AGREEMENT TO TERMINATE AND DISSOLVE THE CENTRAL COAST BLUE
REGIONAL RECYCLED WATER AUTHORITY
THIS AGREEMENT TO TERMINATE THE CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY (“Termination Agreement”), is made and entered into as of the date the Termination Agreement is fully executed by all parties, by and between the City of Pismo Beach, a California Municipal Corporation (“City”) and the Pismo Beach Public Financing Agency (“Agency”), herein referred to individually as a “Party,” and jointly as the “Parties”. For and in consideration of the mutual covenants and promises set forth herein, the Parties agree as set forth below, with reference to the following facts:
RECITALS
A.WHEREAS, the Cities of Arroyo Grande, Grover Beach, and Pismo Beach (collectively the “Original Member Agencies”) entered into a joint exercise of powers agreement (“Agreement”) for participation in the Central Coast Blue recycled water project, which Agreement established the Central Coast Blue Regional Recycled Water Authority (“Authority” or “JPA”) as a joint powers authority under Section 6500 et seq. of the Government Code of the State of California, effective October 7, 2022; and B.WHEREAS, the Original Member Agencies collectively agreed, by the First Amendment to the Agreement, to reflect the withdrawal of Arroyo Grande and Grover Beach, and to reflect the addition of the Pismo Beach Public Financing Agency as a Member Agency, under the Agreement, as well as other amended provisions, effective June 30, 2024; and C.WHEREAS, the remaining Member Agencies collectively agreed, by the Second Amendment to the Agreement, to formally effectuate the Pismo Beach Public Financing Agency’s status as a signatory to the Agreement, effective July 1, 2024; and D.WHEREAS, the Agreement states in Section 8.1 that “This Agreement shall […] continue in full force and effect until terminated by the mutual written agreement of all Member Agencies”; and
E.WHEREAS, the City of Pismo Beach and the Pismo Beach Public Financing Agency are the sole Member Agencies to the Authority; and
F.WHEREAS, the Member Agencies now desire to terminate the Authority; and G.WHEREAS, all assets, liabilities, contracts, and other powers and obligations of the Authority have been, or readily can be, transferred to, or are already within the control of, the City of Pismo Beach, including personnel, grant funding awards, budgeted funds, service agreements and leases, contractor and consultant solicitations, and real property, and as such there remains no need for a joint powers agreement between multiple agencies; and
H.WHEREAS, all other legal prerequisites to the Termination Agreement have been satisfied, and the Termination Agreement furthers the common benefit of the inhabitants of the city of Pismo Beach; and
Council Agenda 10-6-2026 9.G-11
Attachment 4
Packet Page 122
AGREEMENT TO TERMINATE AND DISSOLVE THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
I. WHEREAS, the City Council of the City of Pismo Beach, the Board of Directors of the Pismo Beach Public Financing Agency, and the Board of Directors of the Central Coast Blue Regional Recycled Water Authority have, by legislative action on October 6, 2022, authorized and directed the termination and dissolution of the Authority.
NOW THEREFORE, in consideration of the mutual covenants, agreements, and representations contained in this Termination Agreement, City and Agency agree as follows:
ARTICLE I
INCORPORATION OF RECITALS
1. The foregoing recitals are true and correct, and incorporated herein by the Parties as a material aspect of this Termination Agreement.
ARTICLE II
TERMINATION OF THE AUTHORITY
2. JPA Termination. Pursuant to the terms and conditions contained in this Termination Agreement, City and Agency agree to terminate and dissolve the Central Coast Blue Regional Recycled Water Authority joint powers authority as of the effective date of the latest resolution approving this Termination Agreement adopted by the governing bodies of the Parties.
ARTICLE III
TRANSFER OF AUTHORITY ASSETS
3.1 Transfer of Assets. Pursuant to the Authority Agreement Section 8.3, as revised by Amendment 1 to the Agreement, which states in pertinent part, “Upon termination of this Agreement, only those Member Agencies who are parties to this Agreement at the time of termination shall be permitted to participate in disbursement of Authority assets”, the Parties agree that all assets of the Authority shall be transferred to the City of Pismo Beach.
3.2 Rights to Recycled Water. The Parties hereto acknowledge and agree that the recycled water injected into the ground as part of the Central Coast Blue project and pursuant to the Authority Agreement, as well as all new developed water subsequently extracted, is New Developed Water as defined in the January 25, 2008 Judgment entered by the Santa Clara Superior Court in the “Santa Maria Groundwater Adjudication litigation” and is an asset of the Authority to be transferred to the City.
ARTICLE IV
REPRESENTATIONS AND WARRANTIES
4.1 City’s Representations and Warranties. City makes the following covenants, representations and warranties, each of which is material and is being relied upon by Agency:
A. Authority. City has the legal power, right, and authority to enter into this Termination Agreement and the instruments referenced herein, and to consummate the transactions contemplated hereby; requisite action has been Council Agenda 10-6-2026 9.G-12
Attachment 4
Packet Page 123
AGREEMENT TO TERMINATE AND DISSOLVE THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
taken by City in connection with the entering into of this Termination Agreement and the instruments referenced herein, and the consummation of the transactions contemplated hereby; and no consent of any other party is required.
B. Legal Power. The individuals executing this Termination Agreement and the instruments referenced herein on behalf of City, have the legal power, right and actual authority to bind City to the terms and conditions hereof and thereof.
4.2 Agency’s Representations, Warranties and Covenants. Agency makes the following representations, warranties and covenants, each of which is material and is being relied upon by City:
A. Authority. Agency has the legal power, right and authority to enter into this Termination Agreement and the instruments referenced herein, and to consummate the transactions contemplated hereby; all requisite action has been taken by Agency in connection with the entering into of this Termination Agreement and the instruments referenced herein, and the consummation of the transactions contemplated hereby; and no consent of any other party is required.
ARTICLE V
MISCELLANEOUS
5.1 Cooperation. Agency and City acknowledge that it may be necessary to execute documents other than those specifically referred to in this Termination Agreement to complete the dissolution of the Authority and transfer of its assets. Each party shall reasonably cooperate with the other in connection with the requirements imposed by this Termination Agreement upon the other, to the end that neither party shall act in any manner to impede the other in performing its obligations under this Termination Agreement. Agency and City hereby agree to cooperate with each other by executing such other documents or taking such other action as may be reasonably necessary in accordance with the intent of the parties as evidenced by this Termination Agreement, provided such documents do not create any additional liability or expense for such party not contemplated by this Termination Agreement.
5.2 Interpretation. This Termination Agreement shall be construed and enforced in accordance with the laws of the State of California as applicable to contracts entered into in California among parties doing business therein. This Termination Agreement may not be modified or amended in any way except by a writing executed by both Agency and City. The section headings of this Termination Agreement are for convenience only and are not to be construed as part of this Termination Agreement and do not in any way amplify or define the terms, conditions, and covenants of this Termination Agreement and shall not be used in construction or interpretation of this Termination Agreement.
There are no third-party beneficiaries to this Termination Agreement. Unless the context otherwise indicates, whenever used in this Termination Agreement, the word “party” or “parties” means Agency or City or both, as the context may require. Time is of the essence in the performance of each term of this Termination Agreement.
5.3 Successors and Assigns. This Termination Agreement shall be binding upon and inure to the benefits of the successors and assigns of the parties to this Termination Agreement.
Council Agenda 10-6-2026 9.G-13
Attachment 4
Packet Page 124
AGREEMENT TO TERMINATE AND DISSOLVE THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
5.4 Severability. If any term or provision of this Termination Agreement is determined to be invalid or unenforceable, the remaining terms and provisions shall not be affected thereby and shall remain in full force and effect to the maximum extent permitted by law.
5.5 Dates. Whenever any determination is to be made or action is to be taken on a date specified in this Termination Agreement, if such date shall fall on Saturday, Sunday, or legal holiday under the laws of the State of California, then in such event said date shall be extended to the next day which is not a Saturday, Sunday, or legal holiday.
5.6 Limitation of Liability. No advisor, trustee, director, officer, partner, member, employee, beneficiary, shareholder, participant or agent of or in City or Agency shall have any personal liability, directly or indirectly, under or in connection with this Termination Agreement or any agreement made or entered into under or pursuant to the provisions of this Termination Agreement, or any amendment or amendments to any of the foregoing made at any time or times, heretofore or hereafter. The terms of this Section survive the Closing or termination of this Termination Agreement.
5.7 Counterparts. This Agreement may be executed in counterparts, each of which shall constitute an original and all of which together shall constitute one and the same agreement.
IN WITNESS WHEREOF, the parties have executed this Termination Agreement as of the date last written below.
_________________________________
Jorge E. Garcia, City Manager
Dated:________________________
Attest:
_________________________________
Erica Kirkwood, City Clerk
_________________________________
Jorge E. Garcia, Executive Director
Dated:________________________
Attest:
_________________________________
Erica Kirkwood, Secretary
Council Agenda 10-6-2026 9.G-14
Attachment 4
Packet Page 125
PISMO BEACH CITY COUNCIL STAF REPOR
Agenda Item #12.A
Meetin Date: October 6, 2026
TITLE:
Capital Improvement Program Semi-Annual Report
RECOMMENDATION:
No action recommended; for information only.
DISCUSSION:
The Ten-Year Capital Improvement Plan (CIP) is one of the most important planning documents for the City of Pismo Beach. This plan not only identifies immediate needs but also seeks to capture the long-term capital requirements of the City. Capital projects are typically projects that lead to the acquisition and/or construction of new assets or the improvement or extension of the useful life of existing capital assets. Capital assets include but are not limited to land, facilities, buildings, parks, playground equipment, streets and sidewalks, bridges, water, wastewater and storm drain infrastructure, technology systems and equipment, traffic control devices, and many other items that deliver public benefit for a prolonged period of time. This report will provide an update on CIP projects currently in progress.
Completed Projects
Cliff Avenue/Ocean Boulevard Utility Undergrounding
The project included undergrounding of the overhead utility lines along the bluff on Cliff Avenue and Ocean Boulevard in the vicinity of the Cliff Avenue/Ocean Boulevard Storm Drain Repair project. A Notice of Completion was approved by the City Council on September 15, 2026.
Dinosaur Caves Playground Expansion
The project expanded the footprint of the play area and installed the friendship swing in a new location. Construction was completed and the final playground inspection was completed in August 2026.
Public Safety Facility
At both the police and the fire station, the final electrical and long lead items, cabinets, and lockers are being installed. Remaining contract items and commissioning of building mechanical and HVAC systems is ongoing. Overall, the buildings warranty work is progressing, and building move in, emergency dispatch call center, and decommissioning of the old temporary facilities is progressing as scheduled with final contract notice of completion expected in December 2026.
Storm Drain Sink Hole Repairs
James Way and Capanna Street: Repair and restoration of a damaged 36-inch corrugated metal storm drain crossing James Way.
Council Agenda 10-6-2026 12.A-1
Packet Page 126
Encanto Avenue and Shell Beach Road. Repair and restoration of a damaged 24- inch corrugated metal storm drain crossing Shell Beach Road.
Studies and Planning Documents
The City’s efforts to plan and prioritize construction projects also include the preparation of studies and planning documents that provide recommendations for future infrastructure improvements. Currently there are six of these plans that are ongoing and in the process of completion: the Sewer Master Plan, Urban Water Management Plan, Water Master Plan, Facilities Condition Assessment, Vision Zero Action Plan and ADA Transition Plan.
The Sewer System Management Plan has been completed in compliance with the City’s regulatory permit.
Sewer Master Plan (SMP)
The SMP provides a prioritized list of capital improvements related to the sanitary sewer system. This document was last updated in 2000. The consultant is currently working on the population projections and flow evaluations and compiling the data from recently completed collection system evaluations. Using the data projections and the evaluations the Consultant will identify capital improvement projects necessary to meet current and future wastewater system requirements.
Sewer System Management Plan (SSMP)
The SSMP provides a plan and schedule to properly manage, operate, and maintain all parts of the sanitary sewer system for regulatory compliance. The 2026 SSMP update evaluates the effects of growth, densification, and conservation on the City’s sewer collection system and identifies long-term strategies to renew existing assets, long term planning and capital improvement recommendations. The 2026 SSMP was adopted by City Council on April 21, 2026.
Urban Water Management Plan (UWMP) and Water Master Plan (WMP) The UWMP provides long-term water resources planning and demonstrates water supply reliability under normal as well as drought conditions. The current UWMP was developed in 2020 and is required to be updated following the California Department of Water Resources guidance to remain in compliance with California Water Code requirements.
The WMP evaluates the water system to identify capital improvement projects necessary to meet current and future water system requirements. The plan was last updated in 2020.
The consultant is currently in the process of collecting data for both plans to develop a list of importance for future water-related capital improvement projects.
Facilities Condition Assessment
This project included preparation of a comprehensive facilities condition assessment of all City-owned facilities and a long-term facilities maintenance plan. The consultant has delivered final reports for each facility and provided the City with access to software to easily view the City’s assets, their condition, and expected maintenance costs for the next 20 years. The consultant-provided data has been uploaded to our Asset Management Council Agenda 10-6-2026 12.A-2
Packet Page 127
Program. Staff will bring the final report to the Council at a future meeting as part of the next budget development process.
ADA Transition Plan Update
Under Title II of the ADA, the City is required to have a current Self-Evaluation and Transition Plan. The City contracted with Disability Access Consultants (DAC) through the California Joint Powers Insurance Authority (CJPIA) ADA Assistance Program to complete a comprehensive update of the 2014 Self-Evaluation and Transition Plan. DAC has completed its inspections of public rights-of-way, parks, and facilities and the data has be entered into the DACTrak software. Staff is currently entering estimated planned completion dates into the software for all records and anticipate all projected dates will be entered in the next six months. DAC is also working on the programmatic evaluation of policies, procedures, and practices. The initial draft was provided to staff for review in late September.
Vision Zero Action Plan
Staff secured a grant through the Federal Highway Administration (FHWA)’s Safe Streets and Roads for All program to complete a Vision Zero Action Plan. The plan will identify and prioritize projects that will eliminate or reduce roadway fatalities and serious injuries.
Staff anticipates releasing an RFP in November 2026, with consultant selection in January 2027.
Citywide Engineering & Traffic Study (Speed Survey)
The City routinely prepares Speed Surveys to justify posted speed limits and enable the Police Department to enforce these limits using electronic devices. California Vehicle Code (CVC) Section 40802 requires Speed Surveys to be updated every 7 to 14 years.
This project will update the City’s Speed Surveys, which was last approved in 2020.
Contract documents with a traffic engineering consultant are currently being prepared.
Title VI Plan Update
Title VI of the Civil Rights Act of 1964 provides that no person in the United States shall, on the grounds of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be subjected to discrimination under any program or activity receiving federal financial assistance. A consultant has been retained to perform an evaluation of and update to the City’s plan to ensure compliance with all federal requirements. It is anticipated the update will be completed by February 2027.
Under Construction
Ventana Sports Courts
Located on Ventana Drive (Ventana Sports Courts) the project consists of construction of one new tennis and two new pickleball courts, a parking lot and a crosswalk connecting Chumash Park to the Ventana Courts. The project is progressing with recent activity including paving of the courts on September 23, 2026.
Council Agenda 10-6-2026 12.A-3
Packet Page 128
2026 Routine Street Maintenance
Regular routine maintenance of City streets benefits all residents and visitors who utilize the City's roadways and prolongs the useful life of the roadways. This project includes crack filling, performing dig-outs, filling potholes, ADA improvements, slurry sealing and striping. A construction contract was awarded and the Notice to Proceed was issued for work to begin on August 24, 2026. The contractor has completed digouts, crack sealing and ADA improvements at various locations. At the time of the writing of this report, slurry sealing is scheduled to begin the week of September 28, 2026. Project completion is anticipated for late October 2026.
Cliff Avenue/Ocean Boulevard Storm Drain
The project will repair the damaged storm drain outfall at the intersection of Cliff Avenue and Ocean Boulevard. The project is funded through the Federal Emergency Relief program. A construction contract was awarded and the Notice to Proceed was issued for work to begin on September 21, 2026.
Pier Avenue Storm Drain Repair
The project will replace the storm drain outfall pipe that was washed away during a storm event in January 2023. The project is funded through the Federal Emergency Management Agency (FEMA). A construction contract has been awarded and at the time of the writing of this report, work is anticipated to begin on October 5, 2026.
Eldwayen Park Sidewalk Re-route
The project will remove the existing sidewalk within the park and install a new decomposed granite path away from the edge of the bluff. A construction contract has been awarded and at the time of the writing of this report a preconstruction meeting is being scheduled. Construction is anticipated to begin in October.
Price Street/Ocean View Avenue Improvements
This project will provide increased pedestrian and cyclist safety at the intersection of Price Street and Ocean View Avenue. A construction contract has been awarded and at the time of the writing of this report a preconstruction meeting is being scheduled.
Construction is anticipated to begin in October.
Dolliver Street and Main Street Parking Lot Lighting
A three-month solar-powered parking lot streetlight demonstration pilot program has been completed, testing two different lighting systems. Both systems performed well and a purchase order has been issued for the preferred light that was installed during the pilot, as well as for additional lights to be installed in the Dolliver Street and Main Street parking lots. The lights are expected to be delivered in mid-October and a contractor will complete the installation following delivery. Installing solar-powered streetlights eliminates the high upfront costs of trenching and utility grid connection while providing immediate illumination.
Council Agenda 10-6-2026 12.A-4
Packet Page 129
Huston Street – Well 31 Test Well
This project will construct a test well at the site of the future Well 31, currently in design.
A construction contract for the test well has been awarded and the Notice to Proceed was issued for work to begin on August 31, 2026. The drilling and pumping tests for Well 31 are anticipated to be completed by the end of November 2026.
Design
Sunset Palisades Lift Station Rehab and Force Main Relocation The Sunset Palisades Lift Station Rehabilitation and Force Main Relocation Project will rehabilitate the aging discharge piping at the lift station to maintain safe and efficient operations. The project will also relocate the existing force main which currently runs behind the residential properties along Searidge Court, into the City’s right-of-way. The project has been advertised for construction bids and a Request for Proposals for Construction Management, Inspection and Administration Services has also been advertised. Bids and proposals are due on October 15, 2026. The current estimated cost of construction is $1,540,000.
Addie Street Restroom Replacement
This project will replace the current restroom at the beach end of Addie Street, adjacent to the Addie Street parking lot, with a larger restroom. An alternative location at the end of Park Avenue is being investigated. Preliminary cost estimates for purchase of the restroom building at this location are in the $750,000 range and additional costs for surrounding site improvements are still being developed.
320/330 Main Street Parking Lot Design
The property at 320 and 330 Main Street, which was used as the location for the temporary Police Department during construction of the Public Safety Facility, is now vacant. The property will be converted into a parking lot connected to the existing parking lot at 321 Pomeroy Ave. A design contract has been executed and the consultant is working on 30% design plans. The current construction cost estimate is $950,000.
Huston Street - Well 31 - Production Well
This project will replace the existing Well 23 with a new water production well (Well 31) in a new location. Well 31 will be located on a parcel at the corner of Huston Street and Farroll Road in Grover Beach. The well is currently in design, along with the design of a pipeline extension within Farroll Road. Test well results are required prior to finalizing the design. The test well project is underway.
Bello Reservoir Roof & Liner
This project will replace the existing Bello Reservoir roof and liner, both of which are past their useful life and in need of replacement. The project has been advertised for construction bids and a Request for Proposals for Construction Management, Inspection and Administration Services has also been advertised. Bids and proposals are due on October 29, 2026. The estimated cost for replacement of both the roof and liner is $740,000.
Council Agenda 10-6-2026 12.A-5
Packet Page 130
Charles Street Reservoir Replacement Project
This project will replace the Charles Street Reservoir, located in Grover Beach, which is nearing the end of its useful life. The project is partially funded with a $500,000 grant from the U.S. Department of Housing and Urban Development (HUD). The current plans are at 95% design. Construction is anticipated to begin the second quarter of 2027 following completion of the Bello Reservoir and Roof Liner Project. The current construction cost estimate is $3.5 million.
2027 Drainage Improvements
This project includes drainage improvements intended to improve groundwater conditions along Placentia Ave and Boeker Ave in Shell Beach based on recommendations in the City’s Drainage Master Plan Update. Drainage improvements will include surface concrete and flowline improvements, drain inlets, longitudinal perforated or slotted underdrains, and new solid wall trunkline storm drains. Following the drainage improvements, the roadway will be repaired with a mill & overlay. A design contract is being presented for Council approval under a separate report at tonight’s meeting.
2027 Roadway Maintenance Project
This project consists of roadway maintenance improvements based on recommendations from the City’s Pavement Management Plan including crack fill, localized dig outs, slurry seal, overlay and mill & overlays. The improvements also include concrete and flowline improvements with ADA improvements incorporated where required based on field conditions. A design contract is being presented for Council approval under a separate report at tonight’s meeting.
Shell Beach Road Shared Use Path – Phase 2 and Phase 3
The “Phase 2” project will connect Avila Beach Drive to Spyglass Drive with a multimodal path. The “Phase 3” project will connect Spyglass Drive to Terrace Drive with a multimodal path. Phase 2 design is funded through a combination of Trade Corridor Enhancement Program (TCEP) and Surface Transportation Block Grant Program funds. The Phase 2 design had progressed to the 95% level, but due to a construction funding shortfall, the consultant has paused construction level design work on Phase 2. Working with SLOCOG and the City, the consultant is now completing preliminary survey and right of way work for future design of Phase 3 in order to prepare a combined Phase 2 and Phase 3 project to submit for a future Active Transportation Program (ATP) grant application. Staff anticipates additional funding will be available through SLOCOG this fall and will return to Council to seek approval for a contract amendment to complete design of Phase 3 and appropriate additional grant funds at that time.
Cliff Avenue Parking
The project will pave and stripe parking stalls at 90° angles in the currently unpaved right- of-way along the south side of Cliff Avenue. Design is in progress and currently at the 90% level. Construction is anticipated to begin the Fall 2028 following completion of the adjacent Cliff Avenue/Ocean Boulevard Storm Drain. The current construction estimate is $1,255,900. Once the final plans and estimate have been completed, staff will return to Council to discuss funding options.
Council Agenda 10-6-2026 12.A-6
Packet Page 131
James Way Irrigation Controllers
This project will install electrical service to the irrigation controllers installed with the James Way Beautification project. The consultant has prepared 60% design plans. The current construction estimate is $152,916.00, not inclusive of PG&E engineering/design/construction or any other soft costs.
Toucan Terrace Sewer Pipe Replacement
This project includes replacement of 510 linear feet of sewer pipe at the Toucan Terrace sewer trestle. The existing sewer trestle pipeline has exceeded its service life and needs to be replaced. The trestle bridge support system also requires seismic upgrades. Draft plans and bid specifications are currently being developed for the Toucan Terrace Pipe Replacement project. The current estimated cost of construction is $307,000 and it is anticipated the project will be advertised for bids in the first quarter of 2027.
Bello/Wadsworth Paving and ADA Improvements
This project includes sections of grind and overlay on Bello Street, Wadsworth Avenue, Pismo Avenue and Hollister Avenue, as well as curb ramp and cross gutter improvements in the vicinity of the Public Safety Facility. The design consultant has prepared 90% plans and it is estimated construction will take place in Summer 2027. The current construction cost estimate is $450,000.
Butterfly Grove Enhanced Parking and Crosswalk
This purpose of the project is to improve parking and pedestrian crossing on Highway 1 at the Butterfly Grove. Staff and the consultant have been evaluating options and working on alternatives with State Parks and the Butterfly Grove Management. Construction would take place once the Highway 1 relinquishment has been finalized.
Vista Del Mar Stairs Foundation Repair
This project will repair the foundation of the existing Vista Del Mar beach access stairs. A consultant has prepared draft plans, and staff is proceeding with the Planning permit process. The current estimated cost of construction is $550,000 and it is anticipated the project will be advertised for bids in the first quarter of 2027.
Other Budgeted Projects on Deck in Fiscal Year 2027
Downtown Sidewalk Replacement
Battery Backup for City Owned Traffic Signals
Price Street Market Lighting Study
Ball Field Lighting Evaluation
Pismo Oaks booster station, Pacific Estates booster station, and Well 5 Variable Frequency Drives (VFD)
Addie Street Force Main
Boosinger Park Softfall Replacement
Highway 1 Traffic Signal Upgrades
Highway 1 Sidewalk Extension
Stratford and Wadsworth Sewer Lining
Oxidation Reduction
Council Agenda 10-6-2026 12.A-7
Packet Page 132
Pier Promenade Transformation
Pismo Oaks Lift Station Rehabilitation
James Way Beautification Feasibility Report for Canyon Side Project Management and Tracking
The City’s robust CIP program requires staff to manage and track a large number of projects concurrently. To help ensure that projects stay on schedule and within budget, the Engineering Division utilizes Virtual Project Manager (VPM), a project management software program that allows staff to track and manage projects from initiation through construction. VPM provides a centralized system for managing key project components, including budget, pay applications, schedules, daily logs, submittals, requests for information (RFIs), change orders and punch list items. VPM also provides a chart view of the City’s CIP projects, allowing staff to view project schedules and key milestones across projects and identify potential scheduling conflicts or delays. The current chart view is provided as Attachment 1.
Conclusion and Recommendation
No action is recommended; for information only.
FISCAL IMPACT:
There is no direct fiscal impact associated with this report.
ATTACHMENTS:
1. VPM Project Chart
Prepared by:
Erin Olsen, Senior Management Analyst
Submitted by: Rosemarie Gaglione, PE, Director of Public Works City Manager Approval:
Council Agenda 10-6-2026 12.A-8
Packet Page 133
Attachment 1
Council Agenda 10-6-2026 12.A-9
Packet Page 134
Attachment 1
Council Agenda 10-6-2026 12.A-10
Packet Page 135
Attachment 1
Council Agenda 10-6-2026 12.A-11
Packet Page 136
Attachment 1
Council Agenda 10-6-2026 12.A-12
Packet Page 137
Attachment 1
Council Agenda 10-6-2026 12.A-13
Packet Page 138
PISMO BEACH CITY COUNCIL STAF REPOR
Agenda Item #12.B
Meetin Date: October 6, 2026
TITLE:
Award of Design-Build Contract and Amendment #1 to the Owner’s Advisor Contract for the Central Coast Blue Project
RECOMMENDATION:
1. Adopt a Resolution authorizing the City Manager to enter into an Agreement with PERC Water Corporation in an amount not to exceed $39,790,682 for the construction of the Central Coast Blue Advanced Water Purification Facility and appropriating related budget adjustments in Fiscal Year 2027;
2. Adopt a Resolution authorizing the City Manager to execute Amendment #1 to the existing Professional Services Agreement with GHD, Inc. for Owner’s Advisor services for the Central Coast Blue Project in an amount not to exceed $2,233,433.
DISCUSSION:
At the October 15, 2025, Joint Meeting of the Pismo Beach City Council, Pismo Beach Financing Agency Board of Directors, and Central Coast Blue Regional Recycled Water Authority Board of Directors, staff received direction to proceed with fixed-price Design- Build as the procurement delivery model for the design and construction of the Central Coast Blue Project (Project) and to procure an Owner’s Advisor.
Design-Build Team Procurement
On April 3, 2026, the City issued a Request for Statements of Qualifications for Design- Build Services for the Central Coast Blue Project. On May 8, 2026, the following three firms submitted Statement of Qualifications (SOQs):
Filanc
GSE Construction Company, Inc.
PERC Water Corporation
After a thorough vetting process, all three firms were deemed qualified to participate further.
On June 15, 2026, the City issued a Request for Proposals (RFP) for Design-Build Services for the Central Coast Blue Advanced Water Purification Facility (AWPF). The RFP was by invitation to the three firms who had submitted qualifying SOQs.
On August 13, 2026, the City received proposals from the three qualified firms. All three firms submitted quality proposals, but after an evaluation process that included a two- hour interview with each firm, PERC Water Corporation (PERC) was determined to have submitted the best overall proposal.
Council Agenda 10-6-2026 12.B-1
Packet Page 139
While there was a slight price difference between the two lowest-cost Design-Build teams (~3.7%), both proposals were within the City's budget. Consistent with the fixed-price Design-Build delivery model and the complexity of the Project, the evaluation process appropriately prioritized qualifications, technical merit, risk reduction, and delivery confidence, while fully accounting for price through the established scoring methodology.
The intent has been to build a 500 acre-foot-per-year (AFY) AWPF that is expandable to 750 AFY at a future date. Given that the Design-Build team will already be at the site, staff asked them to provide an estimate for accelerating the plan and installing the necessary equipment at the plant as well as a stub out for future needs, should they be required.
There were two options considered. Option A would have PERC proceed with the current 500 AFY plant and the City could revisit the expansion at a later date. Staff asked PERC for an estimate to remobilize two years after the plant is constructed; that estimate is roughly $6 million.
Option B would have PERC execute the expansion to 750 AFY during this project; the proposed cost is $3,500,804. The ability to perform the expansion now, at a much lower cost than in the future will allow the City to keep the cost of water lower than performing it under a new contract two or more years after this project is completed. Staff is recommending that the City proceed with Option B, which has been included in the contract cost. PERC’s Fixed-Price Design-Build price is $39,790,682 for Option B.
Owner’s Advisor Services
On November 20, 2025, the City issued a formal Request for Qualifications/Proposals to acquire the services of a qualified firm to serve as the Owner’s Advisor for the Project.
On February 3, 2026, the Pismo Beach City Council approved the award of a contract for Owner’s Advisor Services to GHD, Inc. (GHD) in an amount not to exceed $461,438.
As the project Owner Advisor, GHD led the development of the Design Criteria Report (DCR) and compiled all supporting documentation, Design-Build RFQ/P and rating criteria, while ensuring alignment with project goals and risk management best practices.
GHD maintained a detailed risk register for the project, led efficient and effective team meetings and evaluated and responded to numerous Requests for Information throughout the procurement process. GHD has effectively performed as the Owner’s Advisor throughout this process.
While the process of selecting an Owner’s Advisor included the entire project, the current contract was awarded for the procurement process only. Staff recommends the amendment of the GHD contract for the next phase.
On September 22, 2026, GHD submitted a proposal for continued Owner’s Advisor Services through completion of the Project. The proposed Amendment #1 (Attachment 4) in the amount of $2,233,443 will cover the actual Design-Build process through to Council Agenda 10-6-2026 12.B-2
Packet Page 140
completion. This amendment also includes the expansion to 750 AFY and the transfer of the Well 31 project to PERC.
Future Contracts
Well 31
The award of the Design-Build contract and amendment to the Owner’s Advisor contract are necessary to begin the work immediately. Staff will be returning with an additional contract with PERC for the completion of the new extraction well, Well 31.
The City commenced with the design of Well 31 earlier this year because the condition of Well 23 is tenuous, and staff could not be sure of the outcome of the Project procurement process. Had this not been the case, the design and construction of Well 31 would have been included in the Project. Now that a reasonable price has been secured for the Project, staff has re-evaluated the risk of continuing the design-bid-build path vs. combining Well 31 with the Project.
The risk of the current approach is that once the Well 31 project goes out to bid, the risk of either not receiving any bids or receiving bids that are too high to proceed are concerns.
Additionally, once the project goes into construction, delays or other complications could further delay commissioning of the well. The larger risk is that the Project could potentially be operational before the new Well 31 is prepared to begin extracting water from the aquifer. This is not a risk that is worth taking.
The City has a separate budget for the design and construction of Well 31, and incorporating this work into the current Project is not anticipated to result in additional cost. Knowing that this would be a possibility, an Addendum was issued during the RFP solicitation process to ensure all proposers were aware of the potential additional scope.
PERC will provide a cost proposal once data from the test well currently in progress has been obtained.
Construction Management
When the Project moves into the construction phase in the spring of 2027, a Construction Management (CM) team will become necessary. A Design-Build contract is somewhat different than a design-bid-build contract in that there will not be constructability reviews.
It will be the responsibility of the Design-Build team to design a Project that can be constructed within their budget and meet all of the performance criteria in the contract.
CM will still be important; we will have off-site work in roadways, and tunneling beneath 4th Street, Highway 1 and the Railroad to connect to the outfall. On-site there will need to be record of materials and soils testing, ensuring that all materials meet specifications and Buy America Build America requirements, as well as ensuring labor compliance and other federal regulations. The CM will also enforce safety compliance and traffic control/impacts. It is estimated that the cost of CM will be approximately 5% of the Design- Build contract or $1,989,534.
Council Agenda 10-6-2026 12.B-3
Packet Page 141
Building Permit Plan Check
While the building site is located in Grover Beach, as a municipal corporation that owns property in another jurisdiction, the City may perform its own building permit inspections and issue a building permit. The City of Grover Beach is agreeable to the City taking this approach. The contract to perform building permit plan check is anticipated to be under $30,000.
Plan Check and Inspections to be Performed by Others
The City of Grover Beach will perform plan check and inspection of public improvements such as sidewalk, road work in its rights-of-way, as well as connections to their sewers and waterlines. Grover Beach will also approve traffic control and stormwater plans. The County of San Luis Obispo, Caltrans, and Union Pacific Railroad would review any plans related to work in their respective rights-of-way. Any work in the Railroad right-of-way will require a full-time flagger with per diem and travel expenses. Additionally, Five Cities Fire Authority will review for conformance with fire codes. The cost estimate for all agencies is $100,000.
Future Personnel Costs
Central Coast Blue will be an addition to the City’s operations and will require additional staff to operate legally and safely. Based on careful analysis and the experience of other agencies consulted, it is anticipated that three new Operators will be required once the AWPF is fully operational. When the plant is fully online, the half-time administrative position at the Wastewater Treatment Plant may need to be converted to a full-time position. The following additional staff with Advanced Water Treatment Operator (AWTO) certifications will be required:
One Chief Plant Operator with an AWTO 5 certificate
Two Operators with AWTO 3 certificates
Rather than seeking to hire AWTO certified Operators from the outside, the City intends to first provide existing Operators with the opportunity to certify. The City’s Utilities Manager will obtain their AWTO 3 and will then have three years to obtain their AWTO 5, according to recent conversations with the state. Current Operators who possess a Grade 3 Wastewater or Grade 3 Water Treatment certificate qualify to take the AWTO 3. Even so, if three of the City’s existing staff move into the new AWTO positions, those positions would need to be backfilled for Water and Wastewater.
These will be new positions with differing job duties, and requiring additional certification and will require staff to complete a separate classification and compensation study to incorporate them into the City’s Salary Schedule. Staff will return to the Council at a future date after Human Resources has conducted a classification study and the appropriate conversations with the labor union are completed.
Council Agenda 10-6-2026 12.B-4
Packet Page 142
Conclusion and Recommendation
Staff recommends that the Council adopt a resolution (Attachment 1) authorizing the City Manager to enter into an Agreement with PERC for Design-Build services in an amount not to exceed $39,790,682 and appropriating related budget adjustments in Fiscal Year 2027. Staff also recommends that the Council adopt a resolution (Attachment 2) authorizing the City Manager to execute Amendment #1 to the existing Professional Services Agreement with GHD for Owner’s Advisor services in an amount not to exceed $2,233,443.
FISCAL IMPACT:
The fiscal impact of adopting the subject resolutions is additional expenditures of $42,024,125 for Central Coast Blue, including $13,867,961 in the Water Enterprise Funds and $28,156,164 in the Wastewater Enterprise Funds in Fiscal Year (FY) 2027. The City’s FY 2027 Central Coast Blue budgeted expenditures are $489,179 across both the Water and Wastewater Enterprise Funds.
The City anticipates another estimated $8,543,169 to support construction management, plan check, legal, permitting, funding and financing support, outreach, procurement, and other costs. The total of the proposed agreements plus these estimated additional costs is $50,567,294. The net expenditure budget shortfall comparing the current budget with the proposed project costs is $49,661,677. The ongoing costs for the project include debt service costs, annual operating and maintenance costs, and replacement costs, which are not included in this report. Table 1 illustrates the FY 2027 expenditure budget, proposed project costs, and resulting budget shortfall.
Table 1: Fiscal Impact of Proposed Agreements and Central Coast Blue Projected Costs
A FY 2027 Available Bud et Amount
Water Enterprise Fund $343,218
Wastewater Enterprise Fund $562,399
Total FY 2027 Available Bud et $905,617
B Proposed Pro ect Costs
PERC Water Corporation Desi n-Build $39,790,682
GHD - Owner's Advisor Phase 2 Amendment 1 $2,233,443
Subtotal A reements 42,02 ,125
Estimated Costs: Construction Management,
Plan Check, Permitting, etc. $8,543,169
Total Pro ect Cost $50,567,294
C = A - B Bud et Surplus / Shortfall $49,661,677
Proposed Budget Adjustments
In order to update the City’s budget to reflect some of these costs, staff recommends appropriating the current shortfall of $49,661,677 of expenditures, including $16,388,353 Council Agenda 10-6-2026 12.B-5
Packet Page 143
in the Water Construction Fund and $33,273,324 in the Wastewater Capital Projects Fund, including appropriating related transfers between funds, in FY 2027.
ATTACHMENTS:
1. Resolution - PERC
2. Resolution - GHD
3. PERC Water Corporation Agreement (Online Only Attachment12)
4. GHD Amendment #1 to Vendor Agreement
Submitted by: Rosemarie Gaglione, PE, Director of Public Works City Manager Approval:
Council Agenda 10-6-2026 12.B-6
Packet Page 144
1 Full URL (Part 1): https://portal.laserfiche.com/Portal/DocView.aspx?id=805739&repo=r-f36a9aa0 2 Full URL (Part 2): https://portal.laserfiche.com/Portal/DocView.aspx?id=805741&repo=r-f36a9aa0
RESOLUTION NO. R-2026-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH,
CALIFORNIA AUTHORIZING THE CITY MANAGER TO ENTER INTO AN
AGREEMENT WITH PERC WATER CORPORATION IN AN AMOUNT NOT TO EXCEED $39,790,682 FOR THE CONSTRUCTION OF THE CENTRAL COAST BLUE
ADVANCED WATER PURIFICATION FACILITY AND APPROPRIATING RELATED BUDGET ADJUSTMENTS IN FISCAL YEAR 2027
WHEREAS, the City desires to design and construct Central Coast Blue, an Advanced Water Purification Facility to create a new, high quality, and reliable water supply for the City of Pismo Beach, even in times of water shortage or drought; and WHEREAS, the City undertook a two-step process, consisting of a Request for Statements of Qualifications and Request for Proposals process, to find the most qualified construction and design team; and
WHEREAS, three proposals were submitted to the City by qualified design-build teams; and
WHEREAS, PERC Water Corporation (PERC) was determined to have submitted the best overall proposal providing the best overall value to the City; and WHEREAS, the cost of the project will be supported by grants and low-interest financing.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby authorizes the City Manager to enter into an Agreement, in substantially the form attached to staff’s report dated October 6, 2026, with PERC Water Corporation in an amount not to exceed $39,790,682 for the construction of the Central Coast Blue Advanced Water Purification Facility.
BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby appropriates the following expenditures in Fiscal Year 2027, including appropriating related transfers between funds:
Fund Account Amount ($)
UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 6th day of October 2026, by the following vote:
AYES:
NOES:
Council Agenda 10-6-2026 12.B-7
Attachment 1
Packet Page 145
ABSENT:
ABSTAIN:
RECUSED:
Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Kirkwood, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and official seal of the City of Pismo Beach on _______________________.
________________________
Erica Kirkwood, City Clerk
Council Agenda 10-6-2026 12.B-8
Attachment 1
Packet Page 146
RESOLUTION NO. R-2026-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH, CALIFORNIA AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT #1 TO THE EXISTING PROFESSIONAL SERVICES AGREEMENT WITH GHD, INC.
FOR OWNER’S ADVISOR SERVICES FOR THE CENTRAL COAST BLUE PROJECT IN AN AMOUNT NOT TO EXCEED $2,233,433
WHEREAS, the City desires to design and construct Central Coast Blue, an Advanced Water Purification Facility to create a new, high quality, and reliable water supply for the City of Pismo Beach, even in times of water shortage or drought; and WHEREAS, on February 3, 2026, the City Council approved a Professional Services Agreement with GHD, Inc. for Owner’s Advisor services; and WHEREAS, as the project Owner’s Advisor, GHD led the development of the Design Criteria Report and compiled all supporting documentation, design-build RFQ/P and rating criteria, while ensuring alignment with project goals and risk management best practices; and
WHEREAS, the RFP process of selecting an Owner’s Advisor included the entire project, but the current contract was awarded for the procurement process only; and WHEREAS, GHD has submitted a proposal for continued Owner’s Advisor Services through completion of the Project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby authorizes the City Manager to execute Amendment #1 to the existing Professional Services Agreement, in substantially the form attached to staff’s report dated October 6, 2026, with GHD, Inc. in an amount not to exceed $2,233,433 for Owner’s Advisor Services.
UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 6th day of October 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
RECUSED:
Council Agenda 10-6-2026 12.B-9
Attachment 2
Packet Page 147
Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Kirkwood, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and official seal of the City of Pismo Beach on _______________________.
________________________
Erica Kirkwood, City Clerk
Council Agenda 10-6-2026 12.B-10
Attachment 2
Packet Page 148
AMENDMENT # 1
to the
FEBRUARY 6, 2026 AGREEMENT BETWEEN THE CITY OF PISMO BEACH AND GHD, INC.
Pursuant to the February 6, 2026 Agreement between the City of Pismo Beach, hereinafter referred to as “City,” and GHD, Inc., hereinafter referred to as “Vendor,” City and Vendor hereby agree as follows:
1.Additional services shall be performed as set forth in the proposal dated September 22, 2026, which is attached hereto and by this reference made a part hereof.
2.Compensation for and timing of the additional services shall be as set forth in the referenced proposal. Compensation for the additional services shall not exceed the amount of two million two hundred thirty-three thousand four hundred forty-three dollars ($2,233,443), without prior written approval of the City.
3.The revised fee under the February 6, 2026 contract, plus this addendum, is two million six hundred ninety-four thousand eight hundred eight-one dollars ($2,694,881).
4.All other provisions of the subject agreement between City and Vendor shall remain in full force and effect.
CITY:
City of Pismo Beach, a Municipal Corporation
Signed:
Name: Rosemarie R. Gaglione, PE
Title: Director of Public Works
Dated: ________________________________
Signed:
Name: Jorge E. Garcia
Title: City Manager
Dated: ________________________________
ATTEST:
Signed:
Name: Erica Kirkwood
Title: City Clerk
APPROVED AS TO FORM:
Signed:
Name: Dean J. Pucci
Title: City Attorney
VENDOR:
GHD, Inc.
Signed:
Name: ________________________________
Title: _________________________________
Dated: ________________________________
Address for giving notice:
(if changed from prior agreement)
______________________________________
______________________________________
Email address for official communications:
(if changed from prior agreement)
______________________________________
Vendor Representative:
(if changed from prior agreement)
Name/Title: ____________________________
Attachment: Scope/Cost Proposal
Council Agenda 10-6-2026 12.B-11
Attachment 4
Packet Page 149
320 Goddard #200
Irvine, CA 92618
Your ref:
Our ref: 12686474
22September 2026
Rosemarie Gaglione, PE
Director of Public Works
City of Pismo Beach
Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project
Ms. Gaglione,
The City of Pismo Beach (City) has requested that GHD provide this proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor Services for the Central Coast Blue Advanced Water Purification Facility (AWPF) Design Build Project. GHD has completed the Phase 1 (Procurement) Scope of Work, which focused on refining key technical elements and developing a procurement package for the fixed price Design Build project delivery.
Phase 2 (Design/Construction/Commissioning) will focus on supporting successful project delivery through design, permitting, construction, startup, and commissioning. As the City's Owner's Advisor, GHD will provide project management, technical review, regulatory support, funding assistance, hydrogeologic expertise, and operational readiness services throughout implementation.
This proposal includes services to support City’s project director for GHD and subconsultant Montgomery and Associates.
The proposed amount for Phase 2 (Design/Construction/Commissioning) services is $2,233,443.
Detailed herein is recommended additional services, estimated fee impacts, and associated tasks for the Phase 2 (Design/Construction/Commissioning) scope.
Regards,
Kevin Daniels
Kevin Daniels, PhD, PEProject
Mark Donovan, PE
Project Director
949-585-5251
Council Agenda 10-6-2026 12.B-12
Attachment 4
Packet Page 150
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 1
Proposed Scope of Work
GHD will serve as the City's Owner's Advisor, reporting directly to the City’s project director throughout the delivery of the Advanced Water Purification Facility project. GHD will be providing technical, regulatory, commercial, funding, and project management support from contract execution through startup and initial operations. The purpose of these services is to help the City’s project director protect the City’s contractual interests, maintain regulatory and funding compliance, manage project risks, and support successful delivery of a reliable, operable, and permit-compliant facility. The Design-Build project is anticipated to span approximately 24 months, and GHD has added an additional 6 months of project and operational support, during which GHD will provide the services described below.
1. Task 1 Project Management
GHD will serve as the owner's representative throughout project delivery, coordination, and oversight to support successful execution of the Design-Build contract. This task focuses on maintaining alignment among the City, Design-Builder, Construction Manager, regulators, funding agencies, and other project stakeholders.
Project management services will include the following activities:
•Owner’s representative services — Serve as the City’s project directors’ primary technical advisor and coordinate City decisions, technical reviews, regulatory activities, funding requirements, and interfaces with the Design-Builder and Construction Manager. •General project management — Provide ongoing project management, internal coordination, progress monitoring, issue resolution, and management reporting. The current allowance of two days per week should be treated as a baseline rather than a cap during intensive design, permitting, testing, and acceptance periods.
•Project kick-off and alignment — Facilitate an Owner/Design-Builder/Construction Manager kickoff to confirm responsibilities, deliverables, communication pathways, decision authority, review procedures, and critical project outcomes.
•Project management plan — Develop and maintain the Owner’s project management plan covering governance, decision authority, communication, document control, schedule, budget, risk, permitting, funding, stakeholder coordination, and escalation procedures. •Weekly progress meetings — Attend weekly progress meetings; review agenda and supporting information beforehand; document Owner decisions, risks, action items, and unresolved technical or commercial issues.
•Assist with Board and council support — Prepare staff-report technical content, executive summaries, presentations, decision memoranda, and talking points for City Council, governing boards, and partner agencies.
2. Contract Requirements Management
GHD will help ensure that all contractual obligations, proposal commitments, and procurement requirements are fully understood, tracked, and implemented throughout the project. This task is intended to protect the City's contractual position, maintain fixed-price accountability, and support informed decision-making regarding changes and contract interpretations. Contract administration and compliance oversight services will include the following activities:
•Contract requirements matrix — Translate the Design-Build Agreement, General Conditions, RFP, Design Criteria Report, proposal commitments, addenda, funding conditions, permits, and environmental commitments into a traceable compliance matrix.
Council Agenda 10-6-2026 12.B-13
Attachment 4
Packet Page 151
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 2
•Proposal commitment register — Identify every Design-Builder commitment, qualification, assumption, exclusion, allowance, proposed refinement, and “future evaluation” item in the proposal and track disposition through final design and construction. •Basis-of-price verification — Establish the accepted technical and commercial basis of the fixed price, including capacities, treatment criteria, equipment configuration, redundancy, expansion provisions, well scope, pipelines, buildings, testing, and training. •Fixed-price protection — Evaluate whether proposed clarifications, design development, equipment selections, or revised approaches are already included in the fixed-price obligations before treating them as changes.
•Contract interpretation support — Provide technical interpretation of contract requirements and coordinate with City legal counsel on formal contractual positions, notices, disputes, or entitlement questions.
•Design deviation management — Review deviations from the Design Criteria Report, RFP, proposal basis, permits, or accepted design criteria; document technical, regulatory, lifecycle, schedule, and cost implications.
•Change request evaluation — Independently evaluate technical merit, scope entitlement, cost, schedule effect, funding eligibility, and downstream consequences of Design-Builder change requests. •Owner-requested changes — Develop technical scope, performance requirements, sketches, independent cost basis, schedule impacts, and negotiation support for City-requested changes.
3. Funding Support
GHD will assist the City’s project director in maximizing available funding resources while maintaining compliance with grant, loan, and reimbursement requirements. Funding management activities will focus on strategic cost allocation, documentation, reimbursement optimization, and long-term funding tracking throughout project delivery. Funding management and reimbursement support services will include the following activities:
•Develop One Master Matrix Before Reimbursement Begins
–Project task / work package
–Invoice cost category
–Eligible funding bucket
–Preferred reimbursement source
–Backup funding source
•Develop Special Eligibility Matrix — Recommended Reimbursement Hierarchy (to use restricted grant funding first, apply match strategically, preserve flexible loan capacity, and maintain backup funding assignments for each cost)
–Start with grant-only eligible costs Use grant funds first where a cost clearly fits a narrow grant bucket.
–Apply match strategically Use eligible non-federal or loan-funded costs to satisfy match requirements where allowed.
–Preserve flexible loan capacity Avoid using loan dollars for costs that could be reimbursed by grants.
–Use backup funding assignments Every cost should have a primary and secondary funding path.
–Track remaining balance by bucket. The project should know not only total funding remaining, but remaining funding by eligible category.
Council Agenda 10-6-2026 12.B-14
Attachment 4
Packet Page 152
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 3
•Prepare grant deliverables – Prepare Prop 1 grant deliverables Performance Assessment and Evaluation Plan (PAEP), Monitoring Plan (MP), and Quality Assurance Project Plan (QAPP) for groundwater monitoring. Prepare first year of semi-annual and annual reports required for grant. •Invoice Coding Strategy — Invoices should be structured for reimbursement from the outset, with task-level detail, eligible cost coding, backup documentation, and review before submittal. •Funding Optimization Strategy — Funding optimization requires active allocation, not default proportional splits, so costs are assigned first to the most specific eligible grant source before using loan funds.
–Do not allocate proportionally by default: A simple percentage split may leave grant dollars unused.
–Allocate based on eligibility first: Match each cost to the source where it is most specifically eligible.
–Use grants before loan dollars: Preserve loan flexibility for costs that are not grant eligible. –Revisit the matrix monthly: Actual invoices, change orders, and remaining balances will shift the best allocation strategy.
–Coordinate funding and delivery schedule: Early work packages may need to be sequenced to meet grant deadlines or preserve reimbursement eligibility. –Funding lead review
–Monthly matrix update
–Change order funding review
–Documentation checklist
–Grant/loan compliance log
4. Project Controls and Risk Management
GHD will provide independent oversight of project schedule performance and key project risks to help keep the project on track and support timely decision-making. This effort includes schedule review, milestone forecasting, and proactive identification and management of technical, regulatory, commercial, and funding risks. Project controls and risk management services will include the following activities:
•Baseline schedule review — Review the Design-Builder’s baseline schedule for logic, calendars, durations, constraints, long-lead procurement, regulator dependencies, funding milestones, float, early work, commissioning, and acceptance.
•Monthly schedule review — Review monthly updates, critical and near-critical paths, out-of-sequence work, slippage, recovery actions, forecast dates, and impacts to funding and permits. •Independent milestone forecasting — Maintain an independent forecast for major design, permitting, funding, well, construction, startup, acceptance, and completion milestones. •Schedule recovery review — Evaluate recovery schedules, resequencing, overtime, added resources, concurrent design/construction risk, and impacts to quality or regulatory compliance. •Owner’s risk register — Maintain an Owner-controlled risk register covering technical, regulatory, hydrogeologic, funding, schedule, commercial, permitting, property, utility, operational, environmental, and stakeholder risks.
5. Design Reviews
GHD will perform a multi-discipline design review of all plans and specs. Disciplines include Treatment Process/Mechanical, Electrical, Site Civil/Stormwater, Conveyance Pipelines, Instrumentation and Controls, Building Mechanical and Architectural, and Operations (Note: Well design reviews are captured in Task 7).
Design review services will include the following activities:
Council Agenda 10-6-2026 12.B-15
Attachment 4
Packet Page 153
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 4
•Design management plan review — Review the Design-Builder’s design management, discipline coordination, BIM, quality, calculation, document-control, and design-release procedures. •Design criteria validation — Confirm applicable flows, water-quality envelope, treatment objectives, pathogen log-reduction requirements, finished-water criteria, availability, redundancy, expansion requirements, design life, codes, and Owner preferences. •BODR- Perform multidisciplinary review of the Basis of Design Report, including confirmation that the design remains consistent with the fixed-price basis and regulatory strategy. •30% design review — Review design development, discipline coordination, equipment selections, hydraulics, controls, operability, maintainability, construction interfaces, permits, cost implications, and resolution of prior comments.
•60% design review — Review design development, discipline coordination, equipment selections, hydraulics, controls, operability, maintainability, construction interfaces, permits, cost implications, and resolution of prior comments.
•90% design review — Review near-final drawings, specifications, calculations, procurement packages, control narratives, testing requirements, and regulatory deliverables. •Final/IFC review — Confirm previous comments are resolved, documents are internally coordinated, permits and agency conditions are incorporated, and the final package is suitable for construction.
6. Construction Submittal and RFI Review
GHD will provide technical support during construction by reviewing critical submittals and RFIs that may affect performance, regulatory compliance, funding eligibility, or Owner requirements. This review process provides an additional layer of Owner protection for high-impact decisions and equipment selections.
Construction phase technical review services will include the following activities:
•Critical submittal review — Review selected critical and performance-sensitive submittals independently from routine Construction Manager processing, focusing on process equipment, wells, membranes, UV/AOP, electrical gear, controls, chemical systems, tanks, and specialty materials. •RFI technical support — Review RFIs with potential impacts to performance, permitting, funding, design intent, lifecycle cost, Owner requirements, or fixed-price scope.
7. Hydrogeology, Wells, and Groundwater Modeling
GHD/Montgomery and Associates will provide specialized hydrogeologic, groundwater modeling, and well- related support necessary for successful implementation and regulatory approval of the potable reuse project.
Services include technical review, regulatory support, adjudication-related coordination, monitoring, and operational groundwater activities through the first year of operation. Hydrogeology, groundwater, and well support services will include the following activities:
• Design Reviews for Injection, Monitoring and Production Wells — Perform design reviews of submitted plans, technical specifications, and construction documentation for the injection well, monitoring wells, and production well (Downhole only, equipment reviews are captured I Task 5). • Review of the Groundwater Section of Title 22 Engineering Report — Review sections related to hydrogeologic conditions, wells, calculation of response retention time, underground retention time. and groundwater monitoring. Review documentation of groundwater models used to support sections.
Support discussions with regulators.
• Review Anti-degradation Analysis Revisions — Review revisions and support discussions with regulators.
• Review Tracer Study Protocol — Review protocol and support discussions with regulators. • Review Background Monitoring — Review plan and results of background groundwater monitoring.
Council Agenda 10-6-2026 12.B-16
Attachment 4
Packet Page 154
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 5
• Tracer Study Implementation — Implement tracer study after start of operation based on approved protocol (prepared by DB team); cost estimate subject to change per final protocol. Prepare required reports for submittal to regulators.
8. Regulatory Support
GHD will assist the City’s project director in navigating the complex regulatory approval process associated with potable reuse, groundwater recharge, and related discharge permits. Regulatory support will focus on maintaining alignment between project delivery, permitting requirements, and agency expectations throughout design, construction, and startup. Regulatory coordination and permitting support services will include the following activities:
x DDW strategy and coordination — Participate in regulatory meetings; review agendas, presentations, technical memoranda, responses, commitments, and decisions related to potable reuse approval.
•Title 22 Engineering Report review— Review outlines, draft sections, calculations, supporting data, pathogen-control strategy, monitoring, alarm and diversion logic, hydrogeology, and final report before submittal.
•Operations Optimization Plan review — Review the initial and updated OOP, including critical control points, operating limits, monitoring, response procedures, reporting, optimization, and operator responsibilities.
•RWQCB permitting support — Review permit applications, waste-discharge requirements, injection requirements, monitoring and reporting provisions, concentrate and process-waste discharge requirements, and responses to comments.
•Ocean discharge coordination — Review the regulatory and technical basis for discharging concentrate, backwash, startup water, off-specification water, and other waste streams through the existing ocean outfall, and coordinate with existing consultant(s) who provides NPDES support for this ocean outfall
•Regulatory testing plans review— Review UV/AOP challenge testing, chlorine contactor tracer testing, membrane integrity testing, water-quality validation, well testing, and other regulator-required protocols and reports.
9. Startup, Commissioning and Testing Support
GHD will support the City’s project director through startup, commissioning, performance testing, and acceptance of the completed facility to verify compliance with contract requirements and regulatory obligations. Activities will provide independent technical oversight and support successful transition from construction to operations. Startup, commissioning, testing, and acceptance support services will include the following activities:
x Owner’s commissioning plan — Develop an Owner-side commissioning and acceptance plan defining roles, prerequisites, witness points, documentation, decision authority, acceptance criteria, and regulatory interfaces.
•Commissioning plan review — Review the Design-Builder’s startup and commissioning plan for sequencing, temporary systems, feed-water availability, waste disposal, staffing, safety, test water, chemical supply, sampling, laboratories, and issue resolution. •Startup readiness reviews — Participate in DB team formal readiness reviews before energization, water introduction, membrane loading, chemical introduction, integrated operation, performance testing, and acceptance testing.
•Factory Acceptance Test review and witnessing — Review FAT procedures and witness selected tests for critical process, electrical, instrumentation, and control equipment.
Council Agenda 10-6-2026 12.B-17
Attachment 4
Packet Page 155
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 6
•Functional testing review — Review and witness selected functional tests of individual systems, sequences, permissives, interlocks, alarms, fail-safe actions, and operator interfaces. •Integrated systems testing — Review and witness selected integrated operation across treatment, waste, utilities, electrical, standby power, controls, communications, wells, pipelines, and off- specification diversion.
•Performance test protocol — Review test duration, capacity, availability, feed-water conditions, water- quality requirements, recovery, energy, chemical consumption, sampling, allowable interruptions, calculations, and failure provisions.
•Performance test witnessing — Provide technical observation, independent data review, daily status assessment, issue tracking, and recommendation regarding successful completion. •Regulatory test support — Coordinate Owner review and witnessing of UV/AOP spike testing, chlorine contactor testing, regulator inspections, and other required demonstrations. •Acceptance test review — Confirm prerequisites for the 30-day acceptance test and independently evaluate continuous operation, compliance, reliability, water quality, injection performance, and outstanding deficiencies. The DB team proposal distinguishes component, functional, performance, and 30-day acceptance testing. Provides 40 hours of onsite support during first week of 30-day acceptance test.
•Performance guarantee verification — Independently confirm compliance with contractual guarantees and document any shortfalls, retesting requirements, corrective work, credits, or other remedies.
•Substantial completion recommendation — Advise the City’s project director whether contractual, technical, regulatory, testing, training, documentation, safety, occupancy, and operational prerequisites for substantial completion have been achieved.
•Final acceptance recommendation — Confirm final testing, permits, punch-list closure, record documents, spares, warranties, training, payments, claims, and closeout conditions before final acceptance.
10. Operations Readiness and Training Support
GHD will help prepare City project director, operational systems, and support programs for efficient, safe, and compliant operation of the new facility. The goal is to ensure personnel, procedures, documentation, training, and support resources are in place before startup and throughout the initial operating period.
Operations readiness and training support services will include the following activities:
•Operations readiness plan — Develop a plan covering staffing, certifications, recruitment, operator involvement, SOPs, O&M documentation, maintenance systems, laboratory capability, chemicals, spares, tools, safety, and regulatory reporting.
•Staffing and certification strategy — Evaluate operator staffing levels, shifts, on-call coverage, certification requirements, recruitment timing, and interim contract-operations support. •Operator design reviews — Facilitate structured operator reviews of equipment access, maintainability, controls, sampling, chemical handling, laboratory needs, storage, safety, and day-to- day workflow.
•O&M manual review — Review completeness, consistency, system descriptions, operating limits, startup/shutdown, maintenance, troubleshooting, safety, controls, spare parts, vendor data, and regulatory requirements.
•SOP review — Review normal, startup, shutdown, emergency, off-specification, chemical delivery, membrane cleaning, well operation, sampling, calibration, and reporting procedures. •Training plan review — Review curriculum, audience, instructors, learning objectives, schedule, prerequisites, hands-on activities, recordings, materials, assessments, and make-up sessions. •Training participation and evaluation — Attend selected training sessions, track attendance, identify gaps, evaluate operator readiness, and recommend supplemental instruction.
Council Agenda 10-6-2026 12.B-18
Attachment 4
Packet Page 156
12686474 | Proposal for Phase 2 (Design/Construction/Commissioning) Owner’s Advisor for Central Coast Blue AWPF Design Build Project 7
•Laboratory readiness — Review laboratory equipment, methods, sampling locations, QA/QC, outside- lab contracts, staffing, data management, reporting, and regulatory requirements. •Safety program readiness — Review chemical safety, confined spaces, lockout/tagout, electrical safety, noise exposure, respiratory protection, emergency response, spill response, and operator training.
•Post-startup technical support oversight — Coordinate and monitor the Design-Builder’s post- startup process optimization, certified-operator support, troubleshooting, regulatory assistance, and OOP updates. The proposal provides continued support during the first six months after substantial completion.
11. Asset Management
GHD has included an allowance of 80 hours of Asset Management technical support. As the project progresses, we propose to further evaluate the needs of the City and put forth additional recommendations for scope and fee.
12. Phase 1 (Procurement) Additional Support
This task covers additional Phase 1 (Procurement) support through Phase 2 (Design/Construction/Commissioning) contract award.
13. Fee
GHD’s proposed fee for this Phase 2 (Design/Construction/Commissioning) Services is $2,233,443.
A detailed Fee Table is attached.
Council Agenda 10-6-2026 12.B-19
Attachment 4
Packet Page 157
Pismo Beach Central Coast Blue - Design Build AWPF Owner Advisor Services 12686474
Description Steve Wait Mark Donovan Kevin Daniels Paul Hermann Rebecca Crow Hector Ruiz Mark Waer Various Ulyssis Robin
Allie Syiem
+ Other Joshua Nathan
Total Hours Labor Total
Montgomery & Total
Travel Costs
Total Estimated
Client Laison
Project Project Strategic Funding Asset Water Junior and Raw Water Building Process
Mech. +
Specialist
Cost
Estimating
and Fire Operations & Admin
$350 $405 $350 $405 $350 $405 $350 $284 $360 $293 $350 $350 $335 $350 $320 $350 $350 $350 $375 $210 Task1 Project Management 50 120 785 120 60 0 0 140 4 4 4 4 4 4 12 4 4 4 4 50 1377 $478,402 $0 $0 $0 $30,000 $30,000 $508,402 Subtask 1.1 General Project Management - including items in scope letter 40 100 625 100 40 0 0 80 0 0 0 0 0 0 0 0 0 0 0 40 1025 $358,870 $0 $0 $0 $30,000 $30,000 $388,870 Subtask 1.2 Weekly Progress Meetings - 24 month duration 10 20 160 20 20 0 0 60 4 4 4 4 4 4 12 4 4 4 4 10 352 $119,532 $0 $0 $0 $0 $0 $119,532 Task2 Contract Requirements Management 10 10 80 10 10 0 0 40 0 0 0 0 24 0 0 0 0 0 0 0 184 $62,500 $0 $0 $0 $0 $0 $62,500 Subtask 2.1 Contract and Requirements Management - per items in scope letter 10 10 80 10 10 0 0 40 0 0 0 0 24 0 0 0 0 0 0 0 184 $62,500 $0 $0 $0 $0 $0 $62,500 Task3 Funding Support 0 0 48 0 200 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 268 $92,480 $0 $0 $0 $0 $0 $92,480 Subtask 3.1 USBR Grant Support 0 0 8 0 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 $16,800 $0 $0 $0 $0 $0 $16,800 Subtask 3.2 Prop 1 GW Grant Management Support 0 0 8 0 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 $16,800 $0 $0 $0 $0 $0 $16,800 Subtask 3.3 SWRCB SRF and Recycled Water Funding Support 0 0 8 0 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 $16,800 $0 $0 $0 $0 $0 $16,800 Subtask 3.4 General Funding tracking and compliance support 0 0 24 0 80 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 124 $42,080 $0 $0 $0 $0 $0 $42,080 Task4 Project Controls and Risk Management 0 0 100 0 0 0 0 24 0 0 0 0 40 0 0 0 0 0 0 0 164 $55,216 $0 $0 $0 $0 $0 $55,216 Subtask 4.1 Project Controls and Risk Management - per items in scope letter 0 0 100 0 0 0 0 24 0 0 0 0 40 0 0 0 0 0 0 0 164 $55,216 $0 $0 $0 $0 $0 $55,216 Task5 Design Reviews 0 76 240 0 0 0 40 312 72 72 42 128 0 32 40 32 54 38 52 0 1230 $410,804 $0 $0 $0 $0 $0 $410,804 Subtask 5.1 Basis of Design Report / Preliminary Design Review 0 8 40 0 0 0 4 32 4 4 2 8 0 2 4 2 4 4 4 0 122 $40,820 $0 $0 $0 $0 $0 $40,820 Subtask 5.2 30% Design Review 0 16 60 0 0 0 8 64 12 12 8 24 0 8 8 8 14 8 12 0 262 $87,852 $0 $0 $0 $0 $0 $87,852 Subtask 5.3 60% Design Review 0 24 60 0 0 0 12 120 24 24 12 40 0 10 12 8 16 12 16 0 390 $128,812 $0 $0 $0 $0 $0 $128,812 Subtask 5.4 90% Design Review 0 24 40 0 0 0 8 64 24 24 12 40 0 8 12 10 12 10 12 0 300 $100,908 $0 $0 $0 $0 $0 $100,908 Subtask 5.5 IFC Design Review 0 4 40 0 0 0 8 32 8 8 8 16 0 4 4 4 8 4 8 0 156 $52,412 $0 $0 $0 $0 $0 $52,412 Task6 Construction Submittal & RFI Review 0 36 160 24 0 0 36 40 16 16 16 52 16 16 40 16 44 12 44 0 584 $203,968 $2,400 $240 $2,640 $0 $0 $206,608 Subtask 6.1 Critical Submittal Review 0 8 40 0 0 0 20 0 0 0 0 24 0 0 16 0 16 0 20 0 144 $50,860 $0 $0 $0 $0 $0 $50,860 Subtask 6.2 Critical RFI Review 0 4 40 0 0 0 8 0 0 0 0 12 0 0 8 0 12 0 12 0 96 $33,880 $2,400 $240 $2,640 $0 $0 $36,520 Subtask 6.3 General Construction Phase Technical Support 0 24 80 24 0 0 8 40 16 16 16 16 16 16 16 16 16 12 12 0 344 $119,228 $0 $0 $0 $0 $0 $119,228 Task7 Hydrogeology, Wells, and Groundwater Modeling 0 0 48 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 $16,800 $329,750 $32,975 $362,725 $0 $0 $379,525 Subtask 7.1 Injection, Monitoring, and Production Well Design Reviews 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $90,240 $9,024 $99,264 $0 $0 $102,064 Subtask 7.2 Groundwater Section of Title 22 Engineering Report Review 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $38,320 $3,832 $42,152 $0 $0 $44,952 Subtask 7.3 Tracer Study Protocol 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $78,280 $7,828 $86,108 $0 $0 $88,908 Subtask 7.4 Background Monitoring 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $34,620 $3,462 $38,082 $0 $0 $40,882 Subtask 7.5 Anti-degradation Analysis Revisions 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $25,060 $2,506 $27,566 $0 $0 $30,366 Subtask 7.6 Tracer Study Implementation 0 0 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 $2,800 $63,230 $6,323 $69,553 $0 $0 $72,353 Task8 Regulatory Support 4 26 108 0 0 0 16 48 0 0 0 0 0 0 28 0 0 0 0 0 230 $77,922 0 0 $0 $0 $0 $77,922 Subtask 8.1 General Regulatory Support 4 10 60 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 74 $26,450 $0 $0 $0 $0 $0 $26,450 Subtask 8.2 DDW Title 22 Engineerign Report Review 0 8 24 0 0 0 8 24 0 0 0 0 0 0 12 0 0 0 0 0 76 $25,096 $0 $0 $0 $0 $0 $25,096 Subtask 8.3 DDW Operations Optimization Plan Review 0 8 24 0 0 0 8 24 0 0 0 0 0 0 16 0 0 0 0 0 80 $26,376 $0 $0 $0 $0 $0 $26,376 Task9 Start-up & Commissioning Support 8 20 200 8 0 0 0 104 0 0 0 0 0 0 200 0 0 0 0 0 540 $177,676 0 0 $0 0 $0 $177,676 Subtask 9.1 Start-up & Commissioning Support - including items in scope letter 0 4 80 0 0 0 0 0 0 0 0 0 0 0 120 0 0 0 0 0 204 $68,020 $0 $0 $0 $0 $0 $68,020 Subtask 9.2 Performance Test Support and Evaluation 0 8 40 0 0 0 0 24 0 0 0 0 0 0 40 0 0 0 0 0 112 $36,856 $0 $0 $0 $0 $0 $36,856 Subtask 9.3 Acceptance Test Support and Evaluation 8 8 80 8 0 0 0 80 0 0 0 0 0 0 40 0 0 0 0 0 224 $72,800 $0 $0 $0 $0 $0 $72,800 Task10 Operations Readiness and Training Support 0 4 16 0 0 0 0 0 0 0 0 0 0 0 60 0 0 0 0 0 80 26420 0 0 $0 0 $0 $26,420 Subtask 10.1 Operations Readiness and Training Support 0 4 16 0 0 0 0 0 0 0 0 0 0 0 60 0 0 0 0 0 80 $26,420 $0 $0 $0 $0 $0 $26,420 Task11 Asset Management Support 0 0 0 0 0 40 0 40 0 0 0 0 0 0 0 0 0 0 0 0 80 $27,560 0 0 $0 0 $0 $27,560 Subtask 11.1 Asset Management Support 0 0 0 0 0 40 0 40 0 0 0 0 0 0 0 0 0 0 0 0 80 $27,560 $0 $0 $0 $0 $0 $27,560 Task12 Well 31 - Potential Future Scope 0 4 40 4 0 0 0 80 0 0 0 0 0 0 0 0 0 0 0 0 128 $39,960 $50,000 5000 $55,000 0 $0 $94,960 Subtask 12.1 Well 31 - Potential Future Scope 0 4 40 4 0 0 0 80 0 0 0 0 0 0 0 0 0 0 0 0 128 $39,960 $50,000 $5,000 $55,000 $0 $0 $94,960 Task13 750 AFY Evaluation - Optional 0 4 24 4 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 52 $17,320 0 0 $0 0 $0 $17,320 Subtask 13.1 Optional Task - Additional Effort Associated with 750 AFY Expansion 0 4 24 4 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 52 $17,320 $0 $0 $0 $0 $0 $17,320 Task14 Phase 1 Additional Support 60 26 50 60 0 0 0 80 0 0 0 0 0 0 0 0 0 0 0 0 276 96050 0 0 $0 0 $0 $96,050 Subtask 14.1 Phase 1 Additional Support 60 26 50 60 0 0 0 80 0 0 0 0 0 0 0 0 0 0 0 0 276 $96,050 $0 $0 $0 $0 $0 $96,050 Total Labor Hours 132 326 1,899 230 270 40 92 948 92 92 62 184 84 52 380 52 102 54 100 50 5241 $1,783,078 $382,150 $38,215 $420,365 $30,000 $30,000 $2,233,443 x Estimated Project Total $46,200 $132,030 $664,650 $93,150 $94,500 $16,200 $32,200 $269,232 $33,120 $26,956 $21,700 $64,400 $28,140 $18,200 $121,600 $18,200 $35,700 $18,900 $37,500 $10,500 5241 $1,783,078 $382,150 $38,215 $420,365 $30,000 $30,000 $2,233,443 GHD reserves the right to move budget between Tasks
Council Agenda 10-6-2026 12.B-20
Attachment 4
Packet Page 158
PISMO BEACH CITY COUNCIL STAF REPOR
Agenda Item #12.C
Meetin Date: October 6, 2026
TITLE:
Side Letter Agreement, Position and Salary Schedule Changes, and Budget Adjustments Related to the Tourism and Events Department and Public Works Department
RECOMMENDATION:
Adopt a Resolution:
1. Approving:
A. A title change and salary range adjustment for Recreation and Tourism Director;
B. Creation of Assistant Public Works Director (Temporary) as a budgeted position;
C. An updated combined salary schedule; and
D. A Side Letter Agreement to the Non-Represented Full-Time Employees Resolution; and
2. Appropriating related budget adjustments in Fiscal Year 2027.
DISCUSSION:
In support of both the Tourism and Events Department Organizational and Staffing Assessment and the start of the construction of the Central Coast Blue recycled water project, staff recommends that the City Council adopt a resolution (Attachment 1) that will accomplish the direction of the City Council and staff’s other recommendations as follows:
Recreation and Tourism Director (Title Chage & Salary Adjustment) Per the City Council’s direction on September 29, 2026, and following an independent comprehensive assessment of the Tourism and Events Department, this resolution will change the department Director’s title to Recreation and Tourism Director to better align with current departmental functions and responsibilities. The job specifications (Attachment 1.A) will remain consistent as the position was already responsible for overseeing both the Recreation and Tourism Divisions. This recommendation aligns the position classification with other City director-level positions and adjusts the salary range accordingly to assist in the future recruiting efforts.
Assistant Public Works Director (Temporary) Position Creation Staff recommends the addition of a new temporary mid-management classification, Assistant Public Works Director (Temporary, At-Will), intended to support critical operational and Capital Improvement Program (CIP) oversight functions within the Public Works Department. This temporary classification is recommended in response to the increased project management and construction oversight demands associated with the Central Coast Blue (CCB) project. As CCB advances into major construction phases, the Council Agenda 10-6-2026 12.C-1
Packet Page 159
Public Works Director will be required to dedicate substantial time and attention to CCB project management and direction.
By adding the Assistant Public Works Director on a temporary basis, the City can strategically separate duties to ensure both continuity and stability across essential Public Works operations and allow succession planning over the next four years. This will ensure adequate time for the construction, regulatory startup, and legal phases of the project which will be the focus of the Public Works Director.
The Assistant Public Works Director will assume day-to-day oversight of Engineering and Operations (Streets, Parks, Fleet, Facilities), interdepartmental coordination, and support for CIP development per the new job specifications (Attachment 1.B). This realignment will allow the Public Works Director to concentrate fully on CCB’s complex technical, regulatory, and multijurisdictional components, with a continued focus on the Utilities Division. This will strengthen the City’s ability to deliver CCB successfully while maintaining high service levels across all Public Works functions.
Combined Salary Schedule Update
The combined salary schedule (Attachment 1.C) has been updated to reflect the recommended changes in position classifications and compensation for both the Recreation and Tourism Director and the Assistant Public Works Director (Temporary).
Side Letter Agreement (Non-Represented Employees FT Employee’s) Update Staff recommends the Side Letter Agreement (Attachment 1.D) to amend the Non- Represented Full-Time Employees Wage & Benefits Resolution. This agreement incorporates the recommended position changes and salary schedule adjustments as outlined above and includes the creation of a project incentive compensation program.
This would allow the Public Works Director to receive special project compensation of up to five percent (5%) above their base salary for the duration of the assignment.
Conclusion and Recommendation
The recommended changes to the Recreation and Tourism Director position are based on the findings of an independent assessment of departmental functions. Establishing the Assistant Public Works Director (Temporary) position is intended to ensure the City’s needs for the Central Coast Blue project are fully addressed, while ensuring the continuity of high service levels across all Public Works functions. The project incentive compensation program is crafted to support the City’s evolving organizational structure and operational requirements. By adopting these measures, the City will align leadership roles with departmental responsibilities, meet critical project management demands, and allocate financial resources in a manner that promotes success into the future.
Staff recommends that the City Council adopt the resolution (Attachment 1) approving:
1. Title change and salary range adjustment for Recreation and Tourism Director (currently TED Director);
2. Creation of Assistant Public Works Director (Temporary) as a budgeted position;
3. An updated combined salary schedule; and
Council Agenda 10-6-2026 12.C-2
Packet Page 160
4. A Side Letter Agreement to the Non-Represented Employees Full-Time Employee’s Resolution; and
appropriating related budget adjustments for Recreation and Tourism Director and Assistant Public Works Director (Temporary) in Fiscal Year 2027.
FISCAL IMPACT:
The fiscal impact of changing the Tourism and Events Director position Range 56 Step E to a Recreation and Tourism Director Range 61 Step C is estimated to be an additional cost to the General Fund of $2,851 in Fiscal Year (FY) 2027 for half of the year and $5,703 for a full year.
The fiscal impact of adding a new Assistant Public Works Director (Temporary) position Range 57 Step C, including overhead costs is an estimated additional cost of $165,599 in FY 2027 for half of the year and $314,234 for a full year. Of this amount, 75% is allocated to the General Fund, 15% is allocated to the Wastewater Enterprise Fund, and 10% is allocated to the Water Enterprise Fund.
The fiscal impact of adding an additional 5% to the Public Works Director position is an additional $10,268 in FY 2027 for 8.5 months and an additional $14,496 for a full year across all funds. If this position is fully supported by the Water and Wastewater Enterprise Funds to support the Central Coast Blue project, then there will be budget savings in the General Fund and budgeted expenditure increases in the Water and Wastewater Enterprise Funds.
The fiscal impact for all three changes is $162,754 in FY 2027 across all funds. Staff recommends appropriating the following amounts in FY 2027 listed in Table 1, while future year costs would be included in the next two-year budget.
Table 1: Estimated FY 2027 Fiscal Impact for Position Changes in Salaries, Benefits, & Overhead Accounts
Fund, Department, Division Amount
General Fund, Recreation & Tourism Dept, CVB Division 1,990 General Fund, Recreation & Tourism Dept, Recreation Division 861 Total Recreation and Tourism Director Chan e $2,851
General Fund, Public Works Dept, Engineering Division 110,562 General Fund, Public Works Dept, Facilities Division, Parks 6,968 General Fund, Public Works Dept, Facilities Division, Streets 6,968 Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
24,466
Water Enterprise Fund, Public Works Dept, Water Division 15,635 Total New Assistant Public Works Director-Temporar $164,599 Council Agenda 10-6-2026 12.C-3
Packet Page 161
Fund, Department, Division Amount
General Fund, Public Works Dept, Engineering Division (155,293) General Fund, Public Works Dept, Facilities Division, Parks (11,946) General Fund, Public Works Dept, Facilities Division, Streets (11,946) Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
46,392
Water Enterprise Fund, Public Works Dept, Water Division 143,058 Total Public Works Director 5% Incentive Chan e $10,268 ATTACHMENTS:
1. Resolution
1.A Recreation and Tourism Director Job Specification
1.B Assistant Public Works Director (Temporary) Job Specification
1.C Combined Salary Schedule
1.D Side Letter Agreement
Submitted by:
Silas Clarke, Assistant City Manager
City Manager Approval:
Council Agenda 10-6-2026 12.C-4
Packet Page 162
PAGE 1 OF 3
RESOLUTION NO. R-2026-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH, CALIFORNIA APPROVING: 1. A TITLE CHANGE AND SALARY RANGE ADJUSTMENT FOR RECREATION AND TOURISM DIRECTOR; 2. CREATION OF
ASSISTANT PUBLIC WORKS DIRECTOR (TEMPORARY) AS A BUDGETED POSITION; 3. AN UPDATED COMBINED SALARY SCHEDULE; AND 4. A SIDE
LETTER AGREEMENT TO THE NON-REPRESENTED FULL-TIME EMPLOYEES RESOLUTION; AND APPROPRIATING RELATED BUDGET ADJUSTMENTS IN FISCAL YEAR 2027
WHEREAS, following a comprehensive assessment of the Tourism and Events Department, staff recommends changing the Director’s title to Recreation and Tourism Director to better align with the Department’s current direction and scope of responsibilities; and
WHEREAS, staff recommends adjusting the salary range for the Recreation and Tourism Director to be consistent with the salary range of other Department Directors and as recommended in the assessment's findings; and
WHEREAS, the City and Full-Time Non-Represented Employees have an existing wage and benefits resolution effective from July 1, 2025, through June 30, 2028; and WHEREAS, staff recommends amending the Full-Time Non-Represented Resolution to reflect the creation of a new at-will, temporary mid-management position classification, Assistant Public Works Director (Temporary); and
WHEREAS, this temporary, at-will classification is recommended in response to the Public Works Director’s increased project management and construction oversight demands associated with the Central Coast Blue (CCB) project and will ensure both continuity and stability across essential Public Works operations; and WHEREAS, staff further recommends amending the Full-Time Non-Represented Resolution to establish Project Incentive Pay for eligible project-based assignments, as directed by the City Manager.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby approves:
1. The updated job title for the Recreation and Tourism Director position and salary range (job specification provided as Exhibit A); and
2. The creation of an Assistant Public Works Director (Temporary) position (job specification provided as Exhibit B), as a budgeted position; and
3. The updated Combined Salary Schedule (Exhibit C); and
4. A Side Letter Agreement for Full-Time Non-Represented Employees Resolution for July 1, 2025, through June 30, 2028 (Exhibit D).
Council Agenda 10-6-2026 12.C-5
Attachment 1
Packet Page 163
PAGE 2 OF 3
BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby appropriates the following amounts in FY 2027 in the Funds, Departments, and Divisions as listed below for total expenditure appropriations across all funds of $162,754, supported by unassigned fund balance and net position in the respective funds:
Fund, Department, Division Account Amount
General Fund, Recreation & Tourism Dept, CVB Division Salaries 1,747 General Fund, Recreation & Tourism Dept, CVB Division Benefits 243 General Fund, Recreation & Tourism Dept, Recreation Division Salaries 749 General Fund, Recreation & Tourism Dept, Recreation Division Benefits 112
Total Recreation and Tourism Director Change $2,851 General Fund, Public Works Dept, Engineering Division Salaries 57,372 General Fund, Public Works Dept, Engineering Division Benefits 43,464 General Fund, Public Works Dept, Facilities Division, Parks Salaries 4,413 General Fund, Public Works Dept, Facilities Division, Parks Benefits 1,806 General Fund, Public Works Dept, Facilities Division, Streets Salaries 4,413 General Fund, Public Works Dept, Facilities Division, Streets Benefits 1,806 Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
Salaries 13,241
Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
Benefits 8,982
Water Enterprise Fund, Public Works Dept, Water Division Salaries 8,826 Water Enterprise Fund, Public Works Dept, Water Division Benefits 5,312 Total New Assistant Public Works Director-Temporary $149,635 General Fund, Public Works Dept, Engineering Division Salaries (98,909) General Fund, Public Works Dept, Engineering Division Benefits (48,989) General Fund, Public Works Dept, Engineering Division Travel & Meetings
(7,395)
General Fund, Public Works Dept, Facilities Division, Parks Salaries (7,608) General Fund, Public Works Dept, Facilities Division, Parks Benefits (3,768) General Fund, Public Works Dept, Facilities Division, Parks Travel & Meetings
(569)
General Fund, Public Works Dept, Facilities Division, Streets Salaries (7,608) General Fund, Public Works Dept, Facilities Division, Streets Benefits (3,768) General Fund, Public Works Dept, Facilities Division, Streets Travel & Meetings
(569)
Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
Salaries 29,901
Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
Benefits 14,283
Wastewater Enterprise Fund, Public Works Dept, Wastewater Division
Travel &
Meetings
2,209
Council Agenda 10-6-2026 12.C-6
Attachment 1
Packet Page 164
PAGE 3 OF 3
Fund, Department, Division Account Amount
Water Enterprise Fund, Public Works Dept, Water Division Salaries 91,832 Water Enterprise Fund, Public Works Dept, Water Division Benefits 44,414 Water Enterprise Fund, Public Works Dept, Water Division Travel & Meetings
6,812
Total Public Works Director 5% Incentive Change $10,268 UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 6th day of October 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
RECUSED:
Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Kirkwood, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and official seal of the City of Pismo Beach on _______________________.
________________________
Erica Kirkwood, City Clerk
Council Agenda 10-6-2026 12.C-7
Attachment 1
Packet Page 165
Recreation and Tourism Director
RECREATION AND TOURISM
DIRECTOR
FLSA: EXEMPT
DEFINITION
Under general direction, plans, organizes, oversees, coordinates, and reviews the work of staff performing administrative support related to all programs and activities of the Recreation Division and Conference and Visitors Bureau, including public relatio ns, media relations, marketing, advertising, Visitor Information Center, facilities, community and City events, and promotions to enhance City income derived from the tourism industry. Manages the effective use of the City’s resources to improve organizational productivity and customer service; provides highly complex and responsible support to the City Manager and others in areas of expertise.
SUPERVISION RECEIVED AND EXERCISED
Receives general direction from the City Manager. Exercises general supervision over administrative support staff.
CLASS CHARACTERISTICS
This is a director classification that directs all public information, media relations, marketing, advertising programs, projects, operations, planning, and activities of the Conference and Visitors Bureau, as well as oversees and reviews work and functions of the Recreation Division. Responsibilities include performing diverse, specialized, and complex work involving significant accountability and decision-making responsibility. The incumbent organizes and oversees day-to-day activities and is responsible for providing professional-level support to the City Manager in a variety of areas. Successful performance of the work requires an extensive professional background as well as the ability to coordinate departmental work with that of other City departments and public agencies.
EXAMPLES OF ESSENTIAL FUNCTIONS (Illustrative Only)
Management reserves the right to add, modify, change, or rescind the work assignments of different positions and to make reasonable accommodations so that qualified employees can perform the essential functions of the job.
Attachment 1.A
Council Agenda 10-6-2026 12.C-8
Packet Page 166
Recreation and Tourism Director
•Plans, manages, and oversees the daily functions, programs, projects, and activities of the Recreation Division and Conference and Visitors Bureau (CVB), including community and city events, public information, media relations, marketing, advertising, and promotional activities.
•Manages and participates in the development and implementation of goals, objectives, policies, and priorities for the CVB; recommends within departmental policy, appropriate service and staffing levels; recommends and administers policies and procedures. •Develops and standardizes procedures and methods to improve the efficiency and effectiveness of programs, projects, and activities; assesses and monitors workload, administrative and support systems, and internal reporting relationships; identifies opportunities for improvement and recommends to the City Manager. •Manages and participates in the development and administration of and oversees the CVB budget.
•Participates in selection, trains, motivates, and evaluates assigned personnel, including personnel assigned to the Visitor Information Center; provides or coordinates staff training; works with employees on performance issues; implements discipline and termination procedures.
•Provides highly complex staff assistance to the City Manager; develops and reviews staff reports related to CVB activities, projects, and programs; presents reports to and advises the City Council and CVB Board of Directors.
•Serves as the primary staff liaison to the CVB Board of Directors; attends meetings and oversees the recording of all official proceedings; supervises the preparation of public notifications, agendas, minutes, and other documents.
•Serves as the primary staff liaison to the Chapman Estate Foundation Board; attends meetings and serves at the contact for City operations at the Chapman Estate. •Manages, develops, and directs visitor serving activities, including the Visitor Information Center, City Events and other events as the Chair of the Special Events Committee ; serves as a staff liaison for the Parks, Recreation, and Beautification Commission. •Manages, develops, and directs highly complex marketing, advertising, public information, media relations, and promotions programs and activities; gathers data and analyzes effectiveness of programs; implements changes and modifies programs; develops and recommends strategies to maximize tourism revenues.
•Oversees the development of promotional and collateral materials; produces and distributes press releases and correspondences; develops articles for the City’s newsletter and local newspaper; represents the City with local media as necessary. •Solicits and organizes participation of local businesses in direct sales promotions, trade shows, conferences, cooperative advertising, and other promotional programs. •Plans, organizes, promotes, and conducts tours of the City and surrounding attractions for groups, travel writers, and other travel professionals. •Coordinates with City department representatives to determine City needs and requirements for contractual services; negotiates contracts and agreements; oversees technical consultants’ work products to ensure adherence to City standards and legal provision s; Attachment 1.A
Council Agenda 10-6-2026 12.C-9
Packet Page 167
Recreation and Tourism Director
ensures that deliverables are submitted on time and budget and that progress and payment requests are consistent with City policy and contract provisions. •Conducts a variety of organizational studies, investigations, and operational studies; recommends modifications to programs, policies, and procedures, as appropriate; serves as the SEC Board Chair.
•Attends and participates in trade shows and professional group meetings to promote Pismo Beach as a tourist destination; stays abreast of new trends and innovations in marketing, advertising, promotions, travel and tourism; researches emerging products and enhancements and their applicability to City needs.
•Monitors changes in regulations and technology that may affect operations; implements policy and procedural changes after approval.
•Receives, investigates, and responds to problems and complaints in a professional manner; identifies and reports findings and takes necessary corrective action. •Performs other duties as assigned.
QUALIFICATIONS
Knowledge of:
•Administrative principles and practices, including goal setting, program and project development, implementation, and evaluation.
•Principles and practices of budget development and administration. •Principles and practices of employee supervision, including work planning, assignment, review and evaluation, and the training of staff in work procedures. •Organization and management practices as applied to the development, analysis, and evaluation of programs, policies, and operational needs of the assigned division. •Principles, practices, and procedures related to advertising, marketing, public relations, and travel and tourism.
•Applicable Federal, State, and local laws, regulatory codes, ordinances, and procedures. •Principles and practices of contract administration and evaluation. •Recent and on-going developments, current literature, and sources of information marketing, advertising, public information, travel, and tourism programs, activities, and projects.
•Practices of researching issues, evaluating alternatives, making sound recommendations, and preparing and presenting effective staff reports.
•Methods and techniques of effective technical report preparation and presentation. •Modern office practices, methods, and computer equipment and applications. •English usage, grammar, spelling, vocabulary, and punctuation. •Techniques for effectively representing the City in contacts with governmental agencies, community groups, various business, professional, educational and regulatory organizations, and with property owners, developers, contractors, and the public. •Techniques for providing a high level of customer service by effectively dealing with the public, vendors, contractors, and City staff.
Attachment 1.A
Council Agenda 10-6-2026 12.C-10
Packet Page 168
Recreation and Tourism Director
Ability to:
•Administrative principles and practices, including goal setting, program and project development, implementation, and evaluation.
•Principles and practices of budget development and administration. •Principles and practices of employee supervision, including work planning, assignment, review and evaluation, and the training of staff in work procedures. •Organization and management practices as applied to the development, analysis, and evaluation of programs, policies, and operational needs of the assigned division. •Principles, practices, and procedures related to advertising, marketing, public relations, and travel and tourism.
•Applicable Federal, State, and local laws, regulatory codes, ordinances, and procedures. •Principles and practices of contract administration and evaluation. •Recent and on-going developments, current literature, and sources of information marketing, advertising, public information, travel, and tourism programs, activities, and projects.
•Practices of researching issues, evaluating alternatives, making sound recommendations, and preparing and presenting effective staff reports.
•Methods and techniques of effective technical report preparation and presentation. •Modern office practices, methods, and computer equipment and applications. •English usage, grammar, spelling, vocabulary, and punctuation. •Techniques for effectively representing the City in contacts with governmental agencies, community groups, various business, professional, educational and regulatory organizations, and with property owners, developers, contractors, and the public. •Techniques for providing a high level of customer service by effectively dealing with the public, vendors, contractors, and City staff.
Education and Experience:
Any combination of training and experience that would provide the required knowledge, skills, and abilities is qualifying. A typical way to obtain the required qualifications would be:
Bachelor’s Degree in marketing, advertising, public or business administration, or a related field and ten (10) years of responsible experience in tourism promotion programs.
Licenses and Certifications
•Possession of, or ability to obtain, a valid California Driver’s License by time of appointment.
Physical Demands
Must possess mobility to work in a standard office setting and use standard office equipment, including a computer; to operate a motor vehicle and to visit various City and meeting sites, including city events; vision to read printed materials and a computer screen; and hearing and Attachment 1.A
Council Agenda 10-6-2026 12.C-11
Packet Page 169
Recreation and Tourism Director
speech to communicate in person, before groups, and over the telephone. This is primarily a sedentary office classification although standing in and walking between work areas, as well as active participation during outdoor events is be required. Finger dexterity is needed to access, enter, and retrieve data using a computer keyboard or calculator and to operate standard office equipment. Positions in this classification frequently bend, stoop, kneel, reach, walk on uneven surfaces to participate in city events, push, and pull drawers open and closed to retrieve and file information. Employees must possess the ability to lift, carry, push, and pull materials and objects up to 30 pounds.
Environmental Elements
Employees partially work in an office environment with moderate noise levels, controlled temperature conditions and no direct exposure to hazardous physical substances. Incumbents partially work in the field and may be exposed to inclement weather. Employe es may interact with upset staff and/or public and private representatives in interpreting and enforcing departmental policies and procedures.
Prepared by: Public Sector Personnel Consultants
Updated by: Human Resources, 10/06/2026
Council Approved:
Attachment 1.A
Council Agenda 10-6-2026 12.C-12
Packet Page 170
Assistant Public Works (TEMP)
ASSISTANT PUBLIC WORKS
DIRECTOR (TEMPORARY, AT WILL)
FLSA: EXEMPT
DEFINITION
Plans, organizes, manages, and provides administrative direction and oversight for functions and activities of the Public Works Department, including design and construction activities, maintenance and operations of sanitation, streets, fleet services, facilities, parks, beach and pier maintenance, environmental compliance, traffic, and development and implementation of the City’s Capital Improvement Program (CIP); coordinates assigned activities with other City departments, officials, outside agencies, and the public; fosters cooperative working relationships among City departments and with intergovernmental and regulatory agencies and various public and private groups; provides highly responsible and complex professional assistance to the Public Works Director and Assistant City Manager in areas of expertise. This is a temporary, at-will position.
SUPERVISION RECEIVED AND EXERCISED
Receives administrative direction from the Public Works Director and Assistant City Manager.
The work provides for a wide variety of independent decision-making, within legal and general policy and regulatory guidelines. Exercises general direction and supervision over mid- management, supervisory, professional, technical, and administrative support staff through subordinate levels of supervision.
CLASS CHARACTERISTICS
This is a temporary, at will, limited-term management classification within the Public Works Department. Under limited administrative direction from the Public Works Director and Assistant City Manager, oversees, directs, and participates in Engineering and Operations (Streets, Parks, Fleet and Facilities) activities of the Public Works Department, including short- and long-term planning, development, and administration of departmental policies, procedures, and services.
This class provides assistance to the Public Works Director and the Assistant City Manager in a variety of administrative, coordinative, analytical, and liaison capacities. Successful performance of the work requires knowledge of public policy, municipal functions and activities, including the role of an elected City Council, and the ability to develop, oversee, and implement projects and programs in a variety of areas. Responsibilities include coordinating the activities of the department with those of other departments and outside agencies and managing and overseeing Attachment 1.B
Council Agenda 10-6-2026 12.C-13
Packet Page 171
Assistant Public Works (TEMP)
the complex and varied functions of the department. The incumbent is accountable for accomplishing departmental planning and operational goals and objectives and for furthering City goals and objectives within general policy guidelines.
EXAMPLES OF ESSENTIAL FUNCTIONS (Illustrative Only)
Management reserves the right to add, modify, change, or rescind the work assignments of different positions and to make reasonable accommodations so that qualified employees can perform the essential functions of the job.
• Assumes full management responsibility for the Engineering and Operation Divisions (Streets, Parks, Fleet and Facilities) of the Public Works Department programs, services, and activities. • Develops, directs, and coordinates the implementation of goals, objectives, policies, procedures, and work standards for the department; establishes, within City policy, appropriate budget, service, and staffing levels.
• Manages and participates in the development and administration of the department’s annual budget; directs the forecast of additional funds needed for staffing, equipment, materials, and supplies; directs the monitoring of and approves expenditures; directs and implements adjustments as necessary.
• Selects, trains, motivates, and directs department personnel; evaluates and reviews work for acceptability and conformance with department standards, including program and project priorities and performance evaluations; works with employees on performance issues; implements discipline and termination procedures; responds to staff questions and concerns. • Contributes to the overall quality of the department’s service by developing, reviewing, and implementing policies and procedures to meet legal requirements and City needs; continuously monitors and evaluates the efficiency and effectiveness of service delivery methods and procedures; assesses and monitors the distribution of work, support systems, and internal reporting relationships; identifies opportunities for improvement; directs the implementation of change.
• Evaluates the need for and develops, plans, and schedules for long-term public works maintenance programs; organizes available resources for the maintenance, improvement, and repair of public works facilities and City equipment; compiles estimates, contract provisions, and specifications.
• Develops, plans, organizes, and implements a long-term Capital Improvement Program (CIP) and resource plans for the future development of the community; reviews the designs, materials, and processes proposed in connection with new construction or major repairs for City facilities and capital improvements; prepares and/or reviews ordinances for City Council consideration; recommends levels of service for streets and drainage areas. • Confers with developers, architects, a variety of outside agencies and, the general public in acquiring information and coordination of public works, streets, and related matters; provides information regarding these matters.
• Administers the subdivision approval process including improvement plans, track maps, parcel maps, and development reviews.
Attachment 1.B
Council Agenda 10-6-2026 12.C-14
Packet Page 172
Assistant Public Works (TEMP)
•Oversees the development of consultant requests for proposals for professional services and the advertising and bid processes; evaluates proposals and recommends project award; coordinates with legal counsel to determine City needs and requirements for contractual services; negotiates contracts and agreements and administers same after award. •Represents the department to other City departments, elected officials, and outside agencies; explains and interprets departmental programs, policies, and activities; negotiates and resolves significant and controversial issues.
•Conducts a variety of departmental organizational and operational studies and investigations; recommends modifications to programs, policies, and procedures as appropriate. •Develops financial plans, rate studies, grant proposals and other financing mechanisms to support the department’s goals and objectives.
•Participates in and makes presentations to the City Council and a wide variety of committees, boards, and commissions; represents the community at various regional government meetings regarding transportation, growth, and development issues. •Attends and participates in professional group meetings; stays abreast of new trends and innovations in the field of public works maintenance, operations, and other services as they relate to the area of assignment.
•Maintains and directs the maintenance of working and official departmental files. •Monitors changes in laws, regulations, and technology that may affect City or departmental operations; implements policy and procedural changes as required. •Prepares, reviews, and presents staff reports, various management and information updates, and reports on special projects as assigned by the City Manager. •Responds to difficult and sensitive public inquiries and complaints and assists with resolutions and alternative recommendations.
•Performs other duties as assigned.
QUALIFICATIONS
Knowledge of:
•Administrative principles and practices, including goal setting, program development, implementation, and evaluation, and supervision of staff, either directly or through subordinate levels of supervision.
•Public agency budget development, contract administration, City-wide administrative practices, and general principles of risk management related to the functions of the assigned area.
•Organizational and management practices as applied to the analysis and evaluation of projects, programs, policies, procedures, and operational needs; principles and practices of municipal government administration.
•Principles and practices of public works program development, management in a municipal setting, and public works long-term maintenance planning and budgeting. •Applicable Federal, State, and local laws, regulatory codes, ordinances, and procedures relevant to assigned area of responsibility.
Attachment 1.B
Council Agenda 10-6-2026 12.C-15
Packet Page 173
Assistant Public Works (TEMP)
•Methods and techniques for the development of presentations, contract negotiations, business correspondence, and information distribution; research and reporting methods, techniques, and procedures.
•Record-keeping principles and procedures.
•Modern office practices, methods, and computer equipment and applications related to the work.
•English usage, grammar, spelling, vocabulary, and punctuation. •Techniques for effectively representing the City in contacts with governmental agencies, community groups, and various business, professional, educational, regulatory, and legislative organizations.
•Techniques for providing a high level of customer service by effectively dealing with the public, vendors, contractors, and City staff.
Ability to:
•Develop and implement goals, objectives, policies, procedures, work standards, and internal controls for the department and assigned program areas. •Provide administrative and professional leadership and direction for the department and the City.
•Prepare and administer large and complex budgets; allocate limited resources in a cost effective manner.
•Interpret, apply, and ensure compliance with Federal, State, and local policies, procedures, laws, and regulations.
•Plan, organize, direct, and coordinate the work of management, supervisory, professional, and technical personnel; delegate authority and responsibility; select, motivate, and evaluate the work of staff and train staff in work procedures.
•Research, analyze, and evaluate new service delivery methods, procedures, and techniques. •Effectively administer special projects with contractual agreements and ensure compliance with stipulations; effectively administer a variety of public works programs and administrative activities.
•Conduct effective negotiations and effectively represent the City and the department in meetings with governmental agencies, contractors, vendors, and various businesses, professional, regulatory, and legislative organizations. •Prepare clear and concise reports, correspondence, policies, procedures, and other written materials.
•Conduct complex research projects, evaluate alternatives, make sound recommendations, and prepare effective technical staff reports.
•Establish and maintain a variety of filing, record-keeping, and tracking systems. •Organize and prioritize a variety of projects and multiple tasks in an effective and timely manner; organize own work, set priorities, and meet critical time deadlines. •Operate modern office equipment including computer equipment and specialized software applications programs.
•Use English effectively to communicate in person, over the telephone, and in writing.
Attachment 1.B
Council Agenda 10-6-2026 12.C-16
Packet Page 174
Assistant Public Works (TEMP)
• Use tact, initiative, prudence, and independent judgment within general policy, procedural, and legal guidelines.
• Establish, maintain, and foster positive and harmonious working relationships with those contacted in the course of work.
Education and Experience:
Any combination of training and experience that would provide the required knowledge, skills, and abilities is qualifying. A typical way to obtain the required qualifications would be:
Bachelor’s degree with major coursework in engineering, public administration, or a related field and five (5) years of management and/or administrative experience in professional engineering, capital improvement programs, and public works management and operations.
Licenses and Certifications
• Possession of, or ability to obtain, a valid California Driver’s License by time of appointment.
Physical Demands
Must possess mobility to work in a standard office setting and use standard office equipment, including a computer, to inspect City infrastructure and development sites, to operate a motor vehicle, and to visit various City and meeting sites; vision to read printed materials and a computer screen; and hearing and speech to communicate in person, before groups, and over the telephone. This is primarily a sedentary office classification, although standing in and walking between work areas, construction sites, lift stations, and uneven surfaces is required. Finger dexterity is needed to access, enter, and retrieve data using a computer keyboard or calculator and to operate standard office equipment. Positions in this classification occasionally bend, stoop, kneel, reach, push, and pull drawers open and closed to retrieve and file information.
Employees must possess the ability to lift, carry, push, and pull materials and objects weighing up to 25 pounds.
Environmental Elements
Employees work in an office environment with moderate noise levels, controlled temperature conditions, and no direct exposure to hazardous physical substances. Employees may interact with upset staff and/or public and private representatives in interpreting and enforcing departmental policies and procedures.
Prepared by: Human Resources
Council Approved:
Attachment 1.B
Council Agenda 10-6-2026 12.C-17
Packet Page 175
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
Classification Title Range #Period Step A Step B Step C Step D Step E PT1 1 Hourly 19.31 20.28 21.29 22.36 23.47
Bi-weekly 1,544.80 1,622.40 1,703.20 1,788.80 1,877.60 Monthly 3,347.07 3,515.20 3,690.27 3,875.73 4,068.13 Annual 40,164.80 42,182.40 44,283.20 46,508.80 48,817.60 PT2 2 Hourly 19.79 20.78 21.82 22.91 24.06
Bi-weekly 1,583.20 1,662.40 1,745.60 1,832.80 1,924.80 Monthly 3,430.27 3,601.87 3,782.13 3,971.07 4,170.40 Annual 41,163.20 43,222.40 45,385.60 47,652.80 50,044.80 PT3 3 Hourly 20.29 21.30 22.37 23.49 24.66
Bi-weekly 1,623.20 1,704.00 1,789.60 1,879.20 1,972.80 Monthly 3,516.93 3,692.00 3,877.47 4,071.60 4,274.40 Annual 42,203.20 44,304.00 46,529.60 48,859.20 51,292.80 PT4 4 Hourly 20.80 21.84 22.93 24.07 25.28
Bi-weekly 1,664.00 1,747.20 1,834.40 1,925.60 2,022.40 Monthly 3,605.33 3,785.60 3,974.53 4,172.13 4,381.87 Annual 43,264.00 45,427.20 47,694.40 50,065.60 52,582.40 PT5 5 Hourly 21.32 22.38 23.50 24.68 25.91
Bi-weekly 1,705.60 1,790.40 1,880.00 1,974.40 2,072.80 Monthly 3,695.47 3,879.20 4,073.33 4,277.87 4,491.07 Annual 44,345.60 46,550.40 48,880.00 51,334.40 53,892.80 PT6 6 Hourly 21.85 22.94 24.09 25.29 26.56
Bi-weekly 1,748.00 1,835.20 1,927.20 2,023.20 2,124.80 Monthly 3,787.33 3,976.27 4,175.60 4,383.60 4,603.73 Annual 45,448.00 47,715.20 50,107.20 52,603.20 55,244.80 Office Assistant I 7 Hourly 22.40 23.52 24.69 25.93 27.22 PT7 Bi-weekly 1,792.00 1,881.60 1,975.20 2,074.40 2,177.60 Monthly 3,882.67 4,076.80 4,279.60 4,494.53 4,718.13 Annual 46,592.00 48,921.60 51,355.20 53,934.40 56,617.60 PT8 8 Hourly 22.96 24.10 25.31 26.57 27.90
Bi-weekly 1,836.80 1,928.00 2,024.80 2,125.60 2,232.00 Monthly 3,979.73 4,177.33 4,387.07 4,605.47 4,836.00 Annual 47,756.80 50,128.00 52,644.80 55,265.60 58,032.00 PT9 9 Hourly 23.53 24.71 25.94 27.24 28.60
Bi-weekly 1,882.40 1,976.80 2,075.20 2,179.20 2,288.00 Monthly 4,078.53 4,283.07 4,496.27 4,721.60 4,957.33 Annual 48,942.40 51,396.80 53,955.20 56,659.20 59,488.00 PT10 10 Hourly 24.12 25.32 26.59 27.92 29.32
Bi-weekly 1,929.60 2,025.60 2,127.20 2,233.60 2,345.60 Monthly 4,180.80 4,388.80 4,608.93 4,839.47 5,082.13 Annual 50,169.60 52,665.60 55,307.20 58,073.60 60,985.60 Office Assistant II 11 Hourly 24.72 25.96 27.25 28.62 30.05 PT11 Bi-weekly 1,977.60 2,076.80 2,180.00 2,289.60 2,404.00 Monthly 4,284.80 4,499.73 4,723.33 4,960.80 5,208.67 Annual 51,417.60 53,996.80 56,680.00 59,529.60 62,504.00 Attachment 1.C
Council Agenda 10-6-2026 12.C-18
Packet Page 176
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
PT12 12 Hourly 25.34 26.61 27.94 29.33 30.80
Bi-weekly 2,027.20 2,128.80 2,235.20 2,346.40 2,464.00 Monthly 4,392.27 4,612.40 4,842.93 5,083.87 5,338.67 Annual 52,707.20 55,348.80 58,115.20 61,006.40 64,064.00 Maintenance Worker I 13 Hourly 25.97 27.27 28.63 30.07 31.57 PT13 Bi-weekly 2,077.60 2,181.60 2,290.40 2,405.60 2,525.60 Monthly 4,501.47 4,726.80 4,962.53 5,212.13 5,472.13 Annual 54,017.60 56,721.60 59,550.40 62,545.60 65,665.60 Fleet Mechanic I 14 Hourly 26.62 27.95 29.35 30.82 32.36 PT14 Bi-weekly 2,129.60 2,236.00 2,348.00 2,465.60 2,588.80 Monthly 4,614.13 4,844.67 5,087.33 5,342.13 5,609.07 Annual 55,369.60 58,136.00 61,048.00 64,105.60 67,308.80 Administrative Assistant 15 Hourly 27.29 28.65 30.08 31.59 33.17 PT15 Bi-weekly 2,183.20 2,292.00 2,406.40 2,527.20 2,653.60 Monthly 4,730.27 4,966.00 5,213.87 5,475.60 5,749.47 Annual 56,763.20 59,592.00 62,566.40 65,707.20 68,993.60 Parking Enforcement Technician 16 Hourly 27.97 29.37 30.84 32.38 34.00 PT16 Bi-weekly 2,237.60 2,349.60 2,467.20 2,590.40 2,720.00 Monthly 4,848.13 5,090.80 5,345.60 5,612.53 5,893.33 Annual 58,177.60 61,089.60 64,147.20 67,350.40 70,720.00 Accounting Clerk 17 Hourly 28.67 30.10 31.61 33.19 34.85 PT17 Bi-weekly 2,293.60 2,408.00 2,528.80 2,655.20 2,788.00 Monthly 4,969.47 5,217.33 5,479.07 5,752.93 6,040.67 Annual 59,633.60 62,608.00 65,748.80 69,035.20 72,488.00 Water Systems Operator I 18 Hourly 29.39 30.85 32.40 34.02 35.72 PT18 Bi-weekly 2,351.20 2,468.00 2,592.00 2,721.60 2,857.60 Monthly 5,094.27 5,347.33 5,616.00 5,896.80 6,191.47 Annual 61,131.20 64,168.00 67,392.00 70,761.60 74,297.60 Police Records Technician 19 Hourly 30.12 31.63 33.21 34.87 36.61 Wastewater Operator I Bi-weekly 2,409.60 2,530.40 2,656.80 2,789.60 2,928.80 PT19 Monthly 5,220.80 5,482.53 5,756.40 6,044.13 6,345.73 Annual 62,649.60 65,790.40 69,076.80 72,529.60 76,148.80 Community Services Technician NS 19 Hourly 31.32 32.89 34.53 36.26 38.07 PT-NS19 Bi-weekly 2,505.60 2,631.20 2,762.40 2,900.80 3,045.60 Monthly 5,428.80 5,700.93 5,985.20 6,285.07 6,598.80 Annual 65,145.60 68,411.20 71,822.40 75,420.80 79,185.60 Recreation Coordinator 20 Hourly 30.87 32.42 34.04 35.74 37.53 PT20 Bi-weekly 2,469.60 2,593.60 2,723.20 2,859.20 3,002.40 Monthly 5,350.80 5,619.47 5,900.27 6,194.93 6,505.20 Annual 64,209.60 67,433.60 70,803.20 74,339.20 78,062.40 Accounting Technician 21 Hourly 31.64 33.23 34.89 36.63 38.46 Senior Administrative Assistant Bi-weekly 2,531.20 2,658.40 2,791.20 2,930.40 3,076.80 Permit Technician Monthly 5,484.27 5,759.87 6,047.60 6,349.20 6,666.40 Maintenance Worker II Annual 65,811.20 69,118.40 72,571.20 76,190.40 79,996.80 PT21
Attachment 1.C
Council Agenda 10-6-2026 12.C-19
Packet Page 177
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
PT22 22 Hourly 32.44 34.06 35.76 37.55 39.43
Bi-weekly 2,595.20 2,724.80 2,860.80 3,004.00 3,154.40 Monthly 5,622.93 5,903.73 6,198.40 6,508.67 6,834.53 Annual 67,475.20 70,844.80 74,380.80 78,104.00 82,014.40 Code Compliance Inspector 23 Hourly 33.25 34.91 36.65 38.49 40.41 Senior Police Records Technician Bi-weekly 2,660.00 2,792.80 2,932.00 3,079.20 3,232.80 Water Systems Operator II Monthly 5,763.33 6,051.07 6,352.67 6,671.60 7,004.40 PT23 Annual 69,160.00 72,612.80 76,232.00 80,059.20 84,052.80 Property and Evidence Technician NS 23 Hourly 34.57 36.30 38.12 40.02 42.02 PT-NS23 Bi-weekly 2,765.60 2,904.00 3,049.60 3,201.60 3,361.60 Monthly 5,992.13 6,292.00 6,607.47 6,936.80 7,283.47 Annual 71,905.60 75,504.00 79,289.60 83,241.60 87,401.60 Engineering Technician 24 Hourly 34.08 35.78 37.57 39.45 41.42 Executive Assistant Bi-weekly 2,726.40 2,862.40 3,005.60 3,156.00 3,313.60 Executive Assistant to the City Manager Monthly 5,907.20 6,201.87 6,512.13 6,838.00 7,179.47 Fleet Mechanic II Annual 70,886.40 74,422.40 78,145.60 82,056.00 86,153.60 Lead Maintenance Worker
Tourism Coordinator
PT24
Wastewater Operator II 25 Hourly 34.93 36.68 38.51 40.44 42.46 PT25 Bi-weekly 2,794.40 2,934.40 3,080.80 3,235.20 3,396.80 Monthly 6,054.53 6,357.87 6,675.07 7,009.60 7,359.73 Annual 72,654.40 76,294.40 80,100.80 84,115.20 88,316.80 Public Safety Dispatcher NS 25 Hourly 36.32 38.14 40.05 42.05 44.15 PT-NS25 Bi-weekly 2,905.60 3,051.20 3,204.00 3,364.00 3,532.00 Monthly 6,295.47 6,610.93 6,942.00 7,288.67 7,652.67 Annual 75,545.60 79,331.20 83,304.00 87,464.00 91,832.00 Building Inspector I 26 Hourly 35.80 37.59 39.47 41.45 43.52 Crime Analyst Bi-weekly 2,864.00 3,007.20 3,157.60 3,316.00 3,481.60 PT26 Monthly 6,205.33 6,515.60 6,841.47 7,184.67 7,543.47 Annual 74,464.00 78,187.20 82,097.60 86,216.00 90,521.60 IT Specialist 27 Hourly 36.70 38.53 40.46 42.48 44.61
Lead Water Systems Operator Bi-weekly 2,936.00 3,082.40 3,236.80 3,398.40 3,568.80 PT27 Monthly 6,361.33 6,678.53 7,013.07 7,363.20 7,732.40 Annual 76,336.00 80,142.40 84,156.80 88,358.40 92,788.80 Recreation Supervisor 28 Hourly 37.62 39.50 41.47 43.54 45.72 Facility and Fleet Supervisor Bi-weekly 3,009.60 3,160.00 3,317.60 3,483.20 3,657.60 Parks Maintenance Supervisor Monthly 6,520.80 6,846.67 7,188.13 7,546.93 7,924.80 Streets Maintenance Supervisor Annual 78,249.60 82,160.00 86,257.60 90,563.20 95,097.60 PT28
Assistant Planner 29 Hourly 38.56 40.48 42.51 44.63 46.87 Lead Wastewater Operator Bi-weekly 3,084.80 3,238.40 3,400.80 3,570.40 3,749.60 Regulatory Compliance Coordinator Monthly 6,683.73 7,016.53 7,368.40 7,735.87 8,124.13 PT29 Annual 80,204.80 84,198.40 88,420.80 92,830.40 97,489.60 Attachment 1.C
Council Agenda 10-6-2026 12.C-20
Packet Page 178
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
Senior Public Safety Dispatcher NS 29 Hourly 40.09 42.10 44.20 46.41 48.73 PT-NS29 Bi-weekly 3,207.20 3,368.00 3,536.00 3,712.80 3,898.40 Monthly 6,948.93 7,297.33 7,661.33 8,044.40 8,446.53 Annual 83,387.20 87,568.00 91,936.00 96,532.80 101,358.40 Building Inspector II 30 Hourly 39.52 41.50 43.57 45.75 48.04 Parking Operations Supervisor Bi-weekly 3,161.60 3,320.00 3,485.60 3,660.00 3,843.20 PT30 Monthly 6,850.13 7,193.33 7,552.13 7,930.00 8,326.93 Annual 82,201.60 86,320.00 90,625.60 95,160.00 99,923.20 Accountant 31 Hourly 40.51 42.53 44.66 46.89 49.24
Assistant Engineer Bi-weekly 3,240.80 3,402.40 3,572.80 3,751.20 3,939.20 Management Analyst Monthly 7,021.73 7,371.87 7,741.07 8,127.60 8,534.93 Tourism Manager Annual 84,260.80 88,462.40 92,892.80 97,531.20 102,419.20 Water Systems Supervisor
PT31
Associate Planner 32 Hourly 41.52 43.60 45.78 48.07 50.47 PT32 Bi-weekly 3,321.60 3,488.00 3,662.40 3,845.60 4,037.60 Monthly 7,196.80 7,557.33 7,935.20 8,332.13 8,748.13 Annual 86,361.60 90,688.00 95,222.40 99,985.60 104,977.60 Police Support Services Supervisor NS 32 Hourly 43.18 45.34 47.60 49.98 52.48 PT-NS32 Bi-weekly 3,454.40 3,627.20 3,808.00 3,998.40 4,198.40 Monthly 7,484.53 7,858.93 8,250.67 8,663.20 9,096.53 Annual 89,814.40 94,307.20 99,008.00 103,958.40 109,158.40 Building Inspector/Plans Examiner 33 Hourly 42.56 44.69 46.92 49.27 51.73 Wastewater Systems Supervisor Bi-weekly 3,404.80 3,575.20 3,753.60 3,941.60 4,138.40 PT33 Monthly 7,377.07 7,746.27 8,132.80 8,540.13 8,966.53 Annual 88,524.80 92,955.20 97,593.60 102,481.60 107,598.40 Senior Management Analyst 34 Hourly 43.62 45.80 48.09 50.50 53.02 Senior Accountant Bi-weekly 3,489.60 3,664.00 3,847.20 4,040.00 4,241.60 GIS Analyst Monthly 7,560.80 7,938.67 8,335.60 8,753.33 9,190.13 PT34 Annual 90,729.60 95,264.00 100,027.20 105,040.00 110,281.60 PT35 35 Hourly 44.71 46.95 49.30 51.76 54.35
Bi-weekly 3,576.80 3,756.00 3,944.00 4,140.80 4,348.00 Monthly 7,749.73 8,138.00 8,545.33 8,971.73 9,420.67 Annual 92,996.80 97,656.00 102,544.00 107,660.80 113,048.00 Finance Supervisor 36 Hourly 45.83 48.12 50.53 53.06 55.71 PT36 Bi-weekly 3,666.40 3,849.60 4,042.40 4,244.80 4,456.80 Monthly 7,943.87 8,340.80 8,758.53 9,197.07 9,656.40 Annual 95,326.40 100,089.60 105,102.40 110,364.80 115,876.80 Police Officer SW 36 Hourly 46.74 49.08 51.53 54.11 56.81 PT-SW36 Bi-weekly 3,739.20 3,926.40 4,122.40 4,328.80 4,544.80 Monthly 8,101.60 8,507.20 8,931.87 9,379.07 9,847.07 Annual 97,219.20 102,086.40 107,182.40 112,548.80 118,164.80 Attachment 1.C
Council Agenda 10-6-2026 12.C-21
Packet Page 179
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
Senior Planner 37 Hourly 46.98 49.33 51.79 54.38 57.10
PT37 Bi-weekly 3,758.40 3,946.40 4,143.20 4,350.40 4,568.00 Monthly 8,143.20 8,550.53 8,976.93 9,425.87 9,897.33 Annual 97,718.40 102,606.40 107,723.20 113,110.40 118,768.00 Capital Projects Manager 38 Hourly 48.15 50.56 53.09 55.74 58.53 PT38 Bi-weekly 3,852.00 4,044.80 4,247.20 4,459.20 4,682.40 Monthly 8,346.00 8,763.73 9,202.27 9,661.60 10,145.20 Annual 100,152.00 105,164.80 110,427.20 115,939.20 121,742.40 PT39 39 Hourly 49.35 51.82 54.41 57.13 59.99
Bi-weekly 3,948.00 4,145.60 4,352.80 4,570.40 4,799.20 Monthly 8,554.00 8,982.13 9,431.07 9,902.53 10,398.27 Annual 102,648.00 107,785.60 113,172.80 118,830.40 124,779.20 Public Works Operations Manager 40 Hourly 50.59 53.12 55.77 58.56 61.49 PT40 Bi-weekly 4,047.20 4,249.60 4,461.60 4,684.80 4,919.20 Monthly 8,768.93 9,207.47 9,666.80 10,150.40 10,658.27 Annual 105,227.20 110,489.60 116,001.60 121,804.80 127,899.20 Police Corporal SW 40 Hourly 51.59 54.17 56.88 59.72 62.71 PT-SW40 Bi-weekly 4,127.20 4,333.60 4,550.40 4,777.60 5,016.80 Monthly 8,942.27 9,389.47 9,859.20 10,351.47 10,869.73 Annual 107,307.20 112,673.60 118,310.40 124,217.60 130,436.80 PT41 41 Hourly 51.85 54.45 57.17 60.03 63.03
Bi-weekly 4,148.00 4,356.00 4,573.60 4,802.40 5,042.40 Monthly 8,987.33 9,438.00 9,909.47 10,405.20 10,925.20 Annual 107,848.00 113,256.00 118,913.60 124,862.40 131,102.40 Engineer 42 Hourly 53.15 55.81 58.60 61.53 64.60
Recreation Manager Bi-weekly 4,252.00 4,464.80 4,688.00 4,922.40 5,168.00 PT42 Monthly 9,212.67 9,673.73 10,157.33 10,665.20 11,197.33 Annual 110,552.00 116,084.80 121,888.00 127,982.40 134,368.00
City Clerk 43 Hourly 54.48 57.20 60.06 63.07 66.22
PT43 Bi-weekly 4,358.40 4,576.00 4,804.80 5,045.60 5,297.60 Monthly 9,443.20 9,914.67 10,410.40 10,932.13 11,478.13 Annual 113,318.40 118,976.00 124,924.80 131,185.60 137,737.60 Human Resources Officer 44 Hourly 55.84 58.63 61.56 64.64 67.87 PT44 Bi-weekly 4,467.20 4,690.40 4,924.80 5,171.20 5,429.60 Monthly 9,678.93 10,162.53 10,670.40 11,204.27 11,764.13 Annual 116,147.20 121,950.40 128,044.80 134,451.20 141,169.60 PT45 45 Hourly 57.24 60.10 63.10 66.26 69.57
Bi-weekly 4,579.20 4,808.00 5,048.00 5,300.80 5,565.60 Monthly 9,921.60 10,417.33 10,937.33 11,485.07 12,058.80 Annual 119,059.20 125,008.00 131,248.00 137,820.80 144,705.60 Senior Engineer 46 Hourly 58.67 61.60 64.68 67.91 71.31 PT46 Bi-weekly 4,693.60 4,928.00 5,174.40 5,432.80 5,704.80 Monthly 10,169.47 10,677.33 11,211.20 11,771.07 12,360.40 Annual 122,033.60 128,128.00 134,534.40 141,252.80 148,324.80 Attachment 1.C
Council Agenda 10-6-2026 12.C-22
Packet Page 180
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
Finance Manager 47 Hourly 60.13 63.14 66.30 69.61 73.09 IT Manager Bi-weekly 4,810.40 5,051.20 5,304.00 5,568.80 5,847.20 Planning Manager Monthly 10,422.53 10,944.27 11,492.00 12,065.73 12,668.93 PT47 Annual 125,070.40 131,331.20 137,904.00 144,788.80 152,027.20 Police Sergeant SW 47 Hourly 61.32 64.39 67.61 70.99 74.54 PT-SW47 Bi-weekly 4,905.60 5,151.20 5,408.80 5,679.20 5,963.20 Monthly 10,628.80 11,160.93 11,719.07 12,304.93 12,920.27 Annual 127,545.60 133,931.20 140,628.80 147,659.20 155,043.20 Building Official 48 Hourly 61.64 64.72 67.96 71.35 74.92 Utilities Manager Bi-weekly 4,931.20 5,177.60 5,436.80 5,708.00 5,993.60 PT48 Monthly 10,684.27 11,218.13 11,779.73 12,367.33 12,986.13 Annual 128,211.20 134,617.60 141,356.80 148,408.00 155,833.60 Engineering Manager 49 Hourly 63.18 66.34 69.65 73.14 76.79 PT49 Bi-weekly 5,054.40 5,307.20 5,572.00 5,851.20 6,143.20 Monthly 10,951.20 11,498.93 12,072.67 12,677.60 13,310.27 Annual 131,414.40 137,987.20 144,872.00 152,131.20 159,723.20 PT50 50 Hourly 64.76 68.00 71.40 74.97 78.71
Bi-weekly 5,180.80 5,440.00 5,712.00 5,997.60 6,296.80 Monthly 11,225.07 11,786.67 12,376.00 12,994.80 13,643.07 Annual 134,700.80 141,440.00 148,512.00 155,937.60 163,716.80 PT51 51 Hourly 66.38 69.70 73.18 76.84 80.68
Bi-weekly 5,310.40 5,576.00 5,854.40 6,147.20 6,454.40 Monthly 11,505.87 12,081.33 12,684.53 13,318.93 13,984.53 Annual 138,070.40 144,976.00 152,214.40 159,827.20 167,814.40 PT52 52 Hourly 68.04 71.44 75.01 78.76 82.70
Bi-weekly 5,443.20 5,715.20 6,000.80 6,300.80 6,616.00 Monthly 11,793.60 12,382.93 13,001.73 13,651.73 14,334.67 Annual 141,523.20 148,595.20 156,020.80 163,820.80 172,016.00 City Engineer 53 Hourly 69.74 73.22 76.89 80.73 84.77
PT53 Bi-weekly 5,579.20 5,857.60 6,151.20 6,458.40 6,781.60 Monthly 12,088.27 12,691.47 13,327.60 13,993.20 14,693.47 Annual 145,059.20 152,297.60 159,931.20 167,918.40 176,321.60 PT54 54 Hourly 71.48 75.05 78.81 82.75 86.89
Bi-weekly 5,718.40 6,004.00 6,304.80 6,620.00 6,951.20 Monthly 12,389.87 13,008.67 13,660.40 14,343.33 15,060.93 Annual 148,678.40 156,104.00 163,924.80 172,120.00 180,731.20 Police Commander 55 Hourly 73.27 76.93 80.78 84.82 89.06 PT55 Bi-weekly 5,861.60 6,154.40 6,462.40 6,785.60 7,124.80 Monthly 12,700.13 13,334.53 14,001.87 14,702.13 15,437.07 Annual 152,401.60 160,014.40 168,022.40 176,425.60 185,244.80 PT56 56 Hourly 75.10 78.85 82.80 86.94 91.28
Bi-weekly 6,008.00 6,308.00 6,624.00 6,955.20 7,302.40 Monthly 13,017.33 13,667.33 14,352.00 15,069.60 15,821.87 Annual 156,208.00 164,008.00 172,224.00 180,835.20 189,862.40 Attachment 1.C
Council Agenda 10-6-2026 12.C-23
Packet Page 181
City of Pismo Beach Schedule B
Salary Table
5% between steps
Effective October 7, 2026
Assistant Public Works Director
(Temporary) 57 Hourly 76.98 80.83 84.87 89.11 93.57
PT57 Bi-weekly 6,158.40 6,466.40 6,789.60 7,128.80 7,485.60 Monthly 13,343.20 14,010.53 14,710.80 15,445.73 16,218.80 Annual 160,118.40 168,126.40 176,529.60 185,348.80 194,625.60 PT58 58 Hourly 78.90 82.85 86.99 91.34 95.90
Bi-weekly 6,312.00 6,628.00 6,959.20 7,307.20 7,672.00 Monthly 13,676.00 14,360.67 15,078.27 15,832.27 16,622.67 Annual 164,112.00 172,328.00 180,939.20 189,987.20 199,472.00 PT59 59 Hourly 80.87 84.92 89.16 93.62 98.30
Bi-weekly 6,469.60 6,793.60 7,132.80 7,489.60 7,864.00 Monthly 14,017.47 14,719.47 15,454.40 16,227.47 17,038.67 Annual 168,209.60 176,633.60 185,452.80 194,729.60 204,464.00 PT60 60 Hourly 82.90 87.04 91.39 95.96 100.76
Bi-weekly 6,632.00 6,963.20 7,311.20 7,676.80 8,060.80 Monthly 14,369.33 15,086.93 15,840.93 16,633.07 17,465.07 Annual 172,432.00 181,043.20 190,091.20 199,596.80 209,580.80 Community Development Director 61 Hourly 84.97 89.22 93.68 98.36 103.28 Administrative Services Director Bi-weekly 6,797.60 7,137.60 7,494.40 7,868.80 8,262.40 Management Services Director Monthly 14,728.13 15,464.80 16,237.87 17,049.07 17,901.87 Public Works Director Annual 176,737.60 185,577.60 194,854.40 204,588.80 214,822.40 Recreation and Tourism Director
PT61
PT62 62 Hourly 87.09 91.45 96.02 100.82 105.86
Bi-weekly 6,967.20 7,316.00 7,681.60 8,065.60 8,468.80 Monthly 15,095.60 15,851.33 16,643.47 17,475.47 18,349.07 Annual 181,147.20 190,216.00 199,721.60 209,705.60 220,188.80 PT63 63 Hourly 89.27 93.73 98.42 103.34 108.51
Bi-weekly 7,141.60 7,498.40 7,873.60 8,267.20 8,680.80 Monthly 15,473.47 16,246.53 17,059.47 17,912.27 18,808.40 Annual 185,681.60 194,958.40 204,713.60 214,947.20 225,700.80 Police Chief 64 Hourly 91.50 96.08 100.88 105.92 111.22 PT64 Bi-weekly 7,320.00 7,686.40 8,070.40 8,473.60 8,897.60 Monthly 15,860.00 16,653.87 17,485.87 18,359.47 19,278.13 Annual 190,320.00 199,846.40 209,830.40 220,313.60 231,337.60 Assistant City Manager 65 Hourly 93.79 98.48 103.40 108.57 114.00 PT65 Bi-weekly 7,503.20 7,878.40 8,272.00 8,685.60 9,120.00 Monthly 16,256.93 17,069.87 17,922.67 18,818.80 19,760.00 Annual 195,083.20 204,838.40 215,072.00 225,825.60 237,120.00 City Manager 74 Hourly 117.13 122.99 129.14 135.59 142.37 Bi-weekly 9,370.40 9,839.20 10,331.20 10,847.20 11,389.60 Monthly 20,302.53 21,318.27 22,384.27 23,502.27 24,677.47 Annual 243,630.40 255,819.20 268,611.20 282,027.20 296,129.60 Attachment 1.C
Council Agenda 10-6-2026 12.C-24
Packet Page 182
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
Classification Title Range #Period Step A Step B Step C Step D Step E PT1 1 Hourly 19.89 20.89 21.93 23.03 24.18 Bi-weekly 1,591.20 1,671.20 1,754.40 1,842.40 1,934.40 Monthly 3,447.60 3,620.93 3,801.20 3,991.87 4,191.20 Annual 41,371.20 43,451.20 45,614.40 47,902.40 50,294.40 PT2 2 Hourly 20.39 21.41 22.48 23.60 24.78 Bi-weekly 1,631.20 1,712.80 1,798.40 1,888.00 1,982.40 Monthly 3,534.27 3,711.07 3,896.53 4,090.67 4,295.20 Annual 42,411.20 44,532.80 46,758.40 49,088.00 51,542.40 PT3 3 Hourly 20.90 21.94 23.04 24.19 25.40 Bi-weekly 1,672.00 1,755.20 1,843.20 1,935.20 2,032.00 Monthly 3,622.67 3,802.93 3,993.60 4,192.93 4,402.67 Annual 43,472.00 45,635.20 47,923.20 50,315.20 52,832.00 PT4 4 Hourly 21.42 22.49 23.62 24.80 26.04 Bi-weekly 1,713.60 1,799.20 1,889.60 1,984.00 2,083.20 Monthly 3,712.80 3,898.27 4,094.13 4,298.67 4,513.60 Annual 44,553.60 46,779.20 49,129.60 51,584.00 54,163.20 PT5 5 Hourly 21.96 23.05 24.21 25.42 26.69 Bi-weekly 1,756.80 1,844.00 1,936.80 2,033.60 2,135.20 Monthly 3,806.40 3,995.33 4,196.40 4,406.13 4,626.27 Annual 45,676.80 47,944.00 50,356.80 52,873.60 55,515.20 PT6 6 Hourly 22.51 23.63 24.81 26.05 27.36 Bi-weekly 1,800.80 1,890.40 1,984.80 2,084.00 2,188.80 Monthly 3,901.73 4,095.87 4,300.40 4,515.33 4,742.40 Annual 46,820.80 49,150.40 51,604.80 54,184.00 56,908.80 Office Assistant I 7 Hourly 23.07 24.22 25.43 26.70 28.04 PT7 Bi-weekly 1,845.60 1,937.60 2,034.40 2,136.00 2,243.20 Monthly 3,998.80 4,198.13 4,407.87 4,628.00 4,860.27 Annual 47,985.60 50,377.60 52,894.40 55,536.00 58,323.20 PT8 8 Hourly 23.64 24.83 26.07 27.37 28.74 Bi-weekly 1,891.20 1,986.40 2,085.60 2,189.60 2,299.20 Monthly 4,097.60 4,303.87 4,518.80 4,744.13 4,981.60 Annual 49,171.20 51,646.40 54,225.60 56,929.60 59,779.20 PT9 9 Hourly 24.24 25.45 26.72 28.06 29.46 Bi-weekly 1,939.20 2,036.00 2,137.60 2,244.80 2,356.80 Monthly 4,201.60 4,411.33 4,631.47 4,863.73 5,106.40 Annual 50,419.20 52,936.00 55,577.60 58,364.80 61,276.80 PT10 10 Hourly 24.84 26.08 27.39 28.76 30.19 Bi-weekly 1,987.20 2,086.40 2,191.20 2,300.80 2,415.20 Monthly 4,305.60 4,520.53 4,747.60 4,985.07 5,232.93 Annual 51,667.20 54,246.40 56,971.20 59,820.80 62,795.20 Office Assistant II 11 Hourly 25.46 26.74 28.07 29.48 30.95 PT11 Bi-weekly 2,036.80 2,139.20 2,245.60 2,358.40 2,476.00 Monthly 4,413.07 4,634.93 4,865.47 5,109.87 5,364.67 Annual 52,956.80 55,619.20 58,385.60 61,318.40 64,376.00 Attachment 1.C
Council Agenda 10-6-2026 12.C-25
Packet Page 183
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
PT12 12 Hourly 26.10 27.40 28.77 30.21 31.72
Bi-weekly 2,088.00 2,192.00 2,301.60 2,416.80 2,537.60 Monthly 4,524.00 4,749.33 4,986.80 5,236.40 5,498.13 Annual 54,288.00 56,992.00 59,841.60 62,836.80 65,977.60 Maintenance Worker I 13 Hourly 26.75 28.09 29.49 30.97 32.52 PT13 Bi-weekly 2,140.00 2,247.20 2,359.20 2,477.60 2,601.60 Monthly 4,636.67 4,868.93 5,111.60 5,368.13 5,636.80 Annual 55,640.00 58,427.20 61,339.20 64,417.60 67,641.60 Fleet Mechanic I 14 Hourly 27.42 28.79 30.23 31.74 33.33 PT14 Bi-weekly 2,193.60 2,303.20 2,418.40 2,539.20 2,666.40 Monthly 4,752.80 4,990.27 5,239.87 5,501.60 5,777.20 Annual 57,033.60 59,883.20 62,878.40 66,019.20 69,326.40 Administrative Assistant 15 Hourly 28.11 29.51 30.99 32.54 34.16 PT15 Bi-weekly 2,248.80 2,360.80 2,479.20 2,603.20 2,732.80 Monthly 4,872.40 5,115.07 5,371.60 5,640.27 5,921.07 Annual 58,468.80 61,380.80 64,459.20 67,683.20 71,052.80 Parking Enforcement Technician 16 Hourly 28.81 30.25 31.76 33.35 35.02 PT16 Bi-weekly 2,304.80 2,420.00 2,540.80 2,668.00 2,801.60 Monthly 4,993.73 5,243.33 5,505.07 5,780.67 6,070.13 Annual 59,924.80 62,920.00 66,060.80 69,368.00 72,841.60 Accounting Clerk 17 Hourly 29.53 31.01 32.56 34.18 35.89 PT17 Bi-weekly 2,362.40 2,480.80 2,604.80 2,734.40 2,871.20 Monthly 5,118.53 5,375.07 5,643.73 5,924.53 6,220.93 Annual 61,422.40 64,500.80 67,724.80 71,094.40 74,651.20 Water Systems Operator I 18 Hourly 30.27 31.78 33.37 35.04 36.79 PT18 Bi-weekly 2,421.60 2,542.40 2,669.60 2,803.20 2,943.20 Monthly 5,246.80 5,508.53 5,784.13 6,073.60 6,376.93 Annual 62,961.60 66,102.40 69,409.60 72,883.20 76,523.20 Police Records Technician 19 Hourly 31.02 32.57 34.20 35.91 37.71 Wastewater Operator I Bi-weekly 2,481.60 2,605.60 2,736.00 2,872.80 3,016.80 PT19 Monthly 5,376.80 5,645.47 5,928.00 6,224.40 6,536.40 Annual 64,521.60 67,745.60 71,136.00 74,692.80 78,436.80 Community Services Technician NS 19 Hourly 32.26 33.87 35.57 37.35 39.21 PT-NS19 Bi-weekly 2,580.80 2,709.60 2,845.60 2,988.00 3,136.80 Monthly 5,591.73 5,870.80 6,165.47 6,474.00 6,796.40 Annual 67,100.80 70,449.60 73,985.60 77,688.00 81,556.80 Recreation Coordinator 20 Hourly 31.80 33.39 35.06 36.81 38.65 PT20 Bi-weekly 2,544.00 2,671.20 2,804.80 2,944.80 3,092.00 Monthly 5,512.00 5,787.60 6,077.07 6,380.40 6,699.33 Annual 66,144.00 69,451.20 72,924.80 76,564.80 80,392.00 Accounting Technician 21 Hourly 32.59 34.22 35.93 37.73 39.62 Senior Administrative Assistant Bi-weekly 2,607.20 2,737.60 2,874.40 3,018.40 3,169.60 Permit Technician Monthly 5,648.93 5,931.47 6,227.87 6,539.87 6,867.47 Maintenance Worker II Annual 67,787.20 71,177.60 74,734.40 78,478.40 82,409.60 PT21
Attachment 1.C
Council Agenda 10-6-2026 12.C-26
Packet Page 184
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
PT22 22 Hourly 33.41 35.08 36.83 38.67 40.61
Bi-weekly 2,672.80 2,806.40 2,946.40 3,093.60 3,248.80 Monthly 5,791.07 6,080.53 6,383.87 6,702.80 7,039.07 Annual 69,492.80 72,966.40 76,606.40 80,433.60 84,468.80 Code Compliance Inspector 23 Hourly 34.24 35.96 37.75 39.64 41.62 Senior Police Records Technician Bi-weekly 2,739.20 2,876.80 3,020.00 3,171.20 3,329.60 Water Systems Operator II Monthly 5,934.93 6,233.07 6,543.33 6,870.93 7,214.13 PT23 Annual 71,219.20 74,796.80 78,520.00 82,451.20 86,569.60 Property and Evidence Technician NS 23 Hourly 35.61 37.39 39.26 41.22 43.28 PT-NS23 Bi-weekly 2,848.80 2,991.20 3,140.80 3,297.60 3,462.40 Monthly 6,172.40 6,480.93 6,805.07 7,144.80 7,501.87 Annual 74,068.80 77,771.20 81,660.80 85,737.60 90,022.40 Engineering Technician 24 Hourly 35.10 36.86 38.70 40.63 42.66 Executive Assistant Bi-weekly 2,808.00 2,948.80 3,096.00 3,250.40 3,412.80 Executive Assistant to the City Manager Monthly 6,084.00 6,389.07 6,708.00 7,042.53 7,394.40 Fleet Mechanic II Annual 73,008.00 76,668.80 80,496.00 84,510.40 88,732.80 Lead Maintenance Worker
Tourism Coordinator
PT24
Wastewater Operator II 25 Hourly 35.98 37.78 39.67 41.65 43.73 PT25 Bi-weekly 2,878.40 3,022.40 3,173.60 3,332.00 3,498.40 Monthly 6,236.53 6,548.53 6,876.13 7,219.33 7,579.87 Annual 74,838.40 78,582.40 82,513.60 86,632.00 90,958.40 Public Safety Dispatcher NS 25 Hourly 37.41 39.28 41.25 43.31 45.48 PT-NS25 Bi-weekly 2,992.80 3,142.40 3,300.00 3,464.80 3,638.40 Monthly 6,484.40 6,808.53 7,150.00 7,507.07 7,883.20 Annual 77,812.80 81,702.40 85,800.00 90,084.80 94,598.40 Building Inspector I 26 Hourly 36.88 38.72 40.66 42.69 44.82 Crime Analyst Bi-weekly 2,950.40 3,097.60 3,252.80 3,415.20 3,585.60 PT26 Monthly 6,392.53 6,711.47 7,047.73 7,399.60 7,768.80 Annual 76,710.40 80,537.60 84,572.80 88,795.20 93,225.60 IT Specialist 27 Hourly 37.80 39.69 41.67 43.76 45.95
Lead Water Systems Operator Bi-weekly 3,024.00 3,175.20 3,333.60 3,500.80 3,676.00 PT27 Monthly 6,552.00 6,879.60 7,222.80 7,585.07 7,964.67 Annual 78,624.00 82,555.20 86,673.60 91,020.80 95,576.00 Recreation Supervisor 28 Hourly 38.74 40.68 42.72 44.85 47.09 Facility and Fleet Supervisor Bi-weekly 3,099.20 3,254.40 3,417.60 3,588.00 3,767.20 Parks Maintenance Supervisor Monthly 6,714.93 7,051.20 7,404.80 7,774.00 8,162.27 Streets Maintenance Supervisor Annual 80,579.20 84,614.40 88,857.60 93,288.00 97,947.20 PT28
Assistant Planner 29 Hourly 39.71 41.70 43.78 45.97 48.27 Lead Wastewater Operator Bi-weekly 3,176.80 3,336.00 3,502.40 3,677.60 3,861.60 Regulatory Compliance Coordinator Monthly 6,883.07 7,228.00 7,588.53 7,968.13 8,366.80 PT29 Annual 82,596.80 86,736.00 91,062.40 95,617.60 100,401.60 Attachment 1.C
Council Agenda 10-6-2026 12.C-27
Packet Page 185
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
Senior Public Safety Dispatcher NS 29 Hourly 41.30 43.36 45.53 47.81 50.20 PT-NS29 Bi-weekly 3,304.00 3,468.80 3,642.40 3,824.80 4,016.00 Monthly 7,158.67 7,515.73 7,891.87 8,287.07 8,701.33 Annual 85,904.00 90,188.80 94,702.40 99,444.80 104,416.00 Building Inspector II 30 Hourly 40.71 42.74 44.88 47.12 49.48 Parking Operations Supervisor Bi-weekly 3,256.80 3,419.20 3,590.40 3,769.60 3,958.40 PT30 Monthly 7,056.40 7,408.27 7,779.20 8,167.47 8,576.53 Annual 84,676.80 88,899.20 93,350.40 98,009.60 102,918.40 Accountant 31 Hourly 41.72 43.81 46.00 48.30 50.71 Assistant Engineer Bi-weekly 3,337.60 3,504.80 3,680.00 3,864.00 4,056.80 Management Analyst Monthly 7,231.47 7,593.73 7,973.33 8,372.00 8,789.73 Tourism Manager Annual 86,777.60 91,124.80 95,680.00 100,464.00 105,476.80 Water Systems Supervisor
PT31
Associate Planner 32 Hourly 42.77 44.90 47.15 49.51 51.98 PT32 Bi-weekly 3,421.60 3,592.00 3,772.00 3,960.80 4,158.40 Monthly 7,413.47 7,782.67 8,172.67 8,581.73 9,009.87 Annual 88,961.60 93,392.00 98,072.00 102,980.80 108,118.40 Police Support Services Supervisor NS 32 Hourly 44.47 46.70 49.03 51.48 54.06 PT-NS32 Bi-weekly 3,557.60 3,736.00 3,922.40 4,118.40 4,324.80 Monthly 7,708.13 8,094.67 8,498.53 8,923.20 9,370.40 Annual 92,497.60 97,136.00 101,982.40 107,078.40 112,444.80 Building Inspector/Plans Examiner 33 Hourly 43.84 46.03 48.33 50.74 53.28 Wastewater Systems Supervisor Bi-weekly 3,507.20 3,682.40 3,866.40 4,059.20 4,262.40 PT33 Monthly 7,598.93 7,978.53 8,377.20 8,794.93 9,235.20 Annual 91,187.20 95,742.40 100,526.40 105,539.20 110,822.40 Senior Management Analyst 34 Hourly 44.93 47.18 49.54 52.01 54.61 Senior Accountant Bi-weekly 3,594.40 3,774.40 3,963.20 4,160.80 4,368.80 GIS Analyst Monthly 7,787.87 8,177.87 8,586.93 9,015.07 9,465.73 PT34 Annual 93,454.40 98,134.40 103,043.20 108,180.80 113,588.80 PT35 35 Hourly 46.05 48.36 50.78 53.31 55.98 Bi-weekly 3,684.00 3,868.80 4,062.40 4,264.80 4,478.40 Monthly 7,982.00 8,382.40 8,801.87 9,240.40 9,703.20 Annual 95,784.00 100,588.80 105,622.40 110,884.80 116,438.40 Finance Supervisor 36 Hourly 47.21 49.57 52.04 54.65 57.38 PT36 Bi-weekly 3,776.80 3,965.60 4,163.20 4,372.00 4,590.40 Monthly 8,183.07 8,592.13 9,020.27 9,472.67 9,945.87 Annual 98,196.80 103,105.60 108,243.20 113,672.00 119,350.40 Police Officer SW 36 Hourly 48.14 50.55 53.07 55.73 58.51 PT-SW36 Bi-weekly 3,851.20 4,044.00 4,245.60 4,458.40 4,680.80 Monthly 8,344.27 8,762.00 9,198.80 9,659.87 10,141.73 Annual 100,131.20 105,144.00 110,385.60 115,918.40 121,700.80 Attachment 1.C
Council Agenda 10-6-2026 12.C-28
Packet Page 186
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
Senior Planner 37 Hourly 48.39 50.81 53.35 56.01 58.81
PT37 Bi-weekly 3,871.20 4,064.80 4,268.00 4,480.80 4,704.80 Monthly 8,387.60 8,807.07 9,247.33 9,708.40 10,193.73 Annual 100,651.20 105,684.80 110,968.00 116,500.80 122,324.80 Capital Projects Manager 38 Hourly 49.60 52.08 54.68 57.41 60.28 PT38 Bi-weekly 3,968.00 4,166.40 4,374.40 4,592.80 4,822.40 Monthly 8,597.33 9,027.20 9,477.87 9,951.07 10,448.53 Annual 103,168.00 108,326.40 113,734.40 119,412.80 125,382.40 PT39 39 Hourly 50.84 53.38 56.05 58.85 61.79
Bi-weekly 4,067.20 4,270.40 4,484.00 4,708.00 4,943.20 Monthly 8,812.27 9,252.53 9,715.33 10,200.67 10,710.27 Annual 105,747.20 111,030.40 116,584.00 122,408.00 128,523.20 Public Works Operations Manager 40 Hourly 52.11 54.71 57.45 60.32 63.34 PT40 Bi-weekly 4,168.80 4,376.80 4,596.00 4,825.60 5,067.20 Monthly 9,032.40 9,483.07 9,958.00 10,455.47 10,978.93 Annual 108,388.80 113,796.80 119,496.00 125,465.60 131,747.20 Police Corporal SW 40 Hourly 53.14 55.79 58.58 61.51 64.59 PT-SW40 Bi-weekly 4,251.20 4,463.20 4,686.40 4,920.80 5,167.20 Monthly 9,210.93 9,670.27 10,153.87 10,661.73 11,195.60 Annual 110,531.20 116,043.20 121,846.40 127,940.80 134,347.20 PT41 41 Hourly 53.41 56.08 58.88 61.83 64.92
Bi-weekly 4,272.80 4,486.40 4,710.40 4,946.40 5,193.60 Monthly 9,257.73 9,720.53 10,205.87 10,717.20 11,252.80 Annual 111,092.80 116,646.40 122,470.40 128,606.40 135,033.60 Engineer 42 Hourly 54.74 57.48 60.36 63.37 66.54
Recreation Manager Bi-weekly 4,379.20 4,598.40 4,828.80 5,069.60 5,323.20 PT42 Monthly 9,488.27 9,963.20 10,462.40 10,984.13 11,533.60 Annual 113,859.20 119,558.40 125,548.80 131,809.60 138,403.20 City Clerk 43 Hourly 56.11 58.92 61.86 64.96 68.21
PT43 Bi-weekly 4,488.80 4,713.60 4,948.80 5,196.80 5,456.80 Monthly 9,725.73 10,212.80 10,722.40 11,259.73 11,823.07 Annual 116,708.80 122,553.60 128,668.80 135,116.80 141,876.80 Human Resources Officer 44 Hourly 57.52 60.39 63.41 66.58 69.91 PT44 Bi-weekly 4,601.60 4,831.20 5,072.80 5,326.40 5,592.80 Monthly 9,970.13 10,467.60 10,991.07 11,540.53 12,117.73 Annual 119,641.60 125,611.20 131,892.80 138,486.40 145,412.80 PT45 45 Hourly 58.95 61.90 65.00 68.25 71.66
Bi-weekly 4,716.00 4,952.00 5,200.00 5,460.00 5,732.80 Monthly 10,218.00 10,729.33 11,266.67 11,830.00 12,421.07 Annual 122,616.00 128,752.00 135,200.00 141,960.00 149,052.80 Senior Engineer 46 Hourly 60.43 63.45 66.62 69.95 73.45 PT46 Bi-weekly 4,834.40 5,076.00 5,329.60 5,596.00 5,876.00 Monthly 10,474.53 10,998.00 11,547.47 12,124.67 12,731.33 Annual 125,694.40 131,976.00 138,569.60 145,496.00 152,776.00 Attachment 1.C
Council Agenda 10-6-2026 12.C-29
Packet Page 187
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
Finance Manager 47 Hourly 61.94 65.04 68.29 71.70 75.29 IT Manager Bi-weekly 4,955.20 5,203.20 5,463.20 5,736.00 6,023.20 Planning Manager Monthly 10,736.27 11,273.60 11,836.93 12,428.00 13,050.27 PT47 Annual 128,835.20 135,283.20 142,043.20 149,136.00 156,603.20 Police Sergeant SW 47 Hourly 63.16 66.32 69.64 73.12 76.78 PT-SW47 Bi-weekly 5,052.80 5,305.60 5,571.20 5,849.60 6,142.40 Monthly 10,947.73 11,495.47 12,070.93 12,674.13 13,308.53 Annual 131,372.80 137,945.60 144,851.20 152,089.60 159,702.40 Building Official 48 Hourly 63.49 66.66 69.99 73.49 77.17 Utilities Manager Bi-weekly 5,079.20 5,332.80 5,599.20 5,879.20 6,173.60 PT48 Monthly 11,004.93 11,554.40 12,131.60 12,738.27 13,376.13 Annual 132,059.20 138,652.80 145,579.20 152,859.20 160,513.60 Engineering Manager 49 Hourly 65.07 68.33 71.74 75.33 79.10 PT49 Bi-weekly 5,205.60 5,466.40 5,739.20 6,026.40 6,328.00 Monthly 11,278.80 11,843.87 12,434.93 13,057.20 13,710.67 Annual 135,345.60 142,126.40 149,219.20 156,686.40 164,528.00 PT50 50 Hourly 66.70 70.04 73.54 77.21 81.08 Bi-weekly 5,336.00 5,603.20 5,883.20 6,176.80 6,486.40 Monthly 11,561.33 12,140.27 12,746.93 13,383.07 14,053.87 Annual 138,736.00 145,683.20 152,963.20 160,596.80 168,646.40 PT51 51 Hourly 68.37 71.79 75.38 79.14 83.10 Bi-weekly 5,469.60 5,743.20 6,030.40 6,331.20 6,648.00 Monthly 11,850.80 12,443.60 13,065.87 13,717.60 14,404.00 Annual 142,209.60 149,323.20 156,790.40 164,611.20 172,848.00 PT52 52 Hourly 70.08 73.58 77.26 81.12 85.18 Bi-weekly 5,606.40 5,886.40 6,180.80 6,489.60 6,814.40 Monthly 12,147.20 12,753.87 13,391.73 14,060.80 14,764.53 Annual 145,766.40 153,046.40 160,700.80 168,729.60 177,174.40 City Engineer 53 Hourly 71.83 75.42 79.19 83.15 87.31 PT53 Bi-weekly 5,746.40 6,033.60 6,335.20 6,652.00 6,984.80 Monthly 12,450.53 13,072.80 13,726.27 14,412.67 15,133.73 Annual 149,406.40 156,873.60 164,715.20 172,952.00 181,604.80 PT54 54 Hourly 73.63 77.31 81.17 85.23 89.49 Bi-weekly 5,890.40 6,184.80 6,493.60 6,818.40 7,159.20 Monthly 12,762.53 13,400.40 14,069.47 14,773.20 15,511.60 Annual 153,150.40 160,804.80 168,833.60 177,278.40 186,139.20 Police Commander 55 Hourly 75.47 79.24 83.20 87.36 91.73 PT55 Bi-weekly 6,037.60 6,339.20 6,656.00 6,988.80 7,338.40 Monthly 13,081.47 13,734.93 14,421.33 15,142.40 15,899.87 Annual 156,977.60 164,819.20 173,056.00 181,708.80 190,798.40 PT56 56 Hourly 77.35 81.22 85.28 89.54 94.02 Bi-weekly 6,188.00 6,497.60 6,822.40 7,163.20 7,521.60 Monthly 13,407.33 14,078.13 14,781.87 15,520.27 16,296.80 Annual 160,888.00 168,937.60 177,382.40 186,243.20 195,561.60 Attachment 1.C
Council Agenda 10-6-2026 12.C-30
Packet Page 188
City of Pismo Beach Schedule C
Salary Table
5% between steps
Effective 1st Full Pay Period in July 2027
Assistant Public Works Director
(Temporary) 57 Hourly 79.29 83.25 87.41 91.78 96.37
PT57 Bi-weekly 6,343.20 6,660.00 6,992.80 7,342.40 7,709.60 Monthly 13,743.60 14,430.00 15,151.07 15,908.53 16,704.13 Annual 164,923.20 173,160.00 181,812.80 190,902.40 200,449.60 PT58 58 Hourly 81.27 85.33 89.60 94.08 98.78
Bi-weekly 6,501.60 6,826.40 7,168.00 7,526.40 7,902.40 Monthly 14,086.80 14,790.53 15,530.67 16,307.20 17,121.87 Annual 169,041.60 177,486.40 186,368.00 195,686.40 205,462.40 PT59 59 Hourly 83.30 87.46 91.84 96.43 101.25
Bi-weekly 6,664.00 6,996.80 7,347.20 7,714.40 8,100.00 Monthly 14,438.67 15,159.73 15,918.93 16,714.53 17,550.00 Annual 173,264.00 181,916.80 191,027.20 200,574.40 210,600.00 PT60 60 Hourly 85.38 89.65 94.13 98.84 103.78
Bi-weekly 6,830.40 7,172.00 7,530.40 7,907.20 8,302.40 Monthly 14,799.20 15,539.33 16,315.87 17,132.27 17,988.53 Annual 177,590.40 186,472.00 195,790.40 205,587.20 215,862.40 Community Development Director 61 Hourly 87.52 91.89 96.49 101.31 106.38 Administrative Services Director Bi-weekly 7,001.60 7,351.20 7,719.20 8,104.80 8,510.40 Management Services Director Monthly 15,170.13 15,927.60 16,724.93 17,560.40 18,439.20 Public Works Director Annual 182,041.60 191,131.20 200,699.20 210,724.80 221,270.40 Recreation and Tourism Director
PT61
PT62 62 Hourly 89.70 94.19 98.90 103.84 109.04
Bi-weekly 7,176.00 7,535.20 7,912.00 8,307.20 8,723.20 Monthly 15,548.00 16,326.27 17,142.67 17,998.93 18,900.27 Annual 186,576.00 195,915.20 205,712.00 215,987.20 226,803.20 PT63 63 Hourly 91.95 96.54 101.37 106.44 111.76
Bi-weekly 7,356.00 7,723.20 8,109.60 8,515.20 8,940.80 Monthly 15,938.00 16,733.60 17,570.80 18,449.60 19,371.73 Annual 191,256.00 200,803.20 210,849.60 221,395.20 232,460.80 Police Chief 64 Hourly 94.25 98.96 103.91 109.10 114.56 PT64 Bi-weekly 7,540.00 7,916.80 8,312.80 8,728.00 9,164.80 Monthly 16,336.67 17,153.07 18,011.07 18,910.67 19,857.07 Annual 196,040.00 205,836.80 216,132.80 226,928.00 238,284.80 Assistant City Manager 65 Hourly 96.60 101.43 106.50 111.83 117.42 PT65 Bi-weekly 7,728.00 8,114.40 8,520.00 8,946.40 9,393.60 Monthly 16,744.00 17,581.20 18,460.00 19,383.87 20,352.80 Annual 200,928.00 210,974.40 221,520.00 232,606.40 244,233.60 City Manager 74 Hourly 120.64 126.68 133.01 139.66 146.64 Bi-weekly 9,651.20 10,134.40 10,640.80 11,172.80 11,731.20 Monthly 20,910.93 21,957.87 23,055.07 24,207.73 25,417.60 Annual 250,931.20 263,494.40 276,660.80 290,492.80 305,011.20 Attachment 1.C
Council Agenda 10-6-2026 12.C-31
Packet Page 189
SIDE LETTER AGREEMENT BETWEEN
THE CITY OF PISMO BEACH,
CALIFORNIA
(HEREINAFTER CALLED “CITY”)
AND
FULL-TIME NON-REPRESENTED EMPLOYEES
(HEREINAFTER CALLED “FT NON-REP”)
WHEREAS, the City and FT Non-Rep have an existing Resolution from July 1, 2025, through June 30, 2028; and
WHEREAS, the City recommends amending the FT Non-Rep Resolution to reflect the creation of a new at- will, temporary mid-management position classification, Assistant Public Works Director (Temporary), and to update the title of an existing position classification; and WHEREAS, the City further recommends amending the FT Non-Rep Resolution to establish Project Incentive Pay for eligible project-based assignments, as provided herein; and WHEREAS, if adopted by the City Council, these changes shall become effective October 7, 2026; and NOW, THEREFORE, BE IT RESOLVED City hereby agrees to modify the following sections of the Full-Time Non-Represented Resolution (FT Non-Rep).
[the following paragraphs to be added as amended]
SECTION 1. AFFECTED EMPLOYEES
The wages and benefits set forth herein are to be provided to those full-time employees whose positions are not represented by an employee organization recognized pursuant to Section 9(A) of City of Pismo Beach Resolution No. 1367 (the Employer-Employee Relations Resolution of the City of Pismo Beach). The job classes subject to the provisions of this resolution are set forth as follows:
1.B. Mid-Management/Professional
These job classes are responsible for middle management tasks and/or perform more complex technical or professional tasks. Those with mid-management responsibilities oversee a major division or program area within a department. Employees are exempt from overtime pay requirements of the Fair Labor Standards Act. Unless employed on a less-than full-time basis, employees are part of the Competitive Service and have the full protection of the City’s Personnel Rules and Regulations. Job Classifications in this group include:
•Assistant Engineer
•Assistant Public Works Director - Temporary
•Associate Planner
•Building Official
•Capital Projects Manager
•City Clerk
Attachment 1.D
Council Agenda 10-6-2026 12.C-32
Packet Page 190
•City Engineer
•Crime Analyst
•Engineer
•Finance Manager
•Finance Supervisor
•GIS Analyst
•Human Resources Officer
•IT Manager
•Management Analyst
•Senior Management Analyst
•Planning Manager
•Police Commander
•Public Works Operations Manager
•Recreation Manager
•Senior Civil Engineer
•Senior Planner
•Tourism Coordinator
•Tourism Manager
•Utilities Manager
1.B. Management Employees
These employees are responsible for management of operations and personnel of a City department(s).
Employees in this group are exempt from overtime pay requirements of the Fair Labor Standards Act and are excluded from the competitive service as defined in Section 2.40.020 of the City of Pismo Beach Municipal Code. Job Classifications in this group include:
•Administrative Services Director
•Assistant City Manager
•City Manager
•Community Development Director
•Management Services Director
•Police Chief
•Public Works Director
•Recreation and Tourism Director
•Tourism and Events Director
SECTION 12. POST EDUCATIONAL INCENTIVE PROGRAM
12.A. Purpose
The purpose of the educational incentive program is to motivate employees to achieve higher educational and professional law enforcement-related standards and enhance career development.
Additionally, this program is predicated upon a combination of appropriate educational training and experience as established by standards set forth by Peace Officer Standards and Training (POST).
12.B. POST Management Certification Compensation
Mid-Management/Professional and Management Safety personnel who possess a POST Management Certificate shall receive four hundred dollars ($400) compensation per month above their base salary.
The full monthly amount shall be distributed in equal payments of $184.62 per pay period as earned.
Attachment 1.D
Council Agenda 10-6-2026 12.C-33
Packet Page 191
12.C. Project Incentive Compensation
Mid-Management/Professional and Management personnel assigned to a special project, as directed by the City Manager, in writing, shall receive additional compensation up to five percent (5%) above their base salary for the duration of the assignment. The City Manager may modify, suspend, or discontinue the project incentive compensation prospectively based on the needs of the City. Compensation earned prior to the effective date of such action shall be paid.
This Side Letter Agreement identifies those articles, sections, and subsections of the Full-Time Resolution between the City and the FT Non-Rep. All other terms of the Resolution remain in full force and effect.
CITY OF PISMO BEACH Representative
_______________________________
Date: ___________
Attachment 1.D
Council Agenda 10-6-2026 12.C-34
Packet Page 192