conditions.
d. The Water Capacity Fee Charge for any new or expanded service connection shall be payable prior to the issuance of a building permit at the fee level in effect on the date such permit is issued.
6. The project applicant shall be required to pay all other water-related fees and charges in accordance with the City’s Master Fee Schedule and Municipal Code.
Sewer Requirements
The nearest sanitary sewer main to serve the proposed project is a 10-inch sewer main located in South West Avenue. Sanitary sewer facilities are available to provide service to the site subject to the following requirements:
1. Sewer connection to the 60-inch trunk line isn’t feasible.
2. Installation of sewer house branch(s) shall be required.
3. House branch(sewer lateral) lager than 6-inch shall require a manhole connection.
4. Street work permit is required for any work in the Right-of-Way.
5. On-site sanitary sewer facilities shall be private.
6. Abandon any existing on-site private septic systems.
7. The Project Developer shall contact Utility Billing and Collection Services at (559) 621-6765 prior to pulling building permits regarding conditions of service for special users.
Sanitary Sewer Fees
The following Sewer Connection Charges are due and shall be paid for the Project:
1. Sewer Lateral Charge.
2. Sewer Oversize Area #30.
3. Sewer Facility Charge (Non-Residential)
4. Upon connection of this Project to the City Sewer System the owner shall be subject to payment of Sewer Facility charges per Fresno Municipal Code Sections 6-304 and 6-305. Sewer Facility Charges consist of two components, a Wastewater Facilities Charge and Trunk Sewer Charge where applicable.
MEMORANDUM
MINDI MARIBOHO – Development Services Coordinator
Planning & Development Dept/Current Planning
January 27, 2021
DPU CONDITIONS OF APPROVAL FOR P20-04209 BUSSETO FOODS INC.
5. Sewer Facility Charges are collected after occupancy on a monthly basis over time based on metered (water or sewer effluent) usage. The developer may contact the Department of Public Utilities/Wastewater-Environmental Control at (559) 621-5153 to receive an estimated cost of the Sewer Facility Charges applicable to the project (based on a constant sewer discharge and loading (Biochemical Oxygen Demand [BOD] and Total Suspended Solids [TSS] levels anticipated) at the current rates in effect, at that time, per Fresno's Master Fee Resolution. The developer shall provide data regarding estimated sewer discharge rates [flow] and loading [BOD/TSS levels] required for calculating the estimated charge.
Solidwaste Requirements
1. Based on the square footage and use of the proposed project, the waste generated is the following:
• 607 cubic yards of food waste
• 712 cubic yards of recycle
• 712 cubic yards of refuse
2. Per the number listed above 60 trash enclosures will be required with a service frequency of 3 times of week. Due to these impracticable figures, compactors will be required for food, recycle and refuse seperately.
3. Location will be serviced by Mid Valley Disposal. Please contact at Mid Valley Disposal at 559-237-9425 for servicing.
4. Provide information on trash, food, and recycling compactors.
5. Provide 18’feet of unobstructed clearance in the area where the compactor units are kept.
6. Provided for trash (single cell, curb only if out of view of street would be acceptable)
7. One compactor and one 1-cell enclosure (curb only acceptable) required.
8. Provide 60’feet of clearance in front of compactor units and 3’ on either side for loading and unloading.
9. One compactor and one 1-cell enclosure (curb only acceptable) required.
10.Developer shall stripe the area in front of compactors “No Parking” trash loading only.
MEMORANDUM
MINDI MARIBOHO – Development Services Coordinator
Planning & Development Dept/Current Planning
January 27, 2021
DPU CONDITIONS OF APPROVAL FOR P20-04209 BUSSETO FOODS INC.
11.location will be required to file for a Roll off permit. Contact the City of Fresno, Solid Waste Division at 621-1452.
12.Rolloff permits will be required for each location. Contact Solid Waste Division @ 621-1452.
13.There are no compactors or enclosures shown
14.For every compactor, there needs to be second provided. Recycling and food are mandatory in the City of Fresno.
15.All compactors will need to be located within an enclosure, allowing at least 3' on either side for servicing. Also, compactors require 60' clear directly in front of the compactor for servicing.
16.Solid waste vehicles require 18' clear drive paths and have a 44' turning radius (centerline)
17.Restaurants require 3-cell enclosures for trash, recycling, and grease barrels. It is anticipated that the City of Fresno will be participating in a "Food Waste Program" which means providing 3-cell enclosures for each restaurant is even more critical
CERTIFICATION OF THE INSTALLATION OF REQUIRED
LANDSCAPING AND LANDSCAPE IRRIGATION SYSTEM
City of Fresno Development and Resource Management Department 2600 Fresno Street, Room 3043
Fresno, California 93721-3604
ATTN: ______________________________________________
[printed name of planner who processed the project listed below] REGARDING: ________________________________________________________ [Conditional Use Permit No. / Development Permit Review No. / Variance No. / Tract No.]
I, __________________________________, hereby certify, under penalty of perjury, that all [printed name of landscape professional]
landscaping and related irrigation system improvements have been installed as required pursuant to the final corrected landscape plans/exhibits approved by the City of Fresno for the above development project. These landscape exhibits, numbered ___________________, [numbers from entitlement file]
were submitted on ___________________ and were approved on ____________________ [date] [date]
by the above-named planner.
Certified by: x___________________________________
[signature of landscape professional]
Certified on: ____________________ ____________________________________ [date signed] [type of license, and license number of the signer] Telephone (with area code): (_________)_____________________________ Business Address: ________________________________________ ________________________________________