DISCUSSION

Staff solicited bids for this project pursuant to Municipal Code Section 2.50.100. Two (2) qualified bids were received at the City Clerk's office by 11:00 a.m. on September 9, 2024.

The lowest qualified contractor was RJ Noble Company, with a total bid of $2,883,465. The breakdown of the bid is as follows: $2,092,300 for the Micro -Surfacing improvements, $721,165 for the Parking Lot improvements located at 12966 Euclid Street, and $70,000 for the 5-year Landscape and Irrigation Maintenance. This bid amount is within the project budget. The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.

The anticipated contract schedule is as follows:

Award contract September 24, 2024
Begin construction (estimated) November 4, 2024
Complete construction (estimated) March 14, 2025

FINANCIAL IMPACT

The 2024 Various Streets Micro-Surfacing Project minus the parking lot improvements is funded by Gas Tax and Measure M2. The parking lot located at 12966 Euclid Street and the 5 -Year Landscape and Irrigation Maintenance is funded by the General Fund. All funding needs are included in the Fiscal Year 2024 -25 Amended Budget in the respective funds. No additional appropriation is needed to approve the contract.

RECOMMENDATION

It is recommended that the City Council:
 Award a contract to RJ Noble Company, in the amount of $2,883,465 for the 2024 Various Streets Micro -Surfacing Project, City Project No. CP -1422000 and 5-Year Landscape and Irrigation Maintenance, City Project No. CP-1438000; and  Authorize the City Manager, or designee to execute an agreement with RJ Noble Company, and make minor modifications as appropriate thereto, on behalf of the City.

By: Nick Hsieh, P.E.

ATTACHMENTS

1. Construction agreement

2. Bid Summary

410
-39-

C O N S T R U C T I O N A G R E E M E N T

RJ NOBLE COMPANY

THIS AGREEMENT is made this 24 day of September, 2024 by the CITY OF GARDEN GROVE, a municipal corporation, ("CITY"), and RJ NOBLE COM PANY, hereinafter referred to as ("CONTRACTOR").

RECITALS:

The following recitals are a substantive part of this Agreement:

1. This Agreement is entered into pursuant to Garden Grove City Council Authorization dated September 24, 2024.

2. CITY desires to utilize the services of CONTRACTOR to furnish material, equipment, and labor for the 2024 VARIOUS STREETS MICRO -SURFACING, P ROJECT NO . CP – 1422000 and 5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE , PROJECT NO. CP – 1438000.

3. CONTRACTOR is qualifie d by virtue of experience, training, education, and expertise to accomplish services.

AGREEMENT
THE PARTIES MUTUALLY AGREE AS FOLLOWS:

5.1 General Conditions. CONTRACTOR certifies and agrees that all the terms, conditions and obligations of the Contract Documents as hereinafter defined, the location of the job site, and the conditions under which the work is to be performed have been thoroughly reviewed, and enters into this Contract based upon CONTRACTOR'S investigation of all such matters and is in no w ay relying upon any opinions or representations of CITY. It is agreed that this Contract represents the entire agreement. It is further agreed that the Contract Documents including the Notice Inviting Bids, Special Instructions to Bidders, if any, Plans, Specifications, and CONTRACTOR's Proposal, are incorporated in this Contract by reference, with the same force and effect as if the same were set forth at length herein, and that CONTRACTOR and its subcontractors, if any, will be and are bound by any and all of said Contract Documents insofar as they relate in any part or in any way, directly or indirectly, to the work covered by this Contract.

"Project" as used herein defines the entire scope of the work covered by all the Contract Documents. Anything m entioned in the Specifications and not indicated in the Plans, or indicated in the Plans and not mentioned in the Specifications, shall be of like effect as if indicated and mentioned in both. In case of discrepancy in the Plans or Specifications, the matter shall be immediately submitted to CITY’S Engineer, without whose decision CONTRACTOR shall not adjust said discrepancy save only at CONTRACTOR'S own risk and expense. The decision of the Engineer shall be final.

411
SECTION 5 - AGREEMENT (Continued)
-40-

5.2 Materials and Labor. CONTRACTOR shall furnish, under the conditions expressed in the Plans and Specifications, at CONTRACTOR'S own expense, all labor and materials necessary, except such as are mentioned in the Specifications to be furnished by the CITY, to construct and complete the proj ect, in good workmanlike and substantial order. If CONTRACTOR fails to pay for labor or materials when due, CITY may settle such claims by making demand upon the surety to this Agreement. In the event of the failure or refusal of the surety to satisfy sa id claims, CITY may settle them directly and deduct the amount of payments from the Contract price and any amounts due to CONTRACTOR. In the event CITY receives a stop notice from any laborer or material supplier alleging non -payment by CONTRACTOR, CITY s hall be entitled to deduct all of its costs and expenses incurred relating thereto, including but not limited to administrative and legal fees.

5.3 Project. The PROJECT is described as: 2024 VARIOUS STREETS MICRO - SURFACING, P ROJECT NO . CP – 1422000 and 5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE, PROJECT NO. CP – 1438000.

5.4 Plans and Specifications. The work to be done is shown in a set of detailed Plans and Specifications entitled: 2024 VARIOUS STREETS MICRO-SURFACING, PROJECT NO.

CP – 1422000 and 5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE , PROJECT NO . CP – 1438000. Said Plans and Specifications and any revision, amendments or addenda thereto are attached hereto and incorporated herein as part of this Contract and referred to by reference. Th e work to be done must also be in accordance with the General Provisions, Standard Specifications and Standard Plans of the CITY, which are also incorporated herein and referred to by, reference.

5.5 Time of Commencement and Completion . CONTRACTOR shall have fourteen (14) calendar days from the award of the Contract to execute the Contract and supply the CITY with all the documents and information required by the Instructions to Bidders and the other Contract Documents, including but not limited to, the necessary bonds and insurance certificates and endorsements. Once the CITY receives the executed contract and all of the other properly drafted and executed documents and information, it may issue a Notice to Proceed to the CONTRACTOR. If CONTRACTOR refuses or fails to provide the required documents and information within the ten (10) city working days, the CITY may then rescind the award of the Contract and then award the Contract to the next lowest responsive and responsible bidder.

The Contract time shall begin on November 4, 2024 and the Garden Grove Plaza Parking Lot shall be completed by January 31, 2025 . Upon receipt of the Notice to Proceed, the CONTRACTOR agrees to submit shop drawings within fourteen (14) calendar days. The CONTRACTOR shall diligently prosecute the work within 80 (Eighty) working days to completion as required per the plans and specifications excluding delays caused or authorized by the CITY as set forth in Sections 5.7, 5.8 and 5.9 hereof.

5.6 Time is of the Essence. Time is of the essence of this Contract.

Contractor shall have fourteen (14) calendar days from the award of the Contract to execute the Contract and supply CITY with all of the documents and information required by the Instruction to Bidders and the other Contract Documents, including but not limited to, the necessary bonds and insurance certificates and endorsements. Once the CITY receives the executed Contract and all of the other properly drafted and executed documents and information, it may issue a Notice to Proceed t o the CONTRACTOR. If CONTRACTOR refuses or fails to execute the Contract or refuses or fails to provide the required documents and information within the fourteen (14) calendar days, the CITY may then rescind the 412
SECTION 5 - AGREEMENT (Continued)
-41-

award of the Contract and then award the Co ntract to the next lowest responsible and responsive bidder.

As required by the Contract Documents, CONTRACTOR shall prepare and obtain approval of all shop drawings, details and samples, and do all other things necessary and incidental to the prosecution of CONTRACTOR'S work in conformance with an approved construction progress schedule. CONTRACTOR shall coordinate the work covered by this Contract with that of all other CONTRACTORs, subcontractors and of the CITY, in a manner that will facilitate the efficient completion of the entire work in accordance with Section 5.5 herein.

CITY shall have complete control of the premises on which the work is to be performed and shall have the right to decide the time or order in which the various portions of the work shall be installed or the priority of the work of other subcontractors, and, in general, all matters representing the timely and orderly conduct of the work of CONTRACTOR on the premises.

5.7 Excusable Delays. CONTRACTOR shall be excused for any delay in t he prosecution or completion of the Project caused by acts of God; inclement weather; damages caused by fire or other casualty for which CONTRACTOR is not responsible; any act of negligence or default of CITY; failure of CITY to make timely payments to CONTRACTOR; late delivery of materials required by this CONTRACT to be furnished by CITY; combined action of the workers in no way caused by or resulting from default or collusion on the part of CONTRACTOR; a lockout by CITY; or any other delays unforeseen by CONTRACTOR and beyond CONTRACTOR'S reasonable control.

CITY shall extend the time fixed in Section 5.5 herein for completion of the Project by the number of days CONTRACTOR has thus been delayed, provided that CONTRACTOR presents a written request to CIT Y for such time extension within fifteen (15) days of the commencement of such delay and CITY finds that the delay is justified. CITY'S decision will be conclusive on the parties to this Contract. Failure to file such request within the time allowed shall be deemed a waiver of the claim by CONTRACTOR.

No claims by CONTRACTOR for additional compensation or damages for delays will be allowed unless CONTRACTOR satisfies CITY that such delays were unavoidable and not the result of any action or inaction of C ONTRACTOR and that CONTRACTOR took all available measures to mitigate such damages. Extensions of time and extra compensation as a result of incurring undisclosed utilities would be determined in accordance with SPECIAL PROVISIONS and Section 3 -3 of the S tandard Specifications for Public Works Construction 2006 Edition (GREEN BOOK). The CITY’S decision will be conclusive on all parties to this Contract.

5.8 Extra Work . The Contract price includes compensation for all work performed by CONTRACTOR, unless CONTRACTOR obtains a written change order signed by a designated representative of CITY specifying the exact nature of the extra work and the amount of extra compensation to be paid all as more particularly set forth in Section 5.9 hereof.

CITY shall extend the time fixed in Section 5.5 for completion of the Project by the number of days reasonably required for CONTRACTOR to perform the extra work, as determined by CITY’S Engineer. The decision of the Engineer shall be final. 413
SECTION 5 - AGREEMENT (Continued)
-42-

5.9 Changes in Project.

5.9.1 CITY may at any time, without notice to any surety, by written order designated or indicated to be a change order, make any change in the work within the general scope of the Contract, including but not limited to changes:
a. In the Specifications (including drawings and designs); b. In the time, method or manner of performance of the work; c. In the CITY -furnished facilities, equipment, materials, services or site; or d. Directing acceleration in the performance of the work.

If CONTRACTOR believes that the written order issued as part of this Section 5.9.1 has caused an increase in costs or time, the CONTRACTOR shall submit a written request for equitable adjustment to the CITY that includes a detailed cost breakdown and time impact analysis in sufficient detail to allow the CITY to analyze the request.

Said notice shall be submitted via certified mail within twenty (20) days of the CONTRACTOR’S receipt of the written order. CONTRACTOR’S failure to submit the written request for equitable adjustment within the required twenty (20) days shall constitute a waiver of any potential change order or claim for said alleged change.

The CITY shall review CONTRACTOR’S request and shall provide a written response within thirty (30) days of receipt of the request either approving or denying the request.

5.9.2 A change may also be any other conflict, difficulty or issue which the CONTRACTOR believes caused any change to the CONTRACTOR’S costs or project schedule, provided CONTRACTOR gives the CITY written notice and a request for equitable adjustment that includes a detailed cost breakdown and time impact analysis in sufficient detail to allow the CITY to analyze the request. The notice shall also state the date the CONTRACTOR became aware of the issue, circumstances and source of the issue and that CONTRACTOR regards the issue as a change order. Said written notice shall be delivered to the CITY via certified mail within twenty (20) days of CONTRACTOR’S first notice of the issue.

CONTRACTOR’S failure to submit the n otice, which includes the written request for equitable adjustment within the required twenty (20) days shall constitute a waiver of ant potential change order or claim for said alleged change. The CITY shall review CONTRACTOR’S request and shall provide a written response within thirty (30) days of receipt of the request either approving or denying the request.

5.9.3 Except as provided in this Section 5.9, no order, statement or conduct of the CITY or its representatives shall be treated as a change under this Section 5.9 or entitle CONTRACTOR to an equitable adjustment.

5.9.4 Except for claims based on defective specifications, no claim for any change under paragraph 5.9.1 or 5.9.2 above shall be allowed for any work performed more than 20 days before the CONTRACTOR gives written notice as required in paragraphs

5.9.1 and 5.9.2. In the case of defective specifications for which the CITY is responsible, the equitable adjustment shall include any increased direct cost CONTRACTOR reasonably incurred in att empting to comply with those defective specifications.

414
SECTION 5 - AGREEMENT (Continued)
-43-

5.9.5 If CONTRACTOR intends to assert a claim for an equitable adjustment under this Section 5.9, it must, within thirty (30) days after receipt of a denial of a request for equitable adjustment under paragraphs 5.9.1 and 5.9.2, submit a written statement to the CITY setting forth the general nature and monetary extent of such claim.

The CITY may extend the 30-day period. CONTRACTOR’S failure to submit the notice of a claim, within the required thirty (30) days shall constitute a waiver of the claim by the CONTRACTOR.

5.9.6 No claim by CONTRACTOR for an equitable adjustment shall be allowed if made after final payment under this Agreement.

5.9.7 CONTRACTOR hereby agrees to make any and all changes, furnish the materials and perform the work that CITY may require without nullifying this Contract.

CONTRACTOR shall adhere strictly to the Plans and Specifications unless a change there from is authorized in writing by the CITY. Under no condition shall CONTRACTOR make any changes to the Project, either in additions or deductions, without the written order of the CITY and the CITY shall not pay for any extra charges made by CONTRACTOR that have not been agreed upon in advance in writing by the CITY. CONTRACTOR shall submit immediately to the CITY written copies of its firm's cost or credit proposal for change in the work.

Disputed work shall be performed as ordered in writing by the CITY and the proper cost or credit breakdowns therefor shall be submitte d without delay by CONTRACTOR to CITY.

5.10 Liquidated Damages for Delay. The parties agree that if the total work called for under this Contract, in all parts and requirements, is not completed within the time specified in Section 5.5 herein, plus the al lowance made for delays or extensions authorized under Sections 5.7, 5.8 and 5.9 herein, the CITY will sustain damage which would be extremely difficult and impractical to ascertain. The parties therefor agree that CONTRACTOR will pay to CITY the sum of Two Thousand Dollars ($ 2,000.00) per day for each and every calendar day during which completion of the Project is so delayed. CONTRACTOR agrees to pay such liquidated damages and further agrees that CITY may offset the amount of liquidated damages from any monies due or that may become due CONTRACTOR under the Contract.

5.11 Contract Price and Method of Payment . CITY agrees to pay and the CONTRACTOR agrees to accept as full consideration for the faithful performance of this Contract, subject to any subsequent additions or deductions as provided in approved change orders, the sum of Two Million Eight Hundred Eighty Three Thousand Four Hundred Sixty Five Dollars and No Cents ($ 2,883,165.00 ) as itemized in the bid proposal.

Progress payments shall be made to the CONTRACTOR on a monthly basis for each successive month as the work progresses. The CONTRACTOR shall be paid such sum as will bring the total payments received since the commencement of the work up to ninety-five percent (95%) of the value of the work completed, less all previous payments, provided that the CONTRACTOR submits the request for payment prior to the end of the day required to meet the payment schedule. The CITY will retain five percent (5%) of the amount of each such progress estimate and material cost until 30 days after the recordation of the Notice of Completion.

Payments shall be made on demands drawn in the manner required by law, accompanied by a certificate signed by the CITY’S Engineer, stating that the work for which payment i s demanded has been performed in accordance with the terms of the Contract. Partial 415
SECTION 5 - AGREEMENT (Continued)
-44-

payments of the Contract price shall not be considered as an acceptance of any part of the work.

5.12 Substitution of Securities in Lieu of Retention of Funds. Pursuant to California Public Works Contract Code § 22300, the CONTRACTOR will be entitled to post approved securities with the CITY or an approved financial institution in order to have the CITY release funds retained by the CITY to ensure performance of the Contract. CONTRACTOR shall be required to execute an addendum to this Contract together with escrow instructions and any other documents in order to effect this substitution.

5.13 Completion. Within 10 days after the contract completion date of the Project, CONTRACTOR shall file with the CITY’S Engineer its affidavit stating that all workers and persons employed, all firms supplying materials, and all subcontractors upon the Project have been paid in full, and that there are no claims outstanding against the Project for either labor or material, except those certain items, if any, to be set forth in an affidavit covering disputed claims, or items in connection with Stop Notices which have been filed under the provisions of the statutes of the State of California. CITY may require affidavits or certificates of payment and/or releases from any subcontractor, laborer or material supplier.

5.14 CONTRACTOR 's Employees Compensation

5.14.1 General Prevailing Rate . CITY has ascertained CONTRACTOR shall comply with all applicable req uirements of Division 2, Part 7, Chapter 1 of the California Labor Code and all applicable federal requirements respecting the payment of prevailing wages. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the prevailing wage rates determined by the Director of the Department of Industrial Relations (DIR) for similar classifications of labor, the CONTRACTOR and its Subcontractors shall pay not less than the higher wage rate. The DIR will not accept lower State wage rates not specifically included in the Federal minimum wage determinations. This includes "helper" (or other classifications based on hours of experience) or any other classification not appearing in the Federal Wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the CONTRACTOR and Subcontractors, the CONTRACTOR and its Subcontractors shall pay not less than the Federal Minimum wage rate which most closely approximate s the duties of the employees in question."

5.14.2 Forfeiture for Violation. CONTRACTOR shall, as a penalty to the CITY, forfeit one hundred dollars ($100.00) for each calendar day or portion thereof for each worker paid (either by the CONTRACTOR or any subcontractor under it) less than the prevailing rate of per diem wages as set by the Director of Industrial Relations, in accordance with Sections 1770-1777 of the California Labor Code for the work provided for in this Contract, all in accordance with Sec tion 1775 of the Labor Code of the State of California.

5.14.3 Apprentices. Section 1777.5, 1777.6 and 1777.7 of the Labor Code of the State of California, regarding the employment of apprentices is applicable to this Contract and the CONTRACTOR shall comply therewith; provided, however, that this requirement shall not apply if and/or to the extent that the Contract of the general CONTRACTOR, or the contracts of specialty contractors not bidding for work through a general or prime contractor involve less than thirty thousand dollars ($30,000.00).
416
SECTION 5 - AGREEMENT (Continued)
-45-

5.14.4 Workday. In the performance of this Contract, not more than eight (8) hours shall constitute a day's work, and CONTRACTOR shall not require more than eight (8) hours of labor in a day from any person employed by him hereunder except as provided in paragraph (5.14.2) above. CONTRACTOR shall conform to Article 3, Chapter 1, Part 7 (Sections 1810 et seq.) of the Labor Code of the State of California and shall forfeit to the CITY as a penalty, the sum of twenty -five Dollars ($25.00) for each worker employed in the execution of this Contract by CONTRACTOR or any subcontractor for each calendar day during which any worker is required or permitted to labor more than eight (8) hours in any one calendar day and forty (40) hours in any one week in violation of said Article.

CONTRACTOR shall keep an accurate record showing the name and actual hours worked each calendar day and each calendar week by each worker employed by CONTRACTOR in connection with the Project.

5.14.5 Record of Wages: Inspection . CONTRACTOR agrees to maintain accurate payroll records showing the name, address, social security number, work classification, straight-time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker or other employee employed by it in connection with the Project and agrees to require that each of its subcontractors does the same. The applicable CONTRACTOR or subcontractor or its agent having authority over such matters shall certify all payroll records as accurate. CONTRACTOR further agrees that its payroll records and those of its subcontractors shall be available to the employee or employee's representative, the Division of Labor Standards Enforcement, and the D ivision of Apprenticeship Standards and shall comply with all of the provisions of Labor Code Section 1776, in general. CONTRACTOR shall comply with all of the provisions of Labor Code Section 1776, and shall submit payroll records to the Labor Commissioner pursuant to Labor Code section 1771.4(a)(3). The CONTRACTOR shall submit copies of certified payroll reports and cancelled checks for labors, every two weeks to the Engineer. Certified payroll and cancelled checks submittals are due one month after st art of construction and every two weeks thereafter. If the certified payroll and cancelled checks are not submitted, the CONTRACTOR will be notified that compliance is required within five (5) working days or contract work must cease. The CITY will not be responsible for any delay or acceleration charges or any incurred costs or damages as a result of the work stoppage due to CONTRACTOR’s failure to comply. Work shall be ceased in an orderly, safe fashion with all vehicle access restored. Should this not occur, CITY will correct the deficiencies and deduct the cost from funds due to the CONTRACTOR. In addition, no progress payment shall be made until the copies of certified payroll reports and cancelled checks are submitted.

5.14.6 Contractor Registration. CONTRACTOR and its subcontractors must be registered with the California Department of Industrial Relations pursuant to Labor Code Section 1725.5. This Agreement shall not be effective until CONTRACTOR provides proof of registration to the CITY.

5.14.7 Posting of Job Site Notices . CONTRACTOR shall comply with the job site notices posting requirements established by the Labor Commissioner pursuant to Title 8, California Code of Regulations Section 16461(e) or other regulation promulgated pursuant to Labor Code Section 1771.4(a) (2). 417
SECTION 5 - AGREEMENT (Continued)
-46-

5.14.8 Notice of DIR Compliance Monitoring and Enforcement. Pursuant to Labor Code Section 1771.4, this Project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations.

5.15 Surety Bonds . CONTRACTOR shall, prior to entering into performance of this Agreement, furnish a performance bond, on the CITY's bond form in the amount of one hundred percent (100%) of the Contract price, to guarantee the faithful performance of the work, and a payment bond, on the CITY's form in the amount of one hundred percent (100%) of the Contract price, to guarantee payment of all claims for labor and materials furnished. Bonds submitted on any form other than the CITY's form will be rejected. The required bonds shall be from a surety licensed to do business in the State of California and with a current A.M. Best's rating of A -, VII. This Contract shall not become effective until such bonds are supplied and approved by the CITY."

5.16 Insurance.

5.16.1 COMMENCEMENT OF WORK . CONTRACTOR shall not commence work under this Agreement until all certificates and endorsements have been received and approved by the CITY. All insurance required by this Agreement shall contain a statement of obligation on t he part of the carrier to notify the city of any material change, cancellation, or termination at least thirty (30) days in advance. A waiver of subrogation shall be provided by the insurer for each policy waiving subrogation against CITY, its officers, o fficials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents, and employees, as determined by the CITY, Claims made and modified occurrence policies shall not be accepted for any policy , unless otherwise indicated . All Subcontractors shall be required to provide and maintain the same insurances as required of CONTRACTOR under this contract. CONTRACTOR shall be required to collect and maintain all required insurances from all Subcontractors.

5.16.2 CONTRACTOR is aware of the provisions of Section 3700 of the Labor Code, which requires every employer to be insured against liability for Workers’ Compensation or undertake self -insurance in accordance with the provisio ns of that Code, and will comply with such provisions before commencing the performance of the work of this Contract.

5.16.3 CONTRACTOR and all Subcontractors shall carry workers' compensation insurance for the protection of its employees during the progress of the work. The insurer shall waive its rights of subrogation against the CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents, an d employees, as determined by the CITY, and shall issue a waiver of subrogation.

5.16.4 Before CONTRACTOR performs any work at, or prepares or delivers materials to, the site of construction, CONTRACTOR shall furnish:

Additional Insured Endorsements, ongoing an d products -completed operations, for the Commercial General Liability policy , including mobile equipment and not excluding XCU and on the Contractors’ Pollution Liability policy, if available. Endorsements shall designate CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents, and 418
SECTION 5 - AGREEMENT (Continued)
-47-

employees, as determined by the CITY, as additional insureds for liability arising out of work or operat ions performed by or on behalf of the CONTRACTOR.

CONTRACTOR shall provide to CITY proof of insurance and endorsement forms that conform to CITY’s requirements, as approved by the CITY (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10, CG 20 26, CG 20 33, or CG 20 28; and CG 20 37 forms if later revisions used). Insurance companies must be acceptable to CITY and have a minimum A.M. Best Guide rating of A -, class VII or better, as approved by CITY.

Contractor’s Pollution Legal Liability : Insurance companies must be acceptable to City and have a Best’s Guide Rating of A - Class VII or better, as approved by Authority. If policy is written on a claims-made form:
1) The retroactive date must be shown, and must be before the date of the contract or the beginning of contract work.
2) Insurance must be maintained and evidence of insurance must be provided for at least three (3) years after completion of the contract work.
3) If coverage is canceled or non-renewed, and not replaced with another claims-made policy with a retroactive date prior to the contract effective date, the CONTRACTOR must purchase an extended period coverage for a minimum of three (3) years after completion of the contract work. 4) A copy of the claims reporting requirements must be submi tted to the CITY for review.

Automobile Liability policy and shall designate CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents , and employees, as determined by the CITY, as additional insureds for automobiles owned, leased, hired, or borrowed by the CONTRACTOR. CONTRACTOR shall provide to CITY proof of insurance and endorsement forms that conform to CITY’s requirements, as appro ved by the CITY . Insurance companies must be acceptable to CITY and have a minimum A.M. Best Guide rating of A -, class VII or better, as approved by CITY).

In the event any of CONTRACTOR’S underlying policies do not meet policy limits as required here in, CONTRACTOR shall provide the schedule of underlying polices for a follows form excess liability policy, state that the excess policy follows form on the insurance certificate, and an additional insured endorsement for the excess liability policy designatin g CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents, and employees, as determined by the CITY, as additional insureds . Insurance companies must be acceptable to CITY and have a minimum A.M. Best Guide rating of A -, class VII or better, as approved by CITY.

For any claims related to this Project, the CONTRACTOR’s insurance coverage shall be primary insurance at least as broad as ISO CG 20 01 04 13 as respects CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, 419
SECTION 5 - AGREEMENT (Continued)
-48-

officers, agents, and employees, as determined by the CITY . A ny insurance or self-insurance maintained by the CITY, its officers, officials, employees, agents, and volunteers for this contract and all public agencies from whom permits will be obtained and their directors, officers, agents, and employees, as determin ed by the CITY, shall be excess of the CONTRACTOR’s insurance and not contribute with it.

5.16.5 Before CONTRACTOR performs any work at, or prepares or delivers materials to, the site of construction, CONTRACTOR shall furnish:

CONTRACTOR shall maintain all of the foregoing insurance coverage in force until the work under this Contract is fully completed. The requirement for carrying the foregoing insurance shall not derogate from the provisions for indemnification of CITY by CONTRACTOR under Section 5.17 of this Contract. Notwithstanding nor diminishing the obligations of CONTRACTOR with respect to the foregoing, CONTRACTOR shall subscribe for and maintain in full force and effect during the life of this Contract, the following insurance in amounts not less than the amounts specified and issued by a company admitted and licensed in California and having a Best's Guide Rating of A-Class VII or better:

Workers’ Compensation As required by the State of
California.

Employer’s Liability

Not less than $1,000,000 per
accident for bodily injury or disease.

Commercial General Liability
(including on-going operations, products
- completed operations, and mobile
equipment, and not excluding XCU)

Contractor’s Pollution Legal Liability

Not less than $5,000,000 per
occurrence for bodily injury,
personal injury and property
damage.

Not less than $1,000,000 per
occurrence

Automobile Liability, for all automobiles
including non-owned and hired vehicles
Not less than $2,000,000 combined
single limit for bodily injury and
property damage.

Follows Form Excess Liability

Required for any underlying policy
that does not meet the underlying
policy limits required herein.

If contractor maintains higher insurance limits than the minimums shown above, CONTRACTOR shall provide coverage for the higher limits otherwise maintained by the CONTRACTOR.

CITY or its representatives shall at all times have the right to inspect and receive a certified copy of all said policies of insurance, including certificates and endor sements at 420
SECTION 5 - AGREEMENT (Continued)
-49-

CONTRACTORS sole cost and expense. CONTRACTOR shall pay the premiums on the insurance hereinabove required.

5.17 Risk and Indemnification. All work covered by this Contract done at the site of construction or in preparing or delivering materials to the site shall be at the risk of CONTRACTOR alone.

CONTRACTOR agrees to save, indemnify and keep the CITY, its Officers, Agents, Employees, Engineers, and Consultants for this Contract, and all public agencies from whom permits will be obtained and their directors, Officers, Agents and Employees harmless against any and all liability, claims, judgments, costs and demands, including demands arising from injuries or death of persons (CONTRACTOR'S employees included) and damage to property, arising directly or indirectly out of the obligations herein undertaken or out of the operations conducted by CONTRACTOR, save and except claims or litigation arising through the sole negligence or sole willful misconduct of CITY and will make good to reimburse CITY for any expenditures, including reasonable attorneys' fees CITY may incur by reason of such matters, and if requested by CITY, will defend any such suits at the sole cost and expense of CONTRACTOR.

5.18 Termination. This Contract may be terminated in whole or in part in writing by the CITY in the event of substantial failure by the CONTRACTOR to fulfill its obligations under this Agreement, or it may be terminated by the CITY for its convenience in the manner provided for in subsections A and B below. If termination for default or convenience is effected by the CITY, an equitable adjustment in the price provided for in this Contract shall be made, but (1) no amount shall be allowed for anticipated profit on unperformed services or other work, and (2) any payment due to the CONTRACTOR at the time of termination may be adjusted to cover any additional costs to the CITY because of the CONTRACTOR'S default. Upon receipt of a termination action, the CONTRACTOR shall (1) promptly discontinue all affected work (unless the n otice directs otherwise), and (2) deliver or otherwise make available to the CITY all data, drawings, specifications, reports, estimates, summaries and such other information and materials as may have been accumulated by the CONTRACTOR in performing this C ontract whether completed or in process. Upon termination, the CITY may take over the work and may award another party an agreement to complete the work under this Contract.

A. Termination for Default.

If the CONTRACTOR refuses or fails to prosecute the work or any separable part thereof with such diligence as will ensure its completion within the time specified herein, or any authorized extension thereof, or fails to perform the work in a manner required by the Contract Documents and/or industry standards, or fails to complete such work within such time as required under the Contract Documents or, if the CONTRACTOR should be adjudged as bankrupt, or is otherwise deemed insolvent by CITY based on good cause and is unable to proceed with the work, or if the CONTRACTOR should make a general assignment for the benefit of creditors, or if a receiver should be appointed on account of insolvency, or if the CONTRACTOR files a petition to take advantage of any debtor’s act, or should any subcontractor violate an y of the provisions of the Contract Documents, or if the CONTRACTOR should persistently or repeatedly refuse or fail, except in cases for which an authorized extension of time is provided, to supply enough properly skilled workers or proper materials to co mplete the work in the time specified, or if the CONTRACTOR should fail to make prompt payment to subcontractors for material or labor, or if the CONTRACTOR should persistently disregard laws, or instructions given by CITY, or if the CONTRACTOR otherwise s ubstantially fails to fulfill its obligations under the Contract Documents, CITY may, without prejudice to any other right or remedy, serve 421
SECTION 5 - AGREEMENT (Continued)
-50-

written notice upon the CONTRACTOR and Sureties of CITY’s intention to terminate the CONTRACTOR’s performance under the contract. Said notice shall contain the reasons for such intention to terminate the CONTRACTOR’s performance under the contract, and unless, within ten (10) days after the service of such notice, such violations cease and/or satisfactory arrangements f or the corrections thereof have been made, the CITY may terminate CONTRACTOR’s performance under the contract and the CONTRACTOR shall not be entitled to receive any further payment until the work is completed.

In the event of any such termination, CITY shall serve written notice thereof upon the Surety and CONTRACTOR, and the Surety shall have the right to take over and perform the contract. However, if the Surety, within five (5) days after the service of a notice of termination, does not give CITY writt en notice of its intention to take over and perform the contract, and if it serves such notice of its intent to take over and perform the contract and does not begin performance thereof within fifteen (15) days from the date of serving said notice, CITY ma y take over the work and prosecute the same to completion by contract or by any other method it may deem advisable for the account and at the expense of the CONTRACTOR, and the Sureties and/or CONTRACTOR shall be liable to CITY for any excess cost or other damage incurred by CITY thereby. If the Surety assumes the CONTRACTOR’s terminated work, it shall take the CONTRACTOR’s place in all respects for that part and shall be paid by CITY for all work performed by it in accordance with the terms of the Contract Documents. If the Surety assumes the entire contract, all money due the CONTRACTOR at the time of its default shall be payable to the Surety as the work progresses, subject to the terms of the contract.

CONTRACTOR hereby consents to assigning to CITY and /or CITY’s replacement contractor all subcontracts and other agreements of any and all subcontractors and/or suppliers that may be on the worksite and/or may be necessary to complete the work in the event of Termination for Default or Termination for Conve nience, as set forth below. CONTRACTOR agrees to obtain, by way of a subcontract provision, the consent of each and every subcontractor and/or supplier for such assignment prior to the commencement of each such subcontractor’s and/or supplier’s work on the PROJECT.

In the event of such termination, the CONTRACTOR will be paid the actual amount due based on unit prices or lump sums Bid and the quantity of work completed at the time of termination, less damages caused to CITY by acts of the CONTRACTOR causing the termination, including but not limited to, all costs to CITY arising from professional services and attorneys' fees and all costs generated to insure or bond the work of substituted CONTRACTORS or subcontractors utilized to complete the work, such excess shall be paid to the CONTRACTOR. If such costs exceed the unpaid balance, the CONTRACTOR shall pay the difference to CITY promptly upon demand. On failure of the CONTRACTOR to pay, the Surety shall pay on demand by CITY. Any portion of such difference not paid by the CONTRACTOR or Surety within thirty (30) days following the mailing of a demand for such costs shall earn interest at the maximum rate authorized by California law.

The CONTRACTOR and CITY agree that nothing in this section is intended to be or is a prevailing party clause as it pertains to attorney’s fees.

The foregoing provisions are in addition to and not in limitation of any other rights or remedies under law or in equity available to CITY.

422
SECTION 5 - AGREEMENT (Continued)
-51-

If it is later determined by CITY that the C ONTRACTOR had an excusable reason for not performing, such as a fire, flood, or other event which was not the fault of or was beyond the control of the CONTRACTOR, CITY, after setting up a new performance schedule, may allow the CONTRACTOR to continue work , or treat the termination as a termination for convenience, and the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of CITY.

B. Termination for Convenience.

CITY may terminate the CONTR ACTOR’s performance under the contract, either in whole or in part, at its own discretion or when conditions encountered during the work make it impossible or impracticable to proceed, or when CITY is prevented from proceeding with the contract by act of G od, by law, or by official action of a public authority, or upon a determination that such termination is in the best interest and convenience of CITY, or whenever CITY is prohibited from completing the work for any reason. CITY shall provide no less than ten (10) days written notice of its intent to terminate the Contract for convenience and shall provide the CONTRACTOR with consultation with CITY prior to termination.

1. Upon receipt of such written notice of termination, the CONTRACTOR shall:

a. Stop Work as specified in the written notice;

b. Terminate all orders and Subcontractors except as necessary to complete Work which is not terminated;

c. If directed in writing by CITY to do so, assign all right, title and interest in subcontracts and materia ls in progress, in which case CITY will have the right at its discretion to settle, or pay any or all claims arising out of the termination of such Subcontractors, but in no event shall recovery by any
CONTRACTOR include lost profits for uncompleted portio ns of Work;

d. Deliver or otherwise make available to CITY all data, Drawings, Specifications, reports, estimates, summaries and such other information and material as may have been accumulated by the CONTRACTOR in performing this Contract whether complet ed or in process;

e. Settle outstanding liabilities and claims with the approval of CITY;

f. Complete performance of such part of the work as has not been terminated; and

g. Take such other actions as may be necessary, or as may be directed by CITY for the protection and preservation of the Project and/or property related to the contract.

423
SECTION 5 - AGREEMENT (Continued)
-52-

2. Upon receipt of CITY’s written notice of termination for convenience, and within a period of 30 to 60 days, as determined by the Engineer at the time of terminatio n, the CONTRACTOR shall submit to the Engineer a Termination Proposal which shall include, but is not limited to, the CONTRACTOR’s estimated costs to be incurred by the CONTRACTOR as a result of the termination for convenience, and as allowed by the Contra ct Documents, including all documentation to support such costs; the status of the Work at time of termination; the status of termination of the CONTRACTOR’s subcontractor(s) and supplier(s) agreement(s) including the amount of each said agreement, amount paid under each agreement up to the date of termination, and the amount that currently remains due and owing under each agreement for work completed as of the date of termination, if any; a list, certified as to quantity and quality, of termination invento ry not previously disposed of, excluding items authorized for disposition by the Engineer; and any other information and/or documentation as required by the CITY.

Upon receipt of the CITY’s written notice of termination for convenience, the CONTRACTOR shal l submit to the Engineer a request for final payment, pursuant to the requirements set forth in the contract. Such request shall be submitted promptly, but no later than sixty (60) days from the effective date of termination.

3. The final payment to the CONTRACTOR after termination for convenience shall be limited to amounts due and owing under the contract at time of termination, including the following:

a. Any actual costs incurred by the CONTRACTOR for restocking charges;

b. The agreed upon price of protecting the work in any manner, if any, as directed by CITY;

c. The cost of settling and paying claims arising out of the termination of the work under subcontract agreements or orders with CITY’s approval, as specified above, exclusive of the of the a mounts paid or payable on account of goods delivered or work furnished by subcontractor prior to the effective date of the termination; and

d. The contract price allocable to the portion of the work properly performed or goods supplied by the CONTRACTOR a s of the date of termination, as determined in accordance with the Contract Documents, reduced by any sums previously paid to the CONTRACTOR.

4. CITY shall have the right to withhold any portion or the whole of the final payment under this provision in t he event there are any outstanding claims for compensation asserted by CITY against the CONTRACTOR, or by any third party against CITY which arises out of the CONTRACTOR’s work.
424
SECTION 5 - AGREEMENT (Continued)
-53-

5.19 Warranty. The CONTRACTOR agrees to perform all work under this Contract in accordance with the CITY’s designs, drawings and specifications.

The CONTRACTOR guarantees for a period of one (1) year from the date of the notice of completion of the work that the completed work is free from all defects due to faulty materials, equ ipment or workmanship and that he shall promptly make whatever adjustments or corrections which may be necessary to cure any defects, including repairs or any damage to other parts of the system resulting from such defects. The CITY shall promptly give no tice to the CONTRACTOR of observed defects. In the event that the CONTRACTOR fails to make adjustments, repairs, corrections or other work made necessary by such defects, the CITY may do so and charge the CONTRACTOR the cost incurred. The performance bond shall remain in full force and effect through the guarantee period.

The CONTRACTOR'S obligations under this clause are in addition to the CONTRACTOR'S other express or implied assurances of this Contract or state law and in no way diminish any other ri ghts that the CITY may have against the CONTRACTOR for faulty materials, equipment or work.

5.20 Attorneys' Fees. If any action at law or in equity is necessary to enforce or interpret the terms of this Contract, each shall bear its own attorneys' fees, c osts and necessary disbursements. Notwithstanding the foregoing, if any action is brought against the CONTRACTOR or any subcontractor to enforce a Stop Notice or Notice to Withhold, which named the CITY as a party to said action, the CITY shall be entitled to reasonable attorneys' fees, costs and necessary disbursements arising out of the defense of such action by the CITY. The CITY shall be entitled to deduct its costs for any Stop Notice filed, whether court action is involved or not.

5.21 Notices. Any notice required or permitted under this Contract may be given by ordinary mail at the address set forth below. Any party whose address changes shall notify the other party in writing.

TO CITY: TO CONTRACTOR:

City of Garden Grove
Public Works Department
Attention: Nick Hsieh
11222 Acacia Parkway
Garden Grove, CA 92842
(714) 741-5190
(714) 741-5578 Fax

[SIGNATURES ON NEXT PAGE]

425
SECTION 5 - AGREEMENT (Continued)
-54-

IN WITNESS THEREOF, these parties have executed this Construction Agreement on the day and year shown below.

Date: "CITY"

CITY OF GARDEN GROVE

By:

Lisa Kim
City Manager
ATTEST:

City Clerk

Date:
"CONTRACTOR"

CONTRACTOR'S State License No. 782908 Class A & C12
(Expiration Date: 08/31/2026

CONTRACTOR'S DIR No. 1000004235
Attached Copy of your DIR Certificate.

By: Jacob Breedlove

Title: Secretary

Date:

APPROVED AS TO FORM:

______________________________
Garden Grove City Attorney
If CONTRACTOR is a corporation, a Corporate
Resolution and/or Corporate Seal is required.

Date___________________________

426

-55-

FAITHFUL PERFORMANCE BOND
Bond No.

Premium

NOTICE: TO WHOM IT MAY CONCERN: those we, ,
,
as Principal, and
as Surety, are held and firmly bound unto the City of Garden Grove, (CITY) in the sum of

Lawful money of the United States, for the payment of which we bind heirs, o ur executors, administrators, successors, and ourselves jointly and severally.

That the Surety's office is located at ,
telephone no. ; the Surety is licensed to do business in the State of California; and the California Insurance Agent's License No., address, and telephone no. are as follows:

License No.:

Address:

Telephone No.:

That the following clause must be completed if, in fact, a non-resident agent for the Surety is a party to the transaction:

Name of non-resident agent:

Non-resident agent's office address:

Telephone No.:

THE CONDITION OF THIS OBLIGATION IS SUCH, that:

1. The Principal has agreed entered into a contract attached hereto, dated the day of , 20 , wi th the CITY OF GARDEN GROVE for the 2024 VARIOUS STREETS MICRO-SURFACING, PROJECT NO. CP – 1422000 and 5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE, PROJECT NO. CP – 1438000.

2. If the Principal shall well and truly perform, or cause to be performed, each an d all of the requirements and obligations of the contract to be performed by the Principal, as set forth in the contract, then this bond shall be null and void; otherwise, it shall remain in full force and effect.

In the event that suit is instituted to r ecover on this bond, the Surety will pay reasonable attorneys' fees.

3. Further, the Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, or modification of the contract documents or of work performed sha ll in any way affect its obligation on this bond, and it does hereby waive notice of any change, extension of time, alteration, or modification of the contract documents, or of work to be performed. 427

-56-

FAITHFUL PERFORMANCE BOND (Continues)

Executed this day of , 20___

Principal Principal

By:

Surety

By:

Attorney-in-Fact

California Resident Agent

By:

Non-resident Agent - Attorney-in-Fact

STATE OF CALIFORNIA )
)
COUNTY OF ) ss.

On this day of , 20 , before me, a Notary Public in and for said County, residing therein, duly commissioned and sworn, personally appeared known to me to be the Attorney-in-Fact of the , of (Corporation)
, and acknowledged that it executed the attached bond to the (State)
City of Garden Grove as such Attorney -in-Fact and as the free act a nd deed of the corporation, and that the bond was executed on behalf of the corporation by authority of its Board of Directors.

IN WITNESS WHEREOF, I have herewith set my hand and affixed my Official Seal, the day and year in this certificate first above written.

(Acknowledgment by Non -
resident Agent as Attorney -
in-Fact must be attached.)
Notary Public in and for said County and State
My Commission expires:
428

-57-

LABOR AND MATERIAL BOND
Bond No.

Premium
NOTICE: TO WHOM IT MAY CONCERN: those we,
,
as Principal, and , as Surety,
are held and firmly bound unto the City of Garden Grove, California ("CITY") in the sum of ____ Dollars ($ ), lawful money of the United States, for the payment of the sum, we bind heirs, our executors, administrators, successors, and ourselves jointly and severally.

That the Surety's office is located at ,
telephone no. ; the Surety is licensed to do business in the State of California; and the California Insurance Agent's License No., address, and telephone no. are as follows:

License No.:

Address:

Telephone No.:

That the following clause must be completed if, in fact, a non-resident agent for the Surety is a party to the transaction:

Name of non-resident agent:

Non-resident agent's office address:

Telephone No.:

THE CONDITION OF THIS OBLIGATION IS SUCH, that:

1. The Principal has entered into a contract attached hereto, dated day of ________________, 20 , with the CITY OF GARDEN GROVE for the 2024 VARIOUS STREETS MICRO-SURFACING, PROJECT NO. CP – 1422000 and 5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE, PROJECT NO. CP – 1438000.

2. If the Principal, its heirs, executors, administrators, successors, or assigns, or subcontractors, shall fail to pay for any materials, provisions, provender, or other supplies or teams, implements, or machinery used in, upon, for, or about, the performance of the improvement, or for any work or labor thereon of any kind, or for amounts due under the Unemployment Insurance Code with respect to work or labor, and provided that the claimant shall have complied with the provision of the code, the Surety or Sureties will pay for same in the amount not exceeding the sum specified in this bond; otherwise, the above obligation shall be void. In case suit is brought upon this bond, the Surety will pay reasonable attorneys' fees.

3. The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, or modification of the contract documents, or of work performed, shall in any way affect its obligation on this bond, and it d oes hereby waive notice of any change, extension of time, alteration, or modification of the contract documents, or of work to be performed. 429

-58-

LABOR AND MATERIAL BOND (Continues)

4. This bond shall inure to the benefit of any and all persons, companies, and corporations entitled to the claims under Civil Code 9554 et seq., so as to give a right of action to them or their assignees in any suit brought upon this bond.

Executed this day of , 20 .

Principal Principal

By:

Surety

By:

Attorney-in-Fact

California Resident Agent

By:

Non-resident Agent - Attorney-in-Fact

STATE OF CALIFORNIA )
)
COUNTY OF ) ss.

On this day of , 20 , before me, a Notary Public in and for said County and State, personally appeared
known to me to be the Attorney-in-Fact of
the , of (Corporation)
, and acknowledged that it executed the attached bond to the (State)
City of Garden Grove as such Attorney -in-Fact and as the free act and deed of the corporation, and that the bond was executed on behalf of the corporation by authority of its Board of Directors.

IN WITNESS WHEREOF, I have herewith set my hand and affixed my Official Seal, the day and year in this certificate first above written.

(Acknowledgment by Non -
resident Agent as Attorney -
in-Fact must be attached.)
Notary Public in and for said County and State
My Commission expires:
430

ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION This Escrow Agreement is made and entered into by and between whose address is ,
hereinafter called "owner", ,
whose address is ,
hereinafter called "contractor", ,
and , whose address
is ,
hereinafter called "escrow agent."
For the consideration hereinafter set forth, the owner, contractor, and escrow agent agree as follows:
(1) Pursuant to Section 22300 of the Public Contract Code of the State of California, the contractor has the option to deposit securities with the escrow agent as a substitute for retention earnings required to be withheld by the owner pursuant to the construction contract entered into between the owner and contractor for in the amount of _ dated (hereafter referred to as the "contract"). Alternatively, on written request of the contractor, the owner shall make payments of the retention earnings directly to the escrow agent. When the contractor deposits the securities as a substitute for the contract earnings, the escrow agent shall notify the owner within ten days of the deposit. The market value of the securities at the time of the substitution shall be at least equal to the cash amount then required to be withheld as retention under the terms of the contract between the owner and contractor.

Securities shall be held in the name of the, and shall designate the contractor as the beneficial owner.
(2) The owner shall make progress payments to the contractor for those funds which otherwise would be withheld from progress payments pursuant to the contract provision, pro vided that the escrow agent holds securities in the form and amount specified above. (3) When the owner makes payment of retentions earned directly to the escrow agent, the escrow agent shall hold them for the benefit of the contractor until such time as the e scrow created under this contract is terminated. The contractor may direct the investment of the payments into securities. All terms and conditions of this agreement and the rights and responsibilities of the parties shall be equally applicable and binding when the owner pays the escrow agent directly. (4) The contractor shall be responsible for paying all fees for the expenses incurred by the escrow agent in administering the escrow account. These expenses and payment terms shall be determined by the contractor and escrow agent.
(5) The interest earned on the securities or the money market accounts held in escrow and all interest on the interest shall be the sole account of contractor and shall be subject to withdrawal by contractor at any time and from time to time without notice to the owner. (6) The contractor shall have the right to withdraw all or any part of the principal in the escrow account only by written notice to the escrow agent accompanied by written authorization from the owner to the escrow agent that the owner consents to the withdrawal of the amount sought to be withdrawn by contractor.
(7) The owner shall have a right to draw upon the securities in the event of default by the contractor. Upon two days' written notice to the escrow agent from the owner of the default, the 431

-60-

escrow agent shall immediately convert the securities to cash and shall distribute the cash as instructed by the owner.
(8) Upon receipt of written notification from the owner certifying that the contract is final and complete, and that the contractor has complied with all requirements and procedures applicable to the contract, the escrow agent shall release to the contractor all securities and interest on deposit less escrow fees and charges of the escrow account. The escrow shall be close d immediately upon disbursement of all moneys and securities on deposit and payment of fees and charges. (9) The escrow agent shall rely on the written notifications from the owner and the contractor pursuant to Sections (1) to (8), inclusive, of this agreemen t and the owner and contractor shall hold the escrow agent harmless from the escrow agent's release, conversion, and disbursement of the securities and interest as set forth above. (10) The names of the persons who are authorized to give written notice or to re ceive written notice on behalf of the owner and on behalf of the contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:

On behalf of the owner: On behalf of the contractor:

On behalf of the owner: On behalf of the contractor:

Title Title

Name Name

Signature Signature

Address Address

432

-61-

On behalf of the escrow agent:

Title Title

Name Name

Signature Signature

Address Address

At the time the escrow account i s opened, the owner and contractor shall deliver to the escrow agent a fully executed counterpart of this Agreement.

IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers on the date first set forth above.

Owner/Contractor Dated:

Title/Title

Approved as to Form
City Attorney

433

ATTACHMENT 1

CITY OF GARDEN GROVE

PUBLIC WORKS DEPARTMENT

ENGINEERING DIVISION

BID SUMMARY SHEET

FOR

2024 VARIOUS STREETS MICRO-SURFACING PROJECT
CITY PROJECT NO. CP-1422000

AND

5-YEAR LANDSCAPE AND IRRIGATION MAINTENANCE
CITY PROJECT NO. CP-1438000

BID OPENING: DATE: SEPTEMBER 9, 2024 TIME: 11:00 A.M.

ENGINEER’S ESTIMATE: $ 3,225,700.00

Bidder’s Name Total Bid % Under/Over
Engrs. Est
RJ Noble Company, Orange $2,883,465.00 10.61% Under
Onyx Paving Company, Inc., Anaheim $3,833,000.00 18.83% Over