Prior to the issuance of a Final Certificate of Occupancy, the developer shall comply with City of Milpitas provisions for obtaining business licenses (including amendments to existing licenses) for the building occupant.

D. Infrastructure, Grading and Construction. Any and all approvals, decisions, reviews or actions required under this section and required for development within the Milpitas Commercial Specific Plan area shall be ministerial, final and not subject to appeal, and shall be processed pursuant to Section XI-10-

11.07(E), Administration, of this Specific Plan.

1. Infrastructure.
a. General Provisions. Any development in the Specific Plan area shall comply with the following:
i. All existing on-site public utilities shall be protected in place and if necessary relocated as approved by the City Engineer. No permanent structure shall be permitted within City easements and no trees or deep-rooted shrubs are permitted within City utility easements, where the easement is located within landscape areas.
ii. Submittal of the Sewer Needs Questionnaire and/or Industrial Waste Questionnaire is required with any building permit application. Payment of the storm water connection fee and treatment plant fee shall be paid prior to building permit issuance.
iii. Developer must pay all applicable development fees, including but not limited to, plan check and inspection deposit, and two and one-half percent (2.5%) building permit automation fee. These fees are collected as part of the secured public improvement agreement. The agreement shall be secured for an amount of one hundred percent (100%) of the engineer's estimate of the construction cost for faithful performance and one hundred percent (100%) of the engineer's estimate of the construction cost for labor & materials. All fees shall be paid prior to building permit issuance. iv. Before building permit issuance, developer shall obtain design approval from the City Engineer pursuant to Section XI-10-11.07(F), Environmental Performance Standards, of this Specific Plan, for all necessary public improvements along Ranch Drive, including, but not limited to, the installation of new pedestrian crosswalk and ped-flashing warning signals, new mid-block ramp, signage and striping, and installation of new median. Developer shall bond for such improvements and execute a secured public improvement agreement. The agreement shall be secured for an amount of one hundred percent (100%) of the engineer's estimate of the construction cost for faithful performance and one hundred percent (100%) of the engineer's estimate of the construction cost for labor and materials. All public improvements shall be constructed to the City Engineer's satisfaction and accepted by the City prior to building occupancy permit issuance.
v. At the time of building permit application, developer shall pay any project job account balance due to the City for recovery of review fees. Review of any permit submittals will not be initiated until balance is paid in full.
b. Water Facilities. The Specific Plan area will receive water service from the City of Milpitas. The City of Milpitas's Urban Water Management Plan indicates that under normal water years, water supplies are sufficient to serve demands within the City through 2030. Under multiple dry year scenarios, demand is expected to surpass supply as soon as 2010. Because the Specific Plan area has an existing building, that building's water demand is accounted for in the City's water demand projections. Development within the allowable Floor Area Ratio for the Specific Plan area would not create increased potable water demand that would adversely impact the water system. Development may be suspended, however, prior to building permit issuance if necessary to stay within available water supplies and will remain suspended until water is available. The City shall provide Developer with written evidence that available water supplies do not exist prior to suspending any development within the Specific Plan area. The Specific

Page 112 of 395 ends

Plan area is estimated to generate ten thousand nine hundred (10,900) gallons per day of water demand.

Implementation of the Specific Plan will not require new or expanded water facilities.

Development in the Specific Plan area must install the following indoor water conservation measures prior to issuance of the final certificate of occupancy to reduce overall demand for potable water: low- flow or ultra-low-flow toilets and urinals; and sensor-activated faucets in restrooms. c. Wastewater Facilities. The Specific Plan area would convey wastewater via municipal sewage infrastructure maintained by the City of Milpitas to the San Jose/Santa Clara Water Pollution Control Plant. A wastewater trunk line is located in North McCarthy Boulevard from SR-237 to the Milpitas Pump Station located at Dixon Landing Road. The trunk line ranges in diameter from thirty-six (36) to forty-eight (48) inches. Development within the allowable Floor Area Ratio for the Specific Plan area would not create increased effluent generation that would adversely impact the sewer system or treatment plan capacity. Development may be suspended, however, prior to building permit issuance if necessary to stay within the safe allocated capacity at the San Jose/Santa Clara Water Pollution Control Plant and will remain suspended until sewage capacity is available. The City shall provide Developer with written evidence that available sewage capacity does not exist prior to suspending any development within the Specific Plan area. The Specific Plan area is estimated to generate six thousand three hundred ninety (6,390) gallons per day of effluent. Implementation of the Specific Plan will not require new or expanded wastewater treatment facilities.

Development in the Specific Plan area will be required to pay a Treatment Plant Fee, a standard requirement for new development projects.
d. Storm Drains. Implementation of the Specific Plan will not require new or expanded offsite storm drainage facilities. However, at the time of building permit plan check, the developer shall submit a grading plan and a Drainage Study prepared by a registered Civil Engineer that recommends adequate drainage facilities to properly accept and convey drainage flows from the Specific Plan area. The study shall be reviewed and approved by the City Engineer, pursuant to Section XI-10-11.07(E), Administration, of this Specific Plan. Developer shall incorporate the conclusions and recommendations of the approved Drainage Study prior to building permit issuance. e. Solid Waste Disposal. Republic Services provides solid waste and recycling services to the City of Milpitas, including the Specific Plan area. During construction, it is estimated that the Specific Plan area would generate approximately five thousand seven hundred thirty-seven (5,737) tons of solid waste.

During operation, it is estimated that the Specific Plan area would generate approximately 361.7 tons of solid waste annually. Before starting construction in the Specific Plan area, developer shall retain a qualified contractor to perform construction and demolition debris recycling. Developer must document, to the satisfaction of the City of Milpitas, that construction and demolition debris was recycled. Before building permit issuance, developer shall show on-site facilities necessary to collect and store recyclable materials. The facilities shall include receptacles in public spaces that are of high-quality design and identify accepted materials. Business owners in the Specific Plan area must comply with best management practices for the handling of solid and food wastes, as permitted by and in compliance with local and state solid waste disposal regulations.
f. Natural Gas. PG&E will provide natural gas service to the Specific Plan area and has available natural gas supplies and appropriate transmission capacity to serve the Specific Plan area. The Specific Plan area's estimated annual natural gas consumption is 8.79 million cubic feet. g. Police Protection. The Milpitas Police Department will provide police protection to the Specific Plan area. No new or expanded police protection facilities are necessary to serve the Specific Plan area. h. Fire. The Milpitas Fire Department will provide fire protection and emergency medical services to the Specific Plan area. No new or expanded fire protection facilities are necessary to serve the Specific Plan area.

Page 113 of 395 ends

i. Electricity and Telephone. The Specific Plan area is located within PG&E's service territory.

PG&E would provide electrical services to the Specific Plan area. PG&E has available electricity supplies and appropriate transmission capacity to serve the Specific Plan area. The Specific Plan area's estimated annual electricity consumption is 2.37 million kilowatt hours.

Telephone service to the Specific Plan area will be provided by AT&T. j. Schools. Prior to the issuance of building permits, the developer shall pay school impact fees.

Impact fees are currently forty-seven cents ($0.47) per square foot.

2. Project Access. Access to the Specific Plan area allows for safe and efficient travel to and from the area. Administrative provisions and signage of the Specific Plan will facilitate direction and access throughout the area. Public transportation exists in the Specific Plan area and a direct pedestrian connection links the existing retail building with the Ranch Drive sidewalk, allowing for safe and convenient access between the existing retail building and the bus stop. A designated pedestrian connection between the existing retail building and the balance of the McCarthy Ranch Marketplace to the south and Ranch Drive to the north exists and will be maintained with any development of the Specific Plan area.

Vehicular access to the Specific Plan area will be provided by two (2) driveways onto Ranch Drive and a McCarthy Ranch Marketplace driveway entrance located to the southeast of the existing retail building.

The driveways on Ranch Drive are stop-controlled and provide single-lane ingress and egress. Truck deliveries would enter via the northern driveway along Ranch Drive and immediately turn right and travel westbound towards the loading dock. Trucks exiting the site would retrace their path to the northern Ranch Drive driveway.

Prior to the issuance of a Certificate of Occupancy, Developer shall obtain the necessary approvals for the installation of VTA bus stop improvements consisting of retention of the bus stop in its existing location, and installation of a seven-foot by twenty-foot Portland cement concrete shelter pad behind the sidewalk/passenger waiting pad with retaining wall. Bicycle storage facilities shall also be installed prior to the issuance of the final certificate of occupancy. These facilities shall consist of at least one (1) rack located in a visible and convenient location (i.e., near the entrance to the building) and that provides storage equivalent to two (2) percent of the minimum parking requirement in the Specific Plan area.

Developer also shall work with and negotiate in good faith with the adjacent property owner to obtain permission for the design and construction of striped pedestrian crossing and associated median and/or ramp modifications at the shared driveway for McCarthy Ranch Marketplace and Specific Plan area entrances.

3. Grading. Given the relatively level topography within the Specific Plan area, development will result in modest changes to topography and ground surface features. During grading and construction, however, developer shall adhere to all applicable recommendations for abating expansive soil conditions contained in the Geotechnical Engineering Investigation or comparable geotechnical study. Prior to the issuance of grading permits, developer shall prepare and submit a Stormwater Pollution Prevention Plan (SWPPP) to the City of Milpitas that identifies specific actions and Best Management Practices (BMPs) to prevent stormwater pollution during construction activities.

4. Construction. During all construction activities within the Milpitas Commercial Specific Plan area, the following measures shall be implemented:
a. Water all active construction areas and exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved access roads) at least two (2) times per day; b. Cover all trucks hauling soil, sand, and other loose materials or require all trucks to maintain at least two (2) feet of freeboard;

Page 114 of 395 ends

c. Pave, apply water three (3) times daily, or apply (non-toxic) soil stabilizers on all unpaved access roads, parking areas and staging areas at construction sites; d. Sweep daily (with water sweepers) all paved access roads, parking areas, and staging areas at construction sites;
e. Sweep streets daily (with water sweepers) if visible soil material is carried onto adjacent public streets;
f. All vehicle speeds on unpaved roads shall be limited to fifteen (15) miles per hour; g. All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible.

Building pads shall be laid as soon as possible after grading unless seeding or soil binders are used; h. Idling times shall be minimized either by shutting equipment off when not in use or reducing the maximum idling time to five (5) minutes (as required by the California airborne toxics control measure Title 13, Section 2485 of California Code of Regulations). Clear signage shall be provided for construction workers at all access points;
i. All construction equipment shall be maintained and properly tuned in accordance with manufacturer's specifications. All equipment shall be checked by a certified mechanic and determined to be running in proper condition prior to operation; and, j. A publicly visible sign shall be posted with the telephone number and person to contact at the City of Milpitas regarding dust complaints. This person shall respond and take corrective action within forty-eight (48) hours. The phone number of the Bay Area Air Quality Management District shall also be visible to ensure compliance with applicable regulations.

5. Fiscal Implementation. Implementation of the Specific Plan including, without limitation, construction of all infrastructure and private facilities contemplated in the Specific Plan, will be financed as follows:
a. All infrastructure necessary to implement the Specific Plan will be privately funded (by way of debt and/or equity financing), except to the extent that the cost of components of the infrastructure is a) funded by development impact fees, fair share contributions and other payments to public agencies and/or b) reimbursed from any public source.
b. All private improvements necessary to implement the Specific Plan will be privately financed (by way of debt and/or equity financing).

E. Administration.

1. Permit Processing. Development within the Specific Plan area that is consistent with the provisions of the Milpitas Commercial Specific Plan and the conceptual site plan, elevations, colors and materials, and landscaping as depicted in Figures XI-10-11-07-6 through -9, and the conditions and requirements set forth in Figure 10, shall be processed under building permit and/or construction plan review and no additional approvals or permits shall be required. Any review or action by City agencies, entities or individuals (i.e., the Milpitas Police Department; the City Engineer; the City Building Department; Planning Director) on such development submittals shall be considered part of building permit and/or construction plan review. The action shall be limited to a determination of compliance with the provisions of the Milpitas Commercial Specific Plan and all applicable building codes and other requirements of the City, County, State and/or other responsible agencies. Building permit and/or construction plan review shall be non-discretionary, final actions that cannot be appealed.

Development that is not consistent with the development standards set forth in the Milpitas Commercial Specific Plan, shall either require a Substantial Conformance Determination, as discussed below, or require approval under the provisions and requirements of the Milpitas Zoning Code for development in the C2 Zone.

Page 115 of 395 ends

Any building permit issuance in the Specific Plan area will be conditioned on the availability of water and sewage capacity as set forth in Sections XI-10-11.07(D)(1)(b) and XI-10-11.07(D)(1)(c). Conformance with the provisions of this Specific Plan do not provide a vested right to the issuance of a Building Permit as water and sewage capacity availability is a material (demand/supply) condition to development on the Specific Plan area.

2. Existing Uses. Operation and maintenance of existing uses or structures in the Specific Plan area are not subject to the provisions of the Milpitas Commercial Specific Plan provided a building permit has been obtained and is still valid at the time of the effective date of the provisions codified in this title. Any expansion or development of existing uses or structures, however, would require compliance with the provisions of the Milpitas Commercial Specific Plan.

3. Substantial Conformance Determination.
a. Purpose. A Substantial Conformance Determination is a mechanism to allow the approval of minor modifications for development under the Specific Plan. A Substantial Conformance Determination may include, but is not limited to, minor modifications to the conceptual plans (Figures XI-10-11.07-6 through-9); inclusion of land uses not listed in Section XI-10-11.07(C)(1) of the Specific Plan; modifications that might be necessary to comply with applicable infrastructure, public services and facilities requirements, and landscape palette; and other issues. A Substantial Conformance Determination does not apply to significant modifications in the basic design of the Specific Plan area; changes to the height or bulk of the approved uses; or increases in the density or intensity of the approved uses unless specifically permitted by the provisions of this Specific Plan.

The purpose of a Substantial Conformance Determination is to ensure orderly development, quality aesthetic design, and safe and harmonious placement of uses within the Specific Plan area. A Substantial Conformance Determination (unless specifically noted otherwise) shall be made by the Planning Director or designee administratively, without the need for a public hearing. In making a Substantial Conformance Determination, the Planning Director or designee shall first make all of the required findings set forth in this section.
b. Guidelines For A Substantial Conformance Determination. The following guidelines explain the requirements for making a Substantial Conformance Determination, and the limits placed on the degree of variance from the provisions of the Specific Plan that can occur as part of a Substantial Conformance Determination.
i. Permitted Land Uses. Land uses not listed as permitted in Section XI-10-11.07(C)(1) of this Specific Plan may be permitted, with a Substantial Conformance Determination, provided that:
(1) The proposed use is compatible with the uses permitted described in Section XI-10-11.07(C)(1) of this Specific Plan; and
(2) The proposed use is similar to and will not cause environmental impacts substantially greater than the other permitted uses set forth within Section XI-10-11.07(C)(1) of this Specific Plan. ii. Infrastructure. Any modifications to the alignment of access roads; parking lot configurations, or adjustments to individual infrastructure facilities plans such as drainage, sewer, water, and utilities shall be subject to a Substantial Conformance Determination by the Planning Director or designee. Prior to making a Substantial Conformance Determination, the Planning Director or designee shall make the finding that the proposed modification will not result in any environmental impacts substantially greater than those which would occur without any modification.
iii. Environmental Performance Standards. The Planning Director or designee may approve minor variations from the environmental performance standards set forth in Section XI-10-11.07(F), Environmental Performance Standards, of this Specific Plan, with a Substantial Conformance Determination. In making such a determination, the Planning Director or designee shall first find that the

Page 116 of 395 ends

proposed variation provides substantially equivalent environmental protection as the originally approved standard.
iv. Conceptual Plan and Other Specific Plan Provisions. Provisions of the Specific Plan including, but not limited to, architectural details; landscape palette; building size, height, bulk, and orientation; parking lot layout; and other plan details may be modified with a Substantial Conformance Determination. In making such a determination, the Planning Director or designee shall be required to find that the revisions requested as part of a Substantial Conformance Determination are consistent with the provisions of the Milpitas General Plan, and will not create impacts substantially greater than those that would have resulted from the original approval of the Specific Plan.

A maximum ten (10) percent modification to permitted lot coverage, setbacks, floor area (other than the maximum allowable with the Specific Plan area), parking and fence and wall heights may be permitted subject to a Substantial Conformance Determination by the Planning Director or designee. In making such a determination, the Planning Director or designee shall be required to find that the revisions requested as part of a Substantial Conformance Determination are consistent with the provisions of the Milpitas General Plan, and will not create impacts substantially greater than those that would have resulted from the original approval of the Specific Plan.

The required parking spaces may be reduced by the Planning Director or designee subject to a Substantial Conformance Determination after preparation of a parking study demonstrating the proposed reduction in parking spaces is justified based on the mix of uses within the Specific Plan area and the use of shared parking between those uses.

A comprehensive sign program shall be submitted to the Planning Director for finding that it complies with the signage requirements of the Milpitas Commercial Specific Plan. Such finding shall be made as a part of building permit and/or construction plan review. Any subsequent sign permit applications that substantially comply with the comprehensive sign program shall be shall be processed as a ministerial building permit and/or construction plan review. Any comprehensive sign program that does not comply with the signage requirements of the Milpitas Commercial Specific Plan shall require a Substantial Conformance Determination.

4. Substantial Conformance Determination Procedure.
a. Application. Applications for a Substantial Conformance Determination shall be made on forms provided by the Planning Director or designee and shall be accompanied by a filing fee, equivalent to the fee for a Site Development Permit application. Applications shall be made by the owner of the property for which the approval is sought, or an authorized agent. b. Hearing. No public hearing shall be required for a Substantial Conformance Determination. c. Action by Reviewing Authority. The reviewing authority for a Substantial Conformance Determination shall be the Planning Director or designee. The reviewing authority shall take action by providing written notice to the applicant or developer approving, conditionally approving, or denying a Substantial Conformance Determination. The action of the Planning Director or designee shall be final with no appeal.
d. Findings. The Planning Director or designee must make a Substantial Conformance Determination if all of the following findings, in addition to those identified above, can be made:
i. The physical characteristics of the site have been adequately assessed, and proposed building sites are of adequate size and shape to accommodate proposed uses and all other features of development. ii. There is supporting infrastructure, existing or available, consistent with the requirements of the Milpitas Commercial Specific Plan, to accommodate the development without significantly lowering service levels.

Page 117 of 395 ends

iii. The development resulting from the determination of substantial conformance will not have a substantial adverse effect on surrounding property or the permitted use thereof, and will be compatible with the existing and planned land uses, as well as the character of the surrounding area. iv. The proposed improvements related to the development resulting from a Substantial Conformance Determination adequately address all natural and man-made hazards associated with the proposed development and the project site.

5. Periodic Review. After receiving a certificate of occupancy, development in the Milpitas Commercial Specific Plan Area is subject to a six-, twelve- and eighteen-month review by the Planning Commission. The review shall be a public hearing to review conformance of the development with the requirements of the Milpitas Commercial Specific Plan.

6. Specific Plan Amendments.
a. Purpose. Specific Plan amendments are governed by Government Code Section 65453 and the Milpitas Municipal Code Section XI-10-57.02.
b. Process.
i. The Specific Plan may be amended or repealed only by a majority of the voters voting in an election thereon.
ii. Notwithstanding subsection (a), upon application of the fee title holder of the Milpitas Commercial Specific Plan area, the City Council may amend the Specific Plan to further the purposes of this Specific Plan, but in no case can such amendment reduce or eliminate the parties' obligation to fund, construct, or cause to be funded or constructed, the public benefits or Environmental Performance Standards required.

F. Environmental Performance Standards. The Specific Plan includes environmental performance standards to ensure that development proceeds with appropriate environmental sensitivity. Environmental studies related to aesthetics, light and glare, health risks, air quality, biological resources, geology, soils and seismicity, hazards and hazardous materials, hydrology and water quality, noise, public services and utilities, transportation and urban decay were conducted for an expansion of the existing retail facility in the Specific Plan area. Environmental performance standards were developed from these environmental studies along with information from the City of Milpitas General Plan.

All environmental performance standards shall be implemented in accordance with the Specific Plan's environmental performance standards and implementation process as outlined in Table XI-10-11.07-6, Milpitas Commercial Specific Plan Environmental Performance Standards. The developer of the Specific Plan area shall bear all costs of implementing the environmental performance standards.

Table XI-10-11.07-6 - Milpitas Commercial Specific Plan Environmental Performance Standards Environmental Performance
Standards
Method of
Verification
Timing of
Verification
Responsible for
Verification
Verification
of
Completion
Date Initial

1. Aesthetics, Light, and Glare
AES-1a: Prior to issuance of
building permits, the
developer shall prepare and
submit a sign program to the
Approval of
plans
Prior to
issuance of
City of Milpitas
Planning
Department

Page 118 of 395 ends

City of Milpitas for review
and approval. The sign
program shall demonstrate
compliance with the
applicable requirements with
Milpitas Municipal Code Title
XI, Chapter 30. The approved
sign program shall be
implemented into the proposed
project.
building
permits
AES-1b: Prior to issuance of
grading or building permits,
whichever comes first, the
developer shall obtain a tree
removal permit from the City
of Milpitas for any trees slated
for removal with a trunk
circumference of 37 inches or
more measured at 4.5 feet
above ground level.

Replacement of such trees
shall be performed in
accordance with the
requirements of the Tree
Maintenance and Protection
Ordinance. Removed trees that
are not covered by the Tree
Maintenance and Protection
Ordinance (i.e., less than 37
inches in circumference at 4.5
feet above ground level) shall
be replaced onsite with a
similar tree species at no less
than a 1:1 ratio. All
replacement trees shall be
planted prior to the issuance of
the final certificate of
occupancy.

Issuance of
permit; Site
inspection
Prior to
issuance of
grading or
building
permits
(whichever
comes first);
Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department and
Public Works
Department
AES-1c: Prior to issuance of
the final certificate of
occupancy, the developer shall
do one of the following: 1)
permanently remove all
shipping containers from the
project site; or 2) obtain a
minor Site Development
Permit Approval and install
screening measures in
accordance with Zoning
Site inspection Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department

Page 119 of 395 ends

Ordinance requirements. If the
second option is pursued,
outdoor storage of containers
shall occur in a completely
enclosed building or behind a
visually obscure solid wall or
tight board fence a minimum 6
feet in height and outside any
front or street side yard
setback area.

AES-2: Prior issuance
building permits, the
developer shall ensure that all
exterior lighting fixtures
associated with the existing
retail building (building-
mounted and freestanding) are
shielded, recessed, or directed
downward to prevent
unwanted illumination of
neighboring properties.

Approval of
plans
Prior issuance
building
permits
City of Milpitas
Planning
Department

2. Air Quality
AIR-3: The following
measures shall be
implemented during all
construction activities:

Site inspection During
construction
activities
City of Milpitas
Office of
Building
SafetyBuilding
Safety and
Housing
Department
• Water all active construction
areas and exposed surfaces
(e.g., parking areas, staging
areas, soil piles, graded areas,
and unpaved access roads) at
least two times per day.
• Cover all trucks hauling soil,
sand, and other loose materials
or require all trucks to
maintain at least 2 feet of
freeboard.
• Pave, apply water three
times daily, or apply (non-
toxic) soil stabilizers on all
unpaved access roads, parking
areas and staging areas at
construction sites.

Page 120 of 395 ends

• Sweep daily (with water
sweepers) all paved access
roads, parking areas, and
staging areas at construction
sites.
• Sweep streets daily (with
water sweepers) if visible soil
material is carried onto
adjacent public streets.
• All vehicle speeds on
unpaved roads shall be limited
to 15 miles per hour.
• All roadways, driveways,
and sidewalks to be paved
shall be completed as soon as
possible. Building pads shall
be laid as soon as possible
after grading unless seeding or
soil binders are used.
• Idling times shall be
minimized either by shutting
equipment off when not in use
or reducing the maximum
idling time to 5 minutes (as
required by the California
airborne toxics control
measure Title 13, Section
2485 of California Code of
Regulations). Clear signage
shall be provided for
construction workers at all
access points.
• All construction equipment
shall be maintained and
properly tuned in accordance
with manufacturer's
specifications. All equipment
shall be checked by a certified
mechanic and determined to
be running in proper condition
prior to operation.
• Post a publicly visible sign
with the telephone number and
person to contact at the City of
Milpitas regarding dust
complaints. This person shall

Page 121 of 395 ends

respond and take corrective
action within 48 hours. The
phone number of the Bay Area
Air Quality Management
District shall also be visible to
ensure compliance with
applicable regulations.

AIR-7a: The developer shall
use paving materials with
increased solar reflectivity in
areas where pavement is
replaced. Such materials shall
use light-colored aggregate or
other appropriate methods to
achieve high solar reflectivity.

The developer shall provide
construction details and
specifications that shall be
submitted with construction
drawings and installed with
improvements.

Approval of
plans and site
inspection
Prior to
issuance of
Building
Permit
City of Milpitas
Planning
Department
AIR-7b: Prior to issuance of
the final certificate of
occupancy, the developer shall
post signs in the loading docks
advising truck drivers to turn
off engines when not in use
and advising truck drivers of
state law prohibiting diesel
idling of more than 5 minutes.

Site inspection Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department
AIR-7c: Prior to issuance of
the final certificate of
occupancy, the developer shall
do the following:

Approval of
plans; Site
inspection;
ongoing
Prior to
issuance of the
building
permit;
ongoing.

City of Milpitas
Planning
Department and
Office of
Building
SafetyBuilding
Safety and
Housing
Department
• Prior to building permit
issuance, a secondary closed
loop system shall be evaluated
and implemented, if found to
be technically and
economically feasible. Details
and specifications shall be

Page 122 of 395 ends

included with the construction
drawings.
• The developer shall
maintain the refrigeration
system at least once per year
to ensure that refrigerant leaks
remain minimal. The
maintenance records shall be
kept onsite for review by the
City of Milpitas.
• During installation of the
new refrigerators and freezers,
effort shall be made to reuse
the existing refrigerants in the
new system, unless the old
refrigerant is not the same type
as is proposed in the new
system or more leakage would
occur if the refrigerants are
reused.

AIR-7d: Prior to issuance of
the final certificate of
occupancy, the developer shall
provide the following
Transportation Demand
Management measures:

Site inspection Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department
• Public transit information in
the employee breakroom.

Store management shall post
information such as Santa
Clara Valley Transportation
Authority bus and light rail
schedules, maps, and fares.
• Ride sharing information in
the employee breakroom.

Store management shall
facilitate ride sharing by
providing sign-up sheets or
other measures to allow
interested employees to
identify carpooling
opportunities.
• Bicycling information. Store
management shall post
information such as bicycle
route maps and information

Page 123 of 395 ends

about taking bikes on public
transportation.

AIR-7e: To reduce
construction related
greenhouse gas impacts, the
following measures are
required:

Submittal of
documentation
During
construction
activities
City of Milpitas
Planning
Department
• At least 15 percent of the
construction
vehicles/equipment shall be
fueled by an alternative source
such as biodiesel and/or
electric.
• At least 10 percent of all
building materials shall be
local (within 100 miles); and
• At least 50 percent of
construction and demolition
materials shall be recycled.

This latter provision shall be
coordinated with Mitigation
Measure PSU-6a.

3. Biological Resources
BIO-1: If vegetation removal
associated with development
of the property is to occur
during the nesting bird season
(February 15 through August
31), a qualified biologist shall
conduct a pre-construction
survey for nesting birds to
identify any potential nesting
activity. The pre-construction
surveys for nesting birds shall
be conducted within 14 days
prior to any construction-
related activities (grading,
ground clearing, etc.). If
nesting birds are identified on
the site, a 100-foot buffer shall
be maintained around the
nests; no construction-related
activities shall be permitted
within the 100-foot buffer. A
qualified biologist shall
monitor the nests, and
Submittal of
documentation;
Site inspection
Within 14 days
prior to any
construction-
related
activities
during the
nesting bird
season
(February 15
through August
31)
City of Milpitas
Planning
Department

Page 124 of 395 ends

construction activities may
commence within the buffer
area at the discretion and
presence of the biological
monitor. The pre-construction
survey for nesting birds shall
not be required if construction
activities occur outside of the
nesting bird season
(September 1 through
February 14).

4. Geology, Soils, and Seismicity
GEO-1a: Prior to issuance of
building permits, the
developer shall submit a
seismic hazards technical
study prepared by a qualified
geotechnical engineer to the
City of Milpitas for review
and approval. The report shall
be prepared in accordance
with the requirements of the
Seismic Hazards Mapping Act
and shall identify necessary
design measures to reduce
potential seismic ground
shaking impacts to acceptable
levels. The developer shall
incorporate the approved
design measures into the
project plans.

Approval of
plans
Prior to
issuance of
building
permits
City of Milpitas
Office of
Building
SafetyBuilding
Safety and
Housing
Department
GEO-1b: Prior to issuance of
building permits, the
developer shall submit a
design-level geotechnical
investigation to the City of
Milpitas for review and
approval. The design-level
investigation shall address the
potential for ground failure to
occur onsite and identify
abatement measures to reduce
the potential for such an event
to acceptable levels. The
abatement measures shall be
incorporated into the project
design.

Approval of
plans
Prior to
issuance of
building
permits
City of Milpitas
Office of
Building
SafetyBuilding
Safety and
Housing
Department

Page 125 of 395 ends

GEO-1c: Prior to issuance of
building permits, the
developer shall submit plans to
the City of Milpitas for review
and approval that demonstrate
that the proposed project is
designed in accordance with
all state and local seismic
safety requirements. Such
requirements shall include the
California Building Standards
Code and Milpitas Municipal
Code, Title II. The approved
plans shall be incorporated
into the project design.

Approval of
plans
Prior to
issuance of
building
permits
City of Milpitas
Office of
Building
SafetyBuilding
Safety and
Housing
Department
GEO-4: During grading and
construction, the developer
shall adhere to all applicable
recommendations for abating
expansive soil conditions
contained in the Geotechnical
Engineering Investigation or
comparable geotechnical
study. This includes the
excavation of expansive soils
and the subsequent
replacement of such soils with
non-expansive engineered fill.

Site inspection During grading
and
construction
City of Milpitas
Office of
Building
SafetyBuilding
Safety and
Housing
Department

5. Hydrology and Water Quality
HYD-1: Prior to the issuance
of grading permits for the
proposed project, the
developer shall prepare and
submit a Stormwater Pollution
Prevention Plan (SWPPP) to
the City of Milpitas that
identifies specific actions and
Best Management Practices
(BMPs) to prevent stormwater
pollution during construction
activities. The SWPPP shall
identify a practical sequence
for BMP implementation and
maintenance, site restoration,
contingency measures,
responsible parties, and
agency contacts. The SWPPP
shall include, but not be
Approval of
plan
Prior to the
issuance of
grading permits
City of Milpitas
Planning
Department and
Engineering
DepartmentPublic
Works
Department

Page 126 of 395 ends

limited to, the following
elements:
• Temporary erosion control
measures shall be employed
for disturbed areas.
• No disturbed surfaces shall
be left without erosion control
measures in place during the
winter and spring months.
• Sediment shall be retained
onsite by a system of sediment
basins, traps, or other
appropriate measures.
• The construction contractor
shall prepare Standard
Operating Procedures for the
handling of hazardous
materials on the construction
site to eliminate or reduce
discharge of materials to storm
drains.
• BMP performance and
effectiveness shall be
determined either by visual
means where applicable (e.g.,
observation of above-normal
sediment release), or by actual
water sampling in cases where
verification of contaminant
reduction or elimination (such
as inadvertent petroleum
release) is required by the
RWQCB to determine
adequacy of the measure.
• In the event of significant
construction delays or delays
in final landscape installation,
native grasses or other
appropriate vegetative cover
shall be established on the
construction site as soon as
possible after disturbance, as
an interim erosion control
measure throughout the wet
season.

Page 127 of 395 ends

HYD-2: Prior to the issuance
of building permits for the
proposed project, the
developer shall submit a
stormwater management plan
to the City of Milpitas for
review and approval. The
stormwater management plan
shall comply with the
requirements of Milpitas
Municipal Code Title XI,
Chapter 16 and identify
pollution prevention measures
and practices to prevent
polluted runoff from leaving
the project site. Examples of
stormwater pollution
prevention measures and
practices to be contained in the
plan include, but are not
limited to:

Approval of
plan
Prior to the
issuance of
building
permits
City of Milpitas
Planning
Department and
Engineering
DepartmentPublic
Works
Department
• Strategically placed
bioswales and landscaped
areas that promote percolation
of runoff
• Pervious pavement
• Roof drains that discharge to
landscaped areas
• Trash enclosures with screen
walls
• Stenciling on storm drains
• Curb cuts in parking areas to
allow runoff to enter
landscaped areas
• Rock-lined areas along
landscaped areas in parking
lots
• Catch basins
• Oil/water separators
• Regular sweeping of parking
areas and cleaning of storm
drainage facilities

Page 128 of 395 ends

• Employee training to inform
store personnel of stormwater
pollution prevention measures
The developer shall also
prepare and submit an
Operations and Maintenance
Agreement to the City
identifying procedures to
ensure that stormwater quality
control measures work
properly during operations.

6. Public Services and Utilities
PSU-3: Prior to building
permit issuance, the developer
shall include details and
specification in the
construction drawings and
install the following indoor
water conservation measures:

Approval of
plans
Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department,
Office of
Building Safety
Building Safety
and Housing
Department and
Engineering
DepartmentPublic
Works
Department
• Low-flow or ultra-low-flow
toilets and urinals
• Sensor-activated faucets in
restrooms
PSU-6a: Prior to the
commencement of
construction activities, the
developer shall retain a
qualified contractor to perform
construction and demolition
debris recycling. The
developer shall provide
documentation to the
satisfaction of the City of
Milpitas demonstrating that
construction and demolition
debris was recycled.

Submittal of
documentation
Prior to
issuance of
building
permits
City of Milpitas
Planning
Department
PSU-6b: Prior to building
permit issuance, the developer
shall show onsite facilities
necessary to collect and store
Approval of
plans; Site
inspection
Prior to
issuance of
building
permits
City of Milpitas
Planning
Department

Page 129 of 395 ends

recyclable materials. The
facilities shall include
receptacles in public spaces
that are of high-quality design
and identify accepted
materials.

7. Transportation
TRANS-1a: Prior to the
issuance of building permits,
the developer shall provide
fair-share fees to the City of
Milpitas for improvements to
the Dixon Landing Road/N.

Milpitas Boulevard
intersection and the widening
of Dixon Landing Road in the
amount of $31,960 ($3,000 for
the intersection improvement
and $28,960 for the roadway
widening). The fees will go
towards the following
intersection improvements: 1)
modifying the signal operation
to include a southbound right-
turn overlap and subsequent
signal timing optimization or
2) adding a northbound left
turn lane, a southbound right-
turn lane, and eastbound left-
turn and right-turn lanes. The
widening shall consist of
adding an additional lane in
each direction between I-880
and N. Milpitas Boulevard.

Both improvements are
identified in the Valley
Transportation Plan 2035.

Receipt of fees Prior to the
issuance of
building
permits
City of Milpitas
Planning
Department
TRANS-1b: Prior to the
issuance of final certificate of
occupancy, the developer shall
provide the City of Milpitas
the full cost of signal timing
modifications at the N.

McCarthy Boulevard/Ranch
Drive (south) intersection in
the estimated amount of
$2,500 dollars. The
modifications shall consist of
Receipt of fees Prior to the
issuance of
final certificate
of occupancy
City of Milpitas
Planning
Department

Page 130 of 395 ends

re-timing the signal to increase
the current cycle length. This
mitigation measure shall not
apply if the signal timing is
modified prior to the
developer seeking the final
certificate of occupancy.

TRANS-3: Prior to issuance of
building permits, the
developer shall provide a
traffic management fee in the
amount of $180,000 to the
City of Milpitas. The fees shall
be used for circulation and
traffic operation improvements
within the City of Milpitas,
including signal coordination
and intersection
improvements. Specific
improvements that shall be
fully funded by funds
collected shall include:

Receipt of fees Prior to
issuance of
building
permits
City of Milpitas
Planning
Department
• McCarthy
Boulevard/Technology Drive:

The eastbound approach shall
be re-striped to provide two
left-turn lanes and one shared
through/right lane.
• McCarthy Boulevard/SR-
237 Westbound Ramps: An
additional westbound right-
turn lane shall be constructed
to provide two left-turn lanes,
two through lanes, and two
right-turn lanes for the
westbound approach.
• Ranch Drive: The roadway
shall be restriped to extend the
existing two-way left-turn lane
from the northern driveway of
the existing retail building to
the end of the existing
westbound left-turn lane at the
McCarthy Boulevard/Ranch
Drive (North) intersection.

Page 131 of 395 ends

TRANS-5: Prior to issuance of
building permits, the
developer shall prepare and
submit a site plan to the City
of Milpitas that demonstrates
that off-street parking is
provided onsite complies with
the Milpitas Municipal Code
Parking Regulations and
Development Standards. The
approved site plan shall be
incorporated into the proposed
project.

Approval of
plan
(Note: Project
plans
submitted
comply with
the City's off-
street parking
requirements)
Prior to
issuance of
building
permits
City of Milpitas
Planning
Department
TRANS-8: Prior to building
permit issuance, the developer
shall provide details and
specifications for bicycle
storage facilities on the
construction drawings and
install prior to occupancy.

Bicycle storage facilities shall
consist of at least one rack
located in a visible and
convenient location (e.g., near
the store entrance) and that
provides storage equivalent to
2 percent of the proposed
project's minimum parking
requirement.

Approval of
plans; Site
inspection
Prior to
issuance of the
final certificate
of occupancy
City of Milpitas
Planning
Department
TRANS-9: Prior to
commencement of
construction activities, the
developer shall submit a
Construction Traffic Control
Plan to the City of Milpitas for
review and approval. The plan
shall identify the timing and
routing of all major
construction equipment and
materials deliveries to avoid
potential traffic congestion
and delays on the local street
network and the McCarthy
Ranch Marketplace, and to
encourage the use of I-880 and
SR-237. If necessary,
construction equipment and
materials deliveries shall be
limited to off-peak hours (e.g.,
Approval of
plan
Prior to
commencement
of construction
activities
City of Milpitas
Planning
Department

Page 132 of 395 ends

mornings or evenings) to
avoid conflicts with local
traffic circulation. The plan
shall also identify suitable
locations for construction
worker parking.

XI-10-13.07 Manufactured Homes
A. Purpose and Intent. This Section provides standards and procedures for individual manufactured homes on individual lots in residential zones. These standards are provided to ensure the compatibility of manufactured homes with other surrounding permitted uses, create a safe and desirable living environment for manufactured home residences, and address land use compatibility.

B. Applicability and Review Requirements. A single manufactured home may be permitted on lots zoned for single-family dwellings where it has been determined the lot and structure are compatible:

1. In districts where site plan and architectural review is not generally required for single-family dwellings, the site plan and architectural review process shall be utilized to initially determine if a lot and structure is compatible for a manufactured home. Compatibility of a lot and structure shall be determined by such factors as height, bulk and character of other structures in the neighborhood. If a lot and structure is determined to be compatible, site plan and architectural review is limited only to specifying roof overhang, roofing material and siding material based on the following standards.

C. Development Standards. The following development standards shall be applicable to the establishment of manufactured homes as single-family dwellings in the R1 District:

1. Manufactured homes and any garages, carports, and other structures attached thereto, must conform to all regulations for single-family dwellings applicable to the zone.

2. Manufactured homes must be certified under the National Manufactured Housing Construction and Safety Standards Act of 1974.

3. Manufactured homes must be attached to a permanent engineered perimeter foundation system approved by the Chief Building OfficialBuilding Official and pursuant to Section 18551 of the State Health and Safety Code.

4. Manufactured homes must be covered with stucco and/or wood siding or an exterior material commonly found on new conventionally erected single-family dwellings in the surrounding area.

5. The roofing material must be wood or composition shingles or other materials commonly found on conventionally erected single-family dwellings in the surrounding area. The roof must have a minimum pitch with respect to roofing material in accordance with the City of Milpitas Building Code.

6. The roof must have eave and gable overhangs of not less than eighteen (18) inches measured horizontally from the vertical side of the mobile home. The overhang must be constructed with materials commonly found on conventionally erected single-family dwellings in the surrounding area and must be at the same slope and be covered with the same roofing material as the roof itself.

7. The exterior covering and roofing materials of the garage, carport, or any other structure attached to the manufactured home must be the same as for the manufactured home.

Page 133 of 395 ends

8. As used in this Section, "commonly found" means an architectural feature or construction material that occurs or appears frequently on conventionally erected single-family dwellings within five hundred (500) feet of the boundaries of the lot or parcel on which a manufactured home is proposed.

XI-10-13.14 Emergency Shelters.

A. Purpose and Intent. The purpose of this Section is to comply with California Government Code Section 65583(a)(4), as may be amended, which requires that emergency shelters be permitted by- right in at least one zone with sufficient capacity to accommodate the local need for emergency shelter.

B. Applicability. Standards for Emergency Shelters contained in this Section shall apply to all Emergency Shelters where permitted by this Chapter.

C. Minimum Standards.

1. A management plan shall be submitted to the City Planning Division for review and approval prior to issuance of an occupancy permit. Management plans shall be resubmitted to City Planning Division on an annual basis for review and approval.

2. The number of beds for each Emergency Shelter shall be limited to thirty (30).

3. Parking requirements shall be either one space per three hundred (300) square feet of habitable floor area, or sufficient to serve the parking demand determined in a study prepared by the applicant and approved by the Planning Division.

4. The size of outdoor waiting areas on private property shall be sufficient to accommodate the expected number of clients without infringing upon the public right-of-way.

5. Onsite management shall be provided during the hours that the emergency shelter is in operation.

6. An emergency shelter shall not be located within 300 feet of other emergency shelters.

7. The length of stay for each individual at any emergency shelter shall not exceed 90 days, unless the management plan approved by City provides for longer residency by those enrolled and regularly participating in a training or rehabilitation program.

8. Exterior lighting of the property shall be designed to provide a minimum maintained horizontal illumination of at least one foot candle of light on parking surfaces and walkways that serve the facility. Illumination shall not extend across property lines to an adjacent property.

9. Security shall be provided during the hours that the emergency shelter is in operation. Security plans shall be submitted to City staff for review and approval prior to issuance of an occupancy permit. Security plans shall be resubmitted to City staff on an annual basis for review and approval.

D. Additional Standards. The Director of Planning may adopt additional written objective minimum standards consistent with California Government Code Section 65583(a)(4)(A), as may be amended.

Any such administrative standards adopted by the Director of Planning and Neighborhood Services shall be published on the Planning Division's website.

XI-10-63.03 Declaration of Public Nuisance

1. General. The use of any land, building or other structure hereafter established or conducted or the present use of any land, building or other structure hereafter extended or enlarged or the erection, construction, moving, conversion, remodeling or alteration of any building or other structure

Page 134 of 395 ends

contrary to the provisions of this Chapter shall be and the same is hereby declared to be a public nuisance, and the Attorney for the City of Milpitas shall, upon order of the City Council, immediately commence action or proceedings for the abatement or removal or enjoinment thereof in the manner provided by law.

2. Signs. Any sign or structure erected, constructed, maintained, marked, posted, pasted, painted, printed, altered or repaired in violation of the provisions of the Chapter or after a permit or variance therefore has been revoked or expired is hereby found and declared to be a public nuisance subject to abatement and lien for recovery of abatement costs.
a. Without limitation to the generality of the foregoing, any sign or structure erected, constructed, maintained, marked, posted, pasted, painted, altered or repaired:
i. So as to be unsafe and so as to constitute an immediate peril to persons or property; or ii. Upon public property without written permission of the Planning Division Department or City Manager of the City of Milpitas.

XI-500-6.00 Acceptance by Director
The Community DevelopmentPlanning Director may accept an easement as described in this part on behalf of the City when such an easement is required as a condition of a land use approval, permit or designation pursuant to this Title.

XI-500-7.00 Recordation
The covenant of easement shall be recorded in the county recorder's office. A copy of the recorded document shall be provided to the Community DevelopmentPlanning Director.

XI-500-11.00 Petition for Release
A petition for release of a covenant of easement may be made by any person whether or not that person has title to the real property, and shall be filed in writing with the Community DevelopmentPlanning Director on a form furnished by the Director. The form of the petition and the information required to be set forth in them shall be prescribed by the Director. The Director shall not accept any such petition for filing unless:

A. All information and data is set forth and shown as required by the form; B. The petition is verified by the party making the petition; and C. The filing fee required by Section XI-500-12.00 has been paid.

XI-500-13.00 Hearing by Planning Commission
A. Upon filing of such petition, payment of filing fees, and acceptance of such petition as complete by the Planning Community Development Director, said director shall, subject to the rules of the Planning Commission as to the hour and place of public hearings which shall be conducted by it, set a date for the public hearing which shall be held thereon by the Planning Commission. Said date of hearing shall be not less than twenty nor more than sixty days after the date such application was accepted as complete by the Director.

B. The Director shall provide a report and recommendation to the commission. In addition thereto, the director shall file with the commission at its hearing all papers, documents, and exhibits which are part of the file. Within a reasonable time after the commission has concluded its hearing, it shall, by resolution, set forth its findings and decision on the matter. The Commission may decide to grant the petition, conditionally grant the petition or deny the petition.

Page 135 of 395 ends

XI-500-14.00 Appeal to City Council
Any action taken by the Planning Commission under this part may be appealed to the City Council by filing with the City Clerk a written notice of appeal within twelve (12) calendar days after a copy of the decision of the Planning Commission. The applicant, or any person, may file such a notice of appeal.

The notice of appeal shall be filed on a form furnished by the Community DevelopmentPlanning Director, and the information and data required to be set forth in such notice shall be as prescribed by the Director.

A. The Council shall hold at least one public hearing on the matter. The hearing of the council shall be de novo. The City Clerk shall set the date of the first public hearing by the Council, which date shall not be less than ten nor more than sixty days after the date on which the day of the application and the notice of appeal were filed with the City Clerk. Within a reasonable time after the Council has concluded its hearing, it shall, by resolution, set forth its findings and decision on the matter.

B. The decision of the Council shall be final.

XI-500-17.00 Release to be Recorded
Within fifteen days after the action of the Planning Commission or the City Council in granting a petition for release has become final, the Community Development Planning Director shall cause the release to be recorded in the office of the recorder for the County of Santa Clara.

Chapters 1 and 2 of Title XII of the Milpitas Municipal Code are hereby amended as follows:

XII-1-3.04 Design and distribution of affordable units
Affordable units shall meet the following requirements:

1. The bedroom mix of the affordable units should be proportionate to the bedroom mix of market rate units, provided that the City may allow a different unit mix to meet other City goals as determined by the City Council.

2. The square footage of the affordable housing units must be reasonably consistent with the market rate units in the development although smaller unit sizes may be allowed by the Director or Building Safety and HousingCity Manager if the developer provides adequate justification and reasons why the provision of small unit sizes would further the City's housing goals and this Chapter.

3. All affordable units shall be reasonably comparable in terms of floor plan and base finish amenities to market rate units in the proposed development.

4. The quality of the exterior design, landscaping, and construction of the affordable units shall be consistent with the other units in the proposed development. When affordable units are built off-site they shall be of equivalent or of higher quality compared with the market rate units.

5. Affordable units shall have the same access to common entrances from the exterior as market rate units.

6. Affordable units shall have the same access to all project amenities and recreational facilities available to market rate units. Off-site projects shall have convenient access to equivalent project amenities and recreational facilities compared to the market rate units.

7. All affordable units shall be reasonably dispersed throughout the project and for residential structures higher than eight stories, the affordable units shall be evenly distributed throughout the bottom 60% of the floors or higher.

Page 136 of 395 ends

XII-1-4.00 Payment of fees in lieu of creation of affordable units Upon request of the applicant and subject to the requirements of this Section 4 as set forth above, the City Council may permit the applicant to pay a fee in lieu of constructing the affordable units that the applicant would otherwise be required to construct pursuant to this Chapter. In-lieu fees shall also be paid for requirements to construct fractional units of less than 0.5 units as set forth in Section XII-1-3.00. The City shall adopt, by resolution, current affordable housing in-lieu fee levels as well as administrative guidelines necessary for the implementation of this Chapter.

Fees paid in-lieu of constructing affordable units must be paid prior to the issuance of the building permit for the project, and fees shall be deposited into the City's Affordable Housing Fund. The in-lieu fee shall be calculated based on the gross square footage constructed for each new residential use, taking into account any fee credits that would be applicable based on existing building area. While accessory dwelling units are not counted towards either calculating or meeting the 15% on-site affordable housing requirement pursuant to Section XII-1-3.00, any payment of in-lieu fees must be based on the total gross square footage of all dwelling units developed as part of the project, including any accessory dwelling units.

Unless otherwise specified by resolution of the City Council or amendment to this Chapter, every July 1, or the following business day, if applicable, the City will adjust the affordable housing fees for inflation using the Engineering News Record Building Cost Index for San Francisco. If this index ceases to exist, the Director of Building Safety and HousingCity Manager shall substitute another construction cost index, which in his/her judgment is as nearly equivalent to the original index as possible.

XII-1-5.01 Applicability
Any non-residential development, applicable under the definition set forth in Section XII-1-2.05, is subject to payment of a non-residential affordable housing impact fee. The City shall adopt, by resolution, current non-residential affordable housing impact fee levels. Every July 1, or the following business day, if applicable, the City will adjust affordable housing fees for inflation annually using the Engineering News Record Building Cost Index for San Francisco. If this index ceases to exist, the Director of Building Safety and HousingCity Manager shall substitute another construction cost index, which in his/her judgment is as nearly equivalent to the original index as possible.

The applicant shall pay the non-residential impact fees prior to issuance of the building permit.

Applicable fees will be determined at time of payment. All payment of fees made to the City under this Chapter shall be deposited into the City Affordable Housing Fund.

XII-2-2.04
"Director" means the City's Director of Building and Housing, who is the person designated by the City Manager to direct and manage the rent review program. Any duty required of the director may be delegated to a third party by the director and any service required to be performed by the director may be provided by a designated service provider as authorized by the director.

XII-2-4.01
The notice of availability of rent review shall be provided in English and the most commonly used languages within the City as determined by the director based upon the American Community Survey, the most recent census or other reputable source data and shall read as follows:

NOTICE:

Under California Civil Code Section 827(b), a Landlord must provide a Tenant with 30 days' notice prior to a rent increase of 10 percent (10%) or less and 60 days' notice of a rent increase greater than 10 percent (10%). In addition, Chapter 2 of Title XII of the Milpitas Municipal Code requires that a

Page 137 of 395 ends

Landlord must at the same time provide and serve this written notice of the City's Rent Review Program. This program provides a procedure for Landlords and Tenants to meet to discuss issues related to rent increases. Information about this program and a copy of Chapter 2 of Title XII are available on the City's website at www.ci.milpitas.ca.gov, at City Hall located at 455 E, Calaveras Blvd. in Milpitas, California, the Milpitas Public Library located at 160 N, Main St. in Milpitas, California, and other locations designated by the City's Director of Building SafetyCity Manager and Housing. Copies are also available in English and the most commonly used languages within the City as determined by the Director of Building Safety and HousingCity Manager.

You are encouraged to contact the owner or manager of your rental unit whose name is _______ (landlord to insert the name of the Responsible Party) at _______ (landlord to insert email address and telephone number) to discuss this rent increase for your rental unit.

In addition if you have received notice of a rent increase of more than five percent (5%) in the last 12 months, you are also entitled to review by the City's Rent Review Board. To initiate the rent review process, you must request rent review by contacting the Department of Building Safety and HousingCity Manager (landlords will be advised of the name and contact information for the service provider designated by the director that is to be inserted in this notice) within 15 days of the date of the notice of rent increase. Your Landlord will be notified of your request and you will be contacted by a housing professional to discuss the rent increase. Please note that petitioning for rent review does not guarantee a reduction in the rent increase.

At the hearing, the Rent Review Board will make a decision concerning the rent increase. You and your Landlord may agree to accept the Board's decision, The Rent Review Board's decision as to the rent increase is non-binding on you and your Landlord.

Under California Civil Code Section 1942.5 and Chapter 2 of Title XII of the City's Municipal Code, it is illegal for a Landlord to retaliate against a Tenant for lawfully exercising his or her legal rights.

SECTION 3. CALIFORNIA ENVIROMENTAL QUALITY ACT (CEQA)
The City Council finds and determines that the adoption of this ordinance is not a project and is not subject to CEQA review because it does not have the potential for resulting in either a direct physical change in the environment or a reasonably foreseeable indirect physical change, particularly in that it does not alter the use of land or does a most does not do so inconsistently with uses already authorized, prohibited, or regulated by law. (Cal. Code Regs., tit. 14, § 15378.) This ordinance also is not a project because it amounts to general policy and procedure making that does not relate to the enactment or amendment of zoning ordinances or the other activities identified as potential “projects.” (Cal. Code Regs., tit. 14, § 15378(b)(2).) Furthermore, even if considered a project, this amending ordinance is categorically exempt from CEQA review in that it comprises of non-land use regulations or at most minor alterations in land use limitations that do not result in any changes in land use or density (Cal. Code Regs., tit. 14, § 15305, 15378(a)(1)) and by common sense can be seen with certainly that there is no possibility that the activity in question may have a significant effect on the environment particularly in consideration of the activities already permitted, prohibited, or regulated by law (Cal. Code Regs., tit. 14, § 15061(b)(3)). This amending ordinance is also exempt because it does not affect development density established by existing zoning and the City’s General Plan, for which an Environmental Impact Report was already certified, and does not have any project- specific significant environmental effects peculiar to the project or any site. (Cal. Code Regs., tit. 14, § 15183.)
SECTION 4. SEVERABILITY

Page 138 of 395 ends

The provisions of this Ordinance are separable, and the invalidity of any phrase, clause, provision or part shall not affect the validity of the remainder.

SECTION 5. EFFECTIVE DATE AND POSTING
In accordance with Section 36937 of the Government Code of the State of California, this Ordinance shall take effect thirty (30) days from and after the date of its passage. The City Clerk of the City of Milpitas shall cause this Ordinance or a summary thereof to be published in accordance with Section 36933 of the Government Code of the State of California.

Page 139 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Approve and Authorize the City Manager or Designee to Negotiate and Execute an Agreement with KONE, Inc. for Library Garage Elevator Modernization (Staff Contact: Luz Cofresí-Howe, Finance Director, 408-586-3111; and Christian Di Renzo, Public Works Director, 408-586-2602)
Category: Consent Calendar-Community Services and Sustainable Infrastructure Meeting Date: 1/7/2025
Recommendation: Adopt a resolution to approve and authorize the City Manager, or their designee, to negotiate and execute a contract for an elevator modernization project for the Library Parking Garage with KONE, Inc. for $464,660 with a contingency of $56,401, subject to an executed amendment, for a total amount not-to-exceed $521,061.

BACKGROUND:

The Milpitas Library facilities and garage are the property of the City of Milpitas. The Milpitas Library lease agreement between the City and Santa Clara County Library Joint Powers Authority, effective starting October 21, 2008, has a term of 30 years with the option of two additional periods of 10 years for a total of 50 years.

The Public Works Department is responsible for maintaining the parking garage and elevators and the exterior of the facility.

The Milpitas Library elevators provide essential public access from the parking garage and are facing significant operational challenges. Many components of the elevator design have become obsolete, resulting in ongoing maintenance and repair challenges. There is a documented history of malfunctions, resulting in substantial repair costs to the City, compromising ADA compliance, and disrupting access for the public. These issues increase the risk of entrapment and safety concerns. Additionally, the lack of available mechanical components, modules, and specific electronics for this type of system further exacerbates the problem.

Since May, both elevators have been non-operational due to vandalism. In September, KONE, Inc. (KONE) successfully restored functionality to one of the two elevator cabs, but the call buttons are still not operational on the fourth floor. Modernizing the elevator cabs with updated components, finishes, and security features is crucial to mitigate vandalism and tampering, which have been identified as contributing factors to multiple system failures.

ANALYSIS:

The proposed upgrade will not just replace the critical elements but also modernize the finishes with tamper- resistant controls and enhanced security features, including manual locking mechanisms. These improvements are expected to significantly reduce incidents of vandalism. The current lead time for materials is 15 weeks, with an anticipated 7 week outage per cab for modernization.

Consistent with the City’s Purchasing Ordinance in the Milpitas Municipal Code, the City where practicable engages in competitive procurement. Nevertheless, Milpitas Municipal Code Section I-2-3.06 Sole Source Procurement specifically authorizes the City Purchasing Agent to determine in writing, after conducting a good faith review of available sources, that only one source exists for the required supplies, material, equipment, or general service, or that there is a compelling reason for using only one source.

The City has an existing contract with KONE for on-call elevator repair services, which extends through August 20, 2025. While this contract did not contemplate a major modernization project for the Library Parking Garage elevator system, conducting a request for proposals (RFP) for these services would be unproductive due to the proprietary track systems of the elevators that only KONE can service. As the current maintenance provider for

Page 140 of 395 ends

these elevators, KONE is already familiar with City-specific infrastructure and operational needs and has a deep understanding of the City elevator systems, facilitating the efficient planning and implementation of modernization efforts. KONE's experience with the City setup ensures smooth integration of new components with the existing infrastructure, reducing compatibility issues. Furthermore, as the incumbent provider, KONE can mobilize immediately without the lengthy preliminary assessments a new service provider, if one were available, would require. This positions them to meet the critical project timeline while maintaining consistency in City elevator controls and maintenance practices, which are essential for long-term operational efficiency and safety. As such, the Purchasing Agent has determined there is a compelling reason for approving KONE as the sole source to perform this elevator modernization project for the Library Parking Garage.

KONE will provide the following services for the repair and modernization:

1. Install modular control upgrades

2. Install vandal resistant fixtures, signals, and security features

3. Install upgraded electronic relays

4. Modernize hydraulic system
The Public Works Department recommends approving up to $521,061 for KONE, which includes a contingency for currently unanticipated additional work that is subject to an executed amendment or change order of $56,401, to modernize the garage elevators. Modernizing the Library elevator system is essential for ensuring safety, efficiency, and reliability for the public. This investment will not only help prevent service disruptions but will also help mitigate health and safety concerns that may arise from outdated equipment. The goal of this modernization project is to provide a more dependable and accessible service for everyone.

POLICY ALTERNATIVE(S):

Alternative 1: Do not approve and authorize the City Manager to execute the agreement with KONE, Inc.

Pros: None.

Cons: Continuing to repair and maintain the outdated elevator system not only risks continued escalating costs, potentially exceeding the cost of the recommended modernization work, but also results in diminished public service and disruptions to operations.

Reason for Not Recommending: Modernizing the elevator system is essential for ensuring safety, efficiency, and reliability for the public. This investment will help prevent disruptions and address health and safety concerns that may arise from outdated equipment, providing a more dependable and accessible service for everyone.

FISCAL IMPACT:

Staff is recommending reappropriating $521,061 from the General Fund Facilities Replacement Reserve to CIP 3406 – City Building Improvements to fund the cost of the elevator modernization project at the Library Parking Garage. Per Council Fiscal Policy No. 53, this reserve is meant to fund major rehabilitation or replacement of City facilities. The current reserve balance is $3,700,000. Of the $521,061 in reappropriated funds, $464,660 will be contracted with KONE, Inc. to complete the project, which includes subcontract expenses for MODA Elevator for cab interior finishes. The additional $56,401 will be held as contingency for currently unanticipated related expenses that may be added to the contract through an executed contract amendment or change order.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

Not applicable. The selection and contractual arrangement do not constitute a project, in accordance with Section 15378 of the CEQA Guidelines. Sufficient funding is in the General Fund Facilities Reserve. As of October 2, 2024, the balance of this reserve is $6.2M.

Page 141 of 395 ends

RECOMMENDATION:

Approve and authorize the City Manager or designee to negotiate and execute a contract for an elevator modernization project for the Library Parking Garage with KONE, Inc. for $464,660 with a contingency of $56,401, subject to an executed amendment or change order, for a total amount not-to-exceed $521,061.

ATTACHMENT(S):
(a) Resolution

Page 142 of 395 ends

RESOLUTION NO. XXXX

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MILPITAS APPROVING

AND AUTHORIZING THE CITY MANAGER OR DESIGNEE TO NEGOTIATE AND

EXECUTE A LIBRARY GARAGE ELEVATOR MODERNIZATION AGREEMENT WITH KONE, INC.

WHEREAS, the Santa Clara County Library District is a public library system that serves Santa Clara County and operates the Milpitas Library providing library services to the residents of Milpitas; and WHEREAS, the lease agreement between the City of Milpitas and Santa Clara County Library Joint Powers Authority states that the City is responsible for maintaining the exterior of the facility, the library parking garage and elevators; and
WHEREAS, the elevators at the Milpitas Library provide essential public access from the parking garage and have faced significant operational challenges due to their age and related maintenance and repair difficulties; and
WHEREAS, after conducting a good faith review of available sources and pursuant to Milpitas Municipal Code Section I-2-3.06 (Sole Source Procurement), the Purchasing Agent has determined that KONE, Inc., is the only viable source to execute various modernizing improvements to the elevators at the Milpitas Library parking garage; and
WHEREAS, the costs to fund an elevator modernization project will be funded from Capital Improvement Program (CIP) Project 3406- City Building Improvements via a reappropriation from the General Fund Facilities Replacement Reserve.

NOW, THEREFORE, the City Council of the City of Milpitas hereby finds, determines, and resolves that the City Council approve and authorize the City Manager or designee to negotiate and execute a contract for an elevator modernization project for the Library Parking Garage with KONE, Inc. for $464,660 with a contingency of $56,401, subject to an executed amendment or change order, for a total amount not-to-exceed $521,061.

PASSED AND ADOPTED this day of , 2025, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

ATTEST: APPROVED:

Suzanne Guzzetta, City Clerk Carmen Montano, Mayor
APPROVED AS TO FORM:

Michael Multalipassi, City Attorney

Page 143 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Approve and Authorize the City Manager or Designee to Negotiate and Execute a Design Services Agreement with Wilsey Ham for Force Main A Project, CIP No. 6137 (Staff Contact: Christian Di Renzo, Public Works Director, 408-586- 2602; Michael Silveira, City Engineer, 408-586-3303; and Luz Cofresí-Howe, Finance Director, 408-586-3111)
Category: Consent Calendar-Community Development
Meeting Date: 1/7/2025
Recommendation: (1) Approve and authorize the City Manager or designee to negotiate and execute, with approval of the City Attorney, a four-year Design Services Agreement with Wilsey Ham in an amount not to exceed $1,460,412, (2) Delegate authority to the City Manager or designee to execute amendments and change orders as required to extend the Agreement and complete the work for up to a 15% contingency amount; and (3) Delegate authority to the Public Works Director or designee to amend Exhibit "C" entitled Project Schedule of the Agreement as required without additional approvals for the Force Main A Agreement, CIP Project No. 6137.

BACKGROUND:

The City of Milpitas (City) wastewater collection system consists of approximately 160 miles of sewer pipelines, with pipe diameters ranging from 4-inches to 36-inches. The collection system generally flows from east to west and south to north towards the San Francisco Bay. Most of the collection system flows by gravity to the Milpitas Main Lift Station (Main LS) and is then pumped to the San José/Santa Clara Regional Wastewater Facility (RWF) through force mains that are owned and operated by the City of Milpitas.

Force Main A (FMA) is a 36-inch steel pipeline built in 1974 located in a highly corrosive soil environment. It is one of two force mains which convey sewage from the City of Milpitas to the RWF for treatment. The FMA alignment extends approximately 12,000 linear feet, starting at the Main LS crossing into the City San José under Coyote Creek and traversing through the RWF residual sludge management drying beds to terminate at the RWF.

On August 9, 2022 the City conducted a public hearing and adopted the Sanitary Sewer Master Plan (SSMP), which included recommendations to improve/rehabilitate portions of the sewer collection system in addition to FMA. The SSMP provided two options to replace the FMA: (1) commence the design in Fiscal Year (FY) 24/25 or (2) commence the design in FY27/28. Staff evaluated both timeframes and determined that delaying the design to FY27/28 could result in several adverse consequences, including likelihood of increased customer rates and charges, potential increased construction costs due to inflation, and, most significantly, increase the risk of failure. If the FMA were to fail near or under Coyote Creek, it would lead to serious financial and environmental consequences. This failure could result in untreated sewage being discharged into the waterbody, violating the Clean Water Act. Such a violation could subject the City to expensive mitigation costs, potential financial penalties from regulatory authorities, and possibly lawsuits from third-party environmental groups. Additionally, sewer flows would have to be diverted to the smaller 24-inch pipeline, Force Main B (FMB), until FMA is repaired or replaced. Due to the size and alignment of the FMA, repairs or replacement, construction timelines may span three to four years before FMA would be operational. Upon adoption of the SSMP, City Council directed staff to complete a five-year sewer rate study to analyze the impacts of both options on sewer rates and present the findings to City Council.

On December 6, 2022, staff presented the Draft Sewer Rates Study to City Council for review, proposing to begin FMA design in FY24/25 using $6.1 million from sewer revenues and up to $20 million in 30-year bonds.

Page 144 of 395 ends

This strategy aimed to expedite project work, reduce the risk of system failure, and create a more gradual increase in customer rates and charges, ensuring both current and future beneficiaries equitably share the costs of infrastructure investment. The alternative option of delaying the design to FY27/28 assumed all cash funding using sewer revenues which risked an exacerbation of the infrastructure issue, and a greater likelihood of service disruptions that would affect the community, as well as a likely unsustainable spike in customer rates to support the immediate funding need. Upon receiving the Draft Sewer Rates Study, City Council directed staff to proceed with community engagement on the proposed rates, which included beginning the design in FY24/25.

On March 21, 2023, the City conducted a Public Hearing and introduced Ordinance No. 208.55 to approve updated sewer rates for FY23/24 through FY27/28. As part of the adopted 2024-2028 Capital Improvement Program Project No. 6137, funding for the design and construction of FMA (Project) was approved.

ANALYSIS:

On July 18, 2024, the City released Request for Proposals (RFP) 24-RFP931 to seek a design firm with expertise in planning, design, and construction support services for the Project. The scope of work includes three project phases:

Phase 1: This phase consists of tasks primarily focused on Project feasibility, including reviewing existing information, coordinating with internal and external stakeholders including, but not limited to, the RWF, Valley Water and regional and State permitting agencies, evaluating new pipeline alignment options, initiating environmental impacts evaluations, and submitting regulatory permitting applications.

Phase 2: This phase will commence upon completion of Phase 1, after a new FMA alignment has been established and regulatory permits are approved. Phase 2 consists primarily of developing construction documents including, but not limited to, design drawings, technical specifications, engineer’s cost estimates, Project schedule(s) and other supporting documentation, as needed for the public bidding process.

Phase 3: This phase consists of tasks related to construction activities, after the construction contract has been awarded.

The RFP was publicly noticed on the City website and OpenGov, the City e-procurement website, in accordance with City Municipal Code. Upon release, 63 firms downloaded the RFP documents. Three (3) vendors submitted proposal responses by the published closing date of September 3, 2024.

The RFP was evaluated and scored in accordance with the evaluation criteria set forth in the RFP. Following initial scoring, the two highest ranked firms were invited to participate in oral interviews to further discuss their proposals, provide clarifications, and answer questions. One of the two finalists, West Yost & Associates, withdrew themselves from consideration prior to the interview citing current lack of bandwidth to take on the project commitment. Scores for the remaining finalist are as follows:

Evaluation Criteria Max Points Wilsey Ham
Cover Letter & Compliance with RFP 5 3.67
Company Profile 25 18.95
Execution Plan 25 21.25
References 15 11.37
Personnel Assigned 10 6.83
Proposed Compensation 20 17.66
Total Score 100 79.73

Page 145 of 395 ends

Wilsey Ham was the best value proposer in accordance with the evaluation criteria set forth in the RFP.

POLICY ALTERNATIVE(S):

Alternative 1: Not approving a Design Services Agreement with Wilsey Ham.

Pros: None
Cons: Not approving the Design Services Agreement will delay the start of the Project. FMA is one of the most critical components of the City’s sewer system and delaying the Project would risk its failure, which could place undue strain on the City sewer system. It would also be contradictory to SSMP recommendations and prior City Council direction.

Reason for Not Recommending: This would result in delaying construction of a priority capital improvement project, which has the potential to have significant short-term and long-term environmental and financial ramifications for the City.

FISCAL IMPACT:

Should Council approve this contract, the four-year agreement with Wilsey Ham for a Force Main A Project will be for an amount not to exceed $1,460,412. Moreover, the City Manager or designee may extend the agreement and execute amendments and change orders up to 15% as required to complete the work. The funding for this Design Services Agreement was approved in the current Capital Improvement Program budget for Project No. 6137. There is sufficient funding available in the Project budget for the agreement, the contingency, and City administration. Additional funding will be requested during the budget process of the Capital Improvement Program in fiscal year 2026-27 for the approximate amount of $23.4 million to fund the construction of the improvement, construction management and inspection services. The amount of $23.4 million will be funded by $3.4 million in sewer revenues and debt financing of $20 million.

Fiscal Summary of Contract (4 years):

Phase Task and Description Estimated Not to Exceed*
N/A A: Project Administration and Coordination $44,727
Subtotal Estimated Non-Phased $44,727
1 B: Field and Document Investigation $259,529
1 C: Feasibility Study/Conceptual Plan 152,830
1 D: Preliminary Environmental Feasibility Analysis 33,481 1 E: Alignment Selection and Easement Acquisition 47,159 1 F: Design Development 101,670
1 G: Environmental Study 119,779
1 H: Permitting 75,134
Subtotal Estimated Phase 1 $789,582
2 I: Construction Document Phase - Project Administration and Coordination
$33,456
2 J: Construction Documents 117,272
2 K: Quality Control/Quality Assurance (QC/QA) 29,656
Subtotal Estimated Phase 2 $180,384
3 L: Construction Bidding Phase $49,786
3 M: Construction Support 268,402
3 N: Record Documents and Project Closeout 31,766
3 O: Reimbursable Expenses 10,838
3 P: Aerial Topographic Survey 84,927
Subtotal Estimated Phase 3 $445,719
TOTAL CONTRACT NOT TO EXCEED AMOUNT $1,460,412

Page 146 of 395 ends

*Estimates provided for each task based on Designer’s estimated hours to complete. Final hours may shift between tasks/phases, but Total Contract Not to Exceed Amount may not be exceeded unless modified through an executed amendment or change order.

Available CIP Project 6137 Budget as of November 30, 2024 $ 2,940,000 Summary of Estimated Cost
Design Services Agreement $1,460,412
15% Contingency $219,062
Total Estimated Cost $1,679,474
The 15% contingency established for this agreement will be used as necessary to address unanticipated needs that arise during the Project, subject to an executed amendment or change order. Additionally, to facilitate adjustments in the Project schedule that may be needed throughout the term of the Agreement, staff requests authority for the Public Works Director or designee to approve changes to Exhibit "C" entitled Project Schedule without additional approvals. Staff anticipates Phases 1 and 2 of the Project to be completed by the summer of 2027, and to award a construction contract to the lowest responsive and responsible bidder by the winter of 2027 with construction beginning by spring of 2028, barring any unforeseen delays.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

As part of the SSMP adoption, City Council adopted the California Environmental Quality Act (CEQA) Environmental Impact Report (EIR) Addendum (Addendum) to the Milpitas General Plan Update EIR (Milpitas GP EIR; State Clearinghouse No. 2020070348) on August 9, 2022. The City adopted the Milpitas GP EIR on March 9, 2021.

The City was the lead agency for the Milpitas GP EIR. The EIR evaluated potential environmental impacts, which could occur as a result of implementing the Milpitas GP. The impact analysis is intended to programmatically cover the construction and operation of actions to be taken under the Milpitas GP, such as new utilities and other elements of utilities master plans.

CEQA Guidelines (Sections 15162 and 15164) require a lead agency to prepare an addendum to a previously certified EIR, if some changes or additions to the environmental evaluation of a project are necessary.

Preparing an Addendum to the approved Milpitas GP EIR is deemed acceptable to meet the requirements of CEQA. The Addendum summarized the utility master plans as considered in the GP EIR, described additional changes to the Plans, made since the certification of the GP EIR and analyzed any change in environmental effects associated with those changes.

Environmental review of the master plans, along with environmental review prepared for the Certified Milpitas GP EIR led staff to conclude that the master plans would not result in any new impacts not previously disclosed in the Certified EIR, nor would it result in a substantial increase in the magnitude of any significant environmental impact previously identified. For these reasons, an addendum to the Certified EIR met the requirements of CEQA Section 15164. Staff also concluded the proposed master plan changes did not trigger any of the conditions in CEQA Guidelines Section 15162; therefore, a subsequent EIR was not required.

As part of the Wilsey Ham Design Services Agreement, an initial environmental assessment report will be compiled for the Project, to include information concerning existing environmental conditions. The assessment will focus on relevant environmental statutes and regulations, which may include, but are not limited to, the following: CEQA, state and federal Endangered Species Acts, Clean Air Act, Clean Water Act, California Fish and Game code, cultural and archaeological statutes, and noise ordinances. Following the initial environmental assessment report, the Designer will prepare a CEQA Initial Study/Mitigated Negative Declaration (IS/MND followed by a Notice of Intent (NOI) to adopt the MND to fulfill the public noticing requirements of CEQA Guidelines Section 15072. Upon adoption of the MND, the City will proceed with obtaining required regulatory permits for construction of FMA, which include, but are not limited to, applications for the U.S. Army Corps of Engineers 404 permit, the Regional Water Quality Control Board 401 permit, and the California Department of Fish and Wildlife Lake and Streambed Alteration Agreement.

Page 147 of 395 ends

RECOMMENDATION:
(1) Approve and authorize the City Manager or designee to negotiate and execute, with approval of the City Attorney, a four-year Design Services Agreement with Wilsey Ham in an amount not to exceed $1,460,412. (2) Delegate authority to the City Manager or designee to execute amendments and change orders as required to extend the Agreement and complete the work for up to a 15% contingency amount. (3) Delegate authority to the Public Works Director or designee to amend Exhibit "C" entitled Project Schedule of the Agreement as required without additional approvals for the Force Main A Agreement, CIP Project No. 6137.

ATTACHMENT(S):

None.

Page 148 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Approve and Authorize the City Manager to Execute a Stormwater Management Facilities Operation and Maintenance Agreement Between the City of Milpitas and Sunnyhills Investors LLC for the Sunnyhills Apartments Project at 1724 Sunnyhills Court (Staff Contact: Christian Di Renzo, Public Works Director, 408-586-2602; and Michael Silveira, City Engineer, 408-586-3303) Category: Consent Calendar-Community Development
Meeting Date: 1/7/2025
Recommendation: Approve and authorize the City Manager to execute a Stormwater Management Facilities Operation and Maintenance Agreement between the City of Milpitas and Sunnyhills Investors LLC for the Sunnyhills Apartments Project at 1724 Sunnyhills Court.

BACKGROUND:

On November 17, 2020, the City Council approved the Sunnyhills Investors LLC (Property Owner) application for a Site Development Permit (SD18-0004), Planned Unit Development Amendment (PA19-0002), Tree Removal Permit (TR19-0028) and Environmental Assessment (EA20-0005) to reconstruct the leasing office/community building and construct 44 additional residential apartment units with 87 additional parking spaces and associated site improvements including utilities, landscaping and irrigation, and stormwater treatment measures within an existing 171-unit multi-family dwelling apartment complex on a 12.66 acre site located at 1724 Sunnyhills Court (Project).

The Project is conditioned to comply with State Law and the Santa Clara County Municipal Regional Stormwater NPDES Permit (MRP) issued by the Regional Water Quality Control Board (RWQCB) where new development and redevelopment projects that create and/or replace 10,000 square feet or more of impervious surface are required to incorporate Low Impact Development (LID) post-construction stormwater control measures into their project. LID control measures are considered to be bioretention areas, flow-through planters, permeable pavement, infiltration trenches and tree well filters.

MRP section C.3.h.ii.(1)(a) and Milpitas Municipal Code Title XI Chapter 16 requires property owners of a development project meeting the 10,000 square foot threshold to execute and record a Stormwater Management Facilities Operation and Maintenance Agreement (“Agreement”) with the City for the perpetual operation, maintenance, and annual inspection of LID stormwater treatment facilities.

ANALYSIS:

The Property Owner constructed various stormwater bio-retention treatment areas, low impact development, and integrated management practices for stormwater in accordance with the MRP. The Property Owner will be responsible for the perpetual maintenance and operation of the privately owned stormwater treatment facilities within their private property.

The Property Owner has executed the required Stormwater Management Operations and Maintenance Agreement (“Agreement”) for this Project. The Agreement requires the Property Owner to operate and maintain the installed stormwater treatment facilities in accordance with the MPR and the Property Owner will compensate the City to complete the required annual system inspections.

Staff recommends the City Council approve the Agreement (Attachment A) which has been reviewed and approved by the City Attorney as to form, and by the City Engineer as to content.

Page 149 of 395 ends

POLICY ALTERNATIVE(S):

Alternative 1:

Not approving the Agreement with the City for the operation, maintenance and annual inspection of stormwater treatment facilities.

Pros: None
Cons: The Project will not comply with the conditions of development, the City Municipal Code and the Santa Clara County MRP.

Reason not recommended: The approval of the Agreement allows the City to ensure the Property Owner properly maintains and operates the stormwater treatment facilities in accordance with the Agreement. In addition, the Agreement allows the City to inspect the facilities annually and take enforcement action if the Property Owner is not in compliance.

FISCAL IMPACT:

As required by the Agreement, the Property Owner will pay the City for the required annual inspection of the installed stormwater bio-treatment facilities. No fiscal impact will be realized by the City as a result of this action item.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

The City Council’s approval of the agreement was already reviewed under the California Environmental Quality Act (CEQA) at the time the City Council approved the entitlements for the project through an initial environmental assessment. The Planning Department conducted an initial environmental assessment of the project and prepared an Initial Study and Mitigated Negative Declaration (IS/MND) in accordance with the California Environmental Quality Act (CEQA), including, without limitation, CEQA Guideline sections 15070 et seq. On September 17, 2020, the City posted a Notice of Intent to adopt the MND on the City’s website and the Project site and otherwise complied with the requirements of CEQA Guideline 15072. The IS/MND was available for public review from September 17, 2020, through October 7, 2020. On this basis, the Planning Commission and City Council relied on the previous CEQA review conducted in approving this agreement.

RECOMMENDATION:

Approve and authorize the City Manager to execute a Stormwater Management Facilities Operation and Maintenance Agreement between the City of Milpitas and Sunnyhills Investors LLC for the Sunnyhills Apartments Project at 1724 Sunnyhills Court.

ATTACHMENT(S):
(a) Stormwater Management Facilities Operation and Maintenance Agreement

Page 150 of 395 ends
Page 151 of 395 ends
Page 152 of 395 ends
Page 153 of 395 ends
Page 154 of 395 ends
Page 155 of 395 ends
Page 156 of 395 ends
Page 157 of 395 ends
Page 158 of 395 ends
Page 159 of 395 ends
Page 160 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 1 of 3 Ma rch 16, 2021 Storm Water Control Plan & Drainage Report

SUNNYHILLS APARTMENTS

MILPITAS , CALIFORNIA

M
ARCH 16, 2021

PREPARED FOR :

SUNNYHILLS INVESTORS, LLC
100 SARATOGA AVENUE, SUITE 300
SANTA CLARA, CALIFORNIA 95051

PREPARED BY:

636
9TH STREET
OAKLAND , CA 94607

Page 161 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 2 of 3 Ma rch 16, 2021

TABLE OF CONTENTS
I. Project Data ..................................................................................................................1 I.A. Project Location and Description ................................................................................................................ 1 I.B. Proposed Site Description ............................................................................................................................. 1 I.C. Opportunities and Constraints for Stormwater Control ......................................................................... 1 II. Low Impact Development Design Strategies ..............................................................1 II.A. Bioretention Areas .......................................................................................................................................... 1 II.B. Tree Credits ........................................................................................... Error! Bookmark not defined.

III. Documentation of Drainage Design .............................................................................2 IV. Sour ce Control Measures .............................................................................................2 V. Stormwater Facility Maintenan ce ................................................................................2 V.A. Ownership and Responsibility for Maintenance in Per petuity ............................................................... 2 V.B. Summary of Maintenance Requirements for Each Storm water Facility .............................................. 2 VI. Pipe Hydraulics and Drainage Summary ......................................................................2 VI.A. Background & Model Criteria ...................................................................................................................... 2 VI.B. Model Results & Conclusions....................................................................................................................... 3 VII. Certifications ................................................................................................................3

Page 162 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 3 of 3 Ma rch 16, 2021 Appendix A
County of Santa Clara C.3 Data Form

Appendix B
Soil Classification (Geotechnical Report)

Appendix C
MRP Calculation Worksheet

Appendix D
BMP Sizing Calculations

Appendix E
Site Plan (Storm Water Management Plan)

Appendix F
BMP Enlarged Details

Appendix G
Operations and Maintenance Manual

Appendix H
Storm Drain Analysis Summary

Appendix I
Utility Plan

Appendix J
City of Milpitas Engineering Guidelines Section XIII

Page 163 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 1 of 3 Ma rch 16, 2021 I. PROJECT DATA
I.A. Project Location and Description
The 2.28-acre site is a portion of the Sunnyhills Apartment Complex located in the City of Milpitas .

The project is within an area bounded by Dixon Landing Road to the North, Washington Street to the South, Arizona Avenue to the East, and the North Milpitas Boulevard to the West.

The existing site is an apartment complex with a combination of landscaped areas and existing buildings, walkways, and parking areas. Runoff currently sheet flows towards the west and is captured by area drains spread throughout the site.

As described in the project Geotechnical Report (prepared by Silicon Valley Soil Engineering and dated 11/2/2020) and applicable excerpts attached as appendix B, the subsurface conditions are generally composed of very stiff clays and silts. These soil types continue to a depth of 18 feet below grade. These silty clays allow an infiltration rate of 0.1 inches per hour. Groundwater was encountered in all borings and stabilized at a depth of 15 feet below the existing grade.

I.B. Proposed Site Description
The proposed development demolishes an existing leasing office and constructs six new two- and three-story apartment buildings for a total of forty-four new dwelling units as well as a new leasing office. The project includes bioretention basins throughout the site and along with storm drain piping and structures which conveys stormwater from the bioretention areas to the existing storm drain system in three locations. Two will be made to manholes on the south side of the project that tie into the existing 42” main. The third will be to an existing catch basin on the west side of the project.

I.C. Opportunities and Constraints for Stormwater Control There are a few opportunities on-site which may be used for storm water control measures. The proposed buildings and parking lot can be graded to flow towards adjacent landscaped areas and bioretention facilities. The existing storm drain pipes and structures that cross the property are fairly deep so there is adequate fall to connect to them and install bioretention measures.

The groundwater table is low enough to allow for infiltration into the ground through the bioretention basins. The poor infiltration rate of the native soil limits the quantity of stormwater handled this way, so most of the stormwater runoff will enter the storm drain system after leaving the bioretention basins.

The project will create more than 10,000 SF of impervious surface and will be required per the Municipal Regional Permit (R2-2015-0049) to utilize low impact development treatment measures (LID). The LID treatment measures are infiltration, evapotranspiration, and bioretention.

The project is not within an area subject to hydromodification management.

II. LOW IMPA CT DEVELO PMEN T DESIGN STRATEGIES
II.A. Bioretention Areas
The project will utilize bioretention basins for both treatment and flow control. Impervious surfaces from the site will sheet flow to perforated curbs adjacent to bioretention areas and allow stormwater to collect, filter, attenuate, and ultimately discharge. Runoff from roofs will collect in downspouts and piped to daylight or bubble up into bioretention areas. A minimum of six (6) inches of ponding

Page 164 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 2 of 3 Ma rch 16, 2021 depth is provided for each bioretention area that will store and limit rainwater flow to the storm drain system during normal storm events.

II.B. Tree Credits
Tree Credits will be utilized for a portion of the site to offset nominal onsite sidewalk improvements that cannot be directed into the bioretention areas. These areas are kept to a minimum and include a portion of the project site along the northern edge.

III. DOCUMENTATION OF DRAINAGE DESIGN
The individual watershed sizes, an example BMP Sizing Calculation, individual BMP sizing calculations, and BMP details are included in Appendices C through F. All bioretention areas were sized using the uniform flow method and the four percent (4%) rule as described in Appendix D.

These documents are included to ensure that the C.3 provisions of the Municipal regional Permit (MRP) are met by this project and satisfy the stormwater requirements of the City of Milpitas and the County of Santa Clara.

IV. SOURCE CONTROL MEASURES
The following source control measures will be used on site: covered dumpster area drain to sanitary sewer, maintenance, and storm drain labeling. (See Appendix A). These measures will help reduce the pollution entering the stormwater treatment areas and help ensure the efficacy of the treatment measures.

V. STORMWATER FACILI TY MAINT ENANC E
V.A. Ownership and Responsibility for Maintenance in Perpetuity All storm water treatment facilities in this plan will be owned and maintained by the property owner, Sunnyhills Investors LLC.

V.B. Summary of Maintenance Requirements for Each Storm water Facility See the Stormwater Facilities Operation and Maintenance Plan in Appendix G which sets forth a maintenance schedule for each of the treatment facilities built on the site.

VI. PIPE HYDRAULICS AND DRAINAGE SUMMARY
VI.A. Background & Model Criteria
The following section includes a discussion of pipe hydraulics to show the storm drain hydraulic grade line has at least 1 foot of freeboard (per County of Santa Clara requirements) and that the pipe system is sized adequately for a 10-year storm event.

The pipe system was modeled utilizing Storm and Sanitary Analysis extension from AutoCAD Civil 3D 2020 and was performed using the requirements of the City of Milpitas Engineering Guidelines Section XIII. For the purposes of this model, the detention components of this system were considered “full” and were bypassed to develop peak flows in the pipes The model was run with three points of connection to the existing mains, which were assumed to be full and have a starting HGL at the crown of the existing 12” pipe at the tie in connection in the north west portion of the site. This starting HGL was chosen as the highest of the three POCs. A minimum time of concentration of 10 minutes was assumed for this system. The results of this analysis are attached under Appendix I.

Page 165 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 3 of 3 Ma rch 16, 2021 VI.B. Model Results & Conclusions
The peak flow generated in this model is theoretical to show the pipes as designed are sized sufficiently. The results of the analysis show a theoretical total peak flow rate of approximately 7.61 CFS to the discharge points. As there is no surcharging on any portion of the pipes, we can say that the pipes are sufficiently sized.

The HGL in the model stays about 2 feet below the rim elevations throughout the majority of the system with only two structures closer to, but still exceeding, the 1 foot of minimum freeboard required.

VII. CERTIFICA TIONS
The selection, sizing, and preliminary design of st orm water treatment and other control measures in this plan meet the requirements of the Regional Water Quality Control Board Order R2-2015-0049.

Page 166 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 1 of 10 M arch 16, 2021

APPENDIX A
County of Santa Clara C.3 Form

Page 167 of 395 ends

Urban Runoff
_________________________
03/16/21
Gregory Trela
Sunnyhills Apartments 026-06-009
1724 Sunnyhills Drive, Milpitas CA
North Milpitas Boulevard and Dixon landing Road
Sunnyhills Investors, LLC
1 1 SANDIS Civil Engineers
Demolition of existing leasing ofice and construction of 44 townhomes and new leasing office Baylands

Page 168 of 395 ends

SCVURPPP C.3. Data Form Page 2 of 4 September 2019

2. Project Size
a. Total Site Area: ______________acres b. Total Site Area Disturbed: ____________________ acres (including clearing, grading, or excavating)
Site Totals Total Existing
(Pre-project)
Area (ft2)
Existing Area
Retained1 (ft2)

Existing Area
Replaced2 (ft2)

New Area
Created2 (ft2)

Total Post-
Project Area (ft2)

c. Total Impervious Area (IA)
d. Total new and replaced impervious area
e. Total Pervious Area (PA)3
f. Total Area (IA+PA)
g. Percent Replacement of IA in Redevelopment Projects: (Existing IA Replaced ÷ Existing Total IA) x 100% _______%

3. State Construction General Permit Applicability:
a. Is #2.b. equal to 1 acre or more?
Yes, applicant must obtain coverage under the State Construction General Permit (see https://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.html) No, applicant does not need coverage under the State Construction General Permit.

4. MRP Provision C.3 Applicability:
a. Is #2.d. equal to 10,000 sq. ft. or more, or 5,000 sq. ft. or more for restaurants, auto service facilities, retail gas outlets, and stand-alone uncovered parking? Yes, C.3. source control, site design and treatment requirements apply No, C.3. source control and site design requirements may apply check with local agency b. For redevelopment projects, is #2.g. equal to 50% or more? Yes, C.3. requirements (site design and source control, as appropriate, and stormwater treatment) apply to the entire site
No, C.3. requirements only apply to the impervious area created and/or replaced c. Does the project create and/or replace 5,000 sf or more of impervious surface parking? Yes, C.3. requirements may apply to the entire site check with local agency No

5. Hydromodification Management (HM) Applicability:
a. Does the project create and/or replace one acre or more of impervious surface AND is the total post-project impervious area greater than the pre-project (existing) impervious area? Yes (continue) No exempt from HM, go to page 3
b. Is the project located in an area of HM applicability (green area) on the HM Applicability Map? ( www.scvurppp.org/hmp-map)
Yes, the project must implement HM requirements
No, the project is exempt from HM requirements

1 goes through maintenance (e.g., pavement resurfacing/slurry seal/grind
2 , impervious
IA, if an equal amount of pervious area replaces IA somewhere else on the site.

Constructed IA on a site that does not exceed the total pre-project IA will be considered IA only if the total post-project IA exceeds the total pre-project IA (total post-project IA total pre-project IA = New IA). 3 Include bioretention areas, infiltration areas, green roofs, and pervious pavement in PA calculations. 3,994

Page 169 of 395 ends

SCVURPPP C.3. Data Form Page 3 of 4 September 2019

6. Selection of Specific Stormwater Control Measures:

Site Design Measures
Minimize land disturbed
(e.g., protect trees and soil)
Minimize impervious
surfaces (e.g., reduction in
post-project impervious
surface)
Minimum-impact street or
parking lot design (e.g.,
parking on top of or under
buildings)
Cluster structures/ pavement
Disconnected downspouts
(direct runoff from roofs,
sidewalks, patios to
landscaped areas)
Pervious pavement
Green roof
Other self-treating4 area
(e.g., landscaped areas)
Self-retaining4 area
Interceptor trees3
Rainwater harvesting and
use (e.g., rain barrel, cistern
for designated use) 5
Preserved open space:
_______ ac. or sq. ft. (circle
one)
Protected riparian and
wetland areas/buffers
(Setback from top of bank:
_______ft.)
Other _______________
Source Control Measures
Wash area/racks, drain to
sanitary sewer5
Covered dumpster area,
drain to sanitary sewer6
Sanitary sewer connection
or accessible cleanout for
swimming
pool/spa/fountain6
Beneficial landscaping
(minimize irrigation, runoff,
pesticides and fertilizers;
promotes treatment)
Outdoor material storage
protection
Covers, drains for loading
docks, maintenance bays,
fueling areas
Maintenance (pavement
sweeping, catch basin
cleaning, good
housekeeping)
Storm drain labeling
Other _______________
Treatment Measures
None (all impervious
surface drains to self-
retaining areas)
LID Treatment
Bioretention area
Flow-through planter
Tree Well Filter or Trench
with bioretention soils
Rainwater harvest/use (e.g.,
cistern or rain barrel for
designated use, sized for
C.3.d treatment)
Infiltration trench
Infiltration well/dry well
Subsurface Infiltration
System (e.g. vault or large
diameter conduit over drain
rock)
Other _______________
Non-LID Treatment Methods
Proprietary high flow rate
tree box filter7
Proprietary high flow media
filter (sand, compost, or
proprietary media)7
Vegetated filter strip8
Extended detention basin8
Vegetated swale8
Other _______________
Flow Duration Controls for Hydromodification Management (HM) Extended
Detention basin
Underground tank or
vault
Bioretention with outlet
control
Other
______________

4 See SCVURPPP C3 Handbook for definitions. https://scvurppp.org/2016/06/20/c-3-stormwater-handbook-june-2016/ 5 Optional site design measure; does not have to be sized to comply with Provision C.3.d treatment requirements. 6 Subject to sanitary sewer authority requirements.
7 These
8 These treatment measures are only allowed as part of a multi-step treatment process (i.e., for pretreatment).

Page 170 of 395 ends

7. Stormwater Treatment Measure (STM) Sizing for Projects with Treatment Requirements Stormwater Treatment Measure (STM) Hydraulic Sizing Criteria Used*

8. Alternative Certification:

9. Operation & Maintenance Information
This section to be completed by Municipal staff.

O&M Responsibility Mechanism
This section to be completed by Municipal staff (Note: This is an optional section that agencies should modify per their internal review and tracking process.)
Reviewed By:

Community Development Department Public Works Department Planning Division: ______________ Engineering: _______________ Building Division: _______________ Other (Specify):_______________ Return form to: ______________________ Data entry performed by: ___________ Bioretention
Sunnyhills Investors LLC
Megan Kehriotis
100 Saratoga Ave, Suite 300 Santa Clara, CA 95051
408-249-2500/[email protected]
Choose from list
Choose from list
Choose from list
2c

Page 171 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 8 of 16 M arch 12, 2021

APPENDIX B
Soil Classification

Page 172 of 395 ends

REPORT TO

SUNNYHILLS INVESTORS LLC

SANTA CLARA, CALIFORNIA

FOR

PROPOSED TOWNHOMES
1724 SUNNYHILLS DRIVE

MILPITAS, CALIFORNIA

GEOTECHNICAL INVESTIGATION
NOVEMBER 2020

PREPARED BY

SILICON VALLEY SOIL ENGINEERING
1916 O’TOOLE WAY

SAN JOSE, CALIFORNIA

Page 173 of 395 ends
Page 174 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING

ii

TABLE OF CONTENTS

GEOTECHNICAL INVESTIGATION PAGE

INTRODUCTION ............................................................................ 1 PROJECT LOCATION AND DESCRIPTION ......................................... 1 FIELD INVESTIGATION ................................................................... 1 LABORATORY INVESTIGATION ....................................................... 2 SOIL CONDITIONS ......................................................................... 3 GENERAL GEOLOGY ....................................................................... 4 LIQUEFACTION ANALYSIS .............................................................. 5 A. GROUNDWATER ................................................................... 5 B. SUSPECTED LIQUEFIABLE SOIL LAYERS .................................. 5 C. CONCLUSION ....................................................................... 5 INUNDATION POTENTIAL .............................................................. 6 CONCLUSIONS .............................................................................. 7 RECOMMENDATIONS ..................................................................... 8 GRADING ................................................................................. 8 WATER WELLS .......................................................................... 10 FOUNDATION DESIGN CRITERIA ............................................... 10 2019 CBC SEISMIC VALUES ........................................................ 13 CONCRETE SLAB-ON-GRADE CONSTRUCTION .......................... 13 RETAINING WALLS .................................................................... 14 EXCAVATION ........................................................................... 15 DRAINAGE ............................................................................... 16 ON-SITE UTILITY TRENCHING ................................................... 17 PAVEMENT DESIGN ................................................................... 17 LIME TREATMENT ALTERNATIVES ............................................. 18 CORROSIVITY ANALYSIS ........................................................... 18 LIMITATIONS AND UNIFORMITY OF CONDITIONS ........................... 21 REFERENCES .................................................................................. 23

Page 175 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING

iii

LIST OF TABLES, FIGURES, AND APPENDICES

GEOTECHNICAL INVESTIGATION

TABLES

TABLE I - SUMMARY OF LABORATORY TESTS
TABLE II – PROPOSED ASPHALT PAVEMENT SECTIONS
TABLE III – PROPOSED CONCRETE PAVEMENT SECTIONS
TABLE IV – PROPOSED PAVER PAVEMENT SECTIONS

FIGURES

FIGURE 1 - VICINITY MAP
FIGURE 2 - SITE PLAN
FIGURE 3 - FAULT LOCATION MAP
FIGURE 4 - PLASTICITY INDEX
FIGURE 5 - COMPACTION TEST A
FIGURE 6 – R-VALUE TEST
FIGURE 7 – LIQUEFACTION ANALYSIS (CPT-1)
FIGURE 8 – LIQUEFACTION ANALYSIS (CPT-2)
FIGURE 9 – LIQUEFACTION ANALYSIS (CPT-3)

APPENDICES

MODIFIED MERCALLI SCALE

METHOD OF SOIL CLASSIFICATION CHART

KEY TO LOG OF BORING
EXPLORATORY BORING LOGS (B-1 THROUGH B-5)
SOUNDING LOGS (CPT-1 THROUGH CPT-3)

CONE PENETRATION TEST PROCEDURE

LIQUEFACTION ANALYSIS SUMMARY

CORROSIVITY TESTS SUMMARY

SANTA CLARA VALLEY WATER DISTRICT DRILLING PERMIT

Page 176 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING
1 INTRODUCTION
Per your authorization, Silicon Valley Soil Engineering (SVSE) conducted a geotechnical investigation. The purpose of this investigation was to determine the nature of the surface and subsurface soil conditions at the project site through fiel d investigatio ns and laboratory testing. This report presents an explanation of investigative procedures, results of the testing program, our conclusions, and our recommendations for earthwork and foundation design to adapt the proposed development to the existing soil conditions.

PROJECT LOCATION AND DESCRIPTION
The project site is located at 1724 Sunnyhills Drive in Milpitas, California (Figure 1 – Vicinity Map). Existing commercial/retail developments bounds the subject site to the west, Dixo n Landing R oad to the nor th, and existing residential developments to the east and south. At the time of our investigation, the site was an irregular shaped, relatively flat parcel of land occupied by multi- unit apartments. Access to the subject property is provided by Sunnyhills Drive from Dixon Landing Road and Sunnyhills Court on Milpitas Boulevard. Based on the preliminary plan prepared by the Project Architect for the subject site, the proposed development, eastern portion of the parcel, will include the removal of the existin g structures and construction of townhomes with associated improvements. Location of the proposed townhomes and our borings are shown on the Figure 2 – Site Plan.

FIELD INVESTIGATION
After considering the nature of the proposed development and reviewing available data on the area, a field investigation was conducted at the project site under the direction of our geotechnical engineer. It included a site reconnaissance to detect any unusual surface features, the drilling of five expl oratory tes t borings to

Page 177 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING
2 determine the subsurface soil characteristics, and t he sounding of three penetration tests (CPTs) per ASTM D5778. The borings were drilled and the CPTs were advanced on May 1, 2018. The approximate location of the borings and CPTs is shown on the Site Plan (Figure 2). The borings were drilled to the depths of 20 feet and the CPTs were advanced to the depths of 50 feet below the existing ground surface. The borings were drilled with a truck mounted drill rig using 6-inch diameter solid stem augers.

The soils encountered were logged continuously in the field during the drilling operations. Relatively undisturbed soil samples were obtained by hammering a

2.0-inch outside diameter (O.D.) split -tube sampler for a Standard Penetration Test (SPT), A STM Standard D1586 into the ground at various depths. A 140 - pound hammer with a free fall of 30 inches was used to drive the sampler 18 inches into the ground. Blow counts were recorded on each 6-inch increment of the sampled interval. The blows required for advancing the sampler the last 12 inches of the 18 inch sampled interval were recorded on the boring logs as penetration resistance.

In addition, disturbed bulk samples of the near- surface soil were collected for laboratory analyses. The Exploratory Boring Log contained in the Appendix are a graphic representation of the encountered soil profile; and also show the depths at which the relatively undisturbed soil samples were obtained.

LABORATORY INVESTIGATION
A laboratory -testing program w as performe d to determine the physical and engineering properties of the soils underlying the site.

1. Moisture content and dry density tests were performed on the relatively undisturbed soil samples in order to determine soil consistency and the moisture variation throughout the explored soil profile (Table I).

Page 178 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING
3 2. The strength parameters of the foundation soils were determined from direct shear tests that were performed on selected relatively undisturbed soil samples (Table I).

3. Atterberg Limits tests were also perfor med on the nea r-surface soil to assist in the classification of these soils and to obtain an evaluation of their expansion and shrinkage potential (Figure 4).

4. Laboratory compaction tests of the native soil material were performed to determine the maximum dry density per the ASTM D1557 test procedure (Figure 5).

5. One R –Value test was performed on a near surface soil sample for pavement section design recommendations (Figure 6).

6. Two soil samples collected were submitted to Cooper Testing Lab f or corrosivity analysis (Page 18).

The results of the laboratory -testing program are presented in the Tables and Figures at the end of this report.

SOIL CONDITIONS
In Boring B-1, the surface soil consists of 3.0 inches of organic material. Below the organic layer to a depth of 3 feet, a black, moist, very stiff silty clay layer was encountered. From the depths of 3 feet to 8 feet, the soil became dark gray, moist, very stiff silty clay. A color change of brown was noted at a depth of 5 feet.

From the depths of 8 feet to 13 feet, a tan brown, moist, very stiff clayey silt layer was encountered. From the depths of 13 feet to 18 feet, a reddish brown, moist, stiff silty clay layer was encountered. From the depths of 18 feet to the end of the boring at 20 feet, the soil became brown, moist, medium dense silty sand. The

Page 179 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING
4 sand was medium grained and poorly graded. Similar soil profiles were encountered in other borings.

Groundwater was initially encountered in all borings at the depth of 19 feet and stabilized to static level of 15 feet after the completion of the drilling operation.

It should be noted that the groundwater table would fluctuate as a result of seasonal changes and hydrogeologic variations such as groundwater pumping and/or recharging. A detailed description of th e soil profile s encountered is presented in Exploratory Boring Log contained in the Appendix.

GENERAL GEOLOGY
The site lies in the Santa Clara Valley, which is part of the Coast Ranges geological province. The Santa Clara Valley occupies the s tructural trough formed by two northwest trending mountain ranges; the Santa Cruz Mountains to the southwest of the valley and the Diablo Range to the northeast. The Diablo Range is predominantly composed of Franciscan Formation, which is uppermost Jurassic to lower Upper Cretaceous eugosynclinal assemblage. The Santa Cruz Mountains are predominantly composed of material formed of Cenozoic shelf and slope deposits. A thick blanket of latest Cretaceous and Tertiary clastic sedimentary rocks and isolated in trusions of serpentine covers large parts of the province.

Folds, thrust faults, steep reverse faults, and strikeslip faults developed as a consequence of Cenozoic deformations that occur very often within the province and some of them are continuing today (CDMG; 1966).

Sedimentary marine strata alternating with non -marine strata record the Quaternary history of the region. The changes of the depositional environment are related to the fluctuation of sea level corresponding to the glacial and interglacial periods. Late Quaternary deposits fill the center of the Santa Clara Valley and most of the strata are of continental origin characterized as alluvial

Page 180 of 395 ends

File No. SV1772
November 2, 2020 SILICON VALLEY SOIL ENGINEERING
5 and fluvial materials. The project site is underlain by fluvial deposits (Helley and Brabb, 1971, Rogers & Williams, 1974).

LIQUEFACTION ANALYSIS
A. GROUNDWATER
Groundwater was initially encountered in all borings at a depth of 19 feet and rose to a static level of 15 feet at the end of the drilling operation. Based on the State guidelines and CGS Seism ic Hazard Z one Report 051 [Seismic Hazard Evaluation of the Milpitas 7.5 -Minute Quadrangle, Alameda and Santa Clara Counties, California. 2001 (1/13/06). Department Of Conservation. Division of Mines and Geology], the highest expected groundwater level is approximately 15 feet below ground elevation. Therefore, this depth of the groundwater table will be used for the liquefaction analysis.

B. SUSPECTED LIQUEFIABLE SOIL LAYERS
A computer program named LiquefyPro Version 5.8n (CivilTech Corporation) was used in the liquefaction analysis for CPT-1, CPT-2, and CPT-3. This program is based on the most recent publications of NCEER Workshop and procedure outline in SP117 Implementation. The results show that no potential liquefiable soil layers were identified by LiquefyPro. The liquefaction analysis for CPT -1, CPT-2, and CPT-3 are shown on Figure 7, 8, and 9.

C. CONCLUSION
Since there is no liquefiable soil layer underlying the subject site, the potential for liquefaction is minimal.

Page 181 of 395 ends

Silicon Valley Soil
Engineering

VICINITY MAP

Proposed Townhomes
File No.: SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 1
Milpitas, California Scale: NOT TO SCALE November
2020
SITE

Page 182 of 395 ends

NOTE: DENOTES APPROXIMATE EXPLORATORY BORING LOCATION

DENOTES APPROXIMATE EXPLORATORY BAG SAMPLE LOCATION

DENOTES APPROXIMATE CONE PENETRATION TEST (CPT) LOCATION

Silicon Valley Soil
Engineering

SITE PLAN

Proposed Townhomes
File No.: SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 2
Milpitas, California Scale: NOT TO SCALE November
2020
BAG A
N
B-2

SUNNYHILLS DRIVE
B-1
B-3
CPT-3
CPT-1
B-4
B-5
CPT-2

Page 183 of 395 ends

Silicon Valley Soil
Engineering

FAULT LOCATION MAP

Proposed Townhomes
File No.: SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 3
Milpitas, California Scale: NOT TO SCALE November
2020
SITE

Page 184 of 395 ends

PLASTICITY CHART
60 CV CE

50 CH ME
40 MV
30 CI

20 MH
CL
10 7 MI
4 0
0 10 20 30 40 50 60 70 80 90 100 Liquid Limit %

PLASTICITY DATA

Key
Symbol
Hole
No.

Depth
(ft.)
Liquid
Limit %
Plasticity
Index %
Unified Soil
Classification
Symbol *

BAG A 0-1 52 31 CH

*Soil type classification Based on British suggested revisions to Unified Soil Classification System

N

ML

Silicon Valley Soil
Engineering

PLASTICITY INDEX

Proposed Townhomes
File No.: SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 4
Milpitas, California Scale: NOT TO SCALE November
2020

Page 185 of 395 ends

SAMPLE: A

DESCRIPTION: Black Silty CLAY

LABORATORY TEST PROCEDURE: ASTM D1557

MAXIMUM DRY DENSITY: 105.0 p.c.f.

OPTIMUM MOISTURE CONTENT: 22.0 %

Silicon Valley Soil
Engineering

COMPACTION TEST A

Proposed Townhomes
File No. SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 5
Milpitas, California Scale: NOT TO SCALE November
2020

85 90
95 100
105
110
115
120
125
130
135
140
145
150
0 5 10 15 20 25 30 35
Moisture Content (% of Dry Weight)
Dry Density (p.c.f.)

Page 186 of 395 ends

EXUDATION PRESSURE (P.S.I.)
800 700 600 500 400 300 200 100
24 100

22 90

20 80

18 70

16 60

14 50

12 40

10 30

8 20

6 10

4 0

2 0
0 2 4 6 8 10 12 14 16 18 20 22 24 26

COVER THICKNESS BY EXPANSION PRESSURE - INCHES

SAMPLE: A
DESCRIPTION: Black Silty CLAY

SPECIMEN A B C
EXUDATION PRESSURE (P.S.I.) 149.0 251.0 449.0
EXPANSION DIAL (.0001”) 9.0 14.0 20.0
EXPANSION PRESSURE (P.S.F.) 45.0 76.0 94.0
RESISTANCE VALUE, “R” 1.0 4.0 15.0
% MOISTURE AT TEST 20.7 18.0 17.6
DRY DENSITY AT TEST (P.C.F.) 106.7 108.5 111.2
R-VALUE AT 300 P.S.I.

EXUDATION PRESSURE

=

(6)

RESISTANCE, R-VALUE TEST

STATE OF CALIFORNIA
TEST METHOD N0. CALIFORNIA 301-F

Silicon Valley Soil
Engineering

R-VALUE TEST

Proposed Townhomes
File No. SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 6
Milpitas, California Scale: NOT TO SCALE November
2020

Page 187 of 395 ends

LiquefyPro CivilTech Software USA www.civiltech.com CivilTech Corporation

LIQUEFACTION ANALYSIS
SV1772 - Proposed Townhomes
1724 Sunnyhills Drive, Milpitas, CA. Plate A-1
Hole No.=CPT-1 Water Depth=15 ft Surface Elev.=100 Magnitude=7.9 Acceleration=0.747g
(ft)
0 10
20 30
40 50
60 70

47.55 0.159 121 NoLq

37.36 0.903 121 NoLq

17.77 0.582 121 NoLq

16.75 0.716 121 NoLq

22.68 1.025 121 NoLq

43.11 1.35 121 NoLq

50.46 1.52 121 NoLq

45.23 1.29 121 NoLq

79.18 0.94 121 NoLq

54.16 1.31 121 NoLq

42.2 1.5 121 NoLq

28.1 0.64 121 NoLq

16.88 0.55 121 NoLq

12.75 0.4 121 NoLq

13.22 0.24 121 NoLq

16.39 0.35 121 NoLq

15.98 0.26 121 NoLq

19.73 0.505 121 NoLq

20.78 0.32 121 NoLq

22.08 0.33 121 NoLq

34.53 0.8 121 NoLq

31.74 1.15 121 NoLq

33.15 0.9 121 NoLq

17.88 0.72 121 NoLq

72.03 1.17 121 NoLq

23.86 0.62 121 NoLq

21.72 0.59 121 NoLq

23.4 0.62 121 NoLq

26.85 0.57 121 NoLq
132.0 3.07 121 NoLq
251.8 4.3 121 NoLq

34.55 0.83 121 NoLq

24.5 0.71 121 NoLq

35.08 0.91 121 NoLq

32.69 0.71 121 NoLq

29.25 0.93 121 NoLq

32.4 0.85 121 NoLq

42.53 1.35 121 NoLq

56.02 1.44 121 NoLq

41.3 1.11 121 NoLq
102.9 2.79 121 NoLq
100.1 4.98 121 NoLq

38.03 1.11 121 NoLq

29.56 0.99 121 NoLq

32.46 0.97 121 NoLq

35.35 1.06 121 NoLq
100.8 1.81 121 NoLq

90.27 3.43 121 NoLq

41.26 2.24 121 NoLq
307.8 8.61 121 NoLq

17.27 0.486 121 NoLq
Silty CLAY
Raw Unit Fines
qc fc Weight %
Shear Stress Ratio
CRR CSR f s1
Shaded Zone has Liquefaction Potential
0 1
Soil Description Factor of Safety
0 51
Settlement
Saturated
Unsaturat.

S = 0.00 in.
0 (in.) 1
fs1=1.30

Silicon Valley Soil
Engineering

LIQUEFACTION ANALYSIS
CPT-1
Proposed Townhomes
File No. SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 7
Milpitas, California Scale: NOT TO SCALE November
2020

Page 188 of 395 ends

LiquefyPro CivilTech Software USA www.civiltech.com CivilTech Corporation

LIQUEFACTION ANALYSIS
SV1772 - Proposed Townhomes
1724 Sunnyhills Drive, Milpitas, CA. Plate A-1
Hole No.=CPT-2 Water Depth=15 ft Surface Elev.=100 Magnitude=7.9 Acceleration=0.747g
(ft)
0 10
20 30
40 50
60 70

25.2 0.299 121 NoLq

16.310.62 121 NoLq

13.360.517 121 NoLq

18.930.712 121 NoLq

30.850.698 121 NoLq

29.790.765 121 NoLq

32.780.925 121 NoLq

28.230.783 121 NoLq

21.330.712 121 NoLq

27.400.684 121 NoLq

23.930.722 121 NoLq

17.070.680 121 NoLq

39.671.05 121 NoLq

19.1 0.669 121 NoLq

22.850.506 121 NoLq

26.030.79 121 NoLq

69.581.54 121 NoLq

25.670.5 121 NoLq

34.191.14 121 NoLq

30.0 1.21 121 NoLq

31.210.75 121 NoLq

28.921.5 121 NoLq

21.940.72 121 NoLq

22.6 0.68 121 NoLq

18.660.507 121 NoLq

26.0 0.762 121 NoLq

23.870.615 121 NoLq

51.361.905 121 NoLq

75.042.75 121 NoLq

27.461.01 121 NoLq

18.740.39 121 NoLq

36.871.24 121 NoLq

28.870.79 121 NoLq

27.520.65 121 NoLq

32.260.68 121 NoLq

38.220.76 121 NoLq

59.451.85 121 NoLq

18.020.39 121 NoLq

23.820.423 121 NoLq

31.430.774 121 NoLq

38.9 1.28 121 NoLq

32.5 0.98 121 NoLq

29.120.82 121 NoLq

27.760.67 121 NoLq

37.620.79 121 NoLq

53.652.13 121 NoLq

69.862.01 121 NoLq
212.64.85 121 NoLq

49.171.51 121 NoLq

51.662.92 121 NoLq
Silty CLAY
Raw Unit Fines
qc fc Weight %
Shear Stress Ratio
CRR CSR f s1
Shaded Zone has Liquefaction Potential
0 1
Soil Description Factor of Safety
0 51
Settlement
Saturated
Unsaturat.

S = 0.00 in.
0 (in.) 1
fs1=1.30

Silicon Valley Soil
Engineering

LIQUEFACTION ANALYSIS
CPT-2
Proposed Townhomes
File No. SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 8
Milpitas, California Scale: NOT TO SCALE November
2020

Page 189 of 395 ends

LiquefyPro CivilTech Software USA www.civiltech.com CivilTech Corporation

LIQUEFACTION ANALYSIS
SV1772 - Proposed Townhomes
1724 Sunnyhills Drive, Milpitas, CA. Plate A-1
Hole No.=CPT-3 Water Depth=15 ft Surface Elev.=100 Magnitude=7.9 Acceleration=0.747g
(ft)
0 10
20 30
40 50
60 70

25.3 0.48 121 NoLq

13.740.101 121 NoLq

18.680.326 121 NoLq

42.801.485 121 NoLq

55.911.479 121 NoLq

47.991.339 121 NoLq

63.751.91 121 NoLq
102.42.197 121 NoLq

34.271.165 121 NoLq

26.950.777 121 NoLq

19.200.648 121 NoLq

14.160.51 121 NoLq

15.5 0.22 121 NoLq

24.510.44 121 NoLq

34.110.85 121 NoLq

26.031.03 121 NoLq

31.020.637 121 NoLq

51.892.11 121 NoLq

96.322.36 121 NoLq

33.371.52 121 NoLq

29.641.42 121 NoLq

41.811.41 121 NoLq

23.020.89 121 NoLq

22.240.56 121 NoLq

25.830.98 121 NoLq

27.020.81 121 NoLq

69.052.43 121 NoLq

60.631.94 121 NoLq
161.31.57 121 NoLq

38.421.59 121 NoLq

34.610.724 121 NoLq

37.290.971 121 NoLq

26.910.732 121 NoLq

19.770.352 121 NoLq

19.480.57 121 NoLq

16.310.289 121 NoLq

21.944.01 121 NoLq

13.990.311 121 NoLq

40.4 1.12 121 NoLq
114.64.7 121 NoLq

36.022.0 121 NoLq

20.890.774 121 NoLq

25.790.697 121 NoLq

27.760.74 121 NoLq

31.270.994 121 NoLq

43.6 1.6 121 NoLq

37.561.56 121 NoLq
138.75.43 121 NoLq
250.58.18 121 NoLq

45.342.03 121 NoLq
Silty CLAY
Raw Unit Fines
qc fc Weight %
Shear Stress Ratio
CRR CSR f s1
Shaded Zone has Liquefaction Potential
0 1
Soil Description Factor of Safety
0 51
Settlement
Saturated
Unsaturat.

S = 0.00 in.
0 (in.) 1
fs1=1.30

Silicon Valley Soil
Engineering

LIQUEFACTION ANALYSIS
CPT-3
Proposed Townhomes
File No. SV1772

FIGURE

1916 O’Toole Way
San Jose, CA 95131
(408) 324-1400

1724 Sunnyhills Drive
Drawn by: V.V. 9
Milpitas, California Scale: NOT TO SCALE November
2020

Page 190 of 395 ends

MAJOR DIVISIONS SYMBOL TYPICAL NAMES
GRAVELS GW Well graded gravel or gravel-sand mixtures, little or no fines (More than 1/2 of GP Poorly graded gravel or gravel-sand moistures, little or no fines coarse fraction > GM Silty gravels, gravel-sand-silt mixtures no. 4 sieve size) GC Clayey Gravels, gravel-sand-clay mixtures SANDS SW Well graded sands or gravelly sands, no fines (More than 1/2 of SP Poorly graded sands or gravelly sands, no fines coarse fraction < SM Silty sands, sand-silt mixtures
no. 4 sieve size SC Clayey sands, sand-clay mixtures
SILTS & CLAYS ML Inorganic silts and very fine sand, rock, flour, silty or clayey fine sand or clayey silt/slight plasticity
LL < 50 CL Inorganic clay of low to medium plasticity, gravelly clayes, sandy clay, silty clay, lean clays
OL Organic siltys and organic silty clay of low plasticity SILTS & CLAYS MH Inorganic silts, micaceous or diatocaceous fine sandy, or silty soils, elastic silt
LL > 50 CH Inorganic clays of high plasticity, fat clays OH Organic clays of medium to high plasticity, organic silty clays, organic silts
HIGHLY ORGANIC SOIL PT Peat and other highly organic soils

CLASSIFICATION CHART - UNIFIED SOIL CLASSIFICATION SYSTEM

CLASSIFICATION RANGE OF GRAIN SIZES

U.S. Standard
Sieve Size
Grain Size
In Millimeters
BOULDERS Above 12" Above 305
COBBLES 12" to 3" 305 to 76.2

GRAVELS
Coarse
Fine
3" to No. 4
3" to 3/4"
3/4" to No. 4

76.2 to 4.76

76.2 to 19.1

19.1 to 4.76

SAND
Coarse
Medium
Fine

No. 4 to No. 200
No. 4 to No. 10
No.10 to No. 40
No.40 to No. 200

4.76 to 0.074

4.76 to 2.00

2.00 to 0.420

0.420 to 0.074
SILT AND CLAY Below No. 200 Below 0.074

Method of Soil Classification Chart SILICON VALLEY SOIL ENGINEERING

METHOD OF SOIL CLASSIFICATION CHART
File No. SV1772

Liquid Limit %
0 10 20 30 40 50 60 70 80 90 100 60 50
20 30
40 7
10 4
0 PLASTICITY INDEX CHART
N
CL
ML MI
CI
CH
CV CE
ME
MH
MV

Page 191 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Key to Log of Boring
Material Type
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf
Graphic Log
Water Content, %
Dry Unit Weight, pcfMATERIAL DESCRIPTION
Direct Shear Test - Internal
Friction Angle in degrees
Depth (feet)
Sample Number
Sample Type
Sampling Resistance,
blows/ft
1 2 3 4 5 6 7 8 9 10 11 12 13

COLUMN DESCRIPTIONS
1 Depth (feet): Depth in feet below the ground surface. 2 Sample Type: Type of soil sample collected at the depth interval shown.
3 Sample Number: Sample identification number.
4 Sampling Resistance, blows/ft: Number of blows to advance driven sampler one foot (or distance shown) beyond seating interval using the hammer identified on the boring log.
5 Material Type: Type of material encountered.
6 Graphic Log: Graphic depiction of the subsurface material encountered.
7 MATERIAL DESCRIPTION: Description of material encountered.

May include consistency, moisture, color, and other descriptive text.
8 Water Content, %: Water content of the soil sample, expressed as percentage of dry weight of sample.
9 Dry Unit Weight, pcf: Dry weight per unit volume of soil sample measured in laboratory, in pounds per cubic foot.
10 Direct Shear Test - Cohesion in ksf: Cohesion is the y-axis intercept of the failure envelope tangent to the Mohr circles. 11 Direct Shear Test - Internal Friction Angle in degrees: The internal friction angle (Phi) is the angle inclination of the failure envelope. 12 Liquid Limit - LL, %: Liquid Limit, expressed as a water content. 13 Plasticity Index - PI, %: Plasticity Index, expressed as a water content.

FIELD AND LABORATORY TEST ABBREVIATIONS
CHEM: Chemical tests to assess corrosivity
COMP: Compaction test
CONS: One-dimensional consolidation test
LL: Liquid Limit, percent
PI: Plasticity Index, percent
SA: Sieve analysis (percent passing No. 200 Sieve)
UC: Unconfined compressive strength test, Qu, in ksf
WA: Wash sieve (percent passing No. 200 Sieve)

MATERIAL GRAPHIC SYMBOLS
Fat CLAY, CLAY w/SAND, SANDY CLAY (CH)
Lean CLAY, CLAY w/SAND, SANDY CLAY (CL)

SILTY CLAY (CL-ML)
Grass and/or topsoil
Poorly graded SAND (SP)

TYPICAL SAMPLER GRAPHIC SYMBOLS
Auger sampler
Bulk Sample
3-inch-OD California w/
brass rings
CME Sampler
Grab Sample

2.5-inch-OD Modified
California w/ brass liners
Pitcher Sample
2-inch-OD unlined split
spoon (SPT)
Shelby Tube (Thin-walled,
fixed head)

OTHER GRAPHIC SYMBOLS
Water level (at time of drilling, ATD)
Water level (after waiting)
Minor change in material properties within a
stratum
Inferred/gradational contact between strata
? Queried contact between strata

GENERAL NOTES
1: Soil classifications are based on the Unified Soil Classification System. Descriptions and stratum lines are interpretive, and actual lithologic changes may be gradual. Field descriptions may have been modified to reflect results of lab tests. 2: Descriptions on these logs apply only at the specific boring locations and at the time the borings were advanced. They are not warranted to be representative of subsurface conditions at other locations or times.

Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 192 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Log of Boring B-1
Date(s)
Drilled 05/01/18
Drilling
Method Solid Stem Auger
Groundwater Level
and Date Measured 15 feet (05/01/2018)
Borehole
Backfill Grout
Logged By V.V.

Drill Bit
Size/Type 4-inch
Sampling
Method(s) Modified California
Location
Checked By
Total Depth
of Borehole 20.0 feet
Approximate
Surface Elevation feet
Hammer
Data 140 lbs
Material Type
Grass
CH
CL
CL-ML
CL
SP
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf

0.8 Graphic Log
Water Content, %

19.2 16.3

15.7 17.2

20.0 Dry Unit Weight, pcf
102.4
117.0
116.8
108.2
103.1

MATERIAL DESCRIPTION

3.0 inches of organic material
Black Silty CLAY
Moist, very stiff
Dark Gray Silty CLAY
Moist, very stiff

Color changed to brown
Tan Brown Clayey SILT
Moist, very stiffReddish Brown Silty CLAY
Moist, stiffBrown Silty SAND
Moist, medium dense
SAND: medium-grained, poorly graded
Boring terminated at 20.0 feet
First encountered
Stablized at drilling completion
Direct Shear Test - Internal
Friction Angle in degrees
12 Depth (feet)
0 5
10 15
20 25
30 0.25
3 8
13 18
Sample Number
1-1
1-2
1-3
1-4
1-5
Sample Type
Sampling Resistance,
blows/ft
32 55+
33 20
22 Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 193 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Log of Boring B-2
Date(s)
Drilled 05/01/18
Drilling
Method Solid Stem Auger
Groundwater Level
and Date Measured 15 feet (05/01/2018)
Borehole
Backfill Grout
Logged By V.V.

Drill Bit
Size/Type 4-inch
Sampling
Method(s) Modified California
Location
Checked By
Total Depth
of Borehole 20.0 feet
Approximate
Surface Elevation feet
Hammer
Data 140 lbs
Material Type
Grass
CH
CL
CL-ML
CL
SP
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf
Graphic Log
Water Content, %

18.7 15.5

16.2 16.0

17.3 Dry Unit Weight, pcf
101.2
114.4
115.6
107.9
102.7

MATERIAL DESCRIPTION

3.0 inches of organic material
Black Silty CLAY
Moist, very stiff
Dark Gray Silty CLAY
Moist, very stiff

Color changed to brown
Tan Brown Clayey SILT
Moist, very stiffReddish Brown Silty CLAY
Moist, stiffBrown Silty SAND
Moist, medium dense
SAND: medium-grained, poorly graded
Boring terminated at 20.0 feet
First encountered
Stablized at drilling completion
Direct Shear Test - Internal
Friction Angle in degrees
Depth (feet)
0 5
10 15
20 25
30 0.25
3 8
13 18
Sample Number
2-1
2-2
2-3
2-4
2-5
Sample Type
Sampling Resistance,
blows/ft
30 47
34 22
23 Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 194 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Log of Boring B-3
Date(s)
Drilled 05/01/18
Drilling
Method Solid Stem Auger
Groundwater Level
and Date Measured 15 feet (05/01/2018)
Borehole
Backfill Grout
Logged By V.V.

Drill Bit
Size/Type 4-inch
Sampling
Method(s) Modified California
Location
Checked By
Total Depth
of Borehole 20.0 feet
Approximate
Surface Elevation feet
Hammer
Data 140 lbs
Material Type
Asphalt
CH
CL
CL-ML
CL
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf
Graphic Log
Water Content, %

19.5 16.0

16.9 15.2

17.1 Dry Unit Weight, pcf
102.4
113.8
113.3
106.7
103.1

MATERIAL DESCRIPTION

3.0 inches of Asphalt Concrete (AC)

4.0 inches of Aggregate Base (AB)
Black Silty CLAY
Moist, very stiff
Dark Gray Silty CLAY
Moist, very stiff

Color changed to brown
Tan Brown Clayey SILT
Moist, very stiffReddish Brown Silty CLAY
Moist, stiff
Boring terminated at 20.0 feet
First encountered
Stablized at drilling completion
Direct Shear Test - Internal
Friction Angle in degrees
Depth (feet)
0 5
10 15
20 25
30 Sample Number
3-1
3-2
3-3
3-4
3-5
Sample Type
Sampling Resistance,
blows/ft
31 45
33 24
26 Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 195 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Log of Boring B-4
Date(s)
Drilled 05/01/18
Drilling
Method Solid Stem Auger
Groundwater Level
and Date Measured 15 feet (05/01/2018)
Borehole
Backfill Grout
Logged By V.V.

Drill Bit
Size/Type 4-inch
Sampling
Method(s) Modified California
Location
Checked By
Total Depth
of Borehole 20.0 feet
Approximate
Surface Elevation feet
Hammer
Data 140 lbs
Material Type
Grass
CH
CL
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf
Graphic Log
Water Content, %

20.5 17.1

16.0 19.4

18.7 Dry Unit Weight, pcf
105.0
115.3
111.7
111.6
112.7

MATERIAL DESCRIPTION

3.0 inches of organic material
Black Silty CLAY
Moist, very stiff
Dark Gray Silty CLAY
Moist, very stiff

Color changed to brown

Color changed to reddish brown
Boring terminated at 20.0 feet
First encountered
Stablized at drilling completion
Direct Shear Test - Internal
Friction Angle in degrees
Depth (feet)
0 5
10 15
20 25
30 0.25
Sample Number
4-1
4-2
4-3
4-4
4-5
Sample Type
Sampling Resistance,
blows/ft
22 27
32 16
37 Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 196 of 395 ends

Project: Proposed Townhomes
Project Location: 1724 Sunnyhills Drive
Milpitas, California
Project Number: SV1772
Log of Boring B-5
Date(s)
Drilled 05/01/18
Drilling
Method Solid Stem Auger
Groundwater Level
and Date Measured 15 feet (05/01/2018)
Borehole
Backfill Grout
Logged By V.V.

Drill Bit
Size/Type 4-inch
Sampling
Method(s) Modified California
Location
Checked By
Total Depth
of Borehole 20.0 feet
Approximate
Surface Elevation feet
Hammer
Data 140 lbs
Material Type
Grass
CH
CL
Liquid Limit - LL, %
Plasticity Index - PI, %
Direct Shear Test -
Cohesion in ksf

0.9 Graphic Log
Water Content, %

19.9 22.7

14.9 14.5

18.5 Dry Unit Weight, pcf
101.0
101.0
120.3
117.4
114.2

MATERIAL DESCRIPTION

3.0 inches of organic material
Black Silty CLAY
Moist, very stiff
Dark Gray Silty CLAY
Moist, very stiff

Color changed to brown

Color changed to reddish brown
Boring terminated at 20.0 feet
First encountered
Stablized at drilling completion
Direct Shear Test - Internal
Friction Angle in degrees
12 Depth (feet)
0 5
10 15
20 25
30 0.25
Sample Number
5-1
5-2
5-3
5-4
5-5
Sample Type
Sampling Resistance,
blows/ft
35 27
47 40
35 Sheet 1 of 1
Silicon Valley Soil Engineering
2391 Zanker Road, Suite 350
San Jose, CA 95131
(408) 324-1400

Page 197 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 9 of 16 M arch 12, 2021

APPENDIX C
MRP Calculation Worksheet

Page 198 of 395 ends

SANTA CLARA VALLEY URBAN RUNOFF POLLUTION PREVENTION PROGRAM B-14 Appendix B

Section III. Sizing for Flow-Based Treatment Measures, continued

This method uses the Rational Method equation:

Q=CIA
Where:

Q = the design flow in cubic feet per second (cfs),
C = the drainage area runoff coefficient,
I = the design intensity (in/hr), and
A = the drainage area for the BMP (acres)

Step 1. Determine the drainage area for the BMP, A = _____ acres

Step 2. Determine the runoff coefficient, C = _____ from Table B-3.

Step 3. Use a design intensity of 0.2 in/hr for “I” in the Q=CIA equation.

I = __0.2 in/hr___

Step 4. Determine the design flow (Q) using Q = CIA
Q = C  I  A
Q = (Step 2)  (0.2 in/hr)  (Step 1)
Q = ______ acres-in/hr
Design Flow, Q = __________cfs10

10 No conversion factor for correct units is needed for the rational formula because (1 acre-in/hr) X (43,560 sq. ft./acre) X (1ft/12 in) X (1hr/3600 sec)  1 ft3/sec or cfs.

Section III.C —Sizing Flow-Based Treatment Me asures based on the Uniform Intensity Approach

Page 199 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 10 of 16 March 12, 2021

APPENDIX D
BMP Sizing Calculations

Page 200 of 395 ends

Sandis
636 9th Street
Oakland, CA 94607
April 19, 2019
Storm Water Control Plan - City of Milpitas
BMP Sizing Calculations
Sunnyhills Apartments
Project location: Milpitas, CA
Sandis Project No.: 617012
Date: 3/2/2022
Storm Water Treatment Measures

WATERSHED IMPERVIOUS

AREA (SF)

EXISTING

IMPERVIOUS

AREA (SF)

EFFECTIVE

IMPERVIOUS

AREA (SF)

PERVIOUS

AREA (SF) TOTAL (SF) TREATMENT

METHOD BMP ID

TREATMENT

AREA REQUIRED
(SF) (4% RULE) 1

TREATMENT
AREA

PROVIDED (SF)
AREA 1 6,175 0 6,318 1,433 7,608 BIORETENTION B1 253 254 AREA 2 16,403 0 16,736 3,332 19,735 BIORETENTION B2 7 670 672 AREA 3 4,892 0 5,071 1,791 6,683 BIORETENTION B3 203 277 AREA 4 4,801 0 4,974 1,729 6,530 BIORETENTION B4 199 240 AREA 5 9,385 0 9,576 1,912 11,297 BIORETENTION B5 383 398 AREA 6 3,148 0 3,180 320 3,468 BIORETENTION B6 127 137
AREA 7 1,310 0 1,417 1,074 2,384 INTERCEPTOR
TREE CREDIT - 2,384 2,700
AREA 8 10,352 0 10,886 5,341 15,693 BIORETENTION B8 435 465 AREA 9 2,310 0 2,500 1,900 4,210 BIORETENTION B9 100 129 AREA 10 6,882 2062 5 7,329 4,472 11,354 BIORETENTION B10 293 293 AREA 11 4,623 0 4,871 2,483 7,106 BIORETENTION B11 195 316 AREA 12 2,053 0 2,125 718 2,771 IN-LIEU 6
- 85 2,125
Storm Water Credits For Interceptor Trees

TOTAL AREA
(SF)
SELF

TREATING

LANDSCAPE

AREAS (SF)
NEW

IMPERVIOUS

AREA TO BE

TREATED (SF)

TREATMENT
METHOD
NEW
DECIDUOUS 4

NEW DECIDUOUS

TREE CREDITS
(SF)

IMPERVIOUS
AREA

TREATED

USING TREE

CREDITS (SF)
AREA 7 2,384 1,074 1,310 INTERCEPTOR
TREE CREDIT 2,3 27 2,700 1,310
NOTES:

1.Required treatment area is 4% of the effective impervious area using an infilitration rate of 5 inch es per hour and the uniform intensity of [0.2 in/hr / 5 in/hr] = 4% per hour.

2.Interceptor trees to meet the requirements of the Santa Clara Valley Urban Runoff Pollution Preventi on Program (SCVURPP) C.3 Technical Guidance Manural, Latest Version.

3.Proposed Interceptor trees located within 25-feet of "Existing Impervious Area to Remain" will treat a portion of the existing impervious area and prov ide an "in lieu" treatment area credit for a portion of the impervious area that is being created/replaced in Watersheds A12.

4.New deciduous trees count for 100 square feet of credit per tree. New evergreen trees count for 200 square feet of credit per tree.

5. Existing impervious area is being treated with a new BMP and is being taken as an alternative compliance or in-leiu credit for the site. This will off set a portion of the site's new impervious area that is not proposed to be treated. The total credit available from DMA 10 is 2,062 sf of credit available to offset new untreated imperv ious areas.

6. DMA 12 has a portion of new impervious surface that will be untreated and offset using in-lieu area credit (see note 5). The rest of the DMA consists of landscaping.

7. BMP B2 is located partially within an existing 2 0' wide public sanitary sewer and storm drain easement. In the event the city must access this space to maintain or make repairs to the underlying sewer and storm drain mains, the owner shall maintain operability of the bioretention basin and rebuild affected portio ns of the basin in accordance with the project design drawings and specifications.

X:\P\617012\MODELS AND CALCS\STORM\SWCP\Appendices\Appendix D - BMP Sizing\Updated Calcs\Appendix D - BMP Sizing Calculations

Page 201 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 11 of 16 March 12, 2021

APPENDIX E
Site Plan

Page 202 of 395 ends

ÜÜÜÜ
ÜÜÜÜÜÜÜÜÜÜÜÜ
ÜÜÜ
Ü
ÜÜÜÜ
Ü
ÜÜÜ
ÜÜÜÜÜÜÜÜArchitects1288 Kifer Road, Unit 206,Sunnyvale, CA 94086Telephone : 408-992-0280Fax : 408-992-0281build on.sandis.net Ü

Page 203 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 12 of 16 March 12, 2021

APPENDIX F
BMP Enlarged Details

Page 204 of 395 ends

Architects
1288 Kifer Road, Unit 206,
Sunnyvale, CA 94086
Telephone : 408-992-0280
Fax : 408-992-0281
build on.
sandis.net

CONSTRUCTION

DETAILS
C6.0
27

Page 205 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 13 of 16 March 12, 2021

APPENDIX G
Operations & Maintenance Manual

Page 206 of 395 ends
Page 207 of 395 ends
Page 208 of 395 ends
Page 209 of 395 ends
Page 210 of 395 ends

Sunnyhills Apartments, Milpitas, CA

Page 1 ends

Stormwater Treatment Measure Operation and Maintenance
Inspection Report to the Milpitas, California

This report and attached Inspection and Maintenance Checklists document the inspection and maintenance conducted for the identified stormwater treatment measure(s) subject to the Maintenance Agreement between the City of Milpitas and the property owner during the annual reporting period indicated below.

I. Property Information:

Property Address or APN:

Property Owner:

II. Contact Information:

Name of person to contact regarding this report:

Phone number of contact person: Email:

Address to which correspondence regarding this report should be directed:

III. Reporting Period:

This report, with the attached completed inspection checklists, documents the inspections and maintenance of the identified treatment measures during the time period from to .

IV. Stormwater Treatment Measure Information:

The following stormwater treatment measures (identified treatment measures) are located on the property identified above and are subject to the Maintenance Agreement:

Identifying
Number of
Treatment
Measure
Type of Treatment Measure Location of Treatment Measure on the Property

Page 211 of 395 ends

Sunnyhills Apartments, Milpitas, CA

Page 2 ends

V. Summary of Inspections and Maintenance:

Summarize the following information using the attached Inspection and Maintenance Checklists:

Identifying
Number of
Treatment
Measure
Date of
Inspection
Operation and Maintenance Activities
Performed and Date(s) Conducted
Additional Comments

VI. Sediment Removal:

Total amount of accumulated sediment removed from the stormwater treatment measure(s) during the reporting period: _________ cubic yards.

How was sediment disposed?
 landfill
 other location on-site as described in and allowed by the maintenance plan
 other, explain ___________________

Page 212 of 395 ends

Sunnyhills Apartments, Milpitas, CA

Page 3 ends

VII. Inspector Information:

The inspections documented in the attached Inspection and Maintenance Checklists were conducted by the following inspector(s):

Inspector Name and Title Inspector’s Employer and Address

VIII. Certification:

I hereby certify, under penalty of perjury, that the information presented in this report and attachments is true and complete:

Signature of Property Owner or Other Responsible Party Date

Type or Print Name

Company Name

Address

Phone number: Email:

Please submit the Operation and Maintenance Inspection reports, Maintenance Plan, and Inspection and Maintenance checklist for each BMP to the following address:

City of Milpitas
455 E. Calaveras Blvd.

Milpitas, CA 95035
Attn: Utility Engineer

Page 213 of 395 ends
Page 1 ends

Bioretention Area Maintenance Plan for
Sunnyhills Apartments, Milpitas, CA

10/16/2017
Project Address and Cross Streets: Alder Drive and Barber Lane Assessor’s Parcel No.: 086-02-086
Property Owner: Phone No.:

Designated Contact: Phone No.:

Mailing Address:

The property contains ten (10) bioretention area(s) , located as described below and as shown in the attached site plan

1. Bioretention Area No. 1 is located at the northeast corner of the site.

Bioretention Area No. 2 is located at the southeast corner of the site.

Bioretention Area No. 3 is centrally located in the northern portion of t the site.

Bioretention Area No. 4 is located in the middle of the site, south of Bioretention Area #3.

Bioretention Area No. 5 is centrally located, south of Bioretention Area #4.

Bioretention Area No. 6 is located along the southern edge of the site.

Bioretention Area No. 8 is located west of Bio retention Area #3 and east of Bioretention Area #10.

Bioretention Area No. 9 is located at the northwest corner of the site.

Bioretention Area No. 10 is located along the western boundary of the site, south of Bioretention Area #9.

Bioretention Area No. 11 is centrally located in the site, west of Bioretention Area #4.

I. Routine Maintenance Activities
The principal maintenance objective is to prevent s ediment buildup and clogging, which reduces pollutant removal efficiency and may lead t o bioretention area failure. Routine maintenance activities, and the frequency at which they will be conducted, are shown in Table 1.

Table 1
Routine Maintenance Activities for Bioretention Areas
No. Maintenance Task Frequency of Task
1 Remove obstructions, weeds, debris and trash from
bioretention area and its inlets and outlets; and dispose of properly.

Quarterly, or as needed after storm
events
2 Inspect bioretention area for standing water. If standing water does not drain within 2-3 days, till and replace the surface biotreatment soil with the approved soil mix and replant.

Quarterly, or as needed after storm
events
3 Check underdrains for clogging. Use the cleanout riser to clean any clogged underdrains.

Quarterly, or as needed after storm
events
4 Maintain the irrigation system and ensure that plan ts are receiving the correct amount of water (if applicable).

Quarterly
5 Ensure that the vegetation is healthy and dense enough to provide filtering and protect soils from erosion. P rune and weed the bioretention area. Remove and/or replace a ny
dead plants.

Annually, before the wet season
begins
6 Use compost and other natural soil amendments and
fertilizers instead of synthetic fertilizers, espec ially if the system uses an underdrain.

Annually, before the wet season
begins

1 Attached site plan must match the site plan exhibit to Maintenance Agreement.

Page 214 of 395 ends

Bioretention Area Maintenance Plan Date of Inspection:

Property Address: Treatment Measure No.:

Page 2 ends

7 Check that mulch is at appropriate depth (2 - 3 inches per soil specifications) and replenish as necessary before wet season begins. It is recommended that 2” – 3” of arbor
mulch be reapplied every year.

Annually, before the wet season
begins
8 Inspect the energy dissipation at the inlet to ensure it is functioning adequately, and that there is no scour of the surface mulch. Remove accumulated sediment.

Annually, before the wet season
begins
9 Inspect overflow pipe to ensure that it can safel y convey excess flows to a storm drain. Repair or replace damaged piping.

Annually, before the wet season
begins
10 Replace biotreatment soil and mulch, if needed. Check for standing water, structural failure and clogged overflows.

Remove trash and debris. Replace dead plants.

Annually at the end of the rainy
season, and/or after large storm
events
11 Inspect bioretention area using the attached ins pection checklist.

Annually, before the wet season

II. Use of Pesticides

Do not use pesticides or other chemical applications to treat diseased plants, control weeds or removed unwanted growth. Employ non-chemical controls (biological, physical and cultural controls) to treat a pest problem. Prune plants properly and at the appropriate time of year.

Provide adequate irrigation for landscape plants. Do not over water.

III. Vector Control

Standing water shall not remain in the treatment measures for more than five days, to prevent mosquito generation. Should any mosquito issues arise, contact the Santa Clara Valley Vector Control District (District). Mosquito larvicides shall be applied only when absolutely necessary, as indicated by the District, and then only by a licensed professional or contractor. Contact information for the District is provided below.

Santa Clara Valley Vector Control District
1580 Berger Dr.

San José, California 95112
Phone: (408) 918-4770 / (800) 675-1155 - Fax: (408) 298-6356 www.sccgov.org/portal/site/vector

IV. Inspections
The attached Bioretention Area Inspection and Maint enance Checklist shall be used to conduct inspections monthly (or as needed), identif y needed maintenance, and record maintenance that is conducted.

Page 215 of 395 ends

Bioretention Area Maintenance Plan - Page 3
Bioretention Area
Inspection and Maintenance Checklist

Property Address: Property Owner:

Treatment Measure No.: Date of Inspection: Type of Inspection:  Quarterly  Pre-Wet Season  After heavy runoff  End of Wet Season
Inspector(s):  Other:

Defect Conditions When Maintenance Is
Needed
Maintenance
Needed? (Y/N)
Comments (Describe maintenance
completed and if needed maintenance was
not conducted, note when it will be done)
Results Expected When
Maintenance Is Performed

1. Standing Water Water stands in the bioretention area between storms and does not drain
within 2-3 days after rainfall.

There should be no areas of
standing water once storm event
has ceased. Any of the following
may apply: sediment or trash
blockages removed, improved
grade from head to foot of
bioretention area, or added
underdrains.

2. Trash and Debris
Accumulation
Trash and debris accumulated in the
bioretention area, inlet, or outlet.

Trash and debris removed from
bioretention area and disposed of
properly.

3. Sediment Evidence of sedimentation in
bioretention area.

Material removed so that there is no
clogging or blockage. Material is
disposed of properly.

4. Erosion Channels have formed around inlets,
there are areas of bare soil, and/or
other evidence of erosion.

Obstructions and sediment removed
so that water flows freely and
disperses over a wide area.

Obstructions and sediment are
disposed of properly.

5. Vegetation Vegetation is dead, diseased and/or
overgrown.

Vegetation is healthy and attractive
in appearance.

6. Mulch Mulch is missing or patchy in
appearance. Areas of bare earth are
exposed, or mulch layer is less than 2
inches in depth.

All bare earth is covered, except
mulch is kept 6 inches away from
trunks of trees and shrubs. Mulch is
even in appearance, at a depth of 2
– 3 inches.

7. Miscellaneous Any condition not covered above that
needs attention in order for the
bioretention area to function as
designed.

Meets the design specifications.

Page 216 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 14 of 16 March 12, 2021

APPENDIX H
Storm Drain Analysis Summary

Page 217 of 395 ends

Autodesk Storm and Sanitary AnalysisAutodesk Storm and Sanitary Analysis

Page 218 of 395 ends

Project Description
2021-03-12 Proposed Hydraulics Freeboard Calculations.SPF Project Options
CFS
Elevation
Modified Rational
User-Defined
Hydrodynamic
YES
NO
Analysis Options
Mar 10, 2021 00:00:00
Mar 10, 2021 03:00:00
Mar 10, 2021 00:00:00
0 days
0 01:00:00 days hh:mm:ss
0 00:05:00 days hh:mm:ss
0 00:05:00 days hh:mm:ss
30 seconds
Number of Elements
Qty
0 14
38 25
3 0
0 10
35 0
25 0
10 0
0 0
0 Rainfall Details
10 year(s)
Outlets .........................................................................

Pollutants ..............................................................................

Land Uses ............................................................................

Return Period........................................................................

Links......................................................................................

Channels ......................................................................

Pipes ............................................................................

Pumps ..........................................................................

Orifices .........................................................................

Weirs ............................................................................

Nodes....................................................................................

Junctions ......................................................................

Outfalls .........................................................................

Flow Diversions ............................................................

Inlets ............................................................................

Storage Nodes .............................................................

Runoff (Dry Weather) Time Step ..........................................

Runoff (Wet Weather) Time Step .........................................

Reporting Time Step ............................................................

Routing Time Step ................................................................

Rain Gages ..........................................................................

Subbasins..............................................................................

Enable Overflow Ponding at Nodes .....................................

Skip Steady State Analysis Time Periods ............................

Start Analysis On ..................................................................

End Analysis On ...................................................................

Start Reporting On ...............................................................

Antecedent Dry Days ............................................................

File Name .............................................................................

Flow Units .............................................................................

Elevation Type ......................................................................

Hydrology Method ................................................................

Time of Concentration (TOC) Method ..................................

Link Routing Method .............................................................

Page 219 of 395 ends

Subbasin Summary
SN Subbasin Area Weighted Total Total Total Peak Time of ID Runoff Rainfall Runoff Runoff Runoff Concentration
Coefficient Volume
(ft²) (in) (in) (ac-in) (cfs) (days hh:mm:ss)
1 DMA-01 7735.99 0.8100 0.33 0.27 0.05 0.28 0 00:10:00 2 DMA-02 19711.99 0.8200 0.33 0.27 0.12 0.73 0 00:10:00 3 DMA-03 8714.00 0.7800 0.33 0.26 0.05 0.31 0 00:10:00 4 DMA-04 10028.99 0.7200 0.33 0.24 0.05 0.33 0 00:10:00 5 DMA-05 9256.02 0.8100 0.33 0.27 0.06 0.34 0 00:10:00 6 DMA-06 3504.00 0.8400 0.33 0.27 0.02 0.13 0 00:10:00 7 DMA-07 2326.02 0.6700 0.33 0.22 0.01 0.07 0 00:10:00 8 DMA-08 16462.98 0.7200 0.33 0.24 0.09 0.53 0 00:10:00 9 DMA-09 4241.00 0.7100 0.33 0.23 0.02 0.14 0 00:10:00 10 DMA-10 10803.01 0.6800 0.33 0.22 0.06 0.33 0 00:10:00 11 DMA-11 6849.98 0.8000 0.33 0.26 0.04 0.25 0 00:10:00 12 DMA-12 2640.00 0.7600 0.33 0.25 0.02 0.09 0 00:10:00 13 DMA-13 58003.00 0.7900 0.33 0.26 0.34 2.06 0 00:10:00 14 DMA-14 53518.00 0.8400 0.33 0.27 0.34 2.02 0 00:10:00

Page 220 of 395 ends

Node Summary
SN Element Element Invert Ground/Rim Initial Surcharge Ponded Peak Max HGL Max Min Time of Total Total Time ID Type Elevation (Max) Water Elevation Area Inflow Elevation Surcharge Freeboard Peak Flooded Flooded Elevation Elevation Attained Depth Attained Flooding Volume Attained Occurrence
(ft) (ft) (ft) (ft) (ft²) (cfs) (ft) (ft) (ft) (days hh:mm) (ac-in) (min) 1 SD-01-MH Junction 31.50 43.90 34.96 0.00 0.00 0.61 34.96 0.00 8.94 0 00:00 0.00 0.00 2 SD-02-CO Junction 36.09 40.00 34.96 0.00 0.00 0.92 36.55 0.00 3.45 0 00:00 0.00 0.00 3 SD-03-CB Junction 38.24 40.83 34.96 0.00 0.00 0.15 38.36 0.00 2.47 0 00:00 0.00 0.00 4 SD-04-CO Junction 36.92 41.00 34.96 0.00 0.00 0.81 37.31 0.00 3.69 0 00:00 0.00 0.00 5 SD-05-CB Junction 37.34 42.46 34.96 0.00 0.00 0.30 37.59 0.00 4.87 0 00:00 0.00 0.00 6 SD-06-MH Junction 37.71 43.96 34.96 0.00 0.00 0.51 38.00 0.00 5.96 0 00:00 0.00 0.00 7 SD-07-WYE Junction 37.85 41.00 34.96 0.00 0.00 0.51 38.22 0.00 2.78 0 00:00 0.00 0.00 8 SD-08-CB Junction 38.44 41.58 34.96 0.00 0.00 0.29 38.71 0.00 2.87 0 00:00 0.00 0.00 9 SD-09-CB Junction 41.16 43.83 34.96 0.00 0.00 0.22 41.30 0.00 2.53 0 00:00 0.00 0.00 10 SD-10-CB Junction 39.21 41.83 34.96 0.00 0.00 0.61 39.65 0.00 2.18 0 00:00 0.00 0.00 11 SD-11-WYE Junction 34.29 39.50 34.96 6.00 0.00 1.42 35.35 0.00 4.15 0 00:00 0.00 0.00 12 SD-12-CB Junction 34.74 38.00 34.96 0.00 0.00 0.13 35.36 0.00 2.64 0 00:00 0.00 0.00 13 SD-13-CB Junction 35.72 38.83 34.96 0.00 0.00 0.13 35.87 0.00 2.96 0 00:00 0.00 0.00 14 SD-14-CB Junction 34.76 38.13 34.96 0.00 0.00 1.31 35.72 0.00 2.41 0 00:00 0.00 0.00 15 SD-15-MH Junction 35.95 38.60 34.96 0.00 0.00 1.03 36.33 0.00 2.27 0 00:00 0.00 0.00 16 SD-16-CB Junction 36.15 38.88 34.96 0.00 0.00 0.73 36.62 0.00 2.26 0 00:00 0.00 0.00 17 SD-17-CO Junction 36.66 40.00 34.96 0.00 0.00 0.27 36.91 0.00 3.09 0 00:00 0.00 0.00 18 SD-18-CO Junction 39.50 41.00 34.96 0.00 0.00 0.27 39.68 0.00 1.32 0 00:00 0.00 0.00 19 SD-19-CB Junction 41.16 43.83 34.96 0.00 0.00 0.27 41.32 0.00 2.51 0 00:00 0.00 0.00 20 SD-20-MH Junction 37.27 39.77 34.96 0.00 0.00 0.31 37.57 0.00 2.20 0 00:00 0.00 0.00 21 SD-21-CO Junction 38.51 42.00 34.96 0.00 0.00 0.31 38.68 0.00 3.32 0 00:00 0.00 0.00 22 SD-22-CO Junction 39.54 42.00 34.96 0.00 0.00 0.31 39.85 0.00 2.15 0 00:00 0.00 0.00 23 SD-23-CO Junction 40.58 42.50 34.96 0.00 0.00 0.26 40.83 0.00 1.67 0 00:00 0.00 0.00 24 SD-24-CB Junction 40.74 43.33 34.96 0.00 0.00 0.26 41.03 0.00 2.30 0 00:00 0.00 0.00 25 SD-25-MH Junction 30.71 42.70 34.96 0.00 0.00 1.52 34.96 0.00 7.74 0 00:00 0.00 0.00 26 EXSD-01-MH Outfall 30.71 1.52 34.96
27 EXSD-02-CB Outfall 33.96 3.25 34.96
28 EXSD-03-CB Outfall 27.50 2.11 27.50
29 BMP-01 Storage Node 42.83 43.50 43.33 0.00 0.28 43.40 0.00 0.00 30 BMP-10 Storage Node 37.63 38.30 38.13 0.00 0.33 38.21 0.00 0.00 31 BMP-11 Storage Node 43.33 44.00 43.83 0.00 0.25 43.89 0.00 0.00 32 BMP-2 Storage Node 41.33 42.00 41.83 0.00 0.73 41.96 0.00 0.00 33 BMP-3 Storage Node 43.33 44.00 43.83 0.00 0.31 43.91 0.00 0.00 34 BMP-4 Storage Node 41.08 41.75 41.58 0.00 0.32 41.66 0.00 0.00 35 BMP-5 Storage Node 41.96 42.63 42.46 0.00 0.34 42.54 0.00 0.00 36 BMP-6 Storage Node 40.33 41.00 40.88 0.00 0.13 40.88 0.00 0.00 37 BMP-8 Storage Node 38.38 39.05 38.88 0.00 0.53 38.99 0.00 0.00 38 BMP-9 Storage Node 38.33 39.00 38.83 0.00 0.14 38.88 0.00 0.00

Page 221 of 395 ends

Link Summary
SN Element Element From To (Outlet) Length Inlet Outlet Average Diameter or Manning's Peak Design Flow Peak Flow/ Peak Flow Peak Flow Peak Flow Total Time Reported ID Type (Inlet) Node Invert Invert Slope Height Roughness Flow Capacity Design Flow Velocity Depth Depth/ Surcharged Condition Node Elevation Elevation Ratio Total Depth
Ratio
(ft) (ft) (ft) (%) (in) (cfs) (cfs) (ft/sec) (ft) (min) 1 PIPE-01 Pipe SD-01-MH SD-25-MH 84.91 31.50 30.71 0.9300 42.000 0.0150 0.61 84.11 0.01 0.06 3.48 0.99 0.00 Calculated 2 PIPE-02 Pipe SD-10-CB SD-01-MH 13.67 39.21 39.07 1.0200 8.000 0.0150 0.61 1.06 0.57 2.77 0.40 0.60 0.00 Calculated 3 PIPE-03 Pipe SD-02-CO SD-25-MH 29.15 36.09 35.79 1.0300 10.000 0.0150 0.92 1.93 0.48 3.18 0.43 0.52 0.00 Calculated 4 PIPE-04 Pipe SD-03-CB SD-02-CO 55.79 38.24 36.26 3.5500 6.000 0.0150 0.12 0.92 0.13 2.76 0.21 0.41 0.00 Calculated 5 PIPE-05 Pipe SD-04-CO SD-02-CO 82.83 36.92 36.09 1.0000 10.000 0.0150 0.80 1.90 0.42 2.87 0.43 0.51 0.00 Calculated 6 PIPE-06 Pipe SD-05-CB SD-04-CO 7.88 37.34 37.09 3.1700 6.000 0.0150 0.30 0.87 0.35 3.43 0.24 0.47 0.00 Calculated 7 PIPE-07 Pipe SD-06-MH SD-04-CO 79.55 37.71 36.92 0.9900 10.000 0.0150 0.51 1.89 0.27 2.40 0.34 0.41 0.00 Calculated 8 PIPE-08 Pipe SD-07-WYE SD-06-MH 13.48 37.85 37.71 1.0400 8.000 0.0150 0.51 1.07 0.48 2.92 0.33 0.50 0.00 Calculated 9 PIPE-09 Pipe SD-08-CB SD-07-WYE 29.27 38.44 38.02 1.4300 6.000 0.0150 0.29 0.58 0.50 2.80 0.26 0.53 0.00 Calculated 10 PIPE-10 Pipe SD-09-CB SD-07-WYE 63.76 38.49 37.85 1.0000 8.000 0.0150 0.22 2.39 0.09 1.80 0.25 0.38 0.00 Calculated 11 PIPE-11 Pipe SD-11-WYE EXSD-02-CB 8.16 34.29 33.96 4.0400 8.000 0.0140 1.42 2.26 0.63 4.08 0.67 1.00 180.00 SURCHARGED 12 PIPE-12 Pipe SD-12-CB SD-11-WYE 14.07 34.74 34.46 1.9900 6.000 0.0140 0.13 0.74 0.17 0.64 0.50 1.00 5.00 SURCHARGED 13 PIPE-13 Pipe SD-13-CB SD-12-CB 64.24 35.72 34.74 1.5300 6.000 0.0140 0.13 0.64 0.20 1.00 0.33 0.65 0.00 Calculated 14 PIPE-14 Pipe SD-14-CB SD-11-WYE 11.43 34.76 34.29 4.1100 8.000 0.0140 1.31 2.28 0.57 3.75 0.67 1.00 6.00 SURCHARGED 15 PIPE-15 Pipe SD-15-MH SD-14-CB 31.58 35.95 34.76 3.7700 8.000 0.0140 1.03 2.18 0.47 3.65 0.52 0.78 0.00 Calculated 16 PIPE-16 Pipe SD-16-CB SD-15-MH 20.42 36.15 35.95 0.9800 8.000 0.0140 0.73 1.11 0.65 3.43 0.42 0.63 0.00 Calculated 17 PIPE-17 Pipe SD-17-CO SD-16-CB 44.95 36.66 36.15 1.1300 6.000 0.0140 0.27 0.55 0.49 1.84 0.36 0.71 0.00 Calculated 18 PIPE-18 Pipe SD-18-CO SD-17-CO 77.91 39.50 36.66 3.6500 6.000 0.0140 0.27 0.99 0.28 3.46 0.21 0.43 0.00 Calculated 19 PIPE-19 Pipe SD-19-CB SD-18-CO 24.84 41.16 39.50 6.6800 6.000 0.0140 0.27 1.35 0.20 4.67 0.17 0.34 0.00 Calculated 20 PIPE-20 Pipe SD-20-MH SD-15-MH 58.89 37.27 36.68 1.0000 6.000 0.0140 0.31 0.52 0.59 2.66 0.29 0.57 0.00 Calculated 21 PIPE-21 Pipe SD-21-CO SD-20-MH 21.24 38.51 37.27 5.8400 6.000 0.0140 0.31 1.26 0.25 3.51 0.23 0.47 0.00 Calculated 22 PIPE-22 Pipe SD-22-CO SD-21-CO 103.75 39.54 38.51 0.9900 6.000 0.0140 0.31 0.52 0.60 3.34 0.24 0.48 0.00 Calculated 23 PIPE-23 Pipe SD-23-CO SD-22-CO 103.83 40.58 39.54 1.0000 6.000 0.0140 0.25 0.52 0.49 2.28 0.28 0.56 0.00 Calculated 24 PIPE-24 Pipe SD-24-CB SD-23-CO 16.21 40.74 40.58 0.9900 6.000 0.0140 0.26 0.52 0.50 2.43 0.27 0.53 0.00 Calculated 25 PIPE-25 Pipe SD-25-MH EXSD-01-MH 3.22 30.71 30.71 0.0000 0.000 0.0150 1.52 0.00 0.50 0.00 0.27 0.53 0.00 Calculated 26 OVERFLOW-01 Orifice BMP-01 SD-24-CB 42.83 40.74 12.000 0.26 27 OVERFLOW-02 Orifice BMP-2 SD-10-CB 41.33 39.21 12.000 0.61 28 OVERFLOW-03 Orifice BMP-3 SD-19-CB 43.33 41.16 12.000 0.27 29 OVERFLOW-04 Orifice BMP-4 SD-08-CB 41.08 38.44 12.000 0.29 30 OVERFLOW-05 Orifice BMP-5 SD-05-CB 41.96 37.34 12.000 0.30 31 OVERFLOW-06 Orifice BMP-6 SD-03-CB 40.33 38.24 12.000 0.15 32 OVERFLOW-08 Orifice BMP-8 SD-16-CB 38.38 36.15 12.000 0.46 33 OVERFLOW-09 Orifice BMP-9 SD-13-CB 38.33 35.72 12.000 0.13 34 OVERFLOW-10 Orifice BMP-10 SD-14-CB 37.63 34.76 12.000 0.30 35 OVERFLOW-11 Orifice BMP-11 SD-09-CB 43.33 41.16 12.000 0.22

Page 222 of 395 ends

Subbasin Hydrology
Subbasin : DMA-01
Input Data
Area (ft²) ....................................................... 7735.99 Weighted Runoff Coefficient ......................... 0.8100 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 6303.00 - 0.90
- 1432.99 - 0.40
Composite Area & Weighted Runoff Coeff. 7735.99 0.81
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.27 Peak Runoff (cfs) .......................................... 0.28 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8100 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 223 of 395 ends

Subbasin : DMA-01

Page 224 of 395 ends

Subbasin : DMA-02
Input Data
Area (ft²) ....................................................... 19711.99 Weighted Runoff Coefficient ......................... 0.8200 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 16632.99 - 0.90
- 3079.00 - 0.40
Composite Area & Weighted Runoff Coeff. 19711.99 0.82
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.27 Peak Runoff (cfs) .......................................... 0.73 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8200 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 225 of 395 ends

Subbasin : DMA-02

Page 226 of 395 ends

Subbasin : DMA-03
Input Data
Area (ft²) ....................................................... 8714.00 Weighted Runoff Coefficient ......................... 0.7800 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 6680.01 - 0.90
- 2033.99 - 0.40
Composite Area & Weighted Runoff Coeff. 8714.00 0.78
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.26 Peak Runoff (cfs) .......................................... 0.31 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7800 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 227 of 395 ends

Subbasin : DMA-03

Page 228 of 395 ends

Subbasin : DMA-04
Input Data
Area (ft²) ....................................................... 10028.99 Weighted Runoff Coefficient ......................... 0.7200 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 6518.01 - 0.90
- 3510.98 - 0.40
Composite Area & Weighted Runoff Coeff. 10028.99 0.72
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.24 Peak Runoff (cfs) .......................................... 0.33 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7200 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 229 of 395 ends

Subbasin : DMA-04

Page 230 of 395 ends

Subbasin : DMA-05
Input Data
Area (ft²) ....................................................... 9256.02 Weighted Runoff Coefficient ......................... 0.8100 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 7663.99 - 0.90
- 1591.99 - 0.40
Composite Area & Weighted Runoff Coeff. 9255.98 0.81
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.27 Peak Runoff (cfs) .......................................... 0.34 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8100 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 231 of 395 ends

Subbasin : DMA-05

Page 232 of 395 ends

Subbasin : DMA-06
Input Data
Area (ft²) ....................................................... 3504.00 Weighted Runoff Coefficient ......................... 0.8400 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 3098.99 - 0.90
- 405.02 - 0.40
Composite Area & Weighted Runoff Coeff. 3504.01 0.84
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.27 Peak Runoff (cfs) .......................................... 0.13 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8400 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 233 of 395 ends

Subbasin : DMA-06

Page 234 of 395 ends

Subbasin : DMA-07
Input Data
Area (ft²) ....................................................... 2326.02 Weighted Runoff Coefficient ......................... 0.6700 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 1252.00 - 0.90
- 1074.02 - 0.40
Composite Area & Weighted Runoff Coeff. 2326.02 0.67
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.22 Peak Runoff (cfs) .......................................... 0.07 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.6700 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 235 of 395 ends

Subbasin : DMA-07

Page 236 of 395 ends

Subbasin : DMA-08
Input Data
Area (ft²) ....................................................... 16462.98 Weighted Runoff Coefficient ......................... 0.7200 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 10378.00 - 0.90
- 6084.98 - 0.40
Composite Area & Weighted Runoff Coeff. 16462.98 0.72
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.24 Peak Runoff (cfs) .......................................... 0.53 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7200 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 237 of 395 ends

Subbasin : DMA-08

Page 238 of 395 ends

Subbasin : DMA-09
Input Data
Area (ft²) ....................................................... 4241.00 Weighted Runoff Coefficient ......................... 0.7100 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 2607.98 - 0.90
- 1633.02 - 0.40
Composite Area & Weighted Runoff Coeff. 4241.00 0.71
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.23 Peak Runoff (cfs) .......................................... 0.14 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7100 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 239 of 395 ends

Subbasin : DMA-09

Page 240 of 395 ends

Subbasin : DMA-10
Input Data
Area (ft²) ....................................................... 10803.01 Weighted Runoff Coefficient ......................... 0.6800 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 6065.99 - 0.90
- 4737.02 - 0.40
Composite Area & Weighted Runoff Coeff. 10803.01 0.68
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.22 Peak Runoff (cfs) .......................................... 0.33 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.6800 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 241 of 395 ends

Subbasin : DMA-10

Page 242 of 395 ends

Subbasin : DMA-11
Input Data
Area (ft²) ....................................................... 6849.98 Weighted Runoff Coefficient ......................... 0.8000 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 5485.99 - 0.90
- 1363.99 - 0.40
Composite Area & Weighted Runoff Coeff. 6849.98 0.80
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.26 Peak Runoff (cfs) .......................................... 0.25 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8000 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 243 of 395 ends

Subbasin : DMA-11

Page 244 of 395 ends

Subbasin : DMA-12
Input Data
Area (ft²) ....................................................... 2640.00 Weighted Runoff Coefficient ......................... 0.7600 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 1922.00 - 0.90
- 718.00 - 0.40
Composite Area & Weighted Runoff Coeff. 2640.00 0.76
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.25 Peak Runoff (cfs) .......................................... 0.09 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7600 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 245 of 395 ends

Subbasin : DMA-12

Page 246 of 395 ends

Subbasin : DMA-13
Input Data
Area (ft²) ....................................................... 58003.00 Weighted Runoff Coefficient ......................... 0.7900 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 45723.02 - 0.90
- 12280.00 - 0.40
Composite Area & Weighted Runoff Coeff. 58003.02 0.79
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.26 Peak Runoff (cfs) .......................................... 2.06 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.7900 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 247 of 395 ends

Subbasin : DMA-13

Page 248 of 395 ends

Subbasin : DMA-14
Input Data
Area (ft²) ....................................................... 53518.00 Weighted Runoff Coefficient ......................... 0.8400 Runoff Coefficient
Area Soil Runoff
Soil/Surface Description (ft²) Group Coeff.
- 47206.02 - 0.90
- 6312.02 - 0.40
Composite Area & Weighted Runoff Coeff. 53518.04 0.84
Subbasin Runoff Results
Total Rainfall (in) .......................................... 0.33 Total Runoff (in) ............................................ 0.27 Peak Runoff (cfs) .......................................... 2.02 Rainfall Intensity ........................................... 1.960 Weighted Runoff Coefficient ......................... 0.8400 Time of Concentration (days hh:mm:ss) ....... 0 00:10:00

Page 249 of 395 ends

Subbasin : DMA-14

Page 250 of 395 ends

Junction Input
SN Element Invert Ground/Rim Ground/Rim Initial Initial Surcharge Surcharge Ponded Minimum ID Elevation (Max) (Max) Water Water Elevation Depth Area Pipe Elevation Offset Elevation Depth Cover
(ft) (ft) (ft) (ft) (ft) (ft) (ft) (ft²) (in)
1 SD-01-MH 31.50 43.90 12.40 34.96 3.46 0.00 -43.90 0.00 0.00 2 SD-02-CO 36.09 40.00 3.91 34.96 -1.13 0.00 -40.00 0.00 0.00 3 SD-03-CB 38.24 40.83 2.59 34.96 -3.28 0.00 -40.83 0.00 0.00 4 SD-04-CO 36.92 41.00 4.08 34.96 -1.96 0.00 -41.00 0.00 0.00 5 SD-05-CB 37.34 42.46 5.12 34.96 -2.38 0.00 -42.46 0.00 0.00 6 SD-06-MH 37.71 43.96 6.25 34.96 -2.75 0.00 -43.96 0.00 0.00 7 SD-07-WYE 37.85 41.00 3.15 34.96 -2.89 0.00 -41.00 0.00 0.00 8 SD-08-CB 38.44 41.58 3.14 34.96 -3.48 0.00 -41.58 0.00 0.00 9 SD-09-CB 41.16 43.83 2.67 34.96 -6.20 0.00 -43.83 0.00 0.00 10 SD-10-CB 39.21 41.83 2.62 34.96 -4.25 0.00 -41.83 0.00 0.00 11 SD-11-WYE 34.29 39.50 5.21 34.96 0.67 6.00 -33.50 0.00 0.00 12 SD-12-CB 34.74 38.00 3.26 34.96 0.22 0.00 -38.00 0.00 0.00 13 SD-13-CB 35.72 38.83 3.11 34.96 -0.76 0.00 -38.83 0.00 0.00 14 SD-14-CB 34.76 38.13 3.37 34.96 0.20 0.00 -38.13 0.00 0.00 15 SD-15-MH 35.95 38.60 2.65 34.96 -0.99 0.00 -38.60 0.00 0.00 16 SD-16-CB 36.15 38.88 2.73 34.96 -1.19 0.00 -38.88 0.00 0.00 17 SD-17-CO 36.66 40.00 3.34 34.96 -1.70 0.00 -40.00 0.00 0.00 18 SD-18-CO 39.50 41.00 1.50 34.96 -4.54 0.00 -41.00 0.00 0.00 19 SD-19-CB 41.16 43.83 2.67 34.96 -6.20 0.00 -43.83 0.00 0.00 20 SD-20-MH 37.27 39.77 2.50 34.96 -2.31 0.00 -39.77 0.00 0.00 21 SD-21-CO 38.51 42.00 3.49 34.96 -3.55 0.00 -42.00 0.00 0.00 22 SD-22-CO 39.54 42.00 2.46 34.96 -4.58 0.00 -42.00 0.00 0.00 23 SD-23-CO 40.58 42.50 1.92 34.96 -5.62 0.00 -42.50 0.00 0.00 24 SD-24-CB 40.74 43.33 2.59 34.96 -5.78 0.00 -43.33 0.00 0.00 25 SD-25-MH 30.71 42.70 11.99 34.96 4.25 0.00 -42.70 0.00 0.00

Page 251 of 395 ends

Junction Results
SN Element Peak Peak Max HGL Max HGL Max Min Average HGL Average HGL Time of Time of Total Total Time ID Inflow Lateral Elevation Depth Surcharge Freeboard Elevation Depth Max HGL Peak Flooded Flooded Inflow Attained Attained Depth Attained Attained Attained Occurrence Flooding Volume Attained Occurrence
(cfs) (cfs) (ft) (ft) (ft) (ft) (ft) (ft) (days hh:mm) (days hh:mm) (ac-in) (min) 1 SD-01-MH 0.61 0.00 34.96 3.46 0.00 8.94 34.96 3.46 0 00:10 0 00:00 0.00 0.00 2 SD-02-CO 0.92 0.00 36.55 0.46 0.00 3.45 36.14 0.05 0 00:12 0 00:00 0.00 0.00 3 SD-03-CB 0.15 0.00 38.36 0.12 0.00 2.47 38.26 0.02 0 00:11 0 00:00 0.00 0.00 4 SD-04-CO 0.81 0.00 37.31 0.39 0.00 3.69 36.96 0.04 0 00:12 0 00:00 0.00 0.00 5 SD-05-CB 0.30 0.00 37.59 0.25 0.00 4.87 37.37 0.03 0 00:11 0 00:00 0.00 0.00 6 SD-06-MH 0.51 0.00 38.00 0.29 0.00 5.96 37.74 0.03 0 00:12 0 00:00 0.00 0.00 7 SD-07-WYE 0.51 0.00 38.22 0.37 0.00 2.78 37.89 0.04 0 00:11 0 00:00 0.00 0.00 8 SD-08-CB 0.29 0.00 38.71 0.27 0.00 2.87 38.47 0.03 0 00:11 0 00:00 0.00 0.00 9 SD-09-CB 0.22 0.00 41.30 0.14 0.00 2.53 41.17 0.01 0 00:11 0 00:00 0.00 0.00 10 SD-10-CB 0.61 0.00 39.65 0.44 0.00 2.18 39.26 0.05 0 00:11 0 00:00 0.00 0.00 11 SD-11-WYE 1.42 0.00 35.35 1.06 0.00 4.15 34.98 0.69 0 00:12 0 00:00 0.00 0.00 12 SD-12-CB 0.13 0.00 35.36 0.62 0.00 2.64 34.98 0.24 0 00:12 0 00:00 0.00 0.00 13 SD-13-CB 0.13 0.00 35.87 0.15 0.00 2.96 35.73 0.01 0 00:11 0 00:00 0.00 0.00 14 SD-14-CB 1.31 0.00 35.72 0.96 0.00 2.41 34.99 0.23 0 00:12 0 00:00 0.00 0.00 15 SD-15-MH 1.03 0.00 36.33 0.38 0.00 2.27 35.99 0.04 0 00:12 0 00:00 0.00 0.00 16 SD-16-CB 0.73 0.00 36.62 0.47 0.00 2.26 36.20 0.05 0 00:12 0 00:00 0.00 0.00 17 SD-17-CO 0.27 0.00 36.91 0.25 0.00 3.09 36.69 0.03 0 00:11 0 00:00 0.00 0.00 18 SD-18-CO 0.27 0.00 39.68 0.18 0.00 1.32 39.52 0.02 0 00:11 0 00:00 0.00 0.00 19 SD-19-CB 0.27 0.00 41.32 0.16 0.00 2.51 41.18 0.02 0 00:11 0 00:00 0.00 0.00 20 SD-20-MH 0.31 0.00 37.57 0.30 0.00 2.20 37.30 0.03 0 00:12 0 00:00 0.00 0.00 21 SD-21-CO 0.31 0.00 38.68 0.17 0.00 3.32 38.53 0.02 0 00:12 0 00:00 0.00 0.00 22 SD-22-CO 0.31 0.07 39.85 0.31 0.00 2.15 39.57 0.03 0 00:12 0 00:00 0.00 0.00 23 SD-23-CO 0.26 0.00 40.83 0.25 0.00 1.67 40.61 0.03 0 00:11 0 00:00 0.00 0.00 24 SD-24-CB 0.26 0.00 41.03 0.29 0.00 2.30 40.77 0.03 0 00:11 0 00:00 0.00 0.00 25 SD-25-MH 1.52 0.00 34.96 4.25 0.00 7.74 34.96 4.25 0 00:12 0 00:00 0.00 0.00

Page 252 of 395 ends

Pipe Input
SN Element Length Inlet Inlet Outlet Outlet Total Average Pipe Pipe Pipe Manning's Entrance Exit/Bend Additional Initial Flap No. of ID Invert Invert Invert Invert Drop Slope Shape Diameter or Width Roughness Losses Losses Losses Flow Gate Barrels Elevation Offset Elevation Offset Height
(ft) (ft) (ft) (ft) (ft) (ft) (%) (in) (in) (cfs)
1 PIPE-01 84.91 31.50 0.00 30.71 0.00 0.79 0.9300 CIRCULAR 42.000 42.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1 2 PIPE-02 13.67 39.21 0.00 39.07 7.57 0.14 1.0200 CIRCULAR 8.040 8.040 0.0150 0.5000 0.5000 0.0000 0.00 No 1 3 PIPE-03 29.15 36.09 0.00 35.79 5.08 0.30 1.0300 CIRCULAR 9.960 9.960 0.0150 0.5000 0.5000 0.0000 0.00 No 1 4 PIPE-04 55.79 38.24 0.00 36.26 0.17 1.98 3.5500 CIRCULAR 6.000 6.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1 5 PIPE-05 82.83 36.92 0.00 36.09 0.00 0.83 1.0000 CIRCULAR 9.960 9.960 0.0150 0.5000 0.5000 0.0000 0.00 No 1 6 PIPE-06 7.88 37.34 0.00 37.09 0.17 0.25 3.1700 CIRCULAR 6.000 6.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1 7 PIPE-07 79.55 37.71 0.00 36.92 0.00 0.79 0.9900 CIRCULAR 9.960 9.960 0.0150 0.5000 0.5000 0.0000 0.00 No 1 8 PIPE-08 13.48 37.85 0.00 37.71 0.00 0.14 1.0400 CIRCULAR 8.040 8.040 0.0150 0.5000 0.5000 0.0000 0.00 No 1 9 PIPE-09 29.27 38.44 0.00 38.02 0.17 0.42 1.4300 CIRCULAR 6.000 6.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1 10 PIPE-10 63.76 38.49 -2.67 37.85 0.00 0.64 1.0000 CIRCULAR 8.040 8.040 0.0150 0.5000 0.5000 0.0000 0.00 No 1 11 PIPE-11 8.16 34.29 0.00 33.96 0.00 0.33 4.0400 CIRCULAR 8.040 8.040 0.0140 0.5000 0.5000 0.0000 0.00 No 1 12 PIPE-12 14.07 34.74 0.00 34.46 0.17 0.28 1.9900 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 13 PIPE-13 64.24 35.72 0.00 34.74 0.00 0.98 1.5300 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 14 PIPE-14 11.43 34.76 0.00 34.29 0.00 0.47 4.1100 CIRCULAR 8.040 8.040 0.0140 0.5000 0.5000 0.0000 0.00 No 1 15 PIPE-15 31.58 35.95 0.00 34.76 0.00 1.19 3.7700 CIRCULAR 8.040 8.040 0.0140 0.5000 0.5000 0.0000 0.00 No 1 16 PIPE-16 20.42 36.15 0.00 35.95 0.00 0.20 0.9800 CIRCULAR 8.040 8.040 0.0140 0.5000 0.5000 0.0000 0.00 No 1 17 PIPE-17 44.95 36.66 0.00 36.15 0.00 0.51 1.1300 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 18 PIPE-18 77.91 39.50 0.00 36.66 0.00 2.84 3.6500 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 19 PIPE-19 24.84 41.16 0.00 39.50 0.00 1.66 6.6800 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 20 PIPE-20 58.89 37.27 0.00 36.68 0.73 0.59 1.0000 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 21 PIPE-21 21.24 38.51 0.00 37.27 0.00 1.24 5.8400 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 22 PIPE-22 103.75 39.54 0.00 38.51 0.00 1.03 0.9900 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 23 PIPE-23 103.83 40.58 0.00 39.54 0.00 1.04 1.0000 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 24 PIPE-24 16.21 40.74 0.00 40.58 0.00 0.16 0.9900 CIRCULAR 6.000 6.000 0.0140 0.5000 0.5000 0.0000 0.00 No 1 25 PIPE-25 3.22 30.71 0.00 30.71 0.00 0.00 0.0000 Dummy 0.000 0.000 0.0150 0.5000 0.5000 0.0000 0.00 No 1

Page 253 of 395 ends

Pipe Results
SN Element Peak Time of Design Flow Peak Flow/ Peak Flow Travel Peak Flow Peak Flow Total Time Froude Reported ID Flow Peak Flow Capacity Design Flow Velocity Time Depth Depth/ Surcharged Number Condition Occurrence Ratio Total Depth
Ratio
(cfs) (days hh:mm) (cfs) (ft/sec) (min) (ft) (min)
1 PIPE-01 0.61 0 00:11 84.11 0.01 0.06 23.59 3.48 0.99 0.00 Calculated 2 PIPE-02 0.61 0 00:12 1.06 0.57 2.77 0.08 0.40 0.60 0.00 Calculated 3 PIPE-03 0.92 0 00:12 1.93 0.48 3.18 0.15 0.43 0.52 0.00 Calculated 4 PIPE-04 0.12 0 00:11 0.92 0.13 2.76 0.34 0.21 0.41 0.00 Calculated 5 PIPE-05 0.80 0 00:12 1.90 0.42 2.87 0.48 0.43 0.51 0.00 Calculated 6 PIPE-06 0.30 0 00:11 0.87 0.35 3.43 0.04 0.24 0.47 0.00 Calculated 7 PIPE-07 0.51 0 00:12 1.89 0.27 2.40 0.55 0.34 0.41 0.00 Calculated 8 PIPE-08 0.51 0 00:11 1.07 0.48 2.92 0.08 0.33 0.50 0.00 Calculated 9 PIPE-09 0.29 0 00:11 0.58 0.50 2.80 0.17 0.26 0.53 0.00 Calculated 10 PIPE-10 0.22 0 00:11 2.39 0.09 1.80 0.59 0.25 0.38 0.00 Calculated 11 PIPE-11 1.42 0 00:12 2.26 0.63 4.08 0.03 0.67 1.00 180.00 SURCHARGED 12 PIPE-12 0.13 0 00:11 0.74 0.17 0.64 0.37 0.50 1.00 5.00 SURCHARGED 13 PIPE-13 0.13 0 00:11 0.64 0.20 1.00 1.07 0.33 0.65 0.00 Calculated 14 PIPE-14 1.31 0 00:12 2.28 0.57 3.75 0.05 0.67 1.00 6.00 SURCHARGED 15 PIPE-15 1.03 0 00:12 2.18 0.47 3.65 0.14 0.52 0.78 0.00 Calculated 16 PIPE-16 0.73 0 00:12 1.11 0.65 3.43 0.10 0.42 0.63 0.00 Calculated 17 PIPE-17 0.27 0 00:11 0.55 0.49 1.84 0.41 0.36 0.71 0.00 Calculated 18 PIPE-18 0.27 0 00:11 0.99 0.28 3.46 0.38 0.21 0.43 0.00 Calculated 19 PIPE-19 0.27 0 00:11 1.35 0.20 4.67 0.09 0.17 0.34 0.00 Calculated 20 PIPE-20 0.31 0 00:12 0.52 0.59 2.66 0.37 0.29 0.57 0.00 Calculated 21 PIPE-21 0.31 0 00:12 1.26 0.25 3.51 0.10 0.23 0.47 0.00 Calculated 22 PIPE-22 0.31 0 00:12 0.52 0.60 3.34 0.52 0.24 0.48 0.00 Calculated 23 PIPE-23 0.25 0 00:11 0.52 0.49 2.28 0.76 0.28 0.56 0.00 Calculated 24 PIPE-24 0.26 0 00:11 0.52 0.50 2.43 0.11 0.27 0.53 0.00 Calculated 25 PIPE-25 1.52 0 00:12 0.00 0.50 0.00 0.27 0.53 0.00 Calculated

Page 254 of 395 ends

Storage Nodes
Storage Node : BMP-01
Input Data

42.83 43.50

0.67 43.33

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-01
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 254 0.000

0.67 409 222.11
Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Page 255 of 395 ends
Page 256 of 395 ends

Storage Node : BMP-01 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-01 Bottom Rectangular No 12.00 12.00 43.33 0.63 Output Summary Results

0.28 0.28

0.26 0.00

43.40 0.57

43.34 0.51
0 00:11

0.000
0 0

0.00 Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Page 257 of 395 ends

Storage Node : BMP-10
Input Data

37.63 38.30

0.67 38.13

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-10
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 265 0.000

0.67 427 231.82
Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Page 258 of 395 ends
Page 259 of 395 ends

Storage Node : BMP-10 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-10 Bottom Rectangular No 12.00 12.00 38.13 0.63 Output Summary Results

0.33 0.33

0.30 0.00

38.21 0.58

38.14 0.51
0 00:11

0.000
0 0

0.00 Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Page 260 of 395 ends

Storage Node : BMP-11
Input Data

43.33 44.00

0.67 43.83

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-11
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 316 0.000

0.67 487 269.01
Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Page 261 of 395 ends
Page 262 of 395 ends

Storage Node : BMP-11 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-11 Bottom Rectangular No 12.00 12.00 43.83 0.63 Output Summary Results

0.25 0.25

0.22 0.00

43.89 0.56

43.84 0.51
0 00:11

0.000
0 0

0.00 Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Peak Inflow (cfs) ....................................................................

Page 263 of 395 ends

Storage Node : BMP-2
Input Data

41.33 42.00

0.67 41.83

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-02
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 671 0.000

0.67 920 532.99
Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Page 264 of 395 ends
Page 265 of 395 ends

Storage Node : BMP-2 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-02 Bottom Rectangular No 12.00 12.00 41.83 0.63 Output Summary Results

0.73 0.73

0.61 0.00

41.96 0.63

41.84 0.51
0 00:11

0.000
0 0

0.00 Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Page 266 of 395 ends

Storage Node : BMP-3
Input Data

43.33 44.00

0.67 43.83

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-03
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 278 0.000

0.67 483 254.94
Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Page 267 of 395 ends
Page 268 of 395 ends

Storage Node : BMP-3 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-03 Bottom Rectangular No 12.00 12.00 43.83 0.63 Output Summary Results

0.31 0.31

0.27 0.00

43.91 0.58

43.84 0.51
0 00:11

0.000
0 0

0.00 Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Page 269 of 395 ends

Storage Node : BMP-4
Input Data

41.08 41.75

0.67 41.58

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-04
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 278 0.000

0.67 464 248.57
Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Page 270 of 395 ends
Page 271 of 395 ends

Storage Node : BMP-4 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-04 Bottom Rectangular No 12.00 12.00 41.58 0.63 Output Summary Results

0.32 0.32

0.29 0.00

41.66 0.58

41.59 0.51
0 00:11

0.000
0 0

0.00 Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Peak Inflow (cfs) ....................................................................

Page 272 of 395 ends

Storage Node : BMP-5
Input Data

41.96 42.63

0.67 42.46

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-05
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 320 0.000

0.67 529 284.42
Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Page 273 of 395 ends
Page 274 of 395 ends

Storage Node : BMP-5 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-05 Bottom Rectangular No 12.00 12.00 42.46 0.63 Output Summary Results

0.34 0.34

0.30 0.00

42.54 0.58

42.47 0.51
0 00:11

0.000
0 0

0.00 Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Page 275 of 395 ends

Storage Node : BMP-6
Input Data

40.33 41.00

0.67 40.88

0.55 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-06
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 137 0.000

0.67 257 131.99
Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Page 276 of 395 ends
Page 277 of 395 ends

Storage Node : BMP-6 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-06 Bottom Rectangular No 12.00 12.00 40.83 0.63 Output Summary Results

0.13 0.13

0.15 0.00

40.88 0.55

40.83 0.5
0 00:00

0.000
0 0

0.00 Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Page 278 of 395 ends

Storage Node : BMP-8
Input Data

38.38 39.05

0.67 38.88

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-08
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 465 0.000

0.67 708 392.96
Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Page 279 of 395 ends
Page 280 of 395 ends

Storage Node : BMP-8 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-08 Bottom Rectangular No 12.00 12.00 38.88 0.63 Output Summary Results

0.53 0.53

0.46 0.00

38.99 0.61

38.89 0.51
0 00:11

0.000
0 0

0.00 Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Peak Inflow (cfs) ....................................................................

Page 281 of 395 ends

Storage Node : BMP-9
Input Data

38.33 39.00

0.67 38.83

0.50 0.00

0.00 Storage Area Volume Curves
Storage Curve : BMP-09
Stage Storage Storage
Area Volume
(ft) (ft²) (ft³)
0 111 0.000

0.67 234 115.58
Evaporation Loss ...................................................................

Invert Elevation (ft) ................................................................

Max (Rim) Elevation (ft) .........................................................

Max (Rim) Offset (ft) ..............................................................

Initial Water Elevation (ft) ......................................................

Initial Water Depth (ft) ...........................................................

Ponded Area (ft²) ...................................................................

Page 282 of 395 ends
Page 283 of 395 ends

Storage Node : BMP-9 (continued)
Outflow Orifices
SN Element Orifice Orifice Flap Circular Rectangular Rectangular Orifice Orifice ID Type Shape Gate Orifice Orifice Orifice Invert Coefficient Diameter Height Width Elevation
(in) (in) (in) (ft)
1 OVERFLOW-09 Bottom Rectangular No 12.00 12.00 38.83 0.63 Output Summary Results

0.14 0.14

0.13 0.00

38.88 0.55

38.83 0.5
0 00:10

0.000
0 0

0.00 Total Time Flooded (min) ......................................................

Total Retention Time (sec) ....................................................

Max HGL Depth Attained (ft) .................................................

Average HGL Elevation Attained (ft) .....................................

Average HGL Depth Attained (ft) ...........................................

Time of Max HGL Occurrence (days hh:mm) ........................

Total Exfiltration Volume (1000-ft³) ........................................

Total Flooded Volume (ac-in) ................................................

Peak Inflow (cfs) ....................................................................

Peak Lateral Inflow (cfs) ........................................................

Peak Outflow (cfs) .................................................................

Peak Exfiltration Flow Rate (cfm) ..........................................

Max HGL Elevation Attained (ft) ............................................

Page 284 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 15 of 16 March 12, 2021

APPENDIX I
Utility Plan

Page 285 of 395 ends

Architects1288 Kifer Road, Unit 206,Sunnyvale, CA 94086Telephone : 408-992-0280Fax : 408-992-0281build on.sandis.net

Page 286 of 395 ends

Architects1288 Kifer Road, Unit 206,Sunnyvale, CA 94086Telephone : 408-992-0280Fax : 408-992-0281build on.sandis.net

Page 287 of 395 ends

Sunnyhills Apartments – Milpitas, CA Page 16 of 16 March 12, 2021

APPENDIX J
City of Milpitas Engineering Guidelines XIII

Page 288 of 395 ends
Page 289 of 395 ends
Page 290 of 395 ends
Page 291 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Approve Final Map and Authorize the City Manager to Execute the Subdivision Improvement Agreement with Toll West Coast, LLC for a Residential Project at 612 South Main Street (Staff Contact: Christian Di Renzo, Public Works Director, 408-586-2602; and Michael Silveira, City Engineer, 408-586-3303) Category: Consent Calendar-Community Development
Meeting Date: 1/7/2025
Recommendation: (1) Approve the Final Map, Tract No. 10626, including all offers of dedications as stated and depicted upon completion and acceptance of improvements; and (2) Approve and authorize the City Manager to execute the Subdivision Improvement Agreement between the City of Milpitas and Toll West Coast, LLC., for a residential project at 612 South Main Street.

BACKGROUND:

On April 4, 2023, the City Council approved a Site Development Permit No. SD22-0007, Conditional Use Permit No. UP22-0003, Vesting Tentative Map No. MT22-0003, and Environmental Assessment No. EA22- 0005 to construct a 57-unit townhome-style condominium subdivision comprised of nine multi-family residential buildings up to 37 feet in height (three stories), with 123 vehicle parking spaces and associated site improvements, located on a 2.35 acre site at 612 South Main Street (Project) by Toll West Coast, LLC (Developer).

ANALYSIS:

The Final Map, Tract No. 10626, for the Project is now complete and ready for approval by the City Council.

The City Engineer has examined the Final Map and determined it is substantially in conformance with the approved Vesting Tentative Map and finds that it conforms to all requirements of the State of California Subdivision Map Act and Milpitas Municipal Code, and the terms and conditions of the Vesting Tentative Map.

The Developer has offered required dedications to the City for public use, including easements for streets, services and utilities, and emergency vehicle access purposes, as depicted on the Final Map. Staff recommends the City Council approve the Final Map and accept the dedications, subject to completion and acceptance of public improvements to be installed by the Developer.

The Developer has agreed to enter into a Subdivision Improvement Agreement (SIA) with the City for the construction of off-site public improvements for the Project which will be completed with the on-site work. The public improvements will be accepted by the City after final map approval and completion of construction. Off- site public improvements to be constructed and accepted by the City include asphalt concrete pavement improvements, concrete improvements including driveway approaches, curb and gutter and sidewalk, landscaping and irrigation, signing and striping, street lights, undergrounding of existing overhead utilities, utility mains and services, and other miscellaneous items of work identified on the improvement plans. The improvements will be completed within one year from the date of the SIA, and the work is guaranteed by bonds or similar securities to be posted by the Developer in the amount of $986,000.00.

The City Engineer has reviewed the public improvement plans (2-1461) and is recommending the City Council approve the Subdivision Improvement Agreement to allow for the construction of public improvements after final map approval.

The parcels associated with the Final Map are subject to annexation into the Community Facilities District No. 2005-1 (CFD 2005-1 Annexation No. 25) and will be brought to City Council for consideration at the same meeting of January 7, 2025.

Page 292 of 395 ends

POLICY ALTERNATIVE(S):

Alternative: Deny approval of Final Map and Subdivision Improvement Agreement.

Pros: None
Cons: The denial of approval of the Final Map and Subdivision Improvement Agreement will cause the parcels to remain vacant and undeveloped. The City would not benefit from the addition of 57 new townhome-style condominiums to its property tax revenues.

Reason for Not Recommending: Staff recommends approval of Final Map and Subdivision Improvement Agreement to allow the Development to move forward.

FISCAL IMPACT:

The Developer reimbursed the City for costs associated with plan review, permitting and construction inspection for off-site public improvements constructed by the Developer. The City will have perpetual ownership and maintenance responsibilities for the improvements following construction and acceptance after the one year warranty period has expired. The Public Works Department provides funding for future maintenance of newly accepted City infrastructure through their operating budget and subject to annual appropriations.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

This project is covered under the scope of activities approved under the Midtown Specific Plan Environmental Impact Report, SCH2000092027, which was certified by City Council on March 19, 2002. On April 4, 2023, the City Council found that the project is exempt from further environmental review pursuant to CEQA Guidelines Section 15332 (In-fill Development Projects) in that the Project is consistent with the General Plan and zoning designation while invoking the State Density Bonus Law waivers from development standards and reduced parking requirements, is located in an urban area that has either been previously developed or adjoins existing qualified urban uses on all of the site’s perimeter and is under five-acres in size, has no value to endangered, rare, or threatened species, would not result in any significant effects related to traffic, noise, air quality, or water quality, and the site can be adequately served by all required utilities and public services.

As a separate and independent basis, the Project is also exempt from further environmental review pursuant to CEQA Guidelines Section 15168 (Program EIR) per the Midtown Specific Plan EIR (SCH2000092027) RECOMMENDATION:
(1) Approve the Final Map, Tract No. 10626, including all offers of dedications as stated and depicted upon completion and acceptance of improvements.
(2) Approve and authorize the City Manager to execute the Subdivision Improvement Agreement between the City of Milpitas and Toll West Coast, LLC.

ATTACHMENT(S):
(a) Final Map, Tract No. 10626
(b) Subdivision Improvement Agreement

Page 293 of 395 ends

OWNER'S ACKNOWLEDGMENT:A NOTARY PUBLIC OR OTHER OFFICER COMPLETING THIS CERTIFICATE VERIFIES ONLY THE IDENTITY OF THE INDIVIDUAL WHOSIGNED THE DOCUMENT TO WHICH THIS CERTIFICATE IS ATTACHED, AND NOT THE TRUTHFULNESS, ACCURACY, OR VALIDITY OFTHAT DOCUMENT.STATE OF CALIFORNIA COUNTY OF )ON , 2025, BEFORE ME , A NOTARY PUBLIC, PERSONALLYAPPEARED WHO PROVED TO ME ONTHE BASIS OF SATISFACTORY EVIDENCE TO BE THE PERSON(S) WHOSE NAME(S) IS/ARE SUBSCRIBED TO THE WITHIN INSTRUMENTAND ACKNOWLEDGED TO ME THAT HE/SHE/THEY EXECUTED THE SAME IN HIS/HER/THEIR AUTHORIZED CAPACITY(IES), AND THAT BYHIS/HER/THEIR SIGNATURE(S) ON THE INSTRUMENT THE PERSON(S), OR THE ENTITY UPON BEHALF OF WHICH THE PERSON(S)ACTED, EXECUTED THE INSTRUMENT.I CERTIFY UNDER PENALTY OF PERJURY UNDER THE LAWS OF THE STATE OF CALIFORNIA THAT THE FOREGOING PARAGRAPH ISTRUE AND CORRECT.WITNESS MY HAND:SIGNATURE: PRINTED NAME, NOTARY PUBLIC IN AND FOR SAID COUNTY AND STATEPRINCIPAL PLACE OF BUSINESS: COMMISSION EXPIRES: COMMISSION # OF NOTARY: SOILS REPORT NOTE:GEOTECHNICAL EXPLORATION, DATED FEBRUARY 23, 2024, HAS BEEN PREPARED BY ENGEO INCORPORATED, JOB NO.23358.000.002 "SOUTH MAIN STREET DEVELOPMENT", PREPARED BY TANIA ZAKARIA, SEEMA BARUA, PE 87585, ANDTHEODORE P. BAYHAM, CEG, GE 2480 FOR THIS SUBDIVISION AND ARE ON FILE WITH THE CITY OF MILPITAS.

DECEMBER 2024CONSISTING OF 4 SHEETSFOR CONDOMINIUM PURPOSESBEING A SUBDIVISION OF PARCELS 1 AND 2OF PARCEL MAP, RECORDED IN BOOK 400 OFPARCEL MAPS, AT PAGE 39SANTA CLARA COUNTY RECORDS,MILPITAS, SANTA CLARA COUNTY,CALIFORNIATRACT 10626 NTSVICINITY MAP PARKWAYSOUTH ABEL STREETHAMMOND WAYCURTIS AVENUESITESOUTH MAIN STREETGREAT MALLOWNER'S STATEMENT:WE HEREBY STATE THAT WE ARE THE OWNERS OF OR HAVE SOME RIGHT, TITLE, OR INTEREST IN AND TO THE REALPROPERTY INCLUDED WITHIN THE SUBDIVISION SHOWN HEREON; THAT WE ARE THE ONLY PERSONS WHOSE CONSENT ISNECESSARY TO PASS A CLEAR TITLE TO SAID REAL PROPERTY; THAT WE CONSENT TO THE MAKING AND RECORDING OFTHIS SUBDIVISION MAP AS SHOWN WITHIN THE DISTINCTIVE BOUNDARY LINE.WE HEREBY OFFER FOR DEDICATION TO CITY OF MILPITAS FOR PUBLIC USE FOR OPERATION, ALTERATION, RELOCATION,MAINTENANCE, REPAIR AND REPLACEMENT OF ALL PUBLIC SERVICE FACILITIES AND THEIR APPURTENANCES, OVER,UNDER, ALONG AND ACROSS THE FOLLOWING:1.EASEMENTS FOR PUBLIC SERVICE AND UTILITY EASEMENT PURPOSES (PSUE).2.EASEMENTS FOR EMERGENCY VEHICLE ACCESS PURPOSES (EVAE).THE ABOVE MENTIONED EASEMENTS (PSUE, EVAE) SHALL REMAIN OPEN AND FREE FROM BUILDINGS AND STRUCTURES OFANY KIND EXCEPT PUBLIC SERVICE AND PUBLIC UTILITY STRUCTURES AND THEIR APPURTENANCES, IRRIGATION SYSTEMSAND THEIR APPURTENANCES AND LAWFUL FENCES. UNOBSTRUCTED CONTINUOUS ACCESS SHALL BE MAINTAINED AT ALLTIMES.WE ALSO HEREBY RETAIN FOR THE PRIVATE USE OF THE CONDOMINIUM OWNERS WITHIN THIS SUBDIVISION, THEIRLICENSES, VISITORS AND TENANTS WITH MAINTENANCE THEREOF BY THEIR LOT OWNERS THE FOLLOWING:1.PARCELS A, B AND D THROUGH G FOR PRIVATE STREET PURPOSES.2.PARCEL C, FOR PRIVATE OPEN SPACES PURPOSES (OS).THE DESIGNATED PRIVATE STREETS ON THIS MAP ARE NOT PART OF THE CITY OF MILPITAS STREET SYSTEM ANDARE NOT ACCEPTED FOR PUBLIC MAINTENANCE.THERE ARE EXISTING PUBLIC STORM DRAIN UTILITIES WITHIN THE EXISTING STORM DRAIN EASEMENT. ALL OTHER STORMDRAIN UTILITIES WITHIN THE DISTINCTIVE BOUNDARY LINE OF THIS MAP ARE PRIVATELY OWNED AND MAINTAINED BY THEHOMEOWNER'S ASSOCIATION. ALL DRY UTILITIES (GAS, ELECTRIC, TELEPHONE, CABLE, ETC.) ARE OWNED AND MAINTAINEDBY THE RESPECTIVE UTILITY COMPANY.THIS MAP SHOWS ALL EASEMENTS OF RECORD ON THE PREMISES.OWNER: TOLL WEST COAST LLC, A DELAWARE LIMITED LIABILITY COMPANYPRINTED NAME: SIGNATURE: TITLE: DATE: CITY CLERK'S CERTIFICATE:I, SUZANNE GUZZETTA, CITY CLERK OF THE CITY OF MILPITAS, CALIFORNIA, HEREBY CERTIFY THAT SAID CITY COUNCIL, ASGOVERNING BODY OF SAID CITY AT A REGULAR MEETING HELD ON _____________, 2024, HAS TAKEN THE FOLLOWINGACTIONS:1.APPROVED THIS TRACT MAP NO. 10626.2.ACCEPTED, SUBJECT TO IMPROVEMENT, ON BEHALF OF THE PUBLIC THOSE PARCELS OF LAND OFFERED FORDEDICATION FOR PUBLIC USE IN CONFORMITY WITH THE TERMS OF OFFER OF DEDICATION TO WIT:A.EASEMENTS FOR PUBLIC SERVICE AND UTILITY EASEMENT PURPOSES (PSUE).B. EASEMENTS FOR EMERGENCY VEHICLE ACCESS PURPOSES (EVAE).DATED: _____________ _______________________________ SUZANNE GUZZETTA CITY CLERK, CITY OF MILPITASCOUNTY RECORDER'S STATEMENT:FILE NO. FEE $ PAID. ACCEPTED FOR RECORD AND FILED IN BOOK OF MAPSAT PAGES , SANTA CLARA COUNTY RECORDS, THIS _______ DAY OF ___________, 20___ AT ______M., AT THEREQUEST OF FIRST AMERICAN TITLE INSURANCE COMPANY.REGINA ALCOMENDRAS, RECORDERSANTA CLARA COUNTY, CALIFORNIABY:________________________________DEPUTYSURVEYOR'S STATEMENT:THIS MAP WAS PREPARED BY ME OR UNDER MY DIRECTION AND IS BASED UPON A FIELD SURVEY IN CONFORMANCE WITH THEREQUIREMENTS OF THE SUBDIVISION MAP ACT AT THE REQUEST OF TOLL BROTHERS, LLC IN DECEMBER OF 2023. I HEREBYSTATE THAT THIS FINAL MAP COMPLIES WITH FINAL MAP PROCEDURES OF THE CITY OF MILPITAS AND THAT THIS FINAL MAPCONFORMS TO THE APPROVED TENTATIVE MAP AND THE CONDITIONS OF APPROVAL THEREOF WHICH WERE REQUIRED TO BEFULFILLED PRIOR TO THE FILING OF THE FINAL MAP AND IT IS TECHNICALLY CORRECT. DATE: , 2025IAN BRUCE MACDONALDLS NO. 8817 CITY ENGINEER'S STATEMENT:I HEREBY STATE THAT I HAVE EXAMINED THE HEREIN MAP; THAT THE SUBDIVISION AS SHOWN THEREIN ISSUBSTANTIALLY THE SAME AS IT APPEARED ON THE TENTATIVE MAP AND ANY APPROVED ALTERATIONS THEREOF; THATTHIS SUBDIVISION COMPLIES WITH PROVISIONS OF THE SUBDIVISION MAP ACT AND LOCAL ORDINANCES, APPLICABLE ATTHE TIME OF APPROVAL OF THE TENTATIVE MAP.DATE: , 2025MICHAEL SILVEIRA, RCE 83869, CITY ENGINEERCITY OF MILPITAS, SANTA CLARA COUNTY, CALIFORNIACITY SURVEYOR'S STATEMENT:I HEREBY STATE THAT I HAVE EXAMINED THE HEREIN MAP AND THAT I AM SATISFIED THAT SAID MAP IS TECHNICALLYCORRECT.DATE: , 2025DEAN A. JURADO, PLS 9032, CITY SURVEYORCITY OF MILPITAS, SANTA CLARA COUNTY, CALIFORNIAKIER & WRIGHT

Page 294 of 395 ends

PARCEL DPARCEL A 63 PARCEL B1 42
87 9
5PARCEL C

PARCEL FPARCEL E PARCEL G
BASIS OF BEARINGSFOUND 3/4" IPBENT/DISTURBED LOCATED AT BASEN66°32'55"W 0.92'FROM PROPERTY CORNERFD 3/4" IP,W/ TACK, NO TAGFD 3/4" OPEN IP,NO CAPSNFSNFSNFSNFSNFSNFSNFSNFSNF33'33'R=2573.00'Δ=7°29'34"L=336.48'(R=2561.91'L=335.03'(R-1)(R-2))N76°23'58"E(R)FD 3/4" OPEN IP,NO CAP N78°30'00"E 202.69' BNDY(252.64' (R-1))N11°30'00"W 502.25' BNDY (502.20' (R-1)(R-2))N11°18'15"W 399.85' BNDY(401.26' (R-1)(R-2))Δ=2°17'47" L=103.12'(Δ=2°16'25"L=101.66' (R-1))N18°47'49"W 496.76' (496.75' (R-2))78.52'(78.51' (R-2))156.00' (R-2)190.79' (R-1)71.45' (R-1)N67°24'51"E45.09' (R-1)(262.24' (R-1))100' EX. PSUEBK D878 PG 729139.34' EX. SDE BK C972 PG 21310' EX. PSUEBK I625 PG 536N11°18'15"W 393.74'(393.75' (R-2))249.11'(250.57' (R-1))150.74'(150.69' (R-1))10' EX. SDEBK C972 PG 213N78°41'45"E 203.03' BNDY(202.94' (R-1)(R-2))150.05' (150.00' (R-1))352.20' (R-1)N11°18'15"W 399.85' (401.26' (R-1)(R-2))N78°30'00"E 50.00'(R-1)(R-2)N11°30'00"W 709.84' (R-1)N78°30'00"E 224.50' (R-1)81.99' (R-1)33'N18°47'49"W 379.64' M-M (379.66' (R-1)(R-2))R=4011.14'Δ=7°29'34"L=524.55'(R=4000.00'L=523.09'(R-1)(R-2))Δ=5°11'47"L=233.36'(Δ=5°13'09"L=233.37'(R-1))SNF297.65' (297.67' (R-1))PROPERTY LINE TO BE REMOVEDWITH THIS FINAL MAP10' EX. SDEBK I625 PG 532FD 3/4" OPEN IP,NO CAP DECEMBER 2024CONSISTING OF 4 SHEETSFOR CONDOMINIUM PURPOSESBEING A SUBDIVISION OF PARCELS 1 AND 2OF PARCEL MAP, RECORDED IN BOOK 400 OFPARCEL MAPS, AT PAGE 39SANTA CLARA COUNTY RECORDS,MILPITAS, SANTA CLARA COUNTY,CALIFORNIATRACT 10626

Page 295 of 395 ends

N11°30'00"W 140.12'(T)-N11°30'00"W 142.73'(T)-N11°30'00"W 244.95'(T) PARCEL DPARCEL A 63 PARCEL B1 42
87 9
5PARCEL C

PARCEL FPARCEL E PARCEL G
33'33'N76°23'58"E(R)N78°30'00"E 202.69' BNDYN11°30'00"W 502.25' BNDYN11°18'15"W 399.85' BNDYR=2573.00'Δ=2°17'47"L=103.12'BNDYN78°41'45"E 203.03' BNDY7517± SF710065± SF96763± SF56697± SFPARCEL C2515± SFPARCEL D2515± SFPARCEL A7074± SF67299± SF32515± SFPARCEL B7091± SF16692± SF46526± SF210148± SF8N78°30'00"E 44.81'141.47'N11°30'00"W 93.38'N78°30'00"E 62.72'N11°30'00"W 72.00'N11°30'00"W 139.30'N78°30'00"E 41.87'N78°30'00"E 41.78'N78°30'00"E 114.33'N78°30'00"E 114.33'N78°30'00"E 114.33'N78°30'00"E 114.33'N78°30'00"E 114.33'N78°30'00"E 94.33'N78°30'00"E 94.33'N78°30'00"E 114.33'N78°30'00"E 114.33'N11°30'00"W 34.41'62.22'22.00'9.16'1.26'63.84'22.00'55.63'0.50'71.00'N78°30'00"E 17.50'0.50'N78°30'00"E 17.50'61.87'22.00'59.25'71.00'58.63'22.00'63.84'59.83'22.00'61.83' 114.33'61.86'61.87'22.00'56.25'141.15'103.80'L1L2R=2.50'Δ=90°00'00"L=3.93'R=21.50'Δ=90°00'00"L=33.77'R=21.50'Δ=90°00'00"L=33.77'R=17.50'Δ=90°00'00"L=27.49'114.33'88.70'121.30'162.65'57.71'R=2.50'Δ=90°00'00"L=3.93'9161± SFPARCEL FEVAE, PSUEN11°30'00"W 169.80' M-PLN78°30'00"E 117.83' M-MN11°30'00"W284.45' M-MN67°18'16"W47.15' M-MN78°30'00"E77.77' M-MN11°18'15"W 310.95' M-MN11°18'15"W 66.59'5'9'5'9'9'22.19'9'18'84.83' M-PL

44.77' M-PLN11°18'15"W22.31' M-TIER=4011.14'Δ=7°29'34"L=524.55'EVAE, PSUEEVAE, PSUEEVAE, PSUE21.5'21.5'5'21.5'5'21.5'12.5'21.5'95.67'149.28'188.78' M-PL95.67' M-PL 5'21.5'139.30' PL-PL30.5' M-PLL3(R)0.81'139.31'N78°30'00"E26.50'3692± SFPARCEL G6134± SFPARCEL EEVAE, PSUEEVAE, PSUE25'25'

33.00'M-PL

33.00'M-PL18'Line TableLine #L1L2L3BearingN56°30'00"WN33°30'00"EN78°30'00"ELength10.61'10.61'26.50'DECEMBER 2024CONSISTING OF 4 SHEETSFOR CONDOMINIUM PURPOSESBEING A SUBDIVISION OF PARCELS 1 AND 2OF PARCEL MAP, RECORDED IN BOOK 400 OFPARCEL MAPS, AT PAGE 39SANTA CLARA COUNTY RECORDS,MILPITAS, SANTA CLARA COUNTY,CALIFORNIATRACT 10626

Page 296 of 395 ends

PARCEL DPARCEL A 63 PARCEL B1 42
87 9
5PARCEL C

PARCEL FPARCEL E PARCEL G
795PARCEL CPARCEL DPARCEL A63PARCEL B1428PARCEL FEVAE, PSUE1.67' PSUE1.67'PSUE1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUEEVAE, PSUEEVAE, PSUEEVAE, PSUEPARCEL GPARCEL EEVAE, PSUEEVAE, PSUE6.5' PSUE4' PSUE6.5' PSUE6.5' PSUE6.5'PSUE6.5' PSUE6.5' PSUE4' PSUE4' PSUE6.75'PSUE6.75'PSUE16.5'41.08'20.56'17.50'13.52'13.52'1.67' PSUE1.67' PSUE27.72'75.16'17.51'1.67'PSUE13.52'21.63'10.50'7.67'PSUE4.50'32.21'139.34' EX. SDE BK C972 PG 21310' EX. PSUEBK I625 PG 53610' EX. SDEBK I625 PG 53210' EX. SDEBK C972 PG 2131.74'20.34'3.00'20.00'20.00'34.83'8.50'34.17'1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE1.67'PSUE14.08'14.75'13.52'13.52'11.98'15.78'3.00'3.00'4'PSUE17.38'1.67'PSUE1.67' PSUE1.67' PSUE13.66'13.60'23.55'15.11'22.02'8.50'31.03'32.21'32.21'31.14'32.66'4.50'4.5'14.31'13.52'13.52'13.52'13.52'13.52'13.52'13.52'13.52'20.56'20.56'41.08'41.08'17.50'20.56'41.08'41.08'20.56'17.50'1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE17.50'17.50'1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE1.67' PSUE20.00'14.02'4.17'15.67'15.67'4.17'5.98'PSUER=21.50' Δ=28°45'23" L=10.79'R=21.50' Δ=25°41'42" L=9.64'N11°30'00"W 6.35'N78°30'00"E 7.15'N17°15'23"E(R)N42°57'05"E(R)PSUER=17.50' Δ=9°52'15" L=3.01'R=17.50' Δ=34°32'41" L=10.55'N11°29'59"W 4.74'N78°30'01"E 9.25'N01°37'45"W(R)N32°54'56"E(R)PSUE6.75' PSUE18.50'16.00'SEE DETAIL BELOW884.50'100' EX. PSUE BK D878 PG 72910' PSUEPARCEL FN78°30'00"E 61.44'26.71'12.00'26.68'19.72'N78°30'00"EN11°18'15"W12.9'7.90'5'PSUER=21.50'Δ=15°39'39"L=5.88'5'8N11°30'00"W7.90'N11°30'00"W7.90'N62°15'39"W(R)N77°55'19"W(R)DECEMBER 2024CONSISTING OF 4 SHEETSFOR CONDOMINIUM PURPOSESBEING A SUBDIVISION OF PARCELS 1 AND 2OF PARCEL MAP, RECORDED IN BOOK 400 OFPARCEL MAPS, AT PAGE 39SANTA CLARA COUNTY RECORDS,MILPITAS, SANTA CLARA COUNTY,CALIFORNIATRACT 10626DETAILN.T.S.

Page 297 of 395 ends
Page 298 of 395 ends
Page 299 of 395 ends
Page 300 of 395 ends
Page 301 of 395 ends
Page 302 of 395 ends
Page 303 of 395 ends
Page 304 of 395 ends
Page 305 of 395 ends
Page 306 of 395 ends
Page 307 of 395 ends
Page 308 of 395 ends
Page 309 of 395 ends
Page 310 of 395 ends
Page 311 of 395 ends
Page 312 of 395 ends
Page 313 of 395 ends
Page 314 of 395 ends
Page 315 of 395 ends
Page 316 of 395 ends
Page 317 of 395 ends
Page 318 of 395 ends
Page 319 of 395 ends
Page 320 of 395 ends
Page 321 of 395 ends
Page 322 of 395 ends
Page 323 of 395 ends
Page 324 of 395 ends
Page 325 of 395 ends
Page 326 of 395 ends
Page 327 of 395 ends
Page 328 of 395 ends
Page 329 of 395 ends
Page 330 of 395 ends
Page 331 of 395 ends
Page 332 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Receive an Update on the Security Improvements at the McCarthy Ranch Sewer Lift Station (Main Lift) and Determine that the Condition Continues to Constitute an Emergency (Staff Contact: Christian Di Renzo, Public Works Director, 408-586-2602)
Category: Consent Calendar-Community Services and Sustainable Infrastructure Meeting Date: 1/7/2025
Recommendation: (1) Receive an update on the security improvements at the McCarthy Ranch Sewer Lift Station; and (2) Determine by a four-fifths vote that the condition continues to constitute an emergency.

BACKGROUND:

Pursuant to Public Contract Code section 22050 and the attached Council Resolution No. 9134, the Director of Public Works, in the case of emergency, may authorize a repair of a public facility and procure the work without giving notice for bids. An emergency is defined as “a sudden, unexpected occurrence that poses a clear and imminent danger, requiring immediate action to prevent or mitigate the loss or impairment of life, health, property, or essential public services.” Additionally, State law requires the Public Works Director, as the City official with delegated authority to take emergency action, to report any emergency authorization and the reason(s) for the authorization to the City Council not later than seven days after the action, or at its next regularly scheduled meeting if that meeting will occur not later than 14 days after the action. Further, the Public Works Director is required to report why the emergency would not permit a delay resulting from a competitive solicitation for bids and the City Council is required to review the emergency action at every regularly scheduled meeting thereafter until the emergency repair is completed. The City Council shall continue to review the emergency action at every regularly scheduled meeting thereafter until the action is terminated. At each review, the City Council shall determine, by a four-fifths vote, whether there is a need to continue the action.

Consistent with applicable State law and Council Resolution, on July 30, 2024, the Public Works Director declared an emergency and authorized the City to contract with Trofholz Technologies and Diamond Fencing to implement various security and access control improvements to the McCarthy Ranch Sewer Lift Station (Main Lift). Further, within the required timeframe the Public Works Director informed the City Council via Information Memorandum on July 31, 2024, regarding the emergency authorization, the reasons for the authorization, and the cost for repair in a not-to-exceed amount of $700,000.

PROJECT/STATUS UPDATE:

The installation of security enhancements by Trofholz Technologies, Inc. has been completed. The materials, hardware, and network connections necessary to operate security cameras, card readers, and motion sensors at the Main Lift facility are now installed and operational. Staff conducted a final inspection of the security enhancement features and concluded this portion of the security improvements project on December 19, 2024.

Diamond Fence Co., Inc. will demolish and properly dispose of the existing fence, and install approximately 1,760 linear feet of new, code-compliant fencing using ClearVU reinforced panels topped with ribbon wire, integrated into the current gate structure. Materials have arrived and fence installation will begin in early January. The estimated project completion date is now anticipated in late January 2025.

FISCAL IMPACT:

Funding for these repairs is available in the City’s Capital Improvement Program (CIP) budget. CIP Project 6124 – Sewer Pump Station Rehabilitation Project will fund the installation of security cameras, card readers, and motion sensors. The funding source of this CIP project is Sewer Infrastructure Fund. The available balance as of 12/18/2024 is $1,277,987.

Page 333 of 395 ends

CIP 6130 – Main Lift Odor Emission Control Project will fund the removal and replacement of the perimeter fencing. The funding source of this CIP Project are Sewer Infrastructure Fund, and Sewer Treatment Fund.

The available balance as of 12/18/2024 is $20,217.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

The emergency repair work is exempt from CEQA, per CEQA Guidelines Section 15301, Existing Facilities and 15302, Replacement or Reconstruction.

RECOMMENDATION:
(1) Receive an update on the security improvements at the McCarthy Ranch Sewer Lift Station. (2) Determine by a four-fifths vote that the condition continues to constitute an emergency.

ATTACHMENT(S):

None.

Page 334 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Adopt a Resolution Certifying Election Results and Adding the Property Located at 612 South Main Street into Community Facilities District No. 2005-1 (Annexation No. 25) (Staff Contact: Christian Di Renzo, Public Works Director, 408-586-2602; and Michael Silveira, City Engineer, 408-586-3303) Category: Public Hearings-Community Development
Meeting Date: 1/7/2025
Recommendation: Following receipt of election results from the City Clerk, adopt a resolution certifying election results and adding the property located at 612 South Main Street into Community Facilities District No. 2005-1 (Annexation No. 25).

BACKGROUND:

On April 4, 2023, the City Council approved a Site Development Permit No. SD22-0007, Conditional Use Permit No. UP22-0003, Vesting Tentative Map No. MT22-0003, Density Bonus Permit No. DB22-0002, Tree Removal Permit No. TR22-0014, and Environmental Assessment No. EA22-0005 to allow construction of a 57- unit townhome-style condominium subdivision comprised of nine multi-family residential buildings, and associated site improvements, located on a 2.35 acre site at 612 South Main Street (Project) in the Midtown Specific Plan area which will be constructed by Toll West Coast, LLC (Developer).

ANALYSIS:

The Project is comprised of real property in the City of Milpitas, County of Santa Clara, State of California, described as follows:
•Parcels 1 and 2, as shown on that certain map entitled, "Parcel Map", which map was filed for record in the office of the recorder of the County of Santa Clara, State of California on July 18, 1977 in book 400 of maps, page 39.

The Project is subject to annexation into the Community Facilities District No. 2005-1 (CFD 2005-1). The City has on file a Certificate of Registrar of Voters from the County of Santa Clara certifying that there are zero (0) registered voters within the boundaries of the proposed CFD 2005-1 - Annexation No. 25 for this development.

On January 2, 2025, the property owner voted on agreeing to the proposed annexation. The resolution attached hereto, depending on the results of the election to be determined at the hearing, documents the results of the election for annexation into CFD 2005-1 subject to the provisions of the Mello-Roos Community Facilities Act of 1982, commencing with Section 53311 of the Government Code. While the Act has a number of requirements for annexation and imposition of the special tax, the Developer (as the sole landowner within the annexation territory) has agreed to waive many of the formalities. A copy of the waiver executed by the Developer is on file with the City Clerk.

POLICY ALTERNATIVE(S):

Alternative 1: Deny Annexation of Project to CFD 2005-1 Pros: None
Cons: Denying the Annexation of Project into CFD No. 2005-1 would prevent the City from funding necessary public services through levying special taxes on these parcels.

Reason for Not Recommending: Staff is recommending this action to adequately fund the perpetual maintenance of improvements and services within CFD No. 2005-1.

Page 335 of 395 ends

FISCAL IMPACT:

Staff recommends adoption of a resolution certifying election results and adding the Project into CFD 2005-1 to adequately fund the perpetual maintenance of improvements and services within Annexation No. 25.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

This Project is covered under the scope of activities approved under the Midtown Specific Plan Environmental Impact Report, SCH2000092027, which was certified by City Council on March 19, 2002. On April 4, 2023, the City Council found that the Project is exempt from further environmental review pursuant to CEQA Guidelines Section 15332 (In-fill Development Projects) in that the Project is consistent with the General Plan and zoning designation while invoking the State Density Bonus Law waivers from development standards and reduced parking requirements, is located in an urban area that has either been previously developed or adjoins existing qualified urban uses on all of the site’s perimeter and is under five acres in size, has no value to endangered, rare, or threatened species, would not result in any significant effects related to traffic, noise, air quality, or water quality, and the site can be adequately served by all required utilities and public services.

As a separate and independent basis, the Project is also exempt from further environmental review pursuant to CEQA Guidelines Section 15168 (Program EIR) per the Midtown Specific Plan EIR (SCH2000092027).

RECOMMENDATION:

Following receipt of election results from the City Clerk, adopt a resolution certifying election results and adding 612 South Main Street to Community Facilities District No. 2005-1 (Annexation No. 25) ATTACHMENT(S):
(a) Resolution

Page 336 of 395 ends

38077.00180\29372866.1
RESOLUTION NO. ______ -

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MILPITAS, CALIFORNIA,

CERTIFYING THE RESULTS OF AN ELECTION AND ADDING TERRITORY TO COMMUNITY FACILITIES DISTRICT NO. 2005-1 (PUBLIC SERVICES) (Annexation No. 25)
WHEREAS, the City Council of the City of Milpitas, California (the “City Council”) has previously formed Community Facilities District No. 2005-1 (Public Services) (“CFD No. 2005-1”) pursuant to the Mello-Roos Community Facilities Act of 1982 (the “Act”), as amended, for the purpose of financing certain Public Services; and WHEREAS, acting pursuant to the Act, the City Council also authorized by the adoption of Resolution No. 7521 the annexation in the future of territory to CFD No. 2005-1, such territory designated as Future Annexation Area, Community Facilities District No. 2005-1 (the “Future Annexation Area”); and
WHEREAS, at this time the unanimous consent to the annexation of certain territory located within the Future Annexation Area to CFD No. 2005-1 has been received from the property owner of such territory, and such territory has been designated as Annexation No. 25 (the "Territory"); and
WHEREAS, less than twelve (12) registered voters have resided within the Territory for each of the ninety (90) days preceding the election date established for the Territory, therefore, pursuant to the Act the qualified elector of the Territory shall be the "landowner," as such term is defined in Government Code Section 53317(f), of such Territory and such landowner who is the owner of record as of the applicable election date, or the authorized representative thereof, shall have one vote for each acre or portion of an acre of the parcel of land that landowner owns within such Territory; and
WHEREAS, the time limit specified by the Act for conducting an election to submit the levy of the special taxes on the Territory to the qualified elector thereof and the requirements for impartial analysis and ballot arguments have been waived with the unanimous consent of the qualified elector of the Territory; and WHEREAS, the City Clerk of the City of Milpitas has caused a ballot to be distributed to the qualified elector of the Territory, has received and canvassed such ballot and made a report to the City Council regarding the results of such canvass, a copy of which is attached as Exhibit A hereto and incorporated herein by this reference; and WHEREAS, at this time the measure voted upon and such measure did receive the favorable vote of the qualified elector of the Territory, and the City Council desires to declare the results of the election; and
WHEREAS, a map showing the Territory and designated as Annexation Map No. 25 (the "Annexation Map"), a copy of which is attached as Exhibit B hereto and incorporated herein by this reference, has been submitted to this legislative body.

Page 337 of 395 ends

2 38077.00180\29372866.1
NOW, THEREFORE, IT IS HEREBY RESOLVED by the City Council of the City of Milpitas, California, acting as the legislative body of Community Facilities District No. 2005- 1, as follows:

Section 1. Recitals. The above recitals are true and correct.

Section 2. Findings. This legislative body does hereby further determine as follows:

A. The unanimous consent as described in the recitals hereto to the annexation of the Territory to CFD No. 2005-1 has been given by the owner of the Territory and such consent shall be kept on file in the Office of the City Clerk of the City of Milpitas.

B. Less than twelve (12) registered voters have resided within the Territory for each of the ninety (90) days preceding the election date established for the each of the parcels located within the Territory, therefore, pursuant to the Act the qualified elector for the Territory shall be the "landowner" of the Territory as such term is defined in Government Code Section 53317(f).

C. The qualified elector of the Territory has voted in favor of the levy of special taxes on the Territory upon its annexation to CFD No. 2005-1.

Section 3. Territory. The boundaries and parcels of property within the Territory and on which special taxes will be levied in order to pay for the costs and expenses of authorized Public Services are shown on the Annexation Map as submitted to and hereby approved by this legislative body.

Section 4. Declaration of Annexation. This legislative body does hereby determine and declare that the Territory, and each parcel therein, is now added to and becomes a part of CFD No. 2005-1. The City Council, acting as the legislative body of CFD No. 2005-1, is hereby empowered to levy the authorized special tax within the Territory.

Section 5. Notice. Immediately upon adoption of this Resolution, notice shall be given as follows:

A. A copy of the Annexation Map as approved shall be filed in the Office of the County Recorder no later than fifteen (15) days after the date of adoption of this Resolution.

B. An Amendment to the Notice of Special Tax Lien (Notice of Annexation) shall be recorded in the Office of the County Recorder no later than fifteen (15) days after the date of adoption of this Resolution.

Page 338 of 395 ends

3 38077.00180\29372866.1
Section 6. Effective Date. This Resolution shall become effective upon its adoption.

ADOPTED by the City Council of the City of Milpitas, California, at a Regular Meeting thereof held this __________ day of ___________, 20__, by the following roll call vote to wit:

AYES:

NOES:

ABSENT:

ABSTAIN:

ATTEST
Suzanne Guzzetta, City Clerk

APPROVED
Carmen Montano, Mayor

APPROVED AS TO FORM
Michael Mutalipassi, City Attorney

Page 339 of 395 ends

A - 1
38077.00180\29372866.1
EXHIBIT “A”

CERTIFICATE OF ELECTION OFFICIAL

AND STATEMENT OF VOTES CAST

STATE OF CALIFORNIA )
) ss.

COUNTY OF SANTA CLARA )
The undersigned, ELECTION OFFICIAL OF THE CITY OF MILPITAS, COUNTY OF SANTA CLARA, STATE OF CALIFORNIA, DOES HEREBY CERTIFY that pursuant to the provisions of Section 53326 of the Government Code and Division 12, commencing with Section 17000 of the Elections Code of the State of California, I did canvass the returns of the votes cast at the

CITY OF MILPITAS
COMMUNITY FACILITIES DISTRICT NO. 2005-1
(PUBLIC SERVICES)

SPECIAL ELECTION
ANNEXATION NO. 25
held on the election date established for each parcel located within the territory included in Annexation No. 25.

I FURTHER CERTIFY that this Statement of Votes Cast shows the whole number of votes cast in the area proposed to be annexed to Community Facilities District No. 2005-1 for or against the Measure are full, true and correct.

VOTES CAST ON PROPOSITION 1: YES
NO
WITNESS my hand this day of , 20__.

SUZANNE GUZZETTA

CITY CLERK

CITY OF MILPITAS

OF THE STATE OF CALIFORNIA

Page 340 of 395 ends

B - 1
38077.00180\29372866.1
Exhibit B
Annexation Map

Page 341 of 395 ends

CITY OF MILPITAS

AGENDA REPORT
(AR)
Item Title: Receive Progress Report on the Work Completed on the Milpitas Gateway-Main Street Specific Plan (Staff Contact: Jay Lee, Planning Director, 408-586-3077) Category: Community Development
Meeting Date: 1/7/2025
Recommendation: Receive progress report on the work completed on the Milpitas Gateway-Main Street Specific Plan.

BACKGROUND:

The Milpitas Midtown Specific Plan was originally adopted by City Council in 2002 to maximize land use, transportation, and economic opportunities along the City’s historic Main Street and to energize and catalyze mixed-use, transit-oriented development in the Midtown area, also known as the “heart” of Milpitas. Since adoption of the current Midtown Specific Plan, little of the community vision for this area has been realized, and many potential development sites remain vacant and underutilized, especially along Main Street. As part of the update process, the Midtown Specific Plan will be renamed the “Milpitas Gateway-Main Street Specific Plan.” The Milpitas Gateway-Main Street Specific Plan will provide a new vision and strategic policy framework to guide redevelopment and reinvestment in three focus areas and transform this important gateway into an attractive and vibrant destination for the City and region.

On April 6, 2021, the City Council adopted the FY2022-26 Capital Improvement Plan (CIP), which included the Milpitas Gateway-Main Street Plan (Midtown Specific Plan Update) [Plan] as Project No. 3437 (Project), with an initial outlay of up to $960,000 from the Community Planning Fund. On May 26, 2021, the Metropolitan Transportation Commission (MTC) awarded the City of Milpitas an additional $500,000 through its Priority Development Area (PDA) Planning Grant Program to complete the Project.

On September 21, 2021, City Council authorized the City Manager to execute a master funding agreement with the Metropolitan Transportation Commission to receive funding through the PDA Planning Grant Program and a professional services agreement with Ascent Environmental for consultant services to prepare the Project.

Throughout the preparation of the Plan, the Project area expanded to annex adjacent neighborhoods that would benefit from inclusion into the Plan area. An additional redevelopment focus area was also added to maximize the development potential of new opportunity sites. Additionally, City staff determined the scope of work should include preparing zoning regulations and development standards to ensure consistency between the Plan and Milpitas Zoning Ordinance upon Plan adoption rather than amending the zoning map and text later. Furthermore, the existing condition of utilities and infrastructure within the Plan area requires additional analysis and utility improvements to ensure that future development will be adequately served. As such, the professional services agreement with Ascent Environmental has been amended to increase the Project budget from $930,708 to $1,059,708 and extend the termination date from June 30, 2023 to June 30, 2025 to deliver this additional scopes of work.

The work completed thus far is summarized below.

1.Kick-Off Meeting and Site Tour: The Project team held a virtual kick-off meeting on October 26, 2021 to initiate the Project and discuss City goals and objectives, team roles and responsibilities, Project area context and efforts under way, and Plan and focus area boundaries.

Page 342 of 395 ends

2.Material Review and Preliminary Mapping: The consultant reviewed relevant existing and in- progress studies and created a series of maps to depict the local context.

3.Existing Conditions Assessment: The consultant assessed the physical context of the Plan area with a focus on identifying preliminary opportunities and constraints related to land use and development.

Completed deliverables include the Land Use, Zoning and Urban Form Analysis, Market Study, Transportation Analysis, Affordable Housing and Community Benefits Memorandum, and Resilience and Climate Adaptation Assessment. Please refer to the Existing Conditions Memo (Attachment 1) for more information.

4.Community Outreach: To create awareness and excitement about the Project and receive meaningful community feedback, the Project team prepared a Community Engagement Strategy, facilitated two pop-up events, presented at the Council Ad-Hoc Main Street Revitalization Subcommittee, held stakeholder interviews, hosted two community workshops, conducted study sessions with the Planning Commission and City Council, and hosted two meetings with the Technical Advisory Committee.

Please refer to the Council agenda report from April 25, 2023 (Attachment 2) for more information regarding the community outreach and feedback received.

5.Visioning, Scenario Planning, and Plan Strategies and Alternatives: Based on the robust existing conditions analysis and feedback received from the community, Council, and TAC, the Project team prepared a vision memo with the Plan strategies and alternatives related to land use, mobility, and open space. The consultant also conducted a feasibility analysis for three development scenarios to test different development frameworks to ensure that Plan recommendations will be practical and implementable. Please refer to the Vision Memo (Attachment 3) for more information.

6.Draft Plan: The consultant prepared an Administrative Draft Plan for internal review. The Administrative Draft Plan incorporates goals, policies, findings, and strategies from earlier phases of the Project and includes chapters addressing Plan vision and goals, land use and zoning, objective design standards, mobility, and the public realm. Staff, including members of the TAC, reviewed the Administrative Draft Plan and provided detailed feedback to ensure the Administrative Draft Plan addresses City Council priorities and community needs.

7.Environmental Analysis: The consultant initiated the environmental review process pursuant to the California Environmental Quality Act. The Project requires a Subsequent Environmental Impact Report (EIR), which builds off the General Plan EIR as the Project is an implementation of the General Plan.

The Project team prepared a Notice of Preparation and held a public scoping meeting to share the anticipated environmental impacts of the Project and receive preliminary feedback regarding the environmental analysis. The consultant also prepared the Administrative Draft Subsequent EIR, which staff is currently reviewing.

ANALYSIS:

Following staff feedback on the Administrative Draft Plan, the consultant is preparing a Public Draft Plan, which will be released for public review upon completion, to solicit community feedback on the Draft Plan prior to Plan adoption. While the Public Draft Plan is not yet available, a summary of the Plan components and next steps are outlined below.

Vision and Goals
The Plan area is envisioned as a group of neighborhoods that together create a complete community and center for Milpitas. New infill housing and mixed-use development will be paired with complete streets, new urban open spaces, and placemaking to distinguish the Plan area as a walkable and bike-friendly urban community. The guiding principles are organized around four themes: (1) vision and placemaking, (2) land use and development, (3) transportation and access, and (4) open space and community amenities.

The Plan is organized around four focus areas: 1) Main Street District, 2) Crossroads District, 3) Gateway District, and 4) Abbott District. The Plan also identifies the following eight (8) “big moves” to implement the Plan vision:

1. Redesign Main Street as a “shared street” with active, pedestrian-friendly spaces and outdoor dining;

2. Redevelop Serra Center and the Crossroads as a new center for the community;

Page 343 of 395 ends

3. Prioritize commercial activity and active building frontages;

4. Enhance Calaveras Boulevard and Abel Street as multimodal complete street corridors;

5. Create a connected network of new streets, paseos, alleys, and bike and pedestrian linkages to improve access and walkability;

6. Develop a connected open space network with new urban parks and plazas;

7. Integrate streetscape, branding, and public art at gateways, along streets, and in public spaces; and

8. Support district solutions including shared parking and coordinated infrastructure improvements.

Land Use and Zoning
The Plan establishes new mixed-use zoning districts aimed at supporting a mix of residential, retail, entertainment, office, civic, and recreational uses at a variety of scales. The land use strategy emphasizes flexibility and streamlined permitting to incentivize mixed-use redevelopment, especially on identified opportunity sites throughout the Plan area. The Plan increases the maximum floor area ratio (FAR) for nonresidential land uses to encourage commercial development. For residential uses, the Plan provides the following density ranges and heights to encourage redevelopment of underutilized sites into residential development at an appropriate scale in each district:

District Min. Density (du/ac) Max. Density (du/ac) Max. Bldg. Height (ft.) Max. No. of Stories Main Street 20 65 65 5
Crossroads 40 85 85 7
Gateway 18 65 65 5
Abbott N/A N/A 65 N/A
Library 20 65 65 5
Within these density ranges and maximum heights, the expected residential products include townhomes, stacked condos, and apartments. The Plan will also utilize incentive-based zoning to offer various development incentives such as density bonuses and streamlined permitting in exchange for Project features that offer community benefits such as green building, small business retention, public parking, publicly accessible open space, affordable housing, and historic rehabilitation.

In recognition of the importance of local businesses within the Plan area, the Plan identifies retail priority areas and activity streets to require ground-floor retail and well-designed shopfronts along key streets and corners, and active building frontages and robust streetscape improvements along important pedestrian corridors.

Lastly, the Plan establishes moderate parking ratios complemented by a holistic parking strategy to minimize negative parking impacts on existing residential neighborhoods in the area while removing constraints for new development.

Objective Design Standards
The Plan builds on the Citywide Residential and Mixed-Use Objective Design Standards by providing Plan- specific objective design standards that address the following topics: 1) site planning and design, 2) building design and architecture, and 3) pedestrian level design.

Public Improvements
The Plan includes strategies, policies, and specific improvements related to mobility, public realm, and infrastructure and public services to complement and support the development expected in the Plan area.

Mobility
The Mobility Chapter establishes multimodal corridors along Calaveras Boulevard, Serra Way, Main Street, and Abel Street, which are all envisioned as complete streets serving vehicles, transit, bicyclists, and pedestrians. Street cross sections and standards are provided to implement this vision. The chapter also establishes locations and standards for future streets and connections to connect existing roadways and support a more walkable neighborhood grid pattern, while providing policy direction for public transit and public parking.

Page 344 of 395 ends

Public Realm
The Public Realm Chapter establishes policies for new parks, open space, greenways, and plazas within the Plan area to create an interconnected network appropriate for an area with limited undeveloped land. The parks and open space strategy focuses on smaller pocket parks and urban spaces in strategic locations, rather than large parks and open spaces, to ensure existing and new developments are adequately served by recreational facilities. The chapter also covers important topics including creekside open space, underpasses and other infrastructure spaces, privately-owned public open spaces, gateways and wayfinding, public art and murals, and streetscape and landscaping.

Infrastructure and Public Services
The Infrastructure and Public Services Chapter outlines the infrastructure needed to support public services within the Plan area. It sets forth policies and improvement projects for enhancing and expanding public facilities. Topics include storm drainage, flooding, water supply and distribution, sewer, solid waste, energy and technology, fire protection and emergency response, police services, schools, libraries, and childcare.

Implementation
Lastly, the Plan includes an Administration and Implementation Chapter, which outlines a comprehensive list of implementation actions, assigns responsible leads, establishes time frames, and recommends funding options.

The implementation strategy includes both public and private programs and actions to implement the Plan vision, goals, and policies.

Next Steps
The remaining next steps for the Project are outlined below.

1.Public Draft Plan and EIR (late January 2025): Based on staff and community input received, the consultant will refine and finalize the Public Draft Plan and Subsequent EIR for public review and circulation.

2.Final Plan and EIR (May 2025): Following the release of the Public Draft Plan and Subsequent EIR, the Project team will gather final input received during the public review process and prepare the Final Plan and Subsequent EIR.

3.Adoption Hearings (June 2025): The Project team will present the Final Plan and Subsequent EIR to the Planning Commission for recommendation and the City Council for adoption.

If the Plan is adopted, it will go into effect shortly thereafter and City staff will start reviewing development projects within the Plan area against the new land use and zoning requirements. Staff also initiated the Main St. Sense of Place Plan, which will identify specific public improvements along Main Street to implement the Gateway-Main St. Specific Plan, and establish a Plan-specific development impact fee to fund the identified improvements as sites develop on Main Street.

POLICY ALTERNATIVES:

This is an informational item for Council feedback and direction and is one of several sessions providing Council with the progress of the Gateway-Main Street Specific Plan update.

FISCAL IMPACT:

This is an informational item. As such, there is no fiscal impact.

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA):

This report represents ongoing work on the Milpitas Gateway-Main Street Specific Plan; it is anticipated that an Environmental Impact Report (EIR) will be prepared for consideration prior to Plan adoption.

RECOMMENDATION:

Receive progress report on the work completed on the Milpitas Gateway-Main Street Specific Plan.

ATTACHMENT(S):
(a) Council Agenda Report, April 25, 2023
(b) Existing Conditions Memo
(c) Vision Memo

Page 345 of 395 ends