MISCELLANEOUS PROVISIONS:

1. Operators on hoists with three drums shall receive fifty cents (50¢) per hour additional pay to the regular rate of pay. The additional pay shall be added to the regular rate and become the base rate for the entire shift.

2. All heavy duty repairman and heavy duty combination shall receive one dollar ($1.00) per hour tool allowance in addition to their regular rate of pay and this shall become their base rate of pay.

3. Employees required to suit up and work in a hazardous material environment, shall receive Two Dollars ($2.00) per hour in addition to their regular rate of pay, and that rate shall become the basic hourly rate of pay.
# Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classifications within each group, see Page 3. b Rate applies to the first 4 overtime hours. All other daily overtime is paid at the Sunday rate. c Rate applies to the first 12 hours worked. All other time is paid at the Sunday rate. d Includes an amount for Annuity.
e Includes an amount withheld for supplemental dues.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: BUILDING/CONSTRUCTION INSPECTOR AND FIELD SOILS AND MATERIAL TESTER# Determination:

SC-23-63-2-2026-1D
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pensionb
Vacation
and
Holidayc
Training Other Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rated
(1½ x)
Saturday
Overtime
Hourly
Ratee
(1½ x)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 x)
Group 1 $64.18 $15.20 $15.65 $2.95 $1.10 $0.45 8 $99.53 $131.62 $131.62 $163.71 Group 2 $65.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $101.31 $134.29 $134.29 $167.27 Group 3 $67.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $103.31 $137.29 $137.29 $171.27 Determination: SC-23-63-2-2026-1D

Page 2 of 4 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: BUILDING/CONSTRUCTION INSPECTOR AND FIELD SOILS AND MATERIAL TESTER# (SPECIAL SHIFT)
Determination:

SC-23-63-2-2026-1D
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pensionb
Vacation
and
Holidayc
Training Other Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rated
(1½ x)
Saturday
Overtime
Hourly
Ratee
(1½ x)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 x)
Group 1 $65.18 $15.20 $15.65 $2.95 $1.10 $0.45 8 $100.53 $133.12 $133.12 $165.71 Group 2 $66.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $102.31 $135.79 $135.79 $169.27 Group 3 $68.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $104.31 $138.79 $138.79 $173.27 Determination: SC-23-63-2-2026-1D

Page 3 of 4 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: BUILDING/CONSTRUCTION INSPECTOR AND FIELD SOILS AND MATERIAL TESTER # (MULTI-SHIFT)
Determination:

SC-23-63-2-2026-1D
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classification a
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension b
Vacation
and
Holiday c
Training Other Hoursf
Total
Hourly
Rate
Daily
Overtime
Hourly
Rate d
(1½ x)
Saturday
Overtime
Hourly Rate e
(1½ x)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 x)
Group 1 $65.18 $15.20 $15.65 $2.95 $1.10 $0.45 8 $100.53 $133.12 $133.12 $165.71 Group 2 $66.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $102.31 $135.79 $135.79 $169.27 Group 3 $68.96 $15.20 $15.65 $2.95 $1.10 $0.45 8 $104.31 $138.79 $138.79 $173.27 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703- 4774.

Determination: SC-23-63-2-2026-1D

Page 4 of 4 ends

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Classifications:

Group 1
Field Soils and Materials Tester
Field Asphaltic Concrete (Soils and Materials Tester)
Field Earthwork (Grading Excavation and Filling)
Roof Inspector
Load Testing Inspector
Water Proofer/Methane
Group 2
AWS-CWI Welding Inspector
Building/Construction Inspector
Reinforcing Steel
Reinforced Concrete
Pre-Tension Concrete
Post-Tension Concrete
Structural Steel and Welding Inspector
Glue-Lam and truss Joints
Truss-Type Joint Construction
Shear Wall and Floor System used as diaphragms
Concrete batch Plant
Spray-Applied Fireproofing
Structural masonry
Group 3
Licensed Grading Inspector
Nondestructive Testing (NDT)
Unmanned Aircraft Systems (UAS Drones) Operator (when
used in conjunction with field soils and material testing – building/construction inspection
# Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classifications within each group, see Page 4. b Includes an amount for Annuity.
c Includes an amount withheld for supplemental dues.
d Rate applies to the first 4 overtime hours. All other daily overtime is paid at the Sunday rate. e Rate applies to the first 12 hours worked. All other time is paid at the Sunday rate. f The Third Shift shall work 6.5 hours, exclusive of meal period, for which 8 hours straight-time shall be paid at the non-shift rate, Monday through Friday.

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: OPERATING ENGINEER#
Determination:

SC-23-63-2-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly Rateb
(1½ x)
Saturday
Overtime
Hourly Ratec
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group 1 $63.40 8 $98.75 $130.450 $130.450 $162.15
Group 2 $64.18 8 $99.53 $131.620 $131.620 $163.71
Group 3 $64.47 8 $99.82 $132.055 $132.055 $164.29
Group 4 $65.96 8 $101.31 $134.290 $134.290 $167.27
Group 6 $66.18 8 $101.53 $134.620 $134.620 $167.71
Group 8 $66.29 8 $101.64 $134.785 $134.785 $167.93
Group 10 $66.41 8 $101.76 $134.965 $134.965 $168.17
Group 12 $66.58 8 $101.93 $135.220 $135.220 $168.51
Group 13 $66.68 8 $102.03 $135.370 $135.370 $168.71
Group 14 $66.71 8 $102.06 $135.415 $135.415 $168.77
Group 15 $66.79 8 $102.14 $135.535 $135.535 $168.93
Group 16 $66.91 8 $102.26 $135.715 $135.715 $169.17
Group 17 $67.08 8 $102.43 $135.970 $135.970 $169.51
Group 18 $67.18 8 $102.53 $136.120 $136.120 $169.71
Group 19 $67.29 8 $102.64 $136.285 $136.285 $169.93
Group 20 $67.41 8 $102.76 $136.465 $136.465 $170.17
Group 21 $67.58 8 $102.93 $136.720 $136.720 $170.51
Group 22 $67.68 8 $103.03 $136.870 $136.870 $170.71
Group 23 $67.79 8 $103.14 $137.035 $137.035 $170.93
Group 24 $67.91 8 $103.26 $137.215 $137.215 $171.17
Group 25 $68.08 8 $103.43 $137.470 $137.470 $171.51
Determination: SC-23-63-2-2026-1

Page 2 of 12 ends

Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $15.20
Pensiond $15.65
Vacation and Holidaye $2.95
Training $1.10
Other $0.45
Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-63-2-2026-1

Page 3 of 12 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: OPERATING ENGINEER (SPECIAL SHIFT) #
Determination:

SC-23-63-2-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly Rateb
(1½ x)
Saturday
Overtime
Hourly Ratec
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group 1 $64.40 8 $99.75 $131.950 $131.950 $164.15
Group 2 $65.18 8 $100.53 $133.120 $133.120 $165.71
Group 3 $65.47 8 $100.82 $133.555 $133.555 $166.29
Group 4 $66.96 8 $102.31 $135.790 $135.790 $169.27
Group 6 $67.18 8 $102.53 $136.120 $136.120 $169.71
Group 8 $67.29 8 $102.64 $136.285 $136.285 $169.93
Group 10 $67.41 8 $102.76 $136.465 $136.465 $170.17
Group 12 $67.58 8 $102.93 $136.720 $136.720 $170.51
Group 13 $67.68 8 $103.03 $136.870 $136.870 $170.71
Group 14 $67.71 8 $103.06 $136.915 $136.915 $170.77
Group 15 $67.79 8 $103.14 $137.035 $137.035 $170.93
Group 16 $67.91 8 $103.26 $137.215 $137.215 $171.17
Group 17 $68.08 8 $103.43 $137.470 $137.470 $171.51
Group 18 $68.18 8 $103.53 $137.620 $137.620 $171.71
Group 19 $68.29 8 $103.64 $137.785 $137.785 $171.93
Group 20 $68.41 8 $103.76 $137.965 $137.965 $172.17
Group 21 $68.58 8 $103.93 $138.220 $138.220 $172.51
Group 22 $68.68 8 $104.03 $138.370 $138.370 $172.71
Group 23 $68.79 8 $104.14 $138.535 $138.535 $172.93
Group 24 $68.91 8 $104.26 $138.715 $138.715 $173.17
Group 25 $69.08 8 $104.43 $138.970 $138.970 $173.51
Determination: SC-23-63-2-2026-1

Page 4 of 12 ends

Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $15.20
Pensiond $15.65
Vacation and Holidaye $2.95
Training $1.10
Other $0.45
Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-63-2-2026-1

Page 5 of 12 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: OPERATING ENGINEER (MULTI-SHIFT)#
Determination:

SC-23-63-2-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hoursf
Total
Hourly
Rate
Daily
Overtime
Hourly Rateb
(1½ x)
Saturday
Overtime
Hourly Ratec
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group 1 $64.40 8 $99.75 $131.950 $131.950 $164.15
Group 2 $65.18 8 $100.53 $133.120 $133.120 $165.71
Group 3 $65.47 8 $100.82 $133.555 $133.555 $166.29
Group 4 $66.96 8 $102.31 $135.790 $135.790 $169.27
Group 5 $67.06 8 $102.41 $135.940 $135.940 $169.47
Group 6 $67.18 8 $102.53 $136.120 $136.120 $169.71
Group 7 $67.28 8 $102.63 $136.270 $136.270 $169.91
Group 8 $67.29 8 $102.64 $136.285 $136.285 $169.93
Group 9 $67.39 8 $102.74 $136.435 $136.435 $170.13
Group 10 $67.41 8 $102.76 $136.465 $136.465 $170.17
Group 11 $67.51 8 $102.86 $136.615 $136.615 $170.37
Group 12 $67.58 8 $102.93 $136.720 $136.720 $170.51
Group 13 $67.68 8 $103.03 $136.870 $136.870 $170.71
Group 14 $67.71 8 $103.06 $136.915 $136.915 $170.77
Group 15 $67.79 8 $103.14 $137.035 $137.035 $170.93
Group 16 $67.91 8 $103.26 $137.215 $137.215 $171.17
Group 17 $68.08 8 $103.43 $137.470 $137.470 $171.51
Group 18 $68.18 8 $103.53 $137.620 $137.620 $171.71
Group 19 $68.29 8 $103.64 $137.785 $137.785 $171.93
Group 20 $68.41 8 $103.76 $137.965 $137.965 $172.17
Group 21 $68.58 8 $103.93 $138.220 $138.220 $172.51
Group 22 $68.68 8 $104.03 $138.370 $138.370 $172.71
Group 23 $68.79 8 $104.14 $138.535 $138.535 $172.93
Group 24 $68.91 8 $104.26 $138.715 $138.715 $173.17
Determination: SC-23-63-2-2026-1

Page 6 of 12 ends

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hoursf
Total
Hourly
Rate
Daily
Overtime
Hourly Rateb
(1½ x)
Saturday
Overtime
Hourly Ratec
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group 25 $69.08 8 $104.43 $138.970 $138.970 $173.51
Employer Payments:

Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Type of Fund Amount per Hour
Health and Welfare $15.20
Pensiond $15.65
Vacation and Holidaye $2.95
Training $1.10
Other $0.45
Determination: SC-23-63-2-2026-1

Page 7 of 12 ends

Classifications:

Group 1
Bargeman
Brakeman
Compressor Operator
Ditchwitch, with seat or similar type equipment
Elevator Operator - Inside
Engineer Oiler
Forklift Operator (includes loed, lull or similar types – under 5 tons)
Generator Operator
Generator, Pump or Compressor Plant Operator
Heavy Duty Repairman Helper
Inertial Profiler Operator
Pump Operator
Signalman
Switchman
Group 2
Asphalt-Rubber Plant Operator (Nurse Tank
Operator)
Coil Tubing Rig Operator
Concrete Mixer Operator – Skip Type
Conveyor Operator
Fireman
Forklift Operator (includes loed, lull or similar types – over 5 tons)
Hydrostatic Pump Operator
Oiler Crusher (Asphalt or Concrete Plant)
Petromat Laydown Machine
PJU Side Dump Jack
Rotary Drill Helper (Oilfield)
Screening and Conveyor Machine Operator (or
similar types)
Skiploader (Wheel type up to ¾ yd. without
attachment)
Tar Pot Fireman
Temporary Heating Plant Operator
Trenching Machine Oiler
Group 3
Asphalt Rubber Blend Operator
Bobcat or similar type (Skid Steer, with all
attachments)
Equipment Greaser (rack)
Ford Ferguson (with dragtype attachments)
Helicopter Radioman (ground)
Stationary Pipe Wrapping and Cleaning Machine
Operator
Group 4
Asphalt Plant Fireman
Backhoe Operator (mini-max or similar type)
Boring Machine Operator
Boring System Electronic Tracking Locator
Boxman or Mixerman (asphalt or concrete)
Chip Spreading Machine Operator
Concrete Cleaning Decontamination Machine
Operator
Concrete Pump Operator (small portable)
Drilling Machine Operator, Small Auger types
(Texoma Super Economatic, or similar types –
Hughes 100 or 200, or similar types – drilling
depth of 30 maximum)
Equipment Greaser (grease truck)
Excavator Track/Rubber-Tired-with all attachments
(Operating weight under 21,000 lbs)
Guard Rail Post Driver Operator
Highline Cableway Signalman
Hydra-Hammer-Aero Stomper
Hydraulic Casing Oscillator Operator – drilling depth
of 30’ maximum
Micro Tunneling Operator (above ground tunnel)
Power Concrete Curing Machine Operator
Power Concrete Saw Operator
Power – Driver Jumbo Form Setter Operator
Power Sweeper Operator
Rock Wheel Saw/Trencher
Roller Operator (compacting)
Screed Operator (asphalt or concrete)
Trenching Machine Operator (up to 6 ft.)
Vacuum or Muck Truck
Group 5 (for multi-shift rate, see Pages 5 and 6)
Equipment Greaser (Grease Truck/Multi-Shift)
Group 6
Articulating Material Hauler
Asphalt Plant Engineer
Batch Plant Operator
Bit Sharpener
Concrete Joint Machine Operator (canal and similar
type)
Concrete Placer Operator
Concrete Planer Operator
Determination: SC-23-63-2-2026-1

Page 8 of 12 ends

Dandy Digger
Deck Engine Operator
Deck Engineer
Derrickman (oilfield type)
Drilling Machine Operator, Bucket or Auger types
(Calweld 100 bucker or similar types – Watson
1000 auger or similar types – Texoma 330, 500 or
600 auger or similar types – drilling depth of 45’
maximum)
Drilling Machine Operator (including water wells)
Forced Feed Loader
Hydraulic Casing Oscillator Operator – drilling depth
of 45’ maximum
Hydro Seeder Machine Operator (straw, pulp or seed)
Jackson Track Maintainer, or similar type
Machine Tool Operator
Maginnis Internal Full Slab Vibrator
Mechanical Berm, Curb or Gutter (concrete or
asphalt)
Mechanical Finisher Operator (concrete, ClaryJohnson-Bidwell or similar types) Micro Tunnel System Operator (below ground)
Pavement Breaker Operator
Railcar Mover
Road Oil Mixing Machine Operator
Roller Operator (asphalt or finish)
Rubber-Tired Earthmoving Equipment (single
engine, up to and including 25 yds. struck)
Self-Propelled Tar Pipelining Machine Operator
Skiploader Operator (crawler and wheel type, over
¾ yds. and up to and including 1½ yds.)
Slip Form Pump Operator (power driven hydraulic
lifting device for concrete forms)
Tractor Operator – Bulldozer, Tamper-Scraper
(single engine, up to 100 H.P. flyweel and similar
types, up to and including D-5 and similar types)
Tugger Hoist Operator (1 drum)
Ultra High Pressure Waterjet Cutting Tool System
Operator
Vacuum Blasting Machine Operator
Volumetric Mixer Operator
Welder - General
Group 7 (for multi-shift rate, see Pages 5 and 6)
Welder - General (Multi-Shift)
Group 8
Allroad Mobile Timber Harvester (Albach or similar
types)
Asphalt or Concrete Spreading Operator (tamping or
finishing)
Asphalt Paving Machine Operator (barber greene or
similar type, one (1) Screedman)
Asphalt-Rubber Distributor Operator
Backhoe Operator (up to and including ¾ yds.)
small ford, case or similar types
Backhoe Operator (over ¾ yd. and up to 5 cu. yds.

M.R.C.)
Barrier Rail Mover (BTM Series 200 or similar types)
Cast in Place Pipe Laying Machine Operator
Cold Foamed Asphalt Recycler
Combination Mixer and Compressor Operator
(gunite work)
Compactor Operator – Self Propelled
Concrete Mixer Operator – Paving
Crushing Plant Operator
Drill Doctor
Drilling Machine Operator, Bucket or Auger types
(Calweld 150 bucker or similar types – Watson
1500, 2000, 2500 auger or similar types –
Texoma 700, 800 auger or similar types – drilling
depth of 60’ maximum)
Elevating Grader Operator
Excavator Track/Rubber-Tired with all attachments
(Operating Weight 21,000 lbs – 100,000 lbs)
Global Positioning System/GPS (or Technician)
Grade Checker
Gradall Operator
Grouting Machine Operator
Heavy Duty Repairman/Pump Installer
Heavy Equipment Robotics Operator
Hydraulic Casing Oscillator Operator – drilling depth
of 60’ maximum
Hydraulic Operated Grout Plant (excludes hand
loading)
Kalamazoo Ballast Regulator or similar type
Kalamazoo Switch Tamper, or similar type
Klemm Drill Operator or similar types
Kolman Belt Loader and similar type
Le Tourneau Blob Compactor or similar type
Lo Drill
Loader Operator (Athey, Euclid, Sierra and similar
types)
Determination: SC-23-63-2-2026-1

Page 9 of 12 ends

Master Environmental Maintenance Mechanic
Mobark Chipper or similar types
Ozzie Padder or similar types
P.C. 490 Slot Saw
Pneumatic Concrete Placing Machine Operator
(Hackley-Presswell or similar type)
Prentice 721E Hydro-Ax
Pumpcrete Gun Operator
Rail Tie Crane (Kershaw or similar types)
Rock Drill or Similar Types (see Miscellaneous
Provision #4 for additional information regarding
this classification)
Rotary Drill Operator (excluding caison type)
Rubber-Tired Earth Moving Equipment Operator
(single engine, caterpillar, euclid, athey wagon,
and similar types with any and all attachments
over 25 yds. and up to and including 50 cu yds.
struck)
Rubber-Tired Earth Moving Equipment Operator
(multiple engine – up to and including 25 yds.
struck)
Rubber-Tired Scraper Operator (self-loading paddle
wheel type – John Deere, 1040 and similar single
unit)
Self-Propelled Curb and Gutter Machine Operator
Shuttle Buggy
Skiploader Operator (crawler and wheel type over 1
½ yds. up to and including 6 ½ yds.)
Soil Remediation Plant Operator (CMI, Envirotech or
Similar types)
Soil Stabilizer and Reclaimer (WR-2400)
Somero SXP Laser Screed
Speed Swing Operator
Surface Heaters and Planer Operator
Tractor Compressor Drill Combination Operator
Tractor Operator (any type larger than D-5 – 100
flyweel H.P. and over, or similar types –
bulldozer, tamper, scraper and push tractor,
single engine)
Tractor Operator (boom attachments)
Traveling Pipe Wrapping, Cleaning and Bending
Machine Operator)
Trenching Machine Operator (over 6 ft. depth
capacity, manufacturer’s rating)
Trenching Machine with Road Miner Attachment
(over 6ft. depth capacity, manufacturer’s rating –
Oiler or Journeyman Trainee required)
Ultra High Pressure Waterjet Cutting Tool System
Mechanic
Water Pull (compaction)
Group 9 (for multi-shift rate, see Pages 5 and 6)
Heavy Duty Repairman (Multi-Shift)
Group 10
Backhoe Operator (over 5 cu. yds. M.R.C.)
Drilling Machine Operator, Bucket or Auger types
(Calweld 200 B bucket or similar types – Watson
3000 or 5000 auger or similar types – Texoma
900 auger or similar types – drilling depth of 105’
maximum)
Dual Drum Mixer
Dynamic Compactor LDC350 or similar types
Heavy Duty Repairman-Welder combination
Hydraulic Casing Oscillator Operator – drilling depth
of 105’ maximum
Monorail Locomotive Operator (diesel, gas or
electric)
Motor Patrol – Blade Operator (single engine)
Multiple Engine Tractor Operator (euclid and similar
type – except quad 9 cat.)
Pneumatic Pipe Ramming Tool and similar types
Pre-stressed Wrapping Machine Operator (2
Operators required)
Production Tamper - Harsco or similar types
Rail Dynamic Stabilizer
Rubber – Tired Earth Moving Equipment Operator
(single engine, over 50 yds. struck)
Rubber – Tired Earth Moving Equipment Operator
(multiple engine, euclid caterpillar and similar
types – over 25 yds. and up to 50 yds. struck)
Tower Crane Repairman
Tractor Loader Operator (crawler and wheel-type
over 6 ½ yds.)
Unmanned Aircraft Systems (UAS Drones) Operator
(when used in conjunction with hoisting and
placing materials)
Welder – Certified
Woods Mixer Operator (and similar pugmill
equipment)
Group 11 (for multi-shift rate, see Pages 5 and 6)
Heavy Duty Repairman – Welder Combination
(Multi-Shift)
Welder – Certified (Multi-Shift)
Determination: SC-23-63-2-2026-1

Page 10 of 12 ends

Group 12
Auto Grader Operator
Automatic Slip Form Operator
Backhoe Operator (over 7 cu. yds. M.R.C.)
Drilling Machine Operator, Bucket or Auger types
(Calweld, auger 200 CA or similar types –
Watson, auger 6000 or similar types – hughes
super duty, auger 200 or similar types – drilling
depth of 175’ maximum)
Excavator Track/Rubber Tired- with all attachments
(Operating Weight 100,000 lbs. – 200,000 lbs.)
Hoe Ram or similar types with compressor
Hydraulic Casing Oscillator Operator – drilling depth
of 175’ maximum
Mass Excavator Operator – less than 750 cu. yds.

Mechanical Finishing Machine Operator
Mobile Form Traveler Operator
Motor Patrol Operator (multi-engine)
Pipe Mobile Machine Operator
Rubber-Tired Earth Moving Equipment Operator
(multiple engine, euclid, caterpillar and similar
type, over 50 cu. yds. struck)
Rubber-Tired Self-Loading Scraper Operator
(paddle-wheel-auger type self-loading – (two (2)
or more units)
Group 13
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(single engine, up to and including 25 yds. struck)
Group 14
Canal Liner Operator
Canal Trimmer Operator
Drilling Machine Operator, Bucket or Auger types
(Calweld, auger 200 CA or similar types –
watson, auger 6000 or similar types – hughes
super duty, auger 200 or similar types – drilling
depth of 300’ maximum)
Remote Controlled Earth Moving Operator ($1.00
per hour additional to base rate)
Wheel Excavator Operator (over 750 cu. yds. per
hour)
Group 15
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(single engine, caterpillar, euclid, athey wagon,
and similar types with any and all attachments
over 25 and up to and including 50 cu. yds.
struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(multiple engine - up to and including 25 yds.
struck)
Group 16
Excavator Track/Rubber Tired – with all attachments
(Operating Weight exceeding 200,000 lbs.)
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(single engine, over 50 yds. struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(multiple engine, euclid, caterpillar, and similar,
over 25 yds. and up to 50 yds. struck)
Group 17
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Push-Pull System
(multiple engine, euclid, caterpillar, and similar
type, over 50 cu. yds. struck)
Tandem Tractor Operator (operating crawler type
tractors in tandem – Quad 9 and similar type)
Group 18
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - single engine, up to and
including 25 yds. struck)
Group 19
Rotex Concrete Belt Operator
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - single engine, caterpillar,
euclid, athey wagon, and similar types with any
and all attachments over 25 yds. and up to and
including 50 cu. yds. struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - multiple engines, up to and
including 25 yds. struck)
Determination: SC-23-63-2-2026-1

Page 11 of 12 ends

Group 20
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - single engine, over 50 yds.
struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - multiple engine, euclid,
caterpillar and similar, over 25 yds. and up to 50
yds. struck)
Group 21
Rubber-Tired Earth Moving Equipment Operator,
Operating in Tandem (scrapers, belly dumps, and
similar types in any combination, excluding
compaction units - multiple engine, euclid,
caterpillar and similar type, over 50 cu. yds.
struck)
Group 22
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (single engine, up to and including 25
yds. struck)
Group 23
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (single engine, caterpillar, euclid, athey
wagon, and similar types with any and all
attachments over 25 yds. and up to and including
50 cu. yds. struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (multiple engine, up to and including 25
yds. struck)
Group 24
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (single engine, over 50 yds. Struck)
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (multiple engine, euclid, caterpillar and
similar, over 25 yds. and up to 50 yds. struck)
Group 25
Concrete Pump Operator-Truck Mounted
Pedestal Concrete Pump Operator
Rubber-Tired Earth Moving Equipment Operator,
Operating Equipment with the Tandem Push-Pull
System (multiple engine, euclid, caterpillar and
similar over 50 cu. yds struck
MISCELLANEOUS PROVISIONS:

1. Operators on hoists with three drums shall receive fifty cents (50¢) per hour additional pay to the regular rate of pay. The additional pay shall be added to the regular rate and become the base rate for the entire shift.

2. All heavy duty repairman and heavy duty combination shall receive one dollar ($1.00) per hour tool allowance in addition to their regular rate of pay and this shall become their base rate of pay.

3. Employees required to suit up and work in a hazardous material environment, shall receive Two Dollars ($2.00) per hour in addition to their regular rate of pay, and that rate shall become the basic hourly rate of pay.

4. A review of rock drilling is currently pending. The minimum acceptable rate of pay for this classification or type of work on public works projects is Laborer and Related Classifications/Group 5 (Driller) as published in the Director’s General Prevailing Wage Determinations. However, the published rate for the craft/classification of Operating Engineer/Group 8 (Rock Drill or Similar Types) may be used by contractors to perform rock drilling on public works projects. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classifications within each group, see Pages 7 through 11. b Rate applies to the first 4 overtime hours. All other daily overtime is paid at the Sunday rate.

Determination: SC-23-63-2-2026-1

Page 12 of 12 ends

c Rate applies to the first 12 hours worked. All other time is paid at the Sunday rate. d Includes an amount for Annuity.
e Includes an amount withheld for supplemental dues.
f The Third Shift shall work 6.5 hours, exclusive of meal period, for which 8 hours straight-time shall be paid at the non-shift rate, Monday through Friday.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Laborer and Related Classifications #
Determination:

SC-23-102-2-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday
b
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X)
cd
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Group 1 $46.48 $9.55 $12.57 $5.02 $0.80 $0.67 8.0 $75.09 $98.330 $98.330 $121.570 Group 2 $47.03 $9.55 $12.57 $5.02 $0.80 $0.67 8.0 $75.64 $99.155 $99.155 $122.670 Group 3 $47.58 $9.55 $12.57 $5.02 $0.80 $0.67 8.0 $76.19 $99.980 $99.980 $123.770 Group 4 $49.13 $9.55 $12.57 $5.02 $0.80 $0.67 8.0 $77.74 $102.305 $102.305 $126.870 Group 5 $49.48 $9.55 $12.57 $5.02 $0.80 $0.67 8.0 $78.09 $102.830 $102.830 $127.570 Determination: SC-23-102-2-2025-1

Page 2 of 3 ends

Group 1
Boring Machine Helper (Outside)
Certified Confined Space Laborer
Cleaning and Handling of Panel Forms
Concrete Screeding for Rough Strike-Off
Concrete, Water Curing
Demolition Laborer, the cleaning of brick if performed by an employee performing any other phase of demolition
work, and the cleaning of lumber
Fiberoptic Installation, Blowing, Splicing, and Testing Technician on public right-of-way only
Fire Watcher, Limbers, Brush Loaders, Pilers and
Debris Handlers
Flagman
Gas, Oil and/or Water Pipeline Laborer
Laborer, Asphalt-Rubber Material Loader
Laborer, General or Construction
Laborer, General Cleanup
Laborer, Jetting
Laborer, Temporary Water and Air Lines
Plugging, Filling of Shee-Bolt Holes; Dry Packing of
Concrete and Patching
Post Hole Digger (Manual)
Railroad Maintenance, Repair Trackman and Road
Beds; Streetcar and Railroad Construction Track
Laborers
Rigging and Signaling
Scaler
Slip Form Raisers
Tarman and Mortar Man
Tool Crib or Tool House Laborer
Traffic Control by any method
Water Well Driller Helper
Window Cleaner
Wire Mesh Pulling - All Concrete Pouring Operations
Group 2
Asphalt Shoveler
Cement Dumper (on 1 yard or larger mixer and handling
bulk cement)
Cesspool Digger and Installer
Chucktender
Chute Man, pouring concrete, the handling of the chute
from readymix trucks, such as walls, slabs, decks,
floors, foundations, footings, curbs, gutters and
sidewalks
Concrete Curer-Impervious Membrane and Form Oiler
Cutting Torch Operator (Demolition)
Fine Grader, Highways and Street Paving, Airport,
Runways, and similar type heavy construction
Gas, Oil and/or Water Pipeline Wrapper-Pot Tender and
Form Man
Guinea Chaser
Headerboard Man-Asphalt
Installation of all Asphalt Overlay Fabric and Materials used for Reinforcing Asphalt
Laborer, Packing Rod Steel and Pans
Membrane Vapor Barrier Installer
Power Broom Sweepers (small)
Riprap, Stonepaver, placing stone or wet sacked
concrete
Roto Scraper and Tiller
Sandblaster (Pot Tender)
Septic Tank Digger and Installer (leadman)
Tank Scaler and Cleaner
Tree Climber, Faller, Chain Saw Operator, Pittsburgh
Chipper and similar type Brush Shredders
Underground Laborer, including Caisson Bellower
Group 3
Asphalt Installation of all fabrics
Buggymobile Man
Compactor (all types including Tampers, Barko,
Wacker)
Concrete Cutting Torch
Concrete Pile Cutter
Driller, Jackhammer, 2 1/2 ft. drill steel or longer
Dri Pak-it Machine
Gas, Oil and/or Water Pipeline Wrapper - 6-inch pipe
and over by any method, inside and out
Impact Wrench, Multi-Plate
Kettlemen, Potmen and Men applying asphalt, lay-kold,
creosote, lime caustic and similar type materials
Laborer, Fence Erector
Material Hoseman (Walls, Slabs, Floors and Decks)
Operators of Pneumatic, Gas, Electric Tools, Vibrating
Machines, Pavement Breakers, Air Blasting, ComeAlongs, and similar mechanical tools not separately classified herein; operation of remote controlled
robotic tools in connection with Laborers work
Pipelayer's backup man, coating, grouting, making of
joints, sealing, caulking, diapering and including
rubber gasket joints, pointing and any and all other
services
Power Post Hole Digger
Rock Slinger
Rotary Scarifier or Multiple Head Concrete Chipping
Scarifier
Steel Headerboard Man and Guideline Setter
Trenching Machine, Hand Propelled
Group 4
Any Worker Exposed to Raw Sewage
Asphalt Raker, Luteman, Ironer, Asphalt Dumpman, and
Asphalt Spreader Boxes (all types)
Concrete Core Cutter (walls, floors or ceilings), Grinder or Sander
Concrete Saw Man, Cutting Walls or Flat Work, Scoring
old or new concrete
Cribber, Shorer, Lagging, Sheeting and Trench Bracing,
Hand-Guided Lagging Hammer
Head Rock Slinger
High Scaler (including drilling of same)
Laborer, Asphalt-Rubber Distributor Bootman
Laser Beam in connection with Laborer's work
Oversize Concrete Vibrator Operator, 70 pounds and
over
Pipelayer
Prefabricated Manhole Installer
Sandblaster (Nozzleman), Water Blasting, Porta ShotBlast Subsurface Imaging Laborer
Traffic Lane Closure, certified
Group 5
Blasters Powderman
Driller
Toxic Waste Removal
Welding, certified or otherwise in connection with
Laborers’ work
Determination: SC-23-102-2-2025-1

Page 3 of 3 ends

Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. #
Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classification within each group, see page 2.
b
Includes an amount per hour worked for supplemental dues. c Any hours worked over 12 hours in a single workday are double (2) time. d Saturdays in the same work week may be worked at straight-time if job is shut down during work week due to inclement weather or similar Act of God, or a situation beyond the employer’s control.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Parking and Highway Improvement (Striping, Slurry and Seal Coat Operations-Laborer)# Determination:

SC-23-102-6-2025-2
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation/
Holidayb Training Other Hoursc
Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X)
6th & 7th Day
Overtime
Hourly
Rated
(1½ x)
Holiday
Overtime
Hourly
Rate
(2 X)
Group 1 $49.30 9.55 9.52 5.26 $1.47 $0.56 8.0 $75.66 $100.310 $100.310 $124.96 Group 2 $50.60 9.55 9.52 5.26 $1.47 $0.56 8.0 $76.96 $102.260 $102.260 $127.56 Group 3 $52.61 9.55 9.52 5.26 $1.47 $0.56 8.0 $78.97 $105.275 $105.275 $131.58 Group 4 $54.35 9.55 9.52 5.26 $1.47 $0.56 8.0 $80.71 $107.885 $107.885 $135.06 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Determination: SC-23-102-6-2025-2

Page 2 of 2 ends

Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

CLASSIFICATION GROUPS:

Group 1
Protective coating, Pavement sealing (repairs
and filling of cracks by any method to
parking lots, game courts and playgrounds,
and tracks, whether indoor or outdoor)
Truck Mounted Attenuator
Automatous Truck Mounted Attenuator
Installation of carstops
Traffic Control Person & Serviceman;
including work of installing and protecting
utility covers, traffic delineating devices,
posting of no parking and notifications for
public convenience
Asphalt Repair
Equipment Repair Technician
Truncated Dome Assitant
Decorative Asphalt Surfacing Applicator
Assistant
Group 2
Traffic Surface Abrasive Blaster
Pot Tender
Traffic Control Person/Certified Traffic Control
Person
Repairing and filling of cracks and surface
cleaning on streets, highways, and airports
by any means, and other work not directly
connected with the application of slurry seal
Slurry Seal Squeegeeman (finisher)
Bob Cat/Skid Steer
Seal Roller
Forklift
Group 3
Traffic Delineating Device Applicator
Traffic Protective System Installer
Pavement Marking Applicator
Slurry Seal Applicator Operator (Line Driverincluding self-contained distribution units, aggregate spreader truck)
Shuttleman (loader/slurry machine
operations) operation of all related
machinery and equipment; handling of
related materials
Truncated Dome Technician
Decorative Asphalt Surfacing Applicator
Group 4
Traffic Striping Applicator
Slurry Seal Mixer Operator
Power Broom Sweeper (operation of all
related trucks, machinery and
equipment; Handling of related
materials)
# Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classifications within each group, see Page 2. b Includes an amount per hour worked for Supplemental Dues. c Straight-time hours: 8 consecutive hours per day. 40 hours over 5 consecutive days, Monday through Sunday shall constitute a week’s work at straight time.
d The sixth consecutive day in the same work week may be worked at straight-time if job is shut down during work week due to inclement weather.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: TUNNEL WORKER (LABORER)
Determination:

SC-23-102-12-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation/
Holidayb Training Other Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Ratec
(1½ X)
Saturday
Overtime
Hourly
Ratec
(1½ X)
Sunday/
Holiday
Overtime
Hourly Rate
(2 X)
Group I $53.53 $9.55 $12.57 $5.02 $0.80 $0.67 8 $82.140 $108.905 $108.905 $135.670 Group II $53.85 $9.55 $12.57 $5.02 $0.80 $0.67 8 $82.460 $109.385 $109.385 $136.310 Group III $54.31 $9.55 $12.57 $5.02 $0.80 $0.67 8 $82.920 $110.075 $110.075 $137.230 Group IV $55.00 $9.55 $12.57 $5.02 $0.80 $0.67 8 $83.610 $111.110 $111.110 $138.610 Group V $55.85 $9.55 $12.57 $5.02 $0.80 $0.67 8 $84.460 $112.385 $112.385 $140.310 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-102-12-2025-1

Page 2 of 2 ends

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Classifications:

Group I
Batch Plant Laborer
Bottom Lander
Changehouseman
Dumpman
Outside Dumpman
Loading and Unloading Agitator Cars
Nipper
Pot Tender using mastic or other materials
Rollover Dumpman
Shotcrete Man (helper)
Subsurface Laborer (non-miner)
Swamper/Brakemen (Brakeman and
Switchman on tunnel work)
Tool Man
Top Lander
Tunnel Materials Handling Man
Group II
Chemical Grout Jetman
Chucktender, Cabletender
Concrete crew-include Rodders and
Spreaders
Grout Mixerman
Grout Pumpman
Operating of Troweling and/or Grouting
Machines
Vibratorman, Jack Hammer Pneumatic Tools
(except driller)
Group III
Blaster, Driller, Powderman
Bull Gang Mucker, Trackman
Cherry Pickerman
Grout Gunman
Jackleg Miner
Jumbo Man
Kemper and other Pneumatic Concrete
Placer Operator
Micro-Tunneling, Micro-Tunneling Systems
Nozzleman
Powderman-Primer House
Primer Man
Sandblaster
Segment Erector
Steel Form Raiser and Setter
Timberman, Retimberman, wood or steel
Tunnel Concrete Finisher
Group IV
Shaft and Raise Workd
Diamond Driller
HDPE Membrane Vapor Barrier Welder
Miner - Tunnel (hand or machine)
Group V
Welder, certified as required
a For classifications within each group, see Page 2.
b Includes an amount per hour worked for supplemental dues. c All work performed over 12 hours in a single work day shall be paid for at double time (2x). d The classification “Shaft and Raise Work” shall be applicable to all work from the entrance to the shaft or raise and including surge chambers.

This classification shall apply to all work involving surge chambers up to the ground level.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Cement Mason#
Determination:

SC-23-203-2-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday a
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) b
Saturday
Overtime
Hourly
Rate
(1 ½ X) b
c
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Cement Mason, Curb and
Gutter Machine Operator; Clary
and Similar Type of Screed
Operator (Cement only);
Grinding Machine Operator (all
types); Jackson Vibratory,
Texas Screed and Similar Type
Screed Operator; Scoring
Machine Operator
$47.70 $9.08 $12.35 $7.52 $0.64 $0.24 8.0 $77.53 $101.38 $101.38 $125.230 Magnesite, magnesite-terrazzo
and mastic composition, Epoxy,
Urethanes and exotic coatings,
Dex-O-Tex
$47.82 $9.08 $12.35 $7.52 $0.64 $0.24 8.0 $77.65 $101.56 $101.56 $125.470 Determination: SC-23-203-2-2025-1

Page 2 of 2 ends

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday a
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) b
Saturday
Overtime
Hourly
Rate
(1 ½ X) b
c
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Floating and Troweling Machine
Operator $48.70 $9.08 $12.35 $7.52 $0.64 $0.24 8.0 $78.53 $102.880 $102.880 $127.230 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount for supplemental dues. b Rate applies to the first 4 daily overtime hours and the first 12 hours worked on Saturday. All other time is paid at the double time (2X) rate. c Saturday in the same work week may be worked at straight-time rate, up to 8 hours on Saturday or when the employee has worked a total of 40 hours in the work week, if it is not reasonably possible for any individual employee on a particular job site to complete 40 hours of work on a 8 hour day, Monday through Friday, due to inclement weather or similar act of God or a situation beyond the control of the contractor.

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: #TEAMSTER (APPLIES ONLY TO WORK ON THE CONSTRUCTION SITE) Determination:

SC-23-261-2-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly
Rateb
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group I $41.59 8 $78.54 $99.335 $99.335 $120.13
Group II $41.74 8 $78.69 $99.56 $99.56 $120.43
Group III $41.87 8 $78.82 $99.755 $99.755 $120.69
Group IV $42.06 8 $79.01 $100.04 $100.04 $121.07
Group V $42.09 8 $79.04 $100.085 $100.085 $121.13
Group VI $42.12 8 $79.07 $100.13 $100.13 $121.19
Group VII $42.37 8 $79.32 $100.505 $100.505 $121.69
Group VIII $42.62 8 $79.57 $100.88 $100.88 $122.19
Group IX $42.82 8 $79.77 $101.18 $101.18 $122.59
Group X $43.12 8 $80.07 $101.63 $101.63 $123.19
Group XI $43.62 8 $80.57 $102.38 $102.38 $124.19
Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $4.95
Training $2.02
Other $0.61
Determination: SC-23-261-2-2025-1

Page 2 of 7 ends

Wages and total hourly rates (including employer payments):

Classificationd
(Subjourneyman)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly
Rateb
(1½x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
0-2000 hours $27.80 8 $63.60 $77.50 $77.50 $91.40
2001-4000 hours $29.80 8 $65.85 $80.75 $80.75 $95.65
4001-6000 hours $31.80 8 $68.10 $84.00 $84.00 $99.90
Over 6000 hours and thereafter at journeyman rates.

Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $3.80 ($4.05 for 2001-4000 hours; $4.30 for 4001-6000 hours) Training $2.02
Other $0.61
Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-261-2-2025-1

Page 3 of 7 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: #TEAMSTER (SPECIAL SHIFT)
(APPLIES ONLY TO WORK ON THE CONSTRUCTION SITE)
Determination:

SC-23-261-2-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly
Rateb (1½
x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group I $42.59 8 $79.54 $100.835 $100.835 $122.13
Group II $42.74 8 $79.69 $101.06 $101.06 $122.43
Group III $42.87 8 $79.82 $101.255 $101.255 $122.69
Group IV $43.06 8 $80.01 $101.54 $101.54 $123.07
Group V $43.09 8 $80.04 $101.585 $101.585 $123.13
Group VI $43.12 8 $80.07 $101.63 $101.63 $123.19
Group VII $43.37 8 $80.32 $102.005 $102.005 $123.69
Group VIII $43.62 8 $80.57 $102.38 $102.38 $124.19
Group IX $43.82 8 $80.77 $102.68 $102.68 $124.59
Group X $44.12 8 $81.07 $103.13 $103.13 $125.19
Group XI $44.62 8 $81.57 $103.88 $103.88 $126.19
Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $4.95
Training $2.02
Other $0.61
Determination: SC-23-261-2-2025-1

Page 4 of 7 ends

Wages and total hourly rates (including employer payments):

Classificationd
(Subjourneyman)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly Rateb
(1½x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
0-2000 hours $27.80 8 $63.60 $77.50 $77.50 $91.40
2001-4000 hours $29.80 8 $65.85 $80.75 $80.75 $95.65
4001-6000 hours $31.80 8 $68.10 $84.00 $84.00 $99.90
Over 6000 hours and thereafter at journeyman rates.

Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $3.80 ($4.05 for 2001-4000 hours; $4.30 for 4001-6000 hours) Training $2.02
Other $0.61
Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-261-2-2025-1

Page 5 of 7 ends

GENERAL PREVAILING WAGE DETERMINATION MADE BY

THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS CRAFT: #TEAMSTER (SECOND SHIFT)
(APPLIES ONLY TO WORK ON THE CONSTRUCTION SITE)
Determination:

SC-23-261-2-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now.

Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and total hourly rates (including employer payments):

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Hourse
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly Rateb
(1½ x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
Group I $43.59 8 $80.54 $102.335 $102.335 $124.13
Group II $43.74 8 $80.69 $102.56 $102.56 $124.43
Group III $43.87 8 $80.82 $102.755 $102.755 $124.69
Group IV $44.06 8 $81.01 $103.04 $103.04 $125.07
Group V $44.09 8 $81.04 $103.085 $103.085 $125.13
Group VI $44.12 8 $81.07 $103.13 $103.13 $125.19
Group VII $44.37 8 $81.32 $103.505 $103.505 $125.69
Group VIII $44.62 8 $81.57 $103.88 $103.88 $126.19
Group IX $44.82 8 $81.77 $104.18 $104.18 $126.59
Group X $45.12 8 $82.07 $104.63 $104.63 $127.19
Group XI $45.62 8 $82.57 $105.38 $105.38 $128.19
Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $4.95
Training $2.02
Other $0.61
Determination: SC-23-261-2-2025-1

Page 6 of 7 ends

Wages and total hourly rates (including employer payments):

Classificationd
(Subjourneyman)
Basic
Hourly
Rate
Hours
Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1½ x)
Saturday
Overtime
Hourly Rateb
(1½x)
Sunday/Holiday
Overtime
Hourly Rate
(2 x)
0-2000 hours $27.80 8 $63.60 $77.50 $77.50 $91.40
2001-4000 hours $29.80 8 $65.85 $80.75 $80.75 $95.65
4001-6000 hours $31.80 8 $68.10 $84.00 $84.00 $99.90
Over 6000 hours and thereafter at journeyman rates.

Employer Payments:

Type of Fund Amount per Hour
Health and Welfare $20.37
Pension $9.00
Vacation and Holidayc $3.80 ($4.05 for 2001-4000 hours; $4.30 for 4001-6000 hours) Training $2.02
Other $0.61
Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-23-261-2-2025-1

Page 7 of 7 ends

Classifications:

Group I
Warehouseman and Teamster
Group II
Driver of Vehicle or Combination of Vehicles - 2 axles
Traffic Control Pilot Car, excluding moving heavy
equipment permit load
Truck Mounted Power Broom
Group III
Driver of Vehicle or Combination of Vehicles - 3 axles
Bootman
Cement Mason Distribution Truck
Fuel Truck Driver
Water Truck - 2 axles
Dump Truck of less than 16 yards water level
Erosion Control Driver
Group IV
Driver of Transit Mix Truck-Under 3 yds
Dumpcrete Truck Less than 6½ yards water level
Truck Repairman Helper
Group V
Water Truck 3 or more axles
Warehouseman Clerk
Slurry Truck Driver
Group VI
Driver of Transit Mix Truck - 3 yds or more
Dumpcrete Truck 6½ yds water level and over
Driver of Vehicle or Combination of Vehicles - 4 or
more axles
Driver of Oil Spreader Truck
Dump Truck 16 yds to 25 yds water level
Side Dump Trucks
Flow Boy Dump Trucks
Group VII
A Frame, Swedish Crane or Similar
Forklift Driver
Ross Carrier Driver
Group VIII
Dump Truck of 25 yds to 49 yards water level
Truck Repairman
Water Pull Single Engine
Welder
Group IX
Truck Repairman Welder
Low Bed Driver, 9 axles or over
Group X
Working Truck Driver
Truck Greaser and Tireman - $0.50 additional for
Tireman
Pipeline and Utility Working Truck Driver, including
Winch Truck and Plastic Fusion, limited to Pipeline
and Utility Work
Dump Truck and Articulating - 50 yards or more water
level
Water Pull Single Engine with attachment
Group XI
Water Pull Twin Engine
Water Pull Twin Engine with attachments
Winch Truck Driver - $0.25 additional when operating
a Winch or similar special attachment
# Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a For classifications within each group, see Page 7. b Rate applies to the first 4 daily overtime hours on weekdays and the first 12 hours on Saturday. All other overtime is paid at the Sunday/Holiday double-time rate. c Includes an amount for Supplemental Dues. d Subjourneymen may be employed at a ratio of one subjourneyman for every five journeymen. e The third shift shall work 6.5 hours, exclusive of meal period, for which 8-hours straight time shall be paid at the non-shift rate, Monday through Friday.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Drywall Installer/Lather (Carpenter)#
Determination:

SC-31-X-41-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director - Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday a
Training Other
b
Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X) c
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Drywall Installer/Lather $52.24 $9.50 $6.41 $7.46 $0.77 $5.27 8.0 $81.65 $107.770 $107.770 $133.89 Determination:

SC-31-X-41-2026-1A
Issue Date:

February 22, 2026
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director - Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Determination: SC-31-X-41-2026-1 and SC-31-X-41-2026-1A

Page 2 of 2 ends

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura counties
Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday a
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X) c
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Stocker, Scrapper $21.97 $5.50 $0.00 $8.46 $0.77 $0.00 8.0 $36.70 $47.685 $47.685 $58.67 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount per hour worked for supplemental dues. b Includes an amount for Annuity.
c Rate applies to the first 4 daily overtime hours and to the first 8 hours on Saturday. All other overtime will be paid the Sunday and Holiday double time rate. Saturdays in the same workweek may be worked at straight-time if job is shut down during the normal work week due to inclement weather.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Elevator Constructor#
Determination:

SC-62-X-999-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

December 31, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-477.

Localities:

All localities within Imperial, Los Angeles, Orange, Riverside, San Diego, Santa Barbara and Ventura counties. Portions of Kern, San Bernardino and San Luis Obispo counties are detailed below a.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension
b
Vacation
and
Holiday c
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) d
Saturday
Overtime
Hourly
Rate
(1 ½ X) d
Sunday/
Holiday
Overtime
Hourly
Rate
Mechanic $72.36 $16.375 $21.76 $6.57 $0.85 $1.90 8.0 $119.815 $155.995 $155.995 $192.175 Mechanic (employed in
industry more than 5 years) $72.36 $16.375 $21.76 $8.02 $0.85 $1.90 8.0 $121.265 $157.445 $157.445 $193.625 Helper e $50.65 $16.375 $21.76 $4.60 $0.85 $1.90 8.0 $96.135 $121.460 $121.460 $146.785 Helper (employed in industry
more than 5 years) e $50.65 $16.375 $21.76 $5.61 $0.85 $1.90 8.0 $97.147 $122.472 $122.472 $147.797 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-62-X-999-2026-1

Page 2 of 2 ends

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Applies to that portion of these counties south of the Tehachapi Line. For more information contact the Office of the Director – Research Unit. b Includes an amount for Annuity Trust Fund. c Includes an amount for 8 paid holidays. d For Contract Service work only. All other overtime is paid at the Sunday/Holiday rate. e Ratio: The total number of Helpers employed shall not exceed the number of Mechanics on any one job. When removing old and installing new cables on existing elevator installations, the Company may use two (2) Helpers, Apprentices or Assistant Mechanics to one (1) Mechanic.

Two (2) Helpers, Apprentices or Assistant Mechanics to each three (3) Mechanics may be employed in Contract Service work only. For more information on the use of Helpers, contact the Office of the Director – Research Unit.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Dredger (Operating Engineer)#
Determination:

SC-63-12-23-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

July 31, 2026** The rate to be paid for work performed after this date has been determined. If work will extend past this date, the new rate must be paid and should be incorporated in contracts entered into now. Contact the Office of the Director - Research Unit for specific rates at (415) 703-4774.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara, and Ventura counties.

Wages and Employer Payments:

Classification
Basic
Hourly
Rate
Health
and
Welfare
Pension aVacation
and
Holiday
b
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X) c
Sunday
Overtime
Hourly
Rate
(2 X)
Holiday
Overtime
Hourly
Rate
(3X)
Chief Engineer,
Deck Captain $64.90 $15.20 $19.65 $6.70 $1.10 $0.15 8 $107.70 $140.150 $140.150 $172.60 $237.50 Leverman $67.90 $15.20 $19.65 $6.70 $1.10 $0.15 8 $110.70 $144.65 $144.65 $178.60 $246.50 Watch Engineer,
Deckmate $61.82 $15.20 $19.65 $6.70 $1.10 $0.15 8 $104.62 $135.53 $135.53 $166.44 $228.26 Winchman (Stern
Winch on
Dredge)
$61.27 $15.20 $19.65 $6.70 $1.10 $0.15 8 $104.07 $134.71 $134.71 $165.34 $226.61 Fireman-Oiler,
Leveehand,
Deckhand (can
operate anchor
scow under
direction of mate),
Bargeman
$60.73 $15.20 $19.65 $6.70 $1.10 $0.15 8 $103.53 $133.90 $133.90 $164.26 $224.99 Determination: SC-63-12-23-2026-1

Page 2 of 2 ends

Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

MISCELLANEOUS PROVISION:

Employees required to suit up and work in a hazardous material environment, shall receive Two Dollars ($2.00) per hour in addition to their regular rate of pay, and that rate shall become the basic hourly rate of pay. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount for annuity. b Includes an amount for supplemental dues.
c Rate applies to the first 4 daily overtime hours and first 12 hours on Saturdays. All other time is paid at the Sunday overtime rate.

Classification
Basic
Hourly
Rate
Health
and
Welfare
Pension aVacation
and
Holiday
b
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X) c
Sunday
Overtime
Hourly
Rate
(2 X)
Holiday
Overtime
Hourly
Rate
(3X)
Dozer Operator $61.93 $15.20 $19.65 $6.70 $1.10 $0.15 8 $104.73 $135.70 $135.70 $166.66 $228.59 Hydrographic
Surveyor $63.36 $15.20 $19.65 $6.70 $1.10 $0.15 8 $106.16 $137.84 $137.84 $169.52 $232.88 Barge Mate $61.34 $15.20 $19.65 $6.70 $1.10 $0.15 8 $104.14 $134.81 $134.81 $165.48 $226.82 Welder $63.32 $15.20 $19.65 $6.70 $1.10 $0.15 8 $106.12 $137.78 $137.78 $169.44 $232.76

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Landfill Worker (Operating Engineer)
Determination:

SC-63-12-41-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare a
Pension
Vacation
and
Holiday b
Hours
Total
Hourly
Rate c
Daily/Holiday
Overtime
Hourly Rate
(1 ½ X) d
Sunday
Overtime
Hourly
Rate
(2 X)
Heavy Duty Repairman and/or Welder $40.75 $6.32 $9.65 $0.78e 8.0 $57.50 $70.775 $91.15 Equipment Operator II $31.25 $6.14 $9.65 $0.60f 8.0 $47.64 $56.525 $72.15 Equipment Operator III $32.25 $6.16 $9.65 $0.62g 8.0 $48.68 $58.025 $74.15 PM Tech $33.50 $6.18 $9.65 $0.64h 8.0 $49.97 $59.900 $76.65 Laborer/Spotter $23.60 $5.99 $4.07 $0.45i 8.0 $34.11 $39.470 $51.27 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Determination: SC-63-12-41-2025-1

Page 2 of 2 ends

Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. a Includes amounts for Sick Leave and Health Insurance that apply to the first 173.33 hours worked per month. b This amount applies to the first 173.33 hours worked per month. c Computation is based on the first year of employment. This rate should be increased by any applicable vacation increase as stated in the other footnotes.
d Rate applies to all hours worked in excess of forty (40) hours in a workweek or in excess of eight (8) hours in any one day. Rate also applies to sixth consecutive day of work. For any daily hours worked in excess of twelve (12) hours, the Sunday overtime rate would apply. e $1.57 after 2 years of service; $2.35 after 5 years of service. f $1.20 after 2 years of service; $1.80 after 5 years of service. g $1.24 after 2 years of service; $1.86 after 5 years of service. h $1.29 after 2 years of service; $1.93 after 5 years of service. i $0.91 after 2 years of service; $1.36 after 5 years of service.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Gunite Worker (Laborer)
Determination:

SC-102-345-1-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara, and Ventura counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate a
Health
and
Welfare
Pension Vacation
and
Holiday
b
Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Daily
Overtime
Hourly
Rate
(2 X)
Saturday
Overtime
Hourly
Rate
(1 ½ X) d e
Saturday
Overtime
Hourly
Rate
(2 X) e
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Ground Wire
Man,
Nozzleman,
Rodman
$55.88 $9.55 $10.00 $6.35 $0.21 8.0 $81.99 $109.93 $137.87 $109.93 $137.87 $137.87 Gunman $54.93 $9.55 $10.00 $6.35 $0.21 8.0 $81.04 $108.505 $135.97 $108.505 $135.97 $135.97 Reboundman $51.39 $9.55 $10.00 $6.35 $0.21 8.0 $77.50 $103.195 $128.89 $103.195 $128.89 $128.89 Entry-Level
Gunite Worker
Step 1 f (0-1000
hours)
$38.24 $6.48 $10.00 $6.35 $0.18 8.0 $61.25 $80.37 $99.49 $80.37 $99.49 $99.49 Entry-Level
Gunite Worker
Step 2 f (1001-
2000 hours)
$40.24 $6.48 $10.00 $6.35 $0.18 8.0 $63.25 $83.37 $103.49 $83.37 $103.49 $103.49 Determination: SC-102-345-1-2025-1

Page 2 of 2 ends

Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. a Employees working from a Bos’n’s Chair or suspended from a rope or cable shall receive $0.40/hour above this rate. b Includes an amount per hour worked for Supplemental Dues. c Rate applies to the first 3 overtime hours.
d Rate applies to the first 11 overtime hours.
e In the event it is not reasonably possible to complete forty (40) hours of work on an eight (8) hour day shift, Monday through Friday, then the balance of the forty (40) hours may be worked on Saturday at the straight time rate. f Ratio is one Entry-Level Gunite Worker for the 1st 4 Journeymen on the job (although the Entry-Level Gunite Worker may be the 2nd worker on the job) and 1 Entry-Level Gunite Worker for every 4 Journeymen thereafter (the Entry-Level Gunite Worker may not be on the job until after all 4 Journeymen are on the job).

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Housemover (Laborer)
Determination:

SC-102-507-1-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday a
Training Other
b
Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X) c
Saturday
Overtime
Hourly
Rate
(1 ½ X) c
d
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Housemover $46.53 $9.55 $12.57 $5.02 $0.80 $0.57 8.0 $75.04 $98.305 $98.305 $121.57 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Determination: SC-102-507-1-2025-1

Page 2 of 2 ends

a Includes Supplemental Dues contribution.
b Include an amount for Contract Administration Fund ($0.09), Contract Compliance Trust Fund ($0.30), Industry Fund ($0.12), and Laborers Trusts' Administrative Trust Fund ($0.06).
c Any hours over 12 hours in a single workday are double time. d If the employee is unable to complete the forty (40) hours during the normal workweek, Monday through Friday, due to inclement weather or a situation beyond the employers control, then the balance of the forty (40) hours may be worked on Saturday at the straight-time rate in the same workweek.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Asbestos and Lead Abatement (Laborer) #
Determination:

SC-102-882-1-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

July 31, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relation. Contact the Office of the Director - Research Unit at (415) 703-4774 for the new rates after ten days after the expiration date if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holidaya
Training Otherb Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X)
Saturday
Overtime
Hourly
Ratec
(1 ½ X)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Asbestos and Lead
Abatement Worker $46.48 $9.55 $12.57 $5.02 $0.85 $0.51 8.0 $74.98 $98.22 $98.22 $121.46 Note:

Asbestos Abatement must be trained and the work conducted according to the Code of Federal Regulations 29 CFR 1926.58, the California Labor Code 6501.5 and the California Code of Regulations Title 8, Section 5208. Contractors must be certified by the Contractors' State License Board and registered with the Division of Occupational Safety and Health (DOSH). For further information, contact the Asbestos Contractors Abatement Registration Unit, DOSH at (916) 574-2993.

Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Determination: SC-102-882-1-2025-1

Page 2 of 2 ends

Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount for supplemental dues. b Includes amounts for Center for Contract Compliance, Contract Administration Fund, Industry Fund, and Laborers' Trust Administrative Trust Fund.
c Saturdays in the same work week may be worked at straight-time if the job is shut down during the normal work week due to inclement weather, or reasons beyond the control of the employer.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Horizontal Directional Drilling (Laborer)#
Determination:

SC-102-1184-1-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holidaya
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1 ½ X)
Saturday
Overtime
Hourly
Rate
(1 ½ X)b
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Group 1 (Drilling Crew Laborer) $47.94 $9.55 $8.92 $3.55 $0.46 $1.08 8.0 $71.50 $95.47 $95.47 $119.44 Group 2 (Vehicle Operator/
Hauler)
$48.11 $9.55 $8.92 $3.55 $0.46 $1.08 8.0 $71.67 $95.725 $95.725 $119.78 Group 3 (Horizontal Directional
Drill Operator)
$49.96 $9.55 $8.92 $3.55 $0.46 $1.08 8.0 $73.52 $98.50 $98.50 $123.48 Group 4 (Electronic Tracking
Locator, Subsurface Imaging
Laborer)
$51.96 $9.55 $8.92 $3.55 $0.46 $1.08 8.0 $75.52 $101.50 $101.50 $127.48 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Determination: SC-102-1184-1-2025-1

Page 2 of 2 ends

Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount for Supplemental Dues. b In the event, due to inclement weather, major equipment breakdown, or similar Act of God, it is not reasonably possible to complete forty (40) hours of work Monday through Friday, then the balance of the forty (40) hours may be worked on Saturday at the straight-time rate.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773, AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: LANDSCAPE/IRRIGATION LABORER/TENDER#
Determination:

SC-102-X-14-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

July 31, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Wages and Employer Payments:

Classification
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holidaya
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1 ½ X)
Saturday
Overtime
Hourly
Rateb c
(1 ½ X)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Landscape/Irrigation Laborer $44.67 $9.55 $12.57 $5.02 $0.80 $0.50 8.0 $73.11 $95.445 $95.445 $117.780 Landscape Hydro Seeder $45.77 $9.55 $12.57 $5.02 $0.80 $0.50 8.0 $74.21 $97.095 $97.095 $119.980 Determination:

SC-102-X-14-2026-1A
Issue Date:

February 22, 2026
Expiration date of determination:

July 31, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, and Ventura Counties.

Determination: SC-102-X-14-2025-1

Page 2 of 2 ends

Wages and Employer Payments:

Classification
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holidaya
Training Other Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rateb
(1 ½ X)
Saturday
Overtime
Hourly
Rateb c
(1 ½ X)
Sunday/
Holiday
Overtime
Hourly
Rate
(2 X)
Landscape/Irrigation Tender d $21.97 $4.20 $2.19 $1.18 $0.00 $0.00 8.0 $29.54 $40.525 $40.525 $51.510 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. # Indicates an apprenticeable craft. The current apprentice wage rates are available on the Prevailing Wage Apprentice Determinations Website (http://www.dir.ca.gov/OPRL/PWAppWage/PWAppWageStart.asp). a Includes an amount per hour worked for Supplemental Dues. b Rate applies to first 4 daily overtime hours and the first 12 hours on Saturday. All other time is paid at the Sunday and Holiday double-time rate.
c Saturdays in the same work week may be worked at straight-time if adverse weather or jobsite ground conditions require that the job be shut down for one or more workdays during the regular workweek. d The first employee on the jobsite shall be a Landscape/Irrigation Laborer; the second employee on the jobsite must be an Apprentice or a Landscape/Irrigation Laborer; and the third and fourth employees may be Tenders. The fifth employee on the jobsite shall be a Landscape/Irrigation Laborer; the sixth employee must be an Apprentice or a Landscape/Irrigation Laborer; and the seventh and eight employees may be Tenders. Thereafter, Tenders may be employed with Landscape/Irrigation Laborers in a 50/50 ratio on each jobsite.

However, plant establishment may be performed exclusively by Landscape/Irrigation Tenders without the supervision of a Journeyman.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: TREE MAINTENANCE (LABORER) 1
(APPLIES ONLY TO ROUTINE TREE MAINTENANCE WORK, NOT CONSTRUCTION AND/OR LANDSCAPE CONSTRUCTION) 2 Determination:

SC-102-X-20-2025-1
Issue Date:

August 22, 2025
Expiration date of determination:

June 30, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Imperial, Inyo, Kern, Los Angeles, Mono, Orange, Riverside, San Bernardino, San Diego, San Luis Obispo, Santa Barbara and Ventura Counties.

Wages and Employer Payments:

Classificationa
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension
Vacation
and
Holiday
Training Other Hours
Total
Hourly
Rate
Daily
Overtime
Hourly Rateb
(1 ½ X)
Sunday/Holiday
Overtime Hourly
Rate (2 X)
Senior Tree Trimmer $27.69 $4.10 $2.26 $2.47 $0.00 $0.30 8.0 $36.82 $50.665 $64.51 Tree Trimmer $25.69 $4.10 $2.26 $2.27 $0.00 $0.30 8.0 $34.62 $47.465 $60.31 Groundperson $24.05 $4.10 $2.26 $2.12 $0.00 $0.30 8.0 $32.83 $44.855 $56.88 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Determination: SC-102-X-20-2025-1

Page 2 of 2 ends

Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774. 1 This determination does not apply to the work of a landscape laborer employed on landscape construction (work incidental to construction or post-construction maintenance during the plant installation and establishment period) or to tree trimming work involving line clearance. 2 This determination does not apply to the work of a landscape laborer employed on landscape construction (work incidental to construction or post-construction maintenance during the plant installation and establishment period) or to tree trimming work involving line clearance. a There shall be at least one Senior Tree Trimmer on crews of three or more. b Monday thru Saturday shall constitute a workweek. Rate applies to first 4 overtime hours Monday thru Saturday, and all time worked in excess of forty (40) hours per workweek. All other time is paid at the Sunday and Holiday double-time rate.

GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1

FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS Craft: Light Fixture Maintenance
Determination:

SC-830-61-1-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

March 31, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Localities:

All localities within Riverside County. For other counties please contact the Office of the Director – Research Unit prior to Bid Advertisement at (415) 703-4774.

Wages and Employer Payments:

Classification
(Journeyperson)
Basic
Hourly
Rate
Health
and
Welfare
Pension Vacation
and
Holiday
Training Hours Total
Hourly
Rate
Daily
Overtime
Hourly
Rate
(1½ X)
Saturday/Sunday
Overtime Hourly
Rate
(1½ X)
Holiday
Overtime
Hourly
Rate
(2 X)
Lighting
Maintenance
Service Person
$16.90 $0.29 $0.00 $0.34 $0.00 8.0 $17.53 $25.98 $25.98 $34.43 Determination:

SC-830-61-2-2026-1
Issue Date:

February 22, 2026
Expiration date of determination:

March 31, 2026* Effective until superseded by a new determination issued by the Director of Industrial Relations. Contact the Office of the Director – Research Unit at (415) 703-4774 for the new rates after 10 days from the expiration date, if no subsequent determination is issued.

Determination: SC-830-61-1-2026-1 and SC-830-61-2-2026-1

Page 2 of 2 ends

Localities:

All localities within San Bernardino County. For other counties please contact the Office of the Director – Research Unit prior to Bid Advertisement at (415) 703-4774.

Wages and Employer Payments:

Classification Basic
Hourly
Rate
Health and
Welfare
Pension Vacation and
Holiday
Training Hours Total
Hourly
Rate
Daily Overtime
Hourly Rate
(1 ½ X)
Sunday/
Holiday
Overtime Hourly
Rate
(1 ½ X)
Lighting Maintenance
Service Person $16.90 $2.43 $0.39 $0.00 $0.50 8.0 $20.22 $28.67 $28.67 Recognized holidays:

Holidays upon which the general prevailing hourly wage rate for Holiday work shall be paid, shall be all holidays in the collective bargaining agreement, applicable to the particular craft, classification, or type of worker employed on the project, which is on file with the Director of Industrial Relations. If the prevailing rate is not based on a collectively bargained rate, the holidays upon which the prevailing rate shall be paid shall be as provided in Section 6700 of the Government Code. You may obtain the holiday provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Holiday provisions for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Travel and/or subsistence payment:

In accordance with Labor Code Sections 1773.1 and 1773.9, contractors shall make travel and/or subsistence payments to each worker to execute the work. You may obtain the travel and/or subsistence provisions for the current determinations on the Director's General Prevailing Wage Determinations Website (http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm). Travel and/or subsistence requirements for current or superseded determinations may be obtained by contacting the Office of the Director – Research Unit at (415) 703-4774.

Appendix B
Technical Specifications and Special Conditions
Technical Specifications and Special Conditions as prepared by The Holt Group, Inc. dated 02/18/2026.

CITY OF IMPERIAL

WASTEWATER TREATMENT

PLANT DEMOLITION PROJECT

TECHNICAL SPECIFICATIONS

APPENDIX B
February 18, 2026
CITY OF IMPERIAL BID NO. 2025-019
THG PROJECT NUMBER: 173.138
City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 1 of 21 ends

TECHNICAL SPECIFICATIONS

TECHNICAL SPECIFICATIONS
Table of Contents

1. Demoltion Requirements ....................................................................................... 2

2. Abbreviations.......................................................................................................... 5

3. Definitions ............................................................................................................... 6

4. Diversion Requirements ...................................................................................... 12

5. Source Separation................................................................................................ 13

6. Demolition Debris to be Disposed at Construction and Demoltion Material Facility with a Solids Waste Permit and SWIS Number ........................................... 14

7. California Certified Public Scale Demoltion Material Weighing Requirements…........................................................................................................... 15

8. Asbestos and Lead Requirements ..................................................................... 17 City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 2 of 21 ends

TECHNICAL SPECIFICATIONS

1. DEMOLITION REQUIREMENTS
This project shall be completed in conformance with the Improvement Plans, Technical Specifications and Special Conditions of these contract documents which were prepared specifically for this project and supersede the City of Imperial Municipal mandatory construction and demolition recycling program ordinance prepared for private construction and demolition projects within the City of Imperial. The Technical Specifications and Special Conditions were prepared in accordance with the California Code of Regulations (CCR’s) including the California Green Building Standards Code.

During the preparation of the project design documents a Waste Management Report Identification of Construction and Demolition Debris (WMRIC&D) Chart was prepared.

The WMRIC&D Chart lists the known items compromising the different structures to undergo demolition. Separate WMRIC&D Charts were prepared for each structure to undergo demolition. The WMRIC&D Charts are included as Table “A” in the Special Conditions Section of the specifications.

During the project design, it was attempted to identify and place each type of demolition item on the WMRIC&D – Chart; however, there will likely be unknown below grade items or items which are not visible by observation which will be discovered and required to undergo demolition during the construction period. It is the responsibility of the contractor to review the as-built drawings, as referenced by the improvement plans, and conduct a field review during the bidding period to observe the demolition items on the WMRIC&D – Chart and identify any additional items which may require demolition during project construction.

Diversion requirements as listed in Technical Specification Item 4 require that 100 percent of inert material by weight and a minimum of 65 percent of Construction and Demolition debris (non-inert material) by weight be recycled, reused or salvaged. The weight of the materials on the WMRIC&D – Chart is therefore important and monitoring the weight of the different demolition materials removed from the project site during project construction is very important. The WMRIC&D – Chart prepared during the design period listed the City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 3 of 21 ends

TECHNICAL SPECIFICATIONS
approximate calculated weight of a few of the demolition material items; however the weight of most of the items, such as the clarifier steel bridges, center wells or raker arms, were not possible to calculate and are not included on the WMRIC&D – Chart. The contractor will not be required to estimate the weight of the WMRIC&D – Chart items during the bidding phase, however; the contractor will be required to weigh each item load removed from the project site during project construction. The weight of each demolition material item leaving the project site shall be recorded on the Daily Recycling Log of Construction & Demolition (C & D) Material Chart – Table B.

The Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B is contained in the Special Conditions section of the specifications. The Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B includes eighteen columns. A Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B Chart has been prepared for each project demolition structure. The Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B shall be made current each day; except that copies of the weight slips and vendor receipts will be allowed to be delivered to the Construction Manager the day after the demolition material is delivered to the vendor. Column 16 requires the Construction Manager to initial and date each listed demolition item the day after the item is removed from the project site to verify all columns for a particular item have been satisfactorily completed. The Construction Manager shall require the contractor stop demolition work if the contractor does not maintain the Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B current on a daily basis. The Contractor shall not be compensated for these work stoppages. There will undoubtably be existing unknown buried materials or other unknown materials which will be discovered during the project demolition. All previously unknown materials shall be included on the Daily Recycling Log of Construction & Demolition (C & D) Chart – Table B.

A Waste Management Summary Report – Table C Chart shall be prepared each Monday for the previous week’s demolition work. The Waste Management Summary Report – Table C Chart is contained in the Special Conditions of the specifications. The Waste Management Summary Report – Table C Chart includes thirteen column items. The City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 4 of 21 ends

TECHNICAL SPECIFICATIONS
Waste Management Summary Report – Table C Chart will transfer weight related column information from the previous week from Table B to Table C. The Table C accumulative inert and non-inert diversion percentages will be calculated each week. If diversion percentages are not in conformance with the diversion goals the contractor shall determine on how recycling, reuse or salvage methods will be modified to bring the diversion percentages within the diversion percentage goals. The Construction Manager shall require the contractor stop demolition work if the contractor does not maintain the Waste Management Summary Report current on a weekly basis. The Contractor shall not be compensated for these work stoppages.

Quantity and weight estimates for several of the largest demolition item contributors were completed for several quantifiable items including the pcc concrete and ductile iron piping, valves, fittings and related items. The quantity estimates were completed to determine the rough, approximate weight of these materials and gain insight as to the magnitude of the demolition work. Many of the estimates are relying on as-built plans, which may not be completely accurate. There may have been construction improvements completed over the last 40 years for some of the buried or unobservable items which were not recorded (but will require demolition). The quantity and weight estimates are to be considered rough and accurate within 40 percent of the calculated weight of a particular item designation. The quantity and weight estimates are included as Table D documents in the Special Conditions section of the specifications.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 5 of 21 ends

TECHNICAL SPECIFICATIONS

2. ABBREVIATIONS

1. C&D: Construction and Demolition

2. CalMAX: California Materials Exchange

3. CalRecycle: California Department of Resources and Recycling and Recovery

4. CCR: California Code of Regulations

5. CDRG: Construction and Demolition Recycling Guide

6. LEA: Local Enforcement Agency

7. SWDD Report: Solid Waste Diversion and Disposal Report

8. SWIS – Solid Waste Information System

9. WMRIC&D – Waste Management Report Identification of Construction and Demolition Debris.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 6 of 21 ends

TECHNICAL SPECIFICATIONS

3. DEFINITIONS

3.1 CONSTRUCTION AND DEMOLITION (C&D) / INERT DEBRIS

PROCESSING FACILITIES OPERATING UNDER A SOLIDS WASTE PERMIT A C&D / Inert Debris Processing Facility operating under a Solids Waste Facility Permit accepts loads of Construction and Demolition (C&D) waste for the purpose of recovering re-useable and recyclable inert debris for processing; and disposing of the non- recyclable or non-re-useable debris material. These facilities are approved by the Local Enforcement Agency (LEA), as later defined in this technical specification section, and possess a Solid Waste Information System (SWIS) number.

3.2 C & D DEBRIS
Construction and Demolition Debris, or “C & D Debris” is solid waste that is a portion of the waste stream defined as construction and demolition wastes, as defined in California Code of Regulations Article 4, Section 17225.15 and means source separated or separated for reuse solid waste and recyclable materials, including commingled and separated materials, that result from construction work, that are not hazardous, as defined in California Code of Regulations (CCR), Title 22, Section 66261.3 et seq., and that contain no more than 1 percent putrescible wastes do not constitute a nuisance, as determined by the LEA.

3.3 CLASS III LANDFILL
A landfill that accepts non-hazardous solid waste such as household, commercial, and industrial solid waste. A Class III landfill is regulated by the LEA and must have a CalRecycle solid waste information system (SWIS) number.

3.4 DECONSTRUCTION
The systematic removal of usage items from a structure.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 7 of 21 ends

TECHNICAL SPECIFICATIONS

3.5 DEMOLITION
The complete or partial removal of a structure, building, or site improvement, including associated materials and systems, as part of a construction or renovation project.

3.6 DISPOSAL
Acceptance of solid waste at a legally operating facility for the purpose of landfilling.

3.7 DISPOSED
Solid waste debris to be processed and placed at a landfill site.

3.8 DIVERSION
Activities that result in reducing the amount of solid waste that is disposed at a landfill. This can include source reduction activities, composting, recycling and reuse.

3.9 INERT DEBRIS
Solid waste and recyclable debris that are source separated or separated for reuse and do not contain hazardous waste (as defined in CCR, Title 22, section 66262.3 et. Seq.) or soluble pollutants at concentrations more than applicable water quality requirements. Inert debris may not contain more than 1 percent putrescible wastes by volume and shall not constitute a nuisance, as determined by the LEA. Inert debris shall include non-organic, non-hazardous construction and demolition debris that does not undergo significant physical, chemical, or biological transformation. Acceptable Inert debris include:

3.9.1 Concrete (with or without embedded rebar)

3.9.2 Asphalt Paving

3.9.3 Brick and masonry block

3.9.4 Ceramic and Clay Tile
City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 8 of 21 ends

TECHNICAL SPECIFICATIONS

3.9.5 Glass (non-coated, non-laminated)

3.9.6 Stucco (free of wire mesh or organic contamination)

3.9.7 Sand, gravel and uncontaminated soil.

Items such as wood, drywall, insulation, plastics, metals (excluding embedded rebar in concrete), organic matter, and trash shall not exceed 10% by volume of the inert material.

3.10 INERT DEBRIS RECYCLING CENTER
Per California Code of Regulations, Article 5.9, Section 17381.1a2, an inert debris recycling center can receive only Type “A” inert debris that is source separated or separated for reuse. Type “A” inert debris includes but is not limited to concrete (including fiberglass or steel reinforcing bar embedded in the concrete), fully cured asphalt, glass, fiberglass, asphalt or fiberglass roofing shingles, brick, slag, ceramics, plaster, clay and clay products. Type “A” inert material is waste that does not contain soluble pollutants at concentrations in excess of water quality objectives and has not been treated to reduce pollutants.

Type “B” inert debris is solid waste that is specifically determined to be inert by the applicable Regional Water Quality Control Board, such as treated industrial wastes and de-watered bentonite-based drilling mud but excludes Type “A” inert debris. The LED, upon consultation with the State Water Resources Control Board, will determine on a case-by-case basis whether materials not listed in CCR Article 5.9, Section 17380 qualify as Type “A” inert debris. An inert debris recycling center can operate without a SWIS number, if approved by the LEA.

3.11 LOCAL ENFORCEMENT AGENCY
The Local Enforcement Agency (LEA) is a state-certified entity under the California Department of Resources and Recycling and Recovery (CalRecycle).

The LEA mandate is to enforce federal, state and local laws related to solid waste management within its area of jurisdiction. Although the City of Imperial issues demolition permits and enforces construction and demolition debris City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 9 of 21 ends

TECHNICAL SPECIFICATIONS
recycling, reuse and disposal projects; the LEA performs complementary regulatory functions related to solids waste management within its area of jurisdiction as listed below:

3.11.1 Inspect solid waste landfills and transfer stations for compliance with state solids waste regulations.

3.11.2 Inspect construction and demolition (C&D) debris processing sites for compliance with state waste regulations. The LEA may conduct site inspections or audits of facilities receiving demolition material to verify proper diversion, recycling, or disposal practices.

3.11.3 LEA may respond to complaints or investigate illegal dumping or improper handling of debris.

3.11.4 LEA may inspect waste hauler operations and verify facility permitting

3.12 MIXED DEMOLITION MATERIAL (MDM)
Mixed Demolition Material refers to the heterogeneous combination of debris generated during the demolition of a commercial structure, encompassing both recyclable and non-recyclable components. This material may typically include a blend of concrete, brick, wood, metal, drywall, insulation, glass, plastics, asphalt and other construction-related substances that are not sorted at the point of generation. Mixed Demolition Material must be taken to a CalRecycle designated Certified Construction and Demolition (C&D) Waste Processing Facility for recycling, reuse or salvage purposes.

3.13 RECYCLING
The process of collecting, sorting, cleaning, treating, and reconstituting materials that would otherwise become solid waste, and returning them to the economic mainstream in the form of raw material for new, reused, or reconstituted products that meet the quality standards necessary to be used in the marketplace.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 10 of 21 ends

TECHNICAL SPECIFICATIONS

3.14 RECYCLING FACILITY
An operation that can legally accept materials for the purpose of processing the materials into an altered form for the manufacture of a new product. Depending on the types of materials accepted and the operating procedures, a recycling facility may or may not be required to have a Solid Waste Facilities permit from CalRecycle or be regulated by the LEA.

3.15 REUSE
Materials that are recovered for use in the same form. This includes materials that are reused on-site or off-site.

3.16 SALVAGE
Materials recovered for recycling or reuse or sale or donation to a third party.

3.17 SOURCE SEPARATION
Construction and demolition material that is sorted and segregated at the site of generation by individual material type for the purpose of reuse or recycling. For example, loads of concrete that are source-separated for delivery to an inert debris recycling facility to be crushed into road base material.

3.18 SOLID WASTE
Solid Waste is waste that CalRecycle has deemed acceptable for disposal at a Class III Landfill.

3.19 SOLID WASTE INFORMATION SYSTEM (SWIS)
The Solid Waste Information System (SWIS) is maintained by CalRecycle (California Department of Resources Recycling and Recovery) and serves as the centralized database for tracking the following:

3.19.1 Permitted solid waste facilities.

3.19.2 Closed or abandoned disposal sites.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 11 of 21 ends

TECHNICAL SPECIFICATIONS

3.19.3 Illegal dumping locations.

3.19.4 Inspection and enforcement data
Each site listed in SWIS is assigned a unique SWIS number, which is used for regulatory tracking, permitting, and compliance documentation. The SWIS number ensures alignment with state records and regulatory oversight.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 12 of 21 ends

TECHNICAL SPECIFICATIONS

4. DIVERSION REQUIREMENTS
One hundred percent (100%) of inert material for this project shall be recycled, reused or salvaged. CALGreen Code Section 5.408.1 (for nonresidential projects) and Section

4.408.1 (for residential projects) mandate that at least 65% of nonhazardous construction and demolition (C&D) debris (non-inert material) be recycled and salvaged for reuse, measured by weight. A total of up to 35% by weight of the total nonhazardous C&D debris (non-inert material) may be disposed of at a Class III landfill. These diversion guidelines apply to this project.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 13 of 21 ends

TECHNICAL SPECIFICATIONS

5. SOURCE SEPARATION
Mixed Demolition Material for inert material and non-inert material to be recycled, reused or salvaged shall not be allowed to be removed from the project site. The contractor shall implement on-site Source Separation of all these demolition materials into distinct segregated categories, including but not limited to: concrete, metals, wood, piping, electrical components, pipe fittings, pipe valves, hazardous materials (if applicable) and other distinct items. Each distinct material shall be placed in separate containers or staging areas. Each distinct material shall be hauled separately from the project site to an appropriate recycling, reuse or salvage facility. The contractor shall confirm that each facility will provide documentation of the material accepted for reuse ,recycling or salvage, and provide weight slips for the accepted material. The weight slips shall include the following:

5.1 Name and address of the scale facility

5.2 Date and time of weighing

5.3 Material type

5.4 Gross, tare and net weights

5.5 weight ticket number

5.6 Weight tickets must be legible, original and wet signed by the scale operator.

If the facility does not have the capability of weighing the material or providing the above listed information, then the contractor shall weigh the material at an independent weight scale in accordance with the independent weight scale technical specification prior to delivering the material to the recycling, disposal or salvage facility.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 14 of 21 ends

TECHNICAL SPECIFICATIONS

6. DEMOLITION DEBRIS TO BE DISPOSED AT CONSTRUCTION AND

DEMOLITION MATERIAL FACILITY WITH A SOLIDS WASTE PERMIT AND

SWIS NUMBER
A total of up to 35% by weight of the total nonhazardous C&D debris (non-inert material) may be disposed at a LEA approved C&D material facility with a solids waste permit and SWIS number. The contractor shall confirm the facility will provide documentation of the material accepted for disposal and landfill and provide weight slips for the accepted material. The weight slips shall include the following:

6.1 Name and address of the scale facility

6.2 Date and time of weighing

6.3 Material Descriptions – Description of each type of material being disposed.

6.4 Gross, tare and net weights

6.5 Weight ticket number

6.6 Weight tickets must be legible, original and wet signed by the scale operator.

If the facility does not have the capability of weighing the material or providing the above listed information, then the contractor shall weigh the material at an independent weight scale in accordance with the independent weight scale technical specification prior to delivering the material to the recycling, disposal or salvage facility.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 15 of 21 ends

TECHNICAL SPECIFICATIONS

7. CALIFORNIA CERTIFIED PUBLIC SCALE DEMOLITION MATERIAL

WEIGHING REQUIREMENTS

7.1 PURPOSE
This clause establishes requirements for the use of independent weight scales to verify quantities of demolition materials, including but not limited to metals, ductile iron pipe, pipe fittings, pipe valves, concrete, asphalt pavement and other recoverable or disposable debris.

7.2 CERTIFIED SCALE REQUIREMENT
Facilities without weight scales which comply with Sections 5 and 6 shall be weighed at a California Certified Public Scale.

7.2.1 The State certified commercial weight scale shall be certified under the authority of the California Department of Food and Agriculture (CDFA), Division of Measurement Standards (DMS).

7.2.2 Certification shall be current and verified by the County Sealer of Weights and Measures in the jurisdiction where the scale is located.

7.2.3 Weighing shall occur at a facility listed on the CDFA Public Scales Registry for Imperial County, California.

7.3 INSPECTION AND CALIBRATION

7.3.1 Scales shall be inspected and calibrated at least annually, or more frequently if required by local regulations.

7.3.2 The contractor shall ensure that the scale displays a valid certification seal or sticker indicating the most recent inspection date.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 16 of 21 ends

TECHNICAL SPECIFICATIONS

7.4 CALIFORNIA WEIGHMASTER CERTIFICATE REQUIREMENTS

7.4.1 The Contractor shall obtain California Weighmaster Certificates for each load of demolition material leaving the project site. The Weighmaster Certificates shall include the following:

7.4.1.1 Name and address of the scale facility

7.4.1.2 Date and time of weighing

7.4.1.3 Material type

7.4.1.4 Gross, tare and net weights

7.4.1.5 Certification identification number and seal reference

7.4.1.6 Weight tickets must be legible, original, and wet signed by the scale operator.

7.5 NON-COMPLIANT SCALES

7.5.1 Use of uncertified or expired scales shall result in rejection of weight documentation and withholding of payment or implementation of fines.

7.5.2 Failure to comply with weighmaster documentation requirements shall result in rejection of weight documentation and withholding of payment or implementation of fines.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 17 of 21 ends

TECHNICAL SPECIFICATIONS

8. ASBESTOS AND LEAD REQUIREMENTS

8.1 GENERAL

8.1.1 SUMMARY

8.1.1.1 This section specifies requirements for the identification, handling, removal, transportation, and disposal of asbestos-containing materials (ACM) and lead-based paint (LBP) or lead-containing materials (LCM) encountered during demolition activities.

8.1.1.2 Work shall comply with all applicable federal, state, and local regulations, including but not limited to:

8.1.1.2.1 Cal/OSHA Title 8, Section 1529 (Asbestos)

8.1.1.2.2 Cal/OSHA Title 8, Section 1532.1 (Lead)

8.1.1.2.3 EPA 40 CFR Part 745 (RRP Rule)

8.1.1.2.4 SCAQMD Rule 1403 (if applicable)

8.1.1.2.5 California Contractors State License Board (CSLB) licensing requirements.

8.1.1.2.6 Imperial County LEA and CalRecycle C & D debris handling requirements.

8.1.2 CONTRACTOR QUALIFICATIONS

8.1.2.1 Asbestos Abatement Qualifications:

8.1.2.1.1 Contractor shall possess a valid CSLB C-22, asbestos abatement license or an A, B, C-21 or C-23, as applicable, license with Asbestos Certification.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 18 of 21 ends

TECHNICAL SPECIFICATIONS

8.1.2.1.2 Contractor shall maintain current Cal/OSHA asbestos contractor registration.

8.1.2.2 Lead-Based Paint Disturbance:

8.1.2.2.1 Contractor shall possess a valid California Contractor State License Board license appropriate to the scope of work (C-33, C-21, A or B as applicable).

8.1.2.2.2 Contractor shall maintain EPA renovation, repair and painting firm certification and employ certified renovators.

8.1.2.2.3 Contractor shall comply with Cal/OSHA Lead Standard requirements.

8.1.2.3 Hazardous Substance Removal:

8.1.2.3.1 Contractor shall possess CSLB HAZ Certification when required by the nature of the materials or waste streams.

8.1.3 ITEMS TO BE INCLUDED WITH BID FORMS OR AS SUBMITTAL

DOCUMENTS

8.1.3.1 Licensing and Registration

8.1.3.1.1 Copies of CSLB C-22 license or CSLB A, B, C-21, C-33 license as appropriate with an Asbestos Certification. These items are to be listed on the bid forms by the contractor, subcontractor or subcontractor to a subcontractor performing the asbestos abatement work.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 19 of 21 ends

TECHNICAL SPECIFICATIONS

8.1.3.1.2 Cal/OSHA Asbestos Contractor Registration. To be included on the bid forms by the contractor, subcontractor or subcontractor to a subcontractor performing the asbestos abatement work.

8.1.3.1.3 EPA Renovation, Repair and Painting firm certification (lead removal). To be included on the bid forms by the contractor, subcontractor or subcontractor to a subcontractor performing the lead abatement work.

8.1.3.2 Work Plan

8.1.3.2.1 Site Specific Asbestos Work Plan including
engineering controls, containment, negative air and
containment equipment, PPE and disposal procedures. To be forwarded as a submittal document for review and approval.

8.1.3.2.2 Lead compliance program per Title 8, Section
1532.1 to include as a minimum:

8.1.3.2.2.1 Exposure assessment.

8.1.3.2.2.2 Respiratory protection.

8.1.3.2.2.3 Medical surveillance (if exposure triggers
are met).

8.1.3.2.2.4 A written lead compliance program.

To be forwarded as a submittal document for review and
approval.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 20 of 21 ends

TECHNICAL SPECIFICATIONS

8.1.3.3 AHERA/Cal/OSHA worker training certificates for construction personnel completing asbestos removal shall be provided as submittal documents.

8.1.3.4 Approved facilities for lead and asbestos disposal to be identified and forwarded as submittal documents.

8.1.3.5 Certified Renovator (Lead-Based Items) assigned to the project with approved certification shall be provided as a submittal document.

8.2 EXECUTION

8.2.1 ASBESTOS ABATEMENT

8.2.1.1 Perform all work in accordance with Cal OSHA Class I-IV requirements.

8.2.1.2 Remove, package, label and transport ACM to a permitted disposal facility.

8.2.1.3 Maintain daily air monitoring and clearance testing as required.

8.2.2 LEAD-BASED PAINT AND MATERIAL0 REMOVAL

8.2.2.1 Implement lead-safe work practices per EPA renovation, repair and painting rule.

8.2.2.2 Conduct exposure assessment and implement engineering controls per Cal/OSHA.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 21 of 21 ends

TECHNICAL SPECIFICATIONS

8.2.2.3 Collect, containerize, and dispose of lead waste in accordance with hazardous waste regulations, if applicable.

173.138 Selective Electrical Demolition
City of Imperial Wastewater Treatment Plant Demolition Project 02 41 26 - 1 SECTION 02 41 26

SELECTIVE ELECTRICAL DEMOLITION
PART 1 GENERAL

1.1 SUMMARY
A. Section Includes:

1. Removal of existing electrical equipment, wiring, and conduit in areas to be remodeled; removal of designated construction; dismantling, cutting and alterations for completion of the Work.

2. Disposal of materials.

3. Storage of removed materials.

4. Identification of utilities.

5. Salvaged items.

6. Protection of items to remain as indicated on Drawings.

7. Relocate existing equipment to accommodate construction.

B. Related Sections:

1. Section - Building Demolition: Demolition of utilities and other underground items related to the demolition of the building, submittals, pre-demolition meetings, sequencing, scheduling, and coordination under the supervision of the general contractor.

1.2 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of capped utilities, conduits and equipment abandoned in place, and any field changes or modifications.

1.3 SCHEDULING
A. Schedule work to coincide with demolition by the general contractor and other trades.

B. Cease operations immediately when structure appears to be in danger or suspected hazardous materials are discovered and notify Architect/Engineer. Do not resume operations until directed.

1.4 COORDINATION
A. Conduct demolition to minimize interference with adjacent and occupied building areas.

B. Coordinate demolition work with general contractor and owner.

C. Coordinate and sequence demolition so as not to cause shutdown of operation of surrounding areas.

D. Shut-down Periods:

1. Arrange timing of shut-down periods of in service panels with general contractor and Owner.

Do not shut down any utility without prior written approval.

2. Keep shut-down period to minimum or use intermittent period as directed by general contractor and Owner.
173.138 Selective Electrical Demolition
City of Imperial Wastewater Treatment Plant Demolition Project 02 41 26 - 2

3. Maintain life-safety systems in full operation in occupied facilities, or provide notice minimum 7 days in advance.

E. Identify salvage items in cooperation with Owner.

PART 2 EXECUTION

2.1 EXAMINATION
A. Verify wiring and equipment indicated to be demolished serve only abandoned facilities.

B. Verify termination points for demolished services.

2.2 PREPARATION
A. Erect, and maintain temporary safeguards, including barricades, and similar measures, for protection of the public, Owner, Contractor’s employees, and existing improvements to remain.

B. Temporary egress signage and emergency lighting.

2.3 DEMOLITION
A. Demolition Drawings are based on casual field observation and existing record documents.

Report discrepancies to Architect/Engineer before disturbing existing installation.

B. Coordinate with general contractor to remove abandoned equipment, conduit, and wire at buildings and structures scheduled for demolition. Cut conduit flush with walls and floors scheduled to remain.

C. Remove conduit, wire, boxes, and fastening devices to avoid any interference with new installation.

D. Disconnect electrical systems in walls, floors, and ceilings scheduled for removal.

E. Reconnect equipment being disturbed by renovation work and required for continue service to nearest available panel.

F. Disconnect or shut off service to areas where electrical work is to be removed. Remove electrical fixtures, equipment, and related switches, outlets, conduit and wiring which are not part of final project.

G. Install temporary wiring and connections to maintain existing systems in service during construction.

H. Perform work on energized equipment or circuits with experienced and trained personnel.

I. Remove, relocate, and extend existing installations to accommodate new construction. 173.138 Selective Electrical Demolition
City of Imperial Wastewater Treatment Plant Demolition Project 02 41 26 - 3 J. Repair adjacent construction and finishes damaged during demolition and extension work.

K. Remove exposed abandoned grounding and bonding components, fasteners and supports, and electrical identification components. Cut embedded support elements flush with walls and floors.

L. Clean and repair existing equipment to remain or to be reinstalled.

M. Protect and retain power to existing active equipment remaining.

N. Cap abandoned empty conduit at both ends.

2.4 EXISTING PANELBOARDS
A. Ring out circuits in existing panel affected by the Work. Where additional circuits are needed, reuse circuits available for reuse. Install new breakers.

B. Tag unused circuits as spare.

C. Where existing circuits are indicated to be reused, use sensing measuring devices to verify circuits feeding Project area or are not in use.

D. Remove existing wire no longer in use from panel to equipment.

E. Provide new updated directories where more than three circuits have been modified or rewired.

2.5 SALVAGE ITEMS
A. Remove and protect items indicated on Drawings to be salvaged and turn over to Owner.

B. Items of salvageable value may be removed as work progresses. Transport salvaged items from site as they are removed.

2.6 REUSABLE ELECTRICAL EQUIPMENT
A. Carefully remove equipment, materials, or fixtures which are to be reused.

B. Disconnect, remove, or relocate existing electrical material and equipment interfering with new installation.

2.7 CLEANING
A. Remove demolished materials as work progresses. Legally dispose.

B. Keep workplace neat.

END OF SECTION
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 00 - 1
Basic Electrical Requirements
SECTION 26 05 00

BASIC ELECTRICAL REQUIREMENTS
PART 1 GENERAL

1.01 SCOPE OF WORK
A. Basic Electrical Requirements specifically applicable to Division 26 Sections.

B. All labor, materials, equipment and services necessary to furnish and install complete electrical systems and related items of work as indicated to Drawings or specified herein.

C. The work in general shall consist of, but is not limited to the following:

1. Coordination with the general contractor and utility companies to perform selective electrical demolition work in conjunction with the overall demolition work as indicated on the drawings.

2. Outdoor underground electrical feeder, underground trenching and conduit, and accessories as indicated.

3. Modifications to existing distribution panel, conduit, wiring, etc., for all new electrical distribution as indicated.

4. Interior lighting fixtures with lamps and lighting accessories as indicated D. Drawings are diagrammatic. Refer to Mechanical and Architectural Drawings and specifications for exact locations for equipment furnished by others.

1.02 WORK SEQUENCE
A. Install work as scheduled to accommodate Owner's occupancy requirements. During the construction period coordinate electrical schedule and operations with other trades, Owner and/or Engineer.

1.03 REFERENCES AND REGULATORY REQUIREMENTS
A. Conform to applicable International Building Code.

B. Workmanship and material of electrical work shall comply with or exceed applicable provisions of the following (most recent additions including addenda and errata):

1. All Local Codes and Ordinances.

2. California/National Electrical Code (NEC) (NFPA 70).

3. California/International Building Code (IBC).

4. California/International Existing Building Code (IEBC).

5. California/International Fire Code (IFC).

6. NFPA 72, Fire Alarm Code.

7. National Bureau of Fire Underwriters (NBFU).

8. American National Standards Institute (ANSI).

9. American Society for Testing and Materials (ASTM).

10. National Electrical Manufacturers Association (NEMA).

11. Standards and requirements for serving utilities.

12. Standards of Installation (NECA).

13. Safety and Health Standards (OSHA).

14. Americans with Disabilities Act (ADA).

15. Factory Mutual (FM).
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 00 - 2
Basic Electrical Requirements

1.04 SUBMITTALS
A. Submit shop drawings and product data grouped to include complete submittals of related systems, products, and accessories in a single submittal. Partial submittals will not be reviewed.

B. Mark dimensions and values in units to match those specified.

1.05 PROJECT/SITE CONDITIONS
A. Install Work in locations shown on Drawings, unless prevented by Project conditions.

B. Prepare drawings showing proposed rearrangement of Work to meet Project conditions, including changes to Work specified in other Sections. Obtain permission of Owner and/or Architect before proceeding.

C. SITE WORK: Contractor shall employ an independent locating service to locate and verify all existing services, whether specifically shown on the drawings or not. Location of services shall be recorded on record documents. No trenching or excavation shall commence until locations are verified. The Owner shall be notified in writing prior to any trenching requiring a utility shutdown. Any services interrupted by trenching or excavating shall be repaired by the contractor with no additional cost to the Owner. Existing services not specifically indicated on the drawings to be relocated, which interfere with building components, shall be brought to the Architect's immediate attention. Prepare drawings showing proposed re-routing, area(s) affected, and length of interruption(s).

1.06 SEQUENCING AND SCHEDULING
A. Construct Work in sequence under provisions of the General Specifications.

END OF SECTION 26 05 00
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 1
Low Voltage Electrical Power
Conductors and Cables
SECTION 26 05 19

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes building wire and cable; and wiring connectors and connections.

B. Related Sections:

1. Section 26 05 53 - Identification for Electrical Systems: Product requirements for wire identification.

1.02 REFERENCES
A. International Electrical Testing Association:

1. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

B. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

2. NFPA 262 - Standard Method of Test for Flame Travel and Smoke of Wires and Cables for Use in Air-Handling Spaces.

1.03 SYSTEM DESCRIPTION
A. Product Requirements: Provide products as follows:

1. Solid conductor for feeders and branch circuits 10 AWG and smaller.

2. Stranded conductors for control circuits.

3. Conductor not smaller than 12 AWG for power and lighting circuits.

4. Conductor not smaller than 16 AWG for control circuits.

5. 10 AWG conductors for 20 ampere, 120 volt branch circuits longer than 75 feet.

B. Wiring Methods: Provide the following wiring methods:

1. Concealed Dry Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

2. Exposed Dry Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

3. Above Accessible Ceilings: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

4. Wet or Damp Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

5. Exterior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

6. Underground Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

7. Use wiring and methods indicated on drawings.

1.04 DESIGN REQUIREMENTS
A. Conductor sizes are based on copper.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 2
Low Voltage Electrical Power
Conductors and Cables

1.05 SUBMITTALS
A. Product Data: Submit for building wire and each cable assembly type.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of components and circuits.

1.07 QUALITY ASSURANCE
A. Provide wiring materials located in plenums with peak optical density not greater than 0.5, average optical density not greater than 0.15, and flame spread not greater than 5 feet (1.5 m) when tested in accordance with NFPA 262.

1.08 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

1.09 FIELD MEASUREMENTS
A. Verify field measurements are as indicated on Drawings.

1.10 COORDINATION
A. Where wire and cable destination is indicated and routing is not shown, determine routing and lengths required.

B. Wire and cable routing indicated is approximate unless dimensioned.

PART 2 - PRODUCTS

2.01 BUILDING WIRE
A. Manufacturers:

1. Okonite.

2. General Cable Co.

3. Southwire.

4. American.

5. Substitutions: Under provisions of General Specifications.

B. Product Description: Single conductor insulated wire.

C. Conductor: Copper.

D. Insulation: 600 volt rating; material rated 90 degrees C.

2.02 WIRING CONNECTORS
A. Split Bolt Connectors:

1. Kearney.

2. Teledyne Penn-Union.

B. Solderless Pressure Connectors:
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 3
Low Voltage Electrical Power
Conductors and Cables

1. Cadweld.

2. Burndy.

C. Compression Connectors:

1. Kearney.

2. Teledyne- Penn-Union.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify interior of building has been protected from weather.

B. Verify mechanical work likely to damage wire and cable has been completed.

C. Verify raceway installation is complete and supported.

3.02 PREPARATION
A. Completely and thoroughly swab raceway before installing wire.

3.03 INSTALLATION
A. Route wire and cable to meet Project conditions.

B. Neatly train and lace wiring inside boxes, equipment, and panelboards.

C. Identify and color code wire and cable under provisions of Section 26 05 53. Identify each conductor with its circuit number or other designation indicated.

D. Special Techniques--Building Wire in Raceway:

1. Pull conductors into raceway at same time.

2. Install building wire 4 AWG and larger with pulling equipment.

E. Special Techniques - Cable:

1. Protect exposed cable from damage.

2. Support cables above accessible ceiling, using spring metal clips or cable ties to support cables from structure. Do not rest cable on ceiling panels.

3. Use suitable cable fittings and connectors.

F. Special Techniques - Wiring Connections:

1. Clean conductor surfaces before installing lugs and connectors.

2. Make splices, taps, and terminations to carry full ampacity of conductors with no perceptible temperature rise.

3. Tape uninsulated conductors and connectors with electrical tape to 150 percent of insulation rating of conductor.

4. Install split bolt connectors for copper conductor splices and taps, 6 AWG and larger.

5. Install solderless pressure connectors with insulating covers for copper conductor splices and taps, 8 AWG and smaller.

G. Install solid conductor for feeders and branch circuits 10 AWG and smaller.

3.04 WIRE COLOR
A. General:

1. For wire sizes 10 AWG and smaller, install wire colors in accordance with the following:
a. Black and red for single phase circuits at 120/240 volts. b. Black, red, and blue for circuits at 120/240 volts single or three phase. c. Match existing.

2. For wire sizes 8 AWG and larger, identify wire with colored tape at terminals, splices and boxes. Colors are as follows:
a. Black and red for single phase circuits at 120/240 volts. b. Black, red, and blue for circuits at 120/240 volts single or three phase. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 4
Low Voltage Electrical Power
Conductors and Cables
c. Match existing.

B. Neutral Conductors: White. When two or more neutrals are located in one conduit, individually identify each with proper circuit number.

C. Branch Circuit Conductors: Install three or four wire home runs with each phase uniquely color coded.

D. Feeder Circuit Conductors: Uniquely color code each phase.

E. Ground Conductors:

1. For 6 AWG and smaller: Green.

2. For 4 AWG and larger: Identify with green tape at both ends and visible points including junction boxes.

3.05 FIELD QUALITY CONTROL
A. Inspect and test in accordance with NETA ATS, except Section 4.

B. Perform inspections and tests listed in NETA ATS, Section 7.3.1.

END OF SECTION 26 05 19
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 1
Grounding and Bonding
for Electrical Systems
SECTION 26 05 26

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Rod electrodes.

2. Wire.

3. Mechanical connectors.

4. Exothermic connections.

1.02 REFERENCES
A. Institute of Electrical and Electronics Engineers:

1. IEEE 142 - Recommended Practice for Grounding of Industrial and Commercial Power Systems.

2. IEEE 1100 - Recommended Practice for Powering and Grounding Electronic Equipment.

B. International Electrical Testing Association:

1. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

C. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

1.03 SYSTEM DESCRIPTION
A. Grounding systems use the following elements as grounding electrodes:

1. Metal underground water pipe.

2. Metal building frame.

3. Concrete-encased electrode.

4. Rod electrode.

1.04 PERFORMANCE REQUIREMENTS
A. Grounding System Resistance: 25 ohms maximum.

1.05 SUBMITTALS
A. Product Data: Submit data on grounding electrodes and connections.

B. Test Reports: Indicate overall resistance to ground and resistance of each electrode.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of components and grounding electrodes. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 2
Grounding and Bonding
for Electrical Systems

1.07 QUALITY ASSURANCE
A. Provide grounding materials conforming to requirements of NEC, IEEE 142, and UL labeled.

1.08 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing Products specified in this section with minimum three years documented experience.

1.09 DELIVERY, STORAGE, AND HANDLING
A. Accept materials on site in original factory packaging, labeled with manufacturer's identification.

B. Protect from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original packaging.

C. Do not deliver items to project before time of installation. Limit shipment of bulk and multiple-use materials to quantities needed for immediate installation.

PART 2 - PRODUCTS

2.01 ROD ELECTRODES
A. Manufacturers:

1. Apache Grounding/Erico Inc.

2. Copperweld, Inc.

3. Erico, Inc.

4. O-Z Gedney Co.

B. Product Description:

1. Material: Copper.

2. Diameter: 3/4 inch.

C. Length: 10 feet.

2.02 WIRE
A. Material: Stranded copper.

B. Foundation Electrodes: 4 AWG.

C. Equipment Grounding Conductor: Copper conductor insulated.

D. Bonding Conductor: Copper conductor bare or insulated.

2.03 MECHANICAL CONNECTORS
A. Manufacturers:

1. Apache Grounding/Erico Inc.

2. Copperweld, Inc.

3. ILSCO Corporation.

4. O-Z Gedney Co.

5. Thomas & Betts, Electrical.

B. Description: Bronze connectors, suitable for grounding and bonding applications, in configurations required for particular installation.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 3
Grounding and Bonding
for Electrical Systems

2.04 EXOTHERMIC CONNECTIONS
A. Manufacturers:

1. Cadweld.

2. Copperweld, Inc.

3. Thermoweld.

B. Product Description: Exothermic materials, accessories, and tools for preparing and making permanent field connections between grounding system components.

PART 3 - EXECUTION

3.01 PREPARATION
A. Remove paint, rust, mill oils, and surface contaminants at connection points.

3.02 INSTALLATION
A. Install in accordance with IEEE and manufacturer instructions.

B. Install rod electrodes at locations as indicated on Drawings. Install additional rod electrodes to achieve specified resistance to ground.

C. Install grounding and bonding conductors concealed from view.

D. Equipment Grounding Conductor: Install separate, insulated conductor within each feeder and branch circuit raceway. Terminate each end on suitable lug, bus, or bushing.

E. Install 4 AWG bare copper wire in foundation footing as indicated on Drawings or install grounding electrode conductor and connect to reinforcing steel in foundation footing as indicated on Drawings.

F. Bond together metal siding not attached to grounded structure; bond to ground.

G. Equipment Grounding Conductor: Install separate, insulated conductor within each feeder and branch circuit raceway. Terminate each end on suitable lug, bus, or bushing.

H. Permanently ground entire light and power system in accordance with NEC, including service equipment, distribution panels, lighting panelboards, switch and starter enclosures, motor frames, grounding type receptacles, and other exposed non-current carrying metal parts of electrical equipment.

I. Accomplish grounding of electrical system by using insulated grounding conductor installed with feeders and branch circuit conductors in conduits. Size grounding conductors in accordance with NEC. Install from grounding bus of serving panel to ground bus of served panel, grounding screw of receptacles, lighting fixture housing, light switch outlet boxes or metal enclosures of service equipment. Ground conduits by means of grounding bushings on terminations at panelboards with installed number 12 conductor to grounding bus.

J. Grounding electrical system using continuous metal raceway system enclosing circuit conductors in accordance with NEC.

K. Permanently attach equipment and grounding conductors prior to energizing equipment.

3.03 FIELD QUALITY CONTROL
A. Inspect and test in accordance with NETA ATS, except Section 4.

B. Grounding and Bonding: Perform inspections and tests listed in NETA ATS, Section 7.13.

C. Perform ground resistance testing in accordance with IEEE 142.

D. Perform continuity testing in accordance with IEEE 142.

E. When improper grounding is found on receptacles, check receptacles in entire project and correct. Perform retest.

END OF SECTION 26 05 26
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 1
Hangers and Supports
for Electrical Systems
SECTION 26 05 29

FIRESTOPPING, HANGERS, AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Conduit supports.

2. Formed steel channel.

3. Spring steel clips.

4. Sleeves.

5. Mechanical sleeve seals.

6. Firestopping relating to electrical work.

7. Firestopping accessories.

8. Equipment bases and supports.

1.02 REFERENCES
A. ASTM International:

1. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials.

2. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials.

3. ASTM E814 - Standard Test Method for Fire Tests of Through-Penetration Fire Stops.

4. ASTM E1966 - Standard Test Method for Fire-Resistive Joint Systems.

B. FM Global:

1. FM - Approval Guide, A Guide to Equipment, Materials & Services Approved By Factory Mutual Research For Property Conservation.

C. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

D. Underwriters Laboratories Inc.:

1. UL 263 - Fire Tests of Building Construction and Materials.

2. UL 723 - Tests for Surface Burning Characteristics of Building Materials.

3. UL 1479 - Fire Tests of Through-Penetration Firestops.

4. UL 2079 - Tests for Fire Resistance of Building Joint Systems.

5. UL - Fire Resistance Directory.

1.03 DEFINITIONS
A. Firestopping (Through-Penetration Protection System): Sealing or stuffing material or assembly placed in spaces between and penetrations through building materials to arrest movement of fire, smoke, heat, and hot gases through fire rated construction.

1.04 SYSTEM DESCRIPTION
A. Firestopping Materials: ASTM E814 and UL 1479 to achieve fire ratings as noted on Drawings for adjacent construction.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 2
Hangers and Supports
for Electrical Systems

1.05 PERFORMANCE REQUIREMENTS
A. Firestopping: Conform to applicable code for fire resistance ratings and surface burning characteristics.

1.06 SUBMITTALS
A. Product Data:

1. Hangers and Supports: Submit manufacturers catalog data including load capacity.

2. Firestopping: Submit data on product characteristics, performance and limitation criteria.

B. Firestopping Schedule: Submit schedule of opening locations and sizes, penetrating items, and required listed design numbers to seal openings to maintain fire resistance rating of adjacent assembly.

C. Design Data: Indicate load carrying capacity of hangers and supports.

D. Manufacturer's Installation Instructions:

1. Hangers and Supports: Submit special procedures and assembly of components.

2. Firestopping: Submit preparation and installation instructions.

E. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

1.07 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing Products specified in this section with minimum three years documented experience.

B. Installer: Company specializing in performing work of this section with minimum three years documented experience.

1.08 DELIVERY, STORAGE, AND HANDLING
A. Accept materials on site in original factory packaging, labeled with manufacturer's identification.

B. Protect from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original packaging.

1.09 ENVIRONMENTAL REQUIREMENTS
A. Do not apply firestopping materials when temperature of substrate material and ambient air is below 60 degrees F. Maintain this minimum temperature before, during, and for minimum 3 days after installation of firestopping materials.

PART 2 - PRODUCTS

2.01 CONDUIT SUPPORTS
A. Manufacturers:

1. Allied Tube & Conduit Corp.

2. Electroline Manufacturing Company.

3. O-Z Gedney Co.

4. Substitutions: Under provisions of General Specifications.

B. Hanger Rods: Threaded high tensile strength galvanized carbon steel with free running threads.

C. Beam Clamps: Malleable Iron, with tapered hole in base and back to accept either bolt or hanger rod. Set screw: hardened steel.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 3
Hangers and Supports
for Electrical Systems
D. Conduit clamps for trapeze hangers: Galvanized steel, notched to fit trapeze with single bolt to tighten.

E. Conduit clamps - general purpose: One hole malleable iron for surface mounted conduits.

F. Cable Ties: High strength nylon temperature rated to 185 degrees F. Self locking.

2.02 FORMED STEEL CHANNEL
A. Manufacturers:

1. Unistrut Corp.

2. Allied Tube & Conduit Corp.

3. B-Line Systems.

4. Midland Ross Corporation, Electrical Products Division.

5. Substitutions: Under provisions of General Specifications.

B. Product Description: Galvanized 12 gage thick steel. With holes 1-1/2 inches on center.

2.03 SPRING STEEL CLIPS
A. Manufacturers:

1. O-Z/Gedney.

2. Spring City Electrical Mfg..

3. Erico Products.

4. Substitutions: Under provisions of General Specifications B. Product Description: Mounting hole and screw closure.

2.04 FIRESTOPPING
A. Manufacturers:

1. Dow Corning Corp..

2. Fire Trak Corp.

3. Hilti Corp.

4. International Protective Coating Corp.

5. 3M fire Protection Products.

6. The RectorSeal Corporation Bio Fireshield.

7. Substitutions: Under provisions of General Specifications B. Product Description: Different types of products by multiple manufacturers are acceptable as required to meet specified system description and performance requirements; provide only one type for each similar application.

1. Silicone Firestopping Elastomeric Firestopping: Single or multiple component silicone elastomeric compound and compatible silicone sealant.

2. Foam Firestopping Compounds: Single or multiple component foam compound.

3. Formulated Firestopping Compound of Incombustible Fibers: Formulated compound mixed with incombustible non-asbestos fibers.

4. Fiber Stuffing and Sealant Firestopping: Composite of mineral fiber stuffing insulation with silicone elastomer for smoke stopping.

5. Mechanical Firestopping Device with Fillers: Mechanical device with incombustible fillers and silicone elastomer, covered with sheet stainless steel jacket, joined with collars, penetration sealed with flanged stops.

6. Intumescent Firestopping: Intumescent putty compound which expands on exposure to surface heat gain.

7. Firestop Pillows: Formed mineral fiber pillows.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 4
Hangers and Supports
for Electrical Systems

2.05 FIRESTOPPING ACCESSORIES
A. Primer: Type recommended by firestopping manufacturer for specific substrate surfaces and suitable for required fire ratings.

B. Installation Accessories: Provide clips, collars, fasteners, temporary stops or dams, and other devices required to position and retain materials in place.

C. General:

1. Furnish UL listed products.

2. Select products with rating not less than rating of wall or floor being penetrated.

D. Non-Rated Surfaces:

1. Stamped steel, chrome plated, hinged, split ring escutcheons or floor plates or ceiling plates for covering openings in occupied areas where conduit is exposed.

2. For exterior wall openings below grade, furnish modular mechanical type seal consisting of interlocking synthetic rubber links shaped to continuously fill annular space between conduit and cored opening or water-stop type wall sleeve.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify openings are ready to receive firestopping.

3.02 PREPARATION
A. Clean substrate surfaces of dirt, dust, grease, oil, loose material, or other matter affecting bond of firestopping material.

B. Remove incompatible materials affecting bond.

C. Install backing or damming materials to arrest liquid material leakage.

D. Obtain permission from Architect/Engineer before using powder-actuated anchors.

E. Obtain permission from Architect/Engineer before drilling or cutting structural members.

3.03 INSTALLATION - HANGERS AND SUPPORTS
A. Anchors and Fasteners:

1. Concrete Structural Elements: Provide precast inserts, expansion anchors, powder actuated anchors and preset inserts.

2. Steel Structural Elements: Provide beam clamps, spring steel clips, steel ramset fasteners, and welded fasteners.

3. Concrete Surfaces: Provide self-drilling anchors and expansion anchors.

4. Hollow Masonry, Plaster, and Gypsum Board Partitions: Provide toggle bolts and hollow wall fasteners.

5. Solid Masonry Walls: Provide expansion anchors and preset inserts.

6. Sheet Metal: Provide sheet metal screws.

7. Wood Elements: Provide wood screws.

B. Inserts:

1. Install inserts for placement in concrete forms.

2. Install inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams.

3. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.

4. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.

5. Where inserts are omitted, drill through concrete slab from below and provide throughbolt with recessed square steel plate and nut above slab. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 5
Hangers and Supports
for Electrical Systems
C. Install conduit and raceway support and spacing in accordance with NEC.

D. Do not fasten supports to pipes, ducts, mechanical equipment, or conduit.

E. Install multiple conduit runs on common hangers.

F. Supports:

1. Fabricate supports from structural steel or formed steel channel. Install hexagon head bolts to present neat appearance with adequate strength and rigidity. Install spring lock washers under nuts.

2. Install surface mounted cabinets and panelboards with minimum of four anchors.

3. In wet and damp locations install steel channel supports to stand cabinets and panelboards 1 inch off wall.

3.04 INSTALLATION – FIRESTOPPING
A. Install material at fire rated construction perimeters and openings containing penetrating sleeves, piping, ductwork, conduit and other items, requiring firestopping.

B. Apply primer where recommended by manufacturer for type of firestopping material and substrate involved, and as required for compliance with required fire ratings.

C. Apply firestopping material in sufficient thickness to achieve required fire and smoke rating, to uniform density and texture.

D. Fire Rated Surface:

1. Seal opening at floor, wall, partition, ceiling, and roof as follows:
a. Install sleeve through opening and extending beyond minimum of 1 inch on both sides of building element.
b. Size sleeve allowing minimum of 1 inch void between sleeve and building element. c. Pack void with backing material.
d. Seal ends of sleeve with UL listed fire resistive silicone compound to meet fire rating of structure penetrated.

2. Where cable tray, conduit, and wireway penetrates fire rated surface, install firestopping product in accordance with manufacturer's instructions.

E. Non-Rated Surfaces:

1. Seal opening through non-fire rated wall, partition, floor, ceiling, and roof opening as follows:
a. Install sleeve through opening and extending beyond minimum of 1 inch on both sides of building element.
b. Size sleeve allowing minimum of 1 inch void between sleeve and building element. c. Install type of firestopping material recommended by manufacturer.

2. Install escutcheons, floor plates or ceiling plates where conduit, penetrates non-fire rated surfaces in occupied spaces. Occupied spaces include rooms with finished ceilings and where penetration occurs below finished ceiling.

3. Exterior wall openings below grade: Assemble rubber links of mechanical seal to size of conduit and tighten in place, in accordance with manufacturer's instructions.

3.05 FIELD QUALITY CONTROL
A. Inspect installed firestopping for compliance with specifications and submitted schedule.

3.06 CLEANING AND PROTECTION OF FINISHED WORK
A. Clean adjacent surfaces of firestopping materials.

B. Protect adjacent surfaces from damage by material installation.

END OF SECTION 26 05 29
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 1
Raceways and Boxes
for Electrical Systems
SECTION 26 05 33

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes conduit and tubing, outlet boxes, and junction boxes.

1.02 REFERENCES
A. American National Standards Institute:

1. ANSI C80.1 - Rigid Steel Conduit, Zinc Coated.

2. ANSI C80.3 - Specification for Electrical Metallic Tubing, Zinc Coated.

B. National Electrical Manufacturers Association:

1. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).

2. NEMA FB 1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit and Cable Assemblies.

3. NEMA OS 1 - Sheet Steel Outlet Boxes, Device Boxes, Covers, and Box Supports.

4. NEMA OS 2 - Nonmetallic Outlet Boxes, Device Boxes, Covers, and Box Supports.

5. NEMA RN 1 - Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit.

6. NEMA TC 2 - Electrical Polyvinyl Chloride (PVC) Tubing and Conduit.

7. NEMA TC 3 - PVC Fittings for Use with Rigid PVC Conduit and Tubing.

1.03 SYSTEM DESCRIPTION
A. Raceway and boxes located as indicated on Drawings, and at other locations required for splices, taps, wire pulling, equipment connections, and compliance with regulatory requirements.

Raceway and boxes are shown in approximate locations unless dimensioned. Provide raceway to complete wiring system.

B. Outdoor Locations, Above Grade: Use rigid steel, intermediate metal conduit, and electrical metallic tubing. Provide cast metal or nonmetallic outlet, pull, and junction boxes.

C. Wet and Damp Locations: Provide galvanized rigid steel conduit, intermediate metal conduit and electrical metallic tubing. Provide cast metal or nonmetallic outlet, junction, and pull boxes.

Provide flush mounting outlet box in finished areas.

D. Concealed Dry Locations: Provide rigid steel, intermediate metal conduit, electrical and metallic tubing. Provide sheet-metal boxes. Provide flush mounting outlet box in finished areas. Provide hinged enclosure for large pull boxes.

E. Exposed Dry Locations: Use rigid steel conduit to 8 feet above flush floor or to first junction box.

Use rigid steel conduit, intermediate metal conduit or electrical metallic tubing at other locations.

Provide sheet-metal boxes. Provide flush mounting outlet box in finished areas. Provide hinged enclosure for large pull boxes.

1.04 DESIGN REQUIREMENTS
A. Minimum Raceway Size:

1. Above floor: 1/2 inch unless otherwise specified.

2. Underground: 3/4 inch unless otherwise specified.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 2
Raceways and Boxes
for Electrical Systems

1.05 SUBMITTALS
A. Product Data: Submit for the following:

1. Flexible metal conduit.

2. Liquidtight flexible metal conduit.

3. Nonmetallic conduit.

4. Raceway fittings.

5. Conduit bodies.

6. Surface raceway.

7. Wireway.

8. Pull and junction boxes.

B. Manufacturer's Installation Instructions: Submit application conditions and limitations of use stipulated by Product testing agency specified under Regulatory Requirements. Include instructions for storage, handling, protection, examination, preparation, and installation of Product.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents:

1. Record actual routing of conduits larger than 2 inch trade size.

2. Record actual locations and mounting heights of outlet, pull, and junction boxes.

1.07 DELIVERY, STORAGE, AND HANDLING
A. Protect conduit from corrosion and entrance of debris by storing above grade. Provide appropriate covering.

B. Protect PVC conduit from sunlight.

1.08 COORDINATION
A. Coordinate installation of outlet boxes for equipment connected under Section 26 05 03.

B. Coordinate mounting heights, orientation and locations of outlets mounted above counters, benches, and backsplashes.

PART 2 - PRODUCTS

2.01 METAL CONDUIT
A. Manufacturers:

1. Allied Tube and Conduit.

2. Hubbell Inc.

3. AFC.

4. Substitutions: Under provisions of General Specifications.

B. Rigid Steel Conduit: ANSI C80.1.

C. Intermediate Metal Conduit (IMC): Rigid steel.

D. Fittings and Conduit Bodies: NEMA FB 1; material to match conduit.

2.02 PVC COATED METAL CONDUIT
A. Manufacturers:

1. Occidental Coating.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 3
Raceways and Boxes
for Electrical Systems

2. P.C.D.

3. Robroy Industries.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: NEMA RN 1; rigid steel conduit with external PVC coating, 40 mil thick.

C. Fittings and Conduit Bodies: NEMA FB 1; steel fittings with external PVC coating to match conduit.

2.03 FLEXIBLE METAL CONDUIT
A. Manufacturers:

1. Acme International.

2. Electri-Flex Co.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications B. Product Description: Interlocked steel or aluminum construction.

C. Fittings: NEMA FB 1.

2.04 LIQUIDTIGHT FLEXIBLE METAL CONDUIT
A. Manufacturers:

1. Acme International.

2. Electri-Flex Co.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: Interlocked steel or aluminum construction with PVC jacket.

C. Fittings: NEMA FB 1.

2.05 ELECTRICAL METALLIC TUBING (EMT)
A. Manufacturers:

1. Allied Tube and Conduit.

2. AFC.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: ANSI C80.3; galvanized tubing.

C. Fittings and Conduit Bodies: NEMA FB 1; steel or malleable iron, compression type.

2.06 NONMETALLIC CONDUIT
A. Manufacturers:

1. Carlon.

2. RACO.

3. Can-Tex.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: NEMA TC 2; Schedule 40 or 80 PVC.

C. Fittings and Conduit Bodies: NEMA TC 3.

2.07 WIREWAY
A. Manufacturers:

1. Circle AW.

2. Thomas & Betts Corp.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 4
Raceways and Boxes
for Electrical Systems

3. Substitutions: Under provisions of General Specifications.

B. Product Description: General purpose or Raintight type wireway as required.

C. Knockouts: Manufacturer's standard.

D. Size: Dimensions as indicated on Drawings or as required by the NEC for the intended application.

E. Cover: Hinged or screw cover as indicated or as required for the intended applications. Provide with full gaskets when requried.

F. Connector: Flanged.

G. Fittings: Lay-in type.

H. Finish: Rust inhibiting primer coating with manufacturer’s standard gray enamel finish.

2.08 OUTLET BOXES
A. Sheet Metal Outlet Boxes: NEMA OS 1, galvanized steel.

1. Luminaire and Equipment Supporting Boxes: Rated for weight of equipment supported; furnish 1/2 inch male fixture studs where required.

2. Concrete Ceiling Boxes: Concrete type.

B. Nonmetallic Outlet Boxes: NEMA OS 2.

C. Cast Boxes: NEMA FB 1, Type FD, cast feralloy. Furnish gasketed cover by box manufacturer.

Furnish threaded hubs.

D. Wall Plates for Finished Areas: As specified in Section 26 27 26.

E. Wall Plates for Unfinished Areas: Furnish gasketed cover.

2.09 SMALL PULL AND JUNCTION BOXES
A. Sheet Metal Boxes: NEMA OS 1, galvanized steel.

B. Hinged Enclosures: As specified.

C. Surface Mounted Cast Metal Box: NEMA 250, Type 4; flat-flanged, surface mounted junction box:

1. Material: Galvanized cast iron or aluminum.

2. Cover: Furnish with ground flange, neoprene gasket, and stainless steel cover screws.

D. In-Ground Cast Metal Box: NEMA 250, Type 6, galvanized cast iron, flanged, recessed cover box for flush mounting. Nonskid cover with neoprene gasket and stainless steel cover screws.

Cover Legend: "ELECTRIC" or as indicated.

E. Fiberglass or Concrete Composite Handholes: Die-molded, glass-fiber or concrete composite hand holes. Cable Entrance: Pre-cut 6 inch x 6 inch cable entrance at center bottom of each side. Cover: Glass-fiber or concrete composite, weatherproof cover with nonskid finish. Cover Legend: "ELECTRIC" or as indicated.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify outlet locations and routing and termination locations of raceway prior to rough-in.

3.02 INSTALLATION
A. Ground and bond raceway and boxes in accordance with Section 26 05 26.

B. Fasten raceway and box supports to structure and finishes in accordance with Section 26 05 29.

C. Identify raceway and boxes in accordance with Section 26 05 53.

D. Arrange raceway and boxes to maintain headroom and present neat appearance. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 5
Raceways and Boxes
for Electrical Systems

3.03 INSTALLATION - RACEWAY
A. Install conduit in accordance with NECA "Standard of Installation”.

B. Raceway routing is shown in approximate locations unless dimensioned. Route to complete wiring system.

C. Arrange raceway supports to prevent misalignment during wiring installation.

D. Support raceway using coated steel or malleable iron straps, lay-in adjustable hangers, clevis hangers, and split hangers.

E. Group related raceway; support using conduit rack. Construct rack using steel channel specified in Section 16070; provide space on each for 25 percent additional raceways.

F. Do not support raceway with wire or perforated pipe straps. Remove wire used for temporary supports
G. Do not attach raceway to ceiling support wires or other piping systems.

H. Construct wireway supports from steel channel specified in Section 26 05 29.

I. Route exposed raceway parallel and perpendicular to walls.

J. Route raceway installed above accessible ceilings parallel and perpendicular to walls.

K. Maintain clearance between raceway and piping for maintenance purposes.

L. Maintain 12 inch clearance between raceway and surfaces with temperatures exceeding 104 degrees F.

M. Cut conduit square using saw or pipe cutter; de-burr cut ends.

N. Bring conduit to shoulder of fittings; fasten securely.

O. Join nonmetallic conduit using cement as recommended by manufacturer. Wipe nonmetallic conduit dry and clean before joining. Apply full even coat of cement to entire area inserted in fitting. Allow joint to cure for minimum 20 minutes.

P. Install conduit hubs or sealing locknuts to fasten conduit to sheet metal boxes in damp and wet locations and to cast boxes.

Q. Install no more than equivalent of three 90 degree bends between boxes. Install conduit bodies to make sharp changes in direction, as around beams. Install hydraulic one-shot bender to fabricate or factory elbows for bends in metal conduit larger than 2 inch size.

R. Avoid moisture traps; install junction box with drain fitting at low points in conduit system.

S. Install fittings to accommodate expansion and deflection where raceway crosses seismic, control and expansion joints.

T. Install suitable pull string or cord in each empty raceway except sleeves and nipples.

U. Install suitable caps to protect installed conduit against entrance of dirt and moisture.

V. Surface Raceway: Install flat-head screws, clips, and straps to fasten raceway channel to surfaces; mount plumb and level. Install insulating bushings and inserts at connections to outlets and corner fittings.

W. Close ends and unused openings in wireway.

X. Exposed conduit floor penetrations shall be plastic coated steel or intermediate metal conduit or PVC wrapped (10 mil tape with 1/2 lap) galvanized rigid steel or intermediate metal conduit.

Concealed floor penetrations in a finished wall or chase may be thickwall Schedule 80 nonmetallic conduit. Extend non-metallic conduit to nearest junction box.

3.04 INSTALLATION - BOXES
A. Install wall mounted boxes at elevations to accommodate mounting heights as indicated on Drawings.

B. Adjust box location up to 5 feet prior to rough-in to accommodate intended purpose.

C. Orient boxes to accommodate wiring devices oriented as specified in Section 26 27 26.

D. Install pull boxes and junction boxes above accessible ceilings and in unfinished areas only.

E. In Accessible Ceiling Areas: Install outlet and junction boxes no more than 6 inches from ceiling access panel or from removable recessed luminaire.

F. Locate flush mounting box in masonry wall to require cutting of masonry unit corner only.

Coordinate masonry cutting to achieve neat opening.

G. Do not install flush mounting box back-to-back in walls; install with minimum 6 inches separation. Install with minimum 24 inches separation in acoustic rated walls. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 6
Raceways and Boxes
for Electrical Systems
H. Secure flush mounting box to interior wall and partition studs. Accurately position to allow for surface finish thickness.

I. Install stamped steel bridges to fasten flush mounting outlet box between studs.

J. Install flush mounting box without damaging wall insulation or reducing its effectiveness.

K. Install adjustable steel channel fasteners for hung ceiling outlet box.

L. Do not fasten boxes to ceiling support wires or other piping systems.

M. Support boxes independently of conduit.

N. Install gang box where more than one device is mounted together. Do not use sectional box.

O. Install gang box with plaster ring for single device outlets.

P. Set floor boxes level.

3.05 INTERFACE WITH OTHER PRODUCTS
A. Install conduit to preserve fire resistance rating of partitions and other elements, using materials and methods in accordance with General Specifications.

B. Route conduit through roof openings for piping and ductwork or through suitable roof jack with pitch pocket. Coordinate location with roofing installation specified in Specifications.

C. Locate outlet boxes to allow luminaires positioned as indicated on Drawings.

D. Align adjacent wall mounted outlet boxes for switches, thermostats, and similar devices.

3.06 ADJUSTING
A. Adjust flush-mounting outlets to make front flush with finished wall material.

B. Install knockout closures in unused openings in boxes.

3.07 CLEANING
A. Clean interior of boxes to remove dust, debris, and other material.

B. Clean exposed surfaces and restore finish.

END OF SECTION 26 05 33
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 1
Identification for Electrical Systems
SECTION 26 05 53

IDENTIFICATION FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes building wire and cable; metal clad cable; and wiring connectors and connections.

B. Section Includes:

1. Nameplates.

2. Labels.

3. Wire markers.

4. Conduit markers.

5. Stencils.

6. Underground Warning Tape.

7. Lockout Devices.

C. Related Sections:

1. Section - Paints and Coatings: Execution requirements for painting specified by this section.

1.02 SUBMITTALS
A. Product Data:

1. Submit manufacturer’s catalog literature for each product required.

2. Submit electrical identification schedule including list of wording, symbols, letter size, color coding, tag number, location, and function.

B. Samples:

1. Submit two tags, actual size.

2. Submit two labels, actual size.

C. Manufacturer's Installation Instructions: Indicate installation instructions, special procedures, and installation.

1.03 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of tagged devices; include tag numbers.

1.04 DELIVERY, STORAGE, AND HANDLING
A. Accept identification products on site in original containers. Inspect for damage.

B. Accept materials on site in original factory packaging, labeled with manufacturer's identification, including product density and thickness.

C. Protect insulation from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original wrapping.

1.05 ENVIRONMENTAL REQUIREMENTS
A. Install labels and nameplates only when ambient temperature and humidity conditions for adhesive are within range recommended by manufacturer.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 2
Identification for Electrical Systems

1.06 EXTRA MATERIALS
A. Furnish two containers of spray-on adhesive.

PART 2 - PRODUCTS

2.01 NAMEPLATES
A. Product Description: Laminated three-layer plastic with engraved white letters on black contrasting background color.

B. Letter Size:

1. 1/8 inch high letters for identifying individual equipment and loads.

2. 1/4 inch high letters for identifying grouped equipment and loads.

C. Minimum nameplate thickness: 1/8 inch.

2.02 LABELS
A. Labels: Embossed adhesive tape, with 3/16 inch white letters on black background.

2.03 WIRE MARKERS
A. Description: Cloth tape, split sleeve, or tubing type wire markers.

B. Legend:

1. Power and Lighting Circuits: Branch circuit or feeder number.

2. Control Circuits: Control wire number as indicated on shop drawings.

2.04 CONDUIT AND RACEWAY MARKERS
A. Description: Labels fastened with adhesive.

B. Color:

1. 480 Volt System: Black lettering on white background.

2. 208 or 240 Volt System: Black lettering on white background.

3. Fire Alarm System: Red lettering on white background.

4. Telephone System: Blue lettering on white background.

C. Legend:

1. Fire Alarm System: FIRE ALARM.

PART 3 - EXECUTION

3.01 PREPARATION
A. Degrease and clean surfaces to receive adhesive for identification materials.

3.02 INSTALLATION
A. Install identifying devices after completion of painting.

B. Nameplate Installation:

1. Install nameplate parallel to equipment lines.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 3
Identification for Electrical Systems

2. Install nameplate for each electrical distribution and control equipment enclosure with corrosive-resistant mechanical fasteners, or adhesive.

3. Install nameplates for each control panel and major control components located outside panel with corrosive-resistant mechanical fasteners, or adhesive.

4. Secure nameplate to equipment front using screws, rivets, or adhesive.

5. Secure nameplate to inside surface of door on recessed panelboard in finished locations.

6. Install nameplates for the following:
a. Switchboards.
b. Panelboards.
c. Service Disconnects.

C. Label Installation:

1. Install label parallel to equipment lines.

2. Install label for identification of individual control device stations.

3. Install labels for permanent adhesion and seal with clear lacquer.

D. Wire Marker Installation:

1. Install wire marker for each conductor at panelboard, pull boxes, outlet and junction boxes, and each load connection.

2. Mark data cabling at each end. Install additional marking at accessible locations along the cable run.

3. Install labels at data outlets identifying patch panel and port designation.

E. Conduit Marker Installation:

1. Install conduit marker for each conduit longer than 6 feet.

2. Conduit Marker Spacing: 20 feet on center.

END OF SECTION 26 05 53
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 1
Interior Lighting
SECTION 26 51 00

INTERIOR LIGHTING
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes interior luminaires, lamps, ballasts, and accessories.

B. Related Sections:

1. Section 26 05 26 - Grounding and Bonding for Electrical Systems.

2. Section 26 05 33 - Raceway and Boxes for Electrical Systems.

1.02 SUBMITTALS
A. Shop Drawings: Indicate dimensions and components for each luminaire not standard product of manufacturer.

B. Product Data: Submit manufacturer standard submittal data to include product data, dimensions, ratings, and performance data.

1.03 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

1.04 FIELD MEASUREMENTS
A. Verify field measurements prior to fabrication.

PART 2 - PRODUCTS

2.01 INTERIOR LUMINAIRES
A. Product Description: Complete interior luminaire assemblies, with features, options, and accessories as scheduled.

2.02 LED LIGHT FIXTURES
A. General:

1. LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified.

2. LED light fixtures shall be Reduction of Hazardous Substances (RoHS)-compliant.

3. LED drivers shall include the following features unless otherwise indicated:
a. Minimum efficiency: 85% at full load.
b. Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.) c. Input Voltage: 120 - 277V (±10%) at 60 Hz.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 2
Interior Lighting
d. Integral short circuit, open circuit, and overload protection. e. Power Factor: ≥ 0.95.
f. Total Harmonic Distortion: ≤ 20%.
g. Comply with FCC 47 CFR Part 15.
h. Manufacturer minimum 5-year standard warranty.

4. LED modules shall include the following features unless otherwise indicated:
a. Comply with IES LM-79 and LM-80 requirements.
b. Minimum CRI 80 and color temperature 3000˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE.
c. Minimum Rated Life: 50,000 hours per IES L70.
d. Light output lumens as indicated in the LIGHTING FIXTURE SCHEDULE.

PART 3 - EXECUTION

3.01 INSTALLATION
A. Install surface mounted luminaires plumb and adjust to align with building lines and with each other.

Secure to prevent movement.

B. Install wall-mounted luminaires at height as indicated on Drawings.

C. Install accessories furnished with each luminaire.

D. Connect luminaires to branch circuit outlets provided under Section 26 05 33 as indicated on Drawings.

E. Make wiring connections to branch circuit using building wire with insulation suitable for temperature conditions within luminaire.

F. Install specified lamps in each luminaire.

G. Ground and bond interior luminaires in accordance with Section 26 05 26.

3.02 FIELD QUALITY CONTROL
A. Operate each luminaire after installation and connection. Inspect for proper connection and operation.

3.03 ADJUSTING
A. Aim and adjust luminaires as indicated on Drawings.

3.04 CLEANING
A. Remove dirt and debris from enclosures.

B. Clean photometric control surfaces as recommended by manufacturer.

C. Clean finishes and touch up damage.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 3
Interior Lighting

3.05 PROTECTION OF FINISHED WORK
A. Relamp or replace luminaires having failed lamps at Substantial Completion.

END OF SECTION 26 51 00
173.138 Selective Electrical Demolition
City of Imperial Wastewater Treatment Plant Demolition Project 02 41 26 - 2

3. Maintain life-safety systems in full operation in occupied facilities, or provide notice minimum 7 days in advance.

E. Identify salvage items in cooperation with Owner.

PART 2 EXECUTION

2.1 EXAMINATION
A. Verify wiring and equipment indicated to be demolished serve only abandoned facilities.

B. Verify termination points for demolished services.

2.2 PREPARATION
A. Erect, and maintain temporary safeguards, including barricades, and similar measures, for protection of the public, Owner, Contractor’s employees, and existing improvements to remain.

B. Temporary egress signage and emergency lighting.

2.3 DEMOLITION
A. Demolition Drawings are based on casual field observation and existing record documents.

Report discrepancies to Architect/Engineer before disturbing existing installation.

B. Coordinate with general contractor to remove abandoned equipment, conduit, and wire at buildings and structures scheduled for demolition. Cut conduit flush with walls and floors scheduled to remain.

C. Remove conduit, wire, boxes, and fastening devices to avoid any interference with new installation.

D. Disconnect electrical systems in walls, floors, and ceilings scheduled for removal.

E. Reconnect equipment being disturbed by renovation work and required for continue service to nearest available panel.

F. Disconnect or shut off service to areas where electrical work is to be removed. Remove electrical fixtures, equipment, and related switches, outlets, conduit and wiring which are not part of final project.

G. Install temporary wiring and connections to maintain existing systems in service during construction.

H. Perform work on energized equipment or circuits with experienced and trained personnel.

I. Remove, relocate, and extend existing installations to accommodate new construction. 173.138 Selective Electrical Demolition
City of Imperial Wastewater Treatment Plant Demolition Project 02 41 26 - 3 J. Repair adjacent construction and finishes damaged during demolition and extension work.

K. Remove exposed abandoned grounding and bonding components, fasteners and supports, and electrical identification components. Cut embedded support elements flush with walls and floors.

L. Clean and repair existing equipment to remain or to be reinstalled.

M. Protect and retain power to existing active equipment remaining.

N. Cap abandoned empty conduit at both ends.

2.4 EXISTING PANELBOARDS
A. Ring out circuits in existing panel affected by the Work. Where additional circuits are needed, reuse circuits available for reuse. Install new breakers.

B. Tag unused circuits as spare.

C. Where existing circuits are indicated to be reused, use sensing measuring devices to verify circuits feeding Project area or are not in use.

D. Remove existing wire no longer in use from panel to equipment.

E. Provide new updated directories where more than three circuits have been modified or rewired.

2.5 SALVAGE ITEMS
A. Remove and protect items indicated on Drawings to be salvaged and turn over to Owner.

B. Items of salvageable value may be removed as work progresses. Transport salvaged items from site as they are removed.

2.6 REUSABLE ELECTRICAL EQUIPMENT
A. Carefully remove equipment, materials, or fixtures which are to be reused.

B. Disconnect, remove, or relocate existing electrical material and equipment interfering with new installation.

2.7 CLEANING
A. Remove demolished materials as work progresses. Legally dispose.

B. Keep workplace neat.

END OF SECTION
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 00 - 1
Basic Electrical Requirements
SECTION 26 05 00

BASIC ELECTRICAL REQUIREMENTS
PART 1 GENERAL

1.01 SCOPE OF WORK
A. Basic Electrical Requirements specifically applicable to Division 26 Sections.

B. All labor, materials, equipment and services necessary to furnish and install complete electrical systems and related items of work as indicated to Drawings or specified herein.

C. The work in general shall consist of, but is not limited to the following:

1. Coordination with the general contractor and utility companies to perform selective electrical demolition work in conjunction with the overall demolition work as indicated on the drawings.

2. Outdoor underground electrical feeder, underground trenching and conduit, and accessories as indicated.

3. Modifications to existing distribution panel, conduit, wiring, etc., for all new electrical distribution as indicated.

4. Interior lighting fixtures with lamps and lighting accessories as indicated D. Drawings are diagrammatic. Refer to Mechanical and Architectural Drawings and specifications for exact locations for equipment furnished by others.

1.02 WORK SEQUENCE
A. Install work as scheduled to accommodate Owner's occupancy requirements. During the construction period coordinate electrical schedule and operations with other trades, Owner and/or Engineer.

1.03 REFERENCES AND REGULATORY REQUIREMENTS
A. Conform to applicable International Building Code.

B. Workmanship and material of electrical work shall comply with or exceed applicable provisions of the following (most recent additions including addenda and errata):

1. All Local Codes and Ordinances.

2. California/National Electrical Code (NEC) (NFPA 70).

3. California/International Building Code (IBC).

4. California/International Existing Building Code (IEBC).

5. California/International Fire Code (IFC).

6. NFPA 72, Fire Alarm Code.

7. National Bureau of Fire Underwriters (NBFU).

8. American National Standards Institute (ANSI).

9. American Society for Testing and Materials (ASTM).

10. National Electrical Manufacturers Association (NEMA).

11. Standards and requirements for serving utilities.

12. Standards of Installation (NECA).

13. Safety and Health Standards (OSHA).

14. Americans with Disabilities Act (ADA).

15. Factory Mutual (FM).
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 00 - 2
Basic Electrical Requirements

1.04 SUBMITTALS
A. Submit shop drawings and product data grouped to include complete submittals of related systems, products, and accessories in a single submittal. Partial submittals will not be reviewed.

B. Mark dimensions and values in units to match those specified.

1.05 PROJECT/SITE CONDITIONS
A. Install Work in locations shown on Drawings, unless prevented by Project conditions.

B. Prepare drawings showing proposed rearrangement of Work to meet Project conditions, including changes to Work specified in other Sections. Obtain permission of Owner and/or Architect before proceeding.

C. SITE WORK: Contractor shall employ an independent locating service to locate and verify all existing services, whether specifically shown on the drawings or not. Location of services shall be recorded on record documents. No trenching or excavation shall commence until locations are verified. The Owner shall be notified in writing prior to any trenching requiring a utility shutdown. Any services interrupted by trenching or excavating shall be repaired by the contractor with no additional cost to the Owner. Existing services not specifically indicated on the drawings to be relocated, which interfere with building components, shall be brought to the Architect's immediate attention. Prepare drawings showing proposed re-routing, area(s) affected, and length of interruption(s).

1.06 SEQUENCING AND SCHEDULING
A. Construct Work in sequence under provisions of the General Specifications.

END OF SECTION 26 05 00
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 1
Low Voltage Electrical Power
Conductors and Cables
SECTION 26 05 19

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes building wire and cable; and wiring connectors and connections.

B. Related Sections:

1. Section 26 05 53 - Identification for Electrical Systems: Product requirements for wire identification.

1.02 REFERENCES
A. International Electrical Testing Association:

1. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

B. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

2. NFPA 262 - Standard Method of Test for Flame Travel and Smoke of Wires and Cables for Use in Air-Handling Spaces.

1.03 SYSTEM DESCRIPTION
A. Product Requirements: Provide products as follows:

1. Solid conductor for feeders and branch circuits 10 AWG and smaller.

2. Stranded conductors for control circuits.

3. Conductor not smaller than 12 AWG for power and lighting circuits.

4. Conductor not smaller than 16 AWG for control circuits.

5. 10 AWG conductors for 20 ampere, 120 volt branch circuits longer than 75 feet.

B. Wiring Methods: Provide the following wiring methods:

1. Concealed Dry Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

2. Exposed Dry Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

3. Above Accessible Ceilings: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

4. Wet or Damp Interior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

5. Exterior Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

6. Underground Locations: Use only building wire, Type THHN/THWN 90 degree C rated insulation, in raceway.

7. Use wiring and methods indicated on drawings.

1.04 DESIGN REQUIREMENTS
A. Conductor sizes are based on copper.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 2
Low Voltage Electrical Power
Conductors and Cables

1.05 SUBMITTALS
A. Product Data: Submit for building wire and each cable assembly type.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of components and circuits.

1.07 QUALITY ASSURANCE
A. Provide wiring materials located in plenums with peak optical density not greater than 0.5, average optical density not greater than 0.15, and flame spread not greater than 5 feet (1.5 m) when tested in accordance with NFPA 262.

1.08 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

1.09 FIELD MEASUREMENTS
A. Verify field measurements are as indicated on Drawings.

1.10 COORDINATION
A. Where wire and cable destination is indicated and routing is not shown, determine routing and lengths required.

B. Wire and cable routing indicated is approximate unless dimensioned.

PART 2 - PRODUCTS

2.01 BUILDING WIRE
A. Manufacturers:

1. Okonite.

2. General Cable Co.

3. Southwire.

4. American.

5. Substitutions: Under provisions of General Specifications.

B. Product Description: Single conductor insulated wire.

C. Conductor: Copper.

D. Insulation: 600 volt rating; material rated 90 degrees C.

2.02 WIRING CONNECTORS
A. Split Bolt Connectors:

1. Kearney.

2. Teledyne Penn-Union.

B. Solderless Pressure Connectors:
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 3
Low Voltage Electrical Power
Conductors and Cables

1. Cadweld.

2. Burndy.

C. Compression Connectors:

1. Kearney.

2. Teledyne- Penn-Union.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify interior of building has been protected from weather.

B. Verify mechanical work likely to damage wire and cable has been completed.

C. Verify raceway installation is complete and supported.

3.02 PREPARATION
A. Completely and thoroughly swab raceway before installing wire.

3.03 INSTALLATION
A. Route wire and cable to meet Project conditions.

B. Neatly train and lace wiring inside boxes, equipment, and panelboards.

C. Identify and color code wire and cable under provisions of Section 26 05 53. Identify each conductor with its circuit number or other designation indicated.

D. Special Techniques--Building Wire in Raceway:

1. Pull conductors into raceway at same time.

2. Install building wire 4 AWG and larger with pulling equipment.

E. Special Techniques - Cable:

1. Protect exposed cable from damage.

2. Support cables above accessible ceiling, using spring metal clips or cable ties to support cables from structure. Do not rest cable on ceiling panels.

3. Use suitable cable fittings and connectors.

F. Special Techniques - Wiring Connections:

1. Clean conductor surfaces before installing lugs and connectors.

2. Make splices, taps, and terminations to carry full ampacity of conductors with no perceptible temperature rise.

3. Tape uninsulated conductors and connectors with electrical tape to 150 percent of insulation rating of conductor.

4. Install split bolt connectors for copper conductor splices and taps, 6 AWG and larger.

5. Install solderless pressure connectors with insulating covers for copper conductor splices and taps, 8 AWG and smaller.

G. Install solid conductor for feeders and branch circuits 10 AWG and smaller.

3.04 WIRE COLOR
A. General:

1. For wire sizes 10 AWG and smaller, install wire colors in accordance with the following:
a. Black and red for single phase circuits at 120/240 volts. b. Black, red, and blue for circuits at 120/240 volts single or three phase. c. Match existing.

2. For wire sizes 8 AWG and larger, identify wire with colored tape at terminals, splices and boxes. Colors are as follows:
a. Black and red for single phase circuits at 120/240 volts. b. Black, red, and blue for circuits at 120/240 volts single or three phase. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 19 - 4
Low Voltage Electrical Power
Conductors and Cables
c. Match existing.

B. Neutral Conductors: White. When two or more neutrals are located in one conduit, individually identify each with proper circuit number.

C. Branch Circuit Conductors: Install three or four wire home runs with each phase uniquely color coded.

D. Feeder Circuit Conductors: Uniquely color code each phase.

E. Ground Conductors:

1. For 6 AWG and smaller: Green.

2. For 4 AWG and larger: Identify with green tape at both ends and visible points including junction boxes.

3.05 FIELD QUALITY CONTROL
A. Inspect and test in accordance with NETA ATS, except Section 4.

B. Perform inspections and tests listed in NETA ATS, Section 7.3.1.

END OF SECTION 26 05 19
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 1
Grounding and Bonding
for Electrical Systems
SECTION 26 05 26

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Rod electrodes.

2. Wire.

3. Mechanical connectors.

4. Exothermic connections.

1.02 REFERENCES
A. Institute of Electrical and Electronics Engineers:

1. IEEE 142 - Recommended Practice for Grounding of Industrial and Commercial Power Systems.

2. IEEE 1100 - Recommended Practice for Powering and Grounding Electronic Equipment.

B. International Electrical Testing Association:

1. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

C. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

1.03 SYSTEM DESCRIPTION
A. Grounding systems use the following elements as grounding electrodes:

1. Metal underground water pipe.

2. Metal building frame.

3. Concrete-encased electrode.

4. Rod electrode.

1.04 PERFORMANCE REQUIREMENTS
A. Grounding System Resistance: 25 ohms maximum.

1.05 SUBMITTALS
A. Product Data: Submit data on grounding electrodes and connections.

B. Test Reports: Indicate overall resistance to ground and resistance of each electrode.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of components and grounding electrodes. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 2
Grounding and Bonding
for Electrical Systems

1.07 QUALITY ASSURANCE
A. Provide grounding materials conforming to requirements of NEC, IEEE 142, and UL labeled.

1.08 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing Products specified in this section with minimum three years documented experience.

1.09 DELIVERY, STORAGE, AND HANDLING
A. Accept materials on site in original factory packaging, labeled with manufacturer's identification.

B. Protect from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original packaging.

C. Do not deliver items to project before time of installation. Limit shipment of bulk and multiple-use materials to quantities needed for immediate installation.

PART 2 - PRODUCTS

2.01 ROD ELECTRODES
A. Manufacturers:

1. Apache Grounding/Erico Inc.

2. Copperweld, Inc.

3. Erico, Inc.

4. O-Z Gedney Co.

B. Product Description:

1. Material: Copper.

2. Diameter: 3/4 inch.

C. Length: 10 feet.

2.02 WIRE
A. Material: Stranded copper.

B. Foundation Electrodes: 4 AWG.

C. Equipment Grounding Conductor: Copper conductor insulated.

D. Bonding Conductor: Copper conductor bare or insulated.

2.03 MECHANICAL CONNECTORS
A. Manufacturers:

1. Apache Grounding/Erico Inc.

2. Copperweld, Inc.

3. ILSCO Corporation.

4. O-Z Gedney Co.

5. Thomas & Betts, Electrical.

B. Description: Bronze connectors, suitable for grounding and bonding applications, in configurations required for particular installation.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 26 - 3
Grounding and Bonding
for Electrical Systems

2.04 EXOTHERMIC CONNECTIONS
A. Manufacturers:

1. Cadweld.

2. Copperweld, Inc.

3. Thermoweld.

B. Product Description: Exothermic materials, accessories, and tools for preparing and making permanent field connections between grounding system components.

PART 3 - EXECUTION

3.01 PREPARATION
A. Remove paint, rust, mill oils, and surface contaminants at connection points.

3.02 INSTALLATION
A. Install in accordance with IEEE and manufacturer instructions.

B. Install rod electrodes at locations as indicated on Drawings. Install additional rod electrodes to achieve specified resistance to ground.

C. Install grounding and bonding conductors concealed from view.

D. Equipment Grounding Conductor: Install separate, insulated conductor within each feeder and branch circuit raceway. Terminate each end on suitable lug, bus, or bushing.

E. Install 4 AWG bare copper wire in foundation footing as indicated on Drawings or install grounding electrode conductor and connect to reinforcing steel in foundation footing as indicated on Drawings.

F. Bond together metal siding not attached to grounded structure; bond to ground.

G. Equipment Grounding Conductor: Install separate, insulated conductor within each feeder and branch circuit raceway. Terminate each end on suitable lug, bus, or bushing.

H. Permanently ground entire light and power system in accordance with NEC, including service equipment, distribution panels, lighting panelboards, switch and starter enclosures, motor frames, grounding type receptacles, and other exposed non-current carrying metal parts of electrical equipment.

I. Accomplish grounding of electrical system by using insulated grounding conductor installed with feeders and branch circuit conductors in conduits. Size grounding conductors in accordance with NEC. Install from grounding bus of serving panel to ground bus of served panel, grounding screw of receptacles, lighting fixture housing, light switch outlet boxes or metal enclosures of service equipment. Ground conduits by means of grounding bushings on terminations at panelboards with installed number 12 conductor to grounding bus.

J. Grounding electrical system using continuous metal raceway system enclosing circuit conductors in accordance with NEC.

K. Permanently attach equipment and grounding conductors prior to energizing equipment.

3.03 FIELD QUALITY CONTROL
A. Inspect and test in accordance with NETA ATS, except Section 4.

B. Grounding and Bonding: Perform inspections and tests listed in NETA ATS, Section 7.13.

C. Perform ground resistance testing in accordance with IEEE 142.

D. Perform continuity testing in accordance with IEEE 142.

E. When improper grounding is found on receptacles, check receptacles in entire project and correct. Perform retest.

END OF SECTION 26 05 26
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 1
Hangers and Supports
for Electrical Systems
SECTION 26 05 29

FIRESTOPPING, HANGERS, AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Conduit supports.

2. Formed steel channel.

3. Spring steel clips.

4. Sleeves.

5. Mechanical sleeve seals.

6. Firestopping relating to electrical work.

7. Firestopping accessories.

8. Equipment bases and supports.

1.02 REFERENCES
A. ASTM International:

1. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials.

2. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials.

3. ASTM E814 - Standard Test Method for Fire Tests of Through-Penetration Fire Stops.

4. ASTM E1966 - Standard Test Method for Fire-Resistive Joint Systems.

B. FM Global:

1. FM - Approval Guide, A Guide to Equipment, Materials & Services Approved By Factory Mutual Research For Property Conservation.

C. National Fire Protection Association:

1. NFPA 70 - National Electrical Code.

D. Underwriters Laboratories Inc.:

1. UL 263 - Fire Tests of Building Construction and Materials.

2. UL 723 - Tests for Surface Burning Characteristics of Building Materials.

3. UL 1479 - Fire Tests of Through-Penetration Firestops.

4. UL 2079 - Tests for Fire Resistance of Building Joint Systems.

5. UL - Fire Resistance Directory.

1.03 DEFINITIONS
A. Firestopping (Through-Penetration Protection System): Sealing or stuffing material or assembly placed in spaces between and penetrations through building materials to arrest movement of fire, smoke, heat, and hot gases through fire rated construction.

1.04 SYSTEM DESCRIPTION
A. Firestopping Materials: ASTM E814 and UL 1479 to achieve fire ratings as noted on Drawings for adjacent construction.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 2
Hangers and Supports
for Electrical Systems

1.05 PERFORMANCE REQUIREMENTS
A. Firestopping: Conform to applicable code for fire resistance ratings and surface burning characteristics.

1.06 SUBMITTALS
A. Product Data:

1. Hangers and Supports: Submit manufacturers catalog data including load capacity.

2. Firestopping: Submit data on product characteristics, performance and limitation criteria.

B. Firestopping Schedule: Submit schedule of opening locations and sizes, penetrating items, and required listed design numbers to seal openings to maintain fire resistance rating of adjacent assembly.

C. Design Data: Indicate load carrying capacity of hangers and supports.

D. Manufacturer's Installation Instructions:

1. Hangers and Supports: Submit special procedures and assembly of components.

2. Firestopping: Submit preparation and installation instructions.

E. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

1.07 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing Products specified in this section with minimum three years documented experience.

B. Installer: Company specializing in performing work of this section with minimum three years documented experience.

1.08 DELIVERY, STORAGE, AND HANDLING
A. Accept materials on site in original factory packaging, labeled with manufacturer's identification.

B. Protect from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original packaging.

1.09 ENVIRONMENTAL REQUIREMENTS
A. Do not apply firestopping materials when temperature of substrate material and ambient air is below 60 degrees F. Maintain this minimum temperature before, during, and for minimum 3 days after installation of firestopping materials.

PART 2 - PRODUCTS

2.01 CONDUIT SUPPORTS
A. Manufacturers:

1. Allied Tube & Conduit Corp.

2. Electroline Manufacturing Company.

3. O-Z Gedney Co.

4. Substitutions: Under provisions of General Specifications.

B. Hanger Rods: Threaded high tensile strength galvanized carbon steel with free running threads.

C. Beam Clamps: Malleable Iron, with tapered hole in base and back to accept either bolt or hanger rod. Set screw: hardened steel.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 3
Hangers and Supports
for Electrical Systems
D. Conduit clamps for trapeze hangers: Galvanized steel, notched to fit trapeze with single bolt to tighten.

E. Conduit clamps - general purpose: One hole malleable iron for surface mounted conduits.

F. Cable Ties: High strength nylon temperature rated to 185 degrees F. Self locking.

2.02 FORMED STEEL CHANNEL
A. Manufacturers:

1. Unistrut Corp.

2. Allied Tube & Conduit Corp.

3. B-Line Systems.

4. Midland Ross Corporation, Electrical Products Division.

5. Substitutions: Under provisions of General Specifications.

B. Product Description: Galvanized 12 gage thick steel. With holes 1-1/2 inches on center.

2.03 SPRING STEEL CLIPS
A. Manufacturers:

1. O-Z/Gedney.

2. Spring City Electrical Mfg..

3. Erico Products.

4. Substitutions: Under provisions of General Specifications B. Product Description: Mounting hole and screw closure.

2.04 FIRESTOPPING
A. Manufacturers:

1. Dow Corning Corp..

2. Fire Trak Corp.

3. Hilti Corp.

4. International Protective Coating Corp.

5. 3M fire Protection Products.

6. The RectorSeal Corporation Bio Fireshield.

7. Substitutions: Under provisions of General Specifications B. Product Description: Different types of products by multiple manufacturers are acceptable as required to meet specified system description and performance requirements; provide only one type for each similar application.

1. Silicone Firestopping Elastomeric Firestopping: Single or multiple component silicone elastomeric compound and compatible silicone sealant.

2. Foam Firestopping Compounds: Single or multiple component foam compound.

3. Formulated Firestopping Compound of Incombustible Fibers: Formulated compound mixed with incombustible non-asbestos fibers.

4. Fiber Stuffing and Sealant Firestopping: Composite of mineral fiber stuffing insulation with silicone elastomer for smoke stopping.

5. Mechanical Firestopping Device with Fillers: Mechanical device with incombustible fillers and silicone elastomer, covered with sheet stainless steel jacket, joined with collars, penetration sealed with flanged stops.

6. Intumescent Firestopping: Intumescent putty compound which expands on exposure to surface heat gain.

7. Firestop Pillows: Formed mineral fiber pillows.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 4
Hangers and Supports
for Electrical Systems

2.05 FIRESTOPPING ACCESSORIES
A. Primer: Type recommended by firestopping manufacturer for specific substrate surfaces and suitable for required fire ratings.

B. Installation Accessories: Provide clips, collars, fasteners, temporary stops or dams, and other devices required to position and retain materials in place.

C. General:

1. Furnish UL listed products.

2. Select products with rating not less than rating of wall or floor being penetrated.

D. Non-Rated Surfaces:

1. Stamped steel, chrome plated, hinged, split ring escutcheons or floor plates or ceiling plates for covering openings in occupied areas where conduit is exposed.

2. For exterior wall openings below grade, furnish modular mechanical type seal consisting of interlocking synthetic rubber links shaped to continuously fill annular space between conduit and cored opening or water-stop type wall sleeve.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify openings are ready to receive firestopping.

3.02 PREPARATION
A. Clean substrate surfaces of dirt, dust, grease, oil, loose material, or other matter affecting bond of firestopping material.

B. Remove incompatible materials affecting bond.

C. Install backing or damming materials to arrest liquid material leakage.

D. Obtain permission from Architect/Engineer before using powder-actuated anchors.

E. Obtain permission from Architect/Engineer before drilling or cutting structural members.

3.03 INSTALLATION - HANGERS AND SUPPORTS
A. Anchors and Fasteners:

1. Concrete Structural Elements: Provide precast inserts, expansion anchors, powder actuated anchors and preset inserts.

2. Steel Structural Elements: Provide beam clamps, spring steel clips, steel ramset fasteners, and welded fasteners.

3. Concrete Surfaces: Provide self-drilling anchors and expansion anchors.

4. Hollow Masonry, Plaster, and Gypsum Board Partitions: Provide toggle bolts and hollow wall fasteners.

5. Solid Masonry Walls: Provide expansion anchors and preset inserts.

6. Sheet Metal: Provide sheet metal screws.

7. Wood Elements: Provide wood screws.

B. Inserts:

1. Install inserts for placement in concrete forms.

2. Install inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams.

3. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.

4. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.

5. Where inserts are omitted, drill through concrete slab from below and provide throughbolt with recessed square steel plate and nut above slab. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 29 - 5
Hangers and Supports
for Electrical Systems
C. Install conduit and raceway support and spacing in accordance with NEC.

D. Do not fasten supports to pipes, ducts, mechanical equipment, or conduit.

E. Install multiple conduit runs on common hangers.

F. Supports:

1. Fabricate supports from structural steel or formed steel channel. Install hexagon head bolts to present neat appearance with adequate strength and rigidity. Install spring lock washers under nuts.

2. Install surface mounted cabinets and panelboards with minimum of four anchors.

3. In wet and damp locations install steel channel supports to stand cabinets and panelboards 1 inch off wall.

3.04 INSTALLATION – FIRESTOPPING
A. Install material at fire rated construction perimeters and openings containing penetrating sleeves, piping, ductwork, conduit and other items, requiring firestopping.

B. Apply primer where recommended by manufacturer for type of firestopping material and substrate involved, and as required for compliance with required fire ratings.

C. Apply firestopping material in sufficient thickness to achieve required fire and smoke rating, to uniform density and texture.

D. Fire Rated Surface:

1. Seal opening at floor, wall, partition, ceiling, and roof as follows:
a. Install sleeve through opening and extending beyond minimum of 1 inch on both sides of building element.
b. Size sleeve allowing minimum of 1 inch void between sleeve and building element. c. Pack void with backing material.
d. Seal ends of sleeve with UL listed fire resistive silicone compound to meet fire rating of structure penetrated.

2. Where cable tray, conduit, and wireway penetrates fire rated surface, install firestopping product in accordance with manufacturer's instructions.

E. Non-Rated Surfaces:

1. Seal opening through non-fire rated wall, partition, floor, ceiling, and roof opening as follows:
a. Install sleeve through opening and extending beyond minimum of 1 inch on both sides of building element.
b. Size sleeve allowing minimum of 1 inch void between sleeve and building element. c. Install type of firestopping material recommended by manufacturer.

2. Install escutcheons, floor plates or ceiling plates where conduit, penetrates non-fire rated surfaces in occupied spaces. Occupied spaces include rooms with finished ceilings and where penetration occurs below finished ceiling.

3. Exterior wall openings below grade: Assemble rubber links of mechanical seal to size of conduit and tighten in place, in accordance with manufacturer's instructions.

3.05 FIELD QUALITY CONTROL
A. Inspect installed firestopping for compliance with specifications and submitted schedule.

3.06 CLEANING AND PROTECTION OF FINISHED WORK
A. Clean adjacent surfaces of firestopping materials.

B. Protect adjacent surfaces from damage by material installation.

END OF SECTION 26 05 29
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 1
Raceways and Boxes
for Electrical Systems
SECTION 26 05 33

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes conduit and tubing, outlet boxes, and junction boxes.

1.02 REFERENCES
A. American National Standards Institute:

1. ANSI C80.1 - Rigid Steel Conduit, Zinc Coated.

2. ANSI C80.3 - Specification for Electrical Metallic Tubing, Zinc Coated.

B. National Electrical Manufacturers Association:

1. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).

2. NEMA FB 1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit and Cable Assemblies.

3. NEMA OS 1 - Sheet Steel Outlet Boxes, Device Boxes, Covers, and Box Supports.

4. NEMA OS 2 - Nonmetallic Outlet Boxes, Device Boxes, Covers, and Box Supports.

5. NEMA RN 1 - Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit.

6. NEMA TC 2 - Electrical Polyvinyl Chloride (PVC) Tubing and Conduit.

7. NEMA TC 3 - PVC Fittings for Use with Rigid PVC Conduit and Tubing.

1.03 SYSTEM DESCRIPTION
A. Raceway and boxes located as indicated on Drawings, and at other locations required for splices, taps, wire pulling, equipment connections, and compliance with regulatory requirements.

Raceway and boxes are shown in approximate locations unless dimensioned. Provide raceway to complete wiring system.

B. Outdoor Locations, Above Grade: Use rigid steel, intermediate metal conduit, and electrical metallic tubing. Provide cast metal or nonmetallic outlet, pull, and junction boxes.

C. Wet and Damp Locations: Provide galvanized rigid steel conduit, intermediate metal conduit and electrical metallic tubing. Provide cast metal or nonmetallic outlet, junction, and pull boxes.

Provide flush mounting outlet box in finished areas.

D. Concealed Dry Locations: Provide rigid steel, intermediate metal conduit, electrical and metallic tubing. Provide sheet-metal boxes. Provide flush mounting outlet box in finished areas. Provide hinged enclosure for large pull boxes.

E. Exposed Dry Locations: Use rigid steel conduit to 8 feet above flush floor or to first junction box.

Use rigid steel conduit, intermediate metal conduit or electrical metallic tubing at other locations.

Provide sheet-metal boxes. Provide flush mounting outlet box in finished areas. Provide hinged enclosure for large pull boxes.

1.04 DESIGN REQUIREMENTS
A. Minimum Raceway Size:

1. Above floor: 1/2 inch unless otherwise specified.

2. Underground: 3/4 inch unless otherwise specified.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 2
Raceways and Boxes
for Electrical Systems

1.05 SUBMITTALS
A. Product Data: Submit for the following:

1. Flexible metal conduit.

2. Liquidtight flexible metal conduit.

3. Nonmetallic conduit.

4. Raceway fittings.

5. Conduit bodies.

6. Surface raceway.

7. Wireway.

8. Pull and junction boxes.

B. Manufacturer's Installation Instructions: Submit application conditions and limitations of use stipulated by Product testing agency specified under Regulatory Requirements. Include instructions for storage, handling, protection, examination, preparation, and installation of Product.

1.06 CLOSEOUT SUBMITTALS
A. Project Record Documents:

1. Record actual routing of conduits larger than 2 inch trade size.

2. Record actual locations and mounting heights of outlet, pull, and junction boxes.

1.07 DELIVERY, STORAGE, AND HANDLING
A. Protect conduit from corrosion and entrance of debris by storing above grade. Provide appropriate covering.

B. Protect PVC conduit from sunlight.

1.08 COORDINATION
A. Coordinate installation of outlet boxes for equipment connected under Section 26 05 03.

B. Coordinate mounting heights, orientation and locations of outlets mounted above counters, benches, and backsplashes.

PART 2 - PRODUCTS

2.01 METAL CONDUIT
A. Manufacturers:

1. Allied Tube and Conduit.

2. Hubbell Inc.

3. AFC.

4. Substitutions: Under provisions of General Specifications.

B. Rigid Steel Conduit: ANSI C80.1.

C. Intermediate Metal Conduit (IMC): Rigid steel.

D. Fittings and Conduit Bodies: NEMA FB 1; material to match conduit.

2.02 PVC COATED METAL CONDUIT
A. Manufacturers:

1. Occidental Coating.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 3
Raceways and Boxes
for Electrical Systems

2. P.C.D.

3. Robroy Industries.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: NEMA RN 1; rigid steel conduit with external PVC coating, 40 mil thick.

C. Fittings and Conduit Bodies: NEMA FB 1; steel fittings with external PVC coating to match conduit.

2.03 FLEXIBLE METAL CONDUIT
A. Manufacturers:

1. Acme International.

2. Electri-Flex Co.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications B. Product Description: Interlocked steel or aluminum construction.

C. Fittings: NEMA FB 1.

2.04 LIQUIDTIGHT FLEXIBLE METAL CONDUIT
A. Manufacturers:

1. Acme International.

2. Electri-Flex Co.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: Interlocked steel or aluminum construction with PVC jacket.

C. Fittings: NEMA FB 1.

2.05 ELECTRICAL METALLIC TUBING (EMT)
A. Manufacturers:

1. Allied Tube and Conduit.

2. AFC.

3. Hubbell Inc.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: ANSI C80.3; galvanized tubing.

C. Fittings and Conduit Bodies: NEMA FB 1; steel or malleable iron, compression type.

2.06 NONMETALLIC CONDUIT
A. Manufacturers:

1. Carlon.

2. RACO.

3. Can-Tex.

4. Substitutions: Under provisions of General Specifications.

B. Product Description: NEMA TC 2; Schedule 40 or 80 PVC.

C. Fittings and Conduit Bodies: NEMA TC 3.

2.07 WIREWAY
A. Manufacturers:

1. Circle AW.

2. Thomas & Betts Corp.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 4
Raceways and Boxes
for Electrical Systems

3. Substitutions: Under provisions of General Specifications.

B. Product Description: General purpose or Raintight type wireway as required.

C. Knockouts: Manufacturer's standard.

D. Size: Dimensions as indicated on Drawings or as required by the NEC for the intended application.

E. Cover: Hinged or screw cover as indicated or as required for the intended applications. Provide with full gaskets when requried.

F. Connector: Flanged.

G. Fittings: Lay-in type.

H. Finish: Rust inhibiting primer coating with manufacturer’s standard gray enamel finish.

2.08 OUTLET BOXES
A. Sheet Metal Outlet Boxes: NEMA OS 1, galvanized steel.

1. Luminaire and Equipment Supporting Boxes: Rated for weight of equipment supported; furnish 1/2 inch male fixture studs where required.

2. Concrete Ceiling Boxes: Concrete type.

B. Nonmetallic Outlet Boxes: NEMA OS 2.

C. Cast Boxes: NEMA FB 1, Type FD, cast feralloy. Furnish gasketed cover by box manufacturer.

Furnish threaded hubs.

D. Wall Plates for Finished Areas: As specified in Section 26 27 26.

E. Wall Plates for Unfinished Areas: Furnish gasketed cover.

2.09 SMALL PULL AND JUNCTION BOXES
A. Sheet Metal Boxes: NEMA OS 1, galvanized steel.

B. Hinged Enclosures: As specified.

C. Surface Mounted Cast Metal Box: NEMA 250, Type 4; flat-flanged, surface mounted junction box:

1. Material: Galvanized cast iron or aluminum.

2. Cover: Furnish with ground flange, neoprene gasket, and stainless steel cover screws.

D. In-Ground Cast Metal Box: NEMA 250, Type 6, galvanized cast iron, flanged, recessed cover box for flush mounting. Nonskid cover with neoprene gasket and stainless steel cover screws.

Cover Legend: "ELECTRIC" or as indicated.

E. Fiberglass or Concrete Composite Handholes: Die-molded, glass-fiber or concrete composite hand holes. Cable Entrance: Pre-cut 6 inch x 6 inch cable entrance at center bottom of each side. Cover: Glass-fiber or concrete composite, weatherproof cover with nonskid finish. Cover Legend: "ELECTRIC" or as indicated.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify outlet locations and routing and termination locations of raceway prior to rough-in.

3.02 INSTALLATION
A. Ground and bond raceway and boxes in accordance with Section 26 05 26.

B. Fasten raceway and box supports to structure and finishes in accordance with Section 26 05 29.

C. Identify raceway and boxes in accordance with Section 26 05 53.

D. Arrange raceway and boxes to maintain headroom and present neat appearance. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 5
Raceways and Boxes
for Electrical Systems

3.03 INSTALLATION - RACEWAY
A. Install conduit in accordance with NECA "Standard of Installation”.

B. Raceway routing is shown in approximate locations unless dimensioned. Route to complete wiring system.

C. Arrange raceway supports to prevent misalignment during wiring installation.

D. Support raceway using coated steel or malleable iron straps, lay-in adjustable hangers, clevis hangers, and split hangers.

E. Group related raceway; support using conduit rack. Construct rack using steel channel specified in Section 16070; provide space on each for 25 percent additional raceways.

F. Do not support raceway with wire or perforated pipe straps. Remove wire used for temporary supports
G. Do not attach raceway to ceiling support wires or other piping systems.

H. Construct wireway supports from steel channel specified in Section 26 05 29.

I. Route exposed raceway parallel and perpendicular to walls.

J. Route raceway installed above accessible ceilings parallel and perpendicular to walls.

K. Maintain clearance between raceway and piping for maintenance purposes.

L. Maintain 12 inch clearance between raceway and surfaces with temperatures exceeding 104 degrees F.

M. Cut conduit square using saw or pipe cutter; de-burr cut ends.

N. Bring conduit to shoulder of fittings; fasten securely.

O. Join nonmetallic conduit using cement as recommended by manufacturer. Wipe nonmetallic conduit dry and clean before joining. Apply full even coat of cement to entire area inserted in fitting. Allow joint to cure for minimum 20 minutes.

P. Install conduit hubs or sealing locknuts to fasten conduit to sheet metal boxes in damp and wet locations and to cast boxes.

Q. Install no more than equivalent of three 90 degree bends between boxes. Install conduit bodies to make sharp changes in direction, as around beams. Install hydraulic one-shot bender to fabricate or factory elbows for bends in metal conduit larger than 2 inch size.

R. Avoid moisture traps; install junction box with drain fitting at low points in conduit system.

S. Install fittings to accommodate expansion and deflection where raceway crosses seismic, control and expansion joints.

T. Install suitable pull string or cord in each empty raceway except sleeves and nipples.

U. Install suitable caps to protect installed conduit against entrance of dirt and moisture.

V. Surface Raceway: Install flat-head screws, clips, and straps to fasten raceway channel to surfaces; mount plumb and level. Install insulating bushings and inserts at connections to outlets and corner fittings.

W. Close ends and unused openings in wireway.

X. Exposed conduit floor penetrations shall be plastic coated steel or intermediate metal conduit or PVC wrapped (10 mil tape with 1/2 lap) galvanized rigid steel or intermediate metal conduit.

Concealed floor penetrations in a finished wall or chase may be thickwall Schedule 80 nonmetallic conduit. Extend non-metallic conduit to nearest junction box.

3.04 INSTALLATION - BOXES
A. Install wall mounted boxes at elevations to accommodate mounting heights as indicated on Drawings.

B. Adjust box location up to 5 feet prior to rough-in to accommodate intended purpose.

C. Orient boxes to accommodate wiring devices oriented as specified in Section 26 27 26.

D. Install pull boxes and junction boxes above accessible ceilings and in unfinished areas only.

E. In Accessible Ceiling Areas: Install outlet and junction boxes no more than 6 inches from ceiling access panel or from removable recessed luminaire.

F. Locate flush mounting box in masonry wall to require cutting of masonry unit corner only.

Coordinate masonry cutting to achieve neat opening.

G. Do not install flush mounting box back-to-back in walls; install with minimum 6 inches separation. Install with minimum 24 inches separation in acoustic rated walls. 173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 33 - 6
Raceways and Boxes
for Electrical Systems
H. Secure flush mounting box to interior wall and partition studs. Accurately position to allow for surface finish thickness.

I. Install stamped steel bridges to fasten flush mounting outlet box between studs.

J. Install flush mounting box without damaging wall insulation or reducing its effectiveness.

K. Install adjustable steel channel fasteners for hung ceiling outlet box.

L. Do not fasten boxes to ceiling support wires or other piping systems.

M. Support boxes independently of conduit.

N. Install gang box where more than one device is mounted together. Do not use sectional box.

O. Install gang box with plaster ring for single device outlets.

P. Set floor boxes level.

3.05 INTERFACE WITH OTHER PRODUCTS
A. Install conduit to preserve fire resistance rating of partitions and other elements, using materials and methods in accordance with General Specifications.

B. Route conduit through roof openings for piping and ductwork or through suitable roof jack with pitch pocket. Coordinate location with roofing installation specified in Specifications.

C. Locate outlet boxes to allow luminaires positioned as indicated on Drawings.

D. Align adjacent wall mounted outlet boxes for switches, thermostats, and similar devices.

3.06 ADJUSTING
A. Adjust flush-mounting outlets to make front flush with finished wall material.

B. Install knockout closures in unused openings in boxes.

3.07 CLEANING
A. Clean interior of boxes to remove dust, debris, and other material.

B. Clean exposed surfaces and restore finish.

END OF SECTION 26 05 33
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 1
Identification for Electrical Systems
SECTION 26 05 53

IDENTIFICATION FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes building wire and cable; metal clad cable; and wiring connectors and connections.

B. Section Includes:

1. Nameplates.

2. Labels.

3. Wire markers.

4. Conduit markers.

5. Stencils.

6. Underground Warning Tape.

7. Lockout Devices.

C. Related Sections:

1. Section - Paints and Coatings: Execution requirements for painting specified by this section.

1.02 SUBMITTALS
A. Product Data:

1. Submit manufacturer’s catalog literature for each product required.

2. Submit electrical identification schedule including list of wording, symbols, letter size, color coding, tag number, location, and function.

B. Samples:

1. Submit two tags, actual size.

2. Submit two labels, actual size.

C. Manufacturer's Installation Instructions: Indicate installation instructions, special procedures, and installation.

1.03 CLOSEOUT SUBMITTALS
A. Project Record Documents: Record actual locations of tagged devices; include tag numbers.

1.04 DELIVERY, STORAGE, AND HANDLING
A. Accept identification products on site in original containers. Inspect for damage.

B. Accept materials on site in original factory packaging, labeled with manufacturer's identification, including product density and thickness.

C. Protect insulation from weather and construction traffic, dirt, water, chemical, and mechanical damage, by storing in original wrapping.

1.05 ENVIRONMENTAL REQUIREMENTS
A. Install labels and nameplates only when ambient temperature and humidity conditions for adhesive are within range recommended by manufacturer.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 2
Identification for Electrical Systems

1.06 EXTRA MATERIALS
A. Furnish two containers of spray-on adhesive.

PART 2 - PRODUCTS

2.01 NAMEPLATES
A. Product Description: Laminated three-layer plastic with engraved white letters on black contrasting background color.

B. Letter Size:

1. 1/8 inch high letters for identifying individual equipment and loads.

2. 1/4 inch high letters for identifying grouped equipment and loads.

C. Minimum nameplate thickness: 1/8 inch.

2.02 LABELS
A. Labels: Embossed adhesive tape, with 3/16 inch white letters on black background.

2.03 WIRE MARKERS
A. Description: Cloth tape, split sleeve, or tubing type wire markers.

B. Legend:

1. Power and Lighting Circuits: Branch circuit or feeder number.

2. Control Circuits: Control wire number as indicated on shop drawings.

2.04 CONDUIT AND RACEWAY MARKERS
A. Description: Labels fastened with adhesive.

B. Color:

1. 480 Volt System: Black lettering on white background.

2. 208 or 240 Volt System: Black lettering on white background.

3. Fire Alarm System: Red lettering on white background.

4. Telephone System: Blue lettering on white background.

C. Legend:

1. Fire Alarm System: FIRE ALARM.

PART 3 - EXECUTION

3.01 PREPARATION
A. Degrease and clean surfaces to receive adhesive for identification materials.

3.02 INSTALLATION
A. Install identifying devices after completion of painting.

B. Nameplate Installation:

1. Install nameplate parallel to equipment lines.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 05 53 - 3
Identification for Electrical Systems

2. Install nameplate for each electrical distribution and control equipment enclosure with corrosive-resistant mechanical fasteners, or adhesive.

3. Install nameplates for each control panel and major control components located outside panel with corrosive-resistant mechanical fasteners, or adhesive.

4. Secure nameplate to equipment front using screws, rivets, or adhesive.

5. Secure nameplate to inside surface of door on recessed panelboard in finished locations.

6. Install nameplates for the following:
a. Switchboards.
b. Panelboards.
c. Service Disconnects.

C. Label Installation:

1. Install label parallel to equipment lines.

2. Install label for identification of individual control device stations.

3. Install labels for permanent adhesion and seal with clear lacquer.

D. Wire Marker Installation:

1. Install wire marker for each conductor at panelboard, pull boxes, outlet and junction boxes, and each load connection.

2. Mark data cabling at each end. Install additional marking at accessible locations along the cable run.

3. Install labels at data outlets identifying patch panel and port designation.

E. Conduit Marker Installation:

1. Install conduit marker for each conduit longer than 6 feet.

2. Conduit Marker Spacing: 20 feet on center.

END OF SECTION 26 05 53
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 1
Interior Lighting
SECTION 26 51 00

INTERIOR LIGHTING
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes interior luminaires, lamps, ballasts, and accessories.

B. Related Sections:

1. Section 26 05 26 - Grounding and Bonding for Electrical Systems.

2. Section 26 05 33 - Raceway and Boxes for Electrical Systems.

1.02 SUBMITTALS
A. Shop Drawings: Indicate dimensions and components for each luminaire not standard product of manufacturer.

B. Product Data: Submit manufacturer standard submittal data to include product data, dimensions, ratings, and performance data.

1.03 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

1.04 FIELD MEASUREMENTS
A. Verify field measurements prior to fabrication.

PART 2 - PRODUCTS

2.01 INTERIOR LUMINAIRES
A. Product Description: Complete interior luminaire assemblies, with features, options, and accessories as scheduled.

2.02 LED LIGHT FIXTURES
A. General:

1. LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified.

2. LED light fixtures shall be Reduction of Hazardous Substances (RoHS)-compliant.

3. LED drivers shall include the following features unless otherwise indicated:
a. Minimum efficiency: 85% at full load.
b. Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.) c. Input Voltage: 120 - 277V (±10%) at 60 Hz.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 2
Interior Lighting
d. Integral short circuit, open circuit, and overload protection. e. Power Factor: ≥ 0.95.
f. Total Harmonic Distortion: ≤ 20%.
g. Comply with FCC 47 CFR Part 15.
h. Manufacturer minimum 5-year standard warranty.

4. LED modules shall include the following features unless otherwise indicated:
a. Comply with IES LM-79 and LM-80 requirements.
b. Minimum CRI 80 and color temperature 3000˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE.
c. Minimum Rated Life: 50,000 hours per IES L70.
d. Light output lumens as indicated in the LIGHTING FIXTURE SCHEDULE.

PART 3 - EXECUTION

3.01 INSTALLATION
A. Install surface mounted luminaires plumb and adjust to align with building lines and with each other.

Secure to prevent movement.

B. Install wall-mounted luminaires at height as indicated on Drawings.

C. Install accessories furnished with each luminaire.

D. Connect luminaires to branch circuit outlets provided under Section 26 05 33 as indicated on Drawings.

E. Make wiring connections to branch circuit using building wire with insulation suitable for temperature conditions within luminaire.

F. Install specified lamps in each luminaire.

G. Ground and bond interior luminaires in accordance with Section 26 05 26.

3.02 FIELD QUALITY CONTROL
A. Operate each luminaire after installation and connection. Inspect for proper connection and operation.

3.03 ADJUSTING
A. Aim and adjust luminaires as indicated on Drawings.

3.04 CLEANING
A. Remove dirt and debris from enclosures.

B. Clean photometric control surfaces as recommended by manufacturer.

C. Clean finishes and touch up damage.
173-138
City of Imperial Wastewater Treatment Plant Demolition Project 26 51 00 - 3
Interior Lighting

3.05 PROTECTION OF FINISHED WORK
A. Relamp or replace luminaires having failed lamps at Substantial Completion.

END OF SECTION 26 51 00

CITY OF IMPERIAL

WASTEWATER TREATMENT

PLANT DEMOLITION PROJECT

SPECIAL CONDITIONS

APPENDIX B
February 18, 2026
CITY OF IMPERIAL BID NO. 2025-019
THG PROJECT NUMBER: 173.138
City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 1 of 24 ends

SPECIAL CONDITIONS

SPECIAL CONDITIONS
Table of Contents

1. Project Description................................................................................................. 2

2. Construction Water ................................................................................................ 5

3. City of Imperial Wastewater Treatment Plant Archive Improvement Plans....... 6

4. Native Earth Borrow Material................................................................................. 7

5. Geotechnical Testing ............................................................................................. 9

6. Imperial County Solid Waste Sites, Inert Debris Recycling Centers and Scrap Metal Recycling Vendor.............................................................................................. 10

7. Diversion Guidline Non-Compliance Demoltion Tonnage Deduction.............. 12

8. Lead and Asbestos Survey.................................................................................. 13

9. Imperial County Air Pollution Control District (ICAPCD) Construction/Demoltion Notification Form............................................................... 14

10. United States Environmental Protection Agency Notification of Demoltion and Renovation Form......................................................................................................... 15

11. City of Imperial Building Permit Application Form............................................ 16

12. City of Imperial Asbestos Demolition Declaration ............................................ 17

13. City of Imperial Demolition Permit...................................................................... 18

14. Table A – Waste Management Report Identification of Construction and Demoltion Debris (WMRIC&D) Chart ......................................................................... 19

15. Table B – Daily Recycling Log of Construction & Demoltion (C&D) Material Chart............................................................................................................................. 20

16. Table C – Waste Management Summary Report ............................................... 21

17. Table D – Design Engineer’s Opinion of Probable Quantity (EOOPQ)............ 22

18. Submittal Documents ......................................................................................... 23 City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 2 of 24 ends

SPECIAL CONDITIONS

1. PROJECT DESCRIPTION
The City of Imperial Wastewater Treatment Plant Demolition Project is primarily being completed to allow the area currently occupied by existing structures no longer used or minimally used to be occupied by new wastewater units or facilities. The City of Imperial is planning to construct a new wastewater influent pump station and headworks structure in the demolition area currently occupied by the non-used or minimally used wastewater structures. The following existing wastewater structures or ancillary items are to undergo minor, major or total demolition. Refer to plan sheet number 2 to observe the locations of the existing wastewater structures or ancillary items.

1. Operations Building – Minor Demolition – Also includes the installation of new light fixtures

2. Clarifier Number 1 – Major Demolition

3. Clarifier Number 2 – Major Demolition

4. Sludge Pump Station Building including Scum Pit – Major Demolition - Also includes installation of new lighting within the building, refurbishing emergency light fixtures, backfilling the scum pit and installation of pcc slab at the top of the scum pit and similar improvements.

5. Septic Dump Structure – Total Demolition

6. PCC Retaining Wall – Total Demolition

7. Sidewalk and A.C. Pavement near Structures – Total Demolition

8. Existing Crushed Rock east of Septic Dump Structure – Demolition Salvage – To be removed and placed at another location at the wastewater treatment plant
This project also includes other non-demolition improvements as follows:

1. Sealing a cracked opening along a construction cold joint at the pcc wall and channel of the Ultraviolet Disinfection Facility to stop an existing wastewater effluent leak.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 3 of 24 ends

SPECIAL CONDITIONS

2. Completing site grading within a portion of the demolition area after demolition work is completed. This item includes obtaining, transporting and placing native material obtained at the City of Imperial Water Treatment Plant as borrow material to complete the site grading work.

Refer to the improvement plans and specifications to determine the complete demolition scope of work and any improvements associated with the above listed items.

The demolition area is located within the existing City of Imperial Wastewater Treatment Plant Site. The demolition limits are illustrated on the plans. Demolition excavations are to be completed within the demolition limit lines illustrated on the plans. There are existing underground pipelines and utilities outside of the demolition lines. The location of many of the existing underground pipelines and utilities outside of the demolition lines is not known. It shall therefore be required that all demolition excavations remain inside of the demolition boundary lines illustrated on the plans.

A lead and asbestos survey was completed by Nicklaus Engineering, Inc. for Clarifier Number 1, Clarifier Number 2 and the Operation Building in October 2025. The Nicklaus Engineering asbestos and lead based paint survey report identified asbestos and lead in primarily the Operations Building. A metal standpipe at Clarifier Number 1 was identified to contain lead. Only a limited amount of demolition work is being completed in the Operations Building as illustrated on plan sheets 3 and 20. The contractor shall include the demolition removal and disposal of lead and asbestos items in the Operations Building for those items “called out” for demolition on the plans. If items identified as containing asbestos or lead in the Nicklaus Engineering Report are not “called out” for demolition on improvement plans 3 and 20 then those items shall be “left in place” and remain. The metal stand pipe at Clarifier Number 1 is to be removed and disposed of as a demolition item. The Contractor shall remove and dispose of asbestos and lead items in accordance with the recommendations contained in the Nicklaus Engineering, Inc. October 2025 City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 4 of 24 ends

SPECIAL CONDITIONS
Report and Technical Specification Section 8, entitled, “Asbestos and Lead Requirements”.

An Imperial County Air Pollution Control District Construction/Demolition Notification Form and a U.S Environmental Protection Agency (EPA) Notification of Demolition and Renovation Form are to be submitted to the appropriate agencies prior to the commencement of construction activities. The forms have been included in items 9 and 10 of this document. Both forms require that the demolition contractor be listed on the forms. Since the contractor to complete the demolition project will not be known until the processing of the contract documents between the City of Imperial and the Contractor is finished, it will be necessary for the forms to be completed by the City of Imperial Construction Manager and Contractor and submitted to the appropriate agencies after the agreement between the City of Imperial and Contractor is fully executed.

This project shall be completed in conformance with the improvement plans, technical specifications, special conditions and contract documents. The improvement plans technical specifications and special conditions were prepared specifically for this project and supersede the City of Imperial municipal construction and demolition recycling program requirements. The Technical Specifications and Special Conditions were prepared in accordance with the California Code of Regulations (CCR’s) including the California Green Building Standards Code. A detailed explanation of demolition requirements, demolition material diversion requirements and demolition material recycling, reuse, salvage and disposal requirements are contained in the Technical Specifications. The Contractor shall not be required to obtain a demolition permit from the City of Imperial. The signing of the contract agreement between the Contractor and City of Imperial obligating the Contractor to complete this project in conformance with the contract documents listed in Article I of the Contract Agreement shall serve as the Demolition Permit for this project.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 5 of 24 ends

SPECIAL CONDITIONS

2. CONSTRUCTION WATER
The Contractor can obtain potable construction water for the project from the City of Imperial Wastewater Treatment plant facility at a location designated by the City of Imperial Wastewater Plant Chief Operator. The contractor shall provide any required connection fittings, as designated by the Chief Operator, including but not limited to pipe fittings, reducers, flowmeters, backflow preventors and similar items.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 6 of 24 ends

SPECIAL CONDITIONS

3. CITY OF IMPERIAL WASTEWATER TREATMENT PLANT ARCHIVE

IMPROVEMENT PLANS
There are two (2) sets of archived City of Imperial Wastewater Treatment Plant improvement plans which illustrate a portion of the facilities and structures to undergo demolition. It was not possible to excavate the below grade portions of structures and facilities during the preparation of the design documents. The archived plans illustrate a portion of the existing below grade structures and facilities to undergo demolition. The contractor is encouraged during bid preparation to determine the configuration and quantity of demolition material illustrated on the archived plans.

An archived set of City of Imperial Wastewater Treatment Plant improvement plans prepared by Wisley & Ham dated 1976 is comprised of 46 plan sheets. An archived set of City of Imperial Wastewater Treatment Plant improvement plans prepared by Black and Veatch dated 1994/1995 is comprised of 47 plan sheets.

The archived plans have been included with the electronic documents advertised for bidding. Hard copy archived plans can be obtained for $120 per set of archived plans ($240 for both sets of archived plans) by contacting the City of Imperial Public Services Director at phone number (760) 355-3336 or by e-mail at [email protected] City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 7 of 24 ends

SPECIAL CONDITIONS

4. NATIVE EARTH BORROW MATERIAL
It was estimated that it will require 3,606 cubic yards of native earth to backfill the demolition excavations at the Imperial WWTP and complete the final site grading per plan sheet 30. The 3,606 cubic yards of imported native material was based on a 20 percent shrinkage factor after the imported material is placed and compacted. The native earth estimate completed by the design engineer is included in the Special Conditions Section Table D quantity estimates. The contractor is responsible for completing his/her own native earth import estimate including shrinkage during the bidding phase and be responsible for determining the quantity of native earth import yardage required to complete the demolition excavation backfilling and site grading work. The contractor shall rely on his/her estimated native earth import yardage number and shall not be allowed additional compensation by claiming the native earth import yardage assumed during the bidding period was less than the native earth import yardage required during the construction period.

There is a sufficient quantity of native earth borrow material at the City of Imperial Water Treatment Plant to backfill the demolition excavations and complete the final native earth site grading as illustrated on plan sheet 30. The Contractor shall contact the City of Imperial Wastewater Operator, City of Imperial Public Services Director and Construction Manager prior to commencing transporting the native borrow material from the City of Imperial Water Treatment Plant to the City of Imperial Wastewater Treatment Plant.

Entrance and truck routing through the Water and Wastewater Treatment Plants, daily time schedule for entering and exiting the Water and Wastewater Treatment Plants, location of native borrow material to be transported and other issues shall be reviewed.

The City of Imperial Water Treatment Plant is located at 201 South B Street, Imperial, CA 92251. The City of Imperial Wastewater Treatment Plant is located at 701 West 14th Street Imperial CA, 92251. The suggested routing summary between the City of Imperial Water Treatment Plant and City of Imperial Wastewater Treatment Plant is illustrated on the attached Haul Route Map following this Special Conditions Section.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 8 of 24 ends

SPECIAL CONDITIONS
The contractor shall be allowed to use other routes; however, the streets used on the other routes shall be required to be along truck routes. Other routes may prove more favorable and may be slightly shorter or longer in terms of distance and may be slightly shorter or longer in terms of time. See the attached google earth-based map illustrating the suggested truck route on the following page.

Blythe, Ca 92225
1601 N. Imperial Ave. El Centro, Ca 92243
201 E. Hobsonway
760.337.3883
760.922.4658
EXHIBIT:

SHEET:___ 1
OF____SHEETS 1
THG JOB NUMBER: 173.138
DATE: 02-18-2026
CLIENT: CITY OF IMPERIAL
CITY OF IMPERIAL – WASTEWATER TREATMENT PLANT DEMOLITION PROJECT

HAUL ROUTE FROM IMPERIAL WATER TREATMENT PLANT TO IMPERIAL WASTE WATER TREATMENT PLANT

IMPERIAL
WATER

TREATMENT
PANT

IMPERIAL

WASTEWATER

TREATMENT

PLANT N IMPERIAL AVE
LABRUCHERIE RD. W. BARIONI BLVD. N IMPERIAL AVE
15TH ST NOT-TO-SCALE
WORTHINGTON RD.

CONTRACTOR SHALL ACCESS FORM

NORTHWEST ENTRANCE GATE OF THE
IMPERIAL WATER TREATMENT PLANT.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 9 of 24 ends

SPECIAL CONDITIONS

5. GEOTECHNICAL TESTING
The contractor shall provide the Geotechnical Testing required for this project. The Geotechnical Testing shall consist of obtaining compaction tests for backfilling demolition excavations, final site grading, filling portions of existing structures with compacted native earth and class 2 base installation as required by the plans. The Geotechnical Testing shall include the preparation of proctor curves to determine the maximum density of native import material and completion of compaction testing. See Grading Plan Sheet 30 and other plan sheets for the native earth backfill placement, compaction and testing requirements.

No concrete testing is required for this project; however, the Contractor shall be required to forward all concrete truck delivery slips to the Construction Manager. The Construction Manager will verify that the sacks of cement per cubic yard of concrete and the compressive strength psi information on the concrete truck delivery slips is compliant with the concrete specification requirements.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 10 of 24 ends

SPECIAL CONDITIONS

6. IMPERIAL COUNTY SOLID WASTE SITES, INERT DEBRIS RECYCLING CENTERS

AND SCRAP METAL RECYCLING VENDOR
To assist the Contractor in identifying Solid Waste Sites, Inert Debris Recycling Centers and reuse or recycling vendors in Imperial County research of establishments was conducted during the project design with the assistance of the Local Enforcement Agency (LEA). The establishment list following this paragraph is not intended to be all inclusive and the contractor is encouraged to identify any other establishments in Imperial County, or other Counties, as the Contractor deems appropriate, however; all establishments shall be approved by the Local Enforcement Agency (LEA) and confirmed to be approved by the LEA by the Construction Manager prior to delivering demolition debris to the establishments. The Local Enforcement Agency is the Imperial County Public Health Department – Environmental Health Division. Following is the list of establishments identified during the project design period:

1. Salton City Solid Waste Site (Operated by Burrtec Waste Industries)

1.1 Address: 935 West Highway 86, Salton City, CA 92275

1.2 Contact: David Brischke, (909) 429-4200

1.3 SWIS Number: 13-AA-0011

1.4 Permit Status: This facility is permitted to operate as a C&D/inert debris recycling facility through its Solid Waste Facility Permit. It accepts source separated material and comingled C&D debris, along with inert debris.

2. Imperial Landfill (Operated by Republic Services)

2.1 Address: 3354 Dogwood Road, Imperial, CA 92251

2.2 Contact: Steven Hall, (760) 355-0004

2.3 SWIS Number: 13-AA-0019
City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 11 of 24 ends

SPECIAL CONDITIONS

2.4 Permit Status: This facility is permitted to operate as a C&D/inert debris processing facility through its Solid Waste Facility Permit. It accepts source separated material and comingled C&D waste, along with inert debris.

3. Elms Equipment Inert Debris Recycling Center

3.1 Addresses:

3.1.1 330 West Aten Road, Imperial, CA 92251

3.1.2 4201 Dogwood Road, Brawley, CA 92227

3.2 Contact: Alan Huber, Cell (760) 427-4074; Office (760) 356-6200

3.3 SWIS Number: N/A

3.4 Permit Status: The LEA determined these two sites meet the definition of an inert debris recycling center, and are exempt from a Solids Waste Facility Permit, as outlined in California Code of Regulations (CCR) Title 14, Section 17381.1. This facility is allowed to accept only inert debris, as defined by CCR Title 14, Section 17381.1. No C&D debris is allowed at this facility.

3.5 Specific Requirements: Material brought on-site must be allowed under CCR 17381(k)(1), it must be source separated, the residual amount of solid waste shall be less that 10 percent of the amount of source separated material received by weight, and the amount of putrescible waste in the source separated material shall be less than 1 percent of the amount of source separated material received by weight.

4. SA Recycling – Scrap Metal Recycling

4.1 Address: 460 East Holton Road

4.2 Contact: Freddie Reyes

4.3 SWIS Number: N/A

4.4 Permit Status: SA Recycling has been determined by the LEA as an acceptable facility to take iron and steel items for reuse or recycling.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 12 of 24 ends

SPECIAL CONDITIONS

7. DIVERSION GUIDELINE NON-COMPLIANCE DEMOLITION TONNAGE

DEDUCTION
The City of Imperial could face substantial fines for not meeting the required diversion requirements of 100 percent of inert material and a minimum of 65 percent of C & D debris (non-inert material) as required by Technical Condition Section 4. The contractor shall be fined $500/ton for each ton of demolition material which is not in compliance with the diversion requirements. The fine shall be implemented by means of a negative change order in which the fine amount will be deducted from the contractor’s contract amount per the agreement between the City of Imperial and the Contractor.

City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 13 of 24 ends

SPECIAL CONDITIONS

8. LEAD AND ASBESTOS SURVEY
A lead and asbestos survey was completed by Nicklaus Engineering, Inc. for Clarifier Number 1, Clarifier Number 2 and the Operations Building in October 2025. The Nicklaus Engineering asbestos and lead based paint survey report identified asbestos and lead primarily in the Operation Building. A metal standpipe at Clarifier Number 1 was identified to contain lead. Only a limited amount of demolition work is being completed in the Operations Building as illustrated on plan sheets 3 and 20. The contractor shall include the demolition removal and disposal of lead and asbestos items in the Operations Building for those items “called out” for demolition on the plans. If items identified as containing asbestos or lead in the Nicklaus Engineering Report are not “called out” for demolition on improvement plans 3 and 20 then those items shall be “left in place” and remain. The metal standpipe at Clarifier Number 1 is to be removed and disposed of as a demolition item. The Contractor shall remove and dispose of asbestos and lead items in accordance with the recommendations contained in the Nicklaus Engineering, Inc. October 2025 Report and Technical Specification Section 8, entitled, “Asbestos and Lead Requirements”.

The Asbestos and Lead Based Paint Survey Report prepared by Nicklaus Engineering, Inc. dated October 2025 follows this Special Conditions Section.

Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
1 Asbestos and Lead Based Paint Survey
Report
Imperial Wastewater Treatment Plant
Imperial, California
October 2025
Prepared for:

The Holt Group
1601 North Imperial Avenue
El Centro, CA 92243
Prepared by:

Nicklaus Engineering, Inc.
1851 W. 24th St.

Yuma, AZ 85364
Project: 025-0258.0000000
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
2 Table of Contents

1.0 INTRODUCTION.................................................................................................. 1

2.0 BACKGROUND.................................................................................................... 1

2.1 Regulatory Background .................................................................................... 1

3.0 METHODS............................................................................................................ 2

4.0 FINDINGS ............................................................................................................ 2

4.1 Asbestos ........................................................................................................... 2

4.2 Lead Based Paint.............................................................................................. 3

5.0 Recommendations................................................................................................ 3

5.1 Asbestos ........................................................................................................... 3

5.2 Lead Based Paint.............................................................................................. 4 Table 1............................................................................................................................. 5 Figures .......................................................................................................................... 12 Appendix A.................................................................................................................... 13 Appendix B.................................................................................................................... 14 Appendix C.................................................................................................................... 19 Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
1 1.0 INTRODUCTION
Nicklaus Engineering (Nicklaus) was contracted by The Holt Group (Holt) to conduct a survey to identify asbestos containing materials (ACM) and lead based paint (LBP) at the Imperial Wastewater Treatment Plant in Imperial, California. The survey is to support planned demolition activities at the facility. The survey was conducted on September 10, 2025.

2.0 BACKGROUND
The Imperial Wastewater Treatment Plant is an approximately 18-acre site located at 701 East 14th Street in the City of Imperial in Imperial County, California. Several upgraded facilities have recently been constructed at the plant to implement newer treatment technologies and increase the plant’s treatment capacity. As part of the plant upgrade, older buildings at the facility are planned for demolition or renovation. This survey was conducted on the office/laboratory building (approximately 1,450 square feet) and two adjacent clarifiers.

2.1 Regulatory Background
Asbestos is a naturally occurring fibrous mineral that has been widely used in thousands of building materials. Historically, asbestos was added to building products due to its fire resistant, anti-corrosive, anti-oxidizing, and strengthening properties. ACM is defined by the California Code of Regulations (CCR) Title 17 as materials that contain 1% asbestos content or more. CCR Tile 17 further defines materials containing asbestos in amounts less than 1% as asbestos containing construction material (ACCM). ACM and ACCM may release asbestos fibers if damaged or improperly cut, sanded, or graded. Inhalation of asbestos fibers may cause diseases such as asbestosis, mesothelioma, and lung cancer.

Although asbestos has been used in building products throughout human history, use of asbestos peaked in the mid-20th century. Starting in the 1980s, many asbestos products were banned. However, asbestos products could still be imported and installed.

Therefore, US Environmental Protection Agency (EPA) and the California Department of Environmental Protection (Cal/EPA) requires assessment for asbestos prior to demolition, even in newer buildings.

In the United States, LBP is defined as paint or other surface coating that contains 0.5% lead by dry weight or more. Exposure to lead dust from damaged LBP or through improper renovation/demolition techniques affecting building components with LBP can cause developmental damage to children as well as respiratory issues and cancer to workers and building tenants. All use of LBP was banned in the United States in 1978. However, LBP may still be present in buildings that predate the ban. In addition, lead may be present within certain materials such as porcelain and ceramics (known as lead containing materials). Improper demolition of these materials may also present health hazards. In Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
2 addition, some unpainted materials (such as ceramic and porcelain) may contain lead in glazing and are classified as lead containing materials (LCM). While not LBP, these materials may require special handling during demolition and/or disposal.

3.0 METHODS
The buildings were assessed for ACM/ACCM according to methods defined in the Asbestos Hazard and Emergency Response Act (AHERA). Materials that potentially contain asbestos were visually identified. The condition, friability, and approximate quantity was determined for each identified material. Representative bulk samples were then collected of each material. The number of samples collected from each material was determined using the “3-5-7” rule defined in AHERA. Samples collected were submitted to EMSL laboratories for analysis for asbestos content by polarized light microscopy (PLM) using EPA method 600/R-93/116. EMSL is certified by the National Voluntary Laboratory Acredidation Program (NVLAP) for asbestos analysis by PLM.

The buildings were assessed for LBP by analyzing painted and coated surfaces in situ using a handheld x-ray florescence (XRF) analyzer. All painted/coated building components in the buildings were analyzed systematically by building side going room to room (the north side of the building was designated as side “A,” with sides “B,” “C,” and “D” proceeding in a clockwise fashion). The color, condition, and substrate were recorded for each building component assessed. In accordance with CCR Title 8, surfaces with an XRF result of 1.0 milligrams per square centimeter (mg/cm2) were identified as building components containing LBP.

4.0 FINDINGS
The following section summarizes observations and analytical results resulting from the survey.

4.1 Asbestos
During the asbestos survey, seventeen (17) homogenous materials of suspected ACM were identified. A total for forty-six (46) bulk samples of these materials were collected, thirteen (13) of which contained asbestos. Materials identified as ACM include:
• Black Sink Undercoat (HM-5) (laboratory only): contains 2% chrysotile • Gray Epoxy Floor Coat (HM-7): contains 5% chrysotile
• Residual Floor Tile Mastic (HM-8): contains 4% chrysotile • Laboratory Benchtops (HM-9): contains 15% chrysotile
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
3 • Mortar (HM-12): contains 2% chrysotile
Table 1 provides a log of all asbestos samples collected and their laboratory results.

Figure 1 shows the samples that were identified through laboratory analysis as ACM and/or non-ACM for the identified sampling locations. Appendix A provides the complete laboratory report.

4.2 Lead Based Paint
During the LBP survey, one hundred forty-seven (147) building components were assessed by XRF analysis for lead content. Of these, three (3) building components were identified as containing LBP:
• Red painted metal drawers in laboratory
• Yellow painted metal drawers in laboratory (note: yellow drawers contained 0.9 mg/cm2 of lead. Although this is below the 1.0 mg/cm2 LBP threshold, it is within the XRF margin of error of ± 0.1 mg/cm2 of the threshold and is recommended to be considered LBP.)
• Yellow metal stand pipe at Clarifier #1
In addition, two (2) materials were identified as LCM:
• 4” Blue Ceramic Wall Tile
• 6” Blue Ceramic Wall Tile
Figure 2 shows the location of materials identified as containing LBP or as LCM. Appendix B provides the complete XRF log of the lead survey.

5.0 Recommendations
The following section provides recommendations for abatement, removal, and/or disposal of identified ACM and LBP/LCM that should be considered during the demolition or renovations.

5.1 Asbestos
All identified ACM must be removed prior to commencing any demolition or renovation activities and disposed of in accordance with CCR Tile 17. Gray epoxy floor coat, residual floor mastic, and mortar is considered Class II OSHA work and must be abated using enclosures and wet methods. Removal of sink undercoat and laboratory benchtops is considered Class III OSHA work. These materials may be removed as whole pieces, Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
4 without cutting or damaging them, and wrapped in polyvinyl sheeting. If removed and wrapped properly, these materials may typically be disposed of in municipal landfills. It is recommended that disposal facilities be identified and contacted prior to beginning abatement activities to determine their acceptance criteria. Abatement of these materials must be performed by personnel that have obtained AHERA certification in the class of work that is to be performed and licensed (as applicable) in California.

5.2 Lead Based Paint
All identified building components with LBP were intact and do not require stabilization prior to removal. It is recommended that these building components be removed without damaging their painted surfaces and wrapped in polyvinyl sheeting. It is recommended that disposal facilities be identified and contacted prior to beginning abatement activities to determine their acceptance criteria. However, it is likely that a toxic characteristic leaching procedure (TCLP) or similar analysis to determine toxicity will be required.

Identified LCM is not subject to CCR Title 8 removal requirements or the EPA Lead Renovation, Repair, and Painting Rule (RRP) and may be disposed of as general construction debris. However, dust generated from these materials during demolition activities may pose a risk to workers. Furthermore, if co-mingled with general construction debris waste streams, degraded LCM may raise the toxicity of those waste streams to a level that would require special and more costly disposal requirements. Therefore, it is recommended that damage to the ceramic tile be minimized during removal. It is further recommended that the tile be segregated from the general construction debris waste stream. A TCLP or similar test may then be conducted to determine if the tile may be disposed of in a municipal landfill.

Table 1
Asbestos Sample Log
Imperial Wastewater Treatment Plant
Imperial, California
HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers
Results
1 Drywall/Joint Compound IWWTP-A-01 Good NF N/A Breakroom Northeast corner behind door 3
None Detected
(Drywall)
None Detected
(Joint Compound)
None Detected
(Tape)
1 Drywall/Joint Compound IWWTP-A-02 Good NF N/A
Restroom foyer, South
wall
1 None Detected
(Joint Compound)
1 Drywall/Joint Compound IWWTP-A-03 Good NF N/A Breakroom Southwest corner 3
None Detected
(Drywall)
None Detected
(Joint Compound)
None Detected
(Tape)
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
6 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers
Results
2 Black Covebase/Mastic IWWTP-A-04 Good NF N/A Breakroom by door to storage room 2
None Detected
(Covebase)
None Detected
(Mastic)
2 Black Covebase/Mastic IWWTP-A-05 Good NF N/A Breakroom by South door 2 None Detected
(Covebase)
None Detected
(Mastic)
2 Black Covebase/Mastic IWWTP-A-06 Good NF N/A Breakroom East Wall 2 None Detected
(Covebase)
None Detected
(Mastic)
3 2'x4' Ceiling Panel with Fissures IWWTP-A-07 Good F N/A Breakroom South side 1 None Detected 3 2'x4' Ceiling Panel with Fissures IWWTP-A-08 Good F N/A Breakroom West side 1 None Detected 3 2'x4' Ceiling Panel with Fissures IWWTP-A-09 Good F N/A Breakroom East side 1 None Detected 4 12" Beige Floor Tile/Mastic IWWTP-A-10 Good NF N/A Breakroom by door to office 2 None Detected (Tile)
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
7 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers Results
4 12" Beige Floor Tile/Mastic IWWTP-A-10 Good NF N/A Breakroom by door to office 2 None Detected (Mastic)
4 12" Beige Floor Tile/Mastic IWWTP-A-11 Good NF N/A Breakroom by door to storage room 2
None Detected
(Tile)
None Detected
(Mastic)
4 12" Beige Floor Tile/Mastic IWWTP-A-12 Good NF N/A Breakroom by north exit door 2
None Detected
(Tile)
None Detected
(Mastic)
5 Black Sink Undercoat IWWTP-A-13 Good NF N/A Breakroom sink 1 None Detected 5 Black Sink Undercoat IWWTP-A-14 Good NF
6 Ft2
Lab Sink 1 2% Chrysotile
5 Black Sink Undercoat IWWTP-A-15 Good NF Lab Sink 1 2% Chrysotile 6 2'x4' Ceiling Panel with Gouges IWWTP-A-16 Good F N/A Office north side by
corridor to
breakroom/restroom
1 None Detected
6 2'x4' Ceiling Panel with Gouges IWWTP-A-17 Good F N/A Office west side 1 None Detected Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
8 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers Results
6 2'x4' Ceiling Panel with Gouges IWWTP-A-18 Good F N/A Office East Side 1 None Detected 7 Gray Epoxy Floorcoat IWWTP-A-19 Significantly
Damaged NF
294 Ft2
Office north side 1 None Detected
7 Gray Epoxy Floorcoat IWWTP-A-20 Significantly
Damaged NF Office middle 1 5% Chrysotile
7 Gray Epoxy Floorcoat IWWTP-A-21 Significantly
Damaged NF Office south side 1 4% Chrysotile
8 Residual Floor Tile Mastic IWWTP-A-22 Significantly
Damaged NF
342 Ft2
Restroom foyer near door 1 3% Chrysotile
8 Residual Floor Tile Mastic IWWTP-A-23 Significantly
Damaged NF Restroom foyer near door 1 3% Chrysotile
8 Residual Floor Tile Mastic IWWTP-A-24 Significantly
Damaged NF Restroom foyer near door 1 4% Chrysotile
9 Lab Benchtops IWWTP-A-25 Good NF
72 Ft2

Lab SE corner 1 15% Chrysotile
9 Lab Benchtops IWWTP-A-26 Good NF Lab near sink 1 15% Chrysotile Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
9 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers Results
9 Lab Benchtops IWWTP-A-27 Good NF 72 Ft2 Lab middle of bench 1 15% Chrysotile 10 1" Blue Ceramic Tile/Grout IWWTP-A-28 Good NF N/A Restroom near door 2 None Detected
(Tile)
None Detected
(Grout)
10 1" Blue Ceramic Tile/Grout IWWTP-A-29 Good NF N/A Restroom in shower 2 None Detected
(Tile)
None Detected
(Grout)
10 1" Blue Ceramic Tile/Grout IWWTP-A-30 Good NF N/A Restroom north corner 2 None Detected
(Tile)
None Detected
(Grout)
11 6" Blue Ceramic Tile/Grout IWWTP-A-31 Good NF N/A Restroom west wall 2 None Detected
(Tile)
None Detected
(Grout)
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
10 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers Results
11 6" Blue Ceramic Tile/Grout IWWTP-A-32 Good NF N/A Restroom near sink 2 None Detected
(Tile)
None Detected
(Grout)
11 6" Blue Ceramic Tile/Grout IWWTP-A-33 Good NF N/A Restroom next to toilet 2 None Detected
(Tile)
None Detected
(Grout)
12 Mortar IWWTP-A-34 Good NF
2,004 Ft2
Lab SE Wall 1 2% Chrysotile
12 Mortar IWWTP-A-35 Good NF Janitor closet S wall 1 2% Chrysotile 12 Mortar IWWTP-A-36 Good NF Exterior east wall by door 1 2% Chrysotile 13 White Duct Mastic IWWTP-A-37 Good NF N/A Breakrom above sink 1 None Detected 13 White Duct Mastic IWWTP-A-38 Good NF N/A Breakroom near door to storage room 1 None Detected
13 White Duct Mastic IWWTP-A-39 Good NF N/A Breakroom near east wall 1 None Detected Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
11 HM# Material Description Sample ID Condition Friability Quantity Location Sample Layers Results
14 Exterior Wall Sealant IWWTP-A-40 Good NF N/A West electrical box on South wall 1 None Detected
15 Plaster Wall IWWTP-A-41 Good NF N/A Lab north wall 1 None Detected 15 Plaster Wall IWWTP-A-42 Good NF N/A Office east wall 1 None Detected 15 Plaster Wall IWWTP-A-43 Good NF N/A Office south wall 1 None Detected 16 Roofing Material IWWTP-A-44 Good NF N/A East roof 1 None Detected 17 Concrete IWWTP-A-47 Good NF N/A Clarifier #1 1 None Detected 17 Concrete IWWTP-A-48 Good NF N/A Clarifier #2 1 None Detected Figures

SHOWER BATHROOM CLOSET N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com

SHOWER BATHROOM CLOSET N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com

SHOWER BATHROOM CLOSET N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com
N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com
N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com

SHOWER BATHROOM CLOSET N
E n g i n e e r i n g , I n c . icklaus 1851 West 24th Street Yuma, Arizona 85364 Phone: (928) 344-8374 www.neiaw.com
i
Appendix A
Asbestos Laboratory Report
Appendix B
XRF Log
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
Lead Based Paint Inspection
XRF Inspection Log
Site Name: Imperial Wastewater Treatment Plant
Inspector: Scott Brown Date: 9/10/2025
Room Side Component Condition Color Substrate
XRF
Result
N/A N/A Calibration N/A N/A N/A 1.0
N/A N/A Calibration N/A N/A N/A 1.0
N/A N/A Calibration N/A N/A N/A 1.0
Lab A Wall Intact White Plaster 0.4
Lab B Wall Intact White Plaster 0.4
Lab C Wall Intact White Concrete 0.1
Lab D Wall Intact White Plaster 0.3
Lab A Drawer Intact Red Metal 1.0
Lab A Drawer Intact Blue Metal 0.1
Lab B Drawer Intact Red Metal 0.9
Lab B Drawer Intact White Metal 0.2
Lab B Drawer Intact Green Metal 0.1
Lab B Drawer Intact Blue Metal 0.1
Lab D Drawer Intact Red Metal 1.1
Lab D Drawer Intact Yellow Metal 0.9
Lab D Drawer Intact Blue Metal 0.1
Lab D Drawer Intact Green Metal 0.0
Lab D Door Intact Brown Metal 0.0
Lab D Door Frame Intact Brown Metal 0.6
Lab C Electrical Panel Intact White Metal 0.2
Lab C Electrical Panel Intact Green Metal 0.1
Lab C Conduit Intact White Metal 0.5
Office A Wall Intact White Plaster 0.4
Office A Wall Intact White Concrete 0.4
Office B Wall Intact White Plaster 0.3
Office C Wall Intact White Plaster 0.4
Office D Wall Intact White Plaster 0.4
Office D Door Intact Brown Metal 0.1
Office D Door Frame Intact Brown Metal 0.4
Office N/A Ceiling Intact White Drywall 0.2
Foyer A Wall Intact White Plaster 0.3
Foyer B Wall Intact White Plaster 0.2
Foyer C Wall Intact White Plaster 0.1
Foyer D Wall Intact White Plaster 0.2
Foyer D Door Intact Brown Metal 0.1
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
Room Side Component Condition Color Substrate XRF
Result
Foyer D Door Frame Intact Brown Metal 0.5
Janitor A Wall Intact White Concrete 0.0
Janitor B Wall Intact White Concrete 0.1
Janitor C Wall Intact White Concrete 0.1
Janitor D Wall Intact White Concrete 0.2
Janitor N/A Ceiling Intact White Wood 0.1
Janitor A Shelve Intact White Wood 0.1
Janitor D Shelve Intact White Wood 0.1
N/A N/A Calibration N/A N/A N/A 1.1
N/A N/A Calibration N/A N/A N/A 1.1
N/A N/A Calibration N/A N/A N/A 1.1
Restroom A Wall Intact White Plaster 0.4
Restroom A Wall Intact Blue Ceramic 19.8
Restroom B Wall Intact Blue Ceramic 20.0
Restroom B Wall Intact White Plaster 0.4
Restroom C Wall Intact White Plaster 0.3
Restroom D Wall Intact White Plaster 0.2
Restroom C Wall Intact Blue Ceramic 20.2
Restroom D Shelve Intact White Wood 0.1
Restroom N/A Ceiling Intact White Drywall 0.0
Restroom B Urinal Intact White Porcelain 0.2
Restroom B Toilet Intact White Porcelain 0.4
Restroom B Sink Intact White Porcelain 0.3
Restroom N/A Floor Intact Blue Ceramic 0.2
Restroom A 6" Wall Tile Intact Blue Ceramic 15.9
Restroom B 6" Wall Tile Intact Blue Ceramic 16.5
Restroom C 6" Wall Tile Intact Blue Ceramic 16.3
Restroom D 6" Wall Tile Intact Blue Ceramic 21.8
Office N/A Floor Damaged Blue Concrete 0.3
Breakroom A Wall Intact White Drywall 0.2
Breakroom B Wall Intact White Drywall 0.1
Breakroom C Wall Intact White Drywall 0.1
Breakroom D Wall Intact White Drywall 0.1
Breakroom A Door Intact Brown Metal 0.1
Breakroom A Door Frame Intact Brown Metal 0.4
Breakroom C Door Frame Intact Brown Metal 0.0
Breakroom C Door Frame Intact Brown Metal 0.5
Breakroom C Upper Cabinet Intact N/A Wood 0.2
Breakroom C Lower Cabinet Intact N/A Wood 0.1
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
Room Side Component Condition Color Substrate XRF
Result
Breakroom D Cabinet Intact N/A Wood 0.1
Breakroom C Counertop Intact N/A Wood 0.0
Breakroom C Shelves Intact N/A Wood 0.0
Electrical A Wall Intact White Concrete 0.0
Electrical B Wall Intact White Concrete 0.0
Electrical C Wall Intact White Concrete 0.2
Electrical D Wall Intact White Concrete 0.2
Electrical N/A Ceiling Intact White Drywall 0.0
Electrical D Electrical Panel Intact Gray Metal 0.1
Electrical A Electrical Panel Intact Gray Metal 0.1
N/A N/A Calibration N/A N/A N/A 1.1
N/A N/A Calibration N/A N/A N/A 1.1
N/A N/A Calibration N/A N/A N/A 1.0
Exterior A Wall Intact White Concrete 0.0
Exterior A Foundation Intact White Concrete 0.0
Exterior A Window Frame Intact White Metal 0.2
Exterior A Door Intact White Metal 0.1
Exterior A Door Frame Intact White Metal 0.5
Exterior B Wall Intact White Concrete 0.2
Exterior B Foundation Intact White Concrete 0.1
Exterior B Downspout Intact White Metal 0.2
Exterior B Electrical Box Intact White Metal 0.1
Exterior B Conduit Intact White Metal 0.2
Exterior B Hose Reel Intact White Metal 0.3
Exterior B Door Intact White Metal 0.0
Exterior B Door Frame Intact White Metal 0.5
Exterior B Downspout Intact White Metal 0.2
Exterior C Wall Intact White Concrete 0.0
Exterior C Foundation Intact White Concrete 0.2
Exterior C Door Intact White Metal 0.1
Exterior C Door Frame Intact White Metal 0.4
Exterior C Window Frame Intact White Metal 0.1
Exterior C Electrical Box Intact White Metal 0.0
Exterior C Conduit Intact White Plastic 0.1
Exterior D Wall Intact White Concrete 0.3
Exterior D Foundation Intact White Concrete 0.2
Exterior D Downspout Intact White Metal 0.2
Exterior D Window Frame Intact White Metal 0.1
Exterior D Electrical Box Intact White Metal 0.1
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
Room Side Component Condition Color Substrate XRF
Result
Exterior D Downspout Intact White Metal 0.1
Exterior A Eave
Significant
Damage Blue Wood 0.1
Exterior A Crossbeam
Significant
Damage Blue Wood 0.0
Exterior A Fascia
Significant
Damage Blue Wood 0.0
Exterior A Fascia
Significant
Damage White Wood 0.0
Exterior B Eave
Significant
Damage Blue Wood 0.1
Exterior B Crossbeam
Significant
Damage Blue Wood 0.1
Exterior B Fascia
Significant
Damage Blue Wood 0.2
Exterior B Gutter Intact White Metal 0.1
Exterior B Attic Vent Intact White Metal 0.0
Exterior C Eave Intact Blue Wood 0.1
Exterior C Crossbeam Intact Blue Wood 0.1
Exterior C Fascia Intact Blue Wood 0.1
Exterior C Fascia Intact White Wood 0.0
Exterior D Eave Intact Blue Wood 0.1
Exterior D Crossbeam Intact Blue Wood 0.1
Exterior D Fascia Intact Blue Wood 0.1
Exterior D Gutter Intact White Metal 0.1
Exterior C Backflow Pipes Intact Blue Metal 0.1
Clarifier #1 A Clarifier Intact White Concrete 0.3
Clarifier #1 D Hose Reel Intact Red Metal 0.3
Clarifier #1 D Stand Pipe Intact Yellow Metal 8.6
Clarifier #1 A Stairs Intact Gray Metal 0.1
Clarifier #1 A Catwalk Intact Gray Metal 0.1
Clarifier #1 C Hose Reel Intact Red Metal 0.2
Clarifier #1 C Hose Bib Intact Red Metal 0.1
Clarifier #2 A Clarifier Intact White Concrete 0.0
Clarifier #2 C Stand Pipe Intact Red Metal 0.0
Appendix C
Survey Photographs
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
HM-1: Drywall/Joint Compound HM-2: Black Covebase Mastic HM-3: 2’x4’ Ceiling Panel with Fissures HM-4: 12” Beige Floor Tile/Mastic HM-5: Black Sink Undercoat (ACM) HM-6: 2’x4’ Ceiling Panel with Gouges Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
HM-7: Gray Epoxy Floor Coat (ACM) HM-8: Residual Floor Tile Mastic (ACM) HM-9: Laboratory Benchtops (ACM) HM-10: 1” Blue Ceramic Floor Tile/Grout HM-11: 6” Blue Ceramic Tile/Grout HM-12: Mortar (ACM)
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
HM-13: White Duct Mastic HM-14: Exterior Wall Sealant
HM-15: Plaster Wall HM-16: Roofing Material
HM-17: Concrete
Asbestos and Lead Survey Report
Imperial Wastewater Treatment Plant October 2025
Red Metal Drawer (LBP) Yellow Metal Drawer (LBP)
Yellow Stand Pipe (LBP) 4” and 6” Ceramic Tile (LCM)
City of Imperial – Wastewater Treatment Plant Demolition Project – THG #173.138

Page 14 of 24 ends