AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 148 of 527 GP-23
City Project: BD2209 City of Indio Public Works
The records of disposal, including scale tonnages, shall be furnished to the City on a monthly basis. Failure to comply with the requirements of this Section will result in delay of progress payment.
7-15.2 Contractor’s Obligation
The City is committed to a recycling program. If available, it is the obligation of the Contractor, under this Contract, to recycle the waste material through an approved recycling plant. Records and reports of waste recycle will be submitted to the City on a regular monthly basis.
SECTION 8. FACILITIES FOR AGENCY PERSONNEL
The provisions of Section 8 of the Standard Specifications shall apply except as modified herein.
No field offices for City personnel shall be required; however, City personnel shall have the right to enter upon the Project at all times and shall be admitted to the offices of the Contractor to use the telephone, desk and sanitary facilities provided by the Contractor for its own personnel.
SECTION 9. MEASUREMENT AND PAYMENT
The provisions below shall supplement but not replace those provisions in Section 9 of the Standard Specifications.
9-1.2 Methods of Measurement
The Contract Price shall constitute full compensation for all labor, equipment, materials, tools and incidentals required to complete the Project as outlined in these Contract Documents and as directed by the Engineer.
9-3 PAYMENT
9-3.1 General
In accordance with Public Contract Code Section 7107, if no claims have been filed and ar e still pending, the amount deducted from the final estimate and retained by the City will be paid to the Contractor except such amounts as are required by law to be withheld by properly executed and filed notices to stop payment, or as may be withheld for any other lawful purposes. 9-3.2 Partial and Final Payment
9-3.2.1 Monthly Closure Date and Invoice Date
In accordance with Section 9 -3.2 of the Standard Specifications, the monthly closure date shall be the last Day of each month. A measurement of Work performed and a progress estimate of the value thereof based on the Contract and of the monthly payment shall be prepared by the Contractor and submitted to the Engineer before the tenth (10th) Day of the following month for verification and payment consideration.
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 149 of 527 GP-24
City Project: BD2209 City of Indio Public Works
9-3.2.2 Payments
The City shall make payments within thirty (30) Days after receipt of the Contractor’s undisputed and properly submitted payment request, including an updated construction schedule pursuant to Section 6-1.1 of the General Provisions. The City shall re turn to the Contractor any payment request determined not to be a proper payment request as soon as practicable, but not later than seven (7) Days after receipt, and shall explain in writing the reasons why the payment request is not proper.
9-3.2.3 Retention
If stated in the Contract, the City shall withhold not less than five percent (5%) from each progress payment. However, at any time after fifty percent (50%) of the Work has been completed, if the City Council finds that satisfactory progress is being made, i t may, at its discretion, make any of the remaining progress payments in full for actual Work completed. The City shall withhold not less than five percent (5%) of the Contract Price from the Final Payment Amount (defined in Section 9-3.2.4) until at least thirty-five (35) days after recordation of the Notice of Completion, or recordation of a notice of completion or cessation, but not longer then the period permitted by Public Contract Code Section 7107.
9-3.2.4 Final Invoice and Payment
Whenever the Contractor s hall have completely performed the Contract in the opinion of the Engineer, the Engineer shall notify the City Clerk that the Contract has been completed in its entirety. The Contractor shall then submit to the Engineer a written statement of the final quantities of Contract items for inclusion in the final invoice. Upon receipt of such statement, the Engineer shall check the quantities included therein and shall authorize a payment amount, which in the Engineer’s opinion shall be just and fair, covering the value of the total amount of Work done by the Contractor, less all previous payments and all amounts to be retained under the provisions of the Contract Documents (“Final Payment Amount”). The Engineer shall then request that the City accept the Work and that the City Clerk be authorized to file, on behalf of the City in the office of the County Recorder, a Notice of Completion of the Work herein agreed to be done by the Contractor. In addition, the final payment will not be released until the Contrac tor returns the control set of Plans and Specifications showing the redlined as-built conditions. 9-3.2.5 Substitute Security
In accordance with Public Contract Code Section 22300, the Contractor may request that it be permitted to substitute securities in lieu of having retention withheld by the City from progress payments when such payments become due or, in the alternative, the Contractor may request that the City make payments of earned retentions directly to an agreed upon designated escrow agent at the Contractor’s expense. If the Contractor selects either one of these alternatives, the following shall control.
9-3.2.5.1 Substitution of Securities for Performance Retention At some reasonable time before any progress payment would otherwise be due and payable to the Contractor in the performance of Work under these Contract Documents, the Contractor may submit a request to the City in writing to permit the substitution of retentions with securities equivalent to the amount estimated by the City (“estimated amount of rete ntion”) to be withheld.
The Contractor shall deposit such securities with the City or may, in the alternative, deposit such
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 150 of 527 GP-25
City Project: BD2209 City of Indio Public Works
securities in escrow with a State or federally chartered bank in California, as the escrow agent, at the Contractor’s expense. Suc h securities will be the equivalent or greater in value of the estimated amount of retention. If the Contract is modified by written Modifications or Change Orders or the Contractor otherwise becomes entitled to receive an amount more than the Contract Price at the time the securities are deposited, the Contractor shall, at the request of the City, deposit with the City or escrow agent, whichever is applicable, additional securities within a reasonable time so that the amount of securities on deposit with the City or escrow agent is equivalent or greater in value than the amount of retention the City would otherwise be entitled to withhold from progress payments due or to become due to the Contractor as the Work progresses.
The City shall withhold any retention amount that exceeds the security amount until the additional securities are deposited and, if the deposit is with an escrow agent, the City has confirmation from that escrow agent of the new total value of securities. Upon satisfactory completion of the Contract, which shall mean, among other things, that the City is not otherwise entitled to retain proceeds from progress payments as elsewhere provided in the Contract or under applicable law, the securities shall be returned to the Contractor. The C ity shall, within its sole discretion, determine whether the amount of the securities on deposit with the City or escrow agent is equal to or greater than the amount of estimated retention of progress payments that could otherwise be held by the City if the Contractor had not elected to substitute same with securities. 9-3.2.5.2 Deposit of Retention Proceeds with an Escrow Agent As an alternative to the substitution of securities, as provided above, or the City otherwise retaining and holding retention proceeds from progress payments, the Contractor may request the City to make payments of retentions earned directly to an escrow agent with the same qualifications as required in Section 9-3.2.5.1 above and at the expense of the Contractor. At its sole expense, the Contractor may direct the investment of such retention payments into only such securities as mentioned in Section 9-3.2.5.3 below and shall be entitled to interest earned on such investments on the same terms provided for securities deposited by the Contracto r. Upon satisfactory completion of the Contract, which shall mean when the City would not otherwise be entitled to withhold retention proceeds from progress payments had the Contractor not elected to have such proceeds deposited into escrow, the Contracto r shall be allowed to receive from the escrow agent all securities, interest and payments deposited into escrow pursuant to the terms of this Section. The Contractor shall pay to each Subcontractor, not later than ten (10) Days of receipt of payment, the respective amount of interest earned, net of costs attributed to retention withheld from each Subcontractor, on the amount withheld to ensure performance of the Contractor.
9-3.2.5.3 Subcontractor Entitlement to Interest
If the Contractor elects to receive interest on any moneys withheld in retention by the City, then the Subcontractor shall receive the identical rate of interest received by the Contractor on any retention moneys withheld from the Subcontractor by the Contractor, less any actual pro rata costs associated with administering and calculating that interest. In the event that the interest rate is a fluctuating rate, the rate for the Subcontractor shall be determined by calculating the interest rate paid during the time that retentions were withheld from t he Subcontractor. If the Contractor elects to substitute securities in lieu of retention, then, by mutual consent of the Contractor and the Subcontractor, the Subcontractor may substitute securities in exchange for the release of moneys held in retention by the Contractor. The Contractor shall pay each Subcontractor, not later than ten (10) Days after receipt of escrow moneys, the amount owed to each Subcontractor from the moneys plus the respective amount of interest earned, net of costs
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 151 of 527 GP-26
City Project: BD2209 City of Indio Public Works
attributed to the retention held from each Subcontractor, on the amount of retention withheld to ensure performance of the Subcontractor.
9-3.2.5.4 Securities Eligible for Investment
Securities eligible for investment shall include those listed in Government Code Section 16430, bank or savings and loan certificates of deposit, interest -bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed upon between the Contractor and the City. The Contractor shall be the beneficial owner of any securities substituted for any monies withheld and shall receive any interest thereon.
9-3.2.5.5 Escrow Agreement for Security Deposits in Lieu of Retention The escrow agreement that shall be used for the deposit of securities in lieu of retention shall substantially conform to the form prescribed in Public Contract Code Section 22300(f). 9-3.2.5.6 Inconsistencies with Prevailing Statutory Requirements If there is any inconsistency between or differences in Public Contract Code Section 22300 and the terms of this provision, or any future amendments thereto, Section 22300 shall control. 9-3.4 Mobilization
Mobilization is defined as the preparatory work that must be performed or cost incurred before starting work on the various items on the job site in accordance with Public Contract Code Section 10104. The City makes the partial payments under Public Contract Code Section 10264. 9-4 AUDIT
The City or its representative shall have the option of inspecting and/or auditing all records and other written materials used by the Contractor in preparing its billings to the City as a condition precedent to any payment to the Contractor or in response to a construction claim or a Public Records Act (Government Code Section 6250 et seq.) request. The Contractor will promptly furnish documents requested by the City at no cost. Additionally, the Contractor shall be subject to State Auditor examination and audit at the request of the City or as part of any audit of the City, for a period of three (3) years after final payment under the Contract. The Contractor shall include a copy of this Section 9 -4 in all contracts with its Subcontractors, and the Contractor shall be responsible for immediately obtaining those records or other written material from its Subcontractors upon a request by the State Auditor or th e City. If the Project includes other auditing requirements, those additional requirements will be listed in the Special Provisions.
SECTION 10. ADDITIONAL TERMS
10-1 NONDISCRIMINATORY EMPLOYMENT
The Contractor shall not unlawfully discriminate against any ind ividual based on race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation or military and veteran status. The Contractor understands and agrees that it is bound by and will comply with the nondiscrimination mandates of all statutes and local ordinances and regulations.
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 152 of 527 GP-27
City Project: BD2209 City of Indio Public Works
10-2 NOTICE TO PROCEED
Upon award of this Contract and signing the Contract D ocuments, the City shall issue the Contractor a Notice to Proceed. The City will not authorize any Work to be done under these Contract Documents before the Contract has been fully executed. Any Work that is done by the Contractor in advance of such time shall be considered as being done at the Contractor’s own risk and responsibility, and as a consequence will be subject to rejection. 10-3 CONTRACTOR’S RESPONSIBILITY FOR WORK
Until the final acceptance of the Work by the City as defined in Section 6 -8.2 of th e General Provisions, by written action of the Engineer, the Contractor shall have the charge and care thereof and shall bear the risk of injury or damage to any part of the Work by the action of the elements, criminal acts, or any other cause. The Contra ctor shall rebuild, repair, restore and make good all injuries or damages to any portion of the Work occasioned by any cause before its completion and acceptance and shall bear the expense thereof, except for such injuries or damages arising from the sole negligence or willful misconduct of the City, its officers, agents or employees. In the case of suspension of Work from any cause whatever, the Contractor shall be responsible for all materials and the protection of Work already completed, shall properly store and protect them if necessary, and shall provide suitable drainage and erect temporary structures where necessary.
10-4 PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY
Any portions of curb, gutter, sidewalk or any other City improvement damaged by the Contractor during the course of construction shall be replaced by the Contractor at its own cost. The cost of additional replacement of curb, gutter or sidewalk in excess of the estimated quantities shown in the Bid form and Specifications, and found necessary during the process of construction (but not due to damage resulting from carelessness on the part of the Contractor during its operation), shall be paid to the Contractor at the unit prices submitted in his or her Bid. 10-5 REMOVAL OF INTERFERING OBSTRUCTIONS
The Contractor shall remove and dispose of all debris, abandoned structures, tree roots and obstructions of any character encountered during the process of excavation. It is understood that the cost of any such removals are made a part of the unit price bid by the Contractor under the item for excavation or removal of existing Work.
10-6 SOILS ENGINEERING AND TESTING
A certified materials testing firm may be retained by the City to perform materials tests during the Contractor’s entire operation to ascertain c ompliance with the Contract requirements. The City shall be responsible for the first series of tests. If the initial tests do not meet the Contract requirements, the Contractor shall bear the cost of all subsequent tests.
If the City requires other test s or more specific requirements for testing regarding this Project, those details will be included in the Special Provisions.
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 153 of 527 GP-28
City Project: BD2209 City of Indio Public Works
10-7 ACCESS TO PRIVATE PROPERTY
Unless otherwise stated in the Special Provisions, the Contractor shall be responsible for all fees and costs associated with securing permission to access private property for any portion of the Project.
10-8 WORKING DAYS AND HOURS
Work hours are as follows, unless otherwise approved by the Engineer:
Pacific Standard Time Pacific Daylight Time
Monday through Friday 7:00 a.m. - 6:00 p.m. 6:00 a.m. - 6:00 p.m.
If the Engineer approves weekend days and/or government holidays as working days, City Inspection Fees will be charged at a rate of time and a half per hour of inspection. This includes surveying, material testing, and any and all professional services required.
In addition, no Work will be allowed on any special election Day that may be declared. Should a special election Day be declared, a time extension of one (1) Working Day will be granted fo r each such Day.
A permit may have other hours or Days for the Contractor to do the Work, and those hours and Days shall supersede any hours and Days written in this Section.
Whenever the Contractor is permitted or directed to perform night Work or to vary the period during which Work is performed during the Working Day, the Contractor shall give twelve (12) hours’ notice to the Engineer so that inspection may be provided. Also, a charge may be made to the Contractor for approved overtime or weekend inspections requested by the Contractor. 10-9 CLAIM DISPUTE RESOLUTION
In the event of any dispute or controversy with the City over any matter whatsoever, the Contractor shall not cause any delay or cessation in or of Work, but shall proceed with the performance of the Work in dispute. The Contractor shall retain any and all rights provided that pertain to the resolution of disputes and protests between the parties. The Disputed Work will be categorized as an “unresolved dispute” and payment, if any, shall be as later determined by mutual agreement or a court of law. The Contractor shall keep accurate, detailed records of all Disputed Work, claims and other disputed matters.
All claims arising out of or related to the Contract Documents or this Project, and the consideration and payment of such claims, are subject to the Government Claims Act (Government Code Section 810 et seq.) with regard to filing claims and to Public Contract Code Section 20104 et seq. (Article 1.5) regarding the resolution of public works clai ms of three hundred seventy -five thousand dollars ($375,000) or less. This Contract hereby incorporates those provisions as through fully set forth herein. Thus, the Contractor or any Subcontractor must file a claim in accordance with the Government Clai ms Act as a prerequisite to filing a construction claim in compliance with Article 1.5, and must then adhere to Article 1.5. 10-10 THIRD PARTY CLAIMS
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 154 of 527 GP-29
City Project: BD2209 City of Indio Public Works
The City shall have full authority to compromise or otherwise settle any claim relating to the Project at any ti me. The City shall timely notify the Contractor of the receipt of any third -party claim relating to the Project. The City shall be entitled to recover its reasonable costs incurred in providing this notice.
10-11 COMPLIANCE WITH LAWS
The Contractor shall comply with all applicable federal, State and local laws, ordinances, codes and regulations in force at the time the Contractor performs pursuant to the Contract Documents. 10-12 CONTRACTOR’S REPRESENTATIONS
By signing the Contract, the Contractor represents, covenan ts, agrees, and declares under penalty of perjury under the laws of the State of California that: (a) the Contractor is licensed, qualified, and capable of furnishing the labor, materials, and expertise necessary to perform the services in accordance with the terms and conditions set forth in the Contract Documents ; (b) there are no obligations, commitments, or impediments of any kind that will limit or prevent its full performance under the Contract Documents; (c) there is no litigation pending against the Contractor that could adversely affect its performance of the Contract, and the Contractor is not the subject of any criminal investigation or proceeding; and (d) to the Contractor’s actual knowledge, neither the Contractor nor its personnel have been convicted of a felony. 10-13 CONFLICTS OF INTEREST
The Contractor agrees not to accept any employment or representation during the term of the Contract or within twelve (12) months after acceptance as defined in Section 6-8.2 of the General Provisions that is or ma y likely make the Contractor “financially interested,” as provided in Government Code Sections 1090 and 87100, in any decisions made by the City on any matter in connection with which the Contractor has been retained pursuant to the Contract Documents. 10-14 APPLICABLE LAW
The validity, interpretation, and performance of these Contract Documents shall be controlled by and construed under the laws of the State of California, excluding California’s choice of law rules.
Venue for any such action relating to the Contract shall be in the Riverside County Superior Court. 10-15 TIME
Time is of the essence in these Contract Documents.
10-16 INDEPENDENT CONTRACTOR
The Contractor and Subcontractors shall at all times remain, as to the City, wholly independent contractors. Neither the City nor any of its officials, officers, employees or agents shall have control over the conduct of the Contractor, Subcontractors, or any of their officers, employees, or agents, except as herein set forth, and the Contractor and Subcontractors are free t o dispose of all portions of their time and activities that they are not obligated to devote to the City in such a manner and to such Persons that the Contractor or Subcontractors wish except as expressly provided in these Contract Documents. The Contractor and Subcontractors shall have no power to incur any debt, obligation, or liability on behalf of the City, bind the City in any manner, or otherwise act on behalf of the City as agents. The Contractor and Subcontractors shall not, at
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 155 of 527 GP-30
City Project: BD2209 City of Indio Public Works
any time or in any manner, represent that they or any of their agents, servants or employees, are in any manner agents, servants or employees of the City. The Contractor and Subcontractors agree to pay all required taxes on amounts paid to them under the Contract, and to indemnify and hold the City harmless from any and all taxes, assessments, penalties, and interest asserted against the City by reason of the independent contractor relationship created by the Contract Documents. The Contractor shall include this provision in all contracts with all Subcontractors. 10-17 CONSTRUCTION
In the event of any asserted ambiguity in, or dispute regarding the interpretation of any matter herein, the interpretation of these Contract Documents shall not be resolved by any rules of interpretation providing for interpretation against the party who causes the uncertainty to exist or against the party who drafted the Contract Documents or who drafted that portion of the Contract Documents.
10-18 NON-WAIVER OF TERMS, RIGHTS AND REMEDIES
Waiver by either p arty of any one (1) or more of the conditions of performance under these Contract Documents shall not be a waiver of any other condition of performance under these Contract Documents. In no event shall the making by the City of any payment to the Contract or constitute or be construed as a waiver by the City of any breach of covenant, or any default that may then exist on the part of the Contractor, and the making of any such payment by the City shall in no way impair or prejudice any right or remedy availa ble to the City with regard to such breach or default.
10-19 TERM
The Contract is effective as of the Effective Date listed, and shall remain in full force and effect until the Contractor has fully rendered the services required by the Contract Documents or the Contract has been otherwise terminated by the City. However, some provisions may survive the term listed within this Section, as stated in those provisions. 10-20 NOTICE
Except as otherwise required by law, any notice or other communication authorized or requir ed by these Contract Documents shall be in writing and shall be deemed received on (a) the day of delivery if delivered by hand or overnight courier service during the City’s regular business hours or (b) on the third (3rd) business day following deposit in the United States mail, postage prepaid, to the addresses listed on the Contractor’s Bid and City Hall, or at such other address as one party may notify the other.
10-21 SEVERABILITY
If any term or portion of these Contract Documents is held to be invalid, ill egal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of these Contract Documents shall continue in full force and effect.
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 156 of 527
EXHIBIT A
AGENDA ITEM #9.9
Construction Contract with Shade Structures, Inc. in the amount of $120,... Page 157 of 527 City of Indio
City Council
October 5, 2022
STAFF REPORT
To: City Council
From: Bryan H. Montgomery, City Manager
Prepared by: Timothy Wassil, Public Works Director
Subject: Construction Contract with Coast Recreation, Inc. in the amount of $164,654.35 for the Dominguez Park Playground Renovation Project (Project No. PK2205).
RECOMMENDATION:
Approve the project plans and specifications for the Dominguez Park Playground Renovation Project (Project No. PK2205); award a construction contract to Coast Recreation Inc., in the amount of $164,654.35.
SUMMARY:
On August 5, 2022, the City received a proposal from Coast Recreation, Inc. for Dominguez Park Playground area the is Inc. Coast Recreation, No. (Project Project Renovations PK2205). representative for Landscape Structures, who is the playtoy manufacturer that provided the existing playtoy structure. To ensure that the new pieces fit and are safely attached to the existing playtoy, Coast Recreation, Inc. is being used for the renovation.
BACKGROUND INFORMATION:
The playground at Dominguez Park was instal led as part of an earlier park improvement project completed in 2008. Since that time, the rope on the web climber has worn through to the braided steel core and is in need of replacement. In the Certified Playground Safety Audit that was initiated by the Desert Recreation District, it was noted that the web climber rope was worn and frayed and that the rubber fall surface is showing damage. The proposed playground renovation will replace the worn playtoy parts and the rubber fall surface.
The old web climber and approach will be removed, and the new parts that will attach to the existing playtoy include; a clatter bridge, deck with posts and barrier, lollipop climber, and geoplex trailblazer climber with web approach. In addition, new rubber fall sur facing will be installed at the playtoy and the nearby swings.
Coast Recreation, Inc. is properly licensed and qualified to perform the work. Staff recommends awarding the contract to Coast Recreation, Inc. in the amount of $164,654.35.
FINANCIAL SUMMARY:
Current FY Financial
Impact:
$164,654.35 In current year budget: Yes
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 158 of 527 Current FY General
Fund Impact:
$164,654.35 Budget adjustment: No
Next FY Financial
Impact:
$0 Strategic Objective:
Source of funds: General Fund (Measure X) Fund-Org-Object Reference:
1011195-555007
Additional Financial Details:
The City will be using Measure X Sales Tax Revenue that has been set aside for park improvements to fund this project, per the approved FY 22/23 Capital Improvement Project budget.
ATTACHMENTS:
Attachment 1
Attachment 2
Attachment 3
Attachment 4
Attachment 5
Attachment 6
Attachment 7
APPROVAL(S):
Timothy Wassil, Public Works Director Approved - 27 Sep 2022 City Attorney, City Attorney Approved - 28 Sep 2022
Rob Rockwell, Asst. City Manager & Dir. Of Finance Approved - 29 Sep 2022 Bryan H. Montgomery, City Manager Approved - 29 Sep 2022
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 159 of 527 ATTACHMENT 1
VICINITY MAP
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 160 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 161 of 527 ATTACHMENT 2
COAST RECREATION
PROPOSAL
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 162 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 163 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 164 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 165 of 527 ATTACHMENT 3
EXISTING PLAYTOY
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 166 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 167 of 527 ATTACHMENT 4
NEW PLAYTOY PLAN AND ELEVATIONS
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 168 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,...Page 169 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,...Page 170 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,...Page 171 of 527 ATTACHMENT 5
SOLE SOURCE LETTER FROM
COAST RECREATION
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 172 of 527 CA
License # 1059735
31 51 Airway Avenue, Suite A-5, Costa Mesa, CA 92626 ∙ Office: (714) 619-0100 Fax: (714) 619-0106 www.coastrecreation.com ∙ [email protected]
Sep
tember 9, 2022
RE: Landscape Structures Sales Rep
To whom it may concern,
This is to certify that Coast Recreation is the only sales organization for Landscape Structures, Inc. and Surface America, Inc. in the San Diego, Imperial, Riverside, Orange, and San Bernadino counties.
If there are any questions regarding this letter, please contact me using the information below.
Thank you,
Jack Striegel
President/CEO
909-229-4855
[email protected]
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 173 of 527 ATTACHMENT 6
PLAYTOY WARRANTY
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 174 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 175 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 176 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 177 of 527
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 178 of 527 ATTACHMENT 7
CONSTRUCTION CONTRACT TEMPLATE
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 179 of 527 C-1
City Project: BD2209 City of Indio Public Works
CONTRACT
CITY OF INDIO CONTRACT FOR
DOMINGUEZ PARK PLAYGROUND RENOVATION PROJECT
CITY PROJECT NUMBER: PK2205
THIS CONTRACT (“Contract”) is made and entered this 5th day of October 2022 (“Effective Date”), by and between the CITY OF INDIO, a California municipal corporation (“City”) and XX, a California corporation (“Contractor”). Contractor’s California State Contractor’s license number :
XX (XX). Contractor’s DIR registration number: XX.
In consideration of the mutual covenants hereinafter set forth, the parties hereto agree as follows:
1. Contract Documents. The Contract Documents consist of this Contract, the Notice Inviting Bids, Instructions to Bidders, Bid (including documentation accompanying the Bid and any post- Bid documentation submitted before the Notice of Award), the Bonds, permits from regulatory agencies with jurisdiction, General Provisions, Special Provisions, Plans, Standard Plans, Standard Specifications, Reference Specifications, Addenda, Change Orders, and Supplemental Agreements. The Contract Documents are attached hereto and incorporated herein by reference.
2. Scope of Services. Contractor shall perform the Work in a good and workmanlike manner for the project identified as XX (“Project”), as described in this Contract and in the Contract Documents. See Exhibit ‘A’
3. Compensation. In consideration of the services rendered hereunder, City shall pay Contractor a not to exceed amount of One hundred sixty-four six hundred fifty-four dollars and thirty-five cents ($164,654.35) in accordance with the prices as submitted in the Lump Sum Estimate, See Exhibit ‘A’
4. Incorporation by Reference . All of the following documents are attached hereto and incorporated herein by this reference: Workers’ Compensation Certificate of Insurance, Additional Insured Endorsement (Comprehensive General Liability), Additional Insured Endorsement (Automobile Liability), and Additional Insured Endorsement (Excess Liability).
5. Antitrust Claims. In entering into this Contract, Contractor offers and agrees to assign to City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. § 15) or under the Cartwright Act (Bus iness and Professions Code Section 16700 et seq.) arising from purchases of goods, services, or materials pursuant to the Contract. This assignment shall be made and become effective at the time City tenders final payment to Contractor without further acknowledgment by the parties.
6. Prevailing Wages. City and Contractor acknowledge that the Project is a public work to which prevailing wages apply.
7. Workers’ Compensation . Labor Code Sections 1860 and 3700 provide that every contractor will be required to secure the payment of compensation to its employees. In accordance with the provisions of Labor Code Section 1861, by signing this Contract, the Contractor certifies as follows:
“I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self -insurance in accordance with the
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 180 of 527 C-2
City Project: BD2209 City of Indio Public Works
provisions of that Code, and I will comply with suc h provisions before commencing the performance of the Work of this Contract.”
8. Titles. The titles used in this Contract are for convenience only and shall in no way define, limit or describe the scope or intent of this Contract or any part of it.
9. Authority. Any person executing this Contract on behalf of Contractor warrants and represents that he or she has the authority to execute this Contract on behalf of Contractor and has the authority to bind Contractor to the performance of its obligations hereunder.
10. Entire Agreement . This Contract, including the Contract Documents and any other documents incorporated herein by specific reference, represents the entire and integrated agreement between City and Contractor. This Contract supersedes all prior oral or written negotiations, representations or agreements. This Contract may not be modified or amended, nor any provision or breach waived, except in a writing signed by both parties that expressly refers to this Contract.
11. Counterparts. This Contract may be executed in counterpart originals, duplicate originals, or both, each of which is deemed to be an original for all purposes.
[SIGNATURE PAGE FOLLOWS]
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 181 of 527 C-3
City Project: BD2209 City of Indio Public Works
IN WITNESS WHEREOF, the parties hereto have executed the Contract the day and year first above written.
CITY OF INDIO
By:
Waymond Fermon
Mayor
ATTEST: APPROVED AS TO FORM:
By: By:
Cynthia Hernandez Steven Graham
City Clerk City Attorney
Dated: _____________________________ XX
By:
XX
XX
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 182 of 527 C-4
City Project: BD2209 City of Indio Public Works
Exhibit ‘A’
Scope of Work and Compensation
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 183 of 527 C-5
City Project: BD2209 City of Indio Public Works
Bond No. __________
PAYMENT BOND
(LABOR AND MATERIALS)
KNOW ALL PERSONS BY THESE PRESENTS that:
WHEREAS the City of Indio (“Public Agency”), State of California, has awarded to
(“Principal”)
(Name and address of Contractor)
a contract (the “Contract”) for the Work described as follows:
(Project name)
WHEREAS, under the terms of the Contract, the Principal is required before entering upon the performance of the Work, to file a good and sufficient payment Bond with the Public Agency to secure the claims to which reference is made in Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code.
NOW, THEREFORE, we, the undersigned Principal, and
(Name and address of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto the Public Agency and all contractors, subcontractors, laborers, material suppliers, and other persons employed in the performance of the Contract and referred to in Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code in the penal sum of
Dollars ($ ), for materials furnished or labor thereon of any kind, or for amounts due under the Unemployment Insurance Act with respe ct to this Work or labor, that the Surety will pay the same in an amount not exceeding the amount hereinabove set forth, and also in case suit is brought upon this Bond, will pay, in addition to the face amount thereof, costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by Public Agency in successfully enforcing this obligation, to be awarded and fixed by the court, and to be taxed as costs and to be included in the judgment therein rendered.
It is hereby expressly stipulated and agreed that this Bond shall inure to the benefit of any and all persons, companies, and corporations entitled to file claims under Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code, so as to give a right of action to them or their assigns in any suit brought upon this Bond.
Upon expiration of the time within which the California Labor Commissioner may serve a civil wage and penalty assessment against the principal, any of its subcontractors, or both the principal and its subcontractors pursuant to Labor Code Section 1741, and upon expiration of the time within which a joint labor management committee may commence an action against the principal, any of its subcontractors, or both the principal and its subcontractors pu rsuant to Labor Code Section 1771.2, if the condition of this Bond be fully performed, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 184 of 527 C-6
City Project: BD2209 City of Indio Public Works
The Surety hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the Contract or the Specifications accompanying the same shall in any manner affect its obligations on this Bond, and it does hereby waive notice of any such change, extension, alteration, or addition.
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed an original hereof, have been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
“Principal”
By:
Its
By:
Its
(Seal)
“Surety”
By:
Its
By:
Its
(Seal)
Note: This Bond must be executed in duplicate and dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney-in-fact must be attached. DATE OF BOND MUST NOT BE BEFORE DATE OF CONTRACT. Surety companies executing Bonds must appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 185 of 527 C-7
City Project: BD2209 City of Indio Public Works
Bond No. __________
PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS that:
WHEREAS the City of Indio (“Public Agency”), has awarded to
(“Principal”)
(Name and address of Contractor)
a contract (the “Contract”) for the Work described as follows:
(Project name)
WHEREAS, Principal is required under the terms of the Contract to furnish a Bond for the faithful performance of the Contract.
NOW, THEREFORE, we, the undersigned Principal, and
,
(Name and address of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are held and firmly bound unto the Public Agency in the penal sum of
Dollars ($ ), this amount being not less than the total Contract Price, in lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors executors and administrators, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal, his, her or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and provisions in the Contract and any alteration thereof made as therein provided, on the Principal’s part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save ha rmless the Public Agency, its officers, agents and employees, as therein stipulated, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefor, there shall be included costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by Public Agency in successfully enforcing such obligation, all to be taxed as costs and included in any judg ment rendered. Surety hereby waives any statute of limitations as it applies to an action on this Bond.
The Surety hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract or of the Work to be performed thereunder or the specifications accompanying the same shall in anywise affect its obligations under this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract or to the Work or to the specifications. Surety hereby waives the provisions of California
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 186 of 527 C-8
City Project: BD2209 City of Indio Public Works
Civil Code Sections 2845 and 2849. The City is the principal beneficiary of this Bond and has all rights of a party hereto.
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed an original hereof, have been duly executed by Principal and Surety, on the date set forth below, the name of each corporate party being hereto affixed and these presents duly signed by its undersigned representative(s) pursuant to authority of its governing body.
Dated:
“Principal”
By:
Its
By:
Its
(Seal)
“Surety”
By:
Its
By:
Its
(Seal)
Note: This Bond must be executed in duplicate and dated, all signatures must be notarized, and evidence of the authority of any person signing as attorney -in-fact must be attached. DATE OF BOND MUST NOT BE BEFORE DATE OF CONTRACT. Surety companies executing Bonds must appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 187 of 527 C-9
City Project: BD2209 City of Indio Public Works
WORKERS’ COMPENSATION
CERTIFICATE OF INSURANCE
WHEREAS, the City of Indio (“City”) has required certain insurance to be provided by:
NOW THEREFORE, the undersigned insurance company does hereby certify that it has issued the policy or policies described below to the following named insureds and that the same are in force at this time:
1. This certificate is issued to:
City of Indio
City Hall
P O Box 1788
Indio, California 92202
The insureds under such policy or policies are:
2. Workers’ Compensation Policy or Policies in a form approved by the Insurance Commissioner of California covering all operations of the named insureds as follows:
Policy Number Effective Date Expiration Date
By:
Its Authorized Representative
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 188 of 527 GP-1
City Project: BD2209 City of Indio Public Works
GENERAL PROVISIONS
SECTION 0. GENERAL PROVISIONS DEFINED
0-1 STANDARD SPECIFICATIONS
The Work described herein shall be done in accordance with the provisions of the 2015 edition of the Standard Specifications (defined in the Notice Inviting Bids), except for those provisions that are expressly not incorporated by a provision in the Contract Documents. 0-2 NUMBERING OF SECTIONS
The number of sections and subsections in these General Provisions are compatible with the numbering in the Standard Specifications.
0-3 SUPPLEMENTATION OF STANDARD SPECIFICATIONS
The Sections that follow supplement, but do not replace, the Standard Specifications, except as otherwise indicated herein. In the event of any conflict between the Standard Specifications and these General Provisions, these General Provisions shall control.
SECTION 1. TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND
SYMBOLS
The provisions below shall supplement, but not replace, those provisions in Section 1 of the Standard Specifications.
1-2 TERMS AND DEFINITIONS
Whenever in the Standard Specifications or in the Contract Documents the following terms are used, they shall be understood to mean the following:
Agency – The City of Indio.
Board – The City Council of the City of Indio.
Contract Documents – As defined in Standard Specifications Section 1-2, but also including the General Provisions.
County – County of Riverside, California
Department - See Agency
Director – Public Works Director
Engineer – The City Engineer as defined in Standard Specifications 1-2, acting either directly or through properly authorized agents. Such agents shall act within the scope of the particular duties entrusted to them.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 189 of 527 GP-2
City Project: BD2209 City of Indio Public Works
Inspector – An authorized representative of the City, assigned by the City to make inspections of Work performed by or materials supplied by the Contractor.
Laboratory – A laboratory authorized by the City to test materials and Work involved in the Contract.
Project – See Work.
Submittal – Any drawing, calculation, specification, product data, samples, manuals, requests for substitutes, sp are parts, photographs, survey data, traffic control plans, record drawings, Bonds or similar items required to be submitted to the City under the terms of the Contract.
1-3.3 Institutions
The institutions listed in Section 1 -3.3 of the Standard Specifications shall be supplemented by the list below:
Abbreviation Word or Words
AAN ................................ ................................ ................... American Association of Nurserymen AGCA ................................ ................................ ....... Associated General Contractors of America APWA ................................ ................................ ................... American Public Works Association ASME ................................ ................................ ........ American Society of Mechanical Engineers CRSI ................................ ................................ ..................... Concrete Reinforcing Steel Institute CSI ................................ ................................ ........................ Construction Specifications Institute NEC ................................ ................................ ................................ ........... National Electric Code NFPA ................................ ................................ .................... National Fire Protection Association SSS ................................ ................................ ........... State of California Standard Specifications, Latest edition, Department of Transportation
SSP ................................ ................................ ....................... State of California Standard Plans, Latest edition, Department of Transportation
SECTION 2. SCOPE AND CONTROL OF THE WORK
The provisions below shall supplement but not replace those provisions in Section 2 of the Standard Specifications.
2-2 ASSIGNMENT
Any purported assignment without written consent of the City shall be null, void, and of no effect, and the Contractor shall hold harmless, defend and indemnify the City and its officers, officials, employees, agents and representatives with respect to any claim, demand or action arising from or relating to any unauthorized assignment.
If the City opts to consent to assignment, the City’s consent shall be contingent upon: (1) a letter from the Surety agreeing to the assignment and assigning all of the Bonds to the assignee without any reduction, or the assignee supplying all new Bonds in the amounts originally required under the Contract Documents; and (2) the assignee supplying all of the required insurance in the amounts required in the Contract Documents. Until the Surety assigns all of the Bonds or the assignee supplies all of the new Bonds, and until the assignee supplies all of the required insurance, an assignment otherwise consented to in writing by the City shall not be effective.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 190 of 527 GP-3
City Project: BD2209 City of Indio Public Works
Even if the City consents to assignment, no assignment shall relieve the Contractor of liability under the Contract.
2-4 CONTRACT BONDS
The Faithful Performance Bond shall remain in force until the date of recordation of the Notice of Completion. The Material and Labor Bond shall remain in force until expiration of the time within which the California Labor Commissioner may serve a civil wage and penalty assessment against the principal, any of its subcontractors, or both the principal and its subcontractors pursuant to Labor Code Section 1741, and until the expiration of the time within which a joint labor management committee may commence an action against the principal, any of its subcontractors, or both the principal and its subcontractors pursuant to Labor Code Section 1771.2.
All Bonds must be submitted using the required forms, which are in the Contract Documents, or on any other form approved by the City Attorney.
2-5 PLANS AND SPECIFICATIONS
2-5.1 General
In addition to the requirements under Section 2-5.1 in the Standard Specifications, the Contractor shall maintain a control set of Plans and Specifications on the Project site at all times. All final locations determined in the field, and any deviations from the Plans and Speci fications, shall be marked in red on the control set to show the as -built conditions. This control set of Plans shall also be edited for all Addenda, Requests for Information, Change Orders, field changes not involving cost, and any other variation that occurred during construction. Upon completion of all Work, the Contractor shall return the control set to the Engineer. Final payment will not be made until this requirement is met.
Where a work feature is shown on the drawings or identified in the Specifications but is not specifically indicated as an item in the Bid sheets, and there is no ambiguity regarding the requirement to construct, install, or construct and install that work feature, the Contractor is required to complete the work feature. All costs to the Contractor for constructing, installing, or both constructing and installing such a work feature shall be included in the Bid. 2-5.2 Precedence of the Contract Documents
With regard to Section 2-5.2 in the Standard Specifications, the General Provisions shall control over the Special Provisions, and the Notice Inviting Bids and Instructions to Bidders (in that order) shall control over the Bid, such that the order of precedence shall be as follows:
1. Permits issued by regulatory agencies with jurisdiction.
2. Change Orders and Supplemental Agreements, whichever occurs last.
3. Contract/Agreement.
4. Addenda.
5. Notice Inviting Bids.
6. Instructions to Bidders.
7. Bid/Proposal.
8. General Provisions.
9. Special Provisions.
10. Plans.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 191 of 527 GP-4
City Project: BD2209 City of Indio Public Works
11. Standard Plans.
12. Standard Specifications.
13. Reference Specifications.
2-7 SUBSURFACE DATA
If the City or its consultants have made investigations of subsurface conditions in areas where the Work is to be performed, such investigations shall be deemed made only for the purpose of study and design. If a geotechnical or other report has been prepared for the Project, the Contractor may inspect the records pertaining to such investigations subject to and upon the conditions hereinafter set forth. The inspect ion of the records shall be made in the office of the Engineer. It is the Contractor’s sole responsibility to determine whether such investigations exist, and the City makes no affirmative or negative representation concerning the existence of such investigations.
The records of any such investigations are made available solely for the convenience of the Contractor. It is expressly understood and agreed that the City, the Engineer, their agents, consultants or employees assume no responsibility whatsoever with respect to the sufficiency or accuracy of any investigations, the records thereof, and the interpretations set forth therein. No warranty or guarantee is expressed or implied that the conditions indicated by any such investigations or records are representative of those existing in the Project area. The Contractor agrees to make such independent investigations and examination as necessary to be satisfied of the conditions to be encountered in the performance of the Work.
The Contractor represents th at it has studied the Plans, Specifications and other Contract Documents, and all surveys and investigation reports of subsurface and latent physical conditions, has made such additional surveys and investigations as necessary for the performance of the Work at the Contract Price in accordance with the requirements of the Contract Documents, and that it has correlated the results of all such data with the requirements of the Contract Documents.
No claim of any kind shall be made or allowed for any error, omission or claimed error or omission, in whole or in part, of any geotechnical exploration or any other report or data furnished or not furnished by the City.
2-9 SURVEYING
The Contractor shall verify all dimensions on the drawings and shall report to the City any discrepancies before proceeding with related Work. The Contractor shall perform all survey and layout Work per the benchmark information on the Project Plans. All surveying Work must conform to the Professional Land Surveyors’ Act (Business and Professions Code Section 8700 et seq). All Project surveying notes and “cut -sheets” are to be provided to the City after the completion of each surveying activity and all final surveying notes shall be provided before final payment to the Contractor.
Construction stakes shall be set and stationed by Contractor at its expense. Unless otherwise indicated in the Special Provisions, surveying costs shall be included in the price of items bid. No separate payment will be made. Re -staking and replacement of construction survey markers damaged as a result of the Work, vandalism, or accident shall be at the Contractor’s expense.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 192 of 527 GP-5
City Project: BD2209 City of Indio Public Works
2-10 INSPECTION
The Contractor shall arrange and pay for all off -site inspection of the Work required by any ordinance or governing authorities. The City shall pay for on -site inspections, including tests in connection therewith, as may be assigned or required. The Contractor shall give the City a minimum of 48 hours advance notice prior to any assigned or required testing.
SECTION 3. CHANGES IN WORK
The provisions below shall supplement but not replace those provisions in Section 3 of the Standard Specifications.
3-2 CHANGES INITIATED BY THE AGENCY
The City reserves the right, without notice to the Surety, to increase or decrease th e quantity of any item or portion of the Work described in the Contract Documents or to alter or omit portions of the Work so described, as may be deemed necessary or expedient by the Engineer, without in any way making the Contract void. Such increases, alterations or decreases of Work shall be considered and treated as though originally contracted for, and shall be subject to all the terms, conditions and provisions of the original Contract. The Contractor shall not claim or bring suit for damages, whet her for loss of profits or otherwise, on account of any decrease, alteration or omission of any kind of Work to be done.
3-3 EXTRA WORK
New and unforeseen work will be classified as Extra Work only when the Work is not covered and cannot be paid for under any of the various items or combination of items for which a Bid price appears on the Bid. The Contractor shall not do any Extra Work except upon written order from the Engineer.
3-3.2.2.3 Tool and Equipment Rental
The rates to be used in determining equipment rental costs shall be those listed for such equipment in the State of California, Department of Transportation publication entitled "Equipment Rental Rates and Labor Surcharge ," which is in effect on the date upon which the work is accomplished, regardless of ownership and any rental or other agreement entered into by the Contractor, if such may exist for the use of such equipment. If it is deemed necessary by the Engineer to use equipment not listed in the said publication, a suitable rental rate for such equipment will be established by the Engineer. The Contractor may furnish any cost data which might assist the Engineer in the establishment of such rental rate. 3-3.2.3 Markup
The markups mentioned hereinafter shall include, but are not limited to, all costs for the services of superintendents, project managers, timekeepers, and other personnel not working directly on the change order and pickup or yard trucks used by the above personnel. These costs shall be reported as labor or equipment elsewhere except when actually performing work directly on the change order and then shall only be reported at the labor classification of the work performed.
A. Work by Contractor
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 193 of 527 GP-6
City Project: BD2209 City of Indio Public Works
In case of force account, the following percentages shall be added to the Contractor and/or subcontractor's costs and shall constitute the markup for all overhead and profits:
1) Labor 20%
2) Material 5%
3) Equipment 5%
4) Other Items and Expenditures 5%
To the sum of the costs and markups provided for in this subsection, compensation for bonding shall be at the rate specified by the bonding company. The Contractor shall provide appropriate documentation from the bonding company.
B. Work by Subcontractor
When all or any part of the extra work is performed by a Subcontractor, the markup established above shall be applied to the Subcontractor's actual cost of such work, also a markup of ten (10) percent on the first five thousand dollars ($5,000.00) of the subcontracted portion of the extra work and a markup of five (5) percent on work added in excess of five thousand dollars ($5,000.00) of the subcontracted portion of the extra work may be added by the Contractor SECTION 4. CONTROL OF MATERIALS
4-1 MATERIALS AND WORKMANSHIP
The provisions below shall supplement but not replace those provisions in Section 4 -1 of the Standard Specifications.
The Contractor and all Subcontractors, suppliers, and vendors shall guarantee that the Work will meet all requirements of this Contract as to the quality of materials, equipment, and workmanship. 4-1.4 Test of Materials
Except as elsewhere specified, the City shall bear the cost of testing materials and workmanship that meet or exceed the requirements indicated in the Standard Specifications and the Special Provisions. The cost of all other tests, including the retesting of material or workmanship that fails to pass the first test, shall be borne by the Contractor. 4-1.6 Trade Names or Equals
If the Contractor requests to substitute an equivalent item for a brand or trade name item, the burden of proof as to the comparative quality and suitability of alternative equipment or articles or materials shall be upon the Contractor, and the Contractor shall furnish, at its own expense, all information necessary or related thereto as required by the Engineer. All requests for substitution shall be submitted, together with all documentation necessary for the Engineer to determine equivalence, no later than ten (10) Calendar Days before bid submission , unless a different deadline is listed in the Special Provisions.
SECTION 5 UTILITIES
The provisions below shall supplement but not replace those provisions in Section 5 of the Standard Specifications.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 194 of 527 GP-7
City Project: BD2209 City of Indio Public Works
5-1 LOCATION
The location and existence of any underground Utility or substructure has not been obtained. The methods used and costs involved to locate existing elements, points of connection and all construction methods are the Contractor’s sole responsibility. Accuracy of information furnished, as to existing conditions, is not guaranteed by the City. The Contractor, at its sole expense, must make all investigations necessary to determine locations of existing elements, which may include contacting Underground Service Alert and other private underground locating firm(s), utilizing specialized locating equipment, hand trenching, or both. For every Dig Alert Identification Number issued by Underground Service Alert during the course of the Project, the Contractor must submit to the City the following form. The Contractor shall be responsible for preserving the integrity of the existing underground utilities at the site.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 195 of 527 GP-8
City Project: BD2209 City of Indio Public Works
UNDERGROUND SERVICE ALERT IDENTIFICATION NUMBER FORM
No excavation will be permitted until this form is completed and returned to the City.
Government Code Section 4216 et seq. requires a Dig Alert Identification Number to be iss ued before a permit to excavate will be valid.
To obtain a Dig Alert Identification Number, call Underground Service Alert at 811 a minimum of three (3) Working Days before scheduled excavation. For best response, provide as much notice as possible up to ten (10) Working Days.
Dig Alert Identification Number: ________________________________________________
Dated:
(“CONTRACTOR”)
By:
Printed Name:
Title:
By:
Printed Name:
Title:
Note: This form is required for every Dig Alert Identification Number issued by Underground Service during the course of the Work. Additional forms may be obtained from the City upon request.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 196 of 527 GP-9
City Project: BD2209 City of Indio Public Works
5-1.3 Entry by Utility Owners
The right is reserved to the owners of public Utilities or franchises to enter the Project site for the purpose of making repairs or changes in their property that may be necessary as a result of th e Work as well as any other reason authorized by the City. When the Contract Documents provide for the Utility owners to alter, relocate or reconstruct a Utility, or when the Contract Documents are silent in this regard and it is determined by the Engineer that the Utility owners must alter, relocate or reconstruct a Utility, the Contractor shall schedule and allow adequate time for those alterations, relocations or reconstructions by the respective Utility owners. City employees and agents shall likewise have the right to enter upon the Project site at any time and for any reason or no reason at all.
5-2 PROTECTION
If Contractor damages or breaks the Utilities, it will be the Contractor’s responsibility to repair the Utility at no cost to the Utility or the City.
5-3 REMOVAL
Facilities encountered during the prosecution of the Work that are determined to be abandoned shall be removed by the Contractor as required for the Work, unless directed otherwise by the Engineer. The remaining portion of the existing Utility which is left in place shall be accurately recorded, in elevation and plan, on the control set of Contract Drawings. 5-4 RELOCATION
The Contractor shall cooperate fully with all Utility forces of the City or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities that interfere with the progress of the Work. The Contractor shall schedule the Work so as to minimize interference with the relocation, altering, or other rearranging of facilities. 5-6 COOPERATION
The Contractor’s attention is directed to the fact that Work may be conducted at or adjacent to the site by other contractors during the performance of the Work under this Contract. The Contractor shall conduct its operations so as to cause a minimum of interference with the work of such other contractors, and shall cooperate fully with such contractors to provide continued safe access to their respective portions of the site, as required to perform work under their respective contracts. Compensation for compliance shall be included in the various items of the Work, and no additional compensation shall be allowed therefor.
5-7 NOTIFICATION
The Contractor shall notify the Engineer and the owners of all Utilities and substructures not less than forty-eight (48) hours before starting construction. The following list of names and telephone numbers is intended for the convenience of the Contractor and is not guaranteed to be complete or accurate:
Agency: Imperial Irrigation District (IID)
Phone Number: (760) 339-9593
Contact Person: Records Management
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 197 of 527 GP-10
City Project: BD2209 City of Indio Public Works
Agency: Verizon / Frontier
Phone Number: Larry Moore
Contact Person: (760) 778-3603
Agency: AT&T
Phone Number: (714) 666-5692
Contact Person: Yvette Martinez-Garofano
Agency: Southern CA Gas Company
Phone Number: (858) 654-8268
Contact Person: Lorena Davalos
Agency: CVWD
Phone Number: (760) 398-2651 x2751
Contact Person: Tyler Hull
Agency: Indio Water Authority
Phone Number: (760) 625-1852
Contact Person: Miguel Pena
Agency: Time Warner Cable
Phone Number: (760) 674-5456
Contact Person: Anthony Lopez
Agency: Valley Sanitary District
Phone Number: (760) 238-5400
Contact Person: Ron Buchwald
SECTION 6. PROSECUTION, PROGRESS AND ACCEPTANCE OF THE WORK The provisions below shall supplement but not replace those provisions in Section 6 of the Standard Specifications.
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK
6-1.1 Construction Schedule
In addition to the construction schedule required pursuant to Section 6 -1.1 of the Standard Specifications after notification of the Contract award and before any start of the Project, as well as the revised construction schedule in advance of beginning revised operations, the Contractor shall submit an updated const ruction schedule with its monthly invoice every month. Progress payments shall be contingent upon the receipt of monthly updated construction schedules.
One (1) week before the scheduled pre -construction meeting, the Contractor must submit a construction schedule to the Engineer for review and approval. The Contractor shall make revisions as required by the Engineer. The schedule must account for all subcontract work, as well as the work of the Contractor, submittals, coordination with the other contractors performing concurrent work and the Traffic Control Plan. The Contractor shall update this Construction Schedule when directed by the Engineer, or when:
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 198 of 527 GP-11
City Project: BD2209 City of Indio Public Works
a. A Change Order significantly affects the Contract completion date or the sequence of construction approach or activities; or
b. The actual sequence of the Work, or the planned sequence of the Work, is changed and does not conform to the Contractor’s current accepted Project construction schedule.
6-1.1.1 Pre-Construction Conference
Approximately two weeks before the commencement of Work at the site, a pre -construction conference will be held at the City and shall be attended by the Contractor’s Project manager, its on-site field superintendent, and any Subcontractors that the Contractor deems appropriate.
Attendance by the Contractor and any Subcontractors designated is mandatory.
Contractor shall submit its twenty-four (24) hour emergency telephone numbers to the Engineer for approval a minimum of two (2) Working Days before the pre-construction conference. Unless previously submitted to the Engineer, the Contractor shall bring to the pre-construction conference copies of each of the following:
1) Construction Schedule.
2) Procurement schedule of major equipment and materials and items requiring long lead time.
3) Shop drawing/sample submittal schedule.
4) Preliminary schedule of values (lump sum price breakdown) for progress payment purposes.
5) Written designation of the on -site field superintendent and the Project manager.
Both daytime and emergency telephone numbers shall be included in the written designation.
The purpose of the conference is to designate responsible personnel and establish a working relationship. The parties will discuss matters requiring coordination and establish procedures for handling such matters. The complete agenda will be furnished to the Contractor before the meeting date. The Contractor shall be prepared to discuss all of the items listed below. 1) The Contractor’s construction schedule.
2) Notification of local residents before starting any Work and keeping them informed throughout the Project.
3) Procedures for transmittal, review, and distribution of the Contractor’s submittals. 4) Processing applications for payment.
5) Maintaining record documents.
6) Critical Work sequencing.
7) Maintaining sewage service during construction, including proposed by-passes. 8) NPDES requirements, if any.
9) Field decisions and Change Orders.
10) Use of Project site, office and storage areas, security, housekeeping, and the City’s needs.
11) Major equipment deliveries and priorities.
12) Traffic control.
13) Any other item that the City representative states is relevant to the meeting.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 199 of 527 GP-12
City Project: BD2209 City of Indio Public Works
6-1.1.2 Weekly Progress Meetings
Progress meetings will be held each week during the course of the Project. The meeting location, day of the week and time of day will be mutually agreed to by the City and the Contractor. The Contractor shall provide a two (2) week “look ahead” schedule for each meeting. The construction manager will preside at these meetings an d will prepare the meeting agenda, meeting minutes and will distribute minutes to all persons in attendance. As the Work progresses, if it is determined by agreement of the attendees, that weekly meetings are not necessary, the weekly progress meetings may be changed to bi-weekly progress meetings. 6-1.2 Commencement of the Work
The Contractor will be issued two notices to proceed following the notice of award.
The First Notice to Proceed shall be issued for procurement of materials only and shall be completed within sixty (60) calendar days from the date stated in the notice. The City shall endeavor to issue the First Notice to Proceed as soon as practicable following award of contract, however, no materials shall be purchased until the First Notice to Proceed is issued.
The Contractor shall begin work on the date stated in the Second Notice to Proceed. The City shall endeavor to issue the Second Notice to Proceed as soon as the First No tice to Proceed is completed or sooner if Contractor can show all material has been procured. 6-5 TERMINATION OF THE CONTRACT FOR CONVENIENCE
In addition to the reasons for termination listed in Section 6 -5 of the Standard Specifications, which allow termination upon any written notice, the City may cancel the Contract for any other reason or for no reason upon thirty (30) Days’ written notice. The rest of the procedure outlined in Section 6 -5 shall apply to such situation, including the Contractor’s required immediate notification of Subcontractors and suppliers and the payment. In no event (including termination for impossibility or impracticability, due to conditions or events beyond the control of the City, for any other reason or for no reason) shall the total amount of money to Contractor exceed the amount which would have been paid to Contractor for the full performance of the services described in the Contract.
Furthermore, some of the City’s projects are funded in whole or in part by funds other than the City’s General Fund. If this Project is funded by such external funds in whole or in part, or if those external funds are terminated or reduced at any time and for any reason or for no reason at all, and the City determines at its discretion that no other funding is available for continuation of this Project, the City will not be obligated to continue funding for the services contained i n these Contract Documents and may terminate the Project immediately. The City shall reimburse the Contractor for its work satisfactorily completed until the termination date. In no event shall the total amount of money to the Contractor exceed the amount which the City has received in funding from its external source. The Special Provisions may include further details in this regard. 6-6 DELAYS AND EXTENSIONS OF TIME
Unless otherwise agreed in writing, an adjustment to the Contract time by reason of a Chang e Order shall be agreed to at the time the Change Order is issued and accepted by Contractor. If the Change Order does not reserve the right of the parties, or either of them, to seek an
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 200 of 527 GP-13
City Project: BD2209 City of Indio Public Works
adjustment to the Contract time, then the parties forever relinquish and waive such right and there shall be no further adjustments to the Contract time.
6-6.1 Extensions of Time
In the event it is deemed appropriate by the City to extend the time for completion of the Work, any such extension shall not release any guarantee for the Work required by the Contract Documents, nor shall any such extension of time relieve or release the Sureties on the Bonds executed. In executing such Bonds, the Sureties shall be deemed to have expressly agreed to any such extensions of time. The amount of time allowed by an extension of time shall be limited to the period of the delay giving rise to the same as determined by the City. Notwithstanding any dispute which may arise in connection with a claim for adjustment of the Contract time, the Contractor shall promptly proceed with the Work.
6-6.2 Payment for Delays
Notwithstanding any other terms and conditions of the Contract Documents, the City shall have no obligation whatsoever to increase the Contract Price or extend the time for delays.
Unless compensation and/or markup is agreed upon by the City, the Contractor agrees that no payment of compensation of any kind shall be made to the Contractor for damages or increased overhead costs caused by any delays in the progress of the Contract, whether suc h delays are avoidable or unavoidable or caused by any act or omission of the City or its agents. Any accepted delay claim shall be fully compensated for by an extension of time to complete the performance of the Work.
This Section shall not apply to compensable delays caused solely by the City. If a compensable delay is caused solely by the City, the Contractor shall be entitled to a Change Order that:
(1) extends the time for completion of the Contract by the amount of delay caused by the City; and (2) provides equitable adjustment, as determined by the City, to the Contractor. 6-8 COMPLETION, ACCEPTANCE AND WARRANTY
The Contractor shall complete all Work under the Contract within forty five (45) Working Days from the Notice to Proceed. The Contractor shall not be allowed to begin any construction activity at the site before the issuance of the Notice to Proceed. Between the period of the Notice of Award and Notice to Proceed, the Contractor shall process Shop Drawings and begin procuring equipment and materials.
6-8.2 Acceptance
The Project will not be considered complete and ready for City Council direction to staff regarding recordation of the Notice of Completion until all required Work is completed, the Work site is cleaned up in accordance with Section 7-8 of the Standard Specifications, the General Provisions, and the Special Provisions, and all of the following items have been received by the Engineer:
1. A form of Notice of Completion, with all information required by the California Civil Code;
2. All written guarantees and warranties;
3. All “as-builts”;
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 201 of 527 GP-14
City Project: BD2209 City of Indio Public Works
4. If stated in the contract, the warranty or maintenance Bond or proof from the Surety of the extension of the performance Bond, as more specifically detailed in Section 2 -4 of these General Provisions; and
5. Duplicate copies of all operating instructions and manufacturer’s operating catalogs and data, together with such field instructions as necessary to fully instruct City personnel in correct operation and maintenance procedures for all equipment installed listed under the electrical, air conditioning, heating, ventilating and other trades. This data and instructions shall be furnished for all equipment requiring periodic adjustments, maintenance or other operation procedures.
The Contractor shall allow at least seven (7) Working Days notice for final inspection. Such notice shall be submitted to the Engineer in writing.
6-8.3 Warranty
For the purposes of the calculation of the start of the warranty period, the Work shall be deemed to be completed upon the date of recordation of the Notice of Completion. If that direction is contingent on the completion of any items remaining on a punchlist, the Work shall be deemed to be completed upon the date of the Engineer’s acceptance of the final item(s) on that punchlist.
The Contractor shall repair or replace defective materials and workmanship as required in Section 6-8.3 of the Standard Specification at its own expense. Additionally, the Contractor agrees to defend, indemnify and hold the City harmless from claims of any kind arising from damage, injury or death due to such defects.
The parties agree that no certificate given shall be conclusive evidence of the faithful performance of the Contract, either in whole or in part, and that no payment shall be construed to be in acceptance of any defective Work or improper materials. Further, the certificate or final payment shall not terminate the Contractor’s obligations under the warranty herein. The Contractor agrees that payment of the amount due under the Contract and t he adjustments and payments due for any Work done in accordance with any alterations of the same, shall release the City, the City Council and its officers and employees from any and all claims or liability on account of Work performed under the Contract or any alteration thereof. 6-9 LIQUIDATED DAMAGES
The Contractor shall pay to the City of Indio the sum of $ 250.00 per day, for each and every calendar day's delay in finishing the work in excess of the number of working days as specified for completion of the Work.
For the purposes of the calculation of the start of the liquidated damages, the Work shall be deemed to be completed when the same has been completed in accordance with the Plans and Specifications therefor and to the satisfaction of the Engineer, and the Engineer has certified such completion in accordance with Section 6-8.1 of the Standard Specifications.
SECTION 7. RESPONSIBILITIES OF THE CONTRACTOR
The first paragraph of Section 7-3.1 of the Standard Specifications shall not be incorporated and shall instead be replaced with the following:
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 202 of 527 GP-15
City Project: BD2209 City of Indio Public Works
The Contractor shall provide and maintain insurance naming the City, its elected and appointed offici als, officers, employees, attorneys, agents, designated volunteers, and independent contractors in the role of City officials as insureds or additional insureds regardless of any inconsistent statement in the policy or any subsequent endorsement whether li ability is attributable to the Contractor or the City. The insurance provisions shall not be construed to limit the Contractor’s indemnity obligations contained in the Contract. The City will not be liable for any accident, loss, or damage to the Work be fore completion, except as otherwise specified in Section 6-10.
The first sentence of Section 7-8.4.2 shall not be incorporated, and shall instead be replaced with the following:
Construction materials and equipment shall not be stored in Streets, roads, o r highways unless otherwise specified in the Special Provisions or approved by the Engineer.
The first sentence of the second paragraph of Section 7-9 of the Standard Specifications shall not be incorporated, and shall instead be replaced with the following:
The Contractor shall relocate, repair, replace, or reestablish all existing improvements within the Project limits which are not designated for removal (e.g., curbs, sidewalks, driveways, signal loops, fences, walls, sprinkler systems, signs, Utility installations, pavements, structures, etc.) which are damaged or removed as a result of the Contractor’s or the Subcontractors’ operations or as required by the Plans and Specifications.
The last paragraph of Subsection 7 -9 of the Standard Specifications sha ll not be incorporated, and shall instead be replaced with the following:
All costs to the Contractor for protecting, removing, restoring, relocating, repairing, replacing, or reestablishing existing improvements shall be included in the Bid.
Section 7 -12 of the Standard Specifications shall not be incorporated, and shall instead be replaced with the following:
The names, addresses and specialties of the Contractor, Subcontractors, architects or engineers may not be displayed on any signage within the public right- of-way. This signage prohibition includes advertising banners hung from truck beds or other equipment.
Otherwise, the provisions below shall supplement but not replace those provisions in Section 7 of the Standard Specifications.
7-1 THE CONTRACTOR’S EQUIPMENT AND FACILITIES
Between the hours of 9:00 p.m. and 6:00 a.m. a noise level limit of 86 dbA at a distance of fifty (50) feet shall apply to all construction equipment on or related to the job whether owned by the Contractor or not. The use of excessively loud warning signals shall be avoided, except in those cases required for the protection of personnel.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 203 of 527 GP-16
City Project: BD2209 City of Indio Public Works
7-2 LABOR
7-2.2.1 Public Work
The Contractor acknowledges that the Project is a “public work” as defined in Labor Code Section 1720 et seq. (“Chapter 1”), and that this Project is subject to (a) Chapter 1, including without limitation Labor Code Section 1771 and (b) the rules and regulations established by the Director of Industrial Relations (“DIR”) implementing such statutes. The Contractor shall perform all Work on the Project as a public work. The Contractor shall comply with and be bound by all the terms, rules and regulations described in (a) and (b) as though set forth in full herein. 7-2.2.2 Copies of Wage Rates
Pursuant to Labor Code Section 1773.2, copies of the prevailing rate of per diem wages for each craft, classification, or type of worker needed to perform the Project are on file at City Hall and will be made available to any interested party on request. By initiating any Work on this Project, the Contractor acknowledges receipt of a copy of the DIR determination of such prevailing rate of per diem wages, and the Contractor shall post such rates at each job site covered by these Contract Documents.
7-2.2.3 Job Site Notices
The Contractor is required to post job site notices, as prescribed by regulation. 7-2.2.4 Failure to Pay Prevailing Rates
The Contractor shall comply with and be bound by the provisions of Labor Code Sections 1774 and 1775 concerning the payment of prevailing rates of wages to work ers and the penalties for failure to pay prevailing wages. The Contractor shall, as a penalty paid to the City, forfeit two hundred dollars ($200) for each calendar day, or portion thereof, for each worker paid less than the prevailing rates as determined by the DIR for the work or craft in which the worker is employed for any public work done pursuant to these Contract Documents by the Contractor or by any Subcontractor.
7-2.2.5 Apprentices
The Contractor shall comply with and be bound by the provisions of Labor Code Sections 1777.5, 1777.6 and 1777.7 and California Code of Regulations Title 8, Section 200 et seq. concerning the employment of apprentices on public works projects. The Contractor shall be responsible for compliance with these Sections for all apprenticeable occupations. Before commencing Work on this Project, the Contractor shall provide the City with a copy of the information submitted to any applicable apprenticeship program. Within sixty (60) Days after concluding Work, Contractor and each of i ts Subcontractors shall submit to the City a verified statement of the journeyman and apprentice hours performed under this Contract.
7-2.2.6 Debarment or Suspension
The Contractor shall not perform Work with any Subcontractor that has been debarred or suspended pursuant to California Labor Code Section 1777.1 or any other federal or State law providing for the debarment of contractors from public works. The Contractor and Subcontractors shall not be debarred or suspended throughout the duration of this Contract pursuant to Labor
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 204 of 527 GP-17
City Project: BD2209 City of Indio Public Works
Code Section 1777.1 or any other federal or State law providing for the debarment of contractors from public works. If the Contractor or any Subcontractor becomes debarred or suspended during the duration of the Project, the Contractor shall immediately notify the City. 7-2.3 Payroll Records
The Contractor shall comply with and be bound by the provisions of Labor Code Section 1776, which requires the Contractor and each Subcontractor to (1) keep accurate payroll records and verify such records in writing under penalty of perjury, as specified in Section 1776, (2) certify and make such payroll records available for inspection as provided by Section 1776, and (3) inform the City of the location of the records. The Contractor has ten (10) days in which to comply subsequent to receipt of a written notice requesting these records, or as a penalty to the City, the Contractor shall forfeit one hundred dolla rs ($100) for each Day, or portion thereof, for each worker, until strict compliance is effectuated. Upon the request of the Division of Labor Standards Enforcement, these penalties shall be withheld from progress payments then due. 7-2.4 Hours of Labor
The Con tractor acknowledges that eight (8) hours labor constitutes a legal day’s work. The Contractor shall comply with and be bound by Labor Code Section 1810. The Contractor shall comply with and be bound by the provisions of Labor Code Section 1813 concerning penalties for workers who work excess hours. The Contractor shall, as a penalty paid to the City, forfeit twenty- five dollars ($25) for each worker employed in the performance of this Project by the Contractor or by any Subcontractor for each calendar day during which such worker is required or permitted to work more than eight (8) hours in any one (1) calendar day and forty (40) hours in any one calendar week in violation of the provisions of Division 2, Part 7, Chapter 1, Article 3 of the Labor Code. Pursuant to Labor Code Section 1815, work performed by employees of the Contractor in excess of eight (8) hours per day, and forty (40) hours during any one week shall be permitted upon public work upon compensation for all hours worked in excess of eight (8) hours per day at not less than one and one-half (1-1/2) times the basic rate of pay. 7-2.5 Registration with the DIR
In accordance with Labor Code Sections 1725.5 and 1771.1, no contractor or subcontractor shall be qualified to bid on, be listed in a bid pro posal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to Section 1725.5. 7-2.6 Compliance Monitoring and Posting Job Sites
This Project is subject to compliance monitoring and enforcement by the DIR. The Contractor shall post job site notices, as prescribed by regulation. 7-2.7 Subcontractors
For every Subcontractor who will perform Work on the Project, the Contractor shall be responsible for such Subcontractor’s compliance with Chapter 1 and Labor Code Sections 1860 and 3700, and the Contractor shall include in the written Contract between it and each Subcontractor a copy of the provisions in this Section 7 -2 of the General Provisions and a requirement that each Subcontractor shall comply with those provisions. The Contractor shall be required to take all actions necessary to enforce such contractual provisions and ensure Subcontractor’s compliance,
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 205 of 527 GP-18
City Project: BD2209 City of Indio Public Works
including without limitation, conducting a periodic review of the certified payroll records of the Subcontractor and upon becoming aware of the failure of the Subcontractor to pay its workers the specified prevailing rate of wages. The Contractor shall diligently take corrective action to halt or rectify any failure.
7-2.9 Prevailing Wage Indemnity
To the maximum extent permitted by law, the Contractor shall indemnify, hold harmless and defend (at the Contractor’s expense with counsel reasonably acceptable to the City) the City, its officials, officers, employees, agents and independent contractors s erving in the role of City officials, and volunteers from and against any demand or claim for damages, compensation, fines, penalties or other amounts arising out of or incidental to any acts or omissions listed in Section 7-2 of the General Provisions by any Person (including the Contractor, its Subcontractors, and each of their officials, officers, employees and agents) in connection with any Work undertaken or in connection with the Contract Documents, including without limitation the payment of all consequential damages, attorneys’ fees, and other related costs and expenses. All duties of the Contractor under this Section 7-2.9 shall survive expiration or termination of the Contract. 7-3 LIABILITY INSURANCE
The Contractor shall at all times during the term of the Contract carry, maintain, and keep in full force and effect the insurance referenced in Section 7 -3 of the Standard Specifications, as modified below.
7-3.1.1 Additional Insureds
The City, its elected and appointed officials, officers, employees, attorneys, agents, designated volunteers, and independent contractors in the role of City officials, shall be the insured or named as additional insureds covering the Work, regardless of any inconsistent statement in the policy or any subsequent endorsement, whether liability is attributable to the Contractor or the City. 7-3.1.2 No Limitation on Indemnity
The insurance provisions shall not be construed to limit the Contractor’s indemnity obligations contained in these Contract Documents.
7-3.1.3 Replacement Insurance
The Contractor agrees that it will not cancel, reduce or otherwise modify the insurance coverage.
The Contractor agrees that if it does not keep the required insurance in full force and effect, and such insurance is available at a reasonable cost, the City may take out the necessary insurance and pay the premium thereon, and the repayment thereof shall be deemed an obligation of the Contractor and the cost of such insurance may be deducted, at the option of the City, from payments due the Contractor. This shall be in a ddition to all other legal options available to the City to enforce the insurance requirements.
7-3.1.4 Certificates of Insurance with Original Endorsements The Contractor shall submit to the City certificates of insurance with the original endorsements, both of which reference the same policy number, for each of the insurance policies that meet the insurance requirements, not less than one (1) day before beginning of performance under the
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 206 of 527 GP-19
City Project: BD2209 City of Indio Public Works
Contract. The endorsements are to be signed by a person authorized by that insurer to bind coverage on its behalf. Endorsements may be executed on the City’s standard forms titled “Additional Insured Endorsement,” copies of which are provided in the Contract Documents, or on any other form that contains substantially the same te rms and is approved by the City’s Risk Manager. In any case, the endorsements must specifically name the City of Indio and its elected and appointed officials, officers, employees, attorneys, agents, designated volunteers, and independent contractors in t he role of City officials as insureds or additional insureds. Current insurance certificates and endorsements shall be kept on file with the City at all times during the term of this Contract. The City reserves the right to require complete, certified co pies of all required insurance policies at any time.
7-3.1.5 Subcontractors
The Contractor shall ensure all Subcontractors and their employees are listed as additional insureds on all of the Contractor’s insurance.
7-4 INDEMNIFICATION
The following indemnity provisions shall supersede the indemnity in Section 7-3.1 of the Standard Specifications.
7-4.1 Contractor’s Duty
To the maximum extent permitted by law, the Contractor hereby agrees, at its sole cost and expense, to defend with competent defense counsel approved by the City Attorney, protect, indemnify, and hold harmless the City, its elected and appointed officials, officers, employees, volunteers, attorneys, agents (including those City agents serving as independent contractors in the role of City representatives), successors, and assigns (collectively “Indemnitees”) from and against any and all claims (including, without limitation, claims for bodily injury, death or damage to property), demands, charges, obligations, damages, causes of action, proceedings, suits, losses, stop payment notices, judgments, fines, liens, penalties, liabilities, costs and expenses of every kind and nature whatsoever, in any manner arising out of, incident to, related to, in connection with or resulting from any act, failure to act, error or omission of the Contractor or any of its officers, agents, attorneys, servants, employees, Subcontractors, material suppliers or any of their officers, agents, servants or employees, and/or arising out of, incident to, related to, in connection with or resulting from any term, provision, image, plan, covenant, or condition in the Contract Documents; including, without limitation, the payment of all consequential damages, attorneys’ fees, experts’ fees, and other related costs and expenses (individually, a “Claim,” or collectively, “Claims”). The Contractor shall promptly pay and satisfy any judgment, a ward or decree that may be rendered against any of the Indemnitees as to any such Claim. The Contractor shall reimburse Indemnitees for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity her ein provided. The Contractor’s obligation to indemnify shall not be restricted to insurance proceeds, if any, received by the Contractor or Indemnitees. This indemnity shall apply to all Claims regardless of whether any insurance policies are applicable or whether the Claim was caused in part or contributed to by an Indemnitees.
7-4.2 Civil Code Exception
Nothing in this Section 7 -4 shall be construed to encompass Indemnitees’ sole negligence or willful misconduct to the limited extent that the underlying Contract is subject to Civil Code Section
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 207 of 527 GP-20
City Project: BD2209 City of Indio Public Works
2782(a) or the City’s active negligence to the limited extent that the underlying Contract Documents are subject to Civil Code Section 2782(b), provided such sole negligence, willful misconduct or active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction.
7-4.3 Nonwaiver of Rights
Indemnitees do not and shall not waive any rights that they may possess against the Contractor because the acceptance by the City, or the deposit with the City, of any insurance policy or certificate required pursuant to these Contract Documents. This indemnity provision is effective regardless of any prior, concurrent, or subsequent active or passive negligence by Indemnitees and shall operate to fully indemnify Indemnitees against any such negligence. 7-4.4 Waiver of Right of Subrogation.
The Contractor, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the I ndemnitees, while acting within the scope of their duties, from all Claims arising out of or incident to the activities or operations performed by or on behalf of the Contractor regardless of any prior, concurrent or subsequent active or passive negligence by Indemnitees.
7-4.5 Survival.
The provisions of this Section 7 -4 shall survive the term and termination of the Contract, are intended to be as broad and inclusive as is permitted by the law of the State, and are in addition to any other rights or remedies that Indemnitees may have under the law. Payment is not required as a condition precedent to an Indemnitee’s right to recover under this indemnity provision, and an entry of judgment against the Contractor shall be conclusive in favor of the Indemnitee’s right to recover under this indemnity provision.
7-5 PERMITS
Before starting any construction work, the Contractor will be required to obtain all necessary permits from the City, which may include obtaining a no fee encroachment permit for Work within the public right-of-way, as well as all other permits required from all other agencies. Should this Project require construction of trenches or excavations which are five (5) feet or deeper and into which a person is required to descend, the Contractor shall obtain a Cal/OSHA permit and furnish the City with a copy before Work can commence on this Project. Contractor shall bear all cost for fees for all agencies except for the City’s permit fees. 7-7 COOPERATION AND COLLATERAL WORK
The Contractor shall be responsible for coordinating all Work with the City’s street sweeping, trash pick-up, and street maintenance contractors, emergency services departments, utility companies’ crews, and others when necessary. Payment for conforming to these requirements shall be included in other items of Work, and no additional payment shall be made thereof. 7-8 WORKSITE MAINTENANCE
Clean-up shall be done as Work progresses at the end of each day and thoroughly before weekends. The Contractor shall not allow the Work site to become littered with trash and waste
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 208 of 527 GP-21
City Project: BD2209 City of Indio Public Works
material, but shall maintain the same in a neat and orderly condition throughout the construction operation. Materials which need to be disposed shall not be stored at the Project site, but shall be removed by the end of each Working Day. If the job site is not cleaned to the satisfaction of the Engineer, the cleaning will be done or contracted by the City and shall be back-charged to the Contractor and deducted from the Contract Price.
The Contractor shall make arrangements for storing its equipment and materials. The Contractor shall make its own arrangements for any necessary off-site storage or shop areas necessary for the proper execution of the Work. Approved areas within Work site may be used for temporary storage; however, the Contractor shall be responsible for obtaining any necessary permits from the City. In any case, the Contractor’s equipment and personal vehicles of the Contractor’s employees shall not be parked on the traveled way or on any section where traffic is restricted at any time.
The Contractor shall deliver, handle, and store products in accordance with the manufacturer’s written recommendations and by methods and means that will prevent damage, deterioration, and loss including theft. Delivery schedules shall be controlled to minimize long-term storage of products at the Project site and overcrowding of construction spaces. In particular, the Contractor shall provide delivery and installation coordination to ensure minimum holding or storage times for produ cts recognized to be flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other sources of loss.
Storage shall be arranged to provide access for inspection. The Contractor shall periodically inspect to assure products are undamaged and are maintained under required conditions.
The Contractor shall promptly remove from the vicinity of the completed Work, all rubbish, debris, unused materials, concrete forms, construction equipment, and temporary structures and facilities used during construction. Final acceptance of the Work by the City will be withheld until the Contractor has satisfactorily complied with the foregoing requirements for final clean -up of the Project site.
All costs associated with the clean-up and storage required to complete the Project shall be the sole responsibility of the Contractor.
7-9 SAFETY
The provisions below shall supplement but not replace those provisions in Subsection 7-10 of the Standard Specifications.
7-9.1 Access
All construction work and traffic control shall be scheduled and constructed to provide for a minimum of inconvenience and a maximum of safety to the public vehicular and pedestrian traffic.
The Contractor shall be responsible for the protection of vehicular and pedestrian traffic until the Work called for in the Plans, Standard Specifications, General Provisions and Special Provisions and as directed by the Engineer is complete.
7-10.2.2 Traffic Control Plan
All Work shall require maintenance and control of traffic during the construction period. The Contractor shall provide a detailed Traffic Control Plan (“TCP”) for all phases of construction for
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 209 of 527 GP-22
City Project: BD2209 City of Indio Public Works
review and shall conform to the Standard Specifications, General Provisions, Special Provisions, the latest edition of the California Edition of the Ma nual on Uniform Traffic Control Devices (“MUTCD”), the latest edition of Caltrans Standard Specifications and the latest edition of Caltrans Standard Plans and must be approved by the Engineer before construction. The TCP shall be prepared under the super vision of and signed and stamped by a registered Professional Civil Engineer or a Traffic Engineer licensed to practice in the State of California. The TCP shall cover signing, flagging, detour geometric, delineation and channelization, barriers and barri cades, separation of opposing traffic streams, and hours of flash operation at signalized intersection(s).
The Contractor shall not commence work before receiving an approved TCP. Any delay in acquiring TCP approval will be at the Contractor’s expense an d no additional Working Days will be granted.
Traffic control shall be provided by a qualified traffic control company specializing with a C -31 license during the construction of the Project. Traffic control shall address parking changes as well. Before the beginning of any Work or if there are changes to the proposed TCP and after approval by the City, the qualified traffic control company staff shall complete field checks of the installed traffic control by driving through the Work area at least two (2) times to ensure the adequacy of traffic control. During any period when two (2) way traffic is not provided, the Contractor shall employ properly trained flaggers to control traffic through the construction zone.
For construction in the vicinity of a school, the Contractor shall contact the School District, obtain a school schedule and school circulation plan, and incorporate information into the Project’s schedule and traffic control, such that within one thousand (1,000) feet of the school on routes serving the school for student arrivals and departures are not impacted between one (1) hour before and one-half (1/2) hour after the school day start time and one (1) hour before or one-half 1/2) hour after school day end time. Additionally, the Contractor shall notify all entities listed in General Provisions Section 5-7.
The Contractor shall provide and maintain steel traffic plates securely over the trench whenever required or at the end of the Working Day. The plates shall be pinned and ramped with temporary asphaltic concrete.
7-10.3 Haul routes
Subsection 7-10.3 of the Standard Specifications shall be deleted and replaced as follows:
The Contractor must obtain the Engineer’s approval before using any haul routes.
Further detail requirements for haul traffic are delineated in the Special Provisions. 7-10.5.3 Steel Plate Covers
The Contractor shall cover all openings, trenches and excavations at the end of each Work Day with steel plate covers.
7-15 RECYCLING OF MATERIALS
Subsection 7-15 is hereby added to the Standard Specifications as follows:
7-15.1 Recycling of Asphalt Concrete, Portland Cement Concrete, Aggregate Base, and Green Waste are Required
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 210 of 527 GP-23
City Project: BD2209 City of Indio Public Works
The records of disposal, including scale tonnages, shall be furnished to the City on a monthly basis. Failure to comply with t he requirements of this Section will result in delay of progress payment.
7-15.2 Contractor’s Obligation
The City is committed to a recycling program. If available, it is the obligation of the Contractor, under this Contract, to recycle the waste material through an approved recycling plant. Records and reports of waste recycle will be submitted to the City on a regular monthly basis.
SECTION 8. FACILITIES FOR AGENCY PERSONNEL
The provisions of Section 8 of the Standard Specifications shall apply except as modified herein.
No field offices for City personnel shall be required; however, City personnel shall have the right to enter upon the Project at all times and shall be admitted to the offices of the Contractor to use the telephone, desk and sanitary facilities provided by the Contractor for its own personnel.
SECTION 9. MEASUREMENT AND PAYMENT
The provisions below shall supplement but not replace those provisions in Section 9 of the Standard Specifications.
9-1.2 Methods of Measurement
The Contract Price shall constitute full compensation for all labor, equipment, materials, tools and incidentals required to complete the Project as outlined in these Contract Documents and as directed by the Engineer.
9-3 PAYMENT
9-3.1 General
In accordance with Public Contract Code Section 7107, if no claims have been filed and are still pending, the amount deducted from the final estimate and retained by the City will be paid to the Contractor except such amounts as are required by law to be withheld by properly executed and filed notices to stop payment, or as may be withheld for any other lawful purposes. 9-3.2 Partial and Final Payment
9-3.2.1 Monthly Closure Date and Invoice Date
In accordance with Section 9 -3.2 of the Standard Specifications, the monthly closure date shall be the last Day of each month. A measurement of Work performed and a progress estimate of the value thereof based on the Contract and of the monthly payment shall be prepared by the Contractor and submitted to the Engineer before the tenth (10th) Day of t he following month for verification and payment consideration.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 211 of 527 GP-24
City Project: BD2209 City of Indio Public Works
9-3.2.2 Payments
The City shall make payments within thirty (30) Days after receipt of the Contractor’s undisputed and properly submitted payment request, including an updated construction schedule pursuant to Section 6-1.1 of the General Provisions. The City shall return to the Contractor any payment request determined not to be a proper payment request as soon as practicable, but not later than seven (7) Days after receipt, and shall explain in writing the reasons why the payment request is not proper.
9-3.2.3 Retention
If stated in the Contract, the City shall withhold not less than five percent (5%) from each progress payment. However, at any time after fifty percent (50%) of the Work has been completed, i f the City Council finds that satisfactory progress is being made, it may, at its discretion, make any of the remaining progress payments in full for actual Work completed. The City shall withhold not less than five percent (5%) of the Contract Price from the Final Payment Amount (defined in Section 9-3.2.4) until at least thirty-five (35) days after recordation of the Notice of Completion, or recordation of a notice of completion or cessation, but not longer then the period permitted by Public Contract Code Section 7107.
9-3.2.4 Final Invoice and Payment
Whenever the Contractor shall have completely performed the Contract in the opinion of the Engineer, the Engineer shall notify the City Clerk that the Contract has been completed in its entirety. The C ontractor shall then submit to the Engineer a written statement of the final quantities of Contract items for inclusion in the final invoice. Upon receipt of such statement, the Engineer shall check the quantities included therein and shall authorize a payment amount, which in the Engineer’s opinion shall be just and fair, covering the value of the total amount of Work done by the Contractor, less all previous payments and all amounts to be retained under the provisions of the Contract Documents (“Final Payment Amount”). The Engineer shall then request that the City accept the Work and that the City Clerk be authorized to file, on behalf of the City in the office of the County Recorder, a Notice of Completion of the Work herein agreed to be done by the Contractor. In addition, the final payment will not be released until the Contractor returns the control set of Plans and Specifications showing the redlined as-built conditions. 9-3.2.5 Substitute Security
In accordance with Public Contract Code Section 22300, the Contractor may request that it be permitted to substitute securities in lieu of having retention withheld by the City from progress payments when such payments become due or, in the alternative, the Contractor may request that the City make payments of earned retentions directly to an agreed upon designated escrow agent at the Contractor’s expense. If the Contractor selects either one of these alternatives, the following shall control.
9-3.2.5.1 Substitution of Securities for Performance Retention At some reasonable time before any progress payment would otherwise be due and payable to the Contractor in the performance of Work under these Contract Documents, the Contractor may submit a request to the City in writing to permit the substitution of ret entions with securities equivalent to the amount estimated by the City (“estimated amount of retention”) to be withheld.
The Contractor shall deposit such securities with the City or may, in the alternative, deposit such
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 212 of 527 GP-25
City Project: BD2209 City of Indio Public Works
securities in escrow with a State or federally chartered bank in California, as the escrow agent, at the Contractor’s expense. Such securities will be the equivalent or greater in value of the estimated amount of retention. If the Contract is modified by written Modifications or Change Orders or the Contractor otherwise becomes entitled to receive an amount more than the Contract Price at the time the securities are deposited, the Contractor shall, at the request of the City, deposit with the City or escrow agent, whichever is applicable, additional securities within a reasonable time so that the amount of securities on deposit with the City or escrow agent is equivalent or greater in value than the amount of retention the City would otherwise be entitled to withhold from progress payments due or to become due to the Contractor as the Work progresses.
The City shall withhold any retention amount that exceeds the security amount until the additional securities are deposited and, if the deposit is with an escrow agent, the City has confirmation from that escrow agent of the new total value of securities. Upon satisfactory completion of the Contract, which shall mean, among other things, that the City is not otherwise entitled to retain proceeds from progress payments as elsewhere provided in the Contract or under applicable law, the securities shall be returned to the Contractor. The City shall, within its sole discretion, determine whether the amount of the securities on deposit with the City or escrow agent is equal to or greater than the amount of estimated retention of progress payments that could otherwise be held by the City if the Contractor had not elected to substitute same with securities. 9-3.2.5.2 Deposit of Retention Proceeds with an Escrow Agent As an alternative to the substitution of se curities, as provided above, or the City otherwise retaining and holding retention proceeds from progress payments, the Contractor may request the City to make payments of retentions earned directly to an escrow agent with the same qualifications as required in Section 9-3.2.5.1 above and at the expense of the Contractor. At its sole expense, the Contractor may direct the investment of such retention payments into only such securities as mentioned in Section 9-3.2.5.3 below and shall be entitled to interest earned on such investments on the same terms provided for securities deposited by the Contractor. Upon satisfactory completion of the Contract, which shall mean when the City would not otherwise be entitled to withhold retention proceeds from progress payments had the Contractor not elected to have such proceeds deposited into escrow, the Contractor shall be allowed to receive from the escrow agent all securities, interest and payments deposited into escrow pursuant to the terms of this Section. The Con tractor shall pay to each Subcontractor, not later than ten (10) Days of receipt of payment, the respective amount of interest earned, net of costs attributed to retention withheld from each Subcontractor, on the amount withheld to ensure performance of th e Contractor.
9-3.2.5.3 Subcontractor Entitlement to Interest
If the Contractor elects to receive interest on any moneys withheld in retention by the City, then the Subcontractor shall receive the identical rate of interest received by the Contractor on any retention moneys withheld from the Subcontractor by the Contractor, less any actual pro rata costs associated with administering and calculating that interest. In the event that the interest rate is a fluctuating rate, the rate for the Subcontractor shall be dete rmined by calculating the interest rate paid during the time that retentions were withheld from the Subcontractor. If the Contractor elects to substitute securities in lieu of retention, then, by mutual consent of the Contractor and the Subcontractor, the Subcontractor may substitute securities in exchange for the release of moneys held in retention by the Contractor. The Contractor shall pay each Subcontractor, not later than ten (10) Days after receipt of escrow moneys, the amount owed to each Subcontractor from the moneys plus the respective amount of interest earned, net of costs
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 213 of 527 GP-26
City Project: BD2209 City of Indio Public Works
attributed to the retention held from each Subcontractor, on the amount of retention withheld to ensure performance of the Subcontractor.
9-3.2.5.4 Securities Eligible for Investment
Securities eligible for investment shall include those listed in Government Code Section 16430, bank or savings and loan certificates of deposit, interest -bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed upon between the Contractor and the City. The Contractor shall be the beneficial owner of any securities substituted for any monies withheld and shall receive any interest thereon.
9-3.2.5.5 Escrow Agreement for Security Deposits in Lieu of Retention The escrow agreemen t that shall be used for the deposit of securities in lieu of retention shall substantially conform to the form prescribed in Public Contract Code Section 22300(f). 9-3.2.5.6 Inconsistencies with Prevailing Statutory Requirements If there is any inconsistency between or differences in Public Contract Code Section 22300 and the terms of this provision, or any future amendments thereto, Section 22300 shall control. 9-3.4 Mobilization
Mobilization is defined as the preparatory work that must be performed or cost incurre d before starting work on the various items on the job site in accordance with Public Contract Code Section 10104. The City makes the partial payments under Public Contract Code Section 10264. 9-4 AUDIT
The City or its representative shall have the option of inspecting and/or auditing all records and other written materials used by the Contractor in preparing its billings to the City as a condition precedent to any payment to the Contractor or in response to a construction claim or a Public Records Act (Govern ment Code Section 6250 et seq.) request. The Contractor will promptly furnish documents requested by the City at no cost. Additionally, the Contractor shall be subject to State Auditor examination and audit at the request of the City or as part of any audit of the City, for a period of three (3) years after final payment under the Contract. The Contractor shall include a copy of this Section 9 -4 in all contracts with its Subcontractors, and the Contractor shall be responsible for immediately obtaining th ose records or other written material from its Subcontractors upon a request by the State Auditor or the City. If the Project includes other auditing requirements, those additional requirements will be listed in the Special Provisions.
SECTION 10. ADDITIONAL TERMS
10-1 NONDISCRIMINATORY EMPLOYMENT
The Contractor shall not unlawfully discriminate against any individual based on race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation or military and veteran status. The Contractor understands and agrees that it is bound by and will comply with the nondiscrimination mandates of all statutes and local ordinances and regulations.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 214 of 527 GP-27
City Project: BD2209 City of Indio Public Works
10-2 NOTICE TO PROCEED
Upon award of this Contract and signing the Contract Documents, the City shall issue the Contractor a Notice to Proceed. The City will not authorize any Work to be done under these Contract Documents before the Contract has been fully executed. Any Work that is done by the Contractor in advance of such time shall be considered as being done at the Contractor’s own risk and responsibility, and as a consequence will be subject to rejection. 10-3 CONTRACTOR’S RESPONSIBILITY FOR WORK
Until the final acceptance of the Work by the City as defined in Section 6 -8.2 of the General Provisions, by written action of the Engineer, the Contractor shall have the charge and care thereof and shall bear the risk of injury or damage to any part of the Work by the action of the elements, criminal acts, or any other cause. The Contractor shall rebuild, repair, restore and make good all injuries or damages to any portion of the Work occasioned by any cause before its completion and acceptance and shall bear the expense thereof, exce pt for such injuries or damages arising from the sole negligence or willful misconduct of the City, its officers, agents or employees. In the case of suspension of Work from any cause whatever, the Contractor shall be responsible for all materials and the protection of Work already completed, shall properly store and protect them if necessary, and shall provide suitable drainage and erect temporary structures where necessary.
10-4 PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY
Any portions of curb, gutter, sidewalk or any other City improvement damaged by the Contractor during the course of construction shall be replaced by the Contractor at its own cost. The cost of additional replacement of curb, gutter or sidewalk in excess of the estimated quantities shown in the Bid form and Specifications, and found necessary during the process of construction (but not due to damage resulting from carelessness on the part of the Contractor during its operation), shall be paid to the Contractor at the unit prices submitted in his or her Bid. 10-5 REMOVAL OF INTERFERING OBSTRUCTIONS
The Contractor shall remove and dispose of all debris, abandoned structures, tree roots and obstructions of any character encountered during the process of excavation. It is understood that the cost of any such removals are made a part of the unit price bid by the Contractor under the item for excavation or removal of existing Work.
10-6 SOILS ENGINEERING AND TESTING
A certified materials testing firm may be retained by the City to perform materials tests during the Contractor’s entire operation to ascertain compliance with the Contract requirements. The City shall be responsible for the first series of tests. If the initial tests do not meet the Contract requirements, the Contractor shall bear the cost of all subsequent tests.
If the City requires other tests or more specific requirements for testing regarding this Project, those details will be included in the Special Provisions.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 215 of 527 GP-28
City Project: BD2209 City of Indio Public Works
10-7 ACCESS TO PRIVATE PROPERTY
Unless otherwise stated in the Special Provisions, the Contractor shall be responsible for all fees and costs associated with securing permission to access private property for any portion of the Project.
10-8 WORKING DAYS AND HOURS
Work hours are as follows, unless otherwise approved by the Engineer:
Pacific Standard Time Pacific Daylight Time
Monday through Friday 7:00 a.m. - 6:00 p.m. 6:00 a.m. - 6:00 p.m.
If the Engineer approves weekend days and/or government holidays as working days, City Inspection Fees will be charged at a rate of time and a half per hour of inspection. This includes surveying, material testing, and any and all professional services required.
In addition, no Work will be allowed on any special election Day that may be declared. Should a special election Day be declared, a ti me extension of one (1) Working Day will be granted for each such Day.
A permit may have other hours or Days for the Contractor to do the Work, and those hours and Days shall supersede any hours and Days written in this Section.
Whenever the Contractor is permitted or directed to perform night Work or to vary the period during which Work is performed during the Working Day, the Contractor shall give twelve (12) hours’ notice to the Engineer so that inspection may be provided. Also, a charge may be made to the Contractor for approved overtime or weekend inspections requested by the Contractor. 10-9 CLAIM DISPUTE RESOLUTION
In the event of any dispute or controversy with the City over any matter whatsoever, the Contractor shall not cause any delay or cessation in or of Work, but shall proceed with the performance of the Work in dispute. The Contractor shall retain any and all rights provided that pertain to the resolution of disputes and protests between the parties. The Disputed Work will be categorized as an “unresolved dispute” and payment, if any, shall be as later determined by mutual agreement or a court of law. The Contractor shall keep accurate, detailed records of all Disputed Work, claims and other disputed matters.
All claims arising out of or related to the Contract Documents or this Project, and the consideration and payment of such claims, are subject to the Government Claims Act (Government Code Section 810 et seq.) with regard to filing claims and to Public Contract Code Section 20104 et seq. (Article 1.5) regarding the resolution of public works claims of three hundred seventy -five thousand dollars ($375,000) or less. This Contract hereby incorporates those provisions as through fully set forth herein. Thus, the Contractor or any Subcontractor mu st file a claim in accordance with the Government Claims Act as a prerequisite to filing a construction claim in compliance with Article 1.5, and must then adhere to Article 1.5. 10-10 THIRD PARTY CLAIMS
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 216 of 527 GP-29
City Project: BD2209 City of Indio Public Works
The City shall have full authority to compromise or otherwise settle any claim relating to the Project at any time. The City shall timely notify the Contractor of the receipt of any third -party claim relating to the Project. The City shall be entitled to recover its reasonable costs incurred in providing this notice.
10-11 COMPLIANCE WITH LAWS
The Contractor shall comply with all applicable federal, State and local laws, ordinances, codes and regulations in force at the time the Contractor performs pursuant to the Contract Documents. 10-12 CONTRACTOR’S REPRESENTATIONS
By si gning the Contract, the Contractor represents, covenants, agrees, and declares under penalty of perjury under the laws of the State of California that: (a) the Contractor is licensed, qualified, and capable of furnishing the labor, materials, and expertise necessary to perform the services in accordance with the terms and conditions set forth in the Contract Documents ; (b) there are no obligations, commitments, or impediments of any kind that will limit or prevent its full performance under the Contract Documents; (c) there is no litigation pending against the Contractor that could adversely affect its performance of the Contract, and the Contractor is not the subject of any criminal investigation or proceeding; and (d) to the Contractor’s actual knowledge, neither the Contractor nor its personnel have been convicted of a felony. 10-13 CONFLICTS OF INTEREST
The Contractor agrees not to accept any employment or representation during the term of the Contract or within twelve (12) months after acceptance as defined in Section 6-8.2 of the General Provisions that is or may likely make the Contractor “financially interested,” as provided in Government Code Sections 1090 and 87100, in any decisions made by the City on any matter in connection with which the Contractor has been retained pursuant to the Contract Documents. 10-14 APPLICABLE LAW
The validity, interpretation, and performance of these Contract Documents shall be controlled by and construed under the laws of the State of California, excluding California’s choice of law rules.
Venue for any such action relating to the Contract shall be in the Riverside County Superior Court. 10-15 TIME
Time is of the essence in these Contract Documents.
10-16 INDEPENDENT CONTRACTOR
The Contractor and Subcontractors shall at all times remain, as to the City, wholly independent contractors. Neither the City nor any of its officials, officers, employees or agents shall have control over the conduct of the Contractor, Subcontractors, or any of their officers, employees, or agents, except as herein set forth, and the Contractor and Subcontractors are free to dispose of all portions of their time and activities that they are not obligated to devote to the City in such a manner and to such P ersons that the Contractor or Subcontractors wish except as expressly provided in these Contract Documents. The Contractor and Subcontractors shall have no power to incur any debt, obligation, or liability on behalf of the City, bind the City in any manne r, or otherwise act on behalf of the City as agents. The Contractor and Subcontractors shall not, at
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 217 of 527 GP-30
City Project: BD2209 City of Indio Public Works
any time or in any manner, represent that they or any of their agents, servants or employees, are in any manner agents, servants or employees of the City. The Contractor and Subcontractors agree to pay all required taxes on amounts paid to them under the Contract, and to indemnify and hold the City harmless from any and all taxes, assessments, penalties, and interest asserted against the City by reason of the independent contractor relationship created by the Contract Documents. The Contractor shall include this provision in all contracts with all Subcontractors. 10-17 CONSTRUCTION
In the event of any asserted ambiguity in, or dispute regarding the interpretation of any matter herein, the interpretation of these Contract Documents shall not be resolved by any rules of interpretation providing for interpretation against the party who causes the uncertainty to exist or against the party who drafted the Contract Documents or who drafted that portion of the Contract Documents.
10-18 NON-WAIVER OF TERMS, RIGHTS AND REMEDIES
Waiver by either party of any one (1) or more of the conditions of performance under these Contract Documents shall not be a waiver of any o ther condition of performance under these Contract Documents. In no event shall the making by the City of any payment to the Contractor constitute or be construed as a waiver by the City of any breach of covenant, or any default that may then exist on the part of the Contractor, and the making of any such payment by the City shall in no way impair or prejudice any right or remedy available to the City with regard to such breach or default.
10-19 TERM
The Contract is effective as of the Effective Date listed, and shall remain in full force and effect until the Contractor has fully rendered the services required by the Contract Documents or the Contract has been otherwise terminated by the City. However, some provisions may survive the term listed within this Section, as stated in those provisions. 10-20 NOTICE
Except as otherwise required by law, any notice or other communication authorized or required by these Contract Documents shall be in writing and shall be deemed received on (a) the day of delivery if delivered by hand or overnight courier service during the City’s regular business hours or (b) on the third (3rd) business day following deposit in the United States mail, postage prepaid, to the addresses listed on the Contractor’s Bid and City Hall, or at such other address as one party may notify the other.
10-21 SEVERABILITY
If any term or portion of these Contract Documents is held to be invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of these Contract Documents shall continue in full force and effect.
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 218 of 527
EXHIBIT A
AGENDA ITEM #9.10
Construction Contract with Coast Recreation, Inc. in the amount of $164,... Page 219 of 527 City of Indio
City Council
October 5, 2022
STAFF REPORT
To: City Council
From: Bryan H. Montgomery, City Manager
Prepared by: Timothy Wassil, Public Works Director
Subject: Adopt Resolution No. 10329 ratifying the submission of a grant proposal to the Coachella Valley Mountains Conservancy Proposition 1 Grant Program in the amount of $889,000.
RECOMMENDATION:
Adopt Resolution No. 10329 ratifying the submission of a grant proposal to the Coachella Valley Mountains Conservancy Proposition 1 Grant Program.
SUMMARY:
The City submitted an $889,000 grant application to the Coachella Valley Mountains Conservancy (CVMC) Proposition 1 Grant Program for necessary drainage improvements along Jackson Street, between Avenue 49 and Avenue 52. The improvements include installing parkway underground perforated piping to prevent future flooding and to provide adequate stormwater retention and infiltration. The grant submission requires the City to certify that the applicant possesses legal authority to apply for the grant, and to i mplement the proposed project described in the project narrative.
BACKGROUND INFORMATION:
In 2018, the City submitted a grant application for this project to the CVMC Proposition 1 Grant Program and received tentative project funding approval. This app roval was contingent on the City receiving (CEQA). Act Quality Environmental through the clearance environmental California Unfortunately, because the drainage project is a phase of the larger Jackson Street Improvement Project (from Avenue 49 to Avenue 5 2 in partnership with Riverside County), by the time the CEQA clearance was completed, in October 2021, the CVMC no longer had the 2018 funding. The CVMC recommended that the City resubmit for the 2022 Proposition 1 Grant Program.
The City has since adva nced the Jackson Street Improvement Project, completed the CEQA documentation, and will begin acquiring necessary right of way this year. The CVMC Proposition 1 Grant Program Application was updated to reflect more accurate project information including a more recent construction cost estimate.
The City now seeks up to $889,000 for the construction of the perforated underground retention basin pipe in the street parkway. Unground infiltration systems are highly effective at removing a high percentage of suspended solids and organic compounds, and reduce or prevent pollution to the basin.
The project is estimated to capture 134,000 cubic feet of water resulting from the 100 -year 24-hour AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 220 of 527 storm volume that will then be pretreated for groundwater recharge. The main goal of the proposed project is to reduce flooding on Jackson Street consistent with the City’s Master Drainage Plan.
The grant application was due on September 15, 2022. However, prior to submittal, the City was required to have a pre-screening meeting with CVMC to discuss the project characteristics to ensure grant eligibility. This meeting was held on August 23, 2022, where the CVMC reaffirmed the project’s eligibility. Staff recommends the City Council ratify Staff’s decision to submit the application on behalf of the City and authorize the City Manager, Public Works Director, or their designee, to execute the grant documents and agreements should the City be selected.
FINANCIAL SUMMARY:
Current FY Financial
Impact:
$0 In current year budget: N/A
Current FY General
Fund Impact:
$0 Budget adjustment: N/A
Next FY Financial
Impact:
$1,533,120 Strategic Objective:
Source of funds: Various Fund-Org-Object
Reference:
Various
Additional Financial Details:
The City is seeking up to $889,000 in funding from the CVMC Proposition 1 Grant Program. While there is no required match, the CVMC expressed their limited funding capacity and desire to fund as many projects as possible. The total cost for the drainage phase of the project is currently estimated to be $1,533,120. The remaining cost ($644,120) will be funded with Develop Impact Fee - Storm Drain funds. Costs are not expected to be incurred until FY 23/24.
ATTACHMENTS:
Attachment 1
Attachment 2
Attachment 3
APPROVAL(S):
Timothy Wassil, Public Works Director Approved - 28 Sep 2022 City Attorney, City Attorney Approved - 28 Sep 2022
Rob Rockwell, Asst. City Manager & Dir. Of Finance Approved - 29 Sep 2022 Bryan H. Montgomery, City Manager Approved - 29 Sep 2022
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 221 of 527 ATTACHMENT 1
PROJECT LOCATION MAP
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 222 of 527 Figure 2 - Aerial Map
Sources: Riverside Co. GIS, 2020;
ESRI/Digital Globe, 2018.
RIVERSIDE
COUNTY
52ND AVE
JACKSON ST
CALHOUN ST
AVENUE 50
ODLUM
DR
BAR
RYM
O
RE
ST
AVENUE 49
TODOS SANTOS AVE
SPIRITMOUNTAIN DR
PEMBROKE LN
POLO
C
LUB
DR
CITY OF
INDIO
CITY OF
COACHELLA
LEGEND
Project Footprint
Jurisdictional Boundaries
H:\2019\19-0002\GIS\Aerial.mxd; Map revised 24 Nov 2020 Jackson Street Improvement Project
from Avenue 50 to Avenue 52
I
0 1,000 2,000 3,000
Feet
A L 8 E R T A .
WEBB
ASSOCIATES
19
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 223 of 527
ATTACHMENT 2
RESOLUTION NO. 10329
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 224 of 527
RESOLUTION NO. 10329
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF INDIO,
CALIFORNIA, APPROVING THE SUBMISSION OF A GRANT PROPOSAL TO THE COACHELLA VALLEY MOUNTAINS CONSERVANCY PROPOSITION 1
GRANT PROGRAM AND AUTHORIZING THE EXECUTION OF A GRANT
AGREEMENT AND ACCEPTANCE OF FUNDS SHOULD THE CITY OF INDIO BE SELECTED FOR FUNDING.
WHEREAS, the Coachella Valley Mountains Conservancy has heretofore invited public agencies to submit applications for the Notice of Funding Availability Number 2022-01 for the Proposition 1 Grant Program to implement the Water Action Plan in the Coachella Valley; and
WHEREAS, eligible applicants include state and local public entities, nonprofit organizations, Indian tribes, and mutual water companies; and
WHEREAS, the City Council of the City of Indio is adopting Resolution No. 10329 designating and authorizing the City Manager, Public Works Director, or his designee, to submit said grant application and to execute said grant documents and agreements should the City of Indio be selected for funding; and
WHEREAS, the Coachella Valley Mountains Conservancy requires that the Indio City Council adopts a resolution or similar action authorizing the City Manager, Public Works Director, or his designee, to file said application and to act in connection with the application and to provide such additional information as may be required;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF INDIO DOES RESOLVE, DECLARE, DETERMINE AND ORDER AS FOLLOWS:
Section 1. The submission of the application and acceptance of funds, if selected for funding, on behalf of the City of Indio, a public entity established under the laws of the State of California, is hereby ratified and approved.
Section 2. The City Council of the City of Indio hereby agrees to, and by this Resolution, and does accept any grant funding award provided by the Coachella Valley Mountains Conservancy, without further action of the City Council being required therefore.
Section 3. The City of Indio hereby agrees to comply with each and all of the terms, conditions and limitations imposed by the Coachella Valley Mountains Conservancy upon said Grant award, and the Indio City Manager, Public Works Director, or his designee, is hereby authorized and directed to execute any agreements, assurances, or other documents that are required or necessary in connection with the acceptance or implementation of a grant.
PASSED, APPROVED AND ADOPTED this 5th day of October, 2022.
__________________________
WAYMOND FERMON, MAYOR
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 225 of 527
ATTEST:
__________________________________
CYNTHIA HERNANDEZ, CMC
CITY CLERK
APPROVED AS TO FORM:
________________________________
STEVEN GRAHAM, CITY ATTORNEY
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 226 of 527 ATTACHMENT 3
FINAL CVMC PROPOSITION 1
GRANT APPLICATION
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 227 of 527 Jackson Sreet &
Avenue 50 Flood
Protection Project
City of Indio
Coachella Valley Mountains Conservancy
Proposition 1 Grant Program
73-710 Fred Waring Drive, Suite 112
Palm Desert, CA 92660
September 15, 2022
Submitted by:
City of Indio
100 Civic Center Mall
Indio, CA 92201
(760) 391-4018
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 228 of 527
Table of Contents
CVMC Application Form ............................................................................................................................... 1 Certification .................................................................................................................................................. 2 Section 1 – Project Description .................................................................................................................... 3 Attachment 1 – Preliminary Conceptual Design ....................................................................................... 4 Section 2 – Project Location ....................................................................................................................... 15 Attachment 2 – Project Location Map .................................................................................................... 17 Attachment 3 – Project Area Photos ...................................................................................................... 23 Section 3 – Schedule ................................................................................................................................... 26 Section 4 – Budget & Cost Effectiveness ................................................................................................... 28 Section 5 – Organizational Capacity .......................................................................................................... 30 Project Team Resumes ............................................................................................................................ 32 Section 6 – Grant Program Objectives ....................................................................................................... 40 Section 7 – Project Evaluation Criteria ...................................................................................................... 42 Section 8 – Environmental Review ............................................................................................................ 48 CEQA Notice of Determination ............................................................................................................... 49 Section 9 – Proposed Performance Measures and Monitoring ................................................................ 50 Section 10 – Project Sustainability ............................................................................................................ 51 Section 11 – Project Support ...................................................................................................................... 52 Supplemental Materials – Letters of Support ........................................................................................... 53
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 229 of 527 1 1
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 230 of 527 2 2
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 231 of 527
1. Project Description
Project Description. The proposed Infrastructure Project will construct new drainage facilities to prevent routine flooding occurring at the intersection of Jackson Street and Avenue 50 in the City of Indio. The project aims to permanently de-water the intersection by constructing a flood drainage and underground infiltration system where there is currently none. The City plans to install approximately 2,540 linear feet of 60" perforated underground storage High- Density Polyethylene (HDPE) pipe with gravel pack and filter fabric that will promote water infiltration and groundwater recharge opportunities. The project is estimated to capture 134,000 cubic feet (CF) of water (over a 100-year, 24-hour storm volume) that will then be pre- treated for groundwater recharge.
Scope of Work. The scope of work includes procuring a qualified contractor to construct drainage inlets, relocate existing water/sewer items (as needed), and install roadside underground HDPE perforated piping to prevent future flooding and to provide adequate stormwater retention and infiltration. The project is 90 percent designed and CEQA has been completed.
Background. Due to a lack of drainage facilities, the Jackson Street/Avenue 50 intersection experiences routine flooding, even during minor rain events. Currently, this four-way stop intersection has exceeded its capacity with average daily traffic counts estimated at 10,675 vehicles per day (Ref. CVAG 2017 Traffic Census Report), causing traffic delays and congestion.
Due to the impervious nature of the Jackson Street/Avenue 50 intersection and existing low point of the street, the project site consistently floods during rainfall events. Water then sits for days before slowly draining away or evaporating. The site lacks any type of drainage system except a catch basin located on the southwest corner of the intersection, which is unable to drain the volume of water during a typical rain event. This results in vehicles navigating through significant amounts of water on the roadway causing additional traffic delays, putting life and property at a potential risk.
Implementation of a flood management system will capture and treat stormwater and allow water to help replenish the City’s groundwater storage. The main goal of the proposed project is to construct a new drainage system, where this is currently none, to prevent flooding. New sub-surface drainage facilities will allow for capture of stormwater flows, removal of trash and debris. Reconstruction of curb and gutter will remove the existing low point and cross-gutter at the intersection of Jackson Street and Avenue 50.
See Attachment 1- Design Drawings for reference.
3
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 232 of 527 ŽĂĐŚĞůůĂsĂůůĞLJDŽƵŶƚĂŝŶƐŽŶƐĞƌǀĂŶĐLJʹ WƌŽƉϭ
ŝƚLJŽĨ/ŶĚŝŽʹ :ĂĐŬƐŽŶ^ƚƌĞĞƚĂŶĚǀĞŶƵĞϱϬ&ůŽŽĚ/ŵƉƌŽǀĞŵĞŶƚƐ ƚƚĂĐŚŵĞŶƚϭ
WƌĞůŝŵŝŶĂƌLJŽŶĐĞƉƚƵĂůĞƐŝŐŶ
WĞƌĨŽƌĂƚĞĚ^,W
ƉŝƉĞĂŶĚƚLJƉŝĐĂůŝŶƐƚĂůůĂƚŝŽŶ
4 4
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 233 of 527 ŽĂĐŚĞůůĂsĂůůĞLJDŽƵŶƚĂŝŶƐŽŶƐĞƌǀĂŶĐLJʹ WƌŽƉϭ
ŝƚLJŽĨ/ŶĚŝŽʹ :ĂĐŬƐŽŶ^ƚƌĞĞƚĂŶĚǀĞŶƵĞϱϬ&ůŽŽĚ/ŵƉƌŽǀĞŵĞŶƚƐ ƚƚĂĐŚŵĞŶƚϭ
WƌĞůŝŵŝŶĂƌLJŽŶĐĞƉƚƵĂůĞƐŝŐŶ
ĂƚĐŚďĂƐŝŶƐĂƌĞƐƚŽƌŵŐƌĂƚĞƐƚŚĂƚĐĂŶďĞŝŶƐƚĂůůĞĚ
ĂůŽŶŐƚŚĞƐŝĚĞŽĨƚŚĞƌŽĂĚƚŽĂůůŽǁƌĂŝŶǁĂƚĞƌƚŽ
ĞŶƚĞƌĂĚƌĂŝŶĂŐĞƐLJƐƚĞŵ͘^ŚŽǁŶŚĞƌĞŝƐĂĐƵƌďŝŶůĞƚ
ĐĂƚĐŚďĂƐŝŶ͘tĂƚĞƌĞŶƚĞƌƐƚŚƌŽƵŐŚƚŚĞŐƌĂƚĞŽŶƚŚĞ
ƌŽĂĚĂƐǁĞůůĂƐƚŚĞŽƉĞŶŝŶŐŽŶƚŚĞĨĂĐĞŽĨƚŚĞĐƵƌď͘
dzW/>d,^/EKEE
d/KE
d/>
5 5
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 234 of 527
TITLE SHEET
DECLARATION OF ENGINEER OF RECORD
GEOTECHNICAL ENGINEER'S STATEMENT
VICINITY MAP
N.T.S.
BASIS OF BEARING
“
ABBREVIATIONS
BENCHMARK DATA
CITY OF INDIO PROJECT NO. XXXXXX
CITY OF INDIO'S STANDARD GENERAL NOTES
59835
JOSEPH L. CASTANEDA
12/31/23
31 CITY OF INDIO'S STANDARD GENERAL NOTES
6 6
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 235 of 527 32 J1-1, J1-2, J1-3 AND J1-4
59835
JOSEPH L. CASTANEDA
12/31/23
7 7
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 236 of 527 33 59835
JOSEPH L. CASTANEDA
12/31/23
J2-1, J2-2
8 8
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 237 of 527 34 59835
JOSEPH L. CASTANEDA
12/31/23
J3-1, J3-2
9 9
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 238 of 527 35 59835
JOSEPH L. CASTANEDA
12/31/23
J4-1, J4-2 AND J4-3
10 10
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 239 of 527 36 59835
JOSEPH L. CASTANEDA
12/31/23
A-1 AND A2-1
11 11
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 240 of 527 37 59835
JOSEPH L. CASTANEDA
12/31/23
PROFILE SHEET
12 12
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 241 of 527 38 59835
JOSEPH L. CASTANEDA
12/31/23
PROFILE SHEET
13 13
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 242 of 527
DETAIL SHEET
59835
JOSEPH L. CASTANEDA
12/31/23
39 14
14Page 24 of 67
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 243 of 527
2. Project Location
Project Location. The project is located at the intersection of Jackson Street and Avenue 50 in the City of Indio and Riverside County encompassing 15.6 acres. The site is located along the southeast boundary of the City of Indio where there are no current regional or master plan drainage facilities. The project will improve:
• Jackson Street on the east side to the ultimate cross section from Odlum Drive to Avenue 52 (approximate distance of 8,000 linear feet);
• Avenue 50 to the ultimate cross section on both the north side and south side from Jackson Street to the Indio/Coachella city boundary (approximate distance of 1,000 linear feet); and,
• Avenue 50 on the south side to the ultimate section between the Imperial Irrigation District substation boundary and the Polo Estates improvement area (approximate distance of 300 feet).
See Attachment 2 - Project Location Map for reference.
The project is located within the boundaries of the Coachella Valley Multiple Species Habitat Conservation Plan (CVMSHCP); however, it is not located within a CVMSHCP Conservation Area.
Nonetheless, the project will adhere to all applicable requirements of the CVMSHCP. Applicable requirements of the CVMSHCP were evaluated in the CEQA Initial Study/Mitigated Negative Declaration. Additional technical studies were prepared to support the CEQA document and included cultural resources and paleontological resources assessments and air quality/greenhouse gas analyses. The mitigation monitoring plan can be provided upon request.
Land Ownership. The project site (a total of 15.6 acres) consists of shared jurisdictions between the City of Indio (6.1 acres) and the County of Riverside (9.5 acres). The City of Indio and County of Riverside will complete all initial site control and right-of-way acquisition.
Current Conditions. The Jackson Street/Avenue 50 intersection is an unsignalized four-way stop surrounded by a mix of residential, commercial, and industrial land uses. To the northwest are hundreds of residential homes with industrial/commercial land use to the northeast. On the southeast corner of the intersection is the Coachella Valley Christian Church and an Imperial Irrigation District (IID) Substation is on the southwest corner. Only two of the four corners have paved sidewalks with curbs. However, these pathways are inaccessible during rainfall as water covers the entire intersection flowing over existing curbs due to a lack of drainage facilities.
There is one catch basin located on the northeast corner of the intersection, which does little to alleviate
15
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 244 of 527
flooding - water takes a substantial amount of time to drain through the catch basin and proven ineffective. In addition, road conditions show signs of deterioration; asphalt and concrete cracks are common due to water damage from sitting water during flooding.
See Attachment 3 – Project Site Photos for reference.
16
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 245 of 527 Attachment 2
Project Location Map
Jackson
Street and Avenue 50 Flood Prevention Project
Project Area
City of Indio
- Population 89,996
- 64.9% Hispanic/Latino
- 17.2% living below the poverty
level
Intersection Collisions (2016-2022)
- 24 collisions
- 1 severe
(source: City of Indio)
17 17
AGENDA ITEM #9.11
Resolution No. 10329 ratifying the submission of a grant proposal to the... Page 246 of 527 F i g u r e 1 R e g i o n a l L o c a t i o n M a p Source: Riverside Co. GIS, 2020Map revised March 27, 2020. H:\2019\19-0002\GIS\Regional.mxd P R O J E C T