PURPOSE: The Project Milestone Schedule is a tool to help you know when you need to meet CMO program milestones and to think about the timing and sequence of the project milestones your project needs to have in place to have your project be successful. This template will be included in your voucher agreement and will help to track progress towards your project plan. Your project milestone schedule can be modified and updated over the voucher agreement term.
INSTRUCTIONS: To complete your Project Milestone Schedule, fill out the template below. Items marked RED are requirements, and items color-coded BLUE are for you to modify:
1. Mark the milestone number (Column A), description of the milestone to achieve (Column B), and the month number (Column C) in which you plan to achieve the milestone over the 5-year voucher agreement term, starting with Voucher Execution (0 month). Please leave Calendar Date (Column D) blank. You can insert actual calendar dates (Column D) after your voucher has been executed.
2. Add in milestones and details for your project that are other additional steps critical to achieving launch within 15 months from project kick-off meeting.
3. Add/modify rows to this template, as appropriate, based on your project plan. At a minimum, you may use this template as your project milestone schedule, but you are encouraged to modify this template to suit your project.
4. Include work start dates as individual milestones for sub-contractors and other partners.
NOTE 1: Key CMO Program Requirements with deadlines are already in the template ; you may meet these deadlines sooner than listed, but no later than those listed in order for you to meet the project launch deadline of within 1 year of voucher execution.
NOTE 2: Quarterly status reporting and payment reimbursements templates will be distributed to awardees at a later date, and are intended as opportunities to reflect the progress made on each of the project milestones.
DEADLINE: Submit your completed Project Milestone Schedule to: [email protected] in Word or Excel Format PRIOR TO VOUCHER EXECUTION in order to include in your voucher agreement.
Costa Mesa
PROJECT MILESTONE SCHEDULE
OVER 5-YEAR MOBILITY PROJECT VOUCHER TERM
A.
MILESTONE
NUMBER
B.
DESCRIPTION OF MILESTONE TO BE ACHIEVED
C.
MONTH
NUMBER
ACHIEVED
D.
CALENDAR DATE
[ADD AFTER
VOUCHER
EXECUTION]
Voucher Agreement Execution – COMPLIANCE
1 Voucher agreement executed. 0 months [Input AFTER Voucher executed]
241
CMO PROJECT MILESTONE SCHEDULE
2 Project Kick-Off Meeting: Project must be
deemed insurance compliant by the Program
Administrator.
60 days
(Program
Requirement)
[Input AFTER Voucher
executed]
3 Secure contract with a Mobility Provider.
Provider: Circuit
Provide proof of contract to the Program
Administrator that a mobility provider is secured
and under contract.
3 months
(Program
Requirement)
[Input AFTER Voucher
executed]
1st Funding Year - PLANNING ([Kick-off meeting date] - 15 months) (Launch is required by 15th month)
4 Acquire all planned CMO-funded vehicles and
submit for reimbursement.
15 months
(Program
Requirement)
[Input AFTER Voucher
executed]
5 Complete final installation of all planned CMO-
funded infrastructure and submit for
reimbursement.
15 months
(Program
Requirement)
[Input AFTER Voucher
executed]
6 Soft-launchLaunch mobility service. Intended
users of the service start using the service (if
services have not already been launched).
15 months
(Program
Requirement)
[Input AFTER Voucher
executed]
7 ImplementDevelop and implement Launch
Marketing Plan, including official launch with
launch event.
3-4 months
8 Institute regular schedule of project team
meetings and community engagement
0-4 months
2nd Funding Year - OPERATION YEAR 1
9 Continue operating mobility service in
compliance with CMO T&Cs.
15 -24 months
(Program
Requirement)
[Input AFTER Voucher
executed]
10 Service kick-off with launch event [deleted] 4 months 11 Community Outreach & Engagement (ongoing) 0-24 months 12 Sell and execute third party advertising
campaigns on vehicles (ongoing)
0-24 months
13 Explore additional funding to sustain or expand 4-24 months 242
CMO PROJECT MILESTONE SCHEDULE
program
3rd Funding Year - OPERATION YEAR 2
14 Continue operating mobility service in
compliance with CMO T&Cs
25 -36 months
(Program
Requirement)
[Input AFTER Voucher
executed]
15 Community Outreach & Engagement (ongoing) 25-36 months 16 Sell and execute third party advertising
campaigns on vehicles (ongoing)
25-36 months
17 Explore and/or secure additional funding to
sustain or expand program
25-36 months
4th Voucher Year - OPERATION YEAR 3
18 Continue operating mobility service in
compliance with CMO T&Cs.
37 -48 months
(Program
Requirement)
[Input AFTER Voucher
executed]
19 Sell and execute third party advertising
campaigns on vehicles (ongoing)
37-48 months [Input AFTER Voucher
executed]
20 Community Outreach & Engagement (ongoing) 37-48 months [Input AFTER Voucher executed]
21 Explore and/or secure additional funding to
sustain or expand program
37-48 months
5th Voucher Year (Only CMO Admin Funding) - OPERATION YEAR 4 22 Continue operating mobility service in
compliance with CMO T&Cs.
49 -60 months
(Program
Requirement)
[Input AFTER Voucher
executed]
23 Sell and execute third party advertising
campaigns on vehicles (ongoing)
49-60 months
24 Community Outreach & Engagement (ongoing) 49-60 months [Input AFTER Voucher executed]
25 [Add additional rows as needed.] [deleted] 49-60 months [Input AFTER Voucher executed]
243
CMO PROJECT MILESTONE SCHEDULE
2526 Voucher Agreement Term Ends. 60 months [Input AFTER Voucher executed]
244
1. List of CBOs or community groups
Category 1: RelaƟonships with project-relevant community groups or CBOs The City of Costa Mesa has relaƟonships with project-relevant community groups and CBOs, including but not limited to the AcƟve TransportaƟon CommiƩee, Travel Costa Mesa, the Costa Mesa FoundaƟon, and the Costa Mesa Alliance for BeƩer Streets (CMABS).
2. Task descripƟon / duty statements
Category 3: Project-related labor costs (up to 1 year prior to voucher applicaƟon submission date) City of Costa Mesa staff Ɵme for planning and outreach has been ongoing since January 2023, parƟcularly Jennifer Rosales (TransportaƟon Services Manager, City of Costa Mesa) and BreƩ Atencio Thomas (AcƟve TransportaƟon Coordinator), who have been involved in the Community TransportaƟon Needs Assessment as well as planning the project and coordinaƟng with other City administrators and elected officials.
3. Task descripƟon / duty statements
Category 4: Project-related labor costs during Voucher Funding Term that are not paid through voucher funds
City staff will provide in-kind services throughout the project providing partnership development, planning, outreach, markeƟng, and program management. City staff will also serve as a liaison between the target populaƟon and Circuit for educaƟonal outreach events and leverage exisƟng programs to promote the project.
4. LeƩer of commitment
Category 5: Project-related materials or assets
City staff will provide materials or assets for outreach and educaƟon, including web plaƞorms and newsleƩers.
245
5. Category 7: Energy or fuel costs during the Voucher Funding Term (electricity or hydrogen) and Is the city supplying this?
Category 8: Donated or acquired land for infrastructure or parking spaces City will provide 3 parking spots where the EVs will be stored and charged. City will also provide the electricity. (InstallaƟon of charging infrastructure is budgeted separately.)
[ADDITIONAL]
Category 1: RelaƟonships with project-relevant community groups or CBOs The Costa Mesa Chamber of Commerce has relaƟonships with project-relevant community groups, local businesses, and CBOs. Their engaged consƟtuents will be important partners for educaƟon and outreach as the project progresses.
DocumentaƟon of Community Resource ContribuƟons is included in the aƩached leƩers of support and commitment.
246
Annual Budget
Breakdown for
Year 4 of
Service
Operation
(Administrative
Expenses Only)
(c)
Voucher amount
requested per
unit or hour
($)
(d)
Number of units
or hours
requested
(e)
Total voucher
amount by item
($)
(f)
Project Launch
(Up to 15
Months)
($)
(g)
Year 1 of
Service
Operation
($)
(h)
Year 2 of
Service
Operation
($)
(i)
Year 3 of
Service
Operation
($)
(j)
Year 4 of
Service
Operation
($)
City of Costa Mesa Staff Time $40.00 356 $14,230 $2,035 $4,065 $4,065 $4,065 0 0
0 0
0 0
0 0
CMEA Attendance $775/year 2 yrs $1,550 $775 $775
CMEA Travel $725/year 2 yrs $1,450 $725 $725
0 0
0 0
0 0
0 0
0 0
(a)
Expense Category and
Sub-Category
Voucher Administration
Planning
Outreach and Marketing
Operations and Maintenance
Voucher Administration
Planning Costs
Motor Vehicles and Associated
Hardware
Bicycles and Scooters
Direct Labor (Fringe Benefits & Indirect Costs included) Travel/Mileage
Outreach and Marketing
Operations and Maintenance
Equipment/Capital Costs (LEAD Only)
Mobility Provider Voucher Budget Worksheet
Instructions: Use this budget worksheet to specify items needed for individual expense categories. Enter data in blue cells. Do not enter data in grey or white cells. Add rows as necessary. The entire sheet is "unlocked" and it is the applicant's responsibility to ensure that subtotals and calculations are accurate. Voucher amounts and category totals must comply with allowable voucher amounts in the Implementation Manual. For any contributed resource contributions to meet the 5-year Voucher Agreement Term, indicate monetary assets under "Community Resource Contributions". It is recommended that applicants additionally complete the optional "Category Eligibility Check Worksheet" in the table below to ensure that they meet eligibility requirements for categories that have minimum and maximum requirements. Please note that administrative activities can be reimbursed during the last year of your voucher agreement (Year 4 of Service Operation), this includes insurance compliance, activities associated with payment request submissions, data reporting, printing, record retention, and mailing.
Section 1: Project Components Section 2: Voucher Budget (b)
Item description
Description of Voucher Request Annual Budget Breakdown Up to Year 3 of Service Operation Period
247
Electrical Installation $10,000 1 $10,000 $10,000
0 0
0 0
Additional Transportation
Enhancements (Maximum 25% of
total voucher)
0 0
0 0
0 0
0 0
Marketing $2,754 3 years $8,263 $2,163 $2,600 $2,000 $1,500 0 Vehicle Lease $72,225 3 years $216,676 $70,800 $72,216 $73,660 Driver Hours $25.38 32,448 hours $823,660 $269,135 $274,517 $280,008 Contractor Services $104,665.67 3 years $313,997 $102,600 $104,652 $106,745 0 0
0 0
0 0
0 0
Insurance $36,725 3 years $110,174 $36,000 $36,720 $37,454 0 $1,500,000.00 $14,198.00 $486,700.00 $495,670.00 $503,432.00 $0.00 Operations and Maintenance
Grand Total
Grand Total - Voucher Funding Term (Voucher Funds)
Grand Total - Other Funds Budget (Non-CMO Funds)
Other (LEAD Only)
Voucher Administration
Planning
Capital Acquisition
Outreach and Marketing
Voucher Administration
Planning
Capital Acquisition
Outreach and Marketing
Operations and Maintenance
Subcontractor
Charging/Fueling Equipment and
Installation
Bicycle/Scooter Infrastructure and
Installation (Maximum 300% of
amount of electric bicycle/scooter or
200% of non-electric bicycles/scooter
amount)
Operations and Maintenance
Community Resource Contributions
Resource contributions are assets contributed to the project to support long-term sustainability to meet the 5-year Voucher Agreement Term that includes a minimum of 4 years of service operation and beyond.
Resource contributions are not eligible for payment through voucher funding. Instructions: Add in-kind monetary resource contribution assets. 248
Cost Category Category Total Applicable
Denominator Percentage
Bicycle/Scooter Infrastructure and
Installation
Additional Transportation
Enhancements
Maximum of 300% of amount of electric bicycle/scooter vehicles or 200% of amount of non-electric bicycle/scooter vehicles amount Notes:
Optional: Category Eligibility Check Worksheet
Instructions: Calculate sums in "Category Total" and "Applicable Denominator" Columns. User may need to adjust example formula if additional rows were manually inserted above.
Eligibility Requirement Summary
(See Implementation Manual for Details) Conforms to Eligibility Requirement? Maximum of 25% of total voucher amount
249
250
Circuit Transit, Inc.
www.ridecircuit.com
CALSTART
Attn: Clean Mobility Options
48 So. Chester Avenue
Pasadena, CA 91106
Re: Clean Mobility Options Phase 2 Application, Costa Mesa On behalf of Circuit Transit Inc, we would like to express our commitment to serving as the Mobility Operator and Sub-Applicant for a neighborhood electric vehicle NEV
shuttle program led by the City of Costa Mesa in the California Air Resource Board’s Clean Mobility Options Voucher Pilot Program CMO . This CMO project will increase access to clean mobility options in disadvantaged communities, reduce greenhouse gas emissions GHG and criteria pollutants, increase the uptake of zero-emission vehicles, and improve air quality and public health in the State’s most vulnerable communities. The City of Costa Mesa will lead this program with our support in efforts to create cleaner, greener, more thriving communities.
Circuit is an all-electric shuttle service provider focusing on the first/last mile gap. From its beginning in 2011, Circuit has grown to more than 200 all-electric vehicles and 400
W2 employee drivers nationally. Circuit has nearby operations in San Diego, Orange County, and Los Angeles, including previous CMO programs like the Chula Vista Community Shuttle. Circuit provides all electric solutions that help move people in small areas and bridge gaps between riders and existing transit hubs. Circuit’s goal is to reduce congestion and its harmful effects on the environment and our quality of life. We do this by getting people out of their cars for short trips, encouraging visitors to park once, and by making connections to existing mass transit hubs. We work with innovative cities, private developers and forward-thinking advertising partners to offer electric shuttles that make mobility easier, smarter, safer, more affordable, and fun.
Circuit is partnering with Costa Mesa to provide an on-demand community shuttle service. Circuit is an experienced mobility operator with over 11 years of experience operating similar services. If funded through the CMO Voucher program, Circuit is prepared to play the following role:
● Operating and maintaining an all-electric community shuttle service ● Supporting marketing and outreach efforts and participating in community outreach events
● Providing monthly data reporting on community shuttle service performance Furthermore, Circuit will further make available its existing marketing and promotional materials to help promote the service and educate riders about using the service. 251
We are excited about the opportunity to work with the outstanding team to deliver a program that improves access to clean mobility. We greatly appreciate your consideration in reviewing this commitment letter that will contribute to the State’s ambitious climate change goals. If you have any questions, feel free to contact Daniel Kramer directly at :
[email protected] or 562