or which shows any alteration of form or irregularities of any kind, or which contains any additions or conditional or alternate bids that are not called for, may be considered nonresponsive and may be rejected.
11.9 A b id in which the Acknowledgement of Addenda Received form is missing, or in which the receipt of each Addendum issued has not been acknowledged, may be considered nonresponsive and may be rejected.
11.10 A bid in which the Noncollusion Declaration form is missing, or in which the form has not been executed and signed, may be considered nonresponsive and may be rejected.
11.11 A b id in which the Request for Local D BE Program Preference Consideration and DBE Firm/Organization Information Form is missing, or in which the form has not been completely filed out, may be considered nonresponsive and may be rejected.
11.12 A bid in which the Bidder DBE Information form is required to be submitted with the bid and is missing, or in which the Bidder DBE Information is not submitted within the time specified in the Special Provisions, may be considered nonresponsive and may be rejected.
11.13 A bid in which the List of Subcontractors form is missing will be considered nonresponsive and will be rejected.
11.14 A b id in which the List of Subcontractors form or the Bidder DBE Information form is incomplete, or the data included therein is inaccurate, inconsistent, of a misrepresentation of the work to be subcontracted or materials to be procured, may be considered nonresponsive and may be rejected.
11.15 The bidder must perform, with its own organization, Contract work amounting to at least 50 percent of the Contract Price. A bid which fails to meet this requirement will be considered nonresponsive and will be rejected.
11.16 A bid in which the Bid Guaranty is missing, or in which the Bid Guaranty surety bond is not signed by the Surety, or in which the Surety has not had the Bid Guaranty surety bond notarized, or is not provided to the District, if one of the three lowest bidders, 3 business days after opening as further detailed in the NIB, will be considered nonresponsive and will be rejected.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 8 -
12. Award of Contract
12.1 District reserves the right to reject any and all bids. District also reserves the right to reject any bid that is not in strict accordance with the Contract Documents or, in the alternative, to waive any irregularity or informality in any bid or in the bidding.
12.2 If alternate bids are called for in the Specifications, the contract may be awarded at the election of District to the successful bidder on the base bid or on the base bid and any alternate or combination of alternates specifically identified in the Specifications as being used for the purpose of determining the lowest bid price.
12.3 If the contract is to be awarded, it will be awarded to the lowest responsible bidder. District may conduct such investigations as it deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of the bidders. The award, if made, will be within 60 days after the opening of bids.
12.4 If the lowest responsible bidder refuses or fails to execute the contract, District may consider the next lowest bidder to be the lowest responsible bidder.
12.5 The periods of time specified in this Section within which the award of contract may be made, are subject to extension for such further period as may be agreed upon in writing between District and the bidder concerned.
13. Delivery of Contract
13.1 An official “Notice of Award of Contract” will be emailed or mailed to the successful bidder, enclosing the contract and bond forms for signature.
13.2 Within 10 days after the Notice of Award of Contract, the successful bidder must sign and deliver at least three counterparts of the Contract to the Camarillo Sanitary District together with security in a form acceptable to District’s Legal Counsel’s office guaranteeing both one hundred percent (100%) of payment (labor and materials) and one hundred percent (100%) of performance, certificates and endorsements to satisfy the insurance requirements of the Contract, proof of a valid City of Camarillo business tax certificate and any other documents required by the Contract Documents. Bonds must be submitted on the forms which are part of the Contract Documents; no substitutions will be accepted. Within 10 days of receipt of the Contract and related documents, District will deliver one fully signed counterpart of the Contract to the successful bidder.
13.3 The Contract and each attachment must be executed in the manner required by Section 14 below.
13.4 If the successful bidder fails to execute and deliver the Contract and furnish the required bonds, certificates and other documents within 10 days after the Notice of Award of Contract, District may annul the award of the contract and the bidder’s security will be forfeited, except as provided by Public Contract Code section 20174.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 9 -
14. Signatures
14.1 The Contract Documents and all attachments must be executed in the following manner: If the bidder is:
(a) An individual, in the name of the individual and if doing business by a fictitious name, the fictitious name and, if the document is the Bid Proposal or Contract, the business address and telephone number of the individual must be shown below the signature.
(b) A partnership, in the partnership name and signed by a general partner, whose title must appear under the signature and, if the document is the Bid Proposal or Contract, the business address and telephone number of the partnership must be shown below the signature.
(c) A corporation, in the corporate name by a duly authorized officer or agent accompanied by evidence of authority to sign and the corporate seal must be affixed and attested by the secretary or an assistant secretary. If the document is the Bid Proposal or Contract, the state of incorporation must be shown below the corporation name, and the corporate address and telephone number must be shown below the signatures.
14.2 Attorneys-in-fact who sign any Contract Document or any attachment thereto must file with the document a certified copy of their power of attorney to sign such document.
14.3 Electronic Signatures; Documents will be considered executed when the signature page of a party is delivered by electronic transmission. Such electronic signatures will have the same effect as an original signature.
14.4 Signatures on all bonds must be acknowledged before a notary public and a notary’s certificate of each acknowledgment must be scanned and uploaded to PlanetBids with the document.
15. Time for Commencement and Completion
15.1 Unless otherwise specified in the Special Provisions, the contractor must:
(a) commence the work within 30 days after the award of the contract by the Board of Directors, but not before fully complying with Sections 13 and 14 above; and
(b) diligently prosecute the work to completion within the allowed number of working days specified on Page 1 of the Bid Proposal, counting from the start date given in the Notice to Proceed.
15.2 Upon written request of the Contractor and if approved in writing by the District Engineer, the time for commencement, completion or both may be extended.
(8-2023)
INSTRUCTIONS TO BIDDERS
- 10 -
16. Bid Protest
16.1 An y protest of any bid must be submitted in writing to the Office of the District Assistant Secretary by email to [email protected] or by facsimile transmission to 805-388-5318 no later than 5:00 PM on the seventh calendar day following the date of the bid opening.
16.2 The protest must contain a complete statement of the factual basis for the protest and copies of pertinent documents.
16.3 The protest must identify the specific portion of the document and the specific statute, if any, that forms the basis for the protest. The protest must include the name, mailing address, email address and telephone number of the person representing the protesting party.
16.4 The party filing the protest must have actually submitted a bid for the Project. A subcontractor of a party filing a bid for the Project may not submit a bid protest. A party may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest.
16.5 The procedure and time limits set forth in these Instructions to Bidders are mandatory and are the bidders’ sole and exclusive remedy in the event of a bid protest. Any bidder’s failure to fully comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including filing of a challenge of the award pursuant to the Public Contract Code, filing of a claim pursuant to the Government Code, or filing of any other legal proceedings.
16.6 The Assistant District Manager, or designee, will review all timely protests prior to award of the Project and will recommend that the Board of Directors either reject the protest and award to the lowest responsible and responsive bidder or accept the protest and award the bid to the next lowest responsible and responsive bidder.
17. Liquidated Damages
The amount of liquidated damages for each calendar day , is set forth on page 1 of the Bid Proposal, in accordance with Section 6.5 of the General Conditions/Specifications.
18. Survey Data
18.1 Electronic survey data will not be made available to the bidder as part of the bid process and no such data should be relied upon for the purposes of preparing the bid.
Survey data desired by bidders should be obtained in the field by the bidder. Permits for survey work may be necessary.
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 1 -
CAMARILLO SANITARY DISTRICT
BID PROPOSAL
FOR
WASTEWATER SYSTEM GENERATOR REPLACEMENT AT
PS3 & PS5
PROJECT NO. SS-5120-1
In and for the
CAMARILLO SANITARY DISTRICT
CITY OF CAMARILLO, CALIFORNIA
Project Number SS-5120-1, including Thirty-Seven (37) sheets of plans. Drawings Numbers C-18792 to C-18828.
Completion Time: One Hundred (100) Working Days
Bids To Be Received: 3 :00 p.m. on September 18, 2025__
Liquidated Damages: Project Milestone Dates as follows:
Project Complete: $2,000 Per Calendar Day
Name of Contractor
Address
Telephone
State Contractor’s License Number
Department of Industrial Relations Registration Number
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 2 -
BID PROPOSAL
WORK IDENTIFICATION: WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5 – PROJECT NO. SS-5120-1
NAME AND ADDRESS OF BIDDER:
Before awarding a bid, District will verify that bidder was properly licensed in accordance with Business and Professions Code sections 7000 and following. District will also verify that bidder that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code §7029.1) or if federal funds are involved in the project, then District may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded. Bidder acknowledges that if the bidder is not properly licensed or registered at the time the bid is awarded or as otherwise required by law, the bid will be considered non-responsive and will be rejected.
1. Proposal
(a) Bidder has examined copies of all of the Contract Documents, including without limitation the document wherein each of the other Contract Documents is identified, and accepts all of the terms and conditions of the Contract Documents.
(b) Bidder proposes and agrees, if this bid is accepted, to enter into an agreement with District in the form included in the Contract Documents to complete all work as specified in the Contract for the contract price and within the contract time indicated in this bid and in accordance with the Contract Documents.
(c) This bid will remain open and not be withdrawn for the period specified in the Instructions to Bidders. If awarded the bid, bidder will sign the Contract and submit the bonds, certificates and other documents required by the Contract Documents within 10 days after the date of the Notice of Award of Contract.
(d) Bidder has examined the site and locality where the work is to be performed and the legal requirements and conditions affecting the cost, progress and performance of the work in strict accordance with the Contract Documents.
2. Payroll and Compliance Reports
Each contractor and subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the contractor or subcontractor in connection with the public work. Such records must be certified and made available for inspection at all reasonable hours at the principal place of the contractor as required by Labor Code section 1776. In the case of state funded public works projects, certified payroll reports (5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 3 -
must be provided to District on a weekly basis. In the case of federally -funded public works project and in accordance with 29 C.F.R. § 5.5(a)(3), bidder agrees to furnish to District weekly payroll reports and weekly compliance statements for all labor used on this project.
3. Bid
If the Contract Documents include a Unit Price List, bidder acknowledges that the total bid sum shown on the Bid Schedules(s) and the estimated quantities and amounts shown on the Unit Price List are for purposes of comparison of bids only. Bidder also acknowledges that District does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work as may be deemed necessary or expedient by the District and that final payment will be made at the unit prices bid, upon the basis of actual measured quantities as determined by the District Manager or his/her designee.
Bidder acknowledges that the total Bid Schedule(s) and all sums shown on any Unit Price List attached thereto, includes (i) all labor, materials, tools, equipment and services and all taxes, insurance, other general expenses, overhead and profit and (ii) all trenching, backfilling, grading, excavation and fill, resurfacing of every character, grubbing and clearing and removal of all obstructions necessary for the doing of the work, the preservation of existing structures, shrubs, and trees, where required, and the shoring, bridging and bracing required and incident to the doing of the work, together with all fittings and joints, of every character, connected in place, area clean-up, traffic protection, and the reconstruction and severances required in the doing of the work.
Items for which quantities are indicated as “Lump Sum,” “L.S.,” “job” or words of like import will be paid for at the price named. Such payment will be full compensation for the work named and all work appurtenant thereto required by the contract that is not specifically provided for by other pay items.
4. Schedule
Bidder understands that timely completion is important to District. Therefore, time being of the essence, bidder proposes that the work will be commenced and will be completed as specified herein and in Section 15 of the Instructions to Bidders.
5. Addenda
Bidder acknowledges receipt of Addenda identified as:
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 4 -
6. Bidder Information
(a) Bidder has ________ years of experience as a contractor in construction work.
(b) Bidder has recently completed the three following construction works similar in character and magnitude to the work included in the bid in accordance with Section 3.6 of the Instructions to Bidders:
Class
Amount
Class
of Work
Date
Completed
Name/Address/Telephone # of Owner
7. Designation of Subcontractors
In compliance with the Subletting and Subcontracting Fair Practices Act, Public Contracts Code section 4100 and following, listed on page 5 is each subcontractor who will perform work or labor or render service to the bidder in or about the construction of the work or will specifically fabricate and install a portion of the work in an amount in excess of one half of one percent (0.5%) of the total bid sum or in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of one percent (0.5%) of the total bid or $10,000, whichever is greater. (List only one subcontractor for each portion of the work as is defined by the bidder in this bid.) No other subcontractors may be used other than those specified without written approval of the District Manager; such approval will be made upon showing by the contractor of good and sufficient cause.
Failure to specify a subcontractor or specifying more than one subcontractor for the same portion of work to be performed under the contract in excess of one -half of one percent (0.5%) of the total bid constitutes an agreement that the contractor is fully qualified and will perform that portion of the work. Any contractor who subcontracts for any portion of work not set forth herein, except as otherwise provided by Public Contract Code sections 4107 or 4109, will be subject to the penalties set forth in Public Contract Code sections 4110 and 4111.
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 5 -
PROPOSAL
LIST OF SUBCONTRACTORS
WORK IDENTIFICATION: ________________
NAME AND ADDRESS OF BIDDER:
Completion of this form must comply with Section 7 of the Bid Proposal.
Name/Address/State License
Number of Subcontractor
Department of Industrial
Relations Registration
Number*
Items of Work
Portion of Work
(% of Contract Price)
% of Total Contract
Price by Subcontract
% of Total Contract
Price by Contractor
*Pursuant to Division 2, Part 7, Chapter 1 (commencing with section 1720 including section 1725.5) of the Labor Code
8. Attachments
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 6 -
The following documents, signed in accordance with Section 7 of the Instructions to Bidders, are attached to, and made a part of, this Bid Proposal:
(a) Noncollusion Declaration, as required by Public Contract Code section 7106 and made a part of this Bid Proposal.
(b) Required Bidder’s Security in the form of
(c) Unit Price List, if required
(d) Federal Certificate, if required
(e) Other pertinent Documents (list here and attach to this bid)
Dated this __________ day of ____________________, 20____. (5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 7 -
If BIDDER is:
An Individual
By:
(Print Individual’s Name)
doing business as
Business Address:
Telephone Number:
Signature
A Partnership
(Firm Name)
By:
(Print General Partner’s Name)
(Title)
Business Address:
Telephone Number:
Signature
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 8 -
A Corporation
(Corporation Name)
(State of Incorporation)
By:
(Print Name and Title of Person Authorized to Sign)
(Corporate Seal)
Signature
Attest:
(Secretary)
Business Address:
Telephone Number:
Signature
A Joint Venture
By:
(Print Name)
(Address and Telephone Number)
By:
(Print Name)
(Address and Telephone Number)
Signature
Signature
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 9 -
NONCOLLUSION DECLARATION
TO BE EXECUTED BY BIDDER
AND SUBMITTED WITH BID
The undersigned declares:
I am the _________________ of ______________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham.
The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Executed this ________ day of ___________________, 20___, at _____________________, California.
Firm (print or type) Signature
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 10 -
BID SCHEDULE
UNIT PRICE LIST -- FIGURES
WORK IDENTIFICATION WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5 – PROJECT NO. SS-5120-1
NAME OF BIDDER:
Item
No. Item Description Quantity Unit
Payment
Reference
Unit Price
in Figures
*Item Total
Price in
Figures
1 Mobilization 1 LS 01200
2 Stormwater Pollution Control Plan
Implementation 1 LS 01200
3 Demolition
1 LS 01200
4 Site Work 1 LS 01200
5 Concrete 1 LS 01200
6 Electrical and Instrumentation 1 LS 01200
7 Temporary Bypass Pumps 1 LS 01200
8 New Generator/ATS/MTS Installation
1 LS 01200
9 All Other Work Required in Base Bid Scope of
Work 1 LS 01200
TOTAL BID $
NOTE: Pu rsuant to Public Contract Code section 20103.8, the Camarillo Sanitary District will determine the lowest bid based on the total of the Base Bid.
*NOTE: In case of error in extension of price into the total price column, the unit price will govern. (5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 11 -
BIDDER’S INFORMATION CERTIFICATION
Bidder certifies that the following information is true and correct:
Bidder’s Name
Business Address
Telephone
State Contractor’s License No. and Class
Original Date Issued Expiration Date
The following are the names, titles, addresses, and phone numbers of all individuals, firm members, partners, joint venturers, or corporate officers having a principal interest in this bid:
The dates of any voluntary or involuntary bankruptcy judgments against any principal having an interest in this bid are as follows:
All current and prior DBAs, alias, and/or fictitious business names for any principal having an interest in this bid are as follows:
I declare under penalty of perjury under the laws of the State of California that the above representations are true and correct.
Executed this ________ day of ___________________, 20___, at _____________________, California.
Signature and Title of Authorized Official
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 12 -
DECLARATION OF ELIGIBILITY TO CONTRACT
The undersigned, a duly authorized representative of the bidder, certifies and declares that:
1. The bidder is aware of Labor Code sections 1771.1 and 1777.7, which prohibit a contractor or subcontractor who has been found by the Labor Commissioner or the Director of Industrial Relations to be in violation of certain provisions of the Labor Code from bidding on, being awarded, or performing work as a subcontractor on a public works project for specified periods of time.
2. The bidder is currently registered and qualified to perform public work pursuant to Labor Code section 1725.5 and is not prohibited from bidding on, being awarded, or performing work as a contractor o r subcontractor on a public works project under Labor Code sections 1771.1 and 1777.7, or any other provision of law; provided, however, that if a bidder is a joint venture (Business & Professions Code § 7029.1) or if federal funds are involved in the project, then District may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded.
3. The bidder is aware of Public Contract Code section 6109, which states:
(a) A public entity, as defined in Section 1100 [of the Public Contract Code], may not permit a contractor or subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to Section 1771.1 or 1777.7 of the Labor Code to bid on, be awarded, or perform work as a subcontractor on, a public works project. Every public works project shall contain a provision prohibiting a contractor from performing work on a public works project with a subcontractor who is ineligible to perform work on the public works project pursuant to Section 1777.1 or 1777.7 of the Labor Code. (b) Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract, and any public money that may have been paid to a debarred subcontractor by a contractor on the project will be returned to the awarding body. The contractor is responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project.
4. The bidder has investigated the eligibility of each and every subcontractor that bidder intends to use on this public works project, and determined that none of them is ineligible to perform work as a subcontractor on a public works project by virtue of Public Contract Code section 6109, Labor Code sections 1725.5, 1771.1 and 1777.7, or any other provision of law.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Executed this ________ day of ___________________, 20___, at ______________________, California.
Signature and Title of Authorized Official
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 13 -
BID BOND
(not necessary when certified check or cash accompanies bid)
PROJECT TITLE: ___________________
WHEREAS,
(“Contractor”) intends to submit a bid to the Camarillo Sanitary District, California, a sanitary district (“District”), for the work identified as follows:
NOW, THEREFORE, we, the Contractor, as Principal, and
,
a corporation organized and existing under the laws of the State of and duly authorized to transact business under the laws of the State of California, as Surety, are held and firmly bond unto District in the sum of
dollars ($ )
lawful money of the United States of America, such sum being not less than ten percent (10%) of the bid amount for the payment of which sum to be made, the Principal and Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if District accepts the bid of the Principal and enters into a contract in accordance with the terms of the bid, the Principal must give the bonds, certificates and other documents as required by the Notice Inviting Bids or the other contract documents. In the event Principal fails to enter into such contract or provide the bonds, certificates or other documents, District may apply this security to the difference between the low bid and the next lowest bidder with whom District contracts to perform the work covered by the bid; the surplus, if any, will be returned to Surety. In case suit is brought upon this bond, the court will fix and award and the Surety must pay, in addition to the face amount hereof, all costs and reasonable attorney’s fees incurred by District in successfully enforcing the obligations of this bond.
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 14 -
IN WITNESS THEREOF, we have hereunto set our hands and seals this day of , 20 .
(affix seal below) [PRINCIPAL]
By
Title
(affix seal below) [SURETY]
By
Title
Address
[P.C.C. §§ 20170, 20171]
* ALL SIGNATURES ON THIS BID BOND MUST BE NOTARIZED USING APPROPRIATE 8 ½” x 11” NOTARY ACKNOWLEDGEMENT FORM.
** Corporations must affix corporate seal.
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 15 -
CERTIFICATION FOR CONTRACTS,
GRANTS, AND COOPERATIVE AGREEMENTS
(Federal Fiscal Year October 1, 20____, to September 30, 20____)
I, ,
(Name and Title of Grantee Official)
hereby certify on behalf of that
(Name of Grantee)
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an office or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned must complete and submit Standard Form -LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.
This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U. S. Code. Any person who fails to file the required certification will be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Executed this __________ day of __________________, 20____.
By:
(Signature of Authorized Official)
(Title of Authorized Official)
(5-2023) Project No. __SS-5120-1___
BID PROPOSAL
- 16 -
CERTIFICATION REGARDING DEPARTMENT OF INDUSTRIAL
RELATIONS CONTRACTOR / SUBCONTRACTOR REGISTRATION
By my signature hereunder, as the Contractor, I certify that Contractor, and all Subcontractors listed on the “List of Subcontractors” are registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
Contractor’s Department of Industrial Relations registration number is _____________.
Subcontractors’ Department of Industrial Relations registration numbers are as indicated in the Subcontractors List.
Executed this __________ day of __________________, 20____.
By:
(Signature of Authorized Official)
(Title of Authorized Official)
(5-2025) Project No. SS-5120-1
CONTRACT
CAMARILLO SANITARY DISTRICT
PUBLIC WORKS CONTRACT
This contract (“Contract”) is effective as of __________________________, and is between the C AMARILLO SANITARY DISTRICT , a sanitary district organized pursuant to the California Health and Safety Code (“District”), and ___________________________________, a corporation/partnership/limited liability company (“Contractor”), collectively referred to as the “Parties.”
Section 1. Recitals. This Contract is entered into with respect to the following facts:
1.1 District noticed and received bids for the work involved in Wastewater System Generator Replacement at PS3 & PS5 - Project No. SS-5120-1 (“Project”), which is more fully described in the Contract Documents.
1.2 The Board of Directors of District determined that Contractor was the lowest responsive bidder and awarded to Contractor the bid.
1.3 Contractor has represented it is qualified to perform all of the work required to complete the Project.
1.4 Contractor has agreed to perform all such work in the time and manner set forth in the Contract Documents.
1.5 The Board of Directors of District has determined that the public interest, convenience and necessity require the execution of this Contract and its implementation.
Section 2. Contract Documents. This Contract consists of the following documents (“Contract Documents”), all of which are made a part of this Contract:
2.1 Notice Inviting Bids
2.2 Instructions to Bidders
2.3 Bid Proposal, as accepted, including the Certificate of Bidders’ Experience and Qualifications and the List of Subcontractors
2.4 Notice of Award
2.5 Notice to Proceed
2.6 This Contract
2.7 Verification of California Contractor’s License
2.8 Contractor’s Certificate Regarding Workers’ Compensation
2.9 Security for payment (labor and materials)
(5-2025) Project No. SS-5120-1
CONTRACT
2.10 Security for performance
2.11 Certificate(s) of Insurance
2.12 General Conditions/Specifications
2.13 Special Provisions
2.14 Plans and Standard Drawings
2.15 Prevailing Wage Scales
2.16 S. S. P. W. C.
2.17 Addenda Nos.
2.18 Other documents (list here)
Exhibit A – Compensation
Exhibit B – Insurance
Exhibit C – Not Used
Exhibit D – Adjustment for New Tariffs or Tariff Increases Section 3. The Work.
3.1 The work (“Work”) to be performed by Contractor is described in the Contract Documents.
3.2 In completing the Work, Contractor must employ, at a minimum, the applicable generally accepted professional standards of its industry in existence at the time of performance as utilized by persons engaging in similar work.
3.3 Except as specifically provided in the Contract Documents, Contractor must furnish, at its sole expense, all of the labor, materials, tools, equipment, services and transportation necessary to perform all of the Work.
3.4 Contractor must perform all of the Work in strict accordance with the Contract Documents.
Section 4. Time to Perform the Work.
4.1 Time is of the essence with respect to Contractor’s Work. Contractor agrees to diligently pursue performance of the Work within the time specified by the Contract Documents.
4.2 Contractor will be excused from any delay in performance or failure to perform due to causes beyond the control of Contractor. Such causes include, but are not (5-2025) Project No. SS-5120-1
CONTRACT
limited to, acts of God, acts of terrorism, acts of federal, state or local governments, acts of District, court orders, fires, floods, epidemics, strikes, embargoes, and unusually severe weather.
4.3 If Contractor is delayed by any cause beyond Contractor’s control, District may, but is not required to, grant a time extension for the completion of the Work. If delay occurs, Contractor must notify District in writing within 48 hours of the cause and the extent of the delay and how such delay interferes with Contractor’s performance of the Work.
Section 5. Compensation and Payment.
5.1 Subject to any limitations provided in the Contract Documents, District agrees to pay Contractor as full consideration for the faithful performance of all of the Work the compensation set forth in Exhibit A (“Compensation”), which is made a part of this Contract.
5.2 Contractor must furnish District with a Pay Estimate for the Work performed in accordance with the Contract Documents. Contractor may not submit a Pay Estimate more often than once every 30 days.
5.3 District will review each Pay Estimate and determine whether the Work performed is in accordance with the Contract Documents. The Assistant District Manager may require Contractor to provide a release of all undisputed Contract amounts contained in the Pay Estimate.
5.4 If District disputes any item on a Pay Estimate, District will give Contractor notice stating the reasons for the dispute. The Parties will meet and confer in good faith to attempt to resolve the dispute.
5.5 Except as to any charges for the Work performed that District disputes and the District’s standard five-percent retention of the approved progress payment, District will cause Contractor to be paid within 30 days of the date of the invoice or the date that Contractor furnishes District with a release of all undisputed Contract amounts, whichever occurs later. Federally funded projects will not have a five- percent retention.
5.6 In the event there is any claim specifically excluded by Contractor from the operation of any release, District may retain an amount not to exceed the amount of the excluded claim.
Section 6. Labor Code and Prevailing Wage Requirements.
6.1 Contractor agrees to comply with the requirements of California Labor Code sections 1810 through 1815. Eight hours of labor constitutes a legal day’s work per Labor Code section 1810. Contractor will forfeit the statutory penalty to District for each worker employed in the execution of this Contract by Contractor or any subcontractor for each calendar day during which such worker is required or permitted to work more than eight hours in any one calendar day and 40 hours in (5-2025) Project No. SS-5120-1
CONTRACT
any one calendar week in violation of the provisions of Labor Code sections 1810 through 1815.
6.2 Copies of the determination of the Director of the Department of Industrial Relations of the prevailing rate of per diem wages for each craft, classification or type of worker needed to execute this Contract are available for download from the State website: https://www.dir.ca.gov/OPRL/dprewagedetermination.htm.
6.3 Contractor must post at the work site, or if there is no regular work site then at its principal office, for the duration of the Contract, a copy of the determination by the Director of the Department of Industrial Relations of the specified prevailing rate of per diem wages. (Labor Code § 1773.2.) When applicable, copies of the prevailing rate of per diem wages will be on file at District’s Department of Public Works and available to Contractor and any other interested party upon request.
6.4 Contractor, and any subcontractor engaged by Contractor, may pay not less than the specified prevailing rate of per diem wages to all workers employed in the execution of the contract. (Labor Code § 1774.) Contractor is responsible for compliance with Labor Code section 1776 relative to the retention and inspection of payroll records.
6.5 Contractor must comply with all provisions of Labor Code section 1775. Under Section 1775, Contractor will forfeit the statutory penalty to District for each worker employed in the execution of the Contract by Contractor or any subcontractor for each calendar day, or portion thereof, in which the worker is paid less than the prevailing rates. Contractor may also be liable to pay the difference between the prevailing wage rates and the amount paid to each worker for each calendar day, or portion thereof, for which each worker was paid less than the prevailing wage rate.
6.6 Nothing in this Contract prevents Contractor or any subcontractor from employing properly registered apprentices in the execution of the Contract. Contractor is responsible for compliance with Labor Code section 1777.5 for all apprenticeable occupations. This statute requires that contractors and subcontractors must submit contract award information to the applicable joint apprenticeship committee, must employ apprentices in apprenticeable occupations in a ratio of not less than one hour of apprentice’s work for every five hours of labor performed by a journeyman (unless an exception is granted under § 1777.5), must contribute to the fund or funds in each craft or trade or a like amount to the California Apprenticeship Council, and that contractors and subcontractors must not discriminate among otherwise qualified employees as apprentices solely on the ground of sex, race, religion, creed, national origin, ancestry or color. Only apprentices defined in Labor Code section 3077, who are in training under apprenticeship standards and who have written apprentice contracts, may be employed on public works in apprenticeable occupations.
6.7 Contractor has reviewed and agrees to comply with any applicable provisions for any public work subject to Department of Industrial Relations (DIR) Monitoring and Enforcement of prevailing wages, including the registration requirements of Labor Code Section 1771.1(a). District hereby notifies Contractor that Contractor is (5-2025) Project No. SS-5120-1
CONTRACT
responsible for submitting certified payroll records directly to the State Compliance Monitoring Unit (CMU). For further information concerning compliance monitoring please visit the website location at: https://www.dir.ca.gov/dlse/cmu/cmu.html.
6.8 Contractor must comply with Labor Code section 1771.1(a), which provides that Contractor may award any contracts and subcontracts for work that qualifies as a “public work” only to subcontractors which are at that time registered and qualified to perform public work pursuant to Labor Code Section 1725.5. Contractor must obtain proof of such registration from all such subcontractors.”
6.9 If federal funds are used to pay for the Work, Contractor and any subcontractor agree to comply, as applicable, with the labor and reporting requirements of the Davis-Bacon Act (40 USC § 276a-7), the Copeland Act (40 USC § 276c and 18 USC §874), and the Contract Work Hours and Safety Standards Act (40 USC § 327 and following).
Section 7. Non-Discrimination. Contractor, its officers, agents, employees, and subcontractors may not discriminate in the employment of persons to perform the Work in violation of any federal or state law prohibiting discrimination in employment, including based on the race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation, of any person, except as provided under California Government Code section 12940. Contractor is responsible for compliance with this section.
Section 8. General Legal Compliance.
8.1 In performing the Work, Contractor must comply with all applicable statutes, laws and regulations, including, but not limited to, OSHA requirements and the Camarillo Municipal Code.
8.2 Contractor must, at Contractor’s sole expense, obtain all necessary permits and licenses required for the Work, and give all necessary notices and pay all fees and taxes required by law, including, without limitation, any business license tax imposed by District. Contractor is exempt from any City encroachment permit fee pursuant to Camarillo Municipal Code Section 13.04.020.
8.3 Contractor must maintain a valid California Contractor’s License throughout the term of this Contract.
Section 9. Clayton and Cartwright Act Assignments. In entering into this Contract or a contract with a subcontractor to supply goods, services, or materials pursuant to this Contract for the Project, Contractor and any subcontractor will be deemed to have offered and agreed to assign to District all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700 of Part 2 of Division 7 of the California Business and Professions Code), arising from purchases of goods, services, or materials for the Project. This assignment will be deemed made and will become effective at the time District tenders final payment to Contractor, without further acknowledgement by the Parties. (5-2025) Project No. SS-5120-1
CONTRACT
Section 10. Independent Contractor. Contractor is and will at all times remain as to District a wholly independent contractor. Neither District nor any of its officers, employees, or agents will have control over the conduct of Contractor or any of Contractor’s officers, employees, agents or subcontractors, except as expressly set forth in the Contract Documents. Contractor may not at any time or in any manner represent that it or any of its officers, employees, agents, or subcontractors are in any manner officers, employees, agents or subcontractors of District.
Section 11. Indemnification.
11.1 Contractor agrees to the fullest extent permitted by law to (1) immediately defend and (2) indemnify District from and against, any and all claims and liabilities, regardless of the nature or type, that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor, or its officers, employees, agents, or subcontractors committed in performing any Work under this Contract or the failure to comply with any of the obligations of this Contract (collectively, “Claims”). The Claims subject to Contractor’s duties to defend and indemnify include, without limitation, all claims, actions, causes of action, proceedings, suits, losses, damages, penalties, fines, judgments, liens, levies, and associated investigation and administrative expenses. Such Claims also include defense costs, including reasonable attorneys’ fees and disbursements, expert fees, court costs, and costs of alternative dispute resolution.
11.2 Contractor’s duty to defend is a separate and distinct obligation from Contractor’s duty to indemnify. Contractor is obligated to defend District in all legal, equitable, administrative, or special proceedings, with counsel approved by District, immediately upon tender to Contractor of the Claim in any form or at any stage of an action or proceeding, whether or not liability is established. An allegation or determination that persons other than Contractor are responsible for the Claim does not relieve Contractor from its separate and distinct obligation to defend under this section. The obligation to defend extends through final judgment, including exhaustion of any appeals. The defense obligation includes an obligation to provide independent defense counsel if Contractor asserts that liability is caused in whole or in part by the negligence or willful misconduct of any District indemnified party. If it is finally adjudicated that liability was caused by the comparative active negligence or willful misconduct of any District indemnified party, then Contractor may submit a claim to District for reimbursement of reasonable attorneys’ fees and defense costs in proportion to the established comparative liability of the District indemnified party.
11.3 Contractor agrees that its defense and indemnification obligation under this section, includes the reasonable costs of attorneys’ fees incurred by the District’s legal counsel to monitor and consult with Contractor regarding the defense of any Claims, including providing direction with regard to strategy, preparation of pleadings, settlement discussions, and attendance at court hearings, mediations, or other litigation related appearances. District will use its best efforts to avoid duplicative attorney wor k or appearances in order to keep defense costs to a reasonable minimum.
(5-2025) Project No. SS-5120-1
CONTRACT
11.4 Contractor agrees that settlement of any Claim will require the consent of District.
District agrees that its consent will not be unreasonably withheld provided that Contractor is financially able (based on demonstrated assets) to fulfill its obligation to indemnify District for the costs of any such settlement as required under this Contract.
11.5 Contractor’s obligation to indemnify District applies unless it is finally adjudicated that the liability was caused by the sole active negligence or sole willful misconduct of a District indemnified party. If a Claim is finally adjudicated and a determination made that liability was caused by the sole active negligence or sole willful misconduct of a District indemnified party, then Contractor’s indemnification obligation will be reduced in proportion to the established comparative liability.
11.6 For the purposes of this section, “ District” includes District’s officers, officials, employees and agents.
11.7 The provisions of this section will survive the expiration or earlier termination of this Contract.
Section 12. Insurance. Contractor agrees to have and maintain in full force and effect during the term of this Contract the insurance coverages listed in Exhibit B (“Insurance”), which is made a part of this Contract.
Section 13. Notice.
13.1 All written notices required or permitted to be given under this Contract will be deemed made when received by the other Party at its respective address as follows:
To District: C amarillo Sanitary District
601 Carmen Drive
Camarillo, California 93010
Attention: James Campero
(Tel.) 805-388-5340
(Fax) 805-388-5387
E-Mail [email protected]
To Contractor:
Attention:
(Tel.)
(Fax)
E-Mail
13.2 Notice will be deemed effective on the date personally delivered or transmitted by facsimile or email. If the notice is mailed, notice will be deemed given three days after deposit of the same in the custody of the United States Postal Service, (5-2025) Project No. SS-5120-1
CONTRACT
postage prepaid, for first class delivery, or upon delivery if using a major courier service with tracking capabilities.
13.3 Any Party may change its notice information by giving notice to the other Party in compliance with this section.
Section 14. District Rights of Termination and to Complete the Work.
14.1 The occurrence of any of the following is a default by Contractor under this Contract:
14.1.1 Contractor refuses or fails to prosecute the Work or any part thereof with such diligence as will insure its completion within the time specified or any permitted extension.
14.1.2 Contractor fails to complete the Work on time.
14.1.3 Contractor is adjudged bankrupt, or makes a general assignment for the benefit of creditors, or a receiver is appointed on account of Contractor’s insolvency.
14.1.4 Contractor fails to supply enough properly skilled workers or proper materials to complete the Work in the time specified.
14.1.5 Contractor fails to make prompt payment to any subcontractor or for material or labor.
14.1.6 Contractor fails to abide by any applicable laws, ordinances or instructions of District in performing the Work.
14.1.7 Contractor breaches or fails to perform any obligation or duty under the Contract.
14.2 Upon the occurrence of a default by Contractor, District will serve a written notice of default on Contractor specifying the nature of the default and the steps needed to correct the default. Unless Contractor cures the default within 10 days after the service of such notice, or satisfactory arrangements acceptable to District for the correction or elimination of such default are made, as determined by District, District may thereafter terminate this Contract by serving written notice on Contractor. In such case, Contractor will not be entitled to receive any further payment, except for Work actually completed prior to such termination in accordance with the provisions of the Contract Documents.
14.3 If the Engineer determines that the default should be cured in less than 10 days, then the written notice of default served on the Contractor will specify the shorter deadline for the Contractor to cure the default.
14.4 In event of a termination of this Contract, the District will also immediately serve written notice of the termination upon Contractor’s surety. The surety will have the right to take over and perform pursuant to this Contract; provided, however, that if (5-2025) Project No. SS-5120-1
CONTRACT
the surety does not give District written notice of its intention to take over and perform this Contract within five days after service of the notice of termination or does not commence performance within 10 days from the date of such notice, District may take over the Work and prosecute the same to completion by contract or by any other method it may deem advisable for the account and at the expense of Contractor. Contractor and the surety will be liable to District for any and all excess costs or other damages incurred by District in completing the Work.
14.5 If District takes over the Work as provided in this Section, District may, without liability for so doing, take possession of, and utilize in completing the Work, such materials, appliances, plant, and other property belonging to Contractor as may be on the site of the Work and necessary for the completion of the Work.
14.6 If District takes over the Work, District may also take possession of outstanding materials on order for the completion of the project, upon payment to the vendor.
All excess costs incurred by District in obtaining such materials, will be the responsibility of the Contractor.
14.7 If the Contractor does not cure a default within the time period required, then in lieu of terminating of the Contract, the District, in its sole discretion, may take action to cure the default and all costs incurred by District to cure the default will be deducted from any amount otherwise due to the Contractor.
Section 15. Project Documents. All data, drawings, maps, models, notes, photographs, reports, studies and other documents (collectively, “Project Documents”) prepared, developed or discovered by Contractor in the course of performing any of the Work under this Contract will become the sole property of District. Upon the expiration or termination of this Contract, Contractor must turn over all original Project Documents to District in its possession, but may retain copies of any of the Project Documents it may desire.
Section 16. General Provisions.
16.1 Authority to Execute. Each Party represents and warrants that all necessary action has been taken by such Party to authorize the undersigned to execute this Contract and to bind it to the performance of its obligations.
16.2 Assignment. Contractor may not assign this Contract without the prior written consent of District, which consent may be withheld in District’s sole discretion since the experience and qualifications of Contractor were material considerations for this Contract.
16.3 Binding Effect. This Contract is binding upon the heirs, executors, administrators, successors and permitted assigns of the Parties.
16.4 Integrated Contract. This Contract, including the Contract Documents, is the entire, complete, final and exclusive expression of the Parties with respect to the Work to be performed under this Contract and supersedes all other agreements or understandings, whether oral or written, between Contractor and District prior to the execution of this Contract.
(5-2025) Project No. SS-5120-1
CONTRACT
16.5 Modification of Contract. No amendment to or modification of this Contract will be valid unless made in writing and approved by Contractor and by the Board of Directors of District or District Manager, as applicable. The Parties agree that this requirement for written modifications cannot be waived and that any attempted waiver will be void.
16.6 Electronic Signatures; Counterparts. This Contract and any amendment will be considered executed when the signature page of a party is delivered by electronic transmission. Such electronic signatures will have the same effect as an original signature. The Contract may be executed in multiple counterparts.
16.7 Waiver. Waiver by any Party of any term, condition, or covenant of this Contract will not constitute a waiver of any other term, condition, or covenant. Waiver by any Party of any breach of the provisions of this Contract will not constitute a waiver of any other provision, or a waiver of any subsequent breach or violation of any provision of this Contract. Acceptance by District of any Work performed by Contractor will not constitute a waiver of any of the provisions of this Contract.
16.8 Interpretation. This Contract will be interpreted, construed and governed according to the laws of the State of California. Each party has had the opportunity to review this Contract with legal counsel. The Contract will be construed simply, as a whole, and in accordance with its fair meaning. It will not be interpreted strictly for or against either party.
16.9 Severability. If any term, condition or covenant of this Contract is declared or determined by any court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions of this Contract will not be affected and the Contract will be read and construed without the invalid, void or unenforceable provision.
16.10 Venue. In the event of litigation between the parties, venue in state trial courts will be in the County of Ventura. In the event of litigation in a U.S. District Court, venue will be in the Central District of California, in Los Angeles. [Signatures on the following page.]
(5-2025) Project No. SS-5120-1
CONTRACT
The Parties have caused this Contract to be executed by their undersigned authorized agents as follows:
CAMARILLO SANITARY DISTRICT
Greg Ramirez, District Manager
ATTEST:
Carrie Weal, Assistant Secretary
CONTRACTOR
(If not an individual, two signatures are required)
Name and Title
Name and Title
_ __________________________________ _ ________ Camarillo Business Tax Certificate Number Expiration Date
(5-2025) Project No. SS-5120-1
CONTRACT
A-1
EXHIBIT A
COMPENSATION
The total compensation under this Contract will not exceed:
ALTERNATE 1
If a Lump Sum Bid: “The sum of $ .”
ALTERNATE 2
If a Unit Price Bid: “The total unit prices set forth in the bid and the actual measured quantities utilized for the Project as determined by the Director.” ALTERNATE 3
If both Lump Sum and Unit Price Bid: “The sum of $ , and the amount due based upon the unit prices set forth in the bid and the actual measured quantities utilized for the Project as determined by the Director.”
(5-2025) Project No. SS-5120-1
CONTRACT
B-1
EXHIBIT B
INSURANCE
1. General Requirements. Contractor must procure and maintain in full force and effect during the term of this Contract the following types of insurance with coverage limits complying, at a minimum, with the limits set forth below:
Type of Insurance Limits
Commercial General Liability $2,000,000 / $4,000,000 (occurrence/aggregate) Business Automobile Liability $1,000,000 combined single Workers’ Compensation Statutory Requirements
2. Insurance Rating. All insurance required to be maintained by Contractor must be issued by companies licensed by or admitted to conduct insurance business in the State of California by the California Department of Insurance and must have a rating of A- or better and Financial Size Category Class VII or better by the latest edition of A.M. Best’s Key Rating Guide, unless otherwise approved by City/District’s legal counsel.
3. Commercial General Liability Insurance. The commercial general liability insurance must meet or exceed the requirements of Insurance Services Office (ISO) form CG 00 01, and must be provided on a per occurrence basis for bodily injury, personal injury, and property damage. The policy must include contractual liability that has not been amended.
The insurance must be on an “occurrence” not a “claims made” basis. Defense costs must be paid in addition to limits. There must be no cross -liability exclusion for claims or suits by one insured against another. The insurance must include a waiver of subrogation applicable to the insurance or self-insurance, a primary and non-contributory endorsement, and an additional insured endorsement, all in favor of the City of Camarillo/Camarillo Sanitary District, its officers, employees and agents, and volunteers; blanket endorsements are acceptable. Any endorsement restricting standard ISO “insured contract” language will not be accepted.
4. Business Auto Coverage. The business automobile insurance coverage must be at least as broad as ISO Business Auto Coverage form CA 00 01, covering bodily injury and property damage for all activities of the Contractor arising out of or in connection with the services to be performed under this Agreement, including coverage for any owned, hired, non-owned or rented vehicles, in an amount stated above per combined single limit for each accident. Such insurance must include a waiver of subrogation applicable to the insurance or self-insurance, and a primary and non-contributory endorsement, and an additional insured endorsement, all in favor of the City of Camarillo/Camarillo Sanitary District, its officers, employees and agents, and volunteers; blanket endorsements are acceptable.
5. Workers Compensation. If Contractor has any employees, Contractor must maintain workers’ compensation insurance (statutory limits) and employer’s liability insurance (with limits of at least $1,000,000). Such insurance must include a waiver of subrogation endorsement in favor of the City of Camarillo, its officers, employees, agents, and volunteers; a blanket endorsement is acceptable.
(5-2025) Project No. SS-5120-1
CONTRACT
B-2
6. Umbrella or Excess Liability Insurance. If an excess or umbrella liability policy is used to meet minimum limit requirements, the insurance must provide coverage at least as broad as specified for the underlying coverages. Any such coverage provided under an umbrella or excess liability policy must include a “drop-down provision” requiring the policy to respond in the event that any primary insurance that would otherwise have applied proves to be uncollectable in whole or in part for any reason. Coverage must be provided on a “pay-on-behalf” basis, with defense costs payable in addition to policy limits. There may be no cross-liability exclusion precluding coverage for claims or suits by one insured against another. The policy must “follow form” to the underlying primary policy. Coverage must be applicable to all insureds under the primary policies. The insurance must contain or be endorsed to contain a waiver of subrogation applicable to the insurance or self- insurance, and a primary and non-contributory endorsement for the benefit of City/District.
The scope of coverage provided is subject to approval of City/District following receipt of the required proof of insurance.
7. Contractor’s Limitations and Endorsements. The Contractor’s insurance policies must not include any endorsements or provisions that limit coverage for the following risks:
explosion, collapse, or underground hazards (XCU); products and completed operations; pollution liability; and contractual liability. These coverages must be specifically included without any exclusions, modifications, or restrictions that would limit the scope of protection otherwise afforded by the basic policies. Any endorsement or exclusion that reduces or eliminates coverage for the above-listed risks is unacceptable.
8. Deductibles and Self-Insured Retention. Any deductibles or self-insured retentions applicable to the insurance policies required under this Agreement must be declared to and approved by City/District. In no event may any required insurance policy have a deductible, self-insured retention or other similar policy provision in excess of $50,000 without prior written approval by City/District in its sole discretion. At the option of City/District, either the insurer will reduce or eliminate such deductibles or self-insured retentions with respect to the City/District’s additional insureds or Contractor will procure a bond guaranteeing payment of any losses, damages, expenses, costs or settlements up to the amount of such deductibles or self-insured retentions.
9. Certificates of Insurance and Endorsements; Notice of Termination or Changes to Policies. Prior to commencing any services under this Agreement, Contractor must file with the City/District certificates of insurance and endorsements evidencing the existence of all insurance required by this Agreement, along with such other evidence of insurance or certified copies of policies as may reasonably be required by City/District. These certificates of insurance and endorsements must be in a form approved by the City/District’s legal counsel. Contractor must maintain current certificates and endorsements on file with City/District during the term of this Agreement reflecting the existence of all required insurance. Each of the certificates must expressly provide that no material change in the policy, or termination or cancellation of the required coverage, will be effective except upon 30 days’ prior written notice to City/District by certified mail, return receipt requested (except for nonpayment for which a 10-day notice is required).
The delivery to City/District of any certificates of insurance or endorsements that do not comply with the requirements of this Agreement will not waive the City/District’s right to require compliance. In the event that Contractor’s policies are materially changed, Contractor must provide the City/District with at least 30 days’ prior written notice of the applicable changes. City/District reserves the right to require complete, certified copies of all required insurance policies at any time.
(5-2025) Project No. SS-5120-1
CONTRACT
B-3
10. Failure to Maintain Required Insurance. If Contractor, for any reason, fails to have in place at all times during the term of this Agreement all of the required insurance coverage, the City/District may, but is not obligated to, obtain such coverage at Contractor’s expense and deduct the cost from the sums due Contractor. Alternatively, City/District may terminate the Agreement.
11. Effect of Coverage. The existence of the required insurance coverage under this Agreement will not be deemed to satisfy or limit Contractor’s indemnity obligations under this Agreement. Contractor acknowledges that the insurance coverage and policy limits set forth in this Agreement constitute the minimum coverage and policy limits required.
Should any coverage carried by the Contractor or any subcontractor of any tier have limits of liability that exceed the limits or have broader coverage than required in this Agreement, those higher limits and that broader coverage are deemed to apply for the benefit of any person or organization included as an additional insured and those limits and broader coverage will become the required minimum limits and insurance coverage in all sections of this Agreement. Any insurance proceeds available to City/District in excess of the limits and coverages required by this Agreement, and which is applicable to a given loss, must be made available to City/District to compensate it for such losses.
12. Required Insurance for Subcontractors. Contractor agrees to ensure that any subcontractors providing services under this Agreement provide the same minimum insurance coverage and endorsements required of Contractor. Contractor agrees to review and monitor all such coverage and assumes responsibility for ensuring that such coverage is provided in conformity with the requirements of this Agreement.
13. Right to Revise Insurance Specifications. City/District reserves the right to change the amounts and types of insurance required by giving Contractor at least 90 days advance written notice of such change. If such change results in substantial additional cost to Contractor, the parties may renegotiate Contractor’s compensation.
14. Timely Notice of Claims. Contractor must give City/District prompt notice of claims made of lawsuits initiated that arise out of or result from Contractor’s performance under this Agreement, and that involve or may involve coverage under any of the required liability insurance policies.
(5-2025) Project No. SS-5120-1
CONTRACT
D-1
EXHIBIT D
ADJUSTMENT FOR NEW TARIFFS OR TARIFF INCREASES
1. ENTITLEMENT TO ADJUSTMENT
1.1 If, after the date of Contractor's solicitation submission, the United States government imposes or increases tariffs that directly and demonstrably affect the unit pricing or availability of materials or equipment required for the Work, and such increases were unavoidable, and not reasonably foreseeable at the time of solicitation submission, Contractor may be entitled to an adjustment to the Contract Sum subject to the conditions and limitations set forth in this provision.
2. LIMITATIONS ON ENTITLEMENT
2.1 Reasonably Foreseeable Increases. Contractor shall not be entitled to any adjustment to the Contract Sum for new tariffs or tariff increases that were reasonably foreseeable at the time of solicitation submission. For purposes of this provision, "new tariffs or tariff increases that were reasonably foreseeable" include, without limitation:
a. Any increase in the applicable tariff or tariffs to a level which was already in effect, plus ten percent (10%), at any point during the past ten years; b. Any new tariff or increase in tariff level that was Already Announced prior to solicitation submission, regardless of whether it had taken effect;
i. “Already Announced” includes, without limitation, the following circumstances:
A. Notice of a pertinent tariff, or tariff level, has been published by the United States International Trade Commission, or other federal agency, as of the solicitation submission date, regardless of whether the effective date of the tariff is prior to the solicitation submission date, or after. Publication includes, without limitation, notices on an agency website, the Harmonized Tariff Schedule, or in the Federal Register.
B. The President of the United States, a member of the President’s cabinet, or one of the President’s advisors, has stated the federal government will adopt a new or increased tariff, including without limitation making such a statement through a speech, interview, order, social media post, or otherwise, regardless of formality.
C. A reputable news organization has reported that the U.S. federal government is expected to adopt the new or increased tariff.
2.2 General Market Conditions.
a. Contractor shall not be entitled to any adjustment to the Contract Sum for changes in unit pricing attributable to market conditions other than new or increased U.S. tariffs, including but not limited to general inflation, supply chain disruptions, labor costs, currency fluctuations, or other market factors, except to the extent covered by the force majeure provision and other provisions in the contract documents. (5-2025) Project No. SS-5120-1
CONTRACT
D-2
b. New or increased tariffs imposed by foreign governments, and the effects any such new or increased foreign tariffs have on unit pricing or product availability are general market conditions and do not entitle Contractor to an adjustment in the Contract Sum. New or increased tariffs imposed by foreign governments are not an “acts of a public enemy” or “acts of a governmental entity not occasioned by the Contractor’s, subcontractor’s, or supplier’s conduct” and are considered foreseeable under the contract documents.
2.3 Tariff Avoidance; Duty to Mitigate. Upon learning of a new tariff, or tariff increase, Contractor shall make commercially reasonable efforts to avoid the new costs and mitigate any increased costs to District. Contractor shall, without limitation, determine if there are alternate suppliers that can furnish necessary materials or equipment at a lower cost to Contractor, for example, by sourcing materials or equipment from the United States, or a country subject to lower duties than the Contractor’s original intended supplier. If Contractor is able to identify a lower cost supplier through such efforts, Contractor shall procure supplies from that source before seeking an adjustment in the Contract Sum. Any adjustment to the Contract Sum shall be based on actual increased costs incurred by Contractor despite such efforts.
3. PROCEDURE FOR SEEKING ADJUSTMENT
3.1 Notice Requirement. Contractor shall notify District in writing within fourteen (14) calendar days after Contractor becomes aware or should reasonably have become aware of a new tariff or tariff increase that may entitle Contractor to an adjustment to the Contract Sum.
3.2 Documentation Required. Contractor's request for adjustment shall include:
a. Identification of the specific materials or equipment affected; b. Documentation of the original cost of the affected materials or equipment as included in Contractor's solicitation submission;
c. Documentation of the increased cost directly attributable to the tariff increase; d. Documentation demonstrating that the tariff increase was not reasonably foreseeable as defined in Section 2.1;
e. Documentation demonstrating that the increased costs are not attributable to non- tariff market conditions as defined in Section 2.2; and
f. Proposed adjustment to the Contract Sum.
4. AUDIT RIGHTS
4.1 Prior to agreeing to any adjustment to the Contract Sum, District shall have the right to audit Contractor's books and records to verify that all conditions precedent to a price adjustment have been met.
4.2 Contractor shall provide District and District's authorized representatives access to all books, records, documents, and other evidence pertaining to the request for adjustment, including but not limited to:
a. Original purchase orders and supplier quotes;
b. Subsequent purchase orders and supplier quotes showing increased costs; (5-2025) Project No. SS-5120-1
CONTRACT
D-3
c. Correspondence with suppliers regarding tariff impacts; d. Documentation of tariff rates in effect at the time of solicitation submission and at the time of purchase; and
e. Any other documentation reasonably requested by District to verify the entitlement to and amount of the requested adjustment.
4.3 Contractor shall maintain all such records for a period of not less than three (3) years after final payment.
5. DETERMINATION OF ADJUSTMENT AMOUNT
5.1 Any adjustment to the Contract Sum shall be limited to the actual increased cost directly attributable to the unforeseeable new tariff or tariff increase, without any additional markup for overhead and profit.
5.2 District reserves the right to reject any request for adjustment that does not meet the requirements of this provision or is not substantiated by sufficient documentation.
5.3 Nothing in this provision shall be construed to relieve Contractor of its obligation to complete the Work within the Contract Time or to entitle Contractor to any time extension due to new tariffs or tariff increases.
(5-2025) Project No. SS-5120-1
CONTRACT
VERIFICATION OF CALIFORNIA
CONTRACTOR’S LICENSE
I certify, under penalty of perjury, that I have a valid California Contractor’s license issued pursuant to Business and Professions Code section 7000 and following, and was so licensed at the time that the bid was awarded:
California Contractor’s License:
License Number Class Expiration Date
CONTRACTOR (PRINT OR TYPE)
Date Signature
(Public Contract Code § 6100)
(5-2025) Project No. SS-5120-1
CONTRACT
CERTIFICATE REGARDING
WORKERS’ COMPENSATION
I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self- insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.
Name (print or type)
Date Signature
(5-2025) Project No. SS-5120-1
BOND
BOND NO.
PERFORMANCE BOND
On _____________________________, the Board of Directors of the Camarillo Sanitary District, California, a sanitary district (“DISTRICT”), awarded a contract (“Contract”) to ____________________________________________________________________________ (“CONTRACTOR” or “PRINCIPAL”), for the work (“Work”) identified as ____________________________________________________________________________ The Contract and related documents (“Contract Documents”) are incorporated and made a part of this performance bond.
Under the Contract, CONTRACTOR is required to furnish this bond providing for the faithful performance of the Work
NOW, THEREFORE, we, CONTRACTOR, as PRINCIPAL, and
____________________________________________________________________________, a corporation organized and existing under the laws of the State of ________________________ and duly authorized to transact business under the laws of the State of California, as SURETY, are held and firmly bound unto DISTRICT, in the sum of
_______________________________________________________________________dollars ($_________________________), lawful money of the United States of America, this sum being not less than one hundred percent (100%) of the estimated amount payable by DISTRICT under the terms of the Contract , PRINCIPAL and SURETY, bind ourselves and our heirs, executors, administrators, successors and assigns, jointly and severally, by this instrument.
BOND CONDITIONS
1. PRINCIPAL will perform the Work the identified in the Contract. DISTRICT has estimated the required amount of the bond as shown above.
2. PRINCIPAL’s performance of the Work will be done in accordance with the Contract Documents. Should PRINCIPAL fail to satisfactorily complete all required Work within the time allowed, DISTRICT may, at its sole discretion, either (1) cause all required Work to be done and the parties executing this bond will be firmly bound for the payment of all necessary costs for the performance of this Work or (2) make demand upon the SURETY to complete the required Work in which event the SURETY will commence completion of the Work within 30 days of the DISTRICT’S demand unless otherwise agreed in a writing signed by the parties.
3. PRINCIPAL will guarantee the Work against any defective work, labor or materials for a period of one year following the completion and acceptance of the Work by DISTRICT. (5-2025) Project No. SS-5120-1
BOND
4. This bond is conditioned upon and guarantees due compliance with all applicable law including, without limitation, the Camarillo Municipal Code.
5. SURETY agrees that no changes, extensions of time, alteration or modification of the Contract or of the obligations to be performed thereunder will in any way affect its obligation on this bond, and waives notice of any such change, extension of time, alteration or modification of the Contract or of the obligations to be performed.
Furthermore, SURETY expressly waives the provisions of California Civil Code sections 2845 and 2849.
6. This bond consists of this instrument, the Contract and Contract Documents referenced above, and the following two attached exhibits, all of which are incorporated herein by reference:
A. A certified copy of the appointment, power of attorney, bylaws or other instrument entitling or authorizing the persons executing this bond to do so; and B. A certificate issued by the county clerk for the county in which SURETY’s representative is located conforming with California Code of Civil Procedure § 995.640 and stating that SURETY’s certificate of authority has not been surrendered, revoked, cancelled, annulled, or suspended, or in the event that it has, that renewed authority has been granted.
7. In case suit is brought upon this bond, the court will award and SURETY must pay, in addition to the face amount of this bond, all costs and reasonable attorney’s fees incurred by DISTRICT in successfully enforcing any obligation under this bond.
IN WITNESS THEREOF, we have hereunto set our hands and seals this _______ day of ____________________, 20____.
PRINCIPAL
By
Title
Address
Telephone Number
Signature
(5-2025) Project No. SS-5120-1
BOND
SURETY
By
Title
Address
Telephone Number
Signature
* ALL SIGNATURES ON THIS PERFORMANCE BOND MUST BE NOTARIZED USING APPROPRIATE 8½” x 11” NOTARY ACKNOWLEDGEMENT FORM.
** Appropriate modifications will be made to this form if the bond is being furnished for the performance of an act not provided for by agreement.
*** Corporations must affix corporate seal.
(5-2025) Project No. SS-5120-1
BOND
BOND NO.
PAYMENT BOND
On __________________________, the Board of Directors of the Camarillo Sanitary District, California, a sanitary district (“DISTRICT”), awarded a contract (“Contract”) to ____________________________________________________________________________ (“CONTRACTOR” or “PRINCIPAL”), for the work (“Work”) identified as ____________________________________________________________________________.
PRINCIPAL is required to furnish a bond under the Contract to secure the payment of claims of laborers, mechanics, material persons, and other persons as provided by law.
PRINCIPAL and __________________________________________________ ___________________________________, a corporation incorporated under the laws of the State of _______________________________ and licensed by the State of California to execute bonds and undertakings as sole surety (“SURETY”), are held and firmly bound unto DISTRICT in the sum of ___________________________________________________ ______________________________________ dollars ($_________________________), lawful money of the United States, which may be increased or decreased by a rider hereto executed in the same manner as this bond, for the payment of which sum PRINCIPAL and SURETY bind themselves, their successors, and assigns, jointly and severally, by this instrument.
BOND CONDITIONS
1. PRINCIPAL will construct the Work identified in the Contract. Such performance will be in accordance with the Contract Documents identified in the Contract, which are hereby incorporated and made a part of this bond. DISTRICT has estimated the required amount of the bond as shown above.
2. If PRINCIPAL, its heirs, executors, administrators, successors, assigns or subcontractors fail to pay any of the persons named in California Civil Code section 3181, or any amounts due under the California Unemployment Insurance Code with respect to work or labor performed under the Contract, or any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of the Contractor and its subcontractors under Unemployment Insurance Code section 13020, with respect to work or labor performed under the Contract, SURETY will pay for the same in an amount not exceeding the penal sum specified in this bond.
3. This bond inures to the benefit of any of the persons named in Civil Code section 3181 so as to give a right of action to such persons or their assigns in any suit brought upon this bond. In case suit is successfully brought upon this bond, SURETY further agrees to pay all reasonable attorneys’ fees and costs in an amount fixed by the court.
4. This bond is conditioned upon and guarantees due compliance with all applicable law including, without limitation, the Camarillo Municipal Code. (5-2025) Project No. SS-5120-1
BOND
5. SURETY agrees that no changes, extensions of time, alteration or modification of the Contract or of the obligations to be performed thereunder will in any way affect its obligation on this bond, and waives notice of any such change, extension of time, alteration or modification of the Contract or of the obligations to be performed.
Furthermore, SURETY expressly waives the provisions of California Civil Code sections 2845 and 2849.
6. This bond consists of this instrument, the Contract and Contract Documents referenced above, and the following two attached exhibits, all of which are incorporated herein by reference:
A. A certified copy of the appointment, power of attorney, bylaws or other instrument entitling or authorizing the persons executing this bond to do so; and B. A certificate issued by the county clerk for the county in which SURETY’s representative is located conforming with California Code of Civil Procedure § 995.640 and stating that SURETY’s certificate of authority has not been surrendered, revoked, cancelled, annulled, or suspended, or in the event that it has, that renewed authority has been granted.
IN WITNESS THEREOF, we have hereunto set our hands and seals this _______ day of ____________________, 20____.
PRINCIPAL
By
Title
Address
Telephone Number
Signature
(5-2025) Project No. SS-5120-1
BOND
SURETY
By
Title
Address
Telephone Number
Signature
* ALL SIGNATURES ON THIS PAYMENT BOND MUST BE NOTARIZED USING APPROPRIATE 8½” x 11” NOTARY ACKNOWLEDGEMENT FORM.
** Appropriate modifications will be made to this form if the bond is being furnished for the performance of an act not provided for by agreement.
*** Corporations must affix corporate seal.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 1 -
CAMARILLO SANITARY DISTRICT
GENERAL CONDITIONS/SPECIFICATIONS
WORK IDENTIFICATION: WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5 - PROJECT NO. SS-5120-1__________________
SECTION
NO.
PAGE
NO.
1. Definitions ........................................................................................ 4
1.1 General Construction ........................................................... 4
1.2 Terms Defined ...................................................................... 4
1.3 General Conditions/Specifications ....................................... 5
1.4 Abbreviations ........................................................................ 5
2. Work and Material Requirements ..................................................... 6
2.1 Use of Premises ................................................................... 6
2.2 Materials Furnished By District ............................................. 6
2.3 Or Equal ............................................................................... 6
2.4 Samples ............................................................................... 6
2.5 Warranty ............................................................................... 6
2.6 Liens ..................................................................................... 7
2.7 Manufacturer’s Recommendations ....................................... 8
2.8 Certificates of Compliance ................................................... 8
3. Grading Ordinance ........................................................................... 8
4. Progress Payments to Contractor .................................................... 8
4.1 Progress Payments to Subcontractors ................................. 8
4.2 Substitution of Securities ...................................................... 8
5. Time for Completion ......................................................................... 9
5.1 Payment for Delays to Contractor ........................................ 9
5.2 Rights of District to Increase Working Days ......................... 9
6. Construction Schedule and Commencement of Work ..................... 9
6.1 Proposed Construction Schedule ......................................... 9
6.2 Beginning of Work ................................................................ 11
6.3 Temporary Suspension of Work ........................................... 12
6.4 Starting of Contract Time ..................................................... 12
6.5 Liquidated Damages ............................................................ 12
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 2 -
7. Subcontracting ................................................................................. 13
7.1 Subcontractors Bound By Contract ...................................... 13
7.2 District Consent to Subcontractors ....................................... 13
8. Work By Others ................................................................................ 13
8.1 District’s Right to Award Other Contracts ............................. 13
8.2 Contractor’s Responsibilities ................................................ 13
9. Authority of the District Engineer ...................................................... 14
9.1 General Authority ................................................................... 14
9.2 Interpretation of Drawings and Specifications ........................ 14
9.3 Inspection ............................................................................. 14
9.4 Disputes Pertaining to Payment for Work ............................ 14
10. General Provisions ........................................................................... 14
10.1 Utilities .................................................................................. 14
10.2 Water Supply ........................................................................ 15
10.3 Dust Control ......................................................................... 15
10.4 Removal and Disposal of Structures and
Obstructions .........................................................................
15 10.5 Surveys ................................................................................ 15
10.6 Layout and Field Engineering ............................................... 16
10.7 Traffic Requirements ............................................................ 16
10.8 Tests and Inspections .......................................................... 17
10.9 Soils Investigation Report ..................................................... 17
10.10 Compaction Tests ................................................................ 18
10.11 Cutting and Patching ............................................................ 18
10.12 Earthquake and Tidal Wave Damage .................................... 18
10.13 Highway and Railroad Permits ............................................... 18
10.14 Noise Control ......................................................................... 18
11. Acceptance of Work ......................................................................... 18
11.1 No Waiver of Legal Rights .................................................... 18
11.2 Non-Complying Work ........................................................... 19
11.3 Fulfillment of Contract .......................................................... 19
11.4 Correction of Work Before Acceptance ................................ 19
11.5 Deductions for Uncorrected Work ........................................ 19
11.6 Final Clean Up ...................................................................... 19
11.7 Certificate as to Compliance With
Certain Regulations ..............................................................
20 12. Claims between District and Contractor ........................................... 20
12.1 Definition of Claim ................................................................ 20
12.2 Notice of Potential Claim Procedure .................................... 20
12.3 Claim Processing Procedure ................................................ 21 (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 3 -
13. Assignment of Rights ....................................................................... 22
14. Prohibited Interests .......................................................................... 22
15. Labor Code Requirements ............................................................... 22
15.1 State Wage Determination ................................................... 22
15.2 Compliance Monitoring ......................................................... 23
15.3 Payroll Records .................................................................... 23
15.4 Apprentices .......................................................................... 24
15.5 Working Hours ...................................................................... 25
15.6 Workers Compensation ........................................................ 25
15.7 Protection of Workers in Trench
Excavations ..........................................................................
26 16. Sales and Use Tax Cooperation ...................................................... 26
17. Documentation of Status of Surety .................................................. 26
18. Construction and Demolition Waste ................................................. 27
19. Use of Premises ............................................................................... 27
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 4 -
GENERAL CONDITIONS/SPECIFICATIONS
1. Definitions
1.1 General Construction
Terms used in these General Conditions/Specifications and in other Contract Documents will have the definition provided in this Section 1, unless the context requires a different meaning.
The word “person” includes a corporation, association, partnership and any other form of legal entity.
Unless otherwise specifically defined herein, or unless the context requires a different meaning, all words, terms and phrases having a well -known or technical meaning will be so construed.
In the event of conflict, the order of precedence of governing documents will be as set forth in Section 5.1 of the Instructions to Bidders.
1.2 Terms Defined
Acceptance: The formal written acceptance by District of a project that has been completed in all respects in accordance with the plans and specifications and any modifications.
Addendum: The modification of the plans and/or specifications issued to all prospective bidders during the period when necessary to change, correct, clarify, or further define any phase of the work.
Bidder: Any person submitting a proposal for the work contemplated, acting directly or through a duly authorized representative.
District: The Camarillo Sanitary District, County of Ventura, State of California Assistant Secretary: The Assistant Secretary of District.
Board of Directors: The Board of Directors of District.
District Engineer/Engineer of Work/Engineer : The District Engineer of District or his/her duly authorized deputies, agents, representatives or inspectors.
Contractor: The successful bidder who is awarded the Contract.
Days: Calendar days, unless business days or work days, are expressly specified.
Materials: Any material, equipment, appliance, process, item or article of any nature whatsoever installed or incorporated into the work or provided to District under the Contract.
Project: The project is the total improvement, of which the work performed under the Contract may be the whole or a part.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 5 -
Punch List: List of corrective items, determined by the Engineer, which must be completed by the Contractor.
Special Provisions: Any provision in the Contract Documents that supplements, modifies and, when in conflict, supersedes these General Conditions/Specifications.
Standard Specifications/Green Book/SSPWC: Standard Specifications for Public Works Construction, 2024 edition, written and promulgated by Public Works Standards, Inc. and all supplements thereto.
State Standard Plan: Standard Plans prepared by the State of California, Business & Transportation Agency, Department of Transportation, latest edition.
Subcontractor: Any subcontractor under Contractor.
Work: That which is proposed to be constructed or done under the Contract, in strict accordance with the Contract Documents, including the furnishing of all necessary or convenient tools, equipment, material, labor and transportation.
Working Days: A working day is defined as any day, except Saturdays, Sundays, legal holidays and except days when Work is suspended by the Engineer, and any other day determined to be non-working in accordance with the Contract Documents.
1.3 General Conditions/Specifications
The provisions of these General Conditions/Specifications and any other Contract Document supersede the SSPWC to the extent that the provisions supplement, modify or conflict with the SSPWC in accordance with Section 5.1 of the Instructions to Bidders.
1.4 Abbreviations
AAN American Association of Nurserymen
AGC Associated General Contractors of America
AISC American Institute of Steel Construction
APWA American Public Works Association
ASME American Society of Mechanical Engineers
AWS American Welding Society
AWWA American Water Works Association
EIA Electronic Industries Association
IEEE Institute of Electric and Electronic Engineers
NEC National Electric Code
NEMA National Electrical Manufactures Association
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 6 -
SSS State of California Standard Specifications, Latest edition, Department of Public Works, Department of Transportation VCSS Ventura County Standard Specifications
2. Work and Material Requirements
2.1 Use of Premises
(a) Contractor must confine all tools and equipment, the storage of materials, and the operation of workers to areas designated by the Engineer. (b) With respect to any premises, tools or equipment of District made use of in the performance of the Contract, Contractor will be deemed to have inspected the same prior to use, have accepted them in good and safe condition and have agreed to maintain them in a safe condition for the protection of workmen while using them during the performance of the Work.
2.2 Materials Furnished By District
Materials furnished by District will be available at locations designated in the Special Provisions, or if not designated in the Special Provisions, will be delivered to a single location of District’s choice within the project area. The materials will be hauled to the site of installation by Contractor at its expense, including any necessary loading and unloading that may be involved. The cost of handling and placing materials furnished by District will be considered as included in the price paid for the item involving such furnished material.
2.3 Or Equal
In the event that an item is called for by a specific product or trade name, Contractor will have 35 days after the award of the Contract for submission of data substantiating a request for a substitution of “an equal” item. In the event Contractor furnishes any “or equal” material more expensive than that specified in the bid form, the difference in cost of such material so furnished will be borne by Contractor under Public Contract Code section 3400.
2.4 Samples
Contractor must furnish for approval, within 35 days following notice of award of Contract, all samples as required in specifications together with catalogs and supporting data required by the Engineer. This provision does not authorize any extension of time for performance of the Contract. The Engineer will review such samples only for conformance with design and concept of Work and for compliance with information given in the Contract Documents. Work must be in accordance with approved samples under Public Contract Code section 3400.
2.5 Warranty
(a) The labor and materials bond must remain in effect until expiration of six months after the period in which verified claims may be filed as provided in Civil Code section 9356, and the performance bond must be paid up and in effect for one year after the acceptance of the job by District in accordance with the guarantee required by Subsection 2.5(b), below. (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 7 -
(b) Besides warranties and guaranties otherwise required by the Contract Documents, Contractor warrants and guarantees all Work for a period of one year after date of acceptance of the Work by District, unless a longer period is specified, and must repair or replace any or all such Work, together with any other Work, which may be displaced in so doing, that may prove defective in workmanship, materials or both within one year from date of acceptance without expense whatsoever to District, ordinary wear and tear, unusual abuse or neglect excepted. The Engineer will give notice of observed defects with reasonable promptness. Contractor must notify the Engineer upon completion of repairs. (c) In the event Contractor fails to commence the corrective work within 10 days after being notified in writing to do so by the Engineer and prosecute the corrective work to timely completion, District may proceed to have defects corrected and made good at the expense of Contractor who must pay the costs and charges of such corrective work immediately on demand.
(d) If, in the opinion of the Engineer, defective work creates a condition that requires immediate corrective work, the Engineer will attempt to give the notice required by this Section.
If Contractor cannot be contacted or does not comply with District’s request for correction within a reasonable time as determined by the Engineer, District may, notwithstanding the provisions of this Section, proceed to make such corrective work, and Contractor will be liable for costs of such corrective work. Such action by District will not relieve Contractor of the warranties and guaranties provided in this Section or elsewhere in the Contract. (e) This Section does not in any way limit the warranty or guaranty on any material for which a longer warranty or guaranty is specified in the Contract Documents or on any items for which a manufacturer gives a warranty or guaranty for a longer period. Contractor must furnish the Engineer with all appropriate warranty and guaranty certificates upon completion of the Work.
(f) For federally funded transportation projects, District does not require a warranty and the applicable bonds may be exonerated administratively.
2.6 Liens
No materials, supplies, tools or equipment for Work under this Contract may be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest herein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all materials installed or incorporated in the Work by Contractor or any subcontractor and agrees upon completion of all Work to deliver premises, together with all improvements and appurtenances constructed or placed thereon by Contractor, to District free from any claim, liens, or charges. Contractor further agrees that neither Contractor nor any person furnishing any materials, supplies, tools, equipment or labor for any Work covered by this Contract will have any right to lien upon the premises or any improvement or appurtenance thereon, except that Contractor may install metering devices or other equipment of utility companies or of political subdivisions title to which is commonly retained by utility companies or political subdivisions. In event of the installation of any such metering device or equipment, Contractor will so advise District. Nothing contained in this article, however, will defeat or impair the rights of persons furnishing material or labor under any bond given by Contractor for their protection or any rights under any law permitting such persons to look to funds due Contractor in the hands of District, and this provision will be inserted in all subcontracts and material contracts and notice of its provisions will be given to all persons furnishing material for Work when no formal contract is entered into for such material. (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 8 -
2.7 Manufacturer’s Recommendations
Where the manufacturer of any material or equipment provides written recommendations or instructions for its use or method of installation (including labels, tags, manuals or trade literature), such recommendations or instructions must be complied with, except where the Contract Documents specifically require deviations.
2.8 Certificates of Compliance
The District Engineer may require certificates of compliance with the specifications for materials or manufactured items produced outside of the job site. Such certificates will not relieve Contractor from the requirements of providing materials and manufactured items complying with the specifications even though they have been incorporated into the job.
3. Grading Ordinance
(a) All excavation, filling and grading operations in Camarillo are governed by City’s Grading Ordinance. No grading permit is required of Contractor for Work performed within the limits of the project right-of-way shown on the plans.
(b) Materials, exported or wasted outside of the project right- of-way shown on the plans, are subject to all requirements of the Grading Ordinance. The requirements may include, but are not limited to, submitting a grading plan prepared by a civil engineer, obtaining a grading permit, paying the permit fee, posting a grading bond, hiring professionals for engineering and testing services, compacting fills, constructing drainage facilities, and providing erosion protection. These requirements are the responsibility of the owner of the land on which the material is placed. To ensure that neither District nor Contractor are a party to aiding or abetting any property owner to violate the Grading Ordinance, no material may be exported or wasted outside the limits of the project right -of-way until Contractor has furnished the Engineer a copy of the grading permit or certificate of exemption covering such operation on land where the material is to be deposited.
4. Progress Payments to Contractor
4.1 Progress Payments to Subcontractors
Contractor must pay to any subcontractor, no later than seven days after receipt of each District progress payment, unless otherwise agreed to in writing, the respective amounts allowed Contractor on account of the work performed by the subcontractors, to the extent of each subcontractor’s interest in the progress payment. In the event that there is a good faith dispute over all or any portion of the amount due on a progress payment from the Contractor to a subcontractor, the Contractor may withhold no more than 150% of the amount disputed.
In all contracts between Contractor and its subcontractors, the percentage of the retention of proceeds withheld may not exceed the percentage specified in the Contract Documents between the District and the Contractor.
4.2 Substitution of Securities
Pursuant to Public Contract Code section 22300 and upon Contractor’s request, District will make payment of funds retained from progress payments for performance security, if (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 9 -
Contractor deposits in escrow with District’s Finance Director or with a state or federal chartered bank acceptable to District as escrow agent, securities eligible for the investment of District funds under Government Code section 16430 or bank or savings and loan certificates of deposit. Securities may be substituted upon the following terms and conditions:
(a) Contractor will bear all expenses in connection with the escrow deposit made. (b) Securities or certificates of deposit must be of a value equal to 100% of the amounts of retention to be paid to Contractor.
(c) Contractor must enter into an escrow agreement that is substantially the same as set forth in Public Contract Code section 22300.
(d) Contractor must obtain the written consent of the surety to the escrow agreement.
5. Time for Completion
5.1 Payment for Delays to Contractor
Contractor will be compensated when any extension of time is granted for delays caused solely by action or inaction of District, which the Engineer determines materially increases or decreases the costs of any portion of the Work. If the Engineer determines that compensation is not justified, Contractor will be so advised in writing. Contractor may then submit a notice of potential claim to the Engineer, as provided in the Standard Specifications relative to disputed Work.
5.2 Rights of District to Increase Working Days
If such Work is not completed within the time for completion, the Board of Directors has the right to increase the number of working days in the amount it may determine will best serve the interests of District, and, if it desires to increase the number of working days, it has the further right to charge Contractor and deduct from the final payment for the Work, the actual cost of engineering, inspection, superintendence, and other overhead expenses that are directly chargeable to Contractor, and that accrue during the period of such extension, except that the cost of the final service and preparation of the final estimates may not be included in such charges.
6. Construction Schedule and Commencement of Work
6.1 Proposed Construction Schedule
(a) After notification of award and prior to the start of any Work, Contractor must submit to the District Engineer for approval the proposed construction schedule. The construction schedule must be in the form of a Critical Path Method (CPM) in sufficient logic and detail to show the chronological relationship of all activities of the project, including, but not limited to, estimated starting and completion dates of various activities, procurement of materials and scheduling of equipment, work of subcontractors, interface with work by others, and other tasks required to complete the project. The level of detail must be consistent with the complexity of the project as determined by the District Engineer. The construction schedule must reflect completion of all Work included in the Contract within the Completion Time in accordance with these specifications. A construction schedule showing the project complete in less than the (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 10 -
Completion Time will not be accepted. The construction schedule must be cost loaded on a monthly basis.
(b) If Contractor desires to make a major change in its method of operation after commencing construction, or if its schedules fail to reflect the actual progress, it must submit to District a revised construction schedule in advance of beginning any revised operations. (c) The baseline construction schedule must utilize the Completion Time included in the Contract and must not extend beyond the number of working days. The baseline schedule must have a date of the first working day of the Contract and not include any completed work to date. The baseline construction schedule must not attribute negative float or negative lag to any activity. If the Contractor intends to complete the Work prior to the time of completion, the intended date of completion must be set forth in the construction schedule and the Contractor must execute a zero-cost Contract Change Order that reduces the number of working days allowed for completion to conform to the intended completion date. (d) Float, slack time, or contingency within the schedule and the total float within the overall construction schedule, is not for the exclusive use of the Contractor or the District, but is jointly owned and is a resource to meet Contract milestones and the Contract Completion Time.
The Contractor must not sequester shared float through such strategies as extending activity duration estimates, using preferential logic, or using extensive crew/resource sequencing. Since float time within the construction schedule is jointly owned, no time extensions will be granted nor delay damages paid unless a delay occurs that extends the Work beyond the Contract Completion Time. Since float time within the construction schedule is jointly owned, it is acknowledged that District caused delays can be offset by District caused time savings.
Therefore, the Contractor will not be entitled to receive a time extension or delay damages until all District caused time savings are exceeded and the Contract Completion Time is also exceeded.
(e) If the Contractor has fallen behind the accepted Construction Schedule by more than 15 percentage points based on earned progress payments, the Contractor must take steps, including, but not limited to, increasing the number of personnel, shifts, and/or overtime operations, days of work, and/or amount of construction equipment until such time as the Work is back on schedule. Contractor must also submit for review no later than the next request for partial payment, such supplementary schedule or schedules as may be deemed necessary to demonstrate the manner in which the rate of progress will be regained. All cost required to bring the Project back on schedule will be borne by the Contractor without additional cost to the District.
(f) If the Contractor falls behind the accepted construction schedule, as modified by such time extensions as may have been granted by the District for unavoidable delays, by more than 35 percentage points based on earned progress payments, the Contractor will be deemed in material breach of Contract and the Work turned over to the surety for completion within the scheduled time.
(g) Contractor must include in the schedule, detailed information for each operation.
When the project schedule includes multiple streets or sites, Contractor must include detailed information for each street or site. When notifications or parking restrictions are required such dates must be included in the schedule.
(h) Contractor must provide critical path schedules in legible hardcopy format and must also submit schedules with each update in an editable electronic format compatible with (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 11 -
MS Project or Primavera as directed by Engineer.
6.2 Beginning of Work
(a) The delivery to District, for execution and approval of the Contract Documents properly executed on behalf of Contractor and surety, constitutes Contractor’s authority to enter upon the site of the Work and to begin operations, subject to its assumption of the risk of the disapproval of the Contract, as herein provided, and subject also to the following:
(1) Contractor’s receipt from District for the properly executed Contract Documents, including bonds and certificates of insurance. (2) District may, for any reason, order Contractor not to enter upon the site of the Work, which order will nullify the authority of Contractor to enter upon the site prior to receipt of the Notice to Proceed.
(3) Notice in writing of Contractor’s intention to start Work prior to approval, specifying the date on which Contractor intends to start, must be given to the Engineer at least 48 hours in advance.
(4) Contractor must, on commencing operations, take all precautions required for public safety and observe all the provisions in these General Conditions/Specifications and any Special Provisions.
(5) In the event of disapproval of the Contract, Contractor must, at its expense, do such Work as is necessary to leave the site in a neat condition to the satisfaction of the Engineer. If the Work done affects any existing road or highway, Contractor must, at its expense, restore it to its former condition or the equivalent thereof to the satisfaction of the Engineer.
(6) All Work done according to the Contract prior to its approval will, when the Contract is approved, be considered authorized Work and will be paid for as provided in the Contract.
(b) Entry upon the site without authority will be treated as trespassing. (c) Should Contractor begin the Work in advance of receiving notice that the Contract has been approved as provided above, any Work performed by Contractor in advance of the date of approval will be considered as having been done by Contractor at Contractor’s own risk and as a volunteer unless the Contract is so approved. (d) Contractor may start the Work at any time after the Notice to Proceed is issued, but Work must begin within the number of days indicated on the Bid Proposal after the starting date for the Contract, or at such other times as may be indicated in the Special Provisions. The actual date on which Contractor starts the Work will not affect the required item for completion as provided for in the Contract.
(e) If required by the Special Provisions, Contractor must start construction operations on that part of the project designated by the Engineer. (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 12 -
(f) Contractor must perform all the Work in such a manner and with sufficient materials, equipment, and labor to ensure its completion in accordance with the plans and specifications within the time set forth in the Contract.
6.3 Temporary Suspension of Work
(a) Should suspension of the Work be ordered by reason of the failure of Contractor to carry out orders or to perform any provisions of the Contract; or by reason of weather conditions being unsuitable for performing any item or items of the Work; Contractor, at its expense, must take all steps necessary to provide and maintain a safe, smooth, and unobstructed passageway through construction for use by public traffic during the period of such suspension. In the event that Contractor fails to take such steps, District may perform such tasks and the cost thereof will be deducted from monies due Contractor. (b) If the Engineer orders a suspension of all of the Work or a portion of the Work which is the current controlling operation or operations, due to unsuitable weather or to such other conditions as are considered unfavorable to the suitable prosecution of the Work, the days on which the suspension is in effect will not be considered working days for the purpose of calculating Contractor’s time of performance.
(c) If a portion of the Work at the time of such suspension is not a current controlling operation or operations, but subsequently does become the current controlling operation or operations, the determination of working days will be made on the basis of the then current controlling operation or operations.
(d) If suspension of the Work is ordered by the Engineer, due to the failure on the part of Contractor to carry out orders given or to perform any provision of the Contract, no time extension for such suspension will be granted.
6.4 Starting of Contract Time
As soon as practicable after the Contract has been executed by both parties, a Notice to Proceed will be issued by District stating the starting date of the Contract time, which will be as stated in the Notice to Proceed, unless otherwise provided in the Special Provisions.
6.5 Liquidated Damages
The parties agree that time is of the essence in the completion of the Work, and that in case all the Work called for under the Contract is not completed before or upon the expiration of the time limit as set forth in the Contract Documents, as modified by extensions of time granted by District, damage will be sustained by District. As it is impracticable to determine the actual delay damage, the parties agree that Contractor must pay liquidated damages to District in the amount set forth on page 1 of the Bid Proposal, per calendar day for each and every calendar day’s delay beyond the time prescribed to complete the Work. If Contractor fails to pay the liquidated damages, District may deduct the amount from any monies due or that may become due Contractor under the Contract.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 13 -
7. Subcontracting
7.1 Subcontractors Bound By Contract
Contractor agrees to bind every subcontractor by the terms of the Contract as far as such terms are applicable to the subcontractor’s work. If Contractor subcontracts any part of this Contract, Contractor will be fully responsible to District for the acts and omissions of every subcontractor and of persons either directly or indirectly employed by every such subcontractor.
Nothing contained in the Contract Documents, however, creates any contractual relation between any subcontractor and District.
7.2 District Consent to Subcontractors
District’s consent to, or approval of, any subcontractor under the Contract does not in any way relieve Contractor of its obligations under the Contract nor will such subcontract or approval be deemed to waive any provision of the Contract between District and Contractor.
8. Work By Others
8.1 District’s Right to Award Other Contracts
(a) District reserves the right to award other contracts in connection with the project.
Nothing in these General Conditions/Specifications may be interpreted as granting to Contractor exclusive occupancy at the site of the project.
(b) If simultaneous execution of any contract is likely to cause interference with performance of some other contract or contracts, District will decide which contractor must cease Work temporarily and which contractor must continue or whether Work can be coordinated so that contractors may proceed simultaneously. Notwithstanding any other provision of these General Conditions/Specifications, District is not responsible for any damages suffered or extra costs incurred by Contractor resulting directly or indirectly from the award or performance or attempted performance of any other contract or contracts on the project, or caused by any decision or omission of District respecting the order of precedence in performance of contracts.
8.2 Contractor’s Responsibilities
Contractor must ascertain to its own satisfaction the scope of the project and nature of any other contracts that have been or may be awarded by District in prosecution of the project to the end that Contractor may perform the Contract in consideration of such other contracts, if any.
Contractor must afford other contractors and utilities reasonable opportunity for introduction and storage of their materials and execution of their tasks and must properly connect and coordinate its efforts with theirs. Contractor may not cause any unnecessary hindrance or delay to any other contractor working on the project.
If any part of Contractor’s Work depends for proper execution or results upon Work of any other contractor, Contractor must inspect and promptly report to the District Engineer any defects in such Work that render it unsuitable for such proper execution and results. Its failure so to do constitutes a waiver by Contractor of any claim of delay caused by events beyond Contractor’s control.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 14 -
9. Authority of the Engineer
9.1 General Authority
The Engineer will decide any and all questions which may arise as to the quality or acceptability of materials furnished and Work performed, and as to the manner of performance and rate of progress of the Work, and must decide all questions that may arise as to the interpretation of the drawings and specifications, and all questions as to the acceptable fulfillment of the Contract on the part of Contractor, and as to compensation. The Engineer’s decisions are final and the Engineer has authority to enforce and make effective such decisions and orders.
9.2 Interpretation of Drawings and Specifications
The Engineer will interpret the meaning of any part of the drawings and specifications about which any misunderstanding may arise and the Engineer’s decision will be final. Should there appear to be any error or discrepancy in or between the drawings and specifications, Contractor must refer the matter to the Engineer for adjustment before proceeding with the Work. Should Contractor proceed with the Work without so referring the matter, it does so at its own risk.
9.3 Inspection
(a) The Engineer must be provided full access to all operations involving the Work under the Contract and be provided reasonable advance notice of the time and place of operations which the Engineer desires to observe. The Engineer must be provided with all requested samples of materials and Work for testing purposes. (b) Contractor must furnish the Engineer reasonable facilities for obtaining such information as may be necessary to keep the Engineer fully informed respecting the progress and the manner of the Work. The Engineer’s inspection of the Work will not relieve Contractor from any obligation under the Contract. The Engineer has authority to stop any Work whenever provisions of Contract Documents are not being complied with and Contractor must instruct its employees and any subcontractors accordingly.
9.4 Disputes Pertaining to Payment for Work
Should any dispute arise respecting the true value of any of the Work done, of any of the Work omitted, or any extra Work which Contractor may be required to do, or respecting the size of any payment to Contractor during the performance of the Contract, such dispute will be decided by the Engineer.
10. General Provisions
10.1 Utilities
(a) All utilities, including but not limited to, electricity, water, gas, telephone used on the Work will be furnished at Contractor’s sole expense. Contractor must furnish and install necessary, temporary distribution systems, including meters, from distribution points to points on site where utility is necessary to carry on the Work. Upon completion of the Work, Contractor must remove all temporary distribution systems. Unless otherwise indicated, the Contractor must also arrange for permanent utilities as necessary for completion and operation (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 15 -
of the work. Contractor must pay for utilities until the “Project Acceptance and Final Payment” form is executed and the Work is accepted by the Engineer. (b) If the Contract is for an addition to an existing structure, Contractor may, with written permission of the Engineer, use District’s existing utilities to carry on the Work by making prearranged payments to District.
10.2 Water Supply
Water may only be used in the service area of the applicable water purveyor.
Water may not be imported or exported from one water purveyor’s service area to another water purveyor’s service area. If the work area crosses multiple water purveyor’s service areas, one fire hydrant meter from each water purveyor must be obtained, and water from each fire hydrant meter may only be used in the applicable water service area for each water purveyor.
All water used other than through a service connection and meter must be through a fire hydrant meter. Hydrant meters will be installed by the City of Camarillo Water Division or applicable water purveyor and moved from one location to another only upon approval of the City of Camarillo Water Division or other applicable water purveyor. The Contractor must pay all applicable fees and charges related to the construction water account, including but not limited to deposits, installation, inspection and related costs.
Water used will be charged at the unit rate per 100 cubic feet as currently established by City Council resolution or by the applicable water purveyor.
10.3 Dust Control
Contractor must provide such dust control equipment and methods as may be required to protect adjacent property from annoyance or damage from dust caused by its operations, and failure to control such dust will be cause for the Engineer to stop the Work until the dust is controlled. Contractor will have no recourse to collect from District for any loss of time or expense sustained by Contractor due to such suspension of the Work.
10.4 Removal and Disposal of Structures and Obstructions All fences, trees, and obstructions of any nature to the execution of the Work removed by Contractor must be disposed of, reused or delivered to City’s Corporation Yard as required. These tasks are to be included in the cost of other items bid on, if there is no item covering the same. Any obstruction that is privately owned that is removed by Contractor must be replaced or compensated at Contractor’s sole expense to the satisfaction of the Engineer.
10.5 Surveys
Surveys to determine location of property lines and corners, locations of construction, grading and site Work must be supplied by Contractor.
No survey information beyond the information on the plans will be provided by the Engineer. Contractor must preserve all stakes set for the lines, grades or measurements of the Work until authorized to remove them by the Engineer. Any expense incurred in replacing such stakes which Contractor may have failed to preserve will be borne by Contractor.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 16 -
10.6 Layout and Field Engineering
All field engineering required for laying out the Work and establishing grades for earthwork operations will be furnished by Contractor at its sole expense. Such engineering will be done by a qualified Civil Engineer approved by the Engineer. Any required “as built” drawings of site development must be prepared by the approved Civil Engineer at Contractor’s sole expense.
10.7 Traffic Requirements
(a) Street Closures, Detours, and Barricades.
(1) Street closures require discretionary City Council authorization and are not allowed unless no safe and effective alternative exists. Contractor must prepare a comprehensive justification for the proposed alternative.
Contractor must consider contract time in the justification, and allow at least 45 calendar days for City review and processing. Meetings, including those outside normal working hours may be necessary. (2) All costs involved in complying with the following requirements for street closures, detours and barricades will be borne by Contractor. (3) Contractor must notify the Engineer at least 5 working days before closing or partially closing any street. The Contractor must arrange detour routes and issue signing instructions, if required. All detour routes must be submitted for approval by the Engineer at least 10 working days before the detour.
(4) Contractor must notify the following agencies, at least 48 hours in advance of the closing, partial closing, or opening of any street or alley:
Camarillo Police Department 805-388-5100
Ventura County Fire Department 805-389-9710
Camarillo Public Works Department 805-388-5340
Camarillo Streets Division 805-388-5338
E.J. Harrison 805-207-0159
Camarillo Post Office 805-383-9804
Camarillo Area Transit 805-388-5346
(5) Contractor must install, maintain, and remove all temporary barricades, lights, warning signs, and other facilities necessary to control traffic as specified in the California Manual on Uniform Traffic Control Devices (CMUTCD). Materials for a temporary facility may be provided from new or used materials. If used materials are provided, they must be sound, in good condition, and otherwise meet the requirements of new materials. (6) If at any time any portion of the street is obstructed to traffic, Contractor must post “No Parking Anytime” signs on both sides of the street for a distance of 300 feet beyond the obstructed portion of the street. (7) In addition to the lane width specified in subsection (b) below, Contractor must maintain a minimum clearance of three feet to excavations and a (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 17 -
minimum of two feet to curbs and other obstructions. When traffic patterns required by the Work are such that opposing lanes of traffic must cross the existing centerline, Contractor must separate the opposing lanes at intervals, not to exceed 25 feet, or as directed by the Engineer. (b) Minimum Requirements for Maintaining Traffic Flow: Traffic in each direction must be maintained on all streets at all times. Traffic lanes of at least 10 feet must be used.
10.8 Tests and Inspections
(a) If the Contract, or any laws, ordinances, regulators or any public authority requires any of the Work to be specially inspected, tested or approved, Contractor must give notice in accordance with such authority of its readiness for such inspection or test at least two working days prior to such inspection. If inspection or testing is by an authority other than District, Contractor must arrange for such inspection or testing, and Contractor must also give at least two working days prior written notice to the authority and the Engineer of the date fixed for such inspection. Required certificates of inspection or approval must be secured by Contractor.
The Engineer will promptly make observations, where practicable, and do so at the source of supply. If any of the Work is covered up without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for inspection or testing and satisfactorily reconstructed at Contractor’s sole expense in strict accordance with the Contract Documents. Costs of tests and inspections of any materials found to be not in compliance with the Contract must be paid for by Contractor at its sole expense. Other costs for tests and inspection of materials will be paid by District.
(b) Where such inspection and testing are to be conducted by an independent laboratory agency, such materials or samples of materials to be tested will be selected by such laboratory or agency, or the Engineer, and not by Contractor. (c) Contractor must notify the Engineer in writing a sufficient time in advance of manufacture of materials to be supplied under contract, which must by terms of the contract be tested, in order that the Engineer may arrange for testing of same at the source of supply. Any materials shipped by Contractor from the source of supply prior to having satisfactorily passed such testing and inspection, or prior to receipt of notice from the Engineer that such testing and inspection will not be required, may not be incorporated in the Work without prior approval of the Engineer and subsequent testing and inspections.
(d) Re-examination of questioned Work may be ordered by the Engineer and, if so ordered, the Work must be uncovered by Contractor. If such Work is found to be in accordance with the Contract Documents, District will pay the costs of re-examination and replacement. If such Work is found not to be in accordance with the Contract Documents, Contractor must pay the costs at its sole expense.
10.9 Soils Investigation Report
When a soils investigation report is available from District, such report will not be a part of the Contract. Any information obtained from such report or any information given on drawings as to subsurface soil condition or to elevations of existing grades or elevations of underlying rock is approximate only, is not guaranteed, and does not form a part of the Contract.
Contractor is required to make a visual examination of site and must make whatever tests it deems appropriate to determine underground condition of soil. (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 18 -
10.10 Compaction Tests
(a) Contractor must perform compaction tests as required by the City Engineer, in accordance with ASTM D-1557 or California Test Method No. 216. (b) Contractor must bear the total expense of all failing tests.
10.11 Cutting and Patching
(a) Contractor must do all cutting, fitting, or patching of the Work as required to make its several parts come together properly and fit to receive or be received by other contractors showing upon, or reasonably implied by, the drawings and specifications for the completed project, as the Engineer may direct. All costs caused by defective or ill-timed Work will be borne by the Contractor.
(b) Contractor may not endanger any of the Work by cutting, excavating, or otherwise altering the Work and may not cut or alter any Work of any other contractor, except with the written consent of the Engineer.
10.12 Earthquake and Tidal Wave Damage
Notwithstanding the provisions of Subsection 4-2 of the SSPWC, when the Governor of California or the President of the United States declares that the area where the Work is being constructed is a disaster area due to earthquakes or tidal waves, Contractor will be relieved of the responsibility for repairing damage to the Work caused by earthquake or tidal wave, unless such damage results from negligent acts or omissions of Contractor.
10.13 Highway and Railroad Permits
The Engineer will obtain the basic state highway and railroad encroachment permits, which will include checking of plans. Contractor must also obtain its own permits from these agencies. Inspection and permit fees charged by these agencies must be paid by Contractor. Any other permits must be obtained by Contractor at no additional cost to District.
10.14 Noise Control
Construction Noise Level Limits: Construction operations must comply with City of Camarillo Municipal Code, specifically Chapter 10.34, Noise Regulations.
11. Acceptance of Work
11.1 No Waiver of Legal Rights
(a) District will not be precluded or estopped by any measurement, estimate, or certificate made either before or after the completion and acceptance of the Work and payment therefor from showing the true amount and character of the Work performed and materials furnished by Contractor, nor from showing that any such measurement, estimate, or certificate is untrue or is incorrectly made, nor that the Work or materials do not in fact conform to the Contract.
(b) District will not be precluded or estopped, notwithstanding any such measurement, estimate, or certificate and payment in accordance therewith, from recovering (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 19 -
from Contractor or its surety, or both, such damages as it may sustain by reason of Contractor’s failure to comply with the terms of the Contract.
(c) Neither the acceptance by the Engineer nor by the Engineer’s representative nor any payment for or acceptance of the whole or any part of the Work, nor any extension of time, nor any possession taken by the Engineer will operate as a waiver of any portion of the Contract or of any power herein reserved, or of any right to damages. (d) A waiver of any breach of the Contract will not be held to be a waiver of any other or subsequent breach.
11.2 Non-Complying Work
Neither the final certificate of payment nor any provision in the Contract Documents, nor partial or entire occupancy of the premises by the District, will constitute an acceptance of any of the Work not done in accordance with the Contract Documents or relieve Contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship.
11.3 Fulfillment of Contract
Contractor must, at its sole expense, protect and care for all the Work it performs until the Contract has been fulfilled to the satisfaction of, and the Work has been accepted in writing by, the Engineer. The date upon which the Engineer accepts the Work as complete will be the date that Contractor is relieved from responsibility to protect the Work.
11.4 Correction of Work Before Acceptance
(a) Contractor must promptly remove from the site or premises all Work determined by the Engineer as failing to conform to Contract, whether or not installed or incorporated.
Contractor must promptly replace and re-execute the Work to comply with the Contract Documents without additional expense to District and will bear the expense of making good all Work of other contractors destroyed or damaged by such removal or replacement. (b) If Contractor does not remove such nonconforming Work within a reasonable time, District may remove it and may store the material at Contractor’s expense. If Contractor does not pay expenses of such removal within 10 days’ time thereafter, District may, upon 10 days’ written notice, discard such materials or sell such materials at auction or at private sale and will provide an accounting to Contractor for net proceeds of such sale, after deducting all costs and expenses that should have been borne by Contractor.
11.5 Deductions for Uncorrected Work
If District deems it inexpedient to correct any Work injured or not done in accordance with the Contract, District will make an equitable deduction from the Contract price.
11.6 Final Clean Up
Upon completion of the Work and before acceptance and final payment will be made, Contractor, as its sole expense, must clean the Work area and all premises occupied by it in connection with the Work. All rubbish, weeds, graffiti, one-call USA markings, excess materials, falsework, temporary structures, tools and equipment must be removed and all parts (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 20 -
of the Work must be left in a neat and presentable condition. All excavations left by removal of structures must be filled and compacted with clean suitable soil acceptable to the Engineer.
11.7 Certificate as to Compliance With Certain Regulations Contractor must file with Engineer, prior to the acceptance of the Work, a certificate in form substantially as follows:
I (We) hereby certify that all of the Work has been performed and materials supplied in accordance with the specifications, drawings, and Contract Documents for the Work and that:
(a) no less than the prevailing rates of per diem wages as ascertained by the Director of Industrial Relations has been paid to workers employed on this Work and a copy of these rates has been posted and maintained at the Work site at all times during the course of the Work;
(b) there have been no unauthorized substitutions of subcontractors; nor have any unauthorized subcontracts been entered into;
(c) no subcontract was assigned or transferred or performed by anyone other than the original subcontractor, except as provided in the Subletting and Subcontracting Fair Practices Act, Public Contract Code section 4100 and following; and
(d) all claims for materials and labor and other services performed in connection with the Contract Documents have been paid.
12. Claims between District and Contractor
12.1 Definition of Claim
As used in this section, “claim” means a separate demand by Contractor, sent by registered mail or certified mail with return receipt requested, for (1) a time extension ( including, without limitation, for relief from damages or penalties for delay assessed by the District), (2) payment of money or damages arising from Work done by or on behalf of Contractor pursuant to the Contract and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (3) an amount the payment of which is disputed by District.
12.2 Notice of Potential Claim Procedure
(a) Contractor agrees that it may not be entitled to the payment of any additional compensation for any claim that may be based on any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, RFI response, or for the happening of any event or occurrence, unless the Contractor has given the Engineer written notice of a potential claim as provided in this subsection.
(b) The written notice of a potential claim must be submitted on the District’s claim form and certified with reference to the California False Claims Act, Government Code sections 12650-12655. The written notice of potential claim must include the following information:
(1) The complete nature and circumstances of the dispute which caused the potential claim.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 21 -
(2) The Contract provisions that provide the basis of the claim. (3) The estimated cost of the potential claim, including an itemized breakdown of individual costs and how the estimate was determined. (4) A time impact analysis of the project schedule that illustrates the effect on the scheduled completion date due to schedule changes or disruptions where a request for adjustment of contract
(c) The written notice of potential claim must be submitted to the Engineer prior to the time that the Contractor performs any additional work giving rise to the potential claim for additional compensation, if based on an act or failure to act by the Engineer and for which is not expressly provided for under this Contract. The Contractor must provide the Engineer the opportunity to examine the site or Work and respond within five business days from the date the notice of potential claim was submitted to the Engineer. The Contractor must then proceed with the performance of the additional work unless otherwise specified or directed by the Engineer.
When the affected work is completed, the Contractor must submit substantiation of the Contractor’s actual costs and total amount of the claim within 10 days of completing the work.
Failure to do so will be sufficient cause for denial of any claim subsequently filed on the basis of the notice of potential claim.
(d) In all other cases, the written notice of potential claim must be submitted to the Engineer within 15 days after the happening of the event, occurrence or other cause, giving rise to the potential claim.
12.3 Claim Processing Procedure
All claims for which a written notice of potential claim was filed and which claim is not resolved promptly resolved under subsection 12.2 will be processed and resolved in accordance with Public Contract Code section 9204, which is hereby incorporated by this reference, and the provisions of section 9204 are generally set forth in this subsection. This subsection and the requirements of Public Contract Code will not preclude the claimant and District from entering into a written waiver of the claim processing procedures outlined in this subsection and electing to resolve the dispute by arbitration pursuant to Public Contract Code section 10240 and following.
(a) The claimant must submit a written claim that includes reasonable documentation necessary to substantiate the claim.
(b) Upon receipt of the claim, the District and the claimant may, by mutual written agreement, extend the time period for the District to respond to the Contractor’s claim. (c) District will respond in writing to any written claim within: (i) 45 days of receipt of the claim; (ii) the extended time period according to Section 12.3(b); or (iii) where the Board of Directors does not meet within 45 days or the extended time period, three days after the next duly publicly noticed meeting on calendar.
(d) The District’s written response will identify the disputed and undisputed portions of the claim, and the District will process payment for any undisputed claims within 60 days after the written statement referenced in Section 12.3(c). If the claimant disputes District’s written response, or District fails to respond within the time prescribed in Section 12.3(c), the claimant may so notify District, in writing, and demand an informal conference to meet and confer for (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 22 -
settlement of the issues in dispute. Upon a demand, District will schedule a meet and confer conference within 30 days for settlement of the dispute. (e) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the District will provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the District issues its written statement. (f) Any disputed portion of the claim, as identified by the claimant in writing, must be submitted to nonbinding mediation, with the District and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators may select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
Each party bear s the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute may be resolved through other means, including civil action or arbitration in accordance with Public Contract Code sections 20104.4 and 20104.6.”
13. Assignment of Rights
In entering into this Contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to District all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700 of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment will be made and become effective at the time District tenders final payment to Contractor, without further acknowledgement by the parties. (Pub. Con. Code § 7103.5.)
14. Prohibited Interests
No official, employee, or agent of District, nor any member of their immediate family, may have any direct or indirect interest in this Contract.
15. Labor Code Requirements
15.1 State Wage Determination
(a) Under California Labor Code section 1770 and following, Contractor must pay not less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations. Copies of such prevailing rate of per diem wages are on file at the office of the Owner, which copies must be made available to any interested party on request, and are also available on the Internet at the website of the Department of Industrial Relations: http://www.dir.ca.gov/dlsr/PWD/index.htm. Contractor must post a copy of such determination at each job site.
(b) Under Labor Code section 1775, Contractor will, as a penalty to District, forfeit the statutory penalty each calendar day, or portion thereof, for each worker paid less than the (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 23 -
prevailing rates as determined by the Director for such work or craft in which such worker is employed for any public work done under the Contract by it or by any subcontractor under it. (c) Contractor must comply with all provisions of Labor Code section 1775.
15.2 Compliance Monitoring
(a) The Work is subject to prevailing wage compliance monitoring and enforcement by the Department of Industrial Relations (Labor Code § 1771.4). (b) Pursuant to Labor Code section 1771.4, Contractor and its subcontractor(s) must furnish the payroll records specified in Labor Code section 1776 directly to the Labor Commissioner and to the District, in the following manner:
(1) At least monthly or more frequently if specified in the contract with the awarding body.
(2) In a format prescribed by the Labor Commissioner.
(c) Contractor must post job site notices, as prescribed by regulation (Labor Code § 1771.4).
(d) If the District determines based on its review of the Contractor’s or any of its subcontractor’s certified payroll records that the Contractor or any subcontractor has underpaid its employees, then upon the second occurrence of such underpayment, the District reserves the right to obtain a certified payroll compliance monitoring consultant to assist the District in the additional work required to ensure Contractor or any subcontractor compliance and the associated costs will be the responsibility of the Contractor and will be deducted from Pay Estimates due to the Contractor.
15.3 Payroll Records
(a) Under Labor Code section 1776, Contractor and each subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by it in connection with the public work.
(b) The payroll records enumerated in subsection (a) above, must be certified and made available for inspection at all reasonable hours at the principal office of Contractor on the following basis:
(1) A certified copy of an employee’s payroll record must be made available for inspection or furnished to the employee or his or her authorized representative on request.
(2) A certified copy of all payroll records enumerated in subsection (a) must be made available for inspection or furnished upon request to a representative of the body awarding the Contract, the Division of Labor Standards Enforcement, and the Division of Apprenticeship Standards of the Department of Industrial Relations.
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 24 -
(3) A certified copy of all payroll records enumerated in subsection (a) must be made available upon request by the public for inspection or copies thereof made. However, a request by the public must be made through either the body awarding the Contract, the Division of Apprenticeship Standards, or the Division of Labor Standards Enforcement. If the requested payroll records have not been provided pursuant to subparagraph (2) above, the requesting party must, prior to being provided the records, reimburse the costs of preparation by Contractor, subcontractors, and the entity through which the request was made. The public may not be given access to the records at the principal offices of Contractor.
(c) Contractor or any subcontractor must file a certified copy of the records enumerated in subsection (a) with the entity that requested the records within 10 days after receipt of a written request.
(d) Any copy of records made available for inspection and copies furnished upon request to the public or any public agency by District, the Division of Apprenticeship Standards, or the Division of Labor Standards Enforcement must be marked or obliterated in such a manner as to prevent disclosure of an individual’s name, address, and social security number.
The name and address of Contractor or any subcontractor performing the contract may not be marked or obliterated.
(e) Contractor must inform District of the location of the records enumerated under subsection (a), including the street address, city and county, and must, within five working days, provide a notice of change of location and address.
(f) Contractor or any subcontractor has 10 days in which to comply subsequent to receipt of written notice requesting the records enumerated under subsection (a). In the event of noncompliance with the requirements of this Section, Contractor must, as a penalty to the state or District, forfeit the statutory penalty for each calendar day, or portion thereof, for each worker, until strict compliance is effectuated. These penalties will be withheld from progress payments then due. Responsibility for compliance with Section 15. 3 (a) through ( f) lies with Contractor.
(g) For all projects, the payroll records enumerated in subsection 15.3 ( a) above, must be delivered to the Labor Commissioner (no event less frequently than monthly) directly to the Labor Commissioner in the format prescribed by the Labor Commissioner. (h) For federally funded projects, Contractor must submit certified payroll records weekly to the Engineer.
(i) Upon request, Contractor must submit backup documentation for certified payroll records including cancelled checks, proof of payment of fringe benefits, time cards, apprenticeship documentation, and other backup records.
15.4 Apprentices
(a) Contractor must comply with Labor Code section 1777.5 and following, and Title 8, California Administrative Code section 200 and following, with respect to apprentices. To ensure compliance and complete understanding of the law regarding apprentices, and specifically the required ratio thereunder, Contractor and subcontractors should, where some (5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 25 -
question exists, contact the Division of Apprenticeship Standards prior to commencement of the Work. Responsibility for compliance with this Section lies with Contractor. District policy is to encourage the employment and training of apprentices on its construction contracts as may be permitted under local apprenticeship standards. These provisions require that contractors and subcontractors submit contract award information to the applicable joint apprenticeship committee, employ apprentices in apprenticeable occupations in a ratio of not less than one hour or apprentice’s work for every five hours of labor performed by a journeyman (unless an exception is granted in accordance with Section 1777.5), contribute to the fund or funds in each craft or trade or a like amount to the California Apprenticeship Council, and that contractors and subcontractors may not discriminate among otherwise qualified employees as apprentices solely on the ground of sex, race, religion, creed, national origin, ancestry or color. Only apprentices as defined in Labor Code section 3077, who are in training under apprenticeship standards and who have written apprentice agreements may be employed on public works in apprenticeable occupations. The responsibility for compliance with these provisions is fixed with the prime contractor for all apprenticeable occupations. Contractor agrees to provide Division of Apprenticeship Standards (DAS) Form 13 or any successor apprenticeship reporting form to District no later than the time of Contractor’s execution of the Contract Documents. (b) Contractor must comply with the requirements of Form FHWA 1273 (for federal ly funded projects), and Labor Code sections 1777.5 and 1776. In the event of conflict between the provisions, Contractor must comply with the most stringent provision that requires the largest number of apprentices.
15.5 Working Hours
(a) Contractor must comply with all applicable provisions of Labor Code section 1810 and following relating to working hours. Contractor will forfeit the statutory penalty to District for each worker employed in the execution of the Contract by Contractor or by any subcontractor for each calendar day during which such worker is required or permitted to work more than eight hours in any one calendar day and 40 hours in any one calendar week, unless such worker receives compensation for all hours worked in excess of eight hours at not less than one and a half (1-1/2) times the basic rate of pay. Contractor must comply with all requirements for payment of overtime and holiday rates of pay. (b) District may withhold from any monies payable on account of Work performed by Contractor or any subcontractor, such sums as may administratively be determined to be necessary to satisfy any liabilities of such Contractor or subcontractor, for unpaid wages and liquidated damages as provided for in subsection (a), above.
15.6 Workers Compensation
(a) Under Labor Code sections 1860 and 3700, Contractor is required to secure the payment of compensation of its employees.
(b) Under Labor Code section 1861, Contractor must sign and file with District the following certification prior to performing the Work of the Contract: “I am aware of the provisions of section 3700 of the Labor Code which require every employer to be insured against liability for worker’s compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the Work of this Contract.”
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 26 -
15.7 Protection of Workers in Trench Excavations
As required by Labor Code section 6705, whenever Work under the Contract involves the excavation of any trench or trenches five feet or more in depth, Contractor must submit for acceptance by District or by a registered civil or structural engineer, employed by District, to whom authority to accept has been delegated, in advance of excavation, a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation, of such trench or trenches.
If such plan varies from the shoring system standards established by the Construction Safety Orders of the Division of Industrial Safety, the plan must be prepared by a registered civil or structural engineer employed by Contractor, and all costs therefor will be included in the price named in the Contract for completion of the Work as set forth in the Contract Documents.
Nothing in this Section may be deemed to allow the use of a shoring, sloping, or other protective system less effective than that required by the Construction Safety Orders. Nothing in this Section may be construed to impose tort liability on District, the District Engineer, nor any District officers, agents, representatives, or employees. Unless a specific bid item is included in the Bid Proposal, payment for protection of workers in excavations requiring adequate sheeting, shoring, bracing and other safety provisions must be included in the bid item for mobilization. A separate item must be shown in the schedule of values for protection of workers in trench excavations. Contractor must obtain all necessary permits for excavation work from Cal/OSHA at Contractor’s expense.
16. Sales and Use Tax Cooperation
Contractor must take all steps reasonably necessary, as instructed by the Director of Finance, with respect to collection and reporting California Sales and Use Tax, to ensure that, to the extent legally possible, sales and use taxes collected for personal property purchased pursuant to this Contract, are reported with a point of sale within District.
17. Documentation of Status of Surety
Contemporaneously with the filing of a bid bond, labor and materials bonds, and faithful performance bond (or others), Contractor must obtain and file with District from the following documents:
(a) a certified copy of the unrevoked appointment Power of Attorney, By Laws or other instrument entitling or authorizing the person who executed the bond to do so; and (b) a certified copy of the Certificate of Authority of the issuer issued by the Insurance Commissioner of the State of California; and
(c) a certificate from the Clerk of the County where the principal office of the issuer is located that the Certificate of Authority of the issuer has not been surrendered, revoked, cancelled, annulled or suspended, or, in the event that it has been surrendered, revoked, cancelled, annulled or suspended, that renewed authority has been granted; and (d) copies of the insurers’ most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Article 10 of Chapter 1 of Part 2 of Division 1 of the Insurance Code (section 900 and following).
(5-2023)
GENERAL CONDITIONS/SPECIFICATIONS
- 27 -
18. Construction and Demolition Waste
Contractor must provide an accurate estimate of the amount of construction debris recycled as a result of the project. Any materials that could have been disposed of in a landfill, but were instead processed and reused on the project or elsewhere will be considered recycled.
Amounts must be itemized with description of the items recycled and must be reported in either cubic yards or tons (see Appendix). Examples of recycled construction debris are: asphalt concrete grindings, chunks of broken asphalt concrete, PCC chunks, base, soil, metals, and other similar materials. Contractor must sign the estimate of recycled construction debris and must certify that the estimate is accurate to the best of contractor’s knowledge. Contractor must provide this estimate prior to submittal of the final pay estimate and at such other reasonable intervals during the course of the project as requested by the Engineer.
19. Use of Premises
(a) The Work must be confined to District owned or controlled land or right-of-way as shown on the plans, unless otherwise expressly provided in the Contract Documents. If the right- of-way is not shown on the plans, the Contractor must field verify the right-of-way at no additional cost to the District. Contractor must provide at Contractor’s own expense and without liability to the District any additional land and access thereto that Contractor may desire for temporary construction facilities, or for storage and staging of materials. (b) Contractor may not trespass upon or in any way disturb property adjacent to District owned or controlled land or right -of-way or outside any permanent or temporary project construction easements without first obtaining written permission from the applicable property owner. A copy of such written permission must be furnished to the Engineer. (c) If Contractor finds it necessary to obtain additional working area, it is the responsibility of Contractor to negotiate permissions, obtain applicable permits and pay all costs pertaining to the additional work area.
(d) If additional work area is required and obtained, the following requirements will apply:
(1) Contractor must restore such property to the full satisfaction of the property owner at no additional cost to the District, and must obtain from the property owner a written release stating that restoration has been satisfactorily made. Contractor must provide the Engineer a copy of the written release from the property owner.
(2) Contractor may not place or dispose any excess earth, stone, or other excavated material on any property without first obtaining necessary permits and written permission of the owner of the property and securing the approval of the City Engineer. Contractor must provide the Engineer with one copy of the property owner's written permission and one copy of a written release from the property owner stating that the work has been completed to the satisfaction of the property owner.
(3) All items within any District owned or controlled land or right-of- way or within any permanent or temporary construction easements must be removed, or removed and replaced, or restored as required by the Plans and Specifications, as directed by the Engineer.
CAMARILLO SANITARY DISTRICT
DEPARTMENT OF PUBLIC WORKS
WASTEWATER SYSTEM GENERATOR
REPLACEMENT AT PS3 & PS5
PROJECT NO. SS-5120-1
These Special Provisions have been prepared under the direction of the following professional Engineers, licensed by the State of California
Kennedy Jenks
2775 North Ventura Road, Suite 202
Oxnard, CA 93010
LEAD CIVIL LEAD STRUCTURAL
Jack Stobaugh, P.E.
Registered Civil Engineer #95203
Exp. 09/30/2025
Signed: 06/05/2025
Milad Ketabdar, P.E.
Registered Civil Engineer #90448
Exp. 09/30/2025
Signed: 06/05/2025
LEAD ELECTRICAL
Zachary LeCroix Pyle, PE
Registered Electrical Engineer #24343
Exp. 12/31/2026
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
TC - 1 Table of Contents
WASTEWATER SYSTEM GENERATOR REPLACEMENT AT PS3 & PS5
PROJECT NO. SS-5120-1
TABLE OF CONTENTS
TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01010 Summary of Work
01020 Existing Conditions
01030 Stormwater Pollution Control Plan
01040 Administrative Requirements
01190 Seismic Design Requirements
01200 Measurement and Payment
01300 Submittals
01500 Construction Facilities and Temporary Controls
01505 Mobilization / Demobilization
01650 Facility Commissioning, Testing, and Startup
01700 Contract Closeout
DIVISION 2 - SITE WORK
02050 Demolition
02300 Earthwork
02700 Paving and Surfacing
DIVISION 3 - CONCRETE
03100 Concrete Formwork and Formwork Accessories
03200 Concrete Reinforcement and Reinforcement Supports 03300 Concrete Mixtures Handling Placing and Constructing 03305 Hot Weather Concreting
03306 Cold Weather Concreting
03330 Concrete Curing and Protection
03350 Concrete Finishing (Structural)
03600 Grouts
03935 Repair of Defective Concrete
DIVISION 5 - METALS
05090 Anchors in Concrete and Masonry
05500 Metal Fabrications (Miscellaneous Metal)
DIVISION 16 - ELECTRICAL
16010 General Electrical Requirements
16110 Electrical Raceway Systems
16120 Low Voltage Wire and Cable
16124 Signal Cable
16180 Protective Devices and Switches
TABLE OF CONTENTS
(Continued)
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
TC - 2 Table of Contents
16205 Standby Diesel Engine Generator Sets
16250 Automatic and Non-Automatic Transfer Switches
16402 Underground Electrical Work
16405 Switchboards
16450 Electrical Grounding
16460 Dry-Type Transformers
16950 Electrical Tests
16961 Power System Studies
DIVISION 17 - INSTRUMENTATION AND CONTROL
17010 Instrumentation and Controls, General Requirements
END OF TABLE OF CONTENTS
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 1 Summary of Work
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.01 GENERAL DESCRIPTION OF THE WORK
A. Location:
1. Pump Station #3 near 1682 Pleasant Valley Rd in Camarillo, California.
2. Pump Station #5 near 21 S Wood Rd in Camarillo, California.
B. The project includes but is not limited to:
1. Upgrades to existing site electrical systems at the Pump Station No. 3 and No. 5 sites including modifying the main switchboard, replacing the permanent standby generators with Owner-Furnished, Contractor installed permanent standby generators, replacing the automatic transfer switches (ATS) with Owner-Furnished, Contractor installed ATSs, installing new manual transfer switches (MTS) with Owner-Furnished, Contractor installed MTSs, adding circuits for the new generator load centers, and installing new duct banks with conduit and wiring.
2. Structural modifications including new concrete pads for the generators and electrical equipment.
3. Demolition of the existing concrete pads (at Pump Station No. 3 only) and removal of electrical equipment.
1.02 GENERAL REQUIREMENTS OF THE WORK
A. All work must be coordinated with the Engineer, District staff, Project Schedule, Contract Period, Submittals, and other requirements of these Contract Documents.
B. Construction signage shall be provided by Contractor as directed by the Engineer to ensure safety and convenience for staff and vendors onsite at the plant at no additional cost to the District.
C. The District reserves the right to direct the order of work in the interest of safety and convenience. The Engineer will endeavor to give the Contractor 72 hours of notice of any such directed order of work.
D. The Contractor must diligently execute the contract work within the allowed number of working days specified in Page 1 of the Bid Proposal, counting from the date stated in the Notice to Proceed for construction. The days to finish the punch list, provided by the District, are included in the working days.
E. Contractor shall provide at least ten (10) working days notification in advance of planned connection to the Owner’s existing pipelines, ducts, or electrical facilities or any activity that could potentially interfere with the operation of the District’s facilities. Owner will operate existing valves and facilities.
1.03 STANDARD SPECIFICATIONS AND DETAILS
A. The work provided herein must conform to and be in accordance with the Contract Plans, General Conditions/Specifications and Special Provisions, as well as the 2024 edition Standard Specifications for Public Works Construction (”SSPWC”),
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 2 Summary of Work
written and promulgated by the Public Works Standards, Inc.; herein referred to as the “Standard Specifications”, the State of California Department of Transportation Standard Specifications; hereinafter referred to as the “State Standard Specifications”, California Manual on Uniform Traffic Control Devices (CMUTCD), City of Camarillo (City) Standards, City of Camarillo Water Division Standards, and Camarillo Sanitary District (District) Standards.
B. In resolving conflicts among any of the Contract Documents, the order of precedence shall be as identified in the Instruction to Bidders. In the event of discrepancy between any drawings and the details written thereon, the figures will govern. In the event of a discrepancy within the same type of Contract Document, the more stringent requirement will govern as determined by the Engineer.
C. Whenever in the Contract Documents references are made to published specifications, codes, standards, or other requirements, it is understood that if a date is not specified, only the latest specifications, standards, or requirements of the respective issuing agency which have been published as of the date that the Work is advertised for bids will apply; except to the extent that such standards or requirements may be in conflict with applicable laws, ordinances, or governing codes. No requirements set forth herein or shown on the drawings will be waived because of any provision of, or omission from, the standards or requirements.
1.04 GENERAL SAFETY REQUIREMENTS
A. Contractor must do whatever work is necessary for safety and be solely and completely responsible for conditions of the job site, including safety of all persons (including employees) and property during the Contract period. Safety provisions must conform to Federal and State Departments of Labor Occupational Safety and Health Act (OSHA), and other applicable Federal, State, County and local laws, ordinances, codes, requirements set forth herein, and regulations that may be specified in other parts of these Contract Documents. Contractor must do all work necessary to protect the general public from hazards, including, but not limited to, surface irregularities or unramped grade changes in vehicular travel ways (including but not limited to streets, roads and driveways), pedestrian sidewalks or walkways. Barricades, lanterns, and proper signs must be furnished in sufficient amount to safeguard the public and the work. This requirement applies continuously and is not limited to normal working hours.
B. Contractor must develop and maintain for the duration of the Contract, a safety program that will effectively incorporate and implement required safety provisions.
The Contractor must appoint a qualified employee who is authorized to supervise and enforce compliance with the safety program.
1.05 OWNER-FURNISHED CONTRACTOR INSTALLED ITEMS (O.F.C.I.) A. Certain items required for this project will be furnished by the Owner and installed by the Contractor. Such items are referred to as "Owner-Furnished Contractor Installed (O.F.C.I.)." O.F.C.I. items shall be delivered to the job site by the equipment vendor through which the Owner has procured the equipment. This equipment will be installed by the Contractor.
B. Contractor's installation of O.F.C.I. items shall include attaching or anchoring items, connecting utilities and controls, lubricating and necessary adjustment,
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 3 Summary of Work
startup, testing, placing items in service. If items are new Contractor shall turn over operation and maintenance manuals and equipment warranties to Owner.
C. For this project, the following items shall be O.F.C.I:
1. Emergency Generators
2. ATSs
3. MTSs
1.06 ORDER OF THE WORK
A. It is the Contractor’s responsibility to fully schedule and coordinate the Work. The Contractor is required to submit a detailed step by step construction sequence in accordance with Section 01300 to the Engineer and arrange a meeting to discuss the details. The construction sequence submittal shall accompany the schedule and be submitted at the beginning of the project.
B. The Contractor must control operations such that the following conditions can be met:
1. Demolition of items affecting District operations and facilities cannot start until all associated replacement materials are in possession, immediately accessible by the Contractor, and District is in agreement with Contractor’s proposed schedule.
2. Owner shall be notified ten (10 ) days prior to any work that impacts its operations or connects to existing facilities. The Contractor shall work diligently to coordinate the work and mitigate impacts to the District, its staff, and operations. The Contractor’s use of the premises shall not impede normal operation of the existing facilities.
C. General Requirements. The Pump Stations are a critical source of wastewater disposal/transmission for the area. The Contractor is to conduct work such that the Owner's ability to operate it’s pump stations shall not be impaired or reduced in terms of the ability to pump wastewater to the receiving entity. It is required that the pump stations always remain operational and that standby emergency power be always provided.
1. Work Sequence and Constraints described hereinafter are critical events in work sequence which are presented to underscore the importance of proper sequencing, scheduling, and coordination so that it is integrated with the required pump station operation. The work sequence and constraints presented do not describe all items affecting the completion of the Work but are intended to describe important events necessary to minimize disruption of the existing facilities and to ensure compliance any permit requirements.
2. The existing facility where Contractor's work is to be done will be occupied by the Owner throughout the construction period. The Contractor shall provide all necessary access to the Owner's personnel as required to operate/maintain the facilities safely and efficiently. At all times during the Contract duration, the Contractor is to provide the Owner's personnel and representatives safe and immediate access to all process control equipment.
Additionally, the Contractor is to provide for unimpeded access for all delivery vehicles transporting materials, chemicals, and equipment to the facility for the Owner's operations.
3. The Work shall be bid, scheduled and constructed in such a manner as to result in the least possible disruption to the operations and staff of the existing facility. Modifications that affect or may affect the operation of the
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 4 Summary of Work
facility shall not be made without first obtaining written permission from the Engineer. The Contractor must fully understand any and all possible impacts on wastewater pumping capacity as they plan the Work.
4. The Contractor shall provide adequate bypass pumping for the expected flow rates (6,500 gallons per minute for Pump Station #3 and 2,900 gallons per minute for Pump Station #5) and piping facilities so the pump station continues conveying wastewater as necessary during any shut downs.
Contractor shall clean the work areas as required to perform the work.
Shutdown and isolation of existing facilities by closing existing valves/gates and operating electrical control panels, or as specifically provided for in the Contract Documents, will be performed by Owner personnel.
5. Prior to any shutdown or flow diversion all materials, fittings, supports, equipment and tools shall be on the site and all necessary skilled labor scheduled prior to starting any work. The Contractor shall provide staff following shutdowns to monitor and ensure the proper operation of systems.
6. The Contractor is advised that any shutdown of facilities will place a considerable burden on the Owner's staff before, during and after the shutdown. If through inadequate planning, lack of preparedness, faulty or inefficient workmanship or other causes controllable by the Contractor, delays, excessive time, or additional shutdowns are required that cause the Owner to incur extra cost, said extra cost will be assessed against the Contractor.
7. To minimize impact on the Owner, major outages are not allowed. Minor outages less than 15 minutes for minor work including the removal of existing terminations or terminating new conductors are allowed during low flow periods after written approval from the Engineer.
8. The Contractor shall bear all costs and responsibilities for any sanitary sewer overflows that occur because of the Contractor’s mismanagement of the temporary power or bypass pumping requirements described in this Section.
9. The Contractor shall note that only certain structures, tie-ins and constraints are addressed in this Section. All work, whether or not addressed here, shall be governed by applicable parts of this Section, and schedules and procedures further submitted for approval.
10. The Contractor shall provide telemetry to enable remote monitoring of the temporary generators and bypass pumps.
D. Some construction elements can be accomplished at any time during the contract period, but many will require coordination with other items being completed first.
Therefore, a preliminary construction phase sequence is described below to help define the probable sequence of major activities required for the Contractor to comply with and to properly address the previously mentioned constraints. The Contractor is responsible for the phasing of work to honor the constraints, complete the work, coordinate with Owner's work and meet the schedule for completion.
1. Pump Station 3 (PS3)
a. Phase 1 – Demolish and Replace Standby Generator, Install New MTS 1) Provide temporary standby fuel powered pumps and a remote telemetry system, approved by the Engineer, for the duration of this phase in case circumstances arise that could cause power outage(s). This phase shall take place when the pump station is operating on utility power. If a utility power outage occurs, the Contractor shall operate the pump station using standby fuel powered pumps, immediately.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 5 Summary of Work
a) Demolish the existing generator and all associated
apparatuses. The Contractor shall dispose of fuel in the existing generator fuel tank before removal/demolition
b) Install the new concrete pads, permanent standby generator, disconnects/transformers, required duct bank, and
conductors.
c) Install the new MTS and required duct bank and conductors. d) Terminate the new generator conductors at the MTS.
e) Ensure the new generator fuel tank is full.
2) The fuel powered pumps must always be supervised by the Contractor while operating. At no point should the pump be operated overnight or unattended. Any work requiring bypass pumping should be completed in an 8-hour period whenever possible.
3) The conveyance of wastewater cannot be interrupted. The Contractor must prevent backups in the upstream gravity sewers or sanitary sewer overflows that might result.
4) Temporary piping shall be provided along with the fuel powered pumps to the extent necessary to achieve conveyance of
wastewater to the receiving entity.
b. Phase 2 – Remove and Replace ATS:
1) Provide temporary operational (primary) and standby fuel powered pumps and a remote telemetry system, approved by the Engineer and City, for the duration of this phase as the pump station will be de-energized throughout this phase, the Contractor shall operate the pump station using the operational and standby fuel powered pumps.
a) Demolish the existing ATS inside the existing main
switchboard. The ATS must be de-energized during this
work.
b) Install the new ATS inside the existing main switchboard. c) Intercept the existing ductbank, install new handholes and ductbank to the MTS, and run new conductors from the ATS to the MTS.
d) Provide functional testing of the ATS, MTS, and the
Generator as required by the contract documents prior to un- installing the temporary fuel powered pumps.
2) The fuel powered pumps must always be supervised by the Contractor while operating. At no point should the pump be operated overnight or unattended. Any work requiring bypass pumping should be completed in an 8-hour period whenever possible.
3) The conveyance of wastewater cannot be interrupted. The Contractor must prevent backups in the upstream gravity sewers or sanitary sewer overflows that might result.
4) Temporary piping shall be provided along with the fuel powered pumps to the extent necessary to achieve conveyance of
wastewater to the receiving entity.
2. Pump Station 5 (PS5)
a. Phase 1 – Remove and Replace ATS:
1) Provide temporary operational (primary) and standby fuel powered pumps and a remote telemetry system, approved by the Engineer
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 6 Summary of Work
and City, for the duration of this phase as the pump station will be de-energized throughout this phase, the Contractor shall operate the pump station using the operational and standby fuel powered pumps.
a) Demolish the existing ATS inside the existing main
switchboard. The ATS must be de-energized during this
work.
b) Install the new ATS inside the existing main switchboard.
Terminate the existing generator cables.
c) Provide functional testing of the ATS and the existing Generator as required by the contract documents prior to un- installing the temporary fuel powered pumps.
2) The fuel powered pumps must always be supervised by the Contractor while operating. At no point should the pump be operated overnight or unattended. Any work requiring bypass pumping should be completed in an 8-hour period whenever possible.
3) The conveyance of wastewater cannot be interrupted. The Contractor must prevent backups in the upstream gravity sewers or sanitary sewer overflows that might result.
4) Temporary piping shall be provided along with the fuel powered pumps to the extent necessary to achieve conveyance of
wastewater to the receiving entity.
b. Phase 2 – Install New Standby Generator, New MTS
1) Install the new concrete pads, permanent standby generator, disconnects/transformers, required duct bank, and conductors. 2) Install the new MTS and required duct bank and conductors. 3) Terminate the new generator conductors at the MTS.
4) Terminate the new conductors at the ATS.
5) Provide functional testing of the ATS, MTS, and the Generator as required by the contract documents.
6) Ensure the new generator fuel tank is full.
c. Phase 3 – Demolition
1) Demolish the existing generator and all associated apparatuses.
The Contractor shall dispose of fuel in the existing generator fuel tank before removal/demolition
1.07 CONTRACTOR'S USE OF PREMISES
A. The Contractor’s use of the premises shall not impede normal operation of the existing facilities. Contractor must advise the Engineer at least twenty (20) working days in advance of any activity that could potentially interfere with the operation of the existing treatment facility.
B. Always maintain construction site security and safety and adhere to District’s site security measures.
C. The Contractor shall provide fixed and/or portable chemical toilets and washing facilities for the use of the Contractor’s employees, subcontractors, and visitors to the work site. Contractor employees and subcontractors shall not use District facilities without prior written permission.
1. These accommodations shall be in sufficient quantity and have regular service in order to maintain them in a neat and sanitary condition. Toilets and washing
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 7 Summary of Work
facilities shall conform to the requirements of Title 8, California Code of Regulations, and shall be placed in near proximity to the worksite.
2. Locations to be approved by the District.
3. All temporary toilets and washing facilities shall be furnished and placed during mobilization to the work site and shall be removed upon demobilization.
D. The Contractor shall confine its use of the site for work and storage to the Work Area Limits shown on the Contract Drawings. The Contractor's use of adjacent lands and roads for access to move onto and off of the site and for daily access of workers, material and equipment shall be arranged and scheduled to minimize interference with the Owner's continued operations.
E. The Owner intends to continue operation of portions of its existing facility during all or most of the construction period. The Contractor shall plan and schedule its work to minimize impacting the Owner's continued operations and shall, at all times, maintain safe access for the Owner's operating personnel and equipment.
F. The Contractor shall be responsible for maintaining safe emergency exiting for the Owner's and Contractor's personnel in all areas affected by the Contractor's work.
G. If operation of the Owner's existing facility is adversely affected by the Contractor's work, the Owner may suffer a financial loss and may make a claim against the Contractor to recover that loss.
1.08 COORDINATION WITH OWNER AND IMPACT OF WORK
A. The project sites are in operation 24 hours per day. Work shall be performed in such a manner to mitigate impacts to the District. Shutdown periods shall be avoided or minimized to the greatest extent possible by the Contractor throughout construction.
B. Proposed timing of shutdowns shall be included in the project schedule for Owner’s review and approval. For shutdowns of existing improvements and equipment, Contractor shall submit shutdown and bypass plans for Owner’s review and approval. Contractor is responsible for furnishing and installing bypass pumping equipment, appurtenances, any required electrical/controls infrastructure, and any temporary treatment, instrumentation, or other equipment to facilitate bypass of each process. Contractor shall facilitate coordination with District staff and Owner’s Representative to maintain continuity and operation of all bypass or temporary operations for the duration of the construction period.
C. It is the sole responsibility of the Contractor to ensure systems are usable and accessible during construction. The Contractor shall install temporary systems if required to maintain operations at no extra cost to the District.
1.09 SHUTDOWN OF EXISTING UTILITIES, SERVICES OR OPERATIONS A. The Work under this Contract involves modification of facilities at an existing operating facility, which must continue to meet requirements of the State and Federal regulating agencies. Therefore, those functions shall not be interrupted except as specified herein.
B. Schedule utility service or operations shutdowns for periods of minimum use and at the Owner's convenience. Have all required material, equipment and workers on site prior to beginning any work involving a possible shutdown. Perform work so
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 8 Summary of Work
services will be restored in the minimum time possible. In some cases, this may require increased numbers of workers and/or premium time night or weekend work.
C. The Contract Price shall include the cost of additional workers and premium time work required to minimize the impact of utility service or operations shutdowns. If premium time work is required, the difference in cost between performing the work during normal working hours and premium time will be covered by a Change Order.
1.10 EXISTING UTILITIES
A. General:
1. Existing buried utilities and pipelines are shown in the Drawings in their approximate location based on the best available information available. The actual location, size, type and quantity of utilities and underground facilities may differ from that shown and utilities or underground facilities may be present that are not shown. See the General Conditions for the Contractor's responsibilities and for differing conditions that warrant a change in Contract Price.
2. Utilities are piping, valves, appurtenances, conduits, wire, cable, duct banks.
3. Exercise care in avoiding damage to all utilities . Contractor shall be responsible for repairing or replacing utilities, damaged during construction, in kind or better at no cost to the Owner.
4. Overhead Facilities: There may be existing overhead electric and telephone transmission lines at the site. These overhead utilities are not shown on the Drawings. Extreme caution shall be used when working in the vicinity of overhead utilities to prevent injury to workmen or damage to the utilities. The Contractor shall be required to comply with the applicable provisions of the California Construction Safety Orders when working anywhere on this project.
B. Potholing:
1. Obtain best available current information for location, identification and marking of existing utilities before beginning any excavation. In areas where utilities participate in Underground Service Alert, contact 1-800-424-5555, 811 OR DigAlert for information at least 48 hours in advance of beginning work. Give the Engineer 24 hours-notice before beginning work.
2. Contact all affected utility owners and request them to locate their respective utilities prior to the start of "potholing" procedures. The utility owner shall be given 3 days written notice prior to commencing potholing. If a utility owner is not equipped to locate its utility, the Contractor shall locate it.
3. When in pavement, clearly paint the location of all existing utilities where crossings, interferences, and/or connections to new pipelines or other facilities are shown on the Drawings, marked by the utility companies, or indicated by surface features. If utilities are not in pavement, identify the location with suitable markers.
4. After the utility survey is completed, and prior to preparing piping shop drawings, or the excavating for any new utilities or structures Contractor shall commence “potholing” or hand digging to locate and uncover existing utilities to a point 1 foot below the utility. Identify actual locations and elevations of all utilities where crossings, interferences, and/or connections to new pipelines or other facilities are shown on the Drawings, marked by the utility companies, or indicated by surface features.
5. Submit a report identifying each underground utility, location, at grade elevation, depth of cover, size, and material. Any variation in the actual
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 9 Summary of Work
elevations and the indicated elevations shall be brought to the Engineer's attention.
6. Excavations around underground electrical ducts and conduits shall be performed using extreme caution to prevent injury to workmen or damage to electrical ducts or conduits. Similar precautions shall be exercised around gas lines, telephone, and television cables.
7. Excavations shall have a surface dimension of no more than 18-inch by 18-inch. Air spades and vacuum excavators shall be used to limit the size of the excavation and damage to adjacent facilities. Backfill after completing potholing.
8. The Potholing Report shall be submitted prior to submission of pipe layouts and installation of piping.
C. Interferences:
1. If interferences occur at locations other than shown on the Drawings, notify the Engineer in writing. A method to correct the interferences shall be provided by the Engineer. Payment for interferences that are not shown on the Drawings, nor which may be inferred from surface features, and the Contractor has exposed all required utilities prior to shop drawing preparation, shall be in accordance with the provisions of the General Conditions.
2. Any necessary relocations of utilities, whether shown on the Drawings or not, shall be coordinated with the affected utility Owner. The Contractor shall perform the relocation only if instructed to do so in writing from the utility and the Owner.
1.11 WORK DAYS AND HOURS
A. No work may be performed on Saturday, Sunday, or holidays unless approved in advance by the Engineer. Holidays are anticipated as follows:
Holiday: Date:
New Years Day (January 1)
Martin Luther King Day (3rd Monday in January)
Presidents Day (3rd Monday in February)
Memorial Day (last Monday in May)
Independence Day (July 4th)
Labor Day (1st Monday in September)
Veterans Day (November 11th)
Thanksgiving Day (4th Thursday in November)
Day after Thanksgiving (4th Friday in November)
Christmas Eve (December 24th)
Christmas Day (December 25th)
Note: If a holiday falls on a weekend, a Saturday holiday will be observed on Friday and a Sunday holiday will be on a Monday. If part or all of a 2-day holiday falls on a weekend, the District will determine which 2 weekdays will be holidays.
B. Work shall be executed during all or part of the following time period:
1. Normal daily work hours are from 6:00 a.m. to 3:30 p.m. Work after these hours must be coordinated with District management.
2. Work on arterial streets (four or more lanes) is from 8:30 a.m. to 4:00 p.m.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 10 Summary of Work
3. Work within City Right of Way within two blocks of a school is from 9:00 a.m. to 3:00 p.m.
4. Work hours are subject to change and the District reserves the right to adjust the working hours at specific locations or on specific systems to facilitate District operations as required by the work and as determined during coordination of the project.
C. Contractor may submit a written request to District for extended work hours for specific portions of work as required for safety and convenience or emergency.
District denial of the Contractor’s request for extended work hours does not warrant an extension of the Contract Time.
D. If the Contractor performs any work or has any site presence outside the hours listed in this section, or on weekends or holidays without prior District approval, the District reserves the right to hire a security service to ensure contractor compliance and associated costs will be the responsibility of the contractor and will be deducted from Pay Estimates due to the Contractor.
E. Contractor must reimburse District for costs for overtime inspection associated with project work hours. Costs will include hours in excess of 8-hours per workday shift, hours in excess of 40-hours per work week, and weekend and holiday work when specifically authorized.
1.12 RIGHT-OF-WAY
A. Attention is directed to Section 2-3 “Right-of-Way” of the Standard Specifications, Section 2.1 and Section 19 “Use of Premises” of the General Conditions/Specifications, and these Special Provisions.
B. The Contractor must verify that the acquisition(s) is completed prior to beginning any work outside the public right of way. All cost for remobilization, downtime, etc., due to delays in obtaining the required rights of way, easements, and rights of entry must be included in the lump sum price bid for the various items of work and no additional compensation will be allowed.
C. The Contractor will not be entitled to the exclusive use of any District street or rights-of-way during the performance of the work under the contract, and the Contractor must conduct operations so as not to interfere unnecessarily with business, traffic, pedestrians, and the authorized work of utility companies or other agencies in the street or rights-of-way. Neither the Specifications nor the Plans may be construed to entitle the Contractor to conduct operations within the rights- of-way which are in violation of any local, county, or state ordinance or regulation restricting interference with water courses and drainage channels. The Contractor must take adequate precaution against obstructing storm water flow within the project limits. The Contractor may not deposit excavated materials, store equipment, or construction materials within the street.
1.13 REGULATORY REQUIREMENTS
A. The codes and regulations together with local amendments when applicable adopted by the State and other governmental authorities having jurisdiction shall establish minimum requirements for this project. This project shall comply with the following:
1. International Building Code (IBC) 2021 Edition
2. International Fire Code (IFC) 2021 edition
3. International Mechanical Code (IMC) 2021 edition
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 11 Summary of Work
4. Uniform Plumbing Code (UPC) 2021 edition
5. National Electric Code (NEC) 2020 edition
6. California Fire Code (CFC) 2022 edition
7. California Mechanical Code (CMC) 2022 edition
8. California Plumbing Code (CPC) 2022 edition
9. California Electric Code (CEC) 2022 edition
10. California Energy Code 2022 edition
11. California Code of Regulations
a. Title 8, Industrial Relations: Especially CAL-OSHA and Elevator Safety Orders.
B. The latest edition of the requirements in effect at the date of submission of bids shall apply.
C. General Conditions paragraph 5.11 covers the Contractor's responsibility to comply with laws and codes applicable to Means and Methods for performing the Work.
D. General Conditions paragraph 5.14 covers the Contractor's responsibility to report code deficiencies in the design to the Engineer prior to proceeding with the Work.
E. Paragraphs addressing Pre-Engineered Systems and Performance Specifications in other Sections cover the Contractor's responsibility to comply with code requirements when (1) performance specifications are used to describe all or portions of Work or items and (2) when pre-engineered (contractor designed) systems are specified.
F. In cases where the Contract Documents are more restrictive than applicable codes, the Contractor shall comply with the Contract Documents.
1.14 REFERENCE STANDARDS
A. When these specifications state that Work or tests shall conform to specific provisions in a referenced standard, specification, code, recommendation or manual published by an association, organization, society or agency the referenced provisions, as they apply to the Work of the Contractor only shall be considered a part of these specifications as fully as if included in total. When these specifications or applicable codes contain higher or more restrictive requirements than those contained in reference standards these specifications or applicable codes shall govern.
B. The latest edition of a referenced standard published at the time of submission of bids shall apply unless a specific date for the referenced standard is cited in these specifications.
C. General provisions in referenced standards, specifications, manuals or codes shall not change the specific duties and responsibilities between any of the parties involved in this work from those described in the General Conditions. Provisions in referenced standards with regard to measurement and payment shall not apply to this Work unless specifically cited. See General Conditions paragraph 2.3.
1.15 SPECIFICATION LANGUAGE AND STYLE
A. Many parts of the Specifications as well as notes on the Drawings are written in the active voice and are addressed to the Contractor.
1. When words or phrases requiring an action or performance of a task are used, it means that the Contractor shall provide the action or perform the task. For example: provide, perform, install, furnish, erect, connect, test,
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 12 Summary of Work
operate, adjust or similar words mean that the Contractor shall perform the action or task referred to.
2. When words or phrases requiring selection, acceptance, approval, review, direction, designation or similar actions are referred to, it means that such actions are the Owner's or the Engineer's prerogative and that the Contractor must obtain such action before proceeding.
B. Requirements in the Specifications and Drawings apply to all work of a similar type, kind or class even though the word "all" or "typical" may not be stated.
1.16 DEFINITIONS
A. The following terms, when used in the Contract Documents, shall have the meanings listed:
ACCEPTABLE
CITY, DISTRICT
OR OWNER
"acceptable to the Engineer"
“Camarillo Sanitary District”
PERFORM "perform all operations required to complete the work referred to in accordance with the intent of the Contract Documents" PROVIDE "furnish and install the work referred to including proper anchorage, connection to required utilities or other work, testing, adjustment and startup ready to put in service and perform the intended function"
REQUIRED "required by the Contract Documents or required to complete the Work and produce the intended results"
SATISFACTORY "acceptable to the Engineer"
SHOWN "as indicated on the Drawings"
SITE "geographical location of the Project and land within the work area shown on the contract drawings and within which the Work will be installed or built"
SPECIFIED "as written in the Contract Documents including the Specifications and the Drawings"
SUBMIT "submit to the Engineer"
1.17 ABBREVIATIONS
A. The following acronyms or abbreviations are used in these specifications for the organizations listed.
Abbreviation Stands for
AASHTO American Association of State Highway and Transportation Officials AAMA Architectural Aluminum Manufacturers Association
ABMA American Boiler Manufacturers Association
ACI American Concrete Institute
ADC Air Diffusion Council
AGA American Gas Association
AGMA American Gear Manufacturers Association
AI Asphalt Institute
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
AITC American Institute of Timber Construction
AMCA Air Moving and Conditioning Association
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 13 Summary of Work
Abbreviation Stands for
ANSI American National Standard Institute (formerly United States of America Standards Institute)
APA American Plywood Association
API American Petroleum Institute
APWA American Public Works Association
AREA American Railway Engineering Association
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers
ASME American Society of Mechanical Engineers
ASTM ASTM International
AWPA American Wood-Preservers' Association
AWS American Welding Society
AWWA American Water Works Association
CAGI Compressed Air and Gas Institute
CAL/OSHA State of California Department of Industrial Relations, Division of Industrial Safety
CAL TRANS California Department of Transportation
CBC California Building Code
CBM Certified Ballast Manufacturers
CBR California Bearing Ratio
CEC
CI
California Energy Code
Chlorine Institute
CISPI Cast Iron Soil Pipe Institute
CMAA Crane Manufacturers Association of America
CPSC Consumer Products Safety Commission
CRA California Redwood Association
CRSI Concrete Reinforcing Steel Institute
CS Commercial Standards for the U.S. Department of Commerce CTI Cooling Tower Institute
DFPA Douglas Fir Plywood Association
EIA Electronic Industries Association
EPA U.S. Environmental Protection Agency
ETL Electronic Testing Laboratory
FM Factory Mutual Insurance Company
FPS Fluid Power Society
FS Federal Specifications
GO 95 General Order No. 95, California Public Utilities Commission Rules for Overhead Electric Line Construction
GO 128 General Order No. 128, California Public Utilities Commission Rules for Underground Electrical Construction
HI Hydraulic Institute
HMI Hoist Manufacturers Institute
IAPMO International Association of Plumbing and Mechanical Officials IBC
ICBO
International Building Code
International Conference of Building Officials
IEEE Institute of Electrical and Electronic Engineers
IES Illuminating Engineering Society
IFC
IGCC
International Fire Code
Insulating Glass Certification Council
IMC International Mechanical Code
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01010 - 14 Summary of Work
Abbreviation Stands for
IPCE International Power Cable Engineers Association
ISA Instrument Society of America
NAAMM National Association of Architectural Metal Manufacturers NBS National Bureau of Standards
NCPI National Clay Pipe Institute
NEC National Electric Code
NEMA National Electrical Manufacturers Association
NETA International Electrical Testing Association
NFPA National Fire Protection Association
NGVD National Geodetic Vertical Datum
NSF National Sanitation Foundation
NWMA National Woodwork Manufacturers Association
OSHA Occupational Safety and Health Act
PCA Portland Cement Association
REA Rural Electrification Administration
SAMA Scientific Apparatus Makers Association
SMACNA Sheet Metal and Air Conditioning Contractors National Association SSPC Structural Steel Painting Council
TCA Tile Council of America
UBC Uniform Building Code
UFC Uniform Fire Code
UMC Uniform Mechanical Code
UPC Uniform Plumbing Code
USDC U.S. Department of Commerce
UL Underwriters Laboratories
WCLIB West Coast Lumber Inspection Bureau
WIC Woodwork Institute of California
WQCB Water Quality Control Board (Regional)
WRCB Water Resources Control Board
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01020 - 1 Existing Conditions
SECTION 01020
EXISTING CONDITIONS
PART 1 - GENERAL
1.01 DESCRIPTION
This section generally includes maintenance, repair, rehabilitation, replacement, restoration, preservation, etc. of existing conditions.
1.02 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS A. Attention is directed to Part 4 Existing Improvements, Section 400 “Protection and Restoration” of the Standard Specifications and these Special Provisions.
B. Contractor agrees to assume sole and complete responsibility for protection of public and private property in the vicinity of the job site and further agrees to, at Contractor's expense, repair or replace to original condition all existing improvements within or in the vicinity of the job site which are not designated for removal and which are damaged or removed as a result of Contractor's operations.
C. Repair or replacement must be completed within three (3) working days from the date the damage occurred, unless immediate repair or replacement is determined to be necessary by the Engineer. If the Contractor fails to restore existing improvements in a timely manner, within the timeframe specified, the District may complete the work and costs will be deducted from payments due the Contractor.
D. Contractor must coordinate with operations such that damage to newly constructed improvements is avoided. In the event newly constructed improvements, shown on the Contract Documents, interfere with other project work or is necessary for safety or access and must be removed and replaced, the District will only pay for the improvements to be constructed one time. Multiple replacements or work necessary for the convenience of the Contractor will be considered performed at the Contractor’s expense.
E. Existing improvements, visible at the Work or which can be reasonably ascertained by available information to exist, and which interfere with the completion of the Work but which no specific disposition is made on the Plans or Specifications, shall be addressed by the Contractor as follows:
1. Existing improvements which interfere with the completion of the Work shall be removed and replaced, in kind. The exact location and alignment of the replacement shall be confirmed with the Engineer prior to removal and adjustments to the location to conform to the Work shall be made as necessary.
2. The Engineer may determine that the existing improvements are to be removed and not replaced. Removed improvements shall be properly disposed of by the Contractor.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01020 - 2 Existing Conditions
3. The area where existing improvements were removed shall be restored to conform with the Work and match the surrounding area. Restoration shall conform to adjacent improvements.
4. All costs for addressing proposed improvements in conjunction with existing improvements shall be included in the bid.
1.03 UTILITY REQUIREMENTS AND POTHOLING
A. GENERAL:
1. Attention is directed to Section 402 “Utilities” of the Standard Specifications (SSPWC), the contract Plans, and these Special Provisions. The Contractor must verify the location, size, and type of all existing utilities prior to construction. Utilities include, but are not limited to; telephone, electricity, gas, fiber-optic cable, cable television lines, traffic signal systems, communication systems, petroleum lines, water, irrigation systems, storm drains and sanitary sewer.
2. When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such work must be included in the Bid for the items of work necessitating such work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience are the Contractor’s responsibility and the Contractor must make all arrangements and bear all costs.
3. The Contractor must obtain all necessary permits and notify the utility agencies at least 48 hours in advance of excavating around any of their facilities. It is the responsibility of the Contractor to coordinate all phases of construction with the various utility companies involved.
4. The Contractor must notify Underground Service Alert at 811 at least 48 hours prior to any excavation or construction work. Paint indications for underground utilities must be limited to only those areas to be affected. The Contractor must document USA markings with photographs or video and must provide a copy of the photographs and video to the Engineer. The Contractor must remove any painting marks that remain after the construction is complete as follows:
5. When placing markings on the pavement or other right-of-way areas to indicate the location of underground facilities, Contractors and/or utility companies are required to use a temporary water-based marking chalk with a visibility life not to exceed three (3) weeks. Contractor must arrange for markings to be removed as needed. In the event that a Contractor or utility company uses a non-approved marking material, it will be the responsibility of the Contractor to ensure the complete removal of all pavement markings remaining upon completion of the permitted work. If the Contractor fails to properly and completely remove all pavement markings, the District may affect the removal and deduct from payments due or become due the Contractor for both direct and indirect costs as determined by the Engineer.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01020 - 3 Existing Conditions
B. UTILITY VERIFICATION:
1. The location and existence of utilities shown on the plans are approximate and taken from available records. Not all underground utilities are shown on the Plans. The Contractor must verify the location of existing utilities in coordination with District staff, by potholing or other suitable methods, and must take all precautions to protect them whether shown or not. The exact location and identification of all existing utilities must be determined by the Contractor prior to the start of any work.
2. The Contractor must physically locate, verifying horizontal and vertical locations, and map existing underground facilities within the work area that are marked by Underground Service Alert (USA), shown on the drawings or visible in the field. Contractor must protect all such facilities from damage due to construction activities for the duration of the project. In the event any such unknown facilities or substructures should be disturbed or damaged due to the failure of the Contractor’s exercising reasonable care, the Contractor must at once make necessary emergency repair at no cost to and to the approval of the owner. In the event the utility owner requires its own forces or approved vendors to perform such repairs, Contractor must coordinate and cooperate with the utility to complete the repairs. All costs for repairs, staff time, direct and indirect costs, and any costs billed by the utility must be borne by the Contractor and costs may be deducted from payments due or to become due the Contractor. Contractor is responsible for following all applicable rules and regulations concerning work in the vicinity of underground and/or overhead utilities.
3. All utilities designated on the Plans to be protected in place must be carefully uncovered if located within the lines of excavation and time must be allowed for the Engineer to field check the location of such utilities to make certain that they will not interfere with construction. In the event a utility conflict exists, the District will either arrange for utility owner to relocate the utility or adjust grade and/or alignment of the proposed improvement. Contractor must allow sufficient time for this utility work and must adjust Contractor’s operation to move to other areas to allow the utility relocation work to occur.
4. In the event any such facility should be disturbed or damaged, the Contractor must at once make repairs to the satisfaction of the owner, or arrange with the owner to make repairs, at no cost to the District. Any delays or reconstruction of improvements resulting from the Contractor’s failure to verify utility locations and depths will be made at the Contractor’s expense.
C. UTILITY COMPANY WORK REQUIREMENTS:
1. Where facilities are shown on the Plans, “To be Relocated by Others,” the District will issue the owner a “Notice to Relocate” or by District agreement with owner, require owner to relocate. Contractor must coordinate and schedule work with the various utilities. Contractor must be familiar with the utility company requirements, scheduling the work with adequate time in advance of needing utilities relocated, protected, installed or removed. In the event difficulties delay relocation, which in the judgment of the Engineer cannot reasonably be foreseen, and require a delay in Contractor’s completion date Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01020 - 4 Existing Conditions
after all reasonable remedies for keeping contract on schedule have been exhausted by Contractor including, but not limited to flow -charts and critical path scheduling, work simplification, and alternative construction methods, Engineer may allow extra time to the Contractor, but no additional compensation will be allowed.
2. The Contractor must protect facilities shown on the Plans, “To Be Relocated By Others,” in both original and relocated positions and any damage to such facilities must be immediately repaired to the owner’s satisfaction at no cost to the District.
D. PAYMENT:
1. The cost for coordination with the utility companies and district staff, providing work areas for utilities, locating facilities including potholing and measuring and recording utility depth/location in two directions from a known reference, protecting utility facilities in place, and conforming to the requirements of this section will be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed.
1.04 SUBSURFACE CONDITIONS
A. Where investigations of subsurface conditions have been made by the District with respect to subsurface conditions, utilities, foundation, or other structural designs, and that information is shown in the Plans, it represents only a statement by the District as to the character of materials and general location which have actually been encountered by the District’s investigation. This information is only included for the convenience of Bidders. Not all underground utilities are shown on the plans, and the Contractor shall coordinate with District staff to locate, and Contractor shall pothole as required to perform the work without conflicting utilities.
B. Investigations of subsurface conditions are made for the purpose of design only. The District assumes no responsibility with respect to the sufficiency or accuracy of borings or of the log of test borings or other preliminary investigations or of the inter pretation thereof. There is no guaranty, either expressed or implied, that the conditions indicated are representative of those existing throughout the Work, or any part of it, or that unanticipated conditions may not occur. When a log of test borings is included in the Plans, it is expressly understood and agreed that such log of test borings does not constitute a part of the Contract. The log of test borings represents only an opinion of the District as to the character of the materials to be encountered, and is included in the Plans only for the convenience of the Bidders. Making information available to Bidders is not to be construed in any way as a waiver of the provisions of the first paragraph of this Section, and Bidders must satisfy themselves through their own investigations as to conditions to be encountered.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 1 Stormwater Pollution Control Plan
SECTION 01030
STORMWATER POLLUTION CONTROL PLAN
PART 1 - GENERAL
A. The Contractor shall prepare and maintain a Stormwater Pollution Control Plan (SWPCP) on the form provided by the City, included in this specification, which describes in specific detail the Contractor’s program to prevent contamination of the stormwater collection system. Contractor shall implement, maintain, inspect and remove all erosion and sediment controls identified in the SWPCP. The program shall address both common construction activities and extraordinary events.
B. Contractor shall include water pollution control drawings (WPCD) in the SWPCP to illustrate the locations, applications and deployment of best management practices (BMPs) identified in the SWPCP. The WPCDs shall be included as an attachment to the SWPCP. Sample WPCDs can be obtained from the California Stormwater Quality Association (CASQA) Construction BMP Handbook. The SWPCP shall also comply with the Regional Los Angeles and Ventura Counties Municipal Separate Storm Sewer System (MS4) Permit (Order No. R4-2021-0105, Permit No.
CAS004004). A copy of the permit is available for review from the City of Camarillo Stormwater Program Manager; phone 805-383-5659.
C. The Contractor shall comply with laws, rules, and regulations of the State of California and agencies of the United States Government prohibiting the pollution of lakes, wetlands, streams, or river waters from the dumping of contaminates, refuse, rubbish or debris.
D. The Contractor shall submit three (3) copies of the SWPCP a minimum of 10 working days prior to beginning construction. Construction shall not begin until the SWPCP is approved. Contractor shall update the SWPCP as necessary during the work to prevent contamination of the stormwater collection system. At completion of construction, contractor shall provide City with site copy of the SWPCP, including all required inspection and training reports.
E. Before start of work, Contractor shall train all employees and subcontractors on the SWPCP and related WPCD and provide City with written documentation of said training.
F. Suggested BMPs can be obtained from the following sources:
1. Ventura County Municipal Separate Storm Sewer System Permit/Order 2010- 0108 and the Regional Los Angeles and Ventura Counties MS4 Permit/Order R4-2021-0105 available at Los Angeles Regional Water Quality Control Board web site at
http://www.swrcb.ca.gov/rwqcb4/water_issues/programs/stormwater/municipal /index.shtml
2. California Stormwater BMP Handbooks for Construction or Municipal Activities www.cabmphandbooks.com
3. Ventura Countywide Stormwater Quality Management Program www.vcstormwater.org.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 2 Stormwater Pollution Control Plan
4. Caltrans’ Stormwater Quality Handbooks
http://www.dot.ca.gov/hq/construc/stormwater/stormwater1.htm
CONSTRUCTION
A. The Contractor shall keep a copy of the SWPCP on the job site. The Contractor shall provide continuously at the jobsite all of the tools, equipment, and materials necessary to implement the SWPCP at all times from project initiation through completion, including any punchlist or warranty work on the project.
B. At a minimum the following requirements should be met as applicable, to the maximum extent practicable, at construction sites regardless of size:
1. Storm Drain System Protection – At the first order of work, the Contractor shall protect the existing storm drain system from entrance of construction debris and pollutants. Such protection shall include implementing the BMPs as outlined in the SWPCP. Protection shall prohibit the discharge of untreated runoff from temporary or permanent street maintenance/landscape maintenance material and waste storage areas from entering the storm drain system. Sediment that is generated on the project site shall be retained using structural drainage controls. In addition, the protection system shall have a minimum of three features: 1) a particulate filter of geosynthetic material securely fastened in place such that it cannot be bypassed without significant physical damage; 2) a prefilter for the particulate filter; and 3) on-hand materials to close off the inlet or opening in the case of a significant pollution spill. Contractor shall monitor and maintain all storm drain inlet protection devices during rain events to prevent flooding. All curb inlet BMP devices shall be fabricated “L” or “Z” shaped reusable type with high flow bypass and have gravel bags.
2. Material Management & Storage – No construction-related materials, wastes, spills or residues shall be discharged from the project site to streets, drainage facilities or adjacent properties by wind or runoff. All materials and/or equipment storage areas where liquid construction materials are placed shall be protected by a physical barrier capable of containing the entire volume of stored liquid materials. During active construction activities, portions of the barrier may be removed for access. However, the barrier materials must be readily accessible for replacement by onsite construction personnel. The barrier must be in place at all times during the absence of Contractor personnel at the storage site. Building materials should be placed on pallets and covered in event of rain. Do not store materials in the street or gutter area.
3. Equipment & Vehicle Maintenance – Non-stormwater runoff from equipment and vehicle washing and any other activity shall be contained at the project site and shall not be allowed to discharge from the project site to streets, drainage facilities or adjacent properties by wind or runoff. The Contractor shall inspect vehicles and equipment on each day of use. Leaks shall be repaired off-site if possible. If necessary to repair on site, the runoff must be contained, or the problem vehicle or equipment shall be removed from the project site until repaired. If necessary, drip pans should be placed under the vehicles or equipment while not in use to catch and/or contain drips and leaks.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 3 Stormwater Pollution Control Plan
4. Soil Erosion Control – Erosion from slopes and channels will be significantly reduced by implementing BMPs, including but not limited to, minimizing grading activities during the wet season, inspecting graded areas during rain events, planting and maintaining vegetation on slopes or other erosion controls such as hydraulic mulch, hydroseeding, soil binders, and straw mulch, or covering slopes susceptible to erosion with geotextiles and mats.
5. Spill Prevention & Cleanup Plan - Contractor shall have a spill prevention plan and spill cleanup materials readily available and addressed in the SWPCP. Spills shall be cleaned up immediately using dry methods if possible.
Spill cleanup material shall be properly disposed of. Refer to SC -11 Spill Prevention BMP from the California Stormwater BMP Handbook for Municipal Activities. Contractor shall keep a record of any spills in the inspection log. In addition, at the end of the project, the Contractor must certify that all contaminated materials have been properly disposed in accordance with the SWPCP.
6. Asphalt, Concrete, Road Reconstruction, Roadbed or Street Paving, Repaving, Patching, Digouts, or Resurfacing Roadbed Surfaces, & Related Activities – Contractor shall implement the following BMPs:
a. Restrict paving/repaving activity to exclude periods of rainfall or predicted rainfall unless required by emergency conditions.
b. Install gravel bags and filter fabric at all susceptible storm drain inlets and at manholes to prevent spills of paving products and tack coat. Filter fabric must be fabricated “L” or “Z” shaped reusable type with high flow bypass.
c. Prevent the discharge of release agents including soybean oil, other oils, or diesel to the storm drain system or receiving waters. d. Prevent non-stormwater runoff from water use for the roller and for evaporative cooling of the asphalt.
e. Clean equipment over absorbent pads, drip pans, plastic sheeting or other material to capture all spillage and dispose of properly. f. Collect liquid waste in a container, with a secure lid, for transport to a maintenance facility to be reused, recycled or disposed of properly. g. Collect solid waste by vacuuming or sweeping and securing in an appropriate container for transport to a maintenance facility to be reused, recycled, or disposed of properly.
h. Cover the cold mix, asphalt, materials (i.e., pre-mixed aggregate and asphalt binder) with protective sheeting during a rainstorm. i. Cover loads with tarp before haul-off to a storage site, and do not overload trucks.
j. Minimized airborne dust by using water spray during grinding. k. Avoid stockpiling soil, sand, sediment, asphalt material and asphalt grinding material or rubble in or near storm water drainage systems or receiving waters.
l. Protect stockpiles with a cover or sediment barriers during a rain event.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 4 Stormwater Pollution Control Plan
7. Sidewalk Washing – The following methods should be utilized to prevent discharge of sidewalk cleaning wastewater into the storm drain system:
a. Sweep and remove trash, debris, and free-standing oil/grease spills/leaks (use absorbent material if necessary) from all areas to be cleaned before using water.
b. Manually scrape gum from sidewalks and other surfaces. c. Must use high pressure, low volume spray using only potable water with no cleaning agents at an average usage of 0.006 gallons per square foot of surface area to be rinsed.
d. Use a wet/dry vacuum to collect wash water for disposal. Large volumes of wash water may require the use of a small sump pump to remove wash water from the job site.
e. One or more of the following methods are recommended to prevent pollutants from entering the storm drain system:
• Sandbags can be used to create a barrier around storm drains. * • Rubber mats or plugs can be used to seal drain openings. * • Temporary berms or containment pads help keep water on site. * • Use berms of sandbags to direct wash water to landscaping. * • Use large squeegees to accumulate sheet flow for collection. *Remember to remove plugs, berms, and sandbags or you may be liable for possible flooding.
f. Wash water that may contain hazardous waste such as oil -saturated absorbents, water with lead or other heavy metals from oxidized paint, and solvent cleaners requires special treatment and must be disposed of through a hazardous waste facility.
8. Employee BMP Training – Contractor shall train employees and subcontractors on BMP implementation, general good housekeeping, and proper spill containment and cleanup. Before start of work, Contractor shall provide City with written documentation of training and keep all documentation in the SWPCP.
9. Inspection – The Contractor shall inspect all pollution control BMPs per schedule below. Contractor shall forward electronic copies of inspection reports to City Stormwater Program Manager by the end of the week that inspection took place. The Contractor should also repair/replace any damaged BMP or clogged element on a daily basis. The Contractor shall keep a monitoring inspection log of each inspection in the SWPCP. Minimum inspection frequency:
a. Once per month during the non-rainy season (April 16 – September 30) b. Once per week during the rainy season (Oct. 1 – April 15) c. Before, during and after a major rain event, the area shall be inspected at a minimum twice per day, seven days per week, whether or not any work has been performed. The daily checks shall be between 6 and 9 am and 4 and 8 pm.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 5 Stormwater Pollution Control Plan
10. Dewatering – Avoid dewatering discharges where possible by using the water for dust control, infiltration, etc. If necessary to dewater, Contractor shall obtain a permit from the Los Angeles Regional Water Quality Control Board.
Contractor shall be responsible for all costs related to implementing the dewatering permit. For further instruction refer to the California Construction Handbook – BMP NS-2.
11. Removal of Accumulated Rainwater – The Contractor shall follow the City Camarillo Guidelines for Removal of Rainwater that has accumulated on the job site. The preferred method is to filter the rainwater into a water truck for use in dust control or irrigation. If it is necessary to remove rainwater from the site to the street, gutter or storm drainage system, Contractor shall use BMPs to insure that the water does not exceed 100 mg/l of Total Suspended Solids and no other construction waste is present in the water to be discharged before discharging to drainage facilities.
12. High Risk Sites - Hillside or Construction Discharging Directly to Sediment Impaired Waterbody – Contractor shall implement enhanced BMPs on sites located on hillsides (slopes that are 20 percent or greater) or that discharge directly to Conejo Creek, Calleguas Creek, or Revolon Slough/Beardsley Wash. For a list of enhanced BMPs see Table 9 in Part 4.F.4 in the Ventura County Municipal Stormwater Permit (Order No. 2010-0108) available at:
http://www.swrcb.ca.gov/rwqcb4/water_issues/programs/stormwater/municipal/i ndex.shtml. In addition to enhanced BMPs, these type of “high risk” sites must be inspected by a qualified SWPPP Practitioner or Developer (QSP or QSD) at least weekly during the wet season and once each 24 hour period during a storm event that generates runoff from the site to identify BMPs that need maintenance to operate effectively, that have failed or could fail to operate as intended.
PAYMENT
A. The Contractor shall be paid for work of preparing, implementing, inspecting, maintaining, and removing the SWPCP on a lump sum basis as enumerated in the Bid Schedule for the Stormwater Pollution Control Program. In addition, failure to perform and document the required daily inspections shall result in a daily liquidated damage of $250/calendar day. This liquidated damage shall be in addition to any other liquidated damage. The imposition of the penalty shall not relieve the Contractor of any obligations of these project requirements.
B. Payment for the work involved under the bid item for the Stormwater Pollution Control Program may be made on a partial payment system based on the completion of the following stages of work:
Work Description Payment
Develop Plan 10% of Bid Price
Initial Plan Implementation 10% of Bid Price
Inspection & Maintenance of SWPCP 70% of Bid Price (will be paid Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01030 - 6 Stormwater Pollution Control Plan
incrementally over the life of
the project)
Removal of BMPs at Completion 10% of Bid Price
C. Payment for the SWPCP shall include all the labor, materials, equipment, and incidentals for preparing, maintaining, and updating a SWPCP and complying with all provisions including maintenance and updating of BMPs throughout construction, as specified herein.
D. Fines and penalties from regulatory agencies levied against the City as a result of the Contractor’s work, including actions or inactions shall be the responsibility of the Contractor and may be deducted from payments due or to become due the Contractor.
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 1 Administrative Requirements
SECTION 01040
ADMINISTRATIVE REQUIREMENTS
PART 1 - GENERAL
1.01 DESCRIPTION
This section generally includes administrative and procedural requirements for the management and coordination of the Work, subcontractors, and other contractors and owners.
1.02 PRE-CONSTRUCTION JOB SITE VIDEO
A. A minimum of one week prior to start of construction, the Contractor shall video all areas where construction is to take place. Such videos (DVD or other approved media) must be provided to the Engineer before construction commences. These videos will serve as a record of the existing conditions for disputes arising from restoration and should therefore be taken along the line of construction and site access and staging areas at sufficient detail as necessary to clearly depict details of existing conditions.
1. Video must document existing conditions, roadway, facilities, chemical systems, District property, and all painted curb markings in the project area.
The Contractor must also video any unusual conditions encountered during construction that are not already a matter of photographic record.
2. The videos must be on standard flash drives viewable on a computer, taken in high quality color video 1080p HD (1920x1080p) minimum in MP4, AVCHD, MOV or h.264 format. All videos will become the property of the District.
3. All videos must be indexed and catalogued in such a manner that each photographed area is readily identifiable and must also indicate the date and time on which the video was made.
4. In the event damage to existing improvements occurs, the video will be available as a resource to determine existing conditions. In any areas where existing conditions cannot be determined by means of videos, the area must be restored as approved by the Engineer at Contractor’s expense.
1.03 PRE-CONSTRUCTION CONFERENCE
A. A pre-construction meeting will be conducted prior to commencement of construction at a time and place designated by the Engineer. Those attending the meeting must include, but not be limited to, the Contractor and superintendent who will be supervising the work for the duration of the project, the Owner, Design Engineer, Construction Manager, Engineer, and representatives of affected utility companies.
B. Pre-construction conference will not be scheduled until the following has been submitted:
1. Construction Schedule
2. Project Phasing Plan
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 2 Administrative Requirements
3. Storm Water Pollution Control Plan (SWPCP)
4. Engineer receives any submittals related to first items of work, and major components required have been procured and are in possession of the Contractor.
C. Engineer will record minutes of meeting and distribute copies to participants and interested parties.
D. Agenda shall include, but not be limited to, the following:
1. Adequacy of distribution of Contract Documents.
2. Distribution and discussion of list of major subcontractors and suppliers.
3. Proposed progress schedules and critical construction sequencing.
4. Major equipment deliveries and priorities.
5. Project coordination.
6. Designation of responsible personnel.
7. Procedures and processing of:
i. Field decisions.
ii. Proposal requests.
iii. Submittals.
iv. Change Orders.
v. Request for Information/Interpretations.
vi. Applications for Payment.
vii. Record Documents.
8. Use of premises:
i. Office, construction, and storage areas.
ii. District's requirements.
9. Construction facilities, controls, and construction aids.
10. Temporary utilities.
11. Safety and first aid procedures.
12. Security procedures.
13. Housekeeping procedures.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 3 Administrative Requirements
1.04 PROJECT SCHEDULE AND MEETINGS
A. Schedule Updates:
1. By Tuesday of each week, the Contractor must prepare and submit a detailed schedule of the work projected for the next two weeks on a daily basis. The Contractor must make revisions as required by the Engineer.
B. Weekly Project Status Meeting
1. The Engineer will schedule, prepare for, make arrangements for, and provide materials for the meeting.
2. M ust be attended by the District, Engineer, Operator, Contractor, Contractor’s Project Manager, superintendent, quality control manager, project scheduler, major subcontractors, and suppliers (as required).
3. The meeting will have duration of approximately one hour and will be held on the day, time, and location determined by Engineer.
4. The purpose of this meeting will be to discuss interfacing work, scheduling, problems, issues, and the like. If not previously submitted, the Contractor must submit the following to the Engineer at the beginning of the meeting:
i. Daily manpower and equipment utilization for the preceding week ii. Projected work for the next two weeks on a daily basis.
5. Agenda shall include, but not be limited to, the following:
i. Review minutes of previous meeting/minutes.
ii. Safety and security.
iii. Construction schedule summary.
iv. Review of 6 weeks look-ahead schedule.
v. Review of off-site fabrication and delivery schedules. vi. Review of submittals schedule and status of submittals. vii. Request for information (RFIs) status.
viii. MOPs/shutdown coordination.
ix. Change order management status.
x. Maintenance of quality standards (QA/QC).
xi. Field observations, problems, and conflicts.
xii. Commissioning and process start-up.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 4 Administrative Requirements
xiii. General Items.
xiv. Action items.
xv. Next meeting.
C. The Contractor must attend all miscellaneous meetings as requested by the Engineer.
1.05 CONSTRUCTION SCHEDULE
A. Attention is directed to Section 6-1.1 “Construction Schedule” of the Standard Specifications, Section 6.1 “Proposed Construction Schedule” of the General Conditions/Specifications and these Special Provisions.
B. The Contractor must update the Construction Schedule as specified in the Standard Specifications, the General Conditions/Specifications, or when directed by the Engineer. Preparation and updating of the Construction Schedule must be performed at Contractor's sole expense.
C. Failure by the Contractor to submit updated or revised Construction Schedules when required may prevent acceptance of progress payment requests by the Engineer until such updated or revised Construction Schedules have been submitted for review and have been accepted by the Engineer.
D. The Construction Schedule must include obtaining all necessary materials and equipment and must reflect completing all work within the specified time in accordance with these Specifications. Contractor must show completion of the project completely filling the Contract time and may not show early completion. In the event the Contractor requests early completion, Contractor must execute a no-cost Contract Change Order that reduces the number of Working Days allowed for completion to conform with such intended completion date.
E. Contractor must include in the schedule detailed information for each operation. When the project includes multiple areas or job sites, Contractor must include detailed information for each site. When notifications, parking restrictions, shutdowns, or District support are required, such dates must be included in the schedule.
F. Contractor must provide critical path schedules in legible hardcopy format and must also submit schedules with each update in electronic format compatible with MS Project or Primavera, as directed by the Engineer.
G. Full compensation for the required construction schedules and conforming to the requirements of this section will be considered as included in the contract prices paid for the various items of work involved and no additional compensation will be allowed.
1.06 DAILY REPORT
A. The Contractor must complete a Daily Report indicating manpower, major equipment used and on standby (itemized separately), subcontractors, materials used and similar items involved in the performance of the Work. The Daily Report must be completed on forms prepared by the Contractor and acceptable to the Engineer, and must be submitted to the Engineer prior to construction on the subsequent workday.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 5 Administrative Requirements
B. Contractor must supply daily reports to the inspector at the start of work on a daily basis. If the Contractor fails to provide daily reports for 2 or more working days during the scheduled work week, then a Stop Work Notice will be issued and progress payments will not be processed until all paperwork is current. Contract period will continue to be in force while the Stop Work Notice is in effect.
1.07 COORDINATION WITH CONCURRENT PROJECTS
A. Several projects may be ongoing within the limits of the work during the Contract period. The Contractor is required to coordinate the work with other contractors and District staff such that all projects and operations can be diligently pursued to their timely completion. Interfacing work must be shown on the project schedule, and the Contractor will be responsible for meeting that schedule. Contractor must include time for others to perform work within the Work Area and this must be reflected in the Project Schedule. Delays due to interfacing with concurrent projects are considered avoidable and no compensation will be made therefore such delays. Contractor must include in the bid all costs for coordination, scheduling, meetings, staging and the like that result from interfacing with concurrent work.
B. Contractor is responsible for obtaining contract documents including plans and specifications and thoroughly understanding the requirements of and Work called for in the contract documents for the concurrent projects. The Contractor must include in the bid all costs for Work called for or indicated in Contract Documents for this project even though shown in the contract documents prepared for concurrent projects.
C. Concurrent projects include but are not limited to the following:
1. P ump Station No. 5 Improvements – Camarillo Sanitary District
2. Pleasant Valley Road Bike Lanes – City of Camarillo
3. Pleasant Valley Road Sewer Force Main – Camarillo Sanitary District
4. Frontier work – Contact Jason Eisel – (805) 233-1472, [email protected]
5. SoCalGas work – Contact Phil Wright – (818) 700-3618, [email protected] PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01040 - 6 Administrative Requirements
THIS PAGE INTENTIONALLY BLANK
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01190 - 1 Seismic Requirements
SECTION 01190
SEISMIC REQUIREMENTS
PART 1 - GENERAL
1.01 SUMMARY
A. This Section is applicable to the following secondary structural system elements, non-structural components, and/or equipment supported by structures.
1. Mechanical, electrical, and plumbing equipment and appurtenances and their associated anchorage, including, but not limited to:
1.02 GENERATORS, MTS, AND MOUNTING RACK REFERENCES
A. American Society of Civil Engineers Standard ASCE 7-16, Minimum Design Loads and Associated Criteria for Buildings and Other Structures B. California Building Code (CBC), 2022 Edition.
1.03 GENERAL DESIGN REQUIREMENTS
A. The Contractor and Specialty Engineer are responsible for producing structural designs that resist applicable loads including Dead, Live, Wind, Seismic, Fluid, Snow, Rain, Earth, operational, or other special loads applicable to the component being designed.
B. Minimum design loads shall be based on guidelines given in this Section, the Drawings, ASCE 7-16, CBC, equipment manufacturer's recommendations and/or other industry accepted design standard for the component being designed (i.e.
AWWA D100, API 650, ANSI MH16.1).
1.04 SEISMIC DESIGN REQUIREMENTS
A. The Contractor is responsible for producing designs that resist the total seismic forces in accordance with the seismic design criteria. The Contractor is responsible for coordinating between the Engineer of Record and the Specialty Engineer. The Contractor is responsible to coordinate the favorably reviewed design in the field, and shall provide the proposed design, including any modifications required to the primary structure, at no additional cost to the Owner.
B. The seismic design for non-structural components and equipment anchorage shall be in accordance with the CBC, and the required coefficients and factors for determining the total design seismic forces are shown on the Drawings.
1. Components Coefficient:
Element or Equipment Non-Structural Components and Equipment ap Rp Generator Electrical Equipment 1.0 2.5
C. Design anchorages of all elements of structures, nonstructural components, and equipment supported by structures, to resist static and dynamic operational loads, plus total seismic loads specified in the CBC, ASCE 7-16, and as follows:
1. For anchorage uplift, multiply dead load by 0.9 and subtract 0.2SDS if used to reduce vertical seismic effects.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01190 - 2 Seismic Requirements
2. Post-installed anchors installed in concrete shall be prequalified for seismic application in accordance with ACI 355.2.
D. Design Basis and Coordination: Contractor shall note that the layout of the structure and equipment pads is based on the first named manufacturer and model for the equipment to be anchored.
1. Contractor shall coordinate all attachments and related work and shall provide connections as noted in the favorably reviewed shop drawings.
2. For all suppliers, if the dimensions required by the Contractor's submitted anchorage calculations deviate from those provided on the Contract Drawings, Contractor shall note the deviation in the submittal for review and provide the favorably reviewed pad at no additional cost to the Owner.
3. If a model or manufacturer other than the first name supplier is submitted for use by the Contractor, Contractor shall coordinate all related work and deviations from the Contract Drawings.
4. Where Contractor's specialty engineer proposes a deviation from the contract drawings for any manufacturer, and that deviation is favorably reviewed by the Engineer, Contractor shall provide that modification to the structure at no additional cost.
1.05 SUBMITTALS
A. Submit in accordance with Section 01300
B. Shop Drawings for non-building structures and contractor designed components:
Submit signed and sealed structural calculations and detailed drawings for the following listed elements and where required in Divisions 2 through 17 of the primary structural system and their attachments, the secondary structural system and their attachments, permanent non-structural components and their attachments, and the attachments and anchorage for permanent equipment supported by the structure:
C. Seismic Certification of Equipment.
1. Certification is required for the following elements or components:
a. List items in accordance with note to specifier above b. Any components or equipment where the component importance factor Ip is designated as greater than 1.0.
2. Certification may consist of one of the following methods:
a. Project-specific component design and documentation determined to be acceptable by the Engineer and the authority having jurisdiction. b. Written certification from the manufacturer that the equipment is capable of resisting the internal seismic loads due to the loading conditions noted herein and meeting the requirements based on one of the following:
1) Analysis, where ASCE 7-16, Section 13.2.2 allows, or 2) Testing meeting ASCE 7-16 Section 13.2.5, or
3) Experience Data meeting ASCE 7-16, Section 13.2.6.
3. Level 2 Certification shall consist of a written certification from the manufacturer, and accompanying test results or experiential evidence, indicating compliance with ASCE 7-16, Section 13.2.2.
4. For elements designed using Chapter 15 of ASCE 7-16, Contractor shall submit complete calculations for the element or non-building structure in lieu of seismic certification.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01190 - 3 Seismic Requirements
D. Shop Drawings for Anchorage Calculations: Where required in the equipment specifications in Divisions 2 through 17 or listed below, submit signed and sealed structural calculations and detailed drawings from the Contractor's Specialty Engineer.
1. Required anchorage items include:
a. Generators for Pump Station 3 and Pump Station 5
b. Mounting Rack for Pump Station 3 and Pump Station 5
c. MTS for Pump Station 3 and 5.
E. Structural calculations and detailed drawings shall be prepared by the Contractor's Specialty Engineer.
F. Structural calculations and detailed drawings shall clearly show the total design seismic forces which will be transferred from the elements of the structural system, non-structural components, and/or equipment and their attachments to the primary structure. Calculations must be reviewed by Engineer of Record for general conformance with the design criteria and building code and therefore calculations shall include:
1. Seismic and wind load criteria used to determine design lateral and uplift forces. For external equipment, a statement should be made as to whether wind controls for all equipment.
2. Derivation of forces used, including at least one complete sample calculation, showing the process used so that Engineer of Record may determine general compliance. Printouts of spreadsheets without explanation of calculations used to determine values are not acceptable.
3. Adequacy of anchorage to concrete to transfer the design forces from the element.
4. Detail drawings shall note:
a. Required concrete strength,
b. Anchor type, dimensions, and materials. See Section 05090, c. Edge distance, spacing, embedment depth, substrate thickness and any supplementary reinforcing required for anchors installed in concrete. d. Required dimensions of equipment pads based on equipment size and edge distance. The Contractor shall coordinate dimensions of equipment pads, including any revisions required to meet the requirements of the favorably reviewed submittal by the Specialty Engineer at no additional cost to the Owner.
G. The Engineer of Record's review of items within a Specification Section cannot be completed until all related items have been coordinated and submitted for review.
H. Quality Assurance Submittals
1. Test Reports: Submit test reports for tension testing of anchors.
2. Verification of installation: Submit a letter from the Contractor's Specialty Engineer verifying that the installation was performed as required by the Specialty Engineer's calculations.
1.06 QUALITY ASSURANCE
A. Qualifications: The Contractor is responsible for submitting signed and sealed structural calculations and detailed drawings from a Specialty Structural or Civil Engineer licensed in the State where the project is being built.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01190 - 4 Seismic Requirements
B. Regulatory Requirements: Comply with the jurisdictional State's adopted and amended versions of the CBC, the referenced sections of ASCE 7 plus clarifications and additions specified in this Section.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
PART 4 - FIELD QUALITY CONTROL
A. Site Tests: Tension testing of expansion or adhesive anchors utilized for anchorage shall be done in the presence of the Owner's Representative and a report of the test results shall be submitted. See Specification Section 05090 for additional requirements.
B. Inspection: Special Inspection shall be provided for high strength bolting or bolts installed in concrete. See Specification Section 05090 for additional requirements.
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 1 Measurement and Payment
SECTION 01200
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01 MEASUREMENT – GENERAL
A. Measurement will be in accordance with Standard Specification unless otherwise specified.
Bid Item List Abbreviations
Abbreviation Meaning
CF cubic foot
CY cubic yard
EA each
(F) final pay item
GAL gallon
HR hour
LB pound
LF linear foot
LS lump sum
SF square foot
SY square yard
TN 2,000 pounds
B. When an item of work is designated as (F) in the bid schedule, then the item shall be a final pay item for payment purposes only. For a final pay item, payment shall be based on the quantity shown in the bid schedule for that item, regardless of the actual quantity used, unless the item quantity is changed by the Engineer.
C. Work under this contract will be paid on a lump-sum basis as outlined on the Bid Schedule for the quantity of work installed. The lump-sum prices include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work involved to complete the work included in the contract documents.
D. The application for payment will be for a specific item based on the percentage completed or quantity installed. The percentage complete will be based on the value of the partially completed work relative to the value of the item when entirely completed and ready for service.
E. The bids for the work are intended to establish a total cost for the work in its entirety.
Should the Contractor feel that the cost for the work has not been established by specific items in the Bid Schedule, include the cost for that work in some related bid item so that the Proposal for the project reflects the total cost for completing the work in its entirety.
1.02 LUMP SUM BID ITEMS
The Contractor must submit a detailed Schedule of Values breakdown for all lump sum bid items. The breakdown of items must be submitted to the Engineer for approval and Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 2 Measurement and Payment
the level of detail will be as determined appropriate by the Engineer. The Schedule of Values must be submitted to the Engineer prior to the first progress payment request and the progress payment will not be reviewed without approved Schedule of Values for all Lump Sum bid items. The Schedule of Values will be used as a basis for determining appropriate monthly progress payment amounts for lump sum bid items.
The Schedule of Values must equal, in total, the lump sum bid item cost and be in such form and sufficiently detailed to satisfy the Engineer that it correctly represents a reasonable apportionment of the lump sum.
1.03 WORK NOT LISTED IN THE SCHEDULE OF WORK ITEMS
A. The General Provisions and items in the Special Provisions, general requirements, and specifications which are not listed in the schedule of work items of the Bid Schedule are, in general, applicable to more than one listed work item, and no separate work item is provided therefor. Include the cost of work not listed but necessary to complete the project designated in the contract documents in the various listed work items of the Bid Schedule.
B. The bids for the work are intended to establish a total cost for the work in its entirety.
Should the Contractor feel that the cost for the work has not been established by specific items in the Bid Schedule, include the cost for that work in some related bid item so that the Proposal for the project reflects the total cost for completing the work in its entirety.
C. Work called for on the Plans or required by the Contract Documents, but for which no bid item exists is considered included in the prices paid for the various items of work and no separate payment will be made.
1.04 CHANGES IN WORK
A. Attention is directed to Section 2-6 “Changes Requested by the Contractor,” Section 2-7 “Changes Initiated by the Agency,” and Section 2-8 “Extra Work” of the Standard Specifications and these Special Provisions.
B. The District will issue a Contract Change Order (CCO) if a change to the Total Contract Price or Contract Time is necessary. The Contractor will not be entitled to any adjustments in either Contract Time or Total Contract Price for changes performed without written direction from the District. Adjustments in Contract Time or Total Contract Price for changes performed will not be made until a Contract Change Order is approved. The labor rates paid for time and material work will not be higher than the applicable prevailing wage rate for the worker classifications required for the work.
The Contractor shall prepare a time impact justification for consideration for any adjustments in Contract Time. The time impact justification accepted by the District will be used to adjust the Contract Time in the CCO.
C. If the Contractor requests an extension of time as a part of a contract change order, Contractor must provide a revised construction schedule and written justification for the extension of time, at the time of Contractor’s request for the change order. The justification must include an analysis for the time requested, showing how the change affects the critical path/controlling item of work and must be provided to the Engineer Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 3 Measurement and Payment
in editable electronic format compatible with MS Project, in addition to a legible hardcopy.
D. The sections that follow replace sections of like number in the Standard Specifications for Public Works Construction (SSPWC).
3-2.2.2 Increases of More Than 25 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 25 percent, payment for the quantity in excess of 125 percent of the Bid quantity will be made on the basis of a decrease in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or in the event mutual agreement cannot be reached, on the basis of Extra Work per 2-8 or at the Contract Unit Price at the Agency’s option.
The Extra Work per 2- 8, basis of payment, does not include fixed costs. Fixed costs will be deemed to have been recovered by the Contractor through payment for 125% of the Bid quantity at the Contract Unit Price.
3-2.2.3 Decreases of More Than 25 Percent. The District, at its sole discretion, may decrease the quantities of the items of work to be completed under this contract. In such an event, payment will be made based upon the decrease in quantity at the Contract Unit Price, except for Major Bid Items as described below.
A Major Bid Item is defined as a single Contract item constituting 10% or more of the original Contract Price. In the case of a decrease in a Major Bid Item, the following will apply:
Should the actual quantity of an item of work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less than 75 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per 2-8; however in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 75 percent of the Bid quantity at the Contract Unit Price.
1.05 EXTRA WORK
A. Subsection 7-4.2.1, Labor rates used for Extra Work shall be at applicable prevailing wage rates plus allowable markups per this section.
B. Subsection 7-4.3, “Markup” of the Standard Specifications (SSPWC) is deleted in its entirety and replaced by the following:
7-4.3. Markup.
a) Work by Contractor. When extra work is to be paid for on a force account basis, use the CALTRANS Equipment Rental Rate Book for equipment rental rates. The following percentages will be added to the Contractor’s costs and will constitute the markup for all overhead and profits:
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 4 Measurement and Payment
i. Labor………………………………….35
ii. Materials……………………………...15
iii. Equipment Rentals…………………. 15
The markup percentages above will reimburse the Contractor for all additional costs, and no other additional payment will be made by reason of performance of the extra work.
b) Work by Subcontractor. When extra work to be paid for on a force account or lump sum basis is performed by a subcontractor, the markup established above in 7-4.3 “Work by Contractor” will be applied to the subcontractor’s actual cost of such work.
An additional markup of ten (10) percent of the subcontracted portion of the extra work may be added by the Contractor. The markup will constitute the markup for all overhead and profit for the Contractor on extra work done by the subcontractor, and no other additional payment will be made.
c) Equipment Rental rates will be determined using CALTRANS Labor Surcharge and Equipment Rental Rates in effect at the time the work is performed.
d) The labor rates paid by the District for (time and material) Force Account work will be at the applicable prevailing wage rate for the worker classifications required for the work plus applicable mark-ups described in this section.
1.06 DESCRIPTION OF BID ITEMS
A. Bid Item No. 1 – Mobilization:
1. Measurement:
a. Mobilization shall include all mobilization for the work included in the Base Bid per the requirements of the Contract Documents and described in Sections 01010 and 01040. The lump sum price for mobilization will be considered full compensation for the furnishing of all materials and for all labor, equipment, tools, and incidentals necessary to complete the item. Mobilization shall include compensation for mobilizing equipment, tools, materials, and other items to allow construction to proceed.
2. Payment:
a. Furnish data and documentation to substantiate the amounts claimed under this Bid Schedule item. Payment as required by the Contract Documents shall be at the percentage lump sum of completed Work on this Bid Schedule item and shall include all labor, tools, materials, and equipment to construct the facilities and provisions complete and in place. Payment for this item includes all work mentioned in Bid Item No. 1 - Mobilization in this Section 01200 and Specification Section 01505.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 5 Measurement and Payment
A. Bid Item No. 2 – Stormwater Pollution Control Plan Implementation:
1. Measurement:
a) Furnish all labor, materials, equipment, and services necessary to develop and implement best management practices (BMPs) and mitigation requirements documented in the Stormwater Pollution Control Plan (SWPCP) and Specification Section 01030.
2. Payment:
a) Furnish data and documentation to substantiate the amounts claimed under this Bid Schedule item. Payment as required by the Contract Documents shall be at the percentage lump sum as outlined in Section 01030 and shall include all labor, tools, materials, and equipment to construct the facilities and provisions complete and in place. Payment for this item includes all work mentioned in Bid Item No. 2 - Stormwater Pollution Control Plan Implementation in this Section 01 200 and Specification Section 01030.
B. Bid Item No. 3 – Demolition
1. Measurement:
a) Demolition shall include all abandonment, demolition, and disposal of civil, mechanical, electrical, instrumentation, and structural project components, including but not limited to generators, fuel storage systems, concrete pads, and other electrical equipment as described in Specification Section 02050 and elsewhere in the Contract Documents.
2. Payment:
a) This work shall be bid and paid as a lump sum.
C. Bid Item No. 4 – Site Work:
1. Measurement:
a) Site work shall include furnishing, repairing, and installing all work described in Division 2 of the Technical Specifications including but not limited to earthwork, trenching, site restoration, and new bollards.
2. Payment:
a) This work shall be bid and paid as a lump sum.
D. Bid Item No. 5 – Concrete:
1. Measurement:
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 6 Measurement and Payment
a) Concrete shall include furnishing and installing all work described in Division 3 of the Technical Specifications including but not limited to the installation of the new concrete pads,
2. Payment:
a) This work shall be bid and paid as a lump sum.
E. Bid Item No. 6 – Electrical and Instrumentation:
1. Measurement:
a) Electrical and instrumentation shall include furnishing and installation of all electrical components, instrumentation, and appurtenances as well as testing and startup. Refer to Bid Item 4 for electrical conduit trenching.
2. Payment:
a) This work shall be bid and paid as a lump sum.
F. Bid Item No. 7 – Temporary Bypass Pumps:
1. Measurement:
a) Temporary bypass pumps shall include furnishing and installation of all components required to run the temporary bypass pumps.
2. Payment:
a) This work shall be bid and paid as a lump sum.
G. Bid Item No. 8 – New Generator/ATS/MTS Installation:
1. Measurement:
a) New generator, ATS, and MTS installation shall include installation of the two new generators, ATSs, and MTSs, as well as testing and startup.
2. Payment:
a) This work shall be bid and paid as a lump sum.
H. Bid Item No. 9 – All Other Work Required in Base Bid Scope of Work:
1. Measurement:
a) This bid item is for providing all work called for on the Drawings and in the Specifications, excluding work covered by the other bid items described herein, to be paid at the Contract lump sum price bid therefore in the Bid Schedule, complete and in place in accordance with Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 7 Measurement and Payment
Contract Documents. The lump sum price shall include full compensation for furnishing all labor, tools, equipment, materials, and incidentals and doing all work required to complete the project.
2. Payment:
a) This work shall be bid and paid as a lump sum.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01200 - 8 Measurement and Payment
THIS PAGE INTENTIONALLY BLANK
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01300 - 1 Submittals
SECTION 01300
SUBMITTALS
PART 1 - GENERAL
1.01 DESCRIPTION
This section generally describes the administrative and procedural requirements for processing submittals during the construction phase.
1.02 SUBMITTALS
A. In addition to the required submittals and shop drawings of the Standard and Technical Specifications, the Contractor must submit the following shop drawings and/or submittals in adequate detail, including a list of all deviations from the Contract Documents for each item submitted. The following items marked (*) shall be submitted to the Engineer for review at least five (5) working days prior to the Pre-construction Meeting. All other submittals must be submitted in accordance with the submittal procedures listed below. The Engineer will determine if the specifications are being met for all work including but not limited to the following:
B. GENERAL REQUIREMENTS
1. Key Personnel, Telephone Numbers, and Emergency Telephone Numbers *
2. Project Schedule *
3. Project Phasing Plan *
4. Schedule of Values *
5. Demolition Waste Recycle Plan/Statement
6. Storm Water Pollution Plan (SWPCP) *
7. Preconstruction video *
8. Long Lead Item Schedule *
C. EQUIPMENT
1. Construction Equipment
2. Manufacturer Certifications and Testing Reports
3. Product and Material Specifications
D. SITE WORK
1. Emergency Response and Access Plan *
2. Log of Work-Related Injuries and Illnesses *
3. Job Hazard Analysis *
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01300 - 2 Submittals
E. CONCRETE
1. Portland Cement Concrete Mixes
2. Asphalt Concrete Mixes
3. Cement Masonry components
F. MECHANICAL
1. Pipe, Fittings, Valves, and Appurtenances
2. Pumps, Motors, Meters, and Tanks *
3. Containment Coatings *
4. Contractor must provide all submittals required by Special Provision sections.
G. ELECTRICAL
1. Conduit, Fittings, and Appurtenances
H. Contractor must provide all submittals required by Special Provision sections.
1.03 SUBMITTAL PROCEDURES
A. Where possible, the Contractor shall submit electronically in PDF format compatible with Adobe Acrobat. Files less than 5 MB in size may be submitted to the Owner’s Representative via email. Files larger than 5 MB shall be submitted by means of an FTP server, USB flash drive, external hard drive, or other method approved by Owner’s Representative. Scans shall be at a resolution necessary for legibility and shall be in color when necessary for clarity. Wherever called for in the Contract Documents or where required by the Engineer, the Contractor must furnish to the Engineer for review four (4) physical copies of each submittal.
B. Make submittals promptly in such a sequence as to cause no delay in the work.
Schedule submissions a minimum of twenty (20) working days before reviewed and approved submittals will be needed.
C. Each submittal item must be individually numbered, logged, and must identify the specification section that relates to item being submitted so that approved and rejected submittals can be tracked.
D. Each submittal shall have a transmittal form including the date, project name, project number, submittal number, submittal revision, and submittal content.
1. Each submittal shall be assigned a unique number and numbered sequentially.
Resubmittals shall bear an alphanumeric system denoting the subsequent resubmittal of the original.
2. Every page in a submittal shall be numbered in sequence and shall be collated.
3. Where product data from a manufacturer is submitted, clearly mark which model is proposed with all pertinent data, capacities, dimensions, clearances, Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01300 - 3 Submittals
diagrams, controls, connections, anchorage, and supports. Present a sufficient level of details for assessment of compliance with the contract documents.
Extraneous information should not be included in submittals.
4. Disorganized submittals that do not meet all requirements will be returned without review.
E. At the time of each submission, give Engineer specific written notice of each variation that the submittal may have from the requirements of the Contract Documents. If a variation is identified that was not brought to the attention of the Engineer, correc tion will be at the Contractor’s expense.
F. The Engineer will have a minimum of two weeks to review each submittal, except where specified differently in these special provisions. It is the responsibility of the Contractor to organize submittals in order of importance and need. Resubmittals of submittals will be reviewed and returned in the same review period as for the original submittal. It is considered reasonable that the Contractor shall make a complete and acceptable submittal by the second submission of a submittal item. The Owner’s Representative reserves the right to withhold monies due the Contractor to cover costs of any review beyond the second submittal.
G. Only one submittal will be reviewed for an item and Contractor may not submit multiple shop drawings from multiple vendors for the same item.
H. Engineer’s review will be only for conformance with the design concept of the project and for compliance with the information given in the Contract Documents, not extending to means, methods, techniques, sequences, or procedures of construction (except where indicated or required by the Contract Documents) nor to safety precautions or programs incident thereto. Submittals processed by Engineer do not become Contract Documents and are not Change Orders.
I. Delays caused by the need for re-submittal or replace unaccepted “or equal” items will not constitute a basis for claim.
J. No substitutions will be considered for products determined to be a sole source as noted in the Notice Inviting Bids. For all else, the following applies:
1. In the event that an item is called for by a specific product or trade name, Contractor will have five (5) days after the bid opening for submission of data substantiating a request for a substitution of “an equal” item. In the event Contractor furnishes any “or equal” material more expensive than that specified in the bid form, the difference in cost of such material so furnished will be borne by Contractor under Public Contract Code section 3400.
2. “Or equal” products may be accepted by the Engineer upon submittal of the following information:
i. Product Date Design Criteria
ii. Physical Properties Limitations of Process
iii. Material Specifications List of Previous Projects
iv. Installation Specifications Size of Completed Projects Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01300 - 4 Submittals
v. Testing Methods List of Current Projects
vi. Third Party Test Data
vii. Size of Current Projects
viii. References (All references must include current names and telephone numbers).
ix. List of all deviations from the specifications or referenced product or materials.
x. Additional testing may be required, and all costs for testing will be borne by Contractor.
K. District reserves the right to modify the procedures and requirements for submittals, as necessary to accomplish the specific purpose of each submittal. Direct inquiries regarding the procedure, purpose, or extent of any submittal to the Engineer.
L. Repetitive Review
1. Shop drawings and other submittals will be reviewed no more than twice at the District’s expense. All subsequent reviews will be performed at times convenient to the Engineer and at the Contractor’s expense, including but not limited to consultant costs, staff charges, overhead, and other related expenses. Contractor shall reimburse the District for such costs, and District may deduct these costs from amounts due or to become due the Contractor.
Submittals are required until approved.
2. Any need for more than one resubmission, or any other delay in obtaining Engineer’s review of submittals, will not entitle Contractor to extension of the Contract Time.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01500 - 1 Construction Facilities and Temporary
Controls
SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PART 1 - GENERAL
1.01 TEMPORARY UTILITIES
A. Sanitary Facilities: Provide and maintain self-contained portable sanitary facilities for the Contractor's, subcontractor's, Engineer's, and Owner's use. Facilities shall comply with applicable regulations and shall be serviced, cleaned and disinfected frequently.
B. Temporary Water, Power and Telephone Service: Provide all temporary utility services required for the project. Note that there is no on-site water available for use. Pay all utility service connection and use charges. Provide separate temporary telephone and internet services for the Contractor's and Engineer's field offices. The Contractor shall pay for these services.
C. Temporary Lighting: Provide and maintain lighting for construction operations to achieve a minimum lighting level of 20 foot-candles for rough work and 60 foot- candles for finish work.
D. Temporary Fire Protection:
1. Provide and maintain fire protection equipment, including extinguishers, fire hoses, and other equipment required by law or insurance carriers, or as necessary for proper fire protection during the course of the work.
2. Use fire protection equipment only for fighting fires.
3. Locate fire extinguishers in field offices, storage sheds, tool houses, temporary buildings, and throughout the construction site.
1.02 TEMPORARY CONSTRUCTION
A. The Contractor is solely and exclusively responsible for the design, construction and maintenance of all temporary construction including forms, falsework, shoring, scaffolding, stairs, ladders and all other similar items. See Section 5-7 of the SSPWC and Section 01040.
B. Construct adequate and safe forms and falsework to rigidly support partially completed structures. Provide temporary bridges and decking to maintain vehicular and pedestrian access. Design and construct temporary forms, falsework, bridges and decking in accordance with applicable regulations and codes.
1.03 BARRICADES, FENCES AND ENCLOSURES
A. See Section 5-7 of the SSPWC and Section 01040.
B. Barricades: Provide temporary guardrails, ladders, stairs, guards, and barricades to protect persons in accordance with applicable regulations.
C. Fences:
1. Existing fences/walls enclose the present facilities site. The fences are for the protection and security of the present operating facilities. If it is necessary for the Contractor to remove some of the fences for installation of new work, the Contractor shall provide equivalent temporary protection and security.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01500 - 2 Construction Facilities and Temporary
Controls
Replace fencing removed by the Contractor with new fencing of equivalent quality prior to completion of the project.
D. Enclosures:
1. Provide protective dust covering at doors and other openings to contain dust within the construction area.
2. Provide temporary partitions to prevent dust and moisture from entering Owner-occupied areas and to prevent damage to existing materials and equipment. Temporary partitions shall be of non-combustible construction such as metal studs and gypsum board.
3. Provide temporary watertight closures for openings in exterior surfaces as required to protect interiors from weather, moisture, humidity and extreme temperature.
1.04 PROTECTION OF INSTALLED WORK
A. Provide temporary and removable protection for installed products. Control activity in immediate work area to minimize damage.
B. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by covering surfaces with non-staining heavy-duty reinforced moisture-resistant Kraft building paper with joints continuously taped with waterproof tape or ½ inch-thick CDX plywood with all joints continuously taped with 2-inch-wide duct tape.
C. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is unavoidable, provide adequate protection to prevent damage to waterproof membranes and comply with recommendations for protection of the waterproofing or roofing material manufacturer.
D. Provide heavy planking to protect curbs, gutters, culverts, paving and similar surfaces from damage by heavy equipment or vehicles.
1.05 SECURITY
A. Provide security and facilities to protect the Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.
1.06 ACCESS ROADS AND PARKING AREAS
A. Access Roads: Use only access roads designated on the Drawings.
B. Parking:
1. Utilize the staging areas highlighted on the plans for any necessary parking.
Coordinate with Owner if additional parking is required.
1.07 TEMPORARY CONTROLS
A. Cleaning:
1. During Construction: Maintain the site and all work in a clean orderly fashion free of waste debris and rubbish. Store debris in covered containers. Pick up and remove debris daily if required, but not less frequently than weekly.
Burning debris on site is not permitted. Remove debris from permanently closed spaces prior to enclosing them. Clean mud from vehicles before leaving the site.
2. If work under this Contract creates dusty, dirty or unsightly conditions in adjacent areas, the Contractor shall immediately cleanup the affected areas.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01500 - 3 Construction Facilities and Temporary
Controls
3. Final cleanup is specified in Section 01700.
B. Dust Control: Employ measures to prevent the creation of dust which may produce damage or nuisance to property or persons. Be responsible for all damage resulting from dust produced by construction operations. Periodically wet down unpaved areas where vehicles are operated. See Division 2 Earthwork specification sections.
C. Erosion and Sediment Control: Employ measures to prevent erosion and trap any sediment created by construction operations before it leaves the site. Prevent sediment from entering streams or other water bodies.
D. Noise Control: Comply with regulations limiting construction noise levels. Use whisper quite air compressors. Use jack hammers with exhaust mufflers. Prevent noise disturbance to the public and adjacent property owners.
E. Pest and Rodent Control: Avoid creating conditions conducive to pests and rodents. Comply with regulations governing the use of chemicals to control pests and rodents.
F. Water Control: Maintain excavations free of water. Protect site from puddling or running water. See Division 2 Earthwork specification sections.
1.08 PROTECTION OF TREES
A. Do not attach ropes, cables, guys or braces to trees.
B. Do not trim any trees without the Engineer's authorization.
1.09 TRAFFIC REGULATION
A. Conduct operations so as to offer the least possible obstruction and inconvenience to public traffic. Do not overload or damage paved or improved surfaces, sidewalks, curbs or gutters.
B. Provide temporary barricades, lights, flag persons and other means to safely control pedestrian and vehicular traffic entering and leaving the project site and on the project site.
1.10 FIELD OFFICES
A. Contractor's Office at the Site: Maintain a suitable office at the site for the Contractor's Superintendent who shall be authorized to receive submittals, drawings, instructions, or other communications from the Engineer or the Owner.
PART 2 - PART 2 - PRODUCTS (NOT USED)
PART 3 - PART 3 - EXECUTION (NOT USED)
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01500 - 4 Construction Facilities and Temporary
Controls
THIS PAGE INTENTIONALLY BLANK
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01505 - 1 Mobilization Demobilization
SECTION 01505
MOBILIZATION / DEMOBILIZATION
PART 1 – GENERAL
1.1 DESCRIPTION
A. Mobilization/Demobilization shall include the obtaining of all permits, licenses, bonds, and insurance; moving on to the site of all plant and equipment; furnishing and erecting temporary facilities, and their removal; all as required for the proper performance and completion of the work. Mobilization/Demobilization shall include, but not be limited to, the following principal items:
1. Moving on to the site of all Contractor’s materials and equipment required for operations.
2. Installation of work area fencing.
3. Preparation and processing of shop drawings.
4. Developing and maintaining construction water supply , electrical power and telephone service to the site throughout the duration of construction.
5. Provid ing and maintaining sanitation facilities throughout the duration of construction.
6. Providing and maintaining a field office for the Contractor.
7. Erection of Contractor’s onsite work and storage yard
8. Arranging for and securing Contractor’s offsite work and storage yard.
9. Providing public convenience, safety, and traffic control, including warning signs, high level warning devices, delineators, regulatory signs, barricades and bridged trench plates
10. Obtaining and maintaining all required permits, insurances and bonds.
11. Posting all OSHA required notices and establishment of safety programs.
12. Having the Contractor’s superintendent at the job site full time, at all times when the construction is in progress.
13. Field verifies by potholing the locations, dimensions, and elevation of all existing utilities, conduits, and structures that may interfere with the current work, including the utilities/conduits this project’s work will connect to; and prepare a Report of Findings four (4) weeks prior to construction to allow revisions to the current design.
14. Providing shop drawings, samples, project data and record drawings (As-Builts).
15. Providing construction schedule including monthly updates.
16. Providing three-week look -ahead schedules at the weekly construction progress review meetings.
17. Maintaining the site in a clean, safe and orderly condition.
18. Demobilization and cleanup.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01505 - 2 Mobilization Demobilization
19. Photographic and video documentation of the site and access conditions prior to the start of and at the completion of construction.
PART 2 – NOT USED
PART 3 – EXECUTION
A. All temporary utilities shall be applied for and installed in a timely manner so as not to impact the construction schedule.
1. The temporary water source shall be protected from cross contamination by a reduced pressure backflow device; this device shall be certified on site, in place.
2. The Contractor shall provide sufficient electric lighting so that all work may be properly conducted when there is not adequate daylight in the work area.
3. The Contractor shall have the option of providing dedicated jobsite cellular telephone service during the execution of the work. All costs for cellular telephone service supplied to the jobsite during the completion of the work shall be borne by the Contractor.
B. All temporary utilities shall be removed, and patchwork (if necessary) completed in a timely manner so as not to impact the construction schedule.
PART 4 – PAYMENT
A. Payment for Mobilization and Demobilization” will be made at the contract lump sum price bid under Bid Item “Mobilization/Demobilization”. This price will be considered full compensation for the furnishing of all materials and for all labor, tools, equipment, tools, and incidentals necessary to complete the item.
B. A 25% of the lump sum will be paid with the first progress payment and the remaining 75% will be paid incrementally over the life of the Contract where these subsequent payments will be made based on the percentage of work completed to date.
END OF SECTION
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01650 - 1 Facility Commissioning, Testing,
and Startup
SECTION 01650
FACILITY COMMISSIONING, TESTING, AND STARTUP
PART 1 - GENERAL
1.01 EQUIPMENT AND FACILITY STARTUP
A. Commission all systems and equipment to verify performance, function, and correct operation by performing procedures to activate, startup, adjust, test, and demonstrate that the work is in operating order in accordance with the general requirements of this Section and the detailed requirements of the technical sections under the system or equipment specified. To ensure that the work is ready for full-time operation, the procedures shall include verification, balancing, calibration, witness testing, documentation, inspection by equipment manufacturers and operator training where specified.
B. Notification: Notify the Engineer five (5) days prior to starting each system or piece of equipment.
C. C oordination: During the startup period, coordinate the operation of the facility or equipment with Engineer, subcontractors, Owner's operators, and manufacturer's representatives. Provide regular updates of construction schedule and startup activities to the Owner's PLC/SCADA Programmer (Owner's Programmer).
D. Furnish test equipment, measuring devices, and supplies required to conduct tests.
E. Maintain the equipment until acceptance. Provide all lubricants, chemicals, and electricity necessary until acceptance.
F. Furnish all expendable supplies, gas, water, etc., required for startup, demonstration, and testing, and dispose of all waste or used supplies, water, etc.
G. Favorably reviewed Operations and Maintenance (O&M) Manuals are required twenty (20) days before the startup of new equipment/facilities.
1.02 SUBMITTALS
A. Startup Plan, Forms, and Schedule: Prepare a facility startup plan and schedule.
The plan shall include test methods and procedures and sample forms for recording commission, test, and startup data. The plan and schedule shall include time for testing and debugging of the PLC control logic and HMI interface for each system. The amount of time necessary shall be coordinated with and approved by the Engineer and the Owner's Programmer.
B. Provide Affidavits as described in paragraph 1.04 B.
C. Submit documentation of tests, balancing reports, and the like.
1.03 INITIAL STARTUP AND OPERATION OF FACILITIES
A. The following listing is a general sequence of startup activity steps to be used in placing facility systems into operation:
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01650 - 2 Facility Commissioning, Testing,
and Startup
1. Perform initial lubrication of equipment and have manufacturers check and adjust equipment. Provide all subsequent lubrication and maintenance, and such staff as required for test operation until the Owner assumes equipment maintenance responsibility after Step 15 below.
2. Perform satisfactory testing of electrical work required prior to energizing of the electrical system.
3. After completion of Step 2, perform satisfactory electrical testing required after energizing of the electrical system.
4. Complete calibration of instruments.
5. Satisfactorily complete system verification of instrumentation work.
6. After completion of Steps 1 and 3, perform a rotational test of equipment and correct backward rotating drives.
7. After completion of Steps 5 and 6, test operate the equipment by manually initiating the operation. Where manual operation bypasses alarm or safety monitoring, provide continuous supervision of such parameters. Perform this step using water in lieu of chemicals or other process liquids. Use dry air or nitrogen in lieu of hazardous gases. Following testing with water, chemical lines shall be drained and be fully dried, in accordance with the specifications, prior to introduction of chemical.
8. Concurrent with Step 7, perform instrumentation and control testing and adjustments as related to the equipment being tested. Then allow time in the construction schedule for the Owner's Programmer to debug and test the PLC control logic and HMI interface. Provide personnel to assist in operation of equipment and adjustments of this system debugging and testing. All SCADA controls, interlocks, alarms, etc. including signals from other parts of the facility shall be tested. Provide simulation of inputs if needed during this step. Note: SCADA operational testing requires an approved test plan.
9. Concurrent with Step 7 and where possible at this stage of startup, complete the performance testing specified for the equipment.
10. Concurrent with Step 7, perform adjustments of the electrical work as related to the equipment being tested.
11. Repeat Steps 1 through 10 as required for other equipment items and plant systems until all plant process components and utility systems are ready for total plant and new system(s) operation. It may be necessary for the Contractor to put portions of the newly constructed facility in service before constructing other portions of the facility or completing the Work as a whole.
12. Submit the required documentation of testing, calibration, and equipment affidavits.
13. Notify the Owner and the Engineer 45 days before total plant and new system(s) operation is to occur so that the Owner may order chemicals and make other arrangements for full-time operation. This notification shall have an accuracy of plus or minus seven (7) days. Notify the Owner and Engineer again, exactly seven (7) days before total plant operation is to begin.
14. Submit any remaining documentation of testing, balancing reports, equipment affidavits, and the like commissioning before acceptance.
1.04 MANUFACTURER'S FIELD SERVICE AND AFFIDAVITS
A. Field Service: Where specified, manufacturers of equipment shall provide field service. Field service shall be provided by an authorized factory-trained and
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01650 - 3 Facility Commissioning, Testing,
and Startup
qualified manufacturer's representative for the specific equipment. Equipment shall not be considered ready for full-time operation until after the manufacturer's representative has checked and adjusted the equipment, and certified by written affidavit that the equipment has been properly installed, tested, adjusted, lubricated, and calibrated, and is ready for full-time operation.
B. Affidavits: Acceptable affidavits shall be submitted prior to completion of the work.
1. Affidavits shall contain the following specific wording:
"The generator/ATS/MTS has been properly installed, tested, adjusted, lubricated, and calibrated, and is ready for full-time operation. The installation has been inspected and has been found to be in conformance with our (the manufacturer's) standards and requirements."
2. Except for insertion of the equipment name, no amplification, dilution, or modification of this specific wording will be permitted.
1.05 TRAINING
A. Submit Operation and Maintenance Manuals and Parts Lists specified in Section 01300 at least fifteen (15) days prior to the first training session.
B. Demonstrate the operation, maintenance and safety procedures for all systems and equipment to personnel designated by the Owner.
C. In addition to overall training specified above, provide special demonstration and training for specific pieces of equipment specified in the Technical Specification Sections.
D. A total of two (2) different training sessions shall be provided for District staff.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
A. Equipment reference forms attached to this Section are not specific to any piece of equipment or facility to be installed as a part of this project. The examples are provided as a means of illustrating the level of detail required for the preparation of commission, testing and startup forms for this project. Reference Division 16 Electrical and Division 17 Instrumentation for additional commissioning, testing, and startup requirements.
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01650 - 4 Facility Commissioning, Testing,
and Startup
REFERENCE FORMS
Title
Equipment Test Report Form
Operation and Maintenance Transmittal
Equipment Record Form
Manufacturer’s Installation Certification
Spare Parts / Extra Stock Chain of Custody Form
Job No. 2344245*00
© 2025 Kennedy/Jenks Consultants
01650 - 5 Facility Commissioning, Testing,
and Startup
EQUIPMENT TEST REPORT FORM:
CITY OF SAMPLE
PROJECT NAME HERE
EQUIPMENT TEST REPORT
Equipment Name:
Equipment Number:
Specification Ref:
Location:
Manufacturer Owner Representative
Verified Date Verified Date
PREOPERATIONAL CHECKLIST
Mechanical
Lubrication
Alignment
Anchor bolts
Seal water system operational
Equipment rotates freely
Safety guards
Valves operational
Related systems operational
O&M manual information complete
Electrical (circuit ring-out and high-pot tests)
Circuits:
Power to MCC ??
Control to HOA
Indicators at MCC:
Red (running)
Green (power)
Amber (auto)
Indicators at local control panel
Wiring labels complete
Nameplates:
MCC
Control station
Control panel