38077.00180\29080232.10

-72- 00 72 13 GENERAL CONDITIONS

by this Contract on forms satisfactory to the City. The certificates and endorsements for each insurance policy shall be signed by a person authorized by that insurer to bind coverage on its behalf, and shall be on forms acceptable to the City. All certificates and endorsements must be received and approved by the City before Work commences.

A. Additional Insureds; Waiver of Subrogation . The City, its elected and appointed officials, officers, attorneys, agents employees and volunteers shall be Liability insurance, ISO CG forms 20 10 and 20 37 (or endorsements providing the exact same coverage, including complet
policies of Commercial General Liability insurance, ISO CG form 20 38 (or endorsements providing the exact same coverage). Notwithstanding the minimum limits set forth in this Contract for any type of insurance coverage, all available insurance proceeds in excess of the specified minimum limits of coverage shall be available to the parties required to be named as Additional Insureds hereunder.

Contractor and its insurance carriers shall provide a Waiver of Subrogation in favor of those parties.

B.
compensation insurance for all of the employees engaged in Work under this Contract, on or at the Site, and, in case of any sublet Work, the Contractor shall ompensation insurance for
of employees engaged in work under
Statutes, the Contractor shall provide or shall cause a subcontractor to provide, adequate insurance coverage for the protection of such employees not otherwise protected. The Contractor is required to secure payment of compensation to his employees in accordance with the provisions of section 3700 of the Labor Code.

The Contractor shall file with the City certificates of his insurance protecting workers. Company or companies providing insurance coverage shall be acceptable to the City, if in the form and coverage as set forth in the Contract Documents.

C.

Insurance, including Occupational Disease, in the amount of at least one million dollars ($1,000,000.00) per person per accident. Contractor shall provide City with the provisions of the Contract Documents. The policy shall be endorsed, if applicable, to provide a Borrowed Servant/Alternate Employer Endorsement and contain a Waiver of Subrogation in favor of the City.

D. Commercial General Liability Insurance
form Commercial General Liability insurance coverage at least as broad as the most current ISO CGL Form 00 01, including but not limited to, premises liability, contractual liability, products/completed operations, personal and advertising management of the Site, or the performance of its obligations hereunder. The

Page 133 of 762 ends

38077.00180\29080232.10

-73- 00 72 13 GENERAL CONDITIONS

policy shall not contain any exclusion contrary to this Contract including but not limited to endorsements or provisions limiting coverage for (1) contractual liability (including but not limited to ISO CG 24 26 or 21 39); or (2) cross-liability for claims or suits against one insured against another. Policy limits shall not be less than $1,000,000 per occurrence for bodily injury, personal injury and property damage.

If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit. Defense costs shall be paid in addition to the limits.

1. Such policy shall comply with all the requirements of this Article. The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability.

Further the limits set forth herein shall not be construed to relieve the Contractor from liability in excess of such coverage, nor shall it limit City, and shall not preclude
the City from taking such other actions available to the City under other provisions of the Contract Documents or law.

2. All general liability policies provided pursuant to the provisions of this Article shall comply with the provisions of the Contract Documents.

3. All general liability policies shall be written to apply to all bodily injury, including death, property damage, personal injury, owned and non-owned equipment, blanket contractual liability, completed operations liability, explosion, collapse, under-ground excavation, removal of lateral support, and other covered loss, however occasioned, occurring during the policy term, and shall specifically insure the performance by Contractor of that part of the indemnification contained in these General Conditions relating to liability for injury to or death of persons and damage to property.

4. If the coverage contains one or more aggregate limits, a minimum of 50% of any such aggregate limit must remain available at all times; if over 50% of any aggregate limit has been paid or reserved, the City may require additional coverage to be purchased by Contractor to restore the required limits. Contractor may combine primary, umbrella, and as broad as possible excess liability coverage to achieve the total limits indicated above. Any umbrella or excess liability policy shall include the additional insured endorsement described in the Contract Documents.

5. All policies of general liability insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

E. Automobile Liability Insurance
Automobile Liability Insurance at least as broad as ISO CA 00 01 (Any Auto) in the amount of, at least, one million dollars ($1,000,000) per accident for bodily injury and property damage. Such insurance shall provide coverage with respect to the ownership, operation, maintenance, use, loading or unloading of any auto owned, leased, hired or borrowed by Contractor or for which Contractor is responsible, in a form and with insurance companies acceptable to the City. All policies of

Page 134 of 762 ends

Docusign Envelope ID: F68BB77D-FEA5-402B-AB23-3ABFEC031649 automobile insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

F. Contractor shall require all tiers of sub-contractors working under this Contract to provide the insurance required under this Article unless otherwise agreed to in writing by City. Contractor shall make certain that any and all subcontractors hired coverage does not comply with the foregoing provisions, Contractor shall indemnify and hold the City harmless from any damage, loss, cost, or expense, thereof.

G. Contractor s Pollution Liability Coverage. Contractor shall provide pollution liability insurance in an amount not less than $1,000,000 per occurrence and $2,000,000 aggregate.

ARTICLE 37 FORM AND PROOF OF CARRIAGE OF INSURANCE
A. Any insurance carrier providing insurance coverage required by the Contract Documents shall be admitted to and authorized to do business in the State of have an A.M. Best rating of not less than an A:VII. Insurance deductibles or self- insured retentions must be declared by the Contractor. At the election of the City the Contractor shall either 1) reduce or eliminate such deductibles or self-insured retentions, or 2) procure a bond which guarantees payment of losses and related investigations, claims administration, and defense costs and expenses. If umbrella or excess liability coverage is used to meet any required limit(s) specified herein, indicating that such coverage is subject to the same terms and conditions as the underlying liability policy.

B. Each insurance policy required by this Contract shall be endorsed to state that: (1) coverage shall not be suspended, voided, reduced or cancelled except after thirty (30) days prior written notice by certified mail, return receipt requested, has been given to the City; and (2) any failure to comply with reporting or other provisions of the policies, including breaches of warranties, shall not affect coverage provided to the City, its officials, officers, agents, employees, and volunteers.

C. The Certificates(s) and policies of insurance shall contain or shall be endorsed to contain the covenant of the insurance carrier(s) that it shall provide no less than thirty (30) days written notice be given to the City prior to any material modification or cancellation of such insurance. In the event of a material modification or cancellation of coverage, the City may terminate the Contract or stop the Work in accordance with the Contract Documents, unless the City receives, prior to such effective date, another properly executed original Certificate of Insurance and original copies of endorsements or certified original policies, including all endorsements and attachments thereto evidencing set forth herein and the insurance required herein is in full force and effect. Contractor shall not take possession, or use the Site, or commence operations under this Contract until the City has been furnished original Certificate(s) of Insurance and certified original copies of endorsements or policies of insurance including all endorsements and any and all other attachments as required in this Article. The original endorsements for each policy and the Certificate of Insurance shall be signed by an individual authorized by the insurance carrier to do so on its behalf. 38077.00180\29080232.10 -74- 00 72 13 GENERAL CONDITIONS

Page 135 of 762 ends

38077.00180\29080232.10

-75- 00 72 13 GENERAL CONDITIONS

D. The Certificate(s) of Insurance, policies and endorsements shall so covenant and shall be construed as primary, and the City
self-insured retentions or self-insured programs shall not be construed as contributory.

E. City reserves the right to adjust the monetary limits of insurance coverages during the term of this Contract including any extension thereof if, in the City judgment, the amount or type of insurance carried by the Contractor becomes inadequate.

F. Contractor shall report to the City
all insurance claims submitted by the Contractor in connection with the Work under this Contract.

ARTICLE 38 TIME FOR COMPLETION AND LIQUIDATED DAMAGES
A. Time for Completion/Liquidated Damages. Time is of the essence in the completion of the Work. Work shall be commenced within ten (10) Days of the specified in the Contract Documents. The City is under no obligation to consider early completion of the Project; and the Contract completion date shall not be amend
completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from the City (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If the Work is not completed as stated in the Contract Documents, it is understood that the City will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to determine the amount of actual damage, it is agreed that Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each calendar day of delay until the Work is fully completed as determined by the City. Contractor and its surety shall be liable for any liquidated damages. Any money due or to become due the Contractor may be retained to cover liquidated damages.

B. Extension of Time Due to Weather Delays: The City and Contractor mutually agree that excusable delay events associated with the occurrence of inclement weather will be based only on conditions that were not foreseeable at the time the hedule shall include an
allowance for the following schedule of expected weather delay days. If the Contractor encounters fewer inclement weather days per month or in total than shown below, then the City has the right to use the unencountered balance of days as an offset against any other claims for excusable delays or Owner-caused delays. Actual inclement weather days must prevent work on critical activities for 50 percent or more of the C
for excusable delay due to excessive inclement weather shall be for critical path work only and must be supported by a Time Impact Analysis as described in Article

42. No additional compensation will be granted for an excusable delay.

Page 136 of 762 ends

38077.00180\29080232.10

-76- 00 72 13 GENERAL CONDITIONS

Month Calendar Days
January 6
February 6
March 7
April 4
May 3
June 1
July 0
August 1
September 2
October 2
November 3
December 5
Total Annual Inclement Weather Days 40

A. Extension of Time. Contractor shall not be charged liquidated damages because of any delays in completion of the Work due to unforeseeable causes beyond the control and without the fault or negligence of Contractor (or its subcontractors or suppliers). Contractor shall within five (5) Days of identifying any such delay notify the City in writing of causes of delay. The City shall ascertain the facts and extent of delay and grant extension of time for completing the Work when, in its judgment, the facts justify such an extension. Time extensions to the Project shall be requested by the Contractor as they occur and without delay. No delay claims shall be permitted unless the event or occurrence delays the completion of the Project beyond the Contract completion date.

B. No Damages for Reasonable Delay.
for which the City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall the City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs. Damages caused by unreasonable City delay, including delays caused by items that are the responsibility of the City pursuant to Government Code section 4215, shall be based on actual costs only, no proportions or formulas shall be used to calculate any delay damages.

ARTICLE 39 SCHEDULE OF VALUES, COST BREAKDOWN AND PERIODIC ESTIMATES Contractor shall furnish on forms Approved by the City:

A. When requested by the Engineer, and within ten (10) Days of Notice to Proceed with the Contract, the Contractor shall provide a Schedule of Values consisting of a detailed estimate giving a complete breakdown of the Contract price for each lump sum bid item in the Contract.

B. A monthly itemized estimate of Work done for the purpose of making progress payments. In order for the City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.

Page 137 of 762 ends

38077.00180\29080232.10

-77- 00 72 13 GENERAL CONDITIONS

C. Contractor shall submit, with each of its payment requests, an adjusted list of actual quantities, verified by the Engineer, for unit price items listed, if any, in the Bid Form.

D. Following the Acceptance of the Work, the Contractor shall submit to the City a written statement of the final quantities of unit price items for inclusion in the final payment request.

E. The City shall have the right to adjust any estimate of quantity and to subsequently correct any error made in any estimate for payment.

Contractor shall certify under penalty of perjury, that all cost breakdowns and periodic estimates accurately reflect the Work on the Project.

ARTICLE 40 PROGRESS ESTIMATES AND PAYMENT
A. By the tenth (10th) Day of the following calendar month, Contractor shall submit to Engineer a payment request which shall set forth in detail the value of the Work done for the period beginning with the date work was first commenced and ending on the end of the calendar month for which the payment request is prepared.

Contractor shall include any amount earned for authorized extra work. From the total thus computed, a deduction shall be made in the amount of five percent (5%) for retention, except where the City has adopted a finding that the Work done under the Contract is substantially complex, and then the amount withheld as retention shall be the percentage specified in the Notice Inviting Bids. From the remainder a further deduction may be made in accordance with Section B below. The amount computed, less the amount withheld for retention and any amounts withheld as set

B. The Contractor shall provide an updated project schedule with each payment request.

C. The City may withhold a sufficient amount or amounts of any payment or payments otherwise due to Contractor, as in his judgment may be necessary to cover:

1. Payments which may be past due and payable for just claims against Contractor or any subcontractors for labor or materials furnished in and about the performance of work on the Project under this Contract.

2. Defective work not remedied.

3. Failure of Contractor to make proper payments to his subcontractor or for material or labor.

4. Completion of the Contract if there is a reasonable doubt that the Work can be completed for balance then unpaid.

5. Damage to another contractor or a third party.

6. Amounts which may be due the City for claims against Contractor.

Page 138 of 762 ends

38077.00180\29080232.10

-78- 00 72 13 GENERAL CONDITIONS

7. -

8. Failure to provide update on construction schedule as required herein.

9. Site cleanup.

10. Failure to comply with Contract Documents.

11. Liquidated damages.

12. Legally permitted penalties.

D. The City may apply such withheld amount or amounts to payment of such claims or obligations at its discretion with the exception of subsections (B)(1), (3), and (5) of this Article, which must be retained or applied in accordance with applicable law.

In so doing, the City shall be deemed the agent of Contractor and any payment so made by the City shall be considered as a payment made under contract by the City to Contractor and the City shall not be liable to Contractor for such payments made in good faith. Such payments may be made without prior judicial determination of claim or obligations. The City will render Contractor a proper accounting of such funds disbursed on behalf of Contractor.

E. Upon receipt, the Engineer shall review the payment request to determine whether it is undisputed and suitable for payment. If the payment request is determined to be unsuitable for payment, it shall be returned to Contractor as soon as practicable but not later than seven (7) Days after receipt, accompanied by a document setting forth in writing the reasons why the payment request is not proper. The City shall make the progress payment within 30 calendar days after the receipt of an undisputed and properly submitted payment request from Contractor, provided that a release of liens and claims has been received from the Contractor pursuant to Civil Code section 8132. The number of days available to the City to make a payment without incurring interest pursuant to this paragraph shall be reduced by the number of days by which the Engineer exceeds the seven (7) Day requirement.

F. A payment request shall be considered properly executed if funds are available for payment of the payment request and payment is not delayed due to an audit inquiry by the financial officer of the City.

ARTICLE 41 SECURITIES FOR MONEY WITHHELD
Pursuant to section 22300 of the Public Contract Code of the State of California, Contractor may request the City to make retention payments directly to an escrow agent or may substitute securities for any money withheld by the City to ensure performance under the contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the City or with a state or federally chartered bank as the escrow agent who shall return such securities to Contractor upon satisfactory completion of the contract. Deposit of securities with an escrow agent shall be subject to a written agreement substantially in the form provided in section 22300 of the Public Contract Code.

Page 139 of 762 ends

38077.00180\29080232.10

-79- 00 72 13 GENERAL CONDITIONS

ARTICLE 42 CHANGES AND EXTRA WORK.

A. Contract Change Orders.

1. The City, without invalidating the Contract, may order changes in the Work consisting of additions, deletions or other revisions, and the Contract Price and Contract Time shall be adjusted accordingly. Except as otherwise provided herein, all such changes in the Work shall be authorized by Change Order, and shall be performed under the applicable conditions of the Contract Documents. A Change Order signed by the Contractor indicates the Contractor's agreement therewith, including any adjustment in the Contract Price or the Contract Time, and the full and final settlement of all costs (direct, indirect and overhead) related to the Work authorized by the Change Order.

2. Contractor shall promptly execute changes in the Work as directed in writing by the City even when the parties have not reached agreement on whether the change increases the scope of Work or affects the Contract Price or Contract Time. All claims for additional compensation shall be presented in writing. No claim will be considered after the Work in question has been completed unless a written Change Order has been issued or a timely written notice of claim has been made by Contractor.

3. Whenever any change is made as provided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, conditions, and provisions of the original Contract.

4. Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any decrease or omission of any item or portion of Work to be done.

5. No dispute, disagreement, or failure of the parties to reach agreement on the terms of the Change Order shall relieve the Contractor from the obligation to proceed with performance of the work, including Additional Work, promptly and expeditiously.

6. documents related to the Project immediately upon request of the City, as set forth in Article 52.

7. Any alterations, extensions of time, Additional Work, or any other changes sureties.

B. Contract Price Change.

1. Process for Determining Adjustments in Contract Price. a. Owner Initiated Change. The Contractor must submit a complete cost proposal, including any change in the Contract Price or

Page 140 of 762 ends

38077.00180\29080232.10

-80- 00 72 13 GENERAL CONDITIONS

Contract Time, within seven (7) Days after receipt of a scope of a proposed change order initiated by the City, unless the City requests that proposals be submitted in less than seven (7) Days. b. Contractor Initiated Change. The Contractor must give written notice of a proposed change order required for compliance with the Contract Documents within seven (7) Days of discovery of the facts giving rise to the proposed change order.
c. Whenever possible, any changes to the Contract amount shall be in a lump sum mutually agreed to by the Contractor and the City. d. Price quotations from the Contractor shall be accompanied by sufficiently detailed supporting documentation to permit verification by the City, including but not limited to estimates and quotations from subcontractors or material suppliers, as the City may reasonably request. Contractor shall certify the accuracy of all Change Order Requests under penalty of perjury.
e. If the Contractor fails to submit a complete cost proposal within the seven (7) Day period (or as requested), the City has the right to order the Contractor in writing to commence the Work immediately on a time and materials basis and/or issue a lump sum change to the Contract Price and/or Contract Time in accordance with the City City's
estimate, the Contractor will waive its right to dispute the action unless within fifteen (15) Days following completion of the added/deleted work, the Contractor presents written proof that the City

2. Unit Price Change Orders.
a. When the actual quantity of a Unit Price item is found to vary from the Bid Form, compensation for the change in quantity will be calculated by multiplying the actual quantity by the Unit Price. This calculation may result in either an additive or deductive Final Change Order pursuant to the Contract Documents. Contractor shall immediately inform the Engineer when the actual quanities vary from estimated quantities.
b. No Mark up for Overhead and Profit. Because the Contract Unit Prices provided in the Bid Form include Overhead and Profit as determined by Contractor at the time of Bid submission, no mark up or deduction for Overhead and Profit will be included in Unit Price Change Orders.
c. Bid items included on the Bid Form may be deducted from the Work in their entirety without any negotiated extra costs.
d. Contractor acknowledges that unit quantities are estimates and agrees that the estimated unit quantities listed on the Bid Form will

Page 141 of 762 ends

38077.00180\29080232.10

-81- 00 72 13 GENERAL CONDITIONS

be adjusted to reflect the actual unit quantities which may result in an adjustment to the Contract Unit Prices. Such an adjustment will be made by execution of a final additive or deductive Change Order n notification,
City
Prices and/or Contract Time in accordance with the Contract Documents.

3. Lump Sum Change Orders. Compensation for Lump Sum Change Orders shall be limited to expenditures necessitated specifically by the Additional Work, and shall be segregated as follows:
a. Labor. The costs of labor will be the actual cost for wages prevailing locally for each craft or type of worker at the time the Additional Work is done, plus employer payments of payroll taxes and insurance, health and welfare, pension, vacation, apprenticeship funds, and other direct costs resulting from Federal, State or local laws, as well as assessment or benefits required by lawful collective bargaining agreements. The use of a labor classification which would increase the Additional Work cost will not be permitted unless the Contractor establishes the necessity for such new
classifications. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental.
b. Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available in the quantities involved, plus sales tax, freight, and delivery.

Materials costs
invoice. If invoices or other satisfactory evidence of cost are not furnished within fifteen (15) Days of delivery, then the City shall determine the materials cost, at its sole discretion.
c. Tool and Equipment Use. Costs for the use of small tools, which are tools that have a replacement value of $1,000 or less, shall be considered included in the Overhead and Profit mark-ups established below. Regardless of ownership, the rates to be used in determining equipment use costs shall not exceed listed rates prevailing locally at equipment rental agencies, or distributors, at the time the Work is performed.

4. Time and Materials Change Orders.
a. General. The term Time and Materials means the sum of all costs reasonably and necessarily incurred and paid by Contractor for labor, materials, and equipment in the proper performance of Additional Work. Except as otherwise may be agreed to in writing by the City, such costs shall be in amounts no higher than those prevailing in the locality of the Project, and shall include only the following items.

Page 142 of 762 ends

38077.00180\29080232.10

-82- 00 72 13 GENERAL CONDITIONS

b. Timely and Final Documentation.
i. T&M Daily Sheets. Contractor must submit timesheets, materials invoices, records of equipment hours, and records of rental equipment hours to the City
approval signature each day Additional Work is performed.

Failure to get the City
claim these costs. The City
time sheets only serves as verification that the Work was performed and is not indicative of City

ii. T&M Daily Summary Sheets. All documentation of incurred Contractor within three (3) Days of incurring the cost for labor, material, equipment, and special services as
shall be presented in a summary table in an electronic
spreadsheet file by labor, material, equipment, and special services. Each T&M Daily Summary Sheet shall include
pe
failure to provide a T&M Daily Summary Sheet showing a
total cost summary within three (3) Days but within five (5) Days of performance of the Work will result in the
reduced by 50% for that portion of Additional Work which failure to submit the T&M Daily Summary Sheet within five (5) Days of performance of the Work will result in a total

iii. T&M Total Cost Summary Sheet. Contractor shall submit a T&M Total Cost Summary Sheet, which shall include total actual costs, within seven (7) Days following completion of City
cost shall be presented in a summary table in an electronic spreadsheet file by labor, material, equipment, and special Summary Sheet within seven (7) Days of completion of the waiver for any
reimbursement of any costs associated with the T&M
Summary Sheets or the performance of the Additional Work. c. Labor. The Contractor will be paid the cost of labor for the workers used in the actual and direct performance of the Work. The cost of labor will be the sum of the actual wages paid (which shall include any employer payments to or on behalf of the workers for health and welfare, pension, vacation, and similar purposes) substantiated

Page 143 of 762 ends

38077.00180\29080232.10

-83- 00 72 13 GENERAL CONDITIONS

by timesheets and certified payroll for wages prevailing for each craft or type of workers performing the Additional Work at the time the Additional Work is done, and the labor surcharge set forth in the Department of Transportation publication entitled Labor Surcharge and Equipment Rental Rates , which is in effect on the date upon which the Work is accomplished and which is a part of the Contract.

The labor surcharge shall constitute full compensation for all payments imposed by Federal, State, or local laws and for all other payments made to, or on behalf of, the workers, other than actual wages.
i. Equipment Operator Exception. Labor costs for equipment operators and helpers shall be paid only when such costs are not included in the invoice for equipment rental.
ii. Foreman Exception. The labor costs for foremen shall be proportioned to all of their assigned work and only that applicable to the Additional Work shall be paid. Indirect labor costs, including, without limitation, the superintendent, project manager, and other labor identified in the Contract Documents will be considered Overhead.
d. Materials. The cost of materials reported shall be itemized at invoice or lowest current price at which materials are locally available and delivered to the Project site in the quantities involved, plus the cost of sales tax, freight, delivery, and storage. i. Trade discounts available to the purchaser shall be credited to the City notwithstanding the fact that such discounts may not have been taken by Contractor.
ii. For materials secured by other than a direct purchase and direct billing to the purchaser, the cost shall be deemed to be the price paid to the actual supplier as determined by the City
iii. Payment for materials from sources owned wholly or in part by the purchaser shall not exceed the price paid by the purchaser for similar materials from said sources on
Additional Work items or the current wholesale price for such materials delivered to the Project site, whichever price is lower.
iv. If, in the opinion of the City
materials is excessive, or Contractor does not furnish
satisfactory evidence of the cost of such materials, then the cost shall be deemed to be the lowest current wholesale price for the total quantity concerned delivered to the Project site less trade discounts.

Page 144 of 762 ends

38077.00180\29080232.10

-84- 00 72 13 GENERAL CONDITIONS

v. The City reserves the right to furnish materials for the Additional Work and no Claim shall be allowed by
Contractor for costs of such materials or Indirect Costs or profit on City furnished materials.
e. Equipment.
i. Rental Time. The rental time to be paid for equipment on the Project site shall be the time the equipment is in
productive operation on the Additional Work being
performed and, in addition, shall include the time required to move the equipment to the location of the Additional Work and return it to the original location or to another location requiring no more time than that required to return it to its original location; except that moving time will not be paid if the equipment is used on other than the Additional Work, even though located at the site of the Additional Work. (a) Rental Time Not Allowed. Rental time will not be
allowed while equipment is inoperative due to
breakdowns.
(b) Computation Method. The following shall be used in computing the rental time of equipment on the
Project site.
(i) When hourly rates are paid, any part of an
hour less than 30 minutes of operation shall
be considered to be 1/2-hour of operation,
and any part of an hour in excess of 30
minutes will be considered one hour of
operation.
(ii) When daily rates are paid, any part of a day
less than 4 hours operation shall be
considered to be 1/2-day of operation, and
any part of an hour in excess of 4 hours will
be considered one day of operation.
ii. Rental Rates. Contractor will be paid for the use of equipment at the lesser of (i) the actual rental rate, or (ii) the rental rate listed for that equipment in the California Department of Transportation publication entitled Labor Surcharge and Equipment Rental Rates , which is in effect on the date upon which the Contract was executed. Such rental rates will be used to compute payments for equipment direct ownership, leasing, renting, or another method of acquisition. The rental rate to be applied for use of each item of equipment shall be the rate (i.e., daily, monthly) resulting in the least total cost to the City for the total period

Page 145 of 762 ends

38077.00180\29080232.10

-85- 00 72 13 GENERAL CONDITIONS

of use. If it is deemed necessary by Contractor to use equipment not listed in the publication, an equitable rental rate for the equipment will be established by the City
Representative. Contractor may furnish cost data which might assist the City
of the rental rate.
iii. Contractor-Owned Equipment.
(a) For Contractor-owned equipment, the allowed
equipment rental rate will be limited to the monthly
equipment rental rate using a utilization rate of 173
hours per month.
(b) For Contractor-owned equipment, the rental time to
be paid for equipment on the Site shall be the time
the equipment is in productive operation, unless, in
the instance of standby time, the equipment could be
actively used by Contractor on another project, then
City shall pay for the entirety of the time the
to demonstrate to the City that the equipment could
be actively used on another project.
(i) All equipment shall, in the opinion of the
condition and suitable for the purpose for
which the equipment is to be used.
(ii) Before construction equipment is used on
the Additional Work, Contractor shall plainly
stencil or stamp an identifying number
thereon at a conspicuous location, and shall
furnish to the City
duplicate, a description of the equipment and
its identifying number and the scheduled
Additional Work activities planned.
(iii)
rating and manufacturer approved
modifications shall be used to classify
equipment for the determination of
applicable rental rates. Equipment which
has no direct power unit shall be powered by
a unit of at least the minimum rating
recommended by the manufacturer.
f. Special Services. Special work or services are defined as that Additional Work characterized by extraordinary complexity, sophistication, or innovation or a combination of the foregoing attributes which are unique to the construction industry.

Page 146 of 762 ends

38077.00180\29080232.10

-86- 00 72 13 GENERAL CONDITIONS

i. Invoices for Special Services. When the City
Representative and Contractor determine that a special
service is required which cannot be performed by the forces of Contractor or those of any of its Subcontractors, the special service may be performed by an entity especially skilled in the Additional Work. Invoices for special services based upon the current fair market value thereof may be accepted without complete itemization of labor, material, and equipment rental costs, after validation of market values by the City
ii. Discount and Allowance. All invoices for special services will be adjusted by deducting all trade discounts offered or available, whether the discounts were taken or not. In lieu of Overhead and Profit specified herein, a total allowance not to exceed fifteen percent (15%) for Overhead and Profit will be added to invoices for Special Services.
iii. When the City determines, in its sole discretion, that competitive bidding is necessary for certain special
services, Contractor shall solicit competitive bids for those special services.
g. Excluded Costs. The term Time and Material shall not include any of the following costs or any other home or field office overhead costs, all of which are to be considered administrative costs covered

i. Overhead Cost. Payroll costs and other compensation of managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, timekeepers, clerks, and other personnel employed by
Co
office or any branch office, material yard, or shop for general administration of the Additional Work;
ii. Office Expenses.
branch offices;
iii. Capital Expenses. Any
employed for the Additional Work and charges against
Contractor for delinquent payments;
iv. Negligence. Costs due to the negligence of Contractor or any Subcontractor or Supplier, or anyone directly or
indirectly employed by any of them or for whose acts any of them may be liable, including without limitation the
correction of Defective Work, disposal of materials or

Page 147 of 762 ends

38077.00180\29080232.10

-87- 00 72 13 GENERAL CONDITIONS

equipment wrongly supplied, and making good any damage
to property;
v. Other. Other overhead or general expense costs of any kind and the cost of any item not specifically and expressly included in the Contract Documents;
vi. Small Tools. Cost of small tools valued at less than $1,000 and that remain the property of Contractor;
vii. Administrative Costs. Costs associated with the preparation of Change Orders (whether or not ultimately authorized), cost estimates, or the preparation or filing of Claims; viii. Anticipated Lost Profits. Expenses of Contractor associated with anticipated lost profits or lost revenues, lost income or earnings, lost interest on earnings, or unpaid retention; ix. Home Office Overhead. Costs derived from the
of the Eichleay, Allegheny , burden fluctuation, or other similar methods;
x. Special Consultants and Attorneys. Costs of special consultants or attorneys, whether or not in the direct employ of Contractor, employed for services specifically related to the resolution of a Claim, dispute, or other matter arising out of or relating to the performance of the Additional Work. h. Overhead, Profit and Other Charges. The mark-up for overhead (including supervision) and profit on work added to the Contract shall be according to the following:
i. is defined as consisting of costs of labor,
materials, and tools and equipment only excluding overhead and profit. The costs of applicable insurance and bond premium will be reimbursed to the Contractor and
subcontractors at cost only, without mark-up. Contractor shall provide City with documentation of the costs, including, but not limited to, payroll records, invoices, and such other information as City may reasonably request.
ii. For
cost for overhead and profit shall not exceed fifteen percent (15%) of the Net Cost of the Work.
iii. For Work performed by a subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) Net Cost.

Page 148 of 762 ends

38077.00180\29080232.10

-88- 00 72 13 GENERAL CONDITIONS

iv. For Work performed by a sub-subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the sub-
the subcontractor and general contractor may each add an additional five percent (5%) of the Net Cost of the lower tier subcontractor.
v. No additional mark-up will be allowed for lower tier subcontractors, and in no case shall the added cost for overhead and profit payable by City exceed twenty-five
percent (25%) of the Net Cost as defined herein, of the party that performs the Work.

5. All of the following costs are included in the markups for overhead and profit described above, and Contractor shall not receive any additional compensation for: Submittals, drawings, field drawings, Shop Drawings, including submissions of drawings; field inspection; General Superintendence; General administration and preparation of cost proposals, schedule analysis, Change Orders, and other supporting documentation; computer services; reproduction services; Salaries of project engineer, superintendent, timekeeper, storekeeper, and secretaries; Janitorial services; Small tools, incidentals and consumables; Temporary On-Site facilities (Offices, Telephones, High Speed Internet Access, Plumbing, Electrical Power, Lighting; Platforms, Fencing, Water), Jobsite and Home office overhead or other expenses; vehicles and fuel used for work otherwise included in the Contract Documents; Surveying; Estimating; Protection of Work; Handling and disposal fees; Final Cleanup; Other Incidental Work; Related Warranties; insurance and bond premiums.

6. For added or deducted Work by subcontractors, the Contractor shall furnish to the City
material and equipment, including the subcontractor markup for overhead and profit. The same requirement shall apply to sub-subcontractors

7. For added or deducted work furnished by a vendor or supplier, the Contractor shall furnish to the City a detailed record of the cost to the Contractor, signed by such vendor or supplier.

8. Any change in the Work involving both additions and deletions shall indicate a net total cost, including subcontracts and materials. Allowance for overhead and profit, as specified herein, shall be applied if the net total cost is an increase in the Contract Price; overhead and profit allowances shall not be applied if the net total cost is a deduction to the Contract Price.

The estimated cost of deductions shall be based on labor and material prices on the date the Contract was executed.

9. Contractor shall not reserve a right to assert impact costs, extended job site costs, extended overhead, constructive acceleration and/or actual acceleration beyond what is stated in the Change Order for Work. No claims shall be allowed for impact, extended overhead costs, constructive acceleration and/or actual acceleration due to a multiplicity of changes

Page 149 of 762 ends

38077.00180\29080232.10

-89- 00 72 13 GENERAL CONDITIONS

and/or clarifications. The Contractor may not change or modify the City change order form in an attempt to reserve additional rights.

10. If the City disagrees with the proposal submitted by Contractor, it will notify the Contractor and the City will provide its opinion of the appropriate price and/or time extension. If the Contractor agrees with the City, a Change Order will be issued by the City. If no agreement can be reached, the City shall have the right to issue a unilateral Change Order setting forth its determination of the reasonable additions or savings in costs and time attributable to the extra or deleted work. Such determination shall become final and binding if the Contractor fails to submit a claim in writing to the City within fifteen (15) Days of the issuance of the unilateral Change Order, disputing the terms of the unilateral Change Order, and providing such supporting documentation for its position as the City may require.

C. Change of Contract Times.

1. The Contract Times may only be changed by a Change Order.

2. All changes in the Contract Price and/or adjustments to the Contract Times this Article. No cost or time will be allowed for cumulative effects of multiple changes. All Change Orders must state that the Contract Time is not changed or is either increased or decreased by a specific number of days.

Failure to include a change to time shall waive any change to the time unless the parties mutually agree in writing to postpone a determination of the change to time resulting from the Change Order.

3. Notice of the amount of the request for adjustment in the Contract Times with supporting data shall be delivered within seven (7) Days after such start of occurrence, unless City
period of time to ascertain more accurate data in support of the request.

No extension of time or additional compensation shall be given for a delay if the Contractor failed to give notice in the manner and within the time prescribed.

4. City may elect, at City

5. Use of Float and Critical Path.
a. Float is for the benefit of the Project. Float shall not be considered for the exclusive use or benefit of either the City or the Contractor. b. Contractor shall not be entitled to compensation, and City will not compensate Contractor, for delays which impact early completion. and the Contract Time shall be considered a part of the Project float.

6. a City-

Page 150 of 762 ends

38077.00180\29080232.10

-90- 00 72 13 GENERAL CONDITIONS

concurrent delays, and established by a proper time impact analysis. No time extension shall be allowed unless, and then only to the extent that, the City-caused delay extends the critical path beyond the previously approved Contract Time. If approved, the increase in time required to complete the Work shall be added to the Contract Time.
a. Contractor shall not be entitled to an adjustment in the Contract Price or Contract Times for delays within the control of Contractor.

Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor.
b. If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions (as determined by the City), Acts of God, acts or failures to act of utility owners not under the control of City, or other causes not the fault of and beyond control of City and Contractor, then Contractor shall be entitled to an time extension when the Work stopped is on the critical path. Such a non-compensable adjustment shall be s. Contractor
must submit a timely request in accordance with the requirements of this Article.
c. Utility-Related Delays.
i. Contractor shall immediately notify in writing the utility owner and City
any subsequent changes in the construction schedule which will affect the time available for protection, removal, or relocation of utilities. Requests for extensions of time arising out of utility relocation or repair delays shall be filed in accordance with this Article.
ii. Contractor shall not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, as noted in the Contract Documents or by the Underground Service Alert survey.

7. Content for Requests for Contract Extension.
entitlement shall be clear and complete citing specific Contract Document minimum, each request for a time extension must include:
a. Each request for an extension of Contract Time must identify the impacting event, in narrative form, providing a description of the delay event and sufficient justification as to why the Contractor is entitled to a time extension. Contractor must demonstrate that the delay arises from unforeseeable causes beyond the control and without the fault or negligence of both Contractor and any Subcontractors or Suppliers, or any other persons or organizations employed by any of them or for whose acts any of them may be

Page 151 of 762 ends

38077.00180\29080232.10

-91- 00 72 13 GENERAL CONDITIONS

liable, and that such causes in fact lead to performance or completion of the Work, or specified part in question, beyond the and diligent actions to guard against those effects.
b. Each request for an extension of Contract Time must include a time impact analysis in CPM format, using the Contemporaneous Impacted As-Planned Schedule Analysis to calculate the impact of the delay event.

8. No Damages for Reasonable Delay.
a. City City is responsible
shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs.
b. City and City
partners, employees, agents, consultants, or subcontractors of each of them, shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.

9. request for extensions of the Contract Times. Such failure, neglect, or refusal prejudices City City
and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for extensions of Contract Times, and whether such extensions may be warranted. Contractor hereby waives all rights to extensions of Contract Times due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of this Article.

10. Contractors submission of daily construction reports and schedule updates in accordance with these Contract Documents is required for the evaluation of the merits of time extension request. Failure of the Contractor to submit daily construction reports and schedule updates shall constitute a waiver of its right to seek a time extension or additional compensation.

ARTICLE 43 FINAL ACCEPTANCE AND PAYMENT
A. Final Inspection. Upon written notice from Contractor that the entire Work is complete, the Engineer will promptly make a final inspection and will notify Contractor in writing of all particulars in which this inspection reveals that the Work

Page 152 of 762 ends

38077.00180\29080232.10

-92- 00 72 13 GENERAL CONDITIONS

is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies.

B. Final Acceptance. After Contractor has, in the opinion of the Engineer, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Contract Documents, all maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurance, certificates of inspection, marked-up record documents (as- builts), and other documents required by the Contract Documents, the City shall execute and file with the County in which the Project is located a Notice of Completion, constituting final acceptance and completion of the Project, except as may be expressly noted.

C. Final Payment.

1. Application for Payment. Upon execution of the Notice of Completion, Contractor may make application for final payment following the procedure for progress payments. The final application for payment shall be accompanied (except as previously delivered) by: all documentation called for in the Contract Documents, including but not limited to a fully completed Conditional Waiver and Release on Final Payment

2. . If, on the basis of the City
observation of the Work during construction and final inspection, and review of the final Application for Payment and accompanying documentation as required by the Contract Documents, the City is satisfied that the Work has been completed and Contractor has satisfied all other requirements for final payment, the City will process the final payment appllication. Otherwise, the City will return the payment application to Contractor, indicating in writing the reasons for refusing to recommend final payment, in which case Contractor shall make the necessary corrections and resubmit the application for payment.

3. Payment Becomes Due. Within sixty (60) Days after the presentation to the City of the proper and complete final application for payment and accompanying documentation, the amount recommended by the Engineer, less any sum the City is entitled to set off pursuant to the Contract Documents, will become due and will be paid by the City to Contractor.

D. Waiver of Claims. The making and acceptance of final payment will constitute a waiver of all Claims by Contractor against the City other than those previously made in accordance with the requirements herein and expressly acknowledged by the City in writing as still unsettled.

ARTICLE 44 OCCUPANCY
The City reserves the right to occupy or utilize any portion of the Work at any time before completion, and such occupancy or use shall not constitute acceptance of any part of Work covered by this Contract.This use shall not relieve the Contractor of its responsibilities under the Contract.

Page 153 of 762 ends

38077.00180\29080232.10

-93- 00 72 13 GENERAL CONDITIONS

ARTICLE 45 INDEMNIFICATION
To the fullest extent permitted by law, Contractor shall immediately defend (with counsel of the choosing), indemnify and hold harmless the City, officials, officers, agents, employees, and representatives, and each of them from and against:

A. Any and all claims, demands, causes of action, costs, expenses, injuries, losses or liabilities, in law or in equity, of every kind or nature whatsoever, but not limited to, injury to or death, including wrongful death, of any person, and damages to or destruction of property of any person, arising out of, related to, or in any manner directly or indirectly connected with the Work or this Contract, including claims made by subcontractors for nonpayment, including without limitation the payment of all conseq
expenses, however caused, regardless of whether the allegations are false, fraudulent, or groundless, and regardless of any negligence of the City or its officers, employees, or authorized volunteers (including passive negligence), except the sole negligence or willful misconduct or active negligence of the City or its officials, officers, employees, or authorized volunteers.

B.

Americans with Disabilities Act (ADA) or other federal or state disability access or dis
construction of the improvements or after the Work is complete, as the result of

C. Any and all actions, proceedings, damages, costs, expenses, fines, penalties or liabilities, in law or equity, of every kind or nature whatsoever, arising out of, resulting from, or on account of the violation of any governmental law or regulation, compliance with which is the responsibility of Contractor; D. Any and all losses, expenses, damages (including damages to the Work itself), may incur with respect to the failure, neglect, or refusal of Contractor to faithfully perform the W
incurred by the indemnified parties in any lawsuit to which they are a party.

City
choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or instituted against the City, its officials, officers, agents, employees and representatives. Contractor shall pay and satisfy any judgment, award or decree that may be rendered against the City, its officials, officers, employees, agents, employees and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse the City, its officials, officers, agents, employees and representatives for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code section 2782.

Page 154 of 762 ends

38077.00180\29080232.10

-94- 00 72 13 GENERAL CONDITIONS

ARTICLE 46 PROCEDURE FOR RESOLVING DISPUTES
Contractor shall timely comply with all notices and requests for changes to the Contract Time or Contract Price, including but not limited to all requirements of Article 42, Changes and Extra Work, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely request a change to the Contract Price or Contract Time, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the Contract or at law.

A. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Article shall be construed to be consistent with said statutes.

B. Claims.

Contractor, after a change order duly requested in accordance with Article 42 payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the City. Claims governed by this Article may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the procedures contained in Article 42
request for a change has been denied in whole or in part. Claims governed by this Article must be filed no later than the date of final payment. The claim shall be submitted in writing to the City and shall include on its first page the following in 16 documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra Work, disputed Work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

C. Supporting Documentation. The Contractor shall submit all claims in the following format:

1. Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made

2. List of documents relating to claim:

Specifications
Drawings
Clarifications (Requests for Information)

Page 155 of 762 ends

38077.00180\29080232.10

-95- 00 72 13 GENERAL CONDITIONS

Schedules
Other

3. Chronology of events and correspondence

4. Analysis of claim merit

5. Analysis of claim cost

6. Time Impact Analysis in CPM format
D. Upon receipt of a claim pursuant to this Article, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 Days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 Days after the City issues its written statement.

1. If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to body after the 45-Day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

2. Within 30 Days of receipt of a claim, the City may request in writing additional documentation supporting the claim or relating to defenses or claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement documented, shall be submitted to the Contractor within 30 Days (if the claim is less than $15,000, within 15 Days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

E. Meet and Confer.
fails to respond within the time prescribed, the Contractor may so notify the City, in ilure to respond within the time prescribed, respectively, and demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall schedule a meet and confer conference within 30 Days for settlement of the dispute.

F. Mediation. Within 10 business Days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 Days after the

Page 156 of 762 ends

38077.00180\29080232.10

-96- 00 72 13 GENERAL CONDITIONS

City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business Days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

1. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

2. For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3. Unless otherwise agreed to by the City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.

4. The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are established for all civil actions filed to resolve claims of $375,000 or less:

1. Within 60 Days, but no earlier than 30 Days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. The mediation process shall provide for the selection within 15 Days by both parties of a disinterested third person as mediator, shall be commenced within 30 Days of the submittal, and shall be concluded within 15 Days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

Page 157 of 762 ends

38077.00180\29080232.10

-97- 00 72 13 GENERAL CONDITIONS

2. If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of other party.

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra Work, disputed Work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra Work, disputed Work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the Work is completed or the date the Contractor last performs Work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver.
time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.

ARTICLE 47
A. Termination for Cause by the City:

1. In the sole estimation of the City, if the Contractor refuses or fails to prosecute the Work or any separable part thereof with such diligence as will insure its completion within the time specified by the Contract Documents, or any extension thereof, or fails to complete such Work within such time, or if the Contractor should be adjudged a bankrupt, or if it should make a general assignment for the benefit of its creditors, or if a receiver should be appointed on account of its insolvency, or the Contractor or any of its subcontractors should violate any of the provisions of this Contract, the City may serve written notice upon the Contractor and its Surety of the City's intention to terminate this Contract. This notice of intent to terminate shall contain the reasons for such intention to terminate this Contract, and a statement to the effect that the Contractor's right to perform this Contract shall cease and terminate upon the expiration of ten (10) calendar days

Page 158 of 762 ends

38077.00180\29080232.10

-98- 00 72 13 GENERAL CONDITIONS

unless such violations have ceased and arrangements satisfactory to the City have been made for correction of said violations.

2. In the event that the City serves such written notice of termination upon the Contractor and the Surety, the Surety shall have the right to take over and perform the Contract. If the Surety does not: (1) give the City written notice of Surety's intention to take over and commence performance of the Contract within 15 calendar days of the City's service of said notice of intent to terminate upon Surety; and (2) actually commence performance of the Contract within 30 calendar days of the City's service of said notice upon Surety; then the City may take over the Work and prosecute the same to completion by separate contract or by any other method it may deem advisable for the account and at the expense of the Contractor.

3. In the event that the City elects to obtain an alternative performance of the Contract as specified above: (1) the City may, without liability for so doing, take possession of and utilize in completion of the Work such materials, appliances, plants and other property belonging to the Contractor that are on the site and reasonably necessary for such completion (A special lien to secure the claims of the City in the event of such suspension is hereby created against any property of Contractor taken into the possession of the City under the terms hereof and such lien may be enforced by sale of such property under the direction of the City Council without notice to Contractor.

The proceeds of the sale after deducting all expenses thereof and connected therewith shall be credited to Contractor. If the net credits shall be in excess of the claims of the City against Contractor, the balance will shall be liable to the City for any cost or other damage to the City necessitated by the City securing an alternate performance pursuant to this Article.

B. Termination for Convenience by the City:

1. The City may terminate performance of the Work called for by the Contract Documents in whole or, from time to time, in part, if the City determines that a termination is in the City's interest.

2. The Contractor shall terminate all or any part of the Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of the City, the extent of termination, and the Effective Date of such termination.

3. After receipt of Notice of Termination, and except as directed by the City's Representative, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this Termination for Convenience clause, immediately proceed with the following obligations:
a. Stop Work as specified in the Notice.

Page 159 of 762 ends

38077.00180\29080232.10

-99- 00 72 13 GENERAL CONDITIONS

b. Complete any Work specified in the Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
c. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Document is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety. d. Terminate all subcontracts to the extent that they relate to the portions of the Work terminated.
e. Place no further subcontracts or orders, except as necessary to complete the continued portion of the Contract.
f. Submit to the City's Representative, within ten (10) calendar days from the Effective Date of the Notice of Termination, all of the usual documentation called for by the Contract Documents to
substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the Contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the Effective Date of the Notice of Termination; (2) describe the costs incurred with particularity; and

4. Termination of the Contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the Work performed.

5. In the event that the City exercises its right to terminate this Contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the Contract Documents, the following amounts:
a. All actual reimbursable costs incurred according to the provisions of this Contract.
b. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the City's Representative that it is reasonably probable that Contractor would have made a profit had the Contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.

Page 160 of 762 ends

38077.00180\29080232.10

-100- 00 72 13 GENERAL CONDITIONS

c. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the Contract under this Article.

C. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of the City or the Contract is terminated.

ARTICLE 48 WARRANTY AND GUARANTEE OF WORK
A. Contractor hereby warrants that materials and Work shall be completed in conformance with the Contract Documents and that the materials and Work provided will fulfill the requirements of this Warranty. Contractor hereby agrees to repair or replace, at the discretion of the City, any or all Work that may prove to be defective in its workmanship, materials furnished, methods of installation or fail to conform to the Contract Document requirements together with any other Work which may be damaged or displaced by such defect(s) within a period of one (1) year from the date of the Notice of Completion of the Project without any expense whatever to the City, ordinary wear and tear and unusual abuse and neglect excepted. Contractor shall be required to promptly repair or replace defective equip
corrective actions and testing, including the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of the Contractor.

B.

Work shall be reinstated for an additional one (1) year period, commencing with the date of acceptance of such corrected Work. The reinstatement of the one (1) year warranty shall apply only to that portion of work that was corrected.

Contractor shall perform such tests as City may require to verify that any corrective actions, including, without limitation, redesign, repairs, and replacements comply with the requirements of
with the above-mentioned conditions within ten (10) calendar days after being notified in writing of required repairs, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction reimburse the City for any expenses incurred hereunder immediately upon demand.

C. In addition to the warranty set forth in this Article, Contractor shall obtain for City all warranties that would be given in normal commercial practice and assign to City manufactured by Contractor and provided as part of the Work, to the extent that such third-party warranties are assignable and extend beyond the warranty period set forth in this Article. Contractor shall furnish the City with all warranty and guarantee documents prior to final Acceptance of the Project by the City as required.

Page 161 of 762 ends

38077.00180\29080232.10

-101- 00 72 13 GENERAL CONDITIONS

D. When specifically indicated in the Contract Documents or when directed by the Engineer, the City may furnish materials or products to the Contractor for installation. In the event any act or failure to act by Contractor shall cause a warranty applicable to any materials or products purchased by the City for installation by the Contractor to be voided or reduced, Contractor shall indemnify City from and against any cost, expense, or other liability arising therefrom, and shall be responsible to the City for the cost of any repairs, replacement or other costs that would have been covered by the warranty but for such act or failure to act by Contractor.

E. The Contractor shall remedy at its expense any damage to City-owned or controlled real or personal property.

F. The City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. The Contractor shall within ten (10) calendar days after being notified commence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; the City shall have the right to replace, repair or otherwise remedy the defect, or

G. In the event of any emergency constituting an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, the City may undertake at Contractor s expense, and without prior notice, all Work necessary to correct such condition.

H. Acceptance of Defective Work.

1. If, instead of requiring correction or removal and replacement of Defective Work, the City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to City evaluation of and determination to accept such Defective Work and for the diminished value of the Work.

2. If any acceptance of defective work occurs prior to release of the Project Retention, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work and all costs incurred by City.

3. If the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

4. If the acceptance of Defective Work occurs after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

I. City May Correct Defective Work.

Page 162 of 762 ends

38077.00180\29080232.10

-102- 00 72 13 GENERAL CONDITIONS

1. If Contractor fails within a reasonable time after written notice from City Representative to correct Defective Work, or to remove and replace rejected Work as required by City, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven deficiency.

2. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the the Site, and incorporate in the Work all materials and equipment stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City and City the
agents, employees, other contractors, and consultants of each of them, access to the Site to enable City to exercise the rights and remedies to correct the Defective Work.

3. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by City correcting the Defective Work will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions into the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price.

4. Such claims, costs, losses and damages will include, but not be limited to, all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Defective Work.

5. If the Change Order is executed after all payments under the Contract have been paid by City and the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

6. If the Change Order is executed after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

7. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performance of the Work attributable to City correcting Defective work.

J. Nothing in the Warranty or in the Contract Documents shall be construed to limit the rights and remedies available to City at law or in equity, including, but not limited to, Code of Civil Procedure section 337.15.

Page 163 of 762 ends

38077.00180\29080232.10

-103- 00 72 13 GENERAL CONDITIONS

ARTICLE 49 DOCUMENT RETENTION & EXAMINATION
A. In accordance with Government Code section 8546.7, records of both the City and the Contractor shall be subject to examination and audit by the State Auditor General for a period of three (3) years after final payment.

B. Contractor shall make available to the City
related to the Project immediately upon request of the City.

C. In addition to the State Auditor rights above, the City shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Contractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to the City, for a period of four (4) years after final payment.

ARTICLE 50 SEPARATE CONTRACTS
A. The City reserves the right to let other contracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.

B. To ensure proper execution of its subsequent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the Work in place or discrepancies with the Contract Documents.

C. Contractor shall ascertain to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by the City in prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor exclusive occupancy at site of the Project.

Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer shall decide which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so that contractors may proceed simultaneously. The City shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.

ARTICLE 51 NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to the City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) calendar days after being sent by first class mail, whichever

Page 164 of 762 ends

38077.00180\29080232.10

-104- 00 72 13 GENERAL CONDITIONS

is earlier. Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.

ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS
Pursuant to Public Contract Code section 9201, the City shall provide the Contractor with timely notification of the receipt of any third-party claims relating to the Contract. The City is entitled to recover reasonable costs incurred in providing such notification.

ARTICLE 53 STATE LICENSE BOARD NOTICE
Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Regist
California 95826.

ARTICLE 54 INTEGRATION
A. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.

B. Contract Documents Represent Entire Contract. The Contract Documents represent the entire agreement of the City and Contractor.

ARTICLE 55 ASSIGNMENT OF CONTRACT
Contractor shall not assign, transfer, convey, sublet or otherwise dispose of the rights or title of interest of any or all of this contract without the prior written consent of the City. Any assignment without the written consent of the City shall be void.

Any assignment of money due or to become due under this Contract shall be subject to a prior lien for services rendered or Material supplied for performance of Work called for under the Contract Documents in favor of all persons, firms, or corporations rendering such services or supplying such Materials to the extent that claims are filed pursuant to the Civil Code, the Code of Civil Procedure or the Government Code.

ARTICLE 56
Contractor shall first notify the City in order that proper steps may be taken to have the change will affect City
ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS
Pursuant to Public Contract Code section 7103.5, in entering into a public works contract or subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to the City all rights, title, and interest in and to all

Page 165 of 762 ends

38077.00180\29080232.10

-105- 00 72 13 GENERAL CONDITIONS

causes of action it may have under Section 4 of the Clayton Act (15 USC, Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from the purchase of goods, services, or materials pursuant to this contract or any subcontract. This assignment shall be made and become effective at the time the City tenders final payment to the Contractor, without further acknowledgment by the parties.

ARTICLE 58 PROHIBITED INTERESTS
No City official or representative who is authorized in such capacity and on behalf of the City to negotiate, supervise, make, accept, or approve, or to take part in negotiating, supervising, making, accepting or approving any engineering, inspection, construction or material supply contract or any subcontract in connection with construction of the project, shall be or become directly or indirectly interested financially in the Contract.

ARTICLE 59 CONTROLLING LAW
Notwithstanding any subcontract or other contract with any subcontractor, supplier, or other person or organization performing any part of the Work, this Contract shall be governed by the law of the State of California excluding any choice of law provisions.

ARTICLE 60 JURISDICTION; VENUE
Contractor and any subcontractor, supplier, or other person or organization performing any part of the Work agrees that any action or suits at law or in equity arising out of or related to the bidding, award, or performance of the Work shall be maintained in the Superior Court of Santa Clara County, California, and expressly consent to the jurisdiction of said court, regardless of residence or domicile, and agree that said court shall be a proper venue for any such action.

ARTICLE 61 LAWS AND REGULATIONS
A. Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on conduct of work as indicated and specified. If Contractor observes that drawings and specifications are at variance therewith, it shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided for in this Contract for changes in work. If Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, it shall bear all costs arising therefrom.

B. Contractor shall be responsible for familiarity with the Americans with Disabilities with ADA regulations.

ARTICLE 62 PATENTS
Contractor shall hold and save the City, officials, officers, employees, and authorized volunteers harmless from liability of any nature or kind of claim therefrom including costs and expenses for or on account of any patented or unpatented invention, article or appliance manufactured, furnished or used by Contractor in the performance of this contract.

Page 166 of 762 ends

38077.00180\29080232.10

-106- 00 72 13 GENERAL CONDITIONS

ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS
All Contract Documents furnished by the City are City property. They are not to be used by Contractor or any subcontractor on other work nor shall Contractor claim any right to such documents. With exception of one complete set of Contract Documents, all documents shall be returned to the City on request at completion of the Work.

ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST
In accordance with Revenue and Taxation Code section 107.6, the Contract Documents may create a possessory interest subject to personal property taxation for which Contractor will be responsible.

ARTICLE 65 SURVIVAL OF OBLIGATIONS
All reresentations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor.

Page 167 of 762 ends

38077.00180\29080232.10

-107- 00 73 13 SPECIAL CONDITIONS

00 73 13 SPECIAL CONDITIONS

1.1 Engineer of Record.

A. For purposes of this Project, the Engineer of Record or Engineer shall be: Nicholas Boswell, MNS Engineers. Inc.

1.2 Location of the Project.

A. The Project is located beginning at the Main Lift Station located at 1425 N. McCarthy Blvd., Milpitas. CA and extending to the San Jose-Santa Clara Regional Wastewater Facility (SJ-SC RWF) located at 700 Los Esteros Rd., San Jose CA.

B. The general location of the Project is shown on City Drawing No. G-01.

1.3 Status of the Project Area and Rights-of-Way.

A. City, at its expense, will provide all rights-of-way or permits, or both, covering the crossing of private property and public and private rights-of-way necessary for the permanent Work; provided, however, Contractor shall, at its expense, obtain any bonds or insurance policies or pay any fees and enter into any agreements required by a controlling authority, e.g., Caltrans or Southern Pacific Railroad Company, before Contractor enters upon any property or right-of-way under the jurisdiction of any such controlling authority for the purpose of performing Work.

B. City has acquired or is negotiating to acquire any rights-of-way, or both, necessary for the permanent Work.

C. City will acquire a Right-of-Way Entry Agreement for contractor construction access to the facilities on San Jose property.

D. If such permits are required, all operations of Contractor shall conform to the restrictions, regulations, and requirements set forth in said permits, copies of which will be included in the Contract Documents.

E. Contractor may be required, as a condition for receiving final payment, to obtain, and provide City
private property whose property has been damaged by the Work. The damage releases will be on a form provided by City.

F. Contractor shall, also, as a condition for receiving final payment, obtain, and provide City Representative with copies of, executed damage releases from the owners of certain public and private property or areas which have been crossed by the Work or otherwise affected by the Work. The damage releases will be on a form provided by City.

1.4 Site Data.

NOT USED

1.5 Pre-Purchased or Pre-Negotiated Material.

NOT USED

Page 168 of 762 ends

38077.00180\29080232.10

-108- 00 73 13 SPECIAL CONDITIONS

1.6 Designation of City .

A. Unless otherwise modified by City, City Ariel Morales P.E., Public Works Division Manager Utility Engineering, 408-586-3358.

1.7 Project Retention
In accordance with Public Contract Code § 7201, City will withhold 5% of each progress payment as retention on the Project.

1.8 Liquidated Damages Due to Contractor Delay.

A. Time is of the essence. Should Contractor fail to complete all or any part of the Work within the time specified in the Contract Documents, City will suffer damage, the amount of which is difficult, if not impossible, to ascertain and, pursuant to the authority of Government Code section 53069.85, City shall therefore be entitled to $3600 per Day as liquidated damages for each Day or part thereof that actual completion extends beyond the time specified.

B. Liquidated damages may be deducted from progress payments due to Contractor, Project retention or may be collected directly from Contractor, or from Contractor's surety. These provisions for liquidated damages shall not prevent City, in case of Contractor's default, from terminating the Contractor.

1.9 Utility Outages Notices to Residents.

A.

City at least ten (10) Days prior to the scheduled outage. Contractor will notify all impacted residents on a form provided by City at least seven (7) Days prior to the scheduled outage.

B. Contractor shall be responsible for providing, at its cost, any temporary utility or facilities necessitated by the utility outage.

1.10 Schedule Constraints.

A. The duration for valve replacement will be limited to 30 days. Once construction is started, the Contractor shall work continuously to complete construction.

B. City has considered these Schedule Constraints when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Constraints.

1.11 Safety Programs.

A. In addition to all other safety requirements of the Contract Documents, Contractor must comply with all applicable laws and regulations of the federal, state, and local government, including OSHA/Cal-OSHA requirements, at all times during the completion of the Work.

B. City has considered these Safety Programs when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Programs.

Page 169 of 762 ends

38077.00180\29080232.10

-109- 00 73 13 SPECIAL CONDITIONS

1.12 Coordination with Other Contractors.

A. In addition to the Contract requirements relating to other work at the Site, City anticipates that other agencies will be performing work within the Site. Specifically:

1. Public Works Department Maintenace and operation of Facilities at Main Lift Station. The contractor shall be required to coordinate with the Public Works Department prior to construction as City Operations Staff will need to direct wastewater from the Main Lift Station to Forcemain-A to allow for replacement of the Forcemain-B Air Release Valves.

The contractor will be required to notify the City in writing 21 days prior to the start of field construction activites.

2. San Jose-Santa Clara Regional Wastewater Facility The contractor shall coordinate -SC
RWF property.

3. The contractor shall ensure work is coordinated between the two facilities so as not to impact operation of the Main Lift Station or the SJ-SC Recycled Water Facility.

B. City has considered these other contractors when determining the Contract Times and no additional time or compensation will be added to the Contract due to these other contractors.

1.13 Maintenace of Existing Facilites
A. Prior to replacement of the Forcemain-B ARV valves, the City will shut down pumping of wastewater to Forcemain-B. The City will be responsible for verifying shutdown and depressurization of the Forcemain-B. In the event there is a sewage spillover, the City Operations team will be responsible for treating the spillover.

1.14 Contingency Plan
A. Contractor will be responsible for capping at the end of everyday, so that in the event of an emergency, the City may turn on Forcemain-B. The City reserves the right to turn Forcemain-B on at any time.

1.15 Salvage of Equipment
A. The City has the right to salvage any items identified within the project vicinity.

B.
work.

C.

D. The Contractor shall be responsible for properly disconnecting, removal from their foundations, cleaning and storing salvaged items. Salvaged items shall be delivered by the Contractor to a storage location designated by the City.

E. All drop offs must be coordinated with the City.

Page 170 of 762 ends

38077.00180\29080232.10

-110- 00 73 13 SPECIAL CONDITIONS

END OF SPECIAL CONDITIONS

Page 171 of 762 ends

38077.00180\29080232.10

-111- 01 00 00 GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS
PART 1 GENERAL

1.1 DESCRIPTION
A. The scope of work for this project involves replacement of existing sewage air release valves and existing combination sewage air release and air vacuum valve assemblies, including concrete pads and utility covers on the City of Milpitas Main Lift Station Forcemain-B pipeline.

This project also includes demolition of existing and installation of new concrete pads, piping, valves, and security covers.

PART 2 (NOT USED)
PART 3 EXECUTION

3.1 LAYOUT OF WORK AND QUANTITY SURVEYS
A. General. The Contractor shall utilize a properly licensed surveyor to perform all layout surveys required for the control and completion of the Work, and all necessary surveys to compute quantities of Work performed.

City and/or the Engineer of Record has established primary control to be used by the Contractor for establishing lines and grades required for the Work.

Primary control consists of benchmarks and horizontal control points in the vicinity of the Work.A listing and identification of the primary control is provided on the Drawings. Before beginning any layout work or construction activity, the Contractor shall check and verify primary control, and shall advise the City Representative of any discrepancies.

B. Quantity surveys. The Contractor shall perform such surveys and computations as are necessary to determine quantities of Work performed or placed during each progress payment period, and shall perform all surveys necessary for the City Representative to determine final quantities of Work in place.The City Representative will determine final quantities based upon the survey data provided by the Contractor, and the design lines and grades.If requested by the City Representative, the Contractor shall provide an electronic copy of data used for quantity computations.

All surveys performed for measurement of final quantities of Work and material shall be subject to approval of City s Representative. Unless waived by City s Representative in each specific case, quantity surveys made by the Contractor shall be made in the presence of Representative.

C. Surveying

1. Accuracy. Degree of accuracy shall be an order high enough to satisfy tolerances specified for the Work and the following:
(a) Right-of-way and alignment of tangents and curves shall be within 0.1 foot.

Page 172 of 762 ends

38077.00180\29080232.10

-112- 01 00 00 GENERAL REQUIREMENTS

(b) Structure points shall be set within 0.01 foot, except where operational function of the special features or installation of metalwork and equipment require closer tolerances. When formwork has been placed and is ready for concrete, the Contractor shall check the formwork for conformance with the drawings and to ensure that the forms are sufficiently within the tolerance limits for the completed work.
(c) Cross-section points shall be located within 0.1 foot, horizontally and vertically. (d) Aerial Mapping shall meet National Mapping Standards for 2-foot contour intervals.

D. Records. Survey data shall be recorded in accordance with recognized professional surveying standards. Original field notes, computations, and other surveying data shall be recorded on electronic data collectors or in standard field books and must be of sufficient quality to enable the Contractor to prepare accurate record drawings as required by the Contract Documents.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required for surveys for the layout of work and quantity surveys shall be included in the Schedule of Pay Items for items of work requiring the surveys. No additional compensation shall be made to the Contractor for this Work.

3.2 SCHEDULE
A. Estimated Schedule. Within 21 Days after the issuance of the Notice of Award, Contractor shall prepare a Project schedule and shall submit this to the Engineer for Approval. The receipt or Approval of any schedules by the Engineer or the City shall not in any way relieve the Contractor of its obligations under the Contract Documents. The Contractor is fully responsible to determine and provide for any and all staffing and resources at levels which allow for good quality and timely completion
for the performance of the Contract or any inaccuracy in the schedule shall not excuse the Contractor from performing all Work required for a completed Project within the specified Contract time period. If the required schedule is not received by the time the first payment under the Contract is due, Contractor shall not be paid until the schedule is received, reviewed and accepted by the Engineer.

B. Schedule Contents. The schedule shall indicate the beginning and completion dates of all -critical activities. The schedule shall clearly identify all Project within the time specified for completion. The overall Project Schedule duration shall be within the Contract time.

C. Weather Allowance. The schedule shall allow adequate time for inclement weather.

D. Schedule Updates. Contractor shall continuously update its construction schedule. Contractor shall submit an updated and accurate construction schedule to the Engineer monthly when requested to do so by Engineer. Contractor shall also submit schedules showing a three week detailed look-ahead at bi-weekly meetings conducted with the City. The Engineer may withhold

Page 173 of 762 ends

38077.00180\29080232.10

-113- 01 00 00 GENERAL REQUIREMENTS

progress payments or other amounts due under the Contract Documents if Contractor fails to submit an updated and accurate construction schedule.

3.3 TEMPORARY FIELD OFFICE
A. . The installation of a field offices are subject to City Building Permit requirements.
shall be a substantial waterproof construction with adequate natural light and ventilation by means of stock design windows. Door shall have a key type lock or padlock clasp. The office shall have heating and air conditioning and shall be equipped with a telephone, a telephone answering machine, high-speed i
A table satisfactory for the study of plans and two chairs shall be provided by Contractor.

Contractor shall provide and pay for adequate electric lights, local telephone service, and adequate heat and air conditioning for the field office until authorized removal.

B. Utility Services. Contractor, at its expense, shall arrange for, develop and maintain all utilities, including but not limited to water, electric power, sewage disposal and telephone communications, at the Site to meet the requirements of the Work.

C. Sanitation. The Contractor shall provide sanitary facilities for all persons working on the project.

These facilities shall be kept clean and shall not be unsightly or produce odors.

3.4 PROTECTION OF WORK AND PROPERTY
A. All traffic detector loops, fences, walls, culverts, monuments, or other obstructions (except property line monuments within five (5) feet of the centerline of the mains) which are removed, damaged, or destroyed in the course of the Work, shall be replaced or repaired to the original condition at no additional cost to City. Contractor shall be responsible for the cost to repair, replace, relocate, and replacement of utilities whether or not those obstructions have been employ at its expense a Licensed Land Surveyor to restore all property line monuments located more than five (5) feet from the centerline of the mains, which are destroyed or obliterated.

Property line monuments located within five (5) feet of the centerline of the mains will be replaced by the City at no expense to the Contractor, provided the City is notified at least 48 hours before the property line monuments are damaged.

B. Contractor shall provide such heat, covering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.

C. Contractor shall take adequate precautions to protect existing sidewalks, curbs, pavements, utilities, and other adjoining property and structures, and to avoid damage thereto, and Contractor shall repair any damage thereto caused by the Work operations. Contractor shall:

1. Enclose the working area with a substantial barricade, and arrange work to cause minimum amount of inconvenience and danger to the public.

2. Provide substantial barricades around any shrubs or trees indicated to be preserved.

3. Deliver materials to the Project site over a route designated by the Engineer.

Page 174 of 762 ends

38077.00180\29080232.10

-114- 01 00 00 GENERAL REQUIREMENTS

4. Provide any and all dust control required and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, the City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.

5. Confine
workers to limits required by law, ordinances, permits, or directions of the Engineer.

Contractor shall not unreasonably encumber the Project site with its materials.

6. Take care to prevent disturbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by a civil engineer or land surveyor acceptable to the City, at no cost to the City.

7. Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to the City.

8. Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way.

9. At the completion of work each day, leave the Project site in a clean, safe condition.

10. Comply with any approved stage construction and traffic control plans. Access to residences and businesses shall be maintained at all times, unless otherwise permitted in writing by the City.

11. Cover and or protect work and project site as may be required to prevent or mitigate schedule delay and to allow work to proceed during wet weather or wet conditions.

D. These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefore.

E. Should damage to persons or property occur as a result of the Work, Contractor shall be responsible for proper investigation, documentation, including video or photography, to adequately memorialize and make a record of what transpired. The City shall be entitled to inspect and copy any such documentation, video, or photographs.

3.5 SITE CONDITIONS SURVEYS
A. Work Included.

Contractor shall conduct thorough pre-construction and post-construction site condition surveys of the entire project area. Site Conditions surveys shall include written documentation of the conditions found, as well as photographs and video recordings of the area within at least 80 feet of any construction area and staging area. The written notes, photographs, and video shall be suitable for forensic purposes to resolve any damage claims that may arise as a result of construction.

B. Submittals.

Page 175 of 762 ends

38077.00180\29080232.10

-115- 01 00 00 GENERAL REQUIREMENTS

1. Written documentation of site condition survey at pre-construction and post-construction.

2. Photographs as described herein of pre-construction and post-construction conditions.

3. Video recordings as described herein of pre-construction and post-construction conditions.

4. Submittals shall be made within three days of the surveys. All post-construction data shall be submitted prior to the final project inspection.

C. Site Condition Written Documentation.

Written documentation shall include the time, date, and conditions under which the site survey was made. The documentation shall note the condition of structures, pavement, sidewalks, utilities, fences, and etc. within the work areas.

D. Photographs & Video Recording.

1. General Prior to starting Work, Contractor shall provide a video recording of the project site. Contract shall take enough photographs during each site survey to provide a record of conditions existing prior to construction and conditions after construction. Pre- construction video and photographs shall be taken prior to any construction or mobilization of equipment, but not more that one week prior to actual start of work. The pre-construction photographs may be staged at different times to match the progression of the Work.

2. The photographs shall document existing damage to public and private facilities, both prior to and after construction. Conditions to be documented include, but are not limited to: sidewalk cracks, broken curbs, separated property walls, improvements within public right-of-ways, access roads used, utility covers and markings, signs, pavement striping, pavement, unique or unusual conditions, adjacent driveways, landscaping, survey markers, and any feature directed by the Engineer. Private property that is adjacent to the public right-of-way shall be documented to the extent visible from the public right-of- way.

3. Photographs shall include items to indicate scale, as needed. In particular, scales or other items shall be laid next to close ups of structural cracks and other damaged areas being recorded. Scaling shall also be used to document elevation differences, as needed.

4. One set of color prints and the preconstruction site video shall be submitted. Additional sets shall be available for reviewing in settling any construction disputes. A set of photos shall also be furnished in electronic format. The resolution shall be at least equal to 7 mega-pixels. All photos shall be documented as to time and date taken, photographer, project number, location, and orientation. Documentation shall include a brief description of objects photographed.

E. Video Recording.

1. Video recordings shall document the conditions of the entire area affected by construction, as well as nearby structures and facilities. The general documentation

Page 176 of 762 ends

38077.00180\29080232.10

-116- 01 00 00 GENERAL REQUIREMENTS

requirements for videos are the same as for photographs. Video recorders shall accurately and continuously record the time and date.

2. Video recordings shall include an audio portion made simultaneously during the videoing.

The audio recording shall describe the location, time, orientation, and objects being recorded. Special commentary shall be provided for unusual conditions or damage noted.

3. Video equipment shall be capable of producing high resolution images and shall have zoom capabilities.

4. Video recordings shall provide an overall picture of the sites and shall provide detailed images of damaged areas. Video shall extend to the maximum height of structures.

5. The Engineer shall have the right to reject any audio video recordings submitted with unintelligible audio, uncontrolled pan or zoom, or of poor quality. Video recordings shall be repeated when rejected.

6. Video recordings shall be submitted with labels indicating the project, date, recorder, and other pertinent information. Recordings shall be submitted on standard DVDs in a standard format.

F. Timing.

Contractor shall provide written notice of the time scheduled for the site conditions survey and condition survey. The Engineer reserves the right to cancel the survey due to weather conditions or other problems. Videoing shall be done during times of good visibility and no videoing or photography shall be done during periods of visible precipitation or when standing water obscures pavement. Contractor shall provide the Engineer with an opportunity to have a representative present when taking the photos and provide guidance during photographing.

G. Site Surveyor.

The site condition surveyor(s) shall be experienced in construction and potential damage concerns. The site condition surveyor(s) shall be familiar with the photography and video equipment being used.

H. Field Quality Control.

Prior to submitting videos and photographs, the Contractor shall spot check the photos and videos in the field to insure they accurately reflect the actual conditions and to insure they are correctly labeled.

I. Soils Compaction Testing.

1. All soils compaction testing will be done by a licensed geotechnical engineer furnished by the City. Soils compaction testing will be done for all footings and foundations prior to placement of rebar or concrete.

Page 177 of 762 ends

38077.00180\29080232.10

-117- 01 00 00 GENERAL REQUIREMENTS

2. For pipeline construction, soil compaction testing will be done at 100-foot intervals or as ordered by the project soils/geotechnical report at the bottom of the trench prior to placement of pipe bedding; at the top of the pipe bedding above the pipe; every two vertical feet of trench backfill or as otherwise ordered by the project soils/geotechnical report; at the top of the trench backfill, which sould be the bottom of the pavement section; and at the top of the aggregate base prior to pavement construction.

3.6 SUBMITTAL REQUIREMENTS FOR MANUALS AND RECORD DRAWINGS A. General. The Contractor shall furnish all materials and perform all Work required for furnishing submittals to City in accordance with Contract Documents.The Contractor shall submit Project Record Drawings, Technical Manual, Spare Parts, and other required items within 5 days following completion of project construction, and prior to Contractors request for Project Acceptance.

B. Technical Manuals.

1. The Contractor shall submit technical operation and maintenance information for each item of mechanical, electrical and instrumentation equipment in an organized manner in the Technical Manual. It shall be written so that it can be used and understood by operation and maintenance staff.

2. The Technical Manual shall be subdivided first by specification section number; second, by equipment item; and last, by "Category." The Contractor shall furnish to City four (4) identical Technical Manuals. Each set shall consist of one or more volumes, each of which shall be bound in a standard binder.

C. Spare Parts List - The Contractor shall furnish to City six (6) identical sets of spare parts information for all mechanical, electrical, and instrumentation equipment. The spare parts list shall include the current list price of each spare part. The spare parts list shall include those spare parts which each manufacturer recommends be maintained by City in inventory. Each manufacturer or supplier shall indicate the name, address, and telephone number of its nearest outlet of spare parts to assist City in ordering. The Contractor shall cross-reference all spare parts lists to the equipment numbers designated in the Contract Documents. The spare parts lists shall be bound in standard size, 3-ring binder.

D. Record Drawings

1. The Contractor shall maintain one record set of Drawings at the Site. On these, it shall mark all Project conditions, locations, configurations, and any other changes or deviations which may vary from the information represented in the original Contract Documents, including buried or concealed construction and utility features which are revealed during the course of construction. Special attention shall be given to recording the horizontal and vertical location of all buried utilities that differ from the locations indicated, or which were not indicated on the Contract Drawings. Said record drawings shall be supplemented by any detailed sketches as necessary or directed to fully indicate the Work as actually constructed. These master record drawings of the as-built conditions, including all revisions made necessary by Addenda and Change Orders shall be maintained up-to-date during the progress of the Project. Red ink shall be used for alterations and notes. Notes shall identify relevant Change Orders by number and date.

Page 178 of 762 ends

38077.00180\29080232.10

-118- 01 00 00 GENERAL REQUIREMENTS

2. For all Projects involving the installation of any pipeline, Contractor shall survey and record the top of the pipe at a minimum of every 100 linear feet, and at each bend, recording both the horizontal and vertical locations.

3. Record drawings shall be accessible to Representative at all times during the construction period. The record drawings shall be kept up to date and will be checked by the City prior to each progress payment.
record drawings current could result in withholding partial payment.

4. Upon Completion of the Project and as a condition of final acceptance, the Contractor shall finalize and deliver a complete set of Record Drawings to City s Representative. The information submitted by the Contractor will be assumed to be correct, and the Contractor shall be responsible for, and liable to City, for the accuracy of such information, and for any errors or omissions which may or may not appear on the Record Drawings.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete the Manuals and Record Drawings shall be included in bid and distributed in the Schedule of Pay. No additional compensation shall be made to the Contractor for this Work.

3.7 MATERIALS
A. Materials to be Furnished by the Contractor

1. Inspection of Materials. Materials furnished by the Contractor which will become a part of the Project shall be subject to inspection at any one or more of the following locations, as determined by City Representative: at the place of production or manufacture, at the shipping point, or at the site of the Work. To allow sufficient time to provide for inspection, the Contractor shall submit to City Representative, at the time of issuance, copies of purchase orders or other written instrument confirming procurement of the materials, including drawings and other pertinent information, covering materials on which inspection will be made.

2. No later than fourteen (14) Days prior to manufacture of material, Contractor shall inform City Representative, in writing, the date the material is to be manufactured.

3. Contractors Obligations. The inspection of materials at any of the locations specified above or the waiving of the inspection thereof shall not impact whether the materials and equipment conform to the Contract Documents. Contractor will not be relieved from furnishing materials meeting the requirements of the Contract Documents due to City inspection or lack of inspection of the equipment or materials. Acceptance of any materials will be made only after materials are installed in the Project.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to accommodate City testing efforts, including any travel required by s, shall be included in and distributed in the Schedule of Pay Items related to the materials requiring testing. No additional compensation shall be made to the Contractor for this Work.

3.8 LOCAL CONDITIONS AND REQUIREMENTS

Page 179 of 762 ends

38077.00180\29080232.10

-119- 01 00 00 GENERAL REQUIREMENTS

A. Access to Work and Haul Routes

1. General. All work on the rights-of-way necessary for access to the Site shall be performed by the Contractor. Contractors anticipated Haul Routes shall be in compliance with the City's approved Truck Routes available from the Engineer.

2. Access, Damage, Restoration. The Contractor shall make his own investigation of the condition of available public or private roads and of clearances, restrictions, bridge-load limits, permit or bond requirements, and other limitations that affect or may affect transportation and ingress or egress at the Site.

3. The Contractor shall maintain and repair any damage arising out of operations to all roads used during construction of the Project, and upon completion of all Work, but prior to final acceptance, the roads shall be restored to their original condition. Prior to using any road for access to the Site, the Contractor shall conduct a photograph and/or video survey of the roadway with a copy submitted to City Representative.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

B. Power. Contractor shall provide at its own expense all necessary power required for operations under the contract. The Contractor shall provide and maintain in good order such modern equipment and installations as shall be adequate in the opinion of the Engineer to perform in a safe and satisfactory manner the Work required by the contract.

C. Construction Water.

1. Construction water shall not be used for purposes other than those required to satisfactorily complete the contract.

2. Construction recycled water will be made available to the contractor from one of three fill locations within the city limits. If there is a need for construction recycled water during construction, the contractor shall apply for a city construction recycled water meter at the city hall finance counter prior to the beginning of work. A security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. if the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

3. Construction potable water will only be made available to the contractor if it can be demonstrated that recycled water cannot be used for the construction activities. potable water will be made available from existing city fire hydrant(s) nearest the proposed construction site as approved by the engineer, or by such other means as may be expressly approved in writing by the engineer. If there is a need for water during construction, the contractor shall apply for a city construction water meter at the city hall finance counter prior to the beginning of work. a security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be

Page 180 of 762 ends

38077.00180\29080232.10

-120- 01 00 00 GENERAL REQUIREMENTS

deducted. If the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

4. All required water, all work and materials required for obtaining, pumping, transporting and applying and otherwise disposing of said water shall be in an approved manner and shall be performed by, and at the expense of the contractor and no extra or separate compensation will be made thereof.

D. Operation of Existing Water Facilities

1. The Contractor shall not operate any of the existing water systems, including pumps, motors, valves, and hydrants, but shall contact the City two (2) working days in advance with a list and location of the water system facilities that will require operating, opening, stopping, or closure by the City.

2. At the option of the Engineer, the Contractor may be permitted to operate valves for the purpose of making connections to existing mains. The City will perform all notification to existing customers regarding temporary loss of service.

3. -down of existing
water facilities.

E. Construction at Existing Utilities

1. General. Where the Work to be performed crosses or otherwise interferes with water, sewer, gas, or oil pipelines; buried cable; or other public or private utilities, the Contractor shall perform construction in such a manner so that no damage will result to either public or private utilities. It shall be the responsibility of the Contractor to determine the actual locations of, and make accommodates to maintain, all utilities.

2. Permission, Notice and Liability. Before any utility is taken out of service, permission shall be obtained by the Contractor from the owner. The owner, any impacted resident or business owner and the City Representative will be advised of the nature and duration of required by the owner. The Contractor shall be liable for all damage which may result from its failure to maintain utilities during the progress of the Work, and the Contractor shall indemnify City as required by the Contract Documents from all claims arising out of or connected with damage to utilities encountered during construction; damages resulting from disruption of service; and injury to persons or damage to property resulting from the negligent, accidental, or intentional breaching of utilities.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

F. Traffic Control

1. General. Contractor shall abide by traffic control plans approved by the City.

Page 181 of 762 ends

38077.00180\29080232.10

-121- 01 00 00 GENERAL REQUIREMENTS

2. Protections. Roads subject to interference by the Work shall be kept open or suitable temporary passages through the Work shall be provided and maintained by the Contractor. The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient flasher lights, flag persons, danger signals, and signs, and shall take all necessary precautions for the protection of the Work and the safety of the public. No construction work along public or private roads may proceed until the Contractor has proper barricades, flasher lights, flag persons, signals, and signs in place at the construction site.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

G. Cleaning Up

1. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equipment. Contractor shall not store debris under, in, or about the premises. Contractor shall also clean all asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment, including all USA markings. The use of water, resulting in mud on streets, will not be permitted as substitute for sweeping or other methods. Dust control may require having a water truck onsite for the duration of the project, and/or use of temporary hoses and pipelines to convey water.

2. Contractor shall fully clean up the site at the completion of the Work. If the Contractor fails to immediately clean up at the completion of the Work, the City may do so and the cost of such clean up shall be charged back to the Contractor.

3.9 ENVIRONMENTAL QUALITY PROTECTION
A. Environmental Conditions

1. Contractor must comply with all applicable environmental laws, Project conditions, and constraints.

2. City has considered these Environmental Conditions when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Conditions.

3. City to file for and obtain CEQA exemption from County of Santa Clara.

B. Landscape and Vegetation Preservation

1. General. The Contractor shall exercise care to preserve the natural landscape and vegetation, and shall conduct operations so as to prevent unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the Work.

2. Damage and Restoration. Movement of crews and equipment within the rights-of-way and over routes provided for access to the Work shall be performed in a manner to prevent

Page 182 of 762 ends

38077.00180\29080232.10

-122- 01 00 00 GENERAL REQUIREMENTS

damage to property. When no longer required, construction roads shall be restored to original contours.

3. Upon completion of the Work, and following removal of construction facilities and required cleanup, land used for construction purposes and not required for the completed installation shall be scarified and regraded, as required, so that all surfaces are left in a condition that will facilitate natural revegetation, provide for proper drainage, and prevent erosion.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

C. Protected Species

1. General. If, in the performance of the Work, evidence of the possible occurrence of any State or Federally listed threatened or endangered plant or animal is discovered, the Contractor shall notify the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the endangered plant or animal.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Any City directed changes to the Work as a result of a siting will be pursuant to the Contract Documents.

3. False Siting. Any costs or delays incurred by City or the Contractor due to unreasonable or false notification of an endangered plant or animal will be borne by the Contractor.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

D. Preservation of Historical and Archeological Resources

1. General. If, in the performance of the Work, Contractor should unearth cultural resources (for example, human remains, animal bones, stone tools, artifacts and/or midden deposits) through excavation, grading, watering or other means, the Contractor notify the Construction/Archeological Monitor and/or the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to the Construction/Archeological Monitor and/or City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the cultural resource.

Page 183 of 762 ends

38077.00180\29080232.10

-123- 01 00 00 GENERAL REQUIREMENTS

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or re-sequence and/or alter its performance to ensure full compliance with all applicable permits, laws and regulations.

Should the presence of cultural resources be confirmed, the Contractor will assist the City Representative and the Construction/Archeological Monitor in the preparation and implementation of a data recovery plan. The Contractor shall provide such cooperation and assistance as may be necessary to preserve the cultural resources for removal or other disposition. Any City directed changes to the Work as a result of the cultural resource will be pursuant to the Contract Documents.

3. Liability. Should Contractor, without permission, injure, destroy, excavate, appropriate, or remove any cultural resource on or adjacent to the Site, it will be subject to disciplinary action, arrest and penalty under applicable law. The Contractor shall be principally responsible for all costs of mitigation and/or restoration of cultural resources related to the unauthorized actions identified above. Contractor shall be required to pay for unauthorized damage and mitigation costs to cultural resources (historical and archeological resources) as a result of unauthorized activities that damage cultural resources and shall indemnify City pursuant to the Contract Documents.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

E. Dust and Pollution Control

1. Contractor shall provide all necessary material, equipment and labor to prevent and control the emission of dust and any other potential pollutant on site. Contractor shall remove construction caused debris from streets and sidewalks as directed by the Engineer.

2. Contractor shall not discharge into the atmosphere from any source smoke, dust or other air contaminants in violation of the law, rules, and regulations of the governing agency.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

F. Management of Storm, Surface and Other Waters

1. Storm water, surface water, groundwater, and nuisance, or other waters may be encountered at various times during construction of the Project. Federal and State laws require the City and its contractors to manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ, the Federal Clean Water Act, and the California Porter Cologne Water Quality Control Act.

Contractor acknowledges that it has investigated the risk arising from such waters in conjunction with the Project, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

Page 184 of 762 ends

38077.00180\29080232.10

-124- 01 00 00 GENERAL REQUIREMENTS

2. The Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all
water; the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.); the California Porter-Cologne Water Quality Control Act (Water Code § 13000 et seq.); and any and all regulations, policies, or permits issued pursuant to any such authority. These include, but are not limited to the San Francisco Bay Regional Water Quality Control Board Order No. R2-2015-0049 (NPDES Permit No. CAS 612008), and State Water Resources Control Board Order No. 2010-0014-DWQ, Order No. 2009-0009-DWQ, and Order No. 2012-0006-DWQ, and any amendment or renewal thereof
. Contractor must perform all construction operations in such a manner as to comply, and ensure all subcontractors to comply, with all applicable Federal, State, and local laws, orders, and regulations concerning the control and abatement of water pollution; and all terms and conditions of any applicable permits issued for the Project. In the event there is a conflict between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.

3. Compliance with Construction General Permit. Contractor must comply with all aspects of the Construction General Permit, State Water Resources Control Board (State Board) Water Quality Order No. 2009-0009-DWQ, as amended by Order Nos. 2010-0014-DWQ and 2012-0006-DWQ, and any amendment or renewal thereof (NPDES CAS000002), for all projects that involve construction on or disturbance of one acre or more of land or which are part of a larger common plan of development or sale. (a) Permit registration. Unless otherwise specified in the Special Conditions, Contractor must prepare the Notice of Intet for coverage under the Construction General Permit and all Permit Registration Documents (PRDs), including but not limited to the Storm Water Pollution Prevention Plan (SWPPP), as those terms are defined in the Construction General Permit. Contractor must coordinate Authorized Signatory, as those terms are defined in the Construction General Permit. The Contractor must submit the PRDs, including the SWPPP to the City Representative for review not less than fifteen (15) Days prior to the start of on- site construction work. City will file the Notice of Intent and PRDs and pay the filing fee.
(b) Before any Construction General Permit related documents may be submitted to the State Board or implemented on the Project site, they must first be reviewed and accepted by City. Acceptance by the City does not relieve the Contractor from ensuring such documents comply with all lawsapplicable laws, regulations, and orders.
(c) Contractor must ensure that the SWPPP is developed by a Qualified SWPPP Developer and implemented by a Qualified SWPPP Practitioner as those terms are defined in the Permit. Contractor must implement the SWPPP and all other provisions of the Construction General Permit, including the monitoring and reporting requirements, preparing and submitting all reports, plans, inspections, and monitoring information in compliance with the Construction General Permit.

Page 185 of 762 ends

38077.00180\29080232.10

-125- 01 00 00 GENERAL REQUIREMENTS

The SWPPP must include industry standard requirements for water quality control including but not be limited to the following:
(1) Sediment and erosion control measures to manage sediment and erosion including vegetative practices, structural control, silt fences, straw dikes, sediment controls or operator controls as appropriate.Storm water management measures shall be instituted as required, including velocity dissipaters, and solid waste controls shall address controls for building materials and offsite tracking of sediment.
(2) Wastewater and storm water management controls to divert offsite surface flows around the Project site and to divert surface flows within the Project area away from areas of open earth or stockpiles of building and other materials. Wastewater from general construction activities, such as drain water collection, aggregate processing, concrete batching, drilling, grouting, or other construction operations, shall not enter flowing or dry watercourses without having met the authorized non-storm water discharge requirements listed in State Board Water Quality Order No. 2009-0009-DWQ, Section III.C., including proper notification to the Regional Water Board.
(3) Pollution prevention measures including methods of dewatering, unwatering, excavating, or stockpiling earth and rock materials which include prevention measures to control silting and erosion, and which will intercept and settle any runoff of sediment-laden waters. (4) Turbidity prevention measures for prevention of excess turbidity including, but are not restricted to, intercepting ditches, settling ponds, gravel filter entrapment dikes, flocculating processes, recirculation, combinations thereof, or other approved methods that are not harmful to aquatic life. All such wastewaters discharged into surface waters, shall contain the least concentration of settleable material possible, and shall meet all conditions of section 402, the National Pollutant Discharge Elimination System (NPDES) permit.
(5) Overall construction site management measures to address changes at the Project site as the Project moves through different phases and changes that account for rainy and dry season management practices. (6) Pollution control measures and construction activity methods that will prevent entrance, or accidental spillage, of solid matter, contaminants, debris, or other pollutants or wastes, into streams, flowing or dry watercourses, lakes, wetlands, reservoirs, or underground water sources.

Such pollutants and wastes include, but are not restricted to: refuse, garbage, cement, sanitary waste, industrial waste, hazardous materials, radioactive substances, oil and other petroleum products, aggregate processing, tailings, mineral salts, and thermal pollution. (7) Control measures for stockpiled or deposited materials prohibiting the stockpile or deposit of excavated materials, or other construction

Page 186 of 762 ends

38077.00180\29080232.10

-126- 01 00 00 GENERAL REQUIREMENTS

materials, near or on stream banks, lake shorelines, or other watercourse perimeters where they can be washed away by high water or storm runoff, or can, in any way, encroach upon the watercourse.
(8) Develop and implement a Rain Event Action Plan (REAP), if required, that must be designed and implemented to protect all exposed portions of the site 48 hours prior to any likely precipitation event.
(9) Monitoring, reporting and record keeping, as necessary to achieve compliance with applicable Permit requirements, including but not limited to annual reports and rain event reports.
(d) City retains the right to procure and maintain coverage under the Construction General Permit for the Project site if the Contractor fails to draft a SWPPP or other Construction General Permit related document, or fails to proceed in a manner that is satisfactory to City. City reserves the right to implement its own SWPPP at the Project site, and hire additional contractors to maintain compliance. Whether Contractor has adequately maintained compliance with the Construction General le determination. In the event that Contractor has failed or is unable to maintain compliance with the Construction General Permit, any costs or fines incurred by City in implementing a SWPPP, or otherwise maintaining compliance with the Construction General Permit shall be paid by the Contractor.

4. For those Work sites where construction activity results in the disturbance of less than one acre of total land area and/or do not need coverage under the Construction General Permit, the Contractor shall be responsible for preparing and implementing construction industry best management practices to eliminate or reduce the discharge of pollutants from construction sites, such as the best management practices set forth in the CASQA Construction BMP Handbook.

5. In addition to compliance with the Permit, Contractor shall comply with the lawful requirements of any applicable municipality, district, drainage district, flood control district, and other local agencies regarding discharges of storm water, surface water, groundwater or other nuisance waters off of the Project site.

6. Contractor violations.
(a) Failure to implement the SWPPP or otherwise comply with the Construction General Permit or local state and federal laws is a violation of this Contract.

Notwithstanding any other indemnity contained in this Agreement, Contractor agrees to indemnify, defend with counsel acceptable to the City and hold harmless the City, its officials, officers, agents, employees and authorized volunteers from and against any and all claims, demands, losses or liabilities of any kind or nature which the City, its officials, officers, agents, employees and authorized volunteers may sustain or incur for noncompliance with the laws, regulations, and ordinances listed above, arising out of or in connection with the Work, except for liability resulting from the sole established negligence, willful misconduct or active negligence of the City, its officials, officers, agents, employees or authorized volunteers.

Page 187 of 762 ends

38077.00180\29080232.10

-127- 01 00 00 GENERAL REQUIREMENTS

(b) City reserves the right to defend any enforcement action or civil action brought law, regulation, or policy. Contractor hereby agrees to be bound by, and to reimburse the City for the costs associated with, any enforcement action and/or settlement reached between the City and any relevant enforcement entity. (c) City may seek damages from Contractor for delay in completing the Contract in comply with the the laws, regulations and policies described in this Article, or any other relevant water quality law, regulation, order, or policy. (d) If noncompliance with any relevant law, regulation or permit, order, or policy occurs, the Contractor shall report this to the City Representative immediately, with the specific information submitted in writing within 2 Days. Consistent violations of applicable Federal, State, or local laws, orders, regulations, or Water Quality Standards may result in City stopping all site activity until compliance is ensured. The Contractor shall not be entitled to any change in Contract Price or Contract Times, claim for damage, or additional compensation by reason of such a work stoppage. Corrective measures required to bring activities into compliance shall be at the Contractor's expense.

7. Oil storage tanks management.
(a) Storage tank placement. All oil or other petroleum product (hereinafter referred to collectively as oil) storage tanks shall be placed at least 20 feet from streams, flowing or dry watercourses, lakes, wetlands, reservoirs, and any other water source.
(b) Storage area dikes. Storage areas shall be diked at least 12 inches high or graded and sloped to permit safe containment of leaks and spills equal to the capacity of all tanks and/or containers located within each area, plus a sufficient amount of freeboard to contain the 25-year rainstorm.
(c) Diked area barriers. Diked areas shall have an impermeable barrier at least 10 mils thick. Areas used for refueling operations shall have an impermeable liner at least 10 mils thick buried under 2 to 4 inches of soil. (d) Spill Prevention Control and Countermeasure Plan (SPCC). Where the location of a construction site is such that oil from an accidental spillage could reasonably be expected to enter into or upon the navigable waters of the United States or adjoining shorelines, and the aggregate storage of oil at the site is over 1,320 gallons or a single container has a capacity in excess of 660 gallons, the Contractor shall prepare an SPCC Plan. The Contractor shall submit the SPCC Plan to the Engineer at least 30 days prior to delivery or storage of oil at the site.

The Plan must have been reviewed and certified by a registered professional engineer in accordance with 40 C.F.R., part 112

8. Underground tank prohibition. The Contractor shall not use underground storage tanks.

Page 188 of 762 ends

38077.00180\29080232.10

-128-

9. Construction safety standards. The Contractor shall comply with the sanitation and potable water requirements of Section 7 of United States Bureau of Reclamation's

10. Other Permits.
(a) Other permits applicable to the Project are listed in the Special Conditions. The Contractor shall obtain all other necessary licenses and permits. (b) Monitoring. The Contractor is required to conduct monitoring in order to meet the requirements of the permits, which may include sampling, testing and inspections. (c) Recordkeeping. The Contractor shall retain all records and data required by the permits for the time specified in the contract.

11. Cost. Except as specified herein, the cost of complying with this section shall be included in the Schedule of Pay Items for work which necessitate the water pollution prevention measures required by this paragraph.

END OF GENERAL REQUIREMENTS

Page 189 of 762 ends

38077.00180\29080232.10

-129- 01 20 00 MEASUREMENT AND PAYMENT

01 20 00 MEASUREMENT AND PAYMENT
PART 1 GENERAL

1.1 SUMMARY
A. This section describes requirements and procedures for determining amount of work done and for obtaining payment for work done.

1.2 REFERENCES
A. California Public Contract Code

1.3 SCOPE OF WORK
A. Work under Contract Documents, or under any bid item, allowance or alternate, or Change Order shall include all labor, materials, transport, handling, storage, supervision, administration, and all other incidental work necessary for the satisfactory completion of Work, whether or not expressly specified or shown.

1.4 DETERMINATION OF QUANTITIES
A. Quantity of work to be paid for under any item for which a unit price is fixed in Contract Documents shall be the number, as determined by City, of units of work satisfactorily completed in-place, and suitable for its intended purpose free of defects or poor workmanship in accordance with Contract Documents or as directed by City. Unless otherwise provided, determination of number of units of work so completed will be based, so far as practicable, on actual measurement or count within prescribed or ordered limits, and no payment will be made for work done outside of limits. Measurements and computations will be made by methods as City may consider appropriate for class of work measured. Contractor shall immediately inform City of any disputes regarding quantity measurements and shall immediately supply City with any documentation supporting the disputed measurements.

B. Before ordering any materials or doing any work, the Contractor shall verify all measurements, dimensions, elevations and quantities. No extra charge or compensation over and above payment for the actual quantities of the various items of work at the respective bid prices therefore will be allowed on account of difference between actual measurements, dimensions, elevations and quantities, and those indicated on the drawings, or in the specifications, and any difference therein shall be submitted to the City for consideration before proceeding with the work.

1.5 SCOPE OF PAYMENT
A. Payment to Contractor at the unit price or other price fixed in the contract for Work as described in Paragraph 1.3 above shall be full compensation for completing, in accordance with Contract Documents, all work required under the item or under Contract Documents, and for all expense incurred by Contractor for any purpose in connection with the performance and completion of said work, including all incidental work necessary for completion of the Work.

Page 190 of 762 ends

38077.00180\29080232.10

-130- 01 20 00 MEASUREMENT AND PAYMENT

B. Unless Contract Documents expressly provide otherwise, the Contract Sum shall be deemed to include:

1. Any and all costs arising from any unforeseen difficulties, which may be encountered during, and all risks of any description connected with, prosecution of Work, bid item or unit price item, respectively, until acceptance by City;

2. All expenses incurred due to suspension, or discontinuance of Work, bid item or unit price item, respectively, as provided in Contract Documents;

3. Inflation and/or Escalation to allow for cost increases between time of Contract Award and completion of Work, bid item or unit price item, respectively.

C. Whenever it is specified herein that Contractor is to do work or furnish materials of any class for which no price is fixed in Contract Documents, it shall be understood that Contractor is to do such work or furnish such materials without extra charge or allowance or direct payment of any sort, and that cost of doing work or furnishing materials is to be included in price bid, unless it is expressly specified herein, in particular cases, that work or material is to be paid for as extra work.

D. No payment shall be made for materials or equipment not yet incorporated into the Work.

E. Where Contractor requests payment for materials and equipment not incorporated in the Work, Contractor must satisfy the following conditions:

1. The materials and/or equipment shall be delivered and suitably stored at the site or at another local location agreed to in writing, for example, a mutually acceptable warehouse;

2. Full title to the materials and/or equipment shall vest in City at the time of delivery to the site, warehouse or other storage location;

3. Contractor shall obtain a negotiable warehouse receipt, endorsed over to City for materials and/or equipment stored in an off-site warehouse. No payment shall be made until such endorsed receipts are delivered to City.

4. Stockpiled materials and/or equipment shall be available for City inspection, but City shall have no obligation to inspect them and its inspection or failure to inspect shall not relieve Contractor of any obligations under the Contract Documents. Materials and/or equipment shall be segregated and labeled or tagged to specifically identify these specific Contract Documents;

5. After delivery of materials and/or equipment, if any inherent or acquired defects are discovered, defective materials and/or equipment shall be removed and replaced with

6. At its expense, Contractor shall insure the materials and/or equipment against theft, fire, Contract Documents;

7. other documentation warranting that City has received the materials and equipment free and clear of all liens and evidence that the materials and equipment are covered by all of which must be satisfactory to City. This documentation shall include, but not be all those

Page 191 of 762 ends

38077.00180\29080232.10

-131- 01 20 00 MEASUREMENT AND PAYMENT

providing materials and equipment as to which the application for payment relates, as well as unconditional releases of the same from the same as to the previous application for payment for which they have not already been provided.

1.6 BASIS OF PAYMENT
A. Lump Sum: When estimated quantity for specific portion of Work is not indicated and unit is designated as Lump Sum, payment will be based on the approved Schedule of Values of the work under the lump sum, or in the event a Schedule of Values is not required, on the percentage of the lump sum scope satisfactorily completed.

B. City does not expressly, or by implication, agree, warrant, or represent in any manner, that actual amount of Work will correspond with amount shown or estimated and reserves right to increase or decrease amount of any class or portion of Work, to leave out entire Bid Item or Items, or to add work not included in Bid, when in its judgment such change is in best interest of City. No change in Work shall be considered waiver of any other condition of Contract Documents. No claim shall be made for anticipated profit, for loss of profit, for damages, or for extra payment whatever, except as otherwise expressly provided for in Contract Documents, because of any differences between amount of work actually done and estimated amount as set forth herein, or for elimination of extra Bid Items.

1.7 SCHEDULE OF VALUES AND PROGRESS PAYMENTS
A. If requested by Contractor, progress payments will be made monthly, but not more often than monthly.

B. Schedule of Values:

1. Form to be used: AIA G703 or as approved by the City

2. Within twenty-one (21) calendar days from issuance of Notice of Award and prior to the Schedule of Values, which is a detailed breakdown of its bid for Work items and/or activities, including coordination responsibilities and project record document responsibilities. Where more than one subcontractor comprises the work of a work item or activity, the Schedule of Values shall show a separate line item for each subcontract.

Contractor shall furnish such breakdown by assigning dollar values (cost estimates) to each applicable Progress Schedule network activity, whose cumulative sum equals the total Contract Sum. The format and detail of the breakdown shall be as directed by City to facilitate and clarify future progress payments to Contractor for Work under Contract Documents. Work with lump sum values shall not exceed $10,000 per work item. Work values totaling more than $10,000 per item shall be broken down on a unit basis (e.g., linear foot, square yard, cubic yard, etc.). No line item to exceed one-half of 1% (0.5%) of contract value.

3. cleanup and maintenance, temporary roads and access, off site access roads, temporary power and lighting, security and the like), shall be prorated through all activities so that

Page 192 of 762 ends

38077.00180\29080232.10

-132- 01 20 00 MEASUREMENT AND PAYMENT

Insurances and Bonds shall be a separate schedule of value line item.

4. Include in each line item, the amount of Allowances specified in this section. Separately identity each Allowance and Alternate item, provide breakdown where any one item is in excess of one-half of 1% (0.5%) of contract value.

5. City will review the breakdown in conjunction with the approved progress schedule activities to ensure that the dollar amounts of the Schedule of Values are, in fact, fair market cost allocations for the Work items listed. Upon favorable review by City, City will accept this Schedule of Values for use. City shall be the sole judges of fair market cost allocations.

6. Any attempt to unbalance the distribution of overhead, profit, and other fixed costs, or to manipulate the cost breakdown in any way, or to increase the cost of early activities, i.e. ocation of monies until
such distortion is corrected. Repeated attempts of manipulation may result in suspension or termination of the Work or refusal to process progress payments, until such time as the Schedule of Values is acceptable to City.

C. Payment Requests

1. Form to be used: AIA G702 and G703.

2. For each item, provide a column for listing each of the following:
a. Item Number.
b. Description of work.
c. Scheduled Values.
d. Previous Applications.
e. Work in Place and Stored Materials under this Application. f. Authorized Change Orders.
g. Total Completed and Stored to Date of Application.
h. Percentage of Completion.
i. Balance to Finish.
j. Retainage.

3. A monthly itemized estimate of Work done for the purpose of making progress payments.

In order for the City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.

4. On or before the twenty-fifth (25 th
of the updated schedule as required by Section 01 32 00, Contractor shall meet with the City Representative to measure and verify quantities of work completed which Contractor requests payment for. The Contractor shall submit to City two (2) copies of a request for payment for the cost of the Work put in-place at that time, along with one (1) copy of the City approved updated CPM schedule. Such requests for progress payments shall be based upon Schedule of Values prices of all labor and materials incorporated in the Work up until midnight of the last day of that one-month period, less the aggregate of previous payments. If Contractor is late submitting its payment request, that payment request may be processed at any time during the succeeding one-month period, resulting in

Page 193 of 762 ends

38077.00180\29080232.10

-133- 01 20 00 MEASUREMENT AND PAYMENT

basis.

5. Payment requests may include, but are not necessarily limited to the following:
a. Material, equipment and labor incorporated into the Work, less any previous payments for the same.

6. With each request for payment, Contractor shall fulfill all scheduling requirements of Contractor shall execute and submit the following certification shown below:

_______________________________ (Contractor), the undersigned Contractor, certifies that the Work covered by this request for payment (invoice) has been completed in accordance with the Contract Documents, and that the current progress payment (invoice) shown herein is accurate and now due. Contractor further certifies that all amounts have been paid by the Contractor for Work for which previous invoices for progress payments issued to and paid by the City. The Contractor declares under penalty of perjury under the laws of the State of California, and do personally certify and attest that: I have thoroughly reviewed the attached request for payment (invoice) and know its contents, and said request for payment is made in good faith; that it is supported by truthful and accurate data; that the amount requested accurately reflects the allowable expenses incurred to perform the Work.

signature & date

7. No progress payment will be processed prior to City receiving the above certification and all requested and acceptable schedule update information.

8. With each request for payment, Contractor shall submit following as pre-requisite to its

a. Construction progress schedule, updated to current.
b. Current construction photographs, updated to current. c. Partial release of liens from major subcontractors and vendors. d. Progress project record documents, updated to current. e. Affidavits and bonds attesting to off-site stored products, if any. f. Certified payroll records.
g. Statement under False Claim Act.

9. Contractor shall submit fulfill all record document requirements of Section 01 78 39, progress payment requests may be withheld in the event that the City determines that the job-site record drawings have not been kept up-to-date. Contractor also to submit the following pre-requisites for review of the Payment Application Request.

10. Each payment request shall list each Approved Change Order (See Section 01 26 00) executed prior to date of submission, including a description of the work activities.

Page 194 of 762 ends

38077.00180\29080232.10

-134- 01 20 00 MEASUREMENT AND PAYMENT

11. Monthly progress payments shall be made based on total value of activities completed or partially completed, as determined by City with participation of Contractor, and based upon approved activity costs. Accumulated retainage will be shown as a separate item in payment summary. If Contractor fails or refuses to participate in construction progress evaluation with City, Contractor shall not receive current payment until Contractor has participated fully in providing construction progress information and schedule update information to City.

12. If required by City, Contractor shall submit substantiating data as they relate to payment requests.

D. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. Notice to Proceed

2. List of subcontractors.

3. Schedule of values.

4. Contractor's construction schedule.

E. Progress Payments:

1. If it is determined that the payment request is not a proper payment request suitable for payment, City shall return it to the Contractor as soon as practicable, but no later than seven (7) days after receipt, together with a document setting forth in writing the reasons why the payment request is not proper. If City determines that portions of the payment request is not proper or not due under the Contract Documents, then City may approve the other portions of the payment request, and in the case of disputed items or defective work not remedied, may withhold up to 150% of the disputed amount from the progress payment.

2. The City will mail the progress payment to the Contractor within thirty (30) days from the date of receipt of the invoice in acceptable form, including copies of certified payroll, schedule updates, and progress payment certification. The City will pay to Contractor in manner provided by law, an amount equal to ninety-five percent (95%) (i.e., five percent Documents, provided that payments may at any time be withheld if, in judgment of City, Work is not proceeding in accordance with Contract, or Contractor is not complying with requirements of Contract, or to comply with stop notices or to offset liquidated damages accruing or expected.

3. Before any progress payment or final payment is made, Contractor may be required to submit satisfactory evidence that Contractor is not delinquent in payments to employees, subcontractors, suppliers, or creditors for labor and materials incorporated into Work.

Prior to final payment by the City, the Contractor shall submit a final waiver of lien for the

4. City reserves and shall have the right to withhold payment for any equipment and/or specifically fabricated materials that, in the sole judgment of City, is not adequately and properly protected against weather and/or damage, prior to or following incorporation into the Work.

Page 195 of 762 ends

38077.00180\29080232.10

-135- 01 20 00 MEASUREMENT AND PAYMENT

5. Granting of progress payment or payments by City, or receipt thereof by Contractor, shall not be understood as constituting in any sense acceptance of Work or of any portion thereof, and shall in no way lessen liability of Contractor to replace unsatisfactory work or material, though unsatisfactory character of work or material may have been apparent or detected at time payment was made.

6. When City shall charge sum of money against Contractor under any provision of Contract Documents, amount of charge shall be deducted and retained by City from amount of next succeeding progress payment or from any other payment due or that may become due Contractor under Contract. If, on completion or termination of Contract, such have right to recover balance from Contractor or Sureties.

PART 2 PRODUCTS

2.1 BREAKDOWN
The contract Lump Sum price paid for all bid items listed below shall be considered full compensation for furnishing all labor, materials, equipment, tools, and incidentals for all work involved including the removal, disposal, furnishing, and installation of any bid item listed below as specified in the Contract Documents and as directed by the City Engineer, and no separate payment shall be made.

BASE BID ITEMS

1. Mobilization, Demobilization ,
equipment and incidentals for all work involved including, but not limited to, mobilization, demobilization, preparatory work and operations necessary for the movement of personnel, equipment, sheeting, shoring, bracing, and permitting to ensure compliance with all laws and regulations as shown on the Contract Drawings, dewatering, procurement and installation of Baker Tank, well points, sump pumps, temporary pipelines for water disposal, rock or gravel placement as necessary, standby pumping equipment maintained on the job site continuously; and the safe and proper disposal of excess water in compliance with local and State regulations as shown in the Contract Documents, preparation of potholing plan, excavation and disposal of soil, and backfill and restoration of pavement as shown on the Contract Drawings and specified herein and supplies to and from the project sites as shown on the Contract Drawings and specified herein. No separate payment shall be made. The total lump sum shall not exceed 10% of the Total Base Bid.

2. Erosion and Sediment Control Plan: Erosion
and Sediment Control Plan shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for all work involved including, but not limited to, preparation and maintenance of the erosion control measure, and installation of storm drain inlet protection, fiber roll, construction entrance, and silt fence as shown on the Contract Drawings and specified herein. No separate payment shall be made.

Page 196 of 762 ends

38077.00180\29080232.10

-136- 01 20 00 MEASUREMENT AND PAYMENT

3. Demolish Existing Facilities and Salvage Equipment: The contract lump sum Demolish Existing Facilities and Salvage Equipment
compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved including, but not limited to, demolishing, removing, and disposing of equipment including but not limited to the existing utility covers, valves, piping, pipe supports, and concrete pads identified by Drawings D-01 and D-02. The work includes all materials, labor, and equipment necessary for the demolition work. The bid price shall include, but is not limited to, all cost for protection of and for working around and near existing facilities that are or are not specifically identified by the drawings, as well as saw cutting, removal, hauling, disposal of existing utility covers, concrete and miscellaneous concrete, pipe supports, piping, valves, soil, aggregate base, conduits, and supports as shown shown on the Contract Drawings and specified herein. No separate payment shall be made.

This bid item also includes contractor coordination with the City on items to be salvaged, if any, and transportation and drop off of any salvaged items to City yard.

4. Install ARVs No. 2, 3, 4, 5, and 7 Complete: The contract lump sum price paid for 3, 4, shall include full compensation for
furnishing all labor, materials, tools, equipment, and incidentals for all work involved including, but not limited to, installation of the new ARVs No. 2, 3, 4, 5, and 7, complete, of Force Main B as shown on Drawings M-02 and M-04 including modification to existing vaults, connection to existing piping, new below and above ground piping, cathodic protection, concrete pad, pipe supports, isolation valves, combination AR/AV valves, utility covers, and all other work required to deliver a functional product. The bid price shall include, but is not limited to, all costs for the work as shown on the plans and in accordance with the Technical Specifications.

The work also includes protection of existing facilities and working near or on top of existing facilities, that may or may not be identified by the drawings. No separate payment shall be made.

5. Install ARV No. 1 and 6 Complete:
materials, tools, equipment and incidentals for all work involved including, but not limited to, construct the improvements associated with installation of the new ARVs No. 1 and 7, complete, of Force Main B as shown on Drawings M-01 and M-03 including connection to existing piping, new piping, pipe supports, isolation valves, combination AR/AV valves, and all other work required to deliver a functional product. The bid price shall include, but is not limited to, all costs for the work as shown on the plans and in accordance with the Technical Specifications. No separate payment shall be made.

Page 197 of 762 ends

38077.00180\29080232.10

-137- 01 20 00 MEASUREMENT AND PAYMENT

6. Install ARV No. 6A Complete
6A
full compensation for furnishing all labor, materials, tools, equipment and incidentals for all work involved including, but not limited to, construct the improvements associated with installation of the new ARV No. 6A, complete, of Force Main B as shown on Drawing M-03 including connection to existing piping, new piping, pipe supports, isolation valves, ARV and all other work required to deliver a functional product. The bid price shall include, but is not limited to, all costs for the work as shown on the plans and in accordance with the Technical Specifications. No separate payment shall be made.

Page 198 of 762 ends

38077.00180\29080232.10

-138- 01 20 00 MEASUREMENT AND PAYMENT

TECHNICAL SPECIFICATIONS

Page 199 of 762 ends

CERTIFICATIONS PAGE
ENGINEER’S CERTIFICATIONS :

These Technical Specifications have been prepared for City of Milpitas, for the following project:

Main Lift Station Force Main B Air Release Valves Replacement Project, Project No. 6124 The documents have been prepared by, or under the direct supervision of the following design Professional Engineer, licensed in the State of California:

Nicholas A. Boswell, P.E.

MNS Engineers Inc.
2025 Gateway Place, Suite 328
San Jose, CA 95110
April 4, 2025

Page 200 of 762 ends

FORCE MAIN B AIR RELEASE VALVES

REPLACEMENT PROJECT

LIST OF TECHNICAL SPECIFICATIONS
DIVISION 01: GENERAL REQUIREMENTS
011100 Coordination of Work Permits, and Regulations
013300 Submittals
015100 Construction Facilities and Temporary Controls
017410 Cleaning During Construction and Final Cleaning
019310 Operation and Maintenance Manuals

DIVISION 02: EXISTING CONDITIONS
020120 Protection of Existing Underground Utilities
023219 Subsurface Utility Locating (Potholing)
024100 Equipment, Piping, and Materials Demolition

DIVISION 03: CONCRETE
030500 General Concrete Construction

DIVISION 09: FINISHES
099000 Painting and Coating
099772 Cold-Applied Wax Tape Coating
099754 Polyethylene Sheet Encasement (AWWA C105)
099761 Fusion Bonded Epoxy Lining and Coatings

DIVISION 13: SPECIAL CONSTRUCTION
133438 Expanded Metal Air Release Valve Enclosures

DIVISION 31: EARTHWORK
312300 Earthwork

DIVISION 40: PROCESS INTEGRATION
400500 General Piping Requirements
400515 Pressure Testing of Piping
400520 Manual Process Valves
400560 Air Release and Vacuum Relief Valves
400775 Valve and Piping Identification
402040 Ductile Iron Pipe
402076 Stainless Steel Pipe

ATTACHMENT A – RECORD DRAWINGS

END OF TABLE OF CONTENTS

Page 201 of 762 ends

COORDINATION OF WORK, PERMITS, AND REGULATIONS 011100-1 Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 011100 COORDINATION OF WORK, PERMITS, AND REGULATIONS

1.01 DESCRIPTION
This section generally describes the project and includes work sequence and schedule, Contractor's use of premises, Owner occupancy, maintenance and operation of existing facilities.

1.02 GENERAL NATURE OF WORK
The work involves construction of a Project to replace the existing sewage air release and combination sewage air release and air vacuum valve assemblies including concrete pads and utility covers on the City of Milpitas Main Lift Station Force Main B Pipeline including: demolition of existing concrete pads, piping, valves, and security covers; installation of new concrete pads, piping, valves, security covers, and cathodic protection equipment.

1.03 LOCATION OF PROJECT SITE
The project site is located: Along the alignment of the City of Milpitas Main Lift Station Force Main B beginning at the Main Lift Station Site (1425 N. McCarthy Blvd. Milpitas, CA 95035) and extending through open space to the San Jose-Santa Clara Regional Wastewater Facility (700 Los Esteros Rd., San Jose, CA 95134).

1.04 WORK BY OTHERS
A. With respect to work by others, the Owner will require that:

The Main Lift Station shall remain in service throughout construction. Prior to construction City Operations Staff will direct wastewater from the Main Lift Station to Force Main A to allow for replacement of the Force Main B air release valves. During construction, Force Main B will remain out of service except in the event of emergency.

The Contractor shall maintain a 3 week look ahead schedule and notify the City in writing 21 days prior to the start of field construction activities.

B. In case of conflict in site use, see: MUTUAL RESPONSIBILITY OF CONTRACTORS, General Conditions.

1.05 WORK SEQUENCE AND SCHEDULE
Valve replacement shall be completed within 30 days from the Contractor’s notice to proceed with field construction activity provided by the City. The Contractor shall notify and coordinate with City Operations Staff for shut down of Force Main B. Once started, the Contractor shall work continuously to complete construction.

Page 202 of 762 ends

COORDINATION OF WORK, PERMITS, AND REGULATIONS 011100-2 Main Lift Station Force Main B Air Release Valves Replacement Project

1.06 CONTRACTOR'S USE OF PREMISES
The Contractor shall coordinate use of the premises with the City’s Construction Manager.

1.07 OWNER OCCUPANCY
The City of Milpitas Main Lift Station and San Jose-Santa Clara Regional Wastewater Facility shall remain occupied and in service throughout the duration of construction. The Contractor shall coordinate work such as not to impact operation of either facility.

1.08 MAINTENANCE AND OPERATION OF EXISTING FACILITIES
Prior to the start of construction, the City will halt pumping of wastewater to Force Main B during construction, except in the case of emergency. City staff will depressurize the main, be responsible for verifying the main is shut down and depressurized, and that in the event of a sewage spillover during depressurization, the City Operations team will address the spill and remedy.

Following initial isolation and depressurization by the City, the Contractor will be responsible to collect and legally dispose of sewage as required during construction in order to replace the isolation valves between the force main and the combination AR/AV valves.

1.09 PERMITS
A. The following permits for the permanent work have been obtained by the Owner:

1. Right of Entry Permit – A Right of Entry Permit will be obtained by the City of Milpitas for Contractor access to the Project facilities on San Jose property.

1.10 CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) COMPLIANCE A. The City will be responsible for obtaining CEQA documentation.

1.11 LICENSES
A. The prime contractor and subcontractors shall obtain and pay for a City of Milpitas Business License. Detailed information concerning business license may be obtained from the City’s web site.

1.12 FORCE MAIN CONTINGENCY PLAN
A. The City reserves the right to activate Force Main B at any time during construction as needed for operation of the Main Lift Station. As such, the Contractor shall, prior to the end of each working day, provide temporary caps of all piping that connects to the force main pipeline. In the event the City must activate Force Main B during a Contractor

Page 203 of 762 ends

COORDINATION OF WORK, PERMITS, AND REGULATIONS 011100-3 Main Lift Station Force Main B Air Release Valves Replacement Project

workday, the Contractor shall immediately halt work and cap the connecting piping when notified by the City.

1.13 CONFINED SPACE ENTRY REQUIREMENTS
A. Confined space entry is required when working within the existing vaults used for piping connection between the force main and the combination AR/AV valves. The Contractor shall follow State OSHA requirements for confined space entry at all times including but not limited to continuous fall protection, gas monitoring, and forced air supply and exhaust. The Contractor shall provide submittal outlining the details of the Contractor’s work plan to meet confined space entry requirements for approval prior to beginning work.

END OF SECTION

Page 204 of 762 ends

COORDINATION OF WORK, PERMITS, AND REGULATIONS 011100-4 Main Lift Station Force Main B Air Release Valves Replacement Project

THIS PAGE LEFT INTENTIONALLY BLANK

Page 205 of 762 ends

SUBMITTALS 013300-1
Main Lift Station Force Main B Air Release Valves Replacement Project SECTION 013300 SUBMITTALS
PART 1 - GENERAL

1.01 SHOP DRAWINGS
A. Submit shop drawings in accordance with the General Conditions for all proposed materials and equipment.

B. The use of contract drawing reproductions for shop drawings is subject to rejection.

C. Submit shop drawings electronically in PDF format compatible with Adobe Acrobat Version 9. Files 5MB or less in size may be submitted to the Construction Manager via email. Files larger than 5MB shall be submitted by means of an FTP server, USB flash drive, external hard drive, CD-ROM, or as approved by the Construction Manager.

Pages shall be scanned at a resolution necessary for legibility. Scans shall be in color where necessary for clarity.

D. If the Contractor submits shop drawings of equipment by manufacturers other than those listed in the specifications, provide the following information with the submittal:

1. The name and address of at least three companies or agencies that are currently using the equipment

2. The name and telephone number of at least one person at each of the above companies or agencies whom the Construction Manager may contact.

3. A description of the equipment installed at the above locations. The description shall be in sufficient detail to allow the Construction Manager to compare it with the equipment proposed to be installed in this Project.

E. For materials originating outside of the United States for which tests are required, provide recertification and retesting by an independent domestic testing laboratory.

F. For submittals requiring review of physical items, submit two (2) hard copies of the transmittal along with the two (2) examples of the physical item to the Construction Manager in person or by mail

1.02 SUBMITTAL REQUIREMENTS
A. Make submittals promptly in such sequence as to cause no delay in the Work. Schedule submission a minimum of 30 CALENDAR DAYS before reviewed submittals will be needed.

Page 206 of 762 ends

SUBMITTALS 013300-2
Main Lift Station Force Main B Air Release Valves Replacement Project B. Submittals shall contain:

1. The date of submission and the dates of any previous submissions.

2. The Project title and number.

3. Contract identification.

4. The names of:
a. Contractor.
b. Supplier.
c. Manufacturer.

5. Identification of the product, with the specification section number.

6. Field dimensions, clearly identified as such.

7. Relationship to adjacent or critical features of the Work or materials.

8. Identification of deviations from contract documents.

9. Identification of revisions on resubmittals.

10. Contractor’s stamp, initialed or signed, shall certify Contractor’s review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal documenting the product meets the requirements of the Work and of the contract documents.

1.03 SUBMITTAL FORMAT
A. Each submittal shall have a transmittal form.

B. Where product data from a manufacturer is submitted, clearly mark which model is proposed, with all pertinent data, capacities, dimensions, clearances, diagrams, controls, connections, anchorage, and supports. Present a sufficient level of detail for assessment of compliance with the contract documents.

C. Each submittal shall be assigned a unique number. Submittals shall be numbered sequentially. The submittal numbers shall be clearly noted on the transmittal. Original submittals shall be assigned a numeric submittal number. Resubmittals shall bear an numeric system which consists of the number assigned to the original submittal for that item followed by a number to represent it is a subsequent submittal of the original. For

Page 207 of 762 ends

SUBMITTALS 013300-3
Main Lift Station Force Main B Air Release Valves Replacement Project example, if Submittal 25 requires a resubmittal, the first resubmittal will bear the designation ”25-01” and the second resubmittal will bear the designation “25-02” and so on.

D. Disorganized submittals not meeting the requirements above will be returned without review.

1.04 RESUBMITTALS
A. Resubmittal of submittals will be reviewed and returned in the same review period as for the original submittal. It is considered reasonable the Contractor shall make a complete and acceptable submittal by the second submission of a submittal item. The Construction Manager reserves the right to withhold monies due to the Contractor to cover additional costs of any review beyond the second submittal.

1.05 CONTRACTOR’S JOBSITE DRAWINGS
A. Provide and maintain on the jobsite one complete set of prints of all drawings which form a part of the contract. Immediately after each portion of the Work is installed, indicate all deviations from the original design shown in the drawings either by additional sketches or ink thereon. Upon completion of the job, deliver this record set to the Construction Manager.

B. The Contractor shall keep copies of all approved shop drawings onsite and have this information available for City’s review upon request.

PART 2 – MATERIALS (NOT USED)
PART 3 – EXECUTION (NOT USED)

Page 208 of 762 ends

SUBMITTALS 013300-4
Main Lift Station Force Main B Air Release Valves Replacement Project SHOP DRAWING SUBMITTAL NO. ________
MNS

ATTN: __________________________________

ATTN: __________________________________

PROJECT
MNS PROJECT NO. OWNER PROJECT NO. CONTRACTOR PROJECT NO.

ITEM
NO.

COPIES

DESCRIPTION

PREVIOUS

SUBMITTAL
NO.

SPEC.

SECTION
NO.

PLAN
SHEET NO.

SUBMITTED BY:

CONTRACTOR DATE

SUBMITTAL RETURN (TO BE COMPLETED BY ENGINEER)

ITEM RESUBMIT
NO. COPIES YES NO COMMENTS

COPY: RETURNED BY:

ENGINEER DATE

END OF SECTION

Page 209 of 762 ends

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS 015100-1 Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 015100 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

1.01 CONSTRUCTION WATER
A. Related Work Specified Elsewhere:

1. Pressure Testing of Piping: 400515.

B. The Contractor shall make his own arrangements for developing water sources and supply labor and equipment to collect, load, transport, and supply water as necessary for compaction of materials, concrete construction operations, testing, dust control, and other construction use.

C. Develop sources of water supply or obtain a meter and water from the City of Milpitas.

Payment for costs connected with utilization of the source shall be made by the Contractor. Water shall be clean and free from objectionable deleterious amounts of acids, alkalies, salts, or organic materials.

Include the cost of construction water in the appropriate bid item to which it is appurtenant. The cost shall include full compensation for furnishing all labor, materials, tools, and equipment and doing all the work necessary to develop a sufficient water supply and furnishing the necessary equipment for applying the water as described in these specifications.

1.02 ELECTRICAL POWER-CONSTRUCTION PHASE
Provide for the purchase of power or provide portable power for the construction of the Project where existing outlets are not available. Provide for the extension of utility lines to the point of use. The cost of power shall be included in the appropriate bid items to which it is appurtenant and shall include full compensation for furnishing all labor, materials, tools, and equipment required to obtain and distribute power for construction purposes.

1.03 SANITARY SERVICE--CONSTRUCTION PHASE
Provide, maintain, and protect, portable restrooms throughout the duration of construction as required for construction. This shall include full compensation for furnishing all labor, materials, tools, and equipment required to obtain and maintain the portable sanitary services.

1.04 DUST CONTROL
Perform dust control operations to prevent construction operations from producing dust in amounts harmful to persons or causing a nuisance to persons living nearby or occupying buildings in the vicinity of the work. Use water or dust preventative to control dust.

Page 210 of 762 ends

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS 015100-2 Main Lift Station Force Main B Air Release Valves Replacement Project

1.05 FIRE DANGER
Minimize fire danger in the vicinity of and adjacent to the construction site. Provide labor and equipment to protect the surrounding property from fire damage resulting from construction operations.

1.06 SITE ACCESS
A. The Project site is located on either gated and locked City of Milpitas or City of San Jose property.

B. Obtain access to the Project site through the existing public road right of way. Keep the existing sites accessible at all times so that the City's vehicles have access to the site.

C. The Contractor shall coordinate access to the site via the City’s construction manager.

Access routes for Construction shall be approved in writing by the City’s Operations staff a minimum of 21 days prior to the start of field construction activity.

END OF SECTION

Page 211 of 762 ends

CLEANING DURING CONSTRUCTION AND FINAL CLEANING 017410-1 Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 017410 CLEANING DURING CONSTRUCTION AND FINAL CLEANING

1.01 GENERAL
A. This section includes cleaning during construction and final cleaning on completion of the Work.

B. At all times maintain areas covered by the contract, adjacent properties, and access roads free from accumulations of waste, debris, and rubbish caused by construction operations.

C. Conduct cleaning and disposal operations to comply with local ordinances and antipollution laws. Do not burn or bury rubbish or waste materials on Project site. Do not dispose of volatile wastes, such as mineral spirits, oil, or paint thinner, in storm or sanitary drains. Do not dispose of wastes into streams or waterways.

D. Use only cleaning materials recommended by manufacturer of surface to be cleaned.

1.02 CLEANING DURING CONSTRUCTION
A. During execution of Work, clean sites, adjacent properties, and public access roads and dispose of waste materials, debris, and rubbish to assure that grounds and public properties are maintained free from accumulations of waste materials and rubbish.

B. Wet down dry materials and rubbish to lay dust and prevent blowing dust.

C. Provide containers for collection and disposal of waste materials, debris, and rubbish.

D. Cover or wet excavated material leaving and arriving at the site to prevent blowing dust.

Clean the public access roads to the site of any material falling from the haul trucks.

1.03 FINAL CLEANING
A. At the completion of Work and immediately prior to final inspection, clean the entire Project site as follows.

B. Fill any soil depressions created by the work. Clean, rake, sweep, wash, and polish all Work and equipment including finishes.

C. Remove grease, dust, dirt, stains, labels, fingerprints, and other foreign materials from sight-exposed interior and exterior finished surfaces; polish surfaces.

D. Repair, patch, and touch up marred surfaces to match adjacent surfaces.

E. Broom clean paved surfaces.

Page 212 of 762 ends

CLEANING DURING CONSTRUCTION AND FINAL CLEANING 017410-2 Main Lift Station Force Main B Air Release Valves Replacement Project

F. Remove from the site temporary structures and materials, equipment, and appurtenances not required as a part of, or appurtenant to, the completed Work.

END OF SECTION

Page 213 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-1
Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 019310 OPERATION AND MAINTENANCE MANUALS

1.01 GENERAL
Submit one digital and two physical copies of all manufacturer's operation and maintenance manuals and data pertinent to equipment supplied for the Project. Prepare and organize the material in three-ring binders with divider tabs and labels. Include a table of contents. Include a flash drive of all catalog data in pdf format and all drawings in both pdf and CAD formats. All pdf files shall be formatted to allow word search.

1.02 SUBMITTALS
A. Submittals shall include:

1. List of equipment furnished for Project with name, address, and telephone number of each vendor.

2. List of serial numbers of equipment furnished.

3. A copy of shop drawings for mechanical, electrical, and instrument equipment in final form.

4. Manufacturer's operation and maintenance instructions and parts lists.

5. Tabulation of motor nameplate horsepower, nameplate current, field-measured current, overload relay setting, and catalog number for polyphase motors.

6. List of fuses, lamps, seals, and other expendable equipment and devices. Specify size, type, and ordering description. List name, address, e-mail address, website address, fax number, and telephone number of vendor.

B. Provide manuals for each piece of equipment including individual components and subsystems of complete assemblies. Line out nonapplicable text and illustrations. The section of the manual on operation shall describe the functions and limitations of each component and its relationship to the system of which it is a part. Where several models, options, or styles are described, the manual shall identify the items actually provided.

C. Each manual shall contain the following:

1. Manufacturer's identification, including order number, model, and serial number.

2. Blue line prints or reviewed shop drawings and diagrams of all systems.

3. Certified equipment drawings or reviewed shop drawing data clearly marked for equipment furnished.

4. Complete operating and maintenance instructions for each and every item of equipment, setting forth in detail and step-by-step the procedure for starting,

Page 214 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-2
Main Lift Station Force Main B Air Release Valves Replacement Project

stopping, operating, and maintaining the entire system as installed. Include a schedule of recommended maintenance intervals.

5. Complete parts list of replaceable parts, their part numbers, and the name and address of their nearest vendor.

6. A complete valve tag list including the name and function of the pipe in which the valve is mounted.

7. Any special emergency operating instruction and a list of service organizations (including addresses and telephone numbers) capable of rendering emergency service to the various parts of the system.

8. Copy of manufacturer's equipment guarantees and warranties.

D. Brochures shall be loose leaf with durable plastic or fiberboard covers. Each sheet shall be reinforced to prevent tearing from continued use, and each brochure shall have the following information clearly printed on its cover:

1. Project name, City of Milpitas, and address.

2. Name and address of Project Manager.

3. Name and addresses of contractors and subcontractors and department to contact.

4. Telephone number of contractors, including night and emergency numbers.

5. Major equipment vendors' names and telephone numbers.

E. Submit complete manuals at least two weeks before the date of the instructions required by the subsections on "Manufacturer's Services" in the various specification sections.

F. Operation and maintenance manuals specified herein are in addition to any operation, maintenance, or installation instructions required by the Contractor to install, test, and start up equipment.

1.03 EQUIPMENT DATA SHEETS
Provide two sets of equipment data sheets, bound in three-ring binders, summarizing the equipment manufacturer's maintenance instructions and recommendations. A blank data sheet and a sample data sheet are attached.

Page 215 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-3
Main Lift Station Force Main B Air Release Valves Replacement Project

Preventive Maintenance and Operating Requirement Sheets Preventive Maintenance Program Equipment Record Number

EQUIPMENT DESCRIPTION ELECTRICAL OR MECHANICAL DATA
Name: Size:

Serial No.: Model:

Vendor:

Vendor Address: Type:

Mfr.:

Vendor Rep: Voltage: Amps:

Phone: Phase: rpm:

Maintenance Work to be Done Frequency*

OPERATING REQUIREMENTS AND REFERENCE
*D - Daily; W - Weekly; B - Biweekly; M - Monthly; Q - Quarterly; S - Semiannually; A - Annually.

Page 216 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-4
Main Lift Station Force Main B Air Release Valves Replacement Project

SAMPLE

Preventive Maintenance and Operating Requirement Sheets

Preventive Maintenance Program Equipment Record Number

EQUIPMENT DESCRIPTION ELECTRICAL OR MECHANICAL DATA
Name: Influent Pump No. 1
Tag No.: P01-1
Size: 15 hp
Serial No.: 123456ABC
Vendor: ABC Pump Co.

Model: 140T Frame
Serial No. 987654ZY
Class F Insulation
W/Space Heater
Vendor Address: Type:
1111 Pump Circle
Newport Beach, CA 92663
Mfr.: DEF Motors, Inc.

Vendor Rep: XYZ Equipment, Inc. Voltage: 460 Amps: 20 Phone: 714/752-0505 Phase: 3 rpm: 1,800
Maintenance Work to be Done Frequency*

1. Operate all valves and check such things as a) bearing temperature, b) changes in running sound, c) suction
and discharge gauge readings, d) pump discharge rate,
and e) general condition of the drive equipment.

2. Check packing.

3. Checking pumping unit for any dust, dirt, or debris. (Continued on attached sheet)
D

D
W

OPERATING REQUIREMENTS AND REFERENCE
For manufacturer's instructions regarding installation, operation, maintenance, and trouble shooting of this equipment, see Volume ____, Section ______.

*D - Daily; W - Weekly; B - Biweekly; M - Monthly; Q - Quarterly; S - Semiannually; A - Annually.

Page 217 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-5
Main Lift Station Force Main B Air Release Valves Replacement Project

SAMPLE
Preventive Maintenance and Operating Requirement Sheets Preventive Maintenance Program Equipment Record Number

EQUIPMENT DESCRIPTION ELECTRICAL OR MECHANICAL DATA
Name: Size:

Serial No.: Model:

Vendor:

Vendor Address: Type:

Mfr.:

Vendor Rep: Voltage: Amps:

Phone: Phase: rpm:

Maintenance Work to be Done Frequency*

4. Lubricate bearing frame and motor bearings (consult
manufacturer's instructions for type of grease or oil).

5. Disassemble and change or repair the following: a)
impeller, b) shafts, c) shaft sleeve, d) rotary seals,
and e) sleeve bearings.

Q

A

OPERATING REQUIREMENTS AND REFERENCE
*D - Daily; W - Weekly; B - Biweekly; M - Monthly; Q - Quarterly; S - Semiannually; A – Annually

Page 218 of 762 ends

OPERATION AND MAINTENANCE MANUALS 019310-6
Main Lift Station Force Main B Air Release Valves Replacement Project

THIS PAGE LEFT INTENTIONALLY BLANK

Page 219 of 762 ends

PROTECTING EXISTING UNDERGROUND UTILITIES 020120-1
Main Lift Station Force Main B Air Release Valves Replacement Project SECTION 020120 PROTECTING EXISTING UNDERGROUND UTILITIES PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and procedures for protecting existing underground utilities.

1.02 RELATED WORK SPECIFIED ELSEWHERE
A. Subsurface Utility Locating (Potholing): 023219.

PART 2 - MATERIALS

2.01 REPLACEMENT IN KIND
Except as indicated below or as specifically authorized by the Construction Manager, reconstruct utilities with new material of the same size, type, and quality as that removed.

PART 3 - EXECUTION

3.01 GENERAL
A. Replace in kind improvements, such as curbs, walls, signs, etc., that are cut, removed, damaged, or otherwise disturbed by the construction.

B. Where utilities are parallel to or cross the construction but do not conflict with the permanent work to be constructed, follow the procedures given below and as indicated in the drawings. Notify the utility owner 48 hours in advance of the crossing construction and coordinate the construction schedule with the utility owner's requirements. For utility crossings not shown in the drawings, refer to the General Provisions and the instructions of the Project Manager for guidance.

C. Determine the true location and depth of utilities and service connections which may be affected by or affect the Work. Determine the type, material, and condition of these utilities. In order to provide sufficient lead-time to resolve unforeseen conflicts, order materials and take appropriate measures to ensure that there is no delay in work.

D. The pipelines must be installed at the profile elevations shown on the drawings. Prior to beginning construction of the pipelines, the Contractor shall pothole and expose all utility crossings that have the potential to impact the profile elevations of the pipelines indicated on the plans. The Contractor shall notify the Construction Manager immediately in the event a utility is located in conflict with the new pipelines.

Page 220 of 762 ends

PROTECTING EXISTING UNDERGROUND UTILITIES 020120-2
Main Lift Station Force Main B Air Release Valves Replacement Project Expose utilities in advance of the pipeline construction. Prior to beginning work on installation of pipelines the Contractor shall expose all utility crossings with potential to impact the pipeline profiles. The Contractor shall notify the Construction Manager immediately in the event a utility is located that is in conflict with the new pipelines.

3.02 PROCEDURES
A. Protect in Place: Protect utilities in place, unless abandoned, and maintain the utility in service, unless otherwise specified in the drawings or in the specifications.

B. Cut and Plug Ends: Cut abandoned utility lines and plug the ends. Dispose of the cut pipe as unsuitable material.

3.03 COMPACTION
A. Utilities Protected in Place: Backfill and compact under and around the utility so that no voids are left.

B. Utilities Reconstructed: Prior to replacement of the utility, backfill the trench and compact to an elevation 1 foot above the top of the ends of the utility. Excavate a cross trench of the proper width for the utility and lay, backfill, and compact.

C. Alternative Construction--Sand-Cement Slurry: Sand-cement slurry consisting of one sack (94 pounds) of portland cement per cubic yard of sand and sufficient moisture for workability may be substituted for other backfill materials to aid in reducing compaction difficulties. Submit specific methods and procedures for the review of the Project Manager prior to construction.

END OF SECTION

Page 221 of 762 ends

POTHOLING 023219-1
Main Lift Station Force Main B Air Release Valves Replacement Project SECTION 023219 SUBSURFACE UTILITY LOCATING (POTHOLING)
PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and procedures for performing pothole operations to locate existing underground utilities.

1.02 SUBMITTALS
A. Submit request for premarking of utilities in pothole locations at least ten working days prior to the commencement of field activities.

B. Submit a work plan at least ten working days prior to the commencement of field activities.

C. Submit proposed method of potholing, including description of equipment to be used, and schedule for potholing for approval at least ten working days prior to the commencement of field activities. Obtain the Construction Manager’s approval of pothole locations prior to commencement of field activities.

D. Submit field logs to the Construction Manager within two working days after the completion of pothole excavations at each site. Include dates of potholing operations and any additional discovered information or pertinent data. Include for each pothole excavation field log:

1. Pothole number.

2. Date of pothole.

3. Depths to top and bottom of utility (measured from existing grade over utility at pothole).

4. Size, materials, and type of located utility.

5. Miscellaneous Contractor’s notes.

E. Submit temporary steel cap and/or steel plate bridging shop drawings at least five working days prior to the commencement of field activities.

F. Submit sand-cement slurry mix design at least five working days prior to the commencement of field activities.

Page 222 of 762 ends

POTHOLING 023219-2
Main Lift Station Force Main B Air Release Valves Replacement Project

1.03 PROCEDURES
A. Subsurface utility-locating (potholing) services shall conform to CI/ASCE 38-02. For the purpose of this scope, “locate” means to obtain the horizontal and vertical position of the utility line by excavating a circular test hole or narrow trench. Construct test holes using vacuum excavation or comparable nondestructive equipment in a manner that will cause no damage to the utility.

B. Subsurface utility locating shall consist of test hole excavations at all utility crossing locations. Narrow trench excavations (slot potholes) may be required at locations approved by the Construction Manager or to locate multiple parallel utilities.

1.04 TIME OF COMPLETION/SCHEDULE
The Contractor shall diligently prosecute the potholing work to completion a minimum of five working days prior to start of field construction activity.

1.05 STANDARD SPECIFICATIONS
Wherever reference is made to the Public Works Specifications such reference shall mean the Standard Specifications for Public Works Construction (SSPWC), 2021 edition.

PART 2 - MATERIALS

2.01 SAND-CEMENT SLURRY BACKFILL AT TEST HOLES AND AT

EXPLORATORY TRENCHES
Sand-cement slurry backfill shall consist of two sacks of Type I or II portland cement added per cubic yard of imported sand and sufficient water for workability.

PART 3 - EXECUTION

3.01 POTHOLING OPERATIONS
A. Backfill and repair test hole excavations immediately after obtaining the measurement data. Backfill and repair trench excavations requiring use of temporary steel plate bridging within five working days. Promptly provide notice to the Construction Manager for scheduling field survey activities. Advise Construction Manager of number of pothole excavations completed and number remaining.

B. Underground Service Alert Requirements: Comply with Underground Service Alert requirements for notification prior to excavation. Contact Underground Service Alert at 811 no less than two and no more than ten days prior to the start of exploratory excavation. Verify whether or not a representative of each utility or agency will be

Page 223 of 762 ends

POTHOLING 023219-3
Main Lift Station Force Main B Air Release Valves Replacement Project present during excavation and coordinate with said individual(s). Take any precautions required by the utility owner.

C. Conduct potholing operations in a manner that minimizes the damage potential to existing underground utilities in order to ensure that the existing facilities will remain in operation without interruption.

D. Coordinate and cooperate with and facilitate field data collection by Contractor’s surveyor. Pothole excavations shall sufficiently expose subsurface utilities to allow surveyor to easily determine and measure the following data:

1. Elevation at top and bottom of utility.

2. Elevation of existing grade over utility at pothole.

3. Coordinates at surface.

4. Outside diameter of utility or width of duct banks.

5. Utility material and condition.

E. Location and Depiction of Existing Utilities: Pothole maps for subsurface utility locating shall be present and utilized during potholing activities. The plans shall be compared to utility/agency paint markings following Underground Service Alert notification as well as locations premarked by the Contractor’s surveyor. If discrepancies are found between the plans and paint markings, promptly notify the Construction Manager prior to commencement of any excavation.

3.02 EXCAVATION
A. Protect utilities or underground structures from damage during potholing. Immediately report any damaged utilities to the affected utility’s owner and the Construction Manager. Repair immediately any damaged utilities in accordance with the respective utility owner’s requirements. Neatly cut and remove existing pavement. Excavate test holes in such a manner as to prevent any damage to wrappings, coatings, or other protective coverings, utilizing vacuum excavation or hand digging.

B. Methods: Backhoe excavation is not permitted except for trench excavations . Use the following methods for pothole excavations:

1. Hand Digging: Hand digging is the method of excavating a pothole by manual means with hand-held, nonmechanical equipment such as a shovel.

2. Vacuum Excavation: Vacuum excavation shall consist of air or water pressure to break up the soil and a vacuum device to collect the spoil. Determine if air or water vacuum excavation shall be used depending upon specific site and

Page 224 of 762 ends

POTHOLING 023219-4
Main Lift Station Force Main B Air Release Valves Replacement Project environmental characteristics. Soil type such as heavy clay may require water vacuum excavation. Utilize air vacuum excavators if mud from water vacuum excavators cannot be disposed properly. Use air vacuum excavators if damage to utilities, such as cutting through cables, will occur with the use of water vacuum excavators.
a. Air: Air vacuum excavators shall utilize a high velocity air stream to penetrate, expand, and break up the soil. Remove the loosened particles of soil and rock from the excavation through the use of a vacuum. b. Water: Water vacuum excavation systems shall excavate the pothole using high-pressure water to reduce and loosen the soil. Remove the wet soil and mud slurry to a spoil tank using a vacuum.

C. Size of Test Hole Excavation: Maximum test hole size shall be 8 inches in diameter at surface.

D. Size of Exploratory Trench Excavation: Trench width and length shall be as approved by the City. Trench depth shall be as required to accurately locate subsurface utilities.

3.03 POTHOLE REPAIR
A. After excavating a test hole or trench, provide and install a temporary steel cap (over test hole) or temporary steel plate bridging (over trench) to facilitate data gathering by the Contractor’s surveyor.

B. Following data gathering by surveyor, remove temporary steel caps and/or steel plate bridging, and backfill excavation with approved material as follows:

1. Test Hole Excavations: Sand-cement slurry backfill per Part 2 of this section.

Bring to 6” below grade. Fill final 6” with native material and match existing native soil thickness plus 1 inch.

2. Exploratory Trenches: Sand-cement slurry backfill per Part 2 of this section. Bring to 6” below grade. Fill final 6” with native material and match existing native soil thickness plus 1 inch.

3. The finished surface of the repair shall be of like material and constructed to the same finished grade as adjacent. The finished surface shall be such that it does not allow water to pond. There shall be no discernable difference in surface level at the joint between the existing surface and the completed repair.

3.04 DISPOSAL OF CUTTINGS
Properly dispose of cuttings off-site.

END OF SECTION

Page 225 of 762 ends

EQUIPMENT, PIPING, AND MATERIALS DEMOLITION 024100-1
Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 024100 EQUIPMENT, PIPING, AND MATERIALS DEMOLITION PART 1 - GENERAL

1.01 DESCRIPTION
This section describes demolition, removal, and relocation of existing equipment and piping.

PART 2 - MATERIALS
Refer to other sections of these specifications for material to be used as replacements for removal or abandoned equipment.

PART 3 - EXECUTION

3.01 GENERAL
Perform removal and demolition Work specified and indicated in the drawings. Prepare remaining surfaces to receive new scheduled and specified materials and finishes or finish to match adjacent surfaces if no additional work is scheduled or indicated.

3.02 REMOVAL AND REPLACEMENT
A. Remove and dispose of equipment indicated in the drawings.

B. Replace equipment indicated in the drawings. Install the new equipment in locations as indicated in the drawings.

3.03 SALVAGE
A. The City has the right to salvage any items identified within the Project vicinity.

B. The Contractor shall notify the City’s representative five days prior to any salvage or demolition work.

1. The City’s representative will mark items to be salvaged.

2. The Contractor shall be responsible for properly disconnecting, removal from their foundations, cleaning and storing salvaged items. Salvaged items shall be delivered by the Contractor to a storage location designated by the City.

3. All drop offs must be coordinated with the City.

Page 226 of 762 ends

EQUIPMENT, PIPING, AND MATERIALS DEMOLITION 024100-2
Main Lift Station Force Main B Air Release Valves Replacement Project

3.04 SHUTDOWNS OF EXISTING PIPING
Shut off or disconnect utilities affecting demolition work. Schedule shutdowns with the Construction Manager; notify the Construction Manager in writing 15 working days in advance of any shutdown required to perform the work.

3.05 TEMPORARY SUPPORT OF EXISTING EXPOSED PIPING
A. Provide temporary supports for existing piping that must be kept in service during demolition of adjacent piping or other existing work in the Project.

B. If multiple pipes or piping systems are supported on common or shared pipe supports or suspension units, provide temporary support of piping while the common or shared supports or suspension units are demolished and replaced.

3.06 PATCHING
A. Patching shall mean the restoration of a surface or item to a condition as near as practicable to match the existing adjoining surfaces unless otherwise noted, detailed, or specified.

B. When patching involves painting, special coating, vinyl fabric, or other applied finish, refinish the entire surface plane (i.e., wall or ceiling), unless complete refinishing of the entire space is scheduled or specified.

C. Patching includes cleaning of soiled surfaces.

3.07 DEMOLITION
A. Existing utility covers, piping, valves, and other items are to be removed, altered, salvaged, and disposed of as specified herein or indicated in the drawings. Remove and dispose of all portions of these items that interfere with Project construction.

B. Remove and dispose offsite facilities to be demolished in their entirety including belowground footings, foundations, and other associated appurtenances, as shown in the drawings or as specified herein. Backfill and compact all site areas disturbed by demolition work with structural fill material. Provide fill material as needed to match existing grade, regardless if this is shown on the drawings or is not clarified. Haul off and dispose of material not needed to match existing regardless if this is shown on the drawings or is not clarified.

C. Perform the work in a manner that will not damage parts of the structure not intended to be removed or to be salvaged for the Owner. If, in the opinion of the Construction Manager, the method of demolition used may endanger or damage parts of the structure or affect the satisfactory operation of the facilities, promptly change the method when so notified by the Construction Manager.

Page 227 of 762 ends

EQUIPMENT, PIPING, AND MATERIALS DEMOLITION 024100-3
Main Lift Station Force Main B Air Release Valves Replacement Project

D. Equipment, material, and piping, except as specified to be salvaged for the Owner, or removed by others, within the limits of the demolition, excavations, and backfills, will become the property of the Contractor and shall be removed from the Project site. The salvage value of this equipment, materials, and piping shall be reflected in the contract price of the demolition work.

E. Do not reuse material salvaged from demolition work on this Project, except as specifically shown.

END OF SECTION

Page 228 of 762 ends

EQUIPMENT, PIPING, AND MATERIALS DEMOLITION 024100-4
Main Lift Station Force Main B Air Release Valves Replacement Project

THIS PAGE LEFT INTENTIONALLY BLANK

Page 229 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-1
Main Lift Station Force Main B Air Release Valves Replacement Project SECTION 030500 GENERAL CONCRETE CONSTRUCTION
PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials, installation, and testing of formwork, reinforcing steel, joints, concrete, and finishing and curing for general concrete construction.

1.02 RELATED WORK SPECIFIED ELSEWHERE
A. Painting and Coating: 099000.

B. Earthwork: 312300.

1.03 SUBMITTALS
A. Submit shop drawings in accordance with the General Conditions and Section 013300.

B. Prepare concrete and mortar mix designs and laboratory 7-day and 28-day compressive tests, or submit test reports of 7- and 28-day compressive tests of the mix where the same mix has been used on two previous projects. Prepare mix designs in accordance with ACI 318, Chapters 4 and 5, except as modified herein. Submit mix design in writing for review by the Owner at least 15 days before placing of any concrete.

C. Submit manufacturer's catalog data and descriptive literature for joint sealant, backing rod, joint filler, control joints, expansion joint dowels, epoxy bonding compound, and epoxy anchor adhesive.

D. Submit mill test certificates identifying chemical and physical analyses of each load of reinforcing steel delivered. If mill test reports are unavailable and the quantity of steel for a structure exceeds 5 tons, provide a laboratory test to prove conformance with the specified ASTM standard.

E. Submit reinforcing bending lists and placing drawings for all reinforcing. Placing drawings shall indicate all openings (mechanical, electrical, equipment, and architectural) including additional reinforcing at openings and corner bar arrangements at intersecting beams, walls, and footings indicated in the typical detail and structural drawings. Placing drawings shall be coordinated with the concrete placing schedule.

Each bending list and placing drawing submitted shall be complete for each major element of a structure (grade slabs, footings, walls, deck, floor, or roof slabs) including dowels and corner bars. Furnishing such lists shall not be construed that the lists will be reviewed for accuracy. The Contractor shall be wholly and completely responsible for the accuracy of the lists and for furnishing and placing reinforcing steel in accordance with the details shown in the drawings and as specified. Placing drawings shall be

Page 230 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-2
Main Lift Station Force Main B Air Release Valves Replacement Project prepared by the Contractor and shall not incorporate photocopies of the contract drawings.

F. Calculations and drawings shall be signed by a civil or structural engineer, registered in the State of California.

G. Submit one copy of a report from a testing laboratory verifying that aggregate material conforms to the specified gradations or characteristics.

PART 2 - MATERIALS

2.01 NONDOMESTIC CEMENT AND ADDITIVES
A. The use of nondomestic cement and additives in concrete may be permitted only after review of a written request to use such materials. The request to use nondomestic materials shall include a chemical analysis that indicates the material meets the project specifications. Certifications that state the nondomestic materials meet the project requirements will not be accepted.

B. Test reports for concrete materials shall be current to within three months of inclusion into the project and shall be identifiable to the materials supplied.

2.02 FORMWORK
A. Design forms according to ACI 347.

B. Class I Forms: Use steel forms, ply form, or smooth-surface plywood 3/4-inch minimum thickness for straight surfaces and 1/2-inch minimum thickness for curved surfaces.

C. Class II Forms: Use plywood in good condition, metal, or smooth-planed boards free from large or loose knots with tongue and groove or ship lap joints.

D. Class II forms may be used for exterior concrete surfaces that are 1 foot or more below finished grade. Use Class I forms for all other surfaces.

E. Coat forms with form release agent.

2.03 BOND BREAKER
Bond breaker shall be a nonstaining type which will provide a positive bond prevention, such as Williams Tilt-Up Compound, as manufactured by Williams Distributors, Inc., Seattle, Washington; Silcoseal 77, as manufactured by SCA Construction Supply Division, Superior Concrete Accessories, Franklin Park, Illinois; or equal.

2.04 FORM RELEASE AGENT
A. Form release agent shall effectively prevent absorption of moisture and prevent bond with the concrete. Agent shall be nonstaining and nontoxic after 30 days.

Page 231 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-3
Main Lift Station Force Main B Air Release Valves Replacement Project B. For steel forms, release agent shall prevent discoloration of the concrete due to rust.

2.05 REINFORCING STEEL
A. Reinforcement shall conform to ASTM A615 or A706, Grade 60.

B. Fabricate reinforcing in accordance with the current edition of the Manual of Standard Practice, published by the Concrete Reinforcing Steel Institute. Bend reinforcing steel cold.

C. Deliver reinforcing steel to the site bundled and with identifying tags.

2.06 WELDED WIRE REINFORCEMENT
Welded wire reinforcement shall conform to ASTM A185.

2.07 TIE WIRE
Tie wire shall be 16 gauge minimum, black, soft annealed.

2.08 BAR SUPPORTS
Bar supports in beams and slabs exposed to view after form stripping shall be galvanized and plastic coated. Use concrete supports for reinforcing in concrete placed on grade.

2.09 BAR COUPLERS
Reinforcing steel bar splicing couplers shall be a mechanical type as manufactured by Dayton Barsplice Inc. or equal. Use couplers that do not reduce tensile or ultimate strength of bars.

2.10 JOINT SEALANT FOR CONCRETE STRUCTURES
A. Joint sealant shall be a multipart, gray, nonstaining, nonsagging, gun grade polyurethane sealant, which cures at ambient temperature to a firm, flexible, resilient, tear-resistant rubber. Sealant shall comply with ASTM C920, Type M, Grade P, Class 25 for horizontal joints and Grade NS, Class 25 for vertical joints and be recommended by the manufacturer for continuous immersion in water.

Page 232 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-4
Main Lift Station Force Main B Air Release Valves Replacement Project Characteristic or Parameter Technical Requirements
Pot life 1 to 3 hours
Hardness 35 Shore A, ±5, ASTM D2240
Elongation 650%, ASTM D412
Tensile strength 200 psi, ASTM D412
Peel strength on concrete No adhesion loss at 25 pounds Temperature service range 40°F to 167°F
Immersion in water Continuous
B. Sealant shall be Tremco Vulkem 227 or Sikaflex-2CNS (for Grade NS, Class 25), Sikaflex-2CSL of Sika Corporation or Vulkem 245 (for Type M, Grade P, Class 25), or equal. Troweling of sealants into joints will not be permitted.

2.11 BACKING ROD FOR EXPANSION JOINTS
Backing rod shall be an extruded closed-cell polyethylene foam rod, such as Minicel backer rod, manufactured by Industrial Systems Department, Plastic Products Group of Hercules, Inc., Middletown, Delaware; Ethafoam SB, as manufactured by Dow Chemical Company, Midland, Michigan; or equal. The rod shall be 1/4 inch larger in diameter than the joint width. Where possible, provide full-length sections for the joint; minimize splices. Apply backup rod and bond breaker tape in expansion joints.

2.12 BOND BREAKER TAPE
Bond breaker tape shall be an adhesive-backed glazed butyl or polyethylene tape that will adhere to the premolded joint material or concrete surface. The tape shall be the same width as the joint. The tape shall be compatible with the sealant.

2.13 PREFORMED CONTROL JOINT
Preformed control joint shall be a one-piece, flexible, PVC joint former, such as Kold- Seal Zip-Per Strip KSF-150-50-50, manufactured by Vinylex Corp., Knoxville, Tennessee, or a one-piece steel strip with preformed groove, such as Keyed Kold Retained Kap, manufactured by Burke Concrete Accessories, Inc., San Mateo, California, or equal. Provide the preformed control joint material in full-length unspliced pieces.

2.14 PREMOLDED JOINT FILLER
Joint filler shall be preformed, nonextruded type constructed of closed-cell neoprene conforming to ASTM D1752, Type I, as manufactured by W. R. Grace Company of Cambridge, Massachusetts; W. R. Meadows, Inc., Elgin, Illinois; or equal or bituminous-type preformed expansion joint filler conforming to ASTM D994.

Page 233 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-5
Main Lift Station Force Main B Air Release Valves Replacement Project

2.15 STEEL EXPANSION JOINT DOWELS
A. Steel expansion joint dowels shall conform to one of the following:

1. Steel bar dowels with a 12-mil-thick epoxy coating. Steel bar dowels shall conform to ASTM A36 or ASTM 615, plain rounds, Grade 40. Epoxy coating shall be in conformance with ASTM A775.

2. Stainless steel bar dowels conforming to ASTM A276, Type 302.

B. Exposed portion of expansion joint dowels shall be thoroughly greased prior to casting of adjoining wall or slab.

2.16 CEMENT
A. Use domestic portland cement that conforms to ASTM C150 Type II or V.

B. any individual structure. Use no cement that has become damaged, partially set, lumpy, or caked. Reject the entire contents of the sack or container that contains such cement.

Use no salvaged or reclaimed cement.

C. Maximum tricalcium aluminate shall not exceed 8%. The maximum percent alkalies shall not exceed 0.6%.

2.17 AGGREGATES
Aggregates shall be natural rock, sand, or crushed natural rock and shall comply with ASTM C33. Aggregates shall be free from any substances that will react with the cement alkalies, as determined by Appendix X-1 of ASTM C33.

2.18 WATER AND ICE
Use water and ice that is clean and free from objectionable quantities of organic matter, alkali, salts, and other impurities that might reduce the strength, durability, or otherwise adversely affect the quality of the concrete. Water shall not contain more than 500 mg/L of chlorides or more than 500 mg/L of sulfate.

2.19 COLOR ADDITIVE FOR EXTERIOR ELECTRICAL DUCT ENCASEMENT For exterior electrical duct concrete encasements, use a color additive for identification purposes: brick red "Colorfull" as manufactured by Owl Manufacturing Company, Arcadia, California; coral red "Chromix C-22" as manufactured by L. M. Scofield Company, Los Angeles, California; or equal. Add the color additive while the concrete is being mixed using the quantity per cubic yard of concrete recommended by the manufacturer for the class of concrete indicated.

Page 234 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-6
Main Lift Station Force Main B Air Release Valves Replacement Project

2.20 CONCRETE ADMIXTURES
A. Class A concrete shall contain an air-entraining admixture conforming to ASTM C260.

Admixtures shall be Master Builders MB-AE 90, Sika AER, or equal.

B. Class A concrete shall contain a water-reducing admixture conforming to ASTM C494, Type A. It shall be compatible with the air-entraining admixtures. The amount of admixture added to the concrete shall be in accordance with the manufacturer's recommendations. Admixture shall be Master Builders Pozzolith polymer-type normal setting, Plastocrete 161 or Plastiment, Sika Chemical Corporation, or equal.

C. Do not use any admixture that contains chlorides or other corrosive elements in any concrete. Admixtures shall be nontoxic after 30 days.

2.21 GROUT
A. Nonshrink grout shall conform to ASTM C1107 and to these specifications. Use a nongas-liberating type, cement base, premixed product requiring only the addition of water for the required consistency. Grout shall be UPCON High Flow, Master Flow 928, or equal. Components shall be inorganic.

B. Ordinary type grout (dry pack) shall consist of one part portland cement to two parts sand (100% passing a No. 8 sieve). Add sufficient water to form a damp formable consistency.

C. Expansive Grout: Premixed, cementitious mixture with a minimum 28-day strength of 3,500 psi. Provide air-entraining admixture as recommended by the manufacturer.

D. Epoxy Grout:

1. Mix the two components of epoxy bonding compound in compliance with the manufacturer's instructions.

2. Use sand that is oven dry and meets the following gradation requirements for epoxy grout:

Sieve Size No. 8 No. 50 No. 100
% Passing 100 30 ±15 5 ±5

2.22 GROUT BEDDING FOR HORIZONTAL JOINTS
The grout placed on horizontal construction joints shall be a mixture of cement, sand, and water in the same proportions and strength used in the overplaced concrete with coarse aggregate omitted.

Page 235 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-7
Main Lift Station Force Main B Air Release Valves Replacement Project

2.23 REPAIR MORTAR
A. Mortar used for repair of concrete voids shall be made of the same materials as used for concrete, except that the coarse aggregate shall be omitted or the mortar shall consist of not more than one part cement to two and one-half parts sand by damp loose volume.

The quantity of mixing water shall be no more than necessary for handling and placing.

B. Materials for repair of major defects or cracks shall be in accordance with “Repair of Defects and Cracks” specified in Part 3.

2.24 BONDING COMPOUND
A. Epoxy bonding compound shall be Sikadur 32 Hi-Mod, Sika Chemical Corporation, Lyndhurst, New Jersey; Concresive by BASF; Euco Epoxy 452 by Euclid Chemical Company; or equal.

B. Nonepoxy bonding compound shall be Weldcrete by Larsen Products Corp., Link by Sta-Dry Manufacturing Corp., Euco Weld by Euclid Chemical Co., or equivalent. The compound shall be rewettable for up to two weeks.

2.25 CONCRETE MIX DESIGN
A. Conform to ASTM C94, except as modified by these specifications.

B. Air content as determined by ASTM C231 shall be 4% ±1%.

C. Maximum water-cement ratio for Class A concrete = 0.45 by weight.

D. Use classes of concrete as described in the following table:

Class Type of Work
28-Day
Compressive
Strength
(in psi)
Minimum
Cement Content
(in lbs per C.Y.)
A Concrete for all slabs
and concrete not
otherwise specified.

Concrete fill at structure
foundations, cradle,
supports across pipe
trenches, and reinforced
pipe encasement.
4,000 564
E. Aggregate size shall be 3/4 inch maximum for slabs and sections 8 inches thick and less.

Aggregate size shall be 1 inch maximum for slabs and sections greater than 8 inches and less than 17 inches. Aggregate size shall be 1 1/2 inches maximum for all larger slabs and sections. Aggregate size for floor grout shall be maximum 3/8 inch.

Page 236 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-8
Main Lift Station Force Main B Air Release Valves Replacement Project F. Combined aggregate grading shall be as shown in the following table:

Maximum Aggregate Size
1 1/2" 1" 3/4" 3/8"
Aggregate Grade per
ASTM C33 467 57 67 8
G. Mix design for pumped concrete shall produce a plastic and workable mix. The percentage of sand in the mix shall be based on the void content of the coarse aggregate.

2.26 SLURRY CEMENT BACKFILL
A. Slurry cement backfill shall consist of a fluid, workable mixture of aggregate, cement, and water.

B. Aggregate shall be either:

1. Material selected from excavation, imported material, or a combination thereof, free from organic matter and other deleterious materials and meeting the following gradation:

Sieve Sieves Percentage Passing
1 1/2 inches 100
1 inch 80 to 100
3/4 inch 60 to 100
3/8 inch 50 to 100
No. 4 40 to 80
No. 100 10 to 40

2. Commercial quality concrete sand.

C. Proportion the aggregate, cement, and water by either weight or volume. Include at least 94 pounds of cement per cubic yard produced. The water content shall be sufficient to produce a fluid, workable mix that will flow and can be pumped without segregation of the aggregate while being placed.

D. Thoroughly machine-mix the materials for the slurry cement backfill in pugmill, rotary drum, or other mixer. Continue the mixing until the cement and water are thoroughly dispersed throughout the material. Place slurry cement backfill within one hour after mixing.

2.27 CURING COMPOUND
A. Curing compound shall conform to ASTM C309, Type 1, Class A.

Page 237 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-9
Main Lift Station Force Main B Air Release Valves Replacement Project B. Curing compound shall be compatible with required finishes and coatings and shall meet the State of California Clean Air Quality Standards which limit the quantity of volatile organic compounds.

2.28 MATS, PAPER, AND SHEETING FOR CURING
A. Burlap mats shall conform to AASHTO M182.

B. Sisal-kraft paper and polyethylene sheets shall conform to ASTM C171.

2.29 REINFORCING DOWEL ADHESIVE
Dowel anchor adhesive shall be HIT-RE 500-SD by Hilti; Sikadur 31, Hi-Mod Gel by Sika; or equal.

PART 3 - EXECUTION

3.01 FORM TOLERANCES
A. Failure of the forms to produce the specified concrete surface and surface tolerance shall be grounds for rejection of the concrete work. Rejected work shall be repaired or replaced at no additional cost to the Owner.

B. The following table indicates tolerances or allowable variations from dimensions or positions of structural concrete work:

Maximum Tolerance
(inch)
Sleeves and inserts +1/4 -1/4
Projected ends of anchors +1/4 -0.0
Anchor bolt setting +1/4 -1/4
Finished concrete, all locations
+1/4 -1/4 in 10 feet
Max ±1-inch in total length
The planes or axes from which the above tolerances are to be measured shall be as follows:

Sleeves and inserts: Centerline of sleeve or insert.

Projected ends of anchors: Plane perpendicular to the end of the anchor as located in the drawings.

Anchor bolt setting: Centerline of anchor bolt.

Finish concrete: The concrete surface as defined in the drawings.

Page 238 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-10
Main Lift Station Force Main B Air Release Valves Replacement Project Where equipment is to be installed, comply with manufacturer's tolerances if more restrictive than above.

3.02 FORM SURFACE PREPARATION
A. Clean form surfaces to be in contact with concrete of foreign material prior to installation.

B. Coat form surfaces in contact with concrete with a release agent prior to form installation.

3.03 FORM REUSE
Reuse only forms that provide a uniform surface texture on exposed concrete surfaces.

Apply light sanding or other surface treatment between uses for uniform texture. Plug unused tie rod holes with corks, shave flush, and sand the concrete surface side. Do not patch forms other than filling tie rod holes, except in the case of Class II forms. Do not use metal patching discs on Class I forms.

3.04 REMOVAL OF FORMS
A. Forms and shoring for elevated structural slabs or beams shall remain in place until the concrete has reached a compressive strength equal to the specified 28-day compressive strength as determined by test cylinders. Do not remove supports and reshore. The following table indicates the minimum allowable time after the last cast concrete is placed before forms, shoring, or wall bracing may be removed:

Sides of footings and encasements 24 hours
Walls, vertical sides of beams, girders,
columns, and similar members not
supporting loads 48 hours
Slabs, beams, and girders 10 days (forms only)
Shoring for slabs, beams, and girders Until concrete strength reaches specified 28-day strength
Wall bracing Until top or roof slab concrete
reaches specified 28-day strength
B. Do not remove forms from concrete that has been placed with outside air temperature below 50°F without first determining if the concrete has properly set without regard for time. Do not apply heavy loading on green concrete. Immediately after forms are removed, the surface of the concrete shall be carefully examined and any irregularities in the surface shall be repaired and finished as specified.

Page 239 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-11
Main Lift Station Force Main B Air Release Valves Replacement Project

3.05 FORMED OPENINGS
Openings shall be of sufficient size to permit final alignment of pipes or other items without deflection or offsets of any kind. Allow space for packing where items pass through the wall to ensure watertightness. Provide openings with continuous keyways and water stops. Provide a slight flare to facilitate grouting and the escape of entrained air during grouting. Provide formed openings with reinforcement as indicated in the typical structural details. Reinforcing shall be at least 2 inches clear from the opening surfaces and encased items.

3.06 EMBEDDED ITEMS
Set anchor bolts and other embedded items accurately and hold securely in position until the concrete is placed and set. Check all special castings, channels, or other metal parts that are to be embedded in the concrete prior to and again after concreting. Check nailing blocks, plugs, and strips necessary for the attachment of trim, finish, and similar work prior to concreting.

3.07 BEVELED EDGES (CHAMFER)
Form 3/4-inch beveled edges on exposed concrete edges and corners, beam soffit corners, and where indicated in the drawings. Reentrant corners in concrete members shall not have fillets, unless otherwise shown in the drawings. The top edges of slabs, walkways, beams, and walls may be beveled with an edging trowel in lieu of using chamfer strips.

3.08 CONSTRUCTION JOINTS
A. Provide construction joints where shown in the drawings.

3.09 EXPANSION JOINTS
Provide expansion joints with continuous edge reservoirs, which shall be filled with a joint sealant. Leave the material used for forming the reservoirs in place until immediately before the grooves are cleaned and filled with joint sealant. After removing edge forms from the reservoir, remove grout, loose concrete, and fins; then sandblast the slots. Allow the reservoirs to become thoroughly dry; then blow out the reservoirs and immediately prime and fill with the expansion joint sealant and backup materials. The primer used shall be supplied by the same manufacturer supplying the joint sealant.

3.10 TIME BETWEEN POURS
At least two hours shall elapse after depositing concrete in the columns or walls before depositing in beams, girders, or slabs supported thereon. Place beams, girders, brackets, column capitals, and haunches monolithically as part of the floor or roof system, unless otherwise indicated in the drawings.

Page 240 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-12
Main Lift Station Force Main B Air Release Valves Replacement Project

3.11 INSTALLATION OF PREMOLDED JOINT FILLER
Install in joint accurately as shown. Attach to concrete with a bonding agent recommended by the joint sealant and joint filler manufacturer for compatibility.

3.12 INSTALLATION OF JOINT SEALANTS
A. Immediately before installing the joint sealant, clean the joint cavity by sandblasting or power wire brushing. Install bond breaker tape per manufacturer's instructions.

B. After the joints have been prepared as described above, apply the joint sealant. Apply the primer, if required, and joint sealant only with the equipment and methods recommended by the joint sealant manufacturer. Application criteria for the sealant materials, such as temperature and moisture requirements and primer cure time, shall be in accordance with the recommendations of the sealant manufacturer.

C. Apply masking tape along the edges of the exposed surface of the exposed joints. Trowel the joints smooth with a tuck pointing tool wiped with a solvent recommended by the sealant manufacturer.

D. After the sealant has been applied, remove the masking tape and any sealant spillage.

3.13 INSTALLATION OF STEEL EXPANSION JOINT DOWELS
Align dowels as indicated in the drawings. Secure tightly in forms with rigid ties. Orient dowels to permit joint movement.

3.14 PLACING REINFORCEMENT
A. Place reinforcing steel in accordance with the current edition of Recommended Practice for Placing Reinforcing Bars, published by the Concrete Reinforcing Steel Institute.

B. Place reinforcing in accordance with the following, unless otherwise indicated:

1. Reinforcement indicated in the drawings is continuous through the structure to the farthest extent possible. Terminate bars and hooks 2 inches clear from faces of concrete.

2. Splices may be used to provide continuity due to bar length limitations. Minimum length of bars spliced for this reason is 30 feet. Splicing of reinforcement that is detailed to be continuous in the drawings is not permitted.

C. Reinforcing steel, before being positioned and just prior to placing concrete, shall be free from loose mill and rust scale and from any coatings that may destroy or reduce the bond. Clean reinforcing steel by sandblasting or wire brushing and remove mortar, oil, or dirt to remove materials that may reduce the bond.

D. Do not straighten or rebend reinforcing steel in the field.

Page 241 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-13
Main Lift Station Force Main B Air Release Valves Replacement Project E. Position reinforcing steel in accordance with the drawings and secure by using annealed wire ties or clips at intersections and support by concrete or metal supports, spacers, or metal hangers. Do not place metal clips or supports in contact with the forms. Bend tie wires away from the forms to provide the specified concrete coverage. Bars, in addition to those shown in the drawings, which may be found necessary or desirable by the Contractor for the purpose of securing reinforcement in position shall be provided by the Contractor at his own expense.

F. Place reinforcement a minimum of 2 inches clear of any metal pipe or fittings.

G. Secure reinforcing dowels in place prior to placing concrete. Do not press dowels into the concrete after the concrete has been placed.

H. Roll wire mesh used for reinforcement flat before placing concrete. Support and tie wire mesh to prevent movement during concrete placement.

I. Position dowels for masonry walls to occur at reinforced block cells.

3.15 SITE-MIXED CONCRETE
Conform to ACI 304.

3.16 READY-MIXED CONCRETE
Conform to ASTM C94.

3.17 PLACING CONCRETE
Conform to ACI 304.

3.18 PUMPING CONCRETE
Conform to ACI 304.2R-91.

3.19 WEATHER REQUIREMENTS
A. Conform to ACI 305 for placing during hot weather.

B. Conform to ACI 306 for placing during cold weather.

3.20 BONDING TO OLD CONCRETE
Coat the contact surfaces of structural sections with epoxy bonding compound when noted in the drawings. The method of preparation and application of the bonding compound shall conform to the manufacturer's printed instructions and recommendations for specific application for this project.

Page 242 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-14
Main Lift Station Force Main B Air Release Valves Replacement Project

3.21 BACKFILL AGAINST WALLS
A. Do not place backfill against walls until the concrete has obtained a compressive strength equal to the specified 28-day compressive strength. Where backfill is to be placed on both sides of the wall, place the backfill uniformly on both sides.

B. Do not backfill the walls of structures that are laterally restrained or supported by suspended slabs or slabs on grade until the slab is poured and the concrete has reached the specified compressive strength.

3.22 PLACING SLURRY CEMENT BACKFILL
Place slurry cement backfill in a uniform manner that will prevent voids in, or segregation of, the backfill. Remove foreign material that falls into the excavation or trench. Do not commence backfilling over or place any material over the slurry cement backfill until at least four hours after placing the slurry cement backfill, except that when concrete sand is used for the aggregate and the in-place material is free draining, backfilling may commence as soon as the surface water is gone.

3.23 CONCRETE FINISHES
A. Complete concrete surfaces in accordance with the following schedule:

Finish
Designation Area Applied
F-1 Beams, columns, and exterior walls not exposed to view.

F-3 Beams, columns, and walls of structures or buildings exposed to view. Underside of formed floors or slabs.

F-4 Exterior and interior surfaces to be coated.

S-1 Slabs and floors to be covered with concrete or grout.

S-4 Slabs and floors of structures or buildings exposed to view.

S-5 Slabs and floors at slopes greater than 10% and stairs.

E-1 Exposed edges. EXCEPTION: edges normally covered
with earth.

E-2 Top of walls, beams, and similar unformed surfaces.

B. Finish F-1: Repair defective concrete, fill depressions deeper than 1/2 inch, and fill tie holes.

Finish F-3: In addition to Finish F-1, remove fins, fill depressions 1/4 inch or deeper, fill depressions and airholes with mortar. Dampen surfaces and then spread a slurry consisting of one part cement and one and one-half parts sand by damp loose volume, over the surface with clean burlap pads or sponge rubber floats. Remove any surplus by scraping and then rubbing with clean burlap.

Page 243 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-15
Main Lift Station Force Main B Air Release Valves Replacement Project Finish F-4: Repair defective concrete, remove fins, fill depressions 1/16 inch or deeper, fill tie holes, remove mortar spatter, and remove bulges higher than 1/16 inch.

Finish S-1: Screed to grade without special finish.

Finish S-4: Steel trowel finish without local depressions or high points and apply a light hair-broom finish. Do not use stiff bristle brooms or brushes. Leave hair-broom lines parallel to the direction of slab drainage.

Finish S-5: Steel trowel finish without local depressions or high points. Apply a stiff bristle broom finish. Leave broom lines parallel to the direction of slope drainage.

Finish E-1: Provide chamfer or beveled edges.

Finish E-2: Strike smooth and float to an F-3 or F-4 finish.

3.24 CURING CONCRETE
A. Conform to ACI 308.

B. Water cure with burlap mats unless optional curing methods are permitted.

C. It is the responsibility of the Contractor to select the appropriate curing method in response to climatical and/or site conditions occurring at the time of concrete placement.

Take appropriate measures as described in ACI 305 and 306 for protecting and curing concrete during hot and cold weather.

3.25 REPAIR OF DEFECTS AND CRACKS
A. Do not repair defects until concrete has been evaluated by the Owner's Representative.

B. Surface Defects:

1. Repair surface defects that are smaller than 1 foot across in any direction and are less than 1/2 inch in depth.

2. Repair by removing the honeycombed and other defective concrete down to sound concrete, cut or grind edges perpendicular to the surface and at least 3/8 inch deep, abrasive clean and thoroughly dampen the surface, work into the surface an epoxy bonding agent, and fill the hole with one part cement to one part fine sand. Match the finish on the adjacent concrete, and cure as specified.

C. Severe Defects:

1. Repair severe defects that are larger than surface defects but do not appear to affect the structural integrity of the structure.

2. Repair by removing the honeycombed and other defective concrete down to sound concrete, make edges of the repair area perpendicular to the surface, as required

Page 244 of 762 ends

GENERAL CONCRETE CONSTRUCTION 030500-16
Main Lift Station Force Main B Air Release Valves Replacement Project above, sandblast the sound concrete surface, coat the exposed surfaces with epoxy bonding compound, place nonshrink grout, match the finish on the adjacent concrete, and cure as specified.

D. Repair minor cracks in concrete structures that are wider than 1/10 inch by cutting out a square edged and uniformly aligned joint 3/8 inch wide by 3/4 inch deep, preparing exposed surfaces of the joint, priming the joint, and applying polyurethane joint sealant.

E. If the cracks are major or affect the hydraulic capacity or function of the element, the Owner's Representative may require the concrete to be repaired by epoxy injection.

F. Major Defects and Cracks: If the defects affect the structural integrity of the structure or if patching does not satisfactorily restore quality and appearance to the surface, the Owner’s Representative may require the concrete to be removed and replaced, complete.

3.26 CONCRETE TESTS
A. Concrete quality testing will be performed on the concrete by the Owner as follows:

1. Frequency of Sampling: Cast four concrete test cylinders from each class of concrete placed in any one day. Sampling and curing of cylinders shall conform to ASTM C31.

2. Strength Testing: Test cylinders in accordance with ASTM C39. Test one cylinder at 7 days for information; test two cylinders at 28 days for acceptance; and hold one cylinder for verification. Strength acceptance will be based on the average of the strengths of the two cylinders tested at 28 days. If one cylinder of a 28-day test manifests evidence of improper sampling, molding, or testing, other than low strength, discard it and use the fourth cylinder for the test result.

3. Determine concrete slump by ASTM C143 with each strength test sampling and as required to establish consistency.

4. Determine air content of the concrete using ASTM C231 to verify the percentage of air in the concrete immediately prior to depositing in forms.

B. To facilitate concrete sampling and testing, the Contractor shall:

1. Furnish labor to assist the Owner in obtaining and handling samples at the project site.

2. Advise the Owner in advance of concrete placing operations to allow for scheduling and completion of quality testing.

3. Provide and maintain facilities for safe storage and proper curing of concrete test specimens on the project site, as required by ASTM C31.

END OF SECTION

Page 245 of 762 ends

PAINTING AND COATING 099000-1
Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 099000 PAINTING AND COATING
PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and application of painting and coating systems for the following surfaces:

A. Submerged metal.

B. Exposed metal
C. Buried metal.

1.02 RELATED WORK SPECIFIED ELSEWHERE
A. General Concrete Construction: 030500.

1.03 SUBMITTALS
A. Submit shop drawings in accordance with the General Conditions and Section 013300.

B. Submit manufacturer’s data sheets showing the following information:

1. Percent solids by volume.

2. Minimum and maximum recommended dry-film thickness per coat for prime, intermediate, and finish coats.

3. Recommended surface preparation.

4. Recommended thinners.

5. Statement verifying that the specified prime coat is recommended by the manufacturer for use with the specified intermediate and finish coats.

6. Application instructions including recommended equipment and temperature limitations.

7. Curing requirements and instructions.

C. Submit color swatches.

D. Submit certificate and supplier’s data sheets identifying the type and gradation of abrasives used for surface preparation. The certificate or data sheets shall specifically

Page 246 of 762 ends

PAINTING AND COATING 099000-2
Main Lift Station Force Main B Air Release Valves Replacement Project

identify that the abrasives comply with federal and state of California regulations for materials to be used for abrasive blasting for surface preparation for paints and coatings.

E. Submit material safety data sheets for each coating.

1.04 MANUFACTURER’S SERVICES
Provide coating manufacturer’s services for coatings applied at the jobsite for the minimum labor days listed below, travel time excluded:

A. Two labor days to advise the coating applicators on the following subjects at a minimum: use of plural component equipment (or other application equipment) for the application of the particular coatings specified for the Project ; required degree of mixing for each coating; required coating temperature range during the mixing operations; required coating temperature range in the application or spraying equipment; allowable pot life for each coating; required application viscosity range for each coating; use of dehumidification equipment for the application of the particular coatings specified for the Project ; ambient application temperature range for each coating layer; substrate or surface application temperature range for each coating layer; ambient application relative humidity range for each coating layer; curing requirements for each coating layer; and any particular special issues such as amine blush, formation of exudates, or other chemistry issues and the procedures to be followed to avoid application or curing failures.

B. Two labor days to observe the initial coating applications and make recommendations to the coating applicators regarding any revisions to the coating application procedures.

PART 2 - MATERIALS

2.01 PAINTING AND COATING SYSTEMS
The following index lists the various painting and coating systems by service and generic type:

PAINT COATINGS SYSTEM INDEX

No. Title Generic Coating
Submerged Metal Coating Systems

7. Submerged Metal, Wastewater Epoxy
Exposed Metal Coating Systems

10. Exposed Metal, Corrosive Environment Water-based urethane alkyd

52. Exposed Metal, Galvanized Steel and Copper Synthetic resin Buried Metal Coating Systems

21. Buried Metal Epoxy

Page 247 of 762 ends

PAINTING AND COATING 099000-3
Main Lift Station Force Main B Air Release Valves Replacement Project

25. Buried Metal Piping and Tubing Coal-tar, wax, and
polyethylene tape wrap or
extruded polyethylene
These systems are specified in detail in the following paragraphs. For each coating, the required surface preparation, prime coat, intermediate coat (if required), topcoat, and coating thicknesses are described. Mil thicknesses shown are minimum dry-film thicknesses.

2.02 SUBMERGED METAL COATING SYSTEMS
A. System No. 7--Submerged Metal, Wastewater:

Type: Epoxy.

Service Conditions: For use with structures, valves, piping, or equipment immersed in wastewater.

Surface Preparation: SSPC SP-10.

Coating System: Apply the manufacturer’s recommended number of coats to attain the specified minimum coating thickness. Products: Devoe Bar-Rust 233V, Sherwin- Williams Duraplate UHS B62-210 series, Scotchkote 323+, or equal; 16 mils total. Color of topcoat: pearl gray (pearl gray shall match Benjamin Moore Pearl Gray / 863 / #dee2d9 Hex Color Code). Each coat shall be different color than the one preceding it.

2.03 EXPOSED METAL COATING SYSTEMS
A. System No. 10--Exposed Metal, Corrosive Environment:

Type: Water-based alkyd prime coat having a volume solids of 40.9% ± 2%, with a water-based urethane alkyd finish coat having a minimum volume solids of 37.2% ± 2%.

Service Conditions: For use with metal structures or pipes subjected to water condensation; chemical fumes, such as hydrogen sulfide; salt spray; and chemical contact.

Surface Preparation: SSPC SP-10.

Prime Coat: Water-based alkyd coating recommended by the manufacturer for overcoating with a urethane alkyd finish coat. Apply to a minimum thickness of 2 mils.

Products: Dunn-Edwards BLOC-RUST Premium BRPR00-2-WH, or equal.

Finish Coat: Water-based urethane alkyd coating. Apply two (2) coats to a thickness of at least 1.5 mils per coat. Products: Dunn-Edwards ARISTOSHIELD Semi-Gloss ASHL50, color code DE-576, or equal. pearl gray (pearl gray shall match Benjamin Moore Pearl Gray / 863 / #dee2d9 Hex Color Code). buried metal Coating Systems

Page 248 of 762 ends

PAINTING AND COATING 099000-4
Main Lift Station Force Main B Air Release Valves Replacement Project

B. System No. 52--Exposed Metal, Galvanized Steel and Copper:

Type: Synthetic resin or epoxy primer.

Service Conditions: Coat galvanized steel and copper surfaces with this system before applying topcoat.

Surface Preparation of Galvanized Steel: Surfaces shall be flat with no protrusions.

Remove high spots and tears in the galvanizing with hand and power grinders. Comply with ASTM D6386, paragraph 5.2.1. Do not remove the galvanized coating below the specified thickness. Solvent clean galvanized surfaces per ASTM D6386, paragraph

5.3.2. Then sweep blast per ASTM D6386, paragraph 5.4.1. Use one of the abrasive materials that is described in ASTM D6386, paragraph 5.4.1. Surface preparation for weathered and partially weathered galvanized steel shall be in accordance with ASTM D6386, paragraphs 6 and 7. Apply prime coating within one hour of the surface preparation.

Surface Preparation of Copper: Solvent clean or steam clean copper surfaces per SSPC SP-1; do not use alkali cleaning. Then dust blast.

Prime Coat: Tnemec N69-1211, PPG Amercoat 385, Devoe Devran 224HS, Carboline 890, Sherwin-Williams Macropoxy 646 B58-600 series, PPG PITT-GUARD® Direct- to-Rust Epoxy Mastic Coating 97-145 series, or equal. Apply to a minimum thickness of 4 mils.

2.04 BURIED METAL COATING SYSTEMS
A. System No. 21--Buried Metal:

Type: High solids epoxy or phenolic epoxy having a minimum volume solids of 80% (ASTM D2697).

Service Conditions: Buried metal, such as valves, flanges, bolts, nuts, structural steel, and fittings.

Surface Preparation: SSPC SP-10.

Coating System: Apply three or more coats of PPG Amerlock 400 or 400VOC, Tnemec 104HS or 80, Devoe Bar-Rust 233H, Carboline 890LT, Sherwin-Williams Tank Clad HS B62-80 series, or equal; 30 mils total. Maximum thickness of an individual coating shall not exceed the manufacturer’s recommendation.

B. System No. 25--Buried Metal Piping and Tubing:

Type: Cold-applied coal-tar tape, hot-applied coal-tar tape, extruded polyethylene or cold-applied wax tape.

Service Conditions: Buried ferrous and nonferrous piping and tubing.

Page 249 of 762 ends

PAINTING AND COATING 099000-5
Main Lift Station Force Main B Air Release Valves Replacement Project

Coat with one of the following systems:

1. Wrap with cold-applied coal-tar tape conforming to AWWA C209. Minimum thickness of tape shall be 35 mils. Apply tape with manufacturer’s prime coat.

Tape shall be Tapecoat CT, Protecto-Wrap 200, or equal.

2. Wrap with hot-applied coal-tar tape conforming to AWWA C203, Section 4.6.

Minimum thickness of tape shall be 50 mils. Apply tape with manufacturer’s recommended prime coat. Tape shall be Tapecoat 20, Protecto-Wrap 110, or equal.

3. Wrap with cold-applied wax tape per Section 099752.

Use chloride-free primers with the above coatings when applying to stainless steel piping or tubing.

Coat field joints of buried piping that has a shop-applied coating with primer and tape conforming to AWWA C209. Use Type 1 tape of 35-mil thickness. Products: Protection Engineering Co. Protectowrap 200 GT, Tapecoat CT10/40W, Polyken 930-35, or equal.

Perform electrical inspection of shop and field coating in accordance with Section 5 of AWWA C209.

Install buried pipes with wrapped coatings by extending the wrapping to the first joint after entering a building, penetrating a slab, or 6 inches above finished grade. Wrap joints spirally with a minimum overlap of 50% of the tape width.

2.05 ABRASIVES FOR SURFACE PREPARATION
A. Abrasives used for preparation of ferrous (excluding stainless steel) surfaces shall be one of the following:

1. 16 to 30 or 16 to 40 mesh silica sand or mineral grit.

2. 20 to 40 mesh garnet.

3. Crushed iron slag, 100% retained on No. 80 mesh.

4. SAE Grade G-40 or G-50 iron or steel grit.

B. In the above gradations, 100% of the material shall pass through the first stated sieve size and 100% shall be retained on the second stated sieve size.

PART 3 - EXECUTION

3.01 WEATHER CONDITIONS
A. Do not paint in the rain, wind, snow, mist, and fog or when steel or metal surface temperatures are less than 5°F above the dew point.

Page 250 of 762 ends

PAINTING AND COATING 099000-6
Main Lift Station Force Main B Air Release Valves Replacement Project

B. Do not apply paint when the relative humidity is above 85%.

C. Do not paint when temperature of metal to be painted is above 120°F.

D. Do not apply inorganic or organic zinc, silicone aluminum, or silicone acrylic paints if air or surface temperature is below 40°F or expected to be below 40°F within 24 hours.

E. Do not apply epoxy, acrylic latex, and polyurethane paints on an exterior or interior surface if air or surface temperature is below 60°F or expected to drop below 60°F in 24 hours.

3.02 SURFACE PREPARATION PROCEDURES
A. Remove oil and grease from metal surfaces in accordance with SSPC SP-1. Use clean cloths and cleaning solvents and wipe dry with clean cloths. Do not leave a film or greasy residue on the cleaned surfaces before abrasive blasting.

B. Remove weld spatter and weld slag from metal surfaces and grind smoothly rough welds, beads, peaked corners, and sharp edges including erection lugs in accordance with SSPC SP-2 and SSPC SP-3. Grind 0.020 inch (minimum) off the weld caps on pipe weld seams. Grind outside sharp corners, such as the outside edges of flanges, to a minimum radius of 1/4 inch.

C. Do not abrasive blast or prepare more surface area in one day than can be coated in one day; prepare surfaces and apply coatings the same day. Remove sharp edges, burrs, and weld spatter.

D. Do not abrasive blast epoxy- or enamel-coated pipe that has already been factory coated, except to repair scratched or damaged coatings.

E. For carbon steel, do not touch the surface between the time of abrasive blasting and the time the coating is applied. Apply coatings within two hours of blasting or before any rust bloom forms.

F. Surface preparation shall conform with the SSPC specifications as follows:

Page 251 of 762 ends

PAINTING AND COATING 099000-7
Main Lift Station Force Main B Air Release Valves Replacement Project

Solvent Cleaning SP-1
Hand Tool Cleaning SP-2
Power Tool Cleaning SP-3
White Metal Blast Cleaning SP-5
Commercial Blast Cleaning SP-6
Brush-Off Blast Cleaning SP-7
Pickling SP-8
Near-White Blast Cleaning SP-10
Power Tool Cleaning to Bare Metal SP-11
Surface Preparation and Cleaning of Steel and Other
Hard Materials by High- and Ultrahigh-Pressure Water
Jetting Prior to Recoating
SP-12
Surface Preparation of Concrete SP-13
G. Wherever the words “solvent cleaning,” “hand tool cleaning,” “wire brushing,” or “blast cleaning” or similar words are used in these specifications or in paint manufacturer’s specifications, they shall be understood to refer to the applicable SSPC (Steel Structure Painting Council), surface preparation specifications listed above.

H. Dust blasting is defined as cleaning the surface through the use of very fine abrasives, such as siliceous or mineral abrasives, 80 to 100 mesh. Apply a fine etch to the metal surface to clean the surface of any contamination or oxide and to provide a surface profile for the coating.

I. For carbon steel surfaces, after abrasive blast cleaning, the height of the surface profile shall be 2 to 3 mils. Verify the surface profile by measuring with an impresser tape acceptable to the Project Manager. Perform a minimum of one test per 100 square feet of surface area. Testing shall be witnessed by the Project Manager. The impresser tape used in the test shall be permanently marked with the date, time, and locations where the test was made. Test results shall be promptly presented to the Project Manager.

J. Do not apply any part of a coating system before the Project Manager has reviewed the surface preparation. If coating has been applied without this review, if directed by the Project Manager, remove the applied coating by abrasive blasting and reapply the coat in accordance with this specification.

3.03 ABRASIVE BLAST CLEANING
A. Use dry abrasive blast cleaning for metal surfaces. Do not use abrasives in automatic equipment that have become contaminated. When shop or field blast cleaning with handheld nozzles, do not recycle or reuse blast particles.

B. After abrasive blast cleaning and prior to application of coating, dry clean surfaces to be coated by dusting, sweeping, and vacuuming to remove residue from blasting. Apply the

Page 252 of 762 ends

PAINTING AND COATING 099000-8
Main Lift Station Force Main B Air Release Valves Replacement Project

specified primer or touch-up coating within the period of an eight-hour working day. Do not apply coating over damp or moist surfaces. Reclean prior to application of primer or touch-up coating any blast cleaned surface not coated within said eight-hour period.

C. Keep the area of the work in a clean condition and do not permit blasting particles to accumulate and constitute a nuisance or hazard.

D. During abrasive blast cleaning, prevent damage to adjacent coatings. Schedule blast cleaning and coating such that dust, dirt, blast particles, old coatings, rust, mill scale, etc., will not damage or fall upon wet or newly coated surfaces.

3.04 PROCEDURES FOR ITEMS HAVING SHOP-APPLIED PRIME COATS A. After application of primer to surfaces, allow coating to cure for a minimum of two hours before handling to minimize damage.

B. When loading for shipment to the Project site, use spacers and other protective devices to separate items to prevent damaging the shop-primed surfaces during transit and unloading. If wood spacers are used, remove wood splinters and particles from the shop- primed surfaces after separation. Use padded chains or ribbon binders to secure the loaded items and minimize damage to the shop-primed surfaces.

C. Cover shop-primed items 100% with protective coverings or tarpaulins to prevent deposition of road salts, fuel residue, and other contaminants in transit.

D. Handle shop-primed items with care during unloading, installation, and erection operations to minimize damage. Do not place or store shop-primed items on the ground or on top of other work unless ground or work is covered with a protective covering or tarpaulin. Place shop-primed items above the ground upon platforms, skids, or other supports.

3.05 FIELD TOUCH-UP OF SHOP-APPLIED PRIME COATS
A. Remove oil and grease surface contaminants on metal surfaces in accordance with SSPC SP-1. Use clean rags wetted with a degreasing solution, rinse with clean water, and wipe dry.

B. Remove dust, dirt, salts, moisture, chalking primers, or other surface contaminants that will affect the adhesion or durability of the coating system. Use a high-pressure water blaster or scrub surfaces with a broom or brush wetted with a solution of trisodium phosphate, detergent, and water. Before applying intermediate or finish coats to inorganic zinc primers, remove any soluble zinc salts that have formed by means of scrubbing with a stiff bristle brush. Rinse scrubbed surfaces with clean water.

C. Remove loose or peeling primer and other surface contaminants not easily removed by the previous cleaning methods in accordance with SSPC SP-7. Take care that remaining primers are not damaged by the blast cleaning operation. Remaining primers shall be firmly bonded to the steel surfaces with blast cleaned edges feathered.

Page 253 of 762 ends

PAINTING AND COATING 099000-9
Main Lift Station Force Main B Air Release Valves Replacement Project

D. Remove rust, scaling, or primer damaged by welding or during shipment, storage, and erection in accordance with SSPC SP-10. Take care that remaining primers are not damaged by the blast cleaning operation. Areas smaller than 1 square inch may be prepared per SSPC SP-11. Remaining primers shall be firmly bonded to the steel surfaces with cleaned edges feathered.

E. Use repair procedures on damaged primer that protects adjacent primer. Blast cleaning may require the use of lower air pressure, smaller nozzles, and abrasive particle sizes, short blast nozzle distance from surface, shielding, and/or masking.

F. After abrasive blast cleaning of damaged and defective areas, remove dust, blast particles, and other debris by dusting, sweeping, and vacuuming; then apply the specified touch-up coating.

G. Other surfaces that are shop primed shall receive a field touch-up of the same primer used in the original prime coat.

3.06 PAINTING SYSTEMS
A. All materials of a specified painting system, including primer, intermediate, and finish coats, shall be produced by the same manufacturer. Thinners, cleaners, driers, and other additives shall be as recommended by the paint manufacturer for the particular coating system.

B. Deliver paints to the jobsite in the original, unopened containers.

3.07 PAINT STORAGE AND MIXING
A. Store and mix materials only in areas designated for that purpose by the Project Manager. The area shall be well-ventilated, with precautionary measures taken to prevent fire hazards. Post “No Smoking” signs. Storage and mixing areas shall be clean and free of rags, waste, and scrapings. Tightly close containers after each use. Store paint at an ambient temperature from 50°F to 100°F.

B. Prepare multiple-component coatings using all of the contents of the container for each component as packaged by the paint manufacturer. Do not use partial batches. Do not use multiple-component coatings that have been mixed beyond their pot life. Provide small quantity kits for touch-up painting and for painting other small areas. Mix only the components specified and furnished by the paint manufacturer. Do not intermix additional components for reasons of color or otherwise, even within the same generic type of coating.

3.08 PROCEDURES FOR THE APPLICATION OF COATINGS
A. Conform to the requirements of SSPC PA-1. Follow the recommendations of the coating manufacturer including the selection of spray equipment, brushes, rollers, cleaners, thinners, mixing, drying time, temperature and humidity of application, and safety precautions.

Page 254 of 762 ends

PAINTING AND COATING 099000-10
Main Lift Station Force Main B Air Release Valves Replacement Project

B. Obtain and comply with the coating manufacturer’s recommendations concerning application requirements for the following minimum criteria:

1. Required plural component equipment (or other application equipment) for the application of the particular coatings specified for the Project.

2. Required degree of mixing for each coating.

3. Required coating temperature range during the mixing operations.

4. Required coating temperature range in the application or spraying equipment.

5. Allowable pot life for each coating.

6. Required application viscosity range for each coating.

7. Use of dehumidification equipment for the application of the particular coatings specified for the Project.

8. Ambient application temperature range for each coating layer.

9. Substrate or surface application temperature range for each coating layer.

10. Ambient application relative humidity range for each coating layer.

11. Curing requirements for each coating layer.

12. Any particular special issues such as amine blush, formation of exudates, or other chemistry issues and the procedures to be followed to avoid application or curing failures.

C. Stir, strain, and keep coating materials at a uniform consistency during application.

Power mix components. For multiple component materials, premix each component before combining. Apply each coating evenly, free of brush marks, sags, runs, and other evidence of poor workmanship. Use a different shade or tint on succeeding coating applications to indicate coverage where possible. Finished surfaces shall be free from defects or blemishes.

D. Do not use thinners unless recommended by the coating manufacturer. If thinning is allowed, do not exceed the maximum allowable amount of thinner per gallon of coating material. Stir coating materials at all times when adding thinner. Do not flood the coating material surface with thinner prior to mixing. Do not reduce coating materials more than is absolutely necessary to obtain the proper application characteristics and to obtain the specified dry-film thicknesses.

E. Remove dust, blast particles, and other debris from blast cleaned surfaces by dusting, sweeping, and vacuuming. Allow ventilator fans to clean airborne dust to provide good

Page 255 of 762 ends

PAINTING AND COATING 099000-11
Main Lift Station Force Main B Air Release Valves Replacement Project

visibility of working area prior to coating applications. Remove dust from coated surfaces by dusting, sweeping, and vacuuming prior to applying succeeding coats.

F. Apply coating systems to the specified minimum dry-film thicknesses as determined per SSPC PA-2.

G. Apply primer immediately after blast cleaning and before any surface rusting occurs, or any dust, dirt, or any foreign matter has accumulated. Reclean surfaces by blast cleaning that have surface colored or become moist prior to coating application.

H. Apply a brush coat of primer on welds, sharp edges, nuts, bolts, and irregular surfaces prior to the application of the primer and finish coat. Apply the brush coat prior to and in conjunction with the spray coat application. Apply the spray coat over the brush coat.

I. Before applying subsequent coats, allow the primer and intermediate coats to dry for the minimum curing time recommended by the manufacturer. In no case shall the time between coats exceed the manufacturer’s recommendation.

J. Each coat shall cover the surface of the preceding coat completely, and there shall be a visually perceptible difference in applied shade or tint of colors.

K. Applied coating systems shall be cured at 75°F or higher for 48 hours. If temperature is lower than 75°F, curing time shall be in accordance with printed recommendations of the manufacturer, unless otherwise allowed by the Project Manager.

L. Assembled parts shall be disassembled sufficiently before painting or coating to ensure complete coverage by the required coating.

3.09 SURFACES NOT TO BE COATED
Do not paint the following surfaces unless otherwise noted in the drawings or in other specification sections. Protect during the painting of adjacent areas:

A. Concrete
B. Stainless steel.

3.10 PROTECTION OF SURFACES NOT TO BE PAINTED
Remove, mask, or otherwise protect hardware, lighting fixtures, switch plates, aluminum surfaces, machined surfaces, couplings, shafts, bearings, nameplates on machinery, and other surfaces not intended to be painted. Provide drop cloths to prevent paint materials from falling on or marring adjacent surfaces. Protect working parts of mechanical and electrical equipment from damage during surface preparation and painting process. Mask openings in motors to prevent paint and other materials from entering the motors.

Page 256 of 762 ends

PAINTING AND COATING 099000-12
Main Lift Station Force Main B Air Release Valves Replacement Project

3.11 SURFACES TO BE COATED
The exact coating to be applied in any location is not designated by the descriptive phrases in the coating system titles such as “corrosive environment,” “buried metal,” or “submerged metal.” Coat surfaces with the specific coating systems as described below:

A. Coat aboveground and exposed piping or piping in vaults and structures as described in the various piping specifications. Color of finish coat shall match existing piping.

B. Coat valves as described in the various valve specifications. Aboveground valves, or valves in vaults and structures, shall match the color of the connecting piping.

3.12 DRY-FILM THICKNESS TESTING
A. Measure coating thickness specified for carbon steel surfaces with a magnetic-type dry- film thickness gauge in accordance with SSPC PA-2. Provide certification that the gauge has been calibrated by a certified laboratory within the past six months. Provide dry-film thickness gauge as manufactured by Mikrotest or Elcometer.

B. Test the finish coat of metal surfaces (except zinc primer and galvanizing) for holidays and discontinuities with an electrical holiday detector, low-voltage, wet-sponge type.

Provide measuring equipment. Provide certification that the gauge has been calibrated by a certified laboratory within the past six months. Provide detector as manufactured by Tinker and Rasor or K-D Bird Dog.

C. Check each coat for the correct dry-film thickness. Do not measure within eight hours after application of the coating.

D. Perform tests in the presence of the Project Manager.

3.13 REPAIR OF IMPROPERLY COATED SURFACES
If the item has an improper finish color or insufficient film thickness, clean and topcoat the surface with the specified paint material to obtain the specified color and coverage.

Sandblast or power-sand visible areas of chipped, peeled, or abraded paint, feathering the edges. Then prime and finish coat in accordance with the specifications. Work shall be free of runs, bridges, shiners, laps, or other imperfections.

3.14 CLEANING
A. During the progress of the work, remove discarded materials, rubbish, cans, and rags at the end of each day’s work.

B. Thoroughly clean brushes and other application equipment at the end of each period of use and when changing to another paint or color.

Page 257 of 762 ends

PAINTING AND COATING 099000-13
Main Lift Station Force Main B Air Release Valves Replacement Project

C. Upon completion of painting work, remove masking tape, tarps, and other protective materials, using care not to damage finished surfaces.

END OF SECTION

Page 258 of 762 ends

PAINTING AND COATING 099000-14
Main Lift Station Force Main B Air Release Valves Replacement Project

THIS PAGE LEFT INTENTIONALLY BLANK

Page 259 of 762 ends

COLD-APPLIED WAX TAPE COATING 099752-1
Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 099752 COLD-APPLIED WAX TAPE COATING
PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and application of a three-part, cold-applied wax tape coating system for buried piping per NACE RP0375-2006, Section 4 except as modified herein.

Apply cold-applied wax tape coating system for buried piping, valves and fittings.

1.02 RELATED WORK SPECIFIED ELSEWHERE
Polyethylene Sheet Encasement (AWWA C105): 099754.

1.03 SUBMITTALS
A. Submit shop drawings in accordance with the General Conditions and Section 013300.

B. Submit manufacturer's catalog data sheets and application instructions.

PART 2 - MATERIALS

2.01 PRIMER
A. Primer shall be a blend of petrolatums, plasticizers, and corrosion inhibitors having a paste-like consistency. The primer shall comply with NACE RP0375-2006 and shall have the following properties:

1. Pour Point: 100°F to 110°F.

2. Flash Point: 350°F.

3. Coverage: 1 gallon per 100 square feet.

B. Primer shall be Trenton Wax Tape Primer, Denso Paste Primer, or equal.

2.02 WAX TAPE
A. Wax tape shall consist of a synthetic-fiber felt, saturated with a blend of microcrystalline wax, petrolatums, plasticizers, and corrosion inhibitors, forming a tape coating that is easily formable over irregular surfaces. The tape shall comply with NACE RP0375-2006 and shall have the following properties:

1. Saturant Pour Point: 115°F to 120°F.

Page 260 of 762 ends

COLD-APPLIED WAX TAPE COATING 099752-2
Main Lift Station Force Main B Air Release Valves Replacement Project

2. Thickness: 50 to 70 mils.

3. Tape Width: 6 inches.

B. Wax tapes used for pipe soil-to-air transitions shall be UV light stable so as not to degrade in the presence of sunlight.

C. Wax tape shall be Trenton No. 1 Wax Tape, Denso "Densyl Tape," or equal.

2.03 PLASTIC WRAPPER
A. Wrapper shall be a polyvinylidene chloride plastic with three 50-gauge plies wound together as a single sheet. The wrapper shall have the following properties:

1. Color: Clear.

2. Thickness: 1.5 mils.

3. Tape Width: 6 inches.

B. Plastic wrapper shall be Trenton Poly-Ply, Denso Tape PVC Self-Adhesive, or equal.

2.04 POLYETHYLENE SHEET COATING
See Section 099754.

PART 3 - EXECUTION

3.01 WAX TAPE COATING APPLICATION
A. Surfaces shall be clean and free of dirt, grease, water, and other foreign material prior to the application of the primer and wax tape.

B. Apply primer by hand or brush to fitting surfaces. Work the primer into crevices and completely cover exposed metal surfaces.

C. Apply the wax tape immediately after the primer application. Work the tape into the crevices around fittings. Apply the wax tape by pressing and molding the tape into conformity with the surface so that it does not bridge over irregular surfaces configurations. Begin wrapping approximately 3 inches behind the area to be wrapped.

If starting at a straight edge, wrap the tape spirally around the pipe while touching the end edge before starting the angle to begin the spiral. If the previous roll is headed in a downward direction, tuck the next roll under the previous roll. Stretch each roll tight as wrapping continues to avoid air bubbles.

D. Wrap the wax tape spirally around the pipe and across the fitting. Use a minimum overlap of 50% of the tape width. Apply tape to flanges, mechanical and restrained joint

Page 261 of 762 ends

COLD-APPLIED WAX TAPE COATING 099752-3
Main Lift Station Force Main B Air Release Valves Replacement Project

bolts, nuts and glands, and grooved-end couplings to 6 inches beyond each side of the item.

E. Work the tape into the crevices and contours of irregularly shaped surfaces and smooth out so that there is a continuous protective layer with no voids or spaces under the tape.

F. After application, seal the overlap seams of the tape by hand by tapering and pressing the seam, attempting to create a continuous surface. There shall be no air pockets underneath the tape. The tape shall have direct intimate contact with the pipe surface.

G. On vertical sections of the piping, such as at pipe-to-soil transitions, wrap the pipe starting from the bottom and proceeding upward so that downward flowing water and backfill do not catch in a seam.

H. Overwrap the completed wax tape installation with the plastic wrapping material. Wrap spirally around the pipe and across the fitting. Use a minimum overlap of 55% of the tape width and apply two layers or applications of overwrap. Secure plastic wrapper to pipe with adhesive tape.

3.02 APPLICATION OF POLYETHYLENE SHEET COATING TO BURIED PIPING Wrap completed wax tape coating system with polyethylene film per Section 099754 and secure around the adjacent pipe circumference with adhesive tape.

3.03 HANDLING AND INSTALLING WAX-TAPE COATED PIPE
A. Handle pipe in a manner to minimize damage to the coating. Equipment used for the handling of coated pipe shall be designed and constructed to avoid damaging the protective coating system. Inspect supported areas of the pipe prior to installation.

Repair damaged areas before installation.

B. The pipeline trench shall be free of rocks, foreign matter, and projections that could damage the coating system.

END OF SECTION

Page 262 of 762 ends

COLD-APPLIED WAX TAPE COATING 099752-4
Main Lift Station Force Main B Air Release Valves Replacement Project

THIS PAGE INTENTIONALLY LEFT BLANK

Page 263 of 762 ends

POLYETHYLENE SHEET ENCASEMENT (AWWA C105) 099754-1
Main Lift Station Force Main B Air Release Valves Replacement Project

SECTION 099754 POLYETHYLENE SHEET ENCASEMENT (AWWA C105) PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and installation of a polyethylene sheet encasement for buried ductile iron pipe, fittings, and valves.

1.02 RELATED WORK SPECIFIED ELSEWHERE
A. Cold-Applied Wax Tape Coating: 099752.

B. General Piping Requirements: 400500.

C. Manual, Check, and Process Valves.

D. Flexible Pipe Couplings and Expansion Joints: 400722.

E. Ductile-Iron Pipe: 402040.

1.03 SUBMITTALS
A. Submit shop drawings in accordance with General Conditions and Section 013300.

B. Submit manufacturer's catalog literature and product data sheets describing the physical, chemical, and electrical properties of the encasement material.

PART 2 - MATERIALS

2.01 POLYETHYLENE WRAP
A. The encasement shall consist of low-density polyethylene wrap of at least 8-mil thickness conforming to AWWA C105.

B. Polyethylene encasement for ductile-iron pipe shall be supplied as a flat tube meeting the dimensions of Table 1 in AWWA C105 and shall be supplied by the ductile-iron pipe manufacturer.

C. Provide enhanced 3 layer polyethylene wrap, V-Bio type wrap, or equal.

2.02 PLASTIC ADHESIVE TAPE
A. Tape shall consist of polyolefin backing and adhesive which bonds to common pipeline coatings including polyethylene.

Page 264 of 762 ends