38077.00180\29080232.10
-97- 00 72 13 – GENERAL CONDITIONS
F. Mediation. Within 10 business Days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 Days after the City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business Days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

1. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

2. For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3. Unless otherwise agreed to by the City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.

4. The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are established for all civil actions filed to resolve claims of $375,000 or less:

1. Within 60 Days, but no earlier than 30 Days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. The mediation process shall provide for the selection within 15 Days by both parties of a disinterested third person as mediator,

Page 265 of 557 ends

38077.00180\29080232.10
-98- 00 72 13 – GENERAL CONDITIONS
shall be commenced within 30 Days of the submittal, and shall be concluded within 15 Days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

2. If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra Work, disputed Work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra Work, disputed Work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the Work is completed or the date the Contractor last performs Work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.

ARTICLE 47 CITY’S RIGHT TO TERMINATE CONTRACT
A. Termination for Cause by the City:

1. In the sole estimation of the City, if the Contractor refuses or fails to prosecute the Work or any separable part thereof with such diligence as will insure its completion within the time specified by the Contract Documents, or any extension thereof, or fails to complete such Work within such time, or if the Contractor should be adjudged a bankrupt, or if it should make a general assignment for the benefit of its creditors, or if a receiver should be appointed on account of its insolvency, or the Contractor or any of its subcontractors should violate any of the provisions of this Contract, the City may serve written notice upon the Contractor and its Surety of the City's intention to terminate this Contract. This notice of intent to terminate

Page 266 of 557 ends

38077.00180\29080232.10
-99- 00 72 13 – GENERAL CONDITIONS
shall contain the reasons for such intention to terminate this Contract, and a statement to the effect that the Contractor's right to perform this Contract shall cease and terminate upon the expiration of ten (10) calendar days unless such violations have ceased and arrangements satisfactory to the City have been made for correction of said violations.

2. In the event that the City serves such written notice of termination upon the Contractor and the Surety, the Surety shall have the right to take over and perform the Contract. If the Surety does not: (1) give the City written notice of Surety's intention to take over and commence performance of the Contract within 15 calendar days of the City's service of said notice of intent to terminate upon Surety; and (2) actually commence performance of the Contract within 30 calendar days of the City's service of said notice upon Surety; then the City may take over the Work and prosecute the same to completion by separate contract or by any other method it may deem advisable for the account and at the expense of the Contractor.

3. In the event that the City elects to obtain an alternative performance of the Contract as specified above: (1) the City may, without liability for so doing, take possession of and utilize in completion of the Work such materials, appliances, plants and other property belonging to the Contractor that are on the site and reasonably necessary for such completion (A special lien to secure the claims of the City in the event of such suspension is hereby created against any property of Contractor taken into the possession of the City under the terms hereof and such lien may be enforced by sale of such property under the direction of the City Council without notice to Contractor.

The proceeds of the sale after deducting all expenses thereof and connected therewith shall be credited to Contractor. If the net credits shall be in excess of the claims of the City against Contractor, the balance will be paid to Contractor or Contractor’s legal representatives.); and (2) Surety shall be liable to the City for any cost or other damage to the City necessitated by the City securing an alternate performance pursuant to this Article.

B. Termination for Convenience by the City:

1. The City may terminate performance of the Work called for by the Contract Documents in whole or, from time to time, in part, if the City determines that a termination is in the City's interest.

2. The Contractor shall terminate all or any part of the Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of the City, the extent of termination, and the Effective Date of such termination.

3. After receipt of Notice of Termination, and except as directed by the City's Representative, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this Termination for Convenience clause, immediately proceed with the following obligations:
a. Stop Work as specified in the Notice.

Page 267 of 557 ends

38077.00180\29080232.10
-100- 00 72 13 – GENERAL CONDITIONS
b. Complete any Work specified in the Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
c. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Document is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety. d. Terminate all subcontracts to the extent that they relate to the portions of the Work terminated.
e. Place no further subcontracts or orders, except as necessary to complete the continued portion of the Contract.
f. Submit to the City's Representative, within ten (10) calendar days from the Effective Date of the Notice of Termination, all of the usual documentation called for by the Contract Documents to
substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the Contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the Effective Date of the Notice of Termination; (2) describe the costs incurred with particularity; and (3) be conspicuously identified as “Termination Costs occasioned by the City's Termination for Convenience.”

4. Termination of the Contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the Work performed.

5. In the event that the City exercises its right to terminate this Contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the Contract Documents, the following amounts:
a. All actual reimbursable costs incurred according to the provisions of this Contract.
b. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the City's Representative that it is reasonably probable that Contractor would have made a profit had the Contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.

Page 268 of 557 ends

38077.00180\29080232.10
-101- 00 72 13 – GENERAL CONDITIONS
c. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the Contract under this Article.

C. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of the City or the Contract is terminated.

ARTICLE 48 WARRANTY AND GUARANTEE OF WORK
A. Contractor hereby warrants that materials and Work shall be completed in conformance with the Contract Documents and that the materials and Work provided will fulfill the requirements of this Warranty. Contractor hereby agrees to repair or replace, at the discretion of the City, any or all Work that may prove to be defective in its workmanship, materials furnished, methods of installation or fail to conform to the Contract Document requirements together with any other Work which may be damaged or displaced by such defect(s) within a period of one (1) year from the date of the Notice of Completion of the Project without any expense whatever to the City, ordinary wear and tear and unusual abuse and neglect excepted. Contractor shall be required to promptly repair or replace defective equipment or materials, at Contractor’s option. All costs associated with such corrective actions and testing, including the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of the Contractor.

B. For any Work so corrected, Contractor’s obligation hereunder to correct defective Work shall be reinstated for an additional one (1) year period, commencing with the date of acceptance of such corrected Work. The reinstatement of the one (1) year warranty shall apply only to that portion of work that was corrected.

Contractor shall perform such tests as City may require to verify that any corrective actions, including, without limitation, redesign, repairs, and replacements comply with the requirements of the Contract. In the event of Contractor’s failure to comply with the above-mentioned conditions within ten (10) calendar days after being notified in writing of required repairs, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction thereof at Contractor’s sole expense. Contractor shall be obligated to fully reimburse the City for any expenses incurred hereunder immediately upon demand.

C. In addition to the warranty set forth in this Article, Contractor shall obtain for City all warranties that would be given in normal commercial practice and assign to City any and all manufacturer’s or installer’s warranties for equipment or materials not manufactured by Contractor and provided as part of the Work, to the extent that such third-party warranties are assignable and extend beyond the warranty period set forth in this Article. Contractor shall furnish the City with all warranty and guarantee documents prior to final Acceptance of the Project by the City as required.

Page 269 of 557 ends

38077.00180\29080232.10
-102- 00 72 13 – GENERAL CONDITIONS
D. When specifically indicated in the Contract Documents or when directed by the Engineer, the City may furnish materials or products to the Contractor for installation. In the event any act or failure to act by Contractor shall cause a warranty applicable to any materials or products purchased by the City for installation by the Contractor to be voided or reduced, Contractor shall indemnify City from and against any cost, expense, or other liability arising therefrom, and shall be responsible to the City for the cost of any repairs, replacement or other costs that would have been covered by the warranty but for such act or failure to act by Contractor.

E. The Contractor shall remedy at its expense any damage to City-owned or controlled real or personal property.

F. The City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. The Contractor shall within ten (10) calendar days after being notified commence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; the City shall have the right to replace, repair or otherwise remedy the defect, or damage at the Contractor’s expense.

G. In the event of any emergency constituting an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, the City may undertake at Contractor’s expense, and without prior notice, all Work necessary to correct such condition.

H. Acceptance of Defective Work.

1. If, instead of requiring correction or removal and replacement of Defective Work, the City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to City’s evaluation of and determination to accept such Defective Work and for the diminished value of the Work.

2. If any acceptance of defective work occurs prior to release of the Project Retention, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work and all costs incurred by City.

3. If the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

4. If the acceptance of Defective Work occurs after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

I. City May Correct Defective Work.

Page 270 of 557 ends

38077.00180\29080232.10
-103- 00 72 13 – GENERAL CONDITIONS

1. If Contractor fails within a reasonable time after written notice from City’s Representative to correct Defective Work, or to remove and replace rejected Work as required by City, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) Days’ written notice to Contractor, correct, or remedy any such deficiency.

2. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, take possession of Contractor’s tools, appliances, construction equipment and machinery at the Site, and incorporate in the Work all materials and equipment stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City and City’s Representative, and the agents, employees, other contractors, and consultants of each of them, access to the Site to enable City to exercise the rights and remedies to correct the Defective Work.

3. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by City correcting the Defective Work will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions into the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price.

4. Such claims, costs, losses and damages will include, but not be limited to, all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Defective Work.

5. If the Change Order is executed after all payments under the Contract have been paid by City and the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

6. If the Change Order is executed after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

7. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performance of the Work attributable to City correcting Defective work.

J. Nothing in the Warranty or in the Contract Documents shall be construed to limit the rights and remedies available to City at law or in equity, including, but not limited to, Code of Civil Procedure section 337.15.

Page 271 of 557 ends

38077.00180\29080232.10
-104- 00 72 13 – GENERAL CONDITIONS
ARTICLE 49 DOCUMENT RETENTION & EXAMINATION
A. In accordance with Government Code section 8546.7, records of both the City and the Contractor shall be subject to examination and audit by the State Auditor General for a period of three (3) years after final payment.

B. Contractor shall make available to the City any of the Contractor’s other documents related to the Project immediately upon request of the City.

C. In addition to the State Auditor rights above, the City shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Contractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to the City, for a period of four (4) years after final payment.

ARTICLE 50 SEPARATE CONTRACTS
A. The City reserves the right to let other contracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.

B. To ensure proper execution of its subsequent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the Work in place or discrepancies with the Contract Documents.

C. Contractor shall ascertain to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by the City in prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor exclusive occupancy at site of the Project.

Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer shall decide which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so that contractors may proceed simultaneously. The City shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.

ARTICLE 51 NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor’s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to the City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) calendar days after being sent by first class mail, whichever

Page 272 of 557 ends

38077.00180\29080232.10
-105- 00 72 13 – GENERAL CONDITIONS
is earlier. Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.

ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS
Pursuant to Public Contract Code section 9201, the City shall provide the Contractor with timely notification of the receipt of any third-party claims relating to the Contract. The City is entitled to recover reasonable costs incurred in providing such notification.

ARTICLE 53 STATE LICENSE BOARD NOTICE
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, California 95826.

ARTICLE 54 INTEGRATION
A. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.

B. Contract Documents Represent Entire Contract.The Contract Documents represent the entire agreement of the City and Contractor.

ARTICLE 55 ASSIGNMENT OF CONTRACT
Contractor shall not assign, transfer, convey, sublet or otherwise dispose of the rights or title of interest of any or all of this contract without the prior written consent of the City. Any assignment or change of Contractor’s name of legal entity without the written consent of the City shall be void.

Any assignment of money due or to become due under this Contract shall be subject to a prior lien for services rendered or Material supplied for performance of Work called for under the Contract Documents in favor of all persons, firms, or corporations rendering such services or supplying such Materials to the extent that claims are filed pursuant to the Civil Code, the Code of Civil Procedure or the Government Code.

ARTICLE 56 CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY Should a change be contemplated in the name or nature of the Contractor’s legal entity, the Contractor shall first notify the City in order that proper steps may be taken to have the change reflected on the Contract and all related documents. No change of Contractor’s name or nature will affect City’s rights under the Contract, including but not limited to the bonds.

ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS
Pursuant to Public Contract Code section 7103.5, in entering into a public works contract or subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to the City all rights, title, and interest in and to all

Page 273 of 557 ends

38077.00180\29080232.10
-106- 00 72 13 – GENERAL CONDITIONS
causes of action it may have under Section 4 of the Clayton Act (15 USC, Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from the purchase of goods, services, or materials pursuant to this contract or any subcontract. This assignment shall be made and become effective at the time the City tenders final payment to the Contractor, without further acknowledgment by the parties.

ARTICLE 58 PROHIBITED INTERESTS
No City official or representative who is authorized in such capacity and on behalf of the City to negotiate, supervise, make, accept, or approve, or to take part in negotiating, supervising, making, accepting or approving any engineering, inspection, construction or material supply contract or any subcontract in connection with construction of the project, shall be or become directly or indirectly interested financially in the Contract.

ARTICLE 59 CONTROLLING LAW
Notwithstanding any subcontract or other contract with any subcontractor, supplier, or other person or organization performing any part of the Work, this Contract shall be governed by the law of the State of California excluding any choice of law provisions.

ARTICLE 60 JURISDICTION; VENUE
Contractor and any subcontractor, supplier, or other person or organization performing any part of the Work agrees that any action or suits at law or in equity arising out of or related to the bidding, award, or performance of the Work shall be maintained in the Superior Court of Santa Clara County, California, and expressly consent to the jurisdiction of said court, regardless of residence or domicile, and agree that said court shall be a proper venue for any such action.

ARTICLE 61 LAWS AND REGULATIONS
A. Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on conduct of work as indicated and specified. If Contractor observes that drawings and specifications are at variance therewith, it shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided for in this Contract for changes in work. If Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, it shall bear all costs arising therefrom.

B. Contractor shall be responsible for familiarity with the Americans with Disabilities Act (“ADA”) (42 U.S.C. § 12101 et seq.). The Work will be performed in compliance with ADA regulations.

ARTICLE 62 PATENTS
Contractor shall hold and save the City, officials, officers, employees, and authorized volunteers harmless from liability of any nature or kind of claim therefrom including costs and expenses for or on account of any patented or unpatented invention, article or appliance manufactured, furnished or used by Contractor in the performance of this contract.

Page 274 of 557 ends

38077.00180\29080232.10
-107- 00 72 13 – GENERAL CONDITIONS
ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS
All Contract Documents furnished by the City are City property. They are not to be used by Contractor or any subcontractor on other work nor shall Contractor claim any right to such documents. With exception of one complete set of Contract Documents, all documents shall be returned to the City on request at completion of the Work.

ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST
In accordance with Revenue and Taxation Code section 107.6, the Contract Documents may create a possessory interest subject to personal property taxation for which Contractor will be responsible.

ARTICLE 65 SURVIVAL OF OBLIGATIONS
All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor.

Page 275 of 557 ends

38077.00180\29080232.10
-108- 00 73 13 – SPECIAL CONDITIONS
00 73 13 – SPECIAL CONDITIONS

1.1 Engineer of Record.

A For purposes of this Project, the Engineer of Record or Engineer shall be:

1. Design Engineer – Curtis Lam, HydroScience Engineers, Inc.

1.2 Location of the Project.

A The general location of the Project is shown on the City Drawing No. G005

1.3 Status of the Project Area and Rights-of-Way.

A City, at its expense, will provide all rights-of-way or permits, or both, covering the crossing of private property and public and private rights-of-way necessary for the permanent Work; provided, however, Contractor shall, at its expense, obtain any bonds or insurance policies or pay any fees and enter into any agreements required by a controlling authority, e.g., Caltrans or Southern Pacific Railroad Company, before Contractor enters upon any property or right-of-way under the jurisdiction of any such controlling authority for the purpose of performing Work.

B City has acquired or is negotiating to acquire any rights-of-way, or both, necessary for the permanent Work.

C If such permits are required, all operations of Contractor shall conform to the restrictions, regulations, and requirements set forth in said permits, copies of which will be included in the Contract Documents.

D Contractor may be required, as a condition for receiving final payment, to obtain, and provide City’s Representative with copies of, executed damage releases from the owners of public and private property whose property has been damaged by the Work. The damage releases will be on a form provided by City.

E Contractor shall, also, as a condition for receiving final payment, obtain, and provide City’s Representative with copies of, executed damage releases from the owners of certain public and private property or areas which have been crossed by the Work or otherwise affected by the Work. The damage releases will be on a form provided by City.

1.4 Site Data.

A The data provided herein is for the information of Contractor and is subject to all limitations and conditions set forth in the Contract Documents.

1.5 Pre-Purchased or Pre-Negotiated Material.
[NOT USED.]

1.6 Designation of City’s Representative.

Page 276 of 557 ends

38077.00180\29080232.10
-109- 00 73 13 – SPECIAL CONDITIONS
A Unless otherwise modified by City, City’s Representative shall be Lyhak Eam, P.E., Acting Public Works Division Manager - Engineering.

1.7 Project Retention
In accordance with Public Contract Code § 7201, City will withhold 5% of each progress payment as retention on the Project.

1.8 Liquidated Damages Due to Contractor Delay.

A Time is of the essence. Should Contractor fail to complete all or any part of the Work within the time specified in the Contract Documents, City will suffer damage, the amount of which is difficult, if not impossible, to ascertain and, pursuant to the authority of Government Code section 53069.85, City shall therefore be entitled to $3,600 per Day as liquidated damages for each Day or part thereof that actual completion extends beyond the time specified.

B Liquidated damages may be deducted from progress payments due to Contractor, Project retention or may be collected directly from Contractor, or from Contractor's surety. These provisions for liquidated damages shall not prevent City, in case of Contractor's default, from terminating the Contractor.

1.9 Utility Outages – Notices to Residents.

A Should Contractor’s operation require interruption of any utility service connection, contractor shall notify City at least twenty-one (21) days prior to the scheduled outage. Contractor is responsible to notify all impacted residents by mail on a form provided by City. The outage notification shall be mailed out to residents and businesses fourteen (14) days, seven (7) days, and 24-hours prior to start of work.

B Contractor shall be responsible for providing, at its cost, any temporary utility or facilities necessitated by the utility outage.
a. The supply of portable water to Executive Inn Hotel, located at 95 Dempsey Rd, Milpitas, CA 95035, shall not be interrupted. The Contractor shall be responsible for providing a temporary water connection to ensure the business can continue operations during any water shut off. This will require high-lining the water supply from the nearest fire hydrant to the existing water and fire backflow of the hotel. The contractor will communicate with the City and business owner(s) prior to implementing the high-lining.

1.10 Schedule Constraints.

A The following table shows the City’s recommended water valves replacement sequence of work. The Contractor is encouraged to propose changes or modification to the sequence of work to improve the construction workflow and minimize the interruption to the public. The City may consider these changes or modifications; however, it is at the discretion of the City to approve such changes or modifications. See Appendix A for City Water Valve Location Map

Page 277 of 557 ends

38077.00180\29080232.10
-110- 00 73 13 – SPECIAL CONDITIONS
Order of Work Valve Location No. Drawing Sheet No.
1 3 C103 & C104
2 1 C101
3 2 C102
4 4 C105
5 5 C106
6* 6 C107
7* 7 C108
* T. Marzetti Company, located at 876 Yosemite Drive, requires a 24-hour water supply from Monday to Friday. As the facility does not have its own emergency water supply, water shut-offs to T. Marzetti Company may only occur from Saturday at 9:00 AM to Sunday at 8:00 PM. Other work items that do not impact the water supply may be performed during normal working hours.

B City has considered these Schedule Constraints when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Constraints.

1.11 Safety Programs.

A In addition to all other safety requirements of the Contract Documents, Contractor must comply with Cal/OSHA requirements at all times during the completion of the Work. The Contractor shall practice safe exposure and removal of buried asbestos cement pipe (ACP) where encountered. Follow Technical Specification Section 02 82 33 for procedures.

B City has considered these Safety Programs when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Safety Programs.

1.12 Coordination with Other Contractors.

A In addition to the Contract requirements relating to other work at the Site, City anticipates that other contractors will be performing work within the Site.

Specifically:

1. City Public Works Staff

2. Business owners

Page 278 of 557 ends

38077.00180\29080232.10
-111- 00 73 13 – SPECIAL CONDITIONS
B City has considered these other contractors when determining the Contract Times and no additional time or compensation will be added to the Contract due to these other contractors.

END OF SPECIAL CONDITIONS

Page 279 of 557 ends

38077.00180\29080232.10
-112- 01 00 00 – GENERAL REQUIREMENTS
01 00 00 – GENERAL REQUIREMENTS
PART 1 GENERAL

1.1 DESCRIPTION
A. The Scope of the project includes, but not limited to, demolition, removing and replacing existing gate valves, installing approximately 160 linear feet of 12-inch PVC water main and one (1) new fire hydrant, providing traffic control, dewatering, high-lining, replacing curb and gutter, medians, asphalt paving, restriping and relandscaping.

PART 2 (NOT USED)
PART 3 EXECUTION

3.1 LAYOUT OF WORK AND QUANTITY SURVEYS
A. General. The Contractor shall utilize a properly licensed surveyor to perform all layout surveys required for the control and completion of the Work, and all necessary surveys to compute quantities of Work performed.

City and/or the Engineer of Record has established primary control to be used by the Contractor for establishing lines and grades required for the Work.

Primary control consists of benchmarks and horizontal control points in the vicinity of the Work. A listing and identification of the primary control is provided on the Drawings. Before beginning any layout work or construction activity, the Contractor shall check and verify primary control, and shall advise the City Representative of any discrepancies.

B. Quantity surveys. The Contractor shall perform such surveys and computations as are necessary to determine quantities of Work performed or placed during each progress payment period and shall perform all surveys necessary for the City Representative to determine final quantities of Work in place. The City Representative will determine final quantities based upon the survey data provided by the Contractor, and the design lines and grades. If requested by the City Representative, the Contractor shall provide an electronic copy of data used for quantity computations.

All surveys performed for measurement of final quantities of Work and material shall be subject to approval of City’s Representative. Unless waived by City’s Representative in each specific case, quantity surveys made by the Contractor shall be made in the presence of City’s Representative.

C. Surveying

1. Accuracy. Degree of accuracy shall be an order high enough to satisfy tolerances specified for the Work and the following:

Page 280 of 557 ends

38077.00180\29080232.10
-113- 01 00 00 – GENERAL REQUIREMENTS
(a) Right-of-way and alignment of tangents and curves shall be within

0.1 foot.
(b) Structure points shall be set within 0.01 foot, except where operational function of the special features or installation of metalwork and equipment require closer tolerances. When formwork has been placed and is ready for concrete, the Contractor shall check the formwork for conformance with the drawings and to ensure that the forms are sufficiently within the tolerance limits for the completed work.
(c) Cross-section points shall be located within 0.1 foot, horizontally and vertically.
(d) Aerial Mapping shall meet National Mapping Standards for 2- foot contour intervals.

D. Records. Survey data shall be recorded in accordance with recognized professional surveying standards. Original field notes, computations, and other surveying data shall be recorded on electronic data collectors or in standard field books and must be of sufficient quality to enable the Contractor to prepare accurate record drawings as required by the Contract Documents.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required for surveys for the layout of work and quantity surveys shall be included in the Schedule of Pay Items for items of work requiring the surveys. No additional compensation shall be made to the Contractor for this Work.

3.2 SCHEDULE
A. Estimated Schedule. Within 21 Days after the issuance of the Notice of Award, Contractor shall prepare a Project schedule and shall submit this to the Engineer for Approval. The receipt or Approval of any schedules by the Engineer or the City shall not in any way relieve the Contractor of its obligations under the Contract Documents. The Contractor is fully responsible to determine and provide for any and all staffing and resources at levels which allow for good quality and timely completion of the Project. Contractor’s failure to incorporate all elements of Work required for the performance of the Contract or any inaccuracy in the schedule shall not excuse the Contractor from performing all Work required for a completed Project within the specified Contract time period. If the required schedule is not received by the time the first payment under the Contract is due, Contractor shall not be paid until the schedule is received, reviewed and accepted by the Engineer.

B. Schedule Contents. The schedule shall indicate the beginning and completion dates of all phases of construction; critical path for all critical, sequential time related activities; and “float time” for all “slack” or “gaps” in the non-critical activities.

The schedule shall clearly identify all staffing and other resources which in the Contractor’s judgment are needed to complete the Project within the time specified for completion. The overall Project Schedule duration shall be within the Contract time.

Page 281 of 557 ends

38077.00180\29080232.10
-114- 01 00 00 – GENERAL REQUIREMENTS
C. Weather Allowance. The schedule shall allow adequate time for inclement weather.

D. Schedule Updates. Contractor shall continuously update its construction schedule. Contractor shall submit an updated and accurate construction schedule to the Engineer monthly when requested to do so by Engineer. Contractor shall also submit schedules showing a three-week detailed look-ahead at bi-weekly meetings conducted with the City. The Engineer may withhold progress payments or other amounts due under the Contract Documents if Contractor fails to submit an updated and accurate construction schedule.

E. See Section 01 32 13 for additional information.

3.3 TEMPORARY FIELD OFFICE
A. Utility Services. Contractor, at its expense, shall arrange for, develop and maintain all utilities, including but not limited to water, electric power, sewage disposal, and telephone communications, at the Site to meet the requirements of the Work.

B. Sanitation. The Contractor shall provide sanitary facilities for all persons working on the project. These facilities shall be kept clean and shall not be unsightly or produce odors.

C. See Section 01 50 00 for additional information.

3.4 PROJECT CONSTRUCTION SIGN
A. The Contractor shall furnish, install, and maintain of three (3) Project Construction Signs specified at the locations shown on the plans or field determination with the City. The signs shall be completely removed at the conclusion of the project, post holes shall be filled, and any other damage shall be restored to pre-project conditions as directed by the Engineer.

B. The minimum size of each sign shall be 36” x 60” with black lettering on a white background with the following information, and shall be mounted on two 4 x 4 posts painted black:

1. Firm responsible for project construction with a 24-hour telephone number.

Letter size: 2 inches high.

2. Purpose of project: (nature of work) Letter size: 4 inches

3. Limits of work

4. Start Date and Completion Date. Letter Size: 2 inches

5. City of Milpitas Logo in the upper left corner (12-inch round) as provided by the City
C. All excavations required to install construction area signs shall be performed by hand methods without the use of power equipment. Power equipment may be

Page 282 of 557 ends

38077.00180\29080232.10
-115- 01 00 00 – GENERAL REQUIREMENTS
used if it is determined there are no utility facilities in the area of the proposed signpost holes. Contact Underground Service Alert (USA) 1-800-227-2600 two (2) days prior to any excavation for posts.

D. The signs shall be located in areas visible to the public or as directed by the Engineer. Locations shall be safe for pedestrians and vehicles. The signs shall be maintained by the Contractor in a like new condition, and the information on the signs shall be updated and kept current by the Contractor.

E. Cost. Full compensation for the Work involved in the project construction sign as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made, therefore.

F. See Section 01 50 00 for additional information.

3.5 PROTECTION OF WORK AND PROPERTY
A. All traffic detector loops, fences, walls, culverts, monuments, or other obstructions (except property line monuments within five (5) feet of the centerline of the mains) which are removed, damaged, or destroyed in the course of the Work, shall be replaced or repaired to the original condition at no additional cost to City.

Contractor shall be responsible for the cost to repair, replace, relocate, and replacement of utilities whether or not those obstructions have been shown on the Plans, unless otherwise stated herein. It is then the Contractor’s responsibility to employ at its expense a Licensed Land Surveyor to restore all property line monuments located more than five (5) feet from the centerline of the mains, which are destroyed or obliterated. Property line monuments located within five (5) feet of the centerline of the mains will be replaced by the City at no expense to the Contractor, provided the City is notified at least 48 hours before the property line monuments are damaged.

B. Contractor shall provide such heat, covering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.

C. Contractor shall take adequate precautions to protect existing sidewalks, curbs, pavements, utilities, and other adjoining property and structures, and to avoid damage thereto, and Contractor shall repair any damage thereto caused by the Work operations. Contractor shall:

1. Enclose the working area with a substantial barricade and arrange work to cause minimum amount of inconvenience and danger to the public.

2. Provide substantial barricades around any shrubs or trees indicated to be preserved.

3. Deliver materials to the Project site over a route designated by the Engineer.

4. Provide any and all dust control required and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, the

Page 283 of 557 ends

38077.00180\29080232.10
-116- 01 00 00 – GENERAL REQUIREMENTS
City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.

5. Confine Contractor’s apparatus, the storage of materials, and the operations of its workers to limits required by law, ordinances, permits, or directions of the Engineer. Contractor shall not unreasonably encumber the Project site with its materials.

6. Take care to prevent disturbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by a civil engineer or land surveyor acceptable to the City, at no cost to the City.

7. Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to the City.

8. Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way.

9. At the completion of work each day, leave the Project site in a clean, safe condition.

10. Comply with any approved stage construction and traffic control plans.

Access to residences and businesses shall be maintained at all times, unless otherwise permitted in writing by the City.

11. Cover and or protect work and project site as may be required to prevent or mitigate schedule delay and to allow work to proceed during wet weather or wet conditions.

D. These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefore.

E. Should damage to persons or property occur as a result of the Work, Contractor shall be responsible for proper investigation, documentation, including video or photography, to adequately memorialize and make a record of what transpired.

The City shall be entitled to inspect and copy any such documentation, video, or photographs.

3.6 SITE CONDITIONS SURVEYS
A. Work Included.

Contractor shall conduct thorough pre-construction and post-construction site condition surveys of the entire project area. Site Conditions surveys shall include written documentation of the conditions found, as well as photographs and video

Page 284 of 557 ends

38077.00180\29080232.10
-117- 01 00 00 – GENERAL REQUIREMENTS
recordings of the area within at least 80 feet of any construction area and staging area. The written notes, photographs, and video shall be suitable for forensic purposes to resolve any damage claims that may arise as a result of construction.

B. Submittals.

1. Written documentation of site condition survey at pre-construction and post-construction.

2. Photographs as described herein of pre-construction and post-construction conditions.

3. Video recordings as described herein of pre-construction and postconstruction conditions.

4. Submittals shall be made within three days of the surveys. All postconstruction data shall be submitted prior to the final project inspection.

C. Site Condition Written Documentation.

Written documentation shall include the time, date, and conditions under which the site survey was made. The documentation shall note the condition of structures, pavement, sidewalks, utilities, fences, and etc. within the work areas.

D. Photographs & Video Recording.

1. General – Prior to starting Work, Contractor shall provide a video recording of the project site. Contract shall take enough photographs during each site survey to provide a record of conditions existing prior to construction and conditions after construction. Pre-construction video and photographs shall be taken prior to any construction or mobilization of equipment, but not more that one week prior to actual start of work. The pre-construction photographs may be staged at different times to match the progression of the Work.

2. The photographs shall document existing damage to public and private facilities, both prior to and after construction. Conditions to be documented include, but are not limited to: sidewalk cracks, broken curbs, separated property walls, improvements within public rights-of-way, access roads used, utility covers and markings, signs, pavement striping, pavement, unique or unusual conditions, adjacent driveways, landscaping, survey markers, and any feature directed by the Engineer. Private property that is adjacent to the public right-of-way shall be documented to the extent visible from the public right-of-way.

3. Photographs shall include items to indicate scale, as needed. In particular, scales or other items shall be laid next to close ups of structural cracks and other damaged areas being recorded. Scaling shall also be used to document elevation differences, as needed.

Page 285 of 557 ends

38077.00180\29080232.10
-118- 01 00 00 – GENERAL REQUIREMENTS

4. One set of color prints and the preconstruction site video shall be submitted. Additional sets shall be available for reviewing in settling any construction disputes. A set of photos shall also be furnished in electronic format. The resolution shall be at least equal to 7 mega-pixels. All photos shall be documented as to time and date taken, photographer, project number, location, and orientation. Documentation shall include a brief description of objects photographed.

E. Video Recording.

1. Video recordings shall document the conditions of the entire area affected by construction, as well as nearby structures and facilities. The general documentation requirements for videos are the same as for photographs.

Video recorders shall accurately and continuously record the time and date.

2. Video recordings shall include an audio portion made simultaneously during the videoing. The audio recording shall describe the location, time, orientation, and objects being recorded. Special commentary shall be provided for unusual conditions or damage noted.

3. Video equipment shall be capable of producing high resolution images and shall have zoom capabilities.

4. Video recordings shall provide an overall picture of the sites and shall provide detailed images of damaged areas. Video shall extend to the maximum height of structures.

5. The Engineer shall have the right to reject any audio video recordings submitted with unintelligible audio, uncontrolled pan or zoom, or of poor quality. Video recordings shall be repeated when rejected.

6. Video recordings shall be submitted with labels indicating the project, date, recorder, and other pertinent information. Recordings shall be submitted on standard DVDs in a standard format.

F. Timing.

Contractor shall provide written notice of the time scheduled for the site conditions survey and the place it is to begin. Contractor shall obtain the Engineer’s concurrence prior to beginning the condition survey. The Engineer reserves the right to cancel the survey due to weather conditions or other problems. Videoing shall be done during times of good visibility and no videoing or photography shall be done during periods of visible precipitation or when standing water obscures pavement. Contractor shall provide the Engineer with an opportunity to have a representative present when taking the photos and provide guidance during photographing.

G. Site Surveyor.

Page 286 of 557 ends

38077.00180\29080232.10
-119- 01 00 00 – GENERAL REQUIREMENTS
The site condition surveyor(s) shall be experienced in construction and potential damage concerns. The site condition surveyor(s) shall be familiar with the photography and video equipment being used.

H. Field Quality Control.

Prior to submitting videos and photographs, the Contractor shall spot check the photos and videos in the field to insure they accurately reflect the actual conditions and to insure they are correctly labeled.

I. Soils Compaction Testing.

1. All soils compaction testing will be done by a licensed geotechnical engineer furnished by the City. Soils compaction testing will be done for all footings and foundations prior to placement of rebar or concrete.

2. For pipeline construction, soil compaction testing will be done at 100-foot intervals or as ordered by the project soils/geotechnical report at the bottom of the trench prior to placement of pipe bedding; at the top of the pipe bedding above the pipe; every two vertical feet of trench backfill or as otherwise ordered by the project soils/geotechnical report; at the top of the trench backfill, which should be the bottom of the pavement section; and at the top of the aggregate base prior to pavement construction.

3.7 SUBMITTAL REQUIREMENTS FOR MANUALS AND RECORD DRAWINGS A. General. The Contractor shall furnish all materials and perform all Work required for furnishing submittals to City in accordance with Contract Documents. The Contractor shall submit Project Record Drawings, Technical Manual, Spare Parts, and other required items within 5 days following completion of project construction, and prior to Contractors request for Project Acceptance.

B. Technical Manuals.

1. The Contractor shall submit technical operation and maintenance information for each item of mechanical, electrical and instrumentation equipment in an organized manner in the Technical Manual. It shall be written so that it can be used and understood by City’s operation and maintenance staff.

2. The Technical Manual shall be subdivided first by specification section number; second, by equipment item; and last, by "Category." The Contractor shall furnish to City four (4) identical Technical Manuals. Each set shall consist of one or more volumes, each of which shall be bound in a standard binder.

C. Spare Parts List - The Contractor shall furnish to City six (6) identical sets of spare parts information for all mechanical, electrical, and instrumentation equipment.

The spare parts list shall include the current list price of each spare part. The spare parts list shall include those spare parts which each manufacturer recommends be maintained by City in inventory. Each manufacturer or supplier shall indicate

Page 287 of 557 ends

38077.00180\29080232.10
-120- 01 00 00 – GENERAL REQUIREMENTS
the name, address, and telephone number of its nearest outlet of spare parts to assist City in ordering. The Contractor shall cross-reference all spare parts lists to the equipment numbers designated in the Contract Documents. The spare parts lists shall be bound in standard size, 3-ring binder.

D. Record Drawings

1. The Contractor shall maintain one record set of Drawings at the Site. On these, it shall mark all Project conditions, locations, configurations, and any other changes or deviations which may vary from the information represented in the original Contract Documents, including buried or concealed construction and utility features which are revealed during the course of construction. Special attention shall be given to recording the horizontal and vertical location of all buried utilities that differ from the locations indicated, or which were not indicated on the Contract Drawings.

Said record drawings shall be supplemented by any detailed sketches as necessary or directed to fully indicate the Work as actually constructed.

These master record drawings of the as-built conditions, including all revisions made necessary by Addenda and Change Orders shall be maintained up-to-date during the progress of the Project. Red ink shall be used for alterations and notes. Notes shall identify relevant Change Orders by number and date.

2. For all Projects involving the installation of any pipeline, Contractor shall survey and record the top of the pipe at a minimum of every 100 linear feet, and at each bend, recording both the horizontal and vertical locations.

3. Record drawings shall be accessible to City’s Representative at all times during the construction period. The record drawings shall be kept up to date and will be checked by the City prior to each progress payment.

Failure on the Contractor’s part to keep record drawings current could result in withholding partial payment.

4. Upon Completion of the Project and as a condition of final acceptance, the Contractor shall finalize and deliver a complete set of Record Drawings to City’s Representative. The information submitted by the Contractor will be assumed to be correct, and the Contractor shall be responsible for, and liable to City, for the accuracy of such information, and for any errors or omissions which may or may not appear on the Record Drawings.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete the Manuals and Record Drawings shall be included in Contractor’s bid and distributed in the Schedule of Pay. No additional compensation shall be made to the Contractor for this Work.

3.8 MATERIALS
A. Materials to be Furnished by the Contractor

1. Inspection of Materials. Materials furnished by the Contractor which will become a part of the Project shall be subject to inspection at any one or

Page 288 of 557 ends

38077.00180\29080232.10
-121- 01 00 00 – GENERAL REQUIREMENTS
more of the following locations, as determined by City’s Representative: at the place of production or manufacture, at the shipping point, or at the site of the Work. To allow sufficient time to provide for inspection, the Contractor shall submit to City’s Representative, at the time of issuance, copies of purchase orders or other written instrument confirming procurement of the materials, including drawings and other pertinent information, covering materials on which inspection will be made.

2. No later than fourteen (14) Days prior to manufacture of material, Contractor shall inform City’s Representative, in writing, the date the material is to be manufactured.

3. Contractors Obligations. The inspection of materials at any of the locations specified above or the waiving of the inspection thereof shall not impact whether the materials and equipment conform to the Contract Documents.

Contractor will not be relieved from furnishing materials meeting the requirements of the Contract Documents due to City’s inspection or lack of inspection of the equipment or materials. Acceptance of any materials will be made only after materials are installed in the Project.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to accommodate City’s testing efforts, including any travel required by Contractor’s forces, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items related to the materials requiring testing. No additional compensation shall be made to the Contractor for this Work.

3.9 LOCAL CONDITIONS AND REQUIREMENTS
A. Access to Work and Haul Routes

1. General. All work on the rights-of-way necessary for access to the Site shall be performed by the Contractor. Contractors anticipated Haul Routes shall be in compliance with the City's approved Truck Routes available from the Engineer.

2. Access, Damage, Restoration. The Contractor shall make his own investigation of the condition of available public or private roads and of clearances, restrictions, bridge-load limits, permit or bond requirements, and other limitations that affect or may affect transportation and ingress or egress at the Site.

3. The Contractor shall maintain and repair any damage arising out of Contractor’s operations to all roads used during construction of the Project, and upon completion of all Work, but prior to final acceptance, the roads shall be restored to their original condition. Prior to using any road for access to the Site, the Contractor shall conduct a photograph and/or video survey of the roadway with a copy submitted to City’s Representative.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be

Page 289 of 557 ends

38077.00180\29080232.10
-122- 01 00 00 – GENERAL REQUIREMENTS
included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

B. Power. Contractor shall provide at its own expense all necessary power required for operations under the contract. The Contractor shall provide and maintain in good order such modern equipment and installations as shall be adequate in the opinion of the Engineer to perform in a safe and satisfactory manner the Work required by the contract.

C. Construction Water.

1. Construction water shall not be used for purposes other than those required to satisfactorily complete the contract.

2. Construction recycled water will be made available to the contractor from one of three fill locations within the city limits. If there is a need for construction recycled water during construction, the contractor shall apply for a city construction recycled water meter at the city hall finance counter prior to the beginning of work. A security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. if the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

3. Construction potable water will only be made available to the contractor if it can be demonstrated that recycled water cannot be used for the construction activities. potable water will be made available from existing city fire hydrant(s) nearest the proposed construction site as approved by the engineer, or by such other means as may be expressly approved in writing by the engineer. If there is a need for water during construction, the contractor shall apply for a city construction water meter at the city hall finance counter prior to the beginning of work. a security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. If the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

4. All required water, all work and materials required for obtaining, pumping, transporting and applying and otherwise disposing of said water shall be in an approved manner and shall be performed by, and at the expense of the contractor and no extra or separate compensation will be made thereof.

D. Operation of Existing Water Facilities

1. The Contractor shall not operate any of the existing water systems, including pumps, motors, valves, and hydrants, but shall contact the City two (2) working days in advance with a list and location of the water system facilities that will require operating, opening, stopping, or closure by the City.

Page 290 of 557 ends

38077.00180\29080232.10
-123- 01 00 00 – GENERAL REQUIREMENTS

2. At the option of the Engineer, the Contractor may be permitted to operate valves for the purpose of making connections to existing mains. The City will perform all notification to existing customers regarding temporary loss of service.

3. Contractor shall submit a request on City’s standard form for any shut-down of existing water facilities.

E. Construction at Existing Utilities

1. General. Where the Work to be performed crosses or otherwise interferes with water, sewer, gas, or oil pipelines; buried cable; or other public or private utilities, the Contractor shall perform construction in such a manner so that no damage will result to either public or private utilities. It shall be the responsibility of the Contractor to determine the actual locations of, and make accommodates to maintain, all utilities.

2. Permission, Notice and Liability. Before any utility is taken out of service, permission shall be obtained by the Contractor from the owner. The owner, any impacted resident or business owner and the City Representative will be advised of the nature and duration of the utility outage as well as the Contractor’s plan for providing temporary utilities if required by the owner.

The Contractor shall be liable for all damage which may result from its failure to maintain utilities during the progress of the Work, and the Contractor shall indemnify City as required by the Contract Documents from all claims arising out of or connected with damage to utilities encountered during construction; damages resulting from disruption of service; and injury to persons or damage to property resulting from the negligent, accidental, or intentional breaching of utilities.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

F. Traffic Control

1. General. Contractor shall abide by traffic control plans approved by the City.

2. Protections. Roads subject to interference by the Work shall be kept open or suitable temporary passages through the Work shall be provided and maintained by the Contractor. The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient flasher lights, flag persons, danger signals, and signs, and shall take all necessary precautions for the protection of the Work and the safety of the public. No construction work along public or private roads may proceed until the Contractor has proper barricades, flasher lights, flag persons, signals, and signs in place at the construction site.

Page 291 of 557 ends

38077.00180\29080232.10
-124- 01 00 00 – GENERAL REQUIREMENTS

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

4. Valve #1, #2, and #3 are located within Caltrans right-of-way. The Caltrans Encroachment Permit with Traffic Control Plan (TCP) has been approved and is attached in Appendix B. The Contractor shall submit a 'Contractor Authorization Form' to Caltrans and obtain a permit rider to the City's Encroachment Permit. The Contractor is required to prepare and submit a TCP for the remaining six valve replacement sites. The TCP must be stamped and signed by licensed professional engineer (PE) or licensed traffic engineer (TE). The City must approve the TCP prior to any traffic related work.

5. See Section 01 55 26 for additional information.

G. Cleaning Up

1. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equipment. Contractor shall not store debris under, in, or about the premises. Contractor shall also clean all asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment, including all USA markings. The use of water, resulting in mud on streets, will not be permitted as substitute for sweeping or other methods. Dust control may require having a water truck onsite for the duration of the project, and/or use of temporary hoses and pipelines to convey water.

2. Contractor shall fully clean up the site at the completion of the Work. If the Contractor fails to immediately clean up at the completion of the Work, the City may do so and the cost of such clean up shall be charged back to the Contractor.

3.10 ENVIRONMENTAL QUALITY PROTECTION
A. Environmental Conditions

1. Contractor must comply with all applicable environmental laws, Project conditions, and constraints.

2. City has considered these Environmental Conditions when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Conditions.

B. Landscape and Vegetation Preservation

1. General. The Contractor shall exercise care to preserve the natural landscape and vegetation and shall conduct operations so as to prevent unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the Work.

Page 292 of 557 ends

38077.00180\29080232.10
-125- 01 00 00 – GENERAL REQUIREMENTS

2. Damage and Restoration. Movement of crews and equipment within the rights-of-way and over routes provided for access to the Work shall be performed in a manner to prevent damage to property. When no longer required, construction roads shall be restored to original contours.

3. Upon completion of the Work, and following removal of construction facilities and required cleanup, land used for construction purposes and not required for the completed installation shall be scarified and regraded, as required, so that all surfaces are left in a condition that will facilitate natural revegetation, provide for proper drainage, and prevent erosion.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

C. Protected Species

1. General. If, in the performance of the Work, evidence of the possible occurrence of any State or Federally listed threatened or endangered plant or animal is discovered, the Contractor shall notify the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the endangered plant or animal.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Any City directed changes to the Work as a result of a siting will be pursuant to the Contract Documents.

3. False Siting. Any costs or delays incurred by City or the Contractor due to unreasonable or false notification of an endangered plant or animal will be borne by the Contractor.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

D. Preservation of Historical and Archeological Resources

1. General. If, in the performance of the Work, Contractor should unearth cultural resources (for example, human remains, animal bones, stone tools, artifacts and/or midden deposits) through excavation, grading, watering or other means, the Contractor notify the

Page 293 of 557 ends

38077.00180\29080232.10
-126- 01 00 00 – GENERAL REQUIREMENTS
Construction/Archeological Monitor and/or the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to the Construction/Archeological Monitor and/or City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the cultural resource.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or re-sequence and/or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Should the presence of cultural resources be confirmed, the Contractor will assist the City Representative and the Construction/Archeological Monitor in the preparation and implementation of a data recovery plan. The Contractor shall provide such cooperation and assistance as may be necessary to preserve the cultural resources for removal or other disposition. Any City directed changes to the Work as a result of the cultural resource will be pursuant to the Contract Documents.

3. Contractor’s Liability. Should Contractor, without permission, injure, destroy, excavate, appropriate, or remove any cultural resource on or adjacent to the Site, it will be subject to disciplinary action, arrest and penalty under applicable law. The Contractor shall be principally responsible for all costs of mitigation and/or restoration of cultural resources related to the unauthorized actions identified above. Contractor shall be required to pay for unauthorized damage and mitigation costs to cultural resources (historical and archeological resources) as a result of unauthorized activities that damage cultural resources and shall indemnify City pursuant to the Contract Documents.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

E. Dust and Pollution Control

1. Contractor shall provide all necessary material, equipment and labor to prevent and control the emission of dust and any other potential pollutant on site. Contractor shall remove construction caused debris from streets and sidewalks as directed by the Engineer.

2. Contractor shall not discharge into the atmosphere from any source smoke, dust or other air contaminants in violation of the law, rules, and regulations of the governing agency.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph,

Page 294 of 557 ends

38077.00180\29080232.10
-127- 01 00 00 – GENERAL REQUIREMENTS
shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

F. Dewatering

1. Due to the condition of the existing valves, it is not feasible to completely isolate the water system during construction, leading to potential water leakage from the water main. The Contractor shall be responsible for dewatering the trench as necessary to complete the work as specified in the Contract Documents, at no additional cost to the City. Refer to Technical Specification Section 31 23 19 for detailed procedures.

2. The Contractor is responsible for procuring a Baker Tank to store dewatering water. The stored water shall be discharged to the nearest sewer manhole via gravity flow. The Contractor must continuously monitor the discharge to prevent any sewer backup or overflow resulting from this activity. Contractor to submit Baker Tank product for City’s approval.

G. Asbestos Containing Materials

1. The Contractor shall practice safe exposure and removal of buried asbestos cement pipe (ACP) where encountered. Follow Technical Specification Section 02 82 33 for procedures.

H. Management of Storm, Surface and Other Waters

1. Storm water, surface water, groundwater, and nuisance, or other waters may be encountered at various times during construction of the Project.

Federal and State laws require the City and its contractors to manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ, the Federal Clean Water Act, and the California Porter Cologne Water Quality Control Act.

Contractor acknowledges that it has investigated the risk arising from such waters in conjunction with the Project, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

2. The Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the City’s ordinances regulating discharges of storm water; the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.); the California Porter-Cologne Water Quality Control Act (Water Code § 13000 et seq.); and any and all regulations, policies, or permits issued pursuant to any such authority. These include, but are not limited to the San Francisco Bay Regional Water Quality Control Board Order No. R2-2015- 0049 (NPDES Permit No. CAS 612008), and State Water Resources Control Board Order No. 2010-0014-DWQ, Order No. 2009-0009-DWQ, and Order No. 2012-0006-DWQ, and any amendment or renewal thereof (“Construction General Permit”). Contractor must perform all construction

Page 295 of 557 ends

38077.00180\29080232.10
-128- 01 00 00 – GENERAL REQUIREMENTS
operations in such a manner as to comply, and ensure all subcontractors to comply, with all applicable Federal, State, and local laws, orders, and regulations concerning the control and abatement of water pollution; and all terms and conditions of any applicable permits issued for the Project. In the event there is a conflict between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.

3. For those Work sites where construction activity results in the disturbance of less than one acre of total land area and/or do not need coverage under the Construction General Permit, the Contractor shall be responsible for preparing and implementing construction industry best management practices to eliminate or reduce the discharge of pollutants from construction sites, such as the best management practices set forth in the CASQA Construction BMP Handbook.

4. In addition to compliance with the Permit, Contractor shall comply with the lawful requirements of any applicable municipality, district, drainage district, flood control district, and other local agencies regarding discharges of storm water, surface water, groundwater or other nuisance waters off of the Project site.

5. Contractor violations.
(a) Failure to implement the SWPPP or otherwise comply with the Construction General Permit or local state and federal laws is a violation of this Contract. Notwithstanding any other indemnity contained in this Agreement, Contractor agrees to indemnify, defend – with counsel acceptable to the City – and hold harmless the City, its officials, officers, agents, employees and authorized volunteers from and against any and all claims, demands, losses or liabilities of any kind or nature which the City, its officials, officers, agents, employees and authorized volunteers may sustain or incur for noncompliance with the laws, regulations, and ordinances listed above, arising out of or in connection with the Work, except for liability resulting from the sole established negligence, willful misconduct or active negligence of the City, its officials, officers, agents, employees or authorized volunteers.
(b) City reserves the right to defend any enforcement action or civil action brought against the City for Contractor’s failure to comply with any applicable water quality law, regulation, or policy.

Contractor hereby agrees to be bound by, and to reimburse the City for the costs associated with, any enforcement action and/or settlement reached between the City and any relevant enforcement entity.
(c) City may seek damages from Contractor for delay in completing the Contract in accordance with the Contract Documents, caused by Contractor’s failure to comply with the the laws, regulations and policies described in this Article, or any other relevant water quality law, regulation, order, or policy.

Page 296 of 557 ends

38077.00180\29080232.10
-129- 01 00 00 – GENERAL REQUIREMENTS
(d) If noncompliance with any relevant law, regulation or permit, order, or policy occurs, the Contractor shall report this to the City Representative immediately, with the specific information submitted in writing within 2 Days. Consistent violations of applicable Federal, State, or local laws, orders, regulations, or Water Quality Standards may result in City stopping all site activity until compliance is ensured. The Contractor shall not be entitled to any change in Contract Price or Contract Times, claim for damage, or additional compensation by reason of such a work stoppage. Corrective measures required to bring activities into compliance shall be at the Contractor's expense.

6. Oil storage tanks management.
(a) Storage tank placement. All oil or other petroleum product (hereinafter referred to collectively as oil) storage tanks shall be placed at least 20 feet from streams, flowing or dry watercourses, lakes, wetlands, reservoirs, and any other water source. (b) Storage area dikes. Storage areas shall be diked at least 12 inches high or graded and sloped to permit safe containment of leaks and spills equal to the capacity of all tanks and/or containers located within each area, plus a sufficient amount of freeboard to contain the 25-year rainstorm.
(c) Diked area barriers. Diked areas shall have an impermeable barrier at least 10 mils thick. Areas used for refueling operations shall have an impermeable liner at least 10 mils thick buried under 2 to 4 inches of soil.
(d) Spill Prevention Control and Countermeasure Plan (SPCC). Where the location of a construction site is such that oil from an accidental spillage could reasonably be expected to enter into or upon the navigable waters of the United States or adjoining shorelines, and the aggregate storage of oil at the site is over 1,320 gallons or a single container has a capacity in excess of 660 gallons, the Contractor shall prepare an SPCC Plan. The Contractor shall submit the SPCC Plan to the Engineer at least 30 days prior to delivery or storage of oil at the site. The Plan must have been reviewed and certified by a registered professional engineer in accordance with 40 C.F.R., part 112

7. Underground tank prohibition. The Contractor shall not use underground storage tanks.

8. Construction safety standards. The Contractor shall comply with the sanitation and potable water requirements of Section 7 of United States Bureau of Reclamation's publication “Reclamation Safety And Health Standards.”

9. Other Permits.

Page 297 of 557 ends

38077.00180\29080232.10
-130- 01 00 00 – GENERAL REQUIREMENTS
(a) Other permits applicable to the Project are listed in the Special Conditions. The Contractor shall obtain all other necessary licenses and permits.
(b) Monitoring. The Contractor is required to conduct monitoring in order to meet the requirements of the permits, which may include sampling, testing and inspections.
(c) Recordkeeping. The Contractor shall retain all records and data required by the permits for the time specified in the contract.

10. Cost. Except as specified herein, the cost of complying with this section shall be included in the Schedule of Pay Items for work which necessitate the water pollution prevention measures required by this paragraph.

END OF GENERAL REQUIREMENTS

Page 298 of 557 ends

38077.00180\29080232.10
-131- 01 20 00 Measurement and payments
01 20 00 MEASUREMENT AND PAYMENTS
PART 1 – GENERAL

1.1 SUMMARY
A. This section describes requirements and procedures for determining amount of work done and for obtaining payment for work done.

1.2 REFERENCES
A. California Public Contract Code

1.3 SCOPE OF WORK
A. Work under Contract Documents, or under any bid item, allowance or alternate, or Change Order shall include all labor, materials, transport, handling, storage, supervision, administration, and all other incidental work necessary for the satisfactory completion of Work, whether or not expressly specified or shown.

1.4 DETERMINATION OF QUANTITIES
A. Quantity of work to be paid for under any item for which a unit price is fixed in Contract Documents shall be the number, as determined by City, of units of work satisfactorily completed in-place, and suitable for its intended purpose free of defects or poor workmanship in accordance with Contract Documents or as directed by City. Unless otherwise provided, determination of number of units of work so completed will be based, so far as practicable, on actual measurement or count within prescribed or ordered limits, and no payment will be made for work done outside of limits. Measurements and computations will be made by methods as City may consider appropriate for class of work measured. Contractor shall immediately inform City of any disputes regarding quantity measurements and shall immediately supply City with any documentation supporting the disputed measurements.

B. Before ordering any materials or doing any work, the Contractor shall verify all measurements, dimensions, elevations and quantities. No extra charge or compensation over and above payment for the actual quantities of the various items of work at the respective bid prices therefore will be allowed on account of difference between actual measurements, dimensions, elevations and quantities, and those indicated on the drawings, or in the specifications, and any difference therein shall be submitted to the City for consideration before proceeding with the work.

1.5 SCOPE OF PAYMENT
A. Payment to Contractor at the unit price or other price fixed in the contract for Work as described in Paragraph 1.3 above shall be full compensation for completing, in

Page 299 of 557 ends

38077.00180\29080232.10
-132- 01 20 00 Measurement and payments
accordance with Contract Documents, all work required under the item or under Contract Documents, and for all expense incurred by Contractor for any purpose in connection with the performance and completion of said work, including all incidental work necessary for completion of the Work.

B. Unless Contract Documents expressly provide otherwise, the Contract Sum shall be deemed to include:

1. Any and all costs arising from any unforeseen difficulties, which may be encountered during, and all risks of any description connected with, prosecution of Work, bid item or unit price item, respectively, until acceptance by City;

2. All expenses incurred due to suspension, or discontinuance of Work, bid item or unit price item, respectively, as provided in Contract Documents;

3. Inflation and/or Escalation to allow for cost increases between time of Contract Award and completion of Work, bid item or unit price item, respectively.

C. Whenever it is specified herein that Contractor is to do work or furnish materials of any class for which no price is fixed in Contract Documents, it shall be understood that Contractor is to do such work or furnish such materials without extra charge or allowance or direct payment of any sort, and that cost of doing work or furnishing materials is to be included in price bid, unless it is expressly specified herein, in particular cases, that work or material is to be paid for as extra work.

D. No payment shall be made for materials or equipment not yet incorporated into the Work.

E. Where Contractor requests payment for materials and equipment not incorporated in the Work, Contractor must satisfy the following conditions:

1. The materials and/or equipment shall be delivered and suitably stored at the site or at another local location agreed to in writing, for example, a mutually acceptable warehouse;

2. Full title to the materials and/or equipment shall vest in City at the time of delivery to the site, warehouse or other storage location;

3. Contractor shall obtain a negotiable warehouse receipt, endorsed over to City for materials and/or equipment stored in an off-site warehouse.

No payment shall be made until such endorsed receipts are delivered to City.

4. Stockpiled materials and/or equipment shall be available for City inspection, but City shall have no obligation to inspect them and its inspection or failure to inspect shall not relieve Contractor of any obligations under the Contract Documents. Materials and/or equipment shall be segregated and labeled or tagged to specifically identify these specific Contract Documents;

Page 300 of 557 ends

38077.00180\29080232.10
-133- 01 20 00 Measurement and payments

5. After delivery of materials and/or equipment, if any inherent or acquired defects are discovered, defective materials and/or equipment shall be removed and replaced with suitable materials and/or equipment at Contractor’s expense;

6. At its expense, Contractor shall insure the materials and/or equipment against theft, fire, vandalism, and malicious mischief, as well as any other coverage’s required under the Contract Documents;

7. Contractor’s application for payment shall be accompanied by a bill of sale, invoice or other documentation warranting that City has received the materials and equipment free and clear of all liens and evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect City’s interest therein, all of which must be satisfactory to City. This documentation shall include, but not be limited to, conditional releases of mechanics’ liens and stop notices from all those providing materials and equipment as to which the application for payment relates, as well as unconditional releases of the same from the same as to the previous application for payment for which they have not already been provided.

1.6 BASIS OF PAYMENT
A. Lump Sum: When estimated quantity for specific portion of Work is not indicated and unit is designated as Lump Sum, payment will be based on the approved Schedule of Values of the work under the lump sum, or in the event a Schedule of Values is not required, on the percentage of the lump sum scope satisfactorily completed.

B. City does not expressly, or by implication, agree, warrant, or represent in any manner, that actual amount of Work will correspond with amount shown or estimated and reserves right to increase or decrease amount of any class or portion of Work, to leave out entire Bid Item or Items, or to add work not included in Bid, when in its judgment such change is in best interest of City. No change in Work shall be considered waiver of any other condition of Contract Documents.

No claim shall be made for anticipated profit, for loss of profit, for damages, or for extra payment whatever, except as otherwise expressly provided for in Contract Documents, because of any differences between amount of work actually done and estimated amount as set forth herein, or for elimination of extra Bid Items.

1.7 SCHEDULE OF VALUES AND PROGRESS PAYMENTS
A. If requested by Contractor, progress payments will be made monthly, but not more often than monthly.

B. Schedule of Values:

1. Form to be used: AIA G703 or as approved by the City

2. Within twenty-one (21) calendar days from issuance of Notice of Award and prior to the Contractor’s application for the first progress

Page 301 of 557 ends

38077.00180\29080232.10
-134- 01 20 00 Measurement and payments
payment, Contractor shall submit a Schedule of Values, which is a detailed breakdown of its bid for Work items and/or activities, including coordination responsibilities and project record document responsibilities. Where more than one subcontractor comprises the work of a work item or activity, the Schedule of Values shall show a separate line item for each subcontract. Contractor shall furnish such breakdown by assigning dollar values (cost estimates) to each applicable Progress Schedule network activity, whose cumulative sum equals the total Contract Sum. The format and detail of the breakdown shall be as directed by City to facilitate and clarify future progress payments to Contractor for Work under Contract Documents. Work with lump sum values shall not exceed $10,000 per work item. Work values totaling more than $10,000 per item shall be broken down on a unit basis (e.g., linear foot, square yard, cubic yard, etc.). No line item to exceed one-half of 1% (0.5%) of contract value.

3. Contractor’s overhead, profit, financing, as well as “general conditions costs,” (e.g., site cleanup and maintenance, temporary roads and access, off site access roads, temporary power and lighting, security and the like), shall be prorated through all activities so that the sum of all the Schedule of Values line items equaling Contractor’s total Contract Sum. Insurances and Bonds shall be a separate schedule of value line item.

4. Include in each line item, the amount of Allowances specified in this section. Separately identity each Allowance and Alternate item, provide breakdown where any one item is in excess of one-half of 1% (0.5%) of contract value.

5. City will review the breakdown in conjunction with the approved progress schedule activities to ensure that the dollar amounts of the Schedule of Values are, in fact, fair market cost allocations for the Work items listed. Upon favorable review by City, City will accept this Schedule of Values for use. City shall be the sole judges of fair market cost allocations.

6. Any attempt to unbalance the distribution of overhead, profit, and other fixed costs, or to manipulate the cost breakdown in any way, or to increase the cost of early activities, i.e. “front loading,” will be rejected by City, resulting in a complete reallocation of monies until such distortion is corrected. Repeated attempts of manipulation may result in suspension or termination of the Work or refusal to process progress payments, until such time as the Schedule of Values is acceptable to City.

C. Payment Requests

1. Form to be used: AIA G702 and G703.

2. For each item, provide a column for listing each of the following:
a. Item Number.

Page 302 of 557 ends

38077.00180\29080232.10
-135- 01 20 00 Measurement and payments
b. Description of work.
c. Scheduled Values.
d. Previous Applications.
e. Work in Place and Stored Materials under this Application. f. Authorized Change Orders.
g. Total Completed and Stored to Date of Application.
h. Percentage of Completion.
i. Balance to Finish.
j. Retainage.

3. A monthly itemized estimate of Work done for the purpose of making progress payments. In order for the City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.

4. On or before the twenty-fifth (25th) day of each month and upon receipt of City’s approval of the updated schedule as required by Section 01 32 00, Contractor shall meet with the City Representative to measure and verify quantities of work completed which Contractor requests payment for. The Contractor shall submit to City two (2) copies of a request for payment for the cost of the Work put in-place at that time, along with one (1) copy of the City approved updated CPM schedule.

Such requests for progress payments shall be based upon Schedule of Values prices of all labor and materials incorporated in the Work up until midnight of the last day of that one-month period, less the aggregate of previous payments. If Contractor is late submitting its payment request, that payment request may be processed at any time during the succeeding one-month period, resulting in processing of Contractor’s payment request being delayed for more than a day for day basis.

5. Payment requests may include, but are not necessarily limited to the following:
a. Material, equipment and labor incorporated into the Work, less any previous payments for the same.

6. With each request for payment, Contractor shall fulfill all scheduling requirements of Document 00 72 00, “General Conditions,” and Section 01 32 00 “Progress Schedules and Reports,” including updates and revisions. In addition, a responsible officer of Contractor shall execute and submit the following certification shown below:
“ I, ________________(print name), being the ___________________ of _______________________________ (Contractor), the undersigned Contractor, certifies that the Work covered by this request for payment (invoice) has been completed in accordance with the Contract Documents, and that the current progress payment (invoice) shown herein is accurate and now due. Contractor further certifies that all amounts have been paid by the Contractor for Work for

Page 303 of 557 ends

38077.00180\29080232.10
-136- 01 20 00 Measurement and payments
which previous invoices for progress payments issued to and paid by the City.

The Contractor declares under penalty of perjury under the laws of the State of California, and do personally certify and attest that: I have thoroughly reviewed the attached request for payment (invoice) and know its contents, and said request for payment is made in good faith; that it is supported by truthful and accurate data; that the amount requested accurately reflects the allowable expenses incurred to perform the Work.
___________________________________________”
signature & date

7. No progress payment will be processed prior to City receiving the above certification and all requested and acceptable schedule update information.

8. With each request for payment, Contractor shall submit following as pre-requisite to its review as referenced in Document 00 72 00, “General Conditions.”:
a. Construction progress schedule, updated to current.
b. Current construction photographs, updated to current. c. Partial release of liens from major subcontractors and vendors. d. Progress project record documents, updated to current. e. Affidavits and bonds attesting to off-site stored products, if any. f. Certified payroll records.
g. Statement under False Claim Act.

9. Contractor shall submit fulfill all record document requirements of Section 01 78 39, “Project Record Drawings,” including updates and revisions. An additional 10% of progress payment requests may be withheld in the event that the City determines that the job-site record drawings have not been kept up-to-date. Contractor also to submit the following pre-requisites for review of the Payment Application Request.

10. Each payment request shall list each Approved Change Order (See Section 01 26 00) executed prior to date of submission, including a description of the work activities.

11. Monthly progress payments shall be made based on total value of activities completed or partially completed, as determined by City with participation of Contractor, and based upon approved activity costs.

Accumulated retainage will be shown as a separate item in payment summary. If Contractor fails or refuses to participate in construction progress evaluation with City, Contractor shall not receive current payment until Contractor has participated fully in providing construction progress information and schedule update information to City.

12. If required by City, Contractor shall submit substantiating data as they relate to payment requests.

Page 304 of 557 ends

38077.00180\29080232.10
-137- 01 20 00 Measurement and payments
D. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. Notice to Proceed

2. List of subcontractors.

3. Schedule of values.

4. Contractor's construction schedule.

E. Progress Payments:

1. If it is determined that the payment request is not a proper payment request suitable for payment, City shall return it to the Contractor as soon as practicable, but no later than seven (7) days after receipt, together with a document setting forth in writing the reasons why the payment request is not proper. If City determines that portions of the payment request is not proper or not due under the Contract Documents, then City may approve the other portions of the payment request, and in the case of disputed items or defective work not remedied, may withhold up to 150% of the disputed amount from the progress payment.

2. The City will mail the progress payment to the Contractor within thirty (30) days from the date of receipt of the invoice in acceptable form, including copies of certified payroll, schedule updates, and progress payment certification. The City will pay to Contractor in manner provided by law, an amount equal to ninety-five percent (95%) (i.e., five percent (5%) retention) of City’s estimate, or a lesser amount if so provided in Contract Documents, provided that payments may at any time be withheld if, in judgment of City, Work is not proceeding in accordance with Contract, or Contractor is not complying with requirements of Contract, or to comply with stop notices or to offset liquidated damages accruing or expected.

3. Before any progress payment or final payment is made, Contractor may be required to submit satisfactory evidence that Contractor is not delinquent in payments to employees, subcontractors, suppliers, or creditors for labor and materials incorporated into Work. Prior to final payment by the City, the Contractor shall submit a final waiver of lien for the Contractor’s work, together with releases of lien from any subcontractor or materialmen.

4. City reserves and shall have the right to withhold payment for any equipment and/or specifically fabricated materials that, in the sole judgment of City, is not adequately and properly protected against weather and/or damage, prior to or following incorporation into the Work.

5. Granting of progress payment or payments by City, or receipt thereof by Contractor, shall not be understood as constituting in any sense acceptance of Work or of any portion thereof, and shall in no way

Page 305 of 557 ends

38077.00180\29080232.10
-138- 01 20 00 Measurement and payments
lessen liability of Contractor to replace unsatisfactory work or material, though unsatisfactory character of work or material may have been apparent or detected at time payment was made.

6. When City shall charge sum of money against Contractor under any provision of Contract Documents, amount of charge shall be deducted and retained by City from amount of next succeeding progress payment or from any other payment due or that may become due Contractor under Contract. If, on completion or termination of Contract, such payment due Contractor are found insufficient to cover City’s charges against it, City shall have right to recover balance from Contractor or Sureties.

PART 2 – PRODUCTS

2.1 BREAKDOWN
The contract Lump Sum price paid for all bid items listed below shall be considered full compensation for furnishing all labor, materials, equipment, tools, and incidentals for all work involved including the removal, disposal, furnishing, and installation of any bid item listed below as specified in the Contract Documents and as directed by the City Engineer, and no separate payment shall be made.

BASE BID ITEMS

1. Mobilization and Demobilization: The contract lump sum price paid for “Mobilization and Demobilization” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in mobilization, demobilization, preparatory work and operations necessary for the movement of personnel, equipment, and supplies to the project sites, erosion control, submittals, administration, final clean up as specified herein. No separate payment shall be made. The total lump sum shall not exceed 5% of the total Base Bid.

2. Traffic Control: The contract lump sum price paid for “Traffic Control” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in preparation and implementation of traffic control plan, signage, flaggers as specified herein. No separate payment shall be made.

3. Dewatering: The contract lump sum price paid for “Dewatering” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in removing and storing excess water; procurement and installation of Baker Tank, well points, sump pumps, temporary pipelines for water disposal, rock or

Page 306 of 557 ends

38077.00180\29080232.10
-139- 01 20 00 Measurement and payments
gravel placement, standby pumping equipment maintained on the job site continuously; and the safe and proper disposal of excess water in compliance with local and State regulations as specified herein. No separate payment shall be made.

4. Replacement of 14-inch Water Valve at Location #1 (Caltrans ROW): The contract lump sum price paid for “Replacement of 14-inch Water Valve at Location #1” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

5. Replacement of 14-inch Water Valve at Location #2 (Caltrans ROW): The contract lump sum price paid for “Replacement of 14-inch Water Valve at Location #2” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

6. Replacement of 12-inch Water Valve at Location #3 (Caltrans):

The contract lump sum price paid for “Replacement of 12-inch Water Valve at Location #3” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

7. Replacement of 12-inch Water Main, Fire Hydrant and Valves at Location #4: The contract lump sum price paid for “Replacement of 12-inch Water Main, Fire Hydrant and Valves at location #4” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main

Page 307 of 557 ends

38077.00180\29080232.10
-140- 01 20 00 Measurement and payments
pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

8. Replacement of 8-inch Water Valve at Location #5: The contract lump sum price paid for “Replacement of 8-inch Water Valve at Location #5” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

9. Replacement of 16-inch Water Valve at Location #6: The contract lump sum price paid for “Replacement of Water Valve #6” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

10. Installation of New 16-inch Water Valve at Location #7: The contract lump sum price paid for “Installation of New 16-inch Water Valve at Location #7” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in demolition; saw cutting; removing and disposing of existing water valve and water main pipe; handling and disposing of asbestos cement pipe; trenching and backfilling; shoring; installing of new water valve, valve box, coupling, and water main pipe; cleaning/disinfecting new valve and pipe; restriping, and restoring pavement and/or sidewalk including curb and gutter as specified herein. No separate payment shall be made.

11. Water & Fire Service Bypass (high line) The contract lump sum price paid for “Water & Fire Services bypass (high line)” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in installing temporary water pipe/hose from hydrant to existing water and fire service backflow preventer; providing protection to the pipe to ensure safe vehicle and

Page 308 of 557 ends

38077.00180\29080232.10
-141- 01 20 00 Measurement and payments
pedestrian travel; monitoring the connection throughout the construction period until the permanent connection is restored; and removing temporary set up and cleaning up as specified herein. No separate payment shall be made.

Page 309 of 557 ends

-142-

TECHNICAL PROVISIONS

Page 310 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves August 2024 Replacement Project No. 7118 & 7100 -1- 00 01 05
SECTION 00 01 05

CERTIFICATIONS PAGE
ENGINEER’S CERTIFICATIONS :

These Technical Specifications have been prepared for City of Milpitas, for the following project:

E. Calaveras Blvd. & Yosemite Dr. Water Valves Replacement Project No. 7118 & 7100 The documents have been prepared by, or under the direct supervision of the following design Professional Engineer(s), licensed in the State of California:

Curtis M. Lam, P.E.

HydroScience Engineers
741 Allston Way
Berkeley, CA 94710
August 22, 2024

Page 311 of 557 ends

City of Milpitas E. Calaveras Blvd & Yosemite Dr. Water Valves Replacement Project No. 7118 August 2024 Technical Specifications Table of Contents
356-011 TOC-1

TABLE OF CONTENTS

TECHNICAL SPECIFICATIONS
DIVISION 1 ñ GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 32 13 SCHEDULING OF WORK
01 33 00 SUBMITTAL PROCEDURES
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 51 37 TEMPORARY WATER MAIN
01 55 26 TRAFFIC CONTROL
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 2 ñ EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 33 REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIALS DIVISION 31 ñ EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 23 00 EXCAVATION AND FILL
31 23 19 DEWATERING
31 41 00 SHORING
DIVISION 32 ñ EXTERIOR IMPROVEMENTS
32 12 16 ASPHALT PAVING
32 16 00 CURBS, GUTTERS, SIDEWALKS, AND DRIVEWAYS
DIVISION 33 ñ UTILITIES
33 05 09.23 ADAPTERS FOR UTILITY PIPING
33 14 00 WATER UTILITY TRANSMISSION AND DISTRIBUTION
DIVISION 40 ñ PROCESS INTERCONNECTIONS
40 05 61.23 RESILIENT-SEATED GATE VALVES
**END OF SECTION**

Page 312 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 11 00
SECTION 01 11 00

SUMMARY OF WORK
PART 1 GENERAL

1.1 SUMMARY
A. The work to be done consists of furnishing all labor, materials, equipment, and services to install and replace existing water valves and main on E. Calaveras and Yosemite Drive.

1.2 LOCATION
A. The project is located in the City of Milpitas, California, along E Calaveras Blvd between S Hillview Dr and S Park Victoria Dr, and along Yosemite Dr between S Milpitas Blvd and Piedmont Creek.

1.3 CONTRACTOR SCOPE OF WORK:

A. The work to be performed under this contract comprises furnishing all labor, materials, and equipment required to, but not limited to, perform the following items:

1. Remove and replace six (6) existing isolation valves. The work shall be performed by the Contractor in the sequence specified on the drawings.

2. Install two (2) new isolation valves

3. Install new 12-inch PVC water main, lateral, and fire hydrant, including all of the following:
(a) Pipe, angles, couplings, plugs/caps, and other appurtenances (b) Pipe bedding and backfill

4. Demolish and remove existing asbestos cement water mains, fittings and appurtenances

5. Provide traffic control

6. Replace curb and gutter, medians, and landscaping as removed for completion of work

7. Replace asphalt paving to Caltrans and City of Milpitas requirements

8. Replace traffic striping and pavement markings removed for completion of work

1.4 CITY SCOPE OF SERVICES

NOT USED

1.5 CITY PRE-PURCHASED EQUIPMENT
A. No pre-purchased materials or equipment will be provided by the City.

Page 313 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 11 00

1.6 WORK INCLUDED
A. The Contractor shall furnish all labor, superintendence, materials, power, light, heat, fuel, water, tools, appliances, equipment, supplies, services, and other means of construction necessary or proper for performing and completing the work.

B. The Contractor shall obtain and pay for all required permits.

C. Contractor shall perform and complete the work in the manner best calculated to promote rapid construction consistent with safety of life and property, to the satisfaction of the Cityís Representative and in strict accordance with the Contract Documents.

D. The Contractor shall clean up the work site and maintain it during and after construction, until accepted, and shall do all of the work and pay all costs incidental thereto.

E. The Contractor shall repair all structures, pavement, and property, in kind, that may be damaged or disturbed during performance of the work.

F. The Contractor shall provide and maintain such modern plant, tools, and equipment as may be necessary to perform in a satisfactory and acceptable manner all the work required by this Contract. Only equipment of established reputation and proven efficiency shall be used. The Contractor shall be solely responsible for the adequacy of his equipment.

1.7 COORDINATION WITH OPERATIONS OF EXISTING FACILITIES A. The Contractor shall coordinate all work with City of Milpitas. Contact Tony Cao, Associate Civil Engineer, 408-586-3321
B. The water system is to remain in service through the project. Interruptions to the service shall be minimized and shall be coordinated with the City.

PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
** END OF SECTION **

Page 314 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 32 13
SECTION 01 32 13

SCHEDULING OF WORK
PART 1 GENERAL

1.1 GENERAL
A. The scheduling of the work under the Contract shall be performed in accordance with the requirements of this Section.

B. The development of the schedule, the cost loading of the schedule, monthly payment requisitions and project status reporting requirements of the Contract shall employ computerized Critical Path Method (CPM) or bar chart scheduling.

1.2 DEFINITIONS AND REQUIREMENTS
A. Critical Path Method (CPM): CPM, as required by this Section, shall be interpreted to be generally as outlined in the Association of General Contractors (AGC) publication, "The Use of CPM in Construction." except that either "i-j" arrow diagrams or precedence diagramming format may be utilized. In the case of conflicts between this specification and the AGC Document, this specification shall govern.

B. Construction Schedules: Construction schedules shall include a graphic network diagram and computerized construction schedule reports.

C. Networks: The CPM network shall be in a form of a time scaled "i-j" activity-on-arrow or precedence type diagram and may be divided into a number of separate sheets with suitable match lines relating the interface points among the sheets.

1. Individual sheets shall not exceed 36-inch by 60-inch.

D. All construction activities and procurement shall be indicated in a time-scaled format and a calendar timeline shall be shown along the entire sheet length.

1. Each activity arrow or node shall be plotted so that the beginning and completion dates of each activity are accurately represented along the calendar timeline.

2. All activities shall be shown using the symbols that clearly distinguish between critical path activities, non-critical activities and free float for each non-critical activity.

3. All activity items shall be identified by their respective Activity Number, Responsibility Code, Work Duration, and their Dollar Value.

4. All non-critical path activities shall show their total float time in scale form by utilizing a dotted line or some other graphical means.

E. Duration Estimates: The duration estimate indicated for each activity shall be computed in calendar days and shall represent the single best estimate considering the scope of the activity work and resources planned for the activity. Except for certain non-labor activities, such as curing of concrete or delivery of materials, activity duration

Page 315 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 32 13
shall not exceed 10 calendar days nor be less than one calendar day unless otherwise accepted by the Cityís Representative.

F. Float Time: Float time shall be as follows:

1. Definition: Unless otherwise provided herein, float as referenced in these documents, is total float. Total float is the period of time measured by the number of calendar days each non-critical path activity may be delayed before it and its succeeding activities become part of the critical path. If a non-critical path activity is delayed beyond its float period, that activity then becomes part of the critical path and controls the end date of the project. Thus, the delay of the non-critical path activity beyond its float period will cause delay to the project itself.

2. Float Ownership: Neither the City nor the Contractor owns the float time. The project owns the float time. As such, liability for delay of the project completion date rests with the party actually causing delay to the project completion date.

For example, if Party A uses some, but not all of the float time and Party B later uses the remainder of the float time as well as additional time beyond the float time, Party B shall be liable for the costs associated with the time that represents a delay to the project's completion date. Party A would not be responsible for any costs since it did not consume all of the float time and additional float time remained, therefore, the project's completion date was unaffected.

1.3 SUBMITTALS
A. Submit schedules per requirements of Specification Section 01 33 00 ñ Submittal Procedures.

B. Estimated Schedule

1. The Contractor shall submit an Estimated schedule document within 21 days after the issuance of the Notice of Award.

C. Schedule Updates

1. Submit monthly when requested to do so by the Engineer to reflect changes to Estimated schedule.

1.4 CONSTRUCTION SCHEDULE
A. The schedule shall indicate the major components of the project work and the sequence relations between major components and subdivisions of major components.

B. The schedule shall be cost loaded based on the schedule of values as approved by the Cityís Representative.

C. Sufficient detail shall be included for the identification of subdivisions of major components into such activities as:

1. All work tasks requiring a partial closure of existing facilities and roadways.

Page 316 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 01 32 13

2. Trenching and backfilling.

3. Piping

4. Finished pavement.

5. Site work.

6. Other important work within the overall project scope.

D. Planned durations and start dates shall be indicated for each work item subdivision.

Each major component and subdivision component shall be accurately plotted on time scale sheets not to exceed 36-inch by 60-inch in size. Not more than one sheet shall be employed to represent this information.

1.5 SCHEDULE REVIEW
A. The Cityís Representative and the Contractor shall meet to review and discuss the estimated schedule after it has been submitted to the Cityís Representative.

1. The Cityís Representative's review and comment on the schedules shall be limited to Contract conformance with the sequencing and milestone requirements as stated in other sections of the specifications.

2. The Contractor shall make corrections to the schedules necessary to comply with the Contract requirements and shall adjust the schedules to incorporate any missing information requested by the Cityís Representative.

1.6 ACCEPTANCE
A. The acceptance of the Contractor's schedule by the Cityís Representative and City will be based solely upon the schedule's compliance with the Contract requirements.

B. By way of the Contractor assigning activity durations and proposing the sequence of the Work, the Contractor agrees to utilize sufficient and necessary management and other resources to perform the work in accordance with the schedule.

C. Upon submittal of a schedule update, the updated schedule shall be considered the "current" project schedule.

D. Submission of the Contractor's progress schedule to the City or Cityís Representative shall not relieve the Contractor of the Contractor's total responsibility for scheduling, sequencing, and pursuing the Work to comply with the requirements of the Contract Documents, including adverse effects such as delays resulting from ill-timed work.

1.7 MONTHLY UPDATES AND PERIODIC SCHEDULE SUBMITTALS
A. Following the acceptance of the Contractor's Estimated Construction Schedule, the Contractor shall monitor the progress of the Work and adjust the schedule each month to reflect actual progress and any changes in planned future activities.

1. Each schedule update submitted must be complete including all information requested in the estimated schedule submittal.

Page 317 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 01 32 13

2. Each update shall continue to show all work activities including those already completed.

3. These completed activities shall accurately reflect the "as built" information by indicating when the work was actually started and completed.

B. Neither the submission nor the updating of the Contractor's estimated schedule submittal nor the submission, updating, change or revision of any other report, curve, schedule or narrative submitted to the Cityís Representative by the Contractor under this Contract, nor the Cityís Representative's review or acceptance of any such report, curve, schedule or narrative shall have the effect of amending or modifying, in any way, the Contract completion date or milestone dates or of modifying or limiting, in any way, the Contractor's obligations under this Contract. Only a signed, fully executed change order can modify these contractual obligations.

C. The monthly schedule update submittal will be reviewed with the Contractor during a construction progress meeting held on a month end date to be determined. The goal of these meetings is to enable the Contractor and the Cityís Representative to initiate appropriate remedial action to minimize any known or foreseen delay in completion of the Work and to determine the amount of Work completed since the last month's schedule update.

1. The status of the Work will be determined by the percent complete of each activity shown in the Network Diagram.

2. These meetings are considered a critical component of the overall monthly schedule update submittal and the Contractor shall have appropriate personnel attend.

3. As a minimum, these meetings shall be attended by the Contractor's Project Manager and General Superintendent.

4. Within seven (7) calendar days after the progress meeting, the Contractor shall submit the revised schedule.

5. Within five (5) calendar days of receipt of the above noted revised submittals, the Cityís Representative will either accept or reject the monthly schedule update submittal.

6. If accepted, the percent complete shown in the monthly update will be the basis for the Application for Payment to be submitted by the Contractor.

7. If rejected, the update shall be corrected and resubmitted by the Contractor before the Application for Payment for the update period can be processed.

D. Schedule Revisions: The Contractor shall highlight or otherwise identify all changes from the previous schedule. The Contractor shall modify any portions of the schedule that become infeasible because of activities behind-schedule or for any other valid reason.

1.8 CHANGE ORDERS

Page 318 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 01 32 13
A. Upon approval of a change order, or upon receipt by the Contractor of authorization to proceed with additional work, the change shall be reflected in the next submittal of the schedule by the Contractor.

B. The Contractor shall utilize a sub-network in the schedule depicting the changed work and its effect on other activities.

C. This sub-network shall be tied to the main network with the appropriate logic so that a true analysis of the Critical Path can be made.

1.9 PROJECT STATUS REPORTING
A. In addition to the submittal requirements for the scheduling identified in this Section, the Contractor shall provide monthly project status reports.

B. The Contractor shall prepare monthly written narrative reports of the status of the project for submission to the Cityís Representative. Written status reports shall include:

1. The status of major project components (Percent Complete, amount of time ahead or behind schedule) and an explanation of how the project will be brought back on schedule if delays have occurred.

2. The progress made on critical activities indicated on the schedule.

3. Explanations for any lack of work on critical path activities planned to be performed during the last month.

4. Explanations for any schedule changes, including changes to the logic or to activity durations.

5. A list of the critical activities scheduled to be performed in the next two-month period.

6. The status of major material and equipment procurement.

7. The value of materials and equipment properly stored at the site, but not yet incorporated into the work-in-place.

8. Any delays encountered during the reporting period.

9. An assessment of inclement weather delays and impacts to the progress of the Work.

C. The Contractor may include any other information pertinent to the status of the project.

The Contractor shall include additional status information requested by the Cityís Representative.

1.10 INCLEMENT WEATHER PROVISIONS OF THE SCHEDULE
A. The Contractor's construction schedule shall include lost days on the CPM schedule's critical path due to inclement weather typical for the area of construction based on the average rain days for the past five (5) years.

Page 319 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 01 32 13
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
** END OF SECTION **

Page 320 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 33 00
SECTION 01 33 00

SUBMITTAL PROCEDURES
PART 1 GENERAL

1.1 SUMMARY
A. Section Includes:

1. Description of general requirements for project Submittals.

1.2 SUBMITTALS
A. Where required by the Specifications, the Contractor shall submit descriptive information which will enable the Engineer to advise the City whether the Contractor's proposed materials, equipment or methods of work are in general conformance with the design concept and are in compliance with the drawings and specifications. The information to be submitted shall consist of drawings, specifications, descriptive data, certificates, samples, test results and other such information, all as specifically required in the Specifications.

B. The Contractor shall submit the following items:

1. Schedule of Submittals and Shop Drawings

2. List of Submittals, Shop Drawings, Product Data and Materials

3. Contractorís Safety Program

4. Designated Safety Supervisor

5. Designated ìCompetent Person(s)î

6. Schedule of Values

7. Construction Schedule

8. Substitutions List

9. Shop Drawings

10. Product Data

11. Samples

12. Material Safety Data Sheets

13. Operation and Maintenance Manuals

14. Project Closeout Information

15. Warranty Data

16. Others as Specified in the Technical Specifications

Page 321 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 33 00

17. Manufacturerís Instructions

18. Manufacturerís Certifications and Test Reports
C. Quantity of Submittals:

1. Submit one (1) digital PDF format of all submittals. (a) PDF submittal shall be clear and readable.
(b) Provide searchable PDF file.
(c) Annotate or mark submittal to clearly show the item or model being submitted.
(d) Organization and Binding of Submittals: The initial and subsequent submittals of drawings and data for review shall be organized and bound with a Table of Contents so that eventually they may be used as guides for preparing the required maintenance manuals. PDF files shall have active links in the Table of Contents, or they shall have bookmarks per the Table of Contents.

2. If paper copies are submitted:
(a) Provide three (3) copies to the Cityís Representative and a scanned electronic copy where feasible. The Contractor shall state the number of copies the Contractor wants to be returned where necessary.

D. Where the Contractor is required by these Specifications to submit samples of products, the Contractor shall provide a sufficient number of physical samples to allow three (3) to be retained by the Cityís Representative of all structural and architectural products involving color, finish, texture, or the like.

E. List of Submittals:

1. Within thirty-five (35) days after the Notice to Proceed, the Contractor shall submit a List of Submittals to the Cityís Representative for review.

2. The List shall include all items of equipment and materials for necessary project disciplines (Civil, Electrical, Mechanical etc) and the names of manufacturers with whom purchase orders have been or will be placed.

3. The List shall be arranged in the same order as the Specifications and shall contain sufficient data to identify all items of material and equipment the Contractor proposes to furnish. The List shall include Specification and/or Drawing references.

4. After the submission is favorably reviewed and returned to the Contractor by the Cityís Representative, it shall become the basis for the submission of detailed manufacturer's drawings, catalog cuts, curves, diagrams, schematics, data, and information on each separate item for review as set forth in the Specifications.

Page 322 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 01 33 00
F. The Contractor shall be responsible for the accuracy and completeness of the information contained in each submittal and shall ensure that the material, equipment or method of work shall be as described in the submittal.

1. Submittals shall contain all required information, including satisfactory identification of items, units and assemblies in relation to the contract drawings and specifications.

2. The Contractor shall verify that the material and equipment described in each submittal conforms to the requirements of the specifications and drawings.

3. Unless otherwise approved by the Engineer, submittals shall be made only by the Contractor, who shall indicate by a signed stamp on the submittals that the Contractor has checked the submittals and that the work shown conforms to contract requirements and has been checked for dimensions and relationship with work of all other trades involved.

4. If the information shows deviations from the specifications or drawings, the Contractor, by statement in writing accompanying the information, shall identify the deviations and state the reason(s) therefore.

5. The Contractor shall ensure that there is no conflict with other submittals and shall notify the Engineer in each case where the Contractorís submittal may affect the work of another contractor or the City.

6. The Contractor shall ensure coordination of submittals among the related crafts and subcontractors.

1.3 SUBMITTAL TRANSMITTAL PROCEDURE
A. General: Submittals regarding material and equipment shall be accompanied by a transmittal form from the Contractor. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate, discrete specification sections for which a submittal is required. However, submittals for various items shall be made with a single form only when the items taken together constitute a manufacturer's package or are so functionally related that expediency indicates checking or review of the group or package as a whole.

B. Submittal Identification: Each set of submittals or samples shall be attached to the submittal transmittal form.

1. The submittal number shall be made up of two parts: XXX-ZZ. The XXX shall be sequential number 001 for the first item submitted, 002 for the second, etc.

The ZZ shall be the sequential number of a specific submittal or resubmittal (01 for the first submittal, 02 for the first resubmittal, etc.).

2. All submittals shall show the contract title, shall indicate the name of the vendor, and shall indicate when the equipment and/or material will be required by the construction schedule.

3. The submittal must be adequate to permit a comprehensive review without further reference to the Contractor. The documents submitted must be separately identifiable on the Contractor's submittal transmittal form.

Page 323 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 01 33 00
C. Deviation from Contract: If the Contractor proposes to provide material or equipment which does not conform to the specifications and drawings, this shall be indicated under "deviations" on the submittal transmittal form accompanying the submittal copies.

1. If the City accepts such deviation, the City shall issue an appropriate Contract Change Order, except that, if the deviation is minor, or does not involve a change in price or in time of performance, a Change Order need not be issued.

2. If any deviations from the Contract requirements are not noted on the submittal, the review of the shop drawing shall not constitute acceptance of such deviations.

D. Submittal Completeness: Submittals which do not have all the information required to be submitted, including deviations, shall be considered as not complying with the intent of the contract and are not acceptable and will be returned without review.

1. A complete submittal shall contain sufficient data to demonstrate that the items comply with the Specifications, shall meet the minimum requirements for submissions cited in the technical specifications, shall include materials and equipment data and seismic anchorage certifications where required, and shall include any necessary revisions required for equipment other than first named.

E. Review of Subsequent Resubmittals: It is considered reasonable that the Contractor shall make a complete and acceptable submittal to the Cityís Representative at least by the second submission of data. At the discretion of the Engineer costs associated with the review of any subsequent resubmittals may be borne by the Contractor. The Contractor will be billed for these costs by the City. Costs due may be deducted from progress payments due the Contractor by the City.

1.4 SUBMITTAL REVIEW
A. The Contractor shall provide all submittals to the Cityís representative at the earliest feasible time possible to facilitate a comprehensive review that does not impact construction related progress.

B. Within 14 calendar days after receipt of the submittal by the Engineer, the submittal will be reviewed by the Engineer and the Engineer will return the marked-up submittal. On complex drawings and equipment, the Engineer shall acknowledge receipt within 30 days and advise the Contractor when the submittal will be returned. The returned submittal shall indicate one of the following actions.

1. If the review indicates that the material, equipment or work method is in general conformance with the design concept and complies with the drawings and specifications, submittal copies will be marked "NO EXCEPTIONS TAKEN". In this event, the Contractor may begin to implement the work method or incorporate the material or equipment covered by the submittal.

2. If the review indicates limited corrections are required, copies will be marked "MAKE CORRECTIONS NOTED". The Contractor may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections. Where submittal information will be incorporated in operation and maintenance data, a corrected copy shall be provided. Otherwise, no resubmittal will be required.

Page 324 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 01 33 00

3. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked "REVISE AND RESUBMIT". The Contractor shall not undertake work covered by this submittal until the submittal has been revised, resubmitted and returned marked either 'NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED".

4. If the review indicates that the material, equipment or work method is not in general conformance with the design concept or in compliance with the drawings and specifications, copies of the submittal will be marked "REJECTED - SEE REMARKS". Submittal with deviations which have not been identified clearly may be rejected. The Contractor shall not undertake work covered by such submittal until a new submittal is made and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED".

C. Review of drawings, methods of work, or information regarding materials or equipment the Contractor proposes to provide shall not relieve the Contractor of responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Engineer, the Cityís Representative or the City, or by any officer, employee or subcontractor thereof, and the Contractor shall have no claim under the contract on account of the failure or partial failure of the method of work, material, or equipment so reviewed.

1. A mark of "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED" shall mean that the City has no objection to the Contractor, upon its own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.

2. Favorable review of submittals does not constitute a change order to the Contract requirements.

3. The favorable review of all submittals by the Engineer shall apply in general design only and shall in no way relieve the Contractor from responsibility for errors or omissions contained therein.

4. Favorable review by the Engineer shall not relieve the Contractor of its obligation to meet safety requirements and all other requirements of laws, nor constitute a Contract Change Order.

5. Favorable review by the Engineer will not constitute acceptance by the Engineer of any responsibility for the accuracy, coordination, and completeness of the submittals or the items of equipment represented on the submittals.

6. The favorable review of shop drawings shall be obtained prior to the fabrication, delivery and construction of items requiring shop drawing submittal. **END OF SECTION**

Page 325 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 50 00
SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL

1.1 SUMMARY
A. The Contractor shall provide all temporary facilities and utilities required for execution of the work, protection of employees and the public, protection of the work from damage by fire, weather or vandalism, and such other facilities as may be specified or required by any legally applicable law, ordinance, rule, or regulation.

B. Temporary facilities utilized on the project shall be in complete accordance with requirements set forth in the Caltrans Standard Specifications.

C. The Contractor shall keep the work site clean and free from rubbish and debris. Materials and equipment shall be removed from the site when they are no longer necessary on a daily basis as directed by the Cityís Representative. All cables, slings and other materials used to set the pipe and equipment shall be removed from the project site.

Upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish to present a clean and neat appearance.

1.2 TEMPORARY FACILITIES
A. Electrical Service

1. The Contractor shall arrange, at its own cost, with the local utility to provide adequate temporary electrical service at a mutually agreeable location.

2. The Contractor shall then provide adequate jobsite distribution facilities conforming to applicable codes and safety regulations.

3. The Contractor shall provide, at its own cost, all electric power required for construction, testing, general and security lighting, and all other purposes whether supplied through temporary or permanent facilities.

B. Water

1. The Contractor shall pay for and shall construct all facilities necessary to furnish water for its use during construction.

2. Water used for human consumption shall be kept free from contamination and shall conform to the requirements of the State and local authorities for potable water.

3. The Contractor shall pay for all water used for the Contractor's operations prior to final acceptance.

C. Sanitary Conveniences

1. The Contractor shall provide suitable and adequate sanitary conveniences for the use of all persons at the site of the Work.

Page 326 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 50 00

2. Such conveniences shall include chemical toilets or water closets and shall be located at appropriate locations at the site of the Work.

3. All sanitary conveniences shall conform to the regulations of the public authority having jurisdiction over such matters.

4. At the completion of the Work, all such sanitary conveniences shall be removed, and the site left in a sanitary condition.

D. Telephone/Internet

1. The Contractor shall arrange, at its own cost, with the local utility to provide adequate temporary telephone or internet services for its use during construction.

2. Contractor shall pay for all required services required for its own use as necessary.

1.3 CONSTRUCTION FACILITIES
A. Construction hoists, elevators, scaffolds, stages, shoring, and similar temporary facilities shall be of ample size and capacity to adequately support and move the loads to which they will be subjected. Railings, enclosures, safety devices, and controls required by law or for adequate protection of life and property shall be provided.

B. Staging and Falsework

1. Temporary supports shall be designed by a professional registered engineer with an adequate safety factor to assure adequate load bearing capability. If requested by the City's Representative, the Contractor shall submit design calculations for staging and shoring prior to application of loads.

2. Excavation support shall be in accordance with applicable codes and regulations.

C. Temporary Enclosures

1. When sandblasting, spray painting, spraying of insulation, or other activities inconveniencing or dangerous to property or the health of employees or the public are in progress, the area of activity shall be enclosed adequately to contain the dust, over-spray, or other hazard.

2. In the event there are no permanent enclosures of the area, or such enclosures are incomplete or inadequate, the Contractor shall provide suitable temporary enclosures.

D. Warning Devices and Barricades

1. The Contractor shall adequately identify and guard all hazardous areas and conditions by visual warning devices and, where necessary, physical barriers.

2. Such devices shall, as a minimum, conform to the requirements of Cal/OSHA.

E. Culvert Bypassing and Protection

Page 327 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 01 50 00

1. The Contractor shall provide bypass and pumping facilities for any flowing culverts that encroach upon project trenching activities. (a) Bypassing facilities will only be required in high risk situations to prevent flooding the trench. Culvert bypassing risk shall be at the sole discretion of the Contractor.

2. Culvert bypassing systems shall be submitted to the Engineer for review prior to construction activities. Culvert bypassing plans shall provide, but not be limited to, the following information:
(a) Means of protecting culverts during trench construction activities. (b) Construction means and methods describing culvert plugging, bypassing, and relocation of flowing water.
(c) List all equipment necessary to perform bypassing and culvert protection undertakings.
(d) Detail the bypass systemís receiving stream crossing or drainage channel and the existing condition of the structure.

3. Culvert crossings damaged during construction activities identified by the project Inspector shall be restored in kind by the Contractor at no additional cost to the City unless otherwise negotiated.

1.4 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS A. The Contractor shall be responsible for the protection of public and private property at and adjacent to the Work and shall exercise due caution to avoid damage to such property.

B. The Contractor shall repair or replace all existing improvements which are not designated for removal (e.g., curbs, sidewalks, survey points, fences, walls, signs, utility installations, pavements, structures, etc.) and are damaged or removed as a result of its operations. Repairs and replacements shall be at least equal to existing improvements and shall match them in finish and dimension.

C. Trees, lawns, and shrubbery that are not to be removed shall be protected from damage or injury. If damaged or removed because of the Contractor's operations, they shall be restored or replaced in as nearly the original conditions and location as is reasonably possible. Lawns shall be re-seeded and covered with suitable mulch.

D. The Contractor shall give reasonable notice to occupants or owners of adjacent property to permit them to salvage or relocate plants, trees, fences, sprinklers, and other improvements within the right-of-way which are designated for removal or would be destroyed because of the Work.

1.5 ACCESS ROADS
A. Access roads shall be maintained to all storage areas and other areas to which frequent access is required. Similar roads shall be maintained to all existing facilities on the site of the Work to provide access for delivery of material and for maintenance and operation.

Where such temporary roads cross buried utilities that might be injured by the loads likely

Page 328 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 01 50 00
to be imposed, such utilities shall be adequately protected by steel plates or wood planking, or bridges shall be provided so that no loads shall discharge on such buried utilities.

1.6 AIR POLLUTION AND DUST CONTROL
A. The Contractor at its expense shall take whatever steps, procedures, or means as are required to prevent abnormal dust conditions being caused by its operations in connection with the execution of the Work; and on any unpaved road which the Contractor or any of its subcontractors are using, excavation or fill areas, demolition operations, or other activities.

1. Control shall be by sprinkling, use of dust palliatives, modification of operations, or any other means acceptable to agencies having jurisdiction.

2. Haul routes shall be kept visibly wet during excavation and hauling operations.

3. Exposed stockpiles of soil and other backfill material shall be enclosed, have silt fencing, be covered, be watered regularly or have soil binders added to minimize erosion.

4. Dust-producing activities shall be suspended when high winds create construction-induced visible dust plumes moving beyond the project site, in spite of dust control measures.

B. Unless the construction dictates otherwise, and unless otherwise approved by the City's Representative, the Contractor shall furnish and operate a self-loading motor sweeper with spray nozzle at least once each working day to keep paved areas acceptably clean whenever construction, including restoration, is incomplete.

1. If visible soil material is carried onto adjacent public streets, such streets shall be swept with water sweepers.

1.7 NOISE ABATEMENT
A. Operations at the Worksite shall be performed so as to minimize unnecessary noise.

B. Special measures shall be taken to suppress noise during night hours.

C. Noise levels due to construction activity shall not exceed the levels specified by local ordinance.

D. Internal combustion engines used on the Work shall be equipped with a muffler of a type recommended by the manufacturer. No internal combustion engine shall be operated without said muffler.

1.8 WORKING HOURS
A. Construction shall be allowed only between the hours of 7:00 a.m. and 7:00 p.m. on weekdays Monday through Friday unless otherwise approved in writing by the Cityís Representative. Work areas may be further limited in the Caltrans right-of-way based on the requirements of the Caltrans encroachment permit.

Page 329 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 01 50 00
B. The Contractor shall be responsible for any inspection and additional administration costs incurred by the City, or its agents and representatives, for work by the Contractor outside the hours defined in General Conditions 00 72 13. Such costs shall be withheld from the succeeding monthly progress payment. Any work specifically required to be performed outside the normal working hours is excluded from the provisions of this paragraph.

C. The Contractor shall notify the City's Representative at least 72 hours prior to any work outside the normal working hours defined above, on weekends or holidays.

1.9 DRAINAGE CONTROL

1. In all construction operations, care shall be taken not to disturb the existing drainage pattern whenever possible.

2. Particular care shall be taken not to direct drainage water onto private property.

Drainage water shall not be diverted to streets or drainage ways inadequate for the increased flow.

3. Drainage means shall be provided to protect the Work and adjacent facilities from damage due to water from the site or due to altered drainage patterns from construction operations.

4. Temporary provisions shall be made by the Contractor to insure the proper functioning of gutters, storm drain inlets, drainage ditches, culverts, irrigation ditches, and natural water courses.

1.10 STORMWATER POLLUTION PREVENTION
A. Erosion & Dust Control

1. To reduce potential water-borne erosion impacts, the Contractor shall incorporate the following best management practices into the project:
(a) Erosion control measures to reduce post-construction erosion, such as re-vegetation with local native plant species and installation of appropriate slope protection.
(b) Provide and maintain all necessary erosion and sediment control measures throughout the construction period as required to minimize stormwater pollution control from the Contractorís work area. Erosion and sediment control measures may include, but are not limited to, straw bale dikes, sand bag dikes, silt fences, drainage swales, pipe drains, sediment traps, protective sheets, jute matting, hydro-seeding, and appropriate surface contouring. The Contractor shall notify the Cityís Representative if erosion and sediment control measures do not operate properly and shall take all necessary protective action.
(c) The Contractor shall secure erosion control devices at the end of each work shift during the period from November 1 to April 30, or when rain is forecast prior to the next workday.

Page 330 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 01 50 00
(d) Grading activities shall be prohibited during the period when rain is falling, and runoff is observed at the site. The Contractor shall immediately secure the site for erosion control and storm water runoff. (e) Prepare drainage ways that handle concentrated or increased runoff from disturbed areas by using riprap or other lining materials to control erosion. (f) Reduce erosion by limiting the area and time of exposure, and by the provision of diversion channels.
(g) Use temporary plant cover, mulching, and/or structures to control runoff and protect areas subject to erosion during construction. (h) Minimize soil exposure during the rainy season by proper timing of grading and construction and be prepared to shut down all earthwork if heavy precipitation occurs.
(i) Have erosion control equipment and materials on site if needed in an emergency to quickly construct temporary collectors, diversion channels, intercept drains, berms, dikes or filters.

2. Grading and permits and the appropriate environmental clearances shall be obtained by the Contractor prior to any export of materials off site.

1.11 CONSTRUCTION CLEANING
A. The Contractor shall, at all times, keep property on which work is in progress and the adjacent property free from accumulations of waste material or rubbish caused by employees or by the Work. All surplus material shall be removed from the site immediately after completion of the work causing the surplus materials. Upon completion of the construction, the Contractor shall remove all temporary structures, rubbish, and waste materials resulting from its operations.

1.12 DISPOSAL OF MATERIAL
A. The Contractor shall make arrangements for disposing of materials outside the Site and the Contractor shall pay all costs involved.

1. The Contractor shall first obtain permission from the property owner on whose property the disposal is to be made and absolve the City from any and all responsibility in connection with the disposal of material on said property.

2. When material is disposed of as above provided, the Contractor shall conform to all required codes pertaining to grading, hauling, and filling of earth.

1.13 PARKING AND STORAGE AREAS
A. All stockpiled materials and parked equipment at the job site shall be located to avoid interference with private property and to prevent hazards to the public.

B. Locations of stockpiles, parking areas, and equipment storage must be approved by the City's Representative.

1.14 CULTURAL RESOURCES PROTECTION

Page 331 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -7- 01 50 00
A. If historical, archeological or paleontological artifacts are discovered, all work must stop in the immediate vicinity. The Contractor shall protect the discovered items, notify the Cityís Representative, and comply with applicable law.

B. If human remains are discovered, all work must stop in the immediate vicinity of the find, and the County Coroner must be notified, according to Section 5097.98 of the State Public Resources Code and Section 7050.5 of Californiaís Health and Safety Code.

C. If the remains are determined to be Native American, the coroner will notify the Native American Heritage Commission, and the procedures outlined in CEQA Section 15064.5(d) and (e) shall be followed.

1.15 PROJECT SIGN
A. The Contractor shall provide, install and maintain for the duration of the project a project sign as designated below. The sign shall be installed where directed by the Cityís Representative.

1. 36î x 60î exterior grade plywood, minimum 3/4" thick

2. Two coats exterior quality paint for background, one coat exterior quality paint for lettering.

3. Erect supports and framing on secure foundation, rigidly braced and framed to resist loadings. Install sign surface plumb and level; anchor securely.

4. Colors of sign shall be as designated by the Cityís Representative.

5. Remove sign at the end of the project.

B. Contents of Project Sign

1. Firm responsible for project construction with a 24-hour telephone number.

Letter size: 2 inches high.

2. Purpose of project: (nature of work) Letter size: 4 inches

3. Limits of work

4. Start Date and Completion Date. Letter Size: 2 inches

5. City of Milpitas Logo in the upper left corner (12-inch round) as provided by the City

1.16 PROJECT OFFICE
A. The Contractor shall maintain on the project site a suitable office or other protected area in which shall be kept project copies of the Contract Documents, project progress records, project schedule, shop drawings, and other relevant documents which shall be accessible to the City and City's Representative during normal working hours. ** END OF SECTION **

Page 332 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 51 37
SECTION 01 51 37

TEMPORARY WATER MAIN
PART 1 GENERAL

1.1 SUMMARY
A. The Contractor shall provide all the necessary labor, materials, equipment, tools, and supplies necessary to install a complete temporary water main bypass system as specified in the Contract Documents.

1.2 REFERENCES
A. American Association of State Highway and Transportation Officials (AASHTO) B. American National Standards Institute (ANSI)
C. American Society of Mechanical Engineers (ASME)
D. ASTM International (ASTM)
E. American Water Works Association (AWWA)
F. Cast-Iron Soil Pipe Institute
G. NSF/ANSI Standard 61 Drinking Water System Components (NSF 61)

1.3 SUBMITTALS
A. Contractor shall submit in accordance with Section 01 33 00.

B. Temporary Bypass Plan:

1. Submit a Temporary Bypass Plan outlining all provisions and precautions the Contractor shall take to provide temporary water to all service connections and hydrants.

2. Temporary Bypass Plan shall be submitted to the City Engineer for review and approval twenty-one (21) days prior to commencing work on any portion of the system to be bypassed.

3. The plan must be specific and shall include, but not be limited to, the following details:
(a) Schedule for installation and maintenance of bypass system. (b) Pedestrian and vehicular traffic crossing details.
(c) Protection against main breaks.
(d) Size, length, material, locations, and method of installation for temporary water mains.
(e) Location of temporary hydrants, if used.

Page 333 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 51 37
(f) Shop drawings for temporary connections to existing or new water mains.
(g) Methods for thrust restraint of temporary water mains. (h) Methods for pressure and leakage testing.
(i) Methods for disinfection, flushing, and sampling of temporary water mains.
(j) Contractor must designate and provide a 24-hour contact person who has adequate parts and equipment on hand to make necessary repairs to the temporary water main bypass system in a timely manner.

PART 2 PRODUCTS

2.1 GENERAL
A. Temporary water main bypass pipe and associated appurtenances that may come into contact with water shall be certified for use in water systems. Submit proof of NSF certification for each item submitted.

PART 3 EXECUTION

3.1 GENERAL
A. All work in this section shall be completed in accordance with Sections 01 11 00 and the City of Milpitas Standard Specifications and Drawings.

3.2 FIELD QUALITY CONTROL
A. The City will perform bacteriological analysis for pipelines to be disinfected.

B. Factory Quality Control: The Contractor shall test all products as required herein and by the reference specifications.

C. The Contractor shall:

1. Clean all pipelines by flushing. Flushing of temporary water mains shall achieve a velocity of at least 3 feet per second. The Contractor shall install temporary strainers, temporarily disconnect equipment or take other appropriate measures to protect the existing water mains while cleaning piping.

2. Perform leakage tests.

3. Be responsible for the costs of additional inspection and retesting by the City resulting from non-compliance.
**END OF SECTION**

Page 334 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 55 26
SECTION 01 55 26

TRAFFIC CONTROL
PART 1 GENERAL

1.1 DESCRIPTION
A. The Contractor shall furnish all labor, materials, equipment, tools, and services necessary to provide continuous access to the public; and adequately safeguard the workers and public from construction hazards with a minimum of inconvenience.

B. Work includes but is not limited to the following:

1. Preparation of Traffic Control Plans and obtaining approval of Traffic Control Plans from the Caltrans and City. The TCP must be stamped and signed by licensed professional engineer (PE) or licensed traffic engineer (TE).

2. Masking and restoring permanent signs and striping.

3. Erections and removal of temporary construction signs.

4. Installation and removal of temporary traffic control devices, including barriers, barricades, changeable message boards.

5. Coordinating work with all agencies having jurisdiction.

1.2 REFERENCE STANDARDS
A. The Contractor shall comply with guidelines excluding payment sections of the latest editions of the following reference standards:

1. California Manual of Uniform Traffic Control Devices.

2. Caltrans Standard Specifications

3. Caltrans Standard Plans

4. CAL/OSHA, State of California Construction Safety Orders. (a) Section 1599, Traffic Control for Public Streets and Highways. (b) Section 1599, Flaggers

5. OSHA, Code of Federal Regulations.
(a) Title 19, Part 1926, Construction Safety Health Regulations (b) Title 29, Part 1910, Occupational Safety and Health Standards B. In case of conflict between the above reference standards and the specifications contained herein, these specifications shall take precedence and be used in lieu of such conflicting portions.

1.3 SUBMITTALS

Page 335 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 55 26
A. The Contractor shall provide submittals in accordance with Section 01 33 00, SUBMITTAL PROCEDURES.

B. The Contractor shall at minimum submit the following:

1. Traffic Control Plans shall conform to Standard Specification Section 12-4.02, TRAFFIC CONTROL PLANS (TCP), and Section 6-10, PERMITS, AND LICENSES, AND CERTIFICATIONS, and be submitted for review and approval at least twenty-one (21) calendar days prior to work.

2. Traffic Control Plans shall contain, but not be limited to, location, placement, duration, monitoring schedule and movement of all traffic control devices and bypass piping including, but not limited to, signs, signals, pedestrian and vehicle ramps, barricades, k-rails, and lighting.

C. The Contractor shall submit traffic control plans for each phase of work within a City right-of-way or easements along with an Encroachment Permit. The Contractor will allow for a 15-day review period.

1.4 QUALITY ASSURANCE
A. Traffic Control Plans shall be prepared by a California licensed Civil or Traffic Engineer. The Traffic Engineer who prepared the Traffic Control Plans shall be available at any time during the life of the contract to modify the Traffic Control Plans if and as required by the agency having jurisdiction.

B. No changes or deviations from the approved Traffic Control Plans shall be made, except temporary changes in emergency situations, with prior approval of the Traffic Engineer, the Engineer, and all agencies having jurisdiction.

C. Immediately notify the Traffic Engineer, the Engineer, and the agencies having jurisdiction of occurrences that necessitate modification of the approved Traffic Control Plans.

1.5 TRAFFIC CONTROL
A. Nothing herein shall be construed to entitle the Contractor to the exclusive use of any public street, alleyway, or parking area during the performance of the work hereunder, and the Contractor shall conduct its operations so as not to interfere unnecessarily with the authorized work of utility companies or other agencies in such streets, alleyways, or parking areas.

B. No streets or lane closures of any duration (temporary or permanent) shall occur without first obtaining permission of the Engineer and agency (or agencies) having jurisdiction.

C. Where excavation is being performed in primary streets or highways, one lane in each direction shall be kept open to traffic at all times unless otherwise provided or shown.

Toe boards shall be provided to retain excavated material if required by the Engineer or the agency having jurisdiction over the street or highway. Fire hydrants on or adjacent to the work shall be kept accessible to firefighting equipment at all times.

Temporary provisions shall be made by the Contractor to assure the use of sidewalks and the proper functioning of all gutters, storm sewer inlets and other drainage facilities.

Page 336 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 01 55 26
D. For the protection of traffic in public or private streets and ways, the Contractor shall provide, place and maintain all necessary barricades, traffic cones, warning signs, lights and other safety devices in accordance with requirements of the agency having jurisdiction or the California Manual of Uniform Traffic Control Devices whichever is more strict.

E. Contractor shall take all necessary precautions for the protection of the work and the safety of the public. All barricades and obstructions shall be illuminated at night, and all lights shall be turned on from sunset until sunrise. The Contractor shall station such guards or flaggers and shall conform to such special safety regulations relating to traffic control as may be required by the public authorities within their respective jurisdiction.

F. No work will be allowed in public right-of-way until the Contractor obtains written approval of the proposed Traffic Control Plans from agencies having jurisdiction.

1.6 STREET CLOSURE REQUIRED NOTIFICATION
A. When street closure is required or permitted for the construction of facilities on or under the street, the Contractor shall notify in writing, the occupants of all homes and businesses with access to that street of the proposed closure at least ten (10) Working Days prior to road closures and at least three (3) Working Days prior to disruption of ingress and egress.

B. The notice provided to the residences or businesses shall include, at a minimum, schedule of closures and/or parking restrictions with estimated closure and/or parking restriction times, closure and/or parking restriction location, alternate route or detour, and name and twenty-four (24) hour phone number of a contact person employed by the Contractor.

C. The Contractor shall be prepared to make access available at any time during the day to emergency type vehicles or pre-arrange alternative locations for non-emergency vehicles and operations. At a minimum the following agencies must be notified.

1. Fire Department

2. Police Department

3. Sheriff Department

4. Emergency ambulance companies

5. Waste Management and Recycling
PART 2 PRODUCTS

2.1 TRAFFIC CONTROL DEVICES
A. All traffic control devices shall conform to the provisions in the California Manual of Traffic Control Devices and the agency having jurisdiction.

B. Included, but not limited to, are flag units, construction signs, channelizing devices, barricades, delineators, and lighting devices.

Page 337 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 01 55 26
C. A high-level warning device is required for use on major streets at the direction of the Engineer, when a lane is closed or work encroaches in a lane of traffic or when barricades are placed in a moving lane of traffic. A single barricade shall not be placed alone in the traveled way.

D. Use of flashing arrow signs is required on major (four or more lanes) streets for lane closures during hours of darkness and for all lane closures lasting more than two (2) hours.

E. All signs which are to convey their messages during darkness shall be reflectorized or illuminated.

F. No signs or supports shall bear any commercial advertising.

PART 3 EXECUTION

3.1 ACCESS TO ADJACENT PROPERTIES
A. Provide and maintain access to adjacent properties at all times. The Contractor shall notify homeowners/occupants along the proposed construction route.

3.2 STREET OR PERMANENT LANE CLOSURE
A. If closure of any street is required during construction, a formal application for a street closure shall be made to the authority having jurisdiction at least thirty (30) calendar days prior to the required street or permanent lane closure for approval and to determine necessary sign and detour requirements.

3.3 TRAFFIC COORDINATION WITH OTHER CONTRACTORS
A. The Contractor shall coordinate the traffic routing work with that of other forces working in the same or adjacent areas.

3.4 CONSTRUCTION PARKING CONTROL
A. Curb parking shall be removed in accordance with the Traffic Control Plan. Removal of curb parking shall be minimized.

B. The Contractor shall make arrangements directly with local authorities to keep the working area clear of parked vehicles.

C. The Contractor may prohibit stopping in parking lanes where and when necessary in order to gain access to the work to provide the required traffic lanes in city streets and parking areas.

D. The Contractor shall coordinate with the agency having jurisdiction and Sacramento County Sheriff for the location of ìNo Stoppingî and ìNo Parkingî signs.

E. At least seventy-two (72) hours in advance of construction, the Contractor shall furnish and place, where approved by the City and the Engineer, portable ìTOW AWAY ñ NO STOPPINGî signs. The dates and times of parking removal shall be posted on the signs.

Page 338 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 01 55 26
F. The Contractor shall notify the policing agency having jurisdiction of all parking violators who require tow away from construction areas.

G. Construction equipment not actively engaged in the work and employee vehicles shall not be parked in the vicinity of the work in such a manner as to further restrict or obstruct traffic flow. Vehicles and equipment in continuous or frequent use may be operated or parked in the same traffic lane as the work obstruction.

3.5 CONSTRUCTION SIGNAGE
A. All construction area signs shall conform to Section 10.06(F), Construction Signs, of the City General Provisions.

B. Sign spacing shall conform to the California Manual of Traffic Control Devices.

C. Signs normally shall be installed 14 calendar days before work is to commence and must be removed immediately after work is complete. If at any time a sign is not required, it shall be covered or removed.

D. The Contractor shall be responsible for the placement of advisory signs to inform the public of any street closure, detour, or construction affecting traffic at least 7 days before the closure or other significant disruption of normal traffic flow.

E. Existing roadside signs conflicting with the construction area signs shall be either removed and reset upon completion of work or securely covered.

3.6 ILLUMINATION
A. Provide sufficient visibility on a 24-hour basis to approaching traffic whenever a street is closed partially or completely. Ensure that sufficient illumination is provided by means of portable flashing beacons, floodlights, or other similar devices. Mount all lighting fixtures in a manner which precludes glare to approaching traffic.

B. Arrow boards or other traffic control devices and lighting which will operate outside of the normal working hours shall be battery-operated. The use of gas-fired generators during nonworking hours will not be allowed.

3.7 FLAGGING
A. Flaggers shall be required:

1. When workers or equipment intermittently block a traffic lane

2. When trucks or equipment enter or leave the work site from an adjacent traffic lane.

3. Where Plans or permits allow the use of one lane for two directions of traffic.

4. Wherever the safety of the public and/or workers determine there is a need.

B. Flagging shall be carried out in accordance with California Manual of Uniform Traffic Control Devices. All flagging costs shall be considered as included in pay items for traffic control.

Page 339 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 01 55 26

3.8 PEDESTRIAN SAFETY
A. The Contractor shall maintain safe and adequate pedestrian zones and public transportation stops as well as provide pedestrian crossings at intervals not to exceed 300 feet within the work zone.

B. When the construction area crosses a crosswalk, the crosswalk shall be barricaded and signed accordingly.

3.9 TRAFFIC HANDLING AT SPECIFIC LOCATIONS
A. The Contractor shall maintain the full visibility and function of all school safety signing and striping within the work area. Additional temporary safety striping and signage shall be installed if deemed necessary by the agency having jurisdiction.

3.10 VEHICULAR AND PEDESTRIAN RAMPS
A. The Contractor shall provide and maintain ramps as shown on Plans or required by the Resident Engineer. Pedestrian ramps shall meet Americans with Disabilities Act requirements.

3.11 BARRICADING OPEN TRENCHES
A. Any excavation permitted by the City to be left open shall be barricaded with Type II or Type III barricades with flashers. Signs stating ìOPEN TRENCHî shall be posted when requested by the City. All open excavated areas shall be barricaded with at least two (2) Type III barricades at the end of the excavation that faces oncoming traffic.

B. Any excavation within four (4) feet of the traveled way, not protected by K-rail or a similar traffic control barrier approved by the City, shall be backfilled at the end of the work shift or plated.
** END OF SECTION **

Page 340 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 01 78 23
SECTION 01 78 23

OPERATING AND MAINTENANCE DATA
PART 1 GENERAL

1.1 SUMMARY
A. Contractor shall supply Operations and Maintenance (O&M) Manuals for equipment as specified in other parts of the Project Documents.

1.2 DESCRIPTION
A. The Contractor shall provide four (4) sets of operating and maintenance instructions for all equipment and devices furnished under this contract and one (1) pdf set. The operating and maintenance material supplied shall be original printed copies of manufacturer's brochures and/or manuals. Photocopied material will not be acceptable.

Operating and maintenance instructions for each item of equipment and each equipment assembly shall consist of:

1. Names and addresses of manufacturer, nearest representative of manufacturer, and nearest supplier of manufacturer's equipment and parts

2. For equipment requiring lubrication, the manufacturer's recommended lubricants and lubrication schedule.

3. For equipment containing integral electrical controls, diagrams showing internal and connection wiring.

4. Specified operating and maintenance information. This information shall include, but not necessarily be limited to, the following items:
(a) Equipment data: The Contractor shall provide a good quality photocopy of the Equipment Maintenance Summary sheets for review and shall make corrections to the originals as noted in the submittal review comments. Sufficient copies of the blank forms will be furnished by the City.
(b) Start-up procedures: These instructions shall include equipment manufacturer's recommendations regarding installation, adjustment, calibration and trouble-shooting.
(c) Operating procedures: These instructions shall include the equipment manufacturer's recommended step-by-step procedures for starting, operating and stopping the equipment under all modes of operation. (d) Preventive maintenance procedures: These instructions shall include the equipment manufacturer's recommendations regarding the steps and schedules to be followed in maintaining the equipment.
(e) Parts list: This list shall include generic title and identification number of each component part of the equipment.
(f) Exploded views: These shall be provided where appropriate.

Page 341 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 01 78 23
(g) Spare parts list: This list shall include the manufacturer's recommendations of number of parts that should be stored by the City. (h) Overhaul instructions: These instructions shall consist of the manufacturer's directions for the disassembly, repair and reassembly of the equipment.

1.3 SUBMITTAL PROCEDURE
A. Operating and maintenance (O&M) instructions shall be submitted to the Cityís Representative accompanied by the submittal transmittal form described in Section 01 33 00 ñ Submittal Procedures.

B. Required submittals:

1. Initial Submittal: One (1) copy of O & M Manual shall be submitted for approval.

Initial O&M submittal may be hard copy or PDF format.

2. Intermediate Submittal: One (1) copy of revised O & M Manual shall be submitted for approval. Intermediate O&M may be hard copy or PDF format.

3. Final Submittal: Once approved, submit four (4) paper copies and one (1) PDF.

4. The submitted O&M Manuals shall have a separate submittal numbering system from the general equipment and material submittals required to confirm conformance with the design specifications.

C. PDF Format shall be manufacturerís data converted directly to PDF. Scanned PDF information is not acceptable unless approved by the Cityís Representative.

1. PDF documents shall be bookmarked, indexed and in searchable format.

D. For ease of identification, each manufacturer's brochure and manual shall be appropriately labeled with the equipment name, equipment number and specification number, as it appears in the contract documents.

E. The information shall be organized in binders in numerical order by the specification section numbers assigned in the contract documents. The binders shall be provided with a table of contents and tab sheets to permit easy location of desired information. Each numerical section shall contain a complete itemized data list with equipment name and equipment number for the information contained in that section. Binders shall be threering with clear vinyl pockets on the front and spine. The binder title shall be clearly visible on the spine and the front cover.

F. The following procedures shall be used:

1. Contractor shall include in each O&M submittal a good quality photocopy of associated Equipment Maintenance Summary sheets, for each specification section for review.

2. Submittals will be returned with a review sheet and comments.

3. Contractor shall resubmit, if requested by the Cityís Representative, and retain all copies of approved submittals until all sections have been approved.

Page 342 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 01 78 23

4. When all sections have been approved, Contractor shall organize and bind the manuals for all the sections of the contract specifications according to the above instructions and submit one complete set of O&M Manuals for final review.

Contractor shall submit separately and unbound the completed original Equipment Maintenance Summary sheets.

5. Final review will be for the organization and binding of a complete set of manuals as specified and will not include review of previously approved material.

6. When the complete set is approved, the Contractor shall submit four (4) complete sets to the Cityís Representative as approved and specified.

G. If the manufacturer's standard brochures and manuals are used to describe operating and maintenance procedures, such brochures and manuals shall be modified to reflect only the model or series of equipment used on this project.

1. Clearly mark or annotate the actual model supplied for the project.

2. Extraneous material shall be crossed out neatly or otherwise annotated or eliminated.

1.4 FIELD CHANGES
A. Following the acceptable installation and operation of an equipment item, the item's operating and maintenance instructions, including drawings, shall be modified and supplemented by the Contractor to reflect any as-built conditions, field changes or information required by field conditions.

PART 2 MATERIALS (NOT USED)
PART 3 EXECUTION (NOT USED)
**END OF SECTION**

Page 343 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 02 41 00
SECTION 02 41 00

DEMOLITION
PART 1 GENERAL

1.1 SUMMARY
A. Demolition and site preparation includes all clearing, grubbing, facility abandonment, and demolition Work.

1.2 JOB CONDITIONS
A. The Contractor shall determine the actual condition of the site as it affects the Work.

1.3 QUALITY ASSURANCE
A. General: All work shall be performed in accordance with the local building codes, State Industrial Safety Orders and requirements of the Occupational Safety and Health Act requirements.

B. Schedule: Demolition must be scheduled to allow all existing roadways and utilities to remain in continuous operation. No interruption in operation will be permitted without previous authorization from the Cityís Representative.

C. Protection

1. Demolition shall be performed in such a manner as to not harm adjacent structures, equipment, existing landscaping or natural vegetation. (a) The Contractor shall assume full responsibility for such disturbance. (b) All costs of any such repair, rehabilitation, or modifications shall be borne by the Contractor.

2. The Contractor shall provide such protection as may be required to transfer material to the ground.
(a) Throwing, dropping or permitting the free fall of material and debris from heights which would cause damage to other work, existing structures, or equipment; undue noise or nuisance; or excessive dust will be expressly prohibited.

PART 2 PRODUCTS

2.1 MATERIAL FOR FACILITY ABANDONMENT
A. Controlled Low Strength Material (CLSM) for abandonments shall be 1 ½ - 90 pound sack of Portland Cement per cubic yard of sand slurry. CLSM shall have an unconfined compressive strength of 100 psi or less.

Page 344 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 02 41 00
PART 3 EXECUTION

3.1 GENERAL
A. Coordinate with City to properly remove or abandon in place unused existing City utility service lines discovered that were left in place by others.

B. Contact utility companies for removal, abandonment, adjustment or relocation of their facilities.

C. See Contract Drawing for abandonment and removal of water facilities.

D. Contractor is responsible for verifying the location of any existing utilities.

E. Maintain and provide redline improvement plans to the engineer of record to identify all facilities that have been abandoned in place or removed for record drawings.

F. The Contractor shall adhere to all demolition and site preparation requirements set forth in the City Standard Specifications.

G. The Contractor shall notify the Cityís Representative when demolition of existing is completed and dispose of refuse materials in an appropriate manner.

3.2 PERFORMANCE
A. Clearing and Grubbing

1. The site of all open-cut excavations and areas to be cleared as indicated on the Plans shall be cleared and grubbed prior to excavation.

B. Equipment and Piping Removal

1. All equipment and piping to be removed shall be properly disconnected from structures, piping, electrical, and instrumentation systems.

2. The Contractor shall do all resurfacing and other work as necessary to comply with the above requirements.

C. Water Main Abandonment

1. Excavate to expose water mains and/or service lines as needed for work to be performed by the City. City crews to perform City water mains operation of isolating necessary valves. Coordinate with Public Works Inspector in advance to schedule City's work.

2. Remove the valve can and riser pipe to valve top. If the valve operating nut is less than the 18-inches below grade then the valve bonnet must be removed to acquire the necessary clearance for proper abandonment.

3. Backfill and restore the roadway in accordance with City Standards and the Contract Documents when work on the water main, valve or service is complete.

Page 345 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 02 41 00

4. For fire hydrant abandonment: remove the hydrant bury, breakoff rise, and any other spools or pipe 24-inches below grade. The bury is to be capped or plugged. Fire Hydrant shall be returned to the City Corp Yard.

5. Fill all water mains and Fire Hydrant laterals to be abandoned-in-place with CLSM/concrete mix within the public right-of-way.

6. For service lines less than 4" diameter: Remove or abandon unused existing water service lines in place. Any portion of the service line that is less than 3 feetí below grade shall be removed to the city's satisfaction.

7. Ensure that all pipelines to be abandoned have a minimum of a three foot separation from the live portion of the water main (a section removed) line for pipes 4 inches" and larger in diameter. The end of the pipe shall be securely sealed at the pipe ends by installing a watertight plug of concrete not less than one foot thick.

8. Coordinate with Public Works Inspector to ensure all domestic, fire and irrigation meters are removed and salvaged EXCLUSIVELY by the City and protected in place until City crews have removed them. After City removes the meters, remove entire box/vault and properly complete the backfill in accordance with City standards and requirements.

D. Pavement Removal

1. All pavements and concrete pads shall be saw-cut on a neat line at right angles to the curb or concrete face.

E. Utility Interference

1. Where existing utilities interfere with the prosecution of the work, the Contractor shall temporarily relocate the utilities out of the construction projectís right of way and restore in kind prior to final backfilling efforts.

3.3 SALVAGE
A. The City has the right to salvage any items identified within the project vicinity.

B. The Contractor shall notify the Cityís Representative five days prior to any salvage or demolition work.

1. The Cityís Representative will mark items to be salvaged.

2. The Contractor shall be responsible for properly disconnecting, removal from their foundations, cleaning and storing salvaged items. Salvaged items shall be delivered by the Contractor to a storage location designated by the City.

3. All drop offs must be coordinated with the City.

3.4 REMOVED MATERIAL AND DEBRIS
A. Where Contractor is directed on the Drawings to ìDemolishî or ìRemoveî material or facilities it is understood that the material will be removed and disposed of offsite unless specifically stated otherwise or directed by the Cityís Representative.

Page 346 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 02 41 00
B. All removed material not designated for salvage and all debris shall become the property of the Contractor and shall be removed from the site.

C. Materials and debris generated by demolition activities shall not be allowed to accumulate. Debris shall be removed daily and disposed of in a manner allowed by law.

3.5 BACKFILL
A. Holes or depressions in the ground remaining after demolition of structures, pipelines, or equipment shall be filled with compacted backfill materials as specified in Section 31 23 00 ñ Excavation and Fill.

3.6 RESTORATION
A. Restore adjacent structures and facilities damaged during demolition or other construction to original or better condition.
** END OF SECTION **

Page 347 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 02 82 33
SECTION 02 82 33

REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIALS
PART 1 GENERAL

1.1 SUMMARY
A. This specification section includes:

1. Safe exposure and removal of buried asbestos cement pipe (ACP, commonly referred to as ìtransite) where encountered; the asbestos is not anticipated to be friable.

2. Handling and storage of ACP (or ACM, ìasbestos-containing materialî)

3. Transport and disposal of ACP

4. Decontamination of equipment

5. Confirmation sampling and report.

1.2 CODE COMPLIANCE AND REGULATIONS
A. The Contractor will assume full responsibility and liability for compliance with all applicable Federal, State, and Local regulations. Specifically, regulations pertaining to work practices, protection of workers, visitors to the site, persons occupying areas adjacent to the site, hauling, and disposal. As required by all applicable Federal, State and local regulations, the Contractor is responsible for providing medical examinations, and maintaining medical records of personnel. shall determine the actual condition of the site as it affects the Work.

B. The Contractor shall comply with all pertinent laws, rules, and regulations existing at the time of the work including, but not limited to the following:

1. Federal Regulations
(a) United States Environmental Protection Agency (EPA), Title 40, Code of Federal Regulations (CFR), Part 61, National Emission Standards for Hazardous Air Pollutants (NESHAP), National Emission Standard for Asbestos (40 CFR, Part 61, Subpart A & M).
(b) 40 CFR 268, Land Disposal Restrictions
(c) 40 CFR 763 including all Appendices, Asbestos Hazard Emergency Response Act (AHERA)
(d) 49 CFR Parts 171 through 180 ñ Department of Transportation (DOT), Hazardous Substances
(e) 29 CFR 1926.1101 and 29 CFR 1910.1001 - Occupational Exposure to Asbestos
(f) 29 CFR 1910.134 and 42 CFR Part 84, Respiratory Protection

Page 348 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 02 82 33
(g) 29 CFR 1910.1200, Hazard Communication
(h) 29 CFR 1910.145, Accident Prevention Signs and Tags (i) 29 CFR 1910, Subpart I, Personal Protective Equipment (j) 29 CFR 1910.1020, Access of Employee Exposure/Medical Records

2. State and Local Regulations
(a) The State of California, Business and Professions Code, ß 7058.5 (Asbestos Certification) and other corresponding regulations in the California CONTRACTORs State License Board, Title 16, California Code of Regulations, Division 8 (16 CCR Division 8).
(b) Title 8 CCR, Section 1529, Asbestos in Construction (c) Title 8 CCR, Section 341.6, Registration, Asbestos-Related Work (d) Title 8, Division 1, Chapter 4, Division of Industrial Safety (1) Title 8 CCR 3203, Injury and Illness Prevention Program (e) Title 8 CCR 5194, Hazard Communication
(f) Title 22 CCR 66699, Persistent and Bio-accumulative Toxic Substance (g) Title 22 CCR, Hazardous Waste Handling
(1) Health and Safety Code, Section 25249.5 and 25249.6 (h) California Labor Code, Sections 6501.5, 6501.7, 6501.8, and 6501.9. (i) Bay Area Air Quality Management District (BAAQMD): Regulation 11 Rule 2
(j) City of Milpitas or Santa Clara County, Fire Code, whichever is applicable,

3. Miscellaneous Standards and References
(a) Underwriters Laboratories (UL) Standard 586, 2009 High Efficiency, Particulate, Air Filter Units.
(b) ANSI/ASSP Z88.2-2015, Practice for Respiratory Protection. (c) National Fire Protection Association (NFPA), Standard 10, Standard for Portable Fire Extinguishers.

Page 349 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 02 82 33

1.3 SUBMITTALS
A. Contractor shall submit the following documentation prior to the start of work:

1. A detailed job-specific plan of the work procedures to be used for the work to be completed. The plan shall be compliant with this specification and regulations. (Contractorís ACM Work Plan)

2. A copy of the State Contractorís Licensing Board Asbestos Certification in accordance with the California Business and Professional Code, ß 7058.5.

3. Proof that the Contractor possesses a current California Class C Asbestos Removal License.

4. A copy of the Contractorís current California DOSH registration to conduct asbestos-related work.

5. Proof of asbestos supervisor and worker training. Include a copy of the most current refresher training certificate as issued by a DOSH-approved training provider.

6. Physicianís written medical opinion, current to within one year that contractorís employees can wear respiratory protection.

7. Documentation of respirator fit-testing for all contractorís employees and agents who are required to wear a respirator. Fit-testing shall be current within one year.

8. Documentation of medical surveillance required in CCR Title 8, Sections 1529 (m) and 1532.1 (j).

9. If rental equipment is to be used during asbestos handling and disposal, a copy of the written notification concerning the intended use of the equipment that was furnished to the rental agency.

10. Submit any current and valid licenses, permits, and notices required by federal/state/local regulations and proof of timely transmittal of notices to the respective agency requiring the notices including, but not limited to:
(a) California Division of Occupational Safety and Health in accordance with Title 8, Sections 1529 and 1532.1 (p).
(b) Bay Area Air Quality Management District (BAAQMD) in accordance with Regulation 11 Rule 2.
(c) Proof of BAAQMD permits for HEPA-filtered air filtration machines.

11. An emergency preparedness plan as specified in Paragraph 1.7 below.

12. Safety Data Sheets (SDS) for solvents, caustic stripping agents, paints, encapsulants, adhesives, detergents, and replacement materials, as necessary.

B. Contractor shall submit the following information on a daily basis during progression of the work or as requested:

Page 350 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 02 82 33

1. Copies of daily project site entry logbooks with information on worker and visitor access.

2. Logs documenting filter changes on respirators, HEPA vacuums, differential pressure air filtration devices, and other engineering controls.

C. Contractor shall submit the following close-out information following completion of the Project:

1. Any documentation listed in Paragraphs 1.3.A or 1.3.B above not collected during the Project.

1.4 QUALITY ASSURANCE
A. Qualifications:

1. Qualifications of Contractor (or Subcontractor as applicable):
(a) Work performed under this Section shall be by a single Contractor. (b) The Contractor shall have a minimum of five (5) yearsí experience as an approved asbestos abatement contractor unless approved by the Engineer to have less than five (5) yearsí experience. If requested, the Contractor shall provide the names and locations of 5 projects of similar size and scope that he has completed within the previous five years. (c) Contractor must hold a current and valid asbestos license issued by the California Contractorís State Licensing Board (CSLB).
(d) Contractor must hold a current and valid Certificate of Registration for Asbestos-Related Work issued by the California Department of Industrial Relations, Division of Occupational Safety and Health (Cal/OSHA).
(e) Contractor must hold all insurance and bonds as required by other sections of this specification and maintain as valid and current for the duration of the project.

2. Qualifications of Asbestos Abatement Personnel:
(a) All work shall be completed utilizing fully qualified persons who are trained, experienced, and knowledgeable in the proper techniques and procedures for asbestos abatement activities covered by this Section. (b) Asbestos Workers: All workers performing asbestos related work shall be currently certified as AHERA asbestos workers.
(c) Asbestos in Construction Contractor Supervisor: The Contractorís Supervisor shall be identified in writing and currently certified as an AHERA Asbestos Contractor Supervisor.

Page 351 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 02 82 33

1.5 NOTICES
A. Post a list containing the names, addresses, and telephone numbers of Contractor, and emergency medical services.

B. Additional postings shall include:

1. Visitor Entry and Exit Log.

2. Employee Daily Sign in Log.

3. Entry and Exit Procedures

1.6 SITE SECURITY
A. Access to the work areas shall be limited to authorized, trained and properly equipped personnel, including Contractor, Subcontractors, Contractor's employees, and regulatory agency inspectors.

B. Entry into the work area by unauthorized individuals shall be reported immediately.

C. Contractor shall be responsible for Project site security during abatement operations in order to protect work efforts and equipment.

1.7 EMERGENCY PLANNING
A. Emergency planning and procedures shall be developed by Contractor prior to abatement initiation.

B. Emergency procedures shall be in written form and prominently posted. Contractor shall ensure that all persons entering the work area read these procedures and understand the Project site layout, location of emergency exits and emergency procedures.

C. Emergency planning shall include considerations of fire, explosion, electrical hazards, slips, trips and falls, confined spaces, and heat related injury. Written procedures shall be developed and employee training in procedures shall be furnished by Contractor.

D. Employees shall be trained in evacuation procedures in the event of work place emergencies.

1. For minor injuries and illness, employees injured or otherwise incapacitated shall decontaminate following normal procedures with assistance from fellow workers, if necessary, before exiting the work area to obtain proper medical treatment.

2. For serious injury or illness, worker decontamination shall take least priority.

After stabilizing the injured worker, remove him from the work area and seek proper medical treatment.

3. Telephone numbers of all emergency response personnel shall be prominently posted in the clean and equipment rooms.

Page 352 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 02 82 33
PART 2 PRODUCTS

2.1 MATERIALS
A. Contractor must supply abatement materials and equipment that are undamaged, and in serviceable condition. Only materials and equipment that are recognized as being suitable for the intended use, by compliance with appropriate standards, will be utilized.

B. All plastic, spray-on strippable coatings and structural materials used shall be UL certified as fire retardant or non-combustible. SDS for fire retardant materials shall be made available upon request.

C. Polyethylene sheeting utilized for worker decontamination units and barriers shall be black in color and shall be a minimum of six mils thick.

D. For disposal of asbestos waste, Contractor shall furnish EPA and OSHA labeled 6- mil polyethylene disposal bags.

E. Stick-on hazardous waste labels as per EPA or Cal-OSHA regulations.

F. Contractor shall supply, and post warning signs as required by applicable Cal-OSHA regulations. Signs should be printed in English and Spanish.

G. All replacement materials shall be delivered in the original packages, containers, or bundles bearing the name of the manufacturer and brand name.

H. Damaged, deteriorating or previously used materials shall not be used and shall be removed from the Project site.

2.2 EQUIPMENT
A. General:

1. CONTRACTOR shall provide first aid supplies that comply with governing regulations, and recognized recommendations within the construction industry.

In addition, the Contractor Supervisor shall have current first aid training, including Cardiopulmonary Resuscitation (CPR).

2. Respirators shall be furnished to the abatement workers by CONTRACTOR.

The type of respirator to be furnished shall be determined by air sampling CCR Title 8, Sections 1529 and 1532.1. The respirators shall have been tested and approved by National Institute of Occupational Safety and Health (NIOSH) for use in contaminated atmospheres.

3. Full body disposable protective clothing, including head, body, and foot coverings shall be furnished to workers and visitors in sizes adequate to accommodate movement without tearing.

4. Additional safety equipment (e.g. hard hats meeting the requirements of ANSI Standard Z89.1-1997 or later, eye protection meeting the requirements of ANSI Standard Z87.1-1989, safety shoes meeting the requirements of ANSI Standard Z41.1-2005, disposable gloves), as necessary, shall be furnished to all workers and authorized visitors.

Page 353 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -7- 02 82 33

5. Non-skid footwear shall be furnished to all abatement workers. Disposable clothing shall be adequately sealed to the footwear to prevent body contamination

6. Provide NIOSH-approved disposable respirator cartridges capable of filtering dusts, mists, and radionuclides.

B. Removal:

1. Filters on vacuums and exhaust equipment shall be HEPA filters and UL 586 labeled.

2. Sprayers are required with pumps capable of providing 500 pounds per square inch (PSI) at the nozzle tip at a flow rate of 2 gallons per minute for spraying amended water.

3. A sufficient supply of HEPA filtered vacuum cleaning systems shall be furnished during cleanup.

PART 3 EXECUTION

3.1 PREPARATION
A. General:

1. Secure the Work Area:
(a) Provide and maintain temporary partitions to prevent spread of dust, fumes, and odors.
(b) Demarcate the regulated work area, as required by OSHA regulation 29 CFR 1926.1101, by posting warning signs
(c) Provide labels affixed to all asbestos waste containers, as required by OSHA regulation 29 CFR 1926.1101
(d) Do not block, or reduce width, of egress to exits.
(e) Conduct operations with minimum interference to corridors, exits, and public thoroughfares.
(f) Path of travel for debris removal shall be maintained dust free and clean at all times.
(g) Water used during this project shall be collected and prevented from entering storm water drains.
(h) Eating, drinking, smoking, chewing tobacco or gum, or applying cosmetics is prohibited in the work area.

Page 354 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -8- 02 82 33

3.2 PERFORMANCE
A. Clearing and Grubbing

1. The site of all open-cut excavations and areas to be cleared as indicated on the Plans shall be cleared and grubbed prior to excavation.

B. Piping Excavation

1. Contractor shall carefully excavate to locate buried ACP using methods that will not destroy the pipe and potentially make asbestos friable. Methods such as vacuum excavation, use of tools, or other means shall be chosen as appropriate.

2. Upon exposure, qualified personnel shall assess the pipe to determine if it might be in a condition that could contain friable asbestos.

3. Fully expose the portions of ACP to be removed.

4. Where possible, do not break pipe, fittings, or couplers. Breakage of couplings is preferred should no other viable option exist to remove pipe.

5. When pipe is removed, removed entire lengths of pipe to the next joint necessary to achieve the work. Except as noted on drawings r as directed by Engineer, only remove ACP necessary to accomplish the work.

6. Where bells exist on ACP that must be removed to connect CP to remain in service with new PVC pipe or ductile iron fittings, use a snap tool or least destructive method to leave a clean surface and minimize potential for release of friable material.

7. Upon removing asbestos-containing coupling, pipe, or other materials, immediately separate, place in appropriate double bag with 6-mil polyethylene sheeting to yield a total of at least 12-mil, the asbestos pipe in the trench or immediately when it comes out of the trench. Seal and label as required by EPA Regulation 40 CFR 61.150 (a)(1)(iv) or OSHA requirement 29 CFR 1926.1101(k)(8), and remove from site in a protected area.

8. City shall sign all manifests as generator of the waste.

C. Storage

1. Store all ACP and other asbestos-containing materials in accordance with all state and federal regulations.

2. Removed ACP shall be stored in a clearly-marked area protected from accidental breakage of the pipe with substantial barriers such as k-rail or within conex-type boxes.

D. Transport and Disposal

1. ACP shall be transported for disposal in accordance with all state and federal regulations. Transporting company shall have any required licenses and use appropriate equipment to load, transport, and dispose of ACP.

Page 355 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -9- 02 82 33

2. Dispose of ACM at a California disposal facility operating under a RWQCB permit to accept asbestos waste. Notify the facility at least 5 business days before the delivery of ACM.
(a) Generate manifests at the time of transfer that include the name of the transporter, asbestos transporter license number, and the name of the permitted landfill where the AC pipe and ACM will be buried.

3. City shall sign each disposal manifest.

4. Contractor will pay for all disposal ìtipping feesî charged by landfill accepting the waste.
(a) Provide all associated paperwork from the landfill within 48 working hours of disposal.

E. Field Quality Control

1. In addition to having appropriately trained personnel, Contractor at all times shall have a Competent Person for ACP on site whenever potential to encounter ACP exists.

F. Abandonment of AC Pipes

1. The Contractor is responsible for isolating any existing mains/laterals to remain in place by capping, plugging, and blocking as necessary. The opening of an abandoned AC pipe shall be blocked off by manually forcing cement grout or concrete into and around the openings in sufficient quantity to provide a permanent watertight seal. Abandonment of AC pipes are considered subsidiary to the work required and no direct payment will be made.

G. Decontamination

1. If required, the Contractor shall decontaminate equipment and personnel impacted by removal of asbestos contaminated particles. The Contractor will be responsible for proper decontamination of all materials which may have been contaminated. It is the responsibility of the Contractor to dispose of all incident residuals and materials used for decontamination in accordance with all regulations.
** END OF SECTION **

Page 356 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 31 11 00
SECTION 31 11 00

CLEARING AND GRUBBING
PART 1 GENERAL

1.1 WORK INCLUDED
A. Clearing and grubbing consists of furnishing transportation, labor, materials, and equipment to:

1. Remove and dispose of all rubbish, debris, and other objectionable material from within the limits of the project as specified.

2. Strip the entire area within the limits of work of trees, shrubs, weeds, and other vegetative growth of any nature, unless otherwise shown as Protect In Place, and disposal of same.

3. Grub the entire area within the limits of work of all roots and vegetative material to the full depth of the root system, and disposal of same.

4. Remove existing pavement markers, pavement markings, traffic lines, pavement legends and weeds along cracks, joints, and gutter lip.

5. Provide dust alleviation and control during the course of the work.

6. Comply with any required abandonment of system facilities, including cutting, capping and slurry filling of abandoned pipelines.

7. Provision of all materials, equipment and apparatus not specifically mentioned herein or noted on the plans, but which are obviously necessary to complete the work specified.

8. Comply with any required salvage of existing facilities.

B. Implementing measures to prevent air pollution during clearing, grubbing and during construction activities in accordance with Federal, State, and local regulations.

1.2 REFERENCES
A. State of California Department of Transportation Standard Specifications (SS):

B. California Air Resources Board, CARB 2003a. California Ambient Air Quality Standards PART 2 PRODUCTS
A. Water shall be available to the Contractor for dust control as specified herein. Dust suppressants other than water shall not be utilized.

B. Temporary fencing shall be heavy-duty, four (4) foot high orange plastic safety fencing as produced by Uline, Model No. S22226, or approved equal.

PART 3 EXECUTION

3.1 PERFORMANCE

Page 357 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 31 11 00
A. Clearing and grubbing shall be in accordance with all applicable state and local requirements.

B. Clearing

1. Remove and dispose of shrubs, brush, limbs, and other vegetative growth.

Remove all evidence of their presence from the surface, including sticks and branches greater than two (2) inches in diameter or thickness. Remove and dispose of trash piles, rubbish, and fencing.

2. Protect trees, shrubs, vegetative growth, and fencing not designated for removal.

C. Grubbing

1. Remove and dispose of wood or root matter below the ground surface remaining after clearing, including stumps, trunks, roots, or root systems greater than 2 inches in diameter or thickness, to a depth of 12 inches. Weed removal shall be accomplished by method(s) that result in complete removal of the weed. Method used must be approved by the Engineer. Surface and crack cleaning shall be accomplished by sweeping, and not by air blowers.

D. Stripping

1. Remove and dispose of all organic sod, topsoil, ash, grass and grass roots, and other structurally unsound material remaining after clearing and grubbing from the areas designated to be stripped. The site shall be stripped to such greater depth, as the Engineer or the project geotechnical engineer may consider necessary to remove materials that, in their opinion, are unsatisfactory. The stripped material shall either be removed from the site or stockpiled for reuse later as topsoil where approved by the Engineer, but none of the stripped material may be used for engineered fill.

2. Remove and dispose of all asphalt, aggregate, concrete and other inorganic materials within the limits of construction. Remove all evidence of their presence from the project site.

E. Trees and Shrubbery

1. Preserve all trees to the maximum extent possible except those that are specifically designated for removal on the Plans.

2. It is possible that existing trees, shrubbery, and other vegetative material are not shown on the Plans. Inspect the site to determine the nature, location, size, and extent of vegetative material to be removed or preserved, as specified herein. Coordinate with City Arborist to determine the necessary plan for protection or removal for all trees not shown on the Plans.

3. The Contractor shall be responsible for the placing, maintaining, and removal of any orange, temporary construction fencing as shown on the Plans or that may be necessary along the line of work or around all trees to preserve and protect all trees to the maximum extent possible and delineate the construction area.

Page 358 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 31 11 00

4. If work will be continued within one foot (1í) of any tree dripline, Contractor must contact City Arborist and continue work under their supervision which may include conducting only hand tool work within their driplines.

5. Contractor shall trim overhanging limbs that may be in conflict with trenching and other construction activities. Tree, roots, and bush pruning shall be performed by a certified arborist and in accordance with "Pruning Standards," published by the Western Chapter of the International Society of Arboriculture.

The certified arborist shall be approved in advance by the Engineer, and all pruning shall be done as directed by and in the presence of the City Arborist and Engineer. Tree limbs damaged by Contractor activities shall be trimmed by certified arborist as described above.

6. Where trees are removed, the soils loosened by the roots shall be overexcavated at least to the bottom of the disturbed zone and to the width of the equipment.

F. Spoil resulting from clearing, grubbing, and stripping operations shall be removed from the entire limits of work and properly disposed of by the Contractor. Materials resulting from clearing, grubbing, and stripping operations shall become the property of the Contractor, to be properly removed from the work site and disposed of from the project site in a lawful manner, at no additional expense to the contract.

G. Furnish, install, maintain, and operate necessary control measures and other equipment necessary to prevent dust. Temporary measures shall be to Contractorís own design and Contractor shall be solely responsible for risks related to the management of dust control during construction.
**END OF SECTION**

Page 359 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 31 23 00
SECTION 31 23 00

EXCAVATION AND FILL
PART 1 GENERAL

1.1 SUMMARY
A. This section specifies all operations necessary to the excavation, loosening, filling, grading, hauling, compacting, removal, and control of earth, rock or other unspecified material for the construction of project facilities. This section also includes the quality assurance and placement requirements for all related backfill materials and their respective standards.

1.2 REFERENCES
A. The following documents are a part of this section insofar as they are specified and modified herein. In case of conflict between the requirements of this Section, and the following documents, the requirements of this section shall prevail.

Reference Title
California Test Method 217 Method of Test for Sand Equivalent ASTM C136 Method of Test for Sieve or Screen Analysis of Fine and Coarse Aggregates
ASTM D420 Standard Recommended Practice for Investigating and Sampling Soil and Rock for Construction Purposes
ASTM D1556 Method of Test for Density of Soil in Place by the SandCone Method ASTM D1557-12 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ftlbf/ft3 (2,700 kN-m/m3)) ASTM D2049 Standard Test Method for Relative Density of Cohesionless Soils
ASTM D6938-17ae1 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods
(Shallow Depth)
ASTM D2419 Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate
ASTM D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
Caltrans 2023 Standard Specifications
B. The Contractor shall also utilize the City Standard Specifications for construction requirements not listed herein.

1.3 DEFINITIONS

Page 360 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 31 23 00
A. Compaction: The degree of compaction is specified as percent of relative compaction.

The relative compactions refer to the maximum relative densities of dry soil obtainable at optimum moisture content.
(a) In-place density of compacted materials determined in accordance with ASTM D 6938.
(b) Maximum density obtained in laboratory when tested in accordance with ASTM D 1557-12.

B. Excavation Slope: Excavation slope shall be defined as an inclined surface formed by removing material from below existing grade.

C. Embankment Slope: Embankment slope shall be defined as an inclined surface formed by placement of material above existing grade.

1.4 NOT USED

1.5 PERFORMANCE REQUIREMENTS
A. Where mud or other soft or unstable material is encountered, remove such material, and refill space with stabilization material approved for use by the Engineer.

B. The Contractor shall obtain acceptable import material from other sources if surplus or borrow materials obtained within project easements do not conform to specified requirements or are not sufficient in quantity.

C. No extra compensation will be made for hauling, fill materials, nor for water required for sufficient compaction.

1.6 SUBMITTALS
A. Submit current technical data for each type of material specified to prove compliance with the specifications in accordance with the requirements of Specification Section 01 33 00 ñ Submittal Procedures.

B. Contractor shall submit an excavation and backfill plan detailing hauling truck staging and routes, expected traffic impacts, proposed equipment and machinery, anticipated construction durations per section, temporary excavation stockpiling areas, and backfilling process. Excavation and backfilling plan shall be separate but consistent with statements provided in the Contractorís shoring plan.

C. Mix Designs for all fill materials indicating referenced testing standards, gradations, Atterberg limits, specific gravity, sand equivalent, R-value, durability, moisture content.

D. Submit documentation related to Contractorís proposed testing laboratory, capabilities, and equipment.

E. Submit certified test reports of all specified tests performed by the Contractor.

1. Test reports shall be signed and sealed by a registered Geotechnical Engineer who practices geotechnical engineering in the State of California.

1.7 QUALITY ASSURANCE

Page 361 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 31 23 00
A. All soils testing will be done by a testing laboratory of the Cityís choice and expense except as otherwise noted.

B. The Cityís Representative will take samples and perform tests for compliance with the specifications including Atterberg limits, specific gravity, sand equivalent, R-value, durability, moisture content, gradation, compaction, and density tests during placement of backfill materials to check compliance with these specifications.

C. The Contractor shall remove surface material at locations designated by the Cityís Representative and provide such assistance as necessary for sampling and testing.

D. The Cityís Representative may direct the Contractor to construct inspection trenches in compacted or consolidated backfill to determine that the Contractor has complied with these specifications.

E. The City will bear the costs for sampling and testing specified in this Paragraph. The Contractor shall pay costs associated with retesting due to the Contractorís failure to comply with the specifications.

F. Sequencing and Scheduling

1. If necessary, stockpile excavated material in order to utilize it in separate locations. The Contractor shall not stockpile excavation spoils in an active roadway at any time during the project.

2. Perform excavation and backfilling in a manner that encourages drainage at all times.

PART 2 PRODUCTS

2.1 FILL MATERIALS
A. Water for earthwork compaction and dust control shall be imported, or from City approved water source.

B. Unless noted herein, fill materials shall be utilized in accordance with requirements shown on the Contract drawings and detailed in the City Standard Specifications.

Minimum trenching dimensions and elevations are reflected in the Contract documents.

C. The Contractor shall not repurpose excavation spoils at any time during the utility trench backfilling process unless otherwise approved by the Engineer of Record and designated as a select fill.

D. Classification of Excavated Materials:

1. Rock:
(a) Earth encountered during the course of excavation which is sufficiently hard to cause refusal to equipment specified below shall be deemed inexcavatable and therefore classified as ërockí. Earth deemed inexcavatable shall be removed by substantial means such as reciprocating hydraulic hammers and shall conform to this specification.

Page 362 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 31 23 00
(b) Refusal to be considered as the inability of the following equipment to excavate material as caused by the hardness of the earth: Tractor mounted excavator, with minimum operating weight of 85,000 lbs and using a single ripper tooth. Refusal shall be demonstrated to Engineer prior to earth being deemed inexcavatable and therefore defined as rock subject to this rock clause and unit price compensation. (c) All rock excavation shall be under one classification. This classification shall include solid ledge rock in its natural location that requires systematic quarrying or drilling, and also boulders that exceed 0.25 CY in volume.
(d) When rock is encountered, strip free of earth. After verification by a representative of the City and/or Engineer that the material encountered is rock (as defined above), employ an independent surveyor to determine rock quantities before removal operation begins. In computing the volumetric content of rock excavation for payment, the pay lines shall be taken as follows:
(1) For structures (including foundations, manholes wet well, emergency storage vaults, etc.): 24 Inches outside the exterior limits of foundations and from rock surface to 12 Inches below bottom of foundations or unless otherwise noted in the project Geotechnical Report.
(2) For piping and utilities: A width 24 Inches wider than the outside diameter of the pipe or conduit and from rock surface to 12 Inches below bottom exterior surface of the pipe or conduit. (3) Rock removed for benching, sloping excavations and other activities that are subject to the Contractorís means and methods shall not be included in the pay quantity.
(e) Hydraulic Hammer: Hydraulic hammering or alternative means approved by the Engineer shall be employed where refusal has been demonstrated and normal excavation procedures are not feasible. (f) Remove and handle excavated materials regardless of its type, character, composition, condition, or depth.
(g) Blasting shall only be allowed under specified circumstances and performed in a method that limits the amount of public impacts. All blasting activities shall be under the discretion of the Engineer, City and City representatives. The contractor shall bear the responsibility for obtaining all required permits and notifications associated with any blasting activities.

E. Pipe Bedding, Initial Backfill, and Trench Backfill for Utilities:

1. Trench Backfill, Initial Backfill, and Pipe Bedding materials shall be in accordance with City Standard Details 220 and 222 unless otherwise Approved by the Engineer. The Pipe Bedding, Initial Backfill, and Trench Backfill sections for utilities and pipelines shall be defined as indicated on the plans.

Page 363 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 31 23 00
F. Pervious Backfill Material

1. Material shall be in accordance with the following gradation requirements, or as defined in the latest Caltrans Standard Specification edition.

Sieve Size Percentage
Passing
2î 100
No. 50 0-100
No. 100 0-8
No. 200 0-4
PART 3 EXECUTION

3.1 GENERAL
A. Overexcavation

1. At the direction of the Cityís Representative: Where the undisturbed condition of natural soils is inadequate for support of planned construction, the Cityís Representative will direct the Contractor to overexcavate to adequate supporting soils. The excavated space shall be backfilled and compacted to the specified elevation with Pervious Backfill Material, wrapped in filter fabric.

2. Due to Contractorís Operations: Should the excavation be carried below the lines and grades specified on the drawings or should the bottom of the excavation be disturbed because of the Contractor's operations and require overexcavation and backfill, the Contractor shall backfill such excavated space with a compacted material in accordance with fill requirements of this Section.

Backfill and compaction shall be at Contractor's expense.

B. Removal of Obstructions

1. The Contractor shall remove all brush, trees, logs, stumps, roots, heavy sods, heavy growth of grass, all decayed vegetative matter, fences, and all structures where the proper construction and completion of the Work require their removal. The Contractor shall also remove all rocks, stones, broken concrete and pavement, debris and all obstructions of whatsoever kind or character, whether natural or artificial, encountered in the Work.

2. Material that is removed as hereinbefore specified, and is not to be incorporated in the Work, shall be properly disposed of off the site.

C. Surplus Material

1. Unless otherwise specified, surplus excavated material shall be disposed of in accordance with applicable ordinances and environmental requirements.

2. No excavated material shall be deposited on private property unless written permission from the City thereof is secured by the Contractor. Before the City will accept the work as being completed, the Contractor shall file a written

Page 364 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 31 23 00
release signed by all property owners with whom the Contractor has entered into agreements for disposal of excess excavated material absolving the City from any liability connected therewith.

3. The Contractor shall satisfy himself that there is sufficient material available for the completion of the required earthwork before disposing of any material inside or outside the site. The Contractor shall replace shortage of material, caused by premature disposal of any material by the Contractor.

4. Material shall not be stockpiled to a depth greater than five (5) feet above finished grade within 25 feet of any excavation or structure except for those areas designated to be preconsolidated. For these areas, the depth of stockpiled material shall be as specified. The Contractor shall maintain stability of the soil adjacent to any excavation.

D. Hauling

1. When hauling is done over highways and/or private streets, the loads shall be trimmed and the vehicle shelf areas shall be cleaned after each loading. The loads shall be watered after trimming to eliminate dust.

E. Control of Erosion

1. The Contractor shall maintain earthwork surface true and smooth and protected from erosion. Where erosion occurs, the Contractor shall provide fill or shall excavate as necessary to return earthwork surfaces to the grade and finish specified.

3.2 NOT USED

3.3 EXCAVATION AND BACKFILL FOR PIPELINES AND CONDUITS
A. Trench Excavation

1. General Requirements:
(a) Unless otherwise specified or indicated, excavation for pipelines and conduits shall be open cut. Trenching machines may be used except where their use will result in damage to existing facilities. (b) Where, in the opinion of the Cityís Representative, the undisturbed condition of the natural soils below the excavation grades indicated or specified is inadequate for the support of the planned pipeline, the Cityís Representative will direct the Contractor to overexcavate to adequate supporting soils and backfill the excavated space to the proper elevation. The bottom of the trench excavation shall be firm and dry. (c) The trench may be excavated by machinery to the grade indicated on the Drawings provided that the soil material remaining in the bottom of the trench is no more than slightly disturbed.
(d) Open Trench:

Page 365 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -7- 31 23 00
(1) Trench Excavation shall proceed in advance of pipe installation only so far as can be backfilled the same day.
(2) Trench Stability:

1. Where necessary to prevent caving, trench excavations in unstable soils shall be adequately supported with steel sheeting or trench boxes. Before sheeting is withdrawn, or trench boxes moved forward, they shall be raised, in place, just above the pipe crown to safely allow the
constructor to completely fill any voids left in the pipe zone.

B. Grading of Pipe Trench Bedding:

1. Bell or coupling holes:
(a) Dig holes after trench bottom has been graded.
(b) Provide holes of sufficient width to provide ample room for grouting, banding, or welding of Welded Steel Piping.
(c) Excavate holes only as necessary for making joints and to ensure that pipe rests upon prepared trench bottom and not supported by any portion of the joint.

2. Depressions for joints, other than bell-and-spigot:
(a) Make in accordance with recommendations of joint manufacturer for particular joint used.

C. Initial Backfill & Pipe Bedding

1. After the pipe has been properly installed on the consolidated bedding and inspected, initial backfill shall be placed around the pipe to a depth over the pipe as shown in the Drawings. The backfill material shall be placed in horizontal layers and compacted by power-operated tampers, rollers, or vibratory equipment. Jetting of bedding or initial backfill is not allowed.

2. After the pipe is laid, place bedding and backfill material in lifts:
(a) First Lift: Place and compact the bedding material in a single lift, even with the spring line of the pipe.
(b) Subsequent Lifts: Place and compact bedding material in lifts not exceeding eight (8) inches in uncompacted depth.
(c) Each layer shall be compacted to the specified relative compaction prior to placing subsequent layers. The thickness of the loose layer may be increased when in-place compaction tests satisfactory to the Cityís Representative show that the specified relative compaction can be obtained. No further backfilling will be permitted until the Cityís Representative has accepted the initial backfill.

Page 366 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -8- 31 23 00
D. Trench Backfill

1. Above the level of pipe bedding and initial backfill, the trench shall be filled with material as specified unless otherwise indicated on the Drawings. The backfill material shall be placed in horizontal layers and shall have a moisture content such that the required degree of compaction may be obtained. Each layer shall be compacted by power-operated tampers, rollers or other suitable equipment.

Each layer shall be compacted to the specified relative compaction prior to placing subsequent layers.

3.4 FIELD QUALITY CONTROL
A. Confirmation tests:

1. Contractor's responsibilities:
(a) Accomplish specified compaction of trench backfill. (b) Control operations by confirmation tests to verify and confirm that compaction work complies, and is complying at all times, with requirements specified in this Section concerning compaction, control, and testing.
(c) Qualifications of Contractor's testing laboratory: Acceptable to Engineer.

Provide lab certification.
(d) Copies of confirmation test reports: Submit promptly to the Engineer.

2. Frequency of confirmation testing:
(a) Perform testing not less than as follows:
(1) For trenches: At each test location include tests for each type or class of backfill from bedding to finish grade.
(2) For each valve replacement site: At least one test per two lifts B. Compliance tests:

1. Frequency of testing: Periodic compliance tests will be made by the Engineer to verify that compaction is meeting requirements previously specified.

2. If compaction fails to meet specified requirements: Perform remedial work by one of the following methods:
(a) Remove and replace backfill at proper density.
(b) Bring density up to specified level by other means acceptable to the Engineer.

C. Retesting:

Page 367 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -9- 31 23 00

1. Costs of retesting: Contractor is responsible for the costs of retesting required to confirm and verify that remedial work has brought compaction within specified requirements.

2. Contractor's confirmation tests during performance of remedial work:
(a) Performance: Perform tests in manner acceptable to the Engineer. (b) Frequency: Double amount specified for initial confirmation tests. ** END OF SECTION **

Page 368 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 31 23 19
SECTION 31 23 19

DEWATERING
PART 1 GENERAL

1.1 SUMMARY
A. Scope: The work of this Section includes dewatering necessary to lower and control groundwater levels, water leaking from water pipe, and hydrostatic pressures to permit excavation and construction to be performed properly under dry conditions.

B. Contractors Responsibility: Dewatering operations shall be adequate to assure the integrity of the finished project. The responsibility for conducting the dewatering operation in a manner that will protect adjacent structures and facilities rests solely with the Contractor. The cost of repairing any damage to adjacent structures and restoration of facilities shall be the responsibility of the Contractor. Contractor shall secure all necessary permits to complete the requirements of this Section of the Specifications.

1.2 REFERENCES
A. Work shall be performed in accordance with the City Standard Construction Specifications Section W ñ Standard Specifications for Water Mains and Services.

1.3 SUBMITTALS
A. The following shall be submitted in compliance with Section 01 33 00 ñ Submittal Procedures:

1. Prior to commencement of excavation, a detailed plan and schedule for dewatering activities of excavations.

2. Demonstration of proposed dewatering system and verification that adequate personnel, materials and equipment are readily available for all dewatering activities.

3. Copy of any permit or discharge requirements.

4. Compliance with SWPPP requirements.

1.4 CONTROL AND OBSERVATION
A. Adequate control shall be maintained to ensure that the stability of excavated and constructed slopes are not adversely affected by water, that erosion is controlled and that flooding of excavation or damage to structures do not occur.

B. It shall be the sole responsibility of the Contractor to control the rate and effect of the dewatering in such a manner as to avoid all objectionable settlement and subsidence.

C. Where critical structures or facilities exist immediately adjacent to areas of proposed dewatering, reference points shall be established and observed at frequent intervals to detect any settlement that may develop.

D. A daily report shall be maintained. The following shall be recorded:

Page 369 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 31 23 19

1. Elevation of ground water and piezometric water levels in observation wells (if any).

2. Change in elevation of reference points established.

PART 2 PRODUCTS

2.1 EQUIPMENT
A. Dewatering system shall include well points, sump pumps, temporary pipelines for water disposal, rock or gravel placement, and other means including standby pumping equipment maintained on the job site continuously.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS
A. An adequate dewatering system shall be maintained to lower and control the groundwater and leaking from existing water main to permit excavation, construction of structures, placement of piping, and placement of fill materials to be performed under dry conditions.

B. Sufficient dewatering equipment shall be installed to predrain the water-bearing strata below the bottom of foundations, drains, sewers, pipelines and other excavations.

C. The Contractor shall maintain the water level below the bottom of excavation in all work areas where groundwater occurs during excavation construction, backfilling, and up to acceptance.

D. The hydrostatic head in water-bearing strata below foundations, drains, sewers, pipelines and other excavations shall be reduced to ensure that the water level and piezometric water levels are below the excavation surface at all times.

1. The piezometric water level shall be maintained a minimum of 3-feet below the excavation surface all times.

E. The dewatering system shall be placed into operation prior to excavation below ground water level to lower the ground water level and shall be operated continuously 24 hours a day, 7 days a week until drains, sewers, pipelines and structures have been constructed and leak tested and fill materials have been placed and dewatering is no longer required.

F. The site shall be graded to facilitate drainage. Surface runoff shall be diverted from excavations. Water entering the excavation from surface runoff shall be collected in shallow ditches around the perimeter of the excavation, drained to sumps, and be pumped or drained by gravity away from the excavation.

G. Dewatering shall at all times be conducted in such a manner as to preserve the undisturbed bearing capacity of the subgrade soils at proposed bottom of excavation.

H. If foundation soils are disturbed or loosened by the upward seepage of water or an uncontrolled flow of water, the affected areas shall be excavated and replaced with drain rock at no additional cost to the City.

Page 370 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 31 23 19
I. Flotation shall be prevented by the Contractor by maintaining a positive and continuous removal of water. The Contractor shall be fully responsible and liable for all damages which may result from failure to adequately keep excavations dewatered.

J. If well points or wells are used, they shall be adequately spaced to provide the necessary dewatering and shall be sandpacked and/or other means shall be used to prevent pumping of fine sands or silts from the subsurface. A continual check shall be maintained to ensure that the subsurface soil is not being removed by the dewatering operation.

K. Water and debris shall be disposed of in a suitable manner in compliance with local and State regulations and without damage to adjacent property. No water shall be drained into the installed or under construction facilities. Water shall be filtered to remove sand and fine-sized soil particles and further treated if required by regulatory agencies before disposal into any drainage system
L. Necessary permits for disposal of water, if applicable, shall be obtained by the Contractor from the appropriate regulatory agencies.

M. The release of groundwater to its original level shall be performed in such manner to prevent disturbance of natural foundation soils, prevent disturbance of compacted backfill and prevent flotation or movement of structures, pipelines, and sewers.

N. Dewatering of trenches and other excavations shall be considered as incidental to the construction of the Work and all costs thereof shall be included in the various contract prices in the Bid Forms, unless a separate bid item has been established for dewatering.

O. Contractor shall comply with all discharge permit and SWPPP requirements. Water shall be disposed of in a manner as not to cause injury to private property, cause violation of the Cityís Municipal Regional Stormwater Permit, nor be a menace to public health.
** END OF SECTION **

Page 371 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 31 41 00
SECTION 31 41 00

SHORING
PART 1 GENERAL

1.1 SCOPE
A. This Section provides specifications for sheeting, shoring, bracing, or other excavation supports.

1.2 REFERENCES
A. This section references the following documents. They are part of this section as specified and modified. In case of conflict between the requirements of this section and those of the listed documents, the most stringent requirement shall prevail.

Reference Title
ASCE Guidelines of Engineering Practice and Tied Back Excavations Caltrans Caltrans California Trenching and Shoring Manual OSHA Occupation Safety and Health Act, US Department of Health CAL OSHA State of California Construction Safety Orders ñ California State Labor Code
CCR California Code of Regulations ñ Title 8
CLC California Labor Code ñ Sections 6705 to 6707
NAVFAC Department of the Navy Naval Facilities Engineering Command USS United States Steel Corp ñ Steel Sheet Piling Design Manual

1.3 DEFINITIONS
A. Shoring: A temporary structural system designed to support vertical faces, or nearly vertical faces, of soil or rock for purposes of excavation. Shoring includes cantilevered sheet piling, internally braced sheet piling, slurry walls, soldier piles and lagging, trench plates and vertical shoring, slide rail, and other similar shoring systems. Sloping (Benching) of the soil is not considered shoring as described herein however, sloping (benching) is considered an appropriate means of constructing a safe trench and may be considered for the use of project excavation.

B. Shielding: A temporary structural system designed to protect workers from trench failure. A shield is not considered to be a temporary structural system designed to support vertical trench faces, or nearly vertical faces, of soil or rock for purposes of excavation and maintain trench wall consolidation. A shield may be used in conjunction with an active shoring system but shall not be substituted as an or equal.

1.4 QUALITY ASSURANCE
A. Protection and Trench Safety

Page 372 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 31 41 00

1. Pursuant to Section 6705 of the State Labor Code, all open excavations greater than 5 feet in depth shall be constructed with bracing, sheeting, shoring, or other equivalent method designed for the protection of life and limb.

2. The trench excavation and support system shall comply in all respects with the requirements of Article 6 of the Construction Safety Orders of the Division of Industrial Safety.

3. The Contractor's attention is directed to the provisions of Subarticle 1540 (4), Article 6 of the California Construction Safety Orders for alternative shoring and sloping system. It shall be the Contractor's responsibility to provide the additional strength required to support the sides of the excavation against loads which may exceed those employed to derive the criteria set forth in the Industrial Safety Orders.

4. The Contractor shall submit to the Cityís Representative a detailed plan showing the design of sheeting, shoring, bracing, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. The plan shall be prepared and stamped by a California registered Civil Engineer.

5. It shall be understood that the above-stipulated requirements are the minimum to be provided. The Contractor shall be solely responsible for all liabilities that may arise from the Contractorís failure to provide adequate shoring, bracing or sheeting as necessary to support the excavation under any or all of the conditions of loading which may exist, or which may arise during the construction of the project.

B. Excavation for structures

1. All excavations shall be properly shored, sheeted and braced to prevent shifting of material, to prevent damage to structures or other work, and to avoid delay to the Work, all in accordance with applicable safety and health regulations.

2. Before starting excavation for structures, the Contractor shall submit, for record purposes, complete design calculations and working drawings of proposed sheeting and bracing arrangements which have been prepared, signed and sealed by a California registered Civil Engineer. Shoring system means and methods are the sole responsibility of the Contractor however, the proposed shoring system shall be applicable to working excavation conditions, existing soils, groundwater tables, and required constructability. The shoring system should be consistent with recommendations provided by the Geotechnical Engineer. If the Inspector or Cityís representative determines that the Contractorís shoring system means and methods are producing an unsafe environment or do not adequately account for the existing work environment, the Inspector may shut down construction until the shoring system is deemed safe by a licensed Civil Engineer.

3. Bracing shall be arranged so as not to place any strain on portions of completed work until the general construction has proceeded far enough to provide ample strength. If the Cityís Representative is of the opinion that, at any point, the sheeting or supports are inadequate or unsuited for the purpose, the Cityís Representative may order the Contractor to resubmit design

Page 373 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 31 41 00
calculations and working drawings for that point, taking into consideration the observed field conditions.

4. If the new calculations show the need for additional sheeting and bracing, the Contractor shall immediately install facilities necessary to meet or exceed identified requirements.

5. The sole responsibility for the design, methods of installation, and adequacy of the sheeting and supports shall be and shall remain that of the Contractor.

6. The working drawings for shoring, sheeting and bracing will not be checked by the Cityís Representative.

C. Submittals

1. The following shall be submitted in compliance with Specification Section 01 33 00 ñ Submittal Procedures.

2. Trench Support Shop Drawings and Calculations:
(a) In accordance with the requirements of Section 6705 of the Labor Code of the State of California, the Contractor shall submit detailed drawings and supporting calculations to the Cityís Representative before excavation, showing the design of sheeting, shoring, bracing, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of any trench or trenches 5 feet or more in depth.
(1) Where such drawings vary from excavation support standards set forth in California Code of Regulations Title 8 - Construction Safety Orders, submit design calculations pursuant to general engineering design practice.
(2) Provide means for safe and stable excavations that are not less effective than required in CCR Title 8 - Construction Safety Orders.
(3) For excavations other than trenches, submit, in advance of excavation work, design calculations as performed pursuant to general engineering design practice, as specified in this Section, and detail drawing showing means for safe and stable
excavations. In design calculations and detail drawing, cover, as a minimum:

1. Excavations adjacent to structures and other
improvements, and

2. Excavations 5 feet or more in depth, or less than five (5) feet in depth when there is potential for cave-in, at other locations.
(b) The Contractorís Sheeting, Shoring and Bracing design submittal shall include the following items:

Page 374 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 31 41 00
(1) Provide calculations for the different load, support, and other conditions that occur during the sequence of installation of shoring, construction of facilities protected by the shoring, and sequence of removal of shoring. Provide design calculations that clearly disclose assumptions made, criteria followed, and stress values used for the materials being used.
(2) Provide sketches showing the condition at various stages of installation and removal of shoring.
(3) Show structures, pipelines, and other improvements located near the shoring, and the shoring on a plan.
(4) When utilities penetrate the shoring, submit an elevation of all sides of the shoring showing the locations of the penetrations.

Submit details on ground support and sealing around utility penetrations.
(c) The design shall be signed and stamped by a California registered Professional Civil Engineer. The drawings and calculations will be for record purposes only and will not be checked by the Cityís Representative. Responsible charge of the submitted sheeting, shoring and bracing drawings and calculations will remain under the sole responsibility of the California registered Professional Civil Engineer of record whom signed and stamped the sheeting, shoring, and bracing design.
(d) The sheeting, shoring and bracing design shall take the geotechnical data, soil characteristics, and sheeting, shoring, and bracing recommendations into consideration reported in the project specific geotechnical report. Please note discrepancies between the submitted design and recommendations listed in the geotechnical report. (e) In accordance with the requirements of CalTrans Standard Specifications, protective plans not requiring a signature shall be submitted at least 5 days before the Contractor intends to begin excavation. If the protective plan requires a signature, the plan shall be submitted at least 20 days before the Contractor intends to begin excavation.
(f) Detailed Sequence of Installation and Removal of Shoring:
(1) Consider effects of ground settlement in the sequence of installation and removal of shoring.
(2) Provide individual drawings/details illustrating the conditions at various stages in the sequence of installation and removal of shoring.

3. Certification
(a) The minimum required protection will be that described in the Cal/OSHA Construction Safety Orders of the California Division of Industrial Safety.

Page 375 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 31 41 00
(b) If the Contractor presents excavation plans that vary from the shoring system standards established by the Construction Safety Orders, the Plans shall be prepared, stamped, and signed by a California registered Civil Engineer.

1.5 SCHEDULING AND SEQUENCING
A. Do not begin work on excavations, trenches, and means for providing stability of excavation and trenches until submittals have been accepted by Engineer and until materials necessary for installation are on site.

B. Submit submittals a minimum of twenty (20) days prior to the scheduled date to begin excavation work.

C. The Contractor shall sequence the installation and removal of the shoring system in strict accordance with the signed and stamped Sheeting, Shoring, and Bracing design.

In soils deemed unstable, the Contractor shall only construct trenching that can be open and closed in one (1) business day. The Contractor shall coordinate closely with the geotechnical engineer to determine the quality of existing soils and the potential for allowing open cut trenches to remain un-backfilled for multiple days.

PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION

3.1 GENERAL
A. The design, planning, installation and removal of all lagging, sheeting, shoring, sheet piling, and bracing shall be accomplished in such a manner as to maintain the undisturbed state of the soils adjacent to the trench and at and below the excavation bottom.

B. The use of horizontal strutting below the barrel of a pipe or the use of a pipe as a support will not be permitted.

C. Sheet piling and timbers in trench excavations shall be withdrawn in a manner so as to prevent subsequent settlement of the pipe or additional backfill loadings that might overload the pipe.

D. Where measurements and observations indicate possibility of failure or excessive movement of excavation support, determined in accordance with general engineering design practice, take appropriate action immediately.

E. In the event of an unknown utility line or obstruction is encountered during trenching activities, the contractor shall discontinue construction progress and notify the Engineer. The Contractor will coordinate with the Civil Engineer of record responsible for the Sheeting, Shoring, and Bracing design and adjust the shoring system design as necessary to accommodate the avoidance of the existing.

F. Installation and Removal

1. The Contractor shall select a shoring system and method of removal which will minimize soil that sticks to shoring from creating large voids and causing settlement. To prevent settlement caused by pulling shoring, the Contractor

Page 376 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -6- 31 41 00
shall fill voids with sand, pea gravel, pressure inject grout or an approved controlled density fill.

3.2 PERFORMANCE REQUIREMENTS:

A. General:

1. Support faces of excavations and protect structures and improvements in vicinity of excavations from damage and loss of function due to settlement or movement of soils, alterations in ground water level caused by such excavations, and related operations.

2. Herein Specified Provisions:
(a) Complement, but do not substitute or diminish, obligations of Contractor for the furnishing of a safe place of work pursuant to provisions of the Occupational Safety and Health Act of 1970 and its subsequent amendments and regulations and for protection of the Work, structures, and other improvements.
(b) Represent minimum requirement for:
(1) Number and types of means needed to maintain soil stability. (2) Strength of such required means.
(3) Methods and frequency of maintenance and observation of means used for maintaining soil stability.

B. Provide safe and stable excavations by means of sheeting, shoring, bracing, sloping, and other means and procedures, such as draining and recharging groundwater and routing and disposing of surface runoff, required to maintain the stability of soils and rock.

C. Provide support for trench excavations for protection of workers from hazard of caving ground.

D. Provide Shoring:

1. Where, as result of excavation work and analysis performed pursuant to general engineering design practice, as defined in this Section:
(a) Excavated face or surrounding soil mass may be subject to slides, caving, or other types of failures.
(b) Stability and integrity of structures and other improvements may be compromised by settlement or movement of soils, or changes in soil load on structures and other improvements.

2. For trenches five (5) feet and deeper.

3. For trenches less than five (5) feet in depth, when there is a potential for cavein.

Page 377 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -7- 31 41 00

4. Where indicated on the Drawings.

5. For safe and stable excavations, use appropriate design and procedures for construction and maintenance to minimize settlement of supported ground and to prevent damage to structures and other improvements, including:
(a) Using stiff support systems.
(b) Following appropriate construction sequence.
(c) Preventing Soil Loss Through or Under Support System:
(1) Provide support system that is tight enough to prevent loss of soil and extend deep enough to prevent heave or flow of soils from supported soil mass into the excavation.
(d) Providing surface runoff routing and discharge away from excavations. (e) Where dewatering is necessary, recharge groundwater as necessary to prevent settlement in area surrounding excavation.
(f) Where sheet piling is used, use interlocking type sheets. The sheet piles shall be continuous and driven in interlock. If the bottom of the excavation is located below the water table, use "thumb and finger" type interlock.
(g) Not applying shoring loads to existing structures and other improvements.
(h) Not changing existing soil loading on existing structures and other improvements.
(i) Provide welded steel packing between soil retaining members such as sheet piles and wales and similar members when the gap exceeds 1/2 inch before the wales are loaded.

3.3 DESIGN
A. General

1. Design means for safe and stable excavations in accordance with general engineering design practice.

2. Design steel members in accordance with CBC (most recent edition) and the AISC Manual of Steel Design.

3. Design shoring involving materials other than steel in accordance with CBC (most recent edition).

4. Perform design in accordance with soil characteristics and design recommendations contained in the project geotechnical report referenced in Section 02 22 13, Movement and Vibration Assessment and provided in Appendix A.

Page 378 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -8- 31 41 00

5. When electing to design with material stresses for temporary construction higher than allowable stresses prescribed in the Manual of Steel Construction and the applicable building codes, increase in such stresses shall not exceed ten (10) percent of value of prescribed stresses.

6. Minimum safety factor used for design shall not be less than 1.5.

7. The calculated minimum depth of penetration of shoring below the bottom of the excavation shall be increased not less than 30 percent if the full value of passive pressure is used in the design.

8. The maximum height of cantilever shoring above the bottom of excavation shall not exceed fifteen (15) feet. Use braced shoring when the height of shoring above the bottom of excavation exceeds fifteen (15) feet.

9. The location of the point of fixity for shoring shall not be less than half the calculated minimum embedment depth below the bottom of the excavation.

10. Generally acceptable references for the design of shoring and excavations are as follows:
(a) Caltrans California Trenching and Shoring Manual.
(b) NAVFAC Design Manual 7.2 - Foundations and Earth Design. (c) NAVFAC Design Manual 7.3 - Soil Dynamics Deep Stabilization and Special Geotechnical Construction.
(d) USS Steel Sheet Piling Design Manual.
(e) Guidelines of Engineering Practice for Braced and Tied-Back Excavations published by American Society of Civil Engineers.

B. Shoring design shall be performed by a Shoring Design Engineer meeting the following qualifications:

1. Shall be registered as a civil or structural engineer in the State of California.

2. Shall have not less than 5 years experience in the design of shoring.

3. The shoring design firm shall obtain errors and omissions insurance for the Project for an amount of not less than $500,000.

C. Soldier Piles and Lagging:

1. Provide lagging over the full face of the excavation. Joints between pieces of lagging shall be tight to prevent loss of soil.

2. Provide full face lagging all around penetrations through the lagging.

3. If the soldier piles are installed in predrilled holes, the predrilled holes shall be filled with controlled density backfill after the soldier piles are installed.

Page 379 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -9- 31 41 00

4. The effective width of driven soldier piles for passive soil resistance shall not exceed 2 times the width of the pile. The effective width of concrete encased soldier piles for passive soil resistance shall not exceed two (2) times the width of the concrete encasement.

5. Fill voids behind lagging with gravel or other material acceptable to the Engineer.

6. Apply loads from tie back soil, rock, or deadman anchors concentrically to soldier piles or wales spanning between soldier piles. Wales shall be back-toback double channels or other members acceptable to the Engineer.

Eccentrically loaded with section soldier piles or wales are not acceptable.

7. Design soldier piles for downward loads including vertical loads from tie back anchors.

D. Soil Anchors, Rock Anchors, and Deadmen Anchors:

1. Design tie back anchors for a safety factor of not less than two (2) times the calculated load from the shoring.

2. Proof load all production anchors to not less than 125 percent of the calculated load from the shoring. Lock off anchors at the calculated anchor load.

3. The length of soil anchors used to calculate resistance to load from the shoring, shall not include any length within the potential active pressure soil failure zone behind the face of shoring.

4. Design tie rods for anchors for 130 percent of the calculated load from the shoring.

5. Design tie rods for anchors for 150 percent of the calculated load from the shoring when tie rod couplers are used and for other conditions where stress concentrations can develop.

E. Steel Plating and Vertical Shoring

1. Steel plating shall be required for all excavations greater than 5-feet in depth.

2. Steel plates utilized for the design shall be nonskid finishes. (a) If excavations are to be left open for five (5) days or less, steel plates may be placed over the excavation.
(b) In existing AC Pavement, the Contractor shall place cold mix Asphalt ìCutbackî around the perimeter of the plates for a smooth transition. If the excavation will be left open longer than five (5) days, the Contractor shall saw cut/grind a key into edges of the pavement around the perimeter of the excavation to support the plates.
(1) These keys shall be cut/ground to a depth equal to the thickness of the plates used to span the excavation.

Page 380 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -10- 31 41 00

3. Hydraulic Vertical shores may be Aluminum and shall be sized in accordance with the horizontal loading calculated in the Sheeting, Shoring and Bracing system design.

4. When excavating in less stable soils requiring close or intermittent sheeting, the Contractor may utilize an Aluminum Waler & Hydraulic Shore System for trench wall support.

3.4 SEQUENCING
A. The Contractor shall not start excavation until the trench support drawings have been returned to the Contractor.

B. When the construction sequence of structures requires the transfer of bracing to the completed portions of any structure, the Contractor shall secure the written acceptance of the Cityís Representative prior to the installation of such bracing. ** END OF SECTION **

Page 381 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 32 12 16
SECTION 32 12 16

ASPHALT PAVING
PART 1 GENERAL

1.1 SUMMARY
A. This section provides specifications for asphalt concrete pavement for prepared subgrade or aggregate base course.

1.2 REFERENCES
A. State of California Department of Transportation Standard Specifications, latest edition (Caltrans Standard Specifications)
B. Caltrans Standard Test Methods:

1. Calif Test 202 - Sieve Analysis of Fine and Coarse Aggregates.

2. Calif Test 304 - Preparation of Bituminous Mixtures for Testing.

3. Calif Test 362 - Determining Asphalt Content in Bituminous Mixtures by Vacuum Extraction.

4. Calif Test 375 - Determining the In-Place Density and Relative Compaction of AC Pavement.

5. Calif Test 379 - Determining Asphalt Content in Bituminous Mixtures (Troxler Nuclear Gauge Model 3241).

C. ASTM International (ASTM):

1. D 1557-12 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

2. D 1561 - Standard Practice for Preparation of Bituminous Mixture Test Specimens by Means of California Kneading Compactor.

1.3 SUBMITTALS
A. Contractor shall submit product data showing that all paving materials conform to the requirements of this section, Caltrans Standard Specifications & Drawings and applicable requirements set forth in the City Standard Specifications & Drawings.

B. Submittals shall be in accordance with Specification Section 01 33 00 ñ Submittal Procedures.

C. Contractor shall submit the following information for review and approval by the Engineer:

1. Mix Design as described in Section 39-2.01A(3)(b).

2. Shop Drawings.

Page 382 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 32 12 16

3. Product Data of proposed Materials:
(a) Aggregate Base
(b) Asphalt Binder

4. Contractor shall submit copies of Quality Control testing laboratory reports verifying that the aggregate material conforms to the specified gradations or characteristics.

5. Certificates of Compliance and Competence by the Contractor performing the work.

D. Delivery & Storage

1. Asphalt pavement delivery:
(a) Transport the mixture from the mixing plant to the point of use in vehicles having tight bodies previously cleaned of all foreign materials. (b) Treat bodies as necessary to prevent material from sticking to the bodies.
(c) Cover each load with canvas or other suitable material of sufficient size and thickness to protect the asphalt mixture from the weather.

E. Project Conditions

1. Environmental requirements:
(a) Asphalt concrete:
(1) Place asphalt concrete only when surface is dry, when atmospheric temperature in the shade is 40 degrees Fahrenheit and rising, or above 50 degrees Fahrenheit if falling.
(2) Do not place asphalt concrete when weather is foggy or rainy nor when base on which material is to be placed is in wet or frozen conditions or when, in the opinion of the Engineer, weather conditions will prevent proper handling, finishing, compaction of the mixtures.

PART 2 PRODUCTS

2.1 ASPHALT CONCRETE MATERIALS
A. All materials shall be in conformance with the following requirements of the latest Caltrans Standard Specification:

Page 383 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 32 12 16
Material Requirements
Asphalt Aggregate Section 39-2.02B(4), 3/4-inch Aggregate as specified in 39-2.02B(4)(b)
Asphalt Concrete Section 39-2.02B(2), Type A Hot Mixed Asphalt (HMA)
Asphalt Binder Section 92, PG 64-10
Tack coat Asphalt Binder specified herein
B. A minimum of 6 inches of aggregate base or as shown on the Drawings, whichever is thicker, will be placed below all new asphalt paving.

2.2 EQUIPMENT
A. Spreading and compacting equipment shall comply with Section 39-2.01C(2) B. Tack Coat Application Equipment shall comply with Section 37-1.03B PART 3 EXECUTION

3.1 EXAMINATION
A. Verification of conditions: Verify surfaces and site conditions are ready to receive work.

If unsatisfactory conditions exist, do not commence installation until such conditions have been corrected. Beginning application means acceptance of existing conditions.

3.2 PREPARATION
A. Protection

1. Protect concrete pavements and walks, curbs and bases, and other improvements adjacent to the operations with suitable materials.

2. Building and other surfaces shall be covered with paper or other protection, when required.

3. Contractor shall be responsible for any damage caused by Contractorís employees. All damage caused by the Contractorís operations shall be repaired to the satisfaction of the Engineer at no additional cost to City.

B. Asphalt Concrete Removal

1. All asphalt concrete pavement surface that has been removed, broken or damaged shall be completely re-paved in accordance with the requirements stated herein unless otherwise noted in the Contract Documents.

2. Existing pavement shall be saw cut and removed clean in accordance with City Standard Specifications & Drawings, and Caltrans Standard Specifications. The Contractor shall coordinate with the Engineer to determine the full extent of pavement restoration/removal.

3. All asphalt paving shall be cut to a neat, straight line and the exposed edge shall be tacked with emulsion prior to paving. The exposed base material shall

Page 384 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -4- 32 12 16
be graded, recompacted, and resealed prior to paving. Reference the Contract Drawings or City Standard Specifications & Drawings for compaction requirements.

4. Removed asphalt shall be disposed from the work site at the Contractorís expense. Removed asphalt shall not be used as backfill material on-site.

5. Reclaimed asphalt material may be used on the Work site only with written approval from the Cityís Representative/Engineer. Reclaimed asphalt is asphalt that has been removed with a ìgrinding machineî and mixed with aggregate material to meet pre-approved requirements.

C. Preparation of Subgrade

1. Subgrade shall be prepared in accordance with the Contract Drawings.

2. Shape subgrade to line, grade, and cross section shown in the drawings.

3. Scarify subgrade to 6 inches depth below the finished subgrade elevation.

Compact to 95 percent relative compaction.

4. Immediately prior to applying tack coat, or immediately prior to placing the asphalt pavement when tack coat is not required, the subgrade to receive asphalt pavement shall conform to the compaction requirement and elevation tolerances specified for the material involved and shall be cleaned to remove any loose or extraneous material.

5. If the asphalt pavement is placed on an existing base or pavement which was not constructed as part of the contract, the Contractor shall clean the surface by sweeping, flushing, or other means to remove all loose particles of paving, all dirt and all other extraneous material immediately before applying the tack coat.

6. The finished subgrade shall be within a tolerance of 0.05 of a foot of the grade and cross section shown and shall be smooth and free from irregularities and at the specified relative compaction.

D. Placement of Aggregate Base Course

1. Place aggregate base course to a minimum thickness as shown on the Contract Drawings. Compact to 95% relative compaction and install in accordance with Caltrans Standard Specification Section 26.

3.3 TACK COAT APPLICATION
A. A tack coat of asphaltic binder shall be applied to all vertical surfaces of existing pavement, curbs, gutters, and construction joints in the surfacing against which new asphalt concrete is to be placed, or as otherwise specified in this Section.

B. Tack coat shall be applied in one application at a rate of 0.1 gallons per square yard of surface covered.

C. Tack coat application rates for HMA shall be applied as shown in the table below.

Page 385 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -5- 32 12 16
HMA over:

Minimum Residual Rate
for Asphalt Binder
(gal/ sq yd)
New HMA (between layers) 0.02
Concrete pavement and existing asphalt
concrete surfacing 0.03
D. Apply tack coat on surfaces to receive finish pavement per Caltrans Standard Specifications 39-2.01C(3)(f). Apply tack to metal or concrete surfaces that will be in contact with the asphalt concrete paving.

3.4 ASPHALT PAVEMENT INSTALLATION
A. Construction of asphalt pavement must comply with Caltrans Specification Section 39-

2.02C.

B. Segregation shall be avoided and the surfacing shall be free of pockets of coarse or fine material. Asphalt pavement containing hardened lumps shall not be used:

1. In areas inaccessible to paving and compacting equipment where spreading is done by hand, minimize the amount of segregation.

C. Location of longitudinal joints in the top layer will be determined by the Engineer and shall not adversely affect the quality of the finished product.

D. At all locations, or as directed by the Engineer, the asphalt concrete shall be square.

Tapering or feathering is not allowed.

3.5 SURFACE TOLERANCE
A. Finished grade shall not deviate more than 0.02 foot in elevation from the grade indicated in the drawings. Slopes shall not vary more than º inch in 10 feet from the slopes shown in the drawings.

3.6 TRAFFIC AND PARKING LOT STRIPING AND MARKING PAINT APPLICATION (IF

REQUIRED AND IF INDICATED ON THE DRAWINGS)
A. Apply in accordance with Caltrans Standard Specification Section 84.

3.7 FIELD QUALITY CONTROL
A. The Contractor shall control the quality of Work and shall provide adequate testing to assure compliance with these Specifications.

B. See Section 39-2.02A(4)(e) for in place testing requirements for acceptance.

C. Cracks, settling of surface, improper drainage, improper compaction, and sloppy connection to previously laid surfaces will be construed as improper workmanship and will not be accepted.
** END OF SECTION **

Page 386 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -1- 32 16 00
SECTION 32 16 00

CONCRETE CURBS, GUTTERS, SIDEWALKS AND DRIVEWAYS
PART 1 - GENERAL

1.1 SUMMARY
A. Section Includes: Concrete curbs, gutters, sidewalks, driveways, and access ramps as new installations and to replace those demolished or damaged during construction.

B. All work within the public rights-of-way shall conform to City of Milpitas Standard Specifications.

1.2 SUBMITTALS
A. Submittals shall be in accordance with Specification Section 01 33 00 ñ Submittal Procedures.

B. Product Data: Submit data completely describing all products to be used.

1.3 PROJECT CONDITIONS
A. Any concrete flatwork damaged during the course of construction, including transportation and delivery, shall be replaced to that flatworkís pre-existing condition or better.

B. Contractor shall be responsible for all field measurements necessary to meet these specifications.

PART 2 - PRODUCTS

2.01 MATERIALS
A. Concrete:

1. Shall contain five hundred sixty-four (564) pounds (6 sacks) of Type I or I/II Portland Cement per cubic yard. Contractor shall provide the City Engineer with certified delivery tickets stating the weight of the separate aggregate and water content of each individual load of concrete used. Curb shall be dipped for driveway entrances where indicated by the Engineer in the field.

2. In lieu of above, the contractor may furnish at his option concrete as follows:
a. Concrete shall be proportioned and mixed to develop strength of 3,000 pounds per square inch at 28 days, as tested in accordance with California Test 521, with cylinders molded and initially field cured under the California Test 540. Concrete should be sampled under California Test 539.
b. Mix Design shall be designed by an approved laboratory employee and paid for by the contractor. The basic proportions of the mix shall be determined by weight o' loose dry material, and all proportioning of the ingredients for each batch shall be done by weighing the fine and

Page 387 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -2- 32 16 00
coarse aggregate separately. Water and cement shall be separately measured and introduced to the mix by such methods that the proportions thereof car, be accurately controlled and easily checked at any time.
c. Approval of the mix shall be by the City Engineer, who shall determine accuracy by making tests.
d. Batch tickets to be provided to the City Engineer with each load.

B. Form Release Material: Light oil or other releasing agent of concrete type that does not discolor concrete or interfere with the application of finishing mortar to curb tops and faces.

C. Dowels: #4 rebar conforming to ASTM A615, Grade 40.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verification of Conditions:

1. Verify field conditions, including subgrade condition and interferences, before beginning construction.

3.02 PREPARATION
A. Surface Preparation:

1. Subgrade:
a. Curb and gutter shall be placed over a minimum of six inches (6") of base or over a base the lower surface of which is a continuation of the subgrade line, whichever is greater.
b. The base shall be constructed true to grade and cross-section as shown on the Contract Drawings. It shall be rolled and watered or hand tamped to 95% relative compaction before placing concrete. The complete base shall be tested for grade and cross-section by means of a template extending the full depth of the curb and gutter and supported between side forms. The base and forms shall be thoroughly watered in Forms and Subgrade: Water immediately in advance of placing concrete.

Sidewalks shall be placed on a minimum of 4" of compacted base rock or sand-gravel material as shown on Standard Drawings.

3.03 INSTALLATION
A. Forms:

1. The depth of forms shall he-equal to the full depth of curbs or gutters. Timber forms shall be surfaced top and bottom and on the side which is placed next to the concrete and shall not be less than one and five-eighth (1-5t8") inches thick after being surfaced. Warped forms and forms not having a smooth, straight

Page 388 of 557 ends

E. Calaveras Blvd & Yosemite Dr. Water Valves July 2024 Replacement Project No. 7118 & 7100 -3- 32 16 00
upper edge shall not be used.

2. Sidewalk Forms: (Concrete) Forms shall be set with the upper edge true to line End grade and shall be held rigidly in place by stakes placed on the outside of the forms and set flush with the top edge of the form. The side forms shall not be removed in less than twelve (12) hours after the finishing has been completed.

3. Curb Forms: Rigid forms shall be provided for all curbs, except that benders or thin plank forms, rigidly placed may be used for curbs or curb returns with a radius of thirty (30') feet or more where there are grade changes in the returns, or where the central angle is such that a rigid form with a central angle of ninety degrees (DOG) cannot be used. Back forms for curb-returns may be of one-half inch (1/2") benders for the full height of the curb cleated together. Curb forms shall be carefully set to alignment and grade and to conform to the dimensions of the curb. Forms shall be held rigidly in place by use of pairs of iron stakes placed at intervals not to exceed four feet (4'). Clamps, spreaders and braces shall be used where required to insure rigidity in the forms. The form on the front of the curbs shall not be removed in less than one (1) hour after the concrete has been placed. In no event, shall the forms be removed while the concrete is sufficiently plastic to slump upon removal of the form.

4. Outside Forms and Temporary Forms: Outside forms and temporary forms contiguous to curbs shall be set with the upper edges true to line and grade,- and shall be held rigidly in place by stakes placed on the outside of the forms and set flush with the top edge of the forms. Temporary forms shall be removed immediately after striking off and tamping the surface of the gutter and the space left thereby immediately filled and finished true to grade and crosssection. Outside forms shall remain in place not less than four (4) hours after the finishing has been completed.

5. Thoroughly clean prior to each use and coat with form releasing material.

B. Score marks and weakened plain joints shall conform to requirements of Contract Drawings or as directed.

C. Concrete:

1. Placing:
a. Thoroughly spade concrete away from forms so that no rock pockets exist next to forms and so that no coarse aggregate will show when forms are removed.

2. Finished Concrete:
a. Concrete walks and curbs shall be brought true to grade with a trowel, scored and brush finished and ramps roughened, as directed by the City Engineer

3. Curing Concrete: Unless otherwise specified on the plans, concrete shall be cured by means of the impervious membrane method, or by water cure.

Page 389 of 557 ends