Cities Index.
Agenda packet

Los Altos Hills City Council
June 26, 2025

Document
Agenda packet
Meeting
June 26, 2025
Body
Los Altos Hills City Council
Pages
485
Original file
69.8 MB
Text extracted from the city's file for reading and search. Open the original on losaltoshillsca.api.civicclerk.com. That file is the official record.

110 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Building Operations (011-3200)
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Licenses and Permits $ 2,529,635 $ 1,364,594 $ 1,835,241 $ 1,647,892 $ 1,043,121 $ 2,012,774 $ 364,882 22% Charges for Services 7,830 5,265 10,330 105,000 - 149,752 44,752 43% Miscellaneous Revenues 32,400 18,588 37,720 - 12,064 - - 0% Total Revenues $ 2,569,865 $ 1,388,447 $ 1,883,291 $ 1,752,892 $ 1,055,185 $ 2,162,527 $ 409,634 23% Expenditures
Personnel $ 372,573 $ 315,439 $ 476,537 $ 587,500 $ 524,542 $ 542,188 $ (45,312) -8% Contractual Services 994,245 639,362 819,917 1,106,558 740,629 782,373 (324,185) -29% Professional Services 185 1,400 24,241 31,955 24,487 - (31,955) 0% Operations 20,436 65,247 72,579 362,641 164,615 237,498 (125,143) -35% Allocations Out 449,825 479,307 515,496 601,894 579,925 634,893 33,000 5% Total Expenditures $ 1,837,263 $ 1,500,754 $ 1,908,769 $ 2,690,548 $ 2,034,198 $ 2,196,953 $ (493,595) -18% Cost Recovery:

The Building Division’s cost recovery target remains between 90% and 95%, consistent with prior financial policies and state law requirements for fee-supported services. As reflected in the financial tables and chart, revenues collected in FY 2024-25 covered a substantial portion of operating costs but fell short of cost recovery, primarily due to fees being less than necessary to achieve targeted revenues Given that the purpose of cost recovery is to collect sufficient fees to offset the staff and consultant costs associated with the full lifecycle of a project, it is important to recognize the timing differences between fee collection and service delivery. The town’s building permit workflow is outlined below.

Plan check fees are collected at the time of initial permit application submittal, while administrative, inspection, impact, and in-lieu fees are collected at permit issuance. However, the services funded by these fees — particularly inspections and construction monitoring — often extend across multiple fiscal years, as many projects in Los Altos Hills, including new home construction and major remodels, typically take two to three years or more to complete.

Building Inspection Expenditures
1,837,263 1,500,754
1,908,769 2,034,198
2,690,548
2,196,953
Actual Budget
0 1,000,000
2,000,000
3,000,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 365 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 111 Depart
ment Budgets
Building Operations (011-3200)
Recent trends, particularly following the COVID-19 pandemic, have led to some projects exceeding even the threeyear construction timeline.

To better align revenues with the timing of expenditures, the Town is implementing a refined strategy to defer the use of inspection-related revenues across multiple fiscal years. This approach will ensure that the revenues collected at permit issuance are matched to the duration of construction activities, smoothing year-over-year revenue and expenditure patterns and protecting the Town against future shortfalls tied to economic cycles or project delays.

Looking forward, the Building Division expects cost recovery performance to improve following the adoption of updated fees based on the Cost-of-Service Study and User Fee Study currently underway. Routine reassessment of fees will ensure continued alignment between fees collected and the actual costs of service delivery while maintaining the Town’s commitment to customer service and operational transparency.

With the delay between the collection of permit fees and the associated expenditure of staff and consultant time, it is important to understand that Building Division revenues and expenses do not necessarily align with the cost recovery model for each fee type. Thus, as long as inspection revenues are pushed forward and the Town’s expenses remain balanced, the Town will be able to maintain cost recovery of 90-95% moving forward. Reassessment every five years is recommended to help ensure effective cost recovery is achieved. This same approach will also be applied to fees within the planning division and engineering departments to ensure they are meeting their cost recovery goals.

STEP 1
STEP 1
STEP 1
STEP 2
STEP 1
STEP 3
STEP 1
STEP 4
STEP 1
STEP 5
STEP 1
STEP 6
STEP 1
STEP 7
STEP 1
STEP 8
Plan reviews are
completed, and
inspection, impact, and
in-lieu fees are
collected, along with any
applicable deposits.

The building permit is
issued, and
construction may
begin.

Inspections are
conducted at specific
construction
milestones.

Inspections may result
in penalty fees,
additional deposits, or
additional plan reviews,
all of which may come
with additional permit
costs. Plan reviews are
collected once the
review is complete.

Once construction is
finished and all
inspections have been
completed, the permit is
finalized, and deposit
refunds can be
requested.

The property records are
reviewed for any
outstanding issues. If
none exist, deposits are
returned.

Documentation is
reviewed for
completeness. Plan
review fees are
collected, and the
technical reviews are
started.

A building permit
application is submitted
to the Town.

Page 366 of 485 ends

112 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Community Services Administration (011-1000)
Community Services (Formerly Parks and Recreation)
Community Services Administration (011-1000)
Mission:

The department develops, implements, and evaluates recreational programs, activities and events for youth, adults, and seniors. Coordinates and supervises recreational uses of Town Hall, Purissima Park, Town Riding Arena and Westwind Community Barn.

Description:

Under the City Manager’s direction, the department comprises one full-time employee, a Community Services Supervisor. Department staff oversees part-time seasonal staff throughout the year, community events, recreation programs, community outreach, independent contractors, Purissima Park, janitorial services for Town facilities, and works closely with Westwind Community Barn Concessionaire.

Program Summary & Major Services:

The Community Services Department performs a variety of assignments including the development, promotion, and management of Town community events, facilities, and recreation programs.

Major services include:
> Community events
> Manages Public Information, and Community Outreach/Engagement on social media, website, and email marketing.
> Produces Bi-Annual Activity Guides
> Manages vendor contracts for community services and recreation services. > Works with Public Works on maintenance/CIP for Purissima Park and Westwind Community Barn > Manages contract with Los Altos/Los Altos Hills Little League and Westwind Community Barn Concessionaire
> Schedules Field and Facility use for Town Hall and Purissima Park > Staff support for Parks, Recreation, and Community Events Committee, Youth and Senior Commissions

Page 367 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 113 Depart
ment Budgets
Community Services Administration (011-1000)
Program Summary:

Activity
Measurement
Method 2022/23 2023/24 2024/25

1. Recreation program
a. Fee Based Classes/Camps April - March 53 84 55
b. Fee-Based Participants April - March 346 409 375
c. Free Programs April - March 56 79 58
d. Total Programs April - March 109 163 113

2. Events FY 17 18 21
a. Shred Event # Households 85/128=213 86/132=218 230
b. Guess the Pumpkins Weights #Entries 98 Entries 223 Entries 210 c. TEDx #Registrations 107
d. Chamber Music #Registrations 56
e. Pathways Run/Walk #Registrations 512 500 424

3. Notarial Acts FY 207 305 110
a. Appointment 100 89 93

4. Field Rental (excludes Little League) FY
# of Bookings 98 60 64
Total Hours Rented 395.5 274.5 285
Revenue $15,680 $5,300 $10,545

4. Westwind Barn Operations FY
a. Summer Camp Registrations 139 145 147
b. Town’s Summer Camp Revenue $17,600 $21,381 $23,358
(scheduled but not held due to COVID-19)
*Limited by Health Restrictions
**Limited due to Phase 1 Council Chambers construction
Department Staffing
The Community Services Department staffing is distributed to various divisions and programs as follows.

Department Staffing

COMMITTEES

COMMUNITY

SERVICES

ADMINISTRATION

PARKS & REC

SPECIAL EVENTS WWB FACILITY
TOTAL 2026 -

PROPOSED
Community Services Supervisor 0.15 0.15 0.50 0.20 1.00
Total Full Time 0.15 0.15 0.50 0.20 1.00

Page 368 of 485 ends

114 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Community Services Administration (011-1000)
Department Goals and Accomplishments:
2024-25 Accomplishments 2025-26 Goals
Town Goal: Maintain Quality of Life & Community Character • Provided community events and activities throughout the year for all ages
• Continue to pivot from virtual/in-person for the changing community needs with COVID-19
• Provided the following in-person community events: Drive Thru Shred Events, Pathways Run/Walk, Car Show, Adult Softball Game, Hoedown, Touch a Truck, Halloween Trick-or-Treating at Town Hall, Barn Lighting, TEDx
• Increase usage of Open Spaces, Pathways and Parks, and Field Rentals
• Conduct Town Surveys for a Facilities Needs Assessment • Deliver monthly community events/activities to enrich the lives of residents
• Promote positive customer service
• Increase program registration
Town Goal: Promote Public Safety
• Continue to use Nixle and social media to disseminate information
• Strengthened number of Community outreach through posting more frequently, updating website
• Completed Annual Inspections on Playground and Outdoor Fitness Equipment
• Ensured all contractors have the Town added as additional insured and contracts updated
• Fire Safety Plan/Emergency Preparedness: Provided consistent messaging and public education for residents regarding safety mitigation measures
• Committees/Volunteers to strengthen effectiveness and leveraged the use of volunteers
• Parks needs assessment: addressed through the budget process • Continue working with PIO team to disseminate information to the community
• Attend trainings for Logistics
• Promote CERT and PEP trainings for the community
• Continue Playground and Outdoor Fitness Equipment annual inspections
• Ensuring all contractors have the Town added as additional insured and contracts updated
Town Goal: Increase Effective Service Delivery & Governance • Made updates to the website, social media, print material, and email marketing materials
• Answered community questions and concerns
• Utilized Recreation software: CivicRec
• Work with community to answer questions and/or concerns • Encouraged community engagement through Committees/
Commissions, programs, activities, and events
• Assist and promote with updating the City Manager Weekly Report
• Work with community to answer questions and/or concerns • Encouraged community engagement through Committees/
Commissions, programs, activities, and events
• Improve Contract Management: Victoria Dye Equestrian
Agreement and Little League Agreement
• Continue Emergency Prep: update training
• Improve Facility Use Policy
• Streamline Facility Rentals
Town Goal: Promote and Maintain Infrastructure
• Assist Public Works with delivery of CIP • Assist Public Works with delivery of CIP

Page 369 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 115 Depart
ment Budgets
Community Services Administration (011-1000)
Budget Summary:

The Community Services Administration expenditures include costs associated with implementing City Council priorities, including community events, Town community surveys, improved communication with staff and Council, increased transparency, and continued emergency preparedness efforts.

The Community Services budget decreased by $559,796, or 62% from the FY 2024-25 adopted budget due to reductions in personnel costs and allocations. This reflects a staffing change from a Community Services Manager and Recreation Specialist in the prior year to a single Community Services Supervisor in FY 2025–26. The increase in Contractual Services and Operations is primarily due to the transfer of activity guide-related costs—including content development, design, and printing—from the City Manager’s budget to the Community Services budget.

With The Quarterly publication no longer in production, the design and implementation of the biannual activity guide has been reinstated within the department. As a result, it is more appropriate for Community Services to manage the project directly. The guide will continue to be supported by consulting services for both design and production.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Expenditures
Personnel $ 151,803 $ 195,679 $ 69,550 $ 156,143 $ 61,618 $ 53,165 $ (102,976) -66% Contractual Services - - 850 3,000 27 32,000 29,000 967% Professional Services 1,633 9 244 2,500 405 2,700 200 8% Operations 29,415 36,990 27,336 16,300 31,436 29,261 12,960 80% Allocations Out 504,798 582,944 569,969 732,037 712,612 233,058 (498,980) -68% Total Expenditures $ 687,648 $ 815,623 $ 667,949 $ 909,980 $ 806,098 $ 350,184 $ (559,796) -62% Community Services Administration Expenditures
687,648
815,623
667,949
806,098 909,980
350,184
Actual Budget
0 500,000
1,000,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 370 of 485 ends

116 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Recreation Programs (011-4110)
Budget Summary:

The Recreation Program’s FY 2024-25 actual expenditures were under budget, reflecting a transitional year marked by strategic realignment and operational efficiencies. While actual revenues were lower than projected, the reduced expenditures demonstrate the department’s ability to adapt and operate leanly during a period of reorganization.

This fiscal year underscored the value of partnerships like LAHCFD and SCCFD and the strength of our volunteer and consultant support network. The lower costs in Contractual Services and Operations are a result of intentional planning, as staff focused on evaluating program delivery models and identifying new opportunities for sustainable growth.

Looking ahead to FY 2025-26, the department is optimistic about re-energizing the Recreation Program through a blend of innovative course offerings and renewed community engagement. With foundational work laid this past year, staff will look to build on these efforts by exploring ways to increase participation, generate additional revenue, and enhance programming, all while continuing to prioritize cost-effective operations.

The Recreation Program’s budget decreased by $27,657, or 60% from the FY 2024-25 adopted budget due to reductions in contract personnel and overhead allocations.

Recreation Programs Expenditures
30,189 33,095 31,580 28,394
45,820
18,163
Actual Budget
0 25,000
50,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 371 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 117 Depart
ment Budgets
Recreation Programs (011-4110)
Tot Lot at Purissima Park
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Charges for Services $ 10,124 $ 9,481 $ 9,584 $ 9,500 $ 6,827 $ 9,500 $ - 0% Total Revenues $ 10,124 $ 9,481 $ 9,584 $ 9,500 $ 6,827 $ 9,500 $ - 0% Expenditures
Personnel $ - $ - $ - $ 605 $ - $ - $ (605) 0%
Contractual Services 7,692 6,763 6,425 16,000 6,800 10,000 (6,000) -37% Operations 434 3,664 1,234 750 369 650 (100) -13%
Allocations Out 22,063 22,667 23,921 28,465 21,226 7,513 (20,952) -74% Total Expenditures $ 30,189 $ 33,095 $ 31,580 $ 45,820 $ 28,394 $ 18,163 $ (27,657) -60%

Page 372 of 485 ends

118 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Special Events (011-4120)
Budget Summary:

Special Events expenditures in FY 2024–25 came in significantly under budget due to a strategic scaling back of operations and a focus on cost containment. Despite reduced costs, the Town successfully delivered a robust calendar of events with the support of volunteers and careful resource management.

With community events remaining a City Council priority, the FY 2025–26 budget reflects a return to more typical funding levels and renewed investment in operations. Staff will continue to explore cost recovery strategies and utilize community feedback to guide programming decisions, ensuring events are engaging, inclusive, and fiscally responsible.

The Special Events budget increased by $25,285, or 10% from the FY 2024-25 adopted budget. The increase is due to an increase in Allocations from a new Cost Allocation Plan. The decrease in Personnel is due to a staffing change: last year’s budget included a Community Services Manager and a Recreation Specialist, whereas the FY 2025–26 budget includes only a Community Services Supervisor.

This year, the Town experienced record-setting attendance at community events, reflecting strong resident engagement and enthusiasm. The event calendar also features a broader array of offerings than in prior years, including new events that appeal to a wide range of age groups and interests.

Special Events Expenditures
125,184 125,184 166,817 166,817
279,533 279,533
131,360 131,360
262,721 262,721 288,006 288,006
Actual Budget
0 200,000
400,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 373 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 119 Depart
ment Budgets
Special Events (011-4120)
Pathways Run
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Charges for Services $ 23,063 $ 26,052 $ 24,976 $ 14,000 $ 19,000 $ 24,000 $ 10,000 71% Total Revenues $ 23,063 $ 26,052 $ 24,976 $ 14,000 $ 19,000 $ 24,000 $ 10,000 71% Expenditures
Personnel $ 7,536 $ 13,398 $ 115,647 $ 115,669 $ 89,581 $ 77,311 $ (38,357) -33% Operations 102,919 138,286 117,120 128,050 27,609 136,600 8,550 7% Allocations Out 14,729 15,132 46,766 19,002 14,170 74,095 55,092 290% Total Expenditures $ 125,184 $ 166,817 $ 279,533 $ 262,721 $ 131,360 $ 288,006 $ 25,285 10%

Page 374 of 485 ends

120 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Parks (Renamed From Field Rentals) (011-5100)
Budget Summary:

The Parks budget reflects expenses related to field maintenance and rentals at Purissima Park and Edith Park.

The Parks budget increased by $82,003, or 33% from the FY 2024-25 adopted budget. The increase in Operations is primarily driven by higher water and electricity costs. The decrease in Contractual Services reflects reduced lawncare and landscaping expenses, partially offset by increased clearing costs.

With rentals expected to rebound, staff will monitor field use trends and maintenance needs closely to ensure high-quality play spaces and sustainable operations moving forward.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Charges for Services $ 51,493 $ 50,212 $ 52,585 $ 55,000 $ 55,000 $ 57,500 $ 2,500 5% Total Revenues $ 51,493 $ 50,212 $ 52,585 $ 55,000 $ 55,000 $ 57,500 $ 2,500 5% Expenditures
Personnel $ 70,647 $ 93,504 $ 79,600 $ 64,193 $ 62,841 $ 91,260 $ 27,067 42% Contractual Services 26,075 25,632 46,816 92,000 62,370 70,740 (21,260) -23% Operations 56,631 67,611 54,267 80,000 63,752 83,564 3,564 4% Allocations Out 11,480 11,794 12,447 14,811 11,044 87,442 72,631 490% Total Expenditures $ 164,833 $ 198,541 $ 193,129 $ 251,003 $ 200,007 $ 333,006 $ 82,002 33% Parks Expenditures
164,833 198,541 193,129 200,007
251,003
333,006
Actual Budget
0 200,000
400,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 375 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 121 Depart
ment Budgets
Westwind Community Barn (011-5300)
Budget Summary:

Westwind Community Barn is a 15-acre property owned by the Town of Los Altos Hills and managed by Concessionaire Victoria Dye Equestrian (VDE). VDE operates the boarding facility and provides instruction. The funding source is Charges for Services; VDE has a new contract and pays the Town 20% of the lesson’s gross revenue and has a step down after $300,000 of gross revenue to 18%. Additionally, the Town collects payment for VDE Riding Camps. Contractual Services is the VDE 80% and 82% split of Camp gross revenue the Town collects and includes VDE concessionaire services approved by the City Council in March 2023. The contract is set to expire on July 31, 2026. In the event of damage caused by weather storms, wildfires, earthquakes or other natural disasters, the Town will cover the costs. For larger projects, VDE must obtain approval of the City Council or City Manager, depending on the scope of the work.

The Westwind Community Barn budget increased by $98,800, or 27% from the FY 2024-25 adopted budget. The increase is due to an increase in Allocations from a new Cost Allocation Plan, as well as Operations costs for supplies.

Westwind Community Barn Expenditures
253,941 280,894 309,386 308,714 364,205
463,005
Actual Budget
0 250,000
500,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 376 of 485 ends

122 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Westwind Community Barn (011-5300)
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Intergovernmental
Subventions $ 5,000 $ - $ - $ 5,000 $ - $ 5,000 $ - 0%
Charges for Services 256,065 248,595 233,545 215,000 198,145 215,000 - 0% Miscellaneous Revenues 500 - - - - - - 0%
Total Revenues $ 261,565 $ 248,595 $ 233,545 $ 220,000 $ 198,145 $ 220,000 $ - 0% Expenditures
Personnel $ 47,853 $ 54,603 $ 83,630 $ 76,356 $ 65,421 $ 80,143 $ 3,788 5% Contractual Services 148,584 182,068 173,503 222,000 175,951 224,780 2,780 1% Professional Services 1,750 - - - - - - 0%
Operations 35,026 22,643 29,857 38,750 41,950 43,926 5,176 13% Allocations Out 20,727 21,580 22,395 27,099 25,391 114,156 87,056 321% Total Expenditures $ 253,941 $ 280,894 $ 309,386 $ 364,205 $ 308,714 $ 463,005 $ 98,800 27%

Page 377 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 123 Depart
ment Budgets
Public Works Administration
Public Works
Public Works Administration
Mission:

To effectively manage the Town’s public infrastructure for the benefit of all users and to provide support to other Town departments.

Organization:

The Public Works Department is composed of engineering and maintenance staff providing support to Town communities and departments and overseeing the Town’s public roadways, pathways, stormwater drainage infrastructure, sanitary sewer system, and facilities.

Description:

The Public Works Department is responsible for major capital projects as well as maintaining the Town’s municipal infrastructure and assets. The department also reviews and inspects any work in the Town’s public right-of-way and works closely with Planning and Building staff on private development projects. The department is headed by the Public Works Director/City Engineer.

Program Summary & Major Services:

The department provides support for private development projects, code enforcement issues, Town events, review and response of resident requests, management of the Town’s capital improvement projects, and oversight and maintenance of the Town’s infrastructure and assets.

Program Summary:

Activity
Measurement
Method 2022/23 2023/24 2024/25

1. Capital project management
a. In progress
• Design phase 13 14 8
• Construction phase 5 5 6
b. Completed 7 8 7

2. Public right-of-way maintenance
a. Pathways Linear miles (LM) 83 83 83
b. Annual tree survey # of trees inspected 220 111 147
• Sudden Oak Death spraying in Byrne Preserve # of trees 238 - 238 c. Streets Maintained ( % of 65 total miles ) Linear miles (LM) 7.4 (12%) 4.1 (6.6%) 4.5 (7.2%) d. Sewer Linear miles (LM) 24.7 25 25

3. Permit Review Total # 120 152 116
a. Sewer # of Sewer Permits 46 40 43

4. Los Altos Hills Connect APP / iWorQ Work Order System & Citizen Engagement
# of service requests (
April 1 to March 31 ) 1183 768 700

Page 378 of 485 ends

124 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Public Works Administration
Department Staffing
Public Works Department staffing is distributed to various divisions and programs as follows.

Page 379 of 485 ends

125 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Department Budgets
Public Works Administration
Building
Operations Committees
Corp Yard
Operations
(for Internal
Service Fund) Engineering Parks
Pathway
Operations Planning
Sewer Fund
Operations
Storm Drain
Operations
Street
Operations
Town Center
Operations
(for Internal
Service Fund)
Vehicle /
Equipment
Operations
(for Internal
Service Fund) Wwb Facility
TOTAL
2026 -

PROPOSED
Assistant Engineer 0.10 0.10 0.05 0.45 0.05 0.40 - 0.40 0.10 0.10 0.25 - - 2.00 Maintenance
Superintendent - - 0.05 - 0.05 0.30 - 0.05 0.10 0.20 0.10 0.10 0.05 1.00 Maintenance Worker I - - 0.05 - 0.05 0.30 - 0.05 0.20 0.25 0.05 0.05 - 1.00 Maintenance Worker II - - 0.05 - 0.10 0.25 - 0.05 0.10 0.25 0.05 0.12 0.03 1.00 Maintenance Worker III - - 0.10 - 0.10 0.60 - 0.10 0.30 0.50 0.10 0.17 0.03 2.00 Project Manager 0.10 - - 0.20 - 0.20 0.20 - 0.10 0.20 - - - 1.00 Public Works Director /
City Engineer 0.05 0.10 0.05 0.10 0.05 0.20 0.05 0.15 0.05 0.10 - 0.05 0.05 1.00 Public Works Inspector 0.10 - - 0.10 0.05 0.20 - 0.20 0.10 0.20 - - 0.05 1.00 Utilities Manager 0.05 0.05 - 0.15 - 0.05 0.05 0.40 0.20 0.05 - - - 1.00 Total Full Time 0.40 0.25 0.35 1.00 0.45 2.50 0.30 1.40 1.25 1.85 0.55 0.49 0.21 11.00

Page 380 of 485 ends

126 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Public Works Administration
Department Goals and Accomplishments:
2024-25 Accomplishments 2025-27 Goals
Town Goal: Maintain Quality of Life & Community Character • Herbicide spraying for selected roadside and off-road pathways to fight stinkwort growth.
• Sudden Oak Death mitigation at Byrne Preserve.
• Addressed approximately 700 work order requests (by end of FY2024/25) through Citizen Engagement portal and iWorQ work order system.
• Stewardship and habitat restoration programs including removal of invasive plants at Byrne Preserve through Grassroot Ecology. • Secured two-year contract extension with Grassroots Ecology for Open Space Stewardship and Education.
• Continue mitigation for roadside pathways and native paths to fight stinkwort growth.
• Increase areas for herbicide spraying to limit stinkwort growth. • Continue Sudden Oak Death mitigation at Byrne Preserve. • Continue to address work order requests through Citizen Engagement portal and iWorQ work order system.

Town Goal: Promote Public Safety
• Started construction for the 2025 Sanitary Sewer Repair Replacement Project.
• Completed Town-wide tree inspections on highly used roadways and pathways, park, and Byrne Preserve. Notified and guided residents on street trees identified as potential hazards. • Sewer operation and maintenance through West Bay Sanitary District.
• Complete construction for the 2025 and 2026 Sanitary Sewer Repair and Replacement project.
• Continue Town-wide tree inspection on highly used roadways and pathways, park, and Byrne Preserve.
• Continue to notify and guide residents of street trees identified with potential hazards.
• Continue sewer operation and maintenance contract with West Bay Sanitary District.
• Apply for grants to complete Local Roadway Safety Plan. • Implement road safety and traffic calming measures on at risk streets.
• Update the Tree Ordinance.

Westwind Community Barn

Page 381 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 127 Depart
ment Budgets
Public Works Administration
Town Goal: Increase Effective Service Delivery & Governance • Preservation of institutional knowledge of Town staff by establishing a standardized filing and archive system.
• Developed a draft of the Public Works Manual for
standardization of process and procedures.
• Provided Public Works updates for the City Manager’s Weekly Report.
• Completed the 2024 Pathway Fee Nexus Study and updated the Pathway In-lieu Fee.
• Promoted biking, walking, and other active means of
transportation through the Measure B Bike/Pedestrian Education & Encouragement Program.
• Purchased two electric vehicles (EVs) for fleet to replace two leased EVs for field visits, inspections, and other Town operations at Town Hall.
• Continue Promoting biking, walking, and other active means of transportation through the Measure B Bike/Pedestrian Education & Encouragement Program.
• Continue to provide Public Works updates for the City Manager’s Weekly Report.
• Continue updating the Public Works Manual for standardization of process and procedures.
• Continue to replace and update Town vehicles and equipment to meet State regulations, Town policies, and goals for Climate Action Plan.

Town Goal: Protect and Maintain Infrastructure
• Bucket/boom truck procurement.
• Ford F250 truck replacement.
• Completed the State Water Board’s annual Storm Water Annual Report.
• Continued to work with Pathway Committee to identify and develop new pathway projects and procedures.
• Completed FY2024/25 Pavement Rehabilitation and Drainage Improvement Project.
• For the El Monte Fire Station Utility Undergrounding (Rule 20A) project, advertised for bid, awarded the construction contract, and completed the joint trench construction for utility companies to undergraound overhead facilities.
• For the Heritage House Upgrade project, completed the Plans and Specificaitons, advertised for bid, awarded the construction project, and submitted all reimbursement invoices to the County for the CDBG program meeting grant requirements.
• For the Corporation Yard Locker Room Phase 1 project, completed the the Plans and Specificaitons, advertised for bid, and awarded the construction project.
• For the Matadero Creek Restoration and Bank Stabilization, completed the value engineering and the Plans and Specifications, advertised for bid, and awarded the construction project. • Replaced over 1/3 of all street name and regulatory signs for the Street Sign Replacement Project.
• Completed offsite mitigation work at Byrne Preserve for the Matadero Creek Restoration and Bank Stabilization project. • Negotiate a fiber infrastructure grant agreement with Los Altos Hills Community Fiber (LAHCF) at priority sites, which Council approved.
• Complete 2025 and 2026 Sanitary Sewer Rehabilitation CIP. • Complete the annual State Water Board’s Storm Water Annual Reports in time.
• Complete FY2025/26 and FY2026/27 Pavement Rehabilitation and Storm Drainage Improvements.
• Work with utility companies to fully underground all overhead facilities at Underground Utility District (UUD).
• Complete the Heritage House Upgrade project.
• Complete the Corp Yard Locker Room Phase 1 project.
• Continue monitoring and maintenance of the offsite mitigation work at Byrne Preserve for the Matadero Creek Restoration and Bank Stabilization project.
• Finalize design and start construction on the Parks & Recreation Building Renovation.
• Finalize updating the pathways fee and develop a long-term plan for pathway construction.
• Construct and rehabilitate pathways as prioritized and approved by the Pathways Committee and City Council.
• Provide routine pathway maintenance and work order service requests throughout the Town pathways.
• Complete design and contruction of Phase 2 of the Summerhill Pathway project
• Complete design and construction of Magdalena Avenue
Pathway.
* Complete design and construction of Page Mill Road -
Christopher’s Lane Pathway Project.
• Initital the design for the Parks and Recreationg Building Renovation.
• Work with LAHCF to complete the installation of fiber infrastructure at priority sites approved by the Technology Committee and the City Council.

Page 382 of 485 ends

128 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Engineering (011-3300)
Budget Summary:

Engineering Administration’s work includes capital improvement management, development reviews, site inspections, contract management, public inquiry research, and support of other Town departments and citizen committees.

The budget decreased by $371,514, or 27% compared to the FY 2024-25 adopted budget largely due to a decrease in billable professional and contract services to be handled by in-house Engineering staff. Engineering review and inspection of private development and sewer projects are reimbursed by applicants. The cost for the Hazardous Waste Program also increased by $15,000 to $35,000.

For FY 2025-26, a Project Manager classification has been created as a mid-level manager position to assist in the management of the Engineering section. This is a promotional opportunity, so there is no change to the total number of full-time employees. The Utility Engineering Manager will focus on managing the sewer and storm infrastructure, while the Project Manager assists in managing engineers for land development reviews, encroachment permits, and CIPs.

Engineering Expenditures
978,883 976,545 1,106,189 1,278,934 1,394,527
1,023,013
Actual Budget
0 1,000,000
2,000,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 383 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 129 Depart
ment Budgets
Engineering (011-3300)
Los Altos Hills Sewer Manhole Replacement Project
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Charges for Services $ 155,081 $ 23,663 $ 105,116 $ 100,000 $ 149,806 $ 130,000 $ 30,000 30% Total Revenues $ 155,081 $ 23,663 $ 105,116 $ 100,000 $ 149,806 $ 130,000 $ 30,000 30% Expenditures
Personnel $ 218,871 $ 299,216 $ 336,634 $ 339,487 $ 311,053 $ 271,174 $ (68,312) -20% Contractual Services 114,764 21,785 89,269 175,000 155,891 107,000 (68,000) -39% Professional Services 30,142 15,098 1,753 51,500 40,500 16,500 (35,000) -68% Operations 52,004 46,790 41,897 83,050 52,699 83,793 743 1% Capital Outlay Spending - - - - 511 - - 0%
Allocations Out 563,103 593,655 636,636 745,490 718,280 544,546 (200,944) -27% Total Expenditures $ 978,883 $ 976,545 $ 1,106,189 $ 1,394,527 $ 1,278,934 $ 1,023,013 $ (371,513) -27%

Page 384 of 485 ends

130 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Sewer (048: Capital, 051: Operation)
Budget Summary:

The Sewer Fund is the Town’s only enterprise fund and is fully supported by sewer service charges to residential and non-residential customers and sewer connection fees for new connections to the sewer system. In 2022, both the sewer connection fees and sewer rate fees were updated to meet the Town’s long-term sewer enterprise funding needs. These funding needs include supporting operations and capital improvements to the Town’s infrastructure.

As a result, the FY 2025-26 and FY 2026-27 sewer service charge rates will increase respectively to $1,957 and $2,035 per main unit of service. FY2026-27 is the last sewer rate increase approved through the 2022 sewer rate study. Each Accessory Dwelling Unit (ADU) sewer service charge is 50% of the main unit service charge.

Due to increasing costs of the Palo Alto Regional Waste Quality Treatment Plant (RWQTP) operations and capital projects, it will be necessary to conduct another sewer rate study in FY 2025-26 in preparation for FY 2026-27.

The Town’s capital budget for sewer main rehabilitation is around $900,000 per year to address the backlog of repairs. In 2024, V.W. Housen & Associates assisted in the development of an asset management approach to the annual sewer capital program. With an overall review of the Town’s sewer system and understanding of the Town’s goals, V.W. Housen & Associates helped develop a five-year capital plan for Town staff to reference when prioritizing project segments for the annual sewer rehabilitation program. The goal still is to limit the number of sanitary sewer overflows (SSOs) and maintain the current service levels. The sewer program expenditures vary from year to year depending on the timing and scope of the capital improvement projects.

While staff manages the overall operations of the sanitary sewer system, the Town contracts with West Bay Sanitary District for the routine maintenance services. Staff manages the sewer contracts, develops and delivers sewer capital projects, prepares studies and long-range planning documents, assists residents with sewer connections and sewer main extensions, and responds to sewer related service requests and emergencies.

The budget increased by $417,959, or 7% from the FY 2024-25 adopted budget. The increase in Contractual Services is primarily due to a $160,000 rise in costs associated with the RWQTP. An additional $125,000 is allocated for consultant services related to Council-directed negotiations with Palo Alto and Los Altos, as well as for a sewer rate study.

Page 385 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 131 Depart
ment Budgets
Sewer (048: Capital, 051: Operation)
Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Use of Money and Property $ (189,081) $ 24,407 $ 171,190 $ - $ 351,516 $ 166,116 $ 166,116 0% Charges for Services 7,349 - 6,145 - 6,691 - - 0%
Miscellaneous Revenues 120 1,946 7,049 - 2,293 - - 0%
Transfers In 9,300 1,179,650 9,858 900,000 910,452 910,976 10,976 1% Sewer Connection Fees 236,512 97,754 154,081 125,660 211,884 129,430 3,770 3% Sewer Assessment Charges 3,070,792 3,263,652 3,534,615 3,715,880 3,719,000 4,105,898 390,018 10% Total Revenues $ 3,134,992 $ 4,567,409 $ 3,882,938 $ 4,741,540 $ 5,201,835 $ 5,312,420 $ 570,880 12% Expenditures
Personnel $ 67,090 $ 353,709 $ 280,727 $ 309,808 $ 461,311 $ 283,190 $ (26,618) -9% Contractual Services 1,981,724 2,088,210 2,461,461 3,141,121 3,068,771 3,436,000 294,879 9% Professional Services 143,013 14,919 13,100 25,500 51,680 25,500 - 0% Operations 29,305 14,823 14,787 18,600 18,498 18,794 194 1% Capital Outlay Spending (82,409) (95,244) (47,931) 900,000 432,409 900,000 - 0% Miscellaneous Expenditures 236,129 260,918 260,918 - - - - 0% Transfers Out - 1,170,350 - 900,000 (900,000) (900,000) - 0% Allocations Out 270,358 289,555 280,939 320,073 348,441 469,578 149,505 47% Total Expenditures $ 2,645,210 $ 4,097,240 $ 3,264,000 $ 5,615,103 $ 5,281,111 $ 6,033,062 $ 417,960 7% Sewer Expenditures
432,409
2,727,619 4,192,484 3,311,931
4,848,702
900,000 900,000
4,715,103 5,133,062
Actual CIP Actual Ops Budget CIP Budget Ops
-4,800,000
-2,400,000
0 2,400,000
4,800,000
7,200,000
9,600,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 386 of 485 ends

132 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Storm Drain Operations (011-4500)
Budget Summary:

The Storm Drain Operations Program involves ongoing management of the Town’s storm infrastructure, including drainage repairs and maintenance, project administration, monitoring, and annual storm water reporting. The major capital storm drainage improvements are funded by the Drainage Fund collected from developments creating more impermeable areas and are addressed by the annual Storm Drain Improvements on an as-needed basis. Staff continues to review updates needed to the 2004 Storm Drainage Infrastructure Master Plan.

The budget increased by $62,613, or 12% from the FY 2025-26 adopted budget. The increase is due to increases in contract services to fund the Storm Drainage fee study.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Expenditures
Personnel $ 160,683 $ 152,423 $ 219,284 $ 257,570 $ 207,198 $ 265,484 $ 7,916 3% Contractual Services 706 245,420 18,763 25,000 8,333 40,000 15,000 60% Professional Services - 800 - 15,000 5,000 15,000 - 0%
Operations 20,091 22,825 31,205 40,100 52,717 40,054 (46) 0% Allocations Out 120,596 132,859 120,769 166,839 166,839 206,584 39,746 24% Total Expenditures $ 302,076 $ 554,327 $ 390,021 $ 504,509 $ 440,087 $ 567,122 $ 62,616 12% Storm Drain Operations Expenditures
302,076
554,327
390,021 440,087 504,509 567,122
Actual Budget
0 250,000
500,000
750,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 387 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 133 Depart
ment Budgets
Street Operations (011-4600)
Budget Summary:

The Street Operations Program supports the ongoing roadway maintenance and operations by the maintenance staff, which includes pavement repairs, crack sealing, and roadside tree maintenance in the public street right-of-way.

The Street Operations budget also covers efforts by the Engineer staff to manage the annual Road Rehabilitation capital program.

The budget increased by $71,685, or 9% from the FY 2024-25 adopted budget. The increase in Personnel is attributed to bringing inspection services in-house, while the decrease in Contractual Services reflects a reduced budget for tree maintenance.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Licenses and Permits $ - $ 652 $ 652 $ - $ 1,387 $ - $ - 0% Miscellaneous Revenues - - 263 - - - - 0%
Total Revenues $ - $ 652 $ 915 $ - $ 1,387 $ - $ - 0%
Expenditures
Personnel $ 208,315 $ 242,952 $ 266,353 $ 314,363 $ 274,345 $ 396,411 $ 82,048 26% Contractual Services 113,487 142,459 87,840 178,300 99,073 148,300 (30,000) -17% Professional Services 3,958 - 2,756 - 159 - - 0%
Operations 12,659 25,487 32,423 27,100 25,101 24,723 (2,377) -9% Allocations Out 236,504 253,144 244,022 317,889 317,889 339,902 22,014 7% Total Expenditures $ 574,923 $ 664,043 $ 633,394 $ 837,652 $ 716,567 $ 909,337 $ 71,685 9% Street Operations Expenditures
574,923 664,043 633,394 716,567 837,652 909,337
Actual Budget
0 500,000
1,000,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 388 of 485 ends

134 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Pathway Operations (011-4740)
Budget Summary:

The Pathway Operations budget increased by $261,331, or 32% from the FY 2024-25 adopted budget, primarily due to higher Personnel costs.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Expenditures
Personnel $ 284,552 $ 348,295 $ 397,589 $ 453,907 $ 438,778 $ 523,648 $ 69,741 15% Contractual Services 84,912 81,431 59,826 90,000 63,881 85,000 (5,000) -6% Professional Services - - - - 350 - - 0%
Operations 2,253 5,246 2,638 12,500 3,455 10,162 (2,338) -19% Allocations Out 188,869 205,248 193,855 257,742 257,742 456,669 198,928 77% Total Expenditures $ 560,586 $ 640,220 $ 653,909 $ 814,148 $ 764,206 $ 1,075,479 $ 261,331 32% Pathway Operations Expenditures
560,586 640,220 653,909 814,148 764,206
1,075,479
Actual Budget
0 500,000
1,000,000
1,500,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 389 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 135 Depart
ment Budgets
Corporation Yard Operations (061-4300)
Budget Summary:

Corporation Yard Operations is an internal service fund division, meaning expenditures are allocated to various departments and accounted for within “Allocations Out”.

The Corporation Yard Operations budget increased by $43,606, or 24% from the FY 2024-25 adopted budget, primarily due to higher Personnel costs, including the addition of standby pay. Additionally, Contractual Services costs rose as a result of transferring Corporation Yard cleaning expenses from the Town Center to the appropriate program.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Allocations In $ 119,337 $ 146,797 $ 142,482 $ 181,682 $ 181,682 $ 225,288 $ 43,606 24% Total Revenues $ 119,337 $ 146,797 $ 142,482 $ 181,682 $ 181,682 $ 225,288 $ 43,606 24% Expenditures
Personnel $ 39,772 $ 59,514 $ 53,210 $ 50,432 $ 75,648 $ 84,169 $ 33,736 67% Contractual Services 29,835 12,035 28,259 25,500 22,347 38,000 12,500 49% Professional Services - - 985 1,000 - 1,000 - 0%
Operations 49,729 69,291 58,662 102,250 49,449 99,619 (2,631) -3% Capital Outlay Spending - 5,744 1,367 2,500 2,851 2,500 - 0% Total Expenditures $ 119,337 $ 146,584 $ 142,482 $ 181,682 $ 150,295 $ 225,288 $ 43,605 24% Corporation Yard Operations Expenditures
119,337 146,584 142,482 150,295 181,682
225,288
Actual Budget
0 100,000
200,000
300,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 390 of 485 ends

136 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Depart
ment Budgets
Vehicle Operations (061-4400)
Budget Summary:

Vehicle Operations is an internal service fund division. Internal Service Fund expenditures are allocated to various departments and accounted for within “Allocations Out.” The Vehicle Operations budget increased by $46,840, or 35% from the FY 2024-25 adopted budget, largely due to increases in personnel costs.

Six-Year Comparison
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal
$ Difference
2024-25
Budget
to 2025-26
% Difference
2024-25
Budget
to 2025-26
Revenues
Allocations In $ 95,468 $ 105,696 $ 94,342 $ 132,086 $ 132,086 $ 178,926 $ 46,840 35% Total Revenues $ 95,468 $ 105,696 $ 94,342 $ 132,086 $ 132,086 $ 178,926 $ 46,840 35% Expenditures
Personnel $ 36,063 $ 44,799 $ 48,707 $ 56,386 $ 84,579 $ 97,165 $ 40,780 72% Contractual Services 1,241 5,332 1,107 5,000 286 5,000 - 0% Operations 33,576 55,565 44,527 70,700 37,809 76,761 6,061 9% Miscellaneous Expenditures 38,075 40,533 37,315 - - - - 0% Total Expenditures $ 108,955 $ 146,230 $ 131,657 $ 132,086 $ 122,674 $ 178,926 $ 46,841 35% Vehicle Operations Expenditures
108,955
146,230 131,657 132,086 122,674
178,926
Actual Budget
0 100,000
200,000
2021-22
Actual
2022-23
Actual
2023-24
Actual
2024-25
Budget
2024-25
Est. Actual
2025-26
Budget
Proposal

Page 391 of 485 ends

(This Page Intentionally Left Blank)

Page 392 of 485 ends

Guide to Five‐
Year CIP

Page 393 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 139 Guide to Five‐Year CIP
Guide to 5-Year CIP
Introduction
The Capital Improvement Program (CIP) identifies the Towns capital investments over a five year term. Itis both a fiscal and strategic device that allows for the planning, scoping, prioritization and monitoring of all capital projects. The document quantifies and defines costs, funding sources, departmental responsibilities, project phases and timing. Each year the CIP is reviewed and updated as part of the Citywide financial planning and goalsetting process. At the same time, it sets a vision for longterm planning. Itis also valuable as a community outreach and communications tool as it speaks to major tax dollar investments that are placed in direct and very visible Citywide infrastructure improvements. Such projects involve larger dollar expenditures that normally have a long useful life cycle.

The CIP includes five years of projected capital needs, the first year of which will be appropriated within the annual budget process. Dollars in the first year of the fiveyear CIP will be authorized for spending in the project planning, bidding and award process. The remaining four years of the CIP serve as a proposed financial plan subject to annual review.

How this Document is Organized
The CIP is broken down into three major sections. The first section is a highlevel overview that describes projects from a variety of informational perspectives. In this section, projects are presented by year, by category and by funding source.

Guide to The Five-Year CIP
The second section provides a detailed description for each capital project within an improvement area or category.

These categories are designed to emphasize the particular infrastructure needs of the Town of Los Altos Hills.

General Capital (041): Accounts for general capital projects including parks and open space improvements, technology purchases, and other infrastructure needs. The main source of revenue comes from the General Fund and special grants, if available.

Pathways (042): Includes updating the pathway system investments. The main sources of revenues are pathway construction fees assessed on site developments and grants. With City Council authorization, General Fund may subsidize any funding gaps. The Pathways Committee, in coordination with Staff, identify and address gaps in the existing pathway system.

Westwind Barn Capital (043): Accounts for facility improvements at Westwind Community Barn. The main source of revenue is Verizon Cell Tower site rental fees. As part of the Westwind Barn Concessionaire agreement, the contracted Barn Management, VDE, prepared a preliminary fiveyear improvement plan.

Drainage Capital (045): Accounts for drainage improvements on Towns right-of-ways and easements. The main sources of revenues are pathway construction fees assessed on site developments and grants. Annual maintenance program is completed in conjunction with the Annual Pavement Rehabilitation program.

Street Capital (046): Accounts for street paving and rehabilitation related capital expenditures. The main sources of revenues are State of California gas tax revenues, encroachment fees, grants and General Fund.

The goal of the program is to maintain the Towns pavement condition index at 80 and above.

Sewer Capital (048): Is part of the Sewer Fund and accounts for sewer system replacements and improvements.

The program is fully supported by sewer fees and charges.

Page 394 of 485 ends

140 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Guide to Five‐Year CIP
Each of the project descriptions within the various service areas display projected costs for each of the next five years including the proposed allocation for FY 2025-26, planned costs for the following four years, a brief description of each project, the identified area of priority/benefit and a brief commentary of the status of ongoing and current expenditures. For projects where the operational cost impact is known, this information is also included in the description. Inflationary factors are also included where appropriate.

CIP Revenue Sources
How CIP Projects Are Financed
When it comes to CIP projects, many cities like the Town of Los Altos Hills, have had to develop a series of internal and external funding mechanisms. This is because local government resources are limited in nature. Many funding sources are restricted in use and subject to discretionary State subventions. Furthermore, local government revenues are highly sensitive to economic movement and prospects for increases are few and far between.

Wherever possible, the Town seeks out external funding sources. These sources, which are restricted to specific application areas, are defined below:

Restricted Revenue Funds
Roadways & Traffic
> Gas Tax Financing is provided by the City’s share of the State tax on gasoline, which can only be used for the research, planning, construction, improvement, maintenance, and operation of public streets and highways or public mass transit corridors.
> Transportation Grants Grant funding from State and Federal sources that can only be used for transportation improvement projects in the Towns right-of-ways. Grants of this type in the Silicon Valley have originated from such agencies as the Valley Transit Authority, Federal Stimulus Funds, and the Metropolitan Transit Commission, among others.
> State Traffic Development Act Funds The Transportation Development Act (TDA) provides two major sources of funding for public transportation: the Local Transportation Fund (LTF) and the State Transit Assistance fund (STA). These funds are for the development and support of public transportation needs that exist in California and are allocated to areas of each County based on population, taxable sales and transit performance. The allocation of these funds is discretionary at the State level.

Community Facilities
> ParkInLieu Fees Funding for open space and parks and recreation facilities can be derived from State and Federal grants and/or mostly developer fees. Developer fees in this area, referred to as Parkinlieu Fees (PIL), are generated based on the growth in the number of livable housing units and can be applied to the acquisition, design, construction or repair of parks and recreation properties and facilities.

Enterprise Funds
> Wastewater Funding from the services rendered on a user surcharge basis to residents located in Los Altos Hills. These revenues also support operation and maintenance of the utility systems. The capital portion is used for underground pipelines, diversion systems, pump stations and distribution channels.

CIP project costs in this area are supported by a multiyear Master Plan for this substantial utility system.

Page 395 of 485 ends

(This Page Intentionally Left Blank)

Page 396 of 485 ends

Capital
Improvement
Plan Summary
and Funding
Sources

Page 397 of 485 ends

143 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improvement Plan Summary and Funding Sources

PROPOSED CAPITAL IMPROVEMENT PROGRAM SUMMARY
FY 2025-2026 through FY 2029-2030
Division Project # Project Name Funding Sources Remaining Budget 2025/26 Budget 2026/27 Budget 2027/28 Budget 2028/29 Budget 2029/30 Budget Total Infrastructure
419300 BROADBAND
INFRASTRUCTURE CIP/ General Fund $ 759,624 $ 0 $ 0 $ 0 $ 0 $ 0 $ 759,624 TR4169-26 BYRNE PRESERVE
RESTORATION CIP/ General Fund $ 57,754 $ 101,310 $ 104,349 $ 0 $ 0 $ 0 $ 263,413 410209-26 CABLE SERVICE COST
SHARING PROGRAM CIP/ General Fund $ 0 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 410234 CORPORATION YARD
IMPROVEMENTS CIP/ General Fund $ 96,548 $ 0 $ 0 $ 0 $ 0 $ 0 $ 96,548 410230 CORPORATION YARD LOCKER
ROOM CIP/ General Fund $ 313,152 $ 0 $ 0 $ 0 $ 0 $ 0 $ 313,152 410216

EL MONTE FIRE STATION

UNDERGROUNDING PROJECT
(RULE 20A) Rule 20A $ 974,192 $ 0 $ 0 $ 0 $ 0 $ 0 $ 974,192 410224 HERITAGE HOUSE UPGRADE CIP/ General Fund $ 553,855 $ 0 $ 0 $ 0 $ 0 $ 0 $ 553,855 410220 HOUSING ELEMENT CIP/ General Fund $ 614,776 $ 53,000 $ 0 $ 0 $ 0 $ 0 $ 667,776 410227-26 MISCELLANEOUS
TECHNOLOGY CIP/ General Fund $ 13,730 $ 80,000 $ 50,000 $ 50,000 $ 0 $ 0 $ 193,730

NEW PARKS AND RECREATION
CENTER RENOVATION (NEW) CIP/ General Fund $ 0 $ 200,000 $ 1,300,000 $ 0 $ 0 $ 0 $ 1,500,000 410225

PURISSIMA PARK

IMPROVEMENT PROGRAM
(FIELD & FACILITY
IMPROVEMENTS) CIP/ General Fund $ 81,379 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ 0 $ 201,379

NEW ROAD SAFETY AND TRAFFIC
CALMING CIP/ General Fund $ 0 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 300,000 410235 SECURITY CAMERA UPGRADE CIP/ General Fund $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 0 $ 0 $ 400,000 410226 STREET SIGN REPLACEMENT CIP/ General Fund $ 15,375 $ 25,000 $ 25,000 $ 25,000 $ 0 $ 0 $ 90,375 410236 TOWN FACILITIES ENERGY
EFFICIENCY (NEW) CIP/ General Fund $ 60,000 $ 150,000 $ 0 $ 0 $ 0 $ 0 $ 210,000 410233 TRAFFIC SIGNAL
IMPROVEMENTS CIP/ General Fund $ 30,821 $ 20,000 $ 0 $ 0 $ 0 $ 0 $ 50,821 410228 WATER WELL AT PURISSIMA
PARK CIP/ General Fund $ 35,013 $ 200,000 $ 0 $ 0 $ 0 $ 0 $ 235,013 Infrastructure
Total $ 3,706,219 $ 1,069,310 $ 1,719,349 $ 315,000 $ 140,000 $ 110,000 $ 7,059,878 Pathways
NEW

MAGDALENA AVENUE
PATHWAY (NEW) Pathway Fund $ 315,000 $ 315,000
NEW

MAPLE LEAF - MIDDLE FORK
LANE PATHWAY (NEW) Pathway Fund $ 100,000 $ 150,000 $ 250,000 427913-26 MISCELLANEOUS PATHWAYS TDA $ 45,136 $ 0 $ 0 $ 0 $ 0 $ 0 $ 45,136 Pathway Fund $ 0 $ 50,000 $ 0 $ 100,000 $ 100,000 $ 100,000 $ 350,000

Page 398 of 485 ends

144 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improvement Plan Summary and Funding Sources

PROPOSED CAPITAL IMPROVEMENT PROGRAM SUMMARY
FY 2025-2026 through FY 2029-2030
Division Project # Project Name Funding Sources Remaining Budget 2025/26 Budget 2026/27 Budget 2027/28 Budget 2028/29 Budget 2029/30 Budget Total 427902 SUMMERHILL PATHWAY Pathway Fund $ 379,018 $ 100,000 $ 0 $ 0 $ 0 $ 0 $ 479,018 Pathways Total $ 424,154 $ 565,000 $ 150,000 $ 100,000 $ 100,000 $ 100,000 $ 1,439,154 Road Rehabilitation
467226-26

ANNUAL ROAD

REHABILITATION PROGRAM
Vehicle Registration
Fees SB 83 $ 0 $ 66,500 $ 69,800 $ 73,300 $ 77,000 $ 80,900 $ 367,500 Street Encroachment
Fees $ 107,100 $ 112,500 $ 118,100 $ 124,000 $ 130,200 $ 591,900 SB1 Funds $ 0 $ 229,559 $ 241,000 $ 253,100 $ 265,800 $ 279,100 $ 1,268,559 Measure B $ 0 $ 254,596 $ 214,158 $ 224,900 $ 236,100 $ 247,900 $ 1,177,654 Gas Tax $ 0 $ 247,920 $ 260,300 $ 273,300 $ 287,000 $ 301,400 $ 1,369,920 Drainage in-lieu $ 0 $ 40,000 $ 40,000 $ 40,000 $ 40,000 $ 40,000 $ 200,000 CIP/ General Fund $ 111,212 $ 429,325 $ 437,242 $ 392,300 $ 345,100 $ 320,500 $ 2,035,679 NEW

LOCAL ROAD SAFETY PLAN
(NEW) Other -TBD $ 0 $ 60,000 $ 0 $ 0 $ 0 $ 0 $ 60,000
CIP/ General Fund $ 0 $ 20,000 $ 0 $ 0 $ 0 $ 0 $ 20,000 467228

MEASURE B BIKE/

PEDESTRIAN EDUCATION &
ENCOURAGEMENT PROGRAM Measure B $ 73,206 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 123,206 Road Rehabilitation Total $ 184,417 $ 1,465,000 $ 1,385,000 $ 1,385,000 $ 1,385,000 $ 1,410,000 $ 7,214,417 Sewer
487918-26

ANNUAL SANITARY SEWER
REPLACEMENT AND REHAB Sewer User Charges $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ 0 $ 4,615,579 Sewer Total $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ 4,615,579 Storm Drain
467209 MATADERO CREEK EROSION Drainage in-lieu $ 458,124 $ 0 $ 0 $ 0 $ 0 $ 0 $ 458,124 CIP/ General Fund $ 514,500 $ 514,500
457202

STORM DRAIN
IMPROVEMENTS Drainage in-lieu $ 77,842 $ 0 $ 0 $ 0 $ 0 $ 0 $ 77,842 Storm Drain Total $ 1,050,465 $ 0 $ 0 $ 0 $ 0 $ 0 $ 1,050,465 Vehicle and Equipment
NEW

VEHICLE AND EQUIPMENT
REPLACEMENT (NEW) CIP/ General Fund $ 0 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Vehicle and Equipment Total $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Westwind Community Barn
437307-26

WESTWIND COMMUNITY
BARN IMPROVEMENTS Westwind Barn Capital $ 240,000 $ 0 $ 0 $ 0 $ 0 $ 0 $ 240,000 CIP/ General Fund $ 50,000 $ 50,000
Cell Tower Rental $ 54,354 $ 50,000 $ 50,000 $ 50,000 $ 0 $ 0 $ 204,354 Westwind Community Barn Total $ 344,354 $ 50,000 $ 50,000 $ 50,000 $ 0 $ 0 $ 494,354 Grand Total $ 6,175,188 $ 4,149,310 $ 4,554,349 $ 3,000,000 $ 2,775,000 $ 1,720,000 $ 22,373,847

Page 399 of 485 ends

145 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improvement Plan Summary and Funding Sources

CAPITAL IMPROVEMENT PROGRAM FUNDING SOURCE
FY 2025-2026 through FY 2029-2030
Funding Source Remaining Balance as of 3/31/2025 Fiscal Year 2025/26 Budget Fiscal Year 2026/27 Budget Fiscal Year 2027/28 Budget Fiscal Year 2028/29 Budget Fiscal Year 2029/30 Budget Total Project
Funding
CDBG $ - $ - $ - $ - $ - $ - $ -
Cell Tower Rental $ 54,354 $ 50,000 $ 50,000 $ 50,000 $ - $ - $ 204,354 CIP/ General Fund $ 3,407,738 $ 1,618,635 $ 2,256,591 $ 807,300 $ 585,100 $ 530,500 $ 9,205,865 Drainage in-lieu $ 535,965 $ 40,000 $ 40,000 $ 40,000 $ 40,000 $ 40,000 $ 735,965 Gas Tax $ - $ 247,920 $ 260,300 $ 273,300 $ 287,000 $ 301,400 $ 1,369,920 Measure B $ 73,206 $ 264,596 $ 224,158 $ 234,900 $ 246,100 $ 257,900 $ 1,300,859 Other -TBD $ - $ 60,000 $ - $ - $ - $ - $ 60,000
Pathway Fund $ 379,018 $ 565,000 $ 150,000 $ 100,000 $ 100,000 $ 100,000 $ 1,394,018 Rule 20A $ 974,192 $ - $ - $ - $ - $ - $ 974,192
SB1 Funds $ - $ 229,559 $ 241,000 $ 253,100 $ 265,800 $ 279,100 $ 1,268,559 Sewer User Charges $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ - $ 4,615,579 Street Encroachment Fees $ - $ 107,100 $ 112,500 $ 118,100 $ 124,000 $ 130,200 $ 591,900 TDA $ 45,136 $ - $ - $ - $ - $ - $ 45,136
Vehicle Registration Fees SB 83 $ - $ 66,500 $ 69,800 $ 73,300 $ 77,000 $ 80,900 $ 367,500 Westwind Barn Capital $ 240,000 $ - $ - $ - $ - $ - $ 240,000 Grand Total $ 6,175,188 $ 4,149,310 $ 4,554,349 $ 3,000,000 $ 2,775,000 $ 1,720,000 $ 22,373,847

Page 400 of 485 ends

146 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

BROADBAND INFRASTRUCTURE
Department: Public Works
Program: Infrastructure
Project Number: 419300
Initial funding year: FY 2022-23
Planned start date: July 2022
Estimated completion date: Q2 FY2025/26
Project Description
The Town applied for the American Rescue Plan Act funds (ARPA) in March 2021 and received $1,007,480 on July 13, 2021. The same amount was received in 2022. At the February 17, 2022 City Council meeting, a resolution was passed to designate a portion of the ARPA funds to create a broadband master plan and to install broadband in areas of Los Altos Hills.

Project Status
The Broadband Feasibility Study was completed in 2023.

In April 2024, the City Council directed staff to work with the Technology Committee to find an eligible broadband infrastructure expenditure using ARPA funds. On May 21, 2024, the City Council authorized staff to negotiate an agreement with Los Altos Hills Community Fiber (LAHCF) to install underground fiber at priority Town sites. Working with the Technology Committee and LAHCF, a funding agreement was negotiated for underground fiber installation at priority sites that include along Fremont Road (near Town Hall) and at La Loma Drive/Prospect Avenue/Stonebrook Drive to the CERT emergency services facility (ARK) located at Foothill college. The funding agreement was approved by Council on October 22, 2024, and the term expires end of 2025.

LAHCF is working separately with Foothill College to install a broadband infrastructure connection between Foothill College and O’Keefe Road through El Monte Road under Highway 280. This work is proposed to be funded by Foothill College.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Broadband Infrastructure $ 813,105 $ 40,376 $ 772,729 $ 13,105 $ 759,624 Total: $ 813,105 $ 40,376 $ 772,729 $ 13,105 $ 759,624
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 759,624 $ 759,624
Total Funding: $ 759,624 $ - $ - $ - $ - $ - $ 759,624
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Broadband Infrastructure $ -
Total Spending: $ - $ - $ - $ - $ - $ - $ -
Recurring annual maintenance and operating costs, if applicable Maintenance and operational needs would be determined through the feasibility study.

Page 401 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 147 Capital Improve
ment Plan Summary and Funding Sources

BYRNE PRESERVE RESTORATION
Department: Public Works
Program: Infrastructure
Project Number: TR4169-26
Initial funding year: FY 2022-23
Planned start date: July 2022
Estimated completion date: June 2027
Project Description
Since 2013, the Town facilitated a stewardship program and public outreach activities for Byrne Preserve, with the goal of preserving Town assets and building community value that protects and enhances our environment. Grassroots Ecology has been the primary vendor at Byrne Preserve, providing habitat restoration activities along Moody Creek, removal of invasive plants, replanting native vegetation, monitoring plant establishment, and replanting as necessary. Grassroots Ecology has also organized volunteer and educational events related to the preservation of open space.

Grassroots Ecology was selected to continue providing services at Byrne Preserves for three years starting in July 2022.

Project Status
With the three-year contract expiring end of FY2024/25, the Town has negotiated a two-year extension for Grassroots Ecology to continue their services until June 30, 2027.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Byrne Preserve Restoration $ 289,575 $ 231,821 $ 57,754 $ 57,754 Total: $ 289,575 $ 231,821 $ 57,754 $ - $ 57,754
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 57,754 $ 101,310 $ 104,349 $ 263,413 Total Funding: $ 57,754 $ 101,310 $ 104,349 $ - $ - $ - $ 263,413 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Byrne Preserve Restoration $ 74,381 $ 101,310 $ 104,349 $ 280,040 Total Spending: $ 74,381 $ 101,310 $ 104,349 $ - $ - $ - $ 280,040 Recurring annual maintenance and operating costs, if applicable The purpose of this program is to remove invasive non-native plants and allow native plants to grow naturally. There is no ongoing maintenance necessary once the native plants have matured.

Page 402 of 485 ends

148 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

CABLE SERVICE COST SHARING PROGRAM
Department: City Manager’s Office
Program: Infrastructure
Project Number: 410209-26
Initial funding year: FY 2022-23
Planned start date: July 2024
Estimated completion date: Ongoing program
Project Description
The City Council believes that it is in the public’s interest to have adequate cable services available to all residents for better access to public safety information, more opportunity for civic engagement, and enhancing education and digital literacy. The purpose of this cost sharing program is to establish a means by which the Town can provide limited financial support for the construction of broadband/cable system equipment within public ways. In August 2016, the City Council approved and adopted Cost Sharing Policy for the Construction of Comcast Cable System Infrastructure Within Public Ways, where the Town will contribute 25% of the cable expansion cost, with a cap of $25,000.

Project Status
In March of 2025 the City Council increased eligibility of this program to cover costs of any internet service provider installing any broadband/cable system equipment in the public right of way (no longer just Comcast). There are no current applications for cost sharing.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Cable Service Expansion $ 50,000 $ 50,000 $ 50,000 $ -
Total: $ 50,000 $ - $ 50,000 $ 50,000 $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 Total Funding: $ - $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Cable Service Expansion $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 Total Spending: $ - $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 250,000 Recurring annual maintenance and operating costs, if applicable Maintenance and operational needs would be determined during the design phase.

Page 403 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 149 Capital Improve
ment Plan Summary and Funding Sources

CORPORATION YARD IMPROVEMENTS
Department: Public Works
Program: Infrastructure
Project Number: 410234
Initial funding year: FY 2024-25
Planned start date: Summer 2024
Estimated completion date: Q2 FY2026/27
Project Description
In the summer of 2024, the Corporation Yard Master Plan Study was completed. This project would fund priority improvements recommended in the study, including the purchase and installation of Conex containers for additional on-site storage, garage door repairs/upgrades, seal coating of the yard pavement, installation of electric vehicle charging stations, and implementation of a backup power system.

Project Status
One Conex container has been purchased and installed in March 2025. The garage door repairs/upgrades anticipated by fall 2025 with a cost estimate of around $25,000. Staff started investigating options for the electric vehicle charging stations.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Improvements $ 100,000 $ 3,452 $ 96,548 $ - $ 96,548
Total: $ 100,000 $ 3,452 $ 96,548 $ - $ 96,548
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 96,548 $ - $ - $ - $ - $ - $ 96,548 Total Funding: $ 96,548 $ - $ - $ - $ - $ - $ 96,548
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Improvements $ 96,548 $ - $ - $ - $ - $ - $ 96,548
Total Spending: $ 96,548 $ - $ - $ - $ - $ - $ 96,548
Recurring annual maintenance and operating costs, if applicable Maintenance and operational needs would be determined during design and construction phases.

Page 404 of 485 ends

150 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

CORPORATION YARD LOCKER ROOM
Department: Public Works
Program: Infrastructure
Project Number: 410230
Initial funding year: FY 2023-24
Planned start date: Summer 2023
Estimated completion date: Q2 FY2025/26
Project Description
In 2022, staff recommended improvements to the Corporation Yard Building to add a locker room with shower and restroom facilities.

The Town’s maintenance members currently use an office space as a locker room to store their safety gear and personal items, and a single unisex restroom is shared. The project is to ensure that maintenance staff have adequate locker room facilities. The Corporation Yard Master Plan Study, completed in July 2024, identified the locker room as a priority project for the facility.

Due to the fire protection/sprinkler requirements for the full locker room on the second floor, the project has been phased. In December 2024, Council approved the conceptual plans for the Corporation Yard Locker Room Project - Phase I involving a new accessible unisex restroom with a shower and lockers on the first floor and a new HVAC system for the building. The future phase would include converting an office space on the second floor into a locker room adequate for the maintenance staff, as well as installing a new fire sprinkler system for the building. which would require a separate fire water line from Purissima Hills Water District.

Project Status
Phase I construction is anticipated to start in summer 2025.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Locker Corp Yard $ 340,000 $ 26,848 $ 313,152 $ - $ 313,152 Total: $ 340,000 $ 26,848 $ 313,152 $ - $ 313,152
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 313,152 $ - $ - $ - $ - $ - $ 313,152 Total Funding: $ 313,152 $ - $ - $ - $ - $ - $ 313,152
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Locker Corp Yard $ 313,152 $ - $ - $ - $ - $ - $ 313,152 Total Spending: $ 313,152 $ - $ - $ - $ - $ - $ 313,152 Recurring annual maintenance and operating costs, if applicable A minor increase to the janitorial services contract.

Page 405 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 151 Capital Improve
ment Plan Summary and Funding Sources
EL MONTE FIRE STATION UNDERGROUNDING PROJECT (RULE 20A) Department: Public Works
Program: Infrastructure
Project Number: 410216
Initial funding year: FY 2019-20
Planned start date: October 2020
Estimated completion date: Q2 FY2025/26
Project Description
The California Public Utilities Commission (CPUC) Rule 20A underground program allows cities and counties to utilize Rule 20A credits (funded by PG&E ratepayers) to finance utility undergrounding projects at locally designated underground districts. The Town has currently $4,656,261 in Rule 20A credit allocation.

The Town has identified the emergency routes near El Monte Fire Station (El Monte Road, Elena Road, and Moody Road) as the underground district area. In October 2020, the Town hired Bellecci & Associates to prepare the undergrounding composite plans and assist with coordination with PG&E and other utility companies. In March 2023, PG&E assigned an estimating team to the Town’s project. The plans, specifications, and estimates (Form B) for the project were completed in April 2024 and approved by the participating utility companies (PG&E, AT&T, and Comcast).

The Town would initially cover the project costs, to be reimbursed through its Rule 20A credit balance and other utility undergrounding programs.

Project Status
The project was advertised for bid in April 2024 and bids were received in May 2024. Joint trench construction started August 2024 and was completed by February 2025. Overhead to underground conversion work by utility companies is anticipated to be completed by fall 2025.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
CIP/General Fund $ 300,000 $ 300,000 $ - $ -
Rule 20A credits 4,656,261 3,682,069 974,192 974,192
Total: $ 4,956,261 $ 3,982,069 $ 974,192 $ - $ 974,192
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Rule 20A $ 974,192 $ - $ - $ - $ - $ - $ 974,192
Total Funding: $ 974,192 $ - $ - $ - $ - $ - $ 974,192
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Rule 20A expenditures $ 974,192 $ - $ - $ - $ - $ - $ 974,192 Total Spending: $ 974,192 $ - $ - $ - $ - $ - $ 974,192 Recurring annual maintenance and operating costs, if applicable No maintenance and operating cost applicable.

Page 406 of 485 ends

152 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

HERITAGE HOUSE UPGRADE
Department: Public Works
Program: Infrastructure
Project Number: 410224
Initial funding year: FY 2021-22
Planned start date: February 2023
Estimated completion date: Q1 FY2025/26
Project Description
The renovation of the Heritage House interior aims to better accommodate various users, including the community, volunteers, and staff who utilize the space. The renovations will ensure protection of historically significant elements of the house while complying with ADA and Building Code provisions. Having already extended a data line from Town Hall to the Heritage House, this CIP will further extend that line throughout the house and provide Wi-Fi service with a direct Ethernet cable connection from the IT room.

Project Status
The Town received $400,000 in Community Development Block Grant (CDBG) funding from the U.S. Department of Housing and Urban Development (HUD) through the County Office of Supportive Housing in May of 2024. CDBG funds were approved soley for ADA access improvements to the Heritage House.

The Heritage House Upgrade project begun construction in December 2024 and is expected to be completed by fall 2025. The Town has invoiced the full $400,000 grant amount for CDBG by April 2025, meeting the grant program deadline. The County will retain ten percent of the amount until the completion of the project and when the first annual program report is received by HUD.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Heritage House Upgrade $ 1,270,000 $ 716,145 $ 553,855 $ 553,855 Total: $ 1,270,000 $ 716,145 $ 553,855 $ - $ 553,855
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 553,855 $ - $ - $ - $ - $ - $ 553,855

CDBG - -
Total Funding: $ 553,855 $ - $ - $ - $ - $ - $ 553,855
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Heritage House Upgrade $ 553,855 $ - $ - $ - $ - $ - $ 553,855 Total Spending: $ 553,855 $ - $ - $ - $ - $ - $ 553,855 Recurring annual maintenance and operating costs, if applicable Additional costs for custodian service, routine maintenance, and utilities anticipated with more active use of the facility.

Page 407 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 153 Capital Improve
ment Plan Summary and Funding Sources

HOUSING ELEMENT
Department: Planning
Program: Infrastructure
Project Number: 410220
Initial funding year: FY 2021-22
Planned start date: July 2021
Estimated completion date: May 2026
Project Description
Since 1969, California has required that all local governments (cities and counties) adequately plan to meet the housing needs of everyone in the community. To date, California is now in its sixth Housing Element cycle (2023-2031) for jurisdictions in the Bay Area).

Before each cycle, the State provides a target for how many homes to plan for in every jurisdiction, known as Regional Housing Needs Allocation (RHNA). On January 30, 2023, the City Council adopted the 6th cycle Housing Element in substantial compliance with the State law, which was timely submitted to California Housing and Community Development Department (HCD) for post-adoption certification. The adopted 6th cycle Housing Element is introducing multi-family zones to accommodate density at twenty (20) to thirty (30) dwellings per acre. The proposed change will require an amendment to the Land Use Element of the General Plan and Municipal Code to establish the multi-family zones with objective development and design standards. In addition, the proposed rezoning requires a Program Environmental Impact Report (EIR) pursuant to the California Environmental Quality Act (CEQA).

The state law requires Safety Element be to be updated with an Housing Element update. Safety Element identifies the need for local jurisdictions to understand their vulnerablities to hazards such as seismic hazards, wildfires, geologic issues, flooding climate change, and other natural hazards. The Safety Element shall also comply with Senate Bill (SB) 379 requirements.

Project Status
The statutory deadline for jurisdictions in the Bay Area to adopt a Housing Element is January 31, 2023, and Los Altos Hills successfully achieved this. Jurisdictions that have their Housing Element certified as compliant by HCD by May 31, 2023 are allowed three (3) years to complete the EIR and Rezoning. The Town awarded a $350,000 contract to Michael Baker International (MBI) for the Housing Element and Safety Element updates. After coordinating with HCD on several technical revisions to the Housing Element, the Town was advised by HCD on May 12, 2023 that the revised Housing Element had been certified as compliant by HCD. The Town also awarded another $601,620 contract to the same consultant for preparation of Zoning standards, objective design standards, and Program EIR to meet the three (3) year timeframe to complete the EIR and Rezoning. Now in 2025 The town has choosen to reduce the denisity to twenty (20) to twenty four (24) dwellings per acre as well as adjusting the zoning approach to target less acrage being rezoned on the twin oaks opertunity site. This Amendment to the certified housing element will rerequire a contract amendment with MBI which if approved through budgeting process will add another $300,000 to the existing contract.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Housing Element $ 1,456,000 $ 841,224 $ 614,776 $ 614,776 Total: $ 1,456,000 $ 841,224 $ 614,776 $ - $ 614,776

Page 408 of 485 ends

154 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 614,776 $ 53,000 $ 667,776
Total Funding: $ 614,776 $ 53,000 $ - $ - $ - $ - $ 667,776 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Housing Element $ 614,776 $ 53,000 $ 667,776
Total Spending: $ 614,776 $ 53,000 $ - $ - $ - $ - $ 667,776 Recurring annual maintenance and operating costs, if applicable N/A

Page 409 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 155 Capital Improve
ment Plan Summary and Funding Sources

PURISSIMA PARK IMPROVEMENT PROGRAM (FIELD & FACILITY IMPROVEMENTS) Department: Public Works
Program: Infrastructure
Project Number: 410225
Initial funding year: FY 2021-22
Planned start date: Ongoing
Estimated completion date: Ongoing
Project Description
List of improvements at Purissima Park to be completed in phases:

1. Continued repair of fencing to provide better safety to those outside of playing fields.

2. Upgrade water fountains (4), adding a fillable station in the back by the basketball court.

3. Parking lot maintenance (re-stripe and seal coat)

4. Playground repair/maintenance, including installing new engineered fibar mulch.

Project Status
Field 3 (P3) fence repair and parking lot pavement digout repairs completed in summer 2023. Field 2 (P2) fence repair completed in spring 2025. Fields 1 (P1) & 4 (P4) fences are planned to be repaired in 2026.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Purissima Park Improvement $ 140,000 $ 58,621 $ 81,379 $ 81,379 Total: $ 140,000 $ 58,621 $ 81,379 $ - $ 81,379
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 81,379 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ - $ 201,379 Total Funding: $ 81,379 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ - $ 201,379 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Purissima Park Improvement $ 81,379 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ - $ 201,379 Total Spending: $ 81,379 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ - $ 201,379 Recurring annual maintenance and operating costs, if applicable No maintenance and operating cost applicable.

Page 410 of 485 ends

156 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

SECURITY CAMERA UPGRADE
Department: City Manager’s Office
Program: Infrastructure
Project Number: 410235
Initial funding year: FY 2024-25
Planned start date: July 2024
Estimated completion date: Ongoing program
Project Description
The security camera system at Town Hall, the Corporation Yard, and Westwind Community Barn need to be replaced. This replacement project was identified on the 2024-25 two-year City Council Work Plan, and reaffirmed in the update to the plan in January 2025. Staff is working with the Technology Committee to research options for each site. It is estimated that each location will cost roughly $100,000 to install. The new system will comply with all state and federal requirements of security camera recording on public land.Given the large cost to the project, staff is recommending to upgrade one location per year at a time (Town Hall 2025, Corp Yard 2026, Westwind Barn, 2027)
Project Status
Staff began working on this project in late 2024, and should have a recommendation to being to the City Council for contract in 2025 for the Town Hall location. No costs were incurred in FY 2024-25. Any budget augmentation can take place at that time.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Security Camera System $ 100,000 $ - $ 100,000 $ - $ 100,000 Total: $ 100,000 $ - $ 100,000 $ - $ 100,000
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ - $ 400,000 Total Funding: $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ - $ 400,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Security Camera System $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ - $ 400,000 Total Spending: $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ - $ 400,000 Recurring annual maintenance and operating costs, if applicable The camera system staff proposes include a service and licensing fee within the proposed budget.

Page 411 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 157 Capital Improve
ment Plan Summary and Funding Sources

STREET SIGN REPLACEMENT
Department: Public Works
Program: Infrastructure
Project Number: 410226
Initial funding year: FY 2021-22
Planned start date: March 2022
Estimated completion date: Ongoing
Project Description
Town street signs require upgrades to meet current sign standards such as for retro-reflectivity. This street sign project began in 2022 with an annual budget of $15,000, which was increased to $25,000 in FY2024/25. The majority of the costs is to purchase street signs, posts, hardware, concrete, and other materials for installation by the Town’s maintenance staff.

Project Status
Regulatory and warning signs such as STOP and YIELD are also being replaced in accordance with CA MUTCD’s new standards. Town maintenance staff have replaced approximately 1/3 of all street signs as of spring 2025.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Street Sign Replacement $ 54,000 $ 38,625 $ 15,375 $ 15,375 Total: $ 54,000 $ 38,625 $ 15,375 $ - $ 15,375
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 15,375 $ 25,000 $ 25,000 $ 25,000 $ 90,375 Total Funding: $ 15,375 $ 25,000 $ 25,000 $ 25,000 $ - $ - $ 90,375 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Street Sign Replacement $ 15,375 $ 25,000 $ 25,000 $ 25,000 $ 90,375 Total Spending: $ 15,375 $ 25,000 $ 25,000 $ 25,000 $ - $ - $ 90,375 Recurring annual maintenance and operating costs, if applicable No maintenance and operating cost applicable.

Page 412 of 485 ends

158 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

MISCELLANEOUS TECHNOLOGY
Department: Administrative Services
Program: Infrastructure
Project Number: 410227-26
Initial funding year: FY 2022-23
Planned start date: July 2022
Estimated completion date: On Going
Project Description
The Miscellaneous Technology CIP for FY 25-26 is designed to improve the Town’s Technology for larger projects that are identified under the Town’s IT Master Plan and are not already included in the operating budget. Projects covered under this CIP will be managed by the City Manager’s Office. This CIP is designed to allow for projects to be completed on shorter timelines as our IT Services vendor can complete.

Project Status
The Town just completed it’s next 3-year IT strategic plan which covered the years of 2026-2028. The proposed IT projects scheduled for FY 25-26 include (but are not limited to): Develop Intranet using SharePoint, Upgrade website, Implementation of an A.I. chatbot for the website, Deploy IT disaster recovery + business continuity plan, and launching a password manager for employees.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Technology $ 100,000 $ 86,270 $ 13,730 $ 13,730
Total: $ 100,000 $ 86,270 $ 13,730 $ - $ 13,730
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 13,730 $ 80,000 $ 50,000 $ 50,000 $ 193,730 Total Funding: $ 13,730 $ 80,000 $ 50,000 $ 50,000 $ - $ - $ 193,730 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Technology $ 13,730 $ 80,000 $ 50,000 $ 50,000 $ 193,730 Total Spending: $ 13,730 $ 80,000 $ 50,000 $ 50,000 $ - $ - $ 193,730 Recurring annual maintenance and operating costs, if applicable N/A

Page 413 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 159 Capital Improve
ment Plan Summary and Funding Sources

TOWN FACILITIES ENERGY EFFICIENCY (NEW)
Department: Public Works
Program: Infrastructure
Project Number: 410236
Initial funding year: FY 2024-25
Planned start date: Summer 2024
Estimated completion date: End of 2026
Project Description
Town is looking to work with an Energy Services Company (ESCO) to conduct energy audits of Town facilities including Town Hall, Heritage House, Parks & Recreation building, Westwind Community Barn, and Corporation Yard. ESCO will also provide recommendations and design for improvements for energy efficiency for implementation, if approved by the City Council. Government Code Section 4217 authorizes local governments to enter into Energy Saving Performance Contracts on terms that are found to be “in the best interests” of the agency, “notwithstanding any other provision of law.” In essence, this law allows a public entity to sole-source or directly engage into an energy contract as long as the anticipated cost(s) for the energy project or efficiency services is less than the anticipated energy cost savings to be derived from those services over the term of the contract.

Project Status
Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Energy Audit & Design $ 60,000 $ - $ 60,000 $ 60,000
Construction - -
Total: $ 60,000 $ - $ 60,000 $ - $ 60,000
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 60,000 $ 150,000 $ 210,000
Total Funding: $ 60,000 $ 150,000 $ - $ - $ - $ - $ 210,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Energy Audit & Design $ 60,000 $ 60,000
Construction $ - $ 150,000 $ 150,000
Total Spending: $ 60,000 $ 150,000 $ - $ - $ - $ - $ 210,000 Recurring annual maintenance and operating costs, if applicable Maintenance and operational needs would be determined during design and construction phases

Page 414 of 485 ends

160 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

TRAFFIC SIGNAL IMPROVEMENTS
Department: Public Works
Program: Infrastructure
Project Number: 410233
Initial funding year: FY 2023-24
Planned start date: Fall 2023
Estimated completion date: Q4 FY2025/26
Project Description
Aging traffic signal equipment at the three signalized intersections along El Monte Road at Voorhees Drive, Stonebrook Drive, and Foothill College require upgrades and modernization. Controller units at Voorhees Drive and Stonebrook Drive intersections require replacements. This project scope will include replacement of traffic signal controller units, installation of battery backup systems and detection cameras, and other updates needed to the Town’s three signalized intersections.

Project Status
Controllers replaced and backup battery system installed for all three intersections. Install detection cameras by end of FY2025/26.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Equipment Replacements $ 70,000 $ 39,179 $ 30,821 $ 30,821 Total: $ 70,000 $ 39,179 $ 30,821 $ - $ 30,821
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 30,821 $ 20,000 $ 50,821
Total Funding: $ 30,821 $ 20,000 $ - $ - $ - $ - $ 50,821 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Equipment Replacements $ 30,821 $ 20,000 $ 50,821
Total Spending: $ 30,821 $ 20,000 $ - $ - $ - $ - $ 50,821 Recurring annual maintenance and operating costs, if applicable New equipment will be maintained by traffic signal maintenance contractor as part of the current scope.

Page 415 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 161 Capital Improve
ment Plan Summary and Funding Sources

WATER WELL AT PURISSIMA PARK
Department: Public Works
Program: Infrastructure
Project Number: 410228
Initial funding year: FY 2021-22
Planned start date: 2022
Estimated completion date: TBD
Project Description
Investigate the viability of a new well and, if viable, drill a new water well; install a water pump and electrical wiring; upgrade the electrical panel; and modify irrigation conduits irrigation at the Little League Fields. A geological desktop study was conducted in September 2022. The geologist recommended additional field investigation, including a site-specific hydrogeologic analysis and drilling a pilot boring to a maximum depth of 400 feet to determine the water table.

Project Status
A geological desktop study has been completed. Additional field investigations and hydrogeologic analyses are expected to begin in 2026.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Water Well at Purissima Park $ 40,000 $ 4,987 $ 35,013 $ 35,013 Total: $ 40,000 $ 4,987 $ 35,013 $ - $ 35,013
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ 35,013 $ 200,000 $ - $ - $ - $ - $ 235,013 Total Funding: $ 35,013 $ 200,000 $ - $ - $ - $ - $ 235,013 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Water Well at Purissima Park $ 35,013 $ 200,000 $ - $ - $ - $ - $ 235,013 Total Spending: $ 35,013 $ 200,000 $ - $ - $ - $ - $ 235,013 Recurring annual maintenance and operating costs, if applicable Maintenance and operational needs would be determined during design and construction phases.

Page 416 of 485 ends

162 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

ROAD SAFETY AND TRAFFIC CALMING (NEW)
Department: Public Works
Program: Infrastructure
Project Number: NEW
Initial funding year: FY 2025/26
Planned start date: Q1 FY2025/26
Estimated completion date: Ongoing
Project Description
Road safety and traffic calming measures shall implement strategies to improve road and pathway safety and reduce vehicle speeds, especially in pedestrian-heavy areas. The goal is to create safer environments for everyone, including drivers, pedestrians, and cyclists.

Road safety and traffic calming measures can consist of signages and markings, intersection modifications, crosswalk enhancements, roadway narrowing, speed humps/tables/cushils, and others to be based on best traffic engineering practices and judgements to produce desired effects.

Project Status
Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Design & Construction $ - $ - $ - $ - $ -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ - $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 300,000 Total Funding: $ - $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 300,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design & Construction $ - $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 300,000 Total Spending: $ - $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 60,000 $ 300,000 Recurring annual maintenance and operating costs, if applicable May depend on the roadway safety and traffic calming measures.

Page 417 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 163 Capital Improve
ment Plan Summary and Funding Sources

PARKS AND RECREATION CENTER RENOVATION (NEW)
Department: Public Works
Program: Infrastructure
Project Number: NEW
Initial funding year: FY 2025/26
Planned start date: Early 2026
Estimated completion date: TBD
Project Description
As one of the design options for the Civic Center Improvements, the City Council approved the concept design for the renovation of the Parks & Recreation building. The goal of the project is to improve the Parks & Recreation Center to create a more functional workspace for Town employees and to make necessary improvements at Town Hall to accommodate any relocation of staffing and programs.

The renovation scope for the Parks and Recreation Center will include making ADA upgrades, modifying the building configuration, creating additional workspaces, improvements to the HVAC system, optimize storage, and potentially expanding the building footprint.

Additional funds may be need if fire sprinklers are required for the Parks and Recreation building and for electrification of the building.

Project Status
The final design phase is anticipated to begin early 2026.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Design $ - $ - $ - $ -
Construction - -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ - $ 200,000 $ 1,300,000 $ 1,500,000 Total Funding: $ - $ 200,000 $ 1,300,000 $ - $ - $ - $ 1,500,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design $ - $ 200,000 $ - $ - $ - $ - $ 200,000
Construction $ - $ - $ 1,300,000 $ - $ - $ - $ 1,300,000 Total Spending: $ - $ 200,000 $ 1,300,000 $ - $ - $ - $ 1,500,000 Recurring annual maintenance and operating costs, if applicable Staff to continue maintenance of Parks & Recreation building.

Page 418 of 485 ends

164 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

MISCELLANEOUS PATHWAYS
Department: Public Works
Program: Pathways
Project Number: 427913-26
Initial funding year: FY 2021-22
Planned start date: Summer 2021
Estimated completion date: Ongoing
Project Description
The Miscellaneous Pathways Capital Improvement Project is designed to improve the Town’s pathways system by filling in gaps and repairing existing segments. The projects included in this CIP will be selected from a list that is maintained and regularly updated by the Pathways Committee. Once the list of eligible projects has been established, work would be initiated and completed by staff and/ or contractor. This CIP is intended to facilitate the completion of smaller pathway projects with shorter timelines as opportunities arise.

Any projects requiring extensive planning, design, and construction would be converted to an individual CIP projects.

Pathway CIPs are funded by the Pathway Fund from pathway development impact fees. Due to escalating costs of pathways design and construction, the Town is in the process of updating the pathway impact fee to be implemented in FY2025/26.

Project Status
In 2024, Town Staff focused on the feasibility and analysis of off-road pathways. The Saddle Mountain–Stirrup Way off-road path was installed in December 2024. For 2025, staff is focusing on the feasibility of roadside pathways and the design of the roadside pathway on Magdalena Avenue. A separate CIP for Magdalena Avenue roadside pathway is proposed for FY2025/26.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
Pathway Fund
Remaining
Budget
Design/Construction $ 1,020,136 $ 520,647 $ 499,489 $ 454,353 $ 45,136 Total: $ 1,020,136 $ 520,647 $ 499,489 $ 454,353 $ 45,136 Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Pathway Fund $ - $ 50,000 $ - $ 100,000 $ 100,000 $ 100,000 $ 350,000 TDA 45,136 45,136
Total Funding: $ 45,136 $ 50,000 $ - $ 100,000 $ 100,000 $ 100,000 $ 395,136 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design/Construction $ 45,136 $ 50,000 $ - $ 100,000 $ 100,000 $ 100,000 $ 395,136 Total Spending: $ 45,136 $ 50,000 $ - $ 100,000 $ 100,000 $ 100,000 $ 395,136 Recurring annual maintenance and operating costs, if applicable The projects in the CIP would be funded by a reoccurring annual contribution from the Pathway Fund, as determined by the City Council.

The general maintenance of the Town’s pathway system would not be funded by this CIP.

Page 419 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 165 Capital Improve
ment Plan Summary and Funding Sources

SUMMERHILL PATHWAY
Department: Public Works
Program: Pathways
Project Number: 427902
Initial funding year: FY 2015-16
Planned start date: June 2016
Estimated completion date: Q2 FY2026/27
Project Description
The existing pedestrian route along Summerhill Avenue on the Town side (west side) iconsists of pathway segments and paved roadway shoulders within the County of Santa Clara public right-of-way. Easements are normally secured as part of property development process; therefore, some parcels along Summerhill Avenue lack necessary easements. Additionally, existing pathways along Summerhill Avenue alternate between sides of the roadway, forcing pedestrians to cross the busy County street.

Phase 1 of the project installed pathways on Summerhill Avenue between El Monte Road and Nicole Lane in 2019. Phase 2 will be from Nicole Lane to Magdalena Avenue, which falls under County jurisdiction.

Project Status
Staff is still working with the County of Santa Clara Roads & Airports Department to obtain an encroachment permit for the project, pending approval of a tree removal permit, a maintenance and indemnification agreement, and improvement plans. Construction is anticipated to begin in summer 2026.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Design/Construction $ 526,103 $ 147,085 $ 379,018 $ 379,018 Total: $ 526,103 $ 147,085 $ 379,018 $ - $ 379,018
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Pathway Fund $ 379,018 $ 100,000 $ 479,018
Total Funding: $ 379,018 $ 100,000 $ - $ - $ - $ - $ 479,018 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design/Construction $ 379,018 $ 100,000 $ 479,018
Total Spending: $ 379,018 $ 100,000 $ - $ - $ - $ - $ 479,018 Recurring annual maintenance and operating costs, if applicable Pathways require annual maintenance. Maintenance costs for the new pathway shall be determined.

Page 420 of 485 ends

166 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

MAGDALENA AVENUE PATHWAY (NEW)
Department: Public Works
Program: Pathways
Project Number: NEW
Initial funding year: FY 2025-26
Planned start date: July 2025
Estimated completion date: Q2 FY2026/27
Project Description
Magdalena Avenue was identified as a priority location for new roadside pathway for FY2025-26 by the Pathways Committee.

Approximately 2,000 linear feet of new pathway segments are proposed along Magdalena Avenue, adjacent to Camino Hermoso Drive on the northern side of the street. Currently, there are segments of unimproved shoulder, which are proposed to be improved with a Type 2B Roadside Path in accordance with the Town’s standards.

Project Status
Topographic survey and staking started in April 2025 and is funded through the Miscellaneous Pathways CIP.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Design & Construction $ - $ - $ - $ - $ -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Pathway Fund $ - $ 315,000 $ - $ - $ - $ - $ 315,000
Total Funding: $ - $ 315,000 $ - $ - $ - $ - $ 315,000
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design/Construction $ - $ 315,000 $ - $ - $ - $ - $ 315,000 Total Spending: $ - $ 315,000 $ - $ - $ - $ - $ 315,000 Recurring annual maintenance and operating costs, if applicable Pathways require annual maintenance. Maintenance costs for the new pathway shall be determined.

Page 421 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 167 Capital Improve
ment Plan Summary and Funding Sources

MAPLE LEAF - MIDDLE FORK LANE PATHWAY (NEW)
Department: Public Works
Program: Pathways
Project Number: NEW
Initial funding year: FY 2025-26
Planned start date: July 2025
Estimated completion date: Q2 FY2027/28
Project Description
The City Council, following a recommendation from the Pathways Committee, directed staff to add the Maple Leaf Court to Middle Fork Lane pathway segment to the Town’s Master Path Plan (MPP). This off-road segment is approximately 1,230 feet long and would traverse through rolling hills, existing vegetation, and a seasonal stream. An Initial Study would be required for a CEQA determination before this segment can be considered for inclusion in the MPP. The Initial Study and CEQA determination may take up to a year to finalize. Changes to the MPP are considered General Plan amendments, as it is an integral component of the Pathway Element.

Project Status
Staff will issue an RFP in spring 2025 to hire a planning and environmental consultant for the Initial Study.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Initial Study $ - $ - $ - $ - $ -
Design/Construction - - - - -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Pathway Fund $ - $ 100,000 $ 150,000 $ - $ - $ - $ 250,000 Total Funding: $ - $ 100,000 $ 150,000 $ - $ - $ - $ 250,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Initial Study $ - $ 100,000 $ - $ - $ - $ - $ 100,000
Design/Construction $ - $ - $ 150,000 $ - $ - $ - $ 150,000 Total Spending: $ - $ 100,000 $ 150,000 $ - $ - $ - $ 250,000 Recurring annual maintenance and operating costs, if applicable Pathways require annual maintenance. Maintenance costs for the new pathway shall be determined.

Page 422 of 485 ends

168 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

ANNUAL ROAD REHABILITATION PROGRAM
Department: Public Works
Program: Road Rehabilitation
Project Number: 467226-26
Initial funding year: FY 2025-26
Planned start date: Fall 2025
Estimated completion date: Q4 FY2025/26
Project Description
The annual street resurfacing program is designed to maintain safe and functional Town streets. The project includes 6” AC deep lift patching, 2” asphalt concrete overlay, micro-surfacing, and all associated work. Street resurfacing includes corresponding drainage improvements. The street selections are based on recommendations from the Metropolitan Transportation Commission’s (MTC’s) Pavement Management Program (StreetSaver), utility coordination, and field inspections. Upon completion of the design phase, a list of streets and the type of work required are presented to the City Council for an authorization to advertise for bid. The roadway segments currently prioritized for the FY2025/26 resurfacing project are shown in the table below. The FY2025/26 project street list is from an updated five-year StreetSaver plan developed by the Town’s MTC consultant. After more indepth site evaluations, project coordination, design, and cost analysis, the FY2025/26 project street list may be further updated.

Project Status
Plans and specifications for the FY2025/26 street resurfacing project to be completed by early 2026 for construction start early summer 2026.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Annual Pavement Rehab $ 1,425,978 $ 1,314,766 $ 111,212 $ 111,212 Total: $ 1,425,978 $ 1,314,766 $ 111,212 $ - $ 111,212
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Gas Tax $ - $ 247,920 $ 260,300 $ 273,300 $ 287,000 $ 301,400 $ 1,369,920 SB1 Funds - 229,559 241,000 253,100 265,800 279,100 1,268,559 Vehicle Registration Fees SB 83 - 66,500 69,800 73,300 77,000 80,900 367,500 Drainage in-lieu - 40,000 40,000 40,000 40,000 40,000 200,000 Street Encroachment Fees - 107,100 112,500 118,100 124,000 130,200 591,900 Measure B - 254,596 214,158 224,900 236,100 247,900 1,177,654 CIP/ General Fund 111,212 429,325 437,242 392,300 345,100 320,500 2,035,679 Total Funding: $ 111,212 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,400,000 $ 7,011,212 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Annual Pavement Rehab $ 111,212 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,400,000 $ 7,011,212 Total Spending: $ 111,212 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,375,000 $ 1,400,000 $ 7,011,212 Recurring annual maintenance and operating costs, if applicable No additional maintenance and operating cost. This program focuses on addressing system deficiencies to maintain operating cost at the current level.

Page 423 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 169 Capital Improve
ment Plan Summary and Funding Sources

MEASURE B BIKE/PEDESTRIAN EDUCATION & ENCOURAGEMENT PROGRAM Department: Public Works
Program: Road Rehabilitation
Project Number: 467228
Initial funding year: FY 2024-25
Planned start date: Summer 2024
Estimated completion date: Ongoing
Project Description
Santa Clara County voters have approved 2016 Measure B, a 30-year, half-cent countywide sales tax to enhance transit, highways, expressways and active transportation (bicycles, pedestrians and complete streets). The measure passed by nearly 72%, the highest level of support for any Santa Clara County transportation tax. Collection of the tax began on April 1, 2017. As one of the approved Measure B programs, Bicycle and Pedestrian Education & Encouragement (E&E) Program provides annual funding to jurisdictions in the county for non-capital improvement projects to promote and educate communities to safely walk, bike, and resort to other multimodal and active transportation options. The E&E program funds are allocated by city population formula with a $10,000 annual minimum allocation per city, and the funds are distributed on a reimbursable basis. The Town is responsible for submitting an annual education & encouragement work program and annual progress report. The Town’s annual allocation of Measure B E&E funds since FY2017-18 has been between $10,000 to $20,000.

Project Status
As of FY2023-24, the total E&E allocation remaining for the Town is $73,286.70.Since FY2023-24, staff has been working on various E&E eligible projects including participating in Bike Month events with the City of Los Altos, working on and implementing Safe Routes to School related programs, and distributing merchandise promoting pathway usage.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
E&E Program $ 80,853 $ 7,647 $ 73,206 $ 73,206
Total: $ 80,853 $ 7,647 $ 73,206 $ - $ 73,206
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Measure B $ 73,206 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 123,206 Total Funding: $ 73,206 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 123,206 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
E&E Program $ 73,206 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 123,206 Total Spending: $ 73,206 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 123,206 Recurring annual maintenance and operating costs, if applicable Staff operating costs may be eligible for Measure B E&E fund reimbursement.

Page 424 of 485 ends

170 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

LOCAL ROAD SAFETY PLAN (NEW)
Department: Public Works
Program: Road Rehabilitation
Project Number: NEW
Initial funding year: FY 2025/26
Planned start date: Early 2026
Estimated completion date: Late 2026
Project Description
A Local Road Safety Plan (LRSP) is an initiative in the State’s Highway Safety Improvement Program (HSIP). Preparing a LRSP provides jurisdictions with an opportunity to address unique local roadway safety needs while contributing to the success of the Strategic Highway Safety Plan. The process of preparing an LRSP establishes a framework for systematically identifying and analyzing safety problems and recommending safety improvements. Additionally, preparing an LRSP facilitates the formation of local agency partnerships and collaboration, resulting in a prioritized list of improvements and actions that demonstrate a clear need and alignment with the Statewide plan. The LRSP offers a proactive approach to addressing safety concerns and showcases an agency’s commitment to improving roadway safety. An LRSP (or its equivalent) will be preferred or required for an agency to be eligible for future federal HSIP funds and other transporation projects.

Project Status
Staff to seek grant funds to implement LRSP, such as the Safe Street and Roads for All (SS4A) grant. SS4A grants have a 20% local match requirement.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
LSRP $ - $ - $ - $ -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ - $ 20,000 $ - $ - $ - $ - $ 20,000 Other -TBD - 60,000 - - - - 60,000
Total Funding: $ - $ 80,000 $ - $ - $ - $ - $ 80,000
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
LRSP $ - $ 80,000 $ - $ - $ - $ - $ 80,000
Total Spending: $ - $ 80,000 $ - $ - $ - $ - $ 80,000
Recurring annual maintenance and operating costs, if applicable N/A

Page 425 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 171 Capital Improve
ment Plan Summary and Funding Sources

ANNUAL SANITARY SEWER REPLACEMENT AND REHAB
Department: Public Works
Program: Sewer
Project Number: 487918-26
Initial funding year: Ongoing
Planned start date: Ongoing
Estimated completion date: Ongoing
Project Description
The main objective of the annual sanitary sewer replacement and rehabilitation program is to repair and improve defective sewer pipes in the Town’s sanitary sewer system, ensuring the uninterrupted conveyance of wastewater to the Palo Alto Regional Water Quality Control Treatment Plant (RWQCTP) through the collection systems of the Cities of Palo Alto and Los Altos. The selection of the sewer segments is based on the review and analysis of the first cycle of CCTV inspections of the Town’s sewer pipes, along with follow-ups from the Town’s sewer maintenance and operation contractor, West Bay Sanitary District.

The Regional Water Quality Control Board has placed an increased emphasis on reviewing sewer system capital improvement programs and operation/maintenance activities, requiring a higher annual sewer replacement rate for agencies with aging sewer collection systems. In alignment with this approach, Town staff recommends an annual average of $900,000 in capital expenditures to address the most problematic areas and to reduce the need for high-frequency cleaning required to keep the system operational and prevent sanitary sewer overflows (SSOs). The annual allocation will be validated, reviewed, and updated as needed during each budget cycle.

In March 2024, V.W. Housen & Associate was hired to develop an asset management protocol to more effectively and holistically determine capital improvement needs and projects. The study was completed in fall 2024.

Project Status
Construction of 2025 Sewer Rehabilitation Project to be completed by fall 2025.

Due to rising capital costs from Palo Alto and Los Altos and in order to maintain an annual budget of $900,000 for sewer capital projects, a new sewer rate study may be required in FY2025/26.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Sewer Rehab CIP $ 900,000 $ 434,421 $ 465,579 $ 465,579 Total: $ 900,000 $ 434,421 $ 465,579 $ - $ 465,579
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Sewer User Charges $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ - $ 4,615,579 Total Funding: $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ - $ 4,615,579 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Sewer Rehab CIP $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ - $ 4,615,579 Total Spending: $ 465,579 $ 900,000 $ 1,150,000 $ 1,050,000 $ 1,050,000 $ - $ 4,615,579 Recurring annual maintenance and operating costs, if applicable The maintenance and operating costs for the Town’s sanitary sewer system is included in the annual operating budget for the sewer program.

Page 426 of 485 ends

172 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improvement Plan Summary and Funding Sources
FY2024-26 Anticipated Sewer Capital Projects:

FY2024-26 Sewer Rehabilitation Projects$ 1,350,000.00
Manhole Cover Replacement Project$ 300,000.00
O’Keefe Pump Station - Control Panel Upgrade$ 100,000.00 Root foaming for sewer mains$ 50,000.00
Total$ 1,800,000.00

Page 427 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 173 Capital Improve
ment Plan Summary and Funding Sources

WESTWIND COMMUNITY BARN IMPROVEMENTS
Department: Public Works
Program: Westwind Community Barn
Project Number: 437307-26
Initial funding year: Ongoing Program
Planned start date: Ongoing
Estimated completion date: Ongoing
Project Description
The annual Westwind Community Barn facility improvements program is designed to improve facility deficiencies and meet the the needs of Barn users. Each year, the Town and Concessionaire, Victoria Dye Equestrian (VDE), identify and prioritize potential improvements. The following projects were identified and prioritized:

1. Lower Arena: Replace and upgrade the existing perimeter fence and sprinkler system, improve site drainage, and regrade and improve the footing.

2. Upper Arena: Regrade and reconstruct the footing with a new textile and sand blend.

3. Installation of Footing Grid Systems in Remaining Five Paddocks: Rain causes water pooling and mud, making paddock grounds unusable. Installing footing grid systems or paddock slabs will help stabilize the grounds. Footing grids for 13 paddocks have been installed. Regrading and the installation of footing grid systems for the remaining five paddocks are estimated cost $60k for each paddock.

4. Paddock Retaining Wall/Fencing repairs: When installing or upgrading paddock footing grids, certain paddocks will also require repairs to their retaining wall/fencing.This involves reinforcing or replacing the posts and lagging boards.

5. Repair Footing Grids in Previously Upgraded Paddocks: Repair footing grids in paddocks that have previously been upgraded with grid systems.

6. Rehabilitation of Barn Exteriors: As funding allows, rehabilitate thelower half of 17 barn exterior doors, sliding doors, and the fence in the courtyard.

7. Addional Toilet: The Barn currently has one existing toilet and a room with a shower. As funding becomes available, adding an additional toilet to the shower room would be beneficial for camp participants, boarders, and event attendees.

8. Electrical Upgrade: Upgrades to the Barn’s electrical systems.

Project Status
The repair of the retaining wall/fencing, regrading, and installation of footing grid systems for one paddock were completed in FY2023-

24. For the Upper Arena, the current plan is to replace and upgrade the footing materials during the summer of 2025. Regarding the improvements needed at the Lower Arena, construction is also anticipated to begin in the summer of 2025, once authorized by the Council.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Paddock Footing $ 172,623 $ 40,280 $ 132,343 $ 132,343
Wall/Fencing 129,994 7,389 122,605 122,605
Lower Arena - -
Upper Arena - -
Drinking Fountain 15,000 - 15,000 15,000
Electrical Upgrade 40,000 - 40,000 40,000
Restroom Renovation $ 3,043 $ 3,043 $ - $ -

Page 428 of 485 ends

174 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Cell Tower Rental $ 54,354 $ 50,000 $ 50,000 $ 50,000 $ - $ 204,354 Westwind Barn Capital 240,000 240,000
CIP/ General Fund 50,000 50,000
Total Funding: $ 344,354 $ 50,000 $ 50,000 $ 50,000 $ - $ - $ 494,354 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Paddock Footing $ 132,343 $ 30,000 $ 30,000 $ 30,000 $ - $ - $ 222,343 Lower Arena $ - $ - $ -
Upper Arena - - -
Wall/Fencing 122,605 20,000 20,000 20,000 182,605
Electrical Upgrade 40,000 40,000
Drinking Fountain 15,000 15,000
Restroom Renovation - -
Feeding Pasture Fencing - -
Water line repairs - -
Site Drainage 34,406 34,406
Total Spending: $ 344,354 $ 50,000 $ 50,000 $ 50,000 $ - $ - $ 494,354 Recurring annual maintenance and operating costs, if applicable These projects are part of an ongoing maintenance program. Minor maintenance is the responsibility of VDE. Repairs above $500 are the Town’s responsibility.

Page 429 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 175 Capital Improve
ment Plan Summary and Funding Sources

MATADERO CREEK EROSION
Department: Public Works
Program: Storm Drain
Project Number: 467209
Initial funding year: FY 2011-12
Planned start date: Ongoing
Estimated completion date:

Q1 FY2025/26; Mitigation monitoring for
10 years
Project Description
The project aims to repair erosion along the edge of Page Mill Road between Baleri Ranch Road and Berry Hill Court at Matadero Creek.

This section of Page Mill Road is within Caltrans right-of-way. Due to the significant overall expense of the erosion repair project, the lengthy permitting process, and the risk of the travel lane being washed out, the project was divided into two phases.

Phase 1 stabilized the roadway and included a geotechnical investigation, topographic survey, design, construction, and inspection work.

Phase 2 will address the creek erosion repair, including environmental study, hydraulic study, permitting process with state and federal agencies, design, construction, inspections, and mitigation/monitoring work as required by the State Water Resources Control Board (Water Board).

Project Status
The cattails and sediments in Matadero Creek at Page Mill Road were removed in January 2023 due to flooding concerns from the atmospheric river storm events.

The Matadero Creek Bank Stabilization onsite project was first advertised in June 2024, and bids opened in July 2024. Four bids were received, and bid prices were at least 21% higher than the Engineer’s estimate. In July 2024, the City Council approved a resolution to reject all bids. Subsequently, the design was value engineered and improved without a new soldier pile retaining wall. In March 2025, the City Council approved the plans and specifications for the project to be advertised. The bids will be opened in May, and construction is anticipated to begin in July and be completed by November.

Water Board has certified the project and conditioned a mitigation and monitoring plan (MMP). The tributary area to Moody Creek at Byrne Preserve is the location for the offsite mitigation, which involves planting vegetation across 1.96 acres of the riparian corridor.

The offsite mitigation work at Byrne Preserve was completed in January 2025. Maintenance and monitoring of this offsite mitigation work will continue for ten (10) years as required by the Water Board.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Phase I $ 338,490 $ 338,490 $ - $ -
Phase 2 Design 429,800 404,169 25,631 25,631
Phase 2 Construction 716,000 716,000 716,000
Mitigation 300,000 69,008 230,992 230,992
Total: $ 1,784,290 $ 811,666 $ 972,624 $ - $ 972,624

Page 430 of 485 ends

176 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Drainage in-lieu $ 458,124 $ 458,124
CIP/ General Fund 514,500 514,500
Total Funding: $ 972,624 $ - $ - $ - $ - $ - $ 972,624
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Phase 2 Design $ 25,631 $ 25,631
Phase 2 Construction $ 716,000 $ 716,000
Mitigation 230,992 230,992
Total Spending: $ 972,624 $ - $ - $ - $ - $ - $ 972,624 Recurring annual maintenance and operating costs, if applicable Upon completion, maintenance of the creek will be included as part of the ongoing drainage maintenance budget. There is no additional cost.

Page 431 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 177 Capital Improve
ment Plan Summary and Funding Sources

STORM DRAIN IMPROVEMENTS
Department: Public Works
Program: Storm Drain
Project Number: 457202
Initial funding year: FY 2023-24
Planned start date: Summer 2023
Estimated completion date: Ongoing
Project Description
Address deficiencies and replace aging storm drain pipes to minimize future failures, flooding, ground erosion, and damage to roadways caused by storm events. Use video inspections to assess the condition of aging corrugated metal storm drain pipes that are prone to failure throughout the Town and schedule replacements as part of the project. As part of this effort,the, Town’s storm drain system will be entered into the Geographic Information System (GIS) application to support better asset management. Staff will continue to access and identify annual needs for storm drainage improvements.

Project Status
Staff compiled an inventory of the Town’s existing storm drain system based on the 2004 Storm Drainage Master Plan, record drawings, and field visits. The Town also hired a contractor to record CCTV videos at two culverts to assess the pipe conditions: one is a 12-inch corrugated metal pipe (CMP) at Paseo Del Roble Drive, and the other is a 15-inch reinforced concrete pipe (RCP) on Fremont Road near Arastradero Road. This inventory of storm drain assets will help identify critical locations and prioritize improvements.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
March 2025
Available
Budget
Return to
Storm Drain
Fund
Remaining
Budget
Design/Construction $ 450,000 $ 262,158 $ 187,842 $ 110,000 $ 77,842 Total: $ 450,000 $ 262,158 $ 187,842 $ 110,000 $ 77,842 Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Drainage in-lieu $ 77,842 $ - $ - $ - $ - $ 77,842
Total Funding: $ 77,842 $ - $ - $ - $ - $ - $ 77,842
Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Design/Construction $ 77,842 $ - $ - $ - $ - $ 77,842
Total Spending: $ 77,842 $ - $ - $ - $ - $ - $ 77,842
Recurring annual maintenance and operating costs, if applicable Staff continues to maintain Town storm drain facilities throughout the year.

Page 432 of 485 ends

178 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Capital Improve
ment Plan Summary and Funding Sources

VEHICLE AND EQUIPMENT REPLACEMENT (NEW)
Department: Public Works
Program: Vehicle and Equipment
Project Number: NEW
Initial funding year: FY2025/26
Planned start date: Summer 2025
Estimated completion date: Ongoing
Project Description
One of the recommended strategies in the Town’s Climate Action Plan (last updated in October 2021) is the Green Fleet Program to consider and prioritize EVs for the Town fleet when possible to reduce greenhouse gas (GHG) emissions. The other recommended strategy is to transition Town fleet to renewable diesel to further cut emissions. Many of the Town’s maintenance vehicles and equipment may soon require major services and should be considered for replacement, such as the 2003 Dodge Dakota, 2008 Ford Ranger, 2010 John Deere tractor, 2010 John Deere backhoe, and 2009 Cariton Chipper. The Vehicle and Equipment Replacement Policy recommends replacements at 13 to 15 years of service, and many of Town’s vehicles and equipment have been in operations longer.

The Town would also need to comply with the Advanced Clean Fleet Regulation of the California Air Resources Board (CARB), which requires all purchase of vehicles to be zero-emissions vehicles (ZEV’s) starting 2027 and all internal combustion engine vehicles to be retired after 13 year of service.

This projet would be funded by the Vehicle and Equipment Replacement Reserve.

Project Status
In FY2024/25, the City Council approved the replacement of the Town’s F250 truck not to exceed $120,000 and purchase of two small EVs not to exceed $80,000. For FY2025/26, staff recommends the replacement of the 2003 Dodge Dakota with a ZEV. Staff anticipates replacement of at least one truck or equipment each fiscal year for the next five years.

Prior Budget and Actual
Project Summary
Project
Budget
Spending Thru
February 2025
Available
Budget
Return to
General Fund
Remaining
Budget
Vehicle and Equipment $ - $ - $ - $ -
Total: $ - $ - $ - $ - $ -
Project Funding Estimate
Funding Source
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
CIP/ General Fund $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Total Funding: $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Project Spending Estimate
Project Spending
Remaining
Budget
2025-26
Planned
2026-27
Planned
2027-28
Planned
2028-29
Planned
2029-30
Planned
Project
Total
Vehicle and Equipment $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Total Spending: $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 Recurring annual maintenance and operating costs, if applicable There will be routine vehicle and equipment maintenance anticpated. The maintenance costs will be lower with new vehicles/equipment and ZEV’s.

Page 433 of 485 ends

(This Page Intentionally Left Blank)

Page 434 of 485 ends

Town Policies

Page 435 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 181 Town Policies
Financial Policy
Proposed for City Council Adoption on June 26, 2025
Resolution XX-XX
This document establishes policies and practices for the Town of Los Altos Hills that provides financial information and manages its financial resources. As well as establishing and maintaining prudent fund balance levels, financial reporting, and investment policies that are in accordance with State Law. Formally adopted financial policies assist elected officials and staff in saving time and energy in making financial decisions, promoting public confidence, and the development of sound fiscal management practices.

In contrast to larger public agencies, the Town of Los Altos Hills is a small town as measured by geography, population, staff, the absence of commercial businesses, and employees who perform fire, policing, water, and sewer services (which are provided by independent third parties.) It has a volunteer, resident elected, five-member Council who are subject to term limits and operates under a Council – City Manager form of government. Town has many volunteer resident committees appointed by Town Council to limited terms, who advise the Council on financial matters, recreation and hospitality events, land development, technology and environmental issues.

Town staff perform planning and building functions, financial functions, maintenance of pathways, and contract for policing, trash removal, street maintenance, legal services, electronic recordkeeping, and recurring specialty services such as review of resident submitted building plans, town news media, treasury, insurance, and other occasional specialty needs.

While these policies will be updated intermittently, they provide the basic framework for many of the financial decisions that will be addressed by the Town. Support long-term planning and enhance the Town’s effectiveness.

This policy will be reviewed annually during the ACFR process to ensure conformance with the Town’s goals and objectives and compliance with any changes in regulations or standards. In conjunction with the annual policy review, the Administrative Services Director will include updated calculated thresholds, review of use and replenishment of the reserves, and any anticipated changes to be included in the annual ACFR preparations.

Financial Controls
Collection of revenues and disbursement of costs and expenses is performed by Town finance staff. An independent audit is performed annually along with the publication of an annual financial report. in accordance with GASB (Governmental Accounting Standard Board) , that includes a description of the Town’s accounting policies (in footnote 1.) An annual or biennial budget is prepared following a format recommended by the Government Financial Officers Association (GFOA) and prepared by Town Staff for presentation to Town Council after review by the Town’s Finance and Investment Committee. With exception of personnel records, Town records are public and are public information available upon request.

Investments
Most of the Town’s funds are maintained, invested, and managed by independent third parties who report monthly and quarterly to the Town Council who, in turn, delegate some of the review responsibility to Staff and the Town’s Finance and Investment Committee. Investments are made in compliance with the Town’s Investment policy which is reviewed annually by the Town’s Finance and Investment Committee.

Page 436 of 485 ends

182 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Financial records
The collection of receipts is recorded and reviewed by Town staff before being deposited in the Town’s bank accounts. Disbursements are prepared by the responsible Town staff, reviewed by Town finance staff, and signed by two independent check signers who are either senior employees or Council members. Bank reconciliations are prepared monthly. Other records are maintained and independently backed up offsite.

Specialty third party financial service providers
Payroll is independently prepared and processed by a third-party specialty service. Employee benefits are managed by responsible third-party health care providers, pension benefit managers, and related periodic reports are reviewed by Staff, the Town’s Finance and Investment Committee and Town Council. Liability insurance services are provided by a Joint Powers Authority who report annually, and town staff attend periodic meetings in an oversight role. Electronic records are maintained offsite by an independent service. Physical asset inventories are conducted annually by Town staff and reviewed as part of the Town’s annual financial audit. The Town maintains employee fidelity insurance purchased from its Joint Powers Authority provider.

Overall controls
The foregoing briefly describes a web of interrelated services performed periodically on annual, quarterly, and monthly cycles. In addition, reserves are provided for several financial risks subject to review by the Town’s Finance and Investment Committee and Town Council. The Town’s employees develop and maintain job descriptions and procedures the objective of which is to enable smooth transition when employee turnover occurs. Compensation surveys are used to assist management and Council in maintaining competitive compensation. Despite its small size, the Town maintains records, produces financial reports, and utilizes financial controls that are comparable to those performed and maintained by larger governmental agencies.

This policy is reviewed and assessed by the Town’s staff, the Finance & Investment Committee, and elected officials and will also be updated annually, if necessary, to reflect any changes within the requirements.

This document discusses the important elements of financial management at the Town of Los Altos Hills, in an all-in-one format and organized into the following areas of discussion:

General Financial Principles Cash Management
Operating Budget Debt Management
Revenues Capitalization Assets
Expenditures Financial Reporting
Capital Improvement Program
General Financial Principles
It is the overall policy of the Town of Los Altos Hills to:
> Provide financial information in a relevant, thorough, timely fashion, and in a format that effectively communicates financial status to City Council, citizens, and Town employees. > Manage its financial resources in a responsible and planned manner. > Establish and maintain prudent fund balance levels.

Page 437 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 183 Town Policies
> Maintain financial reporting in compliance with current governmental accounting standards. > Promote and implement a relevant and strong system of internal financial controls to manage significant risks and monitor the reliability and integrity of financial and operating reporting. > Promote constructive and proactive financial decision making. > Integrate long-term operating and capital resources planning. > Allow for uncertainties and maintain a posture of financial flexibility. > Develop programs in a manner that supports the City’s long-term ability to cover costs and provide the level and quality of service required by its citizens.
> Managing debt responsibility.
> Establish and maintain investment policies in accordance with State law.

Operating Budget
Budget Adoption
The City Council shall adopt the Town’s annual or biennial budget no later than June 30 of each year. The City Manager is responsible for developing and presenting either an annual or biennial budget, as appropriate.

A balanced provisional operating budget will be submitted to the City Council for review and adoption. Total projected expenditures must not exceed estimated revenues, excluding internal overhead allocations. If necessary, the City Council may approve the planned use of accumulated fund balances from prior years to support specific appropriations within the budget.

No funds may be expended for a new fiscal year until the City Council has formally adopted the budget for that year.

One-time revenue sources shall not be relied upon to fund ongoing operations, ensuring structural financial sustainability.

Budgetary Control and Adjustments
Budgetary control is maintained at the fund level. The City Manager has the authority to approve budget transfers between departments or programs within the same fund, provided that such changes do not increase the fund’s total appropriation. However, the following actions require City Council approval:
> Transfers between funds
> Overall increases in fund appropriations
> Increases in capital project budgets
Transfers between departments should be reported to the City Council as part of periodic budget updates, such as during the mid-year review or at the start of a new budget term.

Department heads are accountable for developing and managing their departmental budgets. Budgetary authority is maintained at the department level. For departments operating across multiple funds, expenditures must remain within the appropriate allocation for each fund.

Encumbrances, Lapsed Appropriations, and Carryforwards
Operating expenditure appropriations that are not spent within the fiscal year shall lapse at year-end, with the following exceptions:

Page 438 of 485 ends

184 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
> Encumbrances or legally binding commitments (e.g., purchase orders) issued during the fiscal year but not completed by year-end
> Capital improvement projects or multi-year grant programs with approved life cycles extending beyond one fiscal year
For contracts that remain incomplete at fiscal year-end, the remaining balance must be reappropriated in the subsequent budget cycle.

Basis of Budgeting and Financial Reporting
Governmental funds are budgeted on a modified accrual basis, while proprietary and fiduciary funds follow the full accrual basis of accounting. The Town’s Annual Comprehensive Financial Report (ACFR) is prepared in accordance with Generally Accepted Accounting Principles (GAAP), and the budget is developed in conformity with these standards.

Appropriations Limit Compliance
The Town’s budget must comply with the annually calculated Appropriations Limit as required under Article XIIIB of the California Constitution. A resolution establishing the Town’s appropriations limit shall be adopted annually by the City Council in accordance with State law.

Revenues
The Town will seek out, apply for, and effectively administer federal, state, and other grants that address the Town’s current operating and capital priorities.

Operating departments are to review existing fees periodically and recommend adjustments to fees, as necessary, to reflect changing direct and indirect costs of providing such services. Independent user-fee studies should be performed and updated periodically (three to five years) to ensure the proper balance of costs and service charges.

The Town should strive to cover the full cost of providing non-tax and discretionary fee-based service operations except to the extent that the City Council approves defined subsidy levels by program area.

Operating departments are to periodically review public services to identify and determine those appropriate for fee collection.

Enterprise operations will be self-supporting and shall reimburse the General Fund for any and all material and services provided on their behalf.

Expenditures
Expenditures are to be budgeted and controlled to not exceed estimated revenues plus the approved and planned use of fund balances accumulated in prior years.

The Town will conduct a mid-year financial status review to determine if projected revenues and expenditures meet budgeted levels. If an operating deficit is projected at year-end, the Town should evaluate the need for immediate corrective and/or mitigating actions, including operating or capital expenditures reduction and /or activate the use of established contingency balances. The deferral of essential and scheduled operational expenditures into the following fiscal year or the use of short-term loans and transfers to balance the budget should be avoided.

Page 439 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 185 Town Policies
Capital Improvement Plan
The Town will develop and maintain a five-year Capital Improvement Plan (CIP) to be updated annually in conjunction with the operating budget. The CIP should reflect the current and changing needs of the community as well as enhance the community’s quality of life.

Cash Management
The Financial and Investment Committee will review the Town’s Investment Policy annually and make recommendations to the City Council when appropriate.

The City Manager may delegate to the Administrative Services Director/Finance Director the responsibility of investing Town funds in accordance with the Town’s Investment Policy. Additionally, the City Manager may authorize the Administrative Services Director/Finance Director to present quarterly investment reports to the City Council, providing a summary of the portfolio’s status and its compliance with the Investment Policy’s requirements.

Debt Management
The Town should plan the use of debt in a manner that sustains financing payments at manageable levels. The Town will seek to maintain a high credit rating through sound financial practices as a basis for minimizing borrowing costs.

The Town will make every effort to use pay-as-you-go financing for capital improvement projects. Debt financing for a project can be used if the overall project’s cost exceeds anticipated available resources and/or if financing terms are favorable. The Town will monitor all forms of debt annually in conjunction with the budget preparation process and report concerns and remedies, if necessary, to the City Council. The Town will diligently monitor its compliance with bond covenants.

The Town will not issue long-term debt to finance current operations. Debt financing should only be used for longterm capital improvement projects with a useful life exceeding the term of the financing and for which the project revenues or specific identified revenue sources are sufficient to service the long-term debt.

The Town may use a lease-purchase method of financing for equipment if the lease rates are more favorable than the Town’s expected overall investment rate of return.

The Town will not incur general obligation indebtedness for public improvements which exceed in aggregate 15% of the assessed value of all real and personal property of the Town as specified in the California Government Code Section 43605.

Capitalization Assets and Leases
The Town’s operations require the purchase and construction of certain assets that are used over a long-term period to provide services to the community. To facilitate the proper recording of these assets, the department has established the following procedure.

Acquisition
The acquisition of capital assets is planned in the Town’s budget on an annual basis. Public projects are budgeted in lump sums based on recommendation from the City Manager. The City Manager oversees the various components of the public project to ensure overall budget compliance. Under direction from the City Manager, the Public Works Director has the authority to make necessary changes from the authorized plans, provided the project will not

Page 440 of 485 ends

186 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
exceed the approved budget. With the exception of public works projects, the acquisition of all other capital assets may be managed by the Administrative Services Director under the direction of the City Manager.

Accounting & Tracking
It is the Finance and Administrative Services Department’s policy to record staff time, supplies, services, and applicable overhead to public projects. Public projects are budgeted in distinct capital project funds and tracked by unique account numbers. All costs required to acquire a public project are recorded to the respective account number.

The Administrative Services Director/Finance Director maintains a register of capital assets that is in conformance with generally accepted accounting principles. The register records the asset’s identification (e.g., name, vehicle identification, etc.), year of acquisition, acquisition cost, useful life.

Depreciation Schedule
Capital assets are categorized into one of several categories, each with estimated useful lives. The Administrative Services Director/Finance Director determines the useful life of each item based on historical practice and input from the appropriate department head where necessary. Assets are classified as “capital assets” on the Town’s financial statements and include any tangible goods with an acquisition cost of $25,000 or more and a useful life greater than three years. Depreciation/amortization will be recorded on a straight-line basis (effective rate of interest method for leases) over the following estimated useful lives:

Infrastructure 20 to 50 years
Structures and improvements 10 to 30 years
Vehicles 5 to 10 years
Equipment 3 to 10 years
Leases term of the leases
Disposal of Capital Assets
At the discretion of the City Manager, obsolete or unused capital assets may be recommended for disposal at any time. The Administrative Services Director/Finance Director is responsible for ensuring that all asset disposals comply with the provisions of the Municipal Code.

Leases
The Town is to record the depreciation of equipment, buildings and facilities, infrastructure, and leases as follows and in line with internally established capitalization guidelines:
> Capitalization Thresholds
• Land purchases at any value
• Equipment - $25,000
• Buildings and facility improvements - $100,000
• Leases - $100,000
The interest rate used for GASB 87 leases is the commercial real estate secured loan rate as of July 1st of the commencement year of the lease if there is not an explicit interest rate in the lease agreement.

Page 441 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 187 Town Policies
Fund Balance
This policy is intended to ensure that the Town has sufficient cash flow to meet current and future needs and provide transparency to its residents by establishing fund reserve targets for each of the Town’s governmental funds. Reserve funds are needed to provide funding for planned and unplanned events. Planned events include, but are not limited to, (1) accumulating balances to fund operating and capital needs; (2) debt service obligations; and (3) funding for employee-related pension and other post-employment benefits. Unplanned events include, but are not limited to, (1) accounting for revenue shortfalls; (2) unanticipated expenses; and (3) paying for unforeseen emergency events.

Adequate fund reserves are of value to: (1) provide working capital to fund operating needs; (2) provide a financial cushion for dealing with unanticipated financial needs and emergencies; and (3) are a component of achieving favorable credit ratings which can help reduce the costs of issuing debt. This policy designates specific reserve accounts. For each reserve, this policy specifies the reserve purpose, the threshold amount, allowable uses of reserves, and replenishment of the reserve. This policy establishes committed and assigned reserves. Committed or Assigned reserves may be established, changed, applied, and deleted by Council resolution. Committed reserves may be used for one or more limited activities noted in the purpose or usage of the reserve. Assigned reserves are not limited to one single activity and may be used for any Town specific activity described in the purpose or usage of the reserve.

Fund Balance Classifications
To set forth the Town’s policy for establishing and maintaining fund reserve targets for each of the Town’s governmental funds. Fiscal reserves provide working capital for operations and maintenance activities, funding for IT, vehicle, and equipment needs, fulfillment of legal, regulatory, and contractual obligations and mitigation of risk and liability exposures.

The Town is required to reclassify fund balances into the following five categories to comply with the Governmental Accounting Standards Board Statement (GASB) No. 54, Fund Balance, and Governmental Fund Types.

Non-Spendable: This is a portion of fund balance not available for appropriations by its nature or external restriction.

Examples are inventories, prepaid expenses and loans to other agencies.

Restricted: The restricted portion of the fund balance is subject to externally enforceable legal restrictions. Examples are Gas Tax revenues and grant proceeds.

Committed: The committed portion of the fund balance is constrained by the limitations imposed through formal City Council action. Only formal City Council action can remove or modify a previously committed amount.

Unassigned: The Unassigned portion of fund balance is that remaining after the non-spendable, the restricted, the committed, and the assigned fund balances are identified and recorded. The general fund is the only fund that reports a positive unassigned fund balance.

Assigned: The assigned portion of the fund balance is established for intended use by either the City Council or its designee, such as the City Manager. No formal City Council action is needed to remove the intended use. GAAP required reserves, such as the Other Post-Employment Benefits (OPEB) reserve, belong to this category.

Order of Utilization
The Town will use GASB’s definitions of fund balance for the annual financial reports (audits) and for all other financial reporting. For all financial planning purposes, the term Budgetary Fund Balance will be used and will include

Page 442 of 485 ends

188 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
any portion of the fund balance that is available for appropriation. Portions of the fund balance not available for appropriations will be identified as follows.

The Town shall strive to use the most restricted fund balances prior to utilizing those that are less restricted. This policy establishes the order of use of unrestricted resources as follows:
> Nonspendable (if funds become spendable)
> Restricted
> Committed
> Assigned
> Unassigned
Finance Reporting
A system of effective internal controls will be maintained that ensures only properly authorized expenditures, recordings of financial transactions, and accounting entries are executed. Along with providing management information and meeting reporting requirements.

Accounting and Finance Responsibilities
Management’s discussion and analysis (MD&A). MD&A should introduce the basic financial statements and provide an analytical overview of the government’s financial activities. Each basic financial statement should include:

1. Government-wide financial statements, consisting of a statement of net assets and a statement of activities.

2. A series of statements that focus on information about the government’s major governmental and enterprise funds, including its blended component units.

Annual Audit
The Town aims to maintain its accounting records, processes, and procedures in a manner that supports the issuance of an unmodified (clean) audit opinion. Responsibility for the accuracy of financial information and the completeness and fairness of its presentation—including all required disclosures—rests with Town management.

Each year, an independent public accounting firm with expertise in municipal finance conducts the Town’s financial audit. The resulting audit opinion is included in the Town’s Annual Comprehensive Financial Report (ACFR), which is organized into three primary sections: introductory, financial, and statistical. The independent auditor’s report appears first within the financial section.

Following the auditor’s report, the Management’s Discussion and Analysis (MD&A) provides a narrative overview of the Town’s financial performance. It includes a comparative analysis of current and prior year results, highlights significant financial trends, and discloses key events or decisions affecting the Town’s fiscal position. The MD&A serves to enhance readers’ understanding of the Town’s financial statements by offering context and analysis.

Accounting During a Disaster
The Finance and Administrative Services Department is responsible for the Town’s participation in disaster assistance funding. Breaking down responsibilities into four main sections, (1) Compensation and Claims Unit, (2) Cost and Purchasing Unit, (3) Time Keeping Unit, and the (4) Recovery Unit. Ensuring that the Finance and Administrative Services Department continues to assist staff, elected officials, and the Town in saving time and energy when making financial decisions, promoting public confidence, and the development emergency management.

Page 443 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 189 Town Policies
In the case of an emergency all reimbursements that are based on disaster related expenses should be recorded by each department. Each department is responsible for keeping thorough, accurate and complete records regarding all expenses that are incurred as a latter result of a declared disaster. Without proper documentation, requests for reimbursement will be denied.

Page 444 of 485 ends

190 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Investment Policy
Adopted by the City Council on February 20, 2025

1.0 Philosophy
It is the policy of the Town of Los Altos Hills to invest public funds in a manner that will provide a reasonable rate of investment return while minimizing exposure to loss of capital and thereby maintaining a consistent source of revenues for the Town. This policy establishes the parameters for the Town’s investment strategies.

2.0 Delegation of Authority
Authority to manage the Town of Los Altos Hills’ investment program is derived from the California Government Code Section 53600 et seq. The City Council shall approve all modifications to the investment strategy and the selection or dismissal of an investment advisor. Administration of the Council-approved investment strategy is hereby delegated to the City Manager, who shall be responsible for supervising all treasury activities of the Town’s Finance Director and who shall establish written procedures for the operation of the investment program consistent with this investment policy. Procedures should include reference to: safekeeping, delivery vs. payment, investment accounting, wire transfer agreements, banking service contracts and collateral/ depository agreements. Such procedures shall include explicit delegations of authority to persons responsible for investment transactions. No person may engage in any investment transactions except as provided under the terms of this policy and the procedures established by the City Manager or her/his designee. The City Manager or her/his designee shall be responsible for all transactions undertaken and shall establish a system of controls to regulate the activities of subordinate officials.

3.0 Scope
This investment policy applies to all financial assets of the Town of Los Altos Hills. These funds are accounted for in the Town of Los Altos Hills’ Annual Comprehensive Financial Report (ACFR) and include:

3.1 Funds
General Fund Enterprise Funds
Special Revenue Funds Capital Projects Funds
Trust and Agency Funds
Any new fund, unless specifically exempted

3.2 The following financial assets are excluded:

Deferred Compensation Plans – Investments are directed by the individual plan participants.

Debt Service Funds Held by Trustees – Investments are placed in accordance with bond indenture provisions.

Notes and Loans – Investments are authorized by separate agreements approved by City Council.

Retiree and Retiree Medical Plans
Except as noted, the Town of Los Altos Hills will consolidate cash balances from all funds to maximize investment earnings. Investment income will be allocated to the various funds based on their respective participation and in accordance with generally accepted accounting principles.

Page 445 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 191 Town Policies

4.0 Prudence
Investments shall be made with judgment and care – under circumstances then prevailing – which persons of prudence, discretion and intelligence exercise in the management of their own affairs, not for speculation, but for investments, considering the probable safety of their capital as well as the probable income to be derived.

4.1 Standard of prudence:

The standard of prudence to be used by investment officials shall be the “prudent investor” standard and shall be applied in the context of managing an overall portfolio. When investing, reinvesting, purchasing, acquiring, exchanging, selling, or managing public funds, a trustee shall act with care, skill, prudence, and diligence under the circumstances then prevailing, including, but not limited to, the general economic conditions and the anticipated needs of the agency, that a prudent person acting in a like capacity and familiarity with those matters would use in the conduct of funds of a like character and with like aims, to safeguard the principal and maintain the liquidity needs of the agency.

5.0 Objective
The primary objectives, in priority order, of the Town of Los Altos Hills’ investment activities shall be:

5.1 Safety:

Safety of principal is the foremost objective of the investment program. Investments of the Town of Los Altos Hills shall be undertaken in a manner that seeks to ensure the preservation of capital in the overall portfolio. The objective is to minimize (1) credit risk, through diversifying the portfolio among the authorized investment types with pre-qualifying financial institutions and broker dealers, and (2) interest rate risk, by structuring portfolio maturities to match cash requirements and investing operating funds in shorter-term securities.

5.2 Liquidity:

The Town of Los Altos Hills’ investment portfolio will remain sufficiently liquid to enable the Town of Los Altos Hills to meet all operating requirements which might be reasonably anticipated. In addition to structuring the portfolio so that securities mature concurrent with cash needs, suitable investments (Section 6.0) consist largely of securities with active secondary or resale markets.

5.3 Return on Investments:

The Town of Los Altos Hills’ investment portfolio shall be designed with the objective of attaining a market rate of return throughout budgetary and economic cycles, commensurate with the Town of Los Altos Hills’ investment risk constraints and the cash flow characteristics of the portfolio.

6.0 Authorized and Suitable Investments
Where this section specifies a percentage limitation for a particular security type, that percentage is applicable only on the date of purchase. Credit criteria listed in this section refers to the credit rating at the time the security is purchased. Where credit requirements in this section refer to a minimum credit rating, this minimum is regardless of any category modifiers such as “+” or “-”. If an investment’s credit rating falls below the minimum rating required at the time of purchase, the City Manager will perform a timely review and decide whether to sell or hold the investment.

The Town of Los Altos Hills is empowered by Government Code Section 53601, 53601.6, 53601.8, 53635, 53635.2, 53638, and 53684 which includes a number of requirements on how and where public money may be invested. Within the context of limitations, the following investments are authorized, as further

Page 446 of 485 ends

192 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
limited herein. A security purchased in accordance with this section shall not have a forward settlement date exceeding 45 days from the time of investment. The Town is empowered by statute to invest in the following type of securities:

1. United States Treasury notes, bonds, bills, or certificates of indebtedness, or those for which the faith and credit of the United States are pledged for the payment of principal and interest.

2. Federal agency or United States government-sponsored enterprise obligations, participations, or other instruments, including those issued by or fully guaranteed as to principal and interest by federal agencies or United States government-sponsored enterprises.

3. Obligations of the State of California or any local agency within the state, including bonds payable solely out of revenues from a revenue-producing property owned, controlled or operated by the state or any local agency or by a department, Commission, agency or authority of the state or any local agency; provided that the obligations are rated in one of the three highest categories by a nationally recognized statistical rating organization (NRSRO). Purchases of municipal obligations in sections 3 and 4 combined may not exceed 30 percent of the Town’s investment portfolio.

4. Registered treasury notes or bonds of any of the other 49 states in addition to California, including bonds payable solely out of the revenues from a revenue-producing property owned, controlled, or operated by a state, or by a department, board, agency, or authority of any of these states; provided that the obligations are rated in one of the three highest categories by a NRSRO. Purchases of municipal obligations in sections 3 and 4 combined may not exceed 30 percent of the Town’s investment portfolio.

5. Bankers’ Acceptances with a rating of the highest ranking or highest letter and number rating as provided for by a NRSRO. Purchases of bankers’ acceptances may not exceed 180 days. No more than 40% of the Town’s investment portfolio may be invested in bankers’ acceptances and no more than 30% of the Town’s investment portfolio may be invested in the bankers’ acceptances of any one commercial bank.

6. Commercial paper of “prime” quality of the highest ranking or of the highest letter and number rating as provided for by a NRSRO. The entity that issues the commercial paper shall meet all of the following conditions in either paragraph (1) or (2):
(1) The entity meets the following criteria:
(A) Is organized and operating in the United States as a general corporation. (B) Has total assets in excess of five hundred million dollars ($500,000,000). (C) Has debt other than commercial paper, if any, that is rated in a rating category of “A” or its equivalent or higher by a NRSRO.
(2) The entity meets the following criteria:
(A) Is organized within the United States as a special purpose corporation, trust, or limited liability company.
(B) Has program-wide credit enhancements including, but not limited to, overcollateralization, letters of credit, or a surety bond.
(C) Has commercial paper that is rated “A-1” or higher, or the equivalent, by an NRSRO. Eligible commercial paper shall have a maximum maturity of 270 days or less. Local agencies, other than counties or a city and county, may invest no more than 25% of their moneys in eligible commercial paper.

Eligible commercial paper associated with less than $100,000,000 of investments shall have a maximum maturity of 270 days or less. Local agencies, other than counties or a city and

Page 447 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 193 Town Policies
county, may invest no more than 25% of their moneys and no more than 5% per issuer in eligible commercial paper. Eligible commercial paper associated with more than or equal to $100,000,000 of investments and Pooled Funds shall have a maximum maturity of 270 days or less. Local Agencies other than counties or a city and county, may invest no more than 40% of their moneys and no more than 5% per issuer in eligible commercial paper.

7. FDIC insured or fully collateralized time certificates of deposit in financial institutions located in California, including U.S. branches of foreign banks licensed to do business in California. All time deposits must be collateralized in accordance with California Government Code section 53651. Purchase of FDIC insured or fully collateralized time certificates of deposit may not exceed 50% of the Town’s investment portfolio.

8. Negotiable Certificates of Deposit (CD) issued by a nationally or state-chartered bank, a savings association or a federal association (as defined by Section 5102 of the Financial Code), a state or federal credit union, or by a federally- or statelicensed branch of a foreign bank. No more than 30% of the Town’s portfolio may be invested in negotiable CDs and eligible CDs must be rated in one of the three highest categories by a NRSRO.

9. Local Agency Investment Fund (LAIF). Investments in LAIF shall not exceed $75 million.

10. Insured savings account or bank money market account. In accordance with California Government Code Section 53635.2 to be eligible to receive local agency deposits a financial institution must have received a minimum overall “satisfactory” rating for meeting the credit needs of California communities in its most recent evaluation.

11. Shares of beneficial interest issued by diversified management companies that are money market funds registered with the Securities and Exchange Commission under the Investment Company Act of 1940 (15 U.S.C. Sec. 80a1, et seq.). To be eligible for investment pursuant to this subdivision these companies shall either: (1) attain the highest ranking letter or numerical rating provided by not less than two of the three largest nationally recognized rating services or (2) have an investment advisor registered or exempt from registration with the Securities and Exchange Commission with not less than five years’ experience managing money market mutual funds and with assets under management in excess of $500,000,000. The purchase price of shares shall not exceed 20% of the investment portfolio and 10% per money market fund.

12. California Asset Management Program. (CAMP), as long as the portfolio is rated among the top two rating categories by a NRSRO. There is no limit on the percentage of CAMP that may be held in the Town’s portfolio.

13. Medium-term notes, defined as all corporate and depository institution debt securities with a maximum remaining maturity of five years or less, issued by corporations organized and operating within the United States or by depository institutions licensed by the United States or any state and operating within the United States. Notes eligible for investment under this subdivision shall be rated in a rating category of “A” or its equivalent or better by a NRSRO. Purchases of medium-term notes shall not include other instruments authorized by this section and may not exceed 30% of the agency’s money and 5% per issuer that may be invested pursuant to this section.

14. United States dollar denominated senior unsecured unsubordinated obligations issued or unconditionally guaranteed by the International Bank for Reconstruction and Development, International Finance Corporation, or Inter American Development Bank, with a maximum remaining maturity of five years or less, and eligible for purchase and sale within the United States. Investments under this subdivision shall be rated in a rating category of “AA” or its equivalent or better by a NRSRO and shall not exceed 30% of the agency’s moneys that may be invested pursuant to this section. (Supranationals).

Page 448 of 485 ends

194 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies

15. Mortgage Pass-Through and Asset-Backed Securities including equipment lease-backed certificates, consumer receivable passthrough certificates, or consumer receivable-backed bonds of a maximum remaining maturity of five year. Securities eligible for investment under this subdivision shall be rated in a rating category of “AA,” its equivalent or better by at least one NRSRO. Purchase of securities authorized by this subdivision may not exceed 20 percent of the Town’s total portfolio.

Page 449 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 195 Town Policies
Summary Table of Permitted Investments
Investment Instruments
Calif. Code Limitation (Maturity, % of
Portfolio, Rating)
Town Policy Limitation (Maturity, % of
Portfolio, Rating)
U.S. Treasury 5 years
100% of portfolio
5 years
100% of portfolio
Federal Agency
(including mortgagebacked securities and
callable securities)
5 years
100% of portfolio
5 years
100% of portfolio
Municipal Obligations
(including notes issued by the State of
California, California local agencies, and the
other 49 states)
5 years
100% of portfolio
5 years
30% of portfolio Credit rating category of
“A” or its equivalent or higher by a NRSRO
Bankers’ Acceptances 180 days 40% of portfolio 40% per issuer 180 days 40% of portfolio 30% per issuer Commercial Paper (under $100,000,000 of
investments)
270 days
25% of portfolio
10% per issuer
Long term credit rating category of “A” and
short term rating of “A-1” or its equivalent
or higher by a NRSRO
270 days
25% of portfolio
5% per issuer
Long term credit rating category of “A” and
short term rating of “A-1” or its equivalent
or higher by a NRSRO
Commercial Paper (min. $100,000,000 of
investments) and Pooled Funds
270 days
40% of portfolio
10% per issuer
Long term credit rating category of “A” and
short term rating of “A-1” or its equivalent
or higher by a NRSRO
270 days
40% of portfolio
5% per issuer
Long term credit rating category of “A” and
short term rating of “A-1” or its equivalent
or higher by a NRSRO
Deposits
(Collateralized/FDIC) 100%1
of portfolio 5 years
50% of portfolio
Negotiable CDs 5 years
30% of portfolio
5 years
30% of portfolio
5% per issuer
Credit rating category of “A” or its
equivalent or higher by a NRSRO
LAIF $75 million $75 million
Money Market Funds 20% of portfolio
10% per fund
20% of portfolio
10% per fund
JPA
(CAMP) 100% of portfolio 100% of portfolio
Medium-Term Notes
5 years
30% of portfolio
10% per issuer
Credit rating category of “A” or its
equivalent or higher by a NRSRO
5 years
30% of portfolio
5% per issuer
Credit rating category of “A” or its
equivalent or higher by a NRSRO
Supranationals
5 years
30% of portfolio
Credit rating category of “AA” or its
equivalent or higher by a NRSRO
5 years
30% of portfolio
Credit rating category of “AA” or its
equivalent or higher by a NRSRO
Mortgage Pass-through and Asset-Backed
Securities
5 years or less
20% of portfolio
Credit rating category of “AA” or its
equivalent or higher by a NRSRO
5 years or less
20% of portfolio
Credit rating category of “AA” or its
equivalent or higher by a NRSRO
1For deposit placement services.

Page 450 of 485 ends

196 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies

7.0 Authorized Financial Dealers and Institutions
To provide for the optimum yield in the Town’s portfolio, the Town’s procedures shall be designed to encourage competitive bidding on transactions from an approved list of broker/dealers. The Town may engage the services of an external investment advisor to assist in the management of the Town’s investment portfolio in a manner consistent with this investment policy. If the Town hires an investment adviser to provide investment management services, the adviser is authorized to transact with its direct dealer relationships on behalf of the Town. Approved investment adviser firms must provide their services to the Town on a fiduciary capacity and be registered with the Securities and Exchange Commission (SEC) under the Investment Advisor’s Act of 1940. The advisor shall have more than five years’ experience in managing public funds and shall have at minimum $1 billion under management. The City Manager, or the Town’s investment advisor, shall maintain a list of authorized broker/dealers and financial institutions that are approved for investment purposes. This list will be developed after a comprehensive credit and capitalization analysis indicates the firm is adequately financed to conduct business with public entities. It shall be the policy of the Town to purchase securities only from those authorized institutions or firms.

8.0 Safekeeping and Custody
To protect against potential fraud and embezzlement, or losses caused by a collapse of an individual securities dealer all security transactions entered into by the Town of Los Altos Hills shall be conducted on a deliveryversus-payment (DVP) basis. Securities will be held by a third-party custodian, in the Town of Los Altos Hills’ name and control, designated by the City Manager or her/his designee and evidenced by safekeeping receipts.

9.0 Collateralization
Collateralization will be required on certificates of deposit as specified under Government Code Section 63630 et seq in order to anticipate market changes and provide a level of security for all funds. All time deposits must be collateralized in accordance with California Government Code section 53651.

The Town of Los Altos Hills chooses to limit collateral to the following:

Collateral will always be held by an independent third party. A clearly marked evidence of ownership (safekeeping receipt) must be supplied to the Town of Los Altos Hills and retained.

The right of collateral substitution is granted.

10.0 Internal Control
The Town of Los Altos Hills is responsible for establishing and maintaining an internal control structure designed to ensure that the assets of the Town are protected from loss, theft or misuses. The internal control structure shall be designed to provide reasonable assurance that these objectives are met. The concept of reasonable assurance recognizes that (1) the cost of a control should not exceed the benefits likely to be derived and (2) the valuation of costs and benefits requires estimates and judgments by the City Manager and staff.

The City Manager or designee shall arrange for an annual audit by an external CPA firm in compliance with the requirements of state law and generally accepted accounting principles as pronounced by the Government Accounting Standards Board (GASB). As a part of the audit, investment transactions will be tested. The annual audit will be an integral part, but not the sole part of management’s program of monitoring internal controls.

Page 451 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 197 Town Policies
The internal controls shall address the following points:
• Control of collusion
• Separation of transaction authority from accounting and recordkeeping • Custodial safekeeping
• Avoidance of physical delivery securities
• Clear delegation of authority to subordinate staff members • Written confirmation of transactions for investments and wire transfers • Development of a wire transfer agreement with the lead bank and third-party custodian

11.0 Ethics and Conflicts of Interest
Officers and employees involved in the investment process shall refrain from personal business activity that could conflict with proper execution of the investment program, or which could impair their ability to make impartial investment decisions. These officers and employees involved in the investment process shall disclose to the City Manager any material financial interest in financial institutions that conduct business with this jurisdiction, and they shall further disclose any large personal financial/investment positions that could be related to the performance of the Town of Los Altos Hills, particularly with regard to the time of purchases and sales. Employees and investment officials shall refrain from undertaking personal investment transactions with the same individual with whom business is conducted on behalf of the Town of Los Altos Hills.

12.0 Diversification
The Town of Los Altos Hills will diversify its investments by security type and institution. Limits are provided for in Section 6.0. With the exception of U.S. Treasury and Federal Agency securities, municipal bonds, supranational bonds, and authorized pools such as CAMP or LAIF, no more than 5% of the Town of Los Altos Hills’ total investment portfolio will be invested in a single issuer.

13.0 Maximum Maturities
To the extent possible, the Town of Los Altos Hills will attempt to match its investments with anticipated cash flow requirements. The Town of Los Altos Hills will not directly invest in securities maturing more than five (5) years from the settlement date unless City Council has provided approval for a specific purpose at least three (3) months before the investment is made. The calculation of an investment’s remaining maturity/term is to be measured from the settlement date to final maturity.

Debt reserve funds may be invested in securities exceeding five (5) years if the maturities of such investments are made to coincide as nearly as practicable with the expected use of the funds.

The Town of Los Altos Hills will retain operating reserves as adopted by the City Council. The amount of active deposits and inactive investments with a maturity of one year or less shall always be equal to greater than any draw on these reserves required by the annual operating budget.

Securities may be sold prior to maturity to accommodate the Town’s cash flow requirements, to reposition the portfolio to perform well in the current market, or to take advantage of market opportunities to increase the Town’s rate of return.

Page 452 of 485 ends

198 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies

14.0 Performance Standards
The investment portfolio shall be designed with the objective of obtaining a market rate of return throughout budgetary and economic cycles, commensurate with the Town’s investment risk constraints and cash flow needs.

14.1 Market Yield (Benchmark):

Suitability should be the standard for evaluating the success of the Town’s investment portfolio. Given this strategy and the active investment management utilized by the Town, the basis used to determine whether market yields are adequate shall be the ICE BofAML 1-5 year U.S. Treasury Index. 15.0 Reporting The City Manager is charged with the responsibility of including a market report on investment activity and returns in the Town of Los Altos Hills’ Cash and Investment Report. The Report will be in compliance with California Government Code Section 53646. 16.0 Investment Policy Adoption The Town of Los Altos Hills’ investment policy shall be adopted by the City Council. The policy shall be reviewed annually by the Finance and Investment Committee and any modifications made thereto must be approved by the City Council.

15.0 Reporting
The City Manager is charged with the responsibility of including a market report on investment activity and returns in the Town of Los Altos Hills’ Cash and Investment Report. The Report will be in compliance with California Government Code Section 53607 and will include:
• The monthly report shall include an accounting of all receipts, disbursements, and fund balances. • The quarterly reports shall include the book and market value of the cash investment, the classification of the investment, the name of the institution or entity, the rate of interest, and the maturity dates for all securities.
• The quarterly report will include a statement of compliance of the portfolio with the investment policy or an explanation as to why the portfolio is not in compliance per Government Code 53646(b) (2).
• The quarterly report will include a statement on availability of funds to meet its obligations within the next six months per Government Code 53646(b)(3).

As a good reporting practice, the Report will be submitted on a quarterly basis and provided to the Council within 45 days following the end of the month.

16.0 Investment Policy Adoption
The Town of Los Altos Hill’s’ investment policy shall be adopted by the City Council. The policy shall be reviewed annually by the Finance and Investment Committee and any modifications made thereto must be approved by the City Council.

Page 453 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 199 Town Policies
Glossary of Terms - Financial Policy
Bankers’ Acceptances
Short-term credit arrangements that enable businesses to obtain funds to finance commercial transactions. They are time drafts drawn on a bank by an exporter or importer to obtain funds to pay for specific merchandise. By its acceptance, the bank becomes primarily liable for the payment of the draft at maturity. An acceptance is a highgrade negotiable instrument.

Benchmark
A comparative base for measuring the performance or risk tolerance of the investment portfolio. A benchmark should represent a close correlation to the level of risk the average duration of the portfolio’s investments.

Broker
Someone who brings buyers and sellers together and is compensated for her/his service.

California Asset Management Program (CAMP)
CAMP is a joint powers authority which provides investment services to local governments through its investment pool. The pool is AAAm-rated by Standard and Poor’s, and provides same-day availability to funds up to 11:00AM Pacific. The pool strives to maintain stable asset value.

Certificates of Deposit

1. Negotiable Certificates of Deposit are large-denomination CDs. They are issued at face value and typically pay interest at maturity, if maturing in less than 12 months. CDs that mature beyond this range pay interest semi-annually. Negotiable CDs are issued by U.S. banks (domestic CDs), U.S. branches of foreign banks (Yankee CDs), and thrifts. There is an active secondary market for negotiable domestic and Yankee CDs. However, the negotiable thrift CD secondary market is limited. Yields on CDs exceed those on U.S. treasuries and agencies of similar maturities. This higher yield compensates the investor for accepting the risk of reduced liquidity and the risk that the issuing bank might fail. State law does not require the collateralization of negotiable CDs.

2. Non-negotiable Certificates of Deposit are time deposits with financial institutions that earn interest at a specified rate for a specified term. Liquidation of the CD prior to maturity incurs a penalty. There is no secondary market for these instruments; therefore, they are not liquid. They are classified as public deposits, and financial institutions are required to collateralize them. Collateral may be waived for the portion of the deposits that are covered by FDIC insurance.

Collateral
Securities, evidence of deposit or other property, which a borrower pledges to secure repayment of a loan. Also refers to securities pledged by a bank to secure deposits of public monies.

Collateralization
Process by which a borrower pledges securities, property or other deposits for the purpose of securing the repayment of a loan and/or security. Also refers to securities pledged by a bank to secure deposits of public moneys.

Dealer
Someone who acts as a principal in all transactions, including buying and selling from her/his own account.

Page 454 of 485 ends

200 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Delivery v. payment
The preferred method of delivering securities, with an exchange of money for the securities.

Demand deposits
A deposit of monies which are payable by the bank upon demand of the depositor.

Derivative
Securities that are based on, or derived from, some underlying asset, reference date, or index.

Diversification
Dividing investment funds among a variety of securities offering independent returns.

Federal Depository Insurance Corporation (FDIC)
A federal agency that insures bank deposits, currently up to $250,000 per deposit.

Federal Home Loan Bank (FHLB)
A federal agency that provides credit and liquidity in the housing market. FHLB issues discount notes and semiannual pay coupon securities.

Federal Home Loan Mortgage Corporation (FHLMC)
A federal agency that provides credit and liquidity in the housing market. FHLMC, also called “Freddie Mac,” issues discount notes, semi-annual pay coupon securities and mortgage-backed securities.

Federal National Mortgage Association (FNMA)
A federal agency that provides credit and liquidity in the housing market. FHLMC, also called “Fannie Mae,” issues discount notes, semi-annual pay coupon securities and mortgage-backed securities Liquidity
An asset that can easily and rapidly be converted into cash without significant loss of value.

Local Agency Investment Fund (LAIF)
The LAIF was established by the State of California to enable treasurers to place funds in a pool for investments.

There is a limitation of $50 million per agency subject to a maximum of fifteen total transactions per month. The Town uses this fund when market interest rates are declining as well as for short-term investments and liquidity.

Town funds in LAIF are limited to $40 million.

Maturity
The date upon which the principal or stated value of an investment becomes due and payable.

Mortgage-Backed Security
Debt obligations that represent claims to the cash flows from pools of mortgage loans, most commonly on residential property.

Page 455 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 201 Town Policies
Portfolio
Combined holding of more than one stock, bond, commodity, cash equivalent or other asset. The purpose of a portfolio is to reduce risk through diversification.

Repurchase Agreement
A form of collateralized loan involving the sale of a security with a simultaneous agreement by the seller to buy the same security back from the purchaser at an agreed-on price and future date. The party who sells the security at the inception of the repurchase agreement and buys it back at maturity is borrowing money from the other party, and the security sold and subsequently repurchased represents the collateral.

Safekeeping
Offers storage and protection of assets provided by an institution serving as an agent.

Supranational Bonds
A bond issued by a supranational agency such as the World Bank.

U.S. Treasury Bills
Commonly referred to as T-Bills, these are short-term marketable securities sold as obligations of the U.S.

Government. They are offered in three-month, six-month and one year maturities. T-Bills do not accrue interest but are sold at a discount to pay face value at maturity.

U.S. Treasury Notes
These are marketable, medium-term interest-bearing securities sold as obligations of the U.S. Government with original maturities of one to ten years. Interest is paid semiannually.

U.S. Government Agency
Issues Issues which are unconditionally backed by the full faith and credit of the United States.

Yield
The rate of annual income return on an investment, expressed as a percentage. Income yield is obtained by dividing the current dollar income by the current market price for the security. Net yield or yield to maturity is the current income yield minus any premium above par or plus any discount from par in purchase price, with the adjustment spread over the period from the date of purchase to the date of maturity of the bond.

Page 456 of 485 ends

202 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Reserve Policy
Proposed for City Council Adoption on June 26, 2025
Resolution XX-XX
Purpose
This policy establishes reserve targets for the Town’s governmental funds to ensure financial stability, operational continuity, and long-term planning. Reserves provide:
> Working capital for operations and maintenance
> Funding for equipment, technology, and capital needs
> Resources to meet legal, regulatory, and contractual obligations > A buffer against revenue shortfalls and unforeseen emergencies Maintaining adequate reserves enhances transparency, supports credit ratings, and helps manage risk through economic or operational disruptions.

Policy
This policy ensures that the Town maintains sufficient cash flow to meet current and future obligations while providing transparency to the public. By establishing targeted reserve levels for each of the Town’s governmental funds, the policy supports financial stability, risk mitigation, and long-term planning.

Reserves are essential to address both planned and unplanned needs:
> Planned needs may include:
• Funding operating requirements
• Meeting debt service obligations (if any)
• Addressing pension and other post-employment benefit (OPEB) liabilities > Unplanned needs may include:
• Offsetting revenue shortfalls
• Covering unanticipated expenses
• Responding to emergencies or disasters
Establishing formal reserve targets helps the Town:
> Maintain adequate working capital
> Prepare for financial contingencies and emergencies
> Support strong credit ratings and reduce borrowing costs This policy defines specific reserve accounts by outlining their purpose, target thresholds, allowable uses, and replenishment procedures. It distinguishes between committed reserves, which are formally designated by City Council for specific purposes, and assigned reserves, which offer greater flexibility and may be used for a range of Town-identified needs. Both committed and assigned reserves may be established, modified, applied, or eliminated by City Council resolution. Committed reserves are restricted to the purposes explicitly stated at the time of designation. In contrast, assigned reserves may support multiple related activities, provided they align with the stated intent of the reserve.

Page 457 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 203 Town Policies
Policy Review and Monitoring
This policy will be reviewed annually during the budget process to ensure alignment with the Town’s financial goals and compliance with applicable regulations. As part of the annual review, the Administrative Services Director/ Finance Director will:
> Recalculate reserve thresholds based on the most recent financial data > Evaluate reserve usage and replenishment
> Recommend any policy or funding adjustments for inclusion in the budget In addition to the annual review, reserve balances will be monitored mid-year and presented to the City Council as part of the mid-year financial update to promote transparency and timely decision-making.

Committed Reserves

1. Pension Contribution Reserve
Purpose of the Reserve:

The Pension Contribution Reserve is to set aside funds for the Town’s estimated unfunded liability. CalPERS prepares an annual Actuarial Report for each of the Town’s three pension plans. This reserve is for amounts not included in the Accrued Liability and represents the difference between the currently applied Discount Rate and the lowest Discount Rate measured by CalPERS in its most recent actuarial report. This difference is updated to the most recent past fiscal year end as reported in the related ACFR Pension Footnote.

Threshold of the Reserve:

The Pension Contribution Reserve shall maintain a maximum threshold based on the CalPERS annual actuarial report for each of the Town’s three pension plans. The reserve threshold amount is calculated by the following:
the difference between the accrued liability at the current discount rate and the accrued liability calculated using the discount rate that is one percentage point lower than the current rate, as shown in the most recent ACFR pension footnote.

The balance of the Town’s Section 115 Pension Trust shall be included in the calculation of the Pension Contribution Reserve. The sum of the Pension Contribution Reserve and the Pension Trust balance shall be used to evaluate compliance with the policy threshold.

Usage of the Reserve:

Adjustments to the reserve will result from the discount rate changes in succeeding years per the CalPERS annual report per the Analysis of Discount Rate Sensitivity as updated in the most recent ACFR Pension footnote.

Replenishment of the Reserve:

During the annual budget cycle, the Pension Contribution Reserve will be adjusted to reflect the new threshold amount as described in the preceding Threshold of the Reserve section. These adjustments will be approved by the City Council as part of the annual budget cycle.

2. Technology Reserve

Page 458 of 485 ends

204 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Purpose of the Reserve:

The Technology Reserve is to set aside funds for the Town’s future Audio and Visual equipment and software replacement needs.

Threshold of the Reserve:

The threshold will be calculated based on $460K, the budgeted amount of the AV system, and will be $46K for the following 10 years for upgrades and replacement of the equipment.

Usage of the Reserve:

Eligible expenditures will be for AV System and software to be upgraded or replaced throughout the fiscal year. These expenditures will be determined on an annual basis.

Replenishment of the Reserve:

The Technology Reserve will be adjusted up or down, as necessary, to equal the threshold. These expenditures will be determined on an annual basis.

3. Vehicle and Equipment Replacement Reserves
Purpose of the Reserve:

The Vehicle and Equipment Replacement Reserve is to set aside funds for the Town’s current and future vehicle and equipment replacement needs. The Town maintains a vehicle and equipment replacement schedule for all Town vehicles and equipment. This schedule is updated as equipment is added or removed from service.

Threshold of the Reserve:

The threshold of the Vehicle and Equipment Replacement Reserve will be calculated each year during the annual budget cycle. This threshold will be the sum of the amount determined for each piece of equipment on the Vehicle and Equipment replacement schedule based on future replacement costs of the item divided by its useful life and multiplied by the number of years in service, but in no event greater than the future replacement cost.

Usage of the Reserve:

Eligible expenditures include vehicles and/or equipment replacements purchased throughout the fiscal year.

These expenditures will be determined on an annual basis.

Replenishment of the Reserve:

During the annual budget cycle, the Vehicle and Equipment Replacement Reserve will be adjusted up or down, as necessary, to equal the threshold. Any adjustments will be approved by the City Council as part of the annual budget cycle.

4. Facilities Replacement Reserves
Purpose of the Reserve:

The Facilities Replacement Reserve is to set aside funds for the Town’s current and future facility improvement and replacement needs. The Town maintains a facility schedule for all Town facilities. Additions to the facilities schedule occur when Town facilities are either improved or new Town facilities are added. Deletions occur as Town facilities are demolished and removed from service.

Page 459 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 205 Town Policies
Threshold of the Reserve:

The threshold of the Facilities Replacement Reserve will be calculated each year during the annual budget cycle.

This threshold will be comprised of two parts. For existing buildings, it will be the cumulative depreciation of the buildings listed in the fixed asset schedule as reported in the most recent ACFR Capital Asset Footnote.

Added to this amount is any remaining unspent funds appropriated to construct additions or improvements to facilities.

Usage of the Reserve:

Eligible expenditures include facilities improvements, renovations, or demolitions that occur throughout the fiscal year. These expenditures will be determined on an annual basis.

Replenishment of the Reserve:

During the annual budget cycle, the Facilities Replacement Reserve will be adjusted up or down, as necessary, to equal the threshold. Any adjustments will be approved by the City Council as part of the annual budget cycle.

5. Disaster Contingency Reserve:

The Disaster Contingency Reserve is to set aside funds for emergencies that may arise within the Town that have not been federally and or state declared disasters. To constitute a Town emergency, the disaster or emergency would be natural disasters (i.e. earthquakes, landslides, flooding) or temporary service outages of Town facilities and infrastructure (i.e. extensive debris cleanup from wind events that prohibits travel on Town roads). To be declared a Town Emergency, the Emergency Operations Center and team would be activated for any length of time. Town emergencies are smaller in nature than presidentially declared federal disasters and governor declared state disasters and are typically contained within the Town boundaries.

Threshold of the Reserve:

The Disaster Contingency Reserve shall maintain a balance not less than $1,250,000. This amount shall be adjusted up or down, as necessary, each year. Adjustments will be based on the risk assessment performed by the Town’s emergency services personnel.

Usage of the Reserve:

The City Manager is the Director of Emergency Services. In the event of a Town emergency, the City Manager would determine eligible expenditures allowable for use of the reserve on a case-by-case basis. If expenditures are incurred, use of the reserve will be considered on an annual basis.

Replenishment of the Reserve:

During the annual budget cycle, the Disaster Contingency Reserve will be adjusted as necessary to equal the threshold. Any adjustments will be approved by the City Council as part of the annual budget cycle.

6. Capital Projects Reserve
Purpose of the Reserve:

The Capital Projects Reserve is to set aside funds to start or complete projects for which the Council has previously appropriated funds, but the projects have not been started or completed.

Page 460 of 485 ends

206 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Town Policies
Threshold of the Reserve:

The Capital Projects Reserve shall maintain a balance equal to the unused prior appropriated funds as shown in the list of capital projects prepared as part of the annual budget process. This amount shall be adjusted up or down, as necessary, each year.

Usage of the Reserve:

The Capital Projects Reserve will be used to fund the completion of the prior appropriated projects as shown in the list of capital projects in the budget.

Replenishment of the Reserve:

During the annual budget cycle, the Capital Projects Reserve will be adjusted as necessary to equal the threshold. Any adjustments will be approved by the City Council as part of the annual budget cycle.

Assigned Reserves

1. General Fund Stabilization Reserve
Purpose of the Reserve:

The General Fund Stabilization Reserve is to establish a minimum unassigned fund balance and to set aside funds for the Town’s current and future operational needs in the event of economic downtowns or unexpected expenditures.

Threshold of the Reserve:

The General Fund Stabilization Reserve shall maintain a maximum threshold that is equivalent to three months of average operating expenditures in the general fund. Operating expenditures are defined as those expenditures before transfers to other funds and exclude capital expenditures (less that portion of Community Development costs that are recovered through charges for services). The figures from the most recent ACFR shall be used for calculating the threshold amount.

Usage of the Reserve:

Allowable expenditures for use in this reserve shall be determined on a case-by-case basis. Examples of allowable expenditures include, but are not limited to, significant economic downturn that result in diminished property taxes revenues, thus resulting in a need for use of the reserve to balance the annual general fund budget. These expenditures will be recommended by the City Manager and approved by the City Council.

If expenditures are recommended and approved, use of this reserve will be considered on an annual basis.

Replenishment of the Reserve:

During the annual budget cycle, the General Fund Stabilization Reserve will be reviewed and updated based on the most recent audited and issued Annual Comprehensive Financial Report. Any adjustments will be approved by the City Council as part of the annual budget cycle.

Page 461 of 485 ends

(This Page Intentionally Left Blank)

Page 462 of 485 ends

Appendix

Page 463 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 209 Appendix
Glossary of Terms in Budget
Accounting System: The methods and records
established to identify, assemble, analyze, classify,
record and report a government’s transactions and
to maintain accountability for the related assets and
liabilities.

ACFR: abbreviation. Annual Comprehensive Financial
Report. This is the Town’s financial statement,
which includes auditor’s opinion and other financial
information pertinent in evaluating the Town’s financial health.

Adopted Budget: The official budget as approved by
the City Council at the start of each fiscal year.

Agency Fund: A fund normally used to account for
assets held by a government as an agent for individuals, private organizations or other governments and/or
other funds.

Amended Budget: The official budget as adopted and
as amended by the City Council through the course of
a fiscal year.

Annual Budget: A budget applicable to a single fiscal
year.

Annual Financial Report: A financial report applicable
to a single fiscal year.

Appropriated Budget: The expenditure authority
created by the appropriation bills or ordinances, which are signed into law, and the related estimated revenues.

The appropriated budget would include all reserves,
transfers, allocations, supplemental appropriations
and other legally authorized legislative and executive
changes.

Appropriation: A legal authorization granted by a
legislative body for a given period to make expenditures and to incur obligations for specific purposes. An
appropriation usually is limited in amount and time it
may be expended.

ASD: abbreviation. Administrative Services Department
Assessed Valuation: The estimated value placed upon
real and personal property by the County Assessor as
the basis for levying property taxes.

Audit: Prepared by an independent Certified Public
Accountant , the primary objective of an audit is to
determine if the City’s financial statements present
fairly the City’s financial position and results of
operations in conformity with generally accepted
accounting principles.

Authority: A government or public agency created to
perform a single function or restricted group of related activities.

Balanced Budget: A balanced budget exists when total
revenues are equal to, or greater than, total expenses.

Bond Covenant: A legally enforceable promise made
by an issuer of bonds to the bondholders, normally
contained in the bond resolution or indenture.

Budget: A plan of financial operation embodying an
estimate of the proposed expenditures for a given
period and the proposed means of financing them.

Capital Budget: A plan or proposed capital outlays and
the means of financing them.

Capital Improvement Program: A plan for capital
improvements to be implemented each year over a
fixed period of years to meet capital needs arising from the assessment of long‐term needs. It sets forth each
project in which the government is to have a part and
specifies the full resources estimated to be available
to finance the projected expenditures.

Capitalized Expenditures: Expenditures resulting in the acquisition and/or construction of fixed assets.

Contracted Services: Services rendered in support of
City operations and activities by external parties. These may be based upon either formal contracts or ad hoc
charges.

Contingency: A budgetary reserve set‐aside for
emergencies or unforeseen expenditures not otherwise
budgeted.

Cost Accounting: The method of accounting that
provides for assembling and recording of all the
elements of cost incurred to accomplish a purpose, to

Page 464 of 485 ends

210 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Appendix
carry on an activity or operation, or to complete a unit of work or a specific job.

Cost Allocation Plan: A comprehensive analysis of
the appropriate distribution of overhead costs from
the Town’s General Government Departments to
the various service departments – Public Works,
Community Development and Parks & Recreation.

Cost of Services: Payments made by customers
for publicly provided services that benefit specific
individuals and exhibit “public good” characteristics.

They include such fees as recreational fees, building
permit fees, etc.

Debt Service Fund: A fund established for the payment
of interest and principal on all debt other than payable exclusively from special assessments.

Department: A major organizational group of the City
with overall management responsibility for an operation or a group of related operations within a functional area.

Depreciation: (1) Expiration in the service life of capital assets attributable to wear and tear, deterioration,
action of the physical elements, inadequacy or
obsolescence. (2) That portion of the cost of a capital asset which is charged as an expense during a particular period.

Division: An organizational subgroup of a department.

Employee Services: Salaries plus fringe benefits earned by employees of the organization for work performed.

Encumbrance: The commitment of appropriated funds
to purchase goods that have not yet been received, or
services that have yet to be rendered.

Enterprise Fund: A fund established to account for
operations financed and operated in a manner similar to private business enterprises. In this case, the governing body intends that costs of providing goods or services
to the general public on a continuing basis be financed or recovered primarily through user charges.

Entitlement: The amount of payment to which a state
or local government is entitled pursuant to an allocation formula contained in applicable statutes.

EOC: abbreviation. Emergency Operation Center. This
is only activated during an emergency situation by
authorized Town personnel.

ERAF: abbreviation. Educational Revenue
Augmentation Fund. A shift of property tax revenues
from cities, counties and other local agencies to the
State in support of schools.

Expenditure: Decreases in net financial resources.

Expenditures include current operating expenses, which
require the current or future use of net current assets, debt service, and capital outlays.

FIC: abbreviation. Finance and Investment Committee.

Fiscal Year: A 12‐month period (usually July 1st through June 30th) to which the annual operating budget applies and at the end of which a government determines its
financial position and the results of its operations.

Fixed Assets: Equipment costing $5,000 or more,
including tax, and not qualifying as a capital
improvement project.

Full‐Time Equivalent (FTE): The conversion of full‐time and part‐time employee hours to an equivalent of a
full-time position. For example: one person working
half‐time would count as 0.5 FTE.

Fund: A fiscal and accounting entity with a self‐
balancing set of accounts in which cash and other
financial resources, all related liabilities and residual equities, or balances, and changes therein, are
recorded and segregated to carry on specific activities or attain certain objectives in accordance with special regulations, restrictions, or limitations.

Fund Balance: The difference between fund assets and
fund liabilities of governmental and similar trust funds.

General Fund: The fund used to account for all financial resources, except those required to be accounted for
in another fund.

Generally Accepted Accounting Principles (GAAP):

Uniform minimum standards of/ and guidelines for
financial accounting and reporting. They govern the
form and content of the basic financial statements of
an entity. GAAP encompasses the conventions, rules
and procedures necessary to define accepted

Page 465 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 211 Appendix
accounting practices at a particular time. They include not only broad guidelines of general application, but
also detailed practices and procedures. GAAP provides a standard by which to measure financial presentations.

Governmental Funds: Funds general used to account
for tax‐supported activities. There are five different
types of governmental funds: the general fund, special
revenue funds, debt service funds, capital projects
funds, and permanent funds.

Grants: Contributions of cash or other assets from
another governmental agency (usually) to be expended
or used for a specified purpose, activity or facility.

Infrastructure: All City owned facilities supporting
the operation of the governmental unit. It includes:
streets, roads, bridges, curbs and gutters, parks, water and sewer lines, storm drains, water pump stations
and reservoirs, water wells, sewer lift stations, all
government buildings and related facilities.

Internal Service Fund: A fund used to account
for the financing of goods or services provided by
one department to other departments on a costreimbursement basis.

Investment: Securities and real estate purchased and
held for the production of income in the form of interest, dividends, rentals or base payments.

Long Term Debt: Debt with a maturity of more than
one year after the date of the issues.

Materials & Services: Expenses which are charged
directly as a part of the cost of a service.

Modified Accrual Basis: The accrual basis of accounting where revenues are recognized when they become both
“measurable” and “available” to finance expenditures of the current period. All governmental funds and agency
funds are accounted for using the modified accrual basis of accounting.

Net Income (Loss): Proprietary fund excess (deficit) of operating revenues and operating transfers-in over
operating expenses, non-operating expenses and
operating transfers-out.

Non‐Operating Expenses: Proprietary fund expenses
not directly related to the fund’s primary activities (e.g. interest).

Non‐Operating Revenues: Proprietary fund revenues
incidental to, or by‐products of, the fund’s primary
activities.

Operating Expenses: Proprietary fund expenses related
directly to the fund’s primary activities.

Operating Income: The excess of proprietary fund
operating revenues over operating expenses.

Operating Revenues: Proprietary funds revenues
directly related to the fund’s primary activities. They consist primarily of user charges for goods and services.

Operating Transfers: Legally authorized transfers from
a fund receiving revenue to the fund through which
the resources are to be expended, such as transfers
from the General Fund to a Special Revenue or Capital
Projects Fund.

Ordinance: A formal legislative enactment by the City
Council. If it is not in conflict with any higher form of law, it has the full force and effect of law within the boundaries of the City.

PCI: abbreviation. Pavement Condition Index.

Preliminary Budget: A budget in its preliminary
preparation stage prior to review and formulation by
the City Council. In the preliminary stage, a budget
forecasts current costs into the future and new or
modified spending proposals for the future.

Program: Group activities, operations, or organization
units directed to attaining specific purposes or
objectives.

Program Purpose: A general statement explaining the
reason a particular program or division exists.

Proprietary Fund: The classification used to account
for a government’s ongoing organizations and activities that are similar to those often found in the private
sector (i.e., enterprise and internal service funds). All assets, liabilities, equities, revenues, expenses and
transfers relating to the government’s business and

Page 466 of 485 ends

212 Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan Appendix
quasi-business activities are accounted for through
proprietary funds.

Reserved Fund Balance: Those portions of fund balance
that have not been appropriated for expenditure or that are legally segregated for a specific future use.

Resolution: A special or temporary order of the City
Council requiring less formality than an ordinance.

Retained Earnings: An equity account reflecting the
accumulated earning of an enterprise or internal service fund.

Revenues: (1) Increases in net current assets of a
governmental fund type from other than expenditure
refunds and residual equity transfer. (2) Increases in
the net total assets of a proprietary fund type from
other than expense refunds, capital contributions and
residual equity transfers.

Risk Management: All the ways and means used to
avoid accidental loss or to reduce its consequences if
it does occur.

Self‐Insurance: A term often used to describe the
retention by an entity of a risk of loss arising out of the ownership of property or from some other cause,
instead of transferring that risk to an independent third party through the purchase of an insurance policy. It is sometimes accompanied by the setting aside of assets
to fund any related losses. Because no insurance is
involved, the term self‐insurance is a misnomer.

Service Reimbursements: Transactions that constitute
reimbursements to a department/division for
expenditures or expenses initially made from it but
that properly apply to another department/division.

Service Level Measure: A statement describing an
activity conducted or performed by the program/
division. A program will usually have many Service Level Measures. Service Level Measures provide quantifiable
and qualifiable information as to the level of service to be provided in relation to the level of fund indicated in the budget.

Special Revenue Fund: A fund used to account for the
proceeds of specific revenue sources that are legally
restricted to expenditures for specified purposes.

Specific Program Objectives: An “action” statement
indicating the new or special activities proposed for a program.

Taxes: Compulsory charges levied by a government for
the purpose of financing services performed for the
common benefit. This term does not include specific
charges made against particular persons or property
for current or permanent benefits such as special
assessments. Neither does the term include charges
for services rendered only to those paying such charges as, for example, user charges.

Transfers: Payments from one fund to another ideally
for work or services provided, or to cover operating
expense shortfalls.

Triple Flip: Backfill of the confiscated local sales tax reimbursed through a series of revenue swapping
procedures to guarantee repayment for the California
Economic Recovery Bond.

Trust Fund: Funds used to account for assets held by a
government in a trustee capacity for individuals, private organizations, other governments and/or funds.

Page 467 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 213 Appendix
Gann Limit
The Town is required by Article XIIIB of the California Constitution (Proposition 4) to calculate, each fiscal year, the maximum amount of appropriations subject to limitation. This “Gann Limit” is designed to restrict the annual growth of tax revenues used to fund governmental operations.

Proposition 111, approved by voters in June 1990, amended Article XIIIB to provide greater flexibility in calculating the limit by allowing the use of additional growth factors. Each year, the Town selects the applicable factors—such as population and cost of living changes—to determine the maximum allowable increase in the appropriations limit.

For FY 2025–26, the Town’s appropriations subject to limitation are below the Gann Limit.

Appropriations Limit Amount
Prior Year Appropriations Limit $ 9,499,965
Adjustment Factors *
Population Change (POP) 0.33% City Population
Cost of Living (COL) 6.44% State Per Capita Personal Income Adjustment Factor = (1+COL)*(1+POP) 106.79%
Cuurent Year Appropriations Limit $ 10,144,994
Appropriations Subject to Limitation
Proceeds of Taxes $ 10,051,954
Less: Exclusions $ 1,502,095
Appropriations Subject to Limitation $ 8,549,859
Gann Limit Comparison
Current Year Appropriations Limit $ 10,144,994
Less: Appropriations Subject to Limitation $ 8,549,859
Under / (Over) Limit $ 1,595,135
* Source: California Department of Finance

Page 468 of 485 ends

The Town of Los Altos Hills
26379 Fremont Road
Los Altos Hills, CA 94022

Page 469 of 485 ends

Town of Los Altos Hills | FY 2025-26 Operating Budget and FY 2026-2030 Five Year Capital Improvement Plan 215 Appendix

Page 470 of 485 ends

ITEM 8A Staff Report
UPDATED 06.26.2025
TOWN OF LOS ALTOS HILLS June 26, 2025
Staff Report to the City Council
_____________________________________________________________________________ SUBJECT: COUNCIL DISCUSSION AND DIRECTION ON ALLOCATION OF

COMMUNITY SERVICE GRANT FUNDS TO NONPROFIT

ORGANIZATIONS
FROM: Thomas Leung, Finance Director
APPROVED: Peter Pirnejad, City Manager
RECOMMENDATION: That the City Council:

Provide direction on the allocation of the $40,000 Community Service Grant Funds to nonprofit organizations.

BACKGROUND:

Each year, the Town allocates Community Service Grant funding to nonprofit organizations that promote public health, safety, and quality of life. For FY 2025–26, $40,000 is available for distribution.

DISCUSSION:

Staff seeks Council direction on how to distribute the funds among the organizations. Historical allocations and current funding requests are provided below to inform this discussion.

For FY 2025–26, nonprofit organizations have requested a total of $7587,000 in funding—more than the $40,000 available for allocation. Council may consider historical funding levels, the scope of community impact, and alignment with Town priorities in determining how to allocate the available funds.
2020-21 2021-22 2022-23 2023-24 2024-25 2025-26
Actual Actual Actual Actual Actual Request
Friends of Deer Hollow Farm 5,000 5,000 6,000 5,000 5,000 5,000 Hidden Villa 10,000 100,000 10,000 10,000 10,000 10,000 Los Altos Chamber of
Commerce 5,000 15,000 5,000 5,000 5,000 10,000
Community Services Agency
(CSA) 5,000 - 25,000 25,000 10,000 25,000
Counseling and Support
Services for Youth (CASSY) - - - - 10,000 16,000
Los Altos Mountain View
Community Foundation
(LAMVCF)
5,000 - 5,000 5,000 - 8,000

Page 471 of 485 ends

Staff Report to City Council Page 2
Community Service Grants
June 26, 2025
Rotary Club of Los Altos
(Art in the Park) - - - - - 1,000
Community Health
Awareness Council (CHAC) 16,550 120,200 34,000 34,040 - - North County Library
Authority (NCLA)
11,339 6,308 - - - -
Total $57,889 $246,508 $85,000 $84,040 $40,000 $75,000
The mission and impact of each nonprofit organization is provided below. 2025-26 Potential Recipient Nonprofit Organizations
Nonprofit Name Mission Impact
Friends of Deer
Hollow Farm
Supports Deer Hollow Farm’s
educational and historical programs
at Rancho San Antonio Preserve.

Serves over 100,000 visitors
annually, including 5,000 K–12
students. 2025 priorities include
raising $100,000 for the Animal
Trust Fund and building a
protective shelter for the Ohlone
Tule House, an outdoor cultural
education exhibit.

Hidden Villa
Inspires a just and sustainable
future through environmental
education, community programs,
and land stewardship.

Engages 30,000+ visitors annually
through farm tours, youth camps,
and volunteer activities. Donates
organic produce to local food
banks and stewards 1,600 acres of
protected open space.

Los Altos Chamber
of Commerce
Promotes economic vitality in Los
Altos and Los Altos Hills through
advocacy, leadership development,
and events.

Connects local businesses,
residents, and government through
business support programs and
civic events like the Los Altos Fall
Festival. Helps maintain a strong
and vibrant local economy.

Community Services
Agency (CSA)
Provides critical safety-net services
to low-income, unhoused, and
elderly residents in the area.

Served over 6,000 individuals last
year, including 3,200 through food
assistance and 1,300 unhoused
residents. The $25,000 request
supports emergency rental aid,
case management, and food
programs for Los Altos Hills
residents.

Counseling and
Support Services for
Youth (CASSY)
Ensures students have access to
free, culturally responsive mental
health services in school settings.

Provides confidential counseling
for students dealing with anxiety,
depression, trauma, and academic
stress. Its school-based model
reaches youth early, improves
resilience, and reduces stigma
around seeking help.

Page 472 of 485 ends

Staff Report to City Council Page 3
Community Service Grants
June 26, 2025
Los Altos Mountain
View Community
Foundation
(LAMVCF)
Supports community well-being by
funding local nonprofits and
launching initiatives in education,
equity, and sustainability.

Coordinates cross-sector
partnerships and distributes grants
to strengthen local nonprofits. The
$20,000 request would expand
place-based programs benefiting
Los Altos Hills and surrounding
areas.

Rotary Club of Los
Altos (Art in the
Park)
Advances charitable and
humanitarian causes through
volunteer service and community
engagement.

Organizes the annual “Art in the
Park” show to raise funds for local
scholarships, disaster relief, and
health initiatives. All proceeds are
reinvested in both local and
international service projects.

ENVIRONMENTAL REVIEW:

This action does not qualify as a “Project” as defined in California Government Code Section 15378(b) of the Guidelines for California Environmental Quality Act. 2024-2025 CITY COUNCIL WORK PLAN:

This action is not specifically identified in the 2024-25 City Council Work Plan and falls into the day-to-day operations of the Town.

FISCAL IMPACT:

Approval of this action will allocate the $40,000 Community Service Grant Funds included in the FY 2025-26 budget.

ATTACHMENTS:

1. Friends of Deer Hollow Farm Request

2. Los Altos Chamber of Commerce Request

3. Community Services Agency (CSA) Request

4. Counseling and Support Services for Youth (CASSY) Request

5. Los Altos Mountain View Community Foundation (LAMVCF) Request & Local Impact Collective

Page 473 of 485 ends

Outlook
RE: $5,000 Grant for Friends of Deer Hollow Farm
From Peter Pirnejad <[email protected]>
Date Tue 6/10/2025 8:35 PM
To George Tyson
Cc Leona Pearce; Arika Miller <[email protected]>; Thomas Leung <[email protected]> Will do
I will put it on the list
Adding Arika and Thomas
Peter Pirnejad, ICMA-CM
City Manager
Town of Los Altos Hills
[email protected]
From: George Tyson
Sent: Monday, June 9, 2025 4:55 AM
To: Peter Pirnejad <[email protected]>
Cc: Leona Pearce
Subject: Fwd: $5,000 Grant for Friends of Deer Hollow Farm Hi Peter,
I would like to support the following funding request for the City Council to consider in our coming year’s budget.

GT
Sent from my iPhone
Begin forwarded message:

From: Leona Pearce
Date: June 8, 2025 at 2:45:52 AM GMT+2
To: George Tyson
Subject: $5,000 Grant for Friends of Deer Hollow Farm
Hi George,
So glad to hear that you go by Deer Hollow Farm all the time. Rancho San Antonio is such an incredible open preserve. I love it too!!
We are very thankful for the $5,000 grants that the Town of Los Altos Hills has provided in the past and would be delighted to receive another $5,000 grant in 2025. We have two specific projects that we are actively fundraising for:

1. Animal Trust Fund
ITEM 8A, Attachment 1
UPDATED 06.26.2025

Page 474 of 485 ends

Caring for our animals - feeding them, providing medical attention and acquiring new additions costs approximately $45,000 each year. This year, we are aiming to rebuild and grow our Animal Trust Fund to ensure long-term security and care for our beloved animals. Our goal is to raise $100,000 by 30 June 2025.

2. Shelter to Protect Ohlone Village Tule House
The Tule House has to be re-built each year due to rain and decay. The shelter would protect the House for multiple years without the need to re-build. The 18’x18’x18’ structure could accommodate the Tule House and space for 10 students. $7300 is requested solely for materials to build the shelter. To date we have raised $2,000 with $5,300 still to raise. Attached is a photo of what a Tule Shelter would look like.

I have included in this email our 2024 Annual Report. The Annual Report discusses our annual highlights and our events and outreach. If the Town of Los Altos would prefer that their donation be for general expenditure, this report describes the types of places where such funding could be used.

We also refreshed our website earlier this year, which can be found at https://www.deerhollowfarm.org/. Let me know what you think of it. I built the new website as my first job for Friends of Deer Hollow Farm when I joined their board late last year.

Lastly, if you'd like a tour of the farm some day, please do let me know. We hosted Ellen Kamei earlier in the year and she now features in our website:
https://www.deerhollowfarm.org/contact
Please let me know if you need any further information.

Thanks Leona
<Friends of Deer Hollow Farm 2024 Annual Report.pdf>
<Tule shelter.jpg>

Page 475 of 485 ends

June 24, 2025
Mayor Kavita Tankha and Members of the Town Council
Town of Los Altos Hills
26379 Fremont Road
Los Altos Hills, CA 94022
Dear Mayor Tankha and Esteemed Members of the Council,
On behalf of the Los Altos Chamber of Commerce, I am writing to express our deep appreciation for the Town of Los Altos Hills' steadfast support through an annual grant of $5,000. We are truly appreciative of your support which directly impacts the services that we offer to Los Altos Hills residents. This adjustment reflects the enhanced scope, impact, and breadth of services the Chamber proudly provides to residents, businesses, and visitors of Los Altos Hills and takes into account the increase in the cost of goods and services over the past 10 years. There has been no modification to the amount since 2016 and thus we are respectfully requesting an increase in this annual grant to $10,000.

The Los Altos Chamber of Commerce actively serves both the Town of Los Altos Hills and the City of Los Altos. We are so fortunate to have the best of both worlds in our combined community!
The Chamber of Commerce operates the Visitors Center, where we welcome residents and guests and provide essential information, directions to Town Hall, and sell Pathway Maps on behalf of the Town, enhancing both convenience and community engagement.

One of our hallmark events is the annual State of the Cities Luncheon, held at the beautiful Fremont Hills Country Club. This distinguished event brings together 200 of the region’s top elected officials, community leaders, and residents to celebrate the accomplishments of our mayors. Recent speakers have included notable figures such as State Controller Malia Cohen, U.S. Congressman Sam Liccardo, Former U.S. Congresswoman Anna G. Eshoo, CA State Senator Josh Becker, and State Assembly member Marc Berman. This gathering has become a beloved annual tradition which showcases the pastoral charm of the Los Altos Hills community, enriched by the stirring bagpipes of the Santa Clara County Sheriff Pipe & Drum Corp and inspiring addresses from each of our two mayors.

The Chamber proudly supports and collaborates with 32 diverse and dynamic organizations based in Los Altos Hills, including Foothill College, St. Nicholas School, Fremont Hills Country Club, Hidden Villa, Krause Center for Innovation, and the LAH ITEM 8A Attachment 2
UPDATED 06.26.2025

Page 476 of 485 ends

County Fire District. Our partnership with Foothill College notably led to the significant expansion of their international student program, bringing thirty new international students from the United Arab Emirates in 2023. This achievement was facilitated by the Chamber’s innovative leadership. The Chamber Delegation, which included the former Chancellor of Foothill-DeAnza Community College District--Judy Miner met with Dubai Chamber of Commerce and State Department officials. This new student exchange program has resulted in millions of dollars in additional income for the College.

The Chamber proactively promotes Los Altos Hills through strategic publicity and public relations partnerships, including collaborations with Modern Luxury Silicon Valley Magazine and Punch Magazine. We provide interesting stories, beautiful bucolic photography and facilitate interviews. We also independently produce and distribute the acclaimed Los Altos Magazine—a destination guide for Los Altos & Los Altos Hills. This beautiful, glossy publication is beloved by residents and widely available at prime locations. The magazine vividly portrays the vibrancy, innovation, educational excellence, and stunning natural beauty of our region.

A heartfelt new tradition that the Chamber proudly supports is the annual Veterans Day celebration, hosted by Mayor Kavita Tankha and Councilmember Neysa Fligor, and Mistress of Ceremonies by Chamber CEO Kim Mosley. This community gathering draws over 100 residents, reflecting our profound gratitude to veterans for their dedicated service.

The Chamber has consistently advocated for educational initiatives, notably supporting the LASD School Bond Measure EE—a critical $350 million measure aimed at enhancing school facilities and advancing educational excellence. The excellence of our shared elementary school and high school districts is vital to the success of our community and resulting prime property values.

The requested grant of $10,000 will support and enhance these impactful programs and initiatives, directly benefiting the residents of Los Altos Hills. Your continued support will enable us to further champion economic vitality, community engagement, and shared prosperity.

Thank you very much for your consideration and ongoing partnership. We are deeply grateful for your continued investment in the well-being and future of our shared community.

Warm regards,
Kim Mosley
President & CEO
Los Altos Chamber of Commerce

Page 477 of 485 ends

ITEM 8A Attachment 3
UPDATED 06.26.2025
June 23, 2025
Dear Los Altos Hills Council Members,
I am writing to you today on behalf of Community Services Agency of Mountain View, Los Altos and Los Altos Hills. We are seeking general operating support in the amount of $25,000 for Fiscal Year 2026.

Community Services Agency provides a safety net for elderly, low-income, and unhoused residents of Mountain View, Los Altos, and Los Altos Hills. We offer nutrition services, shopping assistance, and case management for seniors; food and emergency financial aid for low-income individuals and families; and comprehensive case management for those experiencing homelessness. Our services are local, direct, and personal, and our staff and volunteers constantly seek to improve our clients’ stability, self-reliance, and dignity.

In these challenging economic times, our services are more essential than ever. CSA’s Food and Nutrition Center served over 3,200 individuals last year. Our Homeless Services Program served 1,300 individuals last year, of whom 320 are children. Rental assistance continues to be critical in preventing our neighbors in need from falling into homelessness, and CSA served nearly 400 individuals through this program last year. Overall, need continues at a higher level than prior to the pandemic, with CSA serving over 6,000 of the most vulnerable members of the community each year, and we are preparing for a potential increase next year due to changing economic conditions.
$25,000 from the Town of Los Altos Hills will help us continue to provide these critical services to those most in need in our community. Our partnership would keep families in their homes, help unhoused individuals find stable housing, ensure that low-income families are fed through their most challenging times, and keep seniors living independently in their homes for as long as possible.

Thank you for considering our proposal, and if you have any questions or want to speak further about our request, please feel free to contact me at (650) 968-5427 or [email protected].

Warm regards,
Tom Myers
Executive Director

Page 478 of 485 ends

544 Valley Way, Milpitas, CA 95035 • 408-493-5289 • www.cassybayarea.org Counseling and Support Services for Youth is a registered 501(c)(3) nonprofit organization June 24, 2025
The Honorable Kavita Tankha
Mayor of the Town of Los Altos Hills
26379 Fremont Road
Los Altos Hills, CA 94022
Dear Mayor Tankha and Members of the Los Altos Hills Town Council, Since 2009, Counseling and Support Services for Youth (CASSY) has partnered with local schools to provide professional, on-campus mental health services to students free of charge. As you may know, a�er a rigorous district process to find a new partner, CASSY was selected to con�nue the work CHAC began at the Mountain View Los Altos High School District. CASSY is now providing the mental health support to these schools that CHAC has provided in the past. The transi�on has been seamless. According to MVLA district staff, there “has been a ridiculously smooth and wonderfully posi�ve transi�on” to CASSY’s assuming responsibility for providing school-based counseling services.

With the support of the Town of Los Altos Hills in the 2024-2025 school year, CASSY provided over 1700 individual, group, and check-in sessions to students, while suppor�ng families 575 �mes and school staff 567 �mes––while providing a mental health safety net for over 4500 students at Los Altos High School, Mountain View High School, and Alta Vista High School.

We are reques�ng $16,000 from the Town of Los Altos Hills to strengthen and expand our reach within the district. Heading into the 2025-2026 school year, the district has approached us for ways to expand footprint through increased staffing and assistance in implemen�ng school-based medical billing. Your investment will help CASSY provide the following services:

Individual, Family, and Group Counseling – Our professional therapy services include both parent/guardian consent and minor consent, when required. While offering services free of charge to students and their families, CASSY provides medical billing assistance to our school partners to help them navigate the new funding landscape in California.

Drop-in and Check-in Services – In addi�on to therapy, CASSY offers drop-in counseling support and check-in services to the en�re student body. Our door is open to all students.

ITEM 8A Attachment 4
UPDATED 06.26.2025

Page 479 of 485 ends

544 Valley Way, Milpitas, CA 95035 • 408-493-5289 • www.cassybayarea.org Counseling and Support Services for Youth is a registered 501(c)(3) nonprofit organization Proac�ve Mental Health Educa�on – Our Tier 1 services include socioemo�onal educa�onal presenta�ons and student workshops, as part of our evidence-based, mul�-�ered mental health support program.

Crisis Interven�on and Treatment – Crisis interven�on services are available to all students, including risk assessments and safety planning, collabora�on with mobile crisis, par�cipa�on in re-entry mee�ngs, and campus-wide crisis and grief support (e.g. death of a community member).

Parent Support and Educa�on – CASSY provides confiden�al consulta�ons, support, and resources to parents and caregivers free of charge.

Staff Support and Educa�on – In addi�on to private consulta�ons with staff, CASSY provides training on mental health issues, wellness center coverage, observa�ons, and atendance in school team mee�ngs (e.g. COST, SST, IEP) to assist with comprehensive student support.

Clinical Administra�on – CASSY’s data repor�ng and analysis con�nuously improve services and measure impact for our school partners.

Amidst the ongoing youth mental health crisis, the need for youth mental health support is great. With youth anxiety and depression at elevated levels, mental health struggles are now the primary reason for child and youth hospitaliza�on in Santa Clara County. School-based counseling helps students reach their full poten�al while serving as a powerful tool in crisis preven�on––keeping students from falling through the cracks. Last year, at one of our local schools, what began as a simple check-in with a student became a life-saving interven�on. Every year, partnering closely with school staff who know students best, CASSY’s compassionate, professional mental health services save lives.

We deeply appreciate your investment in young people in our community. As Surgeon General Vivek Murthy noted, it will take a “whole-of-society effort” to support youth mental wellness. Your con�nued partnership and support will allow us to make a tangible difference in young lives together.

In community,
Kathleen Granger
CASSY
Director of Finance and Opera�ons

Page 480 of 485 ends

Submitted by: Los Altos Mountain View Community Foundation (LAMVCF) Funding Request: $8,000
Funding Period: Juy 1, 2025 – April 30, 2026
Proposal Title: Empowering Local Leaders, Strengthening Los Altos Hills Introduction:

The Los Altos Mountain View Community Foundation (LAMVCF) champions the power of local leadership to drive meaningful change. Through our Local Impact Collective, we serve as fiscal sponsor to 19 community-led projects advancing diverse missions—from youth empowerment and public health to climate resilience and food security—throughout Los Altos, Los Altos Hills, and Mountain View.

These initiatives reflect the heart of Los Altos Hills: engaged, visionary residents striving to uplift their neighbors and environment. Yet behind each project is often a volunteer leader navigating challenges with limited support. LAMVCF seeks to support that by launching a new capacity-building initiative—connecting leaders, fostering growth, and ensuring sustainability.

The Opportunity:

We are seeking an $10,000 investment from the City of Los Altos Hills to help our local leaders engage residents in their work. Your partnership will directly enable:
● A Networking Summit that unites our 19 Local Impact Collective projects to exchange ideas, build peer support, and share best practices.

Why It Matters:

Community strength starts with capable, connected leaders. Many Local Impact Collective leaders lack access to professional training, strategic planning tools, or peer learning networks.

Without these, their important work risks burnout or fragmentation.

Investing in these changemakers is an investment in the community fabric of Los Altos Hills.

Capacity-building funds help ensure they can:
● Raise funds more effectively
● Strengthen governance and accountability
● Plan strategically for growth and longevity
● Improve service delivery to residents
ITEM 8A Attachment 5
UPDATED 06.26.2025

Page 481 of 485 ends

Your Impact:

This grant will help catalyze a more resilient and connected nonprofit ecosystem in Los Altos Hills—one equipped to meet today’s needs and tomorrow’s challenges. It is a direct way for the City to strengthen civic capacity, encourage volunteerism, and expand the reach of essential services.

Project Goals and Objectives:

Goal: Strengthen the organizational capacity of 19 Local Impact Collective projects. ● Host a one-day Networking Summit focused on leadership development, cross-sector collaboration, and resource sharing.

Proposed Activities:

1. Networking Summit
○ Keynotes, workshops, and panels on nonprofit management, succession planning, and local advocacy.
○ Facilitated sessions for collaboration, mentoring, and peer learning. ○ Opportunities for project leaders to showcase their work.

Budget:
● Networking Summit:
○ Venue, AV, logistics: Donated in Kind by the City of Los Altos ■ Additionally $5,000 grant from Los Altos
○ Speaker and three facilitators: $10,000
○ Catering and materials: $2,500
○ Total Summit Cost: $12,500
● LAMVCF Project Management (5%): $625
○ Total Cost - $13,125
● Total Request: $8,000
Expected Outcomes:

1. Demonstrated improvements in project leadership capacity and program effectiveness.

2. Increased collaboration across local initiatives sparked by the Summit.

3. Measurable skill development and strategic progress among project leaders.

Evaluation Plan:
● Post-Summit participant survey
● Follow-up survey six months later to assess continued growth and collaboration

Page 482 of 485 ends

Conclusion:

With the support of the town of Los Altos Hills, LAMVCF can provide resources, training, and networks to those working tirelessly for the good of our shared community. This proposal offers an opportunity to elevate grassroots leadership and secure the long-term vitality of essential programs that directly benefit Los Altos Hills residents.

Together, let’s invest in the people who are investing in our future.

Page 483 of 485 ends

Local Impact Collective
LAMVCF’s Local Impact Collective provides local changemakers with the fiscal sponsorship, strategic guidance, and operational support they need to bring their community-focused visions to life—without the immediate burden of forming a standalone nonprofit. By offering a trusted legal and financial framework, we help emerging leaders focus on what matters most: creating impact. Following is an overview of the 19 fiscally-sponsored projects that make up the Local Impact Collective.

Asian Women Empowered (MV) is dedicated to improving the status of AAPI women and girls in Silicon Valley and supporting them to achieve the highest levels of leadership without obstruction or other boundaries while providing a collective voice on policy issues affecting the Silicon Valley AAPI community.

Center for Age-Friendly Excellence (CAFE) (LA) is advancing our understanding of age-friendly cities and communities. CAFE intends to drive transformational change in creating healthy, active, sustainable, and engaged intergenerational communities.

Evergreen Collective (MV) is a nonprofit organization that builds sustainable financial development systems for BIPOC-led & serving nonprofits and their communities.

Los Altos for Racial Equity (LARE) (LA) was established to ensure equity for the Los Altos BIPOC Community by influencing policy change, engaging the public in racial equity advocacy, and promoting diversity in community businesses, arts and events.

MVLA Service League of Boys (SLOBs) (LA, LAH, MV) is for parents and sons to initiate and promote educational and charitable endeavors that foster community responsibility as well as strengthen their parent-son relationship.

Senior Inclusion and Participation Project (SIPP) (LA) is an innovative, community-based project to raise awareness of the loneliness experienced by many of today’s older adults and to reduce the impact social isolation has on their health and psychological well-being.

The Startup Squad (LA) empowers girls to realize their potential and follow their dreams, whatever their passions, through entrepreneurship.

Performing Arts Theater Project (LA) was established to ignite a capital campaign to support a groundbreaking new theater to downtown Los Altos, bringing together civic pride, artistic innovation, and smart fiscal management.

Community Women’s Chorus (LA) is an ensemble of dedicated singers who are devoted to performing uplifting choral music to those in senior living facilities and memory care centers.

First Fridays (LA) promotes vibrancy and builds community in downtown Los Altos by organizing a free, fun, and family-oriented event on the First Friday of each month from 6-8 pm.

GreenTown Los Altos (LA, LAH) has a mission to protect and enhance the environment of Los Altos & Los Altos Hills through community engagement, education, and advocacy while contributing to and leveraging regional and global environmental efforts.

Los Altos Forward (LA) envisions a downtown that’s more than just buildings in which to shop and dine; it’s a place with wonderful public spaces where citizens can come to have fun, socialize, and see their ____________________________________________________________________________________________ Transforming community potential into action

Page 484 of 485 ends

friends and neighbors.

MVLA Scholars (MV/LA) serves low-income, first-generation college students from Mountain View and Los Altos. A unique combination of ongoing financial support, one-on-one mentoring, an emphasis on career readiness, and a deep community-based network ensure our Scholars are empowered to succeed in life.

Resilient Los Altos (LA) is dedicated to improving the resilience of the community of Los Altos, California, and adjacent areas. Their goal is to work with major stakeholders to help residents be prepared to handle major emergencies.

Soil & Water Garden (MV) is a group of greater Mountain View residents with a love for the outdoors, getting our hands dirty, and creating DIY projects. They aim to help build a community space where people can come to gather, garden, create, and learn from each other.

TACO (Terrible Adult Chamber Orchestra) (LA) is a full symphonic orchestra with musicians from around the Bay Area who gather once a month in Los Altos or Mountain View to play music for fun. It’s a social and supportive intergenerational community with musicians of all skill levels and talents.

The Los Altos Institution (LA) is America's first high school student-run and oriented policy think tank that hosts events, conducts research, and works to build better policy education and dialogue worldwide and in our community.

Marco's Mission (LA) spreads awareness about the dangers of addiction and substance abuse, and provides resources, support, and preventative measures to teenagers struggling with drug addiction. It is dedicated to 19-year-old Marco Troper, who lost his life in February of 2024 to an overdose.

Together We Can (TWC) (LA, LAH) is an organization designed for youth to give back in a meaningful way. Their goal is to have girls find out the true needs of their own community and work together to decide how best to fill in the gaps.

LA: Serves Los Altos and/or started by Los Altos residents LAH: Serves Los Altos Hills and/or started by Los Altos Hills residents MV: Serves Mountain View and/or started by Mountain View residents ____________________________________________________________________________________________ Transforming community potential into action

Page 485 of 485 ends
← All documents from this meeting