1 Agenda
City Council Regular Meeting
Folsom City Hall | City Council Chambers, First Floor
50 Natoma Street, Folsom, CA 95630
May 26, 2026, 6:30 PM

Welcome to Your City Council Meeting
We welcome your interest and involvement in the city’s legislative process. This agenda includes information about topics coming before the City Council and the action recommended by city staff. You can read about each topic in the staff reports, which are available on the city website and in the Office of the City Clerk. The City Clerk is also available to answer any questions you have about City Council meeting procedures.

Participation
If you would like to provide comments to the City Council, please:
 Fill out a blue speaker request form, located at the back table.  Submit the form to the City Clerk before the item begins.  When it’s your turn, the City Clerk will call your name and invite you to the podium.  Speakers generally have three minutes, unless the presiding officer (usually the mayor) changes that time.

Reasonable Accommodations
In compliance with the Americans with Disabilities Act, if you are a person with a disability and you need a disability-related modification or accommodation to participate in this meeting, please contact the City Clerk’s Office at (916) 461-6035, (916) 355-7328 (fax) or [email protected]. Requests must be made as early as possible and at least two full business days before the start of the meeting.

How to Watch
The City of Folsom provides three ways to watch a City Council meeting:

In Person Online On TV

City Council meetings take place at
City Hall, 50 Natoma Street
Watch the livestream and replay past
meetings on the city website,
www.folsom.ca.us
Watch live and replays of meetings on
Sac Metro Cable TV, Channel 14

More information about City Council meetings is available at the end of this agenda

Page 1 ends

2 City Council Regular Meeting

Folsom City Hall | City Council Chambers, First Floor
50 Natoma Street, Folsom, CA 95630
www.folsom.ca.us
Tuesday, May 26, 2026 6:30 PM

Justin Raithel, Mayor

Sarah Aquino, Councilmember Barbara Leary, Councilmember Mike Kozlowski, Councilmember Anna Rohrbough, Vice Mayor

AGENDA

CALL TO ORDER
ROLL CALL: Councilmembers: Rohrbough, Aquino, Kozlowski, Leary, Raithel The City Council has adopted a policy that no new item will begin after 10:30 p.m. Therefore, if you are here for an item that has not been heard by 10:30 p.m., you may leave, as the item will be continued to a future Council meeting.

PLEDGE OF ALLEGIANCE

AGENDA UPDATE
BUSINESS FROM THE FLOOR:

Members of the public are entitled to address the City Council concerning any item within the Folsom City Council's subject matter jurisdiction. Public comments are generally limited to no more than three minutes. Except for certain specific exceptions, the City Council is prohibited from discussing or taking action on any item not appearing on the posted agenda.

CONSENT CALENDAR:

Items appearing on the Consent Calendar are considered routine and may be approved by one motion.

Councilmembers may pull an item for discussion.

1. Approval of the April 28, 2026 City Council Special and Regular Meeting Minutes

2. Resolution No. 11614- A Resolution Authorizing the City Manager to Execute Amendment No. 4 to the Agreement (Contract No. 173-21 14-092) with Water Works Engineers, LLC for $49,823 from the Water Operating Fund (Fund 520) for Fixed Network and Water Consumption Database As-Needed Support

Page 2 ends

3 3. Resolution No. 11615 – A Resolution Authorizing the City Manager to Execute an Agreement with Electric Vehicle Conversions, LLC in the Amount of $240,400.56 from the Solid Waste Operating Fund (Fund 540) for the Purchase of an Electric Flatbed Vehicle and Apply for Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project (HVIP) Funding

4. Resolution No. 11616 -A Resolution Authorizing the City Manager to Execute an Agreement with Waterproofing Associates, Inc. for $103,247 from the Water Operating Fund (Fund 520) for the Water Treatment Plant Roof Restoration Project

5. Resolution No. 11617 – A Resolution Authorizing the City Manager to Execute up to Three One- Year Extensions to the Agreement with the County of Sacramento for a Not to Exceed Annual Cost of $50,000 from the Solid Waste Operating Fund (Fund 540) for Household Hazardous Waste Collection Program Services to Folsom Residents at Sacramento County Owned Facilities

6. Resolution No. 11618 – A Resolution Authorizing the City Manager to Execute up to Two One- Year Extensions to the Agreement with the County of Sacramento for an Estimated Annual Cost of $2.6 million from the Solid Waste Operating Fund (Fund 540) for Reduced Tipping Fees for Municipal Solid Waste Disposal at Kiefer Landfill

7. Resolution No. 11619 - A Resolution Amending Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small-Scale Water Use Efficiency Program Grant

8. Resolution No. 11621 – A Resolution Authorizing the City Manager to Execute an Amendment to the Agreement (Contract No. 173-21 21-068) with Genuine Parts Company dba Napa Auto Parts for an Annual Cost of up to $1,032,600 for Vendor Managed Inventory Services in the Fleet Division, 1300 Leidesdorff Street, from all Department Funds as Required for Vehicle Maintenance and Repairs

9. Resolution No. 11623- A Resolution Authorizing the City Manager to Execute an Agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for Design, Engineering Services During Construction, and Construction Management and Inspection for the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703) and Appropriation of Funds

10. Resolution No. 11624 - A Resolution Authorizing the City Manager to Execute Non-Exclusive Agreements for On-Call Engineering, Construction Inspection, and Surveying Services up to Appropriated and Available Project Specific Budgets with 4LEAF, Inc., BKF Engineers, Boswell & Associates, REY Engineers, Inc., and Unico Engineering

11. Benevento Family Park:
i. Resolution No. 11631 – A Resolution Authorizing the City Manager to Execute a Contract Amendment (Contract No. 173-2123-027) with Helix Environmental for Benevento Family Park Environmental Consulting Services in the Amount of $42,250 from the Park Improvements Fund (412) for a New Total Contract Amount Not-To-Exceed $120,500 ii. Resolution No. 11632 – A Resolution Authorizing the City Manager to Execute a Contract Amendment (Contract No. 173-2120-045) with Wilson Design Studios for Benevento Family Park and Prospector Park Design Services in the Amount of $277,980 from the Park Improvements Fund (Fund 412) and $2,463 from the Folsom Plan Area Specific Plan Capital Fund (Fund 472) for a New Total Contract Amount Not-To-Exceed $1,167,980

Page 3 ends

4 PUBLIC HEARING:

12. Presentation by Staff in Compliance with Assembly Bill 2561/Government Code Section 3502.3 Regarding City Vacancies, Recruitment and Retention Efforts

13. City of Folsom Community Facilities District No. 24 (Alder Creek West) i. Resolution No. 11625- A Resolution of the City Council of the City of Folsom to Form a Community Facilities District, to Designate Improvement Areas within the District, to Designate a Future Annexation Area therein and to Levy Special Taxes therein ii. Resolution No. 11626- A Resolution of the City Council of the City of Folsom Deeming it Necessary to Incur Bonded Indebtedness in and for City of Folsom Community Facilities District No. 24 (Alder Creek West)
iii. Resolution No. 11627 - A Resolution of the City Council of the City of Folsom Calling Special Mailed-Ballot Election in the City of Folsom Community Facilities District No. 24 (Alder Creek West)
iv. Resolution No. 11628 – A Resolution of the City Council of the City of Folsom Declaring Election Results in the City of Folsom Community Facilities District No. 24 (Alder Creek West) v. Ordinance No. 1370 – An Uncodified Ordinance Levying Special Taxes for the Fiscal Year 2026-27 and Following Fiscal Years Solely within and Relating to the City of Folsom Community Facilities District No. 24 (Alder Creek West) (Introduction and First Reading) OLD BUSINESS:

14. Resolution No. 11622 - A Resolution Authorizing the City Manager to Execute an Amendment to the Agreement with the Folsom Tourism Bureau Relative to the Folsom Tourism Business Improvement District (Contract No. 173-21 12-053) AND Appointing Two City Council Members to Serve on the Folsom TBID Capital Improvement Committee

15. Consideration of Potential Ballot Measure(s) Amending the City Charter and/or the Folsom Municipal Code for the 2026 General Municipal Election and Direction to Staff NEW BUSINESS:

16. Resolution No. 11620 - A Resolution Approving the Master Development Plan for Jackrabbit Hill Park

17. Resolution No. 11629– A Resolution Authorizing the City Manager to Execute a Consultant and Professional Services Agreement with Griffin Structures, Inc. for the Corporation Yard Site Planning and Environmental Assessment in the Amount of $335,000 from the Corporation Yard Capital Fund (Fund 459) for the New Corporation Yard Project and Appropriation of Funds

18. Resolution No. 11630 - A Resolution Adopting a List of Projects for Fiscal Year 2026-27 to be Funded by Senate Bill 1: The Road Repair and Accountability Act

19. Presentation of the City Manager’s FY 2026-27 Proposed Operating and Capital Budgets for the City of Folsom, the Successor Agency, the Folsom Public Financing Authority, and the Folsom Ranch Public Financing Authority

CITY MANAGER REPORTS

COUNCIL COMMENTS

ADJOURNMENT

Page 4 ends

5 NOTICE: Members of the p ublic are entitled to directly address the City Council concerning any item that is described in the notice of this meeting, before or during consideration of that item. If you wish to address Council on an issue, which is on this agenda, please complete a blue speaker request card, and deliver it to a staff member at the table on the left side of the Council Chambers prior to discussion of the item. When your name is called, stand to be recognized by the Mayor and then proceed to the podium. If you wish to address the City Council on any other item of interest to the public, when the Mayor asks if there is any “Business from the Floor,” follow the same procedure described above. Please limit your comments to three minutes or less.

NOTICE REGARDING CHALLENGES TO DECISIONS: Pursuant to all applicable laws and regulations, including without limitation, California Government Code Section 65009 and or California Public Resources Code Section 21177, if you wish to challenge in court any of the above decisions (regarding planning, zoning and/or environmental decisions), you may be limited to raising only those issues you or someone else raised at the public hearing(s) described in this notice/agenda, or in written correspondence delivered to the City at, or prior to, the public hearing.

As presiding officer, the Mayor has the authority to preserve order at all City Council meetings, to remove or cause the removal of any person from any such meeting for disorderly conduct, or for making personal, impertinent, or slanderous remarks , using profanity, or becoming boisterous, threatening or personally abusive while addressing said Council, and to enforce the rules of the Council.

PERSONS INTERESTED IN PROPOSING AN ITEM FOR THE CITY COUNCIL AGENDA SHOULD CONTACT A MEMBER OF THE CITY COUNCIL.

This meeting of the City Council is recorded with closed captioning. The recording will be cablecast on Metro Cable Channel 14, the local government affairs channel on the Comcast and DirecTV U -Verse cable system, and will be shown in its entirety on the Friday and Saturday following the meeting, both at 9 a.m. The recording will also be video streamed at metro14live.saccounty.gov.The City does not control scheduling of this telecast and persons interested in watching the televised meeting should co nfirm this schedule with Metro Cable TV, Channel 14. The City of Folsom provides live and archived webcasts of regular City Council meetings. The webcasts can be found on the online services page of the City's website www.folsom.ca.us.

In compliance with the Americans with Disabilities Act, if you are a person with a disability and you need a disability-related modification or accommodation to participate in this meeting, please contact the City Clerk’s Office at (916) 461-6035, (916) 355-7328 (fax) or [email protected]. Requests must be made as early as possible and at least two full business days before the start of the meeting.

Any documents produced by the City and distributed to the City Council regarding any item on this agenda will be made av ailable at the City Clerk’s Counter at City Hall located at 50 Natoma Street, Folsom, California and at the Folsom Public Library located at 411 Stafford Street, Folsom, California during normal business hours.

Page 5 ends

6 This page is intentionally left blank
to facilitate double-sided printing
and minimize paper use.

Page 6 ends

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 1

City Council Special Meeting

MINUTES

Tuesday, April 28, 2026 6:00 PM

CALL TO ORDER

The special City Council meeting was called to order at 6:00 pm with Mayor Raithel presiding.

ROLL CALL:

Councilmembers Present:

Barbara Leary, Councilmember
Sarah Aquino, Councilmember
Justin Raithel, Mayor
Councilmembers Absent: Michael Kozlowski, Councilmember (arrived 6:02 pm) Anna Rohrbough, Vice Mayor (arrived 6:02 pm)

ADJOURNMENT TO CLOSED SESSION FOR THE FOLLOWING PURPOSES:

1. Conference with Legal Counsel – Existing Litigation – Pursuant to Government Code Section 54956.9(d)(1): Ashley Anne Baker v. City of Folsom, County of Sacramento, State of California, California Department of Public Works, and Does 1-50, inclusive, Sacramento County Superior Court Case No. 26CV009465

2. Conference with Legal Counsel – Anticipated Litigation – Significant Exposure to Litigation Pursuant to Government Code Section 54956.9(d)(2): One Potential Case: Notice of Commencement of CEQA Litigation submitted on behalf of Robert Delp

Motion by Councilmember Aquino, second by Councilmember Leary to adjourn to closed session. Motion passed by the following roll-call vote:

AYES: Leary, Aquino, Raithel
NOES: None
ABSENT: Kozlowski, Rohrbough
ABSTAIN: None

Page 7 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 2

RECONVENE
Interim City Attorney Sari Dierking announced that the City Council authorized legal counsel to defend the case identified in agenda item 1 with a unanimous vote 5-0.

ADJOURNMENT
There being no further business to come before the City Council, the meeting was adjourned at 6:32 pm.

SUBMITTED BY:

_______________________________
Christa Freemantle, City Clerk
ATTEST:

______________________________
Justin Raithel, Mayor

Page 8 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 1

City Council Regular Meeting

MINUTES

Tuesday April 28, 2026 6:30 PM

CALL TO ORDER

The regular City Council meeting was called to order at 6:32 pm with Mayor Raithel presiding.

ROLL CALL:

Councilmembers Present: Michael Kozlowski, Councilmember Barbara Leary, Councilmember
Anna Rohrbough, Vice Mayor
Sarah Aquino, Councilmember
Justin Raithel, Mayor

Councilmembers Absent: None

PLEDGE OF ALLEGIANCE

The pledge of allegiance was recited.

AGENDA UPDATE
Interim City Attorney Sari Dierking advised that there was additional information for Item No. 19.

BUSINESS FROM THE FLOOR:

None
SCHEDULED PRESENTATION:

1. Introductory Presentation of Folsom Public Library Programs and Services Library Director Thomas Gruneisen introduced the item. Youth Services Librarian Lindsay Melhus, Senior Librarian Amanda Perez, and Library Supervisor Andrew Tweet provided a presentation.

The following individual spoke regarding this item:
• Solomon Chis

Page 9 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 2

2. Presentation from California State Parks Representatives Regarding Parks Mural Project California State Park Gold Fields District Superintendent Steve Hilton, accompanied by another California State Park representative, provided a presentation and responded to questions from the City Council. Local Artist Stan Padilla provided supplemental information.

3. Presentation from HART (Homeless Assistance Resource Team) Regarding the 2026 Winter Shelter
HART Director Bev Siess provided a presentation and responded to questions from the City Council.

The following individual spoke regarding this item:
• Miranda Pond

BUSINESS FROM THE FLOOR:

There was a late request to speak under this item.

The following individual spoke under this item:

1. Preran Maderella

CONSENT CALENDAR:

Items appearing on the Consent Calendar are considered routine and may be approved by one motion.

Councilmembers may pull an item for discussion.

4. Approval of the April 14, 2026 City Council Special, Regular and Joint Meeting Minutes

5. Ordinance No. 1367 – An Ordinance of the City of Folsom Amending Chapters 13.03, 13.04,

13.08, 13.12, 13.16, 13.20, and 13.25 of the Folsom Municipal Code Concerning the Sanitary Sewer Collection System and Municipal Sewer System Regulations (Second Reading and Adoption)

6. Ordinance No. 1369 – An Ordinance of the City of Folsom Amending Chapter 13.22 of the Folsom Municipal Code Concerning Water System Cross-Connection Control (Second Reading and Adoption)

7. Community Park West Alternative Site Development Agreement Amendments (DEVA26-00028) and determination that these requests are exempt from CEQA pursuant to CEQA Guidelines Section 15061(b)(3)

i. Ordinance No. 1363 - An Uncodified Ordinance of the City of Folsom Approving Amendment No. 2 to the First Amended and Restated Tier 1 Development Agreement By and Between the City of Folsom and Alder Creek West Improvement Company, LLC,

Page 10 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 3

With Respect to Property Previously Owned by Hillsborough North, LLC. (Second Reading and Adoption)
ii.

Ordinance No. 1364 - An Uncodified Ordinance of the City of Folsom Approving Amendment No. 2 to the First Amended and Restated Tier 1 Development Agreement By and Between the City of Folsom and Alder Creek West Improvement Company, LLC, With Respect to Property Previously Owned by Prairie City Commercial Properties, LLC. (Second Reading and Adoption)

iii. Ordinance No. 1365 - An Uncodified Ordinance of the City of Folsom Approving Amendment No. 2 to the First Amended and Restated Tier 1 Development Agreement By and Between the City of Folsom and Alder Creek West Improvement Company, LLC, With Respect to Property Previously Owned by West Hillsborough Investors, LLC. (Second Reading and Adoption)

8. Resolution No. 11594 - A Resolution Authorizing the City Manager to Seek Grant Funds from the United States Bureau of Reclamation for WaterSMART Small-Scale Water Efficiency Projects for $100,000

9. Pulled for discussion

10. Water Treatment Plant Caustic Soda Storage and Feed System Project (WA2401)

i. Resolution No. 11598- A Resolution Authorizing the City Manager to Execute an Agreement with BWD Construction, Inc. dba BWD General Engineering Contractors for $1,311,720 from the Water Operating Fund (Fund 520) and $874,480 from the Water Capital Fund (Fund 521) for Construction of the Water Treatment Plant Caustic Soda Storage and Feed System Project (WA2401)

ii. Resolution No. 11599- A Resolution Authorizing the City Manager to Execute an Agreement with Inferrera Construction Management Group, Inc. for $225,171 from the Water Operating Fund (Fund 520) and $150,114 from the Water Capital Fund (Fund 521) for Construction Management and Inspection Services for the Water Treatment Plant Caustic Soda Storage and Feed System Project (WA2401) and Appropriation of Funds

11. Pulled for discussion

12. Resolution No. 11602 – A Resolution Authorizing the City Manager to Execute a Consultant Services Agreement with Dewberry Engineers, Inc. for Construction Management and Inspection Services in the amount of $57,376.80 from the Drainage Capital Improvement Fund (Fund 448) for the Bidwell Street Storm Drain Replacement Project, Project No. 2499, and Appropriation of Funds

13. Resolution No. 11605- A Resolution Authorizing the City Manager to Execute an Agreement with Axon Enterprise, Inc. for the Renewal of Police Camera and Technology Lease

Page 11 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 4

Motion by Councilmember Aquino second by Councilmember Kozlowski to approve the Consent Calendar Item No. 4-8, 10, and 12-13. Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

PULLED FOR DISCUSSION:

9. Resolution No. 11597 - A Resolution Authorizing Staff to Submit Grant Applications for Funding for the Folsom Boulevard Pedestrian Overcrossing (POC) Project Through the Safe Streets for All (SS4A) Grant Program Administered by the U.S. Department of Transportation and the Statewide Active Transportation Program (ATP) Cycle 8 Administered by the California Department of Transportation
Councilmember Aquino requested a separate discussion on this item to clarify project details and the use of grant funds for the public record. Following remarks from City Manager Whitemyer, Capital Projects Manager Ryan Neves and Public Works Director Rebecca Neves presented further information and addressed questions from the Council.

Motion by Mayor Raithel, second by Councilmember Kozlowski to approve Resolution No. 11597. Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Aquino, Raithel
NOES: Rohrbough
ABSENT: None
ABSTAIN: None

11. Resolution No. 11600- A Resolution Authorizing Applications for Grant Funding from the Sacramento Area Council of Governments (SACOG) 2026 Federal Funding Programs, Authorizing the City Manager to Submit City of Folsom SACOG 2026 Federal Funding Program Application Priorities, and Authorizing the City Manager to Execute All Grant Documents and Timely Project Delivery Requirements
Vice Mayor Rohrbough pulled this item to request additional details regarding the grant programs.

Senior Civil Engineer Zach Bosch provided a staff presentation and addressed inquiries from the City Council.

Motion by Vice Mayor Rohrbough, second by Councilmember Kozlowski to approve Resolution No. 11600. Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

Page 12 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 5

PUBLIC HEARING:

14. Natoma Station Maintenance Assessment District No. 2025-2 Public/Protest Hearing and Ballot Proceedings; Direction to Staff to Tally Ballots and Return with Results at the Next City Council Meeting
Municipal Landscape Services Manager Derik Perez provided a staff presentation and addressed inquiries from the City Council.

Mayor Raithel opened the public hearing at 8:08 p.m. There being no public testimony or further Council discussion, the Mayor noted that all assessment ballots must be submitted to the City Clerk prior to the close of the hearing. The public hearing was closed at 8:09 p.m.

Manager Perez advised that the ballot tabulation is scheduled for April 29, 2026, at 9:00 a.m. in the City Hall Large Public Works conference room; this process is open to the public. Certified results will be posted online on April 29, 2026, and formally presented at the May 12, 2026, City Council meeting.

15. Resolution No. 11539 - A Resolution of the City Council of the City of Folsom Declaring Results of Majority Protest Proceedings and Modifying the Assessment Rate of the Folsom Tourism Business Improvement District (Continued from February 24, 2026) City Manager Bryan Whitemyer presented the item, noting that all previously submitted protests from hotel owners had been rescinded, contingent upon the approval of the proposed TBID governance structure. Choose Folsom CEO Joe Gagliardi provided additional comments.

Mayor Raithel opened the public hearing at 8:13 p.m. Eileen Reynolds addressed the Council. There being no further testimony, the public hearing was closed at 8:14 p.m.

Motion by Mayor Raithel, second by Councilmember Kozlowski to approve Resolution No. 11539.

During the ensuing discussion, the Interim City Attorney addressed Council inquiries and requested the City Clerk to read the protest status into the record. City Clerk Christa Freemantle confirmed that a majority protest did not exist, as all previously submitted protests had been formally withdrawn.

Following further deliberation, Councilmembers Aquino and Leary expressed interest in serving on the TBID governance committee.

Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

Choose Folsom CEO Joe Galliardi made an additional comment.

Page 13 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 6

16. Resolution No. 11601- A Resolution Replacing Resolution No. 11366 and Approving the Updated City Impact and Connection Fee Schedule for Law Enforcement, Fire Suppression, General Facilities, Vehicles and Equipment, Park Improvement, Humbug-Willow Creek, Housing Trust, Water, Sanitary Sewer, Solid Waste, Transportation Improvement, Drainage, and Light Rail Impact Fees

17. Resolution No. 11604- A Resolution Replacing Resolution No. 11364, 11365 and 11371 and Enacting the Annual Inflationary Adjustment for City User Fees

Revenue Services Manager Elizabeth Hanna provided a joint staff presentation for Item Nos. 16 and

17. Mayor Raithel opened the public hearing at 8:19 p.m. Jack Coplen addressed the Council. The public hearing was closed at 8:20 p.m.

Motion by Councilmember Aquino, second by Councilmember Leary to approve Resolution No. 11601. Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

Motion by Councilmember Aquino, second by Mayor Raithel to approve Resolution No. 11604.

Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

OLD BUSINESS:

18. Resolution No. 11596 - A Resolution Approving the Parks & Recreation Commission’s Recommendation to Approve the Benevento Family Park Master Development Plan Park Planning Manager Brad Nelson delivered a staff presentation. Supplemental information was provided by City Manager Bryan Whitemyer and Parks and Recreation Director Kelly Gonzalez.

The following individuals provided public comment:

1. Andrew Silcox

2. Teri Isaacs

3. Karen Gifford

4. Stephanie Parsons

Page 14 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 7

5. Frank Mukhtar

6. Wendy Campbell
Motion by Councilmember Aquino, second by Councilmember Kozlowski to approve Resolution No. 11596 for Master Development Plan No. 2, including all three additional options as add alternates.

Interim City Attorney Sari Dierking requested the City Council to clarify the motion. Park Planning Manager Brad Nelson and City Manager provided further information, noting that once a bid is received, staff can then evaluate (and submit for Council consideration) any add alternate items that fall within the allocated budget.

Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

19. Resolution No. 11603 – A Resolution Authorizing the City Manager to Execute Contract Amendment #1 with R.E.Y. Engineers, Inc. for the Riley Street Safety Improvement Project, Project No. PW2101, in the Amount of $1,616,074 using $1,430,710 from a Federal Grant and $185,364 from the Transportation Improvement Fund (Fund 446) and Appropriation of Funds in the Transportation Improvement Fund (Fund 446)
Capital Projects Manager Ryan Neves provided a presentation and responded to Council questions.

Loretta Hettinger spoke under this item.

Motion by Councilmember Kozlowski, second by Councilmember Leary to approve Resolution No. 11603. Motion passed by the following roll-call vote:

AYES: Kozlowski, Leary, Rohrbough, Aquino, Raithel
NOES: None
ABSENT: None
ABSTAIN: None

CITY MANAGER REPORTS
City Manager Bryan Whitemyer provided an update regarding the upcoming 2025 Urban Water Management Plan meeting and extended commendations to the Folsom Police Department’s Special Investigation Unit for their efforts regarding a recent theft arrest. He further highlighted the City of Folsom’s upcoming 80th anniversary milestone and concluded his report with announcements concerning summer zoo hours and the release of the Summer Activity Guide.

Page 15 ends

06/09/2026 Item No.1.

File 034-21 26-001
Folsom City Council Minutes
April 28, 2026

Draft- Not Official Until Approved by the City Council Page 8

COUNCIL COMMENTS
Councilmember Aquino discussed Historic District shuttle funding and noted the upcoming Fire Department swearing-in ceremony. She requested that Chief McGee extend her congratulations to Chief Solak and a welcome to Battalion Chief Shawn Luce, as she will be unable to attend the event.

Councilmember Leary had no report.

Councilmember Kozlowski provided comments regarding AB 2415.

Vice Mayor Rohrbough expressed gratitude to SacRT for sponsoring her attendance at the CAP-to- CAP program and shared highlights regarding local family celebrations for her mother’s birthday.

Mayor Raithel reported on his participation in CAP-to-CAP, the upcoming FCUSD meeting, and the Ad Hoc Committee meeting.

ADJOURNMENT
There being no further business to come before the City Council, the meeting was adjourned at 9:51 p.m.

SUBMITTED BY:

_______________________________
Christa Freemantle, City Clerk
ATTEST:

______________________________
Justin Raithel, Mayor

Page 16 ends

06/09/2026 Item No.1.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11614 - A Resolution Authorizing the City Manager to Execute Amendment No. 4 to the Agreement
(Contract No. 173-21 14-092) with Water Works Engineers, LLC for $49,823 from the Water Operating Fund (Fund 520) for Fixed Network and Water Consumption Database As-Needed Support

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends that the City Council pass and adopt Resolution No. 11614 - A Resolution Authorizing the City Manager to Execute Amendment No. 4 to the Agreement (Contract No. 173 -21 14-092) with Water Works Engineer s, LLC for $49,823 from the Water Operating Fund (Fund 520) for Fixed Network and Water C onsumption Database As -Needed Support.

BACKGROUND / ISSUE

Since 2014, Water Works Engineers, LLC (Water Works) has provided support to the City of Folsom on an as-needed basis, with ongoing development and modifications to its fixed network and water meter database (WMDB). Water Works has assisted the City with monthly data transfer to the WMDB from Badger meters installed south of Highway 50, and from the fixed network system north of Highway 50 administered mostly by Zenner. Water Works has also helped improve workflow through developing an automated process for transferring meter data from the WMDB to the billing software.

The scope of work for Amendment No. 3, executed in January 2025 is nearing completion and the City desires to execute an amendment to the agreement with Water Works for continued support .

As with any equipment or operations system, the City’s fixed network system and water consumption database requires maintenance and upgrades to be compatible with the water facility’s system improvements, technology upgrades and general operational requirements.

Page 17 ends

06/09/2026 Item No.2.
2 Water Works Engineers, LLC has the expertise for continuing this support. As the water meter database is critical in facilitating accurate, timely billing, water conservation and maintenance of the meter infrastructure, the City would like a comprehensive and updated documentation effort of the system which has evolved since its inception based on as-needed changes.

This resolution will authorize the City Manager to execute Amendment No. 4 to the Agreement (Contract No. 173-21 14-092) with Water Works Engineers, LLC for Fixed Network and Water Consumption Database As-Needed Support.

POLICY / RULE

Section 2.36.120 of the Folsom Municipal Code states, in part, that contracts for supplies, equipment, services, and construction with an estimated value of $77,426 or greater shall be awarded by the City Council.

ANALYSIS

Fixed network systems have complex software and hardware components that require management and modifications periodically. These upgrades and modifications require specially trained personnel to perform these functions. Rather than hire additional staff t o perform these periodic specialty functions, the City proposes to continue to use Water Works Engineers, LLC for this as- needed support.

In order to maintain the fixed network system and provide the necessary expertise, Water Works Engineers, LLC will provide the following services:

 Review, update and documentation of WMDB programming.  On-call technical support related to the Zenner and Badger fixed network systems and the WMDB.

The Utilities Department recommends amending the current agreement with Water Works Engineers, LLC. The amendment will allow Water Works to continue providing as-needed support for two more years and be in the amount of $49,823 increasing the total contract not -to-exceed amount to $231,771.

This resolution will authorize the City Manager to execute Amendment No. 4 to the Agreement (Contract No. 173-21 14-092) with Water Works Engineers, LLC for Fixed Network and Water Consumption Database As-Needed Support.

FINANCIAL IMPACT

In August 2014, the City executed an agreement with Water Works Engineers, LLC for Fixed Network and Water Consumption Database As -Needed Support for a total amount not to exceed $38,900. Amendment No. 1 to the agreement was executed in November 2016 increasing the total compensation by $49,976 for a new not -to-exceed amount of $88,876. Amendment No. 2 to the agreement was executed in April 2022 increasing the total compensation by $43,123 for a new

Page 18 ends

06/09/2026 Item No.2.
3 not-to-exceed amount of $131,999. Amendment No. 3 to the agreement was executed in January 2025 increasing the total compensation by $49,949 for a new not-to-exceed amount of $181,948.

This amendment will cover the two-year period including the remainder of FY 2025- 26, through FY 2026-27 and into FY 2027-28. Funding for this agreement is included in the Fiscal Year 2025- 26 Operating Budget under the Water Operating Fund (Fund 520). It is also planned to be included in the Water Operating Fund (Fund 520) budgets for FY2026- 27 through FY2029- 30 as part of the annual budgeting process.

The Utilities Department recommends the City Manager executes Amendment No. 4 to the Agreement (Contract No. 173-21 14-092) with Water Works Engineers, LLC to increase the total compensation by $49,823 for a new not-to-exceed total amount of $231,771.

ENVIRONMENTAL REVIEW

This project is an operations and maintenance based project pertaining to existing infrastructure; and therefore, is categorically exempt from environmental review under the California Environmental Quality Act as noted in Title 14 – California Code of Regulations, Chapter 3 – Guidelines for Implementation of the California Environmental Quality Act, Article 19 – Categorical Exemptions, Section 15301 – Existing Facilities.

ATTACHMENTS

1. Resolution No. 11614 - A Resolution Authorizing the City Manager to Execute Amendment No. 4 to the Agreement (Contract No. 173- 21 14- 092) with Water Works Engineers, LLC for $49,823 from the Water Operating Fund (Fund 520) for Fixed Network and Water Consumption Database As-Needed Support

2. Scope of Work for Fixed Network and Water Consumption Database As Needed Support - Amendment No 4

Submitted,

_________________________
Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 19 ends

06/09/2026 Item No.2.

Attachment 1

Page 20 ends

06/09/2026 Item No.2.

Resolution No. 11614

Page 1 of 2 ends

RESOLUTION NO. 11614

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
AMENDMENT NO. 4 TO THE AGREEMENT (CONTRACT NO. 173-21 14-092) WITH WATER WORKS ENGINEERS, LLC FOR $49,823 FROM THE WATER OPERATING FUND (FUND 520) FOR FIXED NETWORK AND WATER CONSUMPTION

DATABASE AS-NEEDED SUPPORT

WHEREAS, the Utilities Department currently utilizes a fixed network system (remote tower meter reading) to comply with California Water Code Section 526; and

WHEREAS, the City’s overall fixed network and database system needs to be maintained and upgraded to meet with technology and general operational requirements; and

WHEREAS, Water Works Engineers , LLC by reason of their past experience with performing these services for the City, and abilities for performing these types of services, is uniquely qualified and recommended to continue to perform the required services; and

WHEREAS, this amendment will increase the Fixed Network and Water Consumption Database As-Needed Support project by $49,823, bringing the total contract amount to $231,771; and

WHEREAS, Amendment No. 4 will cover a period of two years including the remainder of FY 2025-26, through FY 2026-27 and into FY 2027-28; and

WHEREAS, sufficient funds are budgeted and available in the Water Operating Fund (Fund 520) for agreement in FY 2025-26, and will be included during the respective budget process in FY 2026-27 and FY 2027-28; and

WHEREAS, the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to Execute Amendment No.4 to the Agreement (Contract No. 173-21 14-092) with Water Works Engineers, LLC for Fixed Network and Water Consumption Database As-Needed Support for a not -to-exceed amount of $49,823, increasing the total contract not -to- exceed amount to $231,771.

PASSED AND ADOPTED this 26
th day of May 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

Page 21 ends

06/09/2026 Item No.2.

Resolution No. 11614

Page 2 of 2 ends

___________________________________
Justin Raithel, MAYOR

ATTEST:

____________________________________
Christa Freemantle, CITY CLERK

Page 22 ends

06/09/2026 Item No.2.

Attachment 2

Page 23 ends

06/09/2026 Item No.2.

FIXED NETWORK AND WATER CONSUMPTION DATABASE AS-NEEDED SUPPORT P A G E | 1 SCOPE OF ENGINEERING SERVICES FEBRUARY 2026 Scope of Engineering Services
Water Works Engineers, LLC (ENGINEER) and City of Folsom (CLIENT) Water Meter Fixed Network and Water Consumption Database As-Needed Support This Scope of Engineering Services is issued by the City of Folsom (herein referred to as CLIENT) and accepted by Water Works Engineers (herein referred to as ENGINEER) pursuant to the mutual promises, covenants and conditions conta ined in the most current Engineering Services Agreement between the City of Folsom (City) and Water Works Engineers.

Project Description
The project specifics are as follows:

Location Folsom, California
Facility Name Folsom Water Meter Fixed Network System
Project As-Needed Database Management Support
Existing
Documentation
• Folsom Water Meter QA/QC Database (WMDB)
• Zenner Fixed Network System (Zenner)
• Badger Fixed Network System (Beacon)
• Financial Billing Software (Central Square)
Project
Background
Water Works has continued to support the City of Fo lsom on an as- needed basis with ongoing development and modificat ions to its fixed network water meter data collection and billing sys tem. The previous scope of work dating back to 2024 (Amendment 3 - XP 2651) is nearing completion and the City desires to execute a new co ntract for ongoing support. The City has a fixed network system on the North side of Route 50 that is administrated mostly by Zenner. With th e new development South of Route 50, the City has begun utilizing Bad ger Meters and Badger’s Beacon Web Services to host this data, whi ch is separate from Zenner. The City is also slowly replacing Zenner m eters with Badger Meters when their batteries die. The City’s water meter database currently intakes data from both data sources and a cts as the City’s main interface for viewing and utilizing all data.

Within the previous scope of work, Water Works and Rob Talavera completed the following updates to the system:
 Supported transition from DropCountr to Badger Eye On Water for customer facing water meter data viewing
 Developed automated process for transferring WMSO d ata from Water Meter Database to Central Square

Page 24 ends

06/09/2026 Item No.2.

FIXED NETWORK AND WATER CONSUMPTION DATABASE AS-NEEDED SUPPORT P A G E | 2 SCOPE OF ENGINEERING SERVICES FEBRUARY 2026 Scope of Services
To meet the general project objectives, ENGINEER wi ll provide services on an “on-call” or “as- needed” extension of staff basis in support of the City’s WMDB. Services will be split into subtasks as follows.

Subtask Title
1 Document Water Meter Database Back-End and Front- End 2 Miscellaneous As-Needed Services
Subtask 1: Document Water Meter Database Back-End and Front-End A comprehensive and updated documentation effort fo r the programming behind the database functionality has not been completed, and its funct ionality has evolved and changed over many years of as-needed changes requested by the City. For a system as critical as this water meter database is for the City’s operations, updated docu mentation is recommended in the case that the original/current programmer is unavailable to p rovide updates or fixes at any time in the future. This task would include a review and updat e of all in-program notation and documentation (i.e. programming comments), and an u pdate to a text version user-guide that describes the current screens, program modules, and functions.

Subtask 2: WMDB Miscellaneous As-Needed Services
ENGINEER will provide on-call as-needed phone, emai l, office and on-site technical support for issues related to the Zenner and Badger fixed netwo rk systems and the WMDB. Given the somewhat undefined nature of these as-needed servic es, support will be provided up to the defined number of hours and budget, and if the budg et is exceeded, additional scope and fee will be required.

Project Schedule
WWE will work with the City in order to determine a n agreed-upon schedule for each task and sub-task as the work progresses and will commit to and meet those schedules as they are developed. The anticipated overall timeline for this project is 2026-2027.

Payment
Given the “on-call / as-needed” nature of this work , these services will be on a Time and Expense basis not to exceed $49,823 without written consent from CLIENT and invoiced in accordance with the Hourly Billing Rates in the fol lowing table. Individual tasks, hours, not-to- exceed budgets by task, schedules and notices to pr oceed will be mutually agreed upon via email correspondence with City Project Manager prior to commencement.

Page 25 ends

06/09/2026 Item No.2.

FIXED NETWORK AND WATER CONSUMPTION DATABASE AS-NEEDED SUPPORT P A G E | 3 SCOPE OF ENGINEERING SERVICES FEBRUARY 2026 Billing Rates (2026)
Billing Categories
Classification Title Hourly Rate
AA1 Administrative $88.00
AA2 Senior Administrative $124.00
E0 Jr Engineer / Jr Field Engineer $124.00
E1 Staff Engineer $156.00
E1A Staff Engineer II $175.00
E2 Associate Engineer $191.00
E2A Associate Engineer II $203.00
E3 Project Engineer $215.00
E3A Project Engineer II $230.00
E4 Senior Project Engineer $249.00
E4A Senior Project Engineer II $268.00
E5 Principal Engineer $289.00
E5A Principal Engineer II $311.00
P Programmer $170.00
Notes: 1. A markup of 10% will be applied to all pr oject related Direct Costs and Expenses.

2. An additional premium of 25% will be added to th e above rates for Expert Witness and Testimony Services.

3. These rates are effective through December 31, 2 026. A 3% mark-up will be added for any services performed in each year thereafter.

The total budget for each task will be as follows:

Subtask Title Budget
1 Document Water Meter Database Back-End and Front-End $17,776 2 Miscellaneous As-Needed Services $32,047
Note: Budget may be shifted between tasks as needed , fee estimate by task is for fee estimating purposes only.

Attachments
Water Works Engineers Fee Basis Work Plan spreadshe et is attached as reference to the Scope of Services described herein.

Page 26 ends

06/09/2026 Item No.2.

FIXED NETWORK AND WATER CONSUMPTION DATABASE AS-NEEDED SUPPORT P A G E | 4 SCOPE OF ENGINEERING SERVICES FEBRUARY 2026

Page 27 ends

06/09/2026 Item No.2.

This page is intentionally left blank
to facilitate double-sided printing
and minimize paper use.

Page 28 ends

06/09/2026 Item No.2.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
SUBJECT: Resolution No. 11615 – A Resolution Authorizing the City Manager to Execute an Agreement with Electric Vehic le
Conversions, LLC in the Amount of $240,400.56 from the Solid Waste Operating Fund (Fund 540) for the Purchase of an Electric Flatbed Vehicle and Apply for Hybrid and Zero-Emiss ion Truck and Bus Voucher Incentive Project (HVIP) Funding

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends that the City C ouncil pass and adopt Resolution No. 11615 – A Resolution Authorizing the City Manager t o Execute an Agreement with Electric Vehicle Conversions, LLC in the Amount of $240,400. 56 from the Solid Waste Operating Fund (Fund 540) for the Purchase of an Electric Fla tbed Vehicle and Apply for Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project (HVIP) Funding.

BACKGROUND / ISSUE

The Folsom 2035 General Plan, adopted by the City C ouncil, establishes a clear goal of reducing the city’s consumption of carbon-intensive fuels. In 2025, operations at the City of Folsom corporation yard utilized approximately 250, 000 gallons of diesel fuel. This demand comes from medium- and heavy-duty work vehicles use d across the city’s field operations, however approximately 90% is associated with waste collection activities. As operational needs continue to grow, diesel fuel consumption has increased correspondingly.

Diesel powered vehicles contribute significantly to greenhouse gas emissions and expose the community to harmful exhaust pollutants. Transition ing portions of the municipal fleet to electric alternatives offers the potential for subs tantial emissions reductions, reduced noise,

Page 29 ends

06/09/2026 Item No.3.
2 and lower long-term operating costs. While the upfront cost of an electric work truck exceeds that of a diesel equivalent, electric platforms typ ically provide lower maintenance and fuel costs over the life of the vehicle.

To evaluate the operational feasibility of electric vehicles within the Utilities department, and to maintain compliance with California Air Resource s Board (CARB) fleet electrification requirements, staff is seeking authorization to purchase one electric flatbed truck from Electric Vehicle Conversions, LLC, DBA Electric Vehicle Choice (EVC).

Understanding the capabilities and limitations of e lectric technology in daily field operations is necessary for future fleet planning and regulato ry compliance. CARB regulations require a progressive increase in the share of medium-duty electric vehicle sales in California, including
Class 4–5 trucks such as the proposed flatbed. Manu facturers must meet increasing zero- emission sales targets through 2035. Deploying this technology incrementally where practical uses are identified will position the City of Folsom for smoother long-term transition and more informed capital planning.

Available funding through the Hybrid and Zero-Emiss ion Truck and Bus Voucher Incentive Project (HVIP) provides incentives to offset the co st of purchasing zero-emission vehicles.

This funding program is currently available to supp ort public agencies transitioning to zero emission fleets, and the Utilities department conti nues to pursue all eligible opportunities to reduce city costs. Funding availability varies by v ehicle type, manufacturer, and duty cycle.

Staff has identified an applicable program for this purchase, and the vendor will apply on behalf of the city for eligible incentives upon Council authorization.

POLICY / RULE

Section 2.36.120 of the Folsom Municipal Code state s, in part, that contracts for supplies, equipment, services, and construction with an estim ated value of $77,426 or greater shall be awarded by the City Council.

Section 2.36.170 of the Folsom Municipal Code permits cooperative purchasing agreements for the procurement of any supplies, equipment, service, or construction with one or more public procurement units in accordance with an agreement entered into or between the participants.

2035 General Plan Natural and Cultural Resources Goal 3.2.2. – Reduce municipal greenhouse gas emissions by 15 percent below 2005 baseline levels by 2020, and further reduce municipal emissions by:
 40 percent below the 2020 target by 2030;
 51 percent below the 2020 target by 2040, and
 80 percent below the 2020 target by 2050

ANALYSIS

Page 30 ends

06/09/2026 Item No.3.
3 Staff has evaluated the operational needs of the ci ty’s fleet and determined that the proposed electric flatbed truck represents an appropriate ad dition to the Waste and Recycling division fleet. The proposed vehicle, manufactured by Rizon and procured through Electric Vehicle Conversions, LLC, meets current service demands whi le advancing the city’s broader goals related to sustainability, regulatory compliance, and operational efficiency.

EVC specializes in the conversion and configuration of existing truck chassis into fully electric platforms. The proposed electric flatbed truck will be used to support Waste and Recycling operations by collecting bulky waste like appliances and tires from City of Folsom residents.

The vehicle will be equipped with a lift gate and t ilt bed, maintaining all critical functionality of the Waste and Recycling division’s other flatbed while improving usability and safety for staff. Additionally, the proposed unit features a l arger bed capacity, which will enhance productivity by allowing crews to transport more ma terials and equipment per trip, reducing the need for multiple trips and improving overall efficiency.

From a performance standpoint, electric medium-duty trucks such as the Rizon flatbed are designed for predictable, route-based municipal operations. The Waste and Recycling division uses local travel, routine stop and go activity, an d local operations which align well with the capabilities of electric vehicle technology. This makes the proposed unit a practical and reliable fleet expansion for operations that are currently c ompleted using only internal combustion engine vehicles.

The transition to an electric flatbed also provides significant environmental and regulatory benefits. Adoption of zero emission vehicles supports the State of California’s ongoing efforts to reduce greenhouse gas emissions and aligns with regulatory frameworks such as the Advanced Clean Fleets requirements. Early adoption positions the city to remain compliant with evolving mandates while avoiding potential future procurement constraints.

Financially, the request for HVIP funding significantly improves the cost-effectiveness of this purchase. HVIP incentives help offset the higher upfront cost associated with electric vehicles, narrowing the gap between traditional and zero-emission technologies. In addition, the electric vehicle is expected to reduce long-term operating costs through lower fuel expenses, decreased maintenance requirements, and reduced wear on braking systems due to regenerative braking.

Maintaining control over fleet assets and transitio ning to zero-emission technology supports the city’s ability to continue delivering essential services reliably and efficiently. The proposed electric flatbed ensures continuity of operations w hile modernizing the fleet with equipment that is cleaner, quieter, and better aligned with t he city’s long-term service and sustainability objectives.

Sourcewell is a national cooperative purchasing ent ity of which the City of Folsom is a member. The city has purchased numerous items throu gh Sourcewell. EVC has a current contract with Sourcewell for electric flatbed trucks at a price that has been assessed to be fair,

Page 31 ends

06/09/2026 Item No.3.
4 reasonable, and competitive. Sourcewell contract nu mber #032824 ELV will be utilized for the purchase of the electric flatbed truck.

EVC is also an HVIP approved dealer. EVC will seek a voucher in the amount of $60,000 to support this purchase. HVIP vouchers are received directly by the vendor and if approved will reduce the amount of the invoice received by the ci ty. Should the city secure HVIP funding, funding will directly reduce the total purchase cost to minimize Enterprise Fund impacts.

FINANCIAL IMPACT

Sufficient funds are budgeted and available in the Fiscal Year 2025-26 Solid Waste Operating Fund (Fund 540) for the purchase for a total of $24 0,400.56. If HVIP funding of $60,000 is awarded, it will apply to the purchase price when t he vehicle is ordered so the net purchase price would be $180,400.56.

ENVIRONMENTAL REVIEW

This action is exempt from environmental review under the California Environmental Quality Act (CEQA).

ATTACHMENTS

1. Resolution No. 11615 – A Resolution Authorizing the City Manager to Execute an Agreement with Electric Vehicle Conversions, LLC in the Amount of $240,400.56, from the Solid Waste Operating Fund (Fund 540) for the Purchase of an Electric Flatbed Vehicle and Apply for Hybrid and Zero-Emiss ion Truck and Bus Voucher Incentive Project (HVIP) Funding

2. Quote and Specifications from Electric Vehicle Conv ersions, LLC, for the Electric Flatbed Vehicle

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 32 ends

06/09/2026 Item No.3.

Attachment 1

Page 33 ends

06/09/2026 Item No.3.

Resolution No. 11615

Page 1 of 2 ends

RESOLUTION NO. 11615

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AN

AGREEMENT WITH ELECTRIC VEHICLE CONVERSIONS, LLC IN THE AMOUNT OF $240,400.56 FROM THE SOLID WASTE OPERATING FUND (FUND 540) FOR

THE PURCHASE OF AN ELECTRIC FLATBED VEHICLE AND APPLY FOR

HYBRID AND ZERO-EMISSION TRUCK AND BUS VOUCHER INCENTIVE

PROJECT (HVIP) FUNDING

WHEREAS, the Utilities Department’s Waste and Recycling division desires to purchase one electric flatbed vehicle to expand the fleet de dicated to the bulky waste collection program; and

WHEREAS, the Folsom 2035 General Plan commits to reducing t he consumption of carbon-intensive fuels through the purchase of more efficient vehicles; and

WHEREAS, the California Air Resources Board (CARB), through the Advanced Clean Fleets Regulations requires that fifty percent of m edium and heavy-duty vehicles purchased by jurisdictions to be zero emission vehicles; and

WHEREAS, an electric flatbed vehicle is suitable for city operational needs while meeting performance, safety, and payload requirements; and

WHEREAS, the Waste and Recycling division has selected Electric Vehicle Conversions, LLC (EVC) to supply an electric flatbed collection vehicle; and

WHEREAS, the Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project (HVIP) provides incentives to help offset the cost of zero-emission vehicles; and

WHEREAS, participation in the program requires authorizatio n for the vendor to apply for and receive such funding on behalf of the city; and

WHEREAS, this purchase will be made through Sourcewell, whi ch used its recognized cooperative purchasing agreement to award a contract to Electric Vehicle Conversions, LLC in an amount not to exceed $240,400.56; and

WHEREAS, sufficient funds are available in the Solid Waste Operating Fund (Fund 540); and

WHEREAS , the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom hereby authorizes the City Manager to Execute an Agreement with Electric Vehicle Conversions, LLC in the amount of $240,400.56 from the Solid Was te Operating Fund (Fund 540) for the Purchase of an Electric Flatbed Vehicle; and

Page 34 ends

06/09/2026 Item No.3.

Resolution No. 11615

Page 2 of 2 ends

BE IT FURTHER RESOLVED that the City Manager is authorized to Apply for Hybrid and Zero-Emission Truck and Bus Voucher Incentive P roject (HVIP) Funding through Electric Vehicle Conversions, LLC.

PASSED AND ADOPTED this 26
th day of May 2026, by the following roll call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

____________________________________
Justin Raithel, MAYOR

ATTEST:

____________________________________
Christa Freemantle, CITY CLERK

Page 35 ends

06/09/2026 Item No.3.

Attachment 2

Page 36 ends

06/09/2026 Item No.3.
2286 E. Date Ave.

Fresno, CA 93706
Phone: 559-237-5541
Fax: 559-237-5554
www.SEINC.com
Quotation
296605
Date: 4/7/2026, 3:14:43 PM
User: Padilla, Leslie
Bill To: SACRAMENTO TRUCK Ship To: Fresno Will Call
End User: CITY OF FOLSOM End User: CITY OF FOLSOM
Attn: LICHTENBERGER, GREG Attn: Scelzi Enterprises
. 2664 S Cherry Ave.

FOLSOM, CA 95630 Fresno, CA 93706
.

Quote Date: 03/03/2025 Salesman: Diaz, Richard
Expiration Date: 04/02/2025 Ship Via: WILL CALL, Fresno, CA - Sales Office (Will Call) Sales Tax Fresno* @ 8.350% Terms: COD
PO Number:

Notes:

MOUNT IN FRESNO

PAINT BODY WHITE

TBD FUEL TANK

SEE DRAWINGS
NOTE:

1.) QUOTE IS SUBJECT TO ADDITIONAL SURCHARGES PRICE IS VALID FOR 30 DAYS QUOTE WILL BE RE- EVALUATED ONCE CHASSIS IS GIVEN A VIN# AND AN ETA OF CHASSIS IS PROVIDED BY FACTORY

2.) CUSTOMER TO PROVIDE CHASSIS SPECS

3.) SCELZI TO INSPECT CHASSIS BEFORE PRODUCTION OF BED

4.) NO HITCH NO PLUG PER CHASSIS
ETA:

Qty Part Number Description Total Tax
1 CUSTOMER TRUCK 2024 - RIZON - E18M - 4X2 - REG CAB - DRW - ELECTRIC - WHITE - 113" CA VIN#
$0.00
https://portal.seinc.com/Pages/Quotes/QuoteView.html?cbResetParam=1&QuoteID=YEOLDPXPOKOW 1/3

Page 37 ends

06/09/2026 Item No.3.

Quotation
296605
Date: 4/7/2026, 3:14:43 PM
User: Padilla, Leslie
1 GARDNER 8X14 B 8 X 14 FLAT BED DUMP WITH:

PACKAGE B
- SMOOTH STEEL FLOOR - 10 GAUGE
- CROSSMEMBERS ON 16'' CENTERS
- ROPE HOOKS ON EACH CROSSMEMBER
- L.E.D. SEAL BEAM CLEARANCE LIGHTS AND OEM TAILLIGHTS
- HEADBOARD 10GA. -STANDARD
1EA - 42'' SOLID STEEL SIDE RACKS WITH FRONT VERTICAL DOOR 48'' WIDE X 42'' HIGH (1) DRIVERSIDE, (1) PASSENGER SIDE
1EA - DOUBLE ACTING 12 VOLT ELECTRIC/HYDRAULIC DUMP ASSEMBLY 1EA - REAR BARN DOORS
1EA - SCELZI DURA PULL TARP INSTALLED
1EA - POLYUREA COMPLETE CARGO AREA - HEADBOARD, FLOOR,
INSIDE OF SIDE RACKS AND INSIDE OF BARN DOORS.
1EA - ECCO #510 BACK UP ALARM IF EQUIPPED
1EA - RELOCATE FACTORY BACK UP CAMERA IF EQUIPPED
1EA - TOMMY GATE 2000 LBS CAPACITY LIFT AND DUMP MODEL G2-92- 2050 LD 33 WITH A 83X33+6" TAPER 50" TRAVEL WITH SCELZI LED LIGHT KIT
1EA - AUXILIARY BATTERY BOX WITH SEPERATOR MOUNTED @REAR

FOR LIFTGATE OPTIONS
$38,497.00
1 HAZ MAT - HWD
FEE
HAZARDOUS WASTE DISPOSAL FEE $50.00
1 WEIGHT

CERTIFICATE
WEIGHT CERTIFICATE OF COMPLETED UNIT $50.00
1 TRANSPORTATION ONE WAY TRANS
Sub Total $38,597.00
Sales Tax $0.00
Total $38,597.00
https://portal.seinc.com/Pages/Quotes/QuoteView.html?cbResetParam=1&QuoteID=YEOLDPXPOKOW 2/3

Page 38 ends

06/09/2026 Item No.3.

Quotation
296605
Date: 4/7/2026, 3:14:43 PM
User: Padilla, Leslie

DISCLAIMERS
TERMS: Standard terms are Net 10 Days, any deviations need to be in writing before production CHASSIS: Scelzi Enterprises, Inc. is not responsible for flashing or modification of any chassis modules due to the installation of a body
Including but not limited to camera installation, erratic turn signal operation, etc CHANGES: Each change after quote is accepted will constitute a $600.00 fee in addition to the cost of the change No changes will be made to orders 2 weeks prior to production start date DRAWINGS:Any changes to drawings after acceptance and 2 weeks prior to production start date will constitute a $500.00 fee or more at $150.00 per hour
No changes will be made to drawings 2 weeks prior to production start date PAINT: Scelzi Enterprises, Inc. does not guarantee a perfect color match due to inconsistencies in factory paints and procedures

THIS WORK AUTHORIZED BY DATE
Payment in full on completion of job if credit arrangements have not been made in advance Estimate Prepared By:

Littlefield,
Eboni
The above quotation is submitted according to specifications submitted by customer. Any alterations or changes increasing production costs will be charged for accordingly. Sales Rep: Diaz, Richard https://portal.seinc.com/Pages/Quotes/QuoteView.html?cbResetParam=1&QuoteID=YEOLDPXPOKOW 3/3

Page 39 ends

06/09/2026 Item No.3.

Electric Vehicle Choice
11033 Shoemaker Ave -
Santa Fe Springs, CA, 90670-4636
USA
562-273-7777
www.evchoice.com

ESTIMATE
Sep-15-2025
Date Exp Date
EV-1370
Quote #
4-6 weeksLead Time
Sep-30-2025
Bill to Address
Description Qty Rate Amount
Greg Bakken
City of Folsom
1300 Leidesdorff St.

Folsom, CA 95630
US
Ship to Address
Greg Bakken
City of Folsom
1300 Leidesdorff St.

Folsom, CA 95630
US
1 $184,548.00E18M - Class 5 (GVWR 18,859lb) - 134 WB & 113 CA (in) Tax$184,548.00Rizon cab/chassis

FECXKELDSUHC
1 $38,597.00Sceizi 14' Flat Bed Dump per attached spec Tax$38,597.00Body 1 $3,859.70Sourced good multiplier (Cost + 10%); Tax$3,859.70032824-ELV 1 -$7,000.00 Tax$-7,000.00Sourcewell
Discount
6 $1.75CA state new tire fee, per tire. Non$10.50California Tire Fee 1 $85.00CA DMV license, registration and all applicable fees. Non$85.00Registration Fees 1 -$60,000.00HVIP voucher for class 4-5. Non$-60,000.00HVIP Class 4-5 Tax
$160,100.20
$3,250.00
$17,050.36
Subtotal
Shipping
Order subject to Terms and Conditions of Sourcewell Contract 032824-ELV.

City of Folsom Sourcewell member No.90124 ; https://www.sourcewell-mn. gov/participating-agency/90124
Accepted By: Accepted Date:

Total USD $180,400.56

Page 40 ends

06/09/2026 Item No.3.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11616 - A Resolution Authorizing the City Manager to Execute an Agreement with Waterproofing Associates, Inc. for $103,247 from the Water Operating Fund (Fund 520) for the Water Treatment Plant Roof Restoration Project

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends that the City Council pass and adopt Resolution No. 11616 - A Resolution Authorizing the City Manager to Execute an Agreement with Waterproofing Associates, Inc. for $103,247 from the Water Operating Fund (Fund 520) for the Water Treatment Plant Roof Restoration Project.

BACKGROUND / ISSUE

In February 2025, the roof of the City of Folsom’s Water Treatment Plant Administration building was assessed by The G arland Company, Inc. to evaluate the existing conditions . The resulting report identified various locations of failure, including joints, seals, old repairs and skylights.

Based on this evaluation, solutions were recommended for maintenance and restoration, including a recommendation to restore the roof on the treatment plant administration operations building.

Recommended restoration w ork include s, but is not limited to, full re storation of the existing roofing materials, replacement of skylights, cleaning the roof, removal and repair of failed sealants and application of roof restoration coating.

This resolution will authorize the City Manager to execute an agreement with Waterproofing Associates, Inc. for the Water Treatment Plant Roof Restoration Project.

POLICY / RULE

Page 41 ends

06/09/2026 Item No.4.
2 Section 2.36.120 of the Folsom Municipal Code states, in part, that contracts for supplies, equipment, services, and construction with an estimated value of $77,426 or greater shall be awarded by the City Council.

ANALYSIS

The City publicly advertised for bids for the Water Treatment Plant Roof Restoration Project in the Sacramento Bee on April 6, 2026. In addition, the City provided these documents to www.publicpurchase.com and www.virtual-bid.com, which are picked up by several area builders’ exchanges, and posted information on the City of Folsom’s website. The Utilities Department received the following bids on May 8, 2026 for construction of the Water Treatment Plant Roof Restoration Project:

Contractor Bid Amount
Waterproofing Associates, Inc. $89,780
State Roofing Systems, Inc. $95,620
Fog City Roofing & Construction LLC $97,200
Universal Coatings, Inc. $99,500
Diablo Roofing, Inc. $133,771
Pacific Builders & Roofing, Inc. DBA WSP Roofing $140,355 All Seasons North Roofing & Waterproofing, Inc. $161,828 Table 1: Construction Bids

Upon review, Waterproofing Associates, Inc. was determined to be the lowest responsible and responsive bidder who meets the requirements and specifications set forth in the invitation for bids.

The estimated cost for this work was $120,000.

FINANCIAL IMPACT

The Utilities Department recommends that the contract be awarded to the lowest responsible, responsive bidder, Waterproofing Associates, Inc. for $89,780 with the project budgeted for this agreement in the amount of $103,247 which will include a 1 5% contingency in the amount of $13,467.

Sufficient funds are budgeted and available in the Water Operating Fund (Fund 520) in FY 2025- 26 to provide for this agreement.

ENVIRONMENTAL REVIEW

This action is exempt from environmental review under the California Environmental Quality Act (CEQA).

ATTACHMENTS

Page 42 ends

06/09/2026 Item No.4.
3 1. Resolution No. 11616 – A Resolution Authorizing the City Manager to Execute an Agreement with Waterproofing Associates, Inc. for $103,247 from the Water Operating Fund (Fund 520) for the Water Treatment Plant Roof Restoration Project.

2. Bid submitted by Waterproofing Associates, Inc.

3. Roof Inspection Report

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 43 ends

06/09/2026 Item No.4.

Attachment 1

Page 44 ends

06/09/2026 Item No.4.

Resolution No. 11616

Page 1 of 1 ends

RESOLUTION NO. 11616

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH WATERPROOFING ASSOCIATES, INC. FOR $103,247 FROM THE WATER OPERATING FUND (FUND 520) FOR THE WATER TREATMENT

PLANT ROOF RESTORATION PROJECT

WHEREAS, based on an assessment performed by The Garland Company, Inc. it is recommended that the roof of the City of Folsom’s Water Treatment Plant Administration building be repaired; and

WHEREAS, plans and specifications were prepared for this work and publicly advertised for bids on April 6, 2026; and

WHEREAS, on May 8, 2026, the Utilities Department received bids for construction of the Water Treatment Plant Roof Restoration Project; and

WHEREAS, Waterproofing Associates, Inc was the lowest responsible and responsive bidder, with an amount of $89,780; and

WHEREAS, sufficient funds are budgeted and available in the Water Operating Fund (Fund 520) for this agreement; and

WHEREAS, the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to execute an agreement with Waterproofing Associates, Inc for construction of the Water Treatment Plant Roof Restoration Project for a not-to-exceed amount of $89,780 with the budgeted amount to include a 15% contingency of $13,467 for a total of $103,247 from the Water Operating Fund (Fund 520).

PASSED AND ADOPTED this 26
th day of May, 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

__________________________________
Justin Raithel, MAYOR

ATTEST:

______________________________
Christa Freemantle, CITY CLERK

Page 45 ends

06/09/2026 Item No.4.

Attachment 2

Page 46 ends

06/09/2026 Item No.4.

Page 47 ends

06/09/2026 Item No.4.

Page 48 ends

06/09/2026 Item No.4.

Page 49 ends

06/09/2026 Item No.4.

Page 50 ends

06/09/2026 Item No.4.

Page 51 ends

06/09/2026 Item No.4.

Page 52 ends

06/09/2026 Item No.4.

Page 53 ends

06/09/2026 Item No.4.

Page 54 ends

06/09/2026 Item No.4.

Page 55 ends

06/09/2026 Item No.4.

Page 56 ends

06/09/2026 Item No.4.

Page 57 ends

06/09/2026 Item No.4.

Page 58 ends

06/09/2026 Item No.4.

Page 59 ends

06/09/2026 Item No.4.

Attachment 3

Page 60 ends

06/09/2026 Item No.4.

The Garland Company, Inc.

Roof Asset Management Program
City of Folsom - Water Treatment Plant Facility Roof Inspections and Budgets Prepared By
Dan Mc Cready
Prepared For
Bryson Pearson
March 03, 2025

Page 61 ends

06/09/2026 Item No.4.

Table of Contents
City of Folsom - Environmental and Water Resources / Client Data..................................................................................3 Water Treatment Plant / Facility Condition Map..................................................................................................................4 Water Treatment Plant / Admin / WTP / Inspection: Mar 02, 2025.....................................................................................5 Water Treatment Plant / Admin / WTP / Solution: 2025 Maintenance..............................................................................13 Water Treatment Plant / Old Filter Building / Inspection: Mar 02, 2025............................................................................15 Water Treatment Plant / Old Filter Building / Solution: 2025 Replace...............................................................................19 Water Treatment Plant / Building 211 / Inspection: Mar 02, 2025.....................................................................................20 Water Treatment Plant / Building 211 / Solution: 2028 Restore........................................................................................23 Water Treatment Plant / Power / Generator Building Area 202 / Inspection: Mar 02, 2025..............................................24 Water Treatment Plant / Power / Generator Building Area 202 / Solution: 2027 Maintenance.........................................28 Water Treatment Plant / Polymer Building / Inspection: Mar 02, 2025..............................................................................30 Water Treatment Plant / Polymer Building / Solution: 2025 Replace................................................................................34 Water Treatment Plant / Bldg 303 / Inspection: Mar 02, 2025..........................................................................................35 Water Treatment Plant / Bldg 303 / Solution: 2026 Replace.............................................................................................39 Water Treatment Plant / Building 401 / Inspection: Mar 02, 2025.....................................................................................40 Water Treatment Plant / Building 401 / Solution: 2025 Replace.......................................................................................44 Water Treatment Plant / Utility Building 301 / Inspection: Mar 02, 2025...........................................................................45 Water Treatment Plant / Utility Building 301 / Solution: 2026 Replace.............................................................................49 Water Treatment Plant / Water Quality Operations / Inspection: Mar 02, 2025...............................................................51 Water Treatment Plant / Water Quality Operations / Solution: 2026 Replace..................................................................57 Water Treatment Plant / Facility Budget Map....................................................................................................................59 Water Treatment Plant / Visual Facility Summary.............................................................................................................60 Water Treatment Plant / Visual Facility Conditions...........................................................................................................61 Water Treatment Plant / Visual Facility Budget.................................................................................................................62

Page 62 ends

06/09/2026 Item No.4.

Client Data

CITY OF FOLSOM -

ENVIRONMENTAL

AND WATER RESOURCES
194 RANDALL DR
FOLSOM, CALIFORNIA 95630
Client Data
Name
City of Folsom -
Environmental and Water Resources
Address 1
194 Randall Dr
City
Folsom
State
California
ZIP
95630
Country
United States
Contact Info
Contact Person
Bryson Pearson
Title
Water Treatment Plant
Supervisor
Mobile Phone:
-
Office Phone:
916-461-6191
Email:
[email protected]
Client Data

Page 3 ends
Page 63 ends

06/09/2026 Item No.4.

Condition
Map

CITY OF FOLSOM -

ENVIRONMENTAL AND WATER

RESOURCES
194 RANDALL DR
FOLSOM, CALIFORNIA 95630
FACILITY:

Water Treatment Plant
Facility Condition Map
Facility Condition Map

Page 4 ends
Page 64 ends

06/09/2026 Item No.4.

Inspection Information
Inspection Date
03/02/2025
Core Data
No
Inspection Type
Visual Inspection
Leakage
No
Overall
Rating
Poor
Condition
Inspection Report

CITY OF FOLSOM -

ENVIRONMENTAL

AND WATER RESOURCES
194 RANDALL DR
FOLSOM, CALIFORNIA 95630
FACILITY:

Water Treatment Plant
ROOF SECTION:

Admin / WTP
DATE:
03/02/2025

1 Front of the building. Four roof sections, all
single ply roofs of different condition and
age.

Inspection: Mar 02, 2025

Page 5 ends
Page 65 ends

06/09/2026 Item No.4.

2 Roof is in fair condition, a known leak on the
far eastern side. This could be due to the
skylights, multiple repairs and sealant on
the dome. It is recommended that these be
replaced and a maintenance done.

3 Overview of the upper roof. Basic
maintenance is recommended for the roof.

Inspection: Mar 02, 2025

Page 6 ends
Page 66 ends

06/09/2026 Item No.4.

4 Seam tape on the skylight curb. This is a
temporary solution.

5 Minimal ponding water and debris on the
roof.

Inspection: Mar 02, 2025

Page 7 ends
Page 67 ends

06/09/2026 Item No.4.

6 Failed sealant around all penetrations to be
removed and sealed.

7 The joint has failed and the backer rod
exposed. The failed sealant needs to be
removed and replaced.

Inspection: Mar 02, 2025

Page 8 ends
Page 68 ends

06/09/2026 Item No.4.

8 9
The western section of the roof is in the
worst condition. Multiple areas have failed,
a restoration is recommended.

Inspection: Mar 02, 2025

Page 9 ends
Page 69 ends

06/09/2026 Item No.4.

10 Previous repair, the sealant is old and failed.

11 Failed sealant on the skylight curb. The
repairs are temporary and the skylight
should be replaced.

Inspection: Mar 02, 2025

Page 10 ends
Page 70 ends

06/09/2026 Item No.4.

12 Failed sealant on the coping cap joints.

13 Overview, the roof has multiple old repairs
that are failing. The roof is near its end of its
lifespan.

Inspection: Mar 02, 2025

Page 11 ends
Page 71 ends

06/09/2026 Item No.4.

14 Upper main roof.

Inspection: Mar 02, 2025

Page 12 ends
Page 72 ends

06/09/2026 Item No.4.

Report Data
Report Date

03/02/2025
Title

Solution for Admin / WTP
Four roof sections, they are in varying condition. Solutions have been given for maintenance and restoration.

Restore Options
Solution Option:

Restore

Action Year:
2025
Square Footage:
5,500
Expected Life (Years):
10 Budget Range:
$105,000.00 - $120,000.00
This roofing assessment was completed on 2/20/2025. The purpose of this assessment was to evaluate the existing roof conditions and provide recommendations as well as budget costs for the recommended solutions. The visual roof assessment consisted of walking the subject roof areas and documenting the existing conditions of the surfacing, membrane, flashings, drainage, and other related rooftop components. We also talked to available on site personnel and walked accessible building interiors to document reported leak locations.

Project budget / cost estimates are approximates for budgetary purposes and are based upon current labor and material rates for the geographical location. Roof budget costs are based on the roofing system noted below, manufacturer inspections, and warranties based on the system chosen. Actual project costs will depend on the quality and quantity of materials used, options chosen by the designer and owner, quality and availability of contractors, extent of work performed at one time, and time of year the work is performed.

Maintenance and Cleaning on Single Ply Roof $7,500 - $9,500 Scope of work includes but is not limited to:
1 .

Clean roof, valleys and drains of debris.
2 .

All debris to be bagged and properly disposed offsite.
3 .

Clean all drain areas, inspect and reseal as needed.
4 .

Walk roof and look for failed sealants at all penetrations and curbs. Remove failed sealants and reseal. 5 .

Inspect all fasteners on coping metal and curbs, replace any loose or missing with new fasteners w/ grommets. Reseal existing fasteners as needed.
6 .

Remove and reseal expansion joint on CMU wall.
7 .

Replace two (2) ~2'x2' skylights with like kind.

Replacing the skylights can be added to the maintenance. 4'x4' skylights with internal fall protection. 1 skylight - $2,350. ~ $2,000 for each additional.

Restoration Budget Entire Roof - $105,000 - $120,000
10-year Manufacturers Warranty
Restoration Budget - Eastern Roof Section $ 35,000 - $45,000 Properly repair the entire roof system to receive the roof restoration coating. The scope of work includes but is not limited to:

Solution Options

CITY OF FOLSOM -

ENVIRONMENTAL

AND WATER RESOURCES
194 RANDALL DR
FOLSOM, CALIFORNIA 95630
FACILITY:

Water Treatment Plant
ROOF SECTION:

Admin / WTP
TITLE:

Solution for Admin / WTP
DATE:
03/02/2025
Solution: 2025 Maintenance

Page 13 ends
Page 73 ends

06/09/2026 Item No.4.
1 .

Surface preperation: Prepare the roofing system to receive the restoration coating. 2 .

Clean roof, valleys and drains of debris.
3 .

Pressure wash the entire roof system.
4 .

Repair/replace metal flashing, pitch pockets, etc.
5 .

Three course all penetrations.
6 .

Remove and replace all failed sealants
7 .

Seal all curbs and surrounding areas.
8 .

Seal all fasteners with mastic.
9 .

Apply Liquitec Base coat to entire roof at a rate of 1.0 gallons per 100sqft. Allow proper cure time but no more than 72 hours.
10 .

Apply LiquiTec top coat at a rate of 1.5 gallons per 100sqft. 11 .

Replace all Skylights. Install fall protection to meet required code.

Solution: 2025 Maintenance

Page 14 ends
Page 74 ends

06/09/2026 Item No.4.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11617 – A Resolution Authorizing the City Manager to Execute up to Three One-Year Extensions to the Agreement with the County of Sacramento for a Not to Exceed Annual Cost of $50,000 from the Solid Waste Operating Fund (Fund 540) for Household Hazardous Waste Collection Program Services to Folsom Residents at Sacramento County Owned Facilities

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends the City Council pass and adopt Resolution No. 11617 – A Resolution Authorizing the City Manager to Execute up to Three One -Year Extensions to the Agreement with the County of Sacramento for a Not to Exceed Annual Cost of $50,000 from the Solid Waste Operating Fund (Fund 540) for Household Hazardous Waste Collection Program Services to Folsom Residents at Sacramento County Owned Facilities.

BACKGROUND / ISSUE

The Integrated Waste Management Act of 1989 (AB 939) required each jurisdiction in California to provide a Household Hazardous Waste Element defining programs they would provide to residents for the safe collection, recycling, treatment and disposal of household hazardous waste (HHW). The City of Folsom complies with these regulations through a variety of programs, one of which is making the County of Sacramento (County) HHW facilities available for Folsom residents to use at no cost to the resident. Access to County facilities compliments the c ity run door-to-door collection and drop- off programs by providing disposal options that are not appointment based and are available on weekends.

Page 75 ends

06/09/2026 Item No.5.
2 The County household hazardous waste collection facilities are located at Kiefer Landfill in Sloughhouse, California, and North Area Recovery Station (NARS) in North Highlands, California. Folsom residents are permitted to use both facilities. Kiefer Landf ill is conveniently located just 13 miles from the center of Folsom; however, the NARS facility accepts a wider range of materials, providing an expanded service for those who need it.

The city has been contracting to reimburse the County for HHW accepted from Folsom residents since 2010. The current agreement was approved by Folsom City Council on April 12, 2022, by Resolution No. 10834. The cost structure is based on recovery of actual costs incurred and includes labor, materials, transportation, and disposal. An administrative fee is charged per load and includes the cost of verifying the origin of the material. A per item fee captures costs that are associated with the specific material being delivered. Fees are evaluated and updated annually on July 1.

The initial term of the current agreement with Sacramento County expires on June 30, 2026, however, it includes the option of three (3) extensions of one (1) year each upon mutual agreement of the parties. The County has expressed interest in continuing this partnership beyond the initial term.

POLICY / RULE

Section 2.36.120 of the Folsom Municipal Code states, in part, that contracts for supplies, equipment, services, and construction with an estimated value of $77,426 or greater shall be awarded by the City Council.

Chapter 5.04, Purchasing and Contracting, of the Folsom City Charter includes in part, a provision for procurement and services and joint contracts with or through other government jurisdictions.

ANALYSIS

The City of Folsom is required to provide access to environmentally responsible options for residents to dispose of Household Hazardous Waste. Maintaining a robust program with a variety of convenient options minimizes liability related to illegally disposed of hazardous waste , including fire, injury, and harm to the environment. The County HHW facilities are an integral part of ensuring residents have adequate resources for safe HHW disposal.

Currently about 400 Folsom residents per year are using a County facility to dispose of household hazardous waste. This represents roughly 8% of the total residential loads per year from the County, door-to-door, and c ity drop-off programs combined. While only a small portion of the city’s total program, the County program compliments the other resources to ensure all residents have a convenient way to dispose of HHW . Considering the County provides these services at cost, the program contribution to the city’s regulatory compliance, and the mitigation of potential harm to life, the environment, and property from illegal disposal of hazardous materials , the Utilities Department recommends continuing the partnership with the County by executing available extensions each year that these benefits persist.

Page 76 ends

06/09/2026 Item No.5.
3 In Fiscal Year 20 25-26 the Waste and Recycling Division is projected to spend approximately $19,000 on services associated with this contract. Over the next three years, if the current trends continue, the division estimates spending an average of approximately $35,000 per year, however, the maximum financial impact permitted within the contract terms is $50,000. Total costs, up to the maximum, will ultimately depend on the number of residents using this program and the amount of waste dropped off at County facilities.

FINANCIAL IMPACT

If approved, the agreement for Household Hazardous Waste Collection Program Services would authorize up to three one-year extensions with the County of Sacramento in an annual amount not to exceed $50,000. Funding for the agreement would be provided through the Solid Waste Operating Fund (Fund 540). Sufficient funds are available to support the agreement costs and will be requested annually through the City’s operating budget process.

ENVIRONMENTAL REVIEW

This action is exempt from environmental review under the California Environmental Quality Act (CEQA).

ATTACHMENTS

1. Resolution No. 11617 – A Resolution Authorizing the City Manager to Execute up to Three One-Year Extensions to the Agreement with the County of Sacramento for a Not to Exceed Annual Cost of $50,000 from the Solid Waste Operating Fund (Fund 540) for Household Hazardous Waste Collection Program Services to Folsom Residents at Sacramento County Owned Facilities

2. Agreement for Household Hazardous Waste Collection Program Services Between the County of Sacramento and the City of Folsom

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 77 ends

06/09/2026 Item No.5.

Attachment 1

Page 78 ends

06/09/2026 Item No.5.

Resolution No. 11617

Page 1 of 2 ends

RESOLUTION NO. 11617

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE UP TO

THREE ONE-YEAR EXTENSIONS TO THE AGREEMENT WITH THE COUNTY OF SACRAMENTO FOR A NOT TO EXCEED ANNUAL COST OF $50,000 FROM THE SOLID WASTE OPERATING FUND (FUND 540) FOR HOUSEHOLD HAZARDOUS

WASTE COLLECTION PROGRAM SERVICES TO FOLSOM RESIDENTS AT

SACRAMENTO COUNTY OWNED FACILITIES

WHEREAS, the City of Folsom is required by California’s Integrated Waste Management Act to provide for the safe collection, recycling, treatment, and disposal of hazardous household waste for residents; and

WHEREAS, preventing household hazardous waste from entering the landfill and other disposal facilities protects the health and welfare of the community and the environment; and

WHEREAS, a component of the City of Folsom’s household hazardous waste program is to provide access to Sacramento County household hazardous waste drop -off facilities at no cost to residents; and

WHEREAS, the initial term of the current agreement will end on June 30, 2026; and

WHEREAS, the agreement contains t hree optional one -year extensions upon mutual agreement of both parties; and

WHEREAS, the division has determined that continuing to provide Folsom residents with access to County facilities is beneficial to program success; and

WHEREAS, sufficient funds are available in the Solid Waste Operating Fund (540); and

WHEREAS, the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to Execute up to Three One -Year Extensions to the Agreement with the County of Sacramento for a Not to Exceed Annual Cost of $50,000 from the Solid Waste Operating Fund (Fund 540) for Household Hazardous Waste Collection Program Services to Folsom Residents at Sacramento County Owned Facilities.

PASSED AND ADOPTED this 26
th day of May, 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

Page 79 ends

06/09/2026 Item No.5.

Resolution No. 11617

Page 2 of 2 ends

__________________________________
Justin Raithel, MAYOR

ATTEST:

______________________________
Christa Freemantle, CITY CLERK

Page 80 ends

06/09/2026 Item No.5.

Attachment 2

Page 81 ends

06/09/2026 Item No.5.

Page 82 ends

06/09/2026 Item No.5.

Page 83 ends

06/09/2026 Item No.5.

Page 84 ends

06/09/2026 Item No.5.

Page 85 ends

06/09/2026 Item No.5.

Page 86 ends

06/09/2026 Item No.5.

Page 87 ends

06/09/2026 Item No.5.

Page 88 ends

06/09/2026 Item No.5.

Page 89 ends

06/09/2026 Item No.5.

Page 90 ends

06/09/2026 Item No.5.

Page 91 ends

06/09/2026 Item No.5.

Page 92 ends

06/09/2026 Item No.5.

Page 93 ends

06/09/2026 Item No.5.

This page is intentionally left blank
to facilitate double-sided printing
and minimize paper use.

Page 94 ends

06/09/2026 Item No.5.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11618 – A Resolution Authorizing the City Manager to Execute up to Two One-Year Extensions to the Agreement with the County of Sacramento for an Estimated Annual Cost of $2.6 Million from the Solid Waste Operating Fund (Fund 540) for Reduced Tipping Fees for Municipal Solid Waste Disposal at Kiefer Landfill

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends the City Council pass and adopt Resolution No. 11618 – A Resolution Authorizing the City Manager to Execute up to Two One-Year Extensions to the Agreement with the County of Sacramento for an Estimated Annual Cost of $2.6 Million from the Solid Waste Operating Fund (Fund 540) for Reduced T ipping Fees for Municipal Solid Waste Disposal at Kiefer Landfill.

BACKGROUND / ISSUE

The County of Sacramento (County) provides discount ed tipping fees for haulers who commit to disposing of a minimum amount of solid waste at a C ounty facility each year. The city has been party to reduced tipping fee agreements with the County since 2007 for the disposal of municipal solid waste at Kiefer Landfill.

The current agreement, authorized by Folsom City Co uncil on April 12, 2022, by Resolution No. 10833, will expire on June 30, 2026, unless extende d. The original term allows two (2) mutually agreed upon one (1) year extensions and the County has expressed interest in extending the agreement.

POLICY / RULE

Page 95 ends

06/09/2026 Item No.6.
2 Section 2.36.120 of the Folsom Municipal Code state s, in part, that contracts for supplies, equipment, services, and construction with an estim ated value of $77,426 or greater shall be awarded by the City Council.

Chapter 5.04, Purchasing and Contracting, of the Folsom City Charter includes in part, a provision for procurement and services and joint contracts with or through other government jurisdictions.

ANALYSIS

The City of Folsom requires a location to dispose of municipal solid waste collected from residents and businesses. Kiefer Landfill offers reduced tipping fees and is closer to the City of Folsom than any other disposal facility, reducing both the cost of labor and fuel to transport waste material relative to other potential options.

Reduced rates are available in four tiers based on the total waste delivered annually. The city’s waste disposal is projected to be in tier two for t he duration of this agreement, which is a commitment to deliver between 25,000 and 49,999 tons of waste each fiscal year. The most recent five-year average disposal is 39,500 tons per year. Tons disposed was 38,800 in calendar year 2022 and have gradually increased to a projected 40,800 in 2026. By the final year of the agreement, the division estimates we will dispose of approximately 42,300 tons. Nearly 100% of the material delivered qualifies for a tier two discount of $3.00 per ton saving the city approximately $127,000 compared to the public rates.

The discount provided to the city primarily benefit s the Waste and Recycling division; however, the division has collaborated with other city opera tions to ensure they are also able to dispose of waste utilizing this account. Currently other city divisions are receiving about $2,000 per year in discounts, with the majority of this being the Streets division.

FINANCIAL IMPACT

In Fiscal Year 2025–26, the Waste and Recycling div ision is projected to spend $2.4 million on waste disposal at Kiefer Landfill, reflecting disco unted tipping fees under the current agreement.

Tipping fees are set by the County Board of Supervi sors and are charged per ton, increasing annually by 3%. At the same time, waste generation from residential and commercial sources is rising by approximately 1.8% per year.

If these trends continue, disposal costs are expected to reach about $2.6 million in the final year of the agreement. The agreement provides a $3.00 per-ton discount on all waste delivered. However, total costs will ultimately depend on the volume of municipal solid waste generated by residents and businesses. Funds are available in the Solid Waste Fund (Fund 540) and will be budgeted for each fiscal year.

ENVIRONMENTAL REVIEW

This action is exempt from environmental review under the California Environmental Quality Act (CEQA).

Page 96 ends

06/09/2026 Item No.6.
3 ATTACHMENTS

1. Resolution No. 11618 – A Resolution Authorizing the City Manager to Execute up to Two One-Year Extensions to the Agreement with the Count y of Sacramento for an Estimated Annual Cost of $2.6 million from the Solid Waste Operating Fund (Fund 540) for Reduced Tipping Fees for Municipal Solid Waste Disposal at Kiefer Landfill

2. Agreement for Reduced Tipping Fees at Kiefer Landfill

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 97 ends

06/09/2026 Item No.6.

Attachment 1

Page 98 ends

06/09/2026 Item No.6.

Resolution No. 11618

Page 1 of 2 ends

RESOLUTION NO. 11618

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE UP TO TWO

ONE-YEAR EXTENSIONS TO THE AGREEMENT WITH THE COUNTY OF SACRAMENTO FOR AN ESTIMATED ANNUAL COST OF $2.6 MILLION FROM THE SOLID WASTE OPERATING FUND (FUND 540) FOR REDUCED TIPPING FEES

FOR MUNICIPAL SOLID WASTE DISPOSAL AT KIEFER LANDFILL

WHEREAS, the City of Folsom Waste and Recycling Division provides waste collection services for Folsom residents and businesses; and

WHEREAS, the division disposes of municipal solid waste though an agreement with the County of Sacramento to deliver waste to Kiefer Landfill; and

WHEREAS, the disposal agreement provides the city with a discounted rate per ton based on the amount of waste delivered annually; and

WHEREAS, the initial term of the agreement will end on June 30, 2026; and

WHEREAS, the agreement contains two optional one-year extens ions upon mutual agreement of both parties; and

WHEREAS, the division has determined that continuing to disp ose of waste at Kiefer Landfill provides the city with substantial cost-savings for municipal solid waste disposal; and

WHEREAS , sufficient funds are available in the Solid Waste Operating Fund (540); and

WHEREAS , the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to Execute up to Two On e-Year Extensions to the Agreement with the County of Sacramento for an Estimated Annual Co st of $2.6 million from the Solid Waste Operating Fund (Fund 540) for Reduced Tipping Fees for Municipal Solid Waste Disposal at Kiefer Landfill.

PASSED AND ADOPTED this 26
th day of May, 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

__________________________________
Justin Raithel, MAYOR

ATTEST:

Page 99 ends

06/09/2026 Item No.6.

Resolution No. 11618

Page 2 of 2 ends

______________________________
Christa Freemantle, CITY CLERK

Page 100 ends

06/09/2026 Item No.6.

Attachment 2

Page 101 ends

06/09/2026 Item No.6.

Page 102 ends

06/09/2026 Item No.6.

Page 103 ends

06/09/2026 Item No.6.

Page 104 ends

06/09/2026 Item No.6.

Page 105 ends

06/09/2026 Item No.6.

Page 106 ends

06/09/2026 Item No.6.

Page 107 ends

06/09/2026 Item No.6.

Page 108 ends

06/09/2026 Item No.6.

Page 109 ends

06/09/2026 Item No.6.

Page 110 ends

06/09/2026 Item No.6.

Page 111 ends

06/09/2026 Item No.6.

Page 112 ends

06/09/2026 Item No.6.

Page 113 ends

06/09/2026 Item No.6.

Page 114 ends

06/09/2026 Item No.6.

Page 115 ends

06/09/2026 Item No.6.

This page is intentionally left blank
to facilitate double-sided printing
and minimize paper use.

Page 116 ends

06/09/2026 Item No.6.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
SUBJECT: Resolution No. 11619 - A Resolution Amending Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small-Scale Water Use
Efficiency Program Grant

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends the City Council pass and adopt Resolution No. 11619 - A Resolution Amending Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fee Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small-Scale Water Use Efficiency Program Grant.

BACKGROUND / ISSUE

The United States Department of the Interior’s WaterSMART (Sustain and Manage America’s Resources for Tomorrow) Program provides a framework for Federal leadership and assistance to stretch and secure water supplies for future generations in support of the Department’s priorities.

Through WaterSMART, the Bureau of Reclamation (Reclamation) leverages Federal and non - Federal funding to work cooperatively with states, tribes, and local entities as they plan for and implement actions to increase water supply reliability through investments in existing infrastructure and attention to local water conflicts. Reclamation issued Funding Opportunity Number R25AS00279 to make funding available for small-scale water efficiency projects.

The goal of the WaterSMART Small -Scale Water Efficiency Projects NOFO is to invite eligible entities to apply for funding to implement projects that conserve water and enhance water supply reliability in water delivery systems. It encourages the implementa tion of small- scale projects identified through prior planning efforts, such as canal lining, water delivery automation, flow measurement, and other projects that increase water efficiency. The WaterSMART Small -Scale

Page 117 ends

06/09/2026 Item No.7.
2 Water Efficiency Projects NOFO prioritizes projects that are supported by an existing water management and conservation plan, System Optimization Review, or other planning effort led by the applicant.

The Utilities Department recommends the City Council pass and adopt Resolution No. 11619 - A Resolution Amending Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small-Scale Water Use Efficiency Program Grant.

POLICY / RULE

The City of Folsom’s financial policy requires that the City Council approve grant applications that require an ongoing commitment of resources or staff. No additional staff are required for the projects included within the grant application.

ANALYSIS

On April 28, 2026, City Council approved Resolution No.11594 to submit a grant proposal for a WaterSMART Small-Scale Water Efficiency Project. After discussions with the City’s Federal Lobbyist team and with Reclamation staff responsible for reviewing grant applications, there is one additional item required for the City’s Resolution. As part of the grant application process, an official Resolution is required to be submitted in the application that identifies the City’s funding match requirement. The updated Resolution No. 11619 includes a recital that the City will provide the correct amount of funding specified in the City’s funding plan within the grant application and specifies the City’s fund to be used for the project. The attached Resolution No. 11619 includes this language, which was not included in Resolution No. 11594.

FINANCIAL IMPACT

To fund the proposed project, estimated at an overall cost of $ 250,000, the City desires to apply for a grant for up to $100,000 from Reclamation . The remaining $150,000 for the project will be funded from the Water Impact Fund (Fund 456). The minimum required cost-share for the City is 50%. The expected award date for the grant is late 202 6. Proposed project costs for the City’s $150,000 share will be requested in the Fiscal Year 2026-2027 budget. In addition, The Ferguson Group will write the grant proposal, perform the necessary outreach to Reclamation, and conduct a review of the necessary City documentation needed for the submittal of the grant application for up to $11,000 as part of their curr ent agreement with the City for Federal Advocacy Services.

Sufficient Funds are available in the Water Impact Fund (Fund 456) for this project and for the grant writing services of The Ferguson Group.

ENVIRONMENTAL REVIEW

This project is replacement and/or improvement of existing infrastructure with negligible or no expansion of use and therefore is categorically exempt from environmental review under the California Environmental Quality Act as noted in Title 14 – California Code of Regula tions, Chapter 3 – Guidelines for Implementation of the California Environmental Quality Act, Article

Page 118 ends

06/09/2026 Item No.7.
3 19 – Categorical Exemptions, Sections 15301 (Existing Facilities), 15302 (Replacement or Reconstruction), and/or 15304 (Minor Alterations to Land).

ATTACHMENT

Resolution No. 11619 - A Resolution Amending Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small-Scale Water Use Efficiency Program Grant.

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 119 ends

06/09/2026 Item No.7.

Attachment 1

Page 120 ends

06/09/2026 Item No.7.

Resolution No. 11619

Page 1 of 2 ends

RESOLUTION NO. 11619

A RESOLUTION AMENDING RESOLUTION NO. 11594 TO INCLUDE THE CITY’S FUNDING COMMITMENT OF $150,000 FROM THE WATER IMPACT FUND (FUND 456) FOR A UNITED STATES BUREAU OF RECLAMATION WATERSMART

SMALL-SCALE WATER USE EFFICIENCY PROGRAM GRANT

WHEREAS, the City is eligible to receive up to $100,000 in federal grant funds through the U.S. Department of the Interior, Bureau of Reclamation WaterSMART Samm- Scale Water Use Efficiency Program Grant for Fiscal Year 2027; and

WHEREAS, the City implements projects and programs that increase water efficiency; and

WHEREAS, Resolution No. 11594 authorized the City Manager to submit an application for the funding opportunity; and

WHEREAS, the City of Folsom commits to the financial and legal obligations associated with receipt of a financial assistance award under this funding opportunity; and

WHEREAS, the Irrigation Tune -Up Project (Project) meets the eligibility requirements of funding opportunity R26AS00279, and the City of Folsom desires to submit an application for consideration; and
WHEREAS, the total estimated cost of the Project is $250,000 of which the City of Folsom is requesting $100,000 in Federal funding and will contribute $150,000 in non-Federal cost share, representing at least 50 percent of total project costs; and WHEREAS, the City of Folsom certifies awareness of and agrees to comply with all currently effective and applicable executive orders, Secretary’s orders, and other Federal requirements that apply to this funding opportunity and any resulting award; and

WHEREAS, the City of Folsom will work with the Bureau of Reclamation to meet established deadlines for entering into a grant or cooperative agreement and for completing the Project; and

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom amends Resolution No. 11594 to include the City’s Funding Commitment of $150,000 from the Water Impact Fund (Fund 456) for a United States Bureau of Reclamation WaterSMART Small - Scale Water Use Efficiency Program Grant.

PASSED AND ADOPTED this 26th day of May 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

Page 121 ends

06/09/2026 Item No.7.

Resolution No. 11619

Page 2 of 2 ends

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

___________________________________
Justin Raithel, MAYOR
ATTEST:

____________________________________
Christa Freemantle, CITY CLERK

Page 122 ends

06/09/2026 Item No.7.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11621 – A Resolution Authorizing the City Manager to Execute an Amendment to the Agreement (Contract No. 173-21 21-068) with Genuine Parts Company DBA Napa
Auto Parts for an Annual Cost of up to $1,032,600 for Vendor Managed Inventory Services in the Fleet Division, 1300
Leidesdorff Street, from all Department Funds as Required for Vehicle Maintenance and Repairs

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends the City Council pass and adopt Resolution No. 11621 – A Resolution Authorizing the City Manager to Execute an Amendment to the Agreement (Contract No. 173-21 21-068) with Genuine Parts Company DBA Napa Auto Parts for an Annual Cost of up to $1,032,600 for Vendor Managed Inventory Services in the Fleet Division, 1300 Leidesdorff Street, from all Department Funds as Required for Vehicle Maintenance and Repairs.

BACKGROUND / ISSUE

The Utilities Department’s Fleet Management Division is responsible for the repair and maintenance of more than 500 vehicles and equipment assets across multiple c ity departments.

Annually, Fleet division staff generate approximately 2,300 work orders and utilize an estimated 56,000 individual parts.

On September 14, 2021, the Folsom City Council adopted Resolution No. 10693, authorizing an agreement with Genuine Parts Company (NAPA) to operate an on-site store supporting the city’s automotive parts needs.

The city entered into this agreement through a cooperative purchasing contract (No. 110520-GPC) between NAPA and Sourcewell, a national cooperative purchasing organization of which the City

Page 123 ends

06/09/2026 Item No.8.
2 of Folsom is a member. While the original Sourcewell contract has since expired, a successor contract with substantially similar terms has been executed, extending service availability through December 2028.

To ensure the continued operation of the on- site store within the F leet division, the agreement between the city and NAPA must be amended to reflect the updated Sourcewell contract number (No. 090624-GPC).

POLICY / RULE

Section 2.36.120 of the Folsom Municipal Code states, in part, that contracts for supplies, equipment, services, and construction with an estimated value of $77,426 or greater shall be awarded by the City Council.

Section 2.36.170 of the Folsom Municipal Code permits cooperative purchasing agreements for the procurement of any supplies, equipment, service, or construction with one or more public procurement units in accordance with an agreement entered into or between the participants.

ANALYSIS

The Vendor Managed Inventory (VMI) agreement ensures consistent, timely, and cost -effective access to parts. Under this model, a full -time Inventory Specialist is assigned on -site to procure parts for all repair activities. This centralized approach provides Fleet division mechanics with a single point of contact, eliminating the need to independently source parts from multiple vendors.

To maintain uninterrupted service, NAPA provides a qualified substitute in the absence of the assigned specialist. As a result, more than 90 percent of parts orders are fulfilled within a two-hour timeframe.

The VMI agreement also eliminated the need for the ci ty to own and manage inventory. NAPA retains ownership of parts until they are needed for a specific repair. The Inventory Specialist assigns each part to the corresponding vehicle and work order, ensuring accurate cost allocation to city departments. The specialist is responsible for tracking all inventory movement within the parts room, and all expenditures must be tied to an authorized work order.

In addition, the VMI program includes routine inventory audits and proactive adjustments to align stock levels with the city’s operational needs. This approach minimizes the city’s exposure to costs associated with excess, obsolete, or unused inventory. If parts are not needed by the c ity, NAPA is able to utilize their network of stores and vendors to circulate parts to other outlets prior to becoming obsolete and losing their value.

Efficient fleet maintenance operations rely on the timely ava ilability of parts. Prior to implementing NAPA’s integrated business solution the c ity employed an Inventory Clerk whose responsibilities extended beyond inventory management. Mechanics frequently had to research parts independently and drive to multiple retail locations to procure what they needed for repairs.

Utilizing VMI brings the expertise and extensive network of NAPA into the c ity operations allowing mechanics to focus on core repair functions . Inventory is actively managed to ensure

Page 124 ends

06/09/2026 Item No.8.
3 accurate accounting and on -hand availability to best meet c ity needs. The Fleet division has determined that the VMI model represents the most cost-effective approach to meeting its ongoing essential parts procurement needs.

FINANCIAL IMPACT

The total financial impact of continuing NAPA’s operation of an on- site store at the corporation yard is not to exceed $1,032,600 annually for parts and store operations, with costs allocated across all city departments. On average, the city spends about $994,000 under this program. The cost of operating the store includes all staff costs, insurance, office equipment, and supplies, and averages $106,000 of the total cost each year . Store operating costs are paid through the Fleet division budget which is funded by a cost allocation plan based on labor hours of fleet staff for each department’s vehicles. Approximately 73% of fleet overhead, including the operating cost of the store, is funded by enterprise funds.

All automotive parts, including NAPA branded or sourced from other vendors, are provided to the city at 10% above NAPA’s cost. Parts expenses are charged directly to the respective departments at the time of use and are budgeted within each department’s vehicle maintenance account.

ENVIRONMENTAL REVIEW

This action is exempt from environmental review under the California Environmental Quality Act (CEQA).

ATTACHMENTS

1. Resolution No. 11621 – A Resolution Authorizing the City Manager to Execute an Amendment to the Agreement (Contract No. 173-21 21-068) with Genuine Parts Company dba Napa Auto Part s for an Annual Cost of up to $1,032,600 for Vendor Managed Inventory Services in the Fleet Division, 1300 Leidesdorff Street, from all Department Funds as Required for Vehicle Maintenance and Repairs

2. Integrated Supply Agreement by and Between Genuine Parts Company and City of Folsom, California

3. Assignment Agreement, assigning the Agreement from Riebe’s Auto Parts, LLC to Genuine Parts Company

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 125 ends

06/09/2026 Item No.8.

Attachment 1

Page 126 ends

06/09/2026 Item No.8.

Resolution No. 11621

Page 1 of 2 ends

RESOLUTION NO. 11621

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AN AMENDMENT TO THE AGREEMENT (CONTRACT NO. 173-21 21-068) WITH

GENUINE PARTS COMPANY DBA NAPA AUTO PARTS FOR AN ANNUAL COST OF UP TO $1,032,600 FOR VENDOR MANAGED INVENTORY SERVICES IN THE FLEET DIVISION, 1300 LEIDESDORFF STREET, FROM ALL DEPARTMENT

FUNDS AS REQUIRED FOR VEHICLE MAINTENANCE AND REPAIRS

WHEREAS, the City of Folsom requires timely and reliable access to automotive parts for the maintenance and repair of city vehicles; and

WHEREAS, the city executed an agreement with Genuine Parts Company (NAPA) to operate an onsite auto parts store; and

WHEREAS, the agreement was made through Sourcewell, which used its recognized cooperative purchasing agreement to award contract #110520-GPC to NAPA; and

WHEREAS, the Sourcewell contract #110520-GPC has expired; and

WHEREAS, Sourcewell has awarded contract #090624 to NAPA extending the availability of vendor managed inventory services; and

WHEREAS, NAPA has continued to operate the onsite store pending the execution of an amendment updating the cooperative purchasing contract number; and

WHEREAS, the Fleet Division has determined NAPA’s performance under the agreement has improved productivity through reliable parts availability and inventory management; and

WHEREAS, funds are budgeted annually in all city departments for the maintenance and repair of vehicles; and

WHEREAS, the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to Execute an Amendment to the Agreement (Contract No. 173- 21 21-068) with Genuine Parts Company DBA Napa Auto Parts for an Annual Cost of up to $1,032,600 for Vendor Managed Inventory Services in the Fleet Division, 1300 Leidesdorff Street, from all Department Funds as Required for Vehicle Maintenance and Repairs.

PASSED AND ADOPTED this 26
th day of May, 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

Page 127 ends

06/09/2026 Item No.8.

Resolution No. 11621

Page 2 of 2 ends

__________________________________
Justin Raithel, MAYOR

ATTEST:

______________________________
Christa Freemantle, CITY CLERK

Page 128 ends

06/09/2026 Item No.8.

Attachment 2

Page 129 ends

06/09/2026 Item No.8.

Page 130 ends

06/09/2026 Item No.8.

Page 131 ends

06/09/2026 Item No.8.

Page 132 ends

06/09/2026 Item No.8.

Page 133 ends

06/09/2026 Item No.8.

Page 134 ends

06/09/2026 Item No.8.

Page 135 ends

06/09/2026 Item No.8.

Page 136 ends

06/09/2026 Item No.8.

Page 137 ends

06/09/2026 Item No.8.

Page 138 ends

06/09/2026 Item No.8.

Page 139 ends

06/09/2026 Item No.8.

Page 140 ends

06/09/2026 Item No.8.

Page 141 ends

06/09/2026 Item No.8.

Page 142 ends

06/09/2026 Item No.8.

Page 143 ends

06/09/2026 Item No.8.

Page 144 ends

06/09/2026 Item No.8.

Page 145 ends

06/09/2026 Item No.8.

Page 146 ends

06/09/2026 Item No.8.

Page 147 ends

06/09/2026 Item No.8.

Page 148 ends

06/09/2026 Item No.8.

Page 149 ends

06/09/2026 Item No.8.

Page 150 ends

06/09/2026 Item No.8.

Page 151 ends

06/09/2026 Item No.8.

Page 152 ends

06/09/2026 Item No.8.

Page 153 ends

06/09/2026 Item No.8.

Page 154 ends

06/09/2026 Item No.8.

Page 155 ends

06/09/2026 Item No.8.

Page 156 ends

06/09/2026 Item No.8.

Page 157 ends

06/09/2026 Item No.8.

Page 158 ends

06/09/2026 Item No.8.

Attachment 3

Page 159 ends

06/09/2026 Item No.8.

Page 160 ends

06/09/2026 Item No.8.

Page 161 ends

06/09/2026 Item No.8.

Page 162 ends

06/09/2026 Item No.8.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
ITEM TITLE: Resolution No. 11623 – A Resolution Authorizing the City Manager to Execute an Agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for Design, Engineering Services During Construction, and
Construction Management and Inspection for the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703) and Appropriation of Funds

FROM: Utilities Department

RECOMMENDATION / CITY COUNCIL ACTION

The Utilities Department recommends the City Council pass and adopt Resolution No. 11623 - A Resolution Authorizing the City Manager to Execute an Agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for Design, Engineering Services During Construction, and Construction Management and Inspection f or the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703) and Appropriation of Funds.

BACKGROUND / ISSUE

The Utilities Department identifies water infrastructure rehabilitation and replacement projects through water master plans, ongoing water condition assessment programs, and regulatory changes. Through these efforts, portions of the water system have been identified as needing rehabilitation or replacement in order to improve the water distribution system reliability. Through these efforts, Utilities department staff identified the Zone 4 Tank Rehabilitation Project as a priority project.

During construction of the current Tower Tank Rehabilitation Project (Project WA2402) involving East Tank No. 2, Tower Tank, and Foothills Tank No. 2, the contractor encountered multiple unforeseen conditions involving structural deficiencies and other items requiring rehabilitation or replacement. Since the tanks involved in the Tower Tank Rehabilitation Project are of a similar

Page 163 ends

06/09/2026 Item No.9.
2 age and construction type as the Zone 4 Tank, the Utilities Department has identified the Zone 4 Tank as a priority project to ensure operational reliability of the city’s water distribution system.

The City of Folsom’s Zone 4 Tank is located on Caversham Drive, in the Broadstone neighborhood. Phase 1 of the Zone 4 Tank Rehabilitation Project involves draining and cleaning the tank so that the contractor can install the necessary scaffolding and perform any required sandblasting to allow a licensed structural engineer access to the interior of the tank . A structural engineer will perform an initial structural assessment of the tank to determine the condition of the tank and provide recommendations rega rding rehabilitation. The required assessment by a structural engineer includes r eview of record drawings, photographs, performing structural steel thickness testing (web, flange, etc.), checking for structural defects (corrosion, pitting, buckling, etc.) and preparing a written report including estimated remaining serviceable life of each component and recommendation for full rehabilitation. Other ancillary work at the Zone 4 Tank includes installation of a mixer and blower, spot repair, and miscellaneous electrical improvements. Additionally, this project will include the installation of a mixer and blower at East Tank to improve water quality.

Design and construction of Phase 2 of the project will occur once the structural engineer's recommendation under Phase 1 is complete. Design is anticipated to begin and be completed in FY 2026-27, and Phase 1 construction is also anticipated to begin and be completed in FY 2026-

27. This Resolution will authorize the City Manager to e xecute an agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for design, engineering services during construction, and construction management and inspection f or the Zone 4 Tank Rehabilitation Project (Phase 1) and appropriation of funds.

POLICY / RULE

Section 2.36.120 of the Folsom Municipal Code states, in part, that contracts for supplies, equipment, services, and construction with an estimated value of $77,426 or greater shall be awarded by the City Council.

ANALYSIS

In January 2025, the Utilities Department completed a pre-qualification process for consultants for design and construction administration services for water and wastewater projects. The consulting firms Dewberry Engineers, Inc., Kennedy/Jenks Consultants, Inc. and HydroScience Engineers, Inc. were among a group of firms selected to provide these services for this type of project through this previously completed pre-qualification process. At that time, the Utilities Department also completed a pre-qualification process for consultants for Construction Management and Inspection (CM&I) services for water and wastewater projects, and consulting firms Psomas, Inferrera Construction Management Group, Inc (ICM), Dewberry Engineers, Inc., Kennedy Jenks, West Yost & Associates, MCK Americas, and Albat were selected to provide these services.

Page 164 ends

06/09/2026 Item No.9.
3 On March 23, 2026, the city sent a Request for Proposals (RFP) to pre-qualified design consultants to provide plans, front end specifications, technical specifications, and other miscellaneous items to complete the project manual for public bid of the construction project, as well as engineering services during construction. The Zone 4 Tank Rehabilitation Project has an accelerated timeline to perform the work and inspection outlined in the RFP due to operational restrictions of when the tanks can be offline for draining, inspection, and repairs, the RFP sent to the pre -qualified design consultants required they partner with one of the city’s pre-approved CM&I firms to expedite the bid process and have the contractor ready to perform the work by October, 2026.

On May 8, 2026, Utilities department staff received proposals from Kennedy/Jenks Consultants, Inc. and HydroScience Engineers, Inc. Dewberry Engineers, Inc. previously notified the city that it was unable to provide the necessary staffing for the project and declined the opportunity to submit a proposal. The proposals were reviewed and scored for project understanding, project team staffing, and recent relevant experience. The technical evaluations were scored as shown in Table 1 based on a maximum technical score of 80.

Consultant UT 1 UT 2 UT 3 Average
Kennedy/Jenks Consultants, Inc. 49 55 48 50.7
HydroScience Engineers, Inc. 65 73 76 71.3
Table 1: Consultant Technical Scores without Costs

After reviewing each proposal for project understanding, project team staffing, and recent relevant project experience, the proposals were reviewed for project costs. The fee schedules for the scope of work outlined in the request for proposal from each consultant are shown in Table 2.

Consultant Fee Amount
Kennedy/Jenks Consultants, Inc. $1,417,926
HydroScience Engineers, Inc. $474,041
Table 2: Consultant Project Costs

HydroScience Engineers, Inc. was determined to provide the best value to the c ity based on the fee amount, past municipal project experience involving work of similar scope and complexity including staff coordination and technical knowledge and expertise for these types of projects.

Additionally, HydroScience Engineers, Inc. has current and relevant project understanding compared to other consultants for this project, including the current Tower Tank Rehabilitation Project that has incurred similar structural inspections and repairs for the City of Folsom.

Table 3 shows the overall total scores including project costs based on a maximum score of 100.

Consultant
Technical Score
(Avg.)
Cost Score Total Score
Kennedy/Jenks Consultants, Inc. 50.7 11.7 62.4
HydroScience Engineers, Inc. 71.3 20 91.3
Table 3: Consultant Overall Scoring Including Project Costs

Page 165 ends

06/09/2026 Item No.9.
4 This resolution will authorize the City Manager to execute an agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for design, engineering services during construction, and construction management and inspection f or the Zone 4 Tank Rehabilitation Project (Phase 1) and appropriation of funds.

FINANCIAL IMPACT

If approved, the agreement with HydroScience Engineers, Inc. for design, engineering services during construction, and c onstruction management and i nspection for the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703) would be in the amount of $474,041. The agreement will require an appropriation of 474,041 in the Water Operating Fund (Fund 520). Sufficient funds are available in the Water Operating Fund (Fund 520) to cover the cost of the agreement and the requested appropriation.

ENVIRONMENTAL REVIEW

This project is replacement and/or improvement of existing infrastructure with negligible or no expansion of use and therefore is categorically exempt from environmental review under the California Environmental Quality Act as noted in Title 14 – California Code of Regulations, Chapter 3 – Guidelines for Implementation of the California Environmental Quality Act, Article 19 – Categorical Exceptions, Section 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction).

ATTACHMENTS

1. Resolution No. 11623 - A Resolution Authorizing the City Manager to Execute an Agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for Design, Engineering Services During Construction, and Construction Management and Inspection for the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703) and Appropriation of Funds

2. Zone 4 Tank and East Tank No.1 Project Map

3. HydroScience Zone 4 Tank Rehabilitation Project (Phase 1) Scope and Fee

Submitted,

Marcus Yasutake, Director

UTILITIES DEPARTMENT

Page 166 ends

06/09/2026 Item No.9.

Attachment 1

Page 167 ends

06/09/2026 Item No.9.

Resolution No. 11623

Page 1 of 2 ends

RESOLUTION NO. 11623

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH HYDROSCIENCE ENGINEERS, INC. FOR $474,041 FROM THE WATER OPERATING FUND (FUND 520) FOR DESIGN, ENGINEERING SERVICES

DURING CONSTRUCTION, AND CONSTRUCTION MANAGEMENT AND
INSPECTION FOR THE ZONE 4 TANK REHABILITATION PROJECT (PHASE 1) (WA2703) AND APPROPRIATION OF FUNDS

WHEREAS, the City has identified this project as a priority to maintain integrity and operation of the water distribution system; and

WHEREAS, the rehabilitation work identified will enhance the city’s water distribution system and to continue to provide reliable water service to the City includes rehabilitating the Zone 4 Tank; and

WHEREAS, HydroScience Engineers, Inc. by reason of their experience and abilities for performing these types of services, are qualified to perform the required additional design and engineering services during construction for this project; and

WHEREAS, sufficient funds are available in the Water Operating Fund (Fund 520) for this agreement and the requested appropriation in the amount of $474,041, and

WHEREAS, the agreement will be in a form acceptable to the City Attorney:

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Folsom authorizes the City Manager to execute an Agreement with HydroScience Engineers, Inc. for $474,041 from the Water Operating Fund (Fund 520) for Design, Engineering Services During Construction, and Construction Management and Inspection for the Zone 4 Tank Rehabilitation Project (Phase 1) (WA2703).

BE IT FURTHER RESOLVED that the Finance Director is authorized to appropriate $474,041 for this agreement. The appropriation will be made in the Water Operating Fund (Fund 520) for the amount of $474,041.

PASSED AND ADOPTED this 26
th day of May, 2026, by the following roll-call vote:

AYES: Councilmember(s):

NOES: Councilmember(s):

ABSENT: Councilmember(s):

ABSTAIN: Councilmember(s):

__________________________________
Justin Raithel, MAYOR

ATTEST:

Page 168 ends

06/09/2026 Item No.9.

Resolution No. 11623

Page 2 of 2 ends

______________________________
Christa Freemantle, CITY CLERK

Page 169 ends

06/09/2026 Item No.9.

ATTACHMENT 2
ZONE 4 TANK REHABILITATION PROJECT MAP

Page 170 ends

06/09/2026 Item No.9.

ATTACHMENT 3
HYDROSCIENCE ZONE 4 TANK REHABILITATION PROJECT

SCOPE AND FEE

Page 171 ends

06/09/2026 Item No.9.

May 8, 2026

Nathan Sites
City of Folsom – Utilities
50 Natoma Street
Folsom, CA 95630
Subject: Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project
Dear Mr. Sites,
HydroScience Engineers, Inc. (HydroScience) is pleased to submit this proposal to provide civil engineering design services for the Zone 4 Phase 1 Tank Rehabilitation Project (Project). We have assembled a team of capable local staff experienced with the design and construction of City water infrastructure projects, who are both intimately familiar with the project elements and committed to a successful outcome. We have additionally included West Yost from the City’s list of pre-qualified Construction Management and Inspection (CM&I) consultants to provide those services on this project.

The following summarizes key benefits of choosing the HydroScience team to provide professional engineering services on this project:
• Proposed Project Manager Eric Jones has significant prior experience completing City design and construction projects, including: Tower Tank Rehabilitation Project, Ashland I and II water distribution improvements, Willow Hill Pipeline Rehabilitation, Hinkle Creek Pipeline Rehabilitation, and multiple water system pressure reducing valve (PRV) design projects. Intimate knowledge of City standards and procedures and a strong working relationship with City staff results in efficient project execution and effective enforcement of City requirements. • Key proposed team members Eric Jones, Austin Poulson, and Brad Friederichs along with West Yost for CM&I are successfully delivering a similar complex tank rehabilitation project for the City: the Tower Tank Rehabilitation Project. This team demonstrated our ability to fast-track design to meet a winter construction schedule, coordinate closely with the City, pivot quickly to address changing conditions, and function as a cohesive team to drive towards successful completion accomplishing all of the City’s objectives. Our combined team will carry this momentum from Tower Tank directly into this project, improving efficiency and accelerating execution. • The proposed project team has worked together to successfully complete dozens of similar water and wastewater infrastructure projects for municipal clients. This team shares a passion for producing high quality results in a collaborative and efficient manner and has a long history of working together effectively.
• Key team members are based in our Sacramento office within 20 minutes driving distance of the City. Being local enhances our ability to get to the site very quickly to address any need and reduces travel cost.
• Principal-in-Charge Bill Slenter is a long-term City resident and is committed to the successful outcome of this project. He can travel to the project site or City Hall on very short notice to address any concerns or needs.

Page 172 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 2 of 12 ends

Proposed Staffing
The organization chart to the right illustrates our proposed key staff and roles. We have included their resumes in Attachment A:

Our Project staffing strategy is as follows:
• Eric Jones, PE will serve as Project
Manager (PM) and Design Engineer-of-
Record. He will apply rigorous project and
technical management practices to keep the
project on-track and moving forward,
communicating with the City in real time. The
City will be regularly informed of project
status, needs, and upcoming activities.
• Austin Poulson will serve as the Project
Engineer (PE). Working with Eric, Austin will
coordinate and execute the technical design
elements; coordinate with our drafting team;
lead the preparation of plans, specifications,
and calculations for the design; assist Eric
during the bid support phase; and perform
RFI and submittal review during construction.

Austin has significant prior experience
including working with Eric on the Tower Tank Rehabilitation Project and will apply his experience regarding the City’s goals for water tank improvements, optimizing the design to achieve the City’s goals for this project.
• Bill Slenter, PE will serve as Principal-in-Charge. He will be the City’s contractual point of contact and alternate contact to Eric and will verify that our team is executing the project in accordance with contractual requirements and HydroScience’s quality standards. He will also be available to assist with any field needs given his close proximity to the sites. • Thinh Le, PE will serve as the lead electrical engineer. Thinh manages our Electrical Department and has almost twenty years of experience. He has worked closely with Eric and Austin on dozens of similar projects. He will design improvements that are easy to operate and maintain and conform to City standards and preferences.
• VE Solutions will provide structural engineering on this project, including providing the structural tank assessment. If needed, they are prepared to develop stamped structural drawings and calculations for tank repairs.
• West Yost will provide CM&I services for the project. They will work in close collaboration with HydroScience on construction activities, following the established procedures demonstrated in the ongoing Tower Tank Rehabilitation Project. Crawford & Associates will provide materials testing and special inspection support as a subcontractor to West Yost.

Page 173 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 3 of 12 ends

• Bay Area Coating Consultants will provide coatings
inspection as a subconsultant to HydroScience. They
bring over 39 years of coating and lining consulting
and inspection firm experience on projects
throughout California and Nevada.

Understanding and Approach
This project will address rehabilitation and operational improvement needs at two potable water storage
reservoirs within the City: the Zone 4 Phase 1
(Broadstone) Tank and the East Tank No.1. The Zone 4
Tank rehabilitation will include draining and cleaning, targeted micro-abrasive sandblasting to expose
structural members, structural engineering inspection
and report preparation, spot repairs, retrofit of a roof- mounted THM mixer and blower, and associated
electrical and controls upgrade work. Site work shall be completed as needed to support the electrical and
blower upgrades. The East Tank No. 1 improvements
will consist of the THM mixer and blower scope only. The THM mixers and venting improvements will reduce the
formation of THMs in the tanks, assist with water age and turnover, and improve water quality.

The scope of services requested by this RFP includes investigation, detailed design, bid phase engineering support, construction phase engineering support, tank condition assessments during construction, CM&I services. A lesson learned during the Tower Tank Rehabilitation Project was that tank interior condition can be significantly worse than expected, even if a pre-construction corrosion inspection is performed, partly because existing coatings can hide significant structural member corrosion. The City had inspections of these tanks which noted corrosion, but the degree is difficult to discern under the existing coatings. HydroScience reviewed the inspection report provided. It supports the City’s strategy and schedule for inspection and ultimate rehabilitation of the tank interior.

The City’s approach to this project bundles the detailed structural inspection into the construction phase, leveraging the planned tank outage and the ability to have the contractor strategically remove coatings in inspection areas. HydroScience believes this is the most effective means to obtain a meaningful condition assessment that can guide further repairs if needed.

The City has planned for more extensive repairs of these tanks in a future CIP project in 3-5 years time.

Based on recent experiences on the Tower Tanks Rehabilitation Project, there is potential that the level of corrosion found on these tanks during the structural inspection may be more severe than expected.

Such a finding would increase the urgency of repairs and likely result in the City moving full rehabilitation of these tanks up the priority list. We further understand that other improvements may be added to the design and rehabilitation scope to bring these tanks up to current City standards. These could include:

Given the HydroScience Team’s experience
on the ongoing Tower Tanks Rehabilitation
Project, where more extensive repairs were
implemented to address unexpected severe
corrosion (see photo), this team is well-
positioned to pivot quickly to any level of
rehabilitation design and construction
required to restore the condition of the Zone
4 Phase 1 (Broadstone) tank.

Page 174 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 4 of 12 ends

Broadstone/Z4
• Water quality monitoring system
• Diver cleanouts
• Stairs
• Level gauge/transmitter enclosures
• Relocate tank outlet above-grade
East Tank No. 2
• Blower/mixer system and curb modifications
• Diver cleanouts

HydroScience demonstrated its effectiveness in helping the City respond to similarly urgent needs on the Tower Tank Rehabilitation Project. This experience positions us to respond quickly should this project see a similar outcome. We are prepared to quickly scope and execute design of any required repairs and incorporate it into this or a future bid package for expedited implementation in the next winter season.

The City provided as-built drawings for both tanks and typical mounting details for the THM mixer system. HydroScience reviewed these documents and considered our understanding of the City’s water distribution system and our experience on recent City projects, particularly the Tower Tank Rehabilitation Project, and similar tank projects in the preparation of this proposal.

The City needs bid documents ready by August 1, 2026 with the goal of construction occurring between October 2026 and April 2027 during the low demand winter season when both tanks can be offline. If necessary, project improvements not tied to the shutdown of a tank (electrical, controls, drainage, etc.) can be constructed during higher demand periods in dry weather.

HydroScience will develop and regularly update a detailed Microsoft Project schedule with all major activities and task interdependencies. At the conclusion of design, the schedule will feed into the preparation of detailed Division 01 specifications describing construction sequencing and constraints and establishing the number of contract days. HydroScience has included a preliminary version of this schedule in accordance with the RFP (Attachment B) illustrating the anticipated design and construction schedule, with the construction schedule depicting how construction may be phased and sequenced for each tank including outage time, draining, inspection, repairs, and restoration of service.

The CM&I proposal is based on the durations shown.

The removal of tanks from service will require careful advance planning and close coordination with City Water System Operations. HydroScience will identify constraints, prerequisite activities, risks, and risk mitigations early in the project and track these as the project definition develops. This tracking will drive critical project decisions and inform the preparation of notes and contract requirements for the contractor to closely adhere to and the construction manager to enforce. Similarly, given the proximity of the tanks to parks and residences, the specifications will carefully describe construction constraints to minimize noise and disruption.

Page 175 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 5 of 12 ends

Scope of Services
We developed this scope based on a review of the RFP, our experience with tank construction and retrofit, and our understanding of City standards and practices from our recent work on similar projects at the City. All deliverables will be in PDF format. Native editable file formats will also be provided with final deliverables.

Task 1 – Project Management and Coordination
Eric Jones will be responsible for the overall project management efforts necessary to oversee and direct the work of the project team. Bill Slenter will provide oversight, resource allocation, and serve as a contractual contact. This task is divided into four subtasks which include general project management (tracking and management of decisions, schedule, budget), project communications with the City and other stakeholders, quality assurance and quality control, and project meetings during the predesign and design phases (construction phase meetings are addressed separately in Tasks 5 & 6). These subtasks are detailed below. Project management activities will be carried throughout all of the project phases (Preliminary Engineering, Design, Bidding, and Construction).

A. Project Management: HydroScience will prepare and maintain a project decision log that records design decisions. This log will include summaries of the decisions made, any key items used to reach those decisions, and any other relevant information. HydroScience will work with the City and stakeholders to settle upon key project decisions early in the project to facilitate efficient progression through the remaining detailed design steps.

The Project Manager will conduct monthly reviews and updates of schedule, design expenditures, and progress. The status of these items will be reported to the City with each monthly invoice. The Project Manager will make internal adjustments as required to comply with the requirements of the services agreement. The Project Manager will identify any external risks to schedule or budget and propose appropriate adjustments to keep the project on track. HydroScience will coordinate the schedule of this project to target bidding and construction in accordance with the City’s scheduling needs.

B. Project Communications: Standing monthly project status conference calls between the City and HydroScience will be held to discuss ongoing coordination items, review project schedule and progress, review the decision log, and address any other project related items as they arise. HydroScience will prepare monthly invoices and project status reports outlining the team’s progress on the project tasks and discuss them with the City's Project Manager. These reports will include budget and work progress updates, work performed during that time period, activities completed, milestones achieved, project schedule status, any issues and proposed resolutions.

C. Quality Assurance and Quality Control: HydroScience will provide quality control and quality assurance (QA/QC) of all submittals prior to City review and in accordance with company policy.

Formal internal review will occur prior to submittal of each major deliverable to provide an objective check on the adequacy of the documents. Principal level staff not directly involved in preparation of the work product will complete these reviews. Internal review comments will be discussed with the product’s author and resolved as appropriate prior to finalizing the draft document. City review comments on draft documents will be responded to in writing and resolved as appropriate. City comments and HydroScience responses will be tracked in a formal comment log.

Page 176 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 6 of 12 ends

D. Project Meetings: Three design phase project meetings will occur including the kickoff meeting and two design progress meetings with City staff scheduled to coincide with submittal of the 50% design and 100% design, to make efficient use of the City's available staff time. For all meetings, HydroScience will be responsible for confirming attendance, preparing the agenda, documenting the meeting minutes, and coordinating action items.

During the kickoff meeting, HydroScience will meet with the City to confirm the project goals and objectives, establish lines of communication, review the project scope and schedule, collect the existing information, and receive City input.

Deliverables:
• Project decision log, updated regularly (PDF)
• Project status reports, submitted monthly with invoices (PDF) • Meeting agenda and minutes (Word)
• City comment log with HydroScience responses, updated at each design submittal (Excel) Task 2 – Preliminary Engineering
HydroScience shall complete the following:

Schedule: Prepare, drive, and maintain a detailed critical path master schedule and roll-up schedule summary throughout the contract period and monitor progress on team activities relative to the schedule. The schedule will be updated at each milestone to reflect any modifications.

Field Investigation: Visit the project sites and meet with City engineering and operations staff. The investigation will identify conditions in the field, note site access and constructability issues, note potential interferences, identify construction access, and identify areas requiring further investigation.

Key areas of concern or project priority areas shall be examined to aid design feasibility and identify possible design alternatives. This can occur on the day of the Kickoff Meeting.

Documentation Review: Review as-builts and any available inspection documentation on existing tank conditions.

CEQA: HydroScience will prepare technical content for the California Environmental Quality Act (CEQA) Documentation with the assumption that the project qualifies for Categorical Exemption.

HydroScience will prepare the project description and complete the Notice of Exemption (NOE) for the City to file.

Preliminary Engineering: HydroScience will confirm the design objectives and criteria with the City.

HydroScience will prepare a preliminary construction sequencing plan and schedule. There are no plans or specifications deliverables in this phase. These will be produced in Task 3.

Deliverables:
• Project schedule, with periodic updates issued monthly and as needed (PDF) • Utility coordination "A" letters
• Sequencing plan outline (PDF)
• CEQA Notice of Exemption documentation for City filing (PDF, Word) • Preliminary construction schedule (PDF)

Page 177 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 7 of 12 ends

Task 3 – Design Phase Services
HydroScience shall complete the following:

Plans, Specifications, and Estimate: HydroScience will complete the 50%, 100%, and Bid Ready submittals. For each submittal, HydroScience will prepare the plans, technical specifications, and the engineer's opinion of probable cost. Comments on each submittal will be incorporated into the subsequent submittal, and a response to comments will be prepared documenting how HydroScience responded to each comment.

The City's standard front-end specifications (general provisions, special provisions, proposal forms, and contract agreement) will be used similar to previous projects that HydroScience has completed with the City. Internal QA/QC (see Task 1) will be applied to each submittal prior to submittal to the City.

HydroScience will submit plans and specifications to the City Engineer, EWR, and Public Works for review as appropriate. Comments received from City departments will be compiled into a comment log and responses will be entered into the same log and distributed with the revised documents.

HydroScience will assist the City with required updates to the water system permit from DDW, assuming one is required. This will consist of filling out a one page form and submitting it with plans and specifications.

Deliverables:
• 50%, 100%, and Final Bid Documents Submittals: plans, specifications, and engineer’s opinion of probable construction costs (PDF). Final includes one full size stamped and signed plan set in PDF format. AutoCAD drawings of the plans. One PDF and Word copy of the specifications. PDF of the final engineer’s opinion of probable construction costs. Native Word and AutoCAD files.

Assumptions:
• Most of the improvements will be located above grade. A geotechnical report is not required to support the design, though any prior reports or boring data provided by the City will be considered. • Potholing will not be performed during the design phase. If appropriate, plans will identify recommended potholing to be performed by the Contractor during Construction and the project budget includes a design allowance for limited design modifications required based on the potholing results.
• Cathodic protection (CP) evaluation or design services not included. • Corrosion engineering services not included but can be optionally obtained as a scope modification. • Existing power utility service and main switchboard at each site has capacity for the THM mixer/blower system without upgrade.
• Topographical surveying not included. Scope assumes design will be performed utilizing traced or scanned as-built drawings and photos as backgrounds. Civil work will be minor and not require precise elevations.
• Base bid construction services includes one construction season where the tanks can be offline.

Page 178 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 8 of 12 ends

• No tank modifications that require recoating are required to install the THM blower/ mixer at East Tank No. 1. The required penetrations and supports are already in place.

Task 4 – Bid Phase Services
HydroScience will attend the pre-bid meeting with the City and provide any technical support required to respond to technical questions from prospective bidders submitted during the bidding phase. Bidding services will include interpreting construction documents, responding to questions posed by the bidders and preparing clarifications and up to three addenda. All communications will be directed through the City. HydroScience will, if necessary, prepare a conformed set of plans to incorporate all addenda issued during the bid phase for up to three bid drawing sheets.

Deliverables:
• Response to bidder inquiries as required (Word)
• Up to 3 addenda – (PDF, Word)
• Up to 3 conformed to bid drawings sheets incorporated into one full conformed set and plans and specifications (PDF, Word, DWG)
Task 5 – Construction Phase Services
HydroScience staff will provide continued support during the construction phase of the project. Project staff will be available to provide the following services:
• Meetings: HydroScience will attend regular construction meetings (16 total, 3 in person) • Site Visits: HydroScience will make up to three site visits during construction. • Submittal Review: HydroScience will receive, and review submittals as directed by the City. Up to 40 submittals will be reviewed by HydroScience with up to 20 resubmittals. • RFI Response: HydroScience will receive and respond to Contractor RFIs during the period of construction as directed by the City. HydroScience will respond to up to 20 RFIs. • Design Modifications: Design modifications (allowance) relating to the potholing results, and/or for other unknown changes upon request (up to 3 items, up to the total number of hours shown in the fee).
• Project Coordination: HydroScience will review up to two Preliminary Change Order requests, and will make recommendations to the City for issuing Contract Change Orders in accordance with the project specifications.
• Startup and Testing: HydroScience will provide the following support services: review of start-up plans submitted by the contractor, make up to two site visits during on-site testing • Project Closeout: Assist the City in the preparation of the project punch lists, and will participate in the final inspection.
• Record Drawings. HydroScience will prepare project record drawings depicting “as-built” conditions based on the Contractor’s submitted redline markups.

HydroScience will retain VE Solutions, a California-licensed Structural Engineer, to perform a structural evaluation of corroded roof framing members at the Zone 4 Tank and to prepare a signed and sealed structural engineering report, as summarized below:

Page 179 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 9 of 12 ends

• Perform review of available record documents, including original design drawings, previous inspection reports (if available), and photographic documentation. • Coordinate with the Contractor to perform the assessment after the tank has been drained, cleaned, and required scaffolding has been installed.
• Perform a structural evaluation of corroded roof framing members (e.g., beams, girders, and columns) to assess remaining effective section after corrosion. • As appropriate and at the Structural Engineer’s discretion, determine remaining member thickness using an ultrasonic thickness measuring device, hand caliper, and/or visual estimate. • Perform structural analysis sufficient to classify evaluated members using a tiered findings approach: Tier 1 (immediate-action / current code non-compliance), Tier 2 (repair recommended in current offline window), Tier 3 (monitor and plan), and Tier 4 (acceptable). • Prepare a structural engineering report documenting the evaluation results, including photographic documentation of significant conditions.
• Provide recommendations for rehabilitation and replacement items, and recommended reassessment intervals, as supported by the evaluation findings. • Provide an estimated remaining serviceable life of evaluated components, per stated methodology, assumptions, and limitations.
• Provide final report documents signed and sealed by a California registered Structural Engineer. • Exclusions (by others): Scaffolding and removal of existing coatings to access framing members (including spot coating repair after removal); and construction/bid documents suitable for bidding or construction of repairs.

Deliverables:
• Responses to submittals – up to 40 submittal responses in format selected by Construction Manager
• RFI Responses – up to 20 RFI responses in format selected by Construction Manager • Up to three design modifications plans.
• Record Drawings – One full size reproducible drawing set and electronic version in AutoCAD and PDF (AutoCAD drawings will have stamps removed).
• Tank assessment report, PDF

Task 6: Construction Management and Inspection Services HydroScience will provide CM&I services through our pre-qualified subconsultant, West Yost. West Yost’s CM&I services shall be as follows:
• Construction coordination: Coordinate construction activities with the City, Contractor, HydroScience design team, and other project stakeholders; support implementation of sequencing requirements and tank outage constraints; and manage interfaces between work at the two tank sites.
• Weekly construction meetings: Conduct weekly construction meetings, prepare agendas and minutes, track action items, and distribute meeting documentation. • RFI and submittal management: Receive, log, track, and process RFIs and submittals in coordination with the City and HydroScience; monitor response status and maintain the project correspondence and document control system.

Page 180 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 10 of 12 ends

• Construction observation/inspection: Provide construction observation and inspection services to monitor general conformance with the contract documents. • Health and safety awareness: Maintain awareness of site safety practices and communicate observed safety concerns to the Contractor and City in accordance with standard CM practices (recognizing Contractor responsibility for site safety). • Material testing / special inspections: Coordinate required material testing and special inspection services, coordinate third-party testing and inspection documentation and follow-up on corrective actions.
• Change order, changes, and claims management: Evaluate and negotiate potential change orders, and maintain logs to track change requests, status, and impacts. Proactively identify, document, and track potential claims and changes throughout the construction process. Review Contractor-submitted claims for merit, validity, and compliance with contract requirements.

Coordinate with the City and project team to evaluate impacts, negotiate resolutions, and document outcomes. Maintain thorough records of all claims-related correspondence and decisions to support timely and equitable resolution.
• Progress payments: Review Contractor pay applications for completeness and general consistency with observed progress and contract requirements; assist the City with progress payment processing.
• Labor compliance: Support labor compliance administration and coordination consistent with the City’s requirements and applicable regulations.
• SWPPP compliance: Monitor SWPPP implementation and BMP maintenance for general conformance and coordinate with the Contractor/City regarding observed deficiencies and needed corrective actions.
• Project closeout: Manage project closeout activities including punch list development and tracking, final inspections, acceptance recommendations, coordination of final documentation (O&M manuals, training, warranties, test reports), and support to startup/testing activities as needed.

The CM&I budget is based on the included preliminary schedule (Attachment B) and following scoping assumptions:
• Projected Notice to Proceed: 9/18/2026
• Anticipated construction completion: 1/29/2027 (about 95 working days) • Staffing levels will be adjusted based on Contractor’s approved schedule and field requirements.

Budgets were developed based on the following average weekly staffing levels:
• 10 CM hours per week
• 28 inspector hours per week
• 5 CM administrative hours per week

Materials testing: West Yost will retain Crawford & Associates to perform materials testing up to the budget amount shown in the fee.

Page 181 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 11 of 12 ends

Coatings inspection: Bay Area Coatings Consultants, under contract with HydroScience, will provide daily Quality Assurance (QA) coating inspection and documentation for the exterior coating operations of repairs at Zone 4 Tank and East Tank No. 1 as follows:
• Surface Preparation: Verification of cleanliness and profile in accordance with specified SSPC/AMPP standards.
• Environmental Conditions: Monitoring ambient conditions to confirm compliance with application requirements.
• Coating Application: Observation of application methods, workmanship, and stripe coating. • Film Thickness: Dry Film Thickness (DFT) measurements per SSPC-PA 2. • Cure/Recoat: Verification of cure and recoat windows, including solvent rub testing as required. • Holiday Testing: Verification of coating continuity and repair of discontinuities. • Documentation: Daily reports including inspection results, environmental conditions, and photographic documentation.
• Non-Conformance: Identification and reporting of work not in compliance with project requirements.

Services will follow applicable SSPC/AMPP, ASTM standards, manufacturer requirements, and project specifications.

Deliverables
• Weekly construction meeting agendas and meeting minutes • Project correspondence and document control records
• Daily inspection reports documenting observed work, site conditions, and non-conforming work • Materials testing and special inspection reports
• Non-conformance reports and corrective action tracking (as required) • Change order and change request logs, including evaluation memoranda and recommendations • Claims and disputes documentation, including correspondence and resolution records (if applicable)
• Progress payment review documentation and payment recommendation summaries • Labor compliance tracking documentation (as required by the City) • SWPPP compliance observation notes and deficiency tracking • Punch list documents and punch list tracking logs
• Final inspection documentation and acceptance recommendations • Project closeout checklist and closeout documentation coordination (As-built drawings, O&M manuals, warranties, test reports, training confirmation) Scope Assumptions, Exclusions, and Notes
• The scope of improvements to each tank are as described on Pages 1-2 of the City’s RFP as clarified by City via email.

Page 182 ends

06/09/2026 Item No.9.

May 8, 2026
Design and Engineering Services During Construction for the City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project

Page 12 of 12 ends

• Mixers will be provided with local on/off control for operations. Automation of the mixers is not included.
• Scope does not include a new geotechnical investigation. Any available past reports/data will be reviewed by HydroScience if provided.
• P&IDs are not included in the design and are considered unnecessary. • Sufficient power capacity and spare breaker capacity exists at all sites for the addition of mixers and other powered improvements specified in the RFP.
• The entire project will be bid as one construction package with one set of bid documents. • Rights of way and easement acquisitions are not required. • Potholing is not included in this scope. Required potholes will be identified in the contract documents and completed by the contractor.

Project Schedule
HydroScience anticipates completing the design phase in accordance with the preliminary schedule provided in Attachment B. All external reviews will need to be accelerated to meet the schedule.

Proposed Fee
The proposed fee schedule for these services has been provided to the City as a separate document per the RFP instructions.

HydroScience appreciates the opportunity to propose our services to the City. I can be contacted at (916) 605-6633 or [email protected] if you have any questions regarding this proposal.

Sincerely,
HYDROSCIENCE ENGINEERS, INC.

Bill Slenter, P.E.

Principal
Attachments:

A. Resumes
B. Preliminary Project Schedule
C. Fee Spreadsheet (Bound Separately)

Page 183 ends

06/09/2026 Item No.9.

EDUCATION
B.S., Mechanical Engineering
(Environmental Engineering
emphasis), University of
California, Santa Barbara

REGISTRATION
Civil Engineer, California,
Registration No. 68550

SELECT PROJECT EXPERIENCE
Eric is a project manager, construction manager and project engineer with 26 years of experience in water, wastewater, and recycled water facility planning, design and construction assistance. His specific areas of focus have included pump station de- sign, pipeline design including trenchless technologies, water and wastewater treat- ment design, feasibility studies and construction management. He has played key roles in several design and construction services teams for many projects throughout California and Australia. Eric has significant experience with rehabilitation and up- grade of existing wastewater treatment plants, including complex coordination with electrical design.

Folsom Tower Tank Rehabilitation
City of Folsom, California
Project Manager. This project involves the re-
habilitation and operational improvements of
five potable water storage tanks in the City of
Folsom, addressing compliance, safety, and
functionality needs. Two tanks require up-
grades to meet California Division of Drinking
Water (DDW) standards. Challenges include
a four-month design window and strict se-
quencing during low-demand winter months
to maintain system operations. Improve-
ments to the Tower Tank include structural
modifications (vent, rafters, bracing), a stair -
case replacing the ladder, safety upgrades, a
THM reduction mixer, and electrical, SCADA,
and utility enhancements, along with antenna
relocation, drainage, sampling, coatings, and
a cathodic protection system. East Tank #2
upgrades focus on overflow, drain, and vent
modifications, exterior coating repairs, and
drainage adjustments to meet DDW compli-
ance. Foothills Tanks (1 & 2) improvements
include staircases, a catwalk bridge, safety
anchors, THM mixers, access upgrades,
monitoring cabinets, and SCADA and electri-
cal updates, along with coatings and a pre-
fabricated canopy. The South Tank upgrades
involve overflow, drain, and vent modifica-
tions, exterior repairs, and drainage improve-
ments, ensuring compliance and operational
efficiency.

Folsom FPA and FSAG Pipeline and
Pump Station
City of Folsom, California
Design Support. The Folsom South Area
Group (FSAG) Transmission Pipeline is re-
quired to supply the Folsom Plan Area (FPA)
with water as it approaches the buildout
phase. All water supply to the FPA is from the
City of Folsom through upgrades and exten-
sions of existing infrastructure. The 3.5 mile,
24-inch transmission pipeline associated with
this project extends under Highway 50 to a
new booster pump station (BPS) located at
the City’s Water Treatment Plant. The new
BPS is planned to have 8,700 gpm firm capac-
ity, 6 vertical turbine pumps, a standby gen-
erator, new power transformer, and a surge
tank. HydroScience completed the 100% de-
sign for the project and is currently rephas-
ing the project in coordination with the CIty.

HydroScience also rephased the project to
improve Z3 hydraulics and provide hydraulic
benefits to the Z3 system north of Highway

50. Major design elements included rout-
ing the new pipeline through sensitive public
rights-of-way that are outside of the roadway,
the trenchless crossing of two creeks, co-
ordination of the pump station design with
existing WTP operations, and significant re-
grading to improve site drainage along East
Bidwell St.

Ashland Water Pipeline Rehabilitation
Project II
City of Folsom, California
Project Manager. This project consisted of
improvements to allow for abandonment of
an existing water main by extending 6 exist-
ing branch mains, replacing 22 water services
and replacing 3 fire hydrant service and con-
nection the new and extended services to an
existing parallel active 14-inch water main lo-
cated along Baldwin Dam Road. The project
also included slurry seal of the entire roadway,
evaluation of the benefits for providing a new
PRV station, and demolition of an existing
Eric Jones, PE
Project Manager

ATTACHMENT A - RESUMES

Page 184 ends

06/09/2026 Item No.9.
vacant pump station. Once completed the existing transmission line provided fully isolated section of main between all branch tie-ins. HydroScience incorporated many measures in design to minimize disruption to customers, including hot tap sleeves for connecting new service to the active ACP and steel pipe- line. Outage maps were provided to the Contractor as an at- tachment to the specifications for each of the planned outages.

These maps showed exactly which customers and fire hydrants would be affected by the outage to help the contractor coordi- nate the notification process during construction.

Red Hawk Wastewater and Recycled Water
Improvements
Shingle Springs Rancheria, El Dorado County, California Project Engineer. HydroScience designed a new membrane
bioreactor (MBR) wastewater treatment plant, recycled water pumping, and effluent disposal systems for Red Hawk Casino.

These facilities were commissioned in 2009. Red Hawk retained HydroScience in 2020 to evaluate and design upgrades to sup- port expansion of the resort with a new hotel and entertainment facilities. Upgrades included two new 3.0 million gallon welded steel tanks, a new recycled water booster pump station with two VFD-driven 75-hp vertical turbine pumps, upgrade of existing chlorine contact basin effluent pumps, improvements to the existing sewer lift station, and a new coarse screening facility.

The project is currently in the later stages of construction. The project was implemented as a collaborative delivery (progres- sive design-build) arrangement and involved significant coordi- nation with the facility operator.

Griffith Water Reclamation Plant Upgrade Concept
Design
Griffith City Council, New South Wales, Australia
Project Engineer. HydroScience was retained by the City of Griffith to design a 2.8 MGD municipal MBR WWTP . The new plant was designed to produce recycled water to supply the City’s ambitious recycled water program. Design features in- cluded use of the existing primary sedimentation tanks to peak wet weather flows. Other design features included a 4 train membrane bioreactor, UV disinfection system, sludge dewa- tering building, operations building, and SCADA control sys- tem. HydroScience services also included commissioning and start-up.

Ashland Water Pipeline Rehabilitation Project I
City of Folsom, California
Project Manager. This project rehabilitates 1,500 linear feet of an existing 20 and 21-inch water transmission pipeline with ductile iron and fusion bonded epoxy steel pipe using open- cut construction and trenchless rehabilitation technologies of the existing pipeline. SCADA was added to an existing PRV station, and miscellaneous replacements of failed valves. The project required coordination with USBR to obtain a temporary construction easement for rehabilitation of the pipeline within USBR property.

Willow Hill Pipeline Rehabilitation
City of Folsom, California
Project Engineer (Phases 1 & 2) / Construction Manager (Phase 2). This project included assessment, preliminary design, final design, construction engineering, construction management, and inspection services for rehabilitation of a 20,585 LF exist- ing raw water main (30- to 48-inch diameter RCP) and potential conversion of that main to future potable water pressure service.

The project included both rehabilitation and realignment seg- ments. The preliminary design included preparation of technical memoranda (TMs) for predesign criteria development and hy- draulics, condition assessment, rehabilitation technology/meth- ods and rehabilitation/alignment assessments. Final design in- cluded realignment using HDPE and fusible PVC pipe as well as HDPE sliplining. Construction management and inspection services included daily field presence at the worksite, written and photographic documentation, pay request and change or - der processing, issue resolution, inspection, City coordination, and property owner coordination. Specific services provided by Eric include design and preparation of final construction docu- ments, including plans, specification and engineer’s opinion of probable cost and fulfilling the role of construction manager during construction and some inspection services. Construction management duties include establishing an electronic, cloud- based construction document tracking, filing, and communica- tion system, evaluate potential change orders to provide recom- mendations to the City, lead any negotiation process with the City and Contractor, coordinate and review contractor progress payment, review contractor’s schedule, serve as a central coor - dination role with all project parties including coordinate con- struction activities with stakeholder agencies and lead weekly meetings, prepare project punch list, schedule inspection ser - vices, review and finalize daily field reports and review and si- gnoff on extra work orders.

Folsom Ashland PRV Project
City of Folsom, California
ESDC / Project Engineer. HydroScience designed improve- ments and modifications to three existing Pressure Reducing Valve (PRV) stations on the City’s water distribution system.

Tasks included the removal and retirement of one PRV station, the relocation of one PRV station to a separate system, the re- configuration of hydrants as blowoffs for system flushing, raising the PRVs above grade to eliminate immersion potential, and the replacement of an isolation valve between two zones with an above-grade PRV station. All designs were completed in accor- dance with CDPH requirements. Specific services provided by Eric included design and preparation of the final construction documents and engineering services during construction.

Eric Jones, PE

Page 185 ends

06/09/2026 Item No.9.

EDUCATION
B.S., Civil Engineering, San
Francisco State University

REGISTRATION
Civil Engineer, California,
Registration No. 57640

AFFILIATIONS
California Water Environment
Association (CWEA)
Central Valley Clean Water
Association – Outreach
Committee Chairperson
Former Chairperson, CWEA
San Francisco Bay Section
Communications Committee
CWEA Sacramento Area
Section

SELECT PROJECT EXPERIENCE
Bill is a civil engineer with 34 years of experience. His areas of expertise include per - mitting, funding, planning, design, and construction support of wastewater, water, and recycled water systems. A principal with HydroScience, he has served as principal, project manager and project engineer on a wide range of water-related projects.

Folsom Tower Tank Rehabilitation
City of Folsom, California
Principal-in-Charge. This project involves
the rehabilitation and operational improve-
ments of five potable water storage tanks in
the City of Folsom, addressing compliance,
safety, and functionality needs. Two tanks re-
quire upgrades to meet California Division of
Drinking Water (DDW) standards. Challenges
include a four-month design window and
strict sequencing during low-demand winter
months to maintain system operations. Im-
provements to the Tower Tank include struc-
tural modifications (vent, rafters, bracing),
a staircase replacing the ladder, safety up-
grades, a THM reduction mixer, and electri-
cal, SCADA, and utility enhancements, along
with antenna relocation, drainage, sampling,
coatings, and a cathodic protection system.

East Tank #2 upgrades focus on overflow,
drain, and vent modifications, exterior coat-
ing repairs, and drainage adjustments to
meet DDW compliance. Foothills Tanks (1 &
2) improvements include staircases, a catwalk
bridge, safety anchors, THM mixers, access
upgrades, monitoring cabinets, and SCADA
and electrical updates, along with coatings
and a prefabricated canopy. The South Tank
upgrades involve overflow, drain, and vent
modifications, exterior repairs, and drainage
improvements, ensuring compliance and op-
erational efficiency.

Ashland Water Pipeline Rehabilitation
Project II
City of Folsom, California
Principal-in-Charge. This project consisted of
improvements to allow for abandonment of
an existing water main by extending 6 exist-
ing branch mains, replacing 22 water services
and replacing 3 fire hydrant service and con-
nection the new and extended services to an
existing parallel active 14-inch water main lo-
cated along Baldwin Dam Road. The project
also included slurry seal of the entire roadway,
evaluation of the benefits for providing a new
PRV station, and demolition of an existing va-
cant pump station. Once completed the ex-
isting transmission line provided fully isolated
section of main between all branch tie-ins.

HydroScience incorporated many measures
in design to minimize disruption to custom-
ers, including hot tap sleeves for connect-
ing new service to the active ACP and steel
pipeline. Outage maps were provided to the
Contractor as an attachment to the specifica-
tions for each of the planned outages. These
maps showed exactly which customers and
fire hydrants would be affected by the outage
to help the contractor coordinate the notifica-
tion process during construction.

Water Treatment and Storage Facility
Lytton Rancheria, Sonoma County, California
Principal-in-Charge and QA/QC.

HydroScience is providing design engineer -
ing and engineering support of construc-
tion for new groundwater wells, groundwa-
ter treatment, treated water storage, and
booster pumping facility to serve the Lytton
Rancheria Project, a tribal residential devel-
opment located near Windsor, CA. HydroSci-
ence’s role is design engineer-of-record as
part of a design/build project team. The fa-
cility will produce an average day flow of ap-
proximately 120K gpd at buildout. New wells
will deliver raw water to a water treatment sys-
tem to reduce concentrations of arsenic and
manganese in the groundwater to below pri-
mary maximum contaminant levels. The treat-
ment process will include pH adjustment, oxi-
dation, coagulation/filtration, post-filtration
adsorption, and backwash thickening. Dosing
of sodium hypochlorite followed by storage
in on-site welded steel storage tanks will fol-
low. A booster pump station consisting of
banks of low and high flow pumps followed
by a hydropneumatic tank will deliver water
Bill Slenter, PE
Principal-in-Charge

Page 186 ends

06/09/2026 Item No.9.
to the distribution system for residential demands and fire flows.

The treatment and pumping equipment will be housed in a new CMU building, which will also contain an operations office, lab, power distribution, and control systems. The design phase has been completed and HydroScience will provide construction phase support including review of RFIs and submittals, field vis- its, and commissioning support.

Red Hawk Wastewater and Recycled Water
Improvements
Shingle Springs Rancheria, El Dorado County, California Project Manager. HydroScience designed a new membrane
bioreactor (MBR) wastewater treatment plant, recycled water pumping, and effluent disposal systems for Red Hawk Casino.

These facilities were commissioned in 2009. Red Hawk retained HydroScience in 2020 to evaluate and design upgrades to sup- port expansion of the resort with a new hotel and entertainment facilities. Upgrades included two new 3.0 million gallon welded steel tanks, a new recycled water booster pump station with two VFD-driven 75-hp vertical turbine pumps, upgrade of existing chlorine contact basin effluent pumps, improvements to the existing sewer lift station, and a new coarse screening facility.

The project is currently in the later stages of construction. The project was implemented as a collaborative delivery (progres- sive design-build) arrangement and involved significant coordi- nation with the facility operator.

Folsom Ashland PRV
City of Folsom, California
Principal-in-Charge. HydroScience designed improvements and modifications to three existing Pressure Reducing Valve (PRV) stations on the City’s water distribution system. Tasks included the removal and retirement of one PRV station, the relocation of one PRV station to a separate system, the reconfiguration of hydrants as blowoffs for system flushing, raising the PRVs above grade to eliminate immersion potential, and the replacement of an isolation valve between two zones with an above-grade PRV station. All designs were completed in accordance with CDPH requirements.

Folsom Plan Area PRV
City of Folsom, California
Principal-in-Charge. The PRV Stations project is part of the ini- tial infrastructure phase to provide potable water distribution system pressure and flow regulation for the Folsom Plan Area (FPA). HydroScience provided preliminary design, final design, and engineering services during bidding and construction for four pressure reducing valve stations (PRV stations), utility and agency coordination, and pipe stub-outs for connection by others to the FPA water supply system. The PRV stations de- sign includes a magnetic flowmeter; and above-ground valve manifolds in insulated enclosures with a separate PRV sized for domestic and fire use.

Ashland Water Pipeline Rehabilitation Project I
City of Folsom, California
Principal-in-Charge. This project rehabilitates 1,500 linear feet of an existing 20 and 21-inch water transmission pipeline with ductile iron and fusion bonded epoxy steel pipe using open- cut construction and trenchless rehabilitation technologies of the existing pipeline. SCADA was added to an existing PRV station, and miscellaneous replacements of failed valves. The project required coordination with USBR to obtain a temporary construction easement for rehabilitation of the pipeline within USBR property.

Hinkle Creek Pipeline Rehabilitation
City of Folsom, California
Principal-in-Charge. HydroScience was retained to provide con- struction management, inspection, and engineering expertise for the rehabilitation of 5,200 LF of 6- to 10-inches vitrified clay gravity sewer main utilizing Cured-In-Place-Pipe (CIPP) trench- less pipeline rehabilitation technology. The work was conducted in a sensitive corridor adjacent to Hinkle Creek and the back- yards of homes. Bypass pumping during sewer lining was care- fully managed to prevent spills and maintain continuous service.

The project also included repair of 25 manholes, installation of six flow level monitoring systems that included SCADA integra- tion, and a complete creek bypass. HydroScience conducted a peer review of the CIPP technical specifications prior to contract bidding, and quickly respond to issues that arose throughout construction.

Willow Hill Pipeline Rehabilitation
City of Folsom, California
Principal-in-Charge for HydroScience. This project included assessment, preliminary design, final design, construction en- gineering, construction management, and inspection services for rehabilitation of a 20,585 LF existing raw water main (30- to 48-inches diameter RCP) and potential conversion of that main to future potable water pressure service. The project included both rehabilitation and realignment segments. The preliminary design included preparation of technical memoranda (TMs) for predesign criteria development and hydraulics, condition as- sessment, rehabilitation technology/methods and rehabilita- tion/alignment assessments. Final design included realignment using HDPE and fusible PVC pipe as well as HDPE sliplining.

Construction management and inspection services included daily field presence at the worksite, written and photographic documentation, pay request and change order processing, is- sue resolution, inspection, City coordination, and property own- er coordination.

Bill Slenter, PE

Page 187 ends

06/09/2026 Item No.9.

Austin Poulson
Project Engineer

EDUCATION
B.S., Civil Engineering,
California State University,
Sacramento

SELECT PROJECT EXPERIENCE
Austin has 11 years of engineering design experience, including the design of waste- water and water treatment systems, sewer lift stations, sewer and water pipelines, booster pump stations, water storage tanks, site drainage, grading and paving, and fire protection systems. He has also served as a construction manager on fire protec- tion projects. Austin’s capabilities include site civil design in AutoCAD Civil3D and encompasses grading, paving, drainage, and design of retention basins.

Folsom Tower Tank Rehabilitation
City of Folsom, California
Project Engineer. This project involves the re-
habilitation and operational improvements of
five potable water storage tanks in the City of
Folsom, addressing compliance, safety, and
functionality needs. Two tanks require up-
grades to meet California Division of Drinking
Water (DDW) standards. Challenges include
a four-month design window and strict se-
quencing during low-demand winter months
to maintain system operations. Improve-
ments to the Tower Tank include structural
modifications (vent, rafters, bracing), a stair -
case replacing the ladder, safety upgrades, a
THM reduction mixer, and electrical, SCADA,
and utility enhancements, along with antenna
relocation, drainage, sampling, coatings, and
a cathodic protection system. East Tank #2
upgrades focus on overflow, drain, and vent
modifications, exterior coating repairs, and
drainage adjustments to meet DDW compli-
ance. Foothills Tanks (1 & 2) improvements
include staircases, a catwalk bridge, safety
anchors, THM mixers, access upgrades,
monitoring cabinets, and SCADA and electri-
cal updates, along with coatings and a pre-
fabricated canopy. The South Tank upgrades
involve overflow, drain, and vent modifica-
tions, exterior repairs, and drainage improve-
ments, ensuring compliance and operational
efficiency.

Folsom Zone 3 and Zone 4 Potable
Water Storage Tanks – Conceptual
Design and Zone 3 Phase 1 Final
Design
City of Folsom, California
Project Engineer. Both the Zone 3 and Zone
4 storage tanks will be located within the
newly developed Folsom Plan Area (FPA).

The Zone 3 distribution system will be served
at buildout by two tanks, each partially bur -
ied AWWA D110 prestressed concrete tanks
with an operating volume of 3 million gallons
(MG). The Zone 4 tank will be an above grade
AWWA D110 prestressed concrete tank with
an operating volume of 2 MG. The Zone 3
tanks will receive water from the FPA/FSAG
transmission pipeline and may also feed the
Zone 4 tank. The Conceptual Design phase
evaluated each zone’s tank and site layouts
within City-owned parcels and established
preliminary design criteria. Both Zone 3 and 4
conceptual design information were present-
ed to the developers, City, and stakeholders
through separate PowerPoint presentations.

These presentations and meeting minutes es-
tablished the basis of design for each zone’s
tank final design. For Zone 3, the first tank will
be installed during Phase 1. When demand
increases, the second Zone 3 tank will be
constructed. HydroScience completed the Z3
tank final design, which will include provisions
for the future installation of the second tank.

Design of the Z4 tank is in progress.

Bickford Ranch Off-Site Water
Infrastructure
Bickford Ranch, Placer County, CA
Design Support. HydroScience prepared a
potable water hydraulic model to serve this
1,928 acre development in Placer County. The
design includes development of a new green-
field tank and pump site adjacent to the Catta
Verdera neighborhood in Lincoln, CA. New
water facilities include one 1.4 MG tank to
mitigate impacts of peak hour deliveries from
Placer County Water Agency (PCWA) and pro-
vide operational storage, a 7.5 mgd booster
pump station with canned vertical turbine
pumps, 10,000 gallon hydropneumatic tank

Page 188 ends

06/09/2026 Item No.9.
for pressure control, CMU pump station building, 4,000 LF of 18-inch transmission main pipeline, and 4,000 LF extension of PCWA’s 60-inch Ophir transmission pipeline. HydroScience also designed the development’s 18-inch off-site sewer trunk. Por - tions of the sewer alignment parallels Hwy 193 and is within Cal- trans right-of-way. As part of the Caltrans Encroachment Permit process, Placer County is obtaining a cooperative agreement with Caltrans because of this complex project.

Water Treatment and Storage Facility
Lytton Rancheria, Sonoma County, California
Project Engineer. HydroScience is providing design engineer - ing and engineering support of construction for new ground- water wells, groundwater treatment, treated water storage, and booster pumping facility to serve the Lytton Rancheria Project, a tribal residential development located near Windsor, CA. Hy- droScience’s role is design engineer-of-record as part of a de- sign/build project team. The facility will produce an average day flow of approximately 120K gpd at buildout. New wells will deliver raw water to a water treatment system to reduce concen- trations of arsenic and manganese in the groundwater to below primary maximum contaminant levels. The treatment process will include pH adjustment, oxidation, coagulation/filtration, post-filtration adsorption, and backwash thickening. Dosing of sodium hypochlorite followed by storage in on-site welded steel storage tanks will follow. A booster pump station consist- ing of banks of low and high flow pumps followed by a hydro- pneumatic tank will deliver water to the distribution system for residential demands and fire flows. The treatment and pumping equipment will be housed in a new CMU building, which will also contain an operations office, lab, power distribution, and control systems. The design phase has been completed and HydroScience will provide construction phase support including review of RFIs and submittals, field visits, and commissioning support.

Red Hawk Wastewater and Recycled Water
Improvements
Shingle Springs Rancheria, El Dorado County, California Support Engineer. HydroScience designed a new membrane
bioreactor (MBR) wastewater treatment plant, recycled water pumping, and effluent disposal systems for Red Hawk Casino.

These facilities were commissioned in 2009. Red Hawk retained HydroScience in 2020 to evaluate and design upgrades to sup- port expansion of the resort with a new hotel and entertainment facilities. Upgrades included two new 3.0 million gallon welded steel tanks, a new recycled water booster pump station with two VFD-driven 75-hp vertical turbine pumps, upgrade of existing chlorine contact basin effluent pumps, improvements to the existing sewer lift station, and a new coarse screening facility.

The project is currently in the later stages of construction. The project was implemented as a collaborative delivery (progres- sive design-build) arrangement and involved significant coordi- nation with the facility operator.

Placer Vineyards Sewer Lift Station #2
Placer County, California
Project Engineer. HydroScience was retained to provide design for a sewer lift station in support of the Placer Vineyards de- velopment. HydroScience prepared a Basis of Design Report to recommend upgrades and construction phasing for the im- provements. Design included a 40-feet deep cast in place con- crete wet well with 1,232 gpm submersible pumps, a 600,000 gallon emergency overflow storage facility using 10-ft diameter reinforced concrete pipe upstream wastewater, MCC/ Chemi- cal Building, control provisions, electrical and controls, and standby power generator. A 32,000 cubic yard excavation will be required for the wet well and emergency storage with provi- sions in the contract document for off haul of 10,000 cubic yards of soil. Austin’s duties include design of lift station, site grad- ing, site piping and equipment, chemical storage building, and overflow storage tanks.

Cordova Hills Special Planning Area Sewer Pump
Station
Rancho Cordova, California
Project Engineer. HydroScience is planning and designing the sewer pump station that will serve the Cordova Hills Special Planning Area, a 2,400+ acre planned development located east of Grant Line Road and south of Douglas Road. HydroScience is working with Cordova Hill’s engineer and SacSewer’s Develop- ment Services Group to design the required sewer facilities that must meet the initial through buildout sewer flow demands. At buildout, this pump station will serve 11,718 equivalent single family dwelling units. The design includes a new sewer pump station with dual wet wells and parallel 14-inch and 20-inch force mains to allow flexibility in phasing of the pumping capacity to meet the phasing of the Cordova Hills development. Austin’s duties include design of lift station, site grading, site piping, electrical building, and overflow storage tanks.

Austin Poulson

Page 189 ends

06/09/2026 Item No.9.

EDUCATION
M.S., Electrical Engineering,
California State University,
Sacramento
B.S., Electrical Engineering,
California State University,
Sacramento

REGISTRATION
Electrical Engineer, California,
Registration No. E18362

SELECT PROJECT EXPERIENCE
Thinh Le has 23 years of experience serving as Project Manager, Lead E&IC Engineer on a variety of water, wastewater, and recycled water projects. He has knowledge of ISA, IEEE, NEC, NFPA, and codes applicable to electrical and I&C system design and construction. He has worked in both electrical and I&C roles on design and construc- tion management projects and has an extensive working knowledge of electrical proj- ect development from analysis, SCADA systems, network & communication security, industrial automation controls, emergency and standby power, and electrical power systems including low and medium voltage electrical systems.

Folsom Tower Tank Rehabilitation
City of Folsom, California
Electrical Engineer. This project involves
the rehabilitation and operational improve-
ments of five potable water storage tanks in
the City of Folsom, addressing compliance,
safety, and functionality needs. Two tanks re-
quire upgrades to meet California Division of
Drinking Water (DDW) standards. Challenges
include a four-month design window and
strict sequencing during low-demand winter
months to maintain system operations. Im-
provements to the Tower Tank include struc-
tural modifications (vent, rafters, bracing),
a staircase replacing the ladder, safety up-
grades, a THM reduction mixer, and electri-
cal, SCADA, and utility enhancements, along
with antenna relocation, drainage, sampling,
coatings, and a cathodic protection system.

East Tank #2 upgrades focus on overflow,
drain, and vent modifications, exterior coat-
ing repairs, and drainage adjustments to
meet DDW compliance. Foothills Tanks (1 &
2) improvements include staircases, a catwalk
bridge, safety anchors, THM mixers, access
upgrades, monitoring cabinets, and SCADA
and electrical updates, along with coatings
and a prefabricated canopy. The South Tank
upgrades involve overflow, drain, and vent
modifications, exterior repairs, and drainage
improvements, ensuring compliance and op-
erational efficiency.

Bickford Ranch Water Infrastructure
Phasing
Placer County, California
Electrical Engineer. HydroScience prepared a
potable water hydraulic model to serve this
1,928 acre development in Placer County.

The design includes development of a new
green-field tank and pump site adjacent to
the Catta Verdera neighborhood in Lincoln,
CA. New water facilities include one 1.4 MG
tank to mitigate impacts of peak hour deliver-
ies from Placer County Water Agency (PCWA)
and provide operational storage, a 7.5 mgd
booster pump station with canned vertical
turbine pumps, 10,000 gallon hydropneu-
matic tank for pressure control, CMU pump
station building, 4,000 LF of 18-inch transmis-
sion main pipeline, and 4,000 LF extension of
PCWA’s 60-inch Ophir transmission pipeline.

HydroScience also designed the develop-
ment’s 18-inch off-site sewer trunk. Portions
of the sewer alignment parallels Hwy 193 and
is within Caltrans right-of-way. As part of the
Caltrans Encroachment Permit process, Plac-
er County is obtaining a cooperative agree-
ment with Caltrans because of this complex
project.

Water Treatment and Storage Facility
Lytton, Sonoma County, California
E&C. HydroScience is providing design en-
gineering and engineering support of con-
struction for new groundwater wells, ground-
water treatment, treated water storage, and
booster pumping facility to serve the Lytton
Rancheria Project, a tribal residential devel-
opment located near Windsor, CA. Hydro-
Science’s role is design engineer-of-record
as part of a design/build project team. The
facility will produce an average day flow of
approximately 120K gpd at buildout. New
wells will deliver raw water to a water treat-
ment system to reduce concentrations of ar -
senic and manganese in the groundwater to
below primary maximum contaminant levels.

The treatment process will include pH ad-
justment, oxidation, coagulation/filtration,
Thinh Le, PE
Lead Electrical Engineer

Page 190 ends

06/09/2026 Item No.9.
post-filtration adsorption, and backwash thickening. Dosing of sodium hypochlorite followed by storage in on-site welded steel storage tanks will follow. A booster pump station consist- ing of banks of low and high flow pumps followed by a hydro- pneumatic tank will deliver water to the distribution system for residential demands and fire flows. The treatment and pumping equipment will be housed in a new CMU building, which will also contain an operations office, lab, power distribution, and control systems. The design phase has been completed and HydroScience will provide construction phase support including review of RFIs and submittals, field visits, and commissioning support.

Pump Station 15 Improvements
City of Santa Rosa, CA
Project Manager. HydroScience designed and prepared bid plans and specifications for the improvement of City of Santa Rosa’s Pump Station 15. This project included, recoating the hydropneumatic tank (inside and out), new 4-inch Flow Switch, new magnetic flow meters, and the replacement of the exist- ing Automatic Transfer Switch, natural gas generator, fire pump starter, PLC, operator terminal, and pressure transmitters. The pump station is the only supply of pressure for the City’s R15 pressure zone, therefore the pump station continued to operate during construction to supply water to the zone. HydroScience developed a construction constraints and sequencing plan and vetted this with City staff. This plan was then reflected in the bid documents and includes construction phasing, shutdown and bypass prerequisites, and temporary construction provisions to maintain facility operations.

Buena Vue Casino Water and Wastewater Facilities
Buena Vue Rancheria, Amador County, California
Electrical Engineer. HydroScience is providing detailed design services for a 100,000 gpd MBR that will provide tertiary treat- ment to serve the casino and produce Title-22 compliant ef- fluent for discharge in accordance with an NPDES permit and onsite irrigation reuse. The flat-plate MBR system includes influ- ent pumps, fine screens, nitrification/denitrification and emer - gency storage. The facility includes an ultraviolet disinfection and a solids handling system. Water treatment will be designed for groundwater from onsite wells and water will be stored in a 1.25 MG water storage tank. Our scope includes design of power distribution, an emergency generator, and controls. The project will be constructed via the design-build project delivery method.

Wolfe-Evelyn Water Plant Reconstruction
City of Sunnyvale, Santa Clara County, California
Electrical Engineer. HydroScience provided planning, design and construction services for the City of Sunnyvale at the Wolfe- Evelyn Water Plant to replace four existing and aged pumps with new VFD controlled pumps with a capacity of approximate- ly 7.9 MGD. The design allows the plant to safely remain on-line while the new electrical system is installed and each existing pump is replaced and tested in succession. The entire outdat- ed electrical system was removed and updated with arc-clash compliant motor control centers. Other site upgrades include site paving around the existing pump building, grading and ac- cess road improvements around the storage tank, a vehicle tire wash down station, and seismic upgrades to the existing pump building. HydroScience prepared the CEQA documentation
for Categorical Exemption for the City, as well as assist in the preparation and acquisition of any other required permitting or documentation.

Recycled Water Project Implementation
City of Hayward, Alameda County, California
Electrical Engineer. HydroScience has been working with the City of Hayward to implement multiple portions of their new recycled water project. HydroScience is providing Engineer - ing Review Services for the design of 10 miles of recycled water distribution system, the new recycled water storage tank and recycled water pump station. HydroScience helped the City optimize the recycled water pipeline, fix significant issues with the 75% design drawings, and ensure that the PS&E contained the information required to result in a constructible project.

HydroScience is the engineer-of-record for the design of all 35 of the recycled water retrofit designs to be connected to the new recycled water distribution system.

Regional Wastewater Control Facilities
Stockton, San Joaquin County, California
Lead EI&C. HydroScience played a lead role on the rehabili- tation of the primary clarifiers and sludge and scum pumping systems as part of this Progressive Design-Build project. The existing clarifiers consisted of three discrete banks constructed at different times (as far back as the 1940s) and configured dif- ferently. Two of the clarifiers were “squircular” (circular mecha- nisms in square tanks) while the remaining ones are rectangular.

HydroScience performed a mechanical condition assessment, utilized a facility mass balance to determine anticipated future sludge removal rates and flows for pumping, developed pro- posed rehabilitation approaches for the clarifiers, worked with the contractor to refine construction approach and develop cost estimates for the improvements, and presented our findings in a workshop to City staff. HydroScience helped develop the pro- cess control narratives and finalized the construction plans and specifications and provided review of construction submittals.

The updated clarifiers now have a total capacity of 80 MGD.

Thinh Le, PE

Page 191 ends

06/09/2026 Item No.9.

HydroScience Engineers
34 Brad Friederichs, SE
Structural Engineer

EDUCATION
B.S., Civil Engineering with
honors, California State
University, Sacramento

REGISTRATION
Structural Engineer, California,
Registration No. S2780

AFFILIATIONS
Structural Engineers Association
of Central California, president
1989-90
American Society of Civil
Engineers
American Concrete Institute
American Institute of Steel
Construction

PROJECTS AS SUBCONSULTANT TO HYDROSCIENCE
Brad has over 40 years of experience as a structural engineer for wastewater, water treat - ment, commercial, industrial, agricultural, retail and residential structures. His expertise is in cast-in-place concrete, prestressed concrete, steel, wood and masonry construction. His specialty is in producing completely detailed, contractor friendly, value-oriented construction documents resulting in projects that bid well with few change orders.

WTP On-Site Residuals Management
San Juan Water District, California
Structural Engineer. HydroScience evaluated the
District’s WTP on-site residuals handling prac -
tices with respect to current and future regula -
tions. Evaluations included quantifying the solids
produced and determining the solids drying
area required under current and buildout con -
ditions. Based on the preliminary evaluations,
HydroScience proposed improvements to the
solids drying area to better retain solids and
capture rain runoff. The recommended improve -
ments include provisions to return runoff into the
WTP process stream. HydroScience prepared
a Technical Memorandum that summarized the
evaluation results and preliminary design param -
eters for a solids retention bed (for additional
drying) and for a sump and pump to collect sur -
face runoff from the solids retention bed.

El Macero Sewer Lift Station and Force
Main Re-Design
City of Davis, California
Structural Engineer. HydroScience is helping the
City of Davis replace the aging Sewer Lift Station
No. 1 (SLS #1), originally built in 1975, due to sig -
nificant maintenance, safety, and reliability issues.

Located in the El Macero community, the new SLS
#1 will be constructed on an adjacent City-acquired
property and will include submersible pumps with
VFDs, a wet well, odor control, bypass provisions,
and connections to both interim (14-inch) and
future (12-inch) force mains. It will be designed to
meet current City standards and blend with the
neighborhood. To support the new lift station, a
new 12-inch sanitary sewer force main approxi -
mately 9,744 feet in length will be constructed in
two phases, phase I will begin from SLS #1 up to
the I-80 crossing and phase II includes crossing
I-80 and UPRR to connect with the City’s sewer
collection system. HydroScience previously
completed the 2015 Lift Station Assessment and
2017 Feasibility Study, which identified SLS #1 for
major upgrades, and is now leading the design
with a focus on minimizing construction impacts
and improving O&M efficiency.

Eagle View Well Site Improvements
City of Morgan Hill
Structural Engineer. HydroScience is designing a
new well for the City that will improve water supply
redundancy and provide an additional source of
drinking water to the City’s Boy’s Ranch pressure
zone..The well design criteria include 800 GPM
capacity at a depth of 370 feet bgs, 16-inch well
casing and using vertical turbine pumps. The proj-
ect includes Phase I for well development with
drilling and testing, and Phase II for well equip -
ping with site improvements, a climate-controlled
building, chemical treatment, electrical equip -
ment and other utilities. Phase I has been bid and
design of Phase II is ongoing.

North Fork Mono Casino Water Treatment
Plant, Well, Pump Station, and Storage
Tank
North Fork Rancheria of Mono Indians, Madera,
California
Structural Engineer. HydroScience served as
engineer-of-record for the design-build proj -
ect to design and construct new water supply
and wastewater treatment facilities serving this
casino. HydroScience also prepared the original
water and wastewater feasibility study in 2008.

The project included site grading, all wet/dry
utilities, electrical, I&C, and SCADA, as well as
operations space, restroom/shower facilities, and
process laboratory, and an on-site diesel backup
generator. Water facilities include two wells, a
sodium hypochlorite system; a 1-million-gallon
steel potable water storage tank, and a booster
pumping station. Wastewater facilities include a
pre-fabricated MBR WWTP producing disinfected
VE Solutions

Page 192 ends

06/09/2026 Item No.9.

HydroScience Engineers
35 tertiary recycled water for reuse as within the Rancheria. The WWTP includes influent screening, equalization storage, sludge storage and dewatering, treatment, ultraviolet disinfection, and effluent pumping.

North Fork Mono Casino Water Treatment Plant, Well,
Pump Station, and Storage Tank
North Fork Rancheria of Mono Indians, Madera, California Structural Engineer. HydroScience served as engineer-of-record for the design-build project to design and construct new water supply and wastewater treatment facilities serving this property.

HydroScience also prepared the original water and wastewater feasibility study in 2008. The project included site grading, all wet/ dry utilities, electrical, I&C, and SCADA, as well as operations space, restroom/shower facilities, and process laboratory, and an on-site diesel backup generator. Water facilities include two wells, a sodium hypochlorite system; a 1-million-gallon steel potable water storage tank, and a booster pumping station. Wastewater facilities include a pre-fabricated MBR WWTP producing disinfected tertiary recycled water for reuse as within the Rancheria. The WWTP includes influ - ent screening, equalization storage, sludge storage and dewatering, treatment, ultraviolet disinfection, and effluent pumping.

Florin Pump Station Ventilation Improvements
City of Sacramento, California
Structural Engineer. Florin Pump Station, a large below-ground water booster pump station, had excessive levels of carbon mon - oxide and methane gases. HydroScience worked closely with City engineering staff to develop a detailed project scope, evaluate ventilation improvement alternatives, and implement a ventilation improvements design to improve worker health and safety and comply with OSHA thresholds. Improvements include: modification of exhaust stack outlets to improve dispersion of gases, installation of a separate air supply and cooling for the control room, and supply and exhaust ducting and fan additions in the equipment room.

HydroScience also designed electrical power and controls modifi - cations to operate the new equipment.

Eagle View Well Site Improvements
City of Morgan Hill, California
Structural Engineer. HydroScience is designing a new production well for the City that will supply 800 gpm of drinking water while meeting primary and secondary water quality standards. The project will increase the water supply redundancy and provide additional source of water to the City’s Boy’s Ranch pressure zone. The well design criteria include 800 GPM capacity at a depth of 370 feet bgs, 16-inch well casing and using vertical turbine pumps. The project includes phase I for well development with drilling and testing, and phase II for well equipping with site improvements, a climate-con - trolled building, chemical treatment, electrical equipment and other utilities.

Manteca Well 29 TCP Treatment
City of Manteca, California
Structural Engineer. HydroScience designed a new wellhead treat - ment system to remove 1,2,3 -Trichloropropane (TCP) from the City of Manteca’s Well 29, a 2,000 gpm well located in Y osemite Village Park. The new treatment system uses granular activated carbon (GAC) filters, which were successfully implemented by the HydroScience team for TCP removal on several other City wells. The DDW had a tight compliance deadline that required careful identifi - cation and management of critical path items from the outset and efficient execution of the preliminary and final designs. Challenges included minimizing aesthetic impacts to the park and residents, facilitating media changeouts and O&M, maximizing media life, com- pleting CEQA documentation on a short timeline, and meeting the fast-track schedule.

CalPoly Water Reclamation Facility
San Luis Obispo, California
Structural Engineer. HydroScience is designing a 1 MGD membrane bioreactor reclamation facility to produce recycled water for on-site irrigation reuse. This facility will treat a portion of the campus waste- water that is currently discharged to the city treatment plant, facili - tate beneficial reuse, and reduce campus reliance on potable water supplies. This project is being implemented through a unique pro - gressive design-build model in partnership with a general contractor and the campus. The treatment system will utilize factory-assembled and tested stainless steel treatment biological and membrane filtra- tion treatment units. It will also utilize a packaged sludge storage, aeration, and dewatering system utilizing screw presses. Recycled water will be stored in a new 85 acre-foot lined reservoir and distrib- uted to irrigation uses around the campus.

Wastewater Treatment and Effluent Management Facilities Lytton Rancheria, Sonoma County, California
Structural Engineer. As part of a design/build team, HydroScience completed design of wastewater and recycled water facilities serv - ing a new tribal residential development in Sonoma County. The Lytton Rancheria project consists of construction of new homes, a community center, and a retreat center. HydroScience designed a complete Membrane Bioreactor (MBR) Wastewater Treatment Facility utilizing shop-fabricated treatment units to treat 250,000 gpd of peak dry weather flow. The design includes an administra - tion building, UV disinfection, solids dewatering system using screw presses, effluent storage pond, and recycled water pump station.

The design was developed through a
Brad Friederichs, SE VE Solutions

Page 193 ends

06/09/2026 Item No.9.

J.P. Davis, PE, CCM, QSP

1 J.P. has
experience in civil engineering, construction management, and construction inspection for commercial, industrial, and capital improvement projects. His focus is on water/wastewater infrastructure projects, including pretreatment and filtration structures,
pump stations, reservoirs, large diameter underground piping, and hydropneumatic surge tanks. His experience as a construction manager, resident engineer, and inspector includes constructability review, management of construction documentation, management
of staff and subconsultants, contract and change order
negotiations, budget and schedule review tracking and analysis, schedule of values and progress payment review, chairing of progress meetings and lead inspection, and project tracking, including writte
n and photographic documentation of daily construction
activities.

J.P. also has a strong background in geotechnical engineering and materials testing and inspection. His experience in these fields
includes

borehole soil logging and sampling;
performance and oversight of laboratory soils and construction materials testing; preparation of geotechnical investigation/compaction reports; grading and AC paving observation/inspection; field in situ compaction test
ing; and special inspection. It also
includes forensic destructive/
nondestructive

data compilation and analysis for
geotechnical expert testimony in residential construction defect litigation. In addition to being a Certified Construction Manager (CCM), J.P. is a California licensed Professional Engineer and a Qualified SWPPP Practitio
ner (QSP).

EXPERIENCE

Tower Tank Rehabilitation Project, City of Folsom, CA:

Project/Construction Manager for
the $5 million Tower Tank Rehabilitation project to meet State of California Department of Drinking Water requirements, provide safer and more efficient maintenance access for City staff, and increase longevity of potable w
ater utility assets. The project consists of
rehab and modification of five (5) existing water storage tanks throughout the City. The project is located at four sites throughout the City including the (1) East Tank No. 2, (2)
South Tank, (3) Foothills Tanks Nos. 1 & 2, and (4) Tower Tank sites. Key modifications and/or upgrades include but are not limited to: crow’s nest installation; beams, bracing, and rafter replacement; interior roof plate seal weld
s; staircase, catwalk, and guardrail
installation; tank overflow system modifications; tank cathodic protection improvements; tank mixer & power vent system installation; interior and exterior tank coatings; storm drain and drain piping installation; and e
lectrical, instrumentation, and SCADA upgrades.

Reservoir No. 2 Rehabilitation Project, City of Folsom, CA:

Construction Manager during rehabilitation of this $1.3 million project involving the City of Folsom’s existing Reservoir Nos. 1 and 2 water tanks located at the Water Treatment Plant. Modification s
consisted of rerouting the inlet and outlet piping, inst alling a cathodic protection system, stairs, and flexible connections, and recoating the interior of Reservoir No. 2 and exteriors of Reservoir Nos. 1 and 2. A key project challenge included tank o utage
constraints, limiting construction to the low
-
demand season between November and April. The project went over schedule due to several contributing factors, including insufficient and unqualified construction personnel, lack of management/supervision by the
contractor, and unforeseen conditions that were not vetted out by the contractor during the early stages of the project. Due to the
late completion of the project, liquidated damages were assessed, and J.P. successfully negotiated coating of two add itional 2.5
MG tanks to offset the losses incurred by the City.

Staff Title:

Construction Management
Business Sector

Lead

/

Construction Manager IV

Office Location:

Sacramento, CA

Years of Experience:

2 7

Years with West Yost:

11 Professional Registrations

Professional Civil Engineer,
California
No. C66826

Certified Construction Manager,
Construction Management
Certification Institute, ID No. 4505

Qualified SWPPP Practitioner,
Certificate No. 25223

10 -
Hour Cal OSHA Construction Safety
Certification, January 2021

Education

BS,
Civil Engineering, University of
California, Irvin
e

Certifications

Confined Space Competent Person &
Confined Space Entry and Non
-
Entry
Rescue,
April

202
4 

First Aid and CPR/AED, American Heart
Association, Certified December 202
4 

Fall Protection,
December

202
5 

US Army Corps of Engineers
Construction Quality Management for
Contractors #784

Professional Affiliations

American Public Works Association

Construction Management Association
of America

American Society of Civil Engineers

Page 194 ends

06/09/2026 Item No.9.

J.P. Davis, PE, CCM, QSP

2 Cimarron, Nimbus, and Reservoir No. 2 Rehabilitation Project, City of Folsom, CA:

Construction Manager for rehabilitation of the
City of Folsom’s existing Cimarron, Nimbus, and Reservoir No. 2 steel water tanks. The project consisted of multiple improvem ents,
including rerouting the inlet piping above ground and installing a seismic fl exible coupling, Tideflex mixing header, cathodic
protection system, roof vent, and stairs, and recoating the exterior roof and all interior components of the Cimarron tank. A lso
included were roof vent replacements at the Nimbus and Reservoir 2 tanks. Key project challenges included strict site access requirements as the Cimarron Tank is located within the Prison Industry Authority (PIA) property and a tight construction compl
etion schedule with multiple milestone completion dates. The 80 calendar day construction schedule with a liquidated damage penalty of $1,000 for each day beyond the completion date was enforced to impress upon the contractor the importance of getting the
tanks back in service before increase in water demand. The project went over schedule due to several contributing factors, including insufficient and unqualified construction personnel, lack of management/supervision by the contractor, and

several days in
which no work was performed on controlling operations. J.P. saw the project through to successful completion while diligently documenting the project, successfully negotiating over $250,000 in liquidated damages to offset the losses incurred by the City.

Bickford Ranch Water Tank No. 1 and Pump Station No. 1, Placer County Water Agency (PCWA):

Construction Manager. West
Yost is providing construction management and inspection services on behalf of PCWA for this developer driven, $9 million pro ject
that includes water distribution, storage, and pumping equipment and facilities to serve the new B ickford Ranch housing
development in unincorporated Placer County, California. The project consists of a new pumping station with four 200 hp and t wo
25 hp jockey ver
tical turbine pumps with VFDs, controls, valves and all other related mechanical and electrical components, site piping including pump suction and discharge, site water, irrigation and drainage, an approximately 1,650 sq. ft. pump station

structure, backup

generator, 10,000 gallon hydropneumatic tank and air compressors, a 1.4 -
MG welded steel water storage tank,
approximately 4,500 feet of new 18 inch ductile iron distribution pipeline, approximately 1,800 feet of new 60 inch welded st eel
transmission pipel
ine, a new 24 foot wide paved access road to Pump Station No. 1 including a new concrete box culvert for crossing the Caperton Canal, and associated side work including grading, paving, landscaping, retaining walls, equipment pads

structural foundations, a
nd retention pond.

East Tank No. 1 Rehabilitation Project, City of Folsom, CA:

Construction Manager during rehabilitation of this $3.1 million project involving the City’s existing steel 3 MG East Tank Nos. 1 and 2, 4 MG Zone 4 Tank, 3 MG Zone 5 Tank, and 3 MG South Tank.

Modifications consisted of recoating the interior of East Tan k No. 1 and the exterior of all four tanks listed above, modifying tank piping and structural roof support systems, constructing two stairways, retrofitting or replacing various tank features, and installing a new cathodic protection system in East Reservoir, Tank No. 1.

Zones 4 and 5 Pump Station (PS) and Zone 6 PS/Zone 5 Tank, City of Folsom, CA:

Lead Inspector for these two projects with a
combined value of $10 million, constructed for supplying potable water to the new Folsom Plan Area (FPA) development south of

Hwy 50. The Zones 4 and 5 PS project included construction of a new booster pump sta tion with three 125 hp 1280
-
GPM vertical
turbine pumps (VTP) and infrastructure for build out to the future Zone 4 Tank. The Zones 4 and 5 PS delivers water from the City’s
existing water system to a new 2.5 MG steel tank (Zone 5 Tank) and gets further dis tributed to the City’s Zone 6 region with two
3,000
-
GPM fire flow and three 400
-
GPM VTP pumps to service the ongoing FPA developments.

Water System Rehabilitation Project #2, City of Folsom, CA:

Construction Manager. This $1.4 million project covered the construction of numerous valves and connections to help improve the reliability and redundancy of the water system in the Cit y
and performing related, required work. There are 12 different locati ons which are in the public right of way and/or on private property. Project Size: Multiple locations requiring construction of valves and connections to new water system pipes.

JM Pike Park Stormwater to Sanitary Sewer Cross Connection Removal and Water Main, City of Modesto, CA:

Project/Construction Manager for the $30.6 million J.M. Pike Park project which aims to address peak wet weather flows in the

north central portion of the City. It involves removal of nine (9) stormwater to sanitary sewer cross connections, installati on of

approximately 10,566 linear feet of new storm drain systems that will carry the runoff to an underground stormwater pre -
treatment facility at J.M. Pike

Park. To minimize disruption to the public and unnecessary replacement of asphalt paving, the Project also includes replacement of existing, deteriorating and undersized water mains in the same general areas where the n ew
storm drain system will be instal
led. The new potable water line piping will consist of approximately 17,213 LF of 8 -
inch and 5,675
LF of 12
-
inch water mains, and associated appurtenances.

Page 195 ends

06/09/2026 Item No.9.

Jason C. Bergh, QSP

1 Jason Bergh has extensive experience in construction observation, materials testing, and special inspections. He has managed materials testing for various projects, including private and large
-
scale residential housing, apartments, multi
-
story commercial b
uildings,
recreational facilities, parking structures, and municipality infrastructure and improvements. As an International Code Council certified Master of Special Inspection, he provides quality control, monitoring, and inspection for reinforced concret e, masonry,
structural steel, and fireproofing. Additionally, he has a strong background

in soil
identifications, mass grading, evaluation and testing of roadway subgrade, aggregate base, and asphalt placement. He is knowledgeable about the use of geotextiles and chemical treatments for mitigating unstable surfaces. Jason is a certified erosi on,
sediment, and stormwater inspector and a Qualified SWPPP Practitioner (QSP) in the state of California. His experience includes testing and monitoring of stormwater, providing recommendations, and implementing corrective measures to comply with local, state, and federal regulations.

EXPERIENCE

Tower Tank Rehabilitation Project, City of Folsom, CA:

Resident Engineer/Inspector

for
the $5 million Tower Tank Rehabilitation project to meet State of California Department of Drinking Water requirements, provide safer and more efficient maintenance access for City staff, and increase longevity of potable water utility assets. The pro ject consists of
rehab and modification of five (5) existing water storage tanks throughout the City. The project is located at four sites throughout the City including the (1) East Tank No. 2, (2) South Tank, (3) Foothills Tanks

Nos. 1 & 2, and (4) Tower Tank sites. Key modifications and/or upgrades include but are not limited to: crow’s nest installation; beams, bracing, and rafter replacement; interior roof plate seal welds; staircase, catwalk, and guardrail installation; tank
overflow system modifications; tank cathodic protection improvements; tank mixer & power vent system installation; interior and exterior tank coatings; storm drain and drain piping installation; and electrical, instrumentation, and SCADA upgrades.

Bickford Ranch Water Tank No. 1 and Pump Station No. 1, Placer County Water Agency (PCWA)
, CA
:

Resident Inspector. Providing inspection services on behalf of PCWA for this developer driven, $9 million project that includes water distribution, storage, and pumping equipment and facilities to serve the new Bickford Ranch housing development in Uninco
rporated Placer County, California. The project consists of a new pumping station with four 200 hp and two 25 hp jockey vertical turbine pumps with VFDs, controls ,
valves and all other related mechanical and electrical components, site piping including pump suction and discharge, site water, irrigation and drainage, an approximately 1,650 sq. ft. pump station structure, backup generator, 10,000 gallon hydropneumati c tank and
air compressors, a 1.4
-
MG welded steel water storage tank, approximately 4,500 feet of new 18 inch ductile iron distribution pipeline, approximately 1,800 feet of new 60 inch welded steel transmission pipeline, a new 24 foot wide paved access ro ad to Pump Station No. 1 including a new concrete box
culvert for crossing the Caperton Canal, and associated side work including grading, paving, landscaping, retaining walls, equipment pads structural foundations, and retention pond.

Zones 4 and 5 Pump Station (PS) and Zone 6 PS/Zone 5 Tank, City of Folsom, CA:

Special Inspector for these two projects with a
combined value of $10 million, constructed for supplying potable water to the new Folsom Plan Area (FPA) development south of

Staff Title:

Resident Inspector (Prevailing
Wage Group 2)

Office Location:

Sacramento, CA

Years of Experience:

2 1

Years with West Yost:

3 Education

MBA, Business Administration,
Chapman University, Orange, CA

Graduate
Certificate, Organizational
Leadership, Orange, CA

BA, Organizational Leadership,
Chapman University, Orange, CA

AA, Cosumnes River College,
Sacramento, CA

Certifications

International Code Council (ICC) No.
8356420

-

Commercial Building
Inspector

-

Commercial Mechanical Inspector

-

Commercial Plumbing Inspector

-

Reinforced Concrete

-

Prestressed Concrete

-

Soils Special Inspector

-

Spray
-
Applied Fireproofing Special
Inspector

-

Structural Masonry Special Inspector

-

Structural Steel and Bolting Special
Inspector

-

Structural Welding Special Inspector

-

Master of Special Inspection

-

American Concrete Institute (ACI)

-

Concrete Field
-
Testing Technician
–

Grade I

10 -
Hour Cal OSHA Construction Safety
Certification, July 2022

Troxler
-

Nuclear Moisture
–

Density
Gauge

CASQA
-

Qualified SWPPP Practitioner
(QSP/CESWI)

Radiation Safety Officer Training
-

(RSO) Certified

California Department of Insurance
–

Licensed Producer

California Department of Real Estate
–

Licensed Broker

Page 196 ends

06/09/2026 Item No.9.

Jason C. Bergh, QSP

2 Highway 50. The Zones 4 and 5 PS project included construction of a new booster pump station with three 125 hp 1280 -
gpm
vertical turbine pumps (VTP) and infrastructure for build out to the future Zone 4 Tank. The Zones 4 and 5 PS delivers water from
the City’s existing water system to a new 2.5
-
MG steel tank (Zone 5 Tank) and gets further distributed to the City’s Zone 6 region
with two 3,000
-
gpm fire flow and three 400
-
gpm VTP pumps to service the ongoing FPA developments.

Owner’s Representative Services, Well 80, Sacramento Suburban Water District, CA:

Resident Inspector. West Yost is providing
Construction Management and Inspection services as part of its Owners Representative’s role beginning with the first of up to

four
new monitoring wells and four new groundwater wells and associated pumping and tr eatment facilities. The projects are being
constructed under a progressive design build project delivery process. As the Owner’s Representative West Yost is representin g
the d
istrict in the contracting and management of the progressive design build team.

Lagoon Valley Project, City of Vacaville, CA:

Resident Inspector. West Yost is providing CM Services on several areas under this contract. Sewage Lift Station: 2.5 MGD lift station with cast -
in
-
place concrete wet well, submersible chopper pumps, associated valving and piping, approximately 20 feet of

dual 10 inch force main; one sanitary sewer manhole; 120 feet of VCP sanitary sewer; control building to house electrical and emergency generator equipment, variable frequency drives and power distribution equi
pment; foul air system; site work; landscaping; electrical and instrumentation work; and miscellaneous improvements for a complete and operational facility. Construction under this Contract involves modification of facilities at the existing opera ting
wast
ewater collection system, which must continue to meet requirements of State and Federal regulating agencies. Lagoon Valley Water Storage Reservoir: Partially buried 2.54 MG circular prestressed

concrete potable water storage reservoir, valve vault and acce
ss roadway. Reservoir is a 136
-
foot diameter,
27 -
foot
-
tall

buried concrete tank with a separate buried 26
-
foot by 21
-
foot
concrete valve vault and associated site work and piping. Water Booster Pump Station: Booster pumping station with four, 50 h p
pumps in a CMU building, two (2) valve vaults, and access roadway . The work includes all site preparation; environmental and erosion control measures; excavation; subgrade preparation; concrete work; process piping; drainage piping; reservoir accesso ries;
electri
cal power and instrumentation; leak testing; disinfection; backfilling; landscape restoration; irrigation; and fencing. North ern
Utilities Offsite Improvements: Approximately 8,000 LF of 6 inches

to 18 inch
es
in

diameter sewer and 23 precast concrete
manholes; 5,500 LF of 12
inches

to 18 inch
es in

diameter waterline and associated valves, hydrants, blow offs and ARV’s; and 435 LF of 15 inch
es

to 48 inch
es in

diameter storm
drainpipe
. This work will include pavement restoration and tie
into

existing
infrastr
ucture. These projects must be in compliance with NSF/ANSI 61 Standards.

Alder Creek Parkway Sewer Lift Station and Force Main, Mangini Improvement Company, Folsom, CA:

As Inspector, Jason
conducted testing during earthwork operations and installation of sewer improvements for a sanitary sewer lift station and fo rce
main. Special inspection services included epoxy placement and concrete observation and testing. (Complete d under prior
employment.)

Water Treatment Plant, Rancho
Murietta

Community Services District, Rancho
Murietta
, CA:

Inspector for this project that
included expansion and improvement of an existing water treatment plant. Observed mass grading and underground utility installation for the expansion and improvement of an existing wastewater treatment plant. Performed comp action testing as well
as numerous special inspection tasks. (Completed under prior employment.)

Greenback Sewer and Lift Pump Station, City of Folsom, CA:

Office/Resident Engineer for this project
involv
ing
comprehensive
construction management and inspection services for upgrades to Pump Station No. 3 (PS3) and sewer system modifications along

Greenback to improve operational flexibility. Key components included piping and sanitary sewer manhole modification s, new
flow control structures, and pipeline abandonment, as well as interior changes to manholes to redirect flow from PS3 to Pump Station No. 2

(PS2). Additional work included relocating city
-
owned sewer mains, reconnecting private sewer connections, and site improvements around PS3 such as drainage modifications, fencing, and new bypass pumping connections. The project also involved equipment up
grades at PS3 and PS2, abandonment of an existing force main, and procurement, startup, and testing of two new portable bypass pumps.

Harvest Water Program Central South Distribution Pipelines Project, Sacramento Regional County Sanitation District (Regional San), CA
:

Resident Engineer
. West Yost is providing construction management and inspection services for the Harvest Water Program, $40M Central South Pipeline Project as a subconsultant to Psomas. West Yost’s $2.1 million scope supports Regional San’s $1.6 billion recycled water Har
vest Water Program, which delivers highly treated tertiary water to agricultural users south of Sacramen
to. This project is for installation of large diameter recycled water pipelines forming the Central South conveyance backbone throughout the City of Elk Grove to farmers in the region. The work includes daily field oversight, documentation, schedule and co
st monitoring, coordination with operations & maintenance staff, public outreach, and quality assurance to verify compliance with project specifications. The Harvest Water Program supports Regional San’s broader goal of reusing up to 50,00 0 acre
-
feet of tr
eated wastewater annually, reducing river discharges while improving groundwater sustainability and agricultural resilience.

Date Completed: 12/2025 (est.)

Page 197 ends

06/09/2026 Item No.9.

Jesse Shah

1 Jesse is
experienced in the construction and steel fabrication industry. He has performed special inspection and testing services on a variety of building and infrastructure projects, including wastewater treatment plants, hospitals, schools, commercial buildings, and
highway projects in accordance with Caltrans, AASHTO, federal, and local quality assurance/quality control test methods. Jesse’s experience includes soils, reinforced concrete, masonry, and structural steel inspection and testing.

EXPERIENCE

Tower Tank Rehabilitation Project, City of Folsom, CA:

Construction inspector
for the $5
million Tower Tank Rehabilitation project to meet State of California Department of Drinking Water requirements, provide safer and more efficient maintenance access for City staff, and increase longevity of potable water utility assets. The proj ect consists of
rehab and modification of five (5) existing water storage tanks throughout the City. The project is located at four sites throughout the City including the (1) Ea st Tank No. 2, (2)
South Tank, (3) Foothills Tanks Nos. 1 & 2, and (4) Tower Tank sites. Key modifications and/or upgrades include but are not limited to: crow’s nest installation; beams, bracing, and rafter replacement; interior roof plate seal welds; sta ircase, catwalk, and guardrail
installation; tank overflow system modifications; tank cathodic protection improvements; tank mixer & power vent system installation; interior and exterior tank coatings; storm drain and drain piping installation; and electri
cal, instrumentation, and SCADA upgrades.

Construction Management Services for the EchoWater Project Procurement 1, Sacramento Regional County Sanitation District (Regional San), Sacramento, CA:

Construction Inspector for the $33 million Site Preparation project as part of the $1.5 billion EchoWater Program. The project consisted of installing over six miles of various pipelines (reclaimed water, digested sludge, secondary effluent, potable and n on
-
potable
water, and storm drain) using HDPE, PVC, and RCP materials throughout the Plant site.

The pro
ject also included approximately three miles of 12 kV and signal duct banks and manholes; replacement of signal wiring with fiber optic cabling; new plant access roads; security fencing; construction water well and access road; construction field office co
mplex with wireless communication system; and a new main construction entrance that included a six
-
lane entrance, security card readers, automatic security gates, and a manned remote security guard facility.

CM for Water Treatment Plant Pretreatment System Improvements Project, City of Folsom, CA:

Resident Inspector. This $2.088
million project consists of modifications to the existing Actiflo and Basin 5 pretreatment systems to increase the City’s tre atment
and distribution capacity. These upgrades will allow the City to meet the increased demand for the FPA development south of Hwy
50, as well as provide redundancy. General upgrades include the addition of tie downs over the lamellar settling tubes at Act iflo

Trains 1 and 2 which will re rate each train from 20
-
MGD to 25
-
MGD, modifications to the raw water inlet piping into
Sedimentation Basin 5, installation of a slide gate to prevent settled water from entering the basin from Actifo when the Cit y
performs it
s annual cleaning, modifications to existing baffle and weir walls within Basin 5 to accommodate change in hydraulics due to increase in flow, and installation of 32 plate settlers which will increase the pretreatment capacity in Basin 5 from 15 -
MGD
to 25
-
MGD. The project was completed in 500 calendar days.

River Trunk Realignment
–

Gravity System, Modesto, CA:

Construction Inspector. West Yost is providing inspection for this $22 million construction project that includes trenching,
conduit,

and pipe placement; backfill and compaction for approximately two miles of large diameter piping. This includes construction of concrete junction structures and requires a large public outrea ch
effort and coordination with multiple stakeholders.

Staff Title:

Resident Inspector (Prevailing
Wage
-

Group 2)

Office Location:

Sacramento, CA

Years of Experience:

2 1

Years with West Yost:

6 Certifications

International Code Council No.
5298462:

-

Structural Masonry Special Inspector
(2025)

-

Structural Steel/Welding Inspector
(2025)

-

Reinforced Concrete Special
Inspector (2025)

American Concrete Institute, Field
Testing Technician, Grade I

American
Portable Nuclear Gauge
Association, Nuclear Gauge Training
Certification

California Department of
Transportation, Materials Engineering
and Testing Services, California Test
Methods: 125, 127, 216, 231, 375, 504,
518, 533, 539, 540, 556, 557

Confined Space Competent Person &
Confined Space Entry and Non
-
Entry
Rescue, June 2021

First Aid and CPR/AED, American Heart
Association, Certified August 2020

10 -
Hour Cal OSHA Construction Safety
Certification, January 2021

Fall Protection, November 2021

Page 198 ends

06/09/2026 Item No.9.

Jesse Shah

2 River Trunk Realignment
–

Shackleford Pump Station, City of Modesto, CA:

Construction Inspector. West Yost is providing
construction management and inspection for the $10 million construction of a 7 MGD sewage pump station, new pressure and gravity pipelines up to 36 inch diameter, and associated structures located in the City of Modesto and unincorporated Stanislaus
County, CA. New facilities will include a sewage pump station with three submersible screw centrifugal pumps located in a belowground cast in
place concrete structure; associated pump station valves and flow meter located in a cast in place belowground concrete structure; a pump station electrical building, outdoor generator, and monorail crane; force main pipelin es
that operate under pressure,
including ductile iron and polyvinyl chloride pipe materials, installed on a pump station site and through Dryden Park Golf Course; and sanitary sewer pipelines that flow by gravity installed on pump station site, within pub lic
right of way and Golf Course
. It will also include asphalt pavement replacement within public right of way and Golf Course; reinforced concrete junction structures and manholes along the new sanitary sewer pipeline alignments; a paved pump station s ite
with retaining wall and fencing
; a grinder pump station located on the Golf Course; and sod restoration for all disturbed area on the Golf Course.

Lagoon Valley Project, City of Vacaville, CA:

Construction Inspector. West Yost is providing CM Services on several areas under this contract. Sewage Lift Station: 2.5 MGD lift station with cast -
in
-
place concrete wet well, submersible chopper pumps, associated valving and piping, approximately 20 fee
t of dual 10 inch force main; one sanitary sewer manhole; 120 feet of VCP sanitary sewer; control building to house electrical and emergency generator equipment, variable frequency drives and power distribution equipment; foul air system; site work; landscaping; electrical and instrumentation work; and miscellaneous improvements for a

complete and operational facility. Construction under this Contract involves modification of facilities at the existing opera ting
wastewater collection system, which must continue to meet requirements of State and Federal regulating agencies. Lagoon Valle y
Water Storage Reservoir: Partially buried 2.54 MG circular prestressed concrete potable water storage reservoir, valve vault and
access roadway. Reservoir is a 136
-
foot diameter,
27 -
foot
-
tall

buried concrete tank with a separate buried 26
-
foot by 21
-
foot
concrete valve vault and associated site work and piping. Water Booster Pump Station: Booster pumping station with four 50 hp

pumps in a CMU building, two (2) valve vaults, and access roadway.

The work includes all site preparation; environmental and erosion control measures; excavation; subgrade preparation; concrete work; process piping; drainage piping; reservoir accesso ries;
elec
trical power and instrumentation; leak testing; disinfection; backfilling; landscape restoration; irrigation and fencing. Nor thern
Utilities Offsite Improvements: Approximately 8,000 LF of 6 inches

to
18 -
inch

diameter sewer and 23 precast concrete manholes;
5,500 LF of 12
-

to
-
18 -
inch

diameter waterline and associated valves, hydrants, blow offs and ARV’s; and 435 LF of 15 inch to 48 inch diameter storm drain pipe. This work will include pavement restoration and tie into

existing infrastructure. These projec
ts
must
follow

NSF/ANSI 61 Standards.

EchoWater Project Nitrifying Sidestream Treatment, Regional San, Sacramento, CA:

Resident Inspector for a $45 million Nitrifying
Sidestream Treatment project that involved construction of three Sequential Batch Reactor (SBR) rectangular concrete tanks th at
nitrify highly concentrated wastewater from the final solid storage basins usin g high
-
speed turbo air blowers and an automated
decanter system. Supporting the process includes a fine screen facility, influent lift station, dedicated electrical building , a
nd a dry
lime storage and slurry feed facility that adjusts the alkalinity of the SBRs. In addition, a basin washdown pump station, an d a
stormwater pump station were constructed.

Headworks and Dryden Box and Influent Plume Improvements Project, City of Modesto, CA:

Construction Inspector for the $18.6
million Headworks and Dryden Box Project at the City of Modesto’s Primary Sutter Avenue treatment plant that is currently und er
construction by general contractor, C. Overaa & Co. The project involves constructing nume rous buried junction structures tying
into existing pipelines, installation of several hundred feet of large diameter fiberglass and RCP pipe, new process equipmen t, odor

control improvements, and major electrical improvements that include replacing motor control centers and upgrading control systems with PLCs to improve remote automated control via the existing SCADA system. The work includes pumped bypasses, shutdowns, t
emporary systems, tie ins, and startups requiring manipulation of existing system valves and gates to test the new system in a loop prior to incorporation into the process with small windows of opportunity for testing and confirming reliabi lity.

The juncti
on structures require control of groundwater and complicated shoring systems to construct the structures, and temporary bypasses to demolish existing piping within the new tie in structures, while minimizing impacts to the operation of

the
existing treatme
nt plant processes. The project started in November 2018 and is scheduled to be completed on or before November 2020.

Main Pump Station Emissions Control Study, City of Milpitas, CA:

Construction Inspector including special inspection services for an alternatives analysis of odor control technologies that could be implemented at the Main Pump Station to identify a techno logy
best suited to reliably control all types of odorous emissio ns, fit within available space at the Main Pump Station site, and minimize life cycle costs. Odor emission control technologies assessed included biofiltration, activated carbon filtration, an d liquid phase
technologies (oxygen balance, chemical oxidation, precipitation, substitute oxygen sources, pH control, and biological contro l).

Page 199 ends

06/09/2026 Item No.9.

Amy Rangel

1 Amy is a construction project
manager and
administrator providing support for
construction management and design of environmental and engineering projects focused on wastewater and potable water treatment facilities and associated infrastructure ranging from $4 million to $47 million in value. Amy

has excellent organization,
communication, and project management skills. Her experience includes document tracking and distribution using Procore,
Ebuilder, CMIS,
Primavera and MS Access
databases. She is experienced in all phases of project administration and effectively manages all documentation between the Design Engineer, Contractor, and Project Owner. Her experience also includes managing daily operations for p rojects with multiple
field locations, construction administration, and vendor coordination.

EXPERIENCE

Tower Tank Rehabilitation Project, City of Folsom, CA:

Construction Administrator

for
the $5 million Tower Tank Rehabilitation project to meet State of California Department of Drinking Water requirements, provide safer and more efficient maintenance access for City staff, and increase longevity of potable water utility assets. The pro ject consists of
rehab and modification of five (5) existing water storage tanks throughout the City. The project is located at four sites throughout the City including the (1) East Tank No. 2, (2) South Tank, (3) Foothills Tanks Nos. 1 & 2, and (4) Tower Tank sites. Key modifications
and/or upgrades include but are not limited to: crow’s nest installation; beams, bracing, and rafter replacement; interior roof plate seal welds; staircase, catwalk, and guardrail installation; tank overflow system modificatio
ns; tank cathodic protection improvements;
tank mixer & power vent system installation; interior and exterior tank coatings; storm drain and drain piping installation; and electrical, instrumentation, and SCADA upgrades.

Bickford Ranch Water Tank No. 1 and Pump Station No. 1, Placer County Water Agency (PCWA):

Construction Administrator. West Yost is providing administration for construction management and inspection services on behalf of PCWA for this developer driven, $9 million project. The project includes water distribution, storage, and pumping equipment and facilities to serve t he new
Bickford Ranch housing development in Unincorporated Placer County, California. The project consists of a new pumping statio n
with fou
r 200 hp and two 25 hp jockey vertical turbine pumps with VFDs, controls, valves and all other related mechanical and electrical components, site piping including pump suction and discharge, site water, irrigation and drainage, an approximatel y
1,650 sq. f
t. pump station structure, backup generator, 10,000 gallon hydropneumatic tank and air compressors, a 1.4 MG welded steel water storage tank, approximately 4,500 feet of new 18 inch ductile iron distribution pipeline, approximately 1,800 fee t of
new 60 inc
h welded steel transmission pipeline, a new 24 foot wide paved access road to Pump Station No. 1 including a new concrete box culvert for crossing the Caperton Canal, and associated side work including grading, paving, landscaping, retain ing
walls, equipme
nt pads structural foundations, and retention pond.

Owner’s Representative Services, Well 80, Sacramento Suburban Water District, CA:

Construction Administrator. West Yost is
providing Construction Management and Inspection services as part of its Owners Representative’s role beginning with the firs t of
up to four new monitoring wells and four new groundwater wells and associated pumpin g and treatment facilities. The projects
are being constructed under a progressive design build project delivery process. As the Owner’s Representative West Yost is representi
ng the district in the contracting and management of the progressive design build team.

River Trunk Realignment
–

Gravity System, City of Modesto, CA:

Construction Administrator for a $22 million construction project that includes trenching, conduit and pipe placement; backfill and compaction for approximately two miles of large diameter pi ping.

Staff Title:

Construction Manager I

Office Location:

Sacramento, CA

Years of Experience:

20 Years with West Yost:

8 Certifications

Confined Space Competent Person &
Confined Space Entry and Non
-
Entry
Rescue, June 2021

First Aid and CPR/AED, American Heart
Association, Certified
December 2023

10 -
Hour Cal OSHA Construction Safety
Certification, January 2021

Page 200 ends

06/09/2026 Item No.9.

Amy Rangel

2 This includes construction of concrete junction structures and requires a large public outreach effort and coordination with multiple stakeholders. The project consists of installation of approximately 1.7 miles of new 42 -
inch to 60
-
inch diameter Fibergla
ss
Reinforced Polymer Mortar Pipe (FRPMP) sanitary sewer pipeline, small diameter sewer collection pipelines, and smaller diamet er
potable water distribution pipelines, and construction of associated reinforced concrete junction structure and appurtenances

at
depths over 30 feet below existing ground surface. Key challenges to be addressed for successful completion of this project i nclude
extensive public outreach and traffic control as approximately ¾ of the alignment is routed along residential streets, d eep
excavation monitoring requiring engineered shoring and strict safety protocol adherence, vibration monitoring services due to

proximity of the work to residences, permit tracking, and coordination with multiple stakeholders such as the Modesto Irrigat i
on
District (MID) and various private utility companies that will be impacted by the project.

Primary administrator for the Construction
Manag
ement
Team, and was responsible for receiving, tracking, and distributing all submittals and RFIs

via CMIS document
management system
, as well as, preparing and issuing all Contract Change Orders

(using Ebuilder document management system)

and field directives.

Attended progress meeting and prepared detailed agendas and minutes as well as monthly status reports for
th
e
Owner.

River Trunk Realignment
–

Shackleford Pump Station, City of Modesto, CA:

Construction Administrator for the $10 million
construction of a 7
-
MGD sewage pump station, new pressure and gravity pipelines up to 36 inch diameter, and associated structures located in the City of Modesto and unincorporated Stanislaus County, CA. New f acilities include a sewage pump station
with three submersible screw centrifugal pumps located in a belowground cast in place concrete structure; associated pump station valves and flo
w meter located in a cast in place belowground concrete structure; a pump station electrical building, outdoor generator, and monorail crane; force main pipelines that operate under pressure, including ductile iron and polyvinyl

chloride pipe materials, in
stalled on a pump station site and through Dryden Park Golf Course; and sanitary sewer pipelines that flow by gravity installed on pump station site, within the public right of way and Golf Course.

Responsible for submittal
management (documenting, routing
, tracking), RFI management, change order creation, and preparing various status reports.

Attended weekly progress meetings, prepare and distributed meeting agendas and
minutes.

Greenback Sewer and Lift Pump Station, City of Folsom, CA:

Construction Administrator for this $2.5 million project that includes upgrades to Pump Station No. 3 (PS3) and sewer system modifications along Greenback to improve operational flexibility. Key components included piping and sanitary sewer manhole modifications, new flow control structures, and pipeline abandonment, as well
as interior changes to manholes to redirect flow from PS3 to Pump Station No. 2 (PS2). Additional work included relocating cit
y
-
owned sewer mains, reconnecting private sewer connections, and site improvements around PS3 such as drainage modifications, fencing, and new bypass pumping connections.

Served as the primary administrator and coordinator using Procore Construction Management Software for all project related documents, such as submittals and RFIs.

Responsible for tracking all
potential changes and preparing and issuing change orders and field directives and assisted with processing monthly pay applications. Attended prog
ress meeting and prepared detailed agendas and minutes.

Ashland Water Rehabilitation Project 1, City of Folsom, CA:

Construction

Administrator for this $2.3 million project
consisting of
the replacement of approximately 450 lineal feet (LF) of existing 20 -
inch ductile iron pipe (DIP) water main along Greenback Lane on the north and south sides of the Rainbow Bridge, relocation of existing and installation of new isolation val ves, rehabilitation of
existing blowoff and air release valves, and closed
-
circuit television (CCTV) inspection of the existing 21 -
inch and

18 -
inch water
main on Greenback Lane to the intersection at Folsom
-
Auburn Boulevard, and northbound along Folsom
-
Auburn Boulevard to
Hillswood Drive.

Served as the primary administrator and coordinator using Procore Construction Management Software for all project related documents, such as submittals and RFIs.

Responsible for tracking all potential changes and preparing and issuing change orders and field directives and assisted

Sanitation Lift Station SCADA Improvements, City of Garden Grove, CA :

Construction Administrator for the Garden Grove
Sanitation SCADA project consisting of

a complete replacement of each control panel, modifications to existing power feeds, installation of new field instrumentation, and integration of signals from MCCs, ATSs, and the generator at each of the three lift
station
site
s
.

Served as the primary administrator and coordinator using Procore Construction Management Software for all project related
documents, such as submittals and RFIs.

Responsible for tracking all potential changes and preparing and issuing change orders and field directives and assisted with processing monthly pay applications. Attended progress meeting and prepared detailed agendas and minutes.

Page 201 ends

06/09/2026 Item No.9.

Benjamin D. Crawford, PE, GE
Principal
Ben Crawford is the Founder and President of Crawford & Associates, Inc. He has managed complex projects including bridges, roadways, pavement rehabilitation, water and wastewater, parks, and trails. Ben leads the Crawford team in providing geotechnical construction observation and testing services. He oversees testing and inspection including soil backfill compaction testing; aggregate base compaction testing; asphalt concrete observation and testing; and concrete special inspection, sampling and testing.

REPRESENTATIVE PROJECTS
River Trunk Realignment: Beard Brook Siphon and Cannery Segregation, Modesto, CA
Principal Geotechnical Engineer. Prepared a Draft Geotechnical Study to upgrade and improve the River Trunk, Beard Brook Siphon, and Cannery Segregation Diversion Structures. Improvements include rehabilitation of the existing Sutter Trunk; replacement of the existing River Trunk with force main and gravity systems; installation of a pump station; replacement of the existing Beard Brook Siphon with a new gravity sewer beneath Dry Creek; reroute Shackelford Siphon to the new River Trunk gravity sewer; and utilization of the existing River Trunk facilities for future Cannery Segregation Line capacity needs. Design issues include deep excavation, dewatering, horizontal directional drilling, and liquefaction mitigation.

River Trunk Pipeline Rehabilitation at Gallo Winery, Modesto, CA As Principal Geotechnical Engineer, Ben oversaw the preparation of a Geotechnical Report for the River Trunk Pipeline Rehabilitation project located within the Gallo Winery property in Modesto, CA. The City of Modesto recently experienced a failure along the River Trunk Pipeline within the Gallo property. The failure occurred near the roof of the pipe due to fatigue and was likely not caused by a lack of soil support. Through this area the River Trunk Pipeline consists of a 45 to 60 inch diameter reinforced concrete pipe (RCP) approximately 10 feet below existing grade . Improvements to the pipeline will include slip lining the existing pipeline. Crawford analyzed subsurface and surface conditions and completed laboratory testing to provide geotechnical considerations for grading; soil excavatability and stability; scarification and compaction; and fill placement and backfill.

Modesto River Trunk Pipeline Realignment & Pump Station Project, Modesto, CA The overall project includes about 23,000 lineal feet of 15-60” diameter pipeline, new pump station with ancillary support structures, and various manhole and vault structures.

Crawford performed Cone Penetrometer Tests and exploratory test borings and installed vibrating wire piezometers during drilling to monitor groundwater conditions. Prepared a Geotechnical Report with analysis of subsurface conditions and provided pipeline, trench sidewalls, backfill material, and compaction recommendations. Foundation recommendations for the pump station and ancillary structures include Mat Foundations and Strip or Spread footings. Key geotechnical considerations include the variability in soil strata throughout the alignment and the presence of loose/soft soils within the planned pipe zone, and groundwater presence within the required deep excavations for the pump station.

Materials Testing for NVRRWP Turlock Component, Turlock, CA Principal-In-Charge. Oversaw staff providing grading observation and compaction testing as well as periodic concrete, bolt, and welding special inspection depending on material selection of the reservoir. Crawford staff were on-site to observe the placement of the rebar cages and concrete for CIDH piles. Reviewed daily field reports.

Materials Testing Industrial Tank No. 13 and Pump Station, Modesto, CA Principal-In-Charge. Oversaw staff provide the required grading observation and compaction testing, and periodic concrete, masonry, steel, and welding special inspection.

Crawford staff also performed laboratory testing on sampled materials, and prepared and provided daily field reports with findings, descriptions of the daily events, test results, and provided Geotechnical consulting services during construction.

EDUCATION
B.S. Civil Engineering,
California Polytechnic
State University, San Luis
Obispo, 2002

REGISTRATIONS
Civil Engineer, CA #68457
Geotechnical Engineer,
CA #2861

ORGANIZATIONS
• Geoprofessional
Business Association
• American Public Works
Association
• Modesto Engineers Club
• American Council of
Engineering Companies
• County Engineers
Association of California

EXPERIENCE
At Crawford: 11 years
Total: 21 years

AVAILABILITY
35%

Page 202 ends

06/09/2026 Item No.9.

Ed F. Darrimon

President/CEO

NACE No. 106

NACE Certified Level 3

(4
5 years of industry experience)

Professional Affiliations

Ed formed
B.A.C.C
. in 1987 and has 4
5 years

of

experience in the Coatings &
Linings Field.

Ed has completed thousands of projects

in

the past 4
5 years.

Ed administers

the daily operations and provides
high performance
technical
coating and lining specifications, failure
analysis, surveys, a
nd technical
consulting

in the water and wastewater industry
.

Ed Darrimon
started his career (1976) with

East Bay Municipal Utility District
for eleven years in the Engineering & Maintenance Departments as supervising coating specialist. Mr. Darrimon de
signed and de
veloped the District’s physical
coating and lining testing lab for accelerated testing and the Districts
Rehabilitation program

of 170 reservoirs, water treatment plants, and two
hydroelectric plants including penstocks
.

ACCOMPLISHMENTS

STEEL STRUCTURES PAINTING COUNCIL: (S.S.P.C.)

* National Board of Directors from 1988
-
92 (Pittsburg PA)
. Re
-
elected in 1992
-
96 to
serve second
four
-
year

term.

* National award 1989 for Outstanding Chairman

award
.

* Past President and F
ounder of the first S.S.P.C. chapter in the U.S.A

and which has
won the most chapter awards since 1986.

* Member of numerous committees, Education, Lead Removal, Urethane, Zinc, Epoxy, and Inspection.

NATIONAL ASSOCIATION OF CORROSION ENGINEERS: (N.A.C.E).

*Past

Chairperson / Bay Area Section

NACE

Ce
rtified Level III Inspector #106

AMERICAN WATER WORKS ASSOCIATION: (A.W.W.A)

*
Committee
Member National D
-
100, 103, 104,

106,

108, & 102 Standards
Comm
ittee

approval (
3 5
+

Years

-
present
)
Life Member award 2020

* Cal/
NV

Corrosion Committee. * Cal/
NV

past Vice Chairman Maintenance Committee.

Mr. Darrimon has presented numerous talks to the following Organizations:

A.W.W.A., N.A.C.E., & S.S.P.C. on the following topics: * Tank linings, 100%
solids technology using epoxies and polyurethanes,
Tank inspection,
Specifications, Abrasive b
lasting, &
Dehumidification use
. Ed has
published
articles

for the National Association of Corrosion Engineers on 100% solids usage,
technology and performance.

Published author in Material Performance

on tank linings
.

Past Projects:

Silicon Valley Water Authority
-

Numerous projects over the past twenty
years, including headworks, digesters, clarifiers, and contact basins.

SFPUC
-
Southeast/Oceanside WWTP. Numerous projects over the past twenty years, including headworks, digesters, clarifiers, and contact basins.

Or
a Loma WWTP
-

Numerous projects over the twelve years, including
headworks, digesters, clarifiers, and contact basins.

Delta Diablo WWTP

Numerous projects over the past
eighteen

years,
including headworks, digesters, clarifiers, and contact basins.

Truc
kee

Meadows Regional WWTP

Numerous projects over the past
twenty
-
five years, including headworks, digesters, clarifiers, and contact basins.

Page 203 ends

06/09/2026 Item No.9.

ID Task Name Duration Start Finish1Notice to Proceed0 daysWed 5/27/26Wed 5/27/262Kickoff Meeting0 daysThu 5/28/26Thu 5/28/263Preliminary Engineering10 daysFri 5/29/26Thu 6/11/264CEQA NOE5 daysFri 6/12/26Thu 6/18/26550% Design15 daysFri 5/29/26Thu 6/18/266City Review10 daysFri 6/19/26Thu 7/2/267Design Meeting0 daysFri 6/26/26Fri 6/26/268100% Design15 daysFri 6/19/26Thu 7/9/269City Review5 daysFri 7/10/26Thu 7/16/2610Design Meeting0 daysWed 7/15/26Wed 7/15/2611Final Bid-Ready Construction Documents3 daysFri 7/17/26Tue 7/21/2612Bidding23 daysWed 7/22/26Fri 8/21/2613Board Approval and Contracting5 daysMon 9/14/26Fri 9/18/2614Construction Phase95 daysFri 9/18/26Fri 1/29/2715Contractor NTP0 daysFri 9/18/26Fri 9/18/2616Submittal Prep, Review, Approval30 daysMon 9/21/26Fri 10/30/2617Mixer Procurement30 daysMon 11/2/26Fri 12/11/2618Zone 4 Tank 165 daysMon 10/5/26Fri 1/1/2719Shutdown0 daysMon 10/5/26Mon 10/5/2620Drain5 daysMon 10/5/26Fri 10/9/2621Scaffolding/Setup5 daysMon 10/12/26Fri 10/16/2622Sandblasting3 daysMon 10/19/26Wed 10/21/2623Structural Inspection3 daysThu 10/22/26Mon 10/26/2624Structural Report5 daysTue 10/27/26Mon 11/2/2625Tank Opening Modifications10 daysTue 10/27/26Mon 11/9/2626Coating and Spot Repair10 daysTue 11/10/26Mon 11/23/2627Mixer Installation and Testing10 daysMon 12/14/26Fri 12/25/2628Clean, Disinfect, Fill, Commission5 daysMon 12/28/26Fri 1/1/2729Site Work50 daysMon 10/19/26Fri 12/25/2630Electrical20 daysMon 11/30/26Fri 12/25/2631East Tank No. 125 daysMon 12/28/26Fri 1/29/2732Mixer Installation and Testing10 daysMon 12/28/26Fri 1/8/2733Miscellaneous Site15 daysMon 1/11/27Fri 1/29/2734Contingency44 daysMon 2/1/27Thu 4/1/273536Allowable Outage Window131 daysThu 10/1/26Thu 4/1/27 Notice to Proceed5/27
Kickoff Meeting5/28Preliminary Engineering6/11CEQA NOE 6/1850% Design 6/18City Review 7/2 Design Meeting 6/26100% Design7/9City Review7/16
Design Meeting7/15Final Bid-Ready Construction Documents 7/21Bidding 8/21Board Approval and Contracting 9/18 Contractor NTP 9/18Submittal Prep, Review, Approval10/30Mixer Procurement12/11 Shutdown10/5Drain 10/9Scaffolding/Setup 10/16Sandblasting 10/21Structural Inspection 10/26Structural Report 11/2Tank Opening Modifications11/9Coating and Spot Repair11/23Mixer Installation and Testing 12/25Clean, Disinfect, Fill, Commission 1/1Site Work 12/25Electrical 12/25 Mixer Installation and Testing 1/8Miscellaneous Site1/29Contingency4/1Allowable Outage Window 4/124/194/265/35/105/175/245/316/76/146/216/287/57/127/197/268/28/98/168/238/309/69/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/31/101/171/241/312/72/142/212/283/73/143/213/284/44/11AprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchApril2027 TaskMilestone
Summary
City TaskBy OthersPage 1City of Folsom - Zone 4 Phase 1 TankDesign and Construction ScheduleDate: Thu 5/7/26 ATTACHMENT B: PRELIMINARY PROJECT SCHEDULE
Schedule Notes:

The design is streamlined into two submittal milestones (50% and 100%) to reach the Bidding phase as soon as possible and ahead of the City's August 1, 2026 bid package deadline. Contractor Notice to Proceed is issued mid-September, providing time for early submittal approvals to enable outage related work activities (shown in orange) to begin near the start of the outage window in October.

Outage-related work is expected to be complete by January 2027. Equipment procurement, site work, and electrical work will proceed in parallel. East Tank No. 1 is understood to already be equipped with the access required to install the mixer/THM blower system. Therefore, no tank outage is anticipated to be needed for that work. Zone 4 Tank 1 will need to be fully drained to complete the work. East Tank No. 1 may need some modest water level adjustments to facilitate construction, but is not expected to require draining.

The schedule provides two months of contingency time for additional outage related work should it be needed, and/or for any unanticipated construction delays.

Page 204 ends

06/09/2026 Item No.9.

HydroScience Engineers
Proposed Fee: City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project Task Description
Bill Slenter, PIC
Eric Jones, Project
Manager
Austin Poulson, Project
Engineer
Thinh Le, Electrical Lead
Electrical Support
CAD ManagerHours Fee
ODCs
VE Solutions - Structural
West Yost - CM&I
Bay Area Coatings
Consultants - Coatings
QA
Expense
Subtotal
with Markup Total Fee
Phase
Totals
Labor Classification Princ E-VI E-II E-IX E-III CADM
Hourly Rate $330 $280 $258 $319 $240 $179
1 Project Management and Coordination $16,310
Project Management 16 16 $4,480 $0 $4,480
Project Communications 10 10 $2,800 $0 $2,800
QA/QC 8 8 $2,640 $0 $2,640
Design Phase Meetings 10 10 3 23 $6,337 $50 $53 $6,390
2 Preliminary Engineering $8,689
Schedule 2 6 8 $2,108 $0 $2,108
Field Investigation 6 6 6 18 $5,142 $100 $105 $5,247
CEQA NOE 2 3 5 $1,334 $0 $1,334
3 Design Phase Services $91,816
Water System Permit Updates 1 3 4 $1,054 $0 $1,054
Cost Estimate 2 6 2 10 $2,746 $0 $2,746
50% Design 35 70 18 55 16 194 $49,666 $0 $49,666
100% Design 25 40 15 24 8 112 $29,297 $0 $29,297
Final Design 5 20 2 4 5 36 $9,053 $0 $9,053
4 Bid Phase Services $10,810
Inquiries and Addenda (up to 3) 3 6 2 4 15 $3,986 $0 $3,986 Attend Pre-Bid Meeting 4 4 8 $2,152 $50 $53 $2,205
Conformed Set (up to 3 plan updates) 3 6 1 2 8 20 $4,619 $0 $4,619 5 Construction Phase Services $123,238
Structural Evaluation and Report 0 $0 $14,500 $15,225 $15,225 Meetings (3 In person, 13 virtual) 14 18 4 36 $9,840 $0 $9,840 Submittals (40 plus 20 resubmittals) 24 100 18 26 168 $44,502 $0 $44,502 RFIs (20 total) and General Proj Coord 8 40 30 8 16 102 $27,972 $0 $27,972 Design Modifications (3 total) 6 12 2 6 4 30 $7,570 $0 $7,570 Project Coordination (3 PCOs reviews) 3 6 3 12 $3,345 $0 $3,345 Site Visits (up to 3) 3 6 3 12 $3,345 $100 $105 $3,450
Startup and Testing Support 4 2 10 16 $4,158 $0 $4,158
Punchlist 4 4 4 12 $3,356 $0 $3,356
Record Drawings 3 6 8 17 $3,820 $0 $3,820
6 Construction Management and Inspection $223,179
CM&I Services 0 $0 $197,071 $206,925 $206,925
Coatings Inspection 0 $0 $15,480 $16,254 $16,254
TOTAL BASE FEE 16 225 358 93 151 49 892 $235,322 $300 $14,500 $197,071 $15,480 $238,719 $474,041 May 8, 2026
Notes:

1. See next page for CM&I fee detail.

Page 205 ends

06/09/2026 Item No.9.

Costs
West Yost Associates
CM IV
RI_G2
CM I

PE/PS/PG II
Hours
Fee
CFD
Sub.

Other
Total
$318
$247
$222
$355
w/ markup
Direct
Costs
PROJECT: City of Folsom Zone 4 Phase 1 Tank Rehabilitation Project - CM&I Services JP D.

Jason B./
Jesse S.

Amy R.

Jim M.
10%
Task
1 Preconstruction Phase (9/1/26 through 10/15/26)

1.01 Preconstruction Conference
2 2
4 8
2,018
$

2,018
$

1.02 Project Setup & Review
2 4
4 10
2,512
$

2,512
$

1.03 Preconstruction Photographic & Video Documentation 4 4
988
$

988
$

Subtotal, Task 1 (hours)
4 10
8 0
22 Subtotal, Task 1 ($)
1,272
$

2,470
$

1,776
$

5,518
$

5,518
$

Task
2 Construction Phase

2.01 Construction Coordination
96 96
30,528
$

30,528
$

2.02 Conduct Weekly Construction Meetings
24 32
56 14,736
$

14,736
$

2.03 Change Order, Changes, and Claims Management
8 8
2,544
$

2,544
$

2.04 Progress Payments
8 8
2,544
$

2,544
$

2.05 RFI & Submittal Management
45 45
9,990
$

9,990
$

2.06 Construction Observation/Inspection Services
420
420
103,740
$

103,740
$

2.07 Health & Safety Awareness
2 2
494
$

494
$

2.08 Material Sampling and Testing
0 5,000
$

5,500
$

5,500
$

2.09 Labor Compliance
28 28
6,216
$

6,216
$

2.10 SWPPP Compliance
4 4
988
$

988
$

2.11 Project Closeout (Punch List, Final Inspections, and Startup/Testing) 2 4
4 2
12 3,222
$

3,222
$

Subtotal, Task 2 (hours)
138
430
109
2 679
Subtotal, Task 2 ($)
43,884
$

106,210
$

24,198
$

710
$

175,002
$

5,500
$

180,502
$

Task
3 ODCs

3.01 Vehicle Usage
0 8,138
$

8,138
$

3.02 Annual Rate Increase (Assume 5%)
0 2,914
$

2,914
$

Subtotal, Task 3 (hours)
0 0
0 0
0 Subtotal, Task 3 ($)

11,051
$

11,051
$

TOTAL (hours)
142
440
117
2 701
TOTAL ($)
45,156
$

108,680
$

25,974
$

710
$

180,520
$

5,000
$

5,500
$

11,051
$

197,071
$

Est. Level of Effort % (TOTAL HRS/Max HRS)
22%
69%
18%
0%
Labor
Task 6 Fee Detail for West Yost Associates

Page 206 ends

06/09/2026 Item No.9.

Folsom City Council
Staff Report

1 MEETING DATE:

5/26/2026
AGENDA SECTION:

Consent Calendar
SUBJECT: Resolution No. 11624 - A Resolution Authorizing the City Manager to Execute Non-Exclusive Agreements for On- Call Engineering, Construction Inspection, and Surveying Services up to appropriated and available project specific budg ets with 4LEAF, Inc., BKF Engineers, Boswell & Associates, R EY
Engineers, Inc., and Unico Engineering
FROM: Public Works Department

RECOMMENDATION / CITY COUNCIL ACTION

The Public Works Department recommends that the Cit y Council pass and adopt Resolution No. 11624 - A Resolution Authorizing the City Manager to Execute Non-Exclusive Agreements for On-Call Engineering, Construction Inspection, a nd Surveying Services up to appropriated and available project specific budgets with 4LEAF, Inc., BKF Engineers, Boswell & Associates, REY Engineers, Inc., and Unico Engineering.

BACKGROUND

The Public Works Department oversees City right of way surveying and acquisition, drainage infrastructure, roadway maintenance and capital imp rovement projects. Many project deliverables and activities require specific techni cal involvement, including: environmental reports, construction drawings, right of way apprai sal/acquisition, utility coordination, and implementation of locally, state, and federally fun ded projects. Additional duties of Public Works staff include extensive coordination related to development projects, state stormwater permitting, regional agency coordination, encroachm ent permits, special event permits, and asset management. Currently, Public Works has two vacancies (Associate/Assistant Civil Engineer and Senior Civil Engineer) and carries a full workload staffed at half capacity.

In September of 2025, in collaboration with the Com munity Development Department, staff posted a Request for Proposal for On-Call Engineeri ng, Construction Inspection, and On-Call Surveying Services. Five Consultant Firms submitted proposals for one or more of the solicited contract services and included specialty subconsult ants such as geotechnical and traffic engineering. Staff rated the Proposals and selecte d all five firms to provide the City with On-

Page 207 ends

06/09/2026 Item No.10.
2 Call Services. Firms were ranked based on services offered, staff expertise and availability, specialty skills, and expenditure. Those firms inc lude 4LEAF, Inc., BKF Engineers, Boswell & Associates, REY Engineers, Inc., and Unico Engine ering. In November of 2026, City Council approved Resolution No. 11501 to approve on -call contracts for the Community Development Department. This is a replication of that effort for the Public Works Department to support capital project delivery and department workload.

Staff is recommending that the City Manager be authorized to execute these five non-exclusive agreements for a three-year period (June 1, 2026, t hrough June 1, 2029), by utilizing appropriated and available project specific budget.

POLICY / RULE

In accordance with Chapter 2.36 of the Folsom Municipal Code, contracts greater than $77,426 shall be awarded by the City Council.

ANALYSIS

Folsom has experienced consistently high volumes of capital project delivery, engineering permit review, and inspections with limited staff c apacity. To meet community needs, Folsom has consistently utilized on-call consultant servic e contracts for engineering, surveying, and inspection services. This resolution would authorize the execution of non-exclusive agreements with five firms to support the Public Works Departm ent. Funding for on-call services is identified through appropriated project budget and services procured through these contracts would be billed directly to capital project budgets.

In implementing these contracts for consulting services, staff will allocate work among the five selected consultants based on workload, technical n eed, expertise, and service costs. It is important to note that the Public Works Department will retain the flexibility to assign work to one or more of the selected firms. In other words, selected firms are not guaranteed assignment of work and are not limited to a fair share of the total. This allows Staff to determine how best to meet service needs as they arise. Example services include:

 Right of Way Surveying and Acquisition Services
 Geotechnical Engineering and Materials Testing
 Traffic Engineering and Analysis Support
 Civil and Structural Engineering (roadway, bridges and retaining walls)

For larger and state or federally funded projects w ith intentional scope of work, staff will continue to prepare Requests for Proposals to meet the requirements of the Caltrans Local Assistance Procedures Manual. For smaller efforts, staff will continue to prepare a cost-benefit analysis of high contract service costs against additional full-time staff to meet project delivery needs while making prudent use of the City’s limite d resources. The proposed on-call service solution allows flexibility in how the City meets c apital project needs and does not preclude alternative or supplemental solutions (e.g., full-t ime permanent staff, part-time temporary contract staff, pass through funding contracts).

Page 208 ends