__. Pre-Construction Conference. City will designate a date and time for a pre- construction conference with Contractor following Contract execution. Project administration procedures and coordination between City and Contractor will be discussed, and Contractor must present City with the following information or documents at the meeting for City’s review and acceptance before the Work commences:
__.1 Name, 24-hour contact information, and qualifications of the proposed on-site superintendent;
__.2 List of all key Project personnel and their complete contact information, including email addresses and telephone numbers during regular hours and after hours;
__.3 Staging plans that identify the sequence of the Work, including any phases and alternative sequences or phases, with the goal of minimizing the impacts on residents, businesses and other operations in the Project vicinity;
__.4 If required, traffic control plans associated with the staging plans that are signed and stamped by a licensed traffic engineer;
__.5 Draft baseline schedule for the Work as required under Section 5.2, to be finalized within ten days after City issues the Notice to Proceed;
__.6 Breakdown of lump sum bid items, to be used for determining the value of Work completed for future progress payments to Contractor;
__.7 Schedule with list of Project submittals that require City review, and list of the proposed material suppliers;
__.8 Plan for coordination with affected utility owner(s) and compliance with any related permit requirements;
__.9 Videotape and photographs recording the conditions throughout the pre- construction Project site, showing the existing improvements and current condition of the curbs, gutters, sidewalks, signs, landscaping, streetlights, structures near the Project such as building faces, canopies, shades and fences, and any other features within the Project area limits;
__.10 If requested by City, Contractor’s cash flow projections; and
__.11 Any other documents specified in the Special Conditions or Notice of Potential Award.
198
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 87
This optional provision is intended for modifying the default insurance requirements under Section 4.3 of the General Conditions by modifying the CGL limits, waiving the pollution liability insurance, and/or waiving the builder’s risk, as indicated in the separate sub-provisions.
__. Insurance Requirements. The insurance requirements under Section 4.3 of the General Conditions are modified for this Contract, as set forth below. Except as expressly stated below, all other provisions in Section 4.3 are unchanged and remain in full force and effect.
The following optional sub-provision may be used to adjust the default insurance limits for CGL coverage in Section 4.3 of the General Conditions, subject to prior consultation with and direction from the City’s Risk Manager.
__.__ Commercial General Liability (“CGL”) Insurance. The CGL insurance policy limits set forth in subsection 4.3(A)(1) of the General Conditions are modified for this Contract to require at least $<______________> per occurrence and at least $<________________> general aggregate.
The following optional sub-provision may be used if pollution liability insurance is not necessary for the project. Consult with the City’s Risk Manager to confirm whether pollution liability insurance is needed for a project.
__.__ Pollution Liability Insurance Waived. The pollution liability insurance policy requirement set forth in subsection 4.3(A)(4) of the General Conditions is hereby waived and does not apply to this Contract.
The following optional sub-provision should only be used if builder’s risk insurance is not applicable, such as for horizontal projects. Consult with the City’s Risk Manager to confirm whether builder’s risk insurance is required for a project.
__.__ Builders Risk Insurance Waived. The builder’s risk insurance policy requirement set forth in subsection 4.3(A)(5) of the General Conditions is hereby waived and does not apply to this Contract.
The following provision may be most useful for longer projects which may extend into the rainy season. As stated, it is intended to supplement Sections 5.2 and
5.3 of the General Conditions. Using reliable data for the Project location, based on normal rainfall patterns over an extended period, e.g., 5-10 years, complete as indicated.
__. Normal Weather Delay Days. This provision is intended to supplement the requirements of General Conditions Section 5.2 on Schedule Requirements and Section 5.3 on Delays and Extensions of Contract Time. Based on historic records for the Project location, Contractor’s schedule should assume the following number of normal Weather Delay Days for each month:
Month # Normal Weather
Delay Days
January __
199
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 88
February __
March __
April __
May __
June __
July __
August __
September __
October __
November __
December __
Weather Delay Days which do not occur during a given month based on the number of days allocated for that month (above) do not carry over to another month.
The following provision may be used when the Project is to be coordinated by a Construction Manager. The language should be tailored to align with the contract between the City and the Construction Manager, and also to reflect Project- specific procedures and requirements.
__. Construction Manager Role and Authority. <___________________> is the Construction Manager for this Project. The Construction Manager will assist City in the management of the construction of the Project. The Construction Manager may perform services in the areas of supervision and coordination of the work of Contractor and/or other contractors, scheduling the Work, monitoring the progress of the Work, providing City with evaluations and recommendations concerning the quality of the Work, recommending the approval of progress payments to Contractor, or other services for the Project in accordance with the Construction Manager’s contract with City.
__.1 Communications. Contractor must submit all notices and communications relating to the Work directly to the Construction Manager in writing, as follows:
<insert contact information>
With a copy to the Engineer:
<insert contact information>
__.2 On-Site Management and Communication Procedures. The Construction Manager will provide and maintain a management team on the Project site to provide contract administration as an agent of City, and will establish and implement coordination and communication procedures among City, the Design Professional, Contractor, and others.
__.3 Contract Administration Procedures. The Construction Manager will establish and implement procedures for reviewing and processing requests for clarifications and interpretations of the Contract Documents, Shop Drawings, samples, other submittals, schedule adjustments, Change Order proposals, written proposals for substitutions, payment applications, and maintenance of logs.
200
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 89
__.4 Pre-Construction Conference. Contractor will attend the pre-construction conference, during which the Construction Manager will review the Contract administration procedures and Project requirements.
__.5 Contractor’s Construction Schedule. The Construction Manager will review Contractor’s construction schedules and will verify that each schedule is prepared in accordance with the requirements of the Contract Documents.
The following should be used for federally funded projects, as applicable. It contains those provisions required under Appendix II to Part 200 of Title 2 of the Code of Federal Regulations (as of 11/10/20) which are not already addressed elsewhere in the Contract Documents. Specific federal funding requirements may vary between federal agencies and may be revised from time to time. These provisions should be used as needed to comply with applicable federal funding requirements. Delete provisions that are not applicable. Consult the funding agency representative for further information and direction.
__. Federally Funded Projects. This Project is funded in whole or in part by federal funds and subject to the following federal requirements under the terms of the funding agreement(s) between City and the federal agency or agencies providing federal funds, which are fully incorporated by this reference and made part of the Contract Documents. Copies of any funding agreement between City and a funding agency will be made available upon request. __.__ Equal Opportunity. During the performance of this Contract, the Contractor agrees as follows:
(A) The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action will include, but not be limited to the following: Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
(B) The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin. (C) The Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision will not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee’s essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in 201
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 90
furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with the Contractor’s legal duty to furnish information.
(D) The Contractor will send to each labor union or representative of workers with which it has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the labor union or workers’ representatives of the Contractor’s commitments under this section, and will post copies of the notice in conspicuous places available to employees and applicants for employment.
(E) The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the United States Secretary of Labor.
(F) The Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the United States Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the United States Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders. (G) In the event of the Contractor’s noncompliance with the nondiscrimination clauses of this contract or with any of the rules, regulations, or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further federal government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the United States Secretary of Labor, or as otherwise provided by law. (H) The Contractor will include the portion of the sentence immediately preceding paragraph (A) and the provisions of paragraphs (A) through (H) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the United States Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each Subcontractor or vendor. The Contractor will take such action with respect to any subcontract or purchase order as the City or funding agency may direct as a means of enforcing such provisions, including sanctions for noncompliance: Provided, however, that in the event a Contractor becomes involved in, or is threatened with, litigation with a Subcontractor or vendor as a result of such direction by the City or funding agency, the Contractor may request the United States to enter into such litigation to protect the interests of the United States.
__.__ Davis-Bacon Act. Contractor will pay wages to laborers and mechanics, not less than once a week, and at a rate not less than the current federal prevailing wages specified in the Davis-Bacon Act Wage Determination attached hereto and incorporated herein. By entering into this Contract, Contractor accepts the attached Wage Determination. <The current Davis-Bacon Act Wage Determination, which may be accessed at https://www.wdol.gov/dba.aspx must be printed and included with the Contract Documents.>
202
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 91
__.__ Copeland “Anti-Kickback” Act. Contractor will comply with 18 U.S.C. § 874, 40 U.S.C. § 3145, and the requirements of 29 CFR Part 3 as may be applicable, which are incorporated by reference into this Contract. Contractor and Subcontractors must insert this requirement into subcontracts of any tier.
Contractor is responsible for compliance with these requirements by each Subcontractor of any tier.
__.__ Contract Work Hours and Safety Standards Act. In addition to the California state law requirements in Article 9 of the General Conditions, Contractor and each Subcontractor must comply with the requirements of the federal Contract Work Hours and Safety Standards Act, as set forth in 40 U.S.C. 3701-3708, as supplemented by the regulations set forth in 29 CFR Part 5, as may be amended from time to time, which are fully incorporated herein, including:
(A) No Contractor or Subcontractor will require or permit any laborer or mechanic performing Work for the Project to work in excess of 40 hours in a work week unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of 40 hours during that work week.
(B) If Contractor or a Subcontractor violates this requirement, the Contractor and any responsible Subcontractor will be liable for the unpaid wages. In addition, the Contractor and Subcontractor will be liable to the United States for liquidated damages. The liquidated damages will be computed with respect to each individual worker as specified under federal law.
(C) Contractor and Subcontractors must insert this requirement into subcontracts of any tier. Contractor is responsible for compliance with these requirements by each Subcontractor of any tier.
__.__ Rights to Inventions. If the federal funding for this Contract meets the definition of “funding agreement” under 37 CFR § 401.2(a) and constitutes an agreement between the City and a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the requirements of 37 CFR Part 401, “Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements,” and any implementing regulations issued by the awarding agency, will apply to this Contract and are fully incorporated into the Contract Documents by this reference.
__.__ Clean Air Act. If the Contract is for an amount in excess of $150,000, Contractor and each Subcontractor must comply with the requirements of the Clean Air Act, as amended, (42 U.S.C. §§ 7401-7671q), which are fully incorporated into the Contract Documents by this reference, including requirements for reporting violations to the awarding agency and the applicable Regional Office for the Environmental Protection Agency. Contractor and Subcontractors must insert this requirement into subcontracts of any tier in excess of $150,000.
__.__ Federal Water Pollution Control Act. If the Contract is for an amount in excess of $150,000, the requirements of the Federal Water Pollution Control Act (33 U.S.C. §§ 1251-1387) apply to this Contract and are fully incorporated into the Contract Documents by this reference, including requirements for reporting violations to the awarding agency and the applicable Regional Office for the 203
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 92
Environmental Protection Agency requirements for reporting violations.
Contractor and Subcontractors must insert this requirement into subcontracts of any tier in excess of $150,000.
__.__ Suspension and Debarment. Contractor is required to verify that neither it, nor its principals, as defined at 2 CFR § 180.995, or its affiliates, as defined at 2 CFR § 180.905, are excluded or disqualified, as defined at 2 CFR §§ 180.935 and 180.940. Contractor must comply with 2 CFR Part 180, subpart C and 2 CFR Part 3000, subpart C, and must include a provision requiring compliance with these regulations in any subcontract of any tier. If it is later determined that the Contractor did not comply with the applicable subparts, the Federal Government may pursue available remedies, including, but not limited to, suspension and/or debarment. By submitting a bid and entering into this Contract, Contractor agrees to comply with these requirements.
__.__ Byrd Anti-Lobbying Amendment. If the Contract is for an amount in excess of $100,000, Contractor must comply with the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1352) and file the certification provided at 44 CFR Part 18, Appendix A, and any disclosures, with the applicable federal agency. Each tier certifies to the tier above that it will not and has not used federal-appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any federal contract, grant, or any other award covered by 31 U.S.C. § 1352.
Each tier will also disclose any lobbying with non-federal funds that takes place in connection with obtaining any federal award. Such disclosures will be forwarded from tier to tier up to the recipient.
__.__ Procurement of Recovered Materials. The requirements of § 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act at 42 U.S.C. § 6962, apply to this Contract and are fully incorporated into the Contract Documents by this reference. For individual purchases of $10,000 or more, Contractor will make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired (A) competitively within the Contract schedule, (B) in conformance with Contract performance requirements, or (C) at a reasonable price. Information on this requirement, including a list of EPA-designated items, is available at the EPA’s Comprehensive Procurement Guidelines website:
https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program.
__.__ Prohibition on Covered Telecommunications. Federal loan or grant funds must not be obligated or expended to procure or obtain, extend or renew a contract to procure or obtain, or enter into a contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, as further specified in 2 CFR § 200.216, which is fully incorporated into the Contract Documents by this reference. Covered telecommunications equipment or services includes equipment produced by, services provided by, or services using equipment produced by: Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities); Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities); or an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, 204
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 93
reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
__.__ Domestic Preferences for Procurements. As appropriate and to the extent consistent with Laws, the City should, to the greatest extent practicable under a federal award, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States, as further specified in 2 CFR § 200.322, which is fully incorporated into the Contract Documents by this reference, including, but not limited to, iron, aluminum, steel, cement, and other manufactured products, as specified therein. The requirements of 2 CFR § 200.322 must be included in all subcontracts and purchase orders for work or products under the federal award.
The following optional provision may be used to attach and incorporate federal contract requirements for projects administered under Caltrans’ Local Assistance Procedures Manual (“LAPM”), as specified in Chapter 12 of the LAPM and exhibits thereto, including “Appendix E” to the Standard Title VI/Non- Discrimination Assurances (DOT Order No. 1050.2A), effective September 17, 2020, which may be downloaded from https://dot.ca.gov/-/media/dot- media/programs/local-assistance/documents/title-vi/appendix-e-of-the-title-v-i- assurances.pdf. Federal law and LAPM requirements are frequently amended.
DELETE ATTACHMENT B IF NOT APPLICABLE. Be sure to use the most current version of the LAPM, which may be downloaded from:
https://dot.ca.gov/programs/local-assistance/guidelines-and-procedures/local- assistance-procedures-manual-lapm.
__. Federal Contract Requirements. This Project is funded in whole or in part by federal funds administered under Caltrans’ Local Assistance Procedures Manual (“LAPM”). LAPM contract requirements are provided in Attachment B - Federal Contract Requirements. Contractor must comply with the requirements set forth in Attachment B.
The following provision may be used to provide more detail on the Contractor’s post-construction restoration requirements. This provision may be adapted by adding Project-Specific requirements or deleting requirements that are not applicable. Cross-reference: General Conditions Section 7.9(E).
__. Close Out Requirements. Contractor’s close out requirements include the following, if applicable:
__.1 Contractor must replace, with thermoplastic, any existing striping within and adjacent to the Project site that is damaged during the Work. Partially damaged striping must be replaced in its entirety.
__.2 Contractor must replace any survey monuments that are damaged or removed during the Work, with a Record of Survey filed by a licensed land surveyor as required by California law.
__.3 Before removing any traffic control or street signs on the Project site, Contractor must take photographs showing their original locations. Upon completion of each phase of construction, Contractor must temporarily reset the signs at those 205
<Project Title> 2022 Form SPECIAL CONDITIONS
<Project Number> Page 94
locations. Contractor must then replace the signs permanently upon completion of the Work and the cost of their removal and replacement must be included in the Bid Proposal.
__.4 Contractor must maintain any rural mail boxes on the Project site and relocate them to their permanent locations as soon as possible in the course of the Work, to the satisfaction of the affected property owners and the postal service.
The following provision may be used to expressly limit circumstances under which a contractor may be entitled to share in the cost savings from value engineering proposed by the Contractor. Reference Public Contract Code § 7107.
__. Value Engineering. The Contractor may be entitled to additional compensation for cost reduction changes made pursuant to a value engineering proposal submitted by the Contractor, subject to the limitations of Public Contract Code § 7107, and in strict compliance with this Section __. Contractor will not be entitled to any such additional compensation unless all of the following requirements have been met:
__.1 The Contractor must submit a written proposal for changes to the Plans or Specifications for the Project, in which it:
(A) Identifies the written proposal as a proposal for cost reduction changes with reference to this section;
(B) Clearly and specifically identifies the proposed cost reduction changes by describing in detail each of the changes proposed with specific references to each of the Specifications and Plans involved in the proposed changes, and providing proposed revised Specifications and Plans as applicable; and
(C) Estimates the net amount of the cost reduction and provides the basis for that estimate.
__.2 The proposed changes have been identified and developed solely by the Contractor, and not, in whole or in part, by the City.
__.3 The City accepts the proposed changes in whole or in part in a writing signed by the Engineer. The Contractor will only be entitled to additional compensation for those changes specifically accepted by the City. The Engineer will determine the net savings in construction costs from any such changes that are both accepted and implemented by the City. Contractor will not be entitled to more than 50% of the net savings as determined by the Engineer, acting in his or her sole discretion.
END OF SPECIAL CONDITIONS
206
<Project Title> 2022 Form ATTACHMENT A – FEDERAL
<Project Number> BIDDING REQUIREMENTS
Attachment A – Federal Bidding Requirements
<insert applicable LAPM requirements or delete Attachment A if not applicable>
END ATTACHMENT A – FEDERAL BIDDING REQUIREMENTS
207
<Project Title> 2022 Form ATTACHMENT B – FEDERAL
<Project Number> CONTRACT REQUIREMENTS
Attachment B – Federal Contract Requirements
<insert applicable LAPM requirements or delete Attachment B if not applicable>
END ATTACHMENT B – FEDERAL CONTRACT REQUIREMENTS
208
<Project Title> 2022 Form
<Project Number> Page 97
[Insert Technical Specifications]
209
<Project Title> 2022 Form NOTICE OF POTENTIAL AWARD
<Project Number> Page 98
[Copy onto City letterhead]
Sent via _______________ <insert delivery method, e.g., certified mail or FedEx>
<Date>
<Contractor representative name and title>
<Contractor business name>
<Contractor address>
<Contractor email>
Re: NOTICE OF POTENTIAL AWARD
<____________________________> Project
Dear <Contractor representative name>:
I am pleased to inform you of the intent to recommend that the City Council or its authorized designee award the Contract for the above-referenced Project (“Project”) to <_______________> (“Contractor”) for the Contract Price of $<_____________>, based on Contractor’s Bid Proposal submitted on <____________, 20__>.
A copy of the Contract accompanies this Notice. Contractor must execute <___> copies of the enclosed Contract and return the wet-inked copies to my attention, accompanied by the required Payment Bond and Performance Bond, and insurance certificates and endorsements, no later than ten days from the date of this Notice of Potential Award, above.
Failure to execute and return the enclosed Contract and required bonds and insurance documentation within the specified time could result in forfeiture of Contractor’s bid security. This Notice of Potential Award does not bind the City to award the Contract. The City, acting through its City Council or authorized designee, reserves the right to reject any or all bids, and the right to decline to award the Contract, notwithstanding any staff recommendation.
Unless expressly authorized or required to engage in any pre-construction activities, such as preparing submittals, Contractor must not commence Work until directed by the Notice to Proceed and will not be entitled to compensation or credit for any Work performed before the date specified in the Notice to Proceed.
Please acknowledge receipt of this Notice of Potential Award by signing the attached Acknowledgement of Notice of Potential Award, as indicated, and transmitting the Acknowledgement to my office via email at: __________________ <Email Address>. Do not hesitate to contact me if you have any questions in this regard.
Sincerely,
_________________<Name>
_________________<Title>
Enclosure
210
<Project Title> 2022 Form NOTICE OF POTENTIAL AWARD
<Project Number> Page 99
Acknowledgement of Notice of Potential Award
On behalf of <________________________________________> (“Contractor”), I acknowledge receipt of the Notice of Potential Award for the <_______________________> Project:
s/_________________________________
Name: _____________________________
Title: ______________________________
Date: ______________________________
211
<Project Title> 2022 Form NOTICE TO PROCEED
<Project Number> Page 100
[Copy onto City letterhead]
Sent via _______________ <insert delivery method, e.g., certified mail or FedEx>
<Date>
<Contractor representative name and title>
<Contractor business name>
<Contractor address>
<Contractor email>
Re: NOTICE TO PROCEED
<____________________________> Project
Dear <Contractor representative name>:
By this letter <______________________________> (“Contractor”) is notified to proceed with its Work for the above-referenced Project (“Project”), as required by the Contract Documents. Contractor should start the Work on or before <____________, 20__> (“Start Date”), and must achieve Final Completion within <_______> calendar days from the Start Date.
[Optional: Contractor and its first-tier Subcontractors must attend a mandatory pre- construction conference on <date> at <time> at <address/location>. The following document(s) must be submitted to the Project Manager at ___________ <email address>, no later than <_______, 20__>: ____________________________ <list required documents, e.g., baseline schedule, subcontracts, submittal schedule, schedule of values, etc.>]
A copy of the fully executed Contract is enclosed for your files.
Please acknowledge receipt of this Notice to Proceed by signing the attached Acknowledgement of Notice to Proceed, as indicated, and transmitting the Acknowledgement to my office via email at: __________________ <Email Address>. Do not hesitate to contact me if you have any questions in this regard.
Sincerely,
_________________<Name>
_________________<Title>
Enclosure
212
<Project Title> 2022 Form NOTICE TO PROCEED
<Project Number> Page 101
Acknowledgement of Notice to Proceed
On behalf of <________________________________________> (“Contractor”), I acknowledge receipt of the Notice to Proceed for the <_______________________________> Project:
s/_________________________________
Name: _____________________________
Title: ______________________________
Date: ______________________________
213
<Project Title> 2022 Form NOTICE OF COMPLETION
<Project Number> Page 102
Recording Requested By:
The City of ___________
When Recorded Mail To:
_____________________ <name, title>
_____________________ <street address>
_____________________ <city, state and zip>
EXEMPT FROM RECORDING FEES PER
GOVERNMENT CODE § 27383
SPACE ABOVE THIS LINE IS FOR RECORDER’S USE
NOTICE OF COMPLETION
Civil Code §§ 8182, 8184, 9204, and 9208
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is the agent of the owner of the Project described below.
2. Owner’s full name is _________________________________________ (“City”)
3. City’s address is __________________________________________
4. The nature of City’s interest in the Project is:
__ Fee Ownership __ Lessee __ Other:__________________
5. Construction work on the Project performed on City’s behalf is generally described as follows:
<____________________________________________________________________________ ____________________________________________________________________________>.
6. The name of the original Contractor for the Project is: <________________> located at <__________________________________>.
7. The Project was accepted as complete on: <_________________, 20__>.
8. The Project is located at: <____________________________________>.
Verification: In signing this document, I, the undersigned, declare under penalty of perjury under the laws of the State of California that I have read this notice, and I know and understand the contents of this notice, and that the facts stated in this notice are true and correct.
__________________________ ________________________________ Date and Place Signature
________________________________
Name and Title
EXEMPT FROM NOTARY ACKNOWLEDGMENT REQUIREMENTS PER
GOVERNMENT CODE § 27287 AND CIVIL CODE § 9208
214
City of Pittsburg, California December 2022
SUMMARY 01 10 00 - 1
SECTION 01 10 00 – SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes the contract and other work, plus project requirements.
B. Related Sections:
1. Division 00 – General Conditions.
1.2 CONTRACT DESCRIPTION
A. Contract: Perform Work of Contract under stipulated sum contract with City per Contract Documents.
B. Responsible Parties: Construction of the Project is governed by the agreement between the City and the Contractor. Statements in the specifications are directed to this contractor, who has overall responsibility for the subcontractors.
C. Project Manager: The City will provide a Project Manager who will administer the project during the contract.
1.3 WORK UNDER OTHER CONTRACTS
A. Separate Contracts: The City may award separate contracts for performance of certain construction operations at the site. Those operations will be conducted simultaneously with the work under the Contract. The Contracts are described in Division 00 Article 2 Section 2.4 – Coordination of Work.
1.4 SCHEDULE OF VALUES
A. Schedule of Values: The Schedule of Values and Bid Schedule are described in Division 00 Article 8 – Payment. Any bid item may be deleted in total or in part prior to or after award of Contract without compensation in any form or adjustment of other bid items or prices, therefore.
1.5 MISCELLANEOUS WORK
A. Miscellaneous Work Requirements: Coordinating, handling, transpo rting, and installing items such as field testing of systems; leveling; furnishing, coordinating, and installing sleeves, anchors, and other embedded items; posting of signs; performing traffic routing work; providing operating and maintenance data and instruction of the City Project Manager; performing warranty work as required; and doing incidental and related work to place all systems and structures in operating condition as designed and as required by Federal, State and Local 215
City of Pittsburg, California December 2022
SUMMARY 01 10 00 - 2
codes and regulations. Refer to Division 00 – General Conditions for a summary of work requirements.
1.6 OWNER-FURNISHED PRODUCTS
A. Owner's Responsibilities:
1. Arrange for and deliver Owner-reviewed Shop Drawings, Product Data, and Samples to Contractor.
2. Upon delivery, inspect products jointly with Contractor.
3. Submit claims for transportation damage and replace damaged, defective, or deficient items.
4. Arrange for manufacturers' warranties, inspections, and service.
B. Contractor's Responsibilities:
1. Review Owner-reviewed Shop Drawings, Product Data, and Samples.
2. Receive and unload products at Site; inspect for completeness or damage jointly with Owner.
3. Arrange and pay for delivery to Site. Retrieve items from City Corporation Yard or other designated location, as required, and transp ort to site.
Transport salvaged items to City Corporation Yard.
4. Handle, store, install, and finish products.
5. Repair or replace items damaged after receipt.
1.7 WORK SEQUENCE
A. Stages: Construct Work in stages and at times to accommodate City operation requirements during the construction period; coordinate construction schedule and operations with Project Manager.
1.8 COOPERATION OF CONTRACTOR AND COORDINATION WITH OTHER WORK
A. Coordination: Coordinate with City and any City forces, or other contractors and forces, as required by Division 00 Article 2 Section 2.4 – Coordination of Work.
1.9 CONTRACTOR USE OF PREMISES
A. General: During the construction period the Contractor shall have full use of the premises within the “limits of work” for construction operations, including use of the site. The Contractor's use of the premises is limited only by the City's right to perform work or to retain other contractors on portions of the Project.
B. Use of the Site:
1. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available for emergency vehicles at all times.
2. Traffic and Barrier Plan: When the Contractor needs to access portions of roadways and driveways, on and adjacent to the work, Contractor is 216
City of Pittsburg, California December 2022
SUMMARY 01 10 00 - 3
required to submit a traffic and barrier plan to the City for their review and approval prior to setting up any traffic control devices.
3. Stored Materials: The Contractor assumes all responsibility for protection and safekeeping of material stored on the premises. Moving stored materials which interfere with the operations of the City or other contractors is the responsibility of the Contractor.
4. Condition of Site: Maintain work areas in a safe condition at all times, remove all graffiti and accumulated rubbish and surplus materials at the end of each work day, and clean and restore the work site at completion of the work to the condition that existed prior to the start of work.
C. Security of the Contractor’s Work Area : The security of the Contractor’s work areas and its property, equipment, construction materials, and all other items contained in the Contractor’s staging areas or elsewhere on the construction site shall be solely the Contractor’s responsibility at all times.
1.10 MAINTENANCE
A. Contractor’s Responsibility: Cost of maintenance of systems and equipment prior to Final Acceptance will be considered as included in prices bid and no direct or additional payment will be made therefore.
1.11 OCCUPANCY REQUIREMENTS
A. Early Occupancy: Whenever, in the opinion of Project Manager, Work or any part thereof is in a condition suitable for use, and the best interest of City requires such use, City may take beneficial occupancy of and connect to, open for public use, or use the Work or such part thereof. In such case, City will inspect the Work or part thereof, and issue a Certificate of Substantial Completion for that part of Work.
B. Repairs: Prior to date of Final Acceptance of the Work by City, all necessary repairs or renewals in Work or part thereof so used, not due to ordinary wear and tear, but due to defective materials or workmanship or to operations of Contractor, shall be made at expense of Contractor, as required in Division 00 Article 11 – Completion and Warranty Provisions.
C. Acceptance: Use by City of Work or part thereof as contemplated by this section shall in no case be construed as constituting acceptance of Work or any part thereof. Such use shall neither relieve Contractor of any responsibilities under Contract, nor act as waiver by City of any of the conditions thereof.
D. Partial Completion: City may specify in the Contract Documents that portions of the Work, including electrical and mechanical systems or separate structures, shall be substantially completed on milestone dates prior to substantial completion of all of the Work. Contractor shall notify Project Manager in writing when Contractor considers any such part of the Work ready for its intended use 217
City of Pittsburg, California December 2022
SUMMARY 01 10 00 - 4
and substantially complete and request Project Manager to issue a Certificate of Substantial Completion for that part of the Work.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 10 00
218
City of Pittsburg, California December 2022
UNIT PRICES 01 22 00 - 1
SECTION 01 22 00 –UNIT PRICES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies procedures and requirements for measurement and payment for unit price items listed on the Bid Form for each unit of work described herein.
B. Refer to the Instruction to Bidders and Division 00 General Conditions and Division 00 Article 8 – Payment for related requirements pertaining to change orders, payments and unit prices.
C. Prices:
1. In addition to Base Bid, Bidder shall quote unit prices, in appropriate spaces on Bid Form for each unit of work as described herein. Change Orders will be based on unit prices quoted on Bid Form for applicable work.
2. In event any unit price quoted appears to compare unfavorably with currently esta blished prices for type of work, City reserves the right to require quoted price to be substantiated or adjusted prior to execution of contract.
3. Unit prices listed on the Bid Form for the following items shall constitute full and complete compensation for each unit, and shall include cost of temporary and administrative work, permits, bonds, insurance, sales taxes, overhead, profit and every other expense, direct or indirect, incident to accomplishment of work under each item.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 MEASUREMENT
A. Measurement of quantities for payment will be made or determined by City's Inspector.
1. Volume of any material shall be based on information included with Drawings and additional measurements obtained by Inspector, or by combination of such information, or in a manner which, in the opinion of the Inspector, is best suited to obtain necessary accuracy. 219
City of Pittsburg, California December 2022
UNIT PRICES 01 22 00 - 2
2. In case of unit prices based upon weight measurement, certified weight tickets shall be supplied at time of delivery of materials.
3. Excess materials delivered to the site, but not incorporated in the work, will not be paid for.
3.2 UNIT PRICE ITEMS
** To be e dited for specific project and connect ed with bid items in Special Conditions **
Example:
A. Aggregate Base Course:
1. Basis of Me asurement: By the cubic yard or tons as specified in the bid form. If measurement is by the ton, water content in excess of optimum moisture content shall be deducted from the total weight of aggregate. If measurement is by the cubic yard, quantities of ag gregates will be calcu- lated on the basis of dimensions shown on the plans. No allowance will be made for aggregate rejected or placed outside said dimensions unless oth- erwise order by the City’s Project Manager. Aggregate Base used under concrete work such as curb and gutter, valley gutter, sidewalk, driveways, curb ramps, median curbs, median nose surfacing, bus turnouts, retaining curbs, and in utility trenches shall not be measured.
2. Basis of Payment: Includes full compensation for furnishing all labor, mate- rials, tools, equipment and incidentals, in aggregate base supplying fill ma- terial, stockpiling, scarifying subgrade surface, placing where required, wa- tering, dust palliative, leveling, compacting and certifying the top of aggre- gate base design grades.
3. Aggregate Base used under concrete work such as curb and gutter, valley gutter, sidewalk, retaining curbs, etc. shall considered incidental to the item most closely related to and no separate compensation will be allowed there- for. Aggregate base used in utility trenches shall be considered incidental to the cost per linear foot paid for the utility pipes as shown on the bid form and no separate compensation will be allowed therefor.
3.3 PAYMENT
A. Payment will be made for actual quantity of work performed at contract unit price, as directed and accepted, in accordance with requirements of the General Conditions.
END OF SECTION 01 22 00
220
City of Pittsburg, California December 2022
ALTERNATES 01 23 00 - 1
SECTION 01 23 00 – ALTERNATES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements governing Alternates. Each Alternate is identified by number and describes the basic changes to be made in the Work.
B. Definition: An alternate is an amount proposed by bidders and stated on the Bid Form for work defined in the Bidding Requirements that the City may elect to add to or deduct from the Base Bid amount, if the City decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate the Alternate into the Work. No other adjustments are made to the Contract Sum.
C. Related Requirements:
1. Instruction to Bidders
2. Materials and Methods Required by Alternates: Pertinent Specification Sections.
1.2 ALTERNATE BIDS
A. Alternates will be accepted at option of the City; the Base Bid, including additive or deductive Alternates accepted by the City, will be an element considered in the award of the Contract.
1.3 SCHEDULE OF ALTERNATES
Examples Add Alternate No. x - [Name of Alternate]: Add [item described here] B. Deduct Alternate No. x - [Name of Alternate]: Delete [item] specified in Section[s] [_______], shown on Drawing[s] [_______].
C. Replace Alternate No. x - [Name of Alternate]: Delete [item] specified in Section[s] [_______], shown on Drawing[s] [_______]; replace with [item] specified in Section[s] [_______], shown on Drawing[s] [_______].
221
City of Pittsburg, California December 2022
ALTERNATES 01 23 00 - 2
PART 2 - EXECUTION
2.1 MODIFICATIONS TO WORK
A. Execute accepted alternates under the same conditions as other Work of this Contract.
B. Immediately following the award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate whether alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to alternates.
C. Modify or adjust affected adjacent Work as required to completely and fully integrate that Work into the Project.
END OF SECTION 01 23 00
222
City of Pittsburg, California December 2022
SUBSTITUTION PROCEDURES 01 25 00 - 1
SECTION 01 25 00 – SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for handling requests for substitutions made after award of the Contract.
B. Related Sections:
1. Notice Inviting Bidders
2. Instructions to Bidders
3. Division 00 – General Conditions Article 7.
1.2 DEFINITIONS
A. Definitions in this Article do not change or modify the meaning of other terms used in the Contract Documents.
B. Substitutions: Changes in products, materials, equipment, and methods of construction required by the Contra ct Documents proposed by the Contractor after award of the Contract are considered to be requests for substitutions.
1. Substitutions will not be considered during the Bid process.
2. The following are not considered to be requests for substitution:
a. Revisions to the Contract Documents requested by the Owner or Architect/Engineer.
b. Specified options of products and construction methods included in the Contract Documents.
3. The following are considered to be requests for substitution:
a. Any manufacturer, product, process, or method identified in the Special Conditions, specifications or on the Drawings as either “or equal” or “equal products of another manufacturer when approved in advance by the Architect /Engineer per this Section 01 25 00 – Substitution Procedures”.
1.3 SUBMITTALS
A. Request for Substitution (RFS) Submittal:
1. Receipt:
a. The Architect/Engineer will consider requests for substitution (RFS) if received within thirty -five (35) calendar days after the Notice to Proceed.
b. Requests received after thirty-five (35) calendar days after the Notice to Proceed may be considered or rejected at the discretion of the Project Manager and/or Architect/Engineer.
223
City of Pittsburg, California December 2022
SUBSTITUTION PROCEDURES 01 25 00 - 2
1. Submit three (3) copies of each request for substitution for consideration.
Submit requests in the form and acc ording to the procedures required in Division 00 – General Conditions.
2. Identify the product or the fabrication or installation method to be replaced in each request. Include related Special Conditions, Specification Section and Drawing numbers.
3. Provide complete documentation showing compliance with the requirements for substitutions, and the following information, as appropriate:
a. Coordination information, including a list of cha nge or modifications needed to other parts of the Work and to construction performed by the Owner and separate contractors that will be necessary to accommodate the proposed substitution.
b. A detailed comparison of significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include elements, such as performance, weight, size, durability, operations, maintenance, and visual effect.
c. Product Data, including Drawings and descriptions of products and fabrication and installation procedures.
d. Samples, where applicable or requested.
e. A statement indicating the substitution’s effect on the Contractor’s Construction Schedule compared to the schedule without the approval of the substitution. Indicate the effect of the pro posed substitution on overall Contract Time.
f. Cost information, including a proposal of net change, if any, in the Contract Sum.
g. The Contractor’s certification that the proposed substitution conforms to the requirements in the Contract Documents, in every respect and is appropriate for the applications indicated.
h. The Contractor’s waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.
4. Architect/Engineer Action: If necessary, the Architect/Engineer will request additional information or documentation for evaluation within fourteen (14) calendar days of receipt of a request for substitution. The Project Manager will route to the Contractor, the Architect/Engineer’s acceptance or rejection of the substitution within fourteen (14) days of the receipt of the request, or receipt of addition information or documentation.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Conditions: The Architect/Engineer will receive and consider the Contractor’s request for substitution when one or more of the following conditions are satisfied, as determined by the Architect/Engineer. If the following conditions are not 224
City of Pittsburg, California December 2022
SUBSTITUTION PROCEDURES 01 25 00 - 3
satisfied, the Architect/Engineer will return the requests without action except to record non-compliance with these requirements:
1. Extensive revisions to the Contract Documents are not required.
2. Proposed changes are in keeping with the general intent of the Contract Documents.
3. The request is timely, fully documented, and properly submitted.
4. The request is directly related to an “or-equal” clause or similar language in the Contract Documents.
5. The requested substitution offers the Owner a substantial advantage, in cost, time, energy conservation, maintainability, or other considerations, after deducting additional responsibilities the Owner must assume. The Owner’s additional responsibilities may include compensation to the Architect/Engineer for redesign and evaluation services, compensation to the Project Manager for additional management and coordination, increased cost of other construction by the Owner, and similar considerations.
6. The specified product or method of construction cannot be provided in a manner that is compatible with other materials and where the Contractor certifies that the substitution will overcome the incompatibility.
7. The specified product or method of construction cannot be coordinated with other materials and where the Contractor certifi es that the proposed substitution can be coordinated.
8. The specified product or method of construction cannot provide a warranty required by the Contract Documents and where the Contractor certifies that the proposed substitution provides the required warranty.
B. The Contractor’s submittal and the Architect/Engineer acceptance of Shop Drawings, Product Data, or Samples for construction activities not complying with the Contract Documents do not constitute an acceptable or valid request for substitution, nor do they constitute approval.
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 25 00
225
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1
SECTION 01 26 00 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes general procedural requirements for alterations, modifications and extras.
B. Related Sections:
1. Division 00 General Conditions, Articles 5, 6, and 8
2. Section 01 29 00 – Payment Procedures
1.2 GENERAL
A. Any change in scope of work or deviation from Drawings, Special Conditions, or Specifications shall be accomplished only when authorized in writing by Project Manager.
B. Changes in scope of Work or deviation from Dr awings, Special Conditions, or Specifications may be initiated only by Contractor or Project Manager.
1. Contractor may initiate changes by submitting Requests for Interpretation (RFI), Requests for Substitution (RFS), Notice of Concealed or Unknown Conditions, or Notice of Hazardous Waste Conditions.
a. RFIs shall be submitted to seek clarification of Contract Documents in accordance with Section 01 26 13 – Requests for Interpretation. b. RFSs shall be submitted in accordance with Section 01 25 00 – Substitution Procedures to request substitution of materials or methods of execution.
c. Notices of Concealed or Unknown Conditions shall be submitted in accordance with Division 00 - General Conditions.
d. Notices of Hazardous Waste Conditions shall be submitted in accordance with Division 00 - General Conditions.
2. Contractor shall be responsible for its costs to implement and administer RFIs and RFSs throughout the Contract duration. Regardless of the number of RFIs submitted, Contractor will not be enti tled to additional compensation.
Contractor shall be responsible for both City's and Architect/Engineer's administrative costs for answering its RFIs where the answer could reasonably be found by reviewing the Contract Documents, as determined by City; such costs will be deducted from progress payments.
3. The City may initiate changes by issuing a Supplemental Instruction.
4. Project Manager may initiate changes in the Work or Contract Time by issuing Requests for Proposal (RFP) to Contractor. Such RFPs will detail all proposed changes in the Work and request a quotation of changes in Contract Sum and Contract Time from Contractor.
226
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2
1.3 PROCEDURE
A. Contractor shall submit RFI to Project Manager in accordance with Section 01 26 13 – Requests for Interpretation. Contractor shall reference each RFI to an activity of Progress Schedule and shall note time criticality of the RFI.
1. If Contractor is satisfied with the Clarification and does not request change in Contract Sum or Contract Time, then the Clarification shall be considered executed without a change.
2. If Contractor believes that the Clarification results in change in Contract Sum or Contract Time, Contractor shall notify Project Manager who may then deny request for change or issue RFP.
B. Contractor shall submit RFS to Project Manager who may then approve or deny request. If denied, Project Manager shall set forth in writing reasons for the denial.
Contractor may revise and resubmit submittal with a rebuttal based on Section 3400 Public Contract Code CA. The RFS should set forth:
1. Reason for substitution
2. Any deviations from Special Conditions or specifications
3. Cost increase or decrease
4. Any necessary revisions to drawings/related work
5. Schedule impacts.
C. Contractor shall submit Notices of Concealed or Unknown Conditions to resolve unanticipated conditions incurred in the execution of the Work. Procedures in Division 00 - General Conditions shall be followed. If Project Manager determines that a change in Contract Sum or Contract Time is justified, Project Manager shall issue RFP.
D. Contractor shall submit Notices of Hazardous Waste Conditions to resolve problems regarding hazardous materials encountered in the execution of the Work.
Procedures in Division 00 - General Conditions shall be followed. If Project Manager determines that a change in Contract Sum or Contract Time is justified, Project Manager shall issue RFP.
E. Project Manager may issue Supplemental Instruction from the Architect/Engineer to Contractor. Contractor shall not proceed with Supplemental Instruction until Project Manager approves it in writing.
1. If Contractor is satisfied with Supplemental Instruction and does not request change in Contract Sum or Contract Time, then Supplement al Instruction shall be executed without a Change Order.
2. If Contractor believes that Supplemental Instruction results in change in Contract Sum or Contract Time, Contractor shall notify Project Manager.
Project Manager may then deny request for change, can cel Supplemental Instruction or issue RFP.
F. If Project Manager issues to Contractor an RFP, then Contractor shall respond to the RFP within fifteen (15) working days by furnishing a complete breakdown of 227
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 3
costs of credits, deducts, extra costs or cost savings, resulting from the change in the Work. Contractor shall itemize materials, labor, taxes, overhead and profit.
Subcontract work shall be so indicated.
G. Upon approval of RFP, Project Manager will issue a Change Order directing Contractor to proceed with extra work. If the parties do not agree on the price for an RFP, the Project Manager may decide the issue per Division 00 - General Conditions.
H. Payment shall be made as follows:
1. Change Orders which increase or decrease the Contract Sum or Contract Time shall be included by Contract Modification Form, signed by Project Manager, accepted by Contractor.
2. Payment shall be made for Change Order work along with other work in progress pa yment following completion of Change Order work. Partial completion of Change Order work shall be paid for that part completed during the period covered by the monthly payment request.
1.4 COST DETERMINATION
A. Total cost of extra work or of work omitted shall be the sum of labor cost (hourly rate plus employer paid benefits, taxes, insurance, etc.), material costs, equipment rental costs and specialist costs as defined herein plus overhead and profit as allowed herein. This limit applies in all cases of claims fo r extra work, whether calculating Change Orders, RFPs, or calculating claims of all types, and applies even in the event of fault, negligence, strict liability, or tort claims of all kinds, including strict liability or negligence. No other costs arising o ut of or connected with the performance of extra work, of any nature, may be recovered by Contractor.
No special, incidental or consequential damages may be claimed or recovered against City, their officers, agents, employees, and consultants (including, but not limited to Architect/Engineer or Construction Manager), whether arising from breach of contract, negligence or strict liability, unless specifically authorized in the Contract Documents.
B. Overhead and Profit:
1. “Overhead and Profit” may also be referred to as “Markup”.
2. Overhead shall be defined in Paragraph 1.8 below.
3. Overhead and profit on labor for extra work shall be thirty-five percent (35%).
4. Overhead and profit on materials shall be fifteen percent (15%).
5. Overhead and profit on equipment rental for extra work shall be fifteen percent (15%).
6. When extra work is performed by a first tier subcontractor, Contractor shall receive a ten percent (10%) markup on subcontractors' total costs of extra work.
C. Taxes:
1. Contra Costa County Sales Tax shall be included.
228
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 4
2. Federal and Excise Tax shall not be included.
D. Owner Operated Equipment:
1. When owner-operated equipment is used to perform extra work, Contractor will be paid for equipment and operator as follows:
a. Payment for equipment will be made in accordan ce with Paragraph
1.5.C below.
b. Payment for cost of labor will be made at no more than rates of such labor established by collective bargaining agreements for type of worker and location of work, whether or not owner-operator is actually covered by such an agreement.
1.5 COST BREAKDOWN
A. Labor: Contractor will be paid cost of labor for workers (including forepersons when authorized by Project Manager) used in actual and direct performance of extra work. Labor rate, whether employer is Contractor, subcontractor or other forces, will be sum of following:
1. Actual Wages: Actual wages paid shall include any employer payments to or on behalf of workers for health and welfare, pension, vacation and similar purposes.
2. Labor Surcharge: Payments imposed by City, County, Stat e and Federal laws and ordinances, and other payments made to, or on behalf of, workers, other than actual wages as defined in subparagraph 1 above, such as taxes and insurances. Labor surcharge shall be as set forth in California Department of Transportation official labor surcharges schedule which is in effect on date upon which extra work is accomplished and which schedule is incorporated herein by reference, as though fully set forth herein.
B. Material: Only materials furnished by Contractor and necessari ly used in performance of extra work will be paid for. Cost of such materials will be cost, including sales tax, to purchaser (Contractor, subcontractor or other forces) from supplier thereof, except as the following are applicable:
1. If cash or trade discount by actual supplier is offered or available to purchaser, it shall be credited to City notwithstanding the fact that such discount may not have been taken.
2. For materials salvaged upon completion of extra work, salvage value of materials shall be deducted from cost, less discount, of materials.
3. If cost of a material is, in opinion of Project Manager, excessive, then cost of material shall be deemed to be lowest current wholesale price at which material is available in quantities concerned delivered t o Site, less any discounts as provided in subparagraph 1 above.
C. Equipment Rental:
1. For Contractor- or subcontractor-owned equipment, payment will be made at rental rates listed for equipment in California Department of Transportation official equipment rental rate schedule which is in effect on date upon which 229
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 5
extra work is accomplished and which schedule is incorporated herein by reference as though fully set forth herein. For rented equipment, payment will be made based on actual rental invoices. Equipment used on extra work shall be of proper size and type. If, however, equipment of unwarranted size or type and cost is used, cost of use of equipment shall be calculated at rental rate for equipment of proper size and type. Rental rates paid shall be deemed to cover cost of fuel, oil, lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Unless otherwise specified, manufacturer's ratings, and manufacturer-approved modifications, shall be used to classify equipment for determination of applicable rental rates. Individual pieces of equipment or tools not listed in said publication and having a replacement value of five hundred dollars ($500) or less, whether or not consumed by use, shall be considered to be small tools and no payment will be made therefore as payment is included in payment for labor. Rental time will not be allowed while equipment is inoperative due to breakdowns.
2. For equipment on Site, rental time t o be paid for equipment shall be time equipment is in operation on extra work being performed or on standby as approved by Project Manager. The following shall be used in computing rental time of equipment:
a. When hourly rates are listed, less than thirty (30) minutes of operation shall be considered to be one-half (1/2) hour of operation. b. When daily rates are listed, less than four (4) hours of operation shall be considered to be one-half (1/2) day of operation.
3. For equipment which must be brought to Site to be used exclusively on extra work, cost of transporting equipment to Site and its return to its original location shall be determined as follows:
a. City will pay for costs of loading and unloading equipment. b. Cost of transporting equipment in low bed trailer s shall not exceed hourly rates charged by established haulers.
c. Cost of transporting equipment shall not exceed applicable minimum established rates of California Public Utilities Commission. d. Payment for transporting, and loading and unloading equipment as above provided will not be made if equipment is used on Work in any other way than upon extra work.
4. Rental period shall begin at time equipment is unloaded at Site of extra work and terminate at end of day on which City’s Project Manager directs Contractor to discontinue use of equipment. Excluding Saturdays, Sundays, and legal holidays, unless equipment is used to perform extra work on such days, rental time to be paid shall be four (4) hours for zero (0) hours of operation, six (6) hours for four (4) hours of operation and eight (8) hours for eight (8) hours of operation, time being prorated between these parameters.
Hours to be paid for equipment which is operated less than eight (8) hours due to breakdowns, shall not exceed eight (8) less number of hour s equipment is inoperative due to breakdowns.
D. Work Performed by Special Forces or Other Special Services:
230
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 6
1. When the City’s Project Manager and Contractor, by agreement, determine that special service or item of extra work cannot be performed by forces of Contractor or those of any subcontractors, service or extra work item may be performed by specialist. Invoices for service or item of extra work on basis of current market price thereof may be accepted without complete itemization of labor, material, and equ ipment rental costs when it is impracticable and not in accordance with established practice of special service industry to provide complete itemization. In those instances, wherein Contractor is required to perform extra work necessitating a fabrication or machining process in a fabrication or machine shop facility away from Site, charges for that portion of extra work performed in such facility may, by agreement, be accepted as a specialist billing. The City’s Project Manager must be notified in advance of all off-site work. To specialist invoice price, less credit to City for any cash or trade discount offered or available, whether or not such discount may have been taken, will be added 15 percent (15%) in lieu of overhead and profit provided in Paragraph 1.4.B.
1.6 FORCE-ACCOUNT
A. City may, at any time, require Contractor to perform Work on a Force Account (time and materials, cost not to exceed) basis. When Contractor performs Force Account Work, the labor, materials and equipment used in performing such Force Account Work shall be subject to City's approval.
B. Whenever any Force-Account work is in progress, definite price for which has not been agreed on in advance, Contractor shall report to the City’s Project Manager each day in writing in detail amount and cost of labor and material used, and any other expense incurred in Force-Account work on preceding work day as required herein. No claim for compensation for Force-Account work will be allowed unless report shall have been made. City may authorize Force Account Work with specific limits on price, which Contractor shall perform up to such limit.
C. Force Account work shall be paid as extra work under this Section 01 26 00 – Contract Modification Procedures . Above described methods of determining payment for work and materials shall not apply to performance of work or furnishings of material which, in judgment of the City’s Project Manager, may properly be classified under items for which prices are established in Contract.
1.7 CITY FURNISHED MATERIALS
A. City reserves right to furnish materials as it deems advisable, and Contractor shall have no claims for costs and overhead and profit on such materials.
1.8 OVERHEAD DEFINED
A. The following constitutes charges that are deemed included in overhead for all contract modifications, including Force-Account work for the entire Contract Time:
231
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 7
1. Drawings: Field drawings, shop drawings, etc. including submissions of drawings
2. Routine field inspection of work proposed
3. General superintendence
4. General administration and preparation of change orders
5. Computer services
6. Reproduction services
7. Salaries of project engineer, project manager, superintendent, timekeeper, storekeeper and secretaries
8. Janitorial services
9. Temporary on-site facilities
10. Offices
11. Telephones
12. Plumbing
13. Electrical: Power, lighting
14. Platforms
15. Fencing, etc.
16. Home office expenses.
17. Insurance and Bond premiums.
18. Procurement and use of vehicles and fuel used coincidentally in base bid work.
19. Surveying
20. Estimating
21. Protection of work
22. Final cleanup
23. Other incidental work
24. Labor liability insurance
1.9 RECORDS AND CERTIFICATION
A. Force-Account (cost reimbursement) charges shall be recorded daily upon Cost Breakdown for Contract Modification Form obtained from Inspector. Contractor or authorized representative shall complete and sign form. Inspector shall sign form for approval. Contract Modification Form shall provide names and classifications of workers and hours worked by each, itemize materials used, and also list size type and identification number of equipment, and hours operated, and shall indicate work done by specialists.
B. No payment for Force-Account work shall be made until Contractor submits original invoices substantiating materials and specialist charges.
C. City shall have the right to audit all records in possession of Contractor relating to activities covered by Contractor's claims for modification of Contract, including Force-Account work, as set forth in Division 00 - General Conditions.
D. Further, City shall have right to audit, inspect, or copy all records maintained in connection with this Contract, including financial records, in possession of 232
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 8
Contractor relating to any transaction or activity occurring or arising out of, or by virtue of, Contract. If Contractor is a joint venture, right of City shall apply collaterally to same extent to records of joint venture sponsor, and of each individual joint venture member.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 26 00
233
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 9
DAILY EXTRA WORK REPORT
COST BREAKDOWN FORM FOR CONTRACT MODIFICATION
SHEET 1 OF 3
One separate form shall be used by Contractor, each first tier subcontractor and each lower tier subcontractor.
One form for each shall be used for each change order. One form for each, for each day shall be used for Force-Account work.
CHANGE ORDER NUMBER: _________________ DATE:______________________
CHANGE ORDER DESCRIPTION: ____________________________________________
_________________________________________________________________________
CONTRACTOR:____________________________________________________________
LABOR
NAME CLASSIFICATION HOURS RATE TOTAL
TOTAL LABOR COSTS (Enter here and on Line 1 of Sheet 3) 234
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 10
COST BREAKDOWN FORM FOR CONTRACT MODIFICATION
SHEET 2 OF 3
MATERIALS
DESCRIPTION COST
TOTAL MATERIAL COSTS (Enter here and on Line 4 of Sheet 3)
EQUIPMENT RENTAL
SIZE AND TYPE I.D. # HOURS RATE TOTAL
TOTAL EQUIPMENT RENTAL COSTS (Enter here and on Line 8)
SPECIALIST
DESCRIPTION COST
TOTAL SPECIALIST COSTS (Enter here and on Line 11)
235
City of Pittsburg, California December 2022
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 11
COST BREAKDOWN FORM FOR CONTRACT MODIFICATION
SHEET 3 OF 3
TOTAL COSTS
1. TOTAL LABOR COSTS
2. 10 % of Line 1
3. ADD Lines 1 and 2
4. TOTAL MATERIAL COSTS
5. 10 % of Line 4
6. 8.25 % of line 4
7. ADD Lines 4, 5 and 6
8. TOTAL EQUIPMENT RENTAL
COSTS
9. 10 % of Line 8
10. ADD Lines 8 and 9
11. TOTAL SPECIALIST COSTS
12. 10 % of Line 11
13. ADD Lines 11 and 12
14. TOTAL COST OF EXTRA WORK (ADD Lines 3, 7, 10 and 13)
CONTRACTOR OR AUTHORIZED REPRESENTATIVE: ____________________________
APPROVED BY INSPECTOR: ________________________________________________ 236
City of Pittsburg, California December 2022
REQUESTS FOR INTERPRETATION 01 26 13 - 1
SECTION 01 26 13 – REQUESTS FOR INTERPRETATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes procedural requirements for requests for interpretation , information, and/or clarification.
B. Related Sections:
1. Division 00 – General Conditions
2. Section 01 26 00 – Contract Modification Procedures
1.2 GENERAL
A. Description: Submit RFI to the Project Manager promptly upon identification of need, and in reasonable time so as not to affect the progress of the Work.
B. Submission Procedures:
1. Pre-submission Review: Before submitting request to the Project Manager, conduct a review to determ ine that the information requested, including items submitted by subcontractors or suppliers, is not shown in the Contract Documents.
2. Category of Request: Submit requests for interpretation when one or more of the following conditions occur.
a. Need for Clarification: When information shown or indicated in the Contract Documents is unclear in its intent.
b. Unforeseen Condition: Discovery of unforeseen condition or circumstance that is not shown or indicated in the Contract Documents.
c. Conflict Within Documents: Discovery of an apparent inconsistency, conflict, or discrepancy between different portions of the Contract Documents, where the intent cannot be reasonab ly inferred from information shown or indicated.
d. Omission: Discovery of what appears to be an omission in the Contract Documents, where the intent cannot be reasonably inferred from information shown or indicated.
e. Coordination Problem: Discovery of unfores een condition in coordinating placement of work that is specifically related to the Contract Documents.
3. Unacceptable Requests:
a. General: Do not submit RFIs for confirmation of any action already taken by the Contractor. Requests will not be accepted that im ply confirmation of any unauthorized change to the Work.
237
City of Pittsburg, California December 2022
REQUESTS FOR INTERPRETATION 01 26 13 - 2
b. Untimely Submission: A n RFI that is submitted in a belated manner without proper coordination and scheduling of the Work of related subcontractors will not be reviewed and will be returned to the Contractor.
c. Submittal: An RFI that is included as part of a submittal will not be processed; see Section 01 33 00 – Submittal Procedures. d. Substitution: A n RFI that is a request for substitution will not be processed; see Section 01 25 00 – Substitution Procedures. e. Exclusionary Submission: A request that implies that specific portions of the work are assumed to be excluded or considering a separate portion of the Contract Documents in part rather than as a whole will not be processed.
C. Log: Prepare and maintain the official log of RFIs. Review status of log at each job progress meeting.
PART 2 - PRODUCTS
A. SUBMISSION REQUIREMENTS:
1. Request for Interpretation (RFI) Form:
a. General: Provide a completed and legible PDF of an RFI form that includes the following required information.
b. RFI Number: Identify RFIs sequentially starting from number one (1); number re-submissions with same number as original and add letter designation A , B, C, etc., in order submitted, until resoluti on is achieved.
c. PDF Name: Include RFI number and reference to name of project in file name; if space allows include brief description of subject in RFI file name.
d. Contractor: Provide company name and mailing address with signature of contact person respon sible for work on th e subject project, certifying to review of RFI.
e. Subcontractor and/or Supplier Provide company name, mailing address, telephone number and name and email of contact person responsible for work on the subject project.
f. RFI Description:
1) General: Describe subject of RFI completely.
2) Drawing References: Identify specific drawing number and/or detail number or note under consideration.
3) Specifications References: Identify specification section number and paragraph number under consideration.
4) Attachments: Identify as required, to support description. 5) Contractor’s Proposed Resolution:
a) General: Describe suggested resolution; support with attachments as required.
238
City of Pittsburg, California December 2022
REQUESTS FOR INTERPRETATION 01 26 13 - 3
b) Cost Impact: Indicate impact on costs; explain Contractor's original b asis for bid and, based on the current request, reason that additional costs should be considered.
c) Time Impact : Indicate effect on schedule; explain
Contractor's original basis for bid and, based on the current request, why a time extension should be considered.
PART 3 - EXECUTION
A. PROJECT MANAGER'S RESPONSE:
1. General: Project Manager will respond on the RFI Form and include attachments, as referenced. Verbal responses to such requests are to be considered informati onal; official written response will only be given on annotated PDF of original RFI Form.
2. Project Manager's Review:
a. General: Allow ten (10) working days after receipt. If more than ten (10) requests are received within one (1) calendar week, the Project Manager will specifically schedule and extend response time as required to accomplish the reviews.
b. Prioritization: If more than five (5) requests have been received by the Project Manager, the Contractor shall identify the order of requests most critical to the schedule of the Project.
B. DISTRIBUTION:
1. General: Submit PDF of original, signed copy. PDF with the official response will be returned to the Contractor.
2. Consultants: The Project Manager will distribute copies of requests for information to project consultants, as required for their participation. Direct communication and response between project consultants and Contractor will be considered informational only.
3. Response: The Contractor will make and distribute copies of the official response to subcontractors and suppliers, as required.
END OF SECTION 01 26 13
239
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 1
SECTION 01 29 00 – PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes the procedures for preparation and submittal of Progress Payment Requests.
B. Related Sections:
1. Division 00 – General Conditions
2. Section 01 32 16 - Construction Progress Schedule
1.2 REFERENCES
A. California Public Contract Code
1.3 SCOPE OF WORK
A. Payment for the various items of the Schedule of Bid Prices, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured products, and for all labor, operations, overhead and profit, applicable taxes, and incidentals appurtenant to the items of Work being described, as necessary to complete the various items of work as specified and as shown on the Drawings. No separate payment will be made for any item that is not specifically set forth in the Schedule of Bid Prices, and all costs therefore shall be included in the prices named in the Schedule of Bid Prices for the various appurtenant items of Work.
B. Contract Prices shall be deemed to include all bonds and insurance, all appurtenances necessary to complete the required Work, including all costs for compliance with the regulations of the public agencies having jurisdiction, including Health and Safety Requirements of the California Division of Industrial Safety and the Occupational Safety and Health Administration of the U.S. Department of Labor (OSHA), and including all costs for loss or damage arising from the Work, or from action of the elements, for any unforeseen difficulties which may be encountered, and for all risks of every description connected with the prosecution of the Work until Project Completion, also for all expenses incurred in consequence of the suspension or discontinuance of the Work as provided in the Contract. Unless the Contract Documents expressly provide otherwise, the Contract Sum shall be deemed to include:
1. Any and all costs arising from any unforeseen difficulties which may be encountered during, and all risks of any description connected with, prosecution of Work until acceptance by City;
240
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 2
2. All expenses incurred due to suspension, or discontinuance of Work as provided in Contract;
3. Escalation to allow for cost increases between time of Contract Award and completion of Work.
C. Whenever it is specified herein that Contractor is to do work or furnish materials of any class for which no price is fixed in the Contract, it shall be understood that Contractor is to do such work or furnish such materials without extra charge or allowance or direct payment of any sort, and that cost of doing work or furnishing materials is to be included in price bid, unless it is expressly specified herein, in particular cases, that work or material is to be paid for as extra work.
D. Neither the payment of any estimate nor of any retained percentages shall relieve Contractor of its obligation to make good all defective work or material.
1.4 DETERMINATION OF QUANTITIES
A. Quantity of work to be paid for under any item for which a unit price is fixed in Contract shall be number, as determined by Project Manager, o f units of work satisfactorily completed in accordance with Drawings, Technical Specifications, and Specifications and as directed pursuant to Drawings, Technical Specifications, and Specifications. Unless otherwise provided, determination of number of units of work so completed will be based, so far as practicable, on actual measurement or count within prescribed or ordered limits, and no payment will be made for work done outside of limits. Measurements and computations will be made by methods as City’s Project Manager may consider appropriate for class of work measured.
1.5 BASIS OF PAYMENT
A. Unit Pay Quantities: When estimated quantity for specific portions of Work is listed in Bid Form, quantity of work to be paid for shall be actual number of units satisfactorily completed in accordance with Drawings, Technical Specifications, and Specifications.
B. Lump Sum: When estimated quantity for specific portion of Work is not indicated and unit is designated as Lump Sum, payment will be on a Lump Sum basis for Work satisfactorily completed in accordance with Drawings, Technical Specifications, and Specifications.
C. City does not expressly, or by implication, agree, warrant, or represent in any manner, that actual amount of Work will correspond with amount shown or estimated and reserves right to increase or decrease amount of any class or portion of Work, to leave out entire Bid Item or Items, or to add work not included in Bid, when in its judgment such change is in best interest of City. No change in Work shall be considered waiver of any other condition of Contract. No claim shall be made for anticipated profit, for loss of profit, for damages, or for extra payment whatever, except as otherwise expressly provided for in Contract Documents, 241
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 3
because of any differences between amount of work actually done and estimated amount as set forth herein, or for elimination of extra Bid Items.
D. Monthly payment requests shall be based upon information developed at monthly Application for Payment meetings and shall be prepared by Con tractor. The approved Schedule of Values will be the basis for Contractor’s payment requests.
1. No partial progress payment shall be made to Contractor until all cost information requested by the City is submitted and reviewed.
2. The following information shal l also be submitted with and as part of the Contractor’s progress payment application; all information, noted below, will cover the same period of the progress payment application. a. Progress Schedule: Submittal of one (1) copy of the progress schedule updated to include the progress achieved as of the date of the Application for Payment in accordance with this Section. 1) Contractor shall, at the time any payment request is submitted, certify in writing the accuracy of the payment request and that Contractor has fulfilled all scheduling requirements of Division 00 – General Conditions and Section 01 32 16 - Construction Progress Schedule , including updat es and revisions. The certification shall be executed by a responsible officer of the Contractor.
b. Project Record Drawings: Submit project record drawings with each progress payment application for the City’s Project Manager’s review.
The drawings shall be returned to the Contractor within fourteen (14) calendar days of submittal.
c. Certified Payroll: Certified payroll for all Contractor and subcontractor staffing pursuant to Section 1776 of the California Labor Code and including all subcontractors, suppliers , or creditors for all labor and materials incorporated into the work.
d. Lien Releases: Conditional or Unconditional lien release for the requested payment. Unconditional lien release for the previous payment.
3. No progress payment will be processed prior to Project Manager receiving all requested information.
E. The City will not be liable for costs arising from the delay in making progress payments.
1.6 PROGRESS PAYMENT PROCEDURES
A. If requested by Contractor, progress payments will be made monthly. 242
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 4
B. Schedule of Values:
1. Within ten (10) calendar days from issuance of Notice of Award and prior to the Contractor's application for the first progress payment, the Contractor shall submit a detailed breakdown of its bid by scheduled Work items and/or activities. This breakdown shall be referred to as the Schedule of Values.
2. If City’s Project Manager requires substantiating data, Contractor shall submit information requested by Project Manager, with cover letter identifying Project, payment request number and date, and detailed list of enclosures.
Contractor shall submit one copy of substantiating data and cover letter for each Payment request submitted.
C. Payment Requests:
1. On or about the 25th of each month, the Contractor may submit to the City’s Project Manager one (1) copy of an itemized Application of Payment on a standard form acceptable to the City’s Project Manager covering the Work completed as of the date of the Application for payment. The following information and/or documentation will be provided as part of the Application for Payment:
a. Payment requests may include, but not necessarily limited to the following:
1) Materials, equipment, and labor incorporated into the Work, less any previous payments for the same;
2) A maximum of ninety percent (90%) of the cost of major equipment, if purchased and delivered to the site or stored offsite, as under control of the City, but not installed by the Contractor. 3) Contractor’s application for payment shall be accompanied by a bill of sale, invoice, or other documentation warranting that the City has received the materials and equipment free and clear of all liens and evidence that the materials and equipment area covered by appropriate property insurance and other
arrangements to protect the City’s interest therein.
b. Such requests for progress payments shall be based upon Schedule of Values prices of all labor and materials incorporated in the Work during the preceding one -month period, less the aggregate of previous payments.
c. Each payment request shall list each Change Order executed prior to the date of submission, including the Change Order Number, a description of the work activities, consistent with the descriptions of original work activities.
1) Contractor shall submit a monthly Change Order status log to the City’s Project Manager as part of that Progress Payment Request.
2. Monthly progress payments shall be made, based on total value of activities completed or partially completed, as determined by City with participation of Contractor, and based upon approved activity costs. Accumulated retainage will be shown as separate it em in payment summary. If Contractor fails or 243
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 5
refuses to participate in construction progress evaluation with City, Contractor shall not receive current payment until Contractor has participated fully in providing construction progress information and sche dule update information for City.
D. Progress Payments:
1. Upon receiving Contractor's payment request, Project Manager will review the payment request and make necessary adjustments to percent of completion of each activity. One copy will be returned to Contra ctor with description of adjustments made. All parties will update percentage of completion values in the same manner, i.e., express value of an accumulated percentage of completion to date.
2. The payment request may be reviewed by Project Manager for the purpose of determining that the payment request is a proper payment request, and shall be rejected, revised or approved by Project Manager pursuant to the cost breakdown prepared in accordance with this Section.
3. If it is determined that the payment request is not a proper payment request suitable for payment, Project Manager shall return it to the Contractor as soon as practicable, but no later than seven (7) working days after receipt, together with a document setting forth in writing the reasons why the payment request is not proper. If Project Manager determines that portions of the payment request are not proper or not due under the Contract Documents, then Project Manager may approve the other portions of the payment request and, in the case of disputed items or defective work not remedied, may withhold up to 150% of the disputed amount from the progress payment.
4. Pursuant to Public Contract Code, Section 20104.50, if City fails to make any progress payment within thirty (30) days after receipt of an undisputed and properly submitted payment request from a contractor, City shall pay interest to the Contractor equivalent to the legal rates set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. The thirty (30) day period shall be reduced by the number of days by which City exceeds the seven (7) day return requirement set forth herein.
5. As soon as practicable after approval of each request for progress payment, City will pay to Contractor in manner provided by law, the amounts provided for below:
a. City shall pay an amount equal to ninety percent (90%) of Project Manager's estimate, which amount shall remain in effect until such time, if any, that the retention is reduced by Project Manager pursuant to the other provisions of this paragraph.
b. At any time after fifty percent (50%) in value of the Work as set forth in the Schedule of Values has been completed and the retained funds are equal to five percent (5%) of the Contract Sum (including Change Orders, if applicab le), and if the progress of the Work under the Progress Schedule is satisfactory, Project Manager may, at its sole discretion, but shall not be obligated to, authorize any remaining 244
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 6
progress payment to be made in the amount of ninety -five percent (95%) of the amount approved for payment.
c. When Project Manager determines that at least ninety -five percent (95%) in value of the Work as set forth in the Schedule of Value s is completed, Project Manager may, at its sole discretion, but shall not be obligated to, reduce the amount of the retained funds to one hundred twenty-five percent (125%) of the value of the Work yet to be completed, as determined by Project Manager.
d. After all Work is completed in accordance with Contract, the remaining retention amount shall be paid to the Contractor in accordance with Paragraph 1.9, below.
e. If a lesser payment amount is provided in the Contract Documents, such lesser amount shall apply instead of the amounts set forth above in this paragraph.
f. Progress payments may at any time be withheld if, in judgment of Project Manager, Work is not proceeding in accordance with Contract, or Contractor is not complying with requirements of Contract, or to comply with stop notices or to offset liquidated damages accruing or expected.
6. Retention will not be reduced if Contractor, in the opinion of the Project Manager, is behind schedule. If retention is reduced at any point during Contract and Contractor subsequently falls behind schedule, retention may be raised back to original percentage.
7. Before any progress payment or final payment is made, the Contractor may be required to submit satisfactory evidence that Contractor is not delinquent in payments to employees, subcontractors, suppliers, or creditors for labor and materials incorporated into Work.
8. City reserves and shall have the right to withhold payment for any equipment and/or specifically fabricated materials that, in the sole judgment of Project Manager, is not adequately and properly protected against weather and/or damage, prior to or following incorporation into the Work.
9. Approval of progress payment and payment by City, or receipt thereof by Contractor, shall not be understood as constituting in any sense acceptance of Work or of any portion thereof, and shall in no way lessen liabil ity of Contractor to replace unsatisfactory work or material, though unsatisfactory character of work or material may have been apparent or detected at time payment was made.
10. When City shall charge sum of money against Contractor under any provision of Contract, amount of charge shall be deducted and retained by City from amount of next succeeding progress payment or from any other monies due or that may become due Contractor under Contract. If, on completion or termination of Contract, such monies due Contractor are found insufficient to cover City's charges against Contractor, City shall have right to recover balance from Contractor or Sureties.
245
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 7
1.7 SUBSTITUTION OF SECURITIES IN LIEU OF RETENTION
A. Pursuant to provisions of Public Contract Code, Section 22300, substitution of securities for any monies withheld under Contract to insure performance is permitted under the following conditions:
1. At request and expense of Contractor, securities listed in Section 16430 of the Government Code, bank or savings and loan certificates of deposit, interest bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed to by Contractor and City which are equivalent to the amount withheld under retention provisions of Contract shall be deposited with Controller or with a state or federally chartered bank in California, as the escrow agent, who shall then pay such monies to Contractor. Upon satisfactory completion of Contract, securities shall be returned to Contractor.
2. Alternatively, Contractor may request and City shall make payment of retentions earned directly to the escrow agent at the expense of the Contractor. At the expense of the Contractor, the Contractor may direct the investment of the payments into securities and the Contractor shall receive the interest earned on the investments upon the same terms provided for in this section for securities deposited by the Contractor. Upon satisfactory completion of the Contract, the Contractor shall receive from escrow agent all securities, interest, and payments received by the escrow agent from City, pursuant to the terms of this section. The Contractor shall pay to each subcontractor, not later than twenty (20) days after receipt of the payment, the respective amount of interest earned, net of costs attributed to retention withheld from each subcontractor, on the amount of retention withheld to insure the performance of the Contractor.
3. Contractor shall be beneficial owner of securities substituted for monies withheld and shall receive any interest thereon.
4. Contractor shall enter into escrow agreement with Controller according to Document 00 53 00 - Escrow Agreement for Security Deposits in Lieu of Retention, as authorized under Public Contract Code, Section 22300, specifying amount of securities to be deposited, terms and conditions of conversion to cash in case of default of Contractor, and termination of escrow upon completion of Contract.
1.8 APPLICATION FOR PAYMENT OF SUBSTANTIAL COMPLETION
A. Following issuance of the Certificate of Substantial Completion, submit an Application for Payment.
1. This application shall reflect Certificates of Partial Substantial Completion issued previously for City occupancy of designated portions of the Work.
2. Administrative actions and submittals that shall precede or coincide with this application include:
a. Occupancy permits and similar approvals.
246
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 8
b. Warranties, guarantees, and maintenance agreements.
c. Test/adjust/balance records.
d. Operations and Maintenance instructions.
e. Meter readings.
f. Startup performance reports.
g. Changeover information related to City's occupancy, use, operation, and maintenance.
h. Final cleaning.
i. Application for reduction of retainage and consent of surety. j. Final progress photographs.
k. List of incomplete Work, recognized as exceptions to Architect/Engineer 's Certificate of Substantial Completion.
1.9 FINAL PAYMENT
A. As soon as practicable after all required Work is completed in accordance with Contract, including Contractor maintenance after Final Acceptance, City will pay to Contractor, in manner provided by law, unpaid balance of contract price of Work, or whole contract price of Work if no progress payment has been made, determined in accordance with terms of Contract, less sums as may be lawfully retained under any provisions of Contract or by law.
B. Prior progress payments shall be subject to correction in the final payment. Project Manager's determination of amount due as fina l payment shall be final and conclusive evidence of amount of Work performed by Contractor under Contract, and shall be full measure of compensation to be received by Contractor.
C. Contractor and each assignee under an assignment in effect at time of final payment shall execute and deliver at time of final payment and as a condition precedent to final payment, Agreement Form, and Release of Any and All Claims, discharging City of Pittsburg, their officers, agents, employees, and consultan ts (including, but not limited to Architect/Engineer and Construction Manager) of and from liabilities, obligations, and claims arising under Contract.
D. Final Payment Application: Administrative actions and submittal s that must precede or coincide with submittal of the final Application for Payment include the following:
1. Completion of Project closeout requirements.
2. Completion of items specified for completion after Substantial Completion.
3. Ensure that unsettled claims will be settled.
4. Ensure that incomplete Work is not accepted and will be completed without undue delay.
5. Transmittal of required Project construction records to the City.
6. Certified property survey.
7. Proof that taxes, fees, and similar obligations were paid.
8. Removal of temporary facilities and services.
9. Removal of surplus materials, rubbish, and similar elements. 247
City of Pittsburg, California December 2022
PAYMENT PROCEDURES 01 29 00 - 9
10. Change of door locks to City's access.
11. All as-built drawings.
12. Lien releases from Contractor and subcontractors.
1.10 EFFECT OF PAYMENT
A. Payment will be made by City, based on Project Manager's observations at the site and the data comprising the Application for Payment. Payment will not be a representation that Project Manager has:
1. made exhaustive or continuous on -site inspections to ch eck the quality or quantity of Work;
2. reviewed construction means, methods, techniques, sequences or procedures;
3. reviewed copies of requisitions received from subcontractors and material suppliers and other data requested by City to substantiate Contractor's right to payment; or
4. made examination to ascertain how or for what purpose Contractor has used money previously paid on account of the Contract Sum.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 29 00
248
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1
SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes requirements for coordination and meetings.
B. Related Sections:
1. Division 00 – General Conditions, Article 2
2. Section 01 32 16 - Construction Progress Schedule
1.2 COORDINATION
A. The Contractor shall be responsible for all Project coordination.
B. Duties of Contractor:
1. Coordinate Work of all subcontractors.
2. Establish on -site lines of authority and communication. Schedule and conduct progress meetings with City and subcontractors.
3. Construction schedules:
a. Prepare detailed schedule of operations of all subcontractors on Project in accordance with Section 01 32 16 – Construction Progress Schedule. b. Monitor and update schedules as Work progresses.
c. Observe Work to monitor compliance with schedule.
4. Temporary facilities:
a. Prepare temporary facilities site plan for City’s approval. b. Allocate space for temporary structures furnished by subcontractors. c. Monitor use of temporary utilities.
d. Verify that adequate services are provided to comply with requirements for Work and climatic conditions.
e. Coordinate traffic control.
f. Administer traffic and parking controls.
5. Changes:
a. Recommend necessary or desirable changes to Architect/Engineer. b. Review subcontractor's request for changes and for substitutions. c. Submit recommendations to Architect /Engineer, through the Project Manager.
d. Process Change Orders.
6. Permits and fees: Verify that subcontractors have obtained permits f or inspections.
7. Review all Shop Drawings, Product Data, and Samples for compliance with Contract Documents prior to submittal to Project Manager. 249
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2
8. Interpretation of Contract Documents:
a. Consult with Project Manager and Architect /Engineer to obtain interpretations.
b. Assist in resolution of questions which may arise.
c. Transmit written interpretations to concerned parties.
9. Maintain reports and records at Project Site:
a. Daily log progress of Work ; make available to Project Manager and Architect/Engineer.
b. Records.
c. Contracts.
d. Purchases.
e. Materials and equipment.
f. Applicable handbooks, codes and standards.
g. Obtain information from subcontractors and maintain record documents. Assemble documentation for handling of claims and disputes.
10. Verify that spec ified cleaning is done during progress of Work and at completion of each contract.
11. For project requiring building permit, coordinate with the Building Division, City of Pittsburg, for inspections.
12. Start-up:
a. Direct the checkout of utilities, operational systems and equipment. b. Assist in initial start-up testing.
c. Record dates of start of operation of systems and equipment. d. Submit to City written notice of beginning of Warranty period for equipment put in service.
1.3 COORDINATION REQUIREMENTS
A. Coordination: Contractor shall coordinate the Work as stated in the Division 00 – General Conditions. Contractor shall also coordinate Work under the Contract with work under separate contracts by City. Contractor shall cooperate with City and others as directed by City in scheduling and sequencing the incorporation into t he Work of City Furnished/Contractor installed products identified in the Contract Drawings, Special Conditions, and Specifications.
B. Relationship of Contract Documents: Drawings, Special Conditions , Specifications, and other Contract Documents in the Project Manual are intended to be complementary. What is required by one shall be as if required by all. What is shown or required, or may be reasonably inferred to be required, or that is usually and customarily provided for similar work, shall be included in the Work.
C. Discrepancies in Contract Documents: In the event of error, omission, ambiguity or conflict in Drawings, Special Conditions , or Specifications, Contractor shall bring the matter to the Architect /Engineer's attention, through the Project Manager, in a timely manner, for the Architect /Engineer's determination and direction in accordance with provisions of Division 00 – General Conditions. 250
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3
D. Construction Interfacing and Coordination: Layout, scheduling and sequencing of Work shall be solely Contractor's responsibility . Contractor shall bring together the various parts, components, systems, and assemblies as required for the correct interfacing and integration of all elements of Work.
E. Contractor shall coordinate Work to correctly and accurately connect abutting adjoining, overlapping and related elements, including work under separate contracts by City, utility agencies and companies.
1.4 COORDINATION OF SUBCONTRACTS AND SEPARATE CONTRACTS
A. Superintendence of Work: Contractor shall appoint a field superintendent who shall directly supervise and coordinate Work shown on the Drawings, Special Conditions, and in the Specifications at all times . In order to maintain an uninterrupted construction schedule, the field superintendent shall not be replaced by the Contractor, for oth er than extenuating circumstances, without prior approval by the Architect/Engineer and/or City.
B. Subcontractors, Trades and Materials Suppliers: Contractor shall require all subcontractors, trades, crafts and suppliers to coordinate their portions of Work with the Superintendent, Engineer and Construction Project Manager to prevent scheduling, sequencing, dimensional and other conflicts and omissions.
C. Coordination with Work under Separate Contracts: Contractor shall coordinate and schedule Work under the Contract with work being performed for Project under separate contracts by City, serving utilities and public agencies. Contractor shall make direct contacts with parties responsible for work of the Project under separate contracts, in order to provide tim ely notifications and to facilitate information exchanges.
1.5 PRECONSTRUCTION CONFERENCE
A. Project Manager will call for and administer Preconstruction Conference at time and place to be announced. Conference will occur as soon after award as can be reasonably scheduled.
B. Contractor, all subcontractors, and major suppliers shall attend Preconstruction Conference.
C. Agenda will include, but not be limited to, the following items:
1. Lines of Communication
2. Schedules
3. Employment Goals
4. Personnel
5. Use of premises
6. Location of Contractor's on-site facilities
7. Project access
251
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4
8. Employee parking
9. Security
10. NPDES Storm Water Pollution Prevention BMPs
11. Contractor’s Questions
12. Housekeeping
13. Submittals
14. Inspection and testing procedures, on-site and off-site
15. Utility shutdown procedures
16. Control and reference point survey procedures
17. Injury and Illness Prevention Program
18. Contractor's Initial CPM Schedule
19. Preparation of Record Documents.
D. Project Manager will distribute copies of minutes to attendees. Attendees shall have five (5) working days to submit comments or additions to minutes. Minutes will constitute final memorialization of results of the Preconstruction Conference.
1.6 SCHEDULING MEETINGS
A. Meet with Project Manager no later than Start Date of Contract and conduct initial review of Contractor's Initial Progress Schedule submittal, draft Shop Drawing and Sample Submittal Schedule, and draft Schedule of Values ("Schedule Review Meeting").
B. Authorized representative in Contractor's organization, designated in writing, who will be responsible for working and coordinating with Project Manager's representative(s) relative to preparation and maintenance of Progress Schedule, shall attend initial Schedule Review Meeting.
C. Contractor shall, within thirty (30) calendar days from the Notice to Proceed date, meet with City to review Contractor's Original CPM Schedule submittal, and final Shop Drawing and Sample Submittal Schedule, and final Schedule of Values.
1. Contractor shall have its manager, superintendent, scheduler, and key subcontractor representatives, as required by City, in attendance. The meeting will take place over a continuous one-day period.
2. City's review of Schedule Submittals will be limited to conformance to Contract requirements, including, but not limited to, coordination requirements. However, review may also include:
a. Clarifications of Contract Requirements
b. Directions to include activities and information missing from submittal c. Requests to Contractor to clarify its schedule
3. Within five (5) working days of the initial Sche dule Review Meeting, Contractor shall respond in writing to all questions and comments expressed by City at the meeting.
D. Project Manager will administer scheduling meetings and shall distribute minutes of scheduling meetings to attendees. Attendees shall have five (5) working days 252
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5
to submit comments or additions to minutes. Minutes will constitute final memorialization of results of the scheduling meetings.
1.7 PROGRESS MEETINGS
A. A progress meeting will be held weekly to review the schedule update submittal and progress payment application. At this meeting, at a minimum, the following items will be reviewed:
1. Previous meeting notes.
2. Percent complete of each activity
3. Time impact evaluations for Change Orders and Time Extension Request
4. Actual and anticipated activity sequence changes
5. Actual and anticipated duration change
6. Actual and anticipated contractor delays
7. Interface requirement
8. Status on submittals
9. Documentation of information for payment request.
B. These meetings are considered a critical component of overall monthly schedule update submittal and Contractor shall have appropriate personnel attend. At a minimum, these meetings shall be attended by Contractor's General Superintendent and Scheduler.
C. Project Manager will record and distribute minutes to Contractor, Building and/or Special Inspector, Architect/Engineer, and all other participants, and those affected by decisions made at the meeting, within five (5 ) working days after the meeting. Attendees shall have five (5) working days to submit comments or additions to the minutes. The Minutes will constitute final memorialization of the results of the progress meeting.
1.8 SPECIAL MEETINGS
A. Special meetings may be called by any party by notifying all desired participants, Project Manager, and Building and/or Special Inspector five (5) working days in advance, giving reason for meeting. Special Meetings may be held without advance notice in emergency situations.
B. At any time during the progress of the Work, any party shall have the right to require attendance at conference, and notice of such conference shall be duly observed and complied with by Contractor.
C. Contractors shall schedule and conduc t coordination meetings as necessary to discharge coordination responsibilities in Division 00 – General Conditions .
Project Manager shall be given five (5) working days written notice of coordination meetings. Contractors shall maintain minutes of coordination meetings.
Attendees shall have five (5) working days to submit comments or additions to minutes. Minutes will constitute final memorialization of results of the meetings. 253
City of Pittsburg, California December 2022
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 6
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 31 00
254
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1
SECTION 01 32 00 – CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Preconstruction photographs and videos.
2. Periodic construction photographs and videos.
B. Submittals:
1. Key Plan: Submit key plan of project site and construction with notation of vantage points marked for location and direction of each photograph and video.
2. Construction Photographs: Submit digital copy of photographs in PDF and JPEG form in a CD or a USB flash drive with a folder containing pictures of each street in subfolders.
3. Identification: Identify the project by Contract Number. Identify each photograph by naming it according to the station number on the drawings.
Example: Sta 10+00 looking northeast; Sta 12+30 looking west.
4. Digital Images:
a. General: Identify electronic media with date photographs were taken.
Submit images that have same aspect ratio as the sensor, uncropped. b. Usage Rights: Submit statement of transfer copyright usage rights to City allowing unlimited reproduction of photographic documentation.
5. Video:
a. General: Submit videos on acceptable electronic transfer medium to the Project Manager, accompanied by a detailed log , inc luding descriptions and corresponding counter numbers to facilitate the quick location of information . Videos will be maintained by the Project Manager during construction and may be viewed at any time by Contractor upon request. Upon final acceptance, the videos w ill become the permanent property of the City.
b. Submit video documentations to the Project Manager prior to start of construction work and as otherwise required.
c. Usage Rights: Submit statement of transfer copyright usage rights to City allowing unlimited reproduction of videographic documentation.
PART 2 - PRODUCTS
2.1 PHOTOGRAPHIC MEDIA
A. Digital Images: Provide images capable of a digital capture resolution of not less than 2240x1680 - 4 Megapixels.
255
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2
B. Videos: Provide videos in high resolution digital format with audio capability.
PART 3 - EXECUTION
3.1 CONSTRUCTION PHOTOGRAPHS
A. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out -of-focus areas will not be accepted.
B. Key Plan: Maintain with each set of construction photographs that identifies each photographic location.
C. Digital Images:
1. General: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
2. Date and Time: Include date and time in filename for each image.
3. Field Office Images: Main tain one set of images on acceptable electronic transfer medium.in the field office at Project Site, available at all times for reference. Identify images same as for those submitted to Project Manager.
D. Preconstruction Photographs:
1. General: Before starting construction, take color photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Project Manager.
2. Construction Limits: Flag before taking construction photographs.
3. Adjacent Conditions:
a. General: Take three (3) color photographs, from different views, to show existing conditions adjacent to property before starting the Work. b. Existing Buildings: Take three (3) color photographs, different views, of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
3.2 CONSTRUCTION VIDEOS
A. Preconstruction Videos: Document existing conditions of adjacent areas (curbs, gutters, sidewalks, driveways, private improvements immediately adjacent to the project site, roadway pavement, access roads, landscaping, etc.) that might be affected by construction operations. Take care to record all existing conditions which exhibit deterioration, imperfections, structural failures, or situations that would be considered substandard.
B. All Videos: Provide temporary lighting as necessary to properly videotape areas where natural lighting is insufficient (shadows, etc.). Include an audio soundtrack to provide the following information:
256
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 3
1. Detailed description of location being viewed.
2. Direction (N, E, S, W, looking up, looking down, etc.) of camera view.
3. Date, time, temperature, environmental conditions at time of videotaping.
4. Describe in detail areas not readily visi ble by video. Unless otherwise approved by the Project Manager, do not perform videotaping during inclement weather or when the ground is covered partially or totally with leaves or debris.
END OF SECTION 01 32 00
257
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 1
SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Scheduling of Work under this Contract shall be performed by Contractor in accordance with requirements of this Section.
1. Development of schedule, cost and resource loading of the schedule, monthly payment requests and project status reporting requirements of the Contract shall employ scheduling as required in this Document.
2. The Schedule shall be cost loaded based on Schedule of Values as approved by City.
3. Submit sche dules and reports as specified in Division 00 – General Conditions.
B. Upon Award of Contract, Contractor shall immediately commence development of Initial Schedule to ensure compliance with schedule submittal requirements.
C. Related Sections
1. Contract
2. Division 00 – General Conditions, Article 5
3. Section 01 10 00 – Summary
4. Section 01 29 00 – Payment Procedures
5. Section 01 31 00 – Project Management and Coordination
6. Section 01 33 00 – Submittal Procedures
1.2 GENERAL
A. Progress Schedule shall be based on and incorporate milestone and completion dates specified in Contract Documents.
B. Overall time of completion and time of completion for each milestone shown on Progress Schedule shall adhere to times in the Contract, unless an earlier (advanced) time of completion is requested by Contractor and agreed to by City.
Any such agreement shall be formalized by a Change Order.
1. City is not required to accept an earlier (advanced) schedule, i.e., one that shows early completion dates for the Contract Times.
2. Contractor shall not be entitled to extra compensation in event agreement is reached on an earlier (advanced) schedule and Contractor completes its Work, for whatever reason, beyond completion date shown in earlier (advanced) schedule but within the Contract Times.
3. A schedule showing the work completed in less than the Contract Times, which has been accepted by City, shall be considered to have Project Float.
The Project Float is the time between the scheduled completion of the work 258
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 2
and Contract Substantial Completion. Project Float is a resource available to both City and Contractor.
C. Progress Schedule shall be the basis for evaluating job progress, payment requests, and time extension requests. Responsibility for developing Contract schedule and monitoring actual progress as compared to Progress Schedule rests with Contractor.
D. Failure of Progress Schedule to include any element of the Work or any inaccuracy in Progress Schedule will not relieve Contractor from responsibility for accomplishing the Work in accordance with the Contract. City's acceptance of Schedule shall be for its use in monitoring and evaluating job progress, payment requests, and time extension requests, and shall not, in any manner, impose a duty of care upon City, or act to re lieve Contractor of its responsibility for means and methods of construction.
E. Transmit each item per Section 01 33 00 – Submittal Procedures under form approved by City.
1. Identify Project with the City Contract number, and name of Contractor.
2. Provide space for Contractor's approval stamp and City's review stamps.
3. Submittals received from sources other than Contractor will be returned to Contractor without City's review.
1.3 INITIAL AND ORIGINAL SCHEDULE
A. Initial Schedule submitted for review at the pre-construction conference shall serve as Contractor's schedule for up to thirty (30) calendar days after the Notice to Proceed.
B. Indicate detailed plan for the Work to be completed in first thirty (30) calendar days of the Contract; details of planned mobilization of plant and equipment; sequence of early operations; and procurement of materials and equipment. Show Work beyond thirty (30) calendar days in summary form.
C. Original (or “Baseline”) Schedule shall be submitted for review no later than Contractor’s first progress payment application submittal.
D. All schedules shall be time-scaled.
E. All schedules shall be cost and resource loaded. Accepted cost and resource loaded schedule will be used as basis for monthly progress payments. Use of Initial Schedule for progress payments shall not exceed thirty (30) calendar days.
F. City and Contractor shall meet to review and discuss the Schedule within seven (7) calendar days after it has been submitted to City.
1. City's review and comment on the schedule shall be limited to Contract conformance (with sequencing, coordination, and milestone requirements). 259
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 3
2. Contractor shall make corrections to Schedule necessary to comply with Contract requirements and shall adjust Schedule to incorporate any missing information requested by City. Contractor shall resubmit Initial Schedule if requested by City.
1.4 CONSTRUCTION SCHEDULE FORMAT AND LEVEL OF DETAIL
A. The Construction Schedule is to indicate all sepa rate fabrication and field construction activities required for completion of the work, including but not limited to the following:
1. All Contractor, Subcontractor and assigned Contractor work shall be shown in a logical work sequence that demonstrates a coordinated plan of work for all contractors. The intent is to provide a common basis of acceptance, understanding and communication, as well as interface with other contractors.
2. Activities related to the delivery of City-furnished equipment to be contractor- installed per Contract shall be shown.
3. All activities shall be identified through codes or other identification to indicate the building (i.e. buildings, site work) and Contractor/subcontractor responsibility to which they pertain.
4. Contractor shall break u p the work schedule into activities of durations of approximately fifteen (15) calendar days or less each, except for non -field construction activities or as otherwise deemed acceptable by the Project Manager.
B. Seasonal weather conditions (which do not constitute a delay as defined herein) shall be considered in the planning and scheduling of all work influenced by high or low ambient temperatures or presence of high moisture for the completion of the work within the allotted contract time.
C. In conformance with the Contract Documents Contractor shall furnish a breakdown of the bid by assigning dollar values (cost estimated) to each applicable network activity, which cumulatively equals the bid. Upon acceptance by City, the values will be used as the basis for determining progress payments. Contractor's overhead, profit, and cost of bonds and insurance, shall be prorated through all activities.
D. Failure by Contractor to include any element of work required for performance of the work on the detailed construction schedule shall not excuse Contractor from completing all work required within the Contract time.
E. A two-week "look ahead" detailed, daily bar chart schedule shall be updated and issued weekly, no later than the time of the scheduled weekly meeting.
F. Contractor shall utilize computer scheduling software, such as PRIMAVERA or approved equivalent software for all scheduling including schedule updates. 260
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 4
Contractor shall supply computer data files for all schedules including the original schedule and monthly schedule updates.
1.5 MONTHLY SCHEDULE UPDATE SUBMITTALS
A. Following acceptance of Contractor's Initial Schedule, Contractor shall monitor progress of Work and adjust schedule each month to reflect actual progress and any anticipated changes to planned activities.
1. Each schedule update submitted shall be complete, including all information requested for the Initial Schedule submittal.
2. Each update shall continue to show all work activities including those already completed. These completed activities shall accurately ref lect "as built" information by indicating when activities were actually started and completed.
B. A meeting will be held after the first Project Meeting of each month to review the schedule update submittal and progress payment application.
1. At this meeting, at a minimum, the following items will be reviewed: percent complete of each activity; time impact evaluations for change orders and time extension requests; actual and anticipated activity sequence changes; actual and anticipated duration changes; and actual and anticipated contractor delays.
2. These meetings are considered a critical component of overall monthly schedule update submittal and Contractor shall have appropriate personnel attend. At a minimum, these meetings shall be attended by Contractor's General Superintendent and Scheduler.
3. Contractor shall plan on the meeting taking no less than two (2) hours.
C. Within five (5) working days after monthly schedule update meeting, Contractor shall submit the updated Schedule update.
D. Within five (5) working days of receipt of above noted revised submittals, City will either accept or reject monthly schedule update submittal.
1. If accepted, percent complete shown in monthly update will be basis for Application for Payment by Contractor. T he schedule update shall be submitted as part of Contractor’s Application for Payment.
2. If rejected, update shall be corrected and resubmitted by Contractor before the Application for Payment is submitted.
E. Neither updating, changing or revising of any report, curve, schedule or narrative submitted to City by Contractor under this Contract, nor City's review or acceptance of any such report, curve, schedule or narrative, shall have the effect of amending or modifying, in any way, the Contract Substantial Completion date or milestone dates or of modifying or limiting, in any way, Contractor's obligations under this Contract.
261
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 5
1.6 SCHEDULE REVISIONS
A. Updating the Schedule to reflect actual progress shall not be considered revisions to the Schedule. Since scheduling is a dynamic process, revisions to activity durations and sequences are expected on a monthly basis.
B. To reflect revisions to the schedule, Contractor shall provide City with a written narrative with a full description and reasons for each Work activity revis ed. For revisions affecting the sequence of work, Contractor shall provide a schedule diagram which compares the original sequence to the revised sequence of work.
Contractor shall provide the written narrative and schedule diagram for revisions two (2) calendar days in advance of the monthly schedule update meeting.
C. Schedule revisions shall not be incorporated into any schedule update until the revisions have been reviewed by City. City may request further information and justification for schedule revisions and Contractor shall, within three (3) calendar days, provide City with a complete written narrative response to City's request.
D. If Contractor's revision is still not accepted by City, and Contractor disagrees with City's position, Contractor has seven (7) calendar days from receipt of City's letter rejecting the revision, to provide a written narrative providing full justification and explanation for the revision. Contractor's failure to respond in writing within seven (7) calendar days of City's writte n rejection of a schedule revision shall be contractually interpreted as acceptance of City's position, and Contractor waives its rights to subsequently dispute or file a claim regarding City's position.
E. At City's discretion, Contractor can be required to provide subcontractor certifications of performance regarding proposed schedule revisions affecting said subcontractors.
1.7 RECOVERY SCHEDULE
A. If the Schedule Update shows a substantial completion date twenty -one (21) calendar days beyond the Contract Substant ial Completion date, or individual milestone completion dates, Contractor shall submit to City the proposed revisions to recover the lost time within seven (7) calendar days. As part of this submittal, Contractor shall provide a written narrative for each revision made to recapture the lost time. If the revisions include sequence changes, Contractor shall provide a schedule diagram comparing the original sequence to the revised sequence of work.
B. The revisions shall not be incorporated into any schedule update until the revisions have been reviewed by City.
C. If Contractor's revisions are not accepted by City, City and Contractor shall follow the procedures in paragraph 1.6.C, 1.6.D and 1.6.E above. 262
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 6
D. At City's discretion, Contractor can be required to provide su bcontractor certifications for revisions affecting said subcontractors.
1.8 TIME EXTENSIONS
A. Contractor is responsible for requesting time extensions for time impacts that, in the opinion of Contractor, impact the critical path of the current schedule update.
Notice of time impacts shall be given in accord with Division 00 – General Conditions, Article 5.
B. Where an event for which City is responsible impacts the projected Substantial Completion date, Contractor shall provide a written mitigation plan, including a schedule diagram, which explains how the impact can be mitigated (e.g., increase crew size, overtime, etc.). Contractor shall also include a detailed cost breakdown of the labor, equipment and material Contractor would expend to mitigate City caused time impact. Contractor shall submit its mitigation plan to City within ten (10) working days from the date of discovery of said impact. Contractor is responsible for the cost to prepare the mitigation plan.
C. Failure to request time or provide the required mitigation plan will result in Contractor waiving its right to a time extension and cost to mitigate the delay.
D. No time will be granted under this Contract for cumulative effect of changes.
E. City will not be obligated to consider any time extension request unless requirements of Contract Documents are satisfied.
F. Failure of Contractor to perform in accordance with the current schedule update shall not be excused by submittal of time extension requests.
1.9 PROJECT STATUS REPORTING
A. In addition to submittal requirements for scheduling identified in this Section, Contractor shall provide a monthly project status report (i.e., written narrative report) to be submitted in conjunction with each Schedule as specified herein.
Status reporting shall be in form specified below.
B. Contractor shall prepare monthly written narrative reports of status of Project for submission to City. Written status reports shall include:
1. Status of major Project components (percent complete, amount of time ahead or behind schedule) and an explanation of how Project will be brought back on schedule if delays have occurred.
2. Progress made on critical activities indicated on Schedule, inspections and visits by the Building and/or Special Inspection Inspector.
3. Explanations for any lack of work on critical path activities planned to be performed during last month.
4. Explanations for any schedule changes, including changes to logic or to activity durations.
263
City of Pittsburg, California December 2022
CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 7
5. List of critical activities scheduled to be performed next month.
6. Status of major material and equipment procurement.
7. Any delays encountered during reporting period.
8. Contractor shall provide a printed report indicating actual versus planned resource loading for each trad e and each activity. This report shall be provided on weekly and monthly basis.
a. Actual resource shall be accumulated in field by Contractor, and shall be as noted on Contractor's daily reports. These reports will be basis for information provided in monthly and weekly printed reports. b. Contractor shall explain all variances and mitigation measures.
9. Contractor may include any other information pertinent to status of Project.
Contractor shall include additional status information requested by City at no additional cost.
10. Status reports, and the information contained therein, shall not be construed as claims, notice of claims, notice of delay, or requests for changes or compensation.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 32 16
264
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 1
SECTION 01 33 00 – SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes general requirements for submittals for the Work:
1. Procedures
2. Schedule of Shop Drawing and Sample Submittals
3. Safety Plan
4. Progress Schedule
5. Product Data
6. Shop drawings
7. Samples
8. Quality Control Submittals
a. Design Data
b. Test Reports
c. Certificates
d. Manufacturers' Instructions
9. Machine Inventory Sheets
10. Operations and Maintenance Manuals
11. Keys
12. Project Record Documents
B. Related Sections:
1. Division 00 – General Conditions, Article 2
2. Section 01 10 00 - Summary
3. Section 01 25 00 – Substitution Procedures
4. Section 01 26 00 – Contract Modification Procedures
5. Section 01 29 00 – Payment Procedures
6. Section 01 32 16 – Construction Progress Schedule
7. Section 01 78 00 – Closeout Submittals
1.2 PROCEDURES
A. Upon issuance of the “Notice to Proceed”, the Contractor shall have thirty-five (35) calendar days to submit, at Contractor/Vendor expense, sets of the following:
Schedule of Shop Drawing and Sample Submittals, Safety Plans, Progress Schedule, Product Data, Shop Drawings, Samples, Quality Control Data, Machine Inventory Sheets, Operations and Maintenance Manuals, and Project Record Documents required by the Contract Documents. Submit these submittals to Project Manager for review and approval in accordance with accepted schedule of Shop Drawings and Samples submittals.
265
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 2
B. Transmit each item with a standard letter of transmittal. Identify project, Contractor, subcontractor, major supplier, pertinent drawing sheet and detail number, technical specifications, and specification section number as appropriate. Provide space for Contractor, Project Manager and Architect/Engineer review stamps. Where manufacturer's standard drawings or data sheets are used, they shall be marked clearly to show those portions of the data which are applicable to this project. The transmittal sheet will include the following:
1. Date
2. Project and Contract Name and Number
3. Subcontractor or supplier as appropriate
4. Trade
5. Contractor Review Stamp
C. The data shown on the Shop Drawings shall be complete with respect to quantities, dimensions, specified performance and design criteria, materials and similar data to show Project Manager and Architect/Engineer the materials and equipment Contractor proposes to provide and to enable Project Manager and Architect/Engineer to review the information for the limited purposes specified below. Samples shall be identified clearly as to material, supplier; pertinent data such as catalog numbers and the use for which it is intended and otherwise as Project Manager and Architect/Engineer may require enabling Project Manager and Architect/Engineer to review the submittal.
D. At the time of each submission, Contractor shall give City specific written notice of all variations, if any; that the Shop Drawing or Sample submitted may have from the requirements of the Contract Documents, and the reasons therefore. This written notice shall be a separate document from the submittal. In addition, Contractor shall cause a specific notation to be made on each Shop Drawing and Sample submitted to City for review and approval of each such variation. If City accepts deviation, City shall issue appropriate Contract Modification.
E. Submittal coordination and verification of contract compliance is responsibility of Contractor; this responsibility shall not be delegated in whole or in part to subcontractors or suppliers. Before submitting each Sho p Drawing or Sample, Contractor shall have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents, and shall have determined and verified:
1. All field measure ments, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers and similar information with respect thereto;
2. All materials with respect to intended use, fabrication, shipping, handling, storage, assembly and installation pertaining to the performance of the Work; and
3. All information relative to Contractor's sole responsibilities and of means, methods, techniques, sequences and procedures of construction and safety precautions and programs incident thereto.
266
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 3
F. Contractor's submission to City of a Shop Drawing or Sample submittal will constitute Contractor's representation that it has satisfied its obligations under the Contract Documents, and as set forth immediately above, with respect to Contractor's review and approval of that submittal.
G. After review by Project Manager and Architect/Engineer of each of Contractor's submittals, one set of materials will be returned to Contractor with actions defined as follows:
1. NO EXCEPTIONS TAKEN - Accepted subject to its compatibility with future submittals and additional partial submittals for portions of the work not covered in this submittal. Does not constitute approval or deletion of specified or required items not shown on the submittal.
2. MAKE CORRECTIONS NOTED (NO RES UBMISSIONS REQUIRED) - Same as 1. above, except that minor corrections as noted shall be made by Contractor.
3. AMEND AND RESUBMIT - Rejected because of major inconsistencies or errors which shall be resolved or corrected by Contractor prior to subsequent review by Project Manager and Architect/Engineer.
4. REJECTED - RESUBMIT - Submitted material does not conform to Plans and Specifications in major respect, i.e.: wrong size, model, capacity, or material.
H. It is considered reasonable that Contractor shall make a complete and acceptable submittal at least by second submission. City reserves the right to deduct monies from payments due Contractor to cover additional costs of Project Manager's and Architect/Engineer's review beyond the second submission. Illegible submittals will be rejected and returned to Contractor for resubmission.
I. Favorable review will not constitute acceptance by City of any responsibility for the accuracy, coordination and completeness of the submittals. Accuracy, coordination, and completeness of Submittals shall be sole responsibility of Contractor, including responsibility to back check comments, corrections, and modifications resulting from City's review which shall be incorporated in design before fabrication. Submittals may be prepared by Contractor, subcontractors, or suppliers, but Contractor shall ascertain that submittals meet requirements of Contract Documents, while conforming to structural space and access conditions at point of installation. Project Manager and Architect/Engineer's review will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as indicated by the Contract Documents. Favorable review of submittal, method of work, or information regarding materials and equipment Contractor proposes to furnish shall not relieve Contractor of responsibility for errors therein and shall not be regarded as assumption of risks or liability by Architect/Engineer or City, or any officer or employee thereof, and Contractor shall have no claim under Contract on account of failure or partial failure or inefficiency or insufficiency of any plan or method of work or material and equipment so accepted. Favorable review shall be considered to mean merely that Architect/Engineer or City has no objection to 267
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 4
Contractor using, upon his own full responsibility, plan or method of work proposed, or furnishing materials and equipment proposed.
J. City’s review shall not be construed as approval of means, methods, techniques, sequences or procedures of construction or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions.
K. Submit complete initial submittal for those items where required by individual technical specifications, or specification sections. Complete submittal shall contain sufficient data to demonstra te that items comply with Specifications, shall meet minimum requirements for submissions cited in technical specifications, shall include motor data and seismic anchorage certifications, where required, and shall include necessary revisions required for e quipment other than first named. If Contractor submits incomplete initial submittal, when complete submittal is required, submittal may be returned to Contractor without review.
L. It shall be Contractor's responsibility to copy, conform and distribute review ed submittals in sufficient numbers for Contractor's files, subcontractors and vendors.
M. After Project Manager's and Architect/Engineer's review of submittal, revise and resubmit as required. Identify changes made since previous submittal.
1. Begin no fabrication or work which require submittals until return of submittals not requiring re-submittal.
2. Normally, submittals will be processed and returned to Contractor within fifteen (15) calendar days of receipt.
N. Distribute copies of reviewed submittals to concerned persons. Instruct recipients to promptly report any inability to comply with provisions.
1.3 SCHEDULE OF SHOP DRAWING AND SAMPLE SUBMITTALS
A. Submit preliminary Schedule of Shop Drawing and Sample Submittals as required by Division 00 - General Conditions or as elsewhere specified in the Contract Documents. Submit three (3) copies and PDF of final and accepted schedule of submittals of shop drawings and samples as required by Division 00 - General Conditions, and in no event later than thirty-five (35) calendar days following Notice to Proceed.
B. Schedule of Shop Drawing and Sample Submittals will be used by Project Manager and Architect/Engineer to schedule their activities relating to review of submittals.
Schedule of submittals shall indicate a spreading out of submittals and early submittals of long-lead-time items and of items which require extensive review.
C. Schedule of Shop Drawing and Sample Submittals shall be reviewed by Project Manager and shall be revised and resubmitted until accepted by Project Manager. 268
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 5
1.4 SAFETY PLAN
A. Submit three (3) copies of Safety Plan specific to this Contract to Project Manager within fifteen (15) calendar days of issuance of the Notice to Proceed.
B. One (1) copy of accepted Safety Plan will be returned to Contractor.
C. No on-site work shall be started until Safety Plan has been reviewed and accepted by City. Acceptance of Safety Plan shall not affe ct Contractor's responsibility for maintaining a safe working place and instituting safety programs in connection with project.
1.5 PROGRESS SCHEDULE
A. See Section 01 32 16 – Construction Progress Schedule for schedule and report requirements.
B. Submit three (3) copies and PDF of schedule at each of the following times:
1. Initial CPM Schedule at the Preconstruction Conference (covering in detail first thirty (30) calendar days of contract performance, and at a summary level for remainder of contract).
2. Original CPM Schedule within thirty (30) calendar days of the Notice to Proceed date (covering in detail entire Work of Contract to completion).
3. Adjustments to the CPM Schedule as required.
4. CPM Schedule updates weekly, two (2) calendar days prior to weekly progress meeting.
C. Submit three (3) copies and PDF of the reports listed in Section 01 32 16 – Construction Progress Schedule with:
1. Initial CPM Schedule
2. Original CPM Schedule
3. Each weekly Schedule update
D. Progress Schedules and Reports shall be submitted electronically and stored in a USB flash drive in addition to hard copies specified above.
1.6 PRODUCT DATA
A. Within ten (10) calendar days after Start Date of the Contract Times, submit copies of complete list of major products and equipment proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
C. Tabulate products by Special Conditions and Specification Section Number. 269
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 6
D. Supplemental Data: Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturer's standard data to provide information unique to Project.
E. Provide copies for Project Record Documents described in Section 01 78 00 – Closeout Submittals.
1.7 SHOP DRAWINGS
A. Submit three (3) copies and PDF of shop drawings.
B. Minimum Sheet Size: 8 -1/2 inches by 11 inches. All others: Multiples of 8 -1/2 inches by 11 inches, 22 inches by 34 inches (ANSI D) maximum.
C. Original sheet or reproducible transparency will be marked with Project Manager's and/or Architect/Engineer’s review comments and returned to Contractor.
D. Mark each copy to identify applicable Products, models, options, and other data; supplement manufacturers' standard data to provide information unique to Work.
E. Include manufacturers' installation instructions when required by technical specifications or specification section.
1.8 SAMPLES
A. Submit full range of manufacturers' standard colors, textures, and patterns for Project Manager's selection where not indicated in documents or for substitutions or “equals”.
B. Submit samples to illustrate functional and aesthetic characteristics of Product, with integral parts and attachment devices. Coordinate submittal of different categories for interfacing work.
C. Include identification on each sample, giving full information.
D. Submit three (3) samples unless otherwise specified.
E. Sizes: Unless otherwise specified, provide the following:
1. Paint Chips: Manufacturers' standard.
2. Flat or Sheet Products: Minimum 6 inches square, maximum 12 inches square.
3. Linear Products: Minimum 6 inches, maximum 12 inches long.
4. Bulk Products: Minimum 1 pint, maximum 1 gallon.
F. Full size samples may be used in Work upon approval.
G. Mock-ups:
270
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 7
1. Erect field samples and mock -ups at Project site in accordance with requirements of Special Conditions or Specification sections.
2. Modify or make additional field samples and mock-ups as required to provide appearance and finishes approved by Project Manager.
3. Approved field samples and mock-ups may be used in Work upon approval.
1.9 QUALITY CONTROL SUBMITTALS
A. Design Data: Three (3) copies and PDF.
B. Test Reports: Three (3) copies and PDF.
1. Indicate that material or product conforms to or exceeds specified requirements.
2. Reports may be from recent or previous tests on material or product, but must be acceptable to Project Manager. Comply with requirements of each individual technical specifications or specification Section.
C. Certificates: Three (3) copies and PDF.
1. Indicate that material or product conforms to or exceeds specified requirements.
2. Submit supporting reference data, affidavits, and certifications as appropriate.
3. Certificates may be recent or from previous test results on material or product, but must be acceptable to Project Manager.
D. Manufacturers' Instructions: Three (3) copies and PDF.
1. Include manufacturer's printed instructions for delivery, stora ge, assembly, installation, startup, adjusting, and finishing.
2. Identify conflicts between manufacturer's instructions and Contract Documents.
1.10 MACHINE INVENTORY SHEETS
A. Submit three (3) copies of machine inventory sheets including inventory list for spare pa rts and materials. If necessary, copies will be marked with Project Manager's and/or Architect/Engineer's review comments and returned to Contractor for correction until satisfactory information is provided. City will retain satisfactorily corrected sheets for its own use.
1.11 OPERATIONS AND MAINTENANCE MANUALS
A. Submit three (3) copies and PDF of manufacturers' operations and maintenance manuals. If necessary, copies will be marked with City's review comments and returned to Contractor for correction until satisfactory information is provided. City will retain satisfactorily corrected manuals for its own use.
B. Operations and maintenance manuals shall include the following as appropriate:
1. Operating instructions.
2. Preventive maintenance instructions.
271
City of Pittsburg, California December 2022
SUBMITTAL PROCEDURES 01 33 00 - 8
3. Cleaning instructions.
4. Safety precautions.
5. Trouble shooting procedures.
6. Theory of operation to discrete component level.
7. Schematic diagrams, flow diagrams, wiring diagrams, logic diagrams, etc. to discrete component level.
8. Parts lists showing all discrete components with part number, current prices and availability.
9. List of replaceable supplies; paper, ink, ribbon, etc. with part numbers, current prices and availability.
10. Recommended levels of spare parts and supplies to keep on hand.
11. Manufacturers' service and maintenance technical manuals.
12. Names, addresses and telephone numbers of service and repair firms for the equipment.
C. Manuals shall be the same as are used by manufacturers' authorized technicians to completely service and repair the equipment.
1.12 KEYS
A. Submit two (2) complete sets of keys for the Project and all related facilities.
B. Submit an inventory list of keys.
1.13 PROJECT RECORD DOCUMENTS
A. Submit copies of each of the Project Record Documents as listed in Section 01 78 00 – Closeout Submittals.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 33 00
272
City of Pittsburg, California December 2022
REGULATORY REQUIREMENTS 01 41 00 - 1
SECTION 01 41 00 – REGULATORY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes some of the key regulatory requirements applicable to Contract, provided for the Contractor’s convenience only, and not intended as a complete list of all currently applicable regulatory requirements.
1.2 REFERENCES TO REGULATORY REQUIREMENTS
A. Codes, laws, ordinances, rules and regulations referred to shall have full force and effect as though printed in full in these specifications.
B. Conform to referenced codes, laws, ordinances, rules and regulations which are in effect on date of receipt of bids.
1.3 CODES
A. Codes which apply to Contract include, but are not limited to, the following:
1. California Building Code (CBC) – Latest Edition:
a. California Administrative Code: Title 24, Part 1.
b. California Building Code: Title 24, Part 2 (Includes the California Historical Building Code, Part 8 and California Existing Building Code, Part 10).
c. California Residential Code: Title 24, Part 2.5
d. California Electrical Code: Title 24, Part 3.
e. California Mechanical Code: Title 24, Part 4.
f. California Plumbing Code: Title 24, Part 5.
g. California Energy Code: Title 24, Part 6.
h. California Fire Code: Title 24, Part 9.
i. California Green Building Standards Code (CALGreen): Title 24, Part
11. j. California Referenced Standards Code: Title 24, Part 12.
1.4 LAWS, ORDINANCES, RULES AND REGULATIONS
A. During prosecution of Work to be done under Contract, comply with applicable laws, ordinances, rules and regulations, including, but not limited to, the following:
1. Federal/National:
a. Americans with Disabilities Act (ADA) : Latest edition ; Civil Rights Division, Office on the Americans with Disabilit ies Act, U.S.
Department of Justice
273
City of Pittsburg, California December 2022
REGULATORY REQUIREMENTS 01 41 00 - 2
b. National Fire Protection Association (NFPA): Life Safety Code - NFPA 101.
c. U. S. Environmental Protection Agency (EPA): Laws and regulations. d. 29 CFR, Section 1910.1001, Asbestos
e. 40 CFR, Subpart M, National Emission Standards for Asbestos f. Executive Order 11246
2. State of California:
a. California Code of Regulations, Titles 5, 8, 19, 21, 24 b. California Education Code
c. California Public Contract Code
d. California Health and Safety Code
e. California Government Code
f. California Labor Code
g. California Civil Code
h. California Code of Civil Procedure
i. CPUC General Order 95, Rules for Overhead Electric Line Construction
j. CPUC General Order 128, Rules for Construction of Underground Electric Supply and Communications Systems
3. State of California Agencies:
a. State and Consumer Services Agency
b. Department of Industrial Relations – Public Works
c. Office of the State Fire Marshal
d. California Environmental Protection Agency (CalEPA) : State regulations and standards.
e. California Integrated Waste Management Board:
1) General: Sustainable Building Guidelines.
2) Construction Waste Management: Construction and Demolition Debris Recycling.
f. California State Water Resources Control Board (SWRCB) : SWPPP Standards.
g. California Department of Toxic Substances Control (DTSC):
Hazardous Waste Management standards.
4. City Codes:
a. Pittsburg Municipal Code
5. Local Agencies:
a. Bay Area Air Quality Management
b. County of Contra Costa
c. City of Pittsburg
1.5 RESERVED
PART 2 - PRODUCTS
NOT USED
274
City of Pittsburg, California December 2022
REGULATORY REQUIREMENTS 01 41 00 - 3
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 41 00
275
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 1
SECTION 01 42 00 – REFERENCES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. This section includes reference standards, symbols and definitions used in Contract Documents.
2. Material and workmanship specified by reference to number, symbol, or title of specific standard such as state standard, commercial standard, federal specifications, technical society, or trade association standard, or other similar standard shall comply with requirements of standards except when more rigid requirements are specified or required by applicable codes.
3. Standards referred to, except as modified herein, shall have full force and effect as though printed in the Contract Documents. Standards are not furnished to Contractor, since manufacturers and trades involved are assumed to be familiar with their requirements.
1.2 REFERENCE TO STANDARDS AND SPECIFICATIONS OF TECHNICAL SOCIETIES; REPORTING AND RESOLVING DISCREPANCIES:
A. Latest in Effect: Reference to standards, specifications, manuals or codes of any technical society, organization or association, or to the laws or regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard, specification, manual, code or laws or regulations in effect at the time of opening of Bids, except as may be otherwise specifically stated in the Contract Documents.
B. Discrepancies: If during the performance of the Work, Contractor discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any provision of any such law or regulation applicable to the performance of the Work or of any such standard, specification, manual or code or of any instruction of any supplier, Contractor shall report it in writing at once to Inspector, wi th copies to Project Manager and Architect/Engineer, and Contractor shall not proceed with the Work affected thereby until consent to do so is given by Project Manager.
C. Precedence: Except as otherwise specifically stated in the Contract Documents, including Division 00 – General Conditions, Article 3, or as may be provided by Change Order, or supplemental instruction, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Documents and:
276
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 2
1. The provisions of any such standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Contract Documents); or
2. The provisions of any such laws or regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such law or regulation).
3. No provision of any such standard, specification, manual, code or instruction shall be effective to change the duties and responsibilities of City, Contractor, Project Manager, or Architect/Engineer, or any of their subcontractors, consultants, agents, or employees, from those set forth in the Contract Documents, nor shall it b e effective to assign to City, Architect/Engineer, Project Manager, or any of their consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents.
1.3 STANDARDS
AASHTO American Association of State Highway and Transportation Officials
ACI American Concrete Institute
AI The Asphalt Institute
AIA American Institute of Architects
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
AITC American Institute of Timber Construction
ANSI American National Standards Institute, Inc.
APA American Plywood Association
APWA American Public Works Association
AREMA The American Railway Engineering and Maintenance -of-Way Association
ASCE American Society of Civil Engineers
ASLA American Society of Landscape Architects
ASME American Society of Mechanical Engineers
277
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 3
ASSE American Society of Sanitary Engineering
ASTM American Society for Testing and Materials
AWS American Welding Society
AWWA American Water Works Association
BASMAA Bay Area Stormwater Management Agencies Association BBC Basic Building Code, Building Officials and Code Administrators International
BFL Bay Friendly Landscaping
CALOSHA California Occupational Safety and Health Administration CA MUTCD California Manual on Uniform Traffic Control Devices CALTRANS State of California Department of Transportation CBC California Building Code
CCR California Code of Regulations
CLFMI Chain Link Fence Manufacturer's Institute
CRSI Concrete Reinforcing Steel Institute
DDW Division of Drinking Water
EIA Electronic Industries Association
IAPMO International Association of Plumbing and Mechanical Officials ICBO International Conference of Building Officials
IEEE Institute of Electrical and Electronics Engineers ISO International Organization for Standardization
ITE Institute of Traffic Engineers
MSS Manufacturers Standardization Society
NACE National Association of Corrosion Engineers
NBS National Bureau of Standards
NEC National Electrical Code
278
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 4
NEMA National Electrical Manufacturer's Association
NFPA National Fire Protection Association
OSHA Occupational Safety and Health Administration (Federal) PCA Portland Cement Association
PUC Public Utilities Commission
SSPC Steel Structures Painting Council
STA Seal of Testing Assurance Program
UL Underwriters Laboratories, Inc
USCC U S Composting Council
1.4 SYMBOLS
A. Symbols, used only on Drawings, are shown thereon.
1.5 DEFINITIONS
A. Wherever any of the words or phrases defined below, or a pronoun used in place thereof, is used in any part of the City Standard Specifications, it shall have the meaning here set forth:
1. ADDENDUM/ADDENDA: Written or graphic instruments issued prior to the opening of Bids which clarify, correct or change the bidding requirements or the Contract Documents.
2. ADDITIVE BID: The sum to be added to the Base Bid if the change in scope of work as described in Additive Bid is accepted by City.
3. AGREEMENT The Contract executed by the parties as further defined in Division 00 – General Conditions, Article 1.
4. ALTERNATE: Work added to or deducted from the Base Bid, if accepted by City.
5. APPROVED EQUAL: Approved in writing by City as being of equivalent quality, utility and appearance.
6. ARCHITECT/ENGINEER:
a. Design Architect: The person holding a valid California State Architect's or Landscape Architect’s license, whose firm has been designated within the Contract Documents to provide architectural or landscape architectural services on the project, and who may have engaged engineering subconsultants to provide services on Project. b. Design Engineer: The person holding a valid California State Engineering license, whose firm has been designated within the Contract Documents to provide civil, structural, traffic or other 279
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 5
engineering services on the project, and who may have engaged engineering subconsultants to provide services on Project. c. When the Architect /Engineer is referred to within the Contract Documents and no Architect or Engineer has in fact been designated, then the matter shall be referred to City. The term Architect/Engineer shall be construed to include all his or her consultants retained for the Project, as well as employees of the Architect /Engineer. When the designated Architect /Engineer is an employee of City, his or her authorized representatives on the Project wi thin the district will be included under the term Architect/Engineer.
7. AS-BUILTS: Project Record Documents as required by the General Conditions and Section 01 78 00 – Closeout Submittals.
8. BID: The offer or proposal of the Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
9. BIDDER: One who submits a Bid.
10. BY CITY: Work that will be performed by City or its age nts at the City's expense.
11. BY OTHERS: Work that is outside scope of Work to be performed by Contractor under this Contract, which will be performed by City, other contractors, or other means.
12. CITY: City of Pittsburg, acting through its City Council or a ny of its authorized agents.
13. CITY CORPORATION YARD: Located at 357 East 12 th Street, Pittsburg, CA 94565-2628.
14. CITY ENGINEER: City employee in charge of Engineering.
15. CITY-FURNISHED, CONTRACTOR-INSTALLED: Items furnished by City at its cost for installation by Contractor at its cost under this Contract.
16. CITY’S PROJECT MANAGER(S): The person or persons assigned by City to be City’s agent(s) or representative(s) at the site. City's authorized agent representing City on all matters of the Contract. Projec t Manager may authorize agents and representatives to act in carrying out Project Manager's duties, including a "Construction Manager", to act under the authority of the Project Manager. As City's agent, the Project Manager is the beneficiary of all contr act obligations of Contractor to City, including without limitation, all releases and indemnities.
17. CHANGE ORDER: A written instrument prepared by City and signed by City and Contractor, stating their agreement upon all of the following:
a. a change in the Work,
b. the amount of the adjustment in the Contract Sum, if any, and c. the amount of the adjustment in the Contract Time, if any.
18. CONCEALED: Work not exposed to view in the finished Work, including within or behind various construction elements.
19. CONTRACT CONDITIONS: Conditions of the Contract define basic rights, responsibilities and relationships of Contractor and City and consists of two parts: General Conditions and Supplementary Conditions. 280
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 6
a. General Conditions are general clauses which are common to the City Contracts.
b. Supplementary conditions modify or supplement General Conditions to meet specific requirements for this Contract.
20. CONTRACT DOCUMENTS: Contract Documents shall consist of the documents identified as the Contract Documents in Division 00 - General Conditions, Article 1, plus all changes, addenda and modifications thereto.
21. CONTRACT MODIFICATION: Either:
a. a written amendment to Contract signed by Contractor and City; or b. a Change Order; or
c. a written directive for a minor change in the Work issued by City.
22. CONTRACT SUM: The sum stated in the Agreement and, including authorized adjustments, the total amount payable by City to Contractor for performance of the Work and the Contract Documents. The Contract Sum is also referred to as the Contract Price or the Contract Amount.
23. CONTRACT TIMES or CONTRACT TIME: The number or numbers of days or the dates stated in the Agreement (i) to achieve substantial completion of the Work or designated milest ones and/or (ii) to complete the Work so that it is ready for final payment and is accepted.
24. CONSTRUCTION MANAGER: A representative of City with authority to act on behalf of City, as specified by City or Project Manager.
25. CONTRACTOR: The person or enti ty identified as such in the Agreement and referred to throughout the Contract Documents as if singular in number and neuter in gender. The term "Contractor" means the Contractor or its authorized representative.
26. CONTRACTOR'S EMPLOYEES: Persons engaged in execution of Work under Contract as direct employees of Contractor, as subcontractors, or as employees of subcontractors.
27. DATE OF SUBSTANTIAL COMPLETION: Date of Substantial Completion of Work or designated portion thereof is date certified by Project Manager when construction is sufficiently complete in accordance with Contract Documents for City to occupy Work or designated portion thereof and have beneficial use of it for the purposes intended.
28. DAY: One calendar day, unless the word "day" is speci fically modified to the contrary.
29. DEFECTIVE: An adjective which, when modifying the word "Work", refers to Work that is unsatisfactory or unsuited for the use intended, faulty, or deficient, that it does not conform to the Contract Documents, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents (including but not limited to approval of samples and "or equal" items), or has been damaged prior to final payment (unless responsibility f or the protection thereof has been assumed by City). Project Manager is the judge of whether Work is defective.
30. DRAWINGS: The graphic and pictorial portions of Contract Documents, wherever located and whenever issued, showing the design, location and 281
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 7
dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams.
31. EQUAL: Equal in opinion of Project Manager. Burden of proof of equality is responsibility of Contractor.
32. EXPOSED: Work exposed to view in the finish ed Work, including behind louvers, grilles, registers and various other construction elements.
33. FINAL ACCEPTANCE or FINAL COMPLETION: City's acceptance of the Work as satisfactorily completed in accordance with Contract Documents.
Requirements for Final Acceptance/Final Completion include, but are not limited to:
a. All Systems having been tested and accepted as having met requirements of Contract Documents.
b. All required instructions and training sessions having been given by Contractor.
c. All as-built drawings, operations and maintenance manuals, and other closeout submittals having been submitted by Contractor, and reviewed and accepted by City.
d. All punch list work, as directed by City, having been completed by Contractor.
e. All Work, except Contractor mainten ance after Final Acceptance, having been completed to satisfaction of City.
f. See Section 01 29 00 – Payment Procedures,1.9.D regarding Final Payment.
g. See Section 01 77 00 – Closeout Requirements.
34. FORCE ACCOUNT: Work directed to be performed without prior agreement as to lump sum or unit price cost thereof, and wh ich is to be billed at cost for labor, materials, equipment, taxes, and other costs, plus a specified percentage for overhead and profit.
35. FURNISH: Supply and deliver to the jobsite.
36. INDICATED: Shown or noted on the Drawings.
37. INSPECTOR: The person engaged by City to inspect the workmanship, materials, or manner of construction of buildings or portions of buildings, to determine if such construction complies with the Contract Documents and applicable codes.
38. INSTALL: Anchor, fasten, or connect in place and adjust for use; place or apply in proper position and location; establish in place for use or service.
39. LATENT: Not apparent by reasonable inspection, including but not limited to, the inspections and research required as a condition to bidding under the General Conditions.
40. MATERIAL OR MATERIALS: These words shall be construed to embrace machinery, manufactured articles, materials of construction (fabricated or otherwise), and any other classes of material to be furnished in connection with Contract, except where a more limited meaning is indicated by context.
41. MILESTONE: A principal event specified in Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all Work.
282
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 8
42. MODIFICATION: Same as Contract Modification.
43. NOT IN CONTRACT: Work that is outside the scope of work to be performed by Contractor under this Contract.
44. NOTICE OF AWARD: A written notice given by City to lowest responsive, responsible bidder advising that Bidder's bid and other qualifying information is acceptable to City, requiring Bidder to fulfill the requirements of Article 4 of Division 00 - General Conditions.
45. NOTICE TO PROCEED: A written notice given by City to Contractor fixing the date on which the Contract Time will commence to run and on which contractor shall start to perform Contractor's obligations under the Contract Documents.
46. OFF SITE: Outside geographical location of the Project.
47. OWNER: City of Pittsburg, acting through its officers, employees, or its authorized agent.
48. PROGRESS REPORT: A periodic report submitted by Contractor to City with progress payment invoices accompanying actual work accomplished to the Program Schedule. See Section 01 32 16 - Construction Progress Schedule and Reports required in Division 00 - General Conditions.
49. PROJECT: Total construction of which Work performed under this Contract may be whole or part.
50. PROJECT MANUAL: Project Manual consists of Bidding Requirements, Agreement, Bonds, Certificates, C ontract Conditions, Technical Specifications, and Specifications.
51. PROVIDE: Furnish and install.
52. REQUESTS FOR INTERPRETATION ("RFI"): A document prepared by Contractor requesting interpretation, information, and/or clarification regarding the Project or Contract Documents.
53. SAMPLES: Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged.
54. SHOP DRAWINGS: All drawings, diagrams, illustrations, schedules and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the work.
55. SITE/JOBSITE: The particular geographical location of Work performed pursuant to Contract.
56. TECHNICAL SPECIFICATIONS : Divisions 01 through 34 – Technical Specifications, which states project-specific requirements.
57. SPECIFICATIONS: The written portion of the Contract Documents consisting of requirements for materials, equipment, construction systems, standards and workmanship for the Work, and performance of related services; and are contained in Divisions 01 through 48.
58. SPECIFIED: As written in Technical Specifications and Specifications.
59. SUBCONTRACTOR: A person or entity who has a direct contract with Contractor to perform a portion of the Work at the site. The term "subcontractor" is referred to throughout the Contract Documents as if 283
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 9
singular in number and neuter in gender and means a subcontractor or an authorized representative of the subcontractor. The term "subcontractor" does not include a separate contractor or subcontractors of a separate contractor.
60. SUBMITTALS: Shop drawings, samples and other items specified in Section 01 33 00 - Submittal Procedures.
61. SUBSTANTIAL COMPLETION: The Work (or a specified part thereof) has progressed to the point where, in the opinion of the Project Manager and Architect/Engineer and as evidenced by a Certificate of Substantial Completion, the Work is sufficiently complete, in accordance with Contract Documents, so that the Work (or specified part) can be utilized for the purposes for which it is intended; or if no such certificate is issued, when the Work is complete and ready for final payment as evidenced by written recommendation of Project Manager and/or Architect/Engineer for final payment. The terms "substantially complete" and "substantially completed" as applied to all or part of the Work refer to Substantial Completion thereof.
See Section 01 29 00 – Payment Procedures,1.8.A.2 regarding application for payment of Substantial Completion and Section 01 77 00 – Closeout Requirements.
62. SUPPLEMENTAL INSTRUCTION: A written work change directive to Contractor from Project Manager or Architect/Engineer, approved by Project Manager, ordering alterations or modif ications which do not result in change in Contract Sum or Contract Times, and do not substantially change Drawings, Technical Specifications, or Specifications.
63. UNDERGROUND FACILITIES: All pipelines, conduits, ducts, cables, wires, manholes, vaults, tank s, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: Electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water.
64. WORK: The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents within the Contract Time. Work includes and is the result of performing or furnishing labor and furnishing and incorporating materials and equipment into the construction, and performing or furnishing services and furnishing documents, all as required by the Contract Documents including the Drawings, Technical Specifications , and Specifications.
Wherever the word "work" is used, rather than the word "Work", it shall be understood to have its ordinary and customary meaning.
65. WORKING DAY. A working day is defined as any day, except as follows:
a. Saturdays, Sundays, and legal holidays
b. Days on which the Contractor i s prevented from performing work by inclement weather or conditions resulting therefrom.
B. Wherever words "as directed", "as required", "as permitted", or words of like effect are used, it shall be understood that direction, requirements, or permission of City 284
City of Pittsburg, California December 2022
REFERENCES 01 42 00 - 10
or Project Manager is intended. Words "sufficient", "necessary", "proper", and the like shall mean sufficient, necessary or proper in judgment of City or Project Manager. Words "approved", "acceptable", "satisfactory", or words of like import, shall m ean approved by, or acceptable to, or satisfactory to, City or Project Manager.
C. Wherever the word "may" is used, the action to which it refers is discretionary.
Wherever the word "shall" is used, the action to which it refers is mandatory.
Where a colon (:) is used within sentences or phrases, the words "shall” or “shall be" are included by inference. Such imperative statements in the specifications are directed to the Contractor, who has overall responsibility for the subcontractors.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 42 00
285
City of Pittsburg December 2022
ABBREVIATIONS 01 42 13 - 1
SECTION 01 42 13 - ABBREVIATIONS
PART 1 - GENERAL
1.1 GENERAL
A. Wherever in these Specifications references are made to the Standards, Specifications or other published data of the various national, regional, or local organizations, such organization may be referred to by their acronym or abbreviation only. As a guide to the use of these Specifications, the following acronyms or abbreviations which may appear in these Specifications shall have the meaning indicated herein.
1.2 ABBREVIATIONS AND ACRONYMS
AASHTO American Association of State Highway and Transportation Officials
ACI American Concrete Institute
AGC Associated General Contractors
AI The Asphalt Institute
AIA American Institute of Architects
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
AITC American Institute of Timber Construction
ANSI American National Standards Institute, Inc.
APA American Plywood Association
APWA American Public Works Association
AREMA The American Railway Engineering and Maintenanc e-of-Way Association
ASCE American Society of Civil Engineers
ASLA American Society of Landscape Architects
286
City of Pittsburg December 2022
ABBREVIATIONS 01 42 13 - 2
ASME American Society of Mechanical Engineers
ASSE American Society of Sanitary Engineering
ASTM American Society for Testing and Materials
AWS American Welding Society
AWWA American Water Works Association
BASMAA Bay Area Stormwater Management Agencies Association BBC Basic Building Code, Building Officials and Code Administrators International
BFL Bay Friendly Landscaping
CALOSHA California Occupational Safety and Health Administration CA MUTCD California Manual on Uniform Traffic Control Devices CALTRANS State of California Department of Transportation CBC California Building Code
CCR California Code of Regulations
CFC California Fire Code
CLFMI Chain Link Fence Manufacturer's Institute
CPC California Plumbing Code
CRSI Concrete Reinforcing Steel Institute
CVC California Vehicle Code
DBE Disadvantaged Business Enterprise
DDW Division of Drinking Water
EIA Electronic Industries Association
ICBO International Conference of Building Officials
IEEE Institute of Electrical and Electronics Engineers ISO International Organization for Standardization
ITE Institute of Traffic Engineers
287
City of Pittsburg December 2022
ABBREVIATIONS 01 42 13 - 3
MSS Manufacturers Standardization Society
NACE National Association of Corrosion Engineers
NBS National Bureau of Standards
NEC National Electrical Code
NEMA National Electrical Manufacturer's Association
NFPA National Fire Protection Association
OSHA Occupational Safety and Health Administration (Federal) PCA Portland Cement Association
PUC Public Utilities Commission
SSPC Steel Structures Painting Council
STA Seal of Testing Assurance Program
UL Underwriters Laboratories, Inc
USCC U S Composting Council
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 42 13
288
City of Pittsburg, California December 2022
QUALITY ASSURANCE 01 43 00 - 1
SECTION 01 43 00 – QUALITY ASSURANCE
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes administrative and procedural requirements for quality assurance.
1. Workmanship: Quality of work.
2. Tolerances: Finished surfaces.
B. References:
1. General: Refer to Division 00 - General Conditions and Section 01 42 00 - References. Products or workmanship specified in the Project Manual by association, trade, or other consensus standards shall conform to the requirements of the s tandard, except when more rigid requirements are specified or are required by applicable codes.
2. Contractual Relationship: The contractual duties and responsibilities of the parties of the Contract and those of the Project Manager shall not be altered from the requirements of the Contract Documents by any statement or inference in any reference document.
C. Testing: Refer to Section 01 45 00 – Quality Control.
PART 2 - PRODUCTS
2.1 Refer to Section 01 60 00 – Product Requirements; assure a consistent quality of products furnished by suppliers and manufacturers as indicated throughout the Project Manual.
PART 3 - EXECUTION
3.1 PERFORMANCE
A. Refer to Section 01 70 00 – Execution.
B. Workmanship: Perform shop and field work with mechanics, craftspersons, artisans, and workers skilled and experienced in the fabrication and installation of work specified. Install and erect work plumb, level, square, and true, or true to indicated angle, and in proper alignment and relationship to other work. Finished work shall be free from defects and damage. Quality of work shall conform to the highest established standards and practices of the various trades required. The Project Manager reserves the right to reject materials and work quality which 289
City of Pittsburg, California December 2022
QUALITY ASSURANCE 01 43 00 - 2
does not meet accepted standards. Repair or replace substandard materia l or work as directed, at no additional cost to the City.
3.2 INSTALLATION
A. General: Conduct quality control in concert with suppliers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Manufacturer's Instructions:
1. General: Follow manufacturer's instructions, including each step in progression of installation. If manufacturer's instructions conflict with Contract Documents, request clarification from Project Manager before commencing Work.
2. Installer: Manufacturer approved, as required in the technical sections of the Project Manual.
3. Field Services: Coordinate with manufacturer of a product, system, or assembly which requires special knowledge and skill for proper application/installation of the produc t, system, or assembly to obtain field service, consultation and inspection as required for the application/installation work at no additional cost to the City.
C. Reference Standards: Conform to specified standards as minimum quality for the Work except where more stringent codes or specified requirements indicate higher standards or more precise workmanship.
D. Anchorage: Secure products in place with positive anchorage devices designed and sized to withstand stress, vibration, physical distortion, or disfigurement.
E. Tolerances: Adjust products to appropriate dimensions; position before securing in place. Monitor and control tolerances of installed products to produce acceptable Work.
END OF SECTION 01 43 00
290
City of Pittsburg, California December 2022
QUALITY CONTROL 01 45 00 - 1
SECTION 01 45 00 – QUALITY CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality - control services.
B. Quality-control services include inspections, tests, and related actions, including reports performed by Contractor, by independent agencies, and by governing authorities. They do not include contract enforcement activities performed by Owner.
C. Inspection and testing services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with Contract Document requirements.
D. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.
E. Specific quality -control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products. Refer to the following:
1. Section 03 30 00 – Utility Cast-in-place Concrete - 3.9 Field Quality Control
2. Section 03 60 00 – Grouting - 3.4 Field Quality Control
3. Section 31 05 13 – Clearing & Grubbing, Excavation, and Earthwork – 2.5 – Source Quality Control.
4. Section 31 23 16 – Utility Trenching - 3.17 Field Quality Control
5. Section 32 11 23 – Aggregate Base Courses – 3.5 Field Quality Control
6. Section 32 12 16 – Asphalt Paving – 1.5 Quality Control Plan & 3.13 – Field Quality Control
7. Section 32 12 17 – Asphalt Paving Rehabilitation – 1.5 Quality Control Plan & 3.17 – Field Quality Control
8. Section 32 13 13 – Concrete Surface Improvements – 3.5 Field Quality Control
9. Section 32 17 26 – Detectable Warning Surfacing – 3.4 Field Quality Control
10. Section 33 01 30 – Testing for Sanitary Se wer, Storm Drainage – Piping and Manholes – 3.3 Field Quality Control
11. Section 33 05 13 – Manholes and Structures – 3.4 Field Quality Control
12. Section 33 05 17 – Precast Concrete Valve Vaults and Meter Boxes – 3.4 Field Quality Control
13. Section 33 11 13 – Water Distribution Piping – 3.6 Field Quality Control
14. Section 33 12 00 – Water Distribution Equipment – 3.4 Field Quality Control
15. Section 33 12 13 – Water Service Connections – 3.4 Field Quality Control 291
City of Pittsburg, California December 2022
QUALITY CONTROL 01 45 00 - 2
16. Section 33 12 16 – Water Distribution Valves – 3.4 Field Quality Control
17. Section 33 12 19 – Water Distribution Fire Hydrants – 3.4 Field Quality Control
18. Section 33 13 00 –Disinfecting of Water Distribution – 3.3 Field Quality Control
19. Section 33 31 13 – Sanitary Sewer Piping – 3.4 Field Quality Control
20. Section 33 41 13 – Storm Drainage Piping – 3.5 Field Quality Control F. Specified inspections, tests, and related actions do not limit Contractor's quality- control procedures that facilitate compliance with Contract Document requirements.
G. Requirements for Contractor to provide quality -control services required by Owner, or authorities having jurisdiction are not limited by provisions of this Section.
1.2 RESPONSIBILITIES
A. Owner's Responsibilities: Unless otherwise indicated as the responsibility of another identified entity, the Owner shall provide inspections, tests, and other quality-control services specified elsewhere in the Contract Documents and required by authorities having jurisdiction.
B. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Contractor's responsibility, the Contractor shall employ and pay a qualified independent testing agency to perform quality - control services. Costs for these services are included in the Contract Sum.’ C. Where the Owner has engaged a testing agency for testing and inspecting part of the Work, and the Contractor is also required to engage an entity for the same or related element, the Contractor shall not employ the entity engaged by the Owner, unless agreed to in writing by the Owner.
D. Retesting: The Contractor is responsible for retesting where results of inspections, tes ts, or other quality -control services prove unsatisfactory and indicate noncompliance with Contract Document requirements, regardless of whether the original test was Contractor's responsibility. Refer to Division 00 - General Conditions, Section 7.8.
1. The cost of retesting construction, revised or replaced by the Contractor, is the Contractor's responsibility and will be at no cost to the Owner where required tests performed on original construction indicated noncompliance with Contract Document requirements.
E. Associated Services: Cooperate with agencies performing require d inspections, tests, and similar services, and provide reasonable auxiliary services as requested. Notify the agency sufficiently in advance of operations to permit assignment of personnel. Auxiliary services required include, but are not limited to, the following:
292
City of Pittsburg, California December 2022
QUALITY CONTROL 01 45 00 - 3
1. Provide access to the Work.
2. Furnish incidental labor and facilities necessary to facilitate inspections and tests.
3. Take adequate quantities of representative samples of materials that require testing or assist the agency in taking samples.
4. Provide facilities for storage and curing of test samples.
5. Deliver samples to testing laboratories.
6. Provide the agency with a preliminary design mix proposed for use for materials mixes that require control by the testing agency.
7. Provide security and protection of samples and test equipment at the Project Site.
F. Duties of the Owner: Owner will retain a qualified independent agency to perform inspections, sampling, and testing of materials and construction specified in individual Sections.
1. Upon rec eipt of notice from the testing agency , Owner will notify the Contractor promptly of irregularities or deficiencies identified in the testing Work performance.
2. The agency is not authorized to release, revoke, alter, or enlarge requirements of the Contract Documents or approve or accept any portion of the Work.
3. The agency shall not perform any duties of the Contractor.
1.3 SUBMITTALS
A. Unless the Contractor is responsible for this service, the independent testing agency shall submit a certified written report, i n duplicate, of each inspection, test, or similar service to the Owner. If the Contractor is responsible for the service, submit a certified written report, in duplicate, of each inspection, test, or similar service through the Contractor.
1. Submit addition al copies of each written report directly to the governing authority, when the authority so directs.
2. Report Data: Written reports of each inspection, test, or similar service include, but are not limited to, the following:
a. Date of issue.
b. Project title and number.
c. Name, address, and telephone number of testing agency. d. Dates and locations of samples and tests or inspections. e. Names of individuals making the inspection or test.
f. Designation of the Work and test method.
g. Identification of product and Special Conditions/Specification Section. h. Complete inspection or test data.
i. Test results and an interpretation of test results.
j. Ambient conditions at the time of sample taking and testing. k. Comments or professional opinion on whether inspected or tested Work complies with Contract Document requirements.
293
City of Pittsburg, California December 2022
QUALITY CONTROL 01 45 00 - 4
l. Name and signature of laboratory inspector.
m. Recommendations on retesting.
1.4 QUALITY ASSURANCE
A. Qualifications for Service Agencies: Owner will engage inspection and testing service agencies, including independent testing laboratories, that are prequalified as complying with the American Council of Independent Laboratories' "Recommended Requirements for Independent Laboratory Qualification" and that specialize in the types of inspections and tests to be performed.
1. Each independent inspection and testing agency engaged on the Project shall be authorized by (authorities having jurisdiction) to operate in the state where the Project is located.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 REPAIR AND PROTECTION
A. General: Upon completion of inspection, testing, sample taking and similar services, repair damaged construction and restore substrates and finishes.
Comply with Contract Document requirements for Section 01 70 00 - Execution.
B. Protect construction exposed by or for quality -control service activities, and protect repaired construction.
END OF SECTION 01 45 00
294
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 1
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes requirements for installation and removal of temporary facilities and controls, including temporary utilities, support facilities, and security and protection. See also, Division 00 – General Conditions, Article 7, including Sections 7.2, 7.4, and 7.9.
B. Temporary utilities include, but are not limited to, the following:
1. Water service and distribution.
2. Temporary electric power and light.
3. Temporary heat.
4. Ventilation.
5. Sanitary facilities, including drinking water.
6. Fire protection water service.
C. Support facilities include, but are not limited to, the following:
1. Temporary enclosures.
2. Temporary project identification signs and bulletin boards.
3. Waste disposal services.
4. Rodent and pest control.
5. Signs.
D. Security and protection facilities include, but are not limited to, the following:
1. Barricades, warning signs, and lights.
2. Sidewalk bridge or enclosure fence for the site.
3. Environmental protection.
1.2 SUBMITTALS
A. Temporary Utilities: Submit reports of tests, inspections, meter readings, and similar procedures performed on temporary utilities.
B. Implementation and Termination Schedule: Within ten (10) working days of the date established for commencement of the Work, submit a schedule indicating implementation and termination of each temporary utility.
C. Temporary Facilities Plan: Within ten (10) working days prior to scheduled installation of any temporary facility, submit a plan to the Project Manager for review and approval.
295
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 2
1.3 TEMPORARY FACILITIES
A. Temporary Structures: Obtain permits for, install and maintain in safe condition, whatever scaffolds, hoisting equipment, barricades, walkways, or other temporary structures which may be required to accomplish the work on the Project. Such structures shall be adequate for the intended use and capable of safely accepting all loads that may be imposed upon them. They shall be installed and maintained in accordance with all applicable State and local codes and regulations.
B. Temporary Heat: Provide and maintain temporary heat from an approved source whenever in the course of the Work it may become necessary for curing and drying of materials, or to warm spaces as may be required for the installation of materials or finishes.
C. Dewatering: Provide and maintain facilities that may be required for dewatering in order that work may proceed on the Project. If it is necessary for dewatering to occur continually, have on hand whatever spare parts or equipment that may be required to prevent interruption of dewatering. If required, obtain Dewatering Permit from Delta Diablo (Sewer District) for waste discharge.
D. Temporary Utilities: Provide and maintain all utility services necessary to perform the work under this Contract. These may include, but are not limited to, temporary electricity, water, gas, sewer and telephone, including charges and installation fees. Furnish and maintain all means of distribution of utility services required within the site to properly complete the Project.
E. Storage: Store materials, tools, accessories, etc., only where directed by City.
Keep s torage area neat and clean. Security of stored items is Contractor's responsibility.
F. Flammable Materials: When flammable materials are stored on site, take extra precautions, including clear identification.
G. Sanitary Facilities: Provide and maintain temporary toilets and wash facilities in quantities and locations as required by CAL/OSHA and other local codes and regulations. Keep them maintained and supplied in a usable and sanitary condition at all times.
H. Drinking Water: Provide and maintain adequate potable water stations at site until final completion of the Project.
I. Field Office: If required by the Special Conditions, m aintain an office at the Project site which will be the Contractor’s headquarters for the Project. Any communications delivered to this office shall be considered as delivered to Contractor. Location and size of office shall be such that it will adequately serve 296
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 3
the needs of Contractor's superintendent and assistants in the performance of their duties.
J. Removal of Temporary Facilities: P romptly remove temporary facilities when they are no longer needed for the work or for completion of the Project, mutually agreed upon by Contractor and City.
K. Fire Hydrant: P rovide site access and operational fire hydrant prior to any combustible construction on site. Fire hydrants to be relocated shall remain operational until the replacement fire hydrant is operational.
1.4 QUALITY ASSURANCE
A. Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including, but not limited to, the following:
1. Building code requirements.
2. Health and safety regulations.
3. Utility company regulations.
4. Police, fire department, and rescue squad rules.
5. Environmental protection regulations.
B. Standards: Comply with the following:
1. NFPA 241 "Standard for Safeguarding Construction, Alterations, and Demolition Operations,"
2. ANSI A10 Series standards for "Safety Requirements for Construction and Demolition," and
3. NECA Electrical Design Library "Temporary Electrical Facilities."
C. Electrical Service:
1. Comply with NEMA, NECA, and UL standards and regulations for temporary electric service.
2. Install service in compliance with NFPA 70 "National Electric Code" and PG&E Green Book, latest edition.
D. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits.
1.5 SIGNS
A. No signs may be displayed on or about City's property (except those required by law) without City's specific approval; the size, content, and location to be as specified by City.
297
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 4
1.6 PROJECT CONDITIONS
A. Temporary Utilities: Prepare a schedule indicating dates for implementation and termination of each temporary utility. At the earliest feasible time, when acceptable to the Owner, change over from use of temporary service to use of permanent service.
B. Conditions of Use: Keep temporary services and facilities clean and neat in appearance. Operate in a safe and efficient manner. Relocate temporary services and facilities as the Work progresses. Do not overload facilities or permit them to interfere with progress. Take necessary fire-prevention measures. Do not allow hazardous, dangerous, or unsanitary conditions, or public nuisances to develop or persist on-site.
C. Use of Roadways and Walkways : Do not block or interfere with use of any existing roadway, walkway or other facility for vehicular or pedestrian traffic, from any party entitled to use it. Wherever and whenever such interference becomes necessary for the proper and convenient performance of the Work, and no satisfactory detour route exists, before beginning the interference, notify City and post signs at least 72 hours in advance of such interference, and provide a satisfactory detour, including temporary bridge if necessary, or other proper facility for traffic to pass around or over the interference. Maintain the detour in a safe and satisfactory condition as long as the interference continues, all without extra payment unless otherwise expressly stipulated in the Special Conditions. Refer to Section 01 55 26 – Temporary Traffic Control.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Provide new materials. If acceptable to the Owner’s Representative, the Contractor may use undamaged, previously used materials in serviceable condition. Provide materials suitable for use intended.
B. Lumber and Plywood:
1. For job-built temporary offices, shops, and sheds within the construction area, provide UL-labeled, fire-treated lumber and plywood for framing, sheathing, and siding.
2. For signs and directory boards, provide exterior-type, Grade B-B high-density concrete form overlay plywood of sizes and thicknesses indicated.
3. For fences and vision barriers, provide minimum 3/8-inch-thick exterior plywood.
4. For safety barriers, sidewalk bridges, and similar uses, provide minimum 5/8- inch-thick exterior plywood.
298
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 5
C. Gypsum Wallboard: Provide gypsum wallboard on interior walls of temporary offices.
D. Roofing Materials: Provide UL Class A standard-weight asphalt shingles or UL Class C mineral-surfaced roll roofing on roofs of job-built temporary offices, shops, and sheds.
E. Paint: Comply with requirements of Section 09 90 00 – Painting and Coating. For sign panels and applying graphics, provide exterior-grade alkyd gloss enamel over exterior primer.
F. Tarpaulins: Provide waterproof, fire-resistant, UL-labeled tarpaulins with flame- spread rating of 15 or less. For temporary enclosures, provide translucent, nylon- reinforced, laminated polyethylene or polyvinyl chloride, fire-retardant tarpaulins.
G. Water: Provide potable water approved by local health authorities.
H. Open-Mesh Fencing: Provide 0.120-inch-thick, galvanized 2-inch chain link fabric fencing 6 feet high with galvanized steel pipe posts; 1-1/2 inches I.D. for line posts and 2-1/2 inches I.D. for corner posts.
2.2 EQUIPMENT
A. General: Provide new equipment. The Contractor may use undamaged, previously used equipment in serviceable condition. Provide equipment suitable for use intended.
B. Water Hoses: For non-potable use (construction water) provide 3/4-inch, heavy- duty, abrasion-resistant, flexible rubber hoses 100 feet long, with pressure rating greater than the maximum pressure of the water distribution system. Provide adjustable shutoff nozzles at hose discharge and backflow devices as required per City standards.
C. Electrical Outlets: Provide properly configured, NEMA-polarized outlets to prevent insertion of 110- to 120-Volt plugs into higher voltage outlets. Provide receptacle outlets equipped with ground-fault circuit interrupters, reset button, and pilot light for connection of power tools and equipment.
D. Electrical Power Cords: Provide grounded extension cords. Use hard -service cords where exposed to abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio.
E. Lamps and Light Fixtures: Provide general service lamps of wattage required for adequate illumination. Provide guard cages or tempered-glass enclosures where exposed to breakage. Provide exterior fixtures where exposed to moisture. 299
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 6
F. Heating Units: Provide temporary heating units that have been tested and labeled by UL, FM, or another recognized trade association related to the type of fuel being consumed.
G. Temporary Offices: If required by the Special Conditions, provide prefabricated or mobile units or similar job-built construction with lockable entrances, operable windows, and serviceable finishes. Provide heated and air-conditioned units on foundations adequate for normal loading.
H. Temporary Toilet Units: Provide self-contained, single-occupant toilet units of the chemical, aerated recirculation, or combustion type. Provide units properly vented and fully enclosed with a glass -fiber-reinforced polyester shell or similar nonabsorbent material.
I. Fire Extinguishers: Provide hand -carried, portable, UL -rated, Class A fire extinguishers for temporary offices and similar spaces. In other locations, provide hand-carried, portable, UL -rated, Class ABC, dry-chemical extinguishers or a combination of extinguishers of NFPA-recommended classes for the exposures.
J. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve the Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.
B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer neede d or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Engage the appropriate local utility company to install temporary service or connect to existing service. Where company provides only part of the service, provide the remainder with matching, compatible materials and equipment.
Comply with company recommendations.
1. Arrange with company and existing users for a time when service can be interrupted, if necessary, to make connections for temporary services.
2. Provide adequate capacity at each stage of construction. Prior to temporary utility availability, provide trucked-in services.
3. Obtain easements to bring temporary utilities to the site where the Owner's 300
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 7
easements cannot be used for that purpose.
B. Water Service: Install water service and distribution piping of sizes and pressures adequate for construction until permanent water ser vice is in use. Sterilize temporary water piping prior to use in compliance with City Standards. Refer to Section 33 13 00 - Disinfecting of Water Distribution.
C. Temporary Electric Power Service: Provide weatherproof, grounded electric power service and distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload-protected disconnects, automatic ground -fault interrupters, and main distribution switchgear. Install wiring overhead and rise vertically where least exposed to damage.
D. Temporary Lighting: When overhead floor or roof deck has been installed, provide temporary lighting with local switching. Install and operate temporary lighting that will fulfill security and protection requirements without operating the entire system.
Provide temporary lighting that will provide adequate illumination for construction operations and traffic conditions.
E. Temporary Heat: Provide temporary heat required by construction activities for curing or drying of completed installations or for protection of installed construction from adverse effects of low temperatures or high humidity. Select safe equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce the ambient condition required and minimize consumption of energy. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
F. Heating Facilities: Except where the Owner authorizes use of the permanent system, provide vented, self-contained, LP-gas or fuel oil heaters with individual space thermostatic control.
G. Sanitary Facilities: Provide lockable temporary toilets and wash facilities. Comply with regulations and health codes for the type, number, location, operation, and maintenance of fixtures and facilities. Install where facilities will best serve the Project's needs. Locate away from storm drainage inlets and other water bodies.
Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Provide covered waste containers for used material.
301
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 8
3.3 SUPPORT FACILITIES INSTALLATION
A. Locate field offices, storage sheds, and other temporary construction and support facilities for easy access. Location will be subject to City’s approval.
B. Provide incombustible construction for offices, shops, and sheds located within the construction area or within 30 feet of building lines. Comply with requirements of NFPA 241.
C. Field Offices: Provide insulated, weather tight temporary offices of sufficient size to accommodate required office personnel at the Project Site. Keep the office clean and orderly for use for small progress meetings.
D. Storage and Fabrication Sheds: Install storage and fabrication sheds sized, furnished, and equipped to accommodate materials and equipment involved, including temporary utility service. Sheds may be open shelters or fully enclosed spaces within the building or elsewhere on-site.
E. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities.
1. Where heat is needed and the permanent building enclosure is not complete, provide temporary enclosures where there is no other provision for containment of heat. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects.
2. Install tarpaulins securely, with incombustible wood framing and other materials. Close openings of 25 square feet or less with plywood or similar materials.
3. Close openings through floor or roof decks and horizontal surfaces with load- bearing, wood-framed construction.
F. Temporary Exterior Lighting: Install exterior yard and sign lights so signs are visible when Work is being performed.
G. Collection and Disposal of Waste: Collect waste from construction areas and elsewhere daily. Comply with re quirements of NFPA 241 for removal of combustible waste material and debris. Enforce requirements strictly. Do not hold materials more than 7 days during normal weather or 3 days when the temperature is expected to rise above 80 deg F. Handle hazardous, dangerous, or unsanitary waste materials separately from other waste by containerizing properly. Dispose of material lawfully.
H. Rodent and Pest Control: Before deep foundation work has been completed, retain an Integrated Pest Management (IPM) Certified exterminator or pest control company to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests. Employ this service to perform extermination and 302
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 9
control procedures at regular intervals so the Project will be free of pests and their residues at Substantial Completion. Perform control operations lawfully, using EPA recommended environmentally safe materials.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Temporary Fire Protection: Until fire-protection needs are supplied by permanent facilities, install and maintain temporary fire -protection facilities of the types needed to protect against reasonably predictable and controllable fire losses.
Comply with NFPA 10 "Standard for Portable Fire Extinguishers" and NFPA 241 "Standard for Safeguarding Construction, Alterations, and Demolition Operations."
1. Locate fire extinguishers where convenient and effective for their intended purpose, but not less than one extinguisher on each floor at or near each usable stairwell.
2. Store combustible materials in containers in fire-safe locations.
3. Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-protection facilities, stairways, and other access routes for fighting fires.
Prohibit smoking in hazardous fire-exposure areas.
4. Provide supervision of welding operations, combustion -type temporary heating units, and similar sources of fire ignition.
B. Permanent Fire Protection: At the earliest feasible date in each area of the Project, complete installation of the permanent fire -protection facility, including connected services, and place into operation and use. Instruct key personnel on use of facilities.
C. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erection of structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and the public of the hazard being protected against. Where appropriate and needed, provide lighting, including flashing red or amber lights.
D. Enclosure Fence: Before construction begins, install an enclosure fence with lockable entrance gates. Provide open-mesh, chain link fencing with posts.
Locate where indicated, or enclose the entire site or the portion determined sufficient to accommodate construction operations. Install in a manner that will prevent people, dogs, and other animals from easily entering the site, except by the entrance gates.
E. Security Enclosure and Lockup: Install substantial temporary enclosure of partially completed areas of construction. Provide locking entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security.
F. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental 303
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 10
regulations, and minimize the possibility that air, waterways, and subsoil might be contaminated or polluted or that other undesirable effects might result. Avoid use of tools and equipment that produce harmful noise. Restrict use of noise-making tools and equipment to hours that will minimize complaints from persons or firms near the site. Contractor is responsible for locking, and any vandalism, theft, unauthorized access and violation are Contractor’s responsibility.
3.5 SIGNS
A. Project Constr uction Sign: Provide minimum 32 -square foot Project identification sign of wood frame and exterior grade plywood construction painted, with exhibit lettering by professional sign painter.
3.6 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. Limit availability of temporary facilities to essential and intended uses to minimize waste and abuse.
B. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage by freezing temperatures and similar elements.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
2. Protection: Prevent water-filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations.
C. Termination and Removal: Remove each temporary facility when the need has ended, when replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have bee n delayed because of interference with the temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are the Contractor's property.
2. Remove temporary paving not intended for or acceptable for integration into permanent paving. Where the area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil in the area. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace street paving, curbs, and sidewalks at the temporary entrances, as required by the governing authority.
3. At Substantial Completion, clean and renovate permanent facilities used during the construction period including, but not limited to, the following:
a. Replace air filters and clean inside of ductwork and housings. b. Replace significantly worn parts and parts subject to unusual operating conditions.
304
City of Pittsburg, California December 2022
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 11
c. Replace lamps burned out or noticeably dimmed by hours of use.
END OF SECTION 01 50 00
305
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 1
SECTION 01 55 26 – TEMPORARY TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: temporary traffic control system including preparing and submitting temporary traffic control, pedestrian and bicycle access plans, temporary traffic signal, traffic control for utility trenching and backfill, utility coordination, vehicular traffic control, traffic control for adjacent property owners, traffic control for on-street parking, traffic control for bus stops and coordination with Tri Delta transit, maintai ning traffic, temporary railing (type K), temporary crash cushion module, construction area signs, and temporary signing and striping.
B. All temporary traffic control plans including temporary pedestrian and bicycle access plans submitted by the Contractor s hall conform to California Manual of Uniform Traffic Control Devices (CA MUTCD) – Latest Edition.
1.2 REFERENCES
A. California Manual of Uniform Traffic Control Devices (CA MUTCD) – Latest Edition.
B. Cal/OSHA – California Division of Occupation Safety and Health C. Caltrans Standard Specifications
1. Section 7 – Legal Relations and Responsibility to the Public
2. Section 12 – Temporary Traffic Control
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Measurement and Payment:
1. When temporary traffic control is included as a bid item, measurement will be made as a percentage of the costs incurred according to the list submitted except that not more than 75% of the bid price shall be paid prior to the final estimate for payment being due, said remaining 25% paid upon completion of cleanup and removal with final payment.
2. When the contract does not include a contract pay item for temporary traffic control, full compensation for any necessary traffic control required shall be 306
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 2
considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed therefore.
3. The adjustment provisions in the State Standard Specifications, Section 4-
1.05, “Changes and Extra Work”, shall not apply to the item of temporary traffic control system. Any adjustment in compensation for temporary traffic control due to an increase or decrease in the amount of traffic c ontrol system required by changes ordered by the Project Manager will be made on the basis of the cost of the increased or decreased temporary traffic control necessary. Such adjustment will be made on a force -account basis as provided in Section 9 -1.04, “ Force Account”, of the State Standard Specifications for increased work.
PART 2 - (NOT USED)
PART 3 - EXECUTION
3.1 TEMPORARY TRAFFIC CONTROL SYSTEM
A. A temporary traffic control system shall consist of closing traffic lanes in conformance with the CA MUTCD, details shown on the Drawings, the provisions in Section 12, “Temporary Traffic Control”, of the State Standard Specifications, the provisions under “Maintaining Traffic”, and “Construction Area Signs” of the State Standard Specifications and the General Conditions, Special C onditions, and Technical Specifications.
B. The provisions in this section will not relieve the Contractor of responsibility for providing additional devices or taking measures as may be necessary to comply with the provisions in Section 7 -1.04, "Public Safety," of the State Standard Specifications and CA MUTCD.
C. During traffic striping and pavement marker placement activities using bituminous adhesive, traffic shall be controlled, at the option of the Contractor, with either stationary or moving l ane closures. During other operations, traffic shall be controlled with stationary lane closures. Attention is directed to the provisions in Section 12-6.03, "Construction," of the State Standard Specifications.
D. If components in the traffic control syste m are displaced or cease to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately repair the components to the original condition or replace the components and shall restore the components to the original location.
E. A traffic control system shall consist of closing traffic lanes in accordance with the details shown on T-9 through T-17 of the latest edition of the Caltrans Standard Plans, California Manual of Uniform Traffic Control Devices (CA MUT CD), the 307
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 3
contract plans, the provisions of Section 12, " Temporary Traffic Control” of the State Standard Specifications and the General Conditions, Special Conditions, and Technical Specifications.
F. Each vehicle used to place, maintain, and remove components of a traffic control system on multilane roadways shall be equipped with a Type II flashing arrow sign which shall be in operation when the vehicle is being used for placing, maintaining, or removing said components. The sign shall be controllable by the operator of the vehicle while the vehicle is in motion.
G. The location of temporary traffic control devices shall be checked by the Contractor especially at the beginning of the work period and periodically throughout the work day, to ensure that the dev ices are properly placed and maintained.
H. If any component in the traffic control system is displaced, or ceases to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately notify the Project Manage r and repair the said component to its original condition or replace said component and shall restore the component to its original location. The cost of providing temporary traffic control as required by the Project Manager shall be considered as included in the cost of traffic control. No additional compensation will be allowed therefor.
I. The Contractor shall furnish competent Flaggers whose sole duties shall consist of directing the movement of traffic through or around the work. Flaggers shall not be used during the hours of darkness unless authorized by the City.
J. The Contractor shall conduct all operations with the least possible obstruction and inconvenience to the public. The Contractor shall have under construction no greater length or amount of work than can be completed within a workday with due regards to the rights of the public.
K. The Contractor shall provide and maintain all traffic control and safety items. The Contractor assumes sole and complete responsibility for the job and site conditions during the course of construction, including safety of all persons and property. This requirement shall apply continuously twenty-four (24) hours/day and shall not be limited to normal work hours.
L. Personal and work vehicles of the Contractor, subcontractor or the Contractor’s employees shall not be parked on the paved shoulders, sidewalk or the traveled way, including any section closed to public traffic. No vehicles of the Contractor shall be parked or driven on the sidewalk.
M. All personnel occupying the roa dway shall be required to wear approved safety vests with protective coloration.
N. The Contractor shall notify local authorities of his intent to begin work at least five (5) working days before work is begun. The Contractor shall cooperate with local 308
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 4
authorities relative to handling traffic through the area and shall make his own arrangements relative to keeping the working area clear of parked vehicles.
O. Upon completion of all work requiring use of lane closures, the Contractor shall remove all temporary si gns, barricades, and markers and shall return the roadway and roadside areas to a condition equal to that which existed prior to construction.
P. All asphalt concrete and temporary pavement delineations including pavement markers at the end of each stage shall be considered as a part of Traffic Control work.
Q. No full road closures are allowed unless approved by the City Manager.
R. No lane closures will be allowed on weekdays from 6:00 AM to 8:30 AM, or from 3:00 PM to 6:00 PM, except for emergencies or unless oth erwise approved by the City Traffic Engineer.
S. The full width of the traveled way shall be open for use by public traffic on Fridays after 3:00pm, Saturdays, Sundays and designated legal holidays, and when construction operations are not actively in progress.
T. Two or more lane closures and lane closures with reversible control will not be allowed on weekdays before 9:00 AM, or after 3:00 PM.
U. The lane closure(s) must be limited in duration and area as practicable and the times and dates of closure must be stat ed on the approved temporary traffic control plan.
V. Lane closures and lane reduction shall conform to the provisions in "Maintaining Traffic" of the State Standard Specifications and the CA MUTCD.
W. When lane closures are made for work periods only, at the en d of each work period, all components of the traffic control system, except temporary portable delineators, K-rails and crash cushions placed along open trenches or excavation adjacent to the traveled way shall be removed from the traveled way and shoulder.
X. To minimize the disruption to traffic, the Contractor shall:
1. Permit local traffic to pass through the work with the least possible inconvenience or delay.
2. Maintain existing driveways, commercial and residential, within the vicinity of the work area, keeping them open and in good, safe condition at all times.
3. Remove or repair any condition resulting from the work that might impede traffic or create a hazard.
4. Keep existing traffic signal and roadway lighting systems in operation throughout the construction work.
5. Maintain continuous ADA accessible pedestrian and bicycle routes. 309
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 5
3.2 TEMPORARY TRAFFIC CONTROL, PEDESTRIAN AND BICYCLE ACCESS PLANS
A. The Contractor shall provide a Temporary Traffic Control, Pedestrian and Bicycle Access Plans for each stage of construction and for each location.
B. Temporary Traffic Control, Pedestrian and Bicycle Access Plans will be hand drawn and legible with an approximate graphic scale.
C. Temporary Traffic Control, Pedestrian and Bicycle Access Plans will show all temporary striping, cones, barricades, channelizers, signs, flaggers, temporary k- rail, crash cushion modules; temporary turn pockets, dimensions of all stri pe segments and lane widths, street names, temporary signal modifications, temporary traffic loops, portable changeable message signs, detour signs, construction area signs on all side streets, construction schedule, work hours and all times the temporary traffic control plan will be in effect.
D. Temporary Traffic Control, Pedestrian and Bicycle Access Plans will also show continuous pedestrian and bicycle path of travel arrows, pedestrian and bicycle signage, pedestrian ADA ramps, bike ramps, temporary pedes trian crosswalks, temporary bike crossings, temporary pedestrian push buttons for signals, pedestrian and bicycle signage on all side streets, pedestrian and bicycle crossing signs, and areas for temporary ADA upgrades along the pedestrian path of travel.
E. Temporary Traffic Control, Pedestrian and Bicycle Access Plans will be submitted to the City Traffic Engineer two (2) weeks prior to commencement of each stage of construction. The Temporary Traffic Control, Pedestrian and Bicycle Access Plans shall be reviewed by the City Traffic Engineer. Contractor to incorporate all comments from the City Traffic Engineer and resubmit the plans for approval prior to implementation. Assume two (2) rounds of review and resubmittal for each stage of construction.
F. Once any segment of sidewalk or trail or corner is commenced with sawcut and/or any segment of sidewalk/trail is closed to pedestrians and bicyclists, Contractor will backfill and complete the improvements unless an approved detour plan is provided and approved by the City Traffic Engineer.
3.3 TRAFFIC SIGNAL
A. If traffic signal inductive vehicle loop detectors and lead-in wiring not designated to be replaced on the Plans are damaged during the course of the construction period, they shall be replaced within one (1) wee k or as directed by the Project Manager. The cost of replacing damaged loop detectors including detector handholes or any other necessary repairs to the components of the traffic signal system shall be included in the cost of traffic control. No additional compensation will be allowed therefore.
310
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 6
3.4 UTILITY COORDINATION
A. Contractor shall notify the utility companies as a first order of work about the project and submit a detailed project schedule to all utility companies.
B. Each stage of construction shall allow for utility companies to complete their work.
If Utility company’s utilities are to be constructed, adjusted or relocated. the Contractor shall provide four (4) week window during each stage of construction for utility companies to have unobstructed access to the site. This four (4) week period will likely occur after demolition and setting of curb forms by the Contractor.
The related utility work shall be coordinated with the utility companies prior to the two (2) week window. The Contractor shall also al low utility companies to work on site during the remaining time of each construction stage.
C. The construction schedule shall identify the related utility work during each stage and shall be submitted for approval. Changes during construction that will impact the related utility work shall be identified on the Progress Schedule.
D. The Contractor shall notify to the utility companies and the Project Manager immediately of any changes to the schedule.
3.5 TEMPORARY TRAFFIC CONTROL FOR UTILITY TRENCHING & BACKFILL A. All excavations shall be backfilled or covered at the end of each workday. Trench covers will be constructed to withstand pedestrian, bicyclist and vehicle loads.
Trench covers in the vehicle areas will be steel plated to withstand vehicle loads.
All trench covers shall be non-skid. In sidewalk areas, AC cutback shall be used as temporary ramps. Contractor shall maintain temporary AC surface to provide safe and comfortable passage over or along same, for pedestrian, bicyclist and vehicular traffic to the satisfaction of the Inspector in the field. Items which will require trench plates include, but are not limited to: storm drain, sewer, water main trenches, and irrigation crossings. Contractor to submit shop drawings to demonstrate method of trench plating, anchoring and asphalt tapers.
B. The Contractor shall comply with the provisions in Section 7 -1.02K(6), "Occupational Safety and Health Standards" of the State Standard Specifications.
C. Spillage resulting from hauling operations along or across any publi c traveled way shall be removed immediately by the Contractor. The Contractor shall leave the project site in a neat, clean, and presentable state at the close of every workday.
D. If material from the trench excavation spills onto the roadway, the roadway ar ea shall be swept and washed with water to provide a safe and dust free surface before the lane is re-opened.
311
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 7
E. The Contractor shall conform to the order of work requirements described on the plans and specifications. If the work items are not completed by the time specified, including any extension of time for excusable delays, the Contractor shall be liable to the City for any additional cost incurred by the City in its completion of the work, and the Contractor shall also be liable to the City for liquidated damages for any delay in the completion of the work.
3.6 TRAFFIC CONTROL FOR ADJACENT PROPERTY OWNERS
A. A. The Contractor shall notify residents/businesses within a closed section by door hanger of sidewalk closures stating the date(s) of closure, limits of sidewalk closure, hours of construction, and detours. The door hangers shall be delivered no later than two (2) working days prior to sidewalk closure. Prior to dissemination, the Contractor shall present a copy to the Project Manager and get approval from the Project Manager for the door hanger.
B. Work shall be accomplished in such a manner as to provide access to all intersecting streets and adjacent properties whenever possible. If during the course of the work, it is necessary to restrict access to cert ain driveways for an extended period of time, the Contractor shall
1. Notify the affected residents, in writing, at least two (2) working days in advance.
2. Provide signage and provide continuous Flaggers to direct traffic in and out of the parking.
3. Maintain 11’ minimum width.
4. Reopen driveway by the end of the work day.
5. Include the signage and Flaggers on the Traffic Control and Pedestrian Access Plans.
C. To protect the rights of abutting property owners, the Contractor shall
1. Conduct the construction so that the least inconvenience as possible is caused to abutting property owners.
2. Maintain ready access to houses or businesses along the line of work, including ramps over work area.
3. Notify all parties at least five (5) days, and again two (2) working days, in advance of work which would affect their property. The Contractor shall coordinate with City to obtain Right of Entry for any work within private property.
4. The Contractor shall maintain access to adjacent private property at all times, and shall address dri veway access on approved Traffic Control Plans.
5. For Utility company and Developer projects, permitee shall obtain right of entry for any work in private properties.
6. The Contractor shall maintain safe pedestrian and bicycle access at all times, including crosswalks, when it is required to close sidewalks. 312
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 8
7. Contractor shall provide Temporary Pedestrian and Bicycle Access Plan for any change in pedestrian and bicycle movements. All openings shall be covered or steel plated at the end of each workday, when wor king in an intersection and traffic lane. Covers in pedestrian areas shall be non -skid and ADA compliant. Contractor shall maintain temporary AC surface to provide safe and comfortable passage over or along same, for pedestrian, bicyclist and vehicular traffic to the satisfaction of the Inspector in the field.
8. The Contractor shall provide temporary pedestrian bridges and walkways as shown on Contractor’s approved Temporary Traffic Control Plans.
Temporary pedestrian bridges shall be provided to each affected doorway.
3.7 TRAFFIC CONTROL FOR ON-STREET PARKING:
A. To maintain On-Street parking, the Contractor shall provide temporary signs for any existing On-Street parking closure and coordinate with adjacent businesses.
Contractor shall restripe the existing On-Street Parking impacted by construction in-kind as required by the Project Manager within the project limits.
B. The Contractor shall post City approved parking restrictions a minimum two (2) working days before work begins. All legal parking areas must be maintained and access to legally parked vehicles doors and storage areas must be maintained.
C. Parking restrictions must be limited in time as practicable.
3.8 TRAFFIC CONTROL FOR BUS STOPS AND COORDINATION WITH TRANSIT
AGENCY (TRI DELTA TRANSIT)
A. If construction shall obstruct a bus stop, the Contractor shall notify the Transit Agency two (2) working days in advance. The Contractor shall be responsible for providing temporary bus stop with temporary bench, bus stop signs posts and no parking signs at locations specified by Transit Agency within a distance of maximum of 400’ from existing bus stop.
B. The Contractor shall be responsible for providing adequate safe guards, safety devices, protective equipment, and any other needed actions to protect life, health, and safety of the public, and to protect property in connection with the performance of the work covered by the contract. The Contractor shall perform any measures or actions the Project Manager may deem necessary to protect the public and property. Contractor shall install K -rail at all new bus stop pad construction areas.
3.9 MAINTAINING TRAFFIC
A. Maintaining traffic shall conform to CA MUTCD, the provisions in Sections 7-1.03, "Public Convenience," Section 7 -1.04, "Public Safety," and Section 12, 313
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 9
"Temporary Traffic Control," of the State Standard Specifications, and the City Standard Specifications.
B. Closure is defined as the closure of a traffic lane or lanes, in cluding shoulder, ramp or connector lanes, within a single traffic control system.
C. The full width of the traveled way shall be open for use by public traffic as specified in Part 3.1 above, when construction operations are not actively in progress.
D. Personal and work vehicles of the Contractor, subcontractor or the Contractor's employees shall not be parked on the traveled way or shoulders including sections closed to public traffic.
E. The Contractor shall immediately restore to the original position and locat ion a temporary traffic cone or delineator that is displaced or overturned, during the progress of work.
F. If minor deviations from the Contractor’s approved lane closure requirements are required, a written request shall be submitted to the City Traffic Engineer at least 15 days before the proposed date of the closure. The City Traffic Engineer may approve the deviations if there is no increase in the cost to the City and if the work can be expedited and better serve the public traffic.
G. Designated legal holidays are:
Holidays
Holiday Date observed
New Year’s Day January 1st
Martin Luther King Jr. Day 3rd Monday in January
Lincoln’s Birthday February 12th
Washington’s Birthday 3rd Monday in February
Cesar Chavez Day March 31st
Memorial Day Last Monday in May
Independence Day July 4th
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veterans Day November 11th
Thanksgiving Holidays 4th Thursday and Friday in November Christmas Day December 25th
If a designated holiday falls on a Sunday, the following Monday is a designated holiday. If November 11th falls on a Saturday, the preceding Friday is a designated holiday.
314
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 10
H. Pedestrian and Bicycle access facilities shall be provided through construction areas within the public right of way as shown on the Contractor’s approved Temporary Traffic control, Pedestrian and Bicycle Access plans and as specified herein. Pedestrian w alkway shall be surfaced with asphalt concrete, Portland cement concrete or timber. The surface shall be skid resistant and free of irregularities. Hand railings shall be provided on each side of pedestrian walkways as necessary to protect pedestrian tra ffic from hazards due to construction operations or adjacent vehicular traffic. Protective overhead covering shall be provided as necessary to insure protection from falling objects and drip from overhead structures. If the Contractor's operations requir e the closure of one walkway, then another walkway shall be provided nearby, off the traveled roadway.
3.10 CONTINGENCY PLAN: A detailed contingency plan shall be prepared for reopening closures to public traffic. The contingency plan shall be submitted to the Project Manager within one (1) business day of the Project Manager's request.
3.11 LATE REOPENING OF CLOSURES
A. If a closure is not reopened to traffic by the specified time, work shall be suspended in conformance with the provisions in Section 8-1.06, "Suspensions" of the State Standard Specifications. No further closures are to be made until the City Traffic Engineer has accepted a work plan, submitted by the Contractor that will insure that future closures will be reopened to traffic at the specified time.
The City Traffic Engineer will have two (2) business days to accept or reject the Contractor's proposed work plan. The Contractor will not be entitled to compensation for the suspension of work resulting from the late reopening of closures.
B. For each 10-minute interval, or fraction thereof past the time specified to reopen the closure, City will deduct payments per interval from moneys due or that may become due the Contractor under the contract. See deductible schedule below:
1. Residential Streets - $50 per 10 minutes
2. Collector Streets - $100 per 10 minutes
3. Arterial Streets - $400 per 10 minutes.
3.12 TEMPORARY RAILING (TYPE K)
A. Temporary railing (Type K) shall be placed as shown on the Contractor’s approved Temporary Traffic Control, Pedestrian and Bicycle Access plans, as specified in the Drawings or where ordered by the Project Manager and shall conform to CA MUTCD, the provisions in Section 12, “Temporary Traffic Control” of the State Standard Specifications and the City Standard Specifications. 315
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 11
B. Temporary railing (Type K) shall consist of interconnected new or undamaged used precast concrete barrier units as shown on the Contractor’s approved Temporary Traffic Control, Pedestrian and Bicycle Access plans. Exposed surfaces of new and used units shall be f reshly coated with a white color paint prior to their first use on the project. The paint shall conform to the provisions in Section 91 -4.02B, "Acrylic Emulsion Paint for Exterior Masonry” of the State Standard Specification.
C. Concrete shall conform to the provisions in Section 90-2, "Minor Concrete” of the State Standard Specifications. Load tickets and a Certificate of Compliance will not be required.
D. Reinforcing steel shall conform to the provisions in Section 52, "Reinforcement" of the State Standard Specifications.
E. Steel bars to receive bolts at ends of concrete panels shall conform to the requirements in ASTM Designation: A 36. The bolts shall conform to the requirements in ASTM Designation: A 307.
F. The final surface finish of temporary railings (T ype K) shall conform to the provisions in Section 51 -1.03F(2), "Ordinary Surface Finish" of the State Standard Specifications. Exposed surfaces of concrete elements shall be cured by the water method, the forms in place method, or the pigmented curing compound method. The pigmented curing compound shall be curing compound (1) as specified in Section 90-1.03B(3), "Curing Compound Method" of the State Standard Specifications. The Contractor shall furnish a Certificate of Compliance to the Project Manager in conformance with the provisions in Section 6 -2.03C "Certificates of Compliance" of the State Standard Specification, for all new or used temporary railing (Type K) that is not cast on the project.
G. Temporary railing (Type K) shall be set on firm, stable foundation. The foundation shall be graded to provide a uniform bearing throughout the entire length of the railing. Any excavation and backfill shall conform to the provisions in Section 19- 3, "Structure Excavation and Backfill" of the State Standard Specification except that compaction of earth fill placed behind the temporary railing (Type K) in a curved layout will not be required.
H. Abutting ends of precast concrete units shall be placed and maintained in alignment without substantial offset to each othe r. The precast concrete units shall be positioned straight on tangent alignment and on a true arc on curved alignment.
I. At the locations required on the plans, threaded rods or dowels shall be bonded in holes drilled in the existing concrete. Drilling of holes and bonding of threaded rods or dowels shall conform to the provisions for bonding dowels in Section 83-
3.01A, "Summary" of the State Standard Specifications. After removal of the temporary railing (Type K), all threaded rods or dowels shall be remov ed to a 316
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 12
depth of at least one inch below the surface of the concrete. The resulting holes shall be filled with mortar in conformance with the provisions in Section 51-1.02F, "Mortar" of the State Standard Specification, except that the mortar shall be cured by either the water method or by the curing compound method. If the curing compound method is used, the curing shall conform to the provisions for curing concrete barrier in Section 83 -3.03A(8), "Curing” of the State Standard Specifications.
J. Each rail unit shall have a reflector installed on top of the rail. Reflectors shall be as specified in the technical specifications, and adhesive shall conform to the reflector manufacturer's recommendations. A Type P marker panel shall also be installed at each end of railing installed adjacent to a two lane, two-way highway and at the end facing traffic of railing installed adjacent to a one-way roadbed. If the railing is placed on a skew, the marker shall be installed at the end of the skew nearest the travele d way. Type P marker panels shall conform to the provisions in Section 82, "Signs and Markers" of the State Standard Specifications, except that the Contractor shall furnish the marker panels.
K. When temporary railings (Type K) are removed, any area where t emporary excavation or embankment was used to accommodate the temporary railing shall be restored to its previous condition or constructed to its planned condition.
L. Prior to each stage of construction Contractor will provide a layout of the proposed tempor ary railing, crash cushion locations, and temporary striping/signing for the railing.
M. Water filled barriers will be considered in lieu of temporary railings (Type K), upon a written request from the contractor along with proposed details, layout plan, temporary signing & striping and installation.
3.13 TEMPORARY CRASH CUSHION MODULE
A. This work shall consist of furnishing, installing, and maintaining sand filled temporary crash cushion modules in groupings or arrays at each location shown on the Contractor’s appro ved traffic control plans, as specified in the technical specifications or where designated by the Project Manager. The grouping or array of sand filled modules shall form a complete sand filled temporary crash cushion in conformance with the details show n on the plans and the technical specifications.
B. Temporary crash cushions shall be secured in place prior to commencing work for which the temporary crash cushions are required.
C. Whenever the work or the Contractor's operations establishes a fixed obstacle, the exposed fixed obstacle shall be protected with a sand filled temporary crash cushion. The sand filled temporary crash cushion shall be in place prior to opening the lanes adjacent to the fixed obstacle to public traffic. 317
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 13
D. Sand filled temporary crash cushions shall be maintained in place at each location, including times when work is not actively in progress. When no longer required, as determined by the Project Manager, sand filled temporary crash cushions shall be removed from the site of the work.
E. Modules contained in each temporary crash cushion shall be of the same type at each location. The color of the modules shall be the standard yellow color, as furnished by the vendor, with black lids. The modules shall exhibit good workmanship free from structural flaws and objectionable surface defects. The modules need not be new. Good used undamaged modules conforming to color and quality of the types specified herein may be utilized.
F. Modules shall be filled with sand in conformance with the manufacturer's directions, and to the sand capacity in pounds for each module shown on the plans. Sand for filling the modules shall be clean washed concrete sand of commercial quality. At the time of placing in the modules, the sand shall contain no more than 7 percent water as determined by California Test 226.
G. Modules damaged due to the Contractor's operations shall be repaired immediately by the Contractor at the Contractor's expense. Modules damaged beyond repair, as determined by the Proje ct Manager, due to the Contractor's operations shall be removed and replaced by the Contractor at the Contractor's expense.
H. A Type R or P marker panel shall be attached to the front of the crash cushion.
The marker panel, when required, shall be firmly fa stened to the crash cushion with commercial quality hardware or by other methods determined by the Project Manager.
I. At the completion of the project, temporary crash cushion modules, sand filling, pallets or frames, and marker panels shall become the property of the Contractor and shall be removed from the site of the work. Temporary crash cushion modules shall not be installed in the permanent work.
J. Repairing modules damaged by public traffic and modules damaged beyond repair by public traffic, when order ed by the Project Manager, shall be removed and replaced immediately by the Contractor. Modules replaced due to damage by public traffic will be not be measured and paid for and shall be considered as included in the lump sum price paid for Temporary Traffic Control.
K. Include allowance for Project Manager to order a lateral move of the sand filled temporary crash cushions where the repositioning is not shown on the Contractor’s approved traffic control plans. Moving the sand filled temporary crash cushion w ill be considered as included in the lump sum price paid for Temporary Traffic Control and no additional compensation will be allowed therefore and these temporary crash cushion modules will not be counted for payment in the new position.
318
City of Pittsburg, California December 2022
TEMPORARY TRAFFIC CONTROL 01 55 26 - 14
3.14 CONSTRUCTION AREA SIGNS
A. Construction area signs shall be furnished, installed, maintained, and removed when no longer required in accordance with CA MUTCD, the provisions in Section 12-3.11, "Construction Area Signs," of the State Standard Specifications, the contract draw ings, and the General Conditions, Special Conditions, and Technical Specifications. The base material of construction area signs shall not be plywood. This includes but not limited to furnishing and installation of Pedestrian and Bicycle Signs.
END OF SECTION 01 55 26
319
City of Pittsburg, California December 2022
PROTECTION OF PROPERTY 01 56 10 - 1
SECTION 01 56 10 – PROTECTION OF PROPERTY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Existing Utilities and Improvements
2. Safeguarding of Existing Facilities
3. Restoration of Pavement
4. Emergency Work
5. Preconstruction Site Documentation
B. Related Sections:
1. Section 01 50 00 – Temporary Facilities and Controls
2. Section 01 32 00 – Construction Progress Documentation
1.2 EXISTING UTILITIES AND IMPROVEMENTS
A. Underground Facilities: Notify Underground Service Alert (U.S.A.) prior to excavating at the site so that utility companies and other City departments having underground facilities in the area may be advised of the work and may field mark or otherwise protect and warn Contractor of their existing utility lines.
1. Provide reasonable access and do not hinder or otherwise interfere with any company or agency having underground facilities in removing, relocating, or protecting such facilities.
B. Excavations: Verify the actual locations and depths of all utilities indicated or field marked. Make a sufficient number of exploratory excavations of all utilities that may interfere with the Work suff iciently in advance of construction to avoid possible delays to Contractor’s work.
1. Notify the City when such exploratory excavations show the utility location as shown or as marked to be in error.
2. When utility lines are encountered within the area of Contr actor’s operations, notify the Project Manager and the Owner(s) of the utility lines sufficiently in advance for the necessary protection measures to be taken to prevent interruption of service or delay to Contractor’s operations.
1.3 SAFEGUARDING OF EXISTING FACILITIES
A. Damage: Perform all work, including dewatering operations, in such a manner as to avoid damage to existing sewer and water systems, fire hydrants, power poles, lighting standards, and all other existing utilities, facilities, trees and vegetatio n, and structures. The Contractor will be held responsible for any damage due to its failure to exercise due care, and at no cost to the City. 320
City of Pittsburg, California December 2022
PROTECTION OF PROPERTY 01 56 10 - 2
B. Removal and Disposal: Broken concrete, debris, and the like, shall be immediately removed from the property site as the Contractor’s property and disposed of in a legal manner.
C. Existing Facilities: Exercise due care to avoid damage to existing pipe and coating, wrapping, sewers, conduit, or other existing facilities and structures.
Should the Contractor damage or dis place any of the above, repair same to the satisfaction of the Project Manager; all expenses in connection therewith shall be borne solely by the Contractor.
D. Sewer System: Do not allow debris to enter the sewer system.
1.4 RESTORATION OF PAVEMENT
A. General: All paved areas cut or damaged during construction shall be replaced with materials of equal thickness to match the existing undisturbed areas, except where specific resurfacing requirements are called for in the Contract Documents or in the permit requireme nts of the agency issuing the permit. All pavements which are subject to partial removal shall be neatly saw cut in straight lines.
B. Temporary Resurfacing: Place temporary surfacing promptly after backfilling and maintain such surfacing in a satisfactory c ondition for the period of time before proceeding with the final restoration.
C. Permanent Resurfacing: Damaged edges of pavement along excavations and elsewhere shall be trimmed back by saw cutting in neat straight lines. All pavement restoration shall be c onstructed to finished grades compatible with undisturbed adjacent pavement.
D. Restoration of Sidewalks or Driveways: Wherever sidewalks, curbs and gutters, or driveways have been removed for construction purposes, place suitable temporary sidewalks, curbs and gutters, or driveways promptly after backfilling and maintain them in satisfactory condition for the period of time before the final restoration has been made.
1.5 EMERGENCY WORK
A. General: At all times have adequate personnel, materials, and equipment available at short notice to protect adjoining property, maintain, or make emergency repairs. If during the progress of the Contract, the Contractor’s construction crews should be absent from the location of the work at a time when any failure or faulty condition of the Contractor’s work requires emergency action in the public interest, the City shall have the right to make repairs and corrections as required with its own forces at the Contractor’s expense.
B. Contact Information: F urnish the Project Manager w ith names and telephone numbers of at least three (3) persons to contact in case of emergencies ; these 321
City of Pittsburg, California December 2022
PROTECTION OF PROPERTY 01 56 10 - 3
persons shall be authorized to perform such work as deemed necessary by the Project Manager.
1.6 PRECONSTRUCTION SITE DOCUMENTATION
A. Prevention of Damage: Use such methods and take adequate precautions to prevent damage to existing buildings, structures, and other improvements during the prosecution of the work.
B. Joint Examination: After the Contract is awarded and before the commencement of work, the Project Manager will arrange for a joint examination of the work, as applicable, which might be damaged by the Contractor’s operations C. Scope of Examination: The examination will include the exterior of existing buildings, structures, and other improvements located within twenty-five (25) feet of the construction excavation. Examination will be made jointly by authorized representatives of the Contractor, the City, and property owners under the supervision of the Project Manager. The scope of each examination will include, but is not limited to, written and photographic recording of cracks in structures, settlement, leakage, and the like.
D. Photos and Videos: Take photos and videos during the joint examination review.
Provide digital photos and videos to the Project Manager within thirty ( 30) consecutive days of the date taken.
E. Use of Records and Photographs : Any and all records and photogra phs are intended for use as indisputable evidence in ascertaining the extent of any damage which may occur as a result of the Contractor’s operations. They are for the protection of the adjacent property owners, the Contractor, and the City and will be a m eans of determining whether and to what extent damage, resulting from the Contractor operations, occurred during the Contract Work.
F. Requirements for Photographs and Videos : Refer to Section 01 32 00 – Construction Progress Documentation.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 56 10
322
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 1
SECTION 01 57 23 – STORM WATER POLLUTION PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: requirements for temporary utilities, support facilities, storm water pollution prevention, erosion control, traffic control, support, and security and protection facilities.
B. Projects that have a soil disturbance of one acre or greater are subject to the State Water Resources Control Board’s (SWRCBs) Construction General Permit.
The appropriate Legally Responsible Person (LRP), or approved representative must obtain coverage by filing the Permit Registration Documents (PRDs) prior to commencement of any construction activity. A Stormwater Pollution Prevention Plan (SWPPP) shall be prepared by a Qualified SWPPP Developer (QSD) and submitted to the City prior to issuance of a grading permit. Contractor shall comply with all requirements of SWRCBs Construction General Permit Order No. 2009-0009-DWQ, and amended Orders 2010-0014-DWQ, and 2012- 0006-DWQ.
C. Projects that are less than one acre and are Caltrans related (State Highway Projects) are required to have a Water Pollution Control Plan (WPCP) prepared in accordance with Caltrans’ standard WPCP template.
D. Projects that are less than one acre and are not Caltrans related are required to have an Erosion and Sedimentation Control Plan prepared and submitted to the City for approval prior to issuance of a grading permit.
1.2 PRICE AND PAYMENT PROCEDURES
A. Section 01 29 00 - Payment Procedures
B. Notice of Intent (NOI) and Annual Permit Fees for Capital Improvement Projects shall be paid by the City.
C. The Developers shall pay all associated Construction General Permit (CGP) fees for all new development/redevelopment projects requiring a permit from the City. 323
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 2
1.3 REFERENCES:
A. California Stormwater Quality Association (CASQA) has developed a standard SWPPP template for traditional Risk 1,2, and 3 projects that is prevalent in California and can be downloaded from www.CASQA.org. (Note: An annual subscription is required to access to access the CASQA construction portal.) B. SWPPP: The Stormwater Pollution Prevention Plan (SWPPP) shall be designed to comply with California’s General Permit for Stormwater Discharges Associated with Construction and Land Disturb ance Activities (General Permit) Order No. 2009-0009-DWQ as amended by Order No. 2010 -0014-DWQ (NPDES No.
CAS000002) and 2012-0006-DWQ, Waste Discharge Requirements (WDRs) for Discharges of Storm Water Runoff Associated with Construction Activity (herein after referred to as General Permit) issued by the State Water Resources Control Board (State Water Board). In accordance with the General Permit, Section XIV, designed to address the following:
1. Pollutants and their sources, including sources of sediment associated with construction, construction site erosion and other activities associated with construction activity are controlled.
2. Where not otherwise required to be under a Regional Water Quality Control Board (Regional Water Board) permit, all non -stormwater discharges are identified and either eliminated, controlled, or treated.
3. Site Best Management Practices (BMPs) are effective and result in the reduction or elimination of pollutants in stormwater discharges and authorized non-stormwater discharges from construction activity to the Best Available Technology/Best Control Technology (BAT/BCT) standard.
4. Calculations and design details as well as BMP controls are complete and correct.
5. Stabilization BMPs will be installed to reduce or eliminate pollutants afte r construction is completed.
1.4 SUBMITTALS
A. Notice of Intent (NOI): The Legally Responsible Person shall file the Notice of Intent (NOI) and submit all PRDs to the SWRCB prior issuance of a grading permit. For City Capital Improvement Projects, the Contractor shall file the NOI and submit all PRDs to the SWQRB on behalf of the City. Contractor to obtain the Waste Discharge Identification Number (WDID #) on behalf of the City, or as otherwise directed by the City Engineer.
B. SWPPP:
1. Contractor shall submit SWPPP for Project Manager’s review within ten (10) calendar days after award of project.
2. The Contractor shall submit a site-specific Storm Water Pollution Prevention Plan (SWPPP) prepared by a Qualified SWPPP Developer (QSD) the Contractor shall amend the SWPPP when required, prepare a Construction 324
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 3
Site Monitoring Plan (CSMP), and perform water pollution control work under the oversight of a Qualified SWPPP Practitioner (QSP), as specified in the General Permit. The Contractor shall identify an individual to be a Data Submitter (DS) for this contract. All reports and data that must be submitted to the State Water Resources Control Board will be uploaded by the Contractor’s DS to the Stormwater Multi -Application and Report Tracking System (SMARTS) website for certification to the state by the City Legally Responsible Person (LRP) or their Approved Signatory (A/S).
3. The QSD, QSP, and DS designated by the Contractor may be different individuals.
4. Storm Water Pollution Prevention Plan (SWPPP):
The Contractor shall prepa re and submit a site -specific Storm Water Pollution Prevention Plan (SWPPP) to the City Engineer for approval. The SWPPP shall be prepared and certified by a Qualified SWPPP Developer (QSD) holding one of the certifications or registrations listed in Secti on VII of the Construction General Permit. Within seven ( 7) working days after contract award, the Contractor shall submit two (2) printed copies of the SWPPP and Site Map and one electronic copy in electronic file (.pdf) format to the Project Manager for review. The Contractor shall allow five ( 5) working days for the Project Manager’s review. If revisions are required, the Project Manager will provide comments, and the Contractor shall revise and resubmit the SWPPP and Site Map in printed and electronic form within five (5) working days of receipt of the Project Manager’s comments. Within three (3) working days of receipt of the City Engineer’s approved SWPPP, the Contractor shall submit three (3) paper copies of the approved SWPPP to the City Engineer. Once the City Engineer has approved the SWPPP for the project, the Contractor may proceed with construction activities requiring coverage under the General Permit.
5. WDID Number: The Contractor shall not perform work that may cause water pollution until the state has issued a WDID number for the project. The City Engineer’s review and approval of the SWPPP shall not waive any contract requirements and shall not relieve the Contractor from complying with Federal, State and local laws, regulations, and requirements. Working days shall not be counted if the controlling item of work cannot be performed during the initial preparation and review of the SWPPP and Site Map and between the date that the approved SWPPP has been received by the City Engineer, and the date the City Engineer has notified the Contractor that a WDID number has been assigned to the project.
6. Approved SWPPP: The Contractor shall keep a copy of the approved SWPPP at the job site t all times during construction. The SWPPP shall be made available when requested by a representative of the Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency, or the local storm water management agency. Requests from the public shall be directed to the Project Manager. 325
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 4
C. WPCP
1. General: Contractor shall submit WPCP for City review within ten (10) calendar days after award of project.
2. Water Pollution Control Plan:
The Contractor shall prepare and submit a site -specific Water Pollution Control Plan (WPCP) to the Project Manager and Construction for approval.
Within seven (7) working days after contract awa rd, the Contractor shall submit two (2) printed copies of the WPCP and Site Map and one electronic copy in electronic file (.pdf) format to the Project Manager for review. The Contractor shall allow five ( 5) working days for the Project Manager’s review. I f revisions are required, the Project Manager will provide comments, and the Contractor shall revise and resubmit the WPCP and Site Map in printed and electronic form within five (5) working days of receipt of the Project Manager’s comments. Within three (3) working days of receipt of the Project Manager’s approved WPCP, the Contractor shall submit three (3) paper copies of the approved WPCP to the Project Manager. Once the Project Manager has approved the WPCP for the project, the Contractor may proceed with construction activities.
The Contractor shall keep a copy of the approved WPCP at the job site. The WPCP shall be made available when requested by a representative of the Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency, or the local storm water management agency. Requests from the public shall be directed to the Project Manager.
1.5 WATER POLLUTION CONTROL DRAWING/EROSION CONTROL PLAN A. General: Contractor shall include a Water Pollution Control Drawing (WPCD) / Erosion and Sediment Control Plan (ESCP) as a part of the SWPPP/WPCP.
Revisions and Amendments to the WPCDs shall be prepared and uploaded to SMARTS by Contractor’s QSP and/or QSD.
B. For any State Highway projects, Contractor shall provide a Water Pollution Control Drawing as required by Caltrans. Contractor to provide an Erosion and Sedimentation Control Plan to the Engineering Division for review and approval prior to issuance of a grading permit.
C. Deficiencies: The Contractor shall construct, inspect, maintain, remove, and dispose of the water pollution control measures. If the Contractor, the Contractor’s QSP, or the City Engineer and/or his representative identifies a deficiency in the implementation of the approved SWPPP/WPCP, the deficiency shall be corrected immediately, and at a minimum of 72 Hours. The deficiency shall be corrected before the onset of precipitation. If the Contractor fails to 326
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 5
correct the deficiency by the 72 -hour timeframe or before the onset of precipitation, the Project Manager may correct the deficiency and deduct the cost of correcting deficiencies from payments. If the Contractor fails to conform to the provisions of this section, the Project Manager may order the suspension of work until the project compl ies with the requirements of the Construction General Permit and this section.
D. Weather Forecasts: The Contractor shall monitor the National Oceanic and Atmospheric Administration (NOAA) weather forecast on a daily basis during the contract. The Contractor shall perform SWPPP/WPCP Inspections according to the Risk Level. The Contractor will provide soil stabilization and sediment control practices whenever there is a 50% probability of rain within 48 hours as predicted by the NOAA. The Contractor shall main tain soil stabilization and sediment control materials on site to protect disturbed soil areas throughout the life of construction project.
1.6 IMPLEMENTATION REQUIREMENTS
A. QSP: The Contractor shall designate in writing a Qualified SWPPP Practitioner (QSP) who shall be responsible for non -storm water and storm water visual observations and inspections, and for ensuring that all BMP required by the SWPPP/WPCP and General Construction Permit are properly implemented and maintained. The QSP shall meet the training and certification requirements in the Construction General Permit.
B. SWPPP Requirements: All measures required by the SWPPP/WPCP shall be implemented concurrent with the commencement of construction. No construction may start without all BMPs in place. Pollution practices and devices shall be followed or installed as early in the construction schedule as possible with frequent upgrading of devices as needed as construction progresses to protect water quality at all times.
C. Inspection and Maintenance: The Contr actor’s Qualified SWPPP Developer (QSD) shall develop and implement a written site -specific Construction Site Monitoring Program (CSMP) in accordance with the requirements of the General Permit and the Technical Specifications, and Contractor’s QSP shall monitor the water pollution control practices identified in the General Permit and SWPPP as follows:
1. Visual Inspections, Quarterly Non-storm water discharge
2. Minimum of Weekly Visual Inspections of all Best Management Practices (BMP) that need maintenance to operate effectively, that have failed or that could fail to operate as intended.
3. BMP Inspections, Baseline Pre-storm event
4. Rain Event Action Plan (REAP)
5. BMP Inspections, 24-Hours during extended rain events
6. BMP Inspections, Post-storm event.
327
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 6
D. The QSP shall oversee the maintenance of the water pollution control practices.
The QSP shall document all visual inspection activities with written reports according to the requirements of the Construction General Permit. The format of the reports shall be approved by the Project Manager.
E. A copy of all written reports documenting implementation of the CSMP shall be submitted to the Project Manager within 48 hours of finishing the inspection and shall remain on site during construction.
F. Reporting Requirements: If the Contractor identifies discharges i nto surface waters or drainage systems causing or potentially causing pollution, or if the project receives a written notice or order from a regulatory agency, the Contractor shall immediately inform the Project Manager. The Contractor shall submit a written report to the Project Manager within 24 hours of the discharge, notice or order. The report shall include the following information:
1. The date, time, location, nature of the operation, type of discharge; and the cause of the notice or order.
2. The water pollution control practices used before the discharge, or before receiving the notice or order.
3. The date of placement and type of additional or altered water pollution control practices placed after the discharge, or after receiving the notice or order.
4. A maintenance schedule for affected water pollution control practices.
G. Annual Report: The Contractor shall complete and submit to the City Engineer an Annual Report, as required by the current State Water Board Industrial General Permit . The Contractor shall s ubmit the Annual Report prior to acceptance of the project. Contractor shall submit the annual report to the SWRCB directly on SMARTS.
1.7 COMPLETION OF WORK
A. Maintenance: Clean -up shall be performed as each portion of the work progresses. All refuse, excess material, and possible pollutants shall be disposed of in a legal manner off-site and all temporary and permanent BMP devices shall be in place and maintained in good condition.
B. Records: At completion of work, inspect installed BMP devices, and present the currently implemented SWPPP/WPCP with all backup records to the Project Manager.
C. BMPs: Contractor must remove all construction materials, temporary facilities, temporary BMPs, equipment and construction related materials from the site.
D. NOTICE OF TERMINATIO N (NOT): A Notice of Termination (NOT) must be submitted by the Contractor to the City Engineer for electronic submittal by the LRP via SMARTS to terminate coverage under the General Permit. The NOT 328
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 7
must include a final Site Map and representative photogra phs of the project site that demonstrate final stabilization has been achieved. The NOT shall be submitted to the City Engineer within 10 days of completion of construction. The NOT will be reviewed and submitted to SMARTS by the City Engineer within 90 days of completion of construction. The Regional Water Board will consider a construction site complete when the conditions of the General Permit, Section II.D have been met. Notice of Termination should be filed by the Contractor via the SMARTS system. The City will allow the Contractor to enter data in SMARTS on the City’s behalf.
1.8 QUALITY ASSURANCE
A. Performance: Perform work in accordance with SWPPP/WPCP. Maintain one copy of document on jobsite.
B. Quality Control and Assurance: Train all employees and subcontractors in these subjects:
1. Material pollution prevention and control
2. Waste management
3. Non-storm water management
4. Identifying and handling hazardous substances
5. Potential dangers to humans and the environment from spills and leaks or exposure to toxic or hazardous substances
C. Training Requirements: Training must take place before starting work on this job.
New employees must receive the complete training before starting work on this job. Conduct weekly meetings to discuss and reinforce spill prevention and control; material delivery, storage, use, and disposal; waste management; and non-storm water management procedures.
1.9 PRE-INSTALLATION CONFERENCE
A. Timing: Convene a conference one week prior to commencing work at the site B. Attendance: Require attendance of part ies directly affecting the work of this Section.
C. Agenda: Review requirements of the SWPPP/WPCP.
1.10 PERFORMANCE REQUIREMENTS
A. General: The SWPPP/WPCP is a minimum requirement. Revisions and modifications to the SWPPP/WPCP are acceptable only if they maintain levels of protection equal to or greater than originally specified. 329
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 8
B. Requirements: Read and be thoroughly familiar with all of the requirements of the SWPPP/WPCP.
C. Compliance: Inspect and monitor all work and storage areas for compliance with the SWPPP/WPCP prior to any anticipated rain.
D. Corrective Measures: Complete any and all corrective measures as may be directed by the regulatory agency.
E. Penalties: Contractor to pay any fees and be liable for any other penalties that may be imposed by the reg ulatory agency for non -compliance with SWPPP during the course of work.
F. Costs: Contractor to pay all costs associated with the implementation of the requirements of the SWPPP/WPCP in order to maintain compliance with the Permit. This includes installation of all Housekeeping BMPs, General Site and Material Management BMPs, Inspection requirements, maintenance requirements, sampling, monitoring, reporting and all other requirements specified in the SWPPP/WPCP and as required by the General Permit, local, state and federal regulations.
1.11 MATERIALS:
A. General: All temporary and permanent storm water pollution prevention facilities, equipment, and materials as required by or as necessary to comply with the SWPPP/WPCP as described in the current California Stormwate r Quality Association (CASQA) BMP Handbook.
1.12 STORM WATER POLLUTION PREVENTION PLAN
A. Plan Preparation and Compliance
1. The Contractor shall conform to Section 13, Water Pollution Control, of the State Standard Specifications and the General Conditions, Special Conditions, and Technical Specifications.
2. The Contractor shall prepare a Storm Water Pollution Prevention Plan (SWPPP) and the necessary Project Registration Documents to be digitally filed with the California State Water Resources Control Board (SWRCB) through the Stormwater Multi -Application and Report Tracking System (SMARTS database). The Contractor will be responsible to provide the Permit Registration Documents (PRDs) to the City; the QSD will submit the PRDs for the WDID number through SMARTS. The SW PPP shall be prepared based upon the most current California Stormwater Quality Association (CASQA) standard SWPPP Template. The Contractor shall perform the role of “Qualified SWPPP Developer” (QSD) and shall be responsible for all formal amendments to the SWPPP. The Contractor shall also perform the role of “Qualified SWPPP Practitioner” (QSP) and shall be 330
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 9
responsible for all field SWPPP implementation, monitoring, sampling, and reporting. The completed SWPPP shall be created by the Contractor as necessary to reflect the necessary sequence and staging of field operations.
3. The SWPPP shall conform to SWRCB Order 2009 -0009-DWQ (“The Construction General Permit” or “CGP”), San Francisco Bay Regional Water Quality Control Board Order R2 -2009-0074 (“Municipal Re gional Stormwater NPDES Permit” or “MRP”), Provisions in Section 13, Water Pollution Control, of the State Standard Specifications, the details, operating procedures, and maintenance guidelines of the California Regional Water Quality Control Board San Fra ncisco Bay Region’s Guidelines for Construction Projects (Guidelines), the California Regional Water Control Board San Francisco Bay Region’s Erosion and Sediment Control Field Manual (Manual), the project plans and the General Conditions, Special Conditions, and Technical Specifications. The SWPPP shall be deemed to fulfill the requirements set forth in Section 13 of the State Standard Specifications for development and submittal of a Water Pollution Control Program.
4. Prior to the Notice to Proceed (with fi eld activities), the State Project Registration Documents (PRDs) will have been filed digitally through SMARTS, and confirmation from the SWRCB will have been received authorizing coverage of this project under the CGP. Construction cannot commence until a WDID has been received.
B. Risk Based Contractor Requirements and City Responsibilities (Applicable for all project risk levels/types) – The following minimum items shall be included within the SWPPP, as prepared by the Contractor
1. Risk Level Determination (to be performed by Contractor)
2. WDID Number (to be obtained by Contractor through coordination with City)
3. Certification by City “Legally Responsible Party” (LRP) (to be provided by City)
4. Placeholder for Contractor SWPPP training throughout construction
5. Name and contact information of Contractor QSD (to be provided by Contractor)
6. Name and contact information of Contractor QSP (to be provided by Contractor)
7. Schedule of Construction and Deployment of BMPs for each phase of work (to be provided by Contractor)
8. Description of minimum year round sediment control measures per Order 2009-009- DWQ
9. Dates and description of all formal SWPPP amendments (to be prepared by Contractor)
10. Description of Construction Site Monitoring Plan (CSMP) per Order 2009 - 009-DWQ (to be done by Contractor) including, but not limited to the following:
a. Sampling preparation,
b. Collection,
c. Quality assurance and quality control,
331
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 10
d. Sample labeling,
e. Collection documentation,
f. Sample shipping,
g. Chain of custody,
h. Sample numbering,
i. Precautions from the construction site health and safety plan, and j. Providing and maintaining a function rain gauge at all times.
11. Minimum required monitoring activities:
a. Post storm event (0.5” or greater) visual discharge inspection (within 48 hours).
b. Sampling for non-visible pollutants:
• Take one or more sample during any breach, spill, malfunction, or leakage that could discharge non visible pollutants into storm- water.
• Samples taken must be large enough to accurately categorize site conditions.
• Samples taken must be within the first 2 hours of rain events that occur during scheduled business hours that produce runoff. • Samples shall be analyzed for pollutants in accordance with • warrant as necessary for protection of surface waters. • An uncontaminated (control) sample must be taken as a basis of comparison.
• Samples must be received by the laboratory within 48 hours of physical sampling. The Contractor must use containers provided by the laboratory.
c. Quarterly inspections for non-stormwater discharges.
12. Minimum scheduled BMP inspections with appropriate documentation:
a. Weekly, on a year round basis, throughout the duration of construction. b. Daily (once every 24 hours) BMP inspection during extended storm events.
c. Inspect drainage areas and BMPs within 48 hou rs of predicted rainfall event (0.5” or greater).
13. Intent of compliance with the following analytical methods and sampling protocol:
a. Standard Methods for the Examination of Water and Wastewater (Amer- ican Public Health Association).
b. 40 CFR Part 136, "Guidelines Establishing Test Procedures for the Anal- ysis of Pollutants."
c. Surface Water Ambient Monitoring Program’s (SWAMP) 2008 Quality Assurance Program Plan.
14. Potential sources of non-visible pollutants
15. Description of all minimum source control measures, “good housekeeping”, and non stormwater management per Order 2009-009-DWQ
16. Other measures as necessary for Order 2009-009-DWQ
332
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 11
C. Risk Based Contractor Requirements and City Responsibilities (Applicable to Risk Level 2/LUP Type 2 or higher)
1. All requirements for Risk Level 1/Type 1 above
2. Description of applicable Numeric Action Levels for pH and turbidity (to be included in SWPPP by Contractor)
a. pH –levels must be maintained within a range of 6.5-8.5. b. Turbidity – 250 NTU maximum.
3. Description of additional provisions within the CSMP for stormwater effluent monitoring and reporting and non -stormwater discharges (to be included within SWPPP by Contractor):
a. Numeric Action Level (NAL) sampling:
• Water quality grab samples shall be taken at a minimum 3 times a day during each rain event of ½ an inch or more, where runoff occurs. The grab samples shall be representative of the flow and characteristic of the discharges. The contractor shall forward grab sampling results to the City within 24 hours of when they are taken. • All discharge points must be sampled, including the one consid- ered to be the “worst case.” Discharge from a silt fence or sheet flow area shall be considered one discharge point.
• All points of run on. A sheet flow area shall be considered one point of run on.
• Sampling to comply with analytical methods and protocol de- scribed in EPA Test Method 180.1.or Standard Method 2130 for turbidity sampling, ASTM D1293- 99(2005) for pH sampling, and Standard Methods for the Examination of Water and Wastewater (American Public Health Association).
c. Sampling for non-stormwater discharges.
4. Description of requirement to create and implement of “Rain Event Action Plans” for each of the following phases of construction (REAPs to be prepared by Contractor’s QSP):
a. Grading and Land Development,
b. Streets and Utilities,
c. Vertical Construction,
d. Final Landscaping and Stabilization,
e. Inactive Construction Status.
f. The Contractor shall create and implement Rainfall Event Action Plans for inclusion within approved SWPPP at least 48 hours prior to any likely (forecast by National Weather Service as 50% or greater chance) pre- cipitation event.
5. Description of year round effective erosion control measures to supplement minimum sediment control measures within active, inactive, and completed areas. Erosion control measures shall be provided to the extent necessary for compliance with Order 2009-009- DWQ.
333
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 12
6. Description of additional Annual Reporting Requirements (Annual reporting information to be prepared by Contractor for review and approval of City prior to submittal):
a. Creation and submittal of NAL exceedance reports, if applicable, b. Creation and submittal of sampling logs for pH and turbidity.
D. Risk Based Contractor Requirements and City Responsibilities (Applicable to Risk Level 3/LUP Type 3 only)
1. All requirements for Risk Level 2 projects described above.
2. Description of Required Compliance with State Board criteria for technology-based numeric effluent limitations for discharge of pH and turbidity (Description of req uirements and physical achievement provided by Contractor):
a. For Projects that employ Advanced Treatment Systems (ATS) - Maxi- mum 10 NTU Daily Weighted Average & Maximum 20 NTU for any sin- gle sample, applicable for events up to 24 hour events of ½ inches1. The ATS system must be able to treat this volume within a maximum 72-hour period.
b. For Projects that do not employ ATS - Maximum 500 NTU for any single sample, applicable for events up to 24 hour events up to ½ inches2. c. Project discharges must maintain pH within a range of 6.0 to 9.0.
3. Description of additional provisions within the CSMP (description of monitoring provided by Contractor, additional monitoring performed by Contractor):
a. Receiving water monitoring, if applicable, based upon the standar ds of Order 2009- 009-DWQ.
b. Bioassessment, if applicable, based upon the standards of Order 2009- 009-DWQ.
c. Sampling for Suspended Sediment Concentration, if applicable, based upon the standards of Order 2009 -009-DWQ. Sampling to comply with analytical methods and protocol described within ASTM Designation: D 3977 for suspended sediment concentration (SSC).
d. Inspection of ATS facilities, if applicable. Sampling of ATS discharge points.
4. Placeholder for Creation of ATS Plan, if applicable, consisting of the following (to be provided by Contractor):
a. ATS Operation and Maintenance Manual for All Equipment. b. ATS Monitoring, Sampling & Reporting Plan, including Quality Assur- ance/Quality Control (QA/QC).
c. ATS Health and Safety Plan.
d. ATS Spill Prevention Plan.
334
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 13
5. Description of Additional annual reporting requirements (Description provided by Contractor, Annual Reporting information to be prepared by Contractor for review and approval of City)
a. Creation and submittal of NEL violation reports, if applicable within 6 hours of occurrence. Reports and related corrective action measures to be reviewed and approved by City prior to submittal to Regional Board b. Completed ATS records, if applicable.
PART 2 - PRODUCTS
2.1 BEST MANAGEMENT PRACTICE (BMP) PRODUCTS
A. Shall be as specified in the most current CASQA BMP Handbook.
B. SWPPP as prepared by Qualified SWPPP Developer (QSD) C. Risk Level Determination
D. Notice of Intent/Notice of Substantial Completion
E. Shall include but is not limited to sampling, reports and other miscellaneous items as determi ned by the State of California and all pertaining regional and local permits.
PART 3 - EXECUTION
3.1 EROSION AND SEDIMENTATION CONTROL
A. Temporary erosion and sediment control work shall consist of applying erosion control materials to embankment slopes, excavation slope s and other areas designated on the plans, installing silt fence, inlet protection, gravel bags, headwall protection and stabilized construction entrance ways, or other measures as specified in the project SWPPP/WPCP or necessary for compliance with the CGP.
B. All temporary erosion and sediment control for the project shall conform to the provisions in Section 13, Water Pollution Control, of the State Standard Specifications and the General Conditions, Special Conditions, and Technical Specifications. All permanent erosion and sediment control for the project shall conform to the provision in Section 21, Erosion Control, of the State Standard Specifications and the General Conditions, Special Conditions, and Technical Specifications.
335
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 14
3.2 INSTALLATION
A. Construction Requirements
1. The Contractor shall design, implement and maintain the SWPPP/WPCP for the project in full compliance with the SWRCB Order 2009-009-DWQ to control the discharge of storm water pollutants. The Contractor shall perform the monitorin g and reporting required to comply with all the state regulations regarding the SWPPP/WPCP for the project. All monitoring, sampling, and reporting information collected by the Contractor shall be subject to the review of the City prior to uploading throug h the SMARTS database.
B. Storm Water Pollution Prevention Plan and Water Pollution Control Plan
1. The SWPPP/WPCP shall identify construction activities that may adversely affect the quality of storm water discharges associated with the project and shall identi fy water pollution control measures, hereinafter referred to as control measures, to be constructed, implemented, and maintained in order to reduce, to the maximum extent feasible, storm water discharges from the construction site both during and after construction is completed under this contract.
2. The Contractor’s “QSD” shall amend the SWPPP/WPCP, graphically and in narrative form, whenever there is a change in construction activities or operations which may affect the discharge of significant quantities o f pollutants to surface waters, ground waters, municipal storm drain systems, whenever there is a change in disturbed area, and/or or when deemed necessary by the City. The SWPPP/WPCP shall be amended if, at any time, the implementation of the SWPPP/WPCP i s not effectively achieving the objective of compliance with the CGP. Amendments shall show additional control measures or revised operations, including those in areas not shown in the initial SWPPP/WPCP, which are required on the project to control water pollution effectively. Amendments to the SWPPP/WPCP shall be closely coordinated with the Contractor’s Qualified SWPPP Practitioner (QSP) within five ( 5) working days. In emergency situations that require immediate changes at the project site, the Contract or’s QSP shall implement the necessary measures and notify the Project Manager and Contractor’s QSD of the changes.
3. The Contractor shall give immediate notice to the Project Manager of any planned changes in construction activity that may result in non-compliance with the General Conditions, Special Conditions, and Technical Specifications or the CGP.
4. By the last day of each month, the Contractor shall submit an affidavit to the Project Manager certifying conformance with the SWPPP/WPCP. The monthly partial payment may be withheld if the affidavit is not received and accepted by the Project Manager. If at any time the project is in non - compliance with the SWPPP/WPCP or the CGP, the Contractor shall submit a written report to the Project Manager immediately upon identifying the 336
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 15
non-compliance. The report shall specify the time and nature of the non - compliance and include a course of action to correct the deficiency.
5. The Contractor shall keep a copy of the State of California Construction Activity General Permit (SWRCB Order No. 2009 -009-DWQ), the SWPPP/WPCP, and any approved amendments at the project site. The SWPPP/WPCP shall be made available upon request of any representative of the Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency, or any City representative. Public requests for copi es of the SWPPP/WPCP shall be directed to the Project Manager.
C. Erosion and Sediment Control
1. The facilities shown on the SWPPP/WPCP are designed to effectively control erosion and sediment on a year-round basis.
a. Construction operations shall be carried out in such a manner that erosion and water pollution will be minimized. Contractor shall comply with state and local laws concerning pollution abatement. b. Contractor shall be responsible for monitoring erosion and sedi- ment control measures prior, during, and a fter storm events.
Monitoring and sampling (as applicable) shall follow the protocol described in the CGP and Project SWPPP//WPCP.
a. Extreme care shall be taken when hauling any earth, sand, gravel, stone, debris, paper, or any other substance over any public street, alley or other public place. Occurrences of material blown, spilled, or tracked over and upon said public or adjacent private property are prohibited and shall be immediately remedied. Discharge of debris is prohibited. Non-stormwater discharge is prohibited, except as speci- fied in SWRCB Order 2009-009-DWQ. Discharge of hazardous sub- stances is prohibited.
b. Inlet protection shall be installed at open inlets to prevent sediment from entering the storm drain system. Inlets not used in conjunction with erosion control are to be blocked to prevent entry of sediment. c. All paved areas shall be kept clear of earth material and debris. The site shall be maintained so as to prevent sediment-laden runoff to any storm drainage system, including existing drainage swales and water- course, to the extent necessary for compliance with applicable nu- meric action or effluent levels specified in the CGP and Project SWPPP/WPCP.
d. Contractor shall install and maintain construction entrances prior to commencement of grading. All construction vehicle traffic entering onto the paved roads must cross stabilized construction entrance ways. Entrance ways may be constructed of two inch to six-inch drain rock, metal grating, or metal cattle -guard, or equivalent material , or may include vehicle wash stations as needed, in sufficient quantity and size to prevent tracking of mud and debris from the construction site.
Tracking of mud or debris onto public streets, or onto adjacent public 337
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 16
or private property, is prohibited and shall be removed immediately as required by the City.
e. Grading operations which leave denuded slopes shall be protected with erosion control measures within 14 days of completion or sus- pension of activity. If hydroseeding is not used or is not effective within this 14-day period, then other immediate methods shall be im- plemented, such as erosion control blankets, blown straw, or a three step application of 1) seed, mulch, fertilizer, 2) blown straw, and 3) tackifier and mulch.
f. Sanitary facilities shall be maintained on the site in a manner to pre- vent inadvertent discharge or leakage of sanitary wastes into the storm drain system either by placing sanitary facilities in locations that do not drain to the storm drain system or by providing secondary con- tainment systems to capture leaked wastes.
g. Contractor shall provide dust control as required by the appropriate federal, state and City requirements and the City Standard Specifica- tions.
h. The erosion and sediment control plan may not cover all the situations that may arise during construction due to unanticipated field condi- tions. Variations and additions may be made to the plan in the field.
That Contractor’s QSP shall notify the Contractor’s QSD of any field changes.
D. Maintenance: The SWPPP/WPCP shall include a plan for maintenance that shall include at a minimum.
1. Immediate repair of damage caused by soil erosion or construction.
2. Inspection of sediment traps, berms, rills, gullies, and swales before, during, and after each storm event or predicted rainfall in accordance with the CGP and project SWPPP/WPCP. This also includes repair or cleaning as needed.
3. Removal of sediment from sediment traps and restoration to original dimensions when sediment has accumulated to a dept h of one foot.
Sediment removed from trap shall be deposited in a suitable area and in such a manner that it will not erode.
4. Regular cleaning of gravel bag inlet protection so that sediment depth never exceeds a maximum of three inches.
E. Risk Based Contractor Requirements and City Responsibilities (Applicable for all project risk levels/types) – The following minimum items shall be performed by the Contractor during field implementation of the Project SWPPP/WPCP throughout the duration of construction until final Notice of Termination
1. Coordinate and conduct periodic SWPPP/WPCP and Erosion and Sediment Control training throughout construction
2. Update schedule of construction and deployment of BMPs for each phase of work on an as-needed basis
3. Physically install and maintain minimum year-round sediment control measures per Order 2009-009-DWQ
338
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 17
4. Perform and file all formal SWPPP/WPCP amendments. All SWPPP/WPCP amendments to be reviewed and approved by the City and the Contractor’s QSD prior to submittal.
5. Physically pe rform and implement all measures found within the SWPPP/WPCP Construction Site Monitoring Plan (CSMP) per Order 2009- 009-DWQ including, but not limited to the following:
a. Sampling preparation,
b. Collection,
c. Quality assurance and quality control,
d. Sample labeling,
e. Collection documentation,
f. Sample shipping,
g. Chain of custody,
h. Sample numbering,
i. Precautions from the construction site health and safety plan, and j. Providing and maintaining a function rain gauge at all times.
6. Minimum required monitoring activities:
a. Post storm event (0.5” or greater) visual discharge inspection (within 48 hours).
7. Sampling for non-visible pollutants:
a. Take one or more sample during any breach, spill, malfunction, or leakage that could discharge nonvisible pollutants into stormwater. • Samples taken must be large enough to accurately categorize site conditions.
• Samples taken must be within the first 2 hour s of rain events that occur during scheduled business hours that produce runoff. • Samples shall be analyzed for pollutants in accordance with an appropriate pollutant source assessment, or as conditions warrant as necessary for protection of surface waters.
• An uncontaminated (control) sample must be taken as a basis of comparison.
• Samples must be received by the laboratory within 48 hours of physical sampling. The Contractor must use containers provided by the laboratory.
b. Quarterly inspections for non-stormwater discharges.
8. Minimum scheduled BMP inspections with appropriate documentation:
a. Weekly, on a year-round basis, throughout the duration of construc- tion.
b. Daily (once every 24 hours) BMP inspection during extended storm events.
c. Inspect drainage areas and BMPs within 48 hours of predicted rainfall event (0.5” or greater).
9. Compliance with the following analytical methods and sampling protocol:
a. Standard Methods for the Examination of Water and Wastewater 339
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 18
(American Public Health Association).
b. 40 CFR Part 136, "Guidelines Establishing Test Procedures for the Analysis of Pollutants."
c. Surface Water Ambient Monitoring Program’s (SWAMP) 2008 Quality Assurance Program Plan.
10. Identify and eliminate potential sources of non-visible pollutants
11. Implementation of all minimum source control measures, “good housekeeping”, and non-stormwater management per Order 2009 -009- DWQ
12. Other measures as necessary for Order 2009-009-DWQ
F. Risk Based Contractor Requirements and City Responsibilities (Applicable to Risk Level 2/LUP Type 2 or higher)
1. All requirements for Risk Level 1/Type 1 above
2. Maintain tolerance of site discharge within applicable Numeric Action Levels for pH and turbidity
a. pH –levels must be maintained within a range of 6.5-8.5. b. Turbidity – 250 NTU maximum.
3. Numeric Action Level (NAL) sampling:
a. Water quality grab samples shall be taken at a minimum 3 times a day during each rain event of ½ an inch or more, where runoff occurs.
The grab samples shall be representative of the flow and character- istic of the discharges. The contractor shall forward grab sampling results to the City within 24 hours of when they are taken. b. All discharge points must be sampled, including the one considered to be the “worst case.” Discharge from a silt fence or sheet flow area shall be considered one discharge point.
c. All points of run on. A sheet flow area shall be considered one point of run on.
d. Sampling to comply with analytical methods and protocol described in EPA Test Method 180.1 or Standard Method 2130 for turbidity sam- pling, ASTM D1293- 99(2005) for pH sampling, and Standard Meth- ods for the Examination of Water and Wastewater (American Public Health Association).
4. Sampling for non-stormwater discharges
5. Create and physically implement of “Rain Event Action Plans” for each of the following phases of construction:
a. Grading and Land Development,
b. Streets and Utilities,
c. Vertical Construction,
d. Final Landscaping and Stabilization,
e. Inactive Construction Status.
340
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 19
6. The Contractor shall create and implement Rainfall Even t Action Plans for inclusion within approved SWPPP/WPCP at least 48 hours prior to any likely (forecast by National Weather Service as 50% or greater chance) precipitation event.
7. Physically implement and maintain year-round effective erosion control measures to supplement minimum sediment control measures within active, inactive, and completed areas. Erosion control measures shall be provided to the extent necessary for compliance with Order 2009 -009- DWQ.
8. Maintain and compile documents to meet Annual Report ing Requirements (Annual reporting information to be prepared by Contractor for review and approval of City prior to submittal):
a. Creation and submittal of NAL exceedance reports within 48 hours, if applicable, based upon review and approval of City.
b. Creation and submittal of sampling logs for pH and turbidity.
G. Risk Based Contractor Requirements and City Responsibilities (Applicable to Risk Level 3/LUP Type 3 only)
1. All requirements for Risk Level 2 projects described above.
2. Maintain physical compliance with State Board criteria for technology-based numeric effluent limitations for discharge of pH and turbidity
3. For Projects that employ Advanced Treatment Systems (ATS) - Maximum 10 NTU Daily Weighted Average & Maximum 20 NTU for any single sample, applicable for events up to 24-hour events of ½ inches3. The ATS system must be able to treat this volume within a maximum 72-hour period.
4. For Projects that do not employ ATS - Maximum 500 NTU for any single sample, applicable for events up to 24-hour events up to ½ inches4.
5. Project discharges must maintain pH within a range of 6.0 to 9.0.
6. Perform additional provisions within the CSMP:
a. Receiving water monitoring, if applicable, based upon the standards of Order 2009- 009-DWQ.
b. Bioassessment, if applicable , based upon the standards of Order 2009-009-DWQ.
c. Sampling for Suspended Sediment Concentration, if applicable, based upon the standards of Order 2009 -009-DWQ. Sampling to comply with analytical methods and protocol described within ASTM Designation: D 3977 for suspended sediment concentration d. Inspection of ATS facilities, if applicable. Sampling of ATS discharge points.
7. Creation and implementation of ATS Plan, if applicable, consisting of the following:
a. ATS Operation and Maintenance Manual for All Equipment. b. ATS Monitoring, Sampling & Reporting Plan, including Quality Assur- ance/Quality Control (QA/QC).
c. ATS Health and Safety Plan.
341
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 20
d. ATS Spill Prevention Plan.
8. Maintain and compile additional annual reporting requirements (Annual Reporting information to be prepared by Contractor for review and approval of City prior to submittal)
a. Creation and submittal of NEL violation reports, if applicable within 6 hours of occurrence. Reports and related corrective action measures to be reviewed and appr oved by City prior to submittal to Regional Board
b. Completed ATS records, if applicable.
3.3 STREET SWEEPING
A. Street sweeping: Street sweeping will be implemented everywhere where sediment is tracked from the project site onto public roads. Sweeping will be done during all construction activities to control tracking of sediments as required as per the guidelines provided in the SWPPP document and as directed in this section.
3.4 DUST CONTROL
A. Contractor’s Responsibility: Use equipment that will generate the least amount of dust. Provide dust control at all times including Saturdays, Sundays, and holidays as ordered by the Project Manager. Whenever the Contractor, in the opinion of the Project Manager, is negligent in controlling dust, the Project Manager may direct attention to the existence of a dust hazard and instruct the Contractor to immediately alleviate the dust hazard. The Contractor shall be responsible for any damage cause by dust generated as a result of its operations.
B. Street Vacuum/Sweeper: Have a commerc ial standard street vacuum/sweeper operational and in operation during each working day. The street vacuum/sweeper shall be able to pick up sand, gravel, dust, and debris, and other things, shall minimize dust generation, and shall also be available during the day and shall sweep as outlined below and as directed by the Project Manager.
C. Sweeping: If the Contractor is performing work that generates dust and debris then during the day (including weekends and holidays) the sweeper shall sweep the project area (full length, width, and all lanes) twice a day sometime between 9:00a.m. and 11:00a.m. and also between 2:00p.m. and 4:00p.m. Hardscape surfaces (including pavers, sidewalks, and areas inaccessible by a mechanical sweeper) shall have dirt, dust, and debris removed by hand sweeping. If the Contractor fails to fulfill the responsibilities of this Section the City will perform or contract with others to perform the work and all costs incurred to the City shall be withheld from future payments to the Contractor.
342
City of Pittsburg, California December 2022
STORM WATER POLLUTION PREVENTION PLAN 01 57 23 - 21
D. Additional Sweeping: Clean the sidewalk and gutter as many times as needed to make sure the sidewalk and gutter are out of dirt, debris and small rocks at all times. Be prepared to sweep surfaces immediately at the request of the Project Manager should it be deemed necessary for public safety and to avoid damage to properties. If streets are not satisfactorily cleaned within 12 hours from verbal or written notice by City personnel, the City will hire an independent sweeping company and deduct the cost for such work from payments due to the Contractor.
E. Payment for Dust Control and Clean Up: Shall be included in the prices paid for Storm Water Pollution Prevention Plan (SWPPP) or Water Pollution Control Plan (WCPC) as shown in the Bid Schedule or considered incidental to the items most closely related to when there is no bid item. This Item shall be considered as full compensation for all labor, materials, tools, equipment and incidentals and for doing the work of Dust Control and Clean Up and no add itional compensation shall be made therefor.
3.5 EMERGENCY EROSION AND SEDIMENT CONTROL
A. Shall consist of any measures not addressed in the SWPPP/WPCP that the Project Manager or QSD deems necessary for compliance with the CGP including, but not limited to all erosion control measures necessary to prevent degradation to water quality.
B. Sediment Control including unforeseen measures not addressed in the Storm Water Pollution Plan pay item in accordance with the National Pollution Discharge Elimination System (NPDES), the City of Pittsburg and the Plans and Specifications and to the satisfaction of the Project Manager. Work under this item shall be considered as extra work paid for on a force account basis.
END OF SECTION 01 57 23
343
City of Pittsburg, California December 2022
PRODUCT REQUIREMENTS 01 60 00 - 1
SECTION 01 60 00 – PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements governing the Contractor's selection of products for use in the Project.
1.2 DEFINITIONS
A. Products:
1. General: Items purchased for incorporation in the Work, whether purchased for the Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.
2. Named Products: Items identified by the manufacturer's product name, including make or model number or other designation, shown or listed in the manufacturer's published product literature, that is current as of the date of the Contract Documents.
3. Materials: Components shaped, cut, worked, mixed, finished, refined or otherwise fabricated, processed, or installed to form a part of the Work.
4. Equipment: Product with operational parts, whether motorized or manually operated, that requires service connections, such as wiring or piping.
1.3 QUALITY ASSURANCE
A. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source.
B. Compatibility of Options: When the Contractor is given the option of selecting between 2 or more products for use on the Project, the product selected shall be compatible with products previously selected, even if previously selected products were also options.
1.4 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. General: Deliver, store, and handle products according to the manufacturer's recommendations, using means and methods that will prevent damage, deterioration, and loss, including theft.
1. Schedule delivery to minimize long-term storage at the site and to prevent overcrowding of construction spaces.
2. Coordinate delivery with installation time to assure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
344
City of Pittsburg, California December 2022
PRODUCT REQUIREMENTS 01 60 00 - 2
3. Deliver products to the site in an undamaged condition in the manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
4. Inspect products upon delivery to ensure compliance with the Contract Documents and to en sure that products are undamaged and properly protected.
5. Store products at the site in a manner that will facilitate inspection and measurement of quantity or counting of units.
6. Store heavy materials away from the Project structure in a manner that will not endanger the supporting construction.
7. Store products subject to damage by the elements above ground, under cover in a weathertight enclosure, with ventilation adequate to prevent condensation. Maintain temperature and humidity within range required by manufacturer's instructions.
PART 2 - PRODUCTS
2.1 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Products complying with specified reference standards or description.
B. Products Specified by Naming One or More Manufacturers: Products of one of manufacturers named and complying with Specifications; no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with Provision for Substitutions: Submit Request for Substitution for any manufacturer not named, according to Section 01 25 00 - Substitution Procedures.
PART 3 - EXECUTION
3.1 INSTALLATION OF PRODUCTS:
A. General: Refer to Section 01 70 00 – Execution.
B. Product Handling: Assure that Work is manufactured and/or fabricated in ample time to not delay construction progress. Transport, handle, store and protect products in accordance with manufacturer’s instructions.
END OF SECTION 01 60 00
345
City of Pittsburg, California December 2022
EXECUTION 01 70 00 - 1
SECTION 01 70 00 – EXECUTION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes requirements for field engineering, examination, preparation, execution, cleaning, and protecting installed construction.
B. Field Engineering: Provide such field engineering services as are required for proper completion of the Work including, but not limited to:
1. Establishing and maintaining lines and levels.
2. Structural design of shores, forms, and similar items provided by the Contractor as part of the means and methods of construction.
1.2 QUALITY ASSURANCE
A. Workers: Use adequate numbers of skilled workers who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specific requirements and the methods needed for pro per performance of the work of this Section.
1.3 SUBMITTALS
A. Comply with Section 01 33 00 - Submittal Procedures.
B. Upon request of the Project Manager, submit the following:
1. Engineering qualifications of persons proposed to be engaged for field engineering services.
2. Documentation verifying accuracy of field engineering work.
3. Certification, signed by the Contractor’s retained field engineer, certifying that elevations and locations of improvements are in conformance with requirements of the Contract Documents. Documentation shall require surveyor’s certification stamp.
1.4 REFERENCE POINTS
A. In addition to the procedures directed by the Contractor for proper perfor mance of the Contractor’s responsibilities:
1. Locate and protect control points before starting work on the site.
2. Preserve permanent reference points during progress of the Work.
3. Do not change or relocate reference points or items of the Work with out specific approval from the Project Manager.
346
City of Pittsburg, California December 2022
EXECUTION 01 70 00 - 2
4. Notify and advise the Project Manager within twenty -four (24) hours when a reference point is lost or destroyed, or requires relocation because of other changes in the Work:
a. Upon direction of the Project Manager, require the field engineer to re- place reference stakes and/or markers.
b. Locate such replacements according to the original survey control.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that existing Site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.
C. Examine and verify specific conditions described in individual Specification Sections.
D. Verify that utility services are available with correct characteristics and in correct locations.
3.2 PREPARATION
A. Clean substrate surfaces prior to applying next material or substance according to manufacturer's instructions.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply manufacturer -required or manufacturer-recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.
3.3 EXECUTION
A. Comply with manufacturer's installation instructions, performing each step-in sequence. Maintain one set of manufacturer's installation instructions at Project Site during installation and until completion of construction.
B. When manufacturer's installation instruc tions conflict with Contract Documents, request clarification from Project Manager before proceeding. 347
City of Pittsburg, California December 2022
EXECUTION 01 70 00 - 3
C. Verify that field measurements are as indicated on approved Shop Drawings or as instructed by manufacturer.
D. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.
1. Secure Work true to line and level and within specified tolerances, or if not specified, industry-recognized tolerances.
2. Physically separate products in place, provide electrical insulation, or provide protective coatings to prevent galvanic action or corrosion between dissimilar metals.
3. Exposed Joints: Provide uniform joint width and arrange to obtain best visual effect. Refer questionable visual -effect choices to Project Manager for final decision.
E. Allow for expansion of materials and/or movement.
F. Climatic Conditions and Project Status: Install each unit of Work under conditions to ensure best possible results in coordination with entire Project.
1. Isolate each unit of Work from incompatible Work as necessary to prevent deterioration.
2. Coordinate enclosure of Work with required inspections and tests to minimize necessity of uncovering Work for those purposes.
G. Mounting Heights: Where not indicated, mount individual units of Work at industry recognized standard mounting heights for particular application indicated.
1. Refer questionable mounting heights choices to Project Manager for final decision.
2. Elements Identified as Accessible to Handicapped: Comply with applicable codes and regulations.
H. Adjust operating products and equipment to ensure smooth and unhindered operation.
I. Clean and perform maintenance on installed Work as frequently as necessary through remainder of construction period. Lubricate operable compone nts as recommended by manufacturer.
3.4 CLEANING
A. Maintain Project Site, surrounding areas and public properties free from accumulations of waste, debris, and rubbish, caused by operations.
B. At completion of Work, remove waste materials, rubbish, tools, equipmen t, machinery and surplus materials, and clean all sight -exposed surfaces; leave Project Site clean and ready for occupancy.
C. Hazards Control:
1. Conduct cleaning and disposal operation in accord with legal requirements. 348
City of Pittsburg, California December 2022
EXECUTION 01 70 00 - 4
2. Do not burn or bury rubbish and waste materials on Project Site.
3. Do not dispose of volatile wastes in storm or sanitary drains.
4. Store volatile wastes in covered metal containers, and remove from premises daily.
5. Prevent accumulation of wastes which create hazardous conditions.
6. Provide adequate ventilation during use of volatile or noxious substances.
Ventilation shall be other than ventilation system.
D. Materials:
1. Use only cleaning materials recommended by manufacturer of surface to be cleaned.
2. Use cleaning materials only on surfaces recommended by cleaning material manufacturer.
E. During Construction:
1. Execute cleaning daily to ensure Project Site, Owner's premises, adjacent and public properties are maintained free from accumulations of waste materials and rubbish.
2. Wet down dry materials and rubbish to control dust.
3. At reasonable intervals during progress of Work, clean Project Site and public properties, and dispose of waste materials, debris and rubbish.
4. Provide on Project Site dump containers for collection of waste materials, debris and ru bbish. Waste containers shall not be used for construction waste.
5. Remove waste materials, debris and rubbish from Owner's premises and legally dispose of off Owner's property.
6. Handle materials in a controlled manner with as few handlings as possible.
Do not drop or throw materials.
3.5 PROTECTING INSTALLED CONSTRUCTION
A. Protect installed Work and provide special protection where specified in individual Specification Sections.
B. Provide temporary and removable protection for installed products. Control activity in immediate Work area to prevent damage.
C. Prohibit traffic from landscaped areas.
END OF SECTION 01 70 00
349
City of Pittsburg, California December 2022
MOBILIZATION 01 71 13 - 1
SECTION 01 71 13 – MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes but not limited to:
1. mobilization and demobilization;
2. preparatory work and activities those necessary for the movement of personnel, equipment, supplies, and incidentals to the job site;
3. for the establishment of all offices, building , trailers, and other facilities necessary for work on the project;
4. submittals, bonding and insurance requirements;
5. public notifications in English and Spanish;
6. contacting and notifying the utility companies;
7. fabricating and installing project identification signs;
8. private property owner agreement for storage facilities;
9. and for all other work and activities which must be performed or costs incurred prior to beginning work on the various contract items on the project site.
1.2 REFERENCES
A. Cal/OSHA – California Division of Occupation Safety and Health B. Underground Services Alert (USA)
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Measurement and Payment:
1. When mobilization is included as a bid item, measurement will be made as a percentage of the costs incurred according to the list submitted except that not more than 75% of the bid price shall be paid prior to the final estimate for payment being due, said remaining 25% paid upon completion of cleanup and removal and demobilization with final payment.
2. When the contract does not include a contract pay item for mobilization, full compensation for any necessary mobilization required shall be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed therefore. 350
City of Pittsburg, California December 2022
MOBILIZATION 01 71 13 - 2
3. The contract price paid for mobilization shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in mobilization and demobilization including the items listed in Part 1.1 of this Section as specified herein, and no additional compensation shall be made therefor.
4. Mobilization shall be considered as a non -adjustable contract item. Any contract change orders shall be considered as including full compensation for mobilization.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 MOBILIZATION
A. Mobilization shall consist of preparatory work and activitie s listed in Part 1.1 above.
B. The Contractor shall insure that adequate existing sanitation facilities are available or the Contractor shall provide and maintain adequate sanitation facilities. All wastes and refuse from sanitary facilities provided by the Contractor’s operations shall be disposed of away from the site in accordance with all laws and regulations pertaining thereto.
C. Mobilization shall also include demobilization upon completion of work and cleanup of the site.
D. The contractor shall provide all labor, materials, equipment and incidentals to prepare the site for the timely start and efficient completion of all work. This includes obtaining all necessary licenses and permits, providing required submittals including but not limited to a detailed project schedule.
E. Mobilization shall also include notifications to all existing utility companies as shown on the Drawings as first order of work.
END OF SECTION 01 71 13
351
City of Pittsburg, California December 2022
CONSTRUCTION SURVEYING 01 71 23 - 1
SECTION 01 71 23 – CONSTRUCTION SURVEYING
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes but not limited to:
1. Control Line Survey
2. Pothole Survey
3. Survey Monument Referencing
4. Construction Staking
5. Quality Control Survey
6. As-built GPS Survey
B. All surveying work shall be performed under the responsible charge of a land surveyor licensed in the State of California.
1.2 REFERENCES
A. Cal/OSHA – California Division of Occupation Safety and Health
B. Underground Services Alert (USA)
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Section 02 21 13 - Survey Monuments.
1.4 MEASUREMENT AND PAYMENT
A. The contract price paid for Construction Surveying shall include full compensation for furnishing all l abor, materials, tools, equipment and incidentals, and for doing all the work involved in control line survey, survey monument referencing, pothole survey, construction staking, quality control survey and as -built GPS Surveys specified herein, and no additional compensation shall be made therefor.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 GENERAL
352
City of Pittsburg, California December 2022
CONSTRUCTION SURVEYING 01 71 23 - 2
A. All work shall be done in accordance with Chapter 12 of the Caltrans Surveys Manual, Division 00 – General Conditions, Section 7.17, the Special Conditions, the Contract Plans, and as directed by the Engineer.
B. Contractor shall provide all the project construction surveying and all costs related to establishing a control line, pothole surveying, construction staking, documenting all changes to plans, providing quality control surveying, performing an as -built survey and submitting AutoCAD files of the as -built information. All construction surveying shall be performed under the direction of a Professional Land Surveyor licensed in the State of California. The Contractor shall be responsible for all land surveying and shall be responsible for replacing control points or survey monuments lost or damaged during the course of construction
3.2 CONTROL LINE SURVEY
A. Prior to any construction surveying contractor will allow for field surveying and office surveying to check the field control shown on the Drawings, and to set construction control points. This survey will be a stand-alone move-in specifically to verify control points. Work includes: collect CAD files from City, submit signed CAD release forms, go to field and tie -in control points, compare the x,y,z of the field data with the x,y,z on the CAD files, establish additional new field control points for construction, and submit CAD file of the existing and new control analysis to engineer for review. All project construction surveying shall be based on this established control line.
3.3 POTHOLE SURVEY
A. For Projects requiring pothole survey by a Lic ensed Land Surveyor, during the potholing excavation and exposure of the existing utility, the Contractor’s licensed Land Surveyor shall perform a topographic survey of the existing grade, top of pipe of the existing utilities, location of the utility on t he project coordinate system.
Contractor shall document the outside diameter of the pipe and the pipe material.
Contractor shall submit the pothole survey with the above specified information in an AutoCAD Drawing file to the City engineer. CAD point descr iptions to include the type of exposed pipe and diameter (example: “12” water”)
3.4 SURVEY MONUMENT REFERENCING
A. For Survey Monument Referencing, refer to Section 02 21 13 - Survey Monuments.
3.5 CONSTRUCTION STAKING
A. The Contractor shall submit a AutoCAD files to the engineer three (3) working days prior to any staking operation. AutoCAD files will show the calculated survey points with CAD elevations and CAD descriptio ns as part of the calculated topographic 353
City of Pittsburg, California December 2022
CONSTRUCTION SURVEYING 01 71 23 - 3
shots. Cut sheets in -lieu of this requirement will not be accepted. CAD points must include the elevations in CAD.
B. Construction staking shall be defined as: “Markings set in the field by a CA Licensed Land Surveyor, prior to construction, with horizontal coordinates and vertical dimensions to the items identified below. All field markings shall be completed under the d irection of Land Surveyor licensed by the State of California.” The Contractor shall be responsible for replacing established survey points lost or damaged during the course of construction.
C. The list below includes some but not limited to items to be surveyed/staked.
1. Curb/Curb & Gutter - Top of curb, flow line and lip of gutter at begin of curve, end of curve, every 25' and at all changes in direction.
2. Flushed concrete curb at begin of curve, end of curve, e very 25' and at all changes in direction.
3. Concrete pavers borders
4. Concrete paving parking
5. Concrete paving intersection
6. Curb ramps (beginning, end, mid-point, back corners)
7. Truncated dome pavers
8. Concrete Expansion Joints
9. Trees
10. Irrigation Meter and Boxes
11. Traffic Signal Poles and Boxes
12. Storm Drainage Inlets and other drainage structures
13. Trench drains
14. Curb drains
15. Storm Drainage Piping Inverts every 25' and at all changes in direction
16. Storm Drainage Manhole Inverts
17. Sanitary Sewer Piping Inverts every 25' and at all changes in direction
18. Sanitary Sewer Manhole Inverts
19. Sanitary Sewer Cleanout
20. Sanitary Sewer Laterals
21. Water Main Piping Inverts every 25' and at all changes in direction
22. Water Main offsets
23. Water Valves
24. Air Release Valves
25. Blow off
26. Water Meters
27. Fire Hydrants
28. Joint Trench every 25' and at all changes in direction
29. Utility Vaults
30. Street light pull boxes
31. Pedestrian Lighting
32. Street Lighting
33. Edges of bands a planter curbs
354
City of Pittsburg, California December 2022
CONSTRUCTION SURVEYING 01 71 23 - 4
34. Concrete band
35. Corners of Concrete at AC paving limits
36. Bottom and top of concrete speed table slopes
37. Parking strip ticks (one stake each)
38. Parking meter (one stake each)
39. Handicap parking (8 Stakes)
40. Bench
41. News rack & corral (3 stakes each)
42. Midblock arbor, park road arbor (12 stakes each)
43. Bike rack
44. Trash receptacle
45. Fixed bollard, retractable bollard
46. Downspout storm lateral connection. Staking calculations to be adjusted based on field verified building drain locations exposed during demolition.
47. Other staking requirements as described in the Technical Specifications.
3.6 QUALITY CONTROL SURVEY
A. These survey verifications shall occur one (1) working days prior to pouring concrete. Submit AutoCAD file of the quality control survey to the Engineer one (1) working days prior to pouring concrete curbs and foundations. AutoCAD survey files will show the topographic survey points with elevations and descriptions. Descriptions and elevations will be on the CAD points and not on a separate cut sheet. Contractor will replace any curbs, street lights and pole foundations not checked prior to pouring concrete.
B. No concrete shall be poured until each quality control survey item described below has been approved by the Engineer, based on survey CAD file provided by contractor’s surveyor. Prior to pouring concrete or proceeding beyond subgrade.
C. Listed below are the project elements which require quality control survey and CAD submittal reviews prior to concrete pouring.
1. Curbs and Curb & Gutter: After the curb forms are set, the contractor’s licensed land surveyor shall survey the top of curb form every 25’ and at key conforms.
2. Subgrade for Street Paving: Field survey and certify the top of aggregate base design grades every 50 feet along the centerline of each lane or on corners of a 12’x50’ grid in a parking lot for projects greater than or equal to 5 ,000 square feet of asphalt concrete. Submit certification signed by a Licensed Land Surveyor.
355
City of Pittsburg, California December 2022
CONSTRUCTION SURVEYING 01 71 23 - 5
3.7 AS-BUILT SURVEY
A. After the trench excavation and pipe installation, the Contractor’s licensed land surveyor shall perform a topographic survey of the top of pipes for the utility lines and invert of pipe for all gravity pipes every 25’, and at all changes in direction both horizontal and vertical, water valves, tees, water services, fire hydrants and at all manhole. This survey verification shall occur 3 days prior to backfilling trench.
AutoCAD files will show the calculated survey points with elevations and descriptions.
B. Contractor shall be responsible for documenting all changes to the plans. The Contractor/Developer shall provide the as ‐built survey in .dwg file (tied to NAD83 California State Planes, Zone III) format in AutoCAD 201 7 or later version electronically and stored in a USB flash drive. The Contractor/Developer shall deliver one full set (22x34) of hard copy certified by the License Land Surveyor.
C. A CAD drawing and coordinates data sheet shall be submitted to the Project Manager for approval. This task must b e performed by a registered professional land surveyor licensed in the state of California. Data shall be tied to NAD83 California State Planes, Zone III, US Foot. The elevations shall be based on NAVD88 datum. This survey shall be delivered to the City’s Engineer of Record.
This survey shall be used for final as‐built record drawings and calculations of the final quantity.
D. The topographic survey for the as -built information shall be performed by a Professional Land Surveyor licensed in the State of Califor nia. After the trench excavation, pipe installation and approval from the inspector, the Contractor’s licensed Land Surveyor shall perform a topographic/As -Built survey of all items described above in Submittals. Surveying will be of the actual pipe, conduit and/or finished facility. As-Built survey shall indicate the actual pipe material installed.
3.8 AS-BUILT GPS SURVEY
A. Contractor shall be responsible for the GPS “As ‐Built” Survey, following the completion of construction, for the location and depth of installed underground utility lines, coordinates of manholes, manhole rim elevations, manhole invert elevations, manhole depths, utility boxes, manhole covers and similar appurtenances. A CAD drawing and coordinates data sheet shall be submitted to the project manager for approval. This task must be performed by a registered professional land surveyor licensed in the state of California. Data shall be tied to California State Plan Coordinate System.
END OF SECTION 01 71 23
356
City of Pittsburg, California December 2022
CUTTING AND PATCHING 01 73 29 - 1
SECTION 01 73 29 – CUTTING AND PATCHING
PART 1 - GENERAL
1.1 SUMMARY
A. General: This section includes requirements for cutting and patching.
1.2 QUALITY ASSURANCE
A. Installers: Employ skilled and experienced installers to perform cutting and patching.
1.3 SUBMITTALS
A. Written Request: Submit written request in advance of cutting or altering elements affecting:
1. Structural integrity of element.
2. Integrity of weather-exposed or moisture-resistant elements.
3. Efficiency, maintenance, or safety of element.
4. Visual qualities of sight-exposed elements.
5. Work of Owner or separate contractor.
B. Request Requirements: Project name and location; description of all affected work; explanation of necessity for cutting, alteration or excavation; impact on the work of the Owner or any separate contractor, or on the structural or weatherproof integrity of the building; description of proposed work, including scope of cutting, patching, alteration, or excavation, products proposed to be used, trades who will complete the work, and ext ent of refinishing to be done; alternatives to cutting and patching; cost proposal, when applicable; written permission from any separate contractor whose work will be affected.
C. Product Substitutions: Should conditions of Work or schedule indicate change of products from original installation, submit request for substitution as specified in Section 01 25 00 - Substitution Procedures.
D. Field Observation: Submi t written notice to Project Manager designating date and time work will be uncovered.
PART 2 - PRODUCTS
NOT USED
357
City of Pittsburg, California December 2022
CUTTING AND PATCHING 01 73 29 - 2
PART 3 - EXECUTION
3.1 EXAMINATION
A. General: Inspect existing conditions; include elements subject to damage or movement during cutting and patching.
B. After Uncovering Work: Inspect conditions affecting the installation of products, or performance of Work.
C. Unsatisfactory Conditions: Report unsatisfactory or questionable conditions to the Project Manager in writing; do not proceed with work until Project Manager has provided further instructions.
3.2 PREPARATION
A. Temporary Support: Provide as necessary to assure structural value or integrity of affected portion of Work.
B. Protection:
1. Provide devices and methods to protect other portions of the Project from damage.
2. Provide protection from elements for that portion of the Project which may be exposed by cutting and patching, and maintain excavations free from water.
3.3 PERFORMANCE
A. Cutting and Patching: Execute cutting, fitting, and patching, including excavation and fill if required, to complete Work and to:
1. Fit the several parts together, to integrate with other Work.
2. Uncover Work to install or correct ill-timed Work.
3. Remove and replace defective and nonconforming Work.
4. Remove samples of installed Work for testing.
5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.
B. Methods: Execute Work by methods to avoid damage to other Work and to provide proper surfaces to receive patching and finishing. Cut masonry and concrete materials using masonry saw or core drill.
C. Restoration: Restore Work with new products according to requirements of Contract Documents. In the case of failure to protect existing or new work, Contractor shall be responsible for costs to repair damage and for restoring the work.
358
City of Pittsburg, California December 2022
CUTTING AND PATCHING 01 73 29 - 3
D. Penetrations: Fit Work tight to pipes, sleeves, ducts, conduits, and other penetrations through surfaces. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.
E. Refinishing: Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.
F. Hazardous Conditions: Identify hazardous substances or conditions exposed during the Work to Project Manager for decision or remedy.
END OF SECTION 01 73 29
359
City of Pittsburg, California December 2022
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 1 SECTION 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL
1.1 SUMMARY
A. Description: Provide Construction Waste Management including salvaging, recycling, and disposing of nonhazardous construction waste, as shown and specified per Contract Documents.
PART 2 - PRODUCTS
2.1 WASTE MANAGEMENT PLAN
A. General: Develop plan, consisting of waste identification and construction methods employed to reduce the amount of waste generated, including separate sections for demolition and construction waste, to re -use and recycle minimum 75% of construction waste materials generated by the Work. Indicate quantities by weight or volume; use same units of measure throughout waste management plan.
B. Quality Requirements: Refer to Section 01 42 00 - References for reference standards, applicable codes and definitions, and to the following:
1. American National Standards Institute (ANSI): ANSI 10.2 - Safety Code for Building Construction.
2. American Society for Testing and Materials (ASTM): Materials and testing standards as identified throughout this Section or within referenced manufacturers’ standard specifications.
3. California Building Code (CBC): California Green Building Standards Code (CALGreen), latest edition: Title 24, Part 11.
4. California Department of Resources Recycling and Recovery (CalRecycle):
a. General: Sustainable Building Guidelines.
b. Recycling and Recovery: Construction and Demolition Debris Recycling guidelines.
5. California Occupational Safety and Health Administration (C alOSHA):
Construction Safety Orders; 29 CFR, PART 1926 Safety and Health Regulations for Construction.
6. Construction & Demolition Recycling Association (CDRA): Standards and guidelines.
7. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.
360
City of Pittsburg, California December 2022
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 2 PART 3 - EXECUTION
3.1 PREPARATION
A. General: Review Waste Management Plan procedures and identify locations established for salvage, recycling, and disposal. Designate and label specific areas on the site for separating materials to be salvaged, recycled, reused, donated, and sold.
3.2 IMPLEMENTATION
A. City of Pittsburg Construction & Demolition (C&D) Recycling and Waste Management requires at least 65% job -site waste materials diverted from the landfill.
B. For newly constructed buildings, demolition projects and all locally permitted additions and alterations to non -residential buildings or structures, Contractor shall submit the C&D Debris Waste Management Plan (WMP) showing diverting from landfills at least 65% of the construction materials generated by the project.
C. Contractor may deliver all approved recycling materials such as wood, metal, plastics, concrete, roofing, cardboard, dirt, sheetrock, t ires, appliances, mattresses, box springs, propane tanks, and electronic waste to Contra Costa Waste Service also known as Recycling Center & Transfer Station (RCTS), located at 1300 Loveridge Road, Pittsburg, California. All materials shall be weighed at the RCTS. For any material code of “CD” (Construction & Demolition Material Processing), 100% diversion rate will be applied to receipts indicating the material code “CW” (Clean Wood), “CG” (Clean Green), or “CR” (Clean Roofing).
D. Recycled Materials: Separ ate recyclable waste from other waste materials, trash, and debris. Provide properly marked containers or bins for controlling recyclable waste until they are removed from Project site. Store materials away from construction area, off the ground and protect from the weather; do not store within drip line of remaining trees. Transport recyclable waste off Owner's property to recycling receiver or processor.
E. Disposal: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction. Except as otherwise specified, do not allow waste materials that are to be disposed of to accumulate on-site. Remove and tran sport debris in a manner that will prevent spillage on adjacent surfaces and areas. Burning and burying of materials is not allowed.
F. Contractor shall submit the following WMP and Water Assessment table forms. 361
City of Pittsburg, California December 2022
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 3
362
City of Pittsburg, California December 2022
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 4
END OF SECTION 01 74 19
363
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 1
SECTION 01 77 00 – CLOSEOUT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes contract closeout procedures including:
1. Removal of temporary construction facilities
2. Substantial completion
3. Final completion
4. Final cleaning
5. Miscellaneous Project Record Submittals
6. Release of claims
1.2 REMOVAL OF TEMPORARY CONSTRUCTION FACILITIES
A. Remove temporary materials, equipment, services, and construction prior to Substantial Completion Inspection.
B. Clean and repair damage caused by installation or use of temporary facilities.
C. Restore permanent facilities used during construction to specified condition.
1.3 SUBSTANTIAL COMPLETION
A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request.
1. In the Application for Payment that coincides with, or first follows, the date Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete.
2. Include supporting documentation for completion as indicated in these Contract Documents and a statement showing an accounting of changes to the Contract Sum.
3. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete.
B. Advise the Project Manager of pending insurance changeover requirements.
C. Submit warranty bonds, final certifications, and similar documents.
D. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
364
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 2
E. Submit record drawings in PDF or hard copies in addition to CAD files , maintenance manuals, final project photographs, damage or settlement surveys, property surveys, and similar final record information.
F. Deliver tools, spare parts, extra stock, and similar items.
G. Make final changeover of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of changeover in security provisions.
H. Complete startup testing of systems and instruction of the Owner's operation and maintenance personnel. Discontinue and remove temporary facilities from the site, along with mockups, construction tools, and similar elements.
I. Complete final cleanup requirements, including touchup painting.
J. Touch up and otherwise repair and restore marred, exposed finishes.
K. Inspection Procedures: On receipt of a request for inspection, the Project Manager will either proceed with inspection or advise the Contractor of unfilled requirements.
The Project Manager will prepare the Certificate of Substantial Completion following inspection or advise the Contractor of construction that must be completed or corrected before the certificate will be issued.
L. The Project Manager will repeat inspection when requested and assured that the Work is substantially complete.
M. Results of the completed inspection will form the basis of requirements for final acceptance.
1.4 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request.
B. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required.
C. Submit an updated final statement, accounting for final additional changes to the Contract Sum.
D. Submit a certified copy of the Project Manager’s final inspection list of items to be completed or corrected, endorsed and dated by the Project Manager. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance and shall be endorsed and dated by the Project Manager. 365
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 3
E. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion or when the Owner took possession of and assumed responsibility for corresponding elements of the Work.
F. Submit consent of surety to final payment.
G. Submit a final liquidated damages settlement statement.
H. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
I. Re-inspection Procedure: The Project Manager will re-inspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to the Project Manager.
1. Upon completion of re -inspection, the Project Manager will prepare a certificate of final acceptance. If the Work is incomplete, the Project Manager will advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance.
2. If necessary, re-inspection will be repeated.
J. Maintenance Manuals: Organize operation and maintenance data into suitable sets of manageable size. Bind properly indexed data in individual, heavy-duty, 2- inch 3-ring, vinyl -covered binders, with pocket folders for folded sheet information. Provide two (2) paper copies and a PDF. Mark appropriate identification on front and spine of each binder. Include the following types of information:
1. Emergency instructions.
2. Spare parts list.
3. Copies of warranties.
4. Wiring diagrams.
5. Recommended "turn-around" cycles.
6. Inspection procedures.
7. Shop Drawings and Product Data.
8. Fixture lamping schedule.
1.5 FINAL CLEANING
A. Execute final cleaning prior to final inspection.
B. Clean interior and exterior surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Clean equipment and fixtures to a sanitary condition, clean or replace filters of mechanical equipment operated during construction, clean ducts, blowers and coils of units operated without filters during construction. 366
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 4
D. Employ skilled workers for final cleaning.
E. Clean Site; mechanically sweep paved areas.
F. Remove waste and surplus materials, rubbish, and construction facilities from Site.
1.6 MISCELLANEOUS PROJECT RECORD SUBMITTALS
A. Refer to Technical Specifications or other Specification Sections for miscellaneous record keeping requirements and submittals in connection with various construction activities. Immediately prior to Substantial Completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for use and reference. Submit to the Project Manager for City's records.
1.7 RELEASE OF CLAIMS
A. Contract will not be closed out and final payment will not be made, subject to provisions of Section 7100 Public Contract Code until all pertinent aspects of Division 00 - General Conditions regarding undisputed/settled amounts are completed per requirements elsewhere in the Technical Specifications and/or Specifications and executed by Contractor and City.
B. Contractor shall submit the following Agreement and Release of Any and All Claims Form.
367
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 5
368
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 6
369
City of Pittsburg, California December 2022
CLOSEOUT REQUIREMENTS 01 77 00 - 7
END OF SECTION 01 77 00
370
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 1
SECTION 01 78 00 – CLOSEOUT SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes contract closeout submittals including:
1. Project record documents
2. Project guarantee
3. Warranties
1.2 PROJECT RECORD DOCUMENTS
A. Project Record Documents required include:
1. Marked-up copies of Contract Drawings
2. Marked-up copies of Shop Drawings
3. Project Record Drawings
4. Marked-up copies of Technical Specifications, Specifications, Addenda and Change Orders
5. Marked-up Project Data submittals
6. Record Samples
7. Field records for variable and concealed conditions
8. Record information on Work that is recorded only schematically
9. GPS As-built Survey
10. Warranty Bonds
B. Specific Project Record Documents requirements that expand requirements of this Section are included in the indi vidual Sections of Divisions 2 through 48 (when provided).
C. General Project closeout requirements are included in Section 01 77 00 - Closeout Requirements.
D. Maintenance of Documents and Samples:
1. Store Project Record Documents and samples in the field office apart from Contract Documents used for construction.
2. Do not permit Project Record Documents to be used for construction purposes.
3. Maintain Project Record Documents in good order, and in a clean, dry, legible condition.
4. Make documents and samples available at all times for inspection by Architect and Project Manager.
371
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 2
E. City will provide one set of reproducibles and one set of the construction drawing prints a nd one project manual for the Contractor's use and copying during construction.
F. Mark-up Procedure: During the construction period, maintain a set of Contract Drawings and Shop Drawings for Project Record Document purposes.
1. Mark these Drawings to indicate the actual installation where the installation varies appreciably from the installation shown originally. Give particular attention to information on concealed elements which would be difficult to identify or measure and record later. Items required to be marked include but are not limited to:
a. Dimensional changes to the Drawings
b. Revisions to details shown on the Drawings
c. Depths of foundations below the first floor
d. Locations and depths of underground utilities
e. Revisions to routing of piping and conduits
f. Revisions to electrical circuitry
g. Actual equipment locations
h. Duct size and routing
i. Locations of concealed internal utilities
j. Changes made by Change Order
k. Details not on original Contract Drawings
2. Mark completely and accurately Project Record Drawing prints of Contract Drawings or Shop Drawings, whichever is the most capable of showing actual physical conditions. Where Shop Drawings are marked, show cross - reference on Contract Drawings location.
3. Mark Project Record Drawing sets with red ink; use other colors to distinguish between changes for different categories of the Work at the same location.
4. Mark important additional information which was either shown schematically or omitted from original Drawings.
5. Note construction change directive numbers; alter nate numbers; Change Order numbers and similar identification.
6. Responsibility for Mark -up: Where feasible, the individual or entity who obtained Project Record Drawing data, whether the individual or entity is the installer, subcontractor, or similar entity, is required to prepare the mark-up on Project Record Drawings.
a. Accurately record information in an understandable and legible drawing technique.
b. Record data as soon as possible after it has been obtained. In the case of concealed installations, record and check the mark-up prior to concealment.
G. Preparation of Transparencies: Prior to inspection for Certification of Substantial Completion, review completed marked -up Project Record Drawings with the Project Manager. When authorized, prepare a full set of correct reproductables of Contract Drawings and Shop Drawings.
372
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 3
1. Incorporate changes and additional information previously marked on print sets. Erase, redraw, and add details and notations where applicable. Identify and date each Drawing; include the print ed designation "PROJECT RECORD DRAWINGS" in a prominent location on each Drawing.
2. Refer instances of uncertainty to the Project Manager for resolution.
3. Review of Reproducible: Before copying and distributing, submit corrected reproducibles and the original marked-up prints to the Project Manager for review. When acceptable, the Project Manager will initial and date each transparency, indicating acceptance of general scope of changes and additional information recorded, and of the quality of drafting. a. Reproducibles and the original marked-up prints will be returned to the Contractor for organizing into sets, printing, binding, and final submittal.
4. Copies and Distribution: After completing the preparation of reproducible Project Record Drawings, print one hard copy and a PDF of each Drawing, whether or not changes and additional information were recorded. Organize the copies into manageable sets. Bind each set with durable paper cover sheets, with appropriate identification, including titles, dates and other information on cover sheets.
a. Organize and bind original marked -up set of prints that were maintained during the construction period in the same manner. b. Organize Project Record Drawings reproducibles into sets matching the print sets. Place these sets in du rable tube -type drawing containers with end caps.
H. Distribution of Marked-Up Drawings and Transparencies: Submit the marked-up Project Record Drawings sets, reproducibles, and one copy to the Project Manager for City's records.
I. Project Record Technical Specifications and Specifications:
1. During the construction period, maintain one copy of the Project Manual, including addenda and modifications issued, for Project Record Document purposes.
2. Mark the Project Record Manual to indicate the actual installation where the installation varies substantially from that indicated in Specifications and Modifications issued. Note related Project Record Drawing information, where applicable. Give particular attention to substitutions, selection of product options, and infor mation on concealed installation that would be difficult to identify or measure and record later.
a. In each Technical Specifications and Specification Section where products, materials or units of equipment are specified or scheduled, mark the copy with the proprietary name and model number of the product furnished.
b. Record the name of the manufacturer, supplier and installer, and other information necessary to provide a record of selections made and to document coordination with Project Record Product Data su bmittals and maintenance manuals.
373
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 4
c. Note related Project Record Product Data, where applicable, for each principal product specified, indicate whether Project Record Product Data has been submitted in maintenance manual instead of submitted as Project Record Product Data.
3. Upon completion of mark-up, submit Project Record Manual to the Project Manager for City's records.
J. Project Record Product Data:
1. During the construction period, maintain one copy of each Project Record Product Data submittal for Project Record Document purposes. a. Mark Project Record Product Data to indicate the actual product installation where the installation varies substantially from that indicated in Project Record Product Data submitted. Include significant changes in the prod uct delivered to the site, and changes in manufacturer's instructions and recommendations for installation. b. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. c. Note related Change Orders and mark -ups of Project Record Drawings, where applicable.
d. Upon completion of mark-up, submit a complete set of Project Record Product Data to the Project Manager for City's records. e. Where Project Record Product Data is required as part of maintenance manuals, submit marked -up Project Record Product Data as an insert in the manual, instead of submittal as Project Record Product Data.
K. Material, Equipment and Finish Data:
1. Provide data for primary materials, equipment and finishes as required under each Technical Specifications/Specification section.
2. Submit one set prior to final inspection, bound in 8-1/2 inches by 11 inches three-ring binders with durable plastic covers and a PDF; provide typewritten table of contents for each volume.
3. Arrange by Technical Specifications/Specification division and give names, addresses, and telephone numbers of subcontractors and suppliers. List:
a. Trade names.
b. Model or type numbers.
c. Assembly diagrams.
d. Operating instructions.
e. Cleaning instructions.
f. Maintenance instructions.
g. Recommended spare parts.
h. Product data.
L. Miscellaneous Project Record Submittals:
1. Refer to other Technical Specifications /Specification Sections for miscellaneous record keeping requirements and submittals in connection with various construction act ivities. Immediately prior to Substantial 374
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 5
Completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for use and reference. Submit to the Project Manager for City's records. Field records documenting elevations and locations of completed improvements shall require Contractor-retained State of California Licensed surveyor’s certification stamp. Categories of requirements resulting in miscellaneous records include, but are not limited to the following:
a. Field records on excavations and foundations
b. Field records on underground construction and similar work c. Survey showing locations and elevations of underground lines d. Invert elevations of drainage piping
e. Surveys establishing building lines and levels
f. Authorized measurements utilizing unit prices or allowances g. Records of plant treatment
h. Ambient and substrate condition tests
i. Certifications received in lieu of labels on bulk products j. Batch mixing and bulk delivery records
k. Testing and qualification of tradespersons
l. Documented qualification of installation firms
m. Load and performance testing
n. Inspections and certifications by governing authorities o. Leakage and water-penetration tests
p. Fire resistance and flame spread test results
q. Final inspection and correction procedures
M. GPS As-built Survey: Refer to Section 01 71 23 - Construction Surveying for As- Built GPS Survey.
N. Periodic Review:
1. Make additions to the Project Record Documents as they occur.
2. Make the Project Record Documents available to the Project Manager for periodic review. The Project Manager’s review of the current status of Project Record Documents is a requisite to approval of requests for progress payment.
3. Prior to submitting each request for progress payment, secure the Project manager’s approval of the current status of the Project Record Documents.
4. Prior to submitting request for final Payment, submit the final Project Record Documents to the Project Manager for approval.
O. Submittal: At the completion of Project, deliver record documents to Project Manager.
1.3 PROJECT GUARANTEE
A. Requirements for Cont ractor's guarantee of completed Work are included in Division 00 - General Conditions. Contractor shall guarantee Work done under Contract against failures, leaks or breaks or other unsatisfactory conditions due to 375
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 6
defective equipment, materials or workmanship, and perform repair work or replacement required, at Contractor's sole expense, for period of one year, unless otherwise subject to any special warranty periods of longer duration, from date of Final Acceptance.
B. Neither recordation of final acceptance nor final certificate for payment nor provision of the Contract nor partial or entire use or occupancy of premises by City shall constitute acceptance of Work not done in accordance with Contract Documents nor relieve Contractor of liability in respect to express warranties or responsibility for faulty materials or workmanship.
C. City ma y make repairs to defective Work as set forth in paragraph 10.C.3 of Division 00 - General Conditions, if, within five (5) working days after mailing of written notice of defective work to Contractor or authorized agent, Contractor shall neglect to make or undertake repair with due diligence; provided, however, that in case of leak or emergency where, in opinion of City, delay would cause hazard to health or serious loss or damage, repairs may be made without notice being sent to Contractor, and Contractor shall pay cost thereof.
D. If, after installation, operation or use of materials or equipment to be furnished under Contract proves to be unsatisfactory to Project Manager, City shall have right to operate and use materials or equipment until it can, without damage to City, be taken out of service for correction or rep lacement. Period of use of defective materials or equipment pending correction or replacement shall in no way decrease guarantee period required for acceptable corrected or replaced items of materials or equipment.
E. Nothing in this Section shall be construed to limit, relieve or release Contractor's, subcontractors' and equipment suppliers' liability to City for damages sustained as result of latent defects in equipment caused by negligence of suppliers' agents, employees or subcontractors. Stated in anoth er manner, warranty contained in the Contract Documents shall not amount to, nor shall it be deemed to be, waiver by City of any rights or remedies (or time limits in which to enforce such rights or remedies) it may have for defective workmanship or defective materials under laws of this State pertaining to acts of negligence.
1.4 WARRANTIES
A. Execute Contractor's submittals and assemble warranty documents executed or supplied by subcontractors, suppliers, and manufacturers.
1. Provide table of contents and assemble in 8-1/2 inches by 11 inches three- ring binder with durable plastic cover.
2. Assemble in Technical Specifications/Specification Section order.
3. Submit material prior to final application for payment.
4. For equipment put into use with City's permission during c onstruction, submit within ten (10) working days after first operation. 376
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 7
5. For items of Work delayed materially beyond Date of Substantial Completion, provide updated submittal within ten (10) working days after acceptance, listing date of acceptance as start of warranty period.
6. Warranties are intended to protect City against failure of work and against deficient, defective and faulty materials and workmanship, regardless of sources.
7. Limitations: Warranties are not intended to cover failures which result from the following:
a. Unusual or abnormal phenomena of the elements
b. Vandalism after substantial completion
c. Insurrection or acts of aggression including war.
B. Related Damages and Losses: Remove and replace Work which is damaged as result of defective Work, or which must be removed and replaced to provide access for correction of warranted Work.
C. Warranty Reinstatement: After correction of warranted Work, reinstate warranty for corrected Work to date of original warranty expiration or to a date not less than ninety (90) days after corrected Work was done, whichever is later.
D. Replacement Cost: Replace or restore failing warranted items without regard to anticipated useful service lives.
E. Warranty Forms: Submit drafts to Project Manager for approval prior to execution.
Forms shall not detract from or confuse requirements or interpretations of Contract Documents.
F. Warranty shall be countersigned by manufacturers.
G. Where specified, warranty shall be countersigned by subcontractors and installers.
H. Rejection of Warranties: City reserves right to reject unsolicited and coincidental product warranties which detract from or confuse requirements or interpretations of Contract Documents.
I. Term of Warranties: For materials, equipment, systems and workmanship warranty period shall be one-year minimum from date of final completion of entire Work except where:
1. Detailed specifications for certain materials, equipment or systems require longer warranty periods.
2. Materials, equipment or systems are put into beneficial use of City prior to Final Completion as agreed to in writing by Project Manager.
J. Warranty of Title: No material, supplies, or equipment for Work under Contract shall be purchased subject to any chattel mortgage, security agreement, or under a conditional sale or oth er agreement by which an interest therein or any part thereof is retained by seller or supplier. Contractor warrants good title to all material, supplies, and equipment installed or incorporated in Work and agrees 377
City of Pittsburg, California December 2022
CLOSEOUT SUBMITTALS 01 78 00 - 8
upon completion of all work to deliver premises, together with improvements and appurtenances constructed or placed thereon by Contractor, to City free from any claim, liens, security interest, or charges, and further agrees that neither Contractor nor any person, firm, or corporation furnishing any materials or labor for any Work covered by Contract shall have right to lien upon premises or improvement or appurtenances thereon. Nothing contained in this Paragraph, however, shall defeat or impair right of persons furnishing materials or labor under bond given by Contractor for their protection or any rights under law permitting persons to look to funds due Contractor in hands of City.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 78 00
378
City of Pittsburg, California December 2022
SURVEY MONUMENTS 02 21 13 - 1
SECTION 02 21 13 – SURVEY MONUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes furnish and install Cast -in-place Portland Cement Survey Monuments and all appurtenant work.
B. Related Requirements:
1. Section 03 30 00 – Utility Cast-in-place Concrete
2. Section 31 23 16 – Utility Trenching
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. Section 01 29 00 - Payment Procedures : Contract Sum/Price modification procedures.
B. Survey Monuments
1. Basis of Measurement: Measured on a per unit basis.
2. Basis of Payment: Includes concrete, placement accessories, consolidating, leveling, troweling, and curing.
1.3 REFERENCE STANDARDS
A. ASTM International:
1. ASTM A48 – Specifications for Gray Iron Castings
B. Caltrans Standard Specifications
1. Section 55 – Steel Structures
2. Section 78-2 – Survey Monuments
1.4 COORDINATION
A. Coordinate placement of concrete formwork and placement of form accessories.
1.5 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. 379
City of Pittsburg, California December 2022
SURVEY MONUMENTS 02 21 13 - 2
B. Product Data: Submit data on bronze survey markers, frame and covers.
1.6 CLOSEOUT SUBMITTALS
A. Section 01 78 00 - Closeout Submittals: Requirements for submittals.
PART 2 - PRODUCTS
2.1 FRAME AND COVER
A. Monument frame and cover shall be gray iron castings conforming to ASTM A48, Class 30 B, designed for a 15,000 lb. wheel load . Monument cover shall be marked “Monument”. Cover shall be non-rocking and will fit in its frame.
B. Monument Frame and Cover shall be Chrisp Company Casting Part No.9279 or 9277M, Phoenix Iron Works 2501or approved equal.
2.2 BRONZE SURVEY MARKER
A. Bronze survey marker shall be 2-1/2 inch domes disk with stem and appropriate survey information as specified on the Drawings.
B. Brass Survey markers are not acceptable unless they are lead-free.
2.3 FORMING TUBE
A. Tubes for forming Portland cement concrete collar and monument shall be non- metallic type of the size and dimensions shown on the Drawings.
2.4 PORTLAND CEMENT CONCRETE
A. Portland Cement Concrete for collars and footings shall conform with Section 03 30 00 – Utility Cast-in Place Concrete.
2.5 HOT MIX ASPHALT
A. Hot Mix Asphalt concrete around monuments shall be in conformance with Section 32 12 16 – Asphalt Paving.
380
City of Pittsburg, California December 2022
SURVEY MONUMENTS 02 21 13 - 3
PART 3 - EXECUTION
3.1 GENERAL
A. Section 01 70 00 - Execution: Requirements for installation examination.
B. Monuments shall not be installed until the asphalt paving has been completed.
C. Concrete, form tube, bronze survey marker, frame and cover, and asphalt paving shall be installed as shown on the Drawings.
D. Cast the monuments in place in neat holes using forming tubes.
E. Thoroughly consolidate the concrete and cure it by the water method per Section 90-1.03B (2) Water Method of State Standard Specifications.
F. Locate the monument such t hat the point being referenced falls within 1/2 -inch from the center of the disk when the disk is placed in the center of the monument.
G. Place the survey marker disk before the concrete reaches its initial set. Firmly embed the disk in the concrete.
H. If base and surfacing are not shown around a monument, fill any space around it with earth. Water and tamp the earth into place.
I. Surplus excavated material shall become the property of the Contractor and the Contractor shall be responsible for disposal of excess excavated material.
J. The Concrete collar shall be circular – 8 inches in diameter around the frame and cover and shall be covered with a minimum of two (2) inches of asphalt concrete paving to level with the adjacent surfacing.
3.2 EXISTING MONUMENT PROTECTION
A. All existing s urvey monuments and benchmarks shall be protected, unless otherwise shown on the Drawings. Upon discovery of a survey monument not identified and located by the City, immediately:
1. Stop work near the monument
2. Notify the Project Manager
B. Do not resume work near the monument until authorized by the Project Manager.
C. Monuments placed by Surveyors must be preserved, in accordance with State Business & Professions Code section 8771.
D. The Contractor shall exercise caution when working around monuments so as not to disturb them. During milling, grinding, excavation or other operations, the 381
City of Pittsburg, California December 2022
SURVEY MONUMENTS 02 21 13 - 4
Contractor shall work around survey monuments unless specifically otherwise indicated on the Plans. If a monument is disturbed or damaged during adjusting, milling or other operations, the Contractor shall be responsible for all costs associated with the reestablishment of the monument including but not limited to surveying performed by a Licensed Surveyor and filing documents with County and constructing the new monument.
E. The existing monument consisting of a concrete core and brass tack, nail or other marking device located inside of a survey monument cover with frame, shall not be disturbed until the contractor’s Licensed Land Surveyor has established of reference points to preserve the location of the monument, in accordance with State Business & Professions Code section 8771.
F. Any survey monument disturbed shall be replaced in accordance with the State Business & Professions Code section 8771 and Contra C osta County Standard Drawings CA40. The Contractor shall be responsible for all costs associated with the reestablishment of the monument including but not limited to surveying performed by a Licensed Surveyor and filing documents with County and constructing the new monument.
G. Contractor shall prepare corner record, submit corner record to the County Surveyors and submit acceptance of monument to the Project Manager.
3.3 CONCRETE PROTECTION
A. The Contractor shall protect all concrete against injury until final acceptance by the City.
END OF SECTION 02 21 13
382
City of Pittsburg, California December 2022
EXPLORATORY EXCAVATIONS 02 32 19 - 1
SECTION 02 32 19 – EXPLORATORY EXCAVATIONS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Exploratory excavation by potholing at all utility conflicts including the locations identified on the plans to determine the location, depth, width, pipe diameter or concrete ductbank thickness, type and condition of existing underground utilities.
1.2 REFERENCES
A. Cal/OSHA – California Division of Occupation Safety and Health B. Caltrans Standard Specifications
1. Section 15 – Existing Facilities
2. Section 19 - Earthwork
C. Underground Services Alert (USA)
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Submittal Data:
1. Contractor shall contact USA to verify the actual location of the pothole prior to beginning pothole. Submit l etters or correspondences of advance notifications to the utility companies as listed below in Part 3.
2. Contractor shall apply and pay for all permits connected with the Work.
3. Contractor shall submit temporary traffic control plan for City’s approval prior to beginning any exploratory excavation.
4. Contractor shall submit potholing methodology.
5. Contractor shall submit photographs in jpeg or PDF format of the pothole locations with the pothole number identified on the photograph as designated below.
6. Pothole data shall also include the thickness of asphalt concrete/Portland cement concrete pavement and aggregate base.
383
City of Pittsburg, California December 2022
EXPLORATORY EXCAVATIONS 02 32 19 - 2
7. At a minimum, pothole data shall be submitted in a tabular format. See sample potholing submittal format below:
# Utility Pipe
diameter
(inch)
Concrete
ductbank
Width x
Depth
Depth to
top of
pipe or
concrete
ductbank
Material AC/AB
Depth
(inch)
Northing or
Distance
from fixed
object A
Easting
or
Distance
from
fixed
object B
PH#1 Water 12 - 3’-6” PVC 4/8 15 ft from FH 12 ft from SSMH
PH#2 Telecom
Duct
- 2 ft x 3 ft 4’-2” Concrete
Ductbank
6/10 22 ft from
SDMH
40 ft from
WV
1.4 MEASUREMENT & PAYMENT
A. Measurement: For measurement of Exploratory excavations (potholing) performed by the Contractor, an exploratory excavation (potholing) will be counted as complete when the intended pipe is exposed, measured, the data has been submitted in the tabular format as specified above, reviewed and approved by the Project Manager, the pothole is backfilled and the surface restoration including any striping is restored. Empty potholes will not be counted as complete.
B. Payment: The Contract unit price paid for Exploratory Excavations (potholing) shall include full compensation for furnishing all labor, tools, equipment’s, incidentals for exploratory excavations by potholing to verify the location, depth, diameter, material and thickness of the existing underground utility, including contacting USA, utility companies, permits, traffic control, compliance with Cal/OSHA, saw cut, excavation, exposing the existing underground utility, measuring depths, diameter and distances as required, backfill, surface restoration, striping restoration, submitting the pothole data in a tabular format for review and approval by the Project Ma nager, as shown on the Drawings, as specified in the City Standard Specifications and as directed by the Project Manager.
C. Full compensation pay clause for furnishing all labor, tools, equipment’s, incidentals for exploratory excavations by potholing for an y utility conflicts not identified on the Drawings including exploratory excavations by potholing to verify the location, depth, diameter, material and thickness of the existing underground utility, including contacting USA, utility companies, permits, tra ffic control, compliance with Cal/OSHA, saw cut, excavation, exposing the existing underground utility, measuring depths, diameter and distances as required, backfill, surface restoration, striping restoration, shall be considered as incidental 384
City of Pittsburg, California December 2022
EXPLORATORY EXCAVATIONS 02 32 19 - 3
to the item most closely related to and no separate compensation will be allowed therefor.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 POTHOLING
A. Contractor shall be responsible for notifying the utility companies for any inspections prior to potholing.
B. Contractor shall be responsible for locating utilities and providing utility markings of the underground utilities prior to potholing.
C. Where gas distribution or gas transmission lines are present, Contractor shall have a PG&E representative present on site during potholing.
D. Contractor shall be responsible for contacting and notifying the utility companies three (3) working days prior to beginning any potholing. Contractor shall be responsible for coordinating any inspections with the respective utility company.
E. Two (2) weeks prior to any construction, potholing shall be performed at all utility conflicts and at all pothole locations shown on the Drawings in order to determine the location, depth, width, pipe diameter, thickness type and condition of existing underground utilities and shall conform to the Technical Specifications.
F. Potholing will be a separate move -in from the underground utility trenching and will be separate from the trenching operations; Exploratory excavations shall be performed with potholing equipment. Potholing as part of the trenching operations is not an acceptable method. Potholing will be shown as a separate line item in the project construction schedule.
G. The methods such as vacuum potholing and other excavation methods used by the Contractor for potholing shall be approved by the Project Manager in advance of commencing any work, along with the required traffic controls.
H. After the completion of the USA markings, but before the actual potholing, Contractor will host a field meeting with the City t o review the locations of the potholes which will be painted in the field. During the meeting, the Project Manager may relocate the potholes based on the field conditions. The Contractor’s price bid will include allowance for moving the locations of the 385
City of Pittsburg, California December 2022
EXPLORATORY EXCAVATIONS 02 32 19 - 4
potholes during the pre -pothole site meeting. No guarantee is made as to the exact locations of the existing utilities.
I. The Contractor shall provide the Project Manager in a tabular format the location, type, depth, diameter and condition of each utility found prior to commencing construction. The potholing table shall include a neatly redlined plan. No trenching work shall be performed until the Project Manager reviews the potholing information submitted by the Contractor.
J. Contractor shall provide the p otholing information to the Project Manager and allow one (1) week for any necessary revisions to the design plan and profiles prior to sawcutting and trenching of the proposed pipe alignment or as shown on the Drawings.
K. The Contractor shall take care not to damage any existing facilities during potholing. Existing facilities damaged by the Contractor’s operations shall be repaired or replaced to the satisfaction of the City Engineer and Utility companies, all at the Contractor’s expense.
L. Backfill with Co ntrolled Low Strength Materials (CLSM) and complete surface restoration to match existing conditions in kind.
M. When pothole locations are located in concrete pavement, Contractor shall remove and replace concrete pavement and base from the nearest joint to joint to match the existing concrete pavement thickness.
END OF SECTION 02 32 19
386
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 1
SECTION 02 41 00 - DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes but not limited to:
1. Demolition & Permits
2. Removal and Disposal
3. Recycling & Salvaging
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. Demolition:
1. Basis of Measurement: Not a measured item, unless specified otherwise on the Drawings.
2. Basis of Payment: The Contract lump sum price paid for “Demolition” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all work involved in Demolition, including obtaining demolition permits, permit fees, sawcut, remove asphalt and concrete paving and base to design subgrade, remove foundation and base; terminating and removing utilities to be demolished and other items of work as specified in the plans, Standa rd Specification and the Technical Specifications, and as directed by the Project Manager.
1.3 REFERENCES & RELATED WORK SPECIFIED ELSWHERE
A. Bay Area Air Quality Management District (BAAQMD) – http://www.baaqmd.gov/
1. Regulation 11 (Hazardous Pollutants) and Rule 2 (Asbestos Demolition, Renovation, and Manufacturing).
B. CALGreen Construction Waste Management Requirements
1. https://www.calrecycle.ca.gov/lgcentral/library/canddmodel/instruction/new structures
C. California Occupational Safety and Health (Cal/OSHA)
1. General Requirements
D. Commercial
1. USA Underground Service Alert
E. Division 1
1. General Requirements
387
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 2
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. The Contractor shall submit to the City a haul route for approval, prior to commencing any work. Truck traffic movement is limited between the hours of 9am to 3pm, unless approved by the Project Manager.
C. Before disposing of any demolished material prior to any work
1. Submit a written agreement from the property owner
a. For the use of the property
b. absolving the City from responsibility in connection with the property.
2. Obtain authorization to start
D. Before Contract acceptance, submit a document signed by the owner of the material disposal site stating that the Contractor has complied with the Contractor-Owner agreement.
E. Demolition Schedule: The Contractor shall submit a complet e coordination schedule for demolition work including shut-off and continuation of utility services prior to start of the work. The schedule shall indicate proposed methods and operations of facility demolition, and provide a detailed sequence of demoliti on and removal work to ensure uninterrupted operation of occupied areas.
F. All affected private properties will receive door hanger notices two (2) weeks prior to any utility shutoffs or frontage demolition and improvements.
1.5 JOB SITE CONDITIONS
A. The Contract or shall visit the site and inspect the existing facilities. The City assumes no responsibility for actual condition of facilities to be demolished.
B. Contractor shall use all means necessary to prevent the spread of dust during performance of the work. Thoroughly moisten all surfaces as required to prevent the generation of dust. No washing of streets is permitted.
C. All liquid, and slurry generated during pavement sawcutting shall be collected and removed from the site. These liquids shall not be washed i nto the area storm drainage system.
D. Contractor shall remove hazardous materials as described per the Project Asbestos and Lead Inspection Report.
E. The Contractor prior to the commencement of the demolition or renovation, thoroughly inspect the affected facility or part of the facility where the demolition or renovation operation will occur for the presence of asbestos, including Category I and Category II nonfriable Asbestos Containing Materials (ACM). 388
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 3
F. The Contractor must also provide the Environmental P rotection Agency (EPA) with a 10 working day advance notice for any disturbance of Regulated Asbestos- Containing Material (RACM) greater than 160 square feet or 260 lineal feet, and as specified in Code of Federal Regulations (CFR) Title 40, Chapter I, Subchapter C, Part 61, Subpart M, Section 61.145.
1.6 DELIVERY, STORAGE AND HANDLING
A. Section 01 60 00 - Product Requirements : Requirements for transporting, handling, storing, and protecting products.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 INSTALLATION
A. Notify anyone to be affected by demolition and construction activities including but not limited to: all schools, residences, businesses, garbage collection (Pittsburg Disposal Serv ice-a Garaventa company), utility companies (PG&E - Gas Distribution, PG&E Gas Transmission, PG&E -Electric, AT&T, Comcast, Verizon, Chevron Pipeline Co, Shell Pipeline Co, Kinder Morgan, Calpine etc.), Delta Diablo (Sewer District), BART, County Connection (bus transit agency), the Owner, etc. at least ten (10) working days prior to commencing the work of this section.
B. Site Inspection:
1. Prior to all work of this section, carefully inspect the site and all objects des- ignated to be removed and to be preserved.
2. Locate all existing active utility lines traversing the site and determine the re- quirements for their removal and/or protection.
C. Clarification:
1. The Drawings do not purport to show all objects existing on the site.
2. Before commencing the work of this section, verify with the Owner all objects to be removed and all objects to be preserved
D. Scheduling:
1. Schedule all work in a careful manner with all necessary consideration for neighbors, operation of the existing facilities, and the public.
2. Avoid interference with the use of, and passage to and from, residences and adjacent facilities.
389
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 4
E. Protection of Utilities: Preserve in operating condition all active utilities traversing the site and designated to remain.
3.2 WATER POLLUTION CONTROL
A. Water sprinkling, temporary enclosures, chutes and other suitable methods shall be used to limit dust and dirt rising and scattering in the air. The Contractor shall comply with all government regulations pertaining to environmental protection.
B. The Contractor shall use equipme nt that will generate the least amount of dust.
The Contractor shall provide dust control at all times including Saturdays, Sundays, and holidays unless directed otherwise by the Project Manager.
C. Whenever the Contractor, in the opinion of the Project Manag er, is negligent in controlling dust, the Project Manager may direct attention to the existence of a dust hazard and instruct the Contractor to immediately alleviate the dust hazard.
The Contractor shall be responsible for any damage cause by dust generated as a result of the Contractor’s operations.
D. The Contractor shall have a commercial standard street vacuum/sweeper operational and in operation during each working day. The street vacuum/sweeper shall be able to pick up sand, gravel, dust, and debris, and other things, shall minimize dust generation, and shall also be available during the day and shall sweep as outlined below and as directed by the Project Manager.
E. If the Contractor is performing work that generates dust and debris then during the day (including weekends and holidays) the sweeper shall sweep the project area (full length, width, and all lanes) twice a day sometime between 9:00a.m. and 11:00a.m. and also between 2:00p.m. and 4:00p.m. Hardscape surfaces (including pavers, sidewalks, and areas inaccessible by a mechanical sweeper) shall have dirt, dust, and debris removed by hand sweeping. If the Contractor fails to fulfill the responsibilities of this section, the City will perform or contract with others to perform the work and all costs incurred to the City shall be withheld from future payments to the Contractor.
F. The Contractor shall clean the sidewalk and gutter as many times as needed to make sure the sidewalk and gutter are out of dirt, debris and small rocks at all times. The Con tractor shall be prepared to sweep surfaces immediately at the request of the Project Manager, should the Project Manager deem it necessary for public safety and to avoid damage to properties. If streets are not satisfactorily cleaned within 12 hours from verbal or written notice by City personnel, the City will hire an independent sweeping company and deduct the cost for such work from payments due to the Contractor.
G. Water shall not be used in a manner that creates hazardous or objectionable conditions such as ice, flooding, or pollution.
390
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 5
H. The site shall be kept neat and orderly during the demolition to the maximum extent practical.
I. Public right-of-way and private property shall be kept free of debris at all times.
J. Stockpiles of demolished items or materials shall be removed from the site on a daily basis or stored in waste containers which shall be emptied on a weekly basis or as conditions require in order to manage the accumulation of waste.
K. Accumulations of flammable materials shall not be permitted.
3.3 PROTECTION
A. Safe passage of persons around area of demolition shall be provided in accordance with all safety and regulatory requirements. Operations shall be conducted to prevent damage to adjacent buildings, structures, other facilities, people and prope rty. Safe passage provided by Contractor will be ADA complaint.
B. Interior and exterior shoring, bracing, or supports shall be provided to prevent movement, settlement or collapse of structures to be demolished and to adjacent facilities to remain.
C. Existing landscaping materials, structures, and appurtenances which are not to be demolished shall be protected and maintained as necessary.
D. The Contractor shall protect and maintain conduits, drains, sewers, pipes and wires that are not to be demolished.
E. Use all means necessary to protect existing objects designated to remain or to be preserved must remain operational during installation of the replacement pipeline. In the event of damage, immediately notify the Owner and make all repairs and replacements necessary for approval by the Owner at no additional cost to the Owner.
3.4 SURFACE DEMOLITION
A. All asphalt concrete and all Portland cement concrete curbs, gutters, sidewalks, access ramps and driveways shall be saw -cut at the nearest scoreline or deep joint and removed entirely to the saw-cut limits.
B. Where adjacent pavement or concrete is broken or damaged sufficiently to prohibit a sound replacement the entire damaged section shall be removed to the limits determined by the Project Manager.
391
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 6
C. Asphalt concrete, sidewalk, concrete curb, and gutter materials to be demolished shall be broken up and removed from the site by the Contractor at no additional cost to the City.
D. Where shown on the Drawings, the Contractor shall remove required pavement section including base material. Subsoil removal is also included where required to achieve design subgrade.
3.5 DEMOLITION BELOW THE SURFACE
A. Existing structures, pavement slabs and structural sections to be abandoned shall be demolished to an elevation three feet be low finished grade. Their bottoms (if any remain) shall be broken thoroughly to prevent entrapment of water and all voids backfilled with suitable backfill
B. Demolition areas and voids resulting from demolition of structures below the surface shall be completely filled.
C. All fill, compaction, and holes created by demolition work shall be backfilled with imported clean fill. Lay fill down in layers not exceeding 6” thickness and compact per the earthwork specifications . Grade the site to drain to the nearest storm drainage system without any low points.
D. All fill and compaction surfaces shall be graded to meet adjacent contours and to provide flow to surface drainage structures, or as shown on the Drawings.
E. Pipes to be demolished that require no future connection shall be removed to the extent required, sealed and capped. Pipe sections shall be removed either by sawcutting, removing a complete pipe section to an existing joint, or other adequate means which results in a clean joint.
F. The Contractor shall demolish or dismantle and remove all items that are noted for demolition and removal in the Contract Documents and that will interfere with the planned construction, or as otherwise directed by the Project Manager.
G. The Contractor shall demolish or dismantle and remove all abandoned conduits or structures that are encountered during the prosecution of the work and which interfere with the construction of the work upon the approval of the Project Manager.
3.6 REMOVAL OF EXISTING WATER AND SEWER SERVICES
A. The Contractor shall submit to the City for approval a detailed sequence and method of work for staking, abandonment of existing sewer services, water services, water meters, boxes, and cleanouts. The submittal shall include an 392
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 7
overview and general sequence of work; t ime and dates for each removal; and method and procedure for each removal.
B. ABANDONMENT OF SEWERS:
1. Contractor shall request an encroachment permit with Delta Diablo (District) for abandoning any existing sanitary sewer lateral pipes.
C. ABANDONMENT OF WATER LINES:
1. For service lines less than 4" diameter:
(a) Contractor shall pothole, cut out at the main, remove the corporation stop and saddle, and install a minimum 12" full circle 316 stainless steel repair clamp with 316 accessories around the pipe.
(b) Abandon unused existing water service lines in place, if at least 18" be- low grade to the Project Manager’s satisfaction.
2. Contact City Water Department in writing 48 hours in advance of abandon- ment, to check the condition of the existing services prior to abandonment.
D. GENERAL ABANDONMENT:
1. When salvage materials are shown on the Drawings; salvage and arrange the existing facilities (i.e., meters, manhole covers, manhole frames, etc.) to be dropped off at the City's Corporation Yard by prior arrangement.
2. Properly remove or abandon in place unused existing City utility service lines discovered that were left in place by others.
3. Contact utility companies for removal, abandonment, adjustment or reloca- tion of their facilities.
4. Contractor is responsible for verifying the location of any existing utilities.
5. Abandonment of pipes will include filling pipe with slurry as specified in Sec- tion 19 -3.02G – Controlled Low -Strength Material of the State Standard Specification and capping the pipes at the ends.
3.7 DISPOSAL OF DEMOLISHED MATERIALS
A. See Section 01 74 19 – Construction Waste Management and Disposal for disposal, salvaging and recycling of demolished materials.
B. Demolition and removal of debris shall be conducted to ensure minimum interference with roads, street s, walks and other adjacent occupied or used facilities which shall not be closed or obstructed without permission from the City.
Alternate routes shall be provided to circumvent closed or obstructed traffic ways.
C. The Contractor shall comply with all pertinent regulations of Cal/OSHA and local codes and practices.
D. All existing materials that are designated to be salvaged shall be removed, cleaned and hauled to the City Corporation Yard, unloaded and stockpiled unless otherwise directed by the Project Manager.
393
City of Pittsburg, California December 2022
DEMOLITION 02 41 00 - 8
E. Site debris, rubbish and other materials resulting from demolition operations shall become the property of the Contractor and shall be removed by the Contractor at the Contractor's expense. The proper and legal disposal of demolished materials shall be the responsibility of the Contractor. All disposal sites and recycling facilities shall be approved by the City prior to initiation of the Work.
1. Concrete debris shall be transported to a recycler of such materials.
2. Hazardous materials shall be handled and disposed of in accordance with all applicable laws, codes, and regulations.
3.8 PATCHING AND REPAIRING
A. The Contractor shall provide patching, replacing, repairing and refinishing of damaged areas or damaged adjacent facilities involved in the demolition.
B. New concrete shall match the existing adjacent surfaces, in kind, or of better quality, to the satisfaction of the Project Manager, at no cost to the City or to the owners of the facilities.
3.9 CLEAN UP
A. During and upon completion of work the Contractor shall promptly remove unused tools and equipment, surplus materials, rubbish, debris and dust and shall leave areas affected by work in a clean, approved condition.
B. The Contractor shall clean adjacent structures and facilities of dust, dirt and debris caused by demolition, as directed by the Project Manager, and return adjacent areas to condition existing prior to start of work.
C. The Contractor shall clean and sweep daily all street and roads affected by its operation.
END OF SECTION 02 41 00
394
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 1
SECTION 03 30 00 – UTILITY CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes Utility Cast-in-Place Concrete for Following Items:
1. Concrete pads around Utility facilities
2. Miscellaneous concrete footings for signs, street lighting, retaining walls, fence posts.
3. Thrust blocks.
4. Manhole Base.
5. Concrete aprons around water valves and manholes
6. Concrete Cap for shallow cover:
7. Retaining Walls
8. Survey Monuments
9. Electrical or Communications Duct Banks
10. Drainage Inlets
11. Concrete Headwalls
B. Related Requirements:
1. Section 31 23 16 – Utility Trenching
2. Section 33 05 13 - Manholes and Structures
3. Section 33 12 13 - Water Service Connections
4. Section 33 11 13 – Water Distribution Piping
5. Section 33 12 16 - Water Distribution Valves
6. Section 33 12 19 - Water Distribution Fire Hydrants
7. Section 33 31 13 - Sanitary Sewer Piping
8. Section 33 41 13 - Storm Drainage Piping
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. Section 01 29 00 - Payment Procedures : Contract Sum/Price modification procedures.
B. Concrete - Miscellaneous Locations:
1. Basis of Measurement:
a. Concrete Pads around Utility Facilities: Not a m easured item and incidental to item most closely related to the utility facility. For example, concrete pad around backflow prevention assembly is incidental to the backflow prevention assembly.
395
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 2
b. Miscellaneous Concrete Footings: Not a measured item and incidental to item most closely related to the facility . For example, footings for signs is incidental to the Sign and footings for Street Light pole is incidental to the bid item for Street lights or Electrical work as listed on the bid form.
c. Thrust Block: Not a measured item and incidental to item most closely related to the water facility – bends or pipes as listed on the bid form d. Manhole Base: Not a measure item and incidental to the unit price paid for manhole.
e. Concrete aprons around water valves and manholes: Not a measured item and incidental to the unit price paid for water valve or water main pipe and manhole respectively as shown on the bid form. f. Concrete Cap for shallow pipe cover: By cubic foot.
g. Retaining Walls: By linear foot measured along the top of wall, height and depth as shown on plans, including foundation, reinforcing steel, drain rock, drain pipe, and geotextile if applicable.
h. Survey Monuments: By unit price.
i. Electrical or Communications Duct Banks: Not a measured item and incidental to the duct bank installation.
j. Drainage Inlets: By unit price.
k. Concrete Headwalls: By unit price.
2. Basis of Payment: Includes concrete, placement accessories, consolidating, leveling, troweling, and curing.
1.3 REFERENCE STANDARDS
A. American Concrete Institute:
1. ACI 301 - Specifications for Structural Concrete.
2. ACI 305R - Guide to Hot Weather Concreting.
3. ACI 306.1 - Standard Specification for Cold Weather Concreting.
4. ACI 308.1 - Specification for Curing Concrete.
5. ACI 318 - Building Code Requirements for Structural Concrete.
B. ASTM International:
1. ASTM C31 - Standard Practice for Making and Curing Concrete Test Specimens in the Field.
2. ASTM C33 - Standard Specification for Concrete Aggregates.
3. ASTM C39 - Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens.
4. ASTM C42 - Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete.
5. ASTM C94 - Standard Specification for Ready-Mixed Concrete.
6. ASTM C143 - Standard Test Method for Slump of Hydraulic -Cement Concrete.
396
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 3
7. ASTM C150 - Standard Specification for Portland Cement.
8. ASTM C172 - Standard Practice for Sampling Freshly Mixed Concrete.
9. ASTM C173 - Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method.
10. ASTM C231 - Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method.
11. ASTM C260 - Standard Specification for Air -Entraining Admixtures for Concrete.
12. ASTM C330 - Standard Specification for Lightweight Aggre gates for Structural Concrete.
13. ASTM C494 - Standard Specification for Chemical Admixtures for Concrete.
14. ASTM C595 - Standard Specification for Blended Hydraulic Cements.
15. ASTM C618 - Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete.
16. ASTM C685 - Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing.
17. ASTM C845 - Standard Specification for Expansive Hydraulic Cement.
18. ASTM C989 - Standard Specification for Slag Cement for Use in Conc rete and Mortars.
19. ASTM C1017 - Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete.
20. ASTM C1064 - Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete.
21. ASTM C1107 - Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink).
22. ASTM C1116 - Standard Specification for Fiber-Reinforced Concrete.
23. ASTM C1157 - Standard Performance Specification for Hydraulic Cement.
24. ASTM C1218 - Standard Test Method for Water-Soluble Chloride in Mortar and Concrete.
25. ASTM C1240 - Standard Specification for Silica Fume Used in Cementitious Mixtures.
26. ASTM D994 - Standard Specification for Preformed Expansion Joint Filler for Concrete (Bituminous Type).
27. ASTM D1751 - Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types).
28. ASTM D1752 - Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction.
29. ASTM D6690 - Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements.
30. ASTM E96 - Standard Test Methods for Water Vapor Transmission of Materials.
31. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials.
397
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 4
32. ASTM E1643 - Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs.
33. ASTM E1745 - Standard Specification for Plastic Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs.
C. California Department of Public Health:
1. Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers, Version 1.1 (2010)
D. Caltrans Standard Specifications
1. Section 51 – Concrete Structures
2. Section 90 – Concrete
E. Bay Area Air Quality Management District:
1. BAAQMD Rule 8-51 - Adhesive and Sealant Applications.
1.4 COORDINATION
A. Coordinate placement of joint devices with erection of concrete formwork and placement of form accessories.
1.5 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit data on mix design, joint devices, attachment accessories, and admixtures.
C. Design Data:
1. Submit concrete mix design for each concrete strength.
2. Submit separate mix designs if admixtures are required for following:
a. Hot and cold weather concrete Work.
b. Air entrained concrete Work.
3. Identify mix ingredients and proportions, including admixtures.
4. Identify chloride content of admixtures and whether or not chlorides were added during manufacture.
D. Delivery Tickets: Provide delivery tickets at the time of delivery of each load of concrete. Each delivery ticket shall be accompanied by ba tch tickets 398
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 5
automatically produced by the batching equipment, indicating quantities of each ingredient. Each delivery ticket shall, in addition, state the mix number, total yield in cubic yards, date and the time of day, to the nearest minute, corresponding to when the batch was loaded, when it was dispatched, when it arrived at the job, and the time that unloading began.
1.6 CLOSEOUT SUBMITTALS
A. Section 01 78 00 – Closeout Submittals: Requirements for submittals.
1.7 QUALITY ASSURANCE
A. Comply with ACI 305R when pouring concrete during hot weather in Section 32 13 13 - Concrete Surface Improvements of the City Standard Specifications.
B. Comply with ACI 306.1 when pouring concrete during cold weather and as specified in Section 32 13 13 - Concrete Surface Improvements of the City Standard Specifications.
C. Acquire cement and aggregate from one source for Work.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Concrete:
1. Cement:
a. Comply with ASTM C150, Type II - Moderate Sulfate Resistant. b. Type: Portland.
2. Fine and Coarse Aggregates:
a. Conform to the requirements of Section 90 -1.02C, “Aggregates”, of the State Standard Specifications.
3. Water:
a. Conform to Section 90 -1.02D, “Water” of the State Standard Specifications.
b. Potable
B. Admixtures:
399
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 6
1. Air Entrainment: Conform to the requirements of Section 90-1.02E(3), “Air- Entraining Admixtures” of the State Standard Specifications.
2. Chemical: Conform to the requirements of Section 90 -1.02E(2), “Chemical Admixtures” of the State Standard Specifications.
3. Supplementary C ementitious Materials – Fly Ash: Conform to the requirements of Section 90 -1.02B(3), “Supplementary Cementitious Materials” of the State Standard Specifications.
4. Supplementary Cementitious Materials – Slag: Conform to the requirements of Section 90 -1.02B(3), “Supplementary Cementitious Materials” of the State Standard Specifications
2.2 CONCRETE MIX
A. Concrete shall conform to Section 90, “Concrete” of the State Standard Specifications.
B. Minimum 28-day compressive strength is 4,000 psi.
C. Concrete shall contain not less than 564 pounds of cemen titious material per cubic yard, except for Cast-in-place Pipe.
D. Ready-Mixed Concrete: Mix and deliver concrete according to ASTM C94.
2.7 CONSISTENCY
A. The consistency of the concrete in successive batches shall be determined by slump tests in accordance with ASTM C 143. Unless otherwise specified the slump for all concrete shall be in 4 inches maximum.
B. Retempering of concrete will not be permitted
2.8 MIXING AND TRANSPORTING
A. All concrete shall be mixed in mechanically operated mixers.
B. Ready-mix concrete shall meet the requirements as to materials, batching, mixing, transporting and placing as specified herein and in accordance with ASTM C94.
C. Ready-mixed concrete shall be delivered to the site of the work, a nd discharge shall be completed within one and one-half hours after the addition of the cement to the aggregates or before the drum has been revolved 250 revolutions, whichever is first. If the completion of delivery and discharge exceeds the above requirements, concrete shall be rejected and shall not be used for the project. 400
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 7
D. Truck mixers shall be equipped with electrically -actuated counters by which the number of revolutions of the drum or blades may be readily verified. The counter shall be of the reset table, recording type, and shall be mounted in the driver's cab. The counters shall be actuated at the time of starting mixers at mixing speeds.
E. Each batch of concrete shall be mixed in a truck mixer for not less than 70 revolutions of the drum or blades at the rate of rotation designated by the manufacturer of equipment. Additional mixing, if any, shall be at the speed designated by the manufacturer of the equipment as agitating speed. All materials including mixing water shall be in the mixer drum befo re actuating the revolution counter for determining the number of revolution of mixing.
F. Each batch of ready -mixed concrete delivered at the job site shall be accompanied by a delivery ticket furnished to the Project Manager.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify requirements for concrete cover over reinforcement.
B. Verify that anchors, bolts, seats, plates, reinforcement, and other items to be cast into concrete are accurately placed, positioned securely, and will not interfere with placing concrete.
3.2 PREPARATION
A. Section 01 70 00 - Execution: Requirements for installation preparation.
B. Previously Placed Concrete:
1. Prepare previously placed concrete by cleaning with stee l brush and applying bonding agent.
2. Remove laitance, coatings, and unsound materials.
C. In locations where new concrete is doweled to existing work, scan for existing rebar locations, drill the holes 1/4-inch larger than the nominal dowel diameter in existing concrete to avoid existing rebar , clean and prepare the holes in accordance with the anchoring system manufacturer’s instructions and thoroughly saturate with water, have all free water removed, and be dried to a saturated surface dry condition, coat the surface of the dowel, place epoxy inside the holes and insert steel dowels as specified per Section 51 -1.03E(4) of the State Standard Specification . Cure epoxy at least three (3) days or until the 401
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 8
dowels are completely encased in epoxy. Replace dowels that fail to bond or are damaged.
D. Remove debris and ice from formwork, reinforcement, and concrete substrates.
E. Remove water from areas receiving concrete before concrete is placed.
F. Thoroughly moisten forms, subgrade and earth surfaces with water imm ediately before placing concrete. An approved form release agent may be used in lieu of water for the forms. These surfaces shall be kept moist by frequent sprinkling up to the time of placing concrete thereon. The surface shall be free from standing water, mud and debris at the time of placing concrete.
G. Hardened concrete surfaces upon or against which concrete is to be placed, are defined as construction joints. The surfaces of horizontal joints shall be given a compacted, roughened surface to a minimum 1/4-inch amplitude for good bond.
Before new concrete is placed, the joint surfaces shall be cleaned of all laitance, loose or defective concrete and foreign material. Any water shall be removed from the surface of construction joints before the new concrete is placed.
H. Interruptions in placing concrete will not be allowed without the written approval of the City. The Contractor shall submit its proposed method of joint construction to the City for review and approval. When interruption of concrete placement operations has been approved the working face shall be given a shape by the use of forms or other means, that will secure proper union with subsequent work.
I. All reinforcement, anchor bolts, sleeves, inserts and similar items shall be set and secured in the forms where shown on the Drawings or by shop drawings and shall be acceptable to the City before any concrete is placed. Accuracy of placement is the responsibility of the Contractor.
J. No concrete shall be placed in any structure until all water entering the space to be filled with concrete has been properly cut off or has been diverted by pipes, or other means, and carried out of the forms, clear of the work. No concrete shall be deposited underwater nor shall the Contractor allow stil l water to rise on any concrete until the concrete has attained its initial set. Water shall not be permitted to flow over the surface of any concrete in such manner and at such velocity as will injure the surface finish of the concrete. Pumping or other necessary dewatering operations for removing ground water, shall be the responsibility of Contractor.
K. Anchor bolts shall be accurately set and shall be maintained in position by templates while being embedded in concrete.
402
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 9
3.3 PLACING
A. Placing of concrete shall conform to the requirements of Section 51 -1.03D, “Placing Concrete”, of the State Standard Specification and the requirements of this Section. All concrete which does not to conform to the requirements of this Section shall be removed from the work.
B. Concrete shall not be dropped through reinforcement steel into any form deeper than three (3) feet. In such cases, hoppers and, if necessary, vertical ducts of canvas, rubber or metal shall be used for placing concrete. In no case shall th e free fall of concr ete exceed three (3) feet below the ends of ducts, chutes or buggies.
C. Concrete in forms shall be deposited in uniform horizontal layers not deeper than 2 feet and care shall be taken to avoid inclined layers. Each layer shall be placed while the previous layer is still soft. The surface of the concrete shall be level whenever a run of concrete is stopped. The temperature of concrete when it is being placed shall be in conformance with Section 32 13 13 - Concrete Surface Improvements of the City Standard Specifications.
3.4 PUMPING OF CONCRETE
A. If the pumped concrete does not produce satisfactory end results as determined by the Project Manager, the Contractor shall discontinue the pumping operation and proceed with the placing of concrete using conventional methods.
3.5 CONSOLIDATION
A. As concrete is placed in the forms or in excavations, it shall be thoroughly settled and compacted in general conformance with Section 51 -1.03D, “Placing Concrete,” of the Caltrans Standard Specifications.
3.6 FINISHING CONCRETE SURFACES
A. Exposed surfaces shall be free from fins, bulges, ridges, offsets, honeycombing, or roughness of any kind, and shall present a finished, smooth, continuous hard surface.
B. No treatment is required after form removal except for curing, repair of defective concrete and treatment of surface defects.
C. After proper and adequate vibration and tamping, all exposed un-formed surfaces of pads and slabs, shall be brought to a uniform surface with suitable tools. The finish for all unformed concrete surfaces shall be a soft broom finish. 403
City of Pittsburg, California December 2022
UTILITY CAST-IN-PLACE CONCRETE 03 30 00 - 10
3.7 CURING
A. All exposed concrete top surfaces of pads, shall be cured in conformance with Section 32 13 13 - Concrete Surface Improvements of the City Standard Specifications.
3.8 PROTECTION
A. The Contractor shall protect all concrete against injury until final acceptance by the City. Holes left by form-tying and other minor imperfections as defined herein shall be repaired in an approved manner with cement grout in conformance with Section 03 60 00 - Grouting.
3.9 FIELD QUALITY CONTROL
A. Section 01 45 00 - Quality Control: Requirements for inspecting and testing.
B. Patching:
1. Allow Project Manager to inspect concrete surfaces immediately upon removal of forms.
2. Honeycombing or Embedded Debris in Concrete:
a. Not acceptable.
b. Notify the Project Manger upon discovery.
3. Patch imperfections according to ACI 301 when directed by the Project Manager.
C. Defective Concrete:
1. Description: Concrete not conforming to required lines, details, dimensions, tolerances, or specified requirements.
2. Repair or replacement of defective concrete will be determined by the Project Manager.
3. Do not patch, fill, touch up, repair, or replace exposed concrete except upon express direction of the Project Manager for each individual area.
END OF SECTION 03 30 00
404
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 1
SECTION 03 60 00 - GROUTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Portland cement grout.
2. Rapid-curing epoxy grout.
3. Non-shrink cementitious grout.
B. Related Requirements:
1. Section 03 30 00 – Utility Cast-in-Place Concrete: Cast-in-place or in -situ concrete for concrete structures and other concrete components.
2. Section 32 13 13 – Concrete Surface Improvements : Form materials, accessories as required to form cast in place concrete and maintain structural integrity until stripping.
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. Section 01 29 00 - Payment Procedures : C ontract Sum/Price modification procedures.
B. Grout:
1. Basis of Measurement: Not measured.
2. Basis of Payment: Inc idental to item most closely related to and includes preparation of substrate and grout, forming, mixing, placement, consolidation, troweling, curing, repairing and finishing grout.
1.3 REFERENCE STANDARDS
A. American Concrete Institute:
1. ACI 301 - Specifications for Structural Concrete for Buildings.
2. ACI 318 - Building Code Requirements for Structural Concrete.
B. ASTM International:
1. ASTM C33 - Standard Specification for Concrete Aggregates.
2. ASTM C40 - Standard Test Method for Organic Impurities in Fine Aggregates for Concrete.
405
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 2
3. ASTM C150 - Standard Specification for Portland Cement.
4. ASTM C191 - Standard Test Methods for Time of Setting of Hydr aulic Cement by Vicat Needle.
5. ASTM C307 - Standard Test Method for Tensile Strength of Chemical - Resistant Mortar, Grouts, and Monolithic Surfacings.
6. ASTM C531 - Standard Test Method for Linear Shrinkage and Coefficient of Thermal Expansion of Chemical -Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
7. ASTM C579 - Standard Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
8. ASTM C827 - Standard Test Method for Change in Height at Early Ages of Cylindrical Specimens of Cementitious Mixtures.
9. ASTM C1107 – Standard Specification for Packaged Dry Hydraulic-Cement Grout (Nonshrink).
C. U. S. Army Corps of Engineers Concrete Research Division (CRD):
1. CRD-C621 - Non-Shrink Grout.
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer information regarding grout.
C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
D. Manufacturer Instructions: Submit instructions for m ixing, handling, surface preparation, and placing epoxy-type and non-shrink grouts.
E. Field Quality -Control Submittals: Indicate results of Contractor -furnished tests and inspections.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Section 01 60 00 - Product Requirements : Requirements for transporting, handling, storing, and protecting products. Total storage time from date of manufacture to date of installation shall be limited to 12 months or the manufacturer’s recommended storage time, whichever is less.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage. Materials which becomes damp or otherwise unacceptable shall be immediately removed from the site and replaced with acceptable material.
406
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 3
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
PART 2 - PRODUCTS
2.1 PORTLAND CEMENT GROUT
A. Portland Cement: Comply with ASTM C150, Type II and per Section 90-1.02B(2) of the State Standard Specifications.
B. Water:
1. Potable and shall be per section 90 -1.02D of the State Standard Specification.
2. No impurities, suspended particles, algae, or dissolved natural salts in quantities capable of causing:
a. Corrosion of steel.
b. Volume change increasing shrinkage cracking.
c. Efflorescence.
d. Excess air entraining.
C. Fine Aggregate:
1. Washed natural sand.
2. Gradation:
a. Comply with Section 90, “Concrete” of the State Standard Specifications.
b. Represented by smooth granulometric curve within required limits.
3. Free from injurious amounts of organic impurities according to ASTM C40.
D. Mix:
1. Portland cement, sand, and water.
2. Do not use ferrous aggregate or staining ingredients in grout mixes.
2.2 RAPID-CURING EPOXY GROUT
A. Manufacturers:
407
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 4
1. Sika Corporation
2. W.R. Meadows, Inc.
3. Euclid Chemical
4. Or approved equal.
B. Description:
1. High-strength, three-component epoxy grout formulated with thermosetting resins and inert fillers.
2. Rapid-curing, high adhesion, and resistant to ordinary chemicals, acids, and alkalis.
3. Resins containing butyl glycidyl ether (BGE) or other highly volatile and hazardous reactive diluents are not acceptable.
C. Performance and Design Criteria:
1. Minimum Compressive Strength:
a. 11,000 psi at seven days.
b. Comply with ASTM C579.
2. Minimum Tensile Strength:
a. 2,000 psi.
b. Comply with ASTM C307.
3. Coefficient of Expansion:
a. 30x10-6 inch per degree F.
b. Comply with ASTM C531.
4. Shrinkage:
a. None.
b. Comply with ASTM C827.
5. Application: Epoxy grout shall be used to embed all anchor bolts and reinforcing steel required to be set in grout, and for all other specified applications.
2.3 NON-SHRINK CEMENTITIOUS GROUT
A. Manufacturers:
1. Sika Corporation
2. W.R. Meadows
3. Euclid Chemical
408
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 5
4. Or approved equal.
B. Description:
1. Pre-mixed and ready-for-use formulation requiring only addition of water.
2. Noshrink grouts shall meet or exceed the requirements of ASTM C1107 Grades B or C and CRD-C621.
3. Non-shrink, non-corrosive, non-metallic, non-gas forming, and no chlorides.
4. Manufacturer's instructions shall be printed on each bag or other container in which the materials are packaged.
C. Performance and Design Criteria:
1. The grouts shall exhibit no shrinkage when tested in conformity with ASTM C827.
2. Certified to maintain initial placement volume or expand after set, and to meet following minimum properties when tested according to CRD-C621 for Type D non-shrink grout:
a. Setting Time:
1) Initial: Approximately two hours.
2) Final: Approximately three hours.
3) Comply with ASTM C191.
b. Maximum Expansion: 0.10 to 0.40 percent.
c. Minimum Compressive Strength:
1) One-Day: 4,000 psi.
2) Seven-Day: 6,000 psi.
3) 28-Day: 7,500 psi.
4) Comply with CRD-C621.
2.4 FORMWORK
A. As specified in Section 32 13 13 – Concrete Surface Improvements.
2.5 CONSISTENCY
A. The consistency of grouts shall be that necessary to completely fill the space to be grouted for the particular application. Dry pack consistency is such that the grout is plastic and moldable but will not flow. Where "dry pack" is specified, it shall mean a grout of that consistency; the type of grout to be used shall be as specified herein for the particular application.
409
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 6
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify areas to receive grout. Reinforcing steel shall be inspected prior to placing grout.
3.2 PREPARATION
A. Section 01 70 00 - Execution: Requirements for installation preparation.
B. Remove defective concrete, laitance, dirt, oil, grease, and other foreign material from concrete surfaces by brushing, hammering, chipping, or other similar means until sound and clean concrete surface is achieved.
C. Roughen concrete lightly, but not to interfere with placement of grout.
D. Remove foreign materials from metal surfaces in contact with grout.
E. Align, level, and maintain final positioning of components to be grouted.
F. Saturate concrete surfaces with clean water, and then remove excess water.
3.3 INSTALLATION
A. Formwork:
1. Construct leakproof forms anchored and shored to withstand grout pressures.
2. Install formwork with clearances to permit proper placement of grout.
3. As specified in Section 32 13 13 – Concrete Surface Improvements.
B. Mixing:
1. Portland Cement Grout:
a. Use proportions of two parts sand and one-part cement, measured by volume.
b. Prepare grout with water to obtain consistency to permit placing and packing.
c. Mix water and grout in two steps:
1) Premix using approximately 2/3 of water.
2) After partial mixing, add remaining water to bring mix to desired placement consistency and continue mixing two to three
minutes.
410
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 7
d. Mix only quantities of grout capable of being placed within 30 minutes after mixing.
2. Rapid-Curing Epoxy Grout:
a. Mix and prepare according to manufacturer instructions. b. Minimum Compressive Strength: 10,000 psi in 72 hours and 13,000 psi in 28 days.
3. Non-shrink Cementitious Grout:
a. Mix and prepare according to manufacturer instructions. b. Minimum Compressive Strength: 4,500psi in 72 hours and 7,500 psi in 28 days.
4. Mix grout components in proximity to Work area and transport mixture quickly and in manner not permitting segregation of materials.
C. Placing of Grout:
1. Place grout material quickly and continuously to avoid cold joints.
2. Do not place cement grout in layers.
3. Do not add additional water to the mix (retemper) after initial stiffening.
4. Do not use pneumatic-pressure or dry-packing methods.
5. Apply grout from one side only to avoid entrapping air.
6. Do not vibrate placed grout mixture or permit placement if area is being vibrated by nearby equipment.
7. Thoroughly compact final installation and eliminate air pockets.
8. Do not remove leveling shims for at least 48 hours after grout has been placed.
D. Curing:
1. Prevent rapid loss of water from grout during first 48 hours by use of approved membrane curing compound or by using wet burlap method.
2. Immediately after placement, protect grout from premature drying, excessively hot or cold temperatures, and mechanical injury.
3. After grout has attained its initial set, keep damp for minimum three days.
Saturate the grout surface by use of wet burlap, ponding or other approved means.
4. Epoxy grouts are self-curing and do not require the application of water.
E. Upon completion of the jacking operations, all voids around the outside face of the conduit shall be filled by grouting.
F. Grouting equipment and material shall be on the job site before jacking operations and drilling of grout holes are completed in order that grouting around 411
City of Pittsburg, California December 2022
GROUTING 03 60 00 - 8
the jacked conduit may be started immediately after the jacking operations have finished.
3.4 FIELD QUALITY CONTROL
A. Section 01 45 00 - Quality Control: Requirements for inspecting and testing.
B. Inspection and Testing:
1. Comply with ACI 301, ACI 318.
2. Submit proposed mix design of each class of grout to the Project Manager for review prior to commencement of Work.
3. Tests of grout components may be performed to ensure compliance with specified requirements.
END OF SECTION 03 60 00
412
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 1
SECTION 09 90 00 - PAINTING AND COATING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Surface preparation and field application of paints, including pretreatment, coating application, touch-up of factory-coated surfaces, protection of surfaces not to be coated, cleanup and other coatings.
B. Glass, stainless steel, and equipment nameplates shall not be protective coated unless shown otherwise on the Drawings.
1.2 DEFINITIONS
A. Refer to ASTM D16 for definitions of terms used in this Section.
B. The term "paint," "coatings," "linings," or "finishes" as used herein, shall include surface treatments, emulsions, enamels, paints, epoxy resins, and all other protective coatings, excepting galvanizing or anodizing, whether used as a pretreatment, primer, intermediate coat, or finish coat. The term "DFT" means minimum dry film thickness.
1.3 REFERENCE STANDARDS
A. ASTM International:
1. ASTM C309 – Standard for Liquid Membrane – Forming Compounds for Curing Concrete.
2. ASTM D16 – Standard Terminology for Paint, Related Coatings, Materials, and Applications.
3. ASTM D4442 - Standard Test Methods for Direct Moisture Content Measurement of Wood and Wood-Base Materials.
4. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials.
B. AWWA
1. AWWA C105 – Standard for Polyet hylene Encasement for Ductile -Iron Piping for Water and Other Liquids.
2. AWWA C205 - Standard for Cement-Mortar Protective lining and Coating for Steel Water Pipe – 4-inch and larger – Shop applied.
3. AWWA C550 - Standard for Protective Epoxy Interior coatin gs for Valves and Hydrants.
413
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 2
C. California Department of Public Health:
1. CA/DHS/EHLB/R-174 - Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers, including 2004 Addenda.
D. Caltrans Standard Specifications
1. Section 59 – Structural Steel Coatings
2. Section 91 – Paint
E. Green Seal:
1. GS-03 - Anti-Corrosive Paints.
2. GS-11 - Paints and Coatings.
F. Master Painters Institute:
1. MPI - Approved Products List.
2. MPI - Architectural Painting Manual.
G. NACE National Association of Corrosion Engineers
H. NSF National Sanitation Foundation
I. SSPC Steel Structures Painting Council
1.4 SEQUENCING
A. Do not apply finish coats until paintable sealant is applied.
B. Back prime wood trim before installation of trim.
1.5 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data:
1. Submit manufacturer data on finishing products, special coatings and paint.
2. Include MPI - Approved Products Lists with proposed products highlighted.
C. Samples:
1. Submit two (2) paper chip samples, 4 inches by 4 inches in size, illustrating range of colors and textures available for each surface finishing product as scheduled.
2. Painted Samples:
414
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 3
a. Submit two (2) painted samples, illustrating selected colors and textures for each selected color and system with specified coats cascaded.
D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
E. Manufacturer Instructions: Submit special surface preparation procedures, substrate conditions requiring special attention.
F. Field Quality -Control Submittals: Indicate results of Contractor-furnished tests and inspections.
1.6 CLOSEOUT SUBMITTALS
A. Section 01 78 00 - Closeout Submittals: Requirements for submittals.
B. Operation and Maintenance Data: Submit information on cleaning, touchup, and repair of painted and coated surfaces.
1.7 QUALITY ASSURANCE
A. MPI Standards:
1. Comply with indicated MPI standards.
2. Products: Listed in MPI - Approved Products List.
B. Surface Burning Characteristics:
1. Fire-Retardant Finishes: Maximum 25/450 flame-spread/smoke-developed index when tested according to ASTM E84.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Section 01 60 00 - Product Requirements : Requirements for transporting, handling, storing, and protecting products.
B. Container Labeling: Include manufacturer's name, type of paint, brand name, lot number, brand code, coverage, surface preparation, drying time, cleanup requirements, color designation, and instructions for mixing and reducing.
C. Inspection:
1. Accept materials on Site in manufacturer's sealed and labeled containers.
2. Inspect for damage and to verify acceptability.
415
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 4
D. Store materials in ventilated area and otherwise according to manufacturer instructions.
E. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
1.9 AMBIENT CONDITIONS
A. Section 01 50 00 - Temporary Facilities and Controls: Requirements for ambient condition control facilities for product storage and installation.
B. Storage Conditions:
1. Minimum Ambient Temperature: 45 degrees F.
2. Maximum Ambient Temperature: 85 degrees F.
C. Application Conditions:
1. Do not apply materials when surface and ambient temperatures are outside temperature ranges required by paint manufacturer.
2. Do not apply exterior coatings during rain, when relative humidity is outside humidity ranges, or when moisture content of surfaces exceeds those required by paint manufacturer.
3. Minimum Application Temperatures for Latex Paints : 45 degrees F for interiors and 50 degrees F for exteriors, unless otherwise indicated by manufacturer instructions.
4. Minimum Application Temperature for Varnish and Finishes: 65 degrees F for interiors and exteriors, unless otherwise indicated by manufact urer instructions.
5. Lighting Level: 80 fc, measured mid-height at substrate surface.
1.10 WARRANTY
A. Section 01 70 00 - Execution and Section 01 77 00 - Closeout Requirements:
Requirements for warranties.
B. Furnish five (5) year manufacturer's warranty for paint and coatings. 416
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 5
PART 2 - PRODUCTS
2.1 PAINTS AND COATINGS
A. Manufacturers:
1. Kelly-Moore Paint Company, Inc.
2. Sherwin-Williams Company
3. Vista Paint
4. Dunn-Edwards Corporation
5. Rust-Oleum
6. Glidden Company
7. Behr Process Corporation
8. Or approved equal
9. Substitutions: As specified in Section 01 60 00 - Product Requirements.
B. Materials:
1. Coatings:
a. Ready mixed, except field-catalyzed coatings.
b. Capable of drying or curing free of streaks or sags.
2. Patching Materials: Latex filler.
3. Fastener Head Cover Materials: Latex filler.
4. Accessories:
a. Grade: Commercial.
b. Linseed oil.
c. Shellac.
d. Turpentine.
e. Paint thinners.
f. Other materials not specifically indicated but required to achieve specified finishes.
PART 3 - EXECUTION
3.1 SURFACE PREPARATION STANDARDS
A. The following referenced surface preparation specifications of the Steel Structures Painting Council's "Steel Structure Painting M anual, Volume 2, Systems and Specification" shall form a part of this specification:
1. Solvent Cleaning (SSPC-SP1): Removal of oil, grease, dirt, soil, salts, and contaminants by cleaning with solvent, vapor, alkali, emulsion, or steam. 417
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 6
2. Hand Tool Cleaning (SSPC-SP2): Removal of loose rust, loose mill scale, and loose paint to degree specified, by hand chipping, scraping, sanding, and wire brushing.
3. Power Tool Cleaning (SSPC-SP3): Removal of loose rust, loose mill scale, and loose paint to degree specifi ed by power tool chipping, descaling, sanding, wire brushing, and grinding.
4. White Metal Blast Cleaning (SSPC -SP5): Removal of all visible rust, mill scale, paint, and foreign matter by blast cleaning by wheel or nozzle (dry or wet) using sand, grit, or shot.
5. Commercial Blast Cleaning (SSPC-SP6): Blast cleaning until at least two - thirds of each element of surface area is free of all visible residues.
6. Brush-Off Blast Cleaning (SSPC -SP7): Blast cleaning of all except tightly adhering residues of mill sca le, rust, and coatings, exposing numerous evenly distributed flecks of underlying metal.
3.2 EXAMINATION
A. Verify that surfaces and substrate conditions are ready to receive Work as recommended by product manufacturer.
B. Evaluate blast cleaned surface preparation work will be based upon comparison of the blasted surfaces with the definitions and standard visual samples available from SSPC, using SSPC-V1S1 Standards.
C. Examine surfaces scheduled to be finished prior to commencement of Work, and report cond itions capable of affecting proper application to City’s Project Manager. The Project Manager shall be sole judge as to whether the quality of blast cleaning conforms to visual comparison standards, and the Project Manager’s decision as to allowability shall be final.
D. Test shop-applied primer for compatibility with subsequent cover materials.
E. Moisture Content:
1. Measure moisture content of surfaces using electronic moisture meter.
2. Do not apply finishes unless moisture content of surfaces are below following maximums:
a. Masonry, Concrete, and Concrete Unit Masonry: 12 percent. b. Exterior Wood: 15 percent, measured according to ASTM D4442. 418
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 7
3.3 PREPARATION
A. Section 01 70 00 - Execution: Requirements for application preparation.
B. Prepare coatings as follows:
1. To soft paste consistency, capable of being readily and uniformly dispersed to homogeneous coating.
2. For smooth flow and brushing properties.
C. Surface Appurtenances: Remove or mask electrical plates, hardware, light fixture trim, escutcheons, and fittings prior to preparing surfaces or finishing.
D. The working parts of all mechanical and electrical e quipment shall be protected from damage during surface preparation and coating operations. Openings in motors shall be masked to prevent entry of coating or other materials.
E. Defects:
1. Correct defects and clean surfaces capable of affecting Work of this Section.
2. Remove or repair existing coatings exhibiting surface defects.
F. Cleaning and coating shall be done such that dust and other contaminants from the cleaning process will not fall on wet, newly-coated surfaces.
G. Marks: Seal marks that may bleed through surface finishes with shellac.
H. Impervious Surfaces:
1. Remove mildew by scrubbing with solution of tetra -sodium or tri -sodium phosphate and bleach.
2. Rinse with clean water and allow surface to dry.
I. Aluminum Surfaces Scheduled for Paint Finish:
1. Remove surface contamination by steam or high-pressure water.
2. Remove oxidation with acid etch and solvent washing.
3. Apply etching primer immediately following cleaning.
J. Asphalt, Creosote, or Bituminous Surfaces Scheduled for Paint Finish:
1. Remove foreign particles to permit adhesion of finishing materials.
2. Apply latex-based or compatible sealer or primer.
K. Copper Surfaces Scheduled for Paint Finish:
1. Remove contamination by steam, high-pressure water, or solvent washing.
2. Apply vinyl-etch primer immediately following cleaning. 419
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 8
L. Copper Surfaces Scheduled for Natural Oxidized Finish:
1. Remove contamination by applying oxidizing solution of copper acetate and ammonium chloride in acetic acid.
2. Rub on repeatedly for required effect, and, once attained, rinse surfaces with clear water and allow to dry.
M. Galvanized Surfaces:
1. Remove surface contamination and oils, and wash with solvent.
2. Apply coat of etching primer.
N. Concrete and Unit Masonry Surfaces Scheduled to Receive Paint Finish:
1. Remove dirt, loose mortar, scale, salt or alkali po wder, and other foreign matter.
2. Remove oil and grease with solution of tri -sodium phosphate, rinse well, and allow to dry.
3. Remove stains caused by weathering of corroding metals with solution of sodium metasilicate after thoroughly wetting with water, and allow to dry.
O. Uncoated Steel and Iron Surfaces:
1. Remove grease, mill scale, weld splatter, dirt, and rust.
2. If heavy coatings of scale are evident, remove by power tool wire brushing or by sandblasting.
3. Clean by washing with solvent.
4. Apply treatment of phosphoric acid solution, ensuring that weld joints, bolts, and nuts are similarly cleaned.
5. Spot-prime paint after repairs.
P. Shop-Primed Steel Surfaces:
1. Sand and scrape to remove loose primer and rust.
2. Feather edges to make touch-up patches inconspicuous.
3. Clean surfaces with solvent.
Q. Exterior Wood Scheduled to Receive Paint Finish:
1. Remove dust, grit, and foreign matter.
2. Seal knots, pitch streaks, and sappy sections.
3. Fill nail holes with tinted exterior paintable calking compound after prime coat has been applied.
R. Exterior Wood Scheduled to Receive Transparent Finish:
1. Remove dust, grit, and foreign matter.
2. Seal knots, pitch streaks, and sappy sections with sealer. 420
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 9
3. Fill nail holes with tinted exterior calking compound after sealer has been applied.
S. Existing Work:
1. Extend existing paint and coatings installations using materials and methods compatible with existing installations and as specified.
3.4 APPLICATION
A. Comply with MPI - Architectural Painting Manual.
B. Do not apply finishes to surfaces that are not dry.
C. Apply each coat to uniform appearance.
D. Apply each coat of paint slightly darker than preceding coat, unless specified otherwise.
E. Prime Coat DFT = 3 mils each
F. Finish Coats (2 or more) DFT = 3 mils each
G. Total System DFT = 6 mils, minimum.
H. Sand wood and metal surfaces lightly between coats to achieve required finish.
I. Cleaning:
1. Vacuum surfaces to remove loose particles.
2. Use tack cloth to remove dust and particles just prior to applying next coat.
J. Fillers:
1. If clear finishes are required, tint fillers to match wood.
2. Work fillers into grain before set, and wipe excess from surface.
K. Concealed Surfaces:
1. Prime concealed surfaces of interior and exterior woodwork with primer paint.
2. Prime concealed surfaces of interior wood surfaces scheduled to receive stain or varnish finish with gloss varnish reduced 25 percent with thinner.
3.5 FIELD QUALITY CONTROL
A. Inspecting and Testing: Comply with MPI - Architectural Painting Manual. 421
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 10
3.6 CLEANING
A. Section 01 77 00 - Closeout Requirements: Requirements for cleaning.
B. Collect waste material that may constitute fire hazards, place in closed metal containers, and remove daily from Site.
C. Improper disposal for hazardous materials will not be allowed.
3.7 COATING SYSTEM
A. Alkyd Enamel: High quality, gloss or semi -gloss, medium long oil alkyd finish shall have a minimum solids content of 49 percent by volume. Primer shall be as recommended by manufacturer.
B. Fusion Bonded Epoxy: The coating material shall be 100 percent powder epoxy applied in conformance with AWWA C550, except that the surface preparation shall be as specified in the Coating System Schedule of this Section.
1. Liquid Epoxy: For field repairs, the use of a liquid epoxy will be permitted, applied in not less than 3 coats to provide a total DFT of 12 mils. The liquid epoxy shall be 100 percent solids epoxy recommended by the powder epoxy manufacturer.
2. Field Repair coatings (DFT = 12 mils), Scotchkote 306 or 312, PCI Augsburg DURA-POX 646 or equal.
C. Polyethylene Encasement: Application of polyethylene encasement shall be in conformance with AWWA C 105 using Method A.
D. Cement Mortar Coating: Unless otherwis e shown on the Drawings, mortar coating and reinforcement shall be in conformance with AWWA C205.
E. Factory Applied Coating: The coating material shall be a liquid epoxy applied in conformance with AWWA C550.
F. Coal Tar Paint: High Solids content coal tar paint for use on buried pipeline and fittings.
1. Prime Coat and finish coats (2 or more, total DFT = 24 mils), Protecto Wrap CA-1200, Polyguard No. CA -14, Kop -Coat Bituminastic Super Service Black, or equal.
3.8 SCHEDULE
A. See below Coating System Schedule A for Ferrous Metal and not galvanized.
Item Surface
Preparation
Coating System
422
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 11
All surfaces, indoors and outdoors,
exposed or covered, except those
surfaces included below
Commercial Blast
Cleaning
SSPC-SP6
Alkyd Enamel
Exposed Fire Hydrant, valve lids,
marker posts, backflow preventor
lettering, exposed pipe, fittings and
vent pipe
Solvent Cleaning
SSPC-SP1
Alkyd Enamel
Buried pipe with a nominal diameter of
less than 6 inches and greater than 2
inches, excluding ductile iron pipe
Solvent Cleaning
SSPC-SP1
Coal Tar Paint
Fittings and flanged joints, where the
piping is plastic. Buried fittings on
ductile iron pipe used for FH laterals,
fire service laterals, and Backflow
Prevention Assemblies. Joints, and
fittings on ductile iron pipe with coal tar
coating.
Commercial Blast
Cleaning
SSPC-SP6
Coal Tar Paint
Buried pipe couplings; fittings; and
flanged joints, including epoxy coated
surfaces, except valves; where the
piping is polyethylene encased ductile
iron
As specified in
Specifications for
appropriate
fittings
Polyethylene
Encasement
Buried pipe couplings, fittings, and
flanged joints, where piping is cement
mortar coated and lined steel pipe,
excluding epoxy coated surfaces.
Solvent Cleaning
SSPC-SP1
Cement Mortar
Coating
Buried cast couplings, buried sleeve-
type tapping sleeves, welded tapping
outlets. Ferrous surfaces of gate
valves.
White Metal Blast
Cleaning
SSPC-SP5
Fusion Bonded
Epoxy
423
City of Pittsburg, California December 2022
COATING AND PAINTING 09 99 00 - 12
External ferrous surfaces of check
valves and ferrous internal surfaces of
fire hydrants.
White Metal Blast
Cleaning
SSPC-SP5
Fusion Bonded
Epoxy
Internal/External Ferrous Surfaces of
butterfly valves
White Metal Blast
Cleaning
SSPC-SP5
Factory Applied
Epoxy
B. See below Coating System Schedule B for Ferrous Metal and Galvanized.
Item Surface
Preparation
Coating System
All exposed surfaces, indoors or
outdoors, including exposed
galvanized pipe, except those surfaces
included below.
Alkaline Cleaning
per
SSPC-SP1
Alkyd Enamel
Buried pipe with a nominal diameter of
2 inches and less, including valves,
fittings
Alkaline Cleaning
per
SSPC-SP1
Coal Tar Paint
END OF SECTION 09 90 00
424
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 1 SECTION 31 05 13 – CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Clearing and Grubbing
2. Excavation
3. Earthwork
4. Grading and Compaction
5. Subsoil materials – Import Fill and Select Fill
6. Topsoil materials.
B. Related Sections:
1. Section 01 74 00 – Construction Waste Management and Disposal
2. Section 31 23 16 – Utility Trenching.
3. Section 32 90 00 – Landscape Work.
4. Project Geotechnical report; bore hole locations and findings of subsurface materials if applicable.
1.2 UNIT PRICES - MEASUREMENT AND PAYMENT
A. Clearing and Grubbing:
1. Basis of Measurement: Clearing and grubbing will be measured on a lump sum basis, unless specified otherwise.
2. Basis of Payment: Clearing and grubbing shall be paid for at the contract lump sum price, which includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in clearing and grubbing as shown on the plans, as specified and as directed by the Project Manager , including the removal and disposal of all the resulting material.
a. When the Contract does not include a pay item for Clearing and Grubbing and removal work, as specified above, and unless noted otherwise in the Technical Specifications, full compensation for any necessary Clearing and Grubbing and removal work shall be considered as included in the unit price paid for the type of earthwork involved, and no additional compensation will be allowed therefor.
B. Subsoil – Select Fill
1. Basis of Measurement: By cubic yard of the compacted soil. 425
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 2
2. Basis of Payment: Includes excavating existing subsoil, verifying if existing subsoil meets the select fill requirements, supplying select fill, materials, stockpiling, maintaining, moving, placing and compacting of select fills.
C. Subsoil – Import Fill
1. Basis of Measurement: By cubic yard of the compacted soil.
2. Basis of Payment: Includes excavating, importing, supplying import fill subsoil materials, stockpiling, surveying stockpile location, maintaining, moving, placing and compacting of import fill.
D. Subsoil – Export Fill
1. Basis of Measurement: By cubic yard of the compacted soil.
2. Basis of Payment: Includes excavating, stockpiling, covering, maintaining, moving, exporting cut subsoil materials, compacting of cut soil at the export location, and all other work described in this section, and as shown on the Drawings.
1.3 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO T180 - Standard Specification for Moisture -Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. City of Pittsburg - Environmental Services Department C. ASTM International:
1. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3).
2. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3).
3. ASTM D2487 - Standard Classification of Soils for Engineering Purposes (Unified Soil Classification System).
D. California Building Code – Appendix J - Grading
E. State Standard Specifications:
1. Section 14 – Environmental Stewardship
2. Section 17 - General
3. Section 19 – Earthwork
426
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 3
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Samples: Submit results of the soil samples by a certified testing laboratory prior to importing onto the site for approval by the Project Manager.
C. Materials Source: Submit name of imported materials source.
D. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.
1.5 QUALITY ASSURANCE
A. Furnish each subsoil material from single source throughout the Work.
PART 2 - PRODUCTS
2.1 SUSTAINABILITY CHARACTERISTICS
A. Materials and Resources Characteristics:
1. Regional Materials: Furnish materials extracted, processed, and manufactured within 250 miles of jobsite.
2.2 SUBSOIL MATERIALS
A. Select Fill Material:
1. Subsoil material is on-site excavated material meeting the requirements of the appurtenant Geotechnical Report.
2. Graded
3. Non-hazardous
4. Free of lumps larger than three (3) inches, rocks larger than two (2) inches, organic matter, frozen or other deleterious materials and debris.
5. Selected material encountered in excavation within the right of way shall be used for finishing the top portion of the roadbed, constructing shoulders, structure backfill; as shown on the Drawings; as specified in the Technical Specifications, or as directed by the Project Manager.
B. Import Fill Material:
1. Subsoil material imported from sources outside the project site meeting the requirements of the appurtenant Geotechnical Report.
427
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 4
2. Graded
3. Non-hazardous
4. Free of lumps larger than three (3) inches, rocks larger than two (2) inches, organic matter, frozen or other deleterious materials and debris.
5. Unless otherwise specified, the Contractor shall obtain from the owners the right to procure material, pay all royalties and other charges involved, and bear all expense of developing the sources, including rights of way for hauling.
6. No import fill material shall be delivered to the site until approved by the Project Manager. Approval of import fill material shall be based on the testing of representative samples submitted by the contractor meeting the appurtenant Geotechnical Report and approved by the Project Manager .
Such representative samples shall be submitted to the Project Manager not less than 15 days prior to commencing the work.
7. Imported fill, delivered to the site, that significantly differs from the submitted samples shall be subject to rejection. Rejected materials shall be removed from the site at the Contractor's expense
8. Approval of a particular import fill material shall constitute approval of only that portion of the propose d borrow source represented by the submitted sample.
10. Except as otherwise permitted, borrow pits and other excavation areas shall be excavated in such manner as will afford adequate drainage. Overburden and other spoil material shall be transported to desig nated spoil areas or otherwise disposed of as directed, local borrow pits shall be neatly trimmed and left in such shape as will facilitate accurate measurement after the excavation is completed.
2.3 FILL MATERIALS:
The following import fill parameters may be used for small City sidewalk and pavement rehabilitation projects; or for site improvements less than 5,000 square feet excluding any buildings or structures and do not have a geotechnical report included:
A. Fill material shall conform to the following as d etermined by ASTM C 117 and ASTM C 136:
1. Maximum particle size 3 inches
2. Percent passing 1-inch sieve 90-100 percent
3. Percent passing No. 200 sieve less than 20 percent
B. Imported non-expansive fill shall consist of a well -graded, slightly cohesive soil with relatively impervious characteristics when compacted.
C. Plasticity Index for acceptable import fill materials shall be a maximum of 15 when determined by the procedure set forth in ASTM D 4318.
428
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 5 D. The liquid limit shall not exceed 40 percent as determined by the procedures set forth in ASTM D 4318.
E. Import fill material shall have an R-value of 25 or greater as determined by ASTM D 2844.
2.4 TOPSOIL MATERIALS
A. Topsoil shall be imported top soil as specified in Section 32 90 00 “Landscape Work” and Project Specifications.
B. Topsoil excavated within the limits of the project meeting the requirements shown in Section 32 90 00, “Landscape Work”, and as shown in the Project Specifications will be considered as a material only for the purpose of backfilling areas to be planted.
2.5 SOURCE QUALITY CONTROL
A. Section 01 45 00 – Quality Control: Testing and Inspection Services Testing and analysis of soil material.
B. Testing and Analysis of Subsoil and Topsoil Materials: Perform in accordance with ASTM D698, ASTM D1557, and AASHTO T180.
C. When tests indicate materials do not meet specified requirements, provide alternate materials and retest.
D. Furnish materials of each type from same source throughout the Work.
PART 3 - EXECUTION
3.1 PREPARATION
A. Call USA not less than three (3) working days before performing Work that can be marked by USA in a timely manner.
B. Request underground utilities to be located and marked within and surrounding construction areas.
C. Identify required lines, levels, contours and datum.
D. Notify utility companies to remove and relocate utilities where shown on the Drawings.
E. Protect utilities indicated to remain from damage.
429
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 6 F. Protect plant life, lawns, and other features remaining as portion of final landscaping.
G. Protect benchmarks or monuments , survey control points, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.
H. The ground shall be prepared to received select fill by removing vegetation, topsoil and other unsuitable materials, scarifying the ground to provide a bond with the fill material, and compacting the fill at optimum moisture content.
3.2 CLEARING AND GRUBBING
A. Clearing and grubbing shall be per Section 17-2, “Clearing and Grubbing”, of the State Standard Specifications.
B. Clear and grub before performing earthwork in an area.
C. Do not injure standing trees, plants, and improvements shown to be protected.
D. Clear and grub the entire length of the job site to the following widths:
1. 5 feet outside of excavation and embankment slope lines where slopes are not rounded
2. Outside limits of slopes where slopes are rounded
3. 5 feet outside of structures
4. 2 feet outside of slope lines for ditches and channels with a bottom width of less than 12 feet
5. 5 feet outside of slope lines for ditches and channels with a bottom width of 12 feet or more
E. Clearing and grubbing shall consist of removing all objectionable material from within the limits of the project. The limits of clearing and grubbing shall be of sufficient area and depth to complete the work shown on the Drawings or as described herein in.
F. Clear all construction areas above original ground of the following to a minimum depth of eight (8) inches below subgrade or eight (8) inches below original ground, or as required by the appurtenant geotechnical report, whichever is lower:
1. all vegetation such as trees, logs, upturned stumps, roots of downed trees, brush, grass, and weeds and
2. other objectionable material including concrete, masonry, and debris.
G. No burning of materials is allowed.
H. The site shall be stripped and cleared of all vegetation, debris, and organic-laden top soil as required by the appurtenant Geotechnical Report. 430
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 7 I. Trees within the limits of work including any traffic control work beyond the limits of work and within the are a of influence shall be evaluated by the City or; a City approved L andscape Architect or certified Arborist to assess protection measures. No trees will be removed until they have been tagged, numbered and a written release for the tree has been issued by the City.
J. Tree which are designated to be removed, shall be excavated and removed 30” down to remove the tree trunk, roots, and backfill with fill material and compact as required in this section, unless specified otherwise on the Drawings.
K. Grub all construction areas to a depth of at least 0.50 feet, necessary to remove all existing tree stumps, roots, buried logs and other objectionable material, unless noted otherwise on the Plans. In embankment areas where the grading plane is 2 feet or more above original ground, cut off trees, stumps, and roots not more than 1 foot above original ground, except, remove trees, stumps, and roots completely where work includes any of the following:
1. Structure construction
2. Pile construction
3. Subdrainage trench excavation
4. Removal of unsuitable material
5. Cutting into slopes of original hillsides, old or new fill
6. Utility line construction
3.3 EXCAVATION
A. Work under this section shall consist of performing all operations necessary to excavate earth and rock, regardless of character and subsurface conditions, from the roadway prism or adjacent thereto, to excavate all materials, of whatever nature, necessary for the construction of foundations for structures and other facilities: to excavate drainage and irrigation ditches ; to excavate drainage channels; to excavate selected material and import material for use as specified; to construct embankments including the placing of selected fill or import fill material in connection therewith as specified; to place backfill for structures, and other facilities; to backfill trenches and depressions resulting from the removal of obstructions; to backfill holes, pits and other depressions; to remove and replace unsuitable material; to excavate and grade road approaches, driveways, sidewalks, curb ramps, curb and gutters, plazas, parking lots, and connections; to construct protection dikes; to remove unstable material, slide material which has come into the graded area, and material which has slipped from embankments; all as shown on the plans and as specified in these Specifications and the Technical Specifications and as directed by the Project Manager; and furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work that may be required to construct and maintain the project facilities, except excavation, trenching and backfilling for pipe, culverts, utility systems, and other subsurface pipes. Excavation , trenching and backfilling for pipe, culverts, 431
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 8 utility systems, and other subsurface pipes is specified in Section 31 23 16 – Utility Trenching of the City Standard Specifications.
B. Excavate subsoil and topsoil from areas designated. Strip topsoil to full depth of topsoil in designated areas.
C. Stockpile excavated material meeting requirements for subsoil fill materials and topsoil materials approved by the Project Manager.
D. If practicable and unless processing of material is required, haul selected material directly from the excavation to its final position in the roadway prism and compact it in place.
E. Excavate to the described or authorized grade. If the Contractor over excavates, backfill with an authorized material and compact it at the Contractor’s own expense.
F. Do not excavate wet subsoil unless directed by the Project Manager.
G. The temporary slope of cut surfaces shall be no steeper than is safe for the intended use, and shall not be more than one-unit vertical in two units horizontal (50-percent slope) unless approved by the Project Manag er or appurtenant geotechnical report.
H. Archaeological Resources: Contractor shall conform to Section 14 , “Environmental Stewardship ”, of the State Standard Specifications. If archaeological resources are discovered within or near construction limits, do not disturb the resources and immediately:
1. Stop all work within a 60-foot radius of the discovery
2. Secure the area
3. Notify the Project Manager.
I. City will investigate the discovery. Do not move archaeological resources or take them from the job site. Do not res ume work within the radius of discovery until authorized.
J. Environmentally Sensitive Areas (ESA): If an ESA is shown on the Drawings, the boundaries are approximate. Do not enter an ESA unless authorized. If an ESA is breached, immediately:
1. Stop all the work within 60 feet of the ESA boundary
2. Secure the area
3. Notify the Project Manager
If an ESA is damaged, the Project Manager determines the necessary remediation and the party to perform the work. The City deducts the cost for this work from the Contractor bid price.
432
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 9 K. Notify the Project Manager when buried man-made objects are encountered in an excavation as part of the excavation work and wait for direction from Project Manager unless shown on the plans for removal . All surplus material shall be disposed offsite.
L. Remove excess excavated materials, subsoil and topsoil not intended for reuse, from site.
M. Remove excavated materials not meeting requirements for subsoil materials and topsoil materials from site.
N. When hauling is done over highways or City streets, and when directed by the Project Manager the loads shall be trimmed and all material removed from shelf areas of vehicles in order to eliminate spilling of material. If directed by the Project Manager, the loads shall be watered down or covered after trimming to eliminate dust.
O. Excavation shall include the satisfactory removal and disposition of all materials not classified as rock excavation.
P. Earth and rock, regardless of character and subsurface conditi ons, shall be excavated to the lines and grades as established by the plans.
Q. All existing materials that are designated to be salvaged shall be removed, cleaned and hauled to the City Corporation Yard, unloaded and stockpiled, by the Contractor unless otherwise directed by the Project Manager.
R. Existing pipes to be abandoned shall be filled with slurry, minimum of thirty (30) feet from either ends of the pipe and capped with concrete at the ends.
S. Existing structures, pavement slabs, and structural sections t o be abandoned shall be demolished to an elevation three (3) feet below finished grade, unless specified otherwise on the Drawings. The bottom (if any remains) shall be broken thoroughly to prevent entrapment of water and all voids backfilled with suitable backfill.
T. Operations shall be conducted in such a manner that existing street, facilities, utilities, railroad tracks and other non-street facilities which are to remain in place will not be damaged.
U. The Contractor, at his expense, shall furnish and ins tall-sheet piling, cribbing, bulkheads, shores or whatever means may be necessary to adequately support material carrying such facilities, or to support the facilities themselves, and shall maintain such supports until they are no longer needed. Temporary pavements, facilities, utilities and installations shall also be protected until they are no longer required. When temporary supports and other protective means are no longer 433
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 10 required, they shall become the property of the Contractor and shall be removed and disposed of from the job site
V. Prior to placing import fill material, all areas to receive fill shall be scarified and compacted. Unless otherwise stated in the appurtenant Geotechnical report, the area shall be scarified to a minimum of eight (8) inches, material shall be moisture conditioned by wetting or drying to optimum moisture content, and compacted.
3.4 ROCK EXCAVATION
A. Rock excavation shall include excavating, grading, and disposing of materials classified as rock and shall include the satisfactory r emoval and disposition of rock 1/2 cubic yard or more in volume.
B. No blasting is allowed.
3.5 GRADING
A. Grading shall consist of placing fill materials on site to contours and elevations with select fill or import fill materials.
B. Place fill material in continuous layers of maximum lifts of 8 inches (0.67 feet) and compact in accordance with schedule shown in this section , unless otherwise shown on the appurtenant Geotechnical Report.
C. Maintain optimum moisture content of fill materials to attain required compaction density.
D. Construct slopes to the lines and grades shown on the Drawings.
E. Slope grade away from the building minimum 2% slope for a minimum distance of 10 feet, unless noted otherwise.
F. Make grade changes gradual. Blend slopes into level areas.
G. Round the tops of excavation slopes and ends of excavation.
H. Maintain completed slopes. Repair any slopes damaged by erosion.
I. Repair or replace items indicated to remain that are damaged by excavation or filling.
J. Identify any site low points which need positive drainage and make adjustments with approval from Project Manager prior to pouring concrete. 434
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 11 K. Protection of existing slopes using erosion control measures as required in Section 01 57 23 – Storm Water Pollution Prevention.
3.6 TOLERANCES
A. Section 01 45 00 – Quality Control: Tolerances.
B. Immediately before placing subsequent layers of material, prepare the grading plane such that the grading plane:
1. Does not vary more than 0.05 foot above or below the grade established by the Engineer where Hot Mix Asphalt (HMA) or aggregate base are to be placed.
2. Does not extend above the grade established by the Engineer where concrete base or pavement is to be placed.
3. Beneath structural approach slabs or the thickened portion of sleeper slabs do not extend above the grade established by the Engineer.
4. At any point is within 0.05 foot above the grade established by the Engineer if the material to be placed on the grading plane is paid by the cubic yard.
3.7 COMPACTION
A. Relative compaction specifications apply to material whether in an excavation or an embankment.
B. The moisture content of material to be compacted to at least 95 percent must be such that the specified relative compaction is attained, unless specified otherwise in the appurtenant Geotechnical Report.
C. Compact earthwork to a relative compaction of at least 95 percent for at least a depth of:
1. 0.5 foot below the grading plane for the width between the outer edges of shoulders
2. 2.5 feet below the finished grade for the width of the traveled way including any parking lots or other vehicular areas; to extend plus two (2) feet on each side.
D. All fill material shall be compacted to at least 90 percent of maximum density as determined by ASTM D1557, Modified Proctor, beyond the depth specified above in 3.7.C, unless otherwise shown in the appurtenant Geotechnical Report.
3.8 STOCKPILING
A. Stockpile materials on site at locations indicated on the plans or as designated by Project Manager.
435
City of Pittsburg, California December 2022
CLEARING & GRUBBING, EXCAVATION, AND EARTHWORK 31 05 13 - 12 B. Stockpile in sufficient quantities to meet Project schedule and requirements.
C. Separate differing materials with dividers or stockpile apart to prevent mixing.
D. Prevent intermixing of soil types or contamination.
E. Direct surface water away from stockpile site to prevent erosion or deterioration of materials.
F. Stockpile unsuitable or hazardous materials on impervious material and cover to prevent erosion and leaching, until disposed of. Dispose unsuitable or hazardous material within 48 hours of removal.
3.9 STOCKPILE CLEANUP
A. Remove stockpile, leave area in clean and neat condition. Grade site surface to prevent free standing surface water.
B. Leave unused materials in neat, compact stockpile.
C. When borrow area is indicated, leave area in clean and neat condition. Grade site surface to prevent free standing surface water.
3.10 PROTECTION
A. Prevent displacement or loose soil from falling into excavation; ma intain soil stability.
B. Protect bottom of excavations and soil adjacent to and beneath foundation from freezing.
C. Protect structures, utilities, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth operations.
END OF SECTION 31 05 13
436
City of Pittsburg, California December 2022
SUBGRADE ENHANCEMENT GEOSYNTHETIC 31 05 14 - 1
SECTION 31 05 14 – SUBGRADE ENHANCEMENT GEOSYNTHETIC
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Subgrade Enhancement Geogrid
2. Subgrade Enhancement Geotextile.
B. Related Sections:
1. Section 31 05 13 – Clearing & Grubbing, Excavation, and Earthwork
2. Project Geotechnical report (if available).
1.2 UNIT PRICES - MEASUREMENT AND PAYMENT
A. Subgrade Enhancement Geogrid/Geotextile
1. Basis of Measurement: By square yard measured parallel to the surface, not including the additional quantity used for overlaps.
2. Basis of Payment: Includes furnishing, storing, maintaining, placing the subgrade enhancement geogrid /geotextile between the subgrade and the pavement structure or as shown on the Drawings.
1.3 REFERENCES
A. State Standard Specifications:
1. Section 19-10 – Subgrade Enhancement Geosynthetic
2. Section 96 - Geosynthetics
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Samples: Submit samples of the geogrid when requested by the Project Manager.
C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.
437
City of Pittsburg, California December 2022
SUBGRADE ENHANCEMENT GEOSYNTHETIC 31 05 14 - 2
PART 2 - PRODUCTS
2.1 SUBGRADE ENHANCEMENT GEOGRID
A. Subgrade enhancement geogrid must be biaxial geogrid. Biaxial georgid must conform to Section 96-1.02P- Biaxial Georgid.
B. Biaxial geogrid must be a punched and drawn polypropylene material formed into an integrally formed biaxial grid.
2.2 SUBGRADE ENHANCEMENT GEOTEXTILE
A. Subgrade enhancement geotextile must be Class B2 as specified in Section 96-
1.02O- Subgrade Enhancement geotextile, unless otherwise shown on the Drawings.
B. A polyester geotextile must not be used for subgrade enhancement geot extile within four (4) inches of recycled concrete.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Before placing subgrade enhancement geogrid/geotextile, remove loose or extraneous material and sharp objects that may come in contact with the geosynthetic material.
B. Place the geosynthetic:
1. Under the manufacturer’s instructions
2. Longitudinally along the roadway alignment
3. Without wrinkles.
C. Overlap the adjacent edges of the rolls at least two (2) feet. Overlap the ends of rolls at least two (2) feet in the direction of spread cover ing the subgrade enhancement geosynthetic. Geogrid or Geotextile should be extended all the way to the gutter lip.
D. Fold or cut the geosynthetic to conform to curves. Overlap any cut material at least two (2) feet. Hold the overlap in place with staples, pi ns, or small piles of material placed on the subgrade enhancement material.
E. Make any repairs to the geogrid or geotextile material by placing a new piece of material over the damaged areas with at least three (3) feet of overlap from the edges of the damaged area.
438
City of Pittsburg, California December 2022
SUBGRADE ENHANCEMENT GEOSYNTHETIC 31 05 14 - 3
F. Compact the aggregate base with either a
1. Smooth wheeled roller with no vibrations
2. Rubber tire roller
G. Do not stockpile material on the geosynthetic.
H. Do not place any geosynthetic material that cannot be covered on the same day.
I. Do not operate equip ment or vehicles directly on geosynthetic material unless one of the following conditions are met:
1. Vehicles and equipment are
a. Equipped with rubber tires
b. Operated under 10 miles per hour
c. Operated in a manner to avoid sudden braking and sharp turns
2. At least 0.35 feet of aggregate base had been placed, spread, and compacted on the geogrid.
J. Do not compact the subgrade geosynthetic material with a sheepsfoot or other non-smooth roller.
K. Do not turn vehicles on material placed directly over geosynthetic material.
L. Before operating equipment on areas where geosynthetic material has been placed, spread and compact 0.5 feet of material on the geosynthetic.
END OF SECTION 31 05 13
439
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 1
SECTION 31 23 16 – UTILITY TRENCHING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The work of this Section includes all saw cutting, utility trenching, earthwork and removal of surface material as required for construction of the utility trenches. Such earthwork shall include, but may not necessarily be limited to, the loosening, removing, loading, transporting, depositing, and compacting in its final location of all materials wet and dry, as required for the purposes of completing the work, whic h shall include, but not necessarily be limited to, the furnishing, placing, and removing of sheeting, shoring and bracing necessary to safely support the sides of all excavations; all pumping, ditching, draining and other required measures for the removal or exclusion of water from the excavation; the supporting of structures above and below the ground; all backfilling around structures and all backfilling of trenches and pits; restoration of surface, pavement markings, the disposal of excess excavated ma terials; borrow of materials to make up deficiencies for fills; and all other incidental earthwork.
2. All utility lines not owned by the City shall be designed and constructed in accordance with the rules and regulations of serving utilities. All utilities shall be installed prior to placement of the wearing surface of the street. It shall be the responsibility of the Contractor to conform to these provisions.
3. All broken concrete, pavement, base and other material and unsuitable and surplus excavated material shall be removed, hauled off the site and disposed of by the Contractor at a location obtained by the Contractor and approved by the Project Manager all at no additional cost to the City; said costs and fees shall be considered as included in the prices bid.
4. All materials regardless of character and subsurface conditions shall be excavated to the depths indicated or specified. During excavation, suitable trench material that will be used as backfill shall be piled in an orderly manner a sufficient distance from the banks of the trench to avoid overloading and to prevent slides or cave -ins, or shall be separately stockpiled. All excavated materials not required or unsuitable for backfill shall be disposed of outside the Right -of-Way as specified in Section 5 -
1.20B(4) “Contractor–Property Owner Agreement” of the State Standard Specifications
440
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 2
5. All hazardous materials shall be handled in accord ance with all regulatory agency requirements and as specified in Section 14 -11.03, “Hazardous Waste Management”, of the State Standard Specifications. Contractor- generated hazardous waste shall be disposed of outside the Right -of-Way as specified in Sectio n 14 -11.06B, “Contractor -Generated Contaminated Soil”, of the State Standard Specifications. Within 5 business days of transporting hazardous waste, submit documentation of proper disposal from the receiving landfill.
6. Where there is not a specific bid item for Hazardous Waste Management, full compensation for furnishing all labor, materials, tool s, equipment, and incidentals, and for doing all the work involved in handling of the hazardous waste shall be considered included in the price paid for various items of work and no separate compensation will be allowed therefor.
7. All surface openings shall be saw cut using a power -driven saw with a diamond blade to provide a smooth joint for both concrete and bituminous street and sidewalk surfaces. All the trenches shall be “T” cut trenches as per City Standard details.
8. Impact pavement breakers (drop hamme rs, stampers, jack hammers ) are not permissible.
9. The requirements of Section 7 -1.02K(6) and 7-1.02L(2) of State Standard Specifications concerning Trench Safety and Antitrust Claims shall be complied with in addition to the requirements of Article 6 and Section 1503 of the State of California Construction Safety Orders.
10. Grading shall be done as may be necessary to prevent surface water from flowing into trenches or other excavations. Unless otherwise indicated, excavation shall be by open cut except that s hort sections of a trench may be tunneled if the pipe, cable, or duct can be safely and properly installed, backfilled with Controlled Low Strength Materials not tamped in such tunnel sections.
B. Related Sections:
1. Section 01 33 00 - Submittal Procedures
2. Section 02 41 00 - Demolition
3. Section 31 05 13 – Clearing & Grubbing, Excavation, and Earthwork
4. Section 32 11 23 - Aggregate Base Courses
5. Section 32 12 16 - Asphalt Paving
6. Section 32 13 13 - Concrete Surface Improvements
7. Section 33 05 13 - Manholes and Structures
8. Section 33 11 13 - Water Distribution Piping
9. Section 33 12 13 – Water Service Connections
10. Section 33 31 13 - Sanitary Sewer Piping
11. Section 33 41 13 - Storm Drainage Piping
441
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 3
C. California Codes:
1. Titles 17 and 22 California Code of Regulations - Chapter 16 – California Waterworks Standards
2. Water Main Separation Criteria: Chapter 16 - California Waterworks Standards Article 6 - §64572
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT (For City CIP Projects only) A. Utility Trenching and Earthwork:
1. Measurement: Utility Trenching is typically not a measured item. However, when a bid item is included for Utility Trenching or Joint Utilities Trenching, measurement, unless otherwise designated, shall be the number of linear feet of longitudinal trench centerline, measured along the design slope of the trench bottom, to the nearest foot to the conduit end, pay line, or outside face of connecting structure as designated. Any trenching or excavation for connecting structures shall be included in the measurement for the structure.
2. Payment: Unless there is a separate bid item, f ull compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in Utility Trenching, complete in place including saw cut, excavating to required elevations, protecting the excavation in compliance with Cal/ OSHA, removing and disposing of excavated materials, removing and disposing of any asphalt paving mats or fabrics, stockpiling excavated materials, dewatering, bedding, backfill, removing trench sheathing, shoring and bracing when no longer required, restoration and disposing of materials outside the Right-of-Way shall be considered as included in various items of work most closely related to and no separate compensation will be allowed therefor . Payment is not made for over excavated work nor for replacement materials , unless approved in writing by the Project Manager.
1.3 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO T180 - Standard Specification for Moisture -Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. ASTM International:
1. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft -lbf/ft3 (600 kN - m/m3).
442
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 4
2. ASTM D1556 - Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method.
3. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft -lbf/ft3 (2,700 kN - m/m3).
4. ASTM D1633 - Standard Test Methods for Compressive Strength of Molded Soil-Cement Cylinders.
5. ASTM D2167 - Standard Test Method for Density and Unit Weight of Soil in Place by the Rubber Balloon Method.
6. ASTM D2419 - Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate.
7. ASTM D2487 - Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System).
8. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).
9. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).
10. ASTM D3776 - Standard Test Methods for Mass Per Unit Area (Weight) of Fabric.
11. ASTM D3786 - Standard Test Method for Bursting Strength of Textile Fabrics -Diaphragm Bursting Strength Tester Method
12. ASTM D4253 - Standard Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table
13. ASTM D4254 - Standard Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density
14. ASTM D4318 - Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
15. ASTM D4491 - Standard Test Methods for Water Permeability of Geotextiles by Permittivity
16. ASTM D4632 - Standard Test Method for Grab Breaking Load and Elongation of Geotextiles
17. ASTM D4751 - Standard Test Method for Determining Apparent Opening Size of a Geotextile
18. Cal/OSHA - Division of Occupational Safety and Health (DOSH) Administration
C. State Codes;
a. California Labor Code
b. Construction Safety Orders of the State of California D. State of California (Caltrans) - State Standard Specifications:
a. Section 25 - Aggregate Subbases
b. Section 26 - Aggregate Bases
443
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 5
1.4 DEFINITIONS
A. Utility: Any buried pipe, duct, conduit, or cable.
B. Utility Structure: Maintenance holes, inlets, catch basins or vaults
1.5 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Excavation Protection Plan: Contractor’s attention is directed to the provisions in Section 6705 of the California Labor Code. Prior to beginning any trench or structure excavation five (5) feet or more in depth, the Contractor shall submit to the Project Manager for review for compliance with Section 6705 of the Contractor’s detailed excavation protection plan showing the design of all shoring, bracing, sloping of the sides of excavation, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trenches or structure excavations.
C. Product Data: Contractor shall submit data for various types of backfill, trenching and shoring plans, and geotextile fabric. Contractor shall submit la boratory results indicating all soils and backfill material are not hazardous.
D. Samples: Contractor shall submit fill samples, in air-tight containers for each type of fill to testing laboratory.
E. Materials Source: Contractor shall s ubmit name of imported fill materials suppliers.
F. Manufacturer's Certificate: Certificates of Compliance shall be provided for all products and materials proposed to be used under this Section.
G. Contractor shall submit a Safety Certification
1.6 QUALITY ASSURANCE
A. Capital Improvement Projects (CIP):
1. All soil and backfill testing shall be done by a testing laboratory of the City’s choice at the City’s expense except as otherwise specified in Paragraph 1.6 B. below. The Contractor shall notify the Project Manager at least 48 hours prior to performing any utility excavation and before beginning of backfill materials.
2. Where soil material is required to be compacted to a percentage of maximum density the maximum density at optimum moisture content will be determined in accordance with ASTM D 1557. Where cohesionless, free draining soil material is required to be densified to a percentage of relative 444
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 6
density the calculation of relative density will be determined in accordance with ASTM D 4253 and D 4254. Field density in -place tests will be performed in accordance wi th ASTM D 29 22, or by such other means acceptable to the Project Manager.
3. In case the first test and one re -test of the fill or backfill show non - compliance with the requirements , the Contractor shall accomplish such remedy as may b e required to insure compliance. Subsequent re-testing after the first re -test to show compliance shall be at the C ontractor’s expense.
B. All Other Projects including but not limited to permit projects, utility company projects, development and redevelopment projects:
1. All soil and backfill te sting shall be by the Permitee/Developer/Utility Company’s Geotechnical Engineer of Record and shall submit all testing information to the City.
2. Maintain one copy of the Construction D ocuments and City Standard Details and Specifications on site.
1.7 QUALIFICATIONS
A. If the Contractor’s excavation protection plan varies from the shoring system standards established in the Construction Safety Orders of the State of California, such alternative system plan shall be prepared, stamped and signed by a Civil or Structural Engineer licensed in the State of California at the Contractor’s expense.
1.8 FIELD MEASUREMENTS
A. Contractor shall verify field measurements prior to fabrication.
1.9 COORDINATION
A. Verify Work associ ated with lower elevation utilities is complete before placing higher elevation utilities.
PART 2 - PRODUCTS
2.1 SUITABLE FILL MATERIALS
A. Suitable backfill shall be a selected or processed clean, fine earth, rock, or sand, free from objectionable materials, vegetation, or other deleterious substances.
B. All import material from a source outside the project limits for use as backfill shall be clean soil, not hazardous, free from organic material, trash, debris, rubbish, 445
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 7
broken Portland cement concrete, bituminous materials or other objectionable materials. Whenever the Contractor elects to use imported material for backfill, it shall be delivered not less than 10 days prior to the intended use and a sample of the material shall be submitted to the Project Manager for review. The sample shall have a minimum dry weight of 100 pounds and shall be clearly identified as to source, including street address and community of origin. The Project Manager will determine the suitability, the minimum relative compaction to be attained, and the placement method. If the backfill material is found not suitable, the Contractor shall remove material from the site and dispose of at no additional cost to the City.
C. Should the imported material not be substantially the same as the approved sample, it shall not be used for backfill and shall be removed from the job site at the Contractor's expense.
D. The densification method for imported material authorized by the Project Manager will be dependent upon its composition, the composition of the in-place soil at the point of placement, once the relative compaction to be obtained.
E. The following are the types of backfill materials:
1. Sand shall be a material with 100 percent passing a 3/8” sieve, at least 90 percent passing a No. 4 sieve, and a sand equivalent value not less than
30. 2. Class 2 Aggregate Base shall be crushed rock aggregate base material meeting the requirements of Section 26, “Aggregate Bases”, for 3/4" maximum aggregate gra dation, of the State Standard Specifications.
Recycled Aggregate Base is an acceptable backfill material.
3. Controlled Low Strength Materials (CLSM) shall be fluid workable mixture of cement, pozzolan, aggregate and water mixed in accordance with ASTM C94. Cement shall be Type II Cement and comply with ASTM C150. Pozzolan shall be added to improve the flowability and shall be Type F in accordance with the requirements of ASTM C618. Water must be free of oil, salts, and other impurities that adversely affect the backfill. Aggregate must consist of well graded mixture of crushed rock, soil, or sand with a maximum aggregate size of 1/2 -inch. 100percent of the aggregate shall pass the 3/4" sieve and not more than 30-percent retained on the 3/8” sieve and not more than 12 percent shall pass the No. 200 sieve. Air entraining admixtures shall be added to improve the workability and shall in accordance with the requirements of ASTM C260. Density of CLSM shall be between 120 pounds p er cubic feet to 135 pounds per cubic feet.
Minimum 28-day compressive strength for CLSM shall be between 50psi minimum to 100psi for depths 20 feet or less in height of cover. For depths greater than 10 feet in height, CLSM mix shall have a minimum 28 -day compressive strength of 100 psi.
446
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 8
4. Native material shall be material obtained from on -site excavations, provided the materials are not classified as unsuitable. Native materials shall be free of stones, lumps, rubbish, debris, organic material, broken concrete or bituminous surfacing over 4 inches in diameter, objectionable material, vegetation, and deleterious substances.
5. Class 2 Permeable Material shall be hard, durable, crushed stone, or gravel, and free from slaking or decomposition under action o f alternate wetting or drying, uniformly graded, and shall meet the requirements of Section 68-2.02F for Class 2 “Permeable Material”, of the State Standard Specifications.
6. Topsoil shall be material which has been obtained at the site or may be imported and shall meet the requirements of Section 32 90 00 - Landscape Work. Removal of topsoil shall be done after the area has been stripped of vegetation and debris as specified.
2.2 UNSUITABLE BACKFILL MATERIALS
A. Any material determined to be hazardous is defined as unsuitable material.
B. Unsuitable soils for backfill material shall include soft, spongy, unstable or other similar soils which, when classified under ASTM D 2487, fall in the classifications of Pt, OH, or OL. Types CH and MH soils will be permitted in unimproved areas only where required compaction and stability can be demonstrated. In addition, any soil which cannot be compacted sufficiently to achieve the percentage of maximum density specified for the intended use, shall be classified as unsuitable material.
C. Washed, smooth rock (pea gravel) is classified as unsuitable material.
2.3 FILTER FABRIC
A. Filter Fabric shall be permeable, non -woven synthetic fabric meeting the requirements of Section 96 -1.02B,” Filter Fabric” of the State Standard Specifications. Filter fabr ic shall have minimum Grab breaking load in each direction of 157 pounds, a minimum puncture strength of 310 pounds, apparent opening size between 40 and 70.
2.4 TEMPORARY STEEL PLATES
A. When approved by the Project Manager , the Contractor may use steel plate bridging in-lieu of backfill and temporary asphalt where the roadway surface is to be opened to traffic. All steel plates shall be without deformation. Inspectors shall 447
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 9
determine the trueness of steel plates by using a straight edge and shall reject any plate that is permanently deformed.
B. Trench plates shall be coated with Antiskid type surface meeting State Standard Specifications of a nominal Coefficient of friction of 0.35 in accordance with California Test Method 342 (Appendix H).
C. The following table shows the advisory minimal thickness of steel plate bridging required for a given trench width (A -36 grade steel, designed for HS20 -44 truck loading per Caltrans Bridge Design Specifications Manual).
Trench Width Minimum Steel Plate Thickness (inches) 10 inches 1/2 inch
1 feet 11 inches 3/4 inch
2 feet 7 inches 7/8 inch
3 feet 5 inches 1 inch
4 feet 3 inches 1-3/4 inch
NOTE: For trench width spans gre ater than 4 feet 3 inches, a structural design shall be prepared, signed, and stamped by a California Registered Civil Engineer.
D. A Rough Road signs (W8-8) with black lettering on an orange background shall be used in advance of steel plate bridging.
PART 3 - EXECUTION
3.1 DEFINITIONS - PIPE ZONE, BEDDING, TRENCH & FINAL ZONE A. Pipe Zone: Pipe Zone is defined as the vertical trench cross-section between the trench subgrade, which is 0.4 times the outside diameter of the pipe in inches below the bottom surface of the pipe or 4” minimum whichever is greater, and 12 inches above the top surface of the pipe.
B. Bedding: Bedding is defined as that portion of the Pipe Zone between the trench subgrade, which is 0.4 times the outside diameter of the pipe in inches below the bottom surface of the pipe or 4” minimum whichever is greater and a level line from the bottom of the pipe.
C. Trench Zone: The Trench Zone is defined as the vertical trench cross -section between top of Pipe Zone and 36” below finish paved surface. In unpaved areas, the Trench Zone shall be the vertical cross-section between the top of Pipe Zone and 24 inches below finished unpaved or landscape surface. 448
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 10
D. Final Zone: The Final Zone is defined as the upper 36 inches of vertical cross- section below the finished paved surface. In unpaved or landscaped areas, the Final Zone is the upper 24 inches of vertical cross -section below the finished surface.
E. Pavement Section: The Pavement Section is defined as the engineered layers of pavement and base conforming to the hot mix asphalt pavement or concrete pavement and aggregate base thickness as shown on the Plans.
F. Backfill: Backfill is considered to be the material used to fill the portion of a trench between the pipe Bedding and the roadway subgrade or finish surface in non - roadway areas
G. Trench Plugs: Trench plugs are temporary barriers placed within an open trench excavation in order to minimize the volume and velocity of trench water flow at the base of slopes and to reduce erosion in the trench, preventing the trench from becoming a subsurface draina ge path. These trench plugs may consist of unexcavated portions of the trench, compacted subsoil, sandbags, or some functional equivalent.
3.2 PIPE ZONE BACKFILL MATERIALS
A. Bedding as defined in this section shall be Sand or Class 2 Aggregate Base.
B. Pipe Zone backfill, excluding bedding as defined in this section shall be
1. Sand for plastic pipe
2. Sand or Class 2 Aggregate Base for ductile iron pipe, vitrified clay pipe and reinforced concrete pipe.
C. For dry utility and/or joint trench, Pipe Zone backfill shall conform to latest Pacific Gas and Electric Company (PG&E) Greenbook’s Engineering Material Specification No. 4123 - Backfill Sand or meeting the utility owner’s specifications.
D. Trench plugs shall be provided at minimum intervals of 200 feet where pipelines are installed on grades exceeding 4 percent, and where backfill materials have gradation less than 10 percent passing a No. 4 sieve.
E. Unless otherwise specified Bedding and b ackfill around sub-drainage systems shall be minimum of 12 inches of Class 2 Permeable Material as specified in Section 68-2.02F(3) of the State Standard Specifications.
3.3 TRENCH ZONE BACKFILL MATERIALS
A. Trench Zone backfill as defined in this section shall be Class 2 Aggregate Base in paved areas.
449
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 11
B. Native backfill material shall be used in unpaved or landscape areas.
3.4 FINAL ZONE BACKFILL MATERIALS
A. Final Zone backfill as defined in this section shall be
1. Native backfill in unpaved areas
2. Native backfill with 6 inches thick minimum Top Soil material in la ndscape areas.
3. Class 2 Aggregate Base in paved areas below the Pavement Section.
3.5 TRENCH WIDTH & LENGTH
A. Minimum Trench width shall be as follows:
Utility Pipe Outside Diameter (O.D.) Minimum Trench Width (inches) (inches)
For Pipe Sizes under 12 inches Pipe O.D. + 12 inches For Pipe Sizes between 12 inches to 48 inches Pipe O.D. + 24 inches For Pipe Sizes above 48 inches Pipe O.D. + 48 inches For Dry Utilities (electrical, telephone, cable, street light and traffic s ignal conduits), the trench width shall be 18” minimum.
B. Maximum Length of Open Trench: Except by permission of the Project Manager, the maximum length of open trench where prefabricated pipe is used shall be the distance necessary to accommodate the amount of pipe installed in a single day and shall not exceed 300 feet . The distance is the collective length at any location, including open excavation, pipe laying and appurtenant construction and backfill which has not been temporarily re-surfaced.
C. Except by permission of the Project Manager, the maximum length of open trench in any one location where concrete structures are cast in place will be that which is necessary to permit uninterrupted progress.
3.6 PREPARATION
A. Call Local Utility Line Information service at USA North 811 not less than three working days before performing Work.
1. Request underground utilities to be located and marked within and surrounding construction areas.
450
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 12
B. Contractor’s Licensed Land Surveyor shall provide all construction surveying and staking prior to beginning any trenching and excavation.
C. Protect bench marks, street monuments, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.
D. Contractor shall m aintain and prot ect above and below grade utilities unless otherwise noted.
E. Establish temporary traffic control per Contractor’s approved traffic control plans when trenching is performed in public right-of-way. Relocate controls as required during progress of Work.
3.7 SHEETING AND SHORING
A. Sheet, shore, and brace excavations more than 5 feet deep to prevent danger to persons, structures and adjacent properties and to prevent caving, erosion, and loss of surrounding subsoil.
B. All sheeting, shoring and bracing shall conform to Cal/OSHA.
C. Support trenches more than 5 feet deep excavated through unstable, loose, or soft material. Provide sheeting, shoring, bracing, or other protection to maintain stability of excavation.
D. Design sheeting and shoring to be removed at completion of excavation work.
E. Repair damage caused by failure of the sheeting, shoring, or bracing and for settlement of filled excavations or adjacent soil.
F. Repair damage to new and existing Work from settlement, water or earth pressure or other causes resulting from inadequate sheeting, shoring, or bracing.
G. Access to Trenches - A stairway, ladder, ramp or other safe means of egress shall be located in trench excavations that are 4 feet or more in depth so as to require no more than 25 feet of lateral travel for the employees, the Contractor, and any other personnel.
H. Bracing Excavations - The manner of bracing excavations shall be as set forth in the rules, orders and regulations of the Division of Industrial Safety of the State at California.
3.8 TEMPORARY ACCESSIBLE PEDESTRIAN BRIDGES
A. Temporary Accessible Pedestrian bridges of approved construction not less than four feet in width in compliance with ADA , and provided with hand rails and supports of dressed lumber, shall be installed over trenches at all crosswalk 451
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 13
intersections, and at such other points where traffic conditions make it advisable.
Substantially constructed bridges, adequate for handling all vehicular traffic, shall be installed over any trench or other excavation in a street intersection, whenever such excavation is in excess of half the width of the street crossing. Adequate bridges shall be provided to make possible the safe and full use of all driveways or roadways used to move vehicles from the public street onto private property.
B. All bridges required to be installed shall be maintained in place as long as the condition of the work requi res their use for the safety and convenience of the public. Removal or relocation of these temporary bridges shall be at the Contractor's own discretion and risk.
3.9 TRENCHING AND EXCAVATION
A. All excavations for utilities, pipelines and Minor Structures shall be open cut trenches, unless otherwise shown.
B. Do not advance open trench more than 200 feet ahead of installed pipe.
C. Cut trenches to widths per Standard Specifications or as indicated on the Drawings and sufficiently wide to enable installation and allow inspection.
Remove water or materials that interfere with Work.
D. Excavate trenches to depth per Standard Specifications or as indicated on Drawings. Provide uniform and continuous bearing and support for bedding material and utility pipes.
E. Do not interfere with 45-degree bearing splay of foundations.
F. When Project conditions permit, slope side walls of excavation per Cal/OSHA.
When side walls cannot be sloped, provide sheeting and shoring to protect excavation as specified in this section.
G. Excavation and other work under or adjacent to existing pipe lines, cables, conduit runs or structures of any kind, shall be prosecuted in such a manner as not to interfere with the safe operation and use of such installations. Should any damage be incurred to existing facilities during the Contractor's operations, the Contractor shall immediately notify the proper owners or authorities, and shall arrange for the immediate repair of same at the Contractor's own expense.
H. Excavations for appurtenant structures , such as but not limited to maintenance holes, transition structures, junction structures, vaults, valve boxes, catch basins, thrust blocks, and boring pits shall, for the purpose of shoring and bracing, be deemed to be in the category of trench excavation.
I. Excavation shall include the removal of all water and materials of any nature which interfere with the construction work. Removal of ground water to a level 452
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 14
below the structure sub-grade will be necessary unless specified otherwise. The water removed during excavation shall not be directed to storm drain system. The contractor shall apply to Delta Diablo for a Discharge Permit to dispose the water encountered during excavations into the sanitary sewer system.
J. Should the Contractor elect to tunnel or jac k any portion, he shall first obtain approval from the Project Manager. Payment for such work will be made as though the originally specified method of construction has been used.
K. Trenching, tunneling, boring and jacking shall comply with the applicable provisions of the State Standard Specifications, these specifications and the plans. All work shall comply with the applicable Federal, State and local laws, regulations, codes and ordinances, and in addition, shall meet the respective utility agencies req uirements for joint trench construction for installation of conduits, including, but not limited to, safety, depth, size, type, connection and other regulations and shall be considered as included in the various contract items of work and no additional compensation shall be made therefore.
L. Pipe will be carefully inspected in the field before and after laying. If any cause for rejection is discovered in a pipe after it has been laid, it shall be subject to rejection. Any corrective work shall be approved b y the Project Manager and shall be at no cost to the City.
M. When connections are to be made to any existing pipe, conduit, or other appurtenances, the actual elevation or position of which cannot be determined without excavation, the Contractor shall excava te for, and expose, the existing improvement before laying any pipe or conduit. The Project Manager shall be given the opportunity to inspect the existing pipe or conduit before connection is made.
N. Gravity flow pipe shall be laid downstream to upstream with the socket or collar ends of the pipe upgrade unless authorized by the Project Manager.
O. Concrete pipe with elliptical reinforcement shall be laid with the minor axis of the reinforcement cage in a vertical position.
P. Any adjustments in line or grade of not more than 0.1 feet up or down which may be necessary to accomplish the intent of the plans shall be considered as included in the various contract items of work and no additional compensation will be made therefore.
Q. Locations of existing underground utilities and structures, insofar as they ore known from information furnished by the respective utility companies and agencies, have been shown on the plans. The City assumes no responsibility for the accuracy or completeness of said data, whi ch is offered solely for the convenience of the Contractor it shall be the Contractor’ s responsibility to verify the location of these obstructions, and to locate any other underground utilities or structures, which might interfere with the Contractor’s operations. 453
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 15
R. If soft spongy, unstable or other similar material is encountered upon which the bedding material or pipe is to be placed, this unsuitable material shall be removed to a depth ordered by the Project Manager and replaced with bedding material suitably densified. Additional bedding so ordered, over the amount required by the plans or specifications, will be paid for as provided in the Proposal or the Technical Specifications. If the necessity for such additional bedding material has been caused by an act or failure to act on the part of the Contractor, or is required for the control of ground water, the Contractor shall bear the expense of the additional excavation and bedding.
S. Where pipe culverts are to be installed in new embankment, it shall fir st be constructed to the required height as shown on the plans, and for a distance each side of the culvert location of not less than five (5) times the diameter of the cuIvert, after which the trench shall be excavated with sides as nearly vertical as soil conditions will permit and culvert installed
T. For excavations in landscape areas , all damaged irrigation systems, including irrigation piping and electrical wiring shall be repaired and restored to the original condition on the same day they are damaged. All landscape surface areas shall be restored to its original condition unless specified otherwise.
U. No tree roots over 1.5 inches in diameter shall be cut without the authorization from the Project Manager or City’s Arborist. If existing roots ove r 1 inch in diameter are cut during the course of work, the cut faces shall be thoroughly coated with emulsified asphalt made especially for use on cut or damaged plant tissues. All exposed roots shall be covered with wet burlap to prevent them from drying out.
V. Trim excavation. Hand trim for bell and spigot pipe joints. Remove loose matter.
W. Correct over excavated areas with compacted backfill as specified for authorized excavation as directed by Project Manager.
X. Remove excess subsoil not intended for reuse, from site. The legal disposal of excess materials shall be the responsibility of the Contractor.
Y. Use of explosives and blasting material will not be permitted.
Z. Stockpile excavated material in area designated on site as shown on the Contractor’s approved Staging Plans.
AA. In areas of high vehicular or pedestrian volumes, the Project Manager may order the immediate removal of excavated material and that sidewalks and gutters be kept clean at all times.
BB. The Contractor may transport or backhaul material to be used as backfill material from any portion of a project to any other portion or line of the same project, or from any project being constructed under one contract to any other project being 454
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 16
constructed under that same contract. Such transported material sha ll be clean soil, free from organic material, trash, debris, rubbish, or other objectionable substances except that broken Portland cement concrete or bituminous type paving allowable for the type of backfill specified may be permitted
3.10 OVER-EXACAVATION
A. When ordered by the Project Manager, whether or not indicated in the project plans and specifications, trenches shall be over -excavated beyond the depths shown and such over -excavation shall be to the depths ordered the Project Manager. Ba ckfill for over excavation backfill shall be Class 2 Permeable materials. For wet trenches, Contractor shall install a filter fabric on top and below the permeable materials.
3.11 PIPE LAYING
A. Lay pipes to lines and grades indicated on Drawings, with uniform bearing under the full length of the barrel of the pipe. Project Manager reserves right to make changes in lines, grades, and depths of utilities when changes are required for Project conditions.
B. Pipe sections shall be laid and joined in such a manner that the offset of the inside of the pipe at any joint will be held to a minimum at the invert. The maximum offset at the invert of pipe shall be 1 percent of the inside diameter of the pipe or 3/8 inch, whichever is smaller.
C. After the joints have been made, the pipe shall not be disturbed in any manner.
D. At the close of work each day, or whenever the work ceases for any reason, the end of the pipe shall be securely closed unless otherwise permitted by the Project Manager.
E. All pipe shall be installed in accordance with the manufacture r's recommendations.
F. The interior of the pipe shall be clean and free from foreign materials before sections of the pipe are connected. The open ends of the pipe shall be sealed with watertight plugs or other approved means at times when pipe laying is not in progress. Under no conditions shall ground water be allowed to enter the pipe.
G. Dropping or bumping of pipe will not be permitted. Care shall be exercised by the Contractor to prevent damage to the pipe during handling. There shall be no distortion or deflection of the pipe which might induce damage to the pipe, pip e lining, pipe coating or joints.
455
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 17
H. Pipe will be carefully inspected in the field before and after laying. In no event shall rejected pipe be installed. Any pipe failin g to pass inspection after laying shall be subject to rejection. Any corrective work shall be approved by the Project Manager and shall be at no cost to the City.
I. The Contractor shall provide a minimum of twelve (12) inches vertical clearance between the pipe and proposed or existing facilities and improvements or per the Utility owner’s requirements . A minimum of twelve inches (12 inches) vertical clearance between the pipe and sanitary sewers, gas or petroleum lines and telephone cables shall be provided. Clearance for electrical conduits shall be as provided in the applicable General Safety Orders or utility regulations. Sanitary sewer and water lines shall be 10 feet horizontally clear and not in the same trench and in conformance with Water Main Sepa ration Criteria: Chapter 16 - California Waterworks Standards Article 6 - §64572, unless specifically shown or directed by the Project Manager.
J. Every precaution shall be taken against floating the pipe. In case of such floating, the Contractor shall repla ce the pipe to its proper location at his own expense, and replace any damaged pipe which may have resulted.
3.12 PLACING AND SPREADING OF BACKFILL MATERIALS
A. Regardless of compaction method, b ackfill shall be evenly spread in horizontal layers so that when comp acted each layer shall not exceed eight (8) inches in thickness. During spreading, each layer shall be thoroughly mixed as necessary to promote uniformity of material and uniformity of moisture throughout backfill materials. Material placed in excess of ei ght (8) inches in thickness shall be removed and re-compacted with the next lift.
B. Systematically backfill to allow maximum time for natural settlement. Do not backfill over porous, wet, frozen, or spongy subgrade surfaces.
C. Water shall be added before or during spreading until the proper moisture content is achieved where the backfill material moisture content is below the optimum moisture content.
D. Where the backfill material moisture content is too high to permit the specified degree of compaction, the material shall be dried or replaced until the moisture content is satisfactory.
E. Unless otherwise approved by the Project Manage r, a ll trenches within the existing roadway shall be backfilled completely and the roadway made passable to traffic at the end of each day's operation.
F. Backfill, or fill, as the case may be, for cast -in-place structures such as, but not limited to, manholes, transition structures, junction structures, vaults, valve boxes and reinforced concrete conduits shall start at the sub-grade for the structure. 456
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 18
G. Except where the pipe must remain exposed for force main leakage tests and subject to the provisions herein, the Contractor shall proceed as soon as possible with backfilling operations. Care shall be exercised so that the conduit will not be damaged or displaced. If the pipe is supported by concrete bedding placed between the trench wall and the pipe, the reminder of any bedding material shall be placed to 1 foot over the top of the conduit. The backfill above the conc rete bedding shall not be placed nor sheeting pulled until the concrete has attained sufficient strength as required by the Project Manager.
H. Trenches shall not be backfilled until all required pressure tests are performed and until the utilities systems as installed conform to the requirements specified in the several sections covering the installation of the various utilities.
I. Voids left by the removal of sheeting, piles and similar sheeting supports shall be immediately backfilled and compacted into place to assure dense and complete filling of the voids.
J. After the placing of backfill has been started, the Contractor shall proceed as soon as practicable with compaction.
K. Backfill shall be mechanically compacted by means of tamping rollers, sheepsfoot rollers, pneumatic tire rollers, vibrating rollers, or other mechanical tampers. All such equipment shall be of a size and type approved by the Project Manager. Impact -type pavement breakers (stompers) will not be permitted.
Sheepsfoot equipment shall be limited to outside the Pipe Zone.
L. Permission to use specific compaction equipment shall not be construed as guaranteeing or implying that the use of such equipment will produce required results or will not result in damage to adjacent ground, existing improvements, or improvements installed under the contract. The Contractor shall make its own determination in this regard.
M. Material for mechanically compacted, backfill shall be placed in lifts which, prior to compaction, shall not exceed the thickness specified above.
N. Mechanically compacted backfill shall be placed in horizontal layers of thickness compatible to the material being placed and the type of equipment being used.
Each layer shall be evenly spread, moistened (or dried, if necessary), and the n tamped, vibrated or rolled until the specified relative compaction has been attained.
3.13 COMPACTION OF BACKFILL MATERIALS
A. Compaction of backfill materials shall be in accordance with ASTM D1557 for cohesive type soils and in accordance with ASTM D4253 and D4254 for cohesionless, free -draining granular type materials. The following compaction test requirements shall apply:
457
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 19
Location of backfill Relative Compaction
Pipe Zone (including Bedding) 90
Trench Zone 90
Final Zone (paved areas, excluding the Pavement Section) 95 Final Zone (unpaved or landscape areas) 90
Over-excavated areas 90
Around minor structures 90
Beneath minor structures 95
B. Compaction of Pipe Zone including Bedding materi al shall be by hand tamping, hand held mechanical vibrating equipment or other means approved by the Project Manager.
C. Each layer of backfill material shall be mechanically compacted to the specified percentage of maximum density. Equipment that is consist ently capable of achieving the required degree of compaction shall be used and each layer shall be compacted over its entire area while the material is at the required moisture content range. Flooding, ponding, or jetting shall not be used.
D. Use hand operated power compaction equipment where use of heavier equipment is impractical or restricted due to weight limitations.
E. Backfill within 3 feet of structures or walls shall be compacted with hand operated equipment. Do not use equipment weighing more tha n 10,000 pounds closer to walls than a horizontal distance equal to the depth of the fill at that time.
3.14 TEMPORARY RESURFACING
A. Unless permanent pavement is placed immediately, temporary bituminous re - surfacing 2 inches thick shall be placed and maintained in streets and parking lot areas and at locations determined by the Project Manager wherever excavation is made through pavement, sidewalk or driveways. Temporary asphalt shall be placed flush with the adjacent pavement grade.
B. Hot Mix Asphalt shall be use d for temporary resurfacing when permanent surfacing is not to be placed within seven (7) days.
C. In sidewalk areas the temporary bituminous re-surfacing shall be at least 1-inch- thick, in all other areas it shall be at least 2 inches thick. At major intersections and other critical locations, a greater thickness may be ordered. Temporary resurfacing shall be placed as soon as the condition of the backfill is suitable to receive it and shall remain in place until the condition of the backfill is suitable for permanent resurfacing. Surfacing shall be maintained in a smooth and level condition. The temporary paving shall conform to the requirements of Section 39 458
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 20
of the State Standard Specifications and unless specified differently in the Technical Specifications, may use any of the mixes allowed in Section 39 for such temporary surfacing of trenches.
D. The re-surfacing shall be placed, rolled, maintained, removed and disposed of by the Contractor.
3.15 PAVEMENT SECTION REPLACEMENT
A. Unless otherwise specified on the plans or in the Technical Specifications, all existing pavement surface improvements damaged or removed as a result of the Contractor's operations shall be reconstructed by the Contractor per City of Pittsburg Standard Detail R -5, to same dimensions, except for pavement thickness, and with the same type materials used in the original work. Trench resurfacing shall match the existing pavement thickness , but no less than 3 inches.
B. The type and thickness of the replacement pavement, base, cement treated base, and sub-base for trenches in public streets and highways shall be as shown on the plans or designated by the Project Manager.
C. Unless otherwise specified, the following requirements shall govern:
Sub-base: Existing sub -base shall be replaced with Class 2 Aggregate Base.
The thickness of sub -base replacement shall be designated by the Project Manager, and that portion of trench backfill lying within such designated limits shall be compacted in accordance with this Section and shall not be less than ninety-five (95) percent as determined by California Test Method No. 216.
D. Surfacing of trenches in new s treet sections shall be as required to match the Pavement Section as shown on the project plans and specifications.
3.16 TOLERANCES
A. Section 01 45 00 - Quality Control: Tolerances.
B. Top Surface of Backfilling under paved areas : Plus or minus 1/2 inch from required elevations.
C. Top Surface of General Backfilling: Plus or minus 1/2 inch from required elevations.
3.17 FIELD QUALITY CONTROL
A. Section 01 45 00 - Quality Control: Field inspecting, testing, adjusting, and balancing.
459
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 21
B. Perform laboratory material tests in accordance with ASTM D1557, ASTM D698, and AASHTO T180.
C. Perform in place compaction tests in accordance with the following:
1. Density Tests: ASTM D1556, ASTM D2167, or ASTM D2922.
2. Moisture Tests: ASTM D3017.
D. When tests indicate Work does no t meet specified requirements, remove Work, replace, compact, and retest at the Contractor’s expense.
3.18 PROTECTION OF FINISHED WORK
A. Section 01 77 00 - Closeout Requirements : Contractor shall protec t all the finished work and any damage to the finished work shall be replaced at the Contractor’s expense.
3.19 TEMPORARY STEEL PLATE BRIDGING
A. When backfilling operations of an excavation in the roadway including bike lanes, sidewalks and parking strip, whether transverse or longitudinal, cannot be properly completed within a work day, steel plate bridging with a non-skid surface and shoring shall be required to preserve unobstructed traffic and pedestrian flow. In such cases, the following conditions shall apply:
1. Steel plates used for bridging must extend a minimum of 12 -inches beyond the edges of the trench.
2. Steel plate bridging shall be installed to operate with minimum noise or movement.
3. The tre nch shall be adequately shored to support the bridg ing and traffic loads.
4. Temporary paving with cold asphalt concrete shall be used to feather the edges of the plates, if plate installation by Method (2) described below, is used.
5. Bridging shall be secured against displacement by using adjustable cleats, shims, or other devices.
B. The Contractor is responsible for maintenance of the steel plates, shoring, asphalt concrete ramps, and ensuring that they meet minimum specifications.
C. All work done by the City crews for lack of maintenance of the temporary steel plates as specified above by the Contractor shall be back charged to the Contractor.
D. Steel plate bridging shall not exceed four (4) consecutive working days in any given week and should not be left through the weekend, unless approved by the Enigneer.
460
City of Pittsburg, California December 2022
UTILITY TRENCHING 31 23 16 - 22
E. Steel plate bridging and shoring shall be installed using either Method (1) or (2):
1. Method 1 For speeds of 45 MPH or greater:
The pavement shall be cold planed to a depth equal to the thickness of the plate and to a width and length equal to the dimensions of the plate. Approach plate(s) and ending plate (if longitudinal placement) shall be attached to the roadway by a minimum of two (2) dowels pre -drilled into the corners of the plate and drilled 2-inches into the pavement. Subsequent plates are to be butted and tack welded to each other.
2. Method 2 For speeds less than 45 MPH:
Approach plate(s) and ending plate (if longitudinal pla cement) shall be attached to the roadway by a minimum of two (2) dowels pre-drilled into the corners of the plate and drilled 2-in into the pavement. Subsequent plates are to be butted and tack welded to each other. Fine graded asphalt concrete shall be compacted to form ramps, maximum slope 8.5 percent with a minimum 12-inch taper to cover all edges of the steel plates. When steel plates are removed, the dowel holes in the pavement shall be backfilled with either graded fines of asphalt concrete mix, concrete slurry, epoxy or an equivalent that is satisfactory to the Project Manager.
END OF SECTION 31 23 16
461
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 1
SECTION 32 11 23 - AGGREGATE BASE COURSES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Class 2 Aggregate Base course.
B. Related Sections:
1. Section 31 23 16 - Utility Trenching: Compacted fill under base course.
2. Section 32 12 16 - Asphalt Paving: Binder and finish asphalt courses.
3. Section 32 13 13 - Concrete Surface Improvements: Finish concrete surface course.
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. Aggregate Base Course:
1. Basis of Measurement: By the cubic yard as specified in the bid form .
Quantities of aggregates will be calculated on the basis of dimensions shown on the plans . No allowance will be made for aggregate rejected or placed outside said dimensions unless otherwise order by the Project Manager.
2. Aggregate Base used under concrete work such as curb and gutter, valley gutter, sidewalk, driveways, curb ramps, median curbs, median nose surfacing, bus turnouts, retaining curbs, and in utility trenches shall not be measured unless specified otherwise in the Contract.
3. Basis of Payment: Inc ludes full compensation for furnishing all labor, materials, tools, equipment and incidentals, in aggregate base supplying fill material, stockpiling, scarifying subgrad e surface, placing where required, watering, dust palliative, leveling , compacting and certifying the top of aggregate base design grades.
4. Aggregate Base used under concrete work such as curb and gutter, valley gutter, sidewalk, retaining curbs, etc. shall considered incidental to the item most closely related to and no separate compensation will be allowed therefor. Aggregate base used in utility trenches shall be considered incidental to the cost per linear foot paid for the utility pipes as shown on the bid form and no separate compensation will be allowed therefor. 462
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 2
1.3 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO M288 - Standard Specification for Ge otextile Specification for Highway Applications.
B. Caltrans Standard Specifications:
1. Section 26 Aggregate Base.
C. CalRecycle
1. http://www.calrecycle.ca.gov/ConDemo/Aggregate/
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data:
1. Submit data for geotextile fabric and herbicide.
C. Samples: Submit, in air-tight containers, 5 lbs sample of each type of aggregate fill to testing laboratory or as required by the City.
D. Submit aggregate base gradation, R -value requirements, and sand equivalent requirements as specified in this sections.
E. Aggregate samples must not be treated with lime, cement, or chemicals before testing for durability index.
F. Aggregate from untr eated reclaimed processed asphalt concrete, Portland cement concrete, lean concrete base or cement -treated base is not considered treated.
G. If the aggregate gradation test results, sand equivalent test results, or both do not comply with the Contract compliance requirements, remove the aggregate base or request a payment deduction. If the payment deduction request is authorized, $2.00/cubic yard is deducted.
H. Materials Source: Submit name of aggregate materials suppliers.
I. Manufacturer's Certificate: Certify products meet or exceed specified requirements.
J. Field survey and certify the top of aggregate base design grades as specified in Section 01 71 23 - Construction Surveying.
463
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 3
K. Supplier shall submi t certification data that aggregate base meets the requirements per Caltrans Testing Methods.
1.5 SUSTAINABLE DESIGN SUBMITTALS
A. Manufacturer's Certificate: Certify products meet or exceed specified sustainable design requirements.
1. Materials Resources Certificates:
a. Certify source and origin for salvaged and reused products. b. Certify recycled material content for recycled content products. c. Certify source for regional materials and distance from jobsite.
1.6 QUALITY ASSURANCE
A. Furnish each aggregate material from single source throughout the Work.
B. Perform Work according to City Standards.
PART 2 - PRODUCTS
2.1 SUSTAINABILITY CHARACTERISTICS
A. Materials and Resources Characteristics:
1. Recycled Content Materials: Furnish materials with maxi mum available recycled content.
2. Regional Materials: Furnish materials extracted, processed, and manufactured within 500 miles of jobsite.
2.2 AGGREGATE MATERIALS
A. Aggregate must be clean and consist of any combination of the following:
1. Broken Stone
2. Crushed Gravel
3. Natural rough-surfaced gravel
4. Sand
5. Processed reclaimed asphalt concrete, Portland cement concrete, lean concrete base, or cement-treated base.
B. Quality: Aggregate base furnished for the base material shall be free from vegetable matter and other deleterious substances, and shall be of such nature 464
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 4
that it can be compacted readily under watering and rolling to form a firm stable base.
C. Maximum aggregate size shall be 3/4-inch maximum aggregate gradation unless specified otherwise.
D. Class 2 Aggregate Base: ASTM D2940; graded type. Conform to Section 26 of the Caltrans Standard Specifications. Aggregate gradation for 3/4-inch maximum aggregate base must be within the percentage passing limits for the sieve siz es shown in the following table:
Aggregate Gradation
Sieve Size Percentage Passing
Operating Range Contract compliance
2” - -
1-1/2” - -
1” 100 100
3/4" 90-100 87-100
No. 4 35-60 30-65
No. 30 10-30 5-35
No. 200 2-9 0-12
E. The aggregate quality characteristic must comply with the requirements shown in the following table:
Aggregate Quality Characteristics
Quality Characteristics Requirement
Operating Range Contract compliance
Resistance (R-value, min.) - 78
Sand Equivalent (min.) 25 22
Durability Index (min.) - 35
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify compacted subgrade is dry and ready to support paving and imposed loads.
1. Proof roll subgrade with minimum two perpendicular passes to identify soft spots unless specified otherwise in the Project Geotechnical Report.
2. Remove soft subgrade and replace with compacted fill unless specified otherwise in the Project Geotechnical Report or as ordered by the Project Manager.
465
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 5
B. Immediately before spreading aggregate base, the subgrade must comply with the specified compaction and elevation tolerance for the material involved and be free from loose or extraneous materials.
C. Contractor may use aggregate base to fill areas of th e subgrade that are lower than the grade as shown on the Drawings.
3.2 PREPARATION
A. Correct irregularities in subgrade gradient and elevation by scarifying, reshaping, and re-compacting.
B. Do not place fill on soft, muddy, or frozen surfaces.
3.3 AGGREGATE PLACEMENT
A. Deliver uniform thickness of aggregate base to the roadbed. Deposit aggregate base in layers or windrows.
B. Spread and shape the aggregate base to such thickness that after watering and compacting, the completed aggregate base is within the tolerances speci fied below in Section 3.5.
C. Avoid material segregation. Segregated materials shall be re-mixed until uniform.
D. Aggregate base must be free from pockets of coarse or fine material.
E. If the aggregate base thickness shown is 0.50 foot or less, spread and compact the aggregate base in one layer. If the thickness shown is more than 0.50 foot, spread and compact the aggregate base in at least 2 approximately equal layers in thickness. The compacted thickness of any one later must not exceed 0.50 foot.
F. At locations inaccessible to spreading equipment, spread and compact aggregate base by any means that will attain the specified requirements ; by hand compaction if needed.
G. Apply water to moisture condition the aggregate base as needed for optimum moisture content for compaction.
H. Compact each aggregate base layer to at least 95 percent relative compaction.
I. If bi-axial is installed as shown on the Drawings or as directed by the City’s Project Manager, compact aggregate base with either (1) a smooth-wheeled roller or (2) a rubber-tired roller. Do not use vibratory devices during compaction.
J. Level and contour surfaces to elevations, profiles, and gradients indicated. 466
City of Pittsburg, California December 2022
AGGREGATE BASE COURSES 32 11 23 - 6
K. Maintain optimum moisture content of fill materials to attain specified compaction density.
L. Correct areas of aggregate base that do not comply with the described thickness.
3.4 TOLERANCES
A. Section 01 45 00 - Quality Control: Tolerances.
B. Maximum Variation from Flat Surface: 1/4 inch measured with 10-foot straight edge.
C. Maximum Variation from Thickness: 1/4-inch.
D. Maximum Variation from Elevation: 1/4-inch.
3.5 FIELD QUALITY CONTROL
A. Section 01 77 00 - Closeout Requirements: Field inspecting, testing, adjusting, and balancing.
B. When tests indicate Work does not meet specified requirements, correct areas of aggregate base that do not comply with the specified requirements and retest, or request a payment deduction. If a payment deduction is authorized, the deduction is calculated by multiplying:
1. Deficient thickness less allowable tolerance
2. Planned width
3. Longitudinal distance of the deficient thickness
4. $17.00/cubic yard of the item price adjust ed for cubic yards, whichever is higher
END OF SECTION 32 11 23
467
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 1
SECTION 32 12 16 - ASPHALT PAVING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Asphalt materials.
2. Aggregate materials.
3. Type A HMA Asphalt paving
4. Tack coat
5. Asphalt Rubber Binder Seal Coat
B. Related Requirement:
1. Section 32 11 23 - Aggregate Base Courses : Compacted subbase f or paving.
2. Section 33 05 13 - Manholes and Structures
1.2 PRICE AND PAYMENT PROCEDURES
A. Section 01 29 00 - Payment Procedures: Contract Sum/Price B. Asphalt Paving or HMA:
1. Basis of Measurement: By ton and will be based on certified weight-meters certificates showing gross, net weight and the type and grading of the mix for each load unless specified otherwise on the Bid Form.
2. Basis of Payment: Includes priming surfaces, tack coating surfaces, fog seal, furnishing, placing, compacting asphalt pavement and temporary HMA tapers.
C. Asphalt Dikes:
1. Basis of Measurement: By lineal foot.
2. Basis of Payment: Includes priming surfaces, tack coating surfaces, furnishing, placing, compacting.
1.3 REFERENCE STANDARDS
A. American Association of State Highway and Transportation Officials:
1. AASHTO M17 - Standard Specification for Mineral Filler for Bituminous Paving Mixtures.
468
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 2
2. AASHTO M29 - Standard Specification for Fine Aggregate for Bituminous Paving Mixtures.
3. AASHTO M140 - Standard Specification for Emulsified Asphalt.
4. AASHTO M208 - Standard Specification for Cationic Emulsified Asphalt.
5. AASHTO M288 - Standard Specification for Geotextile Specification for Highway Applications.
6. AASHTO M320 - Standard Specification for Perfor mance-Graded Asphalt Binder.
7. AASHTO M324 - Standard Specification for Joint and Crack Sealant s, Hot Applied, for Concrete and Asphalt Pavements.
8. AASHTO MP1a - Standard Specification for Performance -Graded Asphalt Binder.
9. AASHTO T283-14 – Standard Method of Test for Resistance of Compacted Asphalt Mixtures to Moisture-Induced Damage.
10. AASHTO T324 (Modified) -Hamburg Wheel-Track Testing of Compacted Hot Mix Asphalt (HMA).
B. Asphalt Institute:
1. AI MS-2 - Mix Design Methods for Asphalt Concrete and Other H ot- Mix Types.
2. AI MS-19 - Basic Asphalt Emulsion Manual.
3. AI SP-2 - Superpave Mix Design.
C. State Standard Specification:
1. Section 39 Asphalt Concrete.
2. Section 92 Asphalt Binder.
3. Section 94 Asphaltic Emulsions
4. Section 96 Geosynthetics
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Job Mix Formula (JMF): Except for the Hot Mix Asphalt (HMA) to be used in miscellaneous areas (median island areas not including inside shoulders, island areas, sidewalk, gutters, ditches, over side drains and aprons at end of drainage structures) and dikes, submit the proposed JMF for Type A HMA.
C. The JMF must be submitted on the Contractor Job Mix Formula Proposal form along with:
1. Mix design documentation on Contractor’s Hot Mix Asphalt Design data form dated with 12 months of submittal.
2. Safety Data Sheets (SDS) for the following:
a. Asphalt Binder
b. Supplemental fine aggregate except fines from dust collectors c. Antistrip additives.
469
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 3
D. The Contractor’s Hot Mix Asphalt Design Data form must show documentation on aggregate quality.
E. Submit QC test results for R eclaimed Asphalt Pavement (R AP) gradation with the combined aggregate gradation within 2 business days of taking RAP samples during Type A HMA production.
F. Contractor shall submit a new JMF if there are changes to any of the following:
1. Target asphalt binder percentage greater than ±0.2 percent.
2. Asphalt binder supplier
3. Combined aggregate gradation
4. Aggregate sources
5. Liquid antistrip producer or dosage
6. Average binder content in a new processed RAP stockpile by more than ±2.0 percent from the average RAP binder content reported on Contractor Hot Mix Asphalt Design Data form.
7. Average maximum specific gravity in a new processed RAP stockpile by more than ±0.060 percent from the average maximum specific gravity value reported on Contractor’s Hot Mix Asphalt Design Data form.
8. Any material in the JMF.
G. Submit a current asphalt concrete mix design from two separate sources (primary source and backup source) for asphalt concrete proposed to be used.
H. Contractor shall provide delivery tickets to the City at the time of delivery of each load of product, including asphalt concrete, tack coat, sealant, and paving reinforcement fabric. Each delivery ticket shall include or be accompanied by appropriate batch information produced by the batching plant or factory of origin and information stating the mix or model number, total yield in tons, gallons, or square feet, and time, date, and location of delivery.
I. Any asphalt concrete rejected by the Project Manager shall be deducted from the total quantity of asphalt concrete tonnage.
J. Reference Plan: Contractor shall have a walk through with the Project Manager for all installed underground boxes and/or iron elements , 10 days prior to any pavement repair. Contractor shall submit a reference plan (RP) to the Project Manager's review for utility facilities adjustment 3 working days prior to lowering any utility facilities.
K. Contractor shall submit a paving plan for longitudinal joints.
1.5 QUALITY CONTROL PLAN
A. The Contractor shall submit a Quality Control (QC) plan for HMA.
B. The QC plan shall describe the organization and procedures for:
470
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 4
1. Controlling HMA quality characteristics
2. Taking samples, including sampling locations.
3. Establishing, implementing, and maintaining QC
4. Determining when corrective actions are needed.
5. Implementing corrective actions.
6. Using methods and materials for backfilling core locations.
C. The QC plan must address the elements affecting HMA Quality, including
1. Aggregates
2. Asphalt binder
3. Additives
4. Productions
5. Paving
D. For CIP projects, the Contractor shall permit the City’s certified testing laboratory to take samples of the aggregate and asphalt emulsion used in the project at the City’s discretion. Gradation and sand equivalent tests may be run on the aggregate and residual asphalt tests on the emulsion. City will compare the test results with this Section and notify the Contractor if any test fails to meet specifications.
E. The Contractor shall furnish all tools and equipment and employ sufficient trained personnel to oper ate all equipment and perform all handwork efficiently and skillfully.
1.6 AGGREGATES TESTING:
A. Contractor shall t est the quality of aggregates under the test methods and frequencies shown in the following table and provide results to the City:
Aggregate Testing Frequencies
Quality Characteristic Test Method Minimum Testing
Frequency
Gradationa AASHTO T 27
1 per 750 tons and
any remaining part
Sand Equivalentb,c AASHTO T 176
Moisture Contentd AASHTO T 255
Crushed particles AASHTO T335 1 per 10,000 tons
or 2 per project
whichever is
greater
Los Angeles Rattler AASHTO T96
Flat and Elongated particles AASHTO D4791
Fine Aggregate angularity AASHTO T 304 Method
A
aIf RAP is used, test the combined aggregate gradation under California Test 384. 471
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 5
bReported Value must be average of 3 tests from a single sample cUse of a sand reading indicator is required as shown in AASHTO T 176, Figure 1.
Sections 4.7, “Manual Shaker,” 7.1.2, “Alternate Method No.2,” and 8.4.3, “Hand Method”, do not apply. Prepare the stock solution as specified in Section 4.8.1, “Stock solution with formaldehyde”, except omit the addition of formaldehyde. dTest at continuous mixing plants only. If RAP is used, test the RAP moisture content at continuous mixing plant and batch mixing plant.
1.7 AMBIENT CONDITIONS
A. Section 01 50 00 - Temporary Facilities and Controls: Ambient conditions control facilities for product storage and installation.
B. Do not place HMA on wet pavement or frozen surface.
C. Maximum lift thickness for asphalt paving shall be 4-inches unless shown otherwise on the Drawings.
D. Spread Type A HMA at the ambient air and surface temperatures shown in the following table unless shown otherwise on the Drawings:
Lift
Thickness
(Feet)
Ambient air (°F) Surface (°F)
Unmodified
asphalt
binder
Modified
asphalt
binder
Unmodified
asphalt
binder
Modified
asphalt
binder
< 0.15 55 50 60 55
≥ 0.15 45 45 50 50
PART 2 - PRODUCTS
2.1 ASPHALT PAVING
A. Asphalt Concrete shall conform to Section 39 , “Asphalt Concrete”, of the State Standard Specifications and the City Standard Specifications.
B. Asphalt Concrete for surfacing shall be Hot Mix Asphalt (HMA) Type A.
C. Asphalt Materials:
1. Asphalt Binder: Asphalt Binder must comply with Section 92 , “ Asphalt Binders” of the State Standard Specifications.
472
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 6
a. For a leveling course, the grade of the asphalt binder for the Hot mix asphalt (HMA) must be PG 64-10 or PG 64-16.
b. For Miscellaneous areas, and asphalt dikes the grade of the asphalt binder for the Hot mix asphalt (HMA) must be PG 70 -10. Minimum asphalt binder content must be 6.40 percent for 3/8” maximum size aggregate.
2. Tack Coat: Diluted cationic emulsified asphalt per Section 94 , “Asphaltic Emulsions”, of the State Standard Specification. Asphaltic emulsion shall be Grade CSS1h setting type.
3. Reclaimed Asphalt Pavement (RAP): Processed material obtained by milling or full depth removal of existing asphalt paving.
D. Reclaimed Asphalt Pavement (RAP) aggregate may be substituted fo r a part of virgin aggregate in a quantity not to exceed fifteen percent (15%) by weight of the aggregate blend.
1. RAP shall conform to Section 39 -2.02A(3)(c), “ Reclaimed Asphalt Pavement”, of the State Standard Specifications.
2. During Type A HMA production, sample RAP twice daily and perform QC testing for:
a. Aggregate gradation at least once a day under California Test 384. b. Moisture content at least twice a day.
3. If RAP is used, RAP quality requirements must be as shown in the following table.
Reclaimed Asphalt Pavement Quality
Quality Characteristic Test method Requirement
Binder Content (% within the average
value reported)
AASHTO T 164 ± 2.00
Specific Gravity (within the average
value reported)
AASHTO T 209 ± 0.06
E. Aggregate Materials:
1. Coarse Aggregate: ASTM D692; Aggregate retained on a no. 4 sieve. crushed stone or gravel.
2. Fine Aggregate: ASTM D1073, AASHTO M29; Aggregate passing a no. 4 sieve. Natural sand or sand manufactured from stone or gravel.
3. Mineral Filler: finely ground mineral particles, free of foreign matter consisting of rock dust, slag dust, hydrated lime, hydraulic cement, or any combination of these and complying with AASHTO M17. Mineral fillers shall only be used if needed to improve the workability of the mix or gradation of the aggregate.
4. The aggregate gradation for Type A HMA must comply with the requirements shown in the following table unless specified otherwise on the Drawings:
473
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 7
Aggregate Gradation Requirements
Type A HMA pavement thickness shown Gradation
Greater than 0.10 to less than 0.20 foot 1/2 inch
0.20 to less than 0.25 foot 3/4 inch
0.25 foot or greater 3/4 inch
5. The top 0.20-foot layer of asphalt pavement on the roadway shall have an aggregate gradation of 1/2" inch maximum.
6. Aggregate gradation must be within the T arget Value (T V) limits for the specified sieve size shown in the following tables:
Aggregate Gradation for Type A HMA (percentage passing) 1 inch
Sieve Size Target value limit Allowable tolerance
1” 100 -
3/4" 88-93 TV ± 5
1/2" 72-85 TV ± 6
3/8” 55-70 TV ± 6
No. 4 35-52 TV ± 7
No. 8 22-40 TV ± 5
No. 30 8-24 TV ± 4
No. 50 5-18 TV ± 4
No. 200 3-7 TV ± 2.0
3/4 inch
Sieve Size Target value limit Allowable tolerance
1” 100 -
3/4" 90-98 TV ± 5
1/2" 70-90 TV ± 6
No. 4 42-58 TV ± 5
No. 8 29-43 TV ± 5
No. 30 10-23 TV ± 4
No. 200 2-7 TV ± 2.0
1/2 inch
Sieve Size Target value limit Allowable tolerance
3/4" 100 -
1/2" 95-98 TV ± 5
3/8” 72-95 TV ± 5
No. 4 52-69 TV ± 5
No. 8 35-55 TV ± 5
No. 30 15-30 TV ± 4
No. 200 2-8 TV ± 2.0
3/8 inch
474
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 8
Sieve Size Target value limit Allowable tolerance
3/4" 100 -
1/2" 95-98 TV ± 5
3/8” 72-95 TV ± 5
No. 4 52-69 TV ± 5
No. 8 35-55 TV ± 5
No. 30 15-30 TV ± 4
No. 200 2-8 TV ± 2.0
7. Before the additional of asphalt binder, the aggregates must comply with the quality requirements shown in the following table:
Quality characteristics Test Method Requirement
Aggregate Gradationa AASHTO T27 JMF ± Tolerance
Percent of crushed particles
Coarse aggregate (min, %)
One-fractured face
Two-fractured face
Fine aggregate (min, %)
Passing No. 4 sieve and
retained on No. 8 sieve.)
One-fractured face
AASHTO T 335
95 90
70 Los Angeles Rattler (max, %)
Loss at 100 Rev.
Loss at 500 Rev.
AASHTO T96
12 40
Sand equivalent (min.) b, c AASHTO T176 47
Flat and elongated particles
(max, % by weight at 5:1)
ASTM D4791 10
Fine aggregate angularity (min,
%)d
AASHTO T304,
Method A
45 aThe Project Manager determines combined aggregate gradations containing RAP under California Test 384.
bReported value must be the average of 3 tests from a single sample. cUse of a sand reading indicator is required as shown in AASHTO T176, Figure 1. Section 4.7, “Manual Shaker”, 7.1.2, “Alternate Method No.2.” and 8.4.3, “Hand Method,” do not apply. Prepare the stock solution as specified in section 4.8.1, “Stock solution with formaldehyde,” except omit the addition of formaldehyde.
dThe Project Manager waives this specification if HMA contains 10 percent or less of nonmanufactured sand by weight of total aggregate.
Manufactured sand is fine aggregate produced by crushing rock or gravel.
475
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 9
2.2 TYPE A HMA PRODUCTION
A. Contractor shall t est the quality characteristics of Type A HMA u nder the test methods and frequencies shown in the following table and provide results to the City:
Type A HMA Production Testing Frequencies
Quality Characteristic Test method Minimum testing
frequency
Asphalt Binder AASHT T 308, Method
A
1 per 750 tons and any
remaining part
HMA Moisture Content AASHTO T 329
1 per 2,500 tons but not
less than 1 per paving
day
Air Void Content AASHTO T 269
1 per 4,000 tons or 2
every 5 paving days
whichever is greater
Voids in mineral
aggregate
SP-2 Asphalt Mixture
Volumetrics 1 per 10,000 tons or 2
per project whichever is
greater Dust proportion SP-2 Asphalt Mixture
Volumetrics
Density of core California Test 375 2 per paving day
Nuclear gauge density California Test 375
3 per 250 tons or 3 per
paving day, whichever
is greater
Hamburg wheel track AASHTO T 324
(Modified)
1 per 10,000 tons or 1
per project whichever is
greater. Moisture susceptibility AASHTO T 283
2.3 TYPE A HMA ACCEPTANCE
A. In place T ype A HMA quality requirements shall be as shown in the following table:
Type A HMA Acceptance In Place
Quality Characteristic Test method Requirement
Asphalt Binder content (%) AASHTO T 308
Method A JMF – 0.3, +0.50
HMA moisture content (max, %) AASHTO T 329 1.00
Voids in mineral aggregate on
laboratory-produced HMA (min,
%)d
Gradation:
No. 4
3/8-inch
1/2-inch
SP-2 Asphaltic
Mixture Volumetrics
16.5-19.5
15.5-18.5
14.5-17.5
476
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 10
3/4-inch
1-inch
with NMAS = 1-inch
with NMAS = 3/4-inch
13.5-16.5
13.5-16.5
14.5-17.5
Voids in mineral aggregate on
plant-produced HMA (min, %)a
Gradation:
No. 4
3/8-inch
1/2-inch
3/4-inch
1-inch
with NMAS = 1-inch
with NMAS = 3/4-inch
SP-2 Asphaltic
Mixture Volumetricsc
15.5-18.5
14.5-17.5
13.5-16.5
12.5-15.5
12.5-15.5
13.5-16.5
Dust proportion SP-2 Asphaltic
Mixture Volumetrics 0.6-1.3g
Density of core (% of max
theoretical density)e,f California Test 375 91.0-97.0
Hamburg wheel track (min
number of passes at 0.5-inch rut
depth)
Binder grade:
PG 58
PG 64
PG 70
PG 76 or higher
AASHTO T 324
(Modified)
10,000
15,000
20,000
25,000
Hamburg wheel track (min
number of passes at inflection
point)
Binder grade:
PG 58
PG 64
PG 70
PG 76 or higher
AASHTO T 324
(Modified)
10,000
10,000
12,500
15,000
Moisture susceptibility (min, psi,
dry strength) AASHTO T 283 100
Moisture susceptibility (min, psi,
wet strength) AASHTO T 283 70
aPrepare 3 briquettes. Report the average of 3 tests,
bFor CIP projects, t he City’s Testing Laboratory determines the bulk specific gravity of each lab-compacted briquette under AASHTO T 275, Method A, and theoretical maximum specific gravity under AASHTO T 209, Method A. cDetermine the bulk specific gravity under AASHTO T 275, Method A. dFor CIP projects, the City’s Testing Laboratory determines the laboratory - prepared Type A HMA value for only mix design verification. 477
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 11
eFor CIP projects, the City’s Testing Laboratory determines percent of theoretical maximum density under
California Test 375 except for CIP Projects, City’s Testing Laboratory uses:
1. AASHTO T 275 to determine in -place density of each density core.
2. AASHTO T 209, method A to determine theoretical maximum density instead of calculating test maximum density.
fFor CIP projects, the City’s Testing Laboratory determines theoretical maximum density under AASHTO T 209, Method A, at the frequency specified in California Test 375, part 5, section D.
gFor lime-treated aggregates, the dust proportion requirement is 0.6-1.5
2.4 SOURCE QUALITY CONTROL
A. Section 01 45 00 - Quality Control: Testing, inspection and analysis requirements.
B. Test samples in accordance with AI MS-2.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 70 00 - Execution: Requirements for installation examination.
B. Verify utilities indicated under paving are installed with excavations and trenches backfilled and compacted.
C. Verify compacted aggregate base is dry and ready to support paving and imposed loads as specified in the project Geotechnical Report or as directed by the Project Manager.
1. Proof roll subbase with minimum two perpendicular passes to identify soft spots.
2. Remove soft subbase and replace with compacted fill.
D. Verify with a licensed land surveyor that the gradients and elevations of base are correct.
E. Verify drainage grates and frames, and manhole frames are installed in correct position and elevation.
3.2 CONSTRUCTION
A. Contractor may deposit HMA in a windrow and load it in the paver if:
1. Paver is equipped with a hopper that automatically feeds the screed. 478
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 12
2. Loading equipment can pick up the windrowed material and deposit it in the paver hopper without contaminating or damaging HMA and subgrade base material.
3. Activities for depositing, pickup loading and paving are continuous.
4. HMA temperature in the windrow does not fall below 260-degree F.
B. HMA placed in a windrow on the roadway surface must not extend more than 250 feet in front of the loading equipment or material transfer vehicle.
C. HMA handled, spread, or windrowed must no t stain the finished surfac e of any improvement, including pavement.
D. Do not use petroleum products such as kerosene or diesel fuel to release HMA from trucks, spreaders, or compactors.
E. HMA must be free of:
1. Segregation
2. Coarse or fine aggregate pockets
3. Hardened lumps
F. Complete finish rolling activities before the pavement surface temperature is
1. Below 150 degrees F for HMA with unmodified binder
2. Below 140 degrees F for HMA with modified binder
3.3 SPREADING AND COMPACTING EQUIPMENT
A. Paving equipment for spreading must be:
1. Self-propelled
2. Mechanical
3. Equipped with a screed or strike -off assembly that can distribute HMA the full width of a traffic lane.
4. Equipped with a full-width compacting device.
5. Equipped with automatic screed controls and sensing devices that control the thickness, longitudinal grade, and transverse screed slope.
B. Install and maintain grade and slope reference.
C. The screed must be heated and produce a uniform HMA surface texture without tearing, shoving, or gouging.
D. The paver must not leave marks such as ridges and indentations unless you can eliminate them by rolling.
E. Rollers must be equipped with a system that prevents HMA from sticking to the wheels. You may use a parting agent that does not damage the HMA or impede the bonding of layers.
479
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 13
F. In areas inaccessible to spreading and compacting equipment:
1. Spread the HMA by any means to obtain the specified lines, grades and cross sections.
2. Use a pneumatic tamper, plate compactor, or equivalent to achieve thorough compaction.
3.4 MATERIAL TRANSFER VEHICLE:
A. The material transfer vehicle must have sufficient capacity to prevent stopping the paver and must be capable of:
1. Either receiving HMA directly from trucks or using a windrow pickup head to load it from a windrow deposited on the roadway surface.
2. Remixing the HMA with augers before transferring into the paver’s receiving hopper or feed system.
3. Transferring HMA directly into the paver’s receiving hopper or feed system.
3.5 METHOD COMPACTION EQUIPMENT:
A. For method compaction, each paver spreading HMA must be followed by 3 rollers:
1. One vibratory roller specified designed to compact HMA. The roller must be capable of at least 2,500 vibrations per minute and must be equipped with amplitude and frequency controls. The roller’s gross static weight must be at least 7.5 tons.
2. One oscillating-type pneumatic-tired roller at least 4 feet wide. Pneumatic tires must be of equal size, diameter, type, and ply. The tires must be inflated to 60 psi minimum and maintained so that the air pressure does not vary more than 5 psi.
3. One steel-tired, 2-axle tandem roller. The roller’s gross static weight must be at least 7.5 tons.
3.6 SURAFCE PREPARATION:
A. Before placing HMA, remove loose paving particles, dirt, and other extraneous material by any means including flushing and sweeping.
B. Prepare subgrade to receive HM A under the sections for the material involved.
Subgrade must be free of loose and extraneous material.
3.7 TACK COAT:
A. Apply tack coat in accordance with Section 39-2.01C(3)(f) of the State Standard Specifications.
480
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 14
B. Apply tack coat:
1. To existing pavement including planed surfaces.
2. Between HMA layers
3. To vertical surfaces of:
a. Curbs
b. Gutters
c. Construction joints.
C. Coat surfaces of manholes and catch basins.
D. Equipment for the application of tack coat must comply with Section 37 -1.03B, “Equipment” of the State Standard Specifications.
E. Before placing HMA, apply tack coat in one (1) application at the minimum residual rate shown in the following table for the condition of the underlying surface:
Tack Coat Application Rates for HMA
HMA Over: Minimum residual rates (gal/sq. yd)
CSS1/CSS1h asphaltic emulsion
New HMA (between layers) 0.02
Concrete Pavement and existing
asphalt concrete surfacing
0.03 Planed pavement 0.05
F. If a stress absorbing membrane interlayer as specified in Section 37-2.05, “Stress Absorbing Membrane Interlayers”, of the State Standard Specification is applied, the tack application rates for new HMA apply.
G. Notify the Project Manager if you dilute asphaltic emulsion with water. The weight ratio of added water to asphaltic emulsion must not exceed 1 to 1.
H. Apply tack coat to vertical surfaces with a residual rate that will thoroughly coat the vertical face without running off.
I. Immediately in advance of placing HMA, apply additional tack coat to damaged areas or where loose or extraneous material is removed.
J. Close areas to traffic receiving tack coat. Do not allow the tracking of tack coat onto pavement surfaces beyond the job site.
K. If an asphalt binder is used for tack coat, the asphalt binder temperature must be from 285 to 350-degree F when applied.
481
City of Pittsburg, California December 2022
ASPHALT PAVING 32 12 16 - 15
3.8 LONGITUDINAL JOINTS
A. Longitudinal joints in the top layer must match lane lines. Alternate the longitudinal joint offsets in the lower layers at least 0.5 foot from each side of the lane line.
B. A vertical longitudinal joint of more than 0.15 foot is not allowed at any time between adjacent open lanes to traffic.
C. For an HMA thickness of 0.15 foot or less, the distance between the ends of t he adjacent surfaced lanes at the end of each day’s work must not be greater than can be completed in the following day of normal paving.
D. For an HMA thickness greater than 0.15 foot, you must place HMA on adjacent travel way lanes or shoulder such that at the end of each work shift the distance between the ends of HMA layers on adjacent lanes is from 5 to 10 feet. Place additional HMA along the transverse edge at each lane’s end and along the exposed longitudinal edges between adjacent lanes. Hand rake and compact the additional HMA to form temporary conforms. Place Kraft paper or other authorized release agent under the conform tapers to facilitate the taper removal when paving activities resume.
E. If placing HMA against the edge of existing pavement, saw cut or grind the pavement straight and vertical the joint to the full depth and remove extraneous material.